LANCASHIRE COUNTY COUNCIL PRESTON BUS STATION AND CAR PARK Rough Order of Cost Estimate 12th November 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE Document Control Sheet BPP 04 F8 Version 7 April 2011 Client: Project: Document Title: Ref. No: ORIGINAL DATE Lancashire County Council Preston Bus Station Rough Order of Cost Estimate Project No: B1814900 Originated by Checked by Reviewed by Approved by NAME NAME NAME NAME E. Lukaseviciene Tony Waite Tony Waite Colin Campbell INITIALS INITIALS INITIALS INITIALS EL rd 23 October 2012 REVISION A DATE Document Status Draft NAME NAME NAME NAME E. Lukaseviciene Tony Waite Tony Waite Colin Campbell INITIALS INITIALS INITIALS INITIALS EL th 12 November 2012 Document Status REVISION NAME NAME NAME NAME DATE INITIALS INITIALS INITIALS INITIALS Document Status REVISION NAME NAME NAME NAME DATE INITIALS INITIALS INITIALS INITIALS Document Status REVISION NAME NAME NAME NAME DATE INITIALS INITIALS INITIALS INITIALS Document Status Jacobs U.K. Limited This document has been prepared by a division, subsidiary or affiliate of Jacobs U.K. Limited (“Jacobs”) in its professional capacity as consultants in accordance with the terms and conditions of Jacobs’ contract with the commissioning party (the “Client”). Regard should be had to those terms and conditions when considering and/or placing any reliance on this document. No part of this document may be copied or reproduced by any means without prior written permission from Jacobs. If you have received this document in error, please destroy all copies in your possession or control and notify Jacobs. Any advice, opinions, or recommendations within this document (a) should be read and relied upon only in the context of the document as a whole; (b) do not, in any way, purport to include any manner of legal advice or opinion; (c) are based upon the information made available to Jacobs at the date of this document and on current UK standards, codes, technology and construction practices as at the date of this document. It should be noted and it is expressly stated that no independent verification of any of the documents or information supplied to Jacobs has been made. No liability is accepted by Jacobs for any use of this document, other than for the purposes for which it was originally prepared and provided. Following final delivery of this document to the Client, Jacobs will have no further obligations or duty to advise the Client on any matters, including development affecting the information or advice provided in this document. This document has been prepared for the exclusive use of the Client and unless otherwise agreed in writing by Jacobs, no other party may use, make use of or rely on the contents of this document. Should the Client wish to release this document to a third party, Jacobs may, at its discretion, agree to such release provided that (a) Jacobs’ written agreement is obtained prior to such release; and (b) by release of the document to the third party, that third party does not acquire any rights, contractual or otherwise, whatsoever against Jacobs and Jacobs, accordingly, assume no duties, liabilities or obligations to that third party; and (c) Jacobs accepts no responsibility for any loss or damage incurred by the Client or for any conflict of Jacobs’ interests arising out of the Client's release of this document to the third party B1814900 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE Contents 1 Project Summary 1-1 2 Cost Summary 2-2 3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 Basis of Cost Estimate Range Form of Contract Basis of Costs Drawings and Information Gross Internal Floor Areas Assumptions Exclusions 2-5 2-5 2-5 2-5 2-5 2-6 2-7 2-8 Appendix A - Alternative Junction Improvement Costs Appendix B - Notional Cost Breakdown for Bus Station B1814900 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE 1 Project Summary This Rough Order of Cost Estimate provides an appraisal of indicative costs for three different options of various potential works in / around the existing Preston Bus Station and multi storey car park. The Rough Order of Cost Estimate provides financial analysis of the following Layout Options: • Option 1 – Retaining the existing Bus Station Structure • Option 2 – New Bus and separate Coach Station (using “Island site”) • Option 3 – New Bus and Coach Station (New facility to the north) Option 2 and 3 layouts include a 350 space surface level Car Park. The costs which are based on current day prices (4Q 2012) are rounded up to the nearest £100,000 and include an Optimism Bias level of 40% and can be summarised as follows: Building Costs £ A Option 1 – Retention of the existing Bus Station Structure 23,100,000.00 B Option 2 – New Bus and separate Coach Station (using “Island site”) 14,700,000.00 Option 3 – New Bus and Coach Station (New facility to the north) 15,300,000.00 C The above costs, at the request of Lancashire County Council, include, for comparative purposes only, the cost of removing the existing Bus Station tenants in all options and the cost of acquiring the land to the island site in Option 2. All other costs relating to land purchase costs and relocation of tenants are excluded from this Report. B1814900 1-1 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE 2 Cost Summary A Option 1 – Retention of the existing Bus Station Structure 1.0 Building Works £ 1.1 Structural alterations and repairs to existing Bus Station Structure 4,935,000.00 1.2 DDA compliance costs and H&S requirements 2,035,000.00 1.3 Removal of existing Bus Station Concrete Aprons 1.4 New Coach Station (350m2 x £2,350/m2) say 1.5 Bus Station refurbishment (2,040m2 x £1,750/m2) 1.6 Bus and Coach Infrastructure (12,140m2 x £110/m2) say £ 250,000.00 825,000.00 3,570,000.00 1,335,000.00 1.7 Allowance for general site landscaping (7,070m2 x £25/m2) say 175,000.00 1.8 Associated Highway works Lancaster Road & Taxi Rank 1.9 Allowance for providing temporary bus station 1.10 Allowance for “open sided” covered walkway (360m2) 1.11 Allowance for cost of removing existing Bus Station tenants 150,000.00 250,000.00 300,000.00 565,000.00 14,390,000.00 2.0 Preliminaries 2.1 Allowance for Main Contractor’s Preliminaries (15% on items 1.1 to 1.10 only) say 2,080,000.00 Sub Total 16,470,000.00 3.0 Main Contractors Overheads and Profit 3.1 Allowance for Main Contractors Overheads and Profit (5% on items 1.1 to 1.9 and 2.1 only) included Sub Total 16,470,000.00 4.0 Optimism Bias 4.1 Allowance for Optimism Bias (40%) 6,620,000.00 Total Current Day Cost (as at 4Q 2012) say B1814900 2-2 £23,090,000.00 £23,100,000.00 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE 2 Cost Summary (Cont’d) B Option 2 – New Bus and separate Coach Station (using “Island site”) 1.0 Building Works £ £ 1.1 Demolition of existing Bus Station and removal of Bus Station concrete aprons 1,250,000.00 1.2 New Bus Station facility (1,500m2 x £2,350/m2) 3,525,000.00 1.3 Bus and Coach Infrastructure (14,091m2 x £110/m2) say 1.4 New Coach Station (100m2 x £2500/m2) 1,550,000.00 250,000.00 1.5 Surface car park provision (8,370m2 x £100/m2) say 840,000.00 1.6 Associated Highway works Lancaster Road 150,000.00 1.7 Allowance for providing temporary bus station / phased construction 1.8 Allowance for “open sided” covered walkway (490m2) 1.9 Cost of acquiring land (Island site) 250,000.00 400,000.00 450,000.00 1.10 Allowance for cost of removing existing Bus Station tenants 565,000.00 9,230,000.00 2.0 Preliminaries 2.1 Allowance for Main Contractor’s Preliminaries (15% on items 1.1 to 1.8 only) 1,230,000.00 Sub Total 10,460,000.00 3.0 Main Contractors Overheads and Profit 3.1 Allowance for Main Contractors Overheads and Profit (5% on items 1.1 to 1.8 and 2.1 only) included Sub Total 10,460,000.00 4.0 Optimism Bias 4.1 Allowance for Optimism Bias (40%) 4,185,000.00 Total Current Day Cost (as at 4Q 2012) Say B1814900 2-3 £14,645,000.00 £14,700,000.00 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE 2 Cost Summary (Cont’d) C Option 3 – New Bus and separate Coach Station (New facility to the North) 1.0 Building Works £ 1.1 Demolition of existing Bus Station and removal of Bus Station concrete aprons 1.2 New Bus Station facility (1,620m2 x £2,350/m2) say £ 1,250,000.00 3,805,000.00 1.3 Bus and Coach Infrastructure (13,514m2 x £110/m2) say 1.4 New Coach Station (300m2 x £2,350/m2) say 1,490,000.00 705,000.00 1.5 Surface car park provision (9,000m2 x £100/m2) 900,000.00 1.6 Associated Highway works Lancaster Road 150,000.00 1.7 Allowance for providing temporary bus station / phased construction 1.8 Allowance for “open sided” covered walkway (520m2) 1.9 Allowance for cost of removing existing Bus Station tenants 250,000.00 425,000.00 565,000.00 9,540,000.00 2.0 Preliminaries 2.1 Allowance for Main Contractor’s Preliminaries (15% on items 1.1 to 1.8 only) 1,350,000.00 Sub Total 10,890,000.00 3.0 Main Contractors Overheads and Profit 3.1 Allowance for Main Contractors Overheads and Profit (5% on items 1.1 to 1.8 and 2.1 only) included Sub Total 10,890,000.00 4.0 Optimism Bias 4.1 Allowance for Optimism Bias (40%) 4,360,000.00 Total Current Day Cost (as at 4Q 2012) Say B1814900 2-4 £15,250,000.00 £15,300,000.00 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE 3 Basis of Cost 3.1 Estimate Range This Rough Order of Cost Estimate can only be regarded as an order of cost at this stage as it has been based on the limited information listed in Section 3.4 of our Rough Order of Cost Estimate. Jacobs would normally include an estimate range, however, Lancashire County Council requested Jacobs adopt the Department of Transport standard method of accounting known as Optimism Bias in this instance. Optimism Bias is a Department for Transport standard method of accounting for the risks involved with estimating a scheme when the finer details are not yet known. This takes into account the risks involved with construction, delays to the programme, increased costs associated with design development and pricing levels associated with the uncertainty around the final specification, including the assumptions that need to be made at each stage of the projects life. At feasibility stage, which is the stage this project has reached, the DfT recommends an Optimism Bias of 40% is added to any cost estimate. This figure reduces as the design of the bus station is refined. 3.2 Form of Contract For the purpose of preparing this Feasibility Cost Plan it has now been assumed that a standard NEC / JCT Form of Contract will be used as the basis for procurement. 3.3 Basis of Costs This Rough Order of Cost Estimate has been prepared using a cost per m2 method for the major elements of the Works. The rates used reflect competitive single stage selective tender prices for building projects of a similar size and nature and at current day prices (as at 4Q 2012). The costs for the Bus Station and Coach Station facilities have been obtained from Spons pricing books. 3.4 Drawings and Information This Rough Order of Cost Estimate has been based upon the following information: Jacobs Indicative Layouts`: Preston Bus Station Preliminary Design Preston Bus Station Option 2 Preliminary Design Preston Bus Station Option 3 Preliminary Design B1814900 2-5 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE 3 Basis of Cost (Cont’d) 3.5 Gross Internal Floor Areas The following gross internal areas have been used as the basis for the Rough Order of Cost Estimate: Option 1 Gross Floor Area m2 Refurbished Bus Station Facility New Coach Station Facility TOTALS 2,020 21,743 350 3,767 2,370 25,510 Option 2 Gross Floor Area m New Bus Station Facility New Coach Station Facility TOTALS 2 ft2 1,500 16,146 100 1,076 1,600 Option 3 17,222 Gross Floor Area New Bus Station Facility New Coach Station Facility TOTALS B1814900 ft2 2-6 m2 ft2 1,620 17,438 300 3,229 1,920 20,667 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE 3 Basis of Cost (Cont’d) 3.6 Assumptions The following items have been assumed for the purpose of preparing the Rough Order of Cost Estimate for all options unless otherwise stated: a) No works beyond the existing site area other than those stated above b) Works undertaken during normal working hours c) Unrestrictive access to the site d) Sufficient space to be provided for Contractor’s accommodation & welfare facilities e) Extent of works and level of specification is as set out in the information listed in 3.4 above and Appendix A of this Report 3.7 Exclusions The following items are excluded from the Rough Order of Cost Estimate for all options unless otherwise stated: a) Land costs, legal fees, finance charges, professional fees, planning and building regulation fees, VAT etc (except for land acquisition costs associated with the island site in Option 2 ) b) Site surveys and ground investigation surveys c) Asbestos and contaminated land removal costs d) Abnormal foundations resulting from poor ground conditions e) Service diversion costs f) Upgrade of existing infrastructure g) Section 106 and other planning requirements h) Works to boundary walls and provision of perimeter fencing j) Fit out of Retail Areas k) Ticket machines to car parks l) Pre – contract inflation m) IT infrastructure, cabling etc n) Alterations to existing internal car park ramps (Option 1) p) Development of existing Ground Floor West Side bus station for retail use (Option 1) B1814900 q) Alterations to existing lift shafts to accommodate new lifts (Option 1) r) LV and Sub mains distribution replacement to existing Car Park (Option 1) 2-7 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE 3 Basis of Cost (Cont’d) s) On going running costs associated with the new and existing Car Parks and Bus Station t) u) B1814900 Air conditioning Relocation of existing Tenants (other than those costs included for relocating existing Bus Stop Tenants) 2-8 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE Appendix A – Alternative Junction Improvement Costs Tenterfield Street (option 1) - Mini Roundabout Re model Ormskirk Road, Tithebarn Street Junction. This will allow buses or coaches to access the bus station via Tenterfield Street Underpass. £250,000.00 Tenterfield Street (option 2) – Traffic Signals Re model Ormskirk Road, Tithebarn Street Junction. This will allow buses or coaches to access the bus station via Tenterfield Street Underpass and allow buses to exit the new bus station directly north onto Ring Way avoiding Old Vicarage. £375,000.00 Ring Way – Bus Gate Construction of short bus only lane on Ring Way would be possible to provide a dedicated ‘Bus gate’ opposite the Junction with Percy Street. Bus could then avoid the Carlisle Street Pole Street one way system. The existing Traffic Signal Junction Ring Way/Church Street will need modification to ensure correct signal phasing. £150,000.00 Bus Station Emergency access or egress Additional gated entrance off Carlisle Street included in all layouts B1814900 2-9 Included 23rd October 2012 PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE Appendix B – Notional Cost Breakdown for Bus Station Option 2 – New Bus Station and separate Coach Station (using “Island site”) The following is an indicative elemental cost breakdown that could be expected for a 1,500m2 medium to high quality Bus Station: £ 1.1 Demolitions and site clearance £ 1,250,000 1.2 Bus Station (1500m2) Substructure 335,000 Frame 245,000 Roof 550,000 Internal roofs to accommodation areas 45,000 External walls, windows and doors 725,000 Internal walls 170,000 Internal doors, windows and screens 120,000 Floor finishes 200,000 Wall finishes 50,000 Ceiling finishes 70,000 Fittings 125,000 Sanitary fittings 25,000 CCTV Installation 200,000 Passenger information display system 200,000 Services installation 465,000 3,525,000 1.3 Bus and Coach Infrastructure Pedestrian paved areas 440,000 Bus manoeuvring areas and roads 765,000 Carried Forward £ B1814900 2012 2-10 1,205,000 4,775,000 23rd October PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE Brought Forward £ 1,205,000 Landscaped areas 25,000 Incoming services to Bus Station and Coach Station 75,000 External lighting 75,000 Drainage 4,775,000 170,000 1,550,000 1.4 New Coach Station (100m2) 250,000 1.5 Car parking 840,000 1.6 Associated highways works in Lancaster Road 150,000 1.7 Allowance for temporary bus station 250,000 1.8 Allowance for “open sided” covered walkway 400,000 1.9 Cost of acquiring land (Island site) 450,000 1.10 Allowance for cost of removing existing Bus Station tenants 565,000 2.0 Preliminaries 1,230,000 3.0 Main Contractor’s Overheads and Profit included 4.0 Optimism Bias 4,185,000 Total Current Day Cost (4Q 2012) Say B1814900 2012 2-11 14,645,000 14,700,000 23rd October PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE Option 3 – New Bus Station and separate Coach Station (new facility to the North) The following is an indicative elemental cost breakdown that could be expected for a 1,620m2 medium to high quality Bus Station: £ 1.1 Demolitions and site clearance £ 1,250,000 1.2 Bus Station (1620m2) Substructure 360,000 Frame 265,000 Roof 595,000 Internal roofs to accommodation areas 50,000 External walls, windows and doors 785,000 Internal walls 180,000 Internal doors, windows and screens 130,000 Floor finishes 215,000 Wall finishes 60,000 Ceiling finishes 75,000 Fittings 135,000 Sanitary fittings 25,000 CCTV Installation 215,000 Passenger information display system 210,000 Services installation 505,000 3,805,000 1.3 Bus and Coach Infrastructure Pedestrian paved areas 300,000 Bus manoeuvring areas and roads 845,000 Landscaped areas 25,000 Incoming services to Bus Station and Coach Station 75,000 Carried Forward £ B1814900 2012 2-12 1,245,000 5,055,000 23rd October PRESTON BUS STATION ROUGH ORDER OF COST ESTIMATE Brought Forward £ 1,245,000 External lighting 5,055,000 75,000 Drainage 170,000 1,490,000 1.4 New Coach Station (300m2) 705,000 1.5 Car parking 900,000 1.6 Associated highways works in Lancaster Road 150,000 1.7 Allowance for temporary bus station 250,000 1.8 Allowance for “open sided” covered walkway 425,000 1.9 Allowance for cost of removing existing Bus Station tenants 565,000 2.0 Preliminaries 1,350,000 3.0 Main Contractor’s Overheads and Profit included 4.0 Optimism Bias 4,360,000 Total Current Day Cost (4Q 2012) Say B1814900 2012 2-13 15,250,000 15,300,000 23rd October