Essar Steel Minnesota Project - NPUC thing to complete as of 4-1-2015
Description Projected completion date
1.
Install electric to ESML facilities on Co Rd 58 Admin., security, truck scale 2015?
Waiting for ESML layouts
2.
Track and monitor project expenses On going
3.
Track ESML construction power to not exceed 6MW ( facility capacity) On going
4.
Verify ESSAR complies with ESA electric installation requirements Late 2015
5.
Verify ESML gas pipeline construction in corridor by electric duct bank 2015-2016
6.
Assist in applying for CIP exception for ESML By ESML& NPUC
7.
ESML-NPUC-MP substation access safety agreement 2015
8.
Re test and Energize McCarthy Lake & Calumet substations Late 2015
9.
Finalize Water/sewer infrastructure agreement 2015
10.
Complete the relocation of sewer- water line in CC area 2015
Waiting for ESML layout
11.
Steve Sherner On- going power supply assistance 2015-2016
12.
Re-inspection and place into service 4 sewer lift stations Late 2015
13.
Finish electric duct bank erosion control after ESML installs gas line and site grading 2016
14.
Inspect water-sewer connection from ESML buildings to NPUC mains 2015
Other Contact issues Direction and guidance from Steve Sherner & Kaela Brennan a.
Finalize Lake Country Power profit sharing agreements 2015 b.
Revise LISA to reflect ESML new start-up schedule Completed c.
Initiate and finalize the electric service territory issues with LCP in the Bozich addition. d.
Agreement to retain portion of 23 KV construction line thru ESML property. 2015-2016 e.
Master development agreement amendment 2016