Automatic Impulse Voltage Routine Testing of Distribution Transformers Reprint L. Furrer S. Kurz M. Loppacher ISH 99 E 1-91 HIGH VOLTAGE TEST Automatic Impulse Voltage Routine Testing of Distribution Transformers L. Furrer, S. Kurz, M. Loppacher Haefely Trench AG Basel, Switzerland Abstract Distribution transformers are often produced by highly automated production lines. Overall factory throughputs for small transformers sometimes reach one unit per minute. This throughput requires a fully automatic impulse test system capable of generating and analysing an impulse every few seconds. In addition production information has to be integrated and verified by a host computer retrieving instantaneous pass / fail information from the impulse test system. High speed, high system reliability and correct pass / fail decisions are the challenges in implementing such an automated test system. In future sophisticated analysis tools such as coherence and transfer functions with tolerance bands could be implemented. This allows a further refinement of pass / fail decisions which have to be investigated. Introduction Distribution transformers are exposed in their daily operation to transient over-voltages: impulses, which are due to atmospheric lightning or switching operations. Field experience has shown that these transients have certainly the most strenuous impact on transformers’ insulation and cause perhaps approx. 50 % of all premature failures ! [1]. Thus the international standards have for a long time adopted impulse tests in their scope of tests. Depending of the rated voltage, lightning and switching impulse tests must be carried out on each terminal of the test object. Since 1993, the L.I. test has also become mandatory for distribution transformers being tested according to ANSI / IEEE standards. Especially US manufacturers are faced with the problem of testing each distribution transformer with impulse voltages (ANSI/IEEE Standard C57.12.90 [2]) to check the manufacturing quality. Often running 3 shifts and 7 days a week, special features are required from the production line test equipment.. To meet these requirements, Haefely Trench AG has developed and delivered customised test systems designed to meet these specifications. A particular emphasis has been laid on the high transformer throughput rate, integration of state of the art software tools and efficient communication between the customer’s production line and the test system. Automatic impulse test system An automatic impulse test system for performing the complete impulse voltage test on distribution transformers (block diagram see figure 2) has to fulfil the following requirements [3]: • • • • • Figure 1 Distribution transformer (400 kVA, 20 kV ; from TESAR) • • • • • Long life expectancy Lowest cycle time Lowest maintenance Automatic report & test certificate generation Customised design according to client’s specification and applicable standards Integration into manufacturing chain Automatic calibration feasibility [4]. Safety features Design suitable also for unskilled operators Possibilities for off-line-analysis of faults [5] Test Object Charging Rectifier Impulse Generator Divider V A Shunt mm Impulse Measuring System Control Unit H.V. Connections Test System Control and Measuring Connections Data Exchance Connections Pass ü Fail û Handling Device Figure 2 Chopping Gap : Host Computer Automatic impulse voltage test system - block diagram Figure 3 shows an impulse voltage test system that fulfils the above mentioned requirements (total charging voltage 300 kV / 15 kJ). A powerful charging rectifier, a fast sphere gap drive system and resistors with a high energy receptivity allow to reach a cycle time between 3 10 seconds between the single impulses. A special design of the components grants a continuous operation of the system 24 hours per day over years with minor maintenance inbetween. The control and measuring systems are customised and prepared for integration into the production line (figure 4). A design with a central host computer allows off-line analysis of the measurements on test objects with faults. Network connections enable the integration into quality systems. Figure 3 Impulse voltage generator with charging rectifier and divider Test Procedure According to the standards, the basic method for judging the results of impulse tests is the comparison between 2 test wave shapes, a reduced and a full level impulse. Figure 5 shows a typical test procedure for a comparison measurement on distribution transformers. The test object has to be identified (e.g. scan of a bar code), the control system inquires test levels, tolerances and pass-fail criteria from a database for the impulse set-up. At first a reduced level Figure 4 Control and measuring system Host Computer/ Control System Measuring System Action Start Setup for 50% BIL impulse Charging/ Trigger for 50% BIL imp Setup for 50% BIL impulse U, i measurement/storage Upeak50 ; tfront; ttai l; ipeak50 within tolerances No Failed message A/B/C or D Yes Setup for 100% BIL (using x) Charging/ Trigger for 100% BIL imp. calculation of efficiency factor x U, i measurement/storage Upeak100 ; tfront; ttail; ipeak100 within tolerances No Failed message E/F/G or H No Failed message I Yes calculation of voltage normalisation factor y impulse will be generated (e.g. 50%). Records of voltage and currents are taken. A check of the wave shape regarding tolerances is performed. The efficiency is calculated, a correction factor is used for the calculation of the charging voltage for the full level impulse test. After the wave shape check of the full level impulse a normalisation and difference calculation of voltage and current traces is carried out. The differences are the criteria for the pass or fail decision. Pass / Fail Analysis At present the maximum difference for voltage and current record are the relevant quantities for pass / fail decisions. The sensitivity to failures is generally different for beginning, centre and end of a voltage or current record, the same is valid for the sensitivity to disturbances. For those reasons it is in most cases wise to select a certain time window where the sensitivity is optimal for fault detection and minimal for influences of disturbances. A typical comparison of a 50% with a 100% L.I. measurement is shown in Figure 6. normalization of 50% impulse voltage shape (using factor y) diff.calculation U100 - U50*y (for a spec.time window) Upeak diff < 3% of BIL Yes normalization of 50% impulse current shape (using factor y) Figure 6 diff. calculation i100 - i50*y (for a Comparison of L.I. 50% with 100% showing both impulses and the maximum deviations numerically spec. time window) ipeak diff.<10% of (i peak50*z) No Failed message J Yes Passed message storage of shapes U, i (50 and 100% impulse) next DUT Figure 5 Automatic impulse voltage test - flow chart Up to now pass / fail analysis are mostly performed by comparison of measurements recorded with the same impulse shape but different voltage level. Such a comparison is sensitive to voltage non-linearities of the test object. An example for such a non-linearity would be an internal "flashover" occurring at 75% B.I.L.. This failure is not effecting the 50% but strongly effecting the 100% amplitude measurement and therefore leading to nonlinearities - clearly visible in the normalised difference calculation. Reporting Depending on customers requirements reporting is performed very detailed for all transformers or just a pass / fail list is printed. Failed transformers are often of higher interest as knowledge about the actual occurring errors can help the manufacturer to improve his production accordingly. However quality standards nowadays require detailed documentation which might in future lead to more detailed reports in general. An example of a distribution transformer test report is given below (figure 7). tool for fully automatic transformer testing. Still though field experience is required and reliability has to be checked before implementing this tool. Conclusions Fully automatic impulse voltage test fields suitable for high throughput production lines have been implemented successfully. The required throughput, reliable pass / fail decisions and - most important - the desired reliability has been reached. Several of these automatic test systems are continuously in operation for months generating and analysing thousands of impulses without interruption. References [1] [2] [3] [4] [5] Figure 7 Example of a fully automatic test report. Shown are for all three phases the two voltage recordings, the voltage difference and the current difference calculation. [6] Outlook Insulation faults generally also show a very specific behaviour in the frequency domain for which sophisticated analysis tools are available. For large power transformer testing Transfer Function [6] and Coherence Function [7] analysis have become well accepted already. However the judgement of differences between two Transfer Functions is still requiring skilled people and, so far, is not ready for automatic testing. A Tolerance Band Method for the Transfer Function [8] might allow using this [7] [8] D. Ballard; „Routine Impulse Testing on Distribution Transformers“; High Voltage Seminar 3rd October 1995 ANSI/IEEE Standard C57.12.90 A. Claudi; „Neue Entwicklungen in der Impulsprüftechnik“; Haefely Symposium 1998 A. Claudi, J. Schramm; „Calibration of Digital Impulse Measuring Systems “; Paper 53.02; 8th International Symposium on HV Engineering, Yokohama; Japan, 1993 R. Malewski, K.Feser, A. Claudi, E. Gulski; „Digital Techniques for Quality Control and In-Service Monitoring of HV Power Apparatus“; Paper 15/21/3303, International Conference on Large High Voltage Electric Systems; CIGRE; Session 1996; Paris; France; 26.8.30.8.1996 R. Malewski; B. Poulin; „Impulse testing of power transformers using the transfer function method“; IEEE Transactions on Power Delivery Vol. 3; No. 2; April 1988 R. Malewski; A. Claudi, Ch. Josephy; St. Jud; „Checking electromagnetic compatibility of a HV impulse measuring circuit with coherence functions“; ERA Technology Conference H.V. Measurements and Calibration; Arnhem, 1994 T. Leibfried; K. Feser; „A new Method for Evaluating Transfer Functions of Power Transformers“; 10th International Symposium on HV Engineering, Montréal; Canada 1997 Haefely Test AG High Voltage Test Division CH-4028 Basel/Switzerland Phone +41.61.373 41 11 Fax +41.61.373 49 12 www.haefely.com e-mail: sales@haefely.com HIGH VOLTAGE TEST