REIA Report - Karnataka State Pollution Control Board

advertisement
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Chapter –1
Introduction
1.0
Purpose of the Report
Jamkhandi Sugars Limited (JSL) is proposed to enhancethe Sugar Unit with a capacity
from 2500 TCD to 3500 TCD along with Cogeneration power plant from 15 MW to 27 MW
capacity at village Nad KD, Taluka Indi, District- Bijapur, State- Karnataka.
The purpose of this report is to present the environmental related issues of the enhanced
project from 2500 TCD to 3500 TCD of sugar unit and 15 MW to 27 MW cogeneration of
power plant in an area of 98.04 acres at NAD KD village, Indi Taluka, Bijapur District of
Karnataka. This project requires environmental clearance as per EIA Notification dated 14th
September 2006.
The Terms of References issued by MoEFvide Letter no. J-13012/38/2012 - IA. II (T) dated
October 29, 2012for carrying out the Environmental Impact Assessment study.
1.1
Identification of Project
The salient features of the study area covering 10 km radius from the project site are
described below in Table 1.1.
Table – 1.1
Salient Features of the Project Site
Enhanced Capacity from 2500 TCD to 3500 TCD
Name of the Project
of Sugar Plant and 15 MW to 27 MW of
Cogeneration Power Plant
Location of Project
Village
Nad KD
Taluka
Indi
District
Bijapur
State
Karnataka
Coordinates of the plant site
17o07‟ 37.40”N , 76 o07‟43.00”E
17 o07‟36.95”N, 76 o 08‟03.20”E
17 o07 ‟12.08”N, 76 o 07‟ 57.98”E
17 o07‟12.19”N, 76 o 07 ‟43.25”E
Elevation
458 m above Mean Sea Level
General Climatic Conditions
Bhagavathi Ana Labs Ltd., Hyderabad.
1
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Maximum Temperature (°C)
45 °C
Minimum Temperature (°C)
20°C
Relative Humidity (Maximum) (%)
55%
Annual average Rainfall (mm)
595 mm
Dominant wind direction (during study
period)
Jamkhandi Sugars Limited
– Unit II
North-East (NE)
Accessibility
Road Connectivity
 National Highway (NH-13)- 13.0 km
 State Highway(SH-34) of Indi-Afazalpur– 2.0 km
Rail Connectivity
Railway station Indi–24km
Airport
Belgaum–300km
Environmental Sensitivity
 Sattanalnadi–1.5 km
Water bodies
 DoddaNalla- 5.2 km
 Bhima river – 9.0 km
Forest Area
Sanctuaries / National Parks
Archaeological/Historically Important Site
Seismic zone
None within the 10 km radius of the proposed plant
site
None within the 10 km radius of the proposed plant
site
None within the 10 km radius of the proposed plant
site
Seismic Zone –II as per IS: 1893-2002 , GOI
The location and topographical mapsof 10 km radius study area of project site is shown in
Fig 1.1 and Fig 1.2 respectively.
1.2
Project Proponent
Jamkhandi Sugars Limited is managed under the leadership of its Chairman Shri S.B.
Nyamagouda, who is an Ex- member of Karnataka State Legislative Council and Ex- Union
Minister.The Managing Director is Shri S. Dhayanandhan.Both the Chairman and the
Managing Director are highly experienced and successfully managing various industries
including the existing sugar unit –I at Jamkhandiand allied co-generation unit. It is under the
leadership of these two that the Jamkhandi Sugars Ltd., was received awards of “Best
Performance Sugar Factory and Best Cane Development” Third Place in Karnataka for the
Crushing Season 2009-2010, “Best Performance Sugar Factory and best Cane
Bhagavathi Ana Labs Ltd., Hyderabad.
2
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Development “second place in Karnataka for the Crushing Season 2006-2007 from the
South Indian Sugarcane & Sugar Technologists „Association (SISSTA )and second place for
Best Cogeneration Award (2007-08).
1.3
Brief Description of Project site
JSL is located in the Bhima river belt, which is ideal basin for growing rich varieties of sugar
cane to achieve highest yield. In view of the cane availability at NAD KD, JSL has
establishedSugar unit and proposed to enhance from 2500 TCD to3500 TCD capacity with
cogeneration of 27 MW.
The site is centrally located in the area of operation and is in heart of sugarcane area.
The project site is well connected to the village roads for transportation of sugar cane by
carts/trucks. An adequate skilled, semi-skilled and unskilled labourforce is available in the
study area.Theinfrastructure facilities like power, road, communication facilities, and banks
are available around the project site.
1.4
Project Importance to the Country & Region
The sugar industry scenario in Karnataka and in Nation is very bright as India being the
second largest producer of sugarcane in the world and the second largest producer of sugar
next to Brazil. There is a very good scope for export of quality sugar.
Present Status of Demand and Availability
The existing Sugar factories could not crush all available cane from the areas of operation
and hence, rest of the sugarcane is being taken to the sugar factories in neighbouring
districts of Karnataka and Maharashtra.Presently, the cane grown by farmers are diverting to
the sugar factories located in Maharashtra, in this connection farmers are suffering like delay
in disposal, less price, less payment etc., Thus, the farmers are facing problems of disposal
of sugarcane in 3-4 seasons. This situation has demanded to need Sugar units at this area.
The demand for electrical power has been increasing at a faster pace after the country‟s
economic development the pace speeded up, especially in Karnataka which has been the
hub of software services. The effective generation of power has not been meeting the
demand and the same trend is expected to continue, especially during the peak hours and
summer seasons. Hence, there is good scope for exporting power to the third parties using
the state grid through power traders / purchasers.
Bhagavathi Ana Labs Ltd., Hyderabad.
3
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
1.5
Jamkhandi Sugars Limited
– Unit II
Scope of the Study
M/s Jamkhandi Sugars Limitedhas entrusted to M/s Bhagavathi Ana Labs Ltd, Hyderabad,
so as to carryout Environmental Impact Assessment (EIA) studies and to prepare an
effective Environmental Management Plan for implementation during the operation of the
project.
Scope of this study is to identify environmental impacts and to provide mitigation measures
as per Ministry of Environment & Forests (MoEF)/ Central Pollution Control Board (CPCB)
guidelines. The report is prepared based on TORs issued by MoEF reference no. F. No J13012/38/2012 - IA. II (T) dated October 29, 2012.
The TORs issued by MOEF Expert Appraisal Committee are given as under:i) Vision document specifying prospective long term plan of the site, if any, shall be
formulated and submitted.
ii) Status of compliance to the conditions stipulated for environmental and CRZ clearances of
the previous phase(s), as applicable, shall be submitted.
iii) Status of compliance to the conditions stipulated in the environmental clearances
accorded for sugar plant shall be submitted as applicable.
iv) Executive summary of the project indicating relevant details along with recent
photographs of the approved site shall be provided. Response to the issues raised
during Public Hearing and to the written representations (if any), along with a time
bound Action Plan and budgetary allocations to address the same, shall be provided in a
tabular form, against each action proposed.
v) Harnessing solar power within the premises of the plant particularly at available roof tops
and other available areas shall be formulated and status of implementation shall be
submitted to the Ministry.
vi) The coordinates of the approved site including location of ash pond shall be submitted
along with topo sheet (1:50,000 scale) and confirmed GPS readings of plant boundary and
NRS satellite map of the area, shall be submitted. Elevation of plant site and ash pond with
respect to HFL of water body/nallah/river shall be specified, if the site is located in proximity
to them.
vii) Layout plan indicating break-up of plant area, ash pond, area for green belt,
infrastructure, roads etc. shall be provided.
viii) Land requirement for the project shall be optimized and in any case not more than what
has been specified by CEA from time to time. Item wise break up of land requirement and
revised layout (as modified by the EAC) shall be provided.
Bhagavathi Ana Labs Ltd., Hyderabad.
4
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
ix) Present land use as per the revenue records (free of all encumbrances of the proposed
site, shall be furnished. Information on land to be acquired) if any, for coal transportation
system as well as for laying of pipeline including ROW shall be specifically stated.
x) The issues relating to land acquisition and R&R scheme with a time bound Action
Plan should be formulated and clearly spelt out in the EIA report.
xi) CWC clearance for drawl of water from the river for the proposed TPP shall be submitted.
xii) Satellite imagery or authenticated toposheet indicating drainage, cropping pattern, water
bodies (wetland, river system, stream, nallahs, ponds etc.), location of nearest villages,
creeks, mangroves, rivers, reservoirs etc. in the study area shall be provided.
xiii) Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as
proposed), migratory routes / wildlife corridor, if any, within 10 km of the project site shall be
specified and marked on the map duly authenticated by the Office of the Chief Wildlife
Warden of the area concerned.
xiv) Topography of the study area supported by toposheet on 1:50,000 scale of Survey of
India, alongwith a large scale map preferably of 1:25,000 scale and the specific information
whether the site requires any filling shall be provided. In that case, details of filling, quantity
of fill material required; its source, transportation etc. shall be submitted.
xv) A detailed study on land use pattern in the study area shall be carried out including
identification of common property resources (such as grazing and community land, water
resources etc.) available and Action Plan for its protection and management shall be
formulated. If acquisition of grazing land is involved, it shall be ensured that an equal area of
grazing land to be acquired is developed alternatively and details plan shall be submitted.
xvi) A mineralogical map of the proposed site (including soil type) and information (if
available) that the site is not located on economically feasible mineable mineral deposit shall
be submitted.
xvii) Details of 100% fly ash utilization plan as per latest fly ash Utilization Notification of GOI
along with firm agreements / MoU with contracting parties including other usages etc. shall
be submitted. The plan shall also include disposal method / mechanism of bottom ash.
xviii) Water requirement, calculated as per norms stipulated by CEA from time to time, shall
be submitted along with water balance diagram. Details of water balance calculated shall
take into account reuse and re-circulation of effluents which shall be explicitly specified.
xix) Water body/nallah (if any) passing across the site should not be disturbed as far as
possible. In case any nallah / drain have to be diverted, it shall be ensured that the diversion
does not disturb the natural drainage pattern of the area. Details of diversion required shall
be furnished which shall be duly approved by the concerned department.
Bhagavathi Ana Labs Ltd., Hyderabad.
5
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
xx) It shall also be ensured that a minimum of 500 m distance of plant boundary is kept from
the HFL of river system / streams etc.
xxi) Hydro-geological study of the area shall be carried out through an institute/ organisation
of repute to assess the impact on ground and surface water regimes. Specific mitigation
measures shall be spelt out and time bound Action Plan for its implementation shall be
submitted.
xxii) Detailed Studies on the impacts of the ecology including fisheries of the
river/estuary/sea due to the proposed withdrawal of water / discharge of treated wastewater
into the river/creek/ sea etc shall be carried out and submitted along with the EIA Report. In
case of requirement of marine impact assessment study, the location of intake and outfall
shall be clearly specified along with depth of water drawl and discharge into open sea.
xxiii) Source of water and its sustainability even in lean season shall be provided along with
details of ecological impacts arising out of withdrawal of water and taking into account interstate shares (if any). Information on other competing sources downstream of the proposed
project. Commitment regarding availability of requisite quantity of water from the Competent
Authority shall be provided along with letter / document stating firm allocation of water.
xxiv) Detailed plan for carrying out rainwater harvesting and its proposed utilisation in the
plant shall be furnished.
xxv) Feasibility of zero discharge concept shall be critically examined and its details
submitted.
xxvi) Optimization of COC along with other water conservation measures in the project shall
be specified.
xxvii) Plan for recirculation of ash pond water and its implementation shall be submitted.
xxviii) Detailed plan for conducting monitoring of water quality regularly with proper
maintenance of records shall be formulated. Detail of methodology and identification of
monitoring points (between the plant and drainage in the direction of flow of surface / ground
water) shall be submitted. It shall be ensured that parameter to be monitored also include
heavy metals.
xxix) Socio-economic study of the study area comprising of 10 km from the plant site shall be
carried out by a reputed institute / agency which shall consist of detail assessment of the
impact on livelihood of local communities.
xxx) Action Plan for identification of local employable youth for training in skills, relevant to
the project, for eventual employment in the project itself shall be formulated and numbers
specified during construction & operation phases of the Project.
Bhagavathi Ana Labs Ltd., Hyderabad.
6
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
xxxi) If the area has tribal population it shall be ensured that the rights of tribals are well
protected. The project proponent shall accordingly identify tribal issues under various
provisions of the law of the land.
xxxii) A detailed CSR plan along with activities wise break up of financial commitment shall
be prepared. CSR component shall be identified considering need based assessment study.
Sustainable income generating measures which can help in upliftment of poor section of
society, which is consistent with the traditional skills of the people, shall be identified.
Separate budget for community development activities and income generating programmes
shall be specified.
xxxiii) While formulating CSR schemes it shall be ensured that an in-built monitoring
mechanism for the schemes identified are in place and mechanism for conducting annual
social audit from the nearest government institute of repute in the region shall be prepared.
The project proponent shall also provide Action Plan for the status of implementation of the
scheme from time to time and dovetail the same with any Govt. scheme(s). CSR details
done in the past should be clearly spelt out in case of expansion projects.
xxxiv) R&R plan, as applicable, shall be formulated wherein mechanism for protecting the
rights and livelihood of the people in the region who are likely to be impacted, is taken into
consideration. R&R plan shall be formulated after a detailed census of population based on
socio economic surveys who were dependant on land falling in the project, as well as,
population who were dependant on land not owned by them.
xxxv) Assessment of occupational health as endemic diseases of environmental origin shall
be carried out and Action Plan to mitigate the same shall be prepared.
xxxvi) Occupational health and safety measures for the workers including identification of
work related health hazards shall be formulated. The company shall engage full time
qualified doctors who are trained in occupational health. Health monitoring of the workers
shall be conducted at periodic intervals and health records maintained. Awareness
programme for workers due to likely adverse impact on their health due to working in nonconducive environment shall be carried out and precautionary measures like use of personal
equipments etc. shall be provided. Review of impact of various health measures undertaken
at intervals of two years shall be conducted with an excellent follow up plan of action
wherever required.
xxxvii) One complete season site specific meteorological and AAQ data (except monsoon
season) as per MoEF Notification dated 16.11.2009 shall be collected and the dates of
monitoring recorded. The parameters to be covered for AAQ shall include SPM, RSPM
(PM10, PM2.5), SO2, NOx, Hg and O3 (ground level). The location of the monitoring stations
Bhagavathi Ana Labs Ltd., Hyderabad.
7
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
should be so decided so as to take into consideration the pre-dominant downwind direction,
population zone, villages in the vicinity and sensitive receptors including reserved forests.
There should be at least one monitoring station each in the upwind and in the pre - dominant
downwind direction at a location where maximum ground level concentration is likely to
occur.
xxxviii) A list of industries existing and proposed in the study area shall be furnished.
xxxix) Cumulative impact of all sources of emissions (including transportation) on the AAQ of
the area shall be well assessed. Details of the model used and the input data used for
modelling shall also be provided. The air quality contours should be plotted on a location
map showing the location of project site, habitation nearby, sensitive receptors, if any. The
wind roses should also be shown on the location map as well.
xl) Composition of fuels and its ratio (as applicable) to be explicitly stated.
xli)Fuel analysis shall be provided. Details of auxiliary fuel, if any, including its quantity,
quality, storage etc. should also be furnished.
xlii) Quantity of fuel required, its source and characteristics and documentary evidence to
substantiate confirmed fuel linkage shall be furnished.
xliii) Details of transportation of fuel from the source (including port handling) to the proposed
plant and its impact on ambient AAQ shall be suitably assessed and submitted. If
transportation entails a long distance it shall be ensured that rail transportation to the site
shall be first assessed. Wagon loading at source shall preferably be through silo/conveyor
belt.
xliv) For proposals based on imported coal, inland transportation and port handling and
rolling stocks /rail movement bottle necks shall be critically examined and details furnished.
xlv) Details regarding infrastructure facilities such as sanitation, fuel, restrooms, medical
facilities, safety during construction phase etc. to be provided to the labour force during
construction as well as to the casual workers including truck drivers during operation phase
should be adequately catered for and details furnished.
xlvi)EMP to mitigate the adverse impacts due to the project along with item - wise cost of its
implementation in a time bound manner shall be specified.
xlvii) A Disaster Management Plan (DMP) along with risk assessment study including fire
and explosion issues due to storage and use of fuel should be carried out. It should take
into account the maximum inventory of storage at site at any point of time. The risk contours
should be plotted on the plant layout map clearly showing which of the proposed activities
would be affected in case of an accident taking place. Based on the same, proposed
Bhagavathi Ana Labs Ltd., Hyderabad.
8
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
safeguard measures should be provided. Measures to guard against fire hazards should
also be invariably provided.
xlviii) The DMP so formulated shall include measures against likely Tsunami/Cyclones/Storm
Surges/Earthquakes etc, as applicable. It shall be ensured that DMP consists of both on-site
and off-site plan, complete with details of containing likely disaster and shall specifically
mention personnel identified for the task. Smaller version of the plan shall be prepared both
in English and local languages.
xlix) Detailed plan for raising green belt of native species of appropriate width (50 to 100 m)
and consisting of at least 3 tiers around plant boundary (except in areas not possible) with
tree density of 2000 to 2500 trees per ha with a good survival rate of about 80% shall be
submitted. Photographic evidence must be created and submitted periodically including
NRSA reports.
l) Status of development of green belt shall also be submitted along with photographic
details.
li) Over and above the green belt, as carbon sink, additional plantation shall be carried out in
identified blocks of degraded forests, in close consultation with the District Forests
Department. In pursuance to this the project proponent shall formulate time bound Action
Plans along with financial allocation and shall submit status of implementation to the Ministry
every six months.
lii) Corporate Environment Policy
i.
Does the company has a well laid down Environment Policy approved by its Board
of Directors? If so, it may be detailed in the EIA report.
ii.
Does the Environment Policy prescribe for standard operating process / procedures
to bring into focus any infringement / deviation / violation of the environmental or
forest norms / conditions? If so, it may be detailed in the EIA.
iii. What is the hierarchical system or Administrative order of the company to deal with
the environmental issues and for ensuring compliance with the environmental
clearance conditions. Details of this system may be given.
iv. Does the company has system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or shareholders
or stakeholders at large? This reporting mechanism should be detailed in the EIA
report.
All the above details should be adequately brought out in the EIA report and in the
presentation to the Committee.
Bhagavathi Ana Labs Ltd., Hyderabad.
9
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
liii) Details of litigation pending or otherwise with respect to project in any court, tribunal etc.
shall invariably be furnished.
Bhagavathi Ana Labs Ltd., Hyderabad.
10
EIA/EMP of 3500 TCD Sugar Plant and 27 MW Cogeneration Power
Plant
M/s Jamkhandi Sugars Limited –
Unit II
Chapter –2
Project Description
2.0 Type of Project
Jamkhandi Sugars Ltd., (JSL) proposesto enhance from 2500 TCD to 3500 TCD of sugar
unit and 15 MW to 27 MW of cogeneration power plant in an area of 98.04 acres at Nad KD
village, Indi Taluka, Bijapur district of Karnataka.
The raw material sugar cane is available in the vicinity of the project site and the bagasse
will be used as fuel for cogeneration power plant.
The project developments of the Jamkhandi Sugars Ltd.,are listed below:

Jamkhandi Sugars Ltd., obtained Environmental Clearance vide letter no. SEIAA
A:29:IND:2007 Dated: 29th December 2009,for 2500 TCD of Sugar Unit along with 15
MW of Co-generation Power Plant by State Level Environment Impact Assessment
Authority, Karnataka.

Consent order for Establishment (CFE) for 2500 TCD of Sugar unit from KSPCB Vide
No. CFE-CELL/JSL-U-IL/EIA-726/2007-2008/110 Dated: 16-06-2007.
2.1
Need for the Project
JSL is located in the Bhima river belt, which is ideal basin for growing rich varieties of sugar
cane to achieve highest yield. In view of the cane availability at NAD KD, JSL has
establishedSugar unit and proposed to enhance from 2500 TCD to3500 TCD capacity with
cogeneration of 27 MW.
The area of Bhima river belt and UKP irrigation in the Indi Taluka is the most ideal belt for
growing rich varieties of sugar cane to achieve highest recovery. Due to continuous water
availability and UKP irrigation facilities, the sugar cane area under cultivation has increased
substantially in Bijapur District than required for the existing sugar factory crushing capacity.
The site is centrally located in the area of operation and is in heart of sugarcane area. The
site of Jamkhandi Sugars Ltd., possess the following advantages:-
Bhagavathi Ana Labs Ltd., Hyderabad.
11
EIA/EMP of 3500 TCD Sugar Plant and 27 MW Cogeneration Power
Plant
M/s Jamkhandi Sugars Limited –
Unit II
 The project site is well connected to the village roads for supply of raw material sugar
cane.
 The adequate skilled, semi-skilled and unskilled labour forceis available in the vicinity
of project area.
 All the infrastructure facilities like power, road, communication facilities, banks are
available in the vicinity of the project area.
2.2
Location
This project of Enhancement from 2500 TCD to 3500 TCD capacity Sugar Plant with
Cogeneration of 15 MW to 27 MW Power Plant is located at Nad KD village ,Indi Taluka,
BijapurDistrict , Karnataka state. The plant layout ofthe project site is shown in Fig.2.1.
2.3
Technical Details
The technical features of 3500 TCD Sugar Unit and 27 MW Cogeneration Plant areprovided
in Table 2.1.
Table 2.1
Technical Information of Sugar Unit and Cogeneration Plant
Parameter
Description
Production Capacity
3500 TCD Sugar Unit and 27 MW Cogeneration Plant
a. Sugar Plant:-Sugar Cane:3500 T/day
Raw Materials Requirement
b. Bagasse:- 1085 T/day
c. Agro Waste: 547 T/day
2600m3/day and will be sourced from Bhima River
through pipeline. The intake point of water is at a
distance of 9.0 km from the project site.
Water drawl permission obtained for 400 KLD
Water source and Requirement LrNo.KNNL/IPZ/CEG/TA-1/AE-1/2011-12/4100 Dated:
09-01-2012.
Revised application submitted for 3000 KLD of water
drawl.
Boiler Capacity
Power Generation
120 TPH Capacity, 110 ata pressure, 540C
Cane Crushing Season:14,540 (KW)
Off Season :21,400 (KW)
2.4
Basic Requirements for the Proposed Project
2.4.1
Land Requirement
The project is identified in a non-agricultural revenue land of 98.04 acres.The Land Use
break up is given in the following Table 2.3.
Bhagavathi Ana Labs Ltd., Hyderabad.
12
EIA/EMP of 3500 TCD Sugar Plant and 27 MW Cogeneration Power
Plant
Table 2.3
Land Use Break up of Project Area
Description
Area in
S.
No.
Acres
17.96
ha
7.27
1.
Built Up Area
2.
Water Storage Facility
5.00
2.02
3.
Area for Green Belt (33%)
32.35
13.10
4.
Future Expansion
42.73
17.30
98.04
39.69
Total Area
2.4.2
M/s Jamkhandi Sugars Limited –
Unit II
Water Requirement
The total water requirement for the project is 2600m3/day during the crushing and during the
slack season. Water will be met from Bhima River through pipeline and the water intake
point is at a distance of 9.0 km from the project site. The total water requirement is given in
Table–2.4.
Table – 2.4
Water for proposed plant
Capacity
No. of
working
days
Standard
water
required
Sugar Unit
3500 TCD
260
120ltr per
ton
Co-generation
MW 27x 24
Hrs
300
3.5 KL/MW
108 persons
365
135 Ltr/day
5321.7
14.58
250 persons
365
45 Ltr/day
4106.25
2362.5
11.25
11.25
Details
KL/Annum
M3/day
Manufacturing Details
32,760
37.8
680400
2268
Staff Quarters and Man Power
Staff Quarters
Employees
Regular Employees
Employees during crushing season
250 persons
210
45 Ltr/day
3000 persons
Approx
210
45 Ltr/day
Indirect Employees
Farmers, visitors, drivers, claners, cart
drivers, bullock carts etc
28350
135
10500
Canteen
Total
28.76712
2506.647
~2600
218837
Cycle of concentration (COC) is considered for the project is 1.5Water balance diagram is
given in Figure-2.3.
Bhagavathi Ana Labs Ltd., Hyderabad.
13
EIA/EMP of 3500 TCD Sugar Plant and 27 MW Cogeneration Power
Plant
M/s Jamkhandi Sugars Limited –
Unit II
Figure-2.3 Water balance diagram (m3/hr)
Bhagavathi Ana Labs Ltd., Hyderabad.
14
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
2.4.3
Jamkhandi Sugars Limited
– Unit II
Raw Material Requirement
The raw materials requirementis given in Table-2.5.
Table- 2.5
Raw Material Requirement
S.No.
Item
Quantity TPD
1
Raw Material Sugarcane
3500
2
Consumables ( Chemicals)
3
2.5
Lime
3.5
Caustic soda (100%)
0.1
Sulphur
0.7
Hydrochloric acid (30%)
0.1
Sodium Chloride
0.1
Phosphoric Acid
0.05
Oils& grease
0.02
Filter aid (Bagasse,50% moisture)
28
Products
Sugar
350
Bagasse,(50% moisture)
1085
Press mud (75% moisture)
140
Molasses (25% moisture)
140
Utilities
Utilitieswill be provided for smooth and efficient functioning of the enhancedproject of 3500
TCD Sugar Unit and 27 MW Cogeneration Plant.
These include the following:2.5.1
Water
The total water requirement for the proposed project is 2600 KLPDduring crushing season
and slack season.
There will be masonry underground reservoir to store water in the plant premises.
Bhagavathi Ana Labs Ltd., Hyderabad.
1
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
There will be an overhead RCC tank to supply drinking water to the colony and the factory.
Nearly, 15 m head should be available from this tank. Arrangement for pumping water from
the underground water reservoir to the M.S. tank to the pan floor directly should also be
made.
2.5.2
Power
The plant requires 500 KVA at 415 V. Three phase electric supply from the State Electricity
Board for initial erection activity and after completion of project, by erection of Cogeneration
Plant which would meet the demand of the plant.500 KVA transformer with necessary switch
gear will be installed.
Standby Power
One set of 500 KW capacity DG set will be installed in the initial stages of construction to
supply standby electric power during power cuts/break downs in grid supply. During crushing
season, all electric requirements, of the plant and machinery and residential complex shall
be met from the Cogeneration plant.
JSL will install the DG set as a standby power supply system unit to meet emergency
requirement.
2.5.3Fuel
Fuel requirement is mainly for generation of steam in the boiler. Bagasse generated from the
Sugar Plant i.e. 1085 TPD will be used as fuel for operation of the boiler. The fuel
characteristics is given as under:Table 2.6
Characteristics of Bagasse
S.No.
Particulars
Value
1
Calorific Value
4400 Kcal/kg (dry)
2250 Kcal/kg (wet)
2
Moisture content
45 – 55%
3
Ash Content
2 – 10 %
4
In sugar mill the crushed cane
forms bagasse
30 -35%
Bhagavathi Ana Labs Ltd., Hyderabad.
2
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Table – 2.7
S. No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
Characteristics of Diesel Fuel (IS: 1448)
Parameter
Value
Acidity
Nil
Ash%, by mass
0.01
Carbon residue %, by mass
0.30
Pour point, Max
03C for winter, 15C for summer
Flash point
35C
Kinematic Viscosity, cSt at 40C
2.5-5.0
Sediment %, by mass (max)
0.05
Sulphur content by mass (max.)
0.05%
Water content, % by volume, Max.
0.05
2.5.4Details of Machinery
Sugar Plant
Table – 2.8
Mill Section
S.No.
Description of Equipment
Qty.(in numbers)
1
Cane loader
2
2
Cane unloader
1
3
Feeder table
2
4
First cane carrier
1
5
Cane chopper
1
6
Cane leveller
1
7
Swing Hammer Fibrizer
1
8
Rake type carrier
1
9
Belt conveyor with tramp iron separator
1
10
Cane equalizer
1
11
Intermediate Rake carrier
3
12
Milling Plant
4
13
Mill house Crane
1
14
Belt Conveyor
1
15
Rake type bagasse elevator
1
Bhagavathi Ana Labs Ltd., Hyderabad.
3
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
16
Lubrication System
1
17
Juice Tray
1
18
Donnelly Chute
4
19
Pumps
4
20
Lubricants for Mill House Package
4
21
Rotary screen juice
1
Boiling House Machinery
Table – 2.9
S.No.
Particulars
1.
Raw juice
2
Juice heaters
3
Juice sulphitor
4
Sulphur burner
5
Air blowers
6
Milk of lime preparation
7
Juice clarifier
8
Vacuum filter
9
Evaporator Quintuple
10
Syrup sulphitor
11
Syrup & molasses storage tanks
12
Batch type vacuum pan
13
Crystallizers
14
Condensor and injection pump station
15
Sugar melter
16
Sugar drying
17
Mild steel fabricated vapour pipe
18
Insulation
Bhagavathi Ana Labs Ltd., Hyderabad.
4
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Power Generating Unit
(i)
Table – 2.10
One TG set of 27 MW rating will be used for the export of power
during season and off season.
(ii)
The TG set of 27 MW will be Extraction cum Condensing type
having Inlet steam pressure 110 ata& temperature 40
degCelcius with all its accessories.
Brief Technical Specification of Turbo Alternator
Particulars
Units
Value
Turbo generator
1
Type
Double Extrn cum
condensing
Rated output (continuous)
KW
27000
Steam pressure before
emergency stop valve
ata
108
Rated pressure at extraction
ata
2.5
Rated pressure at exhaust
ata
0.1
2.5.5 Efficiency Parameters
The plant and machinery shall be of proper design and capacity to have following efficiency
parameters: Preparatory Index- +85 %
 RME- +95 %
 Boiler efficiency- 71 %
 Steam Consumption- less than 42% on cane
 Reduced Boiling house efficiency- +80 %
 Recovery % cane- 10.5 to 12.5
Bhagavathi Ana Labs Ltd., Hyderabad.
5
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
2.5.6Employment
The employment requirement is estimated about 91 personnel. The list of employment is
given below the Table – 2.11.
Table -2.11
Manpower Requirement
Sugar Plant
Employment
Number of personnel
Managers
6
Mechanical Engineer
4
Sugar Technologies
4
Lab Assistance
4
Electrical Engineer
1
Electrical Supervisor
4
Cogeneration Plant
Manager
1
Instrumentation Engineer
1
Mechanical Engineer
4
Electrical Engineer
3
Instrumentation Technicians
4
Electrical supervisor
1
Fuel/ash handling supervisor
4
Working floor staff
50
TOTAL
91
2.6
Process Description
2.6.1 Sugar Plant
Brief Description Of Process To Manufacture White Sugar By Double Sulphitation
Process
The process of manufacturing involves the following steps:
i)
Extraction of cane juice from cane
ii)
Purification of cane juice
iii)
Evaporation of cane juice to facilitates crystallisation
Bhagavathi Ana Labs Ltd., Hyderabad.
6
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
iv)
Crystallisation of Sugar
v)
Separation of sugar and liquid by Centrifugal force
vi)
Re-Boiling of Liquid
vii)
Drying
Jamkhandi Sugars Limited
– Unit II
Brief Description Of The Above Process Steps Are Given Below:I.
Extraction of Cane Juice From Cane
The cane which is brought from fields by carts/trucks/tractors, weighed and unloaded in the
cane carrier for extraction of juice from sugarcane.
The unloaded cane will pass through preparatory devices (Chopper, leveller and fibrizer).
The preparatory devices will cut the cane stalks into pieces. The prepared cane enters mills
consist of multiple units of three roller combination through which the prepared cane.To aid
in the extraction of juice spraying thin juice from previous mills and water before last mill,
directed on the blanket of Bagasse as it emerges from each mill help to leach out the sugar.
Use of Bagasse
The residue that leaves the last mill is called bagasse contains un-extracted sugar, woody
fibre and water. The bagasse will be used as fuel to produce steam and power as cogeneration. The generated steam will be used to run turbines for power generation. The
outlet of the turbine i.e., low pressure steam will be used for mill juice processing. The
condensed water will be sent back to boiler for steam generation during off crushing season.
II.
Purification of Cane Juice – Clarification
The extracted juice from mills is strained to remove bagasse particles before sending for
process. This juice will be sent through a mass flow meter and the quantity automatically
recorded. The dark green juice from mills is acidic and turbid. The universal process
employed to remove both soluble and insoluble impurities is called Sulphitation process. The
juice will be heated up to 70C to 75C to avoid inversion. In sugar plant as a measure of
Bhagavathi Ana Labs Ltd., Hyderabad.
7
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
steam economy primary heating will be done by plate type heat exchanger using heat
energy available from the condensates of evaporators and pans.
Liming and Sulphitation
The process in whichmilk of lime(Ca(OH)2) is added to the juice simultaneously in juice
sulphiter, thereby pH of juice will be increased to 6.9 to 7.2.
CaO+H2O
Ca(OH)2 + Colour
The aim of this neutralization is to remove colourants from the juice, and to neutralize
organic acids. The formation of tri-calcium phosphate and sulphate, which are products on
sedimentation and carry impurities present in the liquid. Lime consumption (Cao) ranges
from 0.18 to 0.25 % on cane according to the treatment strength required.
The absorption of the SO2 gas (sulphurdioxide) by the juice takes place in juice sulphitor.The
SO2 gas is produced in the unit by burning sulphur in the presence of air, in special furnace
and the reaction is given below.
S+O2
SO2
The main objectives of Sulphitation are;

Sulphitation is the practice of adding sulphur dioxide (SO2) to process streams in a
sugar factory. This is done for one of three reasons :

1. pH control - the SO2 in aqueous solution forms sulphurous acid H2SO3(aq) which
reduces the pH of the process stream. An example of this would control of diffusion
water pH in a beet factory, where keeping the pH below 5.5 reduces the extraction of
pectin from the beet cell walls which helps pulp pressing.

2. Biocide - used in sufficient quantities the SO2 inhibits the life cycle of bacteria,
reducing the quantity of sugar lost by bacterial degradation to lactic acid. This is
similar to the use of sodium metabisulphite for sterilising home brewing equipment.
The efficiency of SO2 as a biocide is sometimes challenged in the literature.
Bhagavathi Ana Labs Ltd., Hyderabad.
8
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant

Jamkhandi Sugars Limited
– Unit II
3. Colour blocking - SO2 reacts with the carboxyl groups of invert sugars (glucose
and fructose) to inhibit their participation in the colour forming Maillard reaction with
amino compounds. By adding SO2 to juice before evaporation the increase in colour
through the evaporators is kept to a minimum, protecting the juice from excessive
colour formation at high temperature in the evaporators.

Decreasing the viscosity of the juice and consequently of the syrup, to reduce
viscosity and remove the colouring matters present in the juice. This ultimately
facilitates better evaporation and crystal development.
Average consumption of Sulphur can be estimated in between 0.05% to 0.06% on cane.
The sulphited juice is heated to approximately 101 to 1030C to accelerate and facilitate
the coagulation and flocculation of colloids and non –sugar proteins, emulsify fats and
waxes, or in other words accelerate the chemical process, increasing decanting
efficiency and also enabling removal of gas from the juice. The juice purification by
removing the flocculated impurities from the previous treatments. This process is carried
out continuously in equipment called a claifier. The clarified juice is removed from the
upper part of Solids Recycle Type Clarifiers (SRTC) and sent to the evaporation section
for concentration. The mud will be withdrawn from the bottom of the SRTC and sent to
rotary vacuum filter. In rotary vacuum filters, juice and filter cake will be separated by
vacuum. The cake that is discharged are applied to fields as fertilizer and in some
countries cane wax is extracted from this cake.
III.
Evaporation
The clarified juice obtained in the clarifiers constitutes 75% water. The first stage of
concentration is carried out in equipment called the evaporator, which operates
continuously. The evaporator consists of five bodies, connected in series so that the juice
undergoes progressive concentration from the first effect to the last effect to evaporate
75% of water which is present in the juice we require steam. Henceexhaust steam from
turbines at a pressure of 1.5 kg/cm2 at 133Cwill be fed to the effect of evaporator.
Subsequently due to the evaporation of the water in the first effect will yield the same
Bhagavathi Ana Labs Ltd., Hyderabad.
9
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
amount of vapour, which will be fed to the succeeding bodies. Due to the difference in the
pressure and the vacuum in the bodies the evaporation of juice will takes place in all the
evaporators. Initially clarified juice will have a brix of 14-160C, reaching 55-650C Brix from
the outlet of the V body. This syrup is passed through a tower consists of absorption of
the SO2 (Sulphurdioxide) by the syrup, lowering its original pH from 6.4 -6.8 to 4.6 -5.2.
The water vapour generated from 1st evaporator will be used in subsequent bodies and
the generated condensate will be utilised for cane juice extraction at mills, muddy juice
filtration at vacuum filters, milk of lime preparation, pan washing and centrifuge. The
excess condensate will be cooled and used for plant utilities and on land irrigation.
IV.Crystalisation
Crystallisation takes place in single effect vacuum pan. The syrup obtained from the
evaporator will be boiled until saturated with sugar. At this point „seed grain‟ is added to
serve as nuclei for the sugar crystals and more syrup is added as the water evaporates.
Continuing the above process the pans are filled up till the desire size crystals are built up
and dropped in mixers called crystallisers. The sugar and syrup forms a dense mass
known as Massecuite.
V. Separation of sugar and liquid by centrifugal force
From the crystallizers, the massecuite will be cured in the centrifugal machines . In
centrifugals the sugar and molasses will be separated.
In centrifugals there are two types of machines
I.
Continuous centrifugal Machines
II.
Batch Type centrifugal machine
The continuous centrifugal machines will be used for low grade massecuites like B and C
Massecuites. The separated molasses will be taken back to the process for extracting the
dissolved sugar which is present in molasses. The separated sugar having low purity is
made as a magma minglers and it will be melted in the sugar melter and will be taken
back to the A massecuite boiling.High grade massecuite i.e., A- Massecuite will be cured
Bhagavathi Ana Labs Ltd., Hyderabad.
10
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
in the batchtype centrifugals . The sugar discharged from the batch centrifugal has a high
moisture level with temperature of around 60 to 65 degree centigrade.
VI. Re-boiling of Liquid
The aim of sugar boiling is to recover more sugar and send less purity of molasses ( Final
Molasses) as by product.
„A‟ Massecuite
From Syrup and second grade used as „seed‟ nuclei and high purity washings from high
grade sugar (AL Molasses) high grade or „A‟ Massecuite is boiled. From this A‟
Massecuite we get white sugar, A‟ Heavy Molasses and AL molasses. This AL light
molasses will be sent back for A‟ Massecuite boiling. The AH molasses is being sent for
„A‟ Massecuite boiling. The AH molasses is being sent for „B‟ Massecuite
„B‟ Massecuite
The AH Molasses is taken in to batch pan and boil till the super saturation stage. At this
point „seed slurry‟ is added to serve as nuclei for the sugar crystals. Continuing the boiling
by feeding AH till the crystals size reaches to 160 to 180 µm. The grain will be transferred
to vacuum crystallisers, futher boiling takes place in continuous vacuum pans. The
continuous pan outlet massecuite size will be 250 to 300 microns .The „B‟ grade
Massecuite separation we will get B seed and B heavy molasses. The part of B seed will
be sent for A graining and balance for melting. B heavy molasses sent for „C‟ Boiling.
„C‟ Massecuite or Low Grade Massecuite
As this is the important massecuite from which mother liquor goes out as Final Molasses
must be of low purity. Hence, more number of small crystals must be present to have
larger area to deposit or de-sugar the mother liquor. Here the crystals are smallest to
achieve our aim.
Graining is done using „C‟ light and AH molasses in batch pan and boiled till the super
saturation stage. At this point seed slurry of 3 to 4 microns is added to serve as nuclei for
the sugar crystals. Continuing the boiling by feeding C light and BH molasses till the
crystals size reaches to 70 to 90 microns. The grain will be transferred to C vacuum
Bhagavathi Ana Labs Ltd., Hyderabad.
11
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
crystalliser. Further boiling takes place in continuous pans by feeding BH molasses. The
crystals size of pan outlet is 150 to 180 microns. The massecuite dropped to Mono
Vertical crystalliser for cooling . During cooling of the massecuite the temperature bring
down to 42 to 43 degree centigrade to achieve maximum sugar recovery. The cooled
massecuite fed to continuous centrifugals for separation. The separated mother liquor
termed Final Molasses will sent to distillery industry. The sugar separated from first curing
is mixed with water and sent for second curing. During second curing we will get C seed
and C light molasses. C seed will be sent for „A‟ Boiling and C light molasses sent for C
boiling.
VII. Drying
The separated sugar from „A‟ centrifugals cooling and drying of the sugar is carried out in a
multi tray hopper, in the hopper the cold and hot air will be pass in co-current direction to
bring down the moisture and temperature of the marketable sugar.
From the drier, the sugar passes through grader where the separation of sugar of various
grades depending on the size and colour like: L-30, M-30, S-30 and SS-31 will takes
place. The graded sugar will be collected in bins. The sugar from the bins will be weighed
in automatic weighing scale, stitched and will be sent to the sugar godown. Sugar is stored
in 50 kg PP bags and 100kg “A” twill gunny bags in sugar godown.
2.7 Cogeneration Power Plant
JSL proposes to implement the Cogeneration of 27 MW power plant by installation of 120
TPH boiler of 110 ata pressure and 540C temperature and single T.G. set of 27 MW
extraction cum condensing. The scheme of Co-generation is designed to operate plant at the
rated capacity of 3500 TCD (160 TCH).
2.7.1 Selection of Pressure and Temperature for the proposed Cogeneration Power
Cycle
While going for Sugar Unit of 3500 TCD, the factory has proposed 110 ata and 540C Boiler
of 120 TPH.The adaptation of pressure and temperature are very suitable for obtaining the
maximum power generation for proved technology available for bagasse based
cogeneration. Therefore, while implementation of the cogeneration project; the parameters
Bhagavathi Ana Labs Ltd., Hyderabad.
12
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
adopted shall be based on minimum 110 ata pressure and 540Ctemperature of the boilers.
Further, various parameters viz. optimum cycle efficiency, metallurgy of pressure parts,
standard range of turbine, operability, maintainability and working performance of similar
bagasse based cogeneration plants recently commissioned have been taken into account
2.7.2 Design Parameters for the proposed Cogeneration Plant
Following design parameters for the Expansion project will be taken into account: Actual crushing capacity of Sugar Plant will be 160 TCH on 22 hrs, basis (3840
TCD /24 hrs.)
 Average production of bagasse will be 29.5 % on cane.
 Bagasse used for vacuum filter will be 0.6 % on cane and reserved for start-up to
stoppages and wind age losses will be o.2 % on cane. Thus, the bagasse
available for the steam generation will be 28.27 %
 The gross season will be of 180 days
 Captive power consumption for the sugar unit is 24 KW/TCH ie 3840 KW
 Captive steam consumption:

Sugar factory process (2.5 ata) :44 % on cane

Sugar factory misc. (8.0 ata) :1 % on cane
 Captive power consumption:
 Boiler of 120 TPH and 110 ata pressure and matching TG set of 27 MW will be
used as captive power for Sugar Plant
 Surplus power will be exported during season (180 days) and during off season
(80 days) to KSEDCL grid of 110 KV level at Almal sub station located at 8 km
away from the cogeneration plant.
 GCV of mill wet bagasse: 220 kcal /kg
 Thermal efficiency of boiler on GCV of bagasse: 71 %
 Steam to bagasse ratio (120 TPH , 110 ata boiler) : 2.61
 Actual steam rating (ASR ):27 MW , DEC T.G. Set (110 ata pr.)

@20.11 ata extraction :8.5 kg/KWH

@8.0 ata extraction:6.5 kg/KWH

@2.5 ata extraction:5.3 Kg/KWH

@0.1 ata condensing stage:3.4 kg/KWH
Bhagavathi Ana Labs Ltd., Hyderabad.
13
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
2.7.3 Operation of the Cogeneration Plant during Crushing Season
The 120 TPH , 110 ata boiler with matching 27 MW condensing & extraction TG set will work
to cater the demand for process steam and power of sugar unit and power for auxiliary units
of Cogeneration plant and balance power will be exported to the state grid.
The steam balance, Bagasse balance and Power balance during the season operation of the
Cogeneration Plant are described as below
i)Steam Balance
120 TPH, 110 ata boiler
Steam generated from 120 TPH, 110 ata boiler are 106.4 TPH and is passed through 27 MW
Extraction and condensing TG set from which , 8.4 TPH is extracted at 20.11 ata& used for
ejector and HP Heater -2 , 8.0 TPH is extracted at 8.4 ata& used for sugar processing and
HP Heater 1, 75.0 TPH is extracted at 3.0 ata and after desuper heating it is used for sugar
processing and Deaerator and balance 15.00 TPH is led to condensing stage thus totalling
10.4 TPH steam.
Steam Consumption
*at 20.11 ata (Extracted steam 8.40 TPH)
Ejector
:
0.40 TPH
HP Heater 2 :8.00 TPH
TOTAL :
8.40 TPH
The steam consumption at 20.11 ata is 8.40 TPH.
*AT 8.4 ata (extracted steam 8.0 tph)
SF Process : 1.0 TPH
HP Heater
: 1 .50 TPH
TOTAL
: 8.10 TPH
Considering Desuper water of 0.1 TPH , the steam consumption is 8.0 TPH.
*AT 2.5 ATA (Extracted steam 75.00 TPH )
Bhagavathi Ana Labs Ltd., Hyderabad.
14
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
SF Process :70.40 TPH
Deaerator:5.10 TPH
Total
:75.60 TPH
Considering Desuper water of 0.6 TPH , the steam consumption is 75.0 TPH
*at 0.075 ata condensing stage (15.00 TPH)
The 15.00 TPH steam is passed to the condensing stage of 27 MW EC TG set.
It is to be noted that steam demand at 2.5 ata level for SF process is met through the steam
extracted from 27 MW EC TG set 70.4 TPH ) thus totalling 70.4 TPH which comes to be
44.0 % on cane.
Similarly steam demand at 8.0 ata level for SF misc. is met through the steam extracted at
8.4 ata after desuper (1.6 TPH ) which comes to be about 1.00 % on cane.
Bagasse Balance
 Bagasse production (29.50 % cane ) :47.20 TPH
 Bagasse used for vacuum filter and
Reserved for start up& stoppages(0.625% cane ) : 1.00 tph
 Bagasse available for boilers:46.20 TPH
 Bagasse utilization:120 TPH , 110 ata boiler having 106.4 TPH load
(@steam to bagasse ratio having 2.61 ) :40.77 TPH
 Saved bagasse :4.20-40.77
=5.43 TPH (3.33% cane)
Thus, the total bagasse saved will be about 21, 110 tonnes during the season which will be
used for operating the cogeneration plant in off- season.
Similarly, 3100 tonnes of trash farm will be collected and burnt in the boiler during season
and about same amount of bagasse will be saved.
Power Balance
 Power generation: from 27 MW EC TG set
 8.40 TPH stem at 20.11 ata extraction @8.5kg /KWH :988 KW
Bhagavathi Ana Labs Ltd., Hyderabad.
15
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
 8.00 TPH stem at 8.0 ata extraction @6.5 kg /KWH:1230 KW
 75.00 TPH Stem at 2.5 ata extraction @5.3 kg/KWH:14151KW
 15.00 TPH stem at 0.07 ata exhaust @ 3. 4 Kg/KWH:4411 KW
TOTAL :20780 KW
Thus the total power generation from TG sets 27 MW will be 20780 KW.
Captive power consumption
 Sugar factory(24.0 KW /TCH)
:3840 KW
 Work shop(season –off season)
:25 KW
 Office lighting & Colony
:50 KW
 ETP (Season off season )
:50 KW
 120 TPH , 110 ata boiler and auxiliaries :2275 KW
TOTAL :6240 KW
Thus the total captive power consumption will be 6240 KW.
Power export
 Total power generation:20780 KW
 Total power consumption :6240 KW
 Surplus exportable power :14540 KW
 Power export in season:.56.53 MWH
 Thus the Cogeneration plant will export the power of 1540 KW amounting to 56.53 Million
units during the season.
2.7.4 Operation of the Cogeneration Plant during Off season
Operation of the Cogeneration plant during off season has been shown in the Steam &
Power Cycle.
Only 120 TPH, 110 ata boiler with matching 27 MW ECTG set will be in operation.
The Steam balance, bagasse balance and power balance during off season operation of the
Cogeneration plant are outlined as below:i)Steam Balance
Steam generated from 120 TPH, 110 ata boiler is 88.15 TPH and is passed through 27 MW
ECTG set from which , 7.15 TPH is extracted at 20.11 ata& used for ejector and HP Heater Bhagavathi Ana Labs Ltd., Hyderabad.
16
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
2 , 4.80 TPH is extracted at 8.4 ata& used for HP Heater -1 , 7.20TPH is extracted at 3.0 ata
and after desuper heating it used for Deaerator and balance 69.00 TPH is led to condensing
stage thus totalling 88.15 TPH steam.
Steam Consumption
*at 20.11 ata (Extracted steam 7.15 TPH)
Ejector : 0.40 TPH
HP Heater:6.75 TPH
TOTAL:
7.15 TPH
The steam consumption at 20.11 ata is 7.15 TPH.
*at 8.4 ata (Extracted steam 4.8 TPH )
SF Process :0.00tph
HP Heater -1: 4.80 TPH
TOTAL: 4.80 TPH
The steam consumption is 4.80 TPH.
* at 3.0 ATA (Extracted steam 7.2 TPH )

SF PROCESS :0.00 TPH

Deaerator:7.20 TPH
TOTAL:7.20 TPH
Considering Desuper water of 0.0 TPH , the steam consumption is 7.20 TPH.
*at 0.1 ata condensing stage (69.00 TPH)
The 69.45 TPH steam is passed to the condensing stage of 27 MW EC TG set.
ii)Bagasse balance
 Available bagasse saved in season and procured from JSL –I :64910 T
 Bagasse used for 120 TPH , 110 ata boiler:33.77 TPH
having 88.15 TPH load @steam to bagasse ratio of 2.61
Bhagavathi Ana Labs Ltd., Hyderabad.
17
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
 Operational days: 80 days
Thus the Cogeneration plant will be in operation for 80 days during the off season
period.
iii)Power Balance
*From 27 MW EC TG set
 7.15 TPH steam at 20.11 ata extraction @8.5 kg /KWH: 840 KW
 4.80 TPH steam at 8.0 Extraction @6.5 kg/KWH:
738 KW
 7.20 TPH steam at 2.5 ata extraction @.3 kg/KWH :
358 KW
 69.00 TPH steam at 0.75 ata exhaust @3.3 kg/KWH :
20904 KW
TOTAL:
23840 KW
Thus, the total power generation from 27 MW EC TG set will be 23840 KW.
*Captive power consumption:
 Cogeneration & auxiliary (Boiler and TG set) :2340 KW
 Workshop:
 Office and Lighting:
 ETP:
TOTAL:
25 KW
25 KW
50 KW
2440 KW
Thus, the total captive power consumption will be 2440 KW.
*Power Export
 Total power generation:23840 KW
 Total power consumption:2440 KW
 Surplus exportable power:21,400KW
 Power export in off season:36.97 M KWH
Thus, the cogeneration plant will export the power of 21400 KW amounting to 36.97 Million
units during the off season.
Bhagavathi Ana Labs Ltd., Hyderabad.
18
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
2.8 Air Conditioning System
 The main plant control room housing the controls for boiler, TG Sets and balance of
plant accessories shall be air conditioned with ductable package air conditions which
will be located in an AC room.
 The condensers shall be located above the plant ac rooms.
 A temperature shall b maintained at 22 degCelsius with relative humidity of 55In the
AC room
 Compressor shall be hermetically sealed ,condensors shall be air cooled type.
 Refrigeration piping shall be of hard copper pipe of minimum 10 SWG thickness
 Thermal insulation of ducting shall be 25 mm thick aluminium foil faced glass wool.
2.9 Ventilation System
This consists of positive supply ventilation system and exhaust ventilation system.Positive
supply ventilation system is required for the area of 11 KV switch gear room, MCC rooms
etc. which needs positive pressure to avoid outside air infiltration which is to be achieved by
continuous fresh air supply. Two centrifugal fans of each 0 % capacity to supply air shall be
provided. These fans shall draw air through a bank of coarse filters and then through a bank
of 10 microns filters. Separate branches for each area shall be supplied.
Exhaust ventilation system is required for the area of compressors room , cable gallery , TG
Hall , battery room. Exhaust fans shall be installed in these areas.
2.10 Fire Protection System
The fire protection system shall comprise of: Hydrant system for all areas in the plant
 High velocity water spray system for transformer
 Automatic fire detection and alarm system
 Portable fire extinguishers
Bhagavathi Ana Labs Ltd., Hyderabad.
19
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
2.11
Jamkhandi Sugars Limited
– Unit II
Raw Water system
The raw water will be stored for the Cogeneration Plant is 31.10 MCFT in Season and 16.37
MCFT in Off season.
2.12
Health and Sanitation Facilities
To ensure optimum hygienic conditions in the plant area, proper drainage network will be
provided to avoid water logging and outflow. Adequate health related measures and a well
be equipped Safety and Environment Cell will be established as a part of Environmental
Management Plan.
Bhagavathi Ana Labs Ltd., Hyderabad.
20
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Chapter –3
Description of the Environment
3.0
Introduction
Baseline environmental status in and around enhanced project depicts the existing
environmental conditions of air, noise, water, and soil, biological and socio-economic
environment. With this project as the centre, a radial distance of 10 km is considered as
‘study area’ for baseline data collection and environmental monitoring. Baseline data was
collected for various environmental attributes so as to compute the impacts that are likely to
arise due to proposed developmental activity.
The main aim of the impact assessment study is to find out the impact of the project on the
environment. This study is carried out during the project planning stage itself, so that the
proponent can implement the project in a technically, financially and environmentally viable
way.
Existing environmental conditions are enumerated by collecting baseline data. The
estimated impact due to the enhanced project is superimposed over the existing conditions
to arrive at the post project scenario. The scope of the baseline studies includes detailed
characterization of various environmental components, which are most likely to be
influenced by setting up an industry.
 Meteorological conditions
 Ambient Air Quality
 Noise Levels
 Water Quality (Surface and Ground water)
 Soil Quality
 Socio Economic studies and
 Land use
The baseline data generation for the EIA was carried out during the study period post–
monsoon season 2012 (October–November). The data is generated with respect to
meteorological conditions, air pollution levels, noise levels, water quality, soil quality and
socio economic conditions were carried out during the study period.Secondary
Bhagavathi Ana Labs Ltd., Hyderabad.
21
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
meteorological data collected for reference from the nearest IMD station Bijapurat a distance
of 35 km
3.1
Meteorology
The study of meteorological conditions forms an intrinsic part of the environment impact
assessment study. The meteorological conditions of an area and the industrial process are
both intertwined and each has a definite influence over the other.
Regional meteorological scenario helps to understand the trends of the climatic factors. It
also helps in determining the sampling stations in predicting the post project environmental
scenario. Meteorological Scenario exerts a critical influence on Air Quality as the pollution
arises from the interaction of atmospheric contaminants with adverse meteorological
conditions such as temperature inversions. Atmospheric stability and topographical features
like hills, canyons and valleys.
The critical weather elements that influence air pollution are wind speed, wind direction,
temperature, which together determines atmosphere stability. Hence it is an indispensable
part of any air pollution studies and required for interpretation of base line information.
An automatic weather station was installed in the plant area to study the meteorological
conditions of the study area. It was placed at a height of about 10 m above the ground level
ensuring that there is no obstruction to the free flow of wind. Apart from the wind speed and
direction, temperature, relative humidity and rainfall were also measured.
On site monitoring was undertaken for various meteorological variables in order to generate
site-specific data. Hourly average, maximum and minimum values of wind speed, direction,
relative humidity and temperature were recorded continuously for the study period. The
meteorological data recorded and used for interpretation of the baseline information as well
as for prediction analysis.
Hourly wind speed and direction recorded during the study period to identify the influence of
meteorology on the air quality of the area. Wind rose on sixteen - sector basis i.e., N, NNE,
NE, ENE, E, ESE, SE, SSE, S, SSW, SW, WSW, W, WNW, NW and NNW is prepared.
During the study period the maximum and minimum temperature, relative humidity and
rainfall recorded and wind speeds and pre dominant wind directions observed are given in
Table – 3.1.
Bhagavathi Ana Labs Ltd., Hyderabad.
22
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Table -3.1
Observed Meteorological Data
Period
2012
Temperature
(oC)
Relative
Humidity (%)
Min
Min
Max
Max
October
14.4
32
21
100
November
9.4
31
26
100
Wind Pattern
Direction
ENE
Average
Wind Speed (m/s)
1.2
The frequency of occurrence of wind in various speed categories was calculated on the
basis of total number of observations recorded. The average 24 hour wind rose diagram
during October-November 2012 reveals that the predominant wind direction during the study
period is from East of North-East (ENE). The wind pattern during 00 to 23 hours is shown in
Figure-3.1.
Figure–3.0: Windrose Diagram for Post Monsoon 2012 (October & November)
3.2 Ambient Air Quality
The baseline status of the ambient air quality was assessed through a scientifically designed
ambient air quality network. The design of monitoring network in the air quality surveillance
program is based on the following considerations:

Meteorological parameters
Bhagavathi Ana Labs Ltd., Hyderabad.
23
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II

Major human settlements

Topography of the study area

Representatives of regional background air quality for obtaining baseline status

Representatives of likely impact areas
Ambient Air Quality Monitoring (AAQM) stations were set up at 8 locations with due
consideration to the above mentioned points. AAQ locations were selected in upwind,
downwind, and cross wind directionswith reference to the project site. Ambient Air Quality
Monitoring stations Location map is shown in Figure-3.1.The details of the monitoring
stations are given in Table -3.2.
At each sampling station monitoring was carried for a frequency of twice a week for 4 weeks
in a month during study period. The air pollutants are suspended particulate matter (SPM),
fine particulate matter (PM10& PM2.5),Sulphur dioxide (SO2),Oxides of Nitrogen (NOx),
Carbon Monoxide (CO), Mercury (Hg) and Ozone (O3) were monitored,analysed and
compared with the NAAQ standards stipulated by CPCB.
Table–3.2
Ambient Air Quality Monitoring Stations
Station Name of the Station Direction w.r.t. Distance
Wind Pattern
Code
plant site
w.r.t.
plant w.r.t. wind rose
site
A1
Plant site
-0.0
-A2
Nad KD
2.7
WSW
Downwind
A3
Golsara
3.6
N
Crosswind
A4
Hanchina
4.0
ENE
Upwind
A5
Arjunagi
4.0
E
Crosswind
A6
Marsanahalli
4.5
SE
Crosswind
A7
Vibuthihalli
5.0
ESE
Crosswind
A8
Shrisara
5.2
SSW
Crosswind
3.2.1
Analysis of baseline concentrations
The monitored levels of air pollutants are presented in Table-3.3. Various statistical
parameters like minimum, maximum, Average, Standard deviation and 98 percentiles have
been computed from the observed raw data for all sampling stations and the details are
provided in Annexure–II. These are compared with the NAAQ standards prescribed by
Central Pollution Control Board (CPCB).
Bhagavathi Ana Labs Ltd., Hyderabad.
24
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Table -3.3
Ambient Air Quality in the Study Area (All values are in g/m3)
Air Quality
Station
Plant site
Nad KD
Code Particulars SPM PM10 PM2.5 SO2
A1
A2
Golsara
A3
Hanchina
Arjunagi
A4
A5
Marsanahalli
A6
Vibuthihalli
A7
Shrisara
A8
3.2.2
Minimum
Maximum
Minimum
Maximum
Minimum
Maximum
Minimum
Maximum
Minimum
Maximum
Minimum
Maximum
Minimum
Maximum
Minimum
Maximum
101
112
103
113
106
116
109
121
110
118
108
119
107
117
111
121
30.3
33.6
30.9
33.9
31.8
34.8
32.7
36.3
33.0
35.4
32.4
35.7
32.1
35.1
33.3
36.3
8.0
9.5
8.1
9.7
8.3
9.9
8.9
10.4
8.8
10.3
8.8
12.0
8.7
10.2
8.7
10.3
7.5
8.3
7.6
8.4
7.8
8.5
8.0
8.8
8.1
8.7
7.9
8.7
7.9
8.6
8.1
8.8
NOx
9.1
10.0
9.2
10.1
9.4
10.3
9.6
10.6
9.7
10.4
9.6
10.5
9.5
10.4
9.8
10.6
CO
Hg
mg/m3 ng/m3
1.11
NT
1.21
NT
1.01
NT
1.24
NT
1.10
NT
1.24
NT
1.09
NT
1.20
NT
1.08
NT
1.21
NT
1.11
NT
1.21
NT
1.02
NT
1.21
NT
1.04
NT
1.19
NT
O3
20.0
23.1
20.0
22.6
20
23.1
21.0
24.1
21.0
24.5
21
23.1
21
23.1
21
23.5
Regional Scenario
The results obtained are processed for finding out the percentiles, minimum, and maximum.
Close observation of the processed values reveals the following:
Particulate Matter
Particulate Matter or dust in general terms is the particulate matter in suspension in ambient
air. It includes dust, smoke, carbonaceous matter, trace metals like lead, cadmium, mercury,
etc.
Sources:
The following sources of suspended particulate matter in the study area are identified:
 Emissions due to vehicular movement,
Bhagavathi Ana Labs Ltd., Hyderabad.
25
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
 Air born dust generation from ground and
 Fire wood, garbage and garden waste burning.
Particulate Matter Levels in the study area:
The minimum level of SPM recorded in the study area was 101 µg/m3 at project siteand the
maximum level recorded was 121 µg/m3 at Shrisara.
The minimum level of PM10 recorded in the study area was 30.3 µg/m3 at project siteand the
maximum level recorded was 36.3 µg/m3 at Hanchina&Shrisara.
The minimum level of PM2.5 recorded in the study area was 8.0µg/m3 at project siteand the
maximum level recorded was 12.0µg/m3 at Mavanahalli.
Sulphur Dioxide levels
Sulphur dioxide gas is an inorganic gaseous pollutant. Sulphur dioxide emissions are
expected to emit wherever combustion of any fuel containing elemental sulphur takes place.
The sulphur in the fuel will combine with oxygen to form sulphur dioxide. Sulphur trioxide and
sulphuric acid mist are the other important pollutants in the sulphur group.
Sources:
In general some of the important sources of sulphur dioxide are from nearby industries and
domestic use of fuel. The following sources of Sulphur dioxide in the study area are
identified:

Emissions from domestic burning of fuel (wood, kerosene, etc.)

Emissions from nearby transportation of vehicles.
SO2 Levels in the study area:
The minimum level of SO2 recorded in the study area was 7.5 µg/m3 at Plant siteand the
maximum level recorded was 8.8 µg/m3 at Shrisara&Hanchina.
Bhagavathi Ana Labs Ltd., Hyderabad.
26
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Oxides of Nitrogen
Like Sulphur dioxide, oxides of nitrogen are also an inorganic gaseous pollutant. Oxides of
nitrogen are expected to emit wherever combustion at high temperatures takes place.
Nitrous oxide and nitric acid mist are the other important pollutants in the inorganic nitrogen
group.
Sources:
In general some of the important sources of oxides of nitrogen are acid manufacture, Boilers
in utilities in any industry and Auto exhaust.
The following sources of oxides of nitrogen in the study area are identified:
 Emissions from domestic burning of fuels.
 Emissions from automobiles.
NOx Levels in the study area:
The minimum level of NOx recorded in the study area was 9.1 µg/m3 at project siteand the
maximum level recorded was 10.6 µg/m3 at Shrisara.
HC and COLevels in the study area:
Sources
 Emissions from domestic burning of fuels, & wood.
 Emissions from automobiles.
HC values in the study area were found to be less <0.1 ppm at all locations.
CO values in the study area were in the range of 1.01 to 1.21 mg/m3.
Ozone (O3)
Ozone values in the study area were in the range of 20 – 24.5 µg/m3.
The air quality contours along with wind rose diagram for SPM, PM10, PM2.5, SO2 and NOx
are shown in Figures – 3.1a, 3.1b, 3.1c, 3.1d, & 3.1e respectively.
Bhagavathi Ana Labs Ltd., Hyderabad.
27
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
3.5
Jamkhandi Sugars Limited
– Unit II
Noise Environment
The impact of industrial noise on surrounding community depends on
 Characteristics of noise sources (instantaneous or continuous in nature). It is well
known that a steady noise is not as annoying as one that is continuously varying in
loudness.
 Time of the day at which noise occurs, for example loud noises at night in residential
areas are not acceptable because of sleep disturbance.
 The location of noise source with respect to noise sensitive areas determines the
loudness and period of noise exposure.
Thebaseline data survey for noise levels in the study area has been carried out by selecting
8 noise-monitoring locations. The noise quality monitoring locations are shown in table below
and are shown in the topographical map Figure-3.2.
Table –3.4
Noise Monitoring Locations
Direction w.r.t
Location Name
plant site
S. No.
Location Code
1
N1
Plant site
2
N2
3
Distance w.r.t.
plant site in km
0.0
--
Nad KD
WSW
2.7
N3
Golsara
N
3.6
4
N4
Hanchina
ENE
4.0
5
N5
Arjunagi
E
4.0
6
N6
Marsanahalli
SE
4.5
7
N7
Vibuthihalli
ESE
5.0
8
N8
Shrisara
SSW
5.2
Bhagavathi Ana Labs Ltd., Hyderabad.
28
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Time
Table – 3.5
Noise Levels dB (A)
N4
N5
N1
N2
N3
6:00
41.30
41.20
40.90
40.10
7:00
40.60
40.90
41.10
8:00
41.90
42.50
9:00
45.50
10:00
Jamkhandi Sugars Limited
– Unit II
N8
N6
N7
40.50
40.40
40.70
44.10
41.40
41.70
41.90
42.40
45.80
40.90
42.70
43.30
42.90
43.10
46.50
45.60
44.30
44.40
44.50
44.60
44.80
48.20
47.90
47.50
46.70
47.50
47.10
46.30
46.70
50.10
11:00
50.50
50.70
49.30
49.50
49.70
49.90
50.30
50.70
12:00
50.90
50.50
49.70
50.10
49.70
49.70
49.30
52.30
13:00
51.10
50.50
49.90
50.50
49.90
49.30
49.30
51.60
14:00
50.50
50.90
49.30
50.90
51.30
49.70
51.70
49.80
15:00
49.30
49.70
48.10
48.50
48.90
49.30
50.10
48.60
16:00
50.20
54.80
52.20
52.20
52.40
52.40
51.80
51.60
17:00
51.10
56.40
52.20
52.70
49.50
49.80
50.30
50.50
18:00
51.70
52.40
50.50
51.90
51.20
51.20
51.90
48.60
19:00
47.50
47.10
46.30
46.70
46.30
46.30
45.90
49.30
20:00
43.30
43.60
42.10
42.40
42.70
43.00
43.60
47.00
21:00
43.10
43.20
41.90
42.00
42.10
42.20
42.40
45.80
22:00
42.80
43.40
41.60
42.20
42.80
43.40
44.60
44.00
23:00
42.60
42.40
41.40
42.40
42.20
41.20
42.00
42.50
0:00
42.30
42.80
41.10
43.30
43.80
43.80
44.30
40.50
1:00
42.10
41.80
40.90
41.80
41.50
40.60
41.20
42.60
2:00
42.00
41.50
40.80
41.00
40.50
40.50
40.00
42.60
3:00
42.20
41.60
41.00
42.00
41.40
40.80
41.20
42.70
4:00
42.00
42.60
40.80
43.20
43.80
43.80
44.40
44.50
5:00
42.10
42.50
40.90
42.90
43.30
43.30
43.70
44.20
Max
40.6
51.7
40.9
56.4
40.8
52.2
40.1
52.7
40.5
52.4
40.4
52.4
40.0
51.9
40.5
52.3
Ld
49.7
54.2
50.3
50.6
50.2
50.2
50.1
50.2
Ln
41.2
41.4
40.1
41.8
42.3
42.3
42.8
43.0
Min
3.5.1
Study area Scenario
The minimum noise level during day time Ld 49.7 dB (A) at project site and maximum Ld was
recorded 54.2 dB(A) at NAD KD while the minimum noise level during night time Ln 40.10
dB(A) at Golsaraand maximum Ln43.0 dB (A) was recorded at Shrisara.
Bhagavathi Ana Labs Ltd., Hyderabad.
29
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
3.6
Jamkhandi Sugars Limited
– Unit II
Water Environment
The water quality parameters as per IS: 10500 for water resources within 10 km of the study
area have been used for describing the water environment and assessing the impacts on it.
Based on the water sources in the project area sixground water samples, plant water andsix
surface water samples were collected and analyzed. The details of the locations and
distances from the study area shown in topographical map, in Figure 3.3.
Surface water sampling was carried out inBhimariver (upstream and downstream), Sattanal
river and Doddanalla present in the study area. The Surface water Sampling locations are
given Table 3.6 and the Characteristics of Surface Water are given in Table-3.8.
Location
Code
SW1
SW2
SW3
SW4
Table -3.6
Surface Water Quality Sampling Locations
Sampling Station
Distance w.r.t. Remarks
plant site in km
10.0
Surface
Bhima River Upstream
water(river)
Bhima RiverDownstream
8.5
Surface
water(river)
Sattanal river
3.0
Surface
water(river)
DoddaNalla
4.0
Surface
water(stream)
Table – 3.7
Ground Water Quality Sampling Locations
Location Sampling Station
Distance w.r.t.
Code
site in km
GW1
Project site
0.0
GW2
Mavanahalli
4.5
GW3
Vibuthihalli
5.0
GW4
Hanchina
4.0
GW5
Arjunagi
4.0
GW6
Shrisara
5.2
GW7
Nad KD
2.7
GW8
Golsara
3.6
Bhagavathi Ana Labs Ltd., Hyderabad.
plant
30
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Table–3.8
Surface water Quality Data
S.No.
Parameters
Bhima River
Upstream
Bhima River
Downstream
Sattanal river
DoddaNalla
I.
1.
2.
Essential Characteristics
Colour (Hazen Units)
Odour
<5
<5
<5
<5
Un - Objectionable
Un - Objectionable
Un - Objectionable
3.
4.
5.
6.
7.
Taste
Turbidity, NTU
Dissolved Oxygen, mg/l
pH
Total Hardness as CaCO3,
mg/l
Iron as Fe, mg/l
Chlorides as Cl, mg/l
Residual free, Chlorine,
mg/l
Desirable Characteristics
Total Dissolved Solids,
mg/l
Calcium as Ca, mg/l
Magnesium as Mg, mg/l
Copper as Cu, mg/l
Manganese as Mn, mg/l
Sulphate as SO4, mg/l
Nitrate as NO3, mg/l
Fluoride as F, mg/l
Phenolic Compounds as
C6H5OH, mg/l
Mercury as Hg, mg/l
Cadmium as Cd, mg/l
Selenium as Se, mg/l
Arsenic as As, mg/l
Cyanide as CN, mg/l
Lead as Pb , mg/l
Zinc as Zn, mg/l
Anionic
detergents
as
MBAS, mg/l
+
Chromium as Cr6 , mg/l
Mineral Oil, mg/l
Alkalinity CaCO3, mg/l
Aluminium as Al, mg/l
Boron as B, mg/l
Total Coliform, MPN/100
ml
Agreeable
2
5.2
7.79
166
Agreeable
4
5.1
7.56
136
Agreeable
4
5.2
7.76
142
Agreeable
3
5.1
7.70
153
0.18
130
Nil
0.52
145
Nil
0.38
134
Nil
0.40
130
Nil
910
893
900
892
59
16
<0.01
<0.01
255
17
0.31
<0.001
52
18
<0.01
<0.01
339
26
0.34
<0.001
55
17
<0.01
<0.01
278
14
0.41
<0.001
56
15
<0.01
<0.01
298
20
0.37
<0.001
<0.001
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.02
<0.001
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.02
<0.001
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.02
<0.001
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.02
<0.01
Absent
185
<0.01
<0.1
820
<0.01
Absent
250
<0.01
<0.1
760
<0.01
Absent
192
<0.01
<0.1
628
<0.01
Absent
220
<0.01
<0.1
679
8.
9.
10
II.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
Un
Objectionable
Bhagavathi Ana Labs Ltd., Hyderabad.
-
31
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
Table – 3.9
Ground Water Quality Data
S.No.
Parameters
I.
1.
2.
site
Essential Characteristics
Colour
(Hazen < 5
Un
Units)
Odour
3.
Results Obtained
Project
Mavanahalli
Vibuthihalli
<5
<5
–
Shrisada
Nad KD
Golsara
<5
<5
<5
<5
<5
Un - Objectionable
Un
Objectionabl
e
Un
–
Objectionable
Un - Objectionable
Un
Objectionable
Agreeable
Agreeable
Agreeable
Agreeable
Un
Objectionable
Taste
Agreeable
Agreeable
Agreeable
Agreeable
4.
Turbidity, NTU
<1
<1
<1
<1
2
<1
<1
<1
5.
pH
7.85
7.86
7.78
7.76
8.22
7.92
7.76
7.54
6.
Total Hardness as
CaCO3, mg/l
Iron as Fe, mg/l
230
380
555
255
195
350
700
1050
0.06
0.08
0.07
0.08
0.10
0.07
0.08
0.08
Chlorides as Cl, 20
Residual
free, Nil
mg/l
Chlorine, mg/l
Desirable Characteristics
98
Nil
240
Nil
55
Nil
55
Nil
168
Nil
260
Nil
420
Nil
Dissolved
Solids,
mg/l
Calcium as Ca,
mg/l
Magnesium as Mg,
mg/l
Copper as Cu, mg/l
520
670
1560
74
52
975
1288
2080
54
102
80
17
16
98
168
212
23
30
86
0.50
0.50
26
68
126
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
Manganese as Mn,
mg/l
Sulphate as SO4,
mg/l
Nitrate as NO3, mg/l
Fluoride as F, mg/l
Phenolic
Compounds
as
C6H5OH, mg/l
Mercury as Hg,
mg/l
Cadmium as Cd,
mg/l
Selenium as Se,
mg/l
< 0.01
<0.01
< 0.01
< 0.01
< 0.01
< 0.01
<0.01
<0.01
60
76
380
74
57
179
399
461
31
1.00
<0.001
40
0.60
<0.001
42
1.30
<0.001
16
0.50
<0.001
22
0.50
<0.001
38
1.00
<0.001
2
0.60
<0.001
12
1.20
<0.001
<0.001
<0.001
<0.001
<0.001
<0.001
<0.001
<0.001
<0.001
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
13
14
Arsenic as As, mg/l
Cyanide as CN,
mg/l
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
15
16
Lead as Pb , mg/l
Zinc as Zn, mg/l
<0.01
< 0.01
<0.01
< 0.01
<0.01
< 0.01
<0.01
< 0.01
<0.01
< 0.01
<0.01
< 0.01
<0.01
< 0.01
<0.01
< 0.01
17
Anionic detergents
as MBAS, mg/l
+
Chromium as Cr6 ,
mg/l
Mineral Oil, mg/l
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
Absent
Absent
Absent
Absent
Absent
Absent
Absent
Absent
20
Alkalinity
mg/l
280
260
420
245
125
290
200
510
21
Aluminium as Al,
mg/l
Boron as B, mg/l
< 0.01
< 0.01
< 0.01
< 0.01
< 0.01
< 0.01
< 0.01
< 0.01
< 0.1
< 0.1
< 0.1
< 0.1
< 0.1
< 0.1
< 0.1
< 0.1
8.
9.
II.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10
11
12
18
19
22
CaCO3,
Bhagavathi Ana Labs Ltd., Hyderabad.
Un
Objectionable
Arjunagi
Objectionable
7.
-
Hanchinahalli
32
–
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
RegionalScenario

The pH values for all the samples collected in the study area during study period were
from 7.54 to 8.22 which were well within the limits.

The TDS of all the samples were between 52 to 2080 mg/l.

The Chloride levels in the ground water samples collected in the study area were ranging
from 178 mg/l to a maximum of 255 mg/l except one sample, all are within the desirable
limits.

In the ground water samples collected from the study area, the hardness is varying from
195 mg/l to 1050 mg/l.

In the ground water samples of study area the fluoride value were in the range of 0.50
mg/l to 1.30 mg/l.
Overall all the ground water samples collected from the study area were found to be fit for
human consumption, however the hardness, dissolved solids most of ground water samples
seem to be above desirable limit but well within the permissible limits. The heavy metals in
all samples are below detectable limits.
3.5
Soil Quality
The present study on soil quality establishes the baseline characteristics in the study area
surrounding the project site. The study has been addressed with the following objectives. To
determine the base line characteristics

To determine the existing soil characteristics around proposed project

To determine the impact of industrialization/urbanization on soil characteristics

To determine the impacts on soils from agricultural productivity point of view.
3.5.1
Criteria Adopted For Selection of Sampling Locations
For studying the soil types and soil characteristics, 7 sampling locations were selected to
assess the existing soil conditions representing various land use conditions and geological
features.
3.5.2
Methodology of Sampling
The homogenized soil samples collected at different locations were packed in a polyethylene
plastic bag and sealed. The sealed samples were sent to laboratory for analysis. The
physical, chemical parameter concentrations were determined from all samples.
Bhagavathi Ana Labs Ltd., Hyderabad.
33
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
3.5.3
Jamkhandi Sugars Limited
– Unit II
Soil Sampling Locations
Details of the soil sampling locations are given in Table–3.10. Soil sampling location map is
shown in Figure–3.6. The soil analysis results are shown in Table–3.11. The rating chart of
soil data is given in Table–3.12.
Location
Code
S1
S2
S3
S4
S5
S6
S7
S.No
Table-3.10
Soil Sampling Locations
Sampling Station
Distance w.r.t.
site in km
Project site
0.0
Marsanahalli
4.5
Vibuthihalli
5.0
Arjunagi
4.0
Shrisara
5.2
Nad KD
2.7
Golsara
3.6
Table – 3.11
Soil Quality Data
Parameters
plant
Results
1.
pH (1.2 Soil Water Extract)
8.14
Marsanahalli
Village
8.01
2.
E.C ( mhos) (1:2 Soil water
Extract)
Available Nitrogen, Kg/Hec
140
588
470
220
210
340
160
380
Available Phosphorous as
P2O5, Kg/Hec
Available Potassium as K2O,
Kg/Hec
19
42
14
45
190
295
337
232
6.
Ex. Sodium as Na, ppm
196
421
315
340
7.
Ex. Calcium as Ca, ppm
2080
3560
2360
2520
8.
Ex. Magnesium as Mg, ppm
535
1119
657
316
9.
Sodium
(SAR)
Ratio
0.31
1.30
0.47
0.54
10.
Water soluble Chloride as
Cl, ppm
350
150
120
50
11.
Organic Carbon,%
0.40
0.68
0.32
0.72
12.
Texture
Sandy Clay
Sandy Loam
Clay
a) Sand, %
Sandy
Loam
71
40
68
30
b) Silt, %
12
26
13
29
c) Clay, %
17
34
19
11
Project site
3.
4.
5.
Absorption
Bhagavathi Ana Labs Ltd., Hyderabad.
Vibuthihalli
Village
7.98
Arjunagi
Village
8.30
34
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
S.No
Parameters
Jamkhandi Sugars Limited
– Unit II
Results
1.
pH (1.2 Soil Water Extract)
8.14
Marsanahalli
Village
8.01
2.
E.C ( mhos) (1:2 Soil water
Extract)
Available Nitrogen, Kg/Hec
140
588
250
Nada
KD
Villag
7.96
e
770
210
340
120
250
310
Available Phosphorous as
P2O5, Kg/Hec
Available Potassium as K2O,
Kg/Hec
19
42
10
26
29
190
295
200
337
390
6.
Ex. Sodium as Na, ppm
196
421
324
460
469
7.
Ex. Calcium as Ca, ppm
2080
3560
1400
2680
2320
8.
Ex. Magnesium as Mg, ppm
535
1119
316
584
316
9.
Sodium
(SAR)
Ratio
0.31
1.30
0.64
0.66
0.77
10.
Water soluble Chloride as
Cl, ppm
350
150
60
180
85
11.
Organic Carbon,%
0.40
0.68
0.28
0.52
0.62
12.
Texture
Sandy Clay
40
Sandy
loam
79
Sandy
Clay
41
Clay
a) Sand, %
Sandy
Loam
71
b) Silt, %
12
26
9
27
29
c) Clay, %
17
34
12
32
41
Project site
3.
4.
5.
Absorption
Shrisada
Village
8.44
Golsara
Village
8.11
355
30
Table-3.12
RatingChart of the Soil Test Data
(Indian Council of Agricultural Research, New Delhi)
Nutrient
Units
Low
Medium
High
Organic Carbon (as measure of
available Nitrogen)
Available Nitrogen (N)
Available Phosphorus (P)
Available Potassium (K)
%
Below 0.5
0.5 – 0.75
Above 0.75
Kg/ha
Kg/ha
Kg/ha
Below 280
Below 10
Below 110
280-560
10-25
110-280
Above 560
Above 25
Above 280
PH
Acidic
Below 6.0
Normal
Below 1.0
Normal to saline
Tending to become alkaline
6.0-8.5
8.6-9.0
Total Soluble salts (Conductivity in Millimhos/cm)
Critical for
germination
1.0-2.0
Bhagavathi Ana Labs Ltd., Hyderabad.
Critical for growth of the
sensitive crops
2.0-4.0
Alkaline
Above 9.0
Injurious to most
crops
Above 4.0
35
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
3.5.4
Jamkhandi Sugars Limited
– Unit II
Regional Scenario
The analytical results of the soil samples collected during the study period are summarized
below.
The pH values in the study area are varying from 7.96 to 8.44 indicating that the soils are
falling in normal to saline class.
The electrical conductivity in the study area is varying from 98 to 150 umhos/cm indicating
that soils falling under Normal category.
The organic carbon in the study area is varying from 0.28 to 0.68 %,
The Nitrates as N value in the study area is varying from 120 kg/ha to 380 kg/ha indicating
that it requires addition of nitrates for proper growth.
In the study area Phosphorus is varying from 10 kg/ha to 45 kg/ha.
The Available Potassium in the study area is varying between 190 kg/ha to 390 kg/ha.
3.6
Biological Environment
An ecological survey of the study area was conducted particularly with reference to listing of
flora and fauna. Assessment of area, surrounding the project site in respect of plant species
and animals were carried out by collecting field data and collating available information from
the forest department. The flora and fauna details are presented in Table 3.13 and
Table3.14 respectively.
Flora
The cropping pattern in the district reveals that food crops like jowar, maize, bajra and wheat
among cereals, red gram, Bengal gram and green gram among pulses are major crops
cultivated in the district. The major oilseed crops are sunflower, groundnut and safflower.
Horticulture crops like grapes, pomegranate, ber, guavasapota, lime are also grown. Recent
trend shows that there is a low shift towards fruit crops like Pomegranate and grapes of the
total area of 8.61 lakh ha. Covered during 2002-03 cereals occupy about 55.2% by oilseeds
24.5% pulse 15.6% and other commercial crops like cotton and sugarcane about 4.8%
There is slight shift towards commercial crops like cotton and sugarcane over last 2 years.
Bhagavathi Ana Labs Ltd., Hyderabad.
36
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
S.No.
1
Table 3.13
List Of Flora In The Study Area
Local Name
Botanical Name
Amla ,Nelli
Emblicaofficinalis
2
Bur, Ala
Ficusbengalensis
3
Arali ,Aswatha
Ficusreligiosa
4
Ari basavanapada
Bauhiniracemosa
5
Babul, karijali,Gobli
Acacia nilotica
6
Neem,Bevu
Azadirachtaindica
7
Gulmohar
Delonixregia
8
Wood apple
Feronialimonia
9
Sausage tree
Kigeliapinnata
10
Channangi
Lagerstroemia parviflora
11
Mango, Aam, Mavu
Mangiferaindica
12
Rain tree
Samaniasaman
13
Chinch, Hunse
Tamarindusindica
14
Jamun, Nerale
Syzygiumcumini
15
Woodi, oddi
Delechandronfaicata
16
Bija-sal, Honne
Pterecarpusmarsupium
17
Gotti,Gotte
Zizyphusxylopyra
18
Hanmanki
Flacourtiaramontchi
19
Ippi, mari
Bassialatifolia
20
Khair, Katinamara
Acacia catechu
21
Kari
Randiadumetorum
22
Kakki, Bava
Capparis species
23
Mulmuttal, Pangara
Erythrinaindica
24
Muttal, Palas
Buteafrondosa
25
Mashwal
Chloroxylonswietenia
26
Nekri
Ximenaamericana
27
Siris, Bage
Albizialebbek
28
Niral, Jambul
Eugenia jambolana
29
Sitaphal
Anonasquamosa
30
Tugli
Albizzi
31
Tapasi
Holopteliaintegrifolia
32
Gajag
Ceasalptinabonduce
1
2
3
4
Shrubs
Shisha, kammari
Honnambri, Tarwad
Henkal
Kalli, Sher
Lantana camara
Cassia auriculata
Gymnosporiamontana
Eupnorbiatirucalli
Bhagavathi Ana Labs Ltd., Hyderabad.
37
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
5
6
7
8
1
2
1
2
3
4
5
Karunda
Lekki, Nirgudi
Pargi
Revdi
Herbs
Anantmul (Indian sarsaparila)
Nachikemullu
Climbers
Bondwel
Gulganj
Kusri, Wildjasmin, Advimallige
Palaswel
Wagati
Jamkhandi Sugars Limited
– Unit II
Carissa carandas
Vitexnegundo
Toddaliaaculata
Capparisdivaricata
Hemidusmusindicus
Mimosa pudica
Lettsomiaelliptica
Abrusprecatorius
Jasminum species
Buteasuperba
Wageteaspicata
Fauna
1
2
3
4
5
6
Table – 3.14
List of Fauna In The Study Area
Local Name
Botanical Name
Common Jackal
Canis - aureus
Common Wolf
Canis-lypuspallipes
Common Mongoose
Herpestes-edwardsi
Indian Hare
Lepur-Nigricollis
Pangolin
Manis- crassicaudata
Wild pig
Sus-screfa
Cobra
Naja -naja
Rat snakes
PtyasMucosus
Viper
Viperarusselli
Avifauna (Birds)
Baya – weaver Bird
Ploceusphilppinus
Small -Barbets
Capitomidae
Bulbuls
Pycnonotidae
Bustard Qualis
Turnicidae
Cuckoos
Cuculidae
Common Myna
Acridotherestristis
7
Doves
Columbidae
Schedule -IV
8
Magpies
Corvidae
Schedule -IV
9
Munias
Estrildinae
Schedule -IV
10
Parakeets
Psittacidae
Schedule -IV
11
Pigeons
Columbidae
Schedule -IV
12
Sun birds
Nectarinidae
Schedule -IV
13
Koel
Eudynamysscolopocea
14
Peacock
Pavociristatus
15
16
Yellow throated sparrow
Tailor Bird
Passezdomesticus
Orthotomus
17
White Backed vulture
Gyps-bengalensis
S.No.
1
2
3
4
5
6
7
8
9
Bhagavathi Ana Labs Ltd., Hyderabad.
Schedule
Schedule-II Part-II
Schedule -I
Schedule -IV
Schedule -IV
Schedule -I
Schedule -I
Schedule-II Part-II
Schedule-II Part-II
Schedule-II Part-II
Schedule -IV
Schedule -IV
Schedule -IV
Schedule -IV
Schedule -IV
Schedule -IV
Schedule-I Part-III
Schedule-IV
38
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
3.7
Jamkhandi Sugars Limited
– Unit II
Socio Economic Environment
The study area consists of 15 villages. Total population of the study area is 38266 with
19642 males and 18624 females. The sex ratio of the district as per 2001 census is 950.
The total literacy rate is 44.2 %.Relatively high level of literate population in the locality is an
indicator of the development of the area. The total percent of main and marginalworkers is
39.19 out of which 11.43 % is marginal workers and 27.7 % is main workers and 60.81 % is
non –workers. The demographic, literacy details of the study area are given as under:Table-3.15
Demographic details of the study area
Description
2011
Actual Population
2,175,102
Male
1,112,953
Female
1,062,149
Population Growth
20.38%
Area Sq. Km
10,517
Density/km2
207
Proportion to Karnataka Population
3.56%
Sex Ratio (Per 1000)
954
Child Sex Ratio (0-6 Age)
930
Average Literacy
67.2
Male Literacy
77.41
Female Literacy
56.54
Total Child Population (0-6 Age)
303,480
Male Population (0-6 Age)
157,212
Female Population (0-6 Age)
146,268
Literates
1,257,742
Male Literates
739,873
Female Literates
517,869
Child Proportion (0-6 Age)
13.95%
Boys Proportion (0-6 Age)
14.13%
Girls Proportion (0-6 Age)
13.77%
Infrastructural Facilities
Education Facilities
In the 10 km radius buffer zone comprises 32 primary schools and 22 Middle schools are.
Here is need to focus on Vocational and Degree college and infrastructure in govt.
Bhagavathi Ana Labs Ltd., Hyderabad.
39
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars Limited
– Unit II
educational institutionsi.e. furniture, toilets, drinking water and RCC building for all schools,
library facilities, Girl child and Adult education.
Health Facilities
In the buffer zone of 10 km area Health facilities comprise 1 Public Health Centre is here, 1
Maternity & Child Welfare Centre, 1 Family Welfare Centre and here is need to focus on
Health Care infrastructure facilities.
Animal Husbandry
The study area is provided with veterinary services with Dispensary and local centers for the
livestocks.
Drinking Water Supply
Adequate facilities are available for tapping drinking water in all of the villages and towns.
Most of the villagers depend on underground water resources such as from well, tank etc.
3.8
Land Use Pattern
As per the 2001 census data the land use pattern is like this 23038 hectors comprises in the
buffer zone among that Irrigated land is 2481.28 hectors, un irrigated land is 19270 hectors,
cultivable waste 283.11 hectors, forest area is nil and area not available land for Cultivation
is 1003.6 hectors.
Land use of the study area around the project site as per census 2001 is given below.
Table-3.17
Land Use Pattern of the Study Area
S. No.
Particulars
Land Use pattern (In Ha)
1
Irrigated Area
2481.28
2
Un-irrigated area
19270
3
Cultivable Waste
283.11
4
Forest Area
0
5
Area Not Available for Cultivation
1003.6
Total Area
23038
3.9
Seismicity
The study area fall under seismic zone II as per IS:1893-2002,BIS, GOI ,Seismic zoning
map of India Meteorological Department shown in Figure–3.7.
Bhagavathi Ana Labs Ltd., Hyderabad.
40
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Chapter–4
Anticipated Environmental Impacts & Mitigation Measures
4.0
Identification of Impacts
This chapter presents identification and appraisal of various impacts due to the proposed
EnhancedSugar Plant with Cogeneration Unit. The environmental impacts can be
categorized as either primary or secondary. Primary impacts are those, which are attributed
directly to the project and secondary impacts are those, which are indirectly induced and
typically include associated investment and changed pattern of social and economic
activities due to the project.
The impacts have been assessed during the construction and operation phase of the Sugar
Plant with Cogeneration power plant on different environmental components:4.1
Impacts during Construction Phase and Mitigation Measures
Probable environmental impacts during construction phase are typically due to activities
related to clearing of vegetation, leveling of site, civil constructions erection of structures and
installation of equipment.
4.2
4.2.1
Air Environment
Impact on Air Quality
The main sources for impact of air quality during construction period is due to movement of
vehicles and construction equipment at site, dust emitted during leveling, grading,
earthmoving, foundation works, transportation of construction material etc. Hence, during the
construction phase, particulate matter (PM10& PM2.5) would be the main pollutants. The
emissions from vehicles and construction equipment could also be of some concern on a
local level.
Air Pollution Mitigation Measures
The dust generated will also be fugitive in nature, which can be controlled by sprinkling of
water. The impacts will be localized in nature and the areas outside the project boundary are
not likely to have any major impact with respect to ambient air quality.
The construction of proposed units would result in the increase of SPM concentrations due
to fugitive dust. Frequent water sprinkling in the vicinity of the construction sites would be
undertaken and will be continued after the completion of plant construction as there is scope
Bhagavathi Ana Labs Ltd., Hyderabad.
41
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
forheavy truck mobility. It will be ensured that diesel powered vehicles will be properly
maintained to comply with exhaust emission requirements.
4.2.2
Noise Environment
Impact on Noise Levels
The major sources of noise during the construction phase are vehicles and construction .The
operation of the equipment can generate noise in the range 85-90 dB (A) near the source.
The noise will be generated within the plant boundary and will be temporary in nature.
Noise Levels Mitigation Measures
The noise control measures during the construction phase include provision of caps on the
construction equipment and regular maintenance of the equipment. Equipment will be
maintained appropriately to keep the noise level within 75 dB(A). Wherever possible,
equipment will be provided with silencers and mufflers. High noise producing construction
activities will be restricted to daytime only. Further, workers deployed in high noise areas will
be provided with necessary protective devices such as ear plug, ear-muffs etc. Overall, the
impact due to increase in noise on the environment would be insignificant, localized and
confined to the day hours.
4.2.3
Water Environment
Impact on Water Resources and Quality
Impact on water quality during construction phase is due to non-point discharges of sewage
generated from the construction work force stationed at the site. Plantsanitation facilities
(septic tanks) will be utilized for treatment and disposal of sanitary sewage generated by the
work force.
Runoffs from the construction yards and worker camps during monsoon could affect the
quality of water bodies in the project area. Further there is possibility of water stagnation in
ponds and ditches which can create an environment conducive to disease carrying vectors.
Water Pollution Mitigation Measures
Toilets with septic tanks will be constructed at site for workers and it will be ensured that
domestic wastewater generated in worker colonies does not flow to water bodies. The
overall impact on water environment during construction phase due to expansion activities is
likely to be short term and insignificant. By adopting necessary mitigation measures the
overall impact on water environment during construction phase of the project will be
temporary and insignificant.
Bhagavathi Ana Labs Ltd., Hyderabad.
42
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
4.2.4
Jamkhandi Sugars
Limited – Unit II
Land Environment
Impact on Land use
Preparatory activities like construction of access roads, temporary offices, and go-downs,
piling, storage of construction materials etc. will be confined within the project area. These
will not exercise any significant impact except altering the land use pattern of the existing
site. The impact will be insignificant on the adjoining land. No forestland is involved.
Therefore, impact will be negligible.
Impact on Topography
Topographically, the area forms slightly elevated land and general elevation is from North to
South. Most of the area forms plain land covered with mixed soil. Adequate storm water
drains will be provided to collect and carry the surface runoff during monsoon to the natural
drainage system of the project area.
4.2.5
Socio-economic Environment
The socio-economic impacts during the construction phase of the proposed Enhancement
Sugar plant with Cogeneration Plant could result due to migrant workers, worker camps,
induced development etc. Increase in floating population.
The local population will have employment opportunities in related service activities like petty
commercial establishments, small contracts/sub-contracts and supply of construction
materials for buildings and ancillary infrastructures etc. consequently, this will contribute to
economic up liftment of the area.
Normally, the construction activity will benefit the local population in a number of ways,
which include the increase in requirement of construction skilled, semi-skilled and un-skilled
workers, tertiary sector employment and provision of goods and services for daily needs
including transport.

Local people will be given preference for employment depending on their suitability;

All the applicable guidelines under the relevant Acts and Rules related to labour
welfare and safety will be implemented during the construction phase;

The contractor has been advised to provide fire wood/kerosene/LPG to the workers
to prevent cutting of nearby trees for firewood; and

The construction site will be secured with fencing and is having guarded entry points.
Bhagavathi Ana Labs Ltd., Hyderabad.
43
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
4.2.6
Jamkhandi Sugars
Limited – Unit II
Storage of Hazardous Material
The hazardous materials used during construction may include diesel and lubricating oils..
These materials will be stored and handled carefully under applicable safety guidelines.
Some of the precautions of storage include the following:
Dyked enclosures will be provided so as to contain complete contents of the largest tank;

Diesel and other fuels will be stored in separate dyke enclosures;

Tanks having large storage capacity for will be separated by fire insulating walls from
other storage tanks; and

The distance between the storage tanks will be maintained half their height.
4.2.7
Facilities to be provided by Labour Contractor
The contractor will be made to provide the following facilities to construction work force:
First Aid
At work place, first aid facilities will be maintained at a readily accessible place where
necessary appliances including sterilized cotton wool etc. Ambulance will be kept at the site
and made available at workplace to take injured person to the nearest hospital.
Potable Water
Sufficient supply of water fit for drinking will be provided at suitable places.
Sanitary Facility
Sanitary facilities will be provided at accessible place within the work zone and kept in a
good condition. The contractor will conform to requirement of local medical and health
authorities at all times.
Canteen
The canteen will be provided for the benefit of workers.
Security
JSL will provide necessary security to work force in co-ordination with State authorities.
4.3
Impacts during Operation Phase
During the Operation Phase the establishment of the project, results in emissions,
generation of wastewater and solid waste.
Bhagavathi Ana Labs Ltd., Hyderabad.
44
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
4.3.1
Jamkhandi Sugars
Limited – Unit II
Air Pollution
Major sources of air pollution in power plant are boiler, and crushers. Fugitive dust emissions
are also inevitable from raw material handling system as well as transportation.
The standby DG sets will be provided with adequate stacks as per CPCB norm.
Transportation of Raw Material & Finished Goods
The emissions from transportation of Raw Material and Finished Goods within the plant area
have been considered as line source emissions all along the road. The stack emissions of
other industries are reflected on existing baseline concentrations of the study area.
Table – 4.1
Stack & Emission Details with Pollution control Equipment
Parameters
Number of Stacks
Common Stack with no. of flues
Stack Height from ground level (m)
Stack Dia. (m) (internal)
Exhaust Gas Temperature (0C)
Exit Gas Velocity (m/s)
Volumetric Flow Rate (m3/s)
APCE Proposed
Emission Rate of PM (gm/sec
Emission Rate of SO2 (gm/sec)
Emission Rate of NOx (gm/sec)
1
One flue
90
1.2
140
13.5
140
ESP with outlet concentration PM
<50 mg/Nm3
0.55
37.78
53.42
4.3.2 Input Data for Ground Level Concentrations (GLCs) Predictions
Meteorological Data
The meteorological data recorded continuously during the study period on hourly basis on
wind speed, wind direction and temperature has been processed for application of ISC
AERMOD View model.
Simulation Model for Prediction using Industrial Source Complex AERMOD View
The pollutants released into the atmosphere will disperse in the down wind direction and
finally reach the ground at farther distance from the source. The concentration of ground
level concentrations mainly depends upon the strength of the emission source and
micrometeorology of the study area.
Bhagavathi Ana Labs Ltd., Hyderabad.
45
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
In order to estimate the ground level concentrations due to the emission from the proposed
project, EPA approved Industrial Source Complex AERMOD View Model has been
employed.
The mathematical model used for predictions on air quality impact in the present study is ISCAERMOD View. It is the next generation air dispersion model, which incorporates planetary
boundary layer concepts.
The AERMOD is actually a modelling system with three separate components: AERMOD
(AERMIC Dispersion Model), AERMAP (AERMOD Terrain Pre-processor), and AERMET
(AERMOD Meteorological Pre-processor).
Special features of AERMOD include its ability to treat the vertical in homogeneity of the
planetary boundary layer special treatment of surface releases, irregularly-shaped area
sources, a plume model for the convective boundary layer, limitation of vertical mixing in the
stable boundary layer, and fixing the reflecting surface at the stack base.
The AERMET is the meteorological pre-processor for the AERMOD. Input data can come
from hourly cloud cover observations, surface meteorological observations and twice-a-day
upper air soundings. Output includes surface meteorological observations and parameters
and vertical profiles of several atmospheric parameters.
The AERMAP is a terrain pre-processor designed to simplify and standardize the input of
terrain data for the AERMOD. Input data include receptor terrain elevation data. Output
includes, for each receptor, location and height scale, which are elevations used for the
calculation of airflow around hills.
4.3.3
Post Project Scenario
Predicted maximum ground level concentrations considering micro meteorological data of
Post Monsoon (Oct- Nov) 2012 are superimposed on the maximum baseline concentrations
obtained during the study period to estimate the post project scenario, which would prevail at
the post operational phase. The overall scenario with predicted concentrations over the
maximum baseline concentrations is shown in the Table 4.2along with isopleths shown in
Figures 4.1 to 4.3.
Bhagavathi Ana Labs Ltd., Hyderabad.
46
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Table – 4.2
Over all Scenario
Maximum Incremental Levels (g/m3)
Season
Year
Post Monsoon
(October &
November)
2012
Jamkhandi Sugars
Limited – Unit II
Distance
PM10
SO2
NOx
km
0.51
9.27
13.12
1.0
Direction
WSW
The predicted ground level concentrations obtained when superimposed on the baseline
concentrations are well within the prescribed NAAQ Standards.
Mitigation Measures
The power plant operates during cane crushing season and off season by using bagasse as
a fuel. Electrostatic precipitator is proposed for the boiler. The height of the stack is fixed at
90 m as per CPCB guidelines.
Fugitive emissions at transfer points will be controlled by water sprinklers.
4.4
Impact on Noise Levels
The equipment in the plant would be designed for noise levels not exceeding 90 dB(A) .
Proper encasement of noise generating sources will be done to control the noise levels
below 75 dB(A) at plant boundary.
The steam turbine generator is provided with acoustic enclosures and silencers in the
exhaust. The steam turbine is housed in a closed building which considerably reduces the
noise. In case of maintenance, the persons working near the steam turbine generator
building are provided with ear muffs.
Green belt in an area of 32.35 acres will be developed all around the plant which will act as a
noise barrier.
In general the following methods will be adopted to control the noise pollution from the
proposed Enhancement Project units: The use of concrete and masonry walls and barriers – keeping in view the benefits of
stiffness weight and cavity construction and the need to provide well sealed sound
attenuating doors and windows.
 The use of complete or partial enclosures
 Attenuation by use of sound absorbents on walls and fixed or suspended ceilings
 Introduction of control and monitoring rooms having good sound insulation properties
 The use of vibration insulation techniques
Bhagavathi Ana Labs Ltd., Hyderabad.
47
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
4.5 Impact on Water Quality
Effluent from water treatment plant
Hydrochloric acid and sodium hydroxide will be used as regenerants in the proposed
demineralising water plant. The acid and alkali effluents generated during the regeneration
process of the ion-exchangers would be drained into an epoxy lined underground
neutralizing pit. Theseeffluents are self-neutralizing.However, provisions will be made such
that the effluents will be neutralized by addition of either acid or alkali to achieve neutral pH
of 7.0.The effluent will then be pumped into the effluent treatment plant for treatment.
Chlorine in cooling water
In the auxiliary cooling water, residual chlorine of about 0.2 ppm
Boiler Blow down
The salient features of blow down water from the point of view of pollution are, the pH and
temperature of water since suspended solids are negligible. The pH would be in the range of
9.8 to 10.3 and the temperature of blow down water will be 100C. The quantity of about 1.8
tonnes/hour of blow down is very small and hence, it is proposed to pull the blow down into
the trench and leave it in the effluent ponds.
Waste Water treatment
Waste water treatment for the plant will be based on discharges of the various wastewater to
ponds for clarification and filtration. Oily water will be treated separately to remove oil/grease
before discharge into effluent ponds. The oily water collection in the plant is basically due to
floor cleaning, leaky oil filters, etc.
4.5.1 Waste water generation
The total waste water generation from the Sugar plant along with the Cogeneration Plant will
be432 m3/day. The generated wastewater will be sent to Effluent Treatment Plant (ETP) and
the treated wastewater will be used for cane irrigation and green belt development.
4.6
Solid Waste
4.6.1 Dry fly ash and Furnace bottom ash
Fly ash collected from the ESP hoppers and the airheaters hoppers and the ash collected
from the furnace bottom hoppers can be used as landfill. The ash content in bagasse is less
than 2%. The total fly ash 21.7 TPD will be used as manure. The high potash content in the
bagasse ash makes the ash as good manure.
Bhagavathi Ana Labs Ltd., Hyderabad.
48
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Press mud of 140 TPD will be sold to farmers as manure.
The liquid molasses 140 TPD will be sent to distillery for manufacture of alcohol.
4.6.2 Sewage from various buildings in the plant
Sewage from various buildings in the plant area will be conveyed through separate drains of
the septic tank followed by soak pit. Sludge will be removed occasionally and disposed off as
a land fill at suitable places.
4.8
Impact on Ecology
The enhanced project will not have any significant impact on ecology as there are no reserve
forests in the study area and in addition to that the project will implement an effective
environmental management plan to control the emissions from the project.
Green belt development
The total project area acquired for plant is 98.04 acres, and 33% of it,32.35 acres will be
used for green belt development. Local species will be preferred for green belt development.
4.9
Demography and Socio-economics
The impacts due to enhanced project on demography and socio economic condition are as
follows: Increase in employment opportunities and Reduction in migrants to outside for
employment.
 Increase in literacy rate.
 Growth in service sectors
 Increase in consumer prices of indigenous produce and services, land prices, house
rent rates and Labour prices.
 Improvement in socio cultural environment of the study area.
 Improvement in transport, communication, health and educational services.
 Increase in employment due to increased business, trade commerce and service
sector.
 The overall impact on the socio economic environment will be beneficial.
4.10
Impact on Health
Adequate air pollution and noise control measures will be provided. The environmental
management and emergency preparedness plans will be prepared to ensure that the
probability of undesired events and consequences would be reduced, and adequate
mitigation measures will be provided in case of an emergency. The overall impact on Human
health is negligible during operation of plant.
Bhagavathi Ana Labs Ltd., Hyderabad.
49
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Chapter– 5
Environmental Monitoring Program
Pollution Monitoring and Surveillance Systems
For Proposed Enhanced Sugar Plant and Cogeneration power plant, the Indian Emission
Regulations stipulate the limits for particulate matter emissions and appropriate stack
heights will be maintained for keeping the emission levels in the ambient within the air quality
standards.
The characteristics of the effluent from the plant would be maintained so as to meet the
requirements of the State Pollution Control Board and the National Standards for Sugar
Plant stipulated by the Central Board for Prevention and Control of Water Pollution.
Air Quality monitoring programme
The purpose of air quality monitoring is acquisition of data for comparison against prescribed
standards, thereby ensuring that the quality of air is maintained within the permissible levels.
It is proposed to monitor the following from the stack emissions:
Particulate Matter (SPM, PM10& PM2.5)

Sulphur dioxide

Oxides of Nitrogen
It is proposed to monitor particulate emission qualitatively and quantitatively in the stack and
with the aid of a continuous particulate stack monitoring system. The stack monitoring data
would be utilized to keep a continuous check on the performance of ESPs.
Further it is proposed to monitor and record the weather parameters such as temperature
(maximum & minimum), Relative humidity, wind direction, wind speed, rainfall etc. on daily
basis, for this purpose, it is proposed to install Weather Monitoring Station with necessary
gadgets.
Bhagavathi Ana Labs Ltd., Hyderabad.
50
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
5.0
Jamkhandi Sugars
Limited – Unit II
Post Project Environmental Monitoring
Environmental monitoring will be conducted on regular basis to assess the pollution level in
the plant as well in the surrounding area. Therefore, regular monitoring program of the
environmental parameters is essential to take into account the changes in the environment.
The objectives of monitoring are: To verify the result of the impact assessment study in particular with regards to
new developments;
 To follow the trend of parameters which have been identified as critical;
 To check or assess the efficacy of the controlling measures;
 To ensure that new parameters, other than those identified in the impact
assessment study, do not become critical through the commissioning of new
installations or through the modification in the operation of existing facilities;
 To check assumptions made with regard to the development and to detect
deviations in order to initiate necessary measures; and
 To establish a database for future Impact Assessment Studies for expansion
projects.
The attributes, which merit regular monitoring, are specified below:
Air quality;

Water and wastewater quality;

Noise levels;

Soil quality;

Ecological preservation and afforestation; and

Socio Economic aspects and community development
The post project monitoring will be carried out at the industry level is discussed
below:
5.1
Monitoring and Reporting Procedure
Regular monitoring of important and crucial environmental parameters has an immense
importance to assess the status of environment during plant operation. With the knowledge
of baseline conditions, the monitoring programme can serve as an indicator for any
Bhagavathi Ana Labs Ltd., Hyderabad.
51
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
deterioration in environmental conditions due to operation of the plant and suitable mitigation
steps could be taken in time to safeguard the environment. Monitoring is as important as that
of control of pollution since the efficiency of control measures can only be determined by
monitoring. The following routine monitoring programme would therefore be implemented. A
comprehensive monitoring program will be implemented is given in the Table 5.2.
Source
Location
Table 5.2
Post Project Monitoring
Parameters to
be monitored
Wind speed,
Frequency
direction,
Meteorology
At the project site
temperature,
Hourly
relative humidity
Responsibility
M/s Jamkhandi
Sugars Limited
rainfall
Ambient Air
Quality
Within plant and
surrounding 10km
radial zone.
PM10, PM2.5
SO2, NOx
Monthly
M/s Jamkhandi
Sugars Limited
Within the plant and
surrounding 10km
Water Quality
radial zone
Surface Water
As per IS: 10500
Monthly
Noise levels
Monthly
Soil parameters
Monthly
Particulate
Monthly
M/s Jamkhandi
Sugars Limited
As well as
Ground Water
Within the plant and
Noise Levels
surrounding 10km
radial zone.
Soil quality
Boilers
Within the plant and
10 km radial zone
Individual Units
matter, SO2, NOx
Bhagavathi Ana Labs Ltd., Hyderabad.
M/s Jamkhandi
Sugars Limited
M/s Jamkhandi
Sugars Limited
M/s Jamkhandi
Sugars Limited
52
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Source
Location
Wastewater
Inlet and outlet of
Parameters to
Frequency
be monitored
pH, TDS, COD,
Monthly
ETP
SS and others
Responsibility
.
5.2
Steam–Generator
pH,
SS,
Oil,
Blow down
Grease, Cu, Iron
Cooling Tower
Phosphates
Weekly
M/s Jamkhandi
Sugars Limited
Weekly
Environmental Laboratory Equipment
The plant will have an in-house environmental laboratory for the online monitoring of air,
noise, water and soil. For all non-routine analysis, the plant may utilize the services of
external accredited laboratory facilities. The laboratory equipment required for monitoring
and analysis are given below:
Table-5.3
List of Equipment Proposed for Environmental Laboratory
Name of the Equipment
Automatic Weather Station, which can record wind speed, wind direction
temperature, relative humidity, rainfall, Solar radiation Sunshine
a) Online Automatic gaseous stack monitoring kit for SO 2, NOx, O2, Flue gas
volume, Temperature etc.
b) On line dust monitor
Fine Particulate Matter samplers with PM10& PM2.5 provision
Portable Flue Gas Combustion Analyser
Atomic Absorption Spectrophotometer
Mercury analyzer
Portable Noise level meter (Dosimeter)
Portable Waste Water Analysis Kit
BOD Incubator
COD Digester
Electronic Balance
Calorimeter
Conductivity Meter
Different micron sieves (set)
Dissolved Oxygen Meter – Brief case size
Electronic colony counter
Flask Shaker
Bhagavathi Ana Labs Ltd., Hyderabad.
Nos.
1
1
5
1
1
1
2
1
1
2
1
1
2
1 set
2
1
1
53
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Hot Air Oven
Laboratory Water Distillation and demineralisation (DM) unit
5.3
2
2
Environmental Management Group
A separate environmental management group will be established to implement the
management plan. The group will be headed by a Superintending Engineer. The group will
ensure the suitability, adequacy and effectiveness of the Environment Management
Program. The management review process will ensure that the necessary information is
collected to allow management to carry out its evaluation. This review will be documented.
Functions of Environmental Management Group (EMG) at Site will be: Obtaining consent order from State Pollution Control Board.
 Environmental monitoring.
 Analysis of environmental data, reports, preparations and transmission of
report to statutory authorities, Corporate Centre etc.
 Co-ordinate with statutory bodies, functional groups of the station, head
office etc.
 Interactions for evolving and implementation of modification programs to
improve the availability / efficiency of pollution control devices / systems.
 Environmental Appraisal (Internal) and Environmental Audit.
5.4
Expenditure and Environmental Measures
The budget for Environmental Protection Measures in Lakhs is given as under:Table-5.4
Budget for Environmental Measures
S. No.
Particulars
Capital cost (Rs.Lakhs)
Recurring cost (Rs.Lakhs)
1.
Air Pollution & Noise Control
200.00
25.00
2.
Septic tanks & Soak pits
25.00
2.00
3.
Wastewater Treatment
400.00
25.00
4.
Environment Monitoring and
Management
25.00
3.00
5.
Occupational Health & Safety
50.00
5.00
6.
Green Belt
50.00
5.00
750.00
65.00
TOTAL
Bhagavathi Ana Labs Ltd., Hyderabad.
54
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Chapter–6
Additional Studies
(Risk Assessment & Disaster Management Plan)
6.0
Risk Assessment
6.1
Introduction
The word 'disaster' is synonymous with 'emergency' as defined by the Ministry of
Environment and Forests (MoEF). An emergency occurring in the proposed Enhancement
plant is one that may affect several sections within it and/ or may cause serious injuries, loss
of lives, extensive damage to environment or property or serious disruption outside the plant.
It will require the best use of internal resources and the use of outside resources to handle it
effectively. It may happen usually as the result of a malfunction of the normal operating
procedures.
It is imperative to conduct risk analysis for all the projects where hazardous materials, fuels
are handled.
The following have been addressed as part of the risk analysis.

Introduction

Hazard Identification and Risk Analysis

Risk Reducing Measures
The Introduction deals with the objective and methodology of carrying out the risk analysis.
Hazard Identification and Risk Analysis discusses about the various types of hazards
associated with the operation of the Plant due to process, storage & handling, human errors,
electric failures and natural calamities. It also presents the calculated frequencies of
occurrence of different accident scenarios for the identified potential hazard occurrence in
the proposed plant and the details of consequence modelling/ analysis for the identified
potential accidents/disaster scenarios in the plant.
Risk Reducing Measures based on the calculated frequencies and consequences.
Bhagavathi Ana Labs Ltd., Hyderabad.
55
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
6.2
Jamkhandi Sugars
Limited – Unit II
Objective
The principal objective of the study is to identify the potential hazards from the proposed
Enhancement Project and estimate the effects of the hazards to people and property within
the plant premises.
The consequences resulting due to accidental release of toxic & flammable liquids and
leakage of fuels, will provide data for developing strategies to prevent accidents right from
design to operational phase. This will also generate information for formulating a meaningful
Disaster Management Plan (DMP).
A risk analysis is defined as an assessment of the likelihood of a release of HAZMAT
(hazardous materials) and the consequences that may result, based on information gathered
during the hazard identification and vulnerability analyses. Risk analysis requires evaluation
of existing base and local community plans, response capabilities, and previous incidents.
In order to determine the risk factor at each facility on the base, the following information
was evaluated: Procedures for storing, handling, shipping, and transferring of HAZMAT;
 Facility information including: physical features and location of storm and sanitary
sewer systems;
 Site measures for managing and controlling HAZMAT releases; and,
 Base emergency response and preparedness programs.
6.3
Methodology
The Risk Analysis Study carried out under the following task heads: System Study
The system description covers the plant description, storage & handling of fuels /
chemicals, etc.
 Hazard Identification
The hazards associated with the proposed Enhancement Project have been
discussed in terms of material hazards due to fuel storage.
 Frequency of Hazard Occurrence
Bhagavathi Ana Labs Ltd., Hyderabad.
56
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Based on the available international statistics and in-house risk database, the
frequencies of occurrence for the different accident scenarios were determined. The
frequencies derived from the historical database have been checked with the
possible hazard scenario identified during hazard identification.
 Consequence Analysis
Based on the identified hazards, accident scenarios and the frequency of occurrence,
consequence calculations were done for spreading distances (zone of influence) or
risk distance for Pool fires.
 Risk Reducing Measures
Necessary risk reducing measures have been suggested based on the consequence
scenarios.
6.4
Hazard Identification and Risk Analysis (HIRA)
The main hazard potentials in the Proposed Plant are categorized as below:
Material hazards; Diesel Oil as an auxiliary fuel to start-up and flame
stabilization of the boiler.
 Process hazards due to loss of containment during handling of hazardous
materials or processes resulting in fire, explosion, etc.
 Mechanical hazards due to "mechanical" operations such as welding,
maintenance, falling objects etc. - basically those NOT connected to hazardous
materials.
 Electrical hazards: electrocution, high voltage levels, short circuit, etc.
Out of these, the material and process hazards are the one with a much wider damage
potential as compared to the mechanical and electrical hazards, which are by and large
limited to very small local pockets.
6.4.1
Material Hazards
Diesel Oil is used as an auxiliary fuel, which is inflammable.
6.4.2
Process Hazards
No process hazards are assessed
6.4.3
Hazard Intensity Classification
The hazard intensities of the chemicals that are to be handled in the proposed Enhancement
plant (as per NFPA codes) are presented below.
Bhagavathi Ana Labs Ltd., Hyderabad.
57
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Table -6.3
Hazard Intensity Classification
Remedial measures:
Bhagavathi Ana Labs Ltd., Hyderabad.
58
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 Storage in tightly closed containers in a cool, well-ventilated area away from WATER,
HEAT, COMBUSTIBLES (such as WOOD, PAPER and OIL) and LIGHT.
 Storage away from incompatible materials such as flammable materials, oxidizing
materials, reducing materials, strong bases.
 Use of corrosion-resistant structural materials and lighting and ventilation systems in
the storage area.
 Wood and other organic/combustible materials will not be used on floors, structural
materials and ventilation systems in the storage area.
 Use of airtight containers, kept well sealed, securely labelled and protected from
damage
 Use of suitable, approved storage cabinets, tanks, rooms and buildings.
 Suitable storage will include glass bottles and containers.
 Storage tanks will be above ground and surrounded with dikes capable of holding
entire contents.
 Limit quantity of material in storage. Restrict access to storage area.
 Post warning signs when appropriate. Keep storage area separate from populated
work areas. Inspect periodically for deficiencies such as damage or leaks.
 Have appropriate fire extinguishers available in and near the storage area.
The following measures are adopted for reducing the risk involved in pipeline systems.
Preventive Maintenance:
Routine inspection and preventive maintenance of equipment / facilities at the unit.
Instruments:
All the instruments like pressure, temperature transmitters/gauges and alarms switches and
safety interlocks will be tested for their intended application as per the preventive
maintenance schedule. Similarly, the emergency shutdown system will be tested as per the
preventive maintenance schedule.
6.6
Risk Mitigation Measures
The materials handled at the proposed installation are non-inflammable and non-reactive
substances and based on the consequence analysis; the following measures are adopted as
risk mitigation measures.
Bhagavathi Ana Labs Ltd., Hyderabad.
59
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 The storage area, process area as well as road tankers loading/unloading areas
where there is maximum possibility of presence of flammable hydrocarbons such as
diesel in small quantities, it will be ensured that combustible materials are not placed
here such as oil filled cloth, wooden supports, oil buckets etc. to reduce the
probability of secondary fires in case of release.
 Hydrocarbon, smoke and fire detectors will be suitably located and linked to fire
fighting system to reduce the response time and ensure safe dispersal of vapours
before ignition can occur.
 Emergency procedures will be well rehearsed and state of readiness will be
achieved.
6.6.1
Possibilities, Nature and Effects of Emergency
Leaving aside earthquake, cyclone, flood, arson and sabotage, the possible
emergencies that can arise in the plant due to storage and handling of the above
materials are:
 Explosion in boilers, turbo generators, and transformers.
 Accidental release of huge ash slurry
 Chlorine leakage in the water treatment plant
 Accidental fire due to some other reasons
6.7
Disaster Management Plan
This DMP has been designed based on the range, scales and effects of "Major
Generic Hazards" described in the Risk Assessment Report just mentioned and on
their typical behaviours predicted therein. The DMP addresses the range of thermal
and mechanical impacts of these major hazards so that potential harm to people
onsite and off-site, plant and environment can be reduced to a practicable minimum.
The scenarios of loss of containment are credible worst cases to which this DMP is
linked.
The project is in its formative stage and detail engineering is yet to be done, so the
elements of the DMP are based on concepts.
Bhagavathi Ana Labs Ltd., Hyderabad.
60
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
6.7.1
Jamkhandi Sugars
Limited – Unit II
Capabilities of DMP
The emergency plan envisaged will be designed to intercept full range of hazards
specific 'to Cogeneration power plant such as fire, explosion, major spill etc. In
particular, the DMP will be designed and conducted to mitigate those losses of
containment situations, which have potentials to escalate into major perils.
Another measure of the DMP's capability will be to combat small and large fire due to
ignition of flammable materials, either from storage or from process streams and
evacuate people from the affected areas speedily to safe locations to prevent
irreversible injury.
Emergency medical aid to those who might be affected by incident heat radiation
flux, shock wave overpressures and toxic exposure will be inherent in the basic
capabilities.
The most important capability of this DMP will be the required speed of response to
intercept a developing emergency in good time so that disasters such as explosion,
major fire etc. are never allowed to happen.
6.7.2
Disaster Control Philosophy
The emergency control philosophy of the plant is in line with its normal operational
controls. The emergency control room will be the plant's Central Control Room,
which will employ Distributed Control System (DCS). All emergency operations,
which may involve shutdown of the plant, will be controlled from the Central Control
Room by the same operator(s) using dedicated "Shut-Down Consoles". The consoles
will send commands to initiate the shutdown procedure. Plant shutdown system will
be performed by DCS.
The principal strategy of DMP of the plant is "Prevention" of identified major hazards.
The "Identification" of the hazards will employ one or more of the techniques [e.g.
Hazard and Operability Study (HAZOP), accident consequence analysis etc.]. Since
these hazards can occur only in the event of loss of containment one of the key
objectives of technology selection, project engineering, construction, commissioning
and operation is "Total and Consistent Quality Assurance". The Project Authority will
Bhagavathi Ana Labs Ltd., Hyderabad.
61
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
be committed to this strategy right from the conceptual stage of the plant so that the
objective of prevention can have ample opportunities to mature and be realized in
practice
The DMP or Emergency Preparedness Plan (EPP) will consist of: On-site Emergency Plan
 Off-site Emergency Plan
Disaster Management Plan preparation under the headlines of On-site Emergency
Plan and Off-site Emergency Plan is in consonance with the guidelines laid by the
Ministry of Environment and Forests (MOEF), Govt of India.
"Occupier" of the facility is responsible for the development of the On-site Emergency
Plan as per the guidelines given by the Government; The Off-site Emergency Plan
will be developed by the Government (District Authorities).
6.8
On-Site Emergency Plan
6.8.1
Objectives
The objective of the On-site Emergency Plan should be to make maximum use of the
combined resources of the plant and the outside service to
 Effect the rescue and treatment of casualties
 Safeguard other personnel in the premises
 Minimise damage to property and environment
 Initially contain and ultimately bring the incident under control
 Identify any dead
 Provide for the needs of relatives
 Provide authoritative information to the news media
 Secure the safe rehabilitation of affected areas
 Preserve relevant records and equipment for the subsequent enquiry into the
cause and circumstances of emergency.
6.8.2
Action Plans
The Action Plan consists of:
 Identification of Key Personnel
 Defining responsibilities of Key Personnel
 Designating Emergency Control Centres and Assembly Points
 Declaration of Emergency
 Sending All Clear Signal
Bhagavathi Ana Labs Ltd., Hyderabad.
62
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 Defining action’s to be taken by non-key personnel during emergency
6.8.3
Key Personnel
The actions necessary in an emergency will clearly depend upon the surrounding
circumstances. Nevertheless, it is imperative that the required actions are initiated
and directed by nominated people, each having specified responsibilities as part of
co-ordinated plan. Such nominated personnel are known as Key Personnel.
The Key Personnel are: Site Controller (SC)
 Incidental Controller (IC)
 Liaison and Communication Officer (LCO)
 Fire and Security Officer (FSO)
 Team Leaders (TL)
Site Controller (SC)
In the emergency situation, decisions have to be taken which may affect the whole or
a substantial part of the plant and even places outside. Many of these decisions will
be taken in collaboration with the other officers at the plant and the staff. It is
essential that the authority to make decision be invested in one individual. In this
plan, he is referred to as the 'Site Controller'. The Plant Manager (however called) or
his nominated deputy will assume responsibility as SC.
Incident Controller (IC)
In the emergency situation, someone has to direct the operations in the plant area
and co-ordinate the actions of outside emergency services at the scene of incident.
The one who will shoulder this responsibility is known as 'Incident Controller' in this
plan.
A Senior Operations Officer or an officer of similar rank of the unit may be nominated
to act as the IC.
Liaison and Communication Officer (LCO)
Operations Officer or any other officer of deputy rank will work as LCO and will be
stationed at the main entrance during emergency to handle Police, Press and other
enquiries. He will maintain communication with the IC.
Fire and Safety officer (FSO)
The Fire and Safety Officer will be responsible for fire fighting. On hearing the fire
alarm he shall contact the fire station immediately and advise the security staff in the
Bhagavathi Ana Labs Ltd., Hyderabad.
63
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
plant and cancel the alarm. He will also announce on PAS (public Address System)
or convey through telephones or messengers to the SC, IC and LCO about the
incident zone. He will open the gates nearest to the incident and stand by to direct
the emergency services. He will also be responsible for isolation of equipment from
the affected zone.
Team Leaders (TL)
A number of special activities may have to be carried out by specified personnel to
control as well as minimize the damage and loss. For this purpose designated teams
would be available. Each team will be headed by a Team Leader (TL).
Following teams are suggested:
 Repair Team
 Fire Fighting Team
 Communication Team
 Security Team
 Safety Team
 Medical Team
6.8.4
Responsibilities of Key Personnel
Site Controller (SC)
 On getting information about emergency, proceed to Main Control Centre
 Call in outside emergency services
 Take control of areas outside the plant, which are affected
 Maintain continuous communication, review situation and assess possible
course of events
 Direct evacuation of nearby settlements, if necessary
 Ensure that casualties are getting enough help
 Arrange for additional medical help and inform relatives
 Liaison with Fire and Police Services and Provide advice on possible effects
on outside areas
 Arrange for chronological recording of the emergency
 Where emergency is prolonged, arrange for relieving personnel, their catering
needs etc.
 Inform higher officials in head office
 Ensure preservation of evidence
 Direct rehabilitation work on termination of emergency
Bhagavathi Ana Labs Ltd., Hyderabad.
64
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Incident Controller (IC)
 On getting emergency information, proceed to Main Control Centre
 Activate emergency procedure such as calling in various teams
 Direct all operations within plant with following priorities:
a) Control and contain emergency
b) Secure safety of personnel
c) Minimise damage to plant, property and the environment
d) Minimise loss of material
 Direct rescue and repair activities
 Guide fire-fighting teams
 Arrange to search affected area and rescue trapped persons
 Arrange to evacuate non-essential personnel to safe area/assembly point
 Set up communications network and establish communication with SC
 Arrange for additional help/equipment to key personnel of various teams
 Consider need for preserving all records, information for subsequent
enquiries
Liaison and Communications Officer
 To ensure that casualties receive adequate attention, arrange additional help if
required and inform relatives
 To control traffic movements into the plant and ensure that alternative transport
is available when need arises
 When emergency is prolonged, arrange for the relief of personnel and organize
refreshments/catering facility
 Advise the Site Controller of the situation, recommending (if necessary)
evacuation of staff from assembly points
 Recruit suitable staff to act as runners between the Incident Controller and
himself if the telephone and other system of communication fail. -Maintain
contact with congregation points
 Maintain prior agreed inventory in the Control Room
 Maintain a log of the incident on tape
 In case of a prolonged emergency involving risk to outside areas by windblown
materials - contact local meteorological office to receive early notification of
changes in weather conditions
Bhagavathi Ana Labs Ltd., Hyderabad.
65
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Fire and Safety Officer
 Announce over the PAS in which zone the incident has occurred and on the
advice of the Shift Officer informs the staff to evacuate the assembly
 Inform the Shift Officer In-charge, if there is any large escape of fumes.
 Call out in the following order:
1) Incident Controller or his nominated deputy
2) Maintenance Officer
3) Personnel and Administrative Officer
4) Departmental Head in whose area the incident occurred
5) Team Leaders (TL)
6.8.5
Responsibilities of Teams
1. Repair Team
They will identify source of leak and arrest it, take steps to keep rest of the plant in
safe condition, arrange safe shutdown of operations if necessary, attend to all repair
jobs which are needed from emergency point of view, take steps to contain or reduce
the intensity of emergency, arrange for additional equipment and give temporary
connections as needed.
2. Fire Fighting Team
They will rush to the incident spot and start fighting the fire, maintain adequate water
pressure in the fire hydrant system, arrange first aid fire extinguishers where needed
and guide and direct outside fire fighting agencies.
3. Communication Team
They will maintain the communication network inside the terminal, attend urgent
repairs in the communication system, and arrange messengers for conveying urgent
messages when needed so, help SC, IC, LCO and FSO in their communication
activities.
4. Security Team
They will man all gates, with minimum delay permit the entry of authorized personnel
and outside agencies, vehicles etc. who have come to help, bar entry of unauthorized
persons, allow the ambulance etc. to go through the gates without normal checks.
5. Safety Team
They will rescue the casualties on priority basis, transport casualties to first aid post,
safe places, or medical centres, account the personnel, search for missing
Bhagavathi Ana Labs Ltd., Hyderabad.
66
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
personnel and pass information to the kith and kin of fatal or serious casualties,
arrange required safety equipment, report of status to their leader, record of
accidents, collect and preserve evidences in connection with accident cases, arrange
for transport of casualties, arrange for transport of materials, attend to vehicle
breakdowns, arrange petrol and diesel supply and withdraw and transport materials
from stores.
6. Medical Team
They will arrange for first aid, arrange for stretchers, arrange for immediate medical
attention, arrange for sending the casualties to various hospitals and nursing homes
and arrange for medicines.
6.8.6
Emergency Control Centre
The Emergency Control Centre will be the focal point in case of an emergency from
where the operations to handle the emergency are directed and co-ordinated. It will
control site activities.
Emergency management measures in this case will be carried out from single control
Centre designated as Main Control Centre (MCC)
MCC is the place from which messages to outside agencies will be sent and mutual
aids and other helps for the management of emergency will be arranged. It will be
located in the safe area. It will be equipped with every facility for external and internal
communication, with relevant data, personal protective equipment to assist hose
manning the centre to enable them to co-ordinate emergency control activities. CC
will be attended by SC.
Proposed Location:- Office of the DGM (Maintenance) located in Administrative
Building.
Following facilities would be available in the MCC: P&T phones, mobile phones, intercoms, and wireless
 Fax and telex
 Emergency manuals
 Blown up area maps
 Internal telephone directories
 District telephone directories
 Emergency lights
 Wind direction and speed indicator
Bhagavathi Ana Labs Ltd., Hyderabad.
67
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 Requisite sets of personal protective equipment such as gloves, gumboots
and aprons
 MCC will be furnished with call out
MCC will be furnished with call out list of key persons, fire, safety, first aid, medical,
security, police and district administrative authorities. MCC will also contain safety
data pertaining to all hazardous materials likely to cause emergency and well-defined
procedures of fire fighting, rescue operations, first aid etc.
6.8.7
Assembly Point
In an emergency, it will certainly be necessary to evacuate personnel from affected
areas and as precautionary measure, to further evacuate non-essential workers, in
the first instance, from areas likely to be affected, should the emergency escalate.
The evacuation will be effected on getting necessary message from i.e. On
evacuation; employees would be directed to a predetermined safe place called
Assembly Point.
Proposed Location: Area opposite to service building will be the Assembly Point
where all non-key personnel would assemble on getting direction over PublicAddress System.
Outdoor assembly points, predetermined and premarked, will also be provided to
accommodate evacuees from affected plant area(s). Roll call of personnel collected
at these assembly points, indoor and outdoor will be carried out by roll call crew of
safety team to account for any missing person(s) and to initiate search and rescue
operations if necessary.
6.8.8
Declaration of Emergency
An emergency may arise in the terminal due to major leakage of oil or major outbreak
of fire. In case of major leak or major outbreak of fire the state of emergency has to
be declared by the concerned by sounding Emergency Siren.
Upon manual or sensor detection of a major loss of containment of volatile
hazardous substance, the DMP is activated by raising an audible and visual alarm
through a network of geographically dispersed gas/vapour and heat detectors and
also "break glass" type fire alarm call points with telephone handsets to inform the
Central Control Room.
Bhagavathi Ana Labs Ltd., Hyderabad.
68
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
A separate siren audible to a distance of 5 km range will be available for this
purpose. The alarm is coded such that the nature of emergency can be distinguished
as a leakage or major fire.
The Control Centre and Assembly point have been located at an area of the
minimum risk or vulnerability in the premises concerned, taking into account the wind
direction, areas which might be affected by fire/explosion, leakage etc.
After cessation of emergency, FSO will communicate to IC. After verification of
status, IC will communicate with SC and then announce the "All Clear" by instructing
the Time Office to sound the "All Clear Signal".
Alarms would be followed by an announcement over Public Address System (PAS).
In case of failure of alarm system, communication would be' by telephone operator
who will make announcement in the complex through PAS. Walkie-talkie system is
very useful for communication during emergency with predetermined codes of
communication. If everything fails, a messenger could be used for sending the
information.
Two 5 km, range variable pitch electric sirens (one in service and the other standby)
will generate the main alarm for the entire site as well as for the district fire brigade.
The alarm is coded such that the nature of emergency can be distinguished as a
leakage or major fire. Fire and Gas alarm matrices are provided at the Central
Control room, security gate, on-site fire station and main administrative office corridor
to indicate location of the site of emergency and its nature.
6.8.9
Mutual Aid
Procedure
All factories may not be equipped with an exhaustive stock of equipment/materials
required during an emergency. Further, there may be a need to augment supplies if
an emergency is prolonged.
It would be ideal to pool all resources available in the and nearby outside agencies
especially factories during an emergency, for which a formal Mutual Aid scheme
should be made among industries in the region.
6.8.10 Essential Elements
Essential elements of this scheme are given below: Mutual aid must be a written document, signed by Location In-charge of all the
industries concerned
Bhagavathi Ana Labs Ltd., Hyderabad.
69
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 It should specify available quantity of materials/ equipment that can be spared
(not that which is in stock)
 Mode of requisition during an emergency.
 It
should
authorize
the
shift-in-charge
to
quickly
deploy
available
material/equipment without waiting for formalities like gate pass etc.
 It should spell out mode of payment/replacement of material given during an
emergency
 It should specify key personnel who are authorized to requisition materials
from other industries or who can send materials to other industries
 It should state clearly mode of receipt of materials at the affected unit without
waiting for quantity/quality verification etc.
 Revision number and validity of agreement should be mentioned
 This may be updated from time to time based on experience gained
6.8.11 Emergency Management Training
The Key Personnel would undergo special courses on disaster management. This
may preferably be in-plant training. The Managers, Senior Officers and Staff would
undergo a course on the use of personal protective equipment.
The Key Personnel belonging to various Teams would undergo special courses as
per their expected nature of work at the time of emergency.
The plant management should conduct special courses to outside agencies like
district fire services to make them familiar with the plant layout and other aspects,
which will be helpful to them during an emergency.
6.8.12 Mock Drills
It is imperative that the procedures laid in this Plan are put to the test by conducting
Mock Drills. To avoid any lethality, the emergency response time would be clocked
below 2 minutes during the mock drill.
1st Step: Test the effectiveness of communication system
2nd Step: Test the speed of mobilisation of the plant emergency teams
3rd Step: Test the effectiveness of search, rescue and treatment of casualties
Bhagavathi Ana Labs Ltd., Hyderabad.
70
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
4th Step: Test emergency isolation and shut down and remedial measures taken on
the system
5th Step: Conduct a full rehearsal of all the actions to be taken during an emergency
The Disaster Management Plan would be periodically revised based on experiences
gained from the mock drills.
6.9 Proposed Communication System
The instrument and control system will take care of the following operating
philosophy of the plant:
 The project will be provided with a control system located in a central control
room.
 The shift engineer will operate the plant from his console panel.
 All operations will be represented in a graphic panel on the console and every
operation will be depicted as operating sequences.
 All operating parameters will be displayed in digital format.
 Alarms will be provided for all parameters, when they exceed set values.
 High-High/Low-Low alarms and trip functions will be provided to trip
 Pumps/compressors to bring the entire system to a safe shutdown.
6.10 Proposed Fire Fighting System
Elaborate fire fighting system will be available for fighting fires in any comer of the
plant. A comprehensive fire detection and protection system is envisaged for the
complete power station.

Fire water storage tanks of adequate capacity.

Fire water pump house containing combination of diesel and electrically
driven pumps.

Hydrant system complete with suitable size piping, valves, instrumentation,
hoses, nozzles, hose boxes/stations, monitors etc.

Foam injection system for fuel oil/storage tanks consisting of foam
concentrate tanks, foam pumps, in-line inductors, valves, piping and
instrumentation etc.

Automatic high velocity water spray system consisting of detectors, deluge
valves projectors, valves, piping and instrumentation.
Bhagavathi Ana Labs Ltd., Hyderabad.
71
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II

Automatic medium velocity water spray system consisting of QB

Detectors/smoke detectors, linear heat sensing cable detectors, deluge
valves, isolation valves, nozzles, piping, instrumentation etc.

Suitable "Halon Substitutes" such as INERGEN or FM: 200 or AGGONITE for
protection of control room, equipment room, computer room and other electric
and electronic equipment rooms.

Computerized analogue, addressable, early warning type fire detection and
alarm system consisting various types of fire detection such as ionisation type
smoke detection system, photo electric type smoke detection system, linear
heat sensing cable detector, quartzoid bulb (QB) heat detection system,
infrared heat detectors and spot type electrical heat detectors.

Portable and mobile extinguishers, such as pressurized water type, carbon
dioxide type, foam type, dry chemical powder (DCP) type located at strategic
locations throughout the plant.

Fire tenders/engines of water type, DCP type/foam type, trailer pump with fire
jeep etc. provided in the fire station.

Complete instrumentation and control system for the entire fire detection and
protection system for safe operation of the complete system.
6.11
Other safety Measures
Considering that fire and explosion is the most likely hazard in such installations, the
plant is being provided with systems to guard against such hazards. Salient among
these are: A proper layout to prevent and minimize the effects of any hazardous
situation
 Design of storage vessels and all components to codes and standards to
withstand the rigorous duty
 Provision of operating systems to conduct the process through wellestablished safe operating procedures
 A control system, which monitors all plant parameters and give alarms
 Control system, which has trip provisions to prevent hazard conditions
escalating
 A gas detection system which will provide early warning of any leaks
Bhagavathi Ana Labs Ltd., Hyderabad.
72
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 Provision of a fire protection system to control fire
 Provision of flame-proof lighting system in the fire prone areas
6.12
Proposed First Aid And medical Facilities
The First Aid Medical Centre has been proposed. It will be fully equipped with
emergency facilities. It will be open round the clock. A Medical Officer with
Compounder will always be available in the centre. Emergency cars will be available
in all the shifts. Adequate number of first aid boxes will be kept at strategic locations.
Required stock of first aid medicines will be maintained. Trained first aiders will be
available in all departments.
Facilities to be kept in the Medical Room along with others will include: Oxygen
Cylinders, Injection Corarnine, Glucose Saline, LV. Sets, Syringes, Injection Needles,
Stretchers and medicines.
6.13
Proposed Emergency Power Supply
Strategic areas will be provided with emergency lights fed through station battery
system. Portable emergency lamps will be also available at required points. A Diesel
Driven Generator of adequate capacity will be available to keep the operations
running in case of power failure. Diesel Engine operated fire pumps will be available.
6.14
Off Site Emergency Plan
Objective
If the effects of the accident or disaster inside the plant are felt outside its premises, it
calls for an off-site emergency plan, which should be prepared and documented in
advance in consultation with the District Authorities.
Key Personnel
The ultimate responsibility for the management of the off-site emergencies rests on
the Collector / District Magistrate / Deputy Commissioner. He will be assisted by
representatives from all concerned organisations, departments and services at the
District level. This core group of officers would be called the District Crisis
Management Group (CMG). The members of the group will include:

Collector/District Magistrate Deputy Commissioner
Bhagavathi Ana Labs Ltd., Hyderabad.
73
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II

Commissioner of Police

Municipal Commissioner, if municipalities are involved

Deputy Director, Health

Pollution Control Board Representative
An Operation Response Group (ORG) will then have to be constituted to implement
the directives of the CMG.
The various government departments, some or all of which will be concerned,
depending on the nature of the emergency, could include:

Police

Health & Family Welfare

Medical

Revenue

Fire Service

Transport

Electricity

Animal Husbandry

Agriculture

Civil Defence

PWD

Civil Supplies

Panchayats
The SC and IC, of the on-site emergency team, will also be responsible for
communications with the CMG during the off-site emergency.
Education to Public
People living within the influence zone should be educated on the emergency in a
suitable manner. This can be achieved only through the Local and District
Authorities. However, the Project Authority will extend necessary information to the
Authorities.
Bhagavathi Ana Labs Ltd., Hyderabad.
74
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Chapter – 7
Project Benefits
7.0
Benefits
Jamkhandi Sugars Limited,has proposed Enhancement from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW Cogeneration Unit at Nad KD village , Indi Taluk , Bijapur
district , Karnataka state.
This project development will give rise to social and economic development measures in the
study area.
7.1
Improvement in Physical Infrastructure
The Enhancement project is expected to yield a positive impact on the socio-economic
environment. It helps in sustainable development of this area including further development
of physical Infrastructural facilities. The following physical infrastructure facilities will improve
due to proposed project: Road Transport facilities
 Educational facilities
 Water supply and sanitation
7.2
Improvement in Social Infrastructure
The Enhancement project will lead to direct and indirect employment opportunity.
Employment is expected during civil construction period, in trade, garbage lifting, sanitation,
plantation works and other ancillary services. Employment in these sectors will be primarily
temporary or contractual and involvement of unskilled labour will be more. This will enhance
their income and lead to overall economic growth of the area.
The following changes in socio-economic status are expected to take place with this project.
The project will have a strong positive employment and income effect, both direct as well as
indirect because of better indirect employment opportunities due to this project. The project
is going to have positive impact on consumption behavior by way of raising average
consumption and income through multiplier effect. The project is going to bring about
Bhagavathi Ana Labs Ltd., Hyderabad.
75
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
changes in the pattern of demand from food to non-food items and sufficient income is
generated. Following development of social infrastructures will be carried out:-.
 Education facilities
 Banking facilities
 Post offices and Communication facilities
 Medical facilities
 Recreation facilities
 Business establishments
 Community facilities
7.3
Places of Historical Importance
There is no historical or archaeological monument within 10 km of the area. Industrial
development and consequent economic development will lead to improvement in the living
standards of the people and enhanced social awareness. On the other hand, the
Enhancement project is likely to have several benefits like improvement in indirect
employment generation and economic growth of the area, by way of improved infrastructure
facilities and better socio-economic conditions.
7.4
Other Tangible Benefits
The Expansion project is likely to have other tangible benefits as given below: Indirect employment opportunities to local people in contractual works like housing
construction, transportations, sanitation, for supply of goods and services to the
project and other community services;
 Additional housing demand for rental accommodation will be increased;
 Market and business establishment facilities will be alsoincreased;
 Cultural, recreation and aesthetic facilities will be improved;
 Improvement in communication, transport, education, community development and
medical facilities.
Bhagavathi Ana Labs Ltd., Hyderabad.
76
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Chapter – 8
Environmental Management Plan
8.0
Introduction
The Environment Management Plan describes both generic good practice measures and
site-specific measures so as to mitigate potential impacts associated with the proposed
activities. The Environmental Management Plan (EMP) of the Expansion plant with respect
to noise, air quality, water quality, solid waste, ecology, landscape socio-economic measure
are summarized below:The EMP provides a delivery mechanism to address potential adverse impacts and to
introduce standards of good practice to be adopted for all project works. For each stage of
the program, the EMP lists all the requirements to ensure effective mitigation of every
potential environmental attribute and socio-economic impacts. For each impact type during
construction and operation the following information is presented: A comprehensive listing of the mitigation measures (actions) that are needed to
implement;
 The parameters that will be monitored to ensure effective implementation of the
action;
 The timing for implementation of the action to ensure that the objectives of
mitigation are fully met.
8.1
Environmental Management Plan during Construction Phase
8.1.1
Air Environment
The setting up of enhanced project from 2500 to 3500 TCDof Sugar Plant and 15 MW to 27
MW of Cogeneration power plantwould result in increase of dust concentrations due to
fugitive dust. Frequent water sprinkling in the vicinity of the construction sites would be
undertaken and will be continued after the completion of plant construction, as there is scope
for heavy truck mobility. It will be ensured that both petrol and diesel powered vehicles are
properly maintained to comply with exhaust emission requirements.
8.1.2
Noise Environment
There will be marginal increase in noise levels during construction phase, which is temporary
and intermittent.
Bhagavathi Ana Labs Ltd., Hyderabad.
77
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
8.1.3
Jamkhandi Sugars
Limited – Unit II
Water Environment
During construction, provision for infra-structural services including water supply, sewage,
drainage facilities and electrification will be made.
8.1.4
Land Environment
Any hazardous material required for constructional activity will be stored as per safety
norms. Further construction site will be provided with suitable toilet and treatment facilities
etc for maintaining hygienic conditions.
8.1.5
Socio-economic Environment
Any construction activity will benefit the local population in a number of ways. The company
management will give preference to local eligible people through both direct and indirect
employment. It will provide ample opportunity to the locals to up-lift their living standards by
organizing events that propagate mutual benefits to all, such as health camps, awareness
campaigns, donations to poorer sections of society and down-trodden.
8.1.6
Safety and Health
Adequate space will be provided for construction of temporary sheds for construction
workers mobilized by the contractors. M/s Jamkhandi Sugars Limited will take care of supply
of potable water for the construction workers. The safety department will supervise the safe
working of the contractor and their employees. Work spots will be maintained clean,
provided with optimum lighting and enough ventilation to eliminate dust/fumes. A
comprehensive Occupational Health and Safety management plan is put in place to address
any sort of eventuality.
8.2
Environmental Management Plan during Operations Phase
8.2.1
Air Environment
The major pollutants emerged due to Sugar Plant and Cogeneration Plant operations are
suspended particulate matter(SPM), fine particulate matter (PM10& PM2.5), Sulphur dioxide
(SO2) and Oxides of Nitrogen (NOx).
 All sources of dust generation in the Sugar Plant with Cogeneration Plant shall be
well designed for producing minimum dust and shall be provided with high efficiency
Bag filters and ESP.
Bhagavathi Ana Labs Ltd., Hyderabad.
78
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 Particulate Matter emission level from the stack chimney will be less than 50 mg/Nm3
and the stack height is proposed to 90 m.
 SO2 concentration will be negligible as the bagasse will be used as fuel for boiler.
 The periodic evaluation for the efficiency performance of ESP will be carried out.
 For controlling fugitive dust, in hopper, reclaimer, conveyors, silos etc. bag filters
shall be installed.
 Fugitive emissions due to storage, transportation, etc. and the leakages and spillages
shall be continuously monitored and controlled.
 Water conservation measures shall be undertaken for effective implementation.
Cooling water is put into closed circuit to minimize the evaporation losses.
 Thermal insulation will be provided wherever necessary to minimize heat radiation
from the equipment, piping etc., to ensure protection of personnel.
8.2.2
Noise Environment
 All rotating items are well lubricated and provided with enclosures as far as possible
to reduce noise.
 The design features of machineries shall be provided to ensure low noise levels in
the working areas.
 Extensive vibration monitoring system will be provided to check and reduce
vibrations. Allfans, compressors etc., are provided with vibration isolators to reduce
vibration and noise.
 Noise generating equipment including fans, blowers, pumps, motors etc.,will be
running with speed less than 1500 rpm and reduce noise levels.
 Provision for silencers wherever possible.
 Green belt development will be done and it will act as noise reducers.
 Requisite enclosures will also be provided on the working platform/areas to provide
local protection in high noise level areas.
 All heavy earthmoving equipment will be kept in a well maintained condition.
 Proper lubrication and house equipment will be kept in better condition
 Necessary PPE will be provided such as ear plugs, ear muffs etc.
By these measures, it is anticipated that noise levels in the plant will be maintained within
the permissible limits at the boundary of the plant premises. Plantation on the periphery of
the plant would further attenuate noise levels.
Bhagavathi Ana Labs Ltd., Hyderabad.
79
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
8.2.3
Jamkhandi Sugars
Limited – Unit II
Solid Waste Management
Dry fly ash and furnace bottom ash
Fly ash collected from the ESP hoppers and the airheaters hoppers and the ash collected
from the furnace bottom hoppers can be used as landfill. The ash content in bagasse is less
than 2%. The total fly ash 21.7 TPD will be used as a landfill. The high potash content in the
bagasse ash makes the ash as good manure.
Press mud of 140 TPD will be sold to farmers as manure.
The liquid molasses 140 TPD will be sent to distillery for manufacture of alcohol.
Sewage from various buildings in the plant
Sewage from various buildings in the plant area will be conveyed though separate drains to
the septic tank. The effluent from septic tank will be disposed in soil by providing disposing
trenches. There will be no ground pollution because of leaching due to this. Sludge will be
used as manure for green belt development.
8.2.4
Water and Wastewater Management
Continuous efforts would be made to reduce the water consumption and thereby to reduce
the wastewater generation. Flow meters would be installed for all major water inlet and the
flow rates would be continuously monitored. Periodic water audits would be conducted to
explore the possibilities for minimization of water consumption.
Water will be drawn from Bhima River to meet the plant consumptive water requirement.
Considering the quality of water, the Cycle of Concentration (COC) of the cooling tower is
considered as 1.5.
Waste water Management
The treated water quantity will be used for dust suppression.
Water Pollution control measures to be undertaken are given as under: No trade effluent shall be discharged from the Plants
 Cooling water is put into closed circuit to minimize the evaporation losses
 The domestic sewages from the Plants, Sugar Plant with Cogeneration Unit and
Township shall be treated in the Sewage Treatment Plant to meet the Statutory
Discharge Norms and the treated sewage shall be used for Green Belt;
 No percolation of treated water to deep ground water table is done.
 Periodical monitoring for specific parameters shall be done regularly.
Bhagavathi Ana Labs Ltd., Hyderabad.
80
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 Rainwater harvesting structures shall also be developed as proposed from the roof
tops of Plants as well as Township areas to supplement the water supply from the
river.
Wastewater treatment
Waste water treatment for the plant will be based on discharges of the various effluents to
ponds for clarification and filtration. Oily water will be treated separately to remove oil/grease
before discharge into effluent ponds. The oily water collection in the plant is basically due to
floor cleaning, leaky oil filters, etc.
Clarification is used to settle out large suspended particles and condition smaller colloidal
particles to make them settle. A pond, reservoir tank or tank is used to allow larger particles
to settle in a matter of hours. The finer particles overflow and are made to settle more quickly
by the addition of chemical agents, coagulants and polymers that cause agglomeration to
sizes large enough to settle out of suspension.
As required and with approvals from appropriate regulating bodies, final waste stream pH is
controlled by combining various plant streams to provide a neutral pH product. Where
needed, acid or alkali addition will be used to achieve the final pH.
Final Disposal of the wastewater
The treated effluent from the effluent tank will be used for horticulture and green belt
development within the plant.
Monitoring of Wastewater Treatment
The treated effluent would be monitored regularly for the flow rate and quality to identify any
deviations in performance of Effluent treatment plant.
Thermal Pollution Management
A closed circuit cooling water system with cooling towers is present in the existing area. This
eliminates the letting out of high temperature water into the canals and prevents thermal
pollution. Blow down from the cooling tower will be trenched out and ultimately conveyed to
the effluent ponds. Hence, there is no separate pollution on account of blow down from
cooling water system.
8.4
Rain Water harvesting System
Rain Water harvesting System
The rain (storm) water from the building roofs, non-process area and grade level surfaces
will be directed through the rain water harvesting structures and excess water will be
directed through open drains to the storm drainage system. The storm water from the storm
Bhagavathi Ana Labs Ltd., Hyderabad.
81
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
drainage system will be discharged outside the plant boundary. All drains will be lined and
will be arranged to provide the shortest possible drainage path for efficient drainage.
Rainwater Harvesting System (RWHS) designs and construction details are given below.
Figure :8.1 Rainwater Harvesting Structure
The plant may have an in-house environmental laboratory for the routine monitoring of air,
water, soil and noise. For all non-routine analysis, the plant may utilize the services of
external laboratories and facilities.
Surface Area Rainwater Harvesting
The unit is proposed rain water harvesting by way of surface run-off.
Surface area =244413.94 m2
Annual rainfall = 595mm
Considering Runoff co-efficient as 0.6
Total water recharged by harvesting = (Area X Annual Rainfall X Runoff coefficient for
surface) = 244413.94 x 0.595m x 0.6
Total water recharged by harvesting = 87255.7 m3
Bhagavathi Ana Labs Ltd., Hyderabad.
82
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Roof top Rainwater Harvesting
Rainwater Harvesting scheme is proposed and will be sought for suitable place within the
premises. The unit is proposed to rain water harvesting by way of capturing run-off from
rooftops.
The basic concept of harvesting rainwater is simple. Rainwater is mostly collected from the
roofs of buildings. It flows by gravity through gutters and downspouts into a storage tank.
Roof top area = 152341.8 m2
Annual rainfall = 595mm
Considering Runoff co-efficient as 0.85
Total water recharged by harvesting = (Area X Annual Rainfall X Runoff coefficient for roof
top) = 152341.8m2 x 0.595 m x 0.85
Total water recharged by harvesting = 77046.8m3
Figure :8.2 Rooftop Rain Water Recharge
Bhagavathi Ana Labs Ltd., Hyderabad.
83
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Figure :8.3 Design of Trench cum Injection Wells
The recharging pit i.e., the bottom basin of the recharging pit will be of size 15mx15mx4.5m
deep. The bottom basin will consist of many nos. of 100 mm dia PVC perforated pipes
installed upto the sand strata depth from the basin bed level. The perforated pipes will be
wrapped with coir, so that the water is filtered while passing to the ground. Hand rails will be
provided to the recharging pit at the top bench with hard footpath for safety purpose.
8.5
Housekeeping
Salient features of housekeeping will be adopted are as follows: Mechanized cleaning of roads and floor area inside the plant premises by using
road sweeper and mobile vacuum cleaner on regular basis;
 Training on regular basis to all workers and staff about the importance of
cleanliness;
 Careful garbage transportation to dumping site and disinfection of transport
vehicles body;
 Decorative plantation and gardening to improve aesthetics of the plant; and
 Construction of suitably designed drains all along the roads and boundary of the
plant premises.
Bhagavathi Ana Labs Ltd., Hyderabad.
84
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
8.6
Jamkhandi Sugars
Limited – Unit II
Occupational Health & Safety
During operation stage, dust causes the main health hazard. Other health hazards are due
to gas cutting, welding, noise and high temperature and micro ambient conditions especially
near the boiler and platforms, which may lead to adverse effects (Heat cramps, heat
exhaustion and heat stress reaction) leading to local and systemic disorders.
Table – 8.1
Health Evaluation schedule:
Frequency of Periodical Examination of Occupational Health
Occupation
Type of evaluation
Frequency
Cane Crushing Area
Pre-placement
Chest X-ray, spirometry
and vision testing
Sugar Process Area&
Cogeneration Area
Chest X-ray, spirometry
and vision testing
Noise prone areas
Main Control Room
Audiometry
Far & Near Vision; Colour
Vision; and Hearing tests
Ash Handling Area&
Bagasse Handling Area
Chest X-ray, spirometry,
Vision; and Hearing tests
Every 5 years to age <30;
Every 4 years to age 31-40;
and every 2 years to age 41-50;
Every 5 years to age <30;
Every 4 years to age 31-40;
and every 2 years to age 41-50;
Annually
Every 5 years to age <30;
Every 4 years to age 31-40;
And every 2 years to age 41-50;
Every 5 years to age <30;
Every 4 years to age 31-40;
And very 2 years to age 41-50;
The precautionary measures, which will be followed to reduce the risk due to dust on the
workers, engaged in and around the material handling areas:
 Adequate arrangements are made for preventing the generation of dust by
providing the chutes at transfer points to reduce the falling height of material,
preventing spillage of material by maintaining the handling equipment, isolating
the high dust generating areas by enclosing them in appropriate housing and
appropriately de-dusting through high efficiency bag filters;
 Massive plantation will be undertaken in the plant. The tree cover acts as a sink
for both gaseous as well as particulate matter.
 Due care will be taken to maintain continuous water supply in the water spraying
system and all efforts would be made to suppress the dust by water spraying at
appropriate points;
 All material handling systems are automatic. The workers engaged in material
handling system will be provided with personal protective equipment like dust
masks, respirators, helmets, face shields etc;
Bhagavathi Ana Labs Ltd., Hyderabad.
85
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 All workers engaged in material handling system will be regularly examined for
lung diseases such as PFT (Pulmonary Function Test) tests;
8.7
Design of Green Belt
Green belt development in around 33 % of the total plant area i.e. 32.35 acres will be developed.
Green belt of around 50 m width will be provided throughout the periphery of the existing
project site.
8.7.1 Green Belt and Plantation Plan
Green belt development in an industry is one of the most effective environmental pollution
control measures. Trees play vital role in keeping the ground level concentrations in control
within the plant premises and also in preventing the horizontal dispersion of the pollutants to
the surrounding areas. They are very effective in trapping the pollution causing agents viz.
dust and gaseous pollutants. They are also considered to be excellent indicators of
excessive ground level concentrations. The green belt is being proposed for the following
objectives.
Out of the total 98.04 acres of land, green belt will be developed 33% in 32.35 acres. Apart
from the bulk plantation around the boundaries, Roadside avenue plantations will also be
taken up. Based on the agro-climatic conditions of the region, location of the Sugar Plant
with Cogeneration Unit, physico-bio-chemical properties of the soil strata, nature of the
pollutants and their rate of dispersion, it is suggested to develop greenbelt around the plant.
Such green areas would improve the floral status and serve the dual purpose of arrest of any
fugitive dust from unpaved or open areas and also help to abate the noise effects through
dampening effects.
Table-8.2
Suggested Plant Species for Road Side Plantation
S. No.
Scientific Name
Vernacular name
1
Bauhimapururea
Kachnar
2
Leucaenaleucocephala
Subabool
3
Delonixregia
Gulmohar
4
Cassia fistula
Amaltas
5
Pongamiapinnata
Karanj
6
Samaniasaman
Rain tree
Table - 8.3
Bhagavathi Ana Labs Ltd., Hyderabad.
86
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Plant Species Suggested for Green Belt Development suggested by CPCB
S.No.
Botanical name of the
Size of the
Type and suitable site, where the
plant
grown up
plants are to be plotted
tree
1
Acacia auriculaeformis
Medium
Semi-evergreen fragrant white flowers
suitable in green belts and on road sides
2
Adina corodifolia
Large
Deciduous, a light demander, suitable on
open areas and near flares
3
Aeglemarmelos
Medium
Deciduous, good for green belts near
temples.
4
Anogeissuslatifolia
5
Artabotryshexapetaius
Medium
Small
Deciduous, Suitable for green belts
Evergreen shrub with fragrant flowers
good for gardens and inside boundary
wall and long canals
6
Averrhoacarambola
Small
Semi evergreen, good in narrow green
belts along the ash pond
7
Azadirachtaindica
Large
Evergreen, suitable in green belts along
the
boundary and
outside
office &
sensitive buildings like hospitals.
8
Bauhinia variegate
Medium
Deciduous, good in green belts in garden
and as a second row avenue tree
9
Borassusflabellifer
Large
A tall deciduous palm can be used as
wind break when of different age.
10
Boswelliaserrata
Medium
Deciduous suitable on green belt on
willow soils
11
Bureraserrata
Medium
Evergreen, suitable on willow soils as a
green belt or avenue tree
12
Buteamonosperma
Medium
Deciduous for green belt and as a second
row avenue tree
13
Caesalpiniapulcherrima
Small
A large shrub, suitable for gardens
outside offices and along channels
14
Callistemon
Medium
lanceolatus
15
Carevaaroborea
Bhagavathi Ana Labs Ltd., Hyderabad.
Deciduous for some time, ornamental
plant in garden
Large
Deciduous, good in green belts
87
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
S.No.
Jamkhandi Sugars
Limited – Unit II
Botanical name of the
Size of the
Type and suitable site, where the
plant
grown up
plants are to be plotted
tree
16
CarrisaCarandas
Small
Semi evergreen large bushy shrub good
as a hedge to protect against noise.
17
Carhotaurents
Large
18
Cassia fistula
Medium
A lofty palm, good as a wind break
Deciduous, good ornamental tree in
green belts.
19
C.siamea
20
Casuarinaequisetifolia
Large
Medium
Evergreen, good as an avenue tree.
Evergreen suitable for covering low lying
area and in green belts and along ponds.
21
Cedrelatoona
Large
Deciduous, good in open spaces, in
green belts and along ponds.
22
Ficusbengalensi
Large
Deciduous, widely spaced avenue tree
(15 m apart)
23
Ficusreligiosa
Large
Deciduous, widely spaced avenue tree
also as a single tree in isolated sites.
24
Maducaindica
Medium
Deciduous, good in green belts.
25
Peltophoruminerme
Medium
Semi evergreen, suitable on road sides,
in gardens and outside office buildings.
26
Saracaindica
Medium
Evergreen tree good on road sides within
campus
27
Tamarindusindica
Large
Evergreen tree good along boundary and
road sides.
28
Terminaliacatappa
Large
Deciduous tree
29
Terminaliaarjuna
Large
Evergreen tree for road sides and in
green belts
30
8.8
Zanthoxyium
Medium
Deciduous in green belts
Measures to Improve Socio-Economic Conditions
For the benefit of the community in the vicinity of the project, JSL will take several measures
to develop various amenities in an effort to improve standard of living, some of which are;
Capital budget of Rs.9.00 crores will be allotted for the following works in consultation with
local administration.
Bhagavathi Ana Labs Ltd., Hyderabad.
88
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant

Providing drinking water

Construction of schools

Construction of community centres

Construction of roads and drainage

Construction of health centres
Jamkhandi Sugars
Limited – Unit II
Table – 8.4
Corporate Social Responsibility (CSR) Budget
Description
S. No.
Amount in
Rs. Lakhs
1
Construction of schools, health centre, community centres, and
200
training program for local employable youth
2
Maintenance
of
water
supply,
village
roads,
drainage,
200
Health check-up camps, medical camps, logistic support,
200
development of parks, school buildings
3
Ambulance facility, Fire Safety, drug de-addiction movement
4
Providing scholarships to poor children, distributing books, adult
200
literacy
5
Home for disabledand orphanage
Total
8.9
100
900
Landscaping
The various serviceI utility areas within the plant will be suitably graded to different
elevations. Natural features of the plant site will be retained as far as possible to integrate
with the buildings to form pleasant environment. Areas in front of various buildings and the
entrance of Sugar Plant with Cogeneration Unit will be landscaped with ground cover, plants,
trees based on factors like climate, adaptability, etc. The green belt will consist of native
perennial green and fast growing trees. Trees will also be planted around the plant boundary
to minimize the dust pollution. Adequate afforestation will be carried out as per the
guidelines of MoEF.
8.10
Fire Fighting & Protection System
Safety Policy and Regulations
Bhagavathi Ana Labs Ltd., Hyderabad.
89
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Keeping in view of the safety requirement during construction, operation and maintenance
phase, M/s Jamkhandi Sugars Limited has formulated safety policy with the following
regulations: To allocate sufficient resources to maintain safe and healthy conditions at work
place.
 To take, steps to ensure that all known safety factors are taken into account in the
design, construction, operation and maintenance of plants, machinery and
equipment.
 To ensure that adequate safety instructions are given to all employees.
 To provide wherever necessary, protective equipment, safety appliances and clothing
and to ensure their proper use.
 To inform employees about materials, equipment or processes review for making
necessary changes from the point of view of safety in the light of experience and up
to date knowledge.
 To provide appropriate instruction, training and supervision in health and safety, first
aid and to ensure that adequate publicity is given to these matters.
 To ensure proper implementation of fire prevention and an appropriate fire fighting
service together with training facilities for personnel involved in this service.
 To ensure that professional advice is made available wherever potentially hazardous
situations exists or might arise.
 To organize collection, analysis and presentation of data on accident, sickness and
incident involving personal injury to health with a view to taking corrective, remedial
and preventive action.
 To prepare safety rules for each type of occupation/process involved in a project.
 To ensure regular safety inspection by a competent person at suitable intervals of all
buildings, equipment, work places and operations
Fire Protection System
 The plant has proposed adequate number of wall/column mounted type portable fire
extinguishers in various strategic areas of the plant including the control room,
administration building, stores, pump house etc. These portable fire extinguishers are
basically of carbon dioxide and dry powder type.
 Fire hydrants at suitable locations for TG building, boiler area, & storage area.
 Medium velocity water spray system for the cable gallery
Bhagavathi Ana Labs Ltd., Hyderabad.
90
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
 Necessary electric driven, Jockey pumps with piping valves & instrumentation for
safe operation.
8.11
Corporate Environment Policy
Corporate Responsibility for Environmental Management

The plant has an Environmental Management Committee headed by the Director &
Chief Operating Officer and comprises of key personnel in the plant. The Committee
meets regularly to review the status of various aspects of pollution control measures
will be implemented in the plant.

The unit has also initiated improvement measures to get ISO14001 certification.

Suggestion scheme has been launched and various suggestions given by the
workers and employees have been implemented in order to improve safety and
protect environment.

The unit has resolved to become a zero waste integrated agro business sugar
complex and in itscommitment to ensure zero discharge. Measures will be
implemented to recycle and reuse waste water to avoid effluent discharge into the
environment.

The unit complies with the various requirements and standards stipulated by Ministry
of Environment & Forests, Central Pollution Control Board and Karnataka Pollution
Control Board.

The unit recently commissioned a new mist cooling system with automation for
cooling the evaporator and pan condenser water.

Involvement of workmen in Safety Management through the Safety Committee which
is empowered to review accidents and initiate corrective and preventive action.

Ensuring high standards of housekeeping in the factory premises, resulting in a Safe
Shopfloor,

All personnel are trained on First Aid and basics of Safety Management.
Bhagavathi Ana Labs Ltd., Hyderabad.
91
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Chapter –9
Summary and Conclusions
M/s. Jamkhandi Sugars Limited has proposed for Enhancement of Sugar Unit from 2500
TCD to 3500 TCD and 15 MW to 27 MW Cogeneration Unit at Village Nad KD, Taluk Indi ,
District Bijapur and Karnataka state .
Salient Features of the project
 Capacity of the Plant:-Sugar Unit- 3500 TCD and Cogeneration Plant of 27 MW
capacity
 Project Area:-98.04 acres.
 Cost of the Project:-The total project cost is Rs.180 Crores
 Cost for Environmental Management Plan:- The capital cost for EMP measures is
Rs750 Lakhs and recurring cost is Rs65 lakhs.
 Cost for Corporate Social Responsibility:-The capital cost for CSR activities is Rs
9.00 crores .
3
 Water requirement:-The total Water requirement for the factory is nearly 2600m /day
during the crushing and during the slack season.Water will be sourced from Bhima River.
 Gross Power Generation:-Crushing Season:20,780 KW
Off-season:23,840 KW
 All liquid effluents will be suitably treated and consumed for internal use like landscaping
and green belt. The effluent will be neutralized by the addition of either acid or alkali to
achieve the required pH.
 All equipment vulnerable to explosion or fire will be designed to relevant IS codes &
statutory regulations. Suitable fire protection system comprising hydrants and spray
systems will be provided for fire protection.
 There will be an environment cell and qualified chief chemist in charge of analytical
measurements and qualified engineers for pollution control.
 The total employees required during plant operation are 91persons.
Conclusion
The potential environmental, social and economic impacts have been assessed. The
proposed Sugar Unit and Cogeneration Plant will have certain levels of marginal impacts
Bhagavathi Ana Labs Ltd., Hyderabad.
92
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
onthe local environment. Implementation of the project will have beneficial impact in terms of
providing direct and indirect employment opportunities. There will be a positive socioeconomic development in the region. Quality of life of the people will be improved.
Recommendations made in the CREP for Sugar Plant will be implemented.JSL will also
undertake various community welfare measures for the upliftment of the villages of the study
area.
Bhagavathi Ana Labs Ltd., Hyderabad.
93
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Jamkhandi Sugars
Limited – Unit II
Chapter–10
Disclosure of Consultants Engaged
Name of the Consultants:
M/s Bhagavathi Ana Labs Limited
8-2-248/5/A/42, Venkateswara Hills Colony
Road No. 3, Banjara Hills
Hyderabad – 500 034
Telephone – 040 - 23356908, 23348689
Fax – 040 – 23356909
Email: environ@bhagavathianalabs.com
Website: http://www.bhagavathianalabs.com
Bhagavathi Ana Labs Limited is a professional services company providing Environmental
Consultancy, Environmental Engineering, Analytical and Quality testing, Water Resource
studies, Technical Training and Enviro-legal services. Since inception in 1984, the company
has completed number of projects spread all over India. The company has qualified and
experienced staff of more than 100 people operating across seven offices in India. The
Professionals and Technicians include Environmental Engineers, Environmental Scientists,
Environmental Planners, Chemists, Mining Engineers, Geologists, Hydro-geologists,
Economic and Social Science specialists etc. Bhagavathi Ana Labs Limited is an ISO 90012000 Company and is accredited by:
 Ministry of Environment and Forests (MoEF), Govt. of India, New Delhi
 National Accreditation Board for Education & Training (NABET)
 Registered EIA Consultants Organization, Quality Council of India, Reg No: EIA 81
005
 National Accreditation Board for Testing and Calibration Laboratories (NABL) as per
ISO/IEC 17025:2005
 Bureau of Indian Standards (BIS), New Delhi
Bhagavathi Ana Labs Ltd., Hyderabad.
93
Draft EIA/EMP Report of enhanced from 2500 TCD to 3500 TCD Sugar
Plant and 15 MW to 27 MW of Co-generation Power Plant
Bhagavathi Ana Labs Ltd., Hyderabad.
Jamkhandi Sugars
Limited – Unit II
94
Download