SAN FRANCISCO PLANNING DEPARTMENT Letter of Determination February 15, 2013 1650 Mission St. Suite 400 San Francisco, CA 94103-2479 Reception: 415.558.6378 Steve Atkinson McKenna Long & Aldridge LLP 121 Spear Street, Suite 200 San Francisco CA 94105 415.356.4600 Site Address: Assessor’s Block/Lot: Zoning District: Staff Contact: Fax: 415.558.6409 Planning Information: 415.558.6377 325 Fremont Street 3747/012 Rincon Hill Downtown Residential Mixed Use (RH DTR) District Ben Fu, (415) 558-6613 or ben.fu@sfgov.org Dear Mr. Atkinson: This letter is in response to your request for a Letter of Determination to verify the effect of the Rincon Hill Infrastructure Fee and the SoMa Stabilization Fund on the subject property in question. The Planning Commission first approved 325 Fremont Street (the "Project") on June 08, 2000. On January 27, 2005, the Planning Commission approved the amended Conditional Use (CU) authorization to increase the number of market rate dwelling units from 51 to 70 and the number of Below Market Rate (BMR) units from five to eight. Per Planning Code Section 418, both the Rincon Hill Infrastructure Fee and the SoMa Stabilization Fund were effective on August 19, 2005. The fee ordinance was approved approximately five and a half years after the original project approval and approximately seven months after the amended project. A Letter of Determination issued on June 16, 2006, specified that if a revised or new project was proposed, said project would then be subject to the impact fees as described per Planning Code Section 418. Building permits were issued for the original Project (Building Permit No. 9913300 for the new construction was issued on June 23, 2004, and Building Permit No. 2005.07.20.8180 for the amended project was issued on March 27, 2008). The current project as reviewed under Preliminary Project Assessment (PPA) is a new project. The new project utilizes the height increase in the approved Rincon Hill Plan from 200 to 250 feet to accommodate additional units (70 to 119 units), additional building height (200 to 250 feet), new building faade design, and a larger overall building envelope (96,000 to 160,000 gross square feet). Therefore, it is my determination that the project as reviewed under PPA is a different project than approved in 2000 and 2005 and the impact fees as mandated by Planning Code Section 418 would apply. APPEAL: If you believe this determination represents an error in interpretation of the Planning Code or abuse in discretion by the Zoning Administrator, an appeal may be filed with the Board of Appeals www.sfplanning.org Steve Atkinson McKenna Long & Aldridge LLP 121 Spear Street, Suite 200 San Francisco CA 94105 February 15, 2013 Letter of Determination 325 Fremont Street within 15 days of the date of this letter. For information regarding the appeals process, please contact the Board of Appeals located at 1650 Mission Street, Room 304, San Francisco, or call (415) 575-6880. Sincerely, Scott F. Sanchez Zoning Administrator cc: Ben Fu, Planner Property Owner Neighborhood Groups G \ DOCUMENTS\Ietters\letter_of_determination\Fremont_325_021113.doc SAN FRANCISCO PLANNING DEPARTMENT McKenna Long ’S11 J\..lcEl.ricE[geLLP Albany Atlanta Orange County Rancho Santa Fe Brussels San Diego 121 Spear Street Suite 200 San Francisco, CA 94105 Tel: 415.356.4600 mckennalong.com Denver Los Angeles New York STEVE ATKINSON 415.356.4617 1 San Francisco Washington, DC EMAILADDRESS ,iA/(Z..atkinson@mckennaIong.com Cc)oq/ November 27, 2012 1358 12.00014 Scott Sanchez Zoning Administrator Planning Department 1650 Mission Street, Suite 400 San Francisco, CA 94104 Re: Request for Determination Regarding Application of Rincon Hill Impact Fees to Proposed Modified Project at 325 Fremont (3 T?f 7/ 0 /2>) Dear Scott: We represent Fremont 325 Development LLC ("Fremont 325"), which purchased the 325 Fremont site and entitlements in late 2011. In August 2012, Fremont 325 submitted a PPA application for a possible revision of the project approved in 2005 ("Approved Project") to increase the height to 250 feet and make certain other changes. On October 2, the Planning Department issued its Preliminary Project Assessment ("PPA") which, among other things, indicated that entire gross floor area of the modified 250 foot high project ("Modified Project") would be subject to the Rincon Hill Infrastructure Impact Fee and the SOMA Stabilization Fee. While Fremont 325 recognizes that the Modified Project would be benefitted by the Rincon Hill Plan and zoning adopted in 2005 - most particularly by the increase of the site’s height limit from 200 to 250 feet - and thus would expect to pay the Rincon Hill impact fees for the additional levels that the increased height limit would permit. However, Fremont 325 does not believe the Rincon Hill impact fees should apply to the entire Modified Project. Therefore, for the legal and policy reasons set forth below, we are requesting a determination that the Rincon Hill impact fees only apply to the additional height/area that the Rincon Hill Plan and zoning would permit for the Modified Project as compared to the Approved Project. Background The original project for the 325 Fremont site was approved in June, 2000 as set forth in Planning Commission Motion 15086. That original project included up to 54 residential units, and 54 parking spaces, in a building with a height of 200 feet ("Original Project’). Subsequently, the then-owners sought approval of project modifications, which were approved on January 27, 2005 pursuant to Motion 16935. That Approved Project included up to 70 units and 5 1-70 parking spaces, also in a 200 foot tall building. 802126432.1 Scott Sanchez November 27, 2012 Page 2 Seven months after the Commission’s approval of the Approved Project, the City adopted the Rincon Hill Plan and associated Code amendments, which changed the height limit for the 325 Fremont site to 250 feet, and made other changes to the Planning Code, including the adoption of the Rincon Hill Infrastructure Fee and the SOMA Stabilization Fee. The Rincon Hill Plan and zoning amendments do not specify how those impact fees would apply to either a project such as the Approved Project that was approved prior to the Rincon Hill Plan or to any modification of such an Approved Project. In June 2006, the Zoning Administrator issued a determination that the Approved Project would not be subject to the requirements of the Downtown Residential Community Improvements Fund (now know as the Rincon Hill Infrastructure Fund) or the SOMA Stabilization Fund. The determination went on to state "However, if the Project [Approved Project] were to apply for a revised or new CU, the new application would then be subject to the impact fees as described in Planning Code Section 318" (subsequently re-codified as Planning Code Section 418). No authority or rationale was cited for applying these impact fees to any revision or modified project on the 325 Fremont site, nor did this determination address exactly how these impact fees might apply to a revision of the Approved Project. (We also note that the Modified Project in fact would not require a CU under the Rincon Hill Plan, but instead would be reviewed under section 309.1) In 2008, within the three year time limit, the site permit was issued for the Approved Project. That site permit, and thus the entitlements granted to the Approved Project, remain in effect today. Therefore, the owner of the 325 Fremont site has the right to proceed with construction of the Approved Project (200 feet, 70 units, 51-70 parking spaces) without any further approval by the Planning Commission. (In addition, the project sponsor would have the opportunity to make certain modifications to that Approved Project without Planning Commission approval, so long as the changes were determined by Planning staff to be substantially consistent with the Approved Project, including some increase in the unit count.) In late 2011, Fremont 325 purchased the 325 Fremont site, with the entitlements for the Approved Project. Because of the height limit increase allowed for this site under the Rincon Hill Plan/zoning, Fremont 325 wished to evaluate the feasibility of modifying the Approved Project, including increasing the height to the 250 feet permitted under the 2005 Rincon Hill Plan. A PPA application was submitted in early August 2012 for a project with up to 119 units and 61 off street parking spaces, in a building with a height of 250 feet ("Modified Project"). The PPA was issued on October 2, 2012. Among the many comments in the PPA letter were statements that the Modified Project would be subject to payment of the Rincon Hill Infrastructure Fee and the SOMA Stabilization Fee, and that for the proposed 160,300 sf structure, those fees would be $1,378,580.00 and $1,755,285.00 respectfully. These statements indicated that the Planning staff believed that the impact fees would be calculated based on the 802126432.1 Scott Sanchez November 27, 2012 Page 3 entire gross floor area of the Modified Project, not just the area by which the Modified Project would exceed the Approved Project. (The PPA letter’s use of 160,300 feet for gross floor area of the Modified Project is somewhat incorrect in any event, as that 160,300 gsf area includes parking which is not subject to the impact fees.) As noted above, there is an Approved Project, 70 units within a 200 foot high envelope, that Fremont 325 could construct if it wished, based on the active site permit. If the Approved Project is constructed, benefits to the City would include 8 on site BMR units, but no Rincon Hill impact fees. If the Modified Project is approved, it will provide either 14 on site BMR units, or more likely Fremont 325 would satisfy the BMR requirements by paying the fees for 20 units, which could result in payment of approximately $5.3 million of fees into the City’s affordable housing fund. Under the PPA letter, the project sponsor would also be subject to payment of Infrastructure and SOMA Stabilization Fees totaling approximately $3.1 million. Because the Modified Project would only be about 30,000 sf larger than the Approved Project (based on the area of the 5 levels that would be added above the original 200 foot height limit), the effective fee rate for that additional area would be in the range of $100 for each additional sf. Based on the impact fee burden that would be imposed to achieve that added area, if the impact fees were payable on the entire area of the Modified Project as the PPA letter suggests, Fremont 325 probably would decide to build the Approved Project, rather than the Modified Project, unless market conditions were so extraordinarily favorable enough to justify the additional $100/sf of impact fees for the added building area. Fremont 325 is requesting a determination that if the Modified Project is approved, then the Rincon Hill infrastructure and SOMA impact fees would only be imposed on the additional area that can be built in the Modified Project (as compared to the Approved Project) based on the Rincon Hill zoning. Under this approach, the Modified Project would be viable, and the City would secure many benefits from the Modified Project as compared to the Approved Project. These benefits would include: - Additional residential units (119 vs 70) in a location close to transit, jobs, and services - Additional BMR contribution: approximately $5.3 million in affordable housing fees vs 8 on site units for the Approved Project Approximately $625,000 of Rincon Hill impact fees, based on the added area of the building - Additional revenue from property tax, transfer taxes etc. due to the larger Modified Project 802126432.1 Scott Sanchez November 27, 2012 Page 4 - Zeno Place improvements (provided under the Rincon Hill Plan but not in the Approved Project). Therefore, the City would benefit substantially if you adopt the proposed determination that allows the Modified Project to be financially viable. Thus, there are strong policy arguments for adopting this requested determination. (Note, we are not requesting a determination as to the precise amount of the impact fees, as that will depend on the gross residential floor of the Modified Project that is finally approved by the Commission.) Moreover, there is nothing in this requested determination which is in any way inconsistent with the 2005 Rincon Hill Plan, or the June 2006 determination. There is nothing in the 2005 Rincon Hill Plan and zoning that specifies how the Rincon Hill impact fees would apply to revisions of an Approved Project like 325 Fremont. The proposed determination also is not inconsistent with the 2006 determination - that determination said that in the event of an application for a modified project, such a modified project would be subject to the Rincon Hill impact fees. The 2006 determination did not address exactly how the impact fees would apply to a modified project on the site, and did not address what portion of a modified project might be subject to the fees. Under our proposed determination, the Modified Project would be subject to impact fees imposed on the additional area that the Modified Project would build as a result of the increased height limit of 250 feet provided by the 2005 Rincon Hill Plan and zoning. Thus, the Modified Project would pay the impact fees proportionate to the benefit that the Modified Project would receive based on the Rincon Hill Plan’s increased height limit for the site. In response to the PPA letter, Fremont 325 has submitted an environmental application for the Modified Project. The purpose of this environmental application is to keep the process moving for the Modified Project, in the expectation that you will reach a determination that will make it viable to proceed with the Modified Project. Based on your determination, Fremont 325 will be able to decide whether it is worthwhile to pursue the Modified Project or proceed with the Approved Project. Please contact us if you would like any further information or to discuss this issues raised by this request. We are enclosing a fee of $601 for this determination request. Very truly yours, tkinson Enclosure: Application Fee for Determination 802126432.1