IEEE Transactions on Power Delivery, Vol. 13, No. 3, July 1998 712 A NEW CONCEPT IN CONSTRUCTION OF CABLE TERMINATIONS FOR MEDIUM VOLTAGES S .V. Nikolajevic, Member IEEE The Electric Power Distribution Co. Belgrade, Yugoslavia N.M. Pekaric-Nad R.M. Dimitrijevic Faculty of Technical Sciences University of Novi Sad, Yugoslavia The Cable Factory Jagodina, Yugoslavia Abstract This paper describes a new concept in construction of cable terminations for medium voltages. Layers with a high permittivity and embedded electrodes (EEs) were used. Three groups of configurations were examined. In the first group, the layer of high permittivity was placed partly over the cable insulation and partly over the cable screen. In the second group, the high permittivity layer (HPL) was placed partly over the cable insulation and partly under the semiconducting material, connecting with cable insulation screen. In the third group the cable screen was partly inserted into the H P L whose other part was placed over the cable insulation. The EEs were made in a shape of rings around the HPL. The rings were made either of copper tape or copper wire. Different positions of the EEs were examined. Numerical models of the cable terminations were used to monitor how the electric field changes as a function of the EE distance from the cable screen end. Finally, the new terminations were tested in a high voltage laboratory, according to the standards VDE 0278 and 1 L I I 1 I I Figure 1. The cable termination construction referred as K1. ( 1cable insulation, 2-high permittivity layer (HPL), 3-screen end, 4insulation of shrinking tube, 5-sheat of shrinking tube, 6-embedded electrode, EE, grounded (G),nongrounded (N)or absent (A)) 5 IEEE-404. I INTRODUCTION XLPE cables have been widely used for medium voltages for many years. Their h g h reliability has already been confirmed. The problem of cable terminations still remains incompletely solved. The cable terminations are supposed to have small dimensions and very good service characteristics. There is a number of cable terminations developed in last few years [l-61. Cable failures still happen, causing a great economic loss, mainly because of a cable termination breakdown. For that reason any improvement in the cable termination construction is of interest. Cable breakdown most often happens because of a strong electric field in the cable insulation, close to the cable screen end. Commonly, it is controlled by deflectorsdielectric cones, conventional stress relief cones. SRC. which are geometric solution to the problem. Cable termination constructions with layers of high resistivity or of high dielectric constant are also well known [ 2 ] . Recent papers [7,8] initiated a study of a new cable termination construction. The electric field at the cable termination was controlled by high permittivity material and embedded electrodes. The results were not completely satisfying, Figure 2. The cable termination construction referred as 11. ( 1- cable insulation, 2-high permittivity layer W L ) ,3-screen end, 4-insu1ation of shrinking tube, 5-sbeat of shrinking tube, 6-embedded electrode, EE, grounded (G), nongrounded or (A)) ~ m Figure 3.a. The cable termination construction referred as ET. ( 1cable insulation, 2-high permittivity layer (HPL), 3-screen end, 4insulation of shrinking tube, 5-sheat of shrinking tube, 6-embedded electrode, EE, grounded (G), nongrounded or absent (A)) I PE-893-PWRD-2-06-1997 A paper recommended and approved by the IEEE Insulated Conductors Committee of the IEEE Power Engineering Society for publication in the IEEE Transactions on Power Delivery.Manuscript submitted December 31, 1996; made available for Figure 3.b. The cable termination construction referred as I2M. ( 1printing June 6, 1997. cable insulation, 2-high permittivity layer (HPL), 3-screen end, 4insulation of shrinking tube, 5-sheat of shrinking tube, 6-embedded electrode, EE, grounded (G), nongrounded (N) or absent (A)) 1 0885-8977/98/$10.00 0 1997 IEEE Authorized licensed use limited to: National Cheng Kung University. Downloaded on May 28, 2009 at 09:23 from IEEE Xplore. Restrictions apply. 713 and further investigations were needed. In this paper a hybrid concept is introduced, involving both geometrical control of the electric field, the high permittivity material and embedded electrodes (EEs). Numerical models of different cable terminations were used to calculate and compare the influence of different constructions on electric field mitigation. were formed. Commercially available software was used for preprocessing and postprocessing of the data, as well as for the automated grid generation. The analyzed region was firstly divided into isoparametric triangular elements. The unknown variable, electric potential, V, was defined on the nodes of every element. Two dimensional Laplace's equation, div(-E grad V)=O U THE TERMINATION CONSTRUCTIONS A good cable termination should have no current leakage, no surface erosion and no discharges between the cable screen and the cable conductor. Main problem in the cable termination construction is the stress field reduction in the cable insulation, under the cable screen. Possible methods for the electric field regulation are: 1. geometrical, SRC [ I ] 2. non-linear resistive field grading coatings [6] 3. refractive field grading coatings [2] 4. combination of 2 and 3 [ 3 ] 5. capacitive method and 6. complex method (introduction of ferrite etc.) Introduction of a new concept in this work, is an effort to make a good hybrid of already existing methods. Three types of configurations (See Figs.1-3) were considered in this work: 1. The high permittivity layer (HPL) placed partly over the cable insulation and partly over the cable screen (Fig. 1 ). For simplicity, it shall be referred as K1. 2. The HPL placed partly over the cable insulation and partly under the semiconducting material, connected with cable insulation screen (Fig. 2). For simplicity, it shall be referred as 11. 3. The cable screen partly inserted into the HPL, whose other part was placed over the cable insulation (Fig. 3). For simplicity, it shall be referred as 12. was solved in cylindrical coordinates. The boundaries were defined by the phase conductor potential, V1=10 kV, and the screen ground potential V2=0. Equipotential map was calculated for each termination construction. The electric field was calculated fkom the corresponding potentials. The layers with different relative permittivity were examined. The analysis was performed with the EEs on the top of the HPL. The EEs were isolated or grounded. Different EE distances (denoted as L in Figs.1-3) from the screen end were examined too. Relative permittivities, Er, of some materials used for modeling the cable termination were as follows: Polyethylene 2.3, the HST 3.2, Semiconductive material 1000, Al, Cu 10000, the HPL 10.4 to 40.4. 1V. NUMERICAL RESULTS Numerical models for different termination constructions, (Kl, 11, I2), different relative permittivities of the HPL (typically between 20.4 and 40.4), ring construction and different ring position, L, were examined. All constructions were compared with a conventional stress relief cone, SRC. For a model of the SRC, illustrated in Fig. 5 , maximum electric field was calculated to be Emax=2.12 kV/mm, with an axial component of Emax=l.33 kV/mm. kablrl 600 Figure 4. The cable termination construction. The EEs were made of either copper tape or copper wire. Typically, the tape was 10 mm wide, with variable thickness, 0.2 mm to 1". The different diameters ( less than 2 mm) of wire were also examined. Different numbers of the EEs were considered, but one EE was found to be sufficient. In each configuration, the EEs were placed on the top of the HPL, under the heat shrinkable tube (HST), (See Fig. 4), except for the construction I2M, where the EEs were placed in the middle of the HPL, as illustrated in Fig. 3.b. The EEs were either grounded (G) or floating potential-nongrounded (N). The electric field reduction was monitored as a fbnction of the EE distance, L, from the cable screen end. [r 00 -30 0 10 0 50.0 7a.~ z nl NUMERICAL MODELS Numerical models, based on finite element method (FEM) for each of the above mentioned configurations Figure 5. Equipotential map of the stress relief cone as a cable termination. Legend in k V a-0.5, b-1, c-1.5, d-2, e-2.5, f-3, 8-3.5, h-4, i-4.5, j-5, k-5.5,1-6, m-6.5, n-7, 0-7.5, p-8, q-8.5, r-9, s-9.5, t-10. Authorized licensed use limited to: National Cheng Kung University. Downloaded on May 28, 2009 at 09:23 from IEEE Xplore. Restrictions apply. 714 These two values were taken as the upper limits. All new constructions were supposed to have field intensities lower than that. Numerical calculations had shown that all examined constructions reduced the maximum field, Emax, near the cable screen to: 0 1.99 kV/mm, HPL with ~r=20.4and 0 1.60 kV/mm, HPL with ~r=40.4. The differences between the constructions had a clear effect on the axial component of the electric field, Ez. For the different examined constructions and different EE distances, L, the greatest values of the Ez, E m a x , are illustrated in Figs. 6-9. The place of the greatest potential gradient is the location of the maximum total field, Emax, and it coincides with the location of the E m a x Figs. 10 and 11 represent the equipotential maps for the cable construction referred as 12T and I2M. In Fig. 10, the EE was placed on the top (T) of the HPL and in Fig. 11, the EE was placed in the middle (M). Both constructions similarly reduce the maximum field intensity, but the axial component of the field is better reduced in the case of I2M, as may be seen from Figs. 8 and 9. -12NT I s W 700 1" E lo" 20" I Figure 8. Cable termination E T with a grounded EE on the top ( of the HPL: Intensity of axial component of electric field as a function of the EE position, L-distance from the screen end. (SRC conventional stress relief cone, 12GT-the EE-grounded, IZNT-the EE nongrounded, The UA-without the EE.) I 1400 1200 1000 800 600 400 1" 3" 5" lo" 20" EE distance from the cable screen 1800 E 5: 5" 3" EE distance from the cable screen end E 4 K 1 A -R-SRC I 1700 I E E 1200 5 -KIM 4 1 2 A +SRC J!ieure Y. Cable termination U M C ; with grounded KK in the mid( le of the HPL: Intensity of axial component of electric field as a function of the EE position, L-distance from the screen end. (SRC conventional stress relief cone, UGM-the EE-grounded, 12NM-the EE nongrounded, The I2A-without the EE.) 0 1300 *I w 800 I" 3" 5mm lo" 20" EE distance from the cable screen Figure 6. The cable termination K1 with grounded EE on the top o. the HPL: Intensity of axial component of electric field as a function of the EE position, L-distance from the screen end. (SRC conventional stress relief cone, K1G-the EE-grounded. K1N-the EE nongrounded, The K1A-without the EE.) 400 ! lmm I 3mm 5miu lOmm 20mm EE distance from the cable screen 'igure 7.Cable termination I1 with grounded EE on the top of the HPL: Intensity of axial component of electric field as a function of the EE position-distance from the screen end. (SRC -conventional stress relief cone, I1G-the EE-grounded, I1N-the EE nongrounded, The 11A-without the EE.) z igure 10. Equipotential map of the new type, I2TG, cable termination with grounded EE, made of 0.2 mm thick, 10 mm wide copper tape. Legend in k V a-0.5, b-1, c-1.5, d-2, e-2.5, f-3, 8-3.5, h-4, i-4.5, j-5, k-5.5,I-6, m-6.5, n-7, 0-7.5, p-8, q-8.5, r-9, s-9.5, t-10. Authorized licensed use limited to: National Cheng Kung University. Downloaded on May 28, 2009 at 09:23 from IEEE Xplore. Restrictions apply. 715 VI EXPERIMENTAL RESULTS iznekr The examined configurations have passed the tests according to the standards. Some of those results and the results of some additional nonstandard tests are listed in Table 1. 35.a 30.0 i 25.Q +KIG ITI --.-KIN +KIA 20a 25 1 150 10 0 -I / ; - A 50 300 3511 450 u.0 500 -I z Figure 11. Equipotential map of the new type, I2MG, cab termination with grounded EE, made of 0.2 mm thick, 10 mm wide copper tape. Legend in kV: a-0.5, b-1, c-1.5, d-2, e-2.5, f-3, 8-3.5, h-4, i-4.5, j-5, k-5.5,1-6,m-6.5, n-7, 0-7.5, p-8, q-8.5, r-9, s-9.5, t-10. V. TESTING Based on numerical models, blends of the high permittivity material were prepared for the HPL. Relative permittivity was ~ ~ 4 0 . Dimensions 4. of the HPLs were: length 10 cm, thickness 1". The EEs were made in a shape of 0.2 mm thick copper tape. Samples of standard 10 kV cables were terminated by different types of terminations. Combination pairs of the tested terminations may be seen from the first column of the Table 1. The terminations were tested according to the German standard VDE 0278 and International standard IEEE-48. Additional examinations included voltage withstand tests, up to flashover or break down. The cable samples were exposed to the increasing voltage, starting from 40 kV, in 5 kV steps, in 5 min intervals. In the case of flashovers, the voltage was reduced by 5 kV and the cable samples were left at reduced voltage until breakdown occurred. The measurements, whose results are illustrated in Figs. 12-15, were performed with the cable open ended, conductor on potential V1=10 kV, and the screen grounded on both sides (V2=0). The top of the voltage probe was centered to the cable axis.. The effect of the cable termination construction was monitored by measuring the voltage using a probe. Fixed lcm probe movements were performed in axial direction, on the top of the HST. The probe voltages illustrated in Figs. 12-15 were plotted versus the distance from the cable screen end. Because of the insufficient input impedance of the instrument (Digital voltmeter, input impedance 10 MR. ) and considerable influence of the probe, the results of the measurements can be taken as a relative indicator only. Higher voltages and greater slope indicate a worse situation. Similar measurements were not possible for the conventional stress relief cone (SRC), because the conductive cover of the cone short-circuited the probe. o I 2 3 4 5 6 a 7 9 1 0 bistance from the screen end (cm) ~ ~~ Figure 12. The probe voltage (PV) vs. axial distance from the screen end for the cable termination construction Kl. (KlG-the EEgrounded, K1N-the EE nongrounded, The K1A-without the EE.) The distance of the EE from the cable screen, L=12 mm. -1 0 1 2 3 4 5 6 7 8 9 10 Distance from the screen end (cm) Figure 13. The probe voltage (PV) vs. axial distance from the screen end for the cable termination 11. (IlG-the EE-grounded, I1N-the EE nongrounded, The I1A-without the EE.) The distance of the EE from the cable screen, L=12 m a I 20 pv (VI ' m --I I 8 9 15 5 0 -1 0 1 2 3 4 6 6 7 10 Distance from the screen end (cm) Figure 14. The probe voltage (PV) vs. axial distance from the screen end for the cable termination E T . (I2GT-the EE-grounded, I2NT-the EE nongrounded, The I2A-without the EE.) The distance of the EE from the cable screen, L=12 mm. Authorized licensed use limited to: National Cheng Kung University. Downloaded on May 28, 2009 at 09:23 from IEEE Xplore. Restrictions apply. 716 Tested constructions, pairs examined Partial discharge Cycling heating t,,,=lOO°C 3 cycles at 30 kV satisfied Partial ADDITIONAL TESTS discharge (10 Voltage withstand UD to breakdown at 2U0=24kV (Voltage was increased from 40 kV, (max 20 pC) Q KlA,KlG5 (PC) at 2U0=24kV (max 20 pC) OpC KlG12, KlN12 lOpC(G)/ 20 PC(N) satisfied 2 PC(GY 4 PC(N) llG5,12GT5 2 pC satisfied 0 PC I1G12, 12GT12 2 PC satisfied 0 PC I2GT5, 12GM5 0 PC satisfied 0 PC IlG5, I2GM5 0 pC satisfied 0 PC IlA, 12A 0 PC satisfied 0 PC 11GT12, SRC 0 pC satisfied 0 PC SRC, SRC 0 PC satisfied 0 PC in steps of SkV, after each 5 min.) 0 PC breakdown of K1G5 at 75 kV, after 1 min (both passed 70 kV for 5 min) breakdown of KlG12 at 60 kV, after 2 min ( both passed 55 kV for 5 min) breakdown of I1G5 at 85 kV, 0 min (both passed 80 kV for 5 min) flashover of IlG12 at 85 kV after 3 min (both passed 80 kV for 5 min) breakdown of 11G12 at 75 kV after 80 min flashover of I2GM5 at 80 kV after 0 min, breakdown of I2GM5 at 75 kV after 10 min flashover of I2GM5 at 75 kV, breakdown of I2GM5 at 70 kV after 9 hours flashover of 12A at 85 kV after 3 min, (both passed 80 1 V for 5 min), breakdown of I1A at 75kV after 60 min. flashover of SRC at 55 kV after 0 min, breakdown of at SO kV after 150 min. flashover of SRC at 65 kV after 0 min, breakdown of at 60 kV after 120 min. The KlG5 (L=5 mm) had a breakdown at 75 kV,after 1 minute. The I1 configurations were found to be very good. They satisfied standard tests. With the EE grounded, as may be seen ffom Fig. 7, E m a x was always lower than in SRC. For L=12 mm the I1 configurations were able to stand 75 kV for 80 minutes. As may be seen from Table 1, one sample I1 G5 in a combination with the I2GM5 termination, was not destroyed after 540 minutes on 70 20 15 PV(V) 10 5 kV. 0 -1 0 1 2 3 4 5 6 7 8 9 1 0 Distance from the screen end (cm) igure 15. The probe voltage (PV) vs. axial distance from the screen end for the cable termination construction I2M. (UGM-the EEgrounded, I2NM-the EE nongrounded, The I2A-without the EE.) The distance of the EE from the cable screen. L=12 mm. As the value Ezmax=1,33 kVimm for the SRC was considered a limit, a new cable termination construction may be accepted O n l y if it has h e r l%"x value. Figures 12-15 may be used to judge which constructions may be considered better then the SRC. From all the tests it follows that * The K1 configuration appeared to be the poorest of the three examined in this work. From Fig. 6 it appears that the IClG configuration had Ezinax greater than the SRC. Although the standard tests were satisfied, the KlG12 (L=12 mm) had a breakdown at 60 kV, after 2 minutes. The 12T configurations were found to be very good. From Fig. 8 it may be seen that grounded EE kept Ezinax lower than in the SRC. The construction 12GT12 (for L=12 mm) was not destroyed after 80 minutes on 75kV. It passed standard tests successfully. The 12M configurations were found to be satisfactory. Froin Fig. 9 it can be seen that both grounded and nongrounded configurations had the E m a x lower than the SRC. The I2MGM5 configuration was able to staid 70 kV for 540 minutes. After breaking down, all terminations were examined, For the new-concept the signs of damage were found at the end of the HPL distant from the cable Screen end. In the case of the SRC, the breakdown occurred typically between the cable screen and the cable conductor. V11 DISCUSSION b T h e e configurations were analyzed: K1 -cable screen end partly covered with the HPL Authorized licensed use limited to: National Cheng Kung University. Downloaded on May 28, 2009 at 09:23 from IEEE Xplore. Restrictions apply. 717 11- cable screen end 1 cin on the top of the HPL 12 - cable screen end 1 cm on the top of the HPL, covered with another high permittivity wrap, 1 mm thick. Each configuration was analyzed with or without addition of the embedded electrode (EE). Two types of electrodes were considered: -copper wire ring (radius 0.5 mm to 2 mm) and -copper tape, 1 cm wide, 0.2 mm to 1 inm thick Greater diameter wire was not found to be suitable, because it introduced additional field disturbances. Grounded 0 . 6 m to lmm diameter wire and grounded tapes either 0.2” or 0.4 mm thick, had similar effects. Thicker tape produced 10% lower tangential field components. The EE were either grounded (G) or floating potential nongrounded (N). Grounded EEs were generally found to be better than nongrounded. They moved the strongest electric field away from the cable insulation and reduced the slope of the field rise near the cable screen end (See Figs. 12-15). Typically, relative permittivity, Er, of the HPL was 40.4, but 20.4 was also considered. The lower permittivity was acceptable for maximum field reduction, but higher permittivity was more efficient for suppression of the tangential field components. By introduction of grounded EE, the worst electric stress moved away froin the screen end. Grounded EEs made the field rise slower. The breakdown in the new construction terminations occurred at the end of the HPL, which could be made longer if needed. In the SRC terminations the breakdown occurred always at the screen end. According to the numerical calculations (Figs. 6-9) and the results of measurements (Figs. 12-15), it was expected that the constructions I2GM might bc the best of all. This configuration was found to be satisfactory, but, judging from the Table 1, the configurations I1G and I2GT were found to stand more severe conditions. VI11 CONCLUSIONS If compared by intensity of maximum electric field and its axial component, some of considered new construction cable terminations were found to reduce the electric stress better (25%) than standard stress relief cones, SRC. The new concept cable terminations represent a hybrid solution for the cable end electric stress reduction. They involve high permittivity material, but also make use of geometrical relaxation of the field. The constructions I1G and I2GT were found to be the most serious candidates for the new generation cable terminations. Their advantages over the SRC were in reducing the axial component of the electric field and in channeling the worst electric stress away froin the cable screen end to the HPL. 1X REFERENCES [ 11. McPartland, J.F. Handbook of practical electrical design, McGraw-Hill Inc., 1984, pp. 9.25-9.30 [2]. Nelson, P.N., Hervig, H.C., “High dielectric constant materials for primary voltage cable terminations”, IEEE Trans. Vol. PES-103, Nov. 1984, pp 3211-3216. [3]. Andersen, O.W. “Laplacian electrostatic field calculations by finite elements with automatic grid generation”, IEEE PES Winter Meeting, New York, 1973. [4]. Blake, A.E. et al. ”Improvements in stress control materials”, 7th IEEE/PES Transmition and Distribution Conference, April, 1979. [ 5 ] . Weedy, B.M. and Turvey, N.J. “Resistive stress relieving materials for XLPE cable joints”, Second IEE Conf. on PCA 1OkV to 180 kV, 1986 [6]. Virsberg, L.G. and Ware, P.H.”A new termination for underground distribution”, IEEE Trans. PAS, Sept. 1967 [7].Nikolajevic S. et al. “Optimization of cable terminations” IEEEPES Summer Meeting, Denver, 1996. SM 369-9-PWRD [8]. Nikolajevic, S.V. et al. “Modeling of cable terminations with embedded electrodes, Proc. of the IEEE Int. Symp. on Electrical Insulation, Montreal 1996, pp 703-706 X. BIOGRAPHY Stojan V. Nikolajevie was born in village Vucadelci near Surdulica in Yugoslavia, 1944. He received the B.S., M.S. and Ph.D. degrees from the Faculty of Electrical Engineering, University of Belgrade, in 1968, 1974 and 1987 respectively. In 1968 he joined the Cable Factory, Svetozarevo-Jagodina. In 1994 he joined the Electric Power Distribution Company, Belgrade. His work has been in areas of construction, testing and cable service. Currently he is an Assistant Professor of Faculty of Electrical Engineering, University of Belgrade. Neda M. Pekaric-Nadj was born in 1954 in Novi Sad, Yugoslavia. She received the B.S. degree in 1978 from the Faculty of Technical Sciences, University of Novi Sad, and M.S. and Ph. D. from the Faculty of Electrical Engineering, University of Belgrade, in 1981 and 1984 respectively. She joined the Faculty of Technical Sciences, University of Novi Sad, in 1978 as a teaching assistant. Currently she is an Associated Professor teaching an introductory course in Elecrotechnics. Her work is in connection with electric and magnetic fields calculation. Radisa Dimitrijevic was born in 1961 in Jagodina. He received the B.C. degree in 1986 from the Faculty of Electrical Engineering, University of Belgrade. Since then he has been with the Research Center of the Cable Factory, Jagodina. His work is in connection with cable accessories development. He is working towards his M.S. degree at the Faculty of Electrical Engineering, University of Belgrade. Authorized licensed use limited to: National Cheng Kung University. Downloaded on May 28, 2009 at 09:23 from IEEE Xplore. Restrictions apply.