Building System Commissioning and ReCommissioning © 2010 National Air Balance Company, Inc. Confidential. What We’ll Cover DEFINE BUILDING COMMISSIONING (CX) DEFINE THE PROCESS COMMISSIONING: WHO NEEDS IT AND AT WHAT COST BENEFITS OF COMMISSIONING RECOMMISSIONING (RE-CX) QUESTIONS & ANSWERS © 2010 National Air Balance Company, Inc. Confidential. Building System Commissioning (Cx) New Construction • Commissioning is a systematic process of ensuring that all building systems perform interactively according to the design intent and the owners operational needs. This is achieved by beginning in the design phase, documenting the design intent and continuing through construction, acceptance and warranty period with actual verification of performance. © 2010 National Air Balance Company, Inc. Confidential. Define the Process • Design Phase Cx Requirements - During this phase of commissioning the objective is to ensure the design team applies commissioning concepts to the design. Commissioning focused design reviews are conducted. - Additionally, the design team prepares commissioning specifications and a commissioning plan for inclusion in the bid documents. - Meeting these objectives during design prepares the way so that the: © 2010 National Air Balance Company, Inc. Confidential. Define the Process Contractors can accurately bid the commissioning work. Contractors can understand how to efficiently execute the commissioning process. There is a systematic, efficient and enforceable method to accomplish the commissioning objective. The commissioning objectives are met. © 2010 National Air Balance Company, Inc. Confidential. Define the Process • Construction & Acceptance Phase Cx Requirements - Commissioning during the construction phase of the project is intended to achieve the following specific objectives: Ensure that applicable equipment and systems are installed properly and receive adequate operational checkout by installing contractors. Verify and document performance and equipment and systems. Ensure that O & M documentation left on site is complete Ensure that owner’s operating personnel are adequately trained. © 2010 National Air Balance Company, Inc. Confidential. Define the Process - During this phase the following activities occur: The roles and responsibilities of the commissioning team are defined. A commissioning scoping meeting is planned and conducted. In attendance are the respective representatives of the GC, CM, CA, MP, A/C and the mechanical, electrical, controls and TAB subs. At the meeting commissioning parties are introduced and the commissioning process reviewed. © 2010 National Air Balance Company, Inc. Confidential. Define the Process The draft commissioning plan is reviewed, process questions are addressed, lines of reporting and communications determined and the work products list discussed. Also covered are the general list of each party’s responsibility and the proposed commissioning schedule. The Commissioning Authority finalizes the draft Cx plan using the information gathered from the scoping meeting. The initial commissioning schedule is also developed. © 2010 National Air Balance Company, Inc. Confidential. Define the Process The CxA make periodical site visits to the site as necessary, to witness equipment and system installations. The CxA provides the CM with monthly commissioning progress reports. The CM may adjust the reporting frequently as needed. The CxA also keeps a log of all commissioning related issues that require current or future attention. The CxA provides prefunctional checklist and functional test scripts for each piece of equipment commissioned. The functional testing is conducted by the responsible parties and witnessed by the CxA. © 2010 National Air Balance Company, Inc. Confidential. Define the Process The functional testing is conducted by the responsible parties and witnessed by the CxA. The CxA reviews the O & M manuals, documentation and redline as builts for systems that were commissioned to verify compliance with the specification The CxA will compile the final Cx report. • Post Acceptance/Warranty Period Commissioning - During the warranty period, seasonal testing and other deferred testing required is completed according to the specification. The CxA coordinates this activity. © 2010 National Air Balance Company, Inc. Confidential. ReCommissioning (Re-Cx) • Recommissioning of a previously commissioned facility maintains the efficiency and optimization that the commissioning originally provided and ensures that the current owner’s operational needs are met. • The original commissioning plan provided to the owner may contain a re-commissioning manual. • The Re-Cx manual will allow the facilities group the ability to Re-Cx the facility, re-establishing the building systems are operating efficiently and meeting the owner’s operational needs. © 2010 National Air Balance Company, Inc. Confidential. Commissioning: Who Needs it and at What Cost? • While all buildings can benefit from commissioning, the complexity and type of building will dictate the rigor and cost of the commissioning process. • For discussion purposes we have broken building types into four categories. - Simple: office building, classrooms, packaged equipment and controls; common systems, fewer pieces of equipment. © 2010 National Air Balance Company, Inc. Confidential. Commissioning: Who Needs it and at What Cost? - Moderate: more complex offices, classrooms with some labs, building automation, more control strategies, fewer package equipment; more systems (fire, emergency power, etc.) - Complex: moderate plus most of floor area in complex systems (hospitals, labs, operating rooms, clean rooms, fume hoods or other non-HVAC systems are commissioned such as electrical quality, transformers, security, communications, etc.) - Specialty: Very complex facilities like prisons. © 2010 National Air Balance Company, Inc. Confidential. Commissioning: Who Needs it and at What Cost? Estimating commissioning cost by floor area is a method often used for rough estimates. The cost estimate includes the cost of a commissioning agent from early construction through warranty for HVAC and controls, including lighting, but do not include low voltage grounding, infrared scanning, power quality, switchgear and transformer testing. The task performed include submittal review, construction observation, writing, overseeing and documenting functional test and reviewing staff training and O & M manuals. © 2010 National Air Balance Company, Inc. Confidential. Commissioning: Who Needs it and at What Cost? Commissioned System • HVAC and controls • Electrical system • HVAC, controls and electrical © 2010 National Air Balance Company, Inc. Confidential. Commissioning Cost • 2.0% to 3.0% of total mechanical cost • 1.0% to 2.0% of total electrical cost. • 0.5% to 1.5% of total construction cost Commissioning: Who Needs it and at What Cost? Estimates of Construction Phase Commissioning Costs $3.00 Commissioining Cost, $/sq. ft. $2.50 $2.00 $1.50 $1.00 $0.50 $0.00 0 50 100 150 200 250 300 350 400 450 500 550 600 Floor Area, Thousands of sq. ft. Simple Moderate Complex © 2010 National Air Balance Company, Inc. Confidential. Specialty • There are several things to consider when applying this cost such as construction duration, by project size, project meeting requirements, system complexity and LEED requirements. Commissioning: Who Needs it and at What Cost? • A Lawrence Berkeley National Laboratory (LBNL) study that meticulously compiles and standardizes commissioning data from 224 commercial building experiences-may help owners overcome this hesitancy. © 2010 National Air Balance Company, Inc. Confidential. Commissioning: Who Needs it and at What Cost? • This U.S. DOE-funded study concludes that commissioning is indeed cost-effective for both new and existing buildings over a range of facility types and sizes, not only in terms of energy savings but also in savings from improved equipment lifetimes, reduced maintenance, fewer contractor call-backs, and other nonenergy benefits. Investigators found that commissioning existing buildings achieved median energy cost savings of 15%, with payback periods of 0.7 years. © 2010 National Air Balance Company, Inc. Confidential. Commissioning: Who Needs it and at What Cost? The median payback time for new buildings was 4.8 years, and when non-energy impacts were factored in, those paybacks periods were considerably reduced, often to zero. Looking beyond individual building savings, the study suggests that widespread commissioning of existing commercial building could save the nation over $18 billion a year in energy costs alone. © 2010 National Air Balance Company, Inc. Confidential. Benefits of Commissioning • • • • • Improved efficiency Reduced change orders Improved maintainability Improved occupant comfort and productivity Reduced operating cost © 2010 National Air Balance Company, Inc. Confidential. Benefits of Commissioning • Improved Efficiency - Generally this is one of the easiest areas to substantiate. There is quite a bit of public domain information available that documents commissioning savings in new construction. • Reduced Change Orders - One of the more commonly acknowledged benefits of commissioning (especially design phase commissioning) is that the process will reduce the number of change orders encountered in a typical construction cycle. © 2010 National Air Balance Company, Inc. Confidential. Benefits of Commissioning • Improved Maintainability - Many commissioning related improvements simply make the system and equipment in a building easier to service and maintain. A design phase commissioning finding that makes an equipment room easily save tens of thousands of dollars any time the machinery in the room undergoes a major repair or replacement. - Improvements that make routine and maintenance services easier will also add up to significant savings over the life of a building. © 2010 National Air Balance Company, Inc. Confidential. Benefits of Commissioning • Improved Occupant Comfort & Productivity - There is growing evidence to show that improved occupant comfort translates directly to improved productivity. Improved productivity translates directly to an improved bottom line for most businesses. • Reduced Operating Cost - Commissioning related savings typically extend beyond the construction budget and will show up year after year as reduced operating and maintenance costs. © 2010 National Air Balance Company, Inc. Confidential. Questions & Answers © 2010 National Air Balance Company, Inc. Confidential.