DEMOLITION | CIVIL ENGINEERING | CONCRETE STRUCTURES | BUILDING | ENVIRONMENTAL SOLUTIONS Sector & Retail England Wales Case Studies Case Studies Sector Project Residential & Regeneration / Residential Apartments Kensington High Street Project Overview Scudder was appointed by St Edwards Homes to demolish 375 Kensington High Street (Charles House). The former Inland Revenue offices stood at 10 storey high, plus basements, with a footprint of 50,000sqm. The site is bounded by Kensington High Street with a prestigious London hotel opposite, smart residential streets and a main railway line. Success of the demolition works was such that the Carey Group where then awarded further works drawing on the expertise of both our both Civil Engineering and Concrete Structures divisions. The demolition phase of the project was shortlisted in the Specialist Awards 2012. Services Project Details Client St. Edward Homes a joint venture between Berkeley Homes and The Prudential Location London, England Gallery Principal Contractor St. Edward Homes Engineer / Consultant / PQS Manhire Associates / St. Edward Homes More Information The demolition of the building required meticulous planning, and involved different demolition techniques for each section of the building. 80% of the exterior of the building was encased with monarflex sheeted independent access scaffold, reducing dust and noise transmission. The rear of the building was left clear, allowing long reach remote demolition machines to demolish two of the rear wings and the central spine. The remaining wings (adjacent to the railway and public highways), were simultaneously demolished, top down, using 7 tonne demolition spec machines fitted with pulverisers. In order to remove the basement, a pressed sheet pile retaining wall system was installed tight to the boundary, during the demolition phase. Vibration monitoring with audible and visual early warning alarms, was installed to ensure the gas and water mains were safeguarded at all times. Due to the close proximity of live railway lines, much of the work required close liaison with Network Rail, carefully planning and communicating site activities in advance to ensure smooth progress. With the successful completion of Phase 1, Careys was awarded the second phase of works. Case Studies Sector Project Hotel, Art & Leisure / Leisure The British Museum Project Overview Careys scope of works is for the construction of the reinforced concrete substructure for the World Conservation and Exhibitions Centre at the British Museum. The sub-structure is approximately 18m deep and has 5 levels with a sub floor providing space for lift pits and motor rooms. The site is located within the bounds of the existing British Museum complex. The works area is bound by retained buildings on 3 fronts making the site a very challenging footprint to work on. Prevention of damage to the existing building and exhibits within meant that noise and vibrations were monitored and minimised. Services Project Details Client British Museum Location London, England Principal Contractor Mace Gallery Engineer / Consultant / PQS Ramboll UK / Davis Langdon More Information The British Museum is a world leader in the conservation and display of objects from across the globe. To ensure it can continue and grow its important role through the twenty-first century it has taken the opportunity to expand into this new building which has been created to provide a light finish of specially-produced glass and traditional stone to sit well and blend with its grade I listed surroundings. The new Centre will provide: • dedicated gallery for special exhibitions • conservation and science facilities • a collections’ management hub • world-class stores for the study collection Although we have managed noise and vibration issues on many of our sites we recognise that the concern on this project is such that a higher degree of understanding is required and have therefore employed the services of a specialist, SENSONICS, to assist us with the development of our elimination, management and monitoring strategy. Case Studies Sector Project Retail / Shopping Centres Bull Ring, Spiceal Street Services Project Overview Careys was contracted to Design and Construct the redevelopment of St Martin’s Square and Spiceal Street, which includes; the construction of three new retail units, the extension of two existing units, reconfiguration of open space, and the provision of new public realm hard and soft landscaping works and features. The main contracts works included; demolition, piling, structural steelwork, concrete, structural alterations to existing building, concrete remedial works, and waterproofing, shell and core. The Bullring is already a major attraction in Birmingham, with the addition of the Spiceal Street development extending the availability of amenities into the evening. Project Details Client Bullring Ltd Partnership Location Birmingham, England Principal Contractor Gallery More Information This 20,000sqft development is set around St Martin’s Square and was designed by Chapman Taylor. The architectural design for Spiceal Street includes a striking ‘ribbon concept’ curved roof linking the three new retail units, formal and informal seating areas, a feature green wall and a new water feature as part of the improved public realm. The existing steps linking Central Street to St. Martin’s Square have been relocated to the east and reoriented towards the Church. The third new unit is situated at the pedestrian entrance from Park Street, building on the existing stepped access to the first floor of Selfridges. PJ Carey (Contrators) Ltd Case Studies Sector Project Energy, Power & Waste / Waste Facilities Seneca Materials Recovery Facility Project Overview Seneca; Carey’s Environmental Solutions business, received planning permission in September 2010 to convert a disused distribution centre on a 6.5 hectare site in Brent, into a ‘super’ Materials Recovery Facility (MRF), with a licence to handle up to 1.1m tonnes of mixed waste. Careys Building Division oversaw the 32-week turnkey contract. Works included upgrading the site’s infrastructure, refurbishing the 128,000m2 industrial building and installing the specialist material separation plant and equipment. The existing building was extensively refurbished and achieved a BREEAM Excellent standard. Services Project Details Client Seneca Environmental Solutions Ltd. Location Wembley, England Gallery Principal Contractor P.J. Carey (Contractors) Ltd More Information The Seneca site’s access and perimeter road was modified to suit the revised traffic management requirements of the facility, with a digitised weighbridge system installed to record the weight and origin of each delivered load. Additional pedestrian and cycling access was also constructed, together with car parking for 50 vehicles. The refurbished building gained BREEAM excellence standards, with an integrated greywater harvesting system installed. 5m high in-situ reinforced concrete retaining walls were cast to create material storage and segregation areas. The elevated 40m long picking line area is adjoined by high quality staff welfare facilities. Eight designated material collection bays sit below the picking line, allowing operatives to manually select and divert different material types into collection bays via metal hoppers, located adjacent to the picking line conveyor belt. A series of flip-flow screens were installed to separate out varying sizes of fines, with large magnets to takeout the metal rich items. Once materials have been separated out, they are bailed and stored ready to dispatch for reprocessing or remanufacturing. The facility also benefits from a rail siding which spans the full length of the 175m long site; with two parallel lines running both inside and outside. The rail siding is scheduled to go live early in 2012. Case Studies Sector Project Hotel, Art & Leisure / Leisure The Hippodrome Casino Project Overview Careys was appointed as Principal Contractor to carry out the enabling, demolition and associated shell and core works of the Hippodrome Casino, a Grade II listed building. The scope of works consists of; demolition, underpinning, excavation, piling structural steelworks, concrete and structural alterations to the existing building, concrete remedial works and waterproofing. T.E. Scudder Ltd were appointed as demolition specialist for all demolition, temporary works design and installation, façade retention and associated works. Services Project Details Client United Gaming Leisure Location London Principal Contractor P.J. Carey (Contractors) Ltd. Gallery Engineer / Consultant / PQS Alan Baxter / Box Associates More Information The works that were carried out to the Grade II listed building included an external detailed façade retention scheme to an existing low rise infill building enabling complete demolition down to basement of the attached building, internal bracing to the North West Staircase which allowed the required demolition works to be carried out and various demolition of walls, slabs and staircases to the main auditorium area which also required a temporary propping design which would withstand the loadings. One of the West Ends most popular landmark buildings, the Hippodrome was once known for its variety performances then was renovated into one of the West Ends most popular nightclubs. Now the site has been restored back to its former glory and transformed into The Hippodrome Casino. Case Studies Sector Project Commercial / Business Park Chiswick Park Services Project Overview Careys Civil Engineering division was contracted to carry out a “face-lifting” hard landscaping design at Chiswick Park. The project also included the construction of a service yard and laying the surface in the event square, installation of street furniture, Addagrip and Europave. The paving finishes were completed to a high specification. Latterly Careys were awarded contracts for sub and superstructures on Building 6 within the site, works comprised of 9 storeys above ground, accommodating office space and a below ground level car park. Project Details Client Stanhope Plc Location London, England Gallery Principal Contractor Bovis Lend Lease Engineer / Consultant / PQS Arup / Davis Langdon More Information In phase 1 Careys scope of works was varied and included; hard landscaping around the building and the installation of precast copping units, conservation slabs, kerbs and precast step units. Block paving was laid in the under croft for internal parking and a tarmac surface for the external parking area was added with the footpath laid with resin bonded gravel using Addagrip. An earth reinforced retaining wall and service yard were also constructed as part of the works. Part of the surface of the Square was laid with a red tarmac (Europave) with white lines then stencilled on it to create the event space for basketball and other sports. In the Event Square, precast concrete benches and steps units were constructed. These works had been carried out to such a high level of quality and care that Careys were latterly awarded a further commission by the client on the same site. Careys Concrete Structures division oversaw the building of the post-tensioned (PT) concrete slab in the office areas and a reinforced concrete slab in the core area for Building 6. The building benefits from a central insitu concrete core which acts as a cantilever from undercroft level and provides the lateral stability for the building. Horizontal loads from the façade are transferred through the floor plate back to the core and then down through the walls to the foundations. Case Studies Sector Project Commercial / Mixed Use 27 Regent Street Services Project Overview 27 Regent Street is a grade II listed building in the heart of London’s West End. The scope of Scudder works involved part demolition and part refurbishment to provide new residential and retail units. The first stage of demolition involved the removal of internal two-storey masonry and concrete extension. Following demolition, openings were created and new structural steel work installed to support them. The second stage involved the demolition of an existing stair core (extending over 6 floors) and removal of the lift shaft, including car, guides and rails. The final stages of works were in the basement and ground floors. Project Details Client Crown Estate Location London, England Gallery More Information The removal of the stair core involved significant temporary works designed by the Scudder team. The stair core was them demolished floor by floor using a Brokk 90 remotely controlled demolition machine. Formation of new service void openings was made through slabs on all six floors, with new steels installed to support these openings. The basement and ground floors required temporary works; providing propping in the basement with the removal of walls and insertion of steel box frames to create new spaces along with the waterproofing of the existing basement retail spaces. A secure ATM room was built on the ground floor which involved removal of glass partitions and structural slab alterations. Case Studies Sector Project Retail / Food & General Sainsbury’s Services Project Overview Careys are proud to have worked in partnership with Sainbury’s since 1989 on commissions throughout the UK and Ireland. Our relationship initially developed through our demolition business; Scudder, which carried out projects to such a high standard Careys were invited to tender for main works packages. The continued success of project delivery led to Careys being awarded the design and build/ extension contract for Sainsbury petrol stations, and we have now become a first tier contractor on the nationwide capital car park and drainage maintenance package. Project Details Client Sainsbury’s Supermarkets Plc Location Various Principal Contractor Gallery Various Engineer / Consultant / PQS Various More Information In 1989 we embarked on our 1st major project at London Colney, this external works package proved to be a shining example of Careys commitment to delivery, almost halving the programme from 37 weeks to 20 weeks. As the hypermarket format became more mainstream, other stores were developed across England, with Careys playing an ever larger role in each project. In 1995 Careys received the first commission to carry out substructure and external works at a flagship store in Hamilton, Scotland. This was quickly followed by a rollout programme of stores across the country with Careys undertaking various commissions. The larger store format has proliferated since the late 1990s, and Careys has completed in excess of 200 UK contracts, delivering infrastructure, drainage, landscaping, roadworks and the construction of superstructures. Case Studies Sector Project Retail / Food & General Tesco Services Project Overview Both Scudder and PJ Careys have worked on Tesco sites which have been of varying size and complexity. Projects have included demolition and civil engineering works such as; enabling works, substructures, external works, concrete slabs, drainage, carparks, hard landscaping and section 278 works. Careys has regularly received commissions to work across England on the roll out, redevelopment and refurbishment of Tesco stores since 1999. We have now completed over 32 commissions across 18 sites and are continuing to strengthen the partnership with numerous project awards taking place in the last 3 years. Project Details Client Tesco Location Various Principal Contractor Gallery Various Engineer / Consultant / PQS Various More Information A particuarly complex project the Tesco and Careys teams were involved in was the development of a new store and housing in Seaton. The site was previously a holiday camp and was low lying with a planning requirement being that the site footprint must be raised. A scheme was devised to raise the levels with imported dredged materials that were pumped ashore via a 1.6km pipeline. The materials were discharged into purpose made temporary lagoons from where the water was removed and material then excavated and distributed around the site. The sand was delivered in 14,000m3 boatloads which took 3 hours to pump onto the site and return the 30,000m3 of seawater. In total around 240,000m3 were received and placed by Careys in two weeks. Once the surcharge periods were over half that volume had to be moved again and the final formation trim to all areas. This was carried out by GPS controlled blades to a +/-30mm tolerance which given the material was sand was very tight. Case Studies Sector Project Hotel, Art & Leisure / Leisure M3 Services - Winchester Project Overview Careys was initially appointed by the Highways Agency to carry out a Design and Build contract to construct northbound and southbound on and off slip lanes to the M3 motorway and for access and egress to the planned Winchester Motorway Service Area (MSA). A subsequent Design and Build contract was carried out by Careys for Roadchef Motorways Ltd., involving the construction and fit out of the MSA Amenity Buildings and Travel Inn Hotel on both the North and South bound sites, together with the provision of the sites infrastructure and car parks. Services Project Details Client Highways Agency / Roadchef Location Winchester, England Principal Contractor P.J. Carey (Contractors) Ltd. Gallery Engineer / Consultant / PQS Woods Warren More Information The works were carried out on a greenfield site and required a significant cutting to be constructed into the chalk landscape. Gabion walls were utilised to support the sides of the motorway. All works were constructed whilst the motorway remained open, with traffic management planned, implemented and managed by Careys. The majority of works on both contracts were delivered using Careys own plant and labour, together with specialist roofing and cladding contractors. A particular feature of the scheme was the extensive butterfly roof. Both contracts were delievred to budget and in line with their fast-track programmes. Case Studies Sector Project Retail / Motorway Services & Petrol Stations M1 Services - Northampton Services Project Overview This contract at Junction 15a of the M1 was for the reconstruction of the north and southbound Motorway Services Area. Works included the demolition of existing restaurants and other buildings, service stations and infrastructure, whilst the petrol filling stations remained operational. The layout of the service area was significantly revised; requiring major earthworks, the provision of a piling mat, bored piling, substructures, extensive drainage, a revised road layout, car and lorry parking areas, plus hard and soft landscaping. A BP Connect Petrol Station was also constructed and opened as the existing facility was decommissioned ensuring continuity of service. Project Details Client Roadchef Motorways Ltd. Location Northampton, England Principal Contractor Gallery P.J. Carey (Contractors) Ltd. Engineer / Consultant / PQS Woods Warren / Edmund Shipway More Information This Design & Build contract was Careys second Motorway Services Area (MSA) project for RoadChef Motorway Ltd., following the successful completion of a similar MSA scheme on the M3 at Winchester. Case Studies Sector Project Retail / Retail Parks Morfa Park Services Project Overview River & bridge works were part of Careys contract to build the infrastructure to the new 300,000ft retail and sports development in Swansea. Careys scope included extensive car parking, roads, drainage, hardstandings for HGVs and section 278 works, while Scudder carried out the demolition of the existing stadium and associated running track area. A live railway line was located on the Northern boundary of the site and demarcation zones were established of where plant could work safely. Project Details Client Morfa Retail Park Location Swansea, Wales Principal Contractor Gallery Miller Construction Engineer / Consultant / PQS URS Corporation / Gleeds More Information Site enabling works for the site offices and a piling mat for the piling subcontractor were carried out by Careys. All the piles were broke down and foundations and slabs poured for the retail park with all associated drainage and service ducts. Careys also carried out the lifting of four 96 tonne, 50 metre long steel sections to construct a new road bridge spanning the river Tawe in Swansea. The lift was carried out using a 1,000 tonne crane with beam sections bolted together on-site. Case Studies Sector Project Retail / Retail Parks Greenwich Retail Park Services Project Overview This major Design & Build main contract was built by Careys building division and involved the construction of a 107,500ft2 retail park divided into 12 units. The scope of works included site clearance & demolition, construction of new retail areas, car parking for 305 vehicles, access roads, service yards and associated infrastructure. Project Details Client Deutsche Property Asset Management Location Greenwich, London Principal Contractor Gallery P.J. Carey (Contractors) Ltd Engineer / Consultant / PQS Beattie Watkinson / Potter Raper Partnership More Information The success of this project has led to Careys being appointed to undertake a second major project for the client, with the redevelopment of Erith Town Centre. Case Studies Sector Project Commercial / Business Park Farnborough Business Park Services Project Overview Careys Civil Engineering division and Scudder were both appointed to the carry out works on the prestigious Farnborough Business Park in Surrey. All demolition works on site were carried out by Scudder, while the Civils division of Careys constructed the entire infrastructure for the high end development. The project was designed to a very high specification and is an excellent example of how cross division working in the Carey Group brings a real added value to the client. Project Details Client London, England Location Slough Estates Ltd Principal Contractor Gallery Carillion Engineer / Consultant / PQS Peter Brett & Associates More Information While Scudder was appointed to carry out site clearance works, Careys scope of works were: drainage, landscaping and the construction of a network of roads throughout the business park including roundabouts. Further works undertaken consisted of substructure and external works for two of the buildings on the site. The Business Park was designed to a high specification throughout; the project featured extensive block paving with Chinese granite sets and kerbs. Case Studies Sector Project Industrial & Technology / Pharmaceutical & Research GlaxoSmithKline Project Overview Careys has now undertaken a number of projects for GSK (GlaxoSmithKline) across various sites, giving a true testament to the quality of work delivered by the business. Works have varied across sites but have included; hard & soft landscaping, substructure and extensive earthworks, relocation of existing buildings and S278 works. Additional challenges were undertaking works while ensuring as little disruption to the client as possible enabling them to carry out day to day activities as usual, works were also required to be carried out in a highly sensitive and high security environment with tight restrictions on access. Services Project Details Client Sir Robert Mc Alpine Ltd. Location Bristol, England Principal Contractor Gallery Sir Robert McAlpine Ltd Engineer / Consultant / PQS Waterman More Information Careys undertook a major package of civil engineering, infrastructure and high quality hard landscaping works on the GSK Headquarters. Initial civils works included a 50,0000 m3 bulk excavation and fill operation, soil washing and manual sorting of excavated material, removal of contaminated material, groundwater remediation, the construction of temporary roads, land drains & ducts, an access ramp, foul drainage with pumping station and sheet pile walls. Additionally infrastructure works were undertaken which encompassed all new roads and accesses, surface car parks, areas of high quality paving, hard landscaping features to form terraces and canal frontage, gabion walling and soft landscaping. Careys was also awarded the design and build package for the hard and soft landscape at the GSK Ware site. The package entailed block paved and modular flag stone footways around the newly constructed building 9 laboratory. Initially Careys carried out the bulk excavation and created a piling mat. The scope of works included the relocation Case Studies Sector Project Industrial & Technology / Manufacturing & Distribution BMW Project Overview Careys has now enjoyed working in partnership with BMW for over 7 years and we have now successfully completed over 15 projects with a total value of circa £16 million. Both Scudder and Careys have been employed on various commissions underpinning one of the key success factors of Careys; the ability to provide a full construction service to clients from demolition through build. Services Project Details Client BMW Location Oxford, England Gallery Engineer / Consultant / PQS Rolton Group More Information The main building comprises of the Utilities/Production/Administration and Warehouse Areas and is surrounded by peripheral structures such as a garage and lorry wash area, a waste management building, an Energy Distribution Centre, several bundled RC tank storage bases, a PET Centre and several external chiller bases. The enabling works for the earthworks involved the temporary diversion of the Lissue stream which traversed the site. Following the main body of the earthworks the stream was permanently diverted into a 500m long, 1500mm diameter twin culvert with associated RC manholes and headwalls. The earthworks involved soil modification of 250,000 m3 of lime stabilised clay, and the relocate ion on site of approximately 80,000m3 of topsoil and unsuitable material into landscaped areas. Approximately 1500m of process foul drainage, 1200m of domestic foul drainage and 3600m of storm drainage to depths of up to 7m was installed. An 8m deep wet well pumping chamber for domestic foul sewage was constructed. Four separate lagoons were developed in the landscaped areas with a combined surface area of 11,000m2 to assist with attenuation and enable the controlled discharge of stormwater to a local watercourse. Case Studies Sector Project Industrial & Technology / Pharmaceutical & Research Pfizer Project Overview Careys received two contracts from Pfizer, one as a main contractor on new infrastructure works for the expansion of the Sandwich facility, the other to carry out external works at their Surrey Head Office. Works at Sandwich included extensive earthworks, drainage, and the provision of 1500+ car parking spaces, road and hard landscaping. An additional appointment was for construction of a new visitor centre with attendant security screening facilities. Services Project Details Client Pfizer Pharmaceuticals Ltd. Location Various Principal Contractor Gallery Various Engineer / Consultant / PQS Various / Various More Information Head office works included; construction of coach/car parks, with drainage works involving drilling 20m deep soakways into the underlying chalk. Improvements to site distribution roads and soft landscaping were also included. Case Studies Sector Project Industrial & Technology / Data Centres Morgan Stanley Data Centre Project Overview Careys was contracted to construct a ground floor (transfer slab) and first floor mezzanine slab for the new Morgan Stanley Data Centre. The initial scope of works was to concrete a 350mm thick transfer slab over the existing round floor slab and a 150mm thick concrete mezzanine slab. Added value was brought to the client by completing works 2 weeks ahead of an already ambitious programme. Services Project Details Client Morgan Stanley Location Surrey, England Principal Contractor Gallery PJ Carey Contractors Engineer / Consultant / PQS PJ Carey Contractors More Information On the ground floor slab a Bamtec rolled reinforcement was used by Careys for the first time, enabling the increase of steel fixing outputs while reducing labour considerably. This had a positive effect on the programme as it enabled the works to be completed 2 ahead of schedule. The works comprised of 1,400 tonnes of reinforcement and 5,500 cubic metres of concrete. The scope of works also included the roads, drainage and infrastructure to the project. Case Studies Sector Project Energy, Power & Waste / Power Plant Marchwood CCGT Power Station Project Overview Careys was appointed by Siemens to carry the concrete works package for the new 842 megawatt Combined Cycle Gas Turbine (CCGT) power plant, at Marchwood near Southampton. Works entailed the construction of the foundations to 34 buildings. Foundations were also created for the platforms for the two gas turbines and a steam turbine. Gallery Services Project Details Client Marchwood Power Ltd Location Southampton, England Principal Contractor Siemens Plc. Engineer / Consultant / PQS Siemens Plc. More Information 5,700m of temporary Sheetpiling was used, and 600m2 of permanent sheet piles assisted works. 1,400 piles were cut to formation level. The Steam turbine with a 3.0m deep base, and a total concrete volume of 1200m3 was constructed by means of an open cut excavation. The Turbine table was constructed on 12m high columns, ranging from 1m2 to 1.5m2, and ranged from 3m deep on the east side, to 4.5m deep on the generator side. It contained 286t of reinforcing steel and required a continuous 17 hour 1,800m3 concrete pour. All pours relating to the turbines, were poured monolithically and were monitored with thermocouples ensuring the temperature of the curing concrete never exceed the required values. The three transformer bases were poured to a tolerance of +-3mm to provide an even surface for the transformer, and the 9m high walls surrounding the transformers were built using the EFCO formwork system. The foundations for two boilers consisted of 1,800m3 monolithic concrete pours each and were 1,500mm deep. 27,000m of drainage was laid, ranging from 100-600mm in diameter, as was various waterproof ducts for services ranging from 100-900mm. 4 cofferdams were constructed to allow the workforce to safely construct the deeper elements of the contract and 35 cable pits were constructed out of concrete and built to a watertight specification. 150m of pre-cast concrete duct troughs were laid for Electric supply cables, which were covered with specialised sand and sealed with a precast lid. Case Studies Sector Project Energy, Power & Waste / Renewable Energy Vestas Manufacturing Plant Project Overview Careys was contracted to phase one of the project for demolition and earthworks in preparation for a wind turbine site. The work was carried out adjacent to a tidal estuary and on land previously used as a cement works and which is prone to rainwater run-off from a nearby landfill site, both of which meaning that much of the removed soil was contaminated. After successful completion of phase one, Careys was contracted to work on phase two of the project, the construction of the concrete foundations, a 100m long sheet piling retaining wall adjacent to the river, and for onsite drainage. Services Project Details Client Sir Robert Mc Alpine Ltd. Location Isle of Wight, England Principal Contractor Sir Robert McAlpine Ltd Gallery Engineer / Consultant / PQS Ramboll / Davis Langdon More Information Throughout phase 1 the clients’ environmental consultants were on site to ensure that the earth was removed and dealt with in accordance with specifications. This includes installing newly created land drains for water running from the landfill site. In phase 2 the 100m retaining wall could not be constructed in the water and had to be piled on the land before the old wall was removed. Work was carried out only at low tide and no machinery was allowed in or on the water. To mitigate against this, specialized brackets were used allowing the working platform to be extended out over the river without contamination of the water. Finally, during work on the foundations two old wells were discovered and capped. was done in consultation with the client’s designer and the Environment Agency. This Case Studies Sector Project Energy, Power & Waste / Power Plant Pembroke CCGT Power Station Project Overview Careys was engaged by Alstom Power in a key section of the works on the Pembroke CCGT power station development. The project comprised of civil marine works involving heavy civil engineering works to two crucial existing structures from the previous power stations operations. This involved the demolition of existing load carrying elements and sequential reconstruction of new load carrying elements. The Careys team completed all works successfully managing to accelerate works bringing the client back in-line with their original programme which had previously slipped. Services Project Details Client Alstom Power Ltd Location Pembroke, Wales Principal Contractor Gallery Alstom Power Ltd Engineer / Consultant / PQS Halcrow and IDOM/Alstom Power Ltd More Information Careys works were across two structures the first of which is a large existing inlet pumping chamber, some 20m deep with a plan area of around 1200m2. This structure underwent large scale modification including the demolition of load carrying elements and sequential reconstruction of new load carrying elements. The second structure is the existing seal Weir chamber which consisted of a deep sequence of large culverts. Careys operations included the complete demolition of the culverts followed by the construction of a new chamber measuring some 12m in depth and with a plan area of around 900m2. The sequencing of the external wall pours along with the complex internal wall arrangement was key to the successful completion of the structure within milestone dates. Careys brought real client benefits to the project by being able to resequence the buttress removal in the existing pump chamber to improve the program, accelerating the works back to the original program for Alstom Power. Additionally Careys crushed thousands of tons of dug rock and broken concrete allowing the client to re-use later in the project. Case Studies Sector Project Energy, Power & Waste / Renewable Energy Olympic Park Energy Centres Project Overview This project consisted of two CCHP (Combined Cooling, Heat and Power) energy centres, one located within the Olympic Park supplying heat, power and chilled water to all the Olympic venues and one located within the Westfield retail development supplying heat, power and chilled water. The main plant building is 24m high with the flue structure rising to 45m – resembling a miniature version of the iconic Tate Modern Art Gallery. The second building was a retained Edwardian sweet factory building which was structurally altered by Careys to house biomass boilers and a visitor centre. Services Project Details Client Cofely GDF Suez Location London, England Gallery Principal Contractor PJ Carey (Contractors) Ltd. Engineer / Consultant / PQS Adams Kara Taylor More Information Careys installed more than 500t of steel founded on piled foundations to erect the frame of the buildings. On the Olympic Park the Energy Centres are steel framed structures founded on piled foundations incorporating heavy insitu ground floor slab and composite concrete slabs to first floor, mezzanine level and roof to accommodate heavy plant installations. The structure is clad in a waterproof membrane with an outer Corten shroud to soften the impact of the building size. Scudder was tasked with the partial demolition and enabling works for the conversion of the historic Edwardian mill. The main works included the strip out and opening up of the north side of the mill structure to host the biomass plant whilst retaining the floors in the south side and creating new stairwells and liftwells. Logistically both projects had great degrees of difficulty due to their close proximity to Network Rail lines and the CTRL box as it passes through Stratford. Considerable amounts of liaison between Careys, Network Rail and CTRL was required together with technical submissions prior to any works commencing. Additionally as the Olympic Park is considered a high security risk, access and egress for plant, materials and operatives was a very structured and controlled process. Case Studies Sector Project Transport / Aviation Heathrow Airport Project Overview Careys first appointment was on an Enabling and Main Works contract relating to general groundworks for the construction of a new control post (CP5), sitting alongside the existing live control post. This project took place part airside and part landside in a live airport environment allowing Careys to work innovatively by carrying out vacuum excavation around live services. A further Careys appointment at Heathrow was Terminal 4 Baggage Works and involved the extension of the existing baggage facility; Reclaim 8 by adding a new baggage conveyor and by removing the existing blast screen. Services Project Details Client BAA Airports Limited Location London, England Principal Contractor Gallery More Information Careys were appointed to construct The scope of works on the control point 5 security building works included foundations, services, drainage foundations for blockers and barriers (to control traffic) all within the airside of the airport. Additionally Pavement Quality (PQ) slabs, 350 thick with lean mix underneath were cut by diamond cutting saw. Foundations were excavated by hand-digging due to chartered and unchartered services/ducts present at Heathrow. A stormwater interceptor was installed along with heavy duty aco channels. Working in an airport environment carries a number of unique challenges which the Carey team are adept at tackling, from complying with the latest BAA requirements in health and safety and asset management to working on busy live sites and night time working, the team at Careys are proud to consistently deliver undisputable levels of service. The dedicated and specialist team provides the highest quality of service and continues to receive commissions from Heathrow Airport and has now recently commenced works with Vinci at Gatwick Airport. MACE Case Studies Sector Project Transport / Aviation Gatwick Airport Project Overview Due to the strength of our work at London Heathrow Airport, Vinci appointed Careys on works at Gatwick’s South and North terminal buildings. The scope of works included undertaking civil engineering for the South Terminal Forecourt Enhancement works, as well as engineering and concrete structures for the new passenger terminal interface buildings. Services Project Details Client BAA Location London, England Principal Contractor Vinci Gallery Engineer / Consultant / PQS Rarhborne & Roche More Information Works took place in a live airport environment, with off peak working hours required to work around peak traffic. Case Studies Sector Project Transport / Rail DLR 3 Package 5 Project Overview Careys was awarded the contract for the construction of reinforced concrete pile caps, columns, column heads and the new fly-under structure beneath the existing DLR Railway and above the West India Quay. The concrete was completed to a F3 finish. The scope also included the realignment and reconstruction of the existing viaduct to tie into the new structure. Services Project Details Client VINCI Construction UK Limited Location London, England Gallery More Information The project was DLR’s (Docklands Light Railway) response to increasing passenger and a desire to enable three-carriage trains to operate. Case Studies Sector Project Transport / Rail DLR 3 - Canning Town Flyover Project Overview Careys was awarded the contract for the civil engineering works on the new grade separated junction flyover at Canning Town on the Docklands Light Railway. The works include the construction of a 400m elevated reinforced concrete bridge deck (flyover structure) which comprised of a variety of steel, cast in situ concrete and precast concrete construction methods. The concrete was completed to a F3 /F4 finish. The works were carried out adjacent to the existing DLR and Jubilee line tracks and for a large part underneath high voltage National Grid cables (400,000 Volts) brining extra challenges to the works. Services Project Details Client Vinci Construction Ltd Location London, England Engineer / Consultant / PQS Arup / Vinci Construction Ltd. Gallery More Information The scope of works included the construction of reinforced concrete pile caps and piers and the installation of bridge bearings. Precast concrete diaphragm units were constructed and subsequently lifted into position with a 600t crawler crane. This crane also installed precast concrete bridge breams and GRP permanent slab formwork and precast concrete omnia planks. All associated drainage and earthworks were carried out along with these works. The project was delivered on time. The work was carried out to specification. Our own professional competent tradesmen/skilled workers were employed to carry out the works. Specialist works were carried out by others. Case Studies Sector Project Transport / Highways Magna Park & A421 Project Overview Careys secured a civil engineering contract to construct the infrastructure to serve the new Magna Park development. Works included the road widening works to convert 1.5km from a single to dual carriageway on the busy A421 Milton Keynes and the construction of a dual carriageway (Fen Street) to facilitate access to the new development. Also encompassed in the works were the provision of a foot/cycle path, two underpasses, roads, a roundabout, foul and storm drainage and services for the development. Services Project Details Client Gazely & Fen Farm Developments Location Milton Keynes, England Engineer / Consultant / PQS Capita Symonds / Davis Langdon Gallery More Information Prior to commencement, liaison took place with the police, local public transport, statutory services providers and other interested public bodies. Careys provided traffic management throughout the course of the new roadworks. The scope of works also included first phase of the site infrastructure to serve the new John Lewis distribution centre with extensive earthworks involving cut and fill and over 1.5km of combined services trench, 500m of deep foul drainage, over 2km of polyethylene storm water drainage and ductile iron water main. The contract was divided into two phases. Phase 1 involved the construction of two thirds of the length of the two cast insitu RC pedestrian underpasses. These works then had a one lane road and central reserve lain on top, as part of the 1.5km road widening of the A421. In addition, the new dual carriageway (Fenn St) and roundabout was constructed to form the entrance into the development. Case Studies Sector Project Residential & Regeneration / Residential Mixed Use Wembley Central - Building 1 Project Overview Careys was awarded this Shell & Core contract involving construction of a mixed-use retail and residential development and S278 Works. The residential apartment blocks are faced up with a combination of coloured rain screen and Sto render. The majority of apartments have attached balconies and aluminium windows. The superstructure was formed from 3,500m3 of concrete and 650t of reinforcement. To the front elevation of the project, a 12 storey RC Frame was constructed and an additional 2 floors were constructed of lightweight steel with Kingspan metal cladding to create penthouse duplex apartments with glass terraces. Services Project Details Client Sowcrest Ltd. (Joint venture between St. Modwens and Rotch Group) Location London, England Gallery Principal Contractor T.E. Scudder / P.J. Carey (Contractors) Ltd. Engineer / Consultant / PQS Nolan Associates / Dbk Goyne Adams Ltd. More Information The remaining part of the project comprises of a 2 storey retail shell with an additional 4 storey residential block constructed in lightweight steel frame above. One of the key issues was that the site was above and alongside Wembley Central Station which accommodates both Network Rail and London Underground operating companies. Careys had to submit documentation and seek permission prior to any works commencing. Both transport companies activities remained operational throughout the works. In addition, the site constraints involved working in a very busy city centre environment necessitating the need for careful consideration of public interfacing at site entrances and thoroughfares. Agreement was reached with the local authority highways engineers, as to the measures that had to be undertaken for maintaining the vehicle and pedestrian thoroughfares past the main site access points. There were also restrictions on noise and dust pollution. Careys had to carry out noise suppression measures, putting acoustic barriers around noisy plant and restricting noisy working periods to set times of the day to minimise the impact on the local residents and businesses. Case Studies Sector Project Hotel, Art & Leisure / Leisure ExCel Exhibition Centre Project Overview Careys were appointed to carry out civil engineering works at the Excel Exhibition Centre in London’s Docklands. The scope of works included; excavation to reduced level, capping and sub-base to landscape areas, installation of kerbs, granite setts, pre-cast concrete channels and drainage channels and 28,000m2 of tarmacadam. Paving was carried out to column bases and soft and hard landscaping to piazza area with cleaning, cutting & installation of insitu granite paving, a PQ concrete road, resin bound gravel paving, tactile/block paving and tree planting. Services Project Details Client Abu Dhabi National Exhibition Centre (ADNEC) Location London, England Principal Contractor Sir Robert McAlpine Gallery Engineer / Consultant / PQS McAlpine Design Group / Gardiner & Theobold More Information Concrete Works were also carried out including remedial works to existing Quay. Case Studies Sector Project Public / LA & Development Agencies Watford Fire Station Project Overview Careys was awarded a Design & Build contract for a new fire station serving South Watford. The scope of works included; the construction of a four storey landmark building with fire station and crew accommodation to the ground and first floor levels, with 2 floors of residential flats above. External facilitates, associated Section 278 works, the storage of three additional support vehicles and garaging for the three fire engines were all constructed, as was a museum building next to the fire station for memorabilia. This project was Highly Commended in the 2011 SCALA Awards for Civic Building of the Year. Services Project Details Client Hertfordshire County Council Location Watford, London Gallery Principal Contractor P.J. Carey (Contractors) Ltd. Engineer / Consultant / PQS Hurst Pierce + Malcolm / Mace More Information A ‘grey water harvester’ drainage system is used through-out the building for the toilets. Careys also introduced rain water interception tanks which enabled the fire services to use this water for training purposes rather than using filtered water. A Contiguous Piled Retaining wall on the Northern side of the site was built to maintain a footpath running alongside an existing store. The foundations for this were CFA-piled to a maximum depth of 22m. The Training and Service Yards were constructed of traditional reinforced concrete slabs with a brushed finish. Block paving was installed at the front car park of the fire station and apartments. Soft landscaping was designed to reinforce security and privacy and support footpaths to prevent shortcutting and erosion of edges. Work on the highway was carried out under a Section278 Agreement with the Watford Borough Council to realign the existing road and footpath to accommodate the fire engines access and egress. This included altering the traffic lights to accommodate for a “Green Wave” traffic signal at the junction, to give priority to the fire appliances as they approach the traffic signal. Case Studies Sector Project Public / Defence & Prison Colchester Garrison Project Overview Careys carried out a significant element of the Colchester Garrison redevelopment, a Public Finance Initiative scheme over 5 years. Careys was initially contracted to construct the basements and reinforced concrete podium slabs to two buildings circa 7,000m2, the works were completed two months early allowing the modular superstructure works to be brought forward. Careys was then awarded a design & build contract for the construction of 3 multi storey car parks totalling 750 spaces and a sports pavilion which included substructure and infrastructure works. Services Project Details Client Colchester, England Location RMPA Services Plc. Gallery Principal Contractor Sir Robert McAlpine Engineer / Consultant / PQS Beattie Watkinson Partners / EC Harris More Information Works included the demolition of existing barracks, and the installation of the drainage and 6km of ACO slot channel, gas, water services, telecom and electrical ducting. 22,000m2 of CBM was laid along with extensive hard landscaping works including 100,000m2 of PQ surfacing (brush finished concrete) and bituminous roads. 4km of footpaths and reinforced grass traffic routes were constructed and street furniture installed. Careys carried out an intensive cut and fill exercise with alterations to the existing topography. The car parks consist of structural steel frames with precast flooring and ramps, external cladding is a combination of blockwork and metal-frame windows. Soft landscaping was carried out by Careys with the installation of tree protection, reinstatement of indigenous greenbelts and construction of football pitches. The project had to be delivered to four milestone dates providing the completion of all hard and soft landscaping words in a sequenced manner in line with the clients and main contractor’s requirements. The Colchester Sports Pavilion was additional to the original contract works with Careys being appointed due to the excellent quality of work on the previous commissions. Operating throughout the UK & Ireland, the Carey Group’s Head Office is located in Wembley with further regional offices in Milton Keynes, Scotland and the Republic of Ireland. Headquarters CAREY GROUP PLC Carey House Great Central Way Wembley Middlesex HA9 0HR T 020 8900 0221 admin@careysplc.co.uk Milton Keynes CAREY GROUP PLC Chesney Wold , Bleak Hall Buckinghamshire MK6 1NJ T 01908 668383 Bristol CAREY GROUP PLC 2440 The Quadrant, Aztec West Bristol BS32 4AQ T 01454 877674 Ireland CAREY GROUP PLC Carey House Dardistown, Cloghran Co. Dublin T 00353 1 842 7300 Scotland CAREY GROUP PLC Carey House 21 Shairps Business Park Houstoun Road, Livingston West Lothian EH54 5FD T 01506 444 448 www.careysplc.co.uk