Guidelines for electricity generation facilities with a rated current greater than 16 A per phase, which are connected to the low-voltage network via inverters 22 October 2012 SFJ/AKN These guidelines cover the basic requirements for electricity generation facilities with a rated current exceeding 16 A per phase, which are connected to the lowvoltage network via inverters Electricity generation facilities larger than 1.5 MVA are not covered by these guidelines, as they are expected to be connected at the medium-voltage level. Guidelines for such systems must be agreed with the grid companies. Wind turbines/wind power stations are not covered by these guidelines, as they are covered by Technical Regulation TF 3.2.5. Doc. 14812/11, Case 10/405 1/20 Working group These guidelines have been formulated by an industry working group comprising: • • • • • • • • • • The Danish Energy Association The Danish Solar Cell Association TEKNIQ EnergiMidt Dong Energy Østjysk Energi Schüco International Danfoss Solar Inverters Solarpanels Energinet.dk Reading instructions These guidelines have been subdivided in relation to the phase current of the electricity generation facility: - Electricity generation facilities larger than 16 A and up to and including 75 A per phase - Electricity generation facilities larger than 75 A per phase These guidelines make use of various terms and definitions. The most important of these are explained in section 1. Terms and definitions used in the guidelines have been highlighted in the text using italics. The guidelines have been published by the system operator and can be downloaded from www.energinet.dk. Doc. 14812/11, Case 10/405 2/20 Table of contents 1. 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 Terminology and definitions ................................................... Plant owner ......................................................................... Electricity generation facility .................................................. Electricity generation facility connection point (PGC) ................. Public electricity supply network ............................................. Low-voltage network ............................................................. Supplier .............................................................................. Rated power ........................................................................ Rated current ....................................................................... Grid faults ........................................................................... Grid company ...................................................................... Nominal voltage ................................................................... Normal output range ............................................................. Interconnected electricity supply system ................................. System operator................................................................... Point of Connection (POC) ..................................................... 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 Electricity generation facility connected to low voltage .............. 7 Voltage quality ..................................................................... 7 Engagement and synchronisation .......................................... 14 Asymmetry ......................................................................... 14 Active power regulation ........................................................ 14 Reactive power regulation..................................................... 15 Tolerance of voltage dips and peaks, FRT ............................... 17 Protection towards the grid ................................................... 17 System protection ............................................................... 18 Communication ................................................................... 18 Registration and documentation ............................................ 18 Decommissioning, changes or replacement ............................. 20 2. Doc. 14812/11, Case 10/405 4 4 4 4 4 4 4 4 4 5 5 5 5 5 5 6 3/20 1. Terminology and definitions 1.1 Plant owner The legal owner of the electricity generation facility 1.2 Electricity generation facility Facility producing three-phase alternating current. • • 1.3 The electricity generation facility may consist of one or more units in the same installation The electricity generation facility may consist of one or more units directly connected to the public electricity supply network Electricity generation facility connection point (PGC) The point in the public electricity supply network or the installation where the electricity generation facility is connected. • • 1.4 When connected to the public electricity supply network, the electricity generation facility connection point (PGC) may coincide with the point of connection (POC), see figure 1. When connected within the installation, the electricity generation facility connection point (PGC) is the point in the installation where consumption is connected, see figure 1. If common grid protection is used, consumption must not be connected after this protection. Public electricity supply network Transmission grids and distribution networks the purpose of which is to transmit electricity for an indefinite group of electricity suppliers and consumers on the terms laid down by public authorities. The transmission grid is defined as the public electricity supply network with a nominal voltage greater than 100 kV, while the distribution grid is defined as the public electricity supply network with a nominal voltage lower than 100 kV. 1.5 Low-voltage network The public electricity supply network with a nominal voltage of up to 1000 V AC. 1.6 Supplier The company which supplies the electricity generation facility to the plant owner. The supplier is responsible for ensuring that the electricity generation facility complies with these guidelines. 1.7 Rated power The highest nominal electrical output of an electricity generation facility under nominal operating conditions. Stated in kW or kVA. 1.8 Rated current The greatest nominal current from the electricity generation facility under nominal operating conditions. Doc. 14812/11, Case 10/405 4/20 1.9 Grid faults Failure or faults in the public electricity supply network. 1.10 Grid company An approved company which operates the distribution grid. The grid company is the company which operates the grid the electricity generation facility is physically connected to. 1.11 Nominal voltage The voltage at a point of connection, e.g. 400 V for three-phase connection. 1.12 Normal output range The normal output range specifies the voltage/frequency range within which the facility must be able to constantly produce power, see section 2. 1.13 Interconnected electricity supply system The public electricity supply network and associated facilities in a large region which is interconnected for the purpose of joint operation. 1.14 System operator The company with general responsibility for maintaining security of supply and ensuring effective utilisation of an interconnected electricity supply system. The system operator is Energinet.dk. Doc. 14812/11, Case 10/405 5/20 1.15 Point of Connection (POC) The point in the public electricity supply network where the electricity generation facility or installation is connected. • In the case of direct connection to the public electricity supply network, the electricity generation facility connection point (PGC) is the same as the point of connection (POC), see figure 1. 10 kV 0,4 kV PGC POC POC Direkte tilsluttet til det kollektive elforsyningsnet Installationstilsluttet PGC Forbrug Solcellepanel Solcellepanel POC: Tilslutningspunkt til det kollektive elforsyningsnet PGC: Det elprducerende anlægs tilslutningspunkt Figure 1 Example of points of connection Doc. 14812/11, Case 10/405 6/20 2. Electricity generation facility connected to low voltage The normal output range is defined as the nominal voltage Un ±10% and is within the 47.50-50.05 Hz frequency range. The electricity generation facility must be designed for three-phase connection. If the electricity generation facility consists of three single-phase units, it is also considered to be a three-phase facility, see the requirements in section 2.3. The requirements set in the guidelines apply at the point of connection (POC). If the electricity generation facility complies with the requirements at the electricity generation facility connection point (PGC), it is assumed that the requirements are also met at the point of connection (POC). 2.1 Voltage quality All inverters must be tested and certified for compliance with voltage quality requirements. Voltage quality covers the following elements: • • Flicker Harmonic and interharmonic currents Definitions and explanations for these terms can be read in detail in the following standards, which also specify the associated limit values and requirements: • • • • DS/EN 61000-3-2 "Electromagnetic compatibility (EMC) – Part 3-2: Limits - Limits for harmonic current emissions (equipment input current ≤ 16 A per phase)" DS/EN 61000-3-3 "Electromagnetic compatibility (EMC) – Part 3-3: Limits – Limitation of voltage changes, voltage fluctuations and flicker in public low-voltage supply systems, for equipment with rated current ≤ 16 A per phase and not subject to conditional connection" (IEC61000-3-3) DS/EN 61000-3-11 "Electromagnetic compatibility (EMC) – Part 3-11: Limitation of voltage changes, voltage fluctuations and flicker in public low-voltage supply systems – Equipment with rated current ≤ 75 A and subject to conditional connection" DS/EN 61000-3-12 "Electromagnetic compatibility (EMC) – Part 3-12: Limits – Limits for harmonic currents produced by equipment connected to public low-voltage systems with rated current >16 A and ≤75 A per phase" 2.1.1 Electricity generation facilities producing between 16 A and 75 A per phase Electricity generation facilities producing between 16 A and 75 A per phase are considered to comply with these guidelines if each inverter complies with the above standards. Compliance is demonstrated by submitting the necessary documentation, as described in section 2.10.1 Doc. 14812/11, Case 10/405 7/20 2.1.2 Electricity generation facilities larger than 75 A per phase For electricity generation facilities larger than 75 A per phase, the following requirement must be met. Compliance is demonstrated by submitting the necessary documentation, as described in section 2.10.2 Flicker The electricity generation facility's flicker contribution during continuous operation, Plt, must be complied with at the point of connection (POC). The following limit values must be observed for all electricity generation facilities. Plt ≤ 0.50 2.1.2.1 Electricity generation facilities consisting of a single unit If an electricity generation facility consists of a single unit, flicker contribution, Plt, is calculated in the following manner. Plt = c (ψ k )⋅ Plt: c (ψk): 1 25 long term flicker flicker coefficient (value ψ=30° from the test report) 2.1.2.2 Electricity generation facilities consisting of several identical units If an electricity generation facility consists of several identical units, total flicker contribution, Plt, is calculated in the following manner. First calculate the flicker contribution Plt,i for a single unit: Plt,i = c i (ψ k ) ⋅ 1 N ⋅ 25 Plt,i: i: Ci (ψk): long term flicker for a single unit unit which is part of the facility flicker coefficient (value ψ=30° from the test N: the number of identical units report) Then calculate the flicker contribution for the entire electricity generation facility by adding together the individual flicker contributions, Plt,i, based on the formula: Doc. 14812/11, Case 10/405 8/20 Plt = 2 ∑ (P ) 2 lt,i i Doc. 14812/11, Case 10/405 9/20 Example 1: Four 15 kW inverters with a flicker coefficient c, (ψk)=17.84 1 Plt,i = 17.84 ⋅ Plt = 4 ⋅ 25 = 0.18 4 ⋅ 0.18 2 = 0.36 2 2.1.2.3 Electricity generation facilities consisting of different units If an electricity generation facility consists of different units, flicker contribution, Plt, is calculated in the following manner. First calculate the flicker contribution Plt,i for a single unit: Plt,i = c i (ψ k )⋅ S n ,i S n ⋅ 25 Plt,i: i: Ci (ψk): long term flicker for a single unit unit which is part of the facility flicker coefficient (value ψ=30° from the test Sn,i: Sn: unit i's rated power the facility's total rated power report) Then calculate the flicker contribution, Plt, for the entire electricity generation facility by adding together the individual flicker contributions, Plt,i, based on the formula: Plt = 2 ∑ (P ) 2 lt,i i Plt: Example 2: long term flicker Two 15 kW inverters with a flicker coefficient C15 (ψk)=17.84 and two 12.5 kW inverters with a flicker coefficient c12.5 (ψk)=19.74 Plt,15 k = 17.84 ⋅ 15 (15 + 15 + 12.5 + 12.5) ⋅ 25 Plt,12 k 5 = 19.74 ⋅ Doc. 14812/11, Case 10/405 = 0,19 12.5 (15 + 15 + 12.5 + 12.5) ⋅ 25 = 0.18 10/20 Plt = 2 0.19 2 + 0.19 2 + 0.18 2 + 0.18 2 = 0.37 Doc. 14812/11, Case 10/405 11/20 Harmonic currents The electricity generation facility must comply with the limit values for harmonic currents specified in table 1. Odd harmonic order h (not a multiple of 3) Harmonic Limit value [%] Table 1 Even harmonic order h (not a multiple of 3) 5 7 11 13 17≤h≤49 2 4 8≤h≤50 3.6 2.5 1.0 0.7 – - - - limit values for harmonic current Ih/In (%) Ih ≤ grænseværdi In Ih: I n: (%) harmonic current [5,7,11,13] nominal rated current If an electricity generation facility consists of several inverters, the contributions for each inverter must be summed in accordance with the general summation rule described in IEC 61000-3-6, as specified in the following formula: Ih = α ∑ Iα h ,i i α: h: report i: Table 2 exponent of α (table 2) harmonic [5,7,11,13] (highest value from the test for the given unit) number of units [1,2,3,4…] Harmonic order α (alpha) h<5 1 5 ≤ h ≤ 10 1.4 h > 10 2 Value for the exponent α Doc. 14812/11, Case 10/405 12/20 Example 3: Two 15 kW inverters with rated current of 22A and 5th and 7th harmonics of 0.31% and 0.36% respectively, and two 12.5 kW inverters with rated current of 19A and 5th and 7th harmonics of 0.29% and 0.33% respectively First calculate Ih,i for all the harmonic currents for each unit: I h ,i = I h ,i / I n ,i [%] 100 ⋅ I n ,i 0,31 ⋅ 22 A = 0.0682 A 100 I 5,15 k = I 5,12,5 k = 0,0551A ; I 7 ,15 k = 0.0792 A ; I 7 ,12,5 k = 0.0627 A Then calculate the harmonic currents for the total electricity generation facility using the general summation rule and exponent α=1.4: I5 = 1, 4 0.06821, 4 + 0.06821, 4 + 0.05511, 4 + 0.05511, 4 = 0.166 A I7 = 1, 4 0.07921, 4 + 0.07921, 4 + 0.06271, 4 + 0.06271, 4 = 0.192 A Finally, calculate the harmonic currents as a % of the rated current: I n = 22 + 22 + 19 + 19 = 82 A Ih / In = Ih ⋅ 100% In I5 / In = 0,166 ⋅ 100= 0.20% 82 ; I7 / In = 0,192 ⋅ 100= 0.23% 82 Interharmonic currents The electricity generation facility must comply with the limit values for interharmonic currents specified in table 3. Interharmonic Frequency (Hz) 75 Hz 125 Hz >175 Hz 0.40 0.60 75 f *) Limit value [%] *) But not less than 0.1% Doc. 14812/11, Case 10/405 13/20 Table 3 Limit values for emission of interharmonic currents If the electricity generation facility consists of several inverters, the contributions must be summed in the same way as for emission of harmonic currents, but using exponent α=2. Disturbances from 2-9 kHz The limit values for currents with frequencies in the 2-9 kHz range must not exceed 0.2% of the rated current in any of the measured frequency groups. 2.2 Engagement and synchronisation Within the normal output range, the electricity generation facility must be able to start-up and produce continually within the design specifications, limited only by the protection settings specified in section 2.7. Automatic engagement and synchronisation of the electricity generation facility must be delayed until at least three minutes after the voltage and frequency are within the normal output range. Following automatic re-engagement after a grid fault, the active power output must not rise by more than 10% per minute. Engagement with manual synchronisation is not permitted. As an alternative to the requirements listed above, the requirements in VDEAR-N 4105 may be used. 2.3 Asymmetry During normal operation or in the case of a fault, the electricity generation facility must not have asymmetry greater than 16 A between the phases. If the electricity generation facility consists of three single-phase units, the necessary communication must be established to ensure that the above limit is not exceeded. 2.4 Active power regulation The electricity generation facility must be equipped with an output reduction function for frequencies greater than f1, as specified in figure 2. For frequencies greater than f1, a reduction of the current active power must be effected with a gradient of current power, Pcurrent, which was available at the time the f1 limit was exceeded. Frequency f1 is 50.2 Hz, and the gradient (droop) is 40% per Hz. The active power must continually move up and down the frequency characteristic for frequencies greater than f1 and up to fmax (the disengagement frequency) specified in the protection settings in section 2.7. Doc. 14812/11, Case 10/405 14/20 Aktiv effekt Paktuel Droop 1 fmax fmin Pmin 0 47.00 48.00 49.00 50.00 51.00 52.00 Frekvens [Hz] f1 Figure 2 Power reduction requirements for electricity generation facilities The requirements in VDE-AR-N 4105 may be used as an alternative to the requirements listed above. The only difference is a disengagement frequency of 51.5 Hz. 2.5 Reactive power regulation The electricity generation facility must be able to regulate the reactive power in the following ways: • • constant power factor, cos φ variable power factor, cos φ (P) Any change in the active power must automatically result in the necessary adjustment to the reactive power for the selected power factor (cos φ) setting. Except where agreed otherwise with the grid company, the electricity generation facility must follow the cos φ characteristic specified in figure 3. The setting must be cos φ=1. 2.5.1 Constant power factor The electricity generation facility must have a power factor (cos φ) which can be set to any value within the 0.90 inductive and 0.90 capacitive range when production is greater than 20% of the rated power, and when the voltage and frequency lie within the normal output range specified in section 2. The required adjustment range corresponds to the shaded area in figure 3. Doc. 14812/11, Case 10/405 15/20 P/Pn PF=1 1,0 PF=0,90 + PF=0,90 0,2 Kapacitiv -1,0 - 0,8 Figure 3 Induktiv - 0,6 - 0,4 - 0,2 0,2 0,0 0,4 0,6 0,8 1,0 Q/Pn Characteristic for constant power factor, cos φ As an alternative to the requirements listed above, the requirements in VDEAR-N 4105 may be used, which are identical. 2.5.2 Variable power factor The electricity generation facility must have a characteristic whereby the power factor is dependent on the produced active power, cos φ (P), as specified in figure 4. Depending on the topology (consumption and production) of the public electricity supply network, the grid company may also require a characteristic which deviates from figure 4. P/Pn 1,0 PF=0,90 PF=1 0,5 0,2 Kapacitiv - 1,0 - 0,8 - 0,6 - 0,4 Induktiv - 0,2 0,0 0,2 0,4 0,6 0,8 1,0 Q/Pn Figure 4 Characteristic for variable power factor, cos φ (P) As an alternative to the requirements listed above, the requirements in VDEAR-N 4105 may be used, which are identical. Doc. 14812/11, Case 10/405 16/20 2.6 Tolerance of voltage dips and peaks, FRT The electricity generation facility must remain connected to the public electricity supply network during voltage dips and peaks, limited only by the protection settings specified in section 2.7. There is no requirement to supply active/reactive power during the period of the fault. 2.7 Protection towards the grid The protection equipment must ensure that the electricity generation facility does not impact negatively on the public electricity supply network or the safety of people and equipment. The protection functions for electricity generation facilities connected to the public electricity supply network must be established at the point of connection (POC), as specified in table 4. If the electricity generation facility complies with the requirements at the electricity generation facility connection point (PGC), it is assumed that the requirements are also met at the point of connection (POC). Protection function Symbol Setting a) Maximum function time Minimum measured time d) d) Overvoltage (stage 2) b) U>> 1.13 x Un 0.2 s 0.1 s Overvoltage (stage 1) U> 1.10 x Un 40 s 39 s Undervoltage (stage 1) U> 0.90 x Un 10 s 9s Over-frequency f> 52.0 Hz 0.3 s 0.2 s Under-frequency f< 47.5 Hz 0.3 s 0.2 s df/dt 2.5 Hz/s 0.3 s 0.2 s "ROCOF" Table 4 facilities Protection function requirements for electricity generation a ) All values are RMS values. The electricity generation facility must be disengaged d if a measured value deviates from its nominal value by more than the given setting. A measured value must not give rise to disengagement if the value lies between the nominal value and the setting value. Voltages must be measured as phase-zero voltages. b ) Two-stage overvoltage protection is required. c) The electricity generation facility must be disengaged via mechanical relay contacts for which the control signal is galvanically isolated from the poles (e.g. optically or electrically isolated). d) Maximum function time is the sum of the minimum measured time and time to break. The minimum measured time is the time during which the trip condition must be constantly fulfilled before the protection function Doc. 14812/11, Case 10/405 17/20 may issue a trip signal. It therefore does not refer to a simple delay to the trip signal. A joint protection unit is required at electricity generation facility connection point (PGC) if the electricity generation facility consists of microinverters (typically less than 500 VA) or if the electricity generation facility is larger than 100 kVA. Where there is any doubt, the grid company will decide what requirement applies to the electricity generation facility. Consumption must not be connected after the grid protection unit. As an alternative, the protection functions and settings in table 2 of VDE-AR-N 4105 may be used. There are alternative setting values for voltage and frequency, and the active frequency method is used for islanding detection. 2.8 System protection There are currently no requirements for system protection. 2.9 Communication There are currently no requirements for communication. A requirement of being able to communicate with the electricity generation facility is expected in the future Smart Grid. Implementation is expected to take place in accordance with IEC 61850. 2.10 Registration and documentation Pursuant to the common regulations (for the connection of electrical systems and user devices), registration must take place when an electricity generation facility is connected to the grid. Registration (incl. master data) must be carried out by an authorised electrician prior to commencing installation. Documentation for the electricity generation facility must be as described in this section. A "Grid connection and usage agreement" (Nettilslutnings- og netbenyttelsesaftale) must be prepared for the electricity generation facility. The supplier is responsible, on behalf the plant owner , for preparing the specified documentation for the electricity generation facility and submitting it electronically to the grid company. The required documentation for electricity generation facilities is specified in the following subsections, categorised by phase current. 2.10.1 Electricity generation facilities producing between 16 A and 75 A per phase The supplier must prepare a supplier declaration and a test report, as described below. Supplier declaration The supplier declaration must declare that the requirements in these guidelines have been met. The required contents of the supplier declaration are specified Doc. 14812/11, Case 10/405 18/20 in appendix 1 of the "Guidelines for electricity generation facilities with a rated current of between 16 A and 75 A per phase, which are connected to the lowvoltage network via inverters" Appendix 1 can be downloaded at www.energinet.dk. Doc. 14812/11, Case 10/405 19/20 Test report The test report must document that the requirements in these guidelines have been met. The required contents of the test report are specified in appendix 2 of the "Guidelines for electricity generation facilities with a rated current of between 16 A and 75 A per phase, which are connected to the low-voltage network via inverters" Appendix 2 can be downloaded at www.energinet.dk. As an alternative to the test report in appendix 2, documentation in accordance with VDE-AR-N 4105 appendix F3, F4, G2 and G3 may be used. 2.10.2 Electricity generation facilities larger than 75 A per phase The supplier must prepare a supplier declaration and a test report, as described below. Supplier declaration The supplier declaration must declare that the requirements in these guidelines have been met. The required contents of the supplier declaration are specified in appendix 3 of the "Guidelines for electricity generation facilities with a rated current greater than 75 A per phase, which are connected to the low-voltage network via inverters" Appendix 3 can be downloaded at www.energinet.dk. Test report The test report must document that the requirements in these guidelines have been met. The required contents of the test report are specified in appendix 4 of the "Guidelines for electricity generation facilities with a rated current greater than 75 A per phase, which are connected to the low-voltage network via inverters". Appendix 4 can be downloaded at www.energinet.dk. In addition to the requirements specified above, the following documents must also be supplied: • • • Line diagram including point of connection and settlement meter Documentation for the protection settings for the central grid protection (if used) Calculations in relation to voltage quality (such as supplier-specific test reports) As an alternative to the test report in appendix 4, documentation in accordance with VDE-AR-N 4105 appendix F3 and F4 may be used, whereby the test report must be filled out using values calculated for the total electricity generation facility. 2.11 Decommissioning, changes or replacement Where an electricity generation facility is decommissioned, changed or replaced, the grid company's normal procedures must be followed. Doc. 14812/11, Case 10/405 20/20