Public Version MISO 2014 Spring Coordinated Seasonal Transmission Assessment February 3, 2014 Final Report 1 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release CONTENTS Contents .................................................................................................................................................. 2 1.0 Executive Summary .......................................................................................................................... 3 2.0 Introduction ....................................................................................................................................... 4 3.0 Study Criteria .................................................................................................................................... 7 4.0 Study Participants ............................................................................................................................. 9 5.0 Models and Input Data .................................................................................................................... 11 6.0 Study Methodology ......................................................................................................................... 15 6.1 Steady State AC Contingency Analysis ................................................................................................. 15 7.0 Steady-State Analysis Results......................................................................................................... 16 7.1 Summary ................................................................................................................................................ 16 8.0 IROL Limits .................................................................................................................................... 17 9.0 Nuclear Plant Interface requirements .............................................................................................. 18 10.0 Appendices .................................................................................................................................... 33 11.0 Abbreviations and acroynms ......................................................................................................... 34 2 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 1.0 EXECUTIVE SUMMARY The MISO Coordinated Seasonal Transmission Assessment (CSA) is a reliability assessment that tests the performance of MISO’s transmission network under anticipated and sometimes stressed operating horizon loading conditions. This study is coordinated with other studies performed by MISO members and other adjacent planning entities. This study includes the new MISO South region. The following Balancing Authorities came into the MISO footprint on December 19, 2013: Entergy transmission (EES, EAI), Cleco (CLEC), South Mississippi Electric Power Association (SMEPA), Louisiana Generating, LLC (LAGN), Lafayette Utilities System (LAFA), and Louisiana Energy and Power Authority (LEPA). There were fourteen total new members, resulting in the seven aforementioned new Local Balancing Authorities (LBA) in the MISO South Region. All of these LBAs were MISO transmission owning members when this study was performed. This Spring transmission system assessment was performed as a high wind light load transfer from MISO North and Central Regions to a shoulder peaking MISO South and Central Region, see Figure 5.0-1. The conditions created in this Spring assessment go beyond the planning criteria of most MISO Stakeholders. Portions of the MISO transmission footprint were stressed beyond normal base case assumptions. The constraints shown in this report only apply to the stressed conditions outlined in section 5. This assessment was produced in order to provide system operators with guidance as to possible acute system conditions that would warrant close observation to ensure system reliability, in the event that these extreme conditions were to occur. The 2014 Spring CSA performed the following transmission system assessments and listed the results below: Steady State AC Contingency Analysis was performed of the MISO system. • Category A screening • Category B contingency screening Summary of Results Steady State AC Contingency Analysis In general, the MISO transmission system performed well. There are some contingencies that may require operator action to avoid potential overloads or low voltages during the 2014 Spring conditions, depending on system conditions. These contingencies have been identified and tabulated, with the actions required to address these potential issues contained in Section 7 of this report. 3 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 2.0 INTRODUCTION MISO was approved by FERC as the nation’s first Regional Transmission Organization (RTO) in 2001. MISO launched its wholesale electricity market in 2005 and the Ancillary Services Market (ASM) in year 2009, providing both energy and operating reserves as well as regulation and response services that support reliable transmission system operation and equal access to high voltage transmission system in 14 U.S. states and the Canadian province of Manitoba. The geographic location of the MISO CSA study footprint is shown below in Figure 2.0-1. Figure 2.0-1: MISO CSA Study footprint The Bulk Power System (BPS) within the MISO CSA study footprint consists of an extensive 115 kV to 500 kV network. The 500 kV network in MISO is located in Arkansas, Louisiana, Minnesota, Mississippi, and Texas. The 345 kV networks are located in Arkansas, Illinois, Indiana, Iowa, Kentucky, Louisiana, Michigan, Missouri, Minnesota, North Dakota, South Dakota, Texas, and Wisconsin. The 230 kV networks are located in Arkansas, Illinois, Indiana, Iowa, Louisiana, Michigan, Mississippi, Missouri, Minnesota, North Dakota, South Dakota, Texas, and Wisconsin. MISO’s BPS lies in the following NERC regions: Midwest Reliability Organization (MRO), Reliability First Corporation (RFC) and SERC Reliability Corporation (SERC) regions. 4 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release MISO Regions MISO incorporated 15 new Balancing Authorities on June 1, 2013. These 15 new BAs consolidated into 7 new Local Balancing Authorities as of December 19, 2013; therefore, the MISO transmission system consists of three operating regions. The three operating regions are called MISO North Region, MISO Central Region, and MISO South Region; see Figure 2.0-2 below. North Central South Figure 2.0-2: MISO RC Operating Regions The North Region contains the MISO transmission systems in the states of Iowa, Minnesota, North Dakota, South Dakota and Wisconsin, consisting of the following control areas: Alliant Energy West [ALTW], Dairyland Power Cooperative [DPC], Great River Energy [GRE], MidAmerican Energy Company [MEC], Minnesota Power [MP], Montana-Dakotas Utilities [MDU], Muscatine Power and Water [MPW], Otter Tail Power [OTP], Southern Minnesota Municipal Power Agency [SMMPA] and Xcel Energy [XEL]. The North subregions all belong to the NERC approved MRO Region. The Central Region contains the MISO transmission systems in the states of Illinois, Indiana, Kentucky Michigan, Missouri, and (Eastern) Wisconsin consisting of the following control areas: Alliant Energy East [ALTE], Ameren Missouri [AMMO], Ameren Illinois [AMIL], Big Rivers Electric Cooperation [BREC], Columbia Water & Light Division [CWLD], City of Springfield (IL), Water Light & Power [CWLP], Duke Energy Indiana [DEI], Hoosier Energy [HE], Indianapolis Power and Light [IPL], International Transmission Company [ITCT], Madison Gas and Electric [MGE], Michigan Electric Transmission Company [METC], Northern Indiana Public Service Company [NIPSCO], Southern Illinois Power Cooperative [SIPC] and Southern Indiana Gas & Electric [SIGE], We Energies Corporation [WEC], Wisconsin Public Service [WPS], Wolverine Power [WPSC] and Upper Peninsula Power Company [UPPC]. The Central subregions belong to MRO, SERC or RFC regions of NERC. 5 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release The South Region contains the MISO transmission systems in the states of Arkansas, Louisiana, Mississippi, and Texas consisting of the following control areas: Batesville generation [BBA], Brazos Electric Cooperative [BRAZ], Cleco [CLEC], City of Benton AR [BUBA], City of Conway AR [CWAY], City of North Little Rock AR [NLR], City of Osceola AR [OMLP], City of Ruston, LA [DERS], City of West Memphis AR [WMU], Entergy Transmission [EES], Lafayette Utilities System [LAFA], Louisiana Energy and Power Authority [LEPA], Louisiana Generating LLC [LAGN], Plum Point Energy Associates LLC [PLUM], South Mississippi Electric Power Association [SMEPA], and Union Power Partners L.P. [PUPP]. The South subregions belong to the SERC Region of NERC. Please note that Entergy-Arkansas [EAI] is governed under the Entergy Company but is separate from Entergy transmission [EES] and contains Arkansas’s BA’s. Study Purpose The purpose of this Coordinated Seasonal Transmission Assessment (CSA) is to analyze and assess the MISO transmission system under extreme high wind light load conditions that could be expected for the 2014 Spring season. The coordination of this study across MISO’s area provides the benefit of reviewing the network over a much larger area than would normally be assessed by the individual participating transmission owners. This assessment focused on the performance of large scale category B steady-state contingency analysis during a high wind (90% of nameplate) scenario. Seasonal outages were also applied. The contingency levels included in this assessment are, in many cases, beyond those typically considered and are beyond regional planning criteria. These events have been evaluated in order to provide system operators with guidance as to possible but unlikely system conditions that would warrant close observation to ensure system security. This CSA report does not attempt to determine Available Transfer Capability (ATC), Available Flowgate Capacity (AFC), the availability of transmission service, or provide a forecast of anticipated dispatch patterns for the 2014 Spring season. There were no Capacity Benefit Margins (CBM) or Transmission Reliability Margins (TRMs) included in this assessment. Also, the assessments documented in this report are not intended to fulfil all of the study requirements for Transmission Planners or Planning Coordinators listed in NERC Standards TPL-001 through TPL-004. The results from this year’s assessment do not override the currently posted operating guide limits and values. 6 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 3.0 STUDY CRITERIA The NERC Planning Standards TPL-001, TPL-002, TPL-003 and TPL-004 are the applicable study criteria for this assessment. This assessment evaluates NERC contingency categories A and B. The MISO members’ thermal and voltage thresholds are used to flag thermal and voltage violations and voltage deviation exceptions on their respective systems. Monitored element files for system intact and contingency conditions are included in Appendix A. MISO members’ system elements (> 69 kV) were monitored. Precontingency equipment loadings above 100 percent of normal rating (Rate A) were flagged. Post-contingency equipment loadings above 100 percent of emergency rating (Rate B) were also flagged. Equipment loadings above 125 percent of emergency rating were identified for cascade screening review. All of the MISO members’ systems were studied, except one small radial system. Below is a list of MISO members shown in Table 3.0-1. The table also includes the operating Region and their associated control areas or zones in the power flow model. Note some members are within other members’ control areas so the control area that they belong to is shown as “in xxx”. Table 3.0-1: MISO CSA Systems Studied Region Central Central Area 206 Abbrev OVEC System Ohio Valley Electric Corporation 207 HE Hoosier Energy Rural Electric Cooperative Central 208 DEI Duke Energy Indiana Central 210 SIGE Vectren (Southern Indiana Gas & Electric Co) Central 216 IPL Indianapolis Power & Light Company Central 217 NIPS Northern Indiana Public Service Company Central in 217 IMPA* Indiana Municipal Power Agency Central in 217 WVPA* Wabash Valley Power Association Central 218 METC Michigan Electric Transmission Co. Central in 218 MPPA* Michigan Public Power Agency Central in 218 MSCPA* Michigan South Central Power Agency Central in 218 WPSC* Wolverine Power Supply Cooperative Central 219 ITC International Transmission Company Central 295 WEC Wisconsin Electric Power Company (ATC) Central 314 BREC Big Rivers Electric Corporation Central 333 CWLD Columbia, MO Water and Light Department Central 356 AMMO Ameren Missouri Central 357 AMIL Ameren Illinois Central 360 CWLP City of Springfield (IL) Water Light & Power Central 361 SIPC Southern Illinois Power Cooperative Central 694 ALTE Alliant Energy East (ATC) Central 696 WPS Wisconsin Public Service Corporation (ATC) Central 697 MGE Madison Gas & Electric Company (ATC) Central 698 UPPC Upper Peninsula Power Company (ATC) 7 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Region Area Abbrev South 327 EAI System Entergy Arkansas South in 327 BUBA* City of Benton, Arkansas South in 327 CWAY* City of Conway, Arkansas South in 327 NLR* City of North Little Rock, Arkansas South in 327 OMLP* City of Osceola, Arkansas South in 327 PLUM* Plum Point Energy Associates, LLC South in 327 PUPP* Union Power Partners South in 327 WMU* City of West Memphis, Arkansas South 332 LAGN Louisiana Generating LLC South 349 SMEPA South Mississippi Electric Power Association South in 349 BBA* Batesville Generation South 351 EES Entergy Louisiana South in 351 BRAZ* Brazos Electric Cooperative South in 351 DERS* City of Ruston, Louisiana South 502 CLEC Cleco South 503 LAFA Lafayette Utilities System South 504 LEPA Louisiana Energy and Power Authority North 600 XEL Xcel Energy North in 600 NWEC* Northwestern Wisconsin Electric North 608 MP Minnesota Power & Light North 613 SMMPA Southern Minnesota Municipal Power Agency North 615 GRE Great River Energy North 620 OTP Otter Tail Power Company North in 620 MPC* Minnkota Power Cooperative North 627 ALTW ITC Midwest North 633 MPW Muscatine Power & Water North 635 MEC MidAmerican Energy Company North in 635 CFU* Cedar Falls Utility North 652 WAPA Western Area Power Administration North 661 MDU Montana-Dakota Utilities Company North 667 MH Manitoba Hydro North 680 DPC Dairyland Power Cooperative 8 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 4.0 STUDY PARTICIPANTS Table 4.0-1 below shows the individuals who actively participated in this study. Table 4.0-1: MISO's 2014 Spring CSA Participation List1 1 First Name Last Name Company Name First Name Last Name Company Name Tony Gott AECI* Tim Aliff MISO Evan Shuvo Ameren David Duebner MISO Eric Fleming ATC Scott Goodwin MISO Brad Larson ATC BeiBei Li MISO Kerry Marinan ATC Josh Netherton MISO Chris Bradley BREC Tony Rowan MISO James Simms CLEC Kris Ruud MISO Chris Thibodeaux CLEC Raja Thappetaobula MISO Adam Schuttler CWLD Andy Witmeier MISO Chris Daniels CWLP Ruth Pallapati MP Steve Rose CWLP Peter Schommer MP Phil Briggs DEI Will Lovelace MPC Veronda Johns DEI Pete Schimpke MPPA John Jozefowski DEI Lewis Ross MPW Steve Porter DPC John Stolley MPW Maryclaire Peterson EES Bob Vargus MPW Jared Shaw EES Amir Quadri NIPS Richa Singhal GRE Jake Heck OTP Todd Taft HE Luis Leon OTP Robert Grubb IPL Ryan Abshier SIGE Dave Osterkamp ITCM Jeff Jones SIPC John Andree ITCT Damion Cuevas SMEPA Joshua Hurst ITCT Yu-Loong Liew SMEPA Jeffrey Stewart LAFA Pat Egan SMMPA Wayne Messina LAGN Yassar Bahbaz SPP* Jamal Ahmed LBWL Jason Smith SPP* Kevin Bihm LEPA Nate Schweighart TVA* Shawn Heilman MDU Chris Bultsma WAPA Dan Custer MEC Tom King WPSCI Dan Rathe MEC Dan Wilkinson WPSCI Kris Long MH Michelle Wood XEL Gayan Wijeweera MH Khalid Yousif XEL * denotes non-MISO member participants 9 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release In addition to the aforementioned list of participants above, the final 2014 Spring CSA report will also be distributed to the following entities in accordance with FAC-014-2 and standards. Table 4.0-2: Final Report Distribution List Adjacent Planning Authorities Transmission Planners AECI MH Ameren LBWL ATC Ontario IESO ATC MEC E.ON U.S. PJM Basin Electric METC EEI Sask Power BREC MH EKPC SOCO SPP Cedar Falls MP CIPC MPC TVA CLEC MPW Corn Belt NIPS CWLD OTP Reliability Coordinators CWLP OVEC MISO DEI RPU DPC SIGE EEI SIPC Entergy SMEPA GTC MAPP Transmission Operators Ameren MEC GRE SMMPA ATC METC HE WAPA BREC MH IPL WPSCI CLEC Corn Belt MP ITCM XEL MPC CWLD MPW CWLP NIPS DEI OTP CIPC DPC OVEC Corn Belt MPC EEI RPU DPC OVEC EES SIGE MH RPU GRE SIPC XEL WAPA HE SMEPA ITCT Transmission Service Provider MISO IPL SOCO ITCM WAPA Ontario IESO SOCO ITCT WPSCI PJM SPP LBWL XEL Sask Power TVA MDU Adjacent Reliability Coordinators WECC 10 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 5.0 MODELS AND INPUT DATA The power flow model used for the 2014 Spring assessment was based on the ERAG/MMWG 2012 series model. The MISO control area was built from MOD with the MISO external areas from MMWG 2013 series. The MISO footprint blended two load levels across their operating regions, see Figure 5.0-1 below. o o Spring Light Load: MISO North Region + Michigan, AMIL, CWLP, ATC, NIPS. Spring Peak Load: MISO South Region + AMMO, SIPC, CWLD, SIGE, IPL, DEI, HE, BREC. Light Load Figure 5.0-1: 2014 Spring CSA * Light Load vs. Spring Peak All MISO wind generators were dispatched at 90% of the nameplate full output; a reflection of the 90% MISO wide average capacity credit wind units receive. PJM N. Illinois wind was also dispatched to 90% and that generation was transferred to PJM Ohio. This case was further updated with the most recent transmission system status information and projected capacity backed transfers across the entire eastern interconnect. The MISO data was submitted by MISO stakeholders to MISO’s Model-on-Demand (MOD) tool. The case was then reviewed by CSA study participants for accuracy of the topology, load, generation, and interchange values. The dispatch used was MISO’s Security Constrained Economic Dispatch (SCED) which was achieved by re-dispatch of MISO generation while maintaining MISO’s interchange. The model was developed in accordance with the Operations Reliability Coordination Agreement (ORCA) that was reached between MISO And all Joint Parties (JPs). The projected non-coincident 2014 Spring demand for MISO’s footprint in the power flow model used for this transmission assessment is 92,822 MW. This does include the projected Spring demand of the fifteen new LBAs in the MISO South region; since they have joined MISO starting on December 19, 2013. Power flow model control areas of MISO member utilities include loads of other utilities that are not MISO 11 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release members. Therefore, the demand in the power flow model is not directly comparable to the resource assessment demand forecast for MISO member utilities. The total amount of generation available to serve MISO load from internally and externally designated capacity resources during the 2014 Spring period is 148,516 MW. The net scheduled interchange for MISO in the power flow model is 4,213.9 MW, which indicates a net export of power by the MISO member utilities in the 2014 Spring season. The following seasonal outages were included based on an April 15, 2014 target date in addition to a 30 day duration period. Table 5.0-1: Seasonal Outages Operating Region CA Type Planned Start Planned End Station Name Equip Type kV Pmax Central ALTE P 1/6/2014 06/06/14 Berlin--Omro Industrial Park 69 kV line LN 69 n/a Central ALTE P 3/31/2014 05/30/14 Paddock--Shirland Ave 69 kV line LN 69 n/a Central ALTE P 4/14/2014 05/30/14 Hilltop--Buckhorn Tam 69 kV line LN 69 n/a Central ALTE P 03/19/14 5/9/2014 Boscobel Cap Bank C-5_4 SS Central ALTE P 2014-04-11 2014-06-04 UN 22 260 Central AMIL P 2014-03-03 2014-05-09 MARSEILLE; T138.00 4MARSEILLES 138.00 1 LN 138 n/a Central AMIL E 2011-12-20 2014-12-31 1MERDSA 3 20.000 3 UN 19.2 229 COL G1 22.000 1 n/a Central AMIL P 2012-09-25 2015-10-01 1MERDSA 4 20.000 4 UN 19.2 200 Central AMMO P 2014-03-17 2014-05-17 7WILDWD TP 345.00 7LABADIE3 345.00 1 LN 345 n/a Central AMMO P 2014-03-17 2014-05-17 7MASON 2 345.00 7LABADIE1 345.00 1 LN 345 n/a Central AMMO P 2014-03-17 2014-05-17 7WILDWD TP 345.00 7MASON 3 345.00 1 LN 345 n/a Central AMMO P 01/13/14 05/31/14 7PALM TAP 345.00 SUB T 3 345.00 LN 345 n/a Central AMMO P 2014-04-05 2014-06-02 1LAB G2 20.000 2 UN 20 630 Central AMMO P 2014-01-25 2014-04-28 1SIOUX 2 18.000 H & L UN 18 535 Central AMMO P 2014-04-01 2014-04-30 7PALMYRA 345.00 5PALMYRA 161.00 1 XF 345 n/a Central AMMO P 2014-03-17 2014-05-17 7WILDWD XF 345 n/a Central BREC P 2014-04-05 2014-05-26 COLEMAN3 18.000 3 UN 161 155 Central CWLP P 2014-03-22 2014-05-17 1DALMAN 33 19.000 3 UN 138 199 Central DEI P 2014-01-02 2014-05-31 Central DEI P 2014-03-07 2014-05-19 Central DEI P 2014-04-11 2014-05-12 Central DEI P 2014-04-11 Central DEI P 2014-04-11 Central HE P 2014-03-01 345.00 4WILDWD 1 138.00 1 08KOK HP 230.00 08TIPTN LN 230 n/a UN 24 635 08EDWST1 18.000 ST UN 18 331 2014-05-12 ED_WARDS_CT1_18_not_in_idc UN 18 232 2014-05-12 ED_WARDS_CT2_18_not_in_idc UN 18 232 2014-04-27 07MEROM5 345.00 2 UN 345 600 07MEROM5 345.00 1 UN 345 600 UN 22 438 LN 220 n/a 08GIB4 230.00 1 24.000 42 Central HE P 2014-04-12 2014-05-11 Central IPL P 2014-03-08 2014-04-06 Central ITCT P 2014-01-20 2014-04-17 Central ITCT P 2014-02-14 2014-05-06 19MON2 26.000 2 UN 26 800 Central ITCT P 2014-02-28 2014-05-23 19SC7 18.000 7 UN 18 460 Central METC F 2013-10-07 2014-12-31 18KARN4 26.000 4 UN 26 638 Central METC P 2013-11-09 2014-07-19 18LUDN12 20.000 2 UN 20 340 Central METC P 2014-04-07 2014-05-05 18LUDN12 20.000 1 UN 20 340 STOUT 7 22.000 7 SCOTT_TS 220.00 19B3N PS 220.00 1 2 The outage date was pushed out to September 2014. This unit was still offline in the model. 12 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Operating Region CA Type Planned Start Planned End Station Name Equip Type kV Central METC P 2014-03-15 2014-05-14 18KARN1A 16.000 A UN 16 260 Central METC P 2014-04-12 2014-05-10 18ZELND1 18.000 1 UN 18 181.7 Central MGE P 2014-04-12 2014-06-03 UN 22 125 Central MGE P 2013-04-22 2014-04-22 CARDINAL 345.00 CARDINAL 138.00 1 XF 345 n/a Central NIP F 06/01/14 08/31/14 Babcock--Tower Road LN 138 n/a Central NIP F 06/01/14 08/31/14 Babcock--Tower Road LN 345 n/a Central NIP F 06/01/14 08/31/14 St. John--Schaffer LN 345 n/a Central NIP P 2014-03-22 2014-05-12 17SCHAFER-1824.000 18 UN 345 361 Central NIP P 2014-04-05 2014-05-26 17BAILLY-8 22.000 8 UN 138 320 Central NIP P 2014-03-15 2014-05-05 17BAILLY-7 22.000 7 UN 138 160 Central SIPC P 2014-03-27 2014-05-25 1MRNG4 UN 20 173 Central UPPC P 9/20/2014 6/30/2014 Evergreen Tap--Pine River 69 kV line LN 69 n/a Central UPPC P 9/20/2014 6/30/2014 Straits--Pine River 69 kV line LN 69 n/a Central WEC P 2013-09-20 2014-06-30 BREVRT 138.00 MACKINAC N 138.00 1 LN 138 n/a Central WEC P 4/7/2014 4/25/2014 Bluemound--West Junction Tap 138 kV line LN 138 n/a Central WEC P 4/7/2014 4/25/2014 Everett--28th St 138 kV line LN 138 n/a Central WEC P 2014-03-08 2014-05-19 Central WEC P 2014-03-29 2014-04-28 Central WEC P 2014-04-10 2014-05-05 POWSTG20 18.000 1 Central WEC P 2014-04-10 2014-05-05 Central WEC P 2014-04-10 2014-05-05 Central WEC F 2012-11-06 2014-12-01 PRS GT1 Central WEC F 2012-11-06 2014-12-01 Central WEC P 2014-04-05 2014-05-05 Central WEC P 2014-04-05 2014-05-05 COL G1 22.000 1 20.000 4 Pmax OK C G8 18.000 8 UN 17.2 291 OK C G7 18.000 H UN 17.2 286.4 UN 18 273.7 POWCTG21 18.000 1 UN 18 184 POWCTG22 18.000 1 UN 18 181 13.800 1 UN 13.8 100 PRS GT4 13.800 4 UN 13.8 100 PRS GT4 13.800 4 UN 13.8 100 PRS GT7 13.800 7 UN 13.8 100 Central WEC P 4/7/2014 4/25/2014 Elm Road unit No. 1 UN 25 1272 Central WPS P 2/28/2014 4/28/2018 Pulliam WPS-East Bus time 138 kV line LN 69 n/a Central WPS P 2014-04-11 2014-06-03 22 180 COL G1 22.000 1 UN PUL G8 16.000 8 Central WPS P 2014-02-28 2014-04-28 UN 16 133 North ALTW P 2014-02-17 2014-05-01 COGGON 7 115.00 DUNDEE 7 115.00 1 LN 115 n/a North DPC F 2013-07-19 2014-06-01 ALMA5 5G 14.400 5 UN 161 80 North DPC F 2013-07-19 2014-06-01 ALMA5 4G 13.800 4 UN 161 56 North GRE P 2013-10-31 2014-10-31 GRE-PL VLLY5161.00 AUSTIN 5 161.00 1 LN 161 n/a North GRE P 2014-04-05 2014-05-02 GRE-COAL 41G22.000 1 UN 230 582 North MDU P 2013-06-24 2014-06-27 HESKETT7 115.00 MANDANW7 115.00 1 LN 115 n/a North MEC P 2014-03-21 2014-05-05 NEAL 3G 22.000 3 UN 22 144 North MEC P 2014-04-12 2014-06-02 CBLUF4G North MP P 2014-03-24 2014-04-25 North MP P 2014-04-05 North WAPA P 2014-04-01 North WAPA P North WAPA North North UN 345 77.47 FLDWDTP7 115.00 BLCKBRY7 115.00 1 26.000 4 LN 115 n/a 2014-05-05 BOSWE43G 20.900 3 UN 20.9 362 2014-05-15 GARRISN4 230.00 LELANDO4 230.00 1 LN 230 n/a 04/14/14 05/21/14 FB-WT 230KV LINE, LN 230 n/a P 04/14/14 05/21/14 HU-WT NO.2 230KV LINE, LN 230 n/a WAPA P 2014-03-29 2014-05-25 ANTEL31G 24.000 1 UN 24 477 WAPA P 2013-10-09 2014-12-31 CRESTON5 161.00 CRESTON8 69.000 1 XF 161 n/a 13 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Operating Region CA Type Planned Start Planned End Station Name Equip Type kV Pmax North WAPA P 04/14/14 05/21/14 WATERTN3 345.00 STARBUS245 1.0000 1, XF 345/230 n/a North WAPA P 04/14/14 05/21/14 STARBUS249 230.00 WATERTN4 1.0000 1, XF 345/230 n/a North XEL P 2013-11-01 2014-11-01 FARIBALT P 7115.00 GRE-LKMARN 7115.00 1 LN 115 n/a North XEL P 2014-01-15 2014-10-15 MINVALY7 115.00 LYON CO7 115.00 1 LN 115 n/a North XEL P 2014-03-10 2014-04-04 PR ISLD3 345.00 BLUE LK3 345.00 1 LN 345 n/a North XEL P 2014-03-22 2014-04-27 KING 31G 20.000 1 UN 20 555 North XEL P 2014-02-22 2014-04-22 SHERC33G 26.000 3 UN 26 537 North XEL P 2014-03-29 2014-04-28 RIVRSIDEG9 718.000 9 UN 18 255 North XEL P 2014-03-29 2014-04-28 RIVRSIDG10 718.000 10 UN 18 255 North XEL F 2011-02-21 2015-12-31 FEN 83G 13.800 3 UN 13.8 100 South CLEC P 2014-02-22 2014-04-28 G2RODEMR 22.000 1 UN 22 434 South EAI P 2014-03-03 2014-07-11 LN 161 n/a South EAI P 2014-03-09 2014-04-07 1ANO U2 22.000 1 UN 22 1031 South EAI P 2014-03-15 2014-04-19 1BLUF U2 26.000 1 UN 26 844 South EAI P 2014-04-12 2014-05-17 1CATH U4 22.000 1 UN 22 547 South EAI P 2012-12-01 2017-01-01 1RITC U2 18.000 1 UN 18 544 South EAI P 2012-12-01 2017-01-01 1RITC U2 18.000 1 UN 22 356 South EEI F 2010-09-01 2014-05-01 JOPPA G3 13.800 3 UN 161 62 South EEI F 2013-02-20 2014-04-30 JOPPA G2 13.800 2 UN 161 62 South EEI F 2013-02-21 2014-04-30 South EES P 2014-03-14 2014-04-18 4GONZL 138.00 4SORXFM South EES P 2014-03-03 2014-05-09 4LEWIS 138.00 4EGYPT South EES U 2013-04-01 2015-09-30 South EES P 2014-03-15 2014-05-03 1ANDRUS U1 24.000 1 South EES P 2013-08-31 2014-08-31 1G5WGLEN 20.000 1 South EES P 2014-02-22 2014-04-19 South EES P 2013-08-31 2014-08-31 South EES P 2014-02-15 2014-05-10 South EES P 2012-12-01 South EES P 2014-03-15 South EES P South EES South EES 5CALCR 161.00 5MELBRN 161.00 1 JOPPA G1 13.800 1 UN 161 62 LN 138 n/a LN 138 n/a LN 115 n/a UN 24 761 UN 20 550 1GYP U3 24.000 1 UN 24 545 1G3WGLEN 20.000 1 UN 20 537 1G4NELSON 24.000 1 UN 24 500 2017-01-01 1G10LAST 13.800 1 UN 13 260 2014-05-17 1MICH U2 18.000 1 UN 18 240 2013-08-31 2014-08-31 1G3WGLEN 20.000 1 UN 18 160 F 2013-05-13 2020-08-05 1G3NELSON 18.000 1 UN 18 153 P 2014-04-05 2014-05-17 1G3NELSON 18.000 1 UN 18 153 138.00 1 138.00 1 3STERLING% 115.00 3OKRIDG 4SORXFM 138.00 3SORNTO 115.00 1 South EES P 2014-03-14 2014-04-18 XF 138 n/a South LAGN P 2014-03-01 2014-04-15 1G1INTHB 18.000 1 115.00 1 UN 500 330 South LAGN F 2013-04-04 2015-06-01 1BC1 U4 13.800 1 UN 230 115 Tier-1 CE P 2014-04-19 2014-05-18 KINCAID ;2U20.000 2 UN 20 579 14 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 6.0 STUDY METHODOLOGY The following power system analysis software tools were utilized: Siemens PTI’s PSS/e (ver33). 6.1 Steady State AC Contingency Analysis Siemens PTI’s PSS/e ver33 program was used to analyze the steady-state voltage levels and thermal loadings of the MISO footprint under base case transfers for system intact and contingency conditions. MISO’s three operating regions, greater than 60 kV, were analyzed for category B contingencies. Also, the entire MISO tier1 footprint was analyzed for category B contingencies. Single generator outages by control area were examined. Some neighboring system contingencies were also analyzed, if included by members or non-member participants. The PSS/e solutions options used in the thermal and voltage analysis is shown below in Table 6.1-1. The analyses were conducted enabling transformer taps and switched shunts. These settings were chosen as they represent the post-contingency steady state condition, which is assumed to be at a time when all operator actions have been deployed in order to maintain/re-establish system security levels. The MUST’s default dispatch option (governor control dispatch) was used to specify that all MISO and adjacent control area generators would respond to a generator outage, not just the system swing bus. Table 6.1-1: PSS/e Options used for ACCC Analysis PSS/e AC Load Flow Solution Options Tap Adjustments Area Interchange Control Stepping Disabled Mvar Limits AC LF Method Apply immediately Full Newton Non Divergent LF Solution Options Only If Normal Diverged Phase Shift Adjustment General Solution Options Maximum Load Flow Iterations 20 MW/Mvar tolerance Reactive Adj. De-acceleration Factor 1 0.9 Low Voltage Break Point Max Iteration to freeze adjustment 0.7 99 15 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 7.0 STEADY-STATE ANALYSIS RESULTS 7.1 Summary In general, the MISO transmission system is projected to perform well. There are a number of contingencies that may require operator action to avoid potential overloads or low voltages during the 2014 Spring season. There were 17 category A high voltage violations and 30 category B (thermal/low voltage) contingency violations found in MISO’s BPS (>100 kV). Operational procedures were identified for all category A and B thermal and voltage violations. These contingencies have been tabulated with the actions required to address these potential issues. The steady-state AC contingency analysis results may be seen in Appendix B. HE's Ratts Generating Station in Pike County Indiana 16 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 8.0 IROL LIMITS Interconnection Reliability Operating Limits (IROL) are system operating limits which, if violated, could lead to instability, uncontrolled separation, or cascading outages that adversely impact the reliability of the Bulk Power System. All NERC category B contingencies from the MUST AC analysis that caused facility loading of more than 125 percent of the emergency rating were flagged to determine its potential to become an IROL. The assumption is that cascading or collapse would occur when the monitored element loads to 125 percent or more and trips. All of the aforementioned overloaded elements were screened along with its associated contingency and independently re-analyzed to find any subsequent overloaded branches (line loading > 100 percent of emergency rating). Any branches over 100 percent were manually opened and the process was continued until there were either no overloaded branches or the system collapsed. When the system settles with no overloads, you add up the load that was shed. If the load shed is less than 1,000 MW then there is no IROL event. There were 6 facilities that were evaluated for IROL candidacy in this analysis accompanied with an operating procedure as mitigation. There were no new IROLs identified in this assessment. Xcel's Chippewa Falls Hydro in Wisconsin 17 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 9.0 NUCLEAR PLANT INTERFACE REQUIREMENTS There are nine nuclear plants in the MISO market currently. Each nuclear plant has a set of Nuclear Plant Interface Requirements (NPIR) that need to be met. These NPIRs are all outlined in the Nuclear Plant Operating Agreements (NPOA) that each nuclear plant has reached between the Transmission Planner (TP), the Planning Authority (PA) and the Generator Operator (GOP). It is outlined in each of the NPOAs that the TP will perform the assessment to assure the NPIRs are met. MISO will then provide those results in the CSA report. See Table 9.0-1 for the list of nuclear plants within the MISO market. There are five additional nuclear units in the MISO South region but because those units are not part of the MISO market they are not part of this section. Table 9.0-1: MISO Nuclear Plants Operating Region Plant Name Capacity ( MW) Central Callaway 1,369 Central Clinton 1,264 Central Point Beach 1,162 Central Enrico Fermi 1,138 Central Palisades 955 Central Kewaunee 0 North Prairie Island 1,318 North Monticello 718 North Duane Arnold 630 South Arkansas Nuclear One 2,010 South Grand Gulf 1,544 South Waterford 1,214 South Riverbend 1,080 The results below are from our Transmission Owning Stakeholders who have a nuclear unit within their control area. The timeline of their assessments do not always match that of which MISO requests this information; therefore, in some instances their most recent assessment results were provided. On top of the Transmission Planner’s assessment MISO also screened each nuclear bus for NPIR violations in the 2014 Spring CSA. The MISO nuclear units that are currently in the MISO market can be geographically seen below in Figure 9.0-1. 18 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Figure 9.0-1: Geographic Location of MISO Nuclear Plants 19 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Callaway Description: The Callaway Nuclear Plant is comprised of one 1,373 MVA unit with a maximum auxiliary station service load of 75 MW and 35 Mvar. The step-up transformer is comprised of three 456.3 MVA, 25 kV/345 kV units for a total capability of 1369.5 MVA. The Callaway Nuclear Plant Substation is connected to the Eastern Interconnection at its associated switchyard by four 345 kV circuits. The 345 kV bus is configured with a break and a half scheme. Ameren owns and operates in this plant. 2013-14 Winter Analysis for Nuc-001-2 R9.2.3: Ameren Operations Planning tested the effects of various system configurations on the Callaway 345 kV bus voltage. The 2014 Spring SERC NTSG model was used as the basis for this study work, with the detailed Ameren representation inserted into the model. The load level modeled in the Ameren system was set to the projected 1-in-10 level for 2014 Spring. The LOCA load modeled in these cases was 75 + j35 MVA. Power was imported to the Ameren control area from the Midwest ISO cloud to make up for the power loss from the outage of the Callaway and Labadie units. The following table Summarizes the results at the Callaway bus, under none of the configurations tested did the Callaway bus voltage fall below the allowed limit. Table 9.0-2: Callaway Bus Summary Configuration 0. Base Case 1a. Callaway Offline Callaway 345 kV Bus Limit Simulation 358.8 358.8 332.9 353.7 1b. Callaway Offline & NERC Category B Event 329.8 342 1c. Callaway Offline & only NERC Category B Event 329.8 351.7 1d. Callaway Offline & only NERC Category B Event 329.8 352 1e. Callaway Offline & only NERC Category B Event 329.8 352 2a. Callaway Offline & NERC Category B Event 329.8 354.3 2b. Config. #2a & NERC Category B Event 329.8 354.6 20 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Clinton Description: Clinton Power Station is comprised of one 1264.777 MVA unit with an auxiliary station service load of 43 MW and 16 Mvar. The step-up transformer is a 1,425 MVA, 22 kV/345 kV unit. The Clinton substation is connected to the Eastern Interconnection by three 345 kV circuits and one 138 kV circuit. The 345 kV bus is a ring bus configuration and the 138 kV bus is a straight bus configuration. The 345 kV bus and 138 kV bus are not connected by transformation at the Clinton switchyard. Exelon owns and operates this plant. 2013-14 Winter Analysis for Nuc-001-2 R9.2.3: Ameren tested the effects of various system configurations on the Clinton 345 kV and 138 kV bus voltages. The 2014 Spring SERC NTSG model was used as the basis for this study work, with the detailed Ameren control areas representation inserted into the model. The load level modeled in the Ameren system was set to the projected 1-in-10 level for the 2014 Spring season. The LOCA load modeled in these cases was 44 + j27 MVA. Power was imported to the Ameren control area from the MISO cloud to make up for the power loss from the outage of the Clinton and Kincaid units. The following table Summarizes the results at the Clinton bus, under none of the configurations tested did the Clinton bus voltages fall below the allowed limit. Table 9.0-3: Clinton Bus Summary Configuration 0. Base Case 1a. Clinton Offline 1b. Clinton Offline & NERC Category B Event 1c. Clinton Offline & NERC Category B Event 1d. Clinton Offline & NERC Category B Event 1e. Clinton Offline & NERC Category B Event 1f. Clinton Offline & NERC Category B Event 2a. Clinton Offline & NERC Category B Event Limit 327.75 327.75 327.75 327.75 327.75 327.75 327.75 327.75 Clinton Bus Voltages 345 kV 138 kV Simulation Limit Simulation 358.8 129.72 139.7 351.6 129.72 138.2 348.7 129.72 137 351.4 129.72 138.3 343.8 129.72 135.5 351.4 129.72 134.9 351.7 129.72 139.5 352.4 129.72 138.4 21 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Point Beach Description: The Point Beach Nuclear Plant is located near Two Rivers, WI on the shore of Lake Michigan. This plant has a real gross output of 1,189 MW and is connected to the 345 kV transmission system. The Point Beach Nuclear Plant is owned and operated by NextEra Energy Resources. Analysis: MISO’s incorporated the Point Beach NPIRs into its bi-annual assessments. The analysis was performed as part of the MISO Coordinated Seasonal Transmission Assessment (CSA). Results: The Nuclear Plant Interface Requirements (NPIRs) for Point Beach were incorporated into the MISO CSA study. The results showed that the NPIRs met the required Point Beach performance criteria. 22 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Enrico Fermi Description: Enrico Fermi II Nuclear Plant (Fermi) is comprised of one 1,350 MVA unit connected to the 345 kV transmission grid in South East Michigan. The Fermi nuclear plant has two independent switchyards the 345 kV yard in which the unit is connected has two 345 kV lines. The 120 kV switchyard contains the interconnections for 3 Combustion Turbine Generators which two are normally used for peaking power and one is reserved for plant emergency use. Station service load is split between the two switchyards. The 345 kV yard has a normal loading of 47 MW and 28 Mvar with an additional accident loading adder of 2.69 MW and 11.682 Mvar. The 120 kV yard has a normal loading of 26 MW and 17 Mvar with an additional accident loader of 2.59 MW and 12.095 Mvar. The plant is owned and operated by DTE Electric Company (DECO). Analysis: As required by the Nuclear Plant Operating Agreement between ITC, DECO, Fermi II and MISO; ITC performs an annual grid analysis to insure that the system can meet the above requirements. In addition to the detailed annual grid analysis all planning studies, including but not limited to load interconnections, generator interconnections, seasonal system studies, and system reliability projects are required to use the above limits and values to insure that the transmission system can be operated to meet them. Results: Past studies have indicated potential issues meeting the voltage drop limits and steady state voltage limits in certain shutdown plus contingency scenarios. Long term solutions to these potential issues are currently being developed in coordination with DECO, MISO and the Fermi II Nuclear Power Plant staff and to be proposed in the MISO MTEP process. 23 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Palisades Description: Palisades Nuclear Generating Plant is comprised of one 955 MVA unit connected to the 345 kV transmission grid in southwest Michigan. The Palisades Nuclear Generating Plant has one switch yard with six networked 345 kV transmission lines arranged in a breaker and a half configuration. In addition there is one 345 kV line that runs to the Covert Generating Plant. The plants auxiliary load of 42 MW and 31 Mvar is fed by two independent transformers. Safe-Guard transformer is connected to the “F” bus of the switchyard while Start-up transformer is connected to the “R” bus of the switchyard. Entergy Nuclear Palisades (ENP) is the owner and operator of the plant. Analysis: As required by the NPOA between METC, ENP, and MISO, METC performs an annual grid analysis to insure that the system can meet the above requirements. In addition to the detailed annual grid analysis all planning studies, including but not limited to load interconnections, generator interconnections, seasonal system studies, and system reliability projects are required to use the above limits and values to insure that the transmission system can be operated to meet them. Results: METC’s annual grid study, as well as the other studies in the area, has not indicated any issues with meeting the above NPIRs. However; METC, MISO and ENP are currently engaged in negotiations surrounding proposed changes to the High and Low voltage limits. It is unlikely this will affect the upcoming 2013-14 Winter season. 24 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Kewaunee Description: The Kewaunee Nuclear plant retired on May 7, 2013. NPIRs: Real-time and post-contingent voltage range required by the plant is 128.0 kV to 148.0 kV (Note: ATC controls the real-time voltage on the Kewaunee 138 kV buses to the range of 131.1 kV to 144.9 kV, corresponding to 0.95 – 1.05 pu, since this is more restrictive than the plant’s criteria.) Analysis: MISO’s incorporated the Kewaunee NPIRs into its bi-annual assessments. The analysis was performed as part of the MISO Coordinated Seasonal Transmission Assessment (CSA). Results: The Nuclear Plant Interface Requirements (NPIRs) for Kewaunee were incorporated into the MISO CSA study. The results showed that the NPIRs met the required Kewaunee performance criteria. 25 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Arkansas Nuclear One Description: The Arkansas Nuclear One (ANO) Plant is comprised of two units, unit No. 1 is rated for 1,002.6 MVA and unit No. 2 is rated for 1,133.33 MVA. The ANO combined maximum auxiliary station service load is as stated below for each applicable bus voltage level. The step-up transformer bank for each generating unit is comprised of three single phase transformers. The unit No. 1 three phase transformer bank is rated for 945 MVA and the unit No. 2 three phase transformer bank is rated for 1,448 MVA (FOA). In addition to ANO units No. 1 and No. 2 the ANO 500/161/22 kV auto transformer and the ANO 500 kV bus is connected to Entergy’s Mabelvale, Pleasant Hill & Oklahoma Gas & Electric’s (OG&Es) Fort Smith 500 kV switchyard. The ANO 161 kV bus is connected to Pleasant Hill, Russellville East 161 kV switchyards and the ANO ST No. 3 is an offsite source. Analysis: MISO incorporated the Entergy’s South Nuclear Plants NPIRs into its bi-annual assessments. The analysis was performed as part of the MISO Coordinated Seasonal Transmission Assessment (CSA). Results: The Nuclear Plant Interface Requirements (NPIRs) for Entergy’s South Nuclear Plants were incorporated into the MISO CSA study. The results showed that the NPIRs met the required Entergy’s South Nuclear Plants performance criteria. 26 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Grand Gulf Description: The Grand Gulf plant substation is connected to the Transmission System by 2 500 kV transmission circuits. The 500 kV buses where the transmission lines connecting remote substations to the Grand Gulf 500 kV Switchyard are two-bus-two-breaker schemes. The 115 kV bus configuration where the transmission line connecting the remote substation to the Grand Gulf 115 kV Substation is a remote breaker radial line with no circuit breakers located in the Grand Gulf 115 kV Substation. The Grand Gulf generator step-up transformer and service transformer ST11 are each connected to the Grand Gulf 500 kV Switchyard by a breaker-and-onehalf scheme, located in the same bay of the Grand Gulf 500 kV Switchyard. Service transformer 21 is connected to the Grand Gulf 500 kV Switchyard via a two-bus-two-breaker scheme. Grand Gulf is comprised of one 1,600 MVA unit, with maximum auxiliary station service load as shown below for each applicable bus voltage level: • • • Grand Gulf Normal Operations Loads 500 kV System = 76 MW and 37 Mvar Grand Gulf Accident Loads 500 kV System = 69 MW and 34 Mvar Grand Gulf Accident Loads 115 kV System = 13.05 MW and 6.32 Mvar The step-up transformer bank for the generating unit is comprised of three single phase transformers with a total unit rating of 1,650 MVA. Grand Gulf uses two 500/34.5 kV service transformers and a single 115/4.16 kV ESF Transformer 12 to provide the unit with offsite power. Grand Gulf electrical loads are supplied from the Grand Gulf 500 kV Switchyard located at Grand Gulf via two service transformers. The preferred source of electrical power for Grand Gulf electric loads is the 500 kV offsite power supply. The Grand Gulf connection to the 115 kV Transmission System is a separate (back-up) source of offsite power to Grand Gulf. Analysis: MISO incorporated the Entergy’s South Nuclear Plants NPIRs into its bi-annual assessments. The analysis was performed as part of the MISO Coordinated Seasonal Transmission Assessment (CSA). Results: The Nuclear Plant Interface Requirements (NPIRs) for Entergy’s South Nuclear Plants were incorporated into the MISO CSA study. The results showed that the NPIRs met the required Entergy’s South Nuclear Plants performance criteria. 27 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Waterford Description: Waterford 3 is connected to the utility grid by two transmission lines to the Waterford 230 kV Switchyard via the Switching Station. The Waterford 230 kV Switchyard also has several other 230 kV transmission lines connected to it. Three of these transmission lines connect Waterford Units 1 and 2 to the Switchyard. Three of the transmission lines cross the river on two separate river crossing towers to tie into the Little Gypsy 230 kV Switchyard. There is a 230 kV tie to the adjacent 500 kV Switchyard. There are other transmission lines which tie to other areas of the Entergy grid. The system is designed such that no transmission lines cross the 230 kV lines connecting the Waterford No. 3 switching station to the Waterford No. 3 230 kV Switchyard. In addition to the 230 kV lines connected to the switchyard, there is also a line constructed to 230 kV standards but operating at 115 kV, which passes through the 230 kV switchyard. Power is supplied from the main generator to the Waterford 3 switching station through two main transformers which are in parallel. From the switching station, two overhead lines transmit power to the Waterford switchyard, which is the point of connection to the grid. The Plant Electric Power Distribution System receives power under normal operating conditions from the main generator through two unit auxiliary transformers. For start-up and shutdown, when the main generator is unavailable, power is obtained through two startup transformers from the grid through the switchyard transmission lines and the switching station. When Waterford 3 is not operating, an additional path of supply from the switching station to the Plant Electric Power Distribution System may be made available by opening links in the generator main lead box and by using the main transformers and unit auxiliary transformers instead of the start-up transformers. The Waterford 3 (WF-3) Plant is comprised of one unit rated at 1,333.2 MVA. The Waterford 3 (WF-3) maximum auxiliary station service load is 71.33 MW and 34.21 Mvar. The step-up transformer bank for the generating unit is comprised of two (2) three-phase transformers units, one of the transformer (GSU-3A) is rated at 684 MVA (FOA) the other transformer (GSU-3B) is rated at 672 MVA. Analysis: MISO incorporated the Entergy’s South Nuclear Plants NPIRs into its bi-annual assessments. The analysis was performed as part of the MISO Coordinated Seasonal Transmission Assessment (CSA). Results: The Nuclear Plant Interface Requirements (NPIRs) for Entergy’s South Nuclear Plants were incorporated into the MISO CSA study. The results showed that the NPIRs met the required Entergy’s South Nuclear Plants performance criteria. 28 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Riverbend Description: River Bend is connected to the utility grid by two transmission lines to the Fancy Point 230 kV Switchyard. One transmission line is a double circuit line with one circuit feeding the plant and the other connecting the generator to the grid. The Fancy Point 230 kV Switchyard also has four other 230 kV transmission lines connected to it as well as a connection to the Fancy Point 500 kV Switchyard. The Fancy Point 500 kV switchyard is connected to two 500 kV transmission lines. The Riverbend (RBS) Plant is comprised of one unit rated at 1,151.1 MVA. The RBS maximum auxiliary station service load is 84.7 MW and 59.7 Mvar. The step-up transformer bank for the generating unit is comprised of two (2) three-phase transformers units rated at 518/788.5 MVA (65o C FOA/FOA). River Bend Station uses two 230/13.8 kV Preferred Station Service Transformers and two 230/4.16 kV Preferred Station Service Transformers to provide the unit with offsite power. Analysis: MISO incorporated the Entergy’s South Nuclear Plants NPIRs into its bi-annual assessments. The analysis was performed as part of the MISO Coordinated Seasonal Transmission Assessment (CSA). Results: The Nuclear Plant Interface Requirements (NPIRs) for Entergy’s South Nuclear Plants were incorporated into the MISO CSA study. The results showed that the NPIRs met the required Entergy’s South Nuclear Plants performance criteria. 29 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Prairie Island Description: Prairie Island is located in Southeast Minnesota, along the Mississippi river. It is owned and operated by Xcel Energy. The Prairie Island Plant is comprised of two 659 MVA Generator step-up Transformers with a maximum combined auxiliary station service load of 63.2 MW and 35.3 Mvar. There are two 600 MVA, 20 kV step-up transformers. It has four off site sources, two from the 345 kV bus, one from the 161 kV bus and one from the 345/161 kV transformer tertiary bus. NSPM is the sole provider of offsite power. Analysis: The analysis indicated that the 99.5% voltage criteria at 161 kV bus is not met during certain contingencies, however this is not a concern as additional plant sources are available from the 345 kV bus. The Category D contingency of a two unit trip was also analyzed with all voltages remaining acceptable for the plant. Results: Prairie Island NPIRs are satisfactorily met during this transmission assessment. 30 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Monticello Plant Description: The Monticello plant is located in central Minnesota, along the Mississippi river. It is owned and operated by Xcel Energy. The Monticello Plant is comprised of one 718 MVA Generator Step Up Transformer with no unit connected auxiliary station service transformer. There is one 800 MVA, 22/345 kV generator step-up transformer. It has four off site sources, two from 345 kV bus, one from the 115 kV bus and one from 345/115 kV transformer tertiary bus. NSPM is the sole provider of off-site power. Analysis: The analysis indicated that the 99.1% voltage on the 115 kV bus is not met during certain contingencies (mainly C3), this is not a concern as there are two sources available from the 345 kV bus. The 345 kV low voltage can be addressed by adjusting the generation set point to hold a higher voltage at the 345 kV bus. Results: Monticello NPIRs are satisfactorily met during this transmission assessment. 31 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Duane Arnold Energy Center Description: The Duane Arnold Energy Center (DAEC) is a nuclear plant located in Palo, IA just outside of Cedar Rapids, IA. This plant has a real gross output of 630 MW and is connected to the 161 kV. This nuclear plant is owned and operated by NextEra Energy. Analysis: ITCM Planning incorporated the Duane Arnold Energy Center (DAEC) into its annual transmission assessment. The analysis was performed as part of the MAPP Transmission Reliability Assessment Subcommittee (TRAS) study performed annually. Results: The Nuclear Plant Interface Requirements (NPIRs) for DAEC were incorporated into the TRAS study. The DAEC load was modeled per the NPIRs. The results showed that the Iowa area meets the required DAEC NPIRs performance criteria. 32 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 10.0 APPENDICES Appendices contain the actual study input files and detailed results of the analysis and are located in separate folders on the extranet. Appendix A – Subsystem, Monitored Element, and Contingency Files Appendix B – Steady-State AC Contingency Results Appendix C – FCITC Results Appendix D – Critical Interface Results Appendix E – Large Load Area Results Appendix F – VSAT input files Appendix G – Wind Generation Sensitivity Analysis Appendix H – FCITC Stability Analysis Results 33 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release 11.0 ABBREVIATIONS AND ACROYNMS MISO North Region: ALTW BEPC DPC GRE ITC ITCM MHEB MDU MEC MP MPC MPW NWPS OTP RPU SMMPA WAPA XEL Alliant Energy West Basin Electric Power Cooperative Dairyland Power Cooperative Great River Energy ITC Holdings Corporation International Transmission Company Midwest Manitoba Hydro-Electric Board Montana-Dakota Utilities Company MidAmerican Energy Company Minnesota Power Minnkota Power Cooperative, Incorporated Muscatine Power and Water Company Northwestern Public Service Company Otter Tail Power Company Rochester Public Utilities Southern Minnesota Municipal Power Agency Western Area Power Administration Xcel Energy MISO Central Region: AMIL AMMO ATC ALTE MGE UPPC WEC WPS BREC CWLD CWLP DEI HE IPL ITC ITCT METC LBWL MPPA NIPSCO OVEC SIGE SIPC WPSCI Ameren Illinois Ameren Missouri American Transmission Company Alliant Energy East Madison Gas and Electric Company Upper Peninsula Power Company Wisconsin Electric Power Company (WE) Wisconsin Public Service Corporation Big Rivers Electric Company Columbia Water & Light Department City of Springfield (IL), Water Light & Power Duke Energy Indiana Hoosier Energy Indianapolis Power & Light ITC Holdings Corporation International Transmission Company Michigan Electric Transmission Company City of Lansing Board of Water & Light Michigan Public Power Agency Northern Indiana Public Service Company Ohio Valley Electric Corporation Southern Indiana Gas & Electric (Vectren) Southern Illinois Power Cooperative Wolverine Power Supply Cooperative, Inc. 34 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release MISO South Region: CLEC EAI PUPP PLUM OMLP CWAY NLR BUBA WMU EES DER BRAZ LAFA LAGN LEPA SMEPA BBA Cleco Power LLC Entergy Arkansas Union Power Partners, L.P. Plum Point Energy Associates, LLC City of Osceola, AR City of Conway, AR City of North Little Rock, AR City of Benton, AR City of West Memphis, AR Entergy (Louisiana, Texas, Mississippi, New Orleans) City of Ruston, LA Brazos Electric Cooperative Lafayette Utilities System Louisiana Generation LLC Louisiana Energy and Power Authority Southern Mississippi Electric Power Association Batesville Generation MISO Tier-1: AEC AECI AEP AEPW ATSI CE DAY DEO&K EEI EKPC LGE/KU EMDE GMO IESO KACP LES NPPD OKGE OPPD SOCO SPC SPP SWPA TVA Alabama Electric Corporation (Power South) Associated Electric Cooperative, Inc. American Electric Power AEP – Southwest Power Company American Transmission System Inc. (FirstEnergy Corp.) Commonwealth Edison (Exelon) Dayton Power Duke Energy Ohio & Kentucky Electric Energy, Inc. East Kentucky Power Cooperative Louisville Gas & Electric and Kentucky Utility Empire Electric District KCP&L Greater Missouri Operations Independent Electricity System Operator Kansas City Power & Light Lincoln Electric Services Nebraska Public Power District Oklahoma Gas & Electric Omaha Public Power District Southern Company Saskatchewan Power Company Southwest Power Pool Southwestern Power Administration Tennessee Valley Authority 35 MISO Coordinated Seasonal Assessment – 2014 Spring Contains CEII – Do Not Release Non-MISO: DOE FERC MAPP MRO NERC PJM RCDC RFC SERC WECC Department Of Energy Federal Energy Reliability Council Mid-Continent Area Power Pool Midwest Reliability Organization North America Electric Reliability Corporation PJM Interconnection, LLC Rapid City DC Interconnect ReliabilityFirst Corporation SERC Reliability Corporation Western Electric Coordinating Council 36