NJ MI PA PJM DC IL KY MD DE NC OH IN TN VA WV

advertisement
State RTEP Overview
PJM
DE
DC
IL
IN
4.7: New Jersey RTEP Overview
KY
MD
MI
NJ
NC
OH
PA
TN
VA
Section
4
WV
MAP 4.26: PJM Service Area in New Jersey
PJM operates the electric transmission system for
the delivery area served by several Transmission
Owners in New Jersey: Atlantic Electric (AE),
Jersey Central Power & Light (JCPL, a subsidiary
of FE/GPU), Public Service Electric & Gas
Company (PSEG) and Rockland Electric Company
(Rockland) as shown on MAP 4.26. The Neptune
Regional Transmission System interconnects with
the transmission system in New Jersey at
Sayreville substation. The transmission system in
New Jersey delivers power to customers from
native generation and from power imported from
adjacent systems west and south. New Jersey also
exports power to New York and wheels energy
from upstate New York to New York City.
Critical RTEP Issues and Upgrades
Since 2003, a number of factors have continued
collectively and progressively to reduce system
reliability in eastern Mid-Atlantic PJM:
• Load growth
• Power exports to New York City and Long
Island over merchant transmission facilities
• Deactivation/retirement of generation resources
• Sluggish development of new generating
facilities
• Continued reliance on transmission to meet
load deliverability requirements and to obtain
access to more economical sources of power
west of the Delaware River.
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
221
Section
4
State RTEP Overview
TABLE 4.26: Critical Issues in New Jersey
222
RTEP Topic
Report Sections
Importance to New Jersey
Wind and other renewables
2.2.3, 2.2.4,
4.7.6
Potential for wind and other renewable
generating resources in the state
Susquehanna - Lackawanna Jefferson - Roseland 500 kV Line
3.1, 3.2, 3.5.5,
3.9
Alleviating constrained power transfers, the result of
deliverability based NERC criteria violation overload(s)
beginning in 2015
Amos - Bedington - Kemptown
765 & 500 kV Line
3.1, 3.3, 3.5.5,
3.7.5, 3.8.5, 3.9
Alleviating constrained power transfers, the result of
deliverability based NERC criteria violation overload(s)
beginning in 2012
Mid-Atlantic Power Pathway
(MAPP) Transmission Line
3.1, 3.4, 3.5.5,
3.8.5
Alleviating constrained power transfers, the result of
deliverability based NERC criteria violation overload(s)
beginning in 2012
Load Growth Trends
2.1, 4.0.2, 5.1
10-year forecasted peak power demand for
TO zones within state
Generator Deactivations
2.3, 3.5.2
Impact of generation removed from the system, the result of
requested deactivation.
Generator Interconnection Plans
2.2, 3.5.3, 4.7.2
New sources of electric power for the state.
Merchant Transmission
Interconnection Plans
2.4, 3.5.4
Impact of merchant transmission projects on the state.
Additional Reliability Issues and
Approved Upgrades
3.5.6
Alleviating TO zone-specific baseline reliability violations
within the state.
Additional Backbone Facilities
Under Consideration
3.10
Ongoing assessment of need for new backbone transmission
facilities.
Improvements to PJM RTEP
Process
5.0, 5.1
Market Efficiency studies, cost allocation,
queue process, RPM
RTEP Extrinsic factors
5.0, 5.2
FERC Order 890, NERC/RFC, NIETC corridor, environmental
public policy
PJM 2007 Regional Transmission Expansion Plan
PJM © 2008
Present trends indicate that reliability criteria
violations will continue to be identified in New
Jersey and other areas of eastern Mid-Atlantic PJM
where similar conditions exist.
TABLE 4.26 summarizes key critical issues
facing New Jersey discussed in this report.
State RTEP Overview
4.7.1 – Load Growth and Existing
Generation
Exports by Merchant Transmission
Exports to New York have the impact of new load
in New Jersey. Merchant transmission projects
either in service or currently active in the
interconnection queue for the purpose of delivering
capacity and energy from New Jersey to New York
include:
• The Neptune HVDC project (685 MW)
• The Linden VFT project (330 MW)
• The Bergen O66 project (670 MW)
• The Bergen Q75 project (1200 MW)
As a result of these facilities, the impact of
internal New Jersey load growth is compounded by
the stresses on the transmission system of
4
FIGURE 4.14: Existing Installed Capacity in New Jersey, by Fuel Type
Natural Gas - 6,731 MW
Nuclear - 3,984 MW
Internal Load Growth
Native New Jersey load is served over the
transmission systems of the Transmission Owners
operating in New Jersey: AE, JCPL, PSEG and
Rockland. The load growth forecasts for the
geographic area served by Transmission Owners
are shown in TABLE 4.1 in Section 4.0.2. The
summer peak load growth rate for these four zones
ranges from 0.5% to 2.0% annually over the 10year period through 2017.
Forecasted loads are modeled in power flow
studies used to develop PJM’s RTEP through
December 2007. PJM’s RTEP includes baseline
transmission upgrades in New Jersey to meet
expected 2012 peak load conditions. Beyond 2012,
additional transmission system expansion will be
needed to meet expected peak load supply
requirements.
Section
Kerosene - 2,598 MW
Coal - 2,061.9 MW
Other - Gas - 19 MW
Other - Solid - 104 MW
Oil - 366 MW
Hydro - 405 MW
Distillate Oil - 540.5 MW
potentially having to accommodate more than
2,800 MW of planned exports of power from
eastern PJM to New York City and Long Island and
energy wheeled from upstate New York to New
York City. About one-quarter of that amount –
685 MW - began in July 2007 with the commercial
operation of the Neptune project.
Existing Generating Capability
FIGURE 4.14 provides a snapshot of the existing
installed capacity by fuel type in the TO zones that
serve New Jersey.
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
223
Section
4
State RTEP Overview
4.7.2 – Generator Interconnection Requests
PJM has received interconnection requests for
nearly 150 new generating resources proposed for
installation in New Jersey since 1999, summarized
in the table below.
Queue
Project Name
B19
Melrose 34.5 kV
G20
Essex
H17
Salem 500 kV
MW
MWC
Status
Schedule
TO
Fuel Type
20
20
IS-NC
4/6/2001
JCPL
Natural Gas
6
6
IS-NC
6/1/2003
PSEG
Natural Gas
115
115
ISP
6/1/2008
PSEG
Nuclear
MW
# of Projects
H18
Hope Creek 500 kV
78
78
ISP
12/1/2007
PSEG
Nuclear
4,170
38
H19
Hope Creek 500 kV
43
43
UC
12/1/2007
PSEG
Nuclear
541
6
J05
Huron 69 kV
8
8
ISP
7/30/2003
AEC
Natural Gas
8,845
38
K04
Camden 26 kV
5
ISP
6/30/2005
PSEG
Methane
Withdrawn
23,243
67
N27
Pequest River 34.5 kV
4
4
IS-NC
7/1/2006
JCPL
Methane
O11
Bustelton 13 kV
7.125
7.1
IS-NC
6/1/2007
PSEG
Methane
TOTAL
36,799
149
O20
Lakehurst 34.5 kV
10
9.6
IS-NC
12/31/2006
JCPL
Methane
P06
Cumberland 230 kV
366
225
ACTIVE
12/31/2008
AEC
Natural Gas
P23
Bayonne 138 kV
46
45.5
ACTIVE
6/1/2007
PSEG
Natural Gas
Q08
Red Oak 230 kV
50
50
ACTIVE
6/1/2008
JCPL
Natural Gas
Q11
Red Oak 230 kV
300
300
ACTIVE
6/1/2008
JCPL
Natural Gas
Q22
Columbia 34.5 kV
0.5
0.5
UC
12/26/2006
JCPL
Hydro
Q41
Mt. Hope Mine 34.5 kV
ACTIVE
1/1/2008
JCPL
Biomass
Q74
Linden 230 kV
600
600
ACTIVE
6/1/2009
PSEG
Oil
Q76
Quinton 12 kV
2
2
ACTIVE
11/1/2008
AEC
Methane
Q86
Hudson - Essex 230 kV
455.1
455.1
ACTIVE
5/31/2009
PSEG
Natural Gas
Q90
Mickleton 230 kV
650
650
ACTIVE
6/1/2012
AEC
Coal
R11
South River 230 kV
611
611
ACTIVE
6/30/2009
JCPL
Natural Gas
R23
Lakewood 230 kV
20
20
ACTIVE
1/1/2007
JCPL
Natural Gas
R39
Red Oak 230 kV
300
300
ACTIVE
8/1/2009
JCPL
Natural Gas
R58
Gloucester 230 kV
55
55
ACTIVE
6/1/2008
PSEG
Natural Gas
R66
Fair Lawn 138 kV
67
67
ACTIVE
3/1/2007
PSEG
Natural Gas
R74
Carlls Corner
4.8
4.8
ACTIVE
6/1/2008
AEC
Methane
R91
Columbus-NJ
0.37
0
ACTIVE
6/1/2007
PSEG
Methane
S25
Parlin 230 kV
114
114
ACTIVE
7/1/2007
JCPL
Natural Gas
S43
Vineland
17
17
ACTIVE
6/1/2008
AEC
Oil
In-Service
Under Construction
Active
TABLE 4.27 includes generating resource
interconnection requests located in New Jersey.
PJM received these requests during the windows
of time associated with Queues A through T (as of
December 31, 2007). The generator
interconnection projects in this table are either
under construction or active in PJM’s
interconnection process. Section 2.2 of this report
describes how generation interconnection requests
are modeled in RTEP studies.
For this report, generating resources that are
fully in-service (designated “IS”) are included in the
summary tabulation above but are NOT separately
enumerated in TABLE 4.27.
A status code of “IS-NC” (in-service, no
capacity) indicates a generator that is in-service for
energy only. Such units have not requested
consideration for capacity status.
A status code of “ISP” (in-service, partial)
denotes a generating resource that is only partially
in-service and has not reached full capacity status.
224
TABLE 4.27: Queued Generator Interconnection Requests in New Jersey
PJM 2007 Regional Transmission Expansion Plan
PJM © 2008
30
State RTEP Overview
Section
4
TABLE 4.27: Queued Generator Interconnection Requests in New Jersey (Continued).
Queue
Project Name
MW
MWC
Status
Schedule
TO
Fuel Type
S60
Essex 26 kV
63
63
ACTIVE
6/1/2008
PSEG
Natural Gas
S61
Tosco 230 kV
20
20
ACTIVE
7/1/2007
PSEG
Natural Gas
S121
Vineland 69 kV
63
63
ACTIVE
7/1/2008
AEC
Natural Gas
S122
Churchtown – Cumberland 230 kV
478
478
ACTIVE
11/1/2009
AEC
Natural Gas
T41
Kearny 230 or 138 kV
275
275
ACTIVE
6/1/2010
PSEG
Natural Gas
T42
Kearny 230 or 138 kV
138
138
ACTIVE
6/1/2011
PSEG
Natural Gas
T43
Essex 230 kV
205
205
ACTIVE
6/1/2010
PSEG
Natural Gas
T44
Essex 230 kV
205
205
ACTIVE
6/1/2011
PSEG
Natural Gas
T45
Hudson 230 kV
205
205
ACTIVE
6/1/2011
PSEG
Natural Gas
T54
Cumberland 138 kV
9.4
9.4
ACTIVE
4/1/2009
AEC
Natural Gas
T55
Sherman Ave
12.4
12.4
ACTIVE
4/1/2009
AEC
Natural Gas
T57
Middle
22.2
22.2
ACTIVE
4/1/2009
AEC
Oil
T59
Mickleton
14.4
14.4
ACTIVE
4/1/2009
AEC
Natural Gas
T60
Missouri Ave
10.5
10.5
ACTIVE
4/1/2009
AEC
Oil
T61
Cedar
8.3
8.3
ACTIVE
4/1/2009
AEC
Oil
T63
Carlls Corner
27.2
27.2
ACTIVE
4/1/2009
AEC
Natural Gas
T75
South River 230 kV
20
20
ACTIVE
9/25/2007
JCPL
Natural Gas
T76
South River 230 kV
40
40
ACTIVE
6/15/2009
JCPL
Natural Gas
T77
Linden 230 kV
64
64
ACTIVE
10/4/2007
PSEG
Natural Gas
T81
Cedar 230 kV
350
70
ACTIVE
12/31/2012
AEC
Wind
T82
Cardiff 230 kV
350
70
ACTIVE
12/31/2012
AEC
Wind
T83
Merion 138 kV
350
70
ACTIVE
12/31/2012
AEC
Wind
T84
Corson 138 kV
350
70
ACTIVE
12/31/2012
AEC
Wind
T98
South Mahwah 69 kV
6
6
ACTIVE
10/29/2007
RE
Natural Gas
T107
Essex 230 kV
675
675
ACTIVE
1/31/2012
PSEG
Natural Gas
T119
Sewaren 230 kV
600
600
ACTIVE
1/1/2011
PSEG
Natural Gas
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
225
Section
4
State RTEP Overview
FIGURE 4.15: Queued Capacity by Fuel Type in New Jersey
A generating unit is ineligible for full capacity
status until all transmission upgrades needed to
ensure deliverability are completed. Only then will
PJM grant capacity status designation.
FIGURE 4.15 shows the capacity rights
requested, by fuel type, for generator
interconnection requests in Queues A through T
located in New Jersey and in-service (as of
December 31, 2007), under construction or active
in PJM’s interconnection process.
MAP 4.27 and MAP 4.28 show the locations of
each queued request in TABLE 4.27 for northern
New Jersey and southern New Jersey,
respectively.
Oil, 658 MW
Wind, 1,407.5 MW
Natural Gas, 10,428.3 MW
Diesel, 8 MW
Methane, 43.4 MW
Nuclear, 331 MW
Biomass, 30 MW
Hydro, 0.5 MW
Coal, 650 MW
226
PJM 2007 Regional Transmission Expansion Plan
PJM © 2008
State RTEP Overview
Section
4
MAP 4.27: Queued Generation Interconnection Requests in Northern New Jersey
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
227
Section
4
State RTEP Overview
MAP 4.28: Queued Generation Interconnection Requests in Southern New Jersey
228
PJM 2007 Regional Transmission Expansion Plan
PJM © 2008
State RTEP Overview
4.7.3 – Anticipated Generation Deactivations
Known generator deactivations in New Jersey
between October 2003 and December 2007 are
summarized in TABLE 4.28 and shown in MAP
4.29. The absence of these units has a quantifiable
impact on baseline reliability in New Jersey,
compounded by forecasted summer peak load
growth and sluggish new generation development.
Major transmission upgrades required to address
baseline reliability issues driven by these
deactivations are summarized in Section 4.7.5
together with other known baseline reliability
transmission needs. In addition, Section 3.5.2 of
this report addressed generator deactivation not
only in New Jersey but throughout the rest of
eastern Mid-Atlantic PJM as well. Neither New
Jersey, nor any state within PJM, acts in isolation.
Understanding system conditions throughout
eastern Mid-Atlantic PJM in particular is key to
understanding impacts on New Jersey itself. Thus,
while this report provides results in Section 4 on a
state-by-state basis, RTEP analysis is based on
the aggregate requirements of the entire PJM
system.
NOTE
PSEG indicated in July 2007, that Hudson Unit #2,
originally considered for deactivation as late as
November 2006, will remain operational.
Accordingly, PSEG has withdrawn its deactivation
request.
Section
4
TABLE 4.28: Generation Deactivations in New Jersey
Capacity
(MW) Status
Retirement Date
Generator
TO
Oct-03
Hudson 3 CT
PS
129
No Reliability Issues
Feb-04
Sayreville 4
JC
114
Reliability Issues Identified and Resolved
Feb-04
Sayreville 5
JC
115
Reliability Issues Identified and Resolved
Apr-04
Burlington 101-104
PS
208
No Reliability Issues
Apr-04
Burlington 105
PS
52
No Reliability Issues
Jun-04
Sherman VCLP
AE
46.6
No Reliability Issues
Jan-05
Riegel Paper NUG
(Milford Power LP)
JC
27
No Reliability Issues
May-05
Deepwater CT A
AE
19
Reliability Issue resolved (Blackstart)
Jun-05
Kearny 7
PS
150
Reliability issue identified and resolved
Jun-05
Kearny 8
PS
150
Reliability issue identified and resolved
Jun-05
Howard M. Down
(Vineland) Unit 7
AE
8
No Reliability Issues
Oct-05
DSM (Hoffman LaRoche)
JC
9
No Reliability Issues
Oct-05
Newark Boxboard
PS
52
Reliability issue identified and expected to
be resolved by 6/2007
May-06
Bayonne CT1
PS
21
No Reliability Issues
May-06
Bayonne CT2
PS
21
No Reliability Issues
Sep-10
Hudson 1
PS
383
Deactivated 1/9/2006,
Reactivated for
6/1/2007
Prime Energy (Marcal)
PS
47
No Reliability Issues
Deactivated 4/10/2006,
Reactivated for
6/1/2008
Parlin
JC
114
No Reliability Issues
Deactivated 6/1/2006,
Reactivated for
6/1/2008
Howard M. Down
(Vineland) Unit 9
AE
17
No Reliability Issues
Deferred
Glen Gardner 1&5
JC
40
Reliability Issue - Blackstart
Deferred
Gilbert 1&4 CTs JC
50
Reliability Issue - Blackstart
PJM © 2008
Reliability Issues Identified - Unit retained
through summer 2010
PJM 2007 Regional Transmission Expansion Plan
229
Section
4
State RTEP Overview
TABLE 4.28: Generation Deactivations in New Jersey, Cont.
230
Generator
Withdrawn
Gilbert 2 & 3 CTs JC
48
No Reliability Issues
Withdrawn
Glen Gardner 2-4, 6-8 CTs
JC
120
No Reliability Issues
Withdrawn
Werner 1-4 CTs
JC
212
No Reliability Issues
Withdrawn
Hudson 2
PS
608
Reliability Issues Identified
Withdrawn
B L England 1
AE
129
Reliability Issues Identified and expected
to be resolved by 12/2007
Withdrawn
B L England 2
AE
155
Reliability Issues Identified and expected
to be resolved by 12/2007
Withdrawn
B L England 3
AE
155
Reliability Issues Identified and expected
to be resolved by 12/2007
Withdrawn
B L England IC1-IC4
AE
8
Reliability Issues Identified and expected
to be resolved by 12/2007
Withdrawn
Sewaren 1
PS
104
Reliability Issues Identified - Unit retained
through summer 2008
Withdrawn
Sewaren 2
PS
118
Reliability Issues Identified - Unit retained
through summer 2008
Withdrawn
Sewaren 3
PS
107
Reliability Issues Identified - Unit retained
through summer 2008
Withdrawn
Sewaren 4
PS
124
Reliability Issues Identified - Unit retained
through summer 2008
PJM 2007 Regional Transmission Expansion Plan
TO
Capacity
(MW) Status
Retirement Date
PJM © 2008
State RTEP Overview
Section
4
MAP 4.29: Generation Deactivations in New Jersey
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
231
Section
4
State RTEP Overview
4.7.4 – Merchant Transmission
Interconnection Requests
Merchant transmission interconnection requests
queued in PJM that include a terminal in New
Jersey are shown in TABLE 4.29 and shown on
MAP 4.30.
PJM’s RTEP, representing plans completed and
approved by the PJM Board through December
2007 currently only encompasses the upgrades
required to accommodate the Linden VFT and
Bergen HVDC merchant transmission
interconnection requests.
• The Linden VFT project (G22_MTX5) will
connect PSEG’s 230 kV transmission system in
the Linden area with ConEd’s Goethals 345 kV
substation on Staten Island. The project, under
construction, will consist of three variable
frequency transformers and permit 330 MW
of firm transmission withdrawal rights. A 4th
quarter 2009 in-service date is currently
anticipated.
• The Bergen HVDC (O66) project (Hudson
Transmission Project) proposal would
interconnect PSEG and New York City, from
PSEG’s Bergen 230 kV substation in northern
New Jersey to Consolidated Edison’s W. 49th
Street 345 kV substation. Firm Transmission
Withdrawal Rights of 670 MW are requested. A
late 2010 in-service date is currently
anticipated. If constructed, the facility will
withdraw 670 MWs of firm energy from Bergen
station in northern New Jersey. A facilities study
was underway as of December 31, 2007.
System Impact study results have revealed that
the 670 MW withdrawal of power at Bergen
would introduce almost two dozen overloads,
requiring $450 million of network upgrades
232
PJM 2007 Regional Transmission Expansion Plan
TABLE 4.29: Merchant Transmission Interconnection Request Activity in New Jersey
Queue
Project Name
MW
Status
Schedule
TO
Project Type
G22_MTX5
Linden 230 kV
300
UC
3/31/2009
PSEG
VFT
O66
Bergen 230 kV
670
ACTIVE
7/1/2009
PSEG
DC
Q75
Bergen 230 kV
1,200
ACTIVE
6/1/2010
PSEG
S68
Sayreville 230 kV
660
ACTIVE
12/31/2007
JCPL
S104
Linden 230 kV
200
ACTIVE
6/1/2011
PSEG
DC
throughout the PSEG, JCPL, METEd,
PENELEC, PPL, PEPCo and Dominion TO
zones. Half of these overloads would be
expected to occur prior to 2015.
• PJM’s queue also includes two additional
merchant transmission requests – S68 and
S104 – which are in the Feasibility Study phase
of PJM’s RTEP interconnection process.
In addition, the following merchant transmission
projects are also under development:
Additional discussion of the impact of merchant
transmission interconnection requests on eastern
Mid-Atlantic PJM can be found in Section 3.5.4.
• The Bergen 230 kV project at queue position
Q75 – would include an AC circuit with Phase
Angle Regulator control. PJM has completed a
Feasibility Study with a requested 1,200 MW
firm withdrawal from Bergen. The study
revealed the need for over 1,200 reinforcements
in New Jersey and other areas of PJM caused
by reliability criteria violations. While specific
individual fixes for each of the individual
overloaded facilities have not been fully
determined, based upon the extent of the
upgrades required, PJM estimates that $500
million or more of network upgrades will be
required. Detailed system reinforcements are
being identified and estimated in the System
Impact Study for this project.
PJM © 2008
NOTE
The System Impact Study for Project Q75 was
issued on February 12, 2008, identifying the need
for over $1.1 billion of network upgrades to permit
interconnection of this project.
State RTEP Overview
Section
4
MAP 4.30: Merchant Transmission Interconnection Requests in New Jersey
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
233
Section
4
State RTEP Overview
4.7.5 – Transmission Expansion Plans in
New Jersey
TABLE 4.30 summarizes new RTEP planned
transmission upgrades for New Jersey as
approved by the PJM Board during 2007. MAP
4.31 shows the location of upgrades enumerated in
TABLE 4.30.
System reliability trends that have emerged in
New Jersey, and throughout eastern PJM, over the
past ten years constitute a classic system planning
study:
• Growing native load
• Deactivation/reactivation of existing generation
resources
• Sluggish development of new generating
resources
• Continued reliance on transmission to meet
load deliverability requirements and access to
cheaper sources of power from west of New
Jersey
• Exports to New York
Together, these collectively have a growing
negative impact on sustained system reliability
in New Jersey and throughout eastern MidAtlantic PJM.
The extent to which eastern Mid-Atlantic PJM
continues to rely on transfers into the area to meet
load-serving needs also has a quantifiable,
negative impact on the high voltage backbone
transmission system west and southwest of
New Jersey.
234
PJM 2007 Regional Transmission Expansion Plan
Three new major backbone transmission
facilities have been approved by the PJM Board in
2007 to resolve growing reliability criteria violations
in eastern Mid-Atlantic PJM and west/central
Pennsylvania, upgrades that are now part of PJM’s
RTEP:
• Susquehanna – Lackawanna – Jefferson –
Roseland 500 kV circuit
• Amos – Bedington – Kemptown 765 & 500 kV
circuit
• Possum Point – Calvert Cliffs – Indian River –
Salem 500 kV Circuit; Mid-Atlantic Power
Pathway (MAPP)
These are discussed in Section 3.5.5.
Transmission Upgrades Approved Prior to 2007
Transmission expansion upgrades approved by the
PJM Board prior to 2007 are summarized in TABLE
4.31 and MAP 4.32. Additional discussion of these
upgrades can be found in the February 27, 2007
“PJM Regional Transmission Expansion Plan”
which can be found online at: http://www.pjm.com/
planning/reg-trans-exp-plan.html.
A complete listing of all system reinforcements
approved by the PJM Board can be found online
at: http://www.pjm.com/planning/project-queues/
upgrade-projects.html.
PJM © 2008
State RTEP Overview
Section
4
TABLE 4.30: New Major Transmission Upgrade Plans in New Jersey – Approved During 2007
Increase the emergency rating of Saddle Brook - Athenia
230 kV by 25% by adding forced cooling
2
Supplemental
Upgrade
Transmission
Service
TO – Local Issue
Long-term Firm
Transmission Service
PSEG
NJ
▲
June 2012
$ 606 M
PSEG
NJ
▲
November
2008
$ 17 M
PSEG
NJ
O66
June 2009
$ 75 M
PSEG
NJ
O66
June 2009
$ 12 M
PSEG
NJ
O66
June 2009
$ 15 M
PSEG
NJ
O66
June 2009
$ 20 M
PSEG
NJ
O66
June 2009
$ 25 M
PSEG
NJ
▲
Branchburg – Flagtown 230 kV Line
Somerville – Flagtown 230 kV line
Newton – Montville 230 kV line
Upgrade 230 kV PSEG side of the circuit
8
Merchant Transmission
Interconnection
Network
Upgrades
$ 25 M
Upgrade 230kV with 2x1033 ACSS (5.25 mi)
7
States
June 2012
Upgrade 230kV with 2x1033 ACSS (4 mi)
6
TO Zones
Kittatinny – Newton 230 kV line
Upgrade 230 kV of PSEG side with double 1033 ACSS
conductors
5
Cost
Chichester – Mickleton 230 kV
Loop the 5021 circuit into New Freedom 500 kV substation
4
▲
Date / Status
Deliverability and other reliability criteria violations in 15 year analysisConstruct a Susquehanna - Roseland 500 kV circuit
(PSEG equipment)
3
Generation
Interconnection
Saddle Brook – Athenia 230 kV
Generator
Deactivation
1
Operational
Performance
Limiting Facility / Upgrade Description
Congestion Relief –
Economic
MAP
Ref.
Baseline Load Growth/
Deliverability & Reliability
Baseline
Upgrades
System Upgrade Drivers
Athenia – Saddlebrook 230 kV line
New 230 kV Parallel Circuit
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
235
Section
4
State RTEP Overview
TABLE 4.30: New Major Transmission Upgrade Plans in New Jersey – Approved During 2007
New 230 kV Parallel Circuit
10
Supplemental
Upgrade
Transmission
Service
TO – Local Issue
Long-term Firm
Transmission Service
Network
Upgrades
Merchant Transmission
Interconnection
June 2009
$ 15 M
PSEG
NJ
O66
June 2009
$ 30 M
PSEG
NJ
O66
June 2009
$ 25 M
PSEG
NJ
O66
June 2009
$ 12 M
PSEG
NJ
O66
June 2009
$ 10 M
PSEG
NJ
O66
June 2009
$ 14.35 M
PSEG
NJ
O66
June 2009
$ 125 M
PSEG
NJ
Roseland – Kearny 230 kV line
Convert the 138 kV “D” circuit from Roseland to Kearny to
230 kV and terminate the circuit at Roseland 230 kV and
Hudson 230 kV substations
236
O66
Hudson 230 kV substation
230 kV substation
15
States
Readington – Roseland 230 kV line
Upgrade 230 kV
14
TO Zones
Montville – Roseland 230 kV line
Upgrade 230 kV (8 mi
13
Cost
Maywood – New Milford 230 kV line
New 230 kV Parallel circuit
12
Date / Status
New Milford – Leonia 230 kV line
New 230 kV Parallel circuit
11
Generation
Interconnection
Saddlebrook – Maywood 230 kV line
Generator
Deactivation
9
Operational
Performance
Limiting Facility / Upgrade Description
Congestion Relief –
Economic
MAP
Ref.
Baseline Load Growth/
Deliverability & Reliability
Baseline
Upgrades
System Upgrade Drivers
PJM 2007 Regional Transmission Expansion Plan
PJM © 2008
State RTEP Overview
Section
4
MAP 4.31: Major Transmission Upgrades in New Jersey Approved During 2007
The right-of-way route shown on this map is for illustrative purposes only and may not depict the actual route that may eventually be chosen. Substation locations
may also be modified if a more beneficial connection is determined by PJM.
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
237
Section
4
State RTEP Overview
MAP 4.32: Transmission Upgrades in New Jersey Approved prior to 12/31/06
238
PJM 2007 Regional Transmission Expansion Plan
PJM © 2008
State RTEP Overview
Section
4
TABLE 4.31: Existing Major Transmission Upgrade Plans in New Jersey – Approved Prior to 12/31/06
3
Supplemental
Upgrade
Transmission
Service
Long-term Firm
Transmission Service
States
▲
June 2008
$ 25 M
PSEG
NJ
Dennis, Install Dennis 230/138 kV, Dennis 150 MVAR
SVC and 50 MVAR capacitor
▲
March 2008
$ 27.45 M
AEC
NJ
Install a new 500/230 kV substation in AE area, the high
side will be tapped on the Salem – East Windsor 500 kV
circuit and the low side will be tapped on the Churchtown
– Cumberland 230 kV circuit.
▲
December
2008
$ 52.09 M
AEC
NJ
▲
June 2009
$ 29 M
PSEG
NJ
▲
June 2009
$ 17 M
PSEG
NJ
▲
June 2008
$ 12 M
PSEG
NJ
▲
June 2008
$ 20 M
JCPL
NJ
AE Transmission Voltage Circuits
Metuchen 230/138 kV Transformer
Branchburg – Flagtown 230 kV
Flagtown – Somerville – Bridgewater 230 kV circuit
Reconductor the Flagtown – Somerville – Bridgewater
230 kV circuit with 1590 ACSS
6
TO – Local Issue
TO Zones
Build a new 230 kV section from Branchburg – Flagtown
and move the Flagtown – Somerville 230 kV circuit to the
new section
5
Merchant Transmission
Interconnection
Cost
Install 230/138 kV transformer at Metuchen substation
4
Network
Upgrades
Date / Status
Convert the Bergen – Leonia 138 kV circuit to
230 kV circuit.
2
Generation
Interconnection
Bergen – Leonia Circuit
Generator
Deactivation
1
Operational
Performance
Limiting Facility / Upgrade Description
Congestion Relief –
Economic
MAP
Ref.
Baseline Load Growth/
Deliverability & Reliability
Baseline
Upgrades
System Upgrade Drivers
Portland – Greystone 230 kV Circuit
Upgrade the Portland – Greystone 230 kV circuit
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
239
Section
4
State RTEP Overview
TABLE 4.31: Existing Major Transmission Upgrade Plans in New Jersey – Approved Prior to 12/31/06, Cont.
Replace both 230/138 kV transformers at Roseland
8
Supplemental
Upgrade
Transmission
Service
TO – Local Issue
Long-term Firm
Transmission Service
Network
Upgrades
Merchant Transmission
Interconnection
Cost
TO Zones
States
▲
June 2009
$ 15 M
PSEG
NJ
▲
June 2010
$ 35 M
JCPL
NJ
▲
June 2011
$ 20 M
PSEG
NJ
Kittatinny – Newton 230 kV
Reconductor the PSEG portion of Kittatinny – Newton 230
kV circuit w/ 1590 ACSS
240
Date / Status
Voltage Drop Problems in JCPL and PSEG
Install 600 MVAR Dynamic Reactive Device in the
Whippany 230 kV vicinity
9
Generation
Interconnection
Roseland 230/138 kV Transformer #4
Generator
Deactivation
7
Operational
Performance
Limiting Facility / Upgrade Description
Congestion Relief –
Economic
MAP
Ref.
Baseline Load Growth/
Deliverability & Reliability
Baseline
Upgrades
System Upgrade Drivers
PJM 2007 Regional Transmission Expansion Plan
PJM © 2008
State RTEP Overview
4.7.6 – Interconnection Requests for
Generation Powered by Renewable Fuel
Sources
PJM’s RTEP process offers a structure that
assures consistent, equal opportunity across fuel
types while flexible enough to adapt to specific
technical realities and market challenges.
Presently, PJM’s queues include interconnection
requests in New Jersey for plants fueled by wind,
hydro, biomass and methane, as summarized in
TABLE 4.32 and shown on MAP 4.33.
While some renewable resources can operate
in a manner similar to the traditional fossil fueled
power plants, other renewable energy sources,
such as wind, are recognized as intermittent
resources. Their ability to generate power is
directly determined by the immediate availability
and/or magnitude of their specific “fuel.” For
example, wind turbines can generate electricity
only when wind speed is within a range consistent
with the physical specifications of the related
turbines. This presents challenges with respect to
real-time operational dispatch and specific capacity
value. To address the latter issue, PJM has
established a set of business rules unique to
intermittent resources that provide for the
determination of credible capacity values robust
enough to represent capacity during the PJM
summer peak period.
Section
4
TABLE 4.32: Interconnection Requests by Renewable Fuel Type in New Jersey
Queue
Project Name
MW
K04
Camden 26 kV
5
Q22
Columbia 34.5 kV
Q41
Mt. Hope Mine 34.5 kV
Q76
Quinton 12 kV
R74
0.5
MWC
0.5
30
Status
Schedule
TO
Fuel Type
ISP
6/30/2005
PSEG
Methane
UC
12/26/2006
JCPL
Hydro
ACTIVE
1/1/2008
JCPL
Biomass
2
2
ACTIVE
11/1/2008
AEC
Methane
Carlls Corner
4.8
4.8
ACTIVE
6/1/2008
AEC
Methane
R91
Columbus-NJ
0.37
0
ACTIVE
6/1/2007
PSEG
Methane
T81
Cedar 230 kV
350
70
ACTIVE
12/31/2012
AEC
Wind
T82
Cardiff 230 kV
350
70
ACTIVE
12/31/2012
AEC
Wind
T83
Merion 138 kV
350
70
ACTIVE
12/31/2012
AEC
Wind
T84
Corson 138 kV
350
70
ACTIVE
12/31/2012
AEC
Wind
NOTE
As a matter of internal RTO process and
accounting, hydro plants are not categorized as
renewable resources. However, PJM understands
that some states account for hydro as a renewable
and, thus, to facilitate state understanding of such
activity, hydro is enumerated here merely for
reporting purposes.
PJM © 2008
PJM 2007 Regional Transmission Expansion Plan
241
Section
4
State RTEP Overview
MAP 4.33: Interconnection Requests by Renewable Fuel Type
242
PJM 2007 Regional Transmission Expansion Plan
PJM © 2008
Download