CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Hydro One Networks Inc. Project: Goderich TS- Station Upgrade CAA ID: 2011-EX549 Final Report Goderich TS-Station Upgrade 2011-EX549 IESO EXPEDITED SYSTEM IMPACT ASSESSMENT – 2011-EX549 1. Project Description Hydro One Networks Inc. has proposed an addition of one 115/ 27.6 kV, 50/67/83 MVA transformer and a single 27.6 kV bus at its existing Goderich TS in the western Ontario. The station is connected to the IESO controlled grid through 115 kV radial circuit M18. Presently, Goderich TS is comprised of one (T1)115/27 kV, 15/20/25 MVA transformer and two (T2 and T3) 115/27 kV, 11/15 MVA transformers. According to the information provided by Hydro One, the station has average peak load of approximately 40 MW. Two 27.6 kV feeders from Goderich TS connect the 40 MW Capital Power Kingsbridge wind farm to this station. These feeders will be relocated to the new 27.6 kV bus. Thermal limitations restrict the connection of additional 2.9 MW of planned generation projects to this station. The proposed transformer will mitigate this thermal limitation and facilitate the connection of new generation projects. The proposed in service date for the addition of the new transformer is July 7, 2012. Figure 1: Goderich TS-Existing arrangement 2 Goderich TS-Station Upgrade 2011-EX549 Figure 2: Goderich TS- Proposed arrangement 2. Technical specifications of the equipment Transformer Rating Rated voltage Under load tap changer Grounding reactor 50/67/83 MVA 115/ 27.6 kV +/- 22kV in +/- 16 steps HV: Wye LV: Zig-Zag- grounded 1.5 Ohm High voltage equipment Nominal voltage Rated voltage Ampacity (Continuous) Short circuit capacity 115 kV 127 kV 600 A 50 kA Transformer connections Low voltage breakers Equipment Transformer breaker Bus Tie breaker Feeder breakers Nominal voltage (kV) 27.6 27.6 27.6 Continuous rating (A) 3000 2000 2000 3 Interrupting capability (kA) 17 17 17 Cycles 5 5 5 Goderich TS-Station Upgrade 2011-EX549 3. Findings The review of the information provided for the proposed addition of new 115/ 27.6 kV, 50/67/83 MVA transformer at the existing Goderich TS concludes that the new transformer at Goderich TS will not have any negative impact on the reliability of the IESO controlled grid. 4. IESO’s Requirements for Connection The proposed connection must comply with all the applicable requirements from the Transmission System Code (TSC), IESO Market Rules, and standards and criteria. The most relevant requirements are summarized below: Operating voltages requirement All 115 kV equipment must be capable of continuously operating for all voltages within 113 kV and 127 kV, as per Appendix 4.1, Reference 2 of the Market Rules. Protective relaying must be set to ensure that transmission equipment remains in-service for voltages between 94% of the minimum continuous and 105% of the maximum continuous values in the Market Rules, Appendix 4.1. All equipment shall be capable of continuously operating within the frequency range of 59.5 Hz and 60.5 Hz. Fault levels Hydro One shall ensure that the new equipment be designed to withstand the fault levels in the area. Appendix 2, of TSC, establishes the maximum symmetrical 3-phase and single line to ground (SLG) fault level of 50 kA for 115 kV nominal voltage level and the 3-phase symmetrical fault level of 17 kA and SLG symmetrical fault level of 21 kA for 27.6 kV nominal voltage level. If any future system enhancement results in an increased fault level higher than the equipment’s capability, Hydro One is required to replace the equipment at its own expense with higher rated equipment capable of withstanding the increased fault level, up to the maximum fault level specified in Appendix 2 of the Transmission System Code. Protection requirement New protection systems at Goderich TS must be designed to satisfy all the requirements of the Transmission System Code. New protection systems must be coordinated with existing protection systems. Monitoring requirements As specified in Appendix 4.16 of the Market Rules, Hydro One is required to install all the equipment needed to provide telemetry data to the IESO on a continuous basis. Facility Registration/Market Entry requirements The connection applicant must complete the IESO Facility Registration/Market Entry process in a timely manner before the IESO grants the final approval for the connection. Models and data, including any controls that would be operational, must be provided to the IESO. This information should be submitted at least seven months before energization to the IESOcontrolled grid, to allow the IESO to incorporate this project into IESO work systems and to perform any additional reliability studies. As part of the IESO Facility Registration/Market Entry process, the connection applicant must provide evidence to the IESO confirming that the equipment installed meets the Market Rules 4 Goderich TS-Station Upgrade 2011-EX549 requirements and matches or exceeds the performance predicted in this assessment. This evidence shall be either type tests done in a controlled environment or commissioning tests done on-site. In either case, the testing must be done not only in accordance with widely recognized standards, but also to the satisfaction of the IESO. Until this evidence is provided and found acceptable to the IESO, the Facility Registration/Market Entry process will not be considered complete and the connection applicant must accept any restrictions the IESO may impose upon this project’s participation in the IESO-administered markets or connection to the IESO-controlled grid. The evidence must be supplied to the IESO within 30 days after completion of commissioning tests. Failure to provide evidence may result in disconnection from the IESO-controlled grid. If the submitted models and data differ materially from the ones used in this assessment, then further analysis of the project will need to be done by the IESO. Notification of Conditional Approval From the information provided, the review concludes that the proposed new transformer at Goderich TS will not result in a material adverse effect on the reliability of the IESOcontrolled grid. It is recommended that a Notification of Conditional Approval for Connection be issued for the addition of new 115/ 27.6 kV, 50/67/83 MVA transformer , subject to the implementation of the requirements listed in this report. 5