ESL-IE-99-05-28 GUIDELINES FOR POWER FACTOR IMPROVEMENT PROJECTS Gregory W. Massey, P.E. Electrical Engineer Federal Bureau ofPrisons ABSTRACT KW is the real power output of the electrical system, and KVA is the apparent power consumed by the electrical system in producing the real power output. Power factor is an indication of electrical system efficiency. Low power factor, or low system efficiency, may be due to one or more causes, including lightly loaded transformers, oversized electric motors, and harmonic-generating non-linear loads. Knowing the cause of low power factor is essential to developing an effective remedy. Essentially, this expression of power factor is a simple measure of efficiency: total output divided by total input. The real power output, KW, is the useful work performed in pumping fluids, moving air, producing heat, producing light, etc. The apparent power input, KVA, is the unique composite power required from the utility by the distribution system equipment and by the loads to produce the system­ specific power output in KW. Apparent power is composed of real, reactive, and harmonic power. If low power factor is caused by harmonic loads, for example, the misapplication of capacitor banks alone could create other, more significant problems. Additionally, the goal of power factor improvement can vary from the simple reduction of utility costs to the complex elimination ofharmonic load currents. Regardless of the cause of low power factor or the goal in improving system efficiency, the methodology in defining the solution is similar. This paper discusses the critical issues involved in developing a power factor improvement project Note: The views expressed in this paper do not necessarily represent the views of the United States of America, the U. S. Department of Justice, or the Federal Bureau ofPrisons. Reactive power, expressed as Kilo-Volt Amperes Reactive (KVAR), is the power consumed in establishing and maintaining electric and magnetic fields in induction machines such as motors and transformers. Harmonic power, expressed as Kilo-Volt Amperes-harmonic (KVAh), is the power consumed by non-linear loads such as adjustable speed motor drives, arc furnaces, and switch-mode power supplies, and, to a lesser degree, by the inherent imperfections in linear­ type loads. INTRODUCTION Although power factor can be defined in several different ways, the most useful definition of power factor when dealing with energy-related concerns is the ratio of real power, expressed as KiloWatts (KW), to apparent power, expressed as Kilo-Volt Amperes (KVA), as given by: PF=KW KVA Kansas City, Kansas Using Equation 1 as the basis for analyzing electrical system. efficiency empirically, low power factor is caused either by an excessive reactive power requirement from lightly loaded or oversized motors and transformers, by an excessive harmonic power requirement from large or numerous non-linear loads, or by a combination of both. (1) The pages that follow outline a methodology for quantifying reactive power requirements of the system and load, and for determining the cause of low power factor, either from excessive reactive power or from excessive harmonic power requirements. where PF is Power Factor, 190 Proceedings from the Twenty-first National Industrial Energy Technology Conference, Houston, TX, May 12-13, 1999 ESL-IE-99-05-28 Rearranging Equation 1, and using the maximum historical peak demand and the measured power factor from utility bills gives the maximum peak apparent power demand, KVAD: QUANTIFYING REACTIVE POWER REQUIREMENTS As an overview, it is important to understand the cyclic nature of electrical energy usage prior to performing any type of energy audit. Except for 24 hour per day operations, electrical loads exhibit daily and seasonal demand cycles. KVAD=KWD PF Electrical usage is typically lower at night when employees are away from work. As employees arrive, electrical load builds on the system as lights, computers, fans, heaters, coffee pots, radios, etc., are turned on at the start of the work day. Electrical usage drops off toward the end of the work day as employees prepare to go home. (2) Because apparent, real and reactive power are related by the Pythagorean Theorem through the theoretical power triangle, the reactive power requirement, KVARD, of the maximum peak demand load is given by: (3) Similar to the daily cycling of electrical loads, seasonal loading of electrical systems occurs. Typically, summer months exhibit higher electrical usage and energy demand because air conditioners are in operation. Winter months represent lower electrical usage and demand because most boilers and furnaces operate on fossil fuels. The peak demand reactive power requirement determined by Equation 3 is the amount of reactive capacitance used by the electrical distribution equipment and loads to supply the peak real power output of the system. It is also the amount of compensatory capacitive reactance required to raise power factor of the maximum historical peak demand load to unity, or 1.00. The greatest resource for documenting the daily and seasonal loading of the electrical system under analysis is the utility company providing electric service to the facility. A little research into the historical energy usage provides tremendous insight in developing the scope of work. The method of determining the amount of capacitive reactance required to raise power factor to some value other than unity takes three steps. First, Equation 2 must be solved for the apparent power required for the target power factor. Second, that value is substituted for the apparent power in Equation 3. And third, that result is used in the following equation with the peak demand reactive power requirement of the load at unity power factor: Utility Bill Database Most utility companies provide a wealth of information on the customer's bill. Many times peak demand and power factor are included, along with energy usage, for industrial and commercial energy customers. This information can be used to determine the reactive power requirements of the distribution system up to the point of utility connection. KVARD-.. ~(KVARDoId)-(KVARD...,.) To develop a representative energy consumption database, a minimum of 36 months of the most recent utility bills are required to account for periods of mild weather during summer or winter months. It is helpful to graph the peak demand over time to visualize the seasonal cycles of electrical loading. (4) where: KVARD comp is the required compensatory capacitive reactance required to raise the power factor from the original value to the new target value, KVARD DId is the capacitive reactive power required by the system and loads with the original low power factor, and KVARD.... is the capacitive reactive power required by the system and loads with the new target power factor. Using the utility bills as a guide, the maximum reactive power required by any given system is derived from the peak demand information. Utility companies typically define peak demand as the maximum electrical demand during any given 15 minute period during the billing cycle. Given the cyclic nature of loads as previously discussed, installing capacitive reactance to achieve unity power factor for the peak load could create 191 Proceedings from the Twenty-first National Industrial Energy Technology Conference, Houston, TX, May 12-13, 1999 ESL-IE-99-05-28 voltage stability problems during times of light loading. In short, too much capacitive reactance causes a voltage increase above the nominal voltage that can cause equipment misoperation and failure, along with overvoltage conditions system-wide. Harmonic Resonance While inductive impedance increases with frequency, capacitive impedance decreases with frequency. For any given electrical distribution system, the capacitive reactance will equal the inductive reactance at a specific frequency, essentially canceling both. This condition, when the only impedance to current flow is the pure resistance of circuit conductors, is referred to as resonance. Typically, every power factor improvement project involves some quantity of static, or unswitched, reactive power compensation. Given the inherent cyclic operation of electrical systems, some method of controlling the amount of reactive power compensation must be incorporated into the design to prevent leading power factor. Harmonic resonance is characterized by large magnitudes of voltage and current within the system. The result of resonance varies from equipment malfunction to catastrophic failure. It is important to determine the likelihood of a resonant condition prior to installing capacitors on a distribution system. DesiKD Alternatives Several approaches to improving power factor to acceptable levels while preventing a leading power factor are available. The following equations, common in literature, are useful in determining whether the installation of capacitors on a distribution system might lead to a resonant condition. The short circuit KVA available from the utility must be determined first., and is given by: One method is to design improvement to some level below unity. Improving power factor to 0.95, for example, would ensure some tolerance for fluctuating load levels, but would not necessarily prevent leading power factor during times of light system loading. Alternatively, automatically switched capacitor banks can be used to control capacitive reactive power connected to the system. Depending upon the levels of capacitance that are switched, automatic capacitor banks can introduce voltage transients into the distribution system. Depending upon the presence of harmonic load currents, automatic capacitor banks can also introduce a resonant condition. (5) where KVA.c is the available short circuit KVA from the utility, V L-L is the system operating voltage, and I sc is the available short circuit current. Synchronous motors can be connected to the distribution system with automatic controls for its operation as a reactive power compensator. Synchronous condensers provide an excellent method for "seamless" power factor improvement and harmonic power control, as no switching occurs. Synchronous motors, however, are relatively large and are not practical for use on smaller distribution systems. Next, the building or facility distribution system short circuit capacity must be estimated. Because transformers represent the majority of impedance within the system., the facility short circuit capacity can be approximated by: (6) Installing static capacitors directly at and switched on and offwith the offending load is another solution, but can be costly simply from the number of locations that may be required. where KVA.r. is the short circuit capacity of the secondary electrical system., KV~ is the KVA rating of the system transfonner(s), KVA.c is the available short circuit KVA from the utility, and Z, is the impedance of the system transfonner(s). Finally, harmonic filters may be required if low power factor is contributable in whole or in part to significant harmonic loads. Caution must be exercised when capacitors designed for 60 Hz operation are installed on a system with significant harmonic load currents to prevent harmonic resonance. 192 Proceedings from the Twenty-first National Industrial Energy Technology Conference, Houston, TX, May 12-13, 1999 ESL-IE-99-05-28 Finally, the resonant harmonic of the distribution system under analysis is given by: hr = One-Line The first step is to examine a one-line diagram of the facility to determine concentrations of typical low power factor loads, such as induction motors. Additionally, the KVA ratings of transformers in the system should be swnmed to determine the percentage of their loading during the peak demand. (7) Manufacturers of large mechanical equipment, such as chillers, typically offer power factor improvement capacitors as an option at the time of purchase. Moreover, a power factor improvement project may have been completed in the past. Consequently, it is important to determine the locations and ratings of any existing capacitors or synchronous condensers on the system. where 11, is the resonant hannonic, KVA,y. is the available short circuit KVA from the distribution system, KVA",., is the available short circuit KVA from any motor contribution, and KVARc is the sum of capacitor KVAR ratings. When Equation 7 indicates a relatively low resonant harmonic, and spectrum analyses indicate that the magnitude of harmonic currents are significant at or near the resonant frequency, harmonic filters may be required to provide the necessary capacitive or harmonic reactance power while protecting the capacitor bank from failure. Interviews The next step is to interview maintenance personnel to verify the accuracy of the one-line diagram. These interviews will also provide insight into the level of maintenance that will be performed on any new equipment installed, which may affect the design. Low power factor may in fact be entirely due to harmonic currents generated by non-linear loads. In those instances, power factor may be improved by installing filters alone. In most cases, however, a combination of harmonic filters along with capacitors designed to operate at the fundamental frequency are required to improve power factor to acceptable levels in systems with harmonic currents present. Site Survey The final step is to tour the facility and to take direct measurements at the loads. Gathering preliminary data may involve measuring the power consumption of any distribution feeders that are suspected of supplying significant or numerous low­ power factor loads. Low power factor loads may be concentrated on only a portion of the distribution system, enabling the elimination of one or more areas of the system from the survey. Given the cyclic nature of electrical loading, and given the unique makeup of each electrical distribution system, the optimal technical solution will consist of two or more of the alternatives outlined above. The next step in refining the scope of work is to locate the cause of low power factor. Significant low power factor loads should be individually monitored in order to identify significant reactive power conswnption in relation to real power output. Examples of individual loads that should be monitored separately include any large motors, any concentrations of small motors on a motor control center, any large non-linear loads such as adjustable speed motor drives, and any significant concentrations of non-linear loads such as computer room branch circuit or distribution panelboards. DETERMINING TIlE CAUSE OF LOW POWER FACTOR As previously mentioned, every electrical system is unique. The loads, the distribution system equipment and the interconnection of the distribution circuiting all combine into a type of system "fingerprint." The duration of this phase of the project is dependent upon the complexity of the system. Recording power quality analyzers, including hannonic voltage and current measuring capabilities, are recommended to be installed for a minimum of 24 hours at each location. Measurements should be taken From an engineering standpoint, it is imperative to dissect the electrical system to determine cause of low power factor before applying an inexpensive, cookbook type solution that addresses symptoms but ignores the root cause of the problem. 193 Proceedings from the Twenty-first National Industrial Energy Technology Conference, Houston, TX, May 12-13, 1999 ESL-IE-99-05-28 during periods of peak seasonal loading based upon historical records, which are typically from July through September for facilities with significant air­ conditioning loads. Similar to summing the individual loads, harmonic current magnitudes can be summed at any common points of connection. The combined harmonic profiles of the individual loads at common busses will result in greater magnitudes of harmonic currents than would be measured at the utility meter because of inherent load cycling and cancellation effects. This provides a "worse-than-worst-case" profile of harmonics present in the system, and ensures a conservative design. Additionally, it is important to verify the condition and operation of any existing capacitors on the system. An existing capacitor that has malfunctioned may be an indication of harmonic load currents and/or harmonic resonance. The cause of any previous capacitor malfunction or failure must be determined in order to prevent a similar or more significant problem with new equipment If measured and summed harmonic load currents are either significant or exist near the resonant frequency of the distribution circuit as determined by Equation 7, at least a portion of the capacitive reactance installed should be in the form of a harmonic filter. As the site survey and load monitoring progresses, one interesting fact should become readily apparent; the cyclic nature of electrical loads extends past the utility meter into the distribution system. As a result, the peak demand of the distribution system as measured by the utility will most likely be less than the sum ofpeak demand measured at the individual loads. Harmonic Filters Harmonic filters "capture" harmonic currents by diverting them through a specially designed series resonant, or low impedance, shunt path to ground. Harmonic filters are an effective and economical way of minimizing harmonic current and voltage distortion and to improve power factor in an electrical environment rich in harmonic load currents. In short, an intensive program of metering individual feeders and loads within a system will reveal that the sum of the parts is greater than the whole because individual loads peak at different times. This fact provides the basis for a conservative and effective design. Active Harmonic Filters Active filters have the ability to cancel harmonics in the current waveform by injecting energy into the gaps that are created by non-linear loads. This technology is still developing and not competitive for general use. Once the system has been adequately dissected, the next step in the development of the project is to manipulate the data measured during the site survey and to confirm the empirical data available from the utility database. Passive Harmonic Filters Passive harmonic filters are more commonly used. Passive filters are constructed of one or more tuned resonant circuits. To compensate for capacitor aging over time, the actual resonant frequency of the harmonic filter is designed to be below the target harmonic. For this reason, a nominal Sth harmonic filter is normally designed for the 4.7th harmonic. REFINING THE SCOPE OF WORK Using the measured results from the site survey, the maximum and minimum levels of the individual loads should be determined using Equations 2 and 3. It is important to note any cycling of the individual loads. Whether a load runs constantly or has short, sporadic periods of operation affects the method of improving the power factor for that load. A large, lightly loaded motor that typically runs for 10 minutes every hour, for example, is a good candidate for a capacitor that is connected on the load side of the motor controller and is switched on and offwith the motor. To prevent the filter from trapping harmonics from the utility grid, a decoupling reactor should be installed as part of the filter. Technical literature is replete with examples of damage caused to harmonic filters installed without a decoupling reactor. Additionally, harmonic filters should have internal protection similar to capacitor banks, such as fuses, along with fault indicators for blown fuses or capacitor failure. After examining the individual loads, the next step is to place this information into the context of the facility one-line diagram by separately summing the maximum power requirements of the individual loads, along with the associated harmonic profiles, at the conunon points of connection. 194 Proceedings from the Twenty-first National Industrial Energy Technology Conference, Houston, TX, May 12-13, 1999 ESL-IE-99-05-28 Capacitors experience terminal voltage in excess of rated voltage when installed in a harmonic filter. The following equation expresses the percent of voltage rise that capacitors experience as a function of the harmonic number at which the filter is tuned: Harmonic filters on the market are designed as an assembly. although it is possible to specify components for field assembly into a harmonic filter. Upgrading an existing capacitor bank to make a shunt filter can also be performed, provided several issues are addressed. Capacitors. for example. have definite limitations that must be taken into consideration during normal operation as well as during operation as an integral component of a harmonic filter. Capacitor rating limitations include a maximum of 180% of rated current. a maximum of 110% of rated voltage, and a maximum of 135% of rated reactive power. (10) where % VR is the percent ofvoltage rise above nominal, and h is the tuned harmonic. To account for the extra duty required of a capacitor to operate as a harmonic filter. an additional 15-20% increase in capacitor line-to-neutral voltage rating is reconunended. The capacitor provides the reactive power required by the reactor in the filter along with providing reactive power for the distribution system. Additionally, the reactive power that a capacitor delivers is dependent upon terminal voltage. As such, the capacitor's reactive power output is as given by Equation 11: A capacitor bank: with a nominal voltage rating and an operating temUnal voltage of 480 V. for example. should not be upgraded into a harmonic filter. The steady-state overvoltage from harmonic currents will most likely exceed the 11 00/0 voltage limitation of the capacitor, and may exceed the 135% reactive power limitation. Capacitors within a harmonic filter connected to a 480 V bus are typically rated for 600 V operation, a 25% increase in line-to­ neutral voltage rating, to prevent equipment damage. KV.4 R . --"fill., 2 =(VL_U X -X C (11) L where KV~tcr is the KVAR output of the filter, VL-L is the applied system voltage, Xc is the capacitive reactance of the filter, and XL is the inductive reactance of the filter. Uperadine an Existine Capacitor into a Harmonic Filter The following equations can be used to size an in-line reactor needed to upgrade an existing capacitor bank into a harmonic filter: Finalizing the Scope of Work All of the information required to finalize the scope of work has been gathered, beginning with the macroscopic utility database and ending with the microscopic data measured during the site survey. Modeling of the measured data using the one-line diagram as a guide will provide the framework for making decisions for improving power factor at individual loads, and, subsequently, for improving the power factor for the entire system. (8) and (9) Static Capacitance The minimum reactive power requirements of the facility as determined from Equation 4 using the target power factor and using the minimum measured power requirements will establish the amount of static, or unswitched, capacitive reactance to install on the system. The location of static capacitance will vary, based upon the configuration of the distribution system. Typical locations are any conunon points of connection for equipment. such as branch circuit panelboards, where Xc is the capacitive reactance of the filter, VL-L is the rated voltage of the capacitor bank, KVAR 3_pbue is the ratedKVAR of the capacitor bank, h is the tuned harmonic, and XL is the inductive reactance of the filter. 195 Proceedings from the Twenty-first National Industrial Energy Technology Conference, Houston, TX, May 12-13, 1999 ESL-IE-99-05-28 distribution panelboards, motor control centers, service entrance switchboards, etc. numerous low-power factor loads for further study. A systematic method of measuring actual power requirements offeeders and loads can be used to establish the framework for understanding the quantities calculated base upon the utility database. Harmonic Filters The power requirements of any non-linear loads as determined from measured data will pro~de the basis for establishing the amount, configuration and location of harmonic filters to install on the system. Typical locations are at any large non-linear loads, or at any common points of connection for non-linear loads. Whether any harmonic filters are switched or are static will be determined by the operational nature of the non­ linear loads. Placing the measured power requirements of the individual loads into the context of the system one-line diagram brings the project scope of work into focus. The nature and location of significant reactive power consuming loads will help to determine the optimal engineering solution. Automatically Switched Capacitance The amount of automatically switched capacitive reactance required to improve power factor is determined by the maximum reactive power requirements of the system, minus the minimum reactive power requirements, and minus the harmonic reactive power requirements of the system. Automatically switched capacitance may take one of several forms outlined above, including one or more static capacitor banks switched by the controller of a large motor, one or more automatically switched capacitor banks connected to a common bus, or a synchronous condenser. The location and configuration ofcapacitive reactance is governed by technical concerns and economics. It is more economically feasible to group the capacitance required for several small motors at the common point of connection, namely a motor control center or distribution panel, than to install individual power factor capacitors at each motor. Because economics frequently dictate that a combination ofstatic and automatically switched .capacitance be installed at the same location, capacitor manufacturers typically offer this combination as a standard product. CONCLUSION Every electrical distribution system is unique in composition and in operation. Using a cookbook approach to power factor improvement that neglects the inherent characteristics of the distribution system equipment and loads can result in more significant problems than low power factor. The historical database available from utility bills can be used to determine the peak magnitude of reactive power consumed by the electrical system. The system one-line diagram can be used to identify large or 196 Proceedings from the Twenty-first National Industrial Energy Technology Conference, Houston, TX, May 12-13, 1999