Collin County Regional Airport ALP Update and Narrative Report Preferred Airport Development Alternative SECTION 4 - PREFERRED AIRPORT DEVELOPMENT ALTERNATIVE 4.1 INTRODUCTION This section describes the Preferred Airport Development Alternative identified by the McKinney Airport Development Corporation during the ALP Update process. This development alternative includes the requirements identified in Section 3 following the airport demand / capacity analysis and the following requirements identified by the MADC in the kickoff workshop: General Aviation Terminal Facility Airport Access Improvements Interim Commercial Service Terminal Permanent Commercial Service Terminal Land Acquisition The Preferred Airport Development Alternative (PADA) is depicted graphically in Exhibit 4.1 4.2 AIRSIDE FACILITIES 4.2.1 PARALLEL RUNWAY AND TAXIWAY The airfield capacity analysis identifies the need for additional capacity-related improvements to be planned no later than PAL 2 (154,900 annual operations) and constructed by PAL 4 (230,000 annual operations). The requirements for the parallel runway include a 6,000’ length, 100’ width, and a runway centerline-to-centerline separation of 700’. The 6,000’ runway length accommodates all small aircraft (less than 12,500 pounds) and all large aircraft (less than 60,000 pounds) at 60% of their useful load that are projected to use the Airport8. The 100’ width meets the design standard for ADG III 9 and the 700’ separation meets the requirement for simultaneous VFR operations10. Based on AC 150/5060-5 (Airport Capacity and Delay Manual), there are seven airport characteristics fundamental to the demand/capacity analysis at Collin County Regional Airport. They are: Airfield Characteristics Runway Use Strategies Meteorological Conditions Aircraft Fleet Mix Touch-and-Go Operations Taxiway System Arrivals/Departures Ratio 8 Table 3.2 – Runway Length Analysis Airport’s Critical Aircraft is the Gulfstream G550, paragraph 3.2.3.1 10 Table 3.3 – Runway Dimensional Standards 9 4‐1 Scale: 1" = 1000' Exhibit 4.1 Preferred Airport Development Alternative Kimley-Horn and Associates, Inc. Collin County Regional Airport ALP Update Narrative Report Collin County Regional Airport ALP Update and Narrative Report Preferred Airport Development Alternative After considering the Items above, only two potential capacity improvements were possible at Collin County Regional Airport: optimized aircraft and taxi routing and an additional parallel runway. The current configuration of taxiways on the airfield provides maximum practical capacity for aircraft taxi movements. Therefore, reconfiguring or adding taxiways or changing aircraft taxi procedures will not increase airfield capacity to a level that will meet the forecast demand. Therefore, a parallel runway east of Runway 18-36 is the most practical alternative to provide the Airport with the additional capacity needed to meet the forecast demand. As indicated throughout this process, the timing of the development of any new facilities will depend on the growth of aviation activity that actually occurs at the Airport. The improvement is recommended for implementation based upon a forecast operations count associated with the identified Planning Activity Level (PAL), not a specific year. Actual aviation activity at the airport should be evaluated prior to the execution of the parallel runway project. The PADA features a parallel runway (to be designated 18L-36R) with an ultimate dimension of 7,002’ x 150’ that is located 700’ to the east of Runway 18-36 (to be re-designated 18R-36L). This ultimate parallel runway configuration will be achieved with a phased construction approach based on airport traffic demands. The initial phase of the parallel runway will be constructed at 6,002’ x 100’, meeting the standards for ADG III and the demands identified within the planning period. The initial parallel runway project will also include earthwork off the runway shoulders to the west and east that will accommodate a paved surface expansion to 150’ width in the future if needed to serve ADG IV aircraft. A requirement for this widening was not identified within this planning period. This additional earthwork would generate a nominal increase in the cost of the initial runway project, but once in place the additional paving to widen the runway could be completed at minimal cost and with minimal impact to airport operations. The future full-length parallel taxiway identified on the PADA provides aircraft access to the airfield from facilities on the east side of the Airport and is spaced 400’ to the east of the proposed parallel runway in accordance with design standards for ADG III and ADG IV aircraft, approach categories C and D. Similar to the proposed runway, the parallel taxiway requires a 50’ width but is shown on Exhibit 4.1 at an ultimate width of 75’ in order to accommodate future pavement expansion to ADG IV standards, if required. This expansion was not documented as a requirement within the planning period. The initial project will include pavement for a 50’ width and earthwork to accommodate a 75’ width in the future, should it become necessary. This additional earthwork would generate a nominal increase in the cost of the initial project, but once in place the additional paving to widen the taxiway could be completed at minimal cost and with minimal impact to airport operations. The proposed parallel runway and taxiway reflect a 1,000’ extension to the south to create a 7,000’ landing surface and associated taxiway pavement. A requirement for this extension was not documented within the planning period, but is reflected on the PADA in the event such an extension is required in the future. 4‐3 Collin County Regional Airport ALP Update and Narrative Report Preferred Airport Development Alternative 4.2.2 RUNWAY 18-36 EXTENSION The PADA includes a 1,500’ southerly extension of Runway 18-36 to an ultimate length of 8,500’. A requirement for this extension was not documented within the planning period, but it may be warranted in the future to accommodate heavier aircraft (greater than 60,000 pounds) operating at maximum stage length (greater than 2,000 miles). Additionally, this runway length is fully capable of accommodating most domestic passenger flights throughout the year, should commercial service operations begin at the Airport11 4.2.3 ACCESS IMPROVEMENTS The expansion of the airfield to the east with construction of a parallel runway and taxiway system, as discussed in Section 4.2.1, generates requirements for land acquisition as well as utilities, drainage, and access improvements. Land acquisition is discussed in Section 4.5. Specific utilities and drainage improvements to support airport development will be generated following the associated studies that are identified in the Capital Improvement Program (CIP) for separate funding and execution. The specific access improvements recommended are: Relocation of Enloe Road and southern connection to FM 546 Connection of Airport Drive / Country Lane to FM 546 The relocation of Enloe Road is recommended because the airfield expansion will cut access from Enloe Road to rural roads to the east and FM 546 to the south. The proposed Enloe Road relocation must be executed in conjunction with the parallel runway and taxiway project. The alignment shown is a modified version of the alignment recommended by KSA Engineers to the MADC in the “East Airport Drive / FM 2933 Connector Alignment Study,” which was published in 2010. The Enloe Road relocation is comprised of three sections. The first section, between Airport Drive and the relocated section, will require improvements to meet the standards of a two-lane rural section in order to be used as a connecting roadway between the west and east sides of the airport. Right-of-way should be reserved along this section in order to accommodate future expansion. The second section, from the existing Enloe Road and extending east, will consist of a two-lane, rural section with reserved right-of-way to accommodate expansion in the future. The third section, running north-south and connecting to FM 546, will continue the two-lane section with right-of-way reserved to accommodate ultimate expansion of the thoroughfare identified for this area in the City of McKinney’s Master Thoroughfare Plan12. In addition, increasing aircraft operations and expansion of airport facilities over the planning period will directly generate an increase in the amount of vehicular traffic occupying roadways around the Airport. Therefore, a second access improvement project, connection of Airport Drive to FM 546 in the Airport’s southwest quadrant, should be executed with the airfield expansion to provide a continuous, efficient roadway loop around the Airport. The City of McKinney’s Master Thoroughfare Plan identifies a 1.7 mile westerly extension of FM 546 to State Highway 5. This project adopts the portion of that extension between FM 546 and Airport Drive. Although the ultimate FM 546 extension is an urban major arterial, the project identified in this plan maintains the existing two-lane section of FM 546 and extends it to what is now Country Lane with adequate right-of-way to enable future widening in accordance with the thoroughfare plan. This access improvement also includes extending the current typical section of Airport Drive south to meet the FM 546 extension. 11 Collin County Regional Airport at McKinney “Airport Land Use Study”, pp 15 – 16, KSA Engineers / Coffman Associates, October 2009 12 City Ordinance No. 2010‐01‐001 4‐4 Collin County Regional Airport ALP Update and Narrative Report Preferred Airport Development Alternative 4.2.4 AIRCRAFT HANGAR SPACE The demand / capacity analysis identified various needs by hangar type throughout the planning period, as identified in Table 3.16. Exhibit 4.1 illustrates the proposed siting of hangar facilities. The facilities are generally grouped by hangar type, as follows: T- and Box Hangars – West of Taxiway B5 Community Hangars – West of Taxiway B2 Private Corporate Hangars – West of Taxiway B4 The hangar areas identified in the PADA will be made ready for hangar development with utilities, access, and other infrastructure (if not already in place) so that the Airport is prepared to accommodate hangar developers as demand dictates. 4.3 LANDSIDE FACILITIES 4.3.1 CENTRAL AIRPORT PARKING ADDITIONS The demand / capacity analysis identifies a requirement to construct 123 additional parking spaces in the central portion of the Airport between the Cutter Aviation FBO and Airport Administration offices, the air traffic control tower, and the McKinney Aerospace Hangar. The PADA identifies an infill area to accommodate this parking requirement, although some reconfiguration of existing parking spaces and driveways may be required in order to accommodate all needed spaces. Additional vehicular parking spaces are planned in conjunction with other facility requirements identified by this ALP Update based on facility size, type, and usage. 4.3.2 GENERAL AVIATION TERMINAL FACILITY AND PARKING APRON Inclusion of a second general aviation terminal facility on the PADA enables the McKinney Airport Development Corporation to retain existing and attract new aeronautical businesses and tenants by providing exceptional services and generating revenue that can be used to make the Airport financially self-sustaining. The general aviation terminal facility is sited immediately north of the existing GA parking apron and features a single-story facility of approximately 30,000 square feet, associated vehicular parking, and access to the site via an easterly extension of Elm Street. Approximately 15 acres of GA parking apron is located immediately adjacent to the facility, addressing the requirement for aircraft parking apron space identified in the demand / capacity analysis. The facility site including the building, vehicular parking, aircraft parking apron, and access drive is approximately 33 acres of total land area. The airport currently owns only the acreage immediately adjacent to Taxiway A. Approximately 29 acres of land acquisition is required to accommodate the facility. However, this acreage figure may vary depending on the current landowner’s willingness to subdivide and/or grant easements for access, utilities, etc. 4.4 COMMERCIAL PASSENGER SERVICE SUPPORT FACILITIES The PADA identifies facilities that could be engaged to capture an opportunity for commercial passenger service at Collin County Regional Airport. While no requirements for commercial passenger service operations were generated during the course of the demand / capacity analysis, the MADC recognizes the importance of being prepared with a plan in the event such an opportunity is provided. Therefore, the PADA identifies a means to provide facility support for commercial passenger service operations on an interim basis and in the long-term. 4‐5 Collin County Regional Airport ALP Update and Narrative Report Preferred Airport Development Alternative 4.4.1 INTERIM SOLUTION The interim solution for facility support for commercial service operations requires renovation of the McKinney Aerospace Hangar. The interior space may need to be reconfigured to support passenger functions such as ticketing, baggage, security screening, etc. The facility may also need additional vehicular parking to accommodate short- and long-term passengers. Consideration of TSA requirements regarding commercial service aircraft parking and passenger loading and unloading is also critical. Finally, the entire airport will need to be reviewed for compliance with FAR Part 139 requirements. The specific items to be addressed at the startup of commercial passenger service will be fully defined at the appropriate time by Federal authorities and the airline starting service. 4.4.2 LONG-TERM SOLUTION The proposed commercial service terminal facility is sited on the PADA on the east side of the Airport. Because no demand for long-term commercial passenger service was identified during the planning period, it is assumed that the parallel runway and taxiway will be in place before the commercial service terminal is designed and constructed. In the event commercial passenger service is a reality before the airfield expansion is executed, the parallel taxiway system and vehicular access improvements, including the Enloe Road relocation to the north and east and the FM 546 connection to the southwest, would need to be constructed in conjunction with the terminal to provide adequate passenger access to the terminal and aircraft access to Runway 18-36. 4.5 LAND ACQUISITION Land acquisition is required to support the future airport development requirements identified in the PADA. The land parcels that comprise the areas targeted for acquisition are identified on Exhibit 4.2 and tabulated in Appendix A. The property identified for acquisition on Exhibit 4.2 within the Ultimate Airport Property Line, shown in blue, is an approximation of the minimum area necessary to accommodate and secure the Airport improvements identified in the PADA. The property identified for acquisition beyond the Ultimate Airport Property Line on Exhibit 4.2 accommodates identified access improvements that should accompany future airport development. While Exhibit 4.2 and Appendix A provide a sound estimate, the acreage figures that ultimately must be acquired may vary depending on the current landowners’ willingness to subdivide and/or grant easements for access, utilities, etc. The City’s recent Planning Supplement to its Economic Development Plan, completed by Broaddus Planning in conjunction with TIP Strategies and published in January 2011, identifies the area surrounding Airport Road as an “Aviation Technology Corridor,” which has “a strong focus [on] aviation and technology-related uses.” This corridor is identified on the PADA, along with a similar corridor on the east side. Any acreage owned by the Airport along these “Aviation Compatible Development Corridors” could become a revenue source for the- Airport from development that may be compatible with, but not directly related to, the business of aviation and the Airport. Likewise, additional acreage owned by the Airport outside those corridors could be viable for use as ground lease space to accommodate on-airport development. The identified land acquisition also increases the City’s control over the development that occurs around the Airport, which could help mitigate encroachment issues. 4‐6 Scale: 1" = 1000' Exhibit 4.2 Preferred Airport Development Alternative Property Acquisition Areas Kimley-Horn and Associates, Inc. Collin County Regional Airport ALP Update Narrative Report Collin County Regional Airport ALP Update and Narrative Report Environmental Overview SECTION 5 - ENVIRONMENTAL OVERVIEW 5.1 INTRODUCTION The purpose of this section is to provide an overview of potential environmental impacts associated with the proposed improvements depicted on the Preferred Airport Development Alternative for Collin County Regional Airport at Exhibit 4.1. This environmental overview will provide federal, state, and local officials and the public with an understanding of the potential environmental impacts of the proposed airport development during the 20-year planning horizon. The overview presented in this chapter is modeled after the format of an Environmental Assessment (EA), described in FAA Order 1050.1E, “Environmental Impacts: Policies and Procedures”. Appendix A of Order 1050.1E lists 18 environmental impact categories that should be analyzed to determine impacts that may occur as a result of airport actions. These categories are as follows: Air Quality Coastal Resources Compatible Land Use Construction Impacts Department of Transportation Act: Section 4(f) Farmlands Fish, Wildlife, and Plants Floodplains Hazardous Materials, Pollution Prevention, and Solid Waste Historical, Architectural, Archeological, and Cultural Resources Light Emissions and Visual Impacts Natural Resources, Energy Supply, and Sustainable Design Noise Secondary (Induced) Impacts Socioeconomic Impacts, Environmental Justice, and Children’s Environmental Health and Safety Risks Water Quality Wetlands Wild and Scenic Rivers The information included in this section is not a formal Environmental Assessment (EA) or Environmental Impact Statement (EIS) as referred to in the National Environmental Policy Act of 1969 (NEPA) or the Airport and Airway Improvement Act (1982 as amended). However, this overview will point out those areas that may be potentially impacted by the proposed actions at Collin County Regional Airport and that may require further environmental study before project implementation. Several documents produced in conjunction with previous airport planning and development efforts were referenced in the development of this Section, including: Coffman Associates, Inc., Final Environmental Assessment for Proposed Airport Improvements to Meet FAA Design Standards for Runway/Taxiway Separation and Associated Improvements, June 2007. Environmental Science Associates, 14 CFR Part 150 Study, Noise Exposure Maps and Noise Compatibility Program for Collin County Regional Airport, September 2005. Wilbur Smith Associates, Inc., Airport Master Plan Update for Collin County Regional Airport, October 2004. 5‐1 Collin County Regional Airport 5.2 ALP Update and Narrative Report Environmental Overview ENVIRONMENTAL PROCESS Airport improvement projects that are considered to be Federal actions or receive Federal funding must be assessed from an environmental standpoint in order to comply with NEPA, the Airport and Airway Improvement Act (1982), and other pertinent laws. Further guidance is provided in FAA Order 1050.1E, “Environmental Impacts: Policies and Procedures”; Order 5050.4B, “National Environmental Policy Act Implementing Instructions for Airport Projects”; as well as the Council on Environmental Quality’s “Regulations for Implementing the Procedural Provisions of the National Environmental Policy Act”, found in 40 CFR 1500-1508. For any proposed airport action, the FAA performs an initial environmental determination that considers the type of action and its potential effect upon the environment. The result of the determination is the selection of one of the three following processes: An EIS is prepared for major Federal actions that are generally known to have the potential for significant environmental impacts. Actions that normally require an EIS include: initial Airport Layout Plan or airport location approval and Federal financial participation in or airport layout approval for a new runway capable of handling air carrier aircraft at a commercial service airport. An EIS involves thorough evaluation and documentation of the proposed action’s purpose and need, alternatives, affected environment, and environmental consequences. An EA is prepared to determine whether a proposed action or its alternatives has the potential to significantly affect the environment. An EA requires similar analysis and documentation as an EIS, but with less detail and coordination. If the EA indicates that the proposed action will not result in significant impacts, the FAA will prepare a Finding of No Significant Impact (FONSI), or otherwise require the preparation of an EIS. A Categorical Exclusion (CATEX) applies when a proposed action is included in one of the categories of categorical exclusions in paragraphs 307-312 of Order 1050.1E and no extraordinary circumstances apply. If extraordinary circumstances apply, the FAA may need to conduct consultation with relevant oversight agencies and may need to make appropriate findings and recommendations. When the FAA determines that an EA or EIS is required, FAA Order 5050.4B is used as a guide in the preparation of such studies. 5.3 EXAMINATION OF ENVIRONMENTAL IMPACT CATEGORIES The Preferred Airport Development Alternative at Exhibit 4.1 identifies a series of airfield and landside improvements at Collin County Regional Airport. This section provides a brief overview of the potential environmental impacts associated with these improvements. 5.3.1 AIR QUALITY According to the FAA Environmental Desk Reference for Airport Actions, detailed air quality analysis is needed for a project that due to its size, scope or location has the potential to affect the attainment and maintenance of established air quality standards. Collin County Regional Airport is located in an area designated as being in moderate non-attainment for 8-hour ozone relative to National Ambient Air Quality 5‐2 Collin County Regional Airport ALP Update and Narrative Report Environmental Overview Standards (NAAQS)13. In addition, according to the FAA’s Environmental Desk Reference for Airport Actions, an air quality analysis is required if the proposed improvements occur at an airport having more than 180,000 general aviation operations annually. Because Collin County Regional Airport is forecast to have more than 180,000 annual general aviation operations during the planning period, an air quality analysis will likely be required as part of environmental reviews conducted for projects implemented at the airport. Additionally, in accordance with Title 49 U.S.C. 47106 (c) (1) (B), as amended, certification must be obtained from the Governor of Texas stating that the airport improvements will be located, designed, constructed, and operated in accordance with applicable air quality standards14. 5.3.2 COASTAL RESOURCES The Collin County Regional Airport is located in North Texas, which is inland. Therefore, this resource is not considered or applicable. 5.3.3 COMPATIBLE LAND USE According to FAA Order 1050.1E, the compatibility of existing or future land uses in the vicinity of an airport is usually associated with noise impacts related to that airport. According to the City of McKinney’s “Future Land Use Plan,” existing land use within the airport boundary consists of “Government / Airport” land uses with surrounding properties designated as “Airport Industrial,” “Industrial,” various types of business and commercial uses, “Medium- and Low-Density Residential,” and “Floodplain.” There are also residential developments at the Towns of Fairview and Lowry Crossing that are near the Airport but beyond the limits of the City of McKinney. The proposed improvements appear to be compatible with the existing and future land use plans and future plans for surface transportation and access. The areas identified for future improvements are located within airport property boundaries or on parcels adjacent to the Airport that must be acquired. The land acquisitions identified in Exhibit 4.1 are all within “Airport Industrial” uses except for the small acquisitions on the north end of the field to secure Runway Protection Zones, which are within “Floodplain.” No noise analysis was performed in conjunction with this ALP Update. However, the City of McKinney performed a Part 150 Noise Study in September 2005 to evaluate noise generated by the Airport in its then-current configuration. Further noise analysis was performed in conjunction with the 2007 EA for airfield improvements. Based on limited review of these documents, it is reasonable to assume that a Noise Analysis will be required to accompany the environmental reviews conducted for projects implemented at the Airport. Other improvement actions beyond the planning period may also trigger noise analyses including the ultimate runway extensions and widening. Additionally, the change in air traffic mix that could result due to the start of commercial passenger service at the Airport could generate a requirement for further noise study. 13 14 Coffman Associates, p3‐5 Wilbur Smith, p7‐11 5‐3 Collin County Regional Airport ALP Update and Narrative Report Environmental Overview 5.3.4 CONSTRUCTION IMPACTS Construction impacts are commonly short-term and temporary in nature. Typical impacts resulting from an airport construction project include air, water, and noise pollution, as well as potential impacts resulting from generation and disposal of increased amounts of solid and/or hazardous waste. All on-site construction activities must be conducted in accordance with FAA AC 150/5370-10A, Standards for Specifying Construction of Airports, and incorporate best management practices into project plans. Construction must also comply with the requirements of the National Pollutant Discharge Elimination System (NPDES), including the filing of a Notice of Intent with the State of Texas prior to initiating construction that disturbs more than one acre. Implementing these measures will prevent or minimize most potential construction-related impacts to the environment and surrounding community. 5.3.5 DEPARTMENT OF TRANSPORTATION ACT, SECTION 4(F) Section 4(f) of the Department of Transportation Act provides that the Secretary of Transportation will not approve any program or project that requires the use of any publicly owned land from a public park, recreation area, or wildlife and waterfowl refuge of national, State, or local significance or land from an historic site of national, State or local significance as determined by the officials that have jurisdiction thereof, unless there is no feasible and prudent alternative to the use of such land and such program, and the project includes all possible planning to minimize harm resulting from the use. There do not appear to be any properties meeting these criteria within the airport property limits or within the land areas identified for acquisition on Exhibit 4.1. However, further study of this item may be warranted in conjunction with future environmental assessments, especially if air traffic patterns are altered by proposed airport development. 5.3.6 FARMLANDS Prime Farmland, as identified by the US Department of Agriculture, is land that has the best combination of physical and chemical characteristics for producing food, feed, fiber, forage, oilseed, and other agricultural crops with minimum inputs of fuel, fertilizer, pesticides, and labor, and without intolerable soil erosion. According to the Farmland Protection Policy Act (PL 90-542), lands already committed to urban development, such as the Airport, do not meet the definition of prime or unique farmlands. Some or all of the land surrounding the airport that is identified for acquisition may be designated as Prime Farmland based on a review of the Soil Survey of Collin County, Texas and coordination with the Natural Resource Conservation Service (NRCS). In compliance with the Farmland Protection Policy Act, the conversion of Prime Farmland to a nonagricultural use as a result of development at the Airport should be coordinated with the NRCS during the preparation of the Environmental Documentation prior to construction activities. Additionally, Form AD-1006, Farmland Conversion Impact Rating, should be completed to determine the extent of any farmland impacts15. 5.3.7 FISH, WILDLIFE, AND PLANTS No field investigations were made to determine the presence of sensitive biological resources or protected species or habitat in the proposed project area. Section 7 of the Endangered Species Act, as amended, requires coordination with Federal agencies to ensure that any action the agency authorizes, funds, or carries out is not likely to jeopardize the continued existence of threatened and endangered species or result in the destruction or adverse modification of critical habitat. Additionally, the Fish and Wildlife Coordination Act requires that Federal Agencies consult with State wildlife agencies and the U.S. 15 Wilbur Smith, pp7‐16 – 7‐17 5‐4 Collin County Regional Airport ALP Update and Narrative Report Environmental Overview Fish and Wildlife Service concerning the conservation of wildlife resources when a stream or other water body will be controlled or modified as a result of Federal Action. During the EA completed in June 2007, a field evaluation of the project area (including airport property and immediately adjacent lands) was conducted to identify sensitive biological resources and protected species. During this evaluation “It was determined that the project area consists of grassland with forested areas primarily confined to rivers, streams, and drainages. Dominant plant species include little bluestem and indiangrass, in addition to Bermuda grass and bahaigrass. Woody vegetation in the forested areas includes post oak, blackjack oak, water oak, winged elm, hackberry, and yaupon. All these habitat types are very common within the project area. During the field investigations, no sensitive biotic communities, federally threatened or endangered plant or animal species, or habitat for federally protected species was identified within the project study area16.” The EA found that implementation of the proposed airfield improvements at that time would not create a significant impact to federally listed threatened or endangered species.17 In addition to consideration of the above, the 289-Acre Heard Natural Science Museum and Wildlife Sanctuary is located approximately 2 miles southwest of the Airport along Wilson Creek18. Due to the additional land acquisition proposed in conjunction with the Preferred Airport Development Alternative, which appears to stretch beyond previously-studied areas, and the potential for changes in physical features and shifts in animal populations over time, further study of this item may be warranted in conjunction with future environmental analyses. 5.3.8 FLOODPLAINS The Collin County Regional Airport property is impacted by the 100-year floodplain of the East Fork of the Trinity River and its tributaries. Some of the development depicted on the Preferred Airport Development Alternative, particularly the airfield expansion and relocation of Enloe Road, appears to be located within the 100-year floodplain. This situation is not without precedent at the Airport. The Runway 18-36 replacement project, which is under construction as of the publication of this report, impacted the 100-year floodplain of the East Fork Trinity River and its tributaries. The proposed impacts were modeled and submitted to FEMA for approval. FEMA issued Conditional Letter of Map Revision (CLOMR) approving the construction of the impacts. A Letter of Map Revision (LOMR) will be issued by FEMA at the conclusion of the project based on the as-built conditions of the runway and accompanying drainage structures and stormwater attenuation and treatment facilities. The LOMR will revise the effective FEMA mapping in the area to reflect the impact of constructed improvements on the floodplain. Similar floodplain impacts due to improvements identified on the Preferred Airport Development Alternative will likely need to be addressed in further detail during the environmental review process. A Stormwater and Floodplain Management Master Plan is identified in the Capital Improvements Program as a strategy to effectively minimize and mitigate these floodplain and drainage impacts as the Preferred Airport Development Alternative is implemented over the planning period. 16 Coffman, p3‐6 Coffman, p4‐24 18 Wilbur Smith Associates, p7‐13 17 5‐5 Collin County Regional Airport 5.3.9 ALP Update and Narrative Report Environmental Overview HAZARDOUS MATERIALS, POLLUTION PREVENTION, AND SOLID WASTE 5.3.9.1 Hazardous Materials The Coffman Environmental Assessment (June 2007) noted that “Numerous Phase I Environmental Site Assessments have been undertaken at the airport prior to development projects and/or land acquisition. None of these studies have identified the presence of any hazardous materials; therefore, it is unlikely that earthwork will expose any hazardous materials (p4-27).” The Wilbur Smith Master Plan Update (October 2004) noted that a search of EPA databases identified no hazardous waste sites on airport property but did identify several sites in areas surrounding the Airport. Further analysis may be required in conjunction with environmental review of future development to determine if these circumstances have changed and if the presence of hazardous materials will impact future airport development. 5.3.9.2 Pollution Prevention The Coffman Environmental Assessment (June 2007) also notes that “the City of McKinney maintains a Texas Pollution Discharge Elimination System (TPDES) General Permit for operation of the airport as an industrial facility.” The implementation of development depicted on the Preferred Airport Development Alternative will likely generate a requirement to modify this permit to reflect additional impervious surface on airport property and associated impact mitigation measures. “A construction-related TPDES permit will be required prior to construction of the proposed improvements. This permit requires a Notice of Intent for all construction activities disturbing one acre or more of land. Construction-related water quality impacts are discussed under [Section 5.3.4], Construction, and [should] be minimized through the use of best management practices (BMPs).” 5.3.9.3 Solid Waste In general, the proposed facility development does not appear to produce a significant increase in solid waste generation beyond what the City of McKinney may normally anticipate in planning for future municipal growth. However, the particular solid waste impacts of the Preferred Airport Development Alternative were not evaluated in detail as part of this ALP Update and should be fully analyzed in conjunction with environmental review of future development. 5.3.10 HISTORICAL, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES This category of impact must be in compliance with Section 106 of the National Historic Preservation Act of 1966, as amended (16 USC 470, et seq.), which seeks to ensure the preservation of cultural resources. Research conducted during the Coffman Environmental Assessment (June 2007) revealed four previously recorded sites in the Texas Archaeological Research Laboratory within the Area of Potential Effect (APE) defined for the project. These sites were investigated further and it was determined “the four localities, by definition, are not eligible for inclusion in the [National Register of Historic Places] NHRP or [for designation as a State Archaeological Landmark].” (p3-7) Since the APE for the implementation of the Preferred Airport Development Alternative will likely expand beyond the boundaries of the APE identified in the Environmental Assessment, and because the status of some of the identified sites may have changed or new sites may be evident since 2007, a study of these resources should be included in the environmental review for these future projects. 5‐6 Collin County Regional Airport ALP Update and Narrative Report Environmental Overview 5.3.11 LIGHT EMISSIONS AND VISUAL IMPACTS As noted in the Wilbur Smith Master Plan Update (October 2004), “Light emissions associated with general aviation airports are typically minimal…FAA order 5050.4A [indicates] light emissions do not result in impacts to adjacent residential communities unless there are unusual circumstances, such as high intensity strobe lighting aimed directly at an individual’s house” (p7-17). Currently, the Airport is equipped with approach lighting and medium intensity runway lighting. Runway 18-36, upon completion, will feature high intensity runway lighting. Similar lighting systems can reasonably be expected to accompany future airfield expansion, which would not significantly alter lighting conditions. Although land uses of properties most likely to be impacted by light emissions are generally compatible with airport development, analysis of the light emissions that will accompany airport expansion should be evaluated in future environmental reviews. 5.3.12 NATURAL RESOURCES, ENERGY SUPPLY, AND SUSTAINABLE DESIGN Airport development actions have the potential to change energy requirements or use consumable natural resources. Typical actions that could cause such impacts include airside/landside expansion, land acquisition, significant changes in air traffic and airfield operations, and significant construction activity. The proposed improvements at Collin County Regional Airport may cause an increase in demand for energy during construction and the Airport may experience an increase in energy demand over the planning period due to the forecast growth in air traffic operations and based aircraft and the commissioning of new facilities. Potential impacts in this category may need to be reviewed in conjunction with future environmental analysis related to the projects included in the Preferred Airport Development Alternative. Notably, the City of McKinney has taken active steps to make sustainable design a priority in its community. Sustainable design standards should be considered when possible and practicable in the design of future airport facilities. 5.3.13 NOISE No noise analysis was performed in conjunction with this ALP Update. However, the City of McKinney initiated a Part 150 Noise Study in September 2005 to evaluate noise generated by the Airport in its thencurrent configuration. In addition, a noise analysis was conducted to evaluate airfield improvement alternatives in conjunction with the June 2007 Environmental Assessment by Coffman Associates. None of the near-term (PAL 1) airport improvement projects are anticipated to accompany or generate significant changes in aircraft type or operations that would alter or modify the findings of that analysis. It is reasonable to assume that a Noise Analysis will be required as part of the environmental review of proposed airfield improvement projects, including the parallel 6002’ x 100’ runway (with planning / design at PAL 2 and construction at PAL 4), depicted on the Preferred Airport Development Alternative. Other noise analyses may be required for other airfield expansion projects beyond PAL 4 including the depicted runway extensions and runway widening. Additionally, the change in air traffic mix that could result due to the start of commercial passenger service at the Airport could trigger a requirement for further noise study. 5.3.14 SECONDARY (INDUCED) IMPACTS Secondary (induced) socioeconomic impacts on communities surrounding airports include shifts in patterns of population movement and growth, public service demands, and changes in business and economic activity to the extent influenced by airport development. If land is acquired to expand the Airport eastward and roadway improvements are constructed as depicted in the Preferred Airport Development Alternative shown at Exhibit 4.1, some residences may be displaced and additional land could be made available and feasible for development of aviation-compatible businesses. Although the 5‐7 Collin County Regional Airport ALP Update and Narrative Report Environmental Overview overall economic impact of the Preferred Airport Development Alternative is anticipated to be positive with the generation of temporary construction-related jobs and an increase in the Airport’s permanent jobcreating capacity, its secondary (induced) impacts should be evaluated as part of a future environmental review. 5.3.15 SOCIOECONOMIC IMPACTS, ENVIRONMENTAL JUSTICE, AND CHILDREN’S ENVIRONMENTAL HEALTH AND SAFETY RISKS According to FAA Order 1050.1D, significant social impact thresholds include: Extensive relocation of residents is required, but sufficient replacement housing is unavailable. Extensive relocation of community businesses and that relocation would create economic hardship for the affected community. Disruptions of local traffic patterns that substantially reduce the levels of service of the roads serving the airport and its surrounding communities. A substantial loss in community tax base. The proposed improvements at Collin County Regional Airport may require relocation of a small number of residences due to land acquisition and airfield expansion on the east side of the Airport. At this preliminary stage in the process, significance of impact cannot be determined and further analysis should be conducted when the projects are within five to seven years of construction, based on demand. The proposed improvements must meet 49 CFR Part 24 (Implementing the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970) requirements if an airport action requires purchasing real property or displacing people or businesses. It is anticipated that the proposed improvements would not significantly alter traffic patterns in the surrounding community or cause a substantial loss in the community tax base. Executive Order 12898, “Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations”, provides that “each federal agency shall make achieving environmental justice part of its mission by identifying and addressing, as appropriate, disproportionately high and adverse human health or environmental effects of its programs, policies, and activities on minority populations and low-income populations”. The Council on Environmental Quality (CEQ) environmental justice guidance under NEPA was used to clearly define what a “disproportionately adverse effect to minority or lowincome populations” would be. It states that a minority population should be identified where either the minority population of the affected area exceeds 50% or when the minority population percentage of the affected area is meaningfully greater than the minority population percentage in the general population. This analysis was not conducted as a part of this ALP Update and should be conducted as relevant components of the Preferred Airport Development Program are initiated in order to confirm the minority and low-income population percentages of the affected area are not greater than the minority and lowincome population percentages in the general population, as defined by CEQ. 5‐8 Collin County Regional Airport ALP Update and Narrative Report Environmental Overview 5.3.16 WATER QUALITY As land is developed, surfaces are covered with non-porous materials such as concrete and asphalt. Without interception and depression storage, nearly all the rainfall on the impermeable surfaces (roofs, streets, driveways) becomes runoff, which dissolves or dislodges pollutants and discharges to creeks, rivers, lakes, drainage ditches and irrigation systems. The proposed improvements at Collin County Regional Airport will create new impervious surfaces that result increase stormwater runoff from the Airport. In addition, the proposed improvements as depicted in the Preferred Airport Development Alternative may impact streams and wetlands associated with the South Fork of the Trinity River and Wilson Creek. The airport improvement project that was the subject of the Coffman’s June 2007 Environmental Assessment impacted many of the same areas. According to the EA report, the following permits were required to be received or modified in conjunction with that project: U.S. Army Corps of Engineers (USACE) Section 404 permit; Texas commission on Environmental Quality (TCEQ) Section 401 Certification; TCEQ Texas Pollutant Discharge Elimination System (TPDES) General Permit 150000 for construction activities; and, TCEQ TPDES General Permit 050000 operational permit (p4-14). The USACE Section 404 permit, the requirement for which is generated by the Federal Water Pollution Control Act (commonly known as the Clean Water Act), regulates the discharge of dredged, excavated, or fill material in wetlands, streams, rivers, and other U.S. waters. The U.S. Army Corps of Engineers is the federal agency authorized to issue Section 404 Permits for certain activities conducted in wetlands or other U.S. waters. TCEQ is the state agency that also reviews USACE Section 404 permits for discharge into wetlands and Waters of the U.S. The projects associated with future airport development will be reviewed under these permitting processes to ensure impacts to wetlands and waters of the U.S. are minimized. The TPDES General Permit 15000 is issued after design and prior to construction to ensure TCEQ is notified before construction begins and that a proper Stormwater Pollution Prevention Plan (SWPPP) has been produced for the project. Finally, the Airport’s existing TPDES General Permit 050000 relates to stormwater discharges from the Airport as an industrial activity. This permit must be updated after improvements are constructed to illustrate additional impervious surfaces and new runoff patterns. It is reasonable to assume that, at a minimum, these permits will also be required in order to initiate the various projects that comprise the Preferred Airport Development Alternative over the planning period. A comprehensive review of water quality issues will be necessary as part of future environmental review(s) in order to demonstrate that water quality impacts have been minimized. 5.3.17 WETLANDS A wetlands inventory review was not completed as part of this ALP Update. However, it appears the majority of the Airport property consists of uplands with wetlands found on airport property in the vicinity of tributaries and drainage outfalls associated with the East Fork of the Trinity River and Wilson Creek. A field wetland survey should be conducted in conjunction with future environmental reviews to determine or confirm the presence or absence of waters of the U.S., including wetlands, within the area(s) of proposed development. As described in Section 5.3.16, a USACE Section 404 permit will likely be required for airport improvements in the vicinity of identified wetlands. 5‐9 Collin County Regional Airport ALP Update and Narrative Report Environmental Overview 5.3.18 WILD AND SCENIC RIVERS The Federal Wild and Scenic Rivers Act (PL 90-542 as amended) describes those areas eligible to be included in a system afforded protection under the Act as free flowing and processing “…outstandingly remarkable, scenic, recreational, geologic, fish and wildlife, historic, cultural or other similar values”. The Act restricts development within 1,000 feet of rivers identified as wild and scenic. Limited research of the National Wild and Scenic River System’s National Inventory of Wild and Scenic Rivers indicates that there are no designated “Wild and Scenic Rivers” within a 1,000-foot radius of the Collin County Regional Airport. 5‐10 Collin County Regional Airport ALP Update and Narrative Report Capital Improvements Program and Financial Overview SECTION 6 - CAPITAL IMPROVEMENTS PROGRAM AND FINANCIAL OVERVIEW 6.1 INTRODUCTION This section provides an overview of the Capital Improvements Program (CIP) generated by the Preferred Airport Development Alternative selected by the MADC and depicted at Exhibit 4.1. Additionally, it identifies potential funding sources the Airport may engage to make the identified CIP projects a reality. The overall approach to the development of the CIP and financial plan included the following elements: 6.2 Identify the individual projects that comprise the MADCs Preferred Airport Development Alternative Group individual projects according to Planning Activity Levels Develop conceptual site plans for each project Create a programmatic estimate for each project Review potential sources of public (grant) funding CAPITAL FUNDING SOURCES The projects identified in the Collin County Regional Airport’s CIP will likely be funded by several sources. These sources include federal grants, state grants, net operating revenues/cash reserves, and other unidentified funding sources, including private funding. Each of these sources of funds is described in the following sections. 6.2.1 TEXAS DEPARTMENT OF TRANSPORTATION (TXDOT) AVIATION DIVISION GRANTS Collin County Regional Airport is identified in the FAA’s National Plan of Integrated Airport Systems (NPIAS) and in the Texas Airport System Plan (TASP) as a Reliever Airport. As explained in the TASP, “TxDOT administers the FAA Airport Improvement Program for General Aviation Airports under the State Block Grant Program.” Funds administered by TxDOT are derived from the Federal Airport and Airway Trust Fund and state appropriations for the Aviation Facilities Development Plan. TxDOT Aviation Division administers funds to projects identified in its Aviation Capital Improvement Program (ACIP), a tentative three-year schedule of airport development projects. A project may be inserted into the ACIP with the airport sponsor’s submittal of a written Letter of Interest explaining the project requirement. The project generated by the Letter of Interest is then categorized by the objective it addresses. The Texas Transportation Commission, the approval authority for TxDOT’s ACIP, has assigned the following categorical priorities when evaluating an airport project for grant funding: Safety enhancement Preservation of existing facilities Response to a present need Provision for an anticipated need TxDOT Aviation has established several grant programs through which its grant funding may be distributed on an annual basis. The various grant programs are applied based upon the type of project requested by an airport sponsor. Following is a brief explanation of the various grant programs administered by TxDOT Aviation Division. 6‐1 Collin County Regional Airport ALP Update and Narrative Report Capital Improvements Program and Financial Overview 6.2.1.1 Capital Improvement Projects (CIP) Grant Program In general, projects funded under this grant program must be reflected in a current Airport Layout Plan on file with TxDOT Aviation Division. Projects approved for a CIP grant are funded on a 90% TxDOT / 10% local match, cost-sharing basis. 6.2.1.2 Routine Airport Maintenance Program (RAMP) This grant program is intended to provide airport sponsors with funding assistance for “lower cost” airport improvements and regular maintenance that may not be reflected in a current ALP document. Projects affecting an airfield are given priority to receive funding over landside projects. These funds may be distributed on a 50% TxDOT / 50% local match, cost-sharing basis up to $100,000 per fiscal year. TxDOT Aviation maintains a representative list of project types that are eligible and ineligible for RAMP funding. 6.2.1.3 Terminal Building Program TxDOT Aviation may distribute grant funds for eligible terminal building projects at TASP airports. The funds are administered as follows: 50% TxDOT / 50% local match, cost-share for building design and construction up to $1,000,000 50% TxDOT / 50% local match, cost-share for vehicle parking and entrance road up to $1,000,000 90% TxDOT / 10% local match, cost-share for aircraft parking apron in addition to the building grant amount There are a few requirements an airport must meet in order to be eligible for this grant program: The property on which the facility will be constructed must be considered airport property that is publicly-owned or leased by a public entity for at least 20 years. The airport must have an airport manager or designated person on site on a regular basis during normal daylight business hours. The airport must have aviation fuel available for sale to the flying public. 6.2.1.4 Hangar Program TxDOT Aviation may distribute grant funds to support hangar construction on a 90% TxDOT / 10% local match, cost sharing basis. TxDOT may contribute up to $600,000 on a single project if a NPIAS airport accumulates 4 years of Non-Primary Entitlement federal funds. Non-NPIAS airports are eligible for up to $600,000 in state funds for hangar projects. Additional funding for hangar access taxiway pavement can be had on a 90% TxDOT / 10% local match, cost-sharing basis. There are a few requirements an airport must meet in order to be eligible for this grant program: Airside needs must be met A justification exists for additional hangar space An approved ALP designating the hangar location An acceptable hangar lease and rate structure is in place Airport minimum standards have been adopted 6.2.1.5 Fuel Facility Development Program TxDOT Aviation may distribute grant funds to support fuel facility development on a 75% TxDOT / 25% local match, cost-sharing basis. Funding for NPIAS airports comes from Non-Primary Entitlement federal funds while Non-NPIAS airports receive state funding. Grants may be used for installation of new systems (i.e. above-ground storage tanks, dispensing systems, self-service card readers) owned and 6‐2 Collin County Regional Airport ALP Update and Narrative Report Capital Improvements Program and Financial Overview controlled by the airport sponsor. The use of grants for replacement systems will be evaluated and considered based on the systems’ expired service life. There are a few requirements an airport must meet in order to be eligible for this grant program: Airside needs must be met In-place standards for fuel rates and flowage fees An approved ALP designating fuel facility location Evidence of compliance with environmental regulations, which includes a Storm Water Pollution Prevention Plan and Spill Prevention Control and Countermeasure Plan. Note that development of these plans is eligible for RAMP grant funding. Airport minimum standards have been adopted 6.2.2 FEDERAL AVIATION ADMINISTRATION (FAA) DISCRETIONARY FUNDING In addition to the federal funds received through TxDOT Aviation’s administration of the State Block Grant program, Collin County Regional Airport has been successful in receiving discretionary funding from the FAA’s Southwest Regional Airports District Office via the TxDOT Aviation Division for projects on the Airport’s approved ALP. For example, federal discretionary funds were distributed to the Airport in support of the environmental assessment, engineering, land acquisition, and construction for the Runway 18-36 Replacement Project. It is possible that such discretionary funding could be received from the FAA for future CIP projects at the Airport. 6.2.3 OTHER CAPITAL FUNDING SOURCES In addition to the grant funding sources and the traditional local funding matches identified above, an airport may have the ability to engage other funding sources to design and construct projects on its CIP. These funding sources can be engaged on a case-by-case basis to supplement or, in lieu-of, traditional funding sources. These non-traditional funding sources can include: Airport Operating Revenues Municipal General Fund Revenues Bond Issues Private Funding Economic Development Organization Funding 6.2.3.1 Airport Operating Revenues / Cash Reserves Collin County Regional Airport, operating as an Enterprise Fund within the City of McKinney, generally operates at a loss year-to-year as its operating expenses exceed operating revenues. This requires the City to subsidize a portion of the Airport’s operating costs from the City’s general fund19. Recurring losses year-to-year do not enable the Airport to maintain a sizeable cash reserve. Therefore, the Airport typically does not have cash on-hand to fund its own Capital Improvement Projects. 6.2.3.2 Municipal General Fund Revenues In general, capital development expenditures from municipal general fund revenues have been somewhat difficult to obtain in recent years. One reason for this difficulty is the seemingly universal shortfall in local general fund revenues. Budgetary problems have created an environment where local funding is uncertain. The amount of general fund support for airport improvement projects varies by airport and is 19 Tax revenues generated by the airport routinely exceed the portion of the airport’s operating costs that must be subsidized from the City’s general fund. 6‐3 Collin County Regional Airport ALP Update and Narrative Report Capital Improvements Program and Financial Overview generally based upon the local tax base, priority of the development project, historical funding trends, and, of course, local attitudes concerning the importance of aviation. Historically, Collin County Regional Airport has enjoyed strong support from its municipal leadership. In addition to grant funding matches, the City of McKinney has demonstrated a willingness to provide larger shares of funding for specific airport development projects at the appropriate opportunity. 6.2.3.3 Bond Issues Airport authorities can issue bonds without approval from the city or county. However, they must use their own revenue to repay the bonds. Airport revenue is typically used to repay these bonds. The ability of Collin County Regional Airport to issue bonds is limited because of its tendency to operate at a loss yearto-year with subsidy from the City of McKinney. City bond issues for funding the local share of airport development projects must compete with bond issues for other types of community improvements such as schools, highways, and sewer systems. As with the general fund apportionment, bond issues supporting airport development depend greatly on the priority assigned to such projects by the local community. 6.2.3.4 Private Funding Items such as privately-operated storage and maintenance hangars are not typically eligible for federal or state grant funding at public airports. Collin County Regional Airport may work with private developers and other local businesses to fund these types of improvements in order to enhance the revenuegenerating capability of the airport from ground leases, fuel flowage, etc. 6.2.3.5 Economic Development Organization Funding The McKinney Economic Development Corporation (MEDC) is charged with fostering economic growth in the City of McKinney. The MEDC administers an annual budget generated from a half-cent City sales tax. These funds can be used to assist companies interested in basing in McKinney with infrastructure and other incentives. When prudent, these funds may be used to provide airport improvements associated with a specific project related to economic growth. 6.3 CAPITAL IMPROVEMENTS PROGRAM Appendix B contains conceptual site plans that depict the development identified in the Preferred Airport Development Alternative in greater detail. These conceptual site plans group the recommended development into functional areas as follows: Exhibit 1 – Airfield Expansion Exhibit 2 – General Aviation Terminal Facility Exhibit 3 – Central Terminal Area Exhibit 4 – Hangar Campus Development Exhibit 5 – FM 546 / Airport Drive Improvements Exhibit 6 – Commercial Passenger Service Terminal Exhibit 7 – Enloe Road Improvements Exhibit 8 – East Airport Drive Improvements This section and the tables found at Appendix C provide a summary of the Capital Improvements Program (CIP) that are necessary to implement the Preferred Airport Development Alternative. The CIP has three primary purposes: 6‐4 Collin County Regional Airport ALP Update and Narrative Report Capital Improvements Program and Financial Overview Identify improvement projects that will be required at an airport over a specific period of time; Estimate the order of implementation of the projects included in the plan; and Estimate the total costs of the projects. It is important to note that the CIP becomes less detailed and more flexible in the future years of the planning period. Additionally, the CIP is typically modified on an annual basis and as new projects are identified and completed, requirements change, and financial environments evolve. Within Appendix C, Table 1 lists each project identified in the CIP grouped according to the functional area of the project. With few exceptions, the “Project Name” and “Item Number” correspond to a graphical depiction of the project found on the exhibits within Appendix B. Appendix D contains a number of project worksheets that provide a breakdown of the programmatic estimates listed on Table 1. Each proposed capital improvement project over the 20-year planning horizon has been assigned to one of four specific planning milestones or Planning Activity Levels (PALs). The purpose of the PALs is to guide Airport staff and officials in determining when airport facilities need expansion or upgrades based on recorded aviation activity (i.e. based aircraft and annual operations), and not an arbitrary calendar year. The projects in the CIP are grouped according to the following PALs: PAL 1: PAL 2: PAL 3: PAL 4: 117,600 annual operations (forecast to occur in 2016) 154,000 annual operations (forecast to occur in 2021) 200,300 annual operations (forecast to occur in 2026) 230,000 annual operations (forecast to occur in 2031) Table 2 graphically depicts the PAL at which each project in the CIP, grouped by functional area, should be initiated for preparatory work (such as environmental review, engineering, and design) and, ultimately, construction. Projects identified for construction in PAL 1 must also have the required preparatory work accomplished during PAL 1. Table 3 provides the same information, but in a format that illustrates the CIP projects’ sequential execution throughout the planning period. Finally, Table 4 provides a comprehensive summary of the CIP, tabulating the total programmatic estimates for all projects by PAL and by functional area. In addition to PALs described above, the Airport identified projects for inclusion in the CIP that are not generated by forecast aviation activity during the planning period. The MADC considers these projects to be in the best interest of its mission to “Develop the premier general aviation reliever airport in the D/FW Metroplex with future commercial service goals20.” The programmatic estimates for these projects are tabulated under the column “Beyond PAL 4” since they were not identified as requirements during the planning period due to future projections of airport demand. As such, funding for these projects would likely come from sources other than TxDOT Aviation or the FAA until the projects can be justified based on aviation demand. Total programmatic estimates for the CIP, tabulated by functional area and PAL are provided at Tables 6.1 and 6.2, below.21 20 MADC Strategic Plan, 2010 The MADC requested guidance on the implementation of CIP projects assigned to PAL 1 before adopting this ALP Update. The implementation order for those projects, which was included in the Board’s vote to recommend the City Council’s adoption of the ALP Update, has been included for reference in Appendix C as “Table 5 – MADC Implementation Priorities.” 21 6‐5 Collin County Regional Airport ALP Update and Narrative Report Capital Improvements Program and Financial Overview Table6.1– ProgrammaticEstimates,byAirportFunctionalArea Functional Area Programmatic Estimate Description Area 1 Area 2 Area 3 Area 4 Area 5 Area 6 Area 7 Area 8 Airfield Expansion General Aviation Terminal Facility Central Terminal Area South Hangar Campus Development FM 546 / Airport Drive Improvements Commercial Passenger Service Terminal Enloe Road Improvements East Airport Drive Improvements Property Acquisition and Master Plans Total Capital Improvement Program 1) See Appendix C, Table 1 $128,560,000 $22,768,000 $16,925,000 $19,304,000 $1,559,000 $43,068,000 $3,458,000 $2,710,000 $65,195,000 $303,547,000 Table6.2– ProgrammaticEstimates,byPlanningActivityLevel PAL Anticipated Time Period PAL 1 2012 – 2016 PAL 2 2017 – 2021 PAL 3 2022 – 2026 PAL 4 2027 – 2031 Beyond PAL 4 Beyond 2031 Total Capital Improvement Program 1) See Appendix C, Table 4 Programmatic Estimate $41,703,000 $61,297,000 $23,950,000 $94,495,000 $82,102,000 $303,547,000 6‐6 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX A ‐ PROPERTY ACQUISITION SUMMARY Area # Owner GENERAL AVIATION TERMINAL FACILITY 1 VTCR LP & MADMT LP & Prairie Flight LP 2 VTCR LP & MADMT LP & Prairie Flight LP 3 VTCR LP & MADMT LP & Prairie Flight LP 4 VTCR LP & MADMT LP & Prairie Flight LP 6 VTCR LP & MADMT LP & Prairie Flight LP Subtotal CENTRAL TERMINAL AREA 7 VTCR LP & MADMT LP & Prairie Flight LP 8 VTCR LP & MADMT LP & Prairie Flight LP 9 VTCR LP & MADMT LP & Prairie Flight LP Subtotal AIRFIELD EXPANSION / EAST AIRPORT DEVELOPMENT 10 Edmonds Lavonne Testamentary Trust 11 McKinney Uplands LP 12 VTCR LP & MADMT LP & Prairie Flight LP 13 VTCR LP & MADMT LP & Prairie Flight LP 14 Griffin Wiley E Trust 15 VTCR LP ETAL 16 Griffin Wiley E Trust 17 VTCR LP & MADMT LP & Prairie Flight LP 18 VTCR LP ETAL 19 McKinney Uplands LP Subtotal NORTH RUNWAY PROTECTION ZONE ACQUISITIONS 20 McKinney Uplands LP 21 Map Holdings LP 22 McKinney East Fork LLC Subtotal Acreage Area Total Req'd Parcel CCAD ID# Estimated Cost Notes 0.2 2.6 3.4 3.6 19.1 28.9 10.7 118.2 3.4 3.6 25.3 161.2 R‐7000‐000‐0180‐1 R‐6884‐000‐0290‐1 R‐6747‐000‐0640‐1 R‐6874‐000‐0220‐1 R‐6874‐000‐0040‐1 $ 52,272 $ 679,536 $ 888,624 $ 940,896 $ 4,991,976 Note Parcel 5 , previously identified by MADC for acquisition, is not identified in this plan. $ 7,553,304 14.0 10.3 32.3 10.3 R‐6747‐000‐0620‐1 R‐6874‐000‐0090‐1 $ 3,659,040 $ 2,692,008 3.5 3.5 R‐6691‐001‐0010‐1 $ 914,760 27.8 46.1 39.1 44.4 17.9 20.0 26.0 89.7 10.1 9.2 6.0 37.4 299.8 39.1 99.6 17.9 20.0 50.0 137.0 41.1 9.2 6.0 46.2 466.1 R‐6517‐001‐1170‐1 R‐6517‐001‐2360‐1 R‐6874‐000‐0010‐1 R‐6517‐001‐1180‐1 R‐6517‐001‐1200‐1 R‐6517‐001‐1210‐1 R‐6517‐001‐1220‐1 R‐6691‐001‐0030‐1 R‐6691‐001‐0040‐1 R‐6375‐000‐0180‐1 $ 4,257,990 CCAD Property Details indicate total parcel area of 39.1 acres. $ 4,835,160 $ 1,949,310 $ 2,178,000 $ 2,831,400 $ 9,768,330 $ 1,099,890 $ 1,001,880 MADC originally estimated 9.3 acres; CAD linework shows 9.2 acres. $ 653,400 $ 4,072,860 $ 32,648,220 1.7 1.9 2.5 6.1 4.0 202.8 2.5 209.3 R‐6375‐000‐0190‐1 R‐6375‐000‐0050‐1 R‐6884‐000‐0160‐1 $ 185,130 $ 206,910 $ 272,250 $ 664,290 CCAD Property Details indicate total parcel area of 5.8 acres. 3.5 Acre area based on CAD linework. $ 7,265,808 MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX A ‐ PROPERTY ACQUISITION SUMMARY Area # Owner SOUTH RUNWAY PROTECTION ZONE ACQUISITIONS 23 Fairview City of 24 McKinney 114 Land & Cattle LTD 25 Rutledge Mabel Lois ETAL 26 Powell John Warren Sr 27 Powell John Warren Sr 28 Becerra Jose A 29 Fairview City of Acreage Area Total Req'd Parcel 1.0 58.4 20.8 1.0 36.0 1.7 7.6 1.0 111.8 39.0 1.0 74.1 1.7 82.3 30A&B Fairview Town of 0.4 0.4 31 32 Pecan F.O.R.K. LLC Rutledge Hulan‐LE 27.2 0.3 154.4 517.0 52.6 1.0 364.9 1247.6 Subtotal GRAND TOTAL, PROPERTY ACQUISITION CCAD ID# R‐6517‐003‐2920‐1 R‐6517‐003‐1240‐1 R‐6517‐003‐2060‐1 R‐6691‐001‐0150‐1 R‐6691‐001‐0120‐1 R‐6691‐001‐0130‐1 R‐6691‐001‐0440‐1 R‐6691‐001‐012R‐1 R‐6691‐001‐015R‐1 R‐6517‐003‐2080‐1 R‐6517‐003‐2710‐1 Estimated Cost Notes $ 108,900 $ 6,359,760 $ 2,265,120 $ 108,900 MADC originally estimated 1.1 acres. 1 acre area based on CAD linework. $ 3,920,400 $ 185,130 $ 827,640 $ 43,560 $ 2,962,080 $ 32,670 $ 16,814,160 $ 64,945,782 Sources: Collin County GIS Interactive Maps (Owner, Total Acreage, CCAD ID #), Accessed 12/2011, http://maps.collincountytx.gov/main.html Property cost information and programmatic cost per square foot estimate provided by MADC. Notes: West side parcels estimated at $6.00 per square foot. East, north, and south side parcels estimated at $2.50 per square foot Only property area identified in "Area Required" column has been priced. Actual acreage and acquisition cost may be higher, depending on ability to subdivide. MARCH 2012 PLOTTED BY DWG NAME LAST SAVED IMAGES XREFS JCM PAC FEBRUARY 2012 064445400 Checked by: Date: Project No. PAC Drawn by: KEY MAP 1000' AS NOTED EXHIBIT 5 - FM 546 / AIRPORT DRIVE IMPROVEMENTS 0 Designed by: EXHIBIT 4 - HANGAR CAMPUS DEVELOPMENT Scale: BONDY, SCOTT 2/21/2012 11:43 AM K:\LAC_AVIATION\064445400_CCRA ALP UPDATE\CADD\EXHIBIT\FINAL DELIVERABLE EXHIBITS\EX - OVERALL.DWG 1/23/2012 8:50 AM CCRA Logo XREF xSite - XREF x1117 - XREF xDash - XREF xHatchEX4-1 - XREF xTopo - XREF xGrad - XREF xSiteExst - XREF xSite01 - XREF xBndy IMPROVEMENTS LEGEND EXHIBIT 1 - AIRFIELD EXPANSION EXHIBIT 2 - GENERAL AVIATION TERMINAL FACILITY EXHIBIT 3 - CENTRAL TERMINAL AREA 2000' GRAPHIC SCALE 1000' EXHIBIT 6 - COMMERCIAL PASSENGER SERVICE TERMINAL EXHIBIT 7 - ENLOE ROAD IMPROVEMENTS EXHIBIT 8 - EAST AIRPORT DRIVE IMPROVEMENTS SHEET EX-0 PLOTTED BY DWG NAME LAST SAVED IMAGES XREFS JCM PAC FEBRUARY 2012 064445400 Checked by: Date: Project No. PAC Drawn by: AIRFIELD EXPANSION 600' AS NOTED 0 Designed by: 1.03 - PARALLEL RUNWAY 18L - 36R AND TAXIWAY EXTENSION (1,000' x 150') Scale: BONDY, SCOTT 2/21/2012 11:45 AM K:\LAC_AVIATION\064445400_CCRA ALP UPDATE\CADD\EXHIBIT\FINAL DELIVERABLE EXHIBITS\EX - AREA1.DWG 2/21/2012 11:39 AM CCRA Logo XREF xSite - XREF x1117 - XREF xDash - XREF xHatchEX4-1 - XREF xTopo - XREF xSite01 - XREF xSiteExst - XREF xBndy IMPROVEMENTS LEGEND 1.01 - PARALLEL RUNWAY 18L - 36R (6002' x 100') AND TAXIWAY (50') 1.02 - PARALLEL RUNWAY 18L - 36R (6002' x 150') AND TAXIWAY (75') WIDENING 1.04 - RUNWAY 18R - 36L EXTENSION (1,500' x 150') 1200' GRAPHIC SCALE 600' SHEET EX-1 PLOTTED BY DWG NAME LAST SAVED IMAGES XREFS JCM PAC FEBRUARY 2012 064445400 Checked by: Date: Project No. PAC Drawn by: GA TERMINAL FACILITY 300' AS NOTED 2.03 - GENERAL AVIATION TERMINAL FACILITY ENTRANCE ROAD 0 Designed by: 2.02b - AIRCRAFT PARKING APRON, PHASE 3 (4 AC) Scale: BONDY, SCOTT 2/21/2012 11:46 AM K:\LAC_AVIATION\064445400_CCRA ALP UPDATE\CADD\EXHIBIT\FINAL DELIVERABLE EXHIBITS\EX - AREA2.DWG 1/23/2012 8:53 AM CCRA Logo XREF xSite - XREF x1117 - XREF xDash - XREF xTopo - XREF xSiteExst - XREF xSite01 - XREF xBndy IMPROVEMENTS LEGEND 2.01 - GENERAL AVIATION TERMINAL FACILITY INCLUDING LANDSIDE PARKING, BUILDING, AND PHASE 1 (7 AC) OF AIRCRAFT PARKING APRON 2.02a - AIRCRAFT PARKING APRON, PHASE 2 (4 AC) 600' GRAPHIC SCALE 300' SHEET EX-2 IMPROVEMENTS LEGEND 3.01a - COMMUNITY HANGAR DEVELOPMENT SITES (typ) 3.01b - AERONAUTICAL BUSINESS CAMPUS 3.02a - PRIVATE CORPORATE HANGAR DEVELOPMENT SITES (typ) 3.02b - PRIVATE CORPORATE HANGAR RAMP 3.02c - PRIVATE CORPORATE HANGAR EAST ACCESS AND PARKING 0 250' 500' GRAPHIC SCALE 250' 3.02d - PRIVATE CORPORATE HANGAR WEST ACCESS AND PARKING 3.03 - PUBLIC PARKING INFILL AND REHABILITATE AIRPORT ENTRANCE 3.04 - CENTRAL AIRCRAFT PARKING APRON INFILL IMAGES XREFS PLOTTED BY DWG NAME LAST SAVED PAC FEBRUARY 2012 064445400 Date: Project No. CENTRAL TERMINAL AREA JCM Checked by: PAC Designed by: Drawn by: AS NOTED Scale: CCRA Logo XREF xSite - XREF x1117 - XREF xDash - XREF xGrad - XREF xSiteExst - XREF xTower - XREF xSite01 - XREF xTopo - XREF xBndy BONDY, SCOTT 2/21/2012 11:48 AM K:\LAC_AVIATION\064445400_CCRA ALP UPDATE\CADD\EXHIBIT\FINAL DELIVERABLE EXHIBITS\EX - AREA3.DWG 1/16/2012 4:35 PM 3.05 - REHABILITATE CENTRAL AIRCRAFT PARKING APRON SHEET EX-3 PLOTTED BY DWG NAME LAST SAVED IMAGES XREFS JCM PAC FEBRUARY 2012 064445400 Checked by: Date: Project No. PAC Drawn by: HANGAR CAMPUS DEVELOPEMENT 200' AS NOTED 4.02c - T-AND BOX HANGAR CAMPUS, PHASE 3 0 Designed by: 4.02b - T-AND BOX HANGAR CAMPUS, PHASE 2 Scale: BONDY, SCOTT 2/21/2012 11:49 AM K:\LAC_AVIATION\064445400_CCRA ALP UPDATE\CADD\EXHIBIT\FINAL DELIVERABLE EXHIBITS\EX - AREA4.DWG 1/16/2012 4:38 PM CCRA Logo XREF xSite - XREF x1117 - XREF xDash - XREF xTopo - XREF xGrad - XREF xSiteExst - XREF xSite01 IMPROVEMENTS LEGEND 4.01a - PRIVATE CORPORATE HANGAR DEVELOPMENT SITES (typ) 4.01b - PRIVATE CORPORATE HANGAR RAMP (SOUTH) & VEHICULAR PARKING 4.02a - T-AND BOX HANGAR CAMPUS, PHASE 1 400' 4.03 - MAINTENANCE EQUIPMENT STORAGE BUILDING GRAPHIC SCALE 200' SHEET EX-4 PLOTTED BY DWG NAME LAST SAVED IMAGES XREFS JCM PAC FEBRUARY 2012 064445400 Checked by: Date: Project No. PAC Drawn by: AS NOTED FM 546 / AIRPORT DRIVE IMPROVEMENTS 200' Designed by: 0 Scale: BONDY, SCOTT 2/21/2012 11:49 AM K:\LAC_AVIATION\064445400_CCRA ALP UPDATE\CADD\EXHIBIT\FINAL DELIVERABLE EXHIBITS\EX - AREA5.DWG 1/16/2012 4:41 PM CCRA Logo XREF xSite - XREF x1117 - XREF xDash - XREF xSiteExst - XREF xSite01 - XREF xBndy IMPROVEMENTS LEGEND 5.01 - FM 546 (APPROX. 1,150 LF) 5.02 - AIRPORT DR (APPROX. 775 LF) 400' GRAPHIC SCALE 200' SHEET EX-5 PLOTTED BY DWG NAME LAST SAVED IMAGES XREFS JCM PAC FEBRUARY 2012 064445400 Checked by: Date: Project No. PAC Drawn by: AS NOTED Designed by: COMMERCIAL PASSENGER SERVICE TERMINAL 250' Scale: BONDY, SCOTT 2/21/2012 11:50 AM K:\LAC_AVIATION\064445400_CCRA ALP UPDATE\CADD\EXHIBIT\FINAL DELIVERABLE EXHIBITS\EX - AREA6.DWG 1/16/2012 4:44 PM CCRA Logo XREF x1117 - XREF xDash - XREF xHatchEX4-1 - XREF xTopo - XREF xSiteExst - XREF xSite01 - XREF xBndy 0 500' GRAPHIC SCALE 250' SHEET EX-6 PLOTTED BY DWG NAME LAST SAVED IMAGES XREFS JCM PAC FEBRUARY 2012 064445400 Checked by: Date: Project No. PAC Drawn by: ENLOE ROAD IMPROVEMENTS 500' AS NOTED 0 Designed by: 7.02 - ACCESS IMPROVEMENTS, RELOCATE ENLOE ROAD (APPROX. 4,350 LF) Scale: BONDY, SCOTT 2/21/2012 11:51 AM K:\LAC_AVIATION\064445400_CCRA ALP UPDATE\CADD\EXHIBIT\FINAL DELIVERABLE EXHIBITS\EX - AREA7.DWG 1/16/2012 4:51 PM CCRA Logo XREF xSite - XREF x1117 - XREF xDash - XREF xHatchEX4-1 - XREF xSiteExst - XREF xSite01 - XREF xTopo - XREF xBndy IMPROVEMENTS LEGEND 7.01 - ACCESS IMPROVEMENTS, REHABILITATE ENLOE ROAD (APPROX. 2,500 LF) 1000' GRAPHIC SCALE 500' SHEET EX-7 PLOTTED BY DWG NAME LAST SAVED IMAGES XREFS JCM PAC FEBRUARY 2012 064445400 Checked by: Date: Project No. PAC Drawn by: AS NOTED Designed by: ACCESS IMPROVEMENTS EAST AIRPORT DRIVE 250' Scale: BONDY, SCOTT 2/21/2012 11:51 AM K:\LAC_AVIATION\064445400_CCRA ALP UPDATE\CADD\EXHIBIT\FINAL DELIVERABLE EXHIBITS\EX - AREA8.DWG 1/16/2012 4:54 PM CCRA Logo XREF xSite - XREF x1117 - XREF xDash - XREF xSiteExst - XREF xSite01 - XREF xTopo - XREF xBndy 0 500' GRAPHIC SCALE 250' SHEET EX-8 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 1 ‐ PROJECT COST SUMMARY Item No. Project Name AIRFIELD EXPANSION Parallel Runway 18L‐36R and Taxiway 1.01 Parallel Runway 18L‐36R and Taxiway Widening Runway 18L‐36R and Taxiway Extension Runway 18R‐36L and Taxiway Extension North / East Access Perimeter Road3 SUBTOTAL GA TERMINAL FACILITY GA Terminal Facility ‐ Phase 1 4 2.01 2.02a GA Terminal Facility ‐ Phase 2 2.02b GA Terminal Facility ‐ Phase 3 GA Terminal Facility Entrance Road 2.03 Northwestern Drainage Improvements 5 2.04 SUBTOTAL CENTRAL TERMINAL AREA 6 3.01a Community Hangar Development 6 3.01b Aeronautical Business Campus 6 3.02a Private Corporate Hangar Development 3.02b Private Corporate Hangar Ramp 1.02 1.03 1.04 1.05 3.02c Private Corporate Hangar East Access & Parking Project Preparation Construction Total1,2 $ 8,135,000 $ 81,345,000 $ 89,480,000 $ 784,000 $ 1,028,000 $ 1,313,000 $ 750,000 $ 12,010,000 $ 7,842,000 $ 10,281,000 $ 13,132,000 $ 3,950,000 $ 116,550,000 $ 8,626,000 $ 11,309,000 $ 14,445,000 $ 4,700,000 $ 128,560,000 $ 1,201,800 $ ‐ $ ‐ $ 132,000 $ 430,000 $ 1,763,800 $ 10,816,200 $ 2,565,000 $ 2,565,000 $ 1,188,000 $ 3,870,000 $ 21,004,200 $ 12,018,000 $ 2,565,000 $ 2,565,000 $ 1,320,000 $ 4,300,000 $ 22,768,000 $ ‐ $ 374,000 $ ‐ $ 319,000 $ ‐ $ 1,496,000 $ ‐ $ 3,187,000 $ ‐ $ 1,870,000 $ ‐ $ 3,506,000 $ 403,000 $ 1,610,000 $ 2,013,000 Private Corporate Hangar West Access & Parking Public Parking Infill and Rehabilitate Airport Entrance 3.03 Central Aircraft Parking Apron Infill 3.04 Rehabilitate Central Aircraft Parking Apron7 3.05 SUBTOTAL HANGAR CAMPUS DEVELOPMENT $ 138,000 $ 1,384,000 $ 1,522,000 $ 264,000 $ 228,000 $ ‐ $ 1,726,000 $ 2,643,000 $ 913,000 $ ‐ $ 11,233,000 $ 2,907,000 $ 1,141,000 $ 3,966,000 $ 16,925,000 Private Corporate Hangar Development (South)6 Private Corporate Hangar Ramp (South) and 4.01b Vehicular Parking 6 4.02a T‐ and Box Hangar Campus ‐ Phase 1 6 4.02b T‐ and Box Hangar Campus ‐ Phase 2 6 4.02c T‐ and Box Hangar Campus ‐ Phase 3 Maintenance Equipment Storage Building7 4.03 SUBTOTAL FM 546 / AIRPORT DRIVE IMPROVEMENTS FM 546 Extension 5.01 Airport Drive Improvements 5.02 SUBTOTAL $ ‐ $ ‐ $ ‐ $ 319,000 $ 732,000 $ 325,000 $ 352,000 $ ‐ $ 1,728,000 $ 3,194,000 $ 7,319,000 $ 3,248,000 $ 3,515,000 $ ‐ $ 17,276,000 $ 3,513,000 $ 8,051,000 $ 3,573,000 $ 3,867,000 $ 300,000 $ 19,304,000 3.02d 4.01a $ 177,000 $ 708,000 $ 885,000 $ 135,000 $ 539,000 $ 674,000 $ 312,000 $ 1,247,000 $ 1,559,000 MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 1 ‐ PROJECT COST SUMMARY Item No. Project Name COMMERCIAL PASSENGER SERVICE TERMINAL Commercial Passenger Terminal Complex 6.01 SUBTOTAL ENLOE ROAD IMPROVEMENTS Rehabilitate Enloe Road 7.01 Relocate Enloe Road 7.02 SUBTOTAL EAST AIRPORT DRIVE IMPROVEMENTS East Airport Drive 8.01 SUBTOTAL PROPERTY ACQUISITION AND MASTER PLANS Property Acquisition ‐ General Aviation Terminal 8 9.01a Facility 8 9.01b Property Acquisition ‐ Central Terminal Area Property Acquisition ‐ Airfield Expansion / East 8 9.01c Airport Development Property Acquisition ‐ North Runway Protection 8 9.01d Zone Property Acquisition ‐ South Runway Protection 8 9.01e Zone Stormwater / Floodplain Mgt Master Plan 9.02 Airport Master Utility Plan 9.03 SUBTOTAL TOTAL CAPITAL IMPROVEMENT PROGRAM Project Preparation Construction Total1,2 $ 5,618,000 $ 37,450,000 $ 43,068,000 $ 5,618,000 $ 37,450,000 $ 43,068,000 $ 151,000 $ 1,007,000 $ 1,158,000 $ 300,000 $ 2,000,000 $ 2,300,000 $ 451,000 $ 3,007,000 $ 3,458,000 $ 246,000 $ 2,464,000 $ 2,710,000 $ 246,000 $ 2,464,000 $ 2,710,000 $ ‐ $ ‐ $ ‐ $ ‐ $ 7,553,000 $ 7,266,000 $ ‐ $ ‐ $ 32,648,000 $ ‐ $ ‐ $ 664,000 $ ‐ $ 150,000 $ 100,000 $ 250,000 $ 24,104,800 $ ‐ $ ‐ $ ‐ $ ‐ $ 210,231,200 $ 16,814,000 $ 150,000 $ 100,000 $ 65,195,000 $ 303,547,000 Notes: 1. All figures in 2012 dollars. 2. Additional capital improvement projects may be generated for implementation within the planning period following the master plan items identified in Items 9.02 and 9.03. 3. Programmatic estimate adopted from 2004 Master Plan Update by Wilbur Smith Associates, Inc. 4. Includes Engineering / Design of entire apron area depicted with appropriate construction phasing identified. 5. Programmatic amount as provided by MADC. Improvements identified in CLOMR Submittal, July 2010, by Kimley‐Horn and Associates, Inc. 6. Does not include vertical facility costs. Proposed building costs assumed to be paid by third‐party developers. 7. Programmatic amount provided by MADC. 8. Reference Exhibit 4.2 and Appendix A for parcel identification. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 2 ‐ PROJECT IMPLEMENTATION SCHEDULE (BY DEVELOPMENT AREA) Implementation Schedule Item # Project Name AIRFIELD EXPANSION Parallel Runway 18L‐36R and Taxiway 1.01 Parallel Runway 18L‐36R and Taxiway Widening 1.02 1.03 Runway 18L‐36R and Taxiway Extension Runway 18R‐36L and Taxiway Extension 1.04 North / East Access Perimeter Road 1.05 GA TERMINAL FACILITY GA Terminal Facility ‐ Phase 1 2.01 2.02a GA Terminal Facility ‐ Phase 2 2.02b GA Terminal Facility ‐ Phase 3 GA Terminal Facility Entrance Road 2.03 Northwestern Drainage Improvements 2.04 CENTRAL TERMINAL AREA 3.01a Community Hangar Development 3.01b Aeronautical Business Campus 3.02a 3.02b 3.02c 3.02d 3.03 3.04 Private Corporate Hangar Development Private Corporate Hangar Ramp Private Corporate Hangar East Access and Parking Private Corporate Hangar West Access and Parking Public Parking Infill and Rehabilitate Airport Entrance Central Aircraft Parking Apron Infill Rehabilitate Central Aircraft Parking Apron 3.05 HANGAR CAMPUS DEVELOPMENT Private Corporate Hangar Development 4.01a (South) Private Corporate Hangar Ramp (South) and 4.01b Veh. Parking 4.02a T‐ and Box Hangar Campus ‐ Phase 1 4.02b T‐ and Box Hangar Campus ‐ Phase 2 4.02c T‐ and Box Hangar Campus ‐ Phase 3 4.03 Maintenance Equipment Storage Building PAL 1 (2012‐2016) PAL 2 (2017‐2021) PAL 3 (2022‐2026) PAL 4 (2027‐2031) Beyond PAL 4 0 2 0 3 0 0 0 0 0 3 0 0 0 0 3 0 0 0 0 3 0 3 0 0 0 3 0 0 3 3 0 0 0 0 0 0 3 0 0 0 0 0 3 0 0 0 0 0 0 0 0 2 0 3 0 0 0 0 3 0 0 2 3 0 0 0 2 3 0 0 0 3 0 0 0 0 2 3 0 0 3 0 0 0 0 0 0 0 0 3 3 0 0 0 0 0 0 0 0 3 0 0 0 0 3 3 0 0 0 3 0 0 0 0 0 0 3 0 0 0 3 0 0 0 0 MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 2 ‐ PROJECT IMPLEMENTATION SCHEDULE (BY DEVELOPMENT AREA) Implementation Schedule Item # Project Name FM 546 / AIRPORT DRIVE IMPROVEMENTS FM 546 Extension 5.01 Airport Drive Improvements 5.02 COMMERCIAL PASSENGER SERVICE TERMINAL Commercial Passenger Terminal Complex 6.01 ENLOE ROAD IMPROVEMENTS Rehabilitate Enloe Road 7.01 Relocate Enloe Road 7.02 EAST AIRPORT DRIVE IMPROVEMENTS East Airport Drive 8.01 MISCELLANEOUS Property Acquisition ‐ General Aviation 9.01a Terminal Facility 9.01e Property Acquisition ‐ Central Terminal Area Property Acquisition ‐ Airfield Expansion / East Airport Development Property Acquisition ‐ North Runway Protection Zone Property Acquisition ‐ South Runway Protection Zone 9.02 9.03 Stormwater / Floodplain Mgt Master Plan Airport Master Utility Plan 9.01b 9.01c 9.01d PAL 1 (2012‐2016) PAL 2 (2017‐2021) PAL 3 (2022‐2026) PAL 4 (2027‐2031) Beyond PAL 4 0 0 2 2 0 0 3 3 0 0 0 0 0 0 3 0 0 2 2 0 0 3 3 0 0 0 2 0 3 0 2 0 0 0 0 0 2 0 0 0 0 2 0 0 0 2 0 0 0 0 0 0 2 0 0 2 0 0 0 0 2 0 0 0 0 Legend Project Preparation Construction / Project Implementation MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 3 ‐ PROJECT IMPLEMENTATION SCHEDULE (BY PAL) Implementation Schedule Item # Project Name Rehabilitate Central Aircraft Parking Apron GA Terminal Facility ‐ Phase 1 GA Terminal Facility Entrance Road Northwestern Drainage Improvements Public Parking Infill and Rehabilitate Airport 3.03 Entrance 4.02a T‐ and Box Hangar Campus ‐ Phase 1 3.05 2.01 2.03 2.04 Maintenance Equipment Storage Building Property Acquisition ‐ General Aviation 9.01a Terminal Facility 4.03 9.02 9.03 9.01d 3.01b 1.01 1.05 3.02c 4.02b Stormwater / Floodplain Mgt Master Plan Airport Master Utility Plan Property Acquisition ‐ North Runway Protection Zone Aeronautical Business Campus Parallel Runway 18L‐36R and Taxiway North / East Access Perimeter Road Private Corporate Hangar East Access and Parking T‐ and Box Hangar Campus ‐ Phase 2 9.01b Property Acquisition ‐ Central Terminal Area Property Acquisition ‐ Airfield Expansion / 9.01c East Airport Development 3.02a Private Corporate Hangar Development 3.02b Private Corporate Hangar Ramp Private Corporate Hangar West Access and 3.02d Parking Property Acquisition ‐ South Runway 9.01e Protection Zone 2.02a GA Terminal Facility ‐ Phase 2 PAL 1 (2012‐2016) PAL 2 (2017‐2021) PAL 3 (2022‐2026) PAL 4 (2027‐2031) Beyond PAL 4 3 0 0 0 0 3 3 3 0 0 0 0 0 0 0 0 0 0 0 0 3 0 0 0 0 3 0 0 0 0 3 0 0 0 0 2 0 0 0 0 2 0 0 0 0 2 0 0 0 0 2 0 0 0 0 2 0 0 3 2 3 0 0 0 0 3 0 0 0 0 0 3 0 0 0 0 3 0 0 0 0 2 0 0 0 0 2 0 0 0 0 2 3 0 0 0 2 3 0 0 0 2 3 0 0 0 0 2 0 0 0 0 3 0 0 MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 3 ‐ PROJECT IMPLEMENTATION SCHEDULE (BY PAL) Implementation Schedule Item # Project Name 1.02 GA Terminal Facility ‐ Phase 3 T‐ and Box Hangar Campus ‐ Phase 3 FM 546 Extension Airport Drive Improvements Rehabilitate Enloe Road Relocate Enloe Road East Airport Drive Parallel Runway 18L‐36R and Taxiway Widening 1.03 Runway 18L‐36R and Taxiway Extension 2.02b 4.02c 5.01 5.02 7.01 7.02 8.01 1.04 Runway 18R‐36L and Taxiway Extension 3.01a Community Hangar Development 3.04 Central Aircraft Parking Apron Infill Private Corporate Hangar Development 4.01a (South) Private Corporate Hangar Ramp (South) and 4.01b Veh. Parking 6.01 Commercial Passenger Terminal Complex PAL 1 (2012‐2016) PAL 2 (2017‐2021) PAL 3 (2022‐2026) PAL 4 (2027‐2031) Beyond PAL 4 0 0 0 0 0 0 0 0 0 2 2 2 2 2 0 0 0 0 0 0 0 3 3 3 3 3 3 3 0 0 0 0 0 0 0 0 0 0 0 3 0 0 0 0 3 0 0 0 0 3 0 0 0 0 0 0 0 0 3 3 0 0 0 0 3 0 0 0 0 3 0 0 0 0 3 Legend Project Preparation Construction / Project Implementation MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 4 ‐ SUMMARY Item # Project Name PAL 1 Total (2012‐2016) PAL 2 Total (2017‐2021) PAL 3 Total (2022‐2026) PAL 4 Total Beyond PAL 4 (2027‐2031) Total Program Total1,2 AIRFIELD EXPANSION 1.02 Parallel Runway 18L‐36R and Taxiway Parallel Runway 18L‐36R and Taxiway Widening 1.03 Runway 18L‐36R and Taxiway Extension $ 11,309,000 $ 11,309,000 1.04 Runway 18R‐36L and Taxiway Extension $ 14,445,000 $ 14,445,000 1.01 $ 8,135,000 $ 81,345,000 $ 89,480,000 $ 8,626,000 $ 8,626,000 North / East Access Perimeter Road3 $ 4,700,000 SUBTOTAL $ ‐ $ 12,835,000 $ ‐ $ 81,345,000 $ 34,380,000 GA TERMINAL FACILITY 4 $ 12,018,000 2.01 GA Terminal Facility ‐ Phase 1 2.02a GA Terminal Facility ‐ Phase 2 $ 2,565,000 2.02b GA Terminal Facility ‐ Phase 3 $ 2,565,000 2.03 GA Terminal Facility Entrance Road $ 1,320,000 1.05 2.04 Northwestern Drainage Improvements5 $ 4,300,000 SUBTOTAL $ 17,638,000 $ ‐ $ 2,565,000 $ 2,565,000 $ ‐ $ 4,700,000 $ 128,560,000 $ 12,018,000 $ 2,565,000 $ 2,565,000 $ 1,320,000 $ 4,300,000 $ 22,768,000 MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 4 ‐ SUMMARY Item # Project Name CENTRAL TERMINAL AREA 6 3.01a Community Hangar Development 6 3.01b Aeronautical Business Campus Private Corporate Hangar 6 3.02a Development 3.02b Private Corporate Hangar Ramp Private Corporate Hangar East Access & 3.02c Parking Private Corporate Hangar West Access 3.02d & Parking Public Parking Infill and Rehabilitate 3.03 Airport Entrance 3.04 Central Aircraft Parking Apron Infill Rehabilitate Central Aircraft Parking 3.05 Apron SUBTOTAL PAL 1 Total (2012‐2016) PAL 2 Total (2017‐2021) PAL 3 Total (2022‐2026) PAL 4 Total Beyond PAL 4 (2027‐2031) Total $ ‐ $ 374,000 $ 1,496,000 Program Total1,2 $ ‐ $ 1,870,000 $ ‐ $ ‐ $ 319,000 $ 3,187,000 $ ‐ $ 3,506,000 $ 2,013,000 $ 2,013,000 $ 138,000 $ 1,384,000 $ 1,522,000 $ 2,907,000 $ 2,907,000 $ 1,141,000 $ 1,141,000 $ 3,966,000 $ 7,247,000 $ 3,966,000 $ 4,571,000 $ ‐ $ 3,966,000 $ 1,141,000 $ 16,925,000 MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 4 ‐ SUMMARY Item # Project Name HANGAR CAMPUS DEVELOPMENT Private Corporate Hangar Development 6 4.01a (South) Private Corporate Hangar Ramp (South) 4.01b and Vehicular Parking T‐ and Box Hangar Campus 6 4.02a Phase 1 T‐ and Box Hangar Campus 6 4.02b Phase 2 T‐ and Box Hangar Campus 6 4.02c Phase 3 Maintenance Equipment Storage 7 4.03 Building SUBTOTAL FM 546 / AIRPORT DRIVE IMPROVEMENTS 5.01 FM 546 Extension 5.02 Airport Drive Improvements SUBTOTAL COMMERCIAL PASSENGER SERVICE TERMINAL Commercial Passenger Terminal 6.01 Complex SUBTOTAL ENLOE ROAD IMPROVEMENTS 7.01 Rehabilitate Enloe Road 7.02 Relocate Enloe Road SUBTOTAL EAST AIRPORT DRIVE IMPROVEMENTS 8.01 East Airport Drive SUBTOTAL PAL 1 Total (2012‐2016) PAL 2 Total (2017‐2021) PAL 3 Total (2022‐2026) PAL 4 Total Beyond PAL 4 (2027‐2031) Total $ ‐ Program Total1,2 $ ‐ $ 3,513,000 $ 3,513,000 $ 8,051,000 $ 8,051,000 $ 3,573,000 $ 3,573,000 $ 3,867,000 $ 300,000 $ 8,351,000 $ 3,573,000 $ ‐ $ 3,867,000 $ 300,000 $ 3,867,000 $ 3,513,000 $ 19,304,000 $ ‐ $ 177,000 $ 135,000 $ 312,000 $ ‐ $ 708,000 $ 539,000 $ 1,247,000 $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ 151,000 $ 300,000 $ 451,000 $ ‐ $ 1,007,000 $ 2,000,000 $ 3,007,000 $ ‐ $ 1,158,000 $ 2,300,000 $ 3,458,000 $ ‐ $ 246,000 $ 246,000 $ ‐ $ 2,464,000 $ 2,464,000 $ ‐ $ 2,710,000 $ 2,710,000 $ ‐ $ 885,000 $ 674,000 $ 1,559,000 $ 43,068,000 $ 43,068,000 $ 43,068,000 $ 43,068,000 MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT TABLE 4 ‐ SUMMARY Item # Project Name PAL 1 Total (2012‐2016) PAL 2 Total (2017‐2021) PAL 3 Total (2022‐2026) PAL 4 Total Beyond PAL 4 (2027‐2031) Total PROPERTY ACQUISITION AND MASTER PLANS Property Acquisition ‐ General Aviation 8 9.01a Terminal Facility $ 7,553,000 Property Acquisition ‐ Central Terminal 8 9.01b Area $ 7,266,000 Property Acquisition ‐ Airfield 8 9.01c Expansion / East Airport Development Property Acquisition ‐ North Runway 8 9.01d Protection Zone Property Acquisition ‐ South Runway 8 9.01e Protection Zone Engineer / Design Stormwater / 9.02 Floodplain Mgt Master Plan Engineer / Design Airport Master Utility 9.03 Plan SUBTOTAL TOTAL CAPITAL IMPROVEMENT PROGRAM SHARE OF TOTAL PROGRAM Program Total1,2 $ 7,553,000 $ 7,266,000 $ 32,648,000 $ 32,648,000 $ 664,000 $ 664,000 $ 16,814,000 $ 150,000 $ 16,814,000 $ 150,000 $ 100,000 $ 100,000 $ 8,467,000 $ 39,914,000 $ 16,814,000 $ ‐ $ ‐ $ 65,195,000 $ 41,703,000 $ 61,297,000 $ 23,950,000 $ 94,495,000 $ 82,102,000 $ 303,547,000 14% 20% 8% 31% 27% 100% Notes: 1. All figures in 2012 dollars. 2. Additional capital improvement projects may be generated for implementation within the planning period following the master plan items identified in Items 9.02 & 9.03. 3. Programmatic estimate adopted from 2004 Master Plan Update by Wilbur Smith Associates, Inc. 4. Includes Engineering / Design of entire apron area depicted with appropriate construction phasing identified. 5. Programmatic amount based on bid pricing of this work, as provided by MADC, which was deleted from construction of the runway replacement project. Improvements identified in CLOMR Submittal, July 2010, by Kimley‐Horn and Associates, Inc. 6. Does not include vertical facility costs. Proposed building costs assumed to be paid by third‐party developers. 7. Programmatic amount provided by MADC. 8. Reference Exhibit 4.2 and Appendix A for parcel identification. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 1 - Airfield Expansion Item 1.01 - Parallel Runway 18L - 36R (6002' x 100') and Taxiway (50') 1 QTY Description Unit Unit Price Total MOBILIZATION Mobilization (7.5%) 1 LS $ 4,935,000 $ 4,935,000 Stormwater Pollution Prevention 1 LS $ 100,000 $ 100,000 130 Acre $ 5,000 $ 650,000 Offsite Material Embankment in Place 3,510,000 CY $ 10 $ 35,100,000 Compaction Factor (30%) 1,053,000 CY $ 10 $ 10,530,000 Unclassified Excavation / Embankment 1,000,000 CY $ 2 $ 2,000,000 100,000 CY $ 3 $ 300,000 144,000 SY $ 46 $ 6,624,000 Stabilized Base Course (4" HMA) 31,000 TON $ 65 $ 2,015,000 Lime-Stabilized Subgrade (8") 180,000 SY $ 3 $ 540,000 5,000 TON $ 149 $ 745,000 1 LS $ 2,500,000 $ 2,500,000 Electrical / Equipment Allowance 1 LS $ 3,000,000 $ 3,000,000 Water / Sewer Allowance 1 LS $ 400,000 $ 400,000 7,400 LF $ 40 $ 296,000 1 LS $ 1,000,000 $ 1,000,000 1 LS $ 10,610,000 $ 10,610,000 Subtotal, Construction $ 81,345,000 $ 8,135,000 $ 89,480,000 2 EARTHWORK Clear and Grub Rock Excavation 3 PAVEMENT Surface Course (17" PCC) Hydrated Lime (54 LB/SY) GRADING AND DRAINAGE Grading and Drainage Allowance UTILITIES FENCING Demo / Install 6' Chain Link w/3 Strand Wire & Mow Strip FINISHING Stabilization / Erosion Control CONTINGENCY Contingency (15%) ENVIRONMENTAL REVIEW / ENGINEERING & DESIGN Total Notes / Assumptions: 1. Does not include construction cost of master stormwater facilities that may be required in conjunction with airfield expansion, to be identified by Stormwater / Floodplain Management Master Plan 2. Based on mass grading from proposed surfaces taken from Replacement Runway design drawings, provided by KSA Engineers, Inc. 3. Assumes pavement section matching Runway 18 - 36. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 1 - Airfield Expansion Item 1.02 - Parallel Runway 18L - 36R (6002' x 150') and Taxiway (75') Widening QTY Description Unit Unit Price Total MOBILIZATION Mobilization (7.5%) 1 LS $ 476,000 $ 476,000 Stormwater Pollution Prevention 1 LS $ 100,000 $ 100,000 1 EARTHWORK Clear and Grub 25 Acre $ 5,000 $ 125,000 145,000 CY $ 2 $ 290,000 60,000 SY $ 46 $ 2,760,000 Stabilized Base Course (4" HMA) 13,000 TON $ 65 $ 845,000 Lime-Stabilized Subgrade (8") 75,000 SY $ 3 $ 225,000 Hydrated Lime (54 LB/SY) 2,000 TON $ 149 $ 298,000 1 LS $ 500,000 $ 500,000 1 LS $ 1,000,000 $ 1,000,000 1 LS $ 200,000 $ 200,000 1 LS $ 1,023,000 $ 1,023,000 Subtotal, Construction $ 7,842,000 $ 784,000 $ 8,626,000 Unclassified Excavation PAVEMENT Surface Course (17" PCC) GRADING AND DRAINAGE Grading and Drainage Allowance UTILITIES Electrical / Equipment Allowance FINISHING Stabilization / Erosion Control CONTINGENCY Contingency (15%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes earthwork completed in 1.01 to enable expansion of paved surfaces without mass grading. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 1 - Airfield Expansion Item 1.03 - Parallel Runway 18L - 36R and Taxiway Extension (1000' x 150') 1 QTY Description Unit Unit Price Total MOBILIZATION Mobilization (7.5%) 1 LS $ 624,000 $ 624,000 Stormwater Pollution Prevention 1 LS $ 100,000 $ 100,000 35 Acre $ 5,000 $ 175,000 Offsite Material Embankment in Place 150,000 CY $ 10 $ 1,500,000 Compaction Factor (30%) 45,000 CY $ 10 $ 450,000 Unclassified Excavation / Embankment 175,000 CY $ 2 $ 350,000 Rock Excavation 20,000 CY $ 3 $ 60,000 35,000 SY $ 46 $ 1,610,000 2 EARTHWORK Clear and Grub 3 PAVEMENT Surface Course (17" PCC) Stabilized Base Course (4" HMA) 8,000 TON $ 65 $ 520,000 Lime-Stabilized Subgrade (8") 44,000 SY $ 3 $ 132,000 Hydrated Lime (54 LB/SY) 1,000 TON $ 149 $ 149,000 1 LS $ 750,000 $ 2,000,000 1 LS $ 1,000,000 $ 1,000,000 1 LS $ 270,000 $ 270,000 1 LS $ 1,341,000 $ 1,341,000 Subtotal, Construction $ 10,281,000 $ 1,028,000 $ 11,309,000 GRADING AND DRAINAGE Grading and Drainage Allowance UTILITIES Electrical / Equipment Allowance FINISHING Stabilization / Erosion Control CONTINGENCY Contingency (15%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes runway / taxiway widening (Item 1.02) complete. 2. Based on mass grading from proposed surfaces taken from Replacement Runway design drawings, provided by KSA Engineers, Inc. 3. Assumes pavement section matching Runway 18 - 36. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 1 - Airfield Expansion Item 1.04 - Runway 18R - 36L and Taxiway Extension (1500' x 150') QTY Description Unit Unit Price Total MOBILIZATION Mobilization (7.5%) 1 LS $ 797,000 $ 797,000 Stormwater Pollution Prevention 1 LS $ 100,000 $ 100,000 45 Acre $ 5,000 $ 225,000 190,000 CY $ 10 $ 1,900,000 1 EARTHWORK Clear and Grub Offsite Material Embankment in Place Compaction Factor (30%) 57,000 CY $ 10 $ 570,000 Unclassified Excavation / Embankment 175,000 CY $ 2 $ 350,000 Rock Excavation 20,000 CY $ 3 $ 60,000 PAVEMENT2 Surface Course (17" PCC) 50,000 SY $ 46 $ 2,300,000 Stabilized Base Course (4" HMA) 12,000 TON $ 65 $ 780,000 Lime-Stabilized Subgrade (8") 63,000 SY $ 3 $ 189,000 Hydrated Lime (54 LB/SY) 2,000 TON $ 149 $ 298,000 1 LS $ 1,000,000 $ 1,000,000 1 LS $ 2,500,000 $ 2,500,000 1 LS $ 350,000 $ 350,000 1 LS $ 1,713,000 $ 1,713,000 Subtotal, Construction $ 13,132,000 $ 1,313,000 $ 14,445,000 GRADING AND DRAINAGE Grading and Drainage Allowance UTILITIES Electrical / Equipment Allowance FINISHING Stabilization / Erosion Control CONTINGENCY Contingency (15%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Based on mass grading from proposed surfaces taken from Replacement Runway design drawings, provided by KSA Engineers, Inc. 2. Assumes pavement section matching Runway 18 - 36. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 2 - General Aviation Terminal Facility Item 2.01 - GA Terminal Facility incl. Landside Parking, Facility, and Aircraft Apron Phase 1 1,2 Description Terminal Facility 3 4 QTY Unit 1 EA Unit Price $ Total 5,500,000 $ 5,500,000 Aircraft Parking Apron Auto Parking and Access Road 1 LS $ 3,988,000 1 LS $ 1,320,000 $ $ 3,988,000 1,320,000 Common / Maintenance Hangar 1 LS $ 2,530,000 $ 2,530,000 Total $ 13,338,000 Notes / Assumptions: 1. Based on estimates provided by MADC. 2. Line items include a 10% "Contingency" factor. 3. Approximately 20,000 SF. 4. Approximately 225,000 SF (5+ Acres). MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 3 - Central Terminal Area Item 3.01b - Aeronautical Business Campus QTY Unit Mobilization (7.5%) 1 LS $ 95,000 $ 95,000 Stormwater Pollution Prevention 1 LS $ 25,000 $ 25,000 Clear and Grub 5 Acre $ 5,000 $ 25,000 Unclassified Excavation / Embankment 1 LS $ 75,000 $ 75,000 3 EA $ - $ - Landside Parking Lot / Access Paving 2 5,000 SY $ 40 $ 200,000 Aircraft Parking Apron 3 Landside Parking Lot Striping & Signage 6,000 SY $ 75 $ 450,000 1 LS $ 20,000 $ 20,000 1 LS $ 150,000 $ 150,000 8" DIP (Water) 500 LF $ 40 $ 20,000 8" SDR 35 (Sewer) 500 LF $ 30 $ 15,000 1 LS $ 10,000 $ 10,000 1 LS $ 125,000 $ 125,000 1 LS $ 150,000 $ 150,000 1 LS $ 136,000 $ 136,000 Subtotal, Construction $ 1,496,000 $ 374,000 $ 1,870,000 Description Unit Price Total MOBILIZATION EARTHWORK FACILITIES 7,500 SF Hangar / Office Space 1 PAVEMENT DRAINAGE Stormwater Drainage Allowance UTILITIES Water and Sewer Connections, Etc. ELECTRICAL Conduit / Wire, Trenching, Lighting, Etc. FINISHING Landscape / Irrigation Allowance CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes facility development costs by others. 2. Assumes pavement section matching control tower parking. Ref: Collin County Regional Airport ATCT drawings, Sheet C4, Rev 2 (5/20/2010), provided by KSA Engineers, Inc. 3. Assumes pavement section matching central apron rehabilitation project conceptually developed by KSA Engineers, Inc., per "Request for Financial Assistance" letter, dated 9/7/11, provided by MADC. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 3 - Central Terminal Area Item 3.02b - Private Corporate Hangar Ramp QTY Unit Mobilization (7.5%) 1 LS $ 202,000 $ 202,000 Stormwater Pollution Prevention 1 LS $ 25,000 $ 25,000 9 Acre $ 5,000 $ 45,000 1 LS $ 105,000 $ 105,000 30,000 SY $ 75 $ 2,250,000 1 LS $ 150,000 $ 150,000 3,000 LF $ 40 $ 120,000 1 LS $ 290,000 $ 290,000 Subtotal, Construction $ 3,187,000 $ 319,000 $ 3,506,000 Description Unit Price Total MOBILIZATION EARTHWORK Clearing and Grubbing Unclassified Excavation / Embankment 1 PAVEMENT2 Aircraft Parking Apron DRAINAGE Stormwater Drainage Allowance FENCING Demo / Install 6' Chain Link w/3 Strand Wire & Mow Strip CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes net "Cut" condition with no import fill required. Ref: Mass Grading Exhibit, Collin County Regional Airport Master Drainage and Grading Plan , Kimley-Horn and Associates, Inc. 2004 2. Assumes pavement section matching central apron rehabilitation project conceptually developed by KSA Engineers, Inc., per "Request for Financial Assistance" letter, dated 9/7/11, provided by MADC. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 3 - Central Terminal Area Item 3.02c - Private Corporate Hangar East Access and Parking QTY Unit Mobilization (7.5%) 1 LS $ 102,000 $ 102,000 Stormwater Pollution Prevention 1 LS $ 25,000 $ 25,000 5 Acre $ 5,000 $ 25,000 1 LS $ 75,000 $ 75,000 15,800 SY $ 40 $ 632,000 1 LS $ 125,000 $ 125,000 1 LS $ 150,000 $ 150,000 1 LS $ 180,000 $ 180,000 1 LS $ 150,000 $ 150,000 1 LS $ 146,000 $ 146,000 Subtotal, Construction $ 1,610,000 $ 403,000 $ 2,013,000 Description Unit Price Total MOBILIZATION EARTHWORK Clear and Grub Unclassified Excavation / Embankment PAVEMENT Parking Lot and Access Drive Paving 2 Striping & Signage 1 DRAINAGE Stormwater Drainage Allowance ELECTRICAL Area Lighting FINISHING Landscape / Irrigation Allowance CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes net "Cut" condition with no import fill required. Ref: Mass Grading Exhibit, Collin County Regional Airport Master Drainage and Grading Plan , Kimley-Horn and Associates, Inc. 2004 2. Assumes pavement section matching control tower parking. Ref: Collin County Regional Airport ATCT drawings, Sheet C4, Rev 2 (5/20/2010), provided by KSA Engineers, Inc. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 3 - Central Terminal Area Item 3.02d - Private Corporate Hangar West Access and Parking QTY Unit Mobilization (7.5%) 1 LS $ 88,000 $ 88,000 Stormwater Pollution Prevention 1 LS $ 25,000 $ 25,000 4 Acre $ 5,000 $ 20,000 1 LS $ 75,000 $ 75,000 12,000 SY $ 40 $ 480,000 1 LS $ 100,000 $ 100,000 1 LS $ 120,000 $ 120,000 1 LS $ 200,000 $ 200,000 1 LS $ 150,000 $ 150,000 1 LS $ 126,000 $ 126,000 Subtotal, Construction $ 1,384,000 $ 138,000 $ 1,522,000 Description Unit Price Total MOBILIZATION EARTHWORK Clear and Grub Unclassified Excavation / Embankment PAVEMENT Parking Lot and Access Drive Paving 2 Striping & Signage 1 DRAINAGE Stormwater Drainage Allowance ELECTRICAL Area Lighting FINISHING Landscape / Irrigation Allowance CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes net "Cut" condition with no import fill required. Ref: Mass Grading Exhibit, Collin County Regional Airport Master Drainage and Grading Plan , Kimley-Horn and Associates, Inc. 2004 2. Assumes pavement section matching control tower parking. Ref: Collin County Regional Airport ATCT drawings, Sheet C4, Rev 2 (5/20/2010), provided by KSA Engineers, Inc. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 3 - Central Terminal Area Item 3.03 - Public Parking Infill and Rehabiliate Airport Entrance QTY Unit Mobilization (7.5%) 1 LS $ 168,000 $ 168,000 Maintenance of Traffic 1 LS $ 125,000 $ 125,000 Stormwater Pollution Prevention 1 LS $ 60,000 $ 60,000 5 Acre $ 15,000 $ 75,000 1 LS $ 115,000 $ 115,000 22,000 SY $ 40 $ 880,000 1 LS $ 200,000 $ 200,000 1 LS $ 200,000 $ 200,000 1 LS $ 150,000 $ 150,000 1 LS $ 180,000 $ 180,000 1 LS $ 250,000 $ 250,000 1 LS $ 240,000 $ 240,000 Subtotal, Construction $ 2,643,000 $ 264,000 $ 2,907,000 Description Unit Price Total MOBILIZATION DEMOLITION Clear and Grub / Pavement Demo EARTHWORK Unclassified Excavation / Embankment 1 PAVEMENT Parking Lot and Drive Paving 2 Parking Lot Striping & Signage DRAINAGE Stormwater Drainage Allowance UTILITIES Utility Relo / Adjustment Allowance ELECTRICAL Area Lighting FINISHING Landscape / Irrigation Allowance CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes net "Cut" condition with no import fill required. Ref: Mass Grading Exhibit, Collin County Regional Airport Master Drainage and Grading Plan , Kimley-Horn and Associates, Inc. 2004 2. Assumes pavement section matching control tower parking. Ref: Collin County Regional Airport ATCT drawings, Sheet C4, Rev 2 (5/20/2010), provided by KSA Engineers, Inc. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 3 - Central Terminal Area Item 3.04 - Central Aircraft Parking Apron Infill Description QTY Unit 1 LS $ 58,000 $ 58,000 1 LS $ 110,000 $ 110,000 7,400 SY $ 75 $ 555,000 1 LS $ 75,000 $ 75,000 800 LF $ 40 $ 32,000 1 LS $ 83,000 $ 83,000 Subtotal, Construction $ 913,000 $ 228,000 $ 1,141,000 Unit Price Total MOBILIZATION Mobilization (7.5%) EARTHWORK Site Preparation 1 (1.5 Acres) PAVEMENT Aircraft Parking Apron 2 DRAINAGE Stormwater Drainage Allowance FENCING Demo / Install 6' Chain Link w/3 Strand Wire & Mow Strip CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Approximately 1.5 Acre area to be paved. 2. Assumes pavement section matching central apron rehabilitation project conceptually developed by KSA Engineers, Inc., per "Request for Financial Assistance" letter, dated 9/7/11, provided by MADC. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 4 - Commercial Passenger Service Terminal Item 4.01b - Private Corporate Hangar Ramp (South) and Vehicular Parking QTY Unit Mobilization (7.5%) 1 LS $ 203,000 $ 203,000 Stormwater Pollution Prevention 1 LS $ 25,000 $ 25,000 15 Acre $ 5,000 $ 75,000 1 LS $ 160,000 $ 160,000 20,000 SY $ 75 $ 1,500,000 16,000 SY $ 40 $ 640,000 1 LS $ 150,000 $ 150,000 Description Unit Price Total MOBILIZATION EARTHWORK Clearing and Grubbing Unclassified Excavation / Embankment PAVEMENT 1 Aircraft Parking Apron 2 Landside Parking Lot Paving 3 DRAINAGE Stormwater Drainage Allowance 4 UTILITIES 6" DIP (Water) 1,000 LF $ 30 $ 30,000 1,000 LF $ 30 $ 30,000 Water and Sewer Connections, Etc. 1 LS $ 10,000 $ 10,000 Sanitary Lift Station 1 LS $ 25,000 $ 25,000 1,400 LF $ 40 $ 56,000 1 LS $ 290,000 $ 290,000 Subtotal, Construction $ 3,194,000 $ 319,000 $ 3,513,000 8" SDR 35 (Sewer) FENCING Demo / Install 6' Chain Link w/3 Strand Wire & Mow Strip CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes net "Cut" condition with no import fill required. Ref: Mass Grading Exhibit, Collin County Regional Airport Master Drainage and Grading Plan , Kimley-Horn and Associates, Inc. 2004. Enables pad leveling for all hangar sites. 2. Assumes pavement section matching central apron rehabilitation project conceptually developed by KSA Engineers, Inc., per "Request for Financial Assistance" letter, dated 9/7/11, provided by MADC. 3. Assumes pavement section matching control tower parking. Ref: Collin County Regional Airport ATCT drawings, Sheet C4, Rev 2 (5/20/2010), provided by KSA Engineers, Inc. 4. Assumes service connections available along adjacent FM546 without improvements to the main line. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 4 - Hangar Campus Development Item 4.02a - T- and Box Hangar Campus, Phase 1 1 QTY Unit Mobilization (7.5%) 1 LS $ 464,000 $ 464,000 Stormwater Pollution Prevention 1 LS $ 25,000 $ 25,000 33 Acre $ 5,000 $ 165,000 1 LS $ 250,000 $ 250,000 21,700 SY $ 40 $ 868,000 52,000 SY $ 75 $ 3,900,000 1 LS $ 250,000 $ 250,000 2,500 LF $ 40 $ 100,000 Description Unit Price Total MOBILIZATION 2 EARTHWORK Clear and Grub Unclassified Excavation / Embankment 3 PAVEMENT Parking Lot and Access Drive Paving 4 Aircraft Parking Apron DRAINAGE 5 Stormwater Drainage Allowance 6 UTILITIES 8" DIP (Water) 8" SDR 35 (Sewer) 2,500 LF $ 30 $ 75,000 Water and Sewer Connections, Etc. 1 LS $ 10,000 $ 10,000 Sanitary Lift Station 1 LS $ 25,000 $ 25,000 1,800 LF $ 40 $ 72,000 Landscape / Stabilization Allowance 1 LS $ 400,000 $ 400,000 Irrigation Allowance 1 LS $ 50,000 $ 50,000 1 LS $ 665,000 $ 665,000 Subtotal, Construction $ 7,319,000 $ 732,000 $ 8,051,000 FENCING Demo / Install 6' Chain Link w/3 Strand Wire & Mow Strip FINISHING CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Programmatic estimate includes pavement only, no facilities (all phases). 2. Assumes to accommodate area for all three phases of the campus, enabling pavement expansion on subsequent phases. 3. Assumes net "Cut" condition with no import fill required. Ref: Mass Grading Exhibit, Collin County Regional Airport Master Drainage and Grading Plan , Kimley-Horn and Associates, Inc. 2004 4. Assumes pavement section matching control tower parking. Ref: Collin County Regional Airport ATCT drawings, Sheet C4, Rev 2 (5/20/2010), provided by KSA Engineers, Inc. 5. Assumes pavement section matching central apron rehabilitation project conceptually developed by KSA Engineers, Inc., per "Request for Financial Assistance" letter, dated 9/7/11, provided by MADC. 6. Provides water / sewer service lines and stubouts for all future phases. Assumes connection to main line at adjacent FM 546 without improvements to main line. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 4 - Hangar Campus Development Item 4.02b - T- and Box Hangar Campus, Phase 2 QTY Unit Mobilization (7.5%) 1 LS $ 206,000 $ 206,000 Stormwater Pollution Prevention 1 LS $ 25,000 $ 25,000 1 LS $ 50,000 $ 50,000 11000 CY $ 2 $ 22,000 32,000 SY $ 75 $ 2,400,000 1 LS $ 150,000 $ 150,000 1 LS $ 100,000 $ 100,000 1 LS $ 295,000 $ 295,000 Subtotal, Construction $ 3,248,000 $ 325,000 $ 3,573,000 Description Unit Price Total MOBILIZATION EARTHWORK Clearing and Grubbing Unclassified Excavation PAVEMENT 1 Aircraft Parking Apron 2 DRAINAGE Stormwater Drainage Allowance FINISHING Stabilization / Erosion Control CONTINGENCY Contingency (10%) CONSTRUCTION ADMINISTRATION Total Notes / Assumptions: 1. Assumes cut to accommodate pavement section (approximate 3' depth). 2. Assumes pavement section matching central apron rehabilitation project conceptually developed by KSA Engineers, Inc., per "Request for Financial Assistance" letter, dated 9/7/11, provided by MADC. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 4 - Hangar Campus Development Item 4.02c - T- and Box Hangar Campus, Phase 3 QTY Unit Mobilization (7.5%) 1 LS $ 223,000 $ 223,000 Stormwater Pollution Prevention 1 LS $ 25,000 $ 25,000 1 LS $ 50,000 $ 50,000 11000 CY $ 2 $ 22,000 35,000 SY $ 75 $ 2,625,000 1 LS $ 150,000 $ 150,000 1 LS $ 100,000 $ 100,000 1 LS $ 320,000 $ 320,000 Subtotal, Construction $ 3,515,000 $ 352,000 $ 3,867,000 Description Unit Price Total MOBILIZATION EARTHWORK Clearing and Grubbing Unclassified Excavation PAVEMENT 1 Aircraft Parking Apron 2 DRAINAGE Stormwater Drainage Allowance FINISHING Stabilization / Erosion Control CONTINGENCY Contingency (10%) CONSTRUCTION ADMINISTRATION Total Notes / Assumptions: 1. Assumes cut to accommodate pavement section (approximate 3' depth). 2. Assumes pavement section matching central apron rehabilitation project conceptually developed by KSA Engineers, Inc., per "Request for Financial Assistance" letter, dated 9/7/11, provided by MADC. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 5 - FM 546 / Airport Drive Improvements Item 5.01 - FM 546 Extension QTY Unit Mobilization (7.5%) 1 LS $ 40,000 $ 40,000 Maintenance of Traffic & ROW Prep (4%) 1 LS $ 20,000 $ 20,000 8 $ 41,000 Description Unit Price Total MOBILIZATION EARTHWORK Unclassified Street Excavation 1 Unclassified Embankment 5,100 CY $ 5,000 CY $ 8 $ 40,000 28" Lime Stabilization (@ 32lbs / SY) 5,000 SY $ 18 $ 90,000 4,600 SY $ 45 $ 207,000 1,000 TON $ 65 $ 65,000 1 LS $ 30,000 $ 30,000 1 LS $ 90,000 $ 90,000 3,000 SY $ 5 $ 15,000 1 LS $ 10,000 $ 10,000 1 LS $ 60,000 $ 60,000 Subtotal, Construction $ 708,000 $ 177,000 $ 885,000 2 PAVEMENT 8" Concrete Pavement 4" Asphalt Pavement Striping and Signage Allowance DRAINAGE Stormwater Drainage Allowance FINISHING 4" Topsoil Hydroseed Allowance CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes 1,200 LF length, two lane, undivided roadway with curb. Assumes net "Cut" condition with no import fill required. 2. Based on typical section from relocation of FM 546, provided by MADC. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 5 - FM 546 / Airport Drive Improvements Item 5.02 - Airport Drive Extension QTY Unit Mobilization (7.5%) 1 LS $ 30,000 $ 30,000 Maintenance of Traffic & ROW Prep (4%) 1 LS $ 20,000 $ 20,000 Description Unit Price Total MOBILIZATION EARTHWORK Unclassified Street Excavation 1 Unclassified Embankment 4,000 CY $ 8 $ 32,000 4,000 CY $ 8 $ 32,000 10" Lime Stabilization (@ 32lbs / SY) 5,000 SY $ 6 $ 30,000 5,000 SY $ 45 $ 225,000 1 LS $ 30,000 $ 30,000 1 LS $ 70,000 $ 70,000 2,000 SY $ 5 $ 10,000 1 LS $ 10,000 $ 10,000 1 LS $ 50,000 $ 50,000 Subtotal, Construction $ 539,000 $ 135,000 $ 674,000 PAVEMENT 8" Concrete Pavement Striping and Signage Allowance DRAINAGE Stormwater Drainage Allowance FINISHING 4" Topsoil Hydroseed Allowance CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes 775 LF length, four-lane roadway divided by median to match existing. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 6 - Commercial Passenger Service Terminal Complex QTY Unit Mobilization (7.5%) 1 LS $ 2,375,000 $ 2,375,000 Stormwater Pollution Prevention 1 LS $ 100,000 $ 100,000 50 Acre $ 5,000 $ 250,000 Offsite Material Embankment in Place 375,000 CY $ 10 $ 3,750,000 Compaction Factor (30%) 112,500 CY $ 10 $ 1,125,000 Unclassified Excavation / Embankment 200,000 CY $ 2 $ 400,000 Rock Excavation 30,000 CY $ 3 $ 90,000 50000 SF $ 250 $ 12,500,000 113,000 SY $ 40 $ 4,520,000 52,000 SY $ 95 $ 4,940,000 1 LS $ 900,000 $ 900,000 1 LS $ 1,000,000 $ 1,000,000 1,200 LF $ 45 $ 54,000 1,200 LF $ 30 $ 36,000 Water and Sewer Connections, Etc. 1 LS $ 10,000 $ 10,000 Sanitary Lift Station 1 LS $ 75,000 $ 75,000 Site Power Feed5 1 LS $ 200,000 $ 200,000 Landside Conduit / Wire, Trenching, Ltg, Etc. 1 LS $ 200,000 $ 200,000 Aircraft Parking Area Lighting 1 LS $ 200,000 $ 200,000 3,000 LF $ 40 $ 120,000 1 LS $ 1,000,000 $ 1,000,000 1 LS $ 200,000 $ 200,000 1 LS $ 3,405,000 $ 3,405,000 Subtotal, Construction $ 37,450,000 $ 5,618,000 $ 43,068,000 Description Unit Price Total MOBILIZATION EARTHWORK Clear and Grub FACILITIES Passenger Terminal Facility 1 PAVEMENT Landside Parking Lot Paving 2 Aircraft Parking Apron Striping & Signage 3 DRAINAGE Grading and Drainage Allowance UTILITIES4 12" DIP (Water) 8" SDR 35 (Sewer) ELECTRICAL FENCING Demo / Install 6' Chain Link w/3 Strand Wire & Mow Strip FINISHING Landscape / Stabilization Allowance Irrigation Allowance CONTINGENCY Contingency (10%) 6 ENVIRONMENTAL REVIEW / ENGINEERING & DESIGN Total MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 6 - Commercial Passenger Service Terminal Complex Notes / Assumptions: 1. Per MADC. 2. Assumes pavement section matching control tower parking. Ref: Collin County Regional Airport ATCT drawings, Sheet C4, Rev 2 (5/20/2010), provided by KSA Engineers, Inc. 3. Assumes pavement section matching Runway 18 - 36. 4. Assumes service connections available at East Airport Drive. 5. Allowance for electrical service connections, airport share of line extensions, etc. 6. Well, pump, lines, etc. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 7 - Enloe Road Improvements Item 7.01 - Rehabilitate Enloe Road QTY Unit Mobilization (7.5%) 1 LS $ 62,000 $ 62,000 Maintenance of Traffic & ROW Prep (4%) 1 LS $ 33,000 $ 33,000 5,600 SY $ 5 $ 28,000 7,000 SY $ 5 $ 35,000 Description Unit Price Total MOBILIZATION DEMOLITION Full Depth Asphalt Pavement Removal 1 EARTHWORK Rework Existing Base 2 Unclassified Street Excavation 8" Lime Stabilization (@ 32lbs / SY) 4,000 CY $ 8 $ 32,000 4,000 SY $ 5 $ 20,000 11,000 SY $ 45 $ 495,000 1 LS $ 25,000 $ 25,000 1 LS $ 130,000 $ 130,000 7000 SY $ 5 $ 35,000 1 LS $ 20,000 $ 20,000 1 LS $ 92,000 $ 92,000 Subtotal, Construction $ 1,007,000 $ 151,000 $ 1,158,000 PAVEMENT 6" Concrete Pavement Signage and Striping Allowance DRAINAGE Stormwater Drainage Allowance FINISHING 4" Topsoil Hydroseed / Stabilization Allowance CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes rehab of existing 20' pavement section, approximately 2,500' in length 2. Enables 10' widening from 20' to 30' and addition of curb to match Relocated Enloe Road (Item 7.02) MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 7 - Enloe Road Improvements Item 7.02 - Relocate Enloe Road 1 QTY Unit Mobilization (7.5%) 1 LS $ 122,000 $ 122,000 Maintenance of Traffic & ROW Prep (4%) 1 LS $ 65,000 $ 65,000 Description Unit Price Total MOBILIZATION EARTHWORK Offsite Material Embankment in Place 25,000 CY $ 10 $ 250,000 Unclassified Street Excavation 17,000 CY $ 8 $ 136,000 8" Lime Stabilization (@ 32lbs / SY) 19,000 SY $ 5 $ 95,000 18,000 SY $ 45 $ 810,000 1 LS $ 35,000 $ 35,000 1 LS $ 220,000 $ 220,000 9000 SY $ 5 $ 45,000 1 LS $ 40,000 $ 40,000 1 LS $ 182,000 $ 182,000 Subtotal, Construction $ 2,000,000 $ 300,000 $ 2,300,000 PAVEMENT 6" Concrete Pavement Signage and Striping Allowance DRAINAGE Stormwater Drainage Allowance FINISHING 4" Topsoil Hydroseed / Stabilization Allowance CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes 4,350 LF length, two lane undivided road section. Assumes no import fill required. Floodplain impacts and operational constraints due to this roadway placement to be identified and mitigated in appropriate additional studies and reviews. MARCH 2012 ALP UPDATE ‐ COLLIN COUNTY REGIONAL AIRPORT APPENDIX D ‐ PROGRAMMATIC ESTIMATE WORKSHEET Exhibit 8 - East Airport Drive1 QTY Unit Mobilization (7.5%) 1 LS $ 151,000 $ 151,000 Maintenance of Traffic & ROW Prep (4%) 1 LS $ 80,000 $ 80,000 Description Unit Price Total MOBILIZATION EARTHWORK Offsite Material Embankment In-Place 6,000 CY $ 10 $ 60,000 Unclassified Street Excavation 23,000 CY $ 8 $ 184,000 8" Lime Stabilization (@ 32lbs / SY) 27,000 SY $ 5 $ 135,000 26,000 SY $ 45 $ 1,170,000 1 LS $ 80,000 $ 80,000 1 LS $ 250,000 $ 250,000 14000 SY $ 5 $ 70,000 1 LS $ 60,000 $ 60,000 1 LS $ 224,000 $ 224,000 Subtotal, Construction $ 2,464,000 $ 246,000 $ 2,710,000 PAVEMENT 6" Concrete Pavement Signage and Striping Allowance DRAINAGE Stormwater Drainage Allowance FINISHING 4" Topsoil Hydroseed / Stabilization Allowance CONTINGENCY Contingency (10%) ENGINEERING & DESIGN Total Notes / Assumptions: 1. Assumes 6,150 LF length, two lane undivided road section. Fill for road section immediately adjacent to terminal site accounted for in Exhibit 6 programmatic estimates. MARCH 2012