YORK HAVEN HYDROELECTRIC PROJECT FERC NO. 1888 FINAL LICENSE APPLICATION EXHIBIT A - PROJECT DESCRIPTION August 2012 © Copyright 2012. York Haven Power Company, LLC. All rights reserved. Table of Contents 1.0 GENERAL PROJ ECT DESCRIPTION ........................................................................ 1 1.1 1.2 2.0 Project Overview .................................................................................................... 1 Project Location ...................................................................................................... 2 PROJ ECT FACILITIES.................................................................................................. 2 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 Main Dam and Headrace Wall................................................................................ 2 East Channel Dam................................................................................................... 4 Impoundment .......................................................................................................... 4 Spillway .................................................................................................................. 4 Powerhouse ............................................................................................................. 4 Turbines-Generators ............................................................................................... 4 Tailrace ................................................................................................................... 6 Transformer and Switchyard................................................................................... 6 Transmission ........................................................................................................... 6 Fish Passage Facilities ............................................................................................ 6 Recreation Facilities................................................................................................ 7 3.0 LANDS OF THE UNITED STATES .............................................................................. 8 4.0 COMMENTS ON DRAFT LICENSE APPLICATION ............................................... 8 5.0 LITERATURE CITED .................................................................................................... 9 Page i Exhibit A – Final License Application York Haven Hydroelectric Project – FERC No. 1888 List of Tables Table 2.6-1 York Haven Project turbine and generator information. ........................................ 5 Table 2.8-1 York Haven Project switchyard equipment. ........................................................... 6 Table 2.11-1 Project owned recreation facilities. ......................................................................... 8 Page ii Exhibit A – Final License Application York Haven Hydroelectric Project – FERC No. 1888 List of Figures Figure 1.2-1 York Haven Project location................................................................................... 3 Page iii Exhibit A – Final License Application York Haven Hydroelectric Project – FERC No. 1888 EXHIBIT A - PROJ ECT DESCRIPTION The following excerpt from the Code of Federal Regulations (CFR) at 18 CFR § 4.51(b) describes the required content of this Exhibit. Exhibit A is a description of the project. This exhibit need not include information on project works maintained and operated by the U.S. Army Corps of Engineers, the Bureau of Reclamation, or any other department or agency of the United States, except for any project works that are proposed to be altered or modified. If the project includes more than one dam with associated facilities, each dam and the associated component parts must be described together as a discrete development. The description for each development must contain: (1) (2) (3) (4) (5) (6) The physical composition, dimensions, and general configuration of any dams, spillways, penstocks, powerhouses, tailraces, or other structures, whether existing or proposed, to be included as part of the project; The normal maximum surface area and normal maximum surface elevation (mean sea level), gross storage capacity, and usable storage capacity of any impoundments to be included as part of the project; The number, type, and rated capacity of any turbines or generators, whether existing or proposed, to be included as part of the project; The number, length, voltage, and interconnections of any primary transmission lines, whether existing or proposed, to be included as part of the project (see 16 U.S.C. 796(11)); The specifications of any additional mechanical, electrical, and transmission equipment appurtenant to the project; and All lands of the United States that are enclosed within the project boundary described under paragraph (h) of this section (Exhibit G), identified and tabulated by legal subdivisions of a public land survey of the affected area or, in the absence of a public land survey, by the best available legal description. The tabulation must show the total acreage of the lands of the United States within the project boundary. Page iv Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 1.0 GENERAL PROJECT DESCRIPTION 1.1 Project Overview York Haven Power Company, LLC (YHPC), owns and operates the York Haven Project (Project) on the Susquehanna River in York, Dauphin, and Lancaster counties in Pennsylvania. The Project is licensed by the Federal Energy Regulatory Commission (FERC) as Project No. 1888. Construction of the Project began in 1901. Initial construction of the hydroelectric plant was completed on August 18, 1904, with the last of the 20 units placed in service in 1914. The Project powerhouse is located at river mile (RM) 55 of the Susquehanna River, approximately 17 miles downstream from the City of Harrisburg. The Project has 20 generating units operating in a run-of-river mode with an installed capacity of 19.62 megawatts (MW) and an estimated maximum hydraulic capacity of 17,000 cubic feet per second (cfs) under optimum head conditions. The Project is capable of maintaining run-of-river operations and impoundment water level under low to moderate streamflow conditions. During periods of moderate to high runoff (>17,000 cfs), the Project cannot control water levels. The York Haven powerhouse is located on the western side of the Susquehanna River, parallel to the western river bank. The 20 individual generating units range in size from 700 to 1,600 kilowatts (kW) and are described in more detail in Section 2.6. of this Exhibit. The Project works include a stone masonry headrace wall, which extends 3,000 feet upstream from the north end of the powerhouse in a northerly direction parallel to the west bank of the river. This headrace wall serves to direct water to the powerhouse. The Main Dam is attached to the headrace and runs from the north end of the headrace wall, diagonally, across the main channel of the river approximately 4,970 feet to the west shore of Three Mile Island. The Main Dam is constructed of concrete-covered rock fill and rock fill/timber crib sections with a maximum height at the crest of 18 feet and an average height of 10 feet. The East Channel Dam is a concrete gravity overflow dam, which extends approximately 928 feet in an easterly direction, from the east shore of Three Mile Island to the east bank of the river, with an average height of 9 feet from foundation level. The East Channel Dam incorporates a vertical slot fishway constructed in 2000 to support the upstream passage of anadromous fish, primarily American shad. Two wheel gates, each with a hydraulic capacity of 1,000 cfs, are located just to the east of the fishway to provide the required 2,000 cfs East Channel attraction flow during fish passage operations. Fishway operations for upstream passage occur annually from mid-April to mid-June with the specific dates for each year determined jointly by dam operators, the U.S. Fish and Wildlife Service (USFWS), and the Pennsylvania Fish and Boat Commission (PFBC). At the normal maximum water surface elevation of 277.9 1 feet (NGVD29) 2, Lake Frederic, the Project impoundment, is approximately 3.5 miles long with a surface area of 2,218 acres and 1 The value of 277.9 represents the low point of the Main Dam, which under current operations is considered the normal elevation when river flows are less than maximum turbine capacity. 2 All elevations in the Final License Application are presented in with reference to the 1929 National Geodetic Vertical Datum. Page 1 Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 approximately 9,600 acre-feet of gross storage capacity and a usable storage capacity within its allowable 1.1 feet of fluctuation of about 1,700 acre-feet, or approximately 1 hour of storage at the plant’s maximum hydraulic capacity. The Project is operated with a year-round continuous minimum flow requirement of 1,000 cfs and an average daily minimum flow requirement of 2,500 cfs, or inflow, whichever is less, both of which can be delivered through the powerhouse. YHPC currently maintains the minimum flow requirement through spillage over the existing dam structures in combination with the operation of a minimum of two turbine-generator units. Additionally, YHPC is required to provide a minimum flow of 2,000 cfs at the East Channel Dam and spill 4,000 cfs at the Main Dam during the American shad passage season while the upstream fish passage facility is operating. 1.2 Project Location The Project is located on the Susquehanna River in York, Dauphin, and Lancaster counties in south central Pennsylvania as shown on Figure 1.2-1. The Susquehanna River basin above the York Haven Dam has a drainage area of approximately 24,973 square miles. The Project powerhouse is located approximately 17 miles downstream of the City of Harrisburg. There are four FERC-licensed hydroelectric facilities downstream of York Haven on the Susquehanna River— Safe Harbor at RM 32, Holtwood at RM 24, Muddy Run at RM 22, and Conowingo at RM 10. The Muddy Run Project is a pumped-storage project owned and operated by Exelon Corporation (Exelon) located near the upper end of the Conowingo reservoir. The Three Mile Island Nuclear Station, also owned by Exelon, is situated on Three Mile Island in Lake Frederic, the impoundment formed by the York Haven Dam. PPL’s Brunner Island Station, a coal-fired steam electric generating plant, is located approximately 1.5 miles downstream of the Project. 2.0 PROJECT FACILITIES Descriptions of the major Project facilities and components are provided below. YHPC will preserve the integrity of the existing facilities and will continue normal operations and maintenance into the future. YHPC is not proposing any changes to the power generation equipment at this time. 2.1 Main Dam and Headrace Wall The Main Dam acts as the primary spillway for the Project. It extends from TMI on the east side of the river to the headrace wall on the west side. The Main Dam is a concrete-covered rock fill and rock fill/timber crib structure with a maximum height of 18 ft. The headrace wall extends 3,000 feet in the downstream direction from the Main Dam to the north end of the powerhouse. The headrace wall directs water to the powerhouse. Page 2 Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 Figure 1.2-1 York Haven Project location. Page 3 Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 2.2 East Channel Dam The East Channel Dam is a concrete gravity overflow dam, which extends approximately 928 feet in an easterly direction from the east shore of Three Mile Island to the east bank of the river. It has an average height of 9 feet. The East Channel Dam incorporates a vertical slot fishway constructed in 2000 to support the upstream passage of anadromous fish, primarily American shad. Fishway operations for upstream passage occur annually from mid-April to mid-June with the specific dates for each year determined jointly by dam operators, the USFWS, and the PFBC. 2.3 Impoundment The Project impoundment, Lake Frederic, is approximately 3.5 miles long with approximately 29 miles of total shoreline length within the Project Boundary, including the shoreline of the islands located in Lake Frederic. The maximum depth of Lake Frederic is approximately 18 feet with a mean depth of about 6 feet (GPU Nuclear Corporation 1988). Lake Frederic has a surface area of 2,218 acres and approximately 9,600 acre-feet of gross storage capacity. Usable storage capacity is limited to the allowable 1.1 feet of fluctuation providing about 1,700 acre-feet of storage, or approximately 1 hour of storage at the plant’s maximum hydraulic capacity. 2.4 Spillway The Project operates in a run-of-river mode. During periods of moderate to high runoff in the Susquehanna River that exceed the station’s maximum hydraulic capacity (17,000 cfs), the Project cannot control water levels and spills water. Spills can occur at the Main Dam, Headrace Wall, and East Channel structures. 2.5 Powerhouse The brick and stone masonry powerhouse is approximately 472 feet long and 48 feet wide located parallel to the west bank of the Susquehanna River. This structure contains the turbines, generators, and appurtenant power generating equipment. Steel trashracks with four-inch clear spacing are installed at the intakes at each of the 20 turbine-generator units. The forebay includes a trash sluice gate at its downstream end with dimensions of 14 feet wide by 10.5 feet high. The sluice gate is capable of releasing approximately 600 cfs. 2.6 Turbines-Generators The powerhouse contains 20 turbine units and an installed capacity of 19.62 MW. The estimated maximum hydraulic capacity of the Project is 17,000 cfs (under optimum head conditions). Table 2.6-1 contains information on each of the 20 turbine-generator units at the Project including type, rated unit capacity, rated flow capacity, head, and rotational speed. Page 4 Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 Table 2.6-1 Unit Type York Haven Project turbine and generator information. Turbine Rated Unit Capacity (kW) 1 Propeller 1,600 2 Propeller 1,600 3 Propeller 4 5 Nameplate Generator Capacity at Unity Power Factor (kW) 2,000 Flow at Turbine Rated Capacity (cfs) Rated Head (feet) Turbine Speed (rpm) 1,100 23 200 2,000 1,100 23 200 1,600 2,000 1,100 23 200 Propeller 1,600 2,000 1,100 23 200 Propeller 1,600 2,000 800 23 200 6 Propeller 1,320 1,650 800 23 200 7 Francis 700 875 785 20 84 8 Francis 700 875 785 20 84 9 Francis 700 875 785 20 84 10 Francis 700 875 785 20 84 11 Francis 700 875 785 20 84 12 Francis 700 875 785 20 84 13 Francis 700 875 785 20 84 14 Francis 1,200 1,500 700 20 120 15 Francis 700 875 785 20 84 16 Francis 700 875 785 20 84 17 Francis 700 875 785 20 84 18 Francis 700 875 785 20 84 19 Francis 700 875 785 20 84 20 Francis 700 875 785 20 84 The generators for Units 1 through 5 are vertical-shaft units with a rotational speed of 200 rpm. Each machine is 60-cycle, three-phase, 4,800 volt, 2,000 kilovolt ampere (kVA) unit with Kingsbury thrust bearings and static exciters, manufactured by Westinghouse. The generator for Unit 6 is a vertical-shaft, 200 rpm, 60-cycle, three-phase, 4,800 volt, 1,650 kVA machine, with Kingsbury thrust bearing and static exciter, manufactured by Westinghouse. Units 7 to 13 and 15 to 20 are horizontal shaft, 84 rpm, 60-cycle, three-phase, 2,400 volt, 875 kVA generators manufactured by the Stanley Electric Manufacturing Company. Machine excitation is provided to circumferential stator windings (rather than the typical rotor field winding of modern synchronous generators) by a DC rectifier and rheostat-type excitation system. Unit 14 is a vertical-shaft, 120 rpm, 60-cycle, three-phase, 2,400 volt, 1,500 kVA General Electric Company generator, with spring-mounted thrust bearing. Excitation is provided by a DC rectifier and rheostat-type excitation system. For the purposes of establishing the authorized installed capacity for the new license, generation at the Project is turbine-limited at each of the 20 units, as summarized above in Table 2.6-1. Page 5 Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 2.7 Tailrace The Project does not include a traditional tailrace and each of the units discharge directly into the Susquehanna River. 2.8 Transformer and Switchyard The Project includes an outdoor switchyard that contains the station’s transformers, referred to as GSU units, station service transformers, and manual switching structures. Table 2.8-1 summarizes the switchyard equipment: Table 2.8-1 York Haven Project switchyard equipment. Name Purpose Type Voltage (kV) Capacity (MVA) Bank #6 GSU; U1-U6 3PH; OA/FA/FA 115 (Y) / 16.8/22.4/28 65C Rise 4.8 (D) / 8.4/11.2/14 2.4(D)/4.16(Y) 9.96/13.28/16.6 // 16.8/22.4/28 3PH; OA 115 (D) / 10/11.2 55/65C Rise 2.4(D)/4.16(Y) 10/11.2 Backup Station 3 - 1PH; OA 13.2 / 0.2 Ea; Total capacity 0.6 MVA Service 55C Rise 2.4 0.2 Ea; Total capacity 0.6 MVA Bank #10 Bank #12 GSU; U7-U20 Bank #6 is a three-winding transformer with configurable connections on the low voltage winding to switch from delta to wye. The low voltage winding is currently not in use. The intermediate (4.8 kV) winding serves to step up generators #1-#6 to 115 kV for connection to the grid. 2.9 Transmission There are no primary transmission lines included as part of the Project. The Project interconnects with the 115 kV grid at the substation located immediately downstream of the Project’s downstream forebay wall. A secondary service feed comes into the Project substation via Line No. 722 at 13.2 kV. 2.10 Fish Passage Facilities YHPC entered into a Settlement Agreement in 1993 (67 FERC ¶ 62,291) with other hydroelectric operators on the Susquehanna River, Federal and State resource agencies and local organizations to provide both upstream and downstream fish passage facilities. This Agreement was subsequently modified by a 1997 Settlement Agreement approved by FERC (81 FERC ¶61,214). The present upstream fish passage facility (the East Channel Fish Passage Facility), which is located at the western end of the East Channel Dam, became operational in April 2000. The current fishway includes two sections: a “weir cut” and a vertical-slot fish ladder. The “weir cut” section provides supplemental attraction flows to the fishway and the upper portion of the “weir cut” includes three, 25-foot-diameter cofferdam cells between which two 20-foot fixedwheel gates are installed, with each gate having a 1,000 cfs discharge capacity. The lower section of the “weir cut” includes a 67-foot adjustable weir and a stop gate. The 250-foot-long Page 6 Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 fish ladder has an entrance diffuser, serpentine baffles that form eight pools, and an exit flume. The design capacity of the fish ladder is 500,000 shad equivalents per year, where ten river herring are considered to equal one shad. Attraction flows for the present East Channel fishway are provided through the gated openings and a 17-foot-high by 67-foot-long weir constructed on the East Channel Dam immediately adjacent to the fish passage facility. A total of 200 cfs of flow is passed at the fishway (approximately 40 cfs through the ladder itself and 160 cfs in supplemental attraction flow through a rectangular conduit located under the ladder). The serpentine baffles enclose eight, four-foot-deep, pools that form the fish ladder leading to the impoundment. A counting station is located in the exit channel just upstream of the last fish ladder pool. A minimum flow of 2,000 cfs is required to be passed at the East Channel Dam during the period when the facility is providing upstream passage, generally from mid-April to mid-June. Specific dates for each year are determined jointly by dam operators, USFWS, and the PFBC. The fishway is operable for flows up to 150,000 cfs. Due to safety concerns, the fish passage facility is closed when flows exceed 150,000 cfs. During operation of the facility, YHPC maintains the lake level at an elevation no lower than 277.8 feet as measured at the entrance to the headrace. Under the terms of the 1993 and 1997 Settlement Agreements, the Project is required to provide a minimum flow of 2,000 cfs in the East Channel and spill 4,000 cfs at the Main Dam, as well as maintaining the lake level at 277.8 feet or above while the upstream fish passage facility is operating for passage of American shad. In addition, YHPC and the Pennsylvania Department of Environmental Protection (PADEP) entered into a Consent Order and Agreement dated June 10, 2010, under which the Project committed to (1) operate and maintain the East Channel Fish Passage Facility to allow passage of resident fish species each year from April 1 through the earlier of December 15 or until the average daily river temperature is 40° F for three consecutive days; (2) after the American shad upstream passage season and during the resident fish passage period, provide a minium stream flow of 400 cfs in the East Channel; (3) after the American shad upstream passage season, and when river flows exceed the Project’s hydraulic capacity, provide flows over the Main Dam and through the East Channel in accordance with objectives and details to be developed through further consultations between YHPC and the PFBC; (4) during the period of operation of the East Channel Fish Passage System, manage debris to maintain the functioning and operability of the passage system; and (5) conduct certain monitoring and allow the resource agencies with access to the East Channel Fish Passage System counting room to conduct fish monitoring. 2.11 Recreation Facilities Lake Frederic is a popular recreation site and provides numerous recreational opportunities including fishing, boating, picnicking, and swimming. Lake Frederic contains five significant islands (Battery, Beshore, Goodling, Goosehorn, and Shelley) with picnic facilities and nature trails provided and maintained by YHPC. In addition, Lake Frederic contains several smaller islands which do not have facilities, but may be accessed by boaters. Fishing platforms and designated fishing areas are provided in the headrace and tailrace areas. Portage for canoes and small boats is provided around the dams. Through a licensing program administered by YHPC, recreational lot sites are available on which annual license holders may place trailers or recreational vehicles. Page 7 Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 The Project also provides a recreation site adjacent to the York Haven powerhouse that contains a large grassy area with playground and picnic facilities as well as tennis and basketball courts and ample parking. Table 2.11-1 provides a summary of the Project recreation facilities that will be operated and maintained by YHPC during the term of the new license. Table 2.11-1 Project owned recreation facilities. Site Name York Haven Power Plant Recreation Area Battery Island Picnic Area Goodling Island Picnic Area Shelley Island Recreation Area Goosehorn Island Picnic Area East Shore Boat Launch and Canal Lock 3.0 Recreation Facilities and Opportunities Tailwater fishing, canoe portage, playground, picnic area, sport courts Picnic area Picnic area Nature trail, picnic area Picnic area Boat launch, trail, picnic areas, abandoned canal lock LANDS OF THE UNITED STATES There are no lands of the United States within the Project Boundary. 4.0 COMMENTS ON DRAFT LICENSE APPLICATION Comments received on Exhibit A of the Draft License Application are listed below together with a YHPC response. Comment by FERC staff: “In section 1.1, you state that the gross storage capacity of the impoundment is 10,205 acre-feet at the normal maximum water surface elevation of 277.9 feet; however, the elevation versus storage curve in figure 2.5.3-1 in Exhibit B shows that the storage capacity is less than 10,205 acre-feet at that same elevation. In the final license application, please clarify this discrepancy between exhibits.” YHPC response: YHPC has revised the gross storage capacity of the impoundment to 9,600 acre-feet at the normal maximum water surface elevation of 277.9 feet to correspond to the Figure 2.5.3-1 in Exhibit B. Comment by FERC staff: “Section 4.51(b)(3) of the Commission’s regulations requires the number, type, and rated capacity of any turbines or generators, whether existing or proposed, to be included as part of the project. On page 5, some descriptions of the turbines do not correspond to the contents of table 2.6-1. In the final license application, please correct the descriptions for the turbines.” YHPC response: YHPC has revised the Project’s authorized installed capacity to 19.62 MW. The exact hydraulic capacity of each unit is not known precisely; therefore, it is appropriate to characterize the station hydraulic capacity as estimated to be approximately 17,000 cfs. A new column has also been Page 8 Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 added to Table 2.6-1 showing the corresponding generator nameplate capacities at unity power factor to demonstrate that all of the installed units are turbine-limited. 5.0 LITERATURE CITED GPU Nuclear Corporation. 1988. Hydrographic Survey, Three Mile Island Nuclear Station, May 17, 1988. Prepared by Thomas Starosta, Corporate Environmental Controls, R&EC Division, GPU Nuclear Corporation. July 1988. Page 9 Exhibit A - Final License Application York Haven Hydroelectric Project – FERC No. 1888 YORK HAVEN HYDROELECTRIC PROJECT FERC NO. 1888 FINAL LICENSE APPLICATION EXHIBIT B – PROJECT OPERATIONS AND RESOURCE UTILIZATION August 2012 © Copyright 2012. York Haven Power Company, LLC. All rights reserved. Table of Contents 1.0 BACKGROUND AND PROJECT PURPOSE .............................................................. 1 2.0 CURRENT AND PROPOSED OPERATION OF THE YORK HAVEN PROJECT.......................................................................................................................... 3 2.1 2.2 2.3 2.4 2.5 2.6 Agreements Affecting Current Project Operations................................................. 3 Agreements Affecting Future Project Operations................................................... 4 Day-to-Day Plant Operations and Control.............................................................. 5 2.3.1 Operations during Normal, Dry, and Wet Years .......................................7 2.3.2 Spillway Operations ..................................................................................7 Fishway Operation .................................................................................................. 8 Project Flows and Generation................................................................................. 8 2.5.1 Project Flows .............................................................................................8 2.5.1.1 Mean and Median Flows ..........................................................8 2.5.1.2 Critical Period Flows ................................................................9 2.5.1.3 Flows Downstream of the Main Dam and East Channel Dam...........................................................................................9 2.5.2 Project Generation ...................................................................................10 2.5.2.1 Average Energy Production and Utilization...........................10 2.5.2.2 Annual Plant Factor ................................................................10 2.5.2.3 Estimate of Dependable Capacity...........................................11 2.5.2.4 Plant Capability Versus Head.................................................11 2.5.2.5 Tailwater Rating Curve...........................................................12 2.5.3 Impoundment Operations ........................................................................12 Proposed Future Project Operations ..................................................................... 13 3.0 RESOURCE UTILIZATION AND FUTURE DEVELOPMENT............................. 14 4.0 COMMENTS ON DRAFT LICENSE APPLICATION ............................................. 14 5.0 LITERATURE CITED .................................................................................................. 16 ATTACHMENT Attachment B-1 - Annual and Monthly Flow Duration curves for USGS gage 01570500 (1931 to 2010) Page i Exhibit B – Final License Application York Haven Hydroelectric Project – FERC No. 1888 List of Tables Table 2.5.1-1 Table 2.5.2-1 Table 2.5.2-2 Estimated monthly flows at the York Haven Project. .............................. 9 York Haven’s average annual energy production, 2001-2011. .............. 10 York Haven tailwater rating data. .......................................................... 12 Page ii Exhibit B – Final License Application York Haven Hydroelectric Project – FERC No. 1888 List of Figures Figure 1.0-1 Figure 2.3.1-1 Figure 2.5.2-1 Figure 2.5.2-2 Figure 2.5.3-1 York Haven Project location................................................................................ 2 York Haven river flow in normal, wet and dry years. ......................................... 7 York Haven power plant capacity versus net head under normal headwater of 277.9 feet...................................................................................... 11 York Haven tailwater rating curve..................................................................... 12 York Haven elevation and storage curve. .......................................................... 13 Page iii Exhibit B – Final License Application York Haven Hydroelectric Project – FERC No. 1888 EXHIBIT B – PROJECT OPERATIONS AND RESOURCE UTILIZATION The following excerpt from the Code of Federal Regulations (CFR) at 18 CFR § 4.51(c) describes the required content of this Exhibit. Exhibit B is a statement of project operation and resource utilization. If the project includes more than one dam with associated facilities, the information must be provided separately for each such discrete development. The exhibit must contain: (1) (2) A statement whether operation of the powerplant will be manual or automatic, an estimate of the annual plant factor, and a statement of how the project will be operated during adverse, mean, and high water years; An estimate of the dependable capacity and average annual energy production in kilowatt-hours (or a mechanical equivalent), supported by the following data: (i) (ii) (iii) (iv) (v) The minimum, mean, and maximum recorded flows in cubic feet per second of the stream or other body of water at the powerplant intake or point of diversion, with a specification of any adjustments made for evaporation, leakage, minimum flow releases (including duration of releases), or other reductions in available flow; monthly flow duration curves indicating the period of record and the gauging stations used in deriving the curves; and a specification of the period of critical streamflow used to determine the dependable capacity; An area-capacity curve showing the gross storage capacity and usable storage capacity of the impoundment, with a rule curve showing the proposed operation of the impoundment and how the usable storage capacity is to be utilized; The estimated hydraulic capacity of the powerplant (minimum and maximum flow through the powerplant) in cubic feet per second; A tailwater rating curve; and A curve showing powerplant capability versus head and specifying maximum, normal, and minimum heads; (3) A statement, with load curves and tabular data, if necessary, of the manner in which the power generated at the project is to be utilized, including the amount of power to be used on-site, if any, the amount of power to be sold, and the identity of any proposed purchasers; and (4) A statement of the applicant's plans, if any, for future development of the project or of any other existing or proposed water power project on the stream or other body of water, indicating the approximate location and estimated installed capacity of the proposed developments. Page iv Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 1.0 BACKGROUND AND PROJECT PURPOSE York Haven Power Company, LLC, (YHPC) owns and operates the York Haven Project (Project) on the Susquehanna River in York, Dauphin, and Lancaster counties in Pennsylvania. The Project is licensed by the Federal Energy Regulatory Commission (FERC) as Project No. 1888. The Project is located at river mile (RM) 55 of the Susquehanna River, approximately 17 miles downstream from the City of Harrisburg (Figure 1.0-1). The current license is scheduled to expire on September 1, 2014. The Project was originally built by York Haven Water and Power Company, which was incorporated on January 16, 1895, for the purpose of supplying water and power to the public and to firms, individuals, and corporations in the Borough of York Haven, Pennsylvania and in adjacent towns. Construction of the Project began in 1901. Initial construction of the hydroelectric plant was completed on August 18, 1904, with the last of the original 20 turbinegenerator units placed in service in 1914. The Susquehanna River basin above York Haven Dam has a drainage area of approximately 24,973 square miles. Average monthly flows at York Haven range from approximately 12,000 cubic feet per second (cfs) in August to 75,000 cfs in April. There are four FERC-licensed hydroelectric facilities downstream of York Haven on the Susquehanna River — Safe Harbor, Holtwood, Muddy Run, and Conowingo. The Muddy Run Project is a pumped-storage project operated by Exelon Corporation (Exelon) and located near the upper end of the reservoir formed by Conowingo Dam. The Three Mile Island Nuclear Station, also owned and operated by Exelon, is situated on Three Mile Island along the impoundment formed by the York Haven Dam. Pennsylvania Power and Light (PPL) owns and operates the Brunner Island Station, a coal-fired steam electric generating plant located approximately 1.5 miles downstream of the York Haven Project. The York Haven powerhouse is located on the western side of the Susquehanna River, parallel to the western river bank. The Project powerhouse contains 20 generating units operating in a runof-river mode with an installed capacity of 19.62 megawatts (MW) and an estimated maximum hydraulic capacity of 17,000 cfs under optimum head conditions. The Project is capable of maintaining run-of-river operations and impoundment water level under low to moderate flow conditions. During periods of moderate to high flow conditions (>17,000 cfs), the Project cannot control impoundment water levels. The 20 individual generating units range in size from 700 to 1,600 kilowatts (kW). The Project works include a stone masonry headrace wall, which extends 3,000 feet upstream from the north end of the powerhouse in a northerly direction parallel to the west bank of the river. This headrace wall serves to direct water to the powerhouse. The Main Dam is attached to the headrace and runs from the north end of the headrace wall, diagonally, across the main channel of the river approximately 4,970 feet to the west shore of Three Mile Island. The Main Dam is constructed of concrete-covered rock fill and timber, and has a maximum height at the crest of 18 feet and an average height of 10 feet. The East Channel Dam located on the east side of Three Mile Island, is a gravity overflow structure, which extends approximately 928 feet in an easterly direction, from the east shore of Three Mile Island to the east bank of the river. It has an average height of 9 feet. Exhibit A of this Final License Application presents a detailed description of the York Haven Project facilities. Page 1 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 Figure 1.0-1 York Haven Project location. Page 2 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 The East Channel Dam incorporates a vertical slot fishway constructed in 2000 to support the upstream passage of anadromous fish, primarily American shad. Fishway operations for upstream passage occur annually from mid-April to mid-June with the specific times of operation for each year determined jointly by YHPC, U.S. Fish and Wildlife Service (USFWS), and the Pennsylvania Fish and Boat Commission (PFBC). 2.0 CURRENT AND PROPOSED OPERATION OF THE YORK HAVEN PROJECT Descriptions of the current and proposed operation of the project are provided below. YHPC will preserve the integrity of the existing facilities and will continue normal operations and maintenance into the future. 2.1 Agreements Affecting Current Project Operations YHPC is subject to a number of requirements which affect current Project operations. YHPC is currently subject to Articles 1 through 28 set forth in Form L-3 (Revised October 1975) entitled “Term and Conditions of License for Constructed Major Project Affecting Navigable Waters of the United States” and Articles 29 through 43 set forth in FERC’s Order Issuing a New Major License for the Project issued on August 14, 1980. The articles directly affecting Project operations are Article 30 and Article 41. Article 30 of the current FERC license requires YHPC to discharge from the powerhouse a continuous minimum flow of 1,000 cfs and an average daily flow of not less than 2,500 cfs, except if the inflow to the impoundment is less than these amounts, in which case the discharge from the Project shall not be less than the inflow. These flows may be temporarily modified if required by operating emergencies beyond the control of YHPC. The license requirement with regard to continuous flow is accomplished by maintaining at least two of the York Haven turbines operating at full gate providing approximately 1,000 cfs to 1,500 cfs downstream and supplementing the turbine discharge with spill over the Main Dam spillway. Article 41 addresses the disposition of river-borne debris. Based on a study conducted by YHPC, an agreement on debris handling was reached among the Army Corps of Engineers, the Susquehanna River Basin Commission, Conowingo Project (FERC No. 405), Safe Harbor Project (FERC No. 1025), and the Holtwood Project (FERC No. 1881). Currently, almost all of the debris arrives at the Project during high flow events when river flows far exceed the hydraulic capacity of the Project. Much of that debris simply passes over the Main Dam. A relatively small percentage of the debris accumulates in the forebay. Non-natural debris is removed from the accumulated debris in the forebay and the remaining organic debris material is sluiced downstream through a gated opening in the masonry non-overflow “cable alley” wall located at the downstream end of the forebay. Prior to opening the sluice gate, YHPC notifies PPL’s Brunner Island Station that debris is to be sluiced. In addition, in 2010 YHPC and the Pennsylvania Department of Environmental Protection (PADEP) reached an agreement that is reflected in the Project’s current National Pollution Discharge Elimination System (NPDES) Permit providing for an annual payment to a county Page 3 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 conservation district or other entity designated by PADEP for purposes of financing debris removal in the Lower Susquehanna River Watershed. The York Haven Project also addresses fish passage requirements, including during both attended and unattended fish passage operation. When the current East Channel Fish Passage Facility is operated to support the upstream migration of adult American shad, YHPC is required to spill 4,000 cfs at the Main Dam and to release 2,000 cfs at the East Channel Dam which includes 67 cfs that is provided directly through the fishway facilities as needed for fish ladder operation (typically mid-April to mid-June). At the conclusion of the American shad upstream fish passage season, the Project returns to volitional unattended passage to accommodate the movement of resident fish. YHPC entered into a Consent Order and Agreement with PADEP in June 2010 regarding flow in the East Channel. Under that agreement, after the American shad upstream passage season and during the resident fish passage period, the Project will maintain a minimum flow of 400 cfs in the East Channel during the period that the fishway is operated to enhance passage of resident fish species until the seasonal closure of the fishway. Fishway closure occurs the earlier of December 15th or when average daily river water temperature is equal to or less than 40 degrees Fahrenheit for three consecutive days. 2.2 Agreements Affecting Future Project Operations YHPC is not proposing any substantial modifications to the operations of the York Haven Project at this time. YHPC is committed to implementing fish passage enhancements at the Project. YHPC and resource agencies have been working actively and collaboratively for more than a year on investigations of fish behavior and engineering investigations of alternative fishway configurations. YHPC and resource agencies are currently focusing on developing concepts for a potential nature-like fishway located at the apex of the Main Dam where it abuts Three Mile Island. Feasibility investigations are well along and refinements to design criteria and configurations are in process. Exhibit E, Section 3.5.4.3 provides details of the feasibility investigations and current status. The most recent activities related to refining the fishway configuration occurred on July 27, 2012 when YHPC, HDR, and Dr. Luther Aadland met on site during non-spill conditions to investigate the suitability of river channel rock between the powerhouse and Main Dam to construct the fishway. The results of that site visit are encouraging, suggesting sufficient good quality rock material may be available on-site. During that same field visit, a revised conceptual layout of the in-channel option and modifications to delivering attraction flows were reviewed and vetted. A refined configuration is currently under development based on this field visit. YHPC is fully committed to the development of a final configuration for a nature-like fishway which meets the goal of providing safe, timely, and effective fish passage that is economically feasible for the Project. YHPC believes that a nature-like fishway at the apex location can achieve this goal. All parties recognize that this innovative approach to fish passage will require additional time to finalize the investigations and fishway details. YHPC has already embarked on the next stage in the feasibility process and expects to share with agencies by the end of September 2012 a refined fishway configuration. YHPC then intends, upon resource agency concurrence, to prepare the full fishway functional design as a basis for a fish passage agreement. As the final fishway plan is developed, YHPC recognizes that final plan and schedule for installation will have to be coordinated with the overall final plan for restoration of American shad on the Susquehanna River. Page 4 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 2.3 Day-to-Day Plant Operations and Control The Project is operated in a run-of-river mode. The estimated maximum hydraulic capacity of the turbines is 17,000 cfs under optimum head conditions. River flow constrains daily power generation, and during periods when river flow is less than 17,000 cfs the impoundment is maintained at the normal pool elevation of 277.9 1 feet (NGVD29). 2 During periods of high runoff, the Project turbines cannot control water levels and the impoundment elevation will vary above normal pool elevation depending upon river flow. Under lower flow conditions, YHPC has the ability to draw down the impoundment by up to 1.1 feet, generally for purposes of dam maintenance. The plant contains 20 hydroelectric turbines which have an aggregate discharge capacity of approximately 17,000 cfs under full station load. The hydraulic capacity of the turbines range from 700 to 1,100 cfs at normal operating head (Units 1-4 are 1,000 cfs while Units 5-20 are 700-800 cfs). The forebay sluice gate has a discharge capacity of approximately 600 cfs. At the East Channel Dam, there are two wheel gates adjacent to the fish ladder with a combined hydraulic capacity of 2,000 cfs (1,000 cfs each). The East Channel fish ladder itself has a hydraulic capacity of approximately 67 cfs. River inflow beyond the hydraulic capacity of these Project structures cannot be controlled and all excess water spills over the Project’s spillways in the main channel and the east channel. The Project uses the Susquehanna River gage at Harrisburg, Pennsylvania (USGS 01570500) to estimate the inflows to the Project (Figure 2.3-1). The gage is located 17 miles upstream of the Project resulting in an approximate travel time of 6 hours (depending on river flow) for flows measured at Harrisburg to reach the York Haven Project. Inflow to Lake Frederic can be estimated by multiplying the Harrisburg gage flow by a factor of 1.04 to account for the additional drainage area between Harrisburg and York Haven. The proration factor of 1.04 is based on a direct ratio of the drainage area of the USGS Susquehanna River gage at Harrisburg (24,100 square miles) and the drainage area of the York Haven Project (24,973 square miles). The closest downstream gage, USGS 01576000 Susquehanna River gage at Marietta, Pennsylvania, is located approximately 12 miles downriver (Figure 2.3-1). Project outflow can also be estimated by multiplying the Marietta gage flow (25,990 square mile drainage) by a factor of 0.96 to account for additional water entering the river between York Haven and Marietta. The York Haven station is manually operated at all times with two operators on duty during the day and one operator on duty at night. During normal operations, units are brought on-line based on anticipated flow rates given that the only available method of flow control at the Project is through on/off operation of each of the 20 generating turbines. Project outflow adjustments typically occur in 700 to 1,100 cfs increments, up to the station hydraulic capacity. Historically, adjustments are made during the day-shift or at a shift change. Project operators assure run-ofriver operation through a series of checks and balances, monitoring operations and streamflow gage data, observing impoundment elevations, and applying Project operational experience. 1 The value of 277.9 represents the low point of the Main Dam, which under current operations is considered the normal elevation when river flows are less than maximum turbine capacity. 2 All elevations in the Final License Application are presented in 1929 National Geodetic Vertical Datum. Page 5 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 Figure 2.3-1 Location of USGS gages utilized by the York Haven Project. Page 6 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 The York Haven Project is operated to meet a year-round continuous minimum flow requirement of 1,000 cfs and an average daily minimum flow requirement of 2,500 cfs, or inflow, whichever is less, both of which can be delivered through the powerhouse. YHPC maintains the minimum flow requirement through a combination of keeping at least two units in operation and allowing spill to occur over the existing Main Dam spillway. Additionally, YHPC is required to maintain minimum flows at the East Channel and Main Dam while the upstream fish passage facility is operating to support the upstream migration of American shad, and at the East Channel Dam during all fish passage operations. At this time, YHPC is proposing to continue the current plant operations. Discussions of future fishway facilities are continuing among resource agencies and YHPC. Current operations may be modified to accommodate the development and operation of any new fishway facilities. YHPC has provided a proposed schedule in Exhibit E, Section 3.5 for the completion of the ongoing discussions with resource agencies related to future fish passage at the Project. 2.3.1 Operations during Normal, Dry, and Wet Years As indicated previously in this Exhibit, the York Haven Project operates in a run-of-river mode. The Project is capable of maintaining run-of-river operations and impoundment water levels under low to moderate stream flow conditions. During periods of moderate to high runoff (>17,000 cfs), the Project turbines cannot control water levels. Figure 2.3.1-1 depicts typical hydrology of the York Haven Project during normal (2010), wet (1996), and dry (2001) years. 2.3.2 Spillway Operations The Project operates in a run-of-river mode under low to moderate streamflow conditions. During periods of moderate to high runoff (>17,000 cfs), river flow and spill is intended to be discharged at the Main Dam, East Channel Dam, and headrace walls. The headrace wall also contains three notches used to help pass ice and debris over the wall during high flows as follows: (1) spill section number 1 is approximately 95 feet long with a crest elevation of 278 feet; (2) spill section number 2 is approximately 480 feet long with a crest elevation of 279.2 feet; and (3) spill section number 3 is approximately 250 feet long with an elevation of 279.5 feet. Figure 2.3.1-1 York Haven river flow in normal, wet and dry years. Page 7 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 2.4 Fishway Operation The operation of the current fishway located at the East Channel Dam is part of a cooperative private, state, and federal effort to restore American shad (Alosa sapidissima) and other migratory fish to the Susquehanna River. In 1997, YHPC and the resource agencies reached a settlement agreement to revise the type and location of the York Haven fish passage facility. The fishway is located in Dauphin County, PA at the Three Mile Island end of the East Channel Dam at the York Haven Project. The fishway was first placed into service by YHPC in April 2000. Fishway operation for American shad passage includes the provision of certain additional minimum flow releases at the Project. As part of the 1997 agreement, YHPC agreed to maintain a spill of 4,000 cfs over the Main Dam and a minimum release of approximately 2,000 cfs at the East Channel Dam during operation of the fishway for the upstream passage of American shad. In addition to the minimum required release of 2,000 cfs in the East Channel, the fishway operational protocol flows through the fishway itself are 67 cfs. River flow in excess of spring minimum flow requirements and station capacity is spilled over the Main and East Channel Dams. Spring minimum flows are maintained 24 hours a day during the entire American shad upstream passage operating season. When river flow is less than 23,000 cfs during the shad passage season, East Channel flows are maintained through the wheel gates at the dam and a minimum spill of 4,000 cfs is maintained over the Main Dam by curtailing operation of powerhouse turbines as necessary to maintain the 4,000 cfs spillway flow. YHPC entered into a Consent Order and Agreement with PADEP in June 2010 regarding resident fish passage operations and flow in the East Channel. Under this arrangement, after the American shad upstream passage season ends, the East Channel fishway is operated for the purpose of resident fish passage through the earlier of December 15 or when river temperature is ! "#$! %! &'(! )*(++! ,'-.+,/)01+! 234.5! ! 6&)+(! )*+! 67+(0,3-! .*32! /8.)(+37! 83..39+! .+3.'-:! 3-2! during this resident fish passage period, the Project maintains a minimum stream flow of 400 cfs or greater in the East Channel below the East Channel fishway through the end of the resident fish passage period. At the end of the resident fish passage season, the fishway is closed for the winter. Annual maintenance and repairs are made as needed prior to April 1st of the following year. 2.5 Project Flows and Generation 2.5.1 Project Flows The Project uses the USGS 01570500 Susquehanna River gage at Harrisburg, Pennsylvania to estimate flows to the Project. Inflow to Lake Frederic can be estimated by multiplying the Harrisburg gage flow (24,100 square mile drainage) by a factor of 1.04 to account for the additional drainage area and flows entering the river between Harrisburg and York Haven. 2.5.1.1 Mean and Median Flows The mean annual flow at the Project based on the discharge records at USGS gage 01570500, as adjusted for differences in drainage area, for the period of record 1931 to 2010 is 35,469 cfs. The lowest annual mean flow of 19,523 cfs occurred in 1965 and the highest annual mean flow Page 8 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 of 61,662 cfs occurred in 1972. As shown in Table 2.5.1-1, the mean monthly flows at the Project for the period October 1, 1931 through December 31, 2010 ranged from 11,625 cfs (August) to 74,407 cfs (April). Monthly and annual Project flow duration curves for the period 1931 to 2010 are provided in Attachment B-1. Table 2.5.1-1 Estimated monthly flows at the York Haven Project. January Adjusted Monthly Flows 1931 to 2010 (cfs) Mean Median 39,877 25,906 February 41,913 Month 28,807 March 72,585 54,609 April 74,407 57,459 May 45,197 35,335 June 26,829 18,445 July 14,876 10,984 August 11,625 7,761 September 13,177 6,839 October 17,739 9,067 November 29,082 21,450 December 39,200 27,978 2.5.1.2 Critical Period Flows The lowest annual streamflow for the period of record of 1931 to 2010 occurred in the calendar year 1965. The mean annual flow in that year was 19,523 cfs, compared to the period of record mean annual flow of 35,469 cfs. This year represented the lowest mean annual Project flow recorded at the USGS gage. 2.5.1.3 Flows Downstream of the Main Dam and East Channel Dam The York Haven Project is operated with a year-round continuous minimum flow requirement of 1,000 cfs and an average daily minimum flow requirement of 2,500 cfs, or inflow, whichever is less, both of which can be delivered through the powerhouse. These flows may be temporarily modified if required by operating emergencies beyond the control of YHPC. The Project is also required to provide an average daily minimum flow of 2,000 cfs at the East Channel Dam and spill 4,000 cfs at the Main Dam during the upstream fish passage of American shad. The Project also provides an average daily minimum flow of 400 cfs at the East Channel Dam throughout the resident fish passage season. Additionally, although not specifically required, YHPC provides a minimum flow of 1,000 cfs on the west side of the river for the benefit of the Brunner Island cooling water intake located downstream of the Project. When river inflow exceeds the hydraulic capacity of the Project structures, the available water above the hydraulic capacity spills over the Project spillways at the Main Dam and East Channel Dam. Page 9 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 2.5.2 Project Generation The Project has 20 generating units operating in a run-of-river mode with an installed capacity of 19.62 MW and an estimated maximum hydraulic capacity of 17,000 cfs under optimum head conditions. The 20 individual generating units range in output from 700 to 1,600 kW. The Project is capable of maintaining run-of-river operations and impoundment water level under low to moderate streamflow conditions. Since the installed units are all fixed gate units, the Project’s minimum hydraulic capacity is 700 cfs, which represents operation by Unit 14 alone. The Project is operated in coordination with the operation of other generating facilities on the Susquehanna River and the Pennsylvania-New Jersey-Maryland (PJM) Interconnection. Aside from coordinating regionally, the York Haven Project consults and coordinates with two downstream hydroelectric projects on the Susquehanna River - Holtwood (P-1881) and Safe Harbor (P-1025). York Haven Power Company coordinates with these projects on Project operations, including fish passage, minimum flow releases, and river debris management. 2.5.2.1 Average Energy Production and Utilization As shown in Table 2.5.2-1, the average annual energy production of the York Haven Project for the period of 2001 to 2011 was 132,271 megawatt hours (MWh). Table 2.5.2-1 2.5.2.2 York Haven’s average annual energy production, 2001-2011. Year Average Energy Production (MWh) 2001 116,880 2002 136,128 2003 142,955 2004 140,469 2005 117,849 2006 156,613 2007 119,072 2008 127,350 2009 155,590 2010 124,196 2011 117,878 Average Annual 2001-2011 132,271 Annual Plant Factor Based on the Project’s installed capacity of 19.62 MW and historic average annual plant generation of 132,271 MWh (2001-2011), the Project has an annual plant factor of 0.77. Page 10 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 2.5.2.3 Estimate of Dependable Capacity The Project is estimated to have a dependable capacity of 17.57 MW. This number represents equivalent forced outage rate demand (EFORd) values assigned to the Project by the PJM Interconnection. This performance based value is the average of the PJM’s issuances for the Project for the years 2007 through 2015. The number is a calculation of a variety of factors including service hours, full forced outage hours, equivalent derated hours, full “f” factors, and partial “f” factors. These “f” factors are statistical values that approximate how many full forced outage hours and equivalent derated hours, respectively, were high-demand hours. 2.5.2.4 Plant Capability Versus Head The normal pool elevation of the Project is 277.9 feet and the impoundment is only able to be drawn down 1.1 feet from this elevation. Under current operations, when available water flow to the turbines is less than maximum hydraulic capacity for any hour, the operators at the Project monitor headwater to ensure pool elevations remain at the target elevation required by the FERC license. Under these conditions, headwater variation is typically in the range of +/- 0.2 feet but actual values can vary somewhat. When available flows exceed Project hydraulic capacity, as is the case approximately 60% of the year, water will spill over the Main Dam, East Channel Dam, and headrace walls. The estimated powerhouse capacity at various values of net head is shown in Figure 2.5.2-1. Under a flow of 17,000 cfs and at the normal headwater elevation of 277.9 feet, the net head is approximately 21.3 feet, although this can vary along the length of the powerhouse. The maximum net head is estimated to be about 22.5 feet under low flow conditions and the minimum net head can be limited to just several feet under flood flow conditions. Figure 2.5.2-1 York Haven power plant capacity versus net headwater of 277.9 feet. Page 11 head under normal Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 2.5.2.5 Tailwater Rating Curve The York Haven Project tailwater rating values are shown in Table 2.5.2-2 and Figure 2.5.2-2. Table 2.5.2-2 York Haven tailwater rating data. Flow (cfs) 1,000 2,000 4,000 8,000 17,000 30,000 50,000 100,000 238,000 Tailwater Elevation (feet) 251.1 251.3 251.6 252.3 253.6 255.0 256.5 259.3 264.6 266 264 Tailwater Elevation (ft) 262 260 258 256 254 252 250 0 50,000 100,000 150,000 200,000 250,000 Flow (cfs) Figure 2.5.2-2 York Haven tailwater rating curve. 2.5.3 Impoundment Operations The Project’s impoundment, Lake Frederic, is approximately 3.5 miles long with a surface area of 2,218 acres and approximately 9,600 acre-feet of gross storage capacity. The usable storage capacity within the allowable 1.1 feet of fluctuation is about 1,700 acre-feet, or approximately Page 12 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 1.2 hours of storage at the plant’s maximum hydraulic capacity. The reservoir surface area is estimated to be reduced to approximately 1,990 acres at the maximum draw down of 1.1 feet. Figure 2.5.3-1 provides information on the elevation-storage characteristics of the impoundment (GPU Service Corporation, 1979). No data exist to establish a reliable elevation-water surface area curve. Because of the unique physical configuration of the Project, hydraulic gradients also exist within the impoundment. For example, headwater elevation in the East Channel is driven more by inflow than by main channel conditions, with the entrance to the channel, at the upstream end of Three Mile Island, located approximately five miles upriver from the powerhouse. Elevation gradients can exist from one end of the Main Channel Dam at Three Mile Island to the other at the headrace wall, and also from the upper to the lower portions of the headrace channel. As the powerhouse is long and oriented in an upriver to downriver position, elevation gradients can even exist within the forebay from Unit 1 to Unit 20. 280 279 278 Reservoir Elevation (ft) 277 276 275 Storage Volume Data 274 Normal Water Elevation 273 272 271 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 11,000 12,000 Storage Volume (ac-ft) Figure 2.5.3-1 York Haven elevation and storage curve. 2.6 Proposed Future Project Operations YHPC is proposing to continue current plant operations related to power generation at the Project. Page 13 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 3.0 RESOURCE UTILIZATION AND FUTURE DEVELOPMENT An analysis of resource utilization was conducted by YHPC. Results of this study were included in the Initial Study Report (ISR) filed with FERC on April 4, 2011. The objective of the study was to evaluate the feasibility of increasing the hydraulic capacity of the plant by replacing existing turbine-generator units with new units. Three capacity expansion alternatives were investigated for increased hydropower potential at the site. The incremental energy production provided by each alternative was estimated using monthly flow duration curves developed from mean daily flow data. The results of the engineering evaluations of the three options are summarized below: Option 1 increased annual generation by approximately 9,300 MWh, or 7.2 percent, from 129,900 to 139,200 MWh at a cost in 2011 dollars of $26.8 million. Option 2 increased annual generation by approximately 24,800 MWh, or 19.1 percent, from 129,900 to 154,700 MWh at a cost in 2011 dollars of $93.4 million. Option 3 increased annual generation by approximately 4,700 MWh, or 3.6 percent, from 129,900 to 134,600 MWh at a cost in 2011 dollars of $15.2 million. None of the alternatives were deemed feasible nor are they expected to be in the near term. Therefore, YHPC is not proposing any new development for the Project at this time. 4.0 COMMENTS ON DRAFT LICENSE APPLICATION Comments received on Exhibit B of the Draft License Application are listed below together with YHPC’s response. Comment by FERC staff: “In section 2.5.1.3, you state that the project is required to provide a minimum flow of 2,000 cubic feet per second (cfs) at the East Channel dam and spill 4,000 cfs at the Main dam during the American shad upstream passage season, and 400 cfs at the East Channel dam throughout the resident fish passage season. In the final license application, please specify if these flows are continuous or on an average daily basis.” YHPC response: Flows currently released at the Project for fish passage are on an average daily basis, but YHPC is in discussions with the fishery agencies exploring options for improving fish passage at the Project and these flow releases may be modified during development of the final fishway plan. Comment by FERC staff: “In section 2.5.2, you provide the maximum hydraulic capacity of the project. In the final application, please also provide the minimum hydraulic capacity of the project as required by section 4.51(c)(2) of the Commission’s regulations.” Page 14 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 YHPC response: Because the installed units are all fixed gate units, Section 2.5.2 has been revised to note that the Project’s minimum hydraulic capacity is 700 cfs, which represents operation using only Unit 14. Comment by FERC staff: “Although figure 2.5.3-1 in Exhibit B presents the reservoir storage capacity versus head curve, you do not provide a curve showing impoundment areas with varying heads in the reservoir. In the final application, please provide a reservoir area versus head curve for the project as required by section 4.51(c)(2) of the regulations.” YHPC response: Although the current license allows a 1.1 foot drawdown in impoundment elevations, the Project actually operates in run-of-river mode and as such, has no usable storage capacity that is used to enhance power production. Because there is no use of Project storage, no data were obtained to determine the area of the impoundment under draw down conditions. The area of the impoundment under the 1.1 feet of allowable drawdown used for maintenance purposes is provided in Section 2.5.3. Comment by FERC staff: “In section 2.5.3, table 2.5.3-1 presents tailwater rating data for the project with figure 2.5.3-2 showing the tailwater rating curve; however, the values in the table do no seem to match the values shown in the rating curve. Please correct this discrepancy in the final application.” YHPC response: Table 2.5.2-2 has been revised. Comment by FERC staff: “In section 2.5.2.4, you provide a power plant capacity versus head curve in figure 2.5.2-1, and state that the normal pool elevation is 277.9 feet, with the impoundment only drawn down 1.1 feet from this even during periods of low flow; however, it is not clear what would be the net head shown in figure 2.5.2-1 at the elevation of 277.9 feet. In the final license application, please specify the maximum, minimum, and normal heads in figure 2.5.2-1.” YHPC response: The maximum, minimum, and normal net heads are provided in Section 2.5.2.4. Comment by FERC staff: “Section 4.51(c)(2)(ii) of the Commission’s regulations requires an area-capacity curve showing the gross storage capacity and usable storage capacity of the impoundment, with a rule curve showing the proposed operation of the impoundment and how the usable storage capacity is to be utilized. On page 12, figure 2.5.3-1 shows the York Haven elevation and storage curve; however, the figure does not include a surface area curve within the capacity curve. In the final license application, please add the surface area versus reservoir elevation curve to the capacity curve shown in figure 2.5.3-1.” YHPC response: Data do not exist to develop an elevation-area curve because the only allowed drawdown is 1.1 feet and this is used for maintenance purposes. The estimated water surface area at the drawdown of 1.1 feet is provided in Section 2.5.3 above. Page 15 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 Comment by PPL Brunner Island, LLC staff: “PPL Brunner Island, LLC (PPL BI) requests that the continuous minimum flow requirements be changed to 1,500 cfs to be discharged through the powerhouse and that such continuous flows be directed down the west (York County) side of the river. PPL BI further requests that inflows for the purposes of meeting this continuous minimum flow requirement be natural river flow as measured at the Harrisburg USGS gauging station.” YHPC response: PPL BI filed comments with FERC on August 6, 2012. Comments on the DLA were due to be filed with FERC by July 3, 2012. Currently, no proposed minimum flow modifications have been presented. YHPC will engage in discussions with PPL BI to discuss minimum flows. Comment by PPL Brunner Island, LLC staff: “PPL BI requests that YHPC be required to provide a minimum one-hour notification to the Brunner Island Steam Electric Station Operations staff prior to debris sluicing so that the plant can adequately prepare the intake structure for potential debris and minimize any impacts to plant operations.” YHPC response: Prior to opening the sluice gate, YHPC notifies PPL’s Brunner Island Station that debris is to be sluiced. Absent extraordinary or emergency circumstances, YHPC will provide this notification at least one-hour prior to debris sluicing. 5.0 LITERATURE CITED GPU Service Corporation. 1979. York Haven Project, FERC License No. 1888. Letter to GPU Service Corporation to Susquehanna River Basin Commission. January 12, 1979. Page 16 Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 ATTACHMENT B-1 ANNUAL AND MONTHLY FLOW DURATION CURVES FOR USGS GAGE 01570500 (1931 TO 2010) Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 ANNUAL Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 JANUARY Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 FEBRUARY Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 MARCH Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 APRIL Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 MAY Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 JUNE Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 JULY Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 AUGUST Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 SEPTEMBER Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 OCTOBER Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 NOVEMBER Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 DECEMBER Exhibit B- Final License Application York Haven Hydroelectric Project – FERC No. 1888 Photo 1: Project powerhouse viewed from the east side of the river. Photo 2: Project powerhouse looking upstream from the west side of the river. Photo 3: Main Dam viewed from the west side of Three Mile Island looking south-west. Photo 4: Main Dam viewed from the west side of Three Mile Island looking south-west. Photo 5: East Channel Fishway. Photo 6: East Channel Fishway. Photo 7: East Channel Fishway. Photo 8: East Channel Dam viewed from East Channel Fishway. Photo 9: Project powerhouse and headrace wall viewed from east side of river. Photo 10: Project forebay viewed from west side of river. Photo 11: Interior of Project powerhouse. Photo 12: Catwalk on eastern side of Project powerhouse above the tailrace viewed from the south. Photo 13: Catwalk on eastern side of Project powerhouse above the tailrace viewed from the north. Photo 14: Headrace wall viewed from the south. Photo 15: Headrace wall viewed from the south. Photo 16: Project powerhouse viewed from the north. Photo 17: Portage trail. Photo 18: Portage trail. Photo 19: Picnic area adjacent to Project powerhouse. Photo 20: Picnic area adjacent to Project powerhouse. Photo 21: Representative Project island recreational facilities. Photo 22: Representative Project island recreational facilities. Photo 23: Representative Project island recreational facilities.