(Contractor) SN099021 Page 1 of 9 EXHIBIT E EQUIPMENT LISTING 1.0 INTRODUCTION This is a list of the equipment that is to be part of the maintenance service. 2.0 SCOPE The following apparatus shall be tested in accordance with section 3.0 of this proposal. Switchgear for Sub-Station 2 FPE OPEN AIR SWITCH 2.1 Three (3) sections 2.1.1 One (1) Switch Ckt. #1 FPE Load Interrupter Switch 2.1.2 One (1) Switch Ckt. #4 FPE Load Interrupter Switch STEP DOWN TRANSFORMER 2.1.3 One (1) 1680 KVA Oil Transformer 12,000V Delta - 2,400V Delta MEDIUM VOLTAGE SWITCHGEAR, FEED BREAKERS 2.1.4 2.1.5 2.1.6 2.1.7 2.1.8 2.1.9 2.1.10 2.1.11 2.1.12 2.1.13 2.1.14 2.1.15 Ten (10) Section Switchgear Three (3) Potential Transformers One (1) Feeder Breaker M2, Howe -Yin - North 1200 Amp Vacuum Canister Breaker Four (4) Over Current Relays GE One (1) Buss Voltmeter One (1) Amp meter One (1) Control Transformer One (1) Feeder Breaker F2A Howe -Yin – North 1200 Amp Vacuum Canister Breaker Three (3) Over Current Relays GE One (1) Ground relay One (1) Amp meter One (1) Feeder Breaker F2B, Howe - Yin – North (Contractor) SN099021 Page 2 of 9 2.1.16 2.1.17 2.1.18 2.1.19 2.1.20 2.1.21 2.1.22 1200 Amp Vacuum Canister Breaker Three (3) Over Current Relays GE One (1) Ground Relay B&B One (1) Amp meter One (1) Feeder Breaker F2C, Howe - Yin – North 1200 Amp Vacuum Canister Breaker Three (3) Over Current Relays GE One Ground Relay B&B One (1) Amp meter Switchgear for Sub-Station 3 FPE OPEN AIR SWITCH 2.2 2.2.1 2.2.2 Three (3) Sections Switchgear One (1) Switch Ckt. #1 FPE Load Interrupter Switch One (1) Switch Ckt. #4 FPE Load Interrupter Switch STEP DOWN TRANSFORMER 2.2.3 2.2.4 Two (2) Section Transformer One (1) 1680 KVA Oil Transformer 12,000V Delta - 2,400V Delta SWITCHGEAR FEED BREAKERS 2.2.5 2.2.6 2.2.7 2.2.8 2.2.9 2.2.10 2.2.11 2.2.12 2.2.13 2.2.14 2.2.15 2.2.16 Ten (10) Section Switchgear Three (3) Potential Transformers One (1) Feeder Breaker M3, Howe - Yin - North 1200 Amp Vacuum Canister Breaker Four (4) Over Current relays GE One (1) Buss voltmeter One (1) Amp meter One (1) Control Transformer One (1) Feeder Breaker F3A Howe - Yin - North 1200 Amp Vacuum Canister Breaker Three (3) Over Current Relays GE One (1) Ground Relay B&B One (1) Amp meter One (1) Feeder Breaker F3B Howe - Yin - North (Contractor) SN099021 Page 3 of 9 2.2.17 2.2.18 2.2.19 2.2.20 2.2.21 2.2.22 2.2.23 1200 Amp Vacuum Canister Breaker Three (3) Over Current Relays GE One (1) Ground Relay B&B One (1) Amp meter One (1) Feeder Breaker F3C Howe - Yin - North 1200 Amp Vacuum Canister Breaker Three (3) Over Current Relays GE One (1) Ground Relay B&B One (1) Amp meter Additional Medium Voltage Breaker 2.3 3.0 One (1) Spare Breaker Cutler Hammer 1200 Amp Vacuum Canister Breaker PROCEDURES 3.1 Switchgear and Switchboard Assemblies – General 3.1.1 Visual and Mechanical Inspection .1 Documentation of equipment nameplate data. .2 Inspection for physical damage, electrical, and mechanical condition. .3 Inspection for proper alignment, anchorage, required area clearances and grounding. .4 Inspection all doors, panels, and sections for paint, dents, scratches, fit, and missing hardware. .5 Inspection for proper identification of protective devices and switches. .6 Verification of tightness of all bolted bus joint connections by calibrated torque-wrench method. .7 Cleaning of interior enclosures, insulator surfaces, cables, and bussing. Remove all exterior and interior panels as needed to clean and perform inspections. Inspect insulators for evidence of physical damage or contaminated surfaces. .8 Replace all space heaters located within the switchgear identified within this service contract. Replacement heaters are to match (Contractor) SN099021 Page 4 of 9 existing. Verify proper operation of space heaters and thermostat settings after replacement. .9 Cleaning and lubrication of operating mechanism per manufacture recommendations. .10 Verification that filters are in place and/or vents are clean and clear. .11 Verification of operating mechanism for alignment and clearances. 3.1.2 Electrical Tests .1 3.2 Measurement of insulation resistance of each bus section phaseto-phase and phase-to-ground. Medium Voltage Vacuum Circuit Breakers 3.2.1 Visual and Mechanical Inspection .1 Documentation of equipment nameplate data. .2 Inspection for physical damage. .3 Cleaning and lubrication of operating mechanism. .4 Inspection of breaker for cell alignment, anchorage and grounding. .5 Verification of operating mechanism for alignment and clearances. .6 Documentation of as-found and as-left operation counter readings. .7 Inspection of indicator for contact wear and measurement of critical distances such as contact gap in accordance with manufacturer's instructions. .8 Verification of tightness of accessible bolted connections by calibrated torque-wrench method. 3.2.2 Electrical Tests .1 Measurement of contact resistance. (Contractor) SN099021 Page 5 of 9 3.3 .2 Circuit breaker tripping by operation of each protective device. .3 Closing and tripping of the breaker with the local control switch and verification of trip, close, trip-free, and anti pump functions. .4 Insulation resistance testing phase-to-ground, phase-to phase and across open contacts. .5 Vacuum bottle integrity testing on each phase in accordance with manufacturer's instructions. Protective Relays 3.3.1 Visual and Mechanical Inspection .1 Documentation of equipment nameplate data. .2 Inspection of relays for physical damage. .3 Inspection for presence of foreign material, moisture, corrosion, condition of spiral spring and disc clearance on electromechanical relays. .4 Verification of tightness of case connections. Inspection of cover for correct gasket seal. Inspection of shorting hardware, connection paddles, and/or knife switches. Removal of any foreign material from the case. .5 Verification of target reset. .6 Cleaning of cover glass and relay components as required. 3.3.2 Electrical Tests .1 Testing of the following: • • • • • Pickup parameters on each operating element Timing at three points on time characteristic curve Pickup target and seal-in units, as applicable Verification of operation of indicators Special tests as required to check operation of restraint, directional and other elements. .2 On electro-mechanical relays only, testing of insulation resistance on each circuit branch to frame. .3 Verification that each of the relay contacts operates its associated device. (Contractor) SN099021 Page 6 of 9 3.4 Metering and Instrumentation 3.4.1 Visual and Mechanical Inspection .1 Documentation of device nameplate data. .2 Inspection of all devices for physical damage and connection tightness. .3 Verification of all instrument multipliers and scale factors. 3.4.2 Electrical Tests .1 3.5 Calibration of all panel meters at all cardinal points. Transformers – Liquid Filled 3.5.1 Visual and Mechanical Inspection .1 Documentation of equipment nameplate data. .2 Inspection for physical damage, proper installation, anchorage and grounding. .3 Cleaning of all bushing and insulator surfaces. .4 Verification of dielectric liquid in tank and bushings for proper level and leaks. .5 Documentation of pressure gauge reading, if applicable. .6 Verification that final tap setting is as specified. .7 Verification of tightness of external bolted electrical connections. 3.5.2 Electrical Tests .1 .2 .3 Insulation resistance testing winding-to-winding and winding toground. Turns ratio testing between windings for set tap position. Verification that winding polarities are in accordance with nameplate. Measurement of resistance of each high-voltage winding in the as-found no-load tap-changer position. Measurement of (Contractor) SN099021 Page 7 of 9 resistance of each low-voltage winding at the as-found load tapchanger position, if applicable. .4 Dielectric absorption testing from winding-to-winding and windingto-ground for ten minutes. Calculation of then polarization index. .5 Sampling of insulating oil in accordance with ASTM D-923. Sample is laboratory tested for: • • • • • • .6 3.6 Dielectric strength: ASTM D-877 Acid neutralization number: ASTM D-974 Interfacial tension: ASTM D-971 Color number: ASTM D-1500 Visual Condition: ASTM D-1524 Moisture content: ASTM D-1533 Sampling of insulating liquid in accordance with ASTM D3613 and performance of dissolved gas analysis (DGA) in accordance with ANSI/IEEE C5704 or ASTM D-3612. Molded Case Circuit Breakers 3.6.1 Visual and Mechanical Inspection .1 Documentation of equipment nameplate data. .2 Inspection of circuit breaker for physical damage. .3 Verification of circuit breaker smooth operation. .4 Verification of tightness of accessible bolted connections and/or cable connections by calibrated torque-wrench method. 3.6.2 Electrical Tests .1 Measurement of contact resistance by millivolt drop method at trip unit rated current or by digital low resistance ohmmeter method. .2 Measurement of long-time delay by primary current injection at three times long-time pickup current. .3 Measurement of instantaneous pickup current by primary current injection. .4 Insulation resistance testing from pole-to-pole and from each poleto-ground with breaker closed and across open contacts of each phase. (Contractor) SN099021 Page 8 of 9 3.7 Automatic Transfer Switches 3.7.1 Visual and Mechanical Inspection .1 Documentation of equipment nameplate data. .2 Inspection for physical damage and anchorage. .3 Verification of proper manual transfer operation. .4 Verification that manual transfer instructions and warning labels are installed and visible. .5 Cleaning and lubrication of transfer mechanism, as required. Verification of alignment and operation in accordance with manufacturer's instructions. .6 Verification of tightness of all cable connections, control connections and bus joints. 3.7.2 Electrical Tests .1 Verification of operation and timing of the following items as applicable: • • • • • • • • • "Normal" voltage sensing relays "Alternate" voltage sensing relays Test switch Engine start sequence Time delay upon transfer Alternate voltage sensing relay Time delay and re-transfer upon normal power restoration Engine cool-down time delay and shutdown In-phase monitor .2 Contact resistance measurements on each pole. .3 Insulation resistance testing of phase-to-phase and phase toground with switch in both source positions. .4 Verification of setting and calibration in accordance with customer's specifications: • • • • "Normal" voltage sensing relays "Emergency" voltage sensing relays Time delay for engine start Time delay transfer to emergency (Contractor) SN099021 Page 9 of 9 • • 3.8 Time delay for re-transfer upon normal power restoration Engine cool-down time delay Additional Conditions and Services 3.8.1 Testing Equipment .1 All meters, and associated testing equipment are to have been calibrated, certified and identified as such within the last year. .2 Contractor is to attach a self-adhering label to each piece of equipment tested. This label is to be approximately two inches by two inches and have the following information: • • • • Name of Company performing service. Telephone number of the Company. Name of the person performing the service on the specific piece of equipment. The date that the service was performed. 3.8.2 Replace Strip Heaters .1 The Contractor is to identify the type and number of strip heaters located within the switchgear to be addressed in this service contract prior to any shutdowns. .2 At the time of the shutdown, the Contractor is to replace all strip heaters with exact type located within the switchgear, and identify the date of installation on the specific heater.