UWM CIO Office Demand and Manufacturing Process Improvement DOE Industrial Assessment Center (IAC) Guorong Chen 07/2012 UWM CIO Office Agenda 1. Electricity Usage and Charge – – – – – 1.1 Demand Charge 1.2 Power factor 1.3 Load factor 1.4 Load Shifting 1.5 Heating/Cooling Degree Days 2. Manufacturing Process Improvement – 2.1 Reduce Setup/Changeover Time – 2.2 Waiting for More Unfinished Goods – 2.3 Production System Improvement UWM CIO Office Total Consumption 1. Electricity Usage and Charge (for example) 1,521,686 kWh Customer Demand 5,475.80 kW $1.007/kW On-Peak Consumption 595,915 kWh Customer Demand Rate Off-Peak Consumption 925771 kWh On-Peak Demand Rate $10.882/kW On-Peak Demand On-Peak Energy 4,419,800 kW Rate $0.06985/kWh Off-Peak Demand 3,767,000 kW Off-Peak Energy Rate $0.04974/kWh On Peak Period 10am - 10pm Heating Degree Days 1,142 UWM CIO Office 1.1 Demand Charge • "Demand": total amount of electricity being used by a consumer at any one time, measured in kilowatts (kW). • If a time-of-use rate is applied, there will be two peak demands -- one for on peak and one for off peak. • The on-peak demand time, 10am – 10pm in the example, may vary by season. Electricity used outside of these time periods, before 10am or after 10pm in this example, is considered off peak. • Peak demand: the highest average kW measured in a 15-minute interval during the period. UWM CIO Office 1.1 Demand Charge (cont.) How does the on-peak demand affect the customer’s electric bill? 1. A customer runs a 50 horsepower (hp) pump for only five hours from 10am to 3pm during this month: Demand Charge = 50 hp x .746 kW/hp x $10.882/kW = $405.90 Energy Charge = 50 hp x .746 kW/hp x 5 Hr x $0.06985/kWh = $6.34 2. Same customer runs a 50 hp pump constantly through the entire month: Demand Charge = 50 hp x .746 kW/hp x $10.882/KW = $405.90 Energy Charge = 50 hp x .746 kW/hp x (372 Hr x $0.06985/kWh+372 Hr x $0.04974/kWh) = $1,659.38 UWM CIO Office 1.1 Demand Charge (cont.) Energy companies reserve the right on how to calculate the average demand. Peak demand for this 45-minute period will be 1,600 kW, not 1,800 kW. UWM CIO Office 1.1 Demand Charge (cont.) • It is guarantee to reduce demand only when the electric devices run continuously during on peak hours on every work day, since the peak demand will occur at any time and any day. • Electric devices, such as light bulbs, run 10 hours during on-peak hours (there are 12 on-peak hours in our example)? • How about if they run 24 hours a day but only 4 days a week (assume the plant works 5 days a week)? • Demand may be reduced, but not guaranteed. UWM CIO Office 1.1 Demand Charge (cont.) There are many ways to manage demand, ranging from manual controls and time-clocks to sophisticated automatic units that program buildings and processes. • Motor is the correct size for your pump. An oversized motor could increase demand and cost money. A newer, more efficient pump and motor combination may be available that would save on demand and energy. • Pump and motor combination is the correct size for your system. If you are using a 75 hp pump when a 50 hp pump would do the job, you are wasting 25 hp or 18.7 kW of demand. (25 hp x .746 kW/hp = 18.7 kW) • Worn pumps, motors, nozzles, and leaks are not increasing flow to the point where demand has increased. UWM CIO Office • 1.1 Demand Charge (cont.) Considerable savings can be realized by monitoring power use and turning off or reducing non-essential loads during high power use periods. • Maximum Demand Controller is a device designed to meet the need of industries conscious of the value of load management. UWM CIO Office 1.1 Demand Charge (cont.) Alarm is sounded when demand approaches a preset value. If corrective action is not taken, the controller switches off non-essential loads in a logical sequence. This sequence is predetermined by the user and is programmed jointly by the user and the supplier of the device. The plant equipment selected for the load management are stopped and restarted as per the desired load profile. Demand control scheme is implemented by using suitable control contactors. Audio and visual annunciations could also be used. UWM CIO Office 1.1 Demand Charge (cont.) How much will demand charge increase if the1,800 kW continues until 10:45am? The peak demand will be 1,800 kW rather than 1,600 kW. The peak demand increase will be 200 kW and monthly demand charge will increase by 200×10.882=$2,176.40. In another word, turning off non-essential machines for 7.5 minutes can reduce demand charge by $2,176 in one month. UWM CIO Office 1.1 Demand Charge (cont.) • Be aware of when your meter is read each month. If you only run your pump for a day or two during a billing period (for example, at the beginning or end of the year) your demand cost could far exceed your energy cost. If possible, run equipment that is operated infrequently during a billing month when you’ve already incurred a demand charge for that month. For example, you want to test your irrigation system in the spring, instead of waiting until you need it on a hot day in July, only to discover that it's not running properly. You know that your meter is read on the 25th of each month. If you haven't used the system during the first part of the month, you may want to wait until after the meter is read for the month to test the system. While you’re testing your system, and running your pump motor, you will be billed for the energy used by the irrigation system, plus a demand charge for the entire month. By waiting a few days, you could move that demand charge into a month when you'll be using the irrigation system anyway, saving an extra month's demand charges. UWM CIO Office 1.1 Demand Charge (cont.) • For the average commercial building, the best control over electrical demand may not be in the electric system, but in the building itself. • Good thermal design-tight construction, good window design, and appropriately sized ventilation systems- is the key to limiting demand and avoiding demand charges. UWM CIO Office 1.2 Power Factor Power factor: a unitless quantity, the ratio of the real power flowing to the load to the apparent power in the circuit. To understand power factor, visualize a horse pulling a railroad car down a railroad track. Because of the angle of the horse’s pull, not all of the horse’s effort is used to move the car down the track. The sideways pull of the horse is wasted effort or nonworking (reactive) power. UWM CIO Office 1.2 Power Factor (cont.) Because of the costs of larger equipment and wasted energy, electrical utilities will usually charge a higher cost to industrial or commercial customers if power factor is less than a specific level, such as 0.95. Uncorrected power factor will cause power losses in distribution system, which may result in voltage drop. Excessive voltage drops can cause overheating and premature failure of motors and other inductive equipment. UWM CIO Office 1.2 Power Factor (cont.) • Causes that may be attributed for low power factor: 1. Inductive loads. Especially lightly loaded induction motors, and transformers. 2. Induction Furnaces 3. Arc Lamps and arc furnaces with reactors. 4. Fault limiting reactors 5. High Voltage • Opportunities to improve power factor: 1. Add consumers of reactive power in the system like Capacitors or Synchronous Motors. 2. Using fully loading induction motors and transformers, and higher rpm machines. 3. Using automatic tap changing system in transformers. UWM CIO Office 1.2 Power Factor (cont.) Various types of automatic power factor controls are available with relay/microprocessor logic. Two of the most common controls are: Voltage Control and kVAr Control. UWM CIO Office 1.3 Load Factor UWM CIO Office 1.4 Load Shifting Load shifting involves moving load from on-peak to off-peak periods. Popular applications include: use of storage water heaters, storage space heaters, cool storage and customer load shifts to take advantage of time-of-use or other special rates. UWM CIO Office 1.4 Load Shifting For example, one of the frequently considered examples in IAC assessments is to charge forklift batteries during off-peak hours. UWM CIO Office 1.5 Heating/Cooling Degree Days Degree days are essentially a simplified representation of outside airtemperature data. "Heating degree days" are a measure of how much (in degrees), and for how long (in days), outside air temperature was lower than a specific "base temperature" (or "balance point"). They are used for calculations relating to the energy consumption required to heat buildings. "Cooling degree days“ are a measure of how much (in degrees), and for how long (in days), outside air temperature was higher than a specific base temperature. They are used for calculations relating to the energy consumption required to cool buildings. UWM CIO Office 2. Manufacturing Process Improvement IAC assessments could be more effective if additional efforts were put into direct productivity issues. Implementation of most ARs is expected to be immediate. UWM CIO Office 2.1 Reduce Setup/Changeover Time Example: After installing a rotating nozzle carousel, a company is expected to save $60,750 per year while the implementation cost is merely $4,200 and payback period is one month. The company makes metering pumps about 15 pumps an hour with sales $85,000,000. The pump models differ by size and the nozzle has to be changed and repositioned every time there is a change of a pump size, which takes an operator about 5 minutes. The fix of the problem consisted of rotary mounting hardware making it adaptable to different types of pump cylinders. UWM CIO Office 2.1 Reduce Setup/Changeover Time (cont.) ACS = Annual Cost Savings = Net Sales Increase ACS = (# of pieces/hr) x (value per piece - material cost per piece) x (time saved) x (# of changes/yr) ACS = (15 pieces/hr) x ($950/piece - $500/piece) x (4.5 minutes) x (1/60 hr/min) x 10 x 12 ACS = $60,750/year Implementation requires the manufacture and installation of the nozzle carousel ($1,200). The cost of material was estimated at $800 and labor at $400. It was recommended to buy an extra set of nozzles as a backup in case of failure of existing ones, which are estimated to be $1,800. Total implementation cost will be $4,200. There are other ways to reduce setup/changeover time, such as add more operators to set up machines. UWM CIO Office 2.2 Waiting for More Unfinished Goods If a high power consumption process works faster than the upstream process, it may benefit to wait for more unfinished goods from upstream and turn it off or to a low power consumption state. Example: B (20 parts/hr) Total: 150 parts 30 parts A (25 parts/hr) 0 1.5 7.5 time (hr) UWM CIO Office 2.2 Waiting for More Unfinished Goods (cont.) Then 1.5 hours of A’s running time will be saved. AES = 200×1.5×5×50 = 75,000 kWh ACS = 75,000×0.05 = $3,750 (assume average electricity rate is $0.05/kWh). While machines can be idle, workers must not be because the cost of manpower is generally far higher than the cost of amortizing machines. Therefore the cost savings will be much higher if manpower saving is also considered. However, pay attention to the warm-up/set-up time, space to store upstream parts, and feasibility of waiting in practice. UWM CIO Office 2.3 Production System Improvement In this production system, behavior is affected by RANDOM events: machine breakdowns. The following is one basic type of production system, where the circles represent the producing units and rectangles are the material handling devices: The producing units may be individual machines or operators. The material handing devices may be boxes, or conveyors, or automated guided vehicles, or even empty space. UWM CIO Office 2.3.1 Analysis and Improvement Using the mathematical model of a production system, the following problems can be solved: (1) Evaluation of production rate, throughput, work-in-process, blockage, starvation, etc. (2) Investigation of “what if” scenarios: how will the system performance change if some parameters are changed? (3) Direction for improvement: provide improvement recommendation based on the consideration of more effectiveness, low implementation cost, and feasibility. UWM CIO Office 2.3.2 Steps of Modeling (1) Layout investigation (2) Structural modeling (3) Machine parameter identification (4) Buffer parameter identification (5) Model validation UWM CIO Office 2.3.3 Data to Collect 1. For all the machines, the duration of each occurrence of up time and down time must be recorded during a sufficiently long period of time. 2. The number of parts produced during this period and the cycle time of the machines. 3. The buffer capacity should also be estimated based, for instance, on carrier size, the number of carriers, available space, conveyor speed, etc. UWM CIO Office 2.3.4 Model Validation To validate the model, we can compare the production rate calculated using the model with that measured on the factory floor. If the error is within 5-6%, the model is considered validated. Otherwise, the above process should be repeated anew. UWM CIO Office 2.3.5 Case Study (1) Automotive ignition coil processing system (2) Model Validation UWM CIO Office 2.3.5 Case Study (cont.) (3) “What-IF” Scenario Analysis (a) Eliminating starvations by pallets (sufficient pallets will be provided to operation 1): Conclusion: Since the improvement is just about 1%, the system modification by adjusting the number of pallets is not an effective way for continuous improvement. UWM CIO Office 2.3.5 Case Study (cont.) (b) Increasing buffer capacities Conclusion: Increasing the capacity by 50% leads to about 6% - 7% of throughput improvement, while further increases have practically no effect. Thus, increasing (perhaps, only some of the) buffer capacities may be an effective way for system improvement. UWM CIO Office 2.3.5 Case Study (cont.) (c) Increasing efficiency of m9-10 Conclusion: increasing the efficiency of machine m9-10 leads to a reasonable improvement in system productivity. UWM CIO Office 2.3.5 Case Study (cont.) (d) Increase machine uptime or downtime Performance with increased machine uptime Performance with decreased machine downtime Conclusion: decreasing Tdown is more effective than increasing Tup. UWM CIO Office 2.3.6 PSE Toolbox UWM CIO Office Thank you! UWM CIO Office Reference 1. http://www.mge.com/about/electric/glossary.htm#l 2. http://www.wrcc.dri.edu/cgi-bin/cliGCStH.pl?casjos 3. Productivity Manual. 4. J. Li and S. M. Meerkov, Production Systems Engineering. Springer, 2009. 5. en.wikipedia.org 6. http://www.advancedenergy.org/progressenergy/usage_ vs_demand.html 7. http://www.em-ea.org/Guide%20Books/book-3/Chapter%203.10ENERGY%20EFFICIENT%20TECHNOLOGIES.pdf UWM CIO Office Supplement 1. What is reactive demand? For example, “this provision requires that a customer be billed for the highest 15-minute integrated kVA of lagging reactive demand established during the month less 1/3 of the highest 15-minute kW demand during that month. In simpler terms, a customer is billed for having a power factor that is less than 95% at the rate of $0.83/RkVA.” UWM CIO Office Supplement 2. Power Factor Measurement Power factor in a single-phase circuit (or balanced three-phase circuit) can be measured with the wattmeter-ammeter-voltmeter method, where the power in watts is divided by the product of measured voltage and current. The power factor of a balanced polyphase circuit is the same as that of any phase. The power factor of an unbalanced polyphase circuit is not uniquely defined. UWM CIO Office Supplement 3. What are inductive loads and capacitive loads? Inductive loads such as transformers and motors (any type of wound coil) consume reactive power with current waveform lagging the voltage. Capacitive loads such as capacitor banks or buried cable generate reactive power with current phase leading the voltage. Both types of loads will absorb energy during part of the AC cycle, which is stored in the device's magnetic or electric field, only to return this energy back to the source during the rest of the cycle. For example, to get 1 kW of real power, if the power factor is unity, 1 kVA of apparent power needs to be transferred (1 kW ÷ 1 = 1 kVA). At low values of power factor, more apparent power needs to be transferred to get the same real power. To get 1 kW of real power at 0.2 power factor, 5 kVA of apparent power needs to be transferred (1 kW ÷ 0.2 = 5 kVA). This apparent power must be produced and transmitted to the load in the conventional fashion, and is subject to the usual distributed losses in the production and transmission processes. UWM CIO Office Supplement 4. What is time-of-use pricing? Time-of-use pricing (TOU pricing): electricity prices are set for a specific time period on an advance or forward basis, typically not changing more often than twice a year. Prices paid for energy consumed during these periods are pre-established and known to consumers in advance, allowing them to vary their usage in response to such prices and manage their energy costs by shifting usage to a lower cost period or reducing their consumption overall. UWM CIO Office Supplement 5. How to calculate heating degree days? Heating Degree Day units are computed as the difference between the base temperature and the daily average temperature. (Base Temp. Daily Ave. Temp.) Base temperature is the outside temperature above which a building needs no heating. One unit is accumulated for each degree Fahrenheit the average temperature is below the base temperature. Negative numbers are discarded. Example: If the day’s high temperature was 65 and the low temperature was 31, the base 50 heating degree day units is 50 - ((65 + 31) / 2) = 2. This is done for each day of the month and summed. UWM CIO Office Supplement 6. What is Synchronous Motor? A synchronous electric motor is an AC motor in which the rotation rate of the shaft is synchronized with the frequency of the AC supply current; the rotation period is exactly equal to an integral number of AC cycles. Synchronous motors contain electromagnets on the stator of the motor that create a magnetic field which rotates in time with the oscillations of the line current. The rotor turns in step with this field, at the same rate. UWM CIO Office Supplement Another way of saying this is that the motor does not rely on "slip" under usual operating conditions, and as a result produces torque at synchronous speed. Synchronous motors can be contrasted with induction motors, which must slip in order to produce torque. The speed of the synchronous motor is determined by the number of magnetic poles and the line frequency. Synchronous motors are available in sub-fractional self-excited sizes to high-horsepower direct-current excited industrial sizes. In the fractional horsepower range, most synchronous motors are used where precise constant speed is required. In high-horsepower industrial sizes, the synchronous motor provides two important functions. First, it is a highly efficient means of converting AC energy to work. Second, it can operate at leading or unity power factor and thereby provide power-factor correction. UWM CIO Office Supplement 7. More about Automatic Power Factor Controllers • Voltage alone can be used as a source of intelligence when the switched capacitors are applied at point where the circuit voltage decreases as circuit load increases. Generally, where they are applied the voltage should decrease as circuit load increases and the drop in voltage should be around 4 – 5 % with increasing load. Voltage is the most common type of intelligence used in substation applications, when maintaining a particular voltage is of prime importance. This type of control is independent of load cycle. During light load time and low source voltage, this may give leading PF at the substation. UWM CIO Office Supplement • Kilovar sensitive controls are used at locations where the voltage level is closely regulated and not available as a control variable. The capacitors can be switched to respond to a decreasing power factor as a result of change in system loading. This type of control can also be used to avoid penalty on low power factor by adding capacitors in steps as the system power factor begins to lag behind the desired value. Kilovar control requires two inputs - current and voltage from the incoming feeder, which are fed to the PF correction mechanism, either the microprocessor or the relay. UWM CIO Office Supplement • Automatic Power Factor Control Relay controls the power factor of the installation by giving signals to switch on or off power factor correction capacitors. Relay is the brain of control circuit and needs contactors of appropriate rating for switching on/off the capacitors. There is a built-in power factor transducer, which measures the power factor of the installation and converts it to a DC voltage of appropriate polarity. This is compared with a reference voltage, which can be set by means of a knob calibrated in terms of power factor. When the power factor falls below setting, the capacitors are switched on in sequence. The relays are provided with First in First out (FIFO) and First in Last Out (FILO) sequence. The capacitors controlled by the relay must be of the same rating and they are switched on/off in linear sequence. To prevent over correction hunting, a dead band is provided. This setting determines the range of phase angle over which the relay does not respond; only when the PF goes beyond this range, the relay acts. UWM CIO Office Supplement When the load is low, the effect of the capacitors is more pronounced and may lead to hunting. Under current blocking (low current cut out) shuts off the relay, switching off all capacitors one by one in sequence, when load current is below setting. Special timing sequences ensure that capacitors are fully discharged before they are switched in. This avoids dangerous over voltage transient. The solid state indicating lamps (LEDS) display various functions the operator should know and also and indicate each capacitor switching stage. • Intelligent Power Factor Controller (IPFC) determines the rating of capacitance connected in each step during the first hour of its operation and stores them in memory. Based on this measurement, the IPFC switches on the most appropriate steps, thus eliminating the hunting problems normally associated with capacitor switching. UWM CIO Office Supplement General Rules of Thumb: • The average cost of electricity is $0.05/kWh ($15/MMBtu). • There are 2000 hours per year per shift (based on the assumption that one shift is 8 hours per day, 5 days per week, 50 weeks per year). • Switching from electric heat to natural gas or #2 fuel oil can reduce heating costs by 78%. • Average cost savings for demand reduction: By shifting an operation to off-peak hours, the following savings are achieved: $75/Hp/year. • The average benefit of shifting other electrical equipment to offpeak hours is: $120/kW/year.