addendum no. 1 - wall fill wick drain

advertisement
ADDENDUM NO. 2
TO
CONTRACT DOCUMENTS
FOR
REFRIGERATED CONTAINER SERVICE AREA
WANDO WELCH TERMINAL
MOUNT PLEASANT, SOUTH CAROLINA
PROJECT NUMBER CIF16E010B
SOUTH CAROLINA PORTS AUTHORITY
25 JULY 2016
General
1.
This Addendum shall supplement, amend, and become part of the Bid Documents. All
Bids and the Construction Contract shall be based on these modifications.
2.
Bidders shall acknowledge the receipt of this addendum on their Bid Form.
3.
The information contained in this addendum addresses Bidder’s questions received
through 21 July, 2016.
Specific
The following revisions should be noted at the appropriate part of the Contract Documents and
made a part thereof:
I.
Plans
Sheet G-2; General Notes and Design Criteria: Add to note 4 under Miscellaneous
Steel “Canopy structural steel shall be painted”
Sheet S-8; Wash Station Rack Plan and Elevation: Add the following notes:
10. Miscellaneous fabrication not in contact with hydraulic fluid shall be HDG steel.
Provide drip pan, Type 316 SS.
11. Provide standard industrial motor; hydraulic fluid shall be selected by final
designer.
CIF16E010B – Wando Welch Terminal – Refrigerated Container Service Area
Addendum #2
Page 1 of 4
Addendum No. 2
12. In the event of power failure, the hydraulic system shall return to float mode
and allow manual positioning in either open or closed position.”
Sheet G-2; General Notes and Design Criteria: Replace note 3.0 under Cast-in-Place
Concrete “All finished edges and corners that shall remain exposed at completion shall
be chamfered ¾” unless noted otherwise.”
Sheet C-7; Paving Details: Change detail 2 to show V-brace at top of perimeter fence, 3
strands barbed wire each side. Change tension wire to top bar.
Sheet C-8; Traffic Control Plan – Sheet 1 of 2: Disregard the “end traffic barrier” call-out
on the left hand side of the sheet.
Sheet S-12; Misc. Structural Details: Disregard Note 2 on Sheet S-12.
Sheet E-20; Misc. Structural Details: Callouts referencing E-41 and E-43 should
reference E-31 and E-43, respectively.
Sheet E-21; Lighting Plans: Add note to table that basis of design shall be “ALBEO by
GE.”
II.
Specifications
1. Front End Specs
a. Revised Bid Form Item IV
b. Revised Table of Contents on page vi
2. Revised Technical Spec Table of Contents
3. Added section 26 01 10 Electrical General Requirements
4. Updated section 26 05 43 Underground Electrical Work
5. Added section 26 12 19 MV Transformers
Section 32 13 11; PCC Paving: Replace paragraph 3.08 C with the following:
“Prepare surface for mating with the new concrete at transverse construction joints (at
end of pours) where a smooth bulkhead form was used. Surface shall be roughened by
water blasting or mechanical means after the concrete has gained sufficient strength to
be roughened. This may be assumed to be at the time of form removal.”
Section 32 13 11; PCC Paving: Replace paragraph 3.08 B with the following:
“Place joint filler which conforms to AASHTO M153 between paving components
adjacent building components or other appurtenances. Fiber expansion joint filler
conforming to ASTM D1751 is also acceptable for this application.”
Section 32 13 11; PCC Paving: Add to paragraph 3.05: “The outer perimeter panel shall be tied
with deformed bars in accordance with ACI 330.
Section 32 13 11; PCC Paving: Replace paragraph 3.07 A with the following:
“Concrete shall be placed in long strips with dowels placed through side forms or drilled
and bonded (at construction joints) and in dowel baskets (at control joints) per the
approved jointing plan. Dowel bar insertion for longitudinal joints (in slip form
CIF16E010B – Wando Welch Terminal – Refrigerated Container Service Area
Addendum #2
Page 2 of 4
Addendum No. 2
construction) may be utilized provided there is a demonstrated experience for the
technique.”
Section 32 31 13; PCC Paving: Change paragraph 2.01 to show that fence shall have barbed
selvage required.
Section 32 31 13; PCC Paving: Change paragraph 2.05 barbed wire requirement to require 6
strand on V arms.
Section 32 31 13; PCC Paving: Change paragraph 2.07 to require top rail be used instead of a
top tension wire.
Section 32 31 13; PCC Paving: Change paragraph 3.01 B.1 for 10 ft. typical post spacing.
III.
A.
Bidder Questions & Responses
Question: Drawing 4V6-04 indicates the new security cameras are to be tied into building
449. Where is building 449 in relation to this project?
Response: Building 449 is at the northeast guard gate, approximately 1,200 feet from the
project site
B.
Question: Will the new cameras have to be integrated into the existing security system? If
so, then please provide detailed information about the existing system for integration
pricing.
Response: Confirm that new cameras are to be integrated into the existing security system.
Existing system is PureAcitv outdoor surveillance system by PureTech Systems:
http://www.puretechsystems.com/pureactiv.html
C.
Question: Drawing S-8 calls out for the contractor to design and install a new hydraulic lift
system for the wash canopy. Given there is only 150 days for this contract, is it really
feasible to expect a design to be completed, approved, materials fabricated and installed,
tested and operated in that time frame? Please considered extending the contract duration
Response: The scope of final design is limited to the sizing of the HPU and controls, and
detailing actuator assembly. It is considered that the contract time is sufficient assuming
that design and fabrication proceeds in parallel with site work. The Owner will expedite
submittal reviews to the extent necessary; contract duration cannot be extended for
operational reasons.
D.
Question: Confirm the following finish requirements: Painted: Structural steel column,
girders, rafters, bollards (yellow), roof decking (PVDF). Please specify the roof decking
color. Galvanized: Anchor bolts, bolts, purlin. Please confirm nothing is to be both
galvanized and painted.
Response: Confirm the coating requirements as summarized. No items are to be both hotdip galvanized and painted, but note “galvalume” roofing material with PVDF coating. Color
will be selected by Owner.
CIF16E010B – Wando Welch Terminal – Refrigerated Container Service Area
Addendum #2
Page 3 of 4
Addendum No. 2
E.
Question: Please advise if it is acceptable to replace the utilidor chase with RCP, PVC, Iron
pipe, or a precast concrete chase. The existing utilidor design appears to be cast in place
which will require multiple pours and time consuming formwork. We feel a prefabricated
unit will provide the same utility in a reduced time. If this is acceptable please advise what
area the cross section of the chase needs to be.
Response: Such substitution may be proposed as part of final design of the hydraulic
system. In principle the Owner is not opposed. The cross sectional area shall be sufficient
for installation and future maintenance of hydraulic lines/hoses; the area indicated shall be
considered a minimum unless final designer can justify otherwise.
F.
Question: Will the installed wick/earthquake drains be below the bottom of subgrade? If
not, who is responsible for repair if they are damaged during excavation?
Response: It is understood that the portion of the wick drain in the referenced area will be
damaged during construction. No repair will be required.
G.
Question: Is the surcharge good structural fill material or is it waste ie. Gumbo material
Response: Surcharge material is approximately 50% select granular fill and 50% common
fill with plastic fines. None of the surcharge is considered to be waste material.
H.
Question: Could not locate appendix A
Response: See Addendum no. 2 documents for Appendix A.
End of Addendum No. 2
CIF16E010B – Wando Welch Terminal – Refrigerated Container Service Area
Addendum #2
Page 4 of 4
BID
Dated
Submitted By
(Company Name)
South Carolina Ports Authority
Post Office Box 22287
Charleston, SC 29413-2287
Attention:
Mr. Tim Connor
Procurement Manager
Gentlemen:
Having carefully examined the Instructions to Bidders, the General and Special Conditions of
the Contract, the Specifications, and the Drawings for Refrigerated Container Service Area,
Mount Pleasant, South Carolina, Project No. CIF16E010B, dated April 2016, as well as the
premises and conditions affecting the work, the undersigned proposes to furnish all materials,
labor, equipment, tools, and other things necessary for the execution of the work covered by
the said Specifications and Drawings, for the following price:
BIDDERS MUST COMPLETE ALL ITEMS
I.Mobilization / Demobilization
A.
Mobilization / Demobilization
Lump Sum (Not to Exceed 2% of Bid)
$
II. Site Work
A.
B.
C.
D.
E.
F.
Remove and Stockpile Existing Surcharge
45,000 CY @ $
/CY
$
Proof Roll Subgrade
31,500 SY @ $
$
/SY
Allowance for Undercutting & Backfill
3,500 CY @ $
/Cy
$
Crushed Rock Base
10,500 CY @ $
/CY
$
10” PCC Paving
31,500 SY @ $
/SY
$
Permanent Pavement Marking
B-1 (CIF16E010B)
12,000 LF @ $
G.
H.
I.
J.
K.
L.
III.
/LF
$
Traffic Barriers, and Curbs
Lump Sum
$
Chain Link Fence
1,950 LF @ $________/LF
$
Storm Drain System
Lump Sum
$
Water Distribution
Lump Sum
$
Sanitary Sewer
Lump Sum
$
Erosion and Sediment Control
Lump Sum
$
Structures
A.
B.
C.
Genset Service Canopy
Lump Sum
$
Wash Station Canopy
Lump Sum
$
Wash Rack Platform
Lump Sum
$
IV. Electrical
A.
Medium Voltage Transformer including:
1). 225 KVA pad mounted transformer including rubber goods, elbow surge
Arresters, inserts, and stand-off insulators with caps.
1 EA Material @ $_________/ EA
$_____________
1 EA Labor @ $___________/ EA
$_____________
2). Ground ring including jumpers, exothermic welds,
ground rods, excavation and backfill.
1 EA @ Lump Sum
$_____________
3). Equipment pad for transformer and service equipment.
1 EA @ Lump Sum
$_____________
4). All other associated work not identified above
Lump Sum
$_____________
Total Item A Lump Sum …………………………………………… $_____________
B-2 (CIF16E010B)
B.
15Kv Underground Power including:
1). 15kV shielded wire, #2 AWG, EPR, copper from switch
K12-1 to primary of transformer.
_______LF wire @ $_________LF
$_____________
Labor @ Lump Sum
$_____________
2). #2, 600V primary neutral, XHHW, copper from switch
K12-1 to transformer.
_______LF wire @ $_________LF
$______________
Labor @ Lump Sum
$_____________
3). 2W4 underground duct bank including excavation,
4” PVC ducts, concrete encased with reinforcement,
ground wire, warning tape, backfill and compaction.
________LF@ $__________ LF
$_____________
4). Connect new ducts to existing manhole.
Lump Sum
$_____________
5). Pump manholes and confined space entry into manholes
Lump Sum
$_____________
6). Clean and mandrel ducts and provide pull string.
Lump Sum
$_____________
7). 15kV terminations. Labor and materials.
Lump Sum
$_____________
8). Replace fuses at switch K12-1
3 EA @ $_________EA
$_____________
9). RGS 4” elbow turn ups with bitumen coating
Lump Sum
$_____________
10). All other associated work not identified above
Lump Sum
$_____________
Total Item B Lump Sum……… ………………………… …... $_____________
C. 600 Volt Service Entrance including:
1). 4” RGS conduits from transformer secondary to panelboard
HV including elbows and fittings, trenching, backfill and compaction.
Lump Sum
$_____________
2). 500KCM, XHHW, copper service entrance wire
______LF wire @ $ ________LF
$_____________
Labor @ Lump Sum
$_____________
3). 250KCM, XHHW, copper neutral
______LF wire @ $ ________LF
$_____________
Labor @ Lump Sum
$_____________
4). Terminations for service entrance wires.
Lump Sum
$_____________
6). Megger test service conductors.
Lump Sum
$_____________
7). All other associated work not identified above.
Lump Sum
$______________
Total Item C Lump Sum ………………………………………..$______________
B-3 (CIF16E010B)
D.
Secondary Electrical including:
1). Light Fixtures. Labor and material.
38 Ea @ $ _________EA
$______________
2). Disconnect switches, NEMA 3R. Labor and material.
9 Ea @ $__________EA
$______________
3). Disconnect switch, explosion proof. Labor and material.
1 EA @ $_________EA
$______________
4). 120VAC receptacles, boxes and covers. Labor and Material.
6 EA @ $ _________EA
$______________
5). Panelboard HV, 3R, SS. Labor and Material
1 EA @ $_________EA
$______________
6). Panelboard LV, 3R, SS. Labor and material
1 EA @ $_________EA
$______________
7). Service equipment support stand, galvanized steel
Lump Sum
$______________
8). Dry type 30KVA transformer. Labor and material
1 Ea @ $__________EA
$______________
9). Low voltage ductbank service laterals, concrete encased and reinforced. Includes
excavation, backfill, compaction and warning tape.
Lump Sum
$______________
10). All service lateral circuit conductors. Labor and material.
Lump Sum
$______________
11). All branch circuits lighting and power / conduit and wire.
Labor and material. Including megger tests of circuit wiring.
Lump Sum
$______________
12). All other associated work not identified above.
Lump Sum
$______________
Total Item D Lump Sum……………………………………….………$______________
E.
Electrical Testing Including:
1). Acceptance tests for pad mounted MV transformer.
1 Ea @ $________EA
2). 15kV cable and terminations: High Potential VLF tests.
Lump Sum
3). Ground tests.
Lump Sum
4). All reports
Lump Sum
5). All other associated work not identified above.
Lump Sum
$______________
$______________
$______________
$______________
$______________
Total Item E Lump Sum……………………………………………… $______________
V.
Low Voltage Electrical and Communication
A. Direct Bury Ductbank 2W2 Power, 2W2
Security w/ Trenching and Repair
B-4 (CIF16E010B)
1,900 LF @ $_______________ /LF
$_______________
B. Split Power/Security Handholes
12 EA @ $_______________ /EA
$_______________
C. Security Lighting Fixture Type “S”
12 EA @ $_______________ /EA
$_______________
D. Field Distribution Box (FDB) w/ Backplate
1 EA @ $_______________ /EA
$_______________
E. Device Interface Box (DIB) w/ Backplate
7 EA @ $_______________ /EA
$_______________
F. Camera Power Box (CPB) w/ Backplate
8 EA @ $_______________ /EA
$_______________
G. Ground Rods w/ Conductor, Welds and Connections
12 EA @ $_______________ /EA
$_______________
H. 6-Strand Single Mode Fiber
(including termination and testing)
Lump Sum
$_______________
I.
24-Strand Single Mode Fiber
(including termination and testing)
Lump Sum
J. Power Conductor Cabling and Termination
Lump Sum
$_______________
$_______________
VI. Video Surveillance System
A. Camera/Light Pole Base and Foundation
12 EA @ $_______________ /EA
$_______________
B. Camera/Light Pole
12 A @ $_______________ /EA
$_______________
C. Fixed AXIS IP dome cameras without analytics
12 A @ $_______________ /EA
$_______________
D. PTZ AXIS IP dome cameras without analytics
2 EA @ $_______________ /EA
$_______________
E. Field Distribution Box (FDB)
1 EA @ $_______________ /EA
$_______________
F. Device Interface Box (DIB)
B-5 (CIF16E010B)
7 EA @ $_______________ /EA
$_______________
G. Camera Power Boxes (CPB)
8 EA @ $_______________ /EA
$_______________
H. Cisco Small Form-Factor Pluggable (SFP) Modules
Lump Sum
$_______________
I.
Small Form-Factor Pluggable (SFP) Modules
for Industrial Field Switches
Lump Sum
$_______________
J. Connectors and Cabling
Lump Sum
$_______________
K. Update Head-End System and Recorders
to include new cameras/locations
Lump Sum
$_______________
L. Camera Licensing
Lump Sum
$_______________
M. Additional Video Storage to maintain
30 days of Recorded Video
Lump Sum
$_______________
N. Contractor Field Testing
Lump Sum
$_______________
O. Performance Verification Testing
Lump Sum
$_______________
P. Endurance Testing
Lump Sum
$_______________
Q. Restricted Area Signs at New Perimeter
18 EA @ $_______________ /EA
$_______________
R. Zone Signs at New Perimeter
5 EA @ $_______________ /EA
$_______________
IV. Miscellaneous
A.
All Other Work Not Included Above
Lump Sum
B-6 (CIF16E010B)
$
Section
Safety Requirements
Use of Explosives
Protection of Persons and Property
Hazardous Substances
40
41
42
Miscellaneous Requirements
Supplemental Data
Correlation and Intent of the Contract Documents
Record Drawings
Disposal of Materials Off the Owner’s Property
Utilization of Port Facilities
List of Contractors, Subcontractors & Material Suppliers
43
44
45
46
47
48
Special Requirements – Charleston Naval Base Container Terminal
Air Quality
Noise Pollution
Potential Hazardous Substance – Minimum Mitigation Measures
Spill Prevention and Cleanup Plan
Protection of Manatees
Additional Insurance Coverage
Bainbridge Avenue Requirements
Property Insurance Adjustment
49
50
51
52
53
54
55
56
SPECIFICATIONS
DIVISION 02 – EXISTING CONDITIONS
Section 02 92 00 - Erosion & Sediment Control
DIVISION 03 - CONCRETE
Section 03 10 00 - Concrete Formwork
Section 03 20 00 - Concrete Reinforcement
Section 03 30 00- Cast-in-Place Concrete
Section 03 60 00 - Grout
DIVISION 5 - METALS
Section 05 40 00 - Light Gage Metal Framing
Section 05 50 00 - Metal Fabrications
DIVISION 9 - FINISHES
Section 09 96 00 - High Performance Coatings
(continued)
v (CIF16E010B)
SPECIFICATIONS (continued)
DIVISION 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
Section 26 05 00 – Common Work Results for Electrical Systems
Section 26 05 13 - Medium Voltage Cables
Section 26 05 26 - Grounding and Bonding for Electrical Systems
Section 26 05 29 - Hangers and Supports for Electrical Systems
Section 26 05 33 - Raceways and Boxes for Electrical Systems
Section 26 05 43 - Underground Electrical Work
Section 26 05 26 - Grounding and Bonding for Electrical Systems
Section 26 05 48 - Vibration and Seismic Controls for Electrical Systems
Section 26 05 53 - Identification for Electrical Systems
Section 26 12 19 - Medium Voltage Transformers
Section 26 22 00 - Low Voltage Transformers
Section 26 24 16 – Panelboards
Section 26 56 00 – Exterior Lighting
DIVISION 27 - COMMUNICATIONS
Section 27 00 00 – Communications
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
Section 28 23 23 – Perimeter Security – Video Surveillance System
DIVISION 31 - EARTHWORK
Section 31 23 00 - Earthwork
DIVISION 32 – SITE WORK
Section 32 11 23 – Crushed Rock Base
Section 32 13 11 – PCC Paving
Section 32 31 13 – Chain-Link Fence
DIVISION 33 – UTILITIES
Section 33 10 00 – Water Distribution
Section 33 30 00 – Sanitary Sewer
Section 33 40 00 – Storm Drainage
APPENDICES
I. Soils Data
vi (CIF16E010B)
South Carolina State Ports Authority
Wando Welch Terminal
Contract No. CIF16E010B
Refrigerated Container Service Area Site Development
Technical Specifications
Table of Contents
No. of
Pages
Section
02 92 00 – Erosion and Sediment Control .............................................................2
03 10 00 – Concrete Formwork ..............................................................................5
03 20 00 – Concrete Reinforcement ......................................................................5
03 30 00 – Cast-in-Place Concrete .........................................................................9
03 60 00 – Grout.......................................................................................................3
05 40 00 – Light Gage Metal Framing....................................................................6
05 50 00 – Metal Fabrications................................................................................5
09 96 00 – High-Performance Coatings .................................................................4
26 01 10 – Electrical General Requirements……………………………………………...10
26 05 00 – Common Work Results for Electrical………………………………………….5
26 05 19 – Low Voltage Electrical Power Conductors and Cables ......................4
26 05 26 – Grounding and Bonding for Electrical Systems ..................................6
26 05 29 – Hangers and Supports for Electrical Systems ....................................2
26 05 33 – Raceways and Boxes for Electrical Systems ......................................6
26 05 43 – Underground Electrical Work...............................................................6
26 05 48 – Vibration and Seismic Controls for Electrical Systems .....................6
26 05 53 – Identification for Electrical Systems ...................................................5
26 12 19 – Medium Voltage Transformers.............................................................5
26 22 00 – Low Voltage Transformers....................................................................6
26 24 16 – Panelboards...........................................................................................8
26 56 00 – Exterior Lighting....................................................................................7
27 00 00 – Communications .................................................................................12
28 23 23 – Perimeter Security – Video Surveillance System.............................27
31 23 00 – Earthwork ..............................................................................................9
32 11 23 – Crushed Rock Base...............................................................................7
32 13 11 – PCC Paving ............................................................................................9
32 31 13 – Chain Link Fence ..................................................................................4
33 10 00 – Water Distribution.................................................................................5
33 30 00 – Sanitary Sewer ......................................................................................8
33 40 00 – Storm Drainage ...................................................................................10
END OF SECTION
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
SECTION 26 01 10
ELECTRICAL GENERAL REQUIREMENTS
PART 1 – GENERAL
1.1
SUMMARY
Work under this section includes requirements that apply to all electrical sections and includes
general requirements for labor, materials and equipment specified in the electrical specifications.
The contractor shall furnish all labor, equipment and incidental items necessary to complete the
work as indicated on the project drawings and as specified herein.
1.2
RELATED DOCUMENTS
A.
General:
1. Requirements of the General and Supplemental Conditions apply to all work in this
section. Provide all labor, material, equipment, and services indicated on the
drawings or specified herein or reasonably necessary for and incidental to a
complete job.
B.
Application:
1. This section applies to all electrical sections of this project except as specified
otherwise in the individual sections.
C.
Electrical Drawings:
1. Except where dimensions are specifically indicated, electrical drawings are schematic
in character, and must not be scaled. It is the Contractor’s responsibility to fit the
work to the job carefully; to investigate the civil and structural drawings affecting this
work, and arrange the work accordingly, furnishing necessary bends, offsets, fittings,
and junctions, whether specifically shown or called for or not.
2. Drawings and Specifications shall be considered as supplementary one to the
other, so that materials and labor indicated, called for, or implied by the one and not
by the other, shall be supplied and installed as though specifically called for by both.
1.3
QUALITY ASSURANCE
A.
Materials and Equipment:
1. All materials and apparatus required for the work shall be new of first-class quality,
and shall be furnished, delivered, erected, connected and finished in every detail, and
shall be so selected and arranged as to fit properly on the site. Where no specific
kind of quality of material is given, a first-class standard article as approved by the
Owner/Engineer shall be provided.
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-1
Epic Engineering 15621
June 2016
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
2.
B.
Basis of Design:
1.
C.
1.4
Specification and drawing reference to equipment, product, fixture, or material name,
make or catalog number, shall be interpreted as establishing a minimum standard of
quality and shall not be construed as limiting competition. The Contractor may, at his
option, use any equipment, product, material, fixture, form or type of construction
which, in the opinion of the Owner/Engineer, expressed in writing, is equal to that
specified.
Where specified makes or brands are listed for specific items in the Specifications,
and/or as scheduled or shown on the Drawings, the item detailed and shown
constitutes the basis of design. All other makes or brand items listed in these
Specifications, or approved, must be checked for proper connections, capacities and
dimensions before submitting shop drawings to assure total compliance with the
Specification details. Variances in space requirements, capacity, connections, and
construction details are adequate reasons for disapproval.
Codes, Rules, Permits, and Fees:
1.
The Contractor shall give all necessary notices, obtain all permits and pay all sales
taxes, fees and other costs, including utility connections or extensions, in connection
with his work. He shall also file all necessary drawings, prepare all documents and
obtain all necessary approvals of all governmental departments having jurisdiction.
He shall obtain all required certificates of inspection for his work and deliver same to
the Owner/Engineer before request for acceptance and final payment for the work.
2.
The Contractor shall include in the work, without extra cost to the Owner, any labor,
materials, services, apparatus, drawings, etc., in order to comply with all applicable
laws, ordinances, rules and regulations, whether or not shown on Drawings and/or
specified.
SUBMITTALS
A.
Product Data: The Owner/Engineer reserves the right to reject any product or brand
that conforms to these specifications, but may not be of the quality intended for this
work.
B.
Submit shop drawings and/or data sheets for approval on all items of equipment,
materials, and accessories furnished under this Division whether specifically listed
below or not. Shop drawings and Specification Data Sheets shall show complete
product information, installation requirements, details and instructions, and shall be
marked to indicate compliance with requirements of contract documents.
C.
Specific items requiring submittals shall be as specified in each individual section of
this Division; Shop drawings shall be submitted and approved before procurement,
fabrication, or delivery of such items to the job site. Partial submittals are not
acceptable; such submittals will be returned without review.
D.
Prepare shop-drawing submittals with identification by Specification Section and Article.
Clearly mark the particular make, model number, accessories, and options. Shop
drawings shall show types, sizes, accessories, elevations, floor plans, sectional views,
installation details, elementary diagrams, and wiring diagrams. Wiring diagrams shall
identify circuit terminals and shall indicate the internal wiring for each item of equipment
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-2
Epic Engineering 15621
June 2016
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
and the interconnection between the items. Drawings shall also indicate adequate
clearance for operation, maintenance, and replacement of operating equipment
devices. If any equipment is disapproved, the drawings shall be revised to show
acceptable equipment and be resubmitted.
1.5
E.
Submittals for each manufactured item shall be manufacturer’s descriptive literature,
equipment drawings, diagrams, performance and characteristic curves, and catalog
cuts. Each submittal shall include the manufacturer’s name, trade name, catalog model
or number, nameplate data, size, layout dimensions, capacity, Specification reference,
applicable industry specification references, and all other information necessary to
establish contract compliance.
F.
When materials or equipment must conform to the standards of organizations such as
the American National Standards Institute (ANSI), American Society for Testing and
Materials (ASTM), National Electrical Manufacturers’ Association (NEMA), and
Underwriters’ Laboratories (UL), proof of such conformance shall be submitted to the
Owner/Engineer for approval. If an organization uses a label or listing to indicate
compliance with a particular standard, the label or listing will be acceptable evidence,
unless otherwise specified in the individual sections. In lieu of the label or listing, the
Contractor shall submit a certificate from an independent testing organization which is
competent to perform acceptable tests and is approved by the Owner/Engineer. The
certificate shall state that the item has been tested in accordance with the specified
organization’s test methods and that the item conforms to the specified organization’s
standard. For material and equipment whose compliance with organizational standards
or specifications is not regulated by an organization using its own listing or label as
proof of compliance, a certificate of compliance from the manufacturer shall be
submitted for approval. The certificate shall identify the manufacturer, the product, the
referenced standard, and shall simply state that the manufacturer certifies that the
product conforms to all requirements of the Specifications and of the referenced
standards listed.
G.
Certified Test Reports: Before delivery of materials and equipment, certified copies of
all test reports specified in the individual sections shall be submitted for approval.
H.
Independent Testing Organization Certificate: In lieu of the label or listing, submit a
certificate from an independent testing organization, competent to perform testing, and
approved by the Owner/Engineer. The certificate shall state that it has been tested in
accordance with the specified organization’s test methods and that the item complies
with the specified organization’s reference standard.
I.
Setting Drawings and Templates: Furnish all necessary templates, patterns, etc., for
installing work and for the purpose of making adjoining work conform; furnish setting
drawings and shop details to other trades as required.
IDENTIFICATION
A.
Manufacturers’ Nameplates: Each major component of equipment shall have
manufacturer’s name, address, model number and rating on a plate securely affixed in a
conspicuous place. Nameplate of a distributing agent will not be acceptable. Code
ratings, or other data, which is die-stamped into surface of equipment, shall be stamped in
an easily visible location.
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-3
Epic Engineering 15621
June 2016
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
B.
C.
Labels: Provide engraved Bakelite labels for all equipment furnished under this Division.
Provide labels which indicate the name and function of each item. Where two or more
pieces of equipment of the same model, type and capacity are furnished, identify each
piece as No.1, No. 2, etc., in addition to the name of the equipment.
1.
Label Size: 1” high, minimum; 1/16” thick, minimum.
2.
Lettering: Gothic style, upper case, ½” high.
3.
Color: Black letters on white background.
4.
Method of Attachment: Minimum of two brass screws or pop rivets.
Cable tags in manholes, transformers, and fused switch cabinets:
Provide tags for each cable or wire. Tag new wire and cable provided by this contract.
The tags shall be polyethylene. Do not provide handwritten letters.
1.
1.6
Polyethylene Cable Tags: Provide tags of polyethylene that have an average
tensile strength of 4500-lbs./sq. in.; and that are 0.035” thick, non-corrosive nonconductive; resistive to, alkalis, organic solvents, and salt water; and distortion
resistant to 300° F. Provide a one-piece nylon, self-locking tie at each end of the
cable tag. Ties shall have a minimum loop tensile strength of 175 lbs. The cable
tags shall have block letters, numbers and symbols 1” high on a yellow
background. Letters, numbers, and symbols shall not fall off or change positions
regardless of the cable tags’ orientation.
PRODUCT DELIVERY AND STORAGE
General: Equipment and materials shall be properly stored, adequately protected, and carefully
handled to prevent damage before and during installation. Equipment and materials shall be
handled, stored, and protected in accordance with the manufacturer’s recommendations and as
approved by the Owner/Engineer. Electrical conduit shall be stored to provide protection from the
weather and accidental damage. Plastic conduit shall be stored on even supports and in
locations not subject to direct sunrays, or excessive heat. Cables shall be sealed, stored, and
handled carefully to avoid damage to the outer covering or insulation and damage from moisture
and weather. Damaged or defective items, in the opinion of the Owner/Engineer, shall be
replaced with new items at no additional cost to the Owner.
1.7
INDEPENDENT TESTING FIRM
A.
The testing firm shall provide a Registered Professional Engineer to interface with the
installing Contractor and the Owner. Testing technicians will be provided as required to
do the work under approved schedules. Designated equipment shall be tested to verify
operation and adjustment. Reports shall be issued documenting checks and test results.
B.
Services: The testing firm shall provide the following services:
1.
Cable tests - Hi Pot VLF pass / fail cable tests only. Megger tests may be
performed by the Electrical contractor.
2.
Cable termination tests - Hi Pot only. Megger tests may be performed by the
Electrical contractor
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-4
Epic Engineering 15621
June 2016
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
B.
C.
Qualification of Testers:
1.
The testing firm shall have technicians with two or more years experience related
to the testing of equipment designated herein. They shall be able to identify
suitable engineering and technical resources to complete the work under
approved schedules.
2.
The supervising engineering representative shall have extensive knowledge of
the products involved and at least two years experience in conducting similar
tests. All testing shall be conducted under the direct supervision of the Registered
Professional Engineer. The supervising engineer representative will prepare, seal,
date and sign reports and be available for consultation with the Owner/Engineer.
3.
Testing technicians shall be trained and experienced in the testing they conduct.
Submit testing personnel resumes for approval prior to testing.
4.
Submit certification of the Testing Firm’s qualifications for approval. The
certification shall include the training and experience of the individuals performing
the tests required in the individual specification sections and on the drawings.
Equipment:
1.
D.
Testing equipment required to conduct the specified tests shall be furnished by
the testing organization unless noted otherwise. Testing equipment shall be in
good working order and comply with the requirements of applicable industry
standards.
Reports:
1.
The testing firm shall utilize comprehensive report forms to document test results
on all equipment and products. Upon completion of the work, the report forms
shall be sealed, dated and signed by the Registered Professional Engineer and
included in the final report. Report forms shall identify equipment by model
number or by customer’s identification number (where assigned). Report forms
shall be suitable for reproduction on normal office copying machines. Sample
forms shall be submitted for review by the Owner/Engineer.
2.
Testing shall be done in accordance with the manufacturer’s instructions, these
Specifications and applicable NEMA, ASA, ASTM and NETA Standards. All over
potential-testing values shall be approved by the Owner/Engineer prior to such
tests.
3.
The testing firm shall collaborate with the manufacturer’s representative during
testing as required.
PART 2 – PRODUCTS
2.1
CATALOGED PRODUCTS
Materials and equipment shall be cataloged projects of manufacturers regularly engaged in
production of such materials or equipment and shall be manufacturer’s latest standard design that
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-5
Epic Engineering 15621
June 2016
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
complies with the Specification requirements. When two or more units of the same type, class,
and size of equipment are required, these units shall be products of a single manufacturer;
however, the component parts of the system need not be the products of the same manufacturer.
Each major component of equipment shall have the manufacturer’s name, address, and the
model and serial number on a nameplate securely affixed in a conspicuous place; the nameplate
of the distributing agent will not be acceptable.
PART 3 – EXECUTION
3.1
3.2
INSPECTION AND COORDINATION
A.
General: Examine the areas and conditions under which electrical work will be installed
and notify the Owner/Engineer in writing of conditions detrimental to the proper and
timely completion of the work. Do not proceed with the work until unsatisfactory
conditions have been corrected in an acceptable manner.
B.
Coordination: Electrical work shall be coordinated with other trades involved in the
construction project. All work shall be carefully laid out in advance, coordinating electrical
features with structural and civil features of construction.
C.
Cooperation with Other Trades:
1.
Closely schedule work so that it is installed at the proper time and phase without
delaying the completion of the entire project.
2.
If the work is installed before coordinating with other trades or so as to cause
interference with work of other trades, or cause unacceptable clearance problems,
make necessary changes in work to correct the condition without extra charge.
3.
Symbols, section details, and wiring diagrams are used in conjunction with
drawings and specifications to define the work. Reference to any item on the
drawings shall be construed as being the same as having that item fully
developed on the drawing. All work and material shall be installed in accordance
with the details and diagrams with any necessary accessories and modifications
to adapt the typical detail to actual field conditions. All such modifications shall
be approved by the Owner/Engineer prior to installation.
SPECIAL REQUIREMENTS
A.
General: Provide all wiring and connections and miscellaneous accessories necessary for
the complete installation of and final connections to equipment. Make all final connections
to such, including installation of all special devices furnished with such equipment.
B.
Supervision: Provide the services of an experienced Superintendent, who shall be
constantly in charge of the installation of the work, together with all skilled workmen
required to unload, transfer, erect, connect-up, adjust, start, operate, and test each
system. The Superintendent shall be qualified and authorized to make decisions and
answer questions put by the Owner/Engineer regarding progress and details of the work.
C.
.Manufacturer’s Recommendations: Where installation procedures are specified to be in
accordance with the recommendations of the manufacturer of the material or equipment
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-6
Epic Engineering 15621
June 2016
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
being installed, printed copies of these recommendations shall be furnished to the
Owner/Engineer prior to installation. Installation of the item will not be allowed to proceed
until the recommendations are received. Failure to furnish these recommendations can
be cause for rejection of the material.
3.3
D.
Start-up: No system shall be started up without a prior inspection by the Owner/Engineer
to assure that all safety devices have been installed and that installation complies with
the Specifications.
E.
Owner-Furnished Equipment: There is no Owner furnished equipment.
INSTALLATION, GENERAL
A.
Excavation and Backfill:
Perform all excavation and backfill in accordance with Specifications. Unless otherwise
indicated, bury all underground ducts a minimum of 32” deep.
Excavation for underground duct bank shall be dug at least wide enough to
accommodate the duct plus 6” around and 32” deep. The trench shall further be
backfilled and compacted so that proper grade is obtained. Excess earth shall be
removed from the project site.
B.
Foundations and Supports:
Concrete work for foundations, supports, bases, etc., required for equipment provided
under this Division of the work shall be provided under this Division in accordance with
Section 03 30 00, Cast-In Place Concrete.
Provide all necessary anchors, bolts, etc., for foundations, supports, pads, and bases
required for the support of all equipment furnished under this Division of the work.
C.
Cutting and Patching:
1.
Perform all cutting and patching required for equipment. If cutting is done due to
failure to perform preliminary roughing work, this work shall be performed at no
additional cost to Owner.
2.
All work and material furnished shall be installed in such a manner that no undue
cutting and patching will be required in the construction. Materials shall be
installed in the various portions of the project as the construction of same
progresses and shall not, in any way or manner, delay the construction of the
project.
3.
Furnish, locate and install all sleeves and inserts required before the structures
are built. Cutting and patching required for conduit where sleeves and inserts
were not installed, or where incorrectly located, shall be performed at no additional
cost to the Owner.
4.
No structural members shall be cut without the approval of the Owner/Engineer
and all such cutting shall be done in a manner directed by him.
5.
Any cutting or patching or repairing of rough or finished work that may be
necessary by the failure to cooperate with other trades in obtaining the proper
space conditions for the installation of his work shall be performed by this Division.
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-7
Epic Engineering 15621
June 2016
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
6.
D.
Rigging and Hoisting:
Provide all rigging and hoisting, and services necessary for erection, and/or delivery into
the premises, of any equipment and apparatus furnished. Remove same from the
premises when no longer required.
E.
Covering of Work:
No conduit, fitting, or other work of any kind shall be covered up or hidden from view
before it has been examined or approved by the Owner/Engineer and/or other authority
having jurisdiction over same. Any faulty or imperfect work or materials which may be
discovered shall be removed and corrected immediately after being condemned and
other work and materials shall be provided to the satisfaction of the Owner/Engineer.
F.
Waterproofing:
Where any work pierces waterproofing, including waterproof concrete, the method of
installation shall be as approved by Owner/Engineer before work is done. Provide all
necessary sleeves and caulking required to make opening absolutely watertight.
G.
Accessibility:
H.
3.4
No cutting that may impair strength of construction shall be done. No holes,
except for small screws, may be drilled in structural members without obtaining
prior approval. All work shall be done in a neat manner by mechanics skilled in
their trades and as approved by the Owner/Engineer.
1.
Coordinate work with other trades whose work is in the same spaces, and advise
all trades of requirements. Such spaces and clearances shall, however, be kept
to the minimum size required.
2.
All equipment which must be serviced, operated or maintained shall be located in
fully accessible positions. Equipment shall include, but not be limited to motors,
miscellaneous outlet boxes, etc. Minor deviations from the Drawings may be
made to allow for better accessibility, but changes of magnitude or which involve
extra cost to the Owner shall not be made without approval from the
Owner/Engineer.
Clearances:
Minimum clearances in front of, or around equipment shall conform to the latest
applicable code requirements, the requirements of the equipment manufacturer, or as
shown on drawings, whichever is greater.
EQUIPMENT INSTALLATION
A.
General:
1.
Obtain services of all manufacturers’ representatives of major equipment at site
during erection or construction of their respective equipment to ensure proper
installation of same. Letters will be required from each manufacturer certifying
that equipment has been checked and is properly installed and operating. Letter
shall include the name of the representative and the date the equipment was
checked.
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-8
Epic Engineering 15621
June 2016
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
2.
B.
3.5
3.6
Where necessary, arrangements shall be made to bring items to the ultimate
location in pieces, or otherwise disassembled, and then to assemble them in
place. All necessary flanges, studs, etc., for matching alignment and field
assembly shall be provided by the manufacturer.
Testing:
Arrangements shall be made for a field test of the equipment after assembly. The above
mentioned field tests shall be in addition to all factory tests, shop tests and final tests and
adjustments.
IDENTICATION
A.
Nameplates:
All controls and equipment shall be clearly identified with nameplates, identifying each
item, of laminated phenolic compound, engraved to show black letters on white
background. All labels shall be permanently fastened to the items they identify.
B.
Cable Tag Installation:
Install cable tags to identify cables installed under this contract. Locate the tags so that
they are clearly visible without disturbing any cabling or wiring.
PAINTING
General: Electrical material and equipment shall be furnished factory primed and painted in
accordance with the manufacturer’s standard specifications and color. After installation of
equipment, the Contractor shall clean and repaint all surfaces as required where damaged due to
shipment and/or installation. Use manufacturer’s stand color, unless noted otherwise on the
drawings or in these specifications.
3.7
FINAL INSPECTION
A.
General: Arrange and schedule final inspection of work at the completion of each phase
and at final acceptance of the project. Notify the Owner/Engineer in writing that the work
has been thoroughly checked and is ready for inspection/acceptance.
B.
Certificates: On completion of the work, obtain certificates of compliance, approval or
acceptance from all authorities having jurisdiction over the work and deliver these
certificates to the Owner. The work shall not be deemed to have reached a state of
completion until the certificates have been delivered.
C.
Protection:
1.
Protect the work and material of all trades from damage by the Contractor’s work
or workmen, and make good all damage thus caused.
2.
Responsibility for work and equipment shall remain under this Division until finally
inspected, tested and accepted. Protect work against theft, injury or damage and
carefully store material and equipment received on site which is not immediately
installed. Close open ends of work with temporary covers or plugs during
construction to prevent entry of obstructing material.
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-9
Epic Engineering 15621
June 2016
DIVISON 26 - ELECTRICAL
Section 26 01 10 – Electrical General Requirements
PART 4 – COMPENSATION
4.1
MEASUREMENT AND BASIS OF PAYMENT
No separate payment will be made for this work. The work is considered subsidiary to the
applicable line items of the Total Bid.
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B - Refrigerated Container Service Area
26 01 10 CIF12EU01
26 0110-10
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
SECTION 26 05 43
UNDERGROUND ELECTRICAL WORK
PART 1 - GENERAL
1.1
SUMMARY
Work under this section includes requirements for materials and installation of underground duct
banks and electrical power cables, splices and terminations. The Contractor shall provide all
labor, materials, equipment and incidental items necessary for a complete underground duct and
power cable system.
1.2
1.3
RELATED DOCUMENTS
A.
General: Requirements of the General and Supplemental Conditions apply to all Work in
this section. Provide all labor, material, equipment, and services indicated on the Drawings
or specified herein or reasonably necessary for all incidentals to a complete job.
B.
General Requirements: Section 26 01 10, Electrical General Requirements, applies to this
section, with the additions and modifications specified herein.
REFERENCES
The Contractor shall accomplish the work in accordance with the reference documents except as
modified in the contract documents. The Contractor shall consider all advisory language or
recommended practices to be mandatory.
A.
ASTM D1556
Density and Unit Weight of Soil in Place by the Sand-Cone
Method
B.
ASTM D1557
Laboratory Compaction Characteristics of Soil Using Modified
Effort (56,000 ft-lbf/ft (2,700 kN-m/m))
C.
ASTM D2922
Density of Soil and Soil Aggregate in Place by Nuclear
Methods (Shallow Depth)
D.
ANSI C2
National Electrical Safety Code (NESC)
E.
IEEE 48
Standard Test Procedures and Requirements for High
Voltage Alternating Current Cable Terminators
F.
IEEE 386
Separable Insulated Connector Systems for Power
Distribution Systems above 600-Volt
G.
IEEE 404
Cable Joints for Use with Extruded Dielectric Cable Rated
5000V Through 46000V and Cable Joints for Use with
Laminated Dielectric Cable Rated 2500V Through 500,000V
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -1
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
1.4
H.
NEMA WC8
Ethylene-Propylene-Rubber Insulated Wire and Cable for the
Transmission and Distribution of Electrical Energy (ICEA S68-516)
I.
NEMA TC2
Electrical Plastic Tubing (EPT) and Conduit (EPC-40 and
EPC-80)
J.
NEMA TC3
PVC Fittings for Use with Rigid PVC Conduit and Tubing
K.
NEMA TC6
ABS and PVC Plastic Utilities Duct for Underground
Installation
L.
NFPA 70
National Electrical Code (NEC)
M.
UL 6
Rigid Metal Electrical Conduit
N.
UL 83
Thermoplastic Insulated Wire and Cables
O.
UL 510
Insulating Tape
P.
AEIC C56
Ethylene-Propylene Rubber Insulated Shielded Power Cable
Rated 5-69 kV
SUBMITTALS
A.
Submit the following in accordance with the Special Conditions outlined in the General
Requirements of the Contract. The Owner/Engineer reserves the right to reject any product
or brand that conforms to these specifications, but may not be of the quality intended for
this work.
B.
Catalog Information: Submit the following for approval:
1.
Conduit (each type)
2.
Insulating Tape
3.
Medium Voltage Cables (each type)
4.
Medium Voltage Terminating Kits and Splices (each type)
5.
Terminator Connector
6.
Cable Lubricants
7.
600-Volt Cable Splice Kits and Connectors
8.
Ground Cable
9.
600-Volt Power Cable
10. Medium Voltage End Caps
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -2
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
C.
Manufacturer's Instructions: Submit the following for approval:
1.
D
E
Splice/Terminator Manufacturer's Installation Instructions
Certificates; Material and Equipment: Provide manufacturer's statement certifying that
the product supplied meets or exceeds contract requirements.
1.
Medium voltage cable.
2.
Medium voltage terminator/splicer.
Certificates; Workmen's Competency:
1.
Submit medium voltage terminator's cable certificate
of competency.
2.
Certification of the qualification of the cable splicer/terminator shall be submitted, for
approval, 30 days before terminations are to be made in medium voltage 15 kV
cables. The certification shall include the training, and experience of the individual
on the specific type and classification of cable to be provided under this Contract. The
certification shall indicate that the individual has had three or more years recent
experience splicing and terminating medium voltage cables. The certification shall
also list a minimum of three terminations that have been in operation for more than
one year. In addition, the individual may be required to perform a dummy or practice
termination/splice in the presence of the Owner/Engineer, before being approved as a
qualified cable splicer. If that additional requirement is imposed, the Contractor shall
provide short sections of the approved types of cables along with the approved type of
kit, and detailed manufacturer's instructions for the cable. The Owner reserves the
right to require additional proof of competency or to reject the individual and call for
certification of an alternate cable Terminator/Splicer.
3.
Certificates: High Potential Cable Test Reports: Prior to placing cables in service, all
high potential test results shall be approved by the Owner/Engineer.
PART 2 - PRODUCTS
2.1
MATERIALS AND EQUIPMENT
General: Provide materials and equipment listed by UL or approved by Factory Mutual (FM)
System, when such equipment is listed or approved.
2.2
CONDUIT AND TAPE
A.
General: Provide conduit and fittings conforming to UL.
B.
Plastic Conduit: PVC conforming to NEMA TC2 (conduit) and TC3 (fittings) type
EPC-40-PVC for direct burial and concrete encasement.
C.
Tape: Plastic insulating tape conforming to UL 510.
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -3
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
2.3
WIRE AND CABLE
A.
General: Provide wires and cables which meet all the applicable requirements of the NEC
and UL for the type of insulation, jacket, and conductor specified or indicated. Conductor
sizes are based on copper. Wire and cable conductor sizes are designated by American
Wire Gauge (AWG) and Thousand of Circular Mils (KCM). All conductors shall be copper.
Insulated conductors shall bear the date of manufacture imprinted on the insulation. Do not
use wire and cable manufactured more than 12 months before delivery to the job site.
B.
600-Volt Wire:
1.
2.4
Primary Ground: Conductors rated 600 volts and less in conduit shall conform to UL
44, Type XHHW-2. Conductor shall be stranded copper.
C.
Wires and Cables for Medium Voltages: Provide wires and cables with both conductor and
insulation shielding, and a PVC or polyethylene jacket. Cable shall meet NEMA WC8 and
AEIC C56 for ethylene-propylene-rubber insulation and shall be rated 15 kV for 13.8kV
systems.
D.
Live Front Medium Voltage Cable Terminations: Provide terminations which meet the
requirements of IEEE 48 for Class 1 outdoor terminations, including stress relief. Provide all
components which are the product of one manufacturer, furnished in a package or kit form.
Provide components which are compatible with the cable insulation and conductor materials.
Included in the package, or kit, complete assembly and installation instructions; submit a
copy to the Owner/Engineer for approval.
E.
Load-break connectors shall be the separable insulated type rated 95 KV B.I.L., 200 amps
and shall meet IEEE 386. Associated bushing wells, inserts, and insulated bushings shall be
compatible with the load-break connectors.
NONMETALLIC DUCTS AND DUCT ACCESSORIES
A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering
products that may be incorporated into the Work include, but are not limited to, the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
ARNCO Corp.
Beck Manufacturing.
Cantex, Inc.
CertainTeed Corp.; Pipe & Plastics Group.
Condux International, Inc.
ElecSys, Inc.
Electri-Flex Company.
PEX Inc.
Lamson & Sessions; Carlon Electrical Products.
Manhattan/CDT; a division of Cable Design Technologies.
Spiraduct/AFC Cable Systems, Inc.
B. Duct Accessories:
1.
Duct Separators: Factory-fabricated rigid PVC interlocking spacers, sized for type and
sizes of ducts with which used, and selected to provide minimum duct spacings
indicated while supporting ducts during concreting or backfilling.
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -4
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
2.
2.5
Warning Tape: Underground-line warning tape specified in Division 26 Section
"Identification for Electrical Systems."
RELATED MATERIAL
Grounding: Provide copper clad steel ground rods with diameter adequate to permit driving to full
length of the rod, but no less than 3/4” in diameter. Each rod shall be an assembly of 10 ft. long
sectional rods coupled together, having the total length as indicated.
PART 3 - EXECUTION
3.1
INSPECTION
General: Examine the areas and conditions under which underground electrical work will be
installed. Notify the Owner/Engineer in writing of conditions detrimental to the proper and timely
completion of the Work. Do not proceed with the Work until unsatisfactory conditions have been
corrected in an acceptable manner.
3.2
3.3
INSTALLATION
A.
General: Install underground cable and conduit in conformance with ANSI C2 and NFPA 70
except as otherwise specified or indicated.
B.
Contractor Damage: Promptly repair any damage to indicated utility lines or systems.
UNDERGROUND CONDUIT
A.
General: Conduit type shall be as specified and as indicated.
B.
Underground Conduit with Concrete Encasement: Construct underground duct lines of
individual conduits encased in concrete. PVC schedule 40 conduit as indicated. Conduits
shall be sized as indicated on Project Drawings. Install concrete encasement surrounding
the bank rectangular in cross-section or as indicated on the Drawings and provide at least 3”
of concrete to cover ducts all around and 2” of cover around rebars. Provide steel
reinforcing in concrete duct bank as indicated on drawings. Separate conduits as indicated.
1.
Install the top of the concrete envelope not less than 32" below grade or as indicated
on the Drawings.
2.
Install duct lines with a continuous slope downward toward manholes and away from
foundations and bunkers with a pitch of not less than 3" in 100 ft. Except at conduit
risers, accomplish changes in direction of runs exceeding a total of 10°, either vertical
or horizontal, by long sweep bends having a minimum radius of curvature of 25 ft.;
sweep bends may be made up of one or more curved or straight sections or
combinations thereof. Provide manufactured bends with a minimum radius of 24".
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -5
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
3,
C.
3.4
Provide separators of high impact polystyrene. Stagger the joints of the conduits by
rows and layers so as to provide a duct line having the maximum strength. During
construction, protect partially completed duct lines from the entrance of debris such as
mud, sand and dirt by means of suitable conduit plugs. As each section of a duct line
is completed, draw a testing mandrel not less than 12" long with a diameter 1/4” less
than the size of the conduit through each conduit, after which draw a brush having the
diameter of the conduit, and having stiff bristles through until the conduit is clear of all
particles of earth, sand, and/or gravel; then immediately install conduit plugs.
Concrete: 3000 psi for duct banks. 1" maximum aggregate. Refer to specification
Section 03 30 00, Cast-In-Place Concrete.
1.
Slump: Not to exceed 3".
2.
Concrete Placing: Retempering of concrete will not be permitted.
D.
Backfilling: Provide a plastic warning tape in the backfill above all underground conduits
and duct banks. Provide tape 3" wide, bright, fade-resistant yellow or orange in color,
and include an imprinted legend CAUTION BURIED ELECTRIC LINE BELOW repeated
continuously throughout the entire length. Bury tape 12" above top of duct bank. Place
backfill in layers not more than 6" thick and compact each layer. Backfill as rapidly as the
construction, testing and acceptance of the Work permits. Provide backfill free from roots,
wood scrap material, and other vegetable matter and refuse. Unless indicated otherwise,
compact backfill to a maximum density of at least 95% as determined by ASTM D1557.
Test in-place density in accordance with ASTM D1556 or ASTM D2922.
E.
Reconditioning of Surfaces: Restore paved and unpaved surfaces disturbed during the
installation of duct or direct burial conduit to their original elevation and condition.
F.
Pull String: Provide plastic string having a minimum tensile strength of 200 lbs. in each
empty duct. Leave a minimum of 36" of slack at each end of the pull string unless noted
otherwise.
CABLE PULLING
A.
B.
General: Test existing duct lines with a mandrel and thoroughly swab out to remove foreign
material before the pulling of cables. Pull cables down grade with the feed-in point at the
manhole or structure of the highest elevation. Use flexible cable feeds to convey cables
through the manhole opening and into the duct runs.
1..
Provide lubricants for assisting in the pulling of cables which are specifically
recommended by the cable manufacturer.
2.
Do not exceed the maximum cable pulling tension recommended by the cable
manufacturer.
Installation of Cables in Manholes: Do not install cables utilizing the shortest route. Form all
cables to closely parallel walls; do not interfere with duct entrances, and support on brackets
and cable insulators at a maximum of 4 ft. In existing manholes, where new cables are to
be installed, modify the existing installation of cables, cable supports and grounding as
required for a neat and workmanlike installation with all cables properly arranged and
supported. Provide new racks as required for installation of new cables.
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -6
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
C.
Fireproofing (ARC Proofing) of Cables in Manholes: Fireproof all wire and cables which will
carry current at 2200 volts or more in manholes.
1.
Tape wrap cables without a nonmetallic protective covering over the sheath, prior to
application of the fireproofing. Provide wrap in the form of two tightly applied halflapped layers of a pressure-sensitive 10 mil thick plastic tape, and extend not less
than 1" into the duct. Even out irregularities of the cable, with insulation putty before
the tape is applied.
2.
D.
3.5
3.6
Connections to Manholes: For duct line connections to existing manhole use existing
window terminators if available or provide core bore and seal around conduit entry.
EARTHWORK
A.
Remove excavated materials from the project site. Provide sheeting and shoring
as necessary for protection of Work and safety of personnel. Remove water from
excavation by pumping or other approved method.
B.
Provide backfilling around structures consisting of earth, loam, sand-clay, or sand and
gravel, free from large clods of earth or stones over 1" in size. Place backfill materials
symmetrically on all sides in loose layers not more than 9" deep. Moisten each layer, if
necessary, and compact with mechanical or hand tampers to 95% compaction.
CABLE TERMINATING
A.
3.7
Wrap strips of fireproofing tape, approximately 1/16” thick by 3" wide, tightly around
each cable spirally in half-lapped wrapping, or in two butt-joined wrappings with the
second wrapping covering the joints in the first. Apply the tape with the coated side
toward the cable and extend 1" into the ducts. To prevent unraveling, random wrap
the fireproofing tape the entire length of the fireproofing with pressure sensitive glass
cloth tape. Use fireproofing tape consisting of a flexible, conformable fabric having
one side coated with flame retardant, flexible, polymeric coating and/or a chlorinated
elastomer not less than 0.050" thick weighing not less than 2.5 lbs./sq. yd. Provide
tape which is non-corrosive to cable sheath, self-extinguishing; will not support
combustion, and not deteriorate when subjected to oil, water, gases, saltwater,
sewage, and fungus.
Protect terminations of insulated power cable from accidental contact, deterioration of
coverings, and moisture by the use of terminating devices and materials.
1.
Make terminations using materials and methods as indicated or specified herein or
as designated by the written instructions of the cable manufacturer and termination
kit manufacturer.
2.
Termination for high voltage cable shall be rated, and be capable of withstanding test
voltages, in accordance with the IEEE 48.
SUBMERSIBLE SPLICES FOR 600-VOLT CLASS CABLES
A.
General: Splices are not allowed unless justified by the Contractor and approved by the
Engineer. Cable terminations shall be made on power distribution blocks.
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -7
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
If splices are absolutely necessary then make splices in underground systems subject to
water infiltration by using a compression connector on the conductor and by insulating and
waterproofing by one of the following methods suitable for continuous submersion in water.
3.8
1.
Cast-Type Splice Insulation: Provide by means of a molded casting process
employing a thermosetting epoxy resin insulating material. Apply by a gravity poured
method or by a pressure injected method. Provide packaged form component
materials of the resin insulation ready for convenient mixing without removing from the
package. Do not allow the cables to be moved until after the splicing material has
completely set. Install per splice kit manufacturer's instructions.
2.
Gravity Poured Method: Employ materials and equipment contained in an approved
commercial splicing kit which includes a mold suitable for the cables to be spliced.
When the mold is in place around the joined conductors, prepare the resin mix and
pour into the mold. Do not allow cables to be moved until after the splicing materials
have completely set. Install per splice kit manufacturer's instructions.
DRY SPLICES AND TAPS FOR 600-VOLT CLASS CABLES
General: Provide splices and / or taps of the kind and type as approved for that purpose and as
noted on the drawings.
3.9
SPLICES IN MEDIUM VOLTAGE CABLES
General: Splicing shall be as approved by the Engineer on a case-by-case basis and only where
absolutely necessary. Power cable joints (splices) suitable for continuous immersion in water and
made only in accessible locations in manholes.
A.
3.10
Make medium-voltage joints by using a kit of one manufacturer and with written approval of
the manufacturer of the cable which is to be spliced. Upon request, supply manufacturer's
design qualification test report in accordance with IEEE 404. Joint design shall have been
proof tested in accordance with IEEE 404. Connectors for joint shall be tin-plated
electrolytic copper, having ends tapered and having center stops to equalize cable insertion.
1.
Watertight Tape-Type Joint: Consists of an approved connector, self-fusing tape
(splicing compound), self-bonding semiconducting tape, tinned copper shielding tape or
braid, and plastic tape.
2.
Heat-Shrinkable Joint: A uniform cross-section heat-shrinkable polymeric construction
consisting of a linear stress relief system, a high dielectric strength insulating material,
and an integrally bonded outer conductor layer for shielding. Replace original cable
jacket with a heavy-wall heat-shrinkable sleeve with hot-melt adhesive coating.
Provide joint suitable for the rated voltage of the cable.
3.
Live End Caps: Provide live end caps using a “kit” including a heat-shrinkable tube and
a high dielectric strength, polymeric plug overlapping the conductor. End cap shall
conform to applicable portions of IEEE Std. 48.
GROUNDING
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -8
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
A.
General: Provide non-current carrying metallic parts associated with electrical equipment
with a maximum resistance to solid "earth" ground not exceeding the following values:
1.
Pad-mounted substations without protective fences
5 ohms
2.
Ground in manholes
10 ohms
3.
Grounding other metal enclosures of primary voltage
electrical and electrically operated equipment
10 ohms
Grounded secondary distribution system neutral and
non-current carrying metal parts associated with distribution
systems and grounds not otherwise covered.
5 ohms
4.
3.11
B.
Grounding Electrodes: Provide cone pointed driven ground rods driven full depth plus 6",
installed when indicated to provide an earth ground of the value before stated for the
particular equipment being grounded.
C.
Connections: Make grounding connections which are buried or otherwise normally
inaccessible, and excepting specifically those connections for which access for periodic
testing is required, by exothermic weld or by using a compatible mechanical connection and
brazing over. Make exothermic welds strictly in accordance with the weld manufacturer's
written recommendations. Welds which have "puffed up" or which show convex surfaces,
indicating improper cleaning, are not acceptable. No mechanical connector is required at
exothermic weldments.
FIELD TESTS
A.
General: As an exception to requirements that may be stated elsewhere in the contract,
give the Owner/Engineer 5 days' notice prior to each test.
B.
Distribution Conductors 600-Volt Class: Test all 600-Volt class conductors to verify that no
short circuits or accidental grounds exist. Make tests using an instrument which applies a
voltage of approximately 500 volts to provide a direct reading of resistance.
C.
Medium Voltage Cables: After installation, and before placing in service, the Independent
Electrical Testing firm shall perform a High Potential VLF test on all 15 kV cables. Adhere to
all precautions and limits as specified in the ICEA standard. Utilize test procedure as follows
and record the results for each cable test. Provide Cable Test Report.
1.
Record temperature and relative humidity. Do not perform test unless weather is clear
and relative humidity is below 70%.
2.
Record cable data.
3.
Record normal operating voltage.
4.
Record applied test voltage.
5.
Record test frequency.
6.
Individually test each conductor with all other conductors grounded. Ground all shields.
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -9
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 05 43 – Underground Electrical Work
7.
Properly suppress corona for all terminations.
8.
Apply 100% test voltage for 1 hour. Record PASS or FAIL for each phase.
D.
Ground Rods: Test ground rods for ground resistance value before any wire is connected.
Use a portable ground testing megger to test each ground or group of grounds. Equip the
instrument with a meter reading directly in ohms or fractions thereof to indicate the ground
value of the ground electrode under test. Provide one copy of the megger manufacturer's
directions for use of the ground megger indicating the method to be used. Should any
individual ground rod measure more than 25 ohms resistance, and should any ground
system measure a higher value than that specified in the paragraph entitled Grounding,
notify the Owner/Engineer. Submit written results of all tests.
E.
Compaction: Test backfill in accordance with ASTM D1556 or ASTM D2922.
F.
Test Report: Submit test reports for the following:
1.
600-Volt Cables: Identify each cable and test result.
2.
Medium Voltage Cables: Identify each cable and test result.
3.
Grounding Electrodes and Systems: Identify electrodes and systems, each test.
PART 4 - COMPENSATION
4.1
MEASUREMENT AND BASIS OF PAYMENT
A.
Payment will be made under Items in Section V.
B.
Bid Item extensions are computed in accordance with the quantities and unit prices stated
and reflect full compensation for a complete, finished product.
D.
Quantities stated in the Bid may be adjusted on order of the Owner. The cost or credit to the
Owner shall be computed in accordance with the unit prices stated under the applicable Bid
Item.
D.
No quantity adjustment will be made for work performed outside the scope of work.
E.
No quantity adjustment will be made for work completed within its specified tolerance, nor
the specified tolerance of the preceding completed work Item.
South Carolina Ports Authority – Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
26
05 43
26 05 43 -10
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 12 19 – MV Transformers
PART 1 - GENERAL
1.1
SUMMARY
This specification is to provide a pad-mounted transformer to step down primary voltage
from 13.8 kV to 480Y/277V for power service to the service area for refrigerated
containers. Basis of design is ABB.
1.2
REFERENCES
The Contractor shall accomplish the work in accordance with the reference documents
except as modified in the contract documents. The Contractor shall consider all advisory
language or recommended practices to be mandatory.
A.
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
ASTM D 3487
B.
C.
Mineral Insulating Oil Used in Electrical Apparatus
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERING, INC (IEEE)
IEEE C2
National Electrical Safety Code
IEEE 386
Separable Insulated Connectors for Power Distribution Systems
Above 600 volts.
IEEE C62.11
Metal-Oxide Surge Arresters for AC power Circuits (>1 KV)
(ANSI/IEEE)
NATIONAL ELECTRICAL MANUFACTURERS ACCOCIATION (NEMA)
NEMA C57.12.22 Pad-Mounted Compartmental-Type, Self-Cooled, Three-Phase
Distribution Transformers for use with Separable Insulated HighVoltage Connectors, 2500 KVA and Smaller.
D.
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70
1.3
National Electrical Code
SUBMITTALS
A.
B.
Product Data: The Owner/Engineer reserves the right to reject any product or
brand that conforms to these specifications, but may not be of the quality intended
for this work. Submit the following for approval:
1.
Pad-mounted transformer
2.
Acceptance tests and verifications
3.
Operating and maintenance data
Submit product data for transformer showing overall dimensions, front view,
sectional views, ratings and sizes of all components and wiring diagrams.
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 12 19 – MV Transformers
C.
D.
Transformer Test: Standard tests shall include:
1.
Ratio Test
2.
Polarity Test
3.
Phase Relation Test
4.
No-Load Loss Test
5.
Excitation Current Test
6.
Impedance Voltage test
7.
Load Loss Test
8.
Applied Potential Test
9.
Induced Potential Test
10.
Leak Test
11.
Resistance Measurement Test
12.
Certified Test Report
13.
Factory QC Impulse Test
Operating and Maintenance Data:
1.
Submit operating maintenance data.
2.
Include instructions for operating equipment
3.
Include instructions for operating equipment under emergency conditions.
4.
Identify operating limits which may result in hazardous or unsafe conditions.
5.
Documents rating of equipment and each major component.
6.
Include routine preventive maintenance.
7.
List special tools, maintenance materials, and replacement parts.
PART 2 - PRODUCTS
2.1
PAD-MOUNTED TRANSFORMER
A.
Pad-mounted transformer shall be of the outdoor type and shall consist of a highvoltage (incoming) compartment, a transformer section, and a low-voltage
(outgoing) compartment suitably separated by full height isolating barriers. All
components shall be assembled and shipped by one manufacturer as a unit,
completely weatherproof and tamperproof for mounting on a concrete pad without
additional housing, fences or other enclosures. Unit shall meet all applicable
portions of ANSI C57.12.26.
B.
Primary Components: The incoming compartment shall be deadfront, loop feed
construction (200 amp HV bushing wells) and shall include load-break connectors,
2-position 300 amp LBOR transformer switch, fuses, deadfront surge arresters,
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 12 19 – MV Transformers
parking stands, insulated standoff bushings, insulated protective caps and inserts.
Bayonet fuses shall be accessible from the primary compartment.
C.
Load-break connectors shall be the separable insulated type rated 95 KV B.I.L.,
200 amps and shall meet IEEE 386. Associated bushing wells, inserts, and
insulated bushings shall be compatible with the load-break connectors.
D.
A parking stand shall be provided near each bushing well. Three insulated
bushings shall be provided for parking of energized load-break connectors on
parking stands. Provide insulated protective caps.
E.
Fuses: Provide bayonet oil-immersed, expulsion fuses in series with parallel oilimmersed, partial range current-limiting fuses. Coordinate protection with
expulsion fuse clearing low-current faults and current-limiting fuse clearing
high-current faults up to 50,000 Amperes symmetrical.
F.
Surge arresters shall be 10KV, 8.4 KV MCOV fully shielded, combined dead-front
molded-rubber separable connectors and zinc-oxide gapless varistor surge
protectors. Combination units shall meet the applicable requirements of IEEE 386
and IEEE C62.11.
G.
Transformer Section: Transformers shall be the oil-immersed self-cooled type with
the following ratings and features:
kVA: ........................................225
Phase: .....................................3
Primary Voltage: .....................13,800 Volts Delta
Secondary Voltage:.................480/277 Volts WYE
Frequency: ..............................60 Hz
Mineral Oil: ..............................Shall confirm to ASTM D 3487, Type II
Temperature Rise: ..................65 Degrees C
Primary B.I.L.: .........................95 KV
Secondary B.I.L.: ....................60 KV
Percent Impedance: ................4.10 Percent plus or minus 7%
Taps: .......................................Two 2½ percent above and two 2½ percent below
rated voltage (taps shall be full capacity)
Windings: ................................Aluminum/Aluminum
Sound Level: ...........................65 DB
Base and enclosure ................304 Stainless Steel
Tank…………………………….304 Stainless Steel
H.
Secondary Components: The secondary compartment shall be live front
construction and shall include 600 amp porcelain bushings and spade-type
terminals with four 9/16” diameter holes. Neutral XO bushing with ground strap.
I.
Pad-Mounted Enclosure: A tamperproof and weatherproof pad-mounted enclosure
shall be provided, constructed of 304 stainless steel with a green Munsell 7GY
3.29/1.5 finish. The enclosure shall have lifting provisions, padlock provisions, and
a penta-head security bolt. The enclosure cabinet shall be 18” deep.
J.
Accessories: The transformer shall have the following accessories:
1.
1” Drain Valve with 3/8” Sampler
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 12 19 – MV Transformers
2.
Dial-type thermometer
3.
Liquid level gage
4.
Pressure vacuum gage
5.
Standard pressure relief valve
6.
Nitrogen test port
K.
Warning Signs: ANSI Z35.1.
1. Provide red painted signs that state “DANGER HIGH VOLTAGE” in two lines of
3” high letters on transformer. NEMA Safety Labels.
2. Provide Arc Flash Warning Label.
L.
Paint Finish: Multi-step process: Green epoxy primer by cationic electrode position.
Final coating of two-component urethane paint spray applied for color and
additional film build.
PART 3 EXECUTION
3.1.
INSPECTION
A.
3.2.
INSTALLATION
A.
3.3.
General: Examine the areas and conditions under which the transformer will be
installed and notify the Engineer in writing of conditions detrimental to the proper
and timely completion of the work. Do not proceed with work until unsatisfactory
conditions have been corrected in an acceptable manner.
B.
General: Install the transformer in strict conformance with the manufacturer’s
written recommendations. Electrical installation shall conform to ANSI C2, NFPA
70, and to the requirements specified herein.
Equipment Pad: Provide a concrete and reinforced equipment pad.
C.
Provide bollard protection for the transformer.
FIELD QUALITY CONTROL
A.
Performance of acceptance checks and test shall be by an independent electrical
testing firm. Perform in accordance with the manufacturer’s recommendations,
NFPA 70B, NETA ATS and ANSI standards.
B.
Transformer, Pad-Mounted Type – Medium Voltage
1.
Compare transformer and accessories nameplates information with the
shop drawings and report discrepancies.
2.
Inspect transformer and accessories and report damage, loose material,
shipping blocks or contamination that must be corrected, clean where
appropriate.
3.
Inspect installation location and report any unfavorable environmental
conditions that must be corrected.
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
Epic Engineering 15621
June 2016
DIVISION 26 - ELECTRICAL
Section 26 12 19 – MV Transformers
4.
Check transformer for level, security to foundation and operation of doors.
Report conditions that must corrected, adjust where appropriate.
5.
Visually check the equipment ground. Report deficiencies.
6.
Move no-load tap changer through all positions and test turns-ratio on each
point. Record values and report deficiencies, set on mid tap.
7.
Take a sample of the insulation liquid and perform the following tests.
Record values and provide report.
8.
C.
a.
Visual Analysis
1)
Color
2)
Condition
b.
Sample Analysis
1)
Dielectric Strength
2)
Acidity
3)
Water Content
4)
Dissolved Gas Analysis
Perform the following test on each transformer. Provide report document
that gives analysis and recommendations. Do not perform tests until
transformers are set in place for operation.
a.
Absorption Test
b.
Turns Ratio Test
Follow-Up Verification: Upon completion of acceptance checks, settings, and
tests, the Engineer shall show by demonstration in service that circuits and
devices are in good operating condition and are properly performing the intended
function.
PART 4 COMPENSATION
4.1.
MEASUREMENT AND BASIS OF PAYMENT
Unit Price Items: Unit prices for transformers are included in the Bid Form and are paid
per each inclusive of all materials and labor required for installation and operation.
A.
“Medium Voltage Transformer” shall be maeasured and paid by the Lump Sum,
for pad mounted transformer including rubber goods, elbow surge arresters,
inserts, and stand-off insulators with caps. Also included are ground ring with
jumpers, exothermic welds, ground rods, excavation and backfill; and equipment
pad for transformer and service equipment
South Carolina Ports Authority - Wando Welch Terminal
CIF16E010B – Refrigerated Container Service Area
Epic Engineering 15621
June 2016
SCPA Quality Control Minimum Sampling and Testing Frequency Requirements
Item #
1
Material or Product
Minimum Size of Each Sample1
6
7
Blocks, Concrete
In accordance with ASTM C140
8
Bolts, High Strength
3 assemblies of bolt, nut and washer
10 bricks each source
One (1) 40 inch and
One (1) 12 inch
3
4
5
9
Brick
10
Cable Strand
11
Castings, Catch Basins Drop
Inlets
Cement Stabilized Earth Base
13
Cement Stabilized Earth Base
14
Cement, Fly Ash
1 gallon
15
Cement, Portland & Slag
1 gallon
16
Cement, Masonry
Concrete, Structural,
Prestressed, Lean & Other
Concrete, Structural,
Prestressed, Lean & Other
18
Each 500 tons
Gradation and Approval Sheet 2
Submit one sample of each type, each Contract
Each 500 tons
Gradation and Approval Sheet 1
Submit one sample of each type, each Contract
Approval Sheet 2
Approval Sheet 1
Each 10,000 tons of mix produced
Each source
Approval Sheet 37
Dimensions, Water Absorption,
Compressive Strength
Each possible combination of bolt lot,
nut lot and washer lot
Each 50,000 bricks
Each 5 reels per heat number
Each structure
12
17
Remarks3
Approval Sheet 5 and/or Approval
Sheet 53
Admixtures
See SC-T-1,
Aggregates, Coarse Non-HMA SC-T-3,
and SC-T-4
10 pounds
Aggregates, Fine
See SC-T-2, SC-T-3, and SC-T-4
Non-HMA
Aggregates, Coarse HMA
Aggregates, Fine
HMA
Asphalt, Liquid PG binder
1 quart
2
Test Required2
Minimum Frequency of Sampling
Each 25,000 SF or one day's work
whichever is greater
Each 5,000 SF or one day's work,
whichever is greater
Each 50 tons
Each 100 tons.
On large paving and modified base
projects, rate determined by the
Engineer
Submit Certification for cable strand
Dimension
Inspect all castings for workmanship & Manufacturer’s Certification Required
Compaction
Depth
Mill Test Report Required
Mill Test Report Required
Verify Type in Field
As needed to control consistency
As needed to control
% entrained air
Minimum of one set per 50 yards, or
each day's placement, or for each
structure poured, whichever is greater
Minimum of one set per 50 yards, or
each day's placement, or for each
structure poured, whichever is greater
One (1) set each
one-half day’s production
Four (4) each day’s run and each time
test specimens are made
Four (4) each day’s run and each time
test specimens are made
Slump
Test when consistency is questionable and when cylinders are made
Air Content
Test when air content is questionable and when cylinders are made
Make specimens for compressive
strength.
AASHTO T-23 (ASTM C 31)
Make specimens for compressive
strength.
AASHTO T-23 (ASTM C 31)
Make specimens for compressive
strength.
AASHTO T-23 (ASTM C 31)
Slump
AASHTO T-23 (ASTM C 31)
Air content
AASHTO T-23 (ASTM C 31)
19
Concrete, Structural
Three cylinders, minimum
4-inch cylinders
20
Concrete, Prestressed
Six cylinders, minimum
4-inch cylinders
21
Concrete, Lean
Four (4)
6-inch cylinders.
22
Concrete Pavement
23
Concrete Pavement
24
Concrete Pavement
Four (4) flexural beams
One (1) set each 1500 square yards, or
Make specimens for flexural
part thereof.
strength.
Minimum one (1) set per day.
AASHTO T-23 (ASTM C 31)
25
Coquina Shell Base
25 pounds
Each 25,000 SF
Provide sample to the Engineer and Certification that the source meets or
exceeds the Contract requirements
26
Coquina Shell Base
27
Coquina Shell Base
28
Curing Compound, Spray-On/
Brush-On Concrete Coatings
Appendix A
CIF16E010B
Each 5,000 SF or one day's work,
whichever is greater
Each 25,000 SF or one day's work,
whichever is greater
No samples required
Depth
Compaction
Approval Sheet 7 or
Approval Sheet 33
Manufacturer’s Certification Required
1 of 4
Item #
Material or Product
29
Embankments
30
Embankment Material
31
Embankment Material
32
Emulsions
33
Fence, Barbed Wire
34
Fence, Chain Link
35
Fence, Woven Wire
36
Fence, Hardware
37
Fertilizer
Guardrail, Beams,
Steel Posts & Hardware
Guardrail, Wood Posts &
Blocks
38
39
40
Guardrail, Composite Blocks
41
42
43
46
Handrailing, Steel Pipe
Handrailing, Aluminum
HMA Mixes
Joint Material, Structural and
Pavement
Lime, Agricultural and
Hydrated
Graded Aggregate Base
47
Graded Aggregate Base
48
Graded Aggregate Base
49
Mineral Filler, HMA
Paint,
Structural Steel
Piles, Steel
Piles,
Treated Timber
44
45
50
51
52
Minimum Size of Each Sample1
0.5 gallon
One (1)
3-foot length
One (1)
2-foot length
One (1)
4-foot length
Three (3) each type
Test Required2
Minimum Frequency of Sampling
Each 2000 cubic yards, minimum 1 per
Compaction
lift
One each for each change of source or
appearance.
One each for each change of source or
Proctor
appearance or for each 20,000 cubic
yards
Each 2500 gallon
Approval Sheet 38
Manufacturer’s Certification Required
Each 16,000 feet, each source
Manufacturer’s Certification Required
Each 50 rolls,
each source
Each 50 rolls,
each source
Each 50 rolls,
each source
Manufacturer’s Certification Required
Manufacturer’s Certification Required
Manufacturer’s Certification Required
Visual defects and
Approval Sheet 29
Manufacturer’s Certification Required
Visual defects
Must bear Inspection Agency’s hammer mark
Visual defects and Approval Sheet
49
Manufacturer’s Certification Required
Manufacturer’s Certification Required
See Specifications
See Specifications
See Specifications
See Specifications
Approval Sheet 39 for hydrated lime
See SC-T-1
1 quart
Each 25,000 SF, each layer
Each 5,000 SF or one day's work,
whichever is greater
Each 25,000 SF or one day's work
whichever is greater
Each source Per project
Grain Size Distribution
Depth
Compaction
Manufacturer’s Certification Required
Visual Flaws
Mill Test Report required
Visual Flaws
Must bear Inspection Agency’s hammer mark
Piles, Prestressed
Visual Flaws
54
Pipe Culverts, Concrete
Visual Flaws
55
56
57
Pipe Culverts, High Density
Polyethylene Pipe
58
Rip Rap
59
Sand Clay Base, Roadway
60
Sand Clay Base, Roadway
61
Sand Clay Base, Roadway
Appendix A
CIF16E010B
Submittal of Source Certification is required
Manufacturer’s Certification Required
53
Pipe Culverts, Corrugated
Metal
Pipe Culverts, Corrugated
Aluminum
Remarks3
If ID < 10 inches One (1)
3-foot piece.
If ID > 10 inches One (1)
1-foot piece
Each size, each shipment
Plant must be certified in accordance with Specifications and Plant must
certify each pile
Plant must be certified in accordance with Specifications and Plant must
certify each delivery
Visual Flaws
Mill Test Report required
Visual Flaws
Mill Test Report required
Visual Flaws and Manufacturer’s
Stamp
Manufacturer’s Certification Required
Visual Check for
Size and Quality
10 pounds
Each 25,000 SF, each layer
Each 5,000 SF or one day's work,
whichever is greater
Each 25,000 SF or one day's work
whichever is greater
Submittal of Source Certification is required
Depth
Compaction
When minimum percent
compaction is specified
2 of 4
Item #
Material or Product
62
Seed
63
Steel, Structural
64
Steel, Reinforcing
Subbase,
Cement-Modified
Subbase,
Cement-Modified
Subbase,
Cement-Modified
Subbase,
Cement-Modified
65
66
67
68
69
Minimum Size of Each Sample1
Test Required2
Minimum Frequency of Sampling
Remarks3
Manufacturer’s Certification Required
Visual Defects and Inspection
Agency Marks
40 inches
Each size, each shipment
As required
Once daily
Two (2)
4-inch diameter cores
Once daily
Subgrade, Untreated
% Passing 2 inch and
#4 sieves
Compaction
Depth
Compaction
70
Subgrade, Untreated
71
72
Timber, Treated
Timber, Untreated
Visual Defects
Visual Flaws, Knots, etc.
73
Traffic Marking, Paint
Waterborne or Solventborne
Check batch numbers at job site
Accepted based on Manufacturer Certification
and match certification documents.
74
Traffic Marking, Thermoplastic
or Epoxy
75
Traffic Marking, Pavement
Markers
76
Traffic Marking, Reflective
Beads Spray-on/Drop-on
77
Underdrains & Sectional
Drains, Corrugated
Polyethylene
78
79
Underdrains & Sectional
Drains, Concrete Perforated.
Underdrains & Sectional
Drains, Corrugated Metal
Perforated
80
Underdrains & Sectional
Drains, Asphalt Fiber
81
Underdrains & Sectional
Drains, Corrugated Aluminum
83
Underdrains & Sectional
Drains, Class PS 46 PVC
Water
84
Waterproofing, Asphalt or Tar
85
Waterproofing, Fabric
Wire,
Reinforcement
82
86
87
Wire Mesh Reinforcement
88
89
90
91
92
93
Bollards
Fender Systems
High Mast, Area Lighting
Fiber Optic Cabling
Conduit
Conductors
Appendix A
CIF16E010B
10 pounds
Each 25,000 SF or one day's work
whichever is greater
Each 5,000 SF or one day's work,
whichever is greater
Each 25,000 SF or one day's work
whichever is greater
Each 25,000 SF or one day's work
whichever is greater
Mill Test Report required for components not pre-approved
No field samples required
20 markers per lot.
Randomly selected
One (1) 50 or 55- pound bag when
bagged.
No sample in bulk pack
If ID < 10 inches One (1)
3-foot piece.
If ID > 10 inches One (1)
1-foot piece
2 joints
Must be pre-tested and bear Inspection Agency’s hammer mark
Not pre-tested Or pre-approved
Check batch numbers at job site
Accepted based on Manufacturer Certification
and match certification documents.
Accepted based on Manufacturer Certification
One bag per each batch (44,000
pounds)
Accepted based on Manufacturer Certification
Each size, each shipment
Manufacturer’s Certification Required
Each source
Mill Test Report required
One (1)
Each size, each shipment
2-foot length and One(1) 1-foot length
Manufacturer’s Certification Required
Mill Test Report required
One (1)
3-foot piece
1 gallon
Each size, each shipment
Each source
Not required if obtained from Potable Water Source or approved hydran
Manufacturer’s Certification Required
One (1)
40-inch length
One (1)
24 inch x 24 inch sample
Each size, each shipment
Each size, each shipment
See Specifications
See Specifications
See Specifications
See Specifications
See Specifications
See Specifications
3 of 4
Item #
94
95
96
Material or Product
Electrical Components
Sanitary Sewer
Potable Water
Minimum Size of Each Sample1
Minimum Frequency of Sampling
Test Required2
Remarks3
See Specifications
See Specifications
See Specifications
1. Reference to "SC" test method indicates SCDOT Standard Method of Test in accordance with Appendix C of the SCDOT Construction Manual found at the following location: http://www.scdot.org/doing/construction_Manual.aspx
2. "Approval Sheet" Refers to the SCDOT Qualified Products List found at the following location: http://info.scdot.org/Construction_D/sitePages/qualifiedProducts3.aspx
3. This Appendix shall be used as a supplement to the Specifications. In cases where the test method or frequency is inconsistent with the Specifications, the most stringent requirement applies
Appendix A
CIF16E010B
4 of 4
Download