Participating Generator
Implementation
DB59 Scope Overview
February 13, 2012
Agenda
• DB59 Critical Dates
• Step-by-Step
–
–
–
–
–
–
–
–
Agreement
Spreadsheet
Communications
Specifications
Meter Package
Installation
Test & Inspect
Final Package
Page 2
DB59 Critical Dates
• 2/14/12 – Final Scope Cutoff
– IFC Drawings conformed with Drawing Requirements located in
Section 18 of Telemetry BPM
• 3/22/12 – External Cutoff Date
– Refer to Section 10 of Telemetry BPM for related requirements
• 6/14/12 – Estimated Model Release to Production
+7C days for Master File Data Freeze
+2B days for System Operations Approval
Page 3
Step-by-Step: 8 - Steps
Typically the metering and telemetry
are the last items in an implementation
project to be completed
Final Package
Page 4
Step-by-Step: Agreement
Step 1:
Obtain an Interconnection Agreement to get started in the
Participating Generator Implementation (PGI) process.
Page 5
Step-by-Step: Implementation Spreadsheet
Step 2: Review and Execute the
various steps outline within the
Implementation Spreadsheet.
Key Areas:
• Metering
• Telemetry
• Agreements
• Various Submission/Notification
Page 6
Initial Contact Request Form
• Please complete this form and submit it to the following mailbox:
NewResourceImplementation@caiso.com. The subject of the email should be the
Project Name, concurrent with what is written in the initial contact information request.
• Once this has been submitted you will receive an email shortly after with an
assigned CAISO project number.
Page 7
Project Details for CAISO
• After receiving the assigned CAISO project
number you will receive an email requesting
you to complete a Project Details
template. Please fill this out with all known
project information and submit to the mailbox:
NewResourceImplementation@caiso.com.
The subject of this email and all other project
related email should now always contain both
the CAISO Project Number and Project
Name.
• Please also resubmit the initial resource
package containing the Issued for
Construction drawings and interconnection
studies. This email should be sent to the
NewResourceImplementation@caiso.com
and the subject of the email must contain the
CAISO Project Number and Project Name.
Page 8
Step-by-Step: Communications
Step 3: Establish Communications
•
Order a ECN circuit from AT&T (Requires physical resource facility
address)
•
Install a CAISO Telecommunications Circuit and required
equipment
•
Obtain a CAISO IP addresses from AT&T 5B days prior to FNM
External Cut-off date.
Page 9
FNM Database Submission RIG Requirements
Timing parameters for the FNM process. They are
derived from the FNM External Cutoff date, they are in
business days.
 (-15B) Single-line diagrams that show connection from resource
to grid and initial revenue metering package.
 (-5B) Email to RIG Engineer both ECN IP address range and the
communication block diagram.
 (-1B) Fully collaborated, completed and approved database by
resource owner and CAISO RIG Engineering.
Page 10
FNM Database Build - Timeline
All Generation - Approved
construction single line diagrams and
Initial revenue metering package.
Wind Generation
-Longitude, Latitude, Hub Height of
all Turbines and MET towers.
-List of all DT approved by
forecaster.
-Topographical map of Wind farm
turbine layout
Solar Generation
Identifying the type of solar resource,
type of inverters, and Topographical
map of Solar farm panel layout
-15B
Generator Email
ECN IP Address
to CAISO and
RIG
Communication
Block Diagram.
-5B
A list of owner, site
and integrator
names, phone
numbers, and
email contact
information.
Completed and
approved
database.
-1B
External
Cut-Off
Page 11
New or Modified RIG Database
• CAISO RIG Engineer will start the first draft of the database
spreadsheet
• The resource owner will need to verify all the required data points on
the RIG Engineering spreadsheet will be available.
Page 12
Step-by-Step: Specifications
Step 4: Obtain Metering Documentation Specifications and
Meter Device ID(s) from CAISO.
Documentation specifications are available on the CAISO web site
at: http://www.caiso.com/thegrid/operations/gcp/index.html
Your assigned CAISO Meter Engineer will provide you with device
ID’s for the CAISO certified meter(s).
Page 13
Step-by-Step: Documentation - Initial
Step 5: Compile and Complete “Initial” Metering Package 15 days
prior to Full Network Model (FNM) External Cut-Off date.
•
•
•
•
•
•
•
•
Metering Scheme Overview
CAISO Metering Certification form(s)
Metering One-line Diagram with Point of Receipt (POR)
Metering System 3-line Diagram
Meter Calculation Worksheet
Metering Communications Drawing
Compensation Calculation to POR
Site Location on a Map or Directions
Page 14
Metering Documentation
Metering Packet:
• Metering Scheme Overview
– Allows engineers to validate meter setup and
site layout per the IFC drawings.
• Site Location / Directions (Map)
– List GPS coordinates, site address, driving
directions, and map to each site
Page 15
Metering Documentation
(Use IFC drawings instead)
ISO 115 KV
GRID
Metering Packet:
Point of Delivery
PG&E
Tap Line
• Metering 1-Line Drawing with POR
14 Mi.
– Used to determine loss compensation for
meters
115 kv
FUSE
AND
RELAY
PANEL
115 - 12.5 KV
10 MVA
OA/FA/FA-65 DEG. C
Z= 5.5 % @ 10 MVA
6 Mi.
PG&E
QUAD
4+
METER
ISO
QUAD
4+
METER
TEST SW.
TEST SW.
12.5 kv
3 - 400:5 A
3 - 7200:120 V
• Metering Communication Drawing
4.16/12.0 kv
1.5 mva
– Provides overview of the network topology
1.2MVA
4.16 KV. 60 HZ
PF 0.80
– RIG Communication Drawing is acceptable
APPROVALS
DESIGNED BY
DRAWN BY
AEJ
PROJECT
DESCRIPTION
ABC Landfill Gas Project
ISO INTERCONNECTION
ONE-LINE DIAGRAM
OWNER
ENERGY 2008
REVIEW ENGR
LOCATION
ISO
INGALLS POWER PRODUCTS
BLONDEL
ISO DIVISION
ISO REVENUE METERING
DATE
1111 Nut Rd., Meridian, CA 95648
APRIL 23, 2008
DWG. NO
REV
E 2008 - 0027-1
• IFC Drawings with meter location(s) will be the
only acceptable Drawings after DB59.
Page 16
Metering Documentation
Metering Packet:
• Metering Calculation Worksheet
– Shows methodology for
calculating loss compensation
for meters
• Compensation Calculation to
POR
Page 17
Metering Documentation
• CAISO Metering
Certification Form
– Needed to
configure MV90 for
collection and
processing of
Revenue Quality
Meter Data (RQMD)
Page 18
New Site
CAISO Metering Certification Form
• Triggers the start of the process
• Contains necessary setup information to
interrogate and validate meter data
•
•
•
•
Device ID
Meter Type (Manufacture)
Communication Information
Multipliers
Page 19
Certification Form: Communication
CAISO Metering Certification Form
• Missing, Inaccurate information, or
communication problems will “stop” the
process needed to validate the data.
• It is up to the “owner” to resolve all issues in
order to resume progress and to contact
CAISO meter engineering to verify that all
required data has been received.
• If this is not completed by FNM External Cut
Off date -15 Business Days, the resource will
be moved to the next model build
Page 20
Step-by-Step: Meter Installation
Step 6: Installation of CAISO Revenue Metering:
–
Must be an CAISO Approved Meter
–
Meter installation may be performed by a qualified electrical
contractor or one of the approved Turnkey Metering
companies listed on CAISO.com:
http://www.caiso.com/Documents/CompaniesDoingTurnkeyIS
OMeterInstallations.pdf
Page 21
Metering – Roles & Responsibilities
Resource Owner will:
– Own the CAISO Metering Facilities
– Maintain the CAISO Metering Facilities
– Ensure the accuracy of the meter data
– Submit the original prints and CAISO Metering Certification Form to
CAISO for review and approval
– Contract a CAISO Authorized Inspector to verify Metering Facilities
and submit Site Verification Forms to CAISO
Page 22
Step-by-Step: Validation
Step 7: Test Meter(s) and perform Site Inspection by an CAISO
Certified Inspector.
The certification must be performed by a CAISO approved
company from the following list:
http://www.caiso.com/Documents/ApprovedISOMeterInspectionCo
mpanies.pdf
Page 23
Step-by-Step: Final Documentation
Step 8: Compile and Submit “Final” Metering Package
–
Includes all documentation required within the “Initial” Metering
Package plus
• Site Verification Forms
• Meter(s) Program(s)
• Meter Service Agreement Schedules 1, 2, and 3
–
Must be completed and received by CAISO
- 5B days prior to initial synchronization to the grid
•
Metering certificate shall be final or the meter will not be validated
Page 24
Summary
Step-by-Step
–
–
–
–
–
–
–
–
Agreement
Spreadsheet
Communications
Specifications
Meter Package
Installation
Test & Inspect
Final Package
DB59 Critical Dates
• 2/14/12 – Final Scope Cutoff
–
IFC Drawings conformed with Drawing
Requirements located in Section 18 of
Telemetry BPM
• 3/22/12 – External Cutoff
–
Refer to Section 10 of Telemetry BPM for
related requirements
• 6/14/12 – Estimated Model
Release to Production
+7C days for Master File Data Freeze
+2B days for System Operations Approval
Page 25
Summary
• Next Scheduled DB59 Conference Calls:
– March 7, 2012 at 9:00 am
• For any follow-up questions or concerns, please email
the general New Resource Implementation mailbox at:
NewResourceImplementation@caiso.com