Development and In-Grid Demonstration of a Transmission Voltage SuperLimiterTM Fault Current Limiter Superconductivity for Electric Systems Peer Review July 29-31, 2008 1 SuperLimiterTM Outline • Program, Objectives, Organization and Schedule • FY2008 Accomplishments and Results • FY2009 Planned Performance and Milestones • Summary 2 Project Objectives • Develop 2G wire based on standard insert • Develop reliable HTS switching elements • Develop and fabricate FCL system - based on conventional utility standard relay, protection, DAQ, and communication systems SCE Valley Substation • Select high reliability cryogenic system with low operating and maintenance cost • Single phase high voltage demonstrator test • Test 3 phase FCL to appropriate standards at an accredited laboratory under utility supervision • Install and operate SuperLimiter FCL in the SCE grid The program develops and demonstrates a commercially viable 3 phase transmission level FCL in the SCE Grid 3 SuperLimiterTM Major Elements Cryostat sized for modular expansion Valley Substation 138kV termination in operation at LIPA site Insulation Stainless Strip HTS Film NiW Strip Solder Cooling System Similar to Navy Motor Program N+1 Redundancy Bifilar 2.2 MVA medium voltage module tested Jan. 2007 1.2 cm insulated HTS tape based on standard insert Design based on validated components is designed for modular expansion 4 Project Team • AMSC has supplied wire for 6 FCL programs and has orders for or installed over 7 GW of power equipment - System Engineering, HTS Wire • Southern California Edison has integrated HTS FCL in its grid - Requirements, System Integration, Test Site • Siemens has developed wire and element based FCL systems - FCL Modules, System Modeling • Nexans has provided transmission voltage level terminations for HTS systems - Terminations, High Voltage Design • Los Alamos National Laboratory - strong background in power systems, FCLs and HTS wire - AC Loss Measurements • TCSUH largest multidisciplinary university superconductivity and advanced materials research effort in the US - Wire Characterization Utility Advisory Committee • San Diego Gas and Electric • Pacific Gas and Electric • California Energy Commission • New York ISO • Con Edison • LIPA • Bonneville Power Administration • California ISO • University of California – California Institute of Energy Efficiency The program uses Team experience to prove transmission level FCL 5 FCL Operating Principle During fault conditions, superconductor becomes resistive and with reactor, limits current Supply Bus Normal State Resistance Virtual Switch Superconductor Under normal conditions, power flows through superconductor with virtually no impedance and system is Physical Switch electrically “invisible” Shortly after fault clears, power resumes flow through superconductor Reactor Physical switch opens to protect FCL system; reactor maintains current Load Bus FCL system operation is based on simple operating principles 6 SuperLimiterTM Overall Schedule SuperLimiter Program 2008 4 1 2 3 2009 4 1 2 3 2010 4 1 2 3 2011 4 1 2 3 2012 4 1 2 3 4 Phase 1a Design Model SCE site FCL wire development Switching module development Full size FCL termination manufacture and test Preliminary and detailed system design Phase 1b 1 Phase Demonstration Manufacture 1 phase FCL Laboratory test 1 phase FCL Phase 2 Manufacture and In-Grid Demonstration 3 Phase FCL system manufacture System laboratory test In-grid testing Component Validation Detailed Design Single Phase Test 3 Phase In-Grid Test The 3 Phase program validates the system at 115kV in the SCE grid 7 SuperLimiterTM Phase 1a Milestones HVD1 WS1 WS2 WS3 Milestone Phase 1a Date Detailed PSS/E model n SCE site 15-Sep-08 Analysis verified and accepted by SCE 8-Sep-08 Wire delivered to Siemens with appropriate certifications Slitting and lamination capability, lengths produced meeting specifications Testing capability for characterizing wire, AC loss characterization of coils Demonstrate switching module production capability meeting required specifications 15-Sep-08 10-Dec-08 HVD2 Preliminary design review complete Complete HVD3 Phase 1a detailed design review 14-Nov-08 HVD4 Summary report on Phase 1a 31-Dec-08 Verification Method Approved AMSC wire test procedures and certified test reports, approved LANL bifilar coil AC loss test procedure. Results of power tests and BIL tests. Fab and testing capacity demonstrated Interface of termination design accepted by AMSC and Siemens. Preliminary design drawing of the system. Meeting conducted HV subscale test of 1 termination with connection simulation to bushing validated. Report delivered to DOE 8 SuperLimiterTM Outline • Program Objectives, Organization and Schedule • FY2008 Accomplishments and Results • FY2009 Planned Performance and Milestones • Summary 9 SuperLimiterTM FY2008 Accomplishments and Results • AMSC – Bruce Gamble - System Design - Wire Development - Refrigeration • SCE – Syed Ahmed - Grid Integration • Siemens – Wolfgang Schmidt - Module Design - Performance Modeling - Test Results • Nexans – Frank Schmidt - Termination Design - Testing 10 Basic Specifications Requirement Prototype System Production Units Nominal Voltage 115kV rms 115-138kV Insulation Class 138kV 138kV Reactor Sized to Limiting Requirements Load Opening Switch Nominal Current 1,200A >2,000A Maximum Site Unlimited Fault Current 63kA >80kA Site Limited Current 40kA Source Switch Control FCL Vessel Assembly As required by customer Refrigeration System Protection and DAQ System Trip Current 1.6pu As required by customer Power Heat Team has approved a working specification for system 11 Wide FCL Wire Developed 0.075x12.0mm SS Lamina 10.0mm wide 2G HTS Sn/Pb/Ag Solder Attributes Average laminated wire thickness Laminated wire avg width range Room Temperature axial resistance Room Temperature axial resistance Min tensile strain (77K) Double bend tolerance Ic range over 1 m serial lengths Average wire Ic Criteria 0.26 +-0.03 mm 12 – 12.4 mm Result of 5x10m shipment met met Ω/m 0.09-0.12 (R emax-R emin)/R emean = 10% met met 0.30% 95% Ic retention @50mm met met (Imax-Imin)/Imean <= 20% Ph 1A prototype wires Target 200 A end of 1A met up to 173 Amps (350 A for Ph 1B & 2) FCL Wire performance on track for this phase 12 Two-in-hand Substrate-to-Substrate Configuration Used in FCL Bifilar Coils Two-in-hand Configuration HTS • Substrates are shielded, ferromagnetic loss is eliminated Tape 1 NiW Substrate • Losses close to Norris strip model Tape 2 HTS • Three bi-filar wound coils measured Wire Transport AC Loss Measurement - Bifilar configuration further reduces loss - Includes one 2-in-hand wound coil LANL 1.E-03 Q (J/m/cycle) • Q=650 W/phase extrapolated from coil data 1.E-02 Single Tape 1.E-04 50 Hz Tape 1 110 Hz Tape 1 1.E-05 50 Hz Tape 2 Norris model for strip Two-in-hand Configuration 1.E-06 Single tape 50 Hz 1.E-07 10 100 1000 Ip (A) Extrapolated FCL wire losses are a fraction of total phase refrigeration load 13 SuperLimiterTM Operating Conditions •Constraints -No bubbles around the bottom of bushing – sub-cooled LN2 -Termination dielectric requirement P > 3bar -Fast recovery time – saturated LN2 FCL Vessel Assembly •Solution -Operate FCL in sub-cooled LN2 with nominal operating temperature lower than design point. • FCL design at temperature 74K@5bar(a), but operate at temperature 72K@5bara • Temperature margin determines the number of faults the system can absorb before system is off-line to recool • 2K margin allows LN2 to absorb 57MJ energy (~6 faults) • 5 bar pressure will allow LN2 in coil vicinity absorb fault energy without bubbling Refrigeration System Power Heat FCL operates at high pressure sub-cooled LN2 temperature 14 SuperLimiterTM Refrigeration System Heat Load Value (W) Cryostat 850 Other Refrig. System 200 Terminations 900 Lines, Valves, Bayonets 350 AC Losses 1950 Total Max. Predicted 4250 Planned Capacity 6000 • AMSC has operated HTS systems in utility/harsh industrial conditions - LIPA and TVA/SuperVAR Project • DOE-FCL system based on lessons learned in those systems - Phase 1b – open cycle option shown above - Phase 2 - replace with closed cycle modification • Simplified, COTS based system • Significant margin planned for prototype system Refrigeration based on experience at LIPA and other AMSC utility HTS systems 15 SuperLimiterTM FY2008 Accomplishments and Results • AMSC – Bruce Gamble - System Design - Wire Development - Refrigeration • SCE – Syed Ahmed - Grid Integration • Siemens – Wolfgang Schmidt - Module Design - Performance Modeling - Test Results • Nexans – Frank Schmidt - Termination Design - Testing 16 SCE Profile • 50,000 Mile2 Service Territory • 120 years of service • $17 Billion T&D Assets Distribution • 85,000 Circuit Miles • 690,000 Transformers Customers • 4.7 Million Meters • 13 Million Customers • 22,889 MW Load Transmission • 12,600 Circuit Miles • 4,200 Transformers SCE is one of the largest utilities in the United States 17 SuperLimiterTM Southern California Edison • SCE is investing in the future - > $3 billion invested in T&D over the last five years - $11 billion planned infrastructure investments over the next decade. • SCE has considerable experience with superconducting Fault Current Limiters - Since 1993 in DOE-SPI, tested a 15kV FCL in 1999 - SCE role in this program is • Specifying requirements • Providing the prototype operation site • 138 kV Transmission Voltage level FCL addresses - Elimination of CB and other equip. replacement - Enhanced reliability, shorter customer outages - More stable, higher-quality electricity supply - A “self-healing” grid July 1999: FCL at a Southern California Edison substation SCE has unique experience with HTS FCL technology and this program extends this to transmission voltage levels 18 SuperLimiterTM Demonstration Site • Selection criteria Riverside - Voltage - Transmission planning - Civil engineering • Valley Substation selected • Located near Riverside, CA in a desert climate Valley Substation • Analysis used to select bus tie application • Significant load growth planned over the next 10 years - Tapped external reactor enables device to easily adapt The Valley Substation is selected 19 SuperLimiterTM Test Site Present Installation: Inland Empire • 4-3Phase, 336/448/560 MVA 525-120 kV, OA/FOA/FOA Transformers. • Sectionalized 115 kV bus each section fed by 2 transformers Devers 500 kV Serrano 500 kV “A” “B” 500 kV • Max. single-phase-to-ground fault = 30 kA • All 115 kV CBs rated 40 kA Planned Future Installation: • Load growth in the area and interconnection of new generators will require additional transformers • Fault current duty will rise above 40 kA “C” 115 kV 115 KV Outgoing 1000 MW Feeder Future Gen (Studied) Bus Tie (Selected) “AB” 115 kV 115 kV A bus tie application at the Valley Substation is selected 20 SuperLimiterTM Grid Integration Models • If the parallel reactor is optimized for the location, a greater reduction is achieved Location Fault current before Ipeak Irms Inductance Fault current after Reductions Ipeak Irms Ipeak Irms Outgoing Feeder Load side of fault 52.7 19.2 5.35 mH 37.2 12.4 Bus Tie Bus Tie 29.9 29.9 8.10 mH 8.10 mH 71.0 25.0 12.56% 16.39% 69.6 24.3 14.29% 18.73% Valley 115kV bus "AB" Valley 115kV bus "C" 81.2 81.2 29.5% 35.4% * Current in kA The flexibility afforded by the external reactor permits performance optimization and re-optimization following future system changes 21 SuperLimiterTM FY2008 Accomplishments and Results • AMSC – Bruce Gamble - System Design - Wire Development - Refrigeration • SCE – Syed Ahmed - Grid Integration • Siemens – – Wolfgang Schmidt - Module Design - Performance Modeling - Test Results • Nexans – Frank Schmidt - Termination Design - Testing 22 Siemens‘ Experience in Resistive Limiters Development of the resistive type SFCL for medium voltage based on high Jc YBCO thin films started at Siemens in 1992. 1992 1996 YBCO on IBAD buffered YSZ substrated 1997 100 kVA model, 4-inch-substrates YBCO on sapphire 2001 1.2 MVA; 7.2 kV 2004 0.9 MW; 900 V-DC 100 x 200 mm YBCO on sapphire 2007 2.25 MVA; 7.2 kV AMSC 2G wire 344S superconductors 23 Switching Module for the HV SFCL Project Main design characteristics • The switching module comprises 3 parallel x 17 series = 51 bifilar pancake coils per phase • Two in hand winding with 12 mm wide wire to increase the current Alternating current directions between adjacent turns of bifilar coils cancel most magnetic fields Regions stressed by BIL tests, numbering see next slide • Improved electrical strength due to: - Insulated wire - New contact design - Corona rings around the coils • Horizontal stack with radial supports between module and cryostat wall (1) (2) (3) (1) 24 Performance Modeling and Testing Voltage insulation considerations (1) Corona ring to vessel. Modeling at University of Braunschweig to determine Emax; measurement on mockup. y in m |E| in 106 V/m 0.4 6 (2) Surface flash over along radial supports. (3) Within a coil if one terminal is grounded after a first lightning strike and a second strike applies a voltage along the normal conducting tapes: 0.3 4 0.2 2 0.1 - Turn to turn 0 0.4 0.0 0.2 0.1 0.3 - Contact to tape (weakest part within coil): x in m Breakthrough voltage > 20 kVrms in air at 1 Electric field distribution at bar, even after 60 switching events. 650 kV between module and wall 25 Performance Modeling and Testing Electrode diameter = 100 mm Voltage insulation considerations: Radial supports Surface flashover along the radial supports could lower the breakdown voltage (BD) under lightning impulse test. The University of Braunschweig started small scale BD voltage measurements in air and liquid nitrogen to select an appropriate material for the supports. Sample diameter = 40 mm Average Breakdown Field Strength 14.28 16 14 kV/mm First results: • Significant dependence of BD on material in liquid nitrogen. Less dependence on surface finish. • 10 mm short sample seems not to reduce BD field strength in air. 11.40 12 12.29 8.84 10 8 6 4 2.55 2 0 10mm PMMA polished, air 5mm 10mm 10mm 10mm PMMA PTFE PMMA PMMA polished, machined, polished, machined, LN2 LN2 LN2 LN2 26 Performance Modeling and Testing Switching 2000 400 1000 200 0 0 -200 -1000 Voltage (V) Current (A) • First tests on a 3 m sample of 12 mm wide HTS-wire: Critical current 167 A @ 77 K, 258 A @ 72 K 77 K, sat., t: 100 ms • More than 60 switching test in saturated (77 K) and sub-cooled (72 K, 1.2 bar) LN2 72 K, 1.2 bar, t: 500 ms T: ~72 K -2000 0 10 20 30 Time (ms) 40 -400 50 27 Performance Modeling and Testing Resistance ratio (%) Recovery time • About 12 - 15 sec measured on full size dummy coil in sub-cooled LN2 • 12 mm wide dummy wire insulated with wrapped Teflon tape • Amount of LN2 available for cooling restricted by appropriate enclosure to simulate adjacent coils 110 T: 77 K, p: 1 bar T: 72 K, p: 1.2 bar 100 90 80 70 60 -0.05 10 0 20 Time (s) 28 SuperLimiterTM FY2008 Accomplishments and Results • AMSC – Bruce Gamble - System Design - Wire Development - Refrigeration • SCE – Syed Ahmed - Grid Integration • Siemens – Wolfgang Schmidt - Module Design - Performance Modeling - Test Results • Nexans – Frank Schmidt - Work done by Nicolas Lallouet - Termination Design - Testing 29 NEXANS experience High voltage & Superconductivity • NEXANS is one of the major worldwide leader in the cable industry, including high voltage cable system. • Since 1997, NEXANS is involved in superconductivity and has developed, within the frame of the LIPA 1 project, a complete high voltage superconducting cable system including its high voltage accessories. • LIPA 1 project has involved two world records: - Longest superconducting cable ever installed - Highest voltage used in a superconducting cable system (cable & accessories) • NEXANS experience on high voltage accessories developed within the frame of this project is the basement for the Fault current Limiter termination development. 30 NEXANS experience LIPA cable & accessories type test LIPA terminations design is the baseline of the FCL termination and was validated by type tests in 2006 (NEXANS Hanover laboratory test) • Validation of 138 kV level according IEC 60840: 9 190 kV / 30 min 9 Partial discharge < 5pC at 114 kV (after 1 min at 140 kV) 9 Lightning impulse test 650 kV (10 shots + & -) • Validation with current 9 Load cycle (100% 8 hours – no current 16 hours during > 20 days) 9 Termination designed up to 2400 A but several tests at higher current Specifications in accordance with FCL project 31 NEXANS experience Superconducting cable system connected on LIPA grid • Cable system installation in Long Island in 2007 • 3 phases • 600 m of cable • 6 terminations • Connected to the grid since 22th April 2008 • 138 kV level • No problem identified in cables & terminations since energization High voltage accessories for superconducting system validated in laboratory and inside real grid 32 FCL termination design Adaptation of LIPA termination LIPA termination part insuring thermal & electrical transition between cryogenic and ambient temperature is transfer to FCL termination design 33 FCL termination design Adaptation of LIPA termination LIPA termination part insuring the thermal & electrical transition between cryogenic and ambient temperature is kept for FCL termination design Connection to the grid Insulator: • Electrical field management at ambient temperature Transition insulator / intermediate enclosure: • Thermal stabilization at ambient temperature • Tightness insulator / intermediate enclosure with ambient atmosphere Intermediate enclosure: • Management of thermal gradient • Management of electrical field at cryogenic temperature • Tightness with pressurized liquid nitrogen Inner vessel interface (liquid nitrogen): •Main change with LIPA design •New electrical connection component •New electrical field distribution •Small thermal impact on termination bottom 34 FCL termination design Thermal & electrostatic calculations • Impact of the new cryostat interface has been checked and validated on the part out of liquid nitrogen: 9 E field calculation 9 Temperature distribution • No change on high voltage regarding LIPA project • Better thermal distribution than LIPA design (less losses with full current) Extract of thermal study Extract of Electrostatic study NEXANS termination • Part of the termination immersed in liquid nitrogen has been studied with the new configuration: 9 E field calculation (3D) AMSC Cryostat SIEMENS module • E field distribution less constraining than LIPA design 35 FCL termination design Overview LIPA based termination SIEMENS HTS switching module Termination part immersed in liquid nitrogen (new configuration) Electrical flexible connection (new component developed) 36 FCL termination design validation High voltage test preparation - Full scale assembly achieved in NEXANS Hanover testing laboratory: • All termination components assembled • New interface with cryostat simulated (more constraining E field distribution than real design to insure margin) • New electrical connection to module connected (more constraining E field distribution) Flexible connection simulated (connected to the termination bottom & inserted in testing cryostat) cryostat) 37 FCL termination design validation High voltage test results • AC withstand test successfully completed - 190kV / 30 minutes • Partial Discharge measurement successfully completed - Voltage increase up to 140 kV for few minutes - Decreasing to 114 kV and measurement - No PD measured (noise level < 3pC) • Lightning impulse test successfully completed - 650 kVp (10 shots in both polarity) • Switching impulse successfully completed - Success of the test (540 kVp 250/2500µs – both polarity) FCL termination high voltage design successfully validated 38 FCL termination design validation Electrical test – flexible connection to module - A full scale prototype of the flexible connection to module was also prepared, tested and validated with nominal current: • DC resistance measurement @ 77 K • AC resistance measurement @ 77 K • Temperature measurement all along this connection - This connection allows low thermal losses with nominal current (≈25 W) FCL termination design successfully tested at high voltage and current 39 SuperLimiterTM Outline • Program Objectives, Organization and Schedule • FY2008 Milestones • FY2008 Accomplishments and Results • FY2009 Planned Performance and Milestones • Summary 40 SuperLimiterTM FY2009 Planned Performance and Milestones Milestone Description Date Verification Method Phase 1a WS3 HVD4 Demonstrate switching module production capability meeting required specifications Results of power tests and BIL tests 10-Dec-08 documented to meet specifications. Fabrication and testing demonstrated. Summary report on Phase 1a 31-Dec-08 Report delivered to DOE Phase 1b WS4 Delivery of prototype switching modules for single phase test 1-Apr-09 WS5 Delivery of HTS wire for single phase test 28-May-09 Wire delivered to Siemens with appropriate certifications 23-Jul-09 HTS switching module shipped to AMSC for assembly into single phase FCL system. Records of coil tests complete and sent to partners. WS6 Delivery of HTS switching modules for single phase test Dummy switching module sent to HV test facility The 3 Phase program validates the system at 115kV in the SCE grid 41 SuperLimiterTM Outline • Program Objectives, Organization and Schedule • FY2008 Milestones • FY2008 Accomplishments and Results • FY2009 Planned Performance and Milestones • Summary 42 SuperLimiterTM Summary • Conservative/proven HV design • Adjustable current limiting without NRE (external reactor) • Substantial fault current reduction • Standard 2G insert coil tests demonstrate low ac losses • Bifilar coil technology already proven at medium voltage • Voltage and “trip factor” changed by +/- HTS coil modules • Siemens experience led to a wire based system for reliability • 138kV termination in use at LIPA and 1st article passed HV tests • Program on track for testing a single phase in Phase 1b The SuperLimiter Team experience has led to the selection of a robust modular design based on validated components 43