Dams and Extreme Events — Reducing Risk of Aging Infrastructure under Extreme Loading Conditions 34th Annual USSD Conference San Francisco, California, April 7-11, 2014 Hosted by San Francisco Public Utilities Commission On the Cover Aerial view of the Calaveras Dam Replacement Project taken on January 27, 2014. The San Francisco Public Utilities Commission is building a new earth and rock fill dam immediately downstream of the existing dam. The replacement Calaveras Dam will have a structural height of 220 feet. Upon completion, the Calaveras Reservoir will be restored to its historical storage capacity of 96,850 acre-feet or 31 billion gallons of water. The project is the largest project of the Water System Improvement Program to repair, replace and seismically upgrade key components of the Hetch Hetchy Regional Water System, providing water to 2.6 million customers. U.S. Society on Dams Vision To be the nation's leading organization of professionals dedicated to advancing the role of dams for the benefit of society. Mission — USSD is dedicated to: • Advancing the knowledge of dam engineering, construction, planning, operation, performance, rehabilitation, decommissioning, maintenance, security and safety; • Fostering dam technology for socially, environmentally and financially sustainable water resources systems; • Providing public awareness of the role of dams in the management of the nation's water resources; • Enhancing practices to meet current and future challenges on dams; and • Representing the United States as an active member of the International Commission on Large Dams (ICOLD). The information contained in this publication regarding commercial projects or firms may not be used for advertising or promotional purposes and may not be construed as an endorsement of any product or from by the United States Society on Dams. USSD accepts no responsibility for the statements made or the opinions expressed in this publication. Copyright © 2014 U.S. Society on Dams Printed in the United States of America Library of Congress Control Number: 2014934343 ISBN 978-1-884575-62-2 U.S. Society on Dams 1616 Seventeenth Street, #483 Denver, CO 80202 Telephone: 303-628-5430 Fax: 303-628-5431 E-mail: stephens@ussdams.org Internet: www.ussdams.org CONSTRUCTION TECHNIQUES FOR RCC PLACMENT SAN VICENTE DAM RAISE Frank Collins, P.E.1 Gerard E. Reed III, P.E. 2 Wade Griffis, P.E. 3 Jim McClain 4 Richard Burdette 5 ABSTRACT The San Diego County Water Authority (Water Authority) is near completion of raising the original San Vicente Dam, owned and operated by the City of San Diego, to provide both emergency and carryover storage to increase local reservoir supplies in San Diego County, California. The $1.5 billion Emergency Storage Project (ESP) and Carryover Storage Project (CSP) will also provide a more-flexible conveyance system, and increase water supply reliability in case of catastrophic failure to the delivery system due to a major earthquake. The San Vicente Dam Raise (SVDR) project is a major component of the last phase of the ESP and consists of raising the original 220-foot-high gravity dam with 90,063 acre-feet of storage, by 117 feet to increase reservoir storage capacity by 152,000 acre-feet. Scheduled to be completed in 2013, the SVDR will be the tallest concrete dam raise in the United States and tallest roller compacted concrete (RCC) dam raise in the world. The reservoir capacity will be more than doubled, making it the largest water storage reservoir in the region. This paper presents the unique construction, scheduling, and coordination techniques associated with placing RCC on the downstream face of the original dam. Additionally, construction techniques of dam features such as the dam crest, spillway ogee crest, parapet walls, spillway guide walls, and flip bucket are discussed. INTRODUCTION Original Dam The San Vicente Dam is located in Lakeside, CA, an unincorporated community of San Diego County. The original dam, pictured in Figure 1, constructed between 1941 and 1943, is a conventional concrete gravity dam founded on bedrock. Construction of the 1 Project Manager, Parsons, 110 West A Street, Suite 1050, San Diego, CA 92101, (858) 342-9183, Email: frank.collins@parsons.com 2 Engineering Manager, San Diego County Water Authority, 4677 Overland Avenue, San Diego, CA 92123, (858) 522-6835, Email: JReed@sdcwa.org 3 Sr. Construction Manager, San Diego County Water Authority, 4677 Overland Avenue, San Diego, CA 92123, (619) 390-2310 x3206, Email: WGriffis@sdcwa.org 4 Construction Manager, Black & Veatch Corporation, 300 Rancheros Drive, Suite 250, San Marcos, CA 92069, (760) 602-7528, Email: jmcclain@bv.com 5 Construction Engineer - Asst. Construction Manager, Parsons, 110 West A Street, Suite 1050, San Diego, CA 92101, (951) 252-3520, Email: richard.burdette@parsons.com Construction Techniques for RCC Placement 799 concrete dam was performed using an on-site batch plant and placed via an overhead cable-way. Blocks for construction of the concrete gravity dam generally consisted of 50-foot-wide by about 5-foot-thick sections and extended from the upstream face to the downstream face of the dam, consistent with dam construction methods of the time. The original San Vicente Dam had a structural height of 220 feet, with a crest elevation at 660 feet, a crest length of 963 feet, and a crest width of 14 feet. The dam contains a 275-foot-long spillway, consisting of an uncontrolled ogee-crest overflow section near the center of the dam. Figure 1. Original San Vicente Dam Prior to Dam Raise Construction Concrete aggregate for the original dam was obtained from nearby sources (canyons and creeks). The main source of aggregate consisted of Poway Conglomerate located approximately one mile from the dam site. Other sources of aggregate reported for construction material included a gravel deposit in the San Diego River as well as sand from San Vicente Creek. Two types of cement were used for the dam. The original design mix specified Type IV cement. However a second mix utilizing Type II (low alkali) cement was also used due to cement shortages during World War II. Core tests obtained during the dam raise design for compressive strength of the Type IV cement resulted in a mean average of 4,115 psi while the Type II resulted in a mean of 4,370 psi. Tensile stresses for the Type IV and Type II cement were measured to be 198 psi and 188 psi respectively. 800 Dams and Extreme Events Figure 2. Original San Vicente Dam Prior to Dam Raise Construction New Raised Dam For the new raised dam, the foundation was determined to be expanded by 75 feet downstream of the original dam with RCC placed against the downstream face and above the crest of the original dam, creating a composite, monolithic structure (see Figure 3). Figure 3. Schematic of Cross Section of San Vicente Dam The design required that the new RCC dam has the following target strength properties: • The laboratory compressive strength is 4,840 psi in two years Construction Techniques for RCC Placement 801 • The tensile strength across the RCC joint is 200 psi in two years The RCC mix consists of materials matching the original concrete as closely as possible. The selected mix was comprised of aggregates manufactured from a conglomerate deposit nearby the dam with properties very similar to the original aggregates in strength and thermal properties. The RCC ultimate compressive and tensile strength are expected to closely match that of the existing dam as well. Figure 4. San Vicente Dam Onsite Aggregate Borrow Area Construction Phasing and Contractor Selection Through lessons learned on the construction of the Olivenhain Dam Project, completed in August 2003, the Water Authority elected to package the main features of the San Vicente Dam Raise project into three separate contracts: • • • 802 Phase 1 consisting of a test quarry and test crushing. Phase 2 consisting of the preparation of the original dam to receive concrete (through hydro-demolition of the dam face, and saw-cutting of the dam crest and other features), excavation of the new dam foundation, filling cracks and crevices within the new foundation with dental concrete, and installing a new pipeline through the original dam. Phase 3 consisting of implementing curtain, check, and consolidation grouting program, focusing on manufacture and placement of RCC for the new dam, and the construction of new flow regulating structures. Dams and Extreme Events Phase 2 of the San Vicente Dam project was awarded to Barnard Construction Company (Barnard) on May 28, 2009 for a lump sum contract amount of $23,749,500 and completed on September 24, 2010. Phase 3 of the San Vicente Dam project was awarded to Shimmick/Obayashi, A Joint Venture (SOJV) on April 22, 2010 for lump sum contract amount of $140,206,050. Phase 3 is scheduled to be completed June 2014. FOUNDATION PREPARATION The geology of the site in the area of the dam excavation consisted of two types: slightly weathered granodiorite underlying the right abutment of the dam from about 5 to 20 feet deep while slightly weathered metavolcanic rock underlay the central part and left abutment of the dam and ranging from 5 to 30 feet deep. The surface layer of the excavation consists of a mixture of soil and highly weathered rock. This top layer was able to be removed during excavation with an excavator ripping loose and degraded material down to the slightly weathered bedrock. The granodiorite/metavolcanic areas below this zone was a very hard rock and was removed using conventional drill and shoot techniques. The construction procedures generally consisted of working from the top of the slope to the bottom, preparing the rock foundation. The first step of the cleaning procedure was to excavate all overburden material, and loose rock from the mass excavation. Rock fractures, faults, and shear zones were sinuous and variable in nature with some areas being difficult to identify. The onsite construction management and geotechnical staff assisted in the identification of these areas, which were treated differently than the other competent rock areas with tight seams. At these shear areas, material was excavated beyond the design elevation until competent (fresh) rock/granite was revealed or up to a depth acceptable to the Design Engineer of Record and the California Division of Safety of Dams (DSOD). The depth of excavation varied with the width of the shear zone. Per the project requirements loose material in shear zones, cavities, and seams was removed to a depth 2 times the width for a feature less than 2 inches wide, three times the width for features between 2 inches and 12 inches wide, and to a depth no greater than five feet for a feature greater than 12 inches wide. These areas were cleaned with highpressure water and/or air jets and then surface treated with grout at the time of dental concrete placement. Construction Techniques for RCC Placement 803 Two major fault areas required special treatment prior to commencement of the next foundation preparation phase. One of the faults, located on the right abutment above the top of the original dam, was oriented perpendicular to the dam axis. This fault area was excavated extensively, stepped in five-foot increments and filled in with shaping concrete (see Figure 5). The Design Engineer of Record in coordination with DSOD determined that the stair type of shaping concrete was necessary in order to buttress the upstream and downstream cuts and facilitate the placement on the steep foundation. This would allow the complete covering of the fault zone across the new dam foundation while elevating the excavated foundation grade close to the original design-intended grade and ultimately improve performance of the new dam structure. The second fault area, located on the left abutment near an original adit exit from the dam, was similarly remediated. Both faults were discovered during the original dam construction and extensively investigated prior to the new dam raise; both are classified as “inactive” according to the DSOD’s record. Figure 5. Right Abutment Foundation Shaping Concrete Placement When completed, Barnard excavated approximately 86,000 cubic yards of rock and material for the new dam foundation and 27,000 cubic yards for the saddle dam foundation. HYDRO-DEMOLITION OF DOWNSTREAM FACE In order to achieve a proper bonding surface on the downstream face of the original dam and prepare for new RCC, the Design Engineer of Record in coordination with DSOD, determined that hydro-demolition of existing concrete would be required. RCC placed against this joint would be strengthened at the interface through the use of Grout Enriched Vibratable RCC (GEVR). 804 Dams and Extreme Events The downstream face of the existing dam was prepared by removing up to three inches of surface concrete using high pressure air/water jets (20,000 psi). It was determined during design that the zone of oxidation, or “weathering” was determined to be one to two inches deep. Barnard was required to conduct three field test sections, at different locations, along the downstream face of the existing dam to demonstrate its proposed hydro-demolition equipment and methods. The first section removed one inch of material, the second two inches and the third three inches. Cores were extracted and examined petrographically to determine the appropriate depth of weathered concrete to be removed from the face of the original dam. Barnard selected American Hydro as its specialty subContractor for hydro-demolition of the downstream face. American Hydro designed and built a custom robot equipped with a single nozzle that traversed a pre-determined distance across a beam to achieve the depth of cut (see Figure 6). The depth of cut (two inches) was determined after the test sections were developed and analysis of core samples was conducted to confirm design information. Figure 6. Hydro-demolition Robotic Unit and Rail System The hydro-demolition system consisted of a five-cylinder, 20,000 psi Hammelmann highpressure pump, powered by a 1000 hp Cummings diesel engine, high-pressure delivery hoses, and the hydro-demolition robot which traversed on rails, manufactured by Fraco Products, from the bottom of the dam to the top. The rails were placed plumb on the overflow and non-overflow sections of the dam, maintaining an absolute minimum of 24inch standoff from the original concrete dam surface. The waterjet nozzle directed a high pressure water stream to the concrete to be removed. The Hammelmann pump was mounted on a trailer and needed to remain within 700 feet of the robot at all times. Construction Techniques for RCC Placement 805 The rail system was installed on the dam face by Barnard. The spacing of the rails was at a maximum of 30 feet on center and extended 5 feet above the desired cut line. The American Hydro machine performed the cuts between rails in three consecutive passes. During setup, the nozzle traversed horizontally along the rail until the programmed distance was achieved, at which time the cross feed beam advanced a prescribed distance vertically and the programmed cycle began again. The width of cut was adjusted by controlling the transverse movement of the nozzle, using sensors that were manually adjusted along the crossbar. The locations of these sensors determined the width that the nozzles would traverse; this feature was particularly useful when working on angled surfaces such as the left and right abutments. The hydro-demolition started at the spillway section (see Figure 7). The work progressed from the far right of the overflow section to the left and from the bottom to the top. When the concrete removal was completed on a rail, the rail was removed in sections prior to remounting the robot. Upon completion, Barnard hoisted the 20,000-pound robot from the completed rail to the succeeding rail located to the left. Once the rail was removed, American Hydro performed the third cut from the climber; this allowed the area to be hydro-demolished where the previous rail was placed. Figure 7. Rail Layout for Hydro-Demolition Spillway Section When completed, American Hydro hydro-demolished approximately 145,000 square feet surface area of the downstream face of the original San Vicente Dam. 806 Dams and Extreme Events RCC CONSTRUCTION This section provides a description of the RCC construction means and methods used by the Contractor to raise San Vicente dam. In addition, this section highlights issues faced during construction and provides a brief overview of the instrumentation installed during construction. Approximately 600,000 CY of RCC were placed in the Main Dam from September 12, 2011 to September 20, 2012, as shown in Figures 8 and 11. The average daily production was approximately 2,400 CY/day with a daily maximum of 6,725 CY. The monthly RCC production ranged from 4,150 CY in September 2011 to a peak of 86,195 CY in June 2012, with a monthly average of 46,303 CY. The maximum weekly RCC volume reached 36,265 CY with a weekly average of approximately 12,500 CY. Monthly RCC Placement in Main Dam 100,000 90,000 86,195 79,380 80,000 74,650 70,260 70,000 Volume (CY) 61,062 64,465 60,000 50,427 50,000 39,290 40,000 28,346 30,000 20,000 10,000 16,341 15,057 12,310 4,150 0 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 As of September 21, 2012 Figure 8. Monthly RCC Production in the Main Dam Shimmick-Obayashi Joint Venture (SOJV), the main Contractor for the SVDR, was in charge of the RCC operation. SOJV assisted by Group Delta provided the Quality Control for the RCC Construction, as well. The Construction Manager PARSONS/Black & Veatch, Joint Venture provided Quality Assurance (QA) Inspection on the RCC dam. Construction Techniques for RCC Placement 807 The RCC production plant, as shown in Figure 12 located on the South end of the Marina area consisted of two main components: cooling and batching plants. Once RCC ingredients were blended, the mix was transported via conveyor belt system to the dam where articulated trucks completed the delivery to the point of placement. RCC placements activities are summarized below: • • • • • • • • The first RCC was placed for Trial Placement on March 14, 2011. Trial Placement was complete in 11 lifts on April 1, 2011. The first RCC placement for the main dam occurred on September 12, 2011. The RCC placement for the main dam was complete on September 21, 2012. The first RCC placement for the saddle dam occurred on July 7, 2011. RCC placement for saddle dam (first phase) was complete on August 18, 2011. RCC placement for saddle dam resumed on September 24, 2012. The last RCC was placed for the saddle dam on October 4, 2012. Figure 9. RCC Trial Placement 808 Dams and Extreme Events Figure 10. First RCC Placement at Toe of Main Dam The following Table 1 shows the quantity of RCC placed, aggregate plant production and Quality Control samples: Table 1. Quantity of RCC Placed, Aggregate Plant, QC Samples RCC Placement Aggregate Plant Quality Control Item Total RCC placed for the main dam Total RCC placed for the saddle dam Number of placement shift Materials processed through Primary Plant Materials wasted at the Primary Plant Materials produced at the Primary Plant Aggregate Group 1produced at the Secondary Plant Aggregate Group 2/3 produced at the Secondary Plant Aggregate Group 4 produced at the Secondary Plant Number of density tests Number of VeBe tests Number of temperature tests Number of cast cylinders Number of gradation tests Number of Sand Equivalent tests Construction Techniques for RCC Placement Quantity 600,237 12,470 367 2,587,629 1,352,146 1,235,483 423,266 371,786 427,613 3,096 2,031 2,349 6,492 2,365 1,142 Unit Yd3 Yd3 each ton ton ton ton ton ton each each each each each each 809 As of 9/20/12 RCC Volume Placed on Main Dam Cumulative Volume 650,000 600,237 600,000 550,000 500,000 RCC Volume (CY) 450,000 400,000 350,000 300,000 250,000 200,000 150,000 100,000 Cumulative Vol. (CY) 50,000 3-Nov-12 6-Oct-12 20-Oct-12 8-Sep-12 22-Sep-12 25-Aug-12 28-Jul-12 11-Aug-12 14-Jul-12 30-Jun-12 2-Jun-12 16-Jun-12 5-May-12 19-May-12 7-Apr-12 21-Apr-12 24-Mar-12 25-Feb-12 10-Mar-12 28-Jan-12 11-Feb-12 14-Jan-12 31-Dec-11 3-Dec-11 17-Dec-11 5-Nov-11 19-Nov-11 8-Oct-11 22-Oct-11 24-Sep-11 10-Sep-11 27-Aug-11 13-Aug-11 0 Figure 11. RCC Production in the Main Dam The major challenges encountered during construction included: Maintaining minimum production rate as required by project specifications Consistently preparing the lift surface prior to RCC placement efficiently Consistently and continuously performing water curing procedure Excessive amount of unplanned (warm and cold) lift joints Multiple interruptions of fly ash delivery Consistently producing Group 4 materials that met the minimum Sand Equivalent value RCC Cooling All the cooling capacity for water and aggregate cooling was provided by a single 1,200ton centrifugal chiller as shown Figure 12. The water supplied to the chillers, wet belts, and batch plant was kept in a recycle pit or pond, capable of holding about 140,000 gallons of usable chilled water. As batch water was used for mixing, the water level at the pond decreased during the production hours. The chiller ran during non-production hours to replenish the pond. The temperature of the water in the pond was typically around 40ºF. 810 Dams and Extreme Events Project specifications required RCC to be placed at the following temperatures: Location Trial Placement Main Dam below EL 516 Main dam between EL516 and EL 587 Main Dam between EL 587 and EL 658 Main Dam above EL 658 (top of original dam) Saddle Dam Placing Temperature at or below (ºF) 60 60 62 64 68 68 The Group 4 (fine aggregate) was air cooled via a counter-current rotary cooling drum from an ambient temperature at the entrance to a target exit temperature of 63 F. After exiting the sand drum, fine aggregate was fed to the batch plant overhead bin for use. The coarse aggregates were cooled on two, 140-f00t-long “wet” belt conveyors, one belt for Group 1 (1-1/2") rock and the other for Group 2/3 (3/4") rock. Prior to entering the wet belt, the coarse aggregates were washed on high frequency wash screens. The wet belts were housed in an insulated cover to reduce ambient heat effects. The aggregates on the belt were sprayed with chilled water, which dropped the aggregate temperature to about 50°F. Total belt retention time was in the 2-3 minute range for a combination of cooling and excess water draining. Belt speed was adjustable to modify retention time, if required. The wet belt design used perforated belts for removing most of the excess water from the coarse aggregates. After leaving the belt, coarse aggregates were stored in the batch plant insulated overhead bins for use. At the beginning of the RCC production, it was observed that the excessive moisture was carried over to the overhead bins, thus the system was modified as necessary. Batching The batch plant consisted of a “Con-E-Co Lo-Pro 10” batching module modified to a nominal capacity of 500 CY/hour (based on 30-second mixing time and 6-CY batch in dual twin-shaft mixers), as shown in Figure 13. To meet mixer uniformity requirements, the mixer load was reduced to 5 CY/load and mixing time was kept at 40 seconds. After experiencing problems with the original electronic batch plant control system, the plant was equipped with a new Command Alkon Batch system. During the entire production period, the plant’s peak production rate was about 430 CY/hr. The batching section consisted of three individual aggregate overhead bins with a total capacity of 200-tons each, where cooled aggregate was stored. The plant was equipped with individual weigh batchers for each aggregate group. Weighed aggregate were transferred via a 48-inch batch transfer belt to holding hoppers located directly above the mixers. Construction Techniques for RCC Placement 811 The mixing section consisted of two 6 CY SICOMA model 7500 twin-shaft compulsory mixers, as shown in Figure 13. Above each mixer, there was a separate weigh batcher for cement and fly ash. Each weigh batcher was fed by a screw auger from the 1000-ton cement and fly ash silos. Each silo contained a 24-hour throughput capacity of bulk material. Each mixer was equipped with an individual water weigh hopper mounted above the mixer with fast and slow discharge. Once the mixing cycle was complete, the bomb bay gates discharged the mix to a conveyor belt, which, in turn, discharged it onto the main belt to the dam. Figure 12. RCC Batch Plant 812 Dams and Extreme Events Figure 13. Mixing Section with Cement and Fly Ash Silos RCC Conveying and Hauling Project specifications required RCC for the main dam to be delivered by conveyor belt as shown in Figure 14. The RCC delivery system to the main dam below elevation 642’ consisted of three main components: a) Conveyor belt from the plant to the crest of the original dam, b) 200-foot-long chute from EL. 658 to the hopper/conveyor to load trucks and, c) Articulated trucks to move RCC on the lift. Once RCC was on the dam, trucks were allowed to move it from the loading point to the point of placement. On the other hand, RCC for the trial placement or the saddle dam could be truck hauled from the batch plant to the placement area. SOJV’s original plan was to deliver RCC by conveyor belt to both the saddle and main dams. Also, their original intention was to construct the main dam first and the saddle dam later to allow the conveyor to pass through the saddle dam area for the main dam placement. The conveyor belt for the main dam would be demobilized before saddle dam construction began. However, in the end, SOJV opted to partially construct the saddle dam up to elevation 762; complete the main dam, and come back to top out the saddle dam at the end of the RCC operation. Construction Techniques for RCC Placement 813 Figure 14. General View of Conveyor System The SOJV-selected overland RCC conveyor system to the main dam consisted of a 500 ft/min mine duty Superior Industries truss framed conveyors with a nominal capacity of 1,200 tons per hour of RCC (approximately 600 CY/hour) and an approximate length of 2700 feet from the batch plant to the dam. The belt capacity was designed to handle the scheduled batch plant output. The conveyor was covered almost in its entire length for RCC temperature and moisture control. Figure 14 shows the general views of the conveyor system and the saddle dam crossing. Conveyor segments 1A, 2A, 3A, 3B, as shown in Figure 14, delivered RCC to the right abutment of the main dam. Truss frame conveyors 4A, 4B, and 4C extended down the right abutment to approximately station 3+00 to reach the top of the existing dam, as shown in Figure 15. The truss-framed conveyors (4A, 4B, 4C) were supported in three locations: at the tail end, at the middle, and at the head of the conveyor. During RCC placement, the tower supports were removed before the RCC lifts reached their foundation elevation; but the pipe bents were left within the RCC and grouted after the conveyor belts were removed. 814 Dams and Extreme Events Figure 15. Conveyors 3B through 5C Conveyors 5A, 5B, 5C, and 5D traversed across the top of the existing dam to approximately station 7+00. Conveyor 5D transferred the RCC into a 200-foot-long drop chute. The chute installed down the face of the original dam discharged the RCC onto an 18-CY hopper/conveyor unit to be used for loading trucks on the dam. The hopper/conveyor unit was mounted on a CAT D350E truck for mobility during placement. Initially, the vertical drop chute was made of a 30-inch-diameter HDPE pipe. However, this pipe did not last more than a few shifts of placement because the RCC abraded through the pipe wall. The first alternate chute system trial consisted of a shallow rectangular channel section covered with rubber conveyor belt segments. The chute system invert followed the original dam downstream profile. The shallow, square corner channel section and the misalignments of the field welded channel beams created frequent chute plugging and placement interruptions. After repeated problems, the Contractor abandoned this system. The next alternate trial chute system consisted of a 34-inch-diameter half round metal pipe covered with segments of rubber conveyor belt. In contrast to the previous chute system invert profile this chute invert profile was straight. This alignment was achieved by mounting the chute on EFCO super-stud metal supports. For easy inspection and intervention in case of plugging, the chute was covered with rubber conveyor belt sections. The new chute system introduced an additional conveyor belt segment (Conveyor 5E) at the end of the chute. Conveyor 5E was supported by an EFCO super stud structure attached to the face of the existing dam and used a vertical plastic chute at the end of the conveyor to direct the RCC stream to the trucks, as shown in Figure 16. Construction Techniques for RCC Placement 815 Conveyor 5E was shifted to higher elevation when the clearance between the conveying system and RCC lift was too short for truck loading. Figure 16. Conveyors 5 Series, Half Round Pipe Chute, and Truck Mounted Hopper 816 Dams and Extreme Events When the RCC dam construction reached elevation 642’, SOJV introduced another major change to the RCC conveying and delivery plan by deploying a 150-foot crushing plant “Thor Stacker” to deliver RCC to the trucks. The original submitted plan showed conveyor 4C dropping into the hopper/conveyor unit after the removal of conveyors 5A, 5B, 5C, and 5D from the top of the existing dam. However during construction, conveyor 4B head chute was connected to the tail hopper of the “Thor Stacker”, which then discharged RCC on the trucks. The stacker was positioned on top of a temporary base pad or top of concrete pedestals, which remained in place after stacker removal. Initially, trucks were loaded directly from the stacker belt, but after approximately elevation 658’, SOJV brought in a belly dump hopper to load the trucks as shown in Figure 17. The use of the hopper provided some surge capacity to the delivery system and helped to control excessive RCC mix segregation. Once dam construction progressed to elevation 682’, Conveyor 4C and the stacker were removed to allow conveyor 4B to drop directly into the belly dump hopper. When the dam construction progressed to elevation 688’, conveyors 4A and 4B were removed and conveyor 3B dropped RCC into the “Thor Stacker”, which discharged in the belly dump. Once the dam reached approximately elevation 730’, the stacker was jumped to the access road bench on the right abutment at approximately elevation 780’ and discharge in the belly dump hopper. The stacker remained in that position until the end of the main dam RCC operation. Due to space limitations, at about elevation 738’, lighter 25-ton capacity articulated trucks replaced the original 40-ton trucks used since the beginning of the RCC placement. When the main dam reached elevation 755’, RCC placement between the right abutment and the start of the left abutment chimney was stopped to allow the left chimney construction. To complete the left chimney, the RCC was transferred from conveyor 3B to the “Thor Stacker”, which loaded trucks via belly dump hopper positioned near the right abutment at spillway elevation 755’. The trucks hauled RCC from the hopper and dumped it on a reload conveyor belt positioned in the vicinity of the start of the left abutment. The Reload belt dumped on the tail of a second “Thor Stacker”, which loaded the single 25-ton truck hauling RCC to the final point of placement on the left abutment chimney. After completing the left chimney, placement on the right side of the spillway proceeded using the RCC conveyor belt, belly dump hopper and trucks only. The RCC was hauled from the hopper to the point of placement using one 25-ton articulated truck. RCC Placing: Depositing, Spreading, and Compacting Except for the locations with special features, such as galleries, conduit crossings, and sections above the spillway, the new dam was constructed essentially at the same elevation across its entire length and width. Typically, RCC was placed from abutment to abutment (parallel to the dam axis) for the full width of the dam. The width of the placement was covered by several RCC strips; however, the leading edge of adjacent RCC strips was typically kept at no more than 30 feet apart. Construction Techniques for RCC Placement 817 Trucks hauling RCC on the lift, deposited the material far enough from the leading edge to allow for the dozer to re-blend to minimize segregation. For most of the main dam construction, RCC was spread with a D-6 dozer equipped with an extended blade. For areas where dozer maneuverability was limited, a D-4 dozer equipped with a slope-blade was used. Occasionally a “Bobcat” was used to assist the spreading material in tight areas not accessible for the dozer and to create GEVR dikes. At the bottom of the dam, once the rock foundation was covered with RCC, placement typically proceeded from the farthest opposite end to the point of delivery. At higher elevations, as RCC lift length increased, the relative location of the chute created two “far ends” towards each abutment, with the left abutment being the farthest. For that reason, the Contractor would typically place a “pad” on the right abutment first and then move to the left abutment to complete the lift from left to right. This practice also continued when placement was conducted with the “Thor Stacker” and the belly dump hopper. Figure 17. Thor Stacker Loading Trucks via Belly Dump Hopper RCC compaction was achieved by a single drum CAT CS563 12-ton vibratory roller. Typically, two static passes and six vibratory passes were required to achieve the minimum required density. A smaller BOMAG 120 or INGERSOLL RAND double drum vibratory roller was used to compact on restricted areas and to finish the lift surface close to the forms. The conveying, hauling, depositing, spreading, and compacting equipment type and maker are shown in Table 2. 818 Dams and Extreme Events Table 2. Conveying, Hauling, Depositing, Spreading, and Compacting Equipment Function Conveying Equipment Type Maker and Model Thor Stacker Conveyor Small Stacker CAS RL 34 Reload Conveyor Volvo AD 40, John Deere 400 D Hauling Truck CAT 725, CAT 2532 Spreading Dozer Skid Steer Loading Loader Compacting Roller Plate Compactor Hydraulic Vibrator Vibrating Plate Vibrator Vacuuming Vacuum truck Brooming Mechanical brush Blower Blowing Air compressor Crane Lifting Forklift Man lifter CAT D6, CAT D4 CAT 248B CAT 980, CAT 966, CAT 936F, Komatsu WA 250 CAT CS 563, Bomag BW-211D40 Bomag 120 AD4 DD Vibratory Plate Compactor Gang Vibrators attaced to CAT 307C, Gang Vibrators attached to CAT 305CR Plate Vibrator attached to PC88MR Vermeer LP 555, Vactor 2100, Supersucker CAT 244B with Lay Mor mech. brush Mobile sweeper Billy Goat blower Atlas Copco XAS 756 Sullivan-Pallatek Grove RT870, Grove 5240, Grove RT 855, Kobelco CK 2500, Maeda LC785, Grove 58D Skytrak 10054, CAT TL 1055, Terex JLG 660 SL Note From elevation 642 to the top For Left Chimney For Left Chimney From the bottom to elevation 737 From elevation 738 to 775 For tight area For tight area For finishing GEVR For GEVR For contraction joint Grout Enriched Vibratable RCC (GEVR) The faces of the raised dam were treated using the Grout Enriched Vibratable RCC (GEVR) method. This technique was applied on a 18-24” wide band for both downstream and upstream faces, interface with the dam foundation rock, interface with the original concrete dam, and interface with the precast gallery panels. GEVR placement consisted in forming small RCC dikes by shoveling and filling them with grout as shown in Figure 18. Once the dikes had been filled with grout, RCC was pushed over the dikes to fill the area to grade. Then, gang-mounted 3½-inch, 9000 rpm hydraulic vibrators were used to consolidate the grout enriched RCC mix as shown in Figures 19 and 20. After internal vibrator application, vibratory plates and float were used to finish the GEVR surface at the downstream steps as shown in Figure 21. Construction Techniques for RCC Placement 819 Figure 18. GEVR Dikes against the Original Dam Downstream Face Grout for GEVR consisted of a mixture of water and cement with a target water/cement ratio by weight of 0.55 and an optimum range between 0.50 and 0.60. The cement for GEVR grout was the same as the one used for RCC mix. Also, grout for GEVR used the same proportions as the grout used for lift joint treatment. At Contractor’s discretion, PLASTIMENT ES manufactured by SIKA was used to control grout setting time. At the beginning of RCC placement, SOJV selected to use 7 oz/CWT, but later in the project the Contractor decided to reduce the dosage to about half the initial rate to allow for a faster GEVR hardening. Grout was produced in a standard 60-gallon grout turbo mixer equipped with a 25 tons capacity mobile cement silo. The grout plant was located outside and above of the RCC placement area so that the grout could flow by gravity through rubber hoses to the RCC placement work area. 820 Dams and Extreme Events Figure 19. Vibrating GEVR at the Downstream Steps Figure 20. Four 3.2-inch Hydraulic Vibrators on Mini Excavator Construction Techniques for RCC Placement 821 The Contractor used a magnesium float after GEVR procedure at the downstream step to create a smooth finish. Figure 21. Magnesium Float to Create Smooth Finish for the Downstream Steps Formwork Two formwork systems were used to construct the upstream and downstream faces of the dam. For smoother GEVR face and better performance during vibration, form systems were specified to be metal. The downstream form basic unit manufactured by DOKA was approximately 16 feet long by 2 feet high. The system was a multiple stage “jump” form system that relied on anchors embedded in the RCC to resist the loads. Once the RCC at the lower stage was strong enough, the form was released and installed on top of the downstream formwork system. The form “jumping” was made by crane and carpenters on the lift. The downstream formwork system was demonstrated in the trial placement. Initially the Contractor used at least four form stages, but as the dam increased in length, the number of stages dropped to three. The downstream formwork is shown in Figure 22. The upstream forms consisted of a DOKA climbing Formwork MF, which is designed for structures where formwork has to be shifted upwards in successive lifts. This formwork was used during the trial placement; however, it relied on stiff-backs and supports on the ground. On the dam, the DOKA formwork used was solely supported by 8-foot-long tiebacks with plates embedded in the RCC in the lower portion of the RCC raise section. 822 Dams and Extreme Events In the top two-thirds of the raised section, down-pins were added and driven into RCC to provide additional support to the tiebacks. The basic form unit was 12 feet long by 8 feet high. The upstream formwork was moved by a 70-ton crane (stay-on-the-lift). A picture of the upstream formwork is shown in Figure 23. Figure 22. Downstream Formwork In general, maintaining geometrical tolerances, in particular upstream, posed a major challenge for the Contractor. In one occasion, upstream surface tolerance deviations became so large that RCC placement was stopped to correct misalignments. When the upstream form encroached on the outlet tower alignment, correction to the upstream form alignment had to be made. Maintaining downstream steps quality was a challenging task for the Contractor. Stripping and “jumping” forms frequently damaged the steps. Extensive repairs were required to restore quality and maintain required line and grade tolerances. The Contractor performed significant patching work in an effort to repair the damaged stairs. Curing Project specifications required exposed RCC faces to be continuously moisture cured for 28 days after placement. Water for curing was drawn from the existing reservoir and pumped to holding tanks located above the dam crest elevation on the right abutment. For dam faces, water was delivered via sprinkler system. The Contractor elected to use workers with hoses to keep the RCC lift surface moist. Dam face and RCC lift surface Construction Techniques for RCC Placement 823 curing was a significant issue throughout RCC construction due to the frequent curing system malfunctions and non-uniform moisture coverage by hand held hoses. Figure 23. Upstream Formwork General View Lift Joint Treatment There were four lift joint categories and the lift joint treatment was determined based on the lift joint maturity, which is related to temperature and time of exposure to the environment. The joints were classified as “Hot”, “Warm”, “Cold” or “Super Cold” joint depending on the exposure duration and the ambient air temperature, which was quantified by a Modified Maturity Factor (MMF). The MMF was evaluated by accumulating the average hourly ambient air temperature on the lift in degrees Fahrenheit, minus 10.5 degrees. Air temperature on the lift was recorded by using a recording thermometer. The maturity (MMF) ranges defining each type of joint and the treatments applied to each one of them are summarized in Table 3 below. 824 Dams and Extreme Events Table 3. RCC Lift Joint Classifications and Treatments Joint Type Hot Warm Cold Modified Maturity Factor (mod ºF-hr) < 1000 1000-2500 2500-3500 Super cold >3500 Basic Treatment Cleaning with Air Vacuum/air cleaning; apply grout right before RCC placement Roller brush & low pressure washing (As established in trial placement); apply grout right before RCC placement Hydro blasting with 10,000 psi max; apply grout right before RCC placement. The most frequent joint types encountered during construction were hot or warm joints. Hot joints occurred at exposure below 1000 ºF-hr and required the minimum preparation effort, which consisted of removing all loose materials, pools of water and other foreign matter by blowing the surface off with air. Warm joints occurred at maturities between 1000 and 2500 ºF-hr and required treatment similar to hot joints with the requirement to vacuum as necessary and apply a layer of grout before the placement of the next RCC lift. Cold joints were the least common type of joint encountered during construction as they often evolved to super cold joints. Cold joints occurred between 2500 and 3500 ºFhr and, as established during the trial placement, treatment consisted of roller brush followed by a light pressure water wash, vacuum cleaning and the application of a layer of grout before the placement of the next RCC lift. Super cold joints were experienced at exposures beyond 3500 ºF-hr, which typically occurred during conveyor moves, equipment breakdown, long gallery section setup, or planned holiday. Super cold joints were treated with high pressure (10,000 psi max.) hydro blasting to expose surface aggregates, vacuum cleaning and the application of a layer of grout before placing the next RCC lift. Contraction Joints Contraction joints (CJ) in the raised dam followed the joint pattern established by the existing dam. The typical spacing for the CJ was approximately 50 feet. Contraction joints were formed by inserting a 14 gauge, 9” wide galvanized metal plate in the freshly compacted RCC lift as shown in Figure 24. Initially, the project documents required a standard 48-inch long plate; however, the Contractor requested to use plates with different lengths (48, 60, 72, and 84 inches) to better accommodate the dam width. Plate insertion was accomplished using a mini excavator with vibratory plate attachment. Sometimes, installed CJ deviated from the location specified in the project drawings and had to be corrected while the RCC was still fresh. Occasionally, trucks struck and destroyed recently inserted CJ plates, which also required immediate replacement. In total, more than 200,000 feet of CJ plates were installed during the RCC construction. Construction Techniques for RCC Placement 825 Figure 24. Contraction Joint Installation Precast Gallery Units The location of the inspection and drainage gallery in the raised dam followed the layout of the gallery in the original dam and extended into the new RCC sections. The gallery and adits were constructed using full section precast gallery units. The precast unit manufactured by US Precast Group showed minimal defects upon arrival on site. SOJV experienced problems at the beginning of the installation process, in particular in the adit main entrance and the adit leading to the Gallery Access Building (GAB). Misalignments and cracking caused during installation were the most common problems. However, once the learning curve was overcome, precast unit cracking became less frequent. Figure 25 depicts an inclined roof precast unit installed near the downstream face of the original dam. In general, inclined roof gallery sections were no major obstacle to the RCC placement equipment; however, horizontal roof gallery sections like the ones installed for the main gallery adit and the GAB branch adit at elevation 474 were an obstacle to RCC equipment (accessibility) and impacted RCC productivity. 826 Dams and Extreme Events Figure 25. Inclined Precast Gallery Unit Instrumentation The instrumentation for the Main Dam body consisted of the following items: • • • • • • Multiple-Point Borehole Extensometers (MPBX) Piezometers (Vibrating Wire and Manual Piezometers), Thermocouples Accelerometers Drainage/Seepage Flow Weir Surface Monuments Extensometers, vibrating wire piezometers and thermocouples were installed on the main dam during RCC construction. Installation of manual piezometers, accelerometer, surface monuments, and weirs were installed after RCC placement. This section provides a summary of the instrumentation installation during the RCC dam construction and data collected from the temperature instruments monitored by the CM Team (thermocouples). A three-point MPBX was installed at 45-degree inclination at STA 6+72 near the existing extensometer borehole 407 in the existing inspection and drainage gallery (elevation 468’). Extensometers EX-3, EX-4 and EX-5 were installed at depths of 70, 140, and 280 feet, respectively. The extensometer used was Model A-3 from GEOKON, which was supplied by PROUSYS and installed by Group Delta. Extensometers were monitored during construction by the designer. Construction Techniques for RCC Placement 827 A total of seven foundation vibrating wire piezometers were installed during RCC construction. In order to monitor the temperature rise in the RCC after being placed, project drawings specified the installation of several layers of Type T thermocouples at various elevations in the body of the dam. Each thermocouple layer consisted of eleven units which covered from the upstream to downstream side of the new RCC dam. Thermocouple wires were routed to an 8-inch PVC conduit embedded in the RCC. These wires ended at the reading units installed in the inspection gallery at elevation 468 in the original dam. Except by the thermocouples installed at elevation 601, which were moved one foot up, all other thermometers were installed according to plan. Due to the fluctuations observed in the Contractor’s thermocouple readings, the CM Team installed additional quality assurance (QA) thermometers to validate the Contractor’s (QC) thermocouples. These temperature loggers supplied by Intellirock, were installed and monitored by the RCC Inspection team. The temperature history curves recorded by these instruments at various elevations and offsets are shown in Figure 26. A comparison of these values with the thermal study during design indicates that they are within the range expected by the designer. The peak temperatures recorded by Contractor’s and CM Team’s thermometers in the new dam at different elevations indicates that comparable peak readings were obtained with both sets of instruments. Temperature Rise Main Dam CM Temperature Loggers at Elev. 476, 520, 601,679,720 & 740 Oct 29, 2012 130 122 120.2 120 115 110 Temperature (ºF) 108 107.6 100 96 95 95 90 89.6 86 80 70 EL 740 EL 720 60 EL 679 EL 476 EL 601 EL 520 50 0 30 60 90 120 150 Day zero is Nov. 8, 2011 5109476 MAIN DAM EL 476 STA 6+52 25 DS 8235885 SAN VICENTE 520 1 (8' from existing dam) 8235893 San Vicente 520 3 (8' from D/S) 8235887 EL 601 2 (Mid RCC section) 8235890 SAN VICENTE DAM EL 679 1 8235892 SAN VICENTE DAM EL 679 3 8235891 SAN VICENTE DAM EL 740 1 180 210 240 270 300 330 360 390 Time (Days) 5109475 MAIN DAM EL 476 STA 8+25 30 DS 8235894 San Vicente-520-2 (Mid RCC Section) 8235888 EL 601 1 (8' from existing dam) 8235886 EL 601 3 (8' from D/S steps) 8235889 SAN VICENTE DAM EL 679 2 8275905 SAN VICENTE DAM EL 720 2 8235895 SAN VICENTE DAM EL 740 2 Figure 26. CM Temperature Readings at Various Elevations and Offsets in Main Dam 828 Dams and Extreme Events Spillway, Crest Slab, and Parapet Wall San Vicente Dam is essentially an “all RCC” structure; however, some components of ancillary structures as spillway, crest slab, and parapet wall are constructed with conventional concrete. The spillway of San Vicente Dam takes advantage of the RCC downstream steps to dissipate energy and uses conventional concrete training walls to channel the water flow downstream to the flip bucket. The concrete in the training wall was typically placed with crane and bucket. Training wall placement followed RCC placement. The spillway ogee and flip bucket and training walls were constructed with structural concrete, which was delivered in mixer trucks from a concrete producer located nearby the project. The purpose of flip bucket is to deflect the flow downstream such that the energy is transferred to a position where impact, turbulence, and resulting erosion will not jeopardize safety of the dam. Conventional concrete was used to create the curve shape of flip bucket as shown in Figure 27. Figure 27. Concrete Pour for the Flip Bucket Construction Techniques for RCC Placement 829 Figure 28. Finishing Crest Slab Concrete Pour The top of the dam is one-foot-thick conventional concrete slab, also known as crest slab. On the downstream and upstream sides at the top, a three-and-half-foot-high parapet wall was also constructed from conventional concrete. A picture of in-progress crest slab construction and the parapet wall steel reinforcement is provided in Figure 28. The dam crest spillway is an ogee shape with a crest at elevation 766. A flat sloping surface connects the upstream face of the dam at elevation 756 with the upstream quadrant of the ogee at elevation 765.46. The equation for the shape of an uncontrolled ogee crest downstream from the apex to the point of tangency with the circular flip bucket is given by the USBR Standard (1987a). Steps have been designed into the ogee shape (downstream) beginning at elevation 763. The outer point of the step is on the ogee profile. A picture of in-progress crest spillway ogee construction concrete placement and steel reinforcement is provided in Figure 29. A picture of in-progress crest spillway ogee construction concrete placement and overall formwork layout is provided in Figure 30. 830 Dams and Extreme Events Figure 29. Ogee Spillway Concrete Placement Figure 30. Ogee Placement Formwork Layout Construction Techniques for RCC Placement 831 SUMMARY The presented construction, scheduling, and coordination techniques associated with placing RCC on the downstream face of the original San Vicente Dam were use to raise the original San Vicente Dam 117 feet from 220 feet to a new full height of 337 feet. The near finished full height San Vicente RCC Dam is as shown in Figure 31. Figure 31. New Full Height San Vicente Dam 832 Dams and Extreme Events