SECTION 23 0800 — COMMISSIONING — HVAC PART 1 - GENERAL 1.1 OWNER FURNISHED A. 1.2 See Section 01 9113 – General Requirements - Commissioning RELATED DOCUMENTS A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions. B. Section 01 9113 – General Requirements – Commissioning 1.3 SUMMARY A. The purpose of the commissioning process is to provide the owner/operator of the facility with a high level of assurance that the mechanical systems have been installed in the prescribed manner, and operate within the performance guidelines set in the Contract Documents. The Commissioning Authority shall provide the owner with an unbiased, objective view of the system’s installation, operation, and performance. This process is not i ntended to take away or reduce the responsibility of the design team or installing contractors to provide a finished product. Commissioning is intended to enhance the quality of system start-up and aid in the orderly transfer of systems for beneficial use by the owner. The Commissioning Authority will be a member of the construction team, administrating and coordinating commissioning activities with the design team, construction manager, subcontractors, manufacturers and equipment suppliers. 1.4 REFERENCES A. 1.5 See Section 01 9113 – General Requirements - Commissioning SCOPE A. 1.6 See Section 01 9113 – General Requirements - Commissioning HVAC SYSTEMS / EQUIPMENT, IF INSTALLED, INCLUDED IN THE COMMISSIONING PROCESS: A. Air Handling Units B. Energy Recovery Units C. Variable Air Volume Terminals D. Fan Powered Terminals E. Water Source Heat Pumps F. Propeller Unit Heaters G. Cabinet Unit Heaters H. Finned Tube Radiation I. Radiant Ceiling Panels 23 0800-1 HVAC COMMISSIONING J. Exhaust Fans K. Chillers L. Cooling Towers M. Boilers N. Hydronic Pumps O. DDC Control Systems P. Geothermal devices and equipment Q. Variable Refrigerant Volume devices and equipment R. Chilled Beam devices and equipment PART 2 - COMMISSIONING PLAN 2.1 COMMISSIONING PLAN DOCUMENT A. 2.2 See Section 01 9113 – General Requirements - Commissioning COMMISSIONING TEAM A. 2.3 See Section 01 9113 – General Requirements - Commissioning CONTRACT DOCUMENT A. 2.4 See Section 01 9113 – General Requirements - Commissioning COMMISSIONING MEETINGS A. 2.5 See Section 01 9113 – General Requirements - Commissioning MASTER FINDINGS LIST A. Commissioning Agent (CxA) conducts initial Field Installation Verification (FIV), Operational Performance Test (OPT), or Functional Performance Test (FPT) inspection. B. All findings from these inspections are documented and are posted to the master findings list and website within two business days. C. Construction Manager (CM) will regularly distribute findings list to contractors and will hold contractor accountable to: 1.) correct any items and/or 2.) provide electronic responses for each finding. D. Responsible contractor will correct finding(s) and provide written confirmation that the finding(s) have/has been corrected. If finding was not corrected, contractor provides written explanation. E. Commissioning findings’ status may be considered during the pay application approval process. Approval may be withheld due to unresolved findings and/or findings where written responses have not been provided. F. CM provides responses back to CxA. All responses are updated to the Master Findings List. 23 0800-2 HVAC COMMISSIONING G. Once written responses are provided for each finding, the CxA will re-inspect. The contractor will be back-charged at a rate not to exceed the CxA contract hourly rate for any finding(s) that was/were reported to have been resolved and that are found to be unresolved upon reinspection. H. Status will be tracked for each finding and the Master Findings List will be updated accordingly. I. Once all findings have been resolved and the job is completed, a Final Report will be generated and a final commissioning meeting will be held. 2.6 FIELD INSTALLATION VERIFICATION (FIV) / MANUFACTURER’S CHEC KLISTS A. The Commissioning Authority will complete the FIV for each piece of equipment prior to startup. B. The equipment manufacturers’ checklists must be completed by the installing contractor reviewed by the Commissioning Authority before start-up can commence. 2.7 START-UP A. Start-up of major HVAC systems will be witnessed by the Commissioning Authority. The appropriate contractors and/or manufacturer’s representative will be required on site to perform start-up. No system will be started until the appropriate FIV ’s have been completed. No system will be started until the Manufacturer’s checklists have been completed. Start -up will be performed according to the Manufacturer’s recommended procedures. The Commissioning Authority will visit the site to review completeness of installation in conjunction with progress meetings prior to starting HVAC equipment. B. 2.8 Construction team members involved in installation, fabrication, manufacture, control, or design of equipment are required to be present at the time of start-up. A factory-authorized technician will be on site to start equipment when required by the specifications. This will minimize delays in bringing equipment on line and expedite acceptable functional performance in accordance with the Owner’s Project Req uirements (OPR) and the Basis of Design (BOD). CONTROLS MONITORING A. Close monitoring of the Control Contractor’s progress will promote efficient coor dination of the TAB work. The DDC Contractor will be expected to submit point-to-point checklists verifying that his work has been completed and all systems are ready for TAB work and Functional Performance Testing. Programming and graphics will be surveyed by the Commissioning Authority for completeness and conformance with the Owner’s Project Requirements ( O PR), the Basis of Design (BOD) and the owner’s scheduling requirements. 2.9 TAB MONITORING A. The preliminary TAB report set-up will be reviewed prior to HVAC equipment start-up, in order to assure that the final TAB report format and content is acceptable. B. TAB work will be monitored so that any problems that prevent or hinder proper air and water balance can be addressed and corrected with minimal delays. By addressing these problems as quickly as possible, we can assure that functional performance testing and owner training will take place on schedule. C. A pencil copy of the TAB report will be reviewed prior to submission of the final TAB report. A TAB report approved by the Design Engineer of Record will be required before Functional Performance Testing can be carried out. The Commissioning Authority will visit the site during the TAB process as necessary to verify proper means and methods. 23 0800-3 HVAC COMMISSIONING 2.10 OPERATIONAL PERFORMANCE TESTS (OPT) AND FUNCTIONAL PERFORMANCE TESTS (FPT) A. The Commissioning Authority will perform OPT’s a nd FPT’s based on the Owner’s Project Requirements (OPR) and the Basis of Design (BOD). These tests will be completed for HVAC systems and subsystems. B. Each major system will be tested. A random sample of each subsystem will be tested. This will be coord inated and witnessed by the Commissioning Authority and the owner’s maintenance staff. Witnessing the FPT’s will serve as a compliment to the O&M Training. No OPT’s or FPT’s will be performed until the TAB report and the control contractor Point Installa tion Verification Checklists have been submitted and reviewed by the Commissioning Authority. C. 2.11 Off-season mode testing will be implemented as necessary to assure conformance with the Owner’s Project Requirements (OPR) and the Basis of Design (BOD). Installing contractors will be expected to participate as required by the project specifications. BUILDING TURN-OVER / OWNER ORIENTATION / USER TRAINING A. The Commissioning Authority will assist contractors to prepare, coordinate and review O&M manuals, working closely with each contractor to achieve specificity and completeness. B. The Commissioning Authority will review record drawings, working closely with each contractor to achieve specificity and completeness. C. Owner training will be coordinated with the assistance of the Commissioning Authority. The training will be provided by the installing contractor, or manufacturer’s representative, and witnessed by the Commissioning Authority. This training should include both classroom training and hands-on operational training. The owner may choose to videotape this training for future use. The Commissioning Authority will visit the site during the Turn-Over and Training period to assure that any on-going HVAC related problems are being addressed and corrected in a timely and efficient manner. D. The Commissioning Authority will assist the owner/user with warranty issues. E. The Commissioning Authority will assist in the coordination of off-season testing, calibrating, and servicing as specified in the contract documents. 2.12 WARRANTY REVIEW A. The Commissioning Authority will participate in an 11 th month walk-through to observe the operation of the HVAC system. This will include a review meeting with FMD, a discussion of warranty issues, energy usage, maintenance practices, usage changes, and chronic problems, as well as other issues affecting the owner and the operation of the HVAC systems. PART 3 - EXECUTION RESPONSIBILITIES OF HVAC EQUIPMENT / SYSTEM INSTALLER 3.1 A. The installing contractor in this division shall include in their quote the cost of participating in the commissioning process. B. Include requirements for submittal data (including partial load data), O&M data, and training in each purchase order or sub-contract. C. Assure cooperation and participation of specialty sub-contractors such as sheet metal, piping, refrigeration, and water treatment in commissioning activities. 23 0800-4 HVAC COMMISSIONING D. Assure participation of major equipment manufacturers in appropriate startup, training, and testing activities. E. Attend commissioning meetings scheduled by the Commissioning Authority. F. Assist the Commissioning Authority in system verification and performance testing. G. Prepare preliminary schedule for HVAC system inspections, O & M manual submission, training sessions, pipe and duct system testing, flushing and cleaning, equipment start-up, system verification, performance testing, and system completion for use by the Commissioning Authority. Update schedule as appropriate throughout the construction period. H. Complete System Verification Checklists and manufacturer’s pre -start checklists prior to scheduling startup of Domestic Hot Water equipment. I. Monitor and respond to the Master Findings List distributed by the Commissioning Authority in writing within five (5) business days in order to expedite corrective actions necessary to achieve design intent. Failure to respond in writing within five business days will result in contractor non-compliance and will warrant the provision of a seventy-two (72) hour notice to comply and/or back charge to the contractor for all necessary corrective work. Items that are reported to have been corrected but that are found not to have been corrected after a maximum of two re-inspections will result in a back charge to the responsible contractor for any subsequent reinspection that must be performed by the Commissioning Authority in order to verify that the corrective work has been completed. J. Notify the Commissioning Authority a minimum of two weeks in advance of scheduled system start-up. K. Update drawings to as-built condition and review with the Commissioning Authority throughout the construction process. L. Schedule vendor and subcontractor provided training sessions as required by project specifications. M. Provide written notification to the CM and Commissioning Authority that the following work has been completed in accordance with the project specifications, and that the equipment, systems and sub-systems are operating in accordance with design intent. 1. 2. 3. HVAC equipment including fans, air handling units, dehumidification units, ductwork, dampers, terminal devices, etc. Fire detection and smoke detection devices furnished under other divisions as they affect the operation of the HVAC systems. That BAS is functioning in accordance with design intent. N. Participate in the Functional Performance Tests as required to achieve design intent. O. Participate in the off-season mode testing as required to achieve design intent. P. Participate in O&M Training as required by project specifications. Q. Provide a complete set of as-built drawings and O & M manuals for review. The Commissioning Authority shall review the as-built drawings and O&M manuals concurrently with the design team. 23 0800-5 HVAC COMMISSIONING R. In the event that any portion of the work to be completed by the mechanical contractor is subcontracted, ensure compliance with the commissioning process on the part of any individual(s) performing that work. To that end, ensure that each sub-contractor is provided a copy of this specification. RESPONSIBILITIES OF TEST AND BALANCE CONTRACTOR (TABC) 3.2 A. Include cost for commissioning requirements in the contract price. B. Attend commissioning meetings scheduled by the Commissioning Authority. C. Submit the TAB procedures and preliminary TAB report to the Commissioning Authority for review at least two weeks prior to beginning TAB work. D. Notify the Commissioning Authority a minimum of two weeks in advance of scheduled TAB work. E. Provide partial, preliminary TAB Reports by phase, by building section, by system, or as required by the Commissioning Authority. F. Assist the Commissioning Authority in system verification and performance testing. G. Monitor and respond to the Master Findings List distributed by the Commissioning Authority in writing within five (5) business days in order to expedite corrective actions necessary to achieve design intent. Failure to respond in writing within five business days will result in contractor non-compliance and will warrant the provision of a seventy-two (72) hour notice to comply and/or back charge to the contractor for all necessary corrective work. Items that are reported to have been corrected but that are found not to have been corrected after a maximum of two re-inspections will result in a back charge to the responsible contractor for any subsequent reinspection that must be performed by the Commissioning Authority in order to verify that the corrective work has been completed. H. Participate in verification of the TAB report, which will consist of repeating any selected measurement contained in the TAB report where required by the Commissioning Authority for verification or diagnostic purposes. I. Participate in the Functional Performance Tests as required to achieve design intent. J. Provide sound and vibration testing where required to assist in diagnosis of areas exhibiting unacceptable levels of noise or vibration. K. Participate in the off-season mode testing as required to achieve design intent. L. Participate in O&M Training as required by project specifications. M. In the event that any portion of the work to be completed by the test and balance contractor is subcontracted, ensure compliance with the commissioning process on the part of any individual(s) performing that work. To that end, ensure that each sub-contractor is provided a copy of this specification. RESPONSIBILITIES OF TEMPERATURE CONTROL CONTRACTOR (TCC) 3.3 A. Include cost for commissioning requirements in the contract price. B. Assure cooperation and participation of specialty sub-contractors such as TAB and electrical wiring subcontractor in commissioning activities. C. Review control sequence and component selection for conformance with design intent. 23 0800-6 HVAC COMMISSIONING 1. 2. 3. 4. Verify Verify Verify Verify that specified safeties and interlocks have been selected. proper selection of control valves and actuators based on design parameters. proper selection of control dampers and actuators based on design parameters. that sensor selection conforms to design intent. D. Attend commissioning meetings scheduled by the Commissioning Authority. E. Provide the following submittals to the Commissioning Authority: 1. Hardware and software submittals. 2. Control panel construction shop drawings. Narrative description of control sequences for each HVAC system and subsystem. 3. 4. Schematics showing all control points, sensor locations, point names, actuators, controllers and where necessary, points of access. A list of all control points, including analog inputs, analog outputs, digital inputs and digital 5. outputs. Include the values of all parameters for each system point. Provide a separate list for each stand-alone control unit. 6. A complete listing of all software routines employed in operating the control system. Also provide a program narrative that describes the logic flow of the software and the functions of each routine and sub-routine. The narrative should also explain individual math or logic operations that are not clear from reading the software listing. 7. Hardware operation and maintenance manuals. 8. Application software and project applications code manuals. Panel and equipment insert documents. 9. F. Verify that specified interfaces provided by others are compatible with BAS hardware and software. G. Coordinate installation and programming of BAS with construction and commissioning schedules. H. Complete System Verification Checklists and manufacturer’s pre -start checklists prior to scheduling startup of HVAC equipment. I. Provide control system technician to assist during equipment startup. J. Monitor and respond to the Master Findings List distributed by the Commissioning Authority in writing within five (5) business days in order to expedite corrective actions necessary to achieve design intent. Failure to respond in writing within five business days will result in contractor non-compliance and will warrant the provision of a seventy-two (72) hour notice to comply and/or back charge to the contractor for all necessary corrective work. Items that are reported to have been corrected but that are found not to have been corrected after a maximum of two re-inspections will result in a back charge to the responsible contractor for any subsequent reinspection that must be performed by the Commissioning Authority in order to verify that the corrective work has been completed. K. Participate in the Functional Performance Tests as required by the project specifications as required to achieve design intent. L. Provide a control system technician to assist during verification and performance testing. M. Provide system modifications to achieve system operation as defined by the design intent. N. Provide support and coordination for TAB contractor. Provide all devices, such as portable operator terminals and all software for the TAB to use in completing TAB procedures. O. Participate in the off-season mode testing as required to achieve design intent. 23 0800-7 HVAC COMMISSIONING P. Participate in O&M Training as required by project specifications. Include training on hardware operations and programming. Q. In the event that any portion of the work to be completed by the temperature control contractor is subcontracted, ensure compliance with the commissioning process on the part of any individual(s) performing that work. To that end, ensure that each sub-contractor is provided a copy of this specification. END OF SECTION 23 0800 23 0800-8 HVAC COMMISSIONING