Facility Condition Assessment Final Report Ferris State University August 2006 1900 West Loop South, Suite 400, Houston, TX 77027 T: 713-871-7000 F: 713-871-7171 www.3di.com Ferris State University Facility Condition Assessment Final Report Table of Contents Executive Summary............................................................................................. 2 Objectives Approach Summary of Findings Interpreting Results Conclusions Summary of Results............................................................................................. 5 Background Deficiency Categories Building System Classifications Replacement vs. Renewal Facility FCI by Building Capital Renewal................................................................................................... 9 Funding Requirements – 10 Year Renewal Projection 10 Year Capital Renewal Forecast COMET Assessment ......................................................................................... 12 Level 2 Facilities Assessment Methodology Priorities ........................................................................................................... 12 Categories ......................................................................................................... 13 Definitions ........................................................................................................ 15 Comet Reports……………….………………………………………...……….17 8/22/06 Page 1 3D/I Ferris State University Facility Condition Assessment Final Report In February 2005 Ferris State University (FSU) authorized 3D/I to conduct a Facilities Assessment of 131 buildings, totaling approximately 3,752,778 square feet. This effort is a Level 2 assessment. Objectives Executive Summary The primary objectives of the Facilities Assessment were to identify overall deferred maintenance in each facility, while providing cost estimates for corrections to return the facility to reliable operating condition. Approach The Facilities Assessment performed for the Ferris State University was a detailed visual inspection of each building. The result of the inspection is a database that catalogs every deficiency with a direct project cost. COMET (Condition Management Estimation Technology) is used as the database software for recording all deficiencies. Craig Anding, Frank Orts, Bill Cadle, Phil Trenbath, Chuck Gulley, Tim Marcus and Varun Chandra were the assessment team for the project. Brian Crum served as Student Intern for the project and provided valuable assistance to the assessment teams. Matt Stanke of FSU was our point of contact during the assessment. Research was conducted for existing data prior to visiting the facility. This research included a review of drawings and other facility information provided by FSU staff. The assessment teams then conducted site visits to verify data already gathered as well as to record additional information found during the inspection. Based on visual observations and discussions with facility occupants and maintenance staff, the assessors determined what deficiencies existed in addition to the general conditions of key building systems. A written description of the facility, including an overview of the facility’s construction, building systems and general condition, was then developed. All assessments were conducted from February 28th, 2005 through May 27th, 2005. The teams visited all facilities to collect data on individual deficiencies and life cycle information. The information was compiled in the field on a handheld computer made by Viewsonic. This information was downloaded to the main COMET database, located on the 3D/I server in Houston. Once downloaded, the assessors priced each deficiency, using R.S. Means as the cost basis. In addition, the assessors added a smart icon with deficiency information for each item on the floor plan drawings attached to the database. In addition to data collected in the field, we also incorporated roofing information provided by TSK Roofing Consulting, Inc. 8/22/06 Page 2 3D/I Ferris State University Facility Condition Assessment Final Report Summary of Findings The costs presented below are a summary of the findings of the project for the assessed deficiencies. The table lists total costs without regard to priority of particular deficiencies. The data includes soft costs associated with a rehabilitation project. Gross Area(Sq.Ft.) Facility Name Total Cost of Assessed Deficiencies Replacement Value FCI % Ferris State University 3,752,778 $209,701,395 $647,943,055 32.36% Big Rapids Campus 3,476,798 $190,271,143 $583,795,856 32.59% 1,712,140 $113,615,541 $245,919,077 46.20% 260,800 $16,734,381 $43,101,991 38.83% 1,451,340 $96,881,160 $202,817,086 47.77% 1,764,658 $76,655,602 $337,876,779 22.69% 275,980 $19,430,252 $64,147,199 30.29% Auxiliary Non-Residential Residential General Funded Grand Rapids Campus Interpreting Results The FCI is a ratio of the cost of assessed deficiencies divided by the replacement value of the facility. It describes the relative state or physical condition of a building (or its components, or a group of buildings) against a cost model of a similar building as if it were at the beginning of its useful life, fully “renewed” to today’s standards. The FCI calculation is shown in the following formula: FCI = Cost of Assessed Deficiencies Replacement Value For example, if a building's replacement value is $10,000,000 and the cost of correcting its assessed deficiencies is $1,000,000, the building's FCI is $1,000,000 ÷ $10,000,000 = 0.10, or we might say the facility is 10 percent deficient. The FCI is particularly useful when comparing similar facilities or campuses within the same portfolio. Flite Library The Association of Higher Education Facility Managers (APPA) and the National Association of College and University Business Officials (NACUBO) have established standard guidelines currently used by owners across the country. These guidelines are shown in tabular form in the second column of the table below. 3D/I has assessed over 1 billion square feet for educational clients across the country and our experience, shown in the third column of the table differs somewhat from the industry guidelines. These figures are provided to help you interpret the results of this survey. Assessed Condition Good Fair (Functional & Repairable) Poor (Needs Significant Attention) Suggests beyond useful life APPA/NACUBO Guidelines 3D/I Experience 0 to 5% 0 to 15% 5.01 to 10% 15.01 to 25% > 10% > 25% > 60% > 70% 8/22/06 Page 3 3D/I Ferris State University Facility Condition Assessment Final Report Conclusions The overall FCI of the facilities at Ferris State University is 32.36%. This is typical of what we find for facilities of similar age and function, across the nation. While this is a “poor” FCI the facilities are generally well maintained. While the majority of the deferred maintenance requirements are of the type that can be renewed without major renovation of the facility, a substantial number require major renovations. This does not say that all facilities should be renovated; rather, renovation may be the best option as the planners consider new buildings, high growth areas, population, and other factors. 8/22/06 Page 4 3D/I Ferris State University Facility Condition Assessment Final Report Background Ferris State University is located in Big Rapids, Michigan. Founded in 1884 by Michigan educator and statesman Woodbridge N. Ferris, the University has developed a modern 880-acre campus in west central Michigan's vacation-recreation country. Deficiency Categories Summary Summary Executive of of Summary Results Results The deficiency costs identified in the assessment are grouped in to Capital Renewal, Deferred Maintenance, Modernization, Plant Adaptation and Routine Maintenance categories (see Categories section on Page 13 for more information): The following chart gives a breakdown of the recorded deficiencies by their respective category for the assessment. $62,367 $13,458,352 $56,682,770 $139,497,904 Capital Renewal Plant Adaptation Deferred Maintenance Routine Maintenance Building Systems Classifications In general, the majority of the costs identified in the assessment are for HVAC, Electrical, Exterior Enclosure and Plumbing. Exterior enclosure deficiencies include doors and windows. The majority of the electrical system costs are for replacement of lighting fixtures, wiring and renewal of the main service and branch circuits. The HVAC costs include air handlers, piping, controls and central heating and cooling equipment. Plumbing costs are mainly for replacement of aging piping systems. Within finishes, the bulk of the costs are for replacing ceilings, wall and floor finishes. Although good maintenance has extended the life of many of these systems, you can expect failure where systems have exceeded their predicted useful life. 8/22/06 Page 5 3D/I Ferris State University Facility Condition Assessment Final Report The following chart gives a breakdown of the recorded deficiencies by their respective Building Systems for the assessment. $7,535,519 $2,465,027 $3,096,601 $4,952,243 $8,852,514 $10,750,171 $68,052,574 $17,986,069 $21,250,357 $40,447,221 $24,313,096 HVAC Interior Finishes Conveying Electrical Fire Protection Special Construction Exterior Enclosure Interior Construction Various Plumbing Roofing Replacement vs. Renewal It is generally held in the property management industry that when an FCI is 60% or greater, replacement of the asset should be considered instead of renewal. For any Ferris State University facilities that may later have an FCI in or near this range, the master planning process should carefully weigh issues such as: • Gym-Student Recreation Center • • • The generally good condition of the existing foundations and superstructures. The need for additional space, i.e., new construction. The appropriateness of the location of current assets. Adequacy of the renewed facility to perform its functional mission for the next 30 years. The costs to renovate the Ferris State University facilities are the estimated costs to repair the existing facilities or build new facilities to comply with current building codes, construction practices and provide modern infrastructure. The general functions within a given building, as well as associated amenities, are not significantly different (we did not add a new functional area that does not exist today), however, code and livability issues are included in the cost models. We chose this methodology because the cost 8/22/06 Page 6 3D/I Ferris State University Facility Condition Assessment Final Report estimates generated by this assessment are more relevant to the planning process than the costs associated with replacing a building in kind. Facility FCI by Building The following is a list of Ferris State University facilities, displaying the FCI: Cost Per Sq. Ft. Gross Area (Sq.Ft.) Total Current Repair Cost Replacement Value FCI % Allied Health $228.17 67,400 $2,402,609 $15,378,658 15.62% Alumni Building $203.47 34,600 $3,104,486 $7,040,062 44.10% Arts & Sciences Commons $180.80 79,259 $894,178 $14,330,027 6.24% Automotive Center $152.36 77,000 $6,355,680 $11,731,720 54.18% Facility Name Birkham Health Center $137.05 18,400 $2,066,705 $2,521,720 81.96% Bishop Hall $148.14 50,900 $2,775,850 $7,540,326 36.81% Bond Hall $163.51 90,500 $5,602,493 $14,797,655 37.86% Brophy Hall $138.46 47,000 $3,960,472 $6,507,620 60.86% Business Building $153.50 90,600 $3,117,701 $13,907,100 22.42% Carlisle Hall $147.83 47,200 $3,462,968 $6,977,576 49.63% Carrillon Tower $11,836 44 $5,781 $520,762 1.11% Clark Hall $138.71 41,500 $3,900,671 $5,756,465 67.76% Copy Center $133.54 4,064 $298,216 $542,707 54.95% Cramer Hall $138.71 91,700 $3,636,131 $12,719,707 28.59% Creative Arts Center $140.78 7,200 $872,323 $1,013,616 86.06% East Campus Apartments $129.46 72,603 $7,093,536 $9,399,103 75.47% Flite Library $219.74 173,484 $628,082 $38,121,374 1.65% General Services Annex $124.64 13,289 $0 $1,656,341 0.00% General Services Building $158.61 27,143 $1,041,568 $4,305,151 24.19% Grand Rapids Art Museum $332.85 75,000 $9,566,570 $24,963,750 38.32% Granger Center $277.35 75,298 $48,171 $20,883,900 0.23% Grounds Facility $75.48 9,100 $168,464 $686,868 24.53% Hallisy Hall $138.27 44,700 $2,743,815 $6,180,669 44.39% Heavy Equipment Center $150.33 52,000 $1,804,342 $7,817,160 23.08% Helen Ferris Hall $134.82 44,300 $3,336,839 $5,972,526 55.87% Henderson Hall $138.47 44,900 $1,986,969 $6,217,303 31.96% Ice Arena $234.34 69,460 $5,195,322 $16,227,285 31.92% Instructional Res Ctr * $209.91 54,700 $4,121,963 $11,482,077 35.90% Johnson Hall $148.58 33,600 $3,127,962 $4,992,288 62.66% Katke Club House $149.51 5,700 $10,371 $852,207 1.22% $56.40 2,800 $93,004 $157,920 58.89% Katke Golf Cart Storage Katke Golf Course Maint. $72.14 3,200 $68,520 $230,848 29.68% Kendall - 110 Ionia Street $197.93 104,914 $5,276,193 $20,765,628 25.41% Kendall - 111 N. Division $197.93 85,670 $4,580,639 $16,956,663 27.01% Kendall - 17 Fountain $140.55 10,396 $6,850 $1,461,158 0.47% Knollcrest $142.77 27,676 $2,450,455 $3,951,303 62.02% Masselink Hall $162.92 104,700 $8,430,993 $17,057,724 49.43% McKessy Barn $47.44 2,000 $43,903 $94,880 46.27% McKessy House $124.17 2,800 $158,263 $347,676 45.52% McNerney Hall $140.34 47,000 $3,354,423 $6,595,980 50.86% Merrill Hall $140.67 51,700 $2,796,351 $7,272,639 38.45% 8/22/06 Page 7 3D/I Ferris State University Facility Condition Assessment Final Report Facility Name Merrill/Travis Commons Cost Per Sq. Ft. Gross Area (Sq.Ft.) Total Current Repair Cost Replacement Value FCI % $154.25 10,720 $965,057 $1,653,560 58.36% Miller Hall $139.09 47,382 $2,772,041 $6,590,362 42.06% Music Activity Center $146.54 10,000 $473,652 $1,465,400 32.32% National Elastomer Center $185.42 43,392 $934,641 $8,045,745 11.62% North (Kirby) Storage Bldg $85.93 10,711 $430,176 $920,396 46.74% Pennock Hall $211.96 50,900 $5,173,061 $10,788,764 47.95% Pharmacy Building $196.10 62,200 $3,816,121 $12,197,420 31.29% Pickell Hall $138.66 50,400 $2,993,763 $6,988,464 42.84% Power Plant ** $482.46 19,900 $3,460,035 $9,600,954 36.04% Prakken Building $151.78 42,100 $2,806,620 $6,389,938 43.92% Puterbaugh Hall $137.83 46,400 $2,405,760 $6,395,312 37.62% Racquet & Fitness Ctr $118.65 38,800 $836,667 $4,603,620 18.17% Rankin Student Center $151.11 109,100 $7,781,826 $16,486,101 47.20% Science Building $213.70 107,300 $4,575,779 $22,930,010 19.96% South Campus Apartments $133.60 53,200 $5,217,233 $7,107,627 73.40% South Commons $156.60 32,460 $1,375,598 $5,083,236 27.06% Southwest Commons $142.79 32,745 $3,312,286 $4,675,659 70.84% Southwest Power Plant $483.11 2,200 $98,124 $1,062,842 9.23% Sports Complex $216.87 83,852 $2,030,019 $18,184,670 11.16% Starr Education Center $191.55 86,400 $3,606,101 $16,549,658 21.79% Student Recreation Center $180.44 116,051 $3,510,815 $20,940,242 16.77% Swan Building $168.75 131,600 $7,770,759 $22,207,618 34.99% Taggart Hall $138.67 47,800 $2,604,686 $6,628,426 39.30% 24.37% Technology Transfer Ctr $139.70 18,142 $617,778 $2,534,498 Timme Center $193.76 57,000 $77,032 $11,044,320 0.70% Travis Hall $140.03 51,700 $2,908,814 $7,239,551 40.18% Vandercook Hall $138.98 41,500 $3,239,723 $5,767,670 56.17% Ward Hall $139.12 41,320 $3,346,101 $5,748,438 58.21% West Building $146.40 23,700 $2,951,926 $3,469,680 85.08% West Campus Apartments $124.83 262,125 $15,186,939 $32,721,062 46.41% W Campus Community Ctr $131.85 5,785 $247,498 $762,752 32.45% West Commons $152.83 19,800 $1,501,795 $3,026,034 49.63% Wheeler Pavilion $202.67 10,593 $83,136 $2,146,883 3.87% $172.66 3,752,778 $209,701,395 $647,943,055 32.36% Totals * scheduled for renovation in 2006 ** this report does not include data from Utility Master Plan and Condition Assessment 8/22/06 Page 8 3D/I Ferris State University Facility Condition Assessment Final Report Funding Requirements – 10 Year Renewal Projection Capital Renewal The following chart illustrates the 10-year total funding requirements for the Ferris State University for three (3) funding scenarios. It shows the combined funding needed for the assessed deficiencies and the predicted capital renewal requirements. Using this chart, we can query: • • • “How much funding is required to maintain the current FCI?” “What level of funding is required to achieve an FCI of 15%?” “What trend does the University’s maintenance budget have on the FCI?” $ , , Current FCI = 32.36% 30.0% $50,000,000 25.0% $40,000,000 20.0% $30,000,000 15.0% $20,000,000 10.0% $10,000,000 5.0% $0 0.0% Year Funding Plan 1 Funding Plan 2 Funding Plan 3 FCI% Progress 1 FCI% Progress 2 FCI% Progress 3 Carillon Tower COMET P i t d 8/21/2006 8/22/06 Page 9 3D/I Ferris State University Facility Condition Assessment Final Report We chose to show these three scenarios: • Current FCI: Keep the current FCI Stable (Red) The red line assumes no spending in the current year (2005) for current deficiencies but capital renewal costs over the next 10 years will be required to maintain the current FCI level. • Required funding: Reduce the FCI to 25% (Blue) The blue line assumes no spending in the current year (2005) for all current deficiencies. It assumes the required level of funds for capital renewal over the next 10 years, in addition to a premium to buy-down the current deficiencies to achieve an FCI of 25%. (Poor standard as published by APPA; Fair per 3D/I Experience.) • Required funding: Reduce the FCI to 15% (Green) The green line assumes no spending in the current year (2005) for all current deficiencies. It assumes the required level of funds for capital renewal over the next 10 years, in addition to a premium to buy-down the current deficiencies to achieve an FCI of 15%. (Poor standard as published by APPA; Good per 3D/I Experience.) Supporting data for this chart with a listing of current deficiencies can be found in the “Deficiency Analysis” reports for each building. Future failure data can be found in the “Facility Renewal Schedule” report for each building. These reports are located in the COMET Reports section. The table below shows the 10 year annual capital renewal funding requirements from the chart above. Year 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 $ $ $ $ $ $ $ $ $ $ Current FCI $ 10,650,900 9,849,330 15,111,200 13,315,800 12,852,500 15,119,200 14,434,100 9,329,980 15,969,800 38,628,700 $ $ $ $ $ $ $ $ $ $ FCI 25% $ 15,565,700 14,911,500 20,325,200 18,686,300 18,384,000 20,816,700 20,302,500 15,374,400 22,195,600 45,041,300 $ $ $ $ $ $ $ $ $ $ FCI 15% $ 22,239,500 21,785,500 27,405,500 25,978,900 25,895,500 28,553,500 28,271,400 23,582,400 30,649,800 53,749,100 Total $155,261,510 $211,603,200 $288,111,100 Average $ 15,526,151 $ 21,160,320 $ 28,811,110 8/22/06 Page 10 3D/I Ferris State University Facility Condition Assessment Final Report 10 Year Capital Renewal Forecast $ , , $30,000,000 $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 $0 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Year Big Rapids Campus Grand Rapids Campus The cost models for each building give us a method to predict future needs for capital renewal. Each model allows us to assess the remaining life of each of the main systems in the building, and to enter into the cost model the expected time of replacement. Although that is only a rough approximation for one building, over a larger sample it produces a reliable estimate of the yearly cost to replace building systems. This chart illustrates a 10-year projection of capital renewal funding requirements, excluding current deficiencies for each facility. The data supporting this chart can be found on the Facility Renewal Schedule report for each building included in the Comet Reports section. The rule of thumb accepted by APPA/NACUBO suggests an annual target range of 1.5% to 3% of CRV for funding of capital renewal. Note that removing buildings from the portfolio can have a dramatic effect on your overall FCI and future funding requirements. 8/22/06 Page 11 3D/I Ferris State University Facility Condition Assessment Final Report COMET Assessments Condition Management Estimation Technology 3D/International Facility Management Software Level 2 Facilities Assessment Methodology A Level 2 (L-2) assessment is a detailed physical survey of hundreds or thousands of current deficiencies, which are added to the L-1 component building system life cycles. Together they determine a Facilities Assessment of both current deficiencies and future renewal costs. It is a tactical tool for facility managers to identify specific deferred maintenance and capital renewal items to repair or replace. For this type of assessment, we collected data from a review of drawings and other current documents as well as a complete visual inspection of facilities. All areas of a building are investigated including areas such as crawl spaces, attic spaces, roofs, mechanical rooms, and exterior support areas to include landscaping, parking and sidewalks. The first phase of this L-2 assessment is the review of the drawings of each facility to be assessed. Once reviewed, a “tree” structure, a flow chart of the facility’s rooms and spaces, is designed in the COMET software. The tree structure provides the assessor a road map of the building, and the lowest level of the tree structure is where each deficiency will be recorded. The next step is to develop cost models made up of pertinent building systems. Finally, each room in the building is visited by the assessment team to collect individual deficiencies. Priorities Frequently, many of the buildings assessed are over 40 years old and will have high FCI’s. In order to help prioritize which buildings should be addressed most immediately, we establish repair priorities. These are the priorities established for Ferris State University: . PRIORITY 1 - Currently Critical (Immediate) Projects in this category require immediate action to: 1. Return a facility to normal operation 2. Stop accelerated deterioration 3. Correct a cited safety hazard PRIORITY 2 - Potentially Critical (Year One) Projects in this category, if not corrected expeditiously, will become critical within a year. Situations in this category include: 1. Intermittent interruptions 2. Rapid deterioration 3. Potential safety hazards 8/22/06 Page 12 3D/I Ferris State University Facility Condition Assessment Final Report PRIORITY 3 - Necessary - Not Yet Critical (Year Two - Five) Projects in this category include conditions requiring appropriate attention to preclude predictable deterioration or potential downtime and the associated damage or higher costs if deferred further. PRIORITY 4 - Recommended (Year Six - Ten) Projects in this category include items that represent a sensible improvement to existing conditions. These items are not required for the most basic function of a facility; however, Priority 4 projects will either improve overall usability and/or reduce long term maintenance. With these priorities assigned, we can compare two facilities with similar FCI’s to help determine the most critical need. Categories Categories To further enhance reporting, each Project is assigned a category based on the structure below. Plant Adaptation: Expenditures required to adapt the physical plant to the evolving needs of the institution and to changing standards. These are expenditures in addition to normal maintenance. Examples include compliance with changing codes (e.g., handicapped accessibility), and improvements occasioned by the adoption of modern technology (e.g., the use of personal computer networks). Routine Maintenance: Means the day-to-day efforts to control deterioration of facilities (up keep expenses) through scheduled repetitive activities (e.g. cleaning), periodic scheduled work (e.g., inspections and equipment adjustments) and minor repairs made on an as-needed basis. Deferred Maintenance: Refers to expenditures for repairs which were not accomplished as a part of normal maintenance or capital repair which have accumulated to the point that facility deterioration is evident and could impair the proper functioning of the facility. Costs estimated for deferred maintenance projects should include compliance with applicable codes even if such compliance requires expenditures additional to those essential to affect needed repairs. Deferred maintenance projects represent catch up expenses. Capital Renewal: A subset of regular or normal facility maintenance which refers to major repairs or the replacement/rebuilding of major facility components (e.g., roof replacement at the end of its normal useful life is capital repair; roof replacement several years after its normal useful life is deferred maintenance). 8/22/06 Page 13 3D/I Ferris State University Facility Condition Assessment Final Report Modernization: Refers to system improvement associated with replacement of major facility components (e.g., replacement of the heating and ventilating systems at the end of their normal useful life is capital repair; adding air conditioning to the replacement project is a modernization cost). Loss Control: Refers to expenditures for implementation of recommendations made by FM Global or current university loss control consultant in their quarterly reports. 8/22/06 Page 14 3D/I Ferris State University Facility Condition Assessment Final Report Definitions City Cost Index The R.S. Means data used to develop the cost models is a national average. As such, we modified the costs using a standard index published by the R.S. Means Corporation. The current index for Big Rapids, Michigan is 84.2% of the national average. Facility Condition Index The facility condition index (FCI) represents the relative physical condition of facilities. The FCI measures the estimated cost of the current year deficiencies, including recommended improvements and grandfathered issues, and compares it to the projected replacement cost of the facility. The total cost of the repairs is divided by the current replacement cost for the facility, resulting in the FCI. The higher the FCI is, the poorer the relative condition of the facility. For example, if a building has a replacement value of $1,000,000 and has $100,000 of existing deficiencies, the FCI is $100,000/$1,000,000 or 0.10. Facility Replacement Cost Replacement cost represents the hypothetical expense of rebuilding the existing facilities in a manner similar to the original construction, including appropriate upgrades to meet contemporary codes and standards. It is determined by multiplying the gross area of the facility by a per-square-foot cost estimate. The estimate excludes site development, fixtures, furnishings, and equipment (FF&E). Soft Costs Soft costs are additional costs that are necessary to accomplish the corrective work but are not directly attributable to a deficient system. Soft costs vary by user but can include: construction contingency; design; specialized investigations such as geotechnical, environmental, or hazardous material; program management fees whether in-house or through a consultant; and various administrative fees. Soft costs must be added to the R.S. Means unit costs used in our estimates to show the true cost of the corrections. The costs used in this assessment of these buildings are as follows: General Contract = R.S. Means Unit Prices + General Conditions/Overhead/Profit @12% + Testing @.03% + Performance Bond @1% Owner’s Soft Costs = Contingency @10% + A/E Fees @7% + Construction Mgmt @5% + Project Management @5% + Escalation @3% + Advertising @.01% + Special Consultants @3% 8/22/06 Page 15 3D/I Ferris State University Facility Condition Assessment Final Report Based on these percentages, the prices shown on the reports have a total multiplier of 1.518 over R.S.Means unit prices. An additional soft cost factor of 50% was added to all deficiencies identified in historic buildings. It is important to note that these costs may vary once plans for executing the work are created. Building Systems Buildings are divided into systems, as follows: (with expected life cycles and renewal factors noted) SYSTEM A1010 Standard Foundations A1020 Special Foundations A1030 Slab on Grade A2020 Basement Walls B1010 Floor Construction B1020 Roof Construction B2010 Exterior Walls B2020 Exterior Windows B2030 Exterior Doors B3010 Roof Coverings B3020 Roof Openings C1010 Partitions C1020 Interior Doors C1030 Fittings C2010 Stair Construction C3010 Wall Finishes C3020 Floor Finishes C3030 Ceiling Finishes D1010 Elevators and Lifts D2010 Plumbing Fixtures D2050 Plumbing Piping D3030 Heating/Cooling Generating Systems D4010 Sprinklers D4030 Fire Protection Specialties D5010 Electrical Service/Distribution D5020 Lighting and Branch Wiring D5030 Communications and Security E1010 Commercial Equipment E1020 Institutional Equipment E1030 Vehicular Equipment E2010 Fixed Furnishings E2020 Moveable Furnishings Life 100 100 100 100 100 100 25 25 25 15 20 40 40 40 40 10 15 20 30 30 30 25 25 25 30 20 10 20 20 20 15 15 Renewal Premium 100% 100% 100% 100% 100% 100% 105% 105% 105% 120% 100% 110% 107% 100% 125% 100% 100% 120% 100% 90% 100% 100% 100% 100% 100% 90% 100% 100% 100% 100% 100% 100% 8/22/06 Page 16 3D/I Ferris State University Facility Condition Assessment Final Report Comet Reports 8/22/06 Page 17 3D/I 1900 West Loop South, Suite 400 ▪ Houston, Texas 77027 ▪ T: 713-871-7000 ▪ F: 713-871-7171 3D/I