Clayton Taylor CEO ComRent ® International, LLC. 24 Hour Tests Are Needed! 24 Hour Tests Are Needed! • New New way of testing way of testing • Ways to sell through testing • Go after installed base • Uptime and compliance 2 Eventually Generators Will Be Put To The Test y • Ice storms I t • Black outs • Earth quakes • Hurricanes Hurricanes • Know what you don’tt know you don know 3 4 HR Method At 1.0 – Not Adequate 4 HR Method At 1.0 Not Adequate • 4 hr does not replicate realistic emergency situations • Consider multiple day tests up to 5 days • Does not provide for adequate transient testing • 1.0 power factor does not match real‐world loads at the facility at the facility • .9 leading power factor with capacitor becoming more important more important • Not enough run time to validate the system through temperature, testing and installation g p , g warranty 4 Old Way – 4 Hour Method Old Way 4 Hour Method • Low voltage load banks (typically 480 VAC) • Must be used with step down transformers • Systems can come Systems can come “pre‐wired” pre‐wired with all with all equipment mounted to a single trailer; or can come in separate containers that need to be field come in separate containers that need to be field connected • Low voltage load banks and transformer L lt l db k dt f assemblies introduce more components that can f il d i t ti fail during testing 5 24 Hour Medium Voltage Load Banks • Resistive or reactive load bank • Contains resistors or reactors that operate Contains resistors or reactors that operate above 690 VAC and below 15,000 VAC • Permanent/portable medium voltage load Permanent/portable medium voltage load banks often used for commissioning power plants maritime electrical systems standby plants, maritime electrical systems, standby generator systems and substations • The most common voltages used are 5kV Th t lt d 5kV (4,160V) and 15kV (13,800V) • Commissioning power systems 6 Low Voltage Load Banks vs. Medium Voltage Load Banks d k • • • • • Pieces C Connection points i i Points of failure Mutual inductance Labor • • • • • Pieces C Connection points i i Points of failure Mutual inductance Labor 7 8 9 10 Industry Case Studies 24 HOUR TESTING, CASE IN POINT… 24 HOUR TESTING, CASE IN POINT… 11 Water and Wastewater Emergency Power Why Testing Was Needed: • Commission Commission proper operation of proper operation of the entire system ‐ from fuel line through transfer switch • Generators should be step‐ loaded to accurately reflect system demands and ensure proper emergency load sequencing • Transient response, noise, p , , vibration and fuel‐use rates can be reviewed during the test Prevent disruption of a critical • Prevent disruption of a critical pumping process 12 Water and Wastewater Emergency Power Water and Wastewater Emergency Power Project Scope: j p – 2.8 MW resistive load at 4160V to generator – Commission new Commission new equipment at pump station • 3MW of resistive load banks, 3MW f i ti l d b k a 7MVA transformer, and switchgear with medium and low voltage cable low voltage cable • Labor for unit cable runs and tie in for the transformer 13 Data Centers Data Centers • Medium voltage load banks eliminates the use of ttransformers for testing f f t ti multiple generators in a data center pod data center pod • Safer for the generator since it is not subjected to it is not subjected to fluctuations in voltage and current when a transformer is used to step the voltage down for low voltage load b k banks 14 Oil and Gas Oil and Gas • Ensure that gas turbine generators continued to work while switching out analog controls for digital controls • Generators were absolutely y critical to the ongoing operation of the field. If the turbines ever failed – future flow rates would have been lost in the oil field • With medium voltage load With medium voltage load banks, the performance of the new digital controls was validated and the continued operation of the field ensured 15 Cruise Ships • Losing generator power at sea is a catastrophe that makes front page news • Medium voltage load bank testing right to the dock before testing right to the dock before the ship sets sail • When a cruise line installs new diesel generators , load bank testing ensures ships keep the lights on and the propellers lights on and the propellers turning • Never have to say DIW • Happiness aboard ship 16 Always Specify A 24 Hour Test Always Specify A 24 Hour Test • Closing Closing statements statements – Leaving future risk and downtime intact – 5‐day test to mimic 100 day storm event – Generators don Generators don’tt run run under water (flood plain operation) • Recap • Enforce key messages 17