BIHAR ELECTRICITY REGULATORY COMMISSION Vidyut Bhawan-II, Bailey Road, Patna – 800 021 Case No. 06/2012 IN THE MATTER OF : Petition under section 63 of the Electricity Act, 2003 for approval and adoption of Tariff for procurement of Base Load Power 560 MW (Essar-300 MW & GMR-260 MW) on Long Term Basis under case-1 route of Tariff based on Competitive Bidding Guidelines of Ministry of Power, Government of India. And Bihar State Electricity Board Vidyut Bhawan, Jawahar Lal Nehru Marg, Bailey Road, Patna-800021 …..………. Petitioner Present: 1. Sri U. N. Panjiar - Chairman 2. Sri S. C. Jha - Member 3. Sri K. P. Singh - Member Appearance on behalf of Petitioner, BSEB 1. Mr. Rakesh, EEE(Inter-state) Bihar State Electricity Board Order 1. Dated 27.11.2012 It is a petition filed by the petitioner Bihar State Electricity Board (hereinafter referred to as ‘BSEB’ or ‘petitioner’) under the provision of section 63 of the Electricity Act,2003 (hereinafter referred to as ‘Act’) for approval and adoption of tariff for procurement of 560 MW of power on tariff based competitive bidding in accordance with the “Guidelines for Determination of Tariff by Bidding Procurement of power process for by Distribution Licensees”(hereinafter referred as ‘Competitive Bidding Guidelines’ or Guidelines) issued by 1 the Central Government vide resolution no.23/11/2004 –R&R(vol.II) as amended from time to time. 2. Submission in the Petition In its petition dated 13.02.2012, the BSEB has made following submissions :(i) The Bihar State Electricity Board (hereinafter referred to as ‘BSEB’ or ‘petitioner’), an autonomous body constituted under section 5 of Electricity Supply Act, 1948 duly formed by Government of Bihar under legislative decree having its head office at Vidyut Bhawan, Jawaharlal Nehru Marg, Patna-800021. (ii) The Bihar Electricity Regulatory Commission (hereinafter referred to as Commission or BERC) vide its tariff order dated 06.12.2010 passed in Case no. TP-3 of 2010 pertaining to Determination of ARR and Retail tariff for the financial year 2010-11 of BSEB had under directive-25 (4) has directed BSEB to initiate bidding process for 1050 MW (1500 MW-450 MW) power without any delay. The issue was also discussed in the review meeting taken up by the Chief Minister, Bihar. In compliance of the directive of the BERC and subsequent direction of Govt. of Bihar, BSEB initiated bidding process for long term (25 years) under Case-I based on the standard bidding documents and guidelines issued by Ministry of Power, Govt. of India vide resolution dated 19th January, 2005 and its amendment time to time without any deviation. (iii) Earlier, the Commission vide its letter no. BERC-Misc-1/08-250 dated 21.07.2010 has noted that BSEB intend to procure 1500 MW power under Case-I Standard bidding document based on the guidelines issued by Ministry of Power, Govt. of India without any deviation. BSEB also vide its letter no. 113 dated 14.01.2011 had informed BERC under provision of Clause 3.1 (i) of the Guidelines 2 for Determination of Tariff by Bidding process for procurement of power by Distribution Licensees issued by Ministry of Power, Govt. of India about the procurement of 1050 MW± 20% power at delivery point through competitive bidding process under Case-I. BERC vide its letter no. BERC-Misc.-1/08 (Part)-36 dated 21.01.2011 had informed BSEB that Commission has no objection to the proposal of BSEB to go ahead for procurement of 1050 MW± 20% power at through competitive bidding process under Case-I. The procurement process should be through transparent process of bidding and in accordance with the guidelines issued by Ministry of Power, Govt. of India as amended from time to time. (iv) It is also essential to mention that procurement of 1050 MW± 20% power by BSEB is part of the 1500 MW± 20% power for which BSEB had initially issued NIT no. 212/PR/BSEB/2009 for procurement wanted through tariff based bidding process under Case-I for long term and Commission vide letter no. 250 dated 21.07.2010 had already communicated to BSEB that procurement of 1500 MW power by BSEB through tariff based bidding process under Case-I for long term was noted by BERC. Further, it may not be out of place to mention that BSEB against the tender notice NIT no. 212/PR/BSEB/2009 for procurement of 1500 MW± 20% power, BSEB had contracted 450 MW power from Essar Power(Jharkhand) Limited (L1 bidder). Hon’ble BERC vide its order dated 01.02.2012 passed in case no. 08/2011 had adopted the levellised tariff of Rs. 3.057 per KWh and also the year-wise tariff for which PPA has been signed for procurement of 450 MW power. (v) BERC vide para 12 of the tariff order dated 01.02.2012 passed in Case no. 08/2011 had also noted the justification given by BSEB for procurement of 1500 MW power through competitive bidding process under Case-I for long term. 3 (vi) The petitioner issued the advertisement “Notice Inviting Tender” NIT No. 02/PR/BSEB/2011 on 14.01.2011 for the procurement of balance 1050 MW± 20% power at delivery point through competitive bidding process under Case-1 route of the ‘Guidelines for Determination of Tariff by Bidding Process for procurement of power by Distribution Licensees” as issued by Ministry of Power, Govt. of India on 19.01.2005 and its amendments from time to time (hereinafter referred to as the “Competitive Bidding Guidelines” or “CBG”). The bid documents were made available for download on BSEB website http://bseb.bih.nic.in from 20.01.2011 to 03.02.2011. The single stage bidding documents were prepared in line with the Standard Bid Documents (Case 1) issued by Ministry of Power, Govt. of India on 21st July 2010, without any deviation. The pre-bid meeting for the clarification of the queries raised by the bidders was held on 11.02.2011. The RfP documents, along with the reply to the queries raised by the bidders, were uploaded on BSEB’s website http://bseb.bih.nic.in on 22.02.2011, with submission of bids being 04.04.2011 till 1:00 p.m., providing sufficient time of 45 days to all the bidders in compliance with Clause 5.5 of the tariff based competitive bidding guidelines issued 21st July 2010. (vii) The petitioner constituted a Bid Evaluation Committee (BEC) in compliance with Clause 5.9 of CBG. The BEC comprised of the following members with one independent/external member : Sl.No. Name of the person Position 1. Shri R. P. Choudhary Coordinator Chief Engineer ,Transmission (O & M), BSEB 2. Shri Hemant Kumar External Member Chief Manager, Rural Electrification Corporation, Patna 3. Shri A. K. Sinha Member BSE (Interstate), BSEB 4. Shri P. R. Sinha Member 4 5. 6. ESE (APDRP), BSEB Shri Rakesh Electrical Executive Engineer BSEB Shri N. K. Jha Director (Expenditure), BSEB (Interstate), Member Member (viii) The petitioner submits that, Eight (8) bidders (i.e. twelve nos. of Non Financial Bids as two trading licensees M/s PTC India Ltd. and M/s National Energy & Trading Services Ltd. (NETS) has tied up four and three developers respectively) have submitted their bids of varying capacities against NIT No. 02/PR/BSEB/2011, dated 14.01.2011 and the Non-Financial-Bids were opened as per the schedule date i.e. 04.04.2011 and time i.e. 1500 hrs (IST). The list of the bidders and the capacity offered is listed below : Sl. No Bidders name Nature of the bidder Quantum of power offered 260 MW Fuel Location of Power Source 1 GMR Energy Kamalanga Bidding company Coal Bidding company 1050 MW Coal Bidding company 650 MW Coal 1050 MW Thermal Power Project, Village- Kamalanga, District-Dhenkanal, Orissa 1350 MW Amravati Thermal Power Project (Phase II) Nandgaonpeth, District-Amravati, Maharastra 1.2x350 MW Thermal Power Plant at Sahajbhal, DistrictJharsuguda, Orissa 2. 2x350 MW Thermal Power Plant at Kandarei, Athagarh, DistrictCuttack, Orissa. 3. 2x600 MW Thermal Power Plant at Jangir, DistrictChampa, CG 4. 2X600 MW Thermal Power Plant at District Anupur, State-MP 2. Indiabulls Power Ltd. 3. PTC India Ltd. Trading Company Thru: 1. Ind-Barath Energy (Utkal) Ltd. 2. KVK Nilanchal Power Pvt. Ltd. 3. DB Power Ltd. 4. MB Power (MP) Ltd. 5 4. Essar Power Ltd. Bidding company 300 MW Coal 5. Reliance Power Ltd. Bidding company 1050 MW Natur al Gas 6. National Energy Trading & Services Ltd. Trading Company Thru: 1. Lanco Vedarbha Thermal power Ltd. 2. Lanco Power Ltd. 3. Lanco Babandh Power Ltd. Bidding company 740MW Coal 7. Jaypee Ventures Ltd. power Bidding company 100 MW Coal 8. Shapoorji Pallonji Energy (Gujrat) Pvt. Ltd. Bidding company 255 MW Coal (ix) TehsilChandwa, DistrictLatehar, State- Jharkhand 2400 MW Samalkot Power Project, at Area (IDA) Peddapuram, Industrial Estate, Mandal Samalkot, Dist. East Godwari, AP 1. 2x660 MW Thermal Power Plant at Mandava, District Wardha, Maharashtra 2. 4x660 MW Thermal Power Plant at Village Pathadi, District Korba, Chattishgarh. 3. 2x660 MW Thermal Power Plant at Village Kurunti/ Kharagprasad, District-Dhenkanal, Orissa 2x660 MW Thermal Plant at Village Nigrie, DistrictSingrauli, State MP. 2x660 MW Thermal Plant at Village Kaj & Nanwada DistrictJunagadh, Gujrat The evaluation of the Non financial Bids was carried out by M/s Bihar Power Infrastructure Company Pvt. Ltd., the Bid Process Management consultant (hereinafter referred to as ‘Consultant’) engaged by the petitioner. During the bid evaluation process, BSEB sent written requests to the select bidders to submit certain clarifications in accordance with the Clause 2.5 (g) of the RfP. The last date for the submission of responses to the clarifications sought by BSEB was prescribed as 26.04.2011 which was further extended till 29.04.2011. The responses to the queries from the bidders were received by BSEB in due time. As it look considerable time, the date 6 of opening of the financial bids was extended till 09.05.2011. The bidders were accordingly informed on 16.04.2011 through email, fax and (BSEB) website notice. (x) Based on the submission of the bids by the Bidders, a detailed Non financial Bid Evaluation report (Annexure I) was submitted to Bid Evaluation Committee by the BSEB. There were certain minor deficiencies and non compliances of the provisions of RfP in the Non-financial bids of 6 bidders. A detailed agenda on the nonfinancial bids evaluation was circulated to the members of the Central Purchase Committee (CPC) of BSEB. The CPC, vide its meeting no. 07/2011 dated 17.05.2011 recommended qualifying 7 bidders, except M/s Shapoorji Pallonji Energy (Gujrat) Pvt. Ltd. Subsequently, the matter was placed before the BSEB Board. The Board considered the recommendation of the CPC on approving the minor deficiencies and non compliances and approved qualifying seven (7) bidders, except M/s Shapoorji Pallonji Energy (Gujrat) Pvt. Ltd. vide its resolution no. 8608 in the 540th Board meeting held on 16.06.2011 (Annexure-II), subject to submission of sworn in affidavits to comply with the conditions imposed by BSEB. (xi) Based on the submissions to queries, affidavits and original document verification of the qualified bidders, the seven financial bids of the qualifying bidders were opened on 28.06.2011 in the light of the approval accorded in the Board and in presence of the bidders’ authorized representatives. The summary of the levelized tariff discovered in the financial bids so opened are as under : Rank Name of Bidder Quantum of power offered Details of injection point 1. Essar Power Ltd. 300 MW CTU 400 KV line pooling station at Ranchi 7 Quoted Levelised Tariff (Rs./KWh) 3.690 Criteria for bid evaluation & payments Power generation source with captive coal block 2. Jaypee power Ventures Ltd. 100 MW CTU-PGCIL Satna 3.879 3. National Energy Trading & Services Ltd. (Project Developer-Lanco Babandh Power Ltd.) GMR Kamalanga Energy Ltd. 250 MW ER-CTU 3.902 260 MW 4.030 PTC India Ltd. (Project DeveloperKVK Nilanchal Power Pvt. Ltd.) PTC India Ltd. (Project Developer DB Power Ltd.) 200 MW Angul Pooling Station of Powergrid, Orissa 400 KV at Busbar located in Cuttack district, Orissa PGCIL Pooling station Kotra, Chhattisgarh PTC India Ltd. (Project DeveloperMB Power (MP) Ltd. Indiabulls Power Ltd. 200 MW CTU Anupur, Madhya Pradesh 4.411 1050 MW CTU Pooling Station near Nagpur 4.415 PTC India Ltd. (Project Developer Ind –Barath Energy (utkal) Ltd.) National Energy Trading & Services Ltd. (Project Developer- Lanco Power Ltd.) National Energy Trading & Services Ltd. (Project Developer- Lanco Vedarbha Thermal Power Ltd.) Reliance Power Ltd. 150 MW CTU Pooling station near Jarsugunda 4.591 120 MW Chhatishgarh 4.954 Power generation source linkage based coal 370 MW CTU Maharastra 5.446 Power generation source linkage based coal 1050 MW Vemagiri Pooling Station (PGCIL) 12.445 Power generation source with imported gas (RLNG) 4. 5. 6. 7. 8. 9. 10. 11. 12. 100 MW 8 4.076 4.088 Power generation source with captive coal block Power generation source linkage based coal Power generation source linkage based coal Power generation source linkage based coal Power generation source linkage based coal Power generation source linkage based coal Power generation source linkage based coal Power generation source linkage based coal (xii) M/s Essar Power (Jharkhand) Ltd. (L1) has offered 300 MW capacity having Captive Coal Mine (Pit head Plant) at Distt-Latehar, Jharkhand with tariff of Rupees Three Point Six Nine only (Rs. 3.690) per unit at the BSEB delivery point. The tariff is firm and not subject to escalation except for change on account of transmission charges and losses of Eastern Region for power injected from the injection point to delivery point. (xiii) The outcomes of the financial bids evaluation were placed before the CPC for its recommendation. Considering the meager generation capacity, high dependence of State on central allocation and rise in the cost of power procured even through the competitive bidding route within a span of a year, the CPC vide its meeting no. 09/2011 dated 05.07.2011 recommended the procurement of power 910 MW from L1, L2, L3 & L4 after apprising the state government in this regard, and subject to approval of the Board. (xiv) Meanwhile, considering the vailidity of the bids submitted by the bidders till 2nd August 2011, the Petitioner vide its letter dated 30th July 2011 requested the qualified bidders to extend the validity of their bids for an additional period of 45 days i.e. till 16 th September 2011. The following bidders extended the validity of their bids as requested by BSEB: a. b. c. d. e. (xv) GMR Kamalanga Energy Ltd. PTC India Ltd Essar Power Ltd. Reliance Power Ltd. Jaypee Power Ventures Ltd. The petitioner also submits that M/s Indiabulls Power Ltd. had extended its bid by a period of 15 days only, against the Petitioner’s request for extension of 45 days. M/s National Energy Trading & Services Ltd. (NETS) had extended the bid only for one generation source- Lanco Power Ltd. In case of other two project developers of NETS, it has regretted and not extended the validity of bids. 9 (xvi) The outcomes of the financial bids and the recommendation of the CPC were placed before the Board of BSEB for its consideration and approval. The Board discussed the matter in detail and took cognizance of the facts that: a. During the last one year period i.e, the period between the submission of the bids in current & previous Case 1 bidding process, the tariff has substantially increased. b. There is now acute shortage of coal linkages for all projects. Even the prices of imported coal have risen sharply. c. With the experience of two Case 1 bidding procedures, it also noted that the entire bidding process takes more than 180 days. (xvii) Thereafter, the Board of BSEB vide resolution no. 8619 in the 541 st Board meeting held on 04.08.2011 (Annexure-III) gave approval to issue Lol to M/s Essar Power Ltd. (L1 bidder) for supply of 300 MW power at the quoted levelised tariff of Rs. 3.690 per KWh and further suggested that the L2, L4, L6, L7 may be offered an opportunity to give their counter-offers equal to the levelized tariff of L1 bidder and then the balance requisitioned contracted capacity may be split among the bidders who match the levelized tariff of L1 bidder. Accordingly, the petitioner sent letters to the bidders Jaiprakash Ventures Pvt. Ltd., GMR Kamalanga Energy Ltd., PTC India Ltd. & Indiabulls Power Ltd. to submit the counter-offers to match the levelized tariff of L1. In response, M/s GMR kamalanga Energy Ltd. submitted its counter-offer and match the levelized tariff of L1. (xviii) Further, Board has directed that if the balance requisitioned capacity of 960 MW is not met by the aforesaid bidder who accepts the counter offer, the process will be repeated and counter offers will be made to L9, L10 etc. bidders who have qualified in the evaluation process. 10 (xix) Subsequently, the Petitioner informed the Principal Secretary, Department of Energy, Govt. of Bihar about its intent of procuring 560 MW power from the bidders M/s Essar Power (Jharkhand) Ltd. (300MW) and M/s GMR Kamalanga Energy Ltd. (260 MW), Thereafter, the Petitioner issued the Letter of Intent (LoI) No. 27/Misc/Com/IS/1214/2007/ (Part-V)/1430 dated 17.08.2011 to the Bidder – M/s Essar Power Ltd. for supply of 300 MW with a request to submit the Contract Performance Guarantee (CPG) and sign the “RfP Document” within the stipulated time of 30 days, in compliance with Clause 2.2.9 of RFP. The “ Unconditional Acceptance” of LoI by Ms Essar Power (Jharkhand) Ltd. was received on 20.08.2011 and is attached as Annesure IV. Also, the Petitioner issued the Letter of Intent (LoI) No. 27/Misc/Com/IS/1214/2007/ (Part-V)/1569 dated 06.09.2011 to the Bidder- M/s GMR Kamalanga Energy Ltd. for supply of 260 MW with a request to the to submit the Contract Performance Guarantee (CPG) and sign the “RfP Document” within the stipulated time of 30 days, in compliance with Clause 2.2.9 of RFP. The “ Unconditional Acceptance” of LoI by Ms GMR Kamalanga Energy Ltd. was received on 12.09.2011 and is attached as Annesure V. (xx) On submission of Contract Performance Guarantee (CPG) of the required amount Rupees Ninety Crores only (Rs.90 Crores) in compliance with Format 5.7 of the RFP and as part of Schedule-9 of the PpA by M/s Essar Power (Jharkhand) Ltd. on 17th October 2011, the “RfP Document” was signed with “M/s Essar Power (Jharkhand) Ltd.” the Project company dully incorporated (on 19th October 2005) by the successful bidder, M/s Essar Power Ltd. for supply of 300 MW power from its proposed 2x600 MW power project being implemented at Tahsil; Chandwa, District: Latehar, State:Jharkhand. The signed RfP Document is attached as Annexure 11 VI. During the signing of the RfP documents, M/s Essar Power (Jharkhand) Ltd. submitted to BSEB that the Project Company itself houses the coal mining as well, hence referring to Article 4.2.1(i) should include “if applicable”. The same aspect was considered by BSEB at that moment, as it was not a material change, however, subject to the approval of the Commission. (xxi) Further, on submission of Contract Performance Guarantee (CPG) of the required amount Rupees Seventy Eight Crores only (Rs. 78 Crores) in compliance with Formant 5.7 of the RFP and as part of Schedule-9 of the PPA by M/s GMR Kamalanga Energy Ltd. on 9th November 2011, the “RfP Document” was signed with “M/s GMR Kamalanga Energy Ltd.” the Project company dully incorporated (on 28th December 2007) by the successful bidder, M/s GMR Kamalanga Energy Ltd. for supply of 260 MW power from its proposed 3x350 MW power project being implemented at village Kamalanga, DistrictDhenkanal, State: Orissa. The signed RfP Document is attached as Annexure VII. (xxii) The Petitioner, humbly submits before the Commission that the Technical and Financial bids were received on the Scheduled date of 4th April 2011 and at time 1 PM and that the entire process was concluded within 294 days. A petition was submitted by BSEB vide letter no. 27/Misc/Com/IS/1214/2007/ (Part-V)/1319 dated 29.07.2011 before the Commission for approval of extension of time period beyond 195 days i.e. upto 16.09.2011 to complete the bid process. The actual time taken to complete the bid process under Case-I was 294 days which is 79 days more than the time period of 195 days as per guidelines. The following table-VII captures the time schedule as provided in the RFP versus actual time taken in concluding the procurement process of 560 MW power initiated vide 12 NIT No. 02/PR/BSEB/2011, dated 14.01.2011 under Case-I Competitive Bidding Process for long term under is given below: Table- VII Event Date of Issue of RfP Submission of written clarification/amendments if any, on the RFP/RFP Documents by the Bidders Pre-Bid Meeting Revision of RfP and RfP documents (if required) and issuance of revised RfP and RfP Event Schedule as per RfP 20.01.2011 to 03.02.2011 07.02.2011 ActualEssar - ActualGMR - - - 11.02.2011 18.02.2011 - - - Schedule as per Actual-Essar Actual- RfP Document Bid submission and opening of Non Financial Bid Opening of Financial Bid of Qualified Bidders Shortlisting of Successful Bidder(s) and issue of LOI Signing of RfP Documents Total Days Taken GMR 04.04.2011 - - 19.04.2011 - - 29.04.2011 17.09.2011 26.09.2011 19.05.2011 120 17.10.2011 271 09.11.2011 294 (xxiii) The petitioner successfully completed the activity of ‘Signing of RfP documents’ with the successful bidders on 9th November 2011. (xxiv) The petitioner issued the press note in daily newspaper (Annexure VIII) informing public about the signing of the RfP Documents and then made the evaluation public on the website http://bseb.bih.nic.in as per the provision 6.3 of the competitive bidding guideline issued by Ministry of Power, Govt. of India on 19 th January 2005. 13 (xxv) The petitioner intends to procure only Five Hundred and Sixty Megawatt (560 MW) power from M/s Essar Power (Jharkhand) Ltd. and M/s GMR Kamalanga Energy Ltd. as the tariff offered by them is competitive and firm. The tariff offered by other bidders was found higher than the tariff discovered through the Case-I competitive bidding in other states of India. The tariff discovered by other Distribution Licensees through Case 1 bidding in tabulated in the table below : Sl. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 State Gujart Maharastra Haryana Madhya Pradesh Rajasthan Bihar Karnatka Noida power Reliance Mumbai Round Year Developer Capacity (MW) Fuel I I I I II II II 2006 2006 2006 2006 2010 2010 2010 1000 1000 1000 200 1010 800 800 Coal linkage Coal linkage Imported Coal Coal linkage Coal Block Imported coal Imported Coal I I I II II II I I I 2008 2008 2009 2010 2010 2010 2008 2008 2007 Adani Adani Essar Aryan KSK Energy Essar Shapoorji Pallonji Adani Lanco JSW Adani Indiabulls Emco Adani PTC-GMR Lanco Levelised Tariff (Rs/KWh) 2.89 2.35 2.25 2.40 2.35 2.80 2.80 1320 680 300 1320 1200 300 1424 300 600 Coal linkage Coal linkage Coal linkage Coal linkage Coal linkage Coal linkage Blended coal Coal linkage Coal linkage 2.64 2.72 3.21 3.28 3.26 2.88 2.94 2.86 2.34 I I I I II II I 2007 2007 2009 2010 2011 2011 2010 1241 300 1000 450 300 260 430 Coal NA Coal Coal Coal Coal NA 2.45 2.95 3.25 3.06 3.69 3.69 3.77 I 2010 400 NA 3.89 I III 2010 2011 Reliance Essar Adani Essar Essar GMR Thermal Powertech East Coast Energy NCC Essar 400 200 NA Coal Block 3.89 4.08 RPGDhariwal 200 Coal linkage 3.51 Infra, 2011 14 linkage linkage Block Block linkage (xxvi) The petitioner submits the Evaluation Committee Report (Annexure IX) and certificate (Annexure X) abiding with the clause 6.4 of the Guideline. (xxvii) The petitioner humbly submits this petition to the Commission under following provisions : Section 63 of the Electricity Act 2003 that states : “Notwithstanding anything contained in section 62, the Appropriate Commission shall adopt the tariff if such tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government” Clause 6.4 of the guidelines notified on 27th July 2007 states, that: “The signed PPA along with the certificates provided by the evaluation committee and by the procurer as provided in clause 6.2 shall be forwarded to the Appropriate Commission for adoption of tariffs in terms of section 63 of the Act.” (xxviii) The petitioner submits the following documents along with the petition : Annexure I Annexure II : : Annexure III : Annexure IV Annexure V : Annexure VI Annexure VII Annexure VIII : : : : Non financial Bid Evaluation report Approval of the Board on the Recommendation of CPC pertaining to the infirmities/non-compliance of the provisions of RfP in the non financial bid vide resolution no. 8608 dated 16.06.2011 and opening of the financial bids. Approval of the Board vide resolution no. 8619 dated 04.08.2011 for issue of LoI to L1 Bidder and issue of counter-offers to L2, L4, L6, L7, L8 bidders and thereafter to L9 & L10 bidders to match L1 rate. “Unconditional Acceptance” of LoI by Ms Essar Power (Jharkhand) Ltd. “Unconditional Acceptance” of LoI by Ms GMR Kamalanga Energy Ltd. Signed “RfP Document” with Ms Essar Power (Jharkhand) Ltd. Signed “RfP Document” with Ms GMR Kamalanga Energy Ltd. Press note in daily newspaper informing public about the signing of the RfP Document with M/s Essar Power 15 Annexure IX Annexure X : (Jharkhand) Ltd. and Ms. GMR Kamalanga Energy Ltd. Evaluation Committee Report : Certificate (xxix) The petitioner humbly prays to the Commission : (i) To approve/adopt procurement of Five Hundred Sixty Megawatt (560MW) of power from M/s Essar Power (Jharkhand) Ltd. and M/s GMR Kamalanga Energy Ltd. at the Levelised Tariff of Rupees Three point Six Nine only (Rs. 3.690) per KWh as per the signed “RfP Document” and under the provisions of the RfP. (ii) Approval of the BERC of the time period 294 days i.e. delay of 79 (seventy nine) days beyond the 195 days, taken to complete the bidding process under Case-I. (iii) Condone any inadvertent omission/errors/shortcomings and permit BSEB to add/change/modify/alter this filing and make further submissions as may be required at the future date as per the Commission’s Requirement. (iv) To pass any other order as deemed appropriate for adoption of tariff. 3. Chronology of Hearing 3.1 The petition of BSEB was heard by the Commission on 28.03.2012. An audio-visual presentation was made by BSEB through their consultant (IL&FS). During the presentation, the commission observed that :a. Earlier in 2009 bids were invited for procurement of 1500 MW of power under case -1 of competitive bidding guidelines against which PPA was signed for purchase of 450 MW from Essar Power Ltd. The levelised tariff adopted and approved by the commission for the said purchase was Rs.3.057 per kwh. The present agreed price with Essar Power Ltd is Rs.3.69 per kwh. The reason for increase in the 16 proposed procurement price for power from same project and same supplier during short span of two years, could not be clarified by the BSEB. Even the Bid Evaluation Committee has not made clarification in their recommendation on this specific point. b. In the case of GMR, the commission observed that land requirement, fuel linkage are yet to be completed by the bidder. Even the requirement of water for the proposed project of GMR is 37 million cusec, whereas, the linkage available with them is only for 30 million cusec. c. It also appears that BSEB has taken deviations in the terms and conditions of the bidding conditions approved by Government of India for which prior approval of Commission has not been sought by BSEB. The reasons leading to avoidance of prior approval from the Commission by the BSEB may be obtained from BSEB. Secretary, BERC was directed to take up the matter with BSEB for early submission of the details and the requisite fee. 3.2 The Commission reviewed compliance of it’s directive on 22.05.2012 and directed BSEB vide letter no. BERC/Tariff-03/12-475 dated 24/05/2012 to submit by 6th June 2012 the information/justification as observed by the Commission .The next date for hearing was fixed on 13.06.2012 . In compliance, the BSEB vide letter no.994 dated 23.5.2012 submitted the (i) following documents:- Tariff rates of the case -1 bidding for long term power procurement carried out in other states in near past. (ii) The calculation of the average power purchase cost from NTPC power stations in eastern region for the month of June and July 2011(annexure-II), indicative tariff offered by NTPC for supply of additional 75 MW power from Farakka stage-III (annexure –II/A) and tariff claimed by DVC as per petition filed before CERC for supply of 100 MW power from unit no.7 & 8 of Mejia TPS(2x500MW) annexure-II/B. 17 (iii) Copy of the presentation given before the Hon’ble Commission on 28.3.2012 The BSEB also submitted the justification for the deviations considered by BSEB vide letter no.1239 dated 25.6.2012. 3.3 The matter was heard on 04.07.2012 by the Commission and BSEB was directed to submit clarifications regarding the bidding procedure followed by the BSEB in the present procurement, compliance of the Competitive Bidding Guidelines issued by Govt. of India in this regard and methodology for determination of levelised tariff. The BSEB submitted the following documents vide letter no.1374 dated 10.07.2012:a. Procedure followed by the BSEB in present procurement b. Compliance of the Bidding Guidelines issued by Govt. of India c. 3.4 Methodology for determination of levelised tariff. The matter was heard on 23.07.2012 and a presentation was made by the BSEB indicating the deficiencies of the Non-financial bids of all the bidders namely GMR Kamalanga Energy Ltd, Essar Power Ltd and PTC India Ltd. It was also presented that the deficiencies were considered not very substantial by BSEB and the Board in its meeting held on 16.06.2011 resolved that the bidders may be asked to give the affidavit/undertaking before opening of the financial bid to the effect that they will comply with all the conditions of the nonfinancial bids within one year. In case the successful bidder/bidder with whom PPA is signed after the evaluation of the financial bid, are not able to comply with the conditions as stipulated in the RfP, their security/performance guarantee will be invoked/forfeited. 18 BSEB was directed to provide the following information/documents by 31st July 2012:(i) Copy of the resolution /decision of the Board dated 16.06.2011 (ii) Copy of the letter sent to the bidders in compliance of the Board’s decision/resolution asking them to furnish the required affidavit/undertaking. (iii) Copy of the affidavit/undertaking submitted by the bidders. (iv) The model blank Excel sheet provided to the bidders along with the RfP indicating the formula used for evaluation of bid and computation of levelised tariff. (v) The escalation rates and discount factor notified by CERC which has been used for the purpose of computation of levelised tariff and bid evaluation. In compliance of the direction of the Commission, the BSEB submitted vide letter no.1539 dated 06.08.2012 the following documents:(i) Copy of the letter sent to the bidders regarding submission of the affidavit for meeting the non- compliances before opening of the financial bids. (ii) Copy of the affidavit submitted by the bidder before opening of the financial bids. (iii) Copy of financial bids of the bidders. (iv) Copy of Board Resolution no.8608 for the Board meeting held on 16.06.2011. (v) Soft copy CD of the illustration sheet and the calculation sheets of the levelised tariff of bidders. 3.5 The matter was heard on 13.08.2012 and commission noted that the BSEB has submitted the required information vide letter no.1539 19 dated 06.08.2012 except the relevant CERC notification of the escalation rate and discount factor to be applied for evaluation of levelised tariff and BSEB was directed to submit the required notification of CERC. 3.6 The case was heard again on 11.09.2012 and in course of hearing the BSEB was directed to submit the following at least 3 days before the next date of hearing which was scheduled on 20.9.2012:(i) Copy of letter constituting Bid Evaluation committee with one external member (ii) Certificate of Bid Evaluation Committee and the procurer as per clause 6.2 of guidelines (iv) Paper cutting of RfP notice in two national newspapers as per 5.2 of the guidelines. (v) Atleast 45 days time period in case of single bid process for submission of bids after issue of RfP documents is provided in clause 5.5 of the guidelines. Date of uploading RfP documents mentioned as 22.02.2011, needs to be clarified. (vi) Copy of letter no.113 dated 14.01.2011 regarding intimation for procurement of 1050 MW. (vii) Copy of letter no.1319 dated 29.07.2011 seeking extension of time. 3.7 In compliance of order dated 11th September, 2012, BSEB submitted following documents : (i) A copy of the order of BSEB in its internal file constituting a committee of officers for opening of Non-financial and Financial bid for procurement of 1050 MW power under the process of case-1 along with copy of the internal order of BSEB in which Evaluation Committee has been reconstituted. 20 (ii) In compliance of clause 6.2 of the Competitive Bidding Guidelines, a copy of the certificate of Bid Evaluation Committee to the effect that the bid process evaluation has been done in accordance with the provision of RfP document. The procurer certificate on conformity of the bid process to the guidelines has also been submitted. (iii) Newspaper cuttings of two newspapers in which the bid inviting RfP was published, in compliance of clause 5.2 of the Competitive Bidding Guidelines. (iv) Copy of letter no. 113 dated 14.01.2011 intimating the Commission that BSEB has initiated process of procurement of 1050 MW ±20% power at delivery point through competitive bidding process under Case-1. (v) A copy of letter no. 1319 dated 29.07.2011 along with the petition to approve the deviation for extension of bid process completion time by another 46 days leading to entire bid process for a period of 236 days. 3.8 The matter was heard on 20.9.2012 when the commission acknowledged the documents/information submitted by BSEB and observed that there were some discrepancies in the papers submitted by BSEB in compliance of the order dated 11.09.2012. Moreover, some more clarifications were required on certain issues which are summarised below :(i) BSEB has submitted only a copy of order in the internal file committee for of BSEB opening regarding of the constitution Non-financial of and Financial bids. In addition BSEB has also submitted a copy of the order in the internal file of BSEB in which one Member of the Committee has been substituted. BSEB has not revealed past association with the external member, directly or through its affiliates - that 21 could create potential conflict of interest, as required under clause 5.9 of the Competitive Bidding Guidelines. The Board is also required to clarify whether any formal order constituting the Bid Evaluation Committee has been issued. (ii) As per clause Guidelines, 5.5 of the wherever Competitive Bidding revised bidding documents/amendments are issued, the procurer shall provide bidders at least forty-five (45) days in case of a single stage bidding process after issue of such documents for submission of bids. The BSEB uploaded RfP documents along with replies on 22.02.2011. Thus the bidders were not given 45 days for submission of bids. BSEB is required to clarify whether any modification/amendment in RfP was issued along with clarification. (iii) As per clause Guidelines, the 5.19 of procurer the Competitive may extend Bidding timeframe indicated in the Annexure-II. However, if the bidding process is likely to take more than 195 days, approval of the Appropriate Commission shall be obtained in accordance with the Clause 5.16 which requires that any deviation from these Guidelines shall be with the prior approval of the Appropriate Commission. In the present case the BSEB vide its petition dated 29.07.2011 prayed for extension of time only upto 12th September, 2011 i.e. for a total period of 236 days for completing the bid process but the last RfP document signed was with GMR on 09.11.2011. However the petition filed under Section 63 of the Act indicates that the total period of 294 days has been taken for 22 completion of the bid process for which no prior approval of the Commission was obtained. This lapse on the part of BSEB needs to be explained. (iv) As per Clause 4.11 (ii) of Competitive Bidding Guidelines, the ratio of minimum and maximum energy charges (including both the non-escalable component and escalable component incorporating escalation as per index being used for evaluation) over the term of PPA shall not be less than 0.5 to avoid excessive frontloading or backloading. However this ratio in case of the tariff quoted by M/s Essar Power Limited is less than 0.5 resulting in excessive backloading of tariff. (v) Two bidders with whom BSEB has signed PPA, do not fully meet the qualifying requirement mentioned in the RfP particularly in respect of availability of land and fuel. Deficiencies are as follows:(a) M/s GMR Kamalanga Energy Limited. Land requirement for the project is 1050 acres as per MOEF environment clearance and bidder is already in possession of 861.22 acres of land. Further lease for 138 acres of government land shall be executed shortly. The Bidder has not provided any document in support for balance 50.78 acres land. The bidder has submitted only a certificate from Owner's Engineer certifying that 999.22 acres of land is sufficient for the commissioning of the project. Normative fuel requirement for GMR Kamalange Energy Limited is 5.39 MMTPA and the bidder has a tie up of 4.52 MMTPA. Thus, there is a shortfall of 0.886 MMTPA. 23 Estimated requirement of water for the project is 37 Cusecs but the bidder has got water linkage of 30 Cusecs only. The bidder has a certificate from Owner's Engineer certifying sufficiency of water for operation of the project. (b) M/s Essar Power Limited Requirement of land for the project is 1210 acres. The bidder has indicated availability of only 760.84 acres of land. The bidder has clarified that the land requirement for the project has been reduced from 1210 acres to 750 acres with certain modification in some components of the project. The normative fuel requirement for the project is 6.06 MMTPA and the bidder has a tie up of 5.5 MMTPA leaving a shortfall of 0.56 MMTPA. The Board considered these deficiencies as minor and condoned approval from these the without taking prior Commission. The Board resolved that keeping in view the larger interest of the State the minor deficiencies are condoned and the bidders affidavit/documentary shall evidence/ submit confirmation before the opening of the financial bids to comply with the conditions imposed by the BSEB in the communications to the aforesaid bidders. In compliance of the Board's decision M/s GMR Kamalanga Energy Limited has given affidavit that it is in possession of 1038.625 acres of land. This land is sufficient for the power plant. It has 24 also given the affidavit that the coal requirement for the entire capacity has been tied up. M/s Essar Power Limited has given the affidavit that 750 acres of land is sufficient for the project. It has further given the affidavit confirming reserve of the coal block allotted to them are sufficient for 2x600 MW project. BSEB may submit the copy of study, if any, of Central Electricity Authority (CEA) regarding the requirement of land and fuel for such projects. Alternatively, comments of CEA on the requirement of land and fuel may be procured. A copy of the letter of allotment of coal blocks to M/s Essar Power Limited by the Ministry of Coal which may indicate whether M/s Essar Power Limited is authorised to extract more coal than indicated in the allotment order. (vi) BSEB may also indicate the status of commissioning of these projects. The Commission directed BSEB to submit the following:(i) Clarification on constitution of Bid Evaluation Committee as per para 3.8(i). (ii) Clarification on whether any modification/amendment in RfP was made and issued and if so minimum 45 day time was given for submitting bid as required in Clause 5.5 of the Guidelines. (iii) Clarification for not obtaining prior approval of the Commission for extension of time upto 294 days for completion of bid process as required under Clause 5.19 of the Guidelines. 25 (iv) Clarification regarding less than 0.5 ratio of minimum and maximum energy charges as required under Clause 4.11(ii) of the Guidelines (v) Clarification on giving relaxation in minimum qualifying requirement in non-financial bid without prior approval of the Commission. (vi) A copy of the coal block allotment order of Ministry of Coal to M/s Essar Power Limited indicating that they are authorised to extract more coal than stipulated in the allotment order/mining licence. (vii) Copy of norms/comments of CEA regarding requirement of land and fuel for such projects. (viii) Status of commissioning of the two projects. The aforesaid information was required to be submitted by 7th of October, 2012 and the matter was scheduled for hearing on 17.10.2012. 3.9 As scheduled, the matter was heard on 17.10.2012. BSEB was represented by Shri Rakesh, EEE (Inter-state). In compliance of order dated 20.09.2012, BSEB vide letter no. 2035 dated 17.10.2012 submitted the following :(i) Clarification on constitution of Bid Evaluation Committee. A certificate dated 17.10.2012 has been submitted by BSEB which certifies that Shri Hemant Kumar, Chief Manager, Rural Electrification Corporation, Patna was the external member of the Bid Evaluation Committee for evaluation of the bids for procurement of 1050 MW ±20% through tariff based competitive bidding under case-1. The Certificate also mentions that Shri Hemant Kumar has expertise in financial 26 matters/bid evaluation and BSEB does not have any past associations with him directly or through its affiliates which could create a potential conflict of interest in this bid evaluation process. Thus it is as per the provisions of clause 5.9 of the guidelines. (ii) Clarification on whether any modification / amendment in RfP was made and issued and if so minimum 45 days time was given for submitting bid as required in clause 5.5 of the guidelines It has been informed by BSEB that there was no modification / amendment in the RfP document and only responses / clarifications to the queries received from prospective bidders were furnished and uploaded on website. Since no revision of the bid documents/amendments were issued, provision of minimum 45 days time for submission of the bids thereafter is not applicable. (iii) Clarification for not obtaining prior approval of the Commission for extension of time upto 294 days for completion of bid process as required under clause 5.19 of the Guidelines. BSEB has mentioned that since the tentative date for signing of the RfP was not known to BSEB, a petition for approval of the period beyond 236 days was not filed. The RfP documents with Essar Power Limited and GMR Kamalanga Energy Limited were signed on 17.10.2011 and 9.11.2011 respectively. Earlier a petition dated 29.07.2011 praying extension of time upto 12th September, 2011 for a total period of 236 days was submitted by BSEB for completing the bid process. Since, the total time taken for completion of the bid 27 process is 294 days, approval for extension of time period beyond 195 days is required as per clause 5.19 of the Guidelines. (iv) Clarification regarding less than 0.5 ratio of minimum and maximum energy charges as required under clause 4.11(ii) of the Guidelines. The above provision is applicable where the procurer offers a captive fuel source (such as a captive coal mine) for concurrent development and production of power. In the present case, no captive fuel source has been offered by the procurer. This provision of the Guidelines is not applicable. (v) Clarification on giving relaxation in minimum qualifying requirement in non-financial bid without approval of the Commission BSEB has clarified that minimum qualifying requirement for the non-financial bid as mentioned in the RfP document were strictly as per the Standard Bid Document issued by Ministry of Power for procurement under Case-1 tariff based competitive bidding process for long term procurement. The Board of BSEB decided to approve the minor deficiencies and non compliances in a conscious and considered decision based on the following reasons:(a) The number of bidders/developers in the country is limited and mostly, these bidders participate in the bid processes carried out all over the country. In case the minor deficiencies and non compliances which have no impact on the project execution/plant operation are not relaxed in the above cases, then the participation of bidders at the financial bid evaluation stage shall be very limited which may deprive the state 28 from getting requisite quantum of power at reasonable tariff rates. (b) In case the Board decides to rebid due to requisite quantum of power, not materialising at the reasonable tariff, the capacity offered to the State in the present bid may get unlocked, and may be offered to other bidding States. In the process, the state may not get sufficient competitive bids against the fresh tender enquiry. (c) The projects from which power is offered are under advanced stages and the minor deficiencies and non compliances may not affect the commissioning of the projects/plant operation. A copy of Board resolution no. 8608 dated 16.06.2011 is enclosed as annexure-III (vi) The copies of coal block allotment order of Ministry of Coal for Chakla Coal block and Ashok karkata Central Coal block to M/s Essar Power Limited have been submitted as annexure-IV indicating mine capacity of 2.0 MMTPA and 3.5 MMTPA respectively. Approved mining plan / revised bank guarantee submitted may clarify rated mines capacity. BSEB has made a reference of clause 1(iv) of the coal block allotment order issued by Ministry of Coal in this respect. (vii) The copy of norms/comments of CEA regarding the requirement of land and fuel for such projects. BSEB has submitted in annexure (V) 'Review of land requirement for thermal power stations' issued by CEA in September, 2010. The report recommends 1090 acres of land 29 for 2x500MW pit head/load center, indigenous coal based project and 1520 acres for 2x660MW project. Earlier as per CEA report - 2007, the land requirement for above referred capacity had been 1420 acres and 2050 acres respectively. BSEB has submitted a copy of letter dated 21.04.2011 of Essar Power reducing land requirement from 1210 acres to 750 acres. A copy of letter dated 9th Feb. 2011 written to CEA by Essar Power Ltd. has also been enclosed by BSEB. Regarding fuel requirement, in case of Essar Power Limited, as per coal block allotment order, 5.5 MMTPA is the mines capacity of the two coal blocks against normative requirement of 6.06 MMTPA for the power plant. Approved mining plan/revised bank guarantee submitted may clarify the mines rated capacity. A copy of mines development schedule as per letter of allotment – status report as on 31.12.2010 indicate mines capacity of 4.5 MMTPA in each of the mines (Peak rated capacity) (viii) Status of commissioning of two projects. The commissioning schedule as per 'status of coal block allocated' submitted in respect of Essar Power limited indicates as under :Unit – I 600 MW - September, 2013 Unit – II 600 MW -January, 2014 Status of commissioning in case of GMR Kamalanga Energy Limited has not been submitted. The BSEB was directed to submit the following :- 30 (i) Approved mining plan for both coal blocks allotted to Essar Power and revised bank guarantee submitted by Essar Power Limited. (ii) Letter of approval/comments of CEA regarding reduction in land requirement from 1210 acres to 750 acres for the 2x600 MW power plant of Essar Power Ltd. 3.10. The matter was heard on 7.11.2012. In compliance of Commission’s order dated 17.10.2012, the petitioner Bihar State Power (Holding) Company Ltd. which is a successor company of erstwhile BSEB has submitted written response. The petitioner has not submitted the approval/comments of CEA regarding reduction in land requirement in the project. But it has submitted a report from M/S Essar power in which it has been mentioned that environment clearance given by Ministry of Environment and Forests stipulated that the land requirement will not exceed the limit of 1210 acres and that the mining plan of Chakla Coal Block has been approved by the Coal Controller, Ministry Coal in which annual coal production of 4.5 MMTPA has been approved. In the earlier submission, the petitioner submitted that M/s GMR kamalanga Energy Limited has replied that balance quantity of Coal will be procured through E-auction . In the meanwhile, petitioner is directed to submit a copy of the environment clearance given by the Ministry of Environment and Forests indicating the approval of land requirement not exceeding the limit of 1210 acres. The petitioner will also submit the latest progress report of the project of M/s Essar Power who will supply electricity to the petitioner. 31 The case was scheduled for orders on 27.11.2012. In compliance of the order dated 07.11.2012, the Bihar State Power (Holding) Company Limited, erstwhile BSEB vide letter no.2197 dated 12.11.2012 submitted the following: A.GMR Kamalanga Energy Ltd 1. Clarification from M/s GMR to the queries raised by BSEB, as submitted letter by them vide para-2 of the GMR dated21.04.2011,related with arrangement of balance coal (0.886 MMTPA) for the thermal project and affidavit of GMR on Coal tie up(Appendix-B) B. Essar Power Ltd 1. Letter F, no.3-13011/63/2008 IA.II(T) dated 8th May 2009 of MoEF, Govt.of India – Related with requirement of land under para 3(i). Further, the Bihar State Power(Holding) Company Limited, erstwhile BSEB vide letter no 2256 dated 22.11.2012 submitted a copy of Progress Report of Essar power Limited for the month of October 2012. A copy of Project Progress Report of M/s GMR kamalanga Energy Ltd for the month of September2012 has also been submitted on 26.11.2012. 4.0 Commission’s observation on procedure followed by BSEB and compliance of the Guidelines. The Commission observes that BSEB initiated single stage bidding process for procurement of 1050MW (± 20%) through tariff based competitive bidding for long term (25 years) under case-1 based on the guidelines and standard bid documents issued by Ministry of Power, Government of India without any deviation. The NIT was issued vide no.02/PR/BSEB/2011 on 32 14.01.2011. Eight nos. of bidders submitted their bids for varying capacities. The Bid Evaluation Committee constituted by BSEB with one external member evaluated the non-financial bids. As per the Bid Evaluation Committee report, only two bids met the qualifying requirement of the RfP and deficiencies and non-compliances were observed in case of other five bidders. One bid of M/s Shapoorji Pallonji Energy (Gujrat) Ltd failed to qualify. The Board of the BSEB in it’s 540th meeting held on 16.06.2011 approved opening of financial bids of seven bidders and passed following resolutions: “Resolved that keeping in view of the larger interest of the state the minor deficiencies and non-compliances to the qualifying requirement in the case of GMR Kamalanga Energy Ltd.; PTC India Ltd, Essar power Ltd, Reliance Power Ltd and National Energy Trading & services Ltd are hereby approved, with the condition that these bidders shall submit the sworn in affidavit/documentary evidence/confirmations before opening of the financial bids, to comply with the conditions imposed by BSEB in the communications to the aforesaid five bidders. These are pre-conditions to the opening of their financial bids. In case they do not meet the targets/conditions, the BSEB may terminate the PPA, invoking the provisions of PPA for encashing the contract performance guarantee provided by the developer@ Rs.30 lakhs per MW and initiate fresh bid process.” After submission affidavits by five bidders, financial bids of seven qualifying bidders were opened on 28.06.2011. During opening of financial bids, it was noted that the financial bid of GMR did not contain a part of the format, the envelope contained only the tariff sheet in the specified format of 4.10. At the instant, as per clause 2.2.2 of the RfP, the bid was not considered for evaluation. 33 GMR vide their letter dated 28.08.2011mentioned that the part of format 4.10 not submitted with financial bid had no financial implication and inadvertently, it was placed in the envelope along with non-financial bid. Considering the fact that it has no financial implication, the financial bid of GMR was considered for evaluation . It was found that the levelised tariff of bidder M/s Essar power Ltd offering 300MW was the lowest at Rs3.69 per kwh at delivery point of BSEB. The Board in it’s 541stBoard meeting dated 04.08.2011 gave approval to issue LoI to M/s Essar power Ltd and further suggested that the L2.L4,L6, L7and L8 may be offered an opportunity to give their counter-offers equal to the levelised tariff of L1 bidder and then the balance requisitioned contracted capacity may be split among the bidders who match the levelised tariff of L1 bidder. In response M/s GMR kamalanga Energy Ltd submitted it’s counter-offer and matched the levelised Tariff of L1. The PPA was signed with M/s Essar power Ltd on 17.10.2011 for 300 MW and with M/s GMR kamalanga Ltd on 09.11.2011 for 260 MW. 4.2 Having scrutinised the petition and chronology of different steps taken by the Petitioner BSEB since the initiation of bid process for procurement of power on tariff based competitive bidding in accordance with Competitive Bidding Guidelines, the submissions made by petitioner BSEB and additional information/documents submitted by BSEB, now the Commission proceeds to examine whether in accordance with section 63 of Act, the tariff has been determined by Petitioner BSEB for procurement of (i)300 MW of power from M/s Essar Power Limited(ii)260 MW of power from M/s GMR Kamalanga Energy Ltd through transparent process of bidding as per provisions of the Competitive Bidding Guidelines issued by the Central Government. 34 4.3 The Bihar State Electricity Board (hereinafter referred to as ‘BSEB’ or ‘Petitioner’) an autonomous body constituted under section 5 of Electricity Supply Act, 1948 duly formed by Govt. of Bihar under legislative decree vide Bihar Govt.’s notification no. 2884-A/A1121/57 dated 25th March, 1958 w.e.f. 1st April, 1958. BSEB is a deemed licensee as per section 14 of the Electricity Act, 2003 (hereinafter referred to as ‘Act’) and is an integrated utility engaged in the business of Generation, Transmission and Distribution of electricity in the State of Bihar. In terms of section 172 of the Act, the BSEB constituted under the repealed law shall be deemed to be the State Transmission Utility (STU) and a licensee under the provisions of the Act for a period of one year from 10th June, 2003 i.e. appointed date. On the request of Govt. of Bihar from time to time, Central Govt. has agreed to extend the time to continue the BSEB to function as an STU and distribution licensee and last extension granted to BSEB is up to 31.12.2012. 4.4 Section 63 of the Electricity Act, 2003 (the Act) states that – “Notwithstanding anything contained in section 62, the Appropriate Commission shall adopt the tariff if such tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government.” Ministry of Power, Govt. of India has issued guidelines for “determination of tariff by bidding process for procurement of power by distribution licensees” (Competitive Bidding Guidelines) vide resolution no. 23/11/2004-R&R (Vol.-II) dated 19th January, 2005 and amended the guidelines on 30.03.2006, 18.08.2006, 27.09.2007, 27.03.2009 and 21.07.2010. 35 4.5. These guidelines have been issued for long-term procurement of electricity for a period of seven years and above and medium term procurement for a period of up to seven years but exceeding one year. These guidelines are also applicable for procurement of electricity through competitive bidding in cases where the location, technology, or fuel is not specified by the procurer. In the present case in conformity with clause 2.1(a) of Competitive Bidding Guidelines the Petitioner BSEB which is the procurer has initiated the process for long-term procurement of electricity for a period of 25 years under Case-1 in which the location, technology or fuel has not been specified by the Petitioner for base load of 1050 MW (±20%) which is in conformity with clause 2.2(i) of the Guidelines. 4.6. As per clause 3.1(i) of the guidelines, the bid documents have to be prepared in accordance with these guidelines and the approval of the appropriate Regulatory Commission (BERC in the present case) is to be obtained unless the bid documents are as per the Standard Bid Documents issued by the Central Government. In such cases, an intimation shall be sent by the procurer to the Commission about initiation of the bid process. In the present case, the Commission vide it’s letter no.BERC.Misc1/08-250 dated 21.07.2009 has noted that BSEB intends to procure 1500 MW of power under case -1 standard bidding document based on guidelines issued by Ministry of Power, Govt. of India without any deviation . As per tariff order dated 06.12.2010 ( case no.TP-3 of 2010) for determination of ARR and retail tariff for the FY2010-11,the commission under directive 25(4), has directed BSEB to initiate bidding process for (1500 – 450)1050 MW of power. Earlier BSEB has signed PPA for 450 MW Power with Essar Power Ltd in 2010. The BSEB vide it’s letter no.113 dated 14.01.2011 has informed the Commission under provision of clause 3.1(i) of the guidelines about 36 the procurement of 1050 MW±20% power at delivery point through competitive bidding process under case -1. The commission has also informed BSEB vide it’s letter no.BERC/misc-1/08 (part)-36 dated 21.01.2011 that the Commission has no objection to the proposal of BSEB to go ahead for procurement of 1050 MW±20% power through competitive bidding under case-1. From the above, it is evident that the Petitioner complied with the provision of clause 3.1(i) of the Competitive Bidding Guidelines. 4.7. As per clause 3.1(iii)(a), approval of the Commission is to be sought before initiating the bidding process for the quantum of capacity/energy to be procured in case the same is exceeding the projected additional demand forecast for the next three years following the year of expected commencement of supply proposed to be procured. Such demand forecast shall be based on the latest available Electric Power Survey (EPS) published by the Central Electricity Authority. In the present case, the commencement of supply is expected after 4 years from the date of signing of the PPA i.e by FY2015-16. As per 18th Electric Power survey published by the Central Electricity Authority, the projected peak demand for state in 2012-13 will be 2642 MW which may go up to 5660 MW in 2017-18. The projection of requirement of energy for the FY2015 -16, 2016 -17and 2017-18 are 25489MU, 29447MU and 32964MU respectively. Whereas availability of power as per current Tariff Order for FY2012-13 is 14142 MU and the proposed procurement of additional 560MW would mean increased availability by 4169 MU per annum. Another 450 MW long term PPA signed with M/s Essar Power Ltd will fetch 3351 MU per annum. The total availability including the proposed procurement will be 21662 MU by FY2015-16. Thus, the proposed procurement of 560 MW will be well within the projection made by the 18th EPS. Therefore, 37 prior permission of the commission was not required as per clause 3.1(iii)(a) of the Competitive bidding Guidelines and only intimation was required to be given by the Petitioner. 4.8 The clause3.2(II) of the guidelines is applicable in case -1 procurement to ensure serious participation in the bid process and timely commencement of supply of power, the bidder, in case the supply is proposed from a station to be set up, should be required to submit along with it’s bid, documents in support of having undertaken specific actions for project preparatory activities in respect of matters relating to land ,fuel, water ,environmental clearance and forest clearance etc. In present case, there were deficiencies and non- compliances in case of five bidders . The Board of the BSEB accorded approval for opening of the financial bids after getting sworn in affidavits to comply fully with the qualification requirements as per the RfP. The issues relating to deficiencies have been examined in para 5.2.12 dealing with compliance of clause 5.11. 4.9 The clause 2.3 and 3.1(ii) states that approval of the Appropriate Commission shall be sought in the event of deviations from the bid conditions contained in these guidelines, following the process described in para 5.16 of the Guidelines. The deficiencies and non-compliances in the non-financial bids as mentioned above in para 4.8 have been examined in Para 5.2.12 dealing with compliances of clause 5.11 of the guidelines. Although, these minor deviations do not have any appreciable effect on competitiveness and transparency in bid process and in case, minor deficiencies which hardly have impact on the project execution/operation are not relaxed, the participation of bidders at financial evaluation stage shall be very limited and may deprive the 38 state of required quantum of power at reasonable and competitive tariff rates. However, BSEB should have taken prior approval of the Commission before opening of financial bids. 5.0 Compliance of clause 4(Tariff Structure) of the guidelines 5.1.1 In compliance of clause 4.1 of the guidelines, provision for monthly billing has been made in article 8.2 of the PPA and various parameters of multi-part tariff have been included in the format 4.10 for financial bids in the RfP. 5.1.2 In compliance of clause 4.3, para 8 of the notice inviting RfP provides that tariff shall be payable by the procurer in Indian rupee as per provisions of the PPA. The section 1.3.1.11 of RfP also provides that the transmission charges, for transmission of power from injection point to delivery point, will initially be paid by the seller and will be reimbursed by the procurer. 5.1.3 In compliance of clause 4.4 of the guidelines, the clause 2.4.1.1(B)(vii) of RfP provides that the quoted escalable capacity charges and quoted non-escalable capacity charges shall be based on normative availability . In case of availability being lower, the capacity charges shall be payable on proportionate basis as mentioned in 4.1(iv) of Schedule4 of the PPA 5.1.4 In compliance of clause 4.5, the clause 4.2.4 of schedule 4 of the PPA provides for incentive for availability higher than normative availability. The clause 4.2.5 of Schedule 4 of the PPA also provides for penalty in case availability during a year is less than 80%. 5.1.5 In compliance of clause 4.6 of the Guidelines, Schedule 3.1 of the PPA provides for scheduling, dispatch and grid code and article 4.5.3 of the PPA provides that the seller shall be entitled to sell such available capacity not scheduled by the procurer to any person without losing 39 the right to receive the capacity charges from the procurer for such unscheduled capacity. In such a case, the sale realization in excess of variable charges, shall be equally shared with the procurer. 5.1.6 The articles 10.1.1 and 10.2.1 of the PPA also provides in compliance of clause 4.7 of the guidelines that any change in tax or introduction of any tax made applicable for supply of power by the seller as per the terms of the agreement shall be passed on to the monthly tariff. 5.1.7 Clause 4.8 of the Guidelines is complied through appropriate provision in clause 2.4.1.1(B)(x) of RfP. 5.1.8 The provision of payment security mechanism as per clause 4.10 of the Guidelines has been included in article 8.4 of the PPA. 5.1.9 In compliance of clause 4.11, Section 2.4.1.1(B)(viii) &(ix) and format 4.10 of the RfP provides for option to the bidder to either quote firm capacity and energy charges or both non-escalable and escalable energy charges. 5.1.10 Clause 4.14 of the Guidelines has been complied in art. 4.4.1 and 4.3.1 of schedule 4 of the PPA regarding payable energy charges . 5.2 Compliance of clause 5 (Bidding Process) of the guidelines 5.2.1 As per clause 5.1 of the Competitive Bidding Guidelines, the procurer may, at his option, adopt a single stage tender process for long-term or medium term procurement under Case-1 combining the RfP and RfQ processes. Accordingly the Petitioner BSEB has adopted single stage tender process in the present case for procurement of 1050 MW±20% of power under Case-1 of the Competitive Bidding Guidelines on long-term basis for a period of 25 years. The BSEB issued a ‘Notice inviting tender ‘ no.02/PR/BSEB/2011 for procurement of 1050 MW(±20%)power under case-1 route based on the standard bidding document without any deviation. 40 5.2.2 As per clause 5.2 ,the procurer shall publish RfQ (RfP in single stage bid process)notice in at least two national newspapers, company website and preferably in trade magazines also to accord it wide publicity. The bidding shall necessarily be by way of International Competitive bidding .For the purpose of issue of RfQ (RfP in single stage process) minimum conditions to be met by the bidder shall be specified by the procurer in the notice. In compliance of clause 5.2 of the guidelines, petitioner BSEB published the RfP notice (international competitive bidding) in two national newspapers on 16.01.2011 and RfP was also uploaded on BSEB’s website and made available for downloads from 20.01.2011 to 03.02.2011. Clause 2.1 of the RfP specifies the qualification requirements which was based on standard bid documents issued by Ministry of Power. 5.2.3 As per clause5.3, Procurer shall provide only written interpretation of the tender document to any bidder/participant and the same shall be made available to all other bidders All parties shall rely solely on the written communication and acceptances from bidders. In compliance of clause 5.3 of the Guidelines, BSEB has mentioned to have provided only written interpretation of the tender document at all points of time during the bid process to all the bidders. 5.2.4 In compliance of clause 5.4(i), BSEB has specified 1050 MW as quantum of electricity proposed to be procured in clause1.3.1.2 of the RfP, the minimum bid capacity of 100 MW has been specified in clause 1.3.1.3 of the RfP. Clause 1.3.1.4 of the RfP specifies that proposal is for procurement of base load requirement and the period of contract has been specified as 25 years in clause 1.3.1.1. Further in compliance of clause 5.4(i), the normative availability has been specified as 85% in article 1.1 of the PPA signed with M/s Essar 41 Power Limited and M/s GMR kamalanga Energy Ltd. The Delivery Date has been specified in clause 1.3.1.5 of the RfP as 4 years from the date of signing of the PPA. BSEB has also specified in clause 1.3.1.8 of the RfP that the bidder shall provide the point of injection in its bid. The networh criteria to be fulfilled by all the bidders has been specified in clause 2.1.2.1 of the RfP. Thus, BSEB has complied with clause 5.4(i) of the guidelines. 5.2.5 In compliance of clause 5.4(iii) of the guidelines, clause 2.9 of the RfP specifies that period of validity of the bid is 120 days after the bid deadline. 5.2.6 In compliance of clause 5.4(vi) of the guidelines, BSEB has provided in clause 2.5(i) of the RfP for verification of financial data by checking with bidder’s, lender’s/banker’s/financing institutions/any other persons as necessary. 5.2.7 In compliance of clause 5.5 of the guidelines, the RfP documents, along with reply to queries raised by the bidders were uploaded on BSEB’s website on 22.02.2011, with 4th April, 2011 as the last date of submission of bids. As per guidelines, wherever revised bidding documents/amendments are issued, the procurer has to provide at least 45 days time in case of single stage bidding process for submission of bids .BSEB modification/amendment in has the clarified RfP that there documents was and no only responses/clarifications to the queries received from prospective bidders were furnished and uploaded on website on 22.02.2011and therefore, minimum period of 45 days time thereafter for submission of bids was not applicable. 5.2.8 In compliance of clause 5.6(v), BSEB has specified in the clause 1.3.1. 5 of the RfP that scheduled delivery date will be 4 years from the date of signing of RfP documents and as per provisions of art.4.1 of the 42 PPA. The liquidated damage that would apply in event of delay in supply is provided in art.4.8 of the PPA. 5.2.9 In compliance of clause 5.6(vi) of the guidelines, BSEB has mentioned that escalation rates notified by CERC to be utilised for bid evaluation purpose as per provision in clause no.3.4.4 of RfP. 5.2.10 In compliance of clause 5.7 of the guidelines, the number of qualified bidders after completion of evaluation of the non-financial bids were seven, out of which one bidder M/s PTC India Ltd, an inter-state trading licensee, offered power from four different generating stations and M/s NET&SL, an inter-state Trading licensee, offered power from three different generating stations. Hence, in all there were 12 price bids from different generating stations. 5.2.11 In compliance of clause 5.9 of the guidelines, the Bid Evaluation Committee constituted by BSEB included one external member Shri Hemant Kumar from Rural Electrification Corporation Ltd. As per guidelines, the external member shall have expertise in financial matters/bid evaluation. The procurer shall reveal past associations with external member directly or through it’s affiliates that could create potential conflict of interest. BSEB has submitted a certificate dated 17.10.2012 in compliance of the aforesaid provisions of the guide line. 5.2.12 In compliance of clause 5.11 of the Guidelines, Bid Evaluation Committee reported that only two bidders had fully complied with the stipulation in clause 2.1.2.2 of the RfP in respect of various project preparatory activities. However the Board of Petitioner BSEB vide its Resolution No. 8608 in the 540th Board meeting held on 16.06.2011 accorded approval for opening of financial bids of seven bidders with the condition that the five bidders, with minor deficiencies and non- 43 compliances, should submit sworn in affidavits to comply fully with qualifying requirement of the RfP . After verifying the submission to queries, affidavits and original documents of the bidders, the financial bids were opened on 28.06.2011. The Commission observes that prior approval of the Commission was required in respect of deviations from the qualification requirement of the RfP. 5.2.13 In compliance of clause 5.12 of the guidelines BSEB has reported that there was no deviations from the tender conditions in the price bid submitted by any bidder. 5.2.14 In compliance of clause 5.14(i) of the guidelines, BSEB has reported that in compliance of clause 3.4.5, 3.4.6, 3.4.7 and 3.4.8 of RfP, the bids submitted by bidders developing generating stations outside the state of Bihar were evaluated after loading with the applicable interstate transmission charges and making adjustments for transmission losses. 5.2.15 In compliance of clause 5.15 of the guidelines, the bidder who has quoted the lowest levelised tariff was declared successful bidder. Clause 3.5.2 of the RfP, also mentions that all financial bids of qualified bidders shall be ranked from lowest to the highest .BSEB declared Essar Power Ltd, the bidder, who has quoted the lowest levelised tariff as the ‘successful bidder’. The BSEB Board vide the resolution number 8619 in the 541st Board meeting held on 4.08.2011 gave approval to issue LOI to M/s Essar Power Ltd(L1) bidder for supply of 300 MW power at the quoted levelised tariff of Rs3.69 per kwh and further suggested that the L2,L4,L6,L7 may be offered an opportunity to give their counter-offers equal to the levelised tariff of L1 bidder. In response, M/s GMR 44 kamalanga energy Ltd submitted it’s counter offer and matched the levelised tariff of L1. 5.2.16 In compliance of clause 5.16 of the guidelines, BSEB has reported that the Case-1 bid process was initiated without any deviation from the guidelines. 5.2.17 In compliance of clause 5.19 of the guidelines, The BSEB has mentioned that the last date for submission of bid was 04.04.2011, while the date of issue of RfP was 14.01.2011, thus allowing more than 75 days for submission of the bid. Further, the Case-1 bid process was completed with the signing of the RfP on 09.11.2011 with GMR Kamalanga Energy Ltd. BSEB has further reported that the bid process and signing of the RfP documents completed in 294 days i.e 99 days more than the maximum allowed time period of 195 days as per guidelines. It has been clarified that since the tentative date for signing of RfP documents were not known, the petitioner BSEB had earlier submitted an application vide letter no.1319 dated 29.7.2011 for approval of extension of time for anticipated total period of 236 days to complete the bidding process. 5.3 Compliance of clause 6 of guidelines 5.3.1 The clause 6.2 of the guidelines stipulates that after the completion of bid process , the Bid Evaluation Committee shall give a certificate on conformity of the bid process evaluation according to the provisions of RfP document and the procurer shall provide a certificate on conformity of the bid process to these guidelines. The certificate given by the Bid evaluation committee was not in conformity with the guidelines. In course of hearing on 11.09.2012, BSEB was directed to furnish the required certificates of the bid evaluation committee and 45 the procurer as per provisions of the guidelines . The certificates of Bid Evaluation Committee and the procurer, submitted by BSEB on 20.09.2012 , are in conformity with the guidelines. 5.3.2 In compliance of the clause 6.3 of the guidelines, the BSEB issued press note in daily newspapers informing the public about signing of the PPA and other RfP documents, accessibility to download the signed PPA and other RfP documents from its website. The information about the name of the successful bidder and details of tariff quoted by all the bidders were also given, keeping all other bidders anonymous. 5.3.3 In compliance of clause 6.4 of the Guidelines, BSEB has submitted the petition along with the signed PPA and certification/certificates provided by the Evaluation Committee and by the procurer as provided in clause6.2 of the guidelines. 6.0 Commission findings and views 6.1.1 The Bid Evaluation Committee constituted by BSEB in accordance with the provisions of clause 5.9 of the Guidelines included one external member Shri Hemant Kumar, Chief Manager, Rural Electrification Corporation, Patna. The Bid Evaluation Committee in its report on the evaluation of non-financial bids observed that there were infirmities in the non-financial bids of six bidders with respect to provision of RfP. The committee mentioned that two bidders met the qualifying requirement strictly as per the RfP document namely:(i) India bulls Power Ltd (ii) Jaypee power ventures Ltd. Further, there were minor deficiencies and non-compliances of the qualifying requirement as set out in the RfP document in case of the following five bidders:(a) GMR Kamalanga Energy Ltd (b) PTC India Ltd (c) 46 Essar Power Ltd (d) Reliance Power Ltd (e) National energy trading & services Ltd The report further mentions that the bid of M/s shapoorji Pallonji Energy (Gujrat) pvt. Ltd does not meet the qualification requirements as per RfP document. 6.1.2 The matter was placed before the Board of Petitioner BSEB. The deficiencies and non-compliances in respect of qualification requirements as per clause 2.1.2.2 of the RfP regarding availability of land, fuel, water and forest/environment clearance, etc. were considered and the Board approved opening of the financial bids in it’s 540th Board meeting held on 16.06.2011and passed the following resolution:“Resolved that keeping in view of the larger interest of the state the minor deficiencies and non-compliances of the qualifying requirement in the case of GMR Kamalanga Energy Ltd.; PTC India Ltd, Essar power Ltd, Reliance Power Ltd and National Energy Trading & services Ltd are hereby approved, with the condition that these bidders shall submit the sworn in affidavit/documentary evidence/confirmations before opening of the financial bids, to comply with the conditions imposed by BSEB in the communications to the aforesaid five bidders. These are pre-conditions to the opening of their financial bids. targets/conditions, In case they the BSEB do not may terminate meet the the PPA, invoking the provisions of PPA for encashing the contract performance guarantee provided by the developer@ Rs.30 lakhs per MW and initiate fresh bid process.” 47 6.1.3 The two bidders with whom BSEB has signed PPA do not fully meet the qualification requirement mentioned in the RfP. The deficiencies, as per non-financial bid evaluation report, are as follows:i. GMR Kamalanga Energy Ltd: Land requirement for the Project is 1050 acres as per MOEF environmental clearance and the bidder is already in possession of 861.22 acres of land. Further lease for 138 acres of government land shall be executed shortly. The bidder has not provided any document in support of balance 50.78 acres of land. The fuel requirement is 5.39 MMTPA and the bidder has tied up for 4.52 MMTPA. Thus, there is a shortfall of 0.886 MMTPA..The available water linkage is also less by 7cusec.Against estimated requirement of 37 cusec, water availability is for 30 cusec. ii Essar Power Ltd:- The requirement of land for the project is 1210 acres whereas bidder has indicated availability of only 760.84 acres of land. They have clarified that the land requirement for the project has been reduced from 1210 acres to 750 acres by modifications in the switchyard, colony, cooling and ash disposal systems besides shifting coal crushing system to the captive coal mines area. The fuel requirement for the project is 6.06 MMTPA and the bidder has indicated availability of 5.5MMTPA leaving a short fall of 0.56 MMTPA. The Commission observes that the BSEB should have taken prior permission of the Commission before opening of their financial bids. 6.1.4 In compliance of the Board's decision M/s GMR Kamalanga Energy Limited has given affidavit that it is in possession of 1038.625 acres of land. This land is sufficient for the power plant. It has also given the affidavit that the coal requirement for the entire capacity has been tied up. Against Coal linkage available with them for 4.52 MMTPA, 48 reassessed coal requirement at normative availability is 4.62 MMTPA. The above has been detailed in coal computation sheet of appendix-B, letter dated 21.04.2011 of M/s GMR kamalanga Energy Limited. M/s Essar Power Limited has given the affidavit that 750 acres of land is sufficient for the project. It has further given the affidavit confirming reserve of the coal blocks allotted to them are sufficient for 2x600 MW project. As per annexure-v of letter no. 2035 dated 17.10.2012 submitted by BSEB in compliance of order of the Commission dated 25.09.2012,’Review of land requirement for thermal power stations’ issued by CEA in September 2010 recommends 1090 acres of land for 2x500MW pit head/load center, indigenous coal based project and 1520 acres for 2x660 MW project .Earlier it was 1420 acres and 2050 acres respectively .Thus the land requirement has been reduced by 23% and 26% respectively for the above mentioned capacity by the CEA. As directed by the Commission in course of hearing on 7.11.2012,the BSEB has submitted a copy of environment clearance accorded to M/s Essar Power Ltd dated 8th May 2009 which mentions that total land requirement for 2x600 MW proposed project shall not exceed 1210 acres. The petitioner has submitted a copy of letter dated 5.11.2012 from M/s Essar power Ltd mentioning major factors leading to reduced land requirement of 750 acres only as detailed below:(i) Use of Gas insulated substation (ii) Use of air cooled condenser instead of conventional cooling system (iii) Plan for multi-storied building for colony (iv) Use of High concentration slurry disposal system for ash 49 (v) Coal crushing and storage facility shifted to captive coal mines area. As annex.-VI of letter no.2035 dated 17.10.2012, BSEB has submitted a copy of letter dated 21.4.2011 of Essar power Ltd indicating sectionwise details of reduction in land requirement. A copy of letter ref.no.Tori/phase-1/CEA/001 dated 9.02.2011 written to CEA by the developer has also been enclosed by BSEB as annex.-1 mentioning reduction in land requirement from 1210 acres to 750 acres .They have also mentioned that 760 acres of land has been acquired by them. Regarding status of Coal blocks ,the copy of approved Mining Plan for Chakla coal block of Essar Power Ltd submitted by BSEB as annexure-2 indicate targeted coal production of 4.5 MMTPA. The copy of Status report as on 31.09.2012 for Ashok Karkata coal block submitted to Coal controller ,MOC, Govt.of India mentions 4.5 MMTPA as coal production. A copy of Coal block allotment order dated 6th November 2007 by Ministry of Coal ,Govt of India has also been enclosed wherein assessed mine capacity of 3.5 MMTPA by CMPDIL has been mentioned. The mines capacity of both Chakla and Ashok Karkata blocks are sufficient to meet the requirement of 2x600 MW project has been mentioned in the affidavit submitted by M/s Essar Power limited . As mentioned in the financial bids, the expected date of commissioning for Essar Power is in 2014 and for GMR ,it is in the middle of 2012. The copy of progress report of Essar power Limited for the month of October 2012, submitted on 22.2.2012 by BSEB, mentions date of synchronization in 2014.In case of GMR Kamalanga Energy Limited ,the copy of Project Progress Report for the month of September 2012 50 mentions commissioning of Unit-1 by December 2012 and other units are scheduled to follow by 2 months and 4 months respectively. 6.2 As per para 5.15 of the Guidelines, the Bid evaluation committee shall have right to reject all price bids if rates quoted are not aligned to the prevailing market price. It is provided in art.3.5.12 of the RfP also. In the present case, a glance over the tariff rates submitted by BSEB in annex-1,letter no.994 dated 23.05.2012 indicate that during 2009 to 2011 in case of long term power procurement ( case -1),the power procurement rates varied between Rs2.35 to Rs. 4.08 per kwh in other states of the country. The petitioner has also furnished the average power purchase cost from NTPC power stations in Eastern Region for the months of June & July 2011.The mentioned cost are Rs.4.26 and Rs4.10 per unit respectively. The indicative tariff based on March 2012 fuel cost for Farakka-III STPS of NTPC, as per copy of letter dated 23.04.2012 submitted by BSEB, is Rs4.50 per kwh. In the discussion note of 541st Board meeting of the BSEB dated 4.08.2011, para 8, it has been mentioned that present average landed rate of supply of power by NTPC to the state under central sector allocation is Rs.4.53 per unit. In May2010, when 450 MW power was tied up with M/s Essar power Ltd at the levelised tariff of Rs.3.057 per kwh, the average rate of power supply by CPSU was Rs2.46 per kwh .In the present case, L1 rate of Rs.3.69 per kwh is from the same power station of M/s Essar power Ltd. In short span of 14 months there have been a steep rise in the power supply rates. However, the average rates of power supply to the state from Farakka, Kahalgaon and Talchar stations of NTPC submitted by BSEB as per directive of the Commission on 17.10.2012 for FY2011-12 and 51 FY2012-13(till September 2012) are Rs3.22 per unit and Rs.3.33 per unit respectively. 6.3 BSEB after signing of the PPA has made the PPA public through advertisement in the newspapers. The PPA and other signed RfP documents were also placed on the website of the BSEB. The information about the name of the successful bidder and details of tariff quoted by all the bidders were also given, keeping all other bidders anonymous. 7.0 Conclusion: The Commission observes that the petitioner issued “Notice Inviting Tender” NIT no.02/PR/BSEB/2011 on 14.01.2011 for procurement of 1050MW±20% power through tariff based competitive bidding for long term procurement under case-1, based on the guidelines and Standard Bid Document issued by Ministry of Power ,Govt. of India without any deviation. The Commission further observes that as per Bid Evaluation Committee report, only two bids fully met the qualification requirement of the RfP and minor deficiencies and non-compliances were observed in case of other five bidders in the non –financial bids. However, the Board of BSEB in their 540th Board meeting vide resolution no. 8608 accorded approval for opening of financial bids of seven bidders with the condition that five bidders with minor deficiencies should submit affidavits to comply with qualifying requirement of the RfP. After submission of required affidavits by these five bidders, the financial bids of seven bidders were opened. These minor deviations do not have any appreciable effect on competitiveness and transparency in bid process and in case ,minor deficiencies and non-compliances which hardly have impact on the 52 project execution/operation are not relaxed, the participation of bidders at financial bid evaluation stage shall be very limited and may deprive the state of required quantum of power at reasonable and competitive tariff rates. With the experience of case -1bidding, it is also noted that entire bidding process takes more than 180 days. In case fresh bid is invited, it will take another 180 days to finalise the bid process without any certainty of tariff which may be arrived. As per details submitted by the licensee, the commission observes that in the states like UP and Karnataka, the tariff approved in 2010/2011 for long term power procurement under case -1 bid process have been higher than the tariff of Rs3.69/kwh offered by M/s Essar power Limited and GMR kamlanga Energy Limited in the present case. In UP tariff of Rs4.08/kwh has been approved in case of Noida power and in Karnatka approved tariff rates were Rs3.77/kwh and Rs3.89/kwh. Thus, the Commission is of the view that the tariff arrived by BSEB after following the bid process in accordance with the guidelines is quite competitive and reasonable compared to prevailing scenario of availability and rate of power in the market. The Petitioner has followed a transparent process in procurement of this power on tariff based competitive bidding. Therefore, the commission adopts the levelised tariff of Rs.3.69/kwh and also the year- wise tariff for which PPAs has been signed for procurement of 560 MW of Power to meet its base load requirement for a period of 25 years . 53 In Case No.7/2012,BSEB(now substituted by BSPHCL),has submitted a proposal for approval and adoption of tariff for procurement of additional 75MW base load power offered by Essar Power Limited on long term basis on the same terms and conditions as agreed in PPA executed on 17.10.2012 at levelised tariff of Rs.3.69/kwh. The Commission will issue order separately in that Case no.7/2012. Sd/(K.P.singh) Member Sd/(S. C. Jha) Member 54 Sd/(U.N. Panjiar) Chairman