Determining Currents of Cable Sheaths by means of Current Load Factor and Current Reduction Factor I. Sarajcev, M. Majstrovic, Member, IEEE, and R. Goic Abstract- A new method for determining sheath currents as the consequence of electromagnetic coupling during line-toground short circuit is described in this article. This method is based on using both the current load factor and the current reduction factor. The model cables are selected to represent major constructions encountered in practice. The cable line consists of three single-core cables laid in trefoil formation and touching each other. Cable sheaths are grounded at both ends. Current load factor and current reduction factor are characteristic data of the analyzed cable line. The method presented in this paper is easy to use. p I d , p I i - positive and negative sequence components of the sheath current of the single-core cable L1, respectively, The factor k depends on the current that flows through the earth. It is calculated as follows, [2]: k= Ie 3 Io (2) where Key words- Cable, current, current factor, load factor, sheath, sequence component I. INTRODUCTION Line-to-ground short circuit is an unsymmetrical fault. Currents and voltages can be shown by sequence component phasors. Sequence components of currents flow through phase conductors and through the other active parts of the transmission network. The cable line is an element of the direct-grounded transmission network and consists of three single-core power cables. Their conductive sheaths are grounded at both ends. Currents through cable sheaths flow during line-to-ground short circuit. These currents consist of two components. The first component occurs as the consequence of increased potential of grounding grids. The second component occurs as the consequence of electromagnetic couplings and is analyzed in this paper. So far many methods have been developed to calculate these currents. We propose a new method based on both the current load factor of the cable sheath ( ξ ) and the current reduction factor of the cable line ( k ). The proposed method is presented in this paper. Calculation of the factor ξ is presented in [1]. It is calculated for symmetrical three phase currents (positive and/or negative sequence components) of the analyzed cable line. Three single-core cables in trefoil formation have equal factor ξ . It is calculated as follows: p ξ = Id Id p = Ii I e - current that flows through the earth, I o - zero sequence component of the current that flows through the phase conductor during line-toground short circuit in the transmission network. It is calculated as follows: Io = 1 ( I L1 + I L 2 + I L3 ) 3 where, I L1 , I L 2 and I L3 are phase currents of single-core cables L1, L2 and L3, respectively. II. THEORETICAL BASIS Three-phase cable line consisting of three single-core cables laid in trefoil formation is shown in Fig.1. Their conductive sheaths are grounded at both ends. (1) Ii where Id , Ii - positive and negative sequence components of the phase conductor current of the single-core cable L1, respectively, (3) Fig. 1. Single-core cables laid in trefoil formation According to [1] and [2] factors ξ and k are calculated as follows: j ξ= ωµo D ln c 2π rp (4) ωµo D R p1 + j ln c 2π rp R p1 k= 3 ωµo ωµo 658 + +j ln ( 3 8 2π 3 r D2 p c R p1 ρ ) f (5) where Rp1 - single-core cable sheath resistance per length unit, Ω/m, rp - mean radius of single-core cable sheath, m, Dc - outer diameter of single-core cable, m, ρ - earth electrical resistivity, Ωm, µo - air permeability, µo= 4π 10-7 Vs/Am, ω - angular frequency of the current in phase conductors and cable sheaths. Angular frequency is calculated as follows: ω=2πf (6) where Fig. 2. Currents of the cable line during line-to-ground short circuit The current I L3 usually equals I L 2 . I L3 = I L 2 Substituting from (8) into (7) yields: Io = 1 ( I L1 + 2 I L 2 ) 3 Id = Ii = f - current frequency, Hz. The cable line connected with active networks A and B is shown in Fig. 2. Networks A and B are direct-grounded. Lineto-ground short circuit is in the network B at the phase conductor of L1. Currents flow through phase conductors ( I L1 , I L 2 and I L3 ), through cable sheaths ( p I L1 , p I L 2 and (8) (9) 1 ( I L1 − I L 2 ) 3 (10) According to (1) and (10) positive and negative components of the sheath current are as follows: p Id = p Ii = ξ ( I L1 − I L 2 ) 3 (11) p I L3 ) and through the earth ( I e ) during short circuit. They are shown Fig. 2. Currents I L1 , I L 2 and I L3 are known from the short circuit analysis. They can be shown by sequence components as follows [3]: I o 1 1 1 = I d 1 a I 3 1 a 2 i 1 a 2 a I L1 I L 2 I L3 (7) Besides currents ξ ( IL1 − IL 2 ) 3 p Id and p (12) Ii the zero sequence component of the sheath current p I o flows through the cable sheath. . According to Fig. 2 it follows: 3 Io = Ie + 3 p Io (13) Substituting from (2) into (13) it becomes: where a = e j120o . p I o = (1 − k ) I o According to (9) and (14) it follows: (14) p Io = 1− k ( I L1 + 2 I L 2 ) 3 (15) single-core cables and the current reduction factor of the cable line are: ξ = 0.238 / 76.2o Currents p I L1 , p I L 2 and p I L3 can be calculated by the next matrix equation, [3]: p I L1 1 1 p 2 I L 2 = 1 a p I 1 a L3 1 a a 2 p Io p Id pI i (16) k = 0.104 / -79.7 o Phase currents of single-core cables, during line-to-ground short circuit in the transmission network of 110 kV are known from the short circuit analysis. They are as follows: I L1 = 10500 / -80o Substituting from (11), (12) and (15) into (16) yields: A I L 2 = I L3 = 2000 / 105o p p I L1 = 1− k + 2ξ 2 (1 − k − ξ ) I L1 + I L2 3 3 2 (1 − k ) + ξ 1− k −ξ I L 2 = I L3 = I L1 + I L2 3 3 p (17) Substituting the above values into (17) and (18) yields: p p (19) Equations (17) and (18) become: p p I L1 = 1− k + 2ξ I L1 3 1− k − ξ I L 2 = I L3 = I L1 3 p I L1 = 4722 / -37.7o A (18) In case the network B is a passive network, phase currents I L 2 and I L3 equal zero. I L3 = I L 2 = 0 A (20) I L 2 = p I L3 = 3687 / 178.9o A IV. CONCLUSION A new method for determining sheath currents as the consequence of electromagnetic coupling during line-toground short circuit is described in this article. This method is based on using both the current load factor and the current reduction factor. These factors are the characteristic data of the analyzed cable line. The method presented here can be easily applied in practice. V. REFERENCES (21) Currents p I L1 , p I L 2 and p I L3 , calculated by equations (17), (18), (20) and (21), are an outcome of electromagnetic coupling. They are calculated by both the current load factor ( ξ ) and the current reduction factor ( k ). The current load factor includes the electromagnetic coupling of positive and negative sequence components of the currents. The current reduction factor includes the electromagnetic coupling of zero sequence components of the currents. III. A NUMERIC EXAMPLE The method described in this paper can be applied in transmission and distribution cable networks. The cable line of 110 kV is chosen for the numerical example. It consists of three single-core cables of AXLJ 1x1000/95 mm2 , [4]. Cable data are: DC = 85 mm, rP = 38 mm and RP1 = 0.206 mΩ/m. Single-core cables are laid in trefoil formation and touch each other. Their conductive sheaths are grounded at both ends. The earth resistivity ρ = 500 Ωm. According to (4) and (5), for frequency of f=50 Hz, the sheath current load factor of [1] I. Sarajcev, M. Majstrovic, E. Sutlovic, “Single-core Cable Sheath Current Load Factor”, Proceedings of 12th International DAAAM Symposium, Katalinic, B. (Ed.), [2] I. Sarajcev, “The Cabke Transmission Power Losses”, Ph.D. dissertation, Faculty of Electrical engineering, University of Zagreb, Zagreb, 1985 [3] G. W. Stagg, A. H. El-Abiad, Computer Methods in Power System Analysis,McGraww-Hill, New York, 1968 [4] ABB, “High Voltage Cables AB”, Catalogue Data [5] G. J. Anders Rating of Electric Power Cables - Ampacity Computations for Transmission, Distribution, and Industrial Applications, IEEE PRESS, ISBN 0-78031177-9, New York , 1997 [6] G. J. Jonson et al. , The electric power engineeringhandbook, L.L. Grigsby, (Ed.), CRC Press, ISBN 0-8493-8578-4, Boca Raton, Florida, 2001 [7] L. Heinhold, Power cables and their application, Siemens Aktiengsellschaft, Berlin and Munchen, 1979 [8] S. Y. King, Underground Power Cables, Longman, London, 1983 [9] J. Nahman, Grounding neutral point in a distribution network, Scientific book, ISBN 06-783/1, Beograd, 1980 VI. BIOGRAPHIES Ivan Sarajcev was born in Split, Croatia, on October 28, 1947. He graduated BSEE from the University of Split, Faculty of Electrical Engineering. He obtained his MSEE and Ph.D. in Electrical Engineering from the University of Zagreb in Croatia 1981 and 1985, respectively. He is currently an associated professor at University of Split, Faculty of Electrical Engineering. His research interests include Power System Analysis, Electromagnetic Phenomena, and Protection in Electrical Power System. He is a member of CIGRE, and Energy Association of Croatia. Matislav Majstrovic was born in Dragljane, Croatia, on December 24, 1949. He graduated B.S. degree in Electrical Engineering from the University of Split, Faculty of Electrical Engineering in Croatia He received his M.S. and Ph.D. degrees in Electrical Engineering from the University of Zagreb, Faculty of Electrical Engineering 1979 and 1986, respectively. He is currently a senior researcher at Energy Institute “ Hrvoje Pozar” Zagreb and full professor at University of Split, Faculty of Electrical Engineering. His research interests include Power System Analysis, Implementation of fuzzy system theory and genetic algorithm into Electrical Power System Analysis, Restructuring of Electrical Energy Sector. He is a member of IEEE, IASTED, CIGRE, WEC and Energy Association of Croatia. Ranko Goic was born on the island of Brac, Croatia, on April 11, 1969. He graduated B.S. degree from the Faculty of Electrical Engineering, Mechanical Engineering and Naval Architecture, University of Split, where he also received his M.S. and Ph.D. degree in 1997 and 2002, respectively. After graduating, he has been working at the same faculty, in the Power System department. His main research interests are the power system network analysis and power system planning and optimization. The great part of his research and engineering interests include design and modeling of software tools for network analysis and power system planning. He is member of IEEE, CIGRE, and Energy Association of Croatia.