Recent NERC Approval
• New:
– MOD-032-1 — Data for Power System Modeling and
Analysis
– MOD-033-1 — Steady-State and Dynamic System
Model Validation
• Retires:
– MOD-010-0, MOD -011-0, MOD-012-0, MOD-013-1, MOD-014-0, and MOD-0150.1
– Standard related to data collection, requirements and modeling of steady state
and dynamics models
PJM Planning Committee - 2/6/2014
2
PJM©2014
Standards and Status
•
•
•
•
MOD-032-1 and MOD-033-1
Approved by NERC January 22, 2014
Next Steps: FERC Review
Effective Dates
– MOD-032 R1: 12 Months after FERC approval
– MOD-032 R2-R4: 24 Months after FERC approval
– MOD-033: 36 Months after FERC approval
PJM Planning Committee - 2/6/2014
3
PJM©2014
Impact to PJM
• Previously, Regional Entities (RFC and SERC)
would collect MOD-010 and MOD-012 data
• With these new standards the Planning
Coordinator (PJM) will be the entity responsible
for developing data requirements and collecting
Steady State, Dynamics and Short Circuit data
PJM Planning Committee - 2/6/2014
4
PJM©2014
Other Impacted Entities
• Data reporting requirements (MOD-032-01 Attachment 1)
• Transmission Owners (TO’s); Generation Owners (GO’s)
and Load Serving Entities (LSE’s) have requirements to
provide information required to effectively model the
interconnected transmission system per the table in
attachment 1
PJM Planning Committee - 2/6/2014
5
PJM©2014
MOD-032-01 Attachment 1
PJM Planning Committee - 2/6/2014
6
PJM©2014
MOD-032-01 Attachment 1 con’t
PJM Planning Committee - 2/6/2014
7
PJM©2014
MOD-032-01 Attachment 1 con’t
PJM Planning Committee - 2/6/2014
8
PJM©2014
Next Steps
• In anticipation of these new standards PJM will
begin work to develop:
–
–
–
–
–
Infrastructure for storing data
Modeling data requirements
Process for coordinating and collecting data
Submission guidelines and protocols
Updated contact lists for all impacted entities