Engineering Services, Inc. Porsche Engineering Services, Inc. ULSAB Program Phase 2 Final Report to the Ultra Light Steel Auto Body Consortium Engineering Services, Inc. Ultra Light Steel Auto Body Member Companies Aceralia AK Steel Bethlehem BHP Steel British Steel Cockerill Sambre CSN Dofasco Hoogovens Inland Kawasaki Steel Kobe Krakatau Krupp Hoesch LTV Steel National Steel Nippon Steel NKK POSCO Preussag Rouge Steel SIDERAR SIDMAR SOLLAC SSAB Stelco Sumitomo Tata Thyssen US Steel Group USIMINAS VSZ VOEST-ALPINE WCI Weirton Engineering Services, Inc. ULSAB Final Report Table of Contents Preface 1. Executive Summary 2. Phase 2 Introduction 2.1. 2.2. 2.3. 2.4. 2.5. 2.6. 2.7. Phase 2 Program Goal Phase 2 Design and Analysis Demonstration Hardware (DH) Scope of Work Materials Testing of Test Unit Phase 2 Program Timing 3. ULSAB Phase 2 Package 3.1. General Approach 3.2. Package Definition 3.2.1. Vehicle Concept Type 3.2.2. Exterior Dimensions 3.2.3. Interior Dimensions 3.2.4. Main Component Definition 3.2.5. Underfloor Clearance 3.2.6. Seating Position 3.2.7. Visibility Study 3.2.7.1. Horizontal and Vertical Obstruction 3.2.7.2. A-Pillar Obstruction 3.2.8. Gear Shift Lever Position 3.2.9. Pedal Position 3.2.10. Bumper Height Definition 3.3. Package Drawings Table of Contents - Page 1 Engineering Services, Inc. 4. Styling 4.1. Approach 4.2. 2-D Styling Phase 4.2.1. Sketching 4.2.2. Clinic 4.2.3. Electronic Paint 4.2.4. Styling Theme Selection 4.3. 3-D Styling Model 4.3.1. Surface Release 4.4. Rendering 5. Design and Engineering 5.1. Phase 2 Design and Engineering Approach 5.2. Design and Engineering Process 5.3. ULSAB Phase 2 Design Description 5.3.1. Parts List – Demonstration Hardware 5.3.2. ULSAB Structure Mass 5.3.3. ULSAB Demonstration Hardware Mass 5.3.4. Mass of Brackets and Reinforcements – Phase 2 5.3.5. ULSAB Structure Mass Comparison Phase 1 – Phase 2 5.3.6. DH Part Manufacturing Processes 5.3.7. Material Grades 5.3.8. Material Thickness 5.4. Detail Design 5.4.1. Weld Flange Standards 5.4.1.1. Weld Flanges for Spot or Laser Welding 5.4.1.2. Scalloped Spot Weld Flanges 5.4.1.3. Locator, Tooling and Electrophoresis Holes 5.4.2. Design Refinement Table of Contents - Page 2 Engineering Services, Inc. 6. CAE Analysis Results 6.1. Selected Tests for CAE 6.2. Static and Dynamic Stiffness 6.2.1. Torsional Stiffness 6.2.2. Bending Stiffness 6.2.3. Normal Modes 6.3. Crash Analysis 6.3.1. AMS Offset Crash 6.3.2. NCAP 100% Frontal Crash 6.3.3. Rear Crash 6.3.4. Side Impact Analysis 6.3.5. Roof Crush (FMVSS 216) 6.4. CAE Analysis Summary 7. Materials and Processes 7.1. Material Selection 7.1.1. Material Selection Process 7.1.2. Definition of Strength Levels 7.1.3. Supplier Selection 7.2. Material Specifications 7.2.1. General Specifications 7.2.2. Material Classes 7.2.2.1. 7.2.2.2. 7.2.2.3. 7.2.2.4. 7.2.3. 7.3. Tailor 7.3.1. 7.3.2. 7.3.3. Mild Steel Definition High Strength Steel Definition Ultra High Strength Steel Definition Sandwich Material Definition Material Documentation Welded Blanks Selection of Welding Process Weld Line Layout Production Blank Layout Table of Contents - Page 3 Engineering Services, Inc. 7.4. Hydroforming 7.4.1. General Process Description 7.4.2. Benefit for the Project 7.4.3. Forming Simulation (Review) 7.4.4. Tube Manufacturing 7.4.5. Process Steps for Rail Side Roof 7.4.6. Results 7.5. Hydromechanical Sheet Forming 7.5.1. General Process Description 7.5.2. Benefit for the Project 7.5.3. Process Limitations 7.5.4. Results 8. Parts Manufacturing 8.1. 8.2. 8.3. 8.4. Supplier Selection Simultaneous Engineering Part Manufacturing Feasibility Quality Criteria 9. DH Build 9.1. Introduction 9.2. Joining Technologies 9.2.1. Laser Welding 9.2.2. Spot Welding 9.2.3. Active Gas Metal Arc Welding (MAG) 9.2.4. Adhesive Bonding 9.3. Flexible Modular Assembly Fixture System 9.4. Design of Assembly Fixtures 9.5. DH Build 9.5.1. Assembly Team 9.5.2. Build of the Test Unit 9.5.3. Build of DH #2 to DH #13 Table of Contents - Page 4 Engineering Services, Inc. 9.6. Quality 9.6.1. Body Quality Control Team 9.6.2. Quality Control Measurements of DHs 9.7. Conclusion 10. Testing and Results 10.1. Scope of Work 10.2. Targets 10.3. Static Rigidity 10.3.1. Test Setup 10.3.1.1. General 10.3.1.2. Static Torsion 10.3.1.3. Static Bending 10.3.2. Results 10.3.2.1. Static Torsion 10.3.2.2. Static Bending 10.4. Modal Analysis 10.4.1. Test Setup 10.4.2. Results 10.5. Masses in Test Configuration 10.6. Summary 11. Economic Analysis 11.1. Introduction 11.2. The Process of Cost Estimation 11.2.1. Overview 11.2.2. Cost Model Algorithm Development 11.2.3. General Inputs 11.2.4. Fabrication Input 11.2.5. Assembly Input 11.3. Cost Model Description Table of Contents - Page 5 Engineering Services, Inc. 11.4. ULSAB Cost Results 11.4.1. Overall Cost Results 11.4.2. Cost Breakdown for Fabrication 11.4.3. Cost Breakdown for Assembly 11.4.4. Cost Analysis for New Technologies and Materials 11.4.5. Sensitivity Analysis 11.5. Body Structure – Comparative Study 11.5.1. Overview 11.5.2. Assumptions 11.5.3. Overall Results 11.6. Conclusion NOTE: The cost models may be found on the Porsche ULSAB Phase 2 CD ROM Version 1.0.2. 12. Summary of Phase 2 Results ULSAB Final Report Appendix Table of Contents NOTE: The following information is located on the Porsche ULSAB Phase 2 CD ROM Version 1.0.2. 1. Parts Book 1.1. 1.2. 1.3. 1.4. 1.5. Exploded View Index – Parts Book Sheets Parts Book Sheets Index – Parts book, Brackets & Reinforcements Parts Book Sheets – Brackets & Reinforcements Table of Contents - Page 6 Engineering Services, Inc. 2. Part Drawings 2.1. 2.2. 2.3. 2.4. Exploded View Parts List – Sorted by Part Number Parts List – Sorted by Material Grade Part Drawings 3. Typical Sections 3.1. Overview Illustration 3.2. Index – Typical Sections 3.3. Typical Section Sheets 4. Assembly 4.1. 4.2. 4.3. 4.4. 4.5. 4.6. 4.7. Assembly Tree Index –Weld Assemblies Weld Assembly Drawings Assembly Sequence Illustrations Index – Bolted and / or Bonded Assemblies Assembly Drawings, Bolted and / or Bonded Parts Assembly Illustrations – Bolted and / or Bonded Parts 5. Package Drawings 5.1. Side View 5.2. Plan View 5.3. Front & Rear View 6. Economic Analysis 6.1. Assembly System Data 6.2. Stamping Process Sheets Table of Contents - Page 7 Engineering Services, Inc. Preface In 1994, the steel industry, through the Ultra Light Steel Auto Body Consortium (ULSAB), commissioned Porsche Engineering Services, Inc. (PES) to conduct a concept phase (Phase 1) of the ULSAB project to determine if a substantially lighter steel body structure could be designed. In September 1995, worldwide auto industry attention was focused on the study when the results of Phase 1 were announced. The results also affected the growth of the ULSAB Consortium to 35 member steel companies, representing 18 nations worldwide. Encouraged by the results of Phase 1, the ULSAB Consortium once again commissioned PES to continue with Phase 2, the validation of the Phase 1 concepts, culminating in the build of the demonstration hardware. Phase 2 proved that the weight reduction, predicted in Phase 1, could be achieved. The use of high strength steels, tailor welded blanks, hydroforming and laser welding in assembly were particular challenges to overcome in Phase 2. ULSAB Consortium members committed themselves to supplying all steel materials, as well as the tailor welded blanks and raw materials for hydroforming, for all parts to be manufactured. The focus of Phase 2 was the same as in Phase 1, i.e., weight reduction without compromising safety or structural performance. Without altering the aggressive targets for mass and structural performance, the safety requirements were increased in Phase 2 in response to growing industry and government concern for increased auto safety. It was imperative to keep up with safety requirement changes that occurred during the course of the program, which ran from spring 1994 to spring 1998. As a result, it was necessary to analyze the ULSAB structure for offset crash behavior. With this new challenge, and valuable input gathered in discussions with OEMs during the presentation of Phase 1 findings, PES and the ULSAB Consortium commenced Phase 2. Preface - Page 1 Engineering Services, Inc. Phase 2 ended in Spring 1998 with the debut of the ULSAB demonstration hardware and will prove the Phase 1 concept to be not only feasible, but that performance targets will be exceeded by 60% for torsional rigidity, 48% for bending rigidity and 50% for the normal mode frequency. Relative to the benchmark average, mass reduction remained at 25%, while crash analysis showed excellent results for the selected crash analysis events, including the offset crash. As a result of Phase 2, the use of high strength steels in the ULSAB demonstration hardware structure has now increased to 90% relative to its mass. The trend toward using high strength steel and new technologies to reduce body structure mass while improving safety, can be seen already in recently launched cars. The new Porsche Boxster, for example, uses 30% high strength steel, as well as tailored blanking, hydroforming and laser welding in assembly. Cost analysis in Phase 1 was conducted by IBIS Associates under contract to the ULSAB Consortium. In Phase 2, a more detailed cost analysis study was conducted, under the supervision of PES with the support of ULSAB consortium member companies. With the detailed information provided with the concept validation in Phase 2, a new cost model was created and the cost to produce the ULSAB structure was analyzed. The results show that it is possible to reduce the mass of body structures without cost penalty. Preface - Page 2 Engineering Services, Inc. 1. Executive Summary Engineering Services, Inc. 1. Executive Summary Ultra Light Steel Auto Body (ULSAB) Phase 2 Introduction On behalf of an international Consortium of 35 of the world’s leading sheet-steel producers from 18 countries, Porsche Engineering Services, Inc. (PES) in Troy, Michigan, was responsible for the program management, design, engineering, and the building of the demonstration hardware (DH). In addition, PES conducted the economic analysis study for the Ultra Light Steel Auto Body (ULSAB) program. Program Goal The goal of the ULSAB program was to develop a light-weight body structure design that is predominantly steel. This goal included: • • • Providing a significant mass reduction based on a future reference vehicle Meeting functional and structural performance targets Providing concepts that will be applicable for future car programs Program Structure In order to achieve the above-mentioned goals the program was structured in three phases: • • • Phase 1 Concept Development (paper study) Phase 2 Concept Validation (build of demonstration hardware) Phase 3 Vehicle Feasibility (total vehicle prototype assembly and evaluation) Chapter 1 - Page 1 Engineering Services, Inc. Phase 1 – Concept In September 1995, the results of Phase 1 were published. In this phase, the ULSAB program concentrated on developing design concepts for light-weight body structures and validating crashworthiness. Based on benchmarking data, the performance of a future reference vehicle was predicted and the structural performance targets for the ULSAB structure, excluding doors, rear deck lid, hood and front fenders were established. Because the ULSAB program focuses on mass reduction, a much more aggressive target was set for mass than for the other structural performance targets. These targets were: Performance ULSAB Targets* Mass [ 200 kg Future Reference Vehicle Prediction 250 kg Static torsional rigidity m 13000 Nm/deg 13000 Nm/deg Static bending rigidity m 12200 N/mm 12200 N/mm m 40 Hz 40 Hz First body structure mode * All targets were set for body structure with glass, except the target for mass For the concept validation, the following crash analysis was performed in Phase 1: • • • • NCAP, 100% frontal crash at 35 mph Rear moving barrier crash at 35 mph (FMVSS 301) EEVC, side impact crash at 50 km/h (with rigid barrier) Roof crush (FMVSS 216) The analytical results of Phase 1 were: Performance Phase 1 Results* Mass Static torsional rigidity 205 kg 19056 Nm/deg Static bending rigidity First body structure mode 12529 N/mm 51 Hz *Structural performance results were calculated with glass; the mass excludes glass Chapter 1 - Page 2 Engineering Services, Inc. With the exception of mass, the results exceeded the targets. Mass was calculated at 205 kg and slightly above the aggressive target of 200 kg. An independent cost study indicated that, based on a North American manufacturing scenerio, the Phase 1 concept could cost less to produce than comparable current vehicle structures. This result, based on the relatively low level of detail of the ULSAB Phase 1 concept, indicated that a light weight structure could make substantial use of high strength steel, tailor welded blanks, laser welding in assembly, and hydroforming, and end up in the cost range of structures of similar size using a more conventional approach at a higher mass. Phase 2 - Validation The Phase 1 design concept and its structural and crash performance results having had a relatively low mass, provided an excellent foundation for Phase 2 of the ULSAB program. Based on the success of this Phase 1 paper study, and the positive recognition by OEMs around the world, the ULSAB Consortium commissioned PES to undertake Phase 2 starting in November 1995. The overall goal of Phase 2 was the validation of Phase 1 results, culminating in the build of the ULSAB demonstration hardware structure. The tasks and responsibilities of Phase 2 for PES, besides the program management, were to manage the necessary detail design, engineering, crash analysis, material selection, design optimization for manufacturing, supplier selection for parts and to assemble, test and deliver the demonstration hardware to the ULSAB Consortium. In addition, PES was responsible for a detailed cost analysis based on the Phase 2 detailed design. Chapter 1 - Page 3 Engineering Services, Inc. Crash Analysis During the course of the ULSAB program after the start in Spring 1994, the public demanded increased vehicle safety, and governments reacted with new requirements for crashworthiness. Therefore, the decision was made prior to the beginning of Phase 2, to analyze and to design the ULSAB structure for offset crash. This would enhance the credibility of the results. The AMS (Auto Motor Sport) 50% offset frontal crash at 55 km/h was considered the most severe test at that time and would represent the structural requirements an offset crash demands. This test was then added to the Phase 1 previously selected crash analysis events. For side impact crash analysis, a deformable barrier was used instead of the rigid barrier as used in Phase 1. The following crash analysis was performed in Phase 2: • • • • • AMS, 50% frontal offset crash at 55 km/h NCAP, 100% frontal crash at 35 mph (FMVSS 208) Side impact crash at 50 km/h (96/27 EG, with deformable barrier) Rear moving barrier crash at 35 mph (FMVSS 301) Roof crush (FMVSS 216) All crash calculations indicate excellent crash behavior of the ULSAB structure, even at speeds that exceed federal requirements. The front and rear impacts were run at 5 mph above the required limit, meaning 36% more energy had to be absorbed in the frontal impact. The offset crash also confirmed the overall integrity of the structure. The roof crush analysis validated that the federal standard requirement was met, partialy due to the hydroformed side roof rail concept design. Package At the start of Phase 2, as a result of various discussions with OEMs during the presentation of Phase 1 results, the ULSAB package was re-examined. In order to make the results of Phase 2 more credible, the decision was made not to consider secondary mass savings. This resulted in significant changes in several areas of the body structure. Chapter 1 - Page 4 Engineering Services, Inc. The relatively small engine specified in Phase 1 was replaced by an average size 3-liter V6, necessitating a complete redesign of the front-end structure, including a revised front suspension layout and subframe design. The rear suspension also was revised and the rear rails redesigned accordingly. Essentially, the whole structure was redesigned, from front to rear bumper, but it still maintained the structure features as developed in Phase I, such as the side roof rail and the smooth load flow concept of front and rear rails into the rocker. Styling Using the revised package and the adjusted body structure design, styling the ULSAB was the next challenge. Styling became necessary to create the surfaces for the body side outer panel with its integrated exposed rear quarter panel, the windshield, the backlight and the roof panel. The styling concept for the greenhouse had to consider, in order to integrate, the side roof rail, as well as the overlapping upper door frame concept. This door concept was chosen mainly for cosmetic reasons; to cover the visible weld seams, in the upper door opening area of the body side outer panel which were caused by the tailor welded blank design of the body side outer panel. For the overall styling approach, the decision was made to create a neutral, not too futuristic or radical, more conservative styling. Styling was the first major milestone in Phase 2 and was performed entirely by computer-aided styling (CAS). Design and Engineering After the exterior styling was created, the package was then optimized and the design modified accordingly. The implication of any design change was assessed by modifying the Phase 1 static analysis model. Design changes resulting as an outcome of the analysis were then incorporated into the styling and the package. With the performance targets met, styling and the Phase 2 package were frozen, and with a more detailed Phase 2 design, a new shell model for the structural performance analysis was created. Static analysis was then used to optimize the Chapter 1 - Page 5 Engineering Services, Inc. Phase 2 design until the requirements were met and new crash analysis models were built. In the process of design optimization, which included material grade and thickness selection, both static analysis and crash analysis were performed with constantly updated models until the targets were met. Throughout this process, simultaneous engineering provided input from the tool and part suppliers, as well as from steel manufacturers, to ensure the manufacturing feasibility of the designed parts. As a result of the simultaneous engineering process, only minor design and tool changes were needed after the drawings were released. When the first part set was completed, a workhorse (test unit) was built. The validation of the test unit lead to further part optimization and, finally, to the build of demonstration structures. Suppliers At the start of the detail design process in Phase 2, suppliers for stamped and hydroformed parts were selected in order to be included in the simultaneous engineering process. Among the selection criteria were quality, experience, skills and location. Supplier flexibility and their willingness to explore new manufacturing methods, utilizing material grades rarely used in these applications and to “push the envelope” in the application of tailor welded blanks or in hydroforming technologies, were as important in the selection process as their cost competitiveness. Steel Materials • Steel Grades Perhaps the most important factor in meeting the targets for mass and crash performance is high strength steel. More than 90% of the ULSAB structure utilizes high strength and ultra high strength steel. High strength steels are applied where the design is driven by crash and strength requirements. Ultra high strength steels with yield strength of more than 550 MPa are used for parts to provide additional strength for front and side impact. High strength and ultra high strength steel material specifications range from 210 to 800 MPa yield strength with a thickness range from Chapter 1 - Page 6 Engineering Services, Inc. 0.65 to 2 mm. With the restriction of lower elongation, different forming characteristics and greater spring back of high strength steels, material supplier support combined with forming simulations were important factors in meeting the challenges for the development of manufacturable part designs. • Steel Sandwich Material The use of steel sandwich material has contributed to considerable mass savings. The sandwich material is made with a thermoplastic (polypropylene) core, with a thickness of 0.65 mm and is layered between two thin steel skins, each with a thickness of 0.14 mm and yield strength of 240 MPa for the spare tire tub and 140 MPa for the dash panel insert. The steel sandwich shares many of the same processing possibilities of sheet steel, such as deep drawing, shear cutting, drilling, bonding, and riveting. However, it cannot be welded. Parts manufactured from steel sandwich material can be up to 50% lighter than those made of sheet steel with similar dimensional and functional characteristics. The spare tire tub made of steel sandwich material is a pre-painted module that is preassembled with the spare tire and repair tools. The module is dropped into place and bonded to the structure during the final assembly of the vehicle. Another application of sandwich material is the dash panel insert, which is bolted and bonded into the body structure, during final vehicle assembly. Tailor Welded Blanks Tailor welded blanks enable the engineers to accurately locate the steel within the part precisely where its attributes are most needed, while at the same time allowing for the elimination of mass that does not contribute to performance. Other benefits of tailor welded blanks include the use of fewer parts, dies and joining operations, as well as improved dimensional accuracy through the reduction of assembly steps. Nearly half (45%) of the ULSAB demonstration hardware mass consists of parts manufactured using laser welded tailored blanks. Chapter 1 - Page 7 Engineering Services, Inc. The best example of tailor welded blank usage is the body side outer panel. It employs a fully laser welded tailored blank with different thicknesses and grades of high strength steel. Careful placement of the seams in the tailor welded blank is critical in order to minimize mass and facilitate forming. This consideration was especially important in the body side outer panel because of its complexity and size, its use of high strength steels and the integration of the rear quarter panel with its Class A surface requirement. Mass reduction and the elimination of reinforcements were key goals in the development of this one-piece design. The consolidation of parts reduced mass and assembly steps. Hydroforming • Tubular Hydroforming The use of hydroforming should be considered as one of the most significant manufacturing processes applied in the ULSAB program for part manufacturing. The hydroformed side roof rail represents a significant structural member in the ULSAB structure. The side roof rail distributes loads appearing in the structure during vehicle operation, and in the event of an impact, distributes loads from the top of the A-pillar along the roof into B and C-pillar and then into the rear of the structure. The hydroformed side roof rail reduces the total number of parts and optimizes available package space. The raw material used to manufacture the side roof rail is a laser welded, high-strength steel tube 1 mm thick with an outside diameter of 96 mm and a yield strength of 280 MPa. The design was optimized and analyzed for feasibility using forming simulation. • Hydromechanical Sheet Forming The use of hydromechanical sheet forming was chosen for the roof panel for mass reduction reasons. This process provided the opportunity to manufacture the roof panel at a thinner material thickness and still achieve a work-hardening effect in the center area, where the degree of stretch is normally minimal and an increased material thickness is needed to meet dent resistance requirements. With hydro-mechanical sheet forming, this Chapter 1 - Page 8 Engineering Services, Inc. work-hardening effect is achieved by using fluid pressure to pre-stretch the blanks in the opposite direction towards the punch. This plastic elongation causes a work-hardening effect in the center area of the blank. In the second step, the punch forms the panel towards controlled fluid pressure and because there is no metal-to-metal contact on the outer part surface, excellent part quality is achieved. The ULSAB roof panel is manufactured in 0.7 mm high strength steel with a yield strength of 210 MPa. Tooling All tools for stamped parts are “soft” tools made of materials such as kirksite and built to production intent standards. Tools used for hydroforming are “hard” tools made of steel. In both cases, part manufacturing tolerances and quality standards were the same as those used in high-volume production. DH Assembly • Joining Technologies For the final assembly of the ULSAB structure, four types of joining technologies were applied. Spot welding is used for joining the majority of parts. Laser welding became necessary to join the hydroformed side roof rail to its mating parts. In addition, the rails in the front end structure are laser welded for improved structural performance. Laser welding in body structure assembly is already being used in mass production by many OEMs. The active gas metal arc welding (MAG) process, with its disadvantages, such as slow welding speed and relatively large heat impact zones, was kept to a minimum and used only in locations with no weld access for spot or laser welding. Bonding is used to join the sandwich parts that cannot be spot or laser welded into the structure. For the joining of the DH, about one-third fewer spot welds and significantly more laser welding is employed than for conventional body structures. Chapter 1 - Page 9 Engineering Services, Inc. • Assembly Sequence For the DH build, the assembly sequence uses two stage body side framing. The assembly sequence includes underbody assembly, body side assemblies, roof and rear panel assemblies. All DHs were built in a single build sequence. • Assembly Fixtures To assemble the DH, a modular fixture system was used. The fixtures were developed in a CAD system and the positions of locator holes were then incorporated into the parts design. DH Testing Testing was performed on the ULSAB test unit structure to validate its structural performance and mass. Included were tests for static torsion rigidity, static bending rigidity, modal analysis and mass in various configurations, including some bolt-on parts. Testing was performed at Porsche’s Research & Development Center in Weissach, Germany. Physical testing for crash was not part of the ULSAB program in Phase 2 and may be performed in a possible Phase 3, after the necessary components are built and/or assembled into the ULSAB structure. Economic Analysis With the detailed information created in Phase 2 of the ULSAB program, the costs of parts and assembly of the body structure were analyzed. Under the management of a PES’ team, and with support from the ULSAB Consortium members, an economic analysis group, comprising of analysts from the Massachusetts Institute of Technology (MIT), IBIS Associates and Classic Design, a detailed cost model was constructed that includes all aspects of fabrication and assembly. This cost model will enable the automotive OEMs to calculate ULSAB cost based on their own manufacturing criteria. Considering that the focus of Phase 2 was on mass reduction and not on cost savings, the result of this cost analysis is quite remarkable. It confirms that significant mass reduction of the body structure, in Chapter 1 - Page 10 Engineering Services, Inc. comparision to the benchmark vehicle average mass, was achieved with the use of steel with no cost penalty. Summary/Conclusion Throughout Phase 2, timely execution of the program was critical. All parts designed and released to our suppliers and all tooling and assembly of the first test unit have been on schedule. With the data acquired from the validation of the first test unit and subsequent testing, parts were refined and design optimization was performed. Refined parts were then used to build the demonstration hardware. Based on the testing of the demonstration hardware, the ULSAB structure shows Performance* Mass Target Results [ 200 kg 203 kg Static torsional rigidity m 13000 Nm/deg 20800 Nm/deg Static bending rigidity m 12200 N/mm 18100 N/mm m 40 Hz 60 Hz First body structure mode *Structural performances are test results with glass. ULSAB structure mass without glass the following structural performances: Achieving these results in a timely manner could only be achieved by utilizing the team approach that involved all parties in the early stages of the ULSAB program. A close working relationship with the ULSAB Consortium members and the commitment of our suppliers and their enthusiasm for the program helped to meet the challenge of manufacturing parts made of steel materials and combinations that have not been commonly applied previously. This “pioneering spirit” was carried on by all members of the PES team, including designers and engineers. The ULSAB program has explored the potential for mass reduction in the body structure using steel as the chosen material. State-of-the-art manufacturing and joining technologies, such as laser welding in assembly and hydroforming as well as commercially available materials, contributed to the success of the ULSAB program. It proves that steel offers the potential for light weight vehicle design which contributes to the preservation of resources and the reduction of emissions. Based on this experience, the steel industry should further intensify its dialogue and cooperation with OEMs to achieve their common goal of mass reduction of tomorrow’s vehicles, to protect the environment and to secure mobility of future generations. Chapter 1 - Page 11 Engineering Services, Inc. 2. Phase 2 Introduction Engineering Services, Inc. 2. Phase 2 Introduction 2.1. Phase 2 Program Goal The program goal of Phase 2 was the validation of Phase 1 results and the build of demonstration hardware. Phase 1 was the concept phase and consisted of concept design and analysis. The design was basic wire frame and surface data, without holes for drainage or locators for assembly. The Phase 1 analysis, based on the design concept, was meshed in its basic form to reflect the surfaces of the structure. 2.2. Phase 2 Design and Analysis The design in Phase 2 was a refinement of the Phase 1 design. It includes surface data, allowing for production of tools including principal location points (PLP) and holes for tooling, drainage and weld access. Additionally, refinement of the design for manufacture and assembly (DFMA) was developed as the final design progressed, with emphasis on mass production (more than 100,000 units per year). The intention in Phase 2 was to continue the development of a “generic” structure that takes into consideration manufacturing and assembly methods. With the detailed design of the structural components, and assemblies, and with materials selected, build specifications and the final assembly sequence were established. Chapter 2 - Page 1 Engineering Services, Inc. Computer Aided Engineering (CAE) continued in Phase 2 in conjunction with the refinement of the design. The analysis provided confirmation of the design as well as structural and crash performance. The CAE analysis in Phase 2 included: • • Finite Element Model Modification Structural Analysis consisting of: w Mass w Static Torsion w Static Bending w Modal Analysis Continuing development of crash simulation concentrates on: • • • • • AMS, 50% frontal offset crash at 55 km/h NCAP, 100% frontal crash at 35 mph (FMVSS 208) Side impact crash at 50 km/h (96/27 EG, with deformable barrier) Rear moving barrier crash at 35 mph (FMVSS 301) Roof crush (FMVSS 216) All models were continuously updated to compare Phase 2 and Phase 1 results in order to maintain the same performance standards. 2.3. Demonstration Hardware (DH) The term “demonstration hardware” is used to emphasize that the body structure is not a prototype but a legitimate representation of a production unit. All demonstration hardware components had to be fully tooled (soft tools for stamping and hard tools for hydroforming). All demonstration hardware was built in a single build sequence. The completed structure had to be “clear-coat” painted for unrestricted view of the build and construction methods. Chapter 2 - Page 2 Engineering Services, Inc. 2.4. Scope of Work Porsche Engineering Services, Inc. in Troy, Michigan executed the program. The DH build, testing and the CAE analysis was performed at the Porsche R & D Center in Weissach, Germany. To achieve the targets for performance, timing and cost, the program responsibilities of PES included the following tasks: • • • • • • • • • Program Management and Planning Build Management for the Construction of the Demonstration Hardware Build of Demonstration Hardware Part Supplier/Manufacturer Evaluation and Selection Component Structure Design and Engineering CAE Analysis Physical Testing of Test Unit Economic Analysis Study Final Program Report 2.5. Materials The ULSAB Consortium member companies provided all material-specific data required to design, develop and construct the ULSAB body structure in Phase 2. All materials used to manufacture parts for the DH build were provided to Porsche by ULSAB Consortium member companies including the tailor welded blanks and raw material (tubes) for the manufacturing of the hydroform side roof rail. In addition, the individual ULSAB Consortium member companies supported the program with data related to material selection and tailor welded blank development, as well as forming simulation and circle grid analysis on selected parts in order to create a feasible part design. Chapter 2 - Page 3 Engineering Services, Inc. 2.6. Testing of Test Unit Physical testing was undertaken on the test unit to provide data and allow correlation of the CAE results with regard to: • • • • Mass Static Torsion Static Bending Modal Analysis Physical crash testing was not part of Phase 2. This could be executed in a possible Phase 3, with the necessary components, such as suspension, powertrain, and interior available. 2.7. Phase 2 Program Timing Prior to the start of Phase 2 the program timing was established and the various tasks assigned. Based on this timeline the ULSAB Consortium established specific information release dates to keep Chapter 2 - Page 4 Engineering Services, Inc. ULSAB Phase 2 Program Timeline Task Name 1996 Q4 Q1 Q2 Q3 1997 Q4 Q1 Q2 Q3 Package Refinement Styling (CAS) Class A Surfacing Design & Engineering Economic Analysis CAE Analysis Design Changes CAE Analysis (Iteration 1) Design Changes CAE Analysis (Iteration 2) Design Changes CAE Analysis (Iteration 3) Release Long Lead Items Tooling Test Unit Build Testing Design Changes CAE Validation Tooling Adjustments DH Build Chapter 2 - Page 5 1998 Q4 Q1 Q2 Engineering Services, Inc. 3. ULSAB Phase 2 Package Engineering Services, Inc. 3. ULSAB Phase 2 Package 3.1. General Approach Discussions with OEMs about Phase 1 findings provided valuable input and guidance for the more detailed Phase 2 package layout created at the start of Phase 2. The Phase 2 package was defined as a modification of the Phase 1 package without being too specific so the package findings could apply to more than one body structure concept. The most important components, space definitions and dimensions had to be considered by either defining them using engineering judgment, or by using actual component dimensions. Furthermore, secondary mass savings were not considered in order to take a more conservative and more credible approach. This is also reflected in component size and mass, as well as in the crash mass used for the crash analysis. 3.2. Package Definition The first step in the package phase was to define the vehicle concept type, exterior dimensions, interior dimensions and the main components. With these package definitions, package drawings were revised and structural hard points defined. 3.2.1. Vehicle Concept Type In Phase 2 the same concept type definition was used as in Phase 1, five passenger and four door midsize sedan. Chapter 3 - Page 1 Engineering Services, Inc. 3.2.2. Exterior Dimensions Ident.* Definition Measurements W101 Tread - front 1560 mm W102 Tread - rear 1545 mm W103 W117 Vehicle width Body width at SgRP - front 1819 mm 1767 mm L101 Wheelbase 2700 mm L103 Vehicle length 4714 mm L104 Overhang - front 940 mm L105 Overhang - rear 1074 mm L114 L123 Front wheel centerline to front SgRP Upper structure length 1447 mm 2631 mm L125 Cowl point - X coordinate 2016 mm L126 Front end length 1281 mm L127 Rear wheel centerline - X coordinate 4295 mm L128 Front wheel centerline - X coordinate 1595 mm L129 H101 Rear end length Vehicle height 654 mm 1453 mm H106 Angle of approach 14° H107 Angle of departure 15° H114 Cowl point to ground 1001 mm H121 Backlight slope angle 61° H122 H124 Windshield slope angle Vision angle to windshield upper DLO 59° 15° H136 Zero Z plane to ground - front 112 mm H138 Deck point to ground 1091 mm H152 Exhaust system to ground 170 mm H154 Fuel tank to ground 188 mm H155 Spare tire well to ground 311 mm *SAE J1100 Revised May 95 Chapter 3 - Page 2 Engineering Services, Inc. 3.2.3. Interior Dimensions Ident.* Definition Measurements W3 Shoulder room - front 1512 mm W4 Shoulder room - second 1522 mm W5 W6 Hip room - front Hip room - second 1544 mm 1544 mm W7 Steering wheel center - Y coordinate 350 mm W9 Steering wheel maximum outside diameter 370 mm W20 SgRP - front - Y coordinate 350 mm W25 SgRP - second - Y coordinate 335 mm W27 W33 Head clearance diagonal - driver Head clearance diagonal - second 79 mm 83 mm W35 Head clearance lateral - driver 136 mm W36 Head clearance lateral - second 132 mm L7 Steering wheel torso clearance 418 mm L11 Accelerator heel point to steering wheel center 412 mm L13 L30 Brake pedal knee clearance Front of dash - X coordinate 573 mm 1942 mm L32 SgRP - second to rear wheel centerline 473 mm L34 Effective leg room - front 1043 mm L38 Head clearance to windshield garnish - driver 266 mm L39 Head clearance to backlite garnish 21 mm L40 L41 Torso (back) angle - front Torso (back) angle - second 25° 25° L42 Hip angle - front 93° L43 Hip angle - second 86° L44 Knee angle - front 118° L45 Knee angle - second 88° L46 L47 Foot angle - front Foot angle - second 78° 113° L50 SgRP couple distance 780 mm L51 Effective leg room - second 894 mm L52 Brake pedal to accelerator 48 mm L53 SgRP - front to heel 832 mm *SAE J1100 Revised May 95 Chapter 3 - Page 3 Engineering Services, Inc. 3.2.3. Interior Dimensions (Cont’d) Ident.* Definition Measurements H5 SgRP - front to ground 519 mm H6 SgRP - front to windshield lower DLO 495 mm H10 H11 SgRP - second to ground Entrance height - front 529 mm 798 mm H12 Entrance height - second 810 mm H13 Steering wheel to centerline of thigh 67 mm H14 Eyellipse to bottom of inside rearview mirror 40 mm H17 Accelerator heel point to steering wheel center 645 mm H18 H25 Steering wheel angle Belt height - front 23° 446 mm H26 Interior body height - front at zero Y plane 1011 mm H27 Interior body height - front at SgRP Y plane 1220 mm H29 Interior body height - second at SgRP Y plane 1033 mm H30 SgRP - front to heel 245 mm H31 H32 SgRP - second to heel Cushion deflection - front 303 mm 49 mm H33 Cushion deflection - second 66 mm H35 Vertical head clearance - driver 75 mm H36 Head clearance vertical - second 49 mm H37 Headlining to roof panel - front 7 mm H38 H40 Headlining to roof panel - second Steering wheel to accelerator heel point 7 mm 468 mm *SAE J1100 Revised May 95 Chapter 3 - Page 4 Engineering Services, Inc. 3.2.3. Interior Dimensions (Cont’d) Ident.* Definition Measurements H41 Minimum head clearance - driver 88 mm H42 Minimum head clearance - second 21 mm H49 H50 Eyellipse to top of steering wheel Upper-body opening to ground - front 17 mm 1317 mm H51 Upper-body opening to ground - second 1339 mm H53 D-point - front to heel 137 mm H54 D-point - center passenger - front to tunnel 105 mm H55 D-point - center passenger - second to tunnel 43 mm H56 H57 D-point - front to floor D-point - second to floor 182 mm 72 mm H60 D-point to heel point - second 19 mm H61 Effective head room - front 1019 mm H63 Effective head room - second 972 mm H64 SgRP - front to windshield upper DLO 796 mm H69 H70 Exit height - second SgRP - front - Z coordinate 743 mm 631 mm H71 SgRp - second - Z coordinate 641 mm H75 Effective T-point head room - front 994 mm H76 Effective T-point head room - second 932 mm H77 Seatback height - front 868 mm H78 H94 Seatback height - second Steering wheel to cushion - minimum 781 mm 223 mm *SAE J1100 Revised May 95 Chapter 3 - Page 5 Engineering Services, Inc. 3.2.4. Main Component Definition Component Engine Description Remarks V6 Average size ~ 3000 ccm Engine Mounts Total of 3 2 on top of front rail 1 on subframe 2 Radiator Size .252 m Exhaust System Single routing, 1 catalytic converter, With single fan Vol 2.8 catalytic converter 21 ltr. muffler, LHS 1 muffler Battery L x W x H 280mm x 170mm x 170 mm LHS front of engine compartment Drive Train Transverse front wheel drive Transmission Automatic - manual G-shift for manual included in package Suspension Type, Front McPherson Mounted to front subframe Suspension Type, Rear Twist beam With separate spring Tire Size Front-Rear 195/60R15 Winter tires 185/60R15 Spare Tire Fuel Tank volume Space saver ~65 ltr Tub to fit full size tire Located under rear seat Fuel Filler On RHS Routing in package Bumper Front-Rear Bolt-on Crash boxes included Steering Rack & pinion Steering rack housing on Cargo Volume 490 ltr VDA method with 200 x 100 x 50 mm module Weld through type shock absorber top of crossmember dash Hinges Similar to Porsche 911 / Boxster Head Lamps Part of front end module Interior Front and rear seat concept In package drawing Cockpit Basic concept with I/P beam In package drawing Pedals Unit with integrated foot-parking-brake In package drawing Chapter 3 - Page 6 Engineering Services, Inc. 3.2.5. Underfloor Clearance The underfloor clearance of a vehicle depends on the vehicle load. The determination of the underfloor clearance relative to the road surface was crucial for the body structure design, styling, selection of components and their positioning in the vehicle structure. Underfloor clearance is defined as the summary of five different parameters. These are: • • • • • Curb Clearance Front / Rear Angle of Approach / Departure Ramp Brakeover Angle Oil Pan Clearance Ground Clearance To define these parameters, three vehicle positions, which then depended on three specific load cases, needed to be determined. The three load cases applied to the vehicle were: • Curb weight: The weight of a vehicle equipped for normal driving conditions. This includes fluids such as coolant, lubricants and a fuel tank filled to a minimum of 90%. Also included are the spare tire, tool kit, and car jack. • Design weight: Vehicle curb weight plus the weight of three passengers (68 kg each, with luggage 7 kg each) with 2 passengers in the front seat and 1 passenger in the rear seat. • Gross vehicle weight: Vehicle curb weight plus maximum payload (5 passengers plus luggage). Chapter 3 - Page 7 Engineering Services, Inc. To determine the vehicle position relative to the road surface under these load conditions, the vehicle is positioned relative to zero grid Z-plane. Z R1 A R2 B Ground X Figure 3.2.5-1 ULSAB Vehicle Position Relative to Zero Grid Z-Plane Using the ULSAB data and the weights of the three load cases, the road surface positions relative to the zero grid Z-plane and to the vehicle were calculated. ULSAB Data 5 Number of Seats 2700 mm Wheelbase Tires Front Rear 195/60-R15 195/60-R15 Front Rear 2.5 bar 2.5 bar Pressure Calculation of Road Surface Positions Relative to the Vehicle Distance from Static Tire Load Case Zero Grid Z-Plane Radius A (mm) B (mm) R1 (mm) R2 (mm) Curb Weight 395 392 301 308 Design Weight 413 417 301 305 Gross Vehicle Weight 415 462 303 300 Chapter 3 - Page 8 Weight 1350 kg 1575 kg 1850 kg Engineering Services, Inc. Gross Vehicle Weight Design Weight Curb Weight Figure 3.2.5-2 Road Surface Relative to Vehicle With the road surface positions relative to the vehicle, the underfloor clearance was determined. 170 mm 190 mm Gross Vehicle Weight Design Weight Figure 3.2.5-3 Curb Clearance Front/Rear 14º 15º Design Weight Figure 3.2.5-4 Angle of Approach/Departure Chapter 3 - Page 9 Engineering Services, Inc. 14º Gross Vehicle Weight Figure 3.2.5-5 Ramp Breakover Angle 185 mm Design Weight Figure 3.2.5-6 Oil Pan Clearance 143 m m Gross Vehicle W eight Figure 3.2.5-7 Ground Clearance Chapter 3 - Page 10 Engineering Services, Inc. 3.2.6. Seating Position At first the 2-D manikins (spelling taken from SAE) were aligned in a comfortable seating position taking into consideration the angles between joints such as hip, knee, and foot. When the seating position was defined, verification was made that the operating parts like steering wheel, gearshift lever and pedal were in reach. This was important for ergonomic reasons. Two types of 2-D manikins were used: The small female, 5th percentile with a height of 147.8 cm; and the tall male, 95th percentile with a height of 185.7 cm. (5th percentile means that 5% of the population is smaller or equal in size and 95% is taller. 95th percentile means that 95% of the population is smaller or equal in size and 5% is taller.) For the dash panel layout the tall male 2-D manikin was used because it is more difficult to reach, since the seat position of the taller person is more rearward than it is for a shorter person. Figure 3.2.6-1 Distance to Operating Parts of the 5% Female and the 95% Male Chapter 3 - Page 11 Engineering Services, Inc. 3.2.7. Visibility Study 3.2.7.1. Horizontal and Vertical Obstruction For the study of horizontal, vertical and A-pillar obstruction of the driver’s visibility, the following positions needed to be defined: • Seating Reference Point (SgRP) It was necessary to determine the seating reference point (SgRP) in order to position the eyellipse (spelling taken from SAE) template and the eyepoints V1 / V2. For adjustable seats, the SgRP is defined as the hippoint (H-Point) relative to the driving seat in its most rearward position. The H-point is defined as the pivot center of the torso and thigh center lines. Eyepoints V1, V2 Eyellipse Torso Line Thigh Centerline SgR-Point Accelerator Heel Point Figure 3.2.7-1 SgRP, Eyellipse, Eyepoints • Eyellipse (SAE J941) The eyellipse is a tool to describe the vision of a driver. The template with the eyellipse is positioned with its horizontal reference line 635 mm above the SgRP and with the vertical reference line through the SgRP. Two types of templates, with two eyellipses, take the different seat track travel Chapter 3 - Page 12 Engineering Services, Inc. ranges into consideration. For the ULSAB vehicle, with a seat track travel of 240 mm, a template for seat track travel of more than 130 mm was used. • Eye Points V1 / V2 (RREG 77/649) The coordinates of the eye points V1 / V2 relative to the SgRP were determined by using the following dimensions: Point X Y Z V1 68 -5 665 V2 68 -5 589 Using vision lines through the eye points, the following vision areas are described: Traffic Light Visio n Ang le min . 14º Wiperfie ld Angle 10º Transpare nt Winds cr een A rea 7º Through V 1 (77/649/ EWG) V1 Horizont View Through V1 Steering Wheel Rim Obscuration 1º Through V2 (77/649/EWG) (77/649/EWG) 4º Through V2 9/EWG) Unobstr uctedd Vis ion ugh V2 (77/64 ro Th 5º indscreen Area W t en ar sp Tran V2 Figure 3.2.7-2 Horizontal Vision Chapter 3 - Page 13 Engineering Services, Inc. Visio nA rea Visio n Ar ea B A2 0º ( 78/3 17 2 17º .2/E (78/3 WG 17 2 ) .3/E WG ) V1, V2 Y X WG) 2.2/E 8/317 ) 13º (7 A WG a Are .3/E 17 2 Vision /3 8 7 ( 17º ea B n Ar Visio Figure 3.2.7-3 Vertical Vision 3.2.7.2. A-Pillar Obstruction In order to determine the A-pillar obstruction, points P1 and P2 have to be determined first. The coordinates for these points related to the SgR-point are: Point X Y Z P1 35 mm -20 mm 627 mm P2 63 mm 47 mm 627 mm The ULSAB structure has a seat track travel of 240 mm. Therefore the X-value has to be corrected by -48 mm. Since the torso back angle is 25 degrees, no further correction is necessary for the X-value and Z-value. The new coordinates for the P-points are: Point X Y Z P1 -13 mm -20 mm 627 mm P2 +15 mm 47 mm 627 mm Chapter 3 - Page 14 Engineering Services, Inc. Y P2 +15 mm SgRP Pm +47 mm Horizontal Line -20 mm P1 -13 mm X Figure 3.2.7.2-4 Distance of the P-Points Relative to the SgR-Point Two planes are cutting the A-pillar in an angle of 2 and 5 degrees. In the front most intersection, the horizontal planes S1 and S2 cut the A-pillar (Figure 3.2.7-5). S1 S2 S1 Pm S2 2º 627 mm 5º SgRP Figure 3.2.7.2-5 Determination of the Sections S1 and S2 Chapter 3 - Page 15 Engineering Services, Inc. The sections in the plan view are shown in Figure 3.2.7-6. P2 Pm V1, V2 P1 S1 S2 Figure 3.2.7-6 Sections S1 and S2 in Plan View The point P1 is necessary to determine the A-pillar obscuration for the left side (for a left hand drive vehicle). P2 is necessary for the right side. If P1 fulfills the requirements, it is not necessary to determine the obscuration for the right A-pillar, since the right pillar is farther away from the driver. The template to determine the obstruction is shown in Figure 3.2.7-7. P1 m 1 04 m 65 mm E2 E1 er nn 1I S n c tio Se ter Ou 2 nS c tio Se α Figure 3.2.7-7 Template for A-Pillar Obstruction Chapter 3 - Page 16 Engineering Services, Inc. The point P1 on the template is aligned to the point P1 on the drawing. The line “Section S2 Outer” is laid tangent to the most outer edge of the A-pillar section (S2), including trim, door frame and door seal. The second tangent line “Section S1 inner” is laid to the most inner edge of the A-pillar section (S1), including trim, seal and dot matrix. (Figure 3.2.7-8). P1 1º Figure 3.2.7-8 Template in Position 3.2.8. Gear Shift Lever Postion The position of the gearshift lever depends on the SgRP-position and on the torso back angle. The position of the gearshift lever in the side view is shown in Figure 3.2.8-1. 220 mm m 0m 29 340 mm Figure 3.2.8-1 Distance of Gearshift Lever Relative to SgR-Point Chapter 3 - Page 17 Engineering Services, Inc. 3.2.9. Pedal Position 98 mm 58 mm ) ch 59 mm 53 mm t Clu ( ) ke Bra mm 50 ( mm 48 3m 20 Seating Reference Point m 201 mm 53 mm m m 89 Figure 3.2.9-2 Pedal Position Rear Figure 3.2.9-1 Pedal Position Side 3.2.10. Bumper Height Definition ECE R42 for the bumper height definition requires a pendulum 445 mm above the curb weight vehicle position and the design weight vehicle position. At the same time an overlapping of 35 mm of the pendulum to the bumper is required. C D A B Figure 3.2.10-1 Pendulum in the Extreme Height Position Chapter 3 - Page 18 Engineering Services, Inc. • • • • A: Lower edge of the pendulum in the most upper level to the curb weight vehicle position. B: Upper edge of the pendulum in the most lower level to the design weight vehicle position. C: Overlapping of the pendulum to the bumper in extreme high position. D: Overlapping of the pendulum to the bumper in extreme low position. A B C D Front 467 mm 431 mm 91 mm 40 mm Rear 467 mm 402 mm 89 mm 38 mm Chapter 3 - Page 19 Engineering Services, Inc. 3.3. Package Drawings Since package drawings are orthographic projections of the vehicle contour in side view, plan view, front view and rear view, these views include all essential parts of the interior such as seats, seat position, seating reference point (SgRP), operating parts and the door openings. To define the interior of the vehicle including the seat position, visibility, and obstruction by the pillars, roof, hood and deck lid positions were determined. It was also important to define positions of the steering wheel, pedals, and gearshift lever. Other criteria were visibility to the instrument panel, and head clearance to the front, top and side. In the engine compartment, the engine, gearbox, exhaust system, radiator and battery were used in defining the space for the structural members of the front body structure. Components such as the fuel tank with the fuel filler system, the catalytic converter and exhaust system, and spare tire tub were also included in the package drawings. The package drawings were the starting point for the Phase 2 design. Chapter 3 - Page 20 Figure 3.3.1-1 Packing Drawing Side View 3.3.1. Side View Engineering Services, Inc. Chapter 3 - Page 21 Figure 3.3.2-1 Package drawing Plan View 3.3.2. Plan View Engineering Services, Inc. Chapter 3 - Page 22 Figure 3.3.3-1 Package Drawing Front View 3.3.3. Front and Rear View Figure 3.3.3-2 Package Drawing Rear View Engineering Services, Inc. Chapter 3 - Page 23 Engineering Services, Inc. 4. Styling Engineering Services, Inc. 4. Styling 4.1 . Approach The Phase 1 concept design of the ULSAB program did not account for any Class A surfaces for the outer panels of the structure. To establish Class A surfaces in Phase 2, a complete styling of the ULSAB vehicle was necessary in order to create the surfaces of the roof panel, body side outer panel, the back light and the windshield. Styling also provided the major feature lines for the doors, deck lid, hood, fender and front and rear bumpers; these were needed for the development of the mating structural parts. For Phase 2, styling also gave the ULSAB structure a professional look and provided surfaces for further design studies in the future, i.e. on hoods, doors, deck lids, etc. The styling was developed electronically using CAS (computer aided styling), no clay models were used. With support from Porsche’s styling studio, PES selected A. D. Concepts, a local source, to carry out the computer aided styling in a simultaneous engineering approach with PES. At the first team meetings of PES and A. D. Concepts, several elements of the styling were discussed with a view to creating a 3-dimensional styling model. Using the package drawings, important criteria such as overall vehicle proportions, vision lines, bumper locations and proposed cut lines were specified. After the initial meetings, a clearly defined vehicle architecture had evolved. 4.2. 2-D Styling Phase 4.2.1. Sketching In a team review of the first sketches, a neutral styling approach was chosen to ensure the ULSAB styling model would not be too futuristic or radical. Traditional sketching techniques were used along with the latest electronic paint sketching software from the Alias|Wavefront company entitled StudioPaint running on Silicon Graphics High Impact workstations. Many automotive design studios around the world use this combination of hardware and software. The use of this tool for such a project increased productivity and enhanced the overall styling presentation with professionalism and accuracy, producing tighter sketches and more realistic, achievable styling goals. Chapter 4 - Page 1 Engineering Services, Inc. Figure 4.2.1-1 Styling Sketches Chapter 4 - Page 2 Engineering Services, Inc. 4.2.2. Clinic In the first clinic, dozens of sketches were reviewed by the design and styling team to determine which direction the styling would take prior to its presentation to the ULSAB Consortium. With the best sketches selected, five separate side view proposals and several different front and rear end treatments were developed. Figure 4.2.2-1 Side View Proposal 4.2.3. Electronic Paint In the studio, the CATIA package data was imported into a 3-D conceptual modeling software, called CDRS, and a side view outline drawing was developed for sketching purposes. The drawing was imported into StudioPaint and the five, very disciplined, side view sketch proposals (A-E) along with front and rear end sketch proposals were developed. Chapter 4 - Page 3 Engineering Services, Inc. 4.2.4. Styling Theme Selection The final styling theme selection was made during a meeting of the ULSAB Consortium’s editorial group, together with PES and A. D. Concepts. In a secret ballot, the editorial group members from all around the world selected styling theme A. With the selection of the specific front and rear end treatments for the 3-D model, the 2-D phase of the ULSAB styling reached its conclusion. Figure 4.2.4-1 Selected Styling Theme A Figure 4.2.4-2 Styling Theme B Chapter 4 - Page 4 Engineering Services, Inc. Figure 4.2.4-3 Styling Theme C Figure 4.2.4-4 Styling Theme D Figure 4.2.4-5 Styling Theme E Chapter 4 - Page 5 Engineering Services, Inc. Figure 4.2.4-6 Selected Front View Proposal Figure 4.2.4-7 Selected Rear View Proposal Chapter 4 - Page 6 Engineering Services, Inc. 4.3. 3-D Styling Model To create the 3-D styling model, the package data was imported into CDRS along with the selected theme drawing and then the first phase of the 3-D model commenced. Side view lines, created using 2-D spine curves, were developed to represent the major feature lines of the vehicle. Typical sections at specific X locations were constructed. This data was reviewed by the design team to verify the positions of these major curves. The construction of the greenhouse, (the upper glass and roof surfaces of the vehicle), was started, transferring preliminary surfaces back and forth between CDRS and CATIA using an IGES translator. In the following Class A surfacing using CATIA, only subtle design changes were made to the CDRS surface model until both the styling and engineering teams were comfortable with the result. The release of the styling data by the styling team, in IGES file format, marked the first step in the 3-D modeling phase. Next, body side lines were constructed and surfaces were created. With the wheel openings, and the front and rear stance developed, the model started to take shape. The team developed the best proposal for front and rear door cut lines and this information was then incorporated into the CDRS styling model. After the front and rear end surfaces were completed, shaded tile images of the surface model were used to evaluate the forms. Highlight sections and surface curvature graphs were used to verify the aesthetic value of the model. Chapter 4 - Page 7 Engineering Services, Inc. 4.3.1. Surface Release Prior to the official surface release, the styling was reviewed to establish the exact location of all cut lines and shut lines. Shaded tile model images, with highlight reflection lines, were created in CDRS to allow both styling and engineering to discuss potential areas of concern. With the final release of the IGES surface model, the 3-D modeling phase was complete. Figure 4.3.1- 1 Surface Release 4.4. Rendering After the release of the surface model, the CDRS model was prepared for rendering. Model colors were selected in texture maps created to enhance the overall appearance of the photo realistic rendering. Neutral backgrounds and specific views were selected to create the first ULSAB styling images. To incorporate subtle engineering changes in the model, the CDRS 3-D models were revised and additional renderings were created. The models were enhanced further by the addition of texture maps for items such as license plate and rear window defrost. The 3-D model was imported back into StudioPaint 3-D to examine styling changes to the front and rear lamp treatments. These changes were then incorporated into the CDRS 3-D model and the final renderings completed, which concluded the styling phase. Chapter 4 - Page 8 Engineering Services, Inc. Figure 4.4-1 Figure 4.4-2 Chapter 4 - Page 9 Engineering Services, Inc. 5. Design and Engineering Engineering Services, Inc. 5. Design and Engineering 5.1. Phase 2 Design and Engineering Approach After the package was revised and the styling frozen, the challenge in Phase 2 was to maintain the structural performances, especially the mass, as analyzed in the Phase 1 concept. Further research into steel sandwich material led to additional changes in the Phase 2 design. Because of restrictions in size and application of the material, new design solutions had to be created to compensate for the advantages in mass reductions using sandwich material as it was applied in Phase 1. The hydroformed parts were analyzed for manufacturing feasibility using the detailed design data created in Phase 2. The restrictions of the hydroforming process, in combination with the refinement of the design, led to different concepts, design adjustments, and new solutions to achieve the target for mass. Furthermore, the 50% off-set crash, an additional crash analysis introduced in Phase 2, significantly influenced the design of parts, the application of steel grades, the material thicknesses and in particular, the changes to tailor welded blanks. Every change in the design process also had to be analyzed for its suitability for assembly and parts manufacturing. The design approach was driven by mass reduction and created innovative results without allowing initial component cost consideration to limit options. The design also focused on a production volume of more than 100,000 units per year. As well as concentrating on reaching the targets for performance and mass, importance was also placed on the reduction of assembly steps, the integration of reinforcements, the use of tailor welded blanks, and the avoidance of metal arc welding, wherever possible. Using the same design approach in both Phases 1 and 2, it was possible to maintain low mass and high structural performances. The Phase 1 design concept and approach, the flexibility of the concept and the potential that it could be adjusted to various design tasks, were challenged in Phase 2 and ultimately justified. Chapter 5 - Page 1 Engineering Services, Inc. 5.2. Design and Engineering Process The design and engineering process used in Phase 2 is shown in the flow chart (Fig. 5.2-1). All through this process, a simultaneous engineering approach was taken to find the best solutions to overcome the design and engineering challenges emerging in Phase 2. No No Start Phase 1 Package/Concept Design Phase 2 Package Refinement Create Styling Concept Modify Package/ Styling / Design Modify Phase 1 Shell Model Steel Supplier & Part Supplier Input Modify Design Material / Thickness Adjustment Meets Static Targets Yes Yes No No Meets Static/Crash Targets Create / Modify Phase 2 Crash Model Yes Yes No No Parts Feasible Yes Yes Build of First Test Unit Yes Yes Meets Static Targets No No No No Meets Yes Static / Crash Targets Yes Create / Modify Phase 2 Shell Model Material / Thickness Selection, Design Modification Build of Final Demonstration Hardware Figure 5.2-1 Design and Engineering Process Using the Phase 1 package and concept design as the starting point, Phase 2 then refines the package. This refined Phase 2 package was the basis for the first styling layout, and in an interactive process, both were adjusted until the engineering requirements were met. The styling was frozen and the Phase 1 shell model was adjusted and analyzed using material thickness optimization to achieve Chapter 5 - Page 2 Engineering Services, Inc. the mass target while maintaining the structural performance goals. Together with the selected suppliers and the Material Group of the ULSAB Consortium, the part design was discussed and the material thicknesses were selected. With this information, the design was revised and the Phase 2 shell model created, analyzed and modified until all targets were met. New Phase 2 crash analysis models were built and after the first analysis, design modifications, material grade and thickness selection, further crash analyses were performed, until the results were satisfactory. With the revised design and material selection, the shell model was updated and the static analysis performed. The crash and static analysis models were constantly updated as a result of information from tool, part and steel suppliers. This was repeated until all results were satisfactory. The design was then modified and the part drawings released to the suppliers. With the first part set delivered, a test unit was built and the tests following provided the results for static performance and most importantly for mass. The design was enhanced and material substituted as needed. The process of shell and crash model modifications and analysis was performed again to validate the design. After the final design was released to the suppliers, parts were manufactured and the demonstration hardware built. Part of this process included regular design review meetings (not shown in the flow chart) of the design and engineering team as well as design review meetings with the demonstration hardware build team, engineers and analysts at Porsche R & D Center in Germany. In these internal PES meetings, technical problems were discussed and design directions decided in order to prepare for the demonstration hardware build and meet established deadlines. Chapter 5 - Page 3 Engineering Services, Inc. 5.3. ULSAB Phase 2 Design Description Figure 5.3-1 ULSAB Demonstration Hardware The ULSAB structure went through many adjustments and modifications in its transition from the Phase 1 concept to its final design stage at the end of Phase 2. This was due to added crash performance requirements, package issues, manufacturing processes and material application limitations. The exploded view (see Fig. 5.3-2) shows the demonstration hardware in the final Phase 2 design stage with the exception of minor brackets and reinforcements. Bolt-on parts and components, used in the analysis for crash performance, such as front and rear bumpers, engine, suspension, subframe, shock tower braces, tunnel bridge and fenders, are not considered part of the body structure and therefore are not shown in the exploded view. However, the structure is equipped with important brackets and reinforcements. Because tailor welded blanks can eliminate reinforcements, fewer were required. Included in the demonstration hardware, as shown on the exploded view, are the bolt-on front-end module and the dash-panel insert, including the brake booster reinforcement. Chapter 5 - Page 4 Engineering Services, Inc. 5.3.1. Parts List – Demonstration Hardware The parts list (Fig. 5.3.1-1) corresponds directly with the exploded view of the demonstration hardware (Fig. 5.3.1-2) and shows the part name and number, the material grade, and thickness and the mass of the manufactured part. Parts listed that have two or more material thicknesses and grades indicate that this part is made from a tailor welded blank. The mass of the parts listed, is taken from actual manufactured parts, but does not represent an average of all parts manufactured. Therefore, the mass of the demonstration hardware can vary slightly in comparison to the listed mass of the total number of parts. Demonstration Hardware Parts List Ma te ria l Ma te ria l Actua l Gra de T hickne ss P a rt (MP a ) (mm) Ma ss (kg) P a rt No P a rt N a me 001 Assy Reinf Radiator Support Upper 350 1.00 1.613 002 Reinf Front Rail Extension RH 350 1.00 0.485 003 008 A Reinf Front Rail Extension LH Assy Rail Front Outer RH 350 350 1.00 1.50 0.489 3.013 (Tailor Welded Blank) 350 1.60 350 2.00 Assy Rail Front Outer LH (Tailor Welded Blank) 350 350 1.50 1.60 350 2.00 Assy Rail Front Inner RH 350 1.50 350 350 1.60 1.80 350 1.50 350 1.60 B (Bolted on) C 009 A B C 010 A B C 011 A B (Tailor Welded Blank) Assy Rail Front Inner LH (Tailor Welded Blank) C 3.037 5.470 5.500 012 Rail Front Extension RH 350 350 1.80 1.40 2.096 013 Rail Front Extension LH 350 1.40 2.061 014 Bracket Roof Rail Mount Low er RH 350 1.20 0.153 015 021 Bracket Roof Rail Mount Low er LH Panel Dash 350 210 1.20 0.70 0.150 5.830 022 Panel Dash Insert Sandw ich 0.95 0.875 026 Member Dash Front 600 1.20 2.290 028 032 Panel Cow l Low er Panel Cow l Upper 210 210 0.70 0.70 1.272 1.374 034 Assy Member Front Floor Support (2-Req'd) 800 0.70 1.290 038 Assy Reinf Floor Front Seat Rear Outer (2-Req'd) 280 0.80 0.120 040 Pan Front Floor 210 0.70 14.650 (Bolted on) Figure 5.3.1-1 Chapter 5 - Page 5 Engineering Services, Inc. Demonstration Hardware Parts List (Cont’d) P a rt No P a rt N a me 042 A Panel Rocker Inner RH Ma te ria l Ma te ria l Actua l Gra de T hickne ss P a rt (MP a ) (mm) Ma ss (kg) 350 1.30 350 1.70 Panel Rocker Inner LH 350 1.30 6.625 045 (Tailor Welded Blank) Member Rear Suspension 350 280 1.70 0.70 1.344 046 A Assy Rail Rear Inner RH 350 1.00 5.250 350 1.30 350 350 1.60 1.00 (Tailor Welded Blank) 350 1.30 350 1.60 Assy Rail Rear Outer RH (Tailor Welded Blank) 350 350 1.00 1.30 350 1.60 350 1.00 350 350 1.30 1.60 B 043 A B B C 047 A B (Tailor Welded Blank) (Tailor Welded Blank) Assy Rail Rear Inner LH C 048 A B C 049 A B C Assy Rail Rear Outer LH (Tailor Welded Blank) (Bonded on) 6.490 5.240 2.527 2.565 050 Panel Spare Tire Tub Sandw ich 0.96 2.107 055 Member Panel Back 210 0.65 1.305 057 060 A Panel Back Panel Body Side Outer RH 140 210 0.65 0.70 2.502 15.780 B (Tailor Welded Blank) 280 0.90 C 280 1.30 D E 350 350 1.50 1.70 061 A Panel Body Side Outer LH 210 0.70 B (Tailor Welded Blank) 280 0.90 280 350 1.30 1.50 C D 15.650 350 1.70 062 Panel A-Pillar Inner Low er RH 350 1.00 1.365 063 064 Panel A-Pillar Inner Low er LH Panel B-Pillar Inner RH 350 350 1.00 1.50 1.375 3.586 065 Panel B-Pillar Inner LH 350 1.50 3.586 066 Reinf B-Pillar Low er (2-Req'd) 350 0.90 0.830 068 069 Panel Wheelhouse Inner RH Panel Wheelhouse Inner LH 210 210 0.65 0.65 1.931 1.923 Panel Wheelhouse Outer RH 140 0.65 2.116 (Tailor Welded Blank) 210 0.80 Panel Wheelhouse Outer LH (Tailor Welded Blank) 140 210 0.65 0.80 E 070 A B 071 A B Figure 5.3.1-1 Chapter 5 - Page 6 2.194 Engineering Services, Inc. Demonstration Hardware Parts List (Cont’d) Ma te ria l Ma te ria l Actua l Gra de T hickne ss P a rt (MP a ) (mm) Ma ss (kg) P a rt N o P a rt N a me 072 Rail Side Roof RH 280 1.00 4.700 073 Rail Side Roof LH 280 1.00 4.860 074 075 Panel A-Pillar Inner Upper RH Panel A-Pillar Inner Upper LH 350 350 1.50 1.50 1.425 1.416 080 Panel Package Tray Upper 210 0.65 1.876 081 Panel Package Tray Low er 210 0.65 1.497 082 083 Support Package Tray RH Support Package Tray LH 280 280 0.80 0.80 0.084 0.076 085 Panel Roof 210 0.70 8.680 086 Panel Front Header 280 0.70 0.813 087 090 Panel Rear Header Member Pass Through (2-Req'd) 140 140 0.70 0.65 0.773 0.662 091 Member Kick Up 800 0.70 1.397 094 Reinf Radiator Rail Closeout RH (Bolted on) 350 1.00 0.567 095 096 A Reinf Radiator Rail Closeout LH Panel Skirt RH (Bolted on) 350 140 1.00 2.00 0.575 3.457 140 1.60 Panel Skirt LH 140 2.00 098 (Tailor Welded Blank) Panel Gutter Decklid RH 140 140 1.60 0.65 0.434 099 Panel Gutter Decklid LH 140 0.65 0.437 102 Support Panel Rear Header RH 140 0.70 0.098 103 104 Support Panel Rear Header LH Rail Fender Support Inner RH 140 420 0.70 1.20 0.098 2.712 105 Rail Fender Support Inner LH 420 1.20 2.699 106 Rail Fender Support Outer RH 350 0.90 1.297 107 108 Rail Fender Support Outer LH Reinf Front Rail RH 350 350 0.90 1.00 1.297 0.838 109 Reinf Front Rail LH 350 1.00 0.830 110 Plate Rear Spring Upper (2-Req'd) 350 2.00 0.526 115 116 Reinf Panel Dash Brake Booster Assy Bracket Rear Shock Absorber Mount RH 350 350 1.00 2.00 0.464 0.335 117 Assy Bracket Rear Shock Absorber Mount LH 350 2.00 0.339 120 Reinf Floor Front Seat Rear Center 350 1.20 0.250 122 128 Assy Reinf Rear Seat Inner Belt Mount (2-Req'd) Bracket Member Pass Through Low er (2-Req'd) 350 350 2.00 1.00 0.244 0.056 130 Bracket Member Pass Through Upper Front 350 1.00 0.129 136 Reinf Panel Dash Upper 350 1.00 0.100 140 142 Pan Rear Floor Assy Reinf Hinge Decklid (2-Req'd) 210 350 0.70 1.50 4.240 0.224 144 Reinf A-Pillar RH 350 1.50 0.229 (Tailor Welded Blank) B 097 A B (Bolted on) Figure 5.3.1-1 Chapter 5 - Page 7 3.468 Engineering Services, Inc. Demonstration Hardware Parts List (Cont’d) Ma te ria l Ma te ria l Actua l Gra de T hickne ss P a rt (MP a ) (mm) Ma ss (kg) P a rt N o P a rt N a me 145 152 Reinf A-Pillar LH Bracket Member Pass Through Upper Rear 350 350 1.50 1.00 0.230 0.145 164 Assy Closeout Fender Support Rail RH 350 1.00 0.115 165 Assy Closeout Fender Support Rail LH 350 1.00 0.115 170 171 Reinf Rail Dash RH Reinf Rail Dash LH 350 350 1.30 1.30 0.309 0.312 172 Assy Reinf Cow l Low er 350 1.00 0.127 455 Assy Hinge Door Upper RH (2-Req'd) 280 - 0.515 456 457 Assy Hinge Door Low er RH (2-Req'd) Assy Hinge Door Upper LH (2-Req'd) 280 280 - 0.549 0.515 458 Assy Hinge Door Low er LH (2-Req'd) 280 - 0.549 180 Bracket Trailing Arm Mount RH 350 2.00 0.333 181 188 Bracket Trailing Arm Mount LH Brace Radiator (2-Req'd) 350 350 2.00 0.80 0.341 0.250 190 Assy Reinf Seat Belt Retractor Rear (2-Req'd) 350 1.20 0.104 (Bolted on) Total Mass of Parts Figure 5.3.1-1 Chapter 5 - Page 8 196.770 * * * See Assemblies 455 - 458 * * * * * * Chapter 5 - Page 9 Figure 5.3.1-2 ULSAB Phase 2 Exploded View Engineering Services, Inc. Engineering Services, Inc. 5.3.2. ULSAB Structure Mass For the Phase 1 concept, it was assumed that future average body structures would contain approximately 12 kg of brackets and reinforcements. This number can vary, up or down, depending on the type of vehicle, i.e., front or rear wheel drive, and the package of components. Since the goal of the ULSAB program is to provide solutions for a generic concept, it was assumed in Phase 1 that the 12 kg for brackets and reinforcements have to be considered in the calculation for mass to give the Phase 1 results more credibility. In Phase 1, the ULSAB structure was calculated with a mass of 193 kg. With the 12 kg for brackets and reinforcements, the total mass equals 205 kg. In Phase 2, some of the brackets and reinforcements are already welded into the structure. These are reflected accordingly in the mass of the demonstration hardware and also included in the parts list. With the refinement of the Phase 2 package, minor brackets and reinforcements were designed (but not manufactured) and their mass was calculated to get a more accurate determination than the general assumption used in Phase 1. These brackets and reinforcements represent a more generic, than detailed, selection. The selection was based on package information, chosen components and engineering judgment. It can be assumed that in a possible Phase 3, the number of brackets and reinforcements, and their actual mass when manufactured, can be insignificantly higher or lower. This depends on the final component selection; their position in the structure and efforts made to minimize their mass. Also included in the mass calculation are 100 weld studs. This also represents a generic number for this type of structure and is based on engineering judgment. The calculated mass of the ULSAB structure (Fig. 5.3.2-1) is the measured mass of the demonstration hardware parts and the calculated mass of brackets and reinforcements shown in Fig. 5.3.2-2 and Fig. 5.3.2-3. The ULSAB structure mass in Phase 2 is 203 kg, with the variation assumed to be +/- 1%. This low variation is due to each part being manufactured from one coil of steel. The differences in sheet thicknesses between coils do not apply for the demonstration hardware, but would have to be considered in mass production. ULSAB = Structure Mass 203.2 kg Mass of Demonstration + Hardware (Parts) = 196.8 kg Figure 5.3.2-1 Definition of ULSAB Structure Mass Chapter 5 - Page 10 Calculated Mass of Brackets and Reinforcements + 6.4 kg Engineering Services, Inc. Designed Brackets not Manufactured but Considered Part of the ULSAB Structure Part No 331 Nam e Qty Calc Mass [Kg] Bracket Exhaust Mount 2 0.060 332/333 Bracket Engine Mount RH/LH 2 0.528 334/335 Bracket Fender Mount Rear RH/LH 2 0.228 Bracket Battery Tray 1 0.412 336 337 Bracket Spare Tire Mount 1 0.089 Bracket Fuel Tank Mount Rear RH/LH 2 0.242 340 Bracket Front Tie Dow n Hook 2 0.236 341 Bracket Rear Tie Dow n Hook 2 0.236 342/343 Bracket Front Jack Support RH/LH 2 0.656 344/345 338/339 Bracket Rear Jack Support RH/LH 2 0.548 346 Bracket Plenum Support Center 1 0.445 N/A Weld Studs ~ 100 - 0.300 19 3.980 TOTAL Figure 5.3.2-2 Designed Reinforcements not Manufactured but Considered Part of the ULSAB Structure Part No Nam e Qty Calc Mass [Kg] 310 Reinf Hood Hinge Mount 2 0.086 311 Reinf Instrument Panel Beam Mount 2 0.134 312/313 Reinf Sub-Frame Front Mount 2 0.050 314/315 Reinf Sub-Frame Center Mount 2 0.116 316/317 Reinf Sub-Frame Rear Mount 2 0.418 318 Reinf Steering Rack Assembly Mount RH 1 0.032 319 Reinf Steering Rack Assembly Mount LH 1 0.041 320 Reinf Gear Shift Mount 1 0.271 321 Reinf Front Door Lock Striker 2 0.106 322 Reinf Front Door Check Arm 2 0.030 323 Reinf Rear Door Lock Striker 2 0.146 324 Reinf Rear Door Check Arm 2 0.028 325 Reinf Front D-Ring Adjustment 2 0.298 326 Reinf Rear Seat Cushion Mount 2 0.140 327 Reinf Rear Seat Latch 2 0.068 328 Reinf Rear Seat Back Mount Outer 2 0.278 329 Reinf Rear Seat Back Mount Center 1 0.035 330 Reinf Deck Lid Latch 1 0.136 31 2.413 TOTAL Figure 5.3.2-3 Chapter 5 - Page 11 Engineering Services, Inc. 5.3.3. ULSAB Demonstration Hardware Mass The mass of the demonstration hardware is 196.770 kg. This reflects the total amount of the mass of one complete part set, including brackets, reinforcements and bolt-on parts, as measured. In Phase 1, nearly all brackets and reinforcements were included in the theoretical number of 12 kg and only a few were included in the Phase 1 concept design of the body structure. With the level of detail design in Phase 2 and the refined package, it was now possible to design and finally manufacture most of these brackets and reinforcements and weld or bolt them to the demonstration hardware. It was not the task in Phase 2 of the ULSAB program to design and to manufacture all brackets and reinforcements and therefore, the approach to concentrate only on the important ones was taken. The mass of these manufactured brackets, reinforcements and bolt-on parts is included in the demonstration hardware mass and listed in the parts list (Fig. 5.3.1-1). The parts are shown on the exploded view (Fig. 5.3.1-2). For easier identification, the extracted list from the parts list (Fig. 5.3.3-2, -3 to Fig. 5.3.3-4) identifies these parts including their mass. The mass of the demonstration hardware as shown in Fig 5.3.3-1, consists of the mass of the pure body structure and the mass of brackets, reinforcements, bolt-on parts manufactured and welded or assembled to the body structure. Mass of Brackets, Reinforcements, Bolt-on Parts, DH Mass = Body Structure Mass + Welded and Assembled to the Body Structure 196.8 kg = 186.6 kg + Figure 5.3.3-1 Demonstration Hardware Mass Definition Chapter 5 - Page 12 10.2 kg Engineering Services, Inc. Reinforcements Manufactured and Welded to Structure Part No Nam e Qty Mass [Kg] 038 Assy Reinf Floor Front Seat Rear Outer 2 0.120 110 Plate Rear Spring Upper 2 0.526 120 Reinf Floor Front Seat Rear Center 1 0.250 122 Reinf Rear Seat Inner Belt Mount 2 0.244 136 Reinf Panel Dash Upper 1 0.100 142 Assy Reinf Hinge Decklid 2 0.224 144 Reinf A-Pillar RH 1 0.229 145 Reinf A-Pillar LH 1 0.230 164 Assy Closeout Fender Support Rail RH 1 0.115 165 Assy Closeout Fender Support Rail LH 1 0.115 176 Hinge Base RH 4 0.650 177 Hinge Base LH 4 0.650 178 Hinge Stem 119 4 0.379 179 Hinge Stem 141 4 0.449 172 Assy Reinf Cow l Low er 1 0.127 190 Assy Reinf Seat Belt Retractor Rear 2 0.104 33 parts 4.512 Figure 5.3.3-2 Brackets Manufactured and Welded to Structure Part No Nam e Qty Mass [Kg] 1 0.335 116 Assy Bracket Rear Shock Absorber Mount RH 117 Assy Bracket Rear Shock Absorber Mount LH 1 0.339 180 Bracket Trailing Arm Mount RH 1 0.333 181 Bracket Trailing Arm Mount LH 1 0.341 4 parts 1.348 Figure 5.3.3-3 Bolt-On Parts Manufactured and Attached to Structure Part No Nam e Qty Mass [Kg] 001 Assembly Reinf Radiator Support Upper 1 1.613 022 Panel Dash Insert 1 0.875 094 Reinf Radiator Rail Closeout RH 1 0.567 095 Reinf Radiator Rail Closeout LH 1 0.575 115 Reinf Panel Dash Brake Booster 1 0.464 188 Brace Radiator 2 0.250 7 parts 4.344 Figure 5.3.3-4 Chapter 5 - Page 13 Engineering Services, Inc. 5.3.4. Mass of Brackets and Reinforcements – Phase 2 The total mass of all brackets and reinforcements, (meaning the calculated mass of designed, not manufactured parts) and bolted-on parts welded or assembled to the demonstration hardware, amounts to 16.6 kg, and is included in the ULSAB structure mass of 203.2 kg. Total Mass of Brackets, Reinforcements & Bolt-on Parts - 16.6 kg Calculated mass of brackets & reinforcements, not manufactured or part of the ULSAB Structure Bolt-on parts assembled to body structure 6.4 kg 4.35 kg 1.35 kg 4.5 kg Brackets welded to body structure Reinforcements welded to body structure Figure 5.3.4-1 Mass Breakdown of Brackets, Reinforcements and Bolt-on Parts Chapter 5 - Page 14 Engineering Services, Inc. 5.3.5. ULSAB Structure Mass Comparison Phase 1 – Phase 2 The comparison of the results of the ULSAB structure mass is shown in Fig. 5.3.5-1. In Phase 2 the measured body structure mass has decreased with the refinement of the design, compared with the body structure mass as calculated in Phase 1. The total calculated mass of 205 kg, as in the Phase 1 ULSAB structure, is compared to the Phase 2 ULSAB structure mass of 203.2 kg, which includes the actual mass of the demonstration hardware plus the calculated mass of brackets and reinforcements. Phase 1 Assumed theoretical mass of brackets & reinforcements { Phase 2 6.4 kg 12 kg } } Calculated mass of brackets & reinforcements designed, not manufactured Brackets, reinforcements & bolt-on parts included in demonstration hardware (10.2 kg) Concept Validation 193 kg Body structure Mass ULSAB Structure 205 kg Mass + + + + + + 196.8 kg Offset crash Offset crash Package refinement Package refinement Styling Styling Body Structure Mass ULSAB Structure 203.2 kg Mass ±1% Figure 5.3.5-1 ULSAB Structure Mass Phase 1 - Phase 2 Chapter 5 - Page 15 Mass of Demonstration Hardware Engineering Services, Inc. 5.3.6. DH Part Manufacturing Processes The ULSAB structure as developed during Phase 1 and refined in Phase 2 is in general, a unibody design, with the exception of the hydroformed side roof rails. Stamping was the main manufacturing process considered for the parts design. Relative to the body structure mass of 196.8 kg, 89.2% is the mass of all stamped parts. The stampings can be divided into two groups; conventional stampings and stamped parts made from tailor welded blanks. 42.8% of the body structure mass is represented by conventionally stamped parts and 44.9% is the mass of parts made from tailor welded blanks. This relatively high percentage of tailor welded blank stampings, relative to the body structure mass, is one good indication of how the mass reduction was achieved. Especially if the use of high strength steels, in connection with the tailor welded blanks, is put into consideration. The hydroforming process is applied in the form of two processes: • • The tubular hydroforming process for the side roof rail manufacturing The hydromechanical sheet forming process, for the roof panel manufacturing. The spare tire tub and the dash panel insert are designed to be manufactured from steel sandwich material, also using the stamping process. Chapter 5 - Page 16 Engineering Services, Inc. The mass of the stamped parts made from steel sandwich material is 1.5% relative to the overall mass. 1.5% are miscellaneous parts, stock materials, such as tubes, or the forged hinge base of the weld through hinges. The pie chart in Fig. 5.3.6-1 shows the mass distribution of the manufacturing processes relative to the DH mass. The process used to manufacture the parts is shown in Fig. 5.3.6-2. ÒÒÒ 89.2% Stampings ÒÒ 9.3% Hydroforming Parts Ò 1.5% Misc.(Stock Material) Parts 44.9% Tailor Welded Blank Stamping 42.8% Conventional Blank Stamping 1.5% Miscellaneous 1.5% Steel Sandwich Material Blank Stamping 4.9% Tubular Hydroforming 4.4% Sheet Hydroforming Figure 5.3.6-1 Manufacturing Process Relative to DH Mass Chapter 5 - Page 17 Engineering Services, Inc. * * * * Chapter 5 - Page 18 * * * * Part Manufacturing Process Ò “Conventional Blank”, Stamping Ò Tailor Welded Blank, Stamping Ò Sheet, Hydroforming Ò Tubular Hydroforming Ò Sandwich Material Blank, Stamping Ò Misc.(Stock Materials) * See Assemblies 455 - 458 Figure. 5.3.6-2 ULSAB Manufacturing Processes of Demonstration Hardware Parts Engineering Services, Inc. 5.3.7. Material Grades The selection of the steel grades is a result of the need for good crash performance and mass reduction. In Phase 2, the utilization of high strength steel is 91%, relative to the DH mass (Fig. 5.3.7-1) of Phase 1. The parts design had to consider the lower elongation, and together with the tool manufacturer, the parts design was optimized to accommodate the different forming characteristics and greater spring back of high and ultra high strength steels. This was most important for the design of the tailor welded blank stamped parts which where different grades and thicknesses of high strength steels and combined into one part. High strength and ultra high strength steel material was used on parts contributing to the crash management of the structure, i.e. front rails, rear rails, rocker, etc. (Fig. 5.3.7-2). With this approach, and in combination with tailor welded blanks, it was possible to avoid the need for reinforcements and thus reduced the total number of parts. For mass reduction, steel sandwich material was applied in the spare tire tub and the dash panel insert. Steel sandwich material contributes to 1.5% of the DH mass. Due to the overall design, material specifications of steel sandwich material and restrictions in its applications, such as low heat resistance and available size, this material’s use was limited during Phase 2. Chapter 5 - Page 19 Engineering Services, Inc. Mild Steel 7.6% High Strength Steels 90.9% Steel Sandwich Material 1.5% 45.1% - 350 MPa 13.5% - 280 MPa 27.1% - 210 MPa 2.7% - 420 MPa 7.6% - 140 MPa 1.5% - Steel Sandwich Material Figure 5.3.7-1 Chapter 5 - Page 20 2.5% - Ultra High Strength Steel > 550 MPa Ò 140 MPa Ò 210 MPa Ò 280 MPa Ò 350 MPa Ò 420 MPa Ò > 550 MPa Ultra High Strength Steel Ò Steel Sandwich Material * * * * * * * * Figure. 5.3.7.-2 Material Grades of DH Parts * See Assemblies 455 - 458 Engineering Services, Inc. Chapter 5 - Page 21 Ò 140 MPa Ò 210 MPa Ò 280 MPa Ò 350 MPa Ò 420 MPa Ò >550 MPa Ò Steel Sandwich Material Engineering Services, Inc. 5.3.8. Material Thickness The distribution of the used material sheet thicknesses relative to the DH mass is shown in Fig. 5.3.8-1. The majority of the mass (25%) is made from 0.7 mm sheet steel. Parts with a large surface area such as the panel floor, the panel dash and the panel roof are manufactured of high strength steel of this thickness, and are parts with secondary influence in crash performance. All 1.3 mm thickness material is high strength steel with the yield strength ranging from 280 MPa (46%) to 350 MPa (54%). The parts made of 1.3 mm material used in “conventional” stampings and tailor welded blank stampings have primary influence on crash performance. Since the demonstration hardware mass consists of 91% high strength steel, nearly all parts are made from high strength steel sheets in a thickness ranging from 0.65mm to 2.0mm. Percent Distribution of Material Thickness Relative to DH Mass 25.1% 10.8% 10.9% 9.1% 7.6% 3.0% 4.2% 0.8% 0.65 0.70 2.1% 8.4% 7.6% 3.0% 4.4% 0.80 0.90 1.00 1.20 1.30 1.40 1.50 1.60 1.70 1.80 2.00 Material Thickness Figure. 5.3.8-1 Chapter 5 - Page 22 1.5% 1.5% Sandwich Misc Engineering Services, Inc. 5.4. Detail Design PES executed an entirely paperless design using Computer Aided Design (CAD) and CATIA software for the detail design. With the involvement of part suppliers in the United States and Europe, the Porsche R & D Center, in Germany, and the necessary data exchange for the tool development and the design of the assembly fixtures, this approach proved to be very efficient. 5.4.1. Weld Flange Standards For the detail parts design it was important to define standards for the design of the weld flanges. The decision was made not to reduce the weld flange width for mass reduction, which allowed the use of standard weld equipment for the demonstration hardware assembly. 5.4.1.1. Weld Flanges for Spot or Laser Welding For the design of parts to be spot welded, the flange length was designed to the Porsche standards shown in Fig. 5.4.1.1-1. For the laser welding in assembly, the same standards were applied. Figure 5.4.1.1-1 ULSAB Spot Weld Standards Chapter 5 - Page 23 Engineering Services, Inc. 5.4.1.2. Scalloped Spot Weld Flanges Scalloped flanges were used for mass reduction. Figure 5.4.1.2-1 Part no. 81 Panel Package Tray Lower with Scalloped Flanges The design is similar to the scalloped flanges used in production of the Porsche 911 and Boxster. The second reason for scalloping weld flanges was to create two sheet spot welding where three sheet spot welding would have been applied, otherwise. Scalloped flanges were applied to parts not critical for sealing and not sensitive to crash or durability. The mass reduction achieved with scalloped flanges on the selected parts, based on the calculated part mass equals 0.43 kg. (Fig. 5.4.1.2-4) The flange geometry is shown in Fig. 5.4.1.2-2. The layout for a two sheet weld flange and a three sheet weld flange with scalloped flanges is shown in Fig. 5.4.1.2-3. Chapter 5 - Page 24 Engineering Services, Inc. Flange Geometry Figure 5.4.1.2-2 Flange Geometry Two Sheet Weld Flange Three Sheet Weld Flange Figure 5.4.1.2-3 Layout of 2 and 3 Sheet Weld Flanges Chapter 5 - Page 25 Engineering Services, Inc. Part Number Part Name Calculated Part Mass Calculated Part Mass with Mass Reduction [kg] Scalloped Flange [kg] [kg] 21 Panel Dash 6.180 6.140 0.040 28 Panel Cowl Lower 1.400 1.326 0.074 40 Pan Front Floor 15.934 15.892 0.042 45 Member Rear Suspension 1.486 1.440 0.046 55 Member Panel Back 1.450 1.424 0.026 68 Panel Wheelhouse Inner RH 2.141 2.110 0.031 69 Panel Wheelhouse Inner LH 2.141 2.110 0.031 81 Panel Package Tray Lower 1.700 1.594 0.106 140 Pan Rear Floor 4.330 4.298 0.032 0.428 Figure. 5.4.1.2-4 Mass Reduction with Scalloped Flanges 5.4.1.3. Locator, Tooling and Electrophoresis Holes Included in the detail part design are all locator holes for the assembly. All locator holes needed for parts manufacturing and the holes necessary for the electrophoresis of the body structure. After the location of the holes for electrophoreses were first determined, they were then incorporated into the crash models and the crash analysis was performed to verify that their position did not have any negative influence on the crash performance. After this verification, the holes were incorporated into the parts design. Chapter 5 - Page 26 Engineering Services, Inc. 5.4.2. Design Refinement Phase 1 reflected a concept design. In Phase 2, the task was to make the design feasible for manufacturing of the parts to maintain low mass and structural performances and also, to achieve the crashworthiness of the structure. In the refinement of the design, changes to the design concept were done for the following reasons: • • • • • • • Mass reduction Manufacturing and tooling Assembly Material specifications Crash performance Package Styling The overview of design changes as shown in Fig. 5.4.2-1, names the parts or areas of the structure, the design change and the reason for the different solution or change from Phase 1 to Phase 2. Chapter 5 - Page 27 Engineering Services, Inc. Overview of Major Design Changes in Phase 2 Part No. Part / Location Area Description of Change Reason for Change 1 Fender Support Rail Hydroforming part was replaced with Assembly, part manufacturing 2 part stamping 2 Pan Front & Pan Rear Floor 3 part front floor with sandwich material tunnel deleted Heat resistance of sandwich material not sufficient for bake hardening process 3 Rear Rails Spring & shock absorber relocated with new rear suspension Mass reduction, package 4 Front Rails Space between rails increased Package of bigger engine Rear part of the front wheelhouse deleted Mass reduction Redesigned, tailor welded blank Package of new front suspension in conjunction with #4 5 Panel Skirt Reinforcement shock tower deleted, Mass reduction integrated in new panel skirt 6 Panel Spare Tire Tub designed as separate module Heat resistance of sandwich material, from steel sandwich material and to not sufficient for bake hardening be bonded to the rear floor after final process assembly 7 Package Tray Redesigned from 3 part to 2 part design roll formed member package Assembly tray front deleted 8 Member Dash Front, Member Front Floor Support, Member Kick-up Material changed from high strength to ultra high strength steel >550 MPa Front Crash, side impact crash yield strength 9 Panel Body Side Outer Blank configuration in tailor welded blank with all blanks in high strength Crash analysis, mass reduction steels 10 B-Pillar Joint Rocker inner extended upwards into B-Pillar. B-Pillar lower Side impact, crash assembly reinforcement modified 11 A-Pillar - Cowl - Fender Support Rail-Hinge Pillar Joint Joint modified Assembly, revised fender support rail 12 Panel Back 3 Piece design integrated into one part Mass reduction, assembly 13 Side Roof Rail Design refinements Manufacturing process - hydroforming 14 Bolt on Front End Welded Change in front end module concept Figure 5.4.2-1 Chapter 5 - Page 28 Engineering Services, Inc. 6. CAE Analysis Results Engineering Services, Inc. 6. CAE Analysis Results 6.1. Selected Tests for CAE To verify that the ULSAB meets the targets set in the beginning of Phase 1, the following tests were chosen for the static and dynamic stiffness. Structural Performances Targets Static torsion stiffness ≥ 13000 Nm/deg Static bending stiffness ≥ 12200 N/mm Normal modes (first modes) ≥ 40 Hz Figure 6.1-1 Load cases and targets for static and dynamic stiffness For analytical crash testing the following tests were selected: • • • • • AMS, 50% frontal offset crash at 55 km/h NCAP, 100% frontal crash at 35 mph (FMVSS 208) Side impact crash at 50 km/h (96/27 EG, with deformable barrier) Rear moving barrier crash at 35 mph (FMVSS 301) Roof crush (FMVSS 216) 6.2. Static and Dynamic Stiffness Based on CAD surface data the FE-Model (Figure 6.2-1) for the body in white was created. Because of the structure symmetry, only a half model with certain boundary conditions at the symmetry plane at y=0 for the static and dynamic stiffness simulations were used. The stiffness model consists in triangle and quadrilateral elements. To connect the different structure components, different methods were used. To connect laser welded parts in the FE-Model, the nodes of the flanges were equivalent. For spot welded areas the middle flange nodes are connected with welding point elements. The weld point distance was with a point Chapter 6 - Page 1 Engineering Services, Inc. distance of about 50 mm. The CAE configuration for the static and dynamic simulations consist of the following parts: • • • • • • • • • • Welded Body Structure Bonded Windshield and Back Light Bonded and bolted Panel Dash Insert (Part-No. 022) Bonded Panel Spare Tire Tub (Part-No. 050) Bolted Reinforcement Panel Dash Brake Booster (Part-No. 115) Bolted Braces Radiator (Part-No. 188) Bolted Reinforcement Radiator Rail Closeout RH/LH (Part -No. 094/095) Bolted Reinforcement Radiator Support Upper (Part-No. 001) Bolted Tunnel Bridge Lower/Upper Bolted Brace Cowl to Shock Tower Assembly Figure 6.2-1 FE-Model The stiffness model (per half model) consisted of: • • 54521 shell elements 53460 nodes The deformed shapes for the load cases torsion and bending are shown in the Figures 6.2.1-1 and 6.2.2-1. To view the stiffness distribution vs. the x-axis, the diagrams 6.2.1-2 (torsion) and 6.2.1-3 (bending) are used. The derivation vs. the x-axis for torsion (Fig. 6.2.1-3) and bending (Fig.6.2.2-3) as well as the strain energy contour plots (Fig. 6.2.1-4 and Fig. 6.2.2-4) show the sensitive areas. The colored areas of the strain plots show the elastic energy, which is a result of the Chapter 6 - Page 2 Engineering Services, Inc. deformation stored in the structure, as internal energy. The deformed shape of the dynamic stiffness simulation, the normal modes are shown in the Figures 6.2.3-1 to 6.2.3-3. The deformed frequency mode belongs to the normal modes mentioned in Table 6.2-2. CAE Structural Performance Static Torsional Stiffness 21310 Nm/deg Static Bending Stiffness 20540 N/mm CAE Mass* (with glass) 230.6 kg CAE Mass* (without glass) 202.8 kg First Torsion Mode 61.4 Hz First Bending Mode 61.8 Hz Front End Lateral 60.3 Hz *Mass as in test configuration (Chapter 6, page 2), brackets and reinforcements (6.4 kg) are not included (see Chapter 5, page 10) Figure 6.2-2 Table of CAE Structural Performance 6.2.1. Torsional Stiffness A load of 1000 N was applied at the shock tower front while the body structure was constrained at the rear center spring attachment in the lateral and vertical directions. Figure 6.2.1-1 Deformed Shape for Torsion Chapter 6 - Page 3 Engineering Services, Inc. 21310 Nm/deg Torsion Angle 0.08 Support Angle = atan (zdisp/ycoor) [deg] 0.07 0.06 0.05 0.04 0.03 0.02 0.01 0 -0.01 500 1000 1500 2000 2500 3000 3500 4000 Shock Tower Front 4500 5000 5500 Center, Spring Attachment Rear Longitudinal X-axis [mm] Figure 6.2.1-2 Torsion Angle vs. x-Axis Derivation of Torsion Angle 0.03 Support Derivation of Angle [deg/mm] 0.02 0.01 0 -0.01 -0.02 -0.03 -0.04 -0.05 500 1000 1500 2000 Shock Tower Front 2500 3000 Figure 6.2.1-3 Derivation of Torsion Angle vs. x-Axis Chapter 6 - Page 4 3500 Longitudinal X-axis [mm] 4000 4500 5000 Center, Spring Attachment Rear 5500 Engineering Services, Inc. Figure 6.2.1-4 Strain Energy Contour Plot for Torsion 6.2.2. Bending Stiffness The loads were applied to the center of the front seats and to the center of the two outer rear seats. The measurements were taken under a load of F max = 4000 N b (4 x 1000 N). Figure 6.2.2-1 Deformed Shape for Bending Chapter 6 - Page 5 Engineering Services, Inc. 20540 N/mm Vertical Z-Displacement 0.25 Support Vertical Z-Displacement [mm] 0.2 0.15 0.1 0.05 0 -0.05 -0.1 -0.15 -0.2 500 1000 1500 2000 Shock Tower Front 2500 3000 3500 4000 Longitudinal X-Axis [mm] 4500 5000 5500 Center, Spring Attachment Rear Figure 6.2.2-2 z-Displacement vs. x-Axis, Bending Derivation of Vertical Z-Displacement Derivation of vertical Z-Displacement [mm] 0.4 Support 0.3 0.2 0.1 0 -0.1 -0.2 -0.3 -0.4 500 1000 1500 Shock Tower Front 2000 2500 3000 3500 4000 Figure 6.2.2-3 Derivation of z-Displacement vs. x-Axis, Bending Chapter 6 - Page 6 4500 Longitudinal X-Axis [mm] Center, Spring Attachment Rear 5000 5500 Engineering Services, Inc. Figure 6.2.2-4 Strain Energy Contour Plot for Bending 6.2.3. Normal Modes Figure 6.2.3-1 Front End Lateral Mode Chapter 6 - Page 7 Engineering Services, Inc. Figure 6.2.3-2 First Bending Mode Figure 6.2.3-3 First Torsion Mode Chapter 6 - Page 8 Engineering Services, Inc. 6.3. Crash Analysis For three crash types of the ULSAB project, one common crash model was generated. With this model the crash simulations were conducted: • • • AMS 50% frontal offset crash at 55 km/h NCAP 100% frontal crash FMVSS 208 at 35 mph Side impact crash at 50 km/h (96/27 EG with deformable barrier) For the rear crash (FMVSS 301) at 35mph only a half structure (Fig. 6.3.3-1) was used. Fig. 6.3-1 shows the high level of detail for the FE-Model. To realize a realistic crash behavior of the simulation, all the spot welds and laser welded areas were considered in the models. To analyze the crash behavior, all crash-relevant car components were modeled, such as: • • • • • • • • • • • Wheels with tire model Engine and transmission Steering system Chassis system with subframe Fuel tank Bumper system including crashbox Radiator with fan Battery Spare tire Brake booster, ABS box and cylinder Doors, front and rear without glass The door concept used for all simulations was a typical two shell structure with an inner and outer panel, an upper door reinforcement and two high strength side impact beams at the front door and one side impact beam at the rear door. A three point fixture with reinforcements at the hinges and the locks supported the doors. To reduce the model size for the roof crush analysis, the full model with reduced contents was used (Fig. 6.3.5-1). Chapter 6 - Page 9 Engineering Services, Inc. Figure 6.3-1 Crash Analysis Model A high level of detail of the surfaces, welding and mounting locations was necessary to provide the resolution to be able to access the events. The LS-DYNA complete full model had 178386 elements and 174532 nodes. Chapter 6 - Page 10 Engineering Services, Inc. The vehicle mass was defined to be base curb weight plus two 50th percentile male dummies with 113 kg of luggage. The crash mass of the vehicle was set at 1612 kg. The crash mass of the vehicle is calculated as follows: Curb Mass 1350 kg Luggage 113 kg Dummies 149 kg Total Crash Mass 1612 kg 6.3.1. AMS Offset Crash The AMS offset crash was defined in the year 1990 by the editor of the German automotive magazine ‘Auto Motor Sport’ (AMS). The aim of this offset crash is to secure the passenger compartment residual space. For this requirement a stiff passenger compartment and a good energy absorption in the front structure is needed. The initial velocity for the car is 55 km/h for the AMS crash. The Offset barrier is a block with a 15 degree rotated contact area including two anti-slide devices mounted on the contact surface. The left side of the car hits the barrier with an overlap of 50%. For actual crash tests AMS analyzes the following values: • • • • • • • HIC-value (Head Injury Criterion) Head, chest and pelvis acceleration Maximum belt forces Maximum femur forces Dynamic steering deformation Foot well intrusions Door opening after test Because the analysis did not include dummies, injury assessment could not be made. Injury performance is greatly affected by the structural crash and steering column movement as well as by the knee bar design. Evaluation of passenger compartment intrusion can be made by looking at deformation in the foot well area (Fig. 6.3.1-4). Looking at the overall shape of the deformation (Fig. 6.3.1-2, -3 can assess structural integrity). Chapter 6 - Page 11 Engineering Services, Inc. Figure 6.3.1-1 AMS Offset Crash Analysis Setup The AMS Offset undeformed and deformed shapes are shown in Fig. 6.3.1-2 and 6.3.1-3. The deformed shape in these figures is after 100 ms. The deformation in the footwell area is shown in Fig. 6.3.1-4. The analyzed deformation is measured in the foot well area where it is important to keep the deformations as low as possible, because of the injury of the passenger’s legs. The internal energy absorption diagram in Fig. 6.3.1-5 gives an overview of the internal energy absorbed in the parts subframe, bumper beam, crashbox, front rail and fender side rail after 100 ms. The diagram in Fig. 6.3.1-6 shows the load path for the most important front structure components. The diagram shows the main load path is the rail front. The fender side rail and the subframe have about the same load level. The diagram, AMS Offset Crash Acceleration vs. Time (Fig. 6.3.1-7) shows an average acceleration calculated from the rocker LHS, tunnel, and rocker RHS. After the contact between AMS barrier and engine, a middle acceleration of about 25 g results in the passenger area. The Figure 6.3.1-8 shows the function of the car deformation versus time. After about 90 ms the maximum dynamic deformation is reached. Chapter 6 - Page 12 Engineering Services, Inc. t = 0 ms t = 100 ms Figure 6.3.1-2 AMS Offset Crash Deformed Shapes t = 0 ms t = 100 ms Figure 6.3.1-3 AMS Offset Crash Deformed Shapes of Longitudinals Chapter 6 - Page 13 Engineering Services, Inc. 9 40 80 36 39 146 64 134 92 16 33 102 76 60 82 Figure 6.3.1-4 AMS Offset Crash Maximum Dynamic Foot Room Intrusion in mm Subframe 26.9 Bumper Beam 17.3 Crash Box 5.6 Rail Front 37.6 Fender S. Rail 9.6 0 10 20 30 40 Energy (kJ) Figure 6.3.1-5 AMS Offset Crash Internal Energy Absorption Chapter 6 - Page 14 Engineering Services, Inc. 55 Subframe Front Rail Ext. 50 Rocker 85 115 Rail Front 50 Fender S. Rail 0 20 40 60 80 100 120 140 Force (kN) Figure 6.3.1-6 AMS Offset Crash Typical Cross Section Forces Average Car Acceleration vs. Time Rocker LHS / Tunnel / Rocker RHS 40 -40 30 -30 ax [g] 20 -20 10 -10 0 0 -10 +10 0 20 40 60 80 time [ms] Figure 6.3.1-7 AMS Offset Crash Acceleration vs. Time Chapter 6 - Page 15 100 Engineering Services, Inc. Car Deformation vs. Time 800 600 sx [mm] 400 200 0 -200 0 20 40 60 time [ms] Figure 6.3.1-8 AMS Offset Crash Deformation vs. Time Chapter 6 - Page 16 80 100 Engineering Services, Inc. In the following table (Fig. 6.3.1-9), the AMS crash events vs. time are explained: Time (ms) AMS Offset Crash 12.00 Initial folding of longitudinal LHS 16.00 Initial folding of subframe 18.00 First buckling of rail upper in front of shock tower 36.00 Wheel LHS contacts barrier 40.00 Engine contacts barrier, start of vehicle-rotation around z-axis 44.00 Deformable front end of the subframe totally deformed, stiffer rear end and the extension longitudinal LHS starts moving rearwards and causes deformation in the front floor area, buckling of the longitudinal in the area of the shock tower 48.00 Second buckling of rail upper LHS behind the shock tower 52.00 Buckling of the rear end of the subframe at the fixture on the extension longitudinals 60.00 Buckling of the brace cowl to shock tower LHS. Engine hits the steering gear. 68.00 Contact between gearbox-mounting and brake booster 70.00 Wheel LHS hits the hinge pillar 88.00 Maximum dynamic deformation reached Figure 6.3.1-9 AMS Offset Crash Events Chapter 6 - Page 17 Engineering Services, Inc. This analysis shows good progressive crush on the barrier side (left), as well as crush on the right, indicating transfer of load to the right side of the structure. This transfer means that the barrier side is not relied upon solely to manage the crash event. This transfer also contributes to the preservation of the occupant compartment. The intrusion of 146 mm into the footwell is minimal given the severity of this event. The initial, early peak shown in the pulse graph should trigger air bag systems. Peak deceleration of approximately 35 gs, a good result considering the severity of this event. Chapter 6 - Page 18 Engineering Services, Inc. 6.3.2. NCAP 100% Frontal Crash The conditions for the front crash analysis are based on several requirements. In the ULSAB program, the focus was on progressive crush of the upper and lower load path, sequential stack up of the bumper, radiator, and powertrain, integrity between individual components, A-pillar displacement, definition of the door opening, uniform distribution of the load, toe pan intrusion, and passenger compartment residual space. These requirements contribute towards occupant safety and the United State Federal Motor Vehicle Safety Standard, FMVSS 208. The test sequence of the front crash analysis is set up to duplicate a 35 mph, National Highway and Traffic Safety Association (NHTSA) full frontal barrier test (Fig. 6.3.2-1). Figure 6.3.2-1 NCAP 100% Crash Analysis Setup Chapter 6 - Page 19 Engineering Services, Inc. The NCAP 100% Frontal Crash undeformed and deformed shape is shown in Figures 6.3.2-2 and 6.3.2-3. The deformed shape in the figure is after 100 ms. The deformation in the footwell area is shown in Fig. 6.3.2-4. The analyzed deformations are measured in the foot well area where it is important to keep the deformations as low as possible, because of the injury of the passenger legs. The internal energy absorption diagram in Fig. 6.3.2-5 gives an overview of the internal energy absorbed in the parts subframe, bumper beam, crashbox, front rail and fender side rail after 100 ms. The diagram in Fig. 6.3.2-6 shows the section force for the most important front structure components. The diagram shows that the main load path is the rail front. The components, fender side rail and the subframe have about the same load level. The diagram, NCAP Crash Acceleration vs. Time (Fig. 6.3.2-7), is an average of accelerations at the rocker LHS, tunnel, and rocker RHS. After the contact between barrier and engine it results a middle acceleration of about 29 g at the passenger area. The Figure 6.3.2-8 shows the function of the car deformation versus time. After about 68 ms the maximum dynamic deformation is reached. t = 0 ms Figure 6.3.2-2 NCAP 100% Crash Deformed Shapes Chapter 6 - Page 20 t = 100 ms Engineering Services, Inc. t = 0 ms t = 100 ms Figure 6.3.2-3 NCAP 100% Crash Deformed Shapes of Longitudinals 80 80 85 70 79 94 70 58 73 62 45 51 50 52 40 Figure 6.3.2-4 NCAP 100% Crash Maximum Dynamic Foot Room Intrusion in mm Chapter 6 - Page 21 Engineering Services, Inc. Subframe 30 Rail Upper 12.5 55.3 Rail Front 8 Crash Box Bumper Front 16 0 10 20 30 40 50 60 Energy (kJ) Figure 6.3.2-5 NCAP 100% Crash Internal Energy Absorption Subframe 49 Rocker 50 Rail Upper 41 Rail Front 120 45 Front Rail Ext. 0 20 40 60 80 100 120 140 Force (kN) Figure 6.3.2-6 NCAP 100% Crash Typical Cross Section Forces Chapter 6 - Page 22 Engineering Services, Inc. Average Car Acceleration vs. Time Rocker LHS / Tunnel / Rocker RHS 40 -40 30 -30 ax [g] 20 -20 10 -10 00 +10 -10 0 20 40 60 80 100 80 100 time [ms] Figure 6.3.2-7 NCAP 100% Crash Acceleration vs. Time Car Deformation vs. Time 800 sx [mm] 600 400 200 0 0 20 40 60 time [ms] Figure 6.3.2-8 NCAP 100% Crash Deformation vs. Time Chapter 6 - Page 23 Engineering Services, Inc. The following table (Figure 6.3.2-9) shows the NCAP crash events: Time (ms) NCAP Front Crash 12.00 Initial folding of longitudinal 16.00 Initial folding of subframe 21.00 First buckling of rails upper in front of shock tower 35.00 Engine contacts barrier 37.00 Buckling of the rear end of the subframe at the fixture on the extension longitudinals 50.00 Rear end of longitudinals start to buckle behind the reinforcement (still stable) 51.00 Wheels contacts barrier 67.00 Maximum dynamic deformation reached Figure 6.3.2-9 NCAP Front Crash Events This analysis illustrates good progressive crush of the upper and lower structure and subframe. It shows peak deceleration of 31 gs, which is satisfactory considering that this structure is designed with stiffer body sides to meet 50% AMS offset crash requirements. The pulse graph is sympathetic to current occupant restraint systems. It shows a consistent rise to the peak of 31 gs then a smooth ride down to zero, indicating that the occupant would experience controlled restraint. The initial, early peak should trigger air bag systems. Low intrusion at the footwell indicates that leg damage is unlikely. Chapter 6 - Page 24 Engineering Services, Inc. 6.3.3. Rear Crash The conditions for the rear impact analysis are based on the United States Rear Moving Barrier Test FMVSS-301. The test specifically addresses fuel system integrity during a rear impact. Automotive companies also include structural integrity and passenger compartment volume as additional goals for this test. The impacting barrier is designed to represent a worst case rear crash (Fig. 6.3.31). The rear crash barrier is a rigid body with a mass of 1830 kg, making contact at zero degrees relative to the stationary vehicle. The Federal Standard identifies that the velocity of the rear moving barrier is 30 mph. The ULSAB program has raised the standard to 35 mph, which is 36% more kinetic energy of the moving barrier. Evaluating fuel system integrity is done by representing a fuel tank system. The additional goals of passenger compartment integrity, residual volume, and door opening after the test can be addressed by looking at the deformed shapes of the vehicle during the crash event. During the early stages of the impact, there should be a little or no deformation in the interior. This sequence of events (Fig. 6.3.3-8) is necessary up to the time that the tires make contact with the barrier face and transfer load to the suspension and the rear of the rocker panel. For the rear crash a half structure model was used. The rear crash deformed shapes are shown in Fig 6.3.3-2. To analyze the rear passenger compartment integrity, Figure 6.3.3-3 shows that maximum dynamic intrusion in this area. The diagram (Fig. 6.3.3-4) shows the energy absorption, and the cross sections of the main hood load paths are shown in Figure 6.3.3-5. Due to the results, the rear rail and the rocker were the most important hood paths of the rear structure. The Rear Crash Acceleration vs. Time (Fig. 6.3.3-6) shows an average acceleration of the rocker RHS and the tunnel. Figure 6.3.3-7 shows the total car deformation, at approximately 85 ms, the maximum dynamic deformation was reached. Chapter 6 - Page 25 Engineering Services, Inc. Figure 6.3.3-1 Rear Crash Analysis Setup Chapter 6 - Page 26 Engineering Services, Inc. t = 0 ms t = 100 ms t = 0 ms t = 100 ms Figure 6.3.3-2 Rear Crash Deformed Shapes Chapter 6 - Page 27 Engineering Services, Inc. X 120 X X X 53 X X 73 38 5 X X 4 X 33 2 Figure 6.3.3-3 Rear Crash Maximum Dynamic Room Intrusion (mm) Rear Rail 20.2 1.4 Crash Box Rear Panel Rear Floor 6.3 1.1 Bumper Rear 0 5 10 15 20 25 Energy (kJ) Figure 6.3.3-4 Rear Crash Internal Energy Absorption (kJ) Chapter 6 - Page 28 66 Engineering Services, Inc. Rocker 50 Rear Rail 80 Rail Side Roof 15 20 Spare Wheel 0 10 20 30 40 50 60 70 80 90 Force (kN) Figure 6.3.3-5 Rear Crash Typical Cross Section Forces (kN) Average Car Acceleration vs. Time 40 30 ax [g] 20 10 0 -10 0 20 40 60 80 time [ms] Figure 6.3.3-6 Rear Crash Acceleration vs. Time Chapter 6 - Page 29 100 Engineering Services, Inc. Car Deformation vs. Time 800 sx [mm] 600 400 200 0 0 20 40 60 time [ms] Figure 6.3.3-7 Rear Crash Deformation vs. Time Chapter 6 - Page 30 80 100 Engineering Services, Inc. The following table (Fig. 6.3.3-8) explains the rear crash events after impact: Time (ms) Rear Crash 4.00 Initial folding of longitudinals rear 20.00 Spare tire contacts barrier 35.00 First buckling of crossmember rear suspension 40.00 Spare tire hits crossmember rear suspension 44.00 Buckling of the crossmember rear suspension 48.00 Buckling of the rear end rocker at the connection to longitudinal rear 52.00 Collapse of crossmember rear suspension 56.00 Buckling of the front end longitudinal rear 86.00 Maximum dynamic deformation reached Figure 6.3.3-8 Rear Crash Events This analysis shows that the structural integrity of the fuel tank and fuel filler was maintained during the event, so no fuel leakage is expected. The spare tire tub rides up during impact, avoiding contact with the tank. Rear passenger compartment intrusion was restricted to the rear most portion of the passenger compartment, largely in the area behind rear seat. This result is due to good progressive crush exhibited by the rear rail. Chapter 6 - Page 31 Engineering Services, Inc. 6.3.4. Side Impact Analysis The conditions for the side impact analysis are based on a European Side Moving Barrier Test. The European test specifically addresses injury criterion based on displacement data gathered from EUROSID side impact crash dummies. Automotive companies also include post-crash structural integrity and passenger compartment as additional requirements for this test. The actual European side moving barrier uses a segmented deformable face which complies with a required set of different load versus displacement characteristics and geometric shape and size requirements. The barrier used in the analysis (Fig. 6.3.4-1) conformed to the geometric requirements (i.e., ground clearance, height, width, bumper depth). The European specification requires the impacting barrier to have a mass of 950 kg, making contact at ninety degrees relative to the vehicle longitudinal axis. The center line of the barrier is aligned longitudinally with the front passenger ‘R-point’. The R-point is a car specific point which is defined by the seat/ passenger location. The velocity of the side moving barrier at time of impact is designated to be 50 km/h. Because the scope of analysis did not include side impact dummies, injury assessment could not be made. Injury performance is greatly affected by interior trim panel and foam absorber design as well as by structural crush. Evaluation of passenger compartment intrusion can be made by looking at door and B-pillar displacements and intrusion velocities. Structural integrity can be assessed by looking at the overall shape of the deformation, including any gross buckling of the B-pillar, rotation of the rocker rails, crush of the front body hinge pillar, folding of the door beams and door belts, and cross-car underbody parts such as the seat attachment members and the rear suspension cross member. Chapter 6 - Page 32 Engineering Services, Inc. Figure 6.3.4-1 Side Impact Crash Analysis Setup The side impact undeformed and deformed shapes are shown in Fig. 6.3.4-2 and 6.3.4-3, with the deformed shapes shown after 80 ms of impact. During the early stage of the impact, the outer door structure crushes, the B-pillar is stable. As the impact progresses the rocker starts to buckle and causes also a bulging of the floor section. At about 30 ms, the still stable structure of the B-pillar is moved by the barrier inside the car and therefore the roof starts to bulge. After 40 ms the B-pillar develops an inward buckling. After about 64 ms the maximum dynamic deformation is reached. For the injury performance, the intrusion velocities of the structural parts, which could come in contact with the passengers, are important. Figures 6.3.4-5 and 6.3.4-6 show the intrusion velocities of typical points at the inner front door panel (No. 238) and the B-pillar inner (No. 235) (Fig.6.3.4-4). The following Figures 6.3.4-2 and 6.3.4-3 show the deformed shape of the side structure: Chapter 6 - Page 33 Engineering Services, Inc. t = 0 ms t = 80 ms Figure 6.3.4-2 Side Impact Crash Deformed Shapes Chapter 6 - Page 34 Engineering Services, Inc. t = 0 ms t = 80 ms Figure 6.3.4-3 Side Impact Crash Deformed Shapes of Side Structure No. 238 No. 238 No. 353 No. 353 Measured points for velocity Lower B-pillar enlarged Figure 6.3.4-4 Side Impact Time History Node Chapter 6 - Page 35 Engineering Services, Inc. Velocity vs. Intrusion Door Inner Panel No 353 10 9 8 Y - Velocity [m/s] 7 6 5 4 3 2 1 0 -1 -2 0 50 100 150 200 250 300 250 300 Y - Intrusion [mm] Figure 6.3.4-5 Side Impact Velocity vs. Intrusion at Node 353 Velocity vs. Intrusion B-Pillar No 238 10 9 8 Y - Velocity [m/s] 7 6 5 4 3 2 1 0 -1 -2 0 50 100 150 200 Y - Intrusion [mm] Figure 6.3.4-6 Side Impact Velocity vs. Intrusion at Node 238 Chapter 6 - Page 36 Engineering Services, Inc. The following table (Fig. 6.3.4-7) shows the side impact crash events: Time (ms) Side Impact 16.00 Buckling of the rocker in front of B-pillar 28.00 Buckling of the floor 35.00 Buckling of the roof 40.00 Buckling of the roof frame at the B-pillar 44.00 Buckling of the member kick up, still stable 48.00 Buckling of the brace tunnel 64.00 Maximum dynamic deformation reached Figure 6.3.4-7 Side Impact Crash Events The body side ring and doors maintained their integrity with only 248 mm of intrusion. The velocity of the intruding structure was tracked to determine the degree of injury an occupant may sustain. The maximum velocity was only 8 meters per second. The event is considered complete when the deformable barrier and vehicle reach the same velocity, in this case at 64 msec. Chapter 6 - Page 37 Engineering Services, Inc. 6.3.5. Roof Crush (FMVSS 216) The conditions for the roof crush analysis are based on United States, FMVSS 216. This requirement is designed to protect the occupants in event of a rollover accident. The surface and angle of impact are chosen to represent the entire vehicle impacting the front corner of the roof. The federal standard requires roof deformation to be limited to 127 mm (5 inches) of crush, and roof structure to support 1.5 times the vehicle curb mass or 5,000 lbs (22249 N), whichever is less. For test purposes and repeatability, the complete body in white is assembled and clamped at the lower edge of rocker and the roof crush test is done in a quasi-static force versus displacement arrangement. In the computer analysis, the software program, LS-DYNA, requires that the roof crush be done in a dynamic, moving barrier description as compared to the quasi-static test. Figure 6.3.5-1 shows the undeformed shape of the FE-Model used for the roof crush simulation. The shape of the structure after the limit of 127 mm deformation is shown in Figure 6.3.5-2. The force versus displacement curve is shown in Fig 6.3.5-3. The peak force of 36150 N is reached after a deformation of 72 mm of roof crush. Based on the curb mass of 1350 kg, the crush force of 19865 N is required for the federal standards FMVSS 216. The analysis was continued to 127 mm (5 inches) of deflection in order to determine the ability of the roof to sustain the peak load past 72 mm of crush. The analysis shows that the roof meets the peak load requirements and is steady and predictable. Chapter 6 - Page 38 Engineering Services, Inc. Figure 6.3.5-1 Roof Crush Undeformed Shape Figure 6.3.5-2 Roof Crush Deformed Shape Chapter 6 - Page 39 Engineering Services, Inc. Force vs. Deformation 40 127 35 30 Force [N] 25 20 15 10 5 0 -5 0 25 50 75 100 125 150 Deformation [mm] Figure 6.3.5-3 Roof Crush Deformation vs. Force Analysis showed that 22.25 kN was reached within 30 mm of crush. The structure resisted the applied load all the way up its peak of 36.15 kN and continued to maintain it quite well even after peak, when it dropped to about 28 kN at 127 mm. The load was well distributed through the A, B and C-pillars and down into the rear rail. 6.4. CAE Analysis Summary For the AMS Offset crash test the overall deformation and intrusion are the critical figures. For the NCAP crash test, the critical figure is the vehicle crash pulse. The target for the offset crash was to achieve low footwell intrusion. It is important to achieve a good balance between these two targets. The results of the crash analysis show that for the ULSAB a good compromise has been found to fulfill the AMS as well as the NCAP frontal crash, considering the dependencies between these two crash types. To achieve the low footwell intrusion for the AMS crash a rigid front structure is needed. A rigid front structure, however, means higher acceleration in the NCAP Chapter 6 - Page 40 Engineering Services, Inc. test and results in higher HIC (Head Injury Criteria) values for the passengers, with a maximum footwell intrusion of 149 mm for the AMS Offset crash and a maximum acceleration of 30.4 g for the NCAP crash, the ULSAB structure shows a good balance in these criteria. The results also document the high safety standards of ULSAB, especially if one considers that the NCAP crash analysis was run at 5 miles above the required speed of 30 mph and 36% more energy had to be absorbed. The rear crash test requirements are addressing the fuel system integrity and low deformation in the rear seat area. The analysis shows no collapse of the surrounding structure of the fuel tank, contact with the fuel tank itself or the fuel filler routing. Considering the fact that there was no rear seat structure the analysis also shows a low deformation of the rear floor. For the rear crash analysis in the ULSAB program, the requirement was raised from 30 mph to 35 mph velocity of the rear moving barrier, resulting in an increase of 36% of its kinetic energy. In the side impact crash test, good performance means acceptable intrusion of the side structure at low intrusion velocity. For both criteria the ULSAB achieved satisfactory results. The analysis shows a maximum intrusion of 250 mm and an intrusion velocity of 8 m/s at the inner door panel and the B-pillar. It is assumed that in a fully equipped car the intrusion will be even lower. For the roof crush test the Federal standard requires the roof deformation to be limited to 127 mm of crush and the structure to support 1.5 times the curb mass or 5000 pounds, whichever is less. The force requirement of 19500 N was already met at 27 mm of crush. The continued analysis showed that the structure is steady and peak load of 36 kN was met after 72 mm of crush. This result confirms the role the side roof rail plays as important part of the ULSAB structure. The ULSAB crash analysis has shown that reducing the body structure mass using high strength steel, in various grades and in applications such as tailor welded blanks combined with the applied joining technologies in the assembly, such as laser welding, does not sacrifice safety. The goal was to maintain the high standards of state-of-the-art crash requirements, without compromising the ULSAB program goal to significantly reduce the body structure mass. The crash analysis of the ULSAB supports that this goal is reached. Chapter 6 - Page 41 Engineering Services, Inc. 7. Material & Processes Engineering Services, Inc. 7. Material and Processes 7.1. Material Selection 7.1.1. Material Selection Process Based on ULSAB Phase 1 results, the body structure was redesigned in Phase 2 as described in earlier chapters of this report. With respect to the new influences, such as crash requirements and styling, new calculations had to be made. The calculations concerning static behavior gave us a first indication of the sheet metal thickness needed. This is because performance is mainly related to sheet metal thickness and the design itself, and not to the strength of the material, because the E-modulus is very similar for all steel types. After the initial material selection, the first loop of crash calculations was performed. As a result, the material grades and/ or the sheet metal thicknesses had to be adjusted. Several iterations of the “Material Selection Process” (Figure 7.1.1-1) lead us to the optimal strength/thickness level for each part. This procedure included a manufacturing feasibility check with our selected part suppliers. For the most critical parts, a forming simulation was performed simultaneously by the steel suppliers. The results of these simultaneous engineering processes have been important factors in successfully meeting the challenges of developing manufacturable parts. Different criteria during the material selection process such as formability, weldability, spring-back behavior, and static and dynamic properties were always taken into consideration. Always having “Production Intent” in mind, the focus was on production-ready materials, not on materials that are available only in laboratory scale. General material specifications and the definition of the different material grades are described in section 7.2 of this chapter. Chapter 7 - Page 1 Engineering Services, Inc. Material Selection Process No Start Phase 1 Package / Concept Design Phase 2 Package Refinement Create Styling Concept Modify Package/ Styling / Design Modify Phase 1 Shell Model Steel Supplier and Part Supplier Input Modify Design Material / Thickness Adjustement Meets Static Targets Yes No Meets Static/Crash Targets Create / Modify Phase 2 Crash Model Yes Meets Static Targets Create / Modify Phase 2 Shell Model Material / Thickness Selection, Design Modification No Yes No No Yes Parts Feasible Build of First Test Unit Meets Static / Crash Targets Yes Build of Final Demonstration Hardware Figure 7.1.1-1 7.1.2. Definition of Strength Levels In order to use the minimum variety of materials, every “master item” was defined by thickness and strength. The same master item could be used for different parts, as long as thickness and strength requirements were met, and the part suppliers and forming experts had no concerns. The definition of strength levels as used in ULSAB Phase 2 is shown next in the “ULSAB High Strength Steel Definition.” Chapter 7 - Page 2 Engineering Services, Inc. ULSAB High Strength Steel Definition The ULSAB program designates steel grades by specified minimum yield strength in the part. The following steel grades are utilized in the ULSAB design: Minimum Yield Strength Category 140 MPa Mild Steel 210 MPa High Strength Steel 280 MPa High Strength Steel 350 MPa High Strength Steel 420 MPa High Strength Steel Greater than 550 MPa Ultra High Strength Steel This definition was chosen in order to standardize the steel grade definitions for the ULSAB Consortium member companies since many countries are involved and the standards are not the same around the world. This has to be seen together with the goal that the ULSAB body structure could be built in every region of the world where steel is available. This is also the reason that the suppliers of the material for the DHs are kept anonymous within the ULSAB program. The most suitable material for each part application was chosen with the assistance of experts from the steel suppliers. This process was especially important for the ultra high strength steel because of its more critical forming behavior. Different materials such as dual phase (DP) steels are included in this group of ultra high strength material parts. There are several ways to achieve the 280 MPa yield strength level according to the above definition. This could be done by using microalloyed high strength steel, bake hardening or even dual phase steel. However it is achieved, the minimum yield strength for the finished part has to be 280 MPa in each area of the part. Other material qualities and material types could achieve the same or similar results; therefore, several factors affected material selection including material performance and availability. Chapter 7 - Page 3 Engineering Services, Inc. 7.1.3. Supplier Selection Once the “master items” were defined, the material supplier selection was made. This was done in material group meetings attended by all steel supplier experts and the design and manufacturing team of PES. For every part of the ULSAB, a minimum of two material sources were selected. The fact that different materials with the same yield strength level were available for each part (not only from different suppliers, but also in many cases different material types, such as microalloyed or dual phase) shows that most of the ULSAB parts could be made in multiple ways. No specially treated or designed material was necessary. Most of the material was taken from normal serial production at the steel mills. In order to practice simultaneous engineering most efficiently, the material suppliers were selected by their close proximity to the part supplier’s location (press shop). If the material failed during the first try-outs it was easier to react with corrective steps such as circle grid analysis, material tests, or forming simulations. Similar criteria were used in selecting the welding sources for the tailor welded blanks. In most cases two different companies could have provided the same welded sheet, each with slightly different material qualities. This again underscores that the ULSAB can be built with widely available material and part manufacturing technology. Chapter 7 - Page 4 Engineering Services, Inc. 7.2. Material Specifications 7.2.1. General Specifications General specifications for the material used on the ULSAB only concerned thickness tolerances, coating requirements and coating tolerances. The specifications are as follows: • • • Actual thickness of blanks must measure +0.00 mm/-0.02 mm of the specified thickness Coating may be electro-galvanized (Zn only) or hot dip (Zn or ZnFe) Coating thickness must be 65 gram/m² maximum (0.009 mm) per side with coating on both sides Every delivered material had to be tested at the supplying source before it was shipped to the part manufacturer. A test report accompanied the material until the parts are finished. This is the basis for the Advanced Quality Planning (AQP) report that was performed by the ULSAB Consortium. The test results are also considered for welding parameter evaluation at the prototype shop. 7.2.2. Material Classes 7.2.2.1. Mild Steel Definition Mild steel, which is described in Sec 7.1 Material Selection, is material with a yield strength level of 140 MPa. Mild steel can also be defined in terms of “Draw Quality,” “Deep Draw Quality” or “Extra Deep Draw Quality.” The material has no fixed minimum yield strength but does have a minimum elongation. Mild steels are the most common steels used in auto making today. This is because mild steel has forming and cost advantages compared to high strength steel. On the other hand, the ULSAB clearly shows that the amount of high strength and ultra high strength steel can be used up to more than 90% or more without any cost penalty. Chapter 7 - Page 5 Engineering Services, Inc. 7.2.2.2. High Strength Steel Definition The steel industry has developed various high strength steel qualities. In the ULSAB Phase 2 program the strength levels of 210, 280, 350 and 420 MPa were defined as high strength steel. The values are related to the strength of the finished parts as assumed in the FEA model. This includes additional strengthening as a result of the bake-hardening process also. High strength steels were used where the design required certain crash and strength characteristics. Within the range of this material group, different strengthening mechanisms can contribute to the final result. The DHs used microalloyed steels, phosphor-alloyed steels, bake-hardening steels, isotropic steels, high-strength IF - steels and dual-phase steels, all in the range of the abovementioned yield strength. This engineering report does not include a detailed description of alloying or other metallurgical processes that are used to produce those steel types. 7.2.2.3. Ultra High Strength Steel Definition Ultra high strength steels are defined as steels with a yield strength of more than 550 MPa on the finished part. Parts made from these steels can provide additional strength for front and side impact. In the ULSAB structure, all crossmembers of the floor structure were designed in ultra high and high strength steel. Today, there are different ways to achieve needed strength levels. This could be done for automotive sheet panels with dual phase (DP) steels, or with boron-alloyed types, which have to be hot formed. Within the ULSAB Phase 2, parts were made from DP steels. DP steels were feasible even on parts with a complex shape like the cross member dash. As of today, those types were also available in an appropriate thickness range, which is interesting for automotive applications, e.g. a thickness between 0.7 and 1.5 mm. Chapter 7 - Page 6 Engineering Services, Inc. 7.2.2.4. Sandwich Material Definition The use of sandwich material has contributed to considerable mass savings on the ULSAB. The sandwich material is made with a thermoplastic (polypropylene) core, which has a thickness of about 0.65 mm. This core is “sandwiched” between two thin outer steel sheets with a thickness of about 0.14 mm each. The polypropylene core of this sandwich material acts as a spacer between the two outer sheets, keeping the outer surfaces away from the neutral axis when a bending load is applied (see fig. 7.2.2.4-1). The mentioned material (total thickness about 0.96 mm when coated) has a very similar behavior compared to a solid sheet of steel with a thickness of about 0.7 mm. Steel Sheet 0.14 mm Polypropylene Core 0.65 mm Steel Sheet 0.14 mm Figure 7.2.2.4-1 Sandwich Material This sandwich material shares many of the same processing attributes with steel sheets, like deep drawing, shear cutting, bonding, etc. But, unfortunately, it cannot be welded. Even mechanical joining like riveting, clinching or screwing, can be a problem when the material has to go through the paint-baking oven. The core material is softened by the heat and flows away from the area where a pretension from a screw is applied. This may lead to a loss in joining strength. Therefore, applications used in the ULSAB Phase 2 design were with parts made from sandwich material that did not go through the oven. The spare tire tub is designed as a prepainted module, preassembled with spare tire and tools. This module will be dropped into place and bonded to the structure during the final assembly of the vehicle. No additional heat has to be applied. Another application of sandwich material is the dash panel insert, which was bolted and bonded into the panel dash during final vehicle assembly. Chapter 7 - Page 7 Engineering Services, Inc. Because there was no application similar to the spare tire tub in the past, an extensive forming simulation was performed on this part. Once the design was adjusted using the results of the simulation, there were no major concerns about the feasibility of the spare tire tub. After a small refinement of the best drawable radius, the parts were determined to be manufacturable with no problems. Furthermore, a physical test with the spare tire tub was performed to check the fatigue behavior of this material for the application. Parts from the described sandwich material were made and compared to parts made from solid steel sheets of 0.7 mm thickness. A picture of the test installation is shown below in Fig. 7.2.2.4-2. F Figure 7.2.2.4-2 Test Installation Chapter 7 - Page 8 Engineering Services, Inc. The load signal that was applied was taken from Porsche’s proving ground and adjusted to the situation of the ULSAB. The test concluded there are no restrictions for the use of the sandwich material for the proposed application when it is compared to a conventional design using a 0.7 mm solid steel sheet. The parts that were designed for the ULSAB could be made up to 50% lighter than those made of solid steel under similar dimensional and functional conditions. But, higher costs for the sandwich material have to be taken into consideration as compared to normal coated steel sheets. 7.2.3. Material Documentation As mentioned earlier, every “Master Item” (material defined by thickness and strength) was accompanied by a test report, which includes all important strength properties, r- and n- values and a coating description. Those tests were performed by the supplying steel mills. All the supplied materials are documented at PES with their corresponding values, such as blank size, properties, coatings, material type etc. The “Master List” was also the base for the documentation of the welding parameters and the DH build itself. When the parts were manufactured, the above-mentioned documentation was completed with additional information concerning press conditions for parts made at different locations. For those parts where a forming simulation and/or a circle grid analysis were performed, the documentation was extended with the results from these additional steps. These results are included in the earlier mentioned AQP report. To ensure proper and comparable documentation, material samples from every part, that goes into the DH were collected by PES and sent to a central testing source. At this neutral location, every collected material was tested in the same way and documented again. Chapter 7 - Page 9 Engineering Services, Inc. 7.3. Tailor Welded Blanks Introduction Tailored blanking for vehicle body structures is a well known process with the first applications being done for mass production which started in 1985. Below listed are the main reasons for PES´s decision to use tailor welded blanks in a relatively large number compared to vehicles already on the market: • • • • • • • Mass reduction due to the possibility of placing optimum steel thicknesses and grades where needed Elimination of reinforcements with appropriate material gage selection Simplified logistics due to the reduction of parts Investment cost reduction of dies, presses etc. due to fewer production steps Better corrosion protection by the elimination of overlapped joints Improved structural rigidity due to the smoother energy flow within the tailor welded blank parts Better fatigue and crash behavior compared to a conventional overlapped spot welded design solution 7.3.1. Selection of Welding Process Laser welding and mash seam welding are the most common processes for the manufacturing of tailor welded blanks today. Induction and electron beam welding have a minor importance and they are still under development. All these processes have their advantages and disadvantages, related to the process and the machine itself. Induction welding is a butt welding process. The necessary compressing of the two sheets creates a bulge with the consequence of an increase in thickness in the joined area. Those blanks could not be used in visible areas without an additional surface finishing process. A high accuracy during the movement of the sheets is important. The heating of the weld seam by induction / magnetic current over the total length leads to a larger heat affected zone when compared to laser welded blanks. Chapter 7 - Page 10 Engineering Services, Inc. The non-vacuum electron beam welding process is similar to laser welding in the result of the weld seam geometry. This is due to the fact that it is a non-contact process as well. The beam is a mass beam and the kinetic energy of this beam is used for heating the material. The beam can be focused by a magnetic spool and the diameter can be adjusted easily. The advantage of this process compared to laser is the increased efficiency of about 90% compared to 10% when using laser. But a disadvantage is that the electron beam creates x - rays. This influences the machine design dramatically regarding total investment and material handling. Therefore this process is not used extensively up to now. Mash seam welding needs a narrow overlapping of the sheets which have to be welded. The material in this area becomes doughy, not really fluid. During the welding process the current flows from one electrode to the other one and by resistance heating the sheet material becomes doughy. The electrode force then mashes the weld area and the sheets are joined together in this way. This light overlap and the joining process by force loaded electrodes results in a weld zone between 2.5 and 3.0 mm. The coating maybe is affected in this zone negatively. Furthermore, experience has shown that the surface of the weld zone, where little caves and pinchers occur due to the mash welding process, may not achieve the required corrosion resistance. The laser welding process is used more and more widely. It is a non-contact welding process, and the heat is brought into the material by a coherent light with high energy density. In this way a very narrow weld zone can be achieved. There is almost no influence on the corrosion resistance when coated material is used. The main critical point on this process is without any doubt the need for very precisely prepared edges of the sheet. But this problem could be overcome by today’s available precise cutting technologies or advanced fixing and clamping devices. One of the biggest advantages is the possibility of a non-linear weld line layout. Different combinations of laser sources and clamping devices are on the market today. In many cases the sheets are moved relative to the fixed laser beam. This may lead to a reduction of the cycle time of the whole process. Chapter 7 - Page 11 Engineering Services, Inc. Together with the fact that most of the newest installations for welding blanks are laser equipped devices, and the positive experience of PES, has lead to the decision to use laser welded tailored blanks on the ULSAB body structure exclusively. The blanks were produced at different locations using different equipment from the whole range of possible installations. The weld lines were controlled during the joining process to maintain the following features: • • • • • width of the remaining gap mismatching of blank edges blank position seam geography (concavity, convexity) lack of penetration All of these lead to the high quality of today’s tailor welded blanks. 7.3.2. Weld Line Layout The weld line layout was mainly driven by the crash calculation results. Forming feasibility requirements also influenced it. On some of the most critical parts, e.g. the body side outer panel, a forming simulation was performed. Necessary changes from this simultaneous engineering process were incorporated in the weld line layout. The following parts on the ULSAB body structure were designed as tailor welded blanks: • • • • • • • • Front Rail Outer Front Rail Inner Panel Rocker Inner Rear Rail Inner Rear Rail Outer Panel Body Side Outer Panel Wheelhouse Outer Panel Skirt Chapter 7 - Page 12 Engineering Services, Inc. The weld line layout is shown in the following pages for each part. ULSAB 008 - Rail Front Outer 1.6 1.5 (350 MPa) (350 MPa) 2.0 (350 MPa) ULSAB 010 - Rail Front Inner 1.5 (350 MPa) 1.6 (350 MPa) 1.8 (350 MPa) ULSAB 042 - Panel Rocker Inner 1.7 (350 MPa) 1.3 (350 MPa) Chapter 7 - Page 13 Engineering Services, Inc. ULSAB 046 - Rail Rear Inner 1.6 (350 MPa) 1.3 (350 MPa) 1.0 (350 MPa) ULSAB 048 - Rail Rear Outer 1.6 (350 MPa) 1.3 (350 MPa) 1.0 (350 MPa) ULSAB 060 - Panel Body Side Outer 1.3 (280 MPa) 0.7 (210 MPa) 1.5 (350 MPa) 1.7 (350 MPa) Chapter 7 - Page 14 0.9 (280 MPa) Engineering Services, Inc. ULSAB 070 - Panel Wheelhouse Outer 0.8 (210 MPa) 0.65 (140 MPa) ULSAB 096 - Panel Skirt 2.0 (140 MPa) 1.6 (140 MPa) Chapter 7 - Page 15 Engineering Services, Inc. 7.3.3. Production Blank Layout Figure 7.3.3.-1 For the Economic Analysis cost calculation purposes, the production blank layout for the tailor welded blank parts was developed. 7.4. Hydroforming 7.4.1. General Process Description Today, tubular hydroforming is a well-established process in automotive manufacturing. When ULSAB Phase 1 began several years ago and hydroforming was chosen as the manufacturing process for the side roof rail, the technology was being used mainly for exhaust pipes and some front cradles. These had a much smaller diameter-to-thickness ratio compared to the ULSAB side roof rail. But with the focus on mass savings, it was assumed that hydroforming could reduce the number of parts while helping to optimize available package space. Chapter 7 - Page 16 Engineering Services, Inc. The hyroforming process is described very simply as: “put a tube between a lower and an upper die, close the die, fill the tube with water and increase the internal pressure in order to force the tube to expand into the shape of the die.” However, several things must be taken into consideration within this process technology. This method will work only for straight tubes. In all other cases the tube has to be prebent or preformed depending on the final shape. The various steps necessary for the manufacturing of the ULSAB side roof rail will be explained in the next section. 7.4.2. Benefit for the Project As explained in the Phase 1 report, the use of hydroformed parts instead of conventionally formed and spot-welded structures have certain apparent advantages. Because of the absence of flanges, available space could be utilized with higher efficiency (bigger cross sections were achievable). The homogeneous hydroformed parts also provide an improved load flow in comparison to other structural members made of several parts joined by spot welding. The side roof rail represents a significant structural member in the ULSAB structure and provides an optimal load distribution from the A-pillar along the roof into the B and C-pillar. This is true for the static as well as for the dynamic behavior of the body structure. Also the side impact and the rear crash support is affected positively. The interior of the vehicle is well protected by the “roll bar” design of these two structural members integrated into the body structure. The hydroformed parts described in ULSAB Phase 1 already have led to similar applications in vehicles that are on the road today. There is a high potential for further steel applications on comparable parts that are loaded with high forces. Other opportunities for hydroformed steel structures will be in the area of protection systems for convertibles. Chapter 7 - Page 17 Engineering Services, Inc. 7.4.3. Forming Simulation (Review) First, a feasibility check was made using the predicted bending line along with analyzing the material distribution over the circumference in different cross sections. Next, the design of the side roof rail was analyzed and optimized for feasibility by conducting a forming simulation. Simultaneous engineering was used by the team consisting of PES and the part manufacturer; a similar approach was used for the development of the conventional stamped parts. Conducting a forming simulation for parts like the side roof rail is much more complex than for stamped parts. This is because material properties that are affected by a combination of processes such as prebending, preforming and hydroforming are very difficult to calculate. The first forming simulation has shown that wrinkles will occur during a very early stage of the forming process in the area where the tube was first prebent. The next step is to preform in a different direction to make it fit into the hydroforming tool. A picture of this area taken from the forming simulation program is shown in Figure 7.4.3-1. Figure 7.4.3-1 Forming Simulation As a result of this analysis the design of the side roof rail was modified so that some bending radii were softened. Also some other areas were slightly changed in order to prevent excessive material thinning or cracking during the forming process. The forming simulation also led to the decision of using a separate preforming tool (described in Sec. 7.4.5). Chapter 7 - Page 18 Engineering Services, Inc. 7.4.4. Tube Manufacturing Certain material qualities have to be defined. Standard tubes, beside the fact that the required diameters with the needed thin wall were not available commercially, have no high demand concerning transversal elongation. But this is one of the main factors during the hydroforming process when the tubes are expanded. Even if the difference in diameter on different cross sections of the tube is relatively low, certain areas of the ULSAB hydroformed side roof rail required a high degree of elongation. During the design process, differentiation must be made between local elongation (between two points of the circumference) and the overall elongation (total difference in circumference in a cross section). These two factors must also be taken into consideration for the longitudinal shape of the part. Transitions between shape changes of the cross sections should be as smooth as possible and high elongation is needed. The above mentioned facts led to the decision to manufacture tubes for the ULSAB side roof rail from material different to what is used for conventional tubes. Tubes were made, therefore, from high strength steel sheets to meet yield strength requirements and to have uniform elongation in both directions. High work hardening, which should be achievable by this material, is an important factor as well. Tubes can be made in several different ways. One way is to manufacture them with a continuous roll forming and high frequency welding. This has to be done with extremely high accuracy of the weld geometry especially on such thin walled large diameter tubes. Because the burr (which is unavoidable in this process) has to be removed in an additional planing operation (scarfing), not all of the welds are able to meet the tube specifications. Another approach is to use non-contact laser welding for the joining process. This eliminates the burr and therefore no additional operations are needed; it also creates a much-narrowed heat-affected and dezinced zone. For these reasons the tubes for the ULSAB structure were laser welded. Chapter 7 - Page 19 Engineering Services, Inc. For the prebending process, which requires a tube with small tolerances and a finished part with high strength, the following tube specifications were created: Quality Feature: Material: Yield Strength: Total Elongation: Uniform Elongation: r - Value: Precision steel tube according to the following tolerances Zinc coated on both sides details see below > 260 N/mm² (> 280 N/mm² on finished parts) > 32% (longitudinal and transverse) > 20% > 1.80 Dimensions and Tolerances Outside Diameter: 96 mm +0.1 / 0 Wall Thickness: 1.0 mm; tolerances according to ULSAB specification Total Tube Length: 2700 mm +/- 1 Cutting of Tube Ends: Free of Burr No ovalization or cave-in No chamfers Rectangular to longitudinal axis +/- 0.5° Appearance of Tubes Surface: Free of mechanical damage, splatters, etc. No collapsed areas (no indents, bulges, etc.) Free of impurities (swarf, weld chips etc.) Welding Requirements Welding Process: Laser- or high-frequency welding Weld Seam Area: Outside of tube: Undercut 0.0 mm, no expansion Inside of Tube: Undercut < 0.2 mm, no expansion No mismatch of edges Free of any porosity Strength similar to base material Chapter 7 - Page 20 Engineering Services, Inc. 7.4.5. Process Steps for Rail Side Roof Because the side roof rail has several 2-dimensional bendings with different radii over its length and two 3-dimensional curves in the rear portion, the straight tube has to be prebent. At the beginning of the design phase, bending tubes with such a high diameter (96 mm) -to-wall-thickness (1.0 mm) ratio resulted in very poor bend quality. At first, the tubes were bent by using a conventional mandrel-bending machine modified in such a way that the mandrel was replaced by internal fluid pressure. This inside pressure is working as a substitute for a mandrel. The purpose of this was to maintain stricter tolerances which are directly related to the accuracy of the bending tools, the diameter of the mandrel used, and the tube diameter and wall thickness. In this way, the tubes could be bent into the needed shape without any wrinkles. However, because the pressure was applied inside the whole tube, the tube diameter increased to a point that the tube would not fit into the next die. Therefore, Porsche went back to using the solid mandrel. By holding to stricter tolerances and taking certain other steps, wrinkle-free tubes could be formed. With this process, the clamping force needed to avoid wrinkles or damage to the tube has to be kept within a tight tolerance. Once the tube is prebent, preforming is the next step. This is done in a three-piece tool under low internal pressure to avoid collapsing. The tube is then flattened and bent again in order to fit into the final hydroforming die. The basic layout of the preforming tool and the tool itself is shown in Figure 7.4.5-1, 2 & 3. Outer tool part Tube Section A - A Moving direction of outer tool part Inner tool part Upper tool part not shown Figure 7.4.5-1 Preforming Tool Concept Chapter 7 - Page 21 Engineering Services, Inc. Tube filled with water under low pressure Outer tool part moved to inner pert Upper tool part closed Pressure released and die opened Figure 7.4.5-2 Sec. A-A of Preforming Tool Concept Upper tool part Inner tool part Outer tool part Figure 7.4.5-3 Preforming Tool Chapter 7 - Page 22 Engineering Services, Inc. The final step is the hydroforming process itself. During the down movement of the upper half of the die there is another area preformed again (under low internal pressure) on the tube. This must be done because the hydroforming process is very sensitive to die locking. Once the die is finally closed, the internal pressure is increased and the side roof rail tube is calibrated into its final shape. The pressure has to be raised to 900 bar for the side roof rail in order to set the final shape of the part. This required a closing force of about 3200 tons. This internal calibration pressure was higher than predicted by calculation and forming simulation. A picture of the hydroforming tool is shown in Fig. 7.4.5-4. Figure 7.4.5-4 Hydroforming Tool Chapter 7 - Page 23 Engineering Services, Inc. 7.4.6. Results Hydroforming has never been used previously to form a high strength steel tube with such a high diameter-to-wall-thickness ratio. Nevertheless the goal to manufacture the side roof rails was achieved. There is still room for improvement, but the main problems related to the bending and preforming operations were resolved. Hydroforming will be only a calibration operation if all-important steps before this were optimized. With the experience gained from the ULSAB Phase 2, producing similar hydroformed applications should be easier in the future. Chapter 7 - Page 24 Engineering Services, Inc. 7.5. Hydromechanical Sheet Forming 7.5.1. General Process Description Hoods, roofs and door panels (large body outer panels) produced by conventional forming methods often lack sufficient stiffness against buckling in the center area of the part. Due to the low degree of deformation in the center, there is only a little work hardening effect that could be achieved. Therefore, material thickness has to be increased to meet the dent resistance requirements on those parts. This of course leads to heavier parts and creates extra costs. The “active hydromechanical sheet metal forming process” is a forming technology that uses an active fluid medium. The die consists of three main components: a drawing ring, which is designed as a “water box,” the blankholder (binder) and the drawing punch itself. At the beginning, the die is open and the blank is loaded on the ring (see figure 7.5.1-1). Slide Cylinder Blankholder Cylinder Slide Blankholder Moving Balster Figure 7.5.1-1 Active Hydro-Mec Process Step: Loading / Unloading Chapter 7 - Page 25 Engineering Services, Inc. In the second stage, the die is closed and the blankholder clamps the blank. The die punch has a defined, part specific regress against the clamped blank, as in figure 7.5.1-2. A pressure intensifier is used to introduce the water emulsion into the water box, where a pre-set pressure is generated. The blank is inflated in a controlled manner and stretched over the complete area until it is pressed against the punch. This is the reason why the process is called “active hydromechanical sheet metal forming.” Forming with fluids (or flexible rubber layers) is well known already, but previously there was no forming in the “opposite” direction within those processes. The plastic elongation produces a work-hardening effect, especially in the center of the part. This effect significantly improves the dent resistance of the formed part. Figure 7.5.1-2 Active Hydro-Mec Process Step: Pre-forming Chapter 7 - Page 26 Engineering Services, Inc. Once the first plastic elongation process is done, the draw punch is moved downward, as in figure 7.5.1-3. At the same time, the emulsion is evacuated from the water box and the pressure of the fluid is lowered in a controlled process. After completion of the drawing operation, pressure is increased once more in order to calibrate the part into the final shape. The later visible surface of the part (outer side) is turned towards the active fluid medium. There is no contact to metal on this surface and an excellent surface quality of the part was achieved. Source: SMG Engineering Germany Figure 7.5.1-3 Active Hydro-Mec Process Step: Forming Completed Chapter 7 - Page 27 Engineering Services, Inc. A picture of the formed roof panel is shown below in figure 7.5.1-4. Figure 7.5.1-4 Roof Panel 7.5.2. Benefit for the Project The active hydromechanical sheet metal forming process is characterized by improved component quality and potential mass and cost reduction. The essential features of this new technology are: higher dent resistance achieved by an increased work-hardening effect during the first “counter” forming operation, and superior visible surface quality achieved by using water instead of a metal die for the final forming operation. This leads to a reduced component mass due to increased stability. Sheet thickness could be reduced to 0.7 mm and reinforcement elements could be saved, while all other requirements were still fulfilled. In addition, the cost of dies can be reduced by about 40% because only one polished half of the die is required. In addition, the average lifetime of the dies will last longer, under mass production conditions, than usual because there is little wearing off when forming with a fluid medium. In order to get the most benefit out of this process a forming simulation should be performed. This simulation may help to predict the maximal prestretching amount achievable without damaging the sheet. The absence of friction between the blank Chapter 7 - Page 28 Engineering Services, Inc. and the conventionally used second half of the die makes the result of the simulation very reliable. Furthermore, the process parameters, (e.g., preforming pressure, etc.) could be easily adjusted. 7.5.3. Process Limitations Depending on the grade of prestretching, which is related to the preforming pressure, the size of the forming press (locking force) has to be chosen. This is also influenced by the overall projected area of the part (e.g., for the ULSAB roof panel, a press with a locking force of 4,000 was chosen.) A double (or triple) action hydraulic press must be used to make the process reliable. This press can be used for conventional forming, and with the use of some additional equipment, for the tubular hydroforming process. The filling time for the fluid medium pressure bed has to be taken into account as well. This leads to a calculated cycle time for the ULSAB roof panel of about 30 - 40 seconds. Depending on the design of the part, this has to be compared to a two-step conventional forming operation. Due to potential die locking, it appears that an undercut on the hydroformed parts is not feasible in this process without using a separate tool. This is also relevant for the cutting of flanges. This has to be done separately using laser or conventional trimming operations. Chapter 7 - Page 29 Engineering Services, Inc. 7.5.4. Results Roof panels for the ULSAB could be manufactured by using the active hydromechanical sheet metal forming process. Different material qualities, like isotropic, IF and bake-hardening types, were formed successfully. Due to the workhardening effect, which was applied through the above-described process, the sheet thickness of the roof panel could be lowered to 0.7 mm, while the dent resistance requirements were still met. In order to limit the needed locking force of the press, the flange radii should be designed not too small. The radii are directly related to the needed pressure during the final forming operation, and if too small lead to an uneconomic high-locking force/press size. The surface quality on the visible side of the ULSAB roof panel, which was not in contact with any metal tool, was very high compared to conventional formed (prototype) parts. Chapter 7 - Page 30 Engineering Services, Inc. 8. Parts Manufacturing Engineering Services, Inc. 8. Parts Manufacturing 8.1. Supplier Selection The main criterion for supplier selection was quality. Although the process used “soft” tools and lasers, the contract required production representative parts. Therefore, it was decided to identify companies that specialize in one or more of the following system groups: • • • • • Front End Structure Floor Panels and Body Side Inner Body Side Outer Rear Structure Roof and Roof Side Rails Extensive discussions took place with approximately 30 suppliers on a worldwide basis to identify the sources for the ULSAB program. The criteria used to rationalize the final selections were: • • • • • • • Supplier must have major OEM quality rating or ISO 9000 Must be a system supplier to a major OEM Must be prepared to enter simultaneous engineering prior to contract release CAD/CAM systems compatible with CATIA Program management system established Experience in match metal checks Cost competitive Chapter 8 - Page 1 Engineering Services, Inc. Based on the foregoing, the following companies were selected: • • • • • Front End Structure – Stickel GMBH, leading supplier to Porsche AG Floor Panels and Body Side Inner – Peregrine FormingTechnologies, supplier to GM, Chrysler and Ford Body Side Outer – AutoDie International, leading Body Side supplier to Chrysler, also supplying Ford and GM Rear Structure – Fab All Manufacturing, commodity supplier to Ford Roof and Roof Side Rails – Schaefer Hydroforming Number of Employees Company Name Address Autodie International 44 Coldbrook, Grand Rapids, Michigan, USA 700+ Major products Tools, Dies and Molds, Prototypes & Production Automated Systems Transfer Equipment Welding Fixtures Robotic Vision Systems Other Divisions Customers Progressive Tool WISNE Design WISNE Design - Die Technology WISNE Automation Eagle Engineering Freeland Manufacuturing + Others Chapter 8 - Page 2 Ford Chrysler Tower Spartanburg Navistar Cambridge Major Equipment GM Jaguar BMW Karmax Haworth Presses up to 3000 t Bed Size to 200 x 100 4 CMM 5 Axis Control Laser 1 Lamoine Machine System CNC Mills PDGS CGS CATIA Engineering Services, Inc. Company Name Number of Employees Address Peregrine Forming Technologies 26269 Groesbeck, Warren, Michigan, USA 160 Major products Prototype Tooling Stampings and Assemblies Doors Inner / Outer Cowls, Fenders, Deck Lids Roof Panels and Floor Panels Other Divisions Customers APG - Technical Services Battle Creek Stamping Warren Stamping Warren Assembly Major Equipment Ford GM Dana Tower Ogihara Honda Spartanburg Presses up to 1500 t Bed size to 192 x 79 3 CMM 5 Axis Control Laser Foundry 3 CNC Mills PDGS CGS CATIA Number of Employees Company Name Address Fab All Manufacturers 645 Executive Drive, Troy, Michigan, USA 95 Major products Prototype Tools Stampings and Assemblies Specializing in Underbody, Front Structures and Inner Structures Other Divisions Hubert Group Sharp Mold Engine M & T Design Services Models & Tools Customers GM Ford Chrylser AG Simpson Veltri Narmco Major Equipment Presses up to 1700 t Bed size to 144 x 132 2 CMM 6 Axis Laser NC Machining CATIA PDGS CGS Unigraphics Chapter 8 - Page 3 Engineering Services, Inc. Company Name Address Stickel GmbH Porschestrasse 2, D - 74369 Loechgau Number of Employees 40 Major products Prototype Build Prototype Tooling, Prototype Stampings Low Volume Production Stampings and Subassemblies Other Divisions Customers None Audi BMW Mannesmann Mercedes Benz Opel AG Porsche AG Major Equipment Presses up to 800 t Bed sizes up to 2m x 3m 3D Laser CMM Equipment CATIA CGS Number of Employees Company Name Address Schäfer Hydroforming, Schuler Auf der Landerskrone 2, D - 57234 Wilhelmsdorf 135 Major products Hydroforming Presses (Development, Fabricating) Prototype and Production Parts Technology Development (Active Hydro Mec) Other Divisions Customers Tool Shop FEM Forming Simulation Hydroforming Componenets Chapter 8 - Page 4 Audi Aerosmith GM Benteler Porsche Major Equipment Hydroforming presses to 3000t 10.000 t under Construction High Speed Miling Prebending Equipment Engineering Services, Inc. 8.2 Simultaneous Engineering In order to achieve the optimal design from a manufacturing and assembly standpoint, reviews were held with the suppliers and the assembly facility to evaluate all designs six months prior to design release. Each supplier was represented by specialists in CAD/CAM, tool making and manufacturing. Every detail was reviewed for formability, spring back issues, aesthetic consideration, tolerance control and assembly issues. In addition to the part suppliers, steel companies also attended these sessions in order to discuss and resolve any material issues. These reviews continued after design release, primarily in the suppliers’ facilities, but in addition to the design for manufacture and design for assembly, the reviews also included the supplier maintaining quality and timing plans. 8.3. Part Manufacturing Feasibility Introduction At the request of the ULSAB Steel Consortium and PES, Phoenix Consulting Inc. has assisted in the investigation and documentation of the manufacturing feasibility of the ULSAB components. The study includes the following objectives. • Demonstrate that the processes used to fabricate the ULSAB components meet the following conditions: , Used design intent materials. , Can repeatedly produce parts that meet dimensional requirements. , Can repeatedly produce parts that meet formability requirements. • Demonstrate that through continuous improvement, these processes can be evolved to production capable processes. , Mechanisms are in place and are being followed to address manufacturing feasibility concerns. , Action plans have been developed to address remaining barriers to production capability. Chapter 8 - Page 5 Engineering Services, Inc. • Demonstrate that state of the art methods and technologies have been used to develop the demonstration hardware processes, such as: , Forming Simulation. , Early Steel Involvement. , Dies and fixtures developed from CAD, CNC Machining and CMM Inspection. Overall Assessment Although the components of the ULSAB body structure certainly present a significantly greater challenge to production capability than a conventional design, we are convinced that these components can be fabricated with production capable processes under the following conditions: 1.The process of continuous improvement that has been undertaken by Porsche is continued, including additional soft die tryout and minor product revision. 2.With the use of the more sophisticated press equipment that can be made available in hard tool construction: Multiple Nitrogen Cushions, Toggle Presses and with the superior surfaces encountered in hard tooling. 3.With the implementation of further enhancements in materials, blank development and binder development. The team assembled to fabricate these components has made excellent progress along the learning curve of fabricating with high strength steel and laser welded blanks, advancing the state of the art. The prototype processes have undergone significant continuous improvement toward production capability Documentation Overview The components on the ULSAB body have been classified into three levels of difficulty or criticality. Level C being the most critical, level B the next most critical and all other parts are level A. The extent of documentation provided for a given component has been determined accordingly. The purpose of these documents is to validate the objectives outlined in the introduction. These documents have been assembled into a notebook that can be provided through the ULSAB Consortium. Chapter 8 - Page 6 Engineering Services, Inc. These documents are described below, followed by a list of B and C level parts. In the pages that follow is an example of the detailed summaries for each individual B and C level part that can found in the notebook. Level A - Non Critical • Material Characterization. This validates that the parts are made of material that meets structural requirements and that these materials can be worked into the forms of the respective parts. Level B - Moderately Critical. All Level-A requirements plus the following: • • • Strain Analysis (Circle Grid and or Thickness Strain): Demonstrates that a formability safety margin exists and that parts are not merely split free. The goal and conventional buy off requirement is a 10% safety margin. These Strain Analyses are the responsibility of the Steel Vendors as part of the Early Involvement Program. They should include material properties of metal used to form the evaluated panel and the associated press conditions. This information is documented in AQP Parts format. Process Set Up: After extensive tryout, die shops have arrived at, and documented, optimum press conditions that will repeatedly yield quality panels. These Press Conditions along with other details of die set up are documented on Set Up Sheets. These Set Up Sheets can serve as baseline for further continuous improvement to develop production capable processes. Part submission warrants: These certify that prototype parts meet dimensional requirements. Chapter 8 - Page 7 Engineering Services, Inc. Level C - Most Critical: All level A and B requirements, plus the following. • • • • CMM Reports: Computerized measurement of dimensional integrity. Development Logs: Show that state of the art methods and technologies were used to develop prototype processes and that these processes are undergoing a continuous improvement of evolution toward production capable processes. Proposed Production Process: This is the capstone of the above efforts. It is the culmination of lessons learned in prototype tryout and a demonstration of Porsche’s confidence that the next step of setting up production processes can be taken. Forming Simulation: Finite Element Analysis based on CAD data was used to identify formability concerns before the construction of tools. B and C Level Parts Part Name Part Number Die Shop Level 040 Peregrine C Panel Rocker Inner 042 / 043 Peregrine C Panel B-Pillar Inner 064 / 065 Peregrine C Rail Rear Inner 046 / 047 Fab All C Rail Rear Outer 048 / 049 Fab All B Panel Wheelhouse Outer 070 / 071 Fab All B Panel Body Side Outer 060 / 061 Autodie C 026 Stickel C Panel Skirt (& Shock Tower) 096 / 097 Stickel C Rail Front Inner 010 / 011 Stickel B Rail Front Extension 012 / 013 Stickel B Panel Dash 021 Stickel B Member Kick Up 091 Stickel B 072 / 073 Schaefer C Panel Roof 085 Schaefer B Spare Tire Tub 050 Stickel B Pan Front Floor Member Dash Front Rail Side Roof Chapter 8 - Page 8 Engineering Services, Inc. Documentation Forming Simulation Strain Analysis (Circle Grid, Thickness Strain) Material Characterization Process Set Up (Set UP Sheets) Proposed Production Process Certification of Dimensional Integrity (Warrant) Inspection Report Development Log. Demonstrates state of the art procedures used to develop capable prototype processes & action plans for making processes production capable. Observations and Recommendations Responsible Format Parts Steel Co. Steel Co. Report Select Parts Steel Co. Steel Co. and Phoenix Steel Co, Die Shops and Phoenix Porsche & Phoenix Die Shops AQP B&C AQP Phoenix Summary & Die Shop Set Up Sheet Process Sheet Die Shop Form A, B & C Die Shops CMM or Checking Fixture Report C Die Shops Die Shop Log C Phoenix Phoenix Summary B&C B&C C B&C Summaries of individual B and C level parts. On the following pages you will find an example of the documented data. Included will be: 1.Summary page, including observations and recommendations. 2.Part diagram. 3.Documentation checklist, listing and/or summarizing required documentation. 4.Material characterization sheet. 5.Forming limit diagram (part of strain analysis). NOTE: Complete documentation for all A, B & C level parts is contained In a separate report obtainable through the ULSAB Consortium. Chapter 8 - Page 9 Engineering Services, Inc. Pan Front Floor - 040 Part Manufacturing Feasibility Summary The process involves first forming the front of the panel down, then the middle of panel the down and finally the rear of the panel up. This had to be done in separate operations for several reasons. One was press bed size. Another was the fact that all these areas are on separate levels and proper control of metal cannot be obtained without a more elaborate process involving nitro cushions and dydro units. The availability of these resources for production will enable a reduction in the number of operations, which will be necessary to reduce the total number of operations once trim and flange dies are added. Trimming and flanging is currently performed by laser and hammer form and will require cams in production due to the orientation of some of the trim and flange lines. Marginal strains detected in tryout and GD&T (geometric dimensioning & tolerancing) issues would have to be reassessed after implementing the recommendations below. Recommendations Based on Documentation Checklist Investigating grade change to a dent resistant steel that meets yield strength requirements but has a higher n-value. A dry film lube trial is also recommended. Consider use of a wider blank. This will allow for better control of metal outside of the kickup area by adding a more gradual transition in the addendum and binder. This may also enable the use of patches of higher formability metal where they are needed the most. This exercise would be well worth the effort, considering the portion of overall weight represented by the floor pan, and the challenging forming characteristics associated with it. Consider ways of forming embossed areas as late as possible in the process, either by using restrike die or by delayed action in draw dies, to avoid metal locking on and/or skidding over embossed area when it is required for feeding deep formations. Forming Simulation of first draw predicted wrinkling in tunnel near kickup. This is one of the areas where wrinkling was encountered in tryout. Chapter 8 - Page 10 Engineering Services, Inc. Marginal Forming Strains at locations #2 and #15. Second Form First Form #15 Third Form #2 Increase blank width and implement smooth transition & drawbar. Embossments impede metal flow; result in double draw lines. Implement laser weld for wider blank. Chapter 8 - Page 11 Engineering Services, Inc. ULSAB Part Manufacturing Feasibility Study Documentation Checklist Leve Part l # Part Name Supplier Spc Thk Yield Strength Coating Blank C Pan Frt Floor Peregrine 0.7 mm 210 MPa 60G60GU Rectangle 040 Document Format Status / Summary Forming Simulation Steel Co AQP Material Test Press Conditions Material Test Final / Conam Process Set Up LS-Dyna3D simulation of 1st draw predicted significant wrinkling in the step area of part near the tunnel. This is one of the areas where wrinkling was encountered in tryout. The other areas occurred mainly during subsequent operations. Reports 40_D1.TXF (First Form) & 40_D3.TXF (Third Form) Safety Margin = 3%. Dry film lube trial suggested. Marginal Strains (#2, #15) need to be re-assessed after implementing blank config, binder and die process improvements. Included in AQP. Also see Process Set Up below. AQP Samples shipped to Conam on 12/11/97 Peregrine Proposed Production Process Dimensional Check Dimensional Check Peregrine Set Up Sheet summary: Blank Size = 1829mm x 2057mm 1) PreDraw = Three piece stretch forms tunnel and kickup 2) Draw = Single Action with Upr Binder on Nitro forms deep pocket at rear of kickup 3) Three piece stretch forms shape at rear of panel 4) Flange. Flange at kickup is hand formed. Would have to be Cam Flanged in production. All trimming is by laser. Form #1 Ram = 1000 ton Binder = 160 ton (40 cyl @ 1600 psi) Lube = Quaker Prelube Form #2 Ram = 400 ton Binder = 100 ton Lube = Super Draw Form #3 Ram = 400 ton Binder = 200 ton (toggle press) Lube = Super Draw 1) Draw 2) 1st Trim 3) Re-strike 4) Form/Cam Form 5) Final Trim/Cam Trim Warrant Included CMM Report CMM detected points that deviated from nominal by more than +/- 0.5 mm, however all were vertical and attributable to part length and flexibility, or hammer formed flanges. No difficulty experienced in assembly. Simultaneous Engineering procedures were used to develop the process, and continuous improvement was implemented to evolve the process toward production capability. Supplier concerns were fed back to Porsche and product revisions were subsequently implemented. Summary of development history and log of product changes is included. Also included is sketch of part showing significant manufacturing related changes. Strain Analysis Development Log Chapter 8 - Page 12 Engineering Services, Inc. Chapter 8 - Page 13 Engineering Services, Inc. Chapter 8 - Page 14 Engineering Services, Inc. Chapter 8 - Page 15 Engineering Services, Inc. 8.4. Quality Criteria The quality assurance system utilized on the ULSAB project followed the same standards as normal automotive practices. The key elements of control were: • • • • • Material Engineering levels Process control Dimensional accuracy Parts submission Material: All material received was checked for dimensional accuracy by the part suppliers, the steel suppliers provided the material characterization data which was verified by an independent laboratory. Additionally, Porsche checked the material for weldability. Engineering Levels: A strict engineering change control system was implemented for this program. At each weekly review meeting all product levels were checked against the design status to insure compatibility. Suppliers were not allowed to implement any change without the authorization of PES. Process Control: As previously stated, the components were produced to production intent standards. Therefore, to insure this occurred, regular audits of the process were undertaken. Dimensional Accuracy: For each component, automotive standard checking fixtures were produced. These fixtures were used throughout the development process to provide verification of dimensional accuracy. Additionally for all major parts, the contract with the suppliers called for two fully CMM checked samples. As further assurance, where possible, match checks were undertaken to insure fit and function for the assembly process. Parts Submission: The approval process was based on PPAP (Production Part Approval Process) as outlined in QS 9000 guidelines. Before any part was shipped, the supplier had to provide documentation that showed all material, engineering, process and dimensional controls had been completed and met with the specifications set within the program. Chapter 8 - Page 16 Engineering Services, Inc. 9. DH Build Engineering Services, Inc. 9. DH Build 9.1. Introduction After ULSAB Phase 1 was successfully completed, the ULSAB Consortium decided to proceed with the ULSAB program into Phase 2. This involved proceeding from a conceptual study to the real world hardware, whereby the predicted mass savings and improved performance could be proven by actual product. Due to the experience in laser welding, Porsche’s R & D Center in Weissach, Germany was chosen for the execution of the 13 DH builds. Figure 9.1-1 Prototype Shop Chapter 9 - Page 1 Engineering Services, Inc. 9.2. Joining Technologies 9.2.1. Laser Welding For more than 10 years the laser has shown its production capability. The first auto body application was the blank welding of the floor panel for the Audi 100. Laser welding in the assembly process was first brought into a production plant by BMW for the roof welding of its former touring model 3 series and Volvo for the roof welding of the 850 model. Since then, especially during the last three years, an increasing number of auto manufacturers have installed laser welding equipment within their production lines. Today laser welding applications in production plants are utilized all over the auto body, such as the front end, under body, closure panels and roof panel. Roof Roof • Audi • BMW • Ford • Audi • BMW • Ford • GM • Mercedes • Opel • GM • Mercedes • Opel • Renault • Volvo • Renault • Volvo • Volkswagen • Volkswagen B/C B/CPillars Pillars • Audi • Mercedes • Audi • Mercedes Decklid Decklid/ Tailgate / Tailgate • BMW • Daihatsu • BMW • Daihatsu • Honda • • Suzuki • HondaOpel • Opel • Suzuki • Volkswagen • Volkswagen Hood Hood • Opel • Volvo • Opel • Volvo Doors Doors • Honda • Porsche • Honda • Porsche Front Structures Front Structures • BMW • Mercedes • BMW • Mercedes Laser welding applications on production auto-bodies Fig. 9.2.1-1 Laser Welding in Assembly Chapter 9 - Page 2 Engineering Services, Inc. The major reasons for using laser welding is the predominantly high static and dynamic strength of the joints, one side weld access for the welding equipment, small thermic impact zone and good aesthetic look at the joint area. The total length of the laser welding seams for the assembly on the demonstration hardware is 18.28 meters. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Rail Front Outer to Rail Front Inner Rail Fender Support Inner to Rail Fender Support Outer Panel Body Side Outer to Panel A-Pillar Inner Lower Rail Fender Support Outer to Panel Body Side Outer Panel B-Pillar Inner to Rail Side Roof Bracket Member Pass Through Lower to Member Pass Through Panel Wheelhouse Inner to Rail Side Roof Panel Back to Rail Rear Inner and Rail Rear Outer Panel Dash to Rail Front Extension Panel Cowl Upper to Panel A-Pillar Inner Lower 13 14 15 16 17 (12) 18 19 (14) (3) 10 11 12 20 9 7 5 1 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 2 3 4 Panel B-Pillar Inner to Panel Rocker Inner Panel Roof to Panel Body Side Outer Rail Side Roof to Panel A-Pillar Inner Upper Panel Body Side Outer to Rail Side Roof Panel Package Tray Upper to Support Package Tray Support Panel Rear Header to Rail Side Roof Panel Roof to Rail Side Roof Member Pass Through to Brkt Member Pass Through Upr Frt & Rear Rail Rear Outer to Rail Rear Inner Panel Package Tray Upper to Panel Gutter Decklid Figure 9.2.1-2 Laser Welding on ULSAB Demonstration Hardware Chapter 9 - Page 3 6 8 Engineering Services, Inc. 9.2.2. Spot Welding Spot welding is for all OEMs a well-experienced, reliable, affordable joining technique for steel auto bodies, even with zinc-coated steel materials. Porsche, for example, has been producing cars since 1977 with 100% zinc coated steel sheet metal and was the first company in the world practicing this. Now, more and more OEMs are switching to 100% zinc coated materials to improve corrosion protection and to give a long time anti-corrosion guarantee. Also for ULSAB, 100% of the material is double side zinc coated. control unit power unit transformer current measurement voltage measurement Figure 9.2.2-1 Configuration of a Welding System Porsche’s R & D Center Body Assembly Facility utilizes computer controlled medium frequency (1000 Hz) welding equipment. This system uses calibration to ensure that the welding current is maintained at a constant level. Thereby providing a good weld without disturbances and achieving optimum settings for welding time, welding current and electrode force. Having established the optimum setting, the data is stored in the computer enabling the use of the ‘control mode’ to ensure all subsequent welding operations achieve the same optimum integrity. Chapter 9 - Page 4 Engineering Services, Inc. These control processes inevitably necessitate fast welding current sources. This requirement is fulfilled by medium frequency inverters with a response time of one millisecond at an inverter frequency of 1000 Hz and by the substantially faster transistor DC technology. weld current weld current AC welding operation (50 Hz) medium frequency inverter welding operation (1000 Hz) Comparison of the control response of thyristors and inverter controllers Figure 9.2.2-2 The system is sensitive to: • • • • • • • main voltage fluctuations shunts electrode wear (automatic stepper function) electrode force fluctuations small edge distances welding splashes changes from two sheet to multiple sheet welds Chapter 9 - Page 5 Engineering Services, Inc. The control process compensates the various influencing factors by increasing or reducing the current strength and extending the welding time. Extension of the welding time can be limited. Welding splashes are monitored via output of an error message, with optional shutdown of the welding current. Optimum adaptation to each weld spot guarantees that the required strength for weld joints is maintained throughout broad ranges. Figure 9.2.2-3 Medium Frequency Spot Welding Equipment Spot welding is used on ULSAB in all areas with suitable weld access and normal structural loads. The assembly of the demonstration hardware uses 2,126 spot welds. Chapter 9 - Page 6 Engineering Services, Inc. 9.2.3. Active Gas Metal Arc Welding (MAG) Active Gas Metal Arc Welding, or similar joining techniques, is used at all OEMs in locations with no weld access for spot welding or in areas with high stresses due to its strong structural behavior in comparison to spot welding. The disadvantages of this process, like slow welding speed, big heat impact zone, and pollution by weld fumes, especially with zinc coated materials, forced many OEMs to reduce it to a minimal amount. The targets for ULSAB were established to minimize the MAG welding seams. MAG welding is only used on the ULSAB body structure at locations without weld access for spot and laser welding. In total, there are 1.5 meters of MAG welding on the DH structure. 4 1 3 5 2 1. 2. 3. 4. 5. 6. 7. 6 7 Panel A-Piller Inner Lower to Panel Cowl Upper Door Hinges to Panel Body Side Outer Door Hinges to Panel B-Pillar Inner Door Hinges to Panel A-Pillar Inner Support Package Tray to Rail Side Roof Bracket Roof Rail Mount to Rail Side Roof Bracket Member Pass Through Lower to Rail Side Roof Figure 9.2.3-1 MAG Welding on ULSAB Demonstration Hardware Chapter 9 - Page 7 Engineering Services, Inc. 9.2.4. Adhesive Bonding The ULSAB steel sandwich material cannot resist the high temperatures during the painting process for body structures. Therefore this material is only suitable for parts which are assembled to the body after the painting procedure. Another factor is the non-weldability of the ULSAB sandwich material. So for the two parts on ULSAB made of steel sandwich adhesive bonding is the chosen joining technology. It has not only a structural function, it also provides sealing. The two panels made from steel sandwich material are the Panel Dash Insert (Part No. 022) and the Panel Spare Tire Tub (Part No. 050). Figure 9.2.4-1 Bonding at Panel Dash Insert Chapter 9 - Page 8 Engineering Services, Inc. In the production line, the panel dash insert will be assembled to the painted body structure as part of the instrument panel module. This includes the instrument panel, steering column, air conditioning system and pedal system. The panel dash insert is adhesive bonded and additionally bolted to dash panel. The bolting is necessary to keep the part in position until the bonding material is hardened. The panel spare tire tub will be assembled to the painted body structure as a module including the spare tire and the repair tools. The module is bonded to the structure. The operation does not require additional fixturing. The bonding material is a two component, non-conductive, high modulus, high viscous, chemically-curing polyurethane adhesive/sealant that cures almost independently of temperature and moisture. It is Betaseal X 2500 produced by Gurit Essex. Figure 9.2.4-2 Bonding at Panel Spare Tire Tub Chapter 9 - Page 9 Engineering Services, Inc. Technical Data Basis Polyurethane prepolymer Color black Solids content >98% (GM 042.0) Flash Point Processing temperature Working time >100° C ideal 10° C - 35° C approx. 10 min. at 23° C/50% r.h. (Processing time) Sagging behavior Ultimate tensile strength good, non-sagging > 5.5 MPa (DIN 53 504) Percentage elongation > 200% (DIN 53 504) Combined tension (GM 021) > 4.5 MPa and shear resistance G-Modulus Specific electrical > 2.5 MPa > 10 W cm (volume resistivity) Abrasion resistance Recovery (DIN 52 458) Extremely high approx. 99% Temperature stability - 40° C at 100° C (for short periods up to 140° C) Resistance to chemicals Highly resistant to aqueous chemicals, petrol (in cured conditions) alcohol and oils. Conditionally resistant to esters, aromatics and and chlorinated hydrocarbons. Preparation of bonding surface All bonding surfaces must be free of dirt, dust, water, oil and grease. In general, surfaces should be primed. Chapter 9 - Page 10 Engineering Services, Inc. 9.3. Flexible Modular Assembly Fixture System The body shop in Porsche’s R & D Center used a highly flexible modular fixture system for the DH assembly. It is based on standardized units, which are adjustable in all directions. Figure 9.3-1 Assembly Fixture Module There are many advantages of this fixture system. 95% of the elements in a fixture are from the standardized module system and can be used also for other car programs. Chapter 9 - Page 11 Engineering Services, Inc. Figure 9.3-2a Assembly Fixture Module Detail Figure 9.3-2b Assembly Fixture Module Detail Chapter 9 - Page 12 Engineering Services, Inc. The fixture design performed in CATIA was very efficient, because all models were accessible from the CAD data bank. Therefore, the construction time for assembly fixtures was reduced and modifications or corrections of existing assembly fixtures could be implemented rapidly. Figure 9.3-3 Assembly Fixture - Bodyside Inner Subassembly Chapter 9 - Page 13 Engineering Services, Inc. Porsche is using the flexible modular system in two ways. The first is the so-called shuttle system, which is related to the set-up pallets. The shuttles for different assemblies are stored in a shuttle magazine. During the assembly operation the shuttle is fixed on a set-up pallet. The changeover of various assembly shuttles on a set-up pallet is a very fast process. These assembly shuttles are mobile and can be used at different locations. Figure 9.3-4 Assembly Fixture Shuttle on Setup Pallet Chapter 9 - Page 14 Engineering Services, Inc. The second method is the utilization of a rolling device that supports the modular assembly fixtures independent from set-up pallets. These assembly fixtures work at any location. Figure 9.3-5 Mobile Assembly Fixture - Shock Tower Front SubAssembly RH/LH Chapter 9 - Page 15 Engineering Services, Inc. 9.4. Design of Assembly Fixtures All fixtures are developed with a CAD system (CATIA) based on the existing design data. The CAD data models of the fixture system modules are available from a data bank. Figure 9.4-1 Fixture Development on CAD System Figure 9.4-2 CAD Data Modules of Fixture System Chapter 9 - Page 16 Engineering Services, Inc. The DH assembly sequence is exactly the same as it is foreseen in the production plant. Due to the fact that in prototype productions no cycle time limit is given one fixture can be used for more joining operations than in a production line. This results in a drastically reduced number of assembly fixtures in relation to a production line. For the ULSAB assembly, the Porsche body shop used the following fixtures: • • • • • • Assembly Assembly Assembly Assembly Assembly Assembly Shock Tower Front Front End Floor Complete Under Body Complete Body Side Inner Body Complete An example of a fixture design is shown in Figure 9.4-3. Figure 9.4-3 Fixture Shock Tower Front Chapter 9 - Page 17 Engineering Services, Inc. 9.5. DH Build 9.5.1. Assembly Team The Porsche BIW assembly team consists of the following personnel: • • • 1 foreman 1 expert/deputy foreman 23 workers which include 5 with foreman’s / technician’s degree and 5 workers trained for CATIA Figure 9.5.1-1 Body Shop Chapter 9 - Page 18 Engineering Services, Inc. In a workshop space of 1200 m2, the following equipment is installed: • • • • • 12 setup pallets (6x3m) with surface measuring device 4 mobile welding machines, 1000 Hz with control equipment 5 mobile welding machines, 50 Hz with constant-voltage regulation system 5 overhead spot-welding devices with 3 secondary guns each and a 50 Hz Bosch control system 1 Rofin Sinar Laser device, 2.5 kW Two applications with special interest for ULSAB will be described in more detail. All spot welds on ULSAB were manufactured with a mobile Duering welding cart and a Matuschek medium-frequency inverter device with master control system. Figure 9.5.1-2 Chapter 9 - Page 19 Engineering Services, Inc. The welding gun changeover system allows a rapid change between different types of welding guns, whereby a special gun coding provides the correct weld parameters from an automatic program selection. Figure 9.5.1-3 Weld Gun Station Chapter 9 - Page 20 Engineering Services, Inc. The laser welding and laser cutting cabin is equipped with a KUKA KR 125 robot. The maximal load is 125 kg and the working range of 2410 mm. Figure 9.5.1-4 Laser Cabin Chapter 9 - Page 21 Engineering Services, Inc. The laser source is a Rofin Sinar CW 025 Nd:YAG Laser. The maximum output of 2500 W is transferred through a switching device with two outlets via two 15-m glass fibre cable of 0.6 mm diameter to the laser optic. Figure 9.5.1-5 Laser Besides a laser cutting head three different types of laser welding heads are available. Figure 9.5.1-6 Laser Picker Chapter 9 - Page 22 Engineering Services, Inc. Figure 9.5.1-7 Single Roller Figure 9.5.1-8 Double Roller Chapter 9 - Page 23 Engineering Services, Inc. 9.5.2. Build of the Test Unit The construction of the test unit, internally called “workhorse,” started on May 26, 1997, and began testing on June 27, 1997. The following series of photographs shows steps of the assembly sequence of the test unit. Due to the extensive preparations, the construction worked out excellent, but there was still room for small improvements. Figure 9.5.2-1 Rear Floor Subassembly Chapter 9 - Page 24 Engineering Services, Inc. Figure 9.5.2-2 Subassembly Front End Figure 9.5.2-3 Subassembly Underbody Complete Chapter 9 - Page 25 Engineering Services, Inc. Figure 9.5.2-4 Subassembly Body Side Inner Figure 9.5.2-5 Assembly Body Side Inner to Underbody Chapter 9 - Page 26 Engineering Services, Inc. Figure 9.5.2-6 Subassembly Body Side Inner with Underbody Figure 9.5.2-7 Sub-Assembly Body Side Outer, with Body Side Inner and Underbody Chapter 9 - Page 27 Engineering Services, Inc. 9.5.3. Build of DH #2 to DH #13 After build and testing of the test unit, a design review meeting in Porsche’s R & D Center was held with the experts in the fields of body design, safety, CAE calculations, parts manufacturing and body assembly. Ideas for improvements in respect to performance, parts feasibility, weld access and appearance were generated in this meeting. The next step was a redesign of the ULSAB body structure reflecting the ideas of the design review meeting. The CAE calculations of the changed FE model proved nearly the same performance. Now new parts were manufactured incorporating these changes in the construction of DH #2 to DH #13. Figure 9.5.3-1 Demonstration Hardware #2 in Body Shop The build of DH #2 started on December 1, 1997. The assembly sequence for DH #2 to DH #13 remained the same as test unit. Chapter 9 - Page 28 Engineering Services, Inc. 9.6. Quality 9.6.1. Body Quality Control Team The Porsche Body Quality Control Team includes the following personnel: • • • • 1 2 5 2 engineer technicians foremen specialist workers In a working area of 300 m2 the following equipment is used for body quality control measurement: • • • 1 Stiefelmeyer double-column coordinate measuring machine (CMM) 1 Stiefelmeyer single-column manual measuring machine 1 Zeiss double-column CMM Figure 9.6.1-1 DH #2 during Measuring Procedure Chapter 9 - Page 29 Engineering Services, Inc. The general range of services includes: • • • • • • Part acceptance at supplier’s premises Model acceptance at supplier’s premises Body measurement Digitalization of data for design Trouble-shooting Prototype quality statistics 9.6.2. Quality Control Measurements of DHs The basis for part and assembly quality was the early involvement of all relevant participants in the design and engineering process. Regularly simultaneous engineering meetings were established with designers, engineers, material suppliers, tool and part manufacturers and body shop personnel. The expert group defined locator holes, tooling holes and fixing points. To ensure excellent quality, these defined points were used for the complete process chain from parts manufacturing over subassemblies to final assembly. All manufactured parts were inspected by the supplier’s quality control personnel and approved by Porsche specialists. The first proof of feasibility and design for manufacture was the successful construction of the test unit. This demonstration hardware was fully inspected by Porsche’s quality control team. In total, about 200 different points on the ULSAB body structure were measured and compared to the original CAD data. The measured dimensions were, especially for a first time assembled body structure, in a close range to the nominal values. Chapter 9 - Page 30 Engineering Services, Inc. Figure 9.6.2-1 Measuring protocoll Nevertheless, the results of the test unit were used to develop modifications of the tools for part manufacturing and of the assembly fixtures for improved quality, meaning smaller tolerances for the following DHs. Each DH is or will be inspected to evaluate a quality statistic for the ULSAB program. Chapter 9 - Page 31 Engineering Services, Inc. 9.7. Conclusion The assembled demonstration hardware proved to be a successful execution of the body structure construction. The measured tolerances are in a comparable range in relation to average car programs. The challenges of laser welding in assembly, assembly of hydroformed parts, 90% high strength steel, and steel sandwich material, were mastered. The principle condition for success was the simultaneous engineering process. All project partners contributed to the realization of Phase 2 of the ULSAB program. Through early involvement in the project, all parties involved incorporated all of their expertise into the realization of the demonstration hardware. Figure 9.7-1 Chapter 9 - Page 32 Engineering Services, Inc. 10. Testing and Results Engineering Services, Inc. 10. Testing and Results 10.1. Scope of Work To prove the structural integrity of the ULSAB demonstration hardware, the following test procedures were executed as part of the ULSAB program in Phase 2. • Static rigidity • Static torsion • Static bending • Modal analysis • 1st Torsion mode • 1st Bending mode • 1st Front end lateral mode • Mass • DH mass in test configuration All testing work was performed at Porsche’s R & D Center in Weissach. Fig 10.1-1 Aerial View Chapter 10 - Page 1 Engineering Services, Inc. 10.2. Targets The main factors affecting the ride and handling of the vehicle are Noise, Vibration and Harshness, known as NVH behavior. To achieve the desired levels of comfort for the occupants, the vehicle body must have high static and dynamic rigidity. In other words, the auto body should have high stiffness. This is required because the increased rigidity improves the vehicle resistance to excitement caused by the drive train, the engine or by road conditions such as bumps and potholes. When excited, the car body vibrates at particular frequencies, called its natural frequencies, and also in a particular manner called its mode shape. The mode shapes are for instance on: global torsion mode, global bending mode and front end lateral mode. Another result of good rigidity would be minimal deviations in the dimensions of the body structure openings such as the hood, front door, rear door and deck lid under load conditions. These movements between the body structure and the closure panels often create sounds. Furthermore, it should be proven that the received numbers from the analysis by FE-calculations are in correlation with the results gathered by the testing procedure. Based on the current average of selected, benchmarked vehicles in Phase 1, the following targets for the ULSAB structure were established: Performance Mass Static torsional rigidity Static bending rigidity First body structure mode Targets [ 200 kg m 13,000 Nm/deg m12,200 N/mm m 40 Hz NOTE: Structural performance with windshield and backlight; mass without windshield and backlight. Chapter 10 - Page 2 Engineering Services, Inc. 10.3. Static Rigidity 10.3.1. Test Setup 10.3.1.1. General The DH in full test configuration consists of the following parts: • • • • • • • • • • Welded Body Structure Bonded Windshield and Back Light Bonded and bolted Panel Dash Insert (Part-No. 022) Bonded Panel Spare Tire Tub (Part-No. 050) Bolted Reinforcement Panel Dash Brake Booster (Part-No. 115) Bolted Braces Radiator (Part-No. 188) Bolted Reinforcement Radiator Rail Closeout RH/LH (Part -No. 094/095) Bolted Reinforcement Radiator Support Upper (Part-No. 001) Bolted Tunnel Bridge Lower/Upper Bolted Brace Cowl to Shock Tower Assembly Figure 10.3.1.1-1 DH with Bonded / Bolted Parts Chapter 10 - Page 3 Engineering Services, Inc. The unpainted body structure was measured without front and rear suspension system. The body structure was held at four points: the front; at Panel Skirt RH/LH (Part-No. 096/097) and the rear; at Plate Rear Spring Upper (Part-No. 110). Along the front rails, the rockers, and the rear rails 12 stadia rods were attached. Twenty-four electronic feelers measured the movements of these rods. Aluminum panels with glass thickness were used to simulate the bonded windshield and backlight. Due to the fact that the related material property for rigidity and stiffness, the Youngs modulus, shows a close similarity for glass and aluminum. This can be done without compromising the test results, but taking advantages in timing and cost. 10.3.1.2. Static Torsion The DH was mounted to the test rig with rigid tubes. Two rear locations at the plate spring rear upper were constrained, while the load was applied to panel skirt RH/LH by a scale beam. Figure 10.3.1.2-1 Test Configuration for Static Torsion Chapter 10 - Page 4 Engineering Services, Inc. The measurements were taken with four different loads from M =1000Nm to t M max=4000Nm. t Before starting the measuring procedure, the maximum load was applied to the DH to eliminate the sag rate. 10.3.1.3. Static Bending The DH was mounted to the test rig by rigid tubes. The four fixing points of the DH were constrained. The loads were applied to the center of the front seats and to the center of the two outer rear seats. Figure 10.3.1.3-1 Test Configuration for Static Bending The measurements were taken with four different loads from F = 1000 N b (4 x 250 N) to F max = 4000 N (4 x 1000 N). b Before starting the measuring procedure, the maximum load was applied to the DH to eliminate the sag rate. Chapter 10 - Page 5 Engineering Services, Inc. 10.3.2. Results 10.3.2.1. Static Torsion Figure 10.3.2.1-1 DH on Test Rig for Static Torsion The torsional rigidity for the test unit in the configuration described in section 10.3.1.1 is: With glass Without glass Chapter 10 - Page 6 21,620 Nm/deg 15,790 Nm/deg Engineering Services, Inc. Test Unit Displacement Torsion 20 Rear Axle Front Axle Angle of Twist [min] 15 4000 Nm 3000 Nm 2000 Nm 1000 Nm 10 5 0 -5 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 Longitudinal Axis X [mm] Figure 10.3.2.1-2 Torsion Lines 4 Load Cases with Glass In general, the graph plot is running harmonic. There is only a jump in rigidity between x = 3800 to x = 4200. This is related to the positive impact of the Member Pass Through (Part-No. 090) to the torsional stiffness. Test Unit Gradient Torsion 0.4 Gradient [°/m Rear Axle Front Axle 0.3 0.2 0.1 0 -0.1 -0.2 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 Longitudinal Axis X [mm] Figure 10.3.2.1-3 Gradient of Torsion Line with Glass The above graph shows the gradient of the torsion line. The disharmonies of the torsion line can be seen in a higher resolution. Chapter 10 - Page 7 Engineering Services, Inc. The torsional rigidity for DH #2 in the configuration described in section 10.3.1.1 is: With glass Without glass 20,800 Nm/deg 15,830 Nm/deg DH #2 Displacement Torsion 20 Rear Axle Front Axle 4000 Nm 3000 Nm 2000 Nm 1000 Nm Angle of Twist [min] 15 10 5 0 -5 500 1000 1500 2000 2500 3000 3500 4000 4500 Longitudinal Axis X [mm] Figure 10.3.2.1-4 Torsion Lines 4 Load Cases with Glass As expected, the results are very close to the test unit. This assumption is based on the test results without glass, because these are nearly identical (15,790 Nm/deg vs. 15,830 Nm/deg). Chapter 10 - Page 8 5000 Engineering Services, Inc. DH #2 Gradient Torsion 0.4 Rear Axle Front Axle 0.3 Gradient [°/m] 0.2 0.1 0 -0.1 -0.2 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 Longitudinal Axis X [mm] Figure 10.3.2.1-5 Gradient of Torsion Line with Glass The above graph shows the gradient of the torsion line. The disharmonies of the torsion line can be seen in a higher resolution. Chapter 10 - Page 9 Engineering Services, Inc. To investigate the impact of several bonded and/or bolted parts, additional measurements in various test configurations were undertaken with the test unit. Test Configurations: 1. 2. 3. 4. 5. Full configuration as described in Section 10.3.1.1 As 1, but without braces radiator (Part-No. 188) As 2, but without radiator support upper (Part-No. 001/094/095) As 3, but without bolted brace cowl to shock tower assembly As 4, but without tunnel bridge Torsion Rigidity Torsion Rigidity [%] 110 100 100.0 98.3 98.3 90 92.0 92.0 4 5 80 1 2 3 Test Configuration Figure 10.3.2.1-6 Torsion Rigidity Five Test Configurations As the numbers show, only the bolted brace cowl to shock tower assembly has a significant impact on the torsional rigidity of 6.3%. Chapter 10 - Page 10 Engineering Services, Inc. 10.3.2.2. Static Bending Figure 10.3.2.2-1 DH on Test Rig for Static Bending The bending rigidity of the test unit in the configuration described in Section 10.3.1.1 is: With glass Without glass 20,460 N/mm 17,150 N/mm Chapter 10 - Page 11 Engineering Services, Inc. Test Unit Displacement Bending 0.5 Rear Axle Front Axle 0.4 Vertical Displacement [mm] 0.3 0.2 0.1 0 -0.1 -0.2 4000 N 3000 N 2000 N 1000 N -0.3 -0.4 -0.5 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 Longitudinal Axis X [mm] Figure 10.3.2.2-2 Bending Lines 4 Load Cases with Glass The graph is running harmonic. There is only a local increase in bending rigidity between x = 3500 and x = 4200. This indicates a stiff joint between rocker and rear rails. Furthermore, Porsche relates this to the design of the side roof rail. Test Unit Average Deviation Bending Deviation from the average [%] 50 Front Axle 40 Rear Axle 30 20 10 0 -10 -20 -30 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 Longitudinal Axis X [mm] Figure 10.3.2.2-3 Deviation from the Average Bending Line with Glass The above graph shows the deviation from the average value of the bending line. The disharmonies can be seen in a better resolution. Chapter 10 - Page 12 Engineering Services, Inc. The bending rigidity for DH #2 in the configuration described in Section 10.3.1.1 is: With glass Without glass 18,100 N/mm 15,950 N/mm DH #2 Displacement Bending 0.5 Rear Axle Front Axle Vertical Displacement [mm] 0.4 0.3 0.2 0.1 0 -0.1 -0.2 4000 N 3000 N 2000 N 1000 N -0.3 -0.4 -0.5 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 Longitudinal Axis X [mm] Figure 10.3.2.2-4 Bending Lines 4 Load Cases with Glass The bending lines show the same characteristics as for the test unit, but the absolute value decreased by 11%. The local increase between x=3500 and x=4200 is not so evident as it was on the test unit. This could be created by local modifications of the side roof rail and the rear rails for improved manufacturing. Furthermore, the material gage of the panel roof changed from 0.77mm to 0.70mm due to material availability problems for the test unit; this was also a factor for the decrease of the absolute value. Additionally Porsche has experienced that static rigidities of body structures differ by plus/minus five percent (5%) even under series production conditions. Chapter 10 - Page 13 Engineering Services, Inc. DH #2 Average Deviation Bending 50 Deviation from the average [%] 40 Front Axle Rear Axle 30 20 10 0 -10 -20 -30 -40 -50 500 1000 1500 2000 2500 3000 3500 4000 4500 Longitudinal Axis X [mm] Figure 10.3.2.2-5 Deviation from the Average Bending Line with Glass The above graph shows the deviation from the average value of the bending line. The disharmonies can be seen in a better resolution. Chapter 10 - Page 14 5000 Engineering Services, Inc. To investigate the impact of several bonded and/or bolted parts, additional measurements were undertaken: Test Configurations: 1. 2. 3. 4. 5. Full configuration as described in Chapter 10.3.1.1 As 1, but without braces radiator (Part-No. 188) As 2, but without radiator support upper (Part-No. 001/094/095) As 3, but without bolted brace cowl to shock tower assembly As 4, but without tunnel bridge Bending Rigidity [%] Bending Rigidity 110 100 100.0 100.0 99.0 98.8 1 2 3 4 100.0 90 80 5 Test Configuration Figure 10.3.2.2-6 Bending Rigidity Five Test Configurations As the numbers show, none of these parts display a significant impact on bending rigidity. The increase from test configuration four (4) to test configuration five (5) is caused by local effects of the tunnel bridge to the displacement of the rocker. This behavior was also noticed in other body structures. Chapter 10 - Page 15 Engineering Services, Inc. 10.4. Modal Analysis 10.4.1. Test Setup A modal analysis describes the vibration behavior of a structure. Results of a modal analysis are the resonance frequencies of the specific structure and the corresponding mode shapes (how the structure vibrates). The ULSAB structure was suspended on a test rack held by rubber straps to decouple the test unit from the supporting structure of the test rack. In order to find the mode shapes and the resonance frequencies, energy is applied to the structure. The response of the structure (in general the acceleration at different points) is measured in relation to the input forces. From the contribution of each input force to each response value, the dynamic behavior of the structure is calculated. Figure 10.4.1-1 Test Configuration for Modal Analysis In the case of the ULSAB, the body structure is excited by means of four electrodynamic shakers that are coupled to the corner points of the structure. Chapter 10 - Page 16 Engineering Services, Inc. The simultaneous excitation with four shakers is necessary to provide good energy distribution into the structure and to minimize the influence of possible nonlinearities to the quality on the results. In addition, the torsion and bending modes of the body can be excited definitely. Torsion and bending are the most important global modes of a body structure. Each of the four shakers is driven by a computer-generated, statistical independent band limited (0 to 100 Hz) Gaussian random noise spectrum. The response of the structure is determined by measuring vibration transfer functions between the acceleration at each measurement point in three orthogonal directions and each driving force. Accelerometer HP 9000/700 LMS CADA-X DAC Interface ADC Interface Memory Electrodynamic Shakers Power Amplifier Charge Amplifier Aliasing Filter and Amplifier Figure 10.4.1-2 Set-Up for Modal Analysis The global parameters of the structure, frequency and damping are determined thereafter by a Least Squares Complex Exponential (LSCE) fitting. Chapter 10 - Page 17 Engineering Services, Inc. The modal displacement is calculated subsequently by fitting a Multiple Degree of Freedom (MDOF) model to the transfer functions in the time domain. The test configuration of the test unit was exactly the same as the testing of static rigidities described in section 10.3.1.1. 10.4.2. Results Figure 10.4.2-1 DH on Test Rig for Modal Analysis Chapter 10 - Page 18 Engineering Services, Inc. The global modes of the test unit in the described test configuration can be seen in the following chart: Test Unit Modal Analysis First Modes [Hz] 70 60 60.6 60.8 62.4 64.3 60.6 50 49.1 40 Torsion Bending without glass Front End Lateral with glass Figure 10.4.2-2 Modal Analysis Results - Test Unit The dynamic rigidity of the ULSAB structure is remarkably good, as it was already indicated by the static test results. Windshield and backlight have a significant impact on the first torsion mode. The difference is in the same range, as known from other sedan body structures. The effect on first bending and first front-end lateral mode is relatively small. For the test configuration with glass, the first torsion mode and the first front-end lateral mode are coupled at 60.6 Hz. Chapter 10 - Page 19 Engineering Services, Inc. Frequency Response Function Amplitude [(m/s2)/N] Test Unit Modal Analysis with Screens 2 First Bending 62.4 Hz First Torsion 60.6 Hz 1.8 Bending 63.5 Hz Corner Points Front Left 1.6 Front Right 1.4 Rear Left 1.2 Rear Right 1 0.8 0.6 0.4 0.2 0 50 52 54 56 Test Unit Modal Analysis with Screens Frequency Response Functions, measured at the body corner points Power input by means of electrodynamic shakers at the body corner points 58 60 62 64 66 68 Frequency [Hz] Figure 10.4.2-3 Frequency Response Functions - Test Unit The graph plot above shows the frequency response functions, measured at the four driving points. Second bending mode at 63.5 Hz occurs mainly in the rear; whereas the first bending mode occurs in the front and rear of the structure. Chapter 10 - Page 20 70 Engineering Services, Inc. The global modes for DH #2 in the described test configuration can be seen in the following chart: D H # 2 M o da l A na lys is First Modes [Hz] 70 66.5 63.9 60 64.9 60.1 57.2 50 47 40 Torsion Bending w ithout glass Front End Lateral w ith glass Figure 10.4.2-4 Modal Analysis Results - DH #2 The dynamic rigidity of DH #2 is in the same range as the values of the test unit. The front-end lateral mode changed remarkably. This is created by the change of the material gauge of the rail fender support inner from 0.9mm to 1.2mm. The torsion mode and bending mode without glass decreased slightly, but with glass, the loss of dynamic rigidity is compensated. Chapter 10 - Page 21 Engineering Services, Inc. Frequency Response Function Amplitude [(m/s2)/N] 4 Measurement Points: First Bending 63.9 Hz 3.8 Body Corner Points 3.6 3.4 Driving Points: 3.2 Body Corner Points 3 2.8 Front Left 2.6 Front Right 2.4 First Torsion 60.1 Hz Rear Left 2.2 Rear Right 2 1.8 1.6 1.4 1.2 Project: 1 0.8 Test: 0.6 Date: 0.4 Vehicle: 0.2 0 50 52 54 56 58 60 62 64 Frequency 66 ulsabdh2 ULSAB_DH2_mS 18-12-97 ULSAB DH2 Body Structure with Screens 70 68 Hz DH #2 Modal Analysis with Screens Frequency Response Functions, measured at the body corner points Power input by means of electrodynamic shakers at the body center points Figure 10.4.2-5 Frequency Response Functions - DH #2 The graph plot above shows the frequency response function, measured at the four driving points. The amplitude of the first bending increased in relation to the test unit. This is in correlation with the decrease of the static bending rigidity. Additional modal analysis was conducted on the ULSAB structure, to investigate the influence of several bolted and/or bonded parts. Test configurations: 1. 2. 3. 4. 5. Full test configuration as described in chapter 10.3.1.1. As 1, but without bolted brace cowl to shock tower assembly As 2, but without braces radiator (Part-No.188) As 3, but without tunnel bridge As 4, but without radiator support upper (Part-No. 001/094/095) Chapter 10 - Page 22 Engineering Services, Inc. Modal Analysis 70 62.4 First Modes [Hz] 60.6 60 62.4 61.0 62.4 61.0 62.3 62.3 60.8 60.3 60.6 53.4 50 47.0 47.3 47.2 2 3 4 40 1 5 Test Configuration Front End Lateral Torsion Bending Figure 10.4.2-6 Modal Analysis Five Test Configurations The influence of the bolted brace cowl to shock tower assembly on the front-end lateral mode of 13.6 Hz is evident. Test configuration 5 shows an improvement in the front-end lateral mode, but this is mainly caused by the influence of the mass of assembly radiator support. The other modifications have no evident impact on dynamic rigidity. Chapter 10 - Page 23 Engineering Services, Inc. 10.5. Masses in Test Configuration A crane with a scaled load cell balanced the DH. Figure 10.5-1 DH #2 on Crane The measured mass in full test configuration included the mass of the bolted brace cowl to shock tower assembly and tunnel bridge, which were installed for testing only (see 10.3.1.1 Test Configurations). The mass of Windshield and backlight were not included. The mass in this test configuration was the following: Test Unit DH #2 197.3 kg 198.5 kg *This mass includes 2.86 kg for the bolted brace cowl to shock tower assembly and tunnel bridge The calculated mass for non-constructed reinforcements and brackets has to be added (see Chapter 5 on Design and Engineering). Chapter 10 - Page 24 Engineering Services, Inc. 10.6. Summary All test results proved excellent performance and coordination between test results and CAE results for structural performance values. This is caused by the fact that the approach from former times, to define the structural body parts by these requirements, is superseded. Nowadays, these body parts are mainly specified by safety requirements. ULSAB Testing Results Overview vs. CAE Results Testing Test Testing CAE Final Test Benchmark DH #2 Unit Version Unit Average Targets Static Rigidity Torsion (Nm/deg) 20,800 21,620 20,350 19,020 11,531 ≥ 13,000 Bending (N/mm) 18,100 20,460 20,540 20,410 11,902 ≥ 12,200 Modal Analysis Torsion (Hz) 60.1 60.6 61.4 61.1 38* ≥ 40 Bending (Hz) 63.9 62.4 61.8 64.1 38* ≥ 40 Front End Lateral (Hz) 64.9 60.6 60.3 58.5 38* ≥ 40 *1st mode shape varied for each vehicle benchmarked The results gained by CAE calculations are in good, if not excellent, correlation with the test results. Chapter 10 - Page 25 Engineering Services, Inc. 11. Economic Analysis Engineering Services, Inc. 11. Economic Analysis 11.1. Introduction The objective of this program was to establish a credible cost estimation of the ULSAB body structure by using automotive practices of manufacturing engineering, process engineering and cost estimating. To undertake this program, Porsche Engineering Services, Inc. (PES) organized an interactive process between product designers, stamping process engineers, assembly line designers and cost analysts. The team was comprised of the following organizations: Porsche Engineering Services .... Program Management Knight Engineering .... Stamping Process Engineering Schaefer GmbH .... Hydroform Process Engineering Classic Design .... Assembly Process Design Porsche AG .... Process Validation Camanoe Assoc. / IBIS Assoc .... Cost Analysis Because end users would want to analyze “what if” scenarios and compare existing or potential body structures to ULSAB, the entire program used a technical cost model program developed by Camanoe Associates (a group of MIT researchers) and IBIS Associates. The technical cost model is programmed to allow the user to change any of the general inputs to suit their specific environment or to change specific inputs for alternative processes. In addition, because the costs shown on the ULSAB cost model reflect only factory costs and are relative to the level of product development as of today, a user may wish to enter additional cost categories for both ULSAB and a comparative body structure. The cost model has been arranged to accommodate this. Chapter 11 - Page 1 Engineering Services, Inc. Some of the areas not included in the ULSAB Cost Analysis are: • • • • • • • • SQA (Supplier Quality Assurance), quality testing, auditing Impact on body structure through other system developments, i.e., electrical, trim, powertrain, etc. Changes as a result of physical body structure testing Start up and production launch costs Marketing campaigns Transportation costs Departmental costs, marketing, finance, purchasing, human resources, etc. Preparation for paint 11.2. The Process of Cost Estimation 11.2.1. Overview The Economic Analysis of ULSAB began with the establishment of the basic assumptions regarding general inputs. This was achieved through a series of meetings between the Economic Analysis Committee of ULSAB and the Economic Analysis Team. The program then commenced to establish the estimated production costs against an extremely well defined design. Having a process design meant that costs could be analyzed based on exact definitions concerning fabrication and assembly requirements. On the parts fabrication side, each stamping and hydroformed component was studied to determine the process. This step was undertaken by Knight (Stampings) and Schaefer (Hydroforming) who provided the initial inputs on operation requirements, equipment requirements, tooling costs, manpower requirements, etc. On all major components Porsche, Germany confirmed the data. Chapter 11 - Page 2 Engineering Services, Inc. Complete Porsche Design General Inputs - ULSAB Economic Analysis Committee Part Definitions (mass, area, etc........) Assembly Requirements (number and type of welds) Consensus among: - Camanoe / IBIS - Knight Engineering - Porsche Engineering - Porsche AG Fabrication Process Parameters (line run rate, tool cost, press cost, number of hits) Assembly Line designed explicitly for ULSAB by Classic Engineering Assembly Process Parameters (total equipment cost, number of workers, etc.......) Cost Model Cost Model Algorithm by Camanoe / IBIS Figure 11.2.1-1 Mechanism for Determination of All Part Inputs This data was then compared to the mass industry data bank at the Massachusetts Institute of Technology (MIT) to ensure reasonableness before being used for cost estimating. For the assembly line design and processing, PES provided Classic Design with a detailed bill of materials (BOM) and parts sequencing. From this, each area and station was developed in a macro view, which established the equipment, tooling, building and manpower required to fulfill the production requirements. Following validation by Porsche, Germany this data was then forwarded to Camanoe for final cost estimation. Chapter 11 - Page 3 Engineering Services, Inc. 11.2.2. Cost Model Algorithm Development In this section the methodology for development of the technical cost models is described. The cost models can be used not only for determining manufacturing costs for the ULSAB design, but also for costs associated with alternative designs. The models allow the capability to track the major cost contributors and to determine opportunities for target areas for reduction. The principal objective for this project includes development of a cost estimation tool to aid automotive designers specifically interested in costs associated with the ULSAB design. The cost model permits any user to easily adapt various input parameters, allowing cost investigations for alternative designs on a consistent basis. The cost model must account for various processes used in the manufacture of the body structure, including stamping, hydroforming and assembly. Based on numerous input parameters, both economic and technical, the model tracks cost contributions to the stamping process from blanking, welding (for tailor welded blanks) and stamping for all parts. Similarly, hydroformed part costs are broken down into contributions from bending, pre-forming and the final hydroforming fabrication. The assembly process costs include cost contributions from spot welding, active gas metal arc welding (MAG), laser welding and adhesive bonding. Technical cost modeling is a technique developed and used by Camanoe and IBIS for simulating manufacturing costs. The technique is an extension of conventional process modeling, with particular emphasis on capturing the cost implications of material and process variables and various economic scenarios. The focus of the technical cost models developed for ULSAB are limited to direct manufacturing cost, although the models could be expanded to include indirect costs and aspects of the entire product life-cycle. Direct manufacturing costs involve specific processes: fabrication and assembly of the body structure. Indirect manufacturing costs, including executive salaries, marketing and sales, shipping and purchasing, research and development, and profits are not considered. Chapter 11 - Page 4 Engineering Services, Inc. Cost is assigned to each unit operation from a process flow diagram. For each of these unit operations, total cost is broken down into separately calculated individual elements. • • Variable cost elements: Fixed cost elements: Materials, labor, and energy Equipment, tooling, building, maintenance, overhead labor and cost of capital Developed to breakdown and track contributions from variable and fixed costs, the models identify the major cost contributors to manufacturing. After the direct manufacturing costs are established based on an initial set of input parameters, sensitivity analysis can be performed to indicate the cost impact of changes to key parameters. Technical cost models provide an understanding not only of current costs, but also of how these costs might differ in the face of future technological or economic developments. Typical parameters investigated via sensitivity analyses include: annual production volume, throughput (cycle time or production rate), raw material prices and tooling costs. Models can be implemented in either a descriptive or predictive manner. In either case, direct inputs are specified for the product material, geometry and manufacturing scenario. With descriptive models, the user directly inputs the intermediate parameters such as production rate, equipment cost and tooling cost. In the predictive approach, the model as a function of the product material and geometry calculates the intermediate parameters. These predictive functions are derived from analyzing a continually expanding range of case studies, and are updated routinely. It is this predictive nature of technical cost models that separates them from other cost estimating tools. Chapter 11 - Page 5 Engineering Services, Inc. 11.2.3. General Inputs As stated previously, the Economic Analysis began with the establishment of the general inputs. An example of these inputs is as follows: Input Production Volume 60 jobs per hour Working Days per Year 240 Production Location Mid-West USA Wage including Benefits $44.00 per hour Interest Rate 12% Equipment Life 20 years Production Life 5 years Building Life 25 years 11.2.4. Fabrication Input For each part in the ULSAB design, a press line time requirement was calculated. The machine clean running rate, the line downtimes, the part reject rates and the total annual production volume are used to determine the total time needed on the line for the given year. This information, combined with the technical requirements for stamping each part is used to calculate the total number of each press line type needed to produce the ULSAB body structure. For ULSAB, it was determined that a total of 15 press lines and five blanking lines were needed to produce all the necessary parts and blanks. Chapter 11 - Page 6 Engineering Services, Inc. 1 4500 tons 2 3600 tons 3 4 5 6 7 8 9 10 11 A B C C C D D D D A B C C C D D D D A B C C C D D D D A B C C C E 12 E 13 E 14 E 15 A B3 400 t 400 t B4 B5 1000 t B2 600 t B1 400 t A Figure 11.2.4-1 ULSAB Press Shop Layout The accompanying press shop layout shows the distribution of these 15 press lines and five blanking lines among the various equipment types shown in the previous slide. The layout also shows the number of presses required on each line. For example, there is only one line using “Press Group A” and it contains six presses; there is one line using “Press Group B” containing four presses; three lines using “Press Group C” containing four presses each; and four lines using “Press Group D” containing three presses each. In addition, one of each large transfer press types and four smaller transfer presses suitable for the progressive die parts were also used. Finally, one large, one medium and three small blanking lines were required. Chapter 11 - Page 7 Engineering Services, Inc. The press line descriptions are as follows: Press Capacity Size Press Group A: 1600 ton DA/1000 ton SA 4572 mm x 3048 mm Press Group B: 1000 ton DA/800 ton SA 3048 mm x 2032 mm Press Group C: 800 ton DA/500 ton SA 2743 mm x 1524 mm Press Group D: 500 ton DA/350 ton SA 2438 mm x 1220 mm Press Group E: 350 ton SA 2134 mm x 1220 mm (Progressive Dies) Transfer Presses: 4500 ton & 3600 ton Blanking Lines: 400 ton 2438 mm x 1220 mm 600 ton 2743 mm x 1524 mm 1000 ton 3048 mm x 2032 mm DA = Double Action SA = Single Action 11.2.5. Assembly Input The assembly line was designed explicitly for ULSAB by Classic Engineering which includes equipment and tooling investment, assembly plant area and labor force. Cost enhancements concerning material, energy, overhead labor and maintenance were performed by Camanoe and IBIS. It is very important to remember that the assembly line was designed for a net line rate of 60 jobs per hour. Because of the various line downtimes, this requires a running rate of 72 body structures per hour, which in turn implies that there are only 48 seconds per station to perform assembly operations and transport the body to the next station. In practice, increasing (or decreasing) the line running rate changes the time available at each station to perform the assembly operations and thus changes the line configuration, resulting in different levels of required investment. Because the line was actually designed for one line speed (net rate of 60 body structures per hour), the model is unable to adjust the investment based on the different line rates. Consequently, the user MUST change the assembly investment inputs in order to have an accurate estimate of the assembly cost at other production volumes. Additionally, ULSAB is costed against specific spot welds and laser welds, any alteration to this situation would require a re-evaluation of the equipment and manpower needed. Chapter 11 - Page 8 Engineering Services, Inc. 11.3. Cost Model Description The following chapter describes the salient information and input parameters within the ULSAB Technical Cost Model. With the enormous quantity of input parameters required for cost calculations, validation and consensus among all participants are critical for appropriate ULSAB cost determination. A description of the process for generating consensus on all of the input parameters for the ULSAB design is discussed. Information Machine Rents Calculations Part Inputs General Inputs Investments Cost Breakdown Cost Summary Overall Costs Figure 11.3-1 Technical Cost Model Layout The ULSAB technical cost model consists of the following nine major sections or sheets, in order of appearance: Overall Costs, Cost Summary, Cost Breakdown, Investments, General Inputs, Part Inputs, Calculations, Machine Rents and Information. Chapter 11 - Page 9 Engineering Services, Inc. The Overall Costs sheet, appearing first, reports the total cost for body structure fabrication. This sheet provides the user with a brief synopsis of the model outputs, which include cost contributors for stamping and assembly of a body structure. As mentioned in the introduction, the user will be able to input additional costs as required. The second sheet, Cost Summary, provides more detail by listing cost contributors for each part ID number or assembly area. The next sheet, Cost Breakdown, gives further detail on the contributors to part cost. Cost contributors for each part ID are broken down by process step, and the information in this sheet is organized slightly differently than in the Cost Summary sheet. No information on assembly is contained on the Cost Breakdown sheet, only costs related to part production. The 2 input sheets (General Inputs and Parts Inputs) contain all of the pertinent input parameters for cost calculation. The Calculations sheet lists intermediate cost output calculations that may be of interest. The model includes a sheet that can be used to test the effect of various sets of input parameters on the machine rents. Finally, the Information sheet gives information concerning the size and the gages of the blank sizes to be used for ULSAB. Organizational Format of Model Sheets Stamped Parts: General Output Costs Process Specific Information Tubular and Purchased Parts: General Output Costs Cost Breakdown by Element Assembly: General Output Costs Cost Breakdown by Element Figure 11.3-2 Organizational Format of Model Sheets Chapter 11 - Page 10 Engineering Services, Inc. Most of the eight sheets are organized in a similar manner, as shown schematically in the figure above. This organization is consistent for cost sheets and calculation sheets. By paging down each sheet, three sections become apparent: Stamped Parts, Tubular and Purchased Parts and Assembly. By paging across the sheet within each of these sections, the costs for specific parts or assembly processes (listed by ID) are identified, and sorted into two categories: General Output Costs and Cost Breakdown by Element. Within the General Output Costs regions, the total cost for fabricating parts is listed for each part, identified by part ID and name. Hence part cost information for each stamped, tubular and purchased part is readily available. The total cost for fabrication is summed at the bottom of each column and section. Paging across to the Cost Breakdown by Element region, the total cost for each part is broken down into nine cost categories, including material, energy, labor, equipment, tooling, overhead labor, building, maintenance and working capital costs. Addition of all cost elements in a given row sums to the total part cost. Each of the nine cost elements is also totaled at the bottom of each column for all parts to provide a total cost breakout by element in the Stamping, Tubular and Purchased Parts and Assembly sections. 11.4. ULSAB Cost Results 11.4.1. Overall Cost Results The cost analysis for the ULSAB design is presented, including a breakdown of costs by processes, factor elements, and investments. The costs associated with new technologies are focused upon, specifically for all the tailor welded blank stamped parts and for the hydroformed side roof rail. Sensitivity analyses are included for changes in input parameters, which may affect the cost of TWB processing. The manufacturing costs for the ULSAB body structure at 203.2 kg with 158 parts result in an overall value of $947 per body structure. Chapter 11 - Page 11 Engineering Services, Inc. The body structure cost can be broken down into $666, from parts fabrication and $281 from assembly. Of the 158 parts in the ULSAB design, the 94 major stamped parts make up the majority of the mass (184 kg) and represent the largest cost element at $584. Tubular parts, such as the two hydroformed side roof rails and the member pass through beams, as well as a large number of small brackets and hinges (normally out-sourced by the auto maker), make up only a small portion of both the overall mass and cost. Cost Stamped Parts Tubular & Purchased Parts Assembly Total Body Structure $584 $82 $281 $947 Number Mass of of Parts Parts (kg) 94 64 --158 184.3 18.9 --203.2 Figure 11.4.1-1 ULSAB Overall Cost Results The breakdown of the variable costs (and the remaining fixed cost total), both for parts fabrication and assembly, shows the importance of the material and fixed costs. Material (steel) is the single largest cost driver, accounting for 37% of the total body structure cost. Total fixed costs (for parts fabrication and assembly operations), which primarily derive from the investments in plant equipment and overhead, also lead to 44% of the body structure cost. The labor and energy contributions are relatively small at a combined total of only 10% for the entire assembled body structure. Chapter 11 - Page 12 Engineering Services, Inc. ULSAB % of Total Stamping Hydroforming Purchased Assembly $584 $41 $41 $281 62% 4% 4% 30% Total Body Structure Cost $947 100% Total Number of Parts Total Mass 158 203.2 kg Figure 11.4.1-2 Cost Breakdown by Process Step ULSAB % of Total $353 36 6 189 $584 37% 4% 1% 20% 62% Assembly $41 $41 $0 45 10 226 $281 4% 4% 0% 5% 1% 24% 30% Total Body Structure Cost $947 100% Material Labor Energy Fixed Costs Stamping Parts Fabrication Hydroforming Purchased Material Labor Energy Fixed Costs Figure 11.4.1-3 Cost Breakdown by Factor Chapter 11 - Page 13 Engineering Services, Inc. Investments ULSAB (Millions) % of Total Blanking Tooling $4.4 1.4% $10.1 3.2% $1.2 0.4% $37.2 11.9% Welding Building $5.9 1.9% Stamping Tooling $37.1 11.8% Stamping Lines $102.9 32.8% Stamping Building $6.1 1.9% Hydroform Tooling $1.3 0.4% $16.3 5.2% $0.5 0.2% Assembly Tooling $19.0 6.0% Assembly Equipment $40.4 12.9% Assembly Building $31.3 10.0% $313.7 100% Blanking Lines Blanking Building Welding Line Hydroform Lines Hydroform Building Total Investments Figure 11.4.1-4 Distribution of Investment Costs Investments for each process step show that the assembly line and related tooling and building expenses account for less than one-third of the total. The press shop is the major source of investment. Press lines account for over 30% of the investment total. Welding lines for producing tailored blanks are also significant, despite the fact that there are only 16 tailor welded blank parts used in the body structure 11.4.2. Cost Breakdown for Fabrication The parts fabrication total can be further broken down into $584 for major stamped components (including the Panel Roof which is produced with the Active Hydro-Mec Process), $41 for the two hydroformed side roof rails and $41 for the remaining small purchased parts (including ordinary tubes such as the pass-through beams and a number of small brackets and hinges). Chapter 11 - Page 14 Engineering Services, Inc. The primary driver for the major stamped parts is material. Due to the stage of program development, a very cautious approach was taken in determining blank sizes; therefore the level of engineered scrap results in a relatively high material cost. Cost per Vehicle Breakdown for Stamped Parts Material Cost Labor Cost Energy Cost $353 $36 $6 Total Variable Costs $395 Equipment Cost Tooling Cost Overhead Labor Cost Building Cost Maintenance Cost Working Capital Cost Total Fixed Costs TOTAL COST OF STAMPED PARTS $88 $51 $27 $7 $15 $1 $189 $584 Figure 11.4.2-1 Overall Cost Breakdown for Stamping As is typically the case, the other main cost components for the stamped parts are the equipment (press lines) and the tooling. Chapter 11 - Page 15 Engineering Services, Inc. 11.4.3. Cost Breakdown for Assembly Body structure assembly contributes less than one-third of the overall body structure cost. The main cost elements are the labor (mostly the indirect or overhead labor) and the assembly line equipment. Notable is the relatively low equipment cost which results from the reduced assembly effort required as a result of the parts consolidation. Breakdown for Assembly Material Cost Labor Cost Energy Cost Cost per Vehicle $0 $45 $10 Total Variable Costs Equipment Cost Tooling Cost Overhead Labor Cost Building Cost Maintenance Cost Working Capital Cost Total Fixed Costs TOTAL COST OF ASSEMBLY Figure 11.4.3-1 Overall Cost Breakdown for Assembly Chapter 11 - Page 16 $55 $50 $23 $125 $18 $9 $1 $226 $281 Engineering Services, Inc. 11.4.4. Cost Analysis for New Technologies and Materials While there are only 16 parts (eight left/right part pairs) that use tailor welded blanks, they make up a considerable fraction of the mass of the body structure. These 16 parts weigh 88.38 kg, which is 45% of the total body structure mass. Not surprising, they also represent a significant portion of the total body structure cost. These parts cost $279 to produce, which is 42% of the cost of all parts fabrication. This, of course, means that these parts cost more per kilogram than the rest of the body structure. This result is not unexpected because the additional welding step is required. However, this relatively small cost increase is compensated for by the reduced part count and thus reduced tooling and assembly costs. Further, the tailor welded parts offer the mass savings, which is the main objective of the ULSAB design. Part # Material Cost Blanking Cost Welding Cost Stamping Cost Total Cost 008/009 $11.96 $0.75 $2.75 $3.97 $19.43 010/011 $18.25 $0.99 $3.02 $4.16 $26.42 042/043 $25.39 $1.07 $2.20 $4.63 $33.29 046/047 $19.08 $1.10 $3.30 $4.94 $28.42 048/049 $9.27 $0.74 $1.95 $4.75 $16.71 060 $39.44 $1.90 $9.53 $11.06 $61.93 061 $39.43 $1.90 $9.53 $11.06 $61.92 070/071 $9.13 $0.49 $4.40 $3.91 $17.93 096/097 $6.78 $0.49 $1.64 $3.61 $12.52 TOTAL $178.73 64% $9.43 3% $38.32 14% $52.09 19% $278.57 100% Figure 11.4.4-1 Tailor Welded Blank Part Cost Breakdown Chapter 11 - Page 17 Engineering Services, Inc. The costs of tailor welded parts are still primarily driven by the material costs, which makes up 63% of the total. This is also true for the body sides (parts 060 & 061) where the blanking process was especially productionized to decrease the scrap associated with the large cutouts for the door openings. Processing costs divide fairly evenly between the welding and stamping operations, with the blanking step contributing only a small percentage. $375 Worst of All Inputs $348 Total Cost of TWB Parts $350 $325 Min: 50 mm/s Base: 100 mm/s Max: 150 mm/s Max: 40% Base: 30% Min: 15% Max: $5.3 Million Base: $3.8 Million Min: $3 Million $313 $300 $286 $288 Baseline $279 $275 $268 $272 $274 $260 $250 Best of All Inputs Weld Speed Downtime Equipment Total Figure 11.4.4-2 Effect of Welding Parameters on TWB Total Costs A key question regarding the use of a relatively new technology (i.e. tailor welding of blanks) is the certainty of the process variables and the effect of changes in these parameters on the part cost. Three major input parameters were considered for this sensitivity: the weld speed, the line unplanned downtime and the line cost. The baseline values used in the cost analysis were 100 mm/sec, 30% (four hrs/day downtime) and $3.8 million respectively. These factors were allowed to vary within a range of reasonable values. The graph shows that the cost of the parts is most Chapter 11 - Page 18 Engineering Services, Inc. sensitive to assumptions regarding the weld speed. A weld speed reduction to only 50 mm/sec would raise the cost by approximately $35. The downtime and line equipment costs have much smaller effects that might result in increases (or savings) of less than $10 each. Even under the worst case scenario of low weld speeds and high downtimes and equipment costs, the total part cost would only rise by about $50, or about 18%. Breakdown for One Side Roof Rail Material Cost Labor Cost Energy Cost Total Variable Costs Equipment Cost Tooling Cost Overhead Labor Cost Building Cost Maintenance Cost Working Capital Cost Total Fixed Costs Cost per Rail $11.08 1.53 0.11 $12.72 $4.87 0.82 1.23 0.15 0.58 0.05 $7.70 $20.42 TOTAL COST PER RAIL Figure 11.4.4-3 Cost Breakdown: Hydroformed Side Roof Rail Hydroforming is the other new parts fabrication technology used in the ULSAB design. While there are only two hydroformed parts, the left and right side roof rails, these components enable design changes in numerous other parts in the body structure. Because this process produces only two parts the cost significance is relatively low. Each side roof rail is estimated to cost $20, of which the majority of the non-material related costs result from the hydroforming equipment. Chapter 11 - Page 19 Engineering Services, Inc. The draw operation of the panel roof is planned in hydro-mech technology using a 10,000 ton hydraulic press. The investment cost of this press is $84 million, excluding installation and auxiliary equipment, the resulting operation cost including material is $18.41. The subsequent operations (trimming and flanging) are done in conventional presses. As the draw operation needs a far longer cycle time than the other operations (100 per hour vs. 400 per hour), the production sequencing has been separated. Laser welding has been incorporated into four areas of the assembly system. The total number of laser welders used is 13 at an average cost of $1.2 M each. High strength steels range in cost from $0.85 kg to $1.16 kg compared to mild steel, which costs $0.77. Laminate materials used on the spare tire tub and dash insert is at $3.60 kg. This results in relatively high prices for these parts. Chapter 11 - Page 20 Engineering Services, Inc. 11.4.5. Sensitivity Analysis A key element of the Economic Analysis is to determine the potential cost movements as a result of sensitivity analysis and other scenarios that could impact cost. Areas investigated are labor wage, unit energy costs, equipment life, building unit cost, production life and material costs: 3 years 5 years 8 years + 20% $44 p/hour -20% $1000 $1013 + 10% $352 -10% $994 $982 + 20% 0.10 $/kWh -20% Overall BIW Cost $975 15 years 20 years 25 years $955 $950 $950 + 20% $1500 p/m2 -20% $952 $947 $943 $944 $942 $925 $900 $909 $900 $912 $875 Labor Wage Unit Energy Cost Equipment Life Building Unit Cost Production Life Material Costs Stamping Parts Additionally, Tailored Welded Blanks, Hydroforming and Laser Welding are relatively new processes. As the utilization of these technologies increases so should efficiency and this would result in cost reductions. Chapter 11 - Page 21 Engineering Services, Inc. 11.5. Body Structure – Comparative Study 11.5.1. Overview Due to the fact that ULSAB’s holistic design approach uses new technologies such as hydroforming, laser welding, etc., a comparative study using conventional processes was created in order to analyze the overall competitiveness of ULSAB. A brief description of the models follows: • Year 2000 Reference Model – Base (A) Year 2000 Reference Model is based upon a generic four door passenger car body structure. The general body structure definition consists of a broadly described parts list made of groupings based on their size and complexity, and grouping of assembly operations based on their level of automation and size. Costs are generated via existing data, automotive industry inputs, predictive processes and general assumptions established by the Economic Analysis Group. The manufacturing processes used in this study were conventional stampings, spot welding and limited MAG welding. • Year 2000 Reference Model – PES Internal Study (B) To further analyze ULSAB’s competitiveness, alternative refinements were made to the Year 2000 Reference Model (A) in order to establish the potential range of costs for “classical” structures. To establish this, engineering judgment was used to integrate the general manufacturing assumptions of the Year 2000 Reference Model (A) with the design concept of ULSAB. Allowances for additional parts and gage increases due to the lesser use of high strength steel were made in an effort to simulate the performance characteristics of ULSAB. The result of this exercise was Year 2000 Reference Model (B). As the above described comparative study does not utilize the specific design or detailed manufacturing cost estimates contained within ULSAB, detail or technical comparisons with ULSAB cannot be made. Chapter 11 - Page 22 Engineering Services, Inc. For the purpose of direct comparisons, a specific detailed cost model of ULSAB in spreadsheet format is available and will be provided by the ULSAB Consortium to automotive manufacturers. This will allow the automotive OEMs to directly compare in detail, their current or future planned models with ULSAB. Chapter 11 - Page 23 Engineering Services, Inc. 11.5.2. Assumptions Cost Model Inputs Year 2000 ULSAB (A) (B)* 184 10 9 203 49% 230 0 20 250 55% 248 0 10 258 50% Direct Labor (Manpower) Indirect Labor (Manpower) 59 47 79 36 40 28 Total Parts Count Large Stamped Parts Medium Stamped Parts Small Stamped Parts Hydroformed Rails Purchased Parts 158 11 39 44 2 62 200 6 79 50 0 65 171 12 54 40 0 65 Total Number of Die Sets Transfer Tandem Progressive Hydroform 61 14 27 18 2 109 20 59 30 0 65 14 33 18 0 Transfer Tandem 4.1 3.6 3.8 3.2 4.1 3.6 Hits per Part Transfer/Tandem Combined 2.5 2.5 2.3 64 178 2,206** 18,286 136 13 114 20,865 80 210 3,250 0 200 0 130 30,000 74 202 3,060 0 154 0 128 28,156 Body Structure Mass Stampings (kg) Hydroformings (kg) Purchased Parts (kg) Total Mass (kg) Material Utilization (Stampings) Parts Fabrication Hits per Die Set Assembly Direct Labor (Manpower) Indirect Labor (Manpower) Number of Spot Welds Length (mm) of Laser Welds Number of Robots Number of Laser Welders Number of Assembly Stations Assembly Building Area (m²) * PES Internal study ** Includes 80 spot welds for brackets and reinforcements Chapter 11 - Page 24 Engineering Services, Inc. 11.5.3. Overall Results Year 2000 ULSAB (A) (B)* Stamping $584 $609 $592 Hydroforming 41 0 0 Purchased 41 41 41 Assembly 281 329 308 Total Cost $947 $979 $941 Total Mass (kg) 203 250 258 * PES Internal Study Chapter 11 - Page 25 Engineering Services, Inc. 11.6. Conclusion The ULSAB design is aimed at achieving two significant goals: • • Major mass savings Improved performance These goals have been met by implementing appropriate materials and technologies in to a holistic design approach. Individually some of the processes, such as, high strength steels, tailored welded blanks, hydroforming and laser welding are considered expensive, but when used in conjunction with a good design concept, gage reduction, part consolidation and efficient manufacturing methods, it results in an extremely cost competitive product. The results show that the Year 2000 Reference Model iterations are within 3.5% of the ULSAB cost but carry a major weight penalty. As this cost difference is smaller than the recognized level of variance generally considered for a calculated cost estimate, it is accepted that all models would cost approximately the same. Therefore, in conclusion, when coupled with good design, the technologies of high strength steel, tailor welded blanking, hydroforming and laser welding can be used to achieve mass reduction and performance improvements at no cost penalty. Chapter 11 - Page 26 Engineering Services, Inc. 12. Summary of Phase 2 Results Engineering Services, Inc. 12. Summary of Phase 2 Results The Phase 2 of the ULSAB program has come to its conclusion with the build of the demonstration hardware. The test results of the demonstration hardware are remarkable. Phase 2 Results Performance Mass 203 271 - 68 - 25% Static Torsional Rigidity (Nm/deg) 20800 11531 + 9269 + 80% Static Bending Rigidity (N/mm) 18100 11902 +6198 + 52% (Hz) 60 38 + 22 + 58% First Body Structure Mode (kg) Benchmark Difference Average Difference (%) Figure 12-1 Structural Performance Summary Relative to the benchmark average vehicle mass of 271 kg, the mass reduction achieved is 68 kg (25%). The static torsional rigidity exceeds the target. The efficiency (rigidity / mass) has increased, in relation to Phase 1, to 102.5 [(Nm/deg)/kg] (Fig. 12-2). The Phase 2 structural performance results are shown in the graphs as a tolerance field rather than a fixed point. To indicate that the mass and the performances can vary from one demonstration hardware structures to another, as it would also do in real mass production. The static bending rigidity as well as the first body structure mode have also been increased in comparison to the Phase 1 results (Fig. 12-3 and 12-4). These high levels of static and dynamic rigidity provide an excellent basis for a complete vehicle development in respect to its NVH behavior. Chapter 12 - Page 1 Engineering Services, Inc. Torsional Rigidity vs. Mass 110 24 Cb (x1000) [Nm/deg] Ct/m 60 18 14 80 ULSAB Phase I 20 16 90 70 22 20.8 100 ULSAB Phase II 50 Future Performance Reference ULSAB Target 40 12 30 Current Average 10 8 20 6 4 180 200 203 220 240 260 280 300 320 340 m [kg] All data adjusted to target vehicle Cb with Glass, m without Glass Reference Vehicles: Acura Legend, BMW 5 series, Chevrolet Lumina, Ford Taurus, Honda Accord, Lexus LS 400, Mazda 929, Mercedes Benz 190 E, Toyota Cressida Figure. 12-2 ULSAB Phase 2 Torsional Efficiency Bending Rigidity vs. Mass 110 100 90 80 Cb/m 70 24 22 ULSAB Phase II 60 20 Cb (x1000) [N/mm] 18.1 18 50 16 14 Future Performance Reference ULSAB Phase I ULSAB Target 40 12 30 Current Average 10 8 20 6 4 180 200 220 203 240 260 280 300 320 340 m [kg] All data adjusted to target vehicle Cb with Glass, m without Glass Reference Vehicles: Acura Legend, BMW 5 series, Chevrolet Lumina, Ford Taurus, Honda Accord, Lexus LS 400, Mazda 929, Mercedes Benz 190 E, Toyota Cressida Figure. 12-3 ULSAB Phase 2 Bending Efficiency Chapter 12 - Page 2 Engineering Services, Inc. First Body Structure Frequency vs. Mass 70 65 ULSAB Phase II 60.1 60 ULSAB Phase I 55 Future Performance Reference f [Hz] 50 45 ULSAB Target 40 35 Current Average 30 25 20 180 200 203 220 240 260 280 300 320 340 m [kg] Lowest global frequency f with Glass, m without Glass Reference Vehicles: Acura Legend, Chevrolet Lumina, Ford Taurus, Honda Accord, Lexus LS 400, Mazda 929, Toyota Cressida Figure. 12-4 ULSAB Phase 2 Frequency Efficiency The results of the crash analysis confirmed the integrity and safety of the ULSAB structure. The AMS Offset Crash is considered one of the most severe crash tests of today. In recently performed comparison crash tests of AMS, with the same vehicle towards a deformable barrier with 40% offset at 64 km/h versus the AMS Offset Crash barrier with 50% offset at 55 km/n, the results were nearly equal. This confirms that the decision to analyze the ULSAB structure for its offset crash behavior using the AMS test configuration, determined at the beginning of Phase 2 in 1995, was the right choice. The NCAP 100% Frontal Crash was run at 35 mph, 5 mph above the federal requirement of FMVSS 208, meaning 36% more energy had to be absorbed. In both the 50% Offset and 100% Front Crash low footwell intrusion and structural integrity proved the safety of the structure. Chapter 12 - Page 3 Engineering Services, Inc. The rear impact crash analysis, also run at 5 mph above the required speed of 30mph and showed fuel system integrity, passenger compartment integrity, residual volume and door opening after the analysis. The side impact crash analysis showed good results for criteria, such as passenger compartment intrusion, B-Pillar displacements and overall shape of deformation. The roof crash analysis proves that the roof meets the federal standard requirements and is stable and predictable. The crash analysis was run with a vehicle crash mass of 1612 kg, meaning secondary weight savings of other components such as engine; suspension, etc. were not considered, to achieve a conservative approach. Apart from the design of the structure and its optimized smooth load flow from front and rear rails into the rocker and the side roof rail concept; the use of high strength steels in 90% relative to the ULSAB structure mass was the key to achieve this crash performances at low mass. This need to use high strength steel to achieve this crash performance with the given target for mass was a challenge for the part design and our suppliers. Together with steel suppliers, part manufacturers, designers and engineers, the right materials were selected and the design was modified until it was feasible. Significant mass reduction was also achieved with the use of tailor welded blanks in combination with high strength steel. The elimination of reinforcements and joints between parts reduced mass and enhanced crash and structural performance. Furthermore, the total number of parts and assembly steps was reduced. With the use of the tubular hydroforming manufacturing process for the side roof rail and sheet metal hydroforming for the roof panel, parts could be manufactured, contributing to performance and weight reduction. The hydroformed side roof rail made from a tube with a relatively large diameter of 96mm and a wall thickness of 1mm from high strength steel was made feasible in Phase 2. Chapter 12 - Page 4 Engineering Services, Inc. The assembly sequence of the ULSAB structure with the body side inner subassembly, first assembled to the underbody structure and the body side outer in the following step, gives better weld access, especially in the rear of the structure. With this assembly sequence, weld access holes can be avoided and structural performance can be maintained. Laser welding in assembly is successfully applied to weld the body side outer panel and the roof to the side roof rail. In addition, it was used to join the fender support rails and the front rails to enhance the performance. In terms of the cost analysis, following extensive work in detail processing of components and assemblies, it was established that ULSAB would cost $947 to manufacture. The competitiveness of this cost is due to the design concept, which consolidated parts and eliminated many reinforcements, therefore saving stamping and welding operations. These savings were partially offset by the cost of high strength steel and the new technologies such as laser welding and hydroforming, but the final conclusion of the analysis is that ULSAB can be produced without cost penalty. Chapter 12 - Page 5