TRANSMISSION The world’s biggest FACTS project with series compensation by K Braun, A Krummhoiz, D Retzmann, U Rohr, G Thumm, Cigré Progressive worldwide urbanisation and the trend towards megacities with more than 10-million inhabitants pose new challenges. According to UN statistics more than half of the gross domestic product of every country in the world is produced in the large cities. One of the most important factors for successful economic dynamics in megacities is an effective infrastructure. It goes without saying that the basis for this infrastructure is constituted by a reliable and efficient power supply. An important development in the power supply of megacities is the relocation, for environmental reasons, of power generation from city centres to more distant surrounding regions. However, sufficient power to cover the ever increasing demand must be delivered from additional sources which are normally located very far from the load centres. For this reason transmission of large power blocks over long distances is becoming increasingly important. Furthermore, efficiency and reliability of supply play an important role in planning electrical systems, particularly in the face of increasing energy prices and almost incalculable safety risks during power blackouts. power generated in the Tala hydroelectric power plant (located in Bhutan) is transmitted via a newly built 400 kV double circuit transmission line to Gorakhpur substation. There the line is connected to the existing 400 kV network and feeds into the northern industrialised region around the capital New Delhi. Due to this interconnection the north east of India can also profit from economical hydro power. Benefits of series compensation Series compensation is the ideal “low cost” solution for bulk power long distance AC transmission. Series compensation can also be applied very effectively in meshed systems for balancing the load flow by means of ‘load displacement’. The principle of series compensation consists of using a series capacitor which compensates the for the line’s reactance, so the line becomes virtually shorter. Due to this, the transmission angle is reduced and the system stability is increased. This enables a higher transmission capacity of the existing line without having to install new lines. The simplest form of series compensation is “fixed series compensation” (FSC). The systems at Purnea and Gorakhpur substations use a combination of FSC and TCSC (thyristor controlled series compensation). TCSC is used if fast control of the line impedance is required, for load flow control, and for damping power oscillations. The main features of series compensation schemes are that they increase the transmission capacity and, in the case of controlled series compensation, they also This is also the case in India. An increasing demand for electricity and a growing awareness of the need for reliable power supply, for their fast developing megacities in particular, have prompted Powergrid (the utility company which operates India’s high voltage transmission networks) not only to continue with its transmission plan, but also to strengthen its networks with flexible AC transmission systems (FACTS). This promising transmission enhancement plan was developed and implemented by Powergrid in order to establish an integrated national power grid and to support an additional program for new generation capacities. Today’s program of 9500 MW interregional power transfer capacity is expected to be enhanced to 30 000 MW by 2012. With the help of its 400 kV series compensation systems, which are the preferred FACTS solutions for Purnea and Gorakhpur substations projects (see Fig. 1), Powergrid has taken steps to enhance its east to west power transfer. The Fig. 1: Purnea substation. energize - April 2007 - Page 36 TRANSMISSION Basically, the thyristor valve could have been used to provide the bypass function alone, without the spark gap. For this project, however, it was decided to use a separate triggered spark gap as a fast protecting device, because of very high thermal stress for the thyristors caused by extremely high fault currents. This enables immediate operation of the thyrister valve in the full dynamic range, e.g. for power oscillations damping which is normally required after fault clearing in order to stabilise the system. The capacitor discharge current is limited by means of the bypass damping circuit in the same way as in the case of the FSC. Fig. 2: Single line diagram of Purnea / Gorakhpur substation for FSC and TCSC. provide damping for power oscillations, load flow control and mitigate SSR (subsynchronous resonances) Design aspects of series compensation At Purnea and Gorakhpur substations in the northern part of India both fixed series compensation (FSC) and thyristor controlled series compensation (TCSC) are used. Fig. 2 shows the single line diagram. FSC A segment of a fixed series capacitor bank (FSC) consists of a capacitor bank and a MOV (metal oxide varistor) assembly, connected in parallel. It also includes a spark gap which is used to protect capacitors and MOV against over-voltages which occur during and after faults in the transmission system. protected against over-voltages by the MOV. The MOV is designed to withstand stresses such as these. The operation strategy for the bypass devices is the same as for the FSC. The thyristor valve branch with the reactor is connected in parallel to the capacitor. The impedance of the parallel L C circuit can be varied by means of firing the thyristor valve. In case of AC line faults the thyristor valve can be blocked in order to reduce the capacitive impedance and consequently the fault current. A damping circuit is connected in series with the triggered spark gap and the bypass switch in order to reduce component stress during transient discharge of the capacitor. The bypass switch is connected in parallel with the spark gap to provide current commutation for the time when the current capability of the MOV or the spark gap is exceeded during AC faults. In case of high short circuit currents caused by faults on the AC line, to which the capacitor bank is connected, the spark gap and the bypass switch will be triggered in order to protect the capacitor and the MOV from overload. A fault on other lines, for example behind the neighboring buses, usually produces lower currents in the series capacitor and the bypass devices do not need to be operated. TCSC The main components of the TCSC segment are also shown in Fig. 2. The capacitor is energize - April 2007 - Page 37 The TCSC offers the opportunity of power oscillation damping and power-flow control via the controllable impedance. The thyristor controlled reactor branch is formed by a reactor and a thyristor valve. The thyristor valve is made up of a number of series connected thyristors, two branches of which are connected in anti parallel. The valve is located in a housing on the platform. For FACTS applications, thyristors are a key element in control of passive components. Siemens is the only company which supplies the LTT (direct light triggered thyristor) valves with wafer integrated over-voltage protection for HVDC and FACTS. The system of direct light triggering fires the thyristors with a light pulse. TRANSMISSION A TCSC was found to be the optimal solution to damp these oscillations. For power oscillation damping the full capacitive operating range can be used. The benefits of the damping function are depicted in Fig. 4. Sub-synchronous resonances (SSR) studies Fig. 3: Light triggered thyristor (LTT) technology. The light pulse generated at ground potential is guided by fiber optics directly from the valve control to the thyristor gate. After fault clearing, the TCSC is ready to fulfill its main purpose - power oscillation damping with its full capacitive operating range. Light triggered thyristors offer significant benefits over conventional electrically triggered thyristors - less electronic components on high potential and increased reliability (see Fig. 3). Studies The thyristor valve is fired at an angle which is calculated according to control requirements - impedance control or current control. With impedance control the transmission angle of the line can be influenced and current control determines the load flow. In normal steady state operation the TCSC impedance is set to a value which is 1,2 times the capacitor impedance. The dynamic range covers 1,3 p.u. During remote faults in the system the thyristor valve continues firing. With severe disturbances the thyristor valve is blocked. The rated nominal technical data of the world’s biggest FSC/TCSC project are, for Purnea substation, 420 kV, 743 Mvar FSC and 112 Mvar TCSC and, for Gorakhpur substation, 420 kV, 716 Mvar FSC and 108 Mvar TCSC. In the run up to the basic design specifications, oscillation damping (POD) and subsynchronous resonance (SSR) studies were carried out, as well as calculations necessary for defining the control parameters. Power oscillation damping studies Studies showed that power oscillations occur between the two interconnected systems after severe disturbances, for example due to a loss of generation in one of the two systems. The compensation degree of a line has to be designed according to the system conditions - the line length and stability requirements. However, the design also has to take into account the fact that series compensated lines can excite torsional oscillations in generators with long shafts. These sub-synchronous resonances (SSR), as they are termed, can pose a severe problem for large thermal units such as steam turbines, combined cycle turbines, large gas turbines, and especially for nuclear units. Under certain conditions generator shafts as long as these can be damaged or even destroyed. Depending on the construction of the generator, the turbine and the excitation system, typical resonance frequencies of generator turbo set shafts are between 10 and 45 Hz with very low damping. Using only fixed series compensation without the TCSC, high levels of compensation on transmission lines can produce interaction of the electric resonances of the system with the mechanical torsional frequencies of generator shafts. A small disturbance in the electric torque can excite relatively high amplitudes of torsional oscillations when the corresponding electric frequency matches one of the mechanical oscillation modes of the generator shaft. An electric torque, produced by the LC circuit of line impedance and series capacitor, may act as a negative damping to torsional oscillations when the LC resonance frequency interacts with the generator shaft. The LC resonance frequency is of sub-synchronous nature, as the compensation degree is always less than 100%. A much better effect is produced using the TCSC for SSR mitigation by changing the apparent impedance of the TCSC according to torsional oscillation with a suitable phase to the oscillating electric torque. The passive mitigation effect of the TCSC depends on the resonance frequency, the firing angle, the line configuration, as well as on other system parameters, such as the short circuit power of the system. All these influencing parameters are covered in the SSR study. TCSC control Fig. 4: Power oscillation damping. energize - April 2007 - Page 38 The closed loop control (CLC), the open loop control (OLC) and the redundant protection system are fully digitalised with TRANSMISSION interconnected systems can be avoided. Resynchronisation of the two systems would be of great technical complexity, that is why avoiding separation is of vital interest for transmission. Project overview Siemens received the order for the FSC/ TCSC in the end of May 2004, and a project team with members from both India and Germany worked on it. The responsibilities in this Facts turnkey project, named TALA High Capacity East North Interconnector II, were shared between the head office in Germany and the Dehli office. Reactors, capacitor banks, MOV, circuit breakers, spark gaps, thyristor valves and the control system for this project, financed by World Bank, were supplied by Siemens Germany. All other equipment and activities which included platforms, civil works, installation and commissioning were provided by Siemens India. Erection and commissioning Fig. 5: Gorakhpur substation. Siemens’ Win TDC signal processor system. A number of signals are measured on the platform at high voltage. After conversion into optical pulses the signals are sent to ground potential via fiber optic links, and then reconverted into values in a digital format. The auxiliary power supply for the conversion on platform is sent via a second fibre optic link. The main task of the closed loop control system is to determine the firing angle (alpha) which defines the TCSC impedance. Normally, the TCSC operates in the impedance mode, where the TCSC provides an impedance as required (reference value). As soon as power oscillation along the line is detected by means of line current measurement, the control system switches over to the power oscillation damping mode. The trigger set generates the firing pulses according to the firing angle which is the input value. The correct timing of the firing pulses is continuously synchronised with the AC system frequency through the line current. Digital filtering is used to determine the reference point for each firing pulse. It is also the case under system conditions with non sinusoidal waveforms of line current. The control and protection of the TCSC detects eventual overload of all components, and it takes into account the overload requirements. The protection can respond by blocking the thyristor valves, by triggering the spark gap (fast bypass) and by closing the bypass switch, depending on the type, severity and duration of the fault. After a single phase fault in the system, it is foreseen that only the faulty phase is opened by the line protection, and it will be re closed after about one second. In this case, only one phase element of the TCSC is bypassed to provide the highest possible stabilisation of the system. Only when the line is opened in all three phases, will the TCSC be bypassed in all three phases as well. The use of a configuration with the FSC plus the TCSC offers significant benefits for the transmission of power. The fixed series capacitors (FSC) compensate 40% of the line impedance, reduce transmission losses and, consequently, increase power transfer. They also improve steady state and dynamic stability of the system. Thyristor controlled series capacitors (TCSC) constitute the solution which provides transient stability of the increasing power transfer. Each of the TCSC is designed to compensate 6% of the line impedance during steady state operation, and to vary the impedance in transient conditions in a range between 1 and 3 p.u. This enables damping power oscillations which may occur during and after system disturbances. This means that, with the advanced control features of the TCSC, separation of the two energize - April 2007 - Page 39 Early in 2006 the transmission lines and FACTS equipment were put into operation. Since then they have been providing a reliable transmission corridor for delivering power from the eastern part of India to the load centers in the north of the country. Fig. 5 shows a view of the installation at Gorakhpur substation. Acknowledgement This article was first published in the December 2006 issue of Cigré’s Electra magazine and is republished with permission.