Destructive Arcing of Insulated Joints in DC Electrified Railway Brandon Swartley, P.E. SYSTRA Consulting, Inc. Philadelphia, PA Dave Male, P.E. SYSTRA Engineering, Inc. New York, NY Al Santini, P.E. Metro-North Railroad New York, NY Bob Jaccino, E.I.T. Long Island Rail Road Hollis, NY deliveries of M7 starting in 2002. Similarly, the new MNR M8s (used for testing) that were part of this study demonstrate the same arcing. Visual inspections during testing have shown that large transient electrical arcs are observed across the IJs from passing trains. While arcing is seen when some or many of the axles pass over the IJs in the middle of crossovers, the largest arc is typically observed when the last axle passes over the last IJ. Arcing has also been observed at locations on LIRR that are in straight track and have impedance bonds (IBs) for traction current by‐pass around IJs. This problem has not been observed on MNR. SUMMARY Metro-North Railroad (MNR) and Long Island Rail Road (LIRR) have been experiencing excessive destructive arcing from electric multiple unit (EMU) trains passing over the insulated joints (IJs) at various locations in their third rail electrified territory. The destructive arcing has greatly reduced the life-cycle of insulated joints at these locations. The Railroads have undertaken a study of the phenomena to ascertain the cause(s) and develop possible mitigation of the destructive arcing [1]. The study followed a systems engineering approach, analyzing the elements of the traction system, vehicle propulsion circuits, and signaling system that utilize the track running rails as electrical elements of their circuits. The study included research, testing, analysis, and development of possible mitigations for the Railroads to consider going forward to address the problem. This paper will provide background into the problem, a brief discussion of arcing theory, overview of the testing performed, summary of the findings from the testing, and overview of the potential mitigations developed for the railroads to assess in the stage of resolving the problem. 1.0 Figure 1. Last train axle crossing IJ with no Z-bond and a resulting voltage of 291 V across the IJ INTRODUCTION Metro-North Railroad (MNR) and Long Island Rail Road (LIRR) (referred to in this report as “the Railroads”) have been experiencing excessive destructive arcing from train wheels of electric multiple unit (EMU) trains passing over the insulated joints (IJs) at various locations in the third-rail electrified territory. It has been observed that the arcing across the IJs and the degradation of the insulating material have increased since the introduction of the M7 multiple unit cars on both Railroads, with The current from the train’s propulsion system is returned through the wheels and into the rails back to the rectifier substation. The action of a train passing over the IJs in crossovers between two tracks results in the train’s return current utilizing the running rails of both tracks while straddling the IJs. When the last axle of a train crosses the IJs, the return current through one of those tracks is quickly broken – like a switch opening under 1 Destructive Arcing of Insulated Joints in DC Electrified Railway IJs constrain signal current to the rail sections between adjacent sets of IJs or blocks. load. The arc is created by the current being drawn out between the rail and the wheel, inducing a voltage across the IJ due to the rate of change in current in the rails (from a large value to zero) and proportional to the inductive characteristics of the return circuit, including the combination of all wayside and onboard inductances. Aside from the inductive characteristics of the traction return system elements, including impedance bonds and running rails, two inductors are part of the train/traction system circuits that are the subject of this study: the M7 propulsion circuits and the traction system itself. M7 propulsion circuits (as well as those of M8s and the future M9s) are significantly different in electrical makeup and characteristics than earlier EMU propulsion circuits. In addition to higher train performance requiring more electrical current from the traction system, the ac drive equipment includes an inductive-resistive-capacitive (LRC) circuit for EMI filtering and other purposes that contributes to the aforementioned inductive characteristics of the return. The running rails must also carry the train propulsion and auxiliary current back to the traction power substation (TPS) to complete the electrical circuit. The traction currents for a single 12-car M7 train range from 1200 A dc during coasting to 10500 A dc at full power. Each train’s dc propulsion current in the running rails must by-pass the signal system’s insulated joints. This is accomplished by installing impedance bonds at the IJ locations to allow train propulsion current to pass while blocking the signal current. It is critical to the safety of the system that signal current of a block not by-pass the IJs. Figure 3. Impedance bond across IJ The action of impedance bonds to block signaling current while being very low resistance to dc traction current is critical to the successful operation of the two systems. Ensuring that signaling current is confined within the individual signal blocks defined by IJs is also critical to satisfying the FRA requirement for broken rail detection. Preventing signaling current from running around the condition of a broken rail through the traction system is a major challenge of the railroads’ signal system when electrified traction systems provide for dc bypass of IJs and electrical connection of adjacent tracks via traction substation negative busses. In multi-track territory, adjacent tracks represent multiple electrical paths. Tracks are electrically tied together on the negative bus at substations. Electrical ties between tracks are also provided in order to reduce the resistance of traction return circuits. Tracks that are tied together electrically at substations and at other locations between substations are referred to as cross bonds. Cross bonds need to be located far enough apart such that when a rail breaks, signaling current does not utilize the cross bonds and adjacent track running rails as run around paths. This is depicted in Figure 4 where the signaling current intended for the rail with the break conducts through the tracks and substation cross bonds to complete the circuit around the break. Figure 2. Rail damaged at IJ from arcing Also contributing to the inductance in the traction system are the reactors (air-core coils) in series with the return circuit to increase the impedance of the traction return system in order to maintain broken rail protection. Starting in the late 1980’s, Metro-North and LIRR began installing the reactors as a means of ensuring FRA mandated broken rail detection of the signaling system. While there were cases of arcing prior to the advent of the M7s, they were at few locations, less severe, and generally mitigated with cross bonding. 2.0 TRACK CIRCUIT On an electrified railroad with block signaling, the running rails serve two purposes in addition to supporting and guiding trains: The rails are used as electrical conductors for track circuits that detect the presence of trains within signal blocks, delineated by the installation of insulated joints (IJ) in the track. 2 Destructive Arcing of Insulated Joints in DC Electrified Railway different between the M3 and M7 EMUs. The M7s incorporate conductors other than the car body to carry the return currents to the ground brushes, providing a better conducting path than the M3s for the propulsion return current to the running rails. Depending on the return circuit impedance in the track, more current can be returned through the last axle with the M7s than the M3s because the train has a lower resistance than the track circuit under the train. This may contribute to more severe arcing when operating M7s than M3. Figure 4. Signal Current Runaround Path MNR and LIRR install reactors in the substation return circuit to increase the impedance of the run around paths to the 100 Hz +/- signaling current. Increasing the impedance of the traction return system to signaling currents is necessary where the quantity of substations required for high performance trains results in substation spacing closer than permitted for the signal system to guarantee broken rail detection. The wayside reactors have an adverse effect on IJ arcing by increasing the inductance of the traction return system. The inductance of the wayside reactors in combination with the inductors used for filtering on ac drive propulsion circuits provide the energy storage for bolstering the arc at IJs. Cross-overs and turnouts create electrical connections between running rails of adjacent tracks. Accordingly, IJs are inserted in the rail sections to prevent the flow of signal current between adjacent tracks. When trains change tracks at cross-overs and turnouts, current is interrupted when the wheels pass over the IJs separating the tracks. When this interruption takes place, an arc is generated that produces intense heat, enough to melt a part of the steel rails. Each arc removes a part of the steel and results in rapid erosion of the running rails near the IJ and destruction of the end post. This irregular surface results in a mechanical shock each time a wheel passes over it. After a period of time, the deformed rail head shorts the IJ and signal block isolation is lost, causing the signal system to assume a danger state restricting train movements. At that point, repairs are needed to restore the proper function of the insulated joints. The problem experienced at MNR and LIRR is that arcing at some IJs is so severe that the IJs are failing rapidly after only a few months of operation. 4.0 MNR AND LIRR DIFFERENCES There are a few differences between the LIRR and MNR trains and wayside circuits as noted in Table 1. LIRR limits their 12-car trains to 10500 A, whereas MNR limits their 10-car trains to 7000 A. Since the longer LIRR trains draw higher currents, their respective impedance bonds utilize 3-500 kcmil cables at the rail connections with a solid neutral bus bar between bonds. These high currents can present a problem if the rail return paths do not have relatively equal resistances. For example, a typical IB requires that the impedance (at signal operating frequencies) shall not decrease by more than 10% with an out-of-balance current in one half of the winding exceeding that in the other half by the margin of 12% of the full continuous rated current. Incorporating a continuous current rating of 2000 A means that the difference in current between the rail leads needs to stay within 240 A. An early theory was that impedance bonds near the IJs may be saturating and causing voltage spikes leading to arcing. This theory was dismissed after measuring the current in impedance bond connections and finding them to be within unbalance ratings. LIRR and MNR Equipment Item Impedance bonds Train current LIRR 3-500 kcmil per side lead cables MNR 2-500 kcmil per side lead cables Solid copper busbar neutral connection 12-car trains limited to 875 A per car (10,500 A limit per train) 3-500 kcmil cable neutral connection 10-car trains limited to current draw of 8car train (7,000 A limit per train) Table 1. 5.0 Figure 5. Adjacent track electrical isolation 3.0 ELECTRICAL THEORY The train wheels crossing an IJ are similar to a switch opening in the dc circuit. An arc may be struck by drawing apart two touching electrodes between which a current is passing [2]. The components of the circuit include: TRAIN CIRCUIT The electrical connections of the car body and electrical circuits to the axles via ground brushes are 3 Destructive Arcing of Insulated Joints in DC Electrified Railway Lr, Lt Rr Lb Vc Rc r t τ Carol C1166.21.01, coax cable, RG58/U, 50 ohm, 18 AWG, 1000 ft roll Rail clamps wayside and train inductance rail and IJ (contact) resistance IB inductance across the IJ, if present voltage across the IJ (contact) time-varying IJ (contact) resistance contact resistance under full area time total time for interruption 6.2 These equations show that the voltage developed across the IJ is a proportional to circuit inductance, the magnitude of current in the circuit, and the variable resistance [3] caused by the wheel breaking contact with the rail as it crosses the IJ. FIELD TESTING In order to examine the traction return circuit, quantify the magnitude of the arc, and categorize the factors contributing to the arc, field testing was conducted to measure the current and resulting voltage during arcing conditions at a variety of locations and train performance conditions. Testing was conducted at three MNR and LIRR locations where arcing had been observed to be significant. The premise was that if electrical limits could be established as a function of the arcing conditions, then methods of mitigation could be categorized and investigated. Test Equipment Table 2 provides a list of the major equipment used during the field testing. Hall effect type clamp-on current probes were selected to measure the direct current traction circuits at fouling wires and negative return feeders. Voltage transducers were used to isolate the rails from the test recorder. Field Testing Equipment Item Astro-Med TMX, data recorder, 18 channel, with three (3) UNIV-6 AEMC MR561, clamp-on current sensor, 1500 A dc AYA P3C-7500-C, clamp-on current sensor, 7500 A dc Probe-Master 4231 HV, voltage sensor APC BE550G, UPS to power recorder on board train, 550 VA, 330 W, 120 V ac output Notes on Testing The Astro-Med recorders, cable, and all measuring devices were set up and fully tested prior to transporting to the field. Current and voltage probe polarities were checked and marked on the devices. Coax cable attenuation was checked to ensure that the expected signals would propagate up to 1000 ft. One lesson learned was that a GPS-based time card should have been rented with each recorder in order to synchronize the wayside and onboard recorders. This would have made post-processing of the results easier. RG58 coax cable was suitable for distances up to 1000 ft due to the relatively low frequency of the transients compared to the attenuation ratings of the cable. There were two factors that contribute to interference on long coax cable runs: 1) electromagnetic fields from underground cables and 2) wet conditions. It was noted during testing that when rain made the cable wet, there was noticeable interference on the test signals. Also, at Harold, there was periodic signal interference, but this was eliminated by routing the coax cables using a different path. Large split-core clamp-on hall effect current probes are subject to electromagnetic interference. They are sensitive to how they are positioned. For best results, they need to be zeroed each time they are initially setup. When zeroed (set to 0 A when reading no current), they should ultimately be set after positioning where they will be placed during testing. A small battery-powered coil of wire, current limited by a resistor, and multimeter can be used in the field to test the current probe when zeroed at 0 A and some higher test current, such as 40 A. The test coil is also handy for verifying current probe polarity prior to installing on the test circuit. Eq. 2 6.1 Connect voltage probes to running rails Table 2. Eq. 1 6.0 Connect measuring devices to TMX recorder Use Record voltage across IJ and current in fouling wires and negative returns Measure current in fouling wires and on train Measure current in negative return feeders Measure voltage across IJ Keep Astro-Med TMX powered on train during 3rd rail gaps 4 Destructive Arcing of Insulated Joints in DC Electrified Railway Figure 6. Battery-powered coil and multimeter Figure 7. Crestwood test configuration 6.3 MNR Crestwood Crestwood has experienced rapid destruction of IJs at the #21 crossover due to electrical arcing observed when electrified trains pass over the IJs. These IJs are in a crossover and do not have impedance bonds. A series of tests was performed in order to quantify the magnitude of current and voltage in the track and train circuits under various operating scenarios. The closest substation, B16, was located just south of the #21 crossover. This substation supplies the majority of current to a train at #21 crossover. This test configuration was instrumented by placing 4000 A current probes around the IB rail leads in the return path of train currents flowing to Substation B16. The fouling wires on the crossover were monitored using 1500 A current probes. Voltages across each IJ were measured using voltage probes that could be adjusted to either 140 V or 1400 V full-range. Two recorders, A and B, were used wayside and two recorders, C and D, were used on the train. The equalizer bond between track 1 and 2 was installed for certain tests and is not used during normal operation. In Figure 7, as the train moves south, it crosses the 21E IJ first. The last axle of an 8-car train will break the 21W IJ last. The potential probes were adjusted from 140 V to 1400 V once high transients were measured. The TMX recorder plots are shown below. Recorders A and B measure currents in fouling wires, current in impedance bond leads, and voltages across IJs. Recorder C measures train voltage and current in one car. 21W IJ Volts 21E IJ Volts 21S-FW-1 Amps 21S-FW-2 Amps 21N-FW-1 Amps 21N-FW-2 Amps Figure 8 . Crestwood Recorder A The first two plots in Figure 8 show the voltage measured across each IJ. Note the large spike near the end of the plot. This is the transient arcing voltage that occurs as the last axle crosses the IJ. The bottom four plots in Figure 8 provide indication of the fouling wire currents as the train passes over the IJs. Figure 9 shows the current in the IB leads. Prior to crossing the IJ, the track 1 IB probes B10 and B11 have 2210 A and 2000 A flowing at one instant. This is about a 10% difference in current, demonstrating that the lead resistances are balanced. The other IB leads for track 2 on probes B9 and B10 have 2252 A and 2357 A at on instant, representing a difference of about 4.5%. Figure 10 shows the train increasing from almost 0 A to 757 A in 6.36 s for a rate-of-rise of 119 A/s per car during controlled acceleration. For an 8-car train, this 5 Destructive Arcing of Insulated Joints in DC Electrified Railway equates to 952 A/s. At one point, the car current suddenly dropped to 0 A, then back to 760 A when passing over a third-rail gap. The rate-of-rise during this re-energization occurred in 684 ms for 1111 A/s per car or 8.9 kA/s for an 8-car train. across the IJs, and no equalizer bond in place are shown in Table 3. The highest voltage across the IJ was measured at 291 V. At this time, the current in two fouling wires from one rail peaked at 2012 A as the arc was beginning to form. The train was drawing about 6088 A during this test. About 4250 A returned through IB1 as the train began to cross the IJ and 4633 A was returned through IB2 after the train crossed the IJ. The remaining return current is assumed to have been flowing to the adjacent substation to the north. The arcing duration, from beginning of the voltage rise to the peak, is about 30 ms. Figure 11 shows that the current in the west fouling wires flowing to track 1 almost doubles just prior to the last axle crossing 21W. This is because the train just traversed 21E, the IJs are staggered, and the voltage potential in the track circuits requires the current to rebalance, causing current to flow back to through the train to track 1. The time required for the current to rise is due to the track inductance. The current being broken by the last wheel to cross the IJ is the sum of the two fouling wires measured by probes A5 and A6, which are about 2012 A just prior to the arc development. This current collapses to 160 A in 30 ms, for a di/dt = 61.7 kA/s. The following table provides the maximum voltages and currents recorded at Crestwood. Crestwood Test Results, Test M-1b 2-B16-IB-W Amps 2-B16-IB-E Amps 1-B16-IB-W Amps 1-B16-IB-E Amps Figure 9 . Crestwood Recorder B Train voltage Probe Designation A1-21W-IJ A2-21E-IJ A3-2-21S-FW-1 A4-2-21S-FW-2 A5-1-21N-FW-1 A6-1-21N-FW-2 B8-2-B16-IB-W B9-2-B16-IB-E B10-1-B16-IB-W B11-1-B16-IB-E Train current (reverse polarity) Figure 10. Train Recorder C The train current in Figure 10 is shown with reverse polarity, i.e., as current increases, the above plot shows it increasing in the negative direction. A7-21-EB Train Voltage 291 V transient across IJ Train Current Value 291 V 254 V 749 A 718 A 982 A 1030 A 2264 A 2369 A 2228 A 2022 A 3505 A (121 A just prior to last axle crossing) 576 V 761 A average per car 876 A peak per car 6088 A average for 8-car train Table 3. Subsequent testing at Crestwood showed that the voltage transient was improved by connecting an equalizer bond between tracks 1 and 2 (measured by probe A7-21-EB). The number of train cars can be counted crossing an IJ by observing the pattern in the voltage measurements. A sample observation has been annotated in Figure 12. 982 A to 73 A in 29.4 ms Figure 11. Voltage across 21W and current in fouling wires Significant test results for a train operating at 100% power, moving south across the #21 crossover, no IBs 6 Destructive Arcing of Insulated Joints in DC Electrified Railway Figure 12. Counting Cars Using a Voltage Plot 6.4 LIRR Harold The tests at Harold interlocking shown in Figure 13 were performed using a 12-car train. For full-power run, the 12-car M7 test train started on Track #ML2, at Harold Interlocking, West of the 848E signal. The train Engineer moved the train at low speed into the 849 crossover reverse, stopping the front of the train at the test starting point. The starting point for an eastbound run is defined as the lead car at the 849E turnout. Upon test initiation, the engineer accelerated to full power (100%) up to the permitted crossover speed of 40 mph. After clearing interlocking signal 854E, the engineer stopped the train and the test concluded. Screen captures of the complete Test #L3 and definition of the configured probes are provided in the following figures. An impedance bond was connected across the IJs prior to the start of the tests. However, the neutral connection between the bonds was not connected. While this left the IJs without a connected return path across them, it did allow current to flow between rails. For example, when the last axle of the train crossed the south IJ, the IB connecting the rails allowed current to flow from the north rail through the IB to track ML2, which would not normally have occurred. This was noticed in the recorder plots when the current in probes A3 and A4 dropped an average of 190 A each when the train crossed the south IJ. These IBs could have resulted in lower arc voltages than during normal operations. Figure 13 . Harold test configuration Figure 14. Harold Recorder A A magnified view of the IJ voltages and fouling wire currents is shown in Figure 15. Figure 15. Harold IJ Voltages and Fouling Wire Currents The following table provides the maximum voltage and currents recorded at Harold. 7 Destructive Arcing of Insulated Joints in DC Electrified Railway Harold Test Results, Test L3 Probe Designation A1-849N-IJ A2-849S-IJ A3-ML2-849W-FW-1 A4-ML2-849W-FW-2 A5-ML4-849E-FW-1 A6-ML4-849E-FW-2 A8-ML2-G02-IB-N A9-ML2-G02-IB-S A10-ML4-G02-IB-N A11-ML4-G02-IB-S Train Voltage Train Current Value 124 V 114 V 536 A 583 A 742 A 777 A 1387 A 1378 A 4205 A 3718 A 696 V 870 A average per car 1097 A peak per car 10440 A average for 12-car train Table 4. Testing proved that fouling wires and IBs were connected properly and that the IB imbalance did not exceed 13%. The maximum arcing voltage at Harold was half that of Crestwood. Some of this is attributed to the impedance bonds that were connected across the rails for purposes of connecting an impedance bond across the IJs during testing. However, in cases where the neutral was not connected across the IJ, currents that should have flowed from the crossover out through the fouling wires instead flowed from the crossover through the IB to the frog. Later testing with the neutral connected across the IJ using the IBs reduced the arc voltage to from 124 V to 23 V. Figure 16. Mineola test configuration During the 9:21 pm test at Mineola, the eastbound train has its last axle cross the north rail first, then the south rail. Arcing was only observed on the south rail. P1 Volts P2 Volts P5 Amps P6 Amps P7 Amps P8 Amps 6.5 LIRR Mineola P9 Amps The IJs at Mineola are different than at Crestwood or Harold in that they already have IBs connected across them during normal operating conditions. It was previously thought that arcs would only develop across IJs that did not have IBs. However, the current that passes through the IBs cannot be changed instantly when the train passes over the IJ. The current in the IBs provides a stabilizing voltage across the IJs and reduces the arc across the IJs, but does not eliminate it. Figure 17. Mineola Recorder A The following table provides the maximum voltages and currents recorded at Mineola. Mineola Test Results, Test 9:21 pm Probe Designation P1 IJ-N Trk 2 P2 IJ-s Trk 2 P5 IB-N Trk 2 P6 IB-S Trk 2 P7 G16-Trk 2a P8 G16-Trk 2b P9 G16-Trk 2c Train Voltage Train Current Value 27 V 37 V 4600 A 4261 A 3054 A 3028 A 3134 A Not recorded Not recorded Table 5. The maximum amount of current through the IB neutral across the IJ was the sum of probes P5 and P6, 8 Destructive Arcing of Insulated Joints in DC Electrified Railway which equaled 8861 A. The substation return leads summed up to 9216 A, showing that almost all current flowing through the IB was returning to the substation. An interesting current flow was observed as the last axle crossed the north and south rail IJs. Just before the north rail IJ is crossed (P1), the north rail IB lead (P5) has 3175 A and the south rail IB lead (P6) has 2737 A, a difference of 438 A. When the axle crosses the north IJ, but has not yet crossed the south IJ, the current in the north IB lead (P5) goes from 4261 A to 4179 A, while the south IB lead (P6) goes from 3738 A to 2620 A. Therefore, the difference in the IB leads is 4179 - 2620 A = 1559 A just before the axle crosses the south rail IJ. When the last axle crosses the south rail IJ, the current in the south rail lead (P6) of the IB goes from 2620 A to 3911 A, or a change of 1291 A, while the north rail lead (P5) only changes by 340 A. It is postulated that if the IJs were not staggered, then this transient in current in half of the IB would not take place and the arcing voltage would be less than the 37 V measured in the worst-case condition. Note that this current transient was never seen in the north rail IB lead and, consequently, no arcing was seen across the north rail IJ. As a follow-up to this test, LIRR plans on removing the stagger at this location for a trial period to see if this improves the arcing conditions. 7.0 Crestwood 100% Crestwood 50% Harold 100% Harold 50% Harold 25% Crestwood 100% Harold Coasting Crestwood 25% Crestwood Coasting IJ Type No IB across IJ No IB across IJ No IB across IJ, but in close proximity No IB across IJ, but in close proximity No IB across IJ, but in close proximity Cross bond No IB across IJ No IB across IJ No IB across IJ IJ Type Maximum Arc Voltage Mineola 100% IB across IJ 37 V Harold 100% IB across IJ 23 V 8.0 OBSERVATIONS The tests conducted at three locations and the trends in train operating power, rail and track bonding, and resulting arcing voltages shown in Table 6 lead to the following observations: The highest arc voltage occurred during the maximum train power and no bonding near the IJ. RESULTS Location Train Power Table 6. A summary of significant test results for all three test locations are provided in Table 6. Results are ordered from greatest to least arc voltage. Summary of Arc Voltage Testing Train Power Location Maximum Arc Voltage The lowest arc voltage occurred with impedance bonding across the IJ even with maximum train power. Cross bonding near the IJ lowers the arcing voltage across the IJ. Impedance bonding near an IJ lowers the arcing voltage across the IJ. Brighter arc flashes were noticeable for measurements that recorded higher arc voltages. Higher train currents contributed to higher arcing voltage. Reducing the train power while crossing an IJ reduces the arc transient across the IJ. The effects of higher train current can be mitigated by increasing bonding across the IJ. 132 V While more impedance bonding around the IJs helps mitigate destructive arcing, these cross bonds affect signaling and should be addressed on a case-by-case situation after proper analysis. 124 V 9.0 MITIGATION OPTIONS 9.1 Operational Adjustments 291 V 123 V Both analysis and test results indicate that trains under full power at the time the last axle crosses the IJs are the worst-case conditions contributing to the severe damage to the IJs and rail. Damage of the rail is proportional to the magnitude of the current flowing when the last axle crosses the IJs. As shown in the testing, train operation whereby the Engineer operates the train at coast while the last axle of the train is operating over the IJs reduces the voltage across the IJs and thus the potential arcing and resulting damage. 87 V 74 V 68 V 47 V 42 V 9 Destructive Arcing of Insulated Joints in DC Electrified Railway A potential mitigation then would be to establish in the Timetable Special Instructions "coast zones" whereby Engineers would move to coast for a distance such that the train will not be taking power when the last axle crosses the IJs. The specific limits of the zones could be marked in the field with signs so Engineers would know when to go to coast and when they would be able to resume power. The coast zone would need to account for the worst-case train lengths, i.e., shortest train for start coast and longest train for end coast. The ACSES II system that MNR and LIRR are implementing for Positive Train Control (PTC) has a capability to force a train to operate in coast. The feature was designed to ensure trains were in coast when operating through phase breaks. The feature includes a message from a transponder located at the point where the highest speed train would need to move to coast to ensure not being in a power mode or having pantographs extended (where they need to be lowered for phase breaks.) Due to the complexity of determining train speed and location relative to the phase break and variations in train makeup, the function was not implemented. For similar complexity, the ACSES capability was deemed not suitable to implement coasting to reduce arcing on IJs. 9.2 effectively eliminating the arcing. This was visually bornout in the testing at Harold by observation of the IJs under train movement and by the test results. However, introducing impedance bonds in crossovers both jeopardizes broken rail protection (BRP) and imbalances the track circuit, resulting in a destabilized tract circuit. 9.3.3 Shunting IJs While Train Passes Several methods of shunting IJs until the last wheel of the train passes have been investigated. These methods provide an electrical by-pass in parallel to the IJ in the presence of an electric train, thereby theoretically eliminating the arc at the IJ when wheels cross the IJ. The methods investigated for shunting IJs include: An active circuit that detects the presence of a train and closes a contactor creating the by-pass circuit 9.4 Train Propulsion Circuit A passive circuit using back-to-back GTOs and a trigger mechanism, which activates with a predetermined value of the voltage across the IJ A passive circuit using varistors that are activated by the voltage across the IJ. Concept Solutions Several concept solutions are offered, although none have been tested in actual railway operation for the purpose of reducing arcing across IJs. Although arcing has occurred on the railroads prior to the use of the M7s, it is suspected that the M7 propulsion circuit is contributing to the arcing, which combined with the high current capabilities used to achieve train performance, is damaging IJs. The onboard LRC circuit is integral to the EMI filtering of the propulsion and auxiliary power circuits and is viewed necessary by vehicle engineers. Detailed analysis of the propulsion circuits has been proposed using EMTP software. 9.3 9.4.1 Additional Return Rail (4th Rail) The concept of this mitigation is to provide an additional return path in the area of IJs that have demonstrated arcing. In addition to the supplemental return path around IJs, the concept would require the equivalent of a third rail pickup shoe on all electric rail vehicles. It is noted that a line of the London Underground Transit System uses a 4th rail for traction for the entire system, eliminating the use of running rails at all for the traction system. The 4th rail is installed in the gage of the track. Wayside Systems 9.3.1 Cross Bonding Track Circuits Additional cross bonding can reduce the voltage across the IJs and thus the arcing. This was demonstrated in the testing with equalizer bonds at CP 116 and with impedance bonds in the crossovers at Harold. The problem with additional cross bonding is that they jeopardize the ability of the signaling system to detect broken rails. Cross bonding must be designed and used carefully so as to not impact broken rail detection. 9.4.2 Mechanical Shunting This concept involves placing a non-conductive, spring-loaded bar on the inside of a running rail at the affected IJ location. The non-conductive bar is anchored to the rail at one end and has a free-moving contact at the other end of the bar. The free-moving contact is positioned far enough away from the rail that it won't arc over to the rail. A fixed contact is mounted just below the movable contact on the tie. The fixed contact is wired to the rail on one side of the IJ and the free-moving contact is wired to the other rail on the opposite side of the IJ. As 9.3.2 Impedance Bonds Across IJs The installation of impedance bonds in crossovers provides a path for return current around the IJs, 10 Destructive Arcing of Insulated Joints in DC Electrified Railway the train passes, the wheel flange presses down upon the non-conductive bar, making the contacts touch and shorting the IJ. Once the axle passes, the bar opens and the IJ resistance is restored. Any arcing will occur across the fixed and free-moving contacts. The contacts can be periodically replaced during routine maintenance and should keep destructive arcing from damaging the IJ. electrical property of graduated resistance to electrical current in the vicinity of IJs. Such a rail technology exhibiting this property and having the strength of the existing steel rail is not known to exist and would require research and development. The purpose of the graduated resistance would be to reduce the rapid change in current as the wheels cross the IJ, eliminating the resulting arc. 10.0 RECOMMENDATIONS The near term solutions that can be acted on immediately include operational procedures, such as reducing train power while operating across IJs, and increased cross bonding (subject to broken rail analysis). For the most severe locations that experience arcing damage on a regular basis, such as the 849 crossover at Harold and the 21 crossover at Crestwood, railroads should implement operational procedures to reduce the arcing. Each location that is experiencing arcing can also be looked at on a case by case basis for cross bonding solutions that include using impedance bonds as equalizers. As has been noted, this mitigation requires a thorough analysis of the impacts that the added cross bonding may have on broken rail protection. While this is the quickest and least costly approach to mitigating the worst-case arcing in the near term, this is not considered an optimal solution and additional mitigation should be investigated. Other methods, such as using passive shunts, aligning IJs that already use impedance bonds (such as at Mineola), and modifying vehicle propulsion systems, should be further analyzed and tested. Longer term solutions include additional cross bonding where possible using reactors, if necessary, to provide broken rail protection, new IJ technology, and deploying passive shunts if prototypes prove successful. Use of reactors with added cross bonding is considered long term only because it is assumed that the acquisition and implementation of the reactors is more difficult, costly, and requires more time to implement than the use of impedance bonds in the equalizer configuration. Use of reactors should also be evaluated for their added inductance to the circuit to ensure that they do not exacerbate the arcing. Lap joints and new IJ technology should be monitored and tested where applicable. Contactors and electronic shunting devices may provide a solution, but they need significant development to determine if reliable control circuitry and device ratings could be developed. Figure 18. Mechanical Shunt 9.4.3 Long-Lap IJ The long-angle or long-lap IJ is under test by freight railroads [4]. The purpose of the long-lap joint is to mitigate the effects of mechanical stresses that occur on IJs when each rolling stock wheel crosses over the IJ. The joint has some promise of mitigating the destructive arcing MNR and LIRR have encountered by providing a longer transition of the last axle between the circuit that the train is leaving to the circuit that the train is entering. LIRR intends to test this type of IJ in the future. It has been tested at Transportation Technology Center, Inc. (TTCI) with good results from the mechanical perspective of the IJ. However, TTCI was not testing for the destructive arcing problem encountered on MNR and LIRR. Figure 19. Long-Lap IJ 11.0 9.4.4 Graduated Resistance IJ An ideal solution for the arcing at crossover and turnout IJs would be a rail technology that has the REFERENCES [1] "MNR & LIRR Insulated Joint Arcing Study," SYSTRA Engineering, Inc., January 2013. 11 Destructive Arcing of Insulated Joints in DC Electrified Railway [2] Somerville, J. M., The Electric Arc, London: John Wiley & Sons, Inc., 1959. [3] Rudenberg, R., Transient Performance of Electric Power Systems, New York: McGraw-Hill Book Company, Inc., 1950. [4] Akhtar, M., et al., "Revenue Service Evaluation of Advanced Design Insulated Joints," AREMA Conference Proceedings, 2008. 12