Regional Projects Showcase

advertisement
DEMOLITION | CIVIL ENGINEERING | CONCRETE STRUCTURES | BUILDING | ENVIRONMENTAL SOLUTIONS
Sector & Retail
England
Wales
Case Studies
Case Studies
Sector
Project
Residential & Regeneration /
Residential Apartments
Kensington High Street
Project Overview
Scudder was appointed by St Edwards Homes to demolish 375 Kensington High Street
(Charles House). The former Inland Revenue offices stood at 10 storey high, plus
basements, with a footprint of 50,000sqm. The site is bounded by Kensington High Street
with a prestigious London hotel opposite, smart residential streets and a main railway
line. Success of the demolition works was such that the Carey Group where then awarded
further works drawing on the expertise of both our both Civil Engineering and Concrete
Structures divisions. The demolition phase of the project was shortlisted in the Specialist
Awards 2012.
Services
Project Details
Client
St. Edward Homes a joint venture
between Berkeley Homes and The
Prudential
Location
London, England
Gallery
Principal Contractor
St. Edward Homes
Engineer / Consultant / PQS
Manhire Associates / St. Edward
Homes
More Information
The demolition of the building required meticulous planning, and involved different
demolition techniques for each section of the building. 80% of the exterior of the
building was encased with monarflex sheeted independent access scaffold, reducing
dust and noise transmission. The rear of the building was left clear, allowing long reach
remote demolition machines to demolish two of the rear wings and the central spine.
The remaining wings (adjacent to the railway and public highways), were simultaneously
demolished, top down, using 7 tonne demolition spec machines fitted with pulverisers. In
order to remove the basement, a pressed sheet pile retaining wall system was installed
tight to the boundary, during the demolition phase. Vibration monitoring with audible
and visual early warning alarms, was installed to ensure the gas and water mains were
safeguarded at all times.
Due to the close proximity of live railway lines, much of the work required close liaison
with Network Rail, carefully planning and communicating site activities in advance to
ensure smooth progress.
With the successful completion of Phase 1, Careys was awarded the second phase of
works.
Case Studies
Sector
Project
Hotel, Art & Leisure / Leisure
The British Museum
Project Overview
Careys scope of works is for the construction of the reinforced concrete substructure for
the World Conservation and Exhibitions Centre at the British Museum. The sub-structure
is approximately 18m deep and has 5 levels with a sub floor providing space for lift pits
and motor rooms. The site is located within the bounds of the existing British Museum
complex. The works area is bound by retained buildings on 3 fronts making the site a
very challenging footprint to work on. Prevention of damage to the existing building and
exhibits within meant that noise and vibrations were monitored and minimised.
Services
Project Details
Client
British Museum
Location
London, England
Principal Contractor
Mace
Gallery
Engineer / Consultant / PQS
Ramboll UK / Davis Langdon
More Information
The British Museum is a world leader in the conservation and display of objects from
across the globe. To ensure it can continue and grow its important role through the
twenty-first century it has taken the opportunity to expand into this new building which
has been created to provide a light finish of specially-produced glass and traditional stone
to sit well and blend with its grade I listed surroundings.
The new Centre will provide:
• dedicated gallery for special exhibitions • conservation and science facilities
• a collections’ management hub • world-class stores for the study collection
Although we have managed noise and vibration issues on many of our sites we recognise
that the concern on this project is such that a higher degree of understanding is required
and have therefore employed the services of a specialist, SENSONICS, to assist us with
the development of our elimination, management and monitoring strategy.
Case Studies
Sector
Project
Retail / Shopping Centres
Bull Ring, Spiceal Street
Services
Project Overview
Careys was contracted to Design and Construct the redevelopment of St Martin’s Square
and Spiceal Street, which includes; the construction of three new retail units, the
extension of two existing units, reconfiguration of open space, and the provision of new
public realm hard and soft landscaping works and features.
The main contracts works included; demolition, piling, structural steelwork, concrete,
structural alterations to existing building, concrete remedial works, and waterproofing,
shell and core. The Bullring is already a major attraction in Birmingham, with the addition
of the Spiceal Street development extending the availability of amenities into the evening.
Project Details
Client
Bullring Ltd Partnership
Location
Birmingham, England
Principal Contractor
Gallery
More Information
This 20,000sqft development is set around St Martin’s Square and was designed by
Chapman Taylor. The architectural design for Spiceal Street includes a striking ‘ribbon
concept’ curved roof linking the three new retail units, formal and informal seating areas,
a feature green wall and a new water feature as part of the improved public realm.
The existing steps linking Central Street to St. Martin’s Square have been relocated to the
east and reoriented towards the Church. The third new unit is situated at the pedestrian
entrance from Park Street, building on the existing stepped access to the first floor of
Selfridges.
PJ Carey (Contrators) Ltd
Case Studies
Sector
Project
Energy, Power & Waste / Waste Facilities
Seneca Materials Recovery Facility
Project Overview
Seneca; Carey’s Environmental Solutions business, received planning permission in
September 2010 to convert a disused distribution centre on a 6.5 hectare site in Brent,
into a ‘super’ Materials Recovery Facility (MRF), with a licence to handle up to 1.1m
tonnes of mixed waste. Careys Building Division oversaw the 32-week turnkey contract.
Works included upgrading the site’s infrastructure, refurbishing the 128,000m2 industrial
building and installing the specialist material separation plant and equipment. The
existing building was extensively refurbished and achieved a BREEAM Excellent standard.
Services
Project Details
Client
Seneca Environmental Solutions Ltd.
Location
Wembley, England
Gallery
Principal Contractor
P.J. Carey (Contractors) Ltd
More Information
The Seneca site’s access and perimeter road was modified to suit the revised traffic
management requirements of the facility, with a digitised weighbridge system installed
to record the weight and origin of each delivered load. Additional pedestrian and cycling
access was also constructed, together with car parking for 50 vehicles.
The refurbished building gained BREEAM excellence standards, with an integrated greywater harvesting system installed. 5m high in-situ reinforced concrete retaining walls
were cast to create material storage and segregation areas. The elevated 40m long
picking line area is adjoined by high quality staff welfare facilities. Eight designated
material collection bays sit below the picking line,
allowing operatives to manually select and divert different material types into collection
bays via metal hoppers, located adjacent to the picking line conveyor belt.
A series of flip-flow screens were installed to separate out varying sizes of fines, with
large magnets to takeout the metal rich items. Once materials have been separated out,
they are bailed and stored ready to dispatch for reprocessing or remanufacturing.
The facility also benefits from a rail siding which spans the full length of the 175m long
site; with two parallel lines running both inside and outside. The rail siding is scheduled
to go live early in 2012.
Case Studies
Sector
Project
Hotel, Art & Leisure / Leisure
The Hippodrome Casino
Project Overview
Careys was appointed as Principal Contractor to carry out the enabling, demolition and
associated shell and core works of the Hippodrome Casino, a Grade II listed building.
The scope of works consists of; demolition, underpinning, excavation, piling structural
steelworks, concrete and structural alterations to the existing building, concrete remedial
works and waterproofing. T.E. Scudder Ltd were appointed as demolition specialist for
all demolition, temporary works design and installation, façade retention and associated
works.
Services
Project Details
Client
United Gaming Leisure
Location
London
Principal Contractor
P.J. Carey (Contractors) Ltd.
Gallery
Engineer / Consultant / PQS
Alan Baxter / Box Associates
More Information
The works that were carried out to the Grade II listed building included an external
detailed façade retention scheme to an existing low rise infill building enabling complete
demolition down to basement of the attached building, internal bracing to the North
West Staircase which allowed the required demolition works to be carried out and various
demolition of walls, slabs and staircases to the main auditorium area which also required
a temporary propping design which would withstand the loadings.
One of the West Ends most popular landmark buildings, the Hippodrome was once known
for its variety performances then was renovated into one of the West Ends most popular
nightclubs. Now the site has been restored back to its former glory and transformed into
The Hippodrome Casino.
Case Studies
Sector
Project
Commercial / Business Park
Chiswick Park
Services
Project Overview
Careys Civil Engineering division was contracted to carry out a “face-lifting” hard
landscaping design at Chiswick Park. The project also included the construction of a
service yard and laying the surface in the event square, installation of street furniture,
Addagrip and Europave. The paving finishes were completed to a high specification.
Latterly Careys were awarded contracts for sub and superstructures on Building 6 within
the site, works comprised of 9 storeys above ground, accommodating office space and a
below ground level car park.
Project Details
Client
Stanhope Plc
Location
London, England
Gallery
Principal Contractor
Bovis Lend Lease
Engineer / Consultant / PQS
Arup / Davis Langdon
More Information
In phase 1 Careys scope of works was varied and included; hard landscaping around
the building and the installation of precast copping units, conservation slabs, kerbs and
precast step units. Block paving was laid in the under croft for internal parking and a
tarmac surface for the external parking area was added with the footpath laid with resin
bonded gravel using Addagrip.
An earth reinforced retaining wall and service yard were also constructed as part of the
works. Part of the surface of the Square was laid with a red tarmac (Europave) with white
lines then stencilled on it to create the event space for basketball and other sports. In the
Event Square, precast concrete benches and steps units were constructed. These works
had been carried out to such a high level of quality and care that Careys were latterly
awarded a further commission by the client on the same site.
Careys Concrete Structures division oversaw the building of the post-tensioned (PT)
concrete slab in the office areas and a reinforced concrete slab in the core area for
Building 6. The building benefits from a central insitu concrete core which acts as
a cantilever from undercroft level and provides the lateral stability for the building.
Horizontal loads from the façade are transferred through the floor plate back to the core
and then down through the walls to the foundations.
Case Studies
Sector
Project
Commercial / Mixed Use
27 Regent Street
Services
Project Overview
27 Regent Street is a grade II listed building in the heart of London’s West End. The
scope of Scudder works involved part demolition and part refurbishment to provide new
residential and retail units. The first stage of demolition involved the removal of internal
two-storey masonry and concrete extension. Following demolition, openings were created
and new structural steel work installed to support them. The second stage involved
the demolition of an existing stair core (extending over 6 floors) and removal of the lift
shaft, including car, guides and rails. The final stages of works were in the basement and
ground floors.
Project Details
Client
Crown Estate
Location
London, England
Gallery
More Information
The removal of the stair core involved significant temporary works designed by the
Scudder team. The stair core was them demolished floor by floor using a Brokk 90
remotely controlled demolition machine. Formation of new service void openings was
made through slabs on all six floors, with new steels installed to support these openings.
The basement and ground floors required temporary works; providing propping in the
basement with the removal of walls and insertion of steel box frames to create new
spaces along with the waterproofing of the existing basement retail spaces. A secure
ATM room was built on the ground floor which involved removal of glass partitions and
structural slab alterations.
Case Studies
Sector
Project
Retail / Food & General
Sainsbury’s
Services
Project Overview
Careys are proud to have worked in partnership with Sainbury’s since 1989 on
commissions throughout the UK and Ireland. Our relationship initially developed
through our demolition business; Scudder, which carried out projects to such a high
standard Careys were invited to tender for main works packages. The continued
success of project delivery led to Careys being awarded the design and build/
extension contract for Sainsbury petrol stations, and we have now become a
first tier contractor on the nationwide capital car park and drainage maintenance
package.
Project Details
Client
Sainsbury’s Supermarkets Plc
Location
Various
Principal Contractor
Gallery
Various
Engineer / Consultant / PQS
Various
More Information
In 1989 we embarked on our 1st major project at London Colney, this external works
package proved to be a shining example of Careys commitment to delivery, almost
halving the programme from 37 weeks to 20 weeks.
As the hypermarket format became more mainstream, other stores were developed
across England, with Careys playing an ever larger role in each project. In 1995
Careys received the first commission to carry out substructure and external
works at a flagship store in Hamilton, Scotland. This was quickly followed by a
rollout programme of stores across the country with Careys undertaking various
commissions.
The larger store format has proliferated since the late 1990s, and Careys has
completed in excess of 200 UK contracts, delivering infrastructure, drainage,
landscaping, roadworks and the construction of superstructures.
Case Studies
Sector
Project
Retail / Food & General
Tesco
Services
Project Overview
Both Scudder and PJ Careys have worked on Tesco sites which have been of varying size
and complexity. Projects have included demolition and civil engineering works such as;
enabling works, substructures, external works, concrete slabs, drainage, carparks, hard
landscaping and section 278 works. Careys has regularly received commissions to work
across England on the roll out, redevelopment and refurbishment of Tesco stores since
1999. We have now completed over 32 commissions across 18 sites and are continuing to
strengthen the partnership with numerous project awards taking place in the last 3 years.
Project Details
Client
Tesco
Location
Various
Principal Contractor
Gallery
Various
Engineer / Consultant / PQS
Various
More Information
A particuarly complex project the Tesco and Careys teams were involved in was the
development of a new store and housing in Seaton. The site was previously a holiday
camp and was low lying with a planning requirement being that the site footprint must be
raised. A scheme was devised to raise the levels with imported dredged materials that
were pumped ashore via a 1.6km pipeline. The materials were discharged into purpose
made temporary lagoons from where the water was removed and material then excavated
and distributed around the site.
The sand was delivered in 14,000m3 boatloads which took 3 hours to pump onto the
site and return the 30,000m3 of seawater. In total around 240,000m3 were received and
placed by Careys in two weeks. Once the surcharge periods were over half that volume
had to be moved again and the final formation trim to all areas. This was carried out by
GPS controlled blades to a +/-30mm tolerance which given the material was sand was
very tight.
Case Studies
Sector
Project
Hotel, Art & Leisure / Leisure
M3 Services - Winchester
Project Overview
Careys was initially appointed by the Highways Agency to carry out a Design and Build
contract to construct northbound and southbound on and off slip lanes to the M3
motorway and for access and egress to the planned Winchester Motorway Service Area
(MSA). A subsequent Design and Build contract was carried out by Careys for Roadchef
Motorways Ltd., involving the construction and fit out of the MSA Amenity Buildings and
Travel Inn Hotel on both the North and South bound sites, together with the provision of
the sites infrastructure and car parks.
Services
Project Details
Client
Highways Agency / Roadchef
Location
Winchester, England
Principal Contractor
P.J. Carey (Contractors) Ltd.
Gallery
Engineer / Consultant / PQS
Woods Warren
More Information
The works were carried out on a greenfield site and required a significant cutting to be
constructed into the chalk landscape. Gabion walls were utilised to support the sides
of the motorway. All works were constructed whilst the motorway remained open, with
traffic management planned, implemented and managed by Careys.
The majority of works on both contracts were delivered using Careys own plant and
labour, together with specialist roofing and cladding contractors. A particular feature of
the scheme was the extensive butterfly roof.
Both contracts were delievred to budget and in line with their fast-track programmes.
Case Studies
Sector
Project
Retail / Motorway Services & Petrol Stations
M1 Services - Northampton
Services
Project Overview
This contract at Junction 15a of the M1 was for the reconstruction of the north and
southbound Motorway Services Area. Works included the demolition of existing
restaurants and other buildings, service stations and infrastructure, whilst the petrol
filling stations remained operational. The layout of the service area was significantly
revised; requiring major earthworks, the provision of a piling mat, bored piling,
substructures, extensive drainage, a revised road layout, car and lorry parking areas, plus
hard and soft landscaping. A BP Connect Petrol Station was also constructed and opened
as the existing facility was decommissioned ensuring continuity of service.
Project Details
Client
Roadchef Motorways Ltd.
Location
Northampton, England
Principal Contractor
Gallery
P.J. Carey (Contractors) Ltd.
Engineer / Consultant / PQS
Woods Warren / Edmund Shipway
More Information
This Design & Build contract was Careys second Motorway Services Area (MSA) project
for RoadChef Motorway Ltd., following the successful completion of a similar MSA
scheme on the M3 at Winchester.
Case Studies
Sector
Project
Retail / Retail Parks
Morfa Park
Services
Project Overview
River & bridge works were part of Careys contract to build the infrastructure to the new
300,000ft retail and sports development in Swansea. Careys scope included extensive car
parking, roads, drainage, hardstandings for HGVs and section 278 works, while Scudder
carried out the demolition of the existing stadium and associated running track area. A
live railway line was located on the Northern boundary of the site and demarcation zones
were established of where plant could work safely.
Project Details
Client
Morfa Retail Park
Location
Swansea, Wales
Principal Contractor
Gallery
Miller Construction
Engineer / Consultant / PQS
URS Corporation / Gleeds
More Information
Site enabling works for the site offices and a piling mat for the piling subcontractor were
carried out by Careys. All the piles were broke down and foundations and slabs poured
for the retail park with all associated drainage and service ducts.
Careys also carried out the lifting of four 96 tonne, 50 metre long steel sections to
construct a new road bridge spanning the river Tawe in Swansea. The lift was carried out
using a 1,000 tonne crane with beam sections bolted together on-site.
Case Studies
Sector
Project
Retail / Retail Parks
Greenwich Retail Park
Services
Project Overview
This major Design & Build main contract was built by Careys building division and
involved the construction of a 107,500ft2 retail park divided into 12 units. The scope of
works included site clearance & demolition, construction of new retail areas, car parking
for 305 vehicles, access roads, service yards and associated infrastructure.
Project Details
Client
Deutsche Property Asset Management
Location
Greenwich, London
Principal Contractor
Gallery
P.J. Carey (Contractors) Ltd
Engineer / Consultant / PQS
Beattie Watkinson / Potter Raper
Partnership
More Information
The success of this project has led to Careys being appointed to undertake a second
major project for the client, with the redevelopment of Erith Town Centre.
Case Studies
Sector
Project
Commercial / Business Park
Farnborough Business Park
Services
Project Overview
Careys Civil Engineering division and Scudder were both appointed to the carry out works
on the prestigious Farnborough Business Park in Surrey. All demolition works on site
were carried out by Scudder, while the Civils division of Careys constructed the entire
infrastructure for the high end development. The project was designed to a very high
specification and is an excellent example of how cross division working in the Carey
Group brings a real added value to the client.
Project Details
Client
London, England
Location
Slough Estates Ltd
Principal Contractor
Gallery
Carillion
Engineer / Consultant / PQS
Peter Brett & Associates
More Information
While Scudder was appointed to carry out site clearance works, Careys scope of works
were: drainage, landscaping and the construction of a network of roads throughout the
business park including roundabouts. Further works undertaken consisted of substructure
and external works for two of the buildings on the site.
The Business Park was designed to a high specification throughout; the project featured
extensive block paving with Chinese granite sets and kerbs.
Case Studies
Sector
Project
Industrial & Technology /
Pharmaceutical & Research
GlaxoSmithKline
Project Overview
Careys has now undertaken a number of projects for GSK (GlaxoSmithKline) across
various sites, giving a true testament to the quality of work delivered by the business.
Works have varied across sites but have included; hard & soft landscaping, substructure
and extensive earthworks, relocation of existing buildings and S278 works. Additional
challenges were undertaking works while ensuring as little disruption to the client as
possible enabling them to carry out day to day activities as usual, works were also
required to be carried out in a highly sensitive and high security environment with tight
restrictions on access.
Services
Project Details
Client
Sir Robert Mc Alpine Ltd.
Location
Bristol, England
Principal Contractor
Gallery
Sir Robert McAlpine Ltd
Engineer / Consultant / PQS
Waterman
More Information
Careys undertook a major package of civil engineering, infrastructure and high quality
hard landscaping works on the GSK Headquarters. Initial civils works included a 50,0000
m3 bulk excavation and fill operation, soil washing and manual sorting of excavated
material, removal of contaminated material, groundwater remediation, the construction
of temporary roads, land drains & ducts, an access ramp, foul drainage with pumping
station and sheet pile walls. Additionally infrastructure works were undertaken which
encompassed all new roads and accesses, surface car parks, areas of high quality paving,
hard landscaping features to form terraces and canal frontage, gabion walling and soft
landscaping.
Careys was also awarded the design and build package for the hard and soft landscape at
the GSK Ware site. The package entailed block paved and modular flag stone footways
around the newly constructed building 9 laboratory. Initially Careys carried out the
bulk excavation and created a piling mat. The scope of works included the relocation
Case Studies
Sector
Project
Industrial & Technology /
Manufacturing & Distribution
BMW
Project Overview
Careys has now enjoyed working in partnership with BMW for over 7 years and we have
now successfully completed over 15 projects with a total value of circa £16 million. Both
Scudder and Careys have been employed on various commissions underpinning one of
the key success factors of Careys; the ability to provide a full construction service to
clients from demolition through build.
Services
Project Details
Client
BMW
Location
Oxford, England
Gallery
Engineer / Consultant / PQS
Rolton Group
More Information
The main building comprises of the Utilities/Production/Administration and Warehouse
Areas and is surrounded by peripheral structures such as a garage and lorry wash area,
a waste management building, an Energy Distribution Centre, several bundled RC tank
storage bases, a PET Centre and several external chiller bases.
The enabling works for the earthworks involved the temporary diversion of the Lissue
stream which traversed the site. Following the main body of the earthworks the
stream was permanently diverted into a 500m long, 1500mm diameter twin culvert
with associated RC manholes and headwalls. The earthworks involved soil modification
of 250,000 m3 of lime stabilised clay, and the relocate ion on site of approximately
80,000m3 of topsoil and unsuitable material into landscaped areas.
Approximately 1500m of process foul drainage, 1200m of domestic foul drainage and
3600m of storm drainage to depths of up to 7m was installed. An 8m deep wet well
pumping chamber for domestic foul sewage was constructed. Four separate lagoons
were developed in the landscaped areas with a combined surface area of 11,000m2
to assist with attenuation and enable the controlled discharge of stormwater to a local
watercourse.
Case Studies
Sector
Project
Industrial & Technology /
Pharmaceutical & Research
Pfizer
Project Overview
Careys received two contracts from Pfizer, one as a main contractor on new infrastructure
works for the expansion of the Sandwich facility, the other to carry out external works
at their Surrey Head Office. Works at Sandwich included extensive earthworks, drainage,
and the provision of 1500+ car parking spaces, road and hard landscaping. An additional
appointment was for construction of a new visitor centre with attendant security
screening facilities.
Services
Project Details
Client
Pfizer Pharmaceuticals Ltd.
Location
Various
Principal Contractor
Gallery
Various
Engineer / Consultant / PQS
Various / Various
More Information
Head office works included; construction of coach/car parks, with drainage works
involving drilling 20m deep soakways into the underlying chalk. Improvements to site
distribution roads and soft landscaping were also included.
Case Studies
Sector
Project
Industrial & Technology /
Data Centres
Morgan Stanley Data Centre
Project Overview
Careys was contracted to construct a ground floor (transfer slab) and first floor mezzanine
slab for the new Morgan Stanley Data Centre. The initial scope of works was to concrete
a 350mm thick transfer slab over the existing round floor slab and a 150mm thick
concrete mezzanine slab. Added value was brought to the client by completing works 2
weeks ahead of an already ambitious programme.
Services
Project Details
Client
Morgan Stanley
Location
Surrey, England
Principal Contractor
Gallery
PJ Carey Contractors
Engineer / Consultant / PQS
PJ Carey Contractors
More Information
On the ground floor slab a Bamtec rolled reinforcement was used by Careys for the first
time, enabling the increase of steel fixing outputs while reducing labour considerably. This
had a positive effect on the programme as it enabled the works to be completed 2 ahead
of schedule. The works comprised of 1,400 tonnes of reinforcement and 5,500 cubic
metres of concrete.
The scope of works also included the roads, drainage and infrastructure to the project.
Case Studies
Sector
Project
Energy, Power & Waste / Power Plant
Marchwood CCGT Power Station
Project Overview
Careys was appointed by Siemens to carry the concrete works package for the new
842 megawatt Combined Cycle Gas Turbine (CCGT) power plant, at Marchwood near
Southampton. Works entailed the construction of the foundations to 34 buildings.
Foundations were also created for the platforms for the two gas turbines and a steam
turbine.
Gallery
Services
Project Details
Client
Marchwood Power Ltd
Location
Southampton, England
Principal Contractor
Siemens Plc.
Engineer / Consultant / PQS
Siemens Plc.
More Information
5,700m of temporary Sheetpiling was used, and 600m2 of permanent sheet piles assisted
works. 1,400 piles were cut to formation level.
The Steam turbine with a 3.0m deep base, and a total concrete volume of 1200m3 was
constructed by means of an open cut excavation. The Turbine table was constructed
on 12m high columns, ranging from 1m2 to 1.5m2, and ranged from 3m deep on the
east side, to 4.5m deep on the generator side. It contained 286t of reinforcing steel
and required a continuous 17 hour 1,800m3 concrete pour. All pours relating to the
turbines, were poured monolithically and were monitored with thermocouples ensuring
the temperature of the curing concrete never exceed the required values. The three
transformer bases were poured to a tolerance of +-3mm to provide an even surface for
the transformer, and the 9m high walls surrounding the transformers were built using the
EFCO formwork system.
The foundations for two boilers consisted of 1,800m3 monolithic concrete pours each and
were 1,500mm deep. 27,000m of drainage was laid, ranging from 100-600mm in diameter,
as was various waterproof ducts for services ranging from 100-900mm. 4 cofferdams were
constructed to allow the workforce to safely construct the deeper elements of the contract
and 35 cable pits were constructed out of concrete and built to a watertight specification.
150m of pre-cast concrete duct troughs were laid for Electric supply cables, which were
covered with specialised sand and sealed with a precast lid.
Case Studies
Sector
Project
Energy, Power & Waste / Renewable Energy
Vestas Manufacturing Plant
Project Overview
Careys was contracted to phase one of the project for demolition and earthworks in
preparation for a wind turbine site. The work was carried out adjacent to a tidal estuary
and on land previously used as a cement works and which is prone to rainwater run-off
from a nearby landfill site, both of which meaning that much of the removed soil was
contaminated. After successful completion of phase one, Careys was contracted to work
on phase two of the project, the construction of the concrete foundations, a 100m long
sheet piling retaining wall adjacent to the river, and for onsite drainage.
Services
Project Details
Client
Sir Robert Mc Alpine Ltd.
Location
Isle of Wight, England
Principal Contractor
Sir Robert McAlpine Ltd
Gallery
Engineer / Consultant / PQS
Ramboll / Davis Langdon
More Information
Throughout phase 1 the clients’ environmental consultants were on site to ensure that
the earth was removed and dealt with in accordance with specifications. This includes
installing newly created land drains for water running from the landfill site.
In phase 2 the 100m retaining wall could not be constructed in the water and had to be
piled on the land before the old wall was removed. Work was carried out only at low tide
and no machinery was allowed in or on the water. To mitigate against this, specialized
brackets were used allowing the working platform to be extended out over the river
without contamination of the water.
Finally, during work on the foundations two old wells were discovered and capped.
was done in consultation with the client’s designer and the Environment Agency.
This
Case Studies
Sector
Project
Energy, Power & Waste / Power Plant
Pembroke CCGT Power Station
Project Overview
Careys was engaged by Alstom Power in a key section of the works on the Pembroke
CCGT power station development. The project comprised of civil marine works involving
heavy civil engineering works to two crucial existing structures from the previous power
stations operations. This involved the demolition of existing load carrying elements and
sequential reconstruction of new load carrying elements. The Careys team completed
all works successfully managing to accelerate works bringing the client back in-line with
their original programme which had previously slipped.
Services
Project Details
Client
Alstom Power Ltd
Location
Pembroke, Wales
Principal Contractor
Gallery
Alstom Power Ltd
Engineer / Consultant / PQS
Halcrow and IDOM/Alstom Power Ltd
More Information
Careys works were across two structures the first of which is a large existing inlet
pumping chamber, some 20m deep with a plan area of around 1200m2. This structure
underwent large scale modification including the demolition of load carrying elements and
sequential reconstruction of new load carrying elements.
The second structure is the existing seal Weir chamber which consisted of a deep
sequence of large culverts. Careys operations included the complete demolition of the
culverts followed by the construction of a new chamber measuring some 12m in depth
and with a plan area of around 900m2. The sequencing of the external wall pours along
with the complex internal wall arrangement was key to the successful completion of the
structure within milestone dates.
Careys brought real client benefits to the project by being able to resequence the buttress
removal in the existing pump chamber to improve the program, accelerating the works
back to the original program for Alstom Power. Additionally Careys crushed thousands of
tons of dug rock and broken concrete allowing the client to re-use later in the project.
Case Studies
Sector
Project
Energy, Power & Waste / Renewable Energy
Olympic Park Energy Centres
Project Overview
This project consisted of two CCHP (Combined Cooling, Heat and Power) energy centres,
one located within the Olympic Park supplying heat, power and chilled water to all the
Olympic venues and one located within the Westfield retail development supplying heat,
power and chilled water. The main plant building is 24m high with the flue structure
rising to 45m – resembling a miniature version of the iconic Tate Modern Art Gallery. The
second building was a retained Edwardian sweet factory building which was structurally
altered by Careys to house biomass boilers and a visitor centre.
Services
Project Details
Client
Cofely GDF Suez
Location
London, England
Gallery
Principal Contractor
PJ Carey (Contractors) Ltd.
Engineer / Consultant / PQS
Adams Kara Taylor
More Information
Careys installed more than 500t of steel founded on piled foundations to erect the frame
of the buildings. On the Olympic Park the Energy Centres are steel framed structures
founded on piled foundations incorporating heavy insitu ground floor slab and composite
concrete slabs to first floor, mezzanine level and roof to accommodate heavy plant
installations. The structure is clad in a waterproof membrane with an outer Corten
shroud to soften the impact of the building size.
Scudder was tasked with the partial demolition and enabling works for the conversion of
the historic Edwardian mill. The main works included the strip out and opening up of the
north side of the mill structure to host the biomass plant whilst retaining the floors in the
south side and creating new stairwells and liftwells.
Logistically both projects had great degrees of difficulty due to their close proximity
to Network Rail lines and the CTRL box as it passes through Stratford. Considerable
amounts of liaison between Careys, Network Rail and CTRL was required together with
technical submissions prior to any works commencing. Additionally as the Olympic Park is
considered a high security risk, access and egress for plant, materials and operatives was
a very structured and controlled process.
Case Studies
Sector
Project
Transport / Aviation
Heathrow Airport
Project Overview
Careys first appointment was on an Enabling and Main Works contract relating to general
groundworks for the construction of a new control post (CP5), sitting alongside the
existing live control post. This project took place part airside and part landside in a
live airport environment allowing Careys to work innovatively by carrying out vacuum
excavation around live services. A further Careys appointment at Heathrow was Terminal
4 Baggage Works and involved the extension of the existing baggage facility; Reclaim 8
by adding a new baggage conveyor and by removing the existing blast screen.
Services
Project Details
Client
BAA Airports Limited
Location
London, England
Principal Contractor
Gallery
More Information
Careys were appointed to construct The scope of works on the control point 5 security
building works included foundations, services, drainage foundations for blockers and
barriers (to control traffic) all within the airside of the
airport. Additionally Pavement Quality (PQ) slabs, 350 thick with lean mix underneath
were cut by diamond cutting saw. Foundations were excavated by hand-digging due to
chartered and unchartered services/ducts present at Heathrow. A stormwater interceptor
was installed along with heavy duty aco channels.
Working in an airport environment carries a number of unique challenges which the Carey
team are adept at tackling, from complying with the latest BAA requirements in health
and safety and asset management to working on busy live sites and night time working,
the team at Careys are proud to consistently deliver undisputable levels of service.
The dedicated and specialist team provides the highest quality of service and continues to
receive commissions from Heathrow Airport and has now recently commenced works with
Vinci at Gatwick Airport.
MACE
Case Studies
Sector
Project
Transport / Aviation
Gatwick Airport
Project Overview
Due to the strength of our work at London Heathrow Airport, Vinci appointed Careys
on works at Gatwick’s South and North terminal buildings. The scope of works included
undertaking civil engineering for the South Terminal Forecourt Enhancement works, as
well as engineering and concrete structures for the new passenger terminal interface
buildings.
Services
Project Details
Client
BAA
Location
London, England
Principal Contractor
Vinci
Gallery
Engineer / Consultant / PQS
Rarhborne & Roche
More Information
Works took place in a live airport environment, with off peak working hours required to
work around peak traffic.
Case Studies
Sector
Project
Transport / Rail
DLR 3 Package 5
Project Overview
Careys was awarded the contract for the construction of reinforced concrete pile caps,
columns, column heads and the new fly-under structure beneath the existing DLR Railway
and above the West India Quay. The concrete was completed to a F3 finish. The scope
also included the realignment and reconstruction of the existing viaduct to tie into the
new structure.
Services
Project Details
Client
VINCI Construction UK Limited
Location
London, England
Gallery
More Information
The project was DLR’s (Docklands Light Railway) response to increasing passenger and a
desire to enable three-carriage trains to operate.
Case Studies
Sector
Project
Transport / Rail
DLR 3 - Canning Town Flyover
Project Overview
Careys was awarded the contract for the civil engineering works on the new grade
separated junction flyover at Canning Town on the Docklands Light Railway. The works
include the construction of a 400m elevated reinforced concrete bridge deck (flyover
structure) which comprised of a variety of steel, cast in situ concrete and precast
concrete construction methods. The concrete was completed to a F3 /F4 finish. The works
were carried out adjacent to the existing DLR and Jubilee line tracks and for a large part
underneath high voltage National Grid cables (400,000 Volts) brining extra challenges to
the works.
Services
Project Details
Client
Vinci Construction Ltd
Location
London, England
Engineer / Consultant / PQS
Arup / Vinci Construction Ltd.
Gallery
More Information
The scope of works included the construction of reinforced concrete pile caps and
piers and the installation of bridge bearings. Precast concrete diaphragm units were
constructed and subsequently lifted into position with a 600t crawler crane.
This crane also installed precast concrete bridge breams and GRP permanent slab
formwork and precast concrete omnia planks. All associated drainage and earthworks
were carried out along with these works.
The project was delivered on time. The work was carried out to specification. Our own
professional competent tradesmen/skilled workers were employed to carry out the works.
Specialist works were carried out by others.
Case Studies
Sector
Project
Transport / Highways
Magna Park & A421
Project Overview
Careys secured a civil engineering contract to construct the infrastructure to serve the
new Magna Park development. Works included the road widening works to convert 1.5km
from a single to dual carriageway on the busy A421 Milton Keynes and the construction
of a dual carriageway (Fen Street) to facilitate access to the new development. Also
encompassed in the works were the provision of a foot/cycle path, two underpasses,
roads, a roundabout, foul and storm drainage and services for the development.
Services
Project Details
Client
Gazely & Fen Farm Developments
Location
Milton Keynes, England
Engineer / Consultant / PQS
Capita Symonds / Davis Langdon
Gallery
More Information
Prior to commencement, liaison took place with the police, local public transport,
statutory services providers and other interested public bodies. Careys provided traffic
management throughout the course of the new roadworks. The scope of works also
included first phase of the site infrastructure to serve the new John Lewis distribution
centre with extensive earthworks involving cut and fill and over 1.5km of combined
services trench, 500m of deep foul drainage, over 2km of polyethylene storm water
drainage and ductile iron water main.
The contract was divided into two phases. Phase 1 involved the construction of two
thirds of the length of the two cast insitu RC pedestrian underpasses. These works then
had a one lane road and central reserve lain on top, as part of the 1.5km road widening
of the A421. In addition, the new dual carriageway (Fenn St) and roundabout was
constructed to form the entrance into the development.
Case Studies
Sector
Project
Residential & Regeneration /
Residential Mixed Use
Wembley Central - Building 1
Project Overview
Careys was awarded this Shell & Core contract involving construction of a mixed-use
retail and residential development and S278 Works. The residential apartment blocks
are faced up with a combination of coloured rain screen and Sto render. The majority
of apartments have attached balconies and aluminium windows. The superstructure
was formed from 3,500m3 of concrete and 650t of reinforcement. To the front elevation
of the project, a 12 storey RC Frame was constructed and an additional 2 floors were
constructed of lightweight steel with Kingspan metal cladding to create penthouse duplex
apartments with glass terraces.
Services
Project Details
Client
Sowcrest Ltd. (Joint venture between
St. Modwens and Rotch Group)
Location
London, England
Gallery
Principal Contractor
T.E. Scudder / P.J. Carey
(Contractors) Ltd.
Engineer / Consultant / PQS
Nolan Associates / Dbk Goyne
Adams Ltd.
More Information
The remaining part of the project comprises of a 2 storey retail shell with an additional
4 storey residential block constructed in lightweight steel frame above. One of the
key issues was that the site was above and alongside Wembley Central Station which
accommodates both Network Rail and London Underground operating companies. Careys
had to submit documentation and seek permission prior to any works commencing. Both
transport companies activities remained operational throughout the works.
In addition, the site constraints involved working in a very busy city centre environment
necessitating the need for careful consideration of public interfacing at site entrances and
thoroughfares. Agreement was reached with the local authority highways engineers, as
to the measures that had to be undertaken for maintaining the vehicle and pedestrian
thoroughfares past the main site access points.
There were also restrictions on noise and dust pollution. Careys had to carry out noise
suppression measures, putting acoustic barriers around noisy plant and restricting noisy
working periods to set times of the day to minimise the impact on the local residents and
businesses.
Case Studies
Sector
Project
Hotel, Art & Leisure / Leisure
ExCel Exhibition Centre
Project Overview
Careys were appointed to carry out civil engineering works at the Excel Exhibition Centre
in London’s Docklands. The scope of works included; excavation to reduced level, capping
and sub-base to landscape areas, installation of kerbs, granite setts, pre-cast concrete
channels and drainage channels and 28,000m2 of tarmacadam. Paving was carried out
to column bases and soft and hard landscaping to piazza area with cleaning, cutting
& installation of insitu granite paving, a PQ concrete road, resin bound gravel paving,
tactile/block paving and tree planting.
Services
Project Details
Client
Abu Dhabi National Exhibition Centre
(ADNEC)
Location
London, England
Principal Contractor
Sir Robert McAlpine
Gallery
Engineer / Consultant / PQS
McAlpine Design Group / Gardiner
& Theobold
More Information
Concrete Works were also carried out including remedial works to existing Quay.
Case Studies
Sector
Project
Public / LA & Development Agencies
Watford Fire Station
Project Overview
Careys was awarded a Design & Build contract for a new fire station serving South
Watford. The scope of works included; the construction of a four storey landmark building
with fire station and crew accommodation to the ground and first floor levels, with 2
floors of residential flats above. External facilitates, associated Section 278 works, the
storage of three additional support vehicles and garaging for the three fire engines were
all constructed, as was a museum building next to the fire station for memorabilia. This
project was Highly Commended in the 2011 SCALA Awards for Civic Building of the Year.
Services
Project Details
Client
Hertfordshire County Council
Location
Watford, London
Gallery
Principal Contractor
P.J. Carey (Contractors) Ltd.
Engineer / Consultant / PQS
Hurst Pierce + Malcolm / Mace
More Information
A ‘grey water harvester’ drainage system is used through-out the building for the toilets.
Careys also introduced rain water interception tanks which enabled the fire services to
use this water for training purposes rather than using filtered water.
A Contiguous Piled Retaining wall on the Northern side of the site was built to maintain a
footpath running alongside an existing store. The foundations for this were CFA-piled to
a maximum depth of 22m.
The Training and Service Yards were constructed of traditional reinforced concrete slabs
with a brushed finish. Block paving was installed at the front car park of the fire station
and apartments. Soft landscaping was designed to reinforce security and privacy and
support footpaths to prevent shortcutting and erosion of edges.
Work on the highway was carried out under a Section278 Agreement with the Watford
Borough Council to realign the existing road and footpath to accommodate the fire
engines access and egress. This included altering the traffic lights to accommodate for a
“Green Wave” traffic signal at the junction, to give priority to the fire appliances as they
approach the traffic signal.
Case Studies
Sector
Project
Public / Defence & Prison
Colchester Garrison
Project Overview
Careys carried out a significant element of the Colchester Garrison redevelopment, a
Public Finance Initiative scheme over 5 years. Careys was initially contracted to construct
the basements and reinforced concrete podium slabs to two buildings circa 7,000m2, the
works were completed two months early allowing the modular superstructure works to be
brought forward. Careys was then awarded a design & build contract for the construction
of 3 multi storey car parks totalling 750 spaces and a sports pavilion which included
substructure and infrastructure works.
Services
Project Details
Client
Colchester, England
Location
RMPA Services Plc.
Gallery
Principal Contractor
Sir Robert McAlpine
Engineer / Consultant / PQS
Beattie Watkinson Partners / EC
Harris
More Information
Works included the demolition of existing barracks, and the installation of the drainage
and 6km of ACO slot channel, gas, water services, telecom and electrical ducting.
22,000m2 of CBM was laid along with extensive hard landscaping works including
100,000m2 of PQ surfacing (brush finished concrete) and bituminous roads.
4km of footpaths and reinforced grass traffic routes were constructed and street furniture
installed. Careys carried out an intensive cut and fill exercise with alterations to the
existing topography. The car parks consist of structural steel frames with precast flooring
and ramps, external cladding is a combination of blockwork and metal-frame windows.
Soft landscaping was carried out by Careys with the installation of tree protection,
reinstatement of indigenous greenbelts and construction of football pitches. The project
had to be delivered to four milestone dates providing the completion of all hard and soft
landscaping words in a sequenced manner in line with the clients and main contractor’s
requirements.
The Colchester Sports Pavilion was additional to the original contract works with Careys
being appointed due to the excellent quality of work on the previous commissions.
Operating throughout the UK & Ireland, the Carey Group’s Head Office is located in Wembley
with further regional offices in Milton Keynes, Scotland and the Republic of Ireland.
Headquarters
CAREY GROUP PLC
Carey House
Great Central Way
Wembley
Middlesex HA9 0HR
T 020 8900 0221
admin@careysplc.co.uk
Milton Keynes
CAREY GROUP PLC
Chesney Wold , Bleak Hall
Buckinghamshire MK6 1NJ
T 01908 668383
Bristol
CAREY GROUP PLC
2440 The Quadrant, Aztec West
Bristol BS32 4AQ
T 01454 877674
Ireland
CAREY GROUP PLC
Carey House
Dardistown, Cloghran
Co. Dublin
T 00353 1 842 7300
Scotland
CAREY GROUP PLC
Carey House
21 Shairps Business Park
Houstoun Road, Livingston
West Lothian EH54 5FD
T 01506 444 448
www.careysplc.co.uk
Download