INTERNATIONAL JOURNAL OF ENERGY RESEARCH Int. J. Energy Res. (2009) Published online in Wiley InterScience (www.interscience.wiley.com). DOI: 10.1002/er.1573 Investigation of the distributed generation penetration in a medium voltage power distribution network G. N. Koutroumpezis, A. S. Safigianni,y, G. S. Demetzos and J. G. Kendristakis Electrical and Computer Engineering Department, Democritus University Thrace, GR 67100, Xanthi, Greece SUMMARY This paper investigates the results of the distributed generation penetration in a weak medium voltage power distribution network. The connected distributed generation resources are in their entirety small hydroelectric plants. Their locations are predetermined. Specifically, the influence of distributed generation on the network branch currents and voltage profile as well as on the short-circuit level at the medium voltage busbars of the infeeding substation are examined using a commercial-grade software package. The arising problems are explored and alternative technical solutions to deal with them are proposed. Finally, an initial proposal for an optimum distributed generation penetration in the predetermined network positions is given. A real-world study case, rather than a simplified academic network, is selected to be analysed in order to specify, as accurately as possible, the arising practical problems and to use this experience in the future in the development of a fast and reliable method for the determination of optimal distributed generation allocation in random network positions. Copyright r 2009 John Wiley & Sons, Ltd. KEY WORDS: distributed generation; medium voltage distribution network; short-circuit level; voltage profile 1. INTRODUCTION Distributed generation (DG) is a new approach in the electricity industry. In the literature, a large number of terms and definitions are used in relation to DG, such as ‘embedded generation’, ‘dispersed generation’ and ‘decentralised generation’. As the analysis of the relevant literature shows, there is as yet no generally accepted definition of DG [1,2]. The different issues to be discussed [2] in order to define DG more precisely are its purpose, its location, its rating, the power delivery area, the technology, its environmental impact, its mode of operation, its ownership and its penetration. A general definition for DG suggested in [2], which is now widely accepted, reads as follows: ‘DG is an electric power source connected directly to the distribution network or on the customer site of the meter’. The distinction between distribution and transmission networks is based on the legal definition. The above definition of DG does not define the rating of the generation source, as the maximum rating depends on the local distribution network conditions, e.g. voltage level. *Correspondence to: A. S. Safigianni, Electrical and Computer Engineering Department, Democritus University Thrace, GR 67100, Xanthi, Greece. y E-mail: asafig@ee.duth.gr Copyright r 2009 John Wiley & Sons, Ltd. Received 27 November 2008 Revised 27 April 2009 Accepted 9 May 2009 G. N. KOUTROUMPEZIS ET AL. It is, however, useful to introduce categories of different ratings of DG. The following categories are suggested: Micro distributed generation: 1 Watto5 kW; Small distributed generation: 5 kWo5 MW; Medium distributed generation: 5 MWo50 MW; Large distributed generation: 50 MWo300 MW. Furthermore, this definition neither defines the area of the power delivery, the penetration, the ownership nor the treatment within the network operation. It also does not define the technologies used, which can vary widely. The categories of renewable and non-renewable DG are suggested as possible. DG is now being connected at distribution level, which has led to the characteristics of the network being changed [3]. Existing distribution networks are passive in that they were designed and built purely for the delivery of electricity to customers. The introduction of DG is changing the characteristics of the distribution networks. It has led to increased and bi-directional active and reactive power flows, along with wider variation in voltage levels, both of which affect the operation of equipment on the network and the extent of losses. Distribution networks are also characterised by a design short-circuit capacity. As the level of installed capacity increases, in the case of DG penetration, it is a fundamental requirement that the maximum short-circuit rating for all equipment is not exceeded. The above changes to the use of the network together with the potentially high penetration of DG have led to the need for an effective and easily used technique to optimise both the rating and positioning of these generators within an established network. The issues that need to be considered in the choice of rating and positioning of DG include both technical and commercial factors [4–12]. The technical issues include the adequacy of the network’s and associated plant’s thermal rating, fault levels and sufficient voltage support to insure both the security and quality of electricity supply. The commercial issues include the cost of DG, installation charges, operating Copyright r 2009 John Wiley & Sons, Ltd. costs, revenue expectations and the value of reduced losses in the network. Specifically in [4], the authors employ an optimal power flow technique to maximise DG capacity with respect to voltage and thermal constraints. In [5], genetic algorithms were used to place generation such that losses, costs and network disruption were minimised and the rating of the generator maximised. The constraints considered were voltage, the thermal short circuit and generator active and reactive power capabilities. In [6], a determination of the allowable DG penetration level is carried out based on the harmonic limit consideration, which is restricted to radial distribution feeders with a uniform, linearly increasing or decreasing load pattern. The methodology of [7] determines the optimal DG allocation with respect to technical constraints such as voltage and thermal current constraints, equipment ratings and short-circuit levels. The basis for this methodology is in exploiting the interdependence, if any, of the buses with regard to the constraints. The constraints all have either linear or approximately linear characteristics with respect to increasing power injections, or they place a fixed and independent limit on the power injection. The authors of [8] apply tabu search techniques to locate DGs and minimise overall power losses. The authors of [9] present a genetic algorithm approach that, for a defined planning horizon, minimises the cost of network investment and losses whilst meeting feeder thermal, voltage profile and fault-level constraints. In [10], a combination of fuzzy non-linear goal programming and genetic algorithm techniques is used to locate DGs and minimise overall power losses. In [11], the authors use a heuristic approach to determine the optimal DG size and site from an investment point of view. In [12], a multi-objective procedure for optimal DG siting and sizing is proposed. The goal of the methodology is to establish the best penetration level of DG, which maximises the benefits of the presence of generators in a distribution network as well as limits the network performance deterioration due to DG not being connected in optimal locations. Finally, [13] describes a new model of energy infrastructure, which consists of integrating different kinds of DG Int. J. Energy Res. (2009) DOI: 10.1002/er INVESTIGATION OF THE DISTRIBUTED GENERATION PENETRATION utilities in an energy (electricity and heat) generation network controlled by a central energy management system referred to as virtual utility. This paper investigates the results of DG penetration in a weak medium voltage (20 kV) network. The network is located in West Macedonia, Greece. The connected DG resources are in their entirety small hydroelectric plants with a total capacity of about 11.5 MW. Their locations are predetermined. Specifically, the influence of DG on the network branch currents and voltage profile as well as on the short-circuit level (SCL) at the medium voltage busbars of the infeeding substation are examined using a commercial-grade software package. The arising technical problems are explored and solutions (alternative DG connection, reconductoring) are proposed. An initial proposal for optimum DG penetration in the predetermined network positions is also given. A real-world study case, rather than a simplified academic network, is selected to be analysed in this paper to specify, as accurately as possible, the arising practical problems and to use this experience in the future in the development of a fast and reliable method for the determination of optimal DG allocation in random network positions. 2. TECHNICAL CONSTRAINTS The following constraints are taken into account during the investigation of DG penetration in the examined network: Thermal Constraint: the rated current of the lines, Iirated, must not exceed ð1Þ Ii oIirated where Ii stands for the current flowing at each branch. Transformer Capacity: the amount of generation connected minus the minimum load must not exceed the rating of the transformer at the higher voltage. SCL Constraint: distribution networks are characterised by a design short-circuit capacity, i.e. a maximum fault current never to be exceeded, related to the rating of switchgear and the thermal and mechanical endurance of all Copyright r 2009 John Wiley & Sons, Ltd. equipment and standardised constructions [14]. Hence, a basic requirement for permitting the interconnection of DG is to ensure that the resulting SCL remains below the network design value (SCLrated). The SCL is highest at the medium voltage transformer busbars (SCLmax). The following relation gives the constraint: SCLmax oSCLrated ð2Þ Voltage Variation Constraint: when DG units are connected at the distribution network, the generator voltage will be the load/bus voltage plus some value related to the impedance of the line connecting them and the power flows along that line [7,15]. The increased active power flows on the distribution network have a large impact on the voltage level because the resistive element of the lines on distribution networks is higher than other lines. The following relation gives the constraint: ei % ¼ Ui UT 100pjemax %j i8N U ð3Þ mean where ei is the voltage variation and Ui is the voltage value at the ith bus, UT is the voltage value at the substation busbars (UTmin for minimum load and UTmax for maximum load, determined by the marginal operation of the transformer tap changer), Umean is the mean voltage value at the substation busbars, emax the permissible voltage variation and N is the number of buses. The constraint is usually examined for minimum load, as this is the worst-case scenario for voltage rise. 3. NETWORK DESCRIPTION Figure 1 shows the examined distribution network with DG penetration. This network is situated in West Macedonia, Greece. It is one of the main medium voltage lines (named line 23) fed by a 25 MVA, 150/20 kV substation. There are also three other main lines, which stem from this substation. Line 23 is a radial network having mainly overhead Int. J. Energy Res. (2009) DOI: 10.1002/er G. N. KOUTROUMPEZIS ET AL. Figure 1. Network diagram. lines. The main feeder consists mostly of 95 mm2 ACSR conductors, but there are also many lateral branches consisting of 16 mm2 ACSR conductors. The main buses such as lateral branch origins or load positions are marked with the letter P in Figure 1, whilst the letter S is used for the secondary buses. DG units of a total power of about 11.5 MW are connected in four network positions (P6, P19, P29 and P31). All these resources are small hydroelectric plants. Also given in Figure 1, except for the conductor sizes, are the branch lengths and the installed maximum loads in Amperes, all coincident to the maximum load of the main feeder, which is equal to 110 A (or equally about 4 MVA). Analytical data for all the network components are given in Table I. 4. NETWORK STUDY Taking into account that the total DG penetration is 11.52 MW or about 11.52/0.95 5 12.12 MVA and that the minimum network load is about 20 A or equally 0.706 MVA, their difference is about 11.5 MVA, which is smaller than the substation rating (25 MVA). There is no DG penetration in the other feeder stem from the 25 MVA substation. So the second constraint of Section 2 (transformer capacity) is not breached. Copyright r 2009 John Wiley & Sons, Ltd. The other constraints concerning the conductor rated currents, the voltage profile of the network and the SCLmax are examined by using the NEPLAN software package [16] for power flow analysis and short-circuit computation. Especially for the SCL computation, the IEC60909 [17–20] is used. First, power flow analysis is executed to calculate the branch currents and the bus voltages of the network given in Figure 1 for minimum load and voltage supply (UTmin ¼ 20:4 kV). The results of this analysis according to the branch currents are that these currents are very small without DG penetration. They become much bigger when the DG units are connected to the predetermined network buses, because of the increased power flow, but they remain smaller than the rated conductor currents. So the first constraint (thermal constraint) of Section 2 is not breached. The bus voltage variation is given in Table II according to relation (3) for minimum load. As Table II shows, the permissible voltage variation (73% of the mean voltage value at the substation busbars, which is equal to 21 kV, is the value which the Public Power Corporation demands) is not exceeded when no DG connection exists. But when all the DG units are connected to the network there is an impermissible voltage rise at the buses of the route P4-P8, P9 and a marginally Int. J. Energy Res. (2009) DOI: 10.1002/er INVESTIGATION OF THE DISTRIBUTED GENERATION PENETRATION Table I. Network data. Network Feeder Q UnQ 5 150 kV, SCLQ 5 197 MVA, RQ/XQ 5 0.1 Network Transformer SCLrated 5 250 MVA, SrT 5 25 MVA, tr. 5 150/20 kV, UTmax 5 21.4 kV, UTmin 5 20.4 kV, UmeanE21 kV HEP West Greece Participations S.A. 1, 1.66 MW Generator G1 Synchronous, PELTON, PrG1 ¼ 1:66 MV, UrG1 ¼ 660 V, x00d1 ¼ 0:131 p.u., xd1 ¼ 2:39 p.u., cos jrG1 ¼ 0:95 (inductive) Transformer T1 SrT1 ¼ 2 MVA, trT1 ¼ 20=0:66 kV, ukrT1 ¼ 5:66%, uRrT1 ¼ 1% HEP West Greece Participations S.A. 2, 2 1.58 MW Generators (G2, G3) Synchronous, PELTON, PrG23 ¼ 1:58 MW, UrG23 ¼ 660 V, x00d23 ¼ 0:133 p.u., xd23 ¼ 2:4 p.u., cos jrG23 ¼ 0:95 (inductive) Transformers T2,T3 SrT23 ¼ 2 MVA, trT23 ¼ 20=0:66 kV, ukrT23 ¼ 6:25%, uRrT23 ¼ 1% PPC Renewables S.A., 1.5 MW13.2 MW Generator G4 Synchronous, PELTON, PrG4 ¼ 1:5 MW, UrG4 ¼ 660 V, x00d4 ¼ 0:14 p.u., xd4 ¼ 1:5 p.u., cos jrG4 ¼ 0:95 (inductive) Generator G5 Synchronous, FRANCIS, PrG5 ¼ 3:2 MW, UrG5 ¼ 6:3 kV, x00d5 ¼ 0:23 p.u., xd5 ¼ 2:5 p.u., cos jrG5 ¼ 0:95 (inductive) Transformer T4 SrT4 ¼ 2 MVA, trT4 ¼ 20=0:66 kV, ukrT4 ¼ 6:0%, uRrT4 ¼ 1% Transformer T5 SrT5 ¼ 4 MVA, trT5 ¼ 20=6:3 kV, ukrT5 ¼ 6:0%, uRrT5 ¼ 1% HEP Distratou, 2 MW Generator G6 Synchronous, PrG6 ¼ 2 MW, UrG6 ¼ 690 V, x00d6 ¼ 0:133 p.u., x0d6 ¼ 0:24 p.u., xd6 ¼ 1:77 p.u., cos jrG6 ¼ 1 Transformer T6 SrT6 ¼ 2 MVA, trT6 ¼ 20=0:69 kV, ukrT6 ¼ 5:0%, uRrT6 ¼ 1% Medium Voltage Lines Overhead lines ACSR 16 mm2: RL20 C ¼ 1:098 O=km, XL 5 0.393 W/km, Irated 5 127 A ACSR 35 mm2: RL20 C ¼ 0:52 O=km, XL 5 0.369 O/km, Irated 5 197 A ACSR 95 mm2: RL20 C ¼ 0:192 O=km, XL 5 0.336 O/km, Irated 5 400 A Bunched cable 3 150 mm2: RL20 C ¼ 0:2375 O=km, XL 5 0.125 O/km, Irated 5 280 A Underground cable XLPE (3 240125)mm2: RL20 C ¼ 0:127 O=km, XL 5 0.115 O/km, Irated 5 410 A Additional data Minimum Network Load: 20 A, Maximum Network Load: 110 A, Load power factor: cos j 5 0.9, inductive, Permissible voltage variation: emax% 5 73% impermissible voltage rise at the bus P19, as the greyscale cells in Table II show. The problem is significant at the route P4-P8, P9 and taking into account that the fourth constraint (the voltage variation constraint) of Section 2 is breached, the question is whether the connection of the DG units of PPC Renewables SA to bus P6 is possible without using a voltage regulator. The NEPLAN software package was also used to examine whether the network satisfies the third constraint (the SCL constraint) of Section 2 for maximum voltage supply (UTmax 5 21.4 kV). The result is that DG penetration causes a significant increase in SCLmax (229 MVA instead of 197 MVA without DG connection), as the level of installed capacity increases, but without exceeding SCLrated 5 250 MVA, given in Table I. So the third constraint is not breached. Copyright r 2009 John Wiley & Sons, Ltd. 5. ALTERNATIVE PROPOSALS The connection of the DG units of the PPC Renewables SA to bus P6 leads to an unacceptable network voltage profile, as ascertained in Section 4. Two alternative proposals were examined in order to solve this problem: First proposal: connection of the DG units of the PPC Renewables SA to bus P24 instead of bus P6. This connection can be realised via an existing line having an ACSR 95 mm2 conductor 7 km in length. A relative analysis shows that the thermal constraint is not breached. The SCLmax decreases (226 MVA instead of the initial SCLmax 5 229 MVA). This is to be expected as the distance of the new connection point of the Int. J. Energy Res. (2009) DOI: 10.1002/er G. N. KOUTROUMPEZIS ET AL. Table II. Bus voltage variation ei% for minimum load. ei% with DG ei% with DG Bus ei% without DG Existing DG First proposal Second proposal P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 P13 P14 P15 P16 P17 P18 P19 P20 P21 P22 0.00 0.43 0.46 0.68 0.72 0.76 0.77 0.85 0.80 0.44 0.48 0.60 0.83 0.89 0.99 0.65 0.68 0.73 0.74 0.65 0.79 0.88 0.00 0.03 0.77 6.19 7.49 9.80 9.80 9.72 9.78 0.02 0.07 0.18 0.42 0.47 0.57 0.28 0.76 2.06 3.51 0.29 0.15 0.06 0.00 0.62 0.66 0.88 0.91 0.96 0.97 1.05 1.00 0.63 0.68 0.79 1.03 1.08 1.18 0.54 0.06 1.25 2.71 0.54 0.68 0.77 0.00 0.06 0.08 0.28 0.33 0.45 0.44 0.37 0.42 0.07 0.02 0.09 0.33 0.38 0.48 0.37 0.85 2.15 3.60 0.38 0.24 0.15 PPC Renewables SA units from the network origin increases. The bus voltage variation when one of the two alternative proposals is adopted is also given in Table II. With the presumed DG connection, the network acquires a very good voltage profile and so the relative constraint concerning the permissible voltage rise is no longer breached. Second proposal: conductor replacement at the route P2-P6 with ACSR 95 mm2 conductors (of about 12 km). With the implementation of this proposal, the thermal constraint is satisfied. SCLmax, which is now equal to 232 MVA, remains smaller than SCLrated, even if it is increased (because the route P2-P6 acquires bigger conductors) compared to the initial SCLmax, (229 MVA). The proposal improves remarkably the network voltage profile, as Table II shows. Only the problem related to bus P19 remains, but this is marginal. The implementation of this proposal gives the possibility to supply increased loads to the route P2-P6. Copyright r 2009 John Wiley & Sons, Ltd. Bus ei% without DG Existing DG First proposal Second proposal P23 P24 P25 P26 P27 P28 P29 P30 P31 S01 S02 S03 S04 S05 S06 S07 S08 S09 S10 S11 S12 0.93 0.94 0.94 1.00 1.00 1.08 1.08 1.03 1.03 0.43 0.46 0.43 0.52 0.65 0.67 1.00 1.06 1.02 1.08 1.08 1.08 1.13 1.13 1.16 1.10 1.64 2.34 2.35 1.89 2.05 0.03 0.77 0.03 0.10 0.23 0.32 1.10 2.13 1.72 2.35 2.41 2.56 0.63 0.70 0.66 0.60 1.14 1.85 1.86 1.39 1.55 0.62 0.66 0.62 0.71 0.84 0.51 0.60 1.63 1.22 1.86 1.92 2.06 1.22 1.22 1.25 1.20 1.73 2.43 2.44 1.98 2.14 0.06 0.08 0.06 0.01 0.14 0.41 1.20 2.22 1.81 2.44 2.50 2.65 Both the proposals solve the original problem. The selection of one or the other is a matter of financial evaluation, the possibility of implementation and general Public Power Corporation policy. 6. OPTIMUM DISTRIBUTION FOR MAXIMUM DG PENETRATION The problems arising from an almost arbitrary DG penetration in predetermined buses of a power distribution network were examined in the previous sections and possible ways to deal with them were proposed. This section examines the case where the previously mentioned four buses are possible DG connection points and the determination of an optimum distribution for maximum DG penetration in these positions is desirable without breaching the technical constraints given in Section 2 and also without any network modification. The problem is examined by exploiting the method of [7] and also taking into account the Int. J. Energy Res. (2009) DOI: 10.1002/er INVESTIGATION OF THE DISTRIBUTED GENERATION PENETRATION thermal constraint given in Section 2. The general idea of the above method is the maximisation of an objective function, expressing DG capacity subject to the technical constraints mentioned in Section 2. The basis for the methodology is in exploiting the interdependence, if any, of the buses with regard to the constraints. So the constraints all have either linear or approximately linear characteristics with respect to increasing power injections, or they place a fixed and independent limit on the power injection. Table III gives the resulting DG penetration as well as one that can be practically realised using the standardised DG units for each position with the technical data given in Table I (the last column of Table III). The higher DG penetration in the last case is due to the fact that the DG units connected to bus P29 are working at cos j 5 1 instead of cos j 5 0.95, as the initial theoretical computation considers. As Table III shows, the calculated optimum total DG penetration (theoretical and practical) is higher than the existing one and it has a quite different distribution. After the connection of the standardised DG units given in the last column of Table III, the branch currents remain smaller than the rated conductor currents and the SCLmax (now equal to 229 MVA) is almost the same compared to the initial SCLmax. The network voltage profile for minimum voltage is very good and it is much better than that corresponding to Table III. Optimum DG penetration. Optimum DG penetration with standardised DG units Node P19 P31 P06 Existing DG penetration [MW] 1.66 3.16 4.7 (Inadmissible voltage level) P29 2 Total 11.52 [MW] Optimum DG penetration DG [MW] [MW] units 1.7 5.1 1.5 1.66 G1 6.32 4 G2 1.5 G4 4.25 12.55 4 2 G6 13.48 Copyright r 2009 John Wiley & Sons, Ltd. the existing DG penetration, as a comparison of the relative columns of Table IV shows. So all the technical constraints given in Section 2 are satisfied and the network acquires a very good voltage profile as well. The penetration of DG units having usual sizes in a distribution network with the usual prices of cos j causes a voltage rise. So the examination of the network voltage profile for minimum load is essential in order to avoid an impermissible voltage rise. But when the DG penetration is relatively high and cos j is inductive (even if it is almost equal to the unit), as relevant investigation proves, a voltage drop instead of a voltage rise may appear. For this reason, the examination of the voltage profile of distribution networks with particular DG penetration for maximum load is advisable. Table IV also shows the voltage profile of the network given in Figure 1 for maximum load, with the existing DG penetration and for the optimum DG penetration given in the last but one column of Table III. In the relative columns of Table IV, the buses with an impermissible voltage drop are shown in greyscale. The proposed optimum DG distribution improves the voltage profile of the examined network during the hours of maximum load, particularly at the route P4-P9, in comparison with the existing DG penetration, as Table IV shows. The network voltage profile for maximum load after the connection of the DG units (existing or optimum DG penetration) is generally improved in comparison with the situation without DG penetration, which is an expected result because of the increased active power flows on the distribution network. 7. CONCLUSIONS DG penetration in distribution networks causes changes to their characteristics. These changes are unacceptable, as basic technical constraints do not apply. This paper, exploiting a commercial-grade software package, examines the results of concrete DG penetration on branch currents, the voltage profile and the short-circuit level of a realistic medium-voltage distribution network. Problems related to a voltage rise arose and different ways Int. J. Energy Res. (2009) DOI: 10.1002/er G. N. KOUTROUMPEZIS ET AL. Table IV. Influence of the optimum DG penetration on the bus voltage variation ei%. ei% for minimum load ei% for maximum load Bus Existing DG Optimum DG Existing DG Optimum DG P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 P13 P14 P15 P16 P17 P18 P19 P20 P21 P22 0.00 0.03 0.77 6.19 7.49 9.80 9.80 9.72 9.78 0.02 0.07 0.18 0.42 0.47 0.57 0.28 0.76 2.06 3.51 0.29 0.15 0.06 0.00 1.31 1.04 0.79 1.22 2.01 2.00 1.92 1.98 1.34 1.39 1.50 1.74 1.80 1.90 1.78 1.30 0.03 1.51 1.79 1.93 2.01 0.00 1.57 0.94 3.46 4.57 6.64 6.59 6.22 6.47 1.60 1.83 2.44 3.71 3.99 4.51 2.21 2.35 2.62 2.71 2.22 2.94 3.41 0.00 1.96 1.85 0.99 0.73 0.14 0.20 0.60 0.32 2.00 2.24 2.86 4.16 4.45 4.98 2.73 2.88 3.16 3.24 2.74 3.49 3.96 (an alternative DG connection, reconductoring) to deal with them were proposed. The above mentioned problems are due to the fact that the existing DG penetration is arbitrary to a point, and they can be avoided if a relative study precedes the DG installation in predetermined positions, as the previous section clearly shows. The method applied in the previous section for the determination of optimum DG penetration gives satisfactory results for small distribution networks, a small number of predetermined DG connection points and for DG units with the same features. But in cases of large networks, random penetration points (a marginal case assuming that all the network buses are possible DG locations) and a mix of generator technologies, the method is laborious and time consuming. It also adopts simplifications, which in some cases may lead to incorrect results or perhaps to the failure to find a solution. Therefore, the development of a new, more accurate, fast and flexible method, working for every size of distribution network and giving a Copyright r 2009 John Wiley & Sons, Ltd. ei% for minimum load ei% for maximum load Bus Existing DG Optimum DG Existing DG Optimum DG P23 P24 P25 P26 P27 P28 P29 P30 P31 S01 S02 S03 S04 S05 S06 S07 S08 S09 S10 S11 S12 1.13 1.13 1.16 1.10 1.64 2.34 2.35 1.89 2.05 0.03 0.77 0.03 0.10 0.23 0.32 1.10 2.13 1.72 2.35 2.41 2.56 1.59 1.59 1.56 1.62 0.97 0.06 0.04 0.49 0.16 1.36 1.07 1.36 1.47 1.6 1.86 1.62 0.35 0.83 0.04 0.07 0.32 2.50 2.51 2.50 2.80 2.29 1.91 1.89 2.15 2.02 1.57 0.94 1.57 2.03 2.71 2.23 2.8 2.02 2.27 1.89 1.83 1.69 2.66 2.67 2.64 2.95 2.03 0.93 0.91 1.66 1.37 1.96 1.85 1.96 2.45 3.14 2.76 2.95 1.27 1.94 0.91 0.79 0.51 solution for the optimum DG allocation without fail is necessary. REFERENCES 1. CIRED. ‘Dispersed Generation’; Preliminary report of CIRED (International Conference on Electricity Distribution), Working Group WG04. Brussels, Belgium, June 1999. 2. Ackermann T, Andersson G, Soder L. Distributed generation: a definition. Electric Power Systems Research 2001; 57(3):195–204. 3. Barker PP, De Mello RW. Determining the impact of distributed generation on power systems: Part 1—radial distribution systems. Proceedings of the IEEE PES Summer Meeting, Seattle, WA, U.S.A., July 2000; 1645–1656. 4. Wallace A, Harrison G. Planning for optimal accommodation of dispersed generation in distribution networks. Proceedings of the CIRED 17th International Conference on Electrical Distribution, Barcelona, Spain, May 2003. 5. Kuri B, Redfern M, Li F. Optimization of rating and positioning of dispersed generation with minimum network disruption. Proceedings of the IEEE Power Engineering Society General Meeting, Denver, CO, June 2004; 2074–2078. Int. J. Energy Res. (2009) DOI: 10.1002/er INVESTIGATION OF THE DISTRIBUTED GENERATION PENETRATION 6. Bhowmik A, Maitra A, Halpin SM, Schatz JE. Determination of allowable penetration levels of distributed generation resources based on harmonic limit considerations. IEEE Transactions on Power Delivery 2003; 18(2):619–624. 7. Keane A, O’Malley M. Optimal allocation of embedded generation on distribution networks. IEEE Transactions on Power Systems 2005; 20(3):1640–1646. 8. Nara K, Hayashi Y, Ikeda K, Ashizawa T. Application of tabu search to optimal placement of distributed generators. Proceedings of the IEEE Power Engineering Society Winter Meeting, Colmbus, OH, U.S.A., 2001; 918–923. 9. Celli G, Pilo F. Optimal distributed generation allocation in MV distribution networks. Proceedings of the 22nd IEEE PES International Conference on Power Industry Computer Applications PICA, Sydney, Australia, 20–24 May 2001; 81–86. 10. Kim KH, Lee YJ, Rhee SB, Lee SK, You SK. Dispersed generator placement using fuzzy-GA in distribution systems. Proceedings of the IEEE Power Engineering Society Summer Meeting, Chicago, IL, 21–25 July 2002; 1148–1153. 11. El-Khaltam W, Bhattacharya K, Hegazy Y, Salama MMA. Optimal investment planning for distributed generation in a competitive electricity market. IEEE Transactions on Power Systems 2004; 19(3):1674–1684. 12. Celli G, Ghiani E, Mocci S, Pilo F. A multi-objective approach to maximize the penetration of distributed generation in distribution networks. 9th International Copyright r 2009 John Wiley & Sons, Ltd. 13. 14. 15. 16. 17. 18. 19. 20. Conference on Probabilistic Methods Applied to Power Systems KTH, Stockholm, Sweden, 11–15 June 2006. Coll-Mayor D, Picos R, Garcia-Moreno E. State of the art of the virtual utility: the smart distributed generation network. International Journal of Energy Research 2004; 28:65–80. Boutsika Th, Papathanassiou S, Drossos N. Calculation of the fault level contribution of distributed generation according to IEC standard 60909. CIGRE DG Symposium, Athens, Greece, April 2005. Jenkins N, Allan R, Crossley P, Kirschen D, Strbac G. Embedded Generation. IET Publications: London, 2000. http://www.neplan.ch/sites/en/neplan_elec.asp, Accessed on April 2008. IEC 60909-0: Short-circuit currents in three-phase a.c. systems—Part 0: calculation of short-circuit currents. 2001. IEC 60909-1: Short-circuit currents in three-phase a.c. systems—Part 1: factors for the calculation of short-circuit currents according to IEC 60909-0. 2002. IEC 60909-2: Short-circuit currents in three-phase a.c. systems—Part 2: electrical equipment–data for short-circuit currents calculation in accordance with IEC 909 (1988). 2002. IEC 60909-4: Short-circuit currents in three-phase a.c. systems—Part 4: examples for the calculation of shortcircuit currents. 2002. Int. J. Energy Res. (2009) DOI: 10.1002/er