Project Name : University of Greenwich XCRI stage 2 project Version: 0.9 Date: 21 Nov 2011 JISC WORK PACKAGE Before completing this template please note: The Project Management Guidelines have detailed instructions for preparing project plans and work packages.. Please expand tables as appropriate. Fill in the information in the document header – project name, document version, and date. Text in italics is explanatory and should be deleted in completed documents. WORKPACKAGES 1: Project management 2: Implementation of XCRI-CAP with COOL-URI 3: Embedding collection and updating of XCRI information within existing procedures 4: Embed use of XCRI within external supply of programme information 5: Dissemination and engagement 6: 7: 8: 9: 10: Page 1 of 7 Document title: JISC Work Package Last updated: February 2011 Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Project Name: University of Greenwich XCRI stage 2 project Version: 0.9 Date: 21 Nov 2011 Workpackage and activity Earliest start date Latest completion date Outputs (clearly indicate deliverables & reports in bold) Milestone Responsibility Project start date: Jan 2012 Project completion date: Mar 2013 Duration: 15 months WORKPACKAGE 1: Objective: Project Management 1. Stage 1 project plan 31 Oct 2011 Report using JISC template 2. Stage 1 deliverables: JISC self-assessment framework 3. Stage 1 deliverables: stage 2 project implementation plan 4. Stage 1 completion report 21 Nov 2011 Completion of JISC on-line questionnaire 21 Nov Report using JISC template 30 Jan 2012 Report using JISC template 5. Update and amend stage 2 project implementation plan 6. Set up an UoG XCRI website 29 Feb 2012 Revised XCRI stage 2 Project Implementation plan XCRI webpage with blog, capable of being consumed by an RSS feed Minutes of XCRI Project Board 29 Feb 2012 7. Meetings of XCRI Project Board every 6-8 weeks On going 8. Attend JISC programme meetings and on-line events On going Page 2 of 7 Document title: JISC work package template Last updated: February 2011 Report backs to XCRI Project Board, documented in the minutes Report submitted 28 Oct 2011 19 Oct 2011 21 Nov 2011 Meetings held: 19 Oct 2011 9 Nov 2011 Meetings attended: 16 Sep 2011 26 Oct 2011 28 Oct 2011 14 Nov Project Manager XCRI Project Board Project Manager Project Manager Project Manager Project Manager Project Leader/ Project Manager Project Leader/ Project Manager Project Name: University of Greenwich XCRI stage 2 project Version: 0.9 Date: 21 Nov 2011 Workpackage and activity Earliest start date Latest completion date Outputs (clearly indicate deliverables & reports in bold) Milestone Responsibility 2011 9. First interim report to JISC 25 May 2012 Report using JISC template 10. Second interim report to JISC 24 Nov 2012 Report using JISC template 11. Final report to JISC Draft: 28 Jan 2013, Final version: 10 Mar 2013 28 Apr 2013 Report using JISC template Report using JISC template Project Manager Jan 2012 Mar 2012 Nov 2011 Jan 2012 Agreement documented in XCRI Project Board minutes Specification document XCRI Project Board SRS/IS/PAS Jan 2012 Mar 2012 Jan 2012 Mar 2012 Agreement documented in XCRI Project Board minutes Evaluation of result of ‘quick and dirty’ XCRI feed produced as part of stage1 Jan 2012 Appropriate timing to be agreed June 2012 XCRI Project Board SRS/IS/PAS/ XCRI Project Board Project Manager 12. Stage 2 completion report Project Manager Project Manager Project manager WORKPACKAGE 2: Objective: Implement an XCRI-CAP feed with a COOL URI 13. Reach agreement on the depth of information what will be included in the XCRI output 14. Create a list of all information needed for XCRI – CAP feed and annotate with existing source of the information 15. Agree a policy for electronic access from other systems within the organisation 16. Evaluating the coverage and quality of existing information and identify any gaps 17. Arrange workshop with Alan Paull and technical and semi-technical staff 18. Create XML envelope for the XCRI-CAP information, extended to some fields from the wider XCRI where appropriate Page 3 of 7 Document title: JISC work package template Last updated: February 2011 Workshop Software SRS/IS/PAS Project Name: University of Greenwich XCRI stage 2 project Version: 0.9 Date: 21 Nov 2011 Workpackage and activity Earliest start date Latest completion date Outputs (clearly indicate deliverables & reports in bold) Milestone Responsibility 19. Implement XCRI-CAP feed with a COOL URI June 2012 Sept 2012 Live XCRI feed IS 20. Agree policy on electronic access to information externally from other organisations and possible charging 21. Review the resulting XCRI-CAP information April 2012 Sept 2012 Agreement documented in XCRI Project Board minutes XCRI Project Board Sept 2012 Mar 2013 Review documented in XCRI Project Board minutes XCRI Project Board 22. Agree a strategy for embedding collection and updating of XCRI information in agreed procedures and frequency of update Jan 2012 Mar 2012 Agreement documented in XCRI Project Board minutes 23. Develop the detailed procedures required to collect and update XCRI information Jan 2012 June 2012 Updates to the Quality Assurance Handbook 24. Review working of new procedures after one complete cycle June 2012 June 2013 Review documented in XCRI Project Board minutes Learning and Quality Committee/ XCRI Project Board Learning and Quality Unit in consultation with Marketing / Learning and Quality Committee Learning and Quality Unit/ Learning and Quality Committee WORKPACKAGE 3: Objective: Ensure the sustainability of the XCRI project by embedding the collection and updating of XCRI information within agreed procedures Page 4 of 7 Document title: JISC work package template Last updated: February 2011 Project Name: University of Greenwich XCRI stage 2 project Version: 0.9 Date: 21 Nov 2011 Workpackage and activity Earliest start date Latest completion date Outputs (clearly indicate deliverables & reports in bold) Milestone Responsibility WORKPACKAGE 4: Objective: Embed the use of XCRI information in the external supply of programme information 25. Address the quality of programme marketing information in the light of the XCRI feed July 2012 Dec 2012 Review documented in XCRI Project Board minutes 26. Agree policy for use and update of XCRI information in website, prospectus etc July 2012 Dec 2012 Agreement documented in XCRI Project Board minutes 27. Implement use of XCRI information on website, prospectus etc Oct 2012 Mar 2013 Revised website, prospectus etc 28. Review use of XCRI information on website, prospectus etc Jan 2013 June 2013 Agreement documented in XCRI Project Board minutes Development and Communication s / XCRI Project Board Development and Communication s / XCRI Project Board Development and Communication s Development and Communication s / XCRI Project Board WORKPACKAGE 5: Objective: Dissemination and engagement 29. Publicise XCRI project within the university Page 5 of 7 Document title: JISC work package template Last updated: February 2011 On going Powerpoint presentations Articles Project Leader/ Project Manager Project Name: University of Greenwich XCRI stage 2 project Version: 0.9 Date: 21 Nov 2011 Workpackage and activity Earliest start date Latest completion date Outputs (clearly indicate deliverables & reports in bold) 30. Dissemination to the University of Greenwich’s collaborative partners 31. Workshop for University of Greenwich collaborative partners Jan 2012 Mar 2013 Presentations, articles Sept 2012 Mar 2013 32. Release of all non-proprietary deliverables via the project website and where appropriate to relevant repositories 33. Contact with other users of Sunguard Banner (who hold the same rights as University of Greenwich to source and derivative code) with a view to sharing code Sept 2012 Mar 2013 Training materials which can then be made available to the wider JISC community Software, reports Jan 2012 Mar 2013 Participation in user group forums Page 6 of 7 Document title: JISC work package template Last updated: February 2011 Milestone Responsibility Project Manager Project Manager IS / Project Manager IS / Project Manager Project Name: University of Greenwich XCRI stage 2 project Version: 0.9 Date: 21 Nov 2011 Workpackage and activity Members of Project Team: Name Christine Couper Katarina Thomson Emma Price Further members of the project team Page 7 of 7 Document title: JISC work package template Last updated: February 2011 Earliest start date Latest completion date Outputs (clearly indicate deliverables & reports in bold) Role Project Leader Project Manager Liaison with work within the Learning and Quality Unit TBC Milestone Responsibility