APPENDIX I – SWITCHING SEQUENCES MATL PHASE 2 STUDY CONTINGENCY SWITCHING FILES Page 1 of 722 APPENDIX I – SWITCHING SEQUENCES TABLE OF CONTENTS Page 1. Non-Simultaneous Transient & Post Transient – HS . . . . . . . . . . . . . . . . 3 2. Non-Simultaneous Transient & Post Transient – LSP. . . . . . . . . . . . . . . 89 3. PATH – 1: 07HS - IV2_1 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 176 4. PATH – 1: 07HS - IV2_2 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 210 5. PATH – 1: 07HS - IV2_3 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242 6. PATH – 1: 07HS - IV2_4 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 276 7. PATH – 1: Southern Alberta Wind Sensitivity - Transient Analysis: a. Cases 1 - 4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 307 b. Cases 5 - 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 346 8. PATH – 3: a. 07HS - Transient Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . 396 b. 07HS - Post-Transient Analysis . . . . . . . . . . . . . . . . . . . . . . 418 c. 07LSP - Transient Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . 435 d. 07LSP - Post-Transient Analysis Analysis . . . . . . . . . . . . . . 458 9. PATH – 8: a. 07 ??? Pre – Project Switching Sequences . . . . . . . . . . . . . . 479 b. 07 ??? MATL - North-to-South Switching Sequences . . . . 500 c. 07 ??? MATL - South-to-North Switching Sequences . . . . . 521 10. Non-Simultaneous Analysis – 07 HS – Autocon Files . . . . . . . . . . . 542 11. Non-Simultaneous Analysis – 07 LSP – Autocon File . . . . . . . . . . 590 12. Path – 1: 07HS – Autocon File . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .641 13. Path - 1: HS So. Alberta Wind Sensitivity – Autocon File . . . . . . . 680 14. Path - 8: 07 LSP – Pflopro Input Files. . . . . . . . . . . . . . . . . . . . . . . .708 15. Wanetta – Boundary: 07 HS Autocon Files . . . . . . . . . . . . . . . . . . 717 Page 2 of 722 APPENDIX I – SWITCHING SEQUENCES Non-Simultaneous Transient & Post Transient 07 HS: Page 3 of 722 APPENDIX I – SWITCHING SEQUENCES 3_Csp-Bvw_RAS_N2S3.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1b * * Colstrip - Broadview #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "COLSTRP " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "COLSTRP " 500. * * Trip Colstrip - Broadview #1 500 kV line DL 63.0 "COLSTRP " 500. "BROADV&1" 500. "1 " DL 63.0 "BROADVU " 500. "BROADV&1" 500. "1 " * * No Colstrip ATR Action Page 4 of 722 APPENDIX I – SWITCHING SEQUENCES 3_Csp-Bvw_RAS_Pre3.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1a * * Colstrip - Broadview #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "COLSTRP " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "COLSTRP " 500. * * Trip Colstrip - Broadview #1 500 kV line DL 63.0 "COLSTRP " 500. "BROADV&1" 500. "1 " DL 63.0 "BROADVU " 500. "BROADV&1" 500. "1 " * * No Colstrip ATR Action Page 5 of 722 APPENDIX I – SWITCHING SEQUENCES 3_Csp-Bvw_RAS_S2N3.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1c * * Colstrip - Broadview #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "COLSTRP " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "COLSTRP " 500. * * Trip Colstrip - Broadview #1 500 kV line DL 63.0 "COLSTRP " 500. "BROADV&1" 500. "1 " DL 63.0 "BROADVU " 500. "BROADV&1" 500. "1 " * * No Colstrip ATR Action Page 6 of 722 APPENDIX I – SWITCHING SEQUENCES 4_Bvw-Gsn_RAS_N2S.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1b * * Broadview-Townsend-Garrison #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 500 kV line DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DB 63.0 "TOWN1 " 500. DB 63.0 "GAR1EAST" 500. * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * No Colstrip ATR Page 7 of 722 APPENDIX I – SWITCHING SEQUENCES 4_Bvw-Gsn_RAS_Pre.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1a * * Broadview-Townsend-Garrison #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 500 kV line DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * No Colstrip ATR Page 8 of 722 APPENDIX I – SWITCHING SEQUENCES 4_Bvw-Gsn_RAS_S2N.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1c * * Broadview-Townsend-Garrison #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 500 kV line DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * No Colstrip ATR Page 9 of 722 APPENDIX I – SWITCHING SEQUENCES 5_Gsn-Tft_RAS_N2S.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1b * * Garrison-Taft #1 500 kV line with RAS * Note: Series Caps not bypassed during fault * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 500 kV line DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * No Colstrip ATR Page 10 of 722 APPENDIX I – SWITCHING SEQUENCES 5_Gsn-Tft_RAS_Pre.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1a * * Garrison-Taft #1 500 kV line with RAS * Note: Series Caps not bypassed during fault * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 500 kV line DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * No Colstrip ATR Page 11 of 722 APPENDIX I – SWITCHING SEQUENCES 5_Gsn-Tft_RAS_S2N.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1c * * Garrison-Taft #1 500 kV line with RAS * Note: Series Caps not bypassed during fault * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 500 kV line DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * No Colstrip ATR Page 12 of 722 APPENDIX I – SWITCHING SEQUENCES 10_BND-BEL1_BEL-USK_230_RAS.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #1 and Bell-Usk 230 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Bell - USK 230 kV Line DL 64.0 "BELL S&A" 230. "USK " 230. "1 " * Trip Boundary - Bell 230 kV Line DL 64.0 "BELL S1 " 230. "SACHEEN " 230. "1 " DL 64.0 "BOUNDARY" 230. "SACHEEN " 230. "1 " * Page 13 of 722 APPENDIX I – SWITCHING SEQUENCES 11_BND-BEL3230_ADY-BEL1_115_RAS2.s RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #3 and Addy - Bell #1 115 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Boundary - Bell #3 230 kV Line DL 64.0 "BELL S3 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&A" 230. "1 " DL 64.0 "BOUNDARY" 230. "ADDY 2&A" 230. "1 " * Trip Addy - Bell #1 115 kV Line * The conservative option for this contingency is to only trip the 230/115 kV bank * This option results in maximum post contingency loading on the remaining lines * (for north to south flows). DL 64.0 "ADDY 2 " 230. "ADDY " 115. "1 " Page 14 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS2.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 675 MW * Shed unit at 50769 KCL G1 13.8 110 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 110 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 150 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 150 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 100 MW TG 70.0 "SEV G3 " 13.8 "1 " Page 15 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 51044 ALH G1 13.8 75 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * * Switch off 12kV, 12 MVAR shunt capacitor at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch off 12kV, 12 MVAR shunt capacitor at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * Page 16 of 722 APPENDIX I – SWITCHING SEQUENCES * Switch off 12kV, 75 MVAR shunt capacitor at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* Page 17 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * (Required BC's genshedding amount 413 MW, actual shedding 420 MW) * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 150 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 150 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " Page 18 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * * Switch off 12kV, 12 MVAR shunt capacitor at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch off 12kV, 12 MVAR shunt capacitor at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * * Switch off 12kV, 75 MVAR shunt capacitor at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* Page 19 of 722 APPENDIX I – SWITCHING SEQUENCES 16_Tft-Gar_Tft-Bell_RAS_N2S.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Three Phase Fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 720 * * Apply Three Phase Fault at Taft FB 60.0 "TAFT " 500. 0.0 0.0 * * Clear bus fault at Taft 500 kV CFB 63.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 63.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 63.0 "BELL B&1" 500. "BELL BPA" 500. "1 " * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 68.0 "LIBBY " 13.8 "1 " TG 68.0 "LIBBY " 13.8 "2 " TG 68.0 "LIBBY " 13.8 "3 " TG 68.0 "LIBBY " 13.8 "4 " TG 68.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 Page 20 of 722 APPENDIX I – SWITCHING SEQUENCES MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 21 of 722 APPENDIX I – SWITCHING SEQUENCES 16_Tft-Gar_Tft-Bell_RAS_Pre.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1a * * Three Phase Fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 720 * * Apply Three Phase Fault at Taft FB 60.0 "TAFT " 500. 0.0 0.0 * * Clear bus fault at Taft 500 kV CFB 63.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 63.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 63.0 "BELL B&1" 500. "BELL BPA" 500. "1 " * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 68.0 "LIBBY " 13.8 "1 " TG 68.0 "LIBBY " 13.8 "2 " TG 68.0 "LIBBY " 13.8 "3 " TG 68.0 "LIBBY " 13.8 "4 " TG 68.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 Page 22 of 722 APPENDIX I – SWITCHING SEQUENCES MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 23 of 722 APPENDIX I – SWITCHING SEQUENCES 16_Tft-Gar_Tft-Bell_RAS_S2N.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1c * * Three Phase Fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 720 * * Apply Three Phase Fault at Taft FB 60.0 "TAFT " 500. 0.0 0.0 * * Clear bus fault at Taft 500 kV CFB 63.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 63.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 63.0 "BELL B&1" 500. "BELL BPA" 500. "1 " * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 68.0 "LIBBY " 13.8 "1 " TG 68.0 "LIBBY " 13.8 "2 " TG 68.0 "LIBBY " 13.8 "3 " TG 68.0 "LIBBY " 13.8 "4 " TG 68.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 Page 24 of 722 APPENDIX I – SWITCHING SEQUENCES MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 25 of 722 APPENDIX I – SWITCHING SEQUENCES 17_Tft-Gar_Tft-Bell_1P_RAS_N2S2.sw RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Single line-to-ground fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1350 * * Apply Single Line-to-ground Fault at Taft FB 60.0 "TAFT " 500. 0.00249 0.02685 DL 60.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 60.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 60.0 "BELL B&1" 500. "BELL BPA" 500. "1 " RL 60.0 "TAFT " 500. "BELL B&2" 500. "2P" RL 60.0 "BELL B&2" 500. "BELL B&1" 500. "2P" RL 60.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * Clear bus fault at Taft 500 kV CFB 72.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 72.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 72.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 72.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 72.0 "TAFT " 500. "BELL B&2" 500. "2P" DL 72.0 "BELL B&2" 500. "BELL B&1" 500. "2P" DL 72.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * Trip Garrison Reactor MBS 76.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * * ATR trip time for Colstrip 3 from ATR emulation software (10.2 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW TG 77.0 "COLSTP 3" 26.0 "1 " MBL 77.0 "COLSTP 3" 26.0 "1 " "D" MBL 77.0 "COLSTP 3" 26.0 "2 " "D" * Page 26 of 722 APPENDIX I – SWITCHING SEQUENCES * Trip Libby Generation (Units 1-5) TG 78.0 "LIBBY " 13.8 "1 " TG 78.0 "LIBBY " 13.8 "2 " TG 78.0 "LIBBY " 13.8 "3 " TG 78.0 "LIBBY " 13.8 "4 " TG 78.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line MBL 81.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 85.5 "COLSTRP " 230.0 "c3" "R" * * Insert Shunts at Rosebud and Custer 230 MBS 89.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 27 of 722 APPENDIX I – SWITCHING SEQUENCES 17_Tft-Gar_Tft-Bell_1P_RAS_Pre2.sw RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Single line-to-ground fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 580 * * Apply Single Line-to-ground Fault at Taft FB 60.0 "TAFT " 500. 0.00249 0.02685 DL 60.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 60.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 60.0 "BELL B&1" 500. "BELL BPA" 500. "1 " RL 60.0 "TAFT " 500. "BELL B&2" 500. "2P" RL 60.0 "BELL B&2" 500. "BELL B&1" 500. "2P" RL 60.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * Clear bus fault at Taft 500 kV CFB 72.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 72.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 72.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 72.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 72.0 "TAFT " 500. "BELL B&2" 500. "2P" DL 72.0 "BELL B&2" 500. "BELL B&1" 500. "2P" DL 72.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 76.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 78.0 "LIBBY " 13.8 "1 " TG 78.0 "LIBBY " 13.8 "2 " TG 78.0 "LIBBY " 13.8 "3 " TG 78.0 "LIBBY " 13.8 "4 " TG 78.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line Page 28 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 81.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 89.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 29 of 722 APPENDIX I – SWITCHING SEQUENCES 17_Tft-Gar_Tft-Bell_1P_RAS_S2N2.sw RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Single line-to-ground fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 580 * * Apply Single Line-to-ground Fault at Taft FB 60.0 "TAFT " 500. 0.00249 0.02685 DL 60.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 60.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 60.0 "BELL B&1" 500. "BELL BPA" 500. "1 " RL 60.0 "TAFT " 500. "BELL B&2" 500. "2P" RL 60.0 "BELL B&2" 500. "BELL B&1" 500. "2P" RL 60.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * Clear bus fault at Taft 500 kV CFB 72.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 72.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 72.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 72.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 72.0 "TAFT " 500. "BELL B&2" 500. "2P" DL 72.0 "BELL B&2" 500. "BELL B&1" 500. "2P" DL 72.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 76.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 78.0 "LIBBY " 13.8 "1 " TG 78.0 "LIBBY " 13.8 "2 " TG 78.0 "LIBBY " 13.8 "3 " TG 78.0 "LIBBY " 13.8 "4 " TG 78.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line Page 30 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 81.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 89.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 31 of 722 APPENDIX I – SWITCHING SEQUENCES 21_Bvw-Gsn12_RAS_N2S.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 and #2 500 kV lines DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 63.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (9.2 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (17.7 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.2 "COLSTP 1" 22.0 "1 " MBL 69.2 "COLSTP 1" 22.0 "1 " "D" MBL 69.2 "COLSTP 1" 22.0 "2 " "D" * * Trip Hardin Generation TG 70.0 "HARDIN1 " 13.8 "1 " * * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW TG 70.2 "COLSTP 3" 26.0 "1 " MBL 70.2 "COLSTP 3" 26.0 "1 " "D" MBL 70.2 "COLSTP 3" 26.0 "2 " "D" Page 32 of 722 APPENDIX I – SWITCHING SEQUENCES * * ATR trip time for Colstrip 4 from ATR emulation software (10.2 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 4 26.0 823 MW TG 70.2 "COLSTP 4" 26.0 "1 " MBL 70.2 "COLSTP 4" 26.0 "1 " "D" MBL 70.2 "COLSTP 4" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 77.7 "COLSTRP " 115. "c1" "R" * * ATR trip time for Colstrip 3 from ATR emulation software (10.2 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (18.7 cycles). * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c3" "R" * * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c4" "R" Page 33 of 722 APPENDIX I – SWITCHING SEQUENCES 21_Bvw-Gsn12_RAS_Pre.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1a * * Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 and #2 500 kV lines DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 63.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * * ATR trip time for Colstrip 1 from ATR emulation software (9.2 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (17.7 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.2 "COLSTP 1" 22.0 "1 " MBL 69.2 "COLSTP 1" 22.0 "1 " "D" MBL 69.2 "COLSTP 1" 22.0 "2 " "D" * * Trip Hardin Generation TG 70.0 "HARDIN1 " 13.8 "1 " * * ATR trip time for Colstrip 3 from ATR emulation software (10.2 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW Page 34 of 722 APPENDIX I – SWITCHING SEQUENCES TG 70.2 "COLSTP 3" 26.0 "1 " MBL 70.2 "COLSTP 3" 26.0 "1 " "D" MBL 70.2 "COLSTP 3" 26.0 "2 " "D" * * ATR trip time for Colstrip 4 from ATR emulation software (10.2 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 4 26.0 823 MW TG 70.2 "COLSTP 4" 26.0 "1 " MBL 70.2 "COLSTP 4" 26.0 "1 " "D" MBL 70.2 "COLSTP 4" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 77.7 "COLSTRP " 115.0 "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230.0 "c3" "R" * * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c4" "R" Page 35 of 722 APPENDIX I – SWITCHING SEQUENCES 21_Bvw-Gsn12_RAS_S2N.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1c * * Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 and #2 500 kV lines DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 63.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * * ATR trip time for Colstrip 1 from ATR emulation software (8.0 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (16.5 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.2 "COLSTP 1" 22.0 "1 " MBL 69.2 "COLSTP 1" 22.0 "1 " "D" MBL 69.2 "COLSTP 1" 22.0 "2 " "D" * * Trip Hardin Generation TG 70.0 "HARDIN1 " 13.8 "1 " * * ATR trip time for Colstrip 3 from ATR emulation software (9.0 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (17.5 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW Page 36 of 722 APPENDIX I – SWITCHING SEQUENCES TG 70.2 "COLSTP 3" 26.0 "1 " MBL 70.2 "COLSTP 3" 26.0 "1 " "D" MBL 70.2 "COLSTP 3" 26.0 "2 " "D" * * ATR trip time for Colstrip 4 from ATR emulation software (9.0 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (17.5 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 4 26.0 823 MW TG 70.2 "COLSTP 4" 26.0 "1 " MBL 70.2 "COLSTP 4" 26.0 "1 " "D" MBL 70.2 "COLSTP 4" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 77.7 "COLSTRP " 115. "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c3" "R" * * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c4" "R" Page 37 of 722 APPENDIX I – SWITCHING SEQUENCES 22_Bvw-Gsn12_1P_RAS_N2S.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Double Single Line to Ground Fault on Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Remove Broadview-Townsend-Garrison #1 and #2 500 kV lines * and * Apply double single line to ground fault at Townsend 500 kV using a new * equivalent line model DL 60.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 60.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "GARRISON" 500. "1 " RL 60.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Clear bus fault at Townsend 500 kV DL 63.0 "BROADVU " 500. "GARRISON" 500. "FL" RL 63.0 "BROADVU " 500. "GARRISON" 500. "2P" * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (12.4 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (20.9 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 330 MW TG 73.6 "COLSTP 1" 22.0 "1 " MBL 73.6 "COLSTP 1" 22.0 "1 " "D" MBL 73.6 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (13.4 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (21.9 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 3 26.0 775 MW TG 74.6 "COLSTP 3" 26.0 "1 " Page 38 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 74.6 "COLSTP 3" 26.0 "1 " "D" MBL 74.6 "COLSTP 3" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 82.1 "COLSTRP " 115.0 "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 83.1 "COLSTRP " 230. "c3" "R" * * * Reclose open phases into the fault DL 108.0 "BROADVU " 500. "GARRISON" 500. "2P" RL 108.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Open all three phases of both lines and lock out DL 111.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Trip Hardin Generation TG 119.0 "HARDIN1 " 13.8 "1 " * ATR trip time for Colstrip 4 from ATR emulation software (10.2 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 4 26.0 823 MW TG 127.4 "COLSTP 4" 26.0 "1 " MBL 127.4 "COLSTP 4" 26.0 "1 " "D" MBL 127.4 "COLSTP 4" 26.0 "2 " "D" * * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 135.9 "COLSTRP " 230.0 "c4" "R" Page 39 of 722 APPENDIX I – SWITCHING SEQUENCES 22_Bvw-Gsn12_1P_RAS_Pre.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1a * * Double Single Line to Ground Fault on Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Remove Broadview-Townsend-Garrison #1 and #2 500 kV lines * and * Apply double single line to ground fault at Townsend 500 kV using a new * equivalent line model DL 60.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 60.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "GARRISON" 500. "1 " RL 60.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Clear bus fault at Townsend 500 kV DL 63.0 "BROADVU " 500. "GARRISON" 500. "FL" RL 63.0 "BROADVU " 500. "GARRISON" 500. "2P" * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (12.8 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (21.3 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 74.0 "COLSTP 1" 22.0 "1 " MBL 74.0 "COLSTP 1" 22.0 "1 " "D" MBL 74.0 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (13.8 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (22.3 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 3 26.0 813 MW TG 75.0 "COLSTP 3" 26.0 "1 " Page 40 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 75.0 "COLSTP 3" 26.0 "1 " "D" MBL 75.0 "COLSTP 3" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 82.5 "COLSTRP " 115.0 "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 83.5 "COLSTRP " 230. "c3" "R" * * Reclose open phases into the fault DL 108.0 "BROADVU " 500. "GARRISON" 500. "2P" RL 108.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Open all three phases of both lines and lock out DL 111.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Trip Hardin Generation TG 119.0 "HARDIN1 " 13.8 "1 " * ATR trip time for Colstrip 4 from ATR emulation software (69 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (77.5 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 4 26.0 731 MW TG 117.8 "COLSTP 4" 26.0 "1 " MBL 117.8 "COLSTP 4" 26.0 "1 " "D" MBL 117.8 "COLSTP 4" 26.0 "2 " "D" * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 136.3 "COLSTRP " 230.0 "c4" "R" Page 41 of 722 APPENDIX I – SWITCHING SEQUENCES 22_Bvw-Gsn12_1P_RAS_S2N.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1c * * Double Single Line to Ground Fault on Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Remove Broadview-Townsend-Garrison #1 and #2 500 kV lines * and * Apply double single line to ground fault at Townsend 500 kV using a new * equivalent line model DL 60.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 60.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "GARRISON" 500. "1 " RL 60.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Clear bus fault at Townsend 500 kV DL 63.0 "BROADVU " 500. "GARRISON" 500. "FL" RL 63.0 "BROADVU " 500. "GARRISON" 500. "2P" * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (12.8 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (21.3 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 74.0 "COLSTP 1" 22.0 "1 " MBL 74.0 "COLSTP 1" 22.0 "1 " "D" MBL 74.0 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (13.8 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (22.3 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 3 26.0 813 MW TG 75.0 "COLSTP 3" 26.0 "1 " Page 42 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 75.0 "COLSTP 3" 26.0 "1 " "D" MBL 75.0 "COLSTP 3" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 82.5 "COLSTRP " 115.0 "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 83.5 "COLSTRP " 230. "c3" "R" * * Reclose open phases into the fault DL 108.0 "BROADVU " 500. "GARRISON" 500. "2P" RL 108.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Open all three phases of both lines and lock out DL 111.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Trip Hardin Generation TG 119.0 "HARDIN1 " 13.8 "1 " * ATR trip time for Colstrip 4 from ATR emulation software (69 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (77.5 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 4 26.0 731 MW TG 117.4 "COLSTP 4" 26.0 "1 " MBL 117.4 "COLSTP 4" 26.0 "1 " "D" MBL 117.4 "COLSTP 4" 26.0 "2 " "D" * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 135.9 "COLSTRP " 230.0 "c4" "R" Page 43 of 722 APPENDIX I – SWITCHING SEQUENCES 23_Gsn-Tft12_RAS_N2S.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1b * * Garrison-Taft #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1522 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 and #2 500 kV lines DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&B" 500. "TAFT " 500. "2 " DL 63.0 "GARRIS&B" 500. "GARRIS&A" 500. "2 " DL 63.0 "GARRISON" 500. "GARRIS&A" 500. "2 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (9.6 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (18.1 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.6 "COLSTP 1" 22.0 "1 " MBL 69.6 "COLSTP 1" 22.0 "1 " "D" MBL 69.9 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 2 from ATR emulation software (10.4 cycles). * Time Colstrip 2 aux-load was "hot-transferred" (18.9 cycles). * Trip COLSTP 2 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62049 COLSTP 2 22.0 360 MW TG 70.4 "COLSTP 2" 22.0 "1 " MBL 70.4 "COLSTP 2" 22.0 "1 " "D" MBL 70.4 "COLSTP 2" 22.0 "2 " "D" * Page 44 of 722 APPENDIX I – SWITCHING SEQUENCES * ATR trip time for Colstrip 3 from ATR emulation software (10.6 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (19.1 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW TG 70.6 "COLSTP 3" 26.0 "1 " MBL 70.6 "COLSTP 3" 26.0 "1 " "D" MBL 70.6 "COLSTP 3" 26.0 "2 " "D" * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 78.1 "COLSTRP " 115. "c1" "R" * * shift 80% of Colstrip 2 Aux load to the Colstrip 115kV MBL 78.9 "COLSTRP " 115. "c2" "R" * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 79.1 "COLSTRP " 230. "c3" "R" Page 45 of 722 APPENDIX I – SWITCHING SEQUENCES 23_Gsn-Tft12_RAS_Pre.swt RUN * * Last updated 11/18/2006 by TCL * Non simultaneous Dynamics III-1a * * Garrison-Taft #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1543 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 and #2 500 kV lines DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&B" 500. "TAFT " 500. "2 " DL 63.0 "GARRIS&B" 500. "GARRIS&A" 500. "2 " DL 63.0 "GARRISON" 500. "GARRIS&A" 500. "2 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (9.6 cycles). * * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.6 "COLSTP 1" 22.0 "1 " MBL 69.6 "COLSTP 1" 22.0 "1 " "D" MBL 69.6 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (10.6 cycles). * Shed unit at 62047 COLSTP 3 26.0 823 MW TG 70.6 "COLSTP 3" 26.0 "1 " MBL 70.6 "COLSTP 3" 26.0 "1 " "D" MBL 70.6 "COLSTP 3" 26.0 "2 " "D" * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 Page 46 of 722 APPENDIX I – SWITCHING SEQUENCES MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * ATR trip time for Colstrip 2 from ATR emulation software (10.4 cycles). * Shed unit at 62049 COLSTP 2 22.0 360 MW TG 71.2 "COLSTP 2" 22.0 "1 " MBL 71.2 "COLSTP 2" 22.0 "1 " "D" MBL 71.2 "COLSTP 2" 22.0 "2 " "D" * * Time Colstrip 1 aux-load was "hot-transferred" (18.1 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 78.1 "COLSTRP " 115. "c1" "R" * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * Time Colstrip 4 aux-load was "hot-transferred" (19.1 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 79.1 "COLSTRP " 230. "c3" "R" * * Time Colstrip 2 aux-load was "hot-transferred" (18.9 cycles). * shift 80% of Colstrip 2 Aux load to the Colstrip 115kV MBL 79.7 "COLSTRP " 115. "c2" "R" Page 47 of 722 APPENDIX I – SWITCHING SEQUENCES 23_Gsn-Tft12_RAS_S2N.swt RUN * * Last updated 11/19/2006 by TCL * Non simultaneous Dynamics III-1c * * Garrison-Taft #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1250 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 and #2 500 kV lines DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&B" 500. "TAFT " 500. "2 " DL 63.0 "GARRIS&B" 500. "GARRIS&A" 500. "2 " DL 63.0 "GARRISON" 500. "GARRIS&A" 500. "2 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (9.6 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (18.1 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 70.0 "COLSTP 1" 22.0 "1 " MBL 70.0 "COLSTP 1" 22.0 "1 " "D" MBL 70.0 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (10.6 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (19.1 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW TG 71.0 "COLSTP 3" 26.0 "1 " MBL 71.0 "COLSTP 3" 26.0 "1 " "D" MBL 71.0 "COLSTP 3" 26.0 "2 " "D" * Page 48 of 722 APPENDIX I – SWITCHING SEQUENCES * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 78.5 "COLSTRP " 115. "c1" "R" * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 79.5 "COLSTRP " 230. "c3" "R" Page 49 of 722 APPENDIX I – SWITCHING SEQUENCES Blt-Kph12_240.swt RUN * * Benalto - Keephills #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Keephills #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "03" * DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "90" * Page 50 of 722 APPENDIX I – SWITCHING SEQUENCES Blt-Src12_240.swt RUN * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 51 of 722 APPENDIX I – SWITCHING SEQUENCES Crn-Sel500_RAS_HS.swt RUN * * Cranbrook - Selkirk 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Cranbrook 500 kV Line DL 64.0 "SEL500 " 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * ** the following assumes svd at 50838 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch off 38.4 MVAr ** shunt capacitor at CBK 12 12.6 kV bus 50838 Page 52 of 722 APPENDIX I – SWITCHING SEQUENCES **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) *MBS 90.0 "CBK 12 " 12.6 "b0" "D" *MBS 90.0 "CBK 12 " 12.6 "b1" "D" * * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 53 of 722 APPENDIX I – SWITCHING SEQUENCES Crn-Sel500_RAS_HS_M.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50498 GMS G4 13.8 240 MW TG 72.0 "GMS G4 " 13.8 "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. Page 54 of 722 APPENDIX I – SWITCHING SEQUENCES * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * ** the following assumes svd at 50542 converted to shunt devices ** at 5 seconds if WSN230 voltage is > 1.09 pu, ** switch in one 230 kV 75 MVAr reactor at bus 50542 *MBS 360. "WSN230 " 230. "b2" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50183 converted to shunt devices ** at 10 seconds if ING230 voltage is > 1.06 pu, ** switch in one 230 kV 132 MVAr reactor at bus 50183 Ingledow 230 kV *MBS 660. "ING230 " 230. "b2" "R" ** ** at 20 seconds if ING230 voltage is still > 1.06 pu, ** switch in another 230 kV 132 MVAr reactor at 50183 Ingledow 230 kV *CC MBS 1260 "ING230 " 230. "b3" "R" * Page 55 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr12_500_RAS_HS.swt RUN * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1300 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * required generation shedding 1272 MW, actual shedding is 1300 MW * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50645 REV G2 16.0 450 MW TG 72.0 "REV G2 " 16.0 "1 " * Page 56 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr500.swt RUN * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 57 of 722 APPENDIX I – SWITCHING SEQUENCES Genesee3.swt RUN * * Genessee Unit 3 450 MW * * CC cards for post-transient only * CC DRP 450 * * Apply bus fault at Genesee 500 kV FB 60.0 "GENESEE4" 500. * * Clear bus fault at Genesee 500 kV CFB 64.0 "GENESEE4" 500. * * Trip Genessee Unit 3 450 MW TG 64.0 "GENES 39" 20.5 "3 " * Page 58 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_HS.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50498 GMS G4 13.8 240 MW TG 72.0 "GMS G4 " 13.8 "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * ** the following assumes svd at 50542 converted to shunt devices ** at 5 seconds if WSN230 voltage is > 1.09 pu, ** switch in one 230 kV 75 MVAr reactor at bus 50542 Page 59 of 722 APPENDIX I – SWITCHING SEQUENCES *MBS 360. "WSN230 " 230. "b2" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50183 converted to shunt devices ** at 10 seconds if ING230 voltage is > 1.06 pu, ** switch in one 230 kV 132 MVAr reactor at bus 50183 Ingledow 230 kV *MBS 660. "ING230 " 230. "b2" "R" ** ** at 20 seconds if ING230 voltage is still > 1.06 pu, ** switch in another 230 kV 132 MVAr reactor at 50183 Ingledow 230 kV *CC MBS 1260 "ING230 " 230. "b3" "R" * Page 60 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_HS_M.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50498 GMS G4 13.8 240 MW TG 72.0 "GMS G4 " 13.8 "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. Page 61 of 722 APPENDIX I – SWITCHING SEQUENCES * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * ** the following assumes svd at 50542 converted to shunt devices ** at 5 seconds if WSN230 voltage is > 1.09 pu, ** switch in one 230 kV 75 MVAr reactor at bus 50542 *MBS 360. "WSN230 " 230. "b2" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50183 converted to shunt devices ** at 10 seconds if ING230 voltage is > 1.06 pu, ** switch in one 230 kV 132 MVAr reactor at bus 50183 Ingledow 230 kV *MBS 660. "ING230 " 230. "b2" "R" ** ** at 20 seconds if ING230 voltage is still > 1.06 pu, ** switch in another 230 kV 132 MVAr reactor at 50183 Ingledow 230 kV *CC MBS 1260 "ING230 " 230. "b3" "R" * Page 62 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus500_RAS_HS.swt RUN * * Ingledow - Custer #1 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * Page 63 of 722 APPENDIX I – SWITCHING SEQUENCES Jan-Red12_240.swt RUN * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. * * Clear bus fault at Janet 240 kV CFB 66.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 66.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 66.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 64 of 722 APPENDIX I – SWITCHING SEQUENCES Janet_138Cap.swt RUN * * Switch in one Janet 138 kV capacitor bank * * CC cards for post-transient only * CC DRP 0 * * Insert one cap at Janet 138 (81 MVAr) MBS 60.0 "JANET 7" 138. "b0" "R" 0.0 0.0 * Page 65 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_HS.swt RUN * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 66 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_HS_M.swt RUN * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 67 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Jnt12_240.swt RUN * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 66.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 68 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Jnt240.swt RUN * * Langdon - Janet #1 240 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 240 kV Line DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * Page 69 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Lth12_240.swt RUN * * Langdon - N. Lethbridge #1 and #2 240 kV Lines * Pre-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon #1 and #2 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "N LETHB4" 240. "MILO 2 " 240. "23" * Page 70 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Lth_Lgd-Mtl_240.swt RUN * * Langdon - N. Lethbridge and Langdon - MATL AB 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon and N. Lethbridge - MATL AB 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "MILO 2 " 240. "MATL_AB " 240. "23" * Page 71 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Lth_Mtl-Lth_240.swt RUN * * Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at N. Lethbridge 240 kV FB 60.0 "N LETHB4" 240. * * Clear bus fault at N. Lethbridge 240 kV CFB 66.0 "N LETHB4" 240. * * Trip Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "N LETHB4" 240. "MATL_AB " 240. "23" * Page 72 of 722 APPENDIX I – SWITCHING SEQUENCES Mar-Gfl230.swt RUN * * Marias to Great Falls 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Marias 230 kV FB 60.0 "MARIAS " 230 * * Clear bus fault at Marias 230 kV CFB 64.0 "MARIAS " 230 * * Trip Marias to Great Falls 230 kV Line DL 64.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 64.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 64.0 "MATLN_&2" 230. * * Trip MATL PS to Cutbank 230 kV Line DL 124.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 124.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 124.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DB 124.0 "MATL_AB " 230. DB 124.0 "MATLN_&1" 230. DB 124.0 "MARIAS " 230. * Page 73 of 722 APPENDIX I – SWITCHING SEQUENCES Mtl-Mar230.swt RUN * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DB 64.0 "MATL_AB " 230. DB 64.0 "MATLN_&1" 230. * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 124.0 "MARIAS " 230. DB 124.0 "MATLN_&2" 230. * Page 74 of 722 APPENDIX I – SWITCHING SEQUENCES Nel-Bnd230_RAS_HS.swt RUN * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 72.0 "BOUNDRY2" 14.4 "5 " * Page 75 of 722 APPENDIX I – SWITCHING SEQUENCES Nic-Ack12_500_RAS_HS.swt RUN * * Nicola - Ashton Creek #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1700 * * Apply bus fault at Ashton Creek 500 kV FB 60.0 "ACK500 " 500. * * Clear bus fault at Ashton Creek 500 kV CFB 64.0 "ACK500 " 500. * * Trip Nicola - Ashton Creek #1 and #2 500 kV Lines DL 64.0 "NIC500 " 500. "ACK500 " 500. "1 " DL 64.0 "NIC500 " 500. "ACK500 " 500. "2 " * * required generation shedding 1682 MW, actual shedding is 1700 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Trip VNT138 - VVW138 138 kV Line DL 70.0 "VNT138 " 138. "VVW138 " 138. "1 " * * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50645 REV G2 16.0 450 MW TG 72.0 "REV G2 " 16.0 "1 " * Shed unit at 50646 REV G3 16.0 450 MW TG 72.0 "REV G3 " 16.0 "1 " * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "A " * * Trip SAM138 - STO138 138 kV Line DL 72.0 "SAM138 " 138. "STO138 " 138. "1 " * * 3p reclosing, lead end ACK, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 150. "ACK500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 153. "ACK500 " 500. Page 76 of 722 APPENDIX I – SWITCHING SEQUENCES * ** at 10 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 Ashton Creek 500 kV *MBS 660. "ACK500 " 500. "b0" "C" 0.0 -2.45 * Page 77 of 722 APPENDIX I – SWITCHING SEQUENCES Nic-Ing_Nic-Mdn500_RAS_HS.swt RUN * * Nicola - Ingledow and Nicola - Meridian 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1620 * * Apply bus fault at Nicola 500 kV FB 60.0 "NIC500 " 500. * * Clear bus fault at Nicola 500 kV CFB 64.0 "NIC500 " 500. * * Trip Nicola - Ingledow and Nicola - Meridian 500 kV Lines DL 64.0 "NIC500 " 500. "ING500 " 500. "1 " DL 64.0 "NIC500 " 500. "MDN500 " 500. "1 " * * Disconnect 245 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b " "D" * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1468 MW, actual shedding is 1480 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "A " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * Page 78 of 722 APPENDIX I – SWITCHING SEQUENCES * 3p reclosing, lead end MDN, Follow end NIC * 3p reclosing, lead end ING, Follow end NIC * Meridian - Nicola Rpu=0.002480 Xpu=0.016500 Bpu=0.0 * Ingledow - Nicola Rpu=0.002530 Xpu=0.018370 Bpu=0.0 (Gpu=7.36, Bpu=-53.4) * Apply bus fault at Meridian 500 kV through line impedance FB 120. "MDN500 " 500. .002480 .016500 * * Reinsert shunt at Ingledow with 1/line impedance MBS 120. "ING500 " 500. "FT" R * * Clear bus fault at Meridian 500 kV CFB 123. "MDN500 " 500. * * Disconnect shunt at Ingledow with 1/line impedance MBS 123. "ING500 " 500. "FT" D * Page 79 of 722 APPENDIX I – SWITCHING SEQUENCES Nic-Mdn500_RAS_HS.swt RUN * * Nicola - Meridian 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Meridian 500 kV FB 60.0 "MDN500 " 500. * * Clear bus fault at Meridian 500 kV CFB 64.0 "MDN500 " 500. * * Trip Nicola - Meridian 500 kV Line DL 64.0 "MDN500 " 500. "NIC500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b " "C" 0.0 -1.225 * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * * 3p reclosing, lead end MDN, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 120. "MDN500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "MDN500 " 500. * Page 80 of 722 APPENDIX I – SWITCHING SEQUENCES Red-Elr12_240.swt RUN * * Red Deer - Ellerslie #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Red Deer 240 kV FB 60.0 "RED DEE4" 240. * * Clear bus fault at Red Deer 240 kV CFB 66.0 "RED DEE4" 240. * * Trip Red Deer - Ellerslie #1 and #2 240 kV Lines DL 66.0 "RED DEE4" 240. "ELLERSLI" 240. "10" * DL 66.0 "RED DEE4" 240. "GAETZ 4" 240. "14" DL 66.0 "GAETZ 4" 240. "BIGSTON4" 240. "14" DL 66.0 "BIGSTON4" 240. "ELLERSLI" 240. "14" * Page 81 of 722 APPENDIX I – SWITCHING SEQUENCES Sel-Ack500_RAS_HS.swt RUN * * Selkirk - Ashton Creek 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek 500 kV Line DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b0" "D" * * 3p reclosing, lead end SEL, Follow end ACK * Apply bus fault at Selkirk 500 kV FB 120. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "SEL500 " 500. * Page 82 of 722 APPENDIX I – SWITCHING SEQUENCES Sel-Ack_Sel-Vas500_RAS_HS.swt RUN * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b0" "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 675 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * Shed unit at 50767 SEV G2 13.8 180 MW TG 70.0 "SEV G2 " 13.8 "1 " * Shed unit at 51044 ALH G1 13.8 75 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Trip GFT-161 - OLI-161 161 kV Line DL 70.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 83 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 50838 converted to shunt devices ** if CBK230 voltage is greater than 1.06 pu, then switch off 38.4 MVAr ** shunt capacitor at CBK 12 12.6 kV bus 50838 **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) *MBS 360. "CBK 12 " 12.6 "b0" "D" *MBS 360. "CBK 12 " 12.6 "b1" "D" ** ** if CBK230 voltage is still greater than 1.06 pu, then switch on 24 MVAr ** shunt reactors at CBK 12 12.6 kV bus 50838 *MBS 390. "CBK 12 " 12.6 "b2" "R" *MBS 390. "CBK 12 " 12.6 "b3" "R" * Page 84 of 722 APPENDIX I – SWITCHING SEQUENCES Sel-Ack_Sel-Vas500_RAS_HS_M.swt RUN * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b0" "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 675 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * Shed unit at 50767 SEV G2 13.8 180 MW TG 70.0 "SEV G2 " 13.8 "1 " * Shed unit at 51044 ALH-G1 13.8 75 MW TG 70.0 "ALH-G1 " 13.8 "1 " * * Trip GFT-161 - OLI-161 161 kV Line DL 70.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 85 of 722 APPENDIX I – SWITCHING SEQUENCES * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ** the following assumes svd at 50838 converted to shunt devices ** if CBK230 voltage is greater than 1.06 pu, then switch off 38.4 MVAr ** shunt capacitor at CBK 12 12.6 kV bus 50838 **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) *MBS 360. "CBK 12 " 12.6 "b0" "D" *MBS 360. "CBK 12 " 12.6 "b1" "D" ** ** if CBK230 voltage is still greater than 1.06 pu, then switch on 24 MVAr ** shunt reactors at CBK 12 12.6 kV bus 50838 *MBS 390. "CBK 12 " 12.6 "b2" "R" *MBS 390. "CBK 12 " 12.6 "b3" "R" * Page 86 of 722 APPENDIX I – SWITCHING SEQUENCES Sel-Vas500_RAS_HS.swt RUN * * Selkirk - Vaseux Lake 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Vaseux Lake 500 kV Line DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b " "D" * * 3p reclosing, lead end SEL, Follow end VAS * Apply bus fault at Selkirk 500 kV FB 98.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 101. "SEL500 " 500. * Page 87 of 722 APPENDIX I – SWITCHING SEQUENCES Sun-Blt12_240.swt RUN * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. * * Clear bus fault at Sundance 240 kV CFB 66.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 88 of 722 APPENDIX I – SWITCHING SEQUENCES Non-Simultaneous Transient & Post Transient 07 LSP: Page 89 of 722 APPENDIX I – SWITCHING SEQUENCES 3_Csp-Bvw_RAS_N2S3.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1b * * Colstrip - Broadview #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "COLSTRP " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "COLSTRP " 500. * * Trip Colstrip - Broadview #1 500 kV line DL 63.0 "COLSTRP " 500. "BROADV&1" 500. "1 " DL 63.0 "BROADVU " 500. "BROADV&1" 500. "1 " * * No Colstrip ATR Action Page 90 of 722 APPENDIX I – SWITCHING SEQUENCES 3_Csp-Bvw_RAS_Pre3.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1a * * Colstrip - Broadview #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "COLSTRP " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "COLSTRP " 500. * * Trip Colstrip - Broadview #1 500 kV line DL 63.0 "COLSTRP " 500. "BROADV&1" 500. "1 " DL 63.0 "BROADVU " 500. "BROADV&1" 500. "1 " * * No Colstrip ATR Action Page 91 of 722 APPENDIX I – SWITCHING SEQUENCES 3_Csp-Bvw_RAS_S2N3.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1c * * Colstrip - Broadview #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "COLSTRP " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "COLSTRP " 500. * * Trip Colstrip - Broadview #1 500 kV line DL 63.0 "COLSTRP " 500. "BROADV&1" 500. "1 " DL 63.0 "BROADVU " 500. "BROADV&1" 500. "1 " * * No Colstrip ATR Action Page 92 of 722 APPENDIX I – SWITCHING SEQUENCES 4_Bvw-Gsn_RAS_N2S.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1b * * Broadview-Townsend-Garrison #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 500 kV line DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DB 63.0 "TOWN1 " 500. DB 63.0 "GAR1EAST" 500. * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * No Colstrip ATR Page 93 of 722 APPENDIX I – SWITCHING SEQUENCES 4_Bvw-Gsn_RAS_Pre.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1a * * Broadview-Townsend-Garrison #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 500 kV line DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * No Colstrip ATR Page 94 of 722 APPENDIX I – SWITCHING SEQUENCES 4_Bvw-Gsn_RAS_S2N.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1c * * Broadview-Townsend-Garrison #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 500 kV line DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * No Colstrip ATR Page 95 of 722 APPENDIX I – SWITCHING SEQUENCES 5_Gsn-Tft_RAS_N2S.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1b * * Garrison-Taft #1 500 kV line with RAS * Note: Series Caps not bypassed during fault * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 500 kV line DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * No Colstrip ATR Page 96 of 722 APPENDIX I – SWITCHING SEQUENCES 5_Gsn-Tft_RAS_Pre.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1a * * Garrison-Taft #1 500 kV line with RAS * Note: Series Caps not bypassed during fault * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 500 kV line DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * No Colstrip ATR Page 97 of 722 APPENDIX I – SWITCHING SEQUENCES 5_Gsn-Tft_RAS_S2N.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1c * * Garrison-Taft #1 500 kV line with RAS * Note: Series Caps not bypassed during fault * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 500 kV line DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * No Colstrip ATR Page 98 of 722 APPENDIX I – SWITCHING SEQUENCES 10_BND-BEL1_BEL-USK_230_RAS.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #1 and Bell-Usk 230 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Bell - USK 230 kV Line DL 64.0 "BELL S&A" 230. "USK " 230. "1 " * Trip Boundary - Bell 230 kV Line DL 64.0 "BELL S1 " 230. "SACHEEN " 230. "1 " DL 64.0 "BOUNDARY" 230. "SACHEEN " 230. "1 " * Page 99 of 722 APPENDIX I – SWITCHING SEQUENCES 11_BND-BEL3230_ADY-BEL1_115_RAS2.s RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #3 and Addy - Bell #1 115 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Boundary - Bell #3 230 kV Line DL 64.0 "BELL S3 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&A" 230. "1 " DL 64.0 "BOUNDARY" 230. "ADDY 2&A" 230. "1 " * Trip Addy - Bell #1 115 kV Line * The conservative option for this contingency is to only trip the 230/115 kV bank * This option results in maximum post contingency loading on the remaining lines * (for north to south flows). DL 64.0 "ADDY 2 " 230. "ADDY " 115. "1 " Page 100 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS2.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 675 MW * Shed unit at 50769 KCL G1 13.8 110 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 110 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 150 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 150 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 100 MW TG 70.0 "SEV G3 " 13.8 "1 " Page 101 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 51044 ALH G1 13.8 75 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * * Switch off 12kV, 12 MVAR shunt capacitor at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch off 12kV, 12 MVAR shunt capacitor at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * Page 102 of 722 APPENDIX I – SWITCHING SEQUENCES * Switch off 12kV, 75 MVAR shunt capacitor at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* Page 103 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * (Required BC's genshedding amount 413 MW, actual shedding 420 MW) * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 150 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 150 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " Page 104 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * * Switch off 12kV, 12 MVAR shunt capacitor at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch off 12kV, 12 MVAR shunt capacitor at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * * Switch off 12kV, 75 MVAR shunt capacitor at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* Page 105 of 722 APPENDIX I – SWITCHING SEQUENCES 16_Tft-Gar_Tft-Bell_RAS_N2S.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Three Phase Fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 720 * * Apply Three Phase Fault at Taft FB 60.0 "TAFT " 500. 0.0 0.0 * * Clear bus fault at Taft 500 kV CFB 63.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 63.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 63.0 "BELL B&1" 500. "BELL BPA" 500. "1 " * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 68.0 "LIBBY " 13.8 "1 " TG 68.0 "LIBBY " 13.8 "2 " TG 68.0 "LIBBY " 13.8 "3 " TG 68.0 "LIBBY " 13.8 "4 " TG 68.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 Page 106 of 722 APPENDIX I – SWITCHING SEQUENCES MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 107 of 722 APPENDIX I – SWITCHING SEQUENCES 16_Tft-Gar_Tft-Bell_RAS_Pre.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1a * * Three Phase Fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 720 * * Apply Three Phase Fault at Taft FB 60.0 "TAFT " 500. 0.0 0.0 * * Clear bus fault at Taft 500 kV CFB 63.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 63.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 63.0 "BELL B&1" 500. "BELL BPA" 500. "1 " * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 68.0 "LIBBY " 13.8 "1 " TG 68.0 "LIBBY " 13.8 "2 " TG 68.0 "LIBBY " 13.8 "3 " TG 68.0 "LIBBY " 13.8 "4 " TG 68.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 Page 108 of 722 APPENDIX I – SWITCHING SEQUENCES MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 109 of 722 APPENDIX I – SWITCHING SEQUENCES 16_Tft-Gar_Tft-Bell_RAS_S2N.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1c * * Three Phase Fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 720 * * Apply Three Phase Fault at Taft FB 60.0 "TAFT " 500. 0.0 0.0 * * Clear bus fault at Taft 500 kV CFB 63.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 63.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 63.0 "BELL B&1" 500. "BELL BPA" 500. "1 " * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 68.0 "LIBBY " 13.8 "1 " TG 68.0 "LIBBY " 13.8 "2 " TG 68.0 "LIBBY " 13.8 "3 " TG 68.0 "LIBBY " 13.8 "4 " TG 68.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 Page 110 of 722 APPENDIX I – SWITCHING SEQUENCES MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 111 of 722 APPENDIX I – SWITCHING SEQUENCES 17_Tft-Gar_Tft-Bell_1P_RAS_N2S2.sw RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Single line-to-ground fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1350 * * Apply Single Line-to-ground Fault at Taft FB 60.0 "TAFT " 500. 0.00249 0.02685 DL 60.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 60.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 60.0 "BELL B&1" 500. "BELL BPA" 500. "1 " RL 60.0 "TAFT " 500. "BELL B&2" 500. "2P" RL 60.0 "BELL B&2" 500. "BELL B&1" 500. "2P" RL 60.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * Clear bus fault at Taft 500 kV CFB 72.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 72.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 72.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 72.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 72.0 "TAFT " 500. "BELL B&2" 500. "2P" DL 72.0 "BELL B&2" 500. "BELL B&1" 500. "2P" DL 72.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * Trip Garrison Reactor MBS 76.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * * ATR trip time for Colstrip 3 from ATR emulation software (10.2 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW TG 77.0 "COLSTP 3" 26.0 "1 " MBL 77.0 "COLSTP 3" 26.0 "1 " "D" MBL 77.0 "COLSTP 3" 26.0 "2 " "D" * Page 112 of 722 APPENDIX I – SWITCHING SEQUENCES * Trip Libby Generation (Units 1-5) TG 78.0 "LIBBY " 13.8 "1 " TG 78.0 "LIBBY " 13.8 "2 " TG 78.0 "LIBBY " 13.8 "3 " TG 78.0 "LIBBY " 13.8 "4 " TG 78.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line MBL 81.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 85.5 "COLSTRP " 230.0 "c3" "R" * * Insert Shunts at Rosebud and Custer 230 MBS 89.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 113 of 722 APPENDIX I – SWITCHING SEQUENCES 17_Tft-Gar_Tft-Bell_1P_RAS_Pre2.sw RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Single line-to-ground fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 580 * * Apply Single Line-to-ground Fault at Taft FB 60.0 "TAFT " 500. 0.00249 0.02685 DL 60.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 60.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 60.0 "BELL B&1" 500. "BELL BPA" 500. "1 " RL 60.0 "TAFT " 500. "BELL B&2" 500. "2P" RL 60.0 "BELL B&2" 500. "BELL B&1" 500. "2P" RL 60.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * Clear bus fault at Taft 500 kV CFB 72.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 72.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 72.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 72.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 72.0 "TAFT " 500. "BELL B&2" 500. "2P" DL 72.0 "BELL B&2" 500. "BELL B&1" 500. "2P" DL 72.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 76.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 78.0 "LIBBY " 13.8 "1 " TG 78.0 "LIBBY " 13.8 "2 " TG 78.0 "LIBBY " 13.8 "3 " TG 78.0 "LIBBY " 13.8 "4 " TG 78.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line Page 114 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 81.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 89.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 115 of 722 APPENDIX I – SWITCHING SEQUENCES 17_Tft-Gar_Tft-Bell_1P_RAS_S2N2.sw RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Single line-to-ground fault at Taft * Lose Taft-Garrison #1 and Taft-Bell 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 580 * * Apply Single Line-to-ground Fault at Taft FB 60.0 "TAFT " 500. 0.00249 0.02685 DL 60.0 "TAFT " 500. "BELL B&2" 500. "1 " DL 60.0 "BELL B&2" 500. "BELL B&1" 500. "1 " DL 60.0 "BELL B&1" 500. "BELL BPA" 500. "1 " RL 60.0 "TAFT " 500. "BELL B&2" 500. "2P" RL 60.0 "BELL B&2" 500. "BELL B&1" 500. "2P" RL 60.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * Clear bus fault at Taft 500 kV CFB 72.0 "TAFT " 500. * * Trip Taft-Garrison #1 and Taft-Bell 500 kV lines DL 72.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 72.0 "GARRIS&1" 500. "GARRIS&2" 500. "1 " DL 72.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 72.0 "TAFT " 500. "BELL B&2" 500. "2P" DL 72.0 "BELL B&2" 500. "BELL B&1" 500. "2P" DL 72.0 "BELL B&1" 500. "BELL BPA" 500. "2P" * * No Colstrip ATR Action * * Trip Garrison Reactor MBS 76.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Trip Libby Generation (Units 1-5) TG 78.0 "LIBBY " 13.8 "1 " TG 78.0 "LIBBY " 13.8 "2 " TG 78.0 "LIBBY " 13.8 "3 " TG 78.0 "LIBBY " 13.8 "4 " TG 78.0 "LIBBY " 13.8 "5 " * * Trip Miles City DC Line Page 116 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 81.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 81.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * Insert Shunts at Rosebud and Custer 230 MBS 89.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 89.0 "CUSTER " 230. "b2" "R" 0.0 0.0 Page 117 of 722 APPENDIX I – SWITCHING SEQUENCES 21_Bvw-Gsn12_RAS_N2S.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 and #2 500 kV lines DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 63.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (9.2 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (17.7 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.2 "COLSTP 1" 22.0 "1 " MBL 69.2 "COLSTP 1" 22.0 "1 " "D" MBL 69.2 "COLSTP 1" 22.0 "2 " "D" * * Trip Hardin Generation TG 70.0 "HARDIN1 " 13.8 "1 " * * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW TG 70.2 "COLSTP 3" 26.0 "1 " MBL 70.2 "COLSTP 3" 26.0 "1 " "D" MBL 70.2 "COLSTP 3" 26.0 "2 " "D" Page 118 of 722 APPENDIX I – SWITCHING SEQUENCES * * ATR trip time for Colstrip 4 from ATR emulation software (10.2 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 4 26.0 823 MW TG 70.2 "COLSTP 4" 26.0 "1 " MBL 70.2 "COLSTP 4" 26.0 "1 " "D" MBL 70.2 "COLSTP 4" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 77.7 "COLSTRP " 115. "c1" "R" * * ATR trip time for Colstrip 3 from ATR emulation software (10.2 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (18.7 cycles). * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c3" "R" * * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c4" "R" Page 119 of 722 APPENDIX I – SWITCHING SEQUENCES 21_Bvw-Gsn12_RAS_Pre.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1a * * Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 and #2 500 kV lines DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 63.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * * ATR trip time for Colstrip 1 from ATR emulation software (9.2 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (17.7 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.2 "COLSTP 1" 22.0 "1 " MBL 69.2 "COLSTP 1" 22.0 "1 " "D" MBL 69.2 "COLSTP 1" 22.0 "2 " "D" * * Trip Hardin Generation TG 70.0 "HARDIN1 " 13.8 "1 " * * ATR trip time for Colstrip 3 from ATR emulation software (10.2 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW Page 120 of 722 APPENDIX I – SWITCHING SEQUENCES TG 70.2 "COLSTP 3" 26.0 "1 " MBL 70.2 "COLSTP 3" 26.0 "1 " "D" MBL 70.2 "COLSTP 3" 26.0 "2 " "D" * * ATR trip time for Colstrip 4 from ATR emulation software (10.2 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 4 26.0 823 MW TG 70.2 "COLSTP 4" 26.0 "1 " MBL 70.2 "COLSTP 4" 26.0 "1 " "D" MBL 70.2 "COLSTP 4" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 77.7 "COLSTRP " 115.0 "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230.0 "c3" "R" * * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c4" "R" Page 121 of 722 APPENDIX I – SWITCHING SEQUENCES 21_Bvw-Gsn12_RAS_S2N.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1c * * Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Apply bus fault at Custer 500 kV FB 60.0 "BROADVU " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "BROADVU " 500. * * Trip Broadview-Townsend-Garrison #1 and #2 500 kV lines DL 63.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 63.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 63.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 63.0 "GAR2EAST" 500. "GARRISON" 500. "1 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * * ATR trip time for Colstrip 1 from ATR emulation software (8.0 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (16.5 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.2 "COLSTP 1" 22.0 "1 " MBL 69.2 "COLSTP 1" 22.0 "1 " "D" MBL 69.2 "COLSTP 1" 22.0 "2 " "D" * * Trip Hardin Generation TG 70.0 "HARDIN1 " 13.8 "1 " * * ATR trip time for Colstrip 3 from ATR emulation software (9.0 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (17.5 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW Page 122 of 722 APPENDIX I – SWITCHING SEQUENCES TG 70.2 "COLSTP 3" 26.0 "1 " MBL 70.2 "COLSTP 3" 26.0 "1 " "D" MBL 70.2 "COLSTP 3" 26.0 "2 " "D" * * ATR trip time for Colstrip 4 from ATR emulation software (9.0 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (17.5 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 4 26.0 823 MW TG 70.2 "COLSTP 4" 26.0 "1 " MBL 70.2 "COLSTP 4" 26.0 "1 " "D" MBL 70.2 "COLSTP 4" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 77.7 "COLSTRP " 115. "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c3" "R" * * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 78.7 "COLSTRP " 230. "c4" "R" Page 123 of 722 APPENDIX I – SWITCHING SEQUENCES 22_Bvw-Gsn12_1P_RAS_N2S.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1b * * Double Single Line to Ground Fault on Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Remove Broadview-Townsend-Garrison #1 and #2 500 kV lines * and * Apply double single line to ground fault at Townsend 500 kV using a new * equivalent line model DL 60.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 60.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "GARRISON" 500. "1 " RL 60.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Clear bus fault at Townsend 500 kV DL 63.0 "BROADVU " 500. "GARRISON" 500. "FL" RL 63.0 "BROADVU " 500. "GARRISON" 500. "2P" * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (12.4 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (20.9 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 330 MW TG 73.6 "COLSTP 1" 22.0 "1 " MBL 73.6 "COLSTP 1" 22.0 "1 " "D" MBL 73.6 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (13.4 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (21.9 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 3 26.0 775 MW TG 74.6 "COLSTP 3" 26.0 "1 " Page 124 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 74.6 "COLSTP 3" 26.0 "1 " "D" MBL 74.6 "COLSTP 3" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 82.1 "COLSTRP " 115.0 "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 83.1 "COLSTRP " 230. "c3" "R" * * * Reclose open phases into the fault DL 108.0 "BROADVU " 500. "GARRISON" 500. "2P" RL 108.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Open all three phases of both lines and lock out DL 111.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Trip Hardin Generation TG 119.0 "HARDIN1 " 13.8 "1 " * ATR trip time for Colstrip 4 from ATR emulation software (10.2 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (18.7 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 4 26.0 823 MW TG 127.4 "COLSTP 4" 26.0 "1 " MBL 127.4 "COLSTP 4" 26.0 "1 " "D" MBL 127.4 "COLSTP 4" 26.0 "2 " "D" * * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 135.9 "COLSTRP " 230.0 "c4" "R" Page 125 of 722 APPENDIX I – SWITCHING SEQUENCES 22_Bvw-Gsn12_1P_RAS_Pre.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1a * * Double Single Line to Ground Fault on Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Remove Broadview-Townsend-Garrison #1 and #2 500 kV lines * and * Apply double single line to ground fault at Townsend 500 kV using a new * equivalent line model DL 60.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 60.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "GARRISON" 500. "1 " RL 60.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Clear bus fault at Townsend 500 kV DL 63.0 "BROADVU " 500. "GARRISON" 500. "FL" RL 63.0 "BROADVU " 500. "GARRISON" 500. "2P" * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (12.8 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (21.3 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 74.0 "COLSTP 1" 22.0 "1 " MBL 74.0 "COLSTP 1" 22.0 "1 " "D" MBL 74.0 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (13.8 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (22.3 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 3 26.0 813 MW TG 75.0 "COLSTP 3" 26.0 "1 " Page 126 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 75.0 "COLSTP 3" 26.0 "1 " "D" MBL 75.0 "COLSTP 3" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 82.5 "COLSTRP " 115.0 "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 83.5 "COLSTRP " 230. "c3" "R" * * Reclose open phases into the fault DL 108.0 "BROADVU " 500. "GARRISON" 500. "2P" RL 108.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Open all three phases of both lines and lock out DL 111.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Trip Hardin Generation TG 119.0 "HARDIN1 " 13.8 "1 " * ATR trip time for Colstrip 4 from ATR emulation software (69 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (77.5 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 4 26.0 731 MW TG 117.8 "COLSTP 4" 26.0 "1 " MBL 117.8 "COLSTP 4" 26.0 "1 " "D" MBL 117.8 "COLSTP 4" 26.0 "2 " "D" * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 136.3 "COLSTRP " 230.0 "c4" "R" Page 127 of 722 APPENDIX I – SWITCHING SEQUENCES 22_Bvw-Gsn12_1P_RAS_S2N.swt RUN * * Last updated 12/09/2006 by RPM * Non simultaneous Dynamics III-1c * * Double Single Line to Ground Fault on Broadview-Townsend-Garrison #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1985 * * Remove Broadview-Townsend-Garrison #1 and #2 500 kV lines * and * Apply double single line to ground fault at Townsend 500 kV using a new * equivalent line model DL 60.0 "BROADVU " 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "TOWN1 " 500. "1 " DL 60.0 "GAR1EAST" 500. "GARRISON" 500. "1 " DL 60.0 "BROADVU " 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "TOWN2 " 500. "2 " DL 60.0 "GAR2EAST" 500. "GARRISON" 500. "1 " RL 60.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Clear bus fault at Townsend 500 kV DL 63.0 "BROADVU " 500. "GARRISON" 500. "FL" RL 63.0 "BROADVU " 500. "GARRISON" 500. "2P" * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (12.8 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (21.3 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 74.0 "COLSTP 1" 22.0 "1 " MBL 74.0 "COLSTP 1" 22.0 "1 " "D" MBL 74.0 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (13.8 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (22.3 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62047 COLSTP 3 26.0 813 MW TG 75.0 "COLSTP 3" 26.0 "1 " Page 128 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 75.0 "COLSTP 3" 26.0 "1 " "D" MBL 75.0 "COLSTP 3" 26.0 "2 " "D" * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 82.5 "COLSTRP " 115.0 "c1" "R" * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 83.5 "COLSTRP " 230. "c3" "R" * * Reclose open phases into the fault DL 108.0 "BROADVU " 500. "GARRISON" 500. "2P" RL 108.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Open all three phases of both lines and lock out DL 111.0 "BROADVU " 500. "GARRISON" 500. "FL" * * Trip Hardin Generation TG 119.0 "HARDIN1 " 13.8 "1 " * ATR trip time for Colstrip 4 from ATR emulation software (69 cycles). * Time Colstrip 4 aux-load was "hot-transferred" (77.5 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 4 26.0 731 MW TG 117.4 "COLSTP 4" 26.0 "1 " MBL 117.4 "COLSTP 4" 26.0 "1 " "D" MBL 117.4 "COLSTP 4" 26.0 "2 " "D" * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 135.9 "COLSTRP " 230.0 "c4" "R" Page 129 of 722 APPENDIX I – SWITCHING SEQUENCES 23_Gsn-Tft12_RAS_N2S.swt RUN * * Last updated 11/17/2006 by TCL * Non simultaneous Dynamics III-1b * * Garrison-Taft #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1522 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 and #2 500 kV lines DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&B" 500. "TAFT " 500. "2 " DL 63.0 "GARRIS&B" 500. "GARRIS&A" 500. "2 " DL 63.0 "GARRISON" 500. "GARRIS&A" 500. "2 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (9.6 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (18.1 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.6 "COLSTP 1" 22.0 "1 " MBL 69.6 "COLSTP 1" 22.0 "1 " "D" MBL 69.9 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 2 from ATR emulation software (10.4 cycles). * Time Colstrip 2 aux-load was "hot-transferred" (18.9 cycles). * Trip COLSTP 2 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62049 COLSTP 2 22.0 360 MW TG 70.4 "COLSTP 2" 22.0 "1 " MBL 70.4 "COLSTP 2" 22.0 "1 " "D" MBL 70.4 "COLSTP 2" 22.0 "2 " "D" * Page 130 of 722 APPENDIX I – SWITCHING SEQUENCES * ATR trip time for Colstrip 3 from ATR emulation software (10.6 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (19.1 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW TG 70.6 "COLSTP 3" 26.0 "1 " MBL 70.6 "COLSTP 3" 26.0 "1 " "D" MBL 70.6 "COLSTP 3" 26.0 "2 " "D" * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 78.1 "COLSTRP " 115. "c1" "R" * * shift 80% of Colstrip 2 Aux load to the Colstrip 115kV MBL 78.9 "COLSTRP " 115. "c2" "R" * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 79.1 "COLSTRP " 230. "c3" "R" Page 131 of 722 APPENDIX I – SWITCHING SEQUENCES 23_Gsn-Tft12_RAS_Pre.swt RUN * * Last updated 11/18/2006 by TCL * Non simultaneous Dynamics III-1a * * Garrison-Taft #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1543 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 and #2 500 kV lines DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&B" 500. "TAFT " 500. "2 " DL 63.0 "GARRIS&B" 500. "GARRIS&A" 500. "2 " DL 63.0 "GARRISON" 500. "GARRIS&A" 500. "2 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (9.6 cycles). * * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 69.6 "COLSTP 1" 22.0 "1 " MBL 69.6 "COLSTP 1" 22.0 "1 " "D" MBL 69.6 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (10.6 cycles). * Shed unit at 62047 COLSTP 3 26.0 823 MW TG 70.6 "COLSTP 3" 26.0 "1 " MBL 70.6 "COLSTP 3" 26.0 "1 " "D" MBL 70.6 "COLSTP 3" 26.0 "2 " "D" * * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 Page 132 of 722 APPENDIX I – SWITCHING SEQUENCES MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * ATR trip time for Colstrip 2 from ATR emulation software (10.4 cycles). * Shed unit at 62049 COLSTP 2 22.0 360 MW TG 71.2 "COLSTP 2" 22.0 "1 " MBL 71.2 "COLSTP 2" 22.0 "1 " "D" MBL 71.2 "COLSTP 2" 22.0 "2 " "D" * * Time Colstrip 1 aux-load was "hot-transferred" (18.1 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 78.1 "COLSTRP " 115. "c1" "R" * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * Time Colstrip 4 aux-load was "hot-transferred" (19.1 cycles). * Trip COLSTP 4 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * shift 80% of Colstrip 4 Aux load to the Colstrip 115kV MBL 79.1 "COLSTRP " 230. "c3" "R" * * Time Colstrip 2 aux-load was "hot-transferred" (18.9 cycles). * shift 80% of Colstrip 2 Aux load to the Colstrip 115kV MBL 79.7 "COLSTRP " 115. "c2" "R" Page 133 of 722 APPENDIX I – SWITCHING SEQUENCES 23_Gsn-Tft12_RAS_S2N.swt RUN * * Last updated 11/19/2006 by TCL * Non simultaneous Dynamics III-1c * * Garrison-Taft #1 and #2 500 kV lines with RAS * * CC cards for post-transient only * CC DRP 1250 * * Apply bus fault at Custer 500 kV FB 60.0 "GARRISON" 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "GARRISON" 500. * * Trip Garrison-Taft #1 and #2 500 kV lines DL 63.0 "GARRIS&2" 500. "TAFT " 500. "1 " DL 63.0 "GARRIS&2" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRISON" 500. "GARRIS&1" 500. "1 " DL 63.0 "GARRIS&B" 500. "TAFT " 500. "2 " DL 63.0 "GARRIS&B" 500. "GARRIS&A" 500. "2 " DL 63.0 "GARRISON" 500. "GARRIS&A" 500. "2 " * * Trip Garrison Reactor MBS 66.5 "GARRISON" 500. "b " "C" 0.0 0.0 * * Colstrip ATR Action * ATR trip time for Colstrip 1 from ATR emulation software (9.6 cycles). * Time Colstrip 1 aux-load was "hot-transferred" (18.1 cycles). * Trip COLSTP 1 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 115kV * Shed unit at 62050 COLSTP 1 22.0 360 MW TG 70.0 "COLSTP 1" 22.0 "1 " MBL 70.0 "COLSTP 1" 22.0 "1 " "D" MBL 70.0 "COLSTP 1" 22.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (10.6 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (19.1 cycles). * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW TG 71.0 "COLSTP 3" 26.0 "1 " MBL 71.0 "COLSTP 3" 26.0 "1 " "D" MBL 71.0 "COLSTP 3" 26.0 "2 " "D" * Page 134 of 722 APPENDIX I – SWITCHING SEQUENCES * Trip Miles City DC Line MBL 71.0 "MILCTYDC" 230. "D1" "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b " "D" 0.0 0.0 MBS 71.0 "MILCTYDC" 230. "b1" "D" 0.0 0.0 * * shift 80% of Colstrip 1 Aux load to the Colstrip 115kV MBL 78.5 "COLSTRP " 115. "c1" "R" * * Insert Shunts at Rosebud and Custer 230 MBS 79.0 "ROSEBUD " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b1" "R" 0.0 0.0 MBS 79.0 "CUSTER " 230. "b2" "R" 0.0 0.0 * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 79.5 "COLSTRP " 230. "c3" "R" Page 135 of 722 APPENDIX I – SWITCHING SEQUENCES Blt-Kph12_240.swt RUN * * Benalto - Keephills #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Keephills #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "03" * DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "90" * Page 136 of 722 APPENDIX I – SWITCHING SEQUENCES Blt-Src12_240.swt RUN * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 137 of 722 APPENDIX I – SWITCHING SEQUENCES Crn-Sel500_RAS_HS.swt RUN * * Cranbrook - Selkirk 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Cranbrook 500 kV Line DL 64.0 "SEL500 " 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * ** the following assumes svd at 50838 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch off 38.4 MVAr ** shunt capacitor at CBK 12 12.6 kV bus 50838 Page 138 of 722 APPENDIX I – SWITCHING SEQUENCES **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) *MBS 90.0 "CBK 12 " 12.6 "b0" "D" *MBS 90.0 "CBK 12 " 12.6 "b1" "D" * * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 139 of 722 APPENDIX I – SWITCHING SEQUENCES Crn-Sel500_RAS_HS_M.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50498 GMS G4 13.8 240 MW TG 72.0 "GMS G4 " 13.8 "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. Page 140 of 722 APPENDIX I – SWITCHING SEQUENCES * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * ** the following assumes svd at 50542 converted to shunt devices ** at 5 seconds if WSN230 voltage is > 1.09 pu, ** switch in one 230 kV 75 MVAr reactor at bus 50542 *MBS 360. "WSN230 " 230. "b2" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50183 converted to shunt devices ** at 10 seconds if ING230 voltage is > 1.06 pu, ** switch in one 230 kV 132 MVAr reactor at bus 50183 Ingledow 230 kV *MBS 660. "ING230 " 230. "b2" "R" ** ** at 20 seconds if ING230 voltage is still > 1.06 pu, ** switch in another 230 kV 132 MVAr reactor at 50183 Ingledow 230 kV *CC MBS 1260 "ING230 " 230. "b3" "R" * Page 141 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr12_500_RAS_HS.swt RUN * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1300 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * required generation shedding 1272 MW, actual shedding is 1300 MW * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50645 REV G2 16.0 450 MW TG 72.0 "REV G2 " 16.0 "1 " * Page 142 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr500.swt RUN * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 143 of 722 APPENDIX I – SWITCHING SEQUENCES Genesee3.swt RUN * * Genessee Unit 3 450 MW * * CC cards for post-transient only * CC DRP 450 * * Apply bus fault at Genesee 500 kV FB 60.0 "GENESEE4" 500. * * Clear bus fault at Genesee 500 kV CFB 64.0 "GENESEE4" 500. * * Trip Genessee Unit 3 450 MW TG 64.0 "GENES 39" 20.5 "3 " * Page 144 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_HS.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50498 GMS G4 13.8 240 MW TG 72.0 "GMS G4 " 13.8 "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * ** the following assumes svd at 50542 converted to shunt devices ** at 5 seconds if WSN230 voltage is > 1.09 pu, ** switch in one 230 kV 75 MVAr reactor at bus 50542 Page 145 of 722 APPENDIX I – SWITCHING SEQUENCES *MBS 360. "WSN230 " 230. "b2" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50183 converted to shunt devices ** at 10 seconds if ING230 voltage is > 1.06 pu, ** switch in one 230 kV 132 MVAr reactor at bus 50183 Ingledow 230 kV *MBS 660. "ING230 " 230. "b2" "R" ** ** at 20 seconds if ING230 voltage is still > 1.06 pu, ** switch in another 230 kV 132 MVAr reactor at 50183 Ingledow 230 kV *CC MBS 1260 "ING230 " 230. "b3" "R" * Page 146 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_HS_M.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50498 GMS G4 13.8 240 MW TG 72.0 "GMS G4 " 13.8 "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. Page 147 of 722 APPENDIX I – SWITCHING SEQUENCES * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * ** the following assumes svd at 50542 converted to shunt devices ** at 5 seconds if WSN230 voltage is > 1.09 pu, ** switch in one 230 kV 75 MVAr reactor at bus 50542 *MBS 360. "WSN230 " 230. "b2" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50183 converted to shunt devices ** at 10 seconds if ING230 voltage is > 1.06 pu, ** switch in one 230 kV 132 MVAr reactor at bus 50183 Ingledow 230 kV *MBS 660. "ING230 " 230. "b2" "R" ** ** at 20 seconds if ING230 voltage is still > 1.06 pu, ** switch in another 230 kV 132 MVAr reactor at 50183 Ingledow 230 kV *CC MBS 1260 "ING230 " 230. "b3" "R" * Page 148 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus500_RAS_HS.swt RUN * * Ingledow - Custer #1 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * Page 149 of 722 APPENDIX I – SWITCHING SEQUENCES Jan-Red12_240.swt RUN * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. * * Clear bus fault at Janet 240 kV CFB 66.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 66.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 66.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 150 of 722 APPENDIX I – SWITCHING SEQUENCES Janet_138Cap.swt RUN * * Switch in one Janet 138 kV capacitor bank * * CC cards for post-transient only * CC DRP 0 * * Insert one cap at Janet 138 (81 MVAr) MBS 60.0 "JANET 7" 138. "b0" "R" 0.0 0.0 * Page 151 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_HS.swt RUN * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 152 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_HS_M.swt RUN * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 153 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Jnt12_240.swt RUN * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 66.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 154 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Jnt240.swt RUN * * Langdon - Janet #1 240 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 240 kV Line DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * Page 155 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Lth12_240.swt RUN * * Langdon - N. Lethbridge #1 and #2 240 kV Lines * Pre-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon #1 and #2 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "N LETHB4" 240. "MILO 2 " 240. "23" * Page 156 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Lth_Lgd-Mtl_240.swt RUN * * Langdon - N. Lethbridge and Langdon - MATL AB 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon and N. Lethbridge - MATL AB 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "MILO 2 " 240. "MATL_AB " 240. "23" * Page 157 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Lth_Mtl-Lth_240.swt RUN * * Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at N. Lethbridge 240 kV FB 60.0 "N LETHB4" 240. * * Clear bus fault at N. Lethbridge 240 kV CFB 66.0 "N LETHB4" 240. * * Trip Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "N LETHB4" 240. "MATL_AB " 240. "23" * Page 158 of 722 APPENDIX I – SWITCHING SEQUENCES Mar-Gfl230.swt RUN * * Marias to Great Falls 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Marias 230 kV FB 60.0 "MARIAS " 230 * * Clear bus fault at Marias 230 kV CFB 64.0 "MARIAS " 230 * * Trip Marias to Great Falls 230 kV Line DL 64.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 64.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 64.0 "MATLN_&2" 230. * * Trip MATL PS to Cutbank 230 kV Line DL 124.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 124.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 124.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DB 124.0 "MATL_AB " 230. DB 124.0 "MATLN_&1" 230. DB 124.0 "MARIAS " 230. * Page 159 of 722 APPENDIX I – SWITCHING SEQUENCES Mtl-Mar230.swt RUN * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DB 64.0 "MATL_AB " 230. DB 64.0 "MATLN_&1" 230. * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 124.0 "MARIAS " 230. DB 124.0 "MATLN_&2" 230. * Page 160 of 722 APPENDIX I – SWITCHING SEQUENCES Nel-Bnd230_RAS_HS.swt RUN * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 72.0 "BOUNDRY2" 14.4 "5 " * Page 161 of 722 APPENDIX I – SWITCHING SEQUENCES Nic-Ack12_500_RAS_HS.swt RUN * * Nicola - Ashton Creek #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1700 * * Apply bus fault at Ashton Creek 500 kV FB 60.0 "ACK500 " 500. * * Clear bus fault at Ashton Creek 500 kV CFB 64.0 "ACK500 " 500. * * Trip Nicola - Ashton Creek #1 and #2 500 kV Lines DL 64.0 "NIC500 " 500. "ACK500 " 500. "1 " DL 64.0 "NIC500 " 500. "ACK500 " 500. "2 " * * required generation shedding 1682 MW, actual shedding is 1700 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Trip VNT138 - VVW138 138 kV Line DL 70.0 "VNT138 " 138. "VVW138 " 138. "1 " * * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50645 REV G2 16.0 450 MW TG 72.0 "REV G2 " 16.0 "1 " * Shed unit at 50646 REV G3 16.0 450 MW TG 72.0 "REV G3 " 16.0 "1 " * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "A " * * Trip SAM138 - STO138 138 kV Line DL 72.0 "SAM138 " 138. "STO138 " 138. "1 " * * 3p reclosing, lead end ACK, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 150. "ACK500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 153. "ACK500 " 500. Page 162 of 722 APPENDIX I – SWITCHING SEQUENCES * ** at 10 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 Ashton Creek 500 kV *MBS 660. "ACK500 " 500. "b0" "C" 0.0 -2.45 * Page 163 of 722 APPENDIX I – SWITCHING SEQUENCES Nic-Ing_Nic-Mdn500_RAS_HS.swt RUN * * Nicola - Ingledow and Nicola - Meridian 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1620 * * Apply bus fault at Nicola 500 kV FB 60.0 "NIC500 " 500. * * Clear bus fault at Nicola 500 kV CFB 64.0 "NIC500 " 500. * * Trip Nicola - Ingledow and Nicola - Meridian 500 kV Lines DL 64.0 "NIC500 " 500. "ING500 " 500. "1 " DL 64.0 "NIC500 " 500. "MDN500 " 500. "1 " * * Disconnect 245 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b " "D" * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1468 MW, actual shedding is 1480 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "A " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * Page 164 of 722 APPENDIX I – SWITCHING SEQUENCES * 3p reclosing, lead end MDN, Follow end NIC * 3p reclosing, lead end ING, Follow end NIC * Meridian - Nicola Rpu=0.002480 Xpu=0.016500 Bpu=0.0 * Ingledow - Nicola Rpu=0.002530 Xpu=0.018370 Bpu=0.0 (Gpu=7.36, Bpu=-53.4) * Apply bus fault at Meridian 500 kV through line impedance FB 120. "MDN500 " 500. .002480 .016500 * * Reinsert shunt at Ingledow with 1/line impedance MBS 120. "ING500 " 500. "FT" R * * Clear bus fault at Meridian 500 kV CFB 123. "MDN500 " 500. * * Disconnect shunt at Ingledow with 1/line impedance MBS 123. "ING500 " 500. "FT" D * Page 165 of 722 APPENDIX I – SWITCHING SEQUENCES Nic-Mdn500_RAS_HS.swt RUN * * Nicola - Meridian 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Meridian 500 kV FB 60.0 "MDN500 " 500. * * Clear bus fault at Meridian 500 kV CFB 64.0 "MDN500 " 500. * * Trip Nicola - Meridian 500 kV Line DL 64.0 "MDN500 " 500. "NIC500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b " "C" 0.0 -1.225 * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * * 3p reclosing, lead end MDN, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 120. "MDN500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "MDN500 " 500. * Page 166 of 722 APPENDIX I – SWITCHING SEQUENCES Red-Elr12_240.swt RUN * * Red Deer - Ellerslie #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Red Deer 240 kV FB 60.0 "RED DEE4" 240. * * Clear bus fault at Red Deer 240 kV CFB 66.0 "RED DEE4" 240. * * Trip Red Deer - Ellerslie #1 and #2 240 kV Lines DL 66.0 "RED DEE4" 240. "ELLERSLI" 240. "10" * DL 66.0 "RED DEE4" 240. "GAETZ 4" 240. "14" DL 66.0 "GAETZ 4" 240. "BIGSTON4" 240. "14" DL 66.0 "BIGSTON4" 240. "ELLERSLI" 240. "14" * Page 167 of 722 APPENDIX I – SWITCHING SEQUENCES Sel-Ack500_RAS_HS.swt RUN * * Selkirk - Ashton Creek 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek 500 kV Line DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b0" "D" * * 3p reclosing, lead end SEL, Follow end ACK * Apply bus fault at Selkirk 500 kV FB 120. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "SEL500 " 500. * Page 168 of 722 APPENDIX I – SWITCHING SEQUENCES Sel-Ack_Sel-Vas500_RAS_HS.swt RUN * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b0" "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 675 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * Shed unit at 50767 SEV G2 13.8 180 MW TG 70.0 "SEV G2 " 13.8 "1 " * Shed unit at 51044 ALH G1 13.8 75 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Trip GFT-161 - OLI-161 161 kV Line DL 70.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 169 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 50838 converted to shunt devices ** if CBK230 voltage is greater than 1.06 pu, then switch off 38.4 MVAr ** shunt capacitor at CBK 12 12.6 kV bus 50838 **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) *MBS 360. "CBK 12 " 12.6 "b0" "D" *MBS 360. "CBK 12 " 12.6 "b1" "D" ** ** if CBK230 voltage is still greater than 1.06 pu, then switch on 24 MVAr ** shunt reactors at CBK 12 12.6 kV bus 50838 *MBS 390. "CBK 12 " 12.6 "b2" "R" *MBS 390. "CBK 12 " 12.6 "b3" "R" * Page 170 of 722 APPENDIX I – SWITCHING SEQUENCES Sel-Ack_Sel-Vas500_RAS_HS_M.swt RUN * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b0" "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 675 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * Shed unit at 50767 SEV G2 13.8 180 MW TG 70.0 "SEV G2 " 13.8 "1 " * Shed unit at 51044 ALH-G1 13.8 75 MW TG 70.0 "ALH-G1 " 13.8 "1 " * * Trip GFT-161 - OLI-161 161 kV Line DL 70.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 171 of 722 APPENDIX I – SWITCHING SEQUENCES * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ** the following assumes svd at 50838 converted to shunt devices ** if CBK230 voltage is greater than 1.06 pu, then switch off 38.4 MVAr ** shunt capacitor at CBK 12 12.6 kV bus 50838 **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) *MBS 360. "CBK 12 " 12.6 "b0" "D" *MBS 360. "CBK 12 " 12.6 "b1" "D" ** ** if CBK230 voltage is still greater than 1.06 pu, then switch on 24 MVAr ** shunt reactors at CBK 12 12.6 kV bus 50838 *MBS 390. "CBK 12 " 12.6 "b2" "R" *MBS 390. "CBK 12 " 12.6 "b3" "R" * Page 172 of 722 APPENDIX I – SWITCHING SEQUENCES Sel-Vas500_RAS_HS.swt RUN * * Selkirk - Vaseux Lake 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Vaseux Lake 500 kV Line DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b " "D" * * 3p reclosing, lead end SEL, Follow end VAS * Apply bus fault at Selkirk 500 kV FB 98.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 101. "SEL500 " 500. * Page 173 of 722 APPENDIX I – SWITCHING SEQUENCES Sun-Blt12_240.swt RUN * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. * * Clear bus fault at Sundance 240 kV CFB 66.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "26" Page 174 of 722 APPENDIX I – SWITCHING SEQUENCES * 3_Csp-Bvw_RAS_N2S4.swt RUN * * Last updated 1/23/2007 by TCL * Non simultaneous Dynamics III-2b Checked ok * * Colstrip - Broadview #1 500 kV line with RAS * * CC cards for post-transient only * CC DRP 800 * * Apply bus fault at Custer 500 kV FB 60.0 "COLSTRP " 500. * * Clear bus fault at Custer 500 kV CFB 63.0 "COLSTRP " 500. * * Trip Colstrip - Broadview #1 500 kV line DL 63.0 "COLSTRP " 500. "BROADV&1" 500. "1 " DL 63.0 "BROADVU " 500. "BROADV&1" 500. "1 " * * Colstrip ATR Action * * Trip COLSTP 3 and Hot-Transfer 80% of Colstrip Aux load to the Colstrip 230kV * Shed unit at 62048 COLSTP 3 26.0 802 MW TG 75.0 "COLSTP 3" 26.0 "1 " MBL 75.0 "COLSTP 3" 26.0 "1 " "D" MBL 75.0 "COLSTP 3" 26.0 "2 " "D" * * ATR trip time for Colstrip 3 from ATR emulation software (15.0 cycles). * Time Colstrip 3 aux-load was "hot-transferred" (23.5 cycles). * * shift 80% of Colstrip 3 Aux load to the Colstrip 115kV MBL 83.5 "COLSTRP " 230. "c3" "R" Page 175 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 1: 07 HS Switching Sequences for - IV2_1 Cases Page 176 of 722 APPENDIX I – SWITCHING SEQUENCES 1_MTL-MAR230.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * Page 177 of 722 APPENDIX I – SWITCHING SEQUENCES 2_MAR-GFL230.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Marias to Great Falls 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Marias 230 kV FB 60.0 "MARIAS " 230 * * Clear bus fault at Marias 230 kV CFB 64.0 "MARIAS " 230 * * Trip Marias to Great Falls 230 kV Line DL 64.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 64.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * * Trip MATL PS to Cutbank 230 kV Line DL 124.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 124.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 124.0 "MATLN_&1" 230. "MARIAS " 230. "1 " Page 178 of 722 APPENDIX I – SWITCHING SEQUENCES 3_LGDN-CRNBRK500.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * * Apply bus fault at Langdon2 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon2 - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Note According to PeterM this action is already completed due to tripping the line. * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV * MLS 64 .0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 179 of 722 APPENDIX I – SWITCHING SEQUENCES 4_CRNBRK-SELK500.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-21 * * Cranbrook -- Selkirk 500 kV line Contingency with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Cranbrook - Selkirk 500 kV Line DL 64.0 "CBK500 " 500. "SEL500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 ** * Trip Langdon2 - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " Page 180 of 722 APPENDIX I – SWITCHING SEQUENCES DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.08 p.u. * then switch following shunts in the specified time until the voltage drops below 1.08 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 91.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 91.0 "CBK T7 " 12.6 "b0" "D" * * Switch in 12kV, 12 MVAR shunt reactors at 51364 MBS 109. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt reactors at 50838 MBS 109. "CBK T7 " 12.6 "b1" "R" * * Switch in 12kV, 75 MVAR shunt reactors at 51352 MBS 127. "CBK T2 " 12.6 "b0" "R" * ******************************************************* * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 181 of 722 APPENDIX I – SWITCHING SEQUENCES 5_ING-CUS500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Ingledow - Custer #1 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 240 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * Page 182 of 722 APPENDIX I – SWITCHING SEQUENCES 6_CUS-MNR500.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 183 of 722 APPENDIX I – SWITCHING SEQUENCES 7_ING-CUS12_500_RAS.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1410 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B4" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 80 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 50639 MCA G3, 450 MW TG 72.0 "MCA G3 " 16.0 "1 " * * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * * Shed unit at 50497 GMS G3 13.8 250 MW TG 72.0 "GMS G3 " 13.8 "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " Page 184 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * * Disconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B4" "D" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b2" "R" * Page 185 of 722 APPENDIX I – SWITCHING SEQUENCES 8_CUS-MNR12_500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1210 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B4" "R" * * required generation shedding 1272 MW, actual shedding is 1300 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 72.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 155 MW TG 72.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 155 MW TG 72.0 "SEV G3 " 13.8 "1 " * * Shed unit at 50637 MCA G1 16.0 350 MW TG 74.0 "MCA G1 " 16.0 "1 " * * Shed unit at 50640 MCA G4 16.0 450 MW TG 74.0 "MCA G4 " 16.0 "1 " * * Shed unit at 50496 GMS G2 13.8 250 MW TG 74.0 "GMS G2 " 13.8 "1 " Page 186 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 50497 GMS G3 13.8 250 MW TG 74.0 "GMS G3 " 13.8 "1 " * * Disconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B4" "D" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b2" "R" * Page 187 of 722 APPENDIX I – SWITCHING SEQUENCES 9_SEL-ACK500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Selkirk - Ashton Creek 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 265 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek 500 kV Line DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 52161 WAN G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * 3p reclosing, lead end SEL, Follow end ACK * Apply bus fault at Selkirk 500 kV FB 120. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "SEL500 " 500. * Page 188 of 722 APPENDIX I – SWITCHING SEQUENCES 10_SEL-VAS500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Selkirk - Vaseux Lake 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 310 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Vaseux Lake 500 kV Line DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 80 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Trip GFT-161 to OLI-161 (52227-52261, FortisBC 161 kV line 11W) DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * 3p reclosing, lead end SEL, Follow end VAS * Apply bus fault at Selkirk 500 kV FB 98.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 101. "SEL500 " 500. * Page 189 of 722 APPENDIX I – SWITCHING SEQUENCES 11_NIC-MDN500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nicola - Meridian 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Meridian 500 kV FB 60.0 "MDN500 " 500. * * Clear bus fault at Meridian 500 kV CFB 64.0 "MDN500 " 500. * * Trip Nicola - Meridian 500 kV Line DL 64.0 "MDN500 " 500. "NIC500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "C" 0.0 -1.225 * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * * 3p reclosing, lead end MDN, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 120. "MDN500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "MDN500 " 500. * Page 190 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1575 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 1575 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50771 KCL G3 13.8 120 MW TG 70.0 "KCL G3 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 155 MW TG 70.0 "SEV G2 " 13.8 "1 " Page 191 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 50768 SEV G3 13.8 155 MW TG 70.0 "SEV G3 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 80 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 51045 ALH G2 13.8 80 MW TG 70.0 "ALH G2 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * Page 192 of 722 APPENDIX I – SWITCHING SEQUENCES * Switch in 12kV, 12 MVAR shunt reactors at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt reactors at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * * Switch in 12kV, 75 MVAR shunt reactors at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b2" "R" * Page 193 of 722 APPENDIX I – SWITCHING SEQUENCES 13_NIC-ACK12_500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nicola - Ashton Creek #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1510 * * Apply bus fault at Ashton Creek 500 kV FB 60.0 "ACK500 " 500. * * Clear bus fault at Ashton Creek 500 kV CFB 64.0 "ACK500 " 500. * * Trip Nicola - Ashton Creek #1 and #2 500 kV Lines DL 64.0 "NIC500 " 500. "ACK500 " 500. "1 " DL 64.0 "NIC500 " 500. "ACK500 " 500. "2 " * * required generation shedding 1682 MW, actual shedding is 1510 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50771 KCL G3 13.8 120 MW TG 70.0 "KCL G3 " 13.8 "1 " * * Trip VNT138 - VVW138 138 kV Line DL 70.0 "VNT138 " 138. "VVW138 " 138. "1 " * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 155 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 155 MW TG 70.0 "SEV G3 " 13.8 "1 " * * Shed unit at 50644 REV G1 16.0 355 MW TG 72.0 "REV G1 " 16.0 "1 " Page 194 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip SAM138 - STO138 138 kV Line DL 72.0 "SAM138 " 138. "STO138 " 138. "1 " * * 3p reclosing, lead end ACK, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 150. "ACK500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 153. "ACK500 " 500. * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b2" "R" * Page 195 of 722 APPENDIX I – SWITCHING SEQUENCES 14_NIC-ING_NIC-MDN500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nicola - Ingledow and Nicola - Meridian 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1515 * * Apply bus fault at Nicola 500 kV FB 60.0 "NIC500 " 500. * * Clear bus fault at Nicola 500 kV CFB 64.0 "NIC500 " 500. * * Trip Nicola - Ingledow and Nicola - Meridian 500 kV Lines DL 64.0 "NIC500 " 500. "ING500 " 500. "1 " DL 64.0 "NIC500 " 500. "MDN500 " 500. "1 " * * Disconnect 245 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "D" * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * required generation shedding 1468 MW, actual shedding is 1480 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50639 MCA G3 16.0 450 MW TG 72.0 "MCA G3 " 16.0 "1 " * * Shed unit at 50640 MCA G4 16.0 450 MW TG 72.0 "MCA G4 " 16.0 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " Page 196 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Trip Nelway - Boundary 230 kV Line DL 72.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * * 3p reclosing, lead end MDN, Follow end NIC * 3p reclosing, lead end ING, Follow end NIC * Meridian - Nicola Rpu=0.002480 Xpu=0.016500 Bpu=0.0 * Ingledow - Nicola Rpu=0.002530 Xpu=0.018370 Bpu=0.0 (Gpu=7.36, Bpu=-53.4) * Apply bus fault at Meridian 500 kV through line impedance FB 120. "MDN500 " 500. .002480 .016500 * * Reinsert shunt at Ingledow with 1/line impedance MBS 120. "ING500 " 500. "FT" R * * Clear bus fault at Meridian 500 kV CFB 123. "MDN500 " 500. * * Disconnect shunt at Ingledow with 1/line impedance MBS 123. "ING500 " 500. "FT" D * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b2" "R" * Page 197 of 722 APPENDIX I – SWITCHING SEQUENCES 15_NEL-BND230_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 260 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * actual generation shedding is 260 MW * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 72.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 72.0 "BOUNDARY" 14.4 "2 " * Page 198 of 722 APPENDIX I – SWITCHING SEQUENCES 16_GENESE3.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Genessee Unit 3 250 MW * * CC cards for post-transient only * CC DRP 250 * * Apply bus fault at Genesee 500 kV FB 60.0 "GENESEE4" 500. * * Clear bus fault at Genesee 500 kV CFB 63.0 "GENESEE4" 500. * * Trip Genessee Unit 3 250 MW 54490 TG 63.0 "GENES 39" 20.5 "3 " * Page 199 of 722 APPENDIX I – SWITCHING SEQUENCES 17_LGD-JNT240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - Janet #1 240 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 240 kV Line DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * Page 200 of 722 APPENDIX I – SWITCHING SEQUENCES 18_SUN-BLT12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. * * Clear bus fault at Sundance 240 kV CFB 66.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 201 of 722 APPENDIX I – SWITCHING SEQUENCES 19_BLT-SRC12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 202 of 722 APPENDIX I – SWITCHING SEQUENCES 20_BLT-KPH12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Benalto - Keephills #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Keephills #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "03" * DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "90" * Page 203 of 722 APPENDIX I – SWITCHING SEQUENCES 21_JAN-RED12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. * * Clear bus fault at Janet 240 kV CFB 66.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 66.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 66.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 204 of 722 APPENDIX I – SWITCHING SEQUENCES 22_RED-ELR12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Red Deer - Ellerslie #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Red Deer 240 kV FB 60.0 "RED DEE4" 240. * * Clear bus fault at Red Deer 240 kV CFB 66.0 "RED DEE4" 240. * * Trip Red Deer - Ellerslie #1 and #2 240 kV Lines DL 66.0 "RED DEE4" 240. "ELLERSLI" 240. "10" * DL 66.0 "RED DEE4" 240. "GAETZ 4" 240. "14" DL 66.0 "GAETZ 4" 240. "BIGSTON4" 240. "14" DL 66.0 "BIGSTON4" 240. "ELLERSLI" 240. "14" * Page 205 of 722 APPENDIX I – SWITCHING SEQUENCES 23_LGD-JNT12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 66.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 206 of 722 APPENDIX I – SWITCHING SEQUENCES 24_LGD-LTH12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - N. Lethbridge #1 and #2 240 kV Lines * Pre-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon #1 and #2 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "N LETHB4" 240. "MILO 2 " 240. "23" * Page 207 of 722 APPENDIX I – SWITCHING SEQUENCES 25_LGD-LTH_LGD-MTL_240.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - N. Lethbridge and Langdon - MATL AB 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon and N. Lethbridge - MATL AB 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "MILO 2 " 240. "MATL_AB " 240. "23" * Page 208 of 722 APPENDIX I – SWITCHING SEQUENCES 26_LGD-LTH_MTL-LTH_240.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at N. Lethbridge 240 kV FB 60.0 "N LETHB4" 240. * * Clear bus fault at N. Lethbridge 240 kV CFB 66.0 "N LETHB4" 240. * * Trip Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "N LETHB4" 240. "MATL_AB " 240. "23" * Page 209 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 1: 07 HS Switching Sequences for - IV2_2 Cases Page 210 of 722 APPENDIX I – SWITCHING SEQUENCES 1_MTL-MAR230.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * Page 211 of 722 APPENDIX I – SWITCHING SEQUENCES 2_MAR-GFL230.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Marias to Great Falls 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Marias 230 kV FB 60.0 "MARIAS " 230 * * Clear bus fault at Marias 230 kV CFB 64.0 "MARIAS " 230 * * Trip Marias to Great Falls 230 kV Line DL 64.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 64.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * * Trip MATL PS to Cutbank 230 kV Line DL 124.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 124.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 124.0 "MATLN_&1" 230. "MARIAS " 230. "1 " Page 212 of 722 APPENDIX I – SWITCHING SEQUENCES 3_LGDN-CRNBRK500.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * * Apply bus fault at Langdon2 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon2 - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Note According to PeterM this action is already completed due to tripping the line. * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV * MLS 64 .0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * * Trip Nelway - Boundry 230 kV Line DL 70.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Shed unit at 46405 BDY G1, 130 MW TG 76.0 "BOUNDARY " 14.4 "1 " * * Shed unit at 46405 BDY G2, 130 MW TG 76.0 "BOUNDARY " 14.4 "2 " * Page 213 of 722 APPENDIX I – SWITCHING SEQUENCES * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 214 of 722 APPENDIX I – SWITCHING SEQUENCES 4_CRNBRK-SELk500.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Cranbrook -- Selkirk 500 kV line Contingency with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Cranbrook - Selkirk 500 kV Line DL 64.0 "CBK500 " 500. "SEL500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 ** * Trip Langdon2 - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * Trip Nelway - Boundry 230 kV Line DL 70.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Shed unit at 46405 BDY G1, 130 MW TG 76.0 "BOUNDARY " 14.4 "1 " * Page 215 of 722 APPENDIX I – SWITCHING SEQUENCES * Shed unit at 46405 BDY G2, 130 MW TG 76.0 "BOUNDARY " 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.08 p.u. * then switch following shunts in the specified time until the voltage drops below 1.08 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 91.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 91.0 "CBK T7 " 12.6 "b0" "D" * * Switch in 12kV, 12 MVAR shunt Reactor at 51364 MBS 109. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt Reactor at 50838 MBS 109. "CBK T7 " 12.6 "b1" "R" * * Switch in 12kV, 75 MVAR shunt Reactor at 51352 MBS 127. "CBK T2 " 12.6 "b0" "R" * ******************************************************* * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 216 of 722 APPENDIX I – SWITCHING SEQUENCES 5_ING-CUS500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-22 * * Ingledow - Custer #1 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " * Page 217 of 722 APPENDIX I – SWITCHING SEQUENCES 6_CUS-MNR500.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 218 of 722 APPENDIX I – SWITCHING SEQUENCES 7_ING-CUS12_500_RAS.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 219 of 722 APPENDIX I – SWITCHING SEQUENCES 8_CUS-MNR12_500_RAS.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1300 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 66.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 66.0 "CUSTER W" 500. "ING500 " 500. "2 " * * * Trip Nelway - Boundary 230 kV Line DL 72.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1272 MW, actual shedding is 1300 MW * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 78.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 78.0 "BOUNDARY" 14.4 "2 " * Page 220 of 722 APPENDIX I – SWITCHING SEQUENCES 9_SEL-ACK500_RAS.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Selkirk - Ashton Creek 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek 500 kV Line DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Shed unit at 50769 KCL G1 13.8 110 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 150 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 52163 WAN-G3 14.4 20 MW TG 72.0 "WAN-G3 " 14.4 "3 " * * 3p reclosing, lead end SEL, Follow end ACK * Apply bus fault at Selkirk 500 kV FB 120. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "SEL500 " 500. * Page 221 of 722 APPENDIX I – SWITCHING SEQUENCES 10_SEL-VAS500_RAS.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Selkirk - Vaseux Lake 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Vaseux Lake 500 kV Line DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Shed unit at 50769 KCL G1 13.8 110 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 100 MW TG 70.0 "SEV G3 " 13.8 "1 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip GFT-161 to OLI-161 (52227-52261, FortisBC 161 kV line 11W) DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * 3p reclosing, lead end SEL, Follow end VAS * Apply bus fault at Selkirk 500 kV FB 98.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 101. "SEL500 " 500. * Page 222 of 722 APPENDIX I – SWITCHING SEQUENCES 11_NIC-MDN500_RAS.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Nicola - Meridian 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Meridian 500 kV FB 60.0 "MDN500 " 500. * * Clear bus fault at Meridian 500 kV CFB 64.0 "MDN500 " 500. * * Trip Nicola - Meridian 500 kV Line DL 64.0 "MDN500 " 500. "NIC500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "C" 0.0 -1.225 * * 3p reclosing, lead end MDN, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 120. "MDN500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "MDN500 " 500. * Page 223 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS.swt RUN * * Last updated 11/10/2006 by TCL * Path 1 Dynamics IV-22 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 675 MW * Shed unit at 50769 KCL G1 13.8 110 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 110 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 150 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 150 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 100 MW TG 70.0 "SEV G3 " 13.8 "1 " Page 224 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 51044 ALH G1 13.8 75 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * * Switch in 12kV, 12 MVAR shunt reactors at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt reactors at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * Page 225 of 722 APPENDIX I – SWITCHING SEQUENCES * Switch in 12kV, 75 MVAR shunt reactors at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* Page 226 of 722 APPENDIX I – SWITCHING SEQUENCES 13_NIC-ACK12_500_RAS.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Nicola - Ashton Creek #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1700 * * Apply bus fault at Ashton Creek 500 kV FB 60.0 "ACK500 " 500. * * Clear bus fault at Ashton Creek 500 kV CFB 64.0 "ACK500 " 500. * * Trip Nicola - Ashton Creek #1 and #2 500 kV Lines DL 64.0 "NIC500 " 500. "ACK500 " 500. "1 " DL 64.0 "NIC500 " 500. "ACK500 " 500. "2 " * * required generation shedding 1682 MW, actual shedding is 1700 MW * Shed unit at 50769 KCL G1 13.8 110 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 150 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Trip VNT138 - VVW138 (50654-50655) 138 kV line DL 72.0 "VNT138 " 138. "VVW138 " 138. "1 " * * Shed unit at 50644 REV G1 16.0 200 MW TG 72.0 "REV G1 " 16.0 "1 " * * Shed unit at 52163 WAN-G3 14.4 20 MW TG 72.0 "WAN-G3 " 14.4 "3 " * * Trip SAM138 - STO138 138 kV Line DL 72.0 "SAM138 " 138. "STO138 " 138. "1 " * * 3p reclosing, lead end ACK, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 150. "ACK500 " 500. * * Clear bus fault at Selkirk 500 kV Page 227 of 722 APPENDIX I – SWITCHING SEQUENCES CFB 153. "ACK500 " 500. Page 228 of 722 APPENDIX I – SWITCHING SEQUENCES 14_NIC-ING_NIC-MDN500_RAS.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Nicola - Ingledow and Nicola - Meridian 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1620 * * Apply bus fault at Nicola 500 kV FB 60.0 "NIC500 " 500. * * Clear bus fault at Nicola 500 kV CFB 64.0 "NIC500 " 500. * * Trip Nicola - Ingledow and Nicola - Meridian 500 kV Lines DL 64.0 "NIC500 " 500. "ING500 " 500. "1 " DL 64.0 "NIC500 " 500. "MDN500 " 500. "1 " * * Disconnect 245 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "D" * * * 3p reclosing, lead end MDN, Follow end NIC * 3p reclosing, lead end ING, Follow end NIC * Meridian - Nicola Rpu=0.002480 Xpu=0.016500 Bpu=0.0 * Ingledow - Nicola Rpu=0.002530 Xpu=0.018370 Bpu=0.0 (Gpu=7.36, Bpu=-53.4) * Apply bus fault at Meridian 500 kV through line impedance FB 120. "MDN500 " 500. .002480 .016500 * * Reinsert shunt at Ingledow with 1/line impedance MBS 120. "ING500 " 500. "FT" R * * Clear bus fault at Meridian 500 kV CFB 123. "MDN500 " 500. * * Disconnect shunt at Ingledow with 1/line impedance MBS 123. "ING500 " 500. "FT" D Page 229 of 722 APPENDIX I – SWITCHING SEQUENCES 15_NEL-BND230_RAS.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * actual generation shedding is 260 MW * Shed unit 1 at 46405 BOUNDRY2 14.40 164 MW TG 72.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDRY2 14.40 130 MW TG 72.0 "BOUNDARY" 14.4 "2 " * Page 230 of 722 APPENDIX I – SWITCHING SEQUENCES 16_GENESE3.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Genessee Unit 3 250 MW * * CC cards for post-transient only * CC DRP 250 * * Apply bus fault at Genesee 500 kV FB 60.0 "GENESEE4" 500. * * Clear bus fault at Genesee 500 kV CFB 63.0 "GENESEE4" 500. * * Trip Genessee Unit 3 250 MW 54490 TG 63.0 "GENES 39" 20.5 "3 " * Page 231 of 722 APPENDIX I – SWITCHING SEQUENCES 17_LGD-JNT240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Langdon - Janet #1 240 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 240 kV Line DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * Page 232 of 722 APPENDIX I – SWITCHING SEQUENCES 18_SUN-BLT12_240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. * * Clear bus fault at Sundance 240 kV CFB 66.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 233 of 722 APPENDIX I – SWITCHING SEQUENCES 19_BLT-SRC12_240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 234 of 722 APPENDIX I – SWITCHING SEQUENCES 20_BLT-KPH12_240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Benalto - Keephills #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Keephills #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "03" * DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "90" * Page 235 of 722 APPENDIX I – SWITCHING SEQUENCES 21_JAN-RED12_240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. * * Clear bus fault at Janet 240 kV CFB 66.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 66.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 66.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 236 of 722 APPENDIX I – SWITCHING SEQUENCES 22_RED-ELR12_240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Red Deer - Ellerslie #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Red Deer 240 kV FB 60.0 "RED DEE4" 240. * * Clear bus fault at Red Deer 240 kV CFB 66.0 "RED DEE4" 240. * * Trip Red Deer - Ellerslie #1 and #2 240 kV Lines DL 66.0 "RED DEE4" 240. "ELLERSLI" 240. "10" * DL 66.0 "RED DEE4" 240. "GAETZ 4" 240. "14" DL 66.0 "GAETZ 4" 240. "BIGSTON4" 240. "14" DL 66.0 "BIGSTON4" 240. "ELLERSLI" 240. "14" * Page 237 of 722 APPENDIX I – SWITCHING SEQUENCES 23_LGD-JNT12_240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 66.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 238 of 722 APPENDIX I – SWITCHING SEQUENCES 24_LGD-LTH12_240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Langdon - N. Lethbridge #1 and #2 240 kV Lines * Pre-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon #1 and #2 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "N LETHB4" 240. "MILO 2 " 240. "23" * Page 239 of 722 APPENDIX I – SWITCHING SEQUENCES 25_LGD-LTH_LGD-MTL_240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Langdon - N. Lethbridge and Langdon - MATL AB 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon and N. Lethbridge - MATL AB 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "MILO 2 " 240. "MATL_AB " 240. "23" * Page 240 of 722 APPENDIX I – SWITCHING SEQUENCES 26_LGD-LTH_MTL-LTH_240.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-22 * * Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at N. Lethbridge 240 kV FB 60.0 "N LETHB4" 240. * * Clear bus fault at N. Lethbridge 240 kV CFB 66.0 "N LETHB4" 240. * * Trip Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "N LETHB4" 240. "MATL_AB " 240. "23" * Page 241 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 1: 07 HS Switching Sequences for - IV2_3 Cases Page 242 of 722 APPENDIX I – SWITCHING SEQUENCES 1_MTL-MAR230.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * Page 243 of 722 APPENDIX I – SWITCHING SEQUENCES 2_MAR-GFL230.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Marias to Great Falls 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Marias 230 kV FB 60.0 "MARIAS " 230 * * Clear bus fault at Marias 230 kV CFB 64.0 "MARIAS " 230 * * Trip Marias to Great Falls 230 kV Line DL 64.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 64.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * * Trip MATL PS to Cutbank 230 kV Line DL 124.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 124.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 124.0 "MATLN_&1" 230. "MARIAS " 230. "1 " Page 244 of 722 APPENDIX I – SWITCHING SEQUENCES 3_LGDN-CRNBRK500.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * * Apply bus fault at Langdon2 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon2 - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Note According to PeterM this action is already completed due to tripping the line. * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV * MLS 64 .0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 180 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * Page 245 of 722 APPENDIX I – SWITCHING SEQUENCES 4_CRNBRK-SELk500.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Cranbrook -- Selkirk 500 kV line Contingency with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Cranbrook - Selkirk 500 kV Line DL 64.0 "CBK500 " 500. "SEL500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 ** * Trip Langdon2 - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 180 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW Page 246 of 722 APPENDIX I – SWITCHING SEQUENCES TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.08 p.u. * then switch following shunts in the specified time until the voltage drops below 1.08 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 91.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 91.0 "CBK T7 " 12.6 "b0" "D" * * Switch in 12kV, 12 MVAR shunt Reactor at 51364 MBS 109. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt Reactor at 50838 MBS 109. "CBK T7 " 12.6 "b1" "R" * * Switch in 12kV, 75 MVAR shunt Reactor at 51352 MBS 127. "CBK T2 " 12.6 "b0" "R" * ******************************************************* * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 247 of 722 APPENDIX I – SWITCHING SEQUENCES 5_ING-CUS500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Ingledow - Custer #1 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" Page 248 of 722 APPENDIX I – SWITCHING SEQUENCES 6_CUS-MNR500.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 249 of 722 APPENDIX I – SWITCHING SEQUENCES 7_ING-CUS12_500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B4" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50495 GMS G1 13.8 250 MW TG 72.0 "GMS G1 " 13.8 "1 " * * Shed unit at 50637 MCA G1, 435 MW TG 72.0 "MCA G1 " 16.0 "1 " * * Shed unit at 50640 MCA G4, 450 MW TG 72.0 "MCA G4 " 16.0 "1 " * * Shed unit at 50644 REV G1 16.0 500 MW TG 72.0 "REV G1 " 16.0 "1 " * * Shed unit at 50645 REV G2 16.0 500 MW TG 72.0 "REV G2 " 16.0 "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " Page 250 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1 " 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * * Disconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B4" "D" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 960. "ACK500 " 500. "b2" "R" * Page 251 of 722 APPENDIX I – SWITCHING SEQUENCES 8_CUS-MNR12_500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1300 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B4" "R" * * required generation shedding 1272 MW, actual shedding is 1300 MW * Shed unit at 50639 MCA G3 16.0 450 MW TG 72.0 "MCA G3 " 16.0 "1 " * * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * * Shed unit at 50497 GMS G3 13.8 250 MW TG 72.0 "GMS G3 " 13.8 "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Disconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B4" "D" * Page 252 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 960. "ACK500 " 500. "b2" "R" * Page 253 of 722 APPENDIX I – SWITCHING SEQUENCES 9_SEL-ACK500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Selkirk - Ashton Creek 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek 500 kV Line DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * 3p reclosing, lead end SEL, Follow end ACK * Apply bus fault at Selkirk 500 kV FB 120. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "SEL500 " 500. * Page 254 of 722 APPENDIX I – SWITCHING SEQUENCES 10_SEL-VAS500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Selkirk - Vaseux Lake 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Vaseux Lake 500 kV Line DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * * 3p reclosing, lead end SEL, Follow end VAS * Apply bus fault at Selkirk 500 kV FB 98.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 101. "SEL500 " 500. * Page 255 of 722 APPENDIX I – SWITCHING SEQUENCES 11_NIC-MDN500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Nicola - Meridian 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Meridian 500 kV FB 60.0 "MDN500 " 500. * * Clear bus fault at Meridian 500 kV CFB 64.0 "MDN500 " 500. * * Trip Nicola - Meridian 500 kV Line DL 64.0 "MDN500 " 500. "NIC500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "C" 0.0 -1.225 * * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * * 3p reclosing, lead end MDN, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 120. "MDN500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "MDN500 " 500. * Page 256 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * (Required BC's genshedding amount 729 MW, actual shedding 730 MW) * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 180 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 75 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 51045 ALH G2 13.8 75 MW TG 70.0 "ALH G2 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " Page 257 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * * Switch off 12kV, 12 MVAR shunt capacitor at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch off 12kV, 12 MVAR shunt capacitor at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * * Switch off 12kV, 75 MVAR shunt capacitor at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" Page 258 of 722 APPENDIX I – SWITCHING SEQUENCES * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 960. "ACK500 " 500. "b2" "R" * Page 259 of 722 APPENDIX I – SWITCHING SEQUENCES 13_NIC-ACK12_500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Nicola - Ashton Creek #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1700 * * Apply bus fault at Ashton Creek 500 kV FB 60.0 "ACK500 " 500. * * Clear bus fault at Ashton Creek 500 kV CFB 64.0 "ACK500 " 500. * * Trip Nicola - Ashton Creek #1 and #2 500 kV Lines DL 64.0 "NIC500 " 500. "ACK500 " 500. "1 " DL 64.0 "NIC500 " 500. "ACK500 " 500. "2 " * * required generation shedding 1682 MW, actual shedding is 1700 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50771 KCL G3 13.8 120 MW TG 70.0 "KCL G3 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 75 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Trip VNT138 - VVW138 138 kV Line DL 70.0 "VNT138 " 138. "VVW138 " 138. "1 " * * Shed unit at 50644 REV G1 16.0 500 MW TG 72.0 "REV G1 " 16.0 "1 " * * Shed unit at 50644 REV G2 16.0 500 MW TG 72.0 "REV G2 " 16.0 "1 " Page 260 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Trip SAM138 - STO138 138 kV Line DL 72.0 "SAM138 " 138. "STO138 " 138. "1 " * * 3p reclosing, lead end ACK, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 150. "ACK500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 153. "ACK500 " 500. * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 960. "ACK500 " 500. "b2" "R" * Page 261 of 722 APPENDIX I – SWITCHING SEQUENCES 14_NIC-ING_NIC-MDN500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Nicola - Ingledow and Nicola - Meridian 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1620 * * Apply bus fault at Nicola 500 kV FB 60.0 "NIC500 " 500. * * Clear bus fault at Nicola 500 kV CFB 64.0 "NIC500 " 500. * * Trip Nicola - Ingledow and Nicola - Meridian 500 kV Lines DL 64.0 "NIC500 " 500. "ING500 " 500. "1 " DL 64.0 "NIC500 " 500. "MDN500 " 500. "1 " * * Disconnect 245 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "D" * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * (Required genshedding 1627 MW at REV/KCL/ALH/SEV/WAN, actual shedding 1630 MW) * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50639 MCA G3 16.0 450 MW TG 72.0 "MCA G3 " 16.0 "1 " * * Shed unit at 50640 MCA G4 16.0 450 MW TG 72.0 "MCA G4 " 16.0 "1 " * * Shed unit at 50644 REV G1 16.0 500 MW TG 72.0 "REV G1 " 16.0 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" Page 262 of 722 APPENDIX I – SWITCHING SEQUENCES MBL 104. "GMS138 " 138. "B2" "D" * * 3p reclosing, lead end MDN, Follow end NIC * 3p reclosing, lead end ING, Follow end NIC * Meridian - Nicola Rpu=0.002480 Xpu=0.016500 Bpu=0.0 * Ingledow - Nicola Rpu=0.002530 Xpu=0.018370 Bpu=0.0 (Gpu=7.36, Bpu=-53.4) * Apply bus fault at Meridian 500 kV through line impedance FB 120. "MDN500 " 500. .002480 .016500 * * Reinsert shunt at Ingledow with 1/line impedance MBS 120. "ING500 " 500. "FT" R * * Clear bus fault at Meridian 500 kV CFB 123. "MDN500 " 500. * * Disconnect shunt at Ingledow with 1/line impedance MBS 123. "ING500 " 500. "FT" D * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 960. "ACK500 " 500. "b2" "R" * Page 263 of 722 APPENDIX I – SWITCHING SEQUENCES 15_NEL-BND230_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * actual generation shedding is 260 MW * Shed unit 1 at 46405 BOUNDRY2 14.40 164 MW TG 72.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDRY2 14.40 130 MW TG 72.0 "BOUNDARY" 14.4 "2 " * Page 264 of 722 APPENDIX I – SWITCHING SEQUENCES 16_GENESE3.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Genessee Unit 3 250 MW * * CC cards for post-transient only * CC DRP 250 * * Apply bus fault at Genesee 500 kV FB 60.0 "GENESEE4" 500. * * Clear bus fault at Genesee 500 kV CFB 63.0 "GENESEE4" 500. * * Trip Genessee Unit 3 250 MW 54490 TG 63.0 "GENES 39" 20.5 "3 " * Page 265 of 722 APPENDIX I – SWITCHING SEQUENCES 17_LGD-JNT240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Janet #1 240 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 240 kV Line DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * Page 266 of 722 APPENDIX I – SWITCHING SEQUENCES 18_SUN-BLT12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. * * Clear bus fault at Sundance 240 kV CFB 66.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 267 of 722 APPENDIX I – SWITCHING SEQUENCES 19_BLT-SRC12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 268 of 722 APPENDIX I – SWITCHING SEQUENCES 20_BLT-KPH12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Benalto - Keephills #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Keephills #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "03" * DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "90" * Page 269 of 722 APPENDIX I – SWITCHING SEQUENCES 21_JAN-RED12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. * * Clear bus fault at Janet 240 kV CFB 66.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 66.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 66.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 270 of 722 APPENDIX I – SWITCHING SEQUENCES 22_RED-ELR12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Red Deer - Ellerslie #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Red Deer 240 kV FB 60.0 "RED DEE4" 240. * * Clear bus fault at Red Deer 240 kV CFB 66.0 "RED DEE4" 240. * * Trip Red Deer - Ellerslie #1 and #2 240 kV Lines DL 66.0 "RED DEE4" 240. "ELLERSLI" 240. "10" * DL 66.0 "RED DEE4" 240. "GAETZ 4" 240. "14" DL 66.0 "GAETZ 4" 240. "BIGSTON4" 240. "14" DL 66.0 "BIGSTON4" 240. "ELLERSLI" 240. "14" * Page 271 of 722 APPENDIX I – SWITCHING SEQUENCES 23_LGD-JNT12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 66.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 272 of 722 APPENDIX I – SWITCHING SEQUENCES 24_LGD-LTH12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - N. Lethbridge #1 and #2 240 kV Lines * Pre-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon #1 and #2 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "N LETHB4" 240. "MILO 2 " 240. "23" * Page 273 of 722 APPENDIX I – SWITCHING SEQUENCES 25_LGD-LTH_LGD-MTL_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - N. Lethbridge and Langdon - MATL AB 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon and N. Lethbridge - MATL AB 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "MILO 2 " 240. "MATL_AB " 240. "23" * Page 274 of 722 APPENDIX I – SWITCHING SEQUENCES 26_LGD-LTH_MTL-LTH_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at N. Lethbridge 240 kV FB 60.0 "N LETHB4" 240. * * Clear bus fault at N. Lethbridge 240 kV CFB 66.0 "N LETHB4" 240. * * Trip Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "N LETHB4" 240. "MATL_AB " 240. "23" * Page 275 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 1: 07 HS Switching Sequences for - IV2_4 Cases Page 276 of 722 APPENDIX I – SWITCHING SEQUENCES 1_MTL-MAR230.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * Page 277 of 722 APPENDIX I – SWITCHING SEQUENCES 2_MAR-GFL230.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Marias to Great Falls 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Marias 230 kV FB 60.0 "MARIAS " 230 * * Clear bus fault at Marias 230 kV CFB 64.0 "MARIAS " 230 * * Trip Marias to Great Falls 230 kV Line DL 64.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 64.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * * Trip MATL PS to Cutbank 230 kV Line DL 124.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 124.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 124.0 "MATLN_&1" 230. "MARIAS " 230. "1 " Page 278 of 722 APPENDIX I – SWITCHING SEQUENCES 3_LGDN-CRNBRK500.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * * Apply bus fault at Langdon2 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon2 - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Note According to PeterM this action is already completed due to tripping the line. * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV * MLS 64 .0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 Page 279 of 722 APPENDIX I – SWITCHING SEQUENCES 4_CRNBRK-SELk500.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Cranbrook -- Selkirk 500 kV line Contingency with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Cranbrook - Selkirk 500 kV Line DL 64.0 "CBK500 " 500. "SEL500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 ** * Trip Langdon2 - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.08 p.u. * then switch following shunts in the specified time until the voltage drops below 1.08 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 91.0 "CBK T6 " 12.6 "b0" "D" Page 280 of 722 APPENDIX I – SWITCHING SEQUENCES * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 91.0 "CBK T7 " 12.6 "b0" "D" * * Switch in 12kV, 12 MVAR shunt Reactor at 51364 MBS 109. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt Reactor at 50838 MBS 109. "CBK T7 " 12.6 "b1" "R" * * Switch in 12kV, 75 MVAR shunt Reactor at 51352 MBS 127. "CBK T2 " 12.6 "b0" "R" * ******************************************************* * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 281 of 722 APPENDIX I – SWITCHING SEQUENCES 5_ING-CUS500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Ingledow - Custer #1 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " Page 282 of 722 APPENDIX I – SWITCHING SEQUENCES 6_CUS-MNR500.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 283 of 722 APPENDIX I – SWITCHING SEQUENCES 7_ING-CUS12_500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 284 of 722 APPENDIX I – SWITCHING SEQUENCES 8_CUS-MNR12_500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1300 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 66.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 66.0 "CUSTER W" 500. "ING500 " 500. "2 " * * * Trip Nelway - Boundary 230 kV Line DL 72.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1272 MW, actual shedding is 1300 MW * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 78.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 78.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. Page 285 of 722 APPENDIX I – SWITCHING SEQUENCES * Page 286 of 722 APPENDIX I – SWITCHING SEQUENCES 9_SEL-ACK500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Selkirk - Ashton Creek 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek 500 kV Line DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * 3p reclosing, lead end SEL, Follow end ACK * Apply bus fault at Selkirk 500 kV FB 120. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "SEL500 " 500. * Page 287 of 722 APPENDIX I – SWITCHING SEQUENCES 10_SEL-VAS500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Selkirk - Vaseux Lake 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Vaseux Lake 500 kV Line DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * 3p reclosing, lead end SEL, Follow end VAS * Apply bus fault at Selkirk 500 kV FB 98.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 101. "SEL500 " 500. * Page 288 of 722 APPENDIX I – SWITCHING SEQUENCES 11_NIC-MDN500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Nicola - Meridian 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Meridian 500 kV FB 60.0 "MDN500 " 500. * * Clear bus fault at Meridian 500 kV CFB 64.0 "MDN500 " 500. * * Trip Nicola - Meridian 500 kV Line DL 64.0 "MDN500 " 500. "NIC500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "C" 0.0 -1.225 * * 3p reclosing, lead end MDN, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 120. "MDN500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "MDN500 " 500. * Page 289 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 815 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * (Required BC's genshedding amount 413 MW, actual shedding 420 MW) * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 150 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 150 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " Page 290 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * * Switch off 12kV, 12 MVAR shunt capacitor at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch off 12kV, 12 MVAR shunt capacitor at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * * Switch off 12kV, 75 MVAR shunt capacitor at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* Page 291 of 722 APPENDIX I – SWITCHING SEQUENCES 13_NIC-ACK12_500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Nicola - Ashton Creek #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1700 * * Apply bus fault at Ashton Creek 500 kV FB 60.0 "ACK500 " 500. * * Clear bus fault at Ashton Creek 500 kV CFB 64.0 "ACK500 " 500. * * Trip Nicola - Ashton Creek #1 and #2 500 kV Lines DL 64.0 "NIC500 " 500. "ACK500 " 500. "1 " DL 64.0 "NIC500 " 500. "ACK500 " 500. "2 " * * Trip VNT138 - VVW138 (50654-50655) 138 kV line DL 70.0 "VNT138 " 138. "VVW138 " 138. "1 " * * Trip SAM138 - STO138 138 kV Line DL 72.0 "SAM138 " 138. "STO138 " 138. "1 " * * 3p reclosing, lead end ACK, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 150. "ACK500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 153. "ACK500 " 500. Page 292 of 722 APPENDIX I – SWITCHING SEQUENCES 14_NIC-ING_NIC-MDN500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Nicola - Ingledow and Nicola - Meridian 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1620 * * Apply bus fault at Nicola 500 kV FB 60.0 "NIC500 " 500. * * Clear bus fault at Nicola 500 kV CFB 64.0 "NIC500 " 500. * * Trip Nicola - Ingledow and Nicola - Meridian 500 kV Lines DL 64.0 "NIC500 " 500. "ING500 " 500. "1 " DL 64.0 "NIC500 " 500. "MDN500 " 500. "1 " * * Disconnect 245 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "D" * * * 3p reclosing, lead end MDN, Follow end NIC * 3p reclosing, lead end ING, Follow end NIC * Meridian - Nicola Rpu=0.002480 Xpu=0.016500 Bpu=0.0 * Ingledow - Nicola Rpu=0.002530 Xpu=0.018370 Bpu=0.0 (Gpu=7.36, Bpu=-53.4) * Apply bus fault at Meridian 500 kV through line impedance FB 120. "MDN500 " 500. .002480 .016500 * * Reinsert shunt at Ingledow with 1/line impedance MBS 120. "ING500 " 500. "FT" R * * Clear bus fault at Meridian 500 kV CFB 123. "MDN500 " 500. * * Disconnect shunt at Ingledow with 1/line impedance MBS 123. "ING500 " 500. "FT" D Page 293 of 722 APPENDIX I – SWITCHING SEQUENCES 15_NEL-BND230_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * actual generation shedding is 260 MW * Shed unit 1 at 46405 BOUNDRY2 14.40 164 MW TG 72.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDRY2 14.40 130 MW TG 72.0 "BOUNDARY" 14.4 "2 " * Page 294 of 722 APPENDIX I – SWITCHING SEQUENCES 16_GENESE3.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Genessee Unit 3 250 MW * * CC cards for post-transient only * CC DRP 250 * * Apply bus fault at Genesee 500 kV FB 60.0 "GENESEE4" 500. * * Clear bus fault at Genesee 500 kV CFB 63.0 "GENESEE4" 500. * * Trip Genessee Unit 3 250 MW 54490 TG 64.0 "GENES 39" 20.5 "3 " * Page 295 of 722 APPENDIX I – SWITCHING SEQUENCES 17_LGD-JNT240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Langdon - Janet #1 240 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 240 kV Line DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * Page 296 of 722 APPENDIX I – SWITCHING SEQUENCES 18_SUN-BLT12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. * * Clear bus fault at Sundance 240 kV CFB 66.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 297 of 722 APPENDIX I – SWITCHING SEQUENCES 19_BLT-SRC12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 298 of 722 APPENDIX I – SWITCHING SEQUENCES 20_BLT-KPH12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Benalto - Keephills #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Keephills #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "03" * DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "90" * Page 299 of 722 APPENDIX I – SWITCHING SEQUENCES Page 300 of 722 APPENDIX I – SWITCHING SEQUENCES 21_JAN-RED12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. * * Clear bus fault at Janet 240 kV CFB 66.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 66.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 66.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 301 of 722 APPENDIX I – SWITCHING SEQUENCES 22_RED-ELR12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Red Deer - Ellerslie #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Red Deer 240 kV FB 60.0 "RED DEE4" 240. * * Clear bus fault at Red Deer 240 kV CFB 66.0 "RED DEE4" 240. * * Trip Red Deer - Ellerslie #1 and #2 240 kV Lines DL 66.0 "RED DEE4" 240. "ELLERSLI" 240. "10" * DL 66.0 "RED DEE4" 240. "GAETZ 4" 240. "14" DL 66.0 "GAETZ 4" 240. "BIGSTON4" 240. "14" DL 66.0 "BIGSTON4" 240. "ELLERSLI" 240. "14" * Page 302 of 722 APPENDIX I – SWITCHING SEQUENCES 23_LGD-JNT12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 66.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 303 of 722 APPENDIX I – SWITCHING SEQUENCES 24_LGD-LTH12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Langdon - N. Lethbridge #1 and #2 240 kV Lines * Pre-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon #1 and #2 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "N LETHB4" 240. "MILO 2 " 240. "23" * Page 304 of 722 APPENDIX I – SWITCHING SEQUENCES 25_LGD-LTH_LGD-MTL_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Langdon - N. Lethbridge and Langdon - MATL AB 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon and N. Lethbridge - MATL AB 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "MILO 2 " 240. "MATL_AB " 240. "23" * Page 305 of 722 APPENDIX I – SWITCHING SEQUENCES 26_LGD-LTH_MTL-LTH_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-24 * * Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at N. Lethbridge 240 kV FB 60.0 "N LETHB4" 240. * * Clear bus fault at N. Lethbridge 240 kV CFB 66.0 "N LETHB4" 240. * * Trip Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "N LETHB4" 240. "MATL_AB " 240. "23" * Page 306 of 722 APPENDIX I – SWITCHING SEQUENCES ALBERTA WIND SENSITIVITY ANALYSIS 07 HS CASES: 1 – 4 SWITCHING SEQUENCES Page 307 of 722 APPENDIX I – SWITCHING SEQUENCES 1_MTL-MAR230.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " * * Remove bus, causing divergence problems. CC DB 124.0 "MARIAS " 230. * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * Page 308 of 722 APPENDIX I – SWITCHING SEQUENCES 2_MAR-GFL230.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Marias to Great Falls 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Marias 230 kV FB 60.0 "MARIAS " 230 * * Clear bus fault at Marias 230 kV CFB 64.0 "MARIAS " 230 * * Trip Marias to Great Falls 230 kV Line DL 64.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 64.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * * Remove bus, causing divergence problems. CC DB 124.0 "MARIAS " 230. * * Trip MATL PS to Cutbank 230 kV Line DL 124.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 124.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 124.0 "MATLN_&1" 230. "MARIAS " 230. "1 " Page 309 of 722 APPENDIX I – SWITCHING SEQUENCES 3_LGDN-CRNBRK500.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * * Apply bus fault at Langdon2 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon2 - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Note According to PeterM this action is already completed due to tripping the line. * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV * MLS 64 .0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 310 of 722 APPENDIX I – SWITCHING SEQUENCES 4_CRNBRK-SELK500.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-21 * * Cranbrook -- Selkirk 500 kV line Contingency with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Cranbrook - Selkirk 500 kV Line DL 64.0 "CBK500 " 500. "SEL500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 ** * Trip Langdon2 - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " Page 311 of 722 APPENDIX I – SWITCHING SEQUENCES DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.08 p.u. * then switch following shunts in the specified time until the voltage drops below 1.08 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 91.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 91.0 "CBK T7 " 12.6 "b0" "D" * * Switch in 12kV, 12 MVAR shunt reactors at 51364 MBS 109. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt reactors at 50838 MBS 109. "CBK T7 " 12.6 "b1" "R" * * Switch in 12kV, 75 MVAR shunt reactors at 51352 MBS 127. "CBK T2 " 12.6 "b0" "R" * ******************************************************* * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 312 of 722 APPENDIX I – SWITCHING SEQUENCES 5_ING-CUS500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Ingledow - Custer #1 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 240 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * Page 313 of 722 APPENDIX I – SWITCHING SEQUENCES 6_CUS-MNR500.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 314 of 722 APPENDIX I – SWITCHING SEQUENCES 7_ING-CUS12_500_RAS.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1410 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B4" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 80 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 50639 MCA G3, 450 MW TG 72.0 "MCA G3 " 16.0 "1 " * * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * * Shed unit at 50497 GMS G3 13.8 250 MW TG 72.0 "GMS G3 " 13.8 "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " Page 315 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * * Disconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B4" "D" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b2" "R" * Page 316 of 722 APPENDIX I – SWITCHING SEQUENCES 8_CUS-MNR12_500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 23 * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1730 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B4" "R" * * required generation shedding 1272 MW, actual shedding is 1300 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 72.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 155 MW TG 72.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 155 MW TG 72.0 "SEV G3 " 13.8 "1 " * * Shed unit at 50637 MCA G1 16.0 350 MW TG 74.0 "MCA G1 " 16.0 "1 " * * Shed unit at 50640 MCA G4 16.0 450 MW TG 74.0 "MCA G4 " 16.0 "1 " * * Shed unit at 50496 GMS G2 13.8 250 MW TG 74.0 "GMS G2 " 13.8 "1 " Page 317 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 50497 GMS G3 13.8 250 MW TG 74.0 "GMS G3 " 13.8 "1 " * * Disconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B4" "D" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b2" "R" * Page 318 of 722 APPENDIX I – SWITCHING SEQUENCES 9_SEL-ACK500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Selkirk - Ashton Creek 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 265 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek 500 kV Line DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 52161 WAN G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * 3p reclosing, lead end SEL, Follow end ACK * Apply bus fault at Selkirk 500 kV FB 120. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "SEL500 " 500. * Page 319 of 722 APPENDIX I – SWITCHING SEQUENCES 10_SEL-VAS500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Selkirk - Vaseux Lake 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 310 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Vaseux Lake 500 kV Line DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 80 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Trip GFT-161 to OLI-161 (52227-52261, FortisBC 161 kV line 11W) DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * 3p reclosing, lead end SEL, Follow end VAS * Apply bus fault at Selkirk 500 kV FB 98.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 101. "SEL500 " 500. * Page 320 of 722 APPENDIX I – SWITCHING SEQUENCES 11_NIC-MDN500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nicola - Meridian 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Meridian 500 kV FB 60.0 "MDN500 " 500. * * Clear bus fault at Meridian 500 kV CFB 64.0 "MDN500 " 500. * * Trip Nicola - Meridian 500 kV Line DL 64.0 "MDN500 " 500. "NIC500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "C" 0.0 -1.225 * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * * 3p reclosing, lead end MDN, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 120. "MDN500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "MDN500 " 500. * Page 321 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1575 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 1575 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50771 KCL G3 13.8 120 MW TG 70.0 "KCL G3 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 155 MW TG 70.0 "SEV G2 " 13.8 "1 " Page 322 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 50768 SEV G3 13.8 155 MW TG 70.0 "SEV G3 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 80 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 51045 ALH G2 13.8 80 MW TG 70.0 "ALH G2 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * Page 323 of 722 APPENDIX I – SWITCHING SEQUENCES * Switch in 12kV, 12 MVAR shunt reactors at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt reactors at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * * Switch in 12kV, 75 MVAR shunt reactors at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 CC MBS 960. "ACK500 " 500. "b2" "R" * Page 324 of 722 APPENDIX I – SWITCHING SEQUENCES 13_NIC-ACK12_500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nicola - Ashton Creek #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1510 * * Apply bus fault at Ashton Creek 500 kV FB 60.0 "ACK500 " 500. * * Clear bus fault at Ashton Creek 500 kV CFB 64.0 "ACK500 " 500. * * Trip Nicola - Ashton Creek #1 and #2 500 kV Lines DL 64.0 "NIC500 " 500. "ACK500 " 500. "1 " DL 64.0 "NIC500 " 500. "ACK500 " 500. "2 " * * required generation shedding 1682 MW, actual shedding is 1510 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50771 KCL G3 13.8 120 MW TG 70.0 "KCL G3 " 13.8 "1 " * * Trip VNT138 - VVW138 138 kV Line DL 70.0 "VNT138 " 138. "VVW138 " 138. "1 " * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 155 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 155 MW TG 70.0 "SEV G3 " 13.8 "1 " * * Shed unit at 50644 REV G1 16.0 355 MW TG 72.0 "REV G1 " 16.0 "1 " Page 325 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip SAM138 - STO138 138 kV Line DL 72.0 "SAM138 " 138. "STO138 " 138. "1 " * * 3p reclosing, lead end ACK, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 150. "ACK500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 153. "ACK500 " 500. * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b1" "R" * Page 326 of 722 APPENDIX I – SWITCHING SEQUENCES 14_NIC-ING_NIC-MDN500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nicola - Ingledow and Nicola - Meridian 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1515 * * Apply bus fault at Nicola 500 kV FB 60.0 "NIC500 " 500. * * Clear bus fault at Nicola 500 kV CFB 64.0 "NIC500 " 500. * * Trip Nicola - Ingledow and Nicola - Meridian 500 kV Lines DL 64.0 "NIC500 " 500. "ING500 " 500. "1 " DL 64.0 "NIC500 " 500. "MDN500 " 500. "1 " * * Disconnect 245 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "D" * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * required generation shedding 1468 MW, actual shedding is 1480 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50639 MCA G3 16.0 450 MW TG 72.0 "MCA G3 " 16.0 "1 " * * Shed unit at 50640 MCA G4 16.0 450 MW TG 72.0 "MCA G4 " 16.0 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " Page 327 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Trip Nelway - Boundary 230 kV Line DL 72.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * * Remove bus, causing divergence problems. DB 86.0 "MARIAS " 230. DB 86.0 "MATL_AB " 240. DB 86.0 "MATL_AB " 230. * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * * 3p reclosing, lead end MDN, Follow end NIC * 3p reclosing, lead end ING, Follow end NIC * Meridian - Nicola Rpu=0.002480 Xpu=0.016500 Bpu=0.0 * Ingledow - Nicola Rpu=0.002530 Xpu=0.018370 Bpu=0.0 (Gpu=7.36, Bpu=-53.4) * Apply bus fault at Meridian 500 kV through line impedance FB 120. "MDN500 " 500. .002480 .016500 * * Reinsert shunt at Ingledow with 1/line impedance MBS 120. "ING500 " 500. "FT" R * * Clear bus fault at Meridian 500 kV CFB 123. "MDN500 " 500. * * Disconnect shunt at Ingledow with 1/line impedance MBS 123. "ING500 " 500. "FT" D * ******************************************************* Page 328 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b1" "R" * Page 329 of 722 APPENDIX I – SWITCHING SEQUENCES 15_NEL-BND230_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 260 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * actual generation shedding is 260 MW * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 72.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 72.0 "BOUNDARY" 14.4 "2 " * Page 330 of 722 APPENDIX I – SWITCHING SEQUENCES 16_GENESE3.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Genessee Unit 3 250 MW * * CC cards for post-transient only * CC DRP 250 * * Apply bus fault at Genesee 500 kV FB 60.0 "GENESEE4" 500. * * Clear bus fault at Genesee 500 kV CFB 64.0 "GENESEE4" 500. * * Trip Genessee Unit 3 250 MW 54490 TG 64.0 "GENES 39" 20.5 "3 " * Page 331 of 722 APPENDIX I – SWITCHING SEQUENCES 17_LGD-JNT240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - Janet #1 240 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 64.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 240 kV Line DL 64.0 "LANGDON9" 240. "JANET 4" 240. "36" * Page 332 of 722 APPENDIX I – SWITCHING SEQUENCES 18a_SUN-BLT12_240-SLG.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply SLG bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. 0.00191 0.01667 * * Clear bus fault at Sundance 240 kV CFB 64.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 333 of 722 APPENDIX I – SWITCHING SEQUENCES 18b_SUN-BLT12_240-DLO.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply SLG bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. 0.0005772 0.00429 * * Clear bus fault at Sundance 240 kV CFB 64.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 334 of 722 APPENDIX I – SWITCHING SEQUENCES 18b_SUN-BLT12_240-DLO5cycle.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply SLG bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. 0.0005772 0.00429 * * Clear bus fault at Sundance 240 kV CFB 65.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 65.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 65.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 335 of 722 APPENDIX I – SWITCHING SEQUENCES 18b_SUN-BLT12_240-DLO6cycle.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply SLG bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. 0.0005772 0.00429 * * Clear bus fault at Sundance 240 kV CFB 66.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 66.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 336 of 722 APPENDIX I – SWITCHING SEQUENCES 18_SUN-BLT12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 64.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 64.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 64.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 337 of 722 APPENDIX I – SWITCHING SEQUENCES 19_BLT-SRC12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 64.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 64.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 64.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 338 of 722 APPENDIX I – SWITCHING SEQUENCES 20_BLT-KPH12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Benalto - Keephills #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 64.0 "BENALTO4" 240. * * Trip Benalto - Keephills #1 and #2 240 kV Lines DL 64.0 "BENALTO4" 240. "KEEPHIL4" 240. "03" * DL 64.0 "BENALTO4" 240. "KEEPHIL4" 240. "90" * Page 339 of 722 APPENDIX I – SWITCHING SEQUENCES 21_JAN-RED12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. * * Clear bus fault at Janet 240 kV CFB 64.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 64.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 64.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 340 of 722 APPENDIX I – SWITCHING SEQUENCES 22_RED-ELR12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Red Deer - Ellerslie #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Red Deer 240 kV FB 60.0 "RED DEE4" 240. * * Clear bus fault at Red Deer 240 kV CFB 64.0 "RED DEE4" 240. * * Trip Red Deer - Ellerslie #1 and #2 240 kV Lines DL 64.0 "RED DEE4" 240. "ELLERSLI" 240. "10" * DL 64.0 "RED DEE4" 240. "GAETZ 4" 240. "14" DL 64.0 "GAETZ 4" 240. "BIGSTON4" 240. "14" DL 64.0 "BIGSTON4" 240. "ELLERSLI" 240. "14" * Page 341 of 722 APPENDIX I – SWITCHING SEQUENCES 23_LGD-JNT12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 64.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 64.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 64.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 342 of 722 APPENDIX I – SWITCHING SEQUENCES 24_LGD-LTH12_240.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - N. Lethbridge #1 and #2 240 kV Lines * Pre-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 64.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 64.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon #1 and #2 240 kV Lines DL 64.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 64.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 64.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 64.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 64.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 64.0 "N LETHB4" 240. "MILO 2 " 240. "23" * Page 343 of 722 APPENDIX I – SWITCHING SEQUENCES 25_LGD-LTH_LGD-MTL_240.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - N. Lethbridge and Langdon - MATL AB 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 64.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 64.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon and N. Lethbridge - MATL AB 240 kV Lines DL 64.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 64.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 64.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 64.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 64.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 64.0 "MILO 2 " 240. "MATL_AB " 240. "23" * * Remove bus, causing divergence problems. DB 64.0 "MATL_AB " 240. DB 64.0 "MATL_AB " 230. * Page 344 of 722 APPENDIX I – SWITCHING SEQUENCES 26_LGD-LTH_MTL-LTH_240.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at N. Lethbridge 240 kV FB 60.0 "N LETHB4" 240. * * Clear bus fault at N. Lethbridge 240 kV CFB 64.0 "N LETHB4" 240. * * Trip Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines DL 64.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 64.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 64.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 64.0 "N LETHB4" 240. "MATL_AB " 240. "23" * Page 345 of 722 APPENDIX I – SWITCHING SEQUENCES ALBERTA WIND SENSITIVITY ANALYSIS 07 HS CASES: 5 – 8 SWITCHING SEQUENCES Page 346 of 722 APPENDIX I – SWITCHING SEQUENCES 1_MTL-MAR230.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " * * Remove bus, causing divergence problems. CC DB 124.0 "MARIAS " 230. * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * Page 347 of 722 APPENDIX I – SWITCHING SEQUENCES 2_MAR-GFL230.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Marias to Great Falls 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Marias 230 kV FB 60.0 "MARIAS " 230 * * Clear bus fault at Marias 230 kV CFB 64.0 "MARIAS " 230 * * Trip Marias to Great Falls 230 kV Line DL 64.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 64.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " * * Remove bus, causing divergence problems. CC DB 124.0 "MARIAS " 230. * * Trip MATL PS to Cutbank 230 kV Line DL 124.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 124.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 124.0 "MATLN_&1" 230. "MARIAS " 230. "1 " Page 348 of 722 APPENDIX I – SWITCHING SEQUENCES 3a_LGDN-CBK500_c1.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * * Apply bus fault at Langdon2 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon2 - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Note According to PeterM this action is already completed due to tripping the line. * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV * MLS 64 .0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 180 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * * Trip COLEMAN7 - NTL138 138 kV Line Page 349 of 722 APPENDIX I – SWITCHING SEQUENCES DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 350 of 722 APPENDIX I – SWITCHING SEQUENCES 3_LGDN-CRNBRK500.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * * Apply bus fault at Langdon2 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon2 - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Note According to PeterM this action is already completed due to tripping the line. * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV * MLS 64 .0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 180 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * Page 351 of 722 APPENDIX I – SWITCHING SEQUENCES 4_CRNBRK-SELk500.swt RUN * * Last updated 10/24/2006 by TCL * Path 1 Dynamics IV-21 * * Cranbrook -- Selkirk 500 kV line Contingency with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Cranbrook - Selkirk 500 kV Line DL 64.0 "CBK500 " 500. "SEL500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 ** * Trip Langdon2 - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langdon 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " Page 352 of 722 APPENDIX I – SWITCHING SEQUENCES DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.08 p.u. * then switch following shunts in the specified time until the voltage drops below 1.08 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 91.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 91.0 "CBK T7 " 12.6 "b0" "D" * * Switch in 12kV, 12 MVAR shunt reactors at 51364 MBS 109. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt reactors at 50838 MBS 109. "CBK T7 " 12.6 "b1" "R" * * Switch in 12kV, 75 MVAR shunt reactors at 51352 MBS 127. "CBK T2 " 12.6 "b0" "R" * ******************************************************* * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 353 of 722 APPENDIX I – SWITCHING SEQUENCES 5_ING-CUS500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Ingledow - Custer #1 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 240 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * Page 354 of 722 APPENDIX I – SWITCHING SEQUENCES 6_CUS-MNR500.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 355 of 722 APPENDIX I – SWITCHING SEQUENCES 7_ING-CUS12_500_RAS.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1410 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B4" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 80 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 50639 MCA G3, 450 MW TG 72.0 "MCA G3 " 16.0 "1 " * * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * * Shed unit at 50497 GMS G3 13.8 250 MW TG 72.0 "GMS G3 " 13.8 "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " Page 356 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * * Disconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B4" "D" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b2" "R" * Page 357 of 722 APPENDIX I – SWITCHING SEQUENCES 8_CUS-MNR12_500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 23 * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1730 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B4" "R" * * required generation shedding 1272 MW, actual shedding is 1300 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 72.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 155 MW TG 72.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 155 MW TG 72.0 "SEV G3 " 13.8 "1 " * * Shed unit at 50637 MCA G1 16.0 350 MW TG 74.0 "MCA G1 " 16.0 "1 " * * Shed unit at 50640 MCA G4 16.0 450 MW TG 74.0 "MCA G4 " 16.0 "1 " * * Shed unit at 50496 GMS G2 13.8 250 MW TG 74.0 "GMS G2 " 13.8 "1 " Page 358 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 50497 GMS G3 13.8 250 MW TG 74.0 "GMS G3 " 13.8 "1 " * * Disconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B4" "D" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b2" "R" * Page 359 of 722 APPENDIX I – SWITCHING SEQUENCES 9_SEL-ACK500_RAS.swt10_SELVAS500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Selkirk - Ashton Creek 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek 500 kV Line DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * 3p reclosing, lead end SEL, Follow end ACK * Apply bus fault at Selkirk 500 kV FB 120. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "SEL500 " 500. * Page 360 of 722 APPENDIX I – SWITCHING SEQUENCES 11_NIC-MDN500_RAS.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Nicola - Meridian 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Meridian 500 kV FB 60.0 "MDN500 " 500. * * Clear bus fault at Meridian 500 kV CFB 64.0 "MDN500 " 500. * * Trip Nicola - Meridian 500 kV Line DL 64.0 "MDN500 " 500. "NIC500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "C" 0.0 -1.225 * * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * * 3p reclosing, lead end MDN, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 120. "MDN500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 123. "MDN500 " 500. * Page 361 of 722 APPENDIX I – SWITCHING SEQUENCES 12_SEL-ACK_SEL-VAS500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1575 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Ashton Creek and Selkirk - Vaseux Lake 500 kV Lines DL 64.0 "SEL500 " 500. "ACK500 " 500. "1 " DL 64.0 "SEL500 " 500. "VAS500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Selkirk 500 kV MBS 64.0 "SEL500 " 500. "b1 " "D" * * Disconnect 122.5 MVAR of shunt reactance at Ashton Creek 500 kV MBS 64.0 "ACK500 " 500. "b1 " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 626 MW, actual shedding is 1575 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50771 KCL G3 13.8 120 MW TG 70.0 "KCL G3 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 155 MW TG 70.0 "SEV G2 " 13.8 "1 " Page 362 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 50768 SEV G3 13.8 155 MW TG 70.0 "SEV G3 " 13.8 "1 " * * Shed unit at 51044 ALH G1 13.8 80 MW TG 70.0 "ALH G1 " 13.8 "1 " * * Shed unit at 51045 ALH G2 13.8 80 MW TG 70.0 "ALH G2 " 13.8 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip GFT-161 - OLI-161 161 kV Line DL 72.0 "GFT-161 " 161. "OLI-161 " 161. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ****************************************************** * if bus 50782 (CBK230) voltage is above 1.06 p.u. * then switch following shunts in succession in half second intervals until * the voltage drops below 1.06 * * Switch off 12kV, 19.2 MVAR shunt capacitor at 51364 MBS 360.0 "CBK T6 " 12.6 "b0" "D" * * Switch off 12kV, 19.2 MVAR shunt capacitor at 50838 MBS 390.0 "CBK T7 " 12.6 "b0" "D" * Page 363 of 722 APPENDIX I – SWITCHING SEQUENCES * Switch in 12kV, 12 MVAR shunt reactors at 51364 MBS 420. "CBK T6 " 12.6 "b1" "R" * * Switch in 12kV, 12 MVAR shunt reactors at 50838 MBS 450. "CBK T7 " 12.6 "b1" "R" * * Switch in 12kV, 75 MVAR shunt reactors at 51352 MBS 480. "CBK T2 " 12.6 "b0" "R" * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 CC MBS 960. "ACK500 " 500. "b2" "R" * Page 364 of 722 APPENDIX I – SWITCHING SEQUENCES 13_NIC-ACK12_500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nicola - Ashton Creek #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1510 * * Apply bus fault at Ashton Creek 500 kV FB 60.0 "ACK500 " 500. * * Clear bus fault at Ashton Creek 500 kV CFB 64.0 "ACK500 " 500. * * Trip Nicola - Ashton Creek #1 and #2 500 kV Lines DL 64.0 "NIC500 " 500. "ACK500 " 500. "1 " DL 64.0 "NIC500 " 500. "ACK500 " 500. "2 " * * required generation shedding 1682 MW, actual shedding is 1510 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50771 KCL G3 13.8 120 MW TG 70.0 "KCL G3 " 13.8 "1 " * * Trip VNT138 - VVW138 138 kV Line DL 70.0 "VNT138 " 138. "VVW138 " 138. "1 " * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50767 SEV G2 13.8 155 MW TG 70.0 "SEV G2 " 13.8 "1 " * * Shed unit at 50768 SEV G3 13.8 155 MW TG 70.0 "SEV G3 " 13.8 "1 " * * Shed unit at 50644 REV G1 16.0 355 MW TG 72.0 "REV G1 " 16.0 "1 " Page 365 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Shed unit at 52164 WAN-G4 14.4 110 MW TG 72.0 "WAN-G4 " 14.4 "4 " * * Trip SAM138 - STO138 138 kV Line DL 72.0 "SAM138 " 138. "STO138 " 138. "1 " * * 3p reclosing, lead end ACK, Follow end NIC * Apply bus fault at Selkirk 500 kV FB 150. "ACK500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 153. "ACK500 " 500. * ******************************************************* ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b1" "R" * Page 366 of 722 APPENDIX I – SWITCHING SEQUENCES 14_NIC-ING_NIC-MDN500_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nicola - Ingledow and Nicola - Meridian 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1515 * * Apply bus fault at Nicola 500 kV FB 60.0 "NIC500 " 500. * * Clear bus fault at Nicola 500 kV CFB 64.0 "NIC500 " 500. * * Trip Nicola - Ingledow and Nicola - Meridian 500 kV Lines DL 64.0 "NIC500 " 500. "ING500 " 500. "1 " DL 64.0 "NIC500 " 500. "MDN500 " 500. "1 " * * Disconnect 245 MVAR of shunt reactance at Nicola 500 kV MBS 64.0 "NIC500 " 500. "b1 " "D" * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "B2" "R" * * required generation shedding 1468 MW, actual shedding is 1480 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * * Shed unit at 50770 KCL G2 13.8 120 MW TG 70.0 "KCL G2 " 13.8 "1 " * * Shed unit at 50766 SEV G1 13.8 155 MW TG 70.0 "SEV G1 " 13.8 "1 " * * Shed unit at 50639 MCA G3 16.0 450 MW TG 72.0 "MCA G3 " 16.0 "1 " * * Shed unit at 50640 MCA G4 16.0 450 MW TG 72.0 "MCA G4 " 16.0 "1 " * * Shed unit at 52161 WAN-G1 14.4 110 MW TG 72.0 "WAN-G1 " 14.4 "1 " Page 367 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit at 52162 WAN-G2 14.4 110 MW TG 72.0 "WAN-G2 " 14.4 "2 " * * Trip Nelway - Boundary 230 kV Line DL 72.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * * Remove bus, causing divergence problems. DB 86.0 "MARIAS " 230. DB 86.0 "MATL_AB " 240. DB 86.0 "MATL_AB " 230. * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "B2" "D" * * 3p reclosing, lead end MDN, Follow end NIC * 3p reclosing, lead end ING, Follow end NIC * Meridian - Nicola Rpu=0.002480 Xpu=0.016500 Bpu=0.0 * Ingledow - Nicola Rpu=0.002530 Xpu=0.018370 Bpu=0.0 (Gpu=7.36, Bpu=-53.4) * Apply bus fault at Meridian 500 kV through line impedance FB 120. "MDN500 " 500. .002480 .016500 * * Reinsert shunt at Ingledow with 1/line impedance MBS 120. "ING500 " 500. "FT" R * * Clear bus fault at Meridian 500 kV CFB 123. "MDN500 " 500. * * Disconnect shunt at Ingledow with 1/line impedance MBS 123. "ING500 " 500. "FT" D * ******************************************************* Page 368 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "b0" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 960. "ACK500 " 500. "b1" "R" * Page 369 of 722 APPENDIX I – SWITCHING SEQUENCES 15_NEL-BND230_RAS.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 260 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * actual generation shedding is 260 MW * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 72.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 72.0 "BOUNDARY" 14.4 "2 " * Page 370 of 722 APPENDIX I – SWITCHING SEQUENCES 16_GENESE3.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Genessee Unit 3 450 MW * * CC cards for post-transient only * CC DRP 450 * * Apply bus fault at Genesee 500 kV FB 60.0 "GENESEE4" 500. * * Clear bus fault at Genesee 500 kV CFB 63.0 "GENESEE4" 500. * * Trip Genessee Unit 3 450 MW 54490 TG 63.0 "GENES 39" 20.5 "3 " * Page 371 of 722 APPENDIX I – SWITCHING SEQUENCES 17_LGD-JNT240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Janet #1 240 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 240 kV Line DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * Page 372 of 722 APPENDIX I – SWITCHING SEQUENCES 17_LGD-JNT240_4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Janet #1 240 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 64.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 240 kV Line DL 64.0 "LANGDON9" 240. "JANET 4" 240. "36" * Page 373 of 722 APPENDIX I – SWITCHING SEQUENCES 18a_SUN-BLT-22_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. * * Clear bus fault at Sundance 240 kV CFB 65.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines *DL 63.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * *DL 63.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 374 of 722 APPENDIX I – SWITCHING SEQUENCES 18a_SUN-BLT12_240_DLO_SLG4.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply SLG bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. 0.00191 0.01667 * * Clear bus fault at Sundance 240 kV CFB 64.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 375 of 722 APPENDIX I – SWITCHING SEQUENCES 18b_SUN-BLT12_240-DLO_LLG4.swt RUN * * Last updated 10/20/2006 by TCL * Path 1 Dynamics IV-21 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply SLG bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. 0.0005772 0.00429 * * Clear bus fault at Sundance 240 kV CFB 64.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 376 of 722 APPENDIX I – SWITCHING SEQUENCES 18_SUN-BLT12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. * * Clear bus fault at Sundance 240 kV CFB 64.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 377 of 722 APPENDIX I – SWITCHING SEQUENCES 18_SUN-BLT12_240_4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Sundance - Benalto #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Sundance 240 kV FB 60.0 "SUNDANM9" 240. * * Clear bus fault at Sundance 240 kV CFB 64.0 "SUNDANM9" 240. * * Trip Sundance - Benalto #1 and #2 240 kV Lines DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "22" * DL 64.0 "SUNDANM9" 240. "BENALTO4" 240. "26" * Page 378 of 722 APPENDIX I – SWITCHING SEQUENCES 19_BLT-SRC12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 66.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 379 of 722 APPENDIX I – SWITCHING SEQUENCES 19_BLT-SRC12_240_4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Benalto - Sarcee #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 64.0 "BENALTO4" 240. * * Trip Benalto - Sarcee #1 and #2 240 kV Lines DL 64.0 "BENALTO4" 240. "SARCEE 4" 240. "06" * DL 64.0 "BENALTO4" 240. "SARCEE 4" 240. "28" * Page 380 of 722 APPENDIX I – SWITCHING SEQUENCES 20_BLT-KPH12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Benalto - Keephills #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 66.0 "BENALTO4" 240. * * Trip Benalto - Keephills #1 and #2 240 kV Lines DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "03" * DL 66.0 "BENALTO4" 240. "KEEPHIL4" 240. "90" * Page 381 of 722 APPENDIX I – SWITCHING SEQUENCES 20_BLT-KPH12_240_4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Benalto - Keephills #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Benalto 240 kV FB 60.0 "BENALTO4" 240. * * Clear bus fault at Benalto 240 kV CFB 64.0 "BENALTO4" 240. * * Trip Benalto - Keephills #1 and #2 240 kV Lines DL 64.0 "BENALTO4" 240. "KEEPHIL4" 240. "03" * DL 64.0 "BENALTO4" 240. "KEEPHIL4" 240. "90" * Page 382 of 722 APPENDIX I – SWITCHING SEQUENCES 21a_JAN-RED12_240_DLO_SLG4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. 0.00818 0.03374 * * Clear bus fault at Janet 240 kV CFB 64.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 64.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 64.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 383 of 722 APPENDIX I – SWITCHING SEQUENCES 21b_JAN-RED12_240_DLO_LLG4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. 0.002180 0.008347 * * Clear bus fault at Janet 240 kV CFB 64.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 64.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 64.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 384 of 722 APPENDIX I – SWITCHING SEQUENCES 21_JAN-RED12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. * * Clear bus fault at Janet 240 kV CFB 66.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 66.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 66.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 385 of 722 APPENDIX I – SWITCHING SEQUENCES 21_JAN-RED12_240_4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Janet - Red Deer #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Janet 240 kV FB 60.0 "JANET 4" 240. * * Clear bus fault at Janet 240 kV CFB 64.0 "JANET 4" 240. * * Trip Janet - Red Deer #1 and #2 240 kV Lines DL 64.0 "JANET 4" 240. "RED DEE4" 240. "25" * DL 64.0 "JANET 4" 240. "RED DEE4" 240. "29" * Page 386 of 722 APPENDIX I – SWITCHING SEQUENCES 22_RED-ELR12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Red Deer - Ellerslie #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Red Deer 240 kV FB 60.0 "RED DEE4" 240. * * Clear bus fault at Red Deer 240 kV CFB 66.0 "RED DEE4" 240. * * Trip Red Deer - Ellerslie #1 and #2 240 kV Lines DL 66.0 "RED DEE4" 240. "ELLERSLI" 240. "10" * DL 66.0 "RED DEE4" 240. "GAETZ 4" 240. "14" DL 66.0 "GAETZ 4" 240. "BIGSTON4" 240. "14" DL 66.0 "BIGSTON4" 240. "ELLERSLI" 240. "14" * Page 387 of 722 APPENDIX I – SWITCHING SEQUENCES 22_RED-ELR12_240_4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Red Deer - Ellerslie #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Red Deer 240 kV FB 60.0 "RED DEE4" 240. * * Clear bus fault at Red Deer 240 kV CFB 64.0 "RED DEE4" 240. * * Trip Red Deer - Ellerslie #1 and #2 240 kV Lines DL 64.0 "RED DEE4" 240. "ELLERSLI" 240. "10" * DL 64.0 "RED DEE4" 240. "GAETZ 4" 240. "14" DL 64.0 "GAETZ 4" 240. "BIGSTON4" 240. "14" DL 64.0 "BIGSTON4" 240. "ELLERSLI" 240. "14" * Page 388 of 722 APPENDIX I – SWITCHING SEQUENCES 23a_LGD-JNT12_240_DLO_SLG4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. 0.00608 0.0332 * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 66.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 389 of 722 APPENDIX I – SWITCHING SEQUENCES 23b_LGD-JNT12_240_DLO_LLG4.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. 0.001452 0.008330 * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 66.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 390 of 722 APPENDIX I – SWITCHING SEQUENCES 23_LGD-JNT12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 66.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 66.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 66.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 391 of 722 APPENDIX I – SWITCHING SEQUENCES 23_LGD-JNT12_240_4.swt * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - Janet #1 and #2 240 kV Lines * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 240 kV FB 60.0 "LANGDON9" 240. * * Clear bus fault at Langdon 240 kV CFB 64.0 "LANGDON9" 240. * * Trip Langdon - Janet #1 and #2 240 kV Lines DL 64.0 "LANGDON9" 240. "JANET 4" 240. "36" * DL 64.0 "LANGDON9" 240. "JANET 4" 240. "37" * Page 392 of 722 APPENDIX I – SWITCHING SEQUENCES 24_LGD-LTH12_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - N. Lethbridge #1 and #2 240 kV Lines * Pre-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon #1 and #2 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "N LETHB4" 240. "MILO 2 " 240. "23" * Page 393 of 722 APPENDIX I – SWITCHING SEQUENCES 25_LGD-LTH_LGD-MTL_240.swt RUN * * Last updated 10/23/2006 by TCL * Path 1 Dynamics IV-21 * * Langdon - N. Lethbridge and Langdon - MATL AB 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Insert line from Milo 1 - Milo 2 RL 60.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * Apply bus fault at Milo 1 240 kV FB 60.0 "MILO 1 " 240. * * Clear bus fault at Milo 1 240 kV CFB 66.0 "MILO 1 " 240. * * Disconnect line from Milo 1 - Milo 2 DL 66.0 "MILO 1 " 240. "MILO 2 " 240. "1 " * * N. Lethbridge - Langdon and N. Lethbridge - MATL AB 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "LANGDON9" 240. "MILO 2 " 240. "27" DL 66.0 "MILO 2 " 240. "W BROOK4" 240. "23" DL 66.0 "MILO 2 " 240. "MATL_AB " 240. "23" * * Remove bus, causing divergence problems. DB 66.0 "MATL_AB " 240. DB 66.0 "MATL_AB " 230. * Page 394 of 722 APPENDIX I – SWITCHING SEQUENCES 26_LGD-LTH_MTL-LTH_240.swt RUN * * Last updated 10/25/2006 by TCL * Path 1 Dynamics IV-23 * * Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines * Post-project cases only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at N. Lethbridge 240 kV FB 60.0 "N LETHB4" 240. * * Clear bus fault at N. Lethbridge 240 kV CFB 66.0 "N LETHB4" 240. * * Trip Langdon - N. Lethbridge and MATL AB - N. Lethbridge 240 kV Lines DL 66.0 "N LETHB4" 240. "MILO 1 " 240. "24" DL 66.0 "LANGDON9" 240. "MILO 1 " 240. "24" DL 66.0 "W BROOK4" 240. "MILO 1 " 240. "35" * DL 66.0 "N LETHB4" 240. "MATL_AB " 240. "23" * Page 395 of 722 APPENDIX I – SWITCHING SEQUENCES PATH – 3: 07HS – Transient Analysis Page 396 of 722 APPENDIX I – SWITCHING SEQUENCES 10_BND-BEL1_BEL-USK_230_RAS2.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #1 and Bell-Usk 230 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Bell - USK 230 kV Line DL 64.0 "BELL S&A" 230. "USK " 230. "1 " * Trip Boundary - Bell 230 kV Line DL 64.0 "BELL S1 " 230. "SACHEEN " 230. "1 " DL 64.0 "BOUNDARY" 230. "SACHEEN " 230. "1 " * * For DLO's South of Boundary, Drop Boundary Gen so that post outage gen < 200 MW * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Shed unit 3 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "3 " * * Shed unit 4 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "4 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 397 of 722 APPENDIX I – SWITCHING SEQUENCES 11_BND-BEL3230_ADY-BEL1_115_RAS4.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #3 and Addy - Bell #1 115 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Boundary - Bell #3 230 kV Line DL 64.0 "BELL S3 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&A" 230. "1 " DL 64.0 "BOUNDARY" 230. "ADDY 2&A" 230. "1 " DB 64.0 "ADDY 2 " 230. * * Trip Addy - Bell #1 115 kV Line * The conservative option for this contingency is to only trip the 230/115 kV bank * This option results in maximum post contingency loading on the remaining lines * (for north to south flows). DL 64.0 "ADDY 2 " 230. "ADDY " 115. "1 " * * For DLO's South of Boundary, Drop Boundary Gen so that post outage gen < 650 MW * Starting Gen = 800 MW, Trip Units 1 & 2. Remaining Gen = 540 MW * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Shed unit 3 at 46405 BOUNDARY 14.40 130 MW *TG 76.0 "BOUNDARY" 14.4 "3 " * * Shed unit 4 at 46405 BOUNDARY 14.40 130 MW *TG 76.0 "BOUNDARY" 14.4 "4 " Page 398 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW *TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 399 of 722 APPENDIX I – SWITCHING SEQUENCES Crn-Sel500_RAS_HS_IV32av2.swt RUN * * Cranbrook - Selkirk 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Cranbrook 500 kV Line DL 64.0 "SEL500 " 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * Trip Nelway - Boundary 230 kV Line *DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " **** This is not in bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2 !!!!! * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW ***TG 76.0 "BOUNDRY2" 14.4 "5 " **** This is not in bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2 !!!!! * * Page 400 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 50838 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch off 38.4 MVAr ** shunt capacitor at CBK 12 12.6 kV bus 50838 **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) *MBS 90.0 "CBK 12 " 12.6 "b0" "D" *MBS 90.0 "CBK 12 " 12.6 "b1" "D" * * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 401 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr12_500_RAS_HS_IV32av2.swt RUN * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1880 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * * Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 38 * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "R1" & "R2" MBL 64.0 "GMS138 " 138. "R1" "R" MBL 64.0 "GMS138 " 138. "R2" "R" * * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 35 * Shed unit at 50637 MCA G1 16.0 430 MW TG 72.0 "MCA G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 36 * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 37 * Shed unit at 50646 REV G3 16.0 500 MW TG 72.0 "REV G3 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 44 * Shed unit at 50495 GMS G1 13.8 250 MW TG 72.0 "GMS G1 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 45 * Shed unit at 50496 GMS G2 13.8 250 MW Page 402 of 722 APPENDIX I – SWITCHING SEQUENCES TG 72.0 "GMS G2 " 13.8 "1 " * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 39 * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "R1" "D" MBL 104. "GMS138 " 138. "R2" "D" * Page 403 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr12_500_RAS_HS_IV32av2_M.swt RUN * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1880 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 38 * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "R1" & "R2" MBL 64.0 "GMS138 " 138. "R1" "R" MBL 64.0 "GMS138 " 138. "R2" "R" * * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 35 * Shed unit at 50637 MCA G1 16.0 430 MW TG 72.0 "MCA G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 36 * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 37 * Shed unit at 50646 REV G3 16.0 500 MW TG 72.0 "REV G3 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 44 * Shed unit at 50495 GMS G1 13.8 250 MW TG 72.0 "GMS G1 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 45 * Shed unit at 50496 GMS G2 13.8 250 MW Page 404 of 722 APPENDIX I – SWITCHING SEQUENCES TG 72.0 "GMS G2 " 13.8 "1 " * * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 39 * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "R1" "D" MBL 104. "GMS138 " 138. "R2" "D" * Page 405 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr500.swt RUN * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 406 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_HS_IV32av2.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "R1" MBL 64.0 "GMS138 " 138. "R1" "R" 200.0 0.0 * ** the following assumes svd at 50183 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 9 ** switch out all shunt caps on 50183 MBS 67.0 "ING230 " 230. "c1" "D" MBS 67.0 "ING230 " 230. "c2" "D" MBS 67.0 "ING230 " 230. "c3" "D" MBS 67.0 "ING230 " 230. "c4" "D" * * ** the following assumes svd at 50018 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 10 ** switch out all shunt caps on 50018 MBS 70.0 "ING230 " 230. "c1" "D" MBS 70.0 "ING230 " 230. "c2" "D" MBS 70.0 "ING230 " 230. "c3" "D" MBS 70.0 "ING230 " 230. "c4" "D" * * ** the following assumes svd at 50588 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 11 ** switch out all shunt caps on 50588 MBS 70.0 "ING T4 " 12.6 "r1" "R" * * Page 407 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 51208 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 12 ** switch out all shunt caps on 51208 MBS 70.0 "ING T5 " 12.6 "r1" "R" * * ** the following assumes svd at 50704 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 13 ** switch out all shunt caps on 50704 MBS 70.0 "KLY500 " 500. "r4" "R" MBS 70.0 "KLY500 " 500. "r5" "R" * * ** the following assumes svd at 50703 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 14 ** switch out all shunt caps on 50703 MBS 70.0 "NIC500 " 500. "r3" "R" MBS 70.0 "NIC500 " 500. "r4" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 17 * Shed unit at 50769 KCL G1 13.8 140 MW TG 70.0 "KCL G1 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 18 * Shed unit at 50770 KCL G2 13.8 140 MW TG 70.0 "KCL G2 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 19 * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 19 * Shed unit at 51044 ALH G1 13.8 180 MW TG 70.0 "ALH G1 " 13.8 "1 " * * ** the following assumes svd at 51182 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 21 ** switch out all shunt caps on 51182 MBS 72.0 "MDN T3 " 12.6 "r2" "R" * * ** the following assumes svd at 50018 converted to shunt devices Page 408 of 722 APPENDIX I – SWITCHING SEQUENCES ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 22 ** switch out all shunt caps on 50018 MBS 72.0 "MDN230 " 230. "r1" "R" MBS 72.0 "MDN230 " 230. "r2" "R" * * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 23 * Shed unit at 50637 MCA G1 16.0 430 MW TG 72.0 "MCA G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 24 * Shed unit at 50646 REV G3 16.0 500 MW TG 72.0 "REV G3 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 25 * Shed unit at 50647 REV G4 16.0 500 MW TG 72.0 "REV G4 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 26 * Shed unit at 50495 GMS G1 13.8 250 MW TG 72.0 "GMS G1 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 27 * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 28 * Shed unit 1 at 46405 BOUNDRY2 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 29 * Shed unit 2 at 46405 BOUNDRY2 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "R1" "D" * * ** the following assumes svd at 50702 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 130 ** at 10 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "r2" "R" * * ** the following assumes svd at 50702 converted to shunt devices Page 409 of 722 APPENDIX I – SWITCHING SEQUENCES ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 131 ** at 10 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "r3" "R" * Page 410 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_HS_IV32av2_M.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "R1" MBL 64.0 "GMS138 " 138. "R1" "R" 200.0 0.0 * ** the following assumes svd at 50183 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 9 ** switch out all shunt caps on 50183 MBS 67.0 "ING230 " 230. "c1" "D" MBS 67.0 "ING230 " 230. "c2" "D" MBS 67.0 "ING230 " 230. "c3" "D" MBS 67.0 "ING230 " 230. "c4" "D" * * ** the following assumes svd at 50018 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 10 ** switch out all shunt caps on 50018 MBS 70.0 "ING230 " 230. "c1" "D" MBS 70.0 "ING230 " 230. "c2" "D" MBS 70.0 "ING230 " 230. "c3" "D" MBS 70.0 "ING230 " 230. "c4" "D" * * ** the following assumes svd at 50588 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 11 ** switch out all shunt caps on 50588 MBS 70.0 "ING T4 " 12.6 "r1" "R" * * Page 411 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 51208 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 12 ** switch out all shunt caps on 51208 MBS 70.0 "ING T5 " 12.6 "r1" "R" * * ** the following assumes svd at 50704 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 13 ** switch out all shunt caps on 50704 MBS 70.0 "KLY500 " 500. "r4" "R" MBS 70.0 "KLY500 " 500. "r5" "R" * * ** the following assumes svd at 50703 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 14 ** switch out all shunt caps on 50703 MBS 70.0 "NIC500 " 500. "r3" "R" MBS 70.0 "NIC500 " 500. "r4" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 17 * Shed unit at 50769 KCL G1 13.8 140 MW TG 70.0 "KCL G1 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 18 * Shed unit at 50770 KCL G2 13.8 140 MW TG 70.0 "KCL G2 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 19 * Shed unit at 50766 SEV G1 13.8 180 MW TG 70.0 "SEV G1 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 19 * Shed unit at xxxxxxxxxxxx 180 MW TG 70.0 "ALH G1 " 13.8 "1 " * * ** the following assumes svd at 51182 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 21 ** switch out all shunt caps on 51182 MBS 72.0 "MDN T3 " 12.6 "r2" "R" * * ** the following assumes svd at 50018 converted to shunt devices Page 412 of 722 APPENDIX I – SWITCHING SEQUENCES ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 22 ** switch out all shunt caps on 50018 MBS 72.0 "MDN230 " 230. "r1" "R" MBS 72.0 "MDN230 " 230. "r2" "R" * * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 23 * Shed unit at 50637 MCA G1 16.0 430 MW TG 72.0 "MCA G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 24 * Shed unit at 50646 REV G3 16.0 500 MW TG 72.0 "REV G3 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 25 * Shed unit at 50647 REV G4 16.0 500 MW TG 72.0 "REV G4 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 26 * Shed unit at 50495 GMS G1 13.8 250 MW TG 72.0 "GMS G1 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 27 * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 28 * Shed unit 1 at 46405 BOUNDRY2 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 29 * Shed unit 2 at 46405 BOUNDRY2 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "R1" & "R2" MBL 104. "GMS138 " 138. "R1" "D" * * Page 413 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 50702 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 130 ** at 10 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 MBS 660. "ACK500 " 500. "r2" "R" * * ** the following assumes svd at 50702 converted to shunt devices ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 131 ** at 10 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "r3" "R" * Page 414 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_HS_IV32av2.swt RUN * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line ******DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " **** This is not in bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2 !!!!! * * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW ****TG 76.0 "BOUNDRY2" 14.4 "5 " **** This is not in bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2 !!!!! * * Page 415 of 722 APPENDIX I – SWITCHING SEQUENCES Mtl-Mar230.swt RUN * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DB 64.0 "MATL_AB " 230. DB 64.0 "MATLN_&1" 230. * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 124.0 "MARIAS " 230. DB 124.0 "MATLN_&2" 230. * Page 416 of 722 APPENDIX I – SWITCHING SEQUENCES Nel-Bnd230_RAS_HS_IV32av2.swt RUN * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 83 * Shed unit 1 at 46405 BOUNDARY 14.40 140 MW TG 72.0 "BOUNDARY" 14.4 "1 " * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 84 * Shed unit 1 at 46405 BOUNDARY 14.40 140 MW TG 72.0 "BOUNDARY" 14.4 "2 " * Page 417 of 722 APPENDIX I – SWITCHING SEQUENCES PATH - 3: 07HS - Post-Transient Analysis Page 418 of 722 APPENDIX I – SWITCHING SEQUENCES 10_BND-BEL1_BEL-USK_230_RAS2.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #1 and Bell-Usk 230 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Bell - USK 230 kV Line DL 64.0 "BELL S&A" 230. "USK " 230. "1 " * Trip Boundary - Bell 230 kV Line DL 64.0 "BELL S1 " 230. "SACHEEN " 230. "1 " DL 64.0 "BOUNDARY" 230. "SACHEEN " 230. "1 " * * For DLO's South of Boundary, Drop Boundary Gen so that post outage gen < 200 MW * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Shed unit 3 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "3 " * * Shed unit 4 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "4 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 419 of 722 APPENDIX I – SWITCHING SEQUENCES 11_BND-BEL3230_ADY-BEL1_115_RAS4.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #3 and Addy - Bell #1 115 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Boundary - Bell #3 230 kV Line DL 64.0 "BELL S3 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&A" 230. "1 " DL 64.0 "BOUNDARY" 230. "ADDY 2&A" 230. "1 " DB 64.0 "ADDY 2 " 230. * * Trip Addy - Bell #1 115 kV Line * The conservative option for this contingency is to only trip the 230/115 kV bank * This option results in maximum post contingency loading on the remaining lines * (for north to south flows). DL 64.0 "ADDY 2 " 230. "ADDY " 115. "1 " * * For DLO's South of Boundary, Drop Boundary Gen so that post outage gen < 650 MW * Starting Gen = 800 MW, Trip Units 1 & 2. Remaining Gen = 540 MW * * Shed unit 1 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "1 " * * Shed unit 2 at 46405 BOUNDARY 14.40 130 MW TG 76.0 "BOUNDARY" 14.4 "2 " * * Shed unit 3 at 46405 BOUNDARY 14.40 130 MW *TG 76.0 "BOUNDARY" 14.4 "3 " * * Shed unit 4 at 46405 BOUNDARY 14.40 130 MW *TG 76.0 "BOUNDARY" 14.4 "4 " Page 420 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW *TG 76.0 "BOUNDRY2" 14.4 "5 " * Page 421 of 722 APPENDIX I – SWITCHING SEQUENCES Crn-Sel500_RAS_HS_IV32av2.swt RUN * * Cranbrook - Selkirk 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Cranbrook 500 kV Line DL 64.0 "SEL500 " 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b1" "C" 0.0 -1.225 * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b1" "D" * * Trip Nelway - Boundary 230 kV Line *DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " **** This is not in bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2 !!!!! * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW ***TG 76.0 "BOUNDRY2" 14.4 "5 " **** This is not in bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2 !!!!! * * Page 422 of 722 APPENDIX I – SWITCHING SEQUENCES ** the following assumes svd at 50838 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch off 38.4 MVAr ** shunt capacitor at CBK 12 12.6 kV bus 50838 **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) *MBS 90.0 "CBK 12 " 12.6 "b0" "D" *MBS 90.0 "CBK 12 " 12.6 "b1" "D" * * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 423 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr12_500_RAS_HS_IV32av2.swt RUN * * Custer - Monroe #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1880 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * required generation shedding 1272 MW, actual shedding is 1300 MW * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50645 REV G2 16.0 450 MW TG 72.0 "REV G2 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 38 * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "R1" & "R2" MBL 64.0 "GMS138 " 138. "R1" "R" MBL 64.0 "GMS138 " 138. "R2" "R" * * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 35 * Shed unit at 50637 MCA G1 16.0 430 MW TG 72.0 "MCA G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 36 * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 37 * Shed unit at 50646 REV G3 16.0 500 MW TG 72.0 "REV G3 " 16.0 "1 " Page 424 of 722 APPENDIX I – SWITCHING SEQUENCES * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 44 * Shed unit at 50495 GMS G1 13.8 250 MW TG 72.0 "GMS G1 " 13.8 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 45 * Shed unit at 50496 GMS G2 13.8 250 MW TG 72.0 "GMS G2 " 13.8 "1 " * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 39 * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "R1" "D" MBL 104. "GMS138 " 138. "R2" "D" * Page 425 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr500.swt RUN * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 426 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_HS.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50498 GMS G4 13.8 240 MW TG 72.0 "GMS G4 " 13.8 "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * ** the following assumes svd at 50542 converted to shunt devices ** at 5 seconds if WSN230 voltage is > 1.09 pu, ** switch in one 230 kV 75 MVAr reactor at bus 50542 Page 427 of 722 APPENDIX I – SWITCHING SEQUENCES *MBS 360. "WSN230 " 230. "b2" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50183 converted to shunt devices ** at 10 seconds if ING230 voltage is > 1.06 pu, ** switch in one 230 kV 132 MVAr reactor at bus 50183 Ingledow 230 kV *MBS 660. "ING230 " 230. "b2" "R" ** ** at 20 seconds if ING230 voltage is still > 1.06 pu, ** switch in another 230 kV 132 MVAr reactor at 50183 Ingledow 230 kV *CC MBS 1260 "ING230 " 230. "b3" "R" * Page 428 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_HS_M.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines with RAS * * CC cards for post-transient only * CC DRP 1750 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Reconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "BR" "R" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * required generation shedding 1599 MW, actual shedding is 1610 MW * Shed unit at 50769 KCL G1 13.8 120 MW TG 70.0 "KCL G1 " 13.8 "1 " * Shed unit at 50637 MCA G1 16.0 400 MW TG 72.0 "MCA G1 " 16.0 "1 " * Shed unit at 50638 MCA G2 16.0 400 MW TG 72.0 "MCA G2 " 16.0 "1 " * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * Shed unit at 50498 GMS G4 13.8 240 MW TG 72.0 "GMS G4 " 13.8 "1 " * * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW TG 76.0 "BOUNDRY2" 14.4 "5 " * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. Page 429 of 722 APPENDIX I – SWITCHING SEQUENCES * * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "BR" "D" * ** the following assumes svd at 50542 converted to shunt devices ** at 5 seconds if WSN230 voltage is > 1.09 pu, ** switch in one 230 kV 75 MVAr reactor at bus 50542 *MBS 360. "WSN230 " 230. "b2" "R" * ** the following assumes svd at 50702 converted to shunt devices ** at 5 seconds if ACK500 voltage is > 1.08 pu, ** switch in one 500 kV 122.5 MVAr reactor at bus 50702 *MBS 660. "ACK500 " 500. "b1" "R" * ** the following assumes svd at 50183 converted to shunt devices ** at 10 seconds if ING230 voltage is > 1.06 pu, ** switch in one 230 kV 132 MVAr reactor at bus 50183 Ingledow 230 kV *MBS 660. "ING230 " 230. "b2" "R" ** ** at 20 seconds if ING230 voltage is still > 1.06 pu, ** switch in another 230 kV 132 MVAr reactor at 50183 Ingledow 230 kV *CC MBS 1260 "ING230 " 230. "b3" "R" * Page 430 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus500_RAS_HS_IV32av2.swt RUN * * Ingledow - Custer #1 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 33 * Reconnect 400 MW braking resistor at 50517 GMS138 with load id "BR" MBL 64.0 "GMS138 " 138. "R1" "R" MBL 64.0 "GMS138 " 138. "R2" "R" * * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 35 * Shed unit at 50637 MCA G1 16.0 430 MW TG 72.0 "MCA G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 36 * Shed unit at 50644 REV G1 16.0 450 MW TG 72.0 "REV G1 " 16.0 "1 " * ** Per bctc_simul_SWsequence_dbl_ctg_rsh.xls; Tab=bctc_IV32av2, Line 37 * Shed unit at 50645 REV G2 16.0 450 MW TG 72.0 "REV G2 " 16.0 "1 " * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 39 * Disconnect 200 MW braking resistor at 50517 GMS138 with load id "BR" MBL 104. "GMS138 " 138. "R1" "D" MBL 104. "GMS138 " 138. "R2" "D" * Page 431 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_HS_IV32av2.swt RUN * * Langdon - Cranbrook 500 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "D" "f" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line ******DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " **** This is not in bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2 !!!!! * * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * required generation shedding 150 MW, actual shedding is 140 MW * Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW ****TG 76.0 "BOUNDRY2" 14.4 "5 " **** This is not in bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2 !!!!! * * Page 432 of 722 APPENDIX I – SWITCHING SEQUENCES Mtl-Mar230.swt RUN * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DB 64.0 "MATL_AB " 230. DB 64.0 "MATLN_&1" 230. * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 124.0 "MARIAS " 230. DB 124.0 "MATLN_&2" 230. * Page 433 of 722 APPENDIX I – SWITCHING SEQUENCES Nel-Bnd230_RAS_HS_IV32av2.swt RUN * * Nelway - Boundary 230 kV Line with RAS * * CC cards for post-transient only * CC DRP 140 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 83 * Shed unit 1 at 46405 BOUNDARY 14.40 140 MW TG 72.0 "BOUNDARY" 14.4 "1 " * ** Per bctc_simul_SWSeuqnece_sgl_ctg_RSH.xls; Tab=bctc_IV32av2, Line 84 * Shed unit 1 at 46405 BOUNDARY 14.40 140 MW TG 72.0 "BOUNDARY" 14.4 "2 " * Page 434 of 722 APPENDIX I – SWITCHING SEQUENCES PATH - 3: 07LSP – Transient Analysis Page 435 of 722 APPENDIX I – SWITCHING SEQUENCES 10_BND-BEL1_BEL-USK_230_RAS.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #1 and Bell-Usk 230 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Bell - USK 230 kV Line DL 64.0 "BELL S&A" 230. "USK " 230. "1 " * Trip Boundary - Bell 230 kV Line DL 64.0 "BELL S1 " 230. "SACHEEN " 230. "1 " DL 64.0 "BOUNDARY" 230. "SACHEEN " 230. "1 " * Page 436 of 722 APPENDIX I – SWITCHING SEQUENCES 11_BND-BEL3230_ADY-BEL1_115_RAS4.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #3 and Addy - Bell #1 115 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Boundary - Bell #3 230 kV Line DL 64.0 "BELL S3 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&A" 230. "1 " DL 64.0 "BOUNDARY" 230. "ADDY 2&A" 230. "1 " DB 64.0 "ADDY 2 " 230. * * Trip Addy - Bell #1 115 kV Line * The conservative option for this contingency is to only trip the 230/115 kV bank * This option results in maximum post contingency loading on the remaining lines * (for north to south flows). DL 64.0 "ADDY 2 " 230. "ADDY " 115. "1 " * * For DLO's South of Boundary, Drop Boundary Gen so that post outage gen < 650 MW * Starting Gen = 968 MW, Trip Units 55 & 56. Remaining Gen = 592 MW * * Shed unit 1 at 46464 BOUNDARY 14.40 148 MW *TG 76.0 "BOUNDG51" 14.4 "51 " * * Shed unit 2 at 46466 BOUNDARY 14.40 148 MW *TG 76.0 "BOUNDG52" 14.4 "52 " * * Shed unit 3 at 46468 BOUNDARY 14.40 148 MW *TG 76.0 "BOUNDG53" 14.4 "53 " * * Shed unit 4 at 46470 BOUNDARY 14.40 148 MW *TG 76.0 "BOUNDG54" 14.4 "54 " Page 437 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 5 at 46472 BOUNDRY2 14.40 188 MW TG 76.0 "BOUNDG55" 14.4 "55 " * * Shed unit 6 at 46474 BOUNDRY2 14.40 188 MW TG 76.0 "BOUNDG56" 14.4 "56 " * Page 438 of 722 APPENDIX I – SWITCHING SEQUENCES Crn-Sel500_RAS_LSp2_M.swt RUN * * Cranbrook - Selkirk 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Cranbrook 500 kV Line DL 64.0 "SEL500 " 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "f" "D" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Shed units 4 and 5 at 46470 and 40472 BOUNDRY2 14.40 (148 MW and 188 MW) TG 76.0 "BOUNDG54" 14.4 "54" TG 76.0 "BOUNDG55" 14.4 "55" * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " Page 439 of 722 APPENDIX I – SWITCHING SEQUENCES DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ** the following assumes svds at 50838 and 51364 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch on 12 MVAr ** reactors at CBK T7 12.6 kV bus 50838 and CBK T6 12.6 kV bus 51364, if necessary **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) **MBS 108. "CBK T7 " 12.6 "b2" "R" **MBS 108. "CBK T6 " 12.6 "b2" "R" * ** the following assumes svd at 51352 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch on 75 MVAr ** reactor at CBK T2 12.6 kV bus 51352 **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) **MBS 126. "CBK T2 " 12.6 "b0" "R" * * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 440 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr12_500_RAS_LSp3_BC4.swt RUN * * Custer - Monroe #1 and #2 500 kV Lines * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 66.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 66.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Langdon - Cranbrook 500 kV Line DL 71.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 71.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 71.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 72.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip Williston - Glenannan 500 kV Line (to separate Alcan GLN from BCTC) *DL 72.0 "WSN500 " 500. "GLN500 " 500. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 76.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 77.0 "POCATER7" 138. "FRO T274" 138. "1 " * Page 441 of 722 APPENDIX I – SWITCHING SEQUENCES * actual generation shedding is 336 MW * Shed unit 46470 (BOUNDG54 14.4 kV, 148 MW) TG 78.0 "BOUNDG54" 14.4 "54" * * Shed unit 46472 (BOUNDG55 14.4 kV, 188 MW) TG 78.0 "BOUNDG55" 14.4 "55" * * * Trip Gens - Producing +1000 VARS While Voltage is High TG 90.0 "VIT SC1 " 12.70 "1 " TG 90.0 "VIT SC2 " 12.70 "1 " TG 90.0 "VIT SC3 " 12.60 "1 " TG 90.0 "VIT SC4 " 12.60 "1 " TG 92.0 "KLY SC2 " 12.50 "1 " * * Add Available Shunt Reactors to Bring system voltage down * * MBS 150.0 "NIC500 " 500. "b1" "C" 0.0 -2.45000 MBS 160.0 "ACK500 " 500. "r2" "C" 0.0 -1.22500 MBS 170.0 "KLY500 " 500. "r5" "C" 0.0 -1.22500 MBS 180.0 "KLY500 " 500. "r4" "C" 0.0 -1.22500 MBS 190.0 "ACK500 " 500. "r3" "C" 0.0 -1.22500 Page 442 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr12_500_RAS_LSp3_MBC4.swt RUN * * Custer - Monroe #1 and #2 500 kV Lines * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 66.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 66.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Langdon - Cranbrook 500 kV Line DL 71.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 71.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 71.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 72.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip Williston - Glenannan 500 kV Line (to separate Alcan GLN from BCTC) *DL 72.0 "WSN500 " 500. "GLN500 " 500. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 76.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 77.0 "POCATER7" 138. "FRO T274" 138. "1 " * Page 443 of 722 APPENDIX I – SWITCHING SEQUENCES * actual generation shedding is 336 MW * Shed unit 46470 (BOUNDG54 14.4 kV, 148 MW) TG 78.0 "BOUNDG54" 14.4 "54" * * Shed unit 46472 (BOUNDG55 14.4 kV, 188 MW) TG 78.0 "BOUNDG55" 14.4 "55" * * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * * * Trip Gens - Producing +1000 VARS While Voltage is High TG 90.0 "VIT SC1 " 12.70 "1 " TG 90.0 "VIT SC2 " 12.70 "1 " TG 90.0 "VIT SC3 " 12.60 "1 " TG 90.0 "VIT SC4 " 12.60 "1 " TG 92.0 "KLY SC2 " 12.50 "1 " * * Add Available Shunt Reactors to Bring system voltage down * * MBS 150.0 "NIC500 " 500. "b1" "C" 0.0 -2.45000 MBS 160.0 "ACK500 " 500. "r2" "C" 0.0 -1.22500 MBS 170.0 "KLY500 " 500. "r5" "C" 0.0 -1.22500 MBS 180.0 "KLY500 " 500. "r4" "C" 0.0 -1.22500 MBS 190.0 "ACK500 " 500. "r3" "C" 0.0 -1.22500 * Page 444 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr500.swt RUN * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 445 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_LSp.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * actual generation shedding is 336 MW * Shed unit at 46470 (BOUNDG54 14.4 kV, 148 MW) TG 76.0 "BOUNDG54" 14.4 "54" * Shed unit at 46472 (BOUNDG55 14.4 kV, 188 MW) TG 76.0 "BOUNDG55" 14.4 "55" * Page 446 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_LSp3_IV31av1_BC4.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip Williston - Glenannan 500 kV Line (to separate Alcan GLN from BCTC) ****DL 70.0 "WSN500 " 500. "GLN500 " 500. "1 " This Not in bctc_simul_SWsequence_dbl_ctg_rsh.xls bctc_IV31av1 - - - Why is this here ???? * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * actual generation shedding is 336 MW * Shed unit at 46470 (BOUNDG54 14.4 kV, 148 MW) TG 76.0 "BOUNDG54" 14.4 "54" * Shed unit at 46472 (BOUNDG55 14.4 kV, 188 MW) TG 76.0 "BOUNDG55" 14.4 "55" Page 447 of 722 APPENDIX I – SWITCHING SEQUENCES * * * Trip Gens - Producing +1000 VARS While Voltage is High TG 90.0 "VIT SC1 " 12.70 "1 " TG 90.0 "VIT SC2 " 12.70 "1 " TG 90.0 "VIT SC3 " 12.60 "1 " TG 90.0 "VIT SC4 " 12.60 "1 " TG 92.0 "KLY SC2 " 12.50 "1 " * * Add Available Shunt Reactors to Bring system voltage down * * MBS 150.0 "NIC500 " 500. "b1" "C" 0.0 -2.45000 MBS 160.0 "ACK500 " 500. "r2" "C" 0.0 -1.22500 MBS 170.0 "KLY500 " 500. "r5" "C" 0.0 -1.22500 MBS 180.0 "KLY500 " 500. "r4" "C" 0.0 -1.22500 MBS 190.0 "ACK500 " 500. "r3" "C" 0.0 -1.22500 * Page 448 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_LSp3_M.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip Williston - Glenannan 500 kV Line (to separate Alcan GLN from BCTC) DL 70.0 "WSN500 " 500. "GLN500 " 500. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * actual generation shedding is 336 MW * Shed unit at 46470 (BOUNDG54 14.4 kV, 148 MW) TG 76.0 "BOUNDG54" 14.4 "54" * Shed unit at 46472 (BOUNDG55 14.4 kV, 188 MW) TG 76.0 "BOUNDG55" 14.4 "55" * Page 449 of 722 APPENDIX I – SWITCHING SEQUENCES * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 450 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_LSp3_MBC4.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip Williston - Glenannan 500 kV Line (to separate Alcan GLN from BCTC) ****DL 70.0 "WSN500 " 500. "GLN500 " 500. "1 " This Not in bctc_simul_SWsequence_dbl_ctg_rsh.xls bctc_IV31av1 - - - Why is this here ???? * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * actual generation shedding is 336 MW * Shed unit at 46470 (BOUNDG54 14.4 kV, 148 MW) TG 76.0 "BOUNDG54" 14.4 "54" * Shed unit at 46472 (BOUNDG55 14.4 kV, 188 MW) TG 76.0 "BOUNDG55" 14.4 "55" Page 451 of 722 APPENDIX I – SWITCHING SEQUENCES * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * * * Trip Gens - Producing +1000 VARS While Voltage is High TG 90.0 "VIT SC1 " 12.70 "1 " TG 90.0 "VIT SC2 " 12.70 "1 " TG 90.0 "VIT SC3 " 12.60 "1 " TG 90.0 "VIT SC4 " 12.60 "1 " TG 92.0 "KLY SC2 " 12.50 "1 " * * Add Available Shunt Reactors to Bring system voltage down * * MBS 150.0 "NIC500 " 500. "b1" "C" 0.0 -2.45000 MBS 160.0 "ACK500 " 500. "r2" "C" 0.0 -1.22500 MBS 170.0 "KLY500 " 500. "r5" "C" 0.0 -1.22500 MBS 180.0 "KLY500 " 500. "r4" "C" 0.0 -1.22500 MBS 190.0 "ACK500 " 500. "r3" "C" 0.0 -1.22500 * Page 452 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_LSp2_IV31av1.swt RUN * * Langdon - Cranbrook 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 64.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Shed units 4 and 5 at 46470 and 40472 BOUNDRY2 14.40 (148 MW and 188 MW) TG 76.0 "BOUNDG54" 14.4 "54" TG 76.0 "BOUNDG55" 14.4 "55" * Page 453 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_LSp2_M.swt RUN * * Langdon - Cranbrook 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 64.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Shed units 4 and 5 at 46470 and 40472 BOUNDRY2 14.40 (148 MW and 188 MW) TG 76.0 "BOUNDG54" 14.4 "54" TG 76.0 "BOUNDG55" 14.4 "55" * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 454 of 722 APPENDIX I – SWITCHING SEQUENCES Mtl-Mar230.swt RUN * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DB 64.0 "MATL_AB " 230. DB 64.0 "MATLN_&1" 230. * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 124.0 "MARIAS " 230. DB 124.0 "MATLN_&2" 230. * Page 455 of 722 APPENDIX I – SWITCHING SEQUENCES Nel-Bnd230_RAS_LSp.swt RUN * * Nelway - Boundary 230 kV Line * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * actual generation shedding is 336 MW * Shed unit 46470 (BOUNDG54 14.4 kV, 148 MW) TG 70.0 "BOUNDG54" 14.4 "54" * * Shed unit 46472 (BOUNDG55 14.4 kV, 188 MW) TG 70.0 "BOUNDG55" 14.4 "55" * Page 456 of 722 APPENDIX I – SWITCHING SEQUENCES PATH - 3: 07LSP - Post-Transient Analysis Analysis Page 457 of 722 APPENDIX I – SWITCHING SEQUENCES 10_BND-BEL1_BEL-USK_230_RAS.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #1 and Bell-Usk 230 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Bell - USK 230 kV Line DL 64.0 "BELL S&A" 230. "USK " 230. "1 " * Trip Boundary - Bell 230 kV Line DL 64.0 "BELL S1 " 230. "SACHEEN " 230. "1 " DL 64.0 "BOUNDARY" 230. "SACHEEN " 230. "1 " * Page 458 of 722 APPENDIX I – SWITCHING SEQUENCES 11_BND-BEL3230_ADY-BEL1_115_RAS2.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #3 and Addy - Bell #1 115 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Boundary - Bell #3 230 kV Line DL 64.0 "BELL S3 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&A" 230. "1 " DL 64.0 "BOUNDARY" 230. "ADDY 2&A" 230. "1 " * Trip Addy - Bell #1 115 kV Line * The conservative option for this contingency is to only trip the 230/115 kV bank * This option results in maximum post contingency loading on the remaining lines * (for north to south flows). DL 64.0 "ADDY 2 " 230. "ADDY " 115. "1 " Page 459 of 722 APPENDIX I – SWITCHING SEQUENCES 11_BND-BEL3230_ADY-BEL1_115_RAS4.swt RUN * * Last updated 11/02/2006 by TCL * Path 3 Dynamics IV-31 * * Boundary - Bell #3 and Addy - Bell #1 115 kV Lines with RAS * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Boundary 230 kV FB 60.0 "BOUNDARY" 230. * * Clear bus fault at Boundary 230 kV CFB 64.0 "BOUNDARY" 230. * * Trip Boundary - Bell #3 230 kV Line DL 64.0 "BELL S3 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&1" 230. "1 " DL 64.0 "ADDY 2 " 230. "ADDY 2&A" 230. "1 " DL 64.0 "BOUNDARY" 230. "ADDY 2&A" 230. "1 " DB 64.0 "ADDY 2 " 230. * * Trip Addy - Bell #1 115 kV Line * The conservative option for this contingency is to only trip the 230/115 kV bank * This option results in maximum post contingency loading on the remaining lines * (for north to south flows). DL 64.0 "ADDY 2 " 230. "ADDY " 115. "1 " * * For DLO's South of Boundary, Drop Boundary Gen so that post outage gen < 650 MW * Starting Gen = 968 MW, Trip Units 55 & 56. Remaining Gen = 592 MW * * Shed unit 1 at 46464 BOUNDARY 14.40 148 MW *TG 76.0 "BOUNDG51" 14.4 "51 " * * Shed unit 2 at 46466 BOUNDARY 14.40 148 MW *TG 76.0 "BOUNDG52" 14.4 "52 " * * Shed unit 3 at 46468 BOUNDARY 14.40 148 MW *TG 76.0 "BOUNDG53" 14.4 "53 " * * Shed unit 4 at 46470 BOUNDARY 14.40 148 MW *TG 76.0 "BOUNDG54" 14.4 "54 " Page 460 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 5 at 46472 BOUNDRY2 14.40 188 MW TG 76.0 "BOUNDG55" 14.4 "55 " * * Shed unit 6 at 46474 BOUNDRY2 14.40 188 MW TG 76.0 "BOUNDG56" 14.4 "56 " * Page 461 of 722 APPENDIX I – SWITCHING SEQUENCES Crn-Sel500_RAS_LSp2.swt RUN * * Cranbrook - Selkirk 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Cranbrook 500 kV Line DL 64.0 "SEL500 " 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "f" "D" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Shed units 4 and 5 at 46470 and 40472 BOUNDRY2 14.40 (148 MW and 188 MW) TG 76.0 "BOUNDG54" 14.4 "54" TG 76.0 "BOUNDG55" 14.4 "55" * ** the following assumes svds at 50838 and 51364 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch on 12 MVAr ** reactors at CBK T7 12.6 kV bus 50838 and CBK T6 12.6 kV bus 51364, if necessary Page 462 of 722 APPENDIX I – SWITCHING SEQUENCES **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) **MBS 108. "CBK T7 " 12.6 "b2" "R" **MBS 108. "CBK T6 " 12.6 "b2" "R" * ** the following assumes svd at 51352 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch on 75 MVAr ** reactor at CBK T2 12.6 kV bus 51352 **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) **MBS 126. "CBK T2 " 12.6 "b0" "R" * * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 463 of 722 APPENDIX I – SWITCHING SEQUENCES Crn-Sel500_RAS_LSp2_M.swt RUN * * Cranbrook - Selkirk 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Selkirk 500 kV FB 60.0 "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 64.0 "SEL500 " 500. * * Trip Selkirk - Cranbrook 500 kV Line DL 64.0 "SEL500 " 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " 1 "f" "D" * * Disconnect remaining 122.5 MVAR of shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b " "D" * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Shed units 4 and 5 at 46470 and 40472 BOUNDRY2 14.40 (148 MW and 188 MW) TG 76.0 "BOUNDG54" 14.4 "54" TG 76.0 "BOUNDG55" 14.4 "55" * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " Page 464 of 722 APPENDIX I – SWITCHING SEQUENCES DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * ** the following assumes svds at 50838 and 51364 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch on 12 MVAr ** reactors at CBK T7 12.6 kV bus 50838 and CBK T6 12.6 kV bus 51364, if necessary **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) **MBS 108. "CBK T7 " 12.6 "b2" "R" **MBS 108. "CBK T6 " 12.6 "b2" "R" * ** the following assumes svd at 51352 converted to shunt devices ** if CBK230 voltage is greater than 1.08 pu, then switch on 75 MVAr ** reactor at CBK T2 12.6 kV bus 51352 **MBS time bus_name kV shunt_id code MW(pu) MVAR(pu) **MBS 126. "CBK T2 " 12.6 "b0" "R" * * 3p reclosing, lead end SEL, Follow end CBK * Apply bus fault at Selkirk 500 kV FB 236. "SEL500 " 500. * * Clear bus fault at Selkirk 500 kV CFB 239. "SEL500 " 500. * Page 465 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr12_500_RAS_LSp.swt RUN * * Custer - Monroe #1 and #2 500 kV Lines * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 66.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 66.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Langdon - Cranbrook 500 kV Line DL 71.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 71.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 71.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 72.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 76.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 77.0 "POCATER7" 138. "FRO T274" 138. "1 " * * actual generation shedding is 336 MW * Shed unit 46470 (BOUNDG54 14.4 kV, 148 MW) TG 78.0 "BOUNDG54" 14.4 "54" Page 466 of 722 APPENDIX I – SWITCHING SEQUENCES * * Shed unit 46472 (BOUNDG55 14.4 kV, 188 MW) TG 78.0 "BOUNDG55" 14.4 "55" * Page 467 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr12_500_RAS_LSp3_M.swt RUN * * Custer - Monroe #1 and #2 500 kV Lines * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " DL 64.0 "CUSTER W" 500. "CUSTER&A" 500. "2 " DL 64.0 "CUSTER&A" 500. "MONROE " 500. "2 " * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 66.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 66.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Langdon - Cranbrook 500 kV Line DL 71.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 71.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 71.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 72.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip Williston - Glenannan 500 kV Line (to separate Alcan GLN from BCTC) DL 72.0 "WSN500 " 500. "GLN500 " 500. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 76.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 77.0 "POCATER7" 138. "FRO T274" 138. "1 " * Page 468 of 722 APPENDIX I – SWITCHING SEQUENCES * actual generation shedding is 336 MW * Shed unit 46470 (BOUNDG54 14.4 kV, 148 MW) TG 78.0 "BOUNDG54" 14.4 "54" * * Shed unit 46472 (BOUNDG55 14.4 kV, 188 MW) TG 78.0 "BOUNDG55" 14.4 "55" * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 469 of 722 APPENDIX I – SWITCHING SEQUENCES Cus-Mnr500.swt RUN * * Custer - Monroe #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Custer - Monroe #1 500 kV Line DL 64.0 "CUSTER W" 500. "CUSTER&1" 500. "1 " DL 64.0 "CUSTER&1" 500. "MONROE " 500. "1 " * Page 470 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus12_500_RAS_LSp3bctc_IV31av1_M.swt RUN * * Ingledow - Custer #1 and #2 500 kV Lines * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 and #2 500 kV Lines DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " DL 64.0 "CUSTER W" 500. "ING500 " 500. "2 " * * Trip Langdon - Cranbrook 500 kV Line DL 67.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 67.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 67.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip Williston - Glenannan 500 kV Line (to separate Alcan GLN from BCTC) ****DL 70.0 "WSN500 " 500. "GLN500 " 500. "1 " This Not in bctc_simul_SWsequence_dbl_ctg_rsh.xls bctc_IV31av1 - - - Why is this here ???? * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * actual generation shedding is 336 MW * Shed unit at 46470 (BOUNDG54 14.4 kV, 148 MW) TG 76.0 "BOUNDG54" 14.4 "54" * Shed unit at 46472 (BOUNDG55 14.4 kV, 188 MW) TG 76.0 "BOUNDG55" 14.4 "55" Page 471 of 722 APPENDIX I – SWITCHING SEQUENCES * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 472 of 722 APPENDIX I – SWITCHING SEQUENCES Ing-Cus500_RAS_LSp.swt RUN * * Ingledow - Custer #1 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Custer 500 kV FB 60.0 "CUSTER W" 500. * * Clear bus fault at Custer 500 kV CFB 64.0 "CUSTER W" 500. * * Trip Ingledow - Custer #1 500 kV Line DL 64.0 "CUSTER W" 500. "ING500 " 500. "1 " * Page 473 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_LSp.swt RUN * * Langdon - Cranbrook 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 64.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * Page 474 of 722 APPENDIX I – SWITCHING SEQUENCES Lgd-Crn500_RAS_LSp2_M.swt RUN * * Langdon - Cranbrook 500 kV Line * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at Langdon 500 kV FB 60.0 "LANGDON2" 500. * * Clear bus fault at Langdon 500 kV CFB 64.0 "LANGDON2" 500. * * Trip Langdon - Cranbrook 500 kV Line DL 64.0 "LANGDON2" 500. "CBK500 " 500. "1 " * * Disconnect 122.5 MVAR of line shunt reactance at Langbrook 500 kV MLS 64.0 "CBK500 " 500. "LANGDON2" 500. "1 " 1 "t" "D" * * Disconnect 122.5 MVAR of line shunt reactance at Cranbrook 500 kV MBS 64.0 "CBK500 " 500. "b " "C" 0.0 -1.225 * * Trip Nelway - Boundary 230 kV Line DL 70.0 "BOUNDARY" 230. "NLYPHS " 230. "1 " * * Trip COLEMAN7 - NTL138 138 kV Line DL 72.0 "COLEMAN7" 138. "NTL138 " 138. "1 " * * Trip POCATER7 - FRO T274 138 kV Line DL 73.0 "POCATER7" 138. "FRO T274" 138. "1 " * * Shed units 4 and 5 at 46470 and 40472 BOUNDRY2 14.40 (148 MW and 188 MW) TG 76.0 "BOUNDG54" 14.4 "54" TG 76.0 "BOUNDG55" 14.4 "55" * * Trip MATL Line DL 86.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 86.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DL 86.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 86.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 86.0 "MARIAS " 230. * Page 475 of 722 APPENDIX I – SWITCHING SEQUENCES Mtl-Mar230.swt RUN * * MATL PS to Marias 230 kV Line * Post-Project Only * * CC cards for post-transient only * CC DRP 0 * * Apply bus fault at MATL 240 kV FB 60.0 "MATL_AB " 240. * * Clear bus fault at MATL 240 kV CFB 64.0 "MATL_AB " 240. * * Trip MATL PS to Cutbank 230 kV Line DL 64.0 "MATL_AB " 240. "MATL_AB " 230. "1 " DL 64.0 "MATL_AB " 230. "MATLN_&1" 230. "1 " DL 64.0 "MATLN_&1" 230. "MARIAS " 230. "1 " DB 64.0 "MATL_AB " 230. DB 64.0 "MATLN_&1" 230. * * Trip Marias to Great Falls 230 kV Line DL 124.0 "MARIAS " 230. "MATLN_&2" 230. "1 " DL 124.0 "MATLN_&2" 230. "GT FALLS" 230. "1 " DB 124.0 "MARIAS " 230. DB 124.0 "MATLN_&2" 230. * Page 476 of 722 APPENDIX I – SWITCHING SEQUENCES Nel-Bnd230_RAS_LSp.swt RUN * * Nelway - Boundary 230 kV Line * * CC cards for post-transient only * CC DRP 336 * * Apply bus fault at Nelway 230 kV FB 60.0 "NLYPHS " 230. * * Clear bus fault at Nelway 230 kV CFB 66.0 "NLYPHS " 230. * * Trip Nelway - Boundry 230 kV Line DL 66.0 "NLYPHS " 230. "BOUNDARY" 230. "1 " * * actual generation shedding is 336 MW * Shed unit 46470 (BOUNDG54 14.4 kV, 148 MW) TG 70.0 "BOUNDG54" 14.4 "54" * * Shed unit 46472 (BOUNDG55 14.4 kV, 188 MW) TG 70.0 "BOUNDG55" 14.4 "55" * Page 477 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 8 - Non-Simultaneous 07 ??? – Pre – Project Switching Sequences Page 478 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500.swt **** CASE NUMBER **** 1010 RUN * CC DRP 1126 * FB 60.0 "BROADVU " 500.00 * CFB 63.0 "BROADVU " 500.00 DL 63.0 "BROADVU " 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN1 " 500.00 DB 63.0 "GAR1EAST" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 70.0 "COLSTP 1" 22.00 "1" MBL 70.0 "COLSTP 1" 22.00 "1" "D" MBL 70.0 "COLSTP 1" 22.00 "2" "D" * TG 71.0 "COLSTP 3" 26.00 "1" MBL 71.0 "COLSTP 3" 26.00 "1" "D" MBL 71.0 "COLSTP 3" 26.00 "2" "D" * MBL 78.5 "COLSTRP " 115.00 "c1" "R" * MBL 79.5 "COLSTRP " 230.00 "c3" "R" Page 479 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500_DL1.swt **** CASE NUMBER **** 1015 RUN * CC DRP 2056 * CC MSV 0.0 "COLSTP 2" 22.00 "1" 115.0 -1.0 * FB 60.0 "BROADVU " 500.00 * CFB 63.0 "BROADVU " 500.00 DL 63.0 "BROADVU " 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN1 " 500.00 DB 63.0 "GAR1EAST" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 68.0 "COLSTP 1" 22.00 "1" MBL 68.0 "COLSTP 1" 22.00 "1" "D" MBL 68.0 "COLSTP 1" 22.00 "2" "D" * TG 69.0 "COLSTP 3" 26.00 "1" MBL 69.0 "COLSTP 3" 26.00 "1" "D" MBL 69.0 "COLSTP 3" 26.00 "2" "D" * TG 69.0 "COLSTP 4" 26.00 "1" MBL 69.0 "COLSTP 4" 26.00 "1" "D" MBL 69.0 "COLSTP 4" 26.00 "2" "D" * TG 70.0 "HARDINGN" 13.80 "1" * MBL 76.5 "COLSTRP " 115.0 "c1" "R" * MBL 77.5 "COLSTRP " 230.0 "c3" "R" * MBL 77.5 "COLSTRP " 230.0 "c4" "R" Page 480 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500_DL2.swt **** CASE NUMBER **** 1015 RUN * CC DRP 0 * DL 63.0 "BROADVU " 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN2 " 500.00 DB 63.0 "GAR2EAST" 500.00 Page 481 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500_DLO.swt **** CASE NUMBER **** 1015 RUN * CC DRP 2056 * CC MSV 0.0 "COLSTP 2" 22.00 "1" 115.0 -1.0 * FB 60.0 "BROADVU " 500.00 * CFB 63.0 "BROADVU " 500.00 DL 63.0 "BROADVU " 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN1 " 500.00 DB 63.0 "GAR1EAST" 500.00 DL 63.0 "BROADVU " 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN2 " 500.00 DB 63.0 "GAR2EAST" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 68.0 "COLSTP 1" 22.00 "1" MBL 68.0 "COLSTP 1" 22.00 "1" "D" MBL 68.0 "COLSTP 1" 22.00 "2" "D" * TG 69.0 "COLSTP 3" 26.00 "1" MBL 69.0 "COLSTP 3" 26.00 "1" "D" MBL 69.0 "COLSTP 3" 26.00 "2" "D" * TG 69.0 "COLSTP 4" 26.00 "1" MBL 69.0 "COLSTP 4" 26.00 "1" "D" MBL 69.0 "COLSTP 4" 26.00 "2" "D" * TG 70.0 "HARDINGN" 13.80 "1" * MBL 76.5 "COLSTRP " 115.0 "c1" "R" * MBL 77.5 "COLSTRP " 230.0 "c3" "R" * MBL 77.5 "COLSTRP " 230.0 "c4" "R" Page 482 of 722 APPENDIX I – SWITCHING SEQUENCES COLSTRIP_BROADVIEW_500.swt **** CASE NUMBER **** 1009 RUN * CC DRP 796 * FB 60.0 "COLSTRP " 500.00 * CFB 63.0 "COLSTRP " 500.00 DL 63.0 "COLSTRP " 500.00 "BROADV&1" 500.00 "1" DL 63.0 "BROADVU " 500.00 "BROADV&1" 500.00 "1" * TG 75.0 "COLSTP 3" 26.00 "1" MBL 75.0 "COLSTP 3" 26.00 "1" "D" MBL 75.0 "COLSTP 3" 26.00 "2" "D" * MBL 83.5 "COLSTRP " 230.00 "c3" "R" Page 483 of 722 APPENDIX I – SWITCHING SEQUENCES CRANBROOK_SELKIRK_500.swt **** CASE NUMBER **** 1013 RUN * CC DRP 0 * FB 60.0 "SEL500 " 500.00 * CFB 64.0 "SEL500 " 500.00 DL 64.0 "SEL500 " 500.00 "CBK500 " 500.00 "1" MBS 64.0 "CBK500 " 500.00 "b2" "D" * DL 67.0 "LANGDON2" 500.00 "CBK500 " 500.00 "1" MLS 67.0 "CBK500 " 500.00 "LANGDON2" 500.00 "1" 1 "t" "D" MBS 67.0 "CBK500 " 500.00 "b1" "D" * DL 72.0 "COLEMAN7" 138.00 "NTL138 " 138.00 "1" * DL 73.0 "POCATER7" 138.00 "FRO T274" 138.00 "1" * FB 236.0 "SEL500 " 500.00 * CFB 239.0 "SEL500 " 500.00 Page 484 of 722 APPENDIX I – SWITCHING SEQUENCES CUTBANK_GREAT_FALLS_230.swt **** CASE NUMBER **** 1002 RUN * CC DRP 0 * FB 60.0 "MARIAS " 230.00 * CFB 64.0 "MARIAS " 230.00 DL 64.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 64.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 64.0 "MATLN_&2" 230.00 * DL 124.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 124.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 124.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 124.0 "MATL_AB " 230.00 DB 124.0 "MATLN_&1" 230.00 DB 124.0 "MARIAS " 230.00 Page 485 of 722 APPENDIX I – SWITCHING SEQUENCES FLAT_RUN.swt **** CASE NUMBER **** 0 RUN Page 486 of 722 APPENDIX I – SWITCHING SEQUENCES GARRISON_TAFT_500.swt **** CASE NUMBER **** 1011 RUN * CC DRP 1321 * FB 60.0 "GARRISON" 500.00 FC 60.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 FC 60.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 * CFB 63.0 "GARRISON" 500.00 RC 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 RC 63.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 DL 63.0 "GARRIS&2" 500.00 "TAFT " 500.00 "1" DL 63.0 "GARRIS&2" 500.00 "GARRIS&1" 500.00 "1" DL 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" DB 63.0 "GARRIS&1" 500.00 DB 63.0 "GARRIS&2" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 70.0 "COLSTP 1" 22.00 "1" MBL 70.0 "COLSTP 1" 22.00 "1" "D" MBL 70.0 "COLSTP 1" 22.00 "2" "D" * TG 71.0 "COLSTP 3" 26.00 "1" MBL 71.0 "COLSTP 3" 26.00 "1" "D" MBL 71.0 "COLSTP 3" 26.00 "2" "D" * MBL 71.0 "MILCTYDC" 230.00 "D1" "D" MBS 71.0 "MILCTYDC" 230.00 "b " "D" MBS 71.0 "MILCTYDC" 230.00 "b1" "D" * MBL 78.5 "COLSTRP " 115.00 "c1" "R" * MBS 79.0 "ROSEBUD " 230.00 "b1" "R" MBS 79.0 "CUSTER " 230.00 "b1" "R" MBS 79.0 "CUSTER " 230.00 "b2" "R" * MBL 79.5 "COLSTRP " 230.00 "c3" "R" Page 487 of 722 APPENDIX I – SWITCHING SEQUENCES GARRISON_TAFT_500_DLO.swt **** CASE NUMBER **** 1016 RUN * CC DRP 2142 * CC MSV 0.0 "COLSTP 2" 22.00 "1" 115.0 -1.0 * FB 60.0 "GARRISON" 500.00 FC 60.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 FC 60.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 * CFB 63.0 "GARRISON" 500.00 RC 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 RC 63.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 DL 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" DL 63.0 "GARRIS&2" 500.00 "GARRIS&1" 500.00 "1" DL 63.0 "GARRIS&2" 500.00 "TAFT " 500.00 "1" DB 63.0 "GARRIS&1" 500.00 DB 63.0 "GARRIS&2" 500.00 DL 63.0 "GARRIS&B" 500.00 "TAFT " 500.00 "2" DL 63.0 "GARRIS&B" 500.00 "GARRIS&A" 500.00 "2" DL 63.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" DB 63.0 "GARRIS&A" 500.00 DB 63.0 "GARRIS&B" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 69.2 "COLSTP 1" 22.00 "1" MBL 69.2 "COLSTP 1" 22.00 "1" "D" MBL 69.2 "COLSTP 1" 22.00 "2" "D" * TG 70.2 "COLSTP 3" 26.00 "1" MBL 70.2 "COLSTP 3" 26.00 "1" "D" MBL 70.2 "COLSTP 3" 26.00 "2" "D" * TG 70.2 "COLSTP 4" 26.00 "1" MBL 70.2 "COLSTP 4" 26.00 "1" "D" MBL 70.2 "COLSTP 4" 26.00 "2" "D" * MBL 71.0 "MILCTYDC" 230.00 "D1" "D" MBS 71.0 "MILCTYDC" 230.00 "b " "D" MBS 71.0 "MILCTYDC" 230.00 "b1" "D" * MBL 77.7 "COLSTRP " 115.00 "c1" "R" * Page 488 of 722 APPENDIX I – SWITCHING SEQUENCES MBL * MBL * MBS MBS MBS 78.7 "COLSTRP " 230.00 "c3" "R" 78.7 "COLSTRP " 230.00 "c4" "R" 79.0 "ROSEBUD " 230.00 "b1" "R" 79.0 "CUSTER " 230.00 "b1" "R" 79.0 "CUSTER " 230.00 "b2" "R" Page 489 of 722 APPENDIX I – SWITCHING SEQUENCES GREAT_FALLS_JUDITH_GAP_S_230.swt **** CASE NUMBER **** 1003 RUN * CC DRP 0 * FB 60.0 "GT FALLS" 230.00 * CFB 66.0 "GT FALLS" 230.00 DL 66.0 "GT FALLS" 230.00 "STH_TAP " 230.00 "1" DL 66.0 "STH_TAP " 230.00 "JUDITHGP" 230.00 "1" DL 66.0 "JUDITHGP" 230.00 "JUDITHSO" 230.00 "1" DL 66.0 "JUDITHGP" 230.00 "JUDITHGP" 100.00 "1" Page 490 of 722 APPENDIX I – SWITCHING SEQUENCES GREAT_FALLS_LANDERS_FORK_230.swt **** CASE NUMBER **** 1005 RUN * CC DRP 0 * FB 60.0 "GT FALLS" 230.00 * CFB 66.0 "GT FALLS" 230.00 DL 66.0 "LANDRSFK" 230.00 "GT FALLS" 230.00 "1" DL 66.0 "LANDRSFK" 230.00 "OVANDO " 230.00 "1" Page 491 of 722 APPENDIX I – SWITCHING SEQUENCES JUDITH_GAP_S_BROADVIEW_230.swt **** CASE NUMBER **** 1004 RUN * CC DRP 0 * FB 60.0 "JUDITHSO" 230.00 * CFB 66.0 "JUDITHSO" 230.00 DL 66.0 "JUDITHSO" 230.00 "BROADVU " 230.00 "1" Page 492 of 722 APPENDIX I – SWITCHING SEQUENCES LANDERS_FORK_OVANDO_230.swt **** CASE NUMBER **** 1006 RUN * CC DRP 0 * FB 60.0 "LANDRSFK" 230.00 * CFB 66.0 "LANDRSFK" 230.00 DL 66.0 "LANDRSFK" 230.00 "GT FALLS" 230.00 "1" DL 66.0 "LANDRSFK" 230.00 "OVANDO " 230.00 "1" Page 493 of 722 APPENDIX I – SWITCHING SEQUENCES LANGDON_CRANBROOK_500.swt **** CASE NUMBER **** 1012 RUN * CC DRP 0 * FB 60.0 "LANGDON2" 500.00 * CFB 64.0 "LANGDON2" 500.00 DL 64.0 "LANGDON2" 500.00 "CBK500 " 500.00 "1" MLS 64.0 "CBK500 " 500.00 "LANGDON2" 500.00 "1" 1 "t" "D" MBS 64.0 "CBK500 " 500.00 "b2" "D" * DL 72.0 "COLEMAN7" 138.00 "NTL138 " 138.00 "1" * DL 73.0 "POCATER7" 138.00 "FRO T274" 138.00 "1" Page 494 of 722 APPENDIX I – SWITCHING SEQUENCES MATL_PS_CUTBANK_230.swt **** CASE NUMBER **** 1001 RUN * CC DRP 0 * FB 60.0 "MATL_AB " 240.00 * CFB 64.0 "MATL_AB " 240.00 DL 64.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 64.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 64.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 64.0 "MATL_AB " 230.00 DB 64.0 "MATLN_&1" 230.00 * DL 124.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 124.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 124.0 "MARIAS " 230.00 DB 124.0 "MATLN_&2" 230.00 Page 495 of 722 APPENDIX I – SWITCHING SEQUENCES OVANDO_GARRISON_230.swt **** CASE NUMBER **** 1008 RUN * CC DRP 0 * FB 60.0 "OVANDO " 230.00 * CFB 66.0 "OVANDO " 230.00 DL 66.0 "OVANDO " 230.00 "GARRISON" 230.00 "1" Page 496 of 722 APPENDIX I – SWITCHING SEQUENCES OVANDO_HOT_SPRINGS_230.swt **** CASE NUMBER **** 1007 RUN * CC DRP 0 * FB 60.0 "OVANDO " 230.00 * CFB 66.0 "OVANDO " 230.00 DL 66.0 "OVANDO " 230.00 "HOT SPR " 230.00 "1" Page 497 of 722 APPENDIX I – SWITCHING SEQUENCES TAFT_500_BREAKER_FAILURE.swt **** CASE NUMBER **** 1017 RUN * CC DRP 1706 * FB 60.0 "TAFT " 500.00 0.00249 0.02685 * DL 64.0 "TAFT " 500.00 "BELL S&1" 500.00 "1" DL 64.0 "BELL S&1" 500.00 "BELL SC " 500.00 "1" DL 64.0 "BELL SC " 500.00 "BELL BPA" 500.00 "1" RL 64.0 "TAFT " 500.00 "BELL S&1" 500.00 "2P" RL 64.0 "BELL S&1" 500.00 "BELL SC " 500.00 "2P" RL 64.0 "BELL SC " 500.00 "BELL BPA" 500.00 "2P" * CFB 72.0 "TAFT " 500.00 DL 72.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" DL 72.0 "GARRIS&1" 500.00 "GARRIS&2" 500.00 "1" DL 72.0 "GARRIS&2" 500.00 "TAFT " 500.00 "1" DL 72.0 "TAFT " 500.00 "BELL S&1" 500.00 "2P" DL 72.0 "BELL S&1" 500.00 "BELL SC " 500.00 "2P" DL 72.0 "BELL SC " 500.00 "BELL BPA" 500.00 "2P" * TG 72.4 "COLSTP 1" 22.00 "1" MBL 72.4 "COLSTP 1" 22.00 "1" "D" MBL 72.4 "COLSTP 1" 22.00 "2" "D" * TG 73.4 "COLSTP 3" 26.00 "1" MBL 73.4 "COLSTP 3" 26.00 "1" "D" MBL 73.4 "COLSTP 3" 26.00 "2" "D" * MBS 76.5 "GARRISON" 500.00 "b1" "D" * TG 78.0 "LIB 01 " 13.80 "1" TG 78.0 "LIB 02 " 13.80 "2" TG 78.0 "LIB 03 " 13.80 "3" TG 78.0 "LIB 04 " 13.80 "4" TG 78.0 "LIB 05 " 13.80 "5" * MBL 80.9 "COLSTRP " 115.00 "c1" "R" * MBL 81.9 "COLSTRP " 230.00 "c3" "R" Page 498 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 8 - Non-Simultaneous 07 ??? – MATL - North-to-South Switching Sequences Page 499 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500.swt **** CASE NUMBER **** 1010 RUN * CC DRP 796 * FB 60.0 "BROADVU " 500.00 * CFB 63.0 "BROADVU " 500.00 DL 63.0 "BROADVU " 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN1 " 500.00 DB 63.0 "GAR1EAST" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 75.0 "COLSTP 3" 26.00 "1" MBL 75.0 "COLSTP 3" 26.00 "1" "D" MBL 75.0 "COLSTP 3" 26.00 "2" "D" * MBL 83.5 "COLSTRP " 230.00 "c3" "R" Page 500 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500_DL1.swt **** CASE NUMBER **** 1015 RUN * CC DRP 2056 * CC MSV 0.0 "COLSTP 2" 22.00 "1" 115.0 -1.0 * FB 60.0 "BROADVU " 500.00 * CFB 63.0 "BROADVU " 500.00 DL 63.0 "BROADVU " 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN1 " 500.00 DB 63.0 "GAR1EAST" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 68.4 "COLSTP 1" 22.00 "1" MBL 68.4 "COLSTP 1" 22.00 "1" "D" MBL 68.4 "COLSTP 1" 22.00 "2" "D" * TG 69.4 "COLSTP 3" 26.00 "1" MBL 69.4 "COLSTP 3" 26.00 "1" "D" MBL 69.4 "COLSTP 3" 26.00 "2" "D" * TG 69.4 "COLSTP 4" 26.00 "1" MBL 69.4 "COLSTP 4" 26.00 "1" "D" MBL 69.4 "COLSTP 4" 26.00 "2" "D" * TG 70.0 "HARDINGN" 13.80 "1" * MBL 76.9 "COLSTRP " 115.0 "c1" "R" * MBL 77.9 "COLSTRP " 230.0 "c3" "R" * MBL 77.9 "COLSTRP " 230.0 "c4" "R" Page 501 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500_DL2.swt **** CASE NUMBER **** 1015 RUN * CC DRP 0 * DL 63.0 "BROADVU " 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN2 " 500.00 DB 63.0 "GAR2EAST" 500.00 Page 502 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500_DLO.swt **** CASE NUMBER **** 1015 RUN * CC DRP 2056 * CC MSV 0.0 "COLSTP 2" 22.00 "1" 115.0 -1.0 * FB 60.0 "BROADVU " 500.00 * CFB 63.0 "BROADVU " 500.00 DL 63.0 "BROADVU " 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN1 " 500.00 DB 63.0 "GAR1EAST" 500.00 DL 63.0 "BROADVU " 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN2 " 500.00 DB 63.0 "GAR2EAST" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 68.4 "COLSTP 1" 22.00 "1" MBL 68.4 "COLSTP 1" 22.00 "1" "D" MBL 68.4 "COLSTP 1" 22.00 "2" "D" * TG 69.4 "COLSTP 3" 26.00 "1" MBL 69.4 "COLSTP 3" 26.00 "1" "D" MBL 69.4 "COLSTP 3" 26.00 "2" "D" * TG 69.4 "COLSTP 4" 26.00 "1" MBL 69.4 "COLSTP 4" 26.00 "1" "D" MBL 69.4 "COLSTP 4" 26.00 "2" "D" * TG 70.0 "HARDINGN" 13.80 "1" * MBL 76.9 "COLSTRP " 115.0 "c1" "R" * MBL 77.9 "COLSTRP " 230.0 "c3" "R" * MBL 77.9 "COLSTRP " 230.0 "c4" "R" Page 503 of 722 APPENDIX I – SWITCHING SEQUENCES COLSTRIP_BROADVIEW_500.swt **** CASE NUMBER **** 1009 RUN * CC DRP 0 * FB 60.0 "COLSTRP " 500.00 * CFB 63.0 "COLSTRP " 500.00 DL 63.0 "COLSTRP " 500.00 "BROADV&1" 500.00 "1" DL 63.0 "BROADVU " 500.00 "BROADV&1" 500.00 "1" Page 504 of 722 APPENDIX I – SWITCHING SEQUENCES CRANBROOK_SELKIRK_500.swt **** CASE NUMBER **** 1013 RUN * CC DRP 0 * FB 60.0 "SEL500 " 500.00 * CFB 64.0 "SEL500 " 500.00 DL 64.0 "SEL500 " 500.00 "CBK500 " 500.00 "1" MBS 64.0 "CBK500 " 500.00 "b2" "D" * DL 67.0 "LANGDON2" 500.00 "CBK500 " 500.00 "1" MLS 67.0 "CBK500 " 500.00 "LANGDON2" 500.00 "1" 1 "t" "D" MBS 67.0 "CBK500 " 500.00 "b1" "D" * DL 72.0 "COLEMAN7" 138.00 "NTL138 " 138.00 "1" * DL 73.0 "POCATER7" 138.00 "FRO T274" 138.00 "1" * DL 86.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 86.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 86.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 86.0 "MATL_AB " 230.00 DB 86.0 "MATLN_&1" 230.00 DL 86.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 86.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 86.0 "MARIAS " 230.00 DB 86.0 "MATLN_&2" 230.00 * FB 236.0 "SEL500 " 500.00 * CFB 239.0 "SEL500 " 500.00 Page 505 of 722 APPENDIX I – SWITCHING SEQUENCES CUTBANK_GREAT_FALLS_230.swt **** CASE NUMBER **** 1002 RUN * CC DRP 0 * FB 60.0 "MARIAS " 230.00 * CFB 64.0 "MARIAS " 230.00 DL 64.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 64.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 64.0 "MATLN_&2" 230.00 * DL 124.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 124.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 124.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 124.0 "MATL_AB " 230.00 DB 124.0 "MATLN_&1" 230.00 DB 124.0 "MARIAS " 230.00 Page 506 of 722 APPENDIX I – SWITCHING SEQUENCES FLAT_RUN.swt **** CASE NUMBER **** 0 RUN Page 507 of 722 APPENDIX I – SWITCHING SEQUENCES GARRISON_TAFT_500.swt **** CASE NUMBER **** 1011 RUN * CC DRP 1321 * FB 60.0 "GARRISON" 500.00 FC 60.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 FC 60.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 * CFB 63.0 "GARRISON" 500.00 RC 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 RC 63.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 DL 63.0 "GARRIS&2" 500.00 "TAFT " 500.00 "1" DL 63.0 "GARRIS&2" 500.00 "GARRIS&1" 500.00 "1" DL 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" DB 63.0 "GARRIS&1" 500.00 DB 63.0 "GARRIS&2" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 70.0 "COLSTP 1" 22.00 "1" MBL 70.0 "COLSTP 1" 22.00 "1" "D" MBL 70.0 "COLSTP 1" 22.00 "2" "D" * TG 71.0 "COLSTP 3" 26.00 "1" MBL 71.0 "COLSTP 3" 26.00 "1" "D" MBL 71.0 "COLSTP 3" 26.00 "2" "D" * MBL 71.0 "MILCTYDC" 230.00 "D1" "D" MBS 71.0 "MILCTYDC" 230.00 "b " "D" MBS 71.0 "MILCTYDC" 230.00 "b1" "D" * MBL 78.5 "COLSTRP " 115.00 "c1" "R" * MBS 79.0 "ROSEBUD " 230.00 "b1" "R" MBS 79.0 "CUSTER " 230.00 "b1" "R" MBS 79.0 "CUSTER " 230.00 "b2" "R" * MBL 79.5 "COLSTRP " 230.00 "c3" "R" Page 508 of 722 APPENDIX I – SWITCHING SEQUENCES GARRISON_TAFT_500_DLO.swt **** CASE NUMBER **** 1016 RUN * CC DRP 2142 * CC MSV 0.0 "COLSTP 2" 22.00 "1" 115.0 -1.0 * FB 60.0 "GARRISON" 500.00 FC 60.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 FC 60.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 * CFB 63.0 "GARRISON" 500.00 RC 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 RC 63.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 DL 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" DL 63.0 "GARRIS&2" 500.00 "GARRIS&1" 500.00 "1" DL 63.0 "GARRIS&2" 500.00 "TAFT " 500.00 "1" DB 63.0 "GARRIS&1" 500.00 DB 63.0 "GARRIS&2" 500.00 DL 63.0 "GARRIS&B" 500.00 "TAFT " 500.00 "2" DL 63.0 "GARRIS&B" 500.00 "GARRIS&A" 500.00 "2" DL 63.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" DB 63.0 "GARRIS&A" 500.00 DB 63.0 "GARRIS&B" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 69.2 "COLSTP 1" 22.00 "1" MBL 69.2 "COLSTP 1" 22.00 "1" "D" MBL 69.2 "COLSTP 1" 22.00 "2" "D" * TG 70.2 "COLSTP 3" 26.00 "1" MBL 70.2 "COLSTP 3" 26.00 "1" "D" MBL 70.2 "COLSTP 3" 26.00 "2" "D" * TG 70.2 "COLSTP 4" 26.00 "1" MBL 70.2 "COLSTP 4" 26.00 "1" "D" MBL 70.2 "COLSTP 4" 26.00 "2" "D" * MBL 71.0 "MILCTYDC" 230.00 "D1" "D" MBS 71.0 "MILCTYDC" 230.00 "b " "D" MBS 71.0 "MILCTYDC" 230.00 "b1" "D" * MBL 77.7 "COLSTRP " 115.00 "c1" "R" * Page 509 of 722 APPENDIX I – SWITCHING SEQUENCES MBL * MBL * MBS MBS MBS 78.7 "COLSTRP " 230.00 "c3" "R" 78.7 "COLSTRP " 230.00 "c4" "R" 79.0 "ROSEBUD " 230.00 "b1" "R" 79.0 "CUSTER " 230.00 "b1" "R" 79.0 "CUSTER " 230.00 "b2" "R" Page 510 of 722 APPENDIX I – SWITCHING SEQUENCES GREAT_FALLS_JUDITH_GAP_S_230.swt **** CASE NUMBER **** 1003 RUN * CC DRP 0 * FB 60.0 "GT FALLS" 230.00 * CFB 66.0 "GT FALLS" 230.00 DL 66.0 "GT FALLS" 230.00 "STH_TAP " 230.00 "1" DL 66.0 "STH_TAP " 230.00 "JUDITHGP" 230.00 "1" DL 66.0 "JUDITHGP" 230.00 "JUDITHSO" 230.00 "1" DL 66.0 "JUDITHGP" 230.00 "JUDITHGP" 100.00 "1" Page 511 of 722 APPENDIX I – SWITCHING SEQUENCES GREAT_FALLS_LANDERS_FORK_230.swt RUN * CC DRP 0 * FB 60.0 "GT FALLS" 230.00 * CFB 66.0 "GT FALLS" 230.00 DL 66.0 "LANDRSFK" 230.00 "GT FALLS" 230.00 "1" DL 66.0 "LANDRSFK" 230.00 "OVANDO " 230.00 "1" Page 512 of 722 APPENDIX I – SWITCHING SEQUENCES JUDITH_GAP_S_BROADVIEW_230.swt **** CASE NUMBER **** 1004 RUN * CC DRP 0 * FB 60.0 "JUDITHSO" 230.00 * CFB 66.0 "JUDITHSO" 230.00 DL 66.0 "JUDITHSO" 230.00 "BROADVU " 230.00 "1" Page 513 of 722 APPENDIX I – SWITCHING SEQUENCES LANDERS_FORK_OVANDO_230.swt **** CASE NUMBER **** 1006 RUN * CC DRP 0 * FB 60.0 "LANDRSFK" 230.00 * CFB 66.0 "LANDRSFK" 230.00 DL 66.0 "LANDRSFK" 230.00 "GT FALLS" 230.00 "1" DL 66.0 "LANDRSFK" 230.00 "OVANDO " 230.00 "1" Page 514 of 722 APPENDIX I – SWITCHING SEQUENCES LANGDON_CRANBROOK_500.swt **** CASE NUMBER **** 1012 RUN * CC DRP 0 * FB 60.0 "LANGDON2" 500.00 * CFB 64.0 "LANGDON2" 500.00 DL 64.0 "LANGDON2" 500.00 "CBK500 " 500.00 "1" MLS 64.0 "CBK500 " 500.00 "LANGDON2" 500.00 "1" 1 "t" "D" MBS 64.0 "CBK500 " 500.00 "b2" "D" * DL 72.0 "COLEMAN7" 138.00 "NTL138 " 138.00 "1" * DL 73.0 "POCATER7" 138.00 "FRO T274" 138.00 "1" * DL 86.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 86.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 86.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 86.0 "MATL_AB " 230.00 DB 86.0 "MATLN_&1" 230.00 DL 86.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 86.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 86.0 "MARIAS " 230.00 DB 86.0 "MATLN_&2" 230.00 Page 515 of 722 APPENDIX I – SWITCHING SEQUENCES MATL_PS_CUTBANK_230.swt **** CASE NUMBER **** 1001 RUN * CC DRP 0 * FB 60.0 "MATL_AB " 240.00 * CFB 64.0 "MATL_AB " 240.00 DL 64.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 64.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 64.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 64.0 "MATL_AB " 230.00 DB 64.0 "MATLN_&1" 230.00 * DL 124.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 124.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 124.0 "MARIAS " 230.00 DB 124.0 "MATLN_&2" 230.00 Page 516 of 722 APPENDIX I – SWITCHING SEQUENCES OVANDO_GARRISON_230.swt **** CASE NUMBER **** 1008 RUN * CC DRP 0 * FB 60.0 "OVANDO " 230.00 * CFB 66.0 "OVANDO " 230.00 DL 66.0 "OVANDO " 230.00 "GARRISON" 230.00 "1" Page 517 of 722 APPENDIX I – SWITCHING SEQUENCES OVANDO_HOT_SPRINGS_230.swt **** CASE NUMBER **** 1007 RUN * CC DRP 0 * FB 60.0 "OVANDO " 230.00 * CFB 66.0 "OVANDO " 230.00 DL 66.0 "OVANDO " 230.00 "HOT SPR " 230.00 "1" Page 518 of 722 APPENDIX I – SWITCHING SEQUENCES TAFT_500_BREAKER_FAILURE.swt **** CASE NUMBER **** 1017 RUN * CC DRP 1706 * FB 60.0 "TAFT " 500.00 0.00249 0.02685 * DL 64.0 "TAFT " 500.00 "BELL S&1" 500.00 "1" DL 64.0 "BELL S&1" 500.00 "BELL SC " 500.00 "1" DL 64.0 "BELL SC " 500.00 "BELL BPA" 500.00 "1" RL 64.0 "TAFT " 500.00 "BELL S&1" 500.00 "2P" RL 64.0 "BELL S&1" 500.00 "BELL SC " 500.00 "2P" RL 64.0 "BELL SC " 500.00 "BELL BPA" 500.00 "2P" * CFB 72.0 "TAFT " 500.00 DL 72.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" DL 72.0 "GARRIS&1" 500.00 "GARRIS&2" 500.00 "1" DL 72.0 "GARRIS&2" 500.00 "TAFT " 500.00 "1" DL 72.0 "TAFT " 500.00 "BELL S&1" 500.00 "2P" DL 72.0 "BELL S&1" 500.00 "BELL SC " 500.00 "2P" DL 72.0 "BELL SC " 500.00 "BELL BPA" 500.00 "2P" * TG 72.4 "COLSTP 1" 22.00 "1" MBL 72.4 "COLSTP 1" 22.00 "1" "D" MBL 72.4 "COLSTP 1" 22.00 "2" "D" * TG 73.4 "COLSTP 3" 26.00 "1" MBL 73.4 "COLSTP 3" 26.00 "1" "D" MBL 73.4 "COLSTP 3" 26.00 "2" "D" * MBS 76.5 "GARRISON" 500.00 "b1" "D" * TG 78.0 "LIB 01 " 13.80 "1" TG 78.0 "LIB 02 " 13.80 "2" TG 78.0 "LIB 03 " 13.80 "3" TG 78.0 "LIB 04 " 13.80 "4" TG 78.0 "LIB 05 " 13.80 "5" * MBL 80.9 "COLSTRP " 115.00 "c1" "R" * MBL 81.9 "COLSTRP " 230.00 "c3" "R" Page 519 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 8 - Non-Simultaneous 07 ??? – MATL - South-to-North Switching Sequences Page 520 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500.swt **** CASE NUMBER **** 1010 RUN * CC DRP 1126 * FB 60.0 "BROADVU " 500.00 * CFB 63.0 "BROADVU " 500.00 DL 63.0 "BROADVU " 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN1 " 500.00 DB 63.0 "GAR1EAST" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 70.0 "COLSTP 1" 22.00 "1" MBL 70.0 "COLSTP 1" 22.00 "1" "D" MBL 70.0 "COLSTP 1" 22.00 "2" "D" * TG 71.0 "COLSTP 3" 26.00 "1" MBL 71.0 "COLSTP 3" 26.00 "1" "D" MBL 71.0 "COLSTP 3" 26.00 "2" "D" * MBL 78.5 "COLSTRP " 115.00 "c1" "R" * MBL 79.5 "COLSTRP " 230.00 "c3" "R" Page 521 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500_DL1.swt **** CASE NUMBER **** 1015 RUN * CC DRP 2056 * CC MSV 0.0 "COLSTP 2" 22.00 "1" 115.0 -1.0 * FB 60.0 "BROADVU " 500.00 * CFB 63.0 "BROADVU " 500.00 DL 63.0 "BROADVU " 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN1 " 500.00 DB 63.0 "GAR1EAST" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 68.0 "COLSTP 1" 22.00 "1" MBL 68.0 "COLSTP 1" 22.00 "1" "D" MBL 68.0 "COLSTP 1" 22.00 "2" "D" * TG 69.0 "COLSTP 3" 26.00 "1" MBL 69.0 "COLSTP 3" 26.00 "1" "D" MBL 69.0 "COLSTP 3" 26.00 "2" "D" * TG 69.0 "COLSTP 4" 26.00 "1" MBL 69.0 "COLSTP 4" 26.00 "1" "D" MBL 69.0 "COLSTP 4" 26.00 "2" "D" * TG 70.0 "HARDINGN" 13.80 "1" * MBL 76.5 "COLSTRP " 115.0 "c1" "R" * MBL 77.5 "COLSTRP " 230.0 "c3" "R" * MBL 77.5 "COLSTRP " 230.0 "c4" "R" Page 522 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500_DL2.swt **** CASE NUMBER **** 1015 RUN * CC DRP 0 * DL 63.0 "BROADVU " 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN2 " 500.00 DB 63.0 "GAR2EAST" 500.00 Page 523 of 722 APPENDIX I – SWITCHING SEQUENCES BROADVIEW_GARRISON_500_DLO.swt **** CASE NUMBER **** 1015 RUN * CC DRP 2056 * CC MSV 0.0 "COLSTP 2" 22.00 "1" 115.0 -1.0 * FB 60.0 "BROADVU " 500.00 * CFB 63.0 "BROADVU " 500.00 DL 63.0 "BROADVU " 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "TOWN1 " 500.00 "1" DL 63.0 "GAR1EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN1 " 500.00 DB 63.0 "GAR1EAST" 500.00 DL 63.0 "BROADVU " 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "TOWN2 " 500.00 "2" DL 63.0 "GAR2EAST" 500.00 "GARRISON" 500.00 "1" DB 63.0 "TOWN2 " 500.00 DB 63.0 "GAR2EAST" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 68.0 "COLSTP 1" 22.00 "1" MBL 68.0 "COLSTP 1" 22.00 "1" "D" MBL 68.0 "COLSTP 1" 22.00 "2" "D" * TG 69.0 "COLSTP 3" 26.00 "1" MBL 69.0 "COLSTP 3" 26.00 "1" "D" MBL 69.0 "COLSTP 3" 26.00 "2" "D" * TG 69.0 "COLSTP 4" 26.00 "1" MBL 69.0 "COLSTP 4" 26.00 "1" "D" MBL 69.0 "COLSTP 4" 26.00 "2" "D" * TG 70.0 "HARDINGN" 13.80 "1" * MBL 76.5 "COLSTRP " 115.0 "c1" "R" * MBL 77.5 "COLSTRP " 230.0 "c3" "R" * MBL 77.5 "COLSTRP " 230.0 "c4" "R" Page 524 of 722 APPENDIX I – SWITCHING SEQUENCES COLSTRIP_BROADVIEW_500.swt **** CASE NUMBER **** 1009 RUN * CC DRP 796 * FB 60.0 "COLSTRP " 500.00 * CFB 63.0 "COLSTRP " 500.00 DL 63.0 "COLSTRP " 500.00 "BROADV&1" 500.00 "1" DL 63.0 "BROADVU " 500.00 "BROADV&1" 500.00 "1" * TG 75.0 "COLSTP 3" 26.00 "1" MBL 75.0 "COLSTP 3" 26.00 "1" "D" MBL 75.0 "COLSTP 3" 26.00 "2" "D" * MBL 83.5 "COLSTRP " 230.00 "c3" "R" Page 525 of 722 APPENDIX I – SWITCHING SEQUENCES CRANBROOK_SELKIRK_500.swt **** CASE NUMBER **** 1013 RUN * CC DRP 0 * FB 60.0 "SEL500 " 500.00 * CFB 64.0 "SEL500 " 500.00 DL 64.0 "SEL500 " 500.00 "CBK500 " 500.00 "1" MBS 64.0 "CBK500 " 500.00 "b2" "D" * DL 67.0 "LANGDON2" 500.00 "CBK500 " 500.00 "1" MLS 67.0 "CBK500 " 500.00 "LANGDON2" 500.00 "1" 1 "t" "D" MBS 67.0 "CBK500 " 500.00 "b1" "D" * DL 72.0 "COLEMAN7" 138.00 "NTL138 " 138.00 "1" * DL 73.0 "POCATER7" 138.00 "FRO T274" 138.00 "1" * DL 86.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 86.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 86.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 86.0 "MATL_AB " 230.00 DB 86.0 "MATLN_&1" 230.00 DL 86.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 86.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 86.0 "MARIAS " 230.00 DB 86.0 "MATLN_&2" 230.00 * FB 236.0 "SEL500 " 500.00 * CFB 239.0 "SEL500 " 500.00 Page 526 of 722 APPENDIX I – SWITCHING SEQUENCES CUTBANK_GREAT_FALLS_230.swt **** CASE NUMBER **** 1002 RUN * CC DRP 0 * FB 60.0 "MARIAS " 230.00 * CFB 64.0 "MARIAS " 230.00 DL 64.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 64.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 64.0 "MATLN_&2" 230.00 * DL 124.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 124.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 124.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 124.0 "MATL_AB " 230.00 DB 124.0 "MATLN_&1" 230.00 DB 124.0 "MARIAS " 230.00 Page 527 of 722 APPENDIX I – SWITCHING SEQUENCES FLAT_RUN.swt **** CASE NUMBER **** 0 RUN Page 528 of 722 APPENDIX I – SWITCHING SEQUENCES GARRISON_TAFT_500.swt **** CASE NUMBER **** 1011 RUN * CC DRP 1321 * FB 60.0 "GARRISON" 500.00 FC 60.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 FC 60.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 * CFB 63.0 "GARRISON" 500.00 RC 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 RC 63.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 DL 63.0 "GARRIS&2" 500.00 "TAFT " 500.00 "1" DL 63.0 "GARRIS&2" 500.00 "GARRIS&1" 500.00 "1" DL 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" DB 63.0 "GARRIS&1" 500.00 DB 63.0 "GARRIS&2" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 70.0 "COLSTP 1" 22.00 "1" MBL 70.0 "COLSTP 1" 22.00 "1" "D" MBL 70.0 "COLSTP 1" 22.00 "2" "D" * TG 71.0 "COLSTP 3" 26.00 "1" MBL 71.0 "COLSTP 3" 26.00 "1" "D" MBL 71.0 "COLSTP 3" 26.00 "2" "D" * MBL 71.0 "MILCTYDC" 230.00 "D1" "D" MBS 71.0 "MILCTYDC" 230.00 "b " "D" MBS 71.0 "MILCTYDC" 230.00 "b1" "D" * MBL 78.5 "COLSTRP " 115.00 "c1" "R" * MBS 79.0 "ROSEBUD " 230.00 "b1" "R" MBS 79.0 "CUSTER " 230.00 "b1" "R" MBS 79.0 "CUSTER " 230.00 "b2" "R" * MBL 79.5 "COLSTRP " 230.00 "c3" "R" Page 529 of 722 APPENDIX I – SWITCHING SEQUENCES GARRISON_TAFT_500_DLO.swt **** CASE NUMBER **** 1016 RUN * CC DRP 2142 * CC MSV 0.0 "COLSTP 2" 22.00 "1" 115.0 -1.0 * FB 60.0 "GARRISON" 500.00 FC 60.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 FC 60.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 * CFB 63.0 "GARRISON" 500.00 RC 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" 1 RC 63.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" 1 DL 63.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" DL 63.0 "GARRIS&2" 500.00 "GARRIS&1" 500.00 "1" DL 63.0 "GARRIS&2" 500.00 "TAFT " 500.00 "1" DB 63.0 "GARRIS&1" 500.00 DB 63.0 "GARRIS&2" 500.00 DL 63.0 "GARRIS&B" 500.00 "TAFT " 500.00 "2" DL 63.0 "GARRIS&B" 500.00 "GARRIS&A" 500.00 "2" DL 63.0 "GARRISON" 500.00 "GARRIS&A" 500.00 "2" DB 63.0 "GARRIS&A" 500.00 DB 63.0 "GARRIS&B" 500.00 * MBS 66.5 "GARRISON" 500.00 "b1" "D" * TG 69.2 "COLSTP 1" 22.00 "1" MBL 69.2 "COLSTP 1" 22.00 "1" "D" MBL 69.2 "COLSTP 1" 22.00 "2" "D" * TG 70.2 "COLSTP 3" 26.00 "1" MBL 70.2 "COLSTP 3" 26.00 "1" "D" MBL 70.2 "COLSTP 3" 26.00 "2" "D" * TG 70.2 "COLSTP 4" 26.00 "1" MBL 70.2 "COLSTP 4" 26.00 "1" "D" MBL 70.2 "COLSTP 4" 26.00 "2" "D" * MBL 71.0 "MILCTYDC" 230.00 "D1" "D" MBS 71.0 "MILCTYDC" 230.00 "b " "D" MBS 71.0 "MILCTYDC" 230.00 "b1" "D" * MBL 77.7 "COLSTRP " 115.00 "c1" "R" * Page 530 of 722 APPENDIX I – SWITCHING SEQUENCES MBL * MBL * MBS MBS MBS 78.7 "COLSTRP " 230.00 "c3" "R" 78.7 "COLSTRP " 230.00 "c4" "R" 79.0 "ROSEBUD " 230.00 "b1" "R" 79.0 "CUSTER " 230.00 "b1" "R" 79.0 "CUSTER " 230.00 "b2" "R" Page 531 of 722 APPENDIX I – SWITCHING SEQUENCES GREAT_FALLS_JUDITH_GAP_S_230.swt **** CASE NUMBER **** 1003 RUN * CC DRP 0 * FB 60.0 "GT FALLS" 230.00 * CFB 66.0 "GT FALLS" 230.00 DL 66.0 "GT FALLS" 230.00 "STH_TAP " 230.00 "1" DL 66.0 "STH_TAP " 230.00 "JUDITHGP" 230.00 "1" DL 66.0 "JUDITHGP" 230.00 "JUDITHSO" 230.00 "1" DL 66.0 "JUDITHGP" 230.00 "JUDITHGP" 100.00 "1" Page 532 of 722 APPENDIX I – SWITCHING SEQUENCES GREAT_FALLS_LANDERS_FORK_230.swt **** CASE NUMBER **** 1005 RUN * CC DRP 0 * FB 60.0 "GT FALLS" 230.00 * CFB 66.0 "GT FALLS" 230.00 DL 66.0 "LANDRSFK" 230.00 "GT FALLS" 230.00 "1" DL 66.0 "LANDRSFK" 230.00 "OVANDO " 230.00 "1" Page 533 of 722 APPENDIX I – SWITCHING SEQUENCES JUDITH_GAP_S_BROADVIEW_230.swt **** CASE NUMBER **** 1004 RUN * CC DRP 0 * FB 60.0 "JUDITHSO" 230.00 * CFB 66.0 "JUDITHSO" 230.00 DL 66.0 "JUDITHSO" 230.00 "BROADVU " 230.00 "1" Page 534 of 722 APPENDIX I – SWITCHING SEQUENCES LANDERS_FORK_OVANDO_230.swt **** CASE NUMBER **** 1006 RUN * CC DRP 0 * FB 60.0 "LANDRSFK" 230.00 * CFB 66.0 "LANDRSFK" 230.00 DL 66.0 "LANDRSFK" 230.00 "GT FALLS" 230.00 "1" DL 66.0 "LANDRSFK" 230.00 "OVANDO " 230.00 "1" Page 535 of 722 APPENDIX I – SWITCHING SEQUENCES LANGDON_CRANBROOK_500.swt **** CASE NUMBER **** 1012 RUN * CC DRP 0 * FB 60.0 "LANGDON2" 500.00 * CFB 64.0 "LANGDON2" 500.00 DL 64.0 "LANGDON2" 500.00 "CBK500 " 500.00 "1" MLS 64.0 "CBK500 " 500.00 "LANGDON2" 500.00 "1" 1 "t" "D" MBS 64.0 "CBK500 " 500.00 "b2" "D" * DL 72.0 "COLEMAN7" 138.00 "NTL138 " 138.00 "1" * DL 73.0 "POCATER7" 138.00 "FRO T274" 138.00 "1" * DL 86.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 86.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 86.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 86.0 "MATL_AB " 230.00 DB 86.0 "MATLN_&1" 230.00 DL 86.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 86.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 86.0 "MARIAS " 230.00 DB 86.0 "MATLN_&2" 230.00 Page 536 of 722 APPENDIX I – SWITCHING SEQUENCES MATL_PS_CUTBANK_230.swt **** CASE NUMBER **** 1001 RUN * CC DRP 0 * FB 60.0 "MATL_AB " 240.00 * CFB 64.0 "MATL_AB " 240.00 DL 64.0 "MATL_AB " 240.00 "MATL_AB " 230.00 "1" DL 64.0 "MATL_AB " 230.00 "MATLN_&1" 230.00 "1" DL 64.0 "MATLN_&1" 230.00 "MARIAS " 230.00 "1" DB 64.0 "MATL_AB " 230.00 DB 64.0 "MATLN_&1" 230.00 * DL 124.0 "MARIAS " 230.00 "MATLN_&2" 230.00 "1" DL 124.0 "MATLN_&2" 230.00 "GT FALLS" 230.00 "1" DB 124.0 "MARIAS " 230.00 DB 124.0 "MATLN_&2" 230.00 Page 537 of 722 APPENDIX I – SWITCHING SEQUENCES OVANDO_GARRISON_230.swt **** CASE NUMBER **** 1008 RUN * CC DRP 0 * FB 60.0 "OVANDO " 230.00 * CFB 66.0 "OVANDO " 230.00 DL 66.0 "OVANDO " 230.00 "GARRISON" 230.00 "1" Page 538 of 722 APPENDIX I – SWITCHING SEQUENCES OVANDO_HOT_SPRINGS_230.swt **** CASE NUMBER **** 1007 RUN * CC DRP 0 * FB 60.0 "OVANDO " 230.00 * CFB 66.0 "OVANDO " 230.00 DL 66.0 "OVANDO " 230.00 "HOT SPR " 230.00 "1" Page 539 of 722 APPENDIX I – SWITCHING SEQUENCES TAFT_500_BREAKER_FAILURE.swt **** CASE NUMBER **** 1017 RUN * CC DRP 1706 * FB 60.0 "TAFT " 500.00 0.00249 0.02685 * DL 64.0 "TAFT " 500.00 "BELL S&1" 500.00 "1" DL 64.0 "BELL S&1" 500.00 "BELL SC " 500.00 "1" DL 64.0 "BELL SC " 500.00 "BELL BPA" 500.00 "1" RL 64.0 "TAFT " 500.00 "BELL S&1" 500.00 "2P" RL 64.0 "BELL S&1" 500.00 "BELL SC " 500.00 "2P" RL 64.0 "BELL SC " 500.00 "BELL BPA" 500.00 "2P" * CFB 72.0 "TAFT " 500.00 DL 72.0 "GARRISON" 500.00 "GARRIS&1" 500.00 "1" DL 72.0 "GARRIS&1" 500.00 "GARRIS&2" 500.00 "1" DL 72.0 "GARRIS&2" 500.00 "TAFT " 500.00 "1" DL 72.0 "TAFT " 500.00 "BELL S&1" 500.00 "2P" DL 72.0 "BELL S&1" 500.00 "BELL SC " 500.00 "2P" DL 72.0 "BELL SC " 500.00 "BELL BPA" 500.00 "2P" * TG 72.4 "COLSTP 1" 22.00 "1" MBL 72.4 "COLSTP 1" 22.00 "1" "D" MBL 72.4 "COLSTP 1" 22.00 "2" "D" * TG 73.4 "COLSTP 3" 26.00 "1" MBL 73.4 "COLSTP 3" 26.00 "1" "D" MBL 73.4 "COLSTP 3" 26.00 "2" "D" * MBS 76.5 "GARRISON" 500.00 "b1" "D" * TG 78.0 "LIB 01 " 13.80 "1" TG 78.0 "LIB 02 " 13.80 "2" TG 78.0 "LIB 03 " 13.80 "3" TG 78.0 "LIB 04 " 13.80 "4" TG 78.0 "LIB 05 " 13.80 "5" * MBL 80.9 "COLSTRP " 115.00 "c1" "R" * MBL 81.9 "COLSTRP " 230.00 "c3" "R" Page 540 of 722 APPENDIX I – SWITCHING SEQUENCES Non-Simultaneous Analysis 07 HS – Autocon Files Page 541 of 722 APPENDIX I – SWITCHING SEQUENCES Non-Sim_07hs-III1ac-catb&c.acn DEFINE BASE CASE LIST 07hs_pre_rev22gtcl.sav SS "Non-Simultaneous, Pre-Project Base Case" 07hs_ns_pst_s2n_rev23gtcl.sav SS "Non-Simultaneous, Post-Project, MATL-n2s Case III-1c" DONE # The following contingencies are assembled based on page 9 of the Study Plan. # updated 11-24-2006 tcl # updated 7-18-2006 cet # updated 8-1-2006 jle # # Base Case -- Case Number 0 0 # ######################################################################## ########################## # # PROJECT CONTINGENCIES # ######################################################################## ########################## # # Case Number 1 2 "MATL_AB 240.00" "MATL_AB 230.00" "1" 0 1 "MATL_AB 230.00" "MATLN_&1 230.00" "1" 0 1 "MATLN_&1 230.00" "MARIAS 230.00" "1" 0 1 "MARIAS 230.00" "MATLN_&2 230.00" "1" 0 1 "MATLN_&2 230.00" "GT FALLS 230.00" "1" 0 0 # ######################################################################## ########################## # # All 230 and 500 kV lines in Montana # ######################################################################## ########################## # Page 542 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 2 1 "MILL CRK 230.00" "GARRISON 230.00" "1" 0 0 # # Case Number 3 1 "MILL CRK 230.00" "PTRSNFLT 230.00" "1" 0 1 "PTRSNFLT 230.00" "AMPS 230.00" "1" 0 1 "AMPS 230.00" "ANTLOPP 230.00" "1" 0 2 "AMPS 230.00" "AMPS 69.00" "1" 0 0 # # Case Number 4 1 "MILL CRK 230.00" "THRRIVER 230.00" "1" 0 0 # # Case Number 5 1 "MILL CRK 230.00" "ANA BPA 230.00" "1" 0 20 0 # # Case Number 6 1 "WILSALL 230.00" "SHOREYRD 230.00" "1" 0 0 # # Case Number 7 1 "WILSALL 230.00" "THRRIVER 230.00" "1" 0 0 # # Case Number 8 1 "SHELBY 230.00" "CNRDWAPA 230.00" "1" 0 0 # # Case Number 9 1 "BOLE 230.00" "CNRDWAPA 230.00" "1" 0 20 0 # # Case Number 10 1 "BOLE 230.00" "GT FALLS 230.00" "1" 0 0 # Page 543 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 1 2 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 11 "JUDITHGP 230.00" "GT FALLS 230.00" "1" 0 "JUDITHGP 230.00" "JUDITHSO 230.00" "1" 0 "JUDITHGP 230.00" "JUDITHGP 100.00" "1" 0 Case Number 12 "BROADVU 230.00" "JUDITHSO 230.00" "1" 0 Case Number 13 "BLGS PHA 230.00" "YELOWTLP 230.00" "1" 0 Case Number 14 "HARDIN 230.00" "COLSTRP 230.00" "1" 0 Case Number 15 "HARDIN 230.00" "CRSOVRUM 230.00" "1" 0 Case Number 16 "ALKALI 230.00" "SHOREYRD 230.00" "1" 0 Case Number 17 "ALKALI 230.00" "BILINGS 230.00" "1" 0 Case Number 18 "ALKALI 230.00" "BROADVU 230.00" "1" 0 Case Number 19 "BASELINE 230.00" "SHOREYRD 230.00" "1" 0 Case Number 20 "HUNTLEY 230.00" "BILINGS 230.00" "1" 0 Page 544 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 21 1 "HUNTLEY 230.00" "CRSOVRUM 230.00" "1" 0 0 # # Case Number 22 1 "OVANDO 230.00" "GARRISON 230.00" "1" 0 0 # # Case Number 23 1 "OVANDO 230.00" "HOT SPR 230.00" "1" 0 0 # # Case Number 24 1 "BILINGS 230.00" "BILINGSW 230.00" "1" 0 0 # # Case Number 25 1 "BILINGSW 230.00" "BROADVU 230.00" "1" 0 0 # # Case Number 26 1 "ANA BPA 230.00" "GARRISON 230.00" "1" 0 0 # ######################################################################## ########################## # # All 161 kV and lower voltage lines in Montana north of Great Falls # ######################################################################## ########################## # # Case Number 27 1 "FT PECK 161.00" "RICHARDC 161.00" "1" 0 0 # # Case Number 28 1 "MALTA UM 161.00" "RICHARDC 161.00" "1" 0 0 # # Case Number 29 1 "HARLEM 161.00" "HAVRE 161.00" "1" 0 0 # Page 545 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 30 "HARLEM 161.00" "MALTA UM 161.00" "1" 0 Case Number 31 "HAVRE 161.00" "VERONA 161.00" "1" 0 Case Number 32 "BONNERMT 161.00" "MILL CRK 161.00" "1" 0 Case Number 33 "BONNERMT 161.00" "RATTLE S 161.00" "1" 0 Case Number 34 "BONNERMT 161.00" "MILLERCK 161.00" "1" 0 Case Number 35 "MILL CRK 161.00" "RATTLE S 161.00" "1" 0 Case Number 36 "MILL CRK 161.00" "MT ASIMI 161.00" "1" 0 Case Number 37 "MILL CRK 161.00" "MT ASIMI 161.00" "2" 0 Case Number 38 "MILL CRK 161.00" "DILLON S 161.00" "1" 0 Case Number 39 "KERR B 161.00" "RATTLE S 161.00" "1" 0 Case Number 40 "KERR A 161.00" "RATTLE S 161.00" "1" 0 Page 546 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 41 "RATTLE S 161.00" "RESERVST 161.00" "1" 0 Case Number 42 "BUTTEMHD 161.00" "MT ASIMI 161.00" "1" 0 Case Number 43 "BUTTEMHD 161.00" "BUTTE MT 161.00" "1" 0 Case Number 44 "WILSALL 161.00" "CLYDE P 161.00" "1" 0 Case Number 45 "MT ASIMI 161.00" "BUTTE MT 161.00" "1" 0 Case Number 46 "GT FALLS 161.00" "HAVRE 161.00" "1" 0 Case Number 47 "RAINBOW 161.00" "VERONA 161.00" "1" 0 Case Number 48 "RMRK PHA 161.00" "YELOWTLP 161.00" "1" 0 Case Number 49 "RIMROCK 161.00" "ALKALI 161.00" "1" 0 Case Number 50 "BRADLEYC 161.00" "ENNIS MT 161.00" "1" 0 Case Number 51 "BRADLEYC 161.00" "JACKRABT 161.00" "1" 0 Page 547 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 52 "ENNIS MT 161.00" "SHERDNMT 161.00" "1" 0 Case Number 53 "THRRIVER 161.00" "CLYDE P 161.00" "1" 0 Case Number 54 "THRRIVER 161.00" "GLDNSNLT 161.00" "1" 0 Case Number 55 "THRRIVER 161.00" "JACKRABT 161.00" "1" 0 Case Number 56 "BUTTE MT 161.00" "GLDNSNLT 161.00" "1" 0 Case Number 57 "RESERVST 161.00" "MISSLA 7 161.00" "1" 0 Case Number 58 "MILLERCK 161.00" "MISSLA 7 161.00" "1" 0 Case Number 59 "MILLERCK 161.00" "HAMLTNMA 161.00" "1" 0 Case Number 60 "MILLERCK 161.00" "HAMLTNMB 161.00" "1" 0 Case Number 61 "DILLON S 161.00" "SHERDNMT 161.00" "1" 0 Case Number 62 "DILLON S 161.00" "BIGGRASS 161.00" "1" 0 Page 548 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 63 "CLYDE P 161.00" "EGALTNAB 161.00" "1" 0 Case Number 64 "CLYDE P 161.00" "EGALTNAB 161.00" "2" 0 Case Number 65 "CLYDE P 161.00" "EMIGT AT 161.00" "1" 0 Case Number 66 "CLYDE P 161.00" "DUCKCR-R 161.00" "1" 0 Case Number 67 "ALKALI 161.00" "COLRPLJE 161.00" "1" 0 Case Number 68 "COLRPLJE 161.00" "CLMBUSPM 161.00" "1" 0 Case Number 69 "COLRPLJE 161.00" "BGTMBERA 161.00" "1" 0 Case Number 70 "EGALTNAB 161.00" "JACKRABT 161.00" "1" 0 Case Number 71 "EGALTNAB 161.00" "JACKRABT 161.00" "99" 0 Case Number 72 "EGALTNAB 161.00" "BOZMN WS 161.00" "1" 0 Case Number 73 "BGTMBERA 161.00" "DUCKCR-R 161.00" "1" 0 Page 549 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 74 "JACKRABT 161.00" "BOZMN WS 161.00" "1" 0 Case Number 75 "TAFTAUTO 115.00" "CROWCR B 115.00" "1" 0 Case Number 76 "SHELBY 115.00" "CUTBANK 115.00" "1" 0 Case Number 77 "SHELBY 115.00" "TIBERTAP 115.00" "1" 0 Case Number 78 "CUTBANK 115.00" "CTBPUMP 115.00" "1" 0 Case Number 79 "ANA BPA 115.00" "SLVR BOW 115.00" "1" 0 Case Number 80 "MONTANA1 115.00" "COLSTRP 115.00" "1" 0 Case Number 81 "MONTANA1 115.00" "NICHOL-R 115.00" "1" 0 Case Number 82 "KERR 115.00" "ELMO 115.00" "1" 0 Case Number 83 "KERR 115.00" "PLAINS 115.00" "1" 0 Case Number 84 "KERR 115.00" "THFLPM T 115.00" "99" 0 Page 550 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 85 "CNRDWAPA 115.00" "CONRAD 115.00" "1" 0 Case Number 86 "CNRDWAPA 115.00" "DUTTON 115.00" "1" 0 Case Number 87 "CNRDWAPA 115.00" "CNRD-SRA 115.00" "1" 0 Case Number 88 "GT FALLS 115.00" "DUTTON 115.00" "1" 0 Case Number 89 "HARDIN 115.00" "SARPY AT 115.00" "1" 0 Case Number 90 "COLSTRP 115.00" "ARMELLCR 115.00" "1" 0 Case Number 91 "CROWCR B 115.00" "BURKAVAB 115.00" "1" 0 Case Number 92 "CROWCR B 115.00" "THOMSON 115.00" "1" 0 Case Number 93 "THOMSON 115.00" "BURKAVAA 115.00" "1" 0 Case Number 94 "THOMSON 115.00" "TFALLCIT 115.00" "1" 0 Case Number 95 "THOMSON 115.00" "TFALCITA 115.00" "1" 0 Page 551 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 96 "CONRAD 115.00" "VAL-WILL 115.00" "1" 0 Case Number 97 "CTBPUMP 115.00" "VAL-WILL 115.00" "1" 0 Case Number 98 "NICHOLPM 115.00" "NICHOL-R 115.00" "1" 0 Case Number 99 "ARMELLCR 115.00" "CASTLERT 115.00" "1" 0 Case Number 100 "CASTLERT 115.00" "CASTLERK 115.00" "1" 0 Case Number 101 "CASTLERT 115.00" "SARPY AT 115.00" "1" 0 Case Number 102 "PLAINS 115.00" "TFALCITA 115.00" "1" 0 Case Number 103 "THFLPM T 115.00" "TFALLCIT 115.00" "1" 0 Case Number 104 "THFLPM T 115.00" "THFALLPM 115.00" "1" 0 Case Number 105 "TFALLCIT 115.00" "THFALL-R 115.00" "1" 0 Case Number 106 "THREERIV 100.00" "TRIDENT 100.00" "1" 0 Page 552 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 107 "MADISON 100.00" "BRADLEYC 100.00" "1" 0 Case Number 108 "MORONY 100.00" "GT FALLS 100.00" "1" 0 Case Number 109 "COCHRAN 100.00" "RAINBOW 100.00" "1" 0 Case Number 110 "RYAN 100.00" "MTGENJCT 100.00" "1" 0 Case Number 111 "RYAN 100.00" "MTGENJCT 100.00" "2" 0 Case Number 112 "TRIDENT 100.00" "EUSTIS 100.00" "1" 0 Case Number 113 "TRIDENT 100.00" "TRIDTPLT 100.00" "1" 0 Case Number 114 "TRIDENT 100.00" "THREFORK 100.00" "1" 0 Case Number 115 "BROADVU 100.00" "HARLOWTN 100.00" "1" 0 Case Number 116 "BROADVU 100.00" "PANTROBE 100.00" "1" 0 Case Number 117 "BROADVU 100.00" "LAVINAPT 100.00" "1" 0 Page 553 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 118 "TAFTAUTO 100.00" "SALTESE 100.00" "1" 0 Case Number 119 "WALDORF 100.00" "RATTLE S 100.00" "1" 0 Case Number 120 "WALDORF 100.00" "FRENCH-R 100.00" "1" 0 Case Number 121 "WALDORF 100.00" "HUSON-R 100.00" "1" 0 Case Number 122 "RIMROCK 100.00" "BILINGS 100.00" "1" 0 Case Number 123 "RIMROCK 100.00" "BERTOOTH 100.00" "1" 0 Case Number 124 "RIMROCK 100.00" "BILL ES 100.00" "1" 0 Case Number 125 "BILINGS 100.00" "BILINGS8 100.00" "1" 0 Case Number 126 "BILINGS 100.00" "LAURELMT 100.00" "1" 0 Case Number 127 "BILINGS 100.00" "CONOCOMT 100.00" "1" 0 Case Number 128 "BILINGS 100.00" "BILLCITY 100.00" "1" 0 Page 554 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 129 "BILINGS 100.00" "BILL ES 100.00" "1" 0 Case Number 130 "BILINGS8 100.00" "BILLCITY 100.00" "1" 0 Case Number 131 "BILINGS8 100.00" "BELLROCK 100.00" "1" 0 Case Number 132 "BILINGS8 100.00" "KING AVE 100.00" "1" 0 Case Number 133 "BASELINE 100.00" "MERIDNMT 100.00" "1" 0 Case Number 134 "BASELINE 100.00" "GRNDAV-R 100.00" "1" 0 Case Number 135 "BASELINE 100.00" "BL72ST-R 100.00" "1" 0 Case Number 136 "JUDITHGP 100.00" "JUDITGPT 100.00" "1" 0 Case Number 137 "JUDITHGP 100.00" "STRAWXPT 100.00" "1" 0 Case Number 138 "JUDITHGP 100.00" "FRONTRGT 100.00" "1" 0 Case Number 139 "BRADLEYC 100.00" "HAR-PONY 100.00" "1" 0 Page 555 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 140 "BRADLEYC 100.00" "COBLSTNT 100.00" "1" 0 Case Number 141 "HARLOWTN 100.00" "PANTROBE 100.00" "1" 0 Case Number 142 "HARLOWTN 100.00" "TWO DOT 100.00" "1" 0 Case Number 143 "HARLOWTN 100.00" "JUDITGPT 100.00" "1" 0 Case Number 144 "LAURELMT 100.00" "RAIL TAP 100.00" "1" 0 Case Number 145 "LAURELMT 100.00" "CENEX B 100.00" "1" 0 Case Number 146 "LAURELMT 100.00" "LAURELPM 100.00" "1" 0 Case Number 147 "LAURELMT 100.00" "EDGARXPT 100.00" "1" 0 Case Number 148 "LAURELMT 100.00" "BRIDGERA 100.00" "2" 0 Case Number 149 "MILLERCK 100.00" "MISSLA 5 100.00" "1" 0 Case Number 150 "RESERVST 100.00" "MISSLA 1 100.00" "1" 0 Page 556 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 151 "RESERVST 100.00" "ELMAR-R 100.00" "1" 0 Case Number 152 "RATTLE S 100.00" "MISSLA 1 100.00" "1" 0 Case Number 153 "RATTLE S 100.00" "MISSLA 3 100.00" "1" 0 Case Number 154 "MILL CRK 100.00" "ANA CITY 100.00" "1" 0 Case Number 155 "MILL CRK 100.00" "ANA CITY 100.00" "2" 0 Case Number 156 "MILL CRK 100.00" "MOREL 100.00" "1" 0 Case Number 157 "MILL CRK 100.00" "PCIFICST 100.00" "1" 0 Case Number 158 "BUTTE MT 100.00" "RENOVA 100.00" "1" 0 Case Number 159 "BUTTE MT 100.00" "CONDR TA 100.00" "1" 0 Case Number 160 "BUTTE MT 100.00" "CONDR TB 100.00" "1" 0 Case Number 161 "BUTTE MT 100.00" "BTMINDPK 100.00" "1" 0 Page 557 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 162 "GT FALLS 100.00" "RAINBOW 100.00" "1" 0 Case Number 163 "GT FALLS 100.00" "RAINBOW 100.00" "2" 0 Case Number 164 "GT FALLS 100.00" "GF ESIDE 100.00" "1" 0 "GF ESIDE 100.00" "CANFERTB 100.00" "1" 0 Case Number 165 "GT FALLS 100.00" "GF RVRVW 100.00" "1" 0 Case Number 166 "RAINBOW 100.00" "BELT 100.00" "1" 0 Case Number 167 "RAINBOW 100.00" "GF NEAST 100.00" "1" 0 Case Number 168 "RAINBOW 100.00" "WAYNEPMT 100.00" "1" 0 Case Number 169 "RAINBOW 100.00" "MALMSTRM 100.00" "1" 0 Case Number 170 "RAINBOW 100.00" "MTGENJCT 100.00" "1" 0 Page 558 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 1 1 1 1 1 1 1 0 # # 1 1 1 1 1 0 # # 1 1 1 1 0 # # 1 0 # # 1 1 1 1 1 1 0 # # 1 0 # Case Number 171 "HOLTER 100.00" "CANYONCR 100.00" "1" 0 "CANYONCR 100.00" "GILBERT 100.00" "1" 0 "GOLD CR 100.00" "GILBERT 100.00" "1" 0 "GOLD CR 100.00" "DRLDG CM 100.00" "1" 0 "GOLD CR 100.00" "MT PHOST 100.00" "1" 0 "MT PHOST 100.00" "DRUMPM T 100.00" "1" 0 "DRUMPM T 100.00" "DRUMMNMT 100.00" "1" 0 "DRUMPM T 100.00" "DRUMN PM 100.00" "1" 0 Case Number 172 "E HELENA 100.00" "CANFERTA 100.00" "1" 0 "CANFERTA 100.00" "SPOKANEA 100.00" "1" 0 "CANYON F 100.00" "SPOKANEA 100.00" "1" 0 "ADEL 100.00" "CANFERTA 100.00" "1" 0 "GF SSIDE 100.00" "ADEL 100.00" "1" 0 Case Number 173 "E HELENA 100.00" "CANFERTB 100.00" "1" 0 "GF ESIDE 100.00" "CANFERTB 100.00" "1" 0 "CANFERTB 100.00" "SPOKANEB 100.00" "1" 0 "CANYON F 100.00" "SPOKANEB 100.00" "1" 0 Case Number 174 "HOLTER 100.00" "HELVLY T 100.00" "1" 0 Case Number 175 "E HELENA 100.00" "CONLIM T 100.00" "1" 0 "CONLIM T 100.00" "TOWNSEND 100.00" "1" 0 "CONLIM T 100.00" "CONTLIME 100.00" "1" 0 "TOWNSEND 100.00" "TOSTON 100.00" "1" 0 "TOWNSEND 100.00" "TOWNSD-R 100.00" "1" 0 "TOSTON 100.00" "BRDWTR T 100.00" "1" 0 Case Number 176 "E HELENA 100.00" "HELVLY T 100.00" "1" 0 Page 559 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 1 1 1 1 1 1 1 1 1 0 # # 1 1 1 1 1 1 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 177 "E HELENA 100.00" "HELSS TA 100.00" "1" 0 "HELSS TA 100.00" "CLANCYTA 100.00" "1" 0 "MTTUNTPA 100.00" "CLANCYTA 100.00" "1" 0 "MTTUNTPA 100.00" "MTTUNTIE 100.00" "1" 0 "MTTUNTPA 100.00" "BOULDRTA 100.00" "1" 0 "BOULDRTA 100.00" "BOULDTIE 100.00" "1" 0 "BOULDRAT 100.00" "BOULDTIE 100.00" "1" 0 "BASINMT 100.00" "BOULDRTA 100.00" "1" 0 "PRECIPIT 100.00" "BASINMT 100.00" "1" 0 "BUTECORA 100.00" "PRECIPIT 100.00" "1" 0 Case Number 178 "E HELENA 100.00" "HELSS TB 100.00" "1" 0 "HELSS TB 100.00" "CLANCYTB 100.00" "1" 0 "CLANCYTB 100.00" "CLNCYTIE 100.00" "1" 0 "CLNCYTIE 100.00" "CLANCY 100.00" "1" 0 "MTTUNTAP 100.00" "CLANCYTB 100.00" "1" 0 "MTTUNTAP 100.00" "BOULDRTB 100.00" "1" 0 "BARGE PM 100.00" "BOULDRTB 100.00" "1" 0 Case Number 179 "BEAGLE 100.00" "GF RVRVW 100.00" "1" 0 Case Number 180 "MOREL 100.00" "DERLDG T 100.00" "1" 0 Case Number 181 "MOREL 100.00" "FAIRMTMT 100.00" "1" 0 Case Number 182 "DERLDG T 100.00" "DRLDG CM 100.00" "1" 0 Case Number 183 "FAIRMTMT 100.00" "RAMSAYPM 100.00" "1" 0 Page 560 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 184 "DRLDGCTY 100.00" "DRLDG CM 100.00" "1" 0 Case Number 185 "BUTECRSH 100.00" "MONST TP 100.00" "1" 0 Case Number 186 "BUTECRSH 100.00" "BUT CONC 100.00" "1" 0 Case Number 187 "BUTECORA 100.00" "PCIFICST 100.00" "1" 0 Case Number 188 "BUTECORA 100.00" "MONST TP 100.00" "1" 0 Case Number 189 "BUTECORA 100.00" "TAILBOS2 100.00" "1" 0 Case Number 190 "MONST TP 100.00" "MONT ST 100.00" "1" 0 Case Number 191 "BUT CONC 100.00" "TAILBOOS 100.00" "1" 0 Case Number 192 "BUT CONC 100.00" "CONDR TB 100.00" "1" 0 Case Number 193 "MONT ST 100.00" "RAMSAYPM 100.00" "1" 0 Case Number 194 "MONT ST 100.00" "BTMINDPK 100.00" "1" 0 Page 561 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 195 "TAILBOOS 100.00" "CONDR TA 100.00" "1" 0 Case Number 196 "TAILBOS2 100.00" "BARGE PM 100.00" "1" 0 Case Number 197 "RENOVA 100.00" "MAYFLWRT 100.00" "1" 0 Case Number 198 "RENOVA 100.00" "MONTTALC 100.00" "1" 0 Case Number 199 "DRMCLARK 100.00" "CLINTN-R 100.00" "1" 0 Case Number 200 "DRMCLARK 100.00" "DRUMMNMT 100.00" "1" 0 Case Number 201 "CONDR TB 100.00" "CONTDRVE 100.00" "1" 0 Case Number 202 "MAYFLWRT 100.00" "MAYFLWRM 100.00" "1" 0 Case Number 203 "MAYFLWRT 100.00" "HAR-PONY 100.00" "1" 0 Case Number 204 "GF NWEST 100.00" "GF SWEST 100.00" "1" 0 Page 562 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 1 1 1 1 1 0 # # 1 1 0 # # 1 0 # # 1 0 # # 1 1 1 0 # # 1 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 205 "GF NWEST 100.00" "GF NW T1 100.00" "1" 0 "GF NW T1 100.00" "ULM TAP 100.00" "1" 0 "ULM MT 100.00" "ULM TAP 100.00" "1" 0 "MISSIONM 100.00" "ULM TAP 100.00" "1" 0 "MISSIONM 100.00" "CRAIGMT 100.00" "1" 0 "HOLTER 100.00" "CRAIGMT 100.00" "1" 0 Case Number 206 "GF NWEST 100.00" "GF NW T2 100.00" "1" 0 "GF NW T2 100.00" "GF RVRVW 100.00" "1" 0 Case Number 207 "GF NWEST 100.00" "GFCITYT2 100.00" "1" 0 Case Number 208 "GF SWEST 100.00" "GF SSIDE 100.00" "1" 0 Case Number 209 "GT FALLS 100.00" "GFCITYT1 100.00" "1" 0 "GF CITY 100.00" "GFCITYT1 100.00" "1" 0 "GF CITY 100.00" "GF SSIDE 100.00" "1" 0 Case Number 210 "GF SSIDE 100.00" "GF ES A 100.00" "1" 0 "GF ES A 100.00" "GF NEAST 100.00" "1" 0 Case Number 211 "WAYNE PM 100.00" "WAYNEPMT 100.00" "1" 0 Case Number 212 "RAYNE PM 100.00" "RNFRDP T 100.00" "1" 0 Case Number 213 "MONARCHM 100.00" "KINGHILL 100.00" "1" 0 Page 563 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 214 "MONARCHM 100.00" "BELT 100.00" "1" 0 Case Number 215 "KINGHILL 100.00" "MARTNSDA 100.00" "1" 0 Case Number 216 "RNFRDP T 100.00" "NORNFDPT 100.00" "1" 0 Case Number 217 "RNFRDP T 100.00" "STANFRDM 100.00" "1" 0 Case Number 218 "WAYNEPMT 100.00" "NORNFDPT 100.00" "1" 0 Case Number 219 "NORNFDPT 100.00" "NORNFDPM 100.00" "1" 0 Case Number 220 "RAIL TAP 100.00" "RAILWELD 100.00" "1" 0 Case Number 221 "RAIL TAP 100.00" "BL72ST-R 100.00" "1" 0 Case Number 222 "CENEX A 100.00" "CENEX B 100.00" "1" 0 Case Number 223 "CENEX A 100.00" "LAURELPM 100.00" "1" 0 Case Number 224 "PANTROBE 100.00" "ROUNDUPM 100.00" "1" 0 Page 564 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 225 1 "CONOCOMT 100.00" "BILLNGPM 100.00" "1" 0 0 # # Case Number 226 1 "MERIDNMT 100.00" "BELLROCK 100.00" "1" 0 0 # # Case Number 227 1 "MERIDNMT 100.00" "SHILOH 100.00" "1" 0 0 # # Case Number 228 1 "BILLNGPM 100.00" "BERTOOTH 100.00" "1" 0 0 # # Case Number 229 1 "ABSRKE-R 100.00" "ABSAROKE 100.00" "1" 0 0 # # Case Number 230 1 "ABSAROKE 100.00" "COLBUSAT 100.00" "1" 0 0 # # Case Number 231 1 "ABSAROKE 100.00" "CHROMEAT 100.00" "1" 0 0 # # Case Number 232 1 "KING AVE 100.00" "SHILOH 100.00" "1" 0 0 # # Case Number 233 1 "EDGARXPM 100.00" "EDGARXPT 100.00" "1" 0 0 # # Case Number 234 1 "EDGARXPT 100.00" "BRIDGERA 100.00" "1" 0 0 # # Case Number 235 1 "LAVINAPT 100.00" "LAVINAPM 100.00" "1" 0 20 0 # Page 565 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 236 "LAVINAPT 100.00" "ROUNDUPM 100.00" "1" 0 Case Number 237 "COLRPLJE 100.00" "COLBUSAT 100.00" "1" 0 Case Number 238 "COLBUSAT 100.00" "STLWTRSM 100.00" "1" 0 Case Number 239 "TWO DOT 100.00" "MARTNSDA 100.00" "1" 0 Case Number 240 "TWO DOT 100.00" "LOWETH 100.00" "1" 0 Case Number 241 "UTICAPMP 100.00" "UTICATAP 100.00" "1" 0 Case Number 242 "UTICATAP 100.00" "BENCHLND 100.00" "1" 0 Case Number 243 "UTICATAP 100.00" "UTICA 100.00" "1" 0 Case Number 244 "BENCHLND 100.00" "STANFRDM 100.00" "1" 0 Case Number 245 "BENCHLND 100.00" "GLENGARY 100.00" "1" 0 Case Number 246 "GLENGARY 100.00" "STRAWXPT 100.00" "1" 0 Page 566 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 247 "JUDITGPT 100.00" "JUDTHSMT 100.00" "1" 0 Case Number 248 "JUDGAPSM 100.00" "JUDTHSMT 100.00" "1" 0 Case Number 249 "JUDTHPMP 100.00" "JUDTHSMT 100.00" "1" 0 Case Number 250 "UTICA-R 100.00" "UTICA 100.00" "1" 0 Case Number 251 "UTICA 100.00" "FRONTRGT 100.00" "1" 0 Case Number 252 "STRAWXPM 100.00" "STRAWXPT 100.00" "1" 0 Case Number 253 "EUSTIS 100.00" "CROWCREK 100.00" "1" 0 Case Number 254 "COBLSTON 100.00" "COBLSTNT 100.00" "1" 0 Case Number 255 "FRANCIS 100.00" "LOWETH 100.00" "1" 0 Case Number 256 "THREFORK 100.00" "WILLWCKM 100.00" "1" 0 Case Number 257 "THREFORK 100.00" "COBLSTNT 100.00" "1" 0 Page 567 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 258 1 "WILLWCKM 100.00" "MONTTALC 100.00" "1" 0 0 # # Case Number 259 1 "TOSTON 100.00" "TOSTON-R 100.00" "1" 0 20 0 # # Case Number 260 1 "CROWCREK 100.00" "BRDWTR T 100.00" "1" 0 0 # # Case Number 261 1 "HELVLY T 100.00" "HELVALLY 100.00" "1" 0 0 # # Case Number 262 1 "MTTUNTIE 100.00" "MTTUNELS 100.00" "1" 0 0 # # Case Number 263 1 "BRDWTR T 100.00" "BRODWATR 100.00" "1" 0 0 # # Case Number 264 1 "MISSLA 1 100.00" "CLINTN-R 100.00" "1" 0 0 # # Case Number 265 1 "MISSLA 1 100.00" "MISSLA 2 100.00" "1" 0 0 # # Case Number 266 1 "FRENCH-R 100.00" "ELMAR-R 100.00" "1" 0 0 # # Case Number 267 1 "ALBERTON 100.00" "TARKIO-R 100.00" "1" 0 0 # # Case Number 268 1 "ALBERTON 100.00" "HUSON-R 100.00" "1" 0 0 # Page 568 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 4 4 0 # 1 0 # # 1 0 # Case Number 269 "TARKIO-R 100.00" "DIAMNDMT 100.00" "1" 0 Case Number 270 "DIAMNDMT 100.00" "SUPERRMT 100.00" "1" 0 Case Number 271 "SUPERRMT 100.00" "ST REGIS 100.00" "1" 0 Case Number 272 "ST REGIS 100.00" "HAUGEN 100.00" "1" 0 Case Number 273 "HAUGEN 100.00" "SALTESE 100.00" "1" 0 Case Number 274 "MISSLA 2 100.00" "MISSLA 3 100.00" "1" 0 Case Number 275 "MISSLA 2 100.00" "MISSLA 5 100.00" "1" 0 Case Number 276 "FRONTRGT 100.00" "FRONTRNG 100.00" "1" 0 Case Number 277 "RIMROCK 69.00" "JOHNSONL 69.00" "1" 0 "JOHNSONL 69.00" 0 "1 " 0 "JOHNSONL 69.00" 0 "99" 0 Case Number 278 "BOLE 69.00" "RAINBOW 69.00" "99" 0 Case Number 279 "HAMLTNMT 69.00" "MILLERCK 69.00" "99" 0 Page 569 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 4 5 2 3 0 # # # 1 1 4 4 0 # # 1 4 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 280 "E HELENA 69.00" "HAUSER 69.00" "99" 0 "HAUSER 69.00" 0 "99" 0 "HAUSER 69.00" 0 "b " 0 "HAUSER 69.00" "HAUSER 2.40" "1 " "HAUSER 2.40" 0 "1 " 0 Case Number 281 "BILINGS 69.00" "PRYORREA 69.00" "1" 0 "PRYORREA 69.00" "PRYOR CK 69.00" "1" 0 "PRYORREA 69.00" 0 "1 " 0 "PRYOR CK 69.00" 0 "1 " 0 Case Number 282 "PRYOR CK 69.00" "PRYORREA 69.00" "1" 0 "PRYOR CK 69.00" 0 "1 " 0 Case Number 283 "RIMROCK 50.00" "BILINGSX 50.00" "99" 0 Case Number 284 "BILINGSX 50.00" "BILINGS 50.00" "99" 0 Case Number 285 "BILINGS 50.00" "BILINGSR 50.00" "1" 0 Case Number 286 "BILINGS8 50.00" "LAURELMT 50.00" "99" 0 Page 570 of 722 APPENDIX I – SWITCHING SEQUENCES ######################################################################## ########################## # # All 240 and 500 kV lines in Alberta south of a KEG cut plane. # ######################################################################## ########################## # # Case Number 287 1 "ELLERSLI 500.00" "GENESEE4 500.00" "09" 0 0 # # Case Number 288 1 "GENESEE4 500.00" "KEEPHILS 500.00" "03" 0 0 # # Case Number 289 1 "ELLERSLI 240.00" "E EDMON4 240.00" "08" 0 0 # # Case Number 290 1 "ELLERSLI 240.00" "RED DEE4 240.00" "10" 0 0 # # Case Number 291 1 "ELLERSLI 240.00" "KEEPHIL4 240.00" "02" 0 0 # # Case Number 292 1 "ELLERSLI 240.00" "DOME T29 240.00" "09" 0 0 # # Case Number 293 1 "ELLERSLI 240.00" "LAMBTON4 240.00" "04" 0 0 # # Case Number 294 1 "ELLERSLI 240.00" "ARGYLL E 240.00" "04" 0 0 # # Case Number 295 1 "ELLERSLI 240.00" "PETROLIA 240.00" "08" 0 0 # Page 571 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 296 1 "ELLERSLI 240.00" "946/947X 240.00" "47" 0 0 # # Case Number 297 1 "WABAMUN4 240.00" "SUNDANM9 240.00" "02" 0 0 # # Case Number 298 1 "WABAMUN4 240.00" "N CALDE4 240.00" "05" 0 0 # # Case Number 299 1 "WABAMUN4 240.00" "JASPER 4 240.00" "04" 0 0 # # Case Number 300 1 "SUNDANM9 240.00" "N BARRH4 240.00" "13" 0 20 0 # # Case Number 301 1 "SUNDANM9 240.00" "BENALTO4 240.00" "22" 0 0 # # Case Number 302 1 "SUNDANM9 240.00" "BENALTO4 240.00" "26" 0 0 # # Case Number 303 1 "SUNDANM9 240.00" "SAGITAW4 240.00" "19" 0 0 # # Case Number 304 1 "SUNDANM9 240.00" "SAGITAW4 240.00" "89" 0 20 0 # # Case Number 305 1 "SUNDANM9 240.00" "DOME T29 240.00" "09" 0 0 # Page 572 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 306 1 "SUNDANM9 240.00" "PETROLIA 240.00" "08" 0 0 # # Case Number 307 1 "E EDMON4 240.00" "CLOVERB4 240.00" "15" 0 0 # # Case Number 308 1 "E EDMON4 240.00" "946/947N 240.00" "46" 0 0 # # Case Number 309 1 "E EDMON4 240.00" "904AL TP 240.00" "04" 0 0 # # Case Number 310 1 "N CALDE4 240.00" "JASPER 4 240.00" "30" 0 0 # # Case Number 311 1 "N CALDE4 240.00" "CASTLTX2 240.00" "20" 0 0 # # Case Number 312 1 "GAETZ 4 240.00" "RED DEE4 240.00" "14" 0 0 # # Case Number 313 1 "WILLESD9 240.00" "BRAZEAU4 240.00" "95" 0 0 # # Case Number 314 1 "WILLESD9 240.00" "BENALTO4 240.00" "95" 0 20 0 # # Case Number 315 1 "RED DEE4 240.00" "BENALTO4 240.00" "00" 0 0 # # Case Number 316 1 "RED DEE4 240.00" "JANET 4 240.00" "25" 0 0 # Page 573 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 317 "RED DEE4 240.00" "JANET 4 240.00" "29" 0 Case Number 318 "RED DEE4 240.00" "CROSSF T 240.00" "01" 0 Case Number 319 "RED DEE4 240.00" "NEVIS 4 240.00" "12" 0 Case Number 320 "BENALTO4 240.00" "SARCEE 4 240.00" "06" 0 Case Number 321 "BENALTO4 240.00" "SARCEE 4 240.00" "28" 0 Case Number 322 "BENALTO4 240.00" "BEDDING1 240.00" "18" 0 Case Number 323 "BENALTO4 240.00" "KEEPHIL4 240.00" "03" 0 Case Number 324 "BENALTO4 240.00" "KEEPHIL4 240.00" "90" 0 Case Number 325 "E CROSS4 240.00" "CROSSF T 240.00" "01" 0 Case Number 326 "JANET 4 240.00" "E CALGAR 240.00" "17" 0 Case Number 327 "JANET 4 240.00" "PEIGAN 4 240.00" "11" 0 Page 574 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 328 1 "JANET 4 240.00" "BEDDING1 240.00" "32" 0 0 # # Case Number 329 1 "JANET 4 240.00" "CROSSF T 240.00" "01" 0 0 # # Case Number 330 1 "SARCEE 4 240.00" "E CALGAR 240.00" "16" 0 0 # # Case Number 331 1 "PEIGAN 4 240.00" "N LETHB4 240.00" "77" 0 0 # # Case Number 332 1 "PEIGAN 4 240.00" "PINCHER4 240.00" "75" 0 0 # # Case Number 333 1 "PEIGAN 4 240.00" "PINCHER4 240.00" "76" 0 0 # # Case Number 334 1 "PEIGAN 4 240.00" "GOOSEL4 240.00" "75" 0 0 # # Case Number 335 1 "PEIGAN 4 240.00" "GOOSEL4 240.00" "76" 0 0 # # Case Number 336 # Only works in pre project cases 1 "N LETHB4 240.00" "MATL_AB 240.00" "23" 0 0 # # Case Number 337 # Only works in pre project cases 1 "N LETHB4 240.00" "MILO 2 240.00" "23" 0 1 "LANGDON9 240.00" "MILO 2 240.00" "27" 0 1 "W BROOK4 240.00" "MILO 2 240.00" "23" 0 0 # Page 575 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 338 # Only works in post project cases 1 "MATL_AB 240.00" "MILO 2 240.00" "23" 0 1 "LANGDON9 240.00" "MILO 2 240.00" "27" 0 1 "W BROOK4 240.00" "MILO 2 240.00" "23" 0 0 # # Case Number 339 1 "N LETHB4 240.00" "MILO 1 240.00" "24" 0 1 "LANGDON9 240.00" "MILO 1 240.00" "24" 0 1 "W BROOK4 240.00" "MILO 1 240.00" "35" 0 0 # # Case Number 340 1 "LANGDON9 240.00" "JANET 4 240.00" "36" 0 20 0 # # Case Number 341 1 "PINCHER4 240.00" "WATWND 240.00" "W1" 0 0 # # Case Number 342 1 "BELLAMY4 240.00" "ARGYLL W 240.00" "04" 0 0 # # Case Number 343 1 "BELLAMY4 240.00" "ARGYLL E 240.00" "04" 0 0 # # Case Number 344 1 "ARGYLL W 240.00" "PETROLIA 240.00" "04" 0 0 # # Case Number 345 1 "EAST IN4 240.00" "904AL TP 240.00" "04" 0 2 "EAST IN4 240.00" "EASTINT1 25.00" "1 " 0 4 "EASTINT1 25.00" 0 "9 " 0 0 # # Case Number 346 1 "PAINTRT4 240.00" "CORDEL 4 240.00" "27" 0 0 # Page 576 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 347 1 "PAINTRT4 240.00" "HANSMAN7 240.00" "48" 0 20 0 # # Case Number 348 1 "NEVIS 4 240.00" "CORDEL 4 240.00" "20" 0 0 # # Case Number 349 3 "BAT #5 21.00" 0 "5 " 0 4 "BAT #5 21.00" 0 "SS" 0 20 2 "BAT RV79 240.00" "BAT #5 21.00" "1 " 0 1 "BAT RV79 240.00" "CORDEL 4 240.00" "79" 0 8 "BAT RV79 240.00" 8 "BAT #5 21.00" 20 0 # # Case Number 350 1 "CORDEL 4 240.00" "HANSMAN7 240.00" "53" 0 0 # ######################################################################## ########################## # # All 138 and 69 kV lines in Alberta south of a Calgary - Sheerness cut plane. # ######################################################################## ########################## # # Case Number 351 1 "BANFF 7 138.00" "W.CASC T 138.00" "54" 0 0 # # Case Number 352 1 "CAN CEM9 138.00" "742L JCT 138.00" "42" 0 0 # # Case Number 353 1 "COCHRAN9 138.00" "BEARSPAW 138.00" "60" 0 0 # Page 577 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 354 "COCHRAN9 138.00" "ANG COCH 138.00" "60" 0 Case Number 355 "SEEBE 9 138.00" "GHOST 9 138.00" "56" 0 Case Number 356 "SEEBE 9 138.00" "KANANAS7 138.00" "87" 0 Case Number 357 "SEEBE 9 138.00" "BARRIER7 138.00" "58" 0 Case Number 358 "SEEBE 9 138.00" "POCATER7 138.00" "77" 0 Case Number 359 "SEEBE 9 138.00" "JUMP TP2 138.00" "3" 0 Case Number 360 "SEEBE 9 138.00" "742L JCT 138.00" "54" 0 Case Number 361 "CASCADE7 138.00" "W.CASC T 138.00" "54" 0 Case Number 362 "GHOST 9 138.00" "ANG COCH 138.00" "59" 0 Case Number 363 "GHOST 9 138.00" "SPRAY S 138.00" "13" 0 Case Number 364 "GHOST 9 138.00" "JUMP TP1 138.00" "50" 0 Page 578 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 365 "GHOST 9 138.00" "MADDEN T 138.00" "80" 0 Case Number 366 "BEARSPAW 138.00" "ENMX21S7 138.00" "50" 0 Case Number 367 "BEARSPAW 138.00" "ENMX36S7 138.00" "81" 0 Case Number 368 "RUNDLE S 138.00" "SPRAY S 138.00" "84" 0 Case Number 369 "RUNDLE S 138.00" "54L JNC 138.00" "85" 0 Case Number 370 "SHELL J9 138.00" "JUMP TP1 138.00" "50" 0 Case Number 371 "JUMPPND9 138.00" "JUMP TP2 138.00" "3" 0 Case Number 372 "MOUNT A7 138.00" "BARRIER7 138.00" "90" 0 Case Number 373 "MOUNT A7 138.00" "SPRAY S 138.00" "76" 0 Case Number 374 "SHEPARD9 138.00" "CARSLAND 138.00" "50" 0 Case Number 375 "BLACK D9 138.00" "HART TAP 138.00" "12" 0 Page 579 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 376 "OKOTOKS9 138.00" "MAG TAP7 138.00" "27" 0 Case Number 377 "MAGCAN 7 138.00" "MAG TAP7 138.00" "27" 0 Case Number 378 "HIGH RI9 138.00" "BLACKIE7 138.00" "53" 0 Case Number 379 "HIGH RI9 138.00" "MAG TAP7 138.00" "27" 0 Case Number 380 "HIGH RI9 138.00" "HART TAP 138.00" "12" 0 Case Number 381 "HARTELL9 138.00" "HART TAP 138.00" "12" 0 Case Number 382 "CAVALIER 138.00" "NAMAKA 7 138.00" "01" 0 Case Number 383 "DUCHESS9 138.00" "831A TAP 138.00" "31" 0 Case Number 384 "CARSLAND 138.00" "BLACKIE7 138.00" "51" 0 Case Number 385 "CARSLAND 138.00" "WYNDHAM 138.00" "82" 0 Case Number 386 "BLACKIE7 138.00" "QUENSTWN 138.00" "52" 0 Page 580 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 387 "GLEICHE9 138.00" "QUENSTWN 138.00" "76" 0 Case Number 388 "GLEICHE9 138.00" "NAMAKA 7 138.00" "33" 0 Case Number 389 "BROOKSA9 138.00" "TILLEY 9 138.00" "00" 0 Case Number 390 "BROOKSA9 138.00" "W BROOK9 138.00" "14" 0 Case Number 391 "BROOKSA9 138.00" "W BROOK9 138.00" "27" 0 Case Number 392 "BROOKSA9 138.00" "HAYS 7 138.00" "95" 0 Case Number 393 "BROOKSA9 138.00" "831A TAP 138.00" "31" 0 Case Number 394 "STRATHM9 138.00" "NAMAKA 7 138.00" "33" 0 Case Number 395 "W BROOK9 138.00" "ENCH TAP 138.00" "63" 0 Case Number 396 "W BROOK9 138.00" "BASNTAP 138.00" "53" 0 Case Number 397 "CANMORE9 138.00" "BAYMAGB 138.00" "54" 0 Page 581 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 398 1 "CANMORE9 138.00" "54L JNC 138.00" "54" 0 0 # # Case Number 399 1 "BAYMAGB 138.00" "742L JCT 138.00" "54" 0 0 # # Case Number 400 1 "HUSSAR 8 138.00" "NAMAKA 7 138.00" "86" 0 0 # # Case Number 401 1 "POCATER7 138.00" "FRO T274 138.00" "1" 0 0 # # Case Number 402 # 1 "POCATER7 138.00" "BRITT TP 138.00" "87" 0 #0 # # Case Number 402 1 "QUENSTWN 138.00" "BASNTAP 138.00" "53" 0 0 # # Case Number 403 1 "BASSAN9 138.00" "BASNTAP 138.00" "53" 0 0 # # Case Number 404 1 "SPRINGB9 138.00" "JUMP TP2 138.00" "3" 0 0 # # Case Number 405 1 "CUTNG L9 138.00" "831A TAP 138.00" "31" 0 0 # # Case Number 406 1 "W.CASC T 138.00" "54L JNC 138.00" "54" 0 0 # # Case Number 407 1 "SANDYPT9 138.00" "DOME EM7 138.00" "69" 0 0 # Page 582 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 408 "SANDHIL7 138.00" "DOME EM7 138.00" "71" 0 Case Number 409 "STAVELY9 138.00" "STAVELEY 138.00" "97" 0 Case Number 411 "VULCAN 9 138.00" "BLACKIE7 138.00" "61" 0 Case Number 411 "VULCAN 9 138.00" "STAVELEY 138.00" "80" 0 Case Number 412 "EMP LIQ7 138.00" "EMPLIQTP 138.00" "60" 0 Case Number 413 "PANCAN 9 138.00" "DOME EM7 138.00" "60" 0 Case Number 414 "PANCAN 9 138.00" "CHAPPIC9 138.00" "60" 0 Case Number 415 "DOME EM7 138.00" "EMPLIQTP 138.00" "60" 0 Case Number 416 "DOME EM7 138.00" "MCNEILL 138.00" "30" 0 Case Number 417 "WARLOW9 138.00" "JENNER7 138.00" "52" 0 Case Number 418 "EMPLIQTP 138.00" "OYEN 7 138.00" "60" 0 Page 583 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 419 1 "SUNSHIN8 69.00" "BANFF 8 69.00" "51" 0 0 # # Case Number 420 1 "SUNSHIN8 69.00" "LAKE LO9 69.00" "51" 0 0 # # Case Number 421 4 "BLACK D8 69.00" 0 "9 " 0 20 1 "HIGH RI8 69.00" "BLACK D8 69.00" "13" 0 8 "BLACK D8 69.00" 20 0 # ######################################################################## ########################## # # Remaining contingencies # ######################################################################## ########################## # # Case Number 422 1 "ING500 500.00" "CUSTER W 500.00" "1 " 0 0 # # Case Number 423 1 "CUSTER W 500.00" "CUSTER&1 500.00" "1 " 0 1 "CUSTER&1 500.00" "MONROE 500.00" "1 " 0 20 0 # # Case Number 424 1 "CBK230 230.00" "AAL230 230.00" "1 " 0 1 "AAL230 230.00" "NLY230 230.00" "1 " 0 2 "AAL230 230.00" "AAL63 63.00" "1 " 0 0 # Page 584 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 425 # Nelway - Boundary 230 kV Line with RAS 2 "NLY230 230.00" "NLYPHS 230.00" "2 " 0 1 "NLYPHS 230.00" "BOUNDARY 230.00" "1 " 0 # required generation shedding 150 MW, actual shedding is 140 MW # Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW 3 "BOUNDRY2 14.4" 0 "5 " 0 0 # # Case Number 426 # Trip all 5 Libby units 3 "LIBBY 13.8" 0 "1 " 0 3 "LIBBY 13.8" 0 "2 " 0 20 3 "LIBBY 13.8" 0 "3 " 0 3 "LIBBY 13.8" 0 "4 " 0 3 "LIBBY 13.8" 0 "5 " 0 20 1 "TAFT 500.00" "BELL B&2 500.00" "1 " 0 1 "BELL B&2 500.00" "BELL B&1 500.00" "1 " 0 1 "BELL B&1 500.00" "BELL BPA 500.00" "1 " 0 0 # # Case Number 427 # Trip all 5 Libby units 3 "LIBBY 13.8" 0 "1 " 0 20 3 "LIBBY 13.8" 0 "2 " 0 20 3 "LIBBY 13.8" 0 "3 " 0 20 3 "LIBBY 13.8" 0 "4 " 0 20 3 "LIBBY 13.8" 0 "5 " 0 20 1 "TAFT 500.00" "DWORSH&2 500.00" "1 " 0 20 1 "DWORSH&2 500.00" "DWORSH&1 500.00" "1 " 0 20 1 "DWORSH&1 500.00" "DWORSHAK 500.00" "1 " 0 0 # Page 585 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 428 # Trip all Dworshak Units #2 & #3 3 "DWOR 2 13.8" 0 "1 " 0 20 3 "DWOR 3 13.8" 0 "1 " 0 # 20 # Trip Dworshak Ph 13.8kV bus tie breaker South of Boundary>1000MW -Trip Dworshak #2&#3 via opening betwwn DVOR 1 and DVOR 2 1 "DWOR 1 13.80" "DWOR 2 13.80" "1 " 0 # 20 # Trip all 5 Libby units 3 "LIBBY 13.8" 0 "1 " 0 20 3 "LIBBY 13.8" 0 "2 " 0 20 3 "LIBBY 13.8" 0 "3 " 0 20 3 "LIBBY 13.8" 0 "4 " 0 20 3 "LIBBY 13.8" 0 "5 " 0 20 1 "DWORSHAK 500.00" "HATWAI 500.00" "1 " 0 0 # # Case Number 429 # No Colestrip ATR according to Jeff's spreadsheet 1 "TAFT 500.00" "GARRIS&2 500.00" "1 " 0 20 1 "GARRIS&2 500.00" "GARRIS&1 500.00" "1 " 0 20 1 "GARRIS&1 500.00" "GARRISON 500.00" "1 " 0 0 # # Case Number 430 1 "BOUNDARY 230.00" "CUSICK 230.00" "1 " 0 1 "CUSICK 230.00" "CUSICK&1 230.00" "1 " 0 1 "CUSICK&1 230.00" "USK 230.00" "1 " 0 1 "CUSICK 230.00" "ADDY 230.00" "1 " 0 6 "CUSICK 230.00" 0 "v " 0 0 # Page 586 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 431 # Trip all 5 Libby units 3 "LIBBY 13.8" 0 "1 " 0 20 3 "LIBBY 13.8" 0 "2 " 0 20 3 "LIBBY 13.8" 0 "3 " 0 20 3 "LIBBY 13.8" 0 "4 " 0 20 3 "LIBBY 13.8" 0 "5 " 0 20 1 "TAFT 500.00" "BELL B&2 500.00" "1 " 0 20 1 "BELL B&2 500.00" "BELL B&1 500.00" "1 " 0 20 1 "BELL B&1 500.00" "BELL BPA 500.00" "1 " 0 # 1 "TAFT 500.00" "GARRIS&2 500.00" "1 " 0 20 1 "GARRIS&2 500.00" "GARRIS&1 500.00" "1 " 0 20 1 "GARRIS&1 500.00" "GARRISON 500.00" "1 " 0 0 # # Case Number 432 # Treated as a single Bell outage 1 "BELL S2 230.00" "BELL S&A 230.00" "1 " 0 20 1 "USK 230.00" "BELL S&A 230.00" "1 " 0 # 1 "BELL S1 230.00" "SACHEEN 230.00" "1 " 0 1 "BOUNDARY 230.00" "SACHEEN 230.00" "1 " 0 0 # Page 587 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 433 # Treated as a double Bell outage 1 "BELL S2 230.00" "BELL S&A 230.00" "1 " 0 20 1 "USK 230.00" "BELL S&A 230.00" "1 " 0 # 1 "BELL S1 230.00" "SACHEEN 230.00" "1 " 0 1 "BOUNDARY 230.00" "SACHEEN 230.00" "1 " 0 # required generation shedding must be leave less than 640MW # Shed unit 5 & 6 at 46407 BOUNDRY2 14.40 140 MW 3 "BOUNDRY2 14.4" 0 "5 " 0 3 "BOUNDRY2 14.4" 0 "6 " 0 0 # # Case Number 434 1 "BOUNDARY 230.00" "ADDY 2&A 230.00" "1 " 0 1 "ADDY 2&A 230.00" "ADDY 2 230.00" "1 " 0 1 "ADDY 2 230.00" "ADDY 2&1 230.00" "1 " 0 1 "ADDY 2&1 230.00" "BELL S3 230.00" "1 " 0 2 "ADDY 2 230.00" "ADDY 115.00" "1 " 0 # Loss of the Addy - Bell 1 115kV Line 1 "ADDY 115.00" "LOON LK 115.00" "1 " 0 1 "MEAD TAP 115.00" "BELL BPA 115.00" "1 " 0 0 # -1 # EOF Page 588 of 722 APPENDIX I – SWITCHING SEQUENCES Non-Simultaneous Analysis 07 LSP – Autocon Files Page 589 of 722 APPENDIX I – SWITCHING SEQUENCES Non-Sim_07lspIII2ac.acn DEFINE BASE CASE LIST 07lsp_pre_rev21htcl.sav SS "Non-Simultaneous, Pre-Project Base Case, Case III2a" 07lsp_ns_pst_s2n_rev21jtcl.sav SS "Non-Simultaneous, Post-Project, MATL-s2n flow, Case III-2c" DONE # The following contingencies are assembled based on page 9 of the Study Plan. # updaed 1-27-2007 tcl # updated 7-18-2006 cet # updated 8-1-2006 jle # updaed 9-10-2006 tcl # # Base Case -- Case Number 0 0 # ######################################################################## ########################## # # PROJECT CONTINGENCIES # ######################################################################## ########################## # # Case Number 1 2 "MATL_AB 240.00" "MATL_AB 230.00" "1" 0 1 "MATL_AB 230.00" "MATLN_&1 230.00" "1" 0 1 "MATLN_&1 230.00" "MARIAS 230.00" "1" 0 1 "MARIAS 230.00" "MATLN_&2 230.00" "1" 0 1 "MATLN_&2 230.00" "GT FALLS 230.00" "1" 0 0 # ######################################################################## ########################## # # All 230 and 500 kV lines in Montana # ######################################################################## ########################## # # Case Number 2 1 "MILL CRK 230.00" "GARRISON 230.00" "1" 0 0 Page 590 of 722 APPENDIX I – SWITCHING SEQUENCES # Page 591 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 3 1 "MILL CRK 230.00" "PTRSNFLT 230.00" "1" 0 1 "PTRSNFLT 230.00" "AMPS 230.00" "1" 0 1 "AMPS 230.00" "ANTLOPP 230.00" "1" 0 2 "AMPS 230.00" "AMPS 69.00" "1" 0 0 # # Case Number 4 1 "MILL CRK 230.00" "THRRIVER 230.00" "1" 0 0 # # Case Number 5 1 "MILL CRK 230.00" "ANA BPA 230.00" "1" 0 0 # # Case Number 6 1 "WILSALL 230.00" "SHOREYRD 230.00" "1" 0 0 # # Case Number 7 1 "WILSALL 230.00" "THRRIVER 230.00" "1" 0 0 # # Case Number 8 1 "SHELBY 230.00" "CNRDWAPA 230.00" "1" 0 20 0 # # Case Number 9 1 "BOLE 230.00" "CNRDWAPA 230.00" "1" 0 20 0 # # Case Number 10 1 "BOLE 230.00" "GT FALLS 230.00" "1" 0 0 # # Case Number 11 1 "JUDITHGP 230.00" "GT FALLS 230.00" "1" 0 1 "JUDITHGP 230.00" "JUDITHSO 230.00" "1" 0 2 "JUDITHGP 230.00" "JUDITHGP 100.00" "1" 0 0 # Page 592 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 1 2 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 Case Number 12 "JUDITHGP 230.00" "SOUTHERN 230.00" "1" 0 "JUDITHGP 230.00" "JUDITHSO 230.00" "1" 0 "JUDITHGP 230.00" "JUDITHGP 100.00" "1" 0 Case Number 13 "BROADVU 230.00" "JUDITHSO 230.00" "1" 0 Case Number 14 "BLGS PHA 230.00" "YELOWTLP 230.00" "1" 0 Case Number 15 "HARDIN 230.00" "COLSTRP 230.00" "1" 0 Case Number 16 "HARDIN 230.00" "CRSOVRUM 230.00" "1" 0 Case Number 17 "ALKALI 230.00" "SHOREYRD 230.00" "1" 0 Case Number 18 "ALKALI 230.00" "BILINGS 230.00" "1" 0 Case Number 19 "ALKALI 230.00" "BROADVU 230.00" "1" 0 Case Number 20 "BASELINE 230.00" "SHOREYRD 230.00" "1" 0 Case Number 21 "HUNTLEY 230.00" "BILINGS 230.00" "1" 0 Case Number 22 "HUNTLEY 230.00" "CRSOVRUM 230.00" "1" 0 Page 593 of 722 APPENDIX I – SWITCHING SEQUENCES # # Case Number 23 1 "GT FALLS 230.00" "OVANDO 230.00" "1" 0 0 # # Case Number 24 1 "GT FALLS 230.00" "LANDRSFK 230.00" "1" 0 1 "OVANDO 230.00" "LANDRSFK 230.00" "1" 0 0 # # Case Number 25 1 "GT FALLS 230.00" "SOUTHERN 230.00" "1" 0 0 # # Case Number 26 1 "GT FALLS 230.00" "SOUTHERN 230.00" "2" 0 0 # # Case Number 27 1 "GT FALLS 230.00" "MT 1STMW 230.00" "1" 0 0 # # Case Number 28 1 "GT FALLS 230.00" "MT 1STMW 230.00" "2" 0 0 # # Case Number 29 1 "OVANDO 230.00" "GARRISON 230.00" "1" 0 0 # # Case Number 30 1 "OVANDO 230.00" "HOT SPR 230.00" "1" 0 0 # # Case Number 31 1 "BILINGS 230.00" "BILINGSW 230.00" "1" 0 0 # # Case Number 32 1 "BILINGSW 230.00" "BROADVU 230.00" "1" 0 20 0 # Page 594 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 33 1 "ANA BPA 230.00" "GARRISON 230.00" "1" 0 20 0 # ######################################################################## ########################## # # All 161 kV and lower voltage lines in Montana north of Great Falls # ######################################################################## ########################## # # Case Number 34 1 "FT PECK 161.00" "RICHARDC 161.00" "1" 0 0 # # Case Number 35 1 "MALTA UM 161.00" "RICHARDC 161.00" "1" 0 20 20 0 # # Case Number 36 1 "HARLEM 161.00" "HAVRE 161.00" "1" 0 0 # # Case Number 37 1 "HARLEM 161.00" "MALTA UM 161.00" "1" 0 20 0 # # Case Number 38 1 "HAVRE 161.00" "VERONA 161.00" "1" 0 20 0 # # Case Number 39 1 "BONNERMT 161.00" "MILL CRK 161.00" "1" 0 0 # # Case Number 40 1 "BONNERMT 161.00" "RATTLE S 161.00" "1" 0 0 # Page 595 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 41 "BONNERMT 161.00" "MILLERCK 161.00" "1" 0 Case Number 42 "MILL CRK 161.00" "RATTLE S 161.00" "1" 0 Case Number 43 "MILL CRK 161.00" "MT ASIMI 161.00" "1" 0 Case Number 44 "MILL CRK 161.00" "MT ASIMI 161.00" "2" 0 Case Number 45 "MILL CRK 161.00" "DILLON S 161.00" "1" 0 Case Number 46 "KERR B 161.00" "RATTLE S 161.00" "1" 0 Case Number 47 "KERR A 161.00" "RATTLE S 161.00" "1" 0 Case Number 48 "RATTLE S 161.00" "RESERVST 161.00" "1" 0 Case Number 49 "BUTTEMHD 161.00" "MT ASIMI 161.00" "1" 0 Case Number 50 "BUTTEMHD 161.00" "BUTTE MT 161.00" "1" 0 Case Number 51 "WILSALL 161.00" "CLYDE P 161.00" "1" 0 Page 596 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 52 1 "MT ASIMI 161.00" "BUTTE MT 161.00" "1" 0 0 # # Case Number 53 1 "GT FALLS 161.00" "HAVRE 161.00" "1" 0 0 # # Case Number 54 1 "RAINBOW 161.00" "VERONA 161.00" "1" 0 0 # # Case Number 55 1 "RMRK PHA 161.00" "YELOWTLP 161.00" "1" 0 20 0 # # Case Number 56 1 "RIMROCK 161.00" "ALKALI 161.00" "1" 0 0 # # Case Number 57 1 "BRADLEYC 161.00" "ENNIS MT 161.00" "1" 0 0 # # Case Number 58 1 "BRADLEYC 161.00" "JACKRABT 161.00" "1" 0 0 # # Case Number 59 1 "ENNIS MT 161.00" "SHERDNMT 161.00" "1" 0 0 # # Case Number 60 1 "THRRIVER 161.00" "CLYDE P 161.00" "1" 0 0 # # Case Number 61 1 "THRRIVER 161.00" "GLDNSNLT 161.00" "1" 0 0 # # Case Number 62 1 "THRRIVER 161.00" "JACKRABT 161.00" "1" 0 0 # Page 597 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 63 "BUTTE MT 161.00" "GLDNSNLT 161.00" "1" 0 Case Number 64 "RESERVST 161.00" "MISSLA 7 161.00" "1" 0 Case Number 65 "MILLERCK 161.00" "MISSLA 7 161.00" "1" 0 Case Number 66 "MILLERCK 161.00" "HAMLTNMA 161.00" "1" 0 Case Number 67 "MILLERCK 161.00" "HAMLTNMB 161.00" "1" 0 Case Number 68 "DILLON S 161.00" "SHERDNMT 161.00" "1" 0 Case Number 69 "DILLON S 161.00" "BIGGRASS 161.00" "1" 0 Case Number 70 "CLYDE P 161.00" "EGALTNAB 161.00" "1" 0 Case Number 71 "CLYDE P 161.00" "EGALTNAB 161.00" "2" 0 Case Number 72 "CLYDE P 161.00" "EMIGT AT 161.00" "1" 0 Case Number 73 "CLYDE P 161.00" "DUCKCR-R 161.00" "1" 0 Page 598 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 74 1 "ALKALI 161.00" "COLRPLJE 161.00" "1" 0 0 # # Case Number 75 1 "COLRPLJE 161.00" "CLMBUSPM 161.00" "1" 0 0 # # Case Number 76 1 "COLRPLJE 161.00" "BGTMBERA 161.00" "1" 0 20 0 # # Case Number 77 1 "EGALTNAB 161.00" "BOZMN WS 161.00" "1" 0 0 # # Case Number 78 1 "BGTMBERA 161.00" "DUCKCR-R 161.00" "1" 0 0 # # Case Number 79 1 "JACKRABT 161.00" "BOZMN WS 161.00" "1" 0 0 # # Case Number 80 1 "TAFTAUTO 115.00" "CROWCR B 115.00" "1" 0 0 # # Case Number 81 1 "SHELBY 115.00" "CUTBANK 115.00" "1" 0 0 # # Case Number 82 1 "SHELBY 115.00" "TIBERTAP 115.00" "1" 0 0 # # Case Number 83 1 "CUTBANK 115.00" "CTBPUMP 115.00" "1" 0 0 # # Case Number 84 1 "ANA BPA 115.00" "SLVR BOW 115.00" "1" 0 0 # Page 599 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 85 1 "MONTANA1 115.00" "COLSTRP 115.00" "1" 0 0 # # Case Number 86 1 "MONTANA1 115.00" "NICHOL-R 115.00" "1" 0 0 # # Case Number 87 1 "KERR 115.00" "PLAINS 115.00" "1" 0 0 # # Case Number 88 1 "KERR 115.00" "THMRVR T 115.00" "1" 0 0 # # Case Number 89 1 "CNRDWAPA 115.00" "CONRAD 115.00" "1" 0 0 # # Case Number 90 1 "CNRDWAPA 115.00" "DUTTON 115.00" "1" 0 0 # # Case Number 91 1 "CNRDWAPA 115.00" "CNRD-SRA 115.00" "1" 0 0 # # Case Number 92 1 "GT FALLS 115.00" "DUTTON 115.00" "1" 0 0 # # Case Number 93 1 "HARDIN 115.00" "SARPY AT 115.00" "1" 0 0 # # Case Number 94 1 "COLSTRP 115.00" "ARMELLCR 115.00" "1" 0 20 0 # # Case Number 95 1 "CROWCR B 115.00" "THOMSON 115.00" "1" 0 0 # Page 600 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 96 1 "THOMSON 115.00" "TFALLCIT 115.00" "1" 0 20 0 # # Case Number 97 1 "THOMSON 115.00" "TFALCITA 115.00" "1" 0 0 # # Case Number 98 1 "CONRAD 115.00" "VAL-WILL 115.00" "1" 0 0 # # Case Number 99 1 "CTBPUMP 115.00" "VAL-WILL 115.00" "1" 0 0 # # Case Number 100 1 "NICHOLPM 115.00" "NICHOL-R 115.00" "1" 0 0 # # Case Number 101 1 "ARMELLCR 115.00" "CASTLERT 115.00" "1" 0 0 # # Case Number 102 1 "CASTLERT 115.00" "CASTLERK 115.00" "1" 0 20 0 # # Case Number 103 1 "CASTLERT 115.00" "SARPY AT 115.00" "1" 0 0 # # Case Number 104 1 "PLAINS 115.00" "TFALCITA 115.00" "1" 0 0 # # Case Number 105 1 "THFLPM T 115.00" "TFALLCIT 115.00" "1" 0 0 # # Case Number 106 1 "THFLPM T 115.00" "THFALLPM 115.00" "1" 0 0 Page 601 of 722 APPENDIX I – SWITCHING SEQUENCES # # Case Number 107 1 "THFLPM T 115.00" "THMRVR T 115.00" "1" 0 20 0 # # Case Number 108 1 "TFALLCIT 115.00" "THFALL-R 115.00" "1" 0 0 # # Case Number 109 1 "THMRVRGN 115.00" "THMRVR T 115.00" "1" 0 20 0 # # Case Number 110 1 "CLMBUS-R 100.00" "COLRPLJE 100.00" "1" 0 20 0 # # Case Number 111 1 "CLMBUS-R 100.00" "COLBUSAT 100.00" "1" 0 0 # # Case Number 112 1 "THREERIV 100.00" "TRIDENT 100.00" "1" 0 0 # # Case Number 113 1 "MADISON 100.00" "BRADLEYC 100.00" "1" 0 0 # # Case Number 114 1 "MORONY 100.00" "GT FALLS 100.00" "1" 0 0 # # Case Number 115 1 "COCHRAN 100.00" "RAINBOW 100.00" "1" 0 20 0 # # Case Number 116 1 "RYAN 100.00" "MTGENJCT 100.00" "1" 0 0 # Page 602 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 117 "RYAN 100.00" "MTGENJCT 100.00" "2" 0 Case Number 118 "TRIDENT 100.00" "EUSTIS 100.00" "1" 0 Case Number 119 "TRIDENT 100.00" "TRIDTPLT 100.00" "1" 0 Case Number 120 "TRIDENT 100.00" "THREFORK 100.00" "1" 0 Case Number 121 "BROADVU 100.00" "PANTROBE 100.00" "1" 0 Case Number 122 "BROADVU 100.00" "LAVINAPT 100.00" "1" 0 Case Number 123 "BROADVU 100.00" "FISHCK-R 100.00" "1" 0 Case Number 124 "TAFTAUTO 100.00" "SALTESE 100.00" "1" 0 Case Number 125 "WALDORF 100.00" "FRENCH-R 100.00" "1" 0 Case Number 126 "WALDORF 100.00" "HUSON-R 100.00" "1" 0 Case Number 127 "WALDORF 100.00" "BUTLERCR 100.00" "1" 0 Page 603 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 128 1 "RIMROCK 100.00" "BILINGS 100.00" "1" 0 0 # # Case Number 129 1 "RIMROCK 100.00" "BERTOOTH 100.00" "1" 0 0 # # Case Number 130 1 "RIMROCK 100.00" "BILL ES 100.00" "1" 0 0 # # Case Number 131 1 "BILINGS 100.00" "BILINGS8 100.00" "1" 0 0 # # Case Number 132 1 "BILINGS 100.00" "LAURELMT 100.00" "1" 0 0 # # Case Number 133 1 "BILINGS 100.00" "CONOCOMT 100.00" "1" 0 0 # # Case Number 134 1 "BILINGS 100.00" "BILLCITY 100.00" "1" 0 0 # # Case Number 135 1 "BILINGS 100.00" "BILL ES 100.00" "1" 0 0 # # Case Number 136 1 "BILINGS8 100.00" "BILLCITY 100.00" "1" 0 20 0 # # Case Number 137 1 "BILINGS8 100.00" "BELLROCK 100.00" "1" 0 0 # # Case Number 138 1 "BILINGS8 100.00" "KING AVE 100.00" "1" 0 0 # Page 604 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 139 1 "BASELINE 100.00" "MERIDNMT 100.00" "1" 0 0 # # Case Number 140 1 "BASELINE 100.00" "GRNDAV-R 100.00" "1" 0 20 0 # # Case Number 141 1 "BASELINE 100.00" "BL72ST-R 100.00" "1" 0 0 # # Case Number 142 1 "JUDITHGP 100.00" "JUDITGPT 100.00" "1" 0 0 # # Case Number 143 1 "JUDITHGP 100.00" "STRAWXPT 100.00" "1" 0 0 # # Case Number 144 1 "JUDITHGP 100.00" "FRONTRGT 100.00" "1" 0 0 # # Case Number 145 1 "BRADLEYC 100.00" "HAR-PONY 100.00" "1" 0 0 # # Case Number 146 1 "BRADLEYC 100.00" "COBLSTNT 100.00" "1" 0 0 # # Case Number 147 1 "HARLOWTN 100.00" "PANTROBE 100.00" "1" 0 0 # # Case Number 148 1 "HARLOWTN 100.00" "TWO DOT 100.00" "1" 0 0 # # Case Number 149 1 "HARLOWTN 100.00" "JUDITGPT 100.00" "1" 0 0 # Page 605 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 150 "HARLOWTN 100.00" "FISHCK-R 100.00" "1" 0 Case Number 151 "LAURELMT 100.00" "RAIL TAP 100.00" "1" 0 Case Number 152 "LAURELMT 100.00" "CENEX B 100.00" "1" 0 Case Number 153 "LAURELMT 100.00" "LAURELPM 100.00" "1" 0 Case Number 154 "LAURELMT 100.00" "EDGARXPT 100.00" "1" 0 Case Number 155 "LAURELMT 100.00" "BRIDGERA 100.00" "2" 0 Case Number 156 "LAURELMT 100.00" "LAUREL 100.00" "1" 0 Case Number 157 "MILLERCK 100.00" "MISSLA 5 100.00" "1" 0 Case Number 158 "RESERVST 100.00" "MISSLA 1 100.00" "1" 0 Case Number 159 "RESERVST 100.00" "ELMAR-R 100.00" "1" 0 Case Number 160 "RATTLE S 100.00" "MISSLA 1 100.00" "1" 0 Page 606 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 161 1 "RATTLE S 100.00" "MISSLA 3 100.00" "1" 0 0 # # Case Number 162 1 "RATTLE S 100.00" "BUTLERCR 100.00" "1" 0 0 # # Case Number 163 1 "MILL CRK 100.00" "ANA CITY 100.00" "1" 0 0 # # Case Number 164 1 "MILL CRK 100.00" "ANA CITY 100.00" "2" 0 0 # # Case Number 165 1 "MILL CRK 100.00" "MOREL 100.00" "1" 0 20 0 # # Case Number 166 1 "MILL CRK 100.00" "PCIFICST 100.00" "1" 0 0 # # Case Number 167 1 "BUTTE MT 100.00" "RENOVA 100.00" "1" 0 0 # # Case Number 168 1 "BUTTE MT 100.00" "CONDR TA 100.00" "1" 0 0 # # Case Number 169 1 "BUTTE MT 100.00" "CONDR TB 100.00" "1" 0 0 # # Case Number 170 1 "BUTTE MT 100.00" "BTMINDPK 100.00" "1" 0 0 # # Case Number 171 1 "GT FALLS 100.00" "RAINBOW 100.00" "1" 0 0 # Page 607 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 172 1 "GT FALLS 100.00" "RAINBOW 100.00" "2" 0 0 # # Case Number 173 1 "GT FALLS 100.00" "GFCITYT1 100.00" "1" 0 1 "GF CITY 100.00" "GFCITYT1 100.00" "1" 0 1 "GF CITY 100.00" "GF SSIDE 100.00" "1" 0 0 # # Case Number 174 1 "GT FALLS 100.00" "GF RVRVW 100.00" "1" 0 0 # # Case Number 175 1 "RAINBOW 100.00" "BELT 100.00" "1" 0 0 # # Case Number 176 1 "RAINBOW 100.00" "GF NEAST 100.00" "1" 0 0 # # Case Number 177 1 "RAINBOW 100.00" "WAYNEPMT 100.00" "1" 0 0 # # Case Number 178 1 "RAINBOW 100.00" "MALMSTRM 100.00" "1" 0 20 0 # # Case Number 179 1 "RAINBOW 100.00" "MTGENJCT 100.00" "1" 0 0 # # Case Number 180 1 "HOLTER 100.00" "CANYONCR 100.00" "1" 0 1 "CANYONCR 100.00" "GILBERT 100.00" "1" 0 1 "GOLD CR 100.00" "GILBERT 100.00" "1" 0 1 "GOLD CR 100.00" "DRLDG CM 100.00" "1" 0 1 "GOLD CR 100.00" "MT PHOST 100.00" "1" 0 1 "MT PHOST 100.00" "DRUMPM T 100.00" "1" 0 1 "DRUMPM T 100.00" "DRUMMNMT 100.00" "1" 0 1 "DRUMPM T 100.00" "DRUMN PM 100.00" "1" 0 0 Page 608 of 722 APPENDIX I – SWITCHING SEQUENCES # # 1 0 # # 1 1 1 1 1 0 # # 1 1 1 1 0 # # 1 1 1 1 1 1 0 # # 1 0 # # 1 1 1 1 1 1 1 1 1 1 0 Case Number 181 "HOLTER 100.00" "HELVLY T 100.00" "1" 0 Case Number 182 "E HELENA 100.00" "CANFERTA 100.00" "1" 0 "CANFERTA 100.00" "SPOKANEA 100.00" "1" 0 "CANYON F 100.00" "SPOKANEA 100.00" "1" 0 "ADEL 100.00" "CANFERTA 100.00" "1" 0 "GF SSIDE 100.00" "ADEL 100.00" "1" 0 Case Number 183 "E HELENA 100.00" "CANFERTB 100.00" "1" 0 "GF ESIDE 100.00" "CANFERTB 100.00" "1" 0 "CANFERTB 100.00" "SPOKANEB 100.00" "1" 0 "CANYON F 100.00" "SPOKANEB 100.00" "1" 0 Case Number 184 "E HELENA 100.00" "CONLIM T 100.00" "1" 0 "CONLIM T 100.00" "TOWNSEND 100.00" "1" 0 "CONLIM T 100.00" "CONTLIME 100.00" "1" 0 "TOWNSEND 100.00" "TOSTON 100.00" "1" 0 "TOWNSEND 100.00" "TOWNSD-R 100.00" "1" 0 "TOSTON 100.00" "BRDWTR T 100.00" "1" 0 Case Number 185 "E HELENA 100.00" "HELVLY T 100.00" "1" 0 Case Number 186 "E HELENA 100.00" "HELSS TA 100.00" "1" 0 "HELSS TA 100.00" "CLANCYTA 100.00" "1" 0 "MTTUNTPA 100.00" "CLANCYTA 100.00" "1" 0 "MTTUNTPA 100.00" "MTTUNTIE 100.00" "1" 0 "MTTUNTPA 100.00" "BOULDRTA 100.00" "1" 0 "BOULDRTA 100.00" "BOULDTIE 100.00" "1" 0 "BOULDRAT 100.00" "BOULDTIE 100.00" "1" 0 "BASINMT 100.00" "BOULDRTA 100.00" "1" 0 "PRECIPIT 100.00" "BASINMT 100.00" "1" 0 "BUTECORA 100.00" "PRECIPIT 100.00" "1" 0 Page 609 of 722 APPENDIX I – SWITCHING SEQUENCES # # 1 1 1 1 1 1 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 Case Number 187 "E HELENA 100.00" "HELSS TB 100.00" "1" 0 "HELSS TB 100.00" "CLANCYTB 100.00" "1" 0 "CLANCYTB 100.00" "CLNCYTIE 100.00" "1" 0 "CLNCYTIE 100.00" "CLANCY 100.00" "1" 0 "MTTUNTAP 100.00" "CLANCYTB 100.00" "1" 0 "MTTUNTAP 100.00" "BOULDRTB 100.00" "1" 0 "BARGE PM 100.00" "BOULDRTB 100.00" "1" 0 Case Number 188 "CANYON F 100.00" "SPOKANEB 100.00" "1" 0 Case Number 189 "BEAGLE 100.00" "GF RVRVW 100.00" "1" 0 Case Number 190 "MOREL 100.00" "DERLDG T 100.00" "1" 0 Case Number 191 "MOREL 100.00" "FAIRMTMT 100.00" "1" 0 Case Number 192 "DERLDG T 100.00" "DRLDGCTY 100.00" "1" 0 Case Number 193 "DERLDG T 100.00" "DRLDG CM 100.00" "1" 0 Case Number 194 "FAIRMTMT 100.00" "RAMSAYPM 100.00" "1" 0 Case Number 195 "DRLDGCTY 100.00" "DRLDG CM 100.00" "1" 0 Case Number 196 "BUTECRSH 100.00" "MONST TP 100.00" "1" 0 Page 610 of 722 APPENDIX I – SWITCHING SEQUENCES # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 197 "BUTECRSH 100.00" "BUT CONC 100.00" "1" 0 Case Number 198 "BUTECORA 100.00" "PCIFICST 100.00" "1" 0 Case Number 199 "BUTECORA 100.00" "MONST TP 100.00" "1" 0 Case Number 200 "BUTECORA 100.00" "TAILBOS2 100.00" "1" 0 Case Number 201 "MONST TP 100.00" "MONT ST 100.00" "1" 0 Case Number 202 "BUT CONC 100.00" "TAILBOOS 100.00" "1" 0 Case Number 203 "BUT CONC 100.00" "CONDR TB 100.00" "1" 0 Case Number 204 "MONT ST 100.00" "RAMSAYPM 100.00" "1" 0 Case Number 205 "MONT ST 100.00" "BTMINDPK 100.00" "1" 0 Case Number 206 "TAILBOOS 100.00" "CONDR TA 100.00" "1" 0 Case Number 207 "TAILBOS2 100.00" "BARGE PM 100.00" "1" 0 Page 611 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 1 1 1 1 1 1 0 Case Number 208 "RENOVA 100.00" "MAYFLWRT 100.00" "1" 0 Case Number 209 "RENOVA 100.00" "MONTTALC 100.00" "1" 0 Case Number 210 "DRMCLARK 100.00" "CLINTN-R 100.00" "1" 0 Case Number 211 "DRMCLARK 100.00" "DRUMMNMT 100.00" "1" 0 Case Number 212 "CONDR TA 100.00" "CONTDRVE 100.00" "1" 0 Case Number 213 "CONDR TB 100.00" "CONTDRVE 100.00" "1" 0 Case Number 214 "MAYFLWRT 100.00" "MAYFLWRM 100.00" "1" 0 Case Number 215 "MAYFLWRT 100.00" "HAR-PONY 100.00" "1" 0 Case Number 216 "GF NWEST 100.00" "GF SWEST 100.00" "1" 0 Case Number 217 "GF NWEST 100.00" "GF NW T1 100.00" "1" 0 "GF NW T1 100.00" "HORSHOET 100.00" "1" 0 "HORSHOET 100.00" "ULM TAP 100.00" "1" 0 "ULM MT 100.00" "ULM TAP 100.00" "1" 0 "MISSIONM 100.00" "ULM TAP 100.00" "1" 0 "MISSIONM 100.00" "CRAIGMT 100.00" "1" 0 "HOLTER 100.00" "CRAIGMT 100.00" "1" 0 Page 612 of 722 APPENDIX I – SWITCHING SEQUENCES # # 1 1 1 1 1 1 1 # # 1 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 1 1 1 1 0 # # 1 0 # # 1 0 # # 1 0 Case Number 218 "GF NWEST 100.00" "GF NW T1 100.00" "1" 0 "GF NW T1 100.00" "HORSHOET 100.00" "1" 0 "HORSHOET 100.00" "ULM TAP 100.00" "1" 0 "ULM MT 100.00" "ULM TAP 100.00" "1" 0 "MISSIONM 100.00" "ULM TAP 100.00" "1" 0 "MISSIONM 100.00" "CRAIGMT 100.00" "1" 0 "HOLTER 100.00" "CRAIGMT 100.00" "1" 0 Case Number 219 "GF NWEST 100.00" "GF NW T2 100.00" "1" 0 "GF NW T2 100.00" "GF RVRVW 100.00" "1" 0 Case Number 220 "GF NWEST 100.00" "GFCITYT2 100.00" "1" 0 Case Number 221 "GF SWEST 100.00" "GF SSIDE 100.00" "1" 0 Case Number 222 "GF ESIDE 100.00" "GF ES A 100.00" "1" 0 Case Number 223 "GF SSIDE 100.00" "GF ES A 100.00" "1" 0 "GF ES A 100.00" "GF NEAST 100.00" "1" 0 "GF ESIDE 100.00" "GF ES A 100.00" "1" 0 "GT FALLS 100.00" "GF ESIDE 100.00" "1" 0 "GF ESIDE 100.00" "CANFERTB 100.00" "1" 0 Case Number 224 "WAYNE PM 100.00" "WAYNEPMT 100.00" "1" 0 Case Number 225 "RAYNE PM 100.00" "RNFRDP T 100.00" "1" 0 Case Number 226 "MONARCHM 100.00" "KINGHILL 100.00" "1" 0 Page 613 of 722 APPENDIX I – SWITCHING SEQUENCES # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 Case Number 227 "MONARCHM 100.00" "BELT 100.00" "1" 0 Case Number 228 "KINGHILL 100.00" "MARTNSDA 100.00" "1" 0 Case Number 229 "GF NW T1 100.00" "GF NW T2 100.00" "1" 0 Case Number 230 "GFCITYT1 100.00" "GFCITYT2 100.00" "1" 0 Case Number 231 "RNFRDP T 100.00" "NORNFDPT 100.00" "1" 0 Case Number 232 "RNFRDP T 100.00" "STANFRDM 100.00" "1" 0 Case Number 233 "WAYNEPMT 100.00" "NORNFDPT 100.00" "1" 0 Case Number 234 "NORNFDPT 100.00" "NORNFDPM 100.00" "1" 0 Case Number 235 "RAIL TAP 100.00" "RAILWELD 100.00" "1" 0 Case Number 236 "RAIL TAP 100.00" "BL72ST-R 100.00" "1" 0 Case Number 237 "CENEX A 100.00" "CENEX B 100.00" "1" 0 Page 614 of 722 APPENDIX I – SWITCHING SEQUENCES # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 238 "CENEX A 100.00" "LAURELPM 100.00" "1" 0 Case Number 239 "PANTROBE 100.00" "ROUNDUPM 100.00" "1" 0 Case Number 240 "CONOCOMT 100.00" "BILLNGPM 100.00" "1" 0 Case Number 241 "MERIDNMT 100.00" "BELLROCK 100.00" "1" 0 Case Number 242 "MERIDNMT 100.00" "SHILOH 100.00" "1" 0 Case Number 243 "BILLNGPM 100.00" "BERTOOTH 100.00" "1" 0 Case Number 244 "ABSRKE-R 100.00" "ABSAROKE 100.00" "1" 0 Case Number 245 "ABSAROKE 100.00" "COLBUSAT 100.00" "1" 0 Case Number 246 "ABSAROKE 100.00" "CHROMEAT 100.00" "1" 0 Case Number 247 "KING AVE 100.00" "SHILOH 100.00" "1" 0 Case Number 248 "EDGARXPM 100.00" "EDGARXPT 100.00" "1" 0 Page 615 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 249 "EDGARXPT 100.00" "BRIDGERA 100.00" "1" 0 Case Number 250 "LAVINAPT 100.00" "LAVINAPM 100.00" "1" 0 Case Number 251 "LAVINAPT 100.00" "ROUNDUPM 100.00" "1" 0 Case Number 252 "COLBUSAT 100.00" "STLWTRSM 100.00" "1" 0 Case Number 253 "TWO DOT 100.00" "MARTNSDA 100.00" "1" 0 Case Number 254 "TWO DOT 100.00" "LOWETH 100.00" "1" 0 Case Number 255 "UTICAPMP 100.00" "UTICATAP 100.00" "1" 0 Case Number 256 "UTICATAP 100.00" "BENCHLND 100.00" "1" 0 Case Number 257 "UTICATAP 100.00" "UTICA 100.00" "1" 0 Case Number 258 "BENCHLND 100.00" "STANFRDM 100.00" "1" 0 Case Number 259 "BENCHLND 100.00" "GLENGARY 100.00" "1" 0 Page 616 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 260 "GLENGARY 100.00" "STRAWXPT 100.00" "1" 0 Case Number 261 "JUDITGPT 100.00" "JUDTHSMT 100.00" "1" 0 Case Number 262 "JUDGAPSM 100.00" "JUDTHSMT 100.00" "1" 0 Case Number 263 "JUDTHPMP 100.00" "JUDTHSMT 100.00" "1" 0 Case Number 264 "UTICA-R 100.00" "UTICA 100.00" "1" 0 Case Number 265 "UTICA 100.00" "FRONTRGT 100.00" "1" 0 Case Number 266 "STRAWXPM 100.00" "STRAWXPT 100.00" "1" 0 Case Number 267 "EUSTIS 100.00" "CROWCREK 100.00" "1" 0 Case Number 268 "COBLSTON 100.00" "COBLSTNT 100.00" "1" 0 Case Number 269 "THREFORK 100.00" "WILLWCKM 100.00" "1" 0 Case Number 270 "THREFORK 100.00" "COBLSTNT 100.00" "1" 0 Page 617 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 271 1 "WILLWCKM 100.00" "MONTTALC 100.00" "1" 0 0 # # Case Number 272 1 "CANFERTB 100.00" "SPOKANEB 100.00" "1" 0 0 # # Case Number 273 1 "TOSTON 100.00" "TOSTON-R 100.00" "1" 0 0 # # Case Number 274 1 "CROWCREK 100.00" "BRDWTR T 100.00" "1" 0 0 # # Case Number 275 1 "HELVLY T 100.00" "HELVALLY 100.00" "1" 0 20 0 # # Case Number 276 1 "HELSS TA 100.00" "HELENASS 100.00" "1" 0 0 # # Case Number 277 1 "HELSS TB 100.00" "HELENASS 100.00" "1" 0 0 # # Case Number 278 1 "MTTUNTAP 100.00" "MTTUNTIE 100.00" "1" 0 0 # # Case Number 279 1 "MTTUNTIE 100.00" "MTTUNELS 100.00" "1" 0 0 # # Case Number 280 1 "CLANCYTA 100.00" "CLNCYTIE 100.00" "1" 0 0 # # Case Number 281 1 "BRDWTR T 100.00" "BRODWATR 100.00" "1" 0 0 # Page 618 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 282 1 "MISSLA 1 100.00" "CLINTN-R 100.00" "1" 0 0 # # Case Number 283 1 "MISSLA 1 100.00" "MISSLA 2 100.00" "1" 0 0 # # Case Number 284 1 "FRENCH-R 100.00" "ELMAR-R 100.00" "1" 0 0 # # Case Number 285 1 "ALBERTON 100.00" "TARKIO-R 100.00" "1" 0 20 0 # # Case Number 286 1 "ALBERTON 100.00" "HUSON-R 100.00" "1" 0 0 # # Case Number 287 1 "TARKIO-R 100.00" "DIAMNDMT 100.00" "1" 0 0 # # Case Number 288 1 "DIAMNDMT 100.00" "SUPERRMT 100.00" "1" 0 0 # # Case Number 289 1 "SUPERRMT 100.00" "ST REGIS 100.00" "1" 0 0 # # Case Number 290 1 "ST REGIS 100.00" "HAUGEN 100.00" "1" 0 0 # # Case Number 291 1 "HAUGEN 100.00" "SALTESE 100.00" "1" 0 0 # # Case Number 292 1 "MISSLA 2 100.00" "MISSLA 3 100.00" "1" 0 0 # Page 619 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # 1 0 # # 1 0 # # 1 0 # # # 1 0 # # 1 1 0 # # 1 0 # 1 0 # Case Number 293 "MISSLA 2 100.00" "MISSLA 5 100.00" "1" 0 Case Number 294 "FRONTRGT 100.00" "FRONTRNG 100.00" "1" 0 Case Number 295 "BOULDRTB 100.00" "BOULDTIE 100.00" "1" 0 Case Number 296 "RIMROCK 69.00" "JOHNSONL 69.00" "1" 0 Case Number 297 "BOLE 69.00" "RAINBOW 69.00" "99" 0 Case Number 298 "HAMLTNMT 69.00" "MILLERCK 69.00" "99" 0 Case Number 299 "E HELENA 69.00" "HAUSER 69.00" "99" 0 Case Number 300 "HUNTLEY 69.00" "HARDINA2 69.00" "99" 0 Case Number 301 "BILINGS 69.00" "PRYORREA 69.00" "1" 0 "PRYORREA 69.00" "PRYOR CK 69.00" "1" 0 Case Number 302 "PRYOR CK 69.00" "PRYORREA 69.00" "1" 0 Case Number 303 "RIMROCK 50.00" "BILINGSX 50.00" "99" 0 Page 620 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 304 1 "BILINGSX 50.00" "BILINGS 50.00" "99" 0 0 # # Case Number 305 1 "EGALLATN 50.00" "JACKRABT 50.00" "99" 0 0 # ######################################################################## ########################## # # All 240 and 500 kV lines in Alberta south of a KEG cut plane. # ######################################################################## ########################## # # Case Number 306 1 "ELLERSLI 500.00" "GENESEE4 500.00" "09" 0 0 # # Case Number 307 1 "GENESEE4 500.00" "KEEPHILS 500.00" "03" 0 0 # # Case Number 308 1 "ELLERSLI 240.00" "RED DEE4 240.00" "10" 0 0 # # Case Number 309 1 "ELLERSLI 240.00" "KEEPHIL4 240.00" "02" 0 0 # # Case Number 310 1 "ELLERSLI 240.00" "DOME T29 240.00" "09" 0 0 # # Case Number 311 1 "ELLERSLI 240.00" "LAMBTON4 240.00" "04" 0 0 # # Case Number 312 1 "ELLERSLI 240.00" "ARGYLL E 240.00" "04" 0 0 # Page 621 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 313 "ELLERSLI 240.00" "PETROLIA 240.00" "08" 0 Case Number 314 "ELLERSLI 240.00" "946/947X 240.00" "47" 0 Case Number 315 "WABAMUN4 240.00" "SUNDANM9 240.00" "02" 0 Case Number 316 "WABAMUN4 240.00" "N CALDE4 240.00" "05" 0 Case Number 317 "WABAMUN4 240.00" "JASPER 4 240.00" "04" 0 Case Number 318 "SUNDANM9 240.00" "N BARRH4 240.00" "13" 0 Case Number 319 "SUNDANM9 240.00" "BENALTO4 240.00" "22" 0 Case Number 320 "SUNDANM9 240.00" "BENALTO4 240.00" "26" 0 Case Number 321 "SUNDANM9 240.00" "SAGITAW4 240.00" "19" 0 Case Number 322 "SUNDANM9 240.00" "SAGITAW4 240.00" "89" 0 Case Number 323 "SUNDANM9 240.00" "DOME T29 240.00" "09" 0 Page 622 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 324 1 "SUNDANM9 240.00" "PETROLIA 240.00" "08" 0 0 # # Case Number 325 1 "E EDMON4 240.00" "CLOVERB4 240.00" "15" 0 0 # # Case Number 326 1 "E EDMON4 240.00" "946/947N 240.00" "46" 0 0 # # Case Number 327 1 "E EDMON4 240.00" "904AL TP 240.00" "04" 0 0 # # Case Number 328 1 "N CALDE4 240.00" "JASPER 4 240.00" "30" 0 0 # # Case Number 329 1 "N CALDE4 240.00" "CASTLTX2 240.00" "20" 0 0 # # Case Number 330 1 "GAETZ 4 240.00" "RED DEE4 240.00" "14" 0 0 # # Case Number 331 1 "WILLESD9 240.00" "BRAZEAU4 240.00" "95" 0 0 # # Case Number 332 1 "WILLESD9 240.00" "BENALTO4 240.00" "95" 0 20 0 # # Case Number 333 1 "RED DEE4 240.00" "BENALTO4 240.00" "00" 0 20 0 # # Case Number 334 1 "RED DEE4 240.00" "JANET 4 240.00" "25" 0 0 # Page 623 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 335 "RED DEE4 240.00" "JANET 4 240.00" "29" 0 Case Number 336 "RED DEE4 240.00" "CROSSF T 240.00" "01" 0 Case Number 337 "RED DEE4 240.00" "NEVIS 4 240.00" "12" 0 Case Number 338 "BENALTO4 240.00" "SARCEE 4 240.00" "06" 0 Case Number 339 "BENALTO4 240.00" "SARCEE 4 240.00" "28" 0 Case Number 340 "BENALTO4 240.00" "BEDDING1 240.00" "18" 0 Case Number 341 "BENALTO4 240.00" "KEEPHIL4 240.00" "03" 0 Case Number 342 "BENALTO4 240.00" "KEEPHIL4 240.00" "90" 0 Case Number 343 "E CROSS4 240.00" "CROSSF T 240.00" "01" 0 Case Number 344 "JANET 4 240.00" "E CALGAR 240.00" "17" 0 Case Number 345 "JANET 4 240.00" "PEIGAN 4 240.00" "11" 0 Page 624 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 1 1 0 # Case Number 346 "JANET 4 240.00" "BEDDING1 240.00" "32" 0 Case Number 347 "JANET 4 240.00" "CROSSF T 240.00" "01" 0 Case Number 348 "SARCEE 4 240.00" "E CALGAR 240.00" "16" 0 Case Number 349 "PEIGAN 4 240.00" "N LETHB4 240.00" "77" 0 Case Number 350 "PEIGAN 4 240.00" "N LETHB4 240.00" "78" 0 Case Number 351 "PEIGAN 4 240.00" "PINCHER4 240.00" "75" 0 Case Number 352 "PEIGAN 4 240.00" "PINCHER4 240.00" "76" 0 Case Number 353 "PEIGAN 4 240.00" "GOOSEL4 240.00" "75" 0 Case Number 354 "PEIGAN 4 240.00" "GOOSEL4 240.00" "76" 0 Case Number 355 "N LETHB4 240.00" "MATL_AB 240.00" "23" 0 Case Number 356 "N LETHB4 240.00" "MILO 2 240.00" "23" 0 "LANGDON9 240.00" "MILO 2 240.00" "27" 0 "W BROOK4 240.00" "MILO 2 240.00" "23" 0 Page 625 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 357 1 "MATL_AB 240.00" "MILO 2 240.00" "23" 0 1 "LANGDON9 240.00" "MILO 2 240.00" "27" 0 1 "W BROOK4 240.00" "MILO 2 240.00" "23" 0 0 # # Case Number 358 1 "N LETHB4 240.00" "MILO 1 240.00" "24" 0 1 "LANGDON9 240.00" "MILO 1 240.00" "24" 0 1 "W BROOK4 240.00" "MILO 1 240.00" "35" 0 0 # # Case Number 359 1 "LANGDON9 240.00" "JANET 4 240.00" "36" 0 20 0 # # Case Number 360 1 "PINCHER4 240.00" "WATWND 240.00" "W1" 0 0 # # Case Number 361 2 "KEEPHIL4 240.00" "KEEPHIL7 138.00" "T1" 0 0 # # Case Number 362 1 "BELLAMY4 240.00" "ARGYLL W 240.00" "04" 0 0 # # Case Number 363 1 "BELLAMY4 240.00" "ARGYLL E 240.00" "04" 0 0 # # Case Number 364 1 "ARGYLL W 240.00" "PETROLIA 240.00" "04" 0 0 # # Case Number 365 1 "EASTINT1 240.00" "904AL TP 240.00" "04" 0 0 # # Case Number 366 1 "PAINTRT4 240.00" "CORDEL 4 240.00" "27" 0 0 # Page 626 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 367 1 "PAINTRT4 240.00" "HANSMAN7 240.00" "48" 0 0 # # Case Number 368 1 "NEVIS 4 240.00" "CORDEL 4 240.00" "20" 0 0 # # Case Number 369 3 "BAT #5 21.00" 0 "5 " 0 4 "BAT #5 21.00" 0 "SS" 0 20 2 "BAT RV79 240.00" "BAT #5 21.00" "5T" 0 1 "BAT RV79 240.00" "CORDEL 4 240.00" "79" 0 8 "BAT RV79 240.00" 8 "BAT #5 21.00" 20 0 # # Case Number 370 1 "CORDEL 4 240.00" "HANSMAN7 240.00" "53" 0 0 # ######################################################################## ########################## # # All 138 and 69 kV lines in Alberta south of a Calgary - Sheerness cut plane. # ######################################################################## ########################## # # Case Number 371 1 "BANFF 7 138.00" "W.CASC T 138.00" "54" 0 0 # # Case Number 372 1 "CAN CEM9 138.00" "742L JCT 138.00" "42" 0 0 # # Case Number 373 1 "COCHRAN9 138.00" "BEARSPAW 138.00" "60" 0 0 # Page 627 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 374 "COCHRAN9 138.00" "ANG COCH 138.00" "60" 0 Case Number 375 "SEEBE 9 138.00" "GHOST 9 138.00" "56" 0 Case Number 376 "SEEBE 9 138.00" "KANANAS7 138.00" "87" 0 Case Number 377 "SEEBE 9 138.00" "BARRIER7 138.00" "58" 0 Case Number 378 "SEEBE 9 138.00" "POCATER7 138.00" "77" 0 Case Number 379 "SEEBE 9 138.00" "JUMP TP2 138.00" "3" 0 Case Number 380 "SEEBE 9 138.00" "742L JCT 138.00" "54" 0 Case Number 381 "CASCADE7 138.00" "W.CASC T 138.00" "54" 0 Case Number 382 "GHOST 9 138.00" "ANG COCH 138.00" "59" 0 Case Number 383 "GHOST 9 138.00" "SPRAY S 138.00" "13" 0 Case Number 384 "GHOST 9 138.00" "JUMP TP1 138.00" "50" 0 Page 628 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 385 "GHOST 9 138.00" "MADDEN T 138.00" "80" 0 Case Number 386 "BEARSPAW 138.00" "ENMX21S7 138.00" "50" 0 Case Number 387 "BEARSPAW 138.00" "ENMX36S7 138.00" "81" 0 Case Number 388 "RUNDLE S 138.00" "SPRAY S 138.00" "84" 0 Case Number 389 "RUNDLE S 138.00" "54L JNC 138.00" "85" 0 Case Number 390 "SHELL J9 138.00" "JUMP TP1 138.00" "50" 0 Case Number 391 "JUMPPND9 138.00" "JUMP TP2 138.00" "3" 0 Case Number 392 "MOUNT A7 138.00" "BARRIER7 138.00" "90" 0 Case Number 393 "MOUNT A7 138.00" "SPRAY S 138.00" "76" 0 Case Number 394 "SHEPARD9 138.00" "CARSLAND 138.00" "50" 0 Case Number 395 "BLACK D9 138.00" "HART TAP 138.00" "12" 0 Page 629 of 722 APPENDIX I – SWITCHING SEQUENCES # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # # 1 0 # Case Number 396 "OKOTOKS9 138.00" "MAG TAP7 138.00" "27" 0 Case Number 397 "MAGCAN 7 138.00" "MAG TAP7 138.00" "27" 0 Case Number 398 "HIGH RI9 138.00" "BLACKIE7 138.00" "53" 0 Case Number 399 "HIGH RI9 138.00" "MAG TAP7 138.00" "27" 0 Case Number 400 "HIGH RI9 138.00" "HART TAP 138.00" "12" 0 Case Number 401 "HARTELL9 138.00" "HART TAP 138.00" "12" 0 Case Number 402 "CAVALIER 138.00" "NAMAKA 7 138.00" "01" 0 Case Number 403 "DUCHESS9 138.00" "831A TAP 138.00" "31" 0 Case Number 404 "CARSLAND 138.00" "BLACKIE7 138.00" "51" 0 Case Number 405 "CARSLAND 138.00" "WYNDHAM 138.00" "82" 0 Case Number 406 "BLACKIE7 138.00" "QUENSTWN 138.00" "52" 0 Page 630 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 407 1 "GLEICHE9 138.00" "QUENSTWN 138.00" "76" 0 0 # # Case Number 408 1 "GLEICHE9 138.00" "NAMAKA 7 138.00" "33" 0 0 # # Case Number 409 1 "BROOKSA9 138.00" "TILLEY 9 138.00" "00" 0 0 # # Case Number 410 1 "BROOKSA9 138.00" "W BROOK9 138.00" "14" 0 0 # # Case Number 411 1 "BROOKSA9 138.00" "W BROOK9 138.00" "27" 0 0 # # Case Number 412 1 "BROOKSA9 138.00" "HAYS 7 138.00" "95" 0 20 0 # # Case Number 413 1 "BROOKSA9 138.00" "831A TAP 138.00" "31" 0 0 # # Case Number 414 1 "STRATHM9 138.00" "NAMAKA 7 138.00" "33" 0 0 # # Case Number 415 1 "W BROOK9 138.00" "ENCH TAP 138.00" "63" 0 0 # # Case Number 416 1 "CANMORE9 138.00" "BAYMAGB 138.00" "54" 0 0 # # Case Number 417 1 "CANMORE9 138.00" "54L JNC 138.00" "54" 0 0 # Page 631 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 418 1 "BAYMAGB 138.00" "742L JCT 138.00" "54" 0 0 # # Case Number 419 1 "POCATER7 138.00" "FRO T274 138.00" "1" 0 0 # # Case Number 420 1 "SPRINGB9 138.00" "JUMP TP2 138.00" "3" 0 0 # # Case Number 421 1 "CUTNG L9 138.00" "831A TAP 138.00" "31" 0 0 # # Case Number 422 1 "W.CASC T 138.00" "54L JNC 138.00" "54" 0 0 # # Case Number 423 1 "SANDYPT9 138.00" "DOME EM7 138.00" "69" 0 20 0 # # Case Number 424 1 "SANDHIL7 138.00" "DOME EM7 138.00" "71" 0 0 # # Case Number 425 1 "STAVELY9 138.00" "STAVELEY 138.00" "97" 0 20 0 # # Case Number 426 1 "VULCAN 9 138.00" "BLACKIE7 138.00" "61" 0 0 # # Case Number 427 1 "VULCAN 9 138.00" "STAVELEY 138.00" "80" 0 0 # # Case Number 428 1 "EMP LIQ7 138.00" "EMPLIQTP 138.00" "60" 0 0 Page 632 of 722 APPENDIX I – SWITCHING SEQUENCES # # Case Number 429 1 "PANCAN 9 138.00" "DOME EM7 138.00" "60" 0 0 # # Case Number 430 1 "PANCAN 9 138.00" "CHAPPIC9 138.00" "60" 0 0 # # Case Number 431 1 "DOME EM7 138.00" "EMPLIQTP 138.00" "60" 0 0 # # Case Number 432 1 "DOME EM7 138.00" "MCNEILL 138.00" "30" 0 0 # # Case Number 433 1 "WARLOW9 138.00" "JENNER7 138.00" "52" 0 0 # # Case Number 434 1 "EMPLIQTP 138.00" "OYEN 7 138.00" "60" 0 0 # # Case Number 435 1 "SUNSHIN8 69.00" "BANFF 8 69.00" "51" 0 0 # # Case Number 436 1 "SUNSHIN8 69.00" "LAKE LO9 69.00" "51" 0 0 # # Case Number 437 4 "BLACK D8 69.00" 0 "99" 0 20 1 "HIGH RI8 69.00" "BLACK D8 69.00" "13" 0 8 "BLACK D8 69.00" 20 0 # ######################################################################## ########################## # # Remaining contingencies # Page 633 of 722 APPENDIX I – SWITCHING SEQUENCES ######################################################################## ########################## # # Case Number 438 1 "ING500 500.00" "CUSTER W 500.00" "1 " 0 0 # # Case Number 439 1 "CUSTER W 500.00" "CUSTER&1 500.00" "1 " 0 1 "CUSTER&1 500.00" "MONROE 500.00" "1 " 0 20 0 # # Case Number 440 1 "CBK230 230.00" "AAL230 230.00" "1 " 0 1 "AAL230 230.00" "NLY230 230.00" "1 " 0 2 "AAL230 230.00" "AAL63 63.00" "1 " 0 0 # # Case Number 441 # Nelway - Boundary 230 kV Line with RAS 2 "NLY230 230.00" "NLYPHS 230.00" "2 " 0 1 "NLYPHS 230.00" "BOUNDARY 230.00" "1 " 0 # required generation shedding 150 MW, actual shedding is 140 MW # Shed unit 5 at 46407 BOUNDRY2 14.40 140 MW 3 "BOUNDG55 14.4" 0 "55" 0 0 # Page 634 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 442 1 "TAFT 500.00" "BELL S&1 500.00" "1 " 0 1 "BELL S&1 500.00" "BELL SC 500.00" "1 " 0 1 "BELL SC 500.00" "BELL BPA 500.00" "1 " 0 20 # Tripping Garrison reactor 5 "GARRISON 500.00" 0 "b " 0 20 # Tripping Miles City DC tie 4 "MILCTYDC 230.00" 0 "D1" 0 20 # Trip all 5 Libby units 3 "LIB 01 13.8" 0 "1 " 0 20 3 "LIB 02 13.8" 0 "2 " 0 20 3 "LIB 03 13.8" 0 "3 " 0 20 3 "LIB 04 13.8" 0 "4 " 0 20 3 "LIB 05 13.8" 0 "5 " 0 0 # Page 635 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 443 # Tripping Garrison reactor 5 "GARRISON 500.00" 0 "b " 0 20 # Tripping Miles City DC tie 4 "MILCTYDC 230.00" 0 "D1" 0 20 # Trip all 5 Libby units 3 "LIB 01 13.8" 0 "1 " 0 20 3 "LIB 02 13.8" 0 "2 " 0 20 3 "LIB 03 13.8" 0 "3 " 0 20 3 "LIB 04 13.8" 0 "4 " 0 20 3 "LIB 05 13.8" 0 "5 " 0 # South of Boundary>1000MW -Trip Dworshak #2&#3 via opening betwwn DVOR 1 and DVOR 2 1 40361 40363 "1 " 0 20 # Trip all Dworshak Units #2 & #3 3 "DWOR 2 13.8" 0 "1 " 0 20 3 "DWOR 3 13.8" 0 "1 " 0 # 20 # Trip Dworshak Ph 13.8kV bus tie breaker South of Boundary>1000MW -Trip Dworshak #2&#3 via opening betwwn DVOR 1 and DVOR 2 1 "DWOR 1 13.80" "DWOR 2 13.80" "1 " 0 # 20 # Rathdrum II (Lancaster) Gen Drop 3 "LANCAS G 18.0" 0 "1 " 0 # 20 3 "LANCAS S 13.8" 0 "1 " 0 # 1 "DWORSHAK 500.00" "HATWAI 500.00" "1 " 0 0 # Page 636 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 444 # Rathdrum II (Lancaster) Gen Drop 3 "LANCAS G 18.0" 0 "1 " 0 20 3 "LANCAS S 13.8" 0 "1 " 0 # 20 # Tripping Garrison reactor 5 "GARRISON 500.00" 0 "b " 0 20 # Tripping Miles City DC tie 4 "MILCTYDC 230.00" 0 "D1" 0 # Trip all 5 Libby units 3 "LIB 01 13.8" 0 "1 " 0 20 3 "LIB 02 13.8" 0 "2 " 0 20 3 "LIB 03 13.8" 0 "3 " 0 20 3 "LIB 04 13.8" 0 "4 " 0 20 3 "LIB 05 13.8" 0 "5 " 0 1 "TAFT 500.00" "DWORSH&2 500.00" "1 " 0 20 1 "DWORSH&2 500.00" "DWORSH&1 500.00" "1 " 0 20 1 "DWORSH&1 500.00" "DWORSHAK 500.00" "1 " 0 0 # # Case Number 445 # No Colestrip ATR according to Jeff's spreadsheet # Tripping Miles City DC tie 4 "MILCTYDC 230.00" 0 "D1" 0 20 # Tripping Garrison reactor 5 "GARRISON 500.00" 0 "b " 0 20 1 "TAFT 500.00" "GARRIS&2 500.00" "1 " 0 20 1 "GARRIS&2 500.00" "GARRIS&1 500.00" "1 " 0 20 1 "GARRIS&1 500.00" "GARRISON 500.00" "1 " 0 0 # # Page 637 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 446 1 "BOUNDARY 230.00" "CUSICK 230.00" "1 " 0 1 "CUSICK 230.00" "CUSICK&1 230.00" "1 " 0 1 "CUSICK&1 230.00" "USK 230.00" "1 " 0 1 "CUSICK 230.00" "ADDY 230.00" "1 " 0 6 "CUSICK 230.00" 0 "v " 0 0 # # Case Number 447 # Tripping Garrison reactor 5 "GARRISON 500.00" 0 "b " 0 20 # Tripping Miles City DC tie 4 "MILCTYDC 230.00" 0 "D1" 0 20 # Trip all 5 Libby units 3 "LIB 01 13.8" 0 "1 " 0 20 3 "LIB 02 13.8" 0 "2 " 0 20 3 "LIB 03 13.8" 0 "3 " 0 20 3 "LIB 04 13.8" 0 "4 " 0 20 3 "LIB 05 13.8" 0 "5 " 0 20 1 "TAFT 500.00" "BELL S&1 500.00" "1 " 0 20 1 "BELL S&1 500.00" "BELL SC 500.00" "1 " 0 20 1 "BELL SC 500.00" "BELL BPA 500.00" "1 " 0 # 1 "TAFT 500.00" "GARRIS&2 500.00" "1 " 0 20 1 "GARRIS&2 500.00" "GARRIS&1 500.00" "1 " 0 20 1 "GARRIS&1 500.00" "GARRISON 500.00" "1 " 0 0 # Page 638 of 722 APPENDIX I – SWITCHING SEQUENCES # Case Number 448 # Treated as a single Bell outage 1 "BELL S2 230.00" "BELL S&A 230.00" "1 " 0 20 1 "USK 230.00" "BELL S&A 230.00" "1 " 0 # 1 "BELL S1 230.00" "SACHEEN 230.00" "1 " 0 1 "BOUNDARY 230.00" "SACHEEN 230.00" "1 " 0 0 # # Case Number 449 # Treated as a double Bell outage 1 "BELL S2 230.00" "BELL S&A 230.00" "1 " 0 20 1 "USK 230.00" "BELL S&A 230.00" "1 " 0 # 1 "BELL S1 230.00" "SACHEEN 230.00" "1 " 0 1 "BOUNDARY 230.00" "SACHEEN 230.00" "1 " 0 # required generation shedding must be leave less than 640MW # Shed unit 5 & 6 at 46407 BOUNDRY2 14.40 140 MW 3 "BOUNDG55 14.4" 0 "55" 0 3 "BOUNDG56 14.4" 0 "56" 0 0 # # Case Number 450 1 "BOUNDARY 230.00" "ADDY 2&A 230.00" "1 " 0 1 "ADDY 2&A 230.00" "ADDY 2 230.00" "1 " 0 1 "ADDY 2 230.00" "ADDY 2&1 230.00" "1 " 0 1 "ADDY 2&1 230.00" "BELL S3 230.00" "1 " 0 2 "ADDY 2 230.00" "ADDY 115.00" "1 " 0 # Loss of the Addy - Bell 1 115kV Line 1 "ADDY 115.00" "LOON LK 115.00" "1 " 0 1 "MEAD TAP 115.00" "BELL BPA 115.00" "1 " 0 0 # # -1 # EOF Page 639 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 1 07 HS – Autocon Files Page 640 of 722 APPENDIX I – SWITCHING SEQUENCES PATH1v2.pfp GLOBAL COMMANDS BASE CASE LIST 07hs_pre_iv2-2afix1.sav 07hs_pst_iv2-2bfix1.sav DONE SS "PRE-PROJECT BASE CASE" SS "PST-PROJECT BASE CASE" OUTPUT FILE PATH C:\upslf16\MyPSLF GET CASE PATH C:\upslf16\MyPSLF SAVE CASE PATH C:\upslf16\MyPSLF IN-RUN EPCL PATH C:\upslf16\MyPSLF BASE CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 1 TCUL TAP RATIO ADJUSTMENT 1 AUTOMATIC SVD ADJUSTMENT 1 PHASE SHIFTER ADJUSTMENT 1 AREA INTERCHANGE CONTROL 1 DONE CONTINGENCY CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 0 TCUL TAP RATIO ADJUSTMENT 0 AUTOMATIC SVD ADJUSTMENT 0 PHASE SHIFTER ADJUSTMENT 0 AREA INTERCHANGE CONTROL 0 SOLUTION TOLERANCE 1.0 DONE Page 641 of 722 APPENDIX I – SWITCHING SEQUENCES MONITOR AREA OR ZONE VIOLATIONS AREA 40 AREA 50 AREA 52 AREA 54 AREA 60 AREA 62 AREA 63 DONE # MONITOR BRANCH # "NTL138 138.00" "LCCTAP 138.00" "1" # "NTL138 138.00" "COLEMAN7 138.00" "1" # "MATL_AB 240.00" "MATL_AB 230.00" "1" # DONE LOCAL COMMANDS **** CASE NUMBER **** 0 COMMENT N-0 BASE CASE DONE # PROJECT CONTINGENCIES **** CASE NUMBER **** 1 COMMENT T-1 MATL_AB 240/230KV TRANSFORMER BANK OPEN XFMR "MATL_AB 240.00" "MATL_AB 230.00" "1" OPEN LINE "MATL_AB 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&2 230.00" "1" 1 OPEN LINE "GT FALLS 230.00" "MATLN_&2 230.00" "1" 1 DELETE ISLANDS DONE Page 642 of 722 APPENDIX I – SWITCHING SEQUENCES # All 230 and 500 kV lines in Montana **** CASE NUMBER **** 2 COMMENT N-1 MILL CRK-GARRISON 230kV OPEN LINE "MILL CRK 230.00" "GARRISON 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 3 COMMENT N-1 MILL CRK-PTRSNFLT-AMPS-ANTLOPP 230kV OPEN LINE "MILL CRK 230.00" "PTRSNFLT 230.00" "1" 0 OPEN LINE "PTRSNFLT 230.00" "AMPS 230.00" "1" 0 OPEN LINE "AMPS 230.00" "ANTLOPP 230.00" "1" 0 OPEN XFMR "AMPS 230.00" "AMPS 69.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 4 COMMENT N-1 MILL CRK-THRRIVER 230kV OPEN LINE "MILL CRK 230.00" "THRRIVER 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 5 COMMENT N-1 MILL CRK-ANA BPA 230kV OPEN LINE "MILL CRK 230.00" "ANA BPA 230.00" "1" 0 DELETE ISLANDS DONE Page 643 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 6 COMMENT N-1 WILSALL-SHOREYRD 230kV OPEN LINE "WILSALL 230.00" "SHOREYRD 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 7 COMMENT N-1 WILSALL-THRRIVER 230kV OPEN LINE "WILSALL 230.00" "THRRIVER 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 8 COMMENT N-1 SHELBY-CNRDWAPA 230kV OPEN LINE "SHELBY 230.00" "CNRDWAPA 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 9 COMMENT N-1 BOLE-CNRDWAPA 230kV OPEN LINE "BOLE 230.00" "CNRDWAPA 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 10 COMMENT N-1 BOLE-GT FALLS 230kV OPEN LINE "BOLE 230.00" "GT FALLS 230.00" "1" 0 DELETE ISLANDS DONE Page 644 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 11 COMMENT N-1 JUDITHGP-GT FALLS 230kV OPEN LINE "JUDITHGP 230.00" "GT FALLS 230.00" "1" 0 OPEN LINE "JUDITHGP 230.00" "JUDITHSO 230.00" "1" 0 OPEN XFMR "JUDITHGP 230.00" "JUDITHGP 100.00" "1" 0 DELETE ISLANDS DONE #**** CASE NUMBER **** ?? #COMMENT #N-1 JUDITHGP-SOUTHERN 230kV #OPEN LINE #"JUDITHGP 230.00" "SOUTHERN 230.00" "1" 0 #OPEN LINE #"JUDITHGP 230.00" "JUDITHSO 230.00" "1" 0 #OPEN XFMR #"JUDITHGP 230.00" "JUDITHGP 100.00" "1" 0 #DELETE ISLANDS #DONE **** CASE NUMBER **** 12 COMMENT N-1 BROADVU-JUDITHSO 230kV OPEN LINE "BROADVU 230.00" "JUDITHSO 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 13 COMMENT N-1 BLGS PHA-YELOWTLP 230kV OPEN LINE "BLGS PHA 230.00" "YELOWTLP 230.00" "1" 0 DELETE ISLANDS DONE Page 645 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 14 COMMENT N-1 HARDIN-COLSTRP 230kV OPEN LINE "HARDIN 230.00" "COLSTRP 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 15 COMMENT N-1 HARDIN-CRSOVRUM 230kV OPEN LINE "HARDIN 230.00" "CRSOVRUM 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 16 COMMENT N-1 ALKALI-SHOREYRD 230kV OPEN LINE "ALKALI 230.00" "SHOREYRD 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 17 COMMENT N-1 ALKALI-BILINGS 230kV OPEN LINE "ALKALI 230.00" "BILINGS 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 18 COMMENT N-1 ALKALI-BROADVU 230kV OPEN LINE "ALKALI 230.00" "BROADVU 230.00" "1" 0 DELETE ISLANDS DONE Page 646 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 19 COMMENT N-1 BASELINE-SHOREYRD 230kV OPEN LINE "BASELINE 230.00" "SHOREYRD 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 20 COMMENT N-1 HUNTLEY-BILINGS 230kV OPEN LINE "HUNTLEY 230.00" "BILINGS 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 21 COMMENT N-1 HUNTLEY-RSOVRUM 230kV OPEN LINE "HUNTLEY 230.00" "CRSOVRUM 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 22 COMMENT N-1 GT FALLS-OVANDO 230kV OPEN LINE "GT FALLS 230.00" "OVANDO 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 23 COMMENT N-1 GT FALLS-LANDRSFK-OVANDO 230kV OPEN LINE "GT FALLS 230.00" "LANDRSFK 230.00" "1" 0 OPEN LINE "OVANDO 230.00" "LANDRSFK 230.00" "1" 0 DELETE ISLANDS DONE Page 647 of 722 APPENDIX I – SWITCHING SEQUENCES #**** CASE NUMBER **** ?? #COMMENT #N-1 GT FALLS-SOUTHERN 230kV #1 #OPEN LINE #"GT FALLS 230.00" "SOUTHERN 230.00" "1" 0 #DELETE ISLANDS #DONE #**** CASE NUMBER **** ?? #COMMENT #N-1 GT FALLS-SOUTHERN 230kV #2 #OPEN LINE #"GT FALLS 230.00" "SOUTHERN 230.00" "2" 0 #DELETE ISLANDS #DONE #**** CASE NUMBER **** ?? #COMMENT #N-1 GT FALLS-MT 1STMW 230kV #1 #OPEN LINE #"GT FALLS 230.00" "MT 1STMW 230.00" "1" 0 #DELETE ISLANDS #DONE #**** CASE NUMBER **** ?? #COMMENT #N-1 GT FALLS-MT 1STMW 230kV #2 #OPEN LINE #"GT FALLS 230.00" "MT 1STMW 230.00" "2" 0 #DELETE ISLANDS #DONE **** CASE NUMBER **** 24 COMMENT N-1 OVANDO-GARRISON 230kV OPEN LINE "OVANDO 230.00" "GARRISON 230.00" "1" 0 DELETE ISLANDS DONE Page 648 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 25 COMMENT N-1 OVANDO-HOT SPR 230kV OPEN LINE "OVANDO 230.00" "HOT SPR 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 26 COMMENT N-1 BILINGS-BILINGSW 230kV OPEN LINE "BILINGS 230.00" "BILINGSW 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 27 COMMENT N-1 BILINGSW-BROADVU 230kV OPEN LINE "BILINGSW 230.00" "BROADVU 230.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 28 COMMENT N-1 ANA BPA-GARRISON 230kV OPEN LINE "ANA BPA 230.00" "GARRISON 230.00" "1" 0 DELETE ISLANDS DONE # All 240 and 500 kV lines in Alberta south of a KEG cut plane. **** CASE NUMBER **** 29 COMMENT N-1 ELLERSLI-GENESEE4 500kV OPEN LINE "ELLERSLI 500.00" "GENESEE4 500.00" "09" 0 DELETE ISLANDS DONE Page 649 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 30 COMMENT N-1 GENESEE4-KEEPHILS 500kV OPEN LINE "GENESEE4 500.00" "KEEPHILS 500.00" "03" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 31 COMMENT N-1 ELLERSLI-E EDMON4 240kV OPEN LINE "ELLERSLI 240.00" "E EDMON4 240.00" "08" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 32 COMMENT N-1 ELLERSLI-RED DEE4 240kV OPEN LINE "ELLERSLI 240.00" "RED DEE4 240.00" "10" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 33 COMMENT N-1 ELLERSLI-KEEPHIL4 240kV OPEN LINE "ELLERSLI 240.00" "KEEPHIL4 240.00" "02" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 34 COMMENT N-1 ELLERSLI-DOME T29 240kV OPEN LINE "ELLERSLI 240.00" "DOME T29 240.00" "09" 0 DELETE ISLANDS DONE Page 650 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 35 COMMENT N-1 ELLERSLI-LAMBTON4 240kV OPEN LINE "ELLERSLI 240.00" "LAMBTON4 240.00" "04" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 36 COMMENT N-1 ELLERSLI-ARGYLL E 240kV OPEN LINE "ELLERSLI 240.00" "ARGYLL E 240.00" "04" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 37 COMMENT N-1 ELLERSLI-PETROLIA 240kV OPEN LINE "ELLERSLI 240.00" "PETROLIA 240.00" "08" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 38 COMMENT N-1 ELLERSLI-946/947X 240kV OPEN LINE "ELLERSLI 240.00" "946/947X 240.00" "47" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 39 COMMENT N-1 WABAMUN4-SUNDANM9 240kV OPEN LINE "WABAMUN4 240.00" "SUNDANM9 240.00" "02" 0 DELETE ISLANDS DONE Page 651 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 40 COMMENT N-1 WABAMUN4-N CALDE4 240kV OPEN LINE "WABAMUN4 240.00" "N CALDE4 240.00" "05" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 41 COMMENT N-1 WABAMUN4-JASPER 4 240kV OPEN LINE "WABAMUN4 240.00" "JASPER 4 240.00" "04" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 42 COMMENT N-1 SUNDANM9-N BARRH4 240kV OPEN LINE "SUNDANM9 240.00" "N BARRH4 240.00" "13" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 43 COMMENT N-1 SUNDANM9-BENALTO4 240kV OPEN LINE "SUNDANM9 240.00" "BENALTO4 240.00" "22" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 44 COMMENT N-1 SUNDANM9-BENALTO4 240kV OPEN LINE "SUNDANM9 240.00" "BENALTO4 240.00" "26" 0 DELETE ISLANDS DONE Page 652 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 45 COMMENT N-1 SUNDANM9-SAGITAW4 240kV #19 OPEN LINE "SUNDANM9 240.00" "SAGITAW4 240.00" "19" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 46 COMMENT N-1 SUNDANM9-SAGITAW4 240kV #89 OPEN LINE "SUNDANM9 240.00" "SAGITAW4 240.00" "89" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 47 COMMENT N-1 SUNDANM9-DOME T29 240kV OPEN LINE "SUNDANM9 240.00" "DOME T29 240.00" "09" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 48 COMMENT N-1 SUNDANM9-PETROLIA 240kV OPEN LINE "SUNDANM9 240.00" "PETROLIA 240.00" "08" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 49 COMMENT N-1 E EDMON4-CLOVERB4 240kV OPEN LINE "E EDMON4 240.00" "CLOVERB4 240.00" "15" 0 DELETE ISLANDS DONE Page 653 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 50 COMMENT N-1 E EDMON4-946/947N 240kV OPEN LINE "E EDMON4 240.00" "946/947N 240.00" "46" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 51 COMMENT N-1 E EDMON4-904AL TP 240kV OPEN LINE "E EDMON4 240.00" "904AL TP 240.00" "04" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 52 COMMENT N-1 N CALDE4-JASPER 4 240kV OPEN LINE "N CALDE4 240.00" "JASPER 4 240.00" "30" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 53 COMMENT N-1 N CALDE4-CASTLTX2 240kV OPEN LINE "N CALDE4 240.00" "CASTLTX2 240.00" "20" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 54 COMMENT N-1 GAETZ 4-RED DEE4 240kV OPEN LINE "GAETZ 4 240.00" "RED DEE4 240.00" "14" 0 DELETE ISLANDS DONE Page 654 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 55 COMMENT N-1 WILLESD9-BRAZEAU4 240kV OPEN LINE "WILLESD9 240.00" "BRAZEAU4 240.00" "95" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 56 COMMENT N-1 WILLESD9-BENALTO4 240kV OPEN LINE "WILLESD9 240.00" "BENALTO4 240.00" "95" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 57 COMMENT N-1 RED DEE4-BENALTO4 240kV OPEN LINE "RED DEE4 240.00" "BENALTO4 240.00" "00" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 58 COMMENT N-1 RED DEE4-JANET 4 240kV OPEN LINE "RED DEE4 240.00" "JANET 4 240.00" "25" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 59 COMMENT N-1 RED DEE4-JANET 4 240kV OPEN LINE "RED DEE4 240.00" "JANET 4 240.00" "29" 0 DELETE ISLANDS DONE Page 655 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 60 COMMENT N-1 RED DEE4-CROSSF T 240kV OPEN LINE "RED DEE4 240.00" "CROSSF T 240.00" "01" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 61 COMMENT N-1 RED DEE4-NEVIS 4 240kV OPEN LINE "RED DEE4 240.00" "NEVIS 4 240.00" "12" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 62 COMMENT N-1 BENALTO4-SARCEE 4 240kV OPEN LINE "BENALTO4 240.00" "SARCEE 4 240.00" "06" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 63 COMMENT N-1 BENALTO4-SARCEE 4 240kV OPEN LINE "BENALTO4 240.00" "SARCEE 4 240.00" "28" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 64 COMMENT N-1 BENALTO4-BEDDING1 240kV OPEN LINE "BENALTO4 240.00" "BEDDING1 240.00" "18" 0 DELETE ISLANDS DONE Page 656 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 65 COMMENT N-1 BENALTO4-KEEPHIL4 240kV #03 OPEN LINE "BENALTO4 240.00" "KEEPHIL4 240.00" "03" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 66 COMMENT N-1 BENALTO4-KEEPHIL4 240kV #90 OPEN LINE "BENALTO4 240.00" "KEEPHIL4 240.00" "90" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 67 COMMENT N-1 E CROSS4-CROSSF T 240kV OPEN LINE "E CROSS4 240.00" "CROSSF T 240.00" "01" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 68 COMMENT N-1 JANET 4-E CALGAR 240kV OPEN LINE "JANET 4 240.00" "E CALGAR 240.00" "17" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 69 COMMENT N-1 JANET 4-PEIGAN 4 240kV OPEN LINE "JANET 4 240.00" "PEIGAN 4 240.00" "11" 0 DELETE ISLANDS DONE Page 657 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 70 COMMENT N-1 JANET 4-BEDDING1 240kV OPEN LINE "JANET 4 240.00" "BEDDING1 240.00" "32" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 71 COMMENT N-1 JANET 4-CROSSF T 240kV OPEN LINE "JANET 4 240.00" "CROSSF T 240.00" "01" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 72 COMMENT N-1 SARCEE 4-E CALGAR 240kV OPEN LINE "SARCEE 4 240.00" "E CALGAR 240.00" "16" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 73 COMMENT N-1 PEIGAN 4-N LETHB4 240kV OPEN LINE "PEIGAN 4 240.00" "N LETHB4 240.00" "77" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 74 COMMENT N-1 PEIGAN 4-N LETHB4 240kV OPEN LINE "PEIGAN 4 240.00" "N LETHB4 240.00" "78" 0 DELETE ISLANDS DONE Page 658 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 75 COMMENT N-1 PEIGAN 4-PINCHER4 240kV OPEN LINE "PEIGAN 4 240.00" "PINCHER4 240.00" "75" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 76 COMMENT N-1 PEIGAN 4-PINCHER4 240kV OPEN LINE "PEIGAN 4 240.00" "PINCHER4 240.00" "76" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 77 COMMENT N-1 PEIGAN 4-GOOSEL4 240kV OPEN LINE "PEIGAN 4 240.00" "GOOSEL4 240.00" "75" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 78 COMMENT N-1 PEIGAN 4-GOOSEL4 240kV OPEN LINE "PEIGAN 4 240.00" "GOOSEL4 240.00" "76" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 79 COMMENT N-1 N LETHB4-MATL_AB 240kV OPEN LINE "N LETHB4 240.00" "MATL_AB 240.00" "23" 0 DELETE ISLANDS DONE Page 659 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 80 COMMENT N-1 N LETHB4-MILO 2-LANGDON9-W BROOK4 240kV OPEN LINE "N LETHB4 240.00" "MILO 2 240.00" "23" 0 OPEN LINE "LANGDON9 240.00" "MILO 2 240.00" "27" 0 OPEN LINE "W BROOK4 240.00" "MILO 2 240.00" "23" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 81 COMMENT N-1 MATL_AB-MILO 2-LANGDON9-W BROOK4 240kV OPEN LINE "MATL_AB 240.00" "MILO 2 240.00" "23" 0 OPEN LINE "LANGDON9 240.00" "MILO 2 240.00" "27" 0 OPEN LINE "W BROOK4 240.00" "MILO 2 240.00" "23" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 82 COMMENT N-1 N LETHB4-MILO 1-LANGDON9-W BROOK4 240kV OPEN LINE "N LETHB4 240.00" "MILO 1 240.00" "24" 0 OPEN LINE "LANGDON9 240.00" "MILO 1 240.00" "24" 0 OPEN LINE "W BROOK4 240.00" "MILO 1 240.00" "35" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 83 COMMENT N-1 LANGDON9-JANET 4 240kV OPEN LINE "LANGDON9 240.00" "JANET 4 240.00" "36" 0 DELETE ISLANDS DONE Page 660 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 84 COMMENT N-1 PINCHER4-WATWND 240kV OPEN LINE "PINCHER4 240.00" "WATWND 240.00" "W1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 85 COMMENT T-1 KEEPHILS 500/240kV OPEN XFMR "KEEPHIL4 240.00" "KEEPHILS 500.00" "T6" DELETE ISLANDS DONE **** CASE NUMBER **** 86 COMMENT N-1 BELLAMY4-ARGYLL W 240kV OPEN LINE "BELLAMY4 240.00" "ARGYLL W 240.00" "04" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 87 COMMENT N-1 BELLAMY4-ARGYLL E 240kV OPEN LINE "BELLAMY4 240.00" "ARGYLL E 240.00" "04" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 88 COMMENT N-1 ARGYLL W-PETROLIA 240kV OPEN LINE "ARGYLL W 240.00" "PETROLIA 240.00" "04" 0 DELETE ISLANDS DONE Page 661 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 89 COMMENT N-1 EAST IN4-904AL TP 240kV OPEN LINE "EAST IN4 240.00" "904AL TP 240.00" "04" 0 OPEN XFMR "EAST IN4 240.00" "EASTINT1 25.00" "1 " 0 DROP LOAD "EASTINT1 25.00" "9 " DELETE ISLANDS DONE **** CASE NUMBER **** 90 COMMENT N-1 PAINTRT4-CORDEL 4 240kV OPEN LINE "PAINTRT4 240.00" "CORDEL 4 240.00" "27" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 91 COMMENT N-1 PAINTRT4-HANSMAN7 240kV OPEN LINE "PAINTRT4 240.00" "HANSMAN7 240.00" "48" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 92 COMMENT N-1 NEVIS 4-CORDEL 4 240kV OPEN LINE "NEVIS 4 240.00" "CORDEL 4 240.00" "20" 0 DELETE ISLANDS DONE Page 662 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 93 COMMENT N-1 BAT RV79-CORDEL 4 240kV DROP GENERATION "BAT #5 21.00" "5 " DROP LOAD "BAT #5 21.00" "SS" OPEN XFMR "BAT RV79 240.00" "BAT #5 21.00" "1" 0 OPEN LINE "BAT RV79 240.00" "CORDEL 4 240.00" "79" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 94 COMMENT N-1 CORDEL 4-HANSMAN7 240kV OPEN LINE "CORDEL 4 240.00" "HANSMAN7 240.00" "53" 0 DELETE ISLANDS DONE # All 138 and 69 kV lines in Alberta south of a Calgary- Sheerness cut plane. **** CASE NUMBER **** 95 COMMENT N-1 BANFF 7-W.CASC T 138kV OPEN LINE "BANFF 7 138.00" "W.CASC T 138.00" "54" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 96 COMMENT N-1 CAN CEM9-742L JCT 138kV OPEN LINE "CAN CEM9 138.00" "742L JCT 138.00" "42" 0 DELETE ISLANDS DONE Page 663 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 97 COMMENT N-1 COCHRAN9-BEARSPAW 138kV OPEN LINE "COCHRAN9 138.00" "BEARSPAW 138.00" "60" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 98 COMMENT N-1 COCHRAN9-ANG COCH 138kV OPEN LINE "COCHRAN9 138.00" "ANG COCH 138.00" "60" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 99 COMMENT N-1 SEEBE 9-GHOST 9 138kV OPEN LINE "SEEBE 9 138.00" "GHOST 9 138.00" "56" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 100 COMMENT N-1 SEEBE 9-KANANAS7 138kV OPEN LINE "SEEBE 9 138.00" "KANANAS7 138.00" "87" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 101 COMMENT N-1 SEEBE 9-BARRIER7 138kV OPEN LINE "SEEBE 9 138.00" "BARRIER7 138.00" "58" 0 DELETE ISLANDS DONE Page 664 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 102 COMMENT N-1 SEEBE 9-POCATER7 138kV OPEN LINE "SEEBE 9 138.00" "POCATER7 138.00" "77" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 103 COMMENT N-1 SEEBE 9-JUMP TP2 138kV OPEN LINE "SEEBE 9 138.00" "JUMP TP2 138.00" "3" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 104 COMMENT N-1 SEEBE 9-742L JCT 138kV OPEN LINE "SEEBE 9 138.00" "742L JCT 138.00" "54" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 105 COMMENT N-1 CASCADE7-W.CASC T 138kV OPEN LINE "CASCADE7 138.00" "W.CASC T 138.00" "54" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 106 COMMENT N-1 GHOST 9-ANG COCH 138kV OPEN LINE "GHOST 9 138.00" "ANG COCH 138.00" "59" 0 DELETE ISLANDS DONE Page 665 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 107 COMMENT N-1 GHOST 9-SPRAY S 138kV OPEN LINE "GHOST 9 138.00" "SPRAY S 138.00" "13" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 108 COMMENT N-1 GHOST 9-JUMP TP1 138kV OPEN LINE "GHOST 9 138.00" "JUMP TP1 138.00" "50" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 109 COMMENT N-1 GHOST 9-MADDEN T 138kV OPEN LINE "GHOST 9 138.00" "MADDEN T 138.00" "80" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 110 COMMENT N-1 BEARSPAW-ENMX21S7 138kV OPEN LINE "BEARSPAW 138.00" "ENMX21S7 138.00" "50" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 111 COMMENT N-1 BEARSPAW-ENMX36S7 138kV OPEN LINE "BEARSPAW 138.00" "ENMX36S7 138.00" "81" 0 DELETE ISLANDS DONE Page 666 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 112 COMMENT N-1 RUNDLE S-SPRAY S 138kV OPEN LINE "RUNDLE S 138.00" "SPRAY S 138.00" "84" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 113 COMMENT N-1 RUNDLE S-54L JNC 138kV OPEN LINE "RUNDLE S 138.00" "54L JNC 138.00" "85" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 114 COMMENT N-1 SHELL J9-JUMP TP1 138kV OPEN LINE "SHELL J9 138.00" "JUMP TP1 138.00" "50" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 115 COMMENT N-1 JUMPPND9-JUMP TP2 138kV OPEN LINE "JUMPPND9 138.00" "JUMP TP2 138.00" "3" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 116 COMMENT N-1 MOUNT A7-BARRIER7 138kV OPEN LINE "MOUNT A7 138.00" "BARRIER7 138.00" "90" 0 DELETE ISLANDS DONE Page 667 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 117 COMMENT N-1 MOUNT A7-SPRAY S 138kV OPEN LINE "MOUNT A7 138.00" "SPRAY S 138.00" "76" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 118 COMMENT N-1 SHEPARD9-CARSLAND 138kV OPEN LINE "SHEPARD9 138.00" "CARSLAND 138.00" "50" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 119 COMMENT N-1 BLACK D9-HART TAP 138kV OPEN LINE "BLACK D9 138.00" "HART TAP 138.00" "12" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 120 COMMENT N-1 OKOTOKS9-MAG TAP7 138kV OPEN LINE "OKOTOKS9 138.00" "MAG TAP7 138.00" "27" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 121 COMMENT N-1 MAGCAN 7-MAG TAP7 138kV OPEN LINE "MAGCAN 7 138.00" "MAG TAP7 138.00" "27" 0 DELETE ISLANDS DONE Page 668 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 122 COMMENT N-1 HIGH RI9-BLACKIE7 138kV OPEN LINE "HIGH RI9 138.00" "BLACKIE7 138.00" "53" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 123 COMMENT N-1 HIGH RI9-MAG TAP7 138kV OPEN LINE "HIGH RI9 138.00" "MAG TAP7 138.00" "27" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 124 COMMENT N-1 HIGH RI9-HART TAP 138kV OPEN LINE "HIGH RI9 138.00" "HART TAP 138.00" "12" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 125 COMMENT N-1 HARTELL9-HART TAP 138kV OPEN LINE "HARTELL9 138.00" "HART TAP 138.00" "12" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 126 COMMENT N-1 CAVALIER-NAMAKA 7 138kV OPEN LINE "CAVALIER 138.00" "NAMAKA 7 138.00" "01" 0 DELETE ISLANDS DONE Page 669 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 127 COMMENT N-1 DUCHESS9-831A TAP 138kV OPEN LINE "DUCHESS9 138.00" "831A TAP 138.00" "31" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 128 COMMENT N-1 CARSLAND-BLACKIE7 138kV OPEN LINE "CARSLAND 138.00" "BLACKIE7 138.00" "51" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 129 COMMENT N-1 CARSLAND-WYNDHAM 138kV OPEN LINE "CARSLAND 138.00" "WYNDHAM 138.00" "82" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 130 COMMENT N-1 BLACKIE7-QUENSTWN 138kV OPEN LINE "BLACKIE7 138.00" "QUENSTWN 138.00" "52" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 131 COMMENT N-1 GLEICHE9-QUENSTWN 138kV OPEN LINE "GLEICHE9 138.00" "QUENSTWN 138.00" "76" 0 DELETE ISLANDS DONE Page 670 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 132 COMMENT N-1 GLEICHE9-NAMAKA 7 138kV OPEN LINE "GLEICHE9 138.00" "NAMAKA 7 138.00" "33" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 133 COMMENT N-1 BROOKSA9-TILLEY 9 138kV OPEN LINE "BROOKSA9 138.00" "TILLEY 9 138.00" "00" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 134 COMMENT N-1 BROOKSA9-W BROOK9 138kV OPEN LINE "BROOKSA9 138.00" "W BROOK9 138.00" "14" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 135 COMMENT N-1 BROOKSA9-W BROOK9 138kV OPEN LINE "BROOKSA9 138.00" "W BROOK9 138.00" "27" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 136 COMMENT N-1 BROOKSA9-HAYS 7 138kV OPEN LINE "BROOKSA9 138.00" "HAYS 7 138.00" "95" 0 DELETE ISLANDS DONE Page 671 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 137 COMMENT N-1 BROOKSA9-831A TAP 138kV OPEN LINE "BROOKSA9 138.00" "831A TAP 138.00" "31" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 138 COMMENT N-1 STRATHM9-NAMAKA 7 138kV OPEN LINE "STRATHM9 138.00" "NAMAKA 7 138.00" "33" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 139 COMMENT N-1 W BROOK9-ENCH TAP 138kV OPEN LINE "W BROOK9 138.00" "ENCH TAP 138.00" "63" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 140 COMMENT N-1 W BROOK9-BASNTAP 138kV OPEN LINE "W BROOK9 138.00" "BASNTAP 138.00" "53" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 141 COMMENT N-1 CANMORE9-BAYMAGB 138kV OPEN LINE "CANMORE9 138.00" "BAYMAGB 138.00" "54" 0 DELETE ISLANDS DONE Page 672 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 142 COMMENT N-1 CANMORE9-54L JNC 138kV OPEN LINE "CANMORE9 138.00" "54L JNC 138.00" "54" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 143 COMMENT N-1 BAYMAGB-742L JCT 138kV OPEN LINE "BAYMAGB 138.00" "742L JCT 138.00" "54" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 144 COMMENT N-1 HUSSAR 8-NAMAKA 7 138kV OPEN LINE "HUSSAR 8 138.00" "NAMAKA 7 138.00" "86" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 145 COMMENT N-1 POCATER7-FRO T274 138kV OPEN LINE "POCATER7 138.00" "FRO T274 138.00" "1" 0 DELETE ISLANDS DONE #**** CASE NUMBER **** ??? #COMMENT #N-1 POCATER7-BRITT TP 138kV #OPEN LINE #"POCATER7 138.00" "BRITT TP 138.00" "87" 0 #DELETE ISLANDS #DONE Page 673 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 146 COMMENT N-1 QUENSTWN-BASNTAP 138kV OPEN LINE "QUENSTWN 138.00" "BASNTAP 138.00" "53" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 147 COMMENT N-1 BASSAN9-BASNTAP 138kV OPEN LINE "BASSAN9 138.00" "BASNTAP 138.00" "53" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 148 COMMENT N-1 SPRINGB9-JUMP TP2 138kV OPEN LINE "SPRINGB9 138.00" "JUMP TP2 138.00" "3" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 149 COMMENT N-1 CUTNG L9-831A TAP 138kV OPEN LINE "CUTNG L9 138.00" "831A TAP 138.00" "31" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 150 COMMENT N-1 W.CASC T-54L JNC 138kV OPEN LINE "W.CASC T 138.00" "54L JNC 138.00" "54" 0 DELETE ISLANDS DONE Page 674 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 151 COMMENT N-1 SANDYPT9-DOME EM7 138kV OPEN LINE "SANDYPT9 138.00" "DOME EM7 138.00" "69" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 152 COMMENT N-1 SANDHIL7-DOME EM7 138kV OPEN LINE "SANDHIL7 138.00" "DOME EM7 138.00" "71" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 153 COMMENT N-1 STAVELY9-STAVELEY 138kV OPEN LINE "STAVELY9 138.00" "STAVELEY 138.00" "97" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 154 COMMENT N-1 VULCAN 9-BLACKIE7 138kV OPEN LINE "VULCAN 9 138.00" "BLACKIE7 138.00" "61" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 155 COMMENT N-1 VULCAN 9-STAVELEY 138kV OPEN LINE "VULCAN 9 138.00" "STAVELEY 138.00" "80" 0 DELETE ISLANDS DONE Page 675 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 156 COMMENT N-1 EMP LIQ7-EMPLIQTP 138kV OPEN LINE "EMP LIQ7 138.00" "EMPLIQTP 138.00" "60" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 157 COMMENT N-1 PANCAN 9-DOME EM7 138kV OPEN LINE "PANCAN 9 138.00" "DOME EM7 138.00" "60" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 158 COMMENT N-1 PANCAN 9-CHAPPIC9 138kV OPEN LINE "PANCAN 9 138.00" "CHAPPIC9 138.00" "60" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 159 COMMENT N-1 DOME EM7-EMPLIQTP 138kV OPEN LINE "DOME EM7 138.00" "EMPLIQTP 138.00" "60" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 160 COMMENT N-1 DOME EM7-MCNEILL 138kV OPEN LINE "DOME EM7 138.00" "MCNEILL 138.00" "30" 0 DELETE ISLANDS DONE Page 676 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 161 COMMENT N-1 WARLOW9-JENNER7 138kV OPEN LINE "WARLOW9 138.00" "JENNER7 138.00" "52" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 162 COMMENT N-1 EMPLIQTP-OYEN 7 138kV OPEN LINE "EMPLIQTP 138.00" "OYEN 7 138.00" "60" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 163 COMMENT N-1 SUNSHIN8-BANFF 8 69kV OPEN LINE "SUNSHIN8 69.00" "BANFF 8 69.00" "51" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 164 COMMENT N-1 SUNSHIN8-LAKE LO9 69kV OPEN LINE "SUNSHIN8 69.00" "LAKE LO9 69.00" "51" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 165 COMMENT N-1 HIGH RI8-BLACK D8 69kV DROP LOAD "BLACK D8 69.00" "9" OPEN LINE "HIGH RI8 69.00" "BLACK D8 69.00" "13" 0 DELETE ISLANDS DONE Page 677 of 722 APPENDIX I – SWITCHING SEQUENCES # Remaining contingencies **** CASE NUMBER **** 166 COMMENT N-1 ING500-CUSTER W 500kV W/RAS OPEN LINE "ING500 500.00" "CUSTER W 500.00" "1 " 0 DROP GENERATION "GMS G2 13.8" "1 " DELETE ISLANDS DONE **** CASE NUMBER **** 167 COMMENT N-1 CUSTER W-MONROE 500kV OPEN LINE "CUSTER W 500.00" "CUSTER&1 500.00" "1 " 0 OPEN LINE "CUSTER&1 500.00" "MONROE 500.00" "1 " 0 DELETE ISLANDS DONE **** CASE NUMBER **** 168 COMMENT N-1 LANGDON9-JANET 2400kV OPEN LINE "LANGDON9 240.00" "JANET 4 240.00" "36 " 0 DELETE ISLANDS DONE STOP Page 678 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 1 Southern Alberta Wind Sensitivity Pflopro Input File Page 679 of 722 APPENDIX I – SWITCHING SEQUENCES GLOBAL COMMANDS BASE CASE LIST 07hs_pst_iv2-1b-1_v1b1_rev03tcl.sav SS "WIND=0, MATL=SOUTH, PATH1=803" #07hs_pst_iv2-1b-2_v1b2_rev03tcl.sav SS "WIND=700, MATL=SOUTH, PATH1=800" #07hs_pst_iv2-1c-1_v1b3_rev03tcl.sav SS "WIND=0, MATL=NORTH, PATH1=800" #07hs_pst_iv2-1c-2_v1b4_rev03tcl.sav SS "WIND=700, MATL=NORTH, PATH1=800" # #07hs_ns_pst_n2s-1_v1b5_rev23ntcl.sav SS "WIND=0, MATL=SOUTH, PATH1=-780" #07hs_ns_pst_n2s-2_v1b6_rev23ntcl.sav SS "WIND=700, MATL=NORTH, PATH1=-773" #07hs_ns_pst_s2n-1_v1b7_rev24ntcl.sav SS "WIND=0, MATL=SOUTH, PATH1=-783" #07hs_ns_pst_s2n-2_v1b8_rev24ntcl.sav SS "WIND=700, MATL=NORTH, PATH1=-780" DONE OUTPUT FILE PATH C:\PSLF16_Work\MATL_Path-1_Sens\Pflopro_Analysis GET CASE PATH C:\PSLF16_Work\MATL_Path-1_Sens\Pflopro_Analysis SAVE CASE PATH C:\PSLF16_Work\MATL_Path-1_Sens\Pflopro_Analysis IN-RUN EPCL PATH C:\PSLF16_Work\MATL_Path-1_Sens\Pflopro_Analysis BASE CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 1 TCUL TAP RATIO ADJUSTMENT 1 AUTOMATIC SVD ADJUSTMENT 1 PHASE SHIFTER ADJUSTMENT 1 AREA INTERCHANGE CONTROL 1 DONE CONTINGENCY CASE SOLUTION PARAMETERS Page 680 of 722 APPENDIX I – SWITCHING SEQUENCES MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 9 TCUL TAP RATIO ADJUSTMENT 0 AUTOMATIC SVD ADJUSTMENT 0 PHASE SHIFTER ADJUSTMENT 0 AREA INTERCHANGE CONTROL 0 SOLUTION TOLERANCE 50.0 DONE MONITOR AREA OR ZONE VIOLATIONS AREA 40 AREA 50 AREA 52 AREA 54 AREA 60 AREA 62 AREA 63 DONE # MONITOR BRANCH # "NTL138 138.00" "LCCTAP 138.00" "1" # "NTL138 138.00" "COLEMAN7 138.00" "1" # "MATL_AB 240.00" "MATL_AB 230.00" "1" # DONE LOCAL COMMANDS **** CASE NUMBER **** 0 COMMENT N-0 BASE CASE DONE # PROJECT CONTINGENCIES **** CASE NUMBER **** 1 COMMENT T-1 MATL_AB 240/230KV TRANSFORMER BANK OPEN XFMR "MATL_AB 240.00" "MATL_AB 230.00" "1" OPEN LINE "MATL_AB 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&2 230.00" "1" 1 Page 681 of 722 APPENDIX I – SWITCHING SEQUENCES OPEN LINE "GT FALLS 230.00" "MATLN_&2 230.00" "1" 1 DELETE ISLANDS DONE # All 230 and 500 kV lines in Montana **** CASE NUMBER **** 2 COMMENT N-1 MILL CRK-GARRISON 230kV OPEN LINE "MILL CRK 230.00" "GARRISON 230.00" "1 " 1 DELETE ISLANDS DONE **** CASE NUMBER **** 3 COMMENT N-1 MILL CRK-PTRSNFLT-AMPS-ANTLOPP 230kV OPEN LINE "MILL CRK 230.00" "PTRSNFLT 230.00" "1 " 1 OPEN LINE "PTRSNFLT 230.00" "AMPS 230.00" "1 " 1 OPEN LINE "AMPS 230.00" "ANTLOPP 230.00" "1 " 1 OPEN XFMR "AMPS 230.00" "AMPS 69.00" "1 " 1 DELETE ISLANDS DONE **** CASE NUMBER **** 4 COMMENT N-1 MILL CRK-THRRIVER 230kV OPEN LINE "MILL CRK 230.00" "THRRIVER 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 5 COMMENT N-1 MILL CRK-ANA BPA 230kV OPEN LINE "MILL CRK 230.00" "ANA BPA 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 6 Page 682 of 722 APPENDIX I – SWITCHING SEQUENCES COMMENT N-1 WILSALL-SHOREYRD 230kV OPEN LINE "WILSALL 230.00" "SHOREYRD 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 7 COMMENT N-1 WILSALL-THRRIVER 230kV OPEN LINE "WILSALL 230.00" "THRRIVER 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 8 COMMENT N-1 SHELBY-CNRDWAPA 230kV OPEN LINE "SHELBY 230.00" "CNRDWAPA 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 9 COMMENT N-1 BOLE-CNRDWAPA 230kV OPEN LINE "BOLE 230.00" "CNRDWAPA 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 10 COMMENT N-1 BOLE-GT FALLS 230kV OPEN LINE "BOLE 230.00" "GT FALLS 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 11 COMMENT N-1 JUDITHGP-GT FALLS 230kV OPEN LINE "JUDITHGP 230.00" "GT FALLS 230.00" "1" 1 OPEN LINE "JUDITHGP 230.00" "JUDITHSO 230.00" "1" 1 Page 683 of 722 APPENDIX I – SWITCHING SEQUENCES OPEN XFMR "JUDITHGP 230.00" "JUDITHGP 100.00" "1" 1 DELETE ISLANDS DONE #**** CASE NUMBER **** 12 #COMMENT #N-1 JUDITHGP-SOUTHERN 230kV #OPEN LINE #"JUDITHGP 230.00" "SOUTHERN 230.00" "1" 1 #OPEN LINE #"JUDITHGP 230.00" "JUDITHSO 230.00" "1" 1 #OPEN XFMR #"JUDITHGP 230.00" "JUDITHGP 100.00" "1" 1 #DELETE ISLANDS #DONE **** CASE NUMBER **** 12 COMMENT N-1 BROADVU-JUDITHSO 230kV OPEN LINE "BROADVU 230.00" "JUDITHSO 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 13 COMMENT N-1 BLGS PHA-YELOWTLP 230kV OPEN LINE "BLGS PHA 230.00" "YELOWTLP 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 14 COMMENT N-1 HARDIN-COLSTRP 230kV OPEN LINE "HARDIN 230.00" "COLSTRP 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 15 COMMENT N-1 HARDIN-CRSOVRUM 230kV OPEN LINE "HARDIN 230.00" "CRSOVRUM 230.00" "1" 1 Page 684 of 722 APPENDIX I – SWITCHING SEQUENCES DELETE ISLANDS DONE **** CASE NUMBER **** 16 COMMENT N-1 ALKALI-SHOREYRD 230kV OPEN LINE "ALKALI 230.00" "SHOREYRD 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 17 COMMENT N-1 ALKALI-BILINGS 230kV OPEN LINE "ALKALI 230.00" "BILINGS 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 18 COMMENT N-1 ALKALI-BROADVU 230kV OPEN LINE "ALKALI 230.00" "BROADVU 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 19 COMMENT N-1 BASELINE-SHOREYRD 230kV OPEN LINE "BASELINE 230.00" "SHOREYRD 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 20 COMMENT N-1 HUNTLEY-BILINGS 230kV OPEN LINE "HUNTLEY 230.00" "BILINGS 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 21 COMMENT N-1 HUNTLEY-RSOVRUM 230kV Page 685 of 722 APPENDIX I – SWITCHING SEQUENCES OPEN LINE "HUNTLEY 230.00" "CRSOVRUM 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 22 COMMENT N-1 GT FALLS-LANDRSFK-OVANDO 230kV OPEN LINE "GT FALLS 230.00" "LANDRSFK 230.00" "1" 1 OPEN LINE "OVANDO 230.00" "LANDRSFK 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 23 COMMENT N-1 OVANDO-GARRISON 230kV OPEN LINE "OVANDO 230.00" "GARRISON 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 24 COMMENT N-1 OVANDO-HOT SPR 230kV OPEN LINE "OVANDO 230.00" "HOT SPR 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 25 COMMENT N-1 BILINGS-BILINGSW 230kV OPEN LINE "BILINGS 230.00" "BILINGSW 230.00" "1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 26 COMMENT N-1 BILINGSW-BROADVU 230kV OPEN LINE "BILINGSW 230.00" "BROADVU 230.00" "1" 1 DELETE ISLANDS Page 686 of 722 APPENDIX I – SWITCHING SEQUENCES DONE **** CASE NUMBER **** 27 COMMENT N-1 ANA BPA-GARRISON 230kV OPEN LINE "ANA BPA 230.00" "GARRISON 230.00" "1" 1 DELETE ISLANDS DONE # All 240 and 500 kV lines in Alberta south of a KEG cut plane. **** CASE NUMBER **** 28 COMMENT N-1 ELLERSLI-GENESEE4 500kV OPEN LINE "ELLERSLI 500.00" "GENESEE4 500.00" "09" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 29 COMMENT N-1 GENESEE4-KEEPHILS 500kV OPEN LINE "GENESEE4 500.00" "KEEPHILS 500.00" "03" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 30 COMMENT N-1 ELLERSLI-E EDMON4 240kV OPEN LINE "ELLERSLI 240.00" "E EDMON4 240.00" "08" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 31 COMMENT N-1 ELLERSLI-RED DEE4 240kV OPEN LINE "ELLERSLI 240.00" "RED DEE4 240.00" "10" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 32 COMMENT Page 687 of 722 APPENDIX I – SWITCHING SEQUENCES N-1 ELLERSLI-KEEPHIL4 240kV OPEN LINE "ELLERSLI 240.00" "KEEPHIL4 240.00" "02" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 33 COMMENT N-1 ELLERSLI-DOME T29 240kV OPEN LINE "ELLERSLI 240.00" "DOME T29 240.00" "09" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 34 COMMENT N-1 ELLERSLI-LAMBTON4 240kV OPEN LINE "ELLERSLI 240.00" "LAMBTON4 240.00" "04" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 35 COMMENT N-1 ELLERSLI-ARGYLL E 240kV OPEN LINE "ELLERSLI 240.00" "ARGYLL E 240.00" "04" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 36 COMMENT N-1 ELLERSLI-PETROLIA 240kV OPEN LINE "ELLERSLI 240.00" "PETROLIA 240.00" "08" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 37 COMMENT N-1 ELLERSLI-946/947X 240kV OPEN LINE "ELLERSLI 240.00" "946/947X 240.00" "47" 1 DELETE ISLANDS DONE Page 688 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 38 COMMENT N-1 WABAMUN4-SUNDANM9 240kV OPEN LINE "WABAMUN4 240.00" "SUNDANM9 240.00" "02" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 39 COMMENT N-1 WABAMUN4-N CALDE4 240kV OPEN LINE "WABAMUN4 240.00" "N CALDE4 240.00" "05" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 40 COMMENT N-1 WABAMUN4-JASPER 4 240kV OPEN LINE "WABAMUN4 240.00" "JASPER 4 240.00" "04" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 41 COMMENT N-1 SUNDANM9-N BARRH4 240kV OPEN LINE "SUNDANM9 240.00" "N BARRH4 240.00" "13" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 42 COMMENT N-1 SUNDANM9-BENALTO4 240kV OPEN LINE "SUNDANM9 240.00" "BENALTO4 240.00" "22" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 43 COMMENT N-1 SUNDANM9-BENALTO4 240kV OPEN LINE "SUNDANM9 240.00" "BENALTO4 240.00" "26" 1 Page 689 of 722 APPENDIX I – SWITCHING SEQUENCES DELETE ISLANDS DONE **** CASE NUMBER **** 44 COMMENT N-1 SUNDANM9-SAGITAW4 240kV #19 OPEN LINE "SUNDANM9 240.00" "SAGITAW4 240.00" "19" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 45 COMMENT N-1 SUNDANM9-SAGITAW4 240kV #89 OPEN LINE "SUNDANM9 240.00" "SAGITAW4 240.00" "89" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 46 COMMENT N-1 SUNDANM9-DOME T29 240kV OPEN LINE "SUNDANM9 240.00" "DOME T29 240.00" "09" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 47 COMMENT N-1 SUNDANM9-PETROLIA 240kV OPEN LINE "SUNDANM9 240.00" "PETROLIA 240.00" "08" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 48 COMMENT N-1 E EDMON4-CLOVERB4 240kV OPEN LINE "E EDMON4 240.00" "CLOVERB4 240.00" "15" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 49 COMMENT Page 690 of 722 APPENDIX I – SWITCHING SEQUENCES N-1 E EDMON4-946/947N 240kV OPEN LINE "E EDMON4 240.00" "946/947N 240.00" "46" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 50 COMMENT N-1 E EDMON4-904AL TP 240kV OPEN LINE "E EDMON4 240.00" "904AL TP 240.00" "04" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 51 COMMENT N-1 N CALDE4-JASPER 4 240kV OPEN LINE "N CALDE4 240.00" "JASPER 4 240.00" "30" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 52 COMMENT N-1 N CALDE4-CASTLTX2 240kV OPEN LINE "N CALDE4 240.00" "CASTLTX2 240.00" "20" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 53 COMMENT N-1 GAETZ 4-RED DEE4 240kV OPEN LINE "GAETZ 4 240.00" "RED DEE4 240.00" "14" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 54 COMMENT N-1 WILLESD9-BRAZEAU4 240kV OPEN LINE "WILLESD9 240.00" "BRAZEAU4 240.00" "95" 1 DELETE ISLANDS DONE Page 691 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 55 COMMENT N-1 WILLESD9-BENALTO4 240kV OPEN LINE "WILLESD9 240.00" "BENALTO4 240.00" "95" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 56 COMMENT N-1 RED DEE4-BENALTO4 240kV OPEN LINE "RED DEE4 240.00" "BENALTO4 240.00" "00" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 57 COMMENT N-1 RED DEE4-JANET 4 240kV OPEN LINE "RED DEE4 240.00" "JANET 4 240.00" "25" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 58 COMMENT N-1 RED DEE4-JANET 4 240kV OPEN LINE "RED DEE4 240.00" "JANET 4 240.00" "29" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 59 COMMENT N-1 RED DEE4-CROSSF T 240kV OPEN LINE "RED DEE4 240.00" "CROSSF T 240.00" "01" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 60 COMMENT N-1 RED DEE4-NEVIS 4 240kV OPEN LINE "RED DEE4 240.00" "NEVIS 4 240.00" "12" 1 DELETE ISLANDS Page 692 of 722 APPENDIX I – SWITCHING SEQUENCES DONE **** CASE NUMBER **** 61 COMMENT N-1 BENALTO4-SARCEE 4 240kV OPEN LINE "BENALTO4 240.00" "SARCEE 4 240.00" "06" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 62 COMMENT N-1 BENALTO4-SARCEE 4 240kV OPEN LINE "BENALTO4 240.00" "SARCEE 4 240.00" "28" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 63 COMMENT N-1 BENALTO4-BEDDING1 240kV OPEN LINE "BENALTO4 240.00" "BEDDING1 240.00" "18" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 64 COMMENT N-1 BENALTO4-KEEPHIL4 240kV #03 OPEN LINE "BENALTO4 240.00" "KEEPHIL4 240.00" "03" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 65 COMMENT N-1 BENALTO4-KEEPHIL4 240kV #90 OPEN LINE "BENALTO4 240.00" "KEEPHIL4 240.00" "90" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 66 COMMENT N-1 E CROSS4-CROSSF T 240kV OPEN LINE Page 693 of 722 APPENDIX I – SWITCHING SEQUENCES "E CROSS4 240.00" "CROSSF T 240.00" "01" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 67 COMMENT N-1 JANET 4-E CALGAR 240kV OPEN LINE "JANET 4 240.00" "E CALGAR 240.00" "17" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 68 COMMENT N-1 JANET 4-PEIGAN 4 240kV OPEN LINE "JANET 4 240.00" "PEIGAN 4 240.00" "11" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 69 COMMENT N-1 JANET 4-BEDDING1 240kV OPEN LINE "JANET 4 240.00" "BEDDING1 240.00" "32" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 70 COMMENT N-1 JANET 4-CROSSF T 240kV OPEN LINE "JANET 4 240.00" "CROSSF T 240.00" "01" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 71 COMMENT N-1 SARCEE 4-E CALGAR 240kV OPEN LINE "SARCEE 4 240.00" "E CALGAR 240.00" "16" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 72 COMMENT Page 694 of 722 APPENDIX I – SWITCHING SEQUENCES N-1 PEIGAN 4-PINCHER4 240kV OPEN LINE "PEIGAN 4 240.00" "PINCHER4 240.00" "75" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 73 COMMENT N-1 PEIGAN 4-PINCHER4 240kV OPEN LINE "PEIGAN 4 240.00" "PINCHER4 240.00" "76" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 77 COMMENT N-1 PEIGAN 4-GOOSEL4 240kV OPEN LINE "PEIGAN 4 240.00" "GOOSEL4 240.00" "75" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 78 COMMENT N-1 PEIGAN 4-GOOSEL4 240kV OPEN LINE "PEIGAN 4 240.00" "GOOSEL4 240.00" "76" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 79 COMMENT N-1 N LETHB4-MATL_AB 240kV OPEN LINE "N LETHB4 240.00" "MATL_AB 240.00" "23" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 80 COMMENT N-1 MATL_AB-MILO 2-LANGDON9-W BROOK4 240kV OPEN LINE "MATL_AB 240.00" "MILO 2 240.00" "23" 1 OPEN LINE "LANGDON9 240.00" "MILO 2 240.00" "27" 1 OPEN LINE Page 695 of 722 APPENDIX I – SWITCHING SEQUENCES "W BROOK4 240.00" "MILO 2 240.00" "23" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 81 COMMENT N-1 N LETHB4-MILO 1-LANGDON9-W BROOK4 240kV OPEN LINE "N LETHB4 240.00" "MILO 1 240.00" "24" 1 OPEN LINE "LANGDON9 240.00" "MILO 1 240.00" "24" 1 OPEN LINE "W BROOK4 240.00" "MILO 1 240.00" "35" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 82 COMMENT N-1 LANGDON9-JANET 4 240kV OPEN LINE "LANGDON9 240.00" "JANET 4 240.00" "36" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 83 COMMENT N-1 PINCHER4-WATWND 240kV OPEN LINE "PINCHER4 240.00" "WATWND 240.00" "W1" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 84 COMMENT T-1 KEEPHILS 500/240kV OPEN XFMR "KEEPHIL4 240.00" "KEEPHILS 500.00" "T6" DELETE ISLANDS DONE **** CASE NUMBER **** 85 COMMENT N-1 PAINTRT4-CORDEL 4 240kV OPEN LINE "PAINTRT4 240.00" "CORDEL 4 240.00" "27" 1 Page 696 of 722 APPENDIX I – SWITCHING SEQUENCES DELETE ISLANDS DONE **** CASE NUMBER **** 86 COMMENT N-1 PAINTRT4-HANSMAN7 240kV OPEN LINE "PAINTRT4 240.00" "HANSMAN7 240.00" "48" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 87 COMMENT N-1 NEVIS 4-CORDEL 4 240kV OPEN LINE "NEVIS 4 240.00" "CORDEL 4 240.00" "20" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 88 COMMENT N-1 BAT RV79-CORDEL 4 240kV DROP GENERATION "BAT #5 21.00" "5 " DROP LOAD "BAT #5 21.00" "SS" OPEN XFMR "BAT RV79 240.00" "BAT #5 21.00" "1" 0 OPEN LINE "BAT RV79 240.00" "CORDEL 4 240.00" "79" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 89 COMMENT N-1 CORDEL 4-HANSMAN7 240kV OPEN LINE "CORDEL 4 240.00" "HANSMAN7 240.00" "53" 1 DELETE ISLANDS DONE # All 138 and 69 kV lines in Alberta south of a Calgary- Sheerness cut plane. **** CASE NUMBER **** 90 COMMENT Page 697 of 722 APPENDIX I – SWITCHING SEQUENCES N-1 BANFF 7-W.CASC T 138kV OPEN LINE "BANFF 7 138.00" "W.CASC T 138.00" "54" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 91 COMMENT N-1 CAN CEM9-742L JCT 138kV OPEN LINE "CAN CEM9 138.00" "742L JCT 138.00" "42" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 92 COMMENT N-1 COCHRAN9-BEARSPAW 138kV OPEN LINE "COCHRAN9 138.00" "BEARSPAW 138.00" "60" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 93 COMMENT N-1 COCHRAN9-ANG COCH 138kV OPEN LINE "COCHRAN9 138.00" "ANG COCH 138.00" "60" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 94 COMMENT N-1 SEEBE 9-GHOST 9 138kV OPEN LINE "SEEBE 9 138.00" "GHOST 9 138.00" "56" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 95 COMMENT N-1 SEEBE 9-KANANAS7 138kV OPEN LINE "SEEBE 9 138.00" "KANANAS7 138.00" "87" 1 DELETE ISLANDS DONE Page 698 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 96 COMMENT N-1 SEEBE 9-BARRIER7 138kV OPEN LINE "SEEBE 9 138.00" "BARRIER7 138.00" "58" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 97 COMMENT N-1 SEEBE 9-POCATER7 138kV OPEN LINE "SEEBE 9 138.00" "POCATER7 138.00" "77" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 98 COMMENT N-1 SEEBE 9-JUMP TP2 138kV OPEN LINE "SEEBE 9 138.00" "JUMP TP2 138.00" "3" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 99 COMMENT N-1 SEEBE 9-742L JCT 138kV OPEN LINE "SEEBE 9 138.00" "742L JCT 138.00" "54" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 100 COMMENT N-1 CASCADE7-W.CASC T 138kV OPEN LINE "CASCADE7 138.00" "W.CASC T 138.00" "54" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 101 COMMENT N-1 GHOST 9-ANG COCH 138kV OPEN LINE "GHOST 9 138.00" "ANG COCH 138.00" "59" 1 DELETE ISLANDS Page 699 of 722 APPENDIX I – SWITCHING SEQUENCES DONE **** CASE NUMBER **** 102 COMMENT N-1 GHOST 9-SPRAY S 138kV OPEN LINE "GHOST 9 138.00" "SPRAY S 138.00" "13" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 103 COMMENT N-1 GHOST 9-JUMP TP1 138kV OPEN LINE "GHOST 9 138.00" "JUMP TP1 138.00" "50" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 104 COMMENT N-1 GHOST 9-MADDEN T 138kV OPEN LINE "GHOST 9 138.00" "MADDEN T 138.00" "80" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 105 COMMENT N-1 BEARSPAW-ENMX21S7 138kV OPEN LINE "BEARSPAW 138.00" "ENMX21S7 138.00" "50" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 106 COMMENT N-1 BEARSPAW-ENMX36S7 138kV OPEN LINE "BEARSPAW 138.00" "ENMX36S7 138.00" "81" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 107 COMMENT N-1 SHELL J9-JUMP TP1 138kV Page 700 of 722 APPENDIX I – SWITCHING SEQUENCES OPEN LINE "SHELL J9 138.00" "JUMP TP1 138.00" "50" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 108 COMMENT N-1 JUMPPND9-JUMP TP2 138kV OPEN LINE "JUMPPND9 138.00" "JUMP TP2 138.00" "3" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 109 COMMENT N-1 SHEPARD9-CARSLAND 138kV OPEN LINE "SHEPARD9 138.00" "CARSLAND 138.00" "50" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 110 COMMENT N-1 BLACK D9-HART TAP 138kV OPEN LINE "BLACK D9 138.00" "HART TAP 138.00" "12" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 111 COMMENT N-1 OKOTOKS9-MAG TAP7 138kV OPEN LINE "OKOTOKS9 138.00" "MAG TAP7 138.00" "27" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 112 COMMENT N-1 MAGCAN 7-MAG TAP7 138kV OPEN LINE "MAGCAN 7 138.00" "MAG TAP7 138.00" "27" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 113 Page 701 of 722 APPENDIX I – SWITCHING SEQUENCES COMMENT N-1 HIGH RI9-BLACKIE7 138kV OPEN LINE "HIGH RI9 138.00" "BLACKIE7 138.00" "53" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 114 COMMENT N-1 CAVALIER-NAMAKA 7 138kV OPEN LINE "CAVALIER 138.00" "NAMAKA 7 138.00" "01" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 115 COMMENT N-1 DUCHESS9-831A TAP 138kV OPEN LINE "DUCHESS9 138.00" "831A TAP 138.00" "31" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 116 COMMENT N-1 CARSLAND-BLACKIE7 138kV OPEN LINE "CARSLAND 138.00" "BLACKIE7 138.00" "51" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 117 COMMENT N-1 BLACKIE7-QUENSTWN 138kV OPEN LINE "BLACKIE7 138.00" "QUENSTWN 138.00" "52" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 118 COMMENT N-1 GLEICHE9-QUENSTWN 138kV OPEN LINE "GLEICHE9 138.00" "QUENSTWN 138.00" "76" 1 DELETE ISLANDS DONE Page 702 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 119 COMMENT N-1 GLEICHE9-NAMAKA 7 138kV OPEN LINE "GLEICHE9 138.00" "NAMAKA 7 138.00" "33" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 120 COMMENT N-1 BROOKSA9-TILLEY 9 138kV OPEN LINE "BROOKSA9 138.00" "TILLEY 9 138.00" "00" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 121 COMMENT N-1 BROOKSA9-W BROOK9 138kV OPEN LINE "BROOKSA9 138.00" "W BROOK9 138.00" "14" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 122 COMMENT N-1 BROOKSA9-W BROOK9 138kV OPEN LINE "BROOKSA9 138.00" "W BROOK9 138.00" "27" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 123 COMMENT N-1 BROOKSA9-HAYS 7 138kV OPEN LINE "BROOKSA9 138.00" "HAYS 7 138.00" "95" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 124 COMMENT N-1 STRATHM9-NAMAKA 7 138kV OPEN LINE "STRATHM9 138.00" "NAMAKA 7 138.00" "33" 1 Page 703 of 722 APPENDIX I – SWITCHING SEQUENCES DELETE ISLANDS DONE **** CASE NUMBER **** 125 COMMENT N-1 W BROOK9-ENCH TAP 138kV OPEN LINE "W BROOK9 138.00" "ENCH TAP 138.00" "63" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 126 COMMENT N-1 W BROOK9-BASNTAP 138kV OPEN LINE "W BROOK9 138.00" "BASNTAP 138.00" "53" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 127 COMMENT N-1 POCATER7-FRO T274 138kV OPEN LINE "POCATER7 138.00" "FRO T274 138.00" "1" 1 DELETE ISLANDS DONE #**** CASE NUMBER **** 128 #COMMENT #N-1 POCATER7-BRITT TP 138kV #OPEN LINE #"POCATER7 138.00" "BRITT TP 138.00" "87" 1 #DELETE ISLANDS #DONE **** CASE NUMBER **** 129 COMMENT N-1 SPRINGB9-JUMP TP2 138kV OPEN LINE "SPRINGB9 138.00" "JUMP TP2 138.00" "3" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 130 COMMENT Page 704 of 722 APPENDIX I – SWITCHING SEQUENCES N-1 SANDYPT9-DOME EM7 138kV OPEN LINE "SANDYPT9 138.00" "DOME EM7 138.00" "69" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 131 COMMENT N-1 SANDHIL7-DOME EM7 138kV OPEN LINE "SANDHIL7 138.00" "DOME EM7 138.00" "71" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 132 COMMENT N-1 STAVELY9-STAVELEY 138kV OPEN LINE "STAVELY9 138.00" "STAVELEY 138.00" "97" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 133 COMMENT N-1 VULCAN 9-BLACKIE7 138kV OPEN LINE "VULCAN 9 138.00" "BLACKIE7 138.00" "61" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 134 COMMENT N-1 VULCAN 9-STAVELEY 138kV OPEN LINE "VULCAN 9 138.00" "STAVELEY 138.00" "80" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 135 COMMENT N-1 EMP LIQ7-EMPLIQTP 138kV OPEN LINE "EMP LIQ7 138.00" "EMPLIQTP 138.00" "60" 1 DELETE ISLANDS DONE Page 705 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 136 COMMENT N-1 PANCAN 9-DOME EM7 138kV OPEN LINE "PANCAN 9 138.00" "DOME EM7 138.00" "60" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 137 COMMENT N-1 PANCAN 9-CHAPPIC9 138kV OPEN LINE "PANCAN 9 138.00" "CHAPPIC9 138.00" "60" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 138 COMMENT N-1 DOME EM7-EMPLIQTP 138kV OPEN LINE "DOME EM7 138.00" "EMPLIQTP 138.00" "60" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 139 COMMENT N-1 DOME EM7-MCNEILL 138kV OPEN LINE "DOME EM7 138.00" "MCNEILL 138.00" "30" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 140 COMMENT N-1 WARLOW9-JENNER7 138kV OPEN LINE "WARLOW9 138.00" "JENNER7 138.00" "52" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 141 COMMENT N-1 EMPLIQTP-OYEN 7 138kV OPEN LINE "EMPLIQTP 138.00" "OYEN 7 138.00" "60" 1 DELETE ISLANDS Page 706 of 722 APPENDIX I – SWITCHING SEQUENCES DONE **** CASE NUMBER **** 142 COMMENT N-1 HIGH RI8-BLACK D8 69kV OPEN LINE "HIGH RI8 69.00" "\BLACK D8\ 69.00" "13" 1 DELETE ISLANDS DONE **** CASE NUMBER **** 143 COMMENT N-1 ING500-CUSTER W 500kV W/RAS OPEN LINE "ING500 500.00" "CUSTER W 500.00" "1 " 1 DROP GENERATION "GMS G2 13.8" "1 " DELETE ISLANDS DONE **** CASE NUMBER **** 144 COMMENT N-1 CUSTER W-MONROE 500kV OPEN LINE "CUSTER W 500.00" "CUSTER&1 500.00" "1 " 1 OPEN LINE "CUSTER&1 500.00" "MONROE 500.00" "1 " 1 DELETE ISLANDS DONE **** CASE NUMBER **** 145 COMMENT N-1 LANGDON9-JANET 2400kV OPEN LINE "LANGDON9 240.00" "JANET 4 240.00" "37" 1 DELETE ISLANDS DONE STOP Page 707 of 722 APPENDIX I – SWITCHING SEQUENCES Path – 8 07 LSP - Pflopro Input Files Page 708 of 722 APPENDIX I – SWITCHING SEQUENCES MATL_P8_PRE_V2.pfp GLOBAL COMMANDS BASE CASE LIST 07LSP_P8_PRE_REV32PF.SAV SS "PRE-PROJECT BASE CASE" #07LSP_P8_N2S_REV32PF.SAV SS "PST-PROJECT BASE CASE" #07LSP_P8_S2N_REV32PF.SAV SS "PST-PROJECT BASE CASE" DONE BASE CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 0 TCUL TAP RATIO ADJUSTMENT 1 AUTOMATIC SVD ADJUSTMENT 1 PHASE SHIFTER ADJUSTMENT 1 AREA INTERCHANGE CONTROL 1 SOLUTION TOLERANCE 0.5 DONE CONTINGENCY CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 0 TCUL TAP RATIO ADJUSTMENT 0 AUTOMATIC SVD ADJUSTMENT 0 PHASE SHIFTER ADJUSTMENT 0 AREA INTERCHANGE CONTROL 0 SOLUTION TOLERANCE 0.5 DONE LOCAL COMMANDS **** CASE NUMBER **** 0 COMMENT N-0 BASE CASE #DELETE ISLANDS DONE **** CASE NUMBER **** 1012 COMMENT N-1 LANGDON - CRANBROOK 500 KV LINE (RAS) OPEN LINE "LANGDON2 500.00" "CBK500 500.00" "1" 1 REMOVE SHUNT REACTOR Page 709 of 722 APPENDIX I – SWITCHING SEQUENCES "CBK500 500.00" "LANGDON2 500.00" "t" "1" 1 REMOVE SHUNT REACTOR "CBK500 500.00" "b2" OPEN LINE "COLEMAN7 138.00" "NTL138 138.00" "1" 1 OPEN LINE "POCATER7 138.00" "FRO T274 138.00" "1" 1 #DELETE ISLANDS DONE **** CASE NUMBER **** 1013 COMMENT N-1 CRANBROOK - SELKIRK 500 KV LINE (RAS) OPEN LINE "CBK500 500.00" "SEL500 500.00" "1" 1 OPEN LINE "LANGDON2 500.00" "CBK500 500.00" "1" 1 REMOVE SHUNT REACTOR "CBK500 500.00" "LANGDON2 500.00" "t" "1" 1 REMOVE SHUNT REACTOR "CBK500 500.00" "b1" REMOVE SHUNT REACTOR "CBK500 500.00" "b2" OPEN LINE "COLEMAN7 138.00" "NTL138 138.00" "1" 1 OPEN LINE "POCATER7 138.00" "FRO T274 138.00" "1" 1 #DELETE ISLANDS DONE STOP Page 710 of 722 APPENDIX I – SWITCHING SEQUENCES MATL_P8_N2S_V2.pfp GLOBAL COMMANDS BASE CASE LIST #07LSP_P8_PRE_REV32PF.SAV SS "PRE-PROJECT BASE CASE" 07LSP_P8_N2S_REV32PF.SAV SS "PST-PROJECT BASE CASE" #07LSP_P8_S2N_REV32PF.SAV SS "PST-PROJECT BASE CASE" DONE BASE CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 0 TCUL TAP RATIO ADJUSTMENT 1 AUTOMATIC SVD ADJUSTMENT 1 PHASE SHIFTER ADJUSTMENT 1 AREA INTERCHANGE CONTROL 1 SOLUTION TOLERANCE 0.5 DONE CONTINGENCY CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 0 TCUL TAP RATIO ADJUSTMENT 0 AUTOMATIC SVD ADJUSTMENT 0 PHASE SHIFTER ADJUSTMENT 0 AREA INTERCHANGE CONTROL 0 SOLUTION TOLERANCE 0.5 DONE LOCAL COMMANDS **** CASE NUMBER **** 0 COMMENT N-0 BASE CASE #DELETE ISLANDS DONE **** CASE NUMBER **** 1012 COMMENT N-1 LANGDON - CRANBROOK 500 KV LINE (RAS) OPEN LINE "LANGDON2 500.00" "CBK500 500.00" "1" 1 REMOVE SHUNT REACTOR "CBK500 500.00" "LANGDON2 500.00" "t" "1" 1 Page 711 of 722 APPENDIX I – SWITCHING SEQUENCES REMOVE SHUNT REACTOR "CBK500 500.00" "b2" OPEN LINE "COLEMAN7 138.00" "NTL138 138.00" "1" 1 OPEN LINE "POCATER7 138.00" "FRO T274 138.00" "1" 1 OPEN LINE "MATL_AB 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MATLN_&1 230.00" "MARIAS 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&2 230.00" "1" 1 OPEN LINE "MATLN_&2 230.00" "GT FALLS 230.00" "1" 1 OPEN XFMR "MATL_AB 240.00" "MATL_AB 230.00" "1" 0 #DELETE ISLANDS DONE **** CASE NUMBER **** 1013 COMMENT N-1 CRANBROOK - SELKIRK 500 KV LINE (RAS) OPEN LINE "CBK500 500.00" "SEL500 500.00" "1" 1 OPEN LINE "LANGDON2 500.00" "CBK500 500.00" "1" 1 REMOVE SHUNT REACTOR "CBK500 500.00" "LANGDON2 500.00" "t" "1" 1 REMOVE SHUNT REACTOR "CBK500 500.00" "b1" REMOVE SHUNT REACTOR "CBK500 500.00" "b2" OPEN LINE "COLEMAN7 138.00" "NTL138 138.00" "1" 1 OPEN LINE "POCATER7 138.00" "FRO T274 138.00" "1" 1 OPEN LINE "MATL_AB 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MATLN_&1 230.00" "MARIAS 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&2 230.00" "1" 1 OPEN LINE "MATLN_&2 230.00" "GT FALLS 230.00" "1" 1 OPEN XFMR "MATL_AB 240.00" "MATL_AB 230.00" "1" 0 Page 712 of 722 APPENDIX I – SWITCHING SEQUENCES #DELETE ISLANDS DONE STOP Page 713 of 722 APPENDIX I – SWITCHING SEQUENCES MATL_P8_S2N_V2.pfp GLOBAL COMMANDS BASE CASE LIST 07LSP_P8_S2N_REV42APF.SAV SS "PST-PROJECT BASE CASE" 07LSP_P8_S2N_REV42BPF.SAV SS "PST-PROJECT BASE CASE" 07LSP_P8_S2N_REV42CPF.SAV SS "PST-PROJECT BASE CASE" DONE BASE CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 0 TCUL TAP RATIO ADJUSTMENT 1 AUTOMATIC SVD ADJUSTMENT 1 PHASE SHIFTER ADJUSTMENT 1 AREA INTERCHANGE CONTROL 1 SOLUTION TOLERANCE 0.5 DONE CONTINGENCY CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 0 TCUL TAP RATIO ADJUSTMENT 0 AUTOMATIC SVD ADJUSTMENT 0 PHASE SHIFTER ADJUSTMENT 0 AREA INTERCHANGE CONTROL 0 SOLUTION TOLERANCE 0.5 DONE LOCAL COMMANDS **** CASE NUMBER **** 0 COMMENT N-0 BASE CASE #DELETE ISLANDS DONE **** CASE NUMBER **** 1012 COMMENT N-1 LANGDON - CRANBROOK 500 KV LINE (RAS) OPEN LINE "LANGDON2 500.00" "CBK500 500.00" "1" 1 REMOVE SHUNT REACTOR Page 714 of 722 APPENDIX I – SWITCHING SEQUENCES "CBK500 500.00" "LANGDON2 500.00" "t" "1" 1 REMOVE SHUNT REACTOR "CBK500 500.00" "b2" OPEN LINE "COLEMAN7 138.00" "NTL138 138.00" "1" 1 OPEN LINE "POCATER7 138.00" "FRO T274 138.00" "1" 1 OPEN LINE "MATL_AB 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MATLN_&1 230.00" "MARIAS 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&2 230.00" "1" 1 OPEN LINE "MATLN_&2 230.00" "GT FALLS 230.00" "1" 1 OPEN XFMR "MATL_AB 240.00" "MATL_AB 230.00" "1" 0 #DELETE ISLANDS DONE **** CASE NUMBER **** 1013 COMMENT N-1 CRANBROOK - SELKIRK 500 KV LINE (RAS) OPEN LINE "CBK500 500.00" "SEL500 500.00" "1" 1 OPEN LINE "LANGDON2 500.00" "CBK500 500.00" "1" 1 REMOVE SHUNT REACTOR "CBK500 500.00" "LANGDON2 500.00" "t" "1" 1 REMOVE SHUNT REACTOR "CBK500 500.00" "b1" REMOVE SHUNT REACTOR "CBK500 500.00" "b2" OPEN LINE "COLEMAN7 138.00" "NTL138 138.00" "1" 1 OPEN LINE "POCATER7 138.00" "FRO T274 138.00" "1" 1 OPEN LINE "MATL_AB 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MATLN_&1 230.00" "MARIAS 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&2 230.00" "1" 1 OPEN LINE "MATLN_&2 230.00" "GT FALLS 230.00" "1" 1 OPEN XFMR Page 715 of 722 APPENDIX I – SWITCHING SEQUENCES "MATL_AB 240.00" "MATL_AB 230.00" "1" 0 #DELETE ISLANDS DONE STOP Page 716 of 722 APPENDIX I – SWITCHING SEQUENCES Wanetta – Boundary 07HS - Pflopro Input Files Page 717 of 722 APPENDIX I – SWITCHING SEQUENCES Wan-Bdy_HS.pfp GLOBAL COMMANDS BASE CASE LIST 07hs_PRE.sav SS "PRE-PROJECT BASE CASE" 07hs_PST.sav SS "PST-PROJECT BASE CASE" DONE OUTPUT FILE PATH E:\Data\Projects\MATL\Rating_Process\Phase_2\PSLF_Work GET CASE PATH E:\Data\Projects\MATL\Rating_Process\Phase_2\PSLF_Work SAVE CASE PATH E:\Data\Projects\MATL\Rating_Process\Phase_2\PSLF_Work IN-RUN EPCL PATH E:\Data\Projects\MATL\Rating_Process\Phase_2\PSLF_Work BASE CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 1 TCUL TAP RATIO ADJUSTMENT 1 AUTOMATIC SVD ADJUSTMENT 1 PHASE SHIFTER ADJUSTMENT 1 AREA INTERCHANGE CONTROL 1 DONE CONTINGENCY CASE SOLUTION PARAMETERS MAXIMUM NUMBER OF ITERATIONS 50 MINIMUM NUMBER OF ITERATIONS 0 ITERATIONS BEFORE VAR LIMITS 0 TCUL TAP RATIO ADJUSTMENT 0 AUTOMATIC SVD ADJUSTMENT 0 PHASE SHIFTER ADJUSTMENT 0 AREA INTERCHANGE CONTROL 0 SOLUTION TOLERANCE 1.0 DONE Page 718 of 722 APPENDIX I – SWITCHING SEQUENCES MONITOR AREA OR ZONE VIOLATIONS AREA 40 AREA 50 AREA 52 AREA 54 AREA 60 AREA 62 AREA 63 DONE # MONITOR BRANCH # "NTL138 138.00" "LCCTAP 138.00" "1" # "NTL138 138.00" "COLEMAN7 138.00" "1" # "MATL_AB 240.00" "MATL_AB 230.00" "1" # DONE LOCAL COMMANDS **** CASE NUMBER **** 0 COMMENT N-0 BASE CASE DONE # PROJECT CONTINGENCIES **** CASE NUMBER **** 1 COMMENT T-1 MATL_AB 240/230KV TRANSFORMER BANK OPEN XFMR "MATL_AB 240.00" "MATL_AB 230.00" "1" OPEN LINE "MATL_AB 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&1 230.00" "1" 1 OPEN LINE "MARIAS 230.00" "MATLN_&2 230.00" "1" 1 OPEN LINE "GT FALLS 230.00" "MATLN_&2 230.00" "1" 1 DELETE ISLANDS DONE Page 719 of 722 APPENDIX I – SWITCHING SEQUENCES # 500 kV lines in Montana **** CASE NUMBER **** 7 COMMENT N-1 Colstrip - Broadview #1 500 kV line OPEN LINE "COLSTRP 500.00" "BROADV&1 500.00" "1 " 0 OPEN LINE "BROADVU 500.00" "BROADV&1 500.00" "1 " 0 DONE **** CASE NUMBER **** 5 COMMENT N-1 Broadview-Townsend-Garrison #1 500 kV line OPEN LINE "BROADVU 500.00" "TOWN1 500.00" "1 " 0 OPEN LINE "GAR1EAST 500.00" "TOWN1 500.00" "1 " 0 OPEN LINE "GAR1EAST 500.00" "GARRISON 500.00" "1 " 0 COMMENT Trip Garrison Reactor REMOVE SHUNT REACTOR "GARRISON 500.00" "b " 0 DONE # 138 kV lines in Alberta south of a Calgary- Sheerness cut plane. **** CASE NUMBER **** 422 COMMENT N-1 BANFF 7-W.CASC T 138kV OPEN LINE "BANFF 7 138.00" "W.CASC T 138.00" "54" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 423 COMMENT N-1 CAN CEM9-742L JCT 138kV OPEN LINE "CAN CEM9 138.00" "742L JCT 138.00" "42" 0 DELETE ISLANDS DONE Page 720 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 471 COMMENT N-1 HUSSAR 8-NAMAKA 7 138kV OPEN LINE "HUSSAR 8 138.00" "NAMAKA 7 138.00" "86" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 473 COMMENT N-1 POCATER7-FRO T274 138kV OPEN LINE "POCATER7 138.00" "FRO T274 138.00" "1" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 478 COMMENT N-1 W.CASC T-54L JNC 138kV OPEN LINE "W.CASC T 138.00" "54L JNC 138.00" "54" 0 DELETE ISLANDS DONE **** CASE NUMBER **** 480 COMMENT N-1 SANDHIL7-DOME EM7 138kV OPEN LINE "SANDHIL7 138.00" "DOME EM7 138.00" "71" 0 DELETE ISLANDS DONE # Remaining contingencies **** CASE NUMBER **** 495 COMMENT N-1 ING500-CUSTER W 500kV W/RAS OPEN LINE "ING500 500.00" "CUSTER W 500.00" "1 " 0 DELETE ISLANDS DONE Page 721 of 722 APPENDIX I – SWITCHING SEQUENCES **** CASE NUMBER **** 496 COMMENT N-1 CUSTER W-MONROE 500kV OPEN LINE "CUSTER W 500.00" "CUSTER&1 500.00" "1 " 0 OPEN LINE "CUSTER&1 500.00" "MONROE 500.00" "1 " 0 DELETE ISLANDS DONE **** CASE NUMBER **** 499 COMMENT Trip all 5 Libby units OPEN LINE "TAFT 500.00" "BELL B&2 500.00" "1 " 0 OPEN LINE "BELL B&1 500.00" "BELL B&2 500.00" "1 " 0 OPEN LINE "BELL BPA 500.00" "BELL B&1 500.00" "1 " 0 INTERMEDIATE SOLUTION DROP GENERATION "LIBBY 13.80" "1 " 0 DROP GENERATION "LIBBY 13.80" "2 " 0 INTERMEDIATE SOLUTION DROP GENERATION "LIBBY 13.80" "3 " 0 DROP GENERATION "LIBBY 13.80" "4 " 0 DROP GENERATION "LIBBY 13.80" "5 " 0 DONE STOP Page 722 of 722