ISSUE 02 SAN JOSE CONVENTION CENTER EXPANSION & RENOVATION SEPTEMBER 2011 MONTHLY PROGRESS REPORT Project Summary CONTENTS Project Summary Expansion & Renovation Update Central Utility Plant Update Schedule of Subcontractors Documents /Permit Summary Safety Update September brought more progress in both the design and construction components of the project. Task Order 2a work commenced in order to advance design from 30 to 70% and work continued on-site with abatement and demolition of the old MLK Library. DESIGN Review of the 30% documents was completed by the various teams and major decisions were reached pertaining to options for both the Expansion and Renovation components of the project. Toward the end of the month, a series of meetings took place with in order to help advance the design of many facets of the project, including: the wireless system; plating kitchen; registration power and data needs; lighting design, security review and several code items. Bid Package 2 was issued to prequalified subcontractors for procurement of Fire Protection design-build services. The bid submission date is scheduled for October 7, 2011. CONSTRUCTION Cleveland Wrecking completed the grubbing of the site. In addition, the marquee board was disconnected, dismantled and stored. Abatement of the interior of the MLK Library continued through September. As the building interior soft gut started, additional samples were taken of various materials. Additional asbestos containing materials were identified and abated accordingly. Soft gut of the interiors continued upon completion of abatement utilizing a trash chute to evacuate materials from the building. Stair demolition was completed at the close of the month. The project team worked extensively to find opportunities to complete the demolition of both the MLK library building and the SJCC connection pieces, working around the hotel and convention center’s needs for quiet hours and designated quiet days. This coordination continues as we collectively try to balance the needs of the hoteliers, SJCC and construction schedule. Weekly meetings with the City, Team San Jose and Hunt continue in order to discuss project progress, resolve issues and coordinate activities with the Convention Center events schedule. renovation EXPANSION & DESIGN The 0-30% documents were submitted late last month, marking the first major design milestone. These documents were part of the deliverables due as part of Task Order 1a. September was spent gathering comments from the City and Team San Jose in order to validate the project budget and provide options for prioritization in order to further advance the documents for the forthcoming 70% design development submission. SEPTEMBER HIGHLIGHTS MLK abatement completed MLK exterior site clearing completed MLK interior soft-gut commenced Major decisions were reached related to scope priorities for advancing design A team meeting was convened September 21st to discuss renovation options. Some of the renovation priorities were identified as: ADA upgrades Operable partition replacement Ballroom A upgrades Plating /finishing kitchen enhancements Concourse restrooms Concourse power and data system infra structure At the close of September, several focused meetings were conducted among the team, Team San Jose and DPW in order to review comments received, coordinate among disciplines and further the overall design development effort. These meetings included : DAS/Wireless coordination with carriers Lighting Power/data locations Kitchen layout & equipment needs Security review Fire Department/Life Safety approach Substantial progress was made on the Expansion and Central Plant structural package as the team prepares for an October permit submission. CENTRAL PLANT DESIGN The Central Plant design advanced beyond the 70% completion stage in anticipation of 100% documents planned for issue next month. The team is was successful in revising the location / height of the cooling tower platform down from +13 to +7 above finished grade. This allowed the screen wall around the cooling towers to be reduced to a height of 29’. The generator radiator location has been moved to the ground to the west of the Cooling towers. Moving this off the roof saved structural framing improvements to the roof but the increased length between the generator and radiator will likely necessitate a booster pump. This location requires securing and screening the area. The solution moving forward is an 8’ green screen panel fence that would wrap around all of the existing exposed back flow units, gas meters, utility vent stack and provide yard space for equipment and service. Detailed scheduling of planned equipment cut-overs is currently underway and will be shared with the team once the approach is solidified. OCTOBER OUTLOOK Structural permit package submission 30-70% design completion Major demolition begins Procurement of fire protection, deep foundations, concrete, and steel packages d fountain will be disabled Abatement is slated for completion DESIGN & construction TEAM Design-Builder Hunt Construction Group, Inc. Architect POPULOUS Design Consultants HMC Architects (Design Support and Construction Administration) Rutherford & Chekene (Structural) JMH Weiss (Civil) CM Salter & Associates (Technology) JS Nolan & Associates (Lighting) Verde Design (Landscape Architect) URS (Geotechnical) Cini-Little (Food-Service) Affiliated Engineers (MPE) FACTS & FIGURES 95% of demolition spoils will be recycled Demolition spoils will equate to approximately 1300 truck loads of material MLK concrete will be crushed and brought back to the site as aggregate fill Design-Build Subcontractors ACCO Engineered Systems (Mechanical & Plumbing) Redwood City Electric (Electrical & Low Voltage) Design-Assist Subcontractors Webcor Concrete (Structural Concrete) * Indicates new to project Subcontractors Cleveland Wrecking (Abatement and Demolition) Vendors First Alarm (Site Security) ARS (Archaeological Observation) URS (Abatement Oversight) Sterling & Associates (Environmental Monitoring) DRAWINGS & specifications UPDATE Permit Issue Date Expires Package Title Abatement 8/19/11 12/15/11 No new packages issued this month SWPPP 8/30/11 N/A Demolition 9/1/11 1/13/12 Issue Date WWW.HUNT-CONNECT.COM/SJCC SAFETY UPDATE Every individual who will access the site is required to attend a one-time Safety Orientation prior to arrival on-site and/or start of work. Upon completion of orientation, individuals will be badged and an orientation sticker will be placed on their hard hat. CONTRACTORS ON-SITE Visitors must check in, sign the project Hold Harmless Agreement and be escorted at all times by a designated person who has received Safety Orientation. SAFETY FOCUS During the month of September, safety orientation was conducted for 28 new employees. There were no incidents. Industrial Hygiene baseline monitoring for noise and air quality started on August 29. Test results have been submitted to the City of San Jose. There were no notable concerns in this report. First Alarm Security started security coverage September 6, 2011. Hours of operation will be Monday-Thursday 7:00pm-7:00am. Friday coverage will start at 7:00pm until 7:00am Monday morning. Security will patrol the outside perimeter fence. 1. Cleveland Wrecking Company (CWC) 2. Redwood City Electric 3. ACCO Engineered Systems* *Design Coordination Only September’s project Safety Focus was Job Safety Analysis (JSA). JSA is to give employees the opportunity to think about each of the steps involved in completing a task before they begin the work. Each step analysis is to identify the potential hazards, and recommend actions or procedures to eliminate or reduce those hazards. JSA should include: The steps required to complete the task and the hazards associated with each step. The tools needed to get the task completed and hazards each tool presents. The materials needed to complete the task and any hazards they pose. Safety equipment needed to complete the task The procedures required to prevent injuries. The steps each employee will take to complete the task safely. The goal is to identify potential safety problems and know the solution before starting the task. JSAs are like PPE, they only help if you understand them and use them. San Jose McEnery Convention Center Expansion & Renovation Project 200 East Santa Clara Street, 14th Floor San Jose, CA 95113 T: 408.535.8403 Watch our progress at www.hunt-connect.com/sjcc Monthly Progress Report Issue 02 September 2011