... pack a little more in-between… 04/2014 PFEIFER SEIL- UND HEBETECHNIK GMBH PFEIFER Sandwich Anchor System Dr.-Karl-Lenz-Strasse 66 87700 Memmingen PHONETechnical 08331-937-345 support Sales08331-937-290 FAX 08331-937-342 E-MAILbautechnik@pfeifer.de INTERNETwww.pfeifer.de Pack a little more in-between with the PFEIFER sandwich anchor system… 2 The PFEIFER sandwich anchor system was developed for the connection of the facing layer and load-bearing layer in sandwich elements. The application advantages of this system stand out noticeably here: Advantages for planning • General building authority approval from the German Institute of Building Technology for cylinder and flat anchors, connector pin crosses and connector pins • Insulation layer thicknesses of 400 mm S o ft w ar e • Simple dimensioning with the free PFEIFER software suite • Simple, type-tested dimensioning tables that take into consideration wind, temperature, creeping and shrinkage Advantages for precast element production •Simple and secure installation •Low additional effort for the professional installation of the insulating materials •Flat anchors can be installed directly in the joint area without cutting the insulating boards. •No drilling of insulating boards •Connector pins can simply be pushed through the insulation Advantages in precast element assembly •Trouble-free process without formal problems, since building authority approval and type-tested dimensioning tables take into consideration all necessary stresses •Load-bearing system with low deformations – minimal shifts between load-bearing and facing layer during transport and assembly Advantages in purchasing •Complete product range covers all common insulation layer thicknesses •High-quality, stable implementation in stainless steel •Constant high-quality products •Economical connector pin cross as bearing anchor solution 3 Important design/execution notes for the manufacture of sandwich elements ! 4 Manufacturing conditions When manufacturing sandwich element panels, the following recommendations should be observed in order to ensure ­high-quality production. • A low water cement ratio should be maintained when manufacturing the concrete, since otherwise considerable deformation can be expected due to shrinkage. • Cement paste and powder contents are to be kept low. Both factors have a considerable effect on the shrinkage behaviour of the facing and load bearing layers. • Excessive penetration of water into the insulation layer is prevented by high-quality insulating materials with low water absorption (for example Styrodur). Excessive absorption of water by the insulating material would negatively affect the shrinkage behaviour. • Two offset insulation layers in the joints prevent the excessive penetration of concrete slurry into the gaps between the insulating boards and thus the possible creation of cold bridges. • If only one layer of insulation is used, this should be covered with a separating foil. • Positively manufactured panels (facing layer on top during manufacture) are more favourable with regard to the overall ­deformations. The shrinkage deformations of the facing layer and the load bearing layer act in opposite directions here. • Excessive compaction is to be avoided. • Contact of the vibrator with built-in components can lead to visual marks in the facing layer. ! Storage ! Assembly position and planning • The elements should not be exposed to strong sunshine or wind influences in the first few days, since this considerably increases the uneven drying of the individual layers. • If necessary the elements should be kept moist during the first few days. • Storage under a foil in areas protected against the sun ensures a favourable drying behaviour of the concrete. When planning the sandwich elements, the subsequent alignment or position of the elements should always be considered, since this has a significant influence on exposure to the sun, etc. The danger of warping and thus the formation of cracks in the facing layer can be avoided with simple planning definitions. • Definition of a low W/C ratio as early as the planning stage. See “Manufacturing conditions” regarding this • Definition of suitable storage of the elements (see “Storage”). • The length of the facing layer should be limited in principle to 6 m, since deformations in the form of warping can be expected with larger dimensions. • A light-coloured facing layer has a beneficial effect on the temperature development during exposure to the sun. • A stronger, more rigid formation of the load-bearing layer has a positive effect on the deformations of the facing layer. • The facing layer must have a thickness of at least 7 cm in accordance with DIN EN 1992-1-1. PFEIFER Cylinder Anchor Item No. 05.380 Connection Systems Sandwich Anchor System PFEIFER Cylinder Anchor made of highquality, stainless steel. Used as a bearing anchor in the PFEIFER sandwich anchor system. Thanks to its round form it can absorb stresses in all directions. The PFEIFER Cylinder Anchor is normally used in combination with flat anchors and connector pins. Advantage: Thanks to its rotationally symmetrical form, it is ideal for use if the element is to be turned. Material: Stainless steel G K Ref. no.Type d Sheet metal t Height h mm thickness t mm mm 05.380.051.h 05.380.076.h 05.380.102.h 05.380.127.h 05.380.153.h 05.380.178.h 05.380.204.h 05.380.229.h 05.380.255.h 05.380.280.h ZA 151-1,5-h ZA 176-1,5-h ZA 102-1,5-h ZA 127-1,5-h ZA 153-1,5-h ZA 178-1,5-h ZA 204-1,5-h ZA 229-1,5-h ZA 255-1,5-h ZA 280-1,5-h 51 76 102 127 153 178 204 229 255 280 1,50 1,50 1,50 1,50 1,50 1,50 1,50 1,50 1,50 1,50 150 150 150 150 150 150 – – – – 175 175 175 175 175 175 175 175 175 175 200 200 200 200 200 200 200 200 200 200 225 225 225 225 225 225 225 225 225 225 Weight kg/100 mm Height 260 260 260 260 260 260 260 260 260 260 300 300 300 300 300 300 300 300 300 300 – – – 340 340 340 340 340 340 340 0,11 0,18 0,22 0,28 0,33 0,41 0,46 0,51 0,57 0,65 The type designation or ref. no. must be supplemented by the selected height h! Ordering example for 150 Cylinder Anchors ZA 51-1.5-175 with the ref. no. 05.380.051.175: 150 PFEIFER Cylinder Anchors ref. no. 05.380.051.175 5 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 PFEIFER Flat Anchor Item No. 05.381 Connection Systems Sandwich Anchor System PFEIFER Flat Anchor made of highquality, stainless steel. Used as a bearing anchor or retaining anchor in the ­PFEIFER sandwich anchor system. Thanks to its flat form it can absorb stresses in its longitudinal axis. Usually several PFEIFER Flat Anchors are used as bearing anchors in ­combination with retaining anchors and connector pins. Advantage: Thanks to its flat form it is ideal for installation in the insulation with no great effort. Material: Stainless steel Ref. no. Type Length l mm t mm Height h mm 05.381.080.15.h 05.381.080.20.h FLA 80-1,5-h FLA 80-2,0-h 80 80 1,5 2,0 150 – 175 – 200 200 – 225 – 260 – 280 – – – – – – – – 0,09 0,13 05.381.120.15.h 05.381.120.20.h FLA 120-1,5-h FLA 120-2,0-h 120 120 1,5 2,0 150 – 175 – 200 200 – 225 – 260 – 280 – 300 – 320 – 340 – 360 0,13 0,21 05.381.160.15.h 05.381.160.20.h FLA 160-1,5-h FLA 160-2,0-h 160 160 1,5 2,0 150 – 175 – 200 200 – 225 – 260 – 280 – 300 – 320 – 340 – 360 0,17 0,26 05.381.200.15.h 05.381.200.20.h FLA 200-1,5-h FLA 200-2,0-h 200 200 1,5 2,0 150 – 175 – 200 200 – 225 – 260 – 280 – 300 – 320 – 340 – 360 0,22 0,34 05.381.240.15.h 05.381.240.20.h FLA 240-1,5-h FLA 240-2,0-h 240 240 1,5 2,0 150 – 175 175 200 200 – 225 – 260 – 280 – 300 – 320 – 340 – 360 0,26 0,38 05.381.280.15.h 05.381.280.20.h FLA 280-1,5-h FLA 280-2,0-h 280 280 1,5 2,0 150 – 175 175 200 200 – 225 – 260 – 280 – 300 – 320 – 340 – 360 0,31 0,45 05.381.320.15.h 05.381.320.20.h FLA 320-1,5-h FLA 320-2,0-h 320 320 1,5 2,0 150 – 175 175 200 200 – 225 – 260 – 280 – 300 – 320 – 340 – 360 0,35 0,51 05.381.360.15.h 05.381.360.20.h FLA 360-1,5-h FLA 360-2,0-h 360 360 1,5 2,0 150 – 175 175 200 200 – 225 – 260 – 280 – 300 – 320 – 340 – 360 0,39 0,58 05.381.400.15.h 05.381.400.20.h FLA 400-1,5-h FLA 400-2,0-h 400 400 1,5 2,0 150 – 175 175 200 200 – 225 – 260 – 280 – 300 – 320 – 340 – 360 0,44 0,64 The type designation or ref. no. must be supplemented by the selected height h! 6 Ordering example for 100 flat anchors FLA 80-1,5-150 with the ref. no. 05.381.080.15.150: 100 flat anchors ref. no. 05.381.080.15.150 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 Weight kg/100 mm height PFEIFER Anchor Pins Item No. 05.382 Item No. 05.383 Item No. 05.384 Connection Systems Sandwich Anchor System PFEIFER Anchor Pins made of highquality, stainless steel are used as shear connectors in the PFEIFER sandwich anchor system. They are intended for the connection of the load bearing and facing layer and for absorbing axial stresses in insulated concrete sandwich panel elements. PFEIFER Connector Pins are usually distributed in an even pattern over the entire area of the sandwich panel. The VN connector pins can alternatively be used as retaining and bearing anchors in the connector pin cross. Advantage: Simple installation thanks to idealised design. Material: Stainless steel Connector pin $QVWHFNEJHO 9HUEXQGQDGHO Clip-on stirrup Clip-on pin $QVWHFNQDGHO Connector pin Ref. no. Type b mm d mm 05.382.40.h VN-4,0-h 05.382.50.h VN-5,0-h 05.382.60.h VN-6,0-h 43 45 47 4,0 5,0 6,0 Clip-on pin Ref. no. b mm d mm 43 45 52 4,0 5,0 6,0 b mm d mm 48 55 72 4,0 5,0 6,0 Type 05.383.40.h AN-4,0-h 05.383.50.h AN-5,0-h 05.383.60.h AN-6,0-h Clip-on stirrup Ref. no. Type 05.384.40.h AB-4,0-h 05.384.50.h AB-5,0-h 05.384.60.h AB-6,0-h Height h mm 160 200 220 180 220 240 200 240 260 220 260 280 240 280 300 260 300 320 280 320 340 300 340 360 320 360 380 – 380 400 – 400 420 – – 440 – – 460 – – 480 – – 500 – – 520 – – 540 – – 560 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – Height h mm 160 160 200 200 200 240 240 240 280 280 280 320 – 320 360 – 360 380 – 380 400 – 400 420 – 420 – – – – Height h mm 160 160 200 200 200 240 240 240 280 280 280 320 – 320 360 – 360 380 – 380 400 – 400 420 – 420 – – – – The type designation or ref. no. must be supplemented by the selected height h! 7 Ordering example for 2000-off AN-4.0-220 with the ref. no. 05.383.40.220 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 Instructions for installation and use System FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS Ansteckbügel AB AN Clip-on Stirrup Zylinderanker ZYA Cylinder ZYA Anchor The PFEIFER sandwich anchor system always consists of load-bearing and retaining anchors as well as connector pins and clip-on pins or stirrups. It is intended for the load-bearing connection of the facing and load-bearing layers of concrete sandwich panels. Cylinder anchor, flat anchor and connector pin cross can each act as a bearing anchor. Flat anchors or a connector pin cross are always to be provided for as retaining anchors. Clip-on stirrups, clip-on pins or connector pins can be used as anchor pins. VNVerbundnadel Connector Pin VN otice: no more than one cylinder anchor may be built into each N ­element. Flachanker FLA FLA Flat Anchor VB Clip-on Pin Anstecknadel AN VNK Connector PinVNK Cross Verbundnadelkreuz Use FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS Possible load-bearing systems Dimensioning FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS Definitions: Bearing anchor Shear connector The bearing anchors are intended for the transmission of the dead weight of the facing layer into the load-transmitting load bearing layer. Cylinder and flat anchors or the connector pin cross can be used. They must always be installed without stresses. In order to absorb stresses that act at a right angle to the surface of the facing layer (e.g. wind), shear connectors must be arranged in a defined pattern. Connector pins, clip-on pins and clip-on stirrups can be used here. Retaining/torsion anchor When using a cylinder anchor located at the centre of gravity as a bearing anchor, it is necessary to arrange a torsion anchor to prevent the rotation of the facing layer with respect to the load-bearing layer. When using two or more bearing anchors, a retaining anchor must be installed in order to avoid horizontal shifts. In both cases flat anchors or the connector pin cross can be used. 88 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 Notice: A reinforced normal concrete of the strength class C30/37 to C50/60 according to DIN EN 206-1:2001-07 is to be used for both the facing and load bearing layer. Dimensioning Nachweis: FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS VEd, Anchor ≤ VRd, Anchor VEd, anchor [kN]:stress due to transversal shear force from dead weight Facing layer per anchor VRd, anchor [kN]:dimensioning value per anchor according to type-approved table otice: Both documents, approval and type-approved N dimensioning tables must always be taken into account in the dimensioning. Notice: Type-tested tables are available for the dimensioning that enable verification taking only the dead weight of the facing layer into consideration. Effects in accordance with “General dimensioning information” are taken into consideration here. otice: Tables are available for each combination of facing layer/ N insulation thickness, building height and wind zone. These tables are available from www.pfeifer.de or as part of the free dimensioning software. General dimensioning information Wind pressure/wind suction: SchleswigHolstein MecklenburgVorpommern Hamburg Bremen Brandenburg Niedersachsen Berlin SachsenAnhalt NordrheinWestfalen Sachsen Thüringen Hessen RheinlandPfalz Saarland The stress due to wind suction/pressure always acts perpendicularly to the surface of the facing layer and thus generates tensile/compressive forces in the anchoring elements. Windzone 4 Prerequisite: Windzone 3 Topographical building location: ≤ 800 m above sea level Height/width ≤ 3,0 Windzone 2 ratio h/d: Windzone 1 Table 1: Velocity pressures Wind zone 1 Inland Inland 2 Coast and islands in the Baltic Sea Inland 3 Coast and islands in the Baltic Sea Inland Coast of the North Sea 4 and Baltic Sea, islands in the Baltic Sea Islands in the North Sea Velocity pressure qp at building height h h ≤ 10 m 10 m < h ≤ 18 m 18 m < h ≤ 25 m 0,50 kN/m2 0,65 kN/m2 0,65 kN/m2 0,75 kN/m2 0,80 kN/m2 0,85 kN/m2 1,00 kN/m2 0,90 kN/m2 1,10 kN/m2 0,80 kN/m2 0,95 kN/m2 1,05 kN/m2 1,20 kN/m2 0,95 kN/m2 1,15 kN/m2 1,25 kN/m2 1,40 kN/m2 1,40 kN/m2 – 1,10 kN/m2 1,30 kN/m2 1,30 kN/m2 1,55 kN/m2 – Bayern BadenWürttemberg Windzone 4 Windzone 3 - Windzone Wind zone44 MecklenburgWindzone Wind zone33 Vorpommern Windzone Wind zone22 Windzone Wind zone11 Windzone 2 gn Temperatures: Creep/shrinkage: The external sides of a sandwich element are exposed to different thermal stresses.Berlin On the inside, constant temperatures should be set over the entire year. These different influences can lead to the following deformations: Influences arising from temperature and shrinkage are taken into consideration by a corresponding temperature gradient in the facing layer. Effects arising from wind were also assessed in the context of the type approval. Windzone 1 Brandenburg enburg Notice: The velocity pressures were taken from DIN 1990/NA: 2010-12, table NA.B.3 (simplified velocity pressures for buildings up to 25 m) and apply to heights of the building location up to 800 m above sea level. SachsenBerlin Anhalt a) Change of length of the facing layer due to a temperature change b) Warping of the facing layer due to the temperature gradient within the cross-section Thüringen Hence, Sachsen a relative deformation of the facing layer and the interior load bearing layer results, which stresses the existing anchors. Sachsen 99 Bayern © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 Dimensioning FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS The following static models can be applied: Without rotation of the element: 1 2 / / 3 4 / / 5 + + + + $ 5 $ 5 Determination of the stress for bearing anchors 1 VEd = L · H · V · 2 VEd = L · H · V · 25 kN/m3 · 1,35 2 3 VEd = L · H · V · 25 kN/m3 · 1,35 [L · H · V · 25 kN/m3 · 1,35] · 0,1 · L +Q ; Q= 2A 4 VEd = L · H · V · 25 kN/m3 · 1,35 [L · H · V · 25 kN/m3 · 1,35] · 0,1 · L +Q ; Q= 2A 25 kN/m3 Variables: L=length of facing layer H=height of facing layer V=thickness of facing layer A=distance between bearing anchors R=distance between torsion anchor and edge All dimensions in m! · 1,35 Determination of the stress for retaining anchors/torsion anchors 0,05 · L 1 VEd, Torsion = 2 No retaining/torsion anchors required 3 VEd, Retaining = 0,1 · [L · H · V · 25 kN/m3 · 1,35] 4 VEd, Retaining = 0,1 · [L · H · V · 25 kN/m3 · 1,35] 0,45 · L – R aution: The stresses C determined here via the dead weight alone must be compared with the typeapproved design resistance. Comparison with the approval values leads to reduced safety extending even to failure of the anchor system. · [L · H · V · 25 kN/m3 · 1,35] With rotation of the element: 1 5 2 / + / + 3 + 4 / + $ aution: In the case of rotation of the elements, the determination of C the retaining/torsion anchors can be dispensed with. Instead, the bearing anchors are arranged in both axes. Disregard can lead to damage extending even up to failure of the anchoring system. 10 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 $ $ $ / otice: When dimensioning with two bearing anchors with different N distances to the centre of gravity, they must be taken into account according to the ratio and the anchor stress. Installation ZA Cylinder Anchor 1 FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS Reinforce the facing layer and fix the cylinder anchor to the reinforcement 2 Position the cylinder anchor on the surface reinforcement and if necessary cut through individual bars of a mesh reinforcement. Replace individual bars that have been cut through with additional reinforcement with the same crosssectional area. Push anchoring reinforcements in accordance with table 2 perpendicular to each other through the round holes in the cylinder anchor. Rotate the cylinder anchor with the anchoring reinforcement by 45°, thus clamping the anchoring reinforcement over or under the reinforcement layer. otice: Adhere to the embedment depth of the cylinder anchor N in the facing layer in accordance with table 1! 3 Concrete and compact the facing layer 4 Notice: cylinder anchors may not shift! Install the thermal insulation Cut the thermal insulation to size according to the anchor dimensions and install it. The internal area of the cylinder anchor must be sealed with a suitably shaped piece of thermal insulation. Hollow spaces between the thermal insulation and the anchor are to be avoided. If necessary hollow spaces must be filled with a suitable thermally insulating foam. Reinforce the load bearing layer 6 5 Install and position the surface reinforcement and if necessary cut through individual bars of the mesh reinforcement. Replace individual bars that have been cut through with additional reinforcement with the same cross-sectional area. 1 Fix the cylinder anchor to the reinforcement Push anchoring reinforcements in accordance with table 2, at an angle of 45° to the surface reinforcement and perpendicular to each other, through the round holes in the cylindrical anchor. Then fasten to the reinforcement of the load bearing layer with tying wire to fix the position. 7 Concrete and compact the load bearing layer otice: As an alternative to figures 1 to 7, you can start by manu­ N facturing the load bearing layer and then concrete the facing layer in the last manufacturing step. The procedure must take place ­analogously. 8 Table 1: Minimum embedment depths ev [mm] and eT [mm] Thickness of facing layer V [mm] 70 80 90-120 Thickness of thermal insulation layer D [mm] 30 – 90 55 60 60 100 – 200 60 65 70 11 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 Installation ZA Cylinder Anchor FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS Table 2: Anchoring reinforcement for cylinder anchor (through round hole) Installation method Type Anchoring rods B500 A/B 51-1,5 2 x 2 Ø 6 mm, L = 500 mm 76-1,5 102-1,5 127-1,5 153-1,5 178-1,5 204-1,5 229-1,5 255-1,5 280-1,5 2 x 4 Ø 6 mm, L = 700 mm * In case of a facing layer thickness of V = 70 mm, the additional reinforcement is to be executed in stainless steel for reasons of corrosion protection or the concrete quality must be increased. Table 3: Minimum reinforcement of the concrete layers Reinforcement: Reinforcing steel bar DIN 488-B500A/B, reinforcement mesh DIN 488-B500A/B or made of stainless steel Facing layer Facing or load bearing layer V < 100 mm V ≥ 100 mm bzw. T ≥ 100 mm Minimum reinforcement, single-layer, central as ≥ 1.88 cm²/m per direction (e.g. Q188) Minimum reinforcement, two-layer, near to surface as ≥ 1.88 cm²/m per direction and layer (e.g. Q188) Table 4: required anchor height h =$&\OLQGHU$QFKRU )/$)ODW$QFKRU F V 50 60 70 200 mm 80 90 225 mm 40 175 mm 70 80 90 100 110 120 Thickness of thermal insulation layer D [mm] 30 150 mm Thickness of facing layer V [mm] 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 mm 340 mm Table 5: Minimum axis and edge distances middle diameter d 51 – 102 mm c1.min / c2.min [mm] 300 400 s1.min / s2.min [mm] 500 600 F F 300 mm 3RLQWRIUHVW )L[HGSRLQW 12 12 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 127 – 280 mm not available Installation FLA Flat Anchor 1 FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS Reinforce the facing layer and fix the flat anchor to the reinforcement 2 Bend the outer anchoring reinforcements by 30° - 35° (table 1) and push them through the round holes. Then position the flat anchor on the surface reinforcement and if necessary cut through individual bars of the mesh reinforcement. Replace individual bars that have been cut through with additional reinforcement with the same cross-sectional area. Fold the bent anchoring reinforcements by 90° onto the surface reinforcement. Then push the straight anchoring reinforcements in accordance with table 1 through the round holes. Arrange the straight anchoring reinforcements underneath the surface reinforcement. 3 Fix the bent anchoring rods to the surface reinforcement by means of tying wire. Adhere to the embedment depth of the flat anchor in the facing layer! 4 Concrete and compact the facing layer otice: Flat anchors must not shift during the concreting/ N compaction! otice: The embedment depth of the flat anchor in the facing layer N must be adhered to in accordance with the valid building authority approval. 5 Install the thermal insulation 6 Cut/slit the thermal insulation to size according to the anchor dimensions and install it. Avoid hollow spaces between the thermal insulation material and the anchor; fill with suitable thermally insulating foam if necessary. Reinforce the load bearing layer Install and position the surface reinforcement and if necessary cut through individual bars of the mesh reinforcement. Replace individual bars that have been cut through with additional reinforcement with the same cross-sectional area. 7 Fix the flat anchor to the reinforcement 8 Thread in the bent anchoring reinforcement. Push the straight anchoring reinforcement through the round holes. Fix the reinforcement to the load bearing layer reinforcement Concrete and compact the load bearing layer otice: As an alternative to figures 1 to 7, you can start by N manufacturing the load bearing layer and then concrete the facing layer in the last manufacturing step. The procedure must take place analogously. 9 Embedding depth Facing layer: eV = 55 mm Load bearing layer: eT ≥ 55 mm otice: The embedment N depth eT depends on the height of the flat anchor and is determined as follows: eT = h – D – 55 mm 13 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 Installation FLA Flat Anchor FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS Table 1: Installation method and reinforcement Installation method Length L mm Anchoring rodsB500 A/B 80 2 x 4 Ø 6 mm where L = 400 mm 2 x 5 Ø 6 mm where L = 400 mm 2 x 6 Ø 6 mm where L = 400 mm 2 x 7 Ø 6 mm where L = 400 mm 120 160, 200 240, 280 320, 360, 400 * In case of a facing layer thickness of V = 70 mm, the additional reinforcement is to be executed in stainless steel for reasons of corrosion protection or the concrete quality must be increased. Table 2: Minimum reinforcement of the concrete layers Reinforcement: Reinforcing steel bar DIN 488-B500A/B, reinforcement mesh DIN 488-B500A/B or made of stainless steel Facing layer Facing or load bearing layer V < 100 mm V ≥ 100 mm bzw. T ≥ 100 mm Minimum reinforcement, single-layer, central as ≥ 1.88 cm²/m per direction (e.g. Q188) Minimum reinforcement, two-layer, near to surface as ≥ 1.88 cm²/m per direction and layer (e.g. Q188) Table 3: required anchor height h Thickness of facing 30 layer V [mm] 70-120 Thickness of thermal insulation layer D [mm] 40 150mm 50 60 70 175mm 80 90 200mm 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 225mm 260mm 280mm 300mm 320mm 340mm 360mm Table 4: Minimum axis and edge distances Anchor length L 80 – 400 mm c1.min / c2.min [mm] 300 s1.min / s2.min [mm] 500 F V V V V F F F 14 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 3RLQWRIUHVW )L[HGSRLQW HPD[ HPD[ otice: The maximum N distances to the point of rest of movement are to be taken from the currently valid building authority approval. Installation VNK Connector Pin Cross 1 FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS 2 Reinforce, concrete and compact the facing layer Then install the thermal insulation. 3 4 5 6 Reinforce the load-bearing layer and install the VN Connector Pins. Complete the installation of the connector pins at the latest 60 min after addition of the mixing water. The first connector pin must be inserted at an angle of 45° over a reinforcement cross through the thermal insulation layer into the fresh concrete of the facing layer. The crossing point of the two connector pins must lie in the centre of the thermal insulation layer. Once the tip of the pin has reached the base of the formwork, the pin must be pulled back to the required embedment depth according to fig. 8. Insert the second connector pin at an angle of 45° and perpendicular to the pin inserted first over a reinforcement cross through the thermal insulation layer into the fresh concrete of the facing layer. Once the tip of the pin has reached the base of the formwork, the pin must be pulled back to the required embedment depth according to fig. 8. 1 7 ' 9 Load bearing 7UDJVFKLFKW layer 8 PP P P PP P P / 91 . Facing layer 9RUVDW]VFKLFKW 7 Compact the facing layer and then concrete and compact the load bearing layer. VN9HUEXQG Connector PinQDGHO91 otice: As an alternative to the illustrations, you can start by N manufacturing the load bearing layer and then concrete the facing layer in the last manufacturing step. The procedure must take place analogously. 15 15 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 Installation VNK Connector Pin Cross FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS Table 1: Minimum reinforcement of the concrete layers Reinforcement: R einforcing steel bar DIN 488-B500A/B Reinforcement mesh DIN 488-B500A/B or made of stainless steel Facing layer Facing or load bearing layer V < 100 mm V ≥ 100 mm bzw. T ≥ 100 mm Minimum reinforcement, single-layer, central as ≥ 1.88 cm²/m per direction (e.g. Q188) Minimum reinforcement, two-layer, near to surface as ≥ 1.88 cm²/m per direction and layer (e.g. Q188) Table 2: required connector pin height h Thickness of facing layer V [mm] 30 70-120 220 mm Thickness of thermal insulation layer D [mm] 40 50 240 mm 60 70 80 260 280 mm mm 90 300 mm 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 320 mm 340 mm 360 380 mm mm 400 mm 420 mm 440 mm 460 480 mm mm 500 mm 520 540 mm mm Table 3: Minimum axis and edge distances Diameter of connector pin cross cll, min1) [mm] c⊥, min2) [mm] sll, min1) [mm] s⊥, min1) [mm] VNK 6 VNK 5 0,5 · hD + 200 200 hD + 400 400 2) transverse to load direction in load direction s1 ≥ s⊥, min s2 ≥ max (s⊥, min ; s⊥, min) 1) 16 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 F V V F F 3RLQWRIUHVW )L[HGSRLQW HPD[ HPD[ F otice: The maximum N distances to the point of rest of movement are to be taken from the currently valid building authority approval. Installation VN Connector Pin FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS 1 2 Reinforce, concrete and compact the facing layer Then install the thermal insulation and reinforce the load bearing layer. 3 4 Install the connector pins Insert the connector pins through the insulation at the latest 60 min after addition of the mixing water. Ensure here that the pin is pushed exactly above a reinforcement cross in the mesh and into the fresh concrete layer of the facing layer. The facing layer must then be compacted again. 5 6 Load bearing layer 7UDJVFKLFKW 7 H7 Concrete and compact the load bearing layer Caution: The required embedment depths according to fig. 6, table 2 are to be adhered to. ' H9 9 9RUVDW]VFKLFKW Facing layer PP AN Clip-On Pin 8 7 H EeHrU QnJt upRp cHeKmU Xe Z r %foH rein Fixing the clip-on pin to the facing layer reinforcement: To do this the pin must first be inserted into the upper reinforcement layer and then stood upright. The pin then only needs to be turned clockwise above the lower reinforcement in order to fix it. rei%n XloQwW HeUHr rHcKeU X mQeJ nt HfoZ 9 10 Alternative fixing method: re%i uRpEpHeU nHfZo Hr rHcKeU XmQ eJn t er nt HwUH Je XQloW HKrcU XeQm nZfo r%eHi Alternatively the pin can be fixed with a pin or a nail. To do this the clip-on pin must be guided around the upper reinforcement, stood upright and the nail/pin for fixing inserted laterally. 17 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 Installation AB Clip-on Stirrup 11 rein REuHpUH %fHoZ per rcHeK mU Xe QnJt FOR PLANNERS, FOR PRECAST COMPANIES, FOR USERS 12 Fixing the clip-on stirrup: HUeHr XlQoWw QJent HKcUeXm %iHnZfor For fixing, the clip-on stirrups are initially clamped with the open end of the pin to the upper reinforcement of the mesh. Afterwards the stirrup is stood upright at the reinforcement cross. By pressing together and turning anticlockwise, the stirrup fixes itself by engaging with the lower reinforcement. re 13 14 Insulation and load bearing layer: After the mounting of the clip-on pin/stirrup, the facing layer is concreted and compacted. The thermal insulation is now pressed over the pin or, if using the stirrup, the insulation must be recessed. Afterwards the load bearing layer can be reinforced. 15 F V H P D[ Finally the load bearing layer is concreted and compacted. F V Table 4: Minimum axis and edge distances 3RLQWRIUHVW )L[HGSRLQW VN c1,min / c2.min [mm] s1.min / s2.min [mm] =$&\OLQGHU$QFKRU ZA Cylinder Anchor 91$1$% VN/AN/AB VN Connector Pin / AB Clip-on Stirrup / AN Clip-on Table 1: Minimum reinforcement of the concrete layers Reinforcement: R einforcing steel bar DIN 488-B500A/B Reinforcement mesh DIN 488-B500A/B or made of stainless steel Facing layer Facing or load bearing layer V < 100 mm V ≥ 100 mm bzw. T ≥ 100 mm Minimum reinforcement, single-layer, central as ≥ 1.88 cm²/m per direction (e.g. Q188) Minimum reinforcement, two-layer, near to surface as ≥ 1.88 cm²/m per direction and layer (e.g. Q188) Table 2: Minimum embedment depths [mm] VN AN AB ev ≥ 60 V/2 + ØAN V/2 + ØAB eT ≥ 60 ≥ 65 ≥ 60 otice: The maximum distances to the point of rest of movement are N to be taken from the currently valid building authority approval. 18 © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 AN ≥ 100 ≥ 200 AB Storage otice: Store all components of the PFEIFER sandwich anchor N ­system dry and protected. aution: Stainless steel anchors can be damaged by the effects of C acids, road salt, sea water or also storage in areas where normal steel is processed. Anchors that are already damaged may not be used. Ensure protected storage! Notices Notizen www.pfeifer.de © 2007 Copyright, PFEIFER, 87687 Memmingen / Technical modifications and errors excepted. Status 04/2014 19 Lifting Anchor Systems Thread System J&P Sales Department Connecting and Lifting Systems in Germany Lifting Anchor Systems BS Anchor System Lifting Anchor Systems WK Anchor System Fixing Systems DB Anchor 682 for Permanent Fixing Fixing Systems Socket Dowels Polyamide Sockets Connection Systems Concrete Earthing System BEB Reinforcement Systems PH Reinforcement Continuity System Cable Tension Members Tension Rod System Attachment Materials (Wire Ropes, Chains, Textiles) Lashing Systems Grabs for Reinforcing Steel Balancing Spreader Beams This document is superseded when a new edition appears at www.pfeifer.de. O I T A C O U Reinforcement Systems VS ®-Wire Rope Loop System O Connection Systems Sandwich Anchor System Delta Anchor System in Austria L Connection Systems Stell Bearing Staircase Bearing VarioSonic R Connection Systems Column Shoe System Wall Shoe System N S Fixing Systems HK Assembly Anchor System Nobelstraße 51-55 D-12057 BERLIN Tel. 030-68283-02 Fax 030-68283-497 E-Mail info@jordahl.de Internet www.jordahl.de Am Güterbahnhof 20 D-79771 KLETTGAU Tel. 07742-9215-20 Fax 07742-9215-90 E-Mail klettgau@jp-bautechnik.de Internet www.h-bau.de Fundlandstraße 29 D-45326 ESSEN Tel. 0201-28966-0 Fax 0201-28966-20 E-Mail essen@jp-bautechnik.de Hamburger Ring 1 D-01665 KLIPPHAUSEN/Dresden Tel. 035204-215-11 Fax 035204-215-18 E-Mail dresden@jp-bautechnik.de Markircher Straße 14 D-68229 MANNHEIM Tel. 0621-4840340 Fax 0621-4840344 E-Mail mannheim@jp-bautechnik.de Lechstraße 21 D-90451 NÜRNBERG Tel. 0911-6427808 Fax 0911-6428472 E-Mail nuernberg@jp-bautechnik.de Pfeifer Seil- und Hebetechnik GmbH Klaus Neuhauser Gebietsverkaufsleitung Österreich Bautechnik Dr.-Karl-Lenz-Straße 66 D-87700 Memmingen Telefon: +43 (0)664-88311458 Email: kneuhauser@pfeifer.de in Denmark JORDAHL & PFEIFER BYGGETEKNIK A/S Risgårdevej 66, Risgårde DK-9640 FARSØ Tel. +45-9863-1900 E-Mail info@jordahl-pfeifer.dk in France JORDAHL H-BAU FRANCE SARL (siège) 7, rue des Vallières Sud 25220 CHALEZEULE Tél +33-3 81 25 04 65 Fax +33-3 81 25 07 96 E-Mail info@jordahl-hbau.fr in Spain PFEIFER Cables y Equipos de Ekvacion, SLV. Avda. de los Pirineos, 25 – Nave 20 San Sebastián de los Reyes ES-28703 MADRID Tel. +34-916593185 Fax +34-916593139 E-Mail jp@jp-anclajes.com ES-08820 BARCELONA Tel. +34-93-3741030 Fax +34-93-3741459 in Russia OOO PFEIFER KANATI & PODJÖMNIE TEHNOLOGII RU-119017 MOSCOW Pyzhevskiy pereulok, h.5, bld.1, office 108 Tel. +7-495-363-01-27 Fax +7-495-363-01-28 E-Mail info@pfeiferrussia.ru Our products are sold by: in Ukraine JORDAHL&PFEIFER TECHNIKA BUDOWLANA ul. Pawłyka 17a 76-018 IVANO-FRANKIVSK Tel. +38067442-85-78 (Eastern Region) Tel. +38067442-85-79 (Western Region) E-Mail info@j-p.com.ua in Hungary PFEIFER GARANT KFT. Gyömröi út 128 HU-1103 BUDAPEST Tel. +36-1-2601014 Fax +36-1-2620927 E-Mail info@pfeifer-garant.hu in Singapore J&P BUILDING SYSTEMS PTE LTD. No. 48 Toh Guan Road East #08-104 Enterprise Hub SG-SINGAPORE 608586 Tel. +65-6569-6131 Fax +65-6569-5286 E-Mail info@jnp.com.sg in Brazil PFEIFER CABOS DE AÇO E SISTEMAS DE IÇAMENTO LTDA. Rua da Regeneração, 465 21040-170 RIO DE JANEIRO Tel. +55-21-2560-0673 E-Mail info@pfeifer-brasil.com in the UAE EMIRATES GERMAN BUILDING MATERIALS TRADING (LLC) P. O. Box 18917 UAE-DUBAI Tel. +971-4-2676644 Fax +971-4-2676646 E-Mail gemirate@emirates.net.ae in Switzerland PFEIFER ISOFER AG Hasentalstraße 8 CH-8934 KNONAU Tel. +41-44-7685555 Fax +41-44-7685530 E-Mail info@pfeifer-isofer.ch in the United Kingdom J&P BUILDING SYSTEMS LTD. Unit 5 Thame Forty Jane Morbey Road GB-THAME, OXON OX9 3RR Tel. +44-1844-215200 Fax +44-1844-263257 E-Mail enquiries@jp-uk.com in Czechia JORDAHL & PFEIFER STAVEBNI TECHNIKA S.R.O. Bavorská 856/14 CZ-15500 PRAHA 5 Tel. +420-272700701 Fax +420-272703737 E-Mail info@jpcz.cz in Romania S.C. JORDAHL & PFEIFER TEHNICÃ DE ANCORARE S.R.L Str. Malului Nr. 7, et.1 RO-550197 SIBIU JUD. SIBIU Tel. +40 269 246 098 Fax +40 269 246 099 E-Mail info@jordahl-pfeifer.ro in Poland JORDAHL & PFEIFER TECHNIKA BUDOWLANA SP. Z O.O. ul. Wrocławska 68 PL-55-330 KREPICE k/Wrocławia Tel. +48-71-3968264 Fax +48-71-3968105 E-Mail biuro@jordahl-pfeifer.pl For all other export countries please contact our headquarters in Germany. 02.14 AB/MA 180236 Headquarters PFEIFER SEIL- UND HEBETECHNIK GMBH Dr.-Karl-Lenz-Straße 66 D-87700 MEMMINGEN Telefon +49(0)8331-937-312 Telefax +49(0)8331-937-342 E-Mail export-bt@pfeifer.de Internet www.pfeifer.de