BUILDING COMMISSIONING 101 David Overton Presentation Provided by: The Building Commissioning Association (BCA) What is the BCA? • The Building Commissioning Association is a nonprofit international organization formed in 1998, made up of over 600 members. Members include Cx providers, building owners, energy companies, facility managers, architects, engineers and contractors. • The BCA’s goal is to achieve the highest professional standards for commissioning practice, while allowing for the diverse and creative approaches to building commissioning that benefit our profession and clients. The BCA has established performance standards for commissioning (Essential Attributes) that all members have agreed to abide by when they serve as Commissioning Authorities. Understanding the Basic Commissioning Process What is Commissioning? What is Building Commissioning? “The Commissioning Process is a quality-oriented process for achieving, verifying, and documenting that the performance of facilities, systems, and assemblies meets defined objectives and criteria.” -- ASHRAE Guideline 0 • The process is performed specifically to ensure that the finished facility operates in accordance with the owner’s documented project requirements and the construction documents. • It begins in pre-design and continues through design, construction, and occupancy of the facility. Purpose of Building Commissioning It is BCA’s premise that: “ The basic purpose of building commissioning is to provide a quality based process with documented confirmation that building systems are planned, designed, installed, tested, operated and maintained in compliance with the Owner’s Project Requirements (OPR). Commissioning of existing systems may require the development of new functional criteria in order to address the owner’s current systems performance requirements.” Why is Commissioning Needed? Why do I need it? • Verification of Owner’s Project Requirements (OPR) • Health, safety, and indoor air quality • Peace of mind • Energy conservation and performance • Increased system complexity • Comfort control Don’t I already pay for that? • Design Professional Agreement – Doesn’t allow for “third set of eyes” from Cx – Doesn’t allow for quality control beyond field observations – May not have the same level of field experience • Construction Contract – Cx requirements not specified • • • • Doesn’t require formal Cx program Doesn’t include performance criteria Doesn’t include witnessed tests Not a condition for final acceptance Typical Project Team Configuration Up to the Mid 1970’s Mech Engineer Elec. Engineer Architect General Contractor Elec. Contractor Mech. Contractor Typical Project Team Configuration After the Mid 1970’s Mech Engineer Elec. Engineer Architect General Contractor Data/Security/Misc. Fire Alarm Gaps between disciplines resulting in: • Poor coordination • Lost details • Costly change orders • Delays in schedule Fire Protection Controls Contractor Elec. Contractor Mech. Contractor “..yeah, they’re substantiall y complete, but…” New Project Team Configuration with Commissioning Commissioning helps fill the gaps in coordination Commissioning encompasses “All” How does Commissioning help? • Sets clear measurable goals for everyone – Verifies owner’s requirements are being met throughout the design and construction phases • Establishes accountability – Changes the way people perform – Allows designers and contractors to measure success as well as deficiency How does Commissioning help? • Quality Process – Prevents/resolves problems – Designers focus on owner’s needs • • • • Discover/correct design issues early in design Improves specifications & design documents Reduces RFI’s & change orders Prioritize systems identified for early completion How does Commissioning help? • Contractors focus on quality work – Improves submittal process – Provides resource for MEP coordination prior to construction – Catch problems at the start of installation – Test finished work to verify proper operability – Interfaces builders with operators – Timely delivery of Systems/O&M materials – Creates team atmosphere and accountability How does Commissioning help? • Identifies issues & corrects deficiencies – Failed equipment – Improper installation – Poorly tuned controls/improper sequences – Design errors How does Commissioning help? • Improves – Energy performance – Comfort – Air quality – Occupant productivity – Equipment life – Maintainability – Facility staff preparedness The Commissioning Process Approaches • New Construction – Pre-design through occupancy • Existing Buildings – Retro-Commissioning • In existing, Un-Commissioned buildings – Re-Commissioning • In previously Commissioned buildings Systems to be Commissioned The scope of work is usually determined by the owner; however the following systems/equipment are typically included: • Mechanical Systems – – – – HVAC (Heating, Ventilation, Air Conditioning, Ducting & Accessories) Piping Systems (Pipe, Valves, instrumentation, etc.) Plumbing (Piping and Fixtures) DDC Controls (Software programming and Hardware) • Electrical Systems – Switchgear/Transformers – Grounding/Bonding – Lighting and lighting control • Specialty Systems – – – – Security and Fire Alarm Systems Voice/Data Systems Standby Power Systems Building Envelope The Commissioning Process The Commissioning Process involves steps that are integrated into every phase of the project: PRE-DESIGN DESIGN CONSTRUCTION OCCUPANCY & OPS Commissioning is NOT just testing at the end! Commissioning: Pre-Design Phase PRE-DESIGN DESIGN CONSTRUCTION OCCUPANCY & OPS • Document/Review Owner’s Project Requirements • Scope & budget for commissioning • Select Commissioning Authority • Create Commissioning Plan Commissioning: Design Phase PRE-DESIGN • • • • • DESIGN CONSTRUCTION OCCUPANCY & OPS Document/Review Basis of Design Refine scope of commissioning Perform Design Review Update Commissioning Plan Include commissioning requirements in construction documents – Including pre-functional checklists and functional performance test procedures Commissioning: Construction Phase PRE-DESIGN DESIGN CONSTRUCTION OCCUPANCY & OPS • Update Commissioning Plan & schedule • Review Submittals against Cx Plan, OPR, and BOD • Review control sequences • Update test procedures • Document construction observations • Develop Systems/O&M Manuals Commissioning: Construction Phase, cont. PRE-DESIGN DESIGN CONSTRUCTION OCCUPANCY & OPS • Training of O&M Personnel • Functional Performance Testing (FPT) • Documentation of deficiencies found during FPT’s • Deficiency correction and retesting • Final Report Commissioning: Occupancy and Operations Phase PRE-DESIGN DESIGN CONSTRUCTION OCCUPANCY & OPS • Assist with maintenance management program • Adjust for occupancy/warranty period • Off-season testing • Optional: Lessons-learned meeting • Optional: Periodic re-commissioning Fulfills LEED Certification Requirements Energy and Atmosphere Prerequisite 1 Fundamental Commissioning of the Building Energy Systems Requirements: 1. Designate Commissioning Authority (CxA) a. b. c. d. 2. 3. 4. 5. 6. CxA experienced in at least two building projects CxA independent of project design and CM—may be part of same company. CxA reports directly to owner. Small projects: acceptable to have CxA as part of design or construction team CxA reviews Owner’s Project Requirements and Basis of Design. CxA incorporates Commissioning (Cmx) requirements into Construction Documents CxA develop and implement Cmx Plan CxA verify the installation and performance of the systems to be Cmx. CxA to complete a summary Cmx report LEED template letter is provided stating items have been completed. Energy & Atmosphere Credit 3 Enhanced Commissioning Requirements: 1. Prior to start of Construction Document phase, designate independent CxA. a. CxA experienced in at least 2 building projects. b. CxA shall be: i. Independent of design and construction ii. Not an employee of design firm—may be contracted through them iii. Not an employee of CM iv. Can be a qualified employee or consultant of the Owner c. CxA report directly to the Owner d. Requirement has no deviation for project size. Energy & Atmosphere Credit 3 Enhanced Commissioning Requirements, continued: 2. CxA conducts (minimum) one Cmx design review of OPR and BOD and CD documents. Back-check the review comments. 3. CxA review selected contractor submittals for compliance with the OPR & BOD—concurrent with A/E reviews. 4. CxA assists in the development of the system manual for operating staff. 5. CxA verify requirements for training operating personnel and building occupants. 6. CxA shall be involved with reviewing building operation within 10 months after substantial completion/with staff and occupants. Include a plan for resolution of Cmx issues. Costs of Commissioning Estimated Commissioning Authority Costs to Owner for Construction and Occupancy/Operation Phases: Commissioned Systems HVAC and Controls (a) Electrical System (b) electrical HVAC, Controls and Light Electrical Total Commissioning Cost 2.0 to 3.0% of mechanical 1.0 to 2.0% of 0.5 to 1.5% of construction Sources: (a) Wilkinson, R. (2000). Establishing Commissioning Fees, ASHRAE Journal 42 (4):41-47. (b) PECI (2000). The National Conference on Building Commissioning Proceedings, Portland Energy Conservation Inc. OR. Printed in New Building Commissioning, 2003 ASHRAE Applications Handbook, 42.10 How The BCA Can Help • Member Directory (website) • Performance standards – Essential attributes – Elements of commissioning • Owner & Provider Training • Access to Qualified Providers • Eastern Canada Chapter • www.bcxa.ca 1400 SW 5th Avenue Suite 700 Portland, OR 97201 Phone: 877-666-BCXA (2292) E-mail: info@bcxa.org Web: www.bcxa.org