SUMMARY REPORT RALPH WALDO EMERSON MIDDLE SCHOOL Location/Address Initial Year Built Building Area National S.F./Student PRN SD 64 S.F./Student Difference +/Site Area 8101 N. Cumberland Avenue, Niles, IL 60714 1998 135,579 131 177 -46 18.5 acres Building Capacity Analysis Teaching Stations (TS) Number Students per TS Capacity 23 2 27 10 621 20 Classrooms Special Ed Total 25 System Type Building Factors Electrical Mechanical Roof Total Grounds 641 Cost to Correct Priority 1 Priority 2 Priority 3 $882,590 $16,000 $0 $470,039 $199,750 $0 $0 $449,054 $154,296 $0 $0 $18,780 $528,544 $16,000 $0 $2,205 $882,590 $648,804 $173,076 $546,749 $796,505 $0 $0 $796,505 FCI Replacement 2.6% $33,894,750 $1,679,095 $419,774 Campus Total Other Costs Grand Total $2,098,869 System Deficiency Summary 34% Building Factors Electrical 65% 0% 1% Mechanical Roof Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 19-Jul-11 Building: Reviewer: ASSESSMENT Rating 1-New 2-Good 3-Fair 4-Poor 5-Failed Item No. Description/Evaluation 1 Land Site is approximately 18.5 acres (per 2010 survey), including green space to west, owned by Park District; state guidelines for 7-9 grades is 15 acres, plus 1 acre for every 100 students (23 acres total) Reviewer: OPINION OF PROBABLE CONSTRUCTION COST K. VanSant Rating Photo 1 S-1 SITE Item Land School is located adjacent to busy collector street Site is slightly undersized for current enrollment numbers Soccer field to the west is owned and maintained by the Park District 2 Preparation Site is relatively flat, with areas of poor drainage in the north parking lot; no steep inclines, except to west at soccer field for dual-use detention 19-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL 2 Priority K. VanSant Unit Unit/Cost Number Cost - $0 - $0 $0 $0 $0 $0 - $0 Preparation $0 $0 3 4 Access School is primarily accessed from the west; drive entrance is off of a semi-busy street with 3-way stop sign; additional site access on east side, adjacent to Jefferson School by way of a one-way street terminating at a stop light with a busy collector street Onsite student drop-off area provided to north 3 Parking Approximately parking for 125 cars in west parking lot, and approximately 10 spaces provided in small east lot (not marked well) Parking lot to north needs to be resurfaced, potholes need to be repaired; Plans in place to patch areas of the large north lot and drive aisles this year by using a Change Order for current site project work being conducted at Franklin ES Asphalt parking areas in fair condition 4 6 211056.01 - $0 - $0 $0 $0 - $0 Parking Refer to items below Asphalt drive aisle in fair condition 5 Access Sidewalks Perimeter asphalt sidewalk to east abuts Greendale St. and is separated by only a concrete curb Some onsite sidewalks are generally in good condition; some areas with large cracks ranging 2-3 inches in width, noticeably every 20-25 feet Tall fence provided along busy street (Oakton St.) to south for student safety 5 Drainage Site is in an area with high water table and has poor drainage in some areas; some standing water occurs in north parking lot and portions along west side of building after moderate rainfall In general, Scott believes that the large parking lot to the north of the school has good drainage, but the slopes/pitches in some areas of the site are bothersome to him 6 $0 Provide new asphalt paving and parking striping 3 SY $24.00 6,805 $163,320 Provide new asphalt paving 3 SY $20.00 2,778 $55,560 $0 Sidewalks Patch/compact sections of paved walk $0 3 SY $50.00 20 $1,000 - $0 $0 $0 - $0 - $0 Soccer field slopes from north to south with planned detention area; water from this detention appears to be encroaching too far north at southeast corner of soccer field - $0 Downspouts on the north side of building appear to be tied into underground stormwater system and catch basin to north - $0 Drainage 1 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 19-Jul-11 Building: Reviewer: ASSESSMENT Rating 1-New 2-Good 3-Fair Item No. Description/Evaluation *xA18 7 4-Poor 19-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Reviewer: OPINION OF PROBABLE CONSTRUCTION COST K. VanSant 5-Failed Rating S-1 SITE Item Photo K. VanSant Priority Unit Unit/Cost Number Cost Issues with ice on south path in winter and standing water near the south entrance Provide grading improvements; seed/sod areas 3 SF $2.00 700 $1,400 Grass has receded around stormwater catch basin to north of northwest entrance; grade has eroded leaving catch basin exposed 4-6” above grade Standing water around concrete splash blocks create erosion, areas with grass receding Areas around building perimeter at north exposure where grass has receeded Site has poor drainage and paving areas are in poor condition Provide compacted fill around catch basin, seed area 3 LS $1,000.00 1 $1,000 Provide grading improvements; seed/sod areas 3 EA $500.00 9 $4,500 Seed/sod area Provide grading improvements and new paving 3 3 LS EA $3,000.00 $439,725.00 1 1 $3,000 $439,725 $0 $0 Provide bushes and landscaping 3 LS $100,000.00 1 $100,000 Prune trees and bushes away from building 3 LS $2,000.00 1 $2,000 *xA18 7 Landscaping Area around school has trees ranging from 15-20 feet in height; minimal low-level landscaping/bushes/plantings Pruning and maintenance needed on existing trees/bushes; trees planted too close to exterior building walls Green space provided adjacent to building for outdoor learning, but not much for variation in site to accommodate environmental education Landscaping - $0 $0 $0 8 Athletic Fields Soccer field to the west is owned and maintained by the Park District Existing exterior water fountain at northwest of building is clogged and not draining properly 8 Playground N/A 9 Athletic Fields - $0 $0 $0 9 $0 Provide hard surface play area with basketball hoops, etc. No hard surface play areas provided for student activity (ie basketball, etc.) Rating COST SUB-TOTAL Rating 1-New 211056.01 Playground 3 LS $25,000.00 1 $25,000 $0 $0 $796,505 Recommendations: Priority 2 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 28-Jul-11 Reviewer: ASSESSMENT Rating A-1 Item No. 1 2 1-New 2-Good 3-Fair 4-Poor 5-Failed BUILDING FACTORS - Interior Description/Evaluation ADA Accessibility Entrances are accessible; building appears to meet ADA requirements Accessible shower/toilet stalls provided Multi-purpose room stage accessible by ramp Drinking fountains appear to be in compliance with ADA requirements Foundation: Concrete foundations appear to be strong and stable; no major cracks observed 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: Reviewer: K. VanSant Rating K. VanSant OPINION OF PROBABLE CONSTRUCTION COST Photo A-1 A-1 BUILDING FACTORS - Interior Item No. Item 1 ADA Accessibility - 2 Priority Unit Unit/Cost Number Cost $0 $0 $0 $0 $0 $0 Foundation: - $0 $0 $0 3 Walls: Majority of interior partitions are CMU with some metal wall partitions Interior walls have been constructed with appropriate control and expansion joints 3 Walls: - $0 $0 $0 4 5 Entrance/Exit: Exterior doors open outward and are equipped with panic hardware Proper number of stairways provided for student egress Good circulation and adequate entry/exit points around the building 4 Energy Conservation: 5 Entrance/Exit: - $0 $0 $0 $0 $0 Energy Conservation: $0 $0 $0 6 Windows/Doors: Wood doors provided throughout, generally in good condition; some contain vision panels 6 Windows/Doors: - $0 Hollow metal door frames in good condition - $0 Doors appear to meet wall ratings - $0 Wired glass observed in all openings; size of glazed openings appear to meet current standard for maximum sized openings - $0 $0 $0 7 211056.01 Floors: Corridors contain worn carpet, due for replacement Classrooms contain worn carpet, due for replacement Offices/Administrative contain carpet in fair condition LRC contains carpet in fair condition Multi-purpose room contains rubber flooring in good condition Gymnasium contains wood flooring in good condition Fitness room contains rubber flooring in good condition Entrance lobby contains quarry tile in good condition 7 Floors: Provide new carpet tile Provide new carpet tile Provide new carpet tile Provide new carpet tile 3 3 3 3 - SY SY SY SY $35.00 $35.00 $35.00 $35.00 1,560 5,702 700 700 $54,600 $199,570 $24,500 $24,500 $0 $0 $0 $0 1 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL 28-Jul-11 Date: Building: Reviewer: ASSESSMENT Rating 8 Reviewer: K. VanSant K. VanSant OPINION OF PROBABLE CONSTRUCTION COST 1-New 2-Good 3-Fair 4-Poor 5-Failed Stairways - rubber stair treads/nosing strips in fair condition; strips are damaged/broken in areas Bathrooms areas typically contain ceramic tile in good condition Ceilings: 2'x2' ACT typical throughout building; generally in fair to good condition Lockerooms and kitchen areas provided with ACT appropriate for wet/clean areas Gypsum board soffits in miscellaneous areas appear to be in good condition Large classrooms (with operable partitions) - damage to ceiling grid/tiles adjacent to operable partition 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Provide new rubber treads/nosing strips 1 LF $10.00 100 - 8 Ceilings: Provide new ceiling tiles, grid to remain $1,000 $0 $0 $0 3 SF $2.00 105,187 $210,374 - $0 - $0 Replace tiles and damaged grid components 2 SF $3.50 576 $2,016 $0 $0 9 Casework: Plastic laminate casework provided throughout, generally appears in good condition Science rooms equipped with wood casework and chemical-resistant counters Wood storage cabinets provided in industrial tech areas Plastic laminate and metal shelving units provided in LRC Wood window stools provided throughout building appear to be in good condition 9 Casework: - $0 - $0 - $0 $0 $0 $0 10 11 Hardware: Door hardware in good condition and meets accessibility standards Keying system appears to be compatible throughout building 10 Restrooms: Restrooms comply with current ADA design standards Typical finishes include: ceramic wall and floor tile, ACT ceiling Wall-mounted fixtures provided Mounting locations/heights of accessories and fixtures appear to meet current standards 11 Hardware: - $0 $0 $0 $0 - $0 $0 $0 - $0 Restrooms: $0 $0 12 Support Spaces: Multi-purpose room provided with acoustical wall treatments and acoustical CMU 12 Support Spaces: $0 $0 13 211056.01 Safety: All classrooms, corridors, auxiliary spaces and toilet rooms have strobes; heat detectors are located in corridors School is equipped with fire extinguisher cabinets or fire extinguishers Building is equipped with sprinkler system 13 Safety: - $0 - $0 $0 $0 $0 2 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 28-Jul-11 Reviewer: Rating 14 Reviewer: K. VanSant ASSESSMENT 14 Conveying Systems - Recommendations: A-2 BUILDING FACTORS - Exterior Item No. Description/Evaluation Foundation: 1 K. VanSant OPINION OF PROBABLE CONSTRUCTION COST 1-New 2-Good 3-Fair 4-Poor 5-Failed Conveying Systems Dover elevator provided to access all levels; 2,500 lb. capacity A-1 COST SUB-TOTAL A-1 BUILDING FACTORS - Interior 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: Rating $0 $0 $0 $516,560 Priority Photo A-2 A-2 BUILDING FACTORS - Exterior Item No. Item 1 Foundation: Priority Unit Unit/Cost Number Cost $0 $0 2 3 Walls: Exterior walls have been constructed with appropriate control and expansion joints Exterior walls constructed with brick, board insulation and 8" CMU 2 Entrance/Exit: Main entrance is provided with canopy, other entrances do not have exterior protection 3 Walls: - $0 - $0 $0 $0 Entrance/Exit: Provide entrance canopies 3 EA $5,000.00 3 $15,000 $0 $0 4 Energy Conservation: Large Aluminum windows allow for good natural daylighting; window systems are due for replacement 4 Energy Conservation: Replace aluminum framed windows with double paned window systems 1 EA $750.00 265 $198,750 2 SF $60.00 2,538 $152,280 $0 Large spaces (multi-purpose, gym, etc) have clerestory windows with translucent panels; generally appear to be in good condition Replace clerestory translucent panels 5 Windows/Doors: 5 Windows/Doors: 6 Hardware: 6 Hardware: $0 $0 $0 $0 $0 $0 $0 $0 211056.01 3 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 28-Jul-11 Reviewer: Rating 7 A-2 A-2 1-New 2-Good Safety/Security 3-Fair COST SUB-TOTAL BUILDING FACTORS - Exterior 4-Poor Reviewer: K. VanSant ASSESSMENT 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: K. VanSant OPINION OF PROBABLE CONSTRUCTION COST 5-Failed 7 Safety/Security $0 $0 $0 $366,030 Recommendations: A-3 EDUCATIONAL SPACES Item No. Description/Evaluation Special Education Classrooms 1 Rating Priority Photo A-3 A-3 EDUCATIONAL SPACES Item No. Item 1 Special Education Classrooms Priority Unit Unit/Cost Number Cost $0 $0 $0 2 3 Kindergarten/Pre-K: N/A 2 Classrooms: Larger classrooms are equipped with moveable partitions to provide flexibility in class size 3 Kindergarten/Pre-K: $0 $0 $0 Classrooms: $0 $0 $0 4 Media Center: Large, attractive space with good natural lighting; computer lab space and adequate small group space 4 Media Center: $0 $0 $0 5 Gymnasium: Large gym with operable partition for separation of class activities; allows for different class sizes Gym provided with acoustical wall treatments and acoustical CMU 5 Gymnasium: $0 $0 $0 6 Music: Music spaces appear adequate in size to meet class needs and are provided with proper sound treatment 6 Music: $0 $0 $0 7 8 211056.01 Art: Art spaces appear to be adequate with storage and prep areas 7 Science: Science rooms appear to be well-equipped with casework/storage and workspace; teacher station provided 8 Art: $0 $0 $0 Science: $0 4 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 28-Jul-11 Reviewer: Rating 1-New 2-Good 3-Fair 4-Poor Reviewer: K. VanSant ASSESSMENT 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: K. VanSant OPINION OF PROBABLE CONSTRUCTION COST 5-Failed $0 $0 9 10 11 A-3 A-4 Item No. 1 2 3 Technology: Computer labs provided Smartboards provided in some classrooms 9 Small Group Instruction: Limited areas for small groups provided 10 Storage: 11 COST SUB-TOTAL SUPPORT SPACES Description/Evaluation Administrative Spaces: Administrative areas are basic, but provide proper appearance for age group of children Counselor's office appear to be adequate Administrative personnel are provided sufficient work space and privacy Technology: $0 $0 $0 $0 Small Group Instruction: $0 $0 $0 Storage: $0 $0 $0 $0 Rating Photo A-4 A-4 SUPPORT SPACES Item No. Item 1 Administrative Spaces: Priority Unit Unit/Cost Number Cost $0 $0 $0 $0 $0 Teacher Spaces: Teacher's lounge on first floor with casework, tables, etc. 2 Clinic: Health/clinic area appears to be appropriately sized with cot space and sink/cabinet storage, and adjacent toilet room; a separate office space would be ideal 3 Teacher Spaces: $0 $0 $0 Clinic: $0 $0 $0 4 5 Reception: Suitable reception space is available for students, teachers, and visitors 4 Cafeteria: Full-service kitchen with serving line provided; storage areas provided appear adequate 5 Reception: $0 $0 $0 Cafeteria: $0 $0 $0 6 Misc/Other: 6 Misc/Other: $0 $0 $0 211056.01 5 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 28-Jul-11 Building: Reviewer: Rating 1-New A-4 A-4 COST SUB-TOTAL SUPPORT SPACES 2-Good 3-Fair 4-Poor Reviewer: K. VanSant ASSESSMENT K. VanSant OPINION OF PROBABLE CONSTRUCTION COST 5-Failed $0 Recommendations: S-4 ROOF SYSTEM Item No. Description/Evaluation Roofing Type/Material: Majority of roof areas are pitched with asphalt shingles, original to the building (1998); all pitched areas have ridge vents In general, substrate at pitched roof areas appears to be solid Rating Priority Photo S-4 S-4 ROOF SYSTEM Item No. Item Roofing Type/Material: In general, equipment curbs at flat roof appear to be in good condition Problems during the winter months occur with snow build-up on the ridges; water gets into the ridge vents and leaks into the spaces below Miscellaneous nail pops below asphalt shingles were observed throughout the roof areas N/S west pitched roof area, above classroom wing - multiple areas with missing asphalt shingles N/S west pitched roof area, southwest corner - metal soffit panel is not attached and is hanging down E/W portion of pitched roof, above elective classrooms - shingles missing in central area of roof, near ridge E/W portion of pitched roof, above elective classrooms - miscellaneous "soft" spots observed along the south slope toward the ridge E/W portion of pitched roof, pop-up on north side (above elective classrooms) - shingles missing Roof area over LRC - top layer degrading; large amount of air pockets on south slope Roof area over LRC - multiple punctures/holes in cap sheet Priority Unit Unit/Cost Number Cost $0 - $0 - $0 - $0 Provide heat trace at vented ridge lines 1 LF $45.00 2,000 $90,000 Replace shingles 1 SF $23.00 50 $1,150 Provide new shingles 1 SF $23.00 15 $345 Secure soffit panel 1 LS $150.00 1 $150 Provide new shingles 1 SF $23.00 10 $230 Provide new shingles 1 SF $23.00 10 $230 Provide new shingles 1 SF $23.00 10 $230 Replace roof in this area with shingles, in lieu of modified bitumen 2 SF $23.00 660 $15,180 Refer to roof replacement item above $0 Roof area over LRC - poor transition between different roofing systems, both sides of cricket/gable Refer to roof replacement item above $0 Roof area over LRC - poor transition between different roofing systems at junction of southeast corner of exterior wall Replace transitions 2 LS $500.00 1 $500 Repair gap between soffit and fascia 3 LS $25.00 1 $25 Provide new shingles 1 SF $23.00 3 $69 Provide new protective top coating 1 SF $60.00 5,000 $300,000 Provide splash blocks and protective pad at all downspouts 1 EA $50.00 10 $500 Replace each vent 3 LS $100.00 1 $100 Pitched roof area over LRC/mechanical room (east side) - gap between metal fascia and soffit panels Pitched roof area over LRC (west side) - portions of shingles missing at northwest corner Large flat roof area, adjacent to MPR - top coating is degrading in multiple areas, especially at downspouts from higher roof areas Large flat roof area, adjacent to MPR - no splash blocks provided at downspouts from higher roof areas Large flat roof area, adjacent to MPR - plumbing vents do no meet current standard of 8" above roof surface 211056.01 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL 6 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 28-Jul-11 Building: Reviewer: Rating Reviewer: K. VanSant ASSESSMENT 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL 1-New 2-Good 3-Fair 4-Poor 5-Failed Flat roof area, between LRC/mechanical and south gym roofs - top coating is degrading in multiple areas, especially at downspouts from higher roof areas Flat roof area, between LRC/mechanical and south gym roofs - oil canning occurring at metal fascia on gym roof; gutter system dented Pitched roof area over MPR (west side) - portions of shingles missing and nail pops occurring where gutter straps are fastened to roof Flat roof area over entry (south area) - transition at roof curb needs repaired Issues with roof leaks in Multi-purpose room and Gym K. VanSant OPINION OF PROBABLE CONSTRUCTION COST Provide new protective top coating 1 SF $60.00 760 $45,600 Replace metal fascia 3 SF $8.00 160 $1,280 Replace shingles 2 SF $23.00 80 $1,840 Repair roof curb 3 LS $400.00 1 $400 Repair leaks 1 LS $10,000.00 1 $10,000 Insulation: Board insulation provided in exterior wall cavity Insulation: Drainage: Miscellaneous debris found in gutters Roof area over MPR - Downspout is disconnected from gutter Pitched roof area over MPR (west side) - gutter straps and fasteners are corroded Pitched roof area over LRC (northwest corner) - gutter straps and fasteners are corroded Drainage: Remove all debris from drainage system Connect downspout to gutter system 1 1 LS LS $500.00 $50.00 1 1 $500 $50 Provide new gutter straps and fasteners 2 LF $7.00 150 $1,050 Provide new gutter straps and fasteners 2 LF $7.00 30 $210 - $0 $0 $0 Openings/Skylights: In general, skylight curbs at flat roof appear to be in good condition Openings/Skylights: Flashing: Generally, flashing, counter-flashing and caulking appear to be in good condition; few areas require special attention Southwest corner of large flat roof area (modified bitumen system) crack/gap in counter-flashing at wall, brick visible below Flashing: Lighting Protection Lighting Protection - $0 - $0 Provide new counter-flashing and sealant this area 3 LS $400.00 1 $400 $0 S-4 COST SUB-TOTAL S-4 ROOF SYSTEM 211056.01 $470,039 Recommendations: Priority 7 Date: Building: Date: 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: Reviewer: Reviewer: F. Berger ASSESSMENT Rating 1-New 2-Good 3-Fair 4-Poor 5-Failed Item No. Description/Evaluation Duct Systems: Duct systems generally appear to be in good condition Rating F. Berger OPINION OF PROBABLE CONSTRUCTION COST Photo M-1 VENTILATING AND AIR CONDITIONING SYSTEM Item Priority Duct Systems: Unit Unit/Cost Number Cost $0 $0 $0 Air Handling Systems: Air Handling Systems: Cooling is provided by rooftop-mounted condensing units. There are four Carrier 38AH-084-600 BA units with reciprocating compressors and one McQuay ACP041. There have been numerous compressor failures on the Carrier units over the years. The units are in fair to heating/cooling good condition for the building is accomplished by a Variable Space ventilation and Air Volume system with air handling units located in the mechanical mezzanine. AHUs are all equipped with Variable Frequency Drives, hot water coils for heating, MDF room has a standalone Liebert unit for cooling gym storage rooms do not have auxiliary heating. Heating for the storage rooms is pulled from the gym by exhaust fans. The gym is heating-only, but does include economizer and demand control ventilation Additional ventilation for the main electrical closet needed. M-1 COST SUB-TOTAL M-1 VENTILATING AND AIR CONDITIONING SYSTEM 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL $0 $0 $0 $0 $0 $0 $0 $0 Recommendations: M-2 HEATING SYSTEMS Item No. Description/Evaluation Pumps: Heating water is distributed throughout the building via base-mounted B&G pumps, in a parallel pumping arrangement. The pumps do not have Variable Frequency Drives. Pumps appear in good condition Priority Rating Photo M-2 HEATING SYSTEMS Item Pumps: Priority Unit Unit/Cost Number Cost $0 $0 $0 211056.01 Piping: Hydronic piping appears to be in good condition Piping: Boilers Central heating plant consists of four Patterson Kelly SN1500 direct vent units. Capacity on each boiler is 1,500MBH input of natural gas, output is 1,275MBH. Boilers were constructed in December 1997, and provide hot water. The boilers are It was reported that some classrooms do not receive enough heat during winter Boilers Chiller N/A Chiller $0 $0 $0 $0 $0 $0 $0 $0 $0 1 Date: Building: Date: 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: Reviewer: Rating 1-New 2-Good 3-Fair Description/Evaluation M-2 COST SUB-TOTAL M-2 HEATING SYSTEMS 4-Poor Reviewer: F. Berger ASSESSMENT 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL F. Berger OPINION OF PROBABLE CONSTRUCTION COST 5-Failed M-1 VENTILATING AND AIR CONDITIONING SYSTEM $0 Recommendations: M-3 TEMPERATURE CONTROL SYSTEM Item No. Description/Evaluation Building System Monitoring: Building temperature controls are a hybrid Siemens/Landis and Gyr, Direct Digital Control/pneumatic system. System appears to be in good condition. Building management system front end computer is on an older DOS system, with no color or graphics. Building relief is by both gravity- and controlled-relief hoods and dampers. Problems in the past with snow ingestion into intake plenums M-3 COST SUB-TOTAL M-3 TEMPERATURE CONTROL SYSTEM Priority Rating Photo M-3 TEMPERATURE CONTROL SYSTEM Item Building System Monitoring: Priority Unit Unit/Cost Number Cost $0 $0 $0 $0 Recommendations: M-4 PLUMBING SYSTEM Item No. Description/Evaluation Domestic Water: Domestic cold water enters the building in the boiler room. There is a booster pump provided Domestic water piping appears to be in good condition Domestic hot water for the building is provided by a PVI 54P250 and a PVI 27P250 Waste and Vent: Waste piping systems appear to be in good condition. A new backflow preventer has recently been installed Priority Rating Photo M-4 PLUMBING SYSTEM Item Domestic Water: Priority Unit Unit/Cost Number Cost $0 $0 $0 $0 $0 Waste and Vent: $0 $0 $0 211056.01 Water Heaters Water heater appears in good condition Water Heaters Rainwater/Snow Drains: Some issues with seams on the gutters leaking Rainwater/Snow Drains: Exterior Water: Exterior Water: $0 $0 $0 $0 $0 $0 2 Date: Building: Date: 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: Reviewer: Rating 1-New 2-Good 3-Fair Description/Evaluation 4-Poor Reviewer: F. Berger ASSESSMENT OPINION OF PROBABLE CONSTRUCTION COST 5-Failed 211056.01 F. Berger M-1 VENTILATING AND AIR CONDITIONING SYSTEM $0 $0 Other: Other: Problems in the past with gas pressure. The local utility is in the process of upgrading the gas meter regulator assembly to correct this issue Fixtures appear to be in good condition. Urinals are provided with automatic flush valves Elevator is equipped with a sump pump M-4 COST SUB-TOTAL M-4 PLUMBING SYSTEM 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Recommendations: $0 $0 $0 $0 $0 $0 Priority 3 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 28-Jul-11 Reviewer: 2 Reviewer: F. Berger ASSESSMENT Rating E-1 Item No. 1 1-New 2-Good 3-Fair 4-Poor 5-Failed POWER Description/Evaluation Service: Main electrical service is 480/277 3-phase service 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: Rating F. Berger OPINION OF PROBABLE CONSTRUCTION COST Photo E-1 Item No. 1 E-1 POWER Item Service: Priority Unit Unit/Cost Number Cost $0 $0 $0 2 Switchgear: Main switchgear is Siemens 2500A-rated switch gear. Building is supplied through a 2500A-rated switch Switchgear: $0 $0 $0 3 3 Feeders: Feeders: $0 $0 4 5 *E4 Panelboards: Panel boards are installed throughout the building 4 Branch Distribution: Transformers for 480-208/120 are located in the main electrical room and electrical closet Science Rooms 103, 107, 203, 207, 303,307 - existing floor box receptacles are covered with dirt and may cause safety hazard if used 5 Panelboards: $0 $0 $0 Branch Distribution: $0 *E4 Provide new water-resistance floor boxes and GFCI receptacles 3 EA $762 21 $16,000 $0 $0 6 7 Emergency Systems: Emergency generator that powers emergency lighting 6 Master Clock System: Central clock/sound system is through a Rauland Telecenter 21 system, and includes a battery backup. System appears in good condition 7 E-1 COST SUB-TOTAL E-1 POWER Emergency Systems: $0 $0 $0 Master Clock System: $0 $0 $0 $16,000 Recommendations: E-2 LIGHTING Item No. Description/Evaluation 8 General Lighting Sources: - includes lighting only Priority Rating Photo 9 E-2 LIGHTING Item Priority General Lighting Sources: - includes lighting only Unit Unit/Cost Number Cost $0 $0 9 10 211056.01 Classrooms: T-8 lay-in grid fixtures with prismatic lenses. Lighting is all 277, and switched for two level lighting 9 Corridors/Public Spaces: Lay-in grid fixtures. Entryway and office areas use parabolic lenses 10 Classrooms: $0 $0 $0 Corridors/Public Spaces: $0 1 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: Reviewer: F. Berger ASSESSMENT Rating 1-New 2-Good 3-Fair 4-Poor 28-Jul-11 Reviewer: F. Berger OPINION OF PROBABLE CONSTRUCTION COST 5-Failed $0 $0 $0 11 11 Stage Lighting: Stage Lighting: $0 $0 12 12 Auditorium: Auditorium: $0 $0 13 13 Support Rooms: Support Rooms: $0 $0 14 15 16 17 18 19 Emergency Systems: Boiler room and science rooms are provided with emergency stops to shut off gas supply Emergency lighting is battery operated Fire alarm panel is a Simplex model 4100, with the main panel located in the electrical room 14 Exit Lighting: Exit lighting appears to be adequate 15 Pool: N/A 16 Gymnasium: Lighting in the fitness room is metal halide 17 Site lighting: Parking lot lights are controlled via a time clock 18 Electrial Controls: Washrooms and corridors are equipped with occupancy sensors 19 E-2 COST SUB-TOTAL E-2 LIGHTING E-3 SIGNAL Item No. Description/Evaluation 20 Voice/Telephone/Data: Emergency Systems: $0 $0 $0 $0 $0 Exit Lighting: $0 $0 $0 Pool: $0 $0 $0 Gymnasium: $0 $0 $0 Site lighting: $0 $0 $0 Electrial Controls: $0 $0 $0 $0 Recommendations: Priority Rating Photo 20 E-3 SIGNAL Item Voice/Telephone/Data: Priority Unit Unit/Cost Number Cost $0 $0 $0 211056.01 2 Date: Building: RALPH WALDO EMERSON MIDDLE SCHOOL Date: 28-Jul-11 RALPH WALDO EMERSON MIDDLE SCHOOL Building: Reviewer: F. Berger ASSESSMENT Rating 21 1-New 2-Good Sound Systems: 3-Fair 4-Poor 28-Jul-11 Reviewer: OPINION OF PROBABLE CONSTRUCTION COST F. Berger 5-Failed 21 Sound Systems: $0 $0 $0 22 22 Scoreboard: Scoreboard: $0 $0 $0 23 24 Fire Protection: Building has a sprinkler system with a fire pump and jockey pump. System appears in good condition Classrooms, corridors, auxiliary spaces and toilet rooms have strobes Heat detectors are located in the corridors 23 Initiating Devices 24 Fire Protection: $0 $0 $0 $0 $0 Initiating Devices $0 $0 $0 25 E-3 COST SUB-TOTAL E-3 SIGNAL 211056.01 25 Security: Building entrance is equipped with a security system Recommendations: Security: $0 $0 $0 $0 Priority 3