Development of a Stand-alone Solar Powered Bus Stop Development of a Stand-alone Solar Powered Bus Stop Mohd Afzanizam Mohd Rosli1, Mohd Zaid Akop 2, Muhd Ridzuan Mansor3, Sivarao S.4 Faculty of Mechanical Engineering, Universiti Teknikal Malaysia Melaka, 76100 Durian Tunggal, Melaka. 4 Faculty of Manufacturing Engineering, Universiti Teknikal Malaysia Development of 76100 a Stand-alone Solar Powered Melaka, Durian Tunggal, Melaka. Bus Stop 1,2,3 Mohd Afzanizam MohdEmail: Rosli1, Mohd Zaid Akop 2, Muhd Ridzuan Mansor3, Sivarao S.4 1afzanizam@utem.edu.my 1,2,3 Faculty of Mechanical Engineering, Universiti Teknikal Malaysia Melaka, 76100 Durian Tunggal, Melaka. ABSTRACT 4 Faculty of Manufacturing Engineering, Universiti Teknikal Malaysia Melaka, 76100 Durian Tunggal, Melaka. This paper presents the development of a stand-alone solar photovoltaic (PV) system for busEmail: stop 1afzanizam@utem.edu.my at Universiti Teknikal Malaysia Melaka, Malaysia. The design intent for the bus stop was to provide lighting and information to the bus stop users using reliable renewable energy ABSTRACT system as well as to promote green technology awareness to the university stand-alone system wassolar designed to power twosystem units for of bus stop at This paperresidences. presents theThe development of PV a stand-alone photovoltaic (PV) Universiti CFL Teknikal Malaysia Malaysia. designatintent for stop. the bus stop was to provide lamps and anMelaka, LED display unit The installed the bus Five units lighting and to the bus stop users using reliable renewable system of information polycrystalline photovoltaic modules with 110W rating energy each and fouras well as to promote green awareness to the university residences. PV system was deep technology cycle battery units were utilized to provide threeThe daysstand-alone of autonomy designed toperiod powerfor two units of CFL lamps and an LED display unit installed at the bus stop. Five system operation. A part from that, 15 degree of tilt angle was units of polycrystalline photovoltaic modules with 110W optimum rating each and four deep cycle battery selected for PV module placement to provide energy generation units were utilized to provide three days of autonomy period for system operation. A part from that, as well as self cleaning for the modules. After the bus stop structure 15 degree of tilt angle was selected for PV module placement to provide optimum energy construction, the PV system was installed and commissioned. Final results generation as well as self cleaning for the modules. After the bus stop structure construction, the PV the commissioning process showed is able toprocess operate showed that system wasfrom installed and commissioned. Final resultsthat fromthe thesystem commissioning successfully as per design requirement. the system is able to operate successfully as per design requirement. KEYWORDS: Solar photovoltaic, Bus stop, Stand-alone system KEYWORDS: Solar photovoltaic, Bus stop, Stand-alone system 1.0 INTRODUCTION Photovoltaic or PV is currently one of the most attractive options for renewable energy resources in the world. Malaysia which is blessed with yearly average solar irradiance of 1400 to 1900 kWh/m2 is considered to be in a very advantageous position to harness the unlimited energy towards PV applications to cater current domestic energy demand (Malaysian PV Handbook, 2009). The technology offers free and renewable energy, no emission effects during energy production, help to reduce dependency to conventional power supply, as well as easy to install and maintain due to its modular characteristics (Chow, 2010). Up to date, solar photovoltaic (PV) system application is divided into two distinctive categories, which are grid-connected system and stand-alone or off-grid system. The grid connected PV system operates by linking the solar PV with the utility-grid connection, where as the stand alone PV system operates without connection to the utility grid and ISSN: 2180-1053 3 energy No. 2 July-December 2011solar PV as well 55 as utilize a battery system to store the Vol. excess generated by the supplying the needed energy when no power from the sun is available. Both system are power supply, as well as easy to install and maintain due to its modular characteristics (Chow, 2010). Journal of Mechanical Engineering and Technology Up to date, solar photovoltaic (PV) system application is divided into two distinctive categories, which are grid-connected system and stand-alone or off-grid system. The grid connected PV system operates by linking the solar PV with the utility-grid connection, where as the stand alone PV system operates without connection to the utility grid and utilize a battery system to store the excess energy generated by the solar PV as well as supplying the needed energy when no power from the sun is available. Both system are widely applied especially in Malaysia, however the stand-alone system offer notable advantage of able to operate in remote areas where utility-grid connection are not viable (Zekai, 2008). In this project, an innovative design of bus stops is proposed where the infrastructure is to be equips with lamps and electrical signboard powered by solar PV energy system. The new system is aimed to provide higher level human comfort as well as information to user, and the prototype is targeted to be applied in Main Kampus, Universiti Teknikal Malaysia Melaka. Currently, bus stops in UTeM is designed without any equipment to provide proper notice board and LED display to give better information for the public. This paper described the overall design and development process for the UTeM solar powered bus stop such as PV system sizing, structure design and development as well as PV system installation and commissioning. 2.0 METHODOLOGY The overall research methodology implement in this project is shown in Fgure 1 below. 56 ISSN: 2180-1053 Vol. 3 No. 2 July-December 2011 Development of a Stand-alone Solar Powered Bus Stop Start Project planning Literature Review on Current Design of Solar System System Development Modify Evaluation Not good Good System Installations Modify Evaluation Not good Good System Testing Performance Monitoring End FIGURE 1 Flow Chart FIGURE 1 Overall Research Overall Research Flow Chart Among the important stage in this project was the system development where the sizing of the PV standalone system is conducted. In order to attain an optimum design for the system, several sizing criteria such as location selection, design specification, determination of PV modules and battery capacity etc. were carefully calculated based on MS1837:2005 PV standard requirements (Malaysian Standard, 2005). The structure was later designed to accommodate the system sizing results using Solidworks CAD software. System testing and commissioning were performed in the final stage of the project to ensure that the PV system able to operate as per requirement. 3.0 SYSTEM SIZING ISSN: 2180-1053 Vol. 3 No. 2 July-December 2011 57 accommodate the system sizing results using Solidworks CAD software. System testing and commissioning were performed in the final stage of the project to ensure that the PV system ableJournal to operate as per requirement. of Mechanical Engineering and Technology 3.0 SYSTEM SIZING 3.1 Selection of Bus Stop Location 3.1 Selection of Bus Stop Location The first approach in designing the UTeM solar bus stop was to choose the suitable location The firststructure. approachThis in designing the UTeM solar stopthat wasthe to solar choose the suitable location for the is very crucial in order to bus ensure modules installed later for the structure. This is very crucial in order to ensure that the solar modules installed later on will have exposed to adequate sunray throughout the entire day for maximum power on will have exposed to adequate sunray throughout the entire day for maximum power generation. The surrounding of the bus stop location was also ensured to be clear from generation. Thesuch surrounding of the bus structure stop location was also ensured to be clear shading sources as tress and nearby especially to the solar modules. Thefrom bus shading sources such as tress and nearby the function. solar modules. The bus stop must also be easily accessible to thestructure users toespecially serve its to main The proposed stop must be easily the users to serve its main function. The proposed location of also the UTeM solaraccessible bus stop istoshown in Figure 2 below. location of the UTeM solar bus stop is shown in Figure 2 below. FIGURE 2 FIGURE 2 Location Bus FIGURE 2UTeM UTeMSolar Solar BusStop Stop Location UTeM Solar Bus Stop Location 3.2 Load Determination 3.2 Load Determination The details of the electrical appliances designed for the bus stop and its power rating is The details of the electrical appliances for the of busthestop andselected its power rating on is shown in Table 1 below. Based on Tabledesigned 1, the majority loads operated shown in Table on of Table theofmajority thecomponent loads selected operated on AC current. This1isbelow. mainlyBased because low 1, cost acquiringofthe compared to DC AC current. This is mainly of low cost of acquiring thedivided component compared to DC current components. A partbecause from that, the system load is also into two cases which current part loads. from that, system is also divided into casestowhich are withcomponents. and without Aspare The the spare loadsload are incorporated into thetwo design cater are and without loads. Thein spare loads are intohours the design cater for with unexpected higherspare power usage the future. Theincorporated total load per in the to case of for unexpected higher power usage in theand future. The total load loads per hours in the case of without spare load is 953 Watt-hours daily in the case of spare is 1269 Watt-hours without daily. spare load is 953 Watt-hours daily and in the case of spare loads is 1269 Watt-hours daily. TABLE TABLE 1 Load profile for UTeM1solar bus stop in a day TABLE 1 bus stop in a day Load profile for UTeM solar Load profile for UTeM solar bus stop in a day Load Power/Unit Operating Operating No Type Quantity Power/Unit Operating Operating Load Detail (W) Time hour/Day No Type Quantity Detail (W) Time hour/Day 1 CFL Lamp AC 2 18 7pm – 1am 6 12 CFL AC 2 18 7pm – 1am 6 LED Lamp 1 49 8am – 14 Display 10pm– 2 LED AC 1 49 8am 14 Internal DC & 3 1 8.5 6 System AC *13A 4 AC 1 100 1 socket 58 *Spare ISSN: 2180-1053 2011 5 AC 2 Vol. 3 No. 18 2 July-December 6 loads Total Total Power Power (Wh) (Wh) 216 216 686 686 51 100 216 3 4 5 3.3 Display Internal System *13A socket *Spare loads Development of a Stand-alone Solar Powered Bus Stop 10pm DC & AC 1 8.5 - 6 51 AC 1 100 - 1 100 AC 2 18 - 6 216 System Specification and Tilt Angle Several parameters have been determined for the design specification of the solar bus stop. First and foremost, the new UTeM solar bus stop is set to operate as a standalone system, where the power source is generated through PV modules only. The system is also set to be operated using 12V system voltage and must be able to operate up to 3 days of autonomy (in the case where zero sunlight occurred). The estimated achievable maximum solar radiation per day for the system is set to 3 peak sun hours and because the bus stop is a standalone photovoltaic system, the maximum depth of discharge for the battery used is the system is set to 80% capacity. The solar module is set to be placed on top of the bus stop roof to avoid any shading and to optimize the bus stop area. Hence, another important parameter that was determined was the tilt angle for the solar module installation. The location for the bus stop is roughly at the latitude 2°18'51.61"N and longitude 102°19'8.17"E, where, optimum tilt angle for the solar module is from 2° to 3° facing south. However, it is recommended that for sites at latitudes between 15°S and 15°N, a tilt angle of 15° is used. Hence, the tilt angle selected for the bus stop design is 15° to enable optimum energy generation as well as self cleaning for the modules. Based on solar irradiation data for Malaysia, the approximate average solar irradiance for the given latitude is 1400 W/m2 (Sulaiman et al., 2008). 3.4 Battery and Module Sizing Based on load data in Table 1 and design specifications, the sizing of the battery unit and the solar PV modules were performed. The determination for the number of batteries and PV modules were carefully conducted to ensure optimum sizing of the system can be achieved, which will benefits in lowering down the overall system cost as well as ensuring the system is able to operate efficiently. The sizing approach for standalone system is more delicate because the system operates solely on solar energy and energy from the batteries, compared with grid connected system. The battery must be able to supply the required power for minimum 3 days autonomy while the PV modules must be able to supply the power during sunlight as well as charging the battery to its maximum capacity continuously. Table 2 below shows the final result for the battery and PV module sizing. ISSN: 2180-1053 Vol. 3 No. 2 July-December 2011 59 Journal of Mechanical Engineering and Technology TABLE 2 TABLE 1 Sizing for Battery andModules PV Modules Sizing for Battery and PV Sizing Details A. Battery i. Amp-hour required excluding spare load (Ah) ii. Amp-hour required including spare load (Ah) iii. No of battery need B. PV Module i. Maximum power, Pm (W) ii. Maximum voltage, Vm (V) iii. Maximum current, Im (A) iv. Short-circuit voltage, Voc (V) v. Short-circuit current, Isc (A) vi Total module required excluding spare loads vii. Total module required including spare loads viii. Array configuration 3.5 Value 297.8 396.6 4 110 17.2 6.4 21.7 6.9 4 5 5x1 Balance-of-system (BOS) Sizing The final procedure for the sizing is to determine the specification for charge controller and inverter. The charge controller is used to regulate the power from the PV modules to the loads and vice versa efficiently. The inverter in the other hand is selected to convert the DC voltage produced from the PV modules to AC voltage needed for the load operations (CFL lamps, LED display etc.). The results of the balance of system sizing are shown in Table 3 below. TABLE 3 TABLE 3 Balance-of-system (BOS) for UTeM Solar Bus Stop Balance-of-system (BOS) for UTeM Solar Bus Stop BOS Sizing Details A. Charge Controller i. System voltage : minimum/maximum (V) ii. Total rated solar current (A) iii. Total maximum array current (A) iv. Total rated load current (A) v. Total maximum load current (A) B. Inverter i. AC system voltage (V) ii. AC system frequency (Hz) iii. Power factor (cos(pi)) iv. Rated VA based on excluding spare loads v. Rated VA based on including spare loads 60 ISSN: 2180-1053 Vol. 3 No. 2 Value 12/24 18.5 26.5 7.8 19.2 240 50 0.85 110 270 July-December 2011 Development of a Stand-alone Solar Powered Bus Stop A part from that, another important parameter for the BOS is the appropriate selection of cable size to minimize the power transmission lost in the cables. Due to the small amount of energy generated by the PV modules, thus the sizing process in this project was also focused to reduce any losses that may be created in the system which can deteriorate the system performance. The diameter of cable size selected is 4mm for running from the charge controller to the loads as well as from the batteries to the charge controller and 6mm cable diameter for cable designed from the PV modules to the charge controller. The selected cable sizes for the whole system were carefully calculated to permit maximum cabling losses of 4% based on requirement stated in the Malaysian Standard (Malaysian Standard, 2005). 3.6 Results of System Sizing Based on the system sizing, the appropriate components for the UTeM solar bus stop system were selected. The design specific yield of the system is 1037.1 kWh/kWp. The installation quality of the designed bus stop measured in term of performance ratio was found to be approximately 74% which satisfy the MS1837:2005 PV standard requirements (Malaysian Standard, 2005). A timer was also incorporated in the system to control precisely the operation hours of the loads in the system. Table 4 and Figure 3 below show the description of the selected equipments for the standalone PV system and the system overall schematic diagram. TABLE 4 TABLE 4 Equipments for UTeM solar bus stop Equipments for UTeM solar bus stop No Item 1 Solar Module 2 Battery 3 4 Charge Controller Inverter Quantity Desciptions 5 110 W, 12V, Polycrystalline. Brand: SolarTif 4 100 Ah, 12V, JXH100-12 Valve Regulated Lead Acid. Brand: MPower 1 Model PL40, 12-48V, 30A. Brand: Phocos 1 Standalone Sinewave Inverter, Model Picollo.Brand: ASP ISSN: 2180-1053 Vol. 3 No. 2 July-December 2011 61 Journal of Mechanical Engineering and Technology FIGURE 3 FIGURE 3 Schematic Diagram of the3 UTeM Solar Bus Stop FIGURE Schematic Diagram of the UTeM Solar Bus Stop Schematic Diagram of the UTeM Solar Bus Stop 4.0 4.0 BUS BUS STOP STOP DESIGN DESIGN AND AND CONSTRUCTION CONSTRUCTION The The design design intent intent is is for for the the bus bus stop stop to to provide provide lighting lighting and and visual visual display display to to the the users users of of the the bus stop. A part from that, the bus stop structure must also be able to accommodate the bus stop. A part from that, the bus stop structure must also be able to accommodate the solar solar modules modules as as well well as as the the rest rest of of the the balance balance of of system system components. components. Acknowledging Acknowledging the the above above requirements, a design for the UTeM bus stop was proposed and shown in Figure 4 requirements, a design for the UTeM bus stop was proposed and shown in Figure 4 below. below. FIGURE 4 FIGURE 4 UTeM UTeM Solar Solar Bus Bus Stop Stop Design Design The UTeM bus stop structure encompassed several features. The roof of the structure is ISSN: 2180-1053 Vol. 3 No. 2 July-December 2011 tilted at 15 degree from horizontal plane to enable tilt angle of 15 degree for the module installation. The bus stop foundation is needed to be flat to ensure the tilt angle for the 62 Development FIGURE 4 of a Stand-alone Solar Powered Bus Stop UTeM Solar Bus Stop Design The UTeM bus stop structure encompassed several features. The roof of the structure is tilted at 15 degree from horizontal plane to enable tilt angle of 15 degree for the module installation. The bus stop foundation is needed to be flat to ensure the tilt angle for the modules can be achieved. The roof structure also houses the CFL lamps and LED display unit. Due to the location of the LED display unit where it is placed on the front of the bus stop roof facing the main road, the display is required to be fabricated based on IP65 casing requirement for ensuring reliable outdoor performance. The overall structure of the bus stop will be made from concrete as well as for the base of the bus stop. The balance-of-system components are located separately in a special housing behind the bus stop structure for ease of maintenance and security control. Figure 5 below show the UTeM bus stop in the end of the construction process. FIGURE 5 BusBus Stop after Construction FIGUREUTeM 5 UTeM Stop after Construction FIGURE 5 UTeM Bus Stop after Construction 5.0 SYSTEM INSTALLATION AND COMMISSIONING After the bus stop structure was constructed, the stand-alone PV system was later installed at theINSTALLATION location. Simple L-shapeAND brackets were first placed on top of the structure roof acting SYSTEM COMMISSIONING as the mounting points for the PV modules. Five units of PV modules were installed in 5x1 array configuration as per sizing requirement at 15 degree tilt angle. Later, the CFL lights the bus stop structure waswere constructed, thebus stand-alone PV system was later installe and LED display unit installed on the stop. The batteries and balance-of-system components were installed separately on a special housing behind the bus stop. Wires e location. Simple L-shape brackets were first placed on top of the structure roof actin connecting the modules, loads and the rest of the PV system are secured inside conduits to e mounting points for the PV modules. Five units of PV modules were installed in 5x ensure safety to the users as well as to protect from surrounding effect such as rain water configuration per itsizing requirement at 15 tilt angle. that mayascause to deteriorate prematurely. Thedegree wires connecting theLater, modulesthe andCFL the light balance-of-system is also in ground purposes. Thebalance-of-system installed PV LED display unit were housing installed on burried the bus stop. for Thesafety batteries and ISSN: 2180-1053 Vol. 3 ofNo. 2 July-December 2011 63 7 system on the bus stop and the PV balance system are shown in Figure 6 and Figure ponents were installed separately on a special housing behind the bus stop. Wire below. array configuration as per sizing requirement at 15 degree tilt angle. Later, the CFL lights and LED display unit were installed on the bus stop. The batteries and balance-of-system components were installed separately on a special housing behind the bus stop. Wires Journal of Mechanical Engineering and Technology connecting the modules, loads and the rest of the PV system are secured inside conduits to ensure safety to the users as well as to protect from surrounding effect such as rain water that may cause it to deteriorate prematurely. The wires connecting the modules and the balance-of-system housing is also burried in ground for safety purposes. The installed PV system on the bus stop and the PV balance of system are shown in Figure 6 and Figure 7 below. FIGURE 6 UTeM Stop with Stand-alone PV System FIGURE 6 UTeM Bus Stop with Stand-alone PV System 64 ISSN: 2180-1053 Vol. 3 No. 2 July-December 2011 Development of a Stand-alone Solar Powered Bus Stop FIGURE 7 Housing for Batteries and Balance-of-system Components FIGURE 7 Housing for Batteries and Balance-of-system Components 6.0 CONCLUSION In conclusion, the standalone solar PV system for UTeM green bus stop was successfully developed in this project. The solar PV system comprised of five polycrystalline modules in 5x1 array configuration and four deep cycle batteries which give power to two units of CFL lamps and a LED display unit. The bus stop structure was design and constructed to accommodate the module tilt angle of 15 degree. Results from the testing and commissioning process performed show that the solar PV system was able to perform as per design requirement. The solar powered bus stop developed in this project was proven not only to perform as conventional bus stop, but also able to provide human comfort and information to the users as well as promoting green technology within the university and its residence. 7.0 ACKNOWLEDGEMENT The authors would like to thank Universiti Teknikal Malaysia Melaka for providing the support and fund for accomplishment of this project. The project was funded under UTeM top-down research grant PJP/2010/FKM(15A)-S715. ISSN: 2180-1053 Vol. 3 No. 2 July-December 2011 65 Journal of Mechanical Engineering and Technology 8.0 REFERENCES PV Industry Handbook. 2009. Pusat Tenaga Malaysia. Malaysia. T.T. Chow. 2010. A Review on Photovoltaic/thermal Hybrid Solar Technology, Journal of Applied Energy, Vol. 87, pp. 365-379. S. Zekai. 2008. Solar Energy Fundamental and Modeling Technique: Atmosphere, Environment, Climate Change and Renewable Energy. 1st Ed. Ginora, Spain: Springer Installation of Grid Connected Photovoltaic (PV) System, Malaysian Standard MS1837:2005, SIRIM, Malaysia. Sulaiman S., Kamaruzzaman S., and Ahmad M.O. 2008. Solar Irradiation Handbook for Photovoltaic Systems Design in Malaysia. Solar Energy Research Institute, Universiti Kebangsaan Malaysia, Malaysia. ISBN: 9789675048326. 66 ISSN: 2180-1053 Vol. 3 No. 2 July-December 2011