050506 Approval Of Otay Mesa Power Purchase

advertisement
California Independent
System Operator
Memorandum
To:
ISO Operations (MRTU) Committee
From: Armando J. Perez, Director of Grid Planning
cc:
ISO Board of Governors
ISO Officers
Date:
April 29, 2005
Re:
Otay Mesa Power Purchase Agreement Transmission Project
This memorandum requires Board action.
EXECUTIVE SUMMARY
This memorandum requests ISO Governing Board approval of the Otay Mesa Power Purchase Agreement
Transmission Project (Project). The Project is a combination of new line construction and modifications to
existing lines and substations that will result in the creation of two new 230 kV transmission lines in the San
Diego area (see Figure 1). One of the new lines would go from Otay Mesa Substation to Sycamore Canyon
Substation (37 miles total length - 28 miles of new line construction). The other transmission line would go
from Otay Mesa Substation to Old Town Substation (33 miles total length - 24 miles of new line
construction). The completion of the Miguel–Sycamore Canyon 230 kV transmission line is proposed to be
completed by June 2006. The completion of the Otay Mesa-Old Town 230 kV transmission line is proposed
to be completed by June 2007. The Project is needed to reliably deliver power from the Otay Mesa Power
Plant to San Diego customers. Without this project, congestion north of Miguel Substation would lead to
the need to curtail Otay Mesa output during high load periods when the generation is most needed. The
estimated capital cost of the Project is $ 209 million. Since the Project cost exceeds $20 million, ISO Board
approval is required.
The OMGP is needed to satisfy SDG&E’s resource adequacy requirements. In its decision D.04-06-011,
the California Public Utility Commission (CPUC) approved, among other items, SDG&E’s request to enter
into a ten-year power purchase agreement for the output of the Otay Mesa Generation Project, which is
presently under development by Calpine Corporation. However, the Commission recognized that “the
output of Otay Mesa is not fully deliverable, and cannot fully satisfy SDG&E’s local reliability needs, without
some transmission system upgrades”. The proposed Project is the preferred alternative for reliably
delivering Otay Mesa generation to San Diego. Normally, the ISO reviews and approves projects before
they are presented to the CPUC, however SDG&E has already applied to the CPUC for a Certificate of
Public Convenience and Necessity (CPCN) for the proposed project. To date, there has not been a CPUC
decision on this matter.
Fig. 1. Otay Mesa Power Purchase Agreement Transmission Project Map
Existing transmission lines
Proposed Project
Project’s alternative rejected due to higher cost and environmental
impact
Substation
Power Plant
AJP 4/25/05
-2-
BACKGROUND
In October of 2002, the CPUC directed SDG&E and the other utilities under their jurisdiction to file longterm procurement plans addressing power capacity needs for the years 2004 through 2023. In May of
2003, SDG&E issued a Request for Proposals (RFP) for reliability capacity for the procurement plan.
Additional in-system generation was needed to provide for load growth and to reduce Reliability-Must-Run
generation costs. In response to this RFP, in August 2003, Calpine submitted a proposal to provide
generation capacity and energy from the OMGP. At that time, the Otay Mesa project was already fully
permitted by the California Energy Commission (CEC) and Calpine had procured all the major equipment
and started construction. In June 2004, after review of all the projects submitted for the RFP, the CPUC
issued a decision (D.04-06-011) to approve new electric resource contracts for five proposals for new
resources for San Diego. The Otay Mesa Generation Project was one of the approved proposals.
However, the engineering studies indicated that the OMGP would cause significant congestion on the
transmission system north of Miguel Substation if additional transmission system upgrades were not
implemented. When the CAISO first approved the OMGP in May 2003, the approval letter specified that
extensive congestion management would be required and that the full generation output cannot be
delivered if the transmission system is not upgraded. After the Power Purchase Agreement for the OMGP
was approved by the CPUC, SDG&E performed extensive studies to develop alternative plans for upgrades
to allow for the full delivery of Otay Mesa output to San Diego.
The proposed Project was determined to be the preferred transmission solution. The CAISO sent a letter of
concurrence with the scope of the proposed project in November 2004.
The Existing Transmission System
The electric power needs of San Diego are met by a combination of local generation and imported power.
Transmission connections between San Diego and neighboring regions include five 230 kV lines that head
north towards Los Angeles, one major 500 kV line that heads east to Arizona (the Southwest Power Link or
SWPL), and one 230 kV line that heads south to Mexico. The maximum power that can be reliably imported
into San Diego through these facilities is 2850 MW. With the most critical of these transmission facilities out
of service (the SWPL), this capability is reduced to 2500 MW. The summer peak load in the San Diego
area this year is forecasted to be 4586 MW. The difference between the load in San Diego and the import
capability must be supplied by local generation sources. Current local generating resources include the
Encina Power Plant, the South Bay Power Plant, and a number of combustion turbine facilities located
around the service territory. Both the Encina and South Bay Plants are under Reliability Must Run (“RMR”)
contracts with the CAISO because they are necessary to meet the reliability requirements of the area.
Otay Mesa Generation Project
The OMGP will consist of two combustion turbine generators and one steam turbine generator. The
maximum total net generation output will be 615 MW1. The basic interconnection facilities associated with
the OMGP include:
1. Looping the Miguel-Tijuana 230 kV transmission line into the new Otay Mesa 230 kV switchyard.
1
This value is based on the interconnection capacity provided by Calpine.
AJP 4/25/05
-3-
2. Converting the Miguel-Otay Mesa section of the Miguel-Tijuana 230 kV line to two bundled 900
kCMIL ACSS circuits with separate circuit breakers.
3. Installing two remedial action schemes that will trip Otay Mesa generation for loss of the 230 kV
circuits between Otay Mesa and Miguel which share the same tower
The California Energy Commission has already permitted the above facilities as part of the plant’s basic
interconnection plan of service. The cost of these facilities is not included in the cost estimate for the
Project that is the subject of this memo. Calpine plans to complete construction of the OMGP by December
2007. The anticipated commercial in-service date for the Project is January 2008 when all the transmission
upgrades will be completed. The CAISO and SDG&E agree that the plant should not be allowed to come
on-line before all the transmission additions are completed. Presently, the construction of the plant is on
hold pending the approval of the Project.
Description of the Problem and the Transmission Project
The scope of facilities associated with the basic interconnection of the OMGP to the grid as described
above would connect the OMGP directly to Miguel Substation. However, with the OMGP connected to
Miguel Substation, and without any additional transmission upgrades from Miguel into the San Diego load
area, there would be significant congestion north of Miguel. The most effective means for eliminating this
congestion would be to reduce the output of the OMGP. The likelihood of encountering congestion would
increase with increased San Diego area load. As a result, when the OMGP is most needed (summer peak
load period), it would likely need to be curtailed to mitigate transmission congestion. To mitigate the
transmission constraints north of Miguel the following project was developed:
1. Creation of an Otay Mesa-Sycamore 230 kV line. This will require 28 miles of new overhead line
construction from Miguel to Sycamore on existing structures.
2. Creation of a Miguel-Old Town 230 kV line. This will require construction of a 14-mile overhead line
section (10 miles of new structures in an existing ROW and 4 miles of existing structures) and two
underground sections (7 miles in Downtown San Diego and 3 miles on the Chula Vista Bay front).
Each of these new lines will be routed through Miguel Substation but they will not normally be connected to
Miguel Substation. However, switching will be available to connect these lines to Miguel, which will be
desirable under some operating conditions. To allow this switching, it may be necessary to upgrade several
circuit breakers due to the increased short circuit duty at Miguel and Tijuana. In addition to the two 230 kV
transmission lines, the Project also includes:
•
Installing new 230 kV circuit breakers and associated equipment at the Old Town and Sycamore
Canyon Substations to terminate the new 230 kV lines.
•
Installing two 230 kV circuit breakers and associated equipment at the Miguel Substation to allow
for connections of the new lines to this substation when desired.
•
Reconductoring the Sycamore Canyon-Fanita Junction (Carlton Hills Tap) section of the existing
Chicarita-Carlton Hills- Los Coches 138 kV transmission line.
AJP 4/25/05
-4-
Project Cost
The estimated cost of the Project is $209 million, which excludes the plant’s basic interconnection costs.
DISCUSSION
Benefits of the Project
The Project would provide the following benefits:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Provide for the firm delivery of the OMGP to San Diego;
Support future reliability needs due to continued load growth;
Prevent the OMGP from increasing transmission congestion north of Miguel;
Reduce RMR costs by allowing the displacement of a portion of the RMR generation in the
SDG&E service area;
Provide higher operational flexibility during scheduled outages;
Improve system voltages;
Reduce system losses;
Avoid the need to trip additional generation and load for the Miguel transmission line corridor
outage;
Provide grid expansion capability for future load growth (Specifically, the addition of the Otay
Mesa-Old Town 230 kV line will provide the ability to reinforce the source of power to the
rapidly growing downtown area of San Diego.); and
Enable the retirement of a portion of old and relatively inefficient generation in the San Diego
area.
The studies for the Project and its alternatives indicate that the Project is the preferred alternative for
achieving the benefits listed above. In addition, the Project will minimize environmental impacts by utilizing
underground construction and by striving to avoid residential areas where practicable.
Alternatives to the Project
Several alternatives to the Project were studied. The most competitive alternatives are summarized in the
following table:
Alternatives for the Otay Mesa Power Purchase Transmission Project
Alternative
Advantages
Disadvantages
1. Construct an Otay MesaMission #3 230 kV line instead
of the Otay Mesa -Old Town
Same as the preferred alternative
- Estimated to have a higher cost due
to a longer underground section.
- Higher transmission losses.
- Would require the full dispatch of
South Bay generation where the
preferred alternative would only
require the partial dispatch of South
Bay Generation.
- May constrain exports from Mexico.
AJP 4/25/05
-5-
Alternatives for the Otay Mesa Power Purchase Transmission Project
Alternative
Advantages
2. Construct an Otay Mesa Mission #3 230 kV line instead
of the Otay Mesa - Old Town
230 kV line and connect the
Tijuana 230 kV line to Miguel
instead of Otay Mesa
3. Construct an Otay Mesa South Bay 230 kV line instead
of an Otay Mesa - Old Town
230 kV line, upgrade South
Bay Substation from 138 kV to
230 kV, and complete several
lower voltage upgrades
- Estimated higher cost due to the new
Same as the preferred alternative,
Otay Mesa-Miguel line section.
although, it may reduce potential
congestion north of Otay Mesa while - Congestion north of Miguel with high
CFE exports.
increasing potential congestion
- Higher load tripping requirement for
north of Miguel.
the Miguel corridor outage.
Same as the preferred alternative.
- Does not provide for the combined
deliverability of both OMGP and
South Bay generation.
- Estimated to have a higher cost due
to the 69 kV and 138 kV upgrades
required to provide the combined
deliverability of both OMGP and
South Bay generation.
- Would require a new 230 kV
switchyard and 230/138 kV banks at
South Bay, which is not currently
included in the long-term plan.
- Exports from Mexico may be
constrained.
- Could lead to the need to sectionalize
the 69 kV system and reduce
system reliability.
- Would require excessive generation
tripping for a Miguel corridor outage.
- Higher losses.
Lower cost.
- Does not provide for the full delivery
of the OMGP.
- Would not provide a 230 kV source to
downtown to allow for necessary
upgrades in that area.
- Would cause congestion at South Bay
and Miguel.
- Excessive generation tripping would
be required for the Miguel corridor
outage.
- Higher losses.
4. Construct the Otay Mesa Sycamore 230 kV line but not
the Miguel-Old Town line.
Disadvantages
The detailed engineering analysis for the Project as well as the ISO’s letter detailing its review of this
analysis is available upon request.
AJP 4/25/05
-6-
MANAGEMENT RECOMMENDATION
Based on a thorough analysis of the alternatives, both ISO Management and SDG&E have concluded that
the recommended transmission project is the preferred transmission solution. Therefore, ISO Management
recommends the following motion for Board consideration:
MOVED, that the Board of Governors,
1. Approves the Otay Mesa Power Purchase Agreement (OMPPA) Transmission Project to
allow the full dispatchability and deliverability of the Otay Mesa Generation Project. The
OMPPA was determined to be necessary to satisfy San Diego area resource adequacy
requirements by the California Public Utilities Commission and the San Diego Gas and
Electric Company.
2. Directs San Diego Gas and Electric Company to complete the permitting, design, and
construction of the Otay Mesa Power Purchase Agreement Transmission Project.
AJP 4/25/05
-7-
Download