Standard Design Requirements

advertisement

Standard Design Requirements

DATED OCTOBER 2013

GENERAL DESIGN REQUIREMENTS

Existing Conditions

ASBESTOS: a. Existing piping may be insulated with materials containing asbestos fibers. Various ceilings and walls throughout facilities may contain asbestos materials. Remove all asbestos containing materials from the portion of the structure within the project limits. If an entire building is within the project limits, the building will be certified asbestos free by written documentation at projects’ end. b. Use no asbestos containing materials in renovations or new construction. Submit the appropriate notarized certification certificate stating that no asbestos containing materials were used in the renovation, construction, or placed on the job site.

STRUCTURAL: c. Correct or replace by renovation any portions of the roof and floor structure that are structurally unsound. d. Identify, and include, in the project any brick needing repair, caulking, sealing, or tuck-pointing.

Space Requirements

a. Design internal spaces to permit flexibility. Consider floor heights, loading, atmospherics, lighting, accessibility, security, economical building module, HVAC, etc. b. All new or renovated mechanical equipment rooms shall be of adequate size to ensure proper headroom and provide for removal of all equipment components without encountering any architectural or equipment barriers. c. All mechanical rooms to have an adjacent maintenance storage room of not less than 50 square feet. d. Each new or renovated custodial closet shall be a minimum of 50 square feet. Include a minimum of one closet per 10,000 square feet of gross building space and a minimum of one closet per floor. Locate closets near restrooms. The rooms shall not be entrances to mechanical rooms, roof hatches, or other spaces. e. Provide a main custodial closet near an accessible entrance, delivery area, or elevator of a minimum of

100 square feet. Design space for the storage of all equipment and a thirty (30) day supply of cleaning supplies. f. Provide each building with a custodial personnel break area. g. Install or relocate telephone switchgear in a separate telephone equipment room not in custodial closets or mechanical equipment rooms. Telecommunication closets are required in each quadrant of the facility

(See Telecommunications section for details.) h. Provide a hallway / alcove space 48” deep by 40” wide for each vending machine. i. Provide each building with a recycling room near a delivery area easily accessible from the interior and exterior of the building.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 1 of

SECTION B DETAILED UNIVERSITY REQUIREMENTS

CAMPUS PLANNING and DESIGN:

Drawing and Schedules

a. All project drawings to be CAD based and compatible with the University’s AutoCAD based system. b. Schematic and design-development floor plans shall indicate furniture and equipment. Submit printed copies of drawings and AutoCAD compatible drawing files for University review. c. Working drawings to be of appropriate scale to accurately represent building dimensions, features, materials, and construction. Follow architectural graphic standards, including final and/or “AS-BUILT

CAD files and PDF formats on compact disk. Maximum size of drawings shall not exceed 30” x 42”.

Submit full size drawings and AutoCAD compatible drawing files for University review. d. All project design-development drawings and documentation to reflect spaces numbered according to

The University of Memphis Room Numbering standard procedure memorandum dated 1/4/99, attached to the end of this document. e. Submit a monthly design progress schedule to indicate progress and future completion deadlines.

Regulatory Requirements

a. Provide for fire extinguishers and cabinets in General Contract. b. Give special attention to site controls and temporary facilities. The type of construction will dictate control of the phasing of work and use of surrounding site during construction, etc. c. Comply fully with the Americans with Disabilities Act (ADA), including handicapped access around site. d. Design to meet requirements of Zone 3 Seismic Design as locally amended. All buildings on The

University of Memphis campus will use an acceleration factor of 0.2 or greater. e. Ensure fire emergency access. Schedule a site review meeting with local fire department during schematic design phase. f. Comply with the Tennessee Code for Energy Conservation in New Building Construction , 1978.

Submittals

a. All submittals and shop drawings to be reviewed and approved by the University before final approval of the Designer. b. Provide 3 copies of all submittals, shop drawings, and maintenance / operating manuals.

Contract Close-out

a. Before the University takes control of the building, clean all areas and sanitize the restrooms with a disinfectant approved by the University’s’ Custodial Services. b. All windows shall be cleaned, free of dust, dirt, fingerprints, and smudges. c. Clean and finish the hard floor surfaces with 4 to 6 coats of a high gloss, slip resistant floor finish approved by the University’s Custodial Services. d. All horizontal and vertical surfaces to be clean and dust free. All carpet shall be free of spots, dirt, dust, and visible loose debris. e. Final records documents to completely and accurately reflect “As Built” conditions including all project changes and approved field modifications. Submit full size printed copies of proposed record drawings, documents, and AutoCAD drawing files for University review and approval before submitting final record documents. Final record documents to reflect all changes required by the previous submission and include: 3 complete copies of all record documents; 2 sets of archival processed 35mm roll format microfilm copies of all record documents; 1 set of full sized photo processed, image stabilized, polyester reproductions (mylars) of all drawings; 1 set of the negatives for the photo processed reproductions of all drawings, and 2 copies of AutoCAD compatible drawing and x-referenced drawing files of all drawings on

Compact Disk or DVD.

Facility Operation Procedures

1. Provide pertinent training, orientation, instructions, and assistance – by manuals, specifications, or professionally prepared materials and/or upgrades - to the appropriate personnel on the operation, maintenance, and troubleshooting of all of heavy-duty equipment, HVAC systems, boilers, generators, cooling systems, computer equipment and software, devices, and controls provided under this contract.

2. Provide additional materials to augment the Operating and Maintenance Data binders with instructions for adding these to the binders, or full complete replacement binders.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 2 of

Subsurface Investigation:

1. Tennessee One Call system does not cover the location of all utilities on The University of Memphis campus.

2. Contractor is ultimately responsible for field location of all known utilities and the repair of any form of damage or power / communication outage caused by Contractors’ work. Type and method of repairs to be approved by Physical Plant. Repairs to be made within 24 hours. Any utility not indicated on the

University’s utility or telecommunication plans will not be Contractor's responsibility to repair if damaged by his work.

3. For utilities not covered by the Tennessee One Call System, Physical Plant provides utility plans showing the general location of known electrical, water, gas, sewer, and irrigation lines. Depth and exact location of utilities are not always provided on the University utility plans. Field-verify all University utility plans. Report and document any discrepancies to Physical Plant.

4. Telecommunications has plans showing general locations of known phone or fiber optic cables. Depth and exact locations not always provided on University telecommunication plans. Field-verify ALL utility plans.

5. Utility Markings – If the University marks the locations of existing utilities and they are then damaged or cut, then the responsibility for paying for repairs is the Contractor’s; also the Contractor is to maintain the markings.

CUSTODIAL:

Custodial Closets

a. Custodial closets to have four shelves, a floor service sink and 120-volt electrical outlet (20 amp) capable of charging battery powered floor machines. b. All closet doors to swing out or not interfere with required clearances/floor areas. c. The custodial break area (1 per building) to have HVAC, lighting, electrical outlets, a sink with hot and cold water, and a shelf.

Custodial Contract Close-out

a. Before the University takes control of the building, clean all areas and sanitize the restrooms with a disinfectant approved by the University’s’ Custodial Services. b. All windows shall be cleaned, free of dust, dirt, fingerprints, and smudges. c. Clean and finish the hard floor surfaces with 4 to 6 coats of a high gloss, slip resistant floor finish approved by the University’s Custodial Services. d. All horizontal and vertical surfaces to be clean and dust free. All carpet shall be free of spots, dirt, dust, and visible loose debris.

LANDSCAPING:

Final landscape design to be approved by the University. Include all landscaping and irrigation systems in base

Construction Contract.

Campus existing plant material varies widely. A broad base of material is good. General guidelines for the placement of plant material around new and existing buildings will create a consistent campus image.

Some broad guidelines for plant material choices are:

Native plants that are hardy in Zone 7.

Plan for mature size of plants.

Availability of plants in this area.

Specific, desirable plant materials for the campus are:

Large Trees - Willow Oak, Water Oak, Pin Oak, or Red Maple.

Large Accent Trees - Kentucky Coffee Tree, Yellowwood, Eastern Red Cedar, or Ginkgo.

Small or Flowering Trees - Zelchova, Fringe Tree, Goldenrain Tree, Red Bud, Dogwood, Yoshino, or

Crapemyrtle.

Large Shrubs - American Holly, Foster Holly, or Yaupon.

Medium Shrubs - Needlepoint Holly, Pfitzer Juniper, Carissa Holly, Seagreen Juniper, Aucuba, or Azalea.

Small Shrubs - Dwarf Yaupon, Barberry, Burning Bush, or Nandina.

Ground Covers - Variegated Linope, Big Blue Linope, Pachysandra, or English Ivy.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 3 of

Irrigation

1. In-ground valve box, above ground valve box, and landscape irrigation components - As approved.

Landscape Accessories

a. - Round and rectangular double rim planters in various sizes. b. Tree Grate – NEENAH FOUNDRY, Model R-8707 , Black Cast Iron. c. Pavers -

Site Accessories

Bicycle Racks / Lockers

a. Bike racks – size and number dependent on site requirements, stainless steel finish. b. BRANDIR , New York (212) 505-6500. The Original Ribbon Rack , size dependent on site, powder coated finish.

Fences and Gates

a. Ornamental metal fencing and gates - to match existing.

Recreational Facility and Playground Equipment

a. Playground equipment - type as indicated on drawings.

Signage – see Exterior Design requirements

Site, Street and Mall Furnishings

a. Standard bench – Type 3 – 75” Hyde Park Bench , Rod seat insert. Install on a 3’x7’x4” deep concrete pad with turn down edge, steel trowel finish, on existing grade requiring no site work or landscaping. b. Bench – LANDSCAPE FORMS “ Presidio Bench” without back and no arms, embedded mounting, color to be “Storm Cloud”. c. Tables - d. Trash/Ash Receptacles - (side opening with ash receptacle on top), dark bronze. e. Trash Receptacle – LANDSCAPE FORMS “Chase Park”, 40 gal., side-opening style, keyed lock, surface mounted, color to be “Storm Cloud”. f. Trash dumpster - As approved. g. Waste receptacle - As approved.

Walk, Road, and Parking Appurtenances

a. Bollards - ANTIQUE STREET LAMPS, INC.

Austin, TX. (512) 282-9760. Penn series #BOL/P32/10/BT-

CA/DB , cast aluminum, powder coated, dark bronze finish.

c. Bollards – LANDSCAPE FORMS “ Annapolis”; 6” diameter, with low voltage LED Lighting, embedded mounting, color to be “Storm Cloud” - http://www.landscapeforms.com/en-

US/LFIBrochures/AnnapolisBollard.pdf

d. Parking AMANO McGANN AMG-1750 http://www.amanomcgann.com/Product/Display/4?categoryId=121 e. Parking Gate Controller: DSX ACCESS SYSTEMS, INC . “DSX-1022 Intelligent Controller” http://www.dsxinc.com/hardware.htm

f. Parking Controller Server – DSX ACCESS SYSTEMS, INC.

www.dsxinc.com/Docs/dsxspec.pdf

g. Parking / Access Control Security System - Section 13700 Specification , DSX ACCESS SYSTEMS,

INC. www.dsxinc.com/Docs/dsx spec .pdf

CARPENTRY & PAINTING:

CEILINGS

Acoustical Ceilings - 2’ x 2’ for NEW installations, 2’ x 4’ ONLY to match existing.

Acoustical Tile

1. Existing - Match existing building, salvage from demolition area if in acceptable condition, replace as necessary where existing panels are damaged or missing.

2. 2’ x 2’ x 5/8” fissured – ARMSTRONG Fine Fissured Square Lay-In #1728 , 2' x 2' x 5/8" for 15/16” grid.

White, Colors, or Tech Black. No Substitution.

3. 2’ x 2’ fine textured – ARMSTRONG Chamfered Cirrus #628 , 2' x 2' x ¾" regular edge.

4. 2’ x 4’ Type 6 - USG Interior Tufliner FRP #9121-4 , 2' x 4' x .120".

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 4 of

5. 2’ x 4’ x 5/8” fissured – ARMSTRONG Fine Fissured Square Lay-In #1729 , 2' x 4' x 5/8" for 15/16” grid.

White, colors, or Tech Black. No Substitution .

6. 2' x 4' - ARMSTRONG # 3103 , 2'x 4' x 1" white "Painted Nubby" square cut lay-in ceiling tiles for Prelude

15/16" Exposed Tee grid for full or cut-to-fit applications.

7. 4' x 4' - ARMSTRONG # 5719 Metaphors Coffered Ceiling , 4'x 4' Crown Design mitered moldings (matte white) to hold the # 3110 4'x 4'x 1" Painted Nubby (white) square cut lay-in fiberglass panels.

8. Vandal resistant Type 7 - vandal resistant.

9. High NRC Type 8 - high NRC.

L AY IN C EILING P ANELS (S PECIAL A PPLICATIONS )

1. 2’ x 2’, high moisture areas (shower rooms) – ARMSTRONG Travertine Ceramaguard RH100 #601 , 2’ x

2' x 5/8" lay-in FireGuard (UL), perforated, white, high-density ceramic/mineral fiber composite, ASTM

E1264.

2. 2’ x 4’ moisture resistant – ARMSTRONG Mylar #882 lay-in field units, and #884 lay-in border units, 2'x

4'x 5/8".

3. 2’ x 4’, high moisture areas (shower rooms) – ARMSTRONG Travertine Ceramaguard RH100 # 602, 2’ x 2' x 5/8" lay-in FireGuard (UL), perforated, white, high-density ceramic / mineral fiber composite, ASTM

E1264.

Acoustical Snap-in Metal Pan Ceilings a. Lay-in Parabolic Louvers - A.L.P. Lighting and Ceiling Products, Inc. Para-Lite 4 # PL4 24SPS-AN50.

One-piece injection molded, 2’x 4’ Parabolic louver, specular silver, ¾”x ¾” x ½” cell structure for installation in existing soffit location as indicated on drawings. No Substitution.

Gypsum-Panel Textured Ceilings NO Gypsum board ceilings are to be installed, NO SUBSTITUTION

Attic Ventilation –

Concrete

4” CONCRETE SIDEWALK / PAVEMENT

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 5 of

PEDESTRIAN WALKWAY PAVEMENT PATTERN DESIGN

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 6 of

Inlets

NUMBER 11 INLET

TWIN NUMBER 11 INLET

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 7 of

Doors

1. All interior doors, whether oak, birch, or maple to be stain grade wood with matched veneers.

Security Glazing a. Door Vision Panels ¼" wire reinforced safety glazing, clear polished finish, diamond mesh pattern, size and location as indicated on drawing. Frame – ANEMOSTAT # BFL-123 metal UL or FM approved frame; size and location as shown on drawing and elevations. Color: Gray Primer. b. Security vision light 7/8" thickness Omnilite FR-45 tempered glass. Frame ANEMOSTAT # FGS-IS , metal

UL or WHI approved frame provided with tamper resistant fasteners. Frame color: Gray Primer. c. Standard vision kit 1/2" glazing (1/4" glass+1/4" polycarbonate with standard screws on secure side. At sidelights with stops and vision kits where the screws are on the less secure side use Torx PIN screws.

NOTE: Fabricate, machine, and install according to manufacturer's instructions, approved shop drawings, and submittals. Use screw applied stops and tamper resistant fasteners.

Downspouts –

Fire doors – metal

Gypsum board partitions

2. All new permanent gypsum board partitions shall extend to concrete ceiling/deck and be 1 or 2-hour class as required.

3. All gypsum board to be 5/8” fire rated or 5/8” moisture proof, fire rated unless noted otherwise.

Handrails and Railings

a. Handrails – Use only welded 1-1/2" outside diameter aluminum pipe, mill finish, all # 376 aluminum wall brackets, fittings, fasteners and connections to be nonferrous components. Locate all brackets at spacing required for design loading. Exterior rail color to be clear anodized. NO dark bronze rails are to be used on exterior sun exposed locations.

Field measure, fabricate, shop prime, and install according to manufacturers’ instructions, approved shop drawings, submittals, and all applicable code requirements of the National Life Safety Standards , American s with

Disabilities Act of 1990 , and all local codes. In the case of substitution submit sample.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 8 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 9 of

Overflo w-scupper

Painting

Interior painting

1. Interior paint to be semi-gloss enamels for halls, restrooms, classrooms, and trim and satin finish for offices.

Exterior painting

Roofing

Roof Access –

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 10 of

Roof drain type –

Roofing Guide

GENERAL ARRANGEMENT, ROOF DRAIN GUIDELINES

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 11 of

GENERAL ARRANGEMENT, ROOFING GUIDELINES

Roof membrane –

Waterproofing -

http://www.memphis.edu/cpd/pdfs/div7waterproofing.pdf

LOCKSHOP:

Door Hardware – BEST, VON DUPRIN

1.

Use new locks and hardware throughout; while matching University requirements.

2. Do not use pivots, floor mounted closers, or concealed closers

3. Finishes: b. Bronze colored storefront - all bronze except lockset, lever, and panic bar. Bronze plate behind panic bar c. Aluminum colored storefront - all stainless steel / aluminum

4. Mortise locksets are standard, also spec BEST or CORBIN cylinders. Use cylindrical locksets only in a building with BEST master keys, to match existing locksets

5. Pairs of doors with a fixed astragal have the same hardware as single doors.

6. Double door standards: VON DUPRIN 99 rim panics and removable mullions. NO vertical rods.

7. VON DUPRIN exterior trim should be “NL” - night latch function.

8. Below is the preferred hardware to use on doors. Designer shall verify code requirements.

9. NO “GE” access control products. The campus standard is STANLEY BASIS .

10. Wide stile doors are required with rim panics and removable mullions.

11. Campus Lock Standards - http://www.memphis.edu/cpd/pdfs/div8lock.pdf

Mortise Lock substitutions

BEST number

35H7E15J626

35H7EW15J626

35H7J15J626

35H7EWEU15J626

CORBIN RUSSWIN number

ML2051-NSM-626- (HAND) LC

ML2057-NSM-626- (HAND) LC

ML2055-NSM-626- (HAND) LC

When CORBIN-RUSSWIN locks are used BEST mortise cylinders will have to be ordered. Hardware supplier will be responsible for determining the proper cams for cylinders. Numbers for BEST mortise cylinders are

1E74(CAM) RP3-626

A. Single office doors not fire rated (Fire rated doors same but closer required)

1 - BEST lock set 35H7E15J-626

3 - STANLEY FBB179 NRP 4.5 X 4.5 hinges

1 - LCN 4041 closer (if needed)

B. Double office doors not fire rated (Fire rated doors same but closer required)

1 - BEST lock set 35H7E15J-626

3 - STANLEY FBB179 NRP 4.5 X 4.5 hinges

1 - LCN 4041 closer (if needed)

2 - GLYNN-JOHNSON FB6-626 manual flush bolts

C. Single storeroom and mechanical rooms

1 ea. BEST lock set 35H7Ew15J-626

3 ea. STANLEY FBB179 NRP 4.5 X 4.5 hinges

1 ea. LCN 4041 closer

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 12 of

D. Double storeroom and mechanical room doors

1 - BEST lock set 35H7E15J-626

3 - STANLEY FBB179 NRP 4.5 X 4.5 hinges

1 - LCN 4041 closer

2 - GLYNN-JOHNSON FB6-626 manual flush bolts

E. Classroom doors and multiple use bathrooms that require positive latching.

1 - BEST lock set 35H7J15J-626

3 - STANLEY FBB179 NRP 4.5 X 4.5 hinges

1 - LCN 4041 closer (if needed)

F. Single Fire doors (panic hardware required)

1 - VON-DUPRIN 99LF – 626 –

1 - PEMKO continuous hinge CFM (length in inches) HD (match color to door)

1 - LCN 4041 closer

1 - BEST cylinder 1E72-S2-626

G. Double fire doors (panic hardware required) (no astragal)

1 - VON-DUPRIN 9927LF-626 (HAND)

1 - VON-DUPRIN 9927LF-626-(HAND) DUMMY TRIM

2 - LCN 4041 closers

2 - PEMKO continuous hinges CFM (length in inches) HD (match color to door)

1 - BEST cylinder 1E72-S2-626

H. Double fire doors (panic hardware required, with astragal)

1 – VON-DUPRIN 9975LF-626 (HAND)

1 – VON-DUPRIN 9927LF-626-(HAND) DUMMY TRIM

2 - LCN 4041 closers

2 – PEMKO continuous hinges CFM (length in inches) HD (match color to door)

1 - Coordinator COR85-6261

1 - BEST Cylinder 1E74-C4-626

I. Single non-rated doors (panics required)

1 – VON-DUPRIN CD99L – 626 –

1 – PEMKO continuous hinge CFM (length in inches) HD (match color to door)

1 - LCN 4041 closer

1 - BEST cylinder 1E72-S2-626

J. Store front doors

1 – VON-DUPRIN EL3547L-626-HAND

1 – VON-DUPRIN EL3547L-626-DUMMY TRIM-HAND

2 – VON-DUPRIN power transfer EPT-218 (match color to door)

1 - BEST switch lock 1W7B2-626 (mounted on inside jamb tube or in electric box inside in wall)

1 - BEST cylinder 1E74-C4-626

2 - LCN 4041 CUSH-N-STOP (match color to door)

2 - PEMKO continuous hinge CFM (length in inches) HD (match color to door)

1 EA for up to four panic bars power supply VON-DUPRIN mini power booster PS-873-4

Door to be US ALUMINUM or VISTAWALL with rolling astragal.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 13 of

IF a handicapped opener is required delete one closer and add the following items:

1 – DOOR-A-MATIC SENIOR swing operator with (hand) out swing arm

1 - STANLEY lock relay board

2 – WIKK 4” square stainless steel push plate with handicapped logo

2 – WIKK 300 MHz radio transmitter (delete if buttons can be hard wired)

2 – CURRAN radio receiver (delete if buttons can be hard wired)

1 – 24-volt transformer (delete if buttons can be hard wired)

1 – POTTER & BRUMFIELD # KRPA-14DG-24 triple pole double throw relay (substitutions must use the same base)

K. Door closer substitutions

1. All door closers shall be cast iron cylinders, with seasonal fluid; non-handed, with field adjustable size.

2. Due to restraints on repairs to fire doors, screw patterns shall match LCN 4041.

3. Substitutions MUST be approved before being installed and used.

4. Provide one sample to the University lock shop for testing prior to submittals.

Exit Devices

1. Panic bar substitutions - Any substitution to be equal to VON-DUPRIN panic listed. Provide one sample to the University lock shop for testing prior to submittals.

Sliding and Folding Door Hardware

1. Sliders - STANLEY Dura-Glide 3000 (or equal) with electric locking Fail secure

Electro- Mechanical Hardware

A. Rooms with card reader (networked system, panic not required)

1 - APPLIED REALTIME SYSTEMS IQ2000 reader

1 - BEST lock set 35H7EWEU15J-626

1 - 24-volt transformer.

2 duplex receptacles inside room above ceiling spaced at least 6 inches apart.

1 - AXIS 560 print server

1 - LCN 4041 door closer.

Cat 5 wire - four pair from above ceiling inside room to location of reader head outside room.

Cat 5 wire - four pair from above ceiling inside to nearest computer hub not to exceed 300 feet

B. Rooms with stand alone card reader

1 - VINGCARD PERSONA lock set 32K x ships lever x hand.

1 - LCN 4041 closer (optional, but recommended)

Any substitutes MUST be able to use VINGCARD campus 2000 software.

C. Door openers

1. Openers to be mechanical in design with safety controls that reverse direction when door meets obstructions.

2. Openers shall have field selectable switches that allow set latch speed, backcheck speed, push to open, power boost for 5 seconds selections.

3. Gear boxes motors and control panels shall be stocked in the Memphis area for emergency repairs.

4. Provide one sample to the University lock shop for testing prior to submittals.

5. The Bosch Request to Exit sensors are not desirable. The hand wave sensor is sufficient to operate the automatic operators.

ADA Electro- Mechanical Hardware by STANLEY ACCESS TECHNOLOGIES LLC

OPTION #1

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 14 of

Item "216 TLPP" is manufactured by MS SEDCO and is the wired, touchless, infrared push plate. The relay module is for interfacing the exterior push plate with the building access control system so when the doors lock the exterior push plate is turned off.

OPTION #2:

Heating, Ventilation, and Air Conditioning (HVAC)

Environmental Conditions and General Design Requirements

a. Final design of the energy management system (EMS) or building automation system (BAS) to be evaluated, reviewed, and approved in writing by the University before proceeding to Contract Documents. b. Normally conditioned spaces (e.g. offices and classrooms) design requirements for normal operating hours to be 72

F. ( ± 2

) dry bulb temperature with 45% to 60% relative humidity. c. Verify design requirements for laboratory, archival, computer, etc. spaces. For Lab Standards see separate document called “LabDesignStds2012final document.docx”. d. Size the building chilled water system according to a 50°F leaving water temperature from the central heating/cooling plant. e. Primary cooling to be provided in the following two ways:

1. During summer months, chilled water to be supplied from the central heating/cooling plant via a chilled water transmission system.

2. During spring and fall months, chilled water to be supplied by a centrifugal chiller located in the building. Both chilled water and condenser water pumping systems shall have backup units.

Size chiller and chilled water lines for total building loads. f. “Reheat” systems must be evaluated carefully to determine if they are the most economical for temperature and humidity control. g. Primary heating for the building to be from one or more high-efficiency condensing hot water boilers in the building. Heating systems to be designed as variable flow primary with complete redundancy if possible providing full capacity to the building in case of equipment failure. Steam via a transmission system from the central heating/steam plant could also be used for backup heating in some designs.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 15 of

h. Owner training provided by the equipment manufacturer or the manufacturers’ local trained representative must be included with every project. Training must include a visit to the site, overview of available resources on the equipment and where to find them, explanation of sequence of operations, and some time for questions from the University staff.

100% economizer

Access Doors

1. ACUDOR : http://www.memphis.edu/cpd/pdfs/acudor.pdf

2. DUCTMATE : http://www.memphis.edu/cpd/pdfs/ductmate.pdf

Bath exhaust

Dampers

1.

Fire Dampers & doors: RUSKIN -

http://www.memphis.edu/cpd/pdfs/ruskin.pdf

Domestic water:

a. Domestic water heaters to be gas fired instantaneous (preferred), gas fired condensing models, or heat exchanger systems connected to building heating boilers. The type of system will depend on the specifics of each project and the resources available in the building (natural gas and heating water). b. Storage tanks should not be used unless necessary, and designs should be as efficient as possible.

Equipment

a. Building chiller to be Trane, York, McQuay Magnitude, or Carrier Evergreen (with NO Carrier BAS controls) brand and fitted with “Marine Water Boxes” on both chilled water and condenser water connections. High pressure chillers are preferred. b. Building boilers to be high-efficiency condensing type Cleaver-Brooks, Lochinvar, or Aerco brand with stainless steel construction. Cast iron boilers are not acceptable. c. Provide standby pumps for chilled water, condenser water, and hot water systems. Close-coupled pumps are not to be installed on chilled water systems. d. Air Handling Units to be Trane, McQuay, or York (Johnson Controls) brand e. Condensate return systems shall have duplex pumps and motors. f. Cooling accomplished by variable air volume (VAV) pressure independent systems. g. Refrigerant as approved. h. Roof Pipe Stands - MIRO - http://www.memphis.edu/cpd/pdfs/microroof.pdf

i. Mobile Air - http://www.memphis.edu/cpd/pdfs/mobileair.pdf

j. Packaged Terminal AC & Heat pumps : TRANE - http://www.memphis.edu/cpd/pdfs/terminalac.pdf

Roof Top Units

a. Brands to be Trane, McQuay, and York b. Rooftop Gas Electric 3 – 25 tons : TRANE - http://www.memphis.edu/cpd/pdfs/gerooftop325.pdf

c. Rooftop Intellipak 20 – 130 tons : TRANE - http://www.memphis.edu/cpd/pdfs/rooftop20130.pdf

d. Rooftop Voyager 27.5 – 50 tons : TRANE - http://www.memphis.edu/cpd/pdfs/rooftop27550.pdf

e. For ventilation package units, make-up air package units, and 100% outside air units the approved brands are Aaon, Munters, and Valent.

Hoods

Mechanical Insulation

a. Cover all exposed insulated lines with an aluminum jacket and proper labeling. b. All piping, tanks, valves, and other heat producing or heat absorbing (Chilled Water Pumps) equipment shall be insulated and covered with an aluminum jacket. c. Insulate all mechanical room ceilings. d. All insulated piping shall bear “NO ASBESTOS” warning labels. e. All ductwork shall be externally lined.

HVAC Controls, Building Automation, and Instrumentation

a. All HVAC systems to be monitored and controlled by the University’s building automation system (BAS).

Include all necessary field hardware, and related computer software in all Construction Contracts. The goal is for every building to have a single brand, uniform, control system with access to the entire building

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 16 of

from one front end. If a project will replace only a portion of the building controls, the spec will call for the new controls to match any existing controls that meet University standards. Any approved vendor may submit a bid, but if they do not have any existing controls in the building they will need to replace ALL existing along with the new project controls to keep the system consistent. a. All communicating DDC devices - controllers (supervisory, programmable, configurable, etc) to be from one of the three approved expanding vendor systems: Trane Tracer, Johnson Controls Metasys, and

Distech EC-NET (designed with NiagaraAX). No other brands will be accepted. They must be listed by the BACnet Testing Laboratories (BTL).

b. Supervisory controllers must have a web-based interface, and allow for a “pass-through” software function to service the unit level controllers. c. All communicating field devices (including meters and controllers for power, water, and lighting and other building systems) to use the BACnet open protocol and be listed by the BACnet Testing Laboratories

(BTL). They must transmit across a local MS/TP bus (EIA-485), or use BACnet/IP across the campus

LAN. Packaged equipment and drives (for example chillers and boilers) should be ordered with a

BACnet communication option (if available), but may be integrated directly to a capable supervisory controller using their own protocol if BACnet is not available (for example Modbus or LonTalk). A third party gateway should only be used if these other options do not exist. LonTalk field devices should not be used except in special cases, to be approved individually. d. Every new HVAC project or renovation that includes controls should include; 1) Connection to and communication with one of the three expanding BAS front ends (Tracer ES, Metasys ADX, and Niagara

AX by Distech), 2) A full graphics package including 3D floorplans, 3) Control schematic as-builts

(laminated sheets) for the equipment and the controllers placed in the controls enclosures, electronic copies of the as-builts, and electronic backup copies of all the controller configurations and programs throughout the control system (unit level and supervisory). e. All control system enclosures (panels with BAS equipment/devices) must be equipped with a subpanel or

“perf” panel, disconnect switch or breaker, convenience outlet, and hardwired BAS Ethernet switch (if

LAN connected equipment is present). f. All VAV boxes or terminal units must include a discharge air (leaving air) temperature sensor in addition to the standard points and devices. g. All control valve and damper actuators (and any actuator that is NOT physically integrated into a terminal unit controller) must use a proportional (analog) control signal OR communicate directly on the BACnet comm bus. No “floating” or “tri-state” actuators are permitted. All 24vac actuators must carry a minimum

5 years manufacturer’s warranty. h. All rooms and/or spaces to have individual room temperature control capability.

and space temperature sensors located with customer’s controls (at the same level)—sensors located in the return air are not to be used as space temperature control sensors.

i. No new pneumatic control devices are permitted on any project. j. At the completion of any retrofit/upgrade including new controls, all old control equipment (devices, controllers, wiring, etc.) that will not be immediately reused must be demolished and removed completely.

Some control enclosures and conduits may be emptied and left (with approval) for future use. k. All thermostats and related controls to be DDC. All rooms and/or spaces to have individual DDC room temperature control, provided by DDC sensors. l. Air compressor unit to have dual compressors and sized to operate 1/3 on, 2/3 off. m. All new equipment to have a schematic drawing, sealed in laminate/plastic, mounted on the nearest partition and labeled.

Instrumentation and Control Devices for HVAC

Actuators and Operators

a. All actuators and/or operators for chill water shall be 120vac with compensation heaters for moisture control. All other actuators and operators can be 24vac. b. Electric controls shall be used only in the mechanical room for unit heaters, hydronic, electric, or natural gas.

Sensors and Transmitters

a. Each and every space where there are offices, work space, and classrooms shall have individual control. Sensors and thermostats may be, but not limited to, wired or wireless depending upon circumstance, construction materials and associated costs.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 17 of

Control Valves

a. All chilled water and hot water control valves up to 6 inch to be ball valves with stainless steel ball and trim, equal percentage flow characteristics, and minimum close-off pressure of 100 psi. b. All chilled water and hot water valves 6 inch and larger to be butterfly valves with ductile iron full lug body, stainless steel disc and shaft, and EPDM seat. Butterfly valves shall be rated for a minimum of

100 psid close-off pressure (50 psid for undercut valves). Butterfly control valves to be equipped with

120vac industrial actuators with NEMA 4 enclosure with position indicator (visual), internal overload protection, internal heaters (for CHW applications), electronic position feedback (switches, analog signal, or direct communication), and an external manual override mechanism. All 120vac industrial actuators must carry a minimum 2 year manufacturer’s warranty.

c. Any modulating valves to be equipped with proportional actuators only. No “floating” or “tri-state” actuators are permitted. All actuators to be 24vac for valves up to 2 inch and may be 120vac for larger valves. Only one actuator per valve is permitted; no “stacked” actuators or “dual” actuator configurations on any valve, regardless of size.

d. All steam control valves to be ball valves rated for use with steam (up to 15 psi), temperatures up to

250 deg F, with stainless steel ball and trim, and equal percentage flow characteristics.

e. All chill water control valves on air handlers, incoming feed valves for variable primary pump scheme, shall be the modified sphere construction and be ball valves 8 inches and less and if used at higher diameters shall be concentric - off set seated butterfly style, lug type valve.

f. The only part of the large control valves shall come with 120 vac electric motors. Compensation electric heaters shall be used on air handler chill water valves. The control circuit shall be electronic floating point circuitry with feedback.

Control Dampers

a. Control dampers, depending on use, can be from seal tight for balancing.

Direct - Digital Control System for HVAC a. Energy management system - Match existing Trane, JOHNSON CONTROLS or Automated

Logic. No Substitutions . b. All direct digital control systems shall be either stand alone or capable of connecting to the energy management system. The system can be factory or unit mounted and the pricing of the unit mounted controls shall include the labor to install. All conduit required for low or high voltage shall have compression fittings, not screwed type fasteners. The ends of conduit shall have wire protection on the open ends.

Electric and Electronic Control System for HVAC a. ONLY controls that can be addressed in some manner shall be accepted.

Pneumatic Control System for HVAC a. NO pneumatic control system shall be used on campus unless there is a justified exception and approved by the University. b. Pneumatic damper operators controlled by DDC are acceptable.

Pneumatic and Electric Control System for HVAC a. No combination of Pneumatic and/or electric controls shall be used on campus unless there is a justified exception and approved by the University.

Sequence of Operations for HVAC Controls a. The chill water sequence shall be variable primary pumping, with two- way valving on all end devices. b. The chillers, if incorporated, shall control their own components and be given an enable signal from the central EMS system. The chillers and cooling towers shall be capable of max capping strategy for optimum energy savings. The primary scheme for all chiller plant operation is Primary Variable Flow. c. Hot water hydronic heating systems shall be primary variable flow configuration.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 18 of

d. Air handlers on the air side shall be controlled by VAV using critical zone reset for maximum energy savings and reduced horsepower of the motors. e. The use of powered VAV boxes shall be allowed ONLY by direct written approval of the University. f. The employment of variable refrigerant flow concept that is currently being used in various buildings shall be a predominant factor when low amounts of outside air is required and can incorporate the use of energy recovery devices and can incorporate a diversity up to 150 percent. Large amounts of fresh air requiring separate make-up air units shall incorporate the latest technology such as inverter compressor with infinite stepping TXV, oil recovery and the use of R-410a refrigerants. The make-up air unit shall incorporate the use of energy recovery wheels and the use of Uv emitters and electro static filtration included is a pre-filter that is in a V-configuration. g. In the sequence of operation of air handlers large and small there shall be a reference for full economizing cycle. This includes package or dual fuel units. h. There shall be a sequence of operation for fresh air monitoring and documentation. All drain pans shall be IAQ Stainless Steel construction. No puddle larger than a quarter shall be left in pan after shutdown. i. The chiller room shall be under the control of the chiller sequence for the start and stop of cooling tower fans, no bypasses, pump start and stop. Chiller shall control its own destiny and receive an enable signal. j. VAV Boxes shall be stand alone, capable of connection to an energy management system and must control the temperature of space. It shall monitor discharge air temp., reheat temp., and, since reheat can be hydonic or electric, monitor the status of each. Hydonically the two way valve shall be opened for 10 seconds to determine if hot water is available. Each VAV box shall be capable of programming, monitoring from the thermostat.

HVAC PIPING AND PUMPS

Do NOT use galvanized piping; abandon and remove where possible. All domestic water piping shall be copper. Do

NOT use solder containing lead.

Hydronic Piping

Underground Hydronic Piping a. Underground steam piping shall be engineered and shall be equal to in all aspects to Thermocor.

Thrust blocks that are part of the system shall be rounded and not squared off. No sharp edges shall be felt. It shall be painted with a corrosion inhibiter then shrink wrapped at the factory.

Each wall penetrating end shall have a steel band as it enters and leaves a wall so that the mechanical seal will not crush the jacket.. All specifications shall be strictly adhered. This includes owner and manufacture verification and sign off on all hydronic testing and first inspection of the insulation of the joint process. All piping shall be tested at one and half times the operating pressure which is 95 pounds of steam. All underground piping shall be free of any debris and must be verified and certified by the contractor on the job. All underground projects shall be stamped, engineered projects; no sticks and pieces shall be allowed on any underground project. b. All underground hydronic piping for chill water shall be engineered with the University approving the shop drawings, verification of pressure testing, and factory approved methods of joint insulating. No stick or non-engineered piping shall be approved without specific University approval. If non-engineered piping is installed without University approval it shall be subject to removal at contractor expense.

Above ground Hydronic Piping a. NO above hydronic piping is approved on the University Campus

Hydronic Pumps

In-Line Centrifugal Hydronic Pumps a. When mounted or suspended all pumps shall be supported on both sides. There shall be room for motor removal.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 19 of

b. All pumps shall be flanged and come with an extra set of seals delivered to the University representative. The seal kits shall fit the application of the pump, hot water or chill water. This shall be indicated on the parts box.

Base-Mounted, Centrifugal Hydronic Pumps a. All base mounted pumps shall include volute support and not be supported by the piping. NO

EXCEPTIONS. b. Extra seal kits with the pump application indicated.

Vertical-Mounted, Double-Suction Centrifugal Hydronic Pumps a. All pumps shall be provided with a means to hoist components and move to transport connivance. b. All vertical mounted pumps shall come with a means of motor removal. The removal of the motor shall include self alignment of the coupling and the removal and replacement of seals without the removal of pump. c. The pump shall come with extra seal kits for application and the training required for maintenance.

Vertical-Turbine Hydronic Pumps

Automatic Condensate Pump Units a. All condensate pump sets shall come with pre-wired starter and alternating sequencer. b. All condensate steam pump units shall come with the control package mounted on the tank shell.

This to include the alternator motor starters, disconnect, and heater resets. There shall be extra seal kits for each pump. All sets shall be duplex unless used for make-up to a low pressure steam boiler.

Steam and Condensate Piping and Pumps a. Recommended manufacturer is Thermacor.

Steam and Condensate Heating Piping

Use of Engineered Underground Steam and Condensate Systems.

1. The systems installed on Campus using underground systems have been very successful when installed according to Manufacture’s Specifications.

2. The trench shall be dug according to the drawings attached to the CSI Standard for Underground piping. The University understands there will be points when depth and distance between pipes must change. This can only happen with the consent of the University. All changes in elevation must be approved and new shop drawing sent with the Manufacturer’s approval along with a finished engineered copy with signatures from the University and Designer. No sticks and pieces allowed on any engineered project as they void the warranty.

3. There shall be training by the manufacture’s factory representative for the contractor’s employees and the University shall see and verify the training.

4. No more than a 2 degree deviation from center is allowed for change of direction to get around an obstacle. This has to be approved by the University and Manufacture’s representative.

5. All pressure tests, training on material movement, factory training on installation of insulation shall be verified by both the manufacturer’s representative and University Representative and shall become part of the construction documents.

6. There shall be no 45° joints.

7. All engineered piping shall be tagged for assembly.

8. All pieces entering a wall where link seals shall be used for moisture containment shall come with a metal jacket over the insulation and sealed to the carrier pipe. The metal jacket keeps the insulation from being crushed and deforming the insulation.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 20 of

9. All insulation for steam carrier piping shall be capable of no less than 345° of steam at 95psig.

10. The condensate insulation shall be designed for no less than 250 degrees and for use as pumped condensate. The condensate carrier pipe shall be schedule 80 and schedule 80 fittings shall be used if it meets the Manufacture specifications.

11. The thrust plate shall be treated with a corrosive resistant material and shrink wrapped against the acids that are in concrete. This shall be done at the factory. The thrust plate shall be rounded and not square. There shall be a detail on the plans showing the procedure.

12. Two different steam carrier systems shall not be combined or attached to each other unless the action is taken in a pit situation where the two enter the walls and are connected inside the pits through various methods.

13. All shop drawings must go thru a procedure for approvals that include the manufacture’s engineer, Designer of record and Owner’s representative.

14. All condensate valves used for condensate delivery shall have carbon steel bodies rated at

2000psig. Packing shall be rated for steam. All piping in pits shall be schedule 80 inc. fittings.

15. All below grade steam carrier ball valves shall be stainless steel ball and trim, full-ported, stainless steel bodies. This is good thru and including 8 inches dia.

16. All chill water piping used below grade and in areas (crawl spaces) shall be pre-insulated and follow the manufacturers’ specifications for training, pressure testing as below grade steam pipe.

17. Most important that all changes in field installation due to elevation or change of direction must go thru the Designer of record, Manufacture and Owner and it must be signed off by all.

Underground Steam and Condensate Heating Piping a. All underground steam piping shall be engineered and shall be equal to in all aspects to

THERMOCOR. System thrust blocks shall be rounded and not squared off. It shall be painted with a corrosion inhibiter the shrink wrapped at the factory. Each end that penetrates a wall shall have a steel band as it enters and leaves a wall so the mechanical seal will not crush the insulating jacket. The steam condensate line shall always be schedule 80 piping and meets the same standards as the carrier piping. All high pressure trapping must go thru a flash tank system before it goes into the low pressure pumped condensate system. This system can be mounted in a building or available pit. The insulation shall be appropriate for

345 degrees. All projects shall be stamped and engineered. No sticks and pieces shall be allowed on any University Project. b. All below grade direct burial piping shall be Schedule 80 engineered insulated piping from structure to structure. c. Fittings shall be Schedule 80 welded or threaded. d. Piping in a pit or building may be stick Schedule 80. e. All valves shall be rated body and reinforce packing. See valves. f. The drawing shows High pressure Condensate to Low pressure condensate.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 21 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 22 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 23 of

The above drawing shall be a part of all underground systems.

Above-ground Steam and Condensate Heating Piping a. After the piping enters the building, the piping can be stick and insulated. The condensate return shall be schedule 80 pipe and fittings. The insulation shall be appropriate for the temperature of

345°. The insulation shall be jacked up to 7 feet above grade. b. Above ground only in Mechanical Rooms. All condensate piping, and fittings, shall be Schedule

80. Valves shall have a minimum of 2000 psi rated carbon steel body with reinforce packing.

See valves.

Steam Condensate Pumps

Electric-Driven Steam Condensate Pumps a. All motors shall have electrical protection in the form of a starter sized for the motor specified.

There shall be an alternator to provide equal use of the motors on a duplex system.

Refrigerant Piping

Refrigerant Safety Relief Valve Discharge Piping a. Shall be piped so as to provide vibration isolation and to the highest point of the building.

Refrigerants a. The use of blends shall be restricted and have to be preapproved by the University

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 24 of

HVAC Water Treatment a. The University has a water treatment contract and it should state for the contractor to contact the

University contact person for information. All water treatment shall include the vendor that has the existing water treatment for the University as a whole.

HVAC AIR DISTRIBUTION

Fabricate and support in accordance with SMACNA “Low Pressure Duct Construction Standards” and

ASHRAE handbook and approved methods of rating assembly requirements of designated agencies. Use existing ductwork, make modifications as required. Provide new extensions to match existing ductwork as needed.

HVAC Ducts and Casings

Metal Ducts

Rectangular Metal Ducts

Round and Flat-Oval Spiral Ducts - Any and all air distribution devices used on spiral duct shall be gasketed and part of a system.

Metal Duct Fittings - Hard fittings shall be used on any and all changes of air flow direction.

Non-metal Ducts

Concrete OR Fibrous-Glass Ducts - Not allowed on Campus

Thermoset Fiberglass-Reinforced Plastic Ducts - Flex duct can only be used in the vertical plane and cannot change direction with a hard fitting.

HVAC Casings

Acoustical Air Plenums - Any and all acoustical air Plenums must be pre-approved by the University

Air Duct Accessories a. Pneumatic tubing - Type to match existing provided by the University. All pneumatic lines to be hard-drawn copper tubing. b. Condensate drains - 1-1/2” ID Schedule 40 PVC pipe, all fittings shall be DWV. L copper shall be used long runs and runs that are in a fire rated area. The copper drain line is the preferred material in areas where there is excess heat build up and steam is present or neat by. All condensate lines shall be insulated. c. Install components in strict accordance with manufacturer's installation instructions and approved submittals.

Dampers

Fire Dampers

Interlocking blade fire damper, curtain type. Minimum fire resistance rating to be 1 1/2 hour. Fabricate and install components according to manufacturers’ installation instructions, approved submittals, the requirements of UL-555 and NFPA 90A, and approved methods of rating assembly requirements of designated agencies. a.

Fire Dampers & doors: RUSKIN -

http://www.memphis.edu/cpd/pdfs/ruskin.pdf

Backdraft Dampers b. Wall cap – BROAN 642, aluminum wall cap with built-in back draft damper. c. Wall Vent cap – BROAN 639 (stock # 2C090) 3-1/4" x 10" duct with spring-loaded damper, flange

12-3/4" x 5-5/8" weathertight seal, paint to match brick.

Turning Vanes - Turning vanes shall be installed, even if the duct is semi round.

Access Doors

3. Ductwork access doors - Fabricate and support in accordance with SMACNA "High Pressure Duct

Construction Standards", ASHRAE handbook and approved methods of rating assembly requirements of designated agencies. All door access to duct work and/or walls shall have UL approved labeling and testing.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 25 of

4. ACUDOR : http://www.memphis.edu/cpd/pdfs/acudor.pdf

5. DUCTMATE : http://www.memphis.edu/cpd/pdfs/ductmate.pdf

Flexible Connectors a. All connectors shall be manufactured and NO LOCAL fabrication shall be allowed.

Flexible Ducts a. Flexible Duct – HART & COOLEY 6" and 8" diameter Class 1 air duct metalized jacket. Max. length is 3 feet in the vertical plane only. b. Flexible Duct – DURA FLEX XL1888 silver foil back. Max length is 3 feet vertically only.

c. Hard Insulated Elbow – Any and all changes of direction require a hard duct fitting.

d. Flex duct can ONLY be run vertically, cannot change directions and the length shall not exceed

36 inches. No flex duct shall be used on any inlets to the high pressure side of VAV boxes. Or any boxes that are used as such.

No horizontal use of flex duct shall be accepted.

Fabricate and support in accordance with SMACNA “Low Pressure Duct Construction Standards” and ASHRAE handbook and approved methods of rating assembly requirements of designated agencies. Use existing ductwork, make modifications as required. Provide new extensions to match existing ductwork as needed.

Duct Liners a. Duct liner shall not be used on any return duct work unless expressly said so and a written exception is given. Case in point, transitional returns for acoustical purposes. b. All duct work shall be externally insulated. Duct liner can be used for noise reduction at individual space return above ceiling. This must be used in conjunction with short elbow. c. Any use of duct liner must have University prior approval.

HVAC Fans

Axial HVAC Fans

Centrifugal HVAC Fans a. Centrifugal inline duct fan – KANALFLAKT INC. K4, 4" diameter inlet / outlet, 122 CFM. b. All fans used on air handlers shall be as an assembly and vibration isolated. Assembly includes motor mounts, fan housing, bearings, shaft pulleys, and blower wheel.

HVAC Power Ventilators a. Ceiling ventilating fan - GRAINGER / DAYTON 2D065 with molded white easy-to-clean snap-in grille, galvanized steel housing with integral back-draft damper, 163 CFM at 0.125" SP. b. Ceiling ventilating fan - BROAN, type to match building standard. c. All Ventilators shall be ECM Motors direct drive and be speed adjustable either mechanically or electrically. d. All roof mounted ventilators shall sit on a curb with a minimum of 18 inches above roof grade. e. All electrical whips shall be mounted to a curb mounted rated box as to water proof the inside conduit from the outside conduit.

Air Curtains

Special Exhaust Systems

Bath

Sawdust Collection Systems - They shall be treated as a hazard and potential fire hazard.

Engine Exhaust Systems

Positive-Pressure Engine Exhaust Systems

Mechanical Engine Exhaust Systems

Air Terminal Units

Constant-Air-Volume Units

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 26 of

a. Each unit shall come w/air flow metering device, reheat option mounted. b. Each unit shall come w/air temperature sensor and ddc controls. c. Units can come with factory OR unit mounted ddc controls. If unit mounted; the labor to mount the controls shall be part of the controls package and shall be clearly noted.

Variable-Air-Volume Units a. VAV Boxes - Provided by the University and installed by the Contractor. b. VAV Boxes – TRANE # VDDE2424 variable air volume double duct control terminal units, size 24 heating air valve, 24 cooling air valve, ½” matt faced insulation, field supplied flange connection

(Fld), direct digital controls without remote heat, Ddc sensor, external adjuster, night set back, communication jack (Fld), 120/24 volt transformer, control disconnect switch, control line fuse c. VAV Box – TRANE # VCWE11, MANNING 10" variable air volume single duct terminal unit with:

Size 11 heating air valve, ½” matt faced insulation, Flanged outlet connection, Shutoff with hot water heat, High capacity hot water coil, Left hand coil connection, 120/24 volt transformer,

Control disconnect switch, Control line fuse, Direct digital controls with proportional hot water valve control, and 1 - Ddc sensor, external adjuster, night set back, communication jack (Fld) Part #

X1351060602, and 1 - 1.8Cv (1.55Kv) ddc prop hot water valve (Fld) Part # X13680411020. Note:

Trane's "Everywhere Software" is needed for test and balance. (Fld) indicates furnished by Trane, installed by others. d. Any other Vav boxes specified shall include a control box that is no larger than the VAV box itself.

Any box larger rustics the ability of the contractor to install the vav box close to the deck due to the control box being to large for the intended purpose. Case in point is Downtown Law School. e. Each unit shall come w/air flow metering device; reheat option mounted along with an air temperature sensor and ddc controller, with fused disconnect and hot water valve two way. f. This factory mounting of all controls g. If the controls for the vav box are unit mounted there still has to be the same control configuration and the labor costs must be included.

Air Outlets and Inlets

Diffusers, Registers, and Grilles << Use Hart & Cooley – State or equal >>

All ceiling diffusers, grilles and registers shall come with factory mounted insulation. No work in the field shall be accepted.

Install all components according to manufacturer's installation instructions and approved submittals. After completion of the project - before owner acceptance - test and balance all ductwork and grille modifications / additions according to recommendations of the Associated Air Balance Council. Test quantities must be within 5% of the quantities specified. Submit a formal report to the University for review and comments.

Return air grilles –

1) 1’ x 4’ louvered grille, type and finish to match existing building standard. No Substitution .

2) 16"x16" louvered grille, type and finish to match existing building standard. No Substitution .

COOLEY , Dover white finish, module size for insulation in concealed spline ceiling. No

Substitution .

4) HART & COOLEY 2' x 2' PDR perforated diffuser, Dover white enamel finish. No Substitution .

Supply diffusers –

1) Louvered fan ceiling diffusers, type and finish to match existing building standard or as selected by the

University. No Substitution .

COOLEY , 14" x 8", four-way deflection, Satin Aluminum finish. No Substitution .

COOLEY , 6" x 14" and 8" x 14", 2 way blow. No Substitution .

4) HART & COOLEY 2' x 2' PDSD perforated diffuser supply with deflectors, 3800 series butterfly damper with removable handle, 5400 series snap in collar (as required), Dover white enamel finish. Or equal.

Must have factory insulated backs no exception.

Fabric Air Distribution Devices

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 27 of

The fabric Air distribution devices shall be of slot style at a 22 - 45 degree with the material allowing for air to bleed through all 360 degrees. The material must come with a 10 year warranty and capable of being cleaned using normal non commercial washing methods. The material shall also be capable of decoration as to sell advertisement if so desired.

HVAC Gravity Ventilators

HVAC Gravity Dome Ventilators

HVAC Gravity Louvered-Penthouse Ventilators

HVAC Gravity Upblast Ventilators a) All rotating parts shall be out of air stream and be capable of at least 20 foot plumes. All controls, actuators shall be capable of movement greater than a delta P5 inches of water column or greater. All hoods shall be tested according to ASHRAE Standards

Ventilation Hoods

Commercial-Kitchen Hoods

Fume Hoods

HVAC AIR CLEANING DEVICES

Particulate Air Filtration

Panel Air Filters - The filters must be rated at a MERV 8 or greater.

Renewable- Media Air Filters

Washable Air Filters - Shall be of the type that can be vacuumed or washed and have an everlasting biocide to kill mold and mildew. They shall be from the equipment manufacturer to not allow for air leakage around the media.

Extended Surface Filters - All computer room equipment shall no less than a MERV 11. All other air handling equipment shall be 2 inch MERV 8. All air handling equipment shall come with electrostatic filtration with UV lighting on the coils. The electrostatic shall be capable of .3 micron particulate or less.

And the electrostatic shall not produce ozone.

High-Efficiency Particulate Filtration

Ultra-Low Penetration Filtration - They shall be used as secondary filtration with ultra low static pressure drop and can be electrostatic with no ozone.

Super Ultra-Low Penetration Filtration

Gas-Phase Air Filtration

Activated-Carbon Air Filtration

Chemically-Impregnated Adsorption Air Filtration

Catalytic-Adsorption Air Filtration

Electronic Air Cleaners (Washable, Agglomerator, Self-Contained) a.

Electronic Filter Air Cleaner – HONEYWELL 15000 Enviracaire, 600 CFM.

CENTRAL HEATING EQUIPMENT

Breechings, Chimneys, and Stacks

Draft Control Devices a. Wall vent cap – BROAN 639 (stock # 2C090) 3-1/4" x 10" duct with spring-loaded damper, flange 12-3/4" x

5-5/8" weathertight seal, paint to match brick.

Fabricated Breechings and Accessories

Fabricated Stacks

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 28 of

Gas Vents

Insulated Sectional Chimneys

Flue-Gas Filtration Equipment

Heating Boilers: Electric, Condensing, Pulse Combustion, Cast-Iron, Water-Tube, & Fire-Tube a. Cast iron boilers are not acceptable.

Heating Boiler Feedwater Equipment and Deaerators

Furnaces

Electric -Resistance Furnaces

Fuel-Fired Furnaces

Gas-Fired Furnaces a) All gas fired furnaces shall be a min. of 95% AFLUE. The primary and secondary heat exchanger shall be stainless steel. b) All gas pak style furnaces shall be a min. of 90% efficient with stainless steel heat exchangers

Fuel - Fired Heaters – (Duct Heaters, Gas - Fired Radiant, Fuel - Fired Unit)

Solar Energy Heating Equipment – (Packaged or Heating Solar Collectors)

HVAC Heat Exchangers – (Steam-to-Steam, Steam-to-Water, Liquid-to-Liquid, Direct Geoexchange)

CENTRAL COOLING EQUIPMENT

1. Refrigerant Compressors – (Centrifugal, Reciprocating, Scroll, or Rotary-Screw)

2. Packaged Compressor and Condenser Units - (Packaged Air-Cooled & Packaged Water-Cooled)

3. Refrigerant Condensers - All water cooled condensers shall have marine water boxes on one end of the machine.

4. Packaged Water Chillers - The evaporator shall be separate and located inside a mechanical room.

No water component shall be outside. a. Stainless cooling tower b. Forced, or Natural, Draft Cooling Towers c. Field- Erected Cooling Towers d. Liquid Coolers

CENTRAL HVAC EQUIPMENT

Thermal Storage – (Thermal Heat, Chilled-Water, or Ice Storage)

Air-to-Air Energy Recovery Equipment – (Heat-Wheel, Heat-Pipe, Fixed-Plate, Packaged Units)

Indoor Central-Station Air-Handling Units

1. All air handlers shall come with an access section between hot water and chill water coils.

2. It shall be noted the drain pans shall be arranged to have no more than quarter size of puddled water standing. All drain pans shall be 304 stainless steel and shall be broke to eliminate any puddling of water.

3. All air handlers shall come with a central location for all sensors and actuatrors and controls for mixing box can be wired .

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 29 of

4. All fan sections shall be vibration isolated and bearing support shall be aligned for the greatest bearing support.

5. All air handlers shall have full economizers and the mixing boxes shall be factory made.

Modular Indoor Central-Station Air Handling Units

1) Indoor Central Station Air Handler - TRANE # MCCA008 with the following: a) Modular Base Unit – unit size 08, standard split with 4” to 6 inch base rail mounting legs, UL listed insulation shall be foam no less than R-13. Supports shall be no sweat and all access doors and hardware shall not sweat.. Solid double wall. b) Factory Controls Package – VFD with bypass; PCM 20 point; unit mounted drive side; space sensors with timed override/SP (Fld); outside air sensor (Fld). All controls and sensors shall be wired to a central point c) Air Mixing Module (Pos. # 1) – mixing box with filters; access door; top and back dampers with parallel blades; 2” pleated media unit filters; electronic actuator; averaging temperature sensor. d) Blank Module (Pos. # 2) shall contain access door. e) Vertical Coil Module (Pos. # 3) – stainless steel drain pan; entering air freezestat; electronic 2-way control valve – normally open, water (Fld); chill water shall be no less than a 16 degree deltaT.6 row cooling coil enhanced copper tubes. f) Vertical Fan Module (Pos. # 4) – access door; fan discharge @ top and back; open drip proof high efficient E- motor; ½” rubber-in-shear isolation; 3 hp, 460/60/3 voltage; fan discharge temperature sensor; air flow switch; starter – NEMA 1 enclosed – indoor. g) Deluxe beige finish. Install according to manufacturer's installation instructions and approved submittals. Note: Trane's "Everywhere Software" is needed for test and balance. (Fld) indicates furnished by Trane, installed by others.

Custom Indoor Central-Station Air-Handling Units

Indoor Indirect Fuel – or Gas-Fired – Heating and Ventilating Units

Packaged Outdoor HVAC Equipment - For a quick spec on UNITARY AIR CONDITIONERS see “Air-Cond.doc” in

Standard / Specs / Quikspec

1. All packaged outdoor equipment shall have the utilities come up thru the equipment and/or roof curb.

2. All roof top equipment shall have a roof curb of no less than 18 inches tall.

3. All packaged HVAC equipment shall have the same height (18 inches) and have built-in vibration elimination.

Packaged, Outdoor, Central-Station Air-Handling Units

Packaged, Outdoor, Heating-Only Makeup-Air Units (Direct or In-direct Fired)

Packaged, Outdoor, Heating and Cooling Makeup Air-Conditioners a. Exterior HVAC Unit – JANITROL PGX060 , outdoor package unit, cooling capacity of 60,000

Btu/HR., heating output capacity 78,000 Btu/HR, 208/230V-3ph-60Hz, with low ambient controls and economizer.

Custom - Packaged Outdoor HVAC Equipment

Evaporative Air-Cooling Equipment

DECENTRALIZED HVAC EQUIPMENT

Decentralized Unitary HVAC Equipment

1) HVAC Unit – LIEBERT Mini-Mate Plus, DMC037A condensing unit and MME036E above dropped ceiling evaporator unit, 3 ton split-type, cooling capacity of 32,100 BTU/HR, reheat coils 22,100 BTH/HR, 2 speed circulating air fan for dehumidification control, 208V, 1Ph, 60 Hz., direct-drive fan with self-aligning sleeve bearings and lifetime lubrication, finned tubular electric reheat with safety switch. Each system capable of 1250

CFM at .3 inches of water external static pressure. Control to have 2 humidity setpoints for humidification and dehumidification functions with a minimum 4% RH differential and automatically switch from humidifying to dehumidifying based on return air conditions. Humidity control setpoint range to be 20% - 80% RH. LIEBERT wall mounted microprocessor control, LCD display with 8 key membrane keypad, programmable on a daily basis or 5 day / 2 day schedule, accepting 2 programs per day. Control to activate an audible & visual alarm following field conditions when temperature maxes 90F, min 35F and humidity Max 85%, Min 15% RH. Pre-

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 30 of

charged refrigerant lines sets: Type as recommended by manufacturer. Seamless copper tube water line, hard drawn, type L, ASTM B88. Full port bronze body stainless steel ball valves, unless otherwise noted.

2) HVAC Unit – LIEBERT DataMate DMC037A condensing units and DME037E evaporator units, wall-mounted.

3) HVAC Unit – JANITROL GUPS120-5 vertical, UC-60 evaporator coils, re-pipe as required. Condenser CE60-F .

Thermostats - Pneumatic thermostat provided by the University and installed by the Contractor.

4) HVAC unit – JANITROL 60MAQ-4 horizontal ceiling hung, 120 volts with 60,000 Btu/hr cooling coil and a separate hot water coil, refrigerant lines and control wire. Condenser CE60-3 , 200/230 volt, Thermostat –

HONEYWELL T87F with Q839 sub base.

Packaged Terminal Air Conditioners

Room Air Conditioners a. Air conditioner – WHITE WESTINGHOUSE WAL125P1A , 12,000 Btu, 115 volt, 9.0 EER, through window unit.

Self-Contained Air Conditioners (Small or Large capacity)

Computer Room Air Conditioners

Computer Room units shall comply with IAQ with stainless steel drain pans, electronic control of humidity and temperature of the space. The CPU shall have the capability of monitoring compressor functions, input power, shall have the capability of monitoring compressor functions, input power, chill water coil and chill water temperature to allow the system to work at the most economical manner. It shall have the ability thru open protocol and Web browsing to provide the information necessary of all functions that the unit is monitoring. Any refrigerant circuit shall be separate from the other. Each unit shall come under floor water detection.

Split - System Air Conditioners

The system shall be 16 SEER or better if it is found economically feasible above 16 SEER. The drain pans shall be of IAQ quality and shall come with UV emitters on the coil section. Uv emitters shall be part of any spec sent out by an engineer for any of the units that may be specified. Electrostatic filtration shall be used where there are students, faculty and staff.

Air - Source Unitary Heat Pumps a. Air conditioner / heat pump - GE Zoneline PTAC/PTHP, one fan motor and microprocessor controls,

14,100 / 13,800 Btu, 208 / 230V. Provide with wall case and exterior grille; color as selected. b. Air conditioner / heat pump - GE Zoneline AZ51H15DAC, 5100 series, two fan motor and microprocessor controls, 14,100 / 13,800 Btu, 208 / 230V. Provide with wall case #RAB70, exterior grille #

RAG66 and all necessary components, color as selected.

Water - Source Unitary Heat Pumps

Convection Heating and Cooling Units

Valance Heating and Cooling Units

Air Coils

Fan Coil Units a. Fan Coil Air Conditioner - TRANE UniTrane # FCBB1201KK0A0G1(LH) & # FCBB1201JK0A0G1 (RH); vertical cabinets, size 120, 115v/60hz/1ph, with piping, front toe space return, top quad grille supply, free discharge fan motor, 3 row cooling/1 row heating coil, 144 fins/ft, manual air vent, disconnect switch, 1" throwaway pleated media filter (Farr 30/30), 3 way modulating Cv =1.5 (50 psig) cooling and heating control valves, deluxe ball valves (supply and return) with Autoflow valve, TUC (Terminal Unit Controller) DDC controls, unit-mounted zone sensor module, OALMH fan mode switch and setpoint dial, 9.0 gpm main and 1.0 gpm auxiliary Autoflow valves, deluxe beige finish. Install according to manufacturer's installation instructions and approved submittals.

Unit Ventilators

Induction Units

Radiators

Convectors

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 31 of

a. Convector – INTERNATIONAL ENVIRONMENTAL FHY06 , 2 pipe HW/CW fan coil unit with wall mounted control, 2-way motorized valve and auto C/O Aqua-Stat. b. Convector - TRANE 300 CFM unit, vertical cabinet with baked enamel finish, left hand controls, thermostat, non-corrosive, positively sloped, easily removable drain pan, motor/fan 120V, single phase, 100 watts. Options include factory-installed interconnecting piping package, three-way two position control valves, inlet and outlet style toe space and quad grille; color as selected.

Finned-Tube Radiation Heaters

Unit Heaters – (Cabinet, Propeller, Wall and Ceiling)

Radiant Heating Units

Radiant Heating Electric Cables & Mats

Radiant Heating Hydronic Piping

Radiant Heating Electric Panels

Electric Radiant Heaters

Humidity Control Equipment mist is required. Stainless steel pans are a requirement for units using infra-red light.

b. Dehumidifiers - Dehumidifiers must come with a way for reheat unless the load in the space is sufficient.

Indoor Pool Dehumidification Units

Outdoor Airflow Control

a. When the air handler is providing mechanical cooling control the outdoor air ventilation damper in order to deliver proper outdoor airflow to the VAV system at all load conditions. Outdoor airflow to be sensed by an airflow measuring station (using thermal dispersion technology) at the outdoor air intake and maintained at the calculated minimum outdoor airflow setpoint determined by ASHRAE Standard 62-89,

Equation 6.1. Recalculate the correct minimum outdoor airflow setpoint every 30 minutes (operator adjustable). The ATC system shall solve Equation 6.1 dynamically for all connected VAV spaces to determine minimum outdoor airflow setpoint required to properly ventilate all VAV spaces at all operating conditions. Recalculate the setpoint periodically (every 30 minutes, operator adjustable) based on prevailing VAV space conditions. For each VAV space, the ATC system shall compare actual measured space airflow at each VAV terminal to the required ventilation airflow as scheduled. The ATC system shall determine the critical space ventilation fraction from the VAV zones and the total supply airflow; then use Equation 6.1 to determine the correct minimum outdoor airflow setpoint, adjusting for the recirculation credit allowed by the Equation to reduce energy usage. b. When the air handler is providing economizer cooling determine outdoor airflow by supply air temperature requirements. Compare actual outdoor airflow to calculated minimum outdoor airflow setpoint to ensure flow is higher than minimum outdoor airflow setpoint; then, based on the actual outdoor airflow, the system shall periodically use Equation 6.1 to determine maximum allowable critical space ventilation fraction. c. Alternatively, a demand-based control scheme may be used (instead of ventilating to a minimum occupied volume) incorporating CO2 sensors, IAQ sensors, and/or occupancy sensors in each controlled zone, communicating the need for ventilation back to the supervisory control system and the AHU controller. Each zone will control independently to one global air quality setpoint for the building. d. System to graphically display critical ventilation VAV space location, system supply airflow, ventilation fraction, calculated minimum airflow setpoint, and actual measured outdoor airflow.

Outlet on roof

Stainless Cooling Towers Only

Specifications to Consider When Designing Around A VRF Mechanical HVAC System

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 32 of

Variable Refrigerant Flow Systems (VRF and VRV)

a. VRF systems (of all kinds) must be from one of the three approved vendors for the campus; MITSUBISHI

ELECTRIC, DAIKIN AC, and SANYO.

b.

Specify a complete control system to be integrated into one of the three expanding campus BAS front ends with each VRF installation ( into an existing owner BAS interface)

. This includes interactive 3D floor plans, 3D equipment graphics, and extensive point trending. All communicating control devices (that are not a part of the manufacturer’s VRF system controls network) must use the BACnet protocol (over

MS/TP or IP). An OEM central controller with web interface AND a BACnet integration device/module to be supplied and installed with each new VRF system (unless controllers already exist in the building with room to integrate the new equipment). The OEM central controller should allow “pass-through” remote service connections to the unit level network for data logging and troubleshooting.

Approved control product brands are TRANE, JOHNSON CONTROLS, and DISTECH. c.

All major parts of the systems (indoor and outdoor) must be labeled with the system number (unique to each refrigerant circuit in the building), port assignment, and device address. If a unit has more than one identifying number, such as a group number AND an address number, then both must be present.

BC controllers should be labeled with the location and identification of the outdoor unit that serves them.

Outdoor unit disconnects should be labeled with the name of the electrical panel that feeds them.

d. The OEM VRF controller(s) (and any accessories) must be mounted in a metal enclosure with subpanel , convenience outlet, and disconnect switch and installed according to manufacturer’s instructions. Any

Ethernet ready device (such as a BACnet/IP integration module) must be installed with a panel mounted compact Ethernet switch. e.

Communication and control wire (comm. wire) above the ceiling should be hung from, and run with

(parallel & perpendicular to) the building structure and secured as required by code with the proper hooks/rings. There should be no splices allowed in the comm link; wires should be continuous from one device to the next. All comm. wire should be in hard metal conduit

(specify 3/4 in minimum) in mechanical rooms, closets, and any exposed areas with flexible connections limited to 3 feet in length.

All wall penetrations for plenum rated wire that is not in conduit should have proper sleeves with protection for the cables at each end.

f. Proper protection should be provided for cables penetrating enclosures or wire troughs to avoid damage

(specify metal chase nipples or other proper fittings with minimum 3/4 inch size).

g. Conduit and refrigerant piping, inside and outside, should be run with the structure (as much as possible) and properly supported/secured (especially on the roof) with appropriate supports (no wood allowed) and proper clamps (with vibration isolators as needed).

h. All disconnect switches on indoor and outdoor units should be labeled (not hand written) with power source (panel) and location. Outdoor units should be labeled to indicate the refrigerant circuit number

(found on the commissioning paperwork and as-built documents) that they are connected to.

i. Refrigerant isolation ball valves

(if used) should have ratings that meet or exceed those of the manufacturer's recommended valves .

If the manufacturer provides or recommends a specific valve, that valve should be required.

They should be located for the best possible access...

preferably at the indoor unit .

Installation of valves at another location (for example, at the BC controller) should be approved by the design engineer and the University. If the refrigerant valves must be concealed, an adequate access panel must be installed. j. A complete set of as-built documents should be presented to the owner (paper and electronic copies) when the VRF project is complete. This should include (in addition to all standard requirements) all VRF commissioning paperwork,

(provided by the manufacturer and completed by the installing contractor), and as-built system spreadsheets / refrigeration schematics organized by room numbers and showing address numbers of each major component, branch port assignments, connections to central controllers, refrigerant circuit (system) numbers, and total system refrigerant charges. The as-built schematics should accurately show the path of the refrigerant piping AND the order of the units in the

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 33 of

communication daisy chain (note: the comm link order may not necessarily run sequentially with the address numbers).

k. Wires 8 AWG and smaller should be of proper color from the manufacturer (permanent and continuous color… no tape allowed to identify the color ). l. The installing contractor must provide documentation during the warranty period . Any time a warranty service call is made for mechanical equipment (or controls), a service ticket (or a no-charge invoice) must be done and a copy provided to the owner. At the end of the warranty period a comprehensive record/report of warranty service must be provided to the owner indicating dates, times, locations, system (or unit) identification numbers, and any parts used (including refrigerant) with part numbers. Any modifications, changes, or upgrades done during the warranty period should also be noted in this report so that the as-built documents can be updated as needed by the owner.

Additional mechanical quality control specifications over installation process.

1. Specifications to be more ridged than the manufacturer; especially in pressure testing and evacuation. a. All refrigerant lines shall be installed according to manufactures’ specifications. From the time it is brought to the job site to the installation. The owner, shall upon request, shall be able to inspect the way it is stored and the way it is installed from time the refrigerant lines are put in place, thru the purging process, thru the flaring process, to the brazing process. The owner has the right to reject any materials not stored correctly, not installed correctly and not nitrogen purged during brazing process. These processes shall be done according to manufactures processes and procedures and the Owner has the right to require any and all parts of the system not installed according to the manufactures’ specifications to be totally removed and the process started with new materials to ensure the quality and the Manufacture, not Manufacture’s representative warranty, is fully enforced and not compromised. b. Pressure test at 602 lbs psig or greater, for 24 hours. University personnel assigned must be there during the start and end of pressure testing and must observe during the 24 hour period and document the procedure with time and date and signature. This to help ensure no one adds to the pressure. During pressure testing the nitrogen bottle shall be disconnected from the test port. If there is a leakage during the test period the Owner’s rep. and contractor’s rep. shall verify the procedure for leak check and the contractor shall document where the leak location and what was done to eliminate the leak. c. The first evacuation is just as important as the last one. The first evacuation shall be completed in the same manner as the last most important test. There shall be a period of pressurizing between periods of evacuation and each period shall be documented along with the pressure reading and length of time the system was left on positive pressure. Each level of evacuation shall be documented both by the Owner’s rep. as well as the installer rep. The last evacuation of 500 microns or less shall run for a minimum of 24 hours before the verification process starts. The verification period shall last for min. of two hours. At that point the rise shall not exceed 500 microns and if it does require renew pressure test and leakage check. This is one hour more than manufactures’ specifications but ensures a leak free system at start up and commissioning. All documents for the pressurization and evacuation shall be a part of the close out documents. d. Any and all documents relating to Leak Checking, Pressurization and Evacuation shall be part of the close out documentation. e. Owner personnel training is a major point. All training shall be at least 8 hours and shall include the factory training of the controls and the maintenance and operation of the system/systems installed.

This documentation and the syllabus shall be part of the close out documents along with the names of personnel trained.

2. Owner/Contractor qualifications. a. Contractor shall show evidence of successful installation of systems of similar size and scope.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 34 of

b. In the qualifications the contractor shall have proof of factory training of minimum of 3 persons who will actually work on the system from start of installation to finish. The personnel shall be qualified to supervise personnel and provide the power to instruct and lead other personnel. Personnel not trained on the system specifications or non journey men shall not be allowed to work on the system unless there is direct supervision by a qualified factory trained individual. The trained personnel shall be on site and visible during the whole work period. Work shall stop if there is no trained personnel supervision available. The Owner has the right, once observed that no personnel are available to stop work temporarily till the contractor provides supervision. The Owners rep shall have the list of qualified personnel and their contact numbers to ensure continuity of work so there is no stop time. All stop time, day and location the violation is observed shall be documented and is a part of the close out documents.

This stop time does not qualify for any extension of contract time, or overhead. c. The Owner shall provide Personnel qualified on the Installation procedures of any said system to be visible during the work period for said observation and this person shall be versed in the mechanics of

HVAC system installation, operation and customer relations. Once assigned the same person shall be available thru the whole project. d. The Designers shall not allow refrigerant lines in any open space (no ceiling tile or hard surface ceiling) unless there are significant reasons to do so and there is no other available route. At that time the designer shall coordinate with the architect of record and address measures to make the installation in an open area look presentable.

VFD on AHUs, Fans, and Pumps

a. Variable (Adjustable) Frequency AC Drives (VFDs) mounted alone or with packaged equipment must have inverters from one of the following approved vendors: Danfoss, ABB, Trane, or York. The bypass section (required when the equipment is capable of running across the line) must incorporate a third contactor or a disconnect switch to isolate the inverter for service.

b. All fans and pumps (including cooling towers) that are not single speed to be equipped with VFDs.

Operation and Maintenance of Facility Fuel Systems a.

All fuel lines and tanks shall be cleaned and dried by nitrogen before fuel is added. b. All alarms and status lights shall be operational at time of installation. c. All lines shall be pressure tested and data recorded and given to the Owner. d. Test boilers on oil to be sure the pressure drops are maintained and correct for the application.

Operation and Maintenance of HVAC Piping and Pumps a. All lines shall be pressure tested to one and half time the operating discharge pressure of the pump. b. Pumps: All pumps shall be field aligned and free of any undo pressure due to pipe weight or orientation.

Pumps shall be aligned according to manufacturers’ specification and report(s) turned into the

Owners representative. If pump comes with an inertia frame base, the inner section shall be filled with grout after installation. c. Pump assembly shall come as a complete unit with self-supported volute. The motor shall be mounted and aligned to the pump assembly. Inspect and align per manufacturers specifications. d. The motor shall be connected to the electrical system by no more than 3’ of flex conduit. e. Piping: No PVC shall be used in a rated room or near hot water and steam systems. This includes drain systems for any and all mechanical equipment. f. Copper: Only "K or L" copper shall be used on water side of air handling equipment. g. Refrigeration: Only copper designated for refrigeration shall be used and must come sealed and have a nitrogen charge.

Operation and Maintenance of HVAC Air Distribution

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 35 of

a. No flex duct shall be allowed on any high pressure inputs to VAV boxes. Three (3’) feet will be allowed on low pressure side, vertical plane only,but cannot change direction. b. All 24” x 24” ceiling diffusers shall come with factory mounted insulation to the backs of each diffuser. c. All side-mount, bar type grilles shall come with opposing blade dampers for balancing purposes.

HVAC Air Duct Cleaning a. All duct work shall be clean of all dust and debris before installation. b. All duct work and accessories shall be kept in a clean, dry environment before installation.

Operation and Maintenance of Central Heating Equipment a. All operational and maintenance training and operation shall be the responsibility of the contractor.

Operation and Maintenance of Central Cooling Equipment a. All operational and maintenance training and operation shall be the responsibility of the contractor. b. Chillers shall have a 16° (degree) Delta T across the evaporator. c. Chillers shall control all components that are directly related to the chiller operation, including the cooling tower, bypass, valve operation condenser water pumps. The central ems system shall enable the chiller and provide for chill water temperature reset as determined by algorithm.. Chillers shall operate in the max cap region for energy savings when conditions warrant.

Refrigerant Recovery / Recycling a. It is the Owners’ responsibility to recover and recycle any and all refrigerants and oils and dispose of as and according to EPA regulations in the Clean Air Act.

Common Work Results for HVAC a. All condensing units shall be mounted on the roofs of buildings unless there is specific University approval to place on grade.

Common Motor Requirements for HVAC Equipment << Evaporator (and condenser) fan motors >> a. All motors shall be service factor of no less than 1; preference would be 1.5, b. All large horsepower motors shall be dual voltage. c. All fan coil motors shall be PSC, not shaded pole, unless it is the only thing available and there must be a written exception presented to owner. d. All motors where available shall be the ECM type for efficiency and reliability.

Expansion Fittings and Loops for HVAC Piping a. All piping, fittings and loops shall be engineered; no exceptions. b. All underground thrust block plates shall be round and no pointed edges with corrosive inhibited coating and be shrink-wrapped from the factory. c. All ends shall have a metal jacket to prevent the ends from crushing due to link seal installation. d. All piping end pieces shall be finished a minimum of 6” from the end of insulation.

Meters and Gages for HVAC Piping a. All end devices shall have visual gages and meters installed. b. All meters and gages inside a mechanical room shall be visible / readable with no obstructions from the floor. c. All meters and gages shall be in a brass or stainless steel well filled with a heat transfer compound.

General - Duty Valves for HVAC Piping a. Use threaded full ported, bronze body ball valves with a stainless steel ball and trim, in a nylon or Teflon seat.

NO SUBSTITUTION unless dictated by code. Soldered valves NOT acceptable. b. Provide full port ball isolation valves for each restroom and stops for each fixture. c. Install reduced pressure backflow preventers per code at 7’ maximum above finished floor.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 36 of

d. Use sleeves and link seals, rated per code, at vertical penetrations of mechanical and plumbing piping. e. No globe or gate valves shall be allowed on any project f. No triple duty valves shall be allowed on any project. g. All general ball valves can be brass or carbon steel bodies. The minimum rating is 600psi and all shall be pipe threaded. No sweat ball valves shall be allowed . h. All general ball valves 4 inches and above shall have a gear operator. All mounted 7 feet or higher shall have a chain gear operator. i. Ball valves shall be used on all piping 8 inches and below. Butterfly valves shall be used on all piping 10 inches and above. They shall be the concentric shut-off with built in gaskets.

This is the only time Butterfly valves may be used.

Specialty Valves By Need a. Steam Duty: All valves below grade shall be stainless steel ball and trim and body and can be rebuilt. The packing shall be reinforced and capable of 345° and up to 250 pounds of pressure.

Steam trap valves 2 and 1/2 pipe size or smaller shall be stainless steel ball and trim reinforced packing and rated at 2000 pounds with carbon steel bodies or stainless steel bodies used below grade. b. Chill water: All chill water valves used on air handlers shall come with a modified stainless steel sphere and trim capable of low flow water with minimal pipe noise to shut off. (Control valve). Two way only Cv sized. Fan coil units: control valve shall be capable of shut off with a delta p. of over 50 psig. Two way only size for the Cv of device and cannot be sized smaller than two pipe sizes of coil. c. Hot water: All hot water control valves shall use same sizing as chill water control valves and characteristics d. Low pressure steam valves: These valves shall have the same characteristics as the chill water but must be rated to handle steam pressure and the packing must be able to handle the pressure

They must use reinforced packing

Hangers and Supports for HVAC Piping and Equipment a. Support mechanical equipment according to the SMACNA “Low Pressure Duct Construction Standards” ,

ASHRAE handbook and approved methods of rating assembly requirements of designated agencies. b. Obtain approval from University Representative for all partition or ceiling attachments to be made for any device, fixture, or equipment; especially in exposed, open areas . Existing attachment points or holes must be properly repaired to accept new finish to match surrounding finish.

Heat Tracing for HVAC Piping a. All make-up water piping that is outside a building envelope shall have heat trace installed and an alarm shall be sent to the EMS system should the heat trace fail . b. All cooling towers, and any other outside unit having make-up water or no potable chill water, shall be heat traced and include an alarm picked up by the Energy Management System. Alarm is to indicate that no current is being drawn through the heat trace system after activation by Energy Management System.

Vibration and Seismic Controls for HVAC Piping and Equipment

Identification for HVAC Piping and Equipment a. Signage shall include direction of flow, chill water or hot water, potable and non potable. The equipment shall be numbered. The Electrical side shall indicate the breaker panel from which power originates.

Anti-Microbial Coatings for HVAC Ducts and Equipment a. The use is a favorable option for new installations. Use in conjunction with UV emitters for HVAC duct work on old installations.

Anti-Microbial Ultraviolet Emitters for HVAC Ducts and Equipment a. All emitters shall emit C band Ultraviolet and use a standard base; Phillips or equal.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 37 of

b. All ultraviolet emitters shall have band width indications as to what diseases it will kill and the time required in the light path to be effective.

Testing, Adjusting, and Balancing for HVAC a. Install components according to manufacturer's installation instructions and approved submittals. After completion of the project - before owner acceptance - test and balance all ductwork and grille modifications / additions according to recommendations of the Associated Air Balance Council. Test quantities must be within

5% of the quantities specified. Submit a formal report to the University for review and comments. The test and balance company shall be AABC certified no others shall be accepted. b. Only companies associated with AABC shall be accepted for the adjusting and balance of water side and air side of HVAC.

HVAC Insulation f. All piping, tanks, valves, and other heat producing or heat absorbing (Chilled Water Pumps) equipment shall be insulated and covered with an aluminum jacket. g. Insulate all mechanical room ceilings.

Duct Insulation a. Return duct insulation - interior insulation shall be used only on L-shape noise elimination transfer duct. EXCEL 2lb. FHC/25-50/-1/2 or equal. All other return duct work shall be externally wrapped with the same insulation as the supply duct work. b. Supply duct Insulation – OWENS CORNING Fiberglas all-service faced duct wrap insulation, 2" thick or equal. c. All duct work shall be insulated exterior of the duct on both the low pressure and high pressure side of VAV boxes. All exceptions to this rule must be approved by the University. All ductwork shall be externally lined. External wrapped duct work that is exposed shall have a smooth coating applied.

The material determined by the use of space. d. Noise reduction elbows can be internally lined with a duct liner certified not to be an agent for mold and mildew growth. e. All VAV boxes shall come with a true vapor barrier (aluminum / scrib)

Equipment Insulation a. All equipment shall be double wall construction (large air handlers). Small devices shall come with a vapor barrier on all insulation that meets the air stream. b. The R factor shall be not less than R-13 and all support post, panels, and access doors. All drain pans shall be insulated and shall be free from the threat of condensation. c. All air handlers shall be of double wall construction with or without anti-microbial coatings. The air handler must physically fit the assigned space and provide adequate room for other accessories that are assigned to the air handler first.

Piping Insulation

1. Piping insulation – ARMSTRONG 1 1/2" Fiberglas (NOT Armaflex) .

2. All vertical runs up to 7 feet shall be jacketed.

3. All drain lines from chill water coils and pans shall be insulated with no less than ½” armaflex insulation.

4. ALL Hot water piping shall be insulated a minimum of 1” formed fiber glass with vapor barrier. All fittings to be full to the thickness of the existing insulation. The covering shall match the thickness and be PVC.

5. Chill water piping shall be insulated a minimum of 1-½” of formed fiber glass. All fittings shall be full to the thickness of the existing insulation. The covering shall match the thickness and be PVC. h. Closed cell insulation on refrigerant lines shall be no less than ½” thickness and joints shall be air tight.

Closed cell insulation is good on all valves and accessories that cannot have fiber glass insulation on it.

All voids shall be full. Closed cell insulation is NOT to be used on high temperature piping. i. All insulated piping shall bear “NO ASBESTOS” warning labels

6. Cover all exposed insulated lines with an aluminum jacket and proper labeling.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 38 of

7. Install all components in strict accordance with manufacturer’s installation instructions.

Commissioning of HVAC

1. The commissioning agent shall be under state contract and shall be a part of design, control automation, and all aspects mechanical installation.

2. TBR has commissioning contract with ICE. They are to be a part of the design phase as well as the construction and final evaluation of the systems.

PARKING:

General Design Requirements

a. Parking lot design, including lighting fixtures and levels, access and egress, fire lane requirements, landscaping, islands, curbs, and wheel stops to be considered in final design.

Asphalt

ASPHALT PAVEMENT AND BASE

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 39 of

Curbs –

ASPHALT PAVEMENT (HEAVY-DUTY)

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 40 of

COMMERCIAL CURB CUT

STANDARD HANDICAP RAMP

Drainage piping –

Irrigation – see Landscaping

Landscaping – see Landscaping

Striping –

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 41 of

PLUMBING:

General Design Requirements

a. Retrofit all existing plumbing (faucets, showerheads, piping, etc.) to meet present codes. b. Evaluate facilities for large gatherings of people (auditoriums or stadiums) for the number of toilet fixtures needed based on anticipated usage rather than minimum code requirements. c. Utilize automatic flush systems on all water closets and urinals. d. Provide a hydrant on roofs of buildings. e. ALL bathroom installations – new and renovations - shall have a floor drain.

Catch basins -

http://www.memphis.edu/cpd/pdfs/catchbasins.pdf

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 42 of

Fire Protection

a. Install an automatic fire sprinkler system in all new and renovated facilities unless specifically approved otherwise by the University. b. Fire alarm system and clock system to be SIMPLEX. c. Diagram and sketch - http://www.memphis.edu/cpd/pdfs/fireprotection.pdf

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 43 of

FIRE PROTECTION WATER ENTRANCE

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 44 of

Irrigation

Sample irrigation specification –

http://www.memphis.edu/cpd/pdfs/irrigation2.pdf

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 45 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 46 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 47 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 48 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 49 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 50 of

Manholes

a. Typical manhole specification - http://www.memphis.edu/cpd/pdfs/manholes.pdf

MANHOLES

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 51 of

Plumbing Fixtures

a. Typical fixtures specification – http://www.memphis.edu/cpd/pdfs/plumbingfixtures.pdf

Drinking fountains:

Emergency Safety Shower / Eyewash Station:

a. HAWS with 801RFK body spray unit and which valve? The ANSI standard requires a mixing valve to provide tepid water to the units. Either the 9201H

( http://www.hawsco.com/search/products/8309WC/9201H ) or the 9201E

( http://www.hawsco.com/search/products/8309WC/9201E ) should work; defer to the plumbers on the mixing valve.

b. GUARDIAN Eyewash

Faucets a. DELTA :

http://www.memphis.edu/cpd/pdfs/faucets.pdf

Toilet types –

Vacuum breakers

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 52 of

Water Heaters -

http://www.memphis.edu/cpd/pdfs/waterheaters.pdf

Plumbing Materials -

http://www.memphis.edu/cpd/pdfs/plumbingmaterials.pdf

Pipes and Pipe Fittings

a. Galvanized piping shall not be used and shall be abandoned and removed where possible. All new domestic water piping to be copper. b. Do not use solder containing lead. c. All new sewer pipe, interior rain leaders, etc., to be made of cast iron. d. All steam, condensate, high-pressure drip, chilled water supply and return lines to be in separate conduits. Steam and chilled water service lines to have the insulation end stopped. e. Utility conduit system equal to Perma Pipe “P-P casing” for steam (schedule 40 pipe) or Perma Pipe

“Poly-Therm” for condensate, chilled water supply and return (schedule 80 pipe) if direct buried. Tunnel systems are preferred and indicated in Contract Documents if required. seals on any utility conduit system. g. Provide an entrance pit where steam, condensate, and chilled water lines enter the building. h. All transmission lines to enter entrance pits horizontally through the pit walls. Use sleeves and link seals at each opening. i. Use sleeves and link seals (rated per code) at vertical penetrations of HVAC piping. j. HVAC drains to be sized a minimum of 1-1/2 inch ID. Fittings shall be DWV fittings.

k. Drain piping – l. Drain piping above slab – m. Drain piping below slab – n. 6” roof drains –

Valves

a. Use threaded, full port bronze body ball valves with a stainless steel ball in a nylon or Teflon seat. Use no other unless dictated by code requirements. Do NOT use soldered valves. b. Provide full port ball isolation valves for each restroom and stops for each fixture. c. Use sleeves and link seals, rated per code, at vertical penetrations of plumbing piping. d. Install sufficient ball valves on transmission lines to allow shutting off the various systems. e. Do not use “Butterfly” or disc valves for any reason, unless first approved by the University. f. Vent all steam pressure relief valves to the outside of the building safely.

Cut-off Valves

Reduced Pressure Devices -

http://www.memphis.edu/cpd/pdfs/rpd.pdf

Backflow preventers a. Install reduced pressure backflow preventers per code at a maximum 7’ above finished floor. b. Other devices may be required for the protection of the potable water for the campus. These may be taken from the Watts and Wilkins catalogues. c. ALL devices are to be installed in accordance with manufacturer’s instructuions, taking into consideration accessibility of device.

ELECTRICAL:

General Design Requirements

a. All electrical devices to be UL listed and display the proper labeling. b. Retrofit all existing electrical systems (lighting, outlets, etc.) to meet present codes in renovation projects. c. All new transformers, switches, or other electrical devices to be free of PCB or asbestos. d. Connect the building communication systems, computer systems, and energy management/ building automation systems (EMS or BAS) to the University’s network systems. See Standards for Building

Telecommunication Facilities – Section G. e. New equipment rooms to have an appropriate number of duplex ground fault interrupter receptacles mounted no lower than 4’ above the finished floor. f. Provide one (1) 120v, 20 amp circuit for every two (2) vending machines. g. Provide an appropriate number of communication outlets – both telephone and network. h. Circuits DO NOT share neutrals i. MC cable switch leg only

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 53 of

j. DO NOT use BODINE ballasts k. DO NOT use aluminum wiring or bus bars, screw type connectors, MR-16 in new installation or renovation. l. Provide WT sheets for all proposed fixtures m. Use LED where possible n. Multiple switch in presentation areas o. Keyrite high voltage cable q. 120 volt, 20 amp only

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 54 of

Basic Electric Materials & Methods -

http://www.memphis.edu/cpd/pdfs/basicelec.pdf

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 55 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 56 of

Raceways, Conduits, and Trenches

a. Provide adequate conduit for telephone connections, cable, or future non-determined use. b. Relocate all existing exposed conduit to concealed spaces where possible. Run all new conduit in concealed spaces. c. Use no tie wires to support conduit. Caddy clips, if used, must be properly installed per manufacturer’s requests.

Circuit Breakers a. Square D -

http://www.memphis.edu/cpd/pdfs/circuitbreakers.pdf

Electric Conduit Fittings

a. CARLON - http://www.memphis.edu/cpd/pdfs/fittings.pdf

Electric Panels

a. Size all branch circuit panel boards for a minimum of 25% spare capacity. b. SQUARE D – typical specification - http://www.memphis.edu/cpd/pdfs/panels.pdf

Electric Wires and Cables

a. No aluminum wiring, conductors, or components to remain operational or be used in any renovation or new construction. b.

COLONIAL WIRE & CABLE : http://www.memphis.edu/cpd/pdfs/wires.pdf

c.

Wires 8 AWG and smaller should be of proper color from the manufacturer (permanent and continuous color…no tape allowed to change/identify the color).

Elevators

a. Elevator system As approved. Generic elevator spec. Elevator should comply with our new specifications “non-proprietary equipment”. b. Finishes Rough-in Walk

Off carpet flooring. Brushed metal walls. c. Elevator fire department key box As approved. d. HVAC for elevator equipment e. Elevator sump pumps

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 57 of

Emergency Phones

a. Emergency Phone (New Facility Interiors / Lobby) – Locations and type of emergency phone in lobbies of new facilities to be specified by The University of Memphis designer. b. Emergency Phone (Site) – CODE BLUE; Holland, MI. (616) 392-8296. Model: Code Blue , 8’6”, medium bronze finish, emergency phone and lights. http://www.memphis.edu/cpd/pdfs/emerphones.pdf

c. Emergency Phone (Site) – All NEW Installations as of Summer 2013 shall be TALK-A-PHONE brand. See website at http://www.talkaphone.com/products

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 58 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 59 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 60 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 61 of

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 62 of

Exterior Lighting

a. Exterior lighting to be energy efficient and compatible with that of the existing area. b. HUBBELL “Magnudisc II Series” and poles - http://www.memphis.edu/cpd/pdfs/exteriorlighting.pdf

Exterior Light Levels:

All exterior lighting to be metal halide or fluorescent meeting the following average foot-candle levels for the designated area: Walkways 3 fc; Building Entrances 10 fc; Open Lawns 3 fc; Large

Open Areas 0.5 fc. See specifications, site plan, or Facility Plan.

Parking Lot Lighting

All exterior lighting to be metal halide or fluorescent meeting the following average foot-candle levels for the designated area: Parking 6 fc. and Parking Garages 12 fc. See specifications, site plan, or Facility Plan.

Exterior Post Luminaries

1. Post Top Fixture with 175 watt clear lamp; dome style with luminous top; dark bronze housing; multi-volt quad tap ballast; arch adapter for 3 inch round pole; arm accessory; and medium base socket. a. Post – 3” outer diameter round anodized aluminum pole; 10’ height X 0.072” nominal wall thickness; dark bronze finish; without inlet hole.

b. Base – Heavy duty flange base for 3” outer diameter pole; welded steel construction; dark bronze finish; four (4) 3/8 inch diameter x 12” long zinc plated anchor bolts, nuts, and washers.

c. Base Cover – for heavy-duty flange base; one piece aluminum construction for 3” outer diameter post, dark bronze finish.

Generators

a. Emergency generator to provide power for new emergency systems and emergency lighting. b. ONAN Series of generators - http://www.memphis.edu/cpd/pdfs/generators.pdf

High Voltage Switches

a.

G&W Electric Co . Series of switches -

http://www.memphis.edu/cpd/pdfs/hvswitches.pdf

Interior Lighting

a. Interior lighting to be energy efficient fluorescent except in designated areas. T8 standard 4’ lamp.

b. Exit light – EXITRONIX 400U; Series WB-BL . Single or double faced diffused LED exit; die cast aluminum housing, supplied with completely universal design with 2 face plates, a back plate and mounting canopy. Optional features include self testing/diagnostic operation; flasher, buzzer, LED down light, damp rating, fire alarm interface, etc. Red or green LED’s, ¾” fully illuminated letters, constant uniform illumination, no visible LED’s, maintenance free, battery back-up; 25 year warranty, with 5 year pro-rated battery warranty with short circuit and voltage surge protection.

c. Dispose of all fixtures removed. Verify all fixture locations before beginning installation. Connect new lighting to existing circuits. Install in strict accordance with manufacturers’ instructions, NEC, and approved submittals. Entire installation to be complete and functional without any assistance from the University.

d. Typical specifications for Interior Lighting - http://www.memphis.edu/cpd/pdfs/interiorlighting.pdf

Lighting Controls -

http://www.memphis.edu/cpd/pdfs/lightingcontrols.pdf

Transformers

a. 3 Phase General purpose dry type 600v and below - http://www.memphis.edu/cpd/pdfs/transformers.pdf

ELECTRONIC:

General Design Requirements

1. Fire alarm reports to Miller and Police services

2. All IT equipment in separate closet from ME or Electrical

3. Door system – LENEL BASIS

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 63 of

4. All data wiring and terminations in project to be CAT5.

Audio / Video

Clocks - SIMPLEX -

http://www.memphis.edu/cpd/pdfs/clocks.pdf

Fire Alarm Equipment - SIMPLEX -

http://www.memphis.edu/cpd/pdfs/firealarm.pdf

Audible / Visible a. SIMPLEX multi-application peripherals -

http://www.memphis.edu/cpd/pdfs/audiovideo.pdf

b. Smoke Detectors - SIMPLEX - http://www.memphis.edu/cpd/pdfs/smokedetectors.pdf

Peripherals - SIMPLEX -

http://www.memphis.edu/cpd/pdfs/peripherals.pdf

Radios - MOTOROLA -

http://www.memphis.edu/cpd/pdfs/radios.pdf

Security Systems -

http://www.memphis.edu/cpd/pdfs/security.pdf

Intrusion Detection Remote Devices and Sensors -

a. Occupancy sensor system – LEVITON “Decora” # OSSMTMD/GD wall switch multi-technology

Occupancy sensor. NO SUBSTITUTION. Limited 5-Year warranty. For correct Model Number when ordering see data sheet http://www.leviton.com/OA_HTML/ProductDetail.jsp?partnumber=OSSMT-

MDG&section=38557&minisite=10251

INTERIOR DESIGN:

General Design Requirements

4. All new ceilings to be acoustical lay-in panels, using standard stock ceiling tiles, unless another material is required by code and approved in writing by the University. Grid system to be University standard installed according to Guidelines for Seismic Restraint Direct Hung Suspended Ceiling Assemblies by

Ceiling & Interior Systems Construction Association. Gypsum board ceilings not permitted for any application.

5. Floors in private offices generally are to have carpet. Large areas of system furniture generally to have carpet tile modules. Assembly areas generally are carpeted. Hallways are generally vinyl composition tile. Other specific areas to match specific projects’ Facility Plan.

6. Card access readers must be included in the project according to University standards and details.

7. Security vision lights to be considered in new door applications.

8. Stacked seating – see attached “EDS Maestro 0608” sheets

Blinds –

Carpet –

Paint

a. Interior paint to be semi-gloss enamels for halls, restrooms, classrooms, and trim and satin finish for offices.

Restrooms

a. All toilet partitions to be ceiling hung. b. Toilet tissue dispensers to meet University standard specifications. c. Turn towel dispensers to have a pull handle with automatic paper cutter. d. Floors and walls to be ceramic tile with minimum grout width. Substrate to be concrete, concrete backer board, or other approved waterproof material. Tile finish on walls to be matte glaze finish. Tile finish on floors to be unglazed. e. Countertops to be solid surface with integral bowls. f. Mirrors above lavatories to be full coverage.

Toilet, Bath, and Laundry Accessories

All items are to be sized, configured, and mounted to comply with all regulations and job requirements

MIRRORS:

1. Mirror - BOBRICK B-290 1836 , one-piece stainless steel frame, satin finish, float / plate glass mirror.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 64 of

2. Mirrors – Group - polished plate glass with pencil polished edges trimmed with multi piece metal channel frame system at top and bottom, adhered to substrate, custom size.

3. Mirror – Single - BOBRICK B-165 series, one piece channel frame, stock size.

4. Mirror – Single - BOBRICK B-293 series, fixed tilt, stock size; use at accessible locations where BOBRICK B-

165 series is unable to be mounted to meet accessibility requirements.

5. Mirror - Polished plate glass with pencil polished edges mounted with nickel-plated brass J-clips # 318 at top and bottom.

Provide submittals and dimensions for approval, mount as directed.

GRAB BARS:

Grab bars – BOBRICK B-5806 Series , 1 1/4" diameter stainless steel with concealed mounting snap flange, satin finish. Grab bar and concealed mounting plates to be type-304 stainless steel with satin finish (or satin finish with peened gripping surface; add .99 suffix to model number). Grab bar shall have wall thickness of 18-gauge and outside diameter of 1-1/4". Distance from inside of grab bar to finished wall shall be 1-1/2". Flanges shall be 1/8" thick stainless steel plate, 2” x 3-1/8" in diameter, and each shall have two screws holes. Flange covers shall be 22gauge and snap over mounting flanges to conceal mounting screws. Grab bar shall have 90º return to flange. Ends of grab bar shall pass through flanges and be heliarc welded to form one structural unit. Manufacturer’s service and parts manual shall be provided to building owner/manager upon completion of project.

TOWEL DISPENSERS:

1. Towel dispensers - (all dispensers must accommodate 8" or 9" 800' roll towels and have sub towel feature): a. BOBRICK B-3960 Classic series roll towel dispenser/waste receptacle, flush front unit

(requires 9-5/8" depth mounting) where depth will not permit the above model the following models may be used if accessibility regulations permit: b. BOBRICK B-3961 Classic , semi-recessed, similar to the above, (requires 4" depth mounting) c. BOBRICK B-39619 Classic , surface mounted, similar to the above (stainless steel skirt for surface mounting) where mounting requirements do not permit integrated dispensers / waste receptacles to be used and accessibility regulations permit, the following models may be

used: d. BOBRICK B-3861 Classic series roll towel dispenser, flush front unit, (requires 9-5/8" depth

mounting) e. BOBRICK B-38616 Classic series roll towel dispenser, similar to above, semi-recessed for 3-

1/2" walls f. BOBRICK B-2860 Classic series roll towel dispenser, similar to above, surface mount (use coordinating waste receptacles from BOBRICK line, use fully recessed, semi-recessed, or surface mounted to coordinate to dispenser if possible and conditions / regulations permit, size capacity to job requirements, model numbers are to various to include herein).

Note: BOBRICK Contura series does not include a roll towel unit at the present time, determine if

BOBRICK " Trimline " might be suitable instead. The University will accept this Trimline series if look of components throughout job can be coordinated and our standard towels and other supplies used. This will modify most model numbers herein.

2. Combination Roll towel / waste receptacle BOBRICK B-39617 Classic series Recessed Convertible

Paper Towel Dispenser/Waste Receptacle.

SOAP DISPENSERS:

1. Soap dispenser – At wall hung lavatories: BOBRICK B-2111 Classic , corrosion resistant valve, satin finish stainless steel vertical soap dispenser. Mount per job and accessibility requirements and so drips are caught by lavatories and do not spill on floor. .

2. Soap dispenser – At counter-set lavatories / vanities, moderate demand areas or counters with one, two, or three lavatories - BOBRICK B-822 series, one per sink, top refilled, spout length to depend on lavatory type/size, capacity of individual units per demand. At high demand lavatories or counters with more than 3 sinks –

BOBRICK B-922 series reservoir system, top refilled, spout length to depend on lavatory type/size, maximize capacity for group by interconnecting units full width with 3" black ABS piping, BOBRICK coupling T, and matching BOBRICK end caps. Lavatory layout and counter structure to coordinate with this product so units can interconnect. Units are plastic with double stick tape mounting.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 65 of

TISSUE DISPENSERS:

1. Toilet tissue paper dispenser, double roll – BOBRICK B-2740 . Double-roll toilet tissue dispenser shall have a heavy duty cast-aluminum bracket with satin finish. Theft resistant spindles to be molded highimpact ABS with retractable pins and concealed locking mechanisms. Unit shall accommodate two (2) standard core tissue rolls up to 6” diameter (2000 sheets). NOTE: provide two (2) each at ADA stalls.

2. Toilet tissue paper dispenser, large & stub rolls – GEORGIA-PACIFIC GP #58150 Jumbo Jr.

toilet tissue dispenser with stub roll feature & mandrel. High-capacity VISTA 9” jumbo tissue dispenser holds one roll up to 10.625” in diameter and one 5” diameter stub roll. Covered key lock design. Color: translucent smoke.

3. Toilet Tissue Dispenser – handicap accessible restrooms only : BOBRICK B2740 Classic Series surface mounted for two rolls. For all other compartments : SANJAN Sanr309TBK Reserver Roll Dispenser with stub roll compartment.

SANITARY NAPKIN DISPOSAL UNITS :

1. Sanitary Napkin Disposal Unit - BOBRICK B-354 , Classic Series . Stainless steel with satin finish; partition mounted to serve 2 compartments. Use BOBRICK B-353 for recess wall mount application. For surface mounting where above units are not suitable to job requirements use BOBRICK B-254 . Do not include napkin/tampon vending units in contract .

Provide submittals and dimensions for approval, mount as directed.

Signage

a. Interior signage (including room numbering) to be according to University standard building signage requirements. See attached sheets. b. University standard Logo / Symbol colors : FedEx/U of M Silver: #PMS 877; U of M Blue: #PMS 280;

FedEx Purple: #PMS 2685. In cases where the metallic cannot be used for U of M, specify #PMS 422. c. Restroom Signage – Tennessee Code Annotated § 68-15-301 (2013). Required Posting: Each person, enterprise, agency or entity that maintains publicly-owned restroom facilities available to the general public shall post in a prominent place within each such restroom a sign, at least six inches (6”) high and fourteen inches (14”0 wide, that reads as follows: “ FOR GOOD HEALTH, PLEASE WASH YOUR

HANDS ” (2 lines). HISTORY: Acts 1994, ch. 920, § 1. See sign below:

<< INSERT SIGN IMAGE >> d. Room Numbering procedure –

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 66 of

EXTERIOR DESIGN:

General Design Requirements

a. Exterior building facades - shall incorporate basic elements of brick and limestone to match the existing campus environment unless specifically approved. b. Roofs are to be sloped. c. Entrance Prominence: main entrance to be clearly defined and identifiable. d. Provide space for newspaper and magazine stands near entrances with adequate public access. e. Plaza designs to conform to Campus Master Plan. Concrete reinforcing, patterns, widths and concrete mix to match campus standard details.

Brick

Curtain Walls

Doors

a. All new exterior entrance doors to be aluminum storefront insulated glass with airlock vestibule design and recessed floor mats.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 67 of

Precast

Roofing: -

Elastomeric Membrane Roofing

Ethylene- Propylene- Diene- Monomer (EPDM) Roofing a. Single ply membrane system 60 mil EPDM ballast system. No substitutions. b. EPDM Bonding Adhesive – CARLISLE’s Solvent-Free EPDM Bonding Adhesive. Adhesive is designed for a single-sided, wet lay-in installation on roofs with slopes of 1”:12” or less. No mixing required, solvent-free and non-flammable, odor free, complies with Low-VOC regulation, provides excellent adhesion between various substrates and non-reinforce3d EPDM membranes. Coverage: 100 square feet per gallon of finished surface.

Adhesive is a heat and moisture curing adhesive. Curing times vary depending on weather conditions at time of installation. NO SUBSTITUTION. Refer to manufacturer’s product cut-sheet at http://www.carlislesyntec.com/default.aspx?page=view&mode=media&contentID=1864&frompage=search&s=s olvent-free EPDM Bonding adhesive for more info and installation instructions.

Signage

a. Each facility to have exterior building signage. Provide program and directional signage as required. b. University standard Logo / Symbol colors: FedEx/U of M Silver: #PMS 877; U of M Blue: #PMS 280;

FedEx Purple: #PMS 2685. In cases where the metallic cannot be used for U of M, specify PMS 422.

Weapons on School Property : State official citation and Signage

Tennessee Law Official Citation - Tenn. Code Ann. § 39-17-1309 (2013)

39-17-1309. Carrying weapons on school property.

(a) As used in this section, "weapon of like kind" includes razors and razor blades, except those used solely for personal shaving, and any sharp pointed or edged instrument, except unaltered nail files and clips and tools used solely for preparation of food, instruction and maintenance.

(b) (1) It is an offense for any person to possess or carry, whether openly or concealed, with the intent to go armed, any firearm, explosive, explosive weapon, bowie knife, hawk bill knife, ice pick, dagger, slingshot, leaded cane, switchblade knife, blackjack, knuckles or any other weapon of like kind, not used solely for instructional or school-sanctioned ceremonial purposes, in any public or private school building or bus, on any public or private school campus, grounds, recreation area, athletic field or any other property owned, used or operated by any board of education, school, college or university board of trustees, regents or directors for the administration of any public or private educational institution.

(2) A violation of this subsection (b) is a Class E felony.

(c) (1) It is an offense for any person to possess or carry, whether openly or concealed, any firearm, not used solely for instructional or school-sanctioned ceremonial purposes, in any public or private school building or bus, on any public or private school campus, grounds, recreation area, athletic field or any other property owned, used or operated by any board of education, school, college or university board of trustees, regents or directors for the administration of any public or private educational institution. It is not an offense under this subsection (c) for a nonstudent adult to possess a firearm, if the firearm is contained within a private vehicle operated by the adult and is not handled by the adult, or by any other person acting with the expressed or implied consent of the adult, while the vehicle is on school property.

(2) A violation of this subsection (c) is a Class B misdemeanor.

(d) (1) Each chief administrator of a public or private school shall display in prominent locations about the school a sign (following), at least six inches (6'') high and fourteen inches (14'') wide, stating:

FELONY. STATE LAW PRESCRIBES A MAXIMUM PENALTY OF SIX (6) YEARS

IMPRISONMENT AND A FINE NOT TO EXCEED THREE THOUSAND DOLLARS ($3,000) FOR

CARRYING WEAPONS ON SCHOOL PROPERTY.

(2) As used in this subsection (d), "prominent locations about a school" includes, but is not limited to, sports arenas, gymnasiums, stadiums and cafeterias.

(e) The provisions of subsections (b) and (c) do not apply to the following persons:

(1) Persons employed in the army, air force, navy, coast guard or marine service of the United States or any

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 68 of

member of the Tennessee national guard when in discharge of their official duties and acting under orders requiring them to carry arms or weapons;

(2) Civil officers of the United States in the discharge of their official duties;

(3) Officers and soldiers of the militia and the national guard when called into actual service;

(4) Officers of the state, or of any county, city or town, charged with the enforcement of the laws of the state, when in the discharge of their official duties;

(5) Any pupils who are members of the reserve officers training corps or pupils enrolled in a course of instruction or members of a club or team, and who are required to carry arms or weapons in the discharge of their official class or team duties;

(6) Any private police employed by the administration or board of trustees of any public or private institution of higher education in the discharge of their duties; and

(7) Any registered security guard/officer who meets the requirements of title 62, chapter 35, and who is discharging the officer's official duties.

HISTORY: Acts 1989, ch. 591, § 1; 1990, ch. 1029, § 8; 1991, ch. 510, §§ 1-3; 1996, ch. 1009, § 24.

Windows

a. Windows shall be dark bronze anodized frames with insulated UV protected glazing. Refer to specific projects’ Facility Plan for detailed requirements of location. All exterior windows to be aluminum frame and insulated glass with operable portions.

TELECOMMUNICATIONS:

General Design Requirements

a. Building telecommunications standards - http://www.memphis.edu/cpd/pdfs/telecomstandards.pdf

General Cable Standards - Section 1

The Vendor must respond to the following specifications found in this section when submitting the proposal:

1.0

General Specifications

1.1

Code Compliance

1.2

Conduit / Coring / Sleeves /

Backboards

1.3

TR Hardware

1.4

Fire-stopping

1.5

Indoor UTP Cable

1.6

Cable Manufacturer

1.7

Cable Installation Guidelines

1.8

Workstation Termination

1.9

Information Outlets

1.10

Information Outlet Configuration

1.11

Cable Run per Workstation

1.12

Workstation Cable Run Length

1.13

Telecommunication Rooms (TR)

1.14

TR Tie Cables

Technical Specifications:

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 69 of

1.15

TR Termination Details

1.16

Riser Termination Blocks

1.17

Station Patch Panels

1.18

Station Patch Panel Configuration

1.19

Patch Cables

1.20

Data Racks

1.21

Copper Riser

1.22

Fiber Optic Riser

1.23

Fiber Optic Connectors

1.24

Fiber Optic Distribution Centers

1.25

Patch Cord Management Panels

1.26

Ladder Rack and Accessories

1.27

Flex-Type Cable Tray and

Accessories

1.28

Tie-Wraps

1.0

General Specifications

Vendor must agree to adhere to the specifications and guidelines provided in this section. The Project

Manger must approve any deviation or substitution. Any conflicts between the specifications in this section and the Construction Drawings must be brought to the attention of the Project Manager for resolution or clarification.

1.1

Code and Standards Compliance

Vendor shall comply with all federal, state, county and local building and fire codes applicable to the installation of inside wiring, including articles 800 and 250 of the National Electric Code.

Vendor shall comply with all applicable low voltage cabling standards including:

TIA/EIA 568-B.1, Commercial Building Telecommunications Cabling Standard

ANSI/TIA/EIA 568-B.2, Commercial Building Telecommunications Cabling Standard - Part 2:

Balanced Twisted Pair Cabling Components

ANSI/TIA/EIA 568-B.3, Optical Fiber Cabling Components Standard

TIA/EIA 569-B, Commercial Building Standard for Telecommunications Pathways and Spaces

TIA/EIA 606-A, Administration Standard for Commercial Telecommunications Infrastructure

J-STD-607-A, Commercial Building Grounding (Earthing) and Bonding Requirements for

Telecommunications

TIA/EIA-758, Customer-Owned Outside Plant Telecommunications Cabling Standard

TIA/EIA-942, Telecommunication Infrastructure Standard for Data Centers

BICSI Telecommunications Distribution Methods Manual, version 11

BICSI Information Transport Systems Installation Manual, 4th Edition

In all above listed standards and guidelines, vendor responsible for adhering to the most current versions, TSB, revisions and addenda existing at the time of installation.

Anywhere standards conflict with federal, state, county and local building electrical and fire codes applicable to the installation of inside wiring, vendor will defer to codes.

1.2

Conduit / Coring / Sleeves / Backboards

Vendor shall provide any required riser conduit, sleeves, floor coring, fire-rated backboards, as identified in the Construction Drawings.

1.3

TR Hardware

Vendor will provide any required main distribution or intermediate distribution frames required for installation.

1.4

Fire-stopping

Vendor shall provide or replace any required fire-stopping materials for riser cores which were provided by, or accessed by, the Vendor or its subcontractor during cable installation, as required by local building th and fire codes. All fire-stopping shall comply with recommendations from BICSI TDMM 11 edition, or most current version, except when in conflict with federal, state or local fire codes.

1.5

Indoor UTP Cable

A. Description: Voice and data distribution cables shall be 4-pair, 24 AWG, 100 ohm, UTP, Category-6.

All data distribution cables shall meet or exceed the Category-6 specifications of TIA-568-B.2, all applicable additions and addenda or their current equivalents for maximum NEXT, Attenuation, and

Return Loss. All cable installed in an air plenum environment must be plenum rated and have low smoke properties in accordance with Article 800-3(d) of the National Electric Codes. Vendor shall ensure that plenum-type cable is installed where required.

B. Purpose: To be routed from the TRs or MC (IDFs or MDF / Data Center) to data modules at the workstation outlets and for Tie cables where applicable.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 2 of

Manufacturer

Plenum-rated

Part No.

PUP6504BU-U

Non-Plenum-rated Part

No.

X Panduit TX6500

General GenSPEED 6000 7131431 X

1.6

Cable Manufacturer

Preferred voice and data cable manufacturers and their part numbers are listed above. Any substitutions to this list must have prior approval from the University of Memphis. The cable used shall be part of a certified structured cable plant solution and matched to the proper components.

1.7

Cable Installation Guidelines

A. All cables shall be independently supported throughout the entire project as recommended in

ANSI/TIA/EIA 568B, 569B and in the BICSI TDMM 11 th

Edition or most current versions.

B. All cables shall be protected from harm while passing through spaces that are either not the property of the Owner or are under construction.

C. The Contractor shall route in-groups of similar types (i.e., each voice distribution and data distribution cable shall be grouped with its kind) within the Data Center and TRs.

D. Cables shall be installed in accordance with ANSI/TIA/EIA 568B.1 and TIA-569-B standards.

E. Cables shall be routed point-to-point (home-run). Cables shall not be spliced.

F. When routing cables in furniture systems, Contractor shall utilize raceways provided for this purpose.

G. When routing cables in walls, Contractor shall utilize stub-ups where provided by the Construction

Manager (CM) for this purpose.

H. The outside sheath of any cable shall not be damaged.

I. The Contractor shall terminate cables properly on both ends.

J. The Contractor shall provide and install bushings for any conduit, poke-through or sleeve that will be utilized.

K. The Contractor shall provide and install sleeves for all penetrations where one has not been provided.

L. The Contractor shall provide proper temporary protection for cables after pulling is complete but before final dressing and termination are complete. Cable shall not be left lying on the floor. Cable shall be bundled and tie wrapped above the floor ready for termination.

M. The Contractor shall use Velcro-style straps to tie-wrap all cables. Tie-wrap shall occur on two (2)foot intervals when supported by ladder rack or any exposed cable (i.e., when running from ladder rack down to the equipment racks).

N. Traditional cable ties shall be used where required to properly support cables and to protect them from harm of other environmental elements. (i.e., to be used in ceilings to keep cables off of lighting fixtures or ceiling grids).

O. During installation, the Contractor shall comply with the manufacturer’s recommendation for pulling tensions.

P. The Contractor shall comply with the manufacturer’s recommendation for the short- and long-term minimum bend radius.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 3 of

Q. The Contractor shall provide and install spiral coil-wrap on all cables that are run in an exposed manner, accessing the furniture system, as required.

1.8

Workstation Termination

A. All cable, connecting hardware and terminations shall meet the following standards:

1. TIA/EIA 568-B.2, 568-B.3 and all current TSB, addenda and revisions at the time of installation.

2. Industry standards and methods.

B. The Contractor Shall:

1. Install all connecting hardware per manufacturer’s instructions and recommendations.

2. Field terminate all cables unless otherwise noted.

3. Terminate cables in proper order and sequence.

4. Utilize proper tools when performing terminations.

5. Leave no more that a 0.25 inch of untwisted cable at the terminated ends.

1.9

Information Outlets

A. Description: Outlets shall be a combination of the products listed below to create the proper outlet in compliance with the Construction Drawings. The proper color “blank” insert must occupy any spare ports in a faceplate. Any modular furniture faceplates must be test-fitted with the furniture prior to fulfilling the project’s required quantities. All 8-pin modules shall be Category-6 and wired according to TIA 568B wiring code (pin-out). Provide the proper faceplate for the location. Coordinate with furniture manufacturer as required.

B. Purpose: For termination of typical wall- and furniture-mounted telecommunication outlet cables.

C. Acceptable Products:

Description

Wall-mount 2-port faceplate

Furniture 4-port faceplate*

F-Type Module

Cat 6, 8-pin modular RJ45 jacks

Flat

CFKE2 (EI)

CFFPL4BL

CMFEI

CJ688TGOR**

Slopped

X

X

X

X

Enhanced

X

X

X

X

* Must confirm compatibility with furniture manufacturer

**For other colors replace suffix IW

Typical Configuration

The typical information outlet, wall- or furniture-mounted, shall contain one (1) modular non-keyed RJ-45 type jack unless specified as other on the Construction Drawings. All jacks will provide a universal Voice or Data functionality and shall be terminated sequentially on the patch panel. All colors for outlets and faceplates must be coordinated with the Project Manager. When non-keyed RJ-45 type jacks specified on the Construction Drawings, selected products should be compatible with faceplates listed above when possible.

Modular Furniture Outlets

All modular furniture outlets must be coordinated with other trades to ensure properly sized “in-feeds” and pathway capacity. All cables exiting a wall cavity or floor sleeve must be protected until the cables enter

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 4 of

the furniture system. Any costs for scheduling offsets or “come-backs” for dressing the furniture must be included in base bid price.

1.10

Information Outlet Configuration

The first outlet port jack module shall be installed in the top left port of the wall-mounted faceplate or first

(left) port of the furniture faceplate. The second jack module shall be installed in the second port (top right) of a wall-mount faceplate, or the second port of the furniture faceplate. The third jack module shall be installed in the third port (bottom left), and third port of the furniture faceplate. The fourth jack module shall be installed in the last port.

1.11

Cable Run per Workstation

Each typical workstation (information outlet) shall receive one (1) 4-pair UTP cable. Each cable shall have all four (4) pairs terminated on one (1) jack module. Splitting of cables onto multiple jacks is not acceptable. Any requirements to split or serve multiple devices from a single cable shall be accomplished via external splitters.

1.12

Workstation Cable Run Length

The maximum run of cable from any workstation to a TR closet, or to the MC shall not exceed 290 linear feet with an allowance for patch cords. The overall length of the circuit (including patch cords) from desktop device to LAN equipment shall not exceed 100 meters.

1.13

Telecommunication Rooms (TRs, formerly referred to as IDFs)

TR usage will be dictated by the physical layout of the location including, but not limited to, the number of floors and number of workstation locations. The Project Manager will provide Construction Drawings verifying the layout of the TR. In cases where specific construction documentation is not provided for

TRs, the following specific guidelines must be adhered to:

A. In a multi-floor office situation, each floor will have at least one (1) TR. In the event that more than one (1) TR is utilized on a single floor, each TR will be linked together utilizing a minimum 12 strand multi-mode fiber cable. All cables used under this part shall meet all of the specifications outlined in

Paragraphs 3.5 and 3.6.

B. In a single-floor office situation, the MC (MDF) shall serve as the only termination point for workstation cables.

1.14

TR Termination Details

A. All voice / data station cables shall terminate sequentially on termination panels where they will be patched with RJ-45 patch cables to the network / VoIP switch.

B. All data station cables shall be terminated onto rack-mounted patch panels. Patch panels shall be flat or angled modular patch panels.

C. All voice station cables shall be terminated onto rack-mounted patch panels. Patch panels shall be flat or angled modular patch panels.

1.15

Riser Termination Blocks

A. Description: 300-pair 110-type block field termination kit with label kits and clear covers for TRs and

MDF. Termination blocks in the TRs shall have legs for wall mounting. Label colors must conform to

TIA-606-A standards. Products installed must be part of a certified structured cabling solution.

B. Purpose: To terminate voice riser and distribution cables in TRs and MDF.

C. Acceptable Products:

Item

300-pair 110 block w/ legs

110 Horizontal Wire Management w/ legs

4-pair connector clips

Standard Density High Density

P110BW300-X GPKBW432Y

P110JTW-X P110JTW-X

P110CB4-X GPCB4-XY

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 5 of

5-pair connector clips P110CB5-X GPCB5-XY

D. Installation Guidelines

1. Provide and install 300-pair 110-type blocks (with blue labels) for termination of the voice / data distribution cables in each TR as shown on the Construction Drawings.

2. Install the uppermost termination block or cable management at a height 6’6” AFF as per

Construction Drawings.

3. Terminate individual cable pairs using proper tools.

4. Print and install label strips on the front of each termination block.

5. Each cable shall be labeled before the termination point at the block.

6. Not unravel more than 1/2" of each twisted pair before the termination point.

7. Not strip more than 1/2" of the outer jacket of each cable at the termination point.

8. Terminate distribution cables in proper outlet labeling order as indicated on the floor plans.

1.16

Station Patch Panels

A. Description: Panduit 24 or 48-port Category-6 rack-mounted modular patch panels that accept modules for UPT, fiber optic and audio/video.. Patch panels shall be wired according to TIA 568B. All patch panels shall provide space for a label for each port.

B. Purpose: To terminate data outlet and wall field tie cables in the TRs. To terminate tie cables in the

Data Center and other technology spaces within.

Item

24-port MODUALR Patch Panel

48-port MODULAR Patch Panel

High Density 48-port MODULAR

Patch Panel

Flat Angled

CPP24FMWBLY CPPA24FMWBLY

CPP48FMWBLY CPPA48FMWBLY

CPP48HDEWBL CPPA48HDEWBL

1. Provide and install modular patch panels onto racks in the TRs for terminating the data distribution cables and tie cables.

2. Provide and install label strips on the front and for each port of the patch panels. Labeling type and style shall be per Section 5 and the Construction Drawings.

3. Terminate the distribution cables in proper outlet labeling order as indicated on the floor plans.

4. Terminate individual cable pairs utilizing proper tool.

5. Provide and install horizontal and vertical wire management panels as shown in the construction drawings. There shall also be a wire management panel between each 2 rack units of flat modular patch panel.

1.17

Station Patch Panel Configuration

The Vendor shall install the data and voice station cables such that the data / voice ports appear from left to right on the station patch panel with “Voice 1” appearing next to “Data 1” appearing next to “Data 2” and so on across the entire row before moving down to the next row. Each patch panel port shall have a typed, non-smearing label using a self-adhesive sticker indicating the port number in accordance with the

Cable Identification and Labeling Section. All labels shall be machine generated. Hand written labels will not be accepted.

Patch Panels will be installed on the rack in accordance with the typical elevation drawing provided in these specifications. Any deviation to these drawings will be provided in the Construction Drawings.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 6 of

1.18

Patch Cables

The Vendor shall provide all patch cables required for completing Ethernet connections between the equipment patch panels and station patch panels. Provide one (1) patch cord of the appropriate size for each data cable installed. These patch cables shall be double-ended RJ-45 TIA Category-6 cables.

Cables shall be of the same manufacturer of the structured cabling solution and shall be part of the channel warranty.

1.19

Data Racks and Cabinets

The Vendor shall provide and install open bay, 19-inch wide, 7-foot high data rack(s) to accommodate all station patch panels.

A. Description: Universal 19”, self-supporting 7’0” high rack with double-sided #12-24 EIA universal mounting hole spacing. This rack shall be UL listed for a 1,000 lbs. load rating and assembled using paint piercing washers to electrically bond rack when assembled.

B. Four Post Racks shall have an option for cage nut rails and support a minimum of 2,000 lbs.

Cabinets shall incorporate dual hinged doors and inset frame post that creates large and accessible vertical pathways for routing cables.

C. Purpose: For supporting LAN hardware and patch panels in TRs and MC and to provide adequate path-cord management.

D. Acceptable Product: Panduit.

Description

Standard Two Post Rack

4 Post Rack

Switch Cabinet

Server Cabinet

Cage Nut Rails #12-24 treaded rails

CMR4P84CN

CMR19X84

CMR4P84

CN2C CN1,CN2,CN3

CS2C CS1,CS2,CS3

1. Provide and install racks and cabinets in locations shown on the Construction Drawings.

2. Use Leveling Legs to plumb cabinet. Set all cabinets equally at one-inch (1”) height AFF.

3. Use spacers or other hardware to plumb racks. Adjacent racks shall be bolted together as per manufacturer’s instructions with vertical wire managers in-between.

4. Bolt all 19” racks to floor slab or strut system that is bolted to slab. Racks shall not be bolted to raised floor only.

5. Install racks and cabinets straight and perpendicular to walls.

6. Side panels shall be mounted at the end of each row of cabinets.

7. Provide and install label for each rack and cabinet.

1.20

Copper Riser

If there is a need for a copper riser, then the Vendor shall size each analog/voice riser (cabling between the MDF and TR(s)) to accommodate a minimum of 1 pair of UTP cable per user or network drop being supported by the TR.

A. Description: 50-pair Category-3 cables can be utilized for riser cable. Riser cables shall be 24 AWG,

100 ohm, UTP, CMR or CMP and shall meet or exceed the TIA-568-B specifications for Category-3.

All cable installed in an air plenum environment must be plenum rated and have low smoke properties in accordance with Article 800-3(d) of the National Electric Codes. Vendor shall insure that plenum-type cable is installed.

B. Purpose: To be routed from the riser termination blocks at V-MDF to the wall field in the TRs. To provide connectivity from the PBX and Telco services to desktop devices.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 7 of

C. Acceptable Product or approved equivalent:

Description Manufacturer

Plenum-rated

Part No.

Non-Plenum-rated Part

No.

50-pair General 2131757.99 X

D. Installation Guidelines

1. The Contractor shall provide and install riser cables to each TR. All cables routed vertically shall have independent support structures. Contractor shall provide all vertical and horizontal ladder rack required to support risers.

2. The Contractor shall route all riser cables through slots, sleeves and conduits as shown on the

Construction Drawings.

3. In the TRs, Contractor shall terminate all voice riser cables onto wall-mounted 300-pair, 110- type termination blocks.

4. Upon entering a TR, Contractor shall route riser cable to the back of the backboard, using ladder rack, and terminate on termination blocks. Riser cables shall be routed behind the backboard mounted on standoff brackets or studs.

1.21

Fiber Optic Riser

A. Description: The fiber optic backbone shall consist of 12-strand multimode (MM), plenum rated fiber optic cables with Kevlar-strength member. Cables shall be suitable for indoor use in a ceiling plenum. The backbone cable shall meet EIA-472C and 10 Gigabit Ethernet. All multimode fiber optic cables must be

50 micron laser-optimized and shall meet or exceed all optical and mechanical specifications defined within TIA/EIA-568-B.3-1 Optical Fiber Cabling Components Standard - Addendum 1 – “Additional

Transmission Performance Specifications for 50/125 um Optical Fiber Cables” and TIA-492AAAC-A

“Detail Specification for 850-nm Laser-Optimized, 50-um Core Diameter/125-um Cladding Diameter

Class Ia Graded-Index Multimode Optical Fibers (2003).” The color of the outer jacket shall be orange for

MM. Cable must be part of the warranted system and be consistent and compatible to the products specified. Construction Drawings will specify exact cable types to be installed.

B. Purpose: To provide connectivity between the TRs and the D-MC in the riser and TR-to-TR ties. To be used in the Data Center for inter-rack and cabinet tie cables.

C. Acceptable Products: Panduit and General

Riser Description

6-strand SM OFN

12-strand SM OFN

24-strand SM OFN

48-strand SM OFN

6-strand MM OFN

Plenum

X

X

X

X

X

12-strand MM OFN

24-strand MM OFN

X

BG-0241PNU-1LPA,

FOPPX24Y

48-strand MM OFN X

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 8 of

X

X

X

X

X

X

X

X

1. Do not exceed maximum pulling tension.

2. Do not exceed minimum short-term and long-term bend radius.

3. Avoid sharp bends and corners.

4. Provide additional crush / mechanical protection in high-risk environments.

5. Observe all governing building and fire codes (either by using a properly listed cable or suitable raceway).

6. Do not deform the cable jacket, specifically when using cable fasteners or ties.

7. When routing in conduits with an outside diameter in excess of 2.5”, fiber cables shall be routed through inner duct.

8. Pulling compound shall be used if making long or difficult pulls to reduce cable drag.

9. When Contractor uses any mechanical device to pull the fiber optic cable, a dynameter and clutch or shear pin must be used to ensure the maximum pulling tensile strength of the cable is not exceeded.

10. The fiber cable will be attached to the pull line via the strength member or mesh grip.

11. Install fiber optic cables separated from other cables to minimize potential damage when additional cables are installed or retrieved.

12. A minimum of two (2) one-inch (1”) inner duct shall be installed in any conduits connecting the

TRs on a typical floor or in the riser.

13. Install fiber optic cable to minimize potential damage when additional cables are installed or retrieved.

14. When routing horizontally within the TRs on the ladder rack, utilize one-inch (1”) inner duct to the point of entry of the patch panel. Secure the cable in inner duct every twenty-four (24) inches to the ladder racks, in TRs.

15. Fiber optic riser cables routing vertically in bulk throughout a riser shaft do not require the use of inner duct. One-inch (1”) inner duct shall be used where the fiber optic cables transition horizontally from the riser shaft to the racks for termination.

16. When routing vertically through a riser shaft, keep fiber optic cables segregated from the voice

UTP risers. Cables must be secured and dressed in a neat professional manner without distorting the outer jacket. Prior to installation, the client’s consultant must review the method of securing fiber cables to the vertical ladder rack.

17. Ensure that manufacturer’s recommended minimum bend radiuses, for short and long term, are not exceeded.

18. In the Data Center, all single mode fibers shall terminate in separate patch panels from multimode as per Construction Drawings.

19. In the TRs, all fiber optic cables shall terminate in the same patch panel.

20. The amount of cable slack at termination points shall allow the cable to be routed to the termination location with enough additional cable to reach a convenient location for terminating.

21. Termination hardware location shall allow convenient use, termination and facilitate relocating if required.

22. Fiber optic warning signs shall be placed on all innerduct and conduits containing fiber optic to help prevent potential damage to the cable.

23. A fiber optic warning sign featuring the dangers of LASER shall be visibly affixed to all fiber termination centers.

24. At each end of a cable run, approximately five (5) feet of slack shall be left for cable repairs, connecting and moving of equipment. Coil and dress neatly in the rack.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 9 of

1.22

Fiber Optic Connectors

A. Description: Fiber optic connectors shall be LC-type field polish or cam-style multimode. Insertion loss shall be equal to or less than .2dB. The proper termination kit must be used.

B. Purpose: To terminate all fiber optic riser and tie cables.

C. Acceptable Products:

Description

Multimode (62.5um) SC connector

Field Polish

X

Pre-Polished

X

Multimode (50um) 10 Gig SC connector

Multimode (62.5um) LC connector

Singlemode (8.3um) SC connector

X

X

X

X

X

X

Singlemode (8.3um) LC connector

Multimode (50um) 10 Gig LC connector

X

FLCSMEIY

X

FLCSMCXAQY

D. Installation Guidelines

1. Provide and install an "LC" connector onto each strand of each end of each cable.

2. Follow manufacturer’s instructions for installing each connector.

3. Leave a minimum of three (3) feet of slack of each strand and coiled carefully in termination center tray.

4. Leave a minimum of (6) feet of slack service loop stored on wall, rack, or other appropriate place near fiber cross connect . Service loops shall be mechanically protected (coiled in D-rings on wall or in contained a separate storage enclosure on rack). Free hanging service loops will not be accepted.

1.23

Fiber Optic Distribution Centers

A. Description: Fiber optic termination center loaded with LC coupler panels where required.

Termination centers must be sized for a minimum of 30% growth. The termination must be assembled using the products specified below.

B. Purpose: For termination of fiber optic riser and tie cables in Data Centers, TRs and other technology spaces.

C. Acceptable Products:

Items

24-port Rack Mount Fiber Housing

Manufacturer

Panduit OptiCom

Part No.

FRME1

48-port Rack Mount Fiber Housing

72-port Rack Mount Fiber Housing

144-port Rack Mount Fiber Housing

12-strand SM SC coupler panel

12-strand MM SC coupler panel

12-strand SM LC coupler panel

24-strand SM LC coupler panel

24-strand MM LC coupler panel

12-strand MM LC coupler panel

Panduit OptiCom

Panduit OptiCom

Panduit OptiCom

X

X

X

X

Panduit OptiCom

Panduit OptiCom

FRME2

FRME3

FRME4

X

X

X

X

FAP12WAQDLCZ

FAP6WAQDLCZ

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 10 of

6-port SM SC coupler panel

6-port MM SC coupler panel

X

X

X

X

1. Provide and install 72- and 48-port fiber optic termination centers for TRs.

2. Extend the inner duct to termination center entrances. Cables shall be secured inside the termination center by tie-wrapping the Kevlar fibers and jacket at the entrance point. Individual fiber cables shall be broken out inside the enclosure. Approximately five (5) feet of spare cable shall be coiled up before termination onto the LC connectors.

3. Terminate all strands of the fiber optic data backbone cables onto the backside of LC coupler panels using LC connectors.

4. Install LC connectors on each individual strand of fiber optic cable.

5. Use field installed LC connectors using a field termination kit per manufacturer’s instructions.

6. Label all fiber optic cables using appropriate machine generated, self-laminating cable labels in compliance with TIA/EIA 606-A.

1.24

Patch Cord Management Panels

A. Description: 19” wide cable management units. Will be either one (1) or two (2) RUs in height with front fingers and back D-rings. Hinged covers for both from and rear. Install as per Construction Drawings or typical rack elevation.

B. Vertical cable management panels shall extend from top to bottom of rack and incorporate hinged doors or covers. Management fingers spacing should correspond TIA/EIA Rack spacing.

D.

C. Purpose: To support and manage patch cables on front and rear of equipment racks as shown on

Construction Drawings.

Acceptable Product: Panduit

Description Net Manager Patch Link

2RU 19” Management Panel NM2 WMPH2E

1RU 19” Management Panel NM1 WMPSE

Vertical Cable Mangement

4-inch wide Rack Mounted

6-inch wide Rack Mounted

8- inch wide Rack Mounted

10-inch wide Rack Mounted

Net Runner

WMPV45E

WMPVHC45E

Patch Runner

PRV6

PRV8

PRV8

12-inch wide Rack Mounted PRV12

1.25

Ladder Rack and Accessories

A. Description: Dual Rail “Telco”-type Ladder Rack. Provide ladder rack as shown on Construction

Drawings. Ladder rack system shall be assembled using the product specified below.

1. 12”, 18” and 24” wide ladder rack style.

2. 1-1/2” side rails.

3. 12” rung spacing.

4. Black in color.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 11 of

B. Purpose: For supporting cables overhead, and for supporting the riser cables vertically in the TRs as indicated on the Construction Drawings.

C. Acceptable Products or approved equivalent:

Description

24” Ladder Rack

Manufacturer

AFCO

Part No.

AS-2410S-BLK

18” Ladder Rack

12” Ladder Rack

24” Wall Support Kit

18” Wall Support Kit

AFCO

AFCO

AFCO

AFCO

AS-1810S-BLK

AS-1210S-BLK

AS-WSK24-BLK

AS-WSK18-BLK

12” Wall Support Kit

24” End Closing Kit

18” End Closing Kit

12” End Closing Kit

Butt Splice Kit

Right Angle “T” Splice

Cross Member Radius Drop

Protective End Cap

Moveable Cross-member 18”

Vertical Wall Bracket

(height and width may vary)

Foot Attachment Kit

AFCO

AFCO

AFCO

AFCO

AFCO

AFCO

AFCO

AFCO

AS-WSK12-BLK

AS-ECK24-BLK

AS-ECK18-BLK

AS-ECK12-BLK

AS-BSK

AS-RAT

AS-CRD-18C-BLK

AS-PEC

AFCO SPAS-MCM118-BLK

AFCO AS-CRSB-18-04-BLK

AFCO AS-FAK

1. Install straight, level and perpendicular to walls as indicated on Construction Drawings.

2. When installed vertically, provide the proper gauge hardware to adequately stand off the wall where necessary.

3. Provide accessories to connect and support ladder rack as required.

4. Provide sufficient support methods to support three (3) times the weight of the cable.

5. Utilize accessories listed. Provide additional accessories, fasteners, concrete anchors, etc., necessary to support and install the ladder rack.

6. Install per the Construction Drawings to provide support and management of cables.

7. Materials or hardware necessary is not limited to what has been specified. Any additional miscellaneous hardware is the responsibility of Contractor. Substitute product by same manufacturer is acceptable if it simplifies installation or results in cost savings. The Owner’s representative must approve any such substitutions.

8. Coordinate installation with other trades.

9. When cable quantities warrant it, vendor shall use cable stackers and spillover accessories to avoid crushing fiber cable or violating manufacturers recommended bend radii.

Description Manufacturer Part No.

24” Ladder Rack AFCO AS-2410S-BLK

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 12 of

Description

18” Ladder Rack

Stackable Cable Rack Spacer, .08 OD cable

Stackable Cable Rack Spacer, 1.25 OD cable

Cable management waterfall for use with ladder rack

Manufacturer

AFCO

Part No.

AS-1810S-BLK

Panduit CRS6-X

Panduit CRS4-125-X

Panduit CMW-KIT

1.26

Flex-type Cable Tray and Accessories

A. Description: Basket-type cable tray. Provide cable tray to support the “Day One” cables plus 60% spare

(use a 40% fill ratio).

1. 8”, 12”, 16” wide x 2” deep “flex-type” cable tray.

3. Proper fittings and elbows.

B. Purpose: To provide main pathways for horizontal distribution cables in ceiling plenum and accessible support in ceiling system.

C. Acceptable products or approved equal:

Description

10’ section of 8” x 2” cable tray

10’ section of 12” x 2” cable tray

10’ section of 18” x 2” cable tray

8” and 12” Center-hung support bar

18” Center-hung support bar

Fast Splice kit

Right-angle kit

Manufacturer

EZ Tray

EZ Tray

EZ Tray

EZ Tray

EZ Tray

EZ Tray

EZ Tray

Part No.

CF 54/200 EZ

CF 54/300 EZ

CF 54/450 EZ

FAS P300 CH

FAS P450 CH

EDRN

EZ T90

1. Install straight, level and perpendicular to walls as indicated on the Construction Drawings.

2. Provide accessories to connect and support ladder rack as required.

3. Provide sufficient support methods to support three (3) times the weight of the cable.

4. Cable shall be installed using center-hung brackets and threaded rod at five (5)-foot intervals.

5. Utilize accessories listed. Provide additional accessories, fasteners, concrete anchors, etc., necessary to support and install the ladder rack.

6. Install per the Construction Drawing to provide support and management of cables.

7. Materials or hardware necessary is not limited to what has been specified. Any additional miscellaneous hardware is the responsibility of Contractor. Substitute product by same manufacturer is acceptable if it simplifies installation or results in cost savings. The Owner’s representative must approve any such substitutions.

8. Coordinate installation with other trades.

1.27

Tie-Wraps

A. Two (2) types of tie-wraps shall be utilized: Locking-type and Velcro-type.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 13 of

a) Description: Locking straps, plenum rated, sized adequately to properly bundle, tie and support cable. b) Purpose: To bundle and support cables in the ceiling area. Provide a neat and orderly cabling installation. c) Acceptable Product:

Description

4” Plenum rated cable ties

Manufacturer

Panduit

Part No.

PLT1M-C702

7.4” Plenum rated cable ties

11.6” Plenum rated cable ties

Panduit

Panduit

PLT2S-C702

PLT3S-C702 a) Description: Velcro-type straps, sized adequately to properly bundle, tie and support cable as required. b) Purpose: To bundle and support cables on overhead ladder rack in the TRs and MC. Used to provide a neat and orderly cabling installation. c) Acceptable Product:

Description

Velcro Tak-Ty in 75’ roll. Cut to length

Manufacturer

Panduit

Part No.

HLS-75RO

Testing and Documentation Section 2

This section covers information the vendor needs to cover testing and documentation of the proposed installation.

It also covers the method of payment from USA. This includes:

2.0 Cable Plant Certification and Testing Summary

2.1 Submittals

2.2 Reference and Standards

2.3 UTP Cable Test Equipment

2.4 Fiber Optic Test Equipment

2.5 UTP Test Procedure

2.6 Category-5e/6 Cable System Test

2.7 Category-3 Cable System Test

2.8 Fiber Optic Cable Test

2.9 Test Results

2.10 Successful Test / Certification

2.11 Documentation

Testing and Documentation

2.0

Cable Plant Certification and Testing Summary

The Contractor shall provide all personnel, equipment, instrumentation and supplies necessary to perform the required testing for UTP and fiber optic cables. Notification of any planned testing shall be given to the Owner at least fourteen (14) days prior to any test. The Contractor shall develop the test plans defining all the tests required to ensure that the cable plant meets technical and performance

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 14 of

specifications. The test plans shall define milestones for each test, equipment, personnel, facilities and supplies required. The test plans shall identify the capabilities and functions to be tested. The test plan and test forms shall be reviewed and must be approved by the Owner prior to commencement of any test. Contractor shall implement any comment by the Owner and resubmit the test plan and test form.

All test results will be submitted in electronic format and hardcopy giving all readings, date, tested by and totals.

All testing will be performed on approved equipment.

The Contractor shall test all cables and repair and re-test at the Contractor’s expense. All UTP distribution cables shall be tested for Category-6 compliance in accordance with TIA 568-B.1, TIA 568-

B.2 and TIA 568-B.3. The following systems and cables shall be tested after the installation is fully completed:

1. Voice / Data distribution cables from outlet to the point of termination in TRs.

2. UTP Riser cables, from each termination block in TRs to each termination block in the Data

Center.

3. Fiber optic backbone cables from TRs to the Data Center.

4. Inter-cabinet fiber and copper cabling.

5. Inter-floor tie cables.

6. Cross-floor tie cables.

7. Rack-to-wallfield tie cables.

2.1

Submittals

A. All submittals shall be included in the bid documents.

B. Submit product data of test equipment to be used.

C. Submit sample of reports that will be generated to document test and performance.

2.2

References and Standards

A. TIA 568-B.1 and all applicable TSB, addenda and revisions. Vendor shall use most current version at time of installation.

B. TIA 568-B.2 and all applicable TSB, addenda and revisions. Vendor shall use most current version at time of installation.

C. TIA 568-B.3 and all applicable TSB, addenda and revisions. Vendor shall use most current version at time of installation.

(Telecommunications Distribution Methods Manual, 10 th

edition or most current version).

E. Test equipment instruction and guidelines.

2.3

UTP Cable Test Equipment

A. Test / Certification equipment shall include appropriate test accessories. The test equipment shall comply with all requirements within TIA 568-B.1 and 568-B.2 TIA Level III accuracy, or whatever

Level of accuracy is most current at the time of installation. The test equipment for UTP cables shall be certified and capable of testing Category-6 cables.

B. Acceptable Products: Level III Micro-Test Omni-Scanner, Fluke DSP or DTX test sets.

C. All testers shall have been factory calibrated within 12 months of use of testing. Vendor shall be able to provide proof of factory calibration upon request.

D. All testers shall be field-calibrated prior to each day’s testing and following any break in testing over one hour.

2.4

Fiber Optic Test Equipment

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 15 of

A. Light Source and Power Meter for multimode fiber. Power Meter must operate within the range of

850

30 nm and 1300

20 nm in accordance with TIA526-14-A. All testers must be able to record, store and print test results. The test equipment shall be calibrated and traceable to National

Bureau of Standards (NBS).

B. Acceptable Products: To be provided by the Contractor and approved by Corning.

2.5

UTP Test Procedures

A. Each pair of all UTP cables shall be tested. Each test shall be performed for end-to-end results.

B. The Contractor shall perform inspection for, overall cable length, DC resistance, continuity, proper connectivity, split pairs, open and short pairs, reversed pairs, EMI noise induction, damaged cable, stretched cable, kinked or crimped cable, end-to-end attenuation in dB, NEXT in dB and impedance mismatches.

C. The Contractor shall test cables for end-to-end attenuation and cable length..

2.6

Category-6 Cable System Test

A. Each data outlet and cable shall be tested and certified for permanent link compliance with TIA

Category-6.

B. Each pair shall be tested end-to-end (from the outlet port through the port at Category-6 data patch panels). Two (2) ten (10)-foot patch cables shall be used at the test unit end so that the outlet, outlet termination, cable and termination block can be observed in the test. End-to-end attenuation loss and near-end cross-talk shall be tested from 0.772 to 250 MHz and shall meet or exceed Category-6 TIA 568-B requirements.

C. All tested cables shall pass all performed tests. End-to-end attenuation loss and NEXT shall meet or exceed Category-6, TIA 568-B requirements.

2.7

Category-3 Cable System Test

A. Each pair of all Category-3 cables shall be tested. Each test shall be performed for end-to-end results.

B. The test shall be performed from 0.772 to 16 MHz with approved test equipment. The Contractor shall test each cable according to manufacturer’s instructions.

2.8

Fiber Optic Cable Test

A. All fiber optic cables shall be fully tested in compliance with TIA-526-14-A for multimode..

B. The multimode fiber optic cables shall be tested utilizing a power meter in both directions using

850 nm and 1300 nm wavelengths.

C. The following guidelines must be followed for each system test:

1. All test jumpers shall be of the same fiber core size and connector type as the cable system.

2. The power meter and the light source must be set to the same wavelength.

3. Light source and OTDR must operate within the range of 850

30 nm and 1300

20 nm in accordance with EIA/TIA 526-14. Power meters shall be calibrated and traceable to National

Bureau of Standards (NBS). Proper “Launch Cables” must be provided if needed.

4. All connectors, sleeves and jumpers shall be properly cleaned before start of any test procedure.

5. No strand shall exceed the expected attenuation.

2.9

Test Results

A. The test results for all UTP cables shall include:

1. Overall cable length.

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 16 of

7. EMI noise induction.

9. Stretched, kinked or crimped cable.

10. Attenuation load in dB.

11. NEXT in dB.

2.10

Successful Test / Certification

A. The Contractor shall download the results and measurements obtained from the cable point testing to a computer program. The Contractor shall tabulate individual test results in chart and graph forms. The test result shall be submitted to the Owner and the engineer for evaluation and approval. The Contractor shall comply and implement all comments from the Owner or the engineer without any additional cost to the Owner. Upon receipt of approval, the Contractor and manufacturer shall certify the cable plant and issue a warranty for a minimum of fifteen (20) years.

B. If a problem or fail test occurs, the Contractor shall evaluate and remedy the problem without any additional cost to the Owner.

C. After a problem has been remedied, the Contractor shall retest the circuit and resubmit the test result to the Owner and engineer for analysis. The Contractor is to continue this process until required results are achieved.

D. The Contractor is responsible for correcting and resolving any issues raised by the Owner or its representative with respect to workmanship or deviation from standards stated herein.

2.11

Documentation

Contractor will provide all documents easily understood for each system as follows: Documentation is to be submitted for approval prior to commencement of work.

The above tests results shall be furnished in writing to the University prior to acceptance.

A. As-Builts of Inside Wiring Cable Records (two (2) copies) showing station IDs and Cable Routes.

Station cables shall be marked red. Riser cable shall be marked green. Inter-closet cable / tie cable

(if applicable) shall be marked blue.

B. Cross-Connect Reference Indexes for Cable, TR and MDF I.D (two (2) copies).

2012_STANDARDS_RevisionP (OCT2013).doc 10/31/2013 10:27 AM

Standard Design Requirements Page 17 of

Download