DALLAS-FORT WORTH INTERNATIONAL AIRPORT ADDENDUM NO. 1 TO THE REQUEST FOR BIDS Contract No. 9500540 Terminal B High Gates Electrification August 12, 2014 THE REQUEST FOR BIDS (RFB) FOR THE ABOVE IS HEREBY REVISED AS FOLLOWS: THIS ADDENDUM CONSISTS OF 68 PAGES (INCLUDING ATTACHMENTS). THE CONTRACT DOCUMENTS AND SPECIFICATIONS FOR THE ABOVE TITLED PROJECT ARE HEREBY AMENDED OR REVISED AS FOLLOWS: Item 1: The preliminary Commissioning Plan as referenced by Specification 01 91 00 – Commissioning, is attached (dated July 29, 2014). END OF ADDENDUM NO. 1 Terminal B High Gates Electrification Addendum No. 1 Contract No. 9500540 THIS PAGE INTENTIONALLY BLANK TERMINAL B HIGH GATES ELECTRIFICATION Preliminary Commissioning Plan Bid Phase Project No: 9500540 Permit Numbers: A14-158B Prepared for: Dallas/Fort Worth International Airport July 29, 2014 Swayzer Engineering, Inc. 3102 Maple Ave. Suite 450 Dallas, Tx 75201 Table of Contents Commissioning Plan ............................................................................................................................. 1 1.0 Overview ............................................................................................................................. 1 1.1 Abbreviations and Definitions ........................................................................................... 1 1.2 Commissioning Plan Purpose........................................................................................... 2 1.3 Commissioning Scope ...................................................................................................... 2 1.4 Commissioned Systems ................................................................................................... 2 1.5 Form ............................................................................................................................. 2 2.0 General Project Information .................................................................................................... 3 3.0 Design, Commissioning, and Construction Team Data ....................................................... 3 4.0 Roles and Responsibilities ...................................................................................................... 4 4.1 Role and Responsibility Descriptions and Explanations .................................................. 4 4.2 Team Members ................................................................................................................. 4 4.3 General Management Plan ............................................................................................... 4 4.4 General Role Descriptions ................................................................................................ 4 5.0 Commissioning Process.......................................................................................................... 5 5.1 Commissioning Scoping Meeting ..................................................................................... 5 5.2 Preliminary and Final Commissioning Plan Updates........................................................ 5 5.3 Site Observation ............................................................................................................... 5 5.4 Miscellaneous Meetings ................................................................................................... 6 5.5 Miscellaneous Management Protocols ............................................................................. 6 5.6 Progress Reports and Logs .............................................................................................. 7 5.7 Submittals and Documentation ......................................................................................... 7 5.7.1 Standard Submittals ............................................................................................. 7 5.7.2 Special Submittals, Notifications, and Clarifications ............................................ 7 5.8 Pre-functional Checklists, Pre-functional Testing, and Start-up Plan ............................... 8 5.8.1 Pre-functional Testing and Start-up Plan ............................................................. 8 5.8.2 Pre-functional Testing and Start-up Execution .................................................... 9 5.8.3 Deficiencies and Non-Compliance ....................................................................... 9 5.9 Functional Testing and Verification Development ............................................................ 9 5.9.1 Functional Testing Overview................................................................................ 9 5.9.2 Functional Testing Plan Overview .....................................................................10 5.9.3 Functional Testing Scope ..................................................................................10 5.9.4 Development Process ........................................................................................10 5.10 Functional Testing Execution........................................................................................11 5.10.1 Functional Testing Procedure Overview and Process .....................................11 5.10.2 Deficiencies and Retesting ..............................................................................11 5.10.3 Facility Staff Participation.................................................................................11 5.10.4 Sampling ..........................................................................................................11 5.11 O&M Manuals, Warranties, and Commissioning Record Book ....................................11 5.11.1 O&M Manual and Warranty Overview .............................................................11 5.11.2 Commissioning Record Book...........................................................................11 5.12 Owner Personnel Training and Orientation ..................................................................12 5.13Commissioning Cost Benefits Matrix .............................................................................12 DFW International Airport Project No: 9500540 Terminal B High Gates Electrification i Commissioning Plan Bid Phase Issued July 29, 2014 6.0 Summary Report .....................................................................................................................12 7.0 Schedule ...........................................................................................................................13 7.1 General Issues ................................................................................................................13 7.2 Project Schedule .............................................................................................................13 Table 7.0 Commissioning Process Schedule Summary ..........................................................13 Exhibit A: Cost Benefits Matrix ...................................................................................................16 Exhibit B: Cx Progress Record / Equipment Summary ............................................................18 Appendix 1: Form C-01 C-02 C-03D C-03E C-05C C-06 C-07 C-17 C-18 C-21 C-22 Sample Commissioning Application Forms .................................................20 Title Construction Issues Log / Issues Log Photos ...................................................21 Documentation Tracking and Control Log.........................................................23 Commissioning Request for Information ...........................................................25 Request for Information Log ..............................................................................26 Staff Training and Orientation Log ....................................................................27 Corrective Action Report ...................................................................................28 Commissioning Progress Record / Equipment Summary .................................29 Submittal Review / Submittal Review Log.........................................................30 Field Observations and Tests ...........................................................................32 Operation and Maintenance Manual and Warranty Log ...................................34 Pre-functional Checklist Review........................................................................35 Appendix 2: Form PFC-201 PFC-202 PFC-203 Sample Pre-Functional Checklists ................................................................36 Title Pre Functional Checklist – Ground Power Unit ...............................................37 Pre Functional Checklist – Pre Conditioned Air Unit .........................................42 Pre Functional Checklist – Condensate / Sump Pump .....................................46 Appendix 3: Form FPT-201 FPT-202 FPT-203 Sample Functional Performance Testing Procedures ................................49 Title Functional Performance Test – Ground Power Unit .......................................50 Functional Performance Test - Pre Conditioned Air Unit ..................................56 Functional Performance Test – Condensate/Sump Pump................................61 DFW International Airport Project No: 9500540 Terminal B High Gates Electrification ii Commissioning Plan Bid Phase Issued July 29, 2014 Commissioning Plan Project: Terminal B High Gates Electrification Contact: Ron Wesolak, DFW Airport PM Date: 7/29/14 1.0 Commissioning Plan Version Preliminary – DRAFT X Preliminary – Bid Phase Construction Phase Final Acceptance Phase Overview Fundamental Equipment Systems Commissioning Tasks: 1. Engage a Cx Agent 2. Review design intent and Basis of Design 3. Include Cx Requirements in construction documents 4. Develop and utilize a Cx Plan 5. Verify installation, functional performance, training and documentation for each commissioned system and/or component 6. Complete a Commissioning Report 1.1 Abbreviations and Definitions The following are common abbreviations used in this document. A/E CC CM Cx CxAg CxAu Cx Cord Cx Plan EC 1.2 - Architect & Engineer Design Team Controls Contractor Construction Manager Commissioning Commissioning Agent Commissioning Authority Commissioning Coordinator Commissioning Plan document Electrical Contractor FPT GC LC MC PFC PM SMC Subs TAB - Functional Performance Test General Contractor Louver Contractor Mechanical Contractor Pre-Functional Test Project Manager Sheet Metal Contractor Subcontractors Test and Balance Contractor Commissioning Plan Purpose The Commissioning Plan purpose is to provide clear and concise procedures for the commissioning process and to provide a record of the results of the commissioning process. It is a means of issue resolution, describes the roles of parties, means of reporting, means of approval, and coordination. The structure of this Commissioning Plan is a main body and appendices. The specific sections include: • Project and Contact Information: Proper communication is critical for the success of any project. This section lists the contact information for the commissioning team members. • Roles and Responsibilities: The roles and responsibilities of each commissioning team member are clearly defined in this section. The goal of this section is to have each individual understand what they must do and how they fit into the entire process. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 1 Commissioning Plan Bid Phase Issued July 29, 2014 1.3 • Communication Structures: The communication paths to be used by the commissioning team members are detailed in this section. • Commissioned Systems and Equipment: The commissioned systems include those that are in the commissioning authority’s contract. These systems were expanded using the drawings and specifications to develop a detailed listing of each type of equipment in each system to be commissioned. • Commissioning Process Description: This section provides a detailed description of the tasks to be accomplished during the commissioning process. Focuses specifically on what must be accomplished during the design, construction, turnover, and operation phases of the project. • Commissioning Process Schedule: there are specific sequences of events that must occur during the commissioning process. These events are detailed in this section. Appendices: The appendices present the information developed during the commissioning process. As work is completed, the results are added to the proper appendix and the status and date of the document are inserted into Exhibit B found on page 19 20. Commissioning Scope Commissioning is a systematic process ensuring equipment to be commissioned performs in accordance to the contract documents. For this project, this is achieved by beginning in the construction phase and continuing through the acceptance period with performance verification. The commissioning process is intended to achieve the following specific objectives in accordance with contract documents 1.4 • Ensure applicable equipment and systems are installed properly and receive adequate operational checkout by installing contractors. • Verify and document proper equipment and system functional testing. • Ensure O&M documentation is complete. • Ensure Owner’s operating personnel are adequately trained. Commissioned Equipment / Systems Table 1: The following equipment / systems shall be commissioned. Systems to be Installed Quantity to be Installed Ground Power Units / 400Hz-28v 12 PBB Pre-Conditioned Air Unit 6 Condensate / Sump Pump 12 1.5 Forms Commissioning (application) forms are referred to in this plan by: Form C-xx, where “C” represents Construction phase. Blank forms are found in Appendix 1 at the end of this document. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 2 Commissioning Plan Bid Phase Issued July 29, 2014 2.0 3.0 General Project Information Project Name: Terminal B High Gates Electrification Project Location: DFW International Airport Project Agency: Airport Development and Engineering Department Construction Period: TBD Design, Commissioning, and Construction Team Data Table 2: Team Data Team Member Company and Office / Cell, Fax, and E-mail Address Contact Names Owner DFW International Airport 3200 East Airfield Dr. DFW Airport, TX 75261-9428 Phone: 972-973-3112 DFW Airport Project Manager Ron Wesolak, PM ADE Building 3003 S Service Rd DFW Airport, Tx 75261 Parsons 1301 West President George Bush HWY Suite 350 Richardson, Tx 75080 Phone: Email: 972-973-1820 rwesolak@dfwairport.com Phone: 972-244-6000 Harold John Vetter II Agurirre Roden 10670 N. Central Expressway Dallas, Tx 75231 Jeff Gulrich Phone: 972-788-1508 Phone: Email: Phone: Email: Phone: Email: 972-973-6119 jgulrich@dfwairport.com 972-973-6162 sbelaye@dfwairport.com 972-973-6167 ramartinez@dfwairport.com Design Project Management Engineer Commissioning Authority Designee Shure Belaye Raul Martinez AM Building 3010 East Airfield Dr DFW Airport, Tx 75261 DFW Construction Manager General Contractor TBD Phone: Email: TBD TBD TBD Phone: Email: TBD TBD Commissioning Agent, Representative Michele Swayzer, P.E., QCxP Swayzer Engineering, Inc. 3102 Maple Ave, Suite 450 Dallas, TX 75201 Phone: Cell: 214-880-7929 214-878-7929 E-mail: michele.swayzer@swayzer.com DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 3 Commissioning Plan Bid Phase Issued July 29, 2014 4.0 Roles and Responsibilities 4.1 Role and Responsibility Descriptions and Explanations Role and responsibility descriptions and explanations are found in the following locations: Team Members: General Management Plan Outline: General Role Descriptions: A/E; CM; PM: General Contractor: Mechanical Contractor, TAB Contractor, Controls Contractor: Electrical Contractor, Communications Contractor, Security Contractor: CxAg: CxAu: Manufacturer’s Representative: 4.2 Cx Plan, Section 4.2. Cx Plan, Section 4.3. Cx Plan, Section 4.4. Cx Plan, Section 4.4. Cx Plan, Section 4.4. Cx Plan, Section 4.4. Cx Plan, Section 4.4. Cx Plan, Section 4.4 Cx Plan, Section 4.4 Cx Plan, Section 4.4 Team Members Commissioning team members consist of Dallas Fort Worth Airport Development and Engineering Department (ADE) personnel, Dallas Fort Worth Airport Energy, Transportation, and Asset Management Department (ETAM), CxAu, CxAg, PM, and CM assigned members. Also included are mechanical, electrical, and controls contractors, installing subcontractors and/or equipment suppliers. 4.3 General Management Plan Dallas Fort Worth Airport Development Department contracted the CxAg on behalf of Dallas Fort Worth Airport Development and Engineering Department (ADE). The CxAg coordinates commissioning activities and reports to the Dallas Fort Worth Airport Development and Engineering Department (ADE). All members work together to fulfill their contracted responsibilities and meet contract document objectives. 4.4 General Role Descriptions General commissioning role descriptions are: CxAg: CxAu: Coordinates Cx process, performs limited construction observations, identifies concerns and issues to A/E & PM, writes Cx plan; pre-functional checklists; and functional testing requirements and procedures, functional testing status record, oversees, and documents performance verification tests, and provides limited problem resolution assistance. Reviews and approves Cx Plan. As is the case, when need be, attends meetings. Reviews and approves Final Cx Report. CxAu Designee: Performs the function of the CxAu in their absence. PM: Facilitates and supports the Cx process, approves Cx work, and approves test plans. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 4 Commissioning Plan Bid Phase Issued July 29, 2014 CM: GC: A/E: Subs: Mfr.: 5.0 Facilitates Cx process, ensures Subs perform their responsibilities, and integrates Cx into construction process, schedule, and approves test plans. Responsible for and demonstrates proper system installation and performance (typically through the use of its installers, subs, and/or manufacturer. Performs construction observation, during testing a design issues may result in a request for information from the A/E. The A/E or Contractor provide written response to the CxAg listing their disposition on each issue and their planned actions, reviews, modifies and issues Cx Specifications, approves O&M manuals, and assists in resolving problems. Demonstrates proper system installation and performance. Equipment manufacturers and vendors provide documentation to facilitate commissioning work and perform contracted start-up services. Commissioning Process This section sequentially details the commissioning process by commissioning task or activity. The intent of this section is to document how the tasks are accomplished as part of the commissioning effort for this project. This information is prescriptive and stepwise in nature to focus the commissioning efforts on verifying the owner’s project intent has been met. 5.1 Commissioning Scoping Meeting (K/O) The CxAg conducts a commissioning scoping meeting prior to acceptance phase testing. Representatives of CxAg, CM, PM, A/E, MEP engineers and Subs should attend. The agenda shall be as follows: • • • • • • 5.2 Commissioning party introduction. Commissioning process overview. Preliminary Cx Plan overview. Management and reporting line overview. Roles and responsibilities. Proposed commissioning schedule. Preliminary and Final Commissioning Plan Updates The CxAg prepares the Preliminary Commissioning Plan prior to the Scoping meeting. The Commissioning Plan is then updated from information gathered from the scoping meeting and throughout the project. The initial commissioning schedule is also developed in Section 7. The commissioning schedule shall be adjusted as construction progresses. Prior to primary equipment start-up, the CxAg shall meet with CM and PM to develop a detailed commissioning schedule. The ETAM Cx Authority designees review and approve the final commissioning plan and report. 5.3 Site Observation The CxAg, PM, and selected DFW personnel make periodic site visits as necessary to witness equipment and system installations. As construction progresses and mechanical and electrical system installation activities increase; the CxAg may increase the frequency of site observations as required. A site observation report will provide an overview for each site observation. Observed deficiencies shall be documented on Form C-06, Commissioning Corrective Action Report, and tracked on form C-01, Construction Issues Log, Form C-06 shall be forwarded to the design team for coordination of system deficiency resolution with a copy being sent to the project manager. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 5 Commissioning Plan Bid Phase Issued July 29, 2014 5.4 Miscellaneous Meetings The CxAg attends selected planning and job-site meetings and shall provide meeting minutes thereof. The PM and CM provide the CxAg with information regarding substitutions, change orders, or any Design Change Notices (DCN’s) that may affect commissioned equipment and systems, or the commissioning schedule. The CxAg shall review construction-meeting minutes, or change orders, for the same purpose. The CxAg shall schedule commissioning team member meetings through the PM as required during construction. 5.5 Miscellaneous Management Protocols The following protocols shall be used on this project: Issue Protocol Requests for information (RFI) or formal documentation requests: The CxAg forwards to Design Team or CM as appropriate. Minor or verbal information and clarifications: The CxAg communicates to Design Team or CM as appropriate. Deficiency notification: The CxAg documents deficiencies through A/E, but may discuss deficiency issues with the CM prior to notifying A/E. Copies of deficiency reports shall be provided to PM. FPT’s or Training Scheduling: The CxAg may provide input for (and do some coordination of) training and testing, but does not schedule tests or training. Commissioning meeting scheduling: The CxAg coordinates date and schedules through PM and CM. Significant change requests: The CxAg has no authority to issue contract changes. Minor change requests: The CxAg may suggest (through PM to go to A/E for approval) changes in sequences of operations to improve efficiency or to control or correct deficiencies. Engineer approved changes shall be documented and forwarded to CM for modification by responsible subcontractor. Disagreements between contractors and CxAg’s requests or interpretations: First works with CxAg. Second through CM. The CM shall work with CxAg directly or through PM for resolution as required. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 6 Commissioning Plan Bid Phase Issued July 29, 2014 5.6 Progress Reports and Logs The CxAg provides PM with periodic commissioning progress reports. Progress report frequency may be increased to twice per month, as necessary, just prior to initial major equipment start-up and continuing until functional testing is complete and all non-compliance issues are resolved. Progress reports contain: • Schedule update with requested schedule changes and newly scheduled items. • New and outstanding deficiency list described on Form C-06, Commissioning Corrective Action Report and tracked on form C-01, Construction Issues Log. • Commissioning progress that may include Form C-07, Commissioning Progress Record / Equipment Summary. The CxAg regularly communicates with commissioning team members keeping them apprised of outstanding issues, commissioning progress, and scheduling through memos, progress reports, etc. The CxAg maintains all commissioning related materials to become part of final commissioning report. 5.7 Submittals and Documentation 5.7.1 Standard Submittals The CxAg provides subcontractors responsible for commissioned equipment and systems with respective commissioning documentation requirements through the CM and PM. Subcontractor documentation submissions typically coincide with the Engineer submittal process. At a minimum, documentation submissions shall contain: • Manufacturer’s installation instructions. • Start-up and checkout procedures. • Operation and Maintenance data. • Performance data. • Control drawings. • Sequence of Operations The CxAg reviews commissioning related submissions specified in contract documents. Form C-02, Documentation Tracking Control Log, shall be used to track documents. Form C-02 shall also be used for part of the final O&M documentation review checkoff. 5.7.2 Special Submittals, Notifications, and Clarifications Sub-contractors, CM, or A/E shall notify CxAg within one week of approval of any design intent or operating parameter changes, commissioned system changes, added control strategies and operation sequences, or other change orders that may affect commissioned systems. The GC provides CxAg with a complete points list including details requested by CxAg. Thirty (30) days prior to performing any applicable DFW-contracted tests, the sub’s must provide CxAg with full procedural details. These submittals do not constitute O&M manual submittal compliance. O&M manual documentation requirements are discussed in Commissioning Plan, Section 5.11. The CxAg may request additional design narrative clarification from A/E and/or the Contractor depending on completeness of original bid documents. The CxAg may submit written RFIs to contractors through CM using Form C-03D, Commissioning Request for Information. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 7 Commissioning Plan Bid Phase Issued July 29, 2014 5.8 Pre-functional Checklists, Pre-functional Testing, and Start-up Plan Pre-functional checklists (PFCs) augment and are combined with manufacturer’s installation instructions, start-up instructions, and checkout plans. PFCs help to document that systems have been installed and operate in accordance with contract documents and manufacturer’s recommendations and to ensure functional testing proceeds with minimal delays. Responsible contractors must fill in each commissioned equipment and system pre-functional checklist. No pre-functional testing sampling strategies shall be used. System pre-functional testing must be successfully completed prior to formal respective equipment, subsystem or assembly functional testing. PFCs are primarily static inspections and procedures to identify installation requirements, equipment, or system initial operation requirements (e.g., light levels OK, labels affixed, gages in place, sensor Calibration, etc.). However, some pre-functional items entail simple testing of component function, equipment, or a system piece (such as measuring voltages on a 5-step constant current regulator). As the term implies, “pre-functional” testing refers to testing that takes place prior to functional testing. Contractors perform all pre-functional items recommended by CxAg as part of start-up. This project requires written documentation of the installing contractor’s procedures. The CxAg witnesses selected pre-functional testing and start-up procedures and some spot-checking thereof. The intent of these checklists is to verify the proper equipment was delivered prior to acceptance. If problems are not identified at this stage, then schedules and budgets are often compromised for both the owner and contractors. There are system-based (ductbanks, cabling, etc.) and component-based (light fixtures, CCR’s, etc.) installation checklists. System-based check lists are developed to be used regularly on the systems for which work is on-going, and component-based checklists are separated based on the task being completed (e.g. hanging the box, hooking ductwork up, etc.) and are to be completed during a particular installation step. Pre-functional checklists are provided in Appendix 2 at the end of this document. 5.8.1 Pre-functional Testing and Start-up Plan The CxAg assists commissioning team members to develop detailed equipment pre-functional testing and start-up plans. Responsible parties are identified in Form C-07, Commissioning Progress Record / Equipment Summary, and in PFCs. The following procedures shall be used: 1. The CxAg obtains manufacturer’s installation instructions, start-up instructions, and checkout plans, along with field technician checkout sheets from CM. Contractors shall provide supplemental detail and documentation to CxAg for systems with inadequate manufacturer’s start-up and checkout procedures, particularly components integrated with other equipment. 2. The CxAg develops a pre-functional checklist for each equipment piece from these materials. 3. Pre-functional checklist, manufacturer’s installation instructions, start-up instructions, and checkout plans along with field technician checkout sheets become the Start-up and Checkout Plan. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 8 Commissioning Plan Bid Phase Issued July 29, 2014 4. The CxAg transmits the complete Start-up and Checkout Plan to the CM, who designates which trade or contractor is responsible to fill out each line item as indicated in the “Contr” column on the PFC form. The CM then transmits the full start-up plan to Subs for their review and use. (This usually means PFCs, alone, goes to more than one Sub, while the full plan goes to the primary installing contractor.) 5.8.2 Pre-functional Testing and Start-up Execution Subs and vendors schedule pre-functional testing and start-up with PM, CM, and CxAg four weeks prior to execution. Pre-functional testing and start-up are directed and executed by Subs and/or vendors. The CxAg, assisted by selected Owner Staff and PM, if necessary, observes selected pre-functional testing and start-up procedures. To document pre-functional testing and start-up processes, site technicians performing line item tasks initial and date each pre-functional checklist paragraph, start-up plan, and manufacturer’s field checkout sheets. Only individuals having direct knowledge of a line item being completed shall check and initial forms. Subs and vendors execute and submit signed pre-functional checklist and start-up tests to CxAg for approval/acceptance. The CxAg may review pre-functional testing in progress. Each responsible trade shall fill out their portion of the pre-functional checklist form and provide them to CxAg through CM. The CxAg and/or selected Owner’s Staff may conduct spot-checks of completed forms. 5.8.3 Deficiencies and Non-Compliance Subs must clearly identify incomplete start-up and pre-functional checklist items at bottom of procedure form or attach sheets as required. The procedure form and deficiencies must be provided to CxAg within 7 days of test completion. The CxAg works with Subs and vendors to correct deficiencies or incomplete items and retest, involving CM and others as necessary. Installing Subs or vendors correct deficient or incomplete areas according to checklists and tests. The CxAg completes Form C-7, Commissioning Progress Record, to recommend system start-up approval and forwards it to PM. The CxAg records all issues/deficiencies on Form C-01, as well as tracking of the cost benefits of commissioning. 5.9 Functional Testing and Verification Development The CxAg uses a formal acceptance phase for use in the commissioning process that helps to facilitate the closeout of a project and helps minimize problems upon occupancy. The two items that are critical to this phase is the completion of functional testing and the completion of additional training. 5.9.1 Functional Testing Overview Functional testing is equipment and system dynamic testing under all specified operation modes in lieu of individual system components (e.g., associated airfield lighting fixture is tested interactively with airfield lighting controls to verify consistent performance under various conditions). Systems shall be tested under various modes in accordance with industry established test procedures, such as low or high load, component failure, unoccupied mode, varying outside air temperatures, fire alarm, power failure, etc. Equipment and system responses to all specified operation sequences shall be verified. The CxAg develops functional testing procedures in a sequential written format and coordinates, oversees, and documents installing contractor and/or vendor performed testing. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 9 Commissioning Plan Bid Phase Issued July 29, 2014 5.9.2 Functional Testing Plan Overview and Status Record The CxAg prepares the functional testing schedule and to integrate functional testing into the construction schedule. The CxAg will identify testing prerequisites, required contractors, and estimated time required for each test. The CxAg shall record results during functional testing. 5.9.3 Functional Testing Scope The following equipment / systems shall be commissioned. 1. 2. 3 Ground Power Units Pre-Conditioned Air Units Condensate / Sump Pumps Sample functional performance testing procedures are presented in Appendix 3 at the end of this document. Table 3. List of Systems and Equipment to be Commissioned by the General Contractor (GC). GC to provide Qualified Personnel to commission equipment identified. Pre-functional Checklists and Functional Tests shall be provided to the GC for review and completion prior to scheduling functional tests. See items below. Reviews Checklists Cx’ed System Electrical Equipment Included Ground Power Units - HVAC Pre- Conditioned Air Units - Mech Condensate / Sump Pumps - * NC Represents items not completed to date and “C” represents items completed ** FPT Functional Performance Test 5.9.4 Design Spec Submtl Sys Equip Field Review FPT ** Development Process Before writing testing procedures, the CxAg shall obtain all required documentation and change orders affecting commissioned equipment and systems, including updated points list, control sequences, and set points. The CxAg shall develop specific testing procedures to verify proper operation of all equipment and systems listed in the Commissioning Plan and Specifications. The CxAg shall obtain additional clarification from contractors and/or the Engineer regarding operation sequences as required. Prior to functional testing execution, the CxAg shall provide a copy of equipment, and systems functional testing forms to the PM, who forwards them to installing Subs through the CM. The subs review tests for feasibility, safety, warranty, and equipment protection. Blank test procedure copies are included in O&M manuals for later use by facility operation staff. Functional testing and verification may be performed manually in accordance with FAA, State and Regulatory Guidelines or by manipulating equipment and observing performance. The CxAg follows the specified test procedures when given and uses discretion when test procedures are not given to determine which method is most appropriate. The CxAg reviews Owner-contracted and factory required tests where applicable to determine if further testing is required for specification compliance verification. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 10 Commissioning Plan Bid Phase Issued July 29, 2014 5.10 Functional Testing Execution 5.10.1 Functional Testing Procedure Overview and Process The CxAg schedules functional testing through PM and CM. Prior to performing any equipment or system functional testing, the CxAg obtains PFCs with signatures confirming systems are ready for functional testing. The CxAg oversees, witnesses, and documents all equipment and system functional testing according to Cx Specifications and Plan. The Subs execute tests, unless otherwise specified. Testing proceeds from components, to subsystems, to systems, and finally to system interlocks. Refer to Commissioning Plan, Section 5.9 for additional functional testing scope details. 5.10.2 Deficiencies and Retesting Minor deficiencies discovered during functional testing may be corrected during testing at the CxAg’s discretion. The CxAg records test results on the functional testing procedure form. Deficiencies and non-compliance issues are noted and reported to CM and PM on Form C-6, Commissioning Corrective Action Report. Subs correct deficiencies, notify CxAg of correction, and return Form C-6 certifying correction. The CxAg schedules re-testing through the CM. Decisions regarding deficiencies and corrections are made between CxAg or CM and Sub. Primary dispute resolution authority resides with the Owner followed by the Engineer. The CxAg recommends test acceptance to CM who gives final approval for each test using Form C-22, Pre-functional Checklist Review. Form C-07, Commissioning Progress Record / Equipment Summary, is provided for progress tracking and status. 5.10.3 Facility Staff Participation DFW personnel may/shall assist the CxAg in facilitating and participating in the testing process, e.g. Facility Maintenance may provide access to equipment rooms for testing. The CxAg shall notify the PM, who shall then notify facility staff when commissioning events will occur. 5.10.4 Sampling No sampling strategies will be used. 5.11 O&M Manuals, Warranties, and Commissioning Record Book 5.11.1 O&M Manual and Warranty Overview The CxAg reviews commissioned systems O&M manuals, documentation, and as-built drawings for specification compliance verification. The CxAg recommends O&M manual approval and acceptance to CM. The CxAg also reviews equipment warranties for clear Owner requirement descriptions to keep warranties in force. 5.11.2 Commissioning Record Book The CxAg compiles, organizes, and indexes listed commissioning data by equipment into labeled, indexed, and tabbed three-ring binders. Binders and O&M manuals shall be delivered to the CM upon construction completion. Correspondence, meeting minutes, progress reports, miscellaneous notes, etc. shall be kept in only the Construction Phase Commissioning Record Book. The manual format shall be as follows: DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 11 Commissioning Plan Bid Phase Issued July 29, 2014 General Tab – 1 Tab - 2 Tab - 3 Tab - 4 Tab - 5 Executive Summary Commissioning Plan Exhibit A: Cost benefit Matrix Appendix 1 Commissioning Applications Forms Cx Request For information Construction Issues Log (Form C-01) Submittal reviews (Form C-17) Equipment Specific Tab - 6 Pre-functional Checklists Pre-functional Checklist Ground Power Units (Form PFC-201) Pre-functional Checklist Pre-Conditioned Air Units (Form PFC-202) Pre-functional Checklist Condensate / Sump Pump (Form PFC-203) Tab - 7 Functional Performance Testing Reports Functional Performance Testing Ground Power Units (Form FPT-201) Functional Performance Testing Pre Conditioned Air Units (Form FPT-202) Functional Performance Testing Condensate/Sump Pumps (Form FPT-203) 5.12 Owner Personnel Training and Orientation Refer to Bid Document Specifications. 5.13 Commissioning Cost Benefits Matrix As commissioning is a highly variable process, it is important to develop a consistent and sufficiently specific framework for describing the problems (deficiencies) discovered through the commissioning process and the measures applied to address them. SEI has developed the Commissioning Benefits Matrix,” shown in Exhibit A, which captures information on deficiencies and characterizes a specific commissioning measure with a unique code. The table in Exhibit A lists commissioned components and possible measures for increasing the cost benefits of commissioning. This table will be updated throughout the project capturing all issues, how they were resolved, and an estimate on the cost savings. 6.0 Summary Report The CxAg shall provide PM with a summary report WITHIN 30 days of completion of functional performance testing. The report shall include an executive summary, participant list, participant roles, and brief building description, commissioning scope, testing scope, and testing method description. For all commissioned equipment and systems, the report shall contain the CxAg’s opinion regarding the commissioning team meeting contractual obligations for: • • • • Equipment performing in accordance with design intent. Correct equipment installation. Functional performance and efficiency. Operator training. All outstanding non-compliant items shall be specifically listed. Recommendations for equipment or operation improvement, future actions, commissioning process changes, etc. shall also be included. Each non-compliance issue shall be referenced to specific functional test, inspection, trend log, etc. where deficiency is documented. Equipment functional performance DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 12 Commissioning Plan Bid Phase Issued July 29, 2014 and efficiency shall include a brief verification method description (manual testing, building control system trend log, data loggers, etc.) and include observations and conclusions. Appendices shall contain control sequence documentation, logs, meeting minutes, progress reports, deficiency lists, site visit reports, findings, unresolved issues, communications, etc. Pre-functional checklists and functional tests (along with blanks for operators), and monitoring data and analysis shall be provided in a separate labeled binder. The commissioning plan, pre-functional checklists, functional tests, and monitoring reports shall be included in the Commissioning Record. 7.0 Schedule 7.1 General Issues The following sequential priorities shall be followed: 1. Equipment shall not be used until pre-start checklist items and all manufacturers’ pre-start procedures have been completed. Moisture, dust, and other environmental and building integrity issues must also have been addressed. 2. System functional testing shall begin only after pre-functional testing, and start-up work has been completed. This requirement is not intended to preclude phased functional testing. 3. Functional testing of control system and its controlled equipment shall begin only after all points have been calibrated and pre-functional testing has been completed. 7.2 Project Schedule Refer to master project schedule. Table 7.0 - Commissioning Process Schedule Summary Tasks / Activity Estimated Start Date Estimated End Date Design Phase Project Intent N/A - Initial basis of Design N/A - Commissioning Plan (draft) 7/29/14 - Develop Cx Specifications 7/29/14 - 65% Design Review N/A - 100 % Design Review N/A - IFB Design Reviews N/A - Final Basis of Design N/A - Construction documents review N/A - DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 13 Commissioning Plan Bid Phase Issued July 29, 2014 Tasks / Activity Estimated Start Date Estimated End Date General Tasks / Activities CxAg to prepare Pre-Scoping Meeting Preliminary Construction Phase Commissioning Plan. (Cx Plan, Section 5.2) - - CxAg to conduct scoping meeting. (Cx Plan, Section 5.1) - - CxAg to provide commissioned equipment and system documentation requirements to CM. (Cx Plan, Section 5.7.1) - - Begin construction site visits and inspections. (Cx Plan, Section 5.3) - - Start-up and Checkout Tasks / Activities CM to compile manufacturer’s installation instructions, start-up instructions, and checkout plans and deliver to CxAg. (Cx Plan, Section 5.8.1) - - CxAg to prepare start-up and checkout plans and deliver to CM. (Cx Plan, Section 5.8.1) - - CM to deliver notification of pre-functional testing and start-up execution to CxAg. (Cx Plan, Section 5.8.2) 4 weeks prior to scheduled pre-functional testing and start-up - Execute pre-functional testing and startup. (Cx Plan, Section 5.8.2) Upon completion of each Equipment / System installation - CM to forward completed pre-functional checklists to CxAg. (Cx Plan, Section 5.8.2) Upon completion of checklist; but at least 72 hrs prior to scheduled FPT - Functional testing Tasks / Activities CM to forward all documentation and change orders affecting commissioned equipment and systems to CxAg. (Cx Plan, Section 5.7.2) - - CM to prepare control sequences and deliver to CxAg. N/A - DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 14 Commissioning Plan Bid Phase Issued July 29, 2014 Tasks / Activity Estimated Start Date Estimated End Date CxAg to prepare functional testing forms and deliver to CM. (Cx Plan, Section 5.9.4) - - CxAg to prepare functional testing schedule to CM. (Cx Plan, Section 5.10.1) - - Execute functional performance tests. (Cx Plan, Section 5.10.1) - - O&M Manuals and Training Tasks / Activities CxAg to review O&M manuals and provide approval recommendation to CM. (Cx Plan, Section 5.11.1) - - CxAg to prepare training and orientation agenda and forward to CM. (Cx Plan, Section 5.12) - - Prepare training and orientation materials and forward to CxAg for review. (Cx Plan, Section 5.12) - - Execute training and orientation. (Cx Plan, Section 5.12) - - CxAg to prepare final commissioning summary Report and forward to PM. (Cx Plan, Section 6.0) - - DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 15 Commissioning Plan Bid Phase Issued July 29, 2014 Exhibit A Cost Benefits Matrix DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 16 Commissioning Plan Bid Phase Issued July 29, 2014 DFW Commissioning Benefits Matrix PROJECT : Terminal B High Gates Electrification PROJECT No. 9500540 Ref Date Issue Log Ref Description of Issue Date Updated: 8/8/14 LEGEND I D E A/T System Issue Type Installation Design Existing Condition Acceptance / Testing Issue Type Closure Status/ Remarks Resolution Date $ Estimated Cost Benefit Avoidance Totals Operational $0.00 Notes: This form is to be utilized by the CxAg is exact format provided Ensure that as may issues as possible are allocated ESTIMATED costs DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 17 Commissioning Plan Bid Phase Issued July 29, 2014 Exhibit B Commissioning Report Status and Equipment Summary DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 18 Commissioning Plan Bid Phase Issued July 29, 2014 Commissioning Report Status Date Updated: 8/8/14 PROJECT : Terminal B High Gates Electrification PROJECT No. 9500540 Date I/D N/A A B C D E F G H I J K L M N O P Q Commissioning Process Project Intent Basis of Design Commissioning Specifications / Cx Plan Design Review 65% Design Review 95% IFB Design Review Scoping Cx Meetings Submittal Reviews Commissioning Process Issues / Issues Log Pre Functional Checklists Factory Tests and Start Up Reports Site Visits / Cx Meeting Reports O&M Manual Reviews Test & Balance Reports (TAB) Systems Manual Training Documentation Functional Performance Testing Transition Meetings Warranty Review Draft Cx Report Cx Report Addendum Lessons Learned Workshop Complete Issues or deficiencies Not applicable Started Completed N/C N/S Status Not complete Not started Comments Notes: This form is to be utilized by the CxAg is exact format provided DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 19 Commissioning Plan Bid Phase Issued July 29, 2014 Appendix 1 Sample Commissioning Application Forms DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 20 Commissioning Plan Bid Phase Issued July 29, 2014 C-01 Construction Issues Log Date Updated: 8/8/14 PROJECT : Terminal B High Gates Electrification PROJECT No. 9500540 Issue Ref Date System Description of Issue LEGEND Issue Type I D E O Photo Ref Installation Design Existing Condition Other Issue Type OPEN ITEMS Closed Open Status Open / Closed Response Closed Items Open Items Closed items to be greyed out and struckout Open Items Resolution Verified Closure Date Remarks / Notes 0 0 Notes: This form is to be utilized by the CxAg is exact format provided. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 21 Commissioning Plan Bid Phase Issued July 29, 2014 C-01 Construction Issues Log Photos Date Updated: 8/8/14 PROJECT : Terminal B High Gates Electrification PROJECT No. 9500540 DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 22 Commissioning Plan Bid Phase Issued July 29, 2014 C-02 DOCUMENTATION TRACKING & CONTROL LOG Legend: D= Design Team C= Contractor CxAg= Commissioning Agent Discipline Required By Plans and Specs Current Addendums ALL ALL D D For Commissioning Use For Commissioning Use Schedules Showing Commissioning Activities ALL C For Review and Comments D-ALL D D For Review and Comments For Review and Comments ALL C ALL ALL ALL ALL ALL ALL ALL ALL ALL ALL ALL C,D C,D D,O Required Document Date Received By CxAg O=Owner Date Required Comments Notes Design and Construction Documents Design Intent Document Design Criteria Equipment submittal Schedule Product Submittals Shop Drawings Coordination Drawings Submittal Log or Registry RFI's RFI's with responds RFI Log ASI's, SIs, Bulletins, PCOs CCDs Change Orders DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 4 weeks prior to contract award For Review and Comments Approved with Comments Information Only Information Only Information Only Information Only Information Only Information Only Information Only Information Only Information Only Information Only O D,O C,D D,O O O O 23 Commissioning Plan Bid Phase Issued July 29, 2014 C-02 DOCUMENTATION TRACKING & CONTROL LOG Legend: Required Document D= Design Team Discipline Required By C= Contractor CxAg= Commissioning Agent Date Received By CxAg Date Required O=Owner Comments Notes Design and Construction Documents Equipment Documents for Verification Testing procedures (VTPs) 400Hz/28V DC Units Electric C At 50% construction schedule Pre Cooled Air Units (PCA) Mechanical C At 50% construction schedule Condensate Sump Pumps Mechanical C At 50% construction schedule Manufacturer Start up and recommendations. O&M Material Manufacturer Start up and recommendations. O&M Material Manufacturer Start up and recommendations. O&M Material Contractor Required Tests and Documentation NPD incorporated in VTP form Inclusive of OAC and Progress meetings Name Plate Data All C Prior to FPT Construction Meeting Minutes All C Weekly Contractor Required Testing Reports All C Within 1 week of succesful completion of each test Required by Specifications Verification Testing Schedule All Disciplines involved in FPT C Four (4) weeks prior to testing For Review and Approval All systems requiring training per specifications C Attach to O&M Materials at 50% construction schedule For Review and Approval Mech C All C O&M Training Schedule and plans Test Adjust and Balance Report System readiness checklist DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 2 weeks prior to start of system FPTs 10 days prior to commencement of FPTs 24 For Review and Approval For Review and Approval Commissioning Plan Bid Phase Issued July 29, 2014 FORM C-03D COMMISSIONING REQUEST FOR INFORMATION A. Request for Information (RFI) Identification: RFI ID: RFI Date: General Description Equipment Identification (ID Number / Tag) (Equipment Description) Equipment Location RFI Initiated From: Attachments Included Equipment/System Test Observation No Yes Description: Document Review Discussion B. Information Sought For: Developing construction checklist Maintaining functional performance testing schedule Resolving other issue Developing functional performance testing Resolving functional performance testing issue C. RFI Authored By: (Requestor’s Name) (Company) D. RFI Addressed To: Architect Electrical Engineer Owner Mechanical Engineer Construction Manager/General Contractor Other: E. Copied To: (Name) F. (Company) Requested Information: G. Addressee’s Response: DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 25 Commissioning Plan Bid Phase Issued July 29, 2014 C-03E RFI Log Date Updated: 8/8/14 PROJECT : Terminal B High Gates Electrification PROJECT No. 9500540 Review Document : RFI Number RFI Responses Date Reference Document RFI Request RFI Response Status Open/Closed Open Remarks / Notes Notes: This form is to be utilized by the Cx Agent is exact format provided. Different Documents Reviewed may require different logs, i.e. O&Ms one log, training videos another. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 26 Commissioning Plan Bid Phase Issued July 29, 2014 C-05C Staff Training and Orientation Log Date Updated: 8/8/14 LEGEND PROJECT : Terminal B High Gates Electrification PROJECT No. 9500540 Date I/D N/A Specification Requirements # System or Equipment Involved Maintained Spec Section By Hours of Training Specified Complete Issues or deficiencies Training not required N/C Not complete N/S T/C Not started Training completed; required notifications or documents not provided Prior to Training Notification 20 Days Prior to Training Agenda provided Syllabus/ Training Manuals Training Information and Closeout Trainer Name Proposed and Contact Training Date Info Date Of Training Hours of Training Provided List of attendees Electronic Copies of all handouts Video recording DVD in MP4 format Comments Notes: This form is to be utilized by the CxAg is exact format provided DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 27 Commissioning Plan Bid Phase Issued July 29, 2014 C-06 CORRECTIVE ACTION REPORT A. Report Identification: Correction Action ID: Report Date: Equipment Identification: Issue Date: (ID Number / Tag) Equipment Location: Information Source: Attachments Included: (Equipment Description) Equipment/System Test No Yes Observation Document Review Discussion Description _______________________________________ B. Deficiency and/or Issue and Resulting Effects (To Be Completed By Commissioning Agent): The above equipment has been tested, observed, reviewed, or was discussed and was found to not comply with the contract document. 1. Deficiencies or Issues: 2. Resulting Effects: C. Corrective Actions and Dates (To Be Completed By Commissioning Agent): The below listed corrective actions are: Required Recommended For testing to proceed in a timely manner, it is imperative that the required corrective action be completed by (Date or Event) D. Design Team Action (To Be Completed By Design Team If Indicated): No Design Team action required, information provided for record purposes only. Design Team Corrective action plan required. Design Team Concurrence requested but not required for corrective action execution Design Team Concurrence required prior to corrective action execution (Design Team Concurrence) E. Contacts Relevant to Corrective Actions: Address To: Cx Agent: Owner’s Rep: Report Copied To: (Name) F. (Company) Contractor’s Statement of Correction (To Be Completed By Contractor): Deficiencies identified above have been correct with the following actions: (Signature DFW International Airport Project No: 9500540 Terminal B High Gates Electrification (Company) 28 (Date) Commissioning Plan Bid Phase Issued July 29, 2014 C-07 Commissioning Progress Record / Equipment Summary Date Updated: 8/8/14 PROJECT : Terminal B High Gates Electrification PROJECT No. 9500540 Equipment Item # Equipment ID Type DFW International Airport Project No: 9500540 Terminal B High Gates Electrification Manufacturer Model No. Factory Test LEGEND Complete N/C Not complete I/D Issues / Deficiencies N/S Not started N/A Not applicable I/R In Review Date Start-Up Start Up Closeout PFCs 29 FPTs O&M Warranty Spare Parts Comments Commissioning Plan Bid Phase Issued July 29, 2014 FORM C-17 SUBMITTAL REVIEW A. Submittal Review Identification: Submittal Date: Review Date: Received Date: Submittal Review Index: Specification Number: Submittal Number: Specification Name: B. Submittal Review Disposition: Approval recommended Approval recommended with comments herein Additional information requested Reviewed for Commissioning Consideration Not reviewed Disapproval and entire resubmittal recommended Disapproval and partial resubmittal recommended Other: _______________________________________ C. Submittal Review Executed By: (Name) (Discipline) D. Submittal Review Disposition Forwarded To: Architect Electrical Engineer Owner Project Manager Mechanical Engineer Construction Manager/General Contractor Other:_______________________________________ E. Submittal Review Disposition Copied To: (Name) F. (Discipline) Submittal Review Comments: COMMENT NUMBER RELEVANT SPECIFICATION/ DRAWING A/E DFW International Airport Project No: 9500540 Terminal B High Gates Electrification COMMENT SUBMITTAL 30 Commissioning Plan Bid Phase Issued July 29, 2014 C-17 Submittal Review Log Date Updated: 8/8/14 PROJECT : Terminal B High Gates Electrification PROJECT No. 9500540 Review Document : Ref Date Approved Submittals Reference Document Review Comment Response Status Open/ Remarks / Notes Closed Notes: This form is to be utilized by the CxAg is exact format provided Different Documents Reviewed may require different logs, i.e. O&Ms one log, training videos another. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 31 Commissioning Plan Bid Phase Issued July 29, 2014 FORM C-18 FIELD OBSERVATIONS AND TESTS A. Field Observations and Tests Identification: Report Number: Observation Date: Issue Date: Observation Description: Attachments Included: No Yes Number(s): Description: B. Field Observations and Tests Executed By: (Name) (Discipline) C. Field Observations And Tests Disposition Forwarded To: Architect Electrical Engineer Owner Mechanical Engineer Construction Manager/General Contractor Other: Project Manager D. Field Observations And Tests Copies To: (Name) (Discipline) E. Field Observations And Tests Comments: Classification The purpose of this observation/test report is to document site observation, start-up results, and/or to summarize system Functional Performance Testing (FPT). Information is classified as follows: F. • Back-check System refinement resulting from testing or site observation requiring future backchecking • Correction Clarification of previously issued report. • Corrective Action System deficiency found during site observation or system FPT requiring corrective action prior to system initial FPT execution or FPT re-execution. • Designer Input Designer input requested. • Req Information Requested information. • Terminal Previously identified issue planned to be pursued no further. • Information For informational purposed only. • Start-up Equipment Start-up Observation • Summary Test Results Summary Field Observations And Tests Areas of Concern: Areas of Concern Cited observations are classified according as follows: • GEN General Comment • IEQ Indoor Environmental Quality Issue • COD Code Issue • QC Quality Control Issue • CON Contract Requirement Issue • INST Installation Issue DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 32 Commissioning Plan Bid Phase Issued July 29, 2014 FORM C-18 OBSERV ATION / TEST NO. CLASSIFICATION DFW International Airport Project No: 9500540 Terminal B High Gates Electrification FIELD OBSERVATIONS AND TESTS AREA OF CONCERN OBSERVATION/TEST 33 Commissioning Plan Bid Phase Issued July 29, 2014 C-21 OMM & WARRANTY LOG Date Updated: 8/8/14 PROJECT : Terminal B High Gates Electrification PROJECT No. 9500540 LEGEND Date I/D N/A Specification Requirements # System or Equipment Involved O&M Ref Warranty Ref DFW International Airport Project No: 9500540 Terminal B High Gates Electrification Complete Issues or Deficiencies Not Applicable N/S L R Not Started Late Required OMM Submission O&M Required OMM BP Ref Submitted Under Review Due Date 90 Days Prior to TOC Unless Specified Otherwise Warranty Information Returned to CMAR Complete 34 Warranty Required Special Warranty required OMM BP Ref Under Review Returned to CMAR Complete Comments Commissioning Plan Bid Phase Issued July 29, 2014 FORM C-22 PRE-FUNCTIONAL CHECKLIST REVIEW A. Pre-functional Checklist Review Identification: Received Date: Review Date: Submittal Date: Submittal No: B. Pre-functional Checklist Review Disposition: Approval recommended Approval recommended with comments herein Additional information requested Reviewed for Commissioning Consideration Not reviewed Disapproval and entire resubmittal recommended Disapproval and partial resubmittal recommended Other: _______________________________________ C. Pre-functional Checklist Review Executed By: (Name) (Discipline) D. Pre-functional Checklist Review Disposition Forwarded To: Architect Electrical Engineer Owner Project Manager Mechanical Engineer Construction Manager/General Contractor Other:_______________________________________ E. Pre-functional Checklist Review Disposition Copied To: (Name) F. (Discipline) Construction Checklist Review Comments: COMMENT NUMBER PRE-FUNCTIONAL CHECKLIST IDENTIFICATION NUMBER DFW International Airport Project No: 9500540 Terminal B High Gates Electrification COMMENT DESCRIPTION 35 Commissioning Plan Bid Phase Issued July 29, 2014 Appendix 2 Sample Pre-functional Checklist Forms DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 36 Commissioning Plan Bid Phase Issued July 29, 2014 PFC-201 PRE-FUNCTIONAL CHECKLIST - GROUND POWER UNIT Project Information PROJECT: Terminal B High Gates Electrification PROJECT NUMBER: 9500540 UNIT DESIGNATION: The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This pre-functional checklist is submitted for approval and is subject to an attached list of outstanding items yet to be completed. A Statement of Corrections (SOC) will be submitted for any outstanding items to be completed prior to functional testing. None of the outstanding items preclude safe and reliable operation of the unit(s) being tested. _____ SOC list attached. Sign-off TEST DATE: COMPANY START TIME: NAME CONTACT INFORMATION Mechanical Contractor Electrical Contractor TAB Contractor Controls Contractor Certified Start-up Technician CMAR • Pre-functional checklist is to be completed as part of startup & initial checkout, preparatory to functional testing. • Checklist does not take the place of the Manufacturer's recommended checkout and startup procedures or report. • Items that do not apply shall be noted with the reasons on this form (N/A - not applicable, BO - by others). • Contractor shall be responsible to see that checklist items by their subcontractors are completed and checked off. Approvals CX APPROVAL DATE: COMPANY OAR APPROVAL DATE: NAME CONTACT INFORMATION Commissioning Agent Owner's Authorized Representative DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 37 Commissioning Plan Bid Phase Issued July 29, 2014 PFC-201 PRE-FUNCTIONAL CHECKLIST - GROUND POWER UNIT Project Data Project: Terminal B High Gates Electrification Name: System: Date: Building Equipment Identification Type: Identification: Manufacturer: 400 Hertz and 28 Volt Ground Power Unit Unit Data Model No: Input Voltage: Output Voltage: Phase: Input Frequency: Output Frequency: ITEM Observations YES NO COMMENTS General 1 Cabinet and components mounted in weather-proof enclosure 2 Unit housing and components undamaged 3 Mounting provided on underside of PBB 4 400 Hz Frequency converter installed 5 Unit wired for power 6 Working bundles in control cabinet installed in workmanlike manner 7 Line drop compensator installed 8 Cable installed with molded head 9 Fault isolation features installed 10 Phase models cooled by a sealed fan 11 LCD Display with contrast adjustment 12 Single grounding installed for AC source/output power 13 Cable of sufficient length to reach aircraft connection Memory Storage 14 RS-232 connection installed for memory record downloads DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 38 Commissioning Plan Bid Phase Issued July 29, 2014 ITEM Observations YES NO COMMENTS Controls & Special Features 15 Major components & subassemblies shall be visibly marked/labeled with ID/codes 16 Alarms and indicator lights installed and visible 17 Active operation warning light installed and visible 18 Voltage Adjustment Diagnostics Unit contains diagnostic test system with associated output display 19 Controls 20 600 V, 3-pole 10-amp manually operated disconnect isolation switch provided 21 Step down transformer provided to the low voltage circuits 22 Remote push button station mounted on the outside of the PBB lift column 23 Cable hoist counter disconnects power from the motor when the "raise" and "lower" travel limits have been reached Unit to include On/Off/Up/Down controls Hoist Components 24 Input power cable installed 25 Tunnel mounted cable hoists installed with brackets 26 Remote push button installed for operator controls 27 Hoist is constructed with removable or hinged cover 28 Hoist contains an electric open drip proof gear-motor installed and operational 29 Hoist disc brake installed and operational DFW International Airport Project No: 9500540 Terminal B High Gates Electrification Allow raising and lowering the cable to power aircraft 39 Commissioning Plan Bid Phase Issued July 29, 2014 ITEM Observations YES NO COMMENTS System Monitoring/ Built-in Test Equipment Panel display contains the following parameters: a. Input Voltage (A-Bm B-C, C-A, 3 phase) b. DC Bus Voltage Adjustable c. Output Power 30 d. Power Factor e. Output Factor f. Run Time g. GPU Settings h. GPU Memory Data i. Setup Values j. Phase "A" Output Voltage k. Phase "B" Output Voltage l. Phase "C" Output Voltage m. Average Output Current 30 n. Phase "A" Output Current o. Phase "B" Output Current p. Phase "C" Output Current q. Average Output Current Overloads and System Protection Minimum of 3 lights mounted on the front of the unit: a. Red Light: Presence of fault 31 b. Green Light: Unit working/ power on c. Amber Light: Output contactor on 32 Input & Output Over and Under voltage 33 Output overload 34 Loss of E/F 35 E/F Over voltage 36 Bus discharge fault 37 Heat sink over temperature DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 40 Commissioning Plan Bid Phase Issued July 29, 2014 ITEM 38 Output frequency fault 39 IGBT fault 40 DC link capacitor fault Observations YES NO COMMENTS Notes DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 41 Commissioning Plan Bid Phase Issued July 29, 2014 PFC-202 PRE-FUNCTIONAL CHECKLIST - PRE-CONDITIONED AIR UNIT Project Information Terminal B High Gates Electrification PROJECT: PROJECT NUMBER: 9500540 UNIT DESIGNATION: The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This pre-functional checklist is submitted for approval and is subject to an attached list of outstanding items yet to be completed. A Statement of Corrections (SOC) will be submitted for any outstanding items to be completed prior to functional testing. None of the outstanding items preclude safe and reliable operation of the unit(s) being tested. _____ SOC list attached. Sign-off TEST DATE: COMPANY START TIME: NAME CONTACT INFORMATION Mechanical Contractor Electrical Contractor TAB Contractor Controls Contractor Certified Start-up Technician CMAR • Pre-functional checklist is to be completed as part of startup & initial checkout, preparatory to functional testing. • Checklist does not take the place of the Manufacturer's recommended checkout and startup procedures or report. • Items that do not apply shall be noted with the reasons on this form (N/A - not applicable, BO - by others). • Contractor shall be responsible to see that checklist items by their subcontractors are completed and checked off. Approvals CX APPROVAL DATE: COMPANY OAR APPROVAL DATE: NAME CONTACT INFORMATION Commissioning Agent Owner's Authorized Representative DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 42 Commissioning Plan Bid Phase Issued July 29, 2014 PFC-202 PRE-FUNCTIONAL CHECKLIST - PRE-CONDITIONED AIR UNIT Project Data Project: Name: System: Date: Terminal B High Gates Electrification Building Equipment Identification Type: Identification: Manufacturer: Pre-Conditioned Air Unit Unit Data Motor Nameplate Data Filter Data Model No: Blower Type: Input Power: Manufacturer: Model No: Motor HP: Quantity: Type: Size: Blower RPM: Design Airflow: Operating Static Pressure: Motor RPM: Voltage: Amperage: Hydronic Coil Data Coil Fluid: Coil Flow: Air Temp (◦F): Condensate Pump Data VFD Data Manufacturer: Model No: EAT/LAT: Manufacturer: Cooling Capacity: Fluid Flow: Motor HP: Heating Data Heat Capacity: ITEM Observations YES NO COMMENTS General 1 Unit housing undamaged 2 Permanent labels affixed 3 Flexible duct intact 4 Hydronic hose insulated & sufficient length 5 Fixed walkway vent connections 6 Supply hose adequately supported 7 Power circuit installed 8 PCA rail mounting hung from under bridge 9 Smoke detectors installed and wired 10 Automated dampers installed and open 11 Latches installed and secured 12 NTP plugs provided on discharge nozzle 13 Filters installed & clean 14 Auto-defrost installed on coils DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 43 Commissioning Plan Bid Phase Issued July 29, 2014 ITEM Observations YES 15 Bridge connection installed 16 Unit startup performed 17 Motor vibration isolator installed 18 Motor and blower removable from PCA housing 19 Blower installed: permanently lubricated motor bearings where bearings are not accessible 20 Hydronic coil installed and undamaged 21 Sliding tube assembly: Outer duct section, middle section, inner section of decreasing diameters 22 Rotunda/ C-Tunnel mounted units: devices installed to transport the glycol supply/return lines, PCA electrical supply and condensate return across the bridge 23 Coils mounted on coil casing with the same end connections accessible for service 24 Plenum is insulated 25 Hydronic coil hose connections complete NO COMMENTS Sliding tube insulated throughout the entire length Telescoping 26 Laminate segments with wiper seals 27 Exterior paint finish clean and undamaged 28 Tube insulation installed and undamaged Condensate System (if applicable) 29 Condensate pump installed & operational 30 Internal float switch installed 31 Drain pan installed under cooling coil section and properly sloped 32 Insulated condensate hose installed Controls 33 Controls complete DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 44 Commissioning Plan Bid Phase Issued July 29, 2014 ITEM Observations YES 34 Fan control sequence identified 35 PCA operation warning light installed in bridge panel 36 Hydronic coil control valve installed 37 Smoke detector circuit operational 38 Heating control sequence verified 39 Temperature sensors calibrated NO COMMENTS Heating Components 40 Electric heat wired and operational 41 Heater performance (kW) identified Cooling Coil 42 Entering and leaving gauge ports 43 Balancing devices installed and set 44 Isolation valves installed 45 2 way/ 3 way valve installed 46 Pipe insulation undamaged 47 Fin and tubes intact Notes DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 45 Commissioning Plan Bid Phase Issued July 29, 2014 PFC-203 PRE-FUNCTIONAL CHECKLIST - CONDENSATE / SUMP PUMP Project Information Terminal B High Gates Electrification PROJECT: PROJECT NUMBER: 9500540 UNIT DESIGNATION: The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This pre-functional checklist is submitted for approval and is subject to an attached list of outstanding items yet to be completed. A Statement of Corrections (SOC) will be submitted for any outstanding items to be completed prior to functional testing. None of the outstanding items preclude safe and reliable operation of the unit(s) being tested. _____ SOC list attached. Sign-off TEST DATE: COMPANY START TIME: NAME CONTACT INFORMATION Mechanical Contractor Electrical Contractor Controls Contractor Certified Start-up Technician Other CMAR • Pre-functional checklist is to be completed as part of startup & initial checkout, preparatory to functional testing. • Checklist does not take the place of the Manufacturer's recommended checkout and startup procedures or report. • Items that do not apply shall be noted with the reasons on this form (N/A - not applicable, BO - by others). • Contractor shall be responsible to see that checklist items by their subcontractors are completed and checked off. Approvals CX APPROVAL DATE: COMPANY OAR APPROVAL DATE: NAME CONTACT INFORMATION Commissioning Agent Owner's Authorized Representative DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 46 Commissioning Plan Bid Phase Issued July 29, 2014 PFC-203 PRE-FUNCTIONAL CHECKLIST - CONDENSATE / SUMP PUMP Project Data Project: Name: System: Date: Terminal B High Gates Electrification 9500540 Building Equipment Identification Type: Identification: Manufacturer: Condensate / Sump Pump Unit Data Model No: Serial No: Input Power: Voltage/Phase: RLA: FLA: Motor HP: Motor Eff.: Motor RPM: GPM: ITEM Observations YES NO COMMENTS General 1 Contract required identification complete 2 Vibration isolation devices installed and functional 3 Pipe fittings complete and pipes properly supported 4 Check valve installed in discharge piping 5 6 Operating and alarm floats installed and adjusted based on contract requirements. Sump pit is cleaned of any debris before pump is installed in sump pit 7 Factory sump pump inlet strainer in place and clean 8 Factory supplied or contract required pump removal device installed Electrical and Controls 9 All electric connections verified tight 10 Proper grounding installed 11 Power wiring tested based on contract requirements (Report Attached) 12 Motor safeties in place and operable 13 Local control panel to operating and alarm float wiring complete 14 Local control panel to operating and alarm float wiring point to point verification complete. (Point to point report attached) DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 47 Commissioning Plan Bid Phase Issued July 29, 2014 ITEM Observations YES NO COMMENTS Operational Checks (This is not the functional performance test) 15 Sump pit was cleaned of any debris before pump was started 16 Pump rotation verified correct 17 During pump operation no unusual noise or vibration was seen 18 No leaking apparent in piping and around fittings 19 Record full load running amps for each pump _______ rated FL amps x _______ service factor = _______ Max Amps Running less than Max? 20 Specified sequences of operation and operating schedules have been implemented with all variations documented 21 Specified point-to-point checks have been completed and documentation record submitted for this system 22 All recommended factory start-up procedures were followed during start-up (Start-up report is attached Notes DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 48 Commissioning Plan Bid Phase Issued July 29, 2014 Appendix 3 Sample Functional Performance Testing Forms DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 49 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-201 FUNCTIONAL PERFORMANCE TEST- GROUND POWER UNIT Project Information PROJECT: Terminal B High Gates Electrification PROJECT NUMBER: 9500540 UNIT DESIGNATION: TEST INFORMATION TEST DATE: COMPANY START TIME: PARTICIPANTS: NAME CONTACT INFORMATION Directions: The following pages are to be filled out by a representative of the commissioning firm who will observe the testing described herein. Remarks: Existing movement capabilities shall be recorded and verified to be in acceptance with DFW Airport passenger boarding bridge movement requirements. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 50 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-201 FUNCTIONAL PERFORMANCE TEST- GROUND POWER UNITS Observations REQUIRED ACTION ACTION 1. Operate the hoist selector switch 1. The reel assembly travels in both located at the PBB wheel bogie in the directions and automatically stops in up and down position. either direction when at their travel limits. Y N REMARKS 2. Rotate the hoist switch clockwise to 1. The hoist cable lowers the 400 Hz the "Lower" position. cable in a smooth controlled manner to a ground handling position. 2. The cable hoist limit switch interrupts the control power to the motor contactor when the travel limit "lower" has been reached. 3. Unhook nylon strap connected to hoist cable mounting frame. 1. Cable is released and has sufficient length to reach aircraft connection point. 4. Go to the gate being tested and turn 1. The gate box will be energized. the main power disconnect lever to the "ON" or "UP" position. The main power disconnect is located on the PBB rotunda column next to the PCM. Go to gate box to be tested and turn the gate box disconnects lever or switch to the "ON" or "UP" position. 5. If there is a RED fault light, press the "RESET" or "OFF" pushbutton. 1. After RESET the four red fault lights will come on in sequence, and then turn off. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 51 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-201 FUNCTIONAL PERFORMANCE TEST- GROUND POWER UNITS Observations REQUIRED ACTION ACTION 1. Operate the hoistcable selector switch 1. The reel assembly travels in both 6. Insert an aircraft power remote mounted on 400 Hz source analyzer into the end of the Control station turns on. aircraft cable assembly. Press the ON pushbutton on the remote mounted 400 Hz control station. 7. Check the phase rotation indicator on the phase checker. Y N REMARKS 1. It should be "A", "B", "C" 2. If the phase rotation is in the wrong direction change any two (2) phase leads on the service side of the 575V disconnect switch at the gate box or at the load side of the new 200 amp circuit breaker located at the base of the PBB rotunda. 8. Operate ON/OFF switches at the 400 Hz control station, located on the PBB bogie wheel. 1. This can be determined as the lights for all three phases on the phase checker will be illuminated when the gate box contractor is closed. 9. Operate the ON pushbutton closing 1. The contactor should close. the gate box contactor. 10. Toggle the E&F switch to the NEUTRAL position. 1. The contactor should open. 11. Toggle the E&F switch in the phase checker to the F position and press the ON pushbutton. 1. The contactor should close. 12. Toggle the E&F switch to the OFF 1. The contactor should open. position, or Neutral position. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 52 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-201 FUNCTIONAL PERFORMANCE TEST- GROUND POWER UNITS ACTION 1. Operate the hoist selector switch 13. Close the contactor with the E&F switch in either the E or F position. Then, pull the phase checker out of the end of the cable. Observations REQUIRED ACTION Y N REMARKS 1. The reel assembly travels contactor should open.in both 14. Press the "Reset" button on the gate box. Simulate an overload scenarion on the gate box. 1. The lights on the panel should reset. 2. The overload light on the exterior of the gate box cabinet should illuminate. 15. Press the "Reset" button on the gate box. Simulate an under voltage scenarion on the gate box. 1. The lights on the panel should reset. 2. The under voltage light on the exterior of the gate box cabinet should illuminate. 16. Press the "Reset" button on the gate box. Simulate an over voltage scenario on the gate box. 1. The lights on the panel should reset. 2. The over voltage light on the exterior of the gate box cabinet should illuminate. 17. The manufacturer/seller shall now conduct load bank test as follows: 18. Connect the gate box aircraft output cables to each of the 60KVA load banks. 1. At each of the two (2) output cable connector head assemblies measure and record the Line to Neutral (L-N) voltage for each phase. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 53 Actual Load Voltage: A-N: ____ V B-N: ____ V C-N: _________ V Commissioning Plan Bid Phase Issued July 29, 2014 FPT-201 FUNCTIONAL PERFORMANCE TEST- GROUND POWER UNITS ACTION 1. Operate the hoist selector switch 19. Apply 54 Kvar reactive load to each of the load banks. 20. Add 72KW to the existing 54Kvar load (60kva at 0.8 PF) to each of the load banks 21. Test 28V DC power supply Observations REQUIRED ACTION 1. At The reelof assembly travels in both each the two (2) output cable connector head assemblies measure and record the Line to Neutral (L-N) voltage for each phase. 1. At each of the two (2) output cable connector head assemblies mesure and record the Line to Neutral (L-N) voltage for each phase. 1. With load bank connected, energize the 28v DC power supply verifiy and record the indicated voltage. Y N REMARKS Actual Load Voltage: A-N: ____ V B-N: ____ V C-N: _________ V Actual Load Voltage: A-N: ____ V B-N: ____ V C-N: _________ V Actual Load Voltage: ________________V 22. Reconnect the nylon strap back to 1. The hoist cable raises the 400 Hz the hoist cable mounting frame. cable in a smooth controlled manner Rotate the hoist panel switch counter back to the stowed position. clockwise to the raised position. 2. The cable hoist limit switch interrupts the control power to the motor contractor when the travel limit "raise" has been reached. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 54 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-201 FUNCTIONAL PERFORMANCE TEST- GROUND POWER UNITS ACTION 1. Operate the hoist selector switch Observations REQUIRED ACTION Y N REMARKS 1. The reel assembly travels Notes in both DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 55 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-202 FUNCTIONAL PERFORMANCE TEST- PRE-CONDITIONED AIR UNIT Project Information PROJECT: Terminal B High Gate Electrification PROJECT NUMBER: 9500540 UNIT DESIGNATION: TEST INFORMATION TEST DATE: COMPANY START TIME: PARTICIPANTS: NAME CONTACT INFORMATION Directions: The following pages are to be filled out by a representative of the commissioning firm who will observe the testing described herein. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 56 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-202 FUNCTIONAL PERFORMANCE TEST- PRE-CONDITIONED AIR UNIT Observations REQUIRED ACTION Y Aircraft Hydronic Cooling Mode ACTION 1. Activate the PCA in aircraft cooling mode of operation by setting the DDC. N REMARKS 1. Blower motor activates in cooling mode of operation. 2. Cooling coil valve opens. 3.VFD slowly accelerates preset cooling speed by aircraft selection. 4. Cooling coil valve modulates to maintain outlet air setpoint. 6. Electric heat remains disabled. 2. Verify actual fan speed and airflow cooling mode. 1. Record actual RPM and airflow in remarks Actual Speed: _____________RPM Actual Airflow: _____________CFM 3. Measure the leaving air DB temp. At the leaving air temp. sensor. Observe the LAT at the DDC control readout. 1. The temperature should be within specified tolerance. Sensor Air Temp: ______________F Actual Air Temp: ______________F 4. Using a voltmeter, measure the actual motor voltages. 1. The actual measured voltages should coincide with the motor nameplate voltages. Nameplate Volts: ______________V Actual Volts: ______________V 5. Using an ammeter, measure the 1. The actual measured amperages should be less than actual motor amperage. the motor nameplate amperages and below the motor service factor allowance. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 57 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-202 FUNCTIONAL PERFORMANCE TEST- PRE-CONDITIONED AIR UNIT ACTION 6. Push STOP button on Remote Station. 7. While PCA is running, activate the ventilation mode by setting the DDC controls to simulate an ambient temperature setpoint from >45 F to <55 F. Observations REQUIRED ACTION Y Aircraft Hydronic Cooling Mode 1. Blower stops. 2. Coil Valve Closes. 3. Electric heat remains off. 4. Condensate pump remains disabled (if applicable). 1. Blower motor activates in cooling mode of operation. 2. Cooling coil valve opens. 3. VFD slowly accelerates preset cooling speed by aircraft selection. 4. Cooling coil valve modulates to maintain outlet air setpoint. 5. Condensate pump is automatic (If applicable). N REMARKS Note: Blower may not be re-started for a set period of recycle time, if applicable. Outside Air Setpoint: ________________F ________________Hz 6. Electric heat remains disabled. 8. Verify actual fan speed and airflow ventilation mode. 1. Record actual RPM and airflow in remarks. Actual Speed: ______________RPM Actual Airflow: ______________CFM 9. Measure the entering and leaving air DB temperature at the unit. 1. No observable air temperature difference is measured entering and leaving the unit. 10. Using a voltmeter, measure actual motor voltages. 1. The actual measured voltages should coincide with the motor nameplate voltages. Nameplate Volts: ________________V Actual Volts: ________________V 11. Using an ammeter, measure the actual motor amperage. 1. The actual measured amperages should be less than the motor nameplate amperages and below the motor service factor allowance. 12. Push STOP button on Remote 1. Blower stops. Station. 2. Coil Valve Closes. 3. Electric heat remains off. 4. Condensate pump remains disabled (if applicable). DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 58 Note: Blower may not be re-started for a set period of recycle time, if applicable. Commissioning Plan Bid Phase Issued July 29, 2014 FPT-202 FUNCTIONAL PERFORMANCE TEST- PRE-CONDITIONED AIR UNIT Observations ACTION REQUIRED ACTION Y Aircraft Hydronic Mode 13. While PCA is running, activate 1. Blower motor activates Cooling in the electric heat mode by setting cooling mode of operation. the DDC controls to simulate an 2. Cooling coil valve opens. ambient temperature setpoint from 3.VFD slowly accelerates preset >45 F. cooling speed by aircraft selection. N REMARKS Outside Air Setpoint: _______________F VFD Setting: _______________Hz 4. Cooling coil valve modulates to maintain outlet air setpoint. 5. Condensate pump is automatic (If applicable). 6. Electric heat is enabled. 14. Verify actual fan speed and airflow ventilation mode. 1. Record actual RPM and airflow in remarks Actual Speed: ______________RPM Actual Airflow: ______________CFM 15. Measure the entering and leaving air DB temperature at the unit. 1. The temperature difference indicates heating occurs. Entering Air Temp: ________________F Leaving Air Temp: ________________F 16. Using a voltmeter, measure actual motor voltages. 1. The actual measured voltages should coincide with the motor nameplate voltages. Nameplate Volts: ________________V Actual Volts: ________________V 17. Using an ammeter, measure the actual motor amperage. 1. The actual measured amperages should be less than the motor nameplate amperages and below the motor service factor allowance. Nameplate Amps: ________________A Actual Amps: ________________A 18. Push STOP button on Remote 1. Blower stops. Station. 2. Coil Valve Closes. 3. Electric heat turns off. 4. Condensate pump remains disabled. (if applicable) DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 59 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-202 FUNCTIONAL PERFORMANCE TEST- PRE-CONDITIONED AIR UNIT Observations REQUIRED ACTION Y Aircraft Hydronic Cooling Smoke Detection TestMode ACTION 19. Simulate condition that activates the smoke detector system / PCA safety interlock. 1. The smoke detector interlock shuts down the PCA unit. N REMARKS Note: Reset the PCA after completion of this test. Emergency Stop 20. Press the emergency stop pushbutton while the PCA is running. 1. The PCA shuts down. 21. Verify condensate line section at building is heat traced properly. 1. Minimum of >10 ft of condensate line is heat traced prior to entering building. Note: Reset the PCA after completion of this test. Condensate Heat Trace Notes DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 60 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-203 FUNCTIONAL PERFORMANCE TEST- CONDENSATE / SUMP PUMP Project Information PROJECT: Terminal B High Gates Electrification PROJECT NUMBER: 9500540 UNIT DESIGNATION: TEST INFORMATION TEST DATE: COMPANY START TIME: PARTICIPANTS: NAME CONTACT INFORMATION Directions: The following pages are to be filled out by a representative of the commissioning firm who will observe the testing described herein. DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 61 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-203 FUNCTIONAL PERFORMANCE TEST- CONDENSATE / SUMP PUMP Observations REQUIRED ACTION Initial Check ACTION 1. Set the power switch to the "on" position. 1. The pump energizes. 2. Set the power switch to the "off" position. 1. The pump de-energizes. 3. Simulate a demand for pump operation by filling sump with fluid (water) until float switch is activated. 1. The pump energizes and the fluid is evacuated. 4. Test pump for correct rotation, alignment and connection. 1. Pump operates quietly in the correct rotation with no significant vibration. 5. Using a voltmeter, measure the actual motor voltages. 1. The actual measured voltages should coincide with the actual nameplate voltages. Y N REMARKS Automatic Operation Nameplate Volts: _____________ Actual Volts: _____________ 6. Using an ammeter, measure the actual motor amperage. 1. The actual measured amperages should be less than the motor nameplate amperage and below the motor service factor allowance. Nameplate Amps: _____________ Actual Amps: _____________ High-Level Alarm Test DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 62 Commissioning Plan Bid Phase Issued July 29, 2014 FPT-203 FUNCTIONAL PERFORMANCE TEST- CONDENSATE / SUMP PUMP ACTION 7. Simulate a High-level Alarm condition for pump by disabling pump and filling sump with fluid (water) until high level float switch is activated, then enable pump. Observations REQUIRED ACTION Initial and Check 1. The pump energizes the Y N REMARKS high-level alarm is activated and pump does NOT start. 2. Verify audible and visual alarm. 3. Verify that the remote alarm contact closed to allow for future remote monitoring. 4. Enable pump to normal operation and verify that fluid is evacuated. Notes DFW International Airport Project No: 9500540 Terminal B High Gates Electrification 63 Commissioning Plan Bid Phase Issued July 29, 2014