Power factor correction system Installation, maintenance and commissioning manual. power QUALITY NHP Electrical Engineering Products Pty Ltd Sales 1300 NHP NHP nhp.com.au Commissioning record.....................................................................3 Commissioning manual...................................................................8 Preliminary Check................................................................................................................................................................................................9 Quick Start.................................................................................................................................................................................................................10 i) PFC System with CX controller.............................................................................................................................................10 ii) PFC System with CM controller...........................................................................................................................................11 1.Introduction.................................................................................................................................................................................................12 2.Installation.....................................................................................................................................................................................................13 3. Current Transformer...............................................................................................................................................................................15 4. Beluk Controller.........................................................................................................................................................................................17 4.1 BLR-CX Series Regulator...........................................................................................................................................................17 4.2 BLR-CM Series Regulator..........................................................................................................................................................33 5. Power Factor Correction System Fault Finding.....................................................................................................................53 Maintenance record.........................................................................56 Maintenance of NHP PFC Systems............................................................................................................................................................56 PFC-P Current Envelope, Voltage Reference at Bus Connection............................................................................................62 Maintenance Parts List......................................................................................................................................................................................66 Recommended Torque Settings for specific system components......................................................................................65 Appendix...........................................................................................71 A. Cable Requirements......................................................................................................................................................................................71 B. BLR-CX Setup Menu......................................................................................................................................................................................72 C. BLR-CX Expanded Setup Menu..............................................................................................................................................................73 Any installation or commissioning difficulties or comments can be forwarded to the NHP Power Quality Department. Due to continuous product technical development and improvement the information contained in this document is subject to change without notice. 2 commissioning record End user details: Customer : Site address : Switchboard designation : Installation: Company: Employee: Date: Unit details: Part no. : Shop order no.: kVAr installed: Date of manufacture: kVAr max. : Controller model: Amps max.: CT ratio: System voltage: Controller serial no: Upstream circuit breaker (make/model/reference): Commissioning details: Target Power Factor: Switching time delay: CT current present at controller: Confirmed phase rotation: Switch all steps individually and record phase currents in maintenance log: Turn off unused steps: Commissioned by Employee: Company: Signature: Date: End user signoff: End user name: Recommendations / comments: 3 commissioning record BLR-CX Controller settings Refer to Section 4.1.1 for further information to the settings shown below. MENU FACTORY SETTING NHP SETTING CUSTOMER SETTING 100 FACTORY SETTING NHP SETTING 400 Un 400 V 415V 401 75 s - Ct 1 Set on site 402 5 var (1-max.) - Pt 1 1 403 AUTO (1-max.) AUTO1 Ai NO NO 404 0 (1-max.) - PFC ON ON 500 CP1 1 0.96 501 NO NO St 10 s 40 s 502 NO YES 503 20 % 7% 200 201 400 V 415V 504 NO YES2 202 1 Set on Site 505 60 s 60 s 203 1 1 506 NO NO 204 10% 10% 507 NO YES 205 NO YES 508 262 k 2k 206 90º 90º 509 65.5 k h 65.5 k h 207 NO NO 510 NO NO 208 YES NO 511 NO NO 209 AUTO AUTO 512 NO NO 513 30 °C 30 °C 300 4 MENU 301 60% 60% 514 55 °C 55 °C 302 1 0.96% 515 NO NO 303 0,95 i 0.9% 516 NO YES 304 NO NO 517 NO YES 305 10 s 40 s 518 NO NO 306 2s 10 s 600 307 YES YES 601 NO NO 308 NO YES 602 NO NO 309 YES YES 603 NO NO 310 ON ON 604 NO NO 311 1 1 605 NO NO 312 0 0 606 NO NO 313 1 1 607 1.xx 1.xx 314 NO YES 1. For unused stops set to Foff. 2. Steps switched off if THVD exceeds threshold for specified time. CUSTOMER SETTING commissioning record BLR-CM Settings Adjust controller settings to NHP settings. For NHP settings not specified, leave as factory setting. Factory setting nhp setting Factory setting nhp setting English - Step Fault M, D - CT Ratio 1 Set on Site Step Warning M, D - VT Ratio 1 - Limit Step Warning 50% - Nominal Voltage 400V 415V Limit Switch Cycles 100000 - Connection L-N L-L Alarm power factor Disabled M, D Synchronisation frequency Auto - Limit cos phi min 0.90 c - Phase compensation 90° - Limit cos phi max 0.90 i - V-tolerance min 10% - Time delay 300s - V-tolerance max 10% - Alarm harmonics U M, D - Countdown Start AI Yes - Limit harmonics U 20% 5% Temperature Offset 0°C - Alarm Harmonics I Disabled M, D CT Type 1A No - Limit Harmonics I 50% 20% Discharge Time 75s - Alarm overload P No - Normal - Limit overload P 1.00kW - Control On - Alarm overload Q Disabled - Cos Phi 1 1.00 0.96 i Limit Overload Q 1.00kVAr - Cos Phi 2 0.95 i 0.90 i Alarm P Export Disabled - Switch Interval 10s 40s Alarm temperature 1 DO Disabled Switch Interval Step Exchange 2s 10s Limit Temperature 1 25°C 55°C Asymmetry Factor 1 - Hysteresis temperature 1 1.0°C - Step Recognition On - Alarm temperature 2 M, D, O No Switch Cycle Balancing No - Limit temperature 2 70°C - Switch Cycle Balancing % 10% - Hysteresis temperature 2 1.0°C - Step Exchange Yes - DI Input Alarm Disabled - Control Sensitivity 60% - DI Trigger High - Control Algorithm Auto - Frequency Alarm Disabled - Q Offset 0 kVAr - Limit Low Frequency 45.0 Hz - I < limit freeze steps No - Limit High Frequency 65.0Hz - Q cap. Steps turn off No Yes Modbus Baudrate 9600 - Fast measure delay 50 periods - Modbus Parity 8E1 - Fast max step value 0 kVAr - Modbus address 1 - Fast measure mean 0 periods - Storage Interval 0 min - M, D - Synchronisation DI Input Off - M - Setup DI input High - MENU Language Step Type Control Alarm No Current Alarm 1. 1 menu For unused stops set to Foff. POWER FACTOR CORRECTION SYSTEM 5 commissioning MANUAL commissioning MANUAL Preliminary check................................................................................................................................................. 9 Quick start............................................................................................................................................................ 10 i) PFC system with CX controller............................................................................................................................................ 10 ii) PFC system with CM controller........................................................................................................................................... 11 1.Introduction................................................................................................................................................... 12 2.Installation..................................................................................................................................................... 13 2.1 Location............................................................................................................................................................................................. 13 2.2 Preparation...................................................................................................................................................................................... 13 2.3 Current transformer.................................................................................................................................................................... 13 2.4 Cable.................................................................................................................................................................................................... 14 2.5 Power connection....................................................................................................................................................................... 14 2.6 Control wiring................................................................................................................................................................................ 14 2.7 Ventilation........................................................................................................................................................................................ 14 3. Current transformer..................................................................................................................................... 15 3.1 Specification................................................................................................................................................................................... 15 3.2 Installation........................................................................................................................................................................................ 15 3.3 Connection...................................................................................................................................................................................... 15 3.4 CT Wago connection diagram............................................................................................................................................ 16 4. Beluk controller............................................................................................................................................. 17 4.1 BLR-CX series regulator............................................................................................................................................................ 19 4.1.1 Familiarization with the BLR-CX controller........................................................................................................... 20 4.1.2 Setting up the BLR-CX controller............................................................................................................................... 21 4.1.3 Menu Structures.................................................................................................................................................................... 24 4.1.4 Setting phase compensation for different connections.............................................................................. 29 4.1.5 BLR-CX schematic................................................................................................................................................................ 30 4.1.6 BLR-CX regulator alarm codes...................................................................................................................................... 31 4.2 BLR-CM series regulator........................................................................................................................................................... 33 4.2.1 Getting familiar with the BLR CM Controller....................................................................................................... 35 4.2.2 Setting up the Beluk regulator to measure voltage and current........................................................... 37 4.2.3 Setting up the Beluk regulator’s capacitor steps.............................................................................................. 41 4.2.4 Setting up target power factor.................................................................................................................................... 43 4.2.5 Setting up switch interval time between steps................................................................................................ 43 4.2.6 Commencement of power factor regulation..................................................................................................... 44 4.2.7 Connection issues................................................................................................................................................................ 44 4.2.8 Setting up the Beluk regulator to compensate for different connections....................................... 45 4.2.9 Alarm settings......................................................................................................................................................................... 46 4.2.10 BLR-CM schematic............................................................................................................................................................... 52 5. Power factor correction system fault finding.......................................................................................... 53 Appendix.............................................................................................................................................................. 71 8 Appendix A - Cable requirements .......................................................................................................................................................... 71 Appendix B - BLR-CX setup menus ....................................................................................................................................................... 72 Appendix C - BLR-CX expanded setup menu ................................................................................................................................. 73 commissioning MANUAL Preliminary check Before energising the PFC system. 1. Ensure that all connections are tight. 2. Ensure that all fuses have been installed and that the fuse handle is fully closed on to the fuse base. 3. Ensure that all contactors have free movement of contacts. 4. Ensure the discharge resistors have not been damaged in transport. 5. Ensure correct phase connection/rotation at input to PFC system. Rotation must be clockwise (Red-White-Blue). 6. Ensure CT is correctly connected on the red phase. 7. Ensure the current reference of the regulator is connected to L1 (refer section 3.0) 8. System voltage of 400V ± 10%. Operation exceeding this system voltage may damage equipment. 9. At this stage, if all is in order according to points above, the Current Transformer shorting links can be removed and the Power Factor correction system can be switched on. Allow the Power Factor regulator time to go through its start up procedure. (Up to 90 seconds depending on the type of regulator.) 10. The Current Transformer and Potential Transformer (if used) ratios must be programmed. All Beluk regulators will accept connections from current transformers with a secondary current of either 1A or 5A. 11. For the BLR CM-RMB regulator, ensure appropriate alarm functions have been selected and the alarm limits entered. This will be dependant on what the customer has specified. Refer to section 4.2. Program the Power Factor regulator. Refer to section 4 for CX regulator and the advanced CM regulator. Use this manual in conjunction with the manufacturer’s manual for more advanced settings. Warning! - To protect your new investment the PFC system will automatically turn off in the event that the ambient temperature inside the system is too high. For systems relying on the demand capacity provided by the PFC system, please make use of the provided remote fault indication terminals within the PFC system to initiate load shedding until the environment affecting the PFC system returns to acceptable levels. POWER FACTOR CORRECTION SYSTEM 9 commissioning MANUAL Quick start i) PFC System with CX controller The CX controller has a specific menu (100) designed to incorporate all parameters required for a quick start process. This menu can be navigated to by using the ↓ function key from the top level menu structure. Once the setup light is illuminated on the right hand side of the screen, press the ↵ function key to enter the setup menu. The number 100 should be displayed on the screen, press the ↵ function key again to enter the quick start menu. Settings to be entered: 1. Un – Nominal Voltage Set the nominal voltage value. 2.Ct – Current Transformer Ratio Enter the current transformer ratio. Eg. 500 turns primary to 50 turns secondary = 10 3. Pt – Voltage Transformer Ratio Enter the voltage transformer ratio. If a voltage transformer is not used leave as 1. 4. Ai – Auto Initialize Set the automatic initialization to yes. This process will switch all outputs and gain information to correctly account for voltage and current measurement connections. 5. PFC – Power Factor Correction The power factor correction should be set to Yes to enable the controller to compensate for any reactive loads. 6.CP1 – Cos Phi 1 Set the target power factor. 7.St – Switch Interval Set the switching time interval (Time delay between switching steps). 8.OUt – Step Output Type Set the step outputs to auto. 10 commissioning MANUAL ii) PFC system with CM controller MEAS. VALUES HARMONICS STEPINFO SETUP SETUP MENU PASSWORD 2402 MAIN MENU MEASUREMENT MENU MEASUREMENT CT FACTOR STEP VT FACTOR CONTROL NOMINAL VOLT. MEASUREMENT DISPLAY ALARM MANUAL MODBUS RESET CONFIGURATION CONNECTION MEASUREMENT EXTENDED STEP MENU DISCHARGE TIME STEP TYPE RESET Q (VALUES) With reference to the pathways outlined on this page Settings to be entered: CONTROL MENU 1. Enter CT ratio. An example is: A 500/5A CT is used then we input “100” for the CT Factor COS PHI I 2. Enter VT ratio. If there are no Voltage Transformers then this setting should be left on one SWITCH INTERVAL COS PHI 2 3. Set Nominal Voltage value. SWITCH INTERVAL STEP EXCHANGE 4. Select how the measuring lines are connected (typically L-L). EXTENDED 5. Set up Capacitor Steps: • Discharge time should be set should be set to 70 seconds or more • All steps that are not switching capacitor steps should be switched to the “Off” position ALARM MENU CONTROL ALARM NO CURRENT STE FAULT 6. Enter COS PHI 1 (Target Power Factor) STEP WARNING 7. Adjust SWITCH INTERVAL TIME as required, typically 40 seconds. POWER FACTOR 8. Once the regulator has checked the voltage and current then a “Happy” face will appear and the regulator will switch steps in and out according to the variation of the load. HARMONICS I 9. Ensure power factor is on inductive side – i.e. “i” is displayed on screen. Note: For specific instructions see section 4.2 BLR-CM Series Regulator HARMONICS U OVERLOAD P OVERLOAD Q P-EXPORT TEMP1 TEMP2 DI INPUT P O W E R F A C T O R C O R R E C T I O N S Y S T E M 11 commissioning MANUAL 1.Introduction Before Installation read this manual carefully and keep it as a reference for future maintenance and operation requirements. A microprocessor based regulator, switching a group of capacitors to achieve a pre set Power Factor value controls the Power Factor correction (PFC) system. This manual details the correct installation and commissioning procedures for a NHP Power Factor correction system. The Power Factor regulator requires a current signal, which reflects the load. This can be achieved by using a current transformer appropriately sized in comparison to the load that will be compensated. Power Factor is a measure of how efficient the electrical power is being used. A higher power factor value generally indicates a more efficient electrical distribution system. Electrical power (Apparent power) consists of Active power (the part that actually does the work) and Reactive power (the part that develops and maintains magnetic fields required by windings in inductive loads). The current transformer measures the power consumption. The power factor regulator switches on or off the capacitor steps depending on the system reactive power requirements at any one time until the desired Power Factor is achieved. The NHP Power Factor correction systems are delivered fully assembled and are factory tested in accordance with NHP quality procedures. The Power Factor of a load is defined as the ratio of active power to apparent power, i.e. kW / kVA. The closer the Power Factor is to unity, the less reactive power is drawn from the supply. Improved power factor results in greater electrical efficiency, which in turn means less electrical generating capacity and smaller transformers, bus bars, cables and other distribution system devices that are required to be installed. Therefore, the cost of electricity is reduced and the savings are passed onto the consumers. Any installation or commissioning difficulties or comments can be forwarded to the NHP Power Quality Department. Due to continuous product technical development and improvement the information contained in this document is subject to change without notice. 12 commissioning MANUAL 2. Installation Installation is to be undertaken only by authorised and qualified personnel and is to comply with IEC831-1&2, AS3000 and local supply Authority Rules and Installation instructions. It is recommended that the PFC system be installed as per the diagram shown below, to ensure correct operation and maximum benefit. Additional recommendations for correct installation are also described. Warning! – To protect your new investment the PFC system will automatically turn off in the event that the ambient temperature inside the system is too high. For systems relying on the demand capacity provided by the PFC system, please make use of the provided remote fault indication terminals within the PFC system to initiate load shedding until the environment affecting the PFC system returns to acceptable levels. 2.1Location The PFC system should be installed indoors (unless specifically designed otherwise) and must be situated in well-ventilated areas where the ambient temperature does not exceed a maximum of 40° Celsius. It is recommended that the PFC system is installed as close as possible to the main switchboard electrically, but with mechanical separation. 2.2Preparation Check that the rated voltage of the PFC system is the same as that of the switchboard to which it is to be connected. All components and connections should be checked for tightness after transport and prior to installation. 2.3 Current transformer The current transformers (CT) are an important part of the installation process. The selection of the CT will depend upon site considerations including bus bar / cable size, mains load and switchboard layout. For information regarding installation and connection of the current transformer refer to Section 3. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 13 commissioning MANUAL 2.4Cable 2.6 Control wiring The selection of cables for a PFC system shall be in accordance with AS3000, AS3008 and local supply authority regulations. Consideration should be given to possible future expansion of the PFC system in terms of maximum current carrying capacity. Also refer to Appendix C. We recommend that control wiring from the current transformer for cable runs up to 10 meters be 2.5mm² cross section, flexible cable as a minimum. Increase cable diameter for longer runs. Guidelines to determine the appropriate cable size. • Maximum current rating of PFC system. • Fault rating of system. • Physical location of PFC system in relation to main switchboard. Cables should be over rated 1.35 times the nominal capacitor current of the total PFC system as per AS/NZS 3000:2007 Section 4.15.2.3 Current-carrying capacity of supply conductors. Therefore the cable current carrying capacity can be calculated by current per capacitor step x number of steps x 1.35. Example: 300 kVAr PFC system. Number of steps = 6 x 50 kVAr. Current per 50 kVAr step = 75 A. Cable current carrying capacity = 6 x 75 x 1.35 = 608 Amps. 2.5 Power connection Using the calculated cable size, connect supply to terminals (L1, L2 and L3) in the PFC system. Ensure correct phase rotation of cables from the main switchboard to the incoming connections of PFC system. The main earth should be rated at 30 % of phase current with the maximum earthing conductor size being 120 mm. Refer to AS3000 (Table 5.1) for minimum copper earthing conductor sizes. Neutral connection is required for auxiliary supply to both BLR-CX and BLR-CM RMB regulators. 14 2.7Ventilation Extra care is required when installing PFC systems, to ensure that the capacitors are not damaged by excessive temperature rise within the enclosures. Unlike other electrical equipment, it is not possible to de rate the capacitors when high internal temperatures are encountered. Correct installation requires that air temperature surrounding the capacitor does not exceed the specified limits. Ambient air temperatures are assumed not to exceed +40ºC, with an average over a 24-hour period not to exceed +35ºC (in accordance with AS 4388 and IEC 890). Life of the capacitors will be greatly reduced if its operating temperature exceeds 55ºC. Given the above, ambient temperatures inside the capacitor enclosure should not be greater than 10-15ºC above that of the external ambient air temperature When modules with reactors are used, fan assisted cooling is required to limit the rise in air temperature around capacitors to less than 50ºC. Without fan assistance the temperature will quickly reach levels that will damage the capacitors. A normally open thermostat (blue) set to 35º C should also be located at the top of the cubicle. If the temperature is exceeded the control circuit should be arranged to switch induced ventilation to minimise cubicle temperature. A normally closed thermostat (red) set to 50ºC should be located to sense the temperature at the top of the cubicle. If this temperature is exceeded the control circuit should be arranged to raise an alarm and shut down the PFC system. In addition to the above guidelines important installation requirements are specified in AS3000 (clause 2.4.3). commissioning MANUAL 3. Current transformer A current signal, which reflects the load, is required by the controller in order to determine power factor correction requirements. The Regulator takes a voltage reference from the white and blue phases, assuming rotation to be red–white–blue. Therefore the current transformer must be installed on the red phase. However, it may not always be possible to install the current transformer in the red phase. In these situations the voltage references must be altered to ensure a current reference from one phase and a voltage reference from the other remaining phases in the correct rotation sequence. For example if the CT is mounted on the blue phase, then voltage reference L2 on the regulator shall be red phase and L3 shall be white phase to ensure correct phase rotation (bluered-white). 3.1Specification The Current transformer (CT) should be Class 1 minimum with a 15 VA burden and 1A or 5A secondary current rating. This specification accounts for the Beluk power factor correction regulator and up to 30 metres of 2.5mm² cable. CT with smaller burdens can be used but length and size of the cable must be taken into account. 3.2 Installation The CT must be installed in a position to measure the total load current including the PFC system, a shown in figure 1 in Section 2. For centralised compensation this will normally be close to the incoming supply metering position. Ensure the current transformer is earthed, preferably at the CT secondary, at one point only. 3.3 Connection CT’s are normally marked P1/P2 and S1/S2 and should be positioned so that P1 faces the incoming supply while P2 faces the load side. Control wires from S1 should be connected to the terminal marked 18 and from S2 to terminal marked 19 in the Power Factor correction system. When the connection has been made the shorting links in the Wago terminal (orange jumper) must be removed. When a multi ratio split core CT is used connect S1 to terminal 18 and the selected appropriate ratio (S2, S3 or S4) to terminal 19. The CT should be selected as near as possible to suit the load current. When a summation CT is used the terminal markings will usually be P1, P2, P3, P4 and S1, S2. Connect S1 and S2 of first CT to P1 and P2 of the summation CT, then S1 and S2 of the second CT to P3 and P4 on the summation CT. It is important that all CT’s monitor current in the same direction. In some cases existing customer metering CT’s (e.g. from energy meters, ammeters) can be used. Connect the Power Factor controller in series with these instruments after verifying the burden of the CT and meters. Warning! Dangerous voltages can be present on CT terminals. Always disconnect load or short circuit CT terminals before changing CT polarity if required. Do NOT open CT disconnect terminal levers without inserting the orange CT shorting jumper. Failure to do so could result in permanent damage to the CT, usually associated with an audible continuous humming. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 15 commissioning MANUAL 3.4 CT Wago connection diagram 282CT2 CT test / disconnect terminal 1 2 1 2 Test plugs Switches Jumper k l Normal Operation Figure 2. CT terminal connection 16 k l Transformer Short Circuit commissioning MANUAL 4. Beluk controller 4.1 BLR-CX Series Regulator General Overview The Beluk CX series regulator incorporates an LCD panel for graphical display and four function keys to navigate the menu structure and adjust settings. Upon providing power to the regulator a 90 sec countdown begins. During the countdown the esc key can be pressed to abort the automatic setup and begin manual setup of the controller. To engage the automatic setup the user can either wait for the countdown to expire or simply press the ↵ key. The following sections provide an overview of the controller and describe required settings for basic operation. For further customization the user can consult the Beluk reference guide. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 17 commissioning MANUAL Display and Navigation The display and controls of the BLR-CX regulator are shown and explained below. Display Parameters Explained NT There are two target power factors capable of being set on the CX controller. When the secondary target power factor is active the NT light is illuminated on the display. EXPORT In conditions where the PFC unit is running in conjunction with a generator, the export light will be illuminated if active power is being exported to the grid (i.e. leading PF). If there is no generator in the circuit and the light is illuminated it is likely there is a connection problem. INFO The info menu provides information regarding each step of the PFC unit. This includes the size of the step in kVAr (only if the CT ratio is set), the size of the step as a percentage of the initial size, the number of switch cycles and the operation of the step (automatic, permanently on or off, etc). AUTO The two modes of operation for the controller are automatic or manual. In automatic mode the controller decides which steps are necessary to achieve the target power factor dependent upon the chosen switching algorithm. The Auto light is illuminated when the controller is in this mode. 18 commissioning MANUAL 4.1 BLR-CX Series Regulator cont'd MANUAL The manual mode of operation is used when the user wants direct control of which steps should be on, off, etc. The manual light is illuminated when the controller is in this mode. SETUP The setup menu has all settings that are required to configure the controller. There is an advanced menu which can only be accessed by holding the select/continue button until the 100 menu appears. In some instances a pin code may be required to access these menus. The PIN code is 242. Once entered the user can navigate to all of the other menus (200, 300, 400, 500, 600). ALARM The Alarm light flashes when an alarm has been activated. The details of the alarm will be displayed flashing beneath the reading of the power factor. To reset an alarm the user must hold the esc key for 3-5 seconds. If the reason for the alarm has not been rectified, the alarm will continue. Symbols for navigation and functions Function Move up menu structure / increase selected value Move down menu structure / decrease selected value Select/Continue ESC Step backwards P O W E R F A C T O R C O R R E C T I O N S Y S T E M 19 commissioning MANUAL 4.1.1 Familiarization with the BLR-CX Controller The top level menu structure is shown below and further elaborated on in the following pages. The and function keys can be used to scroll between these menu items and the current menu function key must item is displayed along the right hand side of the screen. To select a menu item the be pressed. To step backward in the menu structure or get back to the home screen the esc key should be pressed. Top Level Structure 1.00i 20 1.00i INFO 1.00i MANUAL 1.00i SETUP commissioning MANUAL 4.1.2 Setting up the BLR-CX Controller There are certain settings that need to be configured for basic operation of the CX controller. Upon first powering up the controller a 90 second countdown will begin. Once the countdown has completed or the user has pressed the function key the automatic initialization process will begin. The following settings will need to be configured by the user. Step 1 - Navigate to the setup menu The settings below are located in the quick setup menu of the controller. From the home screen navigate down using the function key until the setup light is illuminated on the right hand side. SETUP Press the function key to enter the setup menu. A 100 should appear on the screen. 100 Step 2 – Set the Nominal Voltage Press the function key again to enter the quick setup. The nominal voltage is indicated by Un on the display as shown below. Un 415 v SETUP function key. The value must be changed This is the L-L voltage and can be adjusted by pressing the digit by digit starting from the left. A digit can be increased by pressing the function key or decreased function key. When the correct digit has been selected, you can continue and repeat the by pressing the process by pressing the function key. Once the Nominal voltage has been set press the function key to move to the next parameter. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 21 commissioning MANUAL 4.1.2 Setting up the BLR-CX Controller Step 3 – Set the Current Transformer Ratio The current transformer ratio is indicated by Ct on the display. To adjust the CT ratio press the function key. The CT ratio is given by the primary to secondary ratio (eg.250:5 = 250/5 = 50 ratio). The value must be changed digit by digit starting from the left. A digit can be increased by pressing the function key or decreased by pressing the function key. When the correct digit has been selected, you can continue and repeat the process by pressing the function key. Press the function key twice and proceed to the next step. Ct 1 SETUP Step 4 – Run the Automatic Initialization (if necessary) The automatic initialization option is indicated by Ai on the display. If the automatic initialization process needs to be repeated press the function key, then press the function key to select yes and hit the function key to start the initialization process again. Note the process required for automatic initialization will take a minute or two of the controller switching in each of the steps. Else if Automatic Installation is not required, press the function key twice and proceed to the next step. Ai NO SETUP Step 5 – Set the Target Power Factor The target power factor is indicated as CP1 on the display. The default target power factor should be 0.96. function key. The value can be increased by pressing the To adjust the target power factor press the function key or decreased by pressing the function key. The i or c next to CP1 indicates whether the target i s inductive or capacitive. CP1i 0.96 SETUP Step 6 – Set the Step Interval Switching Time The step interval switching time is indicated by St on the display. This is the interval of time that must pass in function key. The value must between switching different steps. To adjust the switching time press the be changed digit by digit starting from the left. A digit can be increased by pressing the function key or decreased by pressing the function key. When the correct digit has been selected, you can continue and repeat the process by pressing the function key. Once complete press the function key and proceed to the next step. St 40 s 22 SETUP commissioning MANUAL Step 7 – Set Step Output type The step outputs are indicated by OUt on the display. The step output type determines how each step is controlled. Exits that have no step connected should be set to permanently off (Foff). All other steps should be left as auto for automatic control unless otherwise desired. To adjust the output type,s press the function key. The different steps can be accessed using the or function keys. To select a step press the or function keys to choose an option. Press the function key when the function key then use the desired option is highlighted, press the esc key to return to the menu. The options are: • • • • Auto – Step is controlled according to switching algorithm of regulator. Fon – Step is permanently switched on. Foff – Step is permanently switched off. Al – If temperature limit 1 is exceeded the step is switched as fan output. Once the desired option has been highlighted press the function key to accept the change. When all steps are configured press the ESC button until back at the home screen. OUt SETUP Step 8 – Set discharge time for Steps and function keys. Once the setup menu Navigate to the setup menu from the main screen using the light is showing on the right hand side, hold the function key (this accesses the advanced menus) until 100 appears on the screen as seen below 100 SETUP To navigate to the capacitor step setup menu press the below. If a PIN code is required enter ‘242’. 400 Press the function key until the 400 menu is displayed as seen SETUP function key to select the menu and the capacitor discharge time will be displayed as seen below. 401 75 s SETUP function key again on 401 to adjust the discharge time for the capacitors. This should be set to Press the at least 75seconds. The value must be changed digit by digit starting from the left. A digit can be increased by pressing the function key or decreased by pressing the function key. When the correct digit has been selected, you can continue and repeat the process by pressing the function key. For other specific settings that can be configured refer to the Advanced Settings section which contains the full menu structure. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 23 commissioning MANUAL 4.1.3 Menu Structures Info menu The info menu is not used for configuration but rather to display information relevant to each step of the system. For each connected step the information menu gives the original step size in kVAr, the current step size as a percentage of the original step size, the number of switching cycles undertaken by that step and the step’s mode of operation. All steps are shown in the information menu. 1.00i INFO - Step Information Menu INFO CC 50 k var 1 2 3 4 5 6 1 2 3 4 5 6 100 % 1 2 3 4 5 6 OC 1 2 3 4 5 6 Auto 1 2 3 4 5 6 INFO 1 2 3 4 5 6 CC 25 k var 1 2 3 4 5 6 100 % 1 2 3 4 5 6 OC 1 2 3 4 5 6 Auto 1 2 3 4 5 6 24 commissioning MANUAL Info menu – Step 1 function key. When the INFO light To navigate to the INFO menu, start at the home screen and press the function key. All of the available steps will be is illuminated on the right hand side of the display, press the displayed along the bottom of the screen with the selected step flashing. In this case it will be the 1st step. INFO 1 2 3 4 5 6 Step 2 and function keys can be used to navigate through the steps. Navigate to the 3rd step and press The the function key when the 3 is flashing. This will display the original step size of the 3rd step as seen similar to below. CC 50 k var INFO 1 2 3 4 5 6 Step 3 To navigate through the step information use the and function keys. The second screen displays a value indicating the current size of the step as a percentage of the original size. The third screen displays OC and a value that corresponds to the number of switch cycles completed by the selected step. The last screen displays the mode of operation of the step. 100 % INFO 1 2 3 4 5 6 Percentage of original step size remaining OC 2 INFO 1 2 3 4 5 6 Number of Switch Cycles Completed Auto INFO 1 2 3 4 5 6 Mode of Operation Step 4 To step backwards press the esc key and the other steps can then be navigated to using the function keys. Press the esc key again to return to the home screen. and P O W E R F A C T O R C O R R E C T I O N S Y S T E M 25 commissioning MANUAL 4.1.3 Menu Structures cont'd Manual menu The manual menu can be used to manually turn off and on any of the available steps. 1.00i MANUAL 1.00i MANUAL - MANUAL OPERATION Menu 1.00i 1 MANUAL 1.00i MANUAL 2 26 1.00i 3 MANUAL 1.00i 4 MANUAL 1.00i 5 MANUAL 1.00i 6 MANUAL commissioning MANUAL Manual menu – Step 1 From the home screen scroll down to the manual menu using the function key. Once the manual light is illuminated on the right hand side of the screen (as pictured right) press and hold the function key to enter the manual menu. 1.00i MANUAL Step 2 The first step is displayed in the centre of the screen indicating the current step (as pictured right). Use the and function keys to navigate to the step you would like to turn on or off. The step can be turned on or off (dependent on its current state) by pressing the function key. 1.00i 1 MANUAL Step 3 function key. To turn on the first step (assuming it is off) press the The first step will now be highlighted at the bottom of the screen as shown right. 1 1.00i 1 MANUAL Step 4 function key again and the first step will no To turn off the step press the longer be highlighted at the bottom of the screen. Note that the step cannot be switched back on until the specified discharge time has elapsed. 1.00i 1 MANUAL Step 5 To move back to the home screen press the esc function key twice. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 27 commissioning MANUAL 4.1.3 Menu Structures cont'd Measurement Menu – Navigation This menu of the controller is for displaying key measurements and is not configurable. The measurement menu is accessed from the home screen. The home screen is identified by when the right hand menu column is blank as indicated in the diagram below. All of the available measurement displays are shown. Those highlighted in grey are not shown in the menu unless the CT ratio has been configured in the setup menu. Measurement Menu 1.00i 1.00i Voltage L-L Odd single harmonics Voltage L-N 3 digit PF Current in measured phase Power factor ratio P/S Active 3 phase power Average PF Reactive 3 phase power Frequency Control deviation in kvar Temperature Apparent 3 phase power Highest measured Temperature Total harmonic Distortion Counter operation Hours Step 1 To navigate to the Measurement menu, start at the home screen or press the ESC key until the right hand column of menus is blank as indicated above. Once at this screen press the function key. Step 2 Navigate through the available options using the To Step back to the home screen press the esc key. 28 and function keys. commissioning MANUAL 4.1.4 Setting phase compensation for different connections In a situation where the connection of the CT or phases can’t be altered to suit the default connection described in the manual, the regulator can be set to compensate for any connection sequence. The following table describes the required compensation angle for any given connection Voltage L1-N L2-N L3-N L1-N L2-N L3-N L1-N L2-N L3-N CT L1 L2 L3 L2 L3 L1 L3 L1 L2 Phase-angle 0⁰ 0⁰ 0⁰ 240⁰ 240⁰ 240⁰ 120⁰ 120⁰ 120⁰ Voltage L2-L3 L3-L1 L1-L2 L2-L3 L3-L1 L1-L2 L2-L3 L3-L1 L1-L2 CT L1 L2 L3 L2 L3 L1 L3 L1 L2 Phase-angle 90⁰ 90⁰ 90⁰ 330⁰ 330⁰ 330⁰ 210⁰ 210⁰ 210⁰ The compensation angle can be set in the measurement 200 menu. Step 1 The user must navigate to the setup menu from the main screen using the and function keys. 1.00i SETUP Once the setup menu light is showing on the right hand side, the user must hold the appears on the screen. function key until 100 100 SETUP To navigate to the measurement setup menu press the function key. If a PIN code is required enter ‘242’. function key and select the 200 menu using the Step 2 The user can scroll down to menu item 206 using the key. 206 0 s function key and then select using the function SETUP or function keys to decrease or increase The compensation angle can then be adjusted using either the the compensation angle in 15⁰ increments according to the connection as shown above. Once the correct angle has been specified, it can be saved using the function key. To navigate back to the home scren, press the esc key. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 29 commissioning MANUAL 4.1.5BLR-CX-Schematic 30 commissioning MANUAL 4.1.6 BLR-CX Regulator Alarm Codes Fault Display Cause Remedial Actions Over or Under Voltage Check nominal voltage and set tolerances and adjust if necessary Measured current may be too small. Check CT connection. Ensure shorting link has been removed from the CT Measured Current is higher than tolerance. Check secondary output of CT. Change CT if necessary. Permanent Over Compensation Check if a step may be set as Fon (permanently on) or if a contact may have welded Permanent Under Compensation Check Capacitors and fuses and see if all steps are coming in. Step switching tolerance may need to be adjusted. THVD Outside of Defined Limits Check Limits. If THVD is > 7 % specific harmonic mitigation is necessary. Three unsuccessful switches (not affecting PF) Check output of controller step, fuses and contactor. A faulty step has been detected A step has fallen below 70 % of its initial power (kVAr value) Temperature 2 limit exceeded Check ventilation and thermostats. Operating Hours Limit Exceeded Schedule maintenance and reset operation hours. Operation Cycle Limit Exceeded Schedule maintenance and reset operation cycles Problem determining step sizes Check connections to controller for correct phases Export light is displayed If a generator is not in circuit, voltage and current measurement may be on the wrong phases Check which phase CT is connected to. If necessary apply phase compensation as per steps listed previously. Incorrect display of current or voltage Incorrect Transformer Ratio Check the CT ratio or VT ratio as set in the 100 menu P O W E R F A C T O R C O R R E C T I O N S Y S T E M 31 commissioning MANUAL 4.1.6 BLR-CX Regulator Alarm Codes cont'd Fault Display Cause Remedial Actions No display Auxiliary voltage missing Check correct connection of auxiliary voltage, if necessary rectify Display “U<>LIMIT” Measurement voltage out of range Wrong settings for voltage measurement Check correct connection of measurement voltage, if necessary rectify Check settings in menu “SETUP / MEASUREMENT”, if necessary rectify Display “I<LIMIT” Measurement current too small Check connection of CT, a probable break in the line CT ratio too high, if necessary replace CT Remove short circuit link of the CT Wrong display of current or voltage Wrong transformer ratio Check settings PT- or CT-ratio in menu “SETUP / MEASUREMENT”, if necessary Wrong power factor is displayed Wrong settings at the regulator Check settings “NOMINAL VOLTAGE” and “CONNECTION” in menu “EXTENDED”, if necessary rectify Power factor doesn’t change after switching on a step, step is switched off again CT mounted in wrong position Check mounting position referring to circuit diagram (current of load and capacitors have to be measured), if necessary rectify Alarm “overcurrent” Current higher than allowed Check CT ratio, probably replace by suitable transformer type Alarm “Control” Permanent overcompensation Permanent Under compensation Check settings Check contactors, probably contactors stick together Check settings Check capacitors, probably fuse defective Check dimensioning of the compensation unit Reversed Control Mode Current or voltage clamps interchanged Correct connection or adapt phase compensation Single steps are not switched on or off Wrong settings Check, if referring steps are defined as fix steps (permanently on or off) Steps are detected as defective Step defective Check capacitor steps, probably fuse, capacitor or contactor defective Steps are not switched on Step size too large Necessary reactive power smaller than switching threshold of step size of the smallest step Regulator still doesn’t work properly 32 Contact NHP Power Quality Department commissioning MANUAL 4.2 BLR-CM Series Regulator The Beluk Regulator requires correct phase rotation. Typically The CT should be mounted on the red phase and the secondary’s connected to the terminals inside the PFC system. Typically S1 of the CT will connect to terminal 18 and S2 will connect to terminal 19 in the PFC unit. The white phase and blue phase voltage references are connected internally. Once the connections to the power factor correction unit have been confirmed and all pre commissioning checks carried out then the current transformer shorting link can be taken out and the power factor correction system switched on. The Beluk regulator incorporates a combination of a graphical LCD display and 4 function keys. The function keys can double for navigation of the menu and inputting the settings. Where the graphic LCD screen presents a symbol above the function key then the symbol will indicate what the function key will do. Arrows generally represent navigation and the + and – symbols represent data input. The following describes a basic setup that will allow the regulator to operate without causing needless alarms. If the user wishes to further customise the settings then they may do so by referring to Beluk’s reference guide. The reference guide covers all of the regulators functions which include alarms for various out of limit conditions. Figure 6. BLR-CM Controller If the connection of the phases and the CT are not correct then refer to “Setting up the Beluk Regulator to compensate for different connections” Section 4.2.8. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 33 commissioning MANUAL The BLRCM advanced regulator is supplied pre programmed and factory tested. The display and controls are shown below. Display of inductive (i) or capacitive (c) load Display of current COS Φ Capacitor step in use Top display area for information and measurement values Regulator status " " shows regulator functioning normally. " " shows regulator is missing vital data Capacitor step available Capacitor step “SWITCHED OFF”. No step attached to relay output Digital Output status. = Active Regulator step “FIXED OFF”. Faulty step or discharge time of capacitor Alarm relay status. Symbols for navigation and functions Digital input status = Active Function keys Figure 7. BLR-CM Controller LCD Screen Table 1. Key for BLR-CM navigation Symbols for navigation and functions Function Go to submenu or scroll to enter a value Leave submenu Scroll up or down in menus Cursor Increase or decrease selected parameter Confirmation or storage of values Scrolls between options 34 = Inactive = Active = Inactive = Inactive commissioning MANUAL 4.2.1 Getting familiar with the BLR CM Controller The list below (figure 8 (a)) contains all the sub menu options accessible from the main screen of the controller. Figure 8(b) shows the main menu as displayed on the controller screen. To access any of the sub menu options listed in figure 8(a) we need to scroll down by pressing the function key. Required sub menus utilised in the commissioning process is shown on the following page. If the wrong function key is pressed and the user is unable to navigate the controller appropriately, please return to the main screen by pressing the leave until you reach the “Main submenu function key Menu” screen. From the “Main Menu” the process can begin again. Helpful Tips: • To enter the right sub menu from the “Main Menu”, the cursor MUST be pointing to the required option. • For example, the cursor in figure 8(a) is pointing to the “SETUP” option and figure 8(b) shows the cursor pointing to “MEAS. VALUES”. To enter the “SETUP” sub menu simply press the function key corresponding to and proceed into the “SETUP” sub menu. To exit from the sub menu function key until the Main simply press the Menu is reached , which is evident when the is no longer displayed as an option. • Refer to Table 2 for navigation symbols and functions. • Refer to the pathways outlined on the following page for reference whilst navigating through the controller. MEAS. VALUES HARMONICS STEPINFO > SETUP < DEVICE INFO The following pages of the BLR CM section contains instructions on the key settings required to be inputted. (a) (b) Figure 8. BLR-CM Controller LCD Screen P O W E R F A C T O R C O R R E C T I O N S Y S T E M 35 commissioning MANUAL MEAS. VALUES HARMONICS STEPINFO SETUP DEVICE INFO SETUP MENU PASSWORD 2402 MAIN MENU MEASUREMENT MENU MEASUREMENT CT FACTOR STEP VT FACTOR CONTROL NOMINAL VOLT. MEASUREMENT DISPLAY ALARM MANUAL MODBUS RESET CONFIGURATION CONNECTION MEASUREMENT EXTENDED STEP MENU DISCHARGE TIME STEP TYPE RESET Q (VALUES) Navigating through the blr-cm rmb controller • The pathways and highlighted menu options indicated on this page highlight the settings related to setting up the Beluk-CM RMB controller for operation. • All sub menu options required for input of settings is accessible via the “SETUP” sub menu. To access this sub menu we are required to enter a password. The default password is “2402”. • The key sub menu options within the “SETUP” sub menu include “MEASUREMENT”, “STEP”, “CONTROL” and “ALARM”. • Within the “MEASUREMENT” sub menu the input settings of the CT, VT, nominal voltage, and connection settings are required to configured appropriately. • As with the “STEP” sub menu, the input settings of the discharge time and step type are required to configured appropriately. • The “CONTROL” sub menu requires the COS PHI I (target PF) as well as switch interval time to be inputted as required and the alarm menu, although not always necessary, can be configured as desired. • The user can move back and forth between the sub menus highlighted on this page by using the appropriate function keys. If necessary, the use can navigate to the “MAIN MENU” screen and begin again. 36 CONTROL MENU COS PHI I COS PHI 2 SWITCH INTERVAL SWITCH INTERVAL STEP EXCHANGE EXTENDED ALARM MENU CONTROL ALARM NO CURRENT STE FAULT STEP WARNING POWER FACTOR HARMONICS U HARMONICS I OVERLOAD P OVERLOAD Q P-EXPORT TEMP1 TEMP2 DI INPUT commissioning MANUAL 4.2.2 Setting up the Beluk Regulator to measure voltage and current Step 1 – Navigate and proceed through the “SETUP” sub menu • From the “Main Menu” (see figure 9(a)) press the function key correlating to the symbol to scroll down to “SETUP” (see figure 9 (b)). • Now press the function key with the symbol and this will bring up the password screen as shown in figure 9(c). Step 2 – Enter Password • The default password “2402” needs to be entered. • To do this, a cursor digit. will appear under the first • Press the function keys with the enter the first digit. • Then press the the next digit. and the to once to advance the cursor to • Use the function keys with the enter the second digit. and the to • Repeat this process to input the final two digits (see figure 10 (a)). • This password can be changed by referring to the Beluk Reference guide. (a) • Once the password has been entered then press the key and this will bring up the password protected menu as shown in figure 10(b). (b) (a) (c) Figure 9. Navigating through to the “SETUP” sub menu (b) Figure 10. (a) Password screen (b) Display screen shown when password entered correctly P O W E R F A C T O R C O R R E C T I O N S Y S T E M 37 commissioning MANUAL 4.2.2 Setting up the Beluk Regulator to measure voltage and current cont'd Step 3 – Enter CT Value NAVIGATION: SETUP PASSWORD MEASUREMENT: CT FACTOR • Note that the cursor is now pointing to “MEASUREMENT” as shown in figure 10(b). • Now press the function key corresponding to the arrow to bring up the first of the data input screens (see figure 11 (a). This screen allows the current transformer (CT) ratio to be inputted. • Then press the arrow which brings up the input screen as shown in figure 11(b). (a) • As with entering the password the CT FACTOR screen displays a cursor under the digit and the and minus plus sign above the middle two keys. • The arrow advances the cursor. • The CT ratio is divided out and the result entered. For example, if a 500/5A CT is being used then we divide 500 (Primary) with 5 (secondary) which give us a result of 100. We then input “100” for the CT Factor as shown in figure 11(c). • When we get to the last digit, the arrow changes to a return symbol which when pressed will bring us back to the “CT FACTOR” menu with the new value showing. (b) (c) (d) Figure 11. Entering the CT Value 38 commissioning MANUAL Step 4 – Enter VT Value NAVIGATION: SETUP PASSWORD MEASUREMENT: VT FACTOR • Press once to take us to the VT FACTOR (Voltage Transformer). See figure 12. • The same process used in step 3 above (inputting the current transformer value) can be followed to enter the Voltage Transformer (VT) ratio. • If there are no Voltage Transformers then this setting should be left on one. Figure 12. VT ratio display screen Step 5 – Enter Nominal Voltage NAVIGATION: SETUP PASSWORD MEASUREMENT: NOMINAL VOLT • Once the VT FACTOR has been entered then press to bring up the nominal voltage value. The minimum and maximum voltage limits are taken from this value. • To input the nominal voltage press and enter the values by following the cursor and using the , as in previous steps. This is and typically set to what the voltage of the system is. For example, 400 V AC or 415 V AC. Figure 13. Nominal Voltage screen display • As with entering the CT ratio, when the last digit is reached the return symbol is displayed and when pressed will take us back to the nominal voltage screen as displayed in figure 13. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 39 commissioning MANUAL 4.2.2 Setting up the Beluk Regulator to measure voltage and current cont'd Step 6 – Setting the Line Connection NAVIGATION: SETUP PASSWORD MEASUREMENT: CONNECTION • To select how the measuring lines are connected press and the Measurement option will be highlighted as shown in figure 14. • Typically these are set to U=L-L because the measuring lines are internally connected within the PFC system and should not require modification. • This setting can be set to either L-L to L-N by pressing the key function as shown in figure 14. (a) (b) Figure 14. Setting the Line Connection. (a) L- L (b) L- N 40 commissioning MANUAL 4.2.3 Setting up the Beluk Regulator’s capacitor steps Step 1 – Setting the discharge time for each step NAVIGATION: SETUP PASSWORD STEP: DISCHARGE TIME • Enter “STEP” sub menu. • The Step Discharge time screen, as shown in figure 15, is the first in this submenu. The discharge time locks the capacitor out for the time that is inputted once it has been switched out by the regulator. This allows the capacitor time to discharge below 10% before being available to be switched back in again. The discharge time must be set for each capacitor step. Figure 15. Setting the discharge time for step 01 • The discharge time should be set to 70 seconds or more. • Press the to access the input field. • As previously done when entering the CT ratio, follow the cursor and use the , . and • As before, when the last digit is reached the return symbol is displayed and when pressed will take us back to the discharge time sub menu for the 1st step. • Pressing the sign increments to the next step and the process can be repeated for each step. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 41 commissioning MANUAL 4.2.3 Setting up the Beluk Regulator’s capacitor steps cont'd Step 2 – Updating status of steps NAVIGATION: SETUP PASSWORD STEP: STEP TYPE • Scroll to and enter STEP TYPE sub menu. All steps that are not switching capacitor steps need to be switched to the “Off” position. This will stop the Beluk controller from testing these unused steps and causing nuisance alarms. • To update the steps required to be selected as “OFF”, press the “ ” function key to cycle through to the first required step. (a) (Figure 16(a) shows step 12 has been selected and its status is “NORMAL”). • To change the status to “OFF” press a few times to scroll through a few options starting from “NORMAL” then “FIX-OFF” followed by “FIX-ON” and then once more, leaving the display indicating “OFF”. 42 Figure 16(b) shows the status of step 12 as being “OFF” for example. (b) • Cycle through to the next required step and repeat the process. Figure 16. Updating the status of relevant steps commissioning MANUAL 4.2.4 Setting up target power factor NAVIGATION: SETUP PASSWORD CONTROL: COS PHI 1 • Enter “CONTROL” sub menu. The screen display should now resemble figure 17. • Press to enter COS PHI 1. • Follow the same method used when entering the CT ratio. Note, when we get to the last digit, which when changes to the return symbol pressed will bring us back to the “COS PHI 1” menu with the new value showing. Figure 17. First “CONTROL” sub menu screen 4.2.5 Setting up switch interval time between steps NAVIGATION: SETUP PASSWORD CONTROL: SWITCH INTERVAL • Scroll to the “SWITCH INTERVAL” display screen (see figure 18). • Press the field. function key to bring up the input • The values are entered by following the cursor and using the , . and • As with entering the CT ratio, when the last digit is reached the return symbol is displayed and when pressed will take us back to the switch interval screen as displayed in figure 18. Figure 18. Setting switch interval time Additional note: Typically the switch time will be set for 40 seconds when the unit is tested at NHP’s premises. Shorter switching times will capture load variations more accurately but will switch the contactors more frequently. A longer switching time will help preserve the life of the contactors by minimising rapid compensation to short term load variation. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 43 commissioning MANUAL 4.2.6 Commencement of power factor regulation After making the above settings then the Beluk regulator will check the measuring lines and current transformer. (Voltage at UM1 and UM2 for nominal voltage and rotation of phases and what is measured from the current transformer.) Once the regulator has checked the voltage and current then the “smiley” face will appear and the regulator will switch steps in and out according to the variation of the load – see figure 19. Figure 19. Commencement of PF Regulation. 4.2.7 Connection issues If the following screen shown in figure 20 appears for longer than 5 seconds then it means that the voltage is out of tolerance. Go back to Section 4.2.2 - Setting up the Beluk Regulator to measure voltage and current and check that the inputted values match what the unit is connected to. Also check the voltage is within tolerance. Figure 20. Voltage out of toleration If the following screen shown in figure 21 appears for longer than 5 seconds then it means that the current is out of tolerance. Go back to Section 4.2.2 - Setting up the Beluk Regulator to measure voltage and current and check that the inputted values match what the regulator is connected to. Also check that CT shorting links have been removed. Figure 21. Current out of toleration 44 commissioning MANUAL 4.2.8 Setting up the Beluk Regulator to compensate for different connections If there is a situation where the connection of the CT or phases can’t be altered and are different from the connection diagram shown in figure 2 and figure 27, then the Beluk regulator can be set up to compensate for any connection sequence. PHASE COMP. allows the phase rotation to be corrected at the regulator. For example, if the connection to the PFC system had the CT on the line 2 (White Phase) then by looking at table 2 we can see that the phase compensation will have to be set to 240+90° because we know that the PFC system already has the measuring lines connected to line 2 and line 3 inside the PFC system. Table 2. Phase compensation depending on voltage and CT location Voltage Connection (UM1 – UM2) L2 – L3 L3 – L1 L1-L2 L2-L3 L3 – L1 L1 – L2 L2 – L3 L3 – L1 L1 – L2 Reversed CT Location of CT L1 L2 L3 L2 L3 L1 L3 L1 L2 Any *Phase offset 0° + 90° 0° + 90° 0° + 90° 240° + 90° 240° + 90° 240° + 90° 120° + 90° 120° + 90° 120° + 90° 180° + 90° Step 1 – Navigating through to the “PHASE COMP” screen NAVIGATION: SETUP PASSWORD measurement extended • Enter the MEASUREMENT sub menu (i.e. indicated pathway above or see section 4.2.2 for more detail). • Now scroll through the “MEASUREMENT” sub menu options and enter the “EXTENDED” sub menu option. The SYNCHRONISATION FREQUENCY AUTOMATIC screen is displayed as shown in figure 22(a). • Press once to bring up the “PHASE COMP” screen as shown in figure 22 (b). (a) (b) (c) Figure 22. Setting to compensate for different connections. Step 2 – Changing the “PHASE COMP” NAVIGATION: SETUP PASSWORD measurement EXTENDED: PHASE COMP • Normally this field will be set on 000°+90°. • Push the function key until the compensation is set to required phase offset as indicated by table 3 (Figure 22(c) is an example where the phase offset was altered to “240+90°”.) P O W E R F A C T O R C O R R E C T I O N S Y S T E M 45 commissioning MANUAL 4.2.9 Alarm settings Table 3 below describes the alarms featured on the BLR CM controller. Table 4 on the following page details the settings that the PFC unit will be set to at time of factory testing. The alarms that are preset are for a basic installation. The flexibility and programmability of the alarms is very extensive and utilising the reference guide the user can program the alarm outputs to suit most site requirements. Table 3. BLR-CM alarm descriptions and associated limits 46 Alarm trigger limits Control Alarm Not achieving power factor after 50 times switching time - No Current Not being able to measure current - Step Fault Step size detection not recognised - Step Warning A) Step size falls below an adjustable percentage range B) Step switching have exceed adjustable limit A) 15-80 % B) 1 - 9999999 Power Factor COS PHI is outside of adjustable range MIN: c0.80 – i0.91 MAX: i0.80 – c0.91 ∆T: 1 -36000 s Harmonics U THD adjustable Voltage limits has been exceeded 1 – 99.9 % Harmonics I THD adjustable Current limits has been exceeded 1 – 99.9 % Overload P Amount of P exceed the adjustable 1 – 99999.9 kW Overload Q Amount of Q exceed the adjustable 1 – 99.9 kVAr P-export Alarm will be triggered as soon as P-Export is recognised - Temp1/Temp2 Ambient temperature has exceeded the limits Temp 1: 20 – 68 °C ∆T – 0.5 – 9.9 Temp 2: 27 – 70 °C ∆T – 0.5 – 9.9 DI (Digital Input) Voltage received at the digital input - Over Current When Current exceeds the measuring range of the regulator Cannot deactivate this alarm. Alarm not shown in ALARM sub menu. - Over/Under Voltage When Voltage exceeds the adjustable limit Cannot deactivate this alarm. Alarm not shown in ALARM sub menu. Alarm settings are adjustable in Extended menu under the MEASUREMENT sub menu. MIN: - 2 – 90% MAX: +2 – 30% commissioning MANUAL Alarm Events M-Relays The M-Relay is a volt free output and can be used as a N0 / NC contact. Max fuse 6A, breaking capacity 250V AC / 5A. Digital out The digital output is a volt free output. Is only a NO contact max. fuse 6A, breaking capacity 250V AC / 5A. Display Shows Alarm on display. Figure 23. Alarm options as shown on the BLR CM display Control sleep All steps are put on hold, control is stopped. Control halt All steps are switched off, control is stopped. Cos phi 2 Switch to second target COS PHI. This is a brief attempt at explaining how the alarm menu is navigated and the various alarms can be either enabled or disabled. It also attempts to address how certain functions can be selected to operate under certain alarm conditions. Each alarm can be enabled or disabled and alarm actions such as the M relay or D – display can be assigned to chosen alarms. As featured on the previous page, a list of alarms featured in the “ALARM” sub menu on the BLR CM controller include: • Control Alarm • No current • Step Fault • Step Warning • Power Factor • Harmonics U • Harmonics I • Overload P • Overload Q • P-Export • TEMP1 • TEMP2 • DI Input P O W E R F A C T O R C O R R E C T I O N S Y S T E M 47 commissioning MANUAL 4.2.9 Alarm settings cont'd Step 1 – Disabling / Enabling the “CONTROL ALARM”. NAVIGATION: SETUP PASSWORD ALARM: CONTROL ALARM • First, from the main menu we need to navigate until the “SETUP” sub menu option is highlighted and press to enter. • As before we must then enter the password. (For more detail see Section 4.2.2). • Press until the “ALARM” sub menu is highlighted (see figure 24 (a)) and press menu. See figure 24(b). to enter into the sub • Now we should see “CONTROL ALARM” on the display with either nothing written below or alarm function(s) already configured. This is evident if “=>M D” etc. is displayed (figure 24 (b) shows no functions have been selected). • If we press the • Pressing (a) symbol then the alarm will be disabled as shown in figure 24(c). again will enable the alarm though no functions have been selected. (b) Figure 24. Disabling / Enabling the “CONTROL ALARM.” 48 (c) commissioning MANUAL Step 2 – Assigning the M relay to the “CONTROL ALARM” NAVIGATION: SETUP • Now press • Then press PASSWORD to move the ALARM: CONTROL ALARM / M RELAY symbol in front of the symbol as shown in figure 25 (a) and (b). to scroll through the alarm actions that can be assigned to the control alarm. • The operation of the M relay can be selected by pressing “NO” to a “YES” (see figure 25 (c) and (d)). which will confirm the selection by changing • If the Beluk regulator goes into CONTROL alarm because the target power factor is not reached then the M relay will operate. (a) (b) (c) (d) Figure 25. Assigning the M relay to operate when the “CONTROL ALARM” is triggered. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 49 commissioning MANUAL Step 3 – Further alarm actions NAVIGATION: SETUP PASSWORD ALARM: CONTROL ALARM / [alarm actions] to scroll to the next alarm action. • Use the • In figure 26 (a), if we decide that we don’t want the “DO” or Digital Output to operate when the control alarm to scroll past it. activates then press • Figure 26 (b) shows that when the control alarm is activated the message is not outputted onto the controllers display. and this option is now enabled as shown in figure 26 (c). • To enable this feature press and make selections to suit (see figure • We can scroll through the rest of the alarm actions by pressing 26(d)-(f)). • Figure 26 (g) shows two alarm functions that we have selected, which are the M relay and a message on the graphical display. we can move the symbol to point at “CONTROL ALARM” as shown in figure 26 (h). • Using the . • We can now scroll through to the next alarm type by pressing • The same process as above can now be repeated for the rest of the alarm types. will exit the “ALARM” sub menu. • Pressing (a) (b) (c) (d) (e) (f) Figure 26. Alarm Settings (g) 50 (h) commissioning MANUAL BLR-CM regulator alarm codes Fault Display Cause Remedial Actions No display Auxiliary voltage missing Check correct connection of auxiliary voltage, if necessary rectify Display “U<>LIMIT” Measurement voltage out of range Wrong settings for voltage measurement Check correct connection of measurement voltage, if necessary rectify Check settings in menu “SETUP / MEASUREMENT”, if necessary rectify Display “I<LIMIT” Measurement current too small Check connection of CT, a probable break in the line CT ratio too high, if necessary replace CT Remove short circuit link of the CT Wrong display of current or voltage Wrong transformer ratio Check settings PT- or CT-ratio in menu “SETUP / MEASUREMENT”, if necessary Wrong power factor is displayed Wrong settings at the regulator Check settings “NOMINAL VOLTAGE” and “CONNECTION” in menu “EXTENDED”, if necessary rectify Power factor doesn’t change after switching on a step, step is switched off again CT mounted in wrong position Check mounting position referring to circuit diagram (current of load and capacitors have to be measured), if necessary rectify Alarm “overcurrent” Current higher than allowed Check CT ratio, probably replace by suitable transformer type Alarm “Control” Permanent overcompensation Permanent Under compensation Check settings Check contactors, probably contactors stick together Check settings Check capacitors, probably fuse defective Check dimensioning of the compensation unit Reversed Control Mode Current or voltage clamps interchanged Correct connection or adapt phase compensation Single steps are not switched on or off Wrong settings Check, if referring steps are defined as fix steps (permanently on or off) Steps are detected as defective Step defective Check capacitor steps, probably fuse, capacitor or contactor defective Steps are not switched on Step size too large Necessary reactive power smaller than switching threshold of step size of the smallest step Regulator still doesn’t work properly Contact NHP Power Quality Department P O W E R F A C T O R C O R R E C T I O N S Y S T E M 51 commissioning MANUAL 4.2.10 BLR-CM schematic Figure 27. BLR-CM Circuit Connections Line – Line Connection 4.3 Parallel controller set-up When commissioning larger PFC systems it is often necessary to connect two regulators to control the required number of steps. When two regulators are utilised on one system the following steps should be taken. 1) Verify the burden of the CT will support two regulators and the associated cable length 2) Connect the CT in series through both controllers. (i.e. CT terminal S1 to Regulator 1 terminal l, regulator 1 terminal k to regulator 2 terminal l, regulator 2 terminal k to CT terminal S2). 3) Set regulator time delay’s to 5 seconds apart. I.e. regulator No.1 40 seconds, regulator No.2 45 seconds. The above procedure should also be used when setting up two individual PFC systems at the same switchboard. By setting the regulator time delay 5 seconds apart the two systems will automatically share the compensation duty. This procedure will be effective if both regulators are of Beluk manufacture. The technology of other regulators may not allow this type of duty sharing. 52 commissioning MANUAL 5. Power factor correction system fault finding General 1. System will not energise If System is energised and regulator has Blank display. • Ensure that normally closed thermostat (red) is set correctly. Refer to section 2.7 for correct settings. • Ensure that CT has been installed correctly. Refer section 3.0 and as per attached diagram. • Ensure all control fuses are installed. 2. Indication of capacitive load on regulator Indication of capacitive load (e.g. c 0.94) on digital display. • Ensure that CT polarity is correct. Refer to section 3.3 for correct connection. • Ensure that CT has been installed correctly. Refer section 3.0 and as per attached diagram. • Ensure CT wiring has been installed to correct terminals. 3. Incorrect operation Switching additional capacity and PF (cos φ) decreases. • Ensure correct phase rotation throughout PFC system. Refer section 2.5. • Ensure that CT has been installed correctly. Refer section 3.0 and as per attached diagram 4. No change in PF If regulator switches steps on and off rapidly in 3 successive attempts, with no change in power factor: • Ensure all fuse disconnector on functional trays are fully closed. • Check fuses in fuse disconnector for continuity 5. Regulator will not turn on any steps • Ensure none of the steps contactors are welded in • Ensure there is sufficient inductive load for compensation • Re-evaluate functional tray step kVAr sizing, may require smaller kVAr step increments to achieve PF target. For example, 2 x 25 kVAr instead of 1 x 50 kVAr. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 53 m ai n t e n a n c e r e c o r d m ai n t e n a n c e r e c o r d Maintenance of NHP PFC systems All electrical equipment requires maintenance of some sort. PFC equipment is no different. In fact, because capacitors are consumable devices and they have no moving parts, it is difficult to tell whether a capacitor is in need of replacement without regular maintenance. The maintenance log is provided to help you periodically test your equipment and keep it in working order. The tasks outlined in the maintenance log are listed below with a brief explanation of how the maintenance should be applied. Check tightness of all electrical connections: All electrical connections should be checked and tightened after transit, and as part of a twelve monthly check. As electrical connections heat up and cool down, they expand and contract, possibly causing the connection to loosen and result in a resistive joint. Remove all dust and deposits, inside and outside: Over time dust will enter the PFC system and accumulate on surfaces, or if any work has been done on the system there may be deposits of some kind left behind. Once every twelve months vacuum the PFC system to remove all dust and deposits. Visual inspection of system: Once every twelve months inspect the PFC system, inside and outside. Things to look for are signs of capacitor case warping, tools or objects left where they shouldn’t be, any liquids that have managed to find their way inside the system, etc. Check function of fans and thermostats: Once every twelve months check that the fans and thermostats are fully operational by applying hot air from a hot air blower or hair dryer to the temperature switches. The fans should turn on at 35°C and the controller (and any active functional steps) should turn off at 50°C. Clean/replace filters: Once every three months the filters should be cleaned. If the environment is dusty, dirty or corrosive, the filters may require more frequent cleaning or replacement. Current measurements: Every six months each capacitor step should be checked. A log is provided to keep a history of how the capacitor steps are performing over time, which will help in diagnosing a problem before it becomes a hazard to your business. This check involves taking the phase voltage readings (RMS voltage), and the current readings per phase. The two indicators of a depleted capacitor are: 1. The current drawn by the capacitor is below the cutoff current as indicated by the charts shown in Appendix A and Appendix B. 2. The current drawn by the capacitor varies across the three phases. Capacitor current draw should be balanced, so if it is unbalanced the capacitor could produce isolated hot spots within the capacitor leading to possible premature depletion. 56 m ai n t e n a n c e r e c o r d General maintenance – every three months Note: The frequency of this task may need to be increased to suit individual site conditions, especially dusty or corrosive environments. Date Task Comments Initials Clean/replace filters Clean/replace filters Clean/replace filters Clean/replace filters Clean/replace filters Clean/replace filters Clean/replace filters Clean/replace filters Clean/replace filters Clean/replace filters Clean/replace filters Clean/replace filters General maintenance – Every twelve months Date Task Comments Initials Check tightness of all electrical connections Remove all dust and deposits, inside and outside Visual inspection of system Check function of fans and thermostats Check tightness of all electrical connections Remove all dust and deposits, inside and outside Visual inspection of system Check function of fans and thermostats Check tightness of all electrical connections Remove all dust and deposits, inside and outside Visual inspection of system Check function of fans and thermostats P O W E R F A C T O R C O R R E C T I O N S Y S T E M 57 m ai n t e n a n c e r e c o r d Current measurements – every six months Note: The frequency of this task may need to be increased to suit individual site conditions, especially high ambient temperatures and excessive harmonics. Step #1 Date I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials Step #2 Date Step #3 Date Step #4 Date 58 m ai n t e n a n c e r e c o r d Current measurements – every six months Note: The frequency of this task may need to be increased to suit individual site conditions, especially high ambient temperatures and excessive harmonics. Step #5 Date I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials Step #6 Date Step #7 Date Step #8 Date P O W E R F A C T O R C O R R E C T I O N S Y S T E M 59 m ai n t e n a n c e r e c o r d Current measurements – every six months Note: The frequency of this task may need to be increased to suit individual site conditions, especially high ambient temperatures and excessive harmonics. Step #9 Date I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials Step #10 Date I1 [A] Step #11 Date I1 [A] Step #12 Date 60 I1 [A] m ai n t e n a n c e r e c o r d Current measurements – every six months Note: The frequency of this task may need to be increased to suit individual site conditions, especially high ambient temperatures and excessive harmonics. Step #13 Date I1 [A] I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials I2 [A] I3 [A] UL1L2 [V] UL1L3 [V] UL2L3 [V] Comments Initials Step #14 Date I1 [A] Step #15 Date I1 [A] Step #16 Date I1 [A] P O W E R F A C T O R C O R R E C T I O N S Y S T E M 61 m ai n t e n a n c e r e c o r d PFC-P Current envelope, voltage reference at bus connection 62 m ai n t e n a n c e r e c o r d P O W E R F A C T O R C O R R E C T I O N S Y S T E M 63 m ai n t e n a n c e r e c o r d PFC-E Current envelope, voltage reference at bus connection 64 m ai n t e n a n c e r e c o r d P O W E R F A C T O R C O R R E C T I O N S Y S T E M 65 m ai n t e n a n c e r e c o r d Maintenance parts list Parts listed involve all possible items that may be required during maintenance on a NHP PFC system. General items Item Description Item no. Red LED Lamp BA9SRLA240VAC Green LED Lamp BA9SGLA240VAC Discharge Resistor 180kΩ – suited for 12.5 kVAr capacitors 27510010180 Discharge Resistor 120kΩ – suited for 25 kVAr capacitors 27510010120 6.25 kVAr capacitor 275546703803 12.5 kVAr capacitor 275176707700 25 kVAr capacitor 275398715401 50 kVAr capacitor (2 x 25 kVAr capacitors connected in parallel) 2 x 275398715401 Wall mount PFC unit specific Item Description Item no. Spare filters – for 37.5 kVAr wall mount unit only AVAFAGN15 Spare filters – for 50 kVAr to 100 kVAr wall mount units AVAFAGN25 Spare grill & filter – for 37.5 kVAr wall mount unit only GKF15 Spare grill & filter – for 50 kVAr to 100 kVAr wall mount units GKF25 Fan, grill and filter for 37.5 kVAr wall mount unit GKV2000220 Fan, grill and filter for 50 kVAr to 100 kVAr wall mount units GKV2500220 6 A 1 phase MCB - Control DTCB6106C 16 A 3 phase MCB – for 6.25 kVAr capacitor DTCB6316D 32 A 3 phase MCB – for 12.5 kVAr capacitor DTCB6332D 63 A 3 phase MCB – for 25 kVAr capacitor DTCB6363D PFC-P unit specific (previously CQ-PFC) 66 Item Description Item no. Spare filters AVAFAGN30 Spare grill & filter GKF30 Axial Fan – 3 are used in single Tier NHP PFC systems AC17320BTP Control Fuse NNS4 DIN fuse links (Wöhner DIN fuse disconnector) – 3 required per 6.25 kVar tray N0016 DIN fuse links (Wöhner DIN fuse disconnector) – 3 required per 12.5 kVar tray N0032 DIN fuse links (Wöhner DIN fuse disconnector) – 3 required per 25 kVar tray N0063 DIN fuse links (Wöhner DIN fuse disconnector) – 3 required per 50 kVar tray N00125 6.25 kVAr functional tray FTSR6CQE 12.5 kVAr functional tray FTSR12CQE 25 kVAr functional tray FTSR25CQE 50 kVAr functional tray FTSR50CQE m ai n t e n a n c e r e c o r d PFC-E unit specific Item Description Item no. Axial Fan – 3 are used in single Tier NHP PFC systems AC17320BTP Control Fuse NNS4 DIN fuse links (Wöhner DIN fuse disconnector) – 3 required per 12.5 kVar tray N0032 DIN fuse links (Wöhner DIN fuse disconnector) – 3 required per 25 kVar tray N0063 DIN fuse links (Wöhner DIN fuse disconnector) – 3 required per 50 kVar tray N00125 12.5 kVAr capacitor 275 166 707 100 25 kVAr capacitor 275 189 714 301 50 kVAr capacitor 2 x 275 189 714 301 Recommended torque settings for specific system components The table below lists the recommended torque settings for affixing PFC system components. These settings ensure that all connections are secure without damaging the nuts and bolts or the equipment itself. Item Torque Setting ( Nm ) Mounting studs of capacitor 7 Screw connections of capacitor 6.25 kVAr Capacitor 1.2 … 2.0 12.5 kVAr Capacitor 2.5 … 3.0 25 kVAr Capacitor 3.2 … 3.7 CA 7-16 1.5 … 2.5 CA 7-23 1.5 … 2.5 CA 7-37 1.5 … 3.5 CA 7-72 2…6 Contactor P O W E R F A C T O R C O R R E C T I O N S Y S T E M 67 A P P END I X NHP SERVICE PROVIDES A COMPREHENSIVE RANGE OF app e n d i x VALUE ADDED SERVICES THAT SUPPORT AND ENHANCE THE RELIABILITY AND PERFORMANCE OF NHP PRODUCTS FIELD SUPPORT SERVICES - PFC Preventative maintenance Our team Products of the power factor correction unit have a finite lifespan. In particular, capacitors and contactors require regular performance analysis to ensure correct and reliable operation. When products do fail, it can lead to costly repair or production losses. Preventative maintenance can extend the life of products and it is possible to predict and avoid failures before they occur. Our team of qualified technicians is available for a variety of lifecycle services, including power factor correction, which involves: An integral component of the power factor correction unit, capacitors require stringent operating conditions to ensure reliable operation. All components can succumb to wear and the ideal situation is to identify and replace these components before they pose a problem for your business. The service • • • • Product repairs and service On site emergency breakdown service Preventative maintenance and Commissioning Economical advantage Through regular maintenance NHP power factor correction systems will provide superior performance. In doing so, each power factor correction system will maintain its target power factor, passing on all economical benefits to the customer. WHAT NHP POWER FACTOR CORRECTION SERVICE PROVIDES: NHP power factor correction servicing involves multiple analysis and tests to certify the unit operation. Service includes: Current measurements – Capacitor depletion analysis Thermal testing – Imperative to component lifespan and function Troubleshooting – Unit functional testing Component replacement – Where required General cleaning – maintain optimal operating environment 70 HOW DO I ARRANGE A SERVICE CONTRACT? Arrangement of a servicing schedule can be organised through a NHP representative who can advise on further details. app e n d i x Appendix A: Cable requirements Copper conductor, de-rating factor 1, Unenclosed In accordance with: a) AS 3000:2007 b) AS3008.1.1:2009 – Table 8, column 9. * Allowance for overloading and cables touching, unenclosed. PFC System Rating Cable rating kVAr Nominal Amps 135% Nominal Amps Min. conductor size (mm²)b) Max. current cap. (A)b) 100 139 188 95 230 150 209 282 150 310 200 278 376 240 250 348 470 2 x 120 ) 530 300 417 563 2 x 150 620 350 487 657 2 x 185 710 400 556 751 2 x 240 850 450 626 845 2 x 240 850 500 696 939 2 3 x 185 ) 1065 550 765 1033 3 x 185 1065 600 835 1127 3 x 240 1275 650 904 1221 3 x 240 1275 700 974 1315 4 x 185 ) 1420 750 1043 1409 4 x 185 ) 1420 425 1 3 3 ) Alternative – 1 x 300 mm² cable. 1 ) Alternative – 2 x 300 mm² cables. 2 ) Alternative – 3 x 300 mm² cables. 3 NHP recommend that the cable size be determined from maximum anticipated installed capacity of the PFC system. Cable sizes are a guide only, always refer to AS/NZS3008 for specific requirements. Individual de-rating based on method of installation, cable lengths, volt drop, ambient temperature and cable configuration must be allowed for when sizing cable. P O W E R F A C T O R C O R R E C T I O N S Y S T E M 71 app e n d i x Appendix B: BLR-CX Setup Menu Advanced Setup The setup menu is broken down into 6 main groups represented by 100-600. They are described as follows. Navigate to the setup menu from the main screen using the and function keys. Once the setup menu light is showing on the right hand side, hold the function key (this accesses the advanced menus) until 100 appears on the screen. 1.00i SETUP This is the quick start menu and contains all basic parameters required to start the PFC. 100 SETUP This is the measurement settings menu and contains all basic connections settings (VT, CT, Compensation angle). 200 SETUP This is the control optimisation menu and contains settings to improve and adjust performance. 300 SETUP This is the step setup menu and allows adjustment and adaptation of the steps. 400 SETUP This is the alarms menu and contains settings to configure all alarms and monitoring capabilities. 500 SETUP This is the reset menu and allows various aspects of the regulator to be reset or everything to be reset to factory standards. 600 72 SETUP app e n d i x Appendix C: BLR-CX Expanded Setup Menu The following describes what each of the menu items are for the measurement (200), control optimization (300) and step setup (400) menu structures. Measurement (200) Menu No. Description Options 201 Nominal Voltage 100…245100V 202 Current Transformer Ratio 1…9600 203 Voltage Transformer Ratio (If not used, left at 1) 1…350 204 Voltage Tolerance (percentage of nominal voltage) This tolerance sets the limits of permissible nominal voltage before an alarm is triggered. 0…100% 205 Voltage Measurement Connection Yes – Line to Line Connection. No – Line to Neutral Connection. Yes / No 206 Phase Compensation To compensate for non standard measurement connections. 0…345 207 Auto Initialize Yes – Starts switching all steps to calibrate and compensate. for measurement connections. Voltage and current must be in acceptable limits. Yes / No 208 Auto Initialize on Startup Yes – Countdown to initialize is shown on starting the BLR-CX No – The countdown is not shown on startup. Yes / No 209 Synchronization Frequency Setting the sampling rate to match the frequency of the grid supply if auto is too unreliable. Auto / FIX50Hz / FIX60Hz 210 Temperature Offset Allows correction of temperature reading. -10ºC…10ºC P O W E R F A C T O R C O R R E C T I O N S Y S T E M 73 app e n d i x Appendix C: BLR-CX Expanded Setup Menu cont'd Control Optimization (300) Menu No. 74 Description Options 301 Control Sensitivity Sensitivity of the switching threshold. Determines when the controller will switch in a step according to percentage terms of closest step size. 55…100% 302 Cos ø 1 This is the primary power factor setting. 0.7…0.99 303 Cos ø 2 This is the secondary power factor setting which can be switched to by the digital input. 0.7…0.99 304 Cos ø 2 for P Export Yes – The controller operates with Cos ø 2 as a control target. No - The controller operates with Cos ø 1 as a control target. Yes / No 305 Switch Interval The time delay in switching steps for regulation. Long enough to build an average reactive power and prolong contactor life. 0…6500s 306 Switch Interval Step Exchange The time delay in swapping out an active step for another step to achieve a better power factor. 0…6500s 307 Activate Step Exchange Yes – Uses Combined filter control algorithm to find an optimum result with different step sizes. Yes / No 308 Step Recognition “Off” Yes – Step sizes have to be programmed by hand. No – Step sizes are corrected and detected automatically and monitored for alarms. Step sizes which are programmed manually will be overwritten. Yes / No 309 Defective Capacitor Blocking Yes – If a step is switched in three times with no measurable reaction to PF, it is blocked and no longer used by the controller. Faulty steps are tested every 24hrs or when the controller starts up. No – Steps are continued to be used even with no network reaction, causing unnecessary switching. Yes / No 310 PF Control On – Automatic Control. Off – Control Stops and active steps are disconnected successively. Hold – Control stops and active steps remain on. On / Off / Hold 311 Control Algorithm 1 - Auto – Before each switching operation all available steps are compared against the control deviation and the best selected. 2 - LIFO – The controller starts regulation by switching in step 1 and continuing with the following steps. When taking out steps it takes out the last active step switched in. 3 - Combined Filter – Special Algorithm for combined filter banks with two different detuned ratings. Working like with best fit. 4 - Progressive – The controller can switch in multiple steps within small amount of switching time if required. Step sizes must be set manually. 1/2/3/4 app e n d i x Menu No. Description Options 312 Offset Reactive Power This can be used to offset a permanent reactive load which cannot be measured (i.e. transformer). 0.0…900.0 kvar 313 Asymmetry Factor This factor is the ratio between switch interval for switching on and switching off. X = 1 = equal X = 2…127: delay switching off X = -2…-127: delay switching on Result = Switch interval multiplied by X. -127…127 314 Q Capacitive Steps Turn Off Yes – When the network condition is considered capacitive, the steps are turned off. No – The controller only considers the cos ø control target. Yes / No Step Setup (400) Menu No. Description Options 401 Discharge Time The discharge time is a blocking time for the capacitor which starts after it has been switched off. It cannot be used again until the discharge time has expired. 5…1200s 402 Step Nominal Value This allows each step size value to be manually entered in kvar. The CT factor and nominal voltage MUST be set beforehand as these values will affect capacitance step sizes. 0.0…999.9 kvar 403 Step Type Auto –Used for normal regulation Al – If temperature limit 1 is exceeded this step is switched as fan output. FOn – Step is permanently on (still monitored and shutdown in critical situations). FOff – Step is permanently off (should be used for inactive steps). Auto / Al / FOn / FOff 404 Switch Cycles Allows resetting of the switching cycles when a contactor is replaced. 0…262,000 P O W E R F A C T O R C O R R E C T I O N S Y S T E M 75 app e n d i x Appendix C: BLR-CX Expanded Setup Menu cont'd Alarm Settings (500) Menu No. 76 Description Options 501 Reset Alarm Manually YES – Have to hold esc key for 5 seconds to reset alarms NO – Once alarm condition is removed, alarm turns off. Yes / No 502 Total Harmonic Distortion Alarm YES - Exceeding threshold activates alarm. NO - Not monitored. Yes / No 503 Total Harmonic Distortion Threshold 1-200% 504 Total Harmonic Distortion > Threshold YES - Exceeding the threshold will result in successively turning off all active steps (Must have 502 as Yes) NO - No response to exceeded threshold. Yes / No 505 Trigger interval time for THD and Temp Threshold 2 The time after the threshold has been breached before triggering an alarm. 1-255 sec 506 Freeze Control if I = 0 YES – The controller is frozen when the measuring current drops below 15mA and all active steps remain on. NO – The controller turns off all active steps successively when the measuring current drops below 15mA. Yes / No 507 Service Alarm YES - Alarm occurs when max amount of step switching cycles has been exceeded or threshold for operation hours has been exceeded. NO – No alarm for exceeding step switching cycles or controller hours of operation. Yes / No 508 Max switching cycles per step Threshold for cycles per step before alarm activates. 0-262,000 509 Max operation Hours Threshold for operation hours before alarm activates. 1-65535 hrs 510 Temperature input as digital input YES – The temperature input is used as a digital input NO – The temperature input works with temperature sensor and the thresholds are set as per 513 and 514. Yes / No 511 Digital input active at high signal YES – DI is activated with closed terminals T1 & T2. NO – DI is activated with open terminals T1 & T2. Yes / No app e n d i x Menu No. Description Options 512 Temperature Alarm YES – The temperature is monitored according to the thresholds and responds accordingly. NO – No alarm for temperature. Yes / No 513 Temperature Threshold 1 When the first temperature threshold is breached, the AL step dedicated to the fan is switched on. Yes / No 514 Temperature Threshold 2 When the second temperature threshold is breached, the controller successively turns off all active steps and the visual high temp alarm is activated. Yes / No 515 Control Alarm (Target cos ø cannot be achieved) YES - Alarm is activated after 75 attempts of switching resulting in over and under compensation. NO – No monitoring for over/under compensation. Yes / No 516 Defective Step Alarm YES – After 3 unsuccessful switching attempts (causing no difference to PF) the alarm is activated. NO – The alarm is disabled. Yes / No 517 Step Power Loss Alarm YES - If the step size reduces to less than 70% of its initial value the alarm is triggered. NO – Capacitor power loss is not monitored. Yes / No Reset Settings (600) Menu No. Description Options 601 Reset Settings Set all settings back to factory standard. Yes / No 602 Reset Step Database Set all step data back to factory standard. Yes / No 603 Reset Operation Hours Set Operation Hours back to 0. Yes / No 604 Reset Average Power Factor Yes / No 605 Reset Maximum Temperature Resets the highest measured temperature. Yes / No 606 Reset Alarms Reset all existing active alarms. Yes / No 607 Display software version of the controller 1.xx P O W E R F A C T O R C O R R E C T I O N S Y S T E M 77 NO T ES .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... 78 NO T ES .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... .......................................................................................................................................................................................................................................................................... P O W E R F A C T O R C O R R E C T I O N S Y S T E M 79 AUSTRALIA New South Wales Queensland Sydney 30-34 Day Street North Silverwater NSW 2128 Tel +61 2 9748 3444 Brisbane 16 Riverview Place Murarrie QLD 4172 Tel +61 7 3909 4999 Melbourne 43-67 River Street Richmond VIC 3121 Tel +61 3 9429 2999 Newcastle 575 Maitland Road Mayfield West NSW 2304 Tel +61 2 4960 2220 Fax +61 2 4960 2203 Townsville 5 Leyland Street Garbutt QLD 4814 Tel +61 7 4779 0700 Fax +61 7 4775 1457 Laverton 104-106 William Angliss Drive Laverton North VIC 3026 Tel +61 3 9368 2901 Wollongong 34 Industrial Road Unanderra NSW 2526 Tel +61 2 4272 5763 Fax +61 2 4272 5957 Rockhampton 1 Lawson Street Parkhurst QLD 4702 Tel +61 7 4927 2277 Fax +61 7 4922 2947 nhp.com.au SALES 1300 NHP NHP FAX 1300 NHP FAX Victoria Albury / Wodonga 847 Ramsden Drive Albury NSW 2640 Tel +61 2 6049 0600 Fax +61 3 6025 0592 Dandenong 40-42 Cyber Loop Dandenong South VIC 3175 Tel +61 3 8773 6400 Fax +61 3 8768 8522 Tasmania Hobart Unit 2 65 Albert Street Moonah TAS 7009 Tel +61 3 6228 9575 Fax +61 3 6228 9757 Launceston Unit 3 13-17 Merino Street Kings Meadows TAS 7249 Tel +61 3 6345 2600 Fax +61 3 6344 6324 ACT Canberra Unit1 187 Gladstone Street Fyshwick ACT 2609 Tel +61 2 6280 9888 Fax +61 2 6280 9588 Western Australia Perth 38 Belmont Ave Rivervale WA 6103 Tel +61 8 9277 1777 Northern Territory Darwin 3 Steele Street Winnellie NT 0820 Tel +61 8 8947 2666 Fax +61 8 8947 2049 NHP Electrical Engineering Products Pty Ltd A.B.N. 84 004 304 812 NHPPFCM 01/12 © Copyright NHP 2012 Toowoomba Cnr Carroll Street and Struan Court QLD 4350 Tel +61 7 4634 4799 Fax +61 7 4633 1796 Cairns Unit 2 1 Bramp Close Portsmith QLD 4870 Tel +61 7 4035 6888 Fax +61 7 4035 6999 South Australia Adelaide 36-38 Croydon Road Keswick SA 5035 Tel +61 8 8297 9055 NEW ZEALAND nhp-nz.com SALES 0800 NHP NHP FAX 0800 FAX NHP PO Box 62-009 Sylvia Park Auckland 1644 New Zealand Auckland 118a Carbine Road Mt Wellington 1060 Tel +64 9 276 1967 Hamilton 78 Rostrevor Street Hamilton 3204 Tel +64 7 849 0257 Fax +64 800 329 647 Napier 126 Taradale Road Onekawa 4110 Tel +64 6 843 6928 Fax +64 800 329 647 New Plymouth 2 Dean Place Waiwhakaiho 4312 Tel 0800 NHP NHP Fax +64 800 329 647 Wellington 52 Victoria Street Lower Hutt 5010 Tel +64 4 570 0634 Fax +64 800 329 647 Christchurch 27 Iversen Terrace Waltham 8011 Tel +64 3 377 4407 Fax +64 3 377 4405 Dunedin 30 Fox Street South Dunedin 9012 Tel 0800 NHP NHP Fax +64 800 329 647