Services Delivery Plan - Projects

advertisement

University of Canberra Public Hospital

Services Delivery Plan

Version Control

Version Date

1.0 13 June 2013

2.0

3.0

3 July 2013

28 August 2013

Remarks

SDP Draft for review

Final Report

Final Report incorporating HSPU,

RACC and Mental

Health Service feedback

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 2 / 37

Table of Contents

List of Acronyms & Abbreviations .............................................................................................................. 5

Executive Summary.................................................................................................................................... 7

1.

Introduction ......................................................................................................................................... 8

1.1. Background ............................................................................................................... 8

1.2. Scope ........................................................................................................................ 8

2.

Governance ........................................................................................................................................ 9

2.1. Governance Structure ................................................................................................ 9

2.2. ACT Health Representatives.................................................................................... 10

2.3. Consultant Team ..................................................................................................... 11

3.

Services Delivery Plan Structure .................................................................................................... 12

4.

Overarching Principles .................................................................................................................... 14

4.1. Overarching Operational Policy Principles ............................................................... 14

4.2. Overarching Design Principles ................................................................................. 14

4.3. Key Issues Register ................................................................................................. 15

4.4. Information and Communication Technology Principles ........................................... 15

5.

Functional Brief ............................................................................................................................... 16

5.1. Methodology ............................................................................................................ 16

5.2. Functional Areas ...................................................................................................... 16

5.3. Content of the Functional Brief ................................................................................. 17

5.4. Furniture, Fittings and Equipment Requirements ..................................................... 20

6.

Strategy Documentation ................................................................................................................. 20

6.1. Communication and Consultation Strategy .............................................................. 20

6.2. Change Management Strategy ................................................................................ 21

6.3. Risk Management Strategy ...................................................................................... 22

6.4. Workforce Change Management ............................................................................. 22

7.

Concept Master Development Plan ............................................................................................... 22

7.1. Architectural Design ................................................................................................. 22

7.2. Engineering Services ............................................................................................... 28

8.

Programme ..................................................................................................................................... 31

9.

Risk Analysis ................................................................................................................................... 32

10. Environmentally Sustainable Design .............................................................................................. 32

10.1. Baseline Inclusions .................................................................................................. 32

10.2. ESD Options ............................................................................................................ 33

10.3. Other ESD Initiatives ............................................................................................... 35

11. Reference Documents .................................................................................................................... 35

12. Qualifications and Limitations ......................................................................................................... 37

13. Recommendation ............................................................................................................................ 37

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 3 / 37

Table of Tables

Table 1: HSPU Personnel ....................................................................................................... 10

Table 2: ERG Members .......................................................................................................... 10

Table 3: UCPH Consultant Team ........................................................................................... 12

Table 4: Structure of the SDP ................................................................................................. 13

Table 5: UCPH Individual HPU Sections of Functional Brief ................................................... 17

Table 6: Project Milestones .................................................................................................... 31

Table 7: ESD Baseline for Capital Cost Estimate and Recurrent Cost .................................... 32

Table 8: Recommended ESD Options .................................................................................... 34

Table 9: Other ESD Initiatives ................................................................................................. 35

Table of Figures

Figure 1: SDP Governance Structure ..................................................................................... 10

Figure 2: Relationship of SDP Components ............................................................................ 12

Figure 3: CMDP Options 1 - 3 ................................................................................................. 24

Figure 4: CMDP Option 4 and Preferred Option 5 ................................................................... 24

Appendices

1. Functional Brief

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 4 / 37

List of Acronyms & Abbreviations

BECHC

BHRC

BRG

CADP

CHHS

CMDP

COW

CTS

DA

DHE

DORSS

ELS

ERG

ESD

FFE

GDK

GFA

HFBS

HIP

HPU

HSPU

ICT

ILC

IPU

Acronym/

Abbreviation

ACTPAS

ACTES

ADL

ADM

AGV

AHFGs

Altus

Aurora

Meaning

B&I

BMS

ACT Patient Administration System

ACT Equipment Service

Activities of Daily Living

Automated Dispensing Machine

Automated Guided Vehicle

Australasian Health Facility Guidelines

Altus Group ( Cost Planner)

Aurora Projects (Project Director, Health Services and Facility Planning, Project

Manager)

Business and Infrastructure, Branch of ACT Health Support Services Group

Building Management System (also known as BMCS, Building Management

Control System)

Belconnen Enhanced Community Health Centre

Brian Hennessy Rehabilitation Centre

Boffa Robertson Group (Architect)

Capital Asset Development Plan (now referred to as HIP)

Canberra Hospital and Health Services

Concept Master Development Plan

Computer on Wheels

Clinical Technology and Equipment Service

Development Approval

Digital Health Enterprise

Domiciliary Oxygen and Respiratory Support Scheme

Equipment Loan Service

Executive Reference Group

Environmentally Sustainable Design

Furniture, Fittings & Equipment

GDK Engineering (Hydraulic/ Wet Fire Services Engineering Consultant)

Gross Floor Area

Health Facility Briefing System

Health Infrastructure Program (formerly CADP)

Health Planning Unit

Health Service Planning Unit

Information and Communication Technology

Independent Living Centre

Inpatient Unit

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 5 / 37

SWAPS

TMV

TTW

UC

UCPH

UG

Varius

VOIP

WAN

WHS

Acronym/

Abbreviation

LAN

MATV

MHAGIC

MOC

NCC

NSQHS

OMPH

P&O

RACC

RDS

RFID

RTLS

SDP

SOA

SSOA

SVA

Meaning

Local Area Network

Master Antenna Television

Mental Health Assessment Generation Information Collection

Model of Care

National Construction Code (formerly BCA)

National Safety and Quality Health Service

Older Persons Mental Health

Prosthetics and Orthotics

Rehabilitation, Aged and Community Care

Room Data Sheets

Radio Frequency Identification

Real Time Location Services

Services Delivery Plan

Schedules of Accommodation

Summary Schedules of Accommodation

Steenson Varming (Electrical, Mechanical, Dry Fire Services and Security

Engineering Consultant)

Specialised Wheelchair and Posture Seating Service

Thermostatic Mixing Valve

Taylor Thomson Whitting (Structural/ Civil Engineering Consultant)

University of Canberra

University of Canberra Public Hospital

User Group

Varius Pty Ltd (ICT adviser)

Voice Over Internet Protocol

Wide Area Network

Work Health & Safety

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 6 / 37

Executive Summary

Aurora Projects (Aurora) and its consultant team were engaged to complete a Services Delivery

Plan (SDP) for the proposed University of Canberra Public Hospital (UCPH). This SDP has been completed within the required timeframe, utilising the existing governance structure as established by ACT Health.

Aurora was appointed in March 2013 with the first round of stakeholder User Group (UG) meetings commencing at the end of March 2013. The subsequent two rounds of UG consultation were undertaken in April and May 2013 with final completion of the SDP report in

June 2013.

Key components of the SDP include the Health Planning Unit (HPU) Briefs, Concept Master

Development Plan and capital and recurrent cost estimates for the proposed UCPH facility.

These documents were developed in consultation with the ACT Health Executive Reference

Group, UG representatives for the development of the individual HPU Briefs and other relevant stakeholders.

The proposed UCPH facility is 20,745m

2

(GFA) in size

.

It is recommended that ACT Health proceed with subsequent planning and design activities and ultimately implementation of the UCPH project, utilising the SDP as guidance to inform the next phase of planning.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 7 / 37

1.

Introduction

1.1. Background

Aurora Projects (Aurora) and its consultant team were commissioned by ACT Health to develop this Services Delivery Plan (SDP) for the proposed University of Canberra Public Hospital

(UCPH).

The objective of the SDP is to:

 Clearly define the services required to be delivered by the facility;

 Outline the concept for the facility that the defined services would be delivered from;

 Include strategies required to support and facilitate actions required during the course of the project i.e. delivery of the facility; and

 Include management strategies that facilitate development of the framework for which services delivery will commence and continue upon.

The SDP is comprised of a Functional Brief, Concept Master Development Plan (CMDP) including departmental concept plans, strategy documents and financial information.

The term CMDP is used to demonstrate that the objective of the SDP is to maintain the planning work at concept level and establish a clear concept master plan for development of the health facilities within the context of the University’s ‘Health Precinct’, noting the importance of relationships with complimentary collocated facilities. The other key objective is that the CMDP is to facilitate the ability to expand components of the health facility in the future.

The SDP has been informed by the following key ACT Health background documents:

 Proposed Northside Subacute Hospital Canberra ACT – Report from Subacute Hospital

Planning Workshop (January 2013)

 Service Models and Projected Service Demand for Adult Rehabilitation and Aged Care

Services Report for the proposed Northside subacute hospital (9 October 2012)

 Northside Subacute Hospital Mental Health Services Consultation Report (August 2012)

 Northside Subacute Hospital Planning Workshop (Mental Health) Summary Reports (22

March 2012 and 2 May 2012)

 Health Infrastructure Program (HIP) Master Documentation

These reports identified the services to be considered during further planning at UCPH as well as overarching models of service delivery and are currently in the process of being endorsed.

The above reports and other relevant documentation were referred to throughout the process of developing the SDP (refer to list of Reference Documents, Section 12).

1.2. Scope

As a result of the objectives and the consultation undertaken the UCPH facility is comprised of subacute rehabilitation and aged care inpatient day and ambulatory services including hydrotherapy, and mental health rehabilitation and day services.

These four services are supported by clinical support services such as pharmacy and pathology and non clinical support services such as food, cleaning, waste management, linen, property management and maintenance. A key component of the scope of UCPH is the research, education and meeting functions which are housed alongside the Executive offices and staff workspaces. Administration services including ACT record management, clinical records, security, switch and mailroom are provided. These services are referenced in detail under the

Functional Brief section of the document, Section 5.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 8 / 37

Upon commencement of the SDP, the proposed UCPH site was identified as being on the

University of Canberra (UC) Bruce campus in the northern suburbs of Canberra (corner of

Aikman and Ginninderra Drives). However, at the time of preparation of the SDP the exact location for the facility had not been formally agreed with UC; the SDP has been developed based upon the UC site as a working assumption.

The new facility will comprise 140 beds plus outpatient/ day/ ambulatory services. Emergency

Department and other acute services will not operate from the site. Contemporary subacute health facility planning principles have underpinned the development of the project.

Other health facility planning working assumptions such as the percentage of single rooms in the rehabilitation and aged care Inpatient Units (IPUs), facility planning for UC space, and the extent of shared space with UC have been made to facilitate the briefing and design process.

Whilst parking for UCPH staff, patients and family/ carers is proposed to be located adjacent to the new facility it will be provided by UC.

2.

Governance

Governance of the UCPH project has been provided within the existing ACT Health governance framework. The governance structure is to be reviewed at each phase of the project to ensure that the reporting structure and terms of reference meet the needs of the project.

2.1. Governance Structure

The meeting and reporting structure for the SDP consisted of the following:

 Executive Reference Group (ERG) – an existing group established by ACT Health for the

UCPH project

Responsible for managing deliverables of the project

Monitoring project objectives, key deliverables, program, budget and scope

Includes members with specialist skills who are able to inform the decision making process

Makes recommendations to the Canberra Hospital and Health Services Project

Control Group for decision/ endorsement by the Redevelopment Committee

 The Principal Consultant (Aurora) – coordinating the activities of the CMDP team

Communication link between the ERG, the CMDP Team, departmental User Groups

(UGs) and ACT Health where necessary

Communication of relevant project information and prioritisation of issues that require resolution or direction

 The CMDP Team

Attendance at start-up workshop (ERG Meeting 1) and site visits as necessary

Attendance at planning coordination meetings with the Principal Consultant

CMDP Lead Consultant (architect) attendance at concept options workshop and preferred option review presentation

 Departmental User Groups

Provide department specific input to inform the development of the HPU Briefs

The SDP governance structure is illustrated in Figure 1.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 9 / 37

Figure 1: SDP Governance Structure

2.2. ACT Health Representatives

The following key personnel (Table 1) from the ACT Health Services Planning Unit (HPSU) were involved in the preparation of the Services Delivery Plan.

Table 1: HSPU Personnel

Representative

Jacinta George

Robert Bampton

Maria Harman

Sandy Myint

Department

Senior Manager, Health Services Planning Unit

Manager, Facility Planning

Health Facility Planning Officer

Administrative & Facility Planning Officer

The ERG was consulted throughout the development of the SDP for resolution regarding key issues and endorsement of the outcomes of the UG meeting process, the ERG consisted of the following members (Table 2).

Table 2: ERG Members

Representative

Grant Carey-Ide (Chair)

Liz Sharpe/ David Robertson

Jacinta George

Jon Barnes

Liz Sharpe

Department

Executive Director, Service and Capital Planning

Executive Officer, Service & Capital Planning

Senior Manager, Health Services Planning Unit

Executive Construction and Program Director,

Redevelopment Unit

A/Operational Director, Redevelopment Unit

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 10 / 37

Representative

Colm Mooney

Stephen Goggs

Ian Thompson

Linda Kohlhagen

Katrina (Tina) Bracher

Judy Redmond

Rosemary Kennedy

Judi Childs

Neil Bulless

Kerry Snell

Dalane Drexler

Dee McGrath

Rhonda Maher

Nicole Masters

Gary Wright

Jennifer Elliott

Amanda Davies

Maria Harman

Rob Bampton

Sam Morgan

Robyn Cross

Department

Director, Procurement, Health Infrastructure

Program (Shared Services Procurement)

Deputy Director-General, Strategy & Corporate

Deputy Director-General, Canberra Hospital &

Health Services

Executive Director, Rehabilitation, Aged and

Community Care

Executive Director, Mental Health , Justice Health and Alcohol & Drug Services

Chief Information Officer EHealth Projects and

Clinical Records

Executive Director, Business & Infrastructure

Executive Director, People, Services & Strategy

Executive Director, Chief Minister and Treasury

Directorate

Health Care Consumer Representative, HCCA

ACT Mental Health Consumer Network

Representative

Consumer Representative, Carers ACT

Proxy for Executive Director, Rehabilitation, Aged and Community Services

Proxy for Executive Director, Chief Minister and

Treasury Directorate

Proxy for Executive Director, Business &

Infrastructure

Proxy for Executive Director, e-Health & Clinical

Records

Proxy for ACT Mental Health Consumer Network

Representative

Facility Planning Officer, Health Services Planning

Unit

Senior Facility Planning Officer, Health Services

Planning Unit

Senior Manager HIP Finance, Service and Capital

Planning

Senior Projects Officer, Service and Capital

Planning

In addition to the above ACT Health representatives, the appended User Group Membership

Schedule details representatives who participated in the UG consultation process.

2.3. Consultant Team

The following Aurora and sub-consultant personnel (Table 3) were involved in the preparation of the SDP.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 11 / 37

Table 3: UCPH Consultant Team

Personnel

Aurora Projects

Jo Thorley

Gavin Thompson

Gemma Hepple

Simone Sharp

Boffa Robertson Group (BRG)

John (Jock) Robertson

Dominic Polito

Steensen Varming (SVA)

Roland Towning

Dan MacKenzie

Michael Fearnley

Dominic Choiligh

Chris Arkins

Taylor Thomson Whitting (TTW)

Robert Mackellar

Paul Yannoulatos

Ross McDougall

GDK Engineering (GDK)

George Koutoulas

Paxon

Michael Palassis

David Bath

Joan Coffey

Altus Group (Altus)

Barry Woollam

Alan Fox

Deane Pondekas

Varius Pty Ltd (Varius)

Greg Bezuidenhout

Role

Project Director

Project Manager

Health Services & Facility Planner

Health Services & Facility Planner

Concept Master Development Planner/ Architect

Concept Master Development Planner/ Architect

Technical Director

Engineering Services Manager

Electrical, BMS Engineer

Mechanical, ESD, Building Services Engineer

Environmentally Sustainable Design Engineer

Structural, Façade Engineer

Civil Engineer

Engineering Support

Hydraulic/ Wet Fire Engineer

Recurrent Cost Planner

Recurrent Cost Planner

Recurrent Cost Planner

Capital Cost Planner

Capital Cost Planner

Capital Cost Planner

ICT Strategic Planner and Adviser

3.

Services Delivery Plan Structure

The SDP incorporates a services delivery driven CMDP solution that responds to the functional and operational requirements of the UCPH project. Figure 2 illustrates the relationship between the different components of the SDP.

Figure 2: Relationship of SDP Components

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 12 / 37

This report describes key summary information regarding each of the above components of the

SDP and detailed reports and documentation are appended.

The SDP content is further outlined in Table 4 below for ease of access in viewing the above figure.

Table 4: Structure of the SDP

SDP Heading and Contents

1. Introduction

 Purpose

 Background

 SDP Structure

2. Governance

3. Services Delivery Plan Structure

4.

Overarching Principles

 Outlines the overarching principles which have been applied to planning for

UCPH as a whole

5. Functional Brief

 Outlines the requirements of each of the individual HPU functional areas within

UCPH

 Includes Schedules of Accommodation

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 13 / 37

SDP Heading and Contents

6. Strategy Documentation

 Outlines strategy documentation which has been prepared in parallel with the

HPU briefing process to inform future planning stages for UCPH

 Includes Communication and Consultation, Change Management and Risk

Management Strategies and Workforce Change Management

7. Concept Master Development Plan

 Summary of five Concept Master Development options and outline of the preferred option

 Design features and other considerations (future expansion)

 Engineering services requirements

8. Project Programme

9. Risk Analysis

10. Financial

 Capital cost estimate and capital cost cash flow

 Recurrent costs

11. Environmentally Sustainable Design

 Baseline inclusions

 ESD options

12. Reference documents

13. Qualification and Limitations

14. Conclusion

15. Recommendation

4.

Overarching Principles

4.1. Overarching Operational Policy Principles

Overarching operational policy principles were developed in consultation with the ERG upon commencement of the UG process. These principles were established to inform and be tested by the UG consultation process. They were further developed in parallel with the development of departmental HPU briefs. Revised principles have been finalised in consultation with the ERG and are included within the appended Functional Brief.

Overarching operational policy principles have been developed to inform the UCPH context and do not override existing ACT Government policies. Specific operational policies noted within each of the individual HPU section of the Functional Brief, should be read in conjunction with the overarching operational policy principles for UCPH.

4.2. Overarching Design Principles

Specific design requirements for functional areas are outlined within the Functional Brief.

Design requirements which are overarching and relevant to the UCPH facility as a whole have

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 14 / 37

been determined throughout the planning process. These requirements have been further developed in relation to the CMDP (refer Concept Master Development Plan, Section 7).

The overarching design principles listed below are detailed within the appended Functional

Brief:

 Compliance with current standards and guidelines

 Alignment with the Australasian Health Facility Guidelines

 Care for patients with dementia

The following general design requirements are also include in the Functional Brief:

 Access

 Wayfinding and signage

 Environment

 Flexibility/ adaptability

 Expansion

 Environmentally sustainable design

 Occupational safety and health

 Infection control

4.3. Key Issues Register

As part of the HPU briefing process, a key issues register was developed to capture key issues and decisions made to inform the development of the HPU briefs, Schedules of Accommodation

(SOA) and subsequent CMDP.

Key issues/ decisions were generated in a number of forums and reported to the ERG for note and/ or approval. A Key Issues Register was developed to record the decisions made. The register is included within the Functional Brief.

4.4. Information and Communication Technology Principles

An Information and Communication Technology (ICT) Principles document included in the

Functional Brief has been prepared for UCPH as a framework document to support the National eHealth and ACT Digital Health Enterprise strategies.

The key features of the document are:

 Implementation of a medical grade network is key

 Network design, building and floor distribution rooms are designed to ensure high levels of redundancy

 UCPH will be a spoke facility accessing servers located in a remote server room

The ICT principles are detailed within the appended Functional Brief and include:

 Current Technologies

 Proposed Technologies

ICT Spatials

Backbone and Active Equipment

Furniture, Fittings & Equipment (FFE)

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 15 / 37

5.

Functional Brief

5.1. Methodology

The Functional Brief for UCPH was developed initially as individual HPU briefs describing the requirements for each of the functional areas within the facility. At the completion of the UG briefing process the individual HPU briefs were combined to form the sections of the Functional

Brief.

UGs representing the requirements of each of the functional areas were established to inform development of the briefs. Refer to appendices for membership of the UGs.

UG consultation was undertaken in three rounds:

Round 1 – 25 & 26 March and 2 April 2013

Initial draft HPU briefs were prepared based on existing documentation, comparison to like facilities and the Australasian Health Facility Guidelines (AHFGs). Principles outlined within the

HIP Master Documentation were incorporated into initial draft briefs e.g. bedroom size, medication management etc.

The description and scope of the future service, the service planning context (as a snapshot from service planning documentation), Model of Care (MOC), specific operational policies for the future service and functional relationships were discussed.

High level discussion of the SOA (departmental room sizes and quantities) was also included.

Feedback from the UGs was incorporated into updated HPU briefs for the next round of meetings.

Round 2

– 15 to 17 April 2013

Updated HPU briefs were reviewed and further developed to include:

 Future MOC and operational policies

 Functional relationships and relative location of the department

 Future service delivery and technological trends

 Specific design considerations

 Specific Furniture and FFE requirements to inform development of the Room Data Sheets

(RDS)

The SOA was further refined and staffing requirements incorporated into the HPU briefs.

Round 3 – 6 to 9 May 2013

The final round of UG meetings focused upon the final resolution of issues and FFE requirements for the non-standard rooms. Confirmation/ endorsement of the HPU Briefs subject to incorporation of changes identified at the meeting was also undertaken.

Throughout the UG consultation process, any variations to the AHFGs were identified and rationale for the variations was confirmed.

5.2. Functional Areas

Following the finalisation of the UG consultation process, HPU briefs were broken down into distinct departmental/ functional areas to inform the spatial allocation (m2) and functional relationship requirements to be represented within the CMDP and subsequent planning phases.

These were ultimately combined in to the overall Functional Brief appended to this report.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 16 / 37

Table 5 outlines the list of individual HPU briefs developed and included in the sections of the

Functional Brief.

Table 5: UCPH Individual HPU Sections of Functional Brief

9

10

11

12

13

14

Section HPU Section

2 Rehabilitation & Aged Care Inpatient Units

3

4

Adult Mental Health Rehabilitation Unit

Rehabilitation & Aged Care Day/ Community/ Ambulatory Services

7

8

5

6

Adult Mental Health Day Service

Hydrotherapy

Executive & Central Staff Workspace

Clinical Technology & Equipment Services

15

Main Entry & Hospital Operations

Central Staff Amenities

Education, Research & Meeting Facilities

Pharmacy

Pathology

Body Holding

Support Services/ Front of House:

ACT Administrative Management; Switch & Mailroom; Security, Fire Safety,

Parking and Fleet Management

16

17

18

19

20

Food Service

Cleaning, Waste Management & Hygiene

Linen Service

Supply & Docks

Support Services/ Back of House:

Clinical Engineering, Shared Services ICT, Property Management & Maintenance

5.3. Content of the Functional Brief

The individual HPU sections of the Functional Brief contain a number of sub-sections required to inform the design of the new facilities. A summary of each of these sections is described below.

5.3.1. Model of Care

The MOC is described for clinical areas where patient care is provided. HPU sections for support services (e.g. Education, Meetings & Research, and Food Services etc.) do not include a description of the MOC. The model of service delivery for these areas is described within the operational policy and other relevant sub-sections of the brief.

The MOC sub-section for the clinical HPU briefs outlines the key aspects of the models that are required to inform the design of these spaces. It is expected that MOCs will be further developed in subsequent stages of planning to include more detail and to incorporate any changes to care delivery etc.

Good public transport links will be essential to the operationalisation of the MOC for this facility.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 17 / 37

5.3.2. Operational Policies

This sub-section outlines the key operational requirements for each of the functional areas. In particular, operational policies which are specific to the functional area are described. This subsection is to be read in conjunction with the Overarching Operational Policy Principles for UCPH

5.3.3. Design Requirements

This sub-section describes specific design requirements for each of the spaces within functional areas. The majority of spaces will be configured to be consistent with the AHFGs. Where there are variations to the AHFGs required, or where spaces are not addressed by the AHFGs, the requirements for these spaces are outlined.

Specific design requirements are to be read in conjunction with the Overarching Design

Principles for UCPH.

5.3.4. Functional Relationships

This sub-section identifies key functional relationships required within each functional area

(internal) and between each area and other areas of UCPH (external). These relationships are required to support the movement of patients, staff and carer/ visitor movements throughout the new facilities.

Functional relationships have been reviewed to inform the CMDP and the location for each functional area in the new facility.

5.3.5. Staff Profile

Proposed workforce requirements for each functional area have been outlined within each of the HPU briefs. Projected staff profiles have been developed to inform this stage of planning and will be subject to adjustment both in numbers and classification as the workforce change management strategy is implemented in parallel with development of the MOCs/ service delivery models.

Proposed staff profile information has been used to inform the requirements for staff amenities and workspace (offices and workstations). The proposed staff profile information will be subject to ongoing review and development as planning progresses. The approach to workforce planning and change management is outlined within the Workforce Change Management

Strategy, Section 6.4.

5.3.6. Schedules of Accommodation

SOA have been developed for each functional area. The SOA identifies all rooms/ spaces and the area (m2) required to accommodate their nominated functions, within each of the functional areas. The SOA includes both enclosed and unenclosed (external) functional areas.

Unenclosed areas include requirements for vehicle access/ pick-up/ set-down on the UCPH site.

The SOA has been developed based on the following:

 AHFGs where possible

 HIP Master Documentation

 Analysis of the UCPH functional requirements

 ACT Health Office and Service Facilities Accommodation Policy (August 2012)

For spaces that are not included within the AHFGs or HIP Master Documentation, a review of functional requirements has been undertaken to inform the spatial allocation. There are some spaces for which a variation to the AHFGs has been included in the SOA. These spaces have

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 18 / 37

been identified as having functionality which is different to that proposed in the AHFGs and so this has been reviewed and variations included within the SOA.

A table outlining variations to the AHFGs is appended to the Functional Brief and describes the rationale for the variations which have been included. Variations to the AHFGs are relatively minor and been reviewed and endorsed by the ERG.

Whilst developing the SOA for different functional areas, consideration was given to the feasibility of sharing spaces between different functional areas and incorporated into the SOA where possible. A further review of the SOA was undertaken upon completion of the UG consultation process by the ACT Health Service Planning Unit in conjunction with Aurora to identify any further opportunities for sharing of like spaces. A table outlining the review and rationalisation of spaces is appended to the Functional Brief as “Summary Information –

Schedules of Accommodation: Rationalisation ”.

The Summary Schedules of Accommodation (SSOA) is also included within the Functional

Brief. The SSOA outlines the space requirements for each functional area and for UCPH as a whole.

Following review and feedback from HSPU additional space was added to the SOA due to increase in medication/ utility room sizes and the change from 40% to 60% single bed rooms in the rehabilitation and aged care IPUs.

As a result of the briefing, rationalisation process and further consultation with HSPU the proposed Gross Floor Area (GFA) for UCPH is 20,745m

2

.

5.3.7. Room Data Sheets

Preliminary RDS have been prepared for each functional area (excluding Food Services). RDS have been prepared as part of the SDP to:

 Test the spatial allocation (m2) for each room/ space

 Inform the capital cost estimate

 Provide a basis for subsequent planning phases.

It was agreed with ACT Health that RDS would not be prepared for Food Services due to the specialist nature of the service and associated FFE. It is intended that RDS for Food Services be developed in the next stage of planning with specialist consultant input to do so.

Preparation of the UCPH RDS has been based on the following:

 AHFGs and Health Facility Briefing System (HFBS) standard rooms

 Incorporation of UCPH specific requirements as identified within the Functional Brief

UCPH RDS consist of both standard and non-standard rooms. Standard rooms are those rooms which have been standardised throughout the facility so that there is consistency throughout all rooms where appropriate. Standard rooms represent approximately 70% of the total UCPH rooms. Non-standard rooms have been generated for those rooms which are unique and not repeated throughout the facility e.g. gymnasiums, Hydrotherapy, Prosthetics & Orthotics workshop and consult room. RDS for these rooms have been generated to capture the specific

UCPH requirements for each of these spaces.

The RDS have been developed within the HFBS and the milestone ‘UCPH SDP’ has been created to signify the completion of the SDP and this phase of planning. As a database (HFBS) has been used to generate the RDS, they have not been appended to this report. For access to the UCPH RDS, please contact:

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 19 / 37

Robert Bampton

Senior Facility Planning Officer

Health Services Planning Unit

(02) 6174-8011

Robert.Bampton@act.gov.au

The RDS have not been updated since the above milestone was created, the total area does not reflect final changes to the SOA, namely increase in single bed rooms from 40% to 60% in the Rehabilitation and Aged Care IPUs and increase in size of the medication/ utility rooms.

5.4. Furniture, Fittings and Equipment Requirements

FFE requirements for UCPH are as detailed within individual RDS. As noted above, FFE has been developed as part of the SDP to inform the spatial allocation for rooms/ spaces as well as the capital cost estimate. The RDS have not been updated since the milestone outlined in

Section 5.3 was created, the FFE list does not reflect final changes, namely additional hoists in

Rehabilitation and Aged Care Day Services treatment room and one of the multifunction consultation rooms and portable hearing loop devices.

Specialty equipment which has been identified for the UCPH to be specifically addressed within the capital cost estimate is as follows:

 Provision of ceiling mounted hoists

Within all Rehabilitation and Aged Care IPU bedrooms as detailed within the Functional

Brief

Within gymnasiums

Within the Rehabilitation and Aged Care Day Services treatment room and one of the multifunction consultation rooms

Within the Hydrotherapy area including one floor mounted hoist

 Automated Dispensing Machine (ADM) within central pharmacy space

 ADMs within the ward medication/ utility rooms

 Hydrotherapy pool and associated plant

6.

Strategy Documentation

The information received during the UG process and ERG meetings, along with existing ACT

Health policy documents, has been used to inform UCPH strategy documents and finalisation of

CMDP and associated cost plans.

6.1. Communication and Consultation Strategy

A Communication and Consultation Strategy has been developed to guide the consultation and communication processes of the project planning phase, ensure robust stakeholder management and engagement, and lay the foundations for good workforce change communication during the UCPH project timeframe.

The strategy identifies the communication objectives and approach that will be adopted in development of the UCPH Communication Action Plan and outlines the governance framework within which it sits.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 20 / 37

Key messages have been identified for delivery to stakeholders at key project milestones during the following phases:

 Project Initiation

 Facility Planning

 Change Management stages

 Design and Construction

 Commissioning

 Post Occupancy

Stakeholders have been identified from the following groups:

 Internal

Internal staff

Staff at other facilities e.g. The Canberra Hospital, Village Creek, Community Team,

Brian Hennessy Rehabilitation Centre, Belconnen Enhanced Community Health

Centre

 External stakeholders including:

Patients and carers

Staff at Calvary Hospital

Consumers and consumer organisations

Media organisations

The strategy provides guidance for internal and external consultation tools and activities and the process for monitoring and evaluation of the strategy and Communications Action Plan.

The Communication Action Plan that will implement the strategy is currently underdevelopment by ACT Health.

Refer appended Communication and Consultation Strategy.

6.2. Change Management Strategy

The Change Management Strategy has been developed to facilitate the identification, assessment of areas of change, and implementation of plans to action and manage the impact of the changes associated with the UCPH development.

The strategy identifies the need to establish a strategy for communication and consultation and linked Change Management Implementation Plan to ensure that key changes arising are communicated to internal and external stakeholders at suitable project milestones.

Changes associated with UCPH development may arise from the new MOCs and service delivery, facility capacity, and operational and business practices delivered through UCPH commissioning. The process for monitoring and reviewing the implementation of change has been identified and involves formal and informal monitoring and evaluation strategies; contingencies for modifying key changes; and development and dissemination of new policies, procedures, and processes as appropriate for each change.

The strategy confirms the UCPH governance structure and identifies the requirements for allocation of resources to manage the associated workforce change process.

Refer appended Change Management Strategy.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 21 / 37

6.3. Risk Management Strategy

The UCPH Risk Management Strategy has been established as an overarching strategy for managing the risks associated with the planning, design, construction and commissioning phases of the UCPH project. The development of the strategy was made in accordance with the

Australian/New Zealand Standard AS/NZS ISO 31000:2009.

The strategy utilises the UCPH project governance structure and describes the approach to analysing and managing risk in collaboration and consultation with project stakeholders to ensure that the identified benefits of the UCPH development are realised within scope, timeframe and budget.

Refer appended Risk Management Strategy.

6.4. Workforce Change Management

The approach to workforce change management to address the workforce requirements for

UCPH will be consistent with ACT HIP methodology. This methodology is based upon well established principles developed by ACT Health to inform workforce requirements for other HIP projects and is currently being updated by ACT Health.

As a new health facility in the ACT, UCPH represents a significant challenge in developing a workforce which is able to meet its needs. The process of addressing workforce planning and change management has been commenced with the development of draft preliminary projected staff profile for each functional area as outlined within each of the individual HPU sections of the

Functional Brief.

Ongoing methodology to address future workforce requirements is detailed within the UCPH

Workforce Change Management Report (refer to appendices).

7.

Concept Master Development Plan

7.1. Architectural Design

7.1.1. Facility Description

The UCPH facility design for the CMDP has been developed upon principles of patient centeredness and optimising service delivery. This philosophy informed many of the decisions made in terms of access, configuration and building massing. From the outset the objective was to provide clear, distinct and separate public and staff only circulation. Staff only/ support services have been considered using AGVs in the future to collect and distribute food, linen, goods and waste, enabling these deliveries to occur being largely unaware by patients and members of the public.

The physical massing has been created with the intention of progressively scaling the buildings in size from the two storey Main Entry component, to the single storey IPUs, through to discrete pods of four clusters of five bedrooms in the Adult Mental Health Rehabilitation Unit at the opposite end. The intention with this approach has been to create a more domestic and less institutional scale, particularly as many of the IPU residents will spend considerable lengths of time there and to create an empathetic healthcare environment that promotes improved healing and recovery.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 22 / 37

7.1.2. Arrangement

Distinct separation of general public access from staff only/ support services was identified as a major driver with regard to the layout of the facility. This front of house/ back of house distinction has informed the eventual facility configuration.

In order to assist in wayfinding, the approach has been to provide public access to the various parts of the facility via a central circulation spine originating at the main entry to the facility. Day

Services are located adjacent the entry, with IPUs located in pairs on either side of the main corridor and pedestrian access at the end of this spine to the Adult Mental Health Rehabilitation

Unit.

Following the first round of UG meetings and initial space requirements identified in the first draft SOA, three concepts were prepared that illustrated how support services could be effectively delivered to each IPU. The options were evaluated and scored at the SDP Options

Review Workshop held on 18 April 2013.

The first option (Option 1) located service corridors at the opposite end of the IPUs to the public entry. This had the effect of creating enclosed courtyards created by an IPU on the north and south, with the main entry spine completing the quadrant. In the evaluation of this scheme, there were mixed views (in relatively equal measure) that the enclosing service corridors created an environment where privacy was limited by being able to be viewed from two sides and denied view outlooks beyond, contradicted by an opposing view that the enclosed courtyards created a more secure environment. There was, in addition, a view that this arrangement best afforded access from the main circulation spine into shared services located between the paired IPUs.

The second option (Option 2) attempted to create a more compact building footprint on the site, again incorporating the Option 1 concept of ‘external’ support services corridors and enclosed courtyards, with 4 x IPUs were located on the first floor, Day Services and Adult and Older

Persons Mental Health (OPMH) IPUs located at ground floor level to provide access to landscaped courtyards. This option was discounted for a number of reasons including limitations on future expansion, limited access to hydrotherapy plant, and having a large proportion of the street frontage dedicated to non-hospital functions.

The third option (Option 3) located support services immediately adjacent the main circulation spine, linking a pair of IPUs with an access corridor between the public entries to each IPU.

This had the advantage of opening up the landscaped courtyards to views beyond, however, it was considered to be problematic in providing direct connection between the main circulation spine and the shared services zone linking both IPUs, the support services zone effectively blocking the potential for such a connection.

These three options are illustrated in Figure 3.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 23 / 37

Figure 3: CMDP Options 1 - 3

The outcome of the workshop resulted in the investigation of a hybrid of Options 1 and 3, being

Option 4. As a result of the decision to locate OPMH Services at another location a further option, Option 5, was developed and taken to the ERG Preferred Option Review held on 31

May 2013, refer Figure 4.

Figure 4: CMDP Option 4 and Preferred Option 5

Following the recommendations from the Preferred Option Review Hydrotherapy was relocated closer to the main entrance with its own entrance, an additional pedestrian access at the end of the main corridor, and a drop off bay for the Clinical Technology and Equipment Service

(CT&ES) were added.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 24 / 37

7.1.3. Departmental Locations

Departments are located to optimise effective access for patients and their visitors, service vehicle movements, and administrative and educational functions. Day patient services are located in close proximity to the main entry to avoid excessive patient travel and additional through traffic through IPUs. A separate entry is also provided on the main frontage which allows more direct access to the Hydrotherapy Service and Rehabilitation and Aged Care Day/

Community/ Ambulatory Services and Adult Mental Health Day Service. In addition, a clear zone for pick up and drop off of equipment to the CT&ES has been located on the main frontage.

The locations of main departments within the facility, as related to the individual HPU sections of the Functional Brief and SOA are as follows:

Lower Ground Floor

Central Staff Amenities

Food Services

 Body Holding

 Cleaning, Waste Management &

Hygiene

 Linen Services

 Communication Room

 Supplies & Docks

 Support Services/ Back of House (Clinical Engineering, Shared Services ICT, Property

Management & Maintenance)

Ground Floor

 Main Entry & Hospital Operations  Rehabilitation & Aged Care Inpatient

Units

 Adult Mental Health Rehabilitation Unit

 Adult Mental Health Day Service

 Clinical Technology & Equipment

Service

 Aged Care and Rehabilitation Day/

Community/ Ambulatory Services

Hydrotherapy

Pharmacy

 Pathology  Communication Rooms

 Support Services/ Front of House (ACT Records Management; Switch & Mailroom;

Security, Fire Safety & Transport)

First Floor

 Executive Offices

 Education, Research & Meeting Facilities

 Central Staff Workspace

7.1.4. Design Features

A key aspect of the arrangement of the patient bedrooms is the provision of a pleasant outlook over courtyard spaces, some of which have been contained, either as part of the arrangement of the IPU’s, or as more intimate spaces attached to clusters of bedrooms, as is the case for the

Adult Mental Health Rehabilitation Unit.

As many of the patients will be undergoing treatment and rehabilitation programs over extended periods of time, it is important to provide environments that will accommodate rest breaks, as well as for the extension of exercise programs through use of outdoor areas.

The courtyards are intended to provide these benefits, as well as to provide access to natural light, fresh air and a natural landscape amenity that provides an alternative environment to that within. These spaces will also assist in reducing stress for both patients and staff.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 25 / 37

Wayfinding is intuitive and logical. Upon entering the building the main reception, passenger lifts and stair to the first floor are immediately apparent. Progressing further into the main entry foyer space, adjacent the reception a main corridor provides access to the Day Service areas, as well as other support service functions.

Progressing further into the facility, Pathology and Pharmacy Services have connections directly off the main entry zone, as does the Adult Mental Health Day Service. The circulation spine then continues, providing public access to the IPU’s beyond. This corridor has been provided with a slight curvature to visually reduce its length and avoid a ‘gun-barrel’ effect. It has been provided with fenestration at various points along the journey to further break the apparent length, provide visual interest with courtyard outlooks, and introduce natural light for the benefit of patients, staff and visitors.

Shared therapy areas are a key feature of the design, providing facilities directly accessed by an IPU on each side, as well as having connection to the main corridor spine for use by the wider UCPH community. Facilities within each shared zone include a gymnasium, ADL bathroom and kitchen, meeting rooms and consult rooms. The exercise/ mobility courtyard is accessible directly from the Day/ Community/ Ambulatory Service and via the main corridor from the

IPU’s; this approach was endorsed by the ERG at the Preferred Option Review.

7.1.5. Terrain

The sloping terrain has informed the general arrangement of the facility. The design utilises the natural land slope and, through use of cut-and-fill, allows for the discrete location of support services at a lower ground floor level, thereby facilitating separate streaming of goods and services vehicular traffic from general public access traffic.

The main hospital facilities, including Day/ Community/ Ambulatory S ervices, IPU’s and clinical support services , are located at natural ground level along the central spine, with IPU’s on each side being located either within an excavated embankment zone, or on excavated fill.

The first floor level contains Education, Meeting and Research facilities and Executive and

Central Staff Workplace, thereby creating distinct separation of clinical areas from executive/ administrative and educational areas, while assisting in the potential for enhanced security containment after-hours. It affords an elevated outlook over the surrounding area, especially to

Lake Ginninderra to the west.

The sloping terrain assists in providing good drainage to and around the site.

7.1.6. Orientation

In order to obtain optimal Environmentally Sustainable Design (ESD) benefits, the arrangement of IPU wings typically runs east-west, thereby minimising heat loads on external walls and glare for occupants within. This provides for north-facing roofs, ideal for installation of solar-boosted hot water systems and photovoltaic panels to generate electricity. Sun-shading of windows is also more easily dealt with, typically with roof overhangs that block higher altitude summer sun, while enabling lower altitude winter sun to enter and provide supplementary heating.

7.1.7. Building Materials

Given the greenfield nature of the site and opportunities for valid view outlooks, much of the façade is intended to be glazed, this will be energyefficient glazing that will be either low ‘e’ to non-patient bedroom or non-clinical areas, or double-glazed with integral venetian blinds affording light, glare and privacy control, particularly to patient bedrooms. The remainder of the façade will be a combination of lightweight, energy-efficient panelling and masonry, depending on the location.

As much of the facility is single-storey, there are opportunities to apply less commercial-style construction techniques and obtain cost efficiencies. Roofs are proposed to be constructed

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 26 / 37

utilising steel roof trusses with insulated coloured metal deck roofing, incorporating a colour palette that reduces heat absorption.

7.1.8. Building Services

Services connections to the building are provided from utilities to the west and north-west, arriving at the lower ground floor level and being reticulated throughout the facility.

Chilled water service runs rise vertically to the roof over the main circulation spine, which will be constructed as a working platform, allowing for location of secondary plant such as condenser units to be positioned adjacent to the IPU or associated areas and reticulated into the roof zone of the IPU. Maintenance of equipment can therefore be undertaken with minimal disruption to

IPU or clinical spaces.

Vertical circulation is provided for by 3 back of house goods lifts capable of accommodating

AGV pallet deliveries and servicing lower ground and ground floor. One of the back of house lifts connects all 3 floors and would provide bariatric and bulky equipment capability. Two passenger lifts are located in the main entry foyer and provide service between the Ground and

First floors.

Supplementing the lift installations are stair connections providing support services/ back of house access between the lower ground and ground floors, as well as fire egress and communication stairs between ground and first floors. A public staircase adjacent to the retail café area provides connection from the main entry to the Education, Research and Meeting facilities on the First Floor.

7.1.9. Future Proofing

Expansion has been allowed for in a number of areas with 4 zones identified for a future IPU; an

Independent Living Centre (ILC), if it is determined that it will be located at UCPH; Education precinct; and Medical Imaging. All with the exception of Medical Imaging are located towards the main entry.

Support services connection to the future IPU is afforded through the provision of a short corridor extension of the ‘back of house’ corridor connected to the large bariatric and equipment service lift, thereby providing flexibility in the type of IPU that could be provided.

7.1.10. National Construction Code Compliance

National Construction Code, 2013 (NCC) requirements have been addressed throughout the

CMDP design process.

Island Plunge Bath

Due to the nature of services to be provided at UCPH, i.e. sub-acute rehabilitation including preparedness training for patients’ return into a domestic environment, the NCC requirement for an island plunge bath is deemed not appropriate as it does not reflect the majority of domestic situations. A bath located adjacent to the wall will be provided within each ADL bathroom to more appropriately reflect a domestic setting.

ACT Health have developed a letter supporting dispensation for inclusion of an island plunge bath, this letter will be available to support the next planning phase.

7.1.11. Concept Plans

High level departmental layouts have been provided in the appended CMDP plans for the purpose of confirming space allocation, departmental footprint arrangements, and access and egress routes.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 27 / 37

Review and associated feedback will be undertaken with UGs during the next phase of planning.

The appended CMDP plans do not reflect the increase in GFA following further consultation with HSPU, i.e. increase in medication/ utility room sizes and change from 40% to 60% single bed rooms in the rehabilitation and aged care IPUs.

7.2. Engineering Services

Engineering services concept reports have been prepared to provide a general description of each system, listing the relevant Australian Standards/ Codes and identifying the proposed systems arrangements.

A summary of the key features of the engineering services design is included within this section, for plans and further detail refer to the appended reports.

7.2.1. Structural and Civil

The key features of structural concept design are:

 The likelihood of encountering very hard rock increases as excavation approaches 4-5m depth, however, some high strength rock has been found at shallower depths in nearby suburbs, this item has been added to the master risk register

 The recommended method for site preparation is by cut and fill

 The final depth required for site preparation is to be determined during the next planning phase and following core drill sampling across the proposed site once the location is confirmed

 Foundations are proposed as pads on siltstone and short bored piers to natural bedrock

 Raft foundations have been proposed for structure over residual ground/ engineered fill

 Floor systems are proposed as a post tensioned banded slab subject to further design development during the next planning phase

The key features of the civil concept design are:

 Stormwater detention will be employed in accordance with Water Sensitive Urban Design principles

 Overland flow levels are to be set to maintain flows around the building

 A new road for services access proposed, this will require consultation with the local authority during subsequent planning phases, this item has been added to the master risk register

 Provision for a 70,000 litre rainwater collection tank

Refer appended Engineering Services: Civil & Structural report.

7.2.2. Hydraulics (incl. Sewer), Gas & Wet Fire Services

Initial correspondence with authorities was undertaken as part of site investigation reports

(UCPH Site Investigation Report from Brown Consulting), this included identification of the following infrastructure connections which have formed the basis of the concept design proposed for hydraulic, gas and wet fire services:

 The sewer connection point has been identified from the existing sewer manhole North

East of the Ginninderra Drive/ Aikman Drive intersection

 Cold water, fire hydrant and fire sprinkler supply is proposed to extend from the water main in the Southern verge of Ginninderra Drive

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 28 / 37

 Gas connection identified from the steel gas main at the corner of Ginninderra Drive and

Haydon Drive/ Baldwin Drive along the Southern verge of Ginninderra Drive to the site

The key features of the concept design are:

 Sewer and trade waste drainage systems – connections and discharge provisions have been identified with trade waste discharged to sewer drainage systems via grease arrestors; separate arrestors are to be provided for the hospital kitchen and retail café

 Water services reticulation – cold water and rain water booster pumps are proposed to be provided sized according to demand which will be determined during the next planning phase. Water filters are proposed for all incoming cold water supply including the rain water reuse system

 Hot water services – the concept design for reticulation has provided for a flow and return loop with Thermostatic Mixing Valves (TMV) to be provided

 Wet fire protection services

– the fire sprinkler system and fire extinguishers are to be provided in accordance with AS 2118.1 - 1999 and AS 2444-2001 respectively

 Gas Services

– the gas supply reticulation is proposed to extend to hot water plant, mechanical plant, kitchen, café and hydrotherapy pool; gas usage meters will be connected to BMS

 Drainage downpipes will be connected to provide rainfall harvesting to a 70,000 litre collection tank for landscape irrigation and hydrotherapy pool top up

 Hydrotherapy pool system requirements have been identified

Refer appended Engineering Services: Hydraulics (incl. Sewer), Gas & Wet Fire Services

Report.

7.2.3. Electrical, Security & Communications

The key features of the electrical concept design are:

 Authority Connections – a new high voltage feed is proposed to be brought in from

Aikman Drive which will follow the entry road and will then run along the Western side of the site into the sub-station. The communication infrastructure will be brought into the site also off Aikman Drive and will follow a similar path into the building as the high voltage service

 Electricity Supply – a three 1000kVA transformer chamber substation will be provided incorporating high voltage and low voltage switchgear to service the power supply requirements for the new building. The substations will be located within the lower ground area on the Western side of the site

 Electro Magnetic Interference (EMI) – to minimise the impact of EMI the main sources of interference such as substations, main switch room and diesel generators are to be located away from sensitive equipment. The reticulation of sub-main routes throughout the building will be through dedicated services risers and along corridors to avoid areas with sensitive equipment or where people will be present for long periods of time. Cabling between the sub-station, main switch board and generator will be in the lower ground floor slab to reduce EMI to occupied areas

 Diesel Generators – a new diesel standby generator, approximately 500kVA, is proposed to be provided to support the life safety and essential business critical loads for the building

 Uninterruptible Power Supply (UPS) – Centralised UPS systems will be adequately sized to accommodate the electrical capacity of the main communications room located on the

Lower Ground Floor

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 29 / 37

 Security – it is proposed that the facility will be provided with an electronic security system comprising access control, intruder alarms, duress alarms, CCTV system and intercom systems

 Nurse Call System – it is proposed that a new IP based nurse call system will be provided to accommodate the requirements of the development and incorporate three levels of call including nurse call, staff assist and emergency call

 Building Management System (BMS) – It is proposed that the major circuit breakers on the main switchboard/s are connected to the BMS to monitor energy usage and open/closed status. The power factor correction system, standby generator, UPS systems, lighting control and security systems are all proposed to interface with the BMS.

 Future Flexibility – in order to provide for future expansion the following spare capacity has been proposed:

The sub-station to have in built 20% spare capacity and space for an additional transformer

The main switch board to have spare capacity and space for additional 20% load and circuits

The sub-mains to load centres to have 20% spare capacity

The distribution boards to have spare capacity and space for additional 20% load and circuits

The standby generator to have 20% spare capacity

Refer appended Engineering Services: Electrical, Security, Communications Report.

7.2.4. Vertical Transportation

The requirements for vertical transportation for passenger lifts, patients, goods and services have been identified as:

 Two passenger lifts linking the ground floor and first floor level

 Two staff/ goods lifts linking the lower ground and ground floor

 One bariatric rated lift linking all three levels

All goods lifts will have capacity to accommodate hospital beds and future AGV.

Machine room-less drive lifts are proposed as the drive motor is placed within the lift shaft and avoids the need for a lift motor room.

The requirements for security, UPS and standby generator requirements have been identified.

Refer appended Engineering Services: Vertical Transportation Report.

7.2.5. Mechanical & Dry Fire (incl. Medical Gases)

The key features of the mechanical concept design are:

 Load Calculations – the report outlines the initial loads for the building and indicates the preliminary primary plant loads which are used for plant room sizing, riser sizing and preliminary costs

 Energy Source and Supply – the source of energy has been included. The primary plant is based on an electrical chiller and gas boiler installation. The location of plant is also detailed with central plant proposed

 Mechanical Plant – a description of each of the systems recommended to be installed has been given along with reasons for selecting the appropriate system and why other systems were not selected. Each system has been outlined in detail including:

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 30 / 37

Central Energy

Cooling shall be provided by high efficiency electrical chillers

Heat rejection shall be provided by cooling towers

Heating shall be provided by gas boilers

 Air handling plant is proposed to consist of:

Multi-zone Face & Bypass Variable Volume Ait Handling Units in the ward areas

Constant Air Volume where required for specialist areas

 Service Zones – the service zones for each department have been outlined and illustrated on floor plans which also show the location of air handling plant serving each zone.

 Medical Gases – the proposed medical gases are detailed with gas cylinder store requirements given. Details of Bulk Oxygen compound are also included.

 Future Flexibility – in order to provide for future expansion the following spare capacity has been proposed:

The proposed chiller plant has been sized for 20% inbuilt spare capacity and with plant room space for an additional chiller should it be required

The proposed cooling towers to match the chillers and to hence have 20% in built spare capacity, space has been allowed for an additional cooling tower

Boiler capacity has been proposed with 20% inbuilt spare capacity but with space for additional boiler modules should they be required

Refer appended Engineering Services: Mechanical & Dry Fire (incl. Medical Gases) Report.

7.2.6. Car Parking

Functional areas have been identified within the individual HPU briefs for the purposes of patient and equipment pick up and drop off. Detailed parking analysis does not form part of this

SDP.

8.

Programme

The cost plan for UCPH has been based upon the Integrated Master Programme dated 6

February 2013 with the key milestones identified in Table 6.

Table 6: Project Milestones

Date

June 2013

August 2013

September 2013

February 2014

February 2014

May 2014

February 2014

May 2014

August 2014

Event

Services Delivery Plan COMPLETE

Shortlist Principal Design Consultant

Appoint Principal Design Consultant

Preliminary Design Complete

Development Approval (DA) lodged

DA Approved

Tender Managing Contractor

Appoint Managing Contractor

Commence construction (Early Works)

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 31 / 37

April 2015

2017

Commence construction (Main Works)

Official opening

It is recommended that development of a detailed programme is undertaken as part of the next planning phase.

If there are any changes to the project milestone dates within the master programme the capital cost cashflow and recurrent cost analysis will need to be updated.

9.

Risk Analysis

A Project Risk Review was undertaken on 6 May 2013 and the Master Risk Register developed from the outcomes of the review. The risks identified have been assessed and mitigation measures undertaken during the SDP design development where possible.

In accordance with the Risk Management Strategy the appended UCPH Master Risk Register has been updated and reflects project risks identified during the course of the SDP development. The register should be used as a basis for further risk identification and mitigation analysis as the project progresses.

10. Environmentally Sustainable Design

10.1. Baseline Inclusions

Baseline guidelines identified in the ACT Health endorsed policies and procedures for ESD have been reviewed and relevant measures applied to the specific nature of the UCPH facility.

Inclusion of these ESD aspects is not intended for the purposes of achieving a Green Star rating for certification.

Table 7 summarises the ESD initiatives that have been incorporated in to the CMDP and subsequent cost estimates.

Table 7: ESD Baseline for Capital Cost Estimate and Recurrent Cost

Item

Architectural

Mechanical

Comment

Orientation on site – to minimise heat loads on external walls and glare for occupants within

North facing roof – suitable for solar-boosted hot water and photovoltaic panels for electricity generation

External double glazing with integral blinds prevent solar gain in summer

Internal Noise Levels – minimised to promote a healthy environment

Material Selection – selection of construction materials to reduce VOC levels;

Formaldehyde Minimisation in the selection of construction materials

Ventilation Rates – increased levels of outdoor air during periods of high occupancy

Carbon Dioxide Monitoring and Control – control of outdoor air for spaces that have periods of low to no occupancy

Supply Air Duct Cleaning – access points to be provided to allow ductwork to be cleaned to promote a healthier environment

Variable Speed Drives to fans – to allow air flow to be set with minimum power losses

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 32 / 37

Item

Electrical

Hydraulic

Waste Management

Façade

Tenant Guide

Comment

BMS – to provide integrated measurement of the building utility usage and provide fault identification

High Frequency Ballasts – to reduce flicker and losses within lighting fittings

(Note: LED lighting likely to be used in final design)

Lighting Switching – occupancy sensors within spaces that have intermittent occupancy such as changing rooms and toilets

Light Fittings – selection of high efficiency light fittings

Rain water collection – to make use of rainwater for irrigation of landscaping

Landscape planting of native plants – to reduce the need for irrigation

Water efficient fixtures and fittings – low water usage taps and shower heads, dual flush toilets

Waste Management During Construction – waste management plan prepared by the contractor

Operational models include waste streaming and recycling

Roof overhang provides shade in summer and allows heat from sun to enter in winter, building envelope analysis to be undertaken during the next planning phase

Guide prepared to enable the tenants to operate the systems to meet the environmental performance

Environmental management plan prepared by the contractor Environmental

Management

Other Indoor Plants – to promote a healthy environment

10.2. ESD Options

Options for further investigation have been recommended for future consideration and incorporation in the UCPH project. These have been listed in Table 8 in descending indicative order of costs.

Detailed lifecycle costing of the asset including comparative analysis for inclusion of ESD initiatives is currently underway as a separate piece of work to the SDP.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 33 / 37

Table 8: Recommended ESD Options

Item

Mixed mode operation of the air conditioning and ventilation system

Comment/ indicative additional capital cost

Feasibility testing is recommended

A mixed-mode ventilation approach should be considered for areas of low sensitivity where suitable. The way in which a mixed mode system works is that during times when the external ambient conditions are not suitable for natural ventilation, the windows are closed and the spaces are ventilated and air conditioned with air being delivered into the space via air handling units, when ambient conditions are suitable for natural ventilation windows can be opened and the air conditioning to the space with the open window is switch off. The disadvantages with mixed mode systems, is that with open windows noise as well as dust can become a nuisance to occupants.

The diagrams included in the appended mechanical services report shows a mixed mode system in natural ventilation mode with the window open and the mechanical air conditioning switched off and mechanical ventilation with the window closed and the air conditioning switched on

Photovoltaic Cells Feasibility testing is recommended; the final cost would depend on the extent of the system adopted

Solar power contributes to reducing the building energy demand, and also makes a visible statement of involvement in renewable energy harvesting

Independent Commissioning Agent appointment

Independent commissioning agent provides a managed process of commissioning the systems by introducing an independent person whose sole responsibility is to plan, manage and monitor the testing and commissioning processes

Solar Hot water Feasibility testing is recommended; cost depends on extent of the system adopted

The development of a soft landing approach to hand over

A soft landing approach to hand over is an approach that engages with the users early in the completion phase of the project such that by the time they move into the facility they are already very familiar with the systems in place

Specific re-tuning of systems during the defects period and beyond

Re-tuning of systems during the defects period and beyond ensures that the systems remain operating in accordance with the design and adjustments are made to them periodically or when necessary to maintain efficient and effective operation

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 34 / 37

10.3. Other ESD Initiatives

The following additional ESD initiatives have been identified; however, these options are not recommended for further investigation for the proposed site due to cost or complexity, refer

Table 9.

Table 9: Other ESD Initiatives

Item

Geothermal Heating & Cooling

Comment

Geothermal cooling/ heating are an initiative where the mass and temperature of the ground is used to pre-treat air or heat/ cool water.

In the air systems a labyrinth is formed and outside air is passed through the labyrinth to pre-cool the air in summer and pre-heat the air in winter. These systems are expensive to construct and need careful design to ensure that the quality of the air does not de-grade as it passes through the labyrinth.

With the water system bore holes are drilled into the ground in an array with tubes installed into the bore holes. These holes are usually 100m deep with tubes spaced at 6000 apart. Water is passed down the tubes and the tubes manifolded into a header where the pipes are connected into a chiller cooling system or boiler heating system.

Use of lake water for cooling Using a water mass as a means of cooling chiller plant is common where the water mass is very close to the chiller plant. The water is passed through a series of filters, and is pumped through a heat exchanger. Chiller condenser water also passes through the heat exchanger where it is cooled before returning to the chiller. The benefit is a lower condenser water temperature and hence more efficient chiller operation.

11. Reference Documents

The following documents have been referenced in the development of the SDP:

 Proposed Northside Subacute hospital Canberra, ACT: Report from Subacute Hospital

Planning Workshop, held 9 th November 2012 Christopher J Poulos, 4 January 2013.

“Poulos Report”

 Northside Subacute Hospital Mental Health Services Consultation Report (August 2012).

 Proposed Northside Subacute Hospital Canberra, ACT: Service Models and Projected

Service Demand for Adult Rehabilitation and Aged Care, Christopher J Poulos, 9 October

2012.

 Adult Mental Health Day Service, National Health Reform Steering Committee Agenda

Item 3, 6 February 2013.

 Northside Sub-acute Hospital Workshop 1 Final Summary Report, 22 March 2012.

 Northside Sub-acute Hospital Rehabilitation Mental Health Services Workshop Final

Summary Report, 2 May 2012.

 Northside Sub-acute Hospital Adult Mental Health Services Workshop Final Summary

Report, 2 May 2012.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 35 / 37

 Northside Subacute Hospital Older Person’s Mental Health Services Workshop Final

Summary Report, 2 May 2012.

 University of Canberra 2012 Campus Master Plan, University of Canberra, 2012.

 University of Canberra Public Hospital Site Investigation Report Draft V2, Brown

Consulting, 1 March 2013.

 Office and Service Facilities Accommodation Policy, ACT Health Service and Capital

Planning, Issued August 2012 (Doc Number DGD12-020).

 ACT Health ICT Strategy Document (under development).

 Digital Health Enterprise Strategy 2 (DRAFT).

 ACT Health Sustainability Strategy Final Report, Thinc, May 2010.

 ACT Health Sustainability Strategy, July 2010.

 ACT Health Sustainable Energy Policy, Energy for a Sustainable City, ACT Government

Environment and Sustainable Development, 2011-2020.

 Weathering the Change, Draft Action Plan 2, Pathway to a Sustainable and Carbon

Neutral ACT 2011-2060, Options Paper for Public Comment, ACT Environment and

Sustainable Development, Dec 2011.

 SUSTAINABILITY

– Environmental Principles and Guidelines, Building and Infrastructure

Projects, ACT Health

 Health Directorate Waste Management Policy, ACT Health Business and Infrastructure,

Issued September 2012 (Doc Number DGD12-031).

 ACT Health Waste Management Policy. V2.0, ACT Health Business and Infrastructure,

Issued November 2010 (Doc Number CED08-009).

 ACT Waste Management Strategy, towards a sustainable Canberra 2011-2025, reducing waste and recovering resources to achieve a sustainable, carbon-neutral Canberra, ACT

Government Environment and Sustainable Development, 2011.

 Infection Prevention and Control Unit (IPCU) Redevelopment and Building Requirements,

IPC Building Paper for Endorsement (MDL), ACT Health.

 Infection Control Principles for the Management of Construction, Renovation, Repairs and

Maintenance within Health Care Facilities, A Manual for Reducing the Risk of Health Care

Associated Infection by Dust and Water Borne Micro-organisms, 2nd Edition, Loddon

Mallee Region, Infection Control Resource Centre, 2005.

 ACT Health – Capital Asset Development Plan, Infection Control Principles, V5.0, Thinc

Health, 16 September 2009.

 Rapid Response Guidelines for the Manual Handling Management of the Extra Large/

Bariatric Patient Guideline, Canberra Hospital, V2.0, Issued January 2009, ACT Health

(Doc Number TCH09 ‐ 031).

 Acute Care of the Elderly Ward Canberra Hospital, Dementia Design Review Report, The

Dementia Centre, 17 April 2013.

 University of Canberra Public Hospital Executive Reference Group Terms of Reference,

ACT Health, Draft, November 2012.

 National Construction Code (NCC) – previously the Building Code of Australia

 New South Wales Engineering Services and Sustainable Guidelines (TS11), 2008

 Guidelines for Sustainability in Health Care Capital Works, 2010

 National Safety and Quality Health Service (NSQHS) Standards, September 2012

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 36 / 37

12. Qualifications and Limitations

Consultation with the ACT Planning and Land Authority and the Territory and Municipal

Services, Engineering Section for ACT Government were not able to be conducted during the time this SDP was developed.

There are items relating to Urban/ Town Planning, Roads and Traffic, Public Transport and

Stormwater that require addressing in the early phases of the next stage of the project.

To date the development of this SDP has been underpinned by the findings as noted in the Site

Investigation Report prepared by Browns Consulting dated February 2013. Consultation with these organisations will need to be undertaken in the early phases of the next stage of the project.

13. Recommendation

It is recommended that ACT Health proceed with subsequent planning and design activities and ultimately implementation of the UCPH project, utilising the SDP as guidance to inform the next phase of planning.

UCPH

– Services Delivery Plan – User Group Consultation - V 3

Page 37 / 37

Download