IFB 9783 (Addendum #3) ADDENDUM NO. 3 DATE: August 3, 2015 TO: ALL BIDDERS OWNER: University of Central Missouri (UCM) Department of Procurement & Materials Management Southeast Complex Building A 415 East Clark Street Warrensburg, MO 64093 SUBJECT: Addendum #3 for IFB 9783 (UCM Greenwood Community Building Project) _____________________________________________________________________________ THIS ADDENDUM IS ISSUED AS PART OF THE BID DOCUMENTS FOR THIS BID AND AMENDS ONLY THOSE ITEMS SPECIFICALLY DEFINED HEREIN. PLEASE ACKNOWLEDGE THE RECEIPT OF THIS ADDENDUM ON THE ATTACHMENT A – BID FORM. ______________________________________________________________________________ This addendum forms a part of the Bid Documents and modifies the Bidding Documents dated July 22, 2015 with clarification noted below. In preparing bids, the Bidder shall take into consideration the following items. Information shown herein supersedes requirements issued under previous date. Replace the Table of Contents with the following (attached): Eliminate Section 311000 from Table of Content Add the following Sections (attached): Added Section 262416 Added Section 270000 Added Section 283111 Panelboards Voice and Data Distribution Systems Digital Addressable Fire Alarm System UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION TABLE OF CONTENTS INTRODUCTORY AND BIDDING INFORMATION 00 0000 00 0001 00 0010 00 0020 00 0025 00 0030 00 0035 00 0040 00 0045 00 0050 00 0055 00 0060 00 0065 00 0070 Invitation For Bid Cover Sheet Project Manual Cover Table of Contents General Requirements Attachment A – Bid Form Attachment B – Contractor Qualification Form Attachment C – Subcontractor Form MBE/WBE Compliance Evaluation Form MBE/WBE Eligibility Determination Form MBE/WBE Eligibility Determination Form for Joint Ventures MBE/WBE Application for Waiver Form Affidavit for Affirmative Action Affidavit of Work Authorization Missouri Division of Labor Standards Annual Wage Order No. 22 DIVISION 1 - GENERAL REQUIREMENTS 01 1000 01 2500 01 2600 01 2900 01 3100 01 3200 01 3300 01 4000 01 5000 01 6000 01 7123 01 7300 01 7700 01 7839 01 7900 Summary of Work Substitution Procedures Contract Modifications Procedures Payment Procedures Project Management and Coordination Construction Progress Documentation Submittal Procedures Quality Requirements Temporary Facilities Project Requirements Construction Layout Execution Closeout Procedures Project Record Documents Demonstration and Training DIVISION 2 - EXISTING CONDITIONS 02 4100 Site Demolition DIVISION 3 – CONCRETE 03 2000 03 3000 03 4100 Concrete Reinforcement Cast-in-Place Concrete Precast Structural Concrete DIVISION 4 - MASONRY 04 2000 Unit Masonry DIVISION 5 – METALS TABLE OF CONTENTS TOC - 1 05 5000 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION Metal Fabrications DIVISION 6 - WOOD, PLASTICS, AND COMPOSITES 06 1000 06 1600 06 1753 06 4116 Rough Carpentry Sheathing Shop-Fabricated Wood Trusses Plastic Laminate Architectural Cabinets DIVISION 7 - THERMAL AND MOISTURE PROTECTION 07 1416 07 1900 07 2100 07 2500 07 3113 07 4600 07 6200 07 8446 07 9200 Cold Fluid-Applied Waterproofing Water Repellents Thermal Insulation Weather Barriers Asphalt Shingles Siding Sheet Metal Flashing and Trim Firestopping Joint Sealants DIVISION 8 – OPENINGS 08 1113 08 1416 08 4213 08 4333 08 7100 08 9119 Hollow Metal Doors and Frames Flush Wood Doors Impact and Wind Resistant Aluminum Door Assemblies Impact and Wind Resistant Aluminum Storefront Door Hardware Fixed Louvers DIVISION 9 – FINISHES 09 2216 09 2900 09 3000 09 5113 09 6513 09 9123 Non-Structural Metal Framing Gypsum Board Tiling Acoustical Panel Ceilings Resilient Base and Accessories Interior Painting DIVISION 10 – SPECIALTIES 10 2600 10 2800 10 4413 Wall and Door Protection Toilet and Bath Accessories Fire Extinguishers and Cabinets DIVISION 11 – EQUIPMENT 11 5213 Projection Screens DIVISION 12 – FURNISHINGS 12 2413 Roller Window Shades TABLE OF CONTENTS TOC - 2 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION DIVISION 13 - SPECIAL CONSTRUCTION (Not Used) DIVISION 14 - CONVEYING EQUIPMENT (Not Used) DIVISION 22 – PLUMBING 22 0517 22 0518 22 0519 22 0523 22 0529 22 0553 22 0719 22 1116 22 1119 22 1316 22 1319 22 421313 22 421613 22 421616 22 4716 Sleeves and Sleeve Seals For Plumbing Piping Escutcheons for Plumbing Piping Meters and Gages for Plumbing Piping General-Duty Valves for Plumbing Piping Hangers And Supports for Plumbing Piping and Equipment Identification for Plumbing Piping and Equipment Plumbing Piping Insulation Domestic Water Piping Domestic Water Piping Specialties Sanitary Waste and Vent Piping Sanitary Waste Piping Specialties Commercial Water Closets Commercial Lavatories Commercial Sinks Pressure Water Coolers DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) 23 0593 23 0713 23 1123 23 2300 23 3113 23 3300 23 3423 23 3713 23 5100 23 5400 23 8126 Testing, Adjusting, and Balancing For HVAC Duct Insulation Facility Natural-Gas Piping Refrigerant Piping Metal Ducts Air Duct Accessories Hvac Power Ventilators Diffusers, Registers, and Grilles Breechings, Chimneys, and Stacks Furnaces Split-System Air-Conditioners DIVISION 26 – ELECTRICAL 26 0519 26 0526 26 0529 26 0533 26 0544 26 0553 26 0923 26 2416 26 2726 26 2816 26 5100 26 5600 Low Voltage Electrical Power Grounding and Bonding for Electrical Systems Hangers and Supports for Electrical Systems Raceway and Boxes for Electrical Systems Sleeves and Sleeve Seals Identification for Electrical Systems Lighting Control Devices Panelboards Wiring Devices Enclosed Switches and Circuit Breakers Interior Lighting Exterior Lighting TABLE OF CONTENTS TOC - 3 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION DIVISION 27 - COMMUNICATIONS 27 0000 Voice and Data Distribution Systems DIVISION 28 – ELECTRONIC SAFETY AND SECURITY 28 0513 28 3111 Conductors for Fire Alarm Digital Addressable Fire Alarm System DIVISION 31 – EARTHWORK 31 1000 31 2300 31 2333 31 2500 Site Clearing Excavation and Fill Trenching and Backfilling Erosion Control DIVISION 32 – EXTERIOR IMPROVEMENTS 32 1123 32 1300 32 1373 32 1723 32 9200 Aggregate Base Course Portland Cement Paving Concrete Pavement Joint Sealant Pavement Markings Turf Restoration DIVISION 33 – UTILITIES 33 1000 33 3000 Water Distribution Sanitary Sewerage END OF DOCUMENT TABLE OF CONTENTS TOC - 4 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION SECTION 262416 - PANELBOARDS PART 1 - GENERAL 1.1 A. 1.2 SUMMARY Section includes service entrance rated panelboards and lighting and appliance branch-circuit panelboards. ACTION SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: For each panelboard and related equipment. 1. 2. 3. 4. 5. 6. 7. 8. 1.3 Include dimensioned plans, elevations, sections, and details. Show tabulations of installed devices, equipment features, and ratings. Detail enclosure types and details for types other than NEMA 250, Type 1. Detail bus configuration, current, and voltage ratings. Short-circuit current rating of panelboards and overcurrent protective devices. Include evidence of NRTL listing for series rating of installed devices. Detail features, characteristics, ratings, and factory settings of individual overcurrent protective devices and auxiliary components. Include wiring diagrams for power, signal, and control wiring. Include time-current coordination curves for each type and rating of overcurrent protective device included in panelboards. INFORMATIONAL SUBMITTALS A. Field quality-control reports. B. Panelboard schedules for installation in panelboards. 1.4 QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. B. Comply with NEMA PB 1. C. Comply with NFPA 70. PANELBOARDS 262416 - 1 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION 1.5 A. WARRANTY Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace transient voltage suppression devices that fail in materials or workmanship within specified warranty period. 1. Warranty Period: Five years from date of Substantial Completion. PART 2 - PRODUCTS 2.1 A. GENERAL REQUIREMENTS FOR PANELBOARDS Enclosures: Flush- and surface-mounted cabinets. 1. Rated for environmental conditions at installed location. a. 2. 3. 4. Indoor Dry and Clean Locations: NEMA 250, Type 1. Front: Secured to box with concealed trim clamps. For surface-mounted fronts, match box dimensions; for flush-mounted fronts, overlap box. Hinged Front Cover: Entire front trim hinged to box and with standard door within hinged trim cover. Directory Card: Inside panelboard door, mounted in transparent card holder. B. Incoming Mains Location: Top and bottom. C. Phase, Neutral, and Ground Buses: Hard-drawn copper, 98 percent conductivity. D. Conductor Connectors: Suitable for use with conductor material and sizes. 1. 2. 3. 4. 5. Material: Hard-drawn copper, 98 percent conductivity. Main and Neutral Lugs: Compression type. Ground Lugs and Bus Configured Terminators: Compression type. Feed-Through Lugs: Compression type, suitable for use with conductor material. Locate at opposite end of bus from incoming lugs or main device. Subfeed (Double) Lugs: Compression type suitable for use with conductor material. Locate at same end of bus as incoming lugs or main device. E. Service Equipment Label: NRTL labeled for use as service equipment for panelboards with one or more main service disconnecting and overcurrent protective devices. F. Future Devices: Mounting brackets, bus connections, filler plates, and necessary appurtenances required for future installation of devices. G. Panelboard Short-Circuit Current Rating: Fully rated to interrupt symmetrical shortcircuit current available at terminals as indicated on the plans. PANELBOARDS 262416 - 2 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION 2.2 A. LIGHTING AND APPLIANCE BRANCH-CIRCUIT PANELBOARDS Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. 2. 3. 4. Eaton Electrical Inc.; Cutler-Hammer Business Unit. General Electric Company; GE Consumer & Industrial - Electrical Distribution. Siemens Energy & Automation, Inc. Square D; a brand of Schneider Electric. B. Panelboards: NEMA PB 1, lighting and appliance branch-circuit type. C. Mains: Circuit breaker. D. Branch Overcurrent Protective Devices: Bolt-on circuit breakers, replaceable without disturbing adjacent units. E. Doors: Concealed hinges; secured with flush latch with tumbler lock; keyed alike. 2.3 A. DISCONNECTING AND OVERCURRENT PROTECTIVE DEVICES Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. 2. 3. 4. B. Eaton Electrical Inc.; Cutler-Hammer Business Unit. General Electric Company; GE Consumer & Industrial - Electrical Distribution. Siemens Energy & Automation, Inc. Square D; a brand of Schneider Electric. Molded-Case Circuit Breaker (MCCB): Comply with UL 489, with interrupting capacity to meet available fault currents. 1. Molded-Case Circuit-Breaker (MCCB) Features and Accessories: a. b. c. d. e. PANELBOARDS Standard frame sizes, trip ratings, and number of poles. Lugs: Compression style, suitable for number, size, trip ratings, and conductor materials. Application Listing: Appropriate for application; Type SWD for switching fluorescent lighting loads; Type HID for feeding fluorescent and highintensity discharge (HID) lighting circuits. Communication Capability: Circuit-breaker-mounted communication module with functions and features compatible with power monitoring and control system specified in Division 26 Section "Electrical Power Monitoring and Control." Handle Padlocking Device: Fixed attachment, for locking circuit-breaker handle in on position. 262416 - 3 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION f. Handle Clamp: Loose attachment, for holding circuit-breaker handle in on position. PART 3 - EXECUTION 3.1 INSTALLATION A. Receive, inspect, handle, store and install panelboards and accessories according to NECA 407. B. Mount top of trim 90 inches maximum above finished floor unless otherwise indicated. C. Mount panelboard cabinet plumb and rigid without distortion of box. Mount recessed panelboards with fronts uniformly flush with wall finish and mating with back box. D. Install overcurrent protective devices and controllers not already factory installed. 1. Set field-adjustable, circuit-breaker trip ranges. E. Install filler plates in unused spaces. F. In ceiling areas stub four 1-inch empty conduits from panelboard into accessible ceiling space or space designated to be ceiling space in the future. Stub four 1-inch empty conduits into raised floor space or below slab not on grade. G. Arrange conductors in gutters into groups and bundle and wrap with wire ties. H. Comply with NECA 1. 3.2 IDENTIFICATION A. Identify field-installed conductors, interconnecting wiring, and components; provide warning signs complying with Division 26 Section "Identification for Electrical Systems." B. Create a directory to indicate installed circuit loads and incorporating City's final room designations. Obtain approval before installing. Use a computer or typewriter to create directory; handwritten directories are not acceptable. C. Panelboard Nameplates: Label each panelboard with a nameplate complying with requirements for identification specified in Division 26 Section "Identification for Electrical Systems." D. Device Nameplates: Label each branch circuit device in distribution panelboards with a nameplate complying with requirements for identification specified in Division 26 Section "Identification for Electrical Systems." PANELBOARDS 262416 - 4 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION 3.3 FIELD QUALITY CONTROL A. Perform tests and inspections. B. Acceptance Testing Preparation: 1. 2. C. Test insulation resistance for each panelboard bus, component, connecting supply, feeder, and control circuit. Test continuity of each circuit. Tests and Inspections: 1. 2. Perform each visual and mechanical inspection and electrical test stated in NETA Acceptance Testing Specification. Certify compliance with test parameters. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest. D. Panelboards will be considered defective if they do not pass tests and inspections. E. Prepare test and inspection reports, including a certified report that identifies panelboards included and that describes scanning results. Include notation of deficiencies detected, remedial action taken, and observations after remedial action. END OF SECTION 262416 PANELBOARDS 262416 - 5 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION SECTION 270000 - VOICE AND DATA DISTRIBUTION SYSTEM PART 1 – GENERAL 1.1 SECTIONS A. Telecommunications service entrance. B. Premises wiring systems. C. Broadband type cable video systems. D. Approved parts and accessories list. 1.2 REFERENCES A. Building Industry Consulting Services International (BiCSi) “TelecommunicationsDistributions Methods Manual,” 2006 11th Edition. B. B. Electronic Industries Association/Telecommunications Industry Association (EIA/TIA) -568B “ Commercial Building Telecommunications Wiring Standard.” C. EIS/TIA-569 “Commercial Building Standards for Telecommunications Pathways and Spaces.” D. EIA/TIA-606 “Administration Standards for the Telecommunications Infrastructure of Commercial Buildings.” E. EIA/TIA-607 “Commercial Building Grounding Bonding Requirements.” F. National Fire Protection Agency (NFPA) 70 - National Electrical Code (NEC), 1996. G. Institute of Electrical and Electronic Engineers (IEEE) 802.3 Carrier Sense Multiple Access with Collision Detection (Ethernet and 10Base-T). H. Avaya Systimax Cabling System (ACS) Manual. I. Federal Communications Commission (FCC) Title 47, Code of Federal Regulations. Part 68. 1.3 1.4 QUALITY ASSURANCE A. All work accomplished shall be in accordance with the most current BiCSi Methods Manual. B. All premise wiring installations shall be in accordance with Avaya Systimax ACS Guidelines. SUBMITTALS VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 1 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION A. Before installation of any wire or equipment, shop drawings shall be submitted to the Department of Telecommunications for approval. B. Installation details indicating cable routing and system configuration shall be included on shop drawings submitted for approval. C. All equipment and parts utilized shall be pre-approved by the Department of Telecommunications Services. 1.5 RECORD DOCUMENTS A. 1.6 All service entrance conduit, termination backboards, outlet boxes, messenger cable, raceways and cable trays, pull boxes equipment boxes, cable plant and associated equipment location shall be accurately recorded using AutoCAD. These data shall be provided to the Department of Telecommunications Services prior to final acceptance. QUALIFICATIONS A. 1.7 Installation of all inside wire, equipment, terminations and associated services shall be performed by Avaya Inc. or a company that is currently an Avaya Inc. Authorized Systimax Certified Premise Distribution System Value Added Re-seller. MAINTENANCE SERVICE A. All installations shall carry an Avaya warranty covering products, applications and workmanship for no less than 15 years. All other non-Systimax products and workmanship shall carry warranties equal to or greater than the Systimax warranty from date of acceptance by the University. PART 2. PRODUCTS 2.1 STATION COPPER CABLE A. Unless otherwise specified by the University, all UTP station copper cable supporting voice and data communications requirements shall be Systimax (where XX is either 10 or 20 depending on installation type), and shall meet Category 5e performance specifications along with the following technical specifications: Pairs/Gauge: Insulation: Outside Diamete Maximum DC Resistance: Normal Mutual Capacitance: Attenuation: Characteristic Impedance: 4/24 AWG PVC (1061) or Teflon (2061) r: 0.22 in (.56cm) 28.6 Ohms/1000ft 14 nF/1000 ft @ 1 kHz 6.3 dB/1000 ft @ 1 kHz 100 Ohms +/- 15% @ 1-25 Mhz B. The cable sheath color for all UTP voice and data communications cabling shall be “blue” unless another color is approved by this department. VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 2 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION C. All copper cable and jumpers shall conform to REA color guides meeting article 725-30, 3(B) 1, 2 and 3. 2.2 DIMENSIONS TO INNERDUCTS A. 2.3 Fiber - 1" Copper - 1.5" Coaxial - 1.5" RISER COPPER CABLE A. All UTP riser copper cable supporting voice communication requirements shall be solid-copper conductors, 24 AWG, paired, dual-insulated, semi-rigid PVC skin over foamed PE, Avaya ARMM XXXR6060 (where XXX is the number of pairs), and shall meet the following specifications: Gauge: DC Resistance: Mutual Capacitance: Characteristic Impedance: Attenuation: 24 AWG solid copper conductor, UTP 26.5 Ohms/1000 ft 16 mF/1000 ft 100 Ohms +/- 15% @ 1-16MHz 7.1 dB/1000 ft @ 1MHz; 32 dB/1000ft @ 16MHz B. All UTP riser copper cable supporting data communication requirements shall be solid-copper conductors, 24 AWG, paired, dual-insulated, semi-rigid PVC skin over foamed PE, Avaya 1061C 25 pair cable and shall meet Category 5e performance specifications along with the following specifications: Gauge: DC Resistance: Mutual Capacitance: Characteristic Impedance: Attenuation: 2.4 24 AWG solid copper conductor, UTP 28.6 Ohms/1000 ft 14 pF/1000 ft 100 Ohms +/- 15% @ 1-100MHz 6.3 dB/1000 ft @ 1MHz; 67dB/1000ft @ 100MHz UNDERGROUND COPPER CABLES A. All underground copper cable supporting voice communication requirements shall be 24 AWG, paired, dual-insulated with foam skin and plastic, flooded with FLEXGEL filling compound and surrounded by an aluminum steel polyethylene (ASP) sheath. And shall meet the following specifications: Gauge: DC Resistance: Mutual Capacitance: Characteristic Impedance: Attenuation: 2.5 24 AWG, solid copper conductor 27,3 Ohms/1000ft 15.7 nF/1000ft @ 1kHz 100 Ohms 6.4 dB/1000ft CABLE PROTECTORS A. For all copper cable exposed to lightning/electrical over-wattage and sneak currents as defined by NFPA and NEC, wide gap, gas-tube surge arresters shall be provided. VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 3 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION B. Communications equipments and circuits exposed to voltages and sneak currents shall have 188-type Multipair Protectors panels installed. 2.6 SINGLEMODE FIBER OPTIC CABLE A. All singlemode fiber (indoor applications) shall meet the following technical specifications: Core Type: 8.3 microns Core Diameter: 125 +/- 1 microns Cladding Non-Circularity: 1 % Maximum Core/Clad Concentricity Error: Coating Diameter: 250 +/-15 Microns Minimum Operating Temperature Range: -40 to +158 degrees F Wavelength Windows: Dual-1310nm & 1550nm Maximum Attention: 0.4dB/km @ 1310nm 0.3dB/km @ 1550nm B. All singlemode fiber cable used shall have the following physical characteristics: Cable Core: Building interior: Building exterior: 900 micron O.D. color coded PVC buffering surrounded by Aramid yarn strength member. Loose tube LXE Lightpack core filled with waterblocking compound surrounded by non-metallic strength member. Cable Composition: Building Interior riser: Building exterior: Cable Strength: OFNR PVC jacket Non-metallic dielectric, HDPE jacket. Maximum pulling tension - 600 lbs. Maximum Bend Radii: After installation (<30% max. Pull tension) 10 times cable diameter. During installation (<30% max. Pull tension) 20 times cable diameter. Fiber Identification:Color coding system adequate to unambiguously identify each fiber. 2.8 OPTICAL FIBER TERMINATIONS A. All singlemode optical fiber cable shall be installed with a split-ferrule alignment sleeve and a precision ceramic tip. All optical fiber connectors shall meet the following specifications: Connector Type: Fiber outside diameter: Loss Repeat: Axial Load Minimum: Temperature Stability: 2-9 ST 125 microns Nominal <0.2 dB per 250 reconnects 35 lbs Minimum +/- 0.1 dB Maximum form -40 to +85C OPTICAL PATCH CORDS A. Provide an optical patch cord for every termination in the communication rooms. The optical patch cords shall be FL2E-E for multimode and FS1E-E for singlemode cables. 2-10 CONNECTING BLOCKS VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 4 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION A. All UTP copper cable utilized for voice and data applications shall be terminated on a highdensity, Avaya, RJ-45 patch panel. B. All optical fiber cable in the Intermediate Distribution Frame (IDF) and the Building Distribution Frame (BDF) rooms shall be terminated in Avaya termination shelves. 2.11 STATION COAX CABLE A. All station coaxial cable in facilities supporting video communications requirements shall be R.-6/U Belden 89248 (Non-Plenum) or R.-6/U Belden 82248 (Plenum) or a University approved equivalent. 2.12 RISER COAXIAL CABLE A. All station coaxial cable in facilities supporting video communications requirements shall be R.11/U Belden 89292 or a University approved equivalent. 2.13 A. 2.14 UNDERGROUND COAXIAL CABLE All interbuilding coaxial cable supporting video communications requirements shall be CommScope coaxial trunk cable, P-3-75-500JCASS or a University approved equivalent. VOICE/DATA JACKS AND COVER PLATES A. The “pinout” wiring assignment for the 4-pair UTP copper cable for both voice and data communications for the telecommunications outlet jack and the IDF connection shall be consistent with EIA/TIA 568B. B. All wall outlets supporting voice and data communications requirements shall be wired with a minimum of four (4) UTP Category 5e, four (4) pair wires (2 voice and 2 data). Exceptions will be made for Emergency, Elevator, Courtesy and Pay Telephones as appropriate. 2.15 2.16 A. 2.17 J-Hooks and Pathways All J-Hooks shall be provided with a center hung, triple tiered, six hook cable support system with a maximum spacing specified as not greater than four feet (4'). Ductbank Innerliners A. Innerliner is required in OSP ducts. Use of any existing duct or innerliner must be pre-approved by the Department of Telecommunications Services. B. Innerliner shall conform to the following University color code: Media Fiber Copper Coaxial Innerliner Color Orange Black Yellow VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 5 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION C. 2.18 A. 2.19 All innerduct shall be provided with a minimum 200 test-rated pull line. CABLE LUBRICANT Cable pulling lubricant, Ideal Yellow 77 or a University approved equal, shall be utilized when pulling all backbone cable through conduit. CASES AND SPLICES A. All building entrance splice cases shall be Avaya type 2400 series fiber optic cable grounding closures and 3-M closures for copper, both with accessories. B. All OSP cable splice cases shall be perform line products, stainless steel with filling flange with a universal approved re-enterable encapsulate. 2.20 A. 2.21 A. FIRESTOPPING Firestopping protection shall meet NFPA Life Safety Code #101, 6-2.3.6, “Penetrations and Miscellaneous Openings and Fire Barriers” and the NEC 300.21 “Fire Stopping” regulations and standards. ACCEPTABLE EQUIPMENT Any telecommunications equipment require for this project, but not listed in the University of Central Missouri (UCM) Standards for Inter/Intra-Building Voice and Data Distribution Systems dated July 25, 1999 (Updated January 7, 2008) must be approved by the UCM Depart of Telecommunications PART 3. EXECUTION 3.1 SYSTEM DESIGN A. The cabling system to support voice, data and video requirements shall be designed in accordance with Avaya, BiCSi, EIA/TIA, NFPA, NEC, IEEE, and regulations, requirements and recommended guidelines, as well as building and electrical codes applicable to the State of Missouri. B. All cabling systems shall be designed and installed in a manner that provides mechanical integrity and symmetry for the cabling media and any associated frames and racks. The design and installation shall also offer ease of access and suitable for future rearrangements and changes. C. The transmission media shall be installed through a network of cable trays, J-Hooks, conduit, sleeves, and chases which interconnect the various room and floors of the building. 3.2 TELECOMMUNICATIONS CLOSETS A. All Telecommunications Closets will be a minimum of 8’ (wide) by 12’ (long). B. Unless otherwise specified in this document, the design and construction of Telecommunications Closets in UCM facilities will adhere to all requirements and specifications in the BICSI VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 6 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION “Telecommunications Distributions Methods Manual,” 2006 11th Edition section 6 labeled “Telecommunications Closets”. 3.3 FORBIDDEN WORK A. Other than entrance splices, no cable splices shall be allowed within the building. B. Aerial cable construction shall not be permitted. 3.4 CONNECTING TO EXISTING SYSTEM A. 3.5 Splicing shall only be allowed in manholes or at building entrance locations. Splice cases in manholes shall be securely supported by support hooks on cable racks not more than two (2) feet away from the splice case. CABLE PLANT LABELING A. All labeling shall be clear, securely affixed, and consistent on both ends of each installed cable. All labeling schemes shall be approved in advance by the Department of Telecommunications Services. B. All labeling shall conform to established CIRCUIT ID standards. The CIRCUIT ID provides an accurate method of identifying components used in network connectivity. To maintain that accuracy, proper labeling must be applied to the wall plates, racks, patch panels, switches, hubs, and other electronic devices. The components of a CIRCUIT ID, an example, and a detailed explanation are shown below. |______CIRC NAME ______|__PANEL #__|_____________ SWITCH ID __________________| BLDG - WALL JACK/port# (P-P PORT #) BLDG – FLR – DATA RM # - RACK# - SWITCH#/port# Example: ADM-304A-1/b (C42) ADM-3-LAV-1-3/0.04 BLDG Use the TLA (three letter acronym) for each building. WALL JACK - The WALL JACK is what you will find as the label of the wall jack. The label should use the TLA as stated above. Rooms within a Suite should be labeled with a capital letter immediately after the room number. When there is more than one wall jack per room number, then an extra number will be used preceded by a dash and beginning with 1. See example above. Most often the RM and the WALL JACK are the same, but there are discrepancies, which should be corrected. /port# - After the WALL JACK put a forward slash (/), then indicate which port, i.e., a, b, c, or d, is being activated. (P-P PORT#) - This part of the CIRCUIT ID indicates which patch panel and port the WALL JACK terminates to. Each patch panel should be labeled with an alpha character beginning with “A”. The top most patch panel is A, the next one down B, and so on. The patch panel shall have numbers assigned to each port, with a label above or below it. BLDG - Same as above. VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 7 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION FLR - Indicate the floor that the data closet is on. DATA RM - Indicate the room number of the data closet. RACK - Indicate which rack the equipment is installed in. If there are no labels, then start with the rack which is closest to the wall and refer to it as “1”. Then mentally label each rack as it increases in distance away from the first rack. SWITCH# - Indicate which device this is on the rack. If the device is not labeled, start from the top and count down. Do not include the BEP router or switch. If more than one rack of switches exists, switch labeling and identification follows the same rules as rack labeling. /port# - Indicate the port on the switch being used. 3.6 TESTING AND ACCEPTANCE A. Prior to acceptance, all “As-Built” and technical documentation shall be received and approved by the Department of Telecommunications. As-built documentation shall include the complete and notarized original copy of the Avaya Systimax Cabling System Registration Documentation. B. All copper cable plant testing shall diagnose at a minimum, the presence of all open-loop conductors, noisy lines and distortion, low-loop current, high-loop current, ringer failures, grounded, shorted or crossed conductors, dB loss, and split conductors. Continuity test must be performed on all pairs installed. All testing shall be performed end to end. All data connections shall be tested as described in the draft IEEE 802.3J “Physical Signaling” for support of 10Base-T requirements. C. Optical fiber cable testing shall at a minimum, quantify the attenuation range, optical loss, bandwidth and misalignment. All optical fiber shall be tested after fiber has been installed and splices have been completed. All optical fiber shall be tested at all applicable wavelengths. For all fiber terminate between the BDF and the main campus service, testing shall include an Optical Time Domain Reflector (OTDR) and a Single-Mode Optical Loss Test Set (SMOLTS). For optical fiber testing between the BDF and IDF, loss testing through the use of a SMOLTS shall be required. All fiber found to be defective, shall be replaced at no cost to the University. All traces and results shall be provided to the University for approval prior to acceptance. D. Coaxial cable and video signal testing shall be performed in the following manner to verify correct installation of coaxial cable and video system electronics: E. Input Signal @ 450MHz After pad & equalizer Output @ 450MHz Output @ 175.2MHz +11 dB +/- 1 dB +40 dBmv =40 dBmv The output of all directional couplers and FFT’s shall be at least +9 dBmv VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 8 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION UNIVERSITY of CENTRAL MISSOURI APPROVED EQUIPMENT LIST NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 ITEM NUMBER LD5EI6-A CFX5EI-X ICFC5EI-X RAFC5EI-X OCFX5EI-X JBX3510EI-A TM3S8-C PLT2S-M PLT3S-M 103 801 247 103 801 254 108 232 737 108 333 154 108 320 045 5EXHP4P24-BL-P-MAX-GP 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 CPC6642-03F005 CPC6642-03F007 L-7200-25-W L-9200-06-V L-9200-12V L-9200-25-V L-9200-06-B L-9200-12-B L-9200-25-B L-9200-06-A L-9200-12-A L-9200-25-A 255444VBA20M 250044VBA25M 006544-VM2-PAK 31 32 33 34 35 36 MP1P 107 535 585 107 059 909 107 831 141 108 168 477 57002-703 37 57004-703 38 39 30130-719 12831-703 40 12830-703 DESCRIPTION LATCH DUCT ELECT IVORY 6 FT P/FT (raceway, 6' section) LD5 COUP FTG ELEC IVORY (coupler fitting) IV CORNER FTG (inside corner fitting, ivory) IV ANGLE FTG (right angle fitting, ivory) IV CORNER FTG (outside corner fitting, ivory) 1G BASE&COVER (single gang box, ivory) CABLE TIE MOUNT (100/pkg) LOCKING TIE BULK-PK, 7 3/8" (1,000/pkg) LOCKING TIE BULK-PK, 11 1/2" (1,000/pkg) BLOCK CONN 10PK 110C-4 (4-pair connecting block,10/pkg) BLOCK CONN 10PK 110C-5 (5-pair connecting block, 10/pkg) MODULE MPS100E-246 IVORY (Cat-5 jack) FACEPLATE M14LE-246 (straight quadplex faceplate ivory) PANEL KIT PM 2150B-48 (48 port patchmax patch panel) 760 041 913 PowerSUM 2061F BL POP (Cat-5 wire, 1,000ft/box) NOTE: WANT TO PURCHASE WIRE WITH THE BEST PRICE, COLOR IS NO OBJECT. D8PS GRAY 5 FT (patch cords) D8PS GRAY 7 FT (patch cords) FUL-MOD 4C LNCRD 25FT SS FUL-MOD 4C HNDST 6 LTASH FUL-MOD 4C HNDST 12 LTASH FUL-MOD 4C HNDST 25 LTASH FUL-MOD 4C HNDST 6 WHT FUL-MOD 4C HNDST 12 WHT FUL-MOD 4C HNDST 25 WHT FUL-MOD 4C HNDST 6 BLK FUL-MOD 4C HNDST 12 BLK FUL-MOD 4C HNDST 25 BLK WALL F-M W/VOL CONTROL (miniature wall phone, ash) T-T DESK STD W/VOL CNTRL (full mod. Telephone, ash) HANDSET VOLUM CTL ASH (handset assembly, complete) (mod. G type for 2500-2554 style phone, ash) SINGLE GANG MNTG PLATE (mounting bracket, 100/pkg) BRACKET W/MTG SCREWS BLOCK110DW2 100 WRG PLSTC (wiring block) 110B3 TROUGH (trough cable support rings) DUPLEX OUTLET FACE PLATE GLOBAL STD RACK PACK, STD RACK PLUS 2-3.65", VERTICAL MGR (BLACK) GLOBAL STD RACK PACK, STD RACK PLUS 2-6.00", VERTICAL MGR (BLACK) 2RMU CABLE MGR GLOBAL VERTICAL CABLE MANAGER, 6" W X 6.76" D., CABLE MANAGER GLOBAL VERTICAL CABLE MANAGER, NARROW 3.65"W X 6.76"D VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 9 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION END SECTION 27000 VOICE DATA AND DISTRIBUTION SYSTEMS 270000 ‐ 10 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Manual fire-alarm boxes. 2. System smoke detectors. 3. Heat detectors. 4. Notification appliances. 5. Addressable interface device. B. Related Requirements: 1. Section 280513 "Conductors for Fire Alarm" for cables and conductors for fire-alarm systems. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product, including furnished options and accessories. B. Shop Drawings: For fire-alarm system. 1. Comply with recommendations and requirements in the "Documentation" section of the "Fundamentals" chapter in NFPA 72. 2. Include plans, elevations, sections, details, and attachments to other work. 3. Include details of equipment assemblies. Indicate dimensions, weights, loads, required clearances, method of field assembly, components, and locations. Indicate conductor sizes, indicate termination locations and requirements, and distinguish between factory and field wiring. 4. Detail assembly and support requirements. 5. Include voltage drop calculations for notification-appliance circuits. 6. Include battery-size calculations. 7. Include input/output matrix. 8. Include statement from manufacturer that all equipment and components have been tested as a system and meet all requirements in this Specification and in NFPA 72. 9. Include performance parameters and installation details for each detector. 10. Verify that each duct detector is listed for complete range of air velocity, temperature, and humidity possible when air-handling system is operating. 11. Include plans, sections, and elevations of heating, ventilating, and air-conditioning ducts, drawn to scale; coordinate location of duct smoke detectors and access to them. a. Show critical dimensions that relate to placement and support of sampling tubes, detector housing, and remote status and alarm indicators. b. Show field wiring required for HVAC unit shutdown on alarm. c. Locate detectors according to manufacturer's written recommendations. 12. Include floor plans to indicate final outlet locations showing address of each addressable device. Show size and route of cable and conduits and point-to-point wiring diagrams. C. General Submittal Requirements: 1. Submittals shall be approved by authorities having jurisdiction prior to submitting them to Architect. DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 1 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION 2. D. 1.3 Shop Drawings shall be prepared by persons with the following qualifications: a. Trained and certified by manufacturer in fire-alarm system design. b. NICET-certified, fire-alarm technician; Level IV minimum. c. Licensed or certified by authorities having jurisdiction. Delegated-Design Submittal: For notification appliances and smoke and heat detectors, in addition to submittals listed above, indicate compliance with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation. 1. Drawings showing the location of each notification appliance and smoke and heat detector, ratings of each, and installation details as needed to comply with listing conditions of the device. 2. Design Calculations: Calculate requirements for selecting the spacing and sensitivity of detection, complying with NFPA 72. Calculate spacing and intensities for strobe signals and sound-pressure levels for audible appliances. 3. Indicate audible appliances required to produce square wave signal per NFPA 72. INFORMATIONAL SUBMITTALS A. Qualification Data: For Installer. B. Field quality-control reports. C. Sample warranty. 1.4 CLOSEOUT SUBMITTALS A. Operation and Maintenance Data: For fire-alarm systems and components to include in emergency, operation, and maintenance manuals. 1. In addition to items specified in Section 017823 "Operation and Maintenance Data," include the following: a. Comply with the "Records" section of the "Inspection, Testing and Maintenance" chapter in NFPA 72. b. Provide "Fire Alarm and Emergency Communications System Record of Completion Documents" according to the "Completion Documents" Article in the "Documentation" section of the "Fundamentals" chapter in NFPA 72. c. Complete wiring diagrams showing connections between all devices and equipment. d. Riser diagram. e. Record copy of site-specific software. f. Provide "Inspection and Testing Form" according to the "Inspection, Testing and Maintenance" chapter in NFPA 72, and include the following: 1) Equipment tested. 2) Frequency of testing of installed components. 3) Frequency of inspection of installed components. 4) Requirements and recommendations related to results of maintenance. 5) Manufacturer's user training manuals. g. Manufacturer's required maintenance related to system warranty requirements. h. Abbreviated operating instructions for mounting at fire-alarm control unit and each annunciator unit. B. Software and Firmware Operational Documentation: 1. Software operating and upgrade manuals. DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 2 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION 2. 3. 4. 1.5 Program Software Backup: On magnetic media or compact disk, complete with data files. Device address list. Printout of software application and graphic screens. QUALITY ASSURANCE A. 1.6 Installer Qualifications: Personnel shall be trained and certified by manufacturer for installation of units required for this Project. WARRANTY A. Special Warranty: Manufacturer agrees to repair or replace fire-alarm system equipment and components that fail in materials or workmanship within specified warranty period. 1. Warranty Extent: All equipment and components not covered in the Maintenance Service Agreement. 2. Warranty Period: Five years from date of Substantial Completion. PART 2 - PRODUCTS 2.1 SYSTEM DESCRIPTION A. Source Limitations for Fire-Alarm System and Components: Components shall be compatible with, and operate as an extension of, existing KC Zoo system. Provide system manufacturer's certification that all components provided have been tested as, and will operate as, a system. B. Noncoded, addressable system, with multiplexed signal transmission and horn/strobe evacuation. C. Automatic sensitivity control of certain smoke detectors. D. All components provided shall be listed for use with the selected system. E. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. 2.2 SYSTEMS OPERATIONAL DESCRIPTION A. Fire-alarm signal initiation shall be by one or more of the following devices and systems: 1. Manual stations. 2. Heat detectors. 3. Smoke detectors. 4. Duct smoke detectors. B. Fire-alarm signal shall initiate the following actions: 1. Continuously operate alarm notification appliances. 2. Identify alarm and specific initiating device at fire-alarm control unit and remote annunciators. 3. Transmit an alarm signal to the remote alarm receiving station. 4. Switch heating, ventilating, and air-conditioning equipment controls to fire-alarm mode. DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 3 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION 5. 6. 7. 8. 9. C. Close smoke dampers in air ducts of designated air-conditioning duct systems. Activate preaction system. Activate emergency lighting control. Activate emergency shutoffs for gas and fuel supplies. Record events in the system memory. Supervisory signal initiation shall be by one or more of the following devices and actions: D. 1. Loss of communication with any panel on the network. E. System trouble signal initiation shall be by one or more of the following devices and actions: 1. Open circuits, shorts, and grounds in designated circuits. 2. Opening, tampering with, or removing alarm-initiating and supervisory signal-initiating devices. 3. Loss of communication with any addressable sensor, input module, relay, control module, or remote annunciator. 4. Loss of primary power at fire-alarm control unit. 5. Ground or a single break in internal circuits of fire-alarm control unit. 6. Abnormal ac voltage at fire-alarm control unit. 7. Break in standby battery circuitry. 8. Failure of battery charging. 9. Abnormal position of any switch at fire-alarm control unit or annunciator. F. System Supervisory Signal Actions: 1. Initiate notification appliances. 2. Identify specific device initiating the event at fire-alarm control unit and remote annunciator. 3. After a time delay of 200 seconds, transmit a trouble or supervisory signal to the remote alarm receiving station. 2.3 MANUAL FIRE-ALARM BOXES A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. AMSECO - A Potter Brand. 2. Bosch Security Systems. 3. Cooper Wheelock. 4. Faraday. 5. Federal Signal Corporation. 6. Fike Corporation. 7. Fire-Lite Alarms. 8. GAMEWELL. 9. GE UTC Fire & Security; A United Technologies Company. 10. Keltron Corporation. 11. Mircom Technologies, Ltd. 12. Notifier. 13. Siemens Industry, Inc.; Fire Safety Division. 14. Silent Knight. 15. SimplexGrinnell LP. 16. System Sensor. DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 4 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION B. 2.4 General Requirements for Manual Fire-Alarm Boxes: Comply with UL 38. 1. Single-action mechanism, pull-lever type; with integral addressable module arranged to communicate manual-station status (normal, alarm, or trouble) to fire-alarm control unit. 2. Station Reset: Key- or wrench-operated switch. SYSTEM SMOKE DETECTORS A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. Bosch Security Systems. 2. Faraday. 3. Fenwal Protection Systems; A UTC Fire & Security Company. 4. Fire-Lite Alarms. 5. GAMEWELL. 6. GE UTC Fire & Security; A United Technologies Company. 7. Gentex Corporation. 8. Harrington Signal, Inc. 9. Keltron Corporation. 10. Mircom Technologies, Ltd. 11. Notifier. 12. Siemens Industry, Inc.; Fire Safety Division. 13. Silent Knight. 14. SimplexGrinnell LP. 15. System Sensor. B. General Requirements for System Smoke Detectors: 1. Comply with UL 268; operating at 24-V dc, nominal. 2. Detectors shall be two-wire type. 3. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to fire-alarm control unit. 4. Base Mounting: Detector and associated electronic components shall be mounted in a twist-lock module that connects to a fixed base. Provide terminals in the fixed base for connection to building wiring. 5. Self-Restoring: Detectors do not require resetting or readjustment after actuation to restore them to normal operation. 6. Integral Visual-Indicating Light: LED type, indicating detector has operated and power-on status. 7. Remote Control: Unless otherwise indicated, detectors shall be digital-addressable type, individually monitored at fire-alarm control unit for calibration, sensitivity, and alarm condition and individually adjustable for sensitivity by fire-alarm control unit. a. Rate-of-rise temperature characteristic of combination smoke- and heat-detection units shall be selectable at fire-alarm control unit for 15 or 20 deg F per minute. b. Fixed-temperature sensing characteristic of combination smoke- and heatdetection units shall be independent of rate-of-rise sensing and shall be settable at fire-alarm control unit to operate at 135 or 155 deg F. C. Photoelectric Smoke Detectors: 1. Detector address shall be accessible from fire-alarm control unit and shall be able to identify the detector's location within the system and its sensitivity setting. 2. An operator at fire-alarm control unit, having the designated access level, shall be able to manually access the following for each detector: a. Primary status. DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 5 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION b. c. d. e. Device type. Present average value. Present sensitivity selected. Sensor range (normal, dirty, etc.). D. Ionization Smoke Detector: 1. Detector address shall be accessible from fire-alarm control unit and shall be able to identify the detector's location within the system and its sensitivity setting. 2. An operator at fire-alarm control unit, having the designated access level, shall be able to manually access the following for each detector: a. Primary status. b. Device type. c. Present average value. d. Present sensitivity selected. e. Sensor range (normal, dirty, etc.). E. Duct Smoke Detectors: Photoelectric type complying with UL 268A. 1. Detector address shall be accessible from fire-alarm control unit and shall be able to identify the detector's location within the system and its sensitivity setting. 2. An operator at fire-alarm control unit, having the designated access level, shall be able to manually access the following for each detector: a. Primary status. b. Device type. c. Present average value. d. Present sensitivity selected. e. Sensor range (normal, dirty, etc.). 3. Weatherproof Duct Housing Enclosure: NEMA 250, Type 4X; NRTL listed for use with the supplied detector for smoke detection in HVAC system ducts. 4. Each sensor shall have multiple levels of detection sensitivity. 5. Sampling Tubes: Design and dimensions as recommended by manufacturer for specific duct size, air velocity, and installation conditions where applied. 6. Relay Fan Shutdown: Fully programmable relay rated to interrupt fan motor-control circuit. 2.5 HEAT DETECTORS A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. Bosch Security Systems. 2. Faraday. 3. Fire-Lite Alarms. 4. GAMEWELL. 5. GE UTC Fire & Security; A United Technologies Company. 6. Gentex Corporation. 7. Harrington Signal, Inc. 8. Keltron Corporation. 9. Mircom Technologies, Ltd. 10. Notifier. 11. Siemens Industry, Inc.; Fire Safety Division. 12. Silent Knight. 13. SimplexGrinnell LP. 14. System Sensor. DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 6 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION B. General Requirements for Heat Detectors: Comply with UL 521. 1. Temperature sensors shall test for and communicate the sensitivity range of the device. C. Heat Detector, Combination Type: Actuated by either a fixed temperature or a rate of rise. 1. Mounting: Twist-lock base interchangeable with smoke-detector bases. 2. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to fire-alarm control unit. 2.6 NOTIFICATION APPLIANCES A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. Cooper Wheelock. 2. Federal Signal Corporation. 3. GE UTC Fire & Security; A United Technologies Company. 4. Gentex Corporation. 5. Harrington Signal, Inc. 6. Keltron Corporation. 7. Mircom Technologies, Ltd. 8. Siemens Industry, Inc.; Fire Safety Division. 9. SimplexGrinnell LP. 10. System Sensor. B. General Requirements for Notification Appliances: Connected to notification-appliance signal circuits, zoned as indicated, equipped for mounting as indicated, and with screw terminals for system connections. 1. Combination Devices: Factory-integrated audible and visible devices in a single-mounting assembly, equipped for mounting as indicated, and with screw terminals for system connections. C. Chimes: Vibrating type. D. Horns: Electric-vibrating-polarized type, 24-V dc; with provision for housing the operating mechanism behind a grille. Comply with UL 464. E. Visible Notification Appliances: Xenon strobe lights complying with UL 1971, with clear or nominal white polycarbonate lens mounted on an aluminum faceplate. The word "FIRE" is engraved in minimum 1-inch- high letters on the lens. 1. Mounting: Wall mounted unless otherwise indicated. 2. Flashing shall be in a temporal pattern, synchronized with other units. 3. Strobe Leads: Factory connected to screw terminals. 4. Mounting Faceplate: Factory finished, red. 2.7 ADDRESSABLE INTERFACE DEVICE A. General: 1. Include address-setting means on the module. 2. Store an internal identifying code for control panel use to identify the module type. 3. Listed for controlling HVAC fan motor controllers. DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 7 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION B. Monitor Module: Microelectronic module providing a system address for alarm-initiating devices for wired applications with normally open contacts. C. Integral Relay: Capable of providing a direct signal to circuit-breaker shunt trip for power shutdown. 1. Allow the control panel to switch the relay contacts on command. 2. Have a minimum of two normally open and two normally closed contacts available for field wiring. D. Control Module: 1. Operate notification devices. 2. Operate solenoids for use in sprinkler service. PART 3 - EXECUTION 3.1 EQUIPMENT INSTALLATION A. Comply with NFPA 72, NFPA 101, and requirements of authorities having jurisdiction for installation and testing of fire-alarm equipment. Install all electrical wiring to comply with requirements in NFPA 70 including, but not limited to, Article 760, "Fire Alarm Systems." B. Install wall-mounted equipment, with tops of cabinets not more than 78 inches above the finished floor. C. Manual Fire-Alarm Boxes: 1. Install manual fire-alarm box in the normal path of egress within 60 inches of the exit doorway. 2. Mount manual fire-alarm box on a background of a contrasting color. 3. The operable part of manual fire-alarm box shall be between 42 inches and 48 inches above floor level. All devices shall be mounted at the same height unless otherwise indicated. D. Smoke- or Heat-Detector Spacing: Comply with NFPA 72. E. Duct Smoke Detectors: Comply with NFPA 72 and NFPA 90A. Install sampling tubes so they extend the full width of duct. Tubes more than 36 inches long shall be supported at both ends. F. Remote Status and Alarm Indicators: Install in a visible location near each smoke detector, sprinkler water-flow switch, and valve-tamper switch that is not readily visible from normal viewing position. G. Audible Alarm-Indicating Devices: Install not less than 6 inches below the ceiling. Install bells and horns on flush-mounted back boxes with the device-operating mechanism concealed behind a grille. Install all devices at the same height unless otherwise indicated. H. Visible Alarm-Indicating Devices: Install adjacent to each alarm bell or alarm horn and at least 6 inches below the ceiling. Install all devices at the same height unless otherwise indicated. I. Device Location-Indicating Lights: Locate in public space near the device they monitor. DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 8 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION 3.2 PATHWAYS A. Pathways above recessed ceilings and in nonaccessible locations may be routed exposed. 1. Exposed pathways located less than 96 inches above the floor shall be installed in EMT. B. Exposed EMT shall be painted red enamel. 3.3 CONNECTIONS A. For fire-protection systems related to doors in fire-rated walls and partitions and to doors in smoke partitions, comply with requirements in Section 087100 "Door Hardware." Connect hardware and devices to fire-alarm system. 1. Verify that hardware and devices are listed for use with installed fire-alarm system before making connections. B. Make addressable connections with a supervised interface device to the following devices and systems. Install the interface device less than 36 inches from the device controlled. Make an addressable confirmation connection when such feedback is available at the device or system being controlled. 1. Electronically locked doors and access gates. 2. Supervisory connections at low-air-pressure switch of each dry-pipe sprinkler system. 3.4 IDENTIFICATION A. Identify system components, wiring, cabling, and terminals. Comply with requirements for identification specified in Section 260553 "Identification for Electrical Systems." B. Install framed instructions in a location visible from fire-alarm control unit. 3.5 GROUNDING A. Ground fire-alarm control unit and associated circuits; comply with IEEE 1100. Install a ground wire from main service ground to fire-alarm control unit. B. Ground shielded cables at the control panel location only. Insulate shield at device location. 3.6 FIELD QUALITY CONTROL A. Field tests shall be witnessed by authorities having jurisdiction. B. Perform the following tests and inspections with the assistance of a factory-authorized service representative: 1. Visual Inspection: Conduct visual inspection prior to testing. a. Inspection shall be based on completed record Drawings and system documentation that is required by NFPA 72 in its "Completion Documents, Preparation" table in the "Documentation" section of the "Fundamentals" chapter. b. Comply with the "Visual Inspection Frequencies" table in the "Inspection" section of the "Inspection, Testing and Maintenance" chapter in NFPA 72; retain the "Initial/Reacceptance" column and list only the installed components. DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 9 UNIVERSITY OF CENTRAL MISSOURI GREENWOOD COMMUNITY BUILDING ISSUED FOR BID SUBMISSION 2. 3. 4. 5. 6. System Testing: Comply with the "Test Methods" table in the "Testing" section of the "Inspection, Testing and Maintenance" chapter in NFPA 72. Test audible appliances for the public operating mode according to manufacturer's written instructions. Perform the test using a portable sound-level meter complying with Type 2 requirements in ANSI S1.4. Test audible appliances for the private operating mode according to manufacturer's written instructions. Test visible appliances for the public operating mode according to manufacturer's written instructions. Factory-authorized service representative shall prepare the "Fire Alarm System Record of Completion" in the "Documentation" section of the "Fundamentals" chapter in NFPA 72 and the "Inspection and Testing Form" in the "Records" section of the "Inspection, Testing and Maintenance" chapter in NFPA 72. C. Reacceptance Testing: Perform reacceptance testing to verify the proper operation of added or replaced devices and appliances. D. Fire-alarm system will be considered defective if it does not pass tests and inspections. E. Prepare test and inspection reports. 3.7 SOFTWARE SERVICE AGREEMENT A. Comply with UL 864. B. Technical Support: Beginning at Substantial Completion, service agreement shall include software support for one year. C. Upgrade Service: At Substantial Completion, update software to latest version. Install and program software upgrades that become available within one year from date of Substantial Completion. Upgrading software shall include operating system and new or revised licenses for using software. 3.8 DEMONSTRATION A. Train Owner's maintenance personnel to adjust, operate, and maintain fire-alarm system. END OF SECTION 283111 DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM 283111 - 10 By the order of: Roderick M. Woolen Buyer of Record END ADDENDUM