central plaza parking garage

advertisement
Table Of Contents
Category
Description
Pages
CENTRAL PLAZA PARKING GARAGE
NE 41ST ST. SEATTLE, WA 98105
FINAL PROPOSAL
MAY 10, 2013
CLIENT
Month Day Year
Table Of Contents
Category
Description
Pages
1
Project Summary
Executive Summary
Summary of Project and Client
Mission Statement
Resumes
Energy Use Analysis/Retrofit
7
Energy Assessment
HVAC Existing Conditions
Proposed HVAC Retrofit
Lighting Existing Conditions
Proposed Lighting Retrofit
10
Lighting Retrofit
New System Design
Assessment of Space
Light Output
Fluorescent Lamp Disposal
Impacts
Table Of Contents
Category
Description
Electrical Vehicle Charging Station
Pages
17
Charging Station Analysis
Implementation
Design
Charging Station Savings Summary
Alternative Energy Retrofit
21
Ventilation Overview
Proposed Ventilation System
Renewable Energy Overview
Proposed Photovoltaic System
Client Image
Schematic Estimate and Schedule
26
Schematic Estimate
Estimate Breakdown
Estimate
Schedule Summary
Schedule
Zoning Plan
Project Management Plan
Site Layout
Safety Plan
31
Table Of Contents
Category
Description
Pages
33
Financing Plan
Grants, Rebates and Incentives
Lighting Incentives
Photovoltaic Incentives
EV Charging Station Incentives
Financing Strategies
Payback Analysis
37
References
Outreach Appendix
Community Energy Awareness
Energy Awareness Plan Feedback &
Poster Example
Article in University Newsletter
Feedback Letter from the Client
Local NECA Chapter Interation
University of Washington Interaction
Appendix
A – Alernatives Considered
B – Lighting
C – EV Charging Station
D – PV Energy
120 Architecture Hall | University of Washington | Seattle, WA 98105
Project Summary
Executive Summary
May 10, 2013
Brian Ho, Parking Facilities and Special Events Manager
University of Washington
3745 15th Avenue NE
Seattle, WA 98195-5360
Dear Mr. Brian Ho,
Husky Electric appreciates the opportunity to present our formal proposal for an energy efficient
upgrade of the Central Parking Garage. Our team intends to deliver the project and complete the
scope of work in 42 calendar days beginning June 14, 2013, and achieve project completion by
August 12, 2013. The initial cost of the project is $423,180. We have identified $227,115 in
incentives and rebates that will reduce the cost to the University of Washington to $196,065.
Projected annual savings indicate this project will earn a return on investment in 1.7 years.
Husky Electric’s scope of work includes:
 A complete retrofit of the lighting system
 Installation of electrical vehicle charging stations
 A ventilation system upgrade
 Implementation of a photovoltaic energy system
Any work within the proposal that is not self-performed will be subcontracted and managed by
Husky Electric. Additionally, Husky Electric aims to work with the UW to increase campus energy
awareness by involving and improving upon current sustainability efforts.
Husky Electric understands UW’s dedication to environmental sustainability without sacrificing
the historical integrity of the campus. We are proud to be given the opportunity to assist the UW
in this commitment. Our team is confident that our proposal will not only meet your
requirements, but also surpass expectations.
Husky Electric would like to apply a technical analysis score adjustments as follows:
Lighting retrofit proposal x 1.4
Energy Audit/Retrofit Proposal x 1.0
PV and Wind Proposal x 0.6
We look forward to providing the electrical work and solution management for this project.
Sincerely,
Brandon Burr
Project Manager
Husky Electric Inc.
May 10, 2013
1
120 Architecture Hall | University of Washington | Seattle, WA 98105
Summary of Project and Client
The University of Washington has provided Husky Electric with many resources and an excellent
opportunity by supporting the NECA Student chapter evaluation of the Central Parking Garage
for “The Green Energy Challenge.” Although the Central Parking Garage and the above Red
Square are seen as iconic structures on campus, it has potential to meet the rising sustainable
standards of the university.
Originally constructed in 1972, the Central Parking Garage is a 416,390 sq. ft. underground
parking garage located in the center of the campus under other iconic buildings including Meany
Hall, Kane Hall, Odegaard Library, and Suzzallo Library. The parking garage features three
separate vehicle entrances and a total of 984 parking stalls on three floors. There are four stairs
that access Odegaard Library, Kane Hall, Meany Hall, and outside to the west side of the
structure. The Central Parking Garage’s outdated electrical systems provide the University of
Washington and Husky Electric the opportunity to work together to save money and reduce the
university’s energy consumption.
Husky Electric has two main points of contact for the retrofit of the Central Parking Garage:
Brian Ho, the Parking Facilities and Special Events Manager, and John Shaheen, Assistant
Director of UW Transportation Services. Also we have worked with the Capital Projects Office,
which is responsible for developing and overseeing most projects on the University of
Washington campus. These points of contact emphasized the importance of financial acuity and
safety on campus during the development of this proposal.
Striving to be a leader in sustainability, the University of Washington is committed to
environmental responsibility. Many of the new construction projects and renovations are
required to meet or exceed a LEED Gold rating. The University of Washington actively works to
become a green campus through a multi-faceted approach. Recycling, composting, and
sustainable dining programs have all been recently implemented around campus. Additionally,
the University of Washington has taken serious efforts to raise awareness of these efforts to
encourage others to follow.
The Central Parking Garage has long been recognized as a building in need of renovation.
Upgrading the Central Parking Garage presents a unique opportunity to further the University of
Washington’s green aspirations while preserving its historical roots. This renovation will further
exemplify the university’s commitment to the environment.
May 10, 2013
2
120 Architecture Hall | University of Washington | Seattle, WA 98105
Mission Statement
“Promoting Green Energy by providing our clients with services that are both
energy efficient and economically effective.”
Husky Electric aims to provide exceptional electrical construction services and energy solutions
consulting to aid in the effort to make the world a more sustainable environment. Our excellent
reputation exemplifies the effectiveness of our involvement and dedication to the green energy
industry. The quality of our services and value added to our clients demonstrate our experience
and expertise in this field.
Project Team
Brandon Burr, Project Manager: Brandon will coordinate all team activities and serve as the
primary source of communication between the project team and client. Brandon managed the
development of this proposal and holds authority over his team’s decision making process.
JB Gibson, Estimator/Scheduler: JB is responsible for handling the team’s budget and developing
and maintaining the project schedule. He will work in conjunction with the superintendent to
determine how the project will be built.
Kali Leachman, Superintendent: Kali will use areas surrounding and inside the Central Parking
Garage to create and adapt the site logistics plan. Also, Kali will be coordinating all work for the
scope of this project.
David Moore, Design Manager: David performs all calculations to determine the annual
savings this project will generate. He also oversees the other design engineers.
Tara Harrington, Lighting Design Engineer: Tara is responsible for the lighting retrofit design
and will work throughout the project to ensure the design requirements are met.
Matthew Watson, Alternative Energy Engineer: Matt is responsible for designing the alternative
energy production system and will work throughout the project to guarantee proper installation
and operation of the new system. He will also oversee the ventilation system upgrade.
Brandon
Burr
Project Manager
David
Moore
JB Gibson
Estimator/Scheduler
Design Manager
Tara
Harrington
Lighting Design
Engineer
May 10, 2013
Matthew
Watson
Alternative
Energy Engineer
Kali
Leachman
Superintendent
3
120 Architecture Hall | University of Washington | Seattle, WA 98105
Resumes
Brandon Burr
(425) 233-7198 | beeyoudoubler@me.com |
4131 Wallingford Ave N, Seattle, WA 98103
Work Experience
Kiewit Construction, Honolulu, HI (2012): Project Engineer Intern
Economy Fence Company, Everett, WA (2009,2011): Lead Laborer Intern
Alpha Sigma Phi, Seattle, WA (2010): Lead Recruitment Director
Education
University of Washington (2009-Present)



Bachelor of Science Degree in Construction Management
GPA: 3.25
Graduation: Spring 2014
Activities


Associated Students in Construction (ASIC) Member
NECA Student Chapter
Awards/Recognition


Guinness Book of World Record Holder
Sigma Lambda Chi Honor Society
Matthew Watson
206) 290-2760 | m9watson@u.washington.edu |
23425 39th Pl Brier, WA 98036
Work Experience
Skanska USA Building, Seattle, WA (2012): Project Engineer Intern
Granite Construction, Bellingham, WA (2011): Project Engineer Intern
All Phase Concrete, Mountlake Terrace, WA (08-12): Concrete Apprentice
Education
University of Washington (2009-Present)



Bachelor of Science Degree in Construction Management
GPA: 3.34
Graduation: Spring 2014
Activities





Associated Students in Construction (ASIC) Member
Fraternity Service Project Chairman
Tree House for Kids
PUSH International Volunteer
NECA Student Chapter
Awards/Recognition

May 10, 2013
ASC Reno LEED Competition – 3rd place
4
120 Architecture Hall | University of Washington | Seattle, WA 98105
David Moore
(360) 632-2094 | dmoore12@u.washington.edu |
5520 17th Ave NE, Seattle, WA 98105
Work Experience
College Pro Painters, Seattle, WA (2012): Franchise Manager
College Pro Painters, Seattle, WA (2011): Job Site Manager
College Pro Painters, Oak Harbor, WA (08-12): Painter/Technician
Education
University of Washington (2009-Present)


Bachelor of Science Degree in Construction Management
Graduation: Spring 2014
Activities



Associated Students in Construction (ASIC) Member
Theta Delta Chi Delegate
NECA Student Chapter
Awards/Recognition

Participant in sustainability study in Fortune 500 companies and worked on
development of scoring system
JB Gibson
(206) 235-8185 | jbgibson6044@gmail.com |
6044 164th Ave SE, Bellevue, WA 98006
Work Experience
Sellen Construction, Seattle, WA (2012): Project Engineer Intern
Beta Theta Pi, Seattle, WA (2012): House Manager
Clise Properties, Seattle, WA (2010,2011): Laborer
Education
University of Washington (2010-Present)




Bachelor of Science Degree in Construction Management
Bachelor of Arts Degree in Business Administration (Entrepreneurship)
GPA: 3.7
Graduation: Spring 2014
Seattle University – Matteo Ricci College (2009-2010)

GPA: 3.9
Activities



Associated Students in Construction (ASIC) AGC FLF Correspondent
ASC 2013 Region 7 Commercial Construction Student Competition
NECA Student Chapter
Awards/Recognition



May 10, 2013
University of Washington Deans List for 7 Quarters
Sigma Lambda Chi Honor Society
2013 AGC Foundation Scholarship Recipient
5
120 Architecture Hall | University of Washington | Seattle, WA 98105
Tara Harrington
(425) 319-1305 | tarah4@uw.edu |
12807 72nd St SE, Snohomish, WA 98290
Work Experience
UW Capital Projects Office, Seattle, WA (2012-13): Student Intern
University of Washington, Seattle, WA (2012): Business School Grader
Dionne and Rorick, Seattle, WA (2012): Receptionist & File Clerk
Education
University of Washington (2010-Present)



Bachelor of Science Degree in Construction Management
GPA: 3.51
Graduation: Spring 2014
Activities






Associated Students in Construction (ASIC) Treasurer
Delta Zeta Sorority Technology Chair/House Manager/Risk Manager
ASUW Senator
UW Leaders
Dream Project Mentor
NECA Student Chapter
Awards/Recognition




University of Washington Deans List for 4 quarters
Sigma Lambda Chi Honor Society
Howard S. Wright, Lee S. Evans, AGC Foundation Scholarship Recipient
ASC 2013 Region 7 Mixed-Use Competition 1st Place Winner
Kali Leachman
(206) 913-9992 | leachmank@yahoo.com |
1904 NE 52nd St Seattle, WA 98290
Work Experience
Guy F. Atkinson Construction, Renton, WA (2012): Estimating Intern
Windermere Services, Seattle, WA (2011-12): Receptionist
Kiewit Construction, Silverdale, WA (2008): Quality Control Office Clerk
Education
University of Washington (2009-Present)



Bachelor of Science Degree in Construction Management
GPA: 3.30
Graduation: Spring 2014
Activities



Associated Students in Construction (ASIC) Member
Member of Kappa Kappa Gamma Sorority
NECA Student Chapter
Awards/Recognition

May 10, 2013
University of Washington Deans List for 5 quarters
6
120 Architecture Hall | University of Washington | Seattle, WA 98105
Energy Use Analysis/Retrofit
Energy Assessment
Energy usage data for the Central Parking Garage was provided by the University of Washington
Facilities Maintenance department with the help of the Energy Database McKinstry created for
the entire campus. Energy use is measured on an hourly basis.
Central Plaza Parking Garage Energy Usage
Energy Usage (kWh)
86,000
84,000
82,000
80,000
78,000
76,000
74,000
72,000
70,000
68,000
Above is the monthly energy usage for the Central Plaza Parking Garage. Total annual energy
usage is 953,467 kWh. The following figure shows the breakdown of this total between the
major systems of the Central Plaza Parking Garage.
Energy Usage Breakdown
HVAC System: 34.1%
Lighting System: 50.5%
Miscellaneous Systems: 15.4%
Note: Miscellaneous systems include all systems that fall beyond Husky Electric’s scope of work
and are incorporated with surrounding buildings.
May 10, 2013
7
120 Architecture Hall | University of Washington | Seattle, WA 98105
HVAC Existing Conditions
The Central Plaza Parking Garage is open all hours of the day and therefore requires continuous
operation at varying levels throughout the day. The exhaust system for Central Plaza Parking
Garage works mainly through the use of a plenum for each mechanical room. These plenums are
large open areas that act as a vacuum to allow the air to be removed from the garage. Through
suction, the air is pulled through the plenum and up the exhaust vent, which also pulls in air
through the intakes. This large vacuum works to provide air to all parts of the garage. This
system uses eight fans located in two separate mechanical rooms to exhaust the garage.



East Fan Room: (4) 40 HP fans that discharge vertically out of three brick stacks in Red
Square
West Fan Room: (4) 30 HP fans that discharge up sloping shaft toward 15th Ave NE
VFD’s are currently installed on all exhaust fans allowing “soft” starts and stops reducing
power surge losses
Currently the garage requires no cooling because of two factors. First, the garage being located
underground helps maintain a consistent temperature. Second, the buildings located around the
garage are exhausted into the garage further regulating the temperature of the garage.
Number of Fans
8
Day(s)
Mon. – Sun.
May 10, 2013
Annual Energy Consumption of Exhaust Fans
Run Time (hrs)
Total Energy Consumption (kWh)
Per Exhaust Fan motor
325,486
speed hours schedule
Exhaust Fan Motor Speed Scheduled Hours
Off
100%
50%
0000-0700
0700-0900
0900-1600
1600-2000
2000-2200
Off
2200-0000
8
120 Architecture Hall | University of Washington | Seattle, WA 98105
Proposed HVAC Retrofit
Husky Electric proposes to adjust the exhaust fan schedule on weekends, summer break,
holidays, and breaks when the utilization of the garage is down. With a very low initial
investment, the schedule can be adjusted and the energy usage will decrease a substantial
amount. For full details and cost analysis see the Ventilation System section.
Lighting Existing Conditions
The Central Plaza Parking Garage currently uses 1,717 4-foot T-8 32 watt fluorescent lamps with
electronic ballasts. Near the 3 garage entrances, cold weather ballasts are used. These fixtures
were installed in 1996. The lighting is designated to 4 main control panels; A-1, A-2, A-3 and an
emergency panel. Some light fixtures remain deactivated from a prior lighting renovation, but all
other fixtures are turned on all hours of the day. The garage is currently unpainted concrete
other than a few columns for safety.
Annual Energy Consumption of Light Fixtures
Number of Fixtures
Run Time (Hrs)
1,717
8,760
Total Energy Consumption
(kWh)
481,309
Proposed Lighting Retrofit
Husky Electric will replace the current T-8 fluorescent fixtures with much more efficient LED
fixtures. This replacement also allows us to install much fewer fixtures and still meet the same
lighting requirements for the garage. This option will have a short payback period due to the cost
savings due to the lower energy use from the lower amount of fixtures in the garage. For detailed
cost analysis see the Lighting Retrofit section.
May 10, 2013
9
120 Architecture Hall | University of Washington | Seattle, WA 98105
Lighting Retrofit
New System Design
To provide a design that meets the requests of our owner, safety requirements, local codes and
provides a significant energy reduction and short payback period we focus on six characteristics.
Our main criterion of analysis included:
 Safety
 Energy consumption
 Future costs



Life Expectancy
Maintenance
Controls
In this design we analyzed the installation of new fixture types, the use of occupancy sensors and
the addition of white – reflective paint to the garage. Results from this analysis provide us with a
retrofit design consisting of fixture replacement and occupancy sensor utilization.
Assessment of Space
Existing
Proposed
Fixtures per Floor Breakdown
Lower Level: 612
Middle Level: 528 Upper Level: 577
Lower Level: 75
Middle Level: 66
Upper Level: 84
Total: 1,717
Total: 225
We have developed a new lighting plan which is located on the following two pages. Please see
Figure 1, 2 and 3 for existing reflected ceiling plans and Figure 4, 5 and 6 for proposed reflected
ceiling plans.
Fixture Replacement
The QLP 32G2 LED lamp with the PX10 Proximo Programmable
Occupancy Detector is our proposed fixture for the garage. With
the use of this lamp, we can reduce the fixture count by 1,492
fixtures and the energy consumption by 70.4%.
Our power consumption from lighting will decrease from 481,309
kWh per year to 142,700.4 kWh per year with the installation of the QLP LED fixtures. The
current lighting system is 50.5% of the total energy consumption for the garage and with a
retrofit will decrease to only 26%.
Initial Investment
$238,084.20
Proposed Lighting Cost Analysis
Tax Incentives Cost Less Incentives
Annual Savings
$192,638.72
$45,445.48
$84,652.15
Payback Period
0.54 yrs.
An analysis of our alternative fixture options can be found in Appendix A.
May 10, 2013
10
120 Architecture Hall | University of Washington | Seattle, WA 98105
QLP 32G2 LED Fixture
This particular fixture includes a programmable occupancy detector that dims the light when
motion is undetected. This dimming feature reduces the light output by an additional 20% resulting in extended energy savings. This device is mounted with the lamp and
provides 360˚ range of detection for a radius of 25 feet when mounted 9 feet
high. This device also detects ambient light and ensures that excessive light is not
distributed when daylight is detected. For commissioning and control a wireless
remote is provided to program and update the device. This is a major factor in
the decision to use this fixture. Currently facilities management is struggling to
keep up on maintenance in the garage – thus having a wireless device and simple programming
strategy will be crucial in the new design of the garage.
This fixture comes with a mounting kit and will be mounted on the underside of the beams at a
height of 9 feet. The current fixtures are mounted between the beams – casting shadows through
the space. The new mounting location will pair with the symmetrical light distribution pattern of
the device and better distribute light throughout the garage. This mounting location also
provides the occupancy detectors optimal range and minimal interruption to the sensor.
May 10, 2013
11
120 Architecture Hall | University of Washington | Seattle, WA 98105
Figure 2. Existing Reflected Ceiling Plan – Middle Level
Figure 1. Existing Reflected Ceiling Plan – Upper Level
1 Single Lamp T8 Fixture
2 Fixtures
3 Fixtures
4 Fixtures
5 Fixtures
6 Fixtures
Figure 3. Existing Reflected Ceiling Plan – Lower Level
May 10, 2013
12
120 Architecture Hall | University of Washington | Seattle, WA 98105
Figure 5. Proposed Reflected Ceiling Plan – Middle Level
Figure 4. Proposed Reflected Ceiling Plan – Upper Level
- QLP G2 LED Fixture
May 10, 2013
Figure 6. Propoesd Reflected Ceiling Plan –Lower Level13
120 Architecture Hall | University of Washington | Seattle, WA 98105
Light Output
Foot-Candle Measurements
Using the Extech Easy View 30 Light Meter, we measured the current foot-candles throughout
the garage. Per the Seattle Energy code, 4.5 foot-candles are required in parking garage spaces.
Since the garage is under the policies of the University of Washington, we have been advised that
exceeding the minimum requirements is recommended and encouraged for safety. This garage is
open and operating 24 hours a day, year round and completely underground – allowing for very
minimal natural light near the entrances and a heightened emphasis on safety precautions. With
the QLP 32G2 LED fixture from Quality Lighting, we have met the requirement of 4.5 footcandles, exceeding it in the vast majority of the garage. This fixture provides a better distribution
of light, higher levels of lighting and increased safety in the garage. Please see Figure 7 below and
Figure 8 on the following page to compare the differences in foot-candles in regions of the
garage.
Figure 7. Existing Foot-Candle
Measurements
In our analysis of existing foot-candles, we
measured 27 locations on the lower level
and found that the garage had sufficient
lighting to meet code requirements. The
minimum foot-candles measured were 6 fc
at the Southwest Corner Ramp, and the
maximum measured were 16 fc near the
Southwest corner entrance during the
afternoon.
Figure 8. Proposed Foot-Candle
Measurements
Based on our foot-candle measurements
and the safety codes of the University of
Washington and Seattle, we have selected
a lighting plan that meets the minimum
foot-candles required in a parking garage
and provides comparable levels of lighting
in the garage.
Average fc
8.6
May 10, 2013
Max fc
12.7
Proposed Foot-Candle Measurements
Min fc
Max/Min
4.5
2.8:1
Avg/Min
1.9:1
14
120 Architecture Hall | University of Washington | Seattle, WA 98105
Fluorescent Lamp Disposal
Since January 1st, 2013 the City of Seattle prohibits the disposal of
fluorescent bulbs/tubes from any commercial customer in the municipal
solid waste or at the Seattle transfer stations. (Seattle Municipal Code
21.36.025 – Unlawful Disposal)
As a way of continuing our efforts to go green, we have prepared a plan to recycle all 1,717
fluorescent bulbs removed from the garage through Eco Lights – a fluorescent lamp recycling
company conveniently located 15 minutes away from the campus.
Our magnitude of disposal will require 12 4-ft. Straight Fluorescent Lamp Large Recycling Kits
from Eco Lights, priced at $89 each. Each kit will accommodate 144 4-foot T8 lamps and includes
a container, heavy duty liner, zip tie, instructions and prepaid return services.
According to the Office of Solid Waste and U.S. Environmental
Protection Agency, a T8 Lamp manufactured in 1996 or prior to 1996
contains 30 milligrams of Mercury. This means that our total lamp
disposal contains 151.51 grams of Mercury. Ensuring that this
mercury does not go to landfills is important to the University and is
crucial to keeping our efforts eco-friendly.
May 10, 2013
15
120 Architecture Hall | University of Washington | Seattle, WA 98105
Impacts
Keeping the six key requests of the owner in mind, we have developed a lighting retrofit that
suits the needs of students, faculty and visitors using the garage; provides the owner with a
reduction in costs and maintenance; and utilizes the new LED technology to conserve energy.
Safety – We have ensured that the minimum foot-candle requirements are met and exceeded
and that fixtures will be on during all hours of the day.
Energy Consumption – We have reduced our energy consumption by 70.4% saving the University
$152,374.15 per year.
Future Costs and Life Expectancy – LED fixtures have a remarkable life expectancy and minimal
future costs. Seattle has an average ambient temperature around 50˚F.The table below indicates
that a lamp in this area will last for 24 years when run 24 hours a day, year round. Future costs of
an LED fixture include replacing bulbs every few decades or replacing malfunctioning occupancy
detectors or fixtures as you would with any other fixture.
Life Expectancy of Fixture
Average Outdoor
Ambient
Temperature
(°F)
-22
4
14
32
50
77
95
Predicted LED Life
Expectancy
L70
(Hrs)
292,000
268,000
244,000
220,000
208,000
160,000
136,000
Predicted
LED Life Expectancy
@ 10 Hrs/Day
(Yrs)
80
73
67
60
57
44
37
Predicted
LED Life Expectancy
@ 24 Hrs/Day
(Yrs)
33
31
28
25
24
18
16
Maintenance and Controls – Considering the longevity of the fixtures and wireless controls for
occupancy detectors, the maintenance required for this lighting system is very minimal and
manageable by the current University facilities staff.
The lighting retrofit is an excellent savings and energy conservation opportunity for the
University of Washington.
May 10, 2013
16
120 Architecture Hall | University of Washington | Seattle, WA 98105
Electric Vehicle Charging Stations
Charging Station Analysis
Husky Electric has worked with the University of Washington (UW) conducting comprehensive
traffic studies. We have also conducted surveys with the Central Plaza Garage (CPG) users to
assess the demand of electric vehicle (EV) charging stations. The University of Washington
currently has three (3) charging stations on campus that has attracted a small community of EV
users. With experts predicting an increase of EV's to 300,000 that will be driving on the
Washington State roads over the next decade, this community on campus will continue to grow.
Implementation
After analyzing the data and the surveys that were conducted and in combination with the
predicted increase in the number of EV's, Husky Electric believes that there is an opportunity to
begin to increase the number of stations that UW houses on campus. Our team believes that the
CPG is the ideal location to begin this increase in the number of stations.
Our team at Husky Electric has developed a design that fits the image of the owner and will
provide an opportunity to increase the EV user community on campus. We are proposing that
UW has our team furnish and install 4 new charging stations at each of the three (3) entrances to
the parking garage.
Disadvantages
UW Transportation Services have addressed some concerns with our design team that are the
key reasons for why they have not already begun this EV movement including:
 Not a strong market currently for EV's
 Limited number of trips allowed by City of Seattle
 Financial burden
Because the market for EV's is so small currently, the university does not believe that there is a
need to increase the total number of stations on campus. The university is also concerned
because they are limited to 25,000 vehicle trips to campus each day by the City of Seattle. By
installing these stations, it would not help reduce the total number of trips. With the market still
not at a desirable level, UW feels that it would be more of a financial burden on them than a
benefit to the community. However, our team believes that it has developed a strategy to
mitigate the concerns that the university has addressed.
May 10, 2013
17
120 Architecture Hall | University of Washington | Seattle, WA 98105
Advantages
By installing only 12 stations initially, our team believes that this helps alleviate two of the main
concerns that the university addressed above. Our team believes that allocating 12 stations in the
984 stall CPG will not create an issue by reducing the number of stalls for motor vehicles. Our
team has also developed a strategy for UW to create an additional source of revenue by charging
to use the stations and implementing a free voucher program for users that utilize carpooling.
University Savings*
Initial Cost
-
Instant Incentives
=
$60,015.00
-
$18,005
=
Total Project
Cost
$42,011
/
Revenue
/
$2,971.51
ROI
(Years)
14.14
The detailed summary includes assumptions based on historical data collected from the
Mountlake Terrace Park & Ride garage and current electrical rates. Our team is also making the
assumption that each station would receive four (4) hours of use each 24-hour period. Obviously,
as the market for the EV's increases, the return on investment will approach the break-even point
at a faster pace.
In order for UW to ensure that these stations are being utilized, they must market the stations to
the EV user community. They must also promote the voucher program that our team is
developing for those who decide to carpool. This will not only help the university and Seattle
increase its rating of being the 8th Greenest City in the United States (according to Popular
Science), but it will be beneficial for the user to create additional savings as well.
Consumer Savings*
Average Motor Vehicle
Fuel Cost
$1,668.62
Average Electric
=
Vehicle Charge Cost
$639.44 =
-
Annual Savings
$1,029.18
*See page 20
19 for detailed savings summary
May 10, 2013
18
120 Architecture Hall | University of Washington | Seattle, WA 98105
Design
Overview
Husky Electric received two (2) quotes for stations based on two different models. The CT2103
(Level 1 charger) and the CT2023 (Level 2 charger). In order to fit the desires of the owner, Husky
Electric proposes that the CT2023 charging stations be chosen. There is an increased cost with
selecting the CT2023, however, these stations are better suited for the newer EV's that are being
developed.
Model
-
(3) Charge Point CT2023 Gateway Dual Head 240 Volt Wall Mount Holster
(3) Charge Point CT2023 Dual Head 240 Volt Wall Mount Holster
(5) Year Network Operation & Driver Support Manager
Power System Integration
May 10, 2013
Three-Line Drawing
19
120 Architecture Hall | University of Washington | Seattle, WA 98105
Charging Station Savings Summary
May 10, 2013
20
120 Architecture Hall | University of Washington | Seattle, WA 98105
Alternative Energy Retrofit
Ventilation Overview
In analyzing the existing system, we identified a potential inefficiency. The baseline schedule for
the existing system assumes the same amount of traffic in the structure 365 days per year.
This leads us to believe that the baseline schedule for these fans should be off completely unless
activated by a CO sensor. However this leads to potential safety hazards with the limited amount
of CO sensors in the building. If air in an area of the building were stagnant, there would a greater
possibility of CO sensors failing to detect higher levels of CO in the building.
Proposed Ventilation System
Proposed Solution: Reprograming the ventilation timing system to reduce peak hour ventilation
power from 100% to 50% during weekends, holidays, breaks, and summer quarter.




Eliminates unnecessary run time of fans
Minimizes initial cost
Maximizes controllability of existing system
Utilizes existing CO sensors to ensure safety
Initial Investment
$500
System Reprogram Cost Analysis
Energy Savings Per Year
Total Yearly Savings
80,539.48 kWh
$20,134.87
The current building management system is perfectly capable of having more control over the
baseline exhaust schedule, which eliminates the need for new systems controls. We determined
that we would be able to reduce the baseline schedule for exhaust fans while still maintaining
safe levels of circulation and CO during weekends, spring break, winter break, and holidays
recognized by the University of Washington schedule based on information obtained from
parking services. We determined that the reduction of daily parking permits sold warranted
following reductions.
Breaks (74 Days)
58%
% Drop In Daily Parking Permit Purchases
Summer Quarter (61 Days)
Weekends/Holidays (72Days)
41%
51%
In maximizing the controllability of this system without installing any new equipment, we
minimize the cost of this aspect of work. The only investment would be the reprogramming of
the ventilation system to a 50% fan schedule on those days.
May 10, 2013
21
120 Architecture Hall | University of Washington | Seattle, WA 98105
In the case that an event were to take place during a reduced schedule time period, the existing
carbon monoxide sensors would detect the predetermined level set by the university and turn
the system on to 100% capacity to maintain a safe and healthy environment
Ventilation Alternative:
Installing (2) Cook TCN-B fans and associated ductwork
 Improves cross sectional flow
 Eliminates risk of air stagnation
 Allows baseline schedule for main fans to be “off”
 Additional upfront cost
 Additional electricity to run fans
In looking for alternatives we determined that installing circulation fans would be a feasible
option. Below is a cost estimate of installing a fan on each floor will improve cross sectional flow
which would ensure the effectiveness of the existing CO sensors. This would ensure there would
be no stagnant pockets of air that could potentially not be occupied by a CO sensor. A detailed
payback analysis is as follows.
Circulation Fan Cost Analysis
Initial Investment
$98,000
Energy Reduction
24,741.57 kWh
Cost Savings
$6,185.39
Payback Period
15.84
Cost analysis shows proposed solution would be a better option.
Renewable Energy Overview
When looking into forms of renewable energy, photovoltaic panels as well as wind turbine
energy were analyzed. Through a cost analysis, wind energy in the Seattle region has proved to
not be as economical as photovoltaic. However in the appendix we have proposed on the most
feasible wind energy system and have provided a payback analysis.
Photovoltaic:
With the Central Plaza Garage being an underground structure, it proved difficult to find
sufficient suitable area for a PV array. Multiple locations were investigated however the best
location we identified was the roof of Odegaard Undergraduate Library. The Odegaard roof
would prove a very effective and economical location for the PV array.



3,158SF due-south Roof Area
36.88 degree (9/12) Slope
Optimal orientation for harvesting potential
The most feasible system installation includes PV panels, Inverters, and conduit traveling through
the elevator shaft of Odegaard Library, which arrives very close to the electrical room of the
Central Plaza Garage.
May 10, 2013
22
120 Architecture Hall | University of Washington | Seattle, WA 98105
Proposed Photovoltaic System
Proposed Solution: 17.28kW Photovoltaic Panel System mounted to the roof of Odegaard
Undergraduate Library consisting of the following.
(64) 270-watt SolarWorld Sunmodule Panel with Unirac Racking System
(1) - Fronius IG Plus 11.4-1 Inverter
(1) - Fronius IG Plus 6.0-1 Inverter
(1) - Web based Monitoring System
The system will consist of
3 rows of panels feeding 2
inverters. A new electrical
panel will be installed in
the electrical room of the
garage in order to handle
the additional feed to the
building. Conduit will be
run from the roof to the
electrical room via the
shared elevator shaft.
Utilizing the 3,158 square
feet of due south sloping
roof area will maximize
the harvesting potential of
this system. Using a Solar Pathfinder, we have determined that the best angle for these panels
for 100% sun exposure is a 34-degree tilt. The slope of these roof surfaces will only result in a
.388% drop from optimal harvesting potential.
May 10, 2013
23
120 Architecture Hall | University of Washington | Seattle, WA 98105
We have decided to utilize Sunmodule solar panels from SolarWorld. In addition, the Fronius IG+
Inverters provide optimal efficiency and are extremely reliable inverters.
SolarWorld PV Panels:
 25 yr. performance warranty
 10 yr. product warranty
 16.1% conversion efficiency
Initial Investment
$54,908
Fronius IG Plus Inverters:
 10 yr. product warranty
 95% efficiency
Proposed PV System Cost Analysis
Tax Rebates
Cost Less Rebates Annual Production
$16,472
$38,436
$7,260
Payback Period
5.29 yrs.
Photovoltaic Array Sizing Calculations
Project: Central Plaza Garage Energy Use Retrofit
Contractor: Husky Electric
Maximum Series Module Calculations
Vadj = Voc + [(Record Low Temp °C - STC Cell Temp °C) * Voltage (Voc)]
= 38.3 + [(-17.8 + 25 °C) * -.3V/°C)]
= 36.14 V
Maximum Modules in Series = UL / Vadj
= 16.6 (Round Down)
Maximum Modules in Series = 16
Minimum Series Module Calculations
Voltage = Vmpp * Power
= 32.8 * -.45
Voltage = -0.15
Vadj = Vmpp + [(Avg. High Temp + 30C - STC Cell Temp)* Voltage]
= 32.8V + (59c - 25c) * -.14V/C
Vadj = 27.8 V
Minimum Modules in Series = Min Operating Power / Vadj
= 244V/27.8V
= 8.77 (round up)
Minimum Modules in Series = 9
Recommendation due to string size
calculations as well space confinements:
3 rows - totaling 64 panels
Bottom row: 24
Middle row: 33
Top row: 18
Inverters: 3 strings of 14 and 2 strings of 11
Racking System: Solarmount flush mount
May 10, 2013
Sunmodule SW 270 mono
Open Circuit (Voc)
38.3
Rated (Vmpp)
32.1
Temp Coefficient for Voltage (Voc)
-0.30%
Temp Coefficient for Power (P)
-0.45%
Max System Voltage (UL)
600V
Fronius IG Inverters
Operating Range (MPPT)
244V - 305V
Solar Radiation Data (Seattle, WA 47.5N,122.3W)
Record Low Temp
-17.8
Average High Temp
29 (add 30
for rack
mount)
24
120 Architecture Hall | University of Washington | Seattle, WA 98105
Client Image
Seattle along with the University of Washington is known in the area as well as the entire nation
for being on the cutting edge of innovation and sustainability. The Central Plaza Parking Garage is
one of the first places many visitors as well as every day users experience upon arriving on
campus. Husky Electric wants every visitor to the University of Washington campus to be well
aware of its commitment to sustainability. This impressive solar harvesting technology can not
only save money and electricity, but serve as an educational tool and resource with our proposed
web based monitoring system.
May 10, 2013
25
120 Architecture Hall | University of Washington | Seattle, WA 98105
Schematic Estimate and Schedule
Schematic Estimate
Husky Electric performed an in depth energy analysis and considered all possible energy efficient
retrofit options to reduce energy costs to the University of Washington Central Parking Garage.
The schematic estimate for this project includes an alternative energy retrofit, energy use
retrofit, lighting retrofit, and electrical vehicle charging station installation. This schematic
estimate contains all materials, labor and small tools. This is intended to provide a clear and
concise breakdown of all the major costs associated with Husky Electric’s scope of work.
Husky Electric obtained labor units from the 2011-2012 NECA Manual of Labor Units. Material
Prices were compiled through a combination of local supplier quotes adjusted accordingly by
local NECA sponsors.
Estimate Breakdown
Alternative Energy Retrofit
 Roof Mounted Photovoltaic System
Energy Use Retrofit
 HVAC Reprogramming
Lighting Retrofit
 Fixture Upgrade
$54,908
$500
$238,084
Electric Car Charging Station
 Charging stations
$60,015
General Conditions
$25,587
Margin, B&O Tax, Contingency
$44,086
Total
(Less Grants, Rebates, Incentives)
Total Installed Cost
May 10, 2013
$423,180
($227,115)
$196,064
26
120 Architecture Hall | University of Washington | Seattle, WA 98105
Estimate
Quantity Unit
PV Panels
PV Panels
Electrical Panel
Racks
Inverters
Conduit/Wire
Mobile Crane
Web based monitoring system
64
1
3
2
100
Labor Rate
E
E
Row
E
LF
Labor Hours Wage Rate
0.6
4
88
3.7
0.16
1E
38.4
4
264
7.4
16
1
$
$
$
$
$
1 $
Labor Cost
$/Unit
60.00
60.00
60.00
60.00
60.00
$ 2,304.00 $
300.00 $ 19,200.00
$
240.00 $
260.00 $
260.00
$ 15,840.00 $ 1,000.00 $
3,000.00
$
444.00 $ 3,450.00 $
6,900.00
$
960.00 $
1.50 $
150.00
Subcontracted
60.00 $
60.00 $
750.00 $
750.00
Total
Ventilation
Reprogramming Existing Units
Lighting
Demo Existing Fixtures
LED Fixtures
Branch Power
Lighting Recycle Boxes
1717
225
9879
12
E
E
LF
E
0.25
1.5
0.03
0
Charging Station
Charge Pro EV Charging Station Wall Mounted
Conduit/Wire
12 E
1450 LF
16
0.03
429.25
337.5
296.37
0
$
$
$
$
192 $
43.5 $
General Conditions
60.00
60.00
60.00
-
$ 25,755.00 $
$ 20,250.00 $
$ 17,782.20 $
$
$
May 10, 2013
Fencing/Temp Walls
Service Van: Foreman
Storage Container
Telephone
Electrical Permit: City of Seattle
Recycling
General Expenses Subtotal
General Conditions Total
Weeks Hours/Week Cost Rate ($)
Cost Extension ($)
7
15 $
80 $
8,400
4
5 $ 100 $
2,000
1
20 $
60 $
1,200
4
5 $
55 $
1,100
2
10 $
45 $
900
7
3 $
40 $
840
5
2 $ 125 $
1,250
7
2 $
55 $
770
$
16,460
Weeks Quantity
7
7
6
7
7
726.00
1.00
89.00
$
$
$
$
$
$
$
$
21,504.00
500.00
18,840.00
7,344.00
1,110.00
4,800.00
810.00
54,908.00
Subcontracted $
500.00
$
$ 163,350.00
$
9,879.00
$
1,068.00
Total
$ 25,755.00
$ 183,600.00
$ 27,661.20
$
1,068.00
$ 238,084.20
60.00 $ 11,520.00 $ 3,642.50 $ 43,710.00 $
60.00 $ 2,610.00 $
1.50 $
2,175.00 $
Total
$
Central Parking Garage
Indirect Labor
Project Manager
Alternative Energy Specialist
Estimator
Lighting Designer
Financial Coordinator
Administration - Accounting Backup
Electrical Engineer
Safety Officer
Indirect Labor Subtotal
General Expenses
Material Cost Total Cost
Cost Rate
$ 300
$ 250
$
50
$
33
1 $ 4,480
$
38
Cost Extension ($)
$
2,100
$
1,750
$
300
$
231
$
4,480
$
266
$
9,127
$
25,587
55,230.00
4,785.00
60,015.00
Subtotal
$ 353,507.20
General Conditions
Margin (10%)
B&O Tax (.471%)
Contingency (2%)
$
$
$
$
Project Total
(Less: Rebates & Incentives)
$ 423,180.08
$ 227,115.22
Proposed Project Total
$ 196,064.86
$
Annual Electric Savings/profits $
Break Even (Years)
25,587.00
35,350.72
1,665.02
7,070.14
115,018
1.70
27
44,085.88
120 Architecture Hall | University of Washington | Seattle, WA 98105
Schedule Summary
The schedule for this project is separated into three main scopes of work:
 Renewable Energy System
 Lighting Retrofit
 Electrical Vehicle Charging Station.
Husky Electric scheduled 9 weeks beginning the week following the last week of spring quarter,
so campus activity will be minimal. Major milestones include Notice to Proceed on June 14, 2013,
Substantial Completion on August 09, 2013, and project completion on August 12, 2013.
Overview
This project will follow a zoning sequence to allow for parts of the garage to remain operable
during construction. Our simple, yet efficient schedule breaks the work into five stages:
1. Mobilization
4. Zoning Plan
2. Ventilation Programming 5. Demobilization
3. PV Panels
Stage 1: Mobilization
Crew mobilization and site preparation facilitate project management for the project.
Stage 2: Ventilation Programming
This work will be subcontracted to a controls contractor.
Stage 3: Photovoltaic Panels
This stage is not a part of the zoning plan. The PV Panel installation consists of 4 major steps:
1. Rack Installation
3. Conduit/Wiring
2. Panel Components Installation
4. Finish/Start-up
Stage 4: Zoning Plan
When one zone is under construction, the two other zones will be operational. Temporary walls
and signage will be restaged when moving zones. Zoning applies to lighting and charging stations.
 The interior lighting upgrade consists of 2 major steps:
1. Old Fixture Demolition/Recycle
Parking Available During Zone
2. New Fixture Installation
Build-Out
 The EV Charging Station installation consists of 3 major steps:
Zone
Available
Duration
1. Attach Wall Mount Brackets
Parking
(Days)
2. Install Circuit Breaker/Run Electrical Conduit
1
859
7
3. Mount Head Unit and Connect Electrical Supply
2
674
12
3
447
18
Stage 5: Demobilization
Activities include:
 Commissioning and Start-Up.
 All equipment and tools will be accounted for and returned.
 Site office space and lunchroom will be taken down and removed.
A punch list will then be created in order to ensure the owner is completely satisfied with all
aspects of the electrical retrofit and every concern and/or problem is resolved.
Warranty / Continuing Operations
Insurance and warranty coverage for defective workmanship within the first year following
completion will be covered in its entirety. Optional continued services may be provided for a
negotiated fee following the warranty period.
May 10, 2013
28
120 Architecture Hall | University of Washington | Seattle, WA 98105
Schedule
Activity Based Crew Forecast for Stages 2-5
Activity Based Crew Forecast
Task #
17-Jun 24-Jun 1-Jul
# Days
Start
Finish
15-Jul
22-Jul
Budget Hours Week Week Week Week Week
Week
Activity
4
Stage 2 - PV System
1
20
Tue 6/25/13 Mon 7/22/13
331
9
Stage 3 - Zone 1
5
Tue 6/18/13 Mon 6/24/13
245
13
Stage 4 - Zone 2
10
Tue 6/25/13 Mon 7/8/13
439
17
Stage 5 - Zone 3
15
Tue 7/9/13 Mon 7/29/13
615
Available work days
30
May 10, 2013
Total Hrs
2
8-Jul
3
4
5
4
2
2
6
6
6
6
8
8
6
6
6
6
1629
Total Crew Size
6
6
10
29
29
May 10, 2013
30
120 Architecture Hall | University of Washington | Seattle, WA 98105
Project Management Plan
Site Layout
LEGEND
Zone 1 Truck Route
Zone 2 Truck Route
Zone 3 Truck Route
Crew Office
Existing Roads
Crane Staging Area
Connex Container
Equipment Staging Area
Crew Parking Area
High-Visibility Fencing
Underground Garage Footprint
Site Logistics
 Crew office, parking area, connex, and equipment area located on Level 1 of garage.
 George Washington Lane NE runs North/South above the Central Plaza Parking Garage.
 High-visibility fence located along zone lines during corresponding zone build out.
Reference Zoning Plan for exact locations.
 Truck route corresponds to designated entrance per the Zoning Plan.
 Mobile crane staging area accessible by Memorial Way and is surrounded by highvisibility fence at all times.
May 10, 2013
31
120 Architecture Hall | University of Washington | Seattle, WA 98105
Safety Plan
Overview
It is the policy of Husky Electric to provide a safe and healthful workplace for its employees that
complies will all the requirements of applicable safety rules and orders on the Central Plaza
Parking Garage Project. Our Experience Modification Rate is an industry low of 0.53 due to our
outstanding lead by example and zero tolerance policies.
The Superintendent is responsible for implementation of the project’s safety program and the
assurance that it is strictly followed.
 Lead by example.
 Correct any unsafe behaviors or unsafe conditions immediately; looking for opportunities
to train employees.
 Perform a daily walk-through of his/her activities, primarily focusing on the identification
and correction of unsafe behaviors.
 Develop hazard analyses with the foreman and crew. Follow up to assure the hazard
analysis is effectively being used in the operation.
 Set expectations of the crews and assure compliance.
 Conduct a monthly Crew Based Safety Observation (CBSO) on an operation other than
their own.
Required Personal Protective Equipment
 Hard Hat
 Safety Glass
 Reflective Vests
 Work Boots with Safety Toe




Work Gloves
Ear Plugs
Fall Protection
Durable Work Attire
Community Safety
The Central Plaza Parking Garage retrofit takes place on the University of Washington campus
creating necessary additional safety measures. The garage will remain operational throughout
the duration of construction with available parking dictated by the Zoning Plan outlined in the
schedule. To compensate for additional safety requirements, we plan to surround all
construction zones with high-visibility fencing and strategically place project signage at the
garage entrances and construction zones to direct pedestrians safely around construction. Trucks
delivering material to and from the job site will be required to travel at speeds no higher than 15
miles per hour.
May 10, 2013
32
120 Architecture Hall | University of Washington | Seattle, WA 98105
Financing Plan
Grants, Rebates and Incentives
Overview
We have researched all grants, tax incentives, and rebates applicable to the retrofit of the Central
Plaza Parking Garage and have included in our financing plan the specific cost savings from each
incentive. Our financial analysis shows a payback period of 2.67 years and our retrofit qualifies
for a total of $235,718 from federal and state incentives that are returned to the client.
Lighting Incentives
Seattle City Light – Commercial Energy Efficiency Rebate Program
Seattle City Light offers rebates to commercial customers through the Energy Smart Services
Program. Rebates are calculated using the annual kWh savings of a given project offering
$0.20/kWh saved for lighting. These incentives have the potential to cover up to 70% of the
installation cost for the project.
Energy-Efficient Commercial Buildings Tax Deduction
The federal Energy Policy Act of 2005 provides a tax deduction for energy-efficient commercial
buildings. A deduction of $0.30 per square foot of the project is available to owners who’s
interior lighting replacement attributes to at least 50% of the reduction of energy and power
cost. Our lighting retrofit accounts for 51% of the total energy and power reduction which
qualifies our project for this tax deduction.
Description
City Light Rebate
Federal Tax Deduction
Lighting Incentives Savings Breakdown
Incentive
Rate
Unit
$0.20
338,608.60 kWh/yr
$0.30
416,390
SF
Savings ($)
$67,721.72
$124,917
Photovoltaic Incentives
Business Energy Investment Credit (ITC)
The federal business energy investment tax credit is available to commercial sectors with eligible
renewable technologies. The implementation of the photovoltaic system in our project qualifies
us for this corporate tax credit. The credit is equal to 30% of expenditures on solar equipment
used to generate electricity with no maximum credit.
May 10, 2013
33
120 Architecture Hall | University of Washington | Seattle, WA 98105
Renewable Energy Cost Recovery Incentive Payment Program
Washington State offers a performance-based incentive for photovoltaic systems up to 75kW.
The incentives equal $0.15 per kWh saved through 6/30/2020 with a maximum incentive per
year of $5,000. We plan to install a 17.28 kW photovoltaic system manufactured in the state of
Oregon which qualifies us for the $0.15 per kWh rate.
Photovoltaic Incentives Savings Breakdown
Description
Incentive
Rate
Unit
Business Energy ITC
30%
54,908
Total Cost
Energy Cost Incentive Payment
$0.15
18,150
kWh/year
Savings
$16,472
$2,722/year
EV Charging Station Incentives
Alternative Fuel Infrastructure Tax Credit
The U.S. Department of Energy’s alternative fuel infrastructure tax credit is available for 30% of
the purchase and installation of EV Chargers up to $30,000 per site. Since we are installing two EV
Chargers at three different sites, each site qualifies for this credit.
EV Charger Incentives Savings Breakdown
Description
Incentive
Rate
Unit
Alternative Fuel Tax Credit
30%
$60,015
Total Cost
May 10, 2013
Savings
$18,005
34
120 Architecture Hall | University of Washington | Seattle, WA 98105
Payback Analysis
Payback Analysis
Central Plaza Parking Garage
Return on Investment & Cumulative Savings (Incentives and Energy Reduction)
Upgrade
Lighting Upgrade
Mechanical System Upgrade
Photovoltaic System
EV Charging Stations
Central Plaza Parking Garage
(inc. GC's)
Initial Cost
-
Instant Incentives
=
$238,084.20
$500.00
$54,908.00
$60,015.00
-
$192,638.72
$$16,472.00
$18,004.50
=
=
=
=
Total Cost
$45,445.48
$500.00
$38,436.00
$42,010.50
/
Annual Energy
Reduction
Return on
Investments (Years)
/
/
/
/
$84,652.15
$20,134.87
$7,259.50*
$2,971.51
0.537
0.025
5.294
14.138
$423,180.08 $227,115.22 =
$196,064.86 /
*includes Annual Reduction and Incentive Payment
$115,018.03
1.705
Energy Savings
Central Plaza Parking Garage
Annual Energy Reduction
Upgrade
Lighting Upgrade
HVAC Upgrade
Photovoltaic System
EV Charging Stations
Central Plaza Parking Garage
May 10, 2013
Annual Reduction (kWh/Yr)
Annual Reduction ($)
338,608.60
$84,652.15
80,539.48
$20,134.87
18,150.00
$7,259.50
(147,198.00)
$2,971.51*
290,100.08
*Profit from sale of energy
$115,018.03
35
120 Architecture Hall | University of Washington | Seattle, WA 98105
Financing Strategies
Husky Electric has designed a very productive PV system and we have decided that it would not
be beneficial for the Central Parking Garage to engage in a solar power purchasing agreement.
Recently Solar Power-Purchasing agreements have grown more popular. In the state of
Washington, they are still relatively new, and there is not much precedent set. Seattle City Light
has a system to buy back excess power generated by PV systems. However, our estimates show
that the Central Parking Garage will not generate more power than is required for the building.
Additionally, the following challenges have confirmed that we will not be negotiating a powerpurchase agreement:
 More complex negotiations and potential higher transaction costs than buying PV system
outright
 Administrative cost of paying two separate electricity bills if system does not meet 100%
of site’s electric load
 Potential increase in property taxes if property value is reassessed
 Fairly limited federal sector experience
3rd-Party Solar PV Power Purchase Agreements
May 10, 2013
36
120 Architecture Hall | University of Washington | Seattle, WA 98105
References
http://www.afdc.energy.gov/laws/law/US/10513
http://www.bls.gov/ro9/cpiseat_energy.pdf
http://cars.uk.msn.com/news/in-pictures-updated-2013-nissan-leaf-to-be-built-in-britain?page=4
http://www.chargenw.com/
http://www.coulombtech.com/library.php
http://dashboard.mckinstry.com/uw/
http://www.dsireusa.org/incentives/incentive.cfm?Incentive_Code=US02F&re=1&ee=1
http://www.dsireusa.org/incentives/incentive.cfm?Incentive_Code=US40F&re=1&ee=1
http://www.dsireusa.org/incentives/incentive.cfm?Incentive_Code=WA89F&re=1&ee=1
http://www.dsireusa.org/incentives/incentive.cfm?Incentive_Code=WA27F&re=1&ee=1
http://www.ecolights.com/
http://www.fronius.com/
http://www.gemi.org/waterplanner/calc-horsepower.asp
http://www.indusprayusa.com/
http://www.popsci.com/environment/article/2008-02/americas-50-greenest-cities?page=1
http://ep-us.mersen.com/resources/media/articles/TT-PVPN5-Sizing-Fuses-of-Photovoltaic-Systemsper-NEC-Tech-Topic.pd
http://www.nws.noaa.gov/climate/
http://www.seattle.gov/dpd/Codes/Energy_Code/Overview/2009_ecupdate.asp
http://www.semaconnect.com/newsroom-pressrelease_pressrel12.php
http://www.sitelighting.com/products.cfm?Style=ELG&Brand=em&ProLine=elg
http://www.solarworld-usa.com/installer-program/products/sunmodule-solarpanels.aspx?gclid=CK6wsZb5gbcCFcU5QgodWXgAIg#tab-tab0
http://voices.yahoo.com/how-much-does-cost-charge-electric-car-7408182.html
https://www.washington.edu/facilities/records/services.php
http://www.widelite.com/products/qlp-gen-2#
http://en.wikipedia.org/wiki/Charging_station
http://en.wikipedia.org/wiki/Plug-in_electric_vehicles_in_the_United_States
http://www.westcoastgreenhighway.com/electrichighways.htm
May 10, 2013
37
120 Architecture Hall | University of Washington | Seattle, WA 98105
Outreach Appendix
Community Energy Awareness
OVERVIEW


Husky Electric’s main objective is to create energy conservation awareness amongst University of
Washington students. Awareness leads to proper consumption.
The retrofit of the Central Plaza Parking Garage is our first step to a green campus.
EXISTING PROGRAMS




U.S. Department of Energy & UW team up
on $178-million Smart Grid Project.
System provides means to track student’s
electricity usages.
Smart meter displays/controls electricity
use accurately by the day.
Has potential to save UW $350,000 on
annual energy bills alone.




SEED’s Students Expressing Environmental
Dedication run by UW students.
Promote sustainability in UW community.
Current programs are composting, proper
disposal, and campus cleanup.
Host successful outreach programs for
students including last year’s “Think
Outside the Bottle” campaign to limit
consumption of bottled-water
PROGRAM DESIGN & INTEGRATION




Smart Grid installed 235 smart meters in
178 buildings on UW campus.
Use social media to educate students on
Smart Grid program and its capabilities.
Advertise app developed by UW students
for smart phones capable of controlling the
smart meters away from home.
Students could turn off their dorm room
lights with their smart phones




Partner with SEED to host a Light Swap
event on UW campus on May 18th, 2013.
Encourage students to swap out their old
bulbs for new, energy efficient LED bulbs.
LED bulbs last 40 times longer than the
commonly used incandescent light bulb.
Advertise Light Swap with distribution of
our event poster and post details using
social media to reach ALL students.
FEEDBACK




Light Swap event is scheduled for May 18th, 2013 at UW. Reference poster example for details.
After little under 2 months of promoting the Smart Grid system, students living in the dormitories
have exhibited a slight decrease in electricity consumption.
Decrease in consumption from a high of 4,000 Kwh to a low of 2,300 Kwh per day.
Husky Electric will continue to promote the usage of the Smart Grid program in the hopes of
creating a permanent change in students’ energy consumption behaviors.
OUTREACH APPENDIX
May 10, 2013
120 Architecture Hall | University of Washington | Seattle, WA 98105
Energy Awareness Plan Feedback & Poster Example
March 20, 2013
To:
Brandon Burr
RE:
Light Swap Event and Energy Awareness Proposal
Mr. Burr,
The Students Expressing Environmental Dedication (SEED) have carefully
reviewed Husky Electric’s proposal for energy awareness through your
involvement with the Smart Grid project as well as the plan for the Light
Swap event. First, we commend you on your involvement with the Smart
Grid project. We agree that this particular program has the potential to
create a lasting change in the consumption behaviors of students. While
social media is a powerful tool to spread information to the University of
Washington’s student body, we believe more interaction in person would
be beneficial to your cause. This would give you the chance to explain all
that you aim to accomplish in your endeavors.
Secondly, we would like to officially accept your proposal to co-host the
Light Swap event in Red Square. We think this is a smart way to inspire
students to make a lasting change to a more energy efficient form of
electricity usage. Perhaps in the future we could hold similar events for
other types of materials and we encourage any ideas you may have on the
subject. I will contact you again within the next few days to figure out the
details of the Light Swap.
We are excited to see your interest in our cause to create energy awareness
on the UW’s campus and we look forward to your further involvement.
Thank you,
SEED
OUTREACH APPENDIX
May 10, 2013
120 Architecture Hall | University of Washington | Seattle, WA 98105
Article in University Newsletter
April 15, 2013
UW Students Propose Central Plaza Parking Garage Renovation
A hardworking team of six Construction Management students are competing in the 5 th
annual Green Energy Challenge national competition sponsored by the National Electrical
Contractors Association (NECA). The competition consists of the selection of a nearby
parking garage and performing an energy audit and design of the power and lighting
systems. The students have chosen to conduct their research on the Central Plaza
Parking Garage, built in 1972 and in need of an electrical retrofit. Team members
Brandon Burr, Matthew Watson, Kali Leachman, Tara Harrington, David Moore and JB
Gibson have conducted thorough
research and developed a smart
and comprehensive plan to
transform the Central Plaza
Parking Garage, familiarly known
as the Odegaard Parking Garage,
into an innovative and energy
efficient
structure.
These
renovations include but are not
limited to upgrading to LED light
fixtures, replacing carbon dioxide
sensors, adding solar panels to the
top of Odegaard, painting the
walls with reflective paint, and
Central Plaza Parking Garage built 1972
installing car charging stations. This
team of students, calling themselves Husky Electric, has teamed up with the UW’s very
own SEED organization and the School of Public Affairs’ pilot Smart Grid project to spread
energy consumption awareness. Make sure to come exchange your old household bulbs
for a new, energy efficient LED bulb at Husky Electric’s Light Swap event in Red Square on
May 18th at noon to support their mission to go green!
OUTREACH APPENDIX
May 10, 2013
120 Architecture Hall | University of Washington | Seattle, WA 98105
Feedback Letter from the Client
OUTREACH APPENDIX
May 10, 2013
120 Architecture Hall | University of Washington | Seattle, WA 98105
Local NECA Chapter Interaction
Person
Company
Means
Mark Anderson
Whidbey Sun & Wind
Email/Phone Conversation
Jim Blaisdell
Charge Northwest LLC
Email/Phone Conversation
Joe Berger
Cochran Inc.
Email/Phone Conversation
Nick Lopez
Cochran Inc.
Email/Phone Conversation
Ken Dyckman
Hermanson Mechanical
Face to Face Visit/Email
Tommy Key
NECA
NECA Board Meeting
Meagan Hillier
NECA
Face to Face Visit
Joe Borrelli
Triarc Electrical
Email/Phone Conversation
Brian Jones
Valley Electric
Face to Face Visit/Email
Interaction
Assisted with designing
the photovoltaic system
Assisted with selecting EV
charging stations and
provided team with price
quote
Assisted with overall
completition and success
of the proposal
Assisted with overal
completition and success
of the proposal
Assisted with analysis of
existing and proposed
mechanical system
Acted as initial contact in
discovering assistance
from local contractors
Day to day local contact
assisting with project
completion
Assisted in designing the
lighting retrofit
Intial contact regarding
lighting retrofit
University of Washington Interaction
Person
John Leaden
Norm Menter
Brian Ho
John Shaheen
Dan Jerome
Steve Tatge
Company
Means
Interaction
Initial contact for existing
UW Facility Services
Face to Face Visit
conditions and initial
retrofit improvements
Assited with receiving
UW Facility Services
Face to Face Visit
current energy usage
quantities
Assisted with information
regarding existing
UW Transportation Services
Face to Face Visit
conditions and proposed
retrofit
Main contact regarding
UW Transportation Services
Face to Face Visit
Central Plaza Parking
Garage
Met with to tour and
WA Community Transit
Face to Face Visit
discuss a newly built
parking structure
Assited with Vehicle Car
Capital Projects Office
Email/Phone Conversation
Charging Stations
OUTREACH APPENDIX
May 10, 2013
120 Architecture Hall | University of Washington | Seattle, WA 98105
Appendix A - Alternatives Considered
HVAC Option 2: Husky Electric also considered the option of installing two Cook TCN-B 20,000
CFM transfer fans to improve the airflow in the garage and allow the CO sensors to be more
accurate. The problem with the current system is that the air will stagnate and there will be
pockets of air that have a much higher concentration of CO. The installation of these fans would
provide a 20% reduction of the required operating time of the exhaust fans. This system
however, would not be as effective as the reprograming of the schedule and with the almost 16
year payback period, it would not be a viable option.
Initial Cost
$98,000.00
HVAC Option 2 Analysis
Energy Savings (kWh)
Cost savings
Payback Period (yrs)
24,741.57
$6,185.39
15.84
*Cost estimate provided by ACI Mechanical
Lighting Option 2: Painting the ceilings was a viable option to consider. Given that white –
reflective paint can increase the light output by up to 517% and reduce the energy
consumption around 20%, we considered using this as a tool to reduce our fixture count.
Following a payback period analysis we determined that using paint in garage would come at
a significant cost in comparison to the amount of energy savings. In the case that we would
have used a newer fluorescent fixture in the garage – the paint would have played a key role
in energy savings. With the efficiency and performance of LED lighting, it would be a minimal
effect due to the high number of light fixtures we are already reducing, causing a larger issue
with safety and full lighting coverage of the garage.
Lighting Option 2 Analysis
Annual Savings
Net Customer Cost
Payback Period(yrs)
$24,065.45
$166,691.20
6.93
*Quote Provided by Induspray ($0.40/SF)
Lighting Option 3: Replacing the existing T8 fixtures with new fluorescent fixtures would
require a 1:1 replacement ratio, resulting in a poor opportunity for energy savings and no real
reduction in future costs. Therefore this option was not practical for our facility. Another LED
fixture considered was the ELG-MR LED fixture from EMCO. This device would result in the same
reduction in fixture count, but did not meet code requirements in all locations of the garage. The
average foot-candle measurement was 6.7 fc, maximum was 12.7 fc and minimum was 2.5 fc.
The EMCO ELG-MR fixtures result in a larger annual savings but due to code requirements and
safety restrictions for the University of Washington the EMCO ELG-MR fixture does not meet the
needs of our owner. The QLP G2 fixture meets all needs of the owner and will be our fixture of
choice.
Alternative Fixture: EMCO ELG-EMR
Annual Savings
Net Customer Cost
Payback Period
$122,502.75
$168,975
1.38 years
May 10, 2013
APPENDIX
120 Architecture Hall | University of Washington | Seattle, WA 98105
Wind Power Overview:
The problem with finding a suitable wind energy harvesting system is that most wind turbines
have a required cut-in speed of 7-10 mph. With an average wind speed in Seattle of 7.53 mph
over the past 3 years, concluded that this system would not be viable in Seattle.
If wind energy were to be introduced on the roof of Odegaard Library, a wind turbine system with
an extremely low cut-in speed must be used. Since 7.53 is only the average wind speed in Seattle,
a lower cut in speed is required. Along with lower cut-in speeds, lower energy production and a
longer payback period would be expected.
Most Feasible Wind Turbine System:
Install a Bergey Excel 10kW turbine on the roof of Odegaard Library.
Wind Power Cost Analysis
Yearly Production
$1,500
Installed Cost
$32,200
Payback Period
21.46 years
Photovoltaic Alternative:
As an alternative to the Sunmodule Photovoltaic panels, we investigated using locally
manufactured panels and inverters in order to utilize more Washington State renewable energy
incentives.
Renewable energy incentives for Washington State:
 15 cents / kWh for renewable energy
 36 cents / kWh if manufactured in WA
In order to utilize the 36-cent incentive, we investigated locally manufactured panels and
inverters. It became apparent that the technology of these panels was lacking in comparison to
the Sunmodule panels. Locally manufactured panels were also more expensive. This information
combined with the fact that these increased energy incentives expire in 2020, we have
determined that Sunmodule panels would be a better investment.
(64) - Iteck Energy PV Panels
(4) - Theia 4.4 Inverters
Initial Investment
$86,198
WA Manufactured PV Panel Cost analysis
Tax Rebates Cost Less Rebates Annual Production
$25,859
$60,338.6
$9,821
Payback Period
6.14 yrs.
Due to the increased payback period in addition to the fact that production incentives will
expire in 2020, our recommendation is to use Sunmodule panels with Fronius inverters.
May 10, 2013
APPENDIX
120 Architecture Hall | University of Washington | Seattle, WA 98105
Appendix B- Lighting
May 10, 2013
APPENDIX
120 Architecture Hall | University of Washington | Seattle, WA 98105
Appendix C – EV Charging Station
May 10, 2013
APPENDIX
120 Architecture Hall | University of Washington | Seattle, WA 98105
Appendix D – PV Energy
9 May 2012
May 10,
2013
May 10,
2013
May
9, 2013
APPENDIX
Download