Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol I HYDERABAD OUTER RING ROAD PROJECT Design, Supply, Installation, Testing, Commissioning, of illumination to the Outer Ring Road, Hyderabad for the Main Carriage Way/ Inter changes/ Junctions/Service Roads and Under Pass areas from Gachibowli to Shamshabad in the state of Telangana, India being taken up with loan assistance of Japan International Cooperation Agency under Phase-2 program and Operation & Maintenance of illumination with connected switch gear for a period of Five years from date of Operational Acceptance Certificate being taken up with HGCL Funds. (Tender Notice No. 4/CGM(T)/HGCL/DGM-I/Street lighting/2014-15) BIDDING DOCUMENTS CONTENTS VOLUME SECTION DESCRIPTION INVITATION FOR BIDS (IFB) I 1 INSTRUCTIONS TO BIDDERS (ITB) 2 BID DATA 3 GENERAL CONDITIONS OF CONTRACT (PART I) 4 CONDITIONS OF PARTICULAR APPLICATION (PART II) FORM OF BID SECURITY (BG) FORM OF AGREEMENT FORM OF PERFORMANCE SECURITY (BG) FORM OF ADVANCE SECURITY (BG) SCHEDULES OF SUPPLIMENTARY INFORMATION SAMPLE FORMS FOR QUALIFICATION INFORMATION ETC. 5 6 7 II III IV 8 9 (a) 9 (b) 10 11 12 13 14 15 FORM OF BID AND APPENDIX TO BID SUMMARY OF COST OF WORKS BILL OF QUANTITIES (PART-A+PART-B) TECHNICAL SPECIFICATIONS LIST OF APPROVED MAKES SPECIAL CONDITIONS FOR O&M SPECIAL CONDITIONS FOR PAYMENT FOR O&M SERVICE LEVELS FOR O&M DRAWINGS December-2014 HYDERABAD GROWTH CORRIDOR LIMITED Name of Work: Design, Supply, Installation, Testing, Commissioning, of illumination to the Outer Ring Road, Hyderabad for the Main Carriage Way/ Inter changes/ Junctions/Service Roads and Under Pass areas from Gachibowli to Shamshabad in the state of Telangana, India being taken up with loan assistance of Japan International Cooperation Agency under Phase-2 program and Operation & Maintenance of illumination with connected switch gear for a period of Five years from date of Operational Acceptance Certificate being taken up with HGCL Funds. (Tender Notice No. 4/CGM(T)/HGCL/DGM-I/Street lighting/2014-15) BIDDING DOCUMENTS FOR ITEM RATE CONTRACT VOLUME I CONTENTS III 10 TECHNICAL SPECIFICATIONS 11 LIST OF APPROVED MAKES 12 SPECIAL CONDITIONS FOR O&M 13 SPECIAL CONDITIONS FOR PAYMENT FOR O&M 14 SERVICE LEVELS FOR O&M SCOPE OF WORK Design, Supply, Installation, Testing, Commissioning, of illumination to the Outer Ring Road, Hyderabad for the Main Carriage Way/ Inter changes/ Junctions/Service Roads and Under Pass areas from Gachibowli to Shamshabad in the state of Telangana, India being taken up with loan assistance of Japan International Cooperation Agency under Phase-2 program and Operation & Maintenance of illumination with connected switch gear for a period of Five years from date of Operational Acceptance Certificate. Street Lighting / High Mast Lighting / UNDER PASS Electrical Work PROJECT BACKGROUND 6/8 Lanes Highway of Outer Ring Road Hyderabad including Service Roads / junctions and flyovers between Shamshabad Airport to Gachi Bowli Flyovers which is approaching High-Tech City ; Hyderabad. CHAINAGE: 0.00 KM [Near Gachi bowli Flyover junction including Flyover Lighting at Gachibowli] to 22 KM [Shamshabad] Junction - 4/6/8 lanes Lighting including service Roads Site location Map Highway Lighting HGCL Hyderabad and their nominated electrical consultant reviewed various 1 Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III updated Lighting technology and standards applicable in India as well as Abroad and using recent trends in International / Domestic Lighting has come to a conclusion to follow following standards for maintaining Illumination level for respective areas Location Horizontal Illumination at 0.0 m level Uniformity Uniformity [E minimum / E [E minimum / E Road surface average] Maximum 4/6/8 Lanes Highways 30 0.4 0.33 Fly-overs 40 0.6 0.4 Service Roads 20 0.6 0.4 Junctions 50 0.4 0.25 Underpass areas 70 0.6 0.3 Under Pass Area Of 70 Flyovers / various Junctions below Main carriage ways 0.6 0.3 Special Note Highway lighting4/6/8 lanes Illumination standards decided by HGCL as per I.S.1944 (Part –I & II) 1970 and as per National Lighting Code 2010(SP72:2010) of BIS. Light Loss Factor: 0.85.to be considered. Major Carriage ways & Flyovers i.e. 6/8 lanes Bidders are requested to match Horizontal Illumination as specified. Grid of illumination Measurement: 3.5m (transverse) x 3,5m (longitudinal) …. For highways Grid of illumination Measurement: 3. 5m (transverse) x 3.5 m (longitudinal) …. For Service Roads Grid of illumination Measurement: 2.5 m (transverse) x 2.5 m (longitudinal) …. For Junctions Grid of illumination Measurement: 2.5m (transverse) x 2.5m (longitudinal) …. For underpass areas of Fly-overs & various junction areas Lighting (General Outdoor Illumination): Outdoor lighting as per Bill of Materials estimated for above project indicates an 2 Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III efficient street lighting/area lighting of the Major Carriage ways / Service Roads / Junctions / Fly-over and underpass. Pease refer Drawing / Bill of Material along Technical Specifications to follow. For Successful Bidders there will be a condition that they have to submit Lighting design for the various locations before execution of the work and same has to be approved by HGCL ‘s Consultant . Lighting design should adhere from the approved Manufacturer list only and there if it is not meeting the desired light level during design or after execution then bidders will have to compensate illumination level with extra supply of Light fittings /poles/electrical mentioned in the list w/o any extra cost. Initial design have been made based on the luminaries reference in the drawings and there though on each item similar equivalent have been approved; however on different manufacturer equivalent in case design does not match as per location wise requirement there initial luminaries type have to give priority with even in case of initial luminaries catalogue reference if bidders are following respective manufacturer design to be submitted for approval. Bidders are requested to follow drawings and pole position / mast position indicated in the drawings with respective type of luminaries. In case any variation with the site that has to be highlighted and get confirmation before execution Successful Bidders will have to submit execution drawing / as built drawings indicating pole/mast positions and a declaration; Specification of High mast/ Poles and light fittings are followed as per specification mentioned along Bill of Materials. Scope of the project The services of Street lighting/ High Mast Lighting & Experienced in Electrical contractors/Manufacturer are called for the New Street lighting/ High mast Lighting on Major 4/ 6/8 lane carriage / Service Roads /Junction areas / Flyover / Underpass area with modern concept of Lighting as planned The broad area of scope is 3 Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III detailed in technical specifications / drawing / and bill of materials. Scope of work: 6/8 Lanes Highway of Outer Ring Road Hyderabad including Service Roads / junctions and flyovers between Shamshabad Airport to Gachi Bowli Flyovers FOLLOWING AREA OF INDIVIDUAL LOCATIONS ARE CONSIDERED FOR ELECTRICAL WORK SL. LOCATION DESCRIPTION 1.0.1 Shamshabad Junction To Gachibowli OUTDOOR LIGHTINGALONG Flyover [ 6/8 lanes & Service Roads UNDER PASS OF THE AREA 1.0.1.1 HIGHWAYS [ Shamshabad to Major Carriage ways street lighting Nanakraman gudda junction [ Entire for 8 Lanes [ using 12 m Pole with 19.7 km length -8 lanes twin bracket of 2.5m length on sides having 2x 1 no 210 watt LED Street Lights @ 25m spacing for 8 lanes. on median. 1.0.1.2 HIGHWAYS [ Nanakramanguda Major Carriage ways street lighting Junction to Gachi Bowli [ Entire 2.3 for 6 Lanes [ using 12 m Pole with km length -6 lanes twin bracket of 2.5 m length both sides having 2x 1 no 210 watt LED Street Lights @ 25mt spacing for 6 lanes on median 1.0.1.3 Cross Roads between Junctions and other areas a) Carriage ways street lighting for 6 Lanes [ using 10 m Pole with Twin Bracketand 210 watt LED Street Lights @ 33m spacing for 6 LANES Roads b) Carriage ways STREET LIGHTING for 4 Lanes [ using 10 m Pole with Twin Bracket- 1.0.2.1 Service Road Lighting [ Nana Karam Guda to Shamshabad ] -125m section [ 2nos service Roads – Both sides ] 2.0.1 Interim Junction areas and cross roads below Main Highways including underpass 2.0.1.1 Shamshabad junction 2.0.1.2 Nanakramaguda Junction [Gopannapali to Mehedipatnam ] Junction area -2nos with 210 watt LED Street Lights @ 33 m spacing for 4 LANES Roads Street Lighting for Service Roads using 6m pole with 1 no 90 watt LED Street Light @25m spacing 30m High mast lighting with 2kw Metal halide flood lights …. 28 mast / 178 nos flood lights area 30m High mast lighting with 1kw Metal halide flood lights …. 2 mast / each having 9 no’s 1kw MH Halide Flood lights a) Carriage ways STREET LIGHTING for 6 Lanes [ using 10 m Pole with Twin Bracket-opposite sides x 1 no 210 watt LED Street Lights @ 33m spacing for 6 LANES Roads b) Carriage ways STREET LIGHTING for 4 Lanes [ using 10 m Pole with Twin Bracket-opposite sides x 1 no 210 watt LED Street Lights @ 33 m spacing for 4 Lanes road Adjacent service Roads meeting Major using 6 m pole with 1 no 90 watt Highways LED Street Light @20m spacing 2.0.1.3 Underpass Lighting 2x28watt T-5 Fluorescent Totally enclosed Luminaries Narasinghi Junction area [ Narasinghi to Pathan Cheruvu ] Carriage ways STREET LIGHTING for 6 Lanes [ using 10 m Pole with Twin Bracket-opposite sides x 1 no 210 watt LED Street Lights @ 33 m spacing for 6 LANES Roads Cross Road Highway below Major Carriage ways Carriage ways STREET LIGHTING for 6 Lanes [ using 10 m Pole with Twin Bracket-opposite sides x 1 no 210 watt LED Street Lights @ 33 m spacing for 6 LANES Roads Adjacent service Roads meeting Major using 6 m pole with 1 no 90 watt Highways LED Street Light @25Mt spacing Underpass Lighting 28watt T-5 Fluorescent Totally enclosed Luminaries Illumination Design Concept Major Carriage ways 6 lanes [Gochibowli to Urdu University – 2.3 Km Main Carriage ways will have 12m Pole with 2.5 m overhung consists of 2 ~ 1 x 210 watts Led Street light to cover Road span 10.75 m on one side. Poles will be spaced at 25 mt Spacing between the poles on same direction. 6 Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III Major Carriage ways 8 lanes [Urdu University to Shamshabad Junction – 19.7Kms Main Carriage ways will have 12m Pole with 2.5 m overhang consists of 2~1x216watt Led street light to cover Road span 14.75 m on one sides . Poles will be spaced at 25 M Spacing between the poles on same direction. On service Roads there will be 6.0 M Pole on which 1x 90 watt (Maximum) LED Street light will be installed. Pole Spacing will be 25 Mts. per Service Road. Section is marked as 125.0 M Section. Junction Areas [ Gachi Bowli to Shamshabad in between areas Junction areas like Appa / Gandhipeth / Nanakramguda Jn/ Narsingi Jn /Rajendranagar (North) Junction. These areas are below level of Main carriage ways and typically of similar construction having two circular junction at the ends where all main carriage ways and service Roads are meeting to junctions. A typical such junctions with luminaries and mast is shown below as plan view. 152 Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III Junction area of 90m app. Dia. will have 1no 30m mast. Mast will have symmetrical loading 9 nos. 1kw flood lights …. Metal halide as per detailed specifications and approved make list will comply Illumination design as desired Underpass areas where ever in junctions applicable of size 125m[ L] x 35m (w) x5.4m (h) maximum will have 2x28watt T-5 Fluorescent luminaries in 3 rows per Underpass to meet desired illumination levels . Luminaries will be IP65 for adverse outdoor condition. Lamp colour will be cool white [4000 deg k]. Shamshabad Junctions near Airport These area is at starting point of highways of Outer ring Road; A form of clover leaf multilevel roadways and these areas specially road portion will be free from any pole structure on the road and the lighting will be covered by using 30m mast with having maximum 9 nos asymmetric Metal halide [long life] lamps. Total 28 masts and 178 nos 2kw Metal halide flood lights will ensure these junction areas of illumination level requirement as per main chart of 50 lux ( av) with uniformity 0.4 . [emin/ eavg]. [Please refer drawing for exact 28 mast locations with mast wise 2kw MH Asymmetric Luminaries. Underpass Lighting There are four underpasses in this project of 22 km length; Location wise these underpasses are located at Appa Jn / Gandhipeth / Nanakaramanguda & Gachibowli below flyover area. Area of under pass for three locations like Appa / Gandhipeth / Nanakarmanguda will be app. 125 M (L) being the sectional length of these areas related to Major Carriage ways or may be slightly lesser x 34/35m width; However in case of Gachibowli flyover the sizes of underpass will be 17.5m (width of Fly-over) x40.5m (Longitudinal direction) - from Hyderabad city to High- Tech City side. Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III Typical Underpass Area & Recommended Lighting: First of all Underpass will have illumination level of 70 lux (Horizontal) at Road surface with 0.6 uniformity [ e min /e av). Further Type of Luminaries / light source will be T-5 /2X28WATT totally enclosed Fluorescent with colour temperature of 4000 deg k. Luminaries will be mounted Please refer drawings ELECTRICAL SYSTEM SECTION WISE –LOCATION WISE Electrical distribution of power is proposed for every 2km span basis where Min Incomer/ Sub-station will be at middle of 2km span; Main HT Lines (11kv/0.415kv will be terminated as In-comer to every Sub-station location Area wise Load distribution and selection of Sub-station as per the load requirements at site in consultation with TSSPDCL. Adequate capacity of Transformers are proposed in the scheme. Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III Total Type of Equipment’s Lighting Gachi-bowli Flyover 02.3km 2.34.0km 4.06.0km 6.08.0km 8.010.0km 10.012.0km 12.014.0km 14.016.0km 16.018.0km 18.020.0km 20.022.0km [ Qty] with 0 140 158 174 174 174 174 174 174 174 174 168 1858 with 0 0 12 90 0 0 78 0 0 0 0 0 180 6m pole with 90w led 0 19 265 326 200 218 384 200 200 200 200 100 2312 30m mast suitable for 1 0 2 2 9 0 18 18 12 m pole 2x210wLED 10m pole 2x210wLED 7 2 9 nos 1ke flood light 30m high mast with 0 0 18 0 0 0 0 0 63 178 178 0 228 9no. 1KW MHL 30m mast with 9 nos 2kw flood lights 0 2x28w fitting Total load 9.9 0 34.1 76 76 87.832 115.55 0 60.02 0 76 0 0 0 0 61.82 118.09 60.02 60.02 60.02 60.02 450.24 1177.64 load in KVA with p.f.of 0.85 11.647 40.118 103.33 135.94 70.612 72.729 138.93 70.612 70.612 70.612 70.612 529.69 Max. load on SS 14.559 50.147 129.16 169.93 88.265 90.912 173.66 88.265 88.265 88.265 88.265 662.12 250 125 125 250 125 125 125 125 3~250 80% Recommend SS 125 160 157 Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III Sub-station Onwards Electrical distribution system feeder pillar (10 Nos) Supplying, installation, testing & commissioning of cubical type IP 65 for outdoor type Distribution Panel for 415V, 3 Phase, 4Wire 50 Hz AC supply system fabricated in compartmentalized (preferably) design from CRCA sheet steel of 2mm thick for frame work and covers, 3mm thick for gland plates i/c cleaning & finishing complete with 7 tank process for powder coating in approved shade, having suitable capacity extensible type TPN Copper bus bars of high conductivity, DMC/ SMC bus bar supports, with short circuit withstand capacity of 50KA for 1 Sec., bottom base channel of MS section not less than 100mm x 50mm x 5mm thick, fabrication shall be done in transportable sections, entire panel shall have a common copper earth bar of size 25mm x 5mm at the rear with 2 Nos. earth stud, solid connections from main bus bar to switch gears with required size of Al. bus bars and control wiring with 1.5 sq.mm. zero halogen fire retardant insulated copper conductor S/C cable, cable alleys, cable gland plates in two half, i/c providing following switch gears.(General arrangement and schematic Drawings to be approved by the HGCL before start of fabrication) Incoming:1 Set of 63A TPN MCCB 35KA. (i) Supply and erection of L.T. 3phase Digital multifunction energy meter with 3 lines LCD display for measuring all the parameters (voltage / Current / Power / frequency / power factor / kw / kwh / KVAR/ KVARH/) on existing box panel board including connections etc., complete. (iii) RYB LED indicating light protected by 2 Amp. S.P. MCB Bus Bar: 100 A, 415V, 4 strip, 16 KA, 50 Hz Copper Bus bar Outgoing 2 Set of 32 A TP MCB 10 KA 5 Set of 16 A TP MCB 10 KA Sub feeder pillar (6Nos) Supplying, installation, testing & commissioning of cubical type IP 65 for outdoor type Distribution Panel for 415V, 3 Phase, 4Wire 50 Hz AC supply system fabricated in compartmentalized (preferably) design from CRCA sheet steel of 2mm thick for frame work and covers, 3mm thick for gland plates i/c cleaning & finishing complete with 7 tank process for powder coating in approved shade, having suitable capacity extensible type TPN Copper bus bars of high conductivity, DMC/ SMC bus bar supports, with short circuit withstand capacity of 50KA for 1 Sec., bottom base channel of MS section not less than 100mm x 50mm x 5mm thick, fabrication shall be done in transportable sections, entire panel shall have a common copper earth bar of size 25mm x 5mm at the rear with 2 Nos. earth stud, solid connections from main bus bar to switch gears with required size of Al. bus bars and control wiring with 1.5 sq.mm. zero halogen fire retardant insulated copper conductor S/C cable, cable alleys, cable gland plates in two half, i/c providing following switch gears.(General arrangement and schematic Drawings to be approved by the HGCL before start of fabrication) Incoming:1 Set of 32A TP MCCB 35KA. (i) Supply and erection of L.T. 3phase Digital multifunction energy meter with 3 lines LCD display for measuring all the parameters (voltage / Current / Power / frequency / power factor / kw / kwh / KVAR/ KVARH/) on existing box panel board including connections etc., complete. (iii) RYB LED indicating light protected by 2 Amp. S.P. MCB Bus Bar: 63 A, 415V, 4 strip, 16 KA, 50 Hz Copper Bus bar Outgoing 3 Set of 16 A TP MCB 10 KA Main feeder pillar (6Nos) Supplying, installation, testing & commissioning of cubical type IP 65 for outdoor type Distribution Panel for 415V, 3 Phase, 4Wire 50 Hz AC supply system fabricated in compartmentalized (preferably) design from CRCA sheet steel of 2mm thick for frame work and covers, 3mm thick for gland plates i/c cleaning & finishing complete with 7 tank process for powder coating in approved shade, having suitable capacity extensible type TPN Copper bus bars of high conductivity, DMC/ SMC bus bar supports, with short circuit withstand capacity of 50KA for 1 Sec., bottom base channel of MS section not less than 100mm x 50mm x 5mm thick, fabrication shall be done in transportable sections, entire panel shall have a common copper earth bar of size 25mm x 5mm at the rear with 2 Nos. earth stud, solid connections from main bus bar to switch gears with required size of Al. bus bars and control wiring with 1.5 sq.mm. zero halogen fire retardant insulated copper conductor S/C cable, cable alleys, cable gland plates in two half, i/c providing following switch gears.(General arrangement and schematic Drawings to be approved by the HGCL before start of fabrication) Incoming:1 Set of 125 TP MCCB 50KA. (i) Supply and erection of L.T.3phase Digital multifunction energy meter with 3 lines LCD display for measuring all the parameters (voltage / Current / Power / frequency / power factor / KW /KWH/ KVAR/ KVARH/) on existing box panel board including connections etc., complete. (iii) RYB LED indicating light protected by 2 Amp. S.P. MCB Bus Bar: 300 A, 415V, 4 strip, 16 KA, 50 Hz Copper Bus bar Outgoing 3 Set of 63 A TP MCB 10 KA 2 Set of 32 A TP MCB 10 KA 6 Set of 16 A TP MCB 10 KA Street Light Poles & High mast Street Lighting Poles: [sixteen Sided] Sixteen sided/ Octagonal Pole M.S. fabricated continuous tapered Profile Hot dip galvanized having base plate & top flange. There will be one no continuous weld joints per sections. Pole will have provision for fixing single or twin bracket as per requirement of site. Pole will be designed as per ILE-TR-7. Maintaining Basic wind speed data of IS-875-PART-3-1987 for Hyderabad at 44m/sec at 10m level. . Steel Grade will be as per BSEN 100025; Having Yield strength of 355 Mpa. for 3mm/4mm/5mm thick steel. Hot dip galvanizing 86 Microns .as per BS729. Type of pole will be as under 12 M Pole with Single Bracket / Twin Bracket as well [For 6/ 8 lanes] Bracket Length 2.5m 12 M Pole with Single Bracket / Twin Bracket as well [For 4 lanes] Bracket Length 1.5m 6 M pole with Single Bracket 1.0m Bracket length [For Service Roads] Basic Pole will be (sixteen Sided) M.S. Hot Rolled Product of NON-Alloys Structural steel of Grade S-355. [As per BSEN 100025/ 100027. with 1.5 M “C” Bracket. Yield Strength: 355 Mpa. Tensile strength: 490-630 Mpa. Elongation: 22%. Chemical Composition C= 0.27%; si=0.6% P=0.055%; NI= 0.011%. Other Parts like bracket / Door cover/ stiffener as per IS- 2062 (Yield Strength: 240 MPA. Welding as per IS-9595,/ IS-4353/ IS-3613 & BS-7280 ( 100% Penetration .Fillet dimension : 5-6mm. Hot dip Galvanizing as per BS-729 / Equivalent IS Specifications ( 65 Microns ) All The dimensions are Nominal Dimension in mm. allowable tolerance limit of (+/_) 100mm. Base Plate thickness minim: 20mm Door positioning from base will be at 600mm (minim) [Lower portion of door should be 600mm from the base. Door size: 240mm (h) x 80mm (w) with lockable hinged flash door. Pole will have inside terminal box for electrical dis-connection with switches/ fuses Pole will be duly wired by using 3cx2.5m.sq. Copper un-armoured cable for electrical connection to street light fixtures. Pole will have in base plates 4-insertion holes –oblong size of 60mm x30mm for insertion of foundation bolts Pole will be supplied with 4-nos stiffener of 8mm size of height 150 mm minims at 90 degree interval. Each pole will be supplied complete with 4nos. 750mm (l) x M-24 Size Foundation bolts of Tor steel Grade: 465 Mpa. Each foundation bolts will have 5 sets of nutwasher for fixing with foundation bolts as well as Anchor plates Foundation bolts above ground level portion should be hot dipped galvanized to prevent rust. Each pole will be supplied complete with Anchor plate and template Pole will be installed on pre-casted foundation of height-300mm from respective Ground level. Pole bottom door position should be at 900mm height from Respective Ground level. Bracket ends should be suitable for fixing 1x210 WATT & 1x90 WATT LED Street light fixture of approved make as specified in the tender. All Major Carriage ways [ 4/ 6/8 lanes] street lighting will be followed as per above luminaries for street lighting or approved equivalent 1X210 WATT LED Street light with maximum Electrical Load including LED Driver load will be restricted to 230 watt per unit light is recommended for use in Highways 4 lanes / 6 lanes & 8 Street Light Luminaries should deliver 18000 Lumens. Minimum Housing: High pressure Die-cast Aluminum . Non-Corrosive Optical Cover. Extra-white Toughened Glass thermally hardened. Mounting bracket: Integrated with Luminaries High pressure die-cast Aluminum Gasket: Silicon Rubber. Connection: Screw Connection block. 1X 90 WATT LED STREET LIGHT High power Modular Street light is a state of art street lights. Lantern with flexible LED modules with its robust product construction high system efficacy and good optical design. LED Street light is recommended for Service Road Illumination Electrical Load is 110 watt. Street Light Luminaries should deliver 7000 Lumens. Minimum Housing: High pressure Die-cast Aluminum . Non-Corrosive Optical Cover. Extra-white Toughened Glass thermally hardened. Mounting bracket: Integrated with Luminaries High pressure die-cast Aluminum . Gasket: Silicon Rubber. TECHNICAL SPECIFICATION [Applicable for Highways as well as For Service Road Luminaries] No Criteria Luminaire configuration / 1 Specification for LED street light fitting Side entry type. Shall consist of separate optical and control gear compartment. Driver should be early technical requirement replaceable in the field condition High pressure Aluminum LM6 housing with corrosion resistant polyester powder coating with 2 3 Housing / Body of fitting Finish manufacturer emblem/logo embossed into the housing. Aesthetically designed housing with corrosion resistant polyester powder coating . Fixture cover 4 UV stabilized Polycarbonate / Cover / glass Toughened glass. Luminaire should be full cut-off as per IS 1944 5 Glare control details 6 Protection – IP Optical and Control gear compartment-IP 66 7 Impact resistance Impact resistance greater than or equal to IK 08 Structured LED array for optimized roadway distributio photometric n with photometric lenses 8 Optical assembly designed to optimize application efficiency and minimal glare. 140-270 volt universal electronic driver 50 Hz 9 10 Operating voltage Frequency 11 12 13 Power factor > 0.95 Fixture designed ambient + 35 degree C Temperature Operating temperature Range 0 to +50 degree C 14 Working Humidity 10% to 90% RH 15 Storage Temperature 0 to 50 degree C Total Current Harmonic Total Current Harmonic Distortion should be lesser 16 distortion 17 18 than 20 % Total system wattage and Nominal value to be printed in the label and within +/lumens of Fixture including 10% variation from the printed value Driver LED efficacy (lumen/watt) Efficacy of LED should be greater than 120 lumens / watt. 19 LED Luminaire efficacy >80 lumen/watt Power efficiency / LED driver The efficiency shall be more than 85 % in all cases at 20 21 22 efficiency all times during project period. Lumen maintenance Correlated Colour L70 @ 50,000 hours Correlated Colour Temperature shall be 4000-6000 K temperature (with variation limits of ±355K) per ANSI C78.377A CCT standard. 23 CRI The value of CRI shall be more than 70. Make of LED: CREE /Philips Lumileds / 26 Make of LED Osram/Nichia . The LED shall be of Surface Mounted Design 27 Lens 28 LED Drive Current 29 Driver Specification Lens to provide on appropriate LEDs to obtain desired distribution. Not more than 85% capacity of LED of the rated current carrying 140-270 Volt universal electronic potted drivers with internal surge protection of 4 kV with Analogue Dimming or Linear Dimming. The Luminaire light shall be constant. The voltage variation / fluctuations in the specified voltage range shall not impinge upon the lumen it produces. Maximum +/- 2% is allowed throughout in the input operating voltage range. As per IEC safety standards IEC61000, 61547, 61347 30 Lumen Output Variation 31 Electrical safety as per IEC. standard Conformation s of The luminaire conform to IEC 60598 / 10322 luminaire Any NABL accredited laboratory for luminaire and Reports / certifications driver 32 33 34 Luminaire protection External surge protection of 10KV (DM / CM) and protection device components should be enclosed in a housing / Luminaire 35 Test reports of luminaire (a)The luminaire should be tested as per IEC 60598 standards and following test reports should be submitted: Heat Resistance Test, Thermal Test, Ingress Protection Test, Electrical / Insulation Resistance Test, Endurance Test, Humidity Test. The luminaire should be tested for 'Drop test' as per IEC 60068-2-31/IS9000 Part 7 / Sec 3 standards. The luminaire should be tested for 'Vibration test' as per ANSI/IEC 68-2-6 standards. (b) Should comply to IESNA LM-79 (Approved method for the Electrical and Photometric Measurements of Solid-State Lighting Products) (c) The LED’ used should comply to LM-80 standards (IESNA: Approved Method for Measuring Lumen Maintenance of LED Light Sources and LED lumen depreciation time to L70 based on LM-80 data) (d)Copy of above test certificates should be submitted with tender. (e) Random samples from supplied lot should be tested at NABL accredited laboratory and report submitted for acceptance. LED street light fitting should be supplied with serial number which should be attached to the fitting. The label should mention: Name of Manufacturer, 36 Serial number model name and number, system lumen pack, nominal CCT, Wattage of fitting, Date of Manufacture, and other labelling details as per IS. 100% replacement guarantee for a period of seven 37 Guarantee years from the date of enerzisation. 2x28watt T-5 Fluorescent tube luminaries for Under Pass Areas Totally enclosed Fluorescent luminaries with blue colour fluorescent T-5 Tube [244nos light fixtures with T-5 cool white Colour Fluorescent tube: 448nos] Functional dust, impact and jet of water proof luminaries with twin TL-5 28W cool white lamps. The luminaries are with the following features:- - Read voltage 220-240V - Specially designed 55 toggles ensuring IP 66 level of protection - IK 08 impact resistance - Polycarbonate housing - 2x28watt Electro-magnetic - ballast PF Improvement - Capacitor - Special clear polycarbonate cover to ensure proper light distribution 1x28watt T-5 Fluorescent Tube 240VOLTS ,50C/S.AC SUPPLY 28WATT –T5 Fluorescent tubes 2950 lumen output Colour Temperature 4000 deg k. – Cool White. Lamp Life … 20000 hrs. 30m high mast with 9 nos 1x1000watt Metal halide flood lights for junctions All interim junction area like Appa Junction/ Gandhipeth / Gachi bowli / Narakarmanguda will have 2nos of 30m mast with 9nos 1x1000watt Metal halide flood lights to cover 90-100m dia area with 50lux avg illumination with 0.4 uniformity Luminaries will be loaded symmetrically. Following Junctions will have this type of Mast Appa Junctions Both sides 1 no High mast : 2 High masts Gandipet Junctions Both sides 1 no High mast : 2 High masts Narakarmaguda Junctions Both sides 1 no High mast : 2 High masts Gachibowli Junctions Starting of 6/8 lanes from Gachibowli side 1 no High mast Total 7nos 30m High mast will be installed for above junctions Type Of 1x1000 watt Metal Halide Flood lights will be used For above Junction Areas SPECIFICATION FOR 1000 Watt Metal Halide Symmetric flood light integral fixture. The ballast and lamp housings shall be die cast of low copper content aluminum alloy. The castings shall be subjected to a 7-stage pre-treatment cleaning prior to being finished with an electrostatically applied and baked on polyester powder coat paint. The bracket arm clamp shall attach to a 51mm (2”) nominal pipe and allow for +/-3° adjustment for levelling the luminaries. A porcelain-enclosed socket with a nickelplated grip screw shell provides lamp support. A stainless steel lamp clamp lined with woven glass cloth shall be provided for standard 1000 watt HID lamps. The fixture shall pass a vibration fatigue test simulating a minimum 1-g peak acceleration. The ballast shall be copper wound with a power factor over 90%. It shall have a published ballast factor of 1 to ensure full lamp output. All ballast components shall be completely removable as a unitized assembly. The optical assembly shall consist of formed aluminum reflectors with anodized finish. The IES cut-off symmetric distribution reflectors are spun and fluted. All optical systems are enclosed with a clear drop borosilicate glass lens in a gasket doorframe should be IP65 rated. The doorframe includes four stainless steel latches and a hinge for re-lamping.The fixture shall be UL/CUL Listed for wet locations in 40° C ambient Temperatures or should be IP65 Rated. 1000 watt Metal Halide Lamps[ Tubular version ] for above flood lights. 1000 watt METAL HALIDE 1000 WATT Lamp Lumen output 85000 lumens 240 volts,50 c/s. A.C .Electrical Supply Lamp colour rendering Index >65 Lamp colour temperature 4300 0 k Lamp Life 12000 burning hours.at 50% survivor. Total 7nos High mast will have 7 x 9 = 63nos 1x1000 watt Metal halide Lamps. 30m high mast with 1x2000watt Metal halide flood lights for Shamshabad Junctions Shamshabad Junction is a larger junction area near Hyderabad Airport; Entire Clover leafs of Junction will be covered with 28nos 30 M high mast. Each mast will have 2kw Asymmetric Flood lights with 2kw Metal halide Lamps. Illumination Level for Shamshabad Junction will be 50lux avg illumination with 0.4 uniformity Luminaries will be loaded symmetrically asymmetrically as per site requirement. 30 M high Mast with 1x2000 watt Metal Halide Flood lights will be used for Shamshabad JunctionI 1x2000 watt Asymmetric Flood Lights suitable for 30m mast 1 x2 kW Asymmetric Flood Light with Metal halide Lamps Housing made of pressure die cast aluminum alloy with low copper content for sturdiness and better corrosion resistance. Profile of flood lights should have better aesthetics and also lower wind resistance; powder coated. The lamp compartment comprises of electrochemically brightened high purity, pre anodized aluminum reflector high efficiency specially profiled to suit application with specially designed lamp support clips ensure correct beam distribution; the front cover comprises of heat resistant toughened flat glass to match the profile specially designed powder coated mounting bracket with graduating disc for ease of mounting and aiming. Flood light fixture should be IP-65. Compact, sturdy non-integral 1x2000 watt metal halide flood light with separate 1x2000 watt control gearbox. High grade asymmetrical reflector Wall, ceiling and surface mounting as per site condition Non-corrosive high pressure die-cast aluminum housing with low copper contain & black powder coated finish. Electro-chemically brightened and anodized high purity stippled aluminum reflector. M.S. powder coated mounting bracket; all external fixing I stainless steel finish. Rugged corrosion resistant housing with integral gear box. Compensated electrical control gear box. Quick easy access to lamp and gear, without affecting beam adjustment through hinged front window with release clips. Heat resistant EPR gasket bonded to housing renders the luminaries as dust proof and jet proof IP-65. Control gear box comprises following M.S. Sheet steel enclosure Minimum 2mm thick with provision for fixing at cat walk or Structure having IP-54 Protection Gear tray inside comprises of 1kw metal halide ballast P.f. improvement capacitor to a p.f. improvement level not less than 0.85. Electrically suitable for operation at 240volts, 50 c/s.; Phase to phase terminal. Terminal Block along 20 amps DP Switches for local isolation /maintenance [Switches should be of approved make as per list.] 2kw Metal Halide Lamps suitable for above flood lights Master MHN-FC 2000W /740 -400V XWUNP Compact quartz Metal halide lamps with double pinch. 210000 lumens after 100 hrs initial run. 3200 deg k colour temperature [ Natural White] lamp life : 14000 hrs at 50% survivor.[ highest usage of 2kw metal halide lamps] TECHNICAL SPECIFICATIONS OF EQUIPMENTS (i) High Mast for 30 m mast with 9nos 1x1000watt Metal halide Symmetric distribution flood lights for Appa / NANAKARMANGUDA/ GANDHI PETH / GACHI BOWLI [ quantity of High mast 7nos with 63nos 1kw Flood Light (ii) High Mast for 30 m mast with 9nos 1x2000watt Metal halide asymmetric distribution flood lights for Shamshabad Junction [ quantity of High mast 28nos with 178nos 2kw Flood Light (iii) High Mast Specifications for 30m suitable for loading of asymmetric [9 nos. 1x1000w Symmetric beam Metal halide flood light] on 360 degree rotation of Flood Lights towards working area……. other junctions. High Mast Specifications for 30m suitable for loading of asymmetric [9nos 1x2000w asymmetric Metal halide flood light] on 180-210 degree Rotation of Flood Lights towards working area……. Shamshabad Junctions (iv) High Mast SCOPE: The scope of the specification covers the manufacture, transport installation; testing & commissioning of the High Mast Tower complete with lighting system. Using Raising & Lowering type Mechanism for easy maintenance of Luminaries from Ground Level. High Mast tower includes the Civil Foundation Works. APPLICABLE STANDARDS. The following shall be the reference standards for manufacturing of High masts including design consideration. CODE NO A) I.S.875 (PART-III)-1987 TITLE Code and Practice for Design loads. B) I.L.E.TR-7; LATEST EDITION Specification for Mast /Foundation. C) BS5649, PART-7 Structural Stability. D) BSEN 100025/100027 Mast Sections …Materials.Gr.50, BS -4360 Equivalent. [Yield strength: 355 Mpa. Tensile strength: 490- 630 Mpa; Elongation:22%] E) IS 2062 frame/Luminaries For Accessories, Base plate/Head F) BIS 7280/5135 or IS.9595/4353 For Welding. Using MIG. Process. G) BS 729/ IS0 1461 For Galvanizing. H) IS1367 For Foundation Bolts. Using Gr.4.87 [Y.S.460 Mpa] Structure: The High Mast Structure shall be of continuously tapered Profile .Polygonal Cross section [at least 20 sided above for 30M. Mast].The Mast structure should be pleasant in appearance & designed for suitable wind loads as mentioned above. Mast structural Life will be 25 years. Galvanizing life depends on Environmental condition Where Mast will be installed; as mentioned in ILE.TR-7 as well as BS729. Minimum Life can be considered as 5 years and after that as guided by ILE.TR-7 Methods of Protection to be followed. Construction Mast sections should be mechanically formed and longitudinally welded [Depending on Market availability of Standard Steel Manufacturers Steel Width] Longitudinal weld more nos technically acceptable Internationally for meeting Larger diameter requirement as per Mast design considerations.. There will not be any circumferential weld on particular sections. Welding continuous [M.I.G] process to be used. The sections shall be constructed so as to overlap each other by a minimum of 1.75 times the inside across flat diameter of the female section & to be easily assembled on site by using simple tools w/o using welding. The Manufacturer shall indicate in finished columns minim. Overlapping by providing Indication Mark. Adequate care should be taken on Door Construction as guided by BS5649.Part-7 – 1985. Base Plate/stiffener/Foundation holes should be also to be checked considering longitudinal shear force/ Ground level Bending Moment/Axial Load/ Torsional Moment. Mast connection at Top with head frame will be through flange plates / fixing bolts between Top of Mast / Bottom of Head frame structure. This will give strength for connection for long duration. Mast section at base will be connected with suitable stiffener/base plate of requisite width. Base plate will have provision for fixing Foundation bolts. Mast base section will have door provision for easy access of Winch/power tool operation. As well as for electrical maintenance. For attachment of Safety wires there will be two sets of M.S.PLATE connected AT BASE SECTIONS [DIAGONALY OR 90 DEG.APART FROM DOOR] Design Loading The Mast sections shall be designed keeping in consideration on following:a) Design wind speed to be calculated based on Topography Factor/ Terrain Category / Probability of Maxim wind speed [at least once in 25 years’ time.].i.e. Risk Co-efficient Factor Guided w.r.t life of Structure. Mast should be designed based on basic wind speed data as mentioned at 10m level from IS875; Part-III; 1987. [ Basic Wind speed : 44m/s at 10m height to be considered for design ]Also with respect to Height it should be calculated; for compliance of Wind loads. As per Respective heights. Using I.L.E.TR-7/IS875 formula for Calculation of Design Wind speed at 10m level also for respective heights. b). Luminaries Wind blockage for Particular arrangements /head frame /accessories like Lantern Ring to be considered c) The loads due to the weight of Columns/ Head frame/ winch load/ lantern ring/ luminaries arm assembly/luminaries loads. d) Adequate care should be taken for base plate selection. Door size selection/ stiffeners selection. e) Wind load factor/ Materials load factor to be considered as per ILE.TR-7 Guide f) Ground level bending moment /Longitudinal shear force to be calculated not on basis of Dynamic Pressure always on Equivalent- static Pressure. g) Shape Factor / Response Factor to be considered based on Mast height / Mean Hourly Wind speed/ Natural frequency [as per Manufacturer Guide line]. Response factor for Normal condition as well as For Deflection Calculation should be as per Log Decrement Curve 0.001[Class-A] specified in ILE.TR-7. h) Foundation design should be guided based on Soil bearing capacity of Site i) j) k) l) m) n) o) p) locations/ Factor of safety Check for Sliding should be > 2.0 Check for Over turning should be > 2.0 For concrete /reinforcement design should be as per IS875. Minim. Depth 1.8m to be used irrespective of Mast heights/dead Load/ wind load. Concrete Columns will have always Rise from Respective Ground level Min. 300 mm. A clear gap should be maintained between Top of Concrete Column / Bottom most of Steel Mast for Ventilation purpose. Mast + Foundation design should comply acceptance norms of IS 875 for Wind load ILE.TR-7 for Manufacturing. Structural stability Compliance as required By ILE.TR-7 & confirmation as per BS5649, Part-7 OTHER ACCESSORIES FOR HIGH MAST HEAD FRAME M.S Fabricated hot dip galvanized housing; using IS2062 Steel grade; having facility for accommodation of 3nos steel wires Pulleys in Upper Tier / 3nos Pulleys in lower tier for Flat Cables. Pulleys are grooved suitably & extreme care has been taken to get maxim facility of breaking capacity of steel wires. Also smaller diameter pulleys are used for Electrical flat cable to avoid any unwanted loose grips /snaps while raising up/lowering down.3 Compartments are placed on 120 degree apart for best balancing facility of luminaries while movement of Raising/lowering. Further no chance of Unbalance. Head frame is having top canopy in Triphodal shape to protect entire Masts from environmental condition. Head frame covers are well protected from entry of birds / having provision for fixing Lightning arrestor on the top of the Masts. To Fix Lighting arrestor is mandatory for any High Mast Structures. Lightning Process completes considering highest shaft as a carrier & it has got a provision for fixing Ear thing point at the base of a Mast. As per ILE. Guide line all luminaries will be protected; as such Height of the Lightning arrestor should be minim. 1.2 m to cover [60 degree all along] of circular area. LANTERN RING/ GUIDE RING Unless required on special design normally a 3-point connection Circular ring of 1600 mm dia. is used. There is a provision for fixing of steel wires; also a guide ring is inbuilt which protects Mast surface while lowering down/ raising up mechanism. Lantern ring are adequately designed using square tube of MS fabricated & 3 sections will be joined at site. Lantern ring will safely accommodate 1000kgs dead load including Luminaries/ Luminaries Arm assembly In case arrangements of Luminaries / no of luminaries are more for Mobile application of Mast we recommend use of Double ring assembly which is interconnected vertically keeping minim. Spacing between the rings as 1200mm height. Interconnection of the ring will be at site by using holding down square tube of MS Fabricated/ Hot dip galvanized sections & interconnection will be by using “U” bolts. LUMINAIRES ARM ASSEMBLY Luminaries / cg box mounting arrangements we provide 900mm length MS Fabricated hot dip galvanized luminaries arm assembly. Each arm can accommodate 2nos Twin Flood light ups/down in the front of the assembly & necessary CGBOX can be mounted in reverse side. Luminaries loading will be front side whereas Control gear box will be in reverse side for balancing of load. Maximum loading on Luminaries assembly is restricted for 450mm/ 900 mm length in totality for Luminaries/ cg box maxim. 70kgs. Suspension arrangements between lantern ring /winch through compensating disc. Suspension Wires arrangements Suspension wire by using Steel wires of 3nos of 6mm dia. [As per AISI –316 Grade; 7x19 construction having tensile strength of 160-180kgf/sqmm. Breaking load capacity: 2300kgf for 6mm wires we use. Factor of Safety………….. Not less than 5.0. Steel wires are connected at Lantern ring using adequate “D” shackle; recommended with respect to diameter of wires. We use “Thimble “as base for end connections. Other ends to compensating disc. COMPENSATING DISC A separator of MS Construction duly galvanized having provision for fixing 3nos suspension wires on Upper deck at 120 degree apart. Also having provision of fixing two nos. wires from Double drum winch. Further it has got a provision to connect safety wires from Base of Mast. Both sides. Shape/size is used for free movement of C/disc up to top of Mast. Normally when Lantern carriage is at Mast Top; Compensating disc position will be just near Door Location Compensating Disc is mandatory as per I.L.E.TR-7. Compensating disc allows holding of suspension wires in case of requirement of dismantling of D/D Winch .by way of connecting to safety wires. Safety Wires arrangements: We provide at base sections of mast diagonally on two phases a provision of fixing holes. By way of attachment/welded properly with the mast sections. Role of this provisional hole to attach safety wires one end & other end to the bottom of compensating disc. This is a parallel arrangement instead of direct load on winch always. Also helps system to remove winch from the system. DOUBLE DRUM WINCH /STEEL WIRES ARRANGEMENTS A self-Sustaining type Double Drum winch will be provided checking necessary Load to be carried for lowering down/ raising up mechanism./maintenance cage operation. Double drum winch is an item which needs a periodical check for lubricating items/ status of gear teeth. This needs at least 3 months interval checking. Even all luminaries are at full glow condition winch needs operation to reset steel wires; which might have shifted due to wind load changes frequently. Due to its Self-sustaining arrangements it does not require any additional Mechanical locking. It has a capacity to station lantern ring at any position in case Electrical Hoist Motor is disengaged. Material for Construction of Gears………High carbon steel/ Phosphor Bronze. Gear Ratio………………………………………..53: 1.0[Self Lubricating] Capacity [In terms of Safe working Load] ; 1200kgs. Lubrication arrangements…………….………Self-lubricating in Oil baths. Type of Lubricants………………………….…. Castrol EP-140/ Equiv. Operating speed of Winch………………...…..180 R.P.M Suitable Electrical Motor speed……………...1400 R.P.M Method of Operation…………………………...Pendant Switch Control. Capacity /Applied Load [Maxim]……………. Winch can be loaded max 80%. Winch operation……………………………..….Manually by using Handle. Electrically…. By Power tool Operation Time………………………………….3M. Per Minutes. Winch Wires/ Size……………………….……. .A pair of bobbins duly having provision of fixing two nos steel wires. Steel wires sizes recommended……………. Up to 1000 kg capacity[ 6mm] [braking load capacity:2300kgf/sqmm] For 1400 kg capacity[8mm] [braking load capacity:3000kgf/sqmm] ELECTRICAL HOIST CABLE A PVC cable; PVC INSULATION COPPER CORE of normally 5corex 4 sq.mm provided between Junction box attached to Lantern Ring/ base of the Masts. Current carrying Capacity trailing cable purpose is minm.22 Amps. Flat cables facilities rotation on minim. Space / no chance of loose gripping on pulleys attached to head frame. Each copper round cables of 5cx4sq.mm will be used as under; 1core…….. “R” Phase. 1 core………”Y” Phase. 1 core……….” B” Phase. 1 core……… Neutral. 1core……….. Earthing. Each 5cx4 sq. mm copper cable can accommodate maxim. 9nos 1x1000 w flood lights/ 6nos 2kw metal halide. Cable-socket: Round cable Base Ends will have one set of suitable Socket for 5-pin [Male-Female] Socket suitable for 5cx4sq.mm PVC copper Cable. Junction Box : A Suitable connecting device between luminaries/ Trailing cables. Incoming is always trailing cable / Outgoing No. of ways to cater luminaries electrical connections. A MS Fabricated IP-55 version Distribution board with suitable no. of out goings w.r.t Luminaries will be provided. a) 12 way. Or its’ Multiple depending On Luminaries Load on High mast POWER TOOL ARRANGEMNTS[Built-in type] This is a combination unit designed as per winch capacity. Power tool consists of 3phase 415volts; 50c/s supply .A gear box to match winch gear ratio & coupled with the motor. A controlling unit for Rotation changes of motor with having provision of Torque limiter; by way of using Electronic Circuits to provide Electrical Protection. A minm.5Mts length control cables are used for using push button control from a safe distance of Mast. RANGE TO BE USED WITH MATCHING WINCH CAPACITY. 2.2 KW POWER TOOL………….FOR 1200 KGS. Dead Load on Lantern Structure [30M Mast with 12nos 2kw Flood Light – Asymmetric Loading MANUAL HANDLE. Each high mast for maintenance purpose needs initially to acclimatise a static winch for a long time. There role of Manual handle to start movement of winch wires slowly so that system comes in practice; then engage Power tool for faster operation. While reaching at Mast Top Lantern carriage needs safe docking. Here again comfortable docking is possible by the help of Manual handle. It is always recommended to use in the beginning at least 0.5m.also at the end 0.5m with the help of Manual Handle. ELECTRICAL DISTRIBUTION BOARD AT THE BASE OF MAST. Wooden base board Non-Hygroscopic provided at the base of the mast near Mast Door. This will have primarily a M.C.B comparing Lighting load of Mast. M.C.B will terminate In-coming cables of Supplies./can be used as a local isolator for maintenance work. Combination of Female sockets which has been explained earlier ; also a 5-pin Power socket for 3-phase Power tool operation External Feeder Pillar Box[Near High Mast Location] To have better control of adjacent mast/ In-coming supplies/making use of auto switching for regular operation it is always recommended to provide an External Control Panel, whose Out-going will be used as In-coming to Mast supplies. Timer provision will be there for day to day operation Automatic against pre time set. Substation: This Project involves Outdoor Sub-Station which are distributed in various locations of ORR. All these substation shall have technical specification which will be as under SCOPE These sub-stations shall be used for locations covering long distances & wide areas where standby transformers are not installed. There use shall normally be restricted to 250KVA. They shall be preferred where Out door type D.P./S.P Structure. along with connected control switchgear is proposed in open space. Sub-station shall consist of double /Single pole structure with AB switch, pole mounted Transformer up to 250KVA with all connection accessories, fitting & auxiliary equipment as per Telangana State SPDCL specifications. The transformer’s L.T. side shall be connected to L.T. Switchgear. The connection cables to consumer shall be taken out from the L.T. switchgear (s). Out Door Type Transformers 11kv/415v; 63/100/125/160 & 250KVA Out-door Type Transformer [Delta on Primary side / Star Connection with Neutral on Secondary side Technical Specifications Distribution Transformer 63KVA Out door type Transformer Supply, transportation and delivery at site of 3 Phase, 50 Hz, oil immersed and naturally cooled, outdoor type of 63 KVA CSP CRGO aluminum wound transformer designed and manufactured as per APCPDCL specifications/IS 2026-1977 and 1st filling of oil as per IS 335 of 1993, connected delta on primary side and Star on secondary side with additional neutral brought out on load side, 1100V / (433V / 415V) with HV tapping + or - 2.5% continuously rated for full load and temperature rise not exceeding 50°C in oil and 55°C rise by the resistance of the winding after continuous run on full load rating complete with the following standard mountings. 1. Rated KVA : .63KVA 2. Service: Outdoor r 3. Mounting : Plinth. 4. Copper wound : Aluminum. 5. Type : Core.(CRGO) 6. Cooling : ONAN 7. Temp . Rise : 55⁰C. 8. Vector Group: Dyn 11 9. Primary Connection : Delta 10. Primary Volts : 11000 11. Primary Frequency : 50 12.Primary Phases : 3 13. Primary wires: 3 14. Secondary connection : Star 15. Secondary Volts : 415 / 433V 16. Secondary phases : 3 17. Secondary wires: 4 18. Taps on primary winding for primary voltage variation : +7.5% to - 7.5% in steps of 2.5%, 19. Terminal arrangement. a. HV: Bare Bushings / Cable end box b. LV : Cable box 20. LV : One separate terminal for earthing. 20. No load losses (Watts): .As per IS specification 21. Load losses (Watts): ..As per IS specification 22. Impedance(Z%) : ......As per IS specification 100KVA Out door type Transformer Supply, transportation and delivery at site of 3 Phase, 50 Hz, oil immersed and naturally cooled, outdoor type of 100 KVA CSP CRGO aluminum wound transformer designed and manufactured as per APCPDCL specifications/IS 2026-1977 and 1st filling of oil as per IS 335 of 1993, connected delta on primary side and Star on secondary side with additional neutral brought out on load side, 1100V / (433V / 415V) with HV tapping + or - 2.5% continuously rated for full load and temperature rise not exceeding 50°C in oil and 55°C rise by th resistance of the winding after continuous run on full load rating complete with the following standard mountings. 1. Rated KVA : 100KVA 2. Service: Outdoor r 3. Mounting : Plinth. 4. Copper wound : Aluminum. 5. Type : Core.(CRGO) 6. Cooling : ONAN 7. Temp . Rise : 55⁰C. 8. Vector Group: Dyn 11 9. Primary Connection : Delta 10. Primary Volts : 11000 11. Primary Frequency : 50 12.Primary Phases : 3 13. Primary wires: 3 14. Secondary connection : Star 15. Secondary Volts : 415 / 433V 16. Secondary phases : 3 17. Secondary wires: 4 18. Taps on primary winding for primary voltage variation : +7.5% to - 7.5% in steps of 2.5%, 19. Terminal arrangement. a. HV: Bare Bushings / Cable end box b. LV : Cable box 20. LV : One separate terminal for earthing. 20. No load losses (Watts): .As per IS specification 21. Load losses (Watts): ..As per IS specification 22. Impedance(Z%) : .............As per IS specification 160KVA Out door type Transformer Supply, transportation and delivery at site of 3 Phase, 50 Hz, oil immersed and naturally cooled, outdoor type of 100 KVA CSP CRGO aluminum wound transformer designed and manufactured as per APCPDCL specifications/IS 2026-1977 and 1st filling of oil as per IS 335 of 1993, connected delta on primary side and Star on secondary side with additional neutral brought out on load side, 1100V / (433V / 415V) with HV tapping + or - 2.5% continuously rated for full load and temperature rise not exceeding 50°C in oil and 55°C rise by th resistance of the winding after continuous run on full load rating complete with the following standard mountings. 1. Rated KVA : 160KVA 2. Service: Outdoor r 3. Mounting : Plinth. 4. Copper wound : Aluminum. 5. Type : Core.(CRGO) 6. Cooling : ONAN 7. Temp . Rise : 55⁰C. 8. Vector Group: Dyn 11 9. Primary Connection : Delta 10. Primary Volts : 11000 11. Primary Frequency : 50 12.Primary Phases : 3 13. Primary wires: 3 14. Secondary connection : Star 15. Secondary Volts : 415 / 433V 16. Secondary phases : 3 17. Secondary wires: 4 18. Taps on primary winding for primary voltage variation : +7.5% to - 7.5% in steps of 2.5%, 19. Terminal arrangement. a. HV: Bare Bushings / Cable end box b. LV : Cable box 20. LV : One separate terminal for earthing. 20. No load losses (Watts): .As per IS specification 21. Load losses (Watts): ..As per IS specification 22. Impedance(Z%) : .............As per IS specification Code & Standards: All equipment and material shall be designed manufactured and tested in accordance with the latest applicable Indian Standard. IEC standard and CBIP manuals except where modified and / or supplemented this specification. Equipment and material confirming to any other standard, which ensures equal or better quality, may be accepted. In such case copies of English version of the standard adopted shall be submitted. The Transformer offered shall in general comply with the latest issues including amendments System Description: The distribution transformers shall be installed at outdoor/indoor location along 11 kV distribution networks, which consists of both underground and overhead network. The HV winding would be connected to SFU/OCB/VCB of the ring main unit through 11 kV (E) XLPE/PILC cable. LV winding would be connected to switch type Fuse section pillar through 2 nos 1.1 kV 3.5c, 185 sq mm XLPE cable Design Criteria: The transformers shall be installed in hot, humid tropical atmosphere. All equipment accessories and wiring shall be provided with tropical finish to prevent fungus growth The transformers shall be capable of continuous operation of rated output under the operating conditions of voltage and frequency variations as per statutory limits governed by relevant Indian Standard and Electricity Act-2003 and its amendments in force. The transformer shall conform to best engineering practice. The design material construction shall be such that to secure reliability, economy, safe and convenient operation and shall include all specified or unspecified incidental items necessary for similar equipment for convenient working in every respect. The transformers shall be capable of withstanding the short circuit stresses due to terminal fault between phase to phase and phase to ground on one winding with full voltage maintained on the other windings for a minimum period of three seconds. The transformers shall be free from annoying hum or vibration. The design shall be such as not to cause any undesirable interference with radio or communication circuits. Atmospheric Condition: The equipment offered shall be suitable for continuous satisfactory operation in following prevailing climatic conditions. All three varieties of Transformers will be installed externally on Double Pole Structure as per State Electricity Rules for Installation. Specific Requirement Requirement: 11000/433 Volt Oil immersed, 63/100/160/315 KVA double wound, core type suitable for installation. Voltage Ratio: No load voltage 11000/433 volts within tolerance as stipulated in IS: 2026. Rating: The transformer shall have a continuous rating as specified at any of the specified tapping position and with the maximum temperature rise specified. The rated KVA shall be the product of the rated voltage in kV, the corresponding rated current and the phase factor 1.73. When the transformer is operated with the rated primary voltage applied to the terminals of the primary winding, the apparent power (kVA) at the terminals of the secondary winding, when carrying the rated secondary current differs from rated kVA by an amount corresponding to the regulation of the transformer and is the product of the actual secondary voltage, the rated secondary current and phase factor 1.73. System: 11000 volts A.C., 50 Hz supply, having non-effectively earthed neutral (resistively earthed) system on H V side. The 11 kV systems shall have basic insulation level of 36 kV for one minute / 95 kVp impulse and maximum fault level of 26 kA. 433 Volts A.C, 50 Hz supply shall be rated for 1.1 kV grade and basic insulation of 3 kV for one minute and 7.5 kV p impulse. The variations in input and output supply shall be as per statutory variation governed by relevant Indian Standard and Electricity Act-2003 with latest amendments in force. The L.V. neutral shall be earthed solidly at each transformer substation. The transformers will be connected in a system Consisting of both overhead and underground mains Temperature Rise: The maximum temperature rise at the specified maximum continuous output shall not exceed 40ºC by thermometer in the hottest portion of the oil or 50ºC measured by resistance of winding above ambient temperature of 47ºC. Type of Load: The transformer shall be suitable for carrying load within temperature rise indicated in the Indian Standard specification IS: 6600 ‘Guide for loading of oil immersed Transformer’. Overloads: The transformers shall be suitable for carrying overload within temperature rise indicated in IS: 6600 ‘Guide for Loading of oil immersed Transformer’. Connections: H.V. Delta and L.V Star connected with neutral brought out on the secondary side for connection to earth; Vector group DYn11 of IS: 2026. Tank The transformer tank and cover shall be fabricated from robust M.S. plate steel without pitting and shall have adequate thickness (Top cover 6 mm min., side plates 5 mm min., Bottom plate 6 mm min.) with either external cooling tubes or radiators as per purchaser’s requirement. The tank and cover shall be of welded construction. All seams shall be welded and where practicable they shall be double welded. All edges shall be double welded. The tank wall shall be reinforced by 2 withstand without any deformation the mechanical shock during transportation. Detachable radiators shall be provided. The shut off valves for radiators should be supplied if required by purchaser. All removable covers shall be provided with weatherproof, hot oil resistant, resilient gaskets. The design shall be such as to prevent any leakage of water into or oil from the tank. The tank shall be subjected to a pressure test of 0.35 kg/cm2 with hot oil for 12 hours when the transformer is complete with all fittings. During the test average oil temperature shall be maintained at 45ºC above Ambient temperature throughout test period by circulating suitable current in H.V. winding and short circuiting L.V. winding. There shall be no leakage of oil during or after the test. Also there shall be no deflection at all when the pressure is removed. The purchaser’s representative may be present during these tests for which advance intimation shall be given. Otherwise, test Certificate shall be produced in triplicate before dispatching the units. The top cover of the tank shall be suitably sloped to facilitate water drain off and shall be so designed as to facilitate lifting of the same, in case required, with minimum disconnection of pipe work and accessories. Air release plugs shall be provided on main tank top cover to cover entire area suitably. Cleaning & Painting: All steel surfaces shall be thoroughly cleaned by Sand blasting or chemical agents, as required to produce a smooth surface free of scales, grease and rust. The terminal surfaces in contact with insulating oil shall be painted with heat resistant and insulating-Oil resistant paint, which shall not react nor be soluble in the insulating liquid used. The external surfaces, after cleaning, shall be given two coats of high quality rust resisting primer as per IS: 2074 with latest amendments thereto followed by two coats of weather resisting battleship poly urethane paint specially recommended for transformer use The paints shall be carefully selected to withstand tropical heat rain, and other environmental effects. The paint shall not scale off or crinkle or be removed by abrasion due to normal handling. Sufficient quantity of touch up paint shall be furnished for application after installation at site. Special care shall be taken by the manufacturer to ensure against rusting of nuts, bolts and fittings during operation. All bushings and current carrying parts shall be cleaned properly after final painting. Cable Boxes The transformer shall be fitted with suitable cable box on 11 kV side to terminate one 11kV/ 3C Aluminum conductor XLPE/PILC cable up to 2x185 sq. mm. size as per standards. The Bidder shall ensure the arrangement of H.T. Cable box so as to prevent the ingress of moisture into the box due to rainwater directly falling on the box. The cable box on H.T. side shall be of the split type with faces plain and machined and fitted with Neo-k-Tex or similar quality cork sheet gasket and complete with brass wiping gland to be mounted on separate split type gland plate with nut-bolt arrangement and M.S. earthing clamp. The bushings of the cable box shall be fitted with nuts & stem to take the cable cores without bending them. The stem shall be of copper with copper nuts. The cross section of the connecting rods shall be stated and shall be adequate for carrying the rated currents. On the HV side the terminal rod shall have a diameter of not less than 12mm. The material of connecting rod shall be copper. H. T. Cable support clamp should be provided to avoid tension due to cable weight. The transformer shall be fitted with suitable LV cable box having non-magnetic material gland plate with appropriate sized single compression brass glands as per the attached drawing on LV side to terminate 1.1 kV /1C XLPE armored cable as mentioned herein below. Terminal: Primary: 12 kV Epoxy bushings as per IS: 2099 for heavily polluted atmosphere having suitable diameter with nuts and check nuts for pad and platform mounted transformer as per drawing. If required by purchaser, 12 kV Porcelain bushing as per IS: 3347 for heavily polluted atmosphere having suitable diameter with nuts and check nuts for pole mounted transformer. Secondary: Terminals shall be provided with 1.1 kV Epoxy bushings as per IS: 3347 for heavily polluted atmosphere having fixed palm type connectors with suitable locking arrangements to restrict the rotation of palm assembly. The palm shall be of copper and stud of copper duly brazed at the joint. A suitable clamping arrangement shall be provided so as to clamp the 1/C x 400mm2 XLPE /PVC cables as per the details given here below for different size of the transformers. Each clamp shall be detachable type with nut bolt arrangement for ease in removal/replacement of LV cables. Epoxy bushings Clamp arrangement with copper/brass terminal assembly is required. Two holes of 13 mm diameter for long palm double hole lug with 2 nos. of ½ ” zinc passivated bolts with suitable spring washers and hole spacing as per the drawing to connect 1 no. of 400 sq. mm. 1C PVC/XLPE LV cable per phase with AL/CU sockets. If required by purchaser, one hole of 20 mm diameter with 1 no. of ¾“ zinc passivated bolts with suitable spring washers and hole spacing as per the drawing. 15 kV Epoxy bushings as per IS: 2099 for heavily polluted atmosphere having fixed palm type connectors with suitable locking arrangements to restrict the tension on bushing fixing. The palm shall be of copper. Both H.V. and L.V. bushings of Epoxy cast resin shall have creep age corresponding to heavily polluted atmosphere. Oil The necessary quantity of new transformer oil according to IS: 335 shall be supplied & filled in the transformer tank up to a height above the minimum filling mark of conservator tank. The Supplier shall furnish the relevant technical particulars and test certificates of the oil supplied. An additional 10% of the total quantity of oil required shall be supplied loose along with the transformer. Leakage of Oil: Suitable approved type of material such as “Neoprene” of RC 70 C grade which has an oil proof agent, as specified in IS: 1866 shall be provided at all joints to prevent leakage of oil during continued operation or during transportation. Drying-Out: The transformer winding shall be thoroughly dried out & kept immersed in oil to avoid any further drying out by the purchaser & to facilitate immediate commissioning of the transformer on receipt. Clamping of Leads: All leads from the coils to the terminals shall be suitably clamped to prevent snagging and fouling with other parts and the tank. Phase Marking: Phase markings as per IS: 2026 punched on small non-corrosion metallic tags shall be permanently fixed for H.V. just below the cable box or on some suitable removable part of the tank and above L.V. Bushings. Phase markings tags shall be properly fixed with proper alignment. Core and Coil: The transformer may be of core type. The core shall be built up with high grade, non-aging, low loss, high permeability, grain oriented, cold-rolled silicon steel laminations especially suitable for core material. The grade of core lamination shall be premium grade M-OH or better quality with appropriate thickness. The transformer shall be so designed as to have minimum humming noise. The coils shall be manufactured from electrolytic copper conductor and fully insulated for rated voltage. Copper for winding shall be purchased from ‘Original Copper Manufacturer’ for the capacities from 250KVA and 315KVA. For 63KVA to 160KVA, the aluminum coils shall be manufactured as per TSSPDCL standards. Insulating material shall be of proven design. The insulating material shall be class `A' specified as per IS: 1271 with latest amendments thereto. Coils shall be so insulated that impulse and power frequency voltage stresses are minimum. Due consideration shall also be given to the fact that the transformers will be connected at the end of 11kV and 433V overloaded feeders, in a lightning prevalent area. Coil assembly shall be suitably supported between adjacent sections by insulating spacers and barriers. Bracing and other insulation used in assembly of the winding shall be arranged to ensure a free circulation of the oil and to reduce the hot spot of the winding. All leads from the windings to the terminal board and bushings shall be rigidly supported to prevent injury from vibration or short circuit stresses. Guide tube shall be used wherever practicable. The core and coil assembly shall be securely fixed in position so that no shifting or deformation occurs during movement of transformer. The core and coil assembly shall be capable of withstanding without injury, the thermal and mechanical effects of short circuit at the terminals of any winding as per IS: 2026 with latest amendments thereto. Insulation Level: The transformer shall be designed to withstand the following. Losses: The transformer losses at 750 C and at normal tap without any positive tolerance shall be as per IE Rules. NOTE: These are maximum permissible values with no positive tolerance. The maximum losses specified as above will be binding on the supplier and any unit, which exceeds these losses, shall be rejected. Percentage impedance The % impedance at 750c temp. For 315 kVA transformer shall be 5%. Regulation: The regulation at 75º C at full load at unity and 0.8 power factor subject to the usual tolerance as per IS: 2026 shall be specified in the bid Over fluxing: The transformer shall be suitable for over fluxing (due to combined effect of voltage and frequency) up to 10% of any tapping without injurious heating at full load conditions.I Maximum efficiency: The distribution transformer shall be designed so as to ensure that the maximum efficiency of the transformer is at the loading above 60 % and the same shall be verified during routine test failing which the same shall be liable for rejection. C.T.’ s with accessories : The current transformers of rating as specified below shall be provided on LV side of the Transformer. C.T.’ s shall be mounted on L.V. Bushing & supported by Bakelite sheet of adequate thickness affixed to main tank by nut-bolt arrangement. It shall be possible to replace these C.T.s by removing fixing nuts of Bakelite sheets after removal of L.T. cable from bus bar without disturbing L.T. Bushings. SL. No. Particulars 315KVA 1 Current Ratio 400/5 Amps 2 Class Of Accuracy 0.5 3 Burden 5 VA 4 Type Resin Cast, Ring Type Suitable for Out-door use The Secondary Terminals of the C.T.’s shall be brought out by using 2.5mm2 multicore, flexible copper cable (with colour coding, and ferrules at both ends) in conduit to the sealable junction box which shall be located outside the Transformer enclosure fixed at a suitable height. Similarly, three phase voltages shall be tapped from the L.T bus bar and brought out in the junction box. Fittings & Accessories: The following accessories conforming to IS: 3639 shall be provided. Oil conservator with drain plug, oil filling hole with blanking plate and oil level indicator with minimum level marking. Conservator tank shall have capacity of for storing 10% of total oil in main tank. Oil level indicator shall be so designed that it indicates 10% to 90 % oil quantity in conservator tank. Normal level shall be marked at 50% of oil level indicator. Silica gel breather shall contain minimum 0.5 kg dehydrated silica gel for 315 kVA size. The Breather shall be connected with conservator with pipe having ¾” diameter. Pressure relief vent Earthing terminals- 2 nos. Lifting lugs Air release plug Oil filling hole with plug Oil drain outlet with sampling facility without valve at the bottom of the main tank with plug or Oil drain outlet with Stainless steel full turn type valve along with valve guard at the bottom of the main tank as per purchaser’s requirement Oil filter inlet without valve and with plug or with Stainless steel full turn type valve as per purchaser’s requirement. Jacking lugs Oil Temperature Indicator of Mercury in steel type with Maximum Temperature Indicator, if required by purchaser. Four nos. of unidirectional flat rollers to facilitate the rolling of transformer in the direction parallel to the side where the terminals have been brought out. LV cable frames with clamps to hold (as per the submitted drawing) o One or Two nos. of 400 sq. mm, 1 core XLPE cable per phase for 250 kVA & 315 kVA transformer and if required by purchase, 1 no. of 240 sq. mm. 3.5 C PVC cable. The rating plate shall be as per the sample provided by the purchaser and shall indicate particulars as may be specified including No load and Copper losses, date of manufacture, order no. etc. Tests: Routine Tests: Following tests shall constitute the routine test. All transformers or a part of the order quantity as may be desired by the purchaser shall be subjected to routine tests as per IS: 2026. All results obtained during the tests shall be furnished to the HGCL and TSSPDCL in triplicate for approvals. Measurement of winding resistance. :Ratio, polarity and phase relationship. Impedance voltage :No load losses and no load current : Load losses Insulation resistance :Induced over voltage withstand test Separate source voltage withstand test :Unbalance current test(unbalance current should not be more than 2% of full load current in neutral at full load condition Tests : Impulse volage test: Temparature rise test , Short circuit test, heat run test. The above tests may or may not be the part of the order but the offer shall specify the cost of these tests, if any. The equipment offered shall be fully type tested as per the relevant standards. In case the equipment of the type and design offered has already been type tested, the bidder shall furnish the type test reports along with the offer. Contract Drawing: An outline drawing front (both primary and secondary sides) and End-elevation and plan of the tank and terminal gear, where in the principal dimensions shall be given. Typical general arrangement drawings of the windings with the details of the insulation at each point and core construction of transformer. Typical general arrangement drawing showing both primary and secondary sides and End-Elevation and plan of the transformer. All the above except the typical drawing shall be given by the particular drawing of the transformer to be supplied Conditions & Requirements: Bidder must specifically confirm that the following will be complied with 20.1 HV and LV bushings shall be on the opposite sides of the transformer main tank. HV bushing shall be mounted at an angle perpendicular to the main tank. Transformer shall be designed for 11 kV non-effectively earthed system. Details in the Data-Sheet: The bidder shall furnish the details of transformer in the data-sheet as attached herewith. Deviations: The Bidders are not allowed to deviate from the principal requirements of the Specifications. However, the Bidder is required to submit with his bid in the relevant schedule a detailed list of all deviations without any ambiguity. In the absence of a deviation list in the deviation schedules, it is understood that such bid conforms to the Bid Specifications. Inspection: In respect of raw material such as core stampings, winding conductors, insulating paper and oil, you shall use these materials manufactured/supplied by standard manufacturers and furnish the manufacturers’ test certificate as well as the proof of purchase from these manufacturers (excise gate pass) for information of the company. The bidder shall furnish following documents along with their offer in respect to the raw materials. Invoice of supplier, Manufacturers certificate, Packing list, Bill of landing.& Bill of entry certificate by custom GUARANTEE FOR THE TRANSFORMERS Guarantee period shall be 60 months from the date of commissioning. If any transformer fails during this guarantee period, the supplier shall repair the same at his cost at his works. The supplier situated outside Hyderabad State shall have to establish suitable andadequate arrangement for repairing and testing of failed transformer in Karnataka State at his cost. This arrangement shall have to be continued up to the completion date of guarantee period of supply of last lot. General Distribution Board Specifications: All MDB’s/ SDB’s/ DB’s should be provided with polythene/PVC plastic cover to protect them from rust/damages, during execution of work till the work is actually completed and handed over to the department. The loose wire boxes/cable end boxes (adaptor boxes) shall be provided on the various electrical boards to facilitate the termination of the wiring in the various mountings. The boxes shall be of the same make as the DB’s as far as possible. Wherever the company made cable end boxes are not available they shall be neatly fabricated with 16 SWG CRCA sheet steel, duly powder coated, dust & vermin proof and the front cover of MS sheet shall be with rubber gasket suitably screwed or with 3mm thick phenolic laminated sheet of Hylam/ Formica instead of MS sheet, as desired by the Engineer-in-charge. The length of such boxes shall be same/or more as the width of the electrical switchboard. Such loose wire boxes are deemed included in the scope of the work and no extra payment shall be made for them. All floor-mounted panels shall invariably be provided with 200mm height blank cubicles at the bottom and shall be mounted on 75mmX75mmX6mm thick M.S. channel on all the sides. It shall have a continuous earth bus of the same size and material as the main phase running continuously along the length of the panel extending on either side for earth connection. The doors of all cubicle panels shall be hinged type including those of bus bar chambers and cable Alleys. The locking shall be with chrome plated metal key locks. All doors shall be earthed with copper conductor wire as approved by the Engineer-in-charge. All panels/DB’s shall be suitable for 50ºC ambient temperature. The MCB should be of the same make as that of MCB DB’s. Contractor shall obtain approval of the Engineer-in-charge before procurement of MCB DB’s. Cables and wires will be connected to MCB’s through screw less connectors. All model of modular accessories required for the work shall be got approved from the Engineer-in-charge from among the approved makes. The base plate shall be preferably in sheet steel or otherwise in unbreakable polycarbonate/ABS. The cover plates shall be screw less type in shade approved by the Engineer-in-charge. The MCCB’s shall be compatible for microprocessor based circuit breaker control modules for reliable protection and accurate measurement. The rated Service breaking capacity (kArms) shall be 100% of Ultimate breaking capacity (kArms). All MCCB’s shall be current limiting type with features of load-line reversibility and suitable for horizontal as well as vertical mounting without any de-rating. MCCB’s shall be used with terminal spreaders and all terminals shall be shrouded to avoid direct contact. Cables and wires will be connected to MCCB’s through screw less connectors. Mechanical Castle key interlock shall be provided between the incomer MCCB’s, wherever two different incomer sources are provided in the panel, as per the directions of the Engineer in charge. The same is deemed included in the scope of work. All measuring and indicating instruments shall be protected through fuses/ MCB’s and isolating switches. All work should be carried out as per drawings and specifications and as approved by the “Engineer- in- Charge”. L.T CABELS 1. GENERAL L.T. Cables shall be supplied, inspected, laid, tested and commissioned in accordance with drawings, specifications, relevant Indian Standards, CPWD specifications and cable manufacturer’s recommendations. The cable shall be delivered at site in original drums with manufacturer’s name clearly written on the drums. The recommendations of the cable manufacturer with regard to jointing and sealing shall be strictly followed. 2. MATERIALS The LT Power cables shall be XLPE insulated PVC sheathed type aluminum conductor armoured cable conforming to IS : 7098 : Part-I : 1988 with up-todate amendments and also PVC insulated copper conductor armoured cable conforming to IS:1554 : Part I : 1988 whereas control cable shall be PVC insulated copper conductor armoured/ unarmoured cable conforming to IS: 1554 : Part-I : 1988. 3. INSTALLATION OF CABLES Cables shall be laid directly in ground, pipes, masonry ducts, on cable tray, surface of wall/ceiling etc. as indicated on drawings, BOQ and/or as per the direction of Engineer-In-Charge. Cable laying shall be carried out as per CPWD specifications. 4. INSPECTION All cables shall be inspected at site and checked for any damage during transit. 5. JOINTS IN CABLES The Contractor shall take care to see that the cables received at site are apportioned to various locations in such a manner as to ensure maximum utilisation and avoiding of cable joints. This apportioning shall be got approved from Engineer-In-Charge before the cables are cut to lengths. 6. LAYING CABLES IN GROUND Cables shall be laid by skilled experienced workmen using adequate rollers to minimize stretching of the cables. The cable drums shall be placed on jacks before unwinding the cable. With great care it shall be unrolled on over wooden rollers placed in trenches at intervals not exceeding 2 metres. Cables and other accessories shall be laid as per CPWD specification and other relevant IS codes. Cable shall not be laid in the same trench or alongside a water main. At all changes in direction in horizontal and vertical planes, the cables shall be bent smooth with a radius of bent not less than 12 times the diameter of cables. Minimum 3 meter long loop shall be provided at both end of cable. Distinguishing marks may be made on the cable ends for identifications of phases. Insulation tapes of appropriate voltage and in red, yellow and blue colours shall be wrapped just below the sockets for phase identifications. PROTECTION OF CABLES The cables shall be protected by bricks laid on the top layer of the sand for the full length of underground cable. Where more than one cables is laid in the same trench, the bricks shall cover all the cables and shall project a minimum of approximately 80mm on either side of the cables. Cable under road crossings and any other places subject to heavy traffic shall be protected by running them through Hume Pipes of suitable size. EXCAVATION & BACK FILL All excavation and back fill required for the installation of the cables shall be carried out by the Contractor in accordance with the drawings and requirements laid down elsewhere. Trenches shall be dug true to line and grades. Back fill for trenches shall be filled in layer not exceeding 150mm. Each layer shall be properly rammed and consolidated before laying the next layer. The Contractor shall restore all surface, roadways, sidewalks, kerbs wall or the works cut by excavation to their original condition to the satisfaction of the Engineer-In-Charge. LAYING OF CABLES ON CABLE TRAY/SURFACE OF WALL / CEILING Cable shall be laid on perforated M.S. Cable tray. Cables shall be properly dressed before cable ties/clamps are fixed. Wherever cable tray is not proposed, cables shall be fixed on surface of wall or ceiling slab by suitable MS clamps/ saddles. Care shall be taken to avoid crossing of cable. CABLES ON HANGERS OR RACKS The Contractor shall provide and install all iron hangers racks or racks with die cast cleats with all fixings, rag bolts or girder clamps or other specialist fixing as required. Where hangers or racks are to be fixed to wall sides, ceiling and other concrete structures, the Contractor shall be responsible for cutting away, fixing and grouting in rag bolts and making good. The hangers or racks shall be designed to leave at least 25mm clearance between the cables and the face to which it is fixed. Multiple hangers shall have two or more fixing holes. All cables shall be saddled at not more than 150mm centres. These shall be designed to keep provision of some spare capacity for future development. CABLES TAGS Cable tags shall be made out of 2 mm thick aluminum sheets, each tag 1-1/2 inch in dia with one hole of 2.5mm dia, 6mm below the periphery. Cable designations are to be punched with letter/number punches and the tags are to be tied inside the panels beyond the glanding as well as below the glands at cable entries. Trays tags are to be tied at all bends. On straight lengths, tags shall be provided at every 5 metres. TESTING OF CABLES Prior to installation, burying of cables, following tests shall be carried out. Insulation test between phases, phase & neutral, phase & earth for each length of cable. a. Before laying. b. After laying. c. After jointing. On completion of cable laying work, the following tests shall be conducted in the presence of the Engineer-In-Charge. a. Insulation Resistance Test (Sectional and overall). b. Continuity Resistance Test. c. Earth Test. All tests shall be carried out in accordance with relevant Indian Standard code of practice and Indian Electricity Rules. The Contractor shall provide necessary instruments, equipment’s and labour for conducting the above tests & shall bear all expenses of conducting such tests. PROTECTIVE EARTHING & LIGHTNING PROTECTION Scope The scope of work shall cover earthing stations, laying copper/GI earth strips and connecting the power panels, DBs and switch boards. Indian TNS system of earthing as shown on IS: 3043 shall be followed for the entire installation under the scope. All the non-current carrying metal parts of electrical installation shall be earthed properly. All metal conduits, trunking, cable sheaths, switchgear, distribution fuse boards, light fittings and all other parts made of metal shall be bonded together and connected by means of specified earthing conductors to an efficient earthing system. All earthing shall be in conformity with Indian Electricity Rules. The Earthing System shall totally comprise the following:-Earth Electrodes Earthing Leads Earth Conductors Residual current earth leakage circuit breakers where applicable per IE rules All three phase equipment shall have two separate and distinct body earths and single phase equipment shall have a single body earth. Standards The following standards and rules shall be applicable: 1) IS: 3043 - 1966 Code of Practice for earthing. 2) Indian Electricity Act and Rules All codes and standards mean the latest. Where not specified otherwise the installation shall generally follow the Indian Standard Code of Practice or the British Standard Code of Practice in the absence of Indian Standards. Scheme: Lightning Protection: To cater for lightning protection of the complete roof structure made of steel including the flood lighting system it has been proposed to provide for 1 no of 1200 mm long GI finial at top of each of the 22 light mast provided in the inner edge of the roof and one no of 1200 mm long GI finial at the top of the alternate cable supporting steel column on the outer edge of the roof structure. Thus there will be 44 finials, which will be interconnected through horizontal run of GI lightening conductors of 20 mm x 3 mm GI tape both radially from inside to outside and circumference on the outer edge. The complete steel structure should be connected to the lightening system through horizontal conductors. 22nos down conductors here been provided on the outer support column structure and connected to the earth, thus GI plate earth and testing joints. Body Earthing: Body earthing of the sports lighting system is provided thus 4nos GI plate earth at each of the sports lighting control room where the earthing is terminated in two nos. of GI earth Busbars. Two sets of GI tape earthing of two no 50 mm X 6 mm GI strip shall independently run from the sports lighting control up to the roof and distribution board placed there. From distribution boards to individual fixture earthing connection to be continued through 3 core power cables. Earthling Material Materials of which the protective system is composed shall be resistant to corrosion or be adequately protected against corrosion. The material shall be as specified in the schedule of quantities BOQ and shall comply with the following requirements: Galvanised Steel - Galvanized steel used shall be thoroughly protected against corrosion by hot dipped Zinc coating. The material coating shall withstand the test specified in IS 2309:1969. The strips to be used shall be in maximum lengths available as manufactured normally avoiding unnecessary joints. Earth Stations Plate Earthing Station The earthing station shall be as shown on the approved working drawing. The earth electrodes shall be 600 x 600 x 6 mm GI plate as required. The earth resistance shall be maintained with a suitable soil treatment and watering arrangement as per approved working shown on drawings or as directed at site. Excavated soft soil shall be thoroughly mixed with 6 percent by weight of common salt with 10 percent by weight of water and alternate layers of charcoal and filled in the earth pit. Independent earth shall have same specification subject to meeting the earthing value criterion for communication system. The resistance of each earth station should not exceed 1 ohms. The earth lead shall be connected to the earth plate through brass bolts as per approved working drawings. Number of Earth Stations In all cases the relevant provision of rule 33, 61 & 67 of the Indian Electricity Rules 1956 as amended shall be complied with. The number of stations shall be large enough to trip on over current largest MCCB in the system Metallic covers or supports of all medium or H.T. apparatus or conductors shall, in all cases be connected to not less than two separate and distinct earth electrodes. Location of Earth Electrode The following guidelines shall be followed for locating the earth electrodes An earth electrode shall not be situated less than 3 metres from any building. The excavations for electrode shall not affect the column footings or foundations of the buildings. Entrances, pavements and road ways shall not be used for locating the earth electrode. In such cases electrode may be further away from the building. The location of the earth electrode shall be such where the soil has reasonable chance of remaining moist, as far as possible. Method of Installing Watering Arrangement In the case of plate earth electrode, a watering pipe of 50mm dia. of medium class G.I. Pipe shall be provided and attached to the electrode. A funnel with mesh shall be provided at the top of this pipe for watering the earth. The watering funnel attachment shall be housed in masonry enclosure of not less than 1000 x 500 x 600 mm. A cast iron/M.S. frame with cover having identity mode “EARTH” and having locking arrangement shall be suitably embedded in the masonry enclosure. Earth leads and connections The strip earthing leads shall be connected to the Earth Electrode at one end and to the main equipment at the other end. The earthing lead shall connect to the earthing network in the installation. Earth lead shall be bare copper or galvanised steel as specified with sizes shown of on approved working drawings. Copper lead shall have a phosphor content of not over 0.15 present. Galvanized steel buried in ground shall be protected with bitumen and hessian wrap or polythene faced hessian and bitumen coating. At road crossings necessary hume pipes or UPVC Pipes shall be laid. Earth lead run on surface of wall or ceiling shall be fixed on saddles or wall so that the strip is at least 8mm away from the wall surface. All earth strips shall be jointed as follows: Copper : Copper riveting with 80mm fish plate and brazing Galvanized : Lap welding with 50mm minimum lap Steel: Overlay: not less than 50 mm in all cases Strip earthing leads shall be of copper/GI and as per specifications. The buried strip earthing lead shall be in trench not less than 0.5 m deep. If conditions necessitates use of more than one earthing lead, they shall be laid as widely distributed as possible, preferably in a single straight trench or in a number of trenches radiating from one point. In the case of plate earth electrode, the earthing lead shall be securely bolted to the plate with two bolts, nuts, check nuts and washers as required by IS 3043:1987. All materials used for connecting the earth lead with electrode shall be GI in case of GI Pipe and GI plate earth electrodes or tinned brass in case of Copper plate electrode. Connection of Earthing Conductors. Main earthing conductors shall be taken from the earth connections at the substation to the earth bar at the main switch boards in the TN-S configuration and the earth bar may also be directly earthed as in Indian TN-S. Sub-mains earthing conductors shall run from the earth bar at the main switch board to the sub distribution boards and to the final distribution boards. Loop earthing conductors shall run from the final distribution boards and shall be connected to any point on the main/sub-main earthing conductor, or its distribution board. Metal conduits, cable sheathing and armouring shall be earthed at the ends adjacent to switch boards at which they originate, or otherwise at the commencement of the run by an earth bonding conductor in effective electrical contact with cable sheathing, switches, accessories, lighting fitting etc. shall be effectively connected to the Loop Earthing Conductors. A metallic conduit shall not be considered as the only protective earth conductor. Point wiring for lights, fans, ceiling fans, exhaust fans, 5 A & 15A sockets and the like and sub-main wiring, shall all have an earth continuity conductor (ECC) width the same cross section and type of wires used, the minimum in this case being 2.5 sqmm copper. Prohibited Connections. Neutral conductor, sprinkler pipes, or pipes conveying gas, water, or inflammable liquid, structural steel work, metallic enclosures, metallic conduits and lighting protection system conductors shall not be used as a means of earthing an installation or even as a link in an earthing system. However, these are to be effectively earth booded. Resistance to Earth. No earth electrode shall have a greater ohmic resistance than 3 ohms as measured by an approved earth testing apparatus. In rocky soil the resistance may be up to 5 ohms. The electrical resistance measured between earth connection at the main switchboard and any other point on the completed installation shall be low enough to permit the passage of current necessary to operate fuses or circuit breakers. The number of earth stations should be increased to effectively achieve the tripping of the over current devices. The clean earth shall be provided for communication system as per the values prescribed by the relevant standards Equipment earthing All apparatus and equipment transmitting or utilising power shall be earthed as per drawings. The earth continuity conductor may be drawn inside the conduit in which case, it should be insulated. Metallic conduit shall not be accepted as an earth continuity conductor. A separate insulated/bare earth continuity conductor of size related to phase conductor shall be provided. Non-metallic conduit shall have an insulated earth continuity conductor of the same size as above. All metal junction and switch boxes shall have an inside earth stud to which the earth conductor shall be connected. The earth conductor shall be distinctly coloured (green) for easy identification. Armoured cables shall be earthed by 2 bonding earth connections to the armouring at both the ends and the size of connection being as above. In multiple cables entering a panel/DB, the cable joints shall be bonded together using a bonding wire selected on the basis of the largest size of cable in the group. In the case of unarmoured cable, an earth continuity conductor shall either be run outside along the cable. 3-Ph. power panels and distribution boards shall have 2 distinct earth connections of the size correlated to the incoming cable size. In case of 1-Ph. DB’s a single earth connection is adequate. Similarly for 3- Ph and 1-Ph. isolating switches there shall be 2 and 1 earth connections respectively, sizes being correlated to the incoming cable. 3-Ph. motors and other 3-Ph. apparatus shall have 2 distinct earth connections of size equal to incoming feeder size. For 1-Ph motor and 1-Ph apparatus, the single earth connections shall be provided of the above size. Artificial treatment of soil If the earth resistance is too high and the multiple electrode earthing does not give adequate low resistance to earth as specified in clause then the soil resistivity immediately surrounding the earth electrodes shall be reduced by adding sodium chloride, calcium chloride, sodium carbonate, salt and soft coke or charcoal in suitable proportions. Testing The following earth resistance values shall be measured with an approved earth megger and recorded. Each earthing station Earthing system as a whole Earth continuity GSM based Street Light Automation System: A) i). Central System Specification: The Streetlight Control System with GSM Interface should have a control station/ server with two way communication using GPRS/Ethernet communication. ii). Street light Automation system should have dimmer option maximum up to 50%. iii). Switching of up to 35 lamps per feeder pillar with load up to 63 Amp continuous load consisting of LED/Fluorescent Tube Lights, HPSV Lamps and Halogen Lamps ( Dimming is available only for HID and LED lamps) Iv). The system should have a provision for remote and local operation with a three way selector switch. Description GSM/GPRS streetlight management system specification: CPU Controller RS485 Communication module Current Interface with 3 Phase Coil & Current Leak Coils Set Battery Module for CPU Vandal Res Antenna Suitable MCCB with Trip contact Contactor Suitable to load set of 6 (5+1 No dedicated for Neutral ) MCB, 2A, 220V AC, 4P 63 A MCCB’S 4 P for outgoing circuit to Luminaires – 4 No’s Auto / Manual selector switch Switch of suitable rating IP55 Rated Enclosure (14 G, CRCA, (1050x600x250 mm) Switch modules Qty. 1 1 1 1 1 1 1 1 1 1 1 2 Set of 3 Toridal Auto Transformer CTs (Cast Resin, Class 0.5, 100/5) - 3 nos. Acrylic Sheet Shroud for bus bars Surge Protector /Lightning arrestor 3 Phase – 4 Wire CT operated KWH meter with RS 485 Timer Relay, delayed close SPNO 1 1 1 3 1 1 . 4 pole MCCB suitable for Positive Isolation with a Trip Contact 3 Pole Contactor with Aux Contact and 220 V AC Coil . Controller with CPU with built-in flash RAM for persistent storage having feature internal health monitoring & logging 2 analog inputs 1 digital input for photocell input Integrated GPRS for wireless communication with the server over internet. Ethernet TCP/IP Port (Ethernet TCP/IP port for wired internet connection ), USB Port for Firmware Upgrade, CPU serves as a WAN communications and data concentrator module Two-way communication with the central server takes place via GPRS, SMS or Ethernet Inbuilt Astro Timer Switch. . Energy Meter Aux relay for interposing the command to contactor from Controller Class 1.0 Cast resin CTs for connecting the Energy meter 4P MCB for control supply The earth conductor GI of size 25 X 3 mm Panel Enclosure The panel shall be wall mounting cubicle type with four supports to accommodate 8 mm Bolts Sheet steel thickness for complete enclosure to be 2 mm Cable entry will be from bottom with a gland plate made of 3 mm sheet steel 25 x 10 mm Aluminum bus bars for each phase and neutral Bus bars shall be mounted on 130 mm long insulators Control wiring shall be 1.5 sq. mm PVC insulated copper cable CT wiring shall be 4 sq. mm PVC insulated copper cable All control cables shall be ferruled at both ends as per drawing Engraved Legend plates shall be provided for equipment designation ‘Danger’ plate shall be provided on the LT compartment Panel shall be painted in Siemens Grey Paint, shade no. RAL7032 A transparent Acrylic Sheet Shroud shall be provided in the LT compartment housing MCCB & Contactor. Two earthings to be provided to the GSM switch. The earth conductor of size 25 X 3 mm will be tapped from the nearest earth mat available. (D) i) ii) iv) v) MCB Should be ISI mark as per IS 8828:96 and IEC 898 with short circuit breaking capacity as 10 kA. Should be classified as per application. B Curve in this case iii) Should be suitable for Isolation Should have positive contact indication Let through energy should be of class 3 vi) vii) viii) ix) x) xii) Should have Low energy watt loss Should offer Protection degree of IP 20 Should have grooved tunnel terminal Should have captive screws Should have an endurance of 20, 000 Number of operations when energized Resistance to electrical shocks (or dielectric withstand) should be 2.5 KV Should have line load reversibility (E) MCCB a) i) General The circuit breakers shall comply with IEC60947.2 & IS 13947 part 2. ii) The breaking capacity performance certificates shall be available for category A to the above mentioned standards. The test shall be carried out under the breaking performance during the ultimate breaking capacity rating = 100% Icu. Certificate for all the sequences should be available (sequence 1 mandatory). xi) iii) All circuit breakers shall have a rated operational voltage of 600V AC (50/60Hz). iv) The rated insulation voltage shall be 600V and 660V at 50/60 Hz. for low breaking capacity and high breaking capacity MCCBs respectively. There should be different levels of breaking capacities starting from 10kA upto 50kAfor flexibility in selection. v) vi) viii) The breaker shall be maintenance free and fully tropicalized. vii) It all have 4 poles (switched neutral). Production site organization shall be certified to comply with ISO 9001 standard. b) Construction i) Operating mechanism shall be of the quick make quick break type, with the speed of operation independent of the operator, and mechanically trip free from the operating handle so as to prevent the contacts from being held closed against short-circuit and overload conditions. The operating mechanism shall be constructed to operate all poles in a multipole breaker simultaneously during opening, closing and tripped conditions. It shall not require any external power supply to operate the tripping mechanism. The breakers shall be operated by a toggle which shall clearly indicate the three fundamental positions ON, OFF and TRIPPED. If required, the breaker will be equipped with rotary handles. The breaking and extinction of the electrical arc shall be achieved by means of non- welding contacts and an arc chute surrounding these contacts. ii) iii) iv) v) c) Characteristics i) The protection unit shall have Short circuit setting fixed at 10In +/- 20% as specified in IEC 947 and IS13947 part2. d) Operation i) ii) The electrical and mechanical endurance of the moulded-case circuit breakers should be as defined by IEC 947-2 standard. The moulded-case circuit breakers shall be equipped with a "push to trip" button in front to test operation and the opening of the poles. e) Options i) Alarm contacts should be available for remote indication of circuit breaker trip condition. f)Installation i) The circuit breaker should provide the flexibility of terminating line and load from any direction. Manufacturers should test the circuit breaker for this condition and requisite test certificate should be available. Phase barrier should be provided as a standard feature. F) Contactor i) ii) iii) iv) v) vi) Should be conforming to IEC 60947-4-1, IS 13947 ii) No. of Poles – 3 Insulation Voltage – 690 V Impulse withstand voltage (Uimp) – 8 KV Should pick-up @ 85 – 110% of control voltage viii) Should drop @ 3060% of control voltage Operating time – 15 to 35 ms Suitable for switching HPSV Lamps (Very high in-rush considering the Capacitance in HPSV) vii) The contactor should be designed and tested for at least 5, 000, 000 mechanical operations & 1, 000,000 electrical operations viii) Should be possible to inspect the contact wear and easy contact replacement Should have Mechanical ON/OFF indicator Should have provision for side mounted aux. Contacts ix) H. Controller The CPU Controller shall be equipped with a 32 Bit processor capable of running DSP, Microcontroller and Java applications, running on open-source operating system i. The CPU module shall serve as a WAN communications and data concentrator module. It shall be capable of two-way communication with the central server takes place via GPRS,SMS ,Ethernet ii. ARM9 - 200 MIPS industrial controller with Linux® kernel. iii.One USB 2.0 (12 MB/s) host port for Diagnostic purpose i. Low voltage measurement inputs analog input 1 and analog input 2 (positive voltage with respect to GND). ii) 1 Digital Potential Free input.. iii) RJ-45 connector, 100 Mbps/10 Mbps, half & full duplex, functional insulated from the secondary connections iv) SMA connector for external GSM antenna. GSM900, GSM1800, GSM1900 v) 2x5 internally connected signals that are used for the Communication Bus. vi) Use shielded twisted pair (2x2) cable. The AmpLight CPU can be connected to any client module in the AmpLight System, e.g. AmpLight RS485, AmpLight Switch. Double connections on the Communication Bus makes daisy-chaining of the signals easy. vii) Input voltage 205 V – 250 V AC (3P + N) Nominal voltage: 230 V AC, Nominal frequency: 50/60 Hz viii)Maximum system < 18 W, CPU and 830 mA on power consumption A-Bus (= 10 W) and 250 mA on USB ix) Shall be able to control up to 1 Km or 35 Lamps. x) Tri band GSM900/EGSM900, GSM1800, 1900 MHz. Compliant to GSM Phase 2/2+ xi) GPRS data downlink transfer: max 21.4 kbps Coding scheme: CS-1, CS-2, CS-3 and CS-4 PPP: Two protocols PAP (Password Authentication Protocol) and CHAP (Challenge Handshake Authentication Protocol) Support of Packet Switched Broadcast Control Channel (PBCCH) xii) SMS MT, MO, CB, Text and PDU SMS storage: SIM card plus. Transmission of SMS can alternatively be user defined xiii) Relay outputs capable of handling over 1 A of power. xiv) TUV certified product line confirming to the following EMC standards a) 2006/95/EC, b) Low Voltage Directive (LVD) 2004/108/EC, c) EMC Directive 1999/5/EC, d) R&TTE Directive 2002/95/EC, e) RoHS Directive 2006/121/EC, f) REACH directive UL 916 g) C22.2 No.205-M1983 h) FCC part 15 B & RSS132, issue1, RSS133, issue3 PTCRB xv) Provision for USB Plug in EEPROM for programming xvi) Storage Temperature of -40 deg. C to + 80 degree C and operating temperature from -20 deg. C to + 60 degree CGM(T) HGCL xvii Shall be able to Monitor the following: 1) Battery shutdown 2) Communication class availability 3) Over/under mains voltage (on every phase) 4) Mains power failure 5) Phase fault (only in multi phase mains networks) 6) Mains rated input for cabinet door detection Photocell input for streetlight control Monitoring GUI SCADA” i) Shall be a reputed make with special functions required for the project ii) Should have unlimited tags (as the expected no. of tags are expected to touch 1 lac nos. or more Should have unlimited number of control cabinets. Should support standard databases . iii) Should be OPC compliant iv) Should have all the possibilities of protocols for future up gradation viz., IEC 60870-5-101/104, DNP3.0 etc It should be possible to create reports, both as html pages or as Excel files. Should have feature of creating Web Clients for future viewing Should support API for third-party software integrations DATA Transmission System: The following options are to be considered: 1. By GPRS/Ethernet connectivity – Energy Meter reading at predefined time periodically and same logged by the central server. 2. By direct polling by Central Station – the Central SCADA/ server will call up each unit periodically and fetch details of metering from each location and update its records with date and time. In this case all controllers will have DATA enabled SIM from GSM service provider. 3. By continuous Connection with the field control units – this option enables the central station to be always in touch with all field controllers and can keep on logging at very frequent intervals. In this case all controllers will have GSM modems with GPRS/EDGE communication capability provided by the GSM service provider. 14.4 Location of CPU controller : The Location of CPU controller have been categorized into the following three categories: i) a) Category I: The Location of CPU Controller in the outdoor kiosks would be installed within the Feeder Pillar Control Panel/DB i) This category is assumed / estimated to have a population of 60% of the installations ii) The CPU controller would be installed on wall by using Anchor Fasteners. b) Category II: Location of CPU controller in the outdoor kiosks i) This category is assumed / estimated to have a population of 30-35% of the installations ii) The CPU controller would be installed within the existing out door kiosk on the existing PCC poles. iii) It is envisaged that at some locations it may not be possible to install the CPU controller within the existing fenced outdoor kiosk, in which case the CPU controller would be installed near to the kiosk or a separate MS Angle frame fabricated from 50 X 50 X 6 mm angle and grouted in ground and the entire area would be suitably fenced. c) Category III: Location of GSM switch in congested areas and Flood light Masts i) This category is assumed / estimated to have a population of 10-15% of theinstallations ii) The flood light masts may be connected to the street light circuit. iii) The GSM switch would be installed in the indoor substations d) High Mast: Falling in proximity of any of the above 3 categories i) The flood-light masts may be connected to the GSM Switches on existing circuits falling in any of the above categories ii) Necessary modification need to be carried out to by-pass the existing highmast control panel Supply and cabling: 1.The LV supply to the GSM switch will have Incoming cable size of 4 Core 50 sqmm( for 100 amp switch) and 4core 95 sqmm cable (for 200 amp switch) XLPE cable and subsequent section of the street light mains shall be done through 4 Core 25 sqmm XLPE cable. 2. The connections from Junction/fuse box to the Luminaries shall be done with 2.5 Sqmmmultistrand copper conductors. Guard for Overvoltage Protection: This module shall provide Overvoltage protection specifically for the CPU, capable of withstanding surge pulses up to ± 6 kV and burst pulses up to ± 4 kV. The module shall consist of four independent protected mains rated channels which each have a built-in thermal protection, Surge protection level ± 6 kV according to EN61000-4-5, Burst protection level ± 4 kV according to EN61000-4-4, Three mains rated phase (line) inputs: L1, L2 and L3 and shall be DIN Rail Mounted. DIN Rail Battery: The Battery module shall supply other modules with emergency power in the event of power failure. All modules in the system shall incorporate RS485 based communication technology used for both power supply and for direct communication between the modules. This Battery module shall be installed together with CPU module, and shall be recharged by the CPU.If the main power fails, Battery shall instantaneously take over the power supply, enabling the CPU module to store data and send a main power failure alarm to the central server via GPRS/SMS before it shuts down safely. Additional System Requirements: The system shall generate power failure alarm or Individual Phase failure alarm The system should able detect the panel door open condition and should notify the user The system shall support to integrate both analog and digital type of Photocell The system shall allow configuring priority levels for commands (Eg. Fixed programs , Manuel switching, twilight switching ) The system shall provide API for integrating with third party applications like SCADA or ERP applications for basic monitoring and control. The system shall provide facility for inventory management for luminaires Web based management of the Lighting system It shall be possible to create a node hierarchy to reflect the geographical area that is monitored and controlled by the system. All actions performed in the GUI are related to selected node and its child nodes. It shall be possible to post messages on the GUI for the other users of the web based management system. The GUI shall have a search box to search for nodes, boxes, modules, meters and programs The GUI shall give an overview of the communication status of all the boxes in the selected node tree. The GUI shall indicate the photocell history. It shall be possible in the GUI to manually operate the light for the selected node tree to switch the light to ON, OFF The GUI shall indicate the light status for all the boxes of the selected node tree. It shall be possible to set an operational mode for the boxes. The operational modes shall be “operational”, “Installation”, “maintenance w/ alarm”, or “maintenance w/o alarm” It shall be possible to generate an alarm overview, filtered on alarm severity, alarm type, alarm state, alarm period. Reporting It shall be possible to create reports, both as html pages or as Excel files. It shall be possible generate an alarm report, filtered on alarm severity, alarm type, alarm state, alarm period, no. of parent nodes. It shall be possible to generate a report on the meter readings. It shall be possible to generate a burn time report. It shall be possible to create an action report, based on modules, light commands, report, alarm, photocell or light status. It shall be possible to create a lamp surveillance report for critical lamp failure, preventive lamp replacement or failures before burning hours. It shall be possible to generate reports from Historical data available in Lighting control system server for following: o Switching operations o Alarms/ Warning generated o Run Time of Circuits Programming It shall be possible to create programs based on a fixed time table. In the fixed time table program, it shall be possible to define ON and OFF commands. It shall be possible to activate the fixed time table on a daily, weekly or monthly basis It shall be possible to activate the fixed time table based on a time period; from day/month to day/month. I It shall be possible to create programs based on a twilight table. It shall be possible to generate a twilight table based on a geographic location. It shall be possible to combine a twilight table with a primary and secondary photocell. In the twilight table program, it shall be possible to define a Twilight table sunrise offset In the twilight table program , it shall be possible to define a Twilight table sunset offset In the twilight table program, it shall be possible to include ON and OFF commands at fixed times between sunset and sunrise. In the twilight table program, it shall be possible to define a photocell event delay for the primary and for the secondary photocell. Software upgrade It shall be possible to upgrade the software locally on the CPU using a USB stick. It shall be possible to upgrade the software remotely through the webpage application. Customers, permission groups and users It shall be possible to define “Customers” to limit access for users within these “Customers” to only a part of the node tree. It shall be possible to define permission groups to define different levels of user access. It shall be possible to design user accounts within customers, and assign a permission group and a password to each user. It shall be possible to subscribe users to alarms via SMS or email. It shall be possible for a user to control ON, OFF Control Room Application The streetlight automation system shall feature a map application that gives an overview of all boxes on top of a street map or a satellite image. It shall be possible to visualize the light status of the boxes or the alarm status of the boxes. It shall be possible to see the geo-location data of a selected box. It shall be possible to see the serial number of a selected box. It shall be possible to see the node of a selected box. It shall be possible to see the name of a selected box. It shall be possible to see the communication status of a selected box. It shall be possible to see the alarm status of a selected box. It shall be possible to see the phone number of a selected box. It shall be possible to see the communication status of the carriers of a selected box. It shall be possible to see the light status of a selected box. It shall be possible to upload and view .jpg pictures of the box. It shall be possible to set the Configurable communication class with Control station / server:- Ethernet, GPRS or SMS The following faults shall be displayed in alarms o Under/over voltage detection o Main breaker error o Contactor fault o Circuit breaker off o Circuit phase errors (fuse, breaker, etc.) o Main power failure o Leakage to ground o Manual switch activated o Phase current out of range o Control cabinet door open o Flashing bulbs o Bulb failures o Low Power Factor Communication failure with server External Electrification works: The external electrification works have to be carried out as per the standards in consultation with TSSPDCL and Chief Electrical Inspector to Government of Telangana, duly obtaining approval to the drawings and to have liaisoning such as processing applications and obtaining estimate approvals including intimations and executing them under exemption process and also during enegisation process. The cost of liaisoning shall be considered as being included in the cost of items of work in the Bill of Quantities. Tests on Completion Tests on Completion procedure shall be applied to the equipment, switch gear comprising illumination including both external and internal electrification and power cables after they are installed at the specified location, and adjusted and tested by the Contractor. Test on completion shall be conducted at two levels; test on completion for a portion of works, and test on completion for the Works. The test on completion for a portion of works shall be conducted for a group of equipment at a site that functions as a subsystem and achieves part of the system functions. The unit of test shall be as specified hereunder. The test on completion for the Works shall be conducted for the whole of the illumination system including the supporting switch gear. Overall system functions as illumination system shall be tested. The Contractor shall keep a clear record of all tests conducted. The record shall include time, place, equipment, procedure, functions, persons attending, and faults or problems encountered. The test results, even if they are not satisfactory, shall be documented and submitted to the Employer’s Representative for review. If permanent electric supply is available the Employer will provide electricity free of charge to the Contractor for the purpose of conducting test on completion if permanent electrical supply is available. Otherwise, the Contractor shall arrange electricity, water and gas necessary for the test on completion. The Contractor shall prepare or arrange the test apparatus and equipment, temporary connection, testing software, test data, test vehicle, tools and other items necessary for conducting test. The cost of such items shall be included in the cost of test in the Pricing Document and no separate payment shall be made. Plant and Equipment In all cases where traffic is permitted to use the whole or a portion of the existing road before the work is completed, all plant items and similar obstructions shall be removed from the road at night, if at all possible. Otherwise, they shall be delineated at night if they stay within 2 meters of the edge of the roadway by two red lights suspended vertically from the point of obstruction nearest to the roadway. The lights may be omitted in cases where there is permanent obstruction, such as trees less than 2 meters from the edge of roadway and the plant or equipment are not closer to the road than the permanent obstruction. During the day, a red flag shall project beyond the extremity of all plant items (other than vehicles) adjacent to the traffic lane Vehicles Vehicles that are used to carry out operations on the roadway and that are required to travel slowly or to stop frequently shall be made as conspicuous as possible. This shall be achieved by painting them in a distinctive colour or painting the rear portion with diagonal stripes of a contrasting colour or providing flashing lights on the top of the vehicle. They shall also have a plate on the rear side with the words "Slow Moving" Safety Plan The Contractor shall prepare and submit a safety plan before the start of installation work at site for approval of the Employer’s Representative. The safety plan shall describe the precautions and measures to be followed by all members of the Contractor including the staff of subcontractors to prevent accident during the work. It shall also contain the emergency response measures in case of accident. The Tenderer shall describe safety plan that the Tenderer intends to adopt for the works at site in his Technical Proposal. Operator's Manual The Contractor shall prepare and submit operator’s manual to be used by the operators belonging to traffic monitoring and control division during their daily operation. The manual shall explain the procedure to log-on and log-off for duty operator console and other procedures necessary for daily operation. In addition, the manual shall describe the operating procedure of the Roadside Equipment. The description shall be plain and concise in a step-by-step manner using illustrations and photos as much as possible. The details of the internal mechanism are not required in the manual. The manual shall also describe the action to be taken by operator in exceptional cases. The description shall be limited to the operation of the Equipment and system operation and the actions related to those events occurring on the road are not required. Likewise, the manual shall describe the actions to be taken when any of the components comprising illumination becomes defective or malfunctions. Detail manual and outline manual shall be provided Workmanship All equipment and components shall be new and shall be designed and manufactured in the soundest manner, using materials most suited to the particular services. All materials shall comply with the latest relevant authorized standards for testing materials unless otherwise specified or permitted by the Employer’s Representative. For the design of all equipment, it shall be considered to enable to make ease of their maintenance work. All workmanship shall be of the highest class throughout to ensure smooth and vibration free operation under all possible operating conditions, and the design, dimensions and materials of all parts shall be such that the stresses to which they may be subjected shall not render them liable to distortion, undue wear, or damage under the most severe conditions encountered in service. All parts shall conform to the dimensions shown on the Employer’s Requirements – Drawings and shall be built in accordance with approved drawings. All joints, datum surfaces, and mating components shall be machined and all castings shall be spot faced for nuts. All machined finishes shall be shown on the approved drawings. All screws, bolts, studs & nuts and threads for pipe shall conform to the latest standards of the International Organization for Standardization covering these components and shall either all conform to the standards for metric sizes. Nameplate All equipment supplied under the Contract shall have a nameplate. The nameplate shall indicate as a minimum, manufacturer’s name, model, type or make, serial number, manufactured month and year. In addition, other information such as input voltage, current, frequency, and complying standards may be described. Information on the nameplate shall be printed or inscribed in indelible manner. The nameplate shall be firmly attached to the cabinet at the suitable position by screw, rivet or adhesive and shall not be easily removed. Wind All outdoor equipment and their support, individually and fully assembled and installed as a whole, shall withstand an instantaneous wind velocity of at least 45 m/sec Cable Identification Cable and wire ends shall be prepared using only approved means which avoid damage to conductors and shall be clearly and indelibly marked in accordance with relevant diagrams for wiring up and circuit checking. Each cable shall have an indelible label securely fixed near each end, giving its reference number in the cable ‘As-Built’ schedules. Throughout the installation the arrangement of wire and terminal identities shall be consistently followed and shall be as agreed with the Employer’s Representative. Any phase wires in power circuits used for distribution other than 240/415V shall have the phase voltage clearly marked at each end of the conductor. SECTION -11 List of approved makes of Electrical materials to be used for the work providing LED Street Lighting ON ORR Hyderabad. S.No. Materials Make 1 Octagonal Poles Bajaj / Valmont / TRANSRAIL. 2 High Mast poles Bajaj / Valmont / TRANSRAIL. 3 LED street Lights a).LUMINAIRE MAKE : Phillips / Osram/GE / Crompton / VIN / Bajaj/Schreder . b) LED MAKE : PHILIPS LUMILEDS / CREE / NICHIA / OSRAM / SAMSUNG. 4 MCBS/Isolators/MCCBs L&T / Schreder / Siemens. 5 MCB Distribution boards L&T / Schreder / Siemens. 6 LT UG aluminum cables Torrent / Universal / CCI / Unicab. 7 HT XLPE cables Torrent / Universal / CCI / Unicab 8 Distribution Transformers TSSPDCL approved make 9 Automatic Street Light Schreder / L & T/ Siemens/ ABB/CROMPTON/Philips/Bajaj Control System 10 Connectors Elmex/ Connect well/ Raychem/ Andrew Yule 11 PVC FRLS / HFFR insulated flexible Copper cable Finolex / RR kabel 12 PVC conduit pipes Sudhakar / Modi / Atul.with ISI marked 13 16 Gauge MS conduit pipe NAI / Bharath / GB. with ISI marked 14 A.B. Switch/H.G. Fuse Set/Lightning arrestor/Insulators TSSPDCL approved make 15 GI pipes TATA/JINDAL with ISI marked 16 L.T. 3phase Digital multifunction energy meter with 3 lines LCD display for measuring all the parameters (voltage / Current / Power / frequency / power factor / kw / kwh / KVAR/ KVARH/) CONZERVE / ELMEASURE / LEGRAND / MECO / HPL MAKE. 17 HT termination kits Reychem/M seal/Denson/Multy 18 HDPE pipes Dura Line (Dura guard) or its equivalent make Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III Design, Supply, Installation, Testing, Commissioning, of illumination to the Outer Ring Road, Hyderabad for the Main Carriage Way/ Inter changes/ Junctions/Service Roads and Under Pass areas from Gachibowli to Shamshabad in the state of Telangana, India being taken up with loan assistance of Japan International Cooperation Agency under Phase-2 program and Operation & Maintenance of illumination with connected switch gear for a period of Five years from date of Operational Acceptance Certificate being taken up with HGCL Funds (Tender Notice No. 4/CGM(T)/HGCL/DGM-I/Street lighting/2014-15) (Special conditions for O&M) SECTION-12 Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III SECTION-12 ESSENTIAL CONDITIONS FOR O&M STREET LIGHTING WORKS:- 1. Operation & maintenance shall be for period of 5 years from the date of successful commissioning of the project is dammed to be included in the prices quoted by the bidder. No extra amount shall be payable to the contractor on account of O&M. 2. The contractor shall be paid for O&M on quarterly basis shown under special conditions. 3. The O&M shall necessarily mean managing all kind of day to day operations (switching on, change over and switching off) and maintenance of entire street lighting system including supply of all kind of materials, painting etc. Contractor shall arrange qualified man power, tools & tackles, equipment’s, spares, statutory clearances etc. without any extra cost implications to the client. O&M staff shall work as per the instructions of the Engineer. 4. The contractor shall depute qualified Electrical engineer cum supervisor having minimum 5 years of relevant experience Wireman, helpers in adequate numbers to meet the requirement of O&M. The contractor shall engage only license holder electricians and wireman. Necessary safety equipment shall be provided by the contractor to his employees/Staff. 5. The Contractor shall have to give the list of names of the personnel to be engaged for the work with their pass port size photographs, certificates & qualifications proof etc. The list will have to be updated once in every six months. 6. The Contractor shall fulfil all provision under various acts like contract labour act, minimum wages act, workman compensation act, Indian Electricity act etc. as applicable to such work. Any financial implication arising due to breach of any act shall be fully borne by the contractor. The contractor shall also be liable to pay service tax or any other taxes to Govt. for carrying out the O&M work. 7. The Contractor shall deploy adequate numbers of mobile ladders/cranes of suitable heights for O&M purpose. 8. The lighting fixtures which are out of order shall have to be repaired within 48 hours. Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III However for critical locations as defined by the Engineer, corrective actions need to be taken up with in 24hours. In case of any electrical shock/ emergency/theft, The Contractor shall attend the same immediately and inform to the Engineer. The Contractor shall also lodge police compliant, if required. The Contractor shall be fully responsible for any damage and /or loss of life, accident occurring during the work. 9. All required maintenance spares such as time switch, contactors, wires, cables, junction box, cable jointing kits, hard ware, all kinds of T&P etc. shall be in the scope of supply of the contractor. HGCL shall not provide any materials at all. The Contractor shall be required to maintain good aesthetics of the equipment’s like poles, brackets, SLFP etc. 10. The Contractor shall provide office accommodation with communication to his engineers/Supervisors. The Maintenance staff of the contractor shall be available round the clock on all days including holidays/Sundays. 11. After successful completion of 5 years of O&M period, The Contractor needs to hand over the complete installation to the Engineer in good working condition. At the time of handing over, The Contractor needs to submit complete item wise inventory as given in the priced BOM format at the time of Bid submission. 12. To watch the day to day functioning of LED road way lighting over the ORR and to maintain day to day power consumption record. 13. To attend the day to day complaints as per the routine maintenance schedule and to see that there should not be any dark spot at any place over the ORR. 14. To attend day to watch over the feeder pillar panels and to see that there should not be any loose connections and any problem noticed with MCBs/MCCBs/relays should be attended immediately. 15. To attend the day to day inspection of pole junction boxes and to see that there should not be any loose connections and any problem noticed with MCBs/Run of mains/connectors should be attended immediately. Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III 16. To keep patrol vehicle along with O&M staff as per the specifications of the agreement 17. on shift duties so as keep ORR lighting in to work in condition at all times. To pour the water in to the earth pits at the transformer yards, feeder pillar panels, pole junction boxes including D.P. Structure and to see that earth resistance is maintained as per the IE rules and there should not be any earth fault at any place. 18. To coordinate with civil O&M agency and Toll agency and to see that there should not be any power supply interruptions and to attend the complaints noticed by the both civil O&M agency and Toll agency immediately. 19. To coordinate with TSSPDCL and to see that there should not be any power supply interruptions and to attend the complaints noticed by the TSSPDCL immediately.. 20. To coordinate with TSCEIG authorities during their inspections and to see that there all observations have to be attended as per IE rules immediately and necessary compliance report have to be furnished through Licensed Electrical Contractor under 21. intimation to the both The Engineer and HGCL. To attend the replacement of worn out HG fuses at the Transformer yards during the interruption of power supply shown under service levels. 22. To conduct periodical check over the underground cable over the both main carriage way and service roads and to test IR values and to see that there should not be any cable failures and cable end terminations. 23. To maintain record over the time to time glowing period of the LED lighting through sub subsisting GSM based automation system and to intimate the same to the Engineer and HGCL. 24. To watch the performance of the GSM based automation system in consultation with manufacturers and to attend the rectifications time to time and to see that there should not be any break down of GSM based automation system at any time. 25. To take all precautionary measures during the natural calamities such as heavy rains etc and there should not be any interruption of illumination over the both main carriage way and service roads. 26. To ensure that only genuine and good quality with ISI marked of materials are used during the course of replacement of worn out parts and break downs. 27. To keep the crane with skilled operator and to see that there should not be any traffic hindrance during the break downs and necessary road safety precautions have to be followed in consultation with civil O&M agency and Toll agency. 28. To keep sufficient stock of required electrical consumables at the site stores so to avoid all possible delays in attending the complaints. 29. To coordinate with both civil police and traffic police and to see that there should not be any power supply interruptions and to attend the complaints noticed by the both civil police and traffic police immediately. 30. To arrange necessary temporary illumination arrangements with generator with required staff during unavoidable circumstances with in no time. 31. To coordinate with both Urban Forestry and Horticulture staff and to see that there should not be any power supply interruptions to the pump sets & water supply and to attend the complaints noticed by the both Urban Forestry and Horticulture staff immediately. 32. To check the poles periodically and to see that there should not be any corrosion is noticed over the poles and necessary anti corrosion process have to be taken up immediately. 33. To check the Feeder pillar panels periodically and to see that there should not be any corrosion is noticed over the poles and necessary anti corrosion process have to be taken up immediately. 34. To check over the High Mast poles periodically and to see that there should not be any defect is noticed over the poles and necessary rectifications have to be taken up immediately. 35. To check over the Metal halide lighting regularly and to see that there should not be any illumination interruption is noticed at any time and necessary rectifications/replacements have to be taken up with in no time. 36. To arrange periodical inspection of transformers and to attend oil filtration top up the oil level and replacement of silica gel breather and to see that required IR values are maintained. 37. It is the complete responsibility of the agency to keep the stand by transformers during the exigencies and to maintain the uninterrupted power supply. 38. To furnish the day to day record, periodical checks record to the Engineer and HGCL during their inspections and to obtain their counter signatures in token of verification. No payment can be considered in the absence of above record. 39. It is the complete responsibility of the agency to interact with local authorities and pay necessary charges to wards ESI and PF contributions regularly and No payment can be considered in the absence of above record. Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III Design, Supply, Installation, Testing, Commissioning, of illumination to the Outer Ring Road, Hyderabad for the Main Carriage Way/ Inter changes/ Junctions/Service Roads and Under Pass areas from Gachibowli to Shamshabad in the state of Telangana, India being taken up with loan assistance of Japan International Cooperation Agency under Phase-2 program and Operation & Maintenance of illumination with connected switch gear for a period of Five years from date of Operational Acceptance Certificate being taken up with HGCL Funds (Tender Notice No. 4/CGM(T)/HGCL/DGM-I/Street lighting/2014-15) SECTION-13 (Special conditions for Payment) 239 Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III SECTION-13 1) The quoted rate is for finished item of work shall be inclusive of all taxes, transportation, labour, etc. Payment in respect of Supply, Installation, Testing & Commissioning (Part-A): 2) The payment during execution of the works will be considered for finished item of work as against each item of work as under. (a) If the quoted rate for O&M (Part-B) is more than 5% of the Contract Value (Part-A + Part-B), the payment will be made at quoted rates. (b) If the quoted rate for O&M (Part-B) is less than 5% of the Contract Value (Part-A + Part-B), the payment will be restricted to 95% of the quoted rates. (c) The withheld amount as per condition (b) above will be released after expiry of Defects Liability Period. Payment in respect of O&M Works (Part-B): 3) The payment during O&M will be considered as under after successful completion of each quarter subject to fulfillment of service level requirements. In case of deficiencies in service levels, the penalties will be levied as stipulated and the balance amount will be considered for payment. Period During first 2 (Two) years rd During 3 Year th During 4 Year th During 5 Year Payment 3% of O&M Contract Price (Part-B) per each quarter 5% of O&M Contract Price (Part-B) per each quarter 6% of O&M Contract Price (Part-B) per each quarter 8% of O&M Contract Price (Part-B) per each quarter Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III Design, Supply, Installation, Testing, Commissioning, of illumination to the Outer Ring Road, Hyderabad for the Main Carriage Way/ Inter changes/ Junctions/Service Roads and Under Pass areas from Gachibowli to Shamshabad in the state of Telangana, India being taken up with loan assistance of Japan International Cooperation Agency under Phase-2 program and Operation & Maintenance of illumination with connected switch gear for a period of Five years from date of Operational Acceptance Certificate being taken up with HGCL Funds (Tender Notice No. 4/CGM(T)/HGCL/DGM-I/Street lighting/2014-15) SECTION-14 Service levels Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III SECTION-14 Service Level Requirements Service level means the operation and maintenance services delivery criteria established for the services specified in service level table. The purpose of Service Levels specified in the Service Levels Tables is to clearly define the levels of service which shall be provided by the Contractor to HGCL during O&M period i.e. Five Years from the date of Operational Acceptance Certificate. The service level parameters mentioned in the service level table shall be measured on a quarterly basis as per the individual service level parameter requirements, through appropriate service level measurement tool. Measurement of service levels for illumination systems shall be automatic using reports from appropriate management tool like GPRS. Measurement of Service Level parameters will be carried out on cumulative basis in a quarter. Non meeting service levels would attract a penalty for every hour of downtime beyond the downtime permissible. The Contractor needs to ensure that the service levels as per service level table is being compiled. Contractor needs to submit service level report along with the quarterly payment invoice. in the event the service level is not achieved, service level penalty as applicable on the quarterly payment would be charged as per Service Level Table. If the level of required performance of the system/services is degraded significantly at any time during the Operation and Maintenance Period, the Contractor shall rectify the situation to the satisfaction of the Employer, failing which the Employer may exercise his right under the Conditions of Contract. The Contractor and HGCL shall regularly review the performance of the services being provided by the Contractor and the effectiveness of these Service Levels. The Contractor is responsible for development and implementation of appropriate management tools like GPRS which shall be basis for all project reviews. The Tender shall report down time that is not attributable to the Contractor, such as public communication failure or thunderbolt to The Employer within three (3) days after the failure. The Employer shall assess the downtime and permit the Tender to consider downtime for the calculation of service level. Service Levels Review Process Either Employer or Contractor may raise an issue by documenting the business or technical problem, which presents a reasonably objective summary of both points of view and identifies specific points of disagreement with possible solutions. o A meeting or conference call will be conducted to resolve the issue in a timely manner. The documented issues will be distributed to the participants at least 24 hours prior to the discussion if the issue is not an emergency requiring immediate attention. Hyderabad Growth Corridor Limited ORR/JICA2/Pkg 1/Vol III o The Employer and the Contractor shall develop an interim solution, if required, and subsequently the permanent solution for the problem at hand. The Contractor will then communicate the resolution to all interested parties. o In case the issue is still unresolved, the arbitration procedures described in the Conditions of Contract Part II Conditions of Particular Applications will be applicable. Service Level Penalties The total deduction should not exceed 20% of the Quarterly Billing Value (QBV). o Three consecutive quarterly deductions of more than 20% of the applicable fee on account of any reasons will be deemed to be an event of default and termination. o The certifications would be obtained by the Contractor latest by end of Third Quarter of the Operations phase failing which the subsequent QBVs will deferred till the certifications is obtained. o In the event of any of the above happening, it shall be governed by terms & conditions defined in this Tender Document Operation and Maintenance Intervention Service Levels Criteria / Extent (% of Sl. No. Defects 1 External Electrification sub section length) Time Allowe d to Penalty to be levied per incident if Treatment / Action Type of Maintenanc e Comple not attended te the in scheduled work time Replacement with new one Urgent Rs 1000/6 Hours per hour/location Rs 1000/6 Hours per hour Rs 1000/6 Hours per hour/location 1.1 HG fuse burnt out Any 1.2 Cable burnt out Any Replacement with new one Urgent 1.3 A.B. Switch not working Any Immediate repairs Urgent 1.4 HT/LT meter not working Any To inform TSSPDCL for rectification Routine Any To inform TSSPDCL and manufacturer of Transformer for permanent restoration and to provide hired transformer for temporary restoration Urgent 3 Days Rs 5000/ Per Day/location Any Permanent restoration and Replacing the damaged poles Urgent 3 Days Rs 5000/ per Day/location Any Permanent restoration and Replacing the damaged poles Immediate / Urgent 3 days Rs 5000/ per Day/location 1.5 2. 2.1 3 3.1 4 Failure of Transformer High Mast poles & Octagonal poles Damage of Octagonal poles/High mast poles Feeder pillar panels Damaged of Feeder pillar panels MCCBs/MCBs 4.1 Damage of Any MCCBs/MCBs 5. UG cables 5.1 Cable failure Immediate Urgent 6 Hours Rs 1000/- repairs/Replacement Any Replacement with new per day Urgent 6 Hours Rs 1000/- one 5.2 Glands failure Any 5.3 Lugs burnt out Any 6 Earthing 6.1 Earthing failures Any 6.2 GI strip failures Any 7. Power supply failures 8. GSM based automation system 8.1 Monitoring of automation 8.2 Automation system failures 9. Illumination 9.1 Illumination 9.2 Illumination levels Any per hour Permanent restoration and Replacing the damaged poles Permanent restoration and Replacing the damaged poles Immediate / Urgent Immediate / Urgent Permanent restoration and Replacing the damaged parts Permanent restoration Immediate / Urgent Immediate and Replacing the damaged parts Immediate restoration and Replacing the damaged parts / Urgent Immediate / Urgent 6 hours 6 hours Rs 1000/ per hour Routine Daily Rs 1000/ per day Urgent 6 hours Rs 1000/ per hour Immediate / Urgent Daily Rs 1000/ per day 6 hours Rs 1000/ per hour 6 hours Rs 1000/ per hour 6 hours Rs 1000/ per Hour Rs 1000/ per To monitor day to day Any operation of the system and to furnish data Any Any Any To repair/replace faulty components and to upkeep the system in to working condition To maintain at least 98% glowing of LED luminaires To maintain minimum 30 Lux level on main carriageway and 20 Lux on service roads Routine Daily hour Rs 1000/ per day