ADDENDUM NO. 2 TO CONTRACT DOCUMENTS FOR REFRIGERATED CONTAINER SERVICE AREA WANDO WELCH TERMINAL MOUNT PLEASANT, SOUTH CAROLINA PROJECT NUMBER CIF16E010B SOUTH CAROLINA PORTS AUTHORITY 25 JULY 2016 General 1. This Addendum shall supplement, amend, and become part of the Bid Documents. All Bids and the Construction Contract shall be based on these modifications. 2. Bidders shall acknowledge the receipt of this addendum on their Bid Form. 3. The information contained in this addendum addresses Bidder’s questions received through 21 July, 2016. Specific The following revisions should be noted at the appropriate part of the Contract Documents and made a part thereof: I. Plans Sheet G-2; General Notes and Design Criteria: Add to note 4 under Miscellaneous Steel “Canopy structural steel shall be painted” Sheet S-8; Wash Station Rack Plan and Elevation: Add the following notes: 10. Miscellaneous fabrication not in contact with hydraulic fluid shall be HDG steel. Provide drip pan, Type 316 SS. 11. Provide standard industrial motor; hydraulic fluid shall be selected by final designer. CIF16E010B – Wando Welch Terminal – Refrigerated Container Service Area Addendum #2 Page 1 of 4 Addendum No. 2 12. In the event of power failure, the hydraulic system shall return to float mode and allow manual positioning in either open or closed position.” Sheet G-2; General Notes and Design Criteria: Replace note 3.0 under Cast-in-Place Concrete “All finished edges and corners that shall remain exposed at completion shall be chamfered ¾” unless noted otherwise.” Sheet C-7; Paving Details: Change detail 2 to show V-brace at top of perimeter fence, 3 strands barbed wire each side. Change tension wire to top bar. Sheet C-8; Traffic Control Plan – Sheet 1 of 2: Disregard the “end traffic barrier” call-out on the left hand side of the sheet. Sheet S-12; Misc. Structural Details: Disregard Note 2 on Sheet S-12. Sheet E-20; Misc. Structural Details: Callouts referencing E-41 and E-43 should reference E-31 and E-43, respectively. Sheet E-21; Lighting Plans: Add note to table that basis of design shall be “ALBEO by GE.” II. Specifications 1. Front End Specs a. Revised Bid Form Item IV b. Revised Table of Contents on page vi 2. Revised Technical Spec Table of Contents 3. Added section 26 01 10 Electrical General Requirements 4. Updated section 26 05 43 Underground Electrical Work 5. Added section 26 12 19 MV Transformers Section 32 13 11; PCC Paving: Replace paragraph 3.08 C with the following: “Prepare surface for mating with the new concrete at transverse construction joints (at end of pours) where a smooth bulkhead form was used. Surface shall be roughened by water blasting or mechanical means after the concrete has gained sufficient strength to be roughened. This may be assumed to be at the time of form removal.” Section 32 13 11; PCC Paving: Replace paragraph 3.08 B with the following: “Place joint filler which conforms to AASHTO M153 between paving components adjacent building components or other appurtenances. Fiber expansion joint filler conforming to ASTM D1751 is also acceptable for this application.” Section 32 13 11; PCC Paving: Add to paragraph 3.05: “The outer perimeter panel shall be tied with deformed bars in accordance with ACI 330. Section 32 13 11; PCC Paving: Replace paragraph 3.07 A with the following: “Concrete shall be placed in long strips with dowels placed through side forms or drilled and bonded (at construction joints) and in dowel baskets (at control joints) per the approved jointing plan. Dowel bar insertion for longitudinal joints (in slip form CIF16E010B – Wando Welch Terminal – Refrigerated Container Service Area Addendum #2 Page 2 of 4 Addendum No. 2 construction) may be utilized provided there is a demonstrated experience for the technique.” Section 32 31 13; PCC Paving: Change paragraph 2.01 to show that fence shall have barbed selvage required. Section 32 31 13; PCC Paving: Change paragraph 2.05 barbed wire requirement to require 6 strand on V arms. Section 32 31 13; PCC Paving: Change paragraph 2.07 to require top rail be used instead of a top tension wire. Section 32 31 13; PCC Paving: Change paragraph 3.01 B.1 for 10 ft. typical post spacing. III. A. Bidder Questions & Responses Question: Drawing 4V6-04 indicates the new security cameras are to be tied into building 449. Where is building 449 in relation to this project? Response: Building 449 is at the northeast guard gate, approximately 1,200 feet from the project site B. Question: Will the new cameras have to be integrated into the existing security system? If so, then please provide detailed information about the existing system for integration pricing. Response: Confirm that new cameras are to be integrated into the existing security system. Existing system is PureAcitv outdoor surveillance system by PureTech Systems: http://www.puretechsystems.com/pureactiv.html C. Question: Drawing S-8 calls out for the contractor to design and install a new hydraulic lift system for the wash canopy. Given there is only 150 days for this contract, is it really feasible to expect a design to be completed, approved, materials fabricated and installed, tested and operated in that time frame? Please considered extending the contract duration Response: The scope of final design is limited to the sizing of the HPU and controls, and detailing actuator assembly. It is considered that the contract time is sufficient assuming that design and fabrication proceeds in parallel with site work. The Owner will expedite submittal reviews to the extent necessary; contract duration cannot be extended for operational reasons. D. Question: Confirm the following finish requirements: Painted: Structural steel column, girders, rafters, bollards (yellow), roof decking (PVDF). Please specify the roof decking color. Galvanized: Anchor bolts, bolts, purlin. Please confirm nothing is to be both galvanized and painted. Response: Confirm the coating requirements as summarized. No items are to be both hotdip galvanized and painted, but note “galvalume” roofing material with PVDF coating. Color will be selected by Owner. CIF16E010B – Wando Welch Terminal – Refrigerated Container Service Area Addendum #2 Page 3 of 4 Addendum No. 2 E. Question: Please advise if it is acceptable to replace the utilidor chase with RCP, PVC, Iron pipe, or a precast concrete chase. The existing utilidor design appears to be cast in place which will require multiple pours and time consuming formwork. We feel a prefabricated unit will provide the same utility in a reduced time. If this is acceptable please advise what area the cross section of the chase needs to be. Response: Such substitution may be proposed as part of final design of the hydraulic system. In principle the Owner is not opposed. The cross sectional area shall be sufficient for installation and future maintenance of hydraulic lines/hoses; the area indicated shall be considered a minimum unless final designer can justify otherwise. F. Question: Will the installed wick/earthquake drains be below the bottom of subgrade? If not, who is responsible for repair if they are damaged during excavation? Response: It is understood that the portion of the wick drain in the referenced area will be damaged during construction. No repair will be required. G. Question: Is the surcharge good structural fill material or is it waste ie. Gumbo material Response: Surcharge material is approximately 50% select granular fill and 50% common fill with plastic fines. None of the surcharge is considered to be waste material. H. Question: Could not locate appendix A Response: See Addendum no. 2 documents for Appendix A. End of Addendum No. 2 CIF16E010B – Wando Welch Terminal – Refrigerated Container Service Area Addendum #2 Page 4 of 4 BID Dated Submitted By (Company Name) South Carolina Ports Authority Post Office Box 22287 Charleston, SC 29413-2287 Attention: Mr. Tim Connor Procurement Manager Gentlemen: Having carefully examined the Instructions to Bidders, the General and Special Conditions of the Contract, the Specifications, and the Drawings for Refrigerated Container Service Area, Mount Pleasant, South Carolina, Project No. CIF16E010B, dated April 2016, as well as the premises and conditions affecting the work, the undersigned proposes to furnish all materials, labor, equipment, tools, and other things necessary for the execution of the work covered by the said Specifications and Drawings, for the following price: BIDDERS MUST COMPLETE ALL ITEMS I.Mobilization / Demobilization A. Mobilization / Demobilization Lump Sum (Not to Exceed 2% of Bid) $ II. Site Work A. B. C. D. E. F. Remove and Stockpile Existing Surcharge 45,000 CY @ $ /CY $ Proof Roll Subgrade 31,500 SY @ $ $ /SY Allowance for Undercutting & Backfill 3,500 CY @ $ /Cy $ Crushed Rock Base 10,500 CY @ $ /CY $ 10” PCC Paving 31,500 SY @ $ /SY $ Permanent Pavement Marking B-1 (CIF16E010B) 12,000 LF @ $ G. H. I. J. K. L. III. /LF $ Traffic Barriers, and Curbs Lump Sum $ Chain Link Fence 1,950 LF @ $________/LF $ Storm Drain System Lump Sum $ Water Distribution Lump Sum $ Sanitary Sewer Lump Sum $ Erosion and Sediment Control Lump Sum $ Structures A. B. C. Genset Service Canopy Lump Sum $ Wash Station Canopy Lump Sum $ Wash Rack Platform Lump Sum $ IV. Electrical A. Medium Voltage Transformer including: 1). 225 KVA pad mounted transformer including rubber goods, elbow surge Arresters, inserts, and stand-off insulators with caps. 1 EA Material @ $_________/ EA $_____________ 1 EA Labor @ $___________/ EA $_____________ 2). Ground ring including jumpers, exothermic welds, ground rods, excavation and backfill. 1 EA @ Lump Sum $_____________ 3). Equipment pad for transformer and service equipment. 1 EA @ Lump Sum $_____________ 4). All other associated work not identified above Lump Sum $_____________ Total Item A Lump Sum …………………………………………… $_____________ B-2 (CIF16E010B) B. 15Kv Underground Power including: 1). 15kV shielded wire, #2 AWG, EPR, copper from switch K12-1 to primary of transformer. _______LF wire @ $_________LF $_____________ Labor @ Lump Sum $_____________ 2). #2, 600V primary neutral, XHHW, copper from switch K12-1 to transformer. _______LF wire @ $_________LF $______________ Labor @ Lump Sum $_____________ 3). 2W4 underground duct bank including excavation, 4” PVC ducts, concrete encased with reinforcement, ground wire, warning tape, backfill and compaction. ________LF@ $__________ LF $_____________ 4). Connect new ducts to existing manhole. Lump Sum $_____________ 5). Pump manholes and confined space entry into manholes Lump Sum $_____________ 6). Clean and mandrel ducts and provide pull string. Lump Sum $_____________ 7). 15kV terminations. Labor and materials. Lump Sum $_____________ 8). Replace fuses at switch K12-1 3 EA @ $_________EA $_____________ 9). RGS 4” elbow turn ups with bitumen coating Lump Sum $_____________ 10). All other associated work not identified above Lump Sum $_____________ Total Item B Lump Sum……… ………………………… …... $_____________ C. 600 Volt Service Entrance including: 1). 4” RGS conduits from transformer secondary to panelboard HV including elbows and fittings, trenching, backfill and compaction. Lump Sum $_____________ 2). 500KCM, XHHW, copper service entrance wire ______LF wire @ $ ________LF $_____________ Labor @ Lump Sum $_____________ 3). 250KCM, XHHW, copper neutral ______LF wire @ $ ________LF $_____________ Labor @ Lump Sum $_____________ 4). Terminations for service entrance wires. Lump Sum $_____________ 6). Megger test service conductors. Lump Sum $_____________ 7). All other associated work not identified above. Lump Sum $______________ Total Item C Lump Sum ………………………………………..$______________ B-3 (CIF16E010B) D. Secondary Electrical including: 1). Light Fixtures. Labor and material. 38 Ea @ $ _________EA $______________ 2). Disconnect switches, NEMA 3R. Labor and material. 9 Ea @ $__________EA $______________ 3). Disconnect switch, explosion proof. Labor and material. 1 EA @ $_________EA $______________ 4). 120VAC receptacles, boxes and covers. Labor and Material. 6 EA @ $ _________EA $______________ 5). Panelboard HV, 3R, SS. Labor and Material 1 EA @ $_________EA $______________ 6). Panelboard LV, 3R, SS. Labor and material 1 EA @ $_________EA $______________ 7). Service equipment support stand, galvanized steel Lump Sum $______________ 8). Dry type 30KVA transformer. Labor and material 1 Ea @ $__________EA $______________ 9). Low voltage ductbank service laterals, concrete encased and reinforced. Includes excavation, backfill, compaction and warning tape. Lump Sum $______________ 10). All service lateral circuit conductors. Labor and material. Lump Sum $______________ 11). All branch circuits lighting and power / conduit and wire. Labor and material. Including megger tests of circuit wiring. Lump Sum $______________ 12). All other associated work not identified above. Lump Sum $______________ Total Item D Lump Sum……………………………………….………$______________ E. Electrical Testing Including: 1). Acceptance tests for pad mounted MV transformer. 1 Ea @ $________EA 2). 15kV cable and terminations: High Potential VLF tests. Lump Sum 3). Ground tests. Lump Sum 4). All reports Lump Sum 5). All other associated work not identified above. Lump Sum $______________ $______________ $______________ $______________ $______________ Total Item E Lump Sum……………………………………………… $______________ V. Low Voltage Electrical and Communication A. Direct Bury Ductbank 2W2 Power, 2W2 Security w/ Trenching and Repair B-4 (CIF16E010B) 1,900 LF @ $_______________ /LF $_______________ B. Split Power/Security Handholes 12 EA @ $_______________ /EA $_______________ C. Security Lighting Fixture Type “S” 12 EA @ $_______________ /EA $_______________ D. Field Distribution Box (FDB) w/ Backplate 1 EA @ $_______________ /EA $_______________ E. Device Interface Box (DIB) w/ Backplate 7 EA @ $_______________ /EA $_______________ F. Camera Power Box (CPB) w/ Backplate 8 EA @ $_______________ /EA $_______________ G. Ground Rods w/ Conductor, Welds and Connections 12 EA @ $_______________ /EA $_______________ H. 6-Strand Single Mode Fiber (including termination and testing) Lump Sum $_______________ I. 24-Strand Single Mode Fiber (including termination and testing) Lump Sum J. Power Conductor Cabling and Termination Lump Sum $_______________ $_______________ VI. Video Surveillance System A. Camera/Light Pole Base and Foundation 12 EA @ $_______________ /EA $_______________ B. Camera/Light Pole 12 A @ $_______________ /EA $_______________ C. Fixed AXIS IP dome cameras without analytics 12 A @ $_______________ /EA $_______________ D. PTZ AXIS IP dome cameras without analytics 2 EA @ $_______________ /EA $_______________ E. Field Distribution Box (FDB) 1 EA @ $_______________ /EA $_______________ F. Device Interface Box (DIB) B-5 (CIF16E010B) 7 EA @ $_______________ /EA $_______________ G. Camera Power Boxes (CPB) 8 EA @ $_______________ /EA $_______________ H. Cisco Small Form-Factor Pluggable (SFP) Modules Lump Sum $_______________ I. Small Form-Factor Pluggable (SFP) Modules for Industrial Field Switches Lump Sum $_______________ J. Connectors and Cabling Lump Sum $_______________ K. Update Head-End System and Recorders to include new cameras/locations Lump Sum $_______________ L. Camera Licensing Lump Sum $_______________ M. Additional Video Storage to maintain 30 days of Recorded Video Lump Sum $_______________ N. Contractor Field Testing Lump Sum $_______________ O. Performance Verification Testing Lump Sum $_______________ P. Endurance Testing Lump Sum $_______________ Q. Restricted Area Signs at New Perimeter 18 EA @ $_______________ /EA $_______________ R. Zone Signs at New Perimeter 5 EA @ $_______________ /EA $_______________ IV. Miscellaneous A. All Other Work Not Included Above Lump Sum B-6 (CIF16E010B) $ Section Safety Requirements Use of Explosives Protection of Persons and Property Hazardous Substances 40 41 42 Miscellaneous Requirements Supplemental Data Correlation and Intent of the Contract Documents Record Drawings Disposal of Materials Off the Owner’s Property Utilization of Port Facilities List of Contractors, Subcontractors & Material Suppliers 43 44 45 46 47 48 Special Requirements – Charleston Naval Base Container Terminal Air Quality Noise Pollution Potential Hazardous Substance – Minimum Mitigation Measures Spill Prevention and Cleanup Plan Protection of Manatees Additional Insurance Coverage Bainbridge Avenue Requirements Property Insurance Adjustment 49 50 51 52 53 54 55 56 SPECIFICATIONS DIVISION 02 – EXISTING CONDITIONS Section 02 92 00 - Erosion & Sediment Control DIVISION 03 - CONCRETE Section 03 10 00 - Concrete Formwork Section 03 20 00 - Concrete Reinforcement Section 03 30 00- Cast-in-Place Concrete Section 03 60 00 - Grout DIVISION 5 - METALS Section 05 40 00 - Light Gage Metal Framing Section 05 50 00 - Metal Fabrications DIVISION 9 - FINISHES Section 09 96 00 - High Performance Coatings (continued) v (CIF16E010B) SPECIFICATIONS (continued) DIVISION 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements Section 26 05 00 – Common Work Results for Electrical Systems Section 26 05 13 - Medium Voltage Cables Section 26 05 26 - Grounding and Bonding for Electrical Systems Section 26 05 29 - Hangers and Supports for Electrical Systems Section 26 05 33 - Raceways and Boxes for Electrical Systems Section 26 05 43 - Underground Electrical Work Section 26 05 26 - Grounding and Bonding for Electrical Systems Section 26 05 48 - Vibration and Seismic Controls for Electrical Systems Section 26 05 53 - Identification for Electrical Systems Section 26 12 19 - Medium Voltage Transformers Section 26 22 00 - Low Voltage Transformers Section 26 24 16 – Panelboards Section 26 56 00 – Exterior Lighting DIVISION 27 - COMMUNICATIONS Section 27 00 00 – Communications DIVISION 28 – ELECTRONIC SAFETY AND SECURITY Section 28 23 23 – Perimeter Security – Video Surveillance System DIVISION 31 - EARTHWORK Section 31 23 00 - Earthwork DIVISION 32 – SITE WORK Section 32 11 23 – Crushed Rock Base Section 32 13 11 – PCC Paving Section 32 31 13 – Chain-Link Fence DIVISION 33 – UTILITIES Section 33 10 00 – Water Distribution Section 33 30 00 – Sanitary Sewer Section 33 40 00 – Storm Drainage APPENDICES I. Soils Data vi (CIF16E010B) South Carolina State Ports Authority Wando Welch Terminal Contract No. CIF16E010B Refrigerated Container Service Area Site Development Technical Specifications Table of Contents No. of Pages Section 02 92 00 – Erosion and Sediment Control .............................................................2 03 10 00 – Concrete Formwork ..............................................................................5 03 20 00 – Concrete Reinforcement ......................................................................5 03 30 00 – Cast-in-Place Concrete .........................................................................9 03 60 00 – Grout.......................................................................................................3 05 40 00 – Light Gage Metal Framing....................................................................6 05 50 00 – Metal Fabrications................................................................................5 09 96 00 – High-Performance Coatings .................................................................4 26 01 10 – Electrical General Requirements……………………………………………...10 26 05 00 – Common Work Results for Electrical………………………………………….5 26 05 19 – Low Voltage Electrical Power Conductors and Cables ......................4 26 05 26 – Grounding and Bonding for Electrical Systems ..................................6 26 05 29 – Hangers and Supports for Electrical Systems ....................................2 26 05 33 – Raceways and Boxes for Electrical Systems ......................................6 26 05 43 – Underground Electrical Work...............................................................6 26 05 48 – Vibration and Seismic Controls for Electrical Systems .....................6 26 05 53 – Identification for Electrical Systems ...................................................5 26 12 19 – Medium Voltage Transformers.............................................................5 26 22 00 – Low Voltage Transformers....................................................................6 26 24 16 – Panelboards...........................................................................................8 26 56 00 – Exterior Lighting....................................................................................7 27 00 00 – Communications .................................................................................12 28 23 23 – Perimeter Security – Video Surveillance System.............................27 31 23 00 – Earthwork ..............................................................................................9 32 11 23 – Crushed Rock Base...............................................................................7 32 13 11 – PCC Paving ............................................................................................9 32 31 13 – Chain Link Fence ..................................................................................4 33 10 00 – Water Distribution.................................................................................5 33 30 00 – Sanitary Sewer ......................................................................................8 33 40 00 – Storm Drainage ...................................................................................10 END OF SECTION DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements SECTION 26 01 10 ELECTRICAL GENERAL REQUIREMENTS PART 1 – GENERAL 1.1 SUMMARY Work under this section includes requirements that apply to all electrical sections and includes general requirements for labor, materials and equipment specified in the electrical specifications. The contractor shall furnish all labor, equipment and incidental items necessary to complete the work as indicated on the project drawings and as specified herein. 1.2 RELATED DOCUMENTS A. General: 1. Requirements of the General and Supplemental Conditions apply to all work in this section. Provide all labor, material, equipment, and services indicated on the drawings or specified herein or reasonably necessary for and incidental to a complete job. B. Application: 1. This section applies to all electrical sections of this project except as specified otherwise in the individual sections. C. Electrical Drawings: 1. Except where dimensions are specifically indicated, electrical drawings are schematic in character, and must not be scaled. It is the Contractor’s responsibility to fit the work to the job carefully; to investigate the civil and structural drawings affecting this work, and arrange the work accordingly, furnishing necessary bends, offsets, fittings, and junctions, whether specifically shown or called for or not. 2. Drawings and Specifications shall be considered as supplementary one to the other, so that materials and labor indicated, called for, or implied by the one and not by the other, shall be supplied and installed as though specifically called for by both. 1.3 QUALITY ASSURANCE A. Materials and Equipment: 1. All materials and apparatus required for the work shall be new of first-class quality, and shall be furnished, delivered, erected, connected and finished in every detail, and shall be so selected and arranged as to fit properly on the site. Where no specific kind of quality of material is given, a first-class standard article as approved by the Owner/Engineer shall be provided. South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-1 Epic Engineering 15621 June 2016 DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements 2. B. Basis of Design: 1. C. 1.4 Specification and drawing reference to equipment, product, fixture, or material name, make or catalog number, shall be interpreted as establishing a minimum standard of quality and shall not be construed as limiting competition. The Contractor may, at his option, use any equipment, product, material, fixture, form or type of construction which, in the opinion of the Owner/Engineer, expressed in writing, is equal to that specified. Where specified makes or brands are listed for specific items in the Specifications, and/or as scheduled or shown on the Drawings, the item detailed and shown constitutes the basis of design. All other makes or brand items listed in these Specifications, or approved, must be checked for proper connections, capacities and dimensions before submitting shop drawings to assure total compliance with the Specification details. Variances in space requirements, capacity, connections, and construction details are adequate reasons for disapproval. Codes, Rules, Permits, and Fees: 1. The Contractor shall give all necessary notices, obtain all permits and pay all sales taxes, fees and other costs, including utility connections or extensions, in connection with his work. He shall also file all necessary drawings, prepare all documents and obtain all necessary approvals of all governmental departments having jurisdiction. He shall obtain all required certificates of inspection for his work and deliver same to the Owner/Engineer before request for acceptance and final payment for the work. 2. The Contractor shall include in the work, without extra cost to the Owner, any labor, materials, services, apparatus, drawings, etc., in order to comply with all applicable laws, ordinances, rules and regulations, whether or not shown on Drawings and/or specified. SUBMITTALS A. Product Data: The Owner/Engineer reserves the right to reject any product or brand that conforms to these specifications, but may not be of the quality intended for this work. B. Submit shop drawings and/or data sheets for approval on all items of equipment, materials, and accessories furnished under this Division whether specifically listed below or not. Shop drawings and Specification Data Sheets shall show complete product information, installation requirements, details and instructions, and shall be marked to indicate compliance with requirements of contract documents. C. Specific items requiring submittals shall be as specified in each individual section of this Division; Shop drawings shall be submitted and approved before procurement, fabrication, or delivery of such items to the job site. Partial submittals are not acceptable; such submittals will be returned without review. D. Prepare shop-drawing submittals with identification by Specification Section and Article. Clearly mark the particular make, model number, accessories, and options. Shop drawings shall show types, sizes, accessories, elevations, floor plans, sectional views, installation details, elementary diagrams, and wiring diagrams. Wiring diagrams shall identify circuit terminals and shall indicate the internal wiring for each item of equipment South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-2 Epic Engineering 15621 June 2016 DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements and the interconnection between the items. Drawings shall also indicate adequate clearance for operation, maintenance, and replacement of operating equipment devices. If any equipment is disapproved, the drawings shall be revised to show acceptable equipment and be resubmitted. 1.5 E. Submittals for each manufactured item shall be manufacturer’s descriptive literature, equipment drawings, diagrams, performance and characteristic curves, and catalog cuts. Each submittal shall include the manufacturer’s name, trade name, catalog model or number, nameplate data, size, layout dimensions, capacity, Specification reference, applicable industry specification references, and all other information necessary to establish contract compliance. F. When materials or equipment must conform to the standards of organizations such as the American National Standards Institute (ANSI), American Society for Testing and Materials (ASTM), National Electrical Manufacturers’ Association (NEMA), and Underwriters’ Laboratories (UL), proof of such conformance shall be submitted to the Owner/Engineer for approval. If an organization uses a label or listing to indicate compliance with a particular standard, the label or listing will be acceptable evidence, unless otherwise specified in the individual sections. In lieu of the label or listing, the Contractor shall submit a certificate from an independent testing organization which is competent to perform acceptable tests and is approved by the Owner/Engineer. The certificate shall state that the item has been tested in accordance with the specified organization’s test methods and that the item conforms to the specified organization’s standard. For material and equipment whose compliance with organizational standards or specifications is not regulated by an organization using its own listing or label as proof of compliance, a certificate of compliance from the manufacturer shall be submitted for approval. The certificate shall identify the manufacturer, the product, the referenced standard, and shall simply state that the manufacturer certifies that the product conforms to all requirements of the Specifications and of the referenced standards listed. G. Certified Test Reports: Before delivery of materials and equipment, certified copies of all test reports specified in the individual sections shall be submitted for approval. H. Independent Testing Organization Certificate: In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Owner/Engineer. The certificate shall state that it has been tested in accordance with the specified organization’s test methods and that the item complies with the specified organization’s reference standard. I. Setting Drawings and Templates: Furnish all necessary templates, patterns, etc., for installing work and for the purpose of making adjoining work conform; furnish setting drawings and shop details to other trades as required. IDENTIFICATION A. Manufacturers’ Nameplates: Each major component of equipment shall have manufacturer’s name, address, model number and rating on a plate securely affixed in a conspicuous place. Nameplate of a distributing agent will not be acceptable. Code ratings, or other data, which is die-stamped into surface of equipment, shall be stamped in an easily visible location. South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-3 Epic Engineering 15621 June 2016 DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements B. C. Labels: Provide engraved Bakelite labels for all equipment furnished under this Division. Provide labels which indicate the name and function of each item. Where two or more pieces of equipment of the same model, type and capacity are furnished, identify each piece as No.1, No. 2, etc., in addition to the name of the equipment. 1. Label Size: 1” high, minimum; 1/16” thick, minimum. 2. Lettering: Gothic style, upper case, ½” high. 3. Color: Black letters on white background. 4. Method of Attachment: Minimum of two brass screws or pop rivets. Cable tags in manholes, transformers, and fused switch cabinets: Provide tags for each cable or wire. Tag new wire and cable provided by this contract. The tags shall be polyethylene. Do not provide handwritten letters. 1. 1.6 Polyethylene Cable Tags: Provide tags of polyethylene that have an average tensile strength of 4500-lbs./sq. in.; and that are 0.035” thick, non-corrosive nonconductive; resistive to, alkalis, organic solvents, and salt water; and distortion resistant to 300° F. Provide a one-piece nylon, self-locking tie at each end of the cable tag. Ties shall have a minimum loop tensile strength of 175 lbs. The cable tags shall have block letters, numbers and symbols 1” high on a yellow background. Letters, numbers, and symbols shall not fall off or change positions regardless of the cable tags’ orientation. PRODUCT DELIVERY AND STORAGE General: Equipment and materials shall be properly stored, adequately protected, and carefully handled to prevent damage before and during installation. Equipment and materials shall be handled, stored, and protected in accordance with the manufacturer’s recommendations and as approved by the Owner/Engineer. Electrical conduit shall be stored to provide protection from the weather and accidental damage. Plastic conduit shall be stored on even supports and in locations not subject to direct sunrays, or excessive heat. Cables shall be sealed, stored, and handled carefully to avoid damage to the outer covering or insulation and damage from moisture and weather. Damaged or defective items, in the opinion of the Owner/Engineer, shall be replaced with new items at no additional cost to the Owner. 1.7 INDEPENDENT TESTING FIRM A. The testing firm shall provide a Registered Professional Engineer to interface with the installing Contractor and the Owner. Testing technicians will be provided as required to do the work under approved schedules. Designated equipment shall be tested to verify operation and adjustment. Reports shall be issued documenting checks and test results. B. Services: The testing firm shall provide the following services: 1. Cable tests - Hi Pot VLF pass / fail cable tests only. Megger tests may be performed by the Electrical contractor. 2. Cable termination tests - Hi Pot only. Megger tests may be performed by the Electrical contractor South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-4 Epic Engineering 15621 June 2016 DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements B. C. Qualification of Testers: 1. The testing firm shall have technicians with two or more years experience related to the testing of equipment designated herein. They shall be able to identify suitable engineering and technical resources to complete the work under approved schedules. 2. The supervising engineering representative shall have extensive knowledge of the products involved and at least two years experience in conducting similar tests. All testing shall be conducted under the direct supervision of the Registered Professional Engineer. The supervising engineer representative will prepare, seal, date and sign reports and be available for consultation with the Owner/Engineer. 3. Testing technicians shall be trained and experienced in the testing they conduct. Submit testing personnel resumes for approval prior to testing. 4. Submit certification of the Testing Firm’s qualifications for approval. The certification shall include the training and experience of the individuals performing the tests required in the individual specification sections and on the drawings. Equipment: 1. D. Testing equipment required to conduct the specified tests shall be furnished by the testing organization unless noted otherwise. Testing equipment shall be in good working order and comply with the requirements of applicable industry standards. Reports: 1. The testing firm shall utilize comprehensive report forms to document test results on all equipment and products. Upon completion of the work, the report forms shall be sealed, dated and signed by the Registered Professional Engineer and included in the final report. Report forms shall identify equipment by model number or by customer’s identification number (where assigned). Report forms shall be suitable for reproduction on normal office copying machines. Sample forms shall be submitted for review by the Owner/Engineer. 2. Testing shall be done in accordance with the manufacturer’s instructions, these Specifications and applicable NEMA, ASA, ASTM and NETA Standards. All over potential-testing values shall be approved by the Owner/Engineer prior to such tests. 3. The testing firm shall collaborate with the manufacturer’s representative during testing as required. PART 2 – PRODUCTS 2.1 CATALOGED PRODUCTS Materials and equipment shall be cataloged projects of manufacturers regularly engaged in production of such materials or equipment and shall be manufacturer’s latest standard design that South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-5 Epic Engineering 15621 June 2016 DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements complies with the Specification requirements. When two or more units of the same type, class, and size of equipment are required, these units shall be products of a single manufacturer; however, the component parts of the system need not be the products of the same manufacturer. Each major component of equipment shall have the manufacturer’s name, address, and the model and serial number on a nameplate securely affixed in a conspicuous place; the nameplate of the distributing agent will not be acceptable. PART 3 – EXECUTION 3.1 3.2 INSPECTION AND COORDINATION A. General: Examine the areas and conditions under which electrical work will be installed and notify the Owner/Engineer in writing of conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected in an acceptable manner. B. Coordination: Electrical work shall be coordinated with other trades involved in the construction project. All work shall be carefully laid out in advance, coordinating electrical features with structural and civil features of construction. C. Cooperation with Other Trades: 1. Closely schedule work so that it is installed at the proper time and phase without delaying the completion of the entire project. 2. If the work is installed before coordinating with other trades or so as to cause interference with work of other trades, or cause unacceptable clearance problems, make necessary changes in work to correct the condition without extra charge. 3. Symbols, section details, and wiring diagrams are used in conjunction with drawings and specifications to define the work. Reference to any item on the drawings shall be construed as being the same as having that item fully developed on the drawing. All work and material shall be installed in accordance with the details and diagrams with any necessary accessories and modifications to adapt the typical detail to actual field conditions. All such modifications shall be approved by the Owner/Engineer prior to installation. SPECIAL REQUIREMENTS A. General: Provide all wiring and connections and miscellaneous accessories necessary for the complete installation of and final connections to equipment. Make all final connections to such, including installation of all special devices furnished with such equipment. B. Supervision: Provide the services of an experienced Superintendent, who shall be constantly in charge of the installation of the work, together with all skilled workmen required to unload, transfer, erect, connect-up, adjust, start, operate, and test each system. The Superintendent shall be qualified and authorized to make decisions and answer questions put by the Owner/Engineer regarding progress and details of the work. C. .Manufacturer’s Recommendations: Where installation procedures are specified to be in accordance with the recommendations of the manufacturer of the material or equipment South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-6 Epic Engineering 15621 June 2016 DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements being installed, printed copies of these recommendations shall be furnished to the Owner/Engineer prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material. 3.3 D. Start-up: No system shall be started up without a prior inspection by the Owner/Engineer to assure that all safety devices have been installed and that installation complies with the Specifications. E. Owner-Furnished Equipment: There is no Owner furnished equipment. INSTALLATION, GENERAL A. Excavation and Backfill: Perform all excavation and backfill in accordance with Specifications. Unless otherwise indicated, bury all underground ducts a minimum of 32” deep. Excavation for underground duct bank shall be dug at least wide enough to accommodate the duct plus 6” around and 32” deep. The trench shall further be backfilled and compacted so that proper grade is obtained. Excess earth shall be removed from the project site. B. Foundations and Supports: Concrete work for foundations, supports, bases, etc., required for equipment provided under this Division of the work shall be provided under this Division in accordance with Section 03 30 00, Cast-In Place Concrete. Provide all necessary anchors, bolts, etc., for foundations, supports, pads, and bases required for the support of all equipment furnished under this Division of the work. C. Cutting and Patching: 1. Perform all cutting and patching required for equipment. If cutting is done due to failure to perform preliminary roughing work, this work shall be performed at no additional cost to Owner. 2. All work and material furnished shall be installed in such a manner that no undue cutting and patching will be required in the construction. Materials shall be installed in the various portions of the project as the construction of same progresses and shall not, in any way or manner, delay the construction of the project. 3. Furnish, locate and install all sleeves and inserts required before the structures are built. Cutting and patching required for conduit where sleeves and inserts were not installed, or where incorrectly located, shall be performed at no additional cost to the Owner. 4. No structural members shall be cut without the approval of the Owner/Engineer and all such cutting shall be done in a manner directed by him. 5. Any cutting or patching or repairing of rough or finished work that may be necessary by the failure to cooperate with other trades in obtaining the proper space conditions for the installation of his work shall be performed by this Division. South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-7 Epic Engineering 15621 June 2016 DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements 6. D. Rigging and Hoisting: Provide all rigging and hoisting, and services necessary for erection, and/or delivery into the premises, of any equipment and apparatus furnished. Remove same from the premises when no longer required. E. Covering of Work: No conduit, fitting, or other work of any kind shall be covered up or hidden from view before it has been examined or approved by the Owner/Engineer and/or other authority having jurisdiction over same. Any faulty or imperfect work or materials which may be discovered shall be removed and corrected immediately after being condemned and other work and materials shall be provided to the satisfaction of the Owner/Engineer. F. Waterproofing: Where any work pierces waterproofing, including waterproof concrete, the method of installation shall be as approved by Owner/Engineer before work is done. Provide all necessary sleeves and caulking required to make opening absolutely watertight. G. Accessibility: H. 3.4 No cutting that may impair strength of construction shall be done. No holes, except for small screws, may be drilled in structural members without obtaining prior approval. All work shall be done in a neat manner by mechanics skilled in their trades and as approved by the Owner/Engineer. 1. Coordinate work with other trades whose work is in the same spaces, and advise all trades of requirements. Such spaces and clearances shall, however, be kept to the minimum size required. 2. All equipment which must be serviced, operated or maintained shall be located in fully accessible positions. Equipment shall include, but not be limited to motors, miscellaneous outlet boxes, etc. Minor deviations from the Drawings may be made to allow for better accessibility, but changes of magnitude or which involve extra cost to the Owner shall not be made without approval from the Owner/Engineer. Clearances: Minimum clearances in front of, or around equipment shall conform to the latest applicable code requirements, the requirements of the equipment manufacturer, or as shown on drawings, whichever is greater. EQUIPMENT INSTALLATION A. General: 1. Obtain services of all manufacturers’ representatives of major equipment at site during erection or construction of their respective equipment to ensure proper installation of same. Letters will be required from each manufacturer certifying that equipment has been checked and is properly installed and operating. Letter shall include the name of the representative and the date the equipment was checked. South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-8 Epic Engineering 15621 June 2016 DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements 2. B. 3.5 3.6 Where necessary, arrangements shall be made to bring items to the ultimate location in pieces, or otherwise disassembled, and then to assemble them in place. All necessary flanges, studs, etc., for matching alignment and field assembly shall be provided by the manufacturer. Testing: Arrangements shall be made for a field test of the equipment after assembly. The above mentioned field tests shall be in addition to all factory tests, shop tests and final tests and adjustments. IDENTICATION A. Nameplates: All controls and equipment shall be clearly identified with nameplates, identifying each item, of laminated phenolic compound, engraved to show black letters on white background. All labels shall be permanently fastened to the items they identify. B. Cable Tag Installation: Install cable tags to identify cables installed under this contract. Locate the tags so that they are clearly visible without disturbing any cabling or wiring. PAINTING General: Electrical material and equipment shall be furnished factory primed and painted in accordance with the manufacturer’s standard specifications and color. After installation of equipment, the Contractor shall clean and repaint all surfaces as required where damaged due to shipment and/or installation. Use manufacturer’s stand color, unless noted otherwise on the drawings or in these specifications. 3.7 FINAL INSPECTION A. General: Arrange and schedule final inspection of work at the completion of each phase and at final acceptance of the project. Notify the Owner/Engineer in writing that the work has been thoroughly checked and is ready for inspection/acceptance. B. Certificates: On completion of the work, obtain certificates of compliance, approval or acceptance from all authorities having jurisdiction over the work and deliver these certificates to the Owner. The work shall not be deemed to have reached a state of completion until the certificates have been delivered. C. Protection: 1. Protect the work and material of all trades from damage by the Contractor’s work or workmen, and make good all damage thus caused. 2. Responsibility for work and equipment shall remain under this Division until finally inspected, tested and accepted. Protect work against theft, injury or damage and carefully store material and equipment received on site which is not immediately installed. Close open ends of work with temporary covers or plugs during construction to prevent entry of obstructing material. South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-9 Epic Engineering 15621 June 2016 DIVISON 26 - ELECTRICAL Section 26 01 10 – Electrical General Requirements PART 4 – COMPENSATION 4.1 MEASUREMENT AND BASIS OF PAYMENT No separate payment will be made for this work. The work is considered subsidiary to the applicable line items of the Total Bid. South Carolina Ports Authority - Wando Welch Terminal CIF16E010B - Refrigerated Container Service Area 26 01 10 CIF12EU01 26 0110-10 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work SECTION 26 05 43 UNDERGROUND ELECTRICAL WORK PART 1 - GENERAL 1.1 SUMMARY Work under this section includes requirements for materials and installation of underground duct banks and electrical power cables, splices and terminations. The Contractor shall provide all labor, materials, equipment and incidental items necessary for a complete underground duct and power cable system. 1.2 1.3 RELATED DOCUMENTS A. General: Requirements of the General and Supplemental Conditions apply to all Work in this section. Provide all labor, material, equipment, and services indicated on the Drawings or specified herein or reasonably necessary for all incidentals to a complete job. B. General Requirements: Section 26 01 10, Electrical General Requirements, applies to this section, with the additions and modifications specified herein. REFERENCES The Contractor shall accomplish the work in accordance with the reference documents except as modified in the contract documents. The Contractor shall consider all advisory language or recommended practices to be mandatory. A. ASTM D1556 Density and Unit Weight of Soil in Place by the Sand-Cone Method B. ASTM D1557 Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft (2,700 kN-m/m)) C. ASTM D2922 Density of Soil and Soil Aggregate in Place by Nuclear Methods (Shallow Depth) D. ANSI C2 National Electrical Safety Code (NESC) E. IEEE 48 Standard Test Procedures and Requirements for High Voltage Alternating Current Cable Terminators F. IEEE 386 Separable Insulated Connector Systems for Power Distribution Systems above 600-Volt G. IEEE 404 Cable Joints for Use with Extruded Dielectric Cable Rated 5000V Through 46000V and Cable Joints for Use with Laminated Dielectric Cable Rated 2500V Through 500,000V South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -1 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work 1.4 H. NEMA WC8 Ethylene-Propylene-Rubber Insulated Wire and Cable for the Transmission and Distribution of Electrical Energy (ICEA S68-516) I. NEMA TC2 Electrical Plastic Tubing (EPT) and Conduit (EPC-40 and EPC-80) J. NEMA TC3 PVC Fittings for Use with Rigid PVC Conduit and Tubing K. NEMA TC6 ABS and PVC Plastic Utilities Duct for Underground Installation L. NFPA 70 National Electrical Code (NEC) M. UL 6 Rigid Metal Electrical Conduit N. UL 83 Thermoplastic Insulated Wire and Cables O. UL 510 Insulating Tape P. AEIC C56 Ethylene-Propylene Rubber Insulated Shielded Power Cable Rated 5-69 kV SUBMITTALS A. Submit the following in accordance with the Special Conditions outlined in the General Requirements of the Contract. The Owner/Engineer reserves the right to reject any product or brand that conforms to these specifications, but may not be of the quality intended for this work. B. Catalog Information: Submit the following for approval: 1. Conduit (each type) 2. Insulating Tape 3. Medium Voltage Cables (each type) 4. Medium Voltage Terminating Kits and Splices (each type) 5. Terminator Connector 6. Cable Lubricants 7. 600-Volt Cable Splice Kits and Connectors 8. Ground Cable 9. 600-Volt Power Cable 10. Medium Voltage End Caps South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -2 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work C. Manufacturer's Instructions: Submit the following for approval: 1. D E Splice/Terminator Manufacturer's Installation Instructions Certificates; Material and Equipment: Provide manufacturer's statement certifying that the product supplied meets or exceeds contract requirements. 1. Medium voltage cable. 2. Medium voltage terminator/splicer. Certificates; Workmen's Competency: 1. Submit medium voltage terminator's cable certificate of competency. 2. Certification of the qualification of the cable splicer/terminator shall be submitted, for approval, 30 days before terminations are to be made in medium voltage 15 kV cables. The certification shall include the training, and experience of the individual on the specific type and classification of cable to be provided under this Contract. The certification shall indicate that the individual has had three or more years recent experience splicing and terminating medium voltage cables. The certification shall also list a minimum of three terminations that have been in operation for more than one year. In addition, the individual may be required to perform a dummy or practice termination/splice in the presence of the Owner/Engineer, before being approved as a qualified cable splicer. If that additional requirement is imposed, the Contractor shall provide short sections of the approved types of cables along with the approved type of kit, and detailed manufacturer's instructions for the cable. The Owner reserves the right to require additional proof of competency or to reject the individual and call for certification of an alternate cable Terminator/Splicer. 3. Certificates: High Potential Cable Test Reports: Prior to placing cables in service, all high potential test results shall be approved by the Owner/Engineer. PART 2 - PRODUCTS 2.1 MATERIALS AND EQUIPMENT General: Provide materials and equipment listed by UL or approved by Factory Mutual (FM) System, when such equipment is listed or approved. 2.2 CONDUIT AND TAPE A. General: Provide conduit and fittings conforming to UL. B. Plastic Conduit: PVC conforming to NEMA TC2 (conduit) and TC3 (fittings) type EPC-40-PVC for direct burial and concrete encasement. C. Tape: Plastic insulating tape conforming to UL 510. South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -3 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work 2.3 WIRE AND CABLE A. General: Provide wires and cables which meet all the applicable requirements of the NEC and UL for the type of insulation, jacket, and conductor specified or indicated. Conductor sizes are based on copper. Wire and cable conductor sizes are designated by American Wire Gauge (AWG) and Thousand of Circular Mils (KCM). All conductors shall be copper. Insulated conductors shall bear the date of manufacture imprinted on the insulation. Do not use wire and cable manufactured more than 12 months before delivery to the job site. B. 600-Volt Wire: 1. 2.4 Primary Ground: Conductors rated 600 volts and less in conduit shall conform to UL 44, Type XHHW-2. Conductor shall be stranded copper. C. Wires and Cables for Medium Voltages: Provide wires and cables with both conductor and insulation shielding, and a PVC or polyethylene jacket. Cable shall meet NEMA WC8 and AEIC C56 for ethylene-propylene-rubber insulation and shall be rated 15 kV for 13.8kV systems. D. Live Front Medium Voltage Cable Terminations: Provide terminations which meet the requirements of IEEE 48 for Class 1 outdoor terminations, including stress relief. Provide all components which are the product of one manufacturer, furnished in a package or kit form. Provide components which are compatible with the cable insulation and conductor materials. Included in the package, or kit, complete assembly and installation instructions; submit a copy to the Owner/Engineer for approval. E. Load-break connectors shall be the separable insulated type rated 95 KV B.I.L., 200 amps and shall meet IEEE 386. Associated bushing wells, inserts, and insulated bushings shall be compatible with the load-break connectors. NONMETALLIC DUCTS AND DUCT ACCESSORIES A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. ARNCO Corp. Beck Manufacturing. Cantex, Inc. CertainTeed Corp.; Pipe & Plastics Group. Condux International, Inc. ElecSys, Inc. Electri-Flex Company. PEX Inc. Lamson & Sessions; Carlon Electrical Products. Manhattan/CDT; a division of Cable Design Technologies. Spiraduct/AFC Cable Systems, Inc. B. Duct Accessories: 1. Duct Separators: Factory-fabricated rigid PVC interlocking spacers, sized for type and sizes of ducts with which used, and selected to provide minimum duct spacings indicated while supporting ducts during concreting or backfilling. South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -4 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work 2. 2.5 Warning Tape: Underground-line warning tape specified in Division 26 Section "Identification for Electrical Systems." RELATED MATERIAL Grounding: Provide copper clad steel ground rods with diameter adequate to permit driving to full length of the rod, but no less than 3/4” in diameter. Each rod shall be an assembly of 10 ft. long sectional rods coupled together, having the total length as indicated. PART 3 - EXECUTION 3.1 INSPECTION General: Examine the areas and conditions under which underground electrical work will be installed. Notify the Owner/Engineer in writing of conditions detrimental to the proper and timely completion of the Work. Do not proceed with the Work until unsatisfactory conditions have been corrected in an acceptable manner. 3.2 3.3 INSTALLATION A. General: Install underground cable and conduit in conformance with ANSI C2 and NFPA 70 except as otherwise specified or indicated. B. Contractor Damage: Promptly repair any damage to indicated utility lines or systems. UNDERGROUND CONDUIT A. General: Conduit type shall be as specified and as indicated. B. Underground Conduit with Concrete Encasement: Construct underground duct lines of individual conduits encased in concrete. PVC schedule 40 conduit as indicated. Conduits shall be sized as indicated on Project Drawings. Install concrete encasement surrounding the bank rectangular in cross-section or as indicated on the Drawings and provide at least 3” of concrete to cover ducts all around and 2” of cover around rebars. Provide steel reinforcing in concrete duct bank as indicated on drawings. Separate conduits as indicated. 1. Install the top of the concrete envelope not less than 32" below grade or as indicated on the Drawings. 2. Install duct lines with a continuous slope downward toward manholes and away from foundations and bunkers with a pitch of not less than 3" in 100 ft. Except at conduit risers, accomplish changes in direction of runs exceeding a total of 10°, either vertical or horizontal, by long sweep bends having a minimum radius of curvature of 25 ft.; sweep bends may be made up of one or more curved or straight sections or combinations thereof. Provide manufactured bends with a minimum radius of 24". South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -5 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work 3, C. 3.4 Provide separators of high impact polystyrene. Stagger the joints of the conduits by rows and layers so as to provide a duct line having the maximum strength. During construction, protect partially completed duct lines from the entrance of debris such as mud, sand and dirt by means of suitable conduit plugs. As each section of a duct line is completed, draw a testing mandrel not less than 12" long with a diameter 1/4” less than the size of the conduit through each conduit, after which draw a brush having the diameter of the conduit, and having stiff bristles through until the conduit is clear of all particles of earth, sand, and/or gravel; then immediately install conduit plugs. Concrete: 3000 psi for duct banks. 1" maximum aggregate. Refer to specification Section 03 30 00, Cast-In-Place Concrete. 1. Slump: Not to exceed 3". 2. Concrete Placing: Retempering of concrete will not be permitted. D. Backfilling: Provide a plastic warning tape in the backfill above all underground conduits and duct banks. Provide tape 3" wide, bright, fade-resistant yellow or orange in color, and include an imprinted legend CAUTION BURIED ELECTRIC LINE BELOW repeated continuously throughout the entire length. Bury tape 12" above top of duct bank. Place backfill in layers not more than 6" thick and compact each layer. Backfill as rapidly as the construction, testing and acceptance of the Work permits. Provide backfill free from roots, wood scrap material, and other vegetable matter and refuse. Unless indicated otherwise, compact backfill to a maximum density of at least 95% as determined by ASTM D1557. Test in-place density in accordance with ASTM D1556 or ASTM D2922. E. Reconditioning of Surfaces: Restore paved and unpaved surfaces disturbed during the installation of duct or direct burial conduit to their original elevation and condition. F. Pull String: Provide plastic string having a minimum tensile strength of 200 lbs. in each empty duct. Leave a minimum of 36" of slack at each end of the pull string unless noted otherwise. CABLE PULLING A. B. General: Test existing duct lines with a mandrel and thoroughly swab out to remove foreign material before the pulling of cables. Pull cables down grade with the feed-in point at the manhole or structure of the highest elevation. Use flexible cable feeds to convey cables through the manhole opening and into the duct runs. 1.. Provide lubricants for assisting in the pulling of cables which are specifically recommended by the cable manufacturer. 2. Do not exceed the maximum cable pulling tension recommended by the cable manufacturer. Installation of Cables in Manholes: Do not install cables utilizing the shortest route. Form all cables to closely parallel walls; do not interfere with duct entrances, and support on brackets and cable insulators at a maximum of 4 ft. In existing manholes, where new cables are to be installed, modify the existing installation of cables, cable supports and grounding as required for a neat and workmanlike installation with all cables properly arranged and supported. Provide new racks as required for installation of new cables. South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -6 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work C. Fireproofing (ARC Proofing) of Cables in Manholes: Fireproof all wire and cables which will carry current at 2200 volts or more in manholes. 1. Tape wrap cables without a nonmetallic protective covering over the sheath, prior to application of the fireproofing. Provide wrap in the form of two tightly applied halflapped layers of a pressure-sensitive 10 mil thick plastic tape, and extend not less than 1" into the duct. Even out irregularities of the cable, with insulation putty before the tape is applied. 2. D. 3.5 3.6 Connections to Manholes: For duct line connections to existing manhole use existing window terminators if available or provide core bore and seal around conduit entry. EARTHWORK A. Remove excavated materials from the project site. Provide sheeting and shoring as necessary for protection of Work and safety of personnel. Remove water from excavation by pumping or other approved method. B. Provide backfilling around structures consisting of earth, loam, sand-clay, or sand and gravel, free from large clods of earth or stones over 1" in size. Place backfill materials symmetrically on all sides in loose layers not more than 9" deep. Moisten each layer, if necessary, and compact with mechanical or hand tampers to 95% compaction. CABLE TERMINATING A. 3.7 Wrap strips of fireproofing tape, approximately 1/16” thick by 3" wide, tightly around each cable spirally in half-lapped wrapping, or in two butt-joined wrappings with the second wrapping covering the joints in the first. Apply the tape with the coated side toward the cable and extend 1" into the ducts. To prevent unraveling, random wrap the fireproofing tape the entire length of the fireproofing with pressure sensitive glass cloth tape. Use fireproofing tape consisting of a flexible, conformable fabric having one side coated with flame retardant, flexible, polymeric coating and/or a chlorinated elastomer not less than 0.050" thick weighing not less than 2.5 lbs./sq. yd. Provide tape which is non-corrosive to cable sheath, self-extinguishing; will not support combustion, and not deteriorate when subjected to oil, water, gases, saltwater, sewage, and fungus. Protect terminations of insulated power cable from accidental contact, deterioration of coverings, and moisture by the use of terminating devices and materials. 1. Make terminations using materials and methods as indicated or specified herein or as designated by the written instructions of the cable manufacturer and termination kit manufacturer. 2. Termination for high voltage cable shall be rated, and be capable of withstanding test voltages, in accordance with the IEEE 48. SUBMERSIBLE SPLICES FOR 600-VOLT CLASS CABLES A. General: Splices are not allowed unless justified by the Contractor and approved by the Engineer. Cable terminations shall be made on power distribution blocks. South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -7 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work If splices are absolutely necessary then make splices in underground systems subject to water infiltration by using a compression connector on the conductor and by insulating and waterproofing by one of the following methods suitable for continuous submersion in water. 3.8 1. Cast-Type Splice Insulation: Provide by means of a molded casting process employing a thermosetting epoxy resin insulating material. Apply by a gravity poured method or by a pressure injected method. Provide packaged form component materials of the resin insulation ready for convenient mixing without removing from the package. Do not allow the cables to be moved until after the splicing material has completely set. Install per splice kit manufacturer's instructions. 2. Gravity Poured Method: Employ materials and equipment contained in an approved commercial splicing kit which includes a mold suitable for the cables to be spliced. When the mold is in place around the joined conductors, prepare the resin mix and pour into the mold. Do not allow cables to be moved until after the splicing materials have completely set. Install per splice kit manufacturer's instructions. DRY SPLICES AND TAPS FOR 600-VOLT CLASS CABLES General: Provide splices and / or taps of the kind and type as approved for that purpose and as noted on the drawings. 3.9 SPLICES IN MEDIUM VOLTAGE CABLES General: Splicing shall be as approved by the Engineer on a case-by-case basis and only where absolutely necessary. Power cable joints (splices) suitable for continuous immersion in water and made only in accessible locations in manholes. A. 3.10 Make medium-voltage joints by using a kit of one manufacturer and with written approval of the manufacturer of the cable which is to be spliced. Upon request, supply manufacturer's design qualification test report in accordance with IEEE 404. Joint design shall have been proof tested in accordance with IEEE 404. Connectors for joint shall be tin-plated electrolytic copper, having ends tapered and having center stops to equalize cable insertion. 1. Watertight Tape-Type Joint: Consists of an approved connector, self-fusing tape (splicing compound), self-bonding semiconducting tape, tinned copper shielding tape or braid, and plastic tape. 2. Heat-Shrinkable Joint: A uniform cross-section heat-shrinkable polymeric construction consisting of a linear stress relief system, a high dielectric strength insulating material, and an integrally bonded outer conductor layer for shielding. Replace original cable jacket with a heavy-wall heat-shrinkable sleeve with hot-melt adhesive coating. Provide joint suitable for the rated voltage of the cable. 3. Live End Caps: Provide live end caps using a “kit” including a heat-shrinkable tube and a high dielectric strength, polymeric plug overlapping the conductor. End cap shall conform to applicable portions of IEEE Std. 48. GROUNDING South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -8 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work A. General: Provide non-current carrying metallic parts associated with electrical equipment with a maximum resistance to solid "earth" ground not exceeding the following values: 1. Pad-mounted substations without protective fences 5 ohms 2. Ground in manholes 10 ohms 3. Grounding other metal enclosures of primary voltage electrical and electrically operated equipment 10 ohms Grounded secondary distribution system neutral and non-current carrying metal parts associated with distribution systems and grounds not otherwise covered. 5 ohms 4. 3.11 B. Grounding Electrodes: Provide cone pointed driven ground rods driven full depth plus 6", installed when indicated to provide an earth ground of the value before stated for the particular equipment being grounded. C. Connections: Make grounding connections which are buried or otherwise normally inaccessible, and excepting specifically those connections for which access for periodic testing is required, by exothermic weld or by using a compatible mechanical connection and brazing over. Make exothermic welds strictly in accordance with the weld manufacturer's written recommendations. Welds which have "puffed up" or which show convex surfaces, indicating improper cleaning, are not acceptable. No mechanical connector is required at exothermic weldments. FIELD TESTS A. General: As an exception to requirements that may be stated elsewhere in the contract, give the Owner/Engineer 5 days' notice prior to each test. B. Distribution Conductors 600-Volt Class: Test all 600-Volt class conductors to verify that no short circuits or accidental grounds exist. Make tests using an instrument which applies a voltage of approximately 500 volts to provide a direct reading of resistance. C. Medium Voltage Cables: After installation, and before placing in service, the Independent Electrical Testing firm shall perform a High Potential VLF test on all 15 kV cables. Adhere to all precautions and limits as specified in the ICEA standard. Utilize test procedure as follows and record the results for each cable test. Provide Cable Test Report. 1. Record temperature and relative humidity. Do not perform test unless weather is clear and relative humidity is below 70%. 2. Record cable data. 3. Record normal operating voltage. 4. Record applied test voltage. 5. Record test frequency. 6. Individually test each conductor with all other conductors grounded. Ground all shields. South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -9 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 05 43 – Underground Electrical Work 7. Properly suppress corona for all terminations. 8. Apply 100% test voltage for 1 hour. Record PASS or FAIL for each phase. D. Ground Rods: Test ground rods for ground resistance value before any wire is connected. Use a portable ground testing megger to test each ground or group of grounds. Equip the instrument with a meter reading directly in ohms or fractions thereof to indicate the ground value of the ground electrode under test. Provide one copy of the megger manufacturer's directions for use of the ground megger indicating the method to be used. Should any individual ground rod measure more than 25 ohms resistance, and should any ground system measure a higher value than that specified in the paragraph entitled Grounding, notify the Owner/Engineer. Submit written results of all tests. E. Compaction: Test backfill in accordance with ASTM D1556 or ASTM D2922. F. Test Report: Submit test reports for the following: 1. 600-Volt Cables: Identify each cable and test result. 2. Medium Voltage Cables: Identify each cable and test result. 3. Grounding Electrodes and Systems: Identify electrodes and systems, each test. PART 4 - COMPENSATION 4.1 MEASUREMENT AND BASIS OF PAYMENT A. Payment will be made under Items in Section V. B. Bid Item extensions are computed in accordance with the quantities and unit prices stated and reflect full compensation for a complete, finished product. D. Quantities stated in the Bid may be adjusted on order of the Owner. The cost or credit to the Owner shall be computed in accordance with the unit prices stated under the applicable Bid Item. D. No quantity adjustment will be made for work performed outside the scope of work. E. No quantity adjustment will be made for work completed within its specified tolerance, nor the specified tolerance of the preceding completed work Item. South Carolina Ports Authority – Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area 26 05 43 26 05 43 -10 Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 12 19 – MV Transformers PART 1 - GENERAL 1.1 SUMMARY This specification is to provide a pad-mounted transformer to step down primary voltage from 13.8 kV to 480Y/277V for power service to the service area for refrigerated containers. Basis of design is ABB. 1.2 REFERENCES The Contractor shall accomplish the work in accordance with the reference documents except as modified in the contract documents. The Contractor shall consider all advisory language or recommended practices to be mandatory. A. AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM) ASTM D 3487 B. C. Mineral Insulating Oil Used in Electrical Apparatus INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERING, INC (IEEE) IEEE C2 National Electrical Safety Code IEEE 386 Separable Insulated Connectors for Power Distribution Systems Above 600 volts. IEEE C62.11 Metal-Oxide Surge Arresters for AC power Circuits (>1 KV) (ANSI/IEEE) NATIONAL ELECTRICAL MANUFACTURERS ACCOCIATION (NEMA) NEMA C57.12.22 Pad-Mounted Compartmental-Type, Self-Cooled, Three-Phase Distribution Transformers for use with Separable Insulated HighVoltage Connectors, 2500 KVA and Smaller. D. NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) NFPA 70 1.3 National Electrical Code SUBMITTALS A. B. Product Data: The Owner/Engineer reserves the right to reject any product or brand that conforms to these specifications, but may not be of the quality intended for this work. Submit the following for approval: 1. Pad-mounted transformer 2. Acceptance tests and verifications 3. Operating and maintenance data Submit product data for transformer showing overall dimensions, front view, sectional views, ratings and sizes of all components and wiring diagrams. South Carolina Ports Authority - Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 12 19 – MV Transformers C. D. Transformer Test: Standard tests shall include: 1. Ratio Test 2. Polarity Test 3. Phase Relation Test 4. No-Load Loss Test 5. Excitation Current Test 6. Impedance Voltage test 7. Load Loss Test 8. Applied Potential Test 9. Induced Potential Test 10. Leak Test 11. Resistance Measurement Test 12. Certified Test Report 13. Factory QC Impulse Test Operating and Maintenance Data: 1. Submit operating maintenance data. 2. Include instructions for operating equipment 3. Include instructions for operating equipment under emergency conditions. 4. Identify operating limits which may result in hazardous or unsafe conditions. 5. Documents rating of equipment and each major component. 6. Include routine preventive maintenance. 7. List special tools, maintenance materials, and replacement parts. PART 2 - PRODUCTS 2.1 PAD-MOUNTED TRANSFORMER A. Pad-mounted transformer shall be of the outdoor type and shall consist of a highvoltage (incoming) compartment, a transformer section, and a low-voltage (outgoing) compartment suitably separated by full height isolating barriers. All components shall be assembled and shipped by one manufacturer as a unit, completely weatherproof and tamperproof for mounting on a concrete pad without additional housing, fences or other enclosures. Unit shall meet all applicable portions of ANSI C57.12.26. B. Primary Components: The incoming compartment shall be deadfront, loop feed construction (200 amp HV bushing wells) and shall include load-break connectors, 2-position 300 amp LBOR transformer switch, fuses, deadfront surge arresters, South Carolina Ports Authority - Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 12 19 – MV Transformers parking stands, insulated standoff bushings, insulated protective caps and inserts. Bayonet fuses shall be accessible from the primary compartment. C. Load-break connectors shall be the separable insulated type rated 95 KV B.I.L., 200 amps and shall meet IEEE 386. Associated bushing wells, inserts, and insulated bushings shall be compatible with the load-break connectors. D. A parking stand shall be provided near each bushing well. Three insulated bushings shall be provided for parking of energized load-break connectors on parking stands. Provide insulated protective caps. E. Fuses: Provide bayonet oil-immersed, expulsion fuses in series with parallel oilimmersed, partial range current-limiting fuses. Coordinate protection with expulsion fuse clearing low-current faults and current-limiting fuse clearing high-current faults up to 50,000 Amperes symmetrical. F. Surge arresters shall be 10KV, 8.4 KV MCOV fully shielded, combined dead-front molded-rubber separable connectors and zinc-oxide gapless varistor surge protectors. Combination units shall meet the applicable requirements of IEEE 386 and IEEE C62.11. G. Transformer Section: Transformers shall be the oil-immersed self-cooled type with the following ratings and features: kVA: ........................................225 Phase: .....................................3 Primary Voltage: .....................13,800 Volts Delta Secondary Voltage:.................480/277 Volts WYE Frequency: ..............................60 Hz Mineral Oil: ..............................Shall confirm to ASTM D 3487, Type II Temperature Rise: ..................65 Degrees C Primary B.I.L.: .........................95 KV Secondary B.I.L.: ....................60 KV Percent Impedance: ................4.10 Percent plus or minus 7% Taps: .......................................Two 2½ percent above and two 2½ percent below rated voltage (taps shall be full capacity) Windings: ................................Aluminum/Aluminum Sound Level: ...........................65 DB Base and enclosure ................304 Stainless Steel Tank…………………………….304 Stainless Steel H. Secondary Components: The secondary compartment shall be live front construction and shall include 600 amp porcelain bushings and spade-type terminals with four 9/16” diameter holes. Neutral XO bushing with ground strap. I. Pad-Mounted Enclosure: A tamperproof and weatherproof pad-mounted enclosure shall be provided, constructed of 304 stainless steel with a green Munsell 7GY 3.29/1.5 finish. The enclosure shall have lifting provisions, padlock provisions, and a penta-head security bolt. The enclosure cabinet shall be 18” deep. J. Accessories: The transformer shall have the following accessories: 1. 1” Drain Valve with 3/8” Sampler South Carolina Ports Authority - Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 12 19 – MV Transformers 2. Dial-type thermometer 3. Liquid level gage 4. Pressure vacuum gage 5. Standard pressure relief valve 6. Nitrogen test port K. Warning Signs: ANSI Z35.1. 1. Provide red painted signs that state “DANGER HIGH VOLTAGE” in two lines of 3” high letters on transformer. NEMA Safety Labels. 2. Provide Arc Flash Warning Label. L. Paint Finish: Multi-step process: Green epoxy primer by cationic electrode position. Final coating of two-component urethane paint spray applied for color and additional film build. PART 3 EXECUTION 3.1. INSPECTION A. 3.2. INSTALLATION A. 3.3. General: Examine the areas and conditions under which the transformer will be installed and notify the Engineer in writing of conditions detrimental to the proper and timely completion of the work. Do not proceed with work until unsatisfactory conditions have been corrected in an acceptable manner. B. General: Install the transformer in strict conformance with the manufacturer’s written recommendations. Electrical installation shall conform to ANSI C2, NFPA 70, and to the requirements specified herein. Equipment Pad: Provide a concrete and reinforced equipment pad. C. Provide bollard protection for the transformer. FIELD QUALITY CONTROL A. Performance of acceptance checks and test shall be by an independent electrical testing firm. Perform in accordance with the manufacturer’s recommendations, NFPA 70B, NETA ATS and ANSI standards. B. Transformer, Pad-Mounted Type – Medium Voltage 1. Compare transformer and accessories nameplates information with the shop drawings and report discrepancies. 2. Inspect transformer and accessories and report damage, loose material, shipping blocks or contamination that must be corrected, clean where appropriate. 3. Inspect installation location and report any unfavorable environmental conditions that must be corrected. South Carolina Ports Authority - Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area Epic Engineering 15621 June 2016 DIVISION 26 - ELECTRICAL Section 26 12 19 – MV Transformers 4. Check transformer for level, security to foundation and operation of doors. Report conditions that must corrected, adjust where appropriate. 5. Visually check the equipment ground. Report deficiencies. 6. Move no-load tap changer through all positions and test turns-ratio on each point. Record values and report deficiencies, set on mid tap. 7. Take a sample of the insulation liquid and perform the following tests. Record values and provide report. 8. C. a. Visual Analysis 1) Color 2) Condition b. Sample Analysis 1) Dielectric Strength 2) Acidity 3) Water Content 4) Dissolved Gas Analysis Perform the following test on each transformer. Provide report document that gives analysis and recommendations. Do not perform tests until transformers are set in place for operation. a. Absorption Test b. Turns Ratio Test Follow-Up Verification: Upon completion of acceptance checks, settings, and tests, the Engineer shall show by demonstration in service that circuits and devices are in good operating condition and are properly performing the intended function. PART 4 COMPENSATION 4.1. MEASUREMENT AND BASIS OF PAYMENT Unit Price Items: Unit prices for transformers are included in the Bid Form and are paid per each inclusive of all materials and labor required for installation and operation. A. “Medium Voltage Transformer” shall be maeasured and paid by the Lump Sum, for pad mounted transformer including rubber goods, elbow surge arresters, inserts, and stand-off insulators with caps. Also included are ground ring with jumpers, exothermic welds, ground rods, excavation and backfill; and equipment pad for transformer and service equipment South Carolina Ports Authority - Wando Welch Terminal CIF16E010B – Refrigerated Container Service Area Epic Engineering 15621 June 2016 SCPA Quality Control Minimum Sampling and Testing Frequency Requirements Item # 1 Material or Product Minimum Size of Each Sample1 6 7 Blocks, Concrete In accordance with ASTM C140 8 Bolts, High Strength 3 assemblies of bolt, nut and washer 10 bricks each source One (1) 40 inch and One (1) 12 inch 3 4 5 9 Brick 10 Cable Strand 11 Castings, Catch Basins Drop Inlets Cement Stabilized Earth Base 13 Cement Stabilized Earth Base 14 Cement, Fly Ash 1 gallon 15 Cement, Portland & Slag 1 gallon 16 Cement, Masonry Concrete, Structural, Prestressed, Lean & Other Concrete, Structural, Prestressed, Lean & Other 18 Each 500 tons Gradation and Approval Sheet 2 Submit one sample of each type, each Contract Each 500 tons Gradation and Approval Sheet 1 Submit one sample of each type, each Contract Approval Sheet 2 Approval Sheet 1 Each 10,000 tons of mix produced Each source Approval Sheet 37 Dimensions, Water Absorption, Compressive Strength Each possible combination of bolt lot, nut lot and washer lot Each 50,000 bricks Each 5 reels per heat number Each structure 12 17 Remarks3 Approval Sheet 5 and/or Approval Sheet 53 Admixtures See SC-T-1, Aggregates, Coarse Non-HMA SC-T-3, and SC-T-4 10 pounds Aggregates, Fine See SC-T-2, SC-T-3, and SC-T-4 Non-HMA Aggregates, Coarse HMA Aggregates, Fine HMA Asphalt, Liquid PG binder 1 quart 2 Test Required2 Minimum Frequency of Sampling Each 25,000 SF or one day's work whichever is greater Each 5,000 SF or one day's work, whichever is greater Each 50 tons Each 100 tons. On large paving and modified base projects, rate determined by the Engineer Submit Certification for cable strand Dimension Inspect all castings for workmanship & Manufacturer’s Certification Required Compaction Depth Mill Test Report Required Mill Test Report Required Verify Type in Field As needed to control consistency As needed to control % entrained air Minimum of one set per 50 yards, or each day's placement, or for each structure poured, whichever is greater Minimum of one set per 50 yards, or each day's placement, or for each structure poured, whichever is greater One (1) set each one-half day’s production Four (4) each day’s run and each time test specimens are made Four (4) each day’s run and each time test specimens are made Slump Test when consistency is questionable and when cylinders are made Air Content Test when air content is questionable and when cylinders are made Make specimens for compressive strength. AASHTO T-23 (ASTM C 31) Make specimens for compressive strength. AASHTO T-23 (ASTM C 31) Make specimens for compressive strength. AASHTO T-23 (ASTM C 31) Slump AASHTO T-23 (ASTM C 31) Air content AASHTO T-23 (ASTM C 31) 19 Concrete, Structural Three cylinders, minimum 4-inch cylinders 20 Concrete, Prestressed Six cylinders, minimum 4-inch cylinders 21 Concrete, Lean Four (4) 6-inch cylinders. 22 Concrete Pavement 23 Concrete Pavement 24 Concrete Pavement Four (4) flexural beams One (1) set each 1500 square yards, or Make specimens for flexural part thereof. strength. Minimum one (1) set per day. AASHTO T-23 (ASTM C 31) 25 Coquina Shell Base 25 pounds Each 25,000 SF Provide sample to the Engineer and Certification that the source meets or exceeds the Contract requirements 26 Coquina Shell Base 27 Coquina Shell Base 28 Curing Compound, Spray-On/ Brush-On Concrete Coatings Appendix A CIF16E010B Each 5,000 SF or one day's work, whichever is greater Each 25,000 SF or one day's work, whichever is greater No samples required Depth Compaction Approval Sheet 7 or Approval Sheet 33 Manufacturer’s Certification Required 1 of 4 Item # Material or Product 29 Embankments 30 Embankment Material 31 Embankment Material 32 Emulsions 33 Fence, Barbed Wire 34 Fence, Chain Link 35 Fence, Woven Wire 36 Fence, Hardware 37 Fertilizer Guardrail, Beams, Steel Posts & Hardware Guardrail, Wood Posts & Blocks 38 39 40 Guardrail, Composite Blocks 41 42 43 46 Handrailing, Steel Pipe Handrailing, Aluminum HMA Mixes Joint Material, Structural and Pavement Lime, Agricultural and Hydrated Graded Aggregate Base 47 Graded Aggregate Base 48 Graded Aggregate Base 49 Mineral Filler, HMA Paint, Structural Steel Piles, Steel Piles, Treated Timber 44 45 50 51 52 Minimum Size of Each Sample1 0.5 gallon One (1) 3-foot length One (1) 2-foot length One (1) 4-foot length Three (3) each type Test Required2 Minimum Frequency of Sampling Each 2000 cubic yards, minimum 1 per Compaction lift One each for each change of source or appearance. One each for each change of source or Proctor appearance or for each 20,000 cubic yards Each 2500 gallon Approval Sheet 38 Manufacturer’s Certification Required Each 16,000 feet, each source Manufacturer’s Certification Required Each 50 rolls, each source Each 50 rolls, each source Each 50 rolls, each source Manufacturer’s Certification Required Manufacturer’s Certification Required Manufacturer’s Certification Required Visual defects and Approval Sheet 29 Manufacturer’s Certification Required Visual defects Must bear Inspection Agency’s hammer mark Visual defects and Approval Sheet 49 Manufacturer’s Certification Required Manufacturer’s Certification Required See Specifications See Specifications See Specifications See Specifications Approval Sheet 39 for hydrated lime See SC-T-1 1 quart Each 25,000 SF, each layer Each 5,000 SF or one day's work, whichever is greater Each 25,000 SF or one day's work whichever is greater Each source Per project Grain Size Distribution Depth Compaction Manufacturer’s Certification Required Visual Flaws Mill Test Report required Visual Flaws Must bear Inspection Agency’s hammer mark Piles, Prestressed Visual Flaws 54 Pipe Culverts, Concrete Visual Flaws 55 56 57 Pipe Culverts, High Density Polyethylene Pipe 58 Rip Rap 59 Sand Clay Base, Roadway 60 Sand Clay Base, Roadway 61 Sand Clay Base, Roadway Appendix A CIF16E010B Submittal of Source Certification is required Manufacturer’s Certification Required 53 Pipe Culverts, Corrugated Metal Pipe Culverts, Corrugated Aluminum Remarks3 If ID < 10 inches One (1) 3-foot piece. If ID > 10 inches One (1) 1-foot piece Each size, each shipment Plant must be certified in accordance with Specifications and Plant must certify each pile Plant must be certified in accordance with Specifications and Plant must certify each delivery Visual Flaws Mill Test Report required Visual Flaws Mill Test Report required Visual Flaws and Manufacturer’s Stamp Manufacturer’s Certification Required Visual Check for Size and Quality 10 pounds Each 25,000 SF, each layer Each 5,000 SF or one day's work, whichever is greater Each 25,000 SF or one day's work whichever is greater Submittal of Source Certification is required Depth Compaction When minimum percent compaction is specified 2 of 4 Item # Material or Product 62 Seed 63 Steel, Structural 64 Steel, Reinforcing Subbase, Cement-Modified Subbase, Cement-Modified Subbase, Cement-Modified Subbase, Cement-Modified 65 66 67 68 69 Minimum Size of Each Sample1 Test Required2 Minimum Frequency of Sampling Remarks3 Manufacturer’s Certification Required Visual Defects and Inspection Agency Marks 40 inches Each size, each shipment As required Once daily Two (2) 4-inch diameter cores Once daily Subgrade, Untreated % Passing 2 inch and #4 sieves Compaction Depth Compaction 70 Subgrade, Untreated 71 72 Timber, Treated Timber, Untreated Visual Defects Visual Flaws, Knots, etc. 73 Traffic Marking, Paint Waterborne or Solventborne Check batch numbers at job site Accepted based on Manufacturer Certification and match certification documents. 74 Traffic Marking, Thermoplastic or Epoxy 75 Traffic Marking, Pavement Markers 76 Traffic Marking, Reflective Beads Spray-on/Drop-on 77 Underdrains & Sectional Drains, Corrugated Polyethylene 78 79 Underdrains & Sectional Drains, Concrete Perforated. Underdrains & Sectional Drains, Corrugated Metal Perforated 80 Underdrains & Sectional Drains, Asphalt Fiber 81 Underdrains & Sectional Drains, Corrugated Aluminum 83 Underdrains & Sectional Drains, Class PS 46 PVC Water 84 Waterproofing, Asphalt or Tar 85 Waterproofing, Fabric Wire, Reinforcement 82 86 87 Wire Mesh Reinforcement 88 89 90 91 92 93 Bollards Fender Systems High Mast, Area Lighting Fiber Optic Cabling Conduit Conductors Appendix A CIF16E010B 10 pounds Each 25,000 SF or one day's work whichever is greater Each 5,000 SF or one day's work, whichever is greater Each 25,000 SF or one day's work whichever is greater Each 25,000 SF or one day's work whichever is greater Mill Test Report required for components not pre-approved No field samples required 20 markers per lot. Randomly selected One (1) 50 or 55- pound bag when bagged. No sample in bulk pack If ID < 10 inches One (1) 3-foot piece. If ID > 10 inches One (1) 1-foot piece 2 joints Must be pre-tested and bear Inspection Agency’s hammer mark Not pre-tested Or pre-approved Check batch numbers at job site Accepted based on Manufacturer Certification and match certification documents. Accepted based on Manufacturer Certification One bag per each batch (44,000 pounds) Accepted based on Manufacturer Certification Each size, each shipment Manufacturer’s Certification Required Each source Mill Test Report required One (1) Each size, each shipment 2-foot length and One(1) 1-foot length Manufacturer’s Certification Required Mill Test Report required One (1) 3-foot piece 1 gallon Each size, each shipment Each source Not required if obtained from Potable Water Source or approved hydran Manufacturer’s Certification Required One (1) 40-inch length One (1) 24 inch x 24 inch sample Each size, each shipment Each size, each shipment See Specifications See Specifications See Specifications See Specifications See Specifications See Specifications 3 of 4 Item # 94 95 96 Material or Product Electrical Components Sanitary Sewer Potable Water Minimum Size of Each Sample1 Minimum Frequency of Sampling Test Required2 Remarks3 See Specifications See Specifications See Specifications 1. Reference to "SC" test method indicates SCDOT Standard Method of Test in accordance with Appendix C of the SCDOT Construction Manual found at the following location: http://www.scdot.org/doing/construction_Manual.aspx 2. "Approval Sheet" Refers to the SCDOT Qualified Products List found at the following location: http://info.scdot.org/Construction_D/sitePages/qualifiedProducts3.aspx 3. This Appendix shall be used as a supplement to the Specifications. In cases where the test method or frequency is inconsistent with the Specifications, the most stringent requirement applies Appendix A CIF16E010B 4 of 4