Technical Specifications Repair/Replace Taxiway G/G1 JBSA – Randolph AFB, Texas TYMX989345A FA3002-09-D-0002 TG02 65% - 01/23/2015 Environmental Quality Management, Inc. 12721 Wolf Road Geneseo, IL 61254 URS Group, Inc. 1950 North Stemmons Freeway, Suite 6000 Dallas, TX 75207 This Page Left Intentionally Blank Technical Specifications Repair/Replace Taxiway G/G1 JBSA – Randolph AFB, Texas TYMX989345A FA3002-09-D-0002 TG02 65% - 01/23/2015 The professional responsibility of the undersigned Professional Engineer is limited to the content contained in this bound volume. The undersigned Professional Engineer disclaims responsibility for all other documents, including but not limited to geotechnical reports, which do not directly bear this professional seal and signature. PRELIMINARY This document is released for the purpose of interim review under the authority of Maribel P. Chavez, P.E. #63385 on 01/23/2015. It is not to be used for construction purposes. URS Group, Inc. Texas Registered Engineering Firm F-15570 Maribel P. Chavez, P.E. 01/23/2015 Texas Professional Engineer #63385 Expires 09/30/2015 URS Group, Inc. 1950 N. Stemmons Freeway, Suite 6000 Dallas, TX 75207 (214) 741-7777 Texas PE Firm 15570 Expires 11/30/2015 This Page Left Intentionally Blank REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 PROJECT TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS 01 33 00 01 42 00 SUBMITTAL PROCEDURES SOURCES FOR REFERENCE PUBLICATIONS DIVISION 02 - EXISTING CONDITIONS 02 41 00 DEMOLITION DIVISION 03 - CONCRETE 03 30 53 03 40 00.00 10 MISCELLANEOUS CAST-IN-PLACE CONCRETE PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE CONSTRUCTION DIVISION 31 - EARTHWORK 31 00 00 EARTHWORK DIVISION 32 - EXTERIOR IMPROVEMENTS 32 01 13 32 01 19 32 32 32 32 32 11 11 12 12 13 23 33 10 17 11 32 17 24.00 10 32 92 19 BITUMINOUS SEAL AND FOG COATS FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE CEMENT STABILIZED BASE COURSE AT AIRFIELDS AND ROADS BITUMINOUS TACK AND PRIME COATS HOT MIX BITUMINOUS PAVEMENT CONCRETE PAVEMENT FOR AIRFIELDS AND OTHER HEAVY-DUTY PAVEMENTS PAVEMENT MARKINGS SEEDING DIVISION 33 - UTILITIES 33 40 00 STORM DRAINAGE UTILITIES -- End of Project Table of Contents -- PROJECT TABLE OF CONTENTS Page 1 This Page Left Intentionally Blank REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-01 33 00 (May 2011) Change 4 - 11/14 ----------------------------Preparing Activity: NASA Superseding UFGS-01 33 00 (February 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION 01 33 00 SUBMITTAL PROCEDURES ************************************************************************** NOTE: This guide specification covers the requirements for general procedures regarding submittals, data normally submitted for review to establish conformance with the design concept and contract documents, called for in other sections of the specifications. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). This guide specification includes tailoring options for Army, Navy, NASA and for NAVFAC component requirements. Selection or deselection of a tailoring option will include or exclude that option in the section, but editing the resulting section to fit the project is still required. ************************************************************************** PART 1 1.1 1.1.1 GENERAL DEFINITIONS Submittal Descriptions (SD) Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows: ************************************************************************** URS FOR EQM SECTION 01 33 00 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NOTE: The SD numbers and names, assigned by the SPECSINTACT Configuration, Control and Coordinating Board, relate to the terminology of the technical sections and should not be changed. Refer to UFC 1-300-02 UNIFIED FACILITIES GUIDE SPECIFICATIONS (UFGS) FORMAT STANDARD for additional information. ************************************************************************** SD-01 Preconstruction Submittals Submittals which are required prior to start of construction (work) Certificates of insurance Surety bonds List of proposed Subcontractors List of proposed products Construction progress schedule Network Analysis Schedule (NAS) Submittal register Schedule of prices or Earned Value Report Health and safety plan Work plan Quality Control (QC) plan Environmental protection plan SD-02 Shop Drawings Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work. Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated. SD-03 Product Data Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work. Samples of warranty language when the contract requires extended product warranties. SD-04 Samples URS FOR EQM SECTION 01 33 00 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged. Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project. Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work. SD-05 Design Data Design calculations, mix designs, analyses or other data pertaining to a part of work. Design submittals, design substantiation submittals and extensions of design submittals. SD-06 Test Reports Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project. Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site. Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation. Investigation reports. Daily logs and checklists. Final acceptance test and operational test procedure. SD-07 Certificates Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project. Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications. URS FOR EQM SECTION 01 33 00 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Confined space entry permits. Text of posted operating instructions. SD-08 Manufacturer's Instructions Preprinted material describing installation of a product, system or material, including special notices and (MSDS) concerning impedances, hazards and safety precautions. SD-11 Closeout Submittals Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism. Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC). Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract. Interim "DD Form 1354" with cost breakout for all assets 30 days prior to facility turnover. 1.1.2 Approving Authority Office or designated person authorized to approve submittal. 1.1.3 Work As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. 1.2 SUBMITTALS ************************************************************************** NOTE: Submittals must be limited to those necessary for adequate quality control. The importance of an item in the project should be one of the primary factors in determining if a submittal for the item should be required. A “G” following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked with a “G”. Only delete an existing “G” if the submittal item is not complex and can be reviewed through the Contractor’s QC system. Only add a “G” if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. URS FOR EQM SECTION 01 33 00 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are [for Contractor QC approval. ][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Submit the following in accordance with this section. SD-01 Preconstruction Submittals Submittal Register[; G][; G, [_____]] 1.3 SUBMITTAL CLASSIFICATION Submittals are classified as follows: 1.3.1 Designer of Record Approved (DA) ************************************************************************** NOTE: Section 01 33 16 DESIGN AFTER AWARD is not a UFGS section. The purpose of the section is to specify design process and submittal requirements in a Design-Build contract. Section 01 33 16 has been developed for the MILCON Business Process (MBP) Model RFP and is available from the RFP Wizard Portal at http://mrsi.usace.army.mil/rfp/SitePages/Home.aspx. ************************************************************************** ************************************************************************** NOTE: This paragraph contains tailoring tags for Army and Design-Build. Use for Army projects only. ************************************************************************** Designer of Record (DOR) approval is required for extensions of design, critical materials, any deviations from the solicitation, the accepted proposal, or the completed design, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled, URS FOR EQM SECTION 01 33 00 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 "Specifications and Drawings for Construction," they are considered to be "shop drawings." Contractor to provide the Government with the number of copies designated hereinafter of all DOR approved submittals. The Government may review any or all Designer of Record approved submittals for conformance to the Solicitation, Accepted Proposal and the completed design. The Government will review all submittals designated as deviating from the Solicitation or Accepted Proposal, as described below. Design submittals to be in accordance with Section 01 33 16 DESIGN AFTER AWARD. Generally, design submittals should be identified as SD-05 Design Data submittals. 1.3.2 Government Approved (G) ************************************************************************** NOTE: This paragraph contains tailoring tags for Design-Bid-Build and Design-Build. ************************************************************************** Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings." Sustainability Submittals (S) Submittals for Guiding Principle Validation (GPV) or Third Party Certification (TPC) are indicated with an "S" designation. Submit the information required by the technical sections that demonstrates compliance with the sustainable requirement, and for inclusion in the Sustainability Notebook as required by Section 01 33 29 SUSTAINABILITY REQUIREMENTS. If the submittal is also provided under another another SD, provide a separate submittal under SD-11 that only provides that portion of the submittal that demonstrates compliance with the sustainable requirement. Schedule submittals for these items throughout the course of construction as provided; do not wait until closeout. 1.4 1.4.1 1.5 PREPARATION Transmittal Form QUANTITY OF SUBMITTALS ************************************************************************** NOTE: The quantities suggested below are consistent with the quantities to be retained by the Government, in paragraph entitled, "QC Organization Responsibilities," of this section; maintain the coordination. ************************************************************************** 1.5.1 Number of Copies of SD-02 Shop Drawings Submit [six][_____] copies of submittals of shop drawings requiring review and approval only by QC organization and [seven][_____] copies of shop drawings requiring review and approval by Contracting Officer. 1.5.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions Submit in compliance with quantity requirements specified for shop drawings. URS FOR EQM SECTION 01 33 00 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.5.3 TYMX989345A FA3002-09-D-0002 TG02 Number of Samples SD-04 Samples ************************************************************************** NOTE: For NAVFAC, require one sample in paragraph "a" and delete the second sentence of paragraph "a". ************************************************************************** a. Submit [two] [_____] samples, or [two] [_____] sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor. b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed. c. Submit one sample installation, where directed. d. Submit one sample of non-solid materials. 1.5.4 Number of Copies SD-05 Design Data and SD-07 Certificates Submit in compliance with quantity requirements specified for shop drawings. 1.5.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports. 1.5.6 Number of Copies of SD-10 Operation and Maintenance Data ************************************************************************** NOTE: NAVFAC requires three copies of O&M Data unless OMSI manual is specified. Coordinate with OMSI requirements. ************************************************************************** Submit [five][three][_____] copies of O&M Data to the Contracting Officer for review and approval. 1.5.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals Unless otherwise specified, submit [two][three] sets of administrative submittals. 1.6 VARIATIONS Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government. 1.6.1 Considering Variations Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met URS FOR EQM SECTION 01 33 00 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP). Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government. 1.6.2 Proposing Variations When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation. 1.6.3 Warranting that Variations are Compatible When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work. 1.6.4 Review Schedule is Modified ************************************************************************** NOTE: Allow a longer additional review period if the construction phase will have geographically scattered reviewers. ************************************************************************** In addition to normal submittal review period, a period of [10] [_____] working days will be allowed for consideration by the Government of submittals with variations. 1.7 SUBMITTAL REGISTER ************************************************************************** NOTE: Create the submittal register from the project specification files, at the conclusion of the design. In SPECSINTACT, choose "Export Submittal Register" from "Process" pull-down menu. Local procedures should be responsive to the requirement that the submittal register, required with the QC plan, is usually due from the Contractor within 20 days after the Notice of Award. ************************************************************************** ************************************************************************** NOTE: Use bracketed items for Army projects only. ************************************************************************** Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. A submittal register showing items of equipment and URS FOR EQM SECTION 01 33 00 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. [ The Government will provide the initial submittal register ][in electronic format][ with the following fields completed, to the extent that will be required by the Government during subsequent usage.] Column (c): required. Lists specification section in which submittal is Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section. Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements. [ Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government. ] 1.7.1 Use of Submittal Register Submit submittal register. Submit with QC plan and project schedule. Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule: [ Column (a) Activity Number: schedule. ][ Column (g) Contractor Submit Date: authority to receive submittals. ][ Column (h) Contractor Approval Date: approval of submittal. ][ Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control. ]1.7.2 Activity number from the project Scheduled date for approving Date Contractor needs Contractor Use of Submittal Register Update the following fields[ in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor] with each submittal throughout contract. Column (b) Transmittal Number: consecutive numbers. Contractor assigned list of Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC. Column (l) List date of submittal transmission. Column (q) List date approval received. URS FOR EQM SECTION 01 33 00 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.7.3 TYMX989345A FA3002-09-D-0002 TG02 Approving Authority Use of Submittal Register Update the following fields[ in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor]. Column (b) Transmittal Number: consecutive numbers. Contractor assigned list of Column (l) List date of submittal receipt. Column (m) through (p) List Date related to review actions. Column (q) List date returned to Contractor. 1.7.4 Copies Delivered to the Government Deliver one copy of submittal register updated by Contractor to Government with each invoice request. 1.8 SCHEDULING Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals. An additional [_____] calendar days will be allowed and shown on the register for review and approval of submittals for [food service equipment] [and] [refrigeration and HVAC control systems] a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements. b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A." c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required. d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register." 1.8.1 Government Reviewed Design ************************************************************************** NOTE: Use this subpart for Army Design-Build projects only. Section 01 33 16 DESIGN AFTER AWARD is not a UFGS. It is part of the MBP Model RFP and is available from the RFP Wizard Portal at http://mrsi.usace.army.mil/rfp/SitePages/Home.aspx. URS FOR EQM SECTION 01 33 00 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** The Government will review design submittals for conformance with the technical requirements of the solicitation. Section 01 33 16 DESIGN AFTER AWARD covers the design submittal and review process in detail. Government review is required for deviation from the completed design. Review will be only for conformance with the contract requirements. Included are only those construction submittals for which the Designer of Record design documents do not include enough detail to ascertain contract compliance. The Government may, but is not required, to review extensions of design such as structural steel or reinforcement shop drawings. 1.9 GOVERNMENT APPROVING AUTHORITY When approving authority is Contracting Officer, the Government will: a. Note date on which submittal was received. b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents. c. Identify returned submittals with one of the actions defined in paragraph entitled, "Review Notations," of this section and with markings appropriate for action indicated. Upon completion of review of submittals requiring Government approval, stamp and date submittals. Two[_____] copies of the submittal will be retained by the Contracting Officer and the remaining[_____] copies of the submittal will be returned to the Contractor. If the Government performs a conformance review of other Designer of Record approved submittals, the submittals will be so identified and returned, as described above. 1.9.1 Review Notations Submittals will be returned to the Contractor with the following notations: a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered. b. Submittals marked "approved as noted" "or approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections. c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved. d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change. URS FOR EQM SECTION 01 33 00 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.10 TYMX989345A FA3002-09-D-0002 TG02 DISAPPROVED[ OR REJECTED] SUBMITTALS Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense. If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved. 1.11 APPROVED[/ACCEPTED] SUBMITTALS ************************************************************************** NOTE: For Navy or NASA projects choose Design-Bid-Build text. On Army projects choose either design-bid-build or design-build text. ************************************************************************** The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work. After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary. 1.12 APPROVED SAMPLES Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved. Match the approved samples for materials and equipment work. If requested, approved samples, including those in testing, will be returned to the Contractor, at his completion of the contract. Samples not approved will the Contractor at its expense, if so requested. incorporated in the which may be damaged expense, upon also be returned to Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service. Samples of various materials or equipment delivered on the site or in place URS FOR EQM SECTION 01 33 00 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals. Contractor to replace such materials or equipment to meet contract requirements. Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract. PART 2 PRODUCTS Not Used PART 3 EXECUTION Not Used -- End of Section -- URS FOR EQM SECTION 01 33 00 Page 13 65% - 01/23/2015 This Page Left Intentionally Blank REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-01 42 00 (November 2014) ----------------------------Preparing Activity: USACE Superseding UFGS-01 42 00 (August 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION 01 42 00 SOURCES FOR REFERENCE PUBLICATIONS ************************************************************************** NOTE: This guide specification provides a listing of organizations whose publications are referenced in other sections of the specifications. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). In accordance with FAR 11.201, identification of sources for obtaining documents referenced in the specificatioins must be provided in contract documents. ************************************************************************** PART 1 1.1 GENERAL REFERENCES Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g. ASTM B564 Standard Specification for Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes. 1.2 ORDERING INFORMATION ************************************************************************** URS FOR EQM SECTION 01 42 00 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NOTE: Information regarding standards producing organizations was in agreement with information contained in the Unified Master Reference List (UMRL) as of date of this guide specification. This paragraph is automatically edited by removal of those organizations not included in other sections of the project specifications when SpecsIntact (Reconcile Addresses item from the Print menu) is use for job processing. However, if publications of organizations in addition to those listed below are used in the project, such additional organizations must be added to this paragraph. ************************************************************************** The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided. Documents listed in the specifications with numbers which were not assigned by the standards producing organization should be ordered from the source by title rather than by number. AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) 444 North Capital Street, NW, Suite 249 Washington, DC 20001 Ph: 202-624-5800 Fax: 202-624-5806 E-Mail: info@aashto.org Internet: http://www.aashto.org AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI) 38800 Country Club Drive Farmington Hills, MI 48331-3439 Ph: 248-848-3700 Fax: 248-848-3701 E-mail: bkstore@concrete.org Internet: http://www.concrete.org AMERICAN CONCRETE PIPE ASSOCIATION (ACPA) 8445 Freeport Parkway, Suite 350 Irving, TX 75063-2595 Ph: 972-506-7216 Fax: 972-506-7682 E-mail: info@concrete-pipe.org Internet: http://www.concrete-pipe.org AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE) 1800 East Oakton Street Des Plaines, IL 60018 Ph: 847-699-2929 Internet: http://www.asse.org AMERICAN WELDING SOCIETY (AWS) 13301 NW 47 Ave Miami, FL 33054 Ph: 888-WELDING, 305-824-1177, 305-826-6192 Fax: 305-826-6195 URS FOR EQM SECTION 01 42 00 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 E-mail: customer.service@awspubs.com Internet: http://www.aws.org ASPHALT INSTITUTE (AI) 2696 Research Park Drive Lexington, KY 40511-8480 Ph: 859-288-4960 Fax: 859-288-4999 E-mail: info@asphaltinstitute.org Internet: http://www.asphaltinstitute.org ASTM INTERNATIONAL (ASTM) 100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 877-909-2786 Internet: http://www.astm.org CSA GROUP (CSA) 178 Rexdale Blvd. Toronto, ON, Canada M9W 1R3 Ph: 416-747-4044 Fax: 416-747-2510 E-mail: sales@csagroup.org Internet: http://www.csagroup.org/us/en/home NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH) 395 E Street, S.W. Suite 9200 Patriots Plaza Building Washington, DC 20201 Ph: 800-232-4636 Fax: 513-533-8347 E-mail: nioshdocket@cdc.gov Internet: http://www.cdc.gov/niosh/ NATIONAL PRECAST CONCRETE ASSOCIATION (NPCA) 1320 City Center Drive, Suite 200 Carmel, IN 46032 Ph: 317-571-9500 or 800 366 7731 Fax: 317-571-0041 Internet: www.precast.org NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA) Manager, Customer Service 900 Spring Street Silver Spring, MD 20910 Ph: 240-485-1165 E-mail: jjenkins@nrmca.org (Jacques Jenkins) Internet: http://www.nrmca.org STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION (CALTRANS) Publication Distribution Unit 1801 30th Street Sacramento, CA 95816-8041 Ph: 916-227-8396 E-mail: michael_campos@dot.ca.gov Internet: http://www.dot.ca.gov/hq/esc/techpubs/ URS FOR EQM SECTION 01 42 00 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 U.S. ARMY CORPS OF ENGINEERS (USACE) CRD-C DOCUMENTS available on Internet: http://www.wbdg.org/ccb/browse_cat.php?c=68 Order Other Documents from: USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102 Ph: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet: http://www.publications.usace.army.mil/ or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx U.S. DEPARTMENT OF AGRICULTURE (USDA) Order AMS Publications from: AGRICULTURAL MARKETING SERVICE (AMS) Seed Regulatory and Testing Branch 801 Summit Crossing Place, Suite C Gastonia, NC 28054-2193 Ph: 704-810-8871 Fax: 704-852-4189 E-mail: seed.ams@usda.gov Internet: http://www.ams.usda.gov/lsg/seed.htm Order Other Publications from: U.S. Department of Agriculture, Rural Utilities Program USDA Rural Development, Room 4051-S Mail Stop 1510 1400 Independence Avenue SW Washington, DC 20250-1510 Phone: (202) 720-9540 TTY: (800) 877-8339 (Federal Relay Service) Fax: (202) 720-1725 Internet: http://www.rurdev.usda.gov/utilities_lp.html U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA) Ariel Rios Building 1200 Pennsylvania Avenue, N.W. Washington, DC 20004 Ph: 202-272-0167 Internet: http://www2.epa.gov/libraries --- Some EPA documents are available only from: National Technical Information Service (NTIS) 5301 Shawnee Road Alexandria, VA 22312 Ph: 703-605-6050 or 1-688-584-8332 Fax: 703-605-6900 E-mail: info@ntis.gov Internet: http://www.ntis.gov U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA) FHWA, Office of Safety 1200 New Jersey Ave., SE Washington, DC 20590 Ph: 202-366-4000 Internet: http://www.fhwa.dot.gov Order from: Superintendent of Documents URS FOR EQM SECTION 01 42 00 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 U. S. Government Printing Office (GPO) 710 North Capitol Street, NW Washington, DC 20401 Ph: 202-512-1800 Fax: 202-512-2104 E-mail: contactcenter@gpo.gov Internet: http://www.gpoaccess.gov U.S. GENERAL SERVICES ADMINISTRATION (GSA) General Services Administration 1275 First St. NE Washington, DC 20417 Ph: 202-501-1231 Internet: http://www.gsaelibrary.gsa.gov/ElibMain/home.do Obtain documents from: Acquisition Streamlining and Standardization Information System (ASSIST) Internet: https://assist.dla.mil/online/start/; account registration required U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA) 8601 Adelphi Road College Park, MD 20740-6001 Ph: 866-272-6272 Fax: 301-837-0483 Internet: http://www.archives.gov Order documents from: Superintendent of Documents U.S.Government Printing Office (GPO) 710 North Capitol Street, NW Washington, DC 20401 Ph: 202-512-1800 Fax: 202-512-2104 E-mail: contactcenter@gpo.gov Internet: http://www.gpoaccess.gov PART 2 PRODUCTS Not used PART 3 EXECUTION Not used -- End of Section -- URS FOR EQM SECTION 01 42 00 Page 5 65% - 01/23/2015 This Page Left Intentionally Blank REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-02 41 00 (May 2010) Change 1 - 08/14 -----------------------Preparing Activity: USACE Superseding UFGS-02 41 00 (October 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 02 41 00 [DEMOLITION][ AND ][DECONSTRUCTION] ************************************************************************** NOTE: This guide specification covers the requirements for demolition, deconstructon, dismantling, reconditioning and disposal of existing building materials, equipment and utilities as a part of new construction or renovation work. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). TO DOWNLOAD UFGS GRAPHICS Go to http://wbdg.org/ccb/NAVGRAPH/graphtoc.pdf. ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: Where premises are occupied, certain spaces may exist where activities cannot be interrupted or disturbed during normal working hours. To prevent disputes or possible contract claims resulting from restriction of demolition or removal work in such spaces, provisions for scheduling of the work must be specified in the contract documents. Restrictions for scheduling of demolition or removal work in areas adjacent to or in occupied spaces should reflect the requirements resulting from the URS FOR EQM SECTION 02 41 00 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 consultation with occupants of the affected spaces. These provisions are necessary to alert prospective bidders about the spaces where business is not to be interrupted or disturbed during construction. Delete requirements if inapplicable. Where suspect deck conditions are encountered during design investigation, identify and include appropriate repair and safety provisions in the design documents to draw attention to the suspect areas and the need for additional safety precautions. Include "Notification of Demolition and Renovation" form for Hawaii only. ************************************************************************** 1.1 REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE) ASSE/SAFE A10.6 (2006) Safety Requirements for Demolition Operations U.S. ARMY CORPS OF ENGINEERS (USACE) EM 385-1-1 (2008; Errata 2011) Safety and Health Requirements Manual U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA) 40 CFR 61 URS FOR EQM National Emission Standards for Hazardous Air Pollutants SECTION 02 41 00 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.2 TYMX989345A FA3002-09-D-0002 TG02 PROJECT DESCRIPTION ************************************************************************** NOTE: Make a determination as to whether any material of a hazardous nature, as classified in the National Emissions Standards, OSHA, or EPA regulations, will result from the work described. If such material is determined likely, specify precautions and standards to be complied with. Since the Contractor performs the work, the Contractor will be the one responsible for complying with all necessary regulations. Protect personnel from possible airborne contaminants, such as asbestos fibers, dried fecal matter (bird droppings) and metal dusts. For Navy projects: Contact an industrial hygienist at (1) A Navy Regional Medical Center, (2) A Navy Environmental and Preventive Medicine Unit, or (3) the Navy Environmental Health Center for assistance. Disposal of materials must not endanger or pollute the environment. Obtain assistance from the environmental branch of the Engineering Field Division of the Naval Facilities Engineering Command or from the Naval Facilities Engineering Service Center, Norfolk, Virginia. Non-friable materials containing asbestos, such as cement-asbestos siding and roofing and vinyl-asbestos flooring materials, normally do not require special handling and disposal procedures unless such materials are sawn, ground, sanded, drilled, pulverized, or handled in such a manner that will cause dust and airborne asbestos fiber to be released. Thus the removal of non-friable asbestos will not normally require the use of Section 02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS or Section 02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES. If the project contains non-friable asbestos that is considered to be hazardous due to material condition (broken down or excessively old and decayed) or demolition or deconstruction procedures to be used, then specify the non-friable asbestos to be removed in accordance with Section 02 82 16.00 20 or 02 82 14.00 10. For "NAVFAC SE" projects use "project site" in Guantanamo Bay, Cuba; for all other projects use "station daily." Deconstruction is the process of taking apart a facility with the primary goal of preserving the value of all useful building materials, so that they may be reused or recycled. It should be considered when adaptive reuse of a building is not an option, and may be used in conjunction with demolition. Deconstruction minimizes demolition landfill URS FOR EQM SECTION 02 41 00 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 materials and reduces material costs for the converted facility. Diverting demolition waste from the landfill contributes to the following LEED credit: MR2. Coordinate with Section 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT. ************************************************************************** 1.2.1 Demolition/Deconstruction Plan ************************************************************************** NOTE: Either a Demolition Plan or a Deconstruction Plan is required. A project requiring both demolition and deconstruction work will name the plan according to the majority of the work being performed, and the plan will include requirements for both types of work. ************************************************************************** Prepare a [Demolition Plan] [Deconstruction Plan] and submit proposed [ salvage,] [demolition,] [deconstruction,] and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress[, a disconnection schedule of [utility services,] [and] [airfield lighting,] a detailed description of methods and equipment to be used for each operation and of the sequence of operations]. Coordinate with Waste Management Plan.[ Include statements affirming Contractor inspection of the existing roof deck and its suitability to perform as a safe working platform or if inspection reveals a safety hazard to workers, state provisions for securing the safety of the workers throughout the performance of the work.] Provide procedures for safe conduct of the work in accordance with EM 385-1-1. Plan shall be approved by [Structural PE] [Contracting Officer] prior to work beginning. 1.2.2 General Requirements Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. [Remove rubbish and debris from the [station daily] [project site]; do not allow accumulations [inside or outside the building[s]] [on airfield pavements].] [The work includes [demolition,] [deconstruction], salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer.] In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable Sections. 1.3 ITEMS TO REMAIN IN PLACE Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer. Coordinate the work of this section with all other work indicated. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload [structural elements] [pavements to remain]. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural URS FOR EQM SECTION 02 41 00 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 replacement require approval by the Contracting Officer prior to performing such work. 1.3.1 Existing Construction Limits and Protection Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove [snow, ]dust, dirt, and debris from work areas daily. Weather Protection For portions of the building to remain, protect building interior and materials and equipment from the weather at all times. Where removal of existing roofing is necessary to accomplish work, have materials and workmen ready to provide adequate and temporary covering of exposed areas. Trees Protect trees within the project site which might be damaged during demolition or deconstruction, and which are indicated to be left in place, by a 6 foot high fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting Officer. 1.3.2 Utility Service ************************************************************************** NOTE: Delete the first bracketed sentence when the Government will disconnect and seal utilities. Delete the second bracketed sentence when the Contractort will disconnect and seal utilities. ************************************************************************** Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, [utilities serving each area of alteration or removal will be shut off by the Government and disconnected and sealed by the Contractor ] [the Government will disconnect and seal utilities serving each area of alteration or removal upon written request from the Contractor]. 1.3.3 Facilities Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer. Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this URS FOR EQM SECTION 02 41 00 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 contract. 1.4 BURNING The use of burning at the project site for the disposal of refuse and debris [will not be permitted] [will be permitted in the area located [_____] and between the hours of [_____] and [_____]]. Where burning is permitted, adhere to federal, state, and local regulations. 1.5 AVAILABILITY OF WORK AREAS Areas in which the work is to be accomplished will be available in accordance with the following schedule:Work shall be completed in phases as depicted on the drawings. Schedule Area Date [_____] [_____] 1.6 SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force URS FOR EQM SECTION 02 41 00 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.][information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-01 Preconstruction Submittals Existing Conditions[; G][; G, [_____]] SD-07 Certificates [ [ Demolition Plan[; G][; G, [_____]]] Deconstruction Plan[; G][; G, [_____]]] Notification[; G][; G, [_____]] SD-11 Closeout Submittals Receipts 1.7 QUALITY ASSURANCE Submit timely notification of [demolition] [deconstruction] [and] [renovation] projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61, Subpart M. Notify the [Regional Office of the United States Environmental Protection Agency (USEPA)] [State's environmental protection agency] [local air pollution control district/agency] and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61, Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSE/SAFE A10.6. Comply with the Environmental Protection Agency requirements specified. Use of explosives [will] [will not] be permitted. 1.7.1 Dust[ and Debris] Control Prevent the spread of dust [and debris] [to occupied portions of the building] [on airfield pavements] and avoid the creation of a nuisance [or hazard] in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. [Vacuum and dust the work area [daily] [_____].] [ Sweep pavements as often as necessary to control the spread of debris that may result in foreign object damage potential to aircraft.] 1.8 PROTECTION ************************************************************************** NOTE: Delete requirements if inapplicable. For aircraft safety, Air Force ETL 11-29: Use of Light Emitting Diode (LED) Fixtures on Air Force Installations and Enduring/Contingency Locations, dated 22 Dec 2011, does NOT allow use of LED URS FOR EQM SECTION 02 41 00 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 fixtures for Obstruction Lighting. For work on airfield, coordinate with the Airfield manager the construction phasing plan and operational safety on the airfield during construction per UFC 3-260-01, Section 14. ************************************************************************** 1.8.1 Traffic Control Signs Where [pedestrian and driver] [aircraft] safety is endangered in the area of removal work, use traffic barricades with flashing lights. [ Anchor barricades in a manner to prevent displacement by wind, jet or prop blast.] Notify the Contracting Officer prior to beginning such work. [Provide a minimum of 2 FAA type L-810 steady burning red obstruction lights on temporary structures (including cranes) over 100 feet, but less than 100 ft, above ground level. The use of LED based obstruction lights are not permitted. For temporary structures (including cranes) over 200 ft above ground level provide obstruction lighting in accordance with FAA AC 70/7460-1. Light construction and installation shall comply with FAA AC 70/7460-1. Lights shall be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer. Maintain the temporary services during the period of construction and remove only after permanent services have been installed and tested and are in operation.] 1.8.2 Protection of Personnel Before, during and after the [demolition][ and ][deconstruction] work continuously evaluate the condition of the structure being [demolished] [and] [deconstructed] and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area. 1.9 FOREIGN OBJECT DAMAGE (FOD) ************************************************************************** NOTE: Delete requirements if inapplicable. Some large scale apron, hangar, or other type projects to be constructed adjacent to areas with operational aircraft may require temporary barricades or debris fences installed in place prior to the start of work. The station's air operations and public works departments must be contacted by the designer to determine project requirements. If fences or other type barricades are required, they must be designed and located to suit the project ************************************************************************** Aircraft and aircraft engines are subject to FOD from debris and waste material lying on airfield pavements. Remove all such materials that may appear on operational aircraft pavements due to the Contractor's operations. If necessary, the Contracting Officer may require the Contractor to install a temporary barricade at the Contractor's expense to URS FOR EQM SECTION 02 41 00 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 control the spread of FOD potential debris. The barricade shall include a fence covered with a fabric designed to stop the spread of debris. Anchor the fence and fabric to prevent displacement by winds or jet/prop blasts. Remove barricade when no longer required. 1.10 RELOCATIONS Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer. 1.11 EXISTING CONDITIONS Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results. PART 2 2.1 a. [ b. c. PRODUCTS FILL MATERIAL Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures. Fill material shall conform to the definition of satisfactory soil material as defined in AASHTO M 145, Soil Classification Groups A-1, A-2-4, A-2-5 and A-3. In addition, fill material shall be free from roots and other organic matter, trash, debris, frozen materials, and stones larger than 2 inches in any dimension. Proposed fill material must be sampled and tested by an approved soil testing laboratory, as follows: Soil classification AASHTO M 145 Moisture-density relations AASHTO T 180, Method B or D ] PART 3 3.1 EXECUTION EXISTING FACILITIES TO BE REMOVED ************************************************************************** NOTE: Thoughtful and considered disassembly as opposed to standard demolition will produce more URS FOR EQM SECTION 02 41 00 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 usable "reusables" and will help prevent damage to items scheduled to remain. Suggested uses for salvaged materials are as follows. 1. Whole buildings can be sold, leased, or donated and either moved or dismantled. 2. Separate asphalt roofing materials for milling and recycling. 3. Salvage whole bricks for reuse, keeping exterior bricks separate. Salvage remaining masonry to be crushed and used as landscape cover, sub-base material, or fill. 4. Salvage precast concrete panels as whole units for use as erosion control or landscape features. Salvage whole concrete blocks for reuse. Salvage concrete block pieces to be crushed and used as sub-base material or fill. Crush and grade remaining concrete for use as riprap, aggregate, sub-base material, or fill. 5. Chipped or shredded wood can be used onsite as ground cover, mulch, compost, pulp, or process fuel. 6. Crushed porcelain may be used for fill. 7. Wood cleared from the site can be chipped or shredded for use as ground cover, mulch, compost, pulp, or process fuel. 8. Salvage clean, unpainted, non-biocide-treated gypsum board to be ground up and used as soil amendment or recycled. ************************************************************************** Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse shall be disassembled. Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified. Materials shall be designated for reuse onsite whenever possible. Structures ************************************************************************** NOTE: Where necessary, add additional requirements relating to specific types of existing construction such as masonry, concrete, and other special requirements for removal work. It is very difficult to specify particular removal criteria in a guide specification or even a project specification. It may be more advantageous to show the work on the drawings. ************************************************************************** a. Remove existing structures indicated to be removed to [grade] [top of foundation walls] [[_____] feet below grade]. Interior walls, other than retaining walls and partitions, shall be removed to [_____] feet below grade or to top of concrete slab on ground. Break up basement slabs to permit drainage. Remove sidewalks, curbs, gutters and street light bases as indicated. b. [Demolish] [Deconstruct] structures in a systematic manner from the top of the structure to the ground. Complete demolition work above each URS FOR EQM SECTION 02 41 00 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 tier or floor before the supporting members on the lower level are disturbed. [Demolish] [Deconstruct] concrete and masonry walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer. c. Locate demolition and deconstruction equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing. d. [Building, or the remaining portions thereof, not exceeding 80 feet in height may be demolished by the mechanical method of demolition.] 3.1.1 3.1.1.1 Utilities and Related Equipment General Requirements Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made. Shut off and cap utilities for future use, as indicated. 3.1.1.2 Disconnecting Existing Utilities ************************************************************************** NOTE: Where the materials, meters, or related equipment to be affected in the area of demolition or deconstruction are the property of the local utility companies and not of the Government, the specifier must contact them, determine the disposition of the existing utilities, and modify the requirements herein as needed. ************************************************************************** Remove existing utilities [, as indicated] [uncovered by work] and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location [on the station] in accordance with instructions of the Contracting Officer. Chain Link Fencing Remove chain link fencing, gates and other related salvaged items scheduled for removal and transport to designated areas. Remove gates as whole units. Cut chain link fabric to [_____] 25 foot lengths and store in rolls off the ground. 3.1.2 Paving and Slabs ************************************************************************** NOTE: Delete requirements if inapplicable. ************************************************************************** [Remove [ground] [scarified] [sawcut] concrete and asphaltic concrete URS FOR EQM SECTION 02 41 00 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 paving and slabs [including aggregate base] [as indicated] to a depth of [_____] inches below [existing adjacent] [new finish] grade. [Provide neat double sawcuts at limits of pavement removal as indicated.]] Pavement and slabs designated to be recycled and utilized in this project shall be moved, ground and stored as directed by the Contracting Officer. Pavement and slabs not to be used in this project shall be removed from the Installation at Contractor's expense. 3.1.3 Roofing ************************************************************************** NOTE: Delete requirements if inapplicable. Where suspect deck conditions are encountered during design investigation, identify and include appropriate repair and safety provisions in the design documents to draw attention to the suspect areas and the need for additional safety precautions. ************************************************************************** [Remove existing roof system and associated components in their entirety down to existing roof deck.] [Remove [built-up] [single-ply] roofing to effect the connections with new flashing or roofing.] [Remove gravel surfacing from existing roofing felts for a minimum distance of 18 inches back from the cut. Remove gravel without damaging felts.] [Salvage asphalt roofing materials.] [Cut existing [felts] [membrane] [and insulation] along straight lines.] [Remove roofing system [and insulation] without damaging the roof deck.] Sequence work to minimize building exposure between demolition or deconstruction and new roof materials installation. 3.1.3.1 Temporary Roofing Install temporary roofing and flashing as necessary to maintain a watertight condition throughout the course of the work. Remove temporary work prior to installation of permanent roof system materials unless approved otherwise by the Contracting Officer. [The existing [deck] [and support structure] is deteriorated where indicated, such that ability to support foot traffic and construction loads is unknown. Make provisions for worker safety during demolition, deconstruction, and installation of new materials as described in paragraphs entitled "Statements" and "Regulatory and Safety Requirements."] 3.1.3.2 Reroofing When removing the existing roofing system from the roof deck, remove only as much roofing as can be recovered by the end of the work day, unless approved otherwise by the Contracting Officer. Do not attempt to open the roof covering system in threatening weather. Reseal all openings prior to suspension of work the same day. Masonry Sawcut and remove masonry so as to prevent damage to surfaces to remain[, to removed materials being salvaged] [and to facilitate the installation of new work]. Where new masonry adjoins existing, the new work shall abut or tie into the existing construction as [indicated] [specified for the new work]. Provide square, straight edges and corners where existing masonry adjoins new work and other locations.[ Masonry removed in whole blocks URS FOR EQM SECTION 02 41 00 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS shall be salvaged and stored for reuse.] [ be crushed[ for use as aggregate]]. TYMX989345A FA3002-09-D-0002 TG02 Masonry removed in pieces shall Concrete Saw concrete along straight lines to a depth of a minimum 2 inch. Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete. [Salvage removed concrete.] 3.1.4 Structural Steel ************************************************************************** NOTE: Delete structural steel and miscellaneous metals only if it is determined that there are no existing metals or structural steel to be recycled or salvaged. ************************************************************************** Dismantle structural steel at field connections and in a manner that will prevent bending or damage. Salvage for [reuse] [recycle] structural steel, steel joists, girders, angles, plates, columns and shapes. [Do not use flame-cutting torches] [Flame-cutting torches are permitted when other methods of dismantling are not practical]. Transport steel joists and girders as whole units and not dismantled. Transport structural steel shapes to a designated [storage area] [recycling facility] [area as directed by the Contracting Officer], stacked according to size, type of member and length, and stored off the ground, protected from the weather. 3.1.5 Miscellaneous Metal Salvage shop-fabricated items such as access doors and frames, steel gratings, metal ladders, wire mesh partitions, metal railings, metal windows and similar items as whole units. Salvage light-gage and cold-formed metal framing, such as steel studs, steel trusses, metal gutters, roofing and siding, metal toilet partitions, toilet accessories and similar items. [Scrap metal shall become the Contractor's property.] Recycle scrap metal as part of demolition and deconstruction operations. Provide separate containers to collect scrap metal and transport to a scrap metal collection or recycling facility, in accordance with the Waste Management Plan. 3.1.6 Carpentry Salvage for [reuse] [recycle] lumber, millwork items, and finished boards, and sort by type and size. [[Chip or shred and ]recycle salvaged wood unfit for reuse, except stained, painted, or treated wood.] [Salvage] [Remove] windows, doors, frames, and cabinets, and similar items as whole units, complete with trim and accessories. [Do not remove hardware attached to units, except for door closers. ] [Salvage hardware attached to units for reuse.] Brace the open end of door frames to prevent damage. 3.1.7 Carpet Remove existing carpet for reclamation in accordance with manufacturer recommendations and as follows. Remove used carpet in large pieces, roll URS FOR EQM SECTION 02 41 00 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 tightly, and pack neatly in a container. Remove adhesive according to recommendations of the Carpet and Rug Institute (CRI). Adhesive removal solvents shall comply with CRI CIS. Recycle removed carpet cushion. Acoustic Ceiling Tile Remove, neatly stack, and recycle acoustic ceiling tiles. Recycling may be available with manufacturer. Otherwise, priority shall be given to a local recycling organization. Recycling is not required if the tiles contain or may have been exposed to asbestos material. Airfield Lighting Remove existing airfield lighting as indicated and terminate in a manner satisfactory to the Contracting Officer. Remove [edge lights], [associated transformers] [and] [_____] as indicated and [deliver to a location on the station in accordance with instructions of the Contracting Officer] [dispose of off station] [_____]. 3.1.8 Patching Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish. Patching shall be as specified and indicated, and shall include: a. Concrete and Masonry: Completely fill holes and depressions, [caused by previous physical damage or] left as a result of removals in existing masonry walls to remain, with an approved masonry patching material, applied in accordance with the manufacturer's printed instructions. b. Where existing partitions have been removed leaving damaged or missing resilient tile flooring, patch to match the existing floor tile. c. Patch acoustic lay-in ceiling where partitions have been removed. The transition between the different ceiling heights shall be effected by continuing the higher ceiling level over to the first runner on the lower ceiling and closing the vertical opening with a painted sheet metal strip. 3.1.9 Air Conditioning Equipment ************************************************************************** NOTE: Delete requirements if inapplicable. Quantify by weight the amount and type of refrigerant to be recovered and indicate on plans. Directives from the Secretary of the Navy prohibit sale or transfer of Class I ODS materials outside of the Navy without prior approval from the Chief of Naval Operations or the Commandant of the Marine Corps. ************************************************************************** URS FOR EQM SECTION 02 41 00 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 [Remove air conditioning, refrigeration, and other equipment containing refrigerants without releasing chlorofluorocarbon refrigerants to the atmosphere in accordance with the Clean Air Act Amendment of 1990.] [Recover all refrigerants prior to removing air conditioning, refrigeration, and other equipment containing refrigerants and dispose of in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)."] [Turn in salvaged Class I ODS refrigerants as specified in paragraph, "Salvaged Materials and Equipment."] 3.1.10 Cylinders and Canisters Remove all fire suppression system cylinders and canisters and dispose of in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)." 3.1.11 Locksets on Swinging Doors ************************************************************************** NOTE: Use this paragraph when project includes removal and disposal of hinged or pivoted swinging doors. (This is a security measure.) ************************************************************************** Remove all locksets from all swinging doors indicated to be removed and disposed of. Deliver the locksets and related items to a designated location for receipt by the Contracting Officer after removal. 3.1.12 Mechanical Equipment and Fixtures ************************************************************************** NOTE: Delete, revise, or add to the text to cover the project requirements. Materials and equipment scheduled for salvage should be noted on the drawings. ************************************************************************** Disconnect mechanical hardware at the nearest connection to existing services to remain, unless otherwise noted. Disconnect mechanical equipment and fixtures at fittings. Remove service valves attached to the unit. Salvage each item of equipment and fixtures as a whole unit; listed, indexed, tagged, and stored. Salvage each unit with its normal operating auxiliary equipment. Transport salvaged equipment and fixtures, including motors and machines, to a designated [on station] storage area as directed by the Contracting Officer. Do not remove equipment until approved. Do not offer low-efficiency equipment for reuse[; provide to recycling service for disassembly and recycling of parts]. 3.1.12.1 Preparation for Storage Remove water, dirt, dust, and foreign matter from units; tanks, piping and fixtures shall be drained; interiors, if previously used to store flammable, explosive, or other dangerous liquids, shall be steam cleaned. Seal openings with caps, plates, or plugs. Secure motors attached by flexible connections to the unit. Change lubricating systems with the proper oil or grease. URS FOR EQM SECTION 02 41 00 Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.1.12.2 TYMX989345A FA3002-09-D-0002 TG02 Piping Disconnect piping at unions, flanges and valves, and fittings as required to reduce the pipe into straight lengths for practical storage. Store salvaged piping according to size and type. If the piping that remains can become pressurized due to upstream valve failure, end caps, blind flanges, or other types of plugs or fittings with a pressure gage and bleed valve shall be attached to the open end of the pipe to ensure positive leak control. Carefully dismantle piping that previously contained gas, gasoline, oil, or other dangerous fluids, with precautions taken to prevent injury to persons and property. Store piping outdoors until all fumes and residues are removed. Box prefabricated supports, hangers, plates, valves, and specialty items according to size and type. Wrap sprinkler heads individually in plastic bags before boxing. Classify piping not designated for salvage, or not reusable, as scrap metal. 3.1.12.3 Ducts Classify removed duct work as scrap metal. 3.1.12.4 Fixtures, Motors and Machines Remove and salvage fixtures, motors and machines associated with plumbing, heating, air conditioning, refrigeration, and other mechanical system installations. Salvage, box and store auxiliary units and accessories with the main motor and machines. Tag salvaged items for identification, storage, and protection from damage. Classify [non-porcelain ]broken, damaged, or otherwise unserviceable units and not caused to be broken, damaged, or otherwise unserviceable as debris to be disposed of by the Contractor. [Salvage and crush porcelain plumbing fixtures unsuitable for reuse.] 3.1.13 Electrical Equipment and Fixtures Salvage motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Salvage wiring systems and components. Box loose items and tag for identification. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system. 3.1.13.1 Fixtures Remove and salvage electrical fixtures. Salvage unprotected glassware from the fixture and salvage separately. Salvage incandescent, mercury-vapor, and fluorescent lamps and fluorescent ballasts manufactured prior to 1978, boxed and tagged for identification, and protected from breakage. 3.1.13.2 Electrical Devices Remove and salvage switches, switchgear, transformers, conductors including wire and nonmetallic sheathed and flexible armored cable, regulators, meters, instruments, plates, circuit breakers, panelboards, outlet boxes, and similar items. Box and tag these items for identification according to type and size. 3.1.13.3 Wiring Ducts or Troughs Remove and salvage wiring ducts or troughs. Dismantle plug-in ducts and wiring troughs into unit lengths. Remove plug-in or disconnecting devices URS FOR EQM SECTION 02 41 00 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 from the busway and store separately. 3.1.13.4 Conduit and Miscellaneous Items Salvage conduit except where embedded in concrete or masonry. Consider corroded, bent, or damaged conduit as scrap metal. Sort straight and undamaged lengths of conduit according to size and type. Classify supports, knobs, tubes, cleats, and straps as debris to be removed and disposed. Elevators and Hoists Remove elevators, hoists, and similar conveying equipment and salvage as whole units, to the most practical extent. Remove and prepare items for salvage without damage to any of the various parts. Salvage and store rails for structural steel with the equipment as an integral part of the unit. 3.2 CONCURRENT EARTH-MOVING OPERATIONS ************************************************************************** NOTE: Caution must be taken to prevent uncovered holes and other such hazards. If work is to be under a separate contract and subsequent filling is not required under the separate contract, arrangements must be made to have the filling done under this contract. ************************************************************************** Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition or deconstruction work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings. 3.3 DISPOSITION OF MATERIAL ************************************************************************** NOTE: This article entitled "Disposition of Material" and the paragraphs that follow are for all projects except as noted. ************************************************************************** 3.3.1 Title to Materials ************************************************************************** NOTE: To minimize the possibility of contested ownership of materials or equipment in structures to be demolished or deconstructed, the following letter should be sent to the station sufficiently in advance of the date on which action is required, and the response thereto incorporated in either the project specifications or bidding documents. The Government shall prepare this letter. For project prepared by an A/E, the A/E must notify the Government the need for this correspondence. From: URS FOR EQM (Appropriate EDF Activity) SECTION 02 41 00 Page 17 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS To: TYMX989345A FA3002-09-D-0002 TG02 Commanding Officer, (Station) Subj: Contract (Number) - [_____]: (Including [Demolition] [and] [Deconstruction] of [(_____)] 1. This activity is preparing the documents preliminary to advertising the subject contract for bids. A portion of this contract will be concerned with the ownership of the materials in the structure(s) and the contents of the building(s) to be [demolished] [and] [deconstructed]. It is normal practice to specify that the structures, and all equipment or other material inside the structures at the time the contract is advertised for bids, become the property of the Contractor. 2. Accordingly, it is requested that this activity be advised of the existence of any material or equipment within the limits of the contract which is to remain the property of the Government. A negative reply is requested. If there is any material or equipment in this category, it is requested that action be initiated to remove it from the limits of the contract. If prompt removal is impractical, it will be necessary for the station to make a complete inventory of, and tag or mark, each item which is to remain the property of the Government. A copy of the inventory, a description of the tag or mark used, and the desired disposition of the item must be forwarded to this activity for inclusion in the specification or bidding documents. 3. In the past, this activity has experienced considerable difficulty where a building evacuated prior to demolition or deconstruction is then used to store other material or equipment temporarily and the items were in storage during the bid advertising period. Upon award of the contract, the Contractor claimed the material and either removed it or claimed and was awarded compensation for it. Therefore, it is requested that the structure(s) to be demolished or deconstructed which are included in this contract not be used for temporary storage during the bid advertising period. 4. It is requested that the reply to this letter be sent to this activity not later than [60] [_____] days after the date of this letter. Failure to do so may result in unnecessary cost to the Government in claims. 5. Insert name of contract and identify buildings(s) to be included under contract. Further revise as necessary to suit conditions. ************************************************************************** Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and URS FOR EQM SECTION 02 41 00 Page 18 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited. 3.3.2 Reuse of Materials and Equipment ************************************************************************** NOTE: Delete if inapplicable, or edit to suit individual requirements. Items to be salvaged must be described in adequate detail to establish the limits of the items involved. Requirements for preparation and disposition will be as required to meet job conditions. ************************************************************************** Remove and store materials and equipment [listed [in the [Demolition] [Deconstruction] Plan] [_____]] [indicated [_____]] to be reused or relocated to prevent damage, and reinstall as the work progresses. Salvaged Materials and Equipment ************************************************************************** NOTE: Delete if inapplicable, or edit to suit individual requirements. Items to be salvaged shall be described in adequate detail to establish the limits of the items involved. Requirements for preparation and disposition will be as required to meet job conditions. ************************************************************************** Remove materials and equipment that are [listed [in the [Demolition] [Deconstruction] Plan][_____]] [indicated [_____]] [and] [specified [_____]] to be removed by the Contractor and that are to remain the property of the Government, and deliver to a storage site [, as directed within [_____] miles of the work site]. a. Salvage items and material to the maximum extent possible. b. Store all materials salvaged for the Contractor as approved by the Contracting Officer and remove from Government property before completion of the contract. On site sales of salvaged material is prohibited. c. Remove salvaged items to remain the property of the Government in a manner to prevent damage, and packed or crated to protect the items from damage while in storage or during shipment. Items damaged during removal or storage must be repaired or replaced to match existing items. Properly identify the contents of containers. Deliver the following items reserved as property of the Government to the areas designated: [_____]. d. Remove the following items reserved as property of the using service URS FOR EQM SECTION 02 41 00 Page 19 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 prior to commencement of work under this contract: e. [_____]. Remove historical items in a manner to prevent damage. Deliver the following historical items to the Government for disposition: Corner stones, contents of corner stones, and document boxes wherever located on the site. ************************************************************************** NOTE: For Class I ODS materials, use the first bracketed statement if the Contractor is to remove the material. Use the second bracketed statement if a Public Works Center or other Navy activity is to remove the Class I ODS materials. Edit statements for the project as necessary. ************************************************************************** f. [Remove and capture all Class I ODS refrigerants in accordance with the Clean Air Act Amendment of 1990, and turn in to the Navy [as directed by the Commanding Officer.] [by shipping the refrigerant container to the Defense Logistics Agency at the following address: Defense Depot Richmond VA (DDRV) SW0400 Cylinder Operations 8000 Jefferson Davis Highway Richmond, VA 23297-5900]] [The Government will remove and capture Class I ODS refrigerants. the web site for ODS, link to: https://www.osd.mil/denix/Public/News/DLA/ODS/sect1.html] To view Disposal of Ozone Depleting Substance (ODS) Class I and Class II ODS are defined in Section, 602(a) and (b), of The Clean Air Act. Prevent discharge of Class I and Class II ODS to the atmosphere. Place recovered ODS in cylinders meeting AHRI Guideline K suitable for the type ODS (filled to no more than 80 percent capacity) and provide appropriate labeling. Recovered ODS shall be [put back into the existing equipment] [turned over to the Contracting Officer] [removed from Government property and disposed of in accordance with 40 CFR 82]. Products, equipment and appliances containing ODS in a sealed, self-contained system (e.g. residential refrigerators and window air conditioners) shall be disposed of in accordance with 40 CFR 82. Submit Receipts or bills of lading, as specified. Submit a shipping receipt or bill of lading for all containers of ozone depleting substance (ODS) shipped to the Defense Depot, Richmond, Virginia. 3.3.3 Special Instructions No more than one type of ODS is permitted in each container. A warning/hazardous label shall be applied to the containers in accordance with Department of Transportation regulations. All cylinders including but not limited to fire extinguishers, spheres, or canisters containing an ODS shall have a tag with the following information: a. Activity name and unit identification code b. Activity point of contact and phone number URS FOR EQM SECTION 02 41 00 Page 20 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 c. Type of ODS and pounds of ODS contained d. Date of shipment e. National stock number (for information, call (804) 279-4525). Fire Suppression Containers Deactivate fire suppression system cylinders and canisters with electrical charges or initiators prior to shipment. Also, safety caps must be used to cover exposed actuation mechanisms and discharge ports on these special cylinders. Transportation Guidance Ship all ODS containers in accordance with MIL-STD-129, DLA 4145.25 (also referenced one of the following: Army Regulation 700-68, Naval Supply Instruction 4440.128C, Marine Corps Order 10330.2C, and Air Force Regulation 67-12), 49 CFR 173.301, and DOD 4000.25-1-M. 3.3.2 Unsalvageable and Non-Recyclable Material Dispose of unsalvageable and non-recyclable noncombustible material in the disposal area located specified by the Contracting Officer[_____]. The fill in the disposal area shall remain below elevation specified by the Contracting Officer[_____] and after disposal is completed, the disposal area shall be uniformly graded to drain. Dispose of unsalvageable and non-recyclable combustible material [in the sanitary fill area located [_____]] [off the site] [by burning]. 3.4 CLEANUP Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal. 3.5 3.5.1 DISPOSAL OF REMOVED MATERIALS Regulation of Removed Materials Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified [off the [_____] center] [in the Waste Management Plan] [_____]. [Storage of removed materials on the project site is prohibited.] 3.5.2 Burning on Government Property [Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property] [Transport combustible materials removed from demolished and deconstructed structures to the areas designated for burning. Control fires for protection of persons and property. Monitor fires continuously until the fires have burned out or have been extinguished. Comply with Federal, State and local laws regulating the building and maintaining of brush and trash fires]. 3.5.3 Removal to Spoil Areas on Government Property Transport noncombustible materials removed from demolition and URS FOR EQM SECTION 02 41 00 Page 21 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 deconstruction structures to designated spoil areas on Government property, if applicable, as directed by the Contracting Officer. 3.5.4 Removal from Government Property Transport waste materials removed from demolished and deconstructed structures, except waste soil, from Government property for legal disposal as directed by the Contracting Officer. Dispose of waste soil as directed by the Contracting Officer. REUSE OF SALVAGED ITEMS Recondition salvaged materials and equipment designated for reuse before installation. Replace items damaged during removal and salvage operations or restore them as necessary to usable condition. -- End of Section -- URS FOR EQM SECTION 02 41 00 Page 22 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-03 30 53 (May 2014) -------------------------Preparing Activity: USACE Superseding UFGS-03 30 53 (April 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE ************************************************************************** NOTE: This guide specification covers the requirements for projects involving amounts of concrete less than 380 cubic meters (500 cubic yards). This section was originally developed for USACE Civil Works projects. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: This specification requires furnishing all material and equipment, and performing all labor for the manufacturing, transporting, placing, finishing, and curing of concrete for recreation sites, road relocations, or other structures such as culvert headwalls, comfort stations, residences, or low head gate structures. Consideration should be given to using Section 03 31 01.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS when the quantity of concrete is 380 cubic meters (500 cubic ) or greater per structure. ************************************************************************** URS FOR EQM SECTION 03 30 53 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.1 TYMX989345A FA3002-09-D-0002 TG02 SUMMARY Perform all work in accordance with ACI 318. 1.2 UNIT PRICES ************************************************************************** ************************************************************************** 1.2.1 Concrete Payment Payment will cover all costs associated with[ manufacturing,] furnishing, delivering, placing, finishing, and curing of concrete for the various items of the schedule, including the cost of all formwork. Payment for concrete, for which payment is made as a lump sum, [is] [is not] to be included in this unit price payment item. Payment for grout, preformed expansion joints, field-molded sealants, waterstops, reinforcing steel bars or wire reinforcement [is] [is not] to be included in this unit price payment item. 1.2.2 Measurement Concrete will be measured for payment on the basis of the actual volume of concrete within the pay lines of the structures as indicated. Measurement of concrete placed against the sides of any excavation without the use of intervening forms will be made only within the pay lines of the structure. No deductions will be made for rounded or beveled edge, for space occupied by metal work, for electrical conduits or timber, or for voids or embedded items that are either less than 5 cubic feet in volume or 1 square foot in cross section. 1.2.3 Unit of Measure Unit of measure: 1.3 cubic yard. REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** URS FOR EQM SECTION 03 30 53 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI) ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary ACI 301 (2010; Errata 2011) Specifications for Structural Concrete ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete ACI 318 (2011; Errata 1 2011; Errata 2 2012; Errata 3-4 2013) Building Code Requirements for Structural Concrete and Commentary ACI 347 (2004; Errata 2008; Errata 2012) Guide to Formwork for Concrete ACI SP-66 (2004) ACI Detailing Manual ASTM INTERNATIONAL (ASTM) ASTM A1064/A1064M (2013) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete ASTM A615/A615M (2014) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement ASTM C1064/C1064M (2011) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete ASTM C1260 (2007) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method) ASTM C143/C143M (2012) Standard Test Method for Slump of Hydraulic-Cement Concrete ASTM C150/C150M (2012) Standard Specification for Portland Cement ASTM C1567 (2013) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method) ASTM C1602/C1602M (2012) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete URS FOR EQM SECTION 03 30 53 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM C172/C172M (2014) Standard Practice for Sampling Freshly Mixed Concrete ASTM C173/C173M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method ASTM C260/C260M (2010a) Standard Specification for Air-Entraining Admixtures for Concrete ASTM C309 (2011) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete ASTM C31/C31M (2012) Standard Practice for Making and Curing Concrete Test Specimens in the Field ASTM C33/C33M (2013) Standard Specification for Concrete Aggregates ASTM C39/C39M (2014a) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens ASTM C494/C494M (2013) Standard Specification for Chemical Admixtures for Concrete ASTM C618 (2012a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete ASTM C685/C685M (2011) Concrete Made by Volumetric Batching and Continuous Mixing ASTM C94/C94M (2014a) Standard Specification for Ready-Mixed Concrete ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA) 40 CFR 247 1.4 Comprehensive Procurement Guideline for Products Containing Recovered Materials SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have URS FOR EQM SECTION 03 30 53 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-02 Shop Drawings Installation Drawings[; G][; G, [_____]] SD-03 Product Data [ [ [ [ Air-Entraining Admixture Accelerating Admixture] Water-Reducing or Retarding Admixture Curing Materials Expansion Joint Filler Strips, Premolded] Joint Sealants - Field Molded Sealants] Waterstops] [Chemical Floor Hardener] Batching and Mixing Equipment Conveying and Placing Concrete [Formwork] Mix Design Data[; G][; G, [_____]] Ready-Mix Concrete [Curing Compound] Mechanical Reinforcing Bar ConnectorsSteel URS FOR EQM SECTION 03 30 53 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 SD-06 Test Reports Aggregates Concrete Mixture Proportions[; G][; G, [_____]] [Measurement of Floor Tolerances] [Compressive Strength Testing[; G][; G, [_____]]] [Slump[; G][; G, [_____]]] [Air Content] Water SD-07 Certificates Cementitious Materials Pozzolan CPG for recycled materials or appropriate Waiver Form Aggregates [Delivery Tickets] SD-08 Manufacturer's Instructions Chemical Floor Hardener Curing Compound 1.5 QUALITY ASSURANCE Indicate specific locations of [Concrete Placement][, Forms][, Steel Reinforcement] [Accessories] [Expansion Joints] [Construction Joints] [Contraction Joints] [Control Joints] on installation drawings and include, but not be limited to, square feet of concrete placements, thicknesses and widths, plan dimensions, and arrangement of cast-in-place concrete section. 1.5.1 Regulatory Requirements ************************************************************************** NOTE: This section relates to the implementation of RCRA of 1976 as amended (42 USC 6901) which requires that EPA designated items be used to the maximum extent practicable. One of the requirements of 40 CFR 247 is that agencies promote the use of products containing recycled materials. Parts of this guide specification are only promotional in nature in that they recommend or encourage, in lieu of requiring, the Contractor to use products containing recycled materials. Coordinate this section with Section 01 62 35 RECYCLED/RECOVERED/BIOBASED MATERIALS in every project where 40 CFR 247 is applicable. Include the applicable state highway department document title in which an acceptable gradation for the concrete aggregate is presented. ************************************************************************** The state statutory and regulatory requirements: [_____] form a part of this specification to the extent referenced. Submit CPG for recycled materials or appropriate Waiver Form. URS FOR EQM SECTION 03 30 53 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Flatness and Levelness of Floor Slabs Conduct floor flatness and levelness test, (FF and FL respectively), on floor slabs in accordance with the provisions set forth in ASTM E1155M or ASTM E1155. Make floor tolerance measurements by the approved laboratory and inspection service within 24 hours after completion of final troweling operation and before forms and shores have been removed. Provide results of floor tolerance tests, including formal notice of acceptance or rejection of the work, to the Contracting Officer within 24 hours after data collection. PART 2 2.1 PRODUCTS SYSTEM DESCRIPTION The Government retains the option to sample and test [joint sealer, joint filler material, waterstop,] aggregates and concrete to determine compliance with the specifications. Provide facilities and labor as may be necessary to assist the Government in procurement of representative test samples. Obtain samples of aggregates at the point of batching in accordance with ASTM D75/D75M. Sample concrete in accordance with ASTM C172/C172M. Determine slump and air content in accordance with ASTM C143/C143M and ASTM C231/C231M, respectively, when cylinders are molded. Prepare, cure, and transport compression test specimens in accordance with ASTM C31/C31M. Test compression test specimens in accordance with ASTM C39/C39M. Take samples for strength tests not less than once each shift in which concrete is produced [from each strength of concrete required]. Provide a minimum of five specimens from each sample; two to be tested at 28 days (90 days if pozzolan is used) for acceptance, two will be tested at 7 days for information and one held in reserve. 2.1.1 Strength Acceptance test results are the average strengths of two specimens tested at 28 days (90 days if pozzolan is used). The strength of the concrete is considered satisfactory so long as the average of three consecutive acceptance test results equal or exceed the specified compressive strength, f'c, but not more than 20 percent, and no individual acceptance test result falls below f'c by more than 500 psi. 2.1.2 Construction Tolerances Apply a Class "C" finish to all surfaces except those specified to receive a Class "D" finish. Apply a Class "D" finish to all post-construction surfaces which will be permanently concealed. Surface requirements for the classes of finish required are as specified in ACI 117. 2.1.3 Concrete Mixture Proportions ************************************************************************** NOTE: The nominal maximum size of the coarse aggregate is as specified in ACI 318, Chapter 3 and ACI 318M. Guidelines for the maximum water cementitious material ratio and air content can be found in ACI 318 Chapter 4. ************************************************************************** Concrete mixture proportions are the responsibility of the Contractor. Mixture proportions must include the dry weights of cementitious URS FOR EQM SECTION 03 30 53 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 material(s); the nominal maximum size of the coarse aggregate; the specific gravities, absorptions, and saturated surface-dry weights of fine and coarse aggregates; the quantities, types, and names of admixtures; and quantity of water per yard of concrete. Provide materials included in the mixture proportions of the same type and from the same source as will be used on the project. The specified compressive strength f'c is [3,000] [_____] psi at 28 days (90 days if pozzolan is used). The maximum nominal size coarse aggregate is [3/4] [1] [1-1/2] inch, in accordance with ACI 304R. The air content must be between 4.5 and 7.5 percent with a slump between 2 and 5 inches. The maximum water-cementitious material ratio is [0.50] [_____]. Submit the applicable test reports and mixture proportions that will produce concrete of the quality required, ten days prior to placement of concrete. 2.2 MATERIALS Submit manufacturer's literature from suppliers which demonstrates compliance with applicable specifications for the specified materials. 2.2.1 Cementitious Materials Submit Manufacturer's certificates of compliance, accompanied by mill test reports, attesting that the concrete materials meet the requirements of the specifications in accordance with the Special Clause "CERTIFICATES OF COMPLIANCE". Also, certificates for all material conforming to EPA's Comprehensive Procurement Guidelines (CPG), in accordance with 40 CFR 247. Provide cementitious materials that conform to the appropriate specifications listed: 2.2.1.1 Portland Cement ************************************************************************** NOTES: Limit the use of air-entraining cement to concrete placements where separate batching of air-entraining admixture is not practical. If high early strength concrete is required, specify Type III after consulting the agency's Subject Matter Expert in Concrete Materials. Tricalcium aluminate, for sulfate resistance, is limited to Type III cement. If high early strength is not required, specify Type II rather than Type I when moderate sulfate resistance is required, or Type V when high sulfate resistance is required. Specify low-alkali cement when the aggregate is either silica or carbonate reactive. ************************************************************************** ASTM C150/C150M, Type [I][II][III][V], [low alkali] [including false set requirements] with tri-calcium aluminates (C3A) content less than 10 percent and a maximum cement-alkali content of 0.80 percent Na2Oe (sodium oxide) equivalent. [2.2.1.2 Blended Hydraulic Cement ************************************************************************** NOTES: Limit the use of air-entraining cement to URS FOR EQM SECTION 03 30 53 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 concrete placements where separate batching of air-entraining admixture is not practical. Specify low-alkali cement when reactive aggregates are to be used. ************************************************************************** Provide blended cement conforming to ASTM C595/C595M and ASTM C1157/C1157M, Type IP or IS, including the optional requirement for mortar expansion [and sulfate soundness] and consist of a mixture of ASTM C150/C150M Type I, or Type II cement and a complementary cementing material. The slag added to the Type IS blend must be ASTM C989/C989M ground granulated blast-furnace slag. The pozzolan added to the Type IP blend must be ASTM C618 Class F, interground with the cement clinker. Provide the manufacturer's written statement that the amount of pozzolan in the finished cement will not vary more than plus or minus 5 mass percent of the finished cement from lot-to-lot or within a lot. Do not change the percentage and type of mineral admixture used in the blend from that submitted for the aggregate evaluation and mixture proportioning. ]2.2.1.2 Pozzolan Provide pozzolan that conforms to ASTM C618, Class F, including requirements of Tables 1A and 2A. 2.2.2 Aggregates ************************************************************************** NOTE: This note may be disregarded for regions where Alkali-Silica Reactivity (ASR) is not a concern. Some aggregate sources may exhibit an ASR potential. ASR is a potentially deleterious reaction between alkalis present in concrete and some siliceous aggregates, reference EM 1110-2-2000 paragraph 2-3b(6) and appendix D. Where ASR is known or suspected to pose a concern for concrete durability, it is recommended that aggregates proposed for use in concrete be evaluated to determine ASR potential and an effective mitigation. EM 1110-2-2000, provides recommendations for evaluating and mitigating ASR in concrete mixtures. Aggregate evaluations may not be practical for projects requiring small quantities of concrete (less than 190 cubic meters (250 cubic yards)). Section 32 13 11 CONCRETE PAVEMENT FOR AIRFIELDS AND OTHER HEAVY-DUTY PAVEMENTS, paragraph ALKALI-SILICA REACTIVITY, provides a specification method for the Contractor to evaluate and mitigate ASR in concrete mixtures. The expansion limits specified in Section 32 13 11 are requirements for pavements and exterior slab construction. For structural concrete applications the measured expansion must be less than 0.10 percent. It may not be economical or practical to specify different test limit requirements for use on the same project, in which case the lower limit is required by the application URS FOR EQM SECTION 03 30 53 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 The designer may use the specification method in Section 32 13 11 by incorporating the relevant paragraphs into this specification, or may use the following requirements (retain either the 0.10 or the 0.08 percent expansion limits as appropriate). ************************************************************************** For fine and coarse aggregates meet the quality and grading requirements of ASTM C33/C33M[ and test and evaluate for alkali-aggregate reactivity in accordance with ASTM C1260. Perform evaluation of fine and coarse aggregates separately and in combination, matching the proposed mix design proportioning. All results of the separate and combination testing must have a measured expansion less than 0.08 percent at 28 days after casting. If the test data indicates an expansion of 0.08 percent or greater, reject the aggregate(s) or perform additional testing using ASTM C1260 and ASTM C1567. Perform the additional testing using ASTM C1260 and ASTM C1567 using the low alkali portland cement in combination with ground granulated blast furnace (GGBF) slag, or Class F fly ash. Use GGBF slag in the range of 40 to 50 percent of the total cementitious material by mass. Use Class F fly ash in the range of 25 to 40 percent of the total cementitious material by mass]. Submit certificates of compliance and test reports for aggregates showing the material(s) meets the quality and grading requirements of the specifications under which it is furnished. 2.2.3 Admixtures Provide admixtures, when required or approved, in compliance with the appropriate specification listed. Retest chemical admixtures that have been in storage at the project site, for longer than 6 months or that have been subjected to freezing, at the expense of the Contractor at the request of the Contracting Officer and will be rejected if test results are not satisfactory. 2.2.3.1 Air-Entraining Admixture Provide air-entraining admixture that meets the requirements of ASTM C260/C260M. [2.2.3.2 Accelerating Admixture Provide calcium chloride meeting the requirements of ASTM D98. Other accelerators must meet the requirements of ASTM C494/C494M, Type C or E. ]2.2.3.2 Water-Reducing or Retarding Admixture Provide water-reducing or retarding admixture meeting the requirements of ASTM C494/C494M, Type A, B, or D. [High-range water reducing admixture Type F [or G] may be used only when approved, approval being contingent upon particular placement requirements as described in the Contractor's Quality Control Plan.] 2.2.4 Water Mixing and curing water in compliance with the requirements of ASTM C1602/C1602M; [potable, and] free of injurious amounts of oil, acid, salt, or alkali. Submit test report showing water complies with ASTM C1602/C1602M. URS FOR EQM SECTION 03 30 53 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS [2.2.5 TYMX989345A FA3002-09-D-0002 TG02 Reinforcing Steel ************************************************************************** NOTE: Delete this paragraph if Section 03 20 00.00 10 CONCRETE REINFORCING is to be used. Also delete this paragraph if fibercrete is accepted for use by the Contracting Officer. ************************************************************************** Provide reinforcing bars conforming to the requirements of ASTM A615/A615M, Grade 60, deformed. Provide welded steel wire reinforcement conforming to the requirements of ASTM A1064/A1064M. Detail reinforcement not indicated in accordance with ACI 301 and ACI SP-66. Provide mechanical reinforcing bar connectors in accordance with ACI 301 and provide 125 percent minimum yield strength of the reinforcement bar. ][2.2.6 Expansion Joint Filler Strips, Premolded ************************************************************************** NOTE: Delete this paragraph if Section 03 15 00.00 10 CONCRETE ACCESSORIES is used. ************************************************************************** Expansion joint filler strips, premolded of sponge rubber conforming to ASTM D1752, Type I. ][2.2.7 Joint Sealants - Field Molded Sealants ************************************************************************** NOTES: Use ASTM C920 for field-molded sealants in small hydraulic structures. ************************************************************************** Conform to ASTM C920, Type M, Grade NS, Class 25, use NT for vertical joints and Type M, Grade P, Class 25, use T for horizontal joints. Provide polyethylene tape, coated paper, metal foil, or similar type bond breaker materials. The backup material needs to be compressible, nonshrink, nonreactive with the sealant, and a nonabsorptive material such as extruded butyl or polychloroprene foam rubber. Immediately prior to installation of field-molded sealants, clean the joint of all debris and further cleaned using water, chemical solvents, or other means as recommended by the sealant manufacturer or directed. ][2.2.6 Formwork Design and engineer the formwork as well as its construction in accordance with ACI 301 Section 2 and 5 and ACI 347. Fabricate of wood, steel, or other approved material. Submit formwork design prior to the first concrete placement. ][2.2.7 Form Coatings Provide form coating in accordance with ACI 301. URS FOR EQM SECTION 03 30 53 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS ][2.2.8 TYMX989345A FA3002-09-D-0002 TG02 Vapor Retarder[ and VaporBarrier] [ASTM E1745 Class [C] [A] [B] polyethylene sheeting, minimum [10] [15] mil thickness or other equivalent material with a maximum permeance rating of 0.04 perms per ASTM E96/E96M.] [ASTM E1745 Class [C] [A] [B] polyethylene sheeting, minimum [10] [15] mil thickness or ASTM E1993/E1993M bituminous membrane or other equivalent material with a maximum permeance rating of 0.01 perms per ASTM E96/E96M.] Consider plastic vapor retarders and adhesives with a high recycled content, low toxicity low VOC (Volatile Organic Compounds) levels. ]2.2.8 Curing Materials Provide curing materials in accordance with ACI 301, Section 5. 2.3 READY-MIX CONCRETE Provide ready-mix concrete with mix design data conforming to ACI 301 Part 2. Submit delivery tickets in accordance with ASTM C94/C94M for each ready-mix concrete delivery, include the following additional information: . a. Type and brand cement b. Cement content in 94-pound bags per cubic yard of concrete c. Maximum size of aggregate d. Amount and brand name of admixture e. Total water content expressed by water cementitious material ratio 2.4 ACCESSORIES 2.4.1 2.4.1.1 Waterstops PVC Waterstop Polyvinylchloride waterstops conforming to COE CRD-C 572. 2.4.1.2 Rubber Waterstop Rubber waterstops conforming to COE CRD-C 513. 2.4.1.3 Thermoplastic Elastomeric Rubber Waterstop Thermoplastic elastomeric rubber waterstops conforming to ASTM D471. 2.4.1.4 Hydrophilic Waterstop Swellable strip type compound of polymer modified chloroprene rubber that swells upon contact with water conforming to ASTM D412 as follows: Tensile strength 420 psi minimum; ultimate elongation 600 percent minimum. Minimum hardness of 50 on the type A durometer and the volumetric expansion ratio in distilled water at 70 degrees F; 3 to 1 minimum. Chemical Floor Hardener Provide hardener which is a colorless aqueous solution containing a blend URS FOR EQM SECTION 03 30 53 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 of inorganic silicate or siliconate material and proprietary components combined with a wetting agent; that penetrates, hardens, and densifies concrete surfaces. Submit manufactures instructions for placement of liquid chemical floor hardener. 2.4.1 Curing Compound Provide curing compound conforming to ASTM C309. instructions for placing curing compound. PART 3 3.1 Submit manufactures EXECUTION PREPARATION Prepare construction joints to expose coarse aggregate. The surface nust be clean, damp, and free of laitance. Construct ramps and walkways, as necessary, to allow safe and expeditious access for concrete and workmen. Remove snow, ice, standing or flowing water, loose particles, debris, and foreign matter. Satisfactorily compact earth foundations. Make spare vibrators available. Placement cannot begin until the entire preparation has been accepted by the Government. 3.1.1 Embedded Items Secure reinforcement in place after joints, anchors, and other embedded items have been positioned. Arrange internal ties so that when the forms are removed the metal part of the tie is not less than 2 inches from concrete surfaces permanently exposed to view or exposed to water on the finished structures. Prepare embedded items so they are be free of oil and other foreign matters such as loose coatings or rust, paint, and scale. The embedding of wood in concrete is permitted only when specifically authorized or directed. Provide all equipment needed to place, consolidate, protect, and cure the concrete at the placement site and in good operating condition. 3.1.2 Formwork Installation Forms must be properly aligned, adequately supported, and mortar-tight. Provide smooth form surfaces, free from irregularities, dents, sags, or holes when used for permanently exposed faces. Chamfer all exposed joints and edges , unless otherwise indicated. [3.1.3 Vapor Retarder[ and Vapor Barrier] Installation ************************************************************************** NOTE: Use a vapor barrier only when it is desirable to prevent migration of moisture through slabs of buildings. ************************************************************************** Install in accordance with ASTM E1643. Apply vapor retarder[ andbarrier] over gravel fill. Lap edges not less than 12 inches. Seal all joints with pressure-sensitive adhesive not less than 2 inches wide. Protect the vapor barrier at all times to prevent injury or displacement prior to and during concrete placement. URS FOR EQM SECTION 03 30 53 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS ]3.1.3 Production of Concrete 3.1.3.1 Ready-Mixed Concrete TYMX989345A FA3002-09-D-0002 TG02 Provide ready-mixed concrete conforming to ASTM C94/C94M except as otherwise specified. 3.1.3.2 Concrete Made by Volumetric Batching and Continuous Mixing Conform to ASTM C685/C685M. [3.1.3.3 Batching and Mixing Equipment The option of using an on-site batching and mixing facility is available. The facility must provide sufficient batching and mixing equipment capacity to prevent cold joints. Submit the method of measuring materials, batching operation, and mixer for review, and manufacturer's data for batching and mixing equipment demonstrating compliance with the applicable specifications. [Provide an Onsite Plant conforming to the requirements of either ASTM C94/C94M or ASTM C685/C685M.] ][3.1.4 Waterstops Install and splice waterstops as directed by the manufacturer. ]3.2 CONVEYING AND PLACING CONCRETE Convey and place concrete in accordance with ACI 301, Section 5. 3.2.1 Cold-Weather Requirements Place concrete in cold weather in accordance with ACI 306R. 3.2.2 Hot-Weather Requirements Place concrete in hot weather in accordance with ACI 305R. 3.3 3.3.1 FINISHING Temperature Requirement Do not finish or repair concrete when either the concrete or the ambient temperature is below 50 degrees F. 3.3.2 Finishing Formed Surfaces Remove all fins and loose materials , and surface defects including filling of tie holes. Repair all honeycomb areas and other defects. Remove all unsound concrete from areas to be repaired. Ream or chip surface defects greater than 1/2 inch in diameter and holes left by removal of tie rods in all surfaces not to receive additional concrete and fill with dry-pack mortar. Brush-coat the prepared area with an approved epoxy resin or latex bonding compound or with a neat cement grout after dampening and filling with mortar or concrete. Use a blend of portland cement and white cement in mortar or concrete for repairs to all surfaces permanently exposed to view shall be so that the final color when cured is the same as adjacent concrete. URS FOR EQM SECTION 03 30 53 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.3.3 TYMX989345A FA3002-09-D-0002 TG02 Finishing Unformed Surfaces Finish unformed surfaces in accordance with ACI 301, Section 5. FINISH LOCATION Float Trowel Broom or Belt Flat Floor Finishes ************************************************************************** NOTE: Floor flatness and floor levelness affects the appearance and function of finishes applied to the concrete and in situations such as large or long expanses of glossy floor materials. Low tolerances for subsequent finish materials (for example, thin set ceramic and porcelain tile and wood gymnasium floors) require the designer to specify higher than normal floor flatness requirements. Higher "F" ratings are more stringent and tighter tolerances of F numbers stop at 100. The numbers provided in brackets are typical numbers, but A/E should research and select F numbers high enough to get desired results but not so high as to cause undue cost increases and construction issues. An FF20/FL15 is equivalent to 8 mm in 3 meters (5/16 inches in 10 feet). This test method is not suitable for unshored decks. Fitted partitions need an FL greater than or equal to 25. The F-numbers are given below for purposes of illustration only. ************************************************************************** In accordance with ACI 302.1R, construct in accordance with one of the methods recommended in Table 7.15.3, "Typical Composite FF/FL Values for Various Construction Methods." ACI 117 for tolerances tested by ASTM E1155M or ASTM E1155. These requirements are based upon the latest FF/FL method. 3.3.3.1 Floor Slabs Conform floor slabs on grade to the following ACI F-number requirements unless noted otherwise: Specified Overall Values FF30/FL23 minimum [FF_____/FL_____] Minimum Local Values FF17/FL15 minimum [FF_____/FL_____] 3.3.3.2 Subject to Vehicular Traffic Floor slabs on grade subject to vehicular traffic or receiving thin-set flooring shall conform to the following ACI F-number requirements: URS FOR EQM SECTION 03 30 53 Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Specified Overall Values FF35/FL25 minimum [FF_____/FL_____] Minimum Local Values FF25/FL17 minimum [FF_____/FL_____] 3.3.3.3 Measurement of Floor Tolerances Test floor slabs within 24 hours of the final troweling. Submit test results to Contracting Officer within 12 hours after collecting data. Floor flatness inspector mustl provide a tolerance report which includes: a. Name of Project b. Name of Contractor c. Date of Data Collection d. Date of Tolerance Report e. A Key Plan Showing Location of Data Collected f. Results Required by ASTM E1155M ASTM E1155 [Expansion and Contraction Joints ************************************************************************** NOTES: Refer to ACI 224.3R for guidance on expansion joints. The depth of contraction joints must be 1/4 to 1/3 of the thickness of the slab. The maximum spacing (in mm) (in feet) between adjacent joints shall be 30 times the concrete thickness (in mm) (in feet) for slabs exposed to the environment. ************************************************************************** Make expansion and contraction joints in accordance with the details shown or as otherwise specified. Provide 1/2 inch thick transverse expansion joints where new work abuts an existing concrete. Provide expansion joints at a maximum spacing of 30 feet on center in sidewalks [and at a maximum spacing of [_____] feet in slabs], unless otherwise indicated. Provide contraction joints at a maximum spacing of [6] [_____] linear feet in sidewalks [and at a maximum spacing of [_____] feet in slabs], unless otherwise indicated. Cut contraction joints at a minimum of [1] [_____] inch(es) deep with a jointing tool after the surface has been finished. ]3.4 CURING AND PROTECTION Cure and protect in accordance with ACI 301, Section 5. 3.5 FORM WORK Provide form work in accordance with ACI 301, Section 2 and Section 5. URS FOR EQM SECTION 03 30 53 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.5.1 TYMX989345A FA3002-09-D-0002 TG02 Removal of Forms Remove forms in accordance with ACI 301, Section 2. 3.6 STEEL REINFORCING Reinforcement must be free from loose, flaky rust and scale, and free from oil, grease, or other coating which might destroy or reduce the reinforcement's bond with the concrete. 3.6.1 Fabrication Shop fabricate steel reinforcement in accordance with ACI 318 and ACI SP-66. Provide shop details and bending in accordance with ACI 318 and ACI SP-66. 3.6.2 Splicing Perform splices in accordance with ACI 318 and ACI SP-66. 3.6.3 Supports Secure reinforcement in place by the use of metal or concrete supports, spacers, or ties. 3.7 EMBEDDED ITEMS Before placing concrete, take care to determine that all embedded items are firmly and securely fastened in place. Provide embedded items free of oil and other foreign matter, such as loose coatings of rust, paint and scale. Embedding of wood in concrete is permitted only when specifically authorized or directed. CHEMICAL FLOOR HARDENER ************************************************************************** NOTE: Clearly indicate slab surfaces requiring a chemical hardener. Such treatment is suitable for surfaces of concrete floors in equipment rooms and on other floor surfaces that are subject to light foot traffic only and will not be covered with resilient flooring, paint, or other finish coating. ************************************************************************** Apply Chemical Floor Hardener where indicated, after curing and drying concrete surface. Dilute liquid hardener with water and apply in three coats. First coat is one-third strength, second coat one-half strength, and third coat two-thirds strength. Apply each coat evenly and allow it to dry 24 hours before applying next coat. Apply proprietary chemical hardeners in accordance with manufacturer's printed directions. 3.8 TESTING AND INSPECTING Report the results of all tests and inspections conducted at the project site informally at the end of each shift. Submit written reports weekly. Deliver within three days after the end of each weekly reporting period. Refer to QUALITY CONTROL requirements in the Request for Proposal (RFP). URS FOR EQM SECTION 03 30 53 Page 17 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.8.1 TYMX989345A FA3002-09-D-0002 TG02 Field Testing Technicians The individuals who sample and test concrete must have demonstrated a knowledge and ability to perform the necessary test procedures equivalent to the ACI minimum guidelines for certification of Concrete Field Testing Technicians, Grade I. 3.8.2 Preparations for Placing Inspect foundation or construction joints, forms, and embedded items in sufficient time prior to each concrete placement to certify that it is ready to receive concrete. 3.8.3 Sampling and Testing a. ProvObtain samples and test concrete for quality control during placement. Sample fresh concrete for testing in accordance with ASTM C172/C172M. Make six test cylinders. b. Test concrete for compressive strength at 7 and 28 days for each design mix and for every 100 cubic yards of concrete. Test two cylinders at 7 days; two cylinders at 28 days; and hold two cylinders in reserve. Conform test specimens to ASTM C31/C31M. Perform compressive strength testing conforming to ASTM C39/C39M. c. Test slump at the [plant] [site of discharge] for each design mix in accordance with ASTM C143/C143M. Check slump [once] [twice] during each shift that concrete is produced [for each strength of concrete required]. d. Test air content for air-entrained concrete in accordance with ASTM C231/C231M. Test concrete using lightweight or extremely porous aggregates in accordance with ASTM C173/C173M. Check air content at least [once] [twice] during each shift that concrete is placed [for each strength of concrete required]. e. Determine temperature of concrete at time of placement in accordance with ASTM C1064/C1064M. Check concrete temperature at least [once] [ twice] during each shift that concrete is placed [for each strength of concrete required]. 3.8.4 3.8.4.1 Action Required Placing Do not begin placement until the availability of an adequate number of acceptable vibrators, which are in working order and have competent operators, has been verified. Discontinue placing if any lift is inadequately consolidated. 3.8.4.2 Air Content Whenever an air content test result is outside the specification limits, adjust the dosage of the air-entrainment admixture prior to delivery of concrete to forms. 3.8.4.3 Slump Whenever a slump test result is outside the specification limits, adjust URS FOR EQM SECTION 03 30 53 Page 18 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the batch weights of water and fine aggregate prior to delivery of concrete to the forms. Make the adjustments so that the water-cementitious material ratio does not exceed that specified in the submitted concrete mixture proportion and the required concrete strength is still met. -- End of Section -- URS FOR EQM SECTION 03 30 53 Page 19 65% - 01/23/2015 This Page Left Intentionally Blank REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-03 40 00.00 10 (August 2006) --------------------------------Preparing Activity: USACE Superseding UFGS-03 40 00.00 10 (July 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 03 40 00.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE CONSTRUCTION ************************************************************************** NOTE: This guide specification covers the requirements for precast, non-prestressed concrete products used for below grade construction (Sewage Systems, Subdrainage Systems, Storm Drainage Systems, Utility and Communications Structures, etc.. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 1.1 GENERAL REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update URS FOR EQM SECTION 03 40 00.00 10 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI) ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete ACI 211.2 (1998; R 2004) Standard Practice for Selecting Proportions for Structural Lightweight Concrete ACI 305R (2010) Guide to Hot Weather Concreting ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting ACI 318 (2011; Errata 1 2011; Errata 2 2012; Errata 3-4 2013) Building Code Requirements for Structural Concrete and Commentary AMERICAN CONCRETE PIPE ASSOCIATION (ACPA) ACPA QPC (2005; Ver 3.0) QCast Plant Certification Manual AMERICAN WELDING SOCIETY (AWS) AWS D1.1/D1.1M (2010; Errata 2011) Structural Welding Code - Steel AWS D1.4/D1.4M (2011) Structural Welding Code Reinforcing Steel ASTM INTERNATIONAL (ASTM) ASTM A1064/A1064M (2013) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete ASTM A153/A153M (2009) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware ASTM A36/A36M (2012) Standard Specification for Carbon Structural Steel URS FOR EQM SECTION 03 40 00.00 10 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM A615/A615M (2014) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement ASTM A706/A706M (2014) Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement ASTM A767/A767M (2009) Standard Specification for Zinc-Coated (Galvanized) Steel Bars for Concrete Reinforcement ASTM A775/A775M (2007b; R2014) Standard Specification for Epoxy-Coated Steel Reinforcing Bars ASTM A884/A884M (2014) Standard Specification for Epoxy-Coated Steel Wire and Welded Wire Reinforcement ASTM C1064/C1064M (2011) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete ASTM C1107/C1107M (2014) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink) ASTM C1240 (2014) Standard Specification for Silica Fume Used in Cementitious Mixtures ASTM C138/C138M (2013a) Standard Test Method for Density ("Unit Weight"), Yield, and Air Content (Gravimetric) of Concrete ASTM C143/C143M (2012) Standard Test Method for Slump of Hydraulic-Cement Concrete ASTM C1478 (2008; R 2013) Standard Specification for Storm Drain Resilient Connectors Between Reinforced Concrete Storm Sewer Structures, Pipes and Laterals ASTM C150/C150M (2012) Standard Specification for Portland Cement ASTM C171 (2007) Standard Specification for Sheet Materials for Curing Concrete ASTM C173/C173M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method ASTM C192/C192M (2013a) Standard Practice for Making and Curing Concrete Test Specimens in the Laboratory ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method URS FOR EQM SECTION 03 40 00.00 10 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM C260/C260M (2010a) Standard Specification for Air-Entraining Admixtures for Concrete ASTM C309 (2011) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete ASTM C31/C31M (2012) Standard Practice for Making and Curing Concrete Test Specimens in the Field ASTM C33/C33M (2013) Standard Specification for Concrete Aggregates ASTM C330/C330M (2014) Standard Specification for Lightweight Aggregates for Structural Concrete ASTM C39/C39M (2014a) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens ASTM C443 (2011) Standard Specification for Joints for Concrete Pipe and Manholes, Using Rubber Gaskets ASTM C494/C494M (2013) Standard Specification for Chemical Admixtures for Concrete ASTM C595/C595M (2014) Standard Specification for Blended Hydraulic Cements ASTM C618 (2012a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete ASTM C877 (2008) External Sealing Bands for Concrete Pipe, Manholes, and Precast Box Sections ASTM C891 (2011) Installation of Underground Precast Concrete Utility Structures ASTM C923 (2008; R 2013) Standard Specification for Resilient Connectors Between Reinforced Concrete Manhole Structures, Pipes and Laterals ASTM C989/C989M (2013) Standard Specification for Slag Cement for Use in Concrete and Mortars ASTM C990 (2009; R 2014) Standard Specification for Joints for Concrete Pipe, Manholes and Precast Box Sections Using Preformed Flexible Joint Sealants CSA GROUP (CSA) CSA A23.4 URS FOR EQM (2009; R 2014) Precast Concrete Materials and Construction SECTION 03 40 00.00 10 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NATIONAL PRECAST CONCRETE ASSOCIATION (NPCA) NPCA QC Manual 1.2 (2012) Quality Control Manual for Precast and Prestressed Concrete Plants SYSTEM DESCRIPTION Furnish precast concrete units designed and fabricated by an experienced and acceptable precast concrete manufacturer who has been, for at least 3 years, regularly and continuously engaged in the manufacture of precast concrete work similar to that indicated on the drawings. Coordinate precast work with the work of other trades. 1.2.1 Standard Precast Units Design standard precast concrete units to withstand indicated design load conditions in accordance with applicable industry design standards [ACI 318, ASTM, ACPA 01-102, Chapter 7-Design for Sulfide Control]. Design shall also consider stresses induced during handling, shipping and installation as to avoid product cracking or other handling damage. Indicate design loads for precast concrete units on the shop drawings. Submit drawings for standard precast concrete units furnished by the precast concrete producer for approval by the Contracting Officer. These drawings shall demonstrate that the applicable industry design standards have been met. Include installation and construction information on shop drawings. Include details of steel reinforcement size and placement as well as supporting design calculations, if appropriate. Produce precast concrete units in accordance with the approved drawings. Submit cut sheets, for standard precast concrete units, showing conformance to project drawings and requirements, and to applicable industry design standards listed in this specification. 1.2.2 Custom-Made Precast Units Submit design calculations for custom-made precast units, prepared and sealed by a registered professional engineer, for approval prior to fabrication. Include in the calculations the analysis of units for lifting stresses and the sizing of lifting devices. Submit drawings furnished by the precast concrete producer for approval by the Contracting Officer. Show on these drawings complete design, installation, and construction information in such detail as to enable the Contracting Officer to determine the adequacy of the proposed units for the intended purpose. Include details of steel reinforcement size and placement as well as supporting design calculations, if appropriate. Produce precast concrete units in accordance with the approved drawings. 1.2.3 Proprietary Precast Units Products manufactured under franchise arrangements shall conform to all the requirements specified by the franchiser. Items not included in the franchise specification, but included in this specification, shall conform to the requirements in this specification. Submit standard plans or informative literature, for proprietary precast concrete units. Make available supporting calculations and design details upon request. Provide sufficient information as to demonstrate that such products will perform the intended task. URS FOR EQM SECTION 03 40 00.00 10 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.2.4 TYMX989345A FA3002-09-D-0002 TG02 Joints and Sealants Provide joints and sealants between adjacent units of the type and configuration indicated on shop drawings meeting specified design and performance requirements. 1.2.5 1.2.5.1 Concrete Mix Design Concrete Mix Proportions Base selection of proportions for concrete on the methodology presented in ACI 211.1 for normal weight concrete and ACI 211.2 for lightweight concrete. Develop the concrete proportions using the same type and brand of cement, the same type and brand of pozzolan, the same type and gradation of aggregates, and the same type and brand of admixture that will be used in the manufacture of precast concrete units for the project. Do not use calcium chloride in precast concrete containing reinforcing steel or other embedded metal items. At a minimum of thirty days prior to precast concrete unit manufacturing, the precast concrete producer will submit a mix design and proportions for each strength and type of concrete that will be used. Furnish a complete list of materials, including quantity, type, brand and applicable data sheets for all mix design constituents as well as applicable reference specifications. The use of self-consolidating concrete is permitted, provided that mix design proportions and constituents meet the requirements of this specification. 1.2.5.2 Concrete Strength Provide precast concrete units with a 28-day compressive strength (f'c) of 5000[_____] psi. 1.2.5.3 Water-to-Cement Ratio Furnish concrete, that will be exposed to freezing and thawing, containing entrained air and with water-cement ratios of 0.45 or less. Furnish concrete which will not be exposed to freezing, but which is required to be watertight, with a water-cement ratio of 0.48 or less if the concrete is exposed to fresh water, or 0.45 or less if exposed to brackish water or sea water. Furnish reinforced concrete exposed to deicer salts, brackish water or seawater with a water-cement ratio of 0.40 or less for corrosion protection. 1.2.5.4 Air Content The air content of concrete that will be exposed to freezing conditions shall be within the limits given below. AIR CONTENT PERCENT NOMINAL MAXIMUM AGGREGATE SIZE 3/8 inch SEVERE EXPOSURE 6.0 to 9.0 MODERATE EXPOSURE 4.5 to 7.5 1/2 inch 5.5 to 8.5 4.0 to 7.0 3/4 inch 4.5 to 7.5 3.5 to 6.5 1.0 inch 4.5 to 7.5 3.0 to 6.0 URS FOR EQM SECTION 03 40 00.00 10 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 AIR CONTENT PERCENT NOMINAL MAXIMUM AGGREGATE SIZE 1.5 inch SEVERE EXPOSURE 4.5 to 7.0 MODERATE EXPOSURE 3.0 to 6.0 Note: For specified compressive strengths greater than 5000 psi, air content may be reduced 1 percent Corrosion Control for Sanitary Sewer Systems Follow design recommendations outlined in Chapter 7 of ACPA 01-102 or the ACPA 01-110 when hydrogen sulfide is indicated as a potential problem. 1.3 SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** All submittals are the responsibility of the precast concrete producer. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.] [information only. When used, a designation following the "G" URS FOR EQM SECTION 03 40 00.00 10 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29SUSTAINABILITY REQUIREMENTS. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-01 Preconstruction Submittals Quality Control Procedures SD-02 Shop Drawings Standard Precast Units[; G][; G, [_____]] Custom-Made Precast Units[; G][; G, [_____]] SD-03 Product Data Standard Precast Units Proprietary Precast Units Embedded Items Accessories SD-05 Design Data Design Calculations Concrete Mix Proportions SD-06 Test Reports Test Reports SD-07 Certificates Quality Control Procedures 1.4 QUALITY ASSURANCE Demonstrate adherence to the standards set forth in NPCA QC Manual and/or ACPA QPC. Meet requirements written in the subparagraphs below. 1.4.1 NPCA and ACPA Plant Certification ************************************************************************** NOTE: The use of this paragraph may limit competition. Verify the availability of NPCA and ACPA certified precasters in the bidding area. ************************************************************************** The precast concrete producer shall be certified by the National Precast Concrete Association's and/or the American Concrete Pipe Association's Plant Certification Program prior to and during production of the products for this project. 1.4.2 1.4.2.1 Qualifications, Quality Control and Inspection Qualifications Select a precast concrete producer that has been in the business of producing precast concrete units similar to those specified for a minimum URS FOR EQM SECTION 03 40 00.00 10 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 of 3 years. The precast concrete producer shall maintain a permanent quality control department or retain an independent testing agency on a continuing basis. 1.4.2.2 Quality Control Procedures Submit quality control procedures established by the precast manufacturer in accordance with NPCA QC Manual and/or ACPA QPC. Show that the following QC tests are performed as required and in accordance with the ASTM standards indicated. a. Slump: Perform a slump test for each 150 cu yd of concrete produced, or once a day, whichever comes first. Perform slump tests in accordance with ASTM C143/C143M. b. Temperature: Measure the temperature of fresh concrete when slump or air content tests are made and when compressive test specimens are made in accordance with ASTM C1064/C1064M. c. Compressive Strength: Make at least four compressive strength specimens for each 150 cubic yards of concrete of each mix in accordance with the following Standards: ASTM C31/C31M, ASTM C192/C192M, ASTM C39/C39M. d. Air Content: Perform tests for air content on air-entrained, wet-cast concrete for each 150 cu yd of concrete, but not less often than once each day when air-entrained concrete is used. Determine the air content in accordance with either ASTM C231/C231M or ASTM C173/C173M for normal weight aggregates and ASTM C173/C173M for lightweight aggregates. e. Unit Weight: Perform tests for unit weight a minimum of once per week to verify the yield of batch mixes. Perform unit weight tests for each 100 cu yd of lightweight concrete in accordance with ASTM C138/C138M. 1.4.2.3 Inspection The Contracting Officer may place an inspector in the plant when the units covered by this specification are being manufactured. The burden of payment for plant inspection will be clearly detailed in the specification. The precast concrete producer shall give notice 14 days prior to the time the units will be available for plant inspection. Neither the exercise nor waiver of inspection at the plant will affect the Government's right to enforce contractual provisions after units are transported or erected. 1.4.2.4 Test Reports Submit the following as specified in paragraph SUBMITTALS: 1.4.2.4.1 Material Certifications and/or Laboratory Test Reports Include mill tests and all other test data, for portland cement, blended cement, pozzolans, ground granulated blast furnace slag, silica fume, aggregate, admixtures, and curing compound proposed for use on this project. 1.4.2.4.2 Mix Test Reports showing that the mix has been successfully tested to produce concrete with the properties specified and will be suitable for the job URS FOR EQM SECTION 03 40 00.00 10 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 conditions. Such tests may include compressive strength, flexural strength, plastic or hardened air content, freeze thaw durability, abrasion and absorption. Clearly detail in the specifications special tests for precast concrete or cast-in items. 1.4.2.4.3 Self-Consolidating Concrete icient documentation, when the use of self-consolidating concrete (SCC) is proposed, showing a minimum of 30-days production track records demonstrating that SCC is appropriate for casting of the product. 1.4.2.4.4 In-Plant QA/QC Inspection Reports Upon the request of the Contracting Officer. 1.5 1.5.1 DELIVERY, STORAGE, AND HANDLING Delivery Deliver precast units to the site in accordance with the delivery schedule to avoid excessive build-up of units in storage at the site. Upon delivery to the jobsite, all precast concrete units will be inspected by the Contracting Officer for quality and final acceptance. 1.5.2 Storage Store units off the ground or in a manner that will minimize potential damage. 1.5.3 Handling Handle, transport, and store products in a manner to minimize damage. Lifting devices or holes shall be consistent with industry standards. Perform lifting with methods or devices intended for this purpose as indicated on shop drawings. PART 2 2.1 PRODUCTS MATERIALS Except as otherwise specified in the following paragraphs, conform material to Section 03 30 53 00.00 10 MISCELLANEOUS CAST-IN-PLACE CONCRETE and Section 03 20 00.00 10 CONCRETE REINFORCING. 2.1.1 Cement Furnish cement conforming to ASTM C150/C150M, Type I, II, III or V. Furnish blended cements that conform to ASTM C595/C595M. 2.1.2 Silica Fume ************************************************************************** NOTE: Silica fume concrete should be used where low permeability and enhanced durability are necessary and justified by additional cost, such as marine structures or other places where low permeability or severe abrasion resistance is required. Finishing is more difficult than conventional concrete. Proper curing is essential because there is a strong URS FOR EQM SECTION 03 40 00.00 10 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 tendency for severe plastic shrinkage cracking. Assistance from a technical representative from the silica fume supplier may be required during batching, finishing, and curing at start-up of the job, when being used for the first time by the precast concrete producer. A HRWR recommended by the manufacturer of the silica fume should be used. ************************************************************************** Provide silica fume conforming to ASTM C1240. Provide available alkalies conforming to the optimal limit given in Table 2 of ASTM C1240. Silica fume may be furnished as a dry, densified material or as a slurry. When necessary, coordinate the services of a technical representative experienced in mixing, proportioning, placement procedures, and curing of concrete containing silica fume. 2.1.3 Fly Ash and Pozzolans Fly ash is [required] [used] as a supplementary cementitious material (SCM) conforming to ASTM C618, Class F[C or F] with 4 percent maximum loss on ignition and 35 percent maximum cement replacement by weight. 2.1.4 Ground Granulated Blast-Furnace Slag ************************************************************************** NOTE: Ground granulated blast furnace slag and fly ash are materials listed in the EPA's Comprehensive Procurement Guidelines (CPG) http://www.epa.gov/cpg). If the Architect/Engineer determines that use of certain materials meeting the CPG content standards and guidelines would result in inadequate competition, do not meet quality/ performance specifications, are available at an unreasonable price or are not available within a reasonable time frame, the Architect/Engineer may submit written justification and supporting documentation for not procuring designated items containing recovered material. Written justification may be submitted on a Request for Waiver Form to the NASA Environmental Program Manager for approval. The Request for Waiver Form is located in the NASA Procedures and Guidelines (NPG 8830.1) (http://nodis3.gsfc.nasa.gov). ************************************************************************** Ground granulated blast furnace slag is [required] [used] as a supplementary cementitious material conforming to ASTM C989/C989M, Grade [ 120] with between 25 to 50 percent maximum cement replacement by weight. 2.1.5 Water Furnish water potable or free of deleterious substances in amounts harmful to concrete or embedded metals. 2.1.6 2.1.6.1 Aggregates Selection ************************************************************************** URS FOR EQM SECTION 03 40 00.00 10 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NOTE: Select gradation(s) based on job requirements and constraints. The nominal maximum aggregate size may not exceed one-fifth the narrowest dimension between sides of forms, nor three-quarters the minimum clear spacing between individual reinforcing bars or wires. ************************************************************************** Furnish aggregates conforming to ASTM C33/C33M. Provide aggregates not containing any substance, which may be deleteriously reactive with the alkalies in the cement. 2.1.6.2 Aggregates for Lightweight Concrete ASTM C330/C330M 2.1.7 Admixtures 2.1.7.1 Air-Entraining ************************************************************************** NOTE: Air-entraining requirements may be deleted when the project is located in a nonfreezing climate. ************************************************************************** ASTM C260/C260M 2.1.7.2 Accelerating, Retarding, Water Reducing [Moderate to High] ASTM C494/C494M Pigments Non-fading and lime-resistant 2.1.8 Reinforcement 2.1.8.1 Reinforcing Bars ************************************************************************** NOTE: Specify ASTM A706/A706M reinforcing where welding or bending of reinforcement bars is important. In addition, ASTM A775/A775M epoxy coated reinforcing may be specified where extra reinforcement corrosion protection is required. ************************************************************************** a. b. Deformed Billet-steel: ASTM A615/A615M Deformed Low-alloy steel: ASTM A706/A706M 2.1.8.2 a. b. Plain Wire: ASTM A1064/A1064M Deformed Wire: ASTM A1064/A1064M 2.1.8.3 a. b. Reinforcing Wire Welded Wire Fabric Plain Wire: ASTM A1064/A1064M Deformed Wire: ASTM A1064/A1064M URS FOR EQM SECTION 03 40 00.00 10 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.1.8.4 a. b. TYMX989345A FA3002-09-D-0002 TG02 Epoxy Coated Reinforcement Reinforcing Bars: ASTM A775/A775M Wires and Fabric: ASTM A884/A884M 2.1.8.5 Galvanized Reinforcement Provide galvanized reinforcement conforming to ASTM A767/A767M. Synthetic Fiber Reinforcement Synthetic fiber shall be polypropylene with a denier less than 100 and a nominal fiber length of 2 inch. 2.1.9 Inserts and Embedded Metal All items embedded in concrete shall be of the type required for the intended task, and meet the following standards. a. b. c. 2.1.10 Structural Steel Plates, Angles, etc.: ASTM A36/A36M Hot-dipped Galvanized: ASTM A153/A153M Proprietary Items: In accordance with manufacturers published literature Accessories Submit proper installation instructions and relevant product data for items including, but not limited to, sealants, gaskets, connectors, steps, cable racks and other items installed before or after delivery. a. Rubber Gaskets for Circular Concrete Sewer Pipe and Culvert Pipe: ASTM C443. b. External Sealing Bands for Noncircular Sewer, Storm Drain and Culvert Pipe: ASTM C877. c. Preformed Flexible Joint Sealants for Concrete Pipe, Manholes, and Manufactured Box Sections: ASTM C990. d. Elastomeric Joint Sealants: ASTM C920. 2.1.11 Pipe Entry Connectors Pipe entry connectors shall conform to ASTM C923 or ASTM C1478. 2.1.12 Grout ************************************************************************** NOTE: Delete air-entraining requirements when the project is located in a nonfreezing climate. ************************************************************************** Nonshrink Grout shall conform to ASTM C1107/C1107M. Cementitious grout shall be a mixture of portland cement, sand, and water. Proportion one part cement to approximately 2.5 parts sand, with the amount of water based on placement method. [Provide air entrainment for grout exposed to the weather.] URS FOR EQM SECTION 03 40 00.00 10 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS PART 3 3.1 TYMX989345A FA3002-09-D-0002 TG02 EXECUTION FABRICATION AND PLACEMENT Perform fabrication in accordance with NPCA QC Manual and/or ACPA QPC unless specified otherwise. 3.1.1 Forms Use forms, for manufacturing precast concrete products, of the type and design consistent with industry standards and practices. They should be capable of consistently providing uniform products and dimensions. Construct forms so that the forces and vibrations to which the forms will be subjected can cause no product damage. Clean forms of concrete build-up after each use. Apply form release agents according to the manufacturers recommendations and do not allow to build up on the form casting surfaces. 3.1.2 Reinforcement Follow applicable ASTM Standard or ACI 318 for placement and splicing. Fabricate cages of reinforcement either by tying the bars, wires or welded wire fabric into rigid assemblies or by welding, where permissible, in accordance with AWS D1.4/D1.4M. Position reinforcing as specified by the design and so that the concrete cover conforms to requirements. The tolerance on concrete cover shall be one-third of that specified but not more than 1/2 inch. Provide concrete cover not less than 1/2 inch. Take positive means to assure that the reinforcement does not move significantly during the casting operations. 3.1.3 Embedded Items Position embedded items at locations specified in the design documents. Perform welding in accordance with AWS D1.1/D1.1M when necessary. Hold rigidly in place inserts, plates, weldments, lifting devices and other items to be imbedded in precast concrete products so that they do not move significantly during casting operations. Submit product data sheets and proper installation instruction for anchors, lifting inserts and other devices. Clearly indicate the products dimensions and safe working load. Synthetic Fiber Reinforced Concrete ************************************************************************** NOTE: Synthetic fiber reinforcement may be used in concrete as an aid in preventing plastic or shrinkage cracking in placements susceptible to this condition. Fiber reinforcement will not be used as a substitute for wire mesh and where service temperature may exceed 150 degrees C (300 degrees F). Concentrations above 0.1 percent by volume are not cost-effective. ************************************************************************** Add fiber reinforcement to the concrete mix in accordance with the applicable sections of ASTM C1116/C1116M and the recommendations of the manufacturer, and in an amount of [0.1] [_____] percent by volume. URS FOR EQM SECTION 03 40 00.00 10 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.2 TYMX989345A FA3002-09-D-0002 TG02 CONCRETE 3.2.1 Concrete Mixing Mixing operations shall produce batch-to-batch uniformity of strength, consistency, and appearance. 3.2.2 Concrete Placing Deposit concrete into forms as near to its final location as practical. Keep the free fall of the concrete to a minimum. Consolidate concrete in such a manner that segregation of the concrete is minimized and honeycombed areas are kept to a minimum. Use vibrators to consolidate concrete with frequencies and amplitudes sufficient to produce well consolidated concrete. 3.2.2.1 Cold Weather Concreting Perform cold weather concreting in accordance with ACI 306.1. a. Provide adequate equipment for heating concrete materials and protecting concrete during freezing or near-freezing weather. b. Free from frost all concrete materials and all reinforcement, forms, fillers, and ground with which concrete is to come in contact. c. Do not use frozen materials or materials containing ice. d. In cold weather the temperature of concrete at the time of placing shall not be below 45 degrees F. Discard concrete that freezes before its compressive strength reaches 500 psi. 3.2.2.2 Hot Weather Concreting Recommendations for hot weather concreting are given in detail in ACI 305R. During hot weather, give proper attention to constituents, production methods, handling, placing, protection, and curing to prevent excessive concrete temperatures or water evaporation that could impair required strength or serviceability of the member or structure. The temperature of concrete at the time of placing shall not exceed 90 degrees F. 3.2.3 Concrete Curing ************************************************************************** NOTE: Due to the immediacy of form removal, dry-cast products have a tendency to undergo undesirable accelerated drying. Consequently, early curing periods are most critical to ensure protection from extreme temperatures and dryness. Dry-cast products must be protected from drafts to prevent cracking. ************************************************************************** Commence curing immediately following the initial set and completion of surface finishing. 3.2.3.1 Curing by Moisture Retention Prevent moisture evaporation from exposed surfaces until adequate strength for stripping is reached by one of the following methods: URS FOR EQM SECTION 03 40 00.00 10 Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 a. Cover with polyethylene sheets a minimum of 6 mils thick in accordance with ASTM C171. b. Cover with burlap or other absorptive material and keep continually moist. c. Use of a membrane-curing compound applied at a rate not to exceed 200 square ft/gallon, or in accordance with manufacturers' recommendations according to ASTM C309. 3.2.3.2 Curing with Heat and Moisture ************************************************************************** NOTE: Cure as above surfaces that will be exposed to weather during service, a minimum of 3 days. Forms should be considered effective in preventing evaporation from the contact surfaces. If air temperature is below 50°F the curing period must be extended. ************************************************************************** Do not subject concrete to steam or hot air until after the concrete has attained its initial set. Apply steam, if used, within a suitable enclosure, which permits free circulation of the steam in accordance with CSA A23.4. If hot air is used for curing, take precautions to prevent moisture loss from the concrete. The temperature of the concrete shall not be permitted to exceed 150 degrees F. These requirements do not apply to products cured with steam under pressure in an autoclave. 3.2.4 Surface Finish Finish unformed surfaces of wet-cast precast concrete products as specified. If no finishing procedure is specified, finish such surfaces using a strike-off to level the concrete with the top of the form. 3.2.4.1 Formed Non-Architectural Surfaces Cast surfaces against approved forms following industry practices in cleaning forms, designing concrete mixes, placing and curing concrete. Normal color variations, form joint marks, small surface holes caused by air bubbles, and minor chips and spalls will be accepted but no major imperfections, honeycombs or other major defects will be permitted. 3.2.4.2 Unformed Surfaces Finish unformed surfaces with a vibrating screed, or by hand with a float. Normal color variations, minor indentations, minor chips and spalls will be accepted but no major imperfections, honeycombs, or other major defects shall be permitted. 3.2.4.3 Special Finishes Troweled, broom or other finishes shall be according to the requirements of project documents and performed in accordance with industry standards or supplier specifications. Submit finishes for approval when required by the project documents. The sample finishes shall be approved prior to the start of production. URS FOR EQM SECTION 03 40 00.00 10 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.2.5 TYMX989345A FA3002-09-D-0002 TG02 Stripping Products from Forms Do not remove products from the forms until the concrete reaches the compressive strength for stripping required by the design. If no such requirement exists, products may be removed from the forms after the final set of concrete provided that stripping damage is minimal. 3.2.6 Patching and Repair No repair is required to formed surfaces that are relatively free of air voids and honeycombed areas, unless the surfaces are required by the design to be finished. 3.2.6.1 Repairing Minor Defects Defects that will not impair the functional use or expected life of a precast concrete product may be repaired by any method that does not impair the product. 3.2.6.2 Repairing Honeycombed Areas When honeycombed areas are to be repaired, remove all loose material and cut back the areas into essentially horizontal or vertical planes to a depth at which coarse aggregate particles break under chipping rather than being dislodged. Use proprietary repair materials in accordance with the manufacturer's instructions. If a proprietary repair material is not used, saturate the area with water. Immediately prior to repair, the area should be damp, but free of excess water. Apply a cement-sand grout or an approved bonding agent to the chipped surfaces, followed immediately by consolidating an appropriate repair material into the cavity. 3.2.6.3 Repairing Major Defects Evaluate, by qualified personnel, defects in precast concrete products which impair the functional use or the expected life of products to determine if repairs are feasible and, if so, to establish the repair procedure. 3.2.7 Shipping Products Do not ship products until they are at least 5 days old, unless it can be shown that the concrete strength has reached at least 75 percent of the specified 28-day strength, or that damage will not result, impairing the performance of the product. 3.3 3.3.1 INSTALLATION Site Access It is the Contractor's responsibility to provide adequate access to the site to facilitate hauling, storage and proper handling of the precast concrete products. 3.3.2 General Requirements a. Install precast concrete products to the lines and grades shown in the contract documents or otherwise specified. b. Lift products by suitable lifting devices at points provided by the URS FOR EQM SECTION 03 40 00.00 10 Page 17 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 precast concrete producer. c. Install products in accordance with the precast concrete producer's instructions. In the absence of such instructions, install underground utility structures in accordance with ASTM C891. Install pipe and manhole sections in accordance with the procedures outlined by the American Concrete Pipe Association. d. Field modifications to the product will relieve the precast producer of liability even if such modifications result in the failure of the product. 3.3.3 Water Tightness Where water tightness is a necessary performance characteristic of the precast concrete product's end use, watertight joints, connectors and inserts should be used to ensure the integrity of the entire system. FIELD QUALITY CONTROL ************************************************************************** NOTE: Manholes should be tested prior to backfilling to verify the integrity of the installed product. Testing prior to backfilling facilitates quick and easy repair when required. When vacuum testing a backfilled manhole, appropriate adjustments must be made to the testing procedure to account for site conditions such as high water tables as to avoid over loading boots and connectors. Prior to vacuum testing, make calculations to ensure that connectors and boots are not loaded past the design limit as indicated in ASTM C923. ************************************************************************** 3.4 Site Tests When water tightness testing is required for an underground product, use one of the following methods: 3.5 Vacuum Testing Prior to backfill vacuum test system according to ASTM C1244. Water Testing Perform water testing according to the contract documents and precast concrete producer's recommendations. -- End of Section -- URS FOR EQM SECTION 03 40 00.00 10 Page 18 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-31 00 00 (August 2008) --------------------------Preparing Activity: USACE Superseding UFGS-31 00 00 (July 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 31 00 00 EARTHWORK ************************************************************************** NOTE: This guide specification covers the requirements for earthwork activities for buildings, utilities, roadways, railroads, and airfields. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: Consult with a soils engineer while editing this section to determine specific requirements for each job. The following information will be indicated on the project drawings: 1. Surface elevations, existing and new; 2. Location of underground obstructions and existing utilities; 3. Location and record of soil borings and test pits. Include ground water observations and topsoil thickness encountered in boring, soil classifications, and properties such as moisture URS FOR EQM SECTION 31 00 00 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 content and Atterberg limit determinations; 4. Location of borrow and disposal area if located on Government property; 5. Clearing stripping and grubbing limits, if different from clearing limits; 6. Areas to be seeded; 7. Hydrological data where available; 8. Shoring and sheeting required (trench protection is specified in Corps of Engineers Manual EM 385-1-1); and 9. 10. Pipe trench excavation details. Location and limits of hard material (rocks); 11. Details of special construction such as under railroad and highways right-of-way requirements for jacking and boring; 12. Details of sewage absorption trenches, absorption pits, and subsurface drains. ************************************************************************** 1.1 MEASUREMENT PROCEDURES ************************************************************************** NOTE: These paragraphs will be deleted when lump-sum payment for work under this section is desired and when the work covered by this section is included in one lump-sum contract price for the entire work covered by the Invitation for Bids. ************************************************************************** 1.1.1 Excavation The unit of measurement for excavation and borrow will be the cubic yard, computed by the average end area method from cross sections taken before and after the excavation and borrow operations, including the excavation for ditches, gutters, and channel changes, when the material is acceptably utilized or disposed of as herein specified. The measurements will include authorized excavation of rock (except for piping trenches that is covered below), authorized excavation of unsatisfactory subgrade soil, and the volume of loose, scattered rocks and boulders collected within the limits of the work; allowance will be made on the same basis for selected backfill ordered as replacement. The measurement will not include the volume of subgrade material or other material that is scarified or plowed and reused in-place, and will not include the volume excavated without authorization or the volume of any material used for purposes other than directed. The volume of overburden stripped from borrow pits and the volume of excavation for ditches to drain borrow pits, unless used as borrow material, will not be measured for payment. The measurement will not include the volume of any excavation performed prior to the taking of elevations and measurements of the undisturbed grade. URS FOR EQM SECTION 31 00 00 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.1.2 TYMX989345A FA3002-09-D-0002 TG02 Piping Trench Excavation ************************************************************************** NOTE: This paragraph will be coordinated with the payment paragraphs of appropriate contract sections to ensure that there are no dual payments or omission of payment for trench excavation. There should be separate payment items established for trench excavation for each different size of pipe in the contract. Payment for trench excavation for heat-distribution system and for underground electrical-distribution system may be excluded for payment from this paragraph, and included in payment under the appropriate utility section, when the work is of such a nature and extent and so clearly indicated that the excavation quantities involved can be estimated with reasonable accuracy. ************************************************************************** Measure trench excavation by the number of linear feet along the centerline of the trench and excavate to the depths and widths specified for the particular size of pipe. Replace unstable trench bottoms with a selected granular material. Include the additional width at manholes and similar structures, the furnishing, placing and removal of sheeting and bracing, pumping and bailing, and all incidentals necessary to complete the work required by this section. Rock Excavation for Trenches ************************************************************************** NOTE: Delete this paragraph when not required in the project. ************************************************************************** Measure and pay for rock excavation by the number of cubic yards of acceptably excavated rock material. Measure the material in place, but base volume on a maximum 30 inches width for pipes 12 inches in diameter or less, and a maximum width of 16 inches greater than the outside diameter of the pipe for pipes over 12 inches in diameter. Provide the measurement to include all authorized overdepth rock excavation as determined by the Contracting Officer. For manholes and other appurtenances, compute volumes of rock excavation on the basis of 1 foot outside of the wall lines of the structures. 1.1.2 Topsoil Requirements Separate excavation, hauling, and spreading or piling of topsoil and related miscellaneous operations will be considered subsidiary obligations of the Contractor, covered under the contract unit price for excavation. Overhaul Requirements Allow the unit of measurement for overhaul to be the station-yard. The overhaul distance will be the distance in stations between the center of volume of the overhaul material in its original position and the center of volume after placing, minus the free-haul distance in stations. The haul distance will be measured along the shortest route determined by the Contracting Officer as feasible and satisfactory. Do no measure or waste unsatisfactory materials for overhaul where the length of haul for borrow URS FOR EQM SECTION 31 00 00 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 is within the free-haul limits. 1.1.3 Select Granular Material Measure select granular material in place as the actual cubic yards replacing wet or unstable material in trench bottoms [within the limits shown] [in authorized overdepth areas]. Provide unit prices which include furnishing and placing the granular material, excavation and disposal of unsatisfactory material, and additional requirements for sheeting and bracing, pumping, bailing, cleaning, and other incidentals necessary to complete the work. 1.2 PAYMENT PROCEDURES ************************************************************************** NOTE: When lump-sum payment for work under this section is desired, these paragraphs will be revised accordingly. These paragraphs will be deleted when the work covered by this section is included in one lump-sum contract price for the entire work covered by the Invitation for Bids. Payment for overhaul will be separate from excavation and borrow. ************************************************************************** Payment will constitute full compensation for all labor, equipment, tools, supplies, and incidentals necessary to complete the work. Classified Excavation Classified excavation will be paid for at the contract unit prices per cubic yard for common or rock excavation. 1.2.1 Piping Trench Excavation Payment for trench excavation will constitute full payment for excavation and backfilling, [including specified overdepth] except in rock or unstable trench bottoms. Rock Excavation for Trenches ************************************************************************** NOTE: Delete this paragraph when not required in the project. ************************************************************************** Payment for rock excavation will be made in addition to the price bid for the trench excavation, and will include all necessary drilling and blasting and all incidentals necessary to excavate and dispose of the rock. Select granular material, used as backfill replacing rock excavation, will not be paid for separately, but will be included in the unit price for rock excavation. 1.2.1 Unclassified Excavation Unclassified excavation will be paid for at the contract unit price per cubic yard for unclassified excavation. URS FOR EQM SECTION 31 00 00 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Classified Borrow Classified borrow will be paid for at the contract unit prices per cubic yard for common or rock borrow. 1.2.2 Unclassified Borrow Unclassified borrow will be paid for at the contract unit price per cubic yard for unclassified borrow. 1.2.3 Authorized Overhaul The number of station-yards of overhaul to be paid for will be the product of number of cubic yards of overhaul material measured in the original position, multiplied by the overhaul distance measured in stations of 100 feet and will be paid for at the contract unit price per station-yard for overhaul in excess of the free-haul limit as designated in paragraph DEFINITIONS. Sheeting and Bracing ************************************************************************** NOTE: Delete subparagraphs or items not required in the project. ************************************************************************** Sheeting and bracing, when shown or authorized by the Contracting Officer to be left in place, will be paid for as follows: [_____]. 1.2.4 Timber Sheeting Timber sheeting will be paid for as the number of board feet of lumber below finish grade measured in place prior to backfilling. Include in the measurement sheeting wasted when cut off between the finished grade and 1 foot below the finished grade. Steel Sheeting and Soldier Piles ************************************************************************** NOTE: The blank will be filled with an appropriate number not greater than 1 meter (3 feet). However, if the quantities of sheeting involved are anticipated to be substantial, and since the cut off steel can be sold by the Contractor as scrap, the whole part in brackets can be deleted and no payment provided for wasted cut off ends. ************************************************************************** Steel sheeting, soldier piles, and steel bracing will be paid for according to the number of pounds of steel calculated. Calculate the steel by multiplying the measured in-place length in feet below finish grade by the unit weight of the section in pounds per foot. Obtain unit weight of rolled steel sections from recognized steel manuals. [Included in the measurement sheeting wasted when cut off between the finished grade and a distance of up to [_____] feet below the finished grade.] 1.3 CRITERIA FOR BIDDING ************************************************************************** URS FOR EQM SECTION 31 00 00 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NOTE: For most projects, the scope of earthwork can accurately be determined. However, if earthwork is approximately known, a unit price for earth work should be provided in the Bid Schedule. Unit-price items are multiplied by the approximated and stated quantity giving a sum that is then added to the price for the rest of the work. The result is a lump sum bid with automatic provision for payment or credit due to variations in earthwork within 15 percent of that shown and bid upon. Variations exceeding 15 percent of that shown and bid upon will become the subject of negotiations in accordance with FAR 52.212.11, "VARIATION IN ESTIMATED QUANTITY." ************************************************************************** Base bids on the following criteria: a. Surface elevations are as indicated. b. Pipes or other artificial obstructions, except those indicated, will not be encountered. c. [Ground water elevations indicated by the boring log were those existing at the time subsurface investigations were made and do not necessarily represent ground water elevation at the time of construction.] [Ground water elevation is [_____] feet below existing surface elevation.] d. [Ground water elevation is [_____] feet below existing surface elevation.] ed. [Material character is indicated by the boring logs.] ************************************************************************** NOTE: Choose the following option if no boring information is available, or if the boring information is insufficient to permit a bidder to develop an accurate estimate of hard material or rock to be encountered. If hard material or rock is to be encountered, the following option should be modified to include a percent figure or an approximate depth at which hard material or rock will be encountered. ************************************************************************** f. 1.4 [Hard materials [and rock] [will not] [will] be encountered [in [_____] percent of the excavations] [at [_____] feet below existing surface elevations]]. REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, URS FOR EQM SECTION 31 00 00 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) AASHTO T 180 (2010) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop AASHTO T 224 (2010) Standard Method of Test for Correction for Coarse Particles in the Soil Compaction Test ASTM INTERNATIONAL (ASTM) ASTM C136 (2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates ASTM D1140 (2000; R 2006) Amount of Material in Soils Finer than the No. 200 (75-micrometer) Sieve ASTM D1556 (2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method ASTM D1557 (2012) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3) ASTM D2487 (2011) Soils for Engineering Purposes (Unified Soil Classification System) ASTM D422 (1963; R 2007; E 2014; E 2014) Particle-Size Analysis of Soils ASTM D4318 (2010; E 2014) Liquid Limit, Plastic Limit, and Plasticity Index of Soils ASTM D6938 (2010) Standard Test Method for In-Place Density and Water Content of Soil and URS FOR EQM SECTION 31 00 00 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Soil-Aggregate by Nuclear Methods (Shallow Depth) U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA) EPA 600/4-79/020 (1983) Methods for Chemical Analysis of Water and Wastes EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test Methods for Evaluating Solid Waste: Physical/Chemical Methods 1.5 DEFINITIONS ************************************************************************** NOTE: Delete definitions that will not be used in the specification text for a specific project. ************************************************************************** 1.5.1 Satisfactory Materials ************************************************************************** NOTE: Satisfactory material will be defined in accordance with locally available materials, design slopes, etc., and suitable classes, based on the geotechnical report, will be listed in the project specification in accordance with the Unified Soil Classification System, ASTM D2487. Maximum rock size will be determined based on how thick the fill is and how it is going to be accomplished. As a rule of thumb, it should be no larger than 1/2 the allowable lift thickness. Clay material should be checked for expansive characteristics and this section should be edited accordingly. ************************************************************************** Satisfactory materials comprise any materials classified by ASTM D2487 as GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, SP, [SM,] [SW-SM,] [SC,] [SW-SC,] [SP-SM,] [SP-SC,] [CL] [ML,] [CL-ML,] [CH,] [MH]. Satisfactory materials for grading comprise stones less than 8 inches, except for fill material for pavements and railroads which comprise stones less than 3 inches in any dimension. 1.5.2 Unsatisfactory Materials ************************************************************************** NOTE: Unsatisfactory material will be defined in accordance with locally available materials, design slopes, etc., and unsuitable classes will be listed in the project specifications in accordance with ASTM D2487. This paragraph should be edited to delete inapplicable materials. ************************************************************************** Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction; and material classified as satisfactory which contains root and other organic matter or frozen material. Notify the Contracting Officer when URS FOR EQM SECTION 31 00 00 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 encountering any contaminated materials. 1.5.3 Cohesionless and Cohesive Materials ************************************************************************** NOTE: When classification will be necessary during construction, determination of grain size for classification will be specified to be made in conformance with ASTM C117, ASTM C136, and ASTM D422. ************************************************************************** Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesionless only when the fines are nonplastic. Perform testing, required for classifying materials, in accordance with ASTM D4318, ASTM C136, ASTM D422, and ASTM D1140. 1.5.4 Degree of Compaction ************************************************************************** NOTE: ASTM D1557 will be used for maximum density determinations, unless soil borings indicate a gradation that may include coarse material where more than 30 percent is retained on the 19 mm (3/4") sieve; in that case, the Contractor will be required to use AASHTO T 180, Method D and corrected with AASHTO T 224 for the maximum density determinations. The designer should determine if AASHTO T 180 is appropriate for the existing soil gradation. If maximum density cannot be determined by either method, the specification may need to require a test section and the COR to determine the number of compaction coverages and equipment type. ************************************************************************** Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum density. Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, express the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve as a percentage of the maximum density in accordance with AASHTO T 180 and corrected with AASHTO T 224. To maintain the same percentage of coarse material, use the "remove and replace" procedure as described in NOTE 8 of Paragraph 7.2 in AASHTO T 180. Overhaul ************************************************************************** NOTE: This paragraph is to be deleted when the earthwork is to be paid for under a lump sum contract. The blank will be filled with the appropriate number of stations. ************************************************************************** Overhaul is the authorized transportation of satisfactory excavation or borrow materials in excess of the free-haul limit of [_____] stations. URS FOR EQM SECTION 31 00 00 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Overhaul is the product of the quantity of materials hauled beyond the free-haul limit, and the distance such materials are hauled beyond the free-haul limit, expressed in station yards. 1.5.5 Topsoil ************************************************************************** NOTE: Additional requirements such as pH value and necessary soil conditioning, according to applicable provisions of Sections 32 92 19 through 32 92 26, should be inserted in this paragraph. The depth of the topsoil should be given in the text of the specification, preferably in this paragraph. ************************************************************************** Material suitable for topsoils obtained from [offsite areas] [excavations] [areas indicated on the drawings] is defined as: Natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth. Amend topsoil pH range to obtain a pH of 5.5 to 7. 1.5.6 Hard/Unyielding Materials ************************************************************************** NOTE: Stones should generally not exceed 75 mm (3 inches) in diameter. However, pipe manufacturer's criteria, if any, should be used. ************************************************************************** Hard/Unyielding materials comprise weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" with stones greater than 3[_____] inch in any dimension or as defined by the pipe manufacturer, whichever is smaller. These materials usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal. 1.5.7 Rock Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding [1/2] [_____] cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production. 1.5.8 Unstable Material Unstable materials are too wet to properly support the utility pipe, conduit, or appurtenant structure. 1.5.9 Select Granular Material ************************************************************************** NOTE: It is important to specify select material under footings and slabs to minimize settlement and URS FOR EQM SECTION 31 00 00 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 to ensure stability of a structure. Consideration should be made of the sensitivity of the structure to total and/or differential settlements related to the structural design. This is particularly true of add-on structures and structures to be founded partly on fill and partly on natural ground. For crib retaining wall, not more than 10 percent by weight of the fill material should be finer than 75 micrometers (No. 200) sieve. Also, specify coefficient of permeability within the range of 0.01 to 1.0 mm per second (0.002 to 0.20 feet per minute) and soil classification GW, GP, SW and SP. Indicate with cross sections or section details on the contract drawings the limits or extents of any controlled fills or backfills. Specify class of material that is acceptable in the fill or backfill giving preference to any types available at or near the site. Select appropriate values for Atterberg limits and percentage of fines and specify maximum thickness of lifts for compaction. For piping bedding the maximum size of aggregate should be not more than 8 mm per 100 mm (1 inch per foot) of pipe diameter, or 75 mm (3 inches) maximum. Refer to pipe manufacturer's criteria for more stringent requirements, if any, on aggregate size and gradation. If suitable materials for this project are limited to materials classified as GW, GP, SW, or SP, delete the bracketed sentences of this paragraph. Coordinate requirements with a geotechnical engineer. Select fill used for structures should extend a minimum of 1.5 m (5 feet) outside the building foundation lines or other building elements gaining support from the fill. ************************************************************************** 1.5.9.1 General Requirements Select granular material consist of materials classified as [GW,] [GP,] [SW,] [ or SP,] or [_____] by ASTM D2487 where indicated. [The liquid limit of such material must not exceed [35] [_____] percent when tested in accordance with ASTM D4318. The plasticity index must not be greater than [ 12] [_____] percent when tested in accordance with ASTM D4318, and not more than [35] [_____] percent by weight may be finer than No. 200 sieve when tested in accordance with ASTM D1140.] [Provide a minimum coefficient of permeability of [0.002] [_____] feet per minute when tested in accordance with ASTM D2434.] California Bearing Ratio Values ************************************************************************** NOTE: Where California Bearing Ratio values are needed include the following paragraph: ************************************************************************** [Bearing Ratio: At 0.1 inch penetration, provide a bearing ratio of [_____] percent at 95 percent ASTM D1557 maximum density as determined in URS FOR EQM SECTION 31 00 00 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 accordance with ASTM D1883 for a laboratory soaking period of not less than 4 days. [Provide [_____] percent maximum expansion.] [Conform the combined material to the following sieve analysis:]] 1.5.10 Sieve Size Percent Passing by Weight 2-1/2 inches 100 No. 4 40 - 85 No. 10 20 - 80 No. 40 10 - 60 No. 200 5 - 25 Initial Backfill Material Initial backfill consists of select granular material or satisfactory materials free from rocks 3[_____] inches or larger in any dimension or free from rocks of such size as recommended by the pipe manufacturer, whichever is smaller. When the pipe is coated or wrapped for corrosion protection, free the initial backfill material of stones larger than 3 [_____] inches in any dimension or as recommended by the pipe manufacturer, whichever is smaller. 1.5.11 Expansive Soils ************************************************************************** NOTE: Additional laboratory testing and analysis might be needed to better define site specific expansive soils. If expansive soils are anticipated at the construction site, this specification should be edited to ensure proper construction techniques are undertaken per UFC 3-220-01. ************************************************************************** Expansive soils are defined as soils that have a plasticity index equal to or greater than 20[_____] when tested in accordance with ASTM D4318. 1.5.12 Nonfrost Susceptible (NFS) Material ************************************************************************** NOTE: Contract specifications for nonfrost-susceptible fill and backfill will follow the gradation requirements recommended in UFC 3-250-01FA. For fill under critical structures, materials with ML, MH, and CH classification will be specified as unsatisfactory (if at all feasible from an economic or material-availability standpoint). If such materials must be used, the specification will point out the critical nature of the materials and the control difficulties to be anticipated. Organic materials and topsoil having OL, OH, and Pt classification will not be used in fill or backfill. ************************************************************************** Nonfrost susceptible material are a uniformly graded washed sand with a URS FOR EQM SECTION 31 00 00 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 maximum particle size of 3/8[_____] inch and less than 5 percent passing the No. 200 size sieve, and with not more than 3 percent by weight finer than 0.02 mm grain size. Pile Supported Structure As used herein, a structure where both the foundation and floor slab are pile supported. 1.6 SYSTEM DESCRIPTION Subsurface soil boring logs are [shown on the drawings] [appended to the SPECIAL CONTRACT REQUIREMENTS]. The subsoil investigation report and samples of materials taken from subsurface investigations may be examined at [_____]upon request. These data represent the best subsurface information available; however, variations may exist in the subsurface between boring locations. 1.6.1 Classification of Excavation ************************************************************************** NOTE: Inapplicable portions will be deleted. Other classifications of excavation may be utilized as required. ************************************************************************** [No consideration will be given to the nature of the materials, and all excavation will be designated as unclassified excavation.] [Finish the specified excavation on a classified basis, in accordance with the following designations and classifications.] 1.6.1.1 Common Excavation Include common excavation with the satisfactory removal and disposal of all materials not classified as rock excavation. 1.6.1.2 Rock Excavation Submit notification of encountering rock in the project. Include rock excavation with blasting, excavating, grading, disposing of material classified as rock, and the satisfactory removal and disposal of boulders 1/2 cubic yard or more in volume; solid rock; rock material that is in ledges, bedded deposits, and unstratified masses, which cannot be removed without systematic drilling and blasting; firmly cemented conglomerate deposits possessing the characteristics of solid rock impossible to remove without systematic drilling and blasting; and hard materials (see Definitions). Include the removal of any concrete or masonry structures, except pavements, exceeding 1/2 cubic yard in volume that may be encountered in the work in this classification. If at any time during excavation, including excavation from borrow areas, the Contractor encounters material that may be classified as rock excavation, uncover such material and notify the Contracting Officer. Do not proceed with the excavation of this material until the Contracting Officer has classified the materials as common excavation or rock excavation and has taken cross sections as required. Failure on the part of the Contractor to uncover such material, notify the Contracting Officer, and allow ample time for classification and cross sectioning of the undisturbed surface of such material will cause the forfeiture of the Contractor's right of claim to any classification or volume of material to be paid for other than that allowed by the Contracting Officer for the areas of work in which such deposits occur. URS FOR EQM SECTION 31 00 00 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Blasting [Perform blasting in accordance with EM 385-1-1 and in conformance with Federal, State, and local safety regulations. Submit notice 15 days prior to starting work. Submit a Blasting Plan, prepared and sealed by a registered professional engineer that includes calculations for overpressure and debris hazard. Provide blasting mats and use the non-electric blasting caps. Obtain written approval prior to performing any blasting and notify the Contracting Officer 24 hours prior to blasting. Include provisions for storing, handling and transporting explosives as well as for the blasting operations in the plan. The Contractor is responsible for damage caused by blasting operations.] [Blasting will not be permitted.] Dewatering Work Plan ************************************************************************** NOTE: Include this paragraph where water levels will impact excavation operations. ************************************************************************** Submit procedures for accomplishing dewatering work. 1.7 SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. URS FOR EQM SECTION 31 00 00 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.] [information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29SUSTAINABILITY REQUIREMENTS. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-01 Preconstruction Submittals Shoring[; G][; G, [_____]] Dewatering Work Plan[; G][; G, [_____]] Blasting[; G][; G, [_____]] SD-03 Product Data Utilization of Excavated Materials[; G][; G, [_____]] Rock Excavation Opening of any Excavation or Borrow Pit Shoulder Construction SD-06 Test Reports Testing Borrow Site Testing Within 24 hours of conclusion of physical tests, submit 5[_____] copies of test results, including calibration curves and results of calibration tests. SD-07 Certificates Testing PART 2 2.1 PRODUCTS REQUIREMENTS FOR OFFSITE SOILS ************************************************************************** NOTE: Check with regional and local authorities as well as the activity to determine actual requirements of bracketed items; values shown come from the Commonwealth of Virginia. Remove this paragraph if not required by the project. ************************************************************************** Test offsite soils brought in for use as backfill for Total Petroleum Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and full Toxicity Characteristic Leaching Procedure (TCLP) including ignitability, corrosivity and reactivity. Backfill shall contain a maximum of [100] [_____] parts per million (ppm) of total petroleum hydrocarbons URS FOR EQM SECTION 31 00 00 Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 (TPH) and a maximum of [10] [_____] ppm of the sum of Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and shall pass the TCPL test. Determine TPH concentrations by using EPA 600/4-79/020 Method 418.1. Determine BTEX concentrations by using EPA SW-846.3-3 Method 5030/8020. Perform TCLP in accordance with EPA SW-846.3-3 Method 1311. Provide Borrow Site Testing for TPH, BTEX and TCLP from a composite sample of material from the borrow site, with at least one test from each borrow site. Do not bring material onsite until tests have been approved by the Contracting Officer. 2.2 BURIED WARNING AND IDENTIFICATION TAPE ************************************************************************** NOTE: Delete paragraph if tape is not required in the project. The use of a plastic warning tape for identification is mandatory for buried hazardous utilities such as electrical conduit, gas lines, fuel lines, high pressure nitrogen, high pressure water and steam lines, domestic sewage force mains, industrial waste force mains and industrial sewers carrying hazardous, explosive, or toxic waste. Coordinate color codes with other specification sections and conform, if possible, to local practice for identifying buried utilities. ************************************************************************** Provide [polyethylene plastic] [and] [metallic core or metallic-faced, acid- and alkali-resistant, polyethylene plastic] warning tape manufactured specifically for warning and identification of buried utility lines. Provide tape on rolls, 3 inches minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording. Provide permanent color and printing, unaffected by moisture or soil. Warning Tape Color Codes Red Electric Yellow Gas, Oil; Dangerous Materials Orange Telephone and Other Communications Blue Water Systems Green Sewer Systems White Steam Systems Gray Compressed Air 2.2.1 Warning Tape for Metallic Piping Provide acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.003 inch and a minimum strength of 1500 psi lengthwise, and URS FOR EQM SECTION 31 00 00 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 1250 psi crosswise, with a maximum 350 percent elongation. 2.2.2 Detectable Warning Tape for Non-Metallic Piping Provide polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.004 inch, and a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Manufacture tape with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to 3 feet deep. Encase metallic element of the tape in a protective jacket or provide with other means of corrosion protection. 2.3 DETECTION WIRE FOR NON-METALLIC PIPING Insulate a single strand, solid copper detection wire with a minimum of 12 AWG. 2.4 MATERIAL FOR RIP-RAP ************************************************************************** NOTE: Make sure there is no duplication of rip-rap requirements between this and other specification sections. In this paragraph refer to standard specifications for rip-rap if local specifications are satisfactory and available. Delete this paragraph or subparagraphs not required in the project. ************************************************************************** Provide [Bedding material] [Grout] [Filter fabric] and rock conforming to [these requirements] [DOT] [SSS-[_____] State Standard] for construction indicated. 2.4.1 Bedding Material Provide bedding material consisting of sand, gravel, or crushed rock, well graded, [or poorly graded] with a maximum particle size of 2 inches. Compose material of tough, durable particles. Allow fines passing the No. 200 standard sieve with a plasticity index less than six. 2.4.2 Grout Provide durable grout composed of cement, water, an air-entraining admixture, and sand mixed in proportions of one part portland cement to [two] [_____] parts of sand, sufficient water to produce a workable mixture, and an amount of admixture which will entrain sufficient air, as determined by the Contracting Officer. Mix grout in a concrete mixer. Allow a sufficient mixing time to produce a mixture having a consistency permitting gravity flow into the interstices of the rip-rap with limited spading and brooming. 2.4.3 Rock ************************************************************************** NOTE: Adjust weights in brackets to fit application. Take local practice into consideration. ************************************************************************** Provide rock fragments sufficiently durable to ensure permanence in the URS FOR EQM SECTION 31 00 00 Page 17 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 structure and the environment in which it is to be used. Use rock fragments free from cracks, seams, and other defects that would increase the risk of deterioration from natural causes. Provide fragments sized so that no individual fragment exceeds a weight of [150] [_____] pounds and that no more than 10 percent of the mixture, by weight, consists of fragments weighing 2 pounds or less each. Provide rock with a minimum specific gravity of [2.50] [_____]. Do not permit the inclusion of more than trace [1 percent] [_____] quantities of dirt, sand, clay, and rock fines. 2.5 CAPILLARY WATER BARRIER Provide capillary water barrier of clean, poorly graded crushed rock, crushed gravel, or uncrushed gravel placed beneath a building slab with or without a vapor barrier to cut off the capillary flow of pore water to the area immediately below. Conform to ASTM C33/C33M for fine aggregate grading with a maximum of 3 percent by weight passing ASTM D1140, No. 200 sieve, [or] [ 1-1/2 inch and no more than 2 percent by weight passing the No. 4 size sieve] [or coarse aggregate Size 57, 67, or 77]. PIPE CASING ************************************************************************** NOTE: Indicate, on the contract drawings, limits of right-of-way and any other site requirements or dimensions conforming to the standards of the railroad or highway owner. Where traffic can be interrupted, trenching in a pipeline casing is more economical with the same advantages of allowing future work without interruption of traffic. ************************************************************************** 2.6 Casing Pipe ASTM A139/A139M, Grade B, or ASTM A252, Grade 2, smooth wall pipe. Match casing size to the outside diameter and wall thickness as indicated on Drawing Sheet No. [_____]. Protective coating is not required on casing pipe. Wood Supports [Treated Yellow Pine or Douglas Fir][Locally available], rough, structural grade. Provide wood with nonleaching water-borne pressure preservative (ACA or CCA) and treatment conforming to AWPA P5 and AWPA C2, respectively. Secure wood supports to carrier pipe with stainless steel or zinc-coated steel bands. PART 3 EXECUTION ************************************************************************** NOTE: Coordinate requirements with Section 31 11 00 CLEARING AND GRUBBING. ************************************************************************** 3.1 STRIPPING OF TOPSOIL ************************************************************************** NOTE: Topsoil will be separately excavated, stored, and used for surface finish in preparation for URS FOR EQM SECTION 31 00 00 Page 18 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 seeding, sodding, or other planting, only where topsoil is definitely superior for grass and plant growth as compared with the remainder of the excavated material. Surface soil that is a heavy clay, predominantly sandy, or is lean in grass- and plant-growth qualities, will not be saved. The hauling, spreading, smoothing, and maintenance of the topsoil in preparation for the seeding and planting operations are generally considered under a separate section, and therefore are not considered in this specification. The blank will be filled with the appropriate depth dimension. ************************************************************************** Where indicated or directed, strip topsoil to a depth of [4] [_____] inches. Spread topsoil on areas already graded and prepared for topsoil, or transported and deposited in stockpiles convenient to areas that are to receive application of the topsoil later, or at locations indicated or specified. Keep topsoil separate from other excavated materials, brush, litter, objectionable weeds, roots, stones larger than 2 inches in diameter, and other materials that would interfere with planting and maintenance operations. [Stockpile in locations indicated] [Remove from the site] any surplus of topsoil from excavations and gradings. 3.2 GENERAL EXCAVATION Perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified. Perform the grading in accordance with the typical sections shown and the tolerances specified in paragraph FINISHING. Transport satisfactory excavated materials and place in fill or embankment within the limits of the work. Excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory materials as directed. Include such excavated material and the satisfactory material ordered as replacement in excavation. Dispose surplus satisfactory excavated material not required for fill or embankment in areas approved for surplus material storage or designated waste areas. Dispose unsatisfactory excavated material in designated waste or spoil areas. During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times. Excavate material required for fill or embankment in excess of that produced by excavation within the grading limits from the borrow areas indicated or from other approved areas selected by the Contractor as specified. 3.2.1 Ditches, Gutters, and Channel Changes Finish excavation of ditches, gutters, and channel changes by cutting accurately to the cross sections, grades, and elevations shown on Drawing Sheet No. [_____]the drawings. Do not excavate ditches and gutters below grades shown. Backfill the excessive open ditch or gutter excavation with satisfactory, thoroughly compacted, material or with suitable stone or cobble to grades shown. Dispose excavated material as shown or as directed, except in no case allow material be deposited a maximum 4 feet from edge of a ditch. Maintain excavations free from detrimental quantities of leaves, brush, sticks, trash, and other debris until final acceptance of the work. URS FOR EQM SECTION 31 00 00 Page 19 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.2.2 TYMX989345A FA3002-09-D-0002 TG02 Drainage Structures ************************************************************************** NOTE: The last two sentences will be removed except when pile foundations are to be used. ************************************************************************** Make excavations to the lines, grades, and elevations shown, or as directed. Provide trenches and foundation pits of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations as shown. Clean rock or other hard foundation material of loose debris and cut to a firm, level, stepped, or serrated surface. Remove loose disintegrated rock and thin strata. Do not disturb the bottom of the excavation when concrete or masonry is to be placed in an excavated area. Do not excavate to the final grade level until just before the concrete or masonry is to be placed. Where pile foundations are to be used, stop the excavation of each pit at an elevation 1 foot above the base of the footing, as specified, before piles are driven. After the pile driving has been completed, remove loose and displaced material and complete excavation, leaving a smooth, solid, undisturbed surface to receive the concrete or masonry. 3.2.3 Drainage Provide for the collection and disposal of surface and subsurface water encountered during construction. Completely drain construction site during periods of construction to keep soil materials sufficiently dry. Construct storm drainage features (ponds/basins) at the earliest stages of site development, and throughout construction grade the construction area to provide positive surface water runoff away from the construction activity [ and] [or] provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed. 3.2.4 Dewatering ************************************************************************** NOTE: Check depth of proposed utilities and foundations relative to the existing ground water elevation prior to editing. ************************************************************************** Control groundwater flowing toward or into excavations to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. Do not permit French drains, sumps, ditches or trenches within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Take control measures by the time the excavation reaches the water level in order to maintain the integrity of the in situ material. While the excavation is open, maintain the water level continuously, at least [_____] feet below the working level. [Operate dewatering system continuously until construction work below existing water levels is complete. Submit performance records weekly.] [Measure and URS FOR EQM SECTION 31 00 00 Page 20 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 record performance of dewatering system at same time each day by use of observation wells or piezometers installed in conjunction with the dewatering system.] [Relieve hydrostatic head in previous zones below subgrade elevation in layered soils to prevent uplift.] Trench Excavation Requirements ************************************************************************** NOTE: The width of the trench below the top of the pipe will depend on the type of pipe used and soil conditions. The pipe manufacturer's installation manual should provide this information, and if so, it will be followed. In general, the width of trench will be 300 mm (12 inches) to 600 mm (24 inches), plus pipe O.D. for smaller pipe sizes, and 600 mm (24 inches) to 900 mm (36 inches) plus pipe O.D. for larger pipe sizes. Sloping walls below the top of the pipe are allowed for certain types of pipe in special ground conditions. ************************************************************************** Excavate the trench as recommended by the manufacturer of the pipe to be installed. Slope trench walls below the top of the pipe, or make vertical, and of such width as recommended in the manufacturer's printed installation manual. Provide vertical trench walls where no manufacturer's printed installation manual is available. Shore trench walls more than [_____] feet high, cut back to a stable slope, or provide with equivalent means of protection for employees who may be exposed to moving ground or cave in. Shore vertical trench walls more than [_____] feet high. Excavate trench walls which are cut back to at least the angle of repose of the soil. Give special attention to slopes which may be adversely affected by weather or moisture content. Do not exceed the trench width below the pipe top of 24 inches plus pipe outside diameter (O.D.) for pipes of less than 24 inches inside diameter, and do not exceed 36 inches plus pipe outside diameter for sizes larger than 24 inches inside diameter. Where recommended trench widths are exceeded, provide redesign, stronger pipe, or special installation procedures by the Contractor. The Contractor is responsible for the cost of redesign, stronger pipe, or special installation procedures without any additional cost to the Government. 3.2.5 Bottom Preparation ************************************************************************** NOTE: Stones 75 mm (3 inches) or greater should be removed. However, pipe manufacturer's criteria, if any, should be used. ************************************************************************** Grade the bottoms of trenches accurately to provide uniform bearing and support for the bottom quadrant of each section of the pipe. Excavate bell holes to the necessary size at each joint or coupling to eliminate point bearing. Remove stones of [_____] inch or greater in any dimension, or as recommended by the pipe manufacturer, whichever is smaller, to avoid point bearing. 3.2.6 Removal of Unyielding Material ************************************************************************** NOTE: Minimum of 100 mm (4 inches) should be URS FOR EQM SECTION 31 00 00 Page 21 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 removed to produce a suitable cushion for the pipe. ************************************************************************** Where [overdepth is not indicated and] unyielding material is encountered in the bottom of the trench, remove such material [_____] inch below the required grade and replaced with suitable materials as provided in paragraph BACKFILLING AND COMPACTION. 3.2.7 Removal of Unstable Material Where unstable material is encountered in the bottom of the trench, remove such material to the depth directed and replace it to the proper grade with select granular material as provided in paragraph BACKFILLING AND COMPACTION. When removal of unstable material is required due to the Contractor's fault or neglect in performing the work, the Contractor is responsible for excavating the resulting material and replacing it without additional cost to the Government. 3.2.8 Excavation for Appurtenances Provide excavation for manholes, catch-basins, inlets, or similar structures [sufficient to leave at least 12 inches clear between the outer structure surfaces and the face of the excavation or support members.] [of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations as shown.] Clean rock or loose debris and cut to a firm surface either level, stepped, or serrated, as shown or as directed. Remove loose disintegrated rock and thin strata. Specify removal of unstable material. When concrete or masonry is to be placed in an excavated area, take special care not to disturb the bottom of the excavation. Do not excavate to the final grade level until just before the concrete or masonry is to be placed. Jacking, Boring, and Tunneling ************************************************************************** NOTE: In situations where utility lines must be installed more than 5 to 7 meters (15 to 20 feet) below ground surface, through embankments, under minor roads or parking areas, or where surface conditions make it difficult or impractical to excavate open trenches, utility lines may be installed by jacking, boring, or tunneling as a Contractor option. Where operational requirements preclude installation by trenching, the use of jacking, boring, or tunneling should be specified as mandatory alternatives. This requirement will normally exist where utilities must cross railroads, highways, primary access roads and airfield pavements. Pipe and conduit smaller than 900 mm (36 inches) in diameter will normally be installed in smooth steel pipe casing. Designing engineers must coordinate with installation facility engineers to identify and validate utility crossings where jacking, boring, or tunneling will be specified as mandatory. ************************************************************************** Unless otherwise indicated, provide excavation by open cut except that sections of a trench may be jacked, bored, or tunneled if, in the opinion URS FOR EQM SECTION 31 00 00 Page 22 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 of the Contracting Officer, the pipe, cable, or duct can be safely and properly installed and backfill can be properly compacted in such sections. 3.2.4 Underground Utilities ************************************************************************** NOTE: Delete this paragraph in its entirety if no known utilities or subsurface construction is located below or adjacent to work covered in this specification. ************************************************************************** The Contractor is responsible for movement of construction machinery and equipment over pipes and utilities during construction. [Perform work adjacent to non-Government utilities as indicated in accordance with procedures outlined by utility company.] [Excavation made with power-driven equipment is not permitted within [2] [_____] feet of known Government-owned utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the Contracting Officer.] Report damage to utility lines or subsurface construction immediately to the Contracting Officer. Structural Excavation Ensure that footing subgrades have been inspected and approved by the Contracting Officer prior to concrete placement. Excavate to bottom of pile cap prior to placing or driving piles, unless authorized otherwise by the Contracting Officer. Backfill and compact over excavations and changes in grade due to pile driving operations to 95 percent of ASTM D698 maximum density. 3.3 SELECTION OF BORROW MATERIAL ************************************************************************** NOTE: Where a substantial quantity of borrow excavation is anticipated, the drawings and specifications will indicate the location or locations within the project site, and the conditions under which borrow may be obtained. ************************************************************************** Select borrow material to meet the requirements and conditions of the particular fill or embankment for which it is to be used. Obtain borrow material from the borrow areas [shown on Drawing Sheet No. [_____]] [within the limits of the project site, selected by the Contractor] [or] [from approved private sources]. Unless otherwise provided in the contract, the Contractor is responsible for obtaining the right to procure material, pay royalties and other charges involved, and bear the expense of developing the sources, including rights-of-way for hauling from the owners. Borrow material from approved sources on Government-controlled land may be obtained without payment of royalties. Unless specifically provided, do not obtain borrow within the limits of the project site without prior written approval. Consider necessary clearing, grubbing, and satisfactory drainage of borrow pits and the disposal of debris thereon related operations to the borrow excavation. URS FOR EQM SECTION 31 00 00 Page 23 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.4 TYMX989345A FA3002-09-D-0002 TG02 OPENING AND DRAINAGE OF EXCAVATION AND BORROW PITS ************************************************************************** NOTE: The first sentence will be deleted when all work covered by Invitation for Bids is to be included in one lump-sum contract price. ************************************************************************** Notify the Contracting Officer sufficiently in advance of the opening of any excavation or borrow pit or borrow areas to permit elevations and measurements of the undisturbed ground surface to be taken. Except as otherwise permitted, excavate borrow pits and other excavation areas providing adequate drainage. Transport overburden and other spoil material to designated spoil areas or otherwise dispose of as directed. Provide neatly trimmed and drained borrow pits after the excavation is completed. Ensure that excavation of any area, operation of borrow pits, or dumping of spoil material results in minimum detrimental effects on natural environmental conditions. SHORING 3.5 General Requirements ************************************************************************** NOTE: Include this paragraph when scope of work requires excavations which are greater than 1.5 m (5 feet) or where it is known that in-situ soils lack the stability to hold near vertical faces. Where sufficient room is available, the Contractor may slope back trench walls rather than having to use a shoring system. However, the Contractor should not be given the opportunity to slope the faces of excavations in lieu of providing shoring unless all the following conditions are met: 1. The excavation is less than 6 m (20 feet) in depth. 2. There are no adjacent structures, roads, or pavements that will affect the excavation. 3. No equipment, stored material, or overlying material will affect the excavation. 4. Vibration from equipment, traffic, or blasting will not affect the excavation. 5. There will be no ground water problems. 6. Surcharges will not affect the excavation. 7. Station operational considerations permit laying back the slopes of the excavation. ************************************************************************** Submit a Shoring and Sheeting plan for approval 15 days prior to starting work. Submit drawings and calculations, certified by a registered professional engineer, describing the methods for shoring and sheeting of URS FOR EQM SECTION 31 00 00 Page 24 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 excavations. Finish shoring, including sheet piling, and install as necessary to protect workmen, banks, adjacent paving, structures, and utilities. Remove shoring, bracing, and sheeting as excavations are backfilled, in a manner to prevent caving. Geotechnical Engineer ************************************************************************** NOTE: Where site conditions require extensive monitoring of excavations and water levels include the following requirement. ************************************************************************** Hire a Professional Geotechnical Engineer to provide inspection of excavations and soil/groundwater conditions throughout construction. The Geotechnical Engineer is responsible for performing pre-construction and periodic site visits throughout construction to assess site conditions. The Geotechnical Engineer is responsible for updating the excavation, sheeting and dewatering plans as construction progresses to reflect changing conditions and submit an updated plan if necessary. Submit a monthly written report, informing the Contractor and Contracting Officer of the status of the plan and an accounting of the Contractor's adherence to the plan addressing any present or potential problems. The Contracting Officer is responsible for arranging meetings with the Geotechnical Engineer at any time throughout the contract duration. 3.5 GRADING AREAS ************************************************************************** NOTE: When spoil areas or borrow areas are within the limits of Government-controlled land, additional requirements based on the following, and as appropriate for the project, will be included in the contract document. Locations of areas will be indicated, or the approximate distances from the project site will be specified. Generally, unburned vegetative material and surplus excavated material will be disposed of in inconspicuous spoil areas where no future construction is planned. If economically justifiable, surplus suitable excavated material may be stockpiled or may be disposed of in areas where future construction is planned and where fill will be required. Spoil materials will be so placed and the worked portions of spoil areas and borrow areas will be so graded and shaped as to minimize soil erosion, siltation of drainage channels, and damage to existing vegetation. The degree of compaction will be specified. ************************************************************************** Where indicated, divide work into grading areas within which satisfactory excavated material will be placed in embankments, fills, and required backfills. Do not haul satisfactory material excavated in one grading area to another grading area except when so directed in writing. Place and grade stockpiles of satisfactory [and unsatisfactory] [and wasted materials] as specified. Keep stockpiles in a neat and well drained condition, giving due consideration to drainage at all times. Clear, grub, and seal by rubber-tired equipment, the ground surface at stockpile locations; separately stockpile excavated satisfactory and unsatisfactory materials. URS FOR EQM SECTION 31 00 00 Page 25 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Protect stockpiles of satisfactory materials from contamination which may destroy the quality and fitness of the stockpiled material. If the Contractor fails to protect the stockpiles, and any material becomes unsatisfactory, remove and replace such material with satisfactory material from approved sources. 3.6 FINAL GRADE OF SURFACES TO SUPPORT CONCRETE Do not excavate to final grade until just before concrete is to be placed. [For pile foundations, stop the excavation at an elevation of from 6 to 12 inches above the bottom of the footing before driving piles. After pile driving has been completed, complete the remainder of the excavation to the elevations shown.]Only use excavation methods that will leave the foundation rock in a solid and unshattered condition. Roughen the level surfaces, and cut the sloped surfaces, as indicated, into rough steps or benches to provide a satisfactory bond. Protect shales from slaking and all surfaces from erosion resulting from ponding or water flow. 3.7 3.7.1 GROUND SURFACE PREPARATION General Requirements Remove and replace unsatisfactory material with satisfactory materials, as directed by the Contracting Officer, in surfaces to receive fill or in excavated areas. Scarify the surface to a depth of 6 inches before the fill is started. Plow, step, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so that the fill material will bond with the existing material. When subgrades are less than the specified density, break up the ground surface to a minimum depth of 6 inches, pulverizing, and compacting to the specified density. When the subgrade is part fill and part excavation or natural ground, scarify the excavated or natural ground portion to a depth of 12 inches and compact it as specified for the adjacent fill. 3.7.2 Frozen Material Do not place material on surfaces that are muddy, frozen, or contain frost. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, or other approved equipment well suited to the soil being compacted. Moisten material as necessary [to plus or minus [_____] percent of optimum moisture] [to provide the moisture content that will readily facilitate obtaining the specified compaction with the equipment used]. 3.8 UTILIZATION OF EXCAVATED MATERIALS ************************************************************************** NOTE: Specifications covering excavated materials authorized to be wasted will usually include the provision that the surface and side slopes formed from such material be shaped and sloped so as to provide for drainage and for later seeding and mowing operations. ************************************************************************** Dispose unsatisfactory materials removing from excavations into designated waste disposal or spoil areas. Use satisfactory material removed from excavations, insofar as practicable, in the construction of fills, embankments, subgrades, shoulders, bedding (as backfill), and for similar URS FOR EQM SECTION 31 00 00 Page 26 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 purposes. Submit procedure and location for disposal of unused satisfactory material. Submit proposed source of borrow material. Do not waste any satisfactory excavated material without specific written authorization. Dispose of satisfactory material, authorized to be wasted, in designated areas approved for surplus material storage or designated waste areas as directed. Clear and grub newly designated waste areas on Government-controlled land before disposal of waste material thereon. Stockpile and use coarse rock from excavations for constructing slopes or embankments adjacent to streams, or sides and bottoms of channels and for protecting against erosion. Do not dispose excavated material to obstruct the flow of any stream, endanger a partly finished structure, impair the efficiency or appearance of any structure, or be detrimental to the completed work in any way. 3.9 3.9.1 BURIED TAPE AND DETECTION WIRE Buried Warning and Identification Tape Provide buried utility lines with utility identification tape. Bury tape 12 inches below finished grade; under pavements and slabs, bury tape 6 inches below top of subgrade. 3.9.2 Buried Detection Wire Bury detection wire directly above non-metallic piping at a distance not to exceed 12 inches above the top of pipe. Extend the wire continuously and unbroken, from manhole to manhole. Terminate the ends of the wire inside the manholes at each end of the pipe, with a minimum of 3 feet of wire, coiled, remaining accessible in each manhole. Furnish insulated wire over it's entire length. Install wires at manholes between the top of the corbel and the frame, and extend up through the chimney seal between the frame and the chimney seal. For force mains, terminate the wire in the valve pit at the pump station end of the pipe. 3.10 BACKFILLING AND COMPACTION ************************************************************************** NOTE: It is imperative to specify a high degree of compaction in fills under structures to minimize settlement and to insure stability of a structure. In addition to the criteria set forth in UFC 3-220-01, the following factors will be considered in establishing the specific requirements: a. The sensitivity of the structure to total and/or differential settlement as related to the structural design. This is particularly true of structures to be founded partly on fill and partly on natural ground. b. The ability of normal compaction equipment to produce the desired densities in existing or locally available materials within a reasonable range of molding moisture content. If considered essential, special equipment will be specified. c. The compaction requirements for clean, cohesionless, granular materials will be generally higher than those for cohesive materials because URS FOR EQM SECTION 31 00 00 Page 27 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 cohesionless materials readily consolidate when subjected to vibration. For structures with critical stability requirements and settlement limitations, the minimum density requirements may be altered. If only a cohesionless soil or only a cohesive soil is used, the inapplicable values will be deleted. d. The exception to required high degree of compaction in fills and backfills is in expansive soils (see UFC 3-220-01). Where it is necessary to use materials having swelling characteristics, usually CL or CH classifications, the specified degree of compaction will be related to laboratory test results for swelling under a considerable range of molding moisture and compactive effort. In swelling soils, it is important to specify a density and molding moisture range that will enable the soil to stay stable, striking a reasonable balance between potential swell and excessive settlement under load, even at the expense of accepting a reduced bearing capacity. A maximum permissible density should be established to minimize swelling. If possible, soils with swelling characteristics will be classified as unsatisfactory material, particularly under critical stability structures. e. ASTM D1557 is satisfactory for establishing moisture density characteristics of a material in most cases. However, other modifications may be necessary as discussed in this ASTM and under soil tests in DM 21.3/ UFC 3-260-02. The procedures and precautions in the subgrade compaction paragraphs of DM 21.3/UFC 3-260-02, will be considered in establishing minimum density requirements for a particular project. Modifications will be made to meet the backfill requirements for deep-seated or subsurface structures as discussed in UFC 3-220-04FA. ************************************************************************** Place backfill adjacent to any and all types of structures, and compact to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials, to prevent wedging action or eccentric loading upon or against the structure. Prepare ground surface on which backfill is to be placed and provide compaction requirements for backfill materials in conformance with the applicable portions of paragraphs GROUND SURFACE PREPARATION. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. 3.10.1 Trench Backfill ************************************************************************** NOTE: Most pressure tests require backfilling to at least 600 mm (2 feet) over the pipe with the joints and couplings left open for inspection. ************************************************************************** URS FOR EQM SECTION 31 00 00 Page 28 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Backfill trenches to the grade shown. [Backfill the trench to [_____] feet above the top of pipe prior to performing the required pressure tests. Leave the joints and couplings uncovered during the pressure test.] [Do not backfill the trench until all specified tests are performed.] 3.10.1.1 Replacement of Unyielding Material Replace unyielding material removed from the bottom of the trench with select granular material or initial backfill material. 3.10.1.2 Replacement of Unstable Material Replace unstable material removed from the bottom of the trench or excavation with select granular material placed in layers not exceeding 6 inches loose thickness. 3.10.1.3 Bedding and Initial Backfill ************************************************************************** NOTE: Bedding is provided to level out any irregularities in the foundation and to assure uniform support along the barrel of each pipe section. Bedding is also constructed to distribute the load bearing reaction, due to the weight of the backfill material, around the lower portion of the pipe. If the pipe or conduit is placed directly on a flat or shaped foundation, delete "bedding" from the title and from any reference in the paragraph. If bedding will be specified, determine type and thickness and show on the plans. Specify compaction to 95 percent maximum density for cohesionless soils, and 90 percent maximum density for cohesive soils. Any locally available fine aggregate for concrete or asphalt mixtures will qualify as sand and may be specified by local gradation and specification number in lieu of "SW" or "SP." Drawings (details) should clearly show where sand backfill or bedding is required. Locally available coarse aggregate for concrete will suffice and may be specified by local gradation and specification number in lieu of "GW" or "GP." Maximum size of aggregate should not be more than 25 mm per 300 mm (one inch per foot) of pipe diameter or 75 mm (3 inches) maximum. Refer to pipe manufacturer's criteria for more stringent requirements, if any, on aggregate size and gradation. On drawings (details), clearly show where gravel backfill or bedding is required. ************************************************************************** [Provide bedding of the type and thickness shown.] Place initial backfill material and compact it with approved tampers to a height of at least one foot above the utility pipe or conduit. Bring up the backfill evenly on both sides of the pipe for the full length of the pipe. Take care to ensure thorough compaction of the fill under the haunches of the pipe. URS FOR EQM SECTION 31 00 00 Page 29 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Except as specified otherwise in the individual piping section, provide bedding for buried piping in accordance with AWWA C600, Type 4, except as specified herein. Compact backfill to top of pipe to 95 percent of ASTM D698 maximum density. Provide plastic piping with bedding to spring line of pipe. Provide materials as follows: 3.10.1.3.1 Class I Angular, 0.25 to 1.5 inch, graded stone, including a number of fill materials that have regional significance such as coral, slag, cinders, crushed stone, and crushed shells. 3.10.1.3.2 Class II Coarse sands and gravels with maximum particle size of 1.5 inch, including various graded sands and gravels containing small percentages of fines, generally granular and noncohesive, either wet or dry. Soil Types GW, GP, SW, and SP are included in this class as specified in ASTM D2487. 3.10.1.3.3 Sand Clean, coarse-grained sand classified as [_____] in accordance with Section 31 23 00.00 20 EXCAVATION AND FILL, [gradation [_____] of the [DOT] [State Standard] or [SW] [or] [SP] by ASTM D2487 for [bedding] [and] [backfill] [as indicated]]. 3.10.1.3.4 Gravel and Crushed Stone Clean, coarsely graded natural gravel, crushed stone or a combination thereof identified as [_____] in accordance with Section 31 23 00.00 20 EXCAVATION AND FILL, [gradation [_____] of the [DOT] [State Standard]] or having a classification of [GW] [GP] in accordance with ASTM D2487 for [bedding] [and] [backfill] [as indicated]. [Do not exceed maximum particle size of [3] [_____] inches.] 3.10.1.4 Final Backfill Fill the remainder of the trench, except for special materials for roadways, railroads and airfields, with satisfactory material. Place backfill material and compact as follows: 3.10.1.4.1 Roadways, Railroads, and Airfields Place backfill up to the required elevation as specified. water flooding or jetting methods of compaction. 3.10.1.4.2 Do not permit Sidewalks, Turfed or Seeded Areas and Miscellaneous Areas Deposit backfill in layers of a maximum of 12 inches loose thickness, and compact it to 85 percent maximum density for cohesive soils and 90 percent maximum density for cohesionless soils. [Allow water flooding or jetting methods of compaction for granular noncohesive backfill material. Do not allow water jetting to penetrate the initial backfill.] [Do not permit compaction by water flooding or jetting.] Apply this requirement to all other areas not specifically designated above. Backfill for Appurtenances ************************************************************************** URS FOR EQM SECTION 31 00 00 Page 30 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NOTE: The number of days the concrete is allowed to cure before backfilling the structure will depend on the type of mix and the concrete strength requirements specified. Three days would be considered as a minimum. ************************************************************************** After the manhole, catchbasin, inlet, or similar structure has been constructed [and the concrete has been allowed to cure for [_____] days], place backfill in such a manner that the structure is not be damaged by the shock of falling earth. Deposit the backfill material, compact it as specified for final backfill, and bring up the backfill evenly on all sides of the structure to prevent eccentric loading and excessive stress. SPECIAL REQUIREMENTS Special requirements for both excavation and backfill relating to the specific utilities are as follows: 3.11 Gas Distribution Excavate trenches to a depth that will provide a minimum 18 inches of cover in rock excavation and a minimum 24 inch of cover in other excavation. 3.12 Water Lines ************************************************************************** NOTE: Minimum depth of cover will be that required for frost penetration in the region and for safe operation of the utility. For fire protection yard mains, reference is made to NFPA 24 for recommended depth of cover. ************************************************************************** Excavate trenches to a depth that provides a minimum cover of [_____] feet from the existing ground surface, or from the indicated finished grade, whichever is lower, to the top of the pipe. [For fire protection yard mains or piping, an additional [_____] inch of cover is required.] 3.13 Heat Distribution System Free initial backfill material of stones larger than 1/4 inch in any dimension. 3.14 Electrical Distribution System Provide a minimum cover of 24 inches from the finished grade to direct burial cable and conduit or duct line, unless otherwise indicated. 3.15 Sewage Absorption Trenches or Pits ************************************************************************** NOTE: Delete these paragraphs when sewage absorption trenches or pits are not included in the project. Consult a geotechnical engineer and local standards in selecting bracketed information. ************************************************************************** URS FOR EQM SECTION 31 00 00 Page 31 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.15.1 TYMX989345A FA3002-09-D-0002 TG02 Porous Fill Provide backfill material consisting of clean crushed rock or gravel having a gradation [such that 100 percent passes the 2 inch sieve and zero percent passes the 1/2 inch sieve.] [conforming to the requirements of gradation [No. 4] [_____] for coarse aggregate in ASTM C33/C33M.] 3.15.2 Cover ************************************************************************** NOTE: Select appropriate bracketed information to correspond to the design indicated on the drawings. ************************************************************************** [Filter fabric] [Concrete] [Kraft paper conforming to CID A-A-203, Grade B, No. 2, 50 pound weight] [or a layer of straw at least 2 inches thick] as indicated. 3.16 Pipeline Casing Provide new smooth wall steel pipeline casing under [new] [existing] [railroad] [and] [pavement] [in a trench] [by the boring and jacking method of installation]. Provide each new pipeline casing, where indicated and to the lengths and dimensions shown, complete and suitable for use with the new piped utility as indicated. [Install pipeline casing by dry boring and jacking method as follows:] 3.16.1 Bore Holes Mechanically bore holes and case through the soil with a cutting head on a continuous auger mounted inside the casing pipe. Weld lengths of pipe together in accordance with AWS D1.1/D1.1M. Do not use water or other fluids in connection with the boring operation. 3.16.2 Cleaning Clean inside of the pipeline casing of dirt, weld splatters, and other foreign matter which would interfere with insertion of the piped utilities by attaching a pipe cleaning plug to the boring rig and passing it through the pipe. 3.16.3 End Seals After installation of piped utilities in pipeline casing, provide watertight end seals at each end of pipeline casing between pipeline casing and piping utilities. Provide watertight [end seals as indicated.] [segmented elastomeric end seals.] Rip-Rap Construction ************************************************************************** NOTE: Select information in brackets to best describe rip-rap construction. Provide detail or typical section through rip-rap on drawings as well as all dimensions necessary for estimating and construction. If DOT standard specifications are referenced for rip-rap construction, paragraphs entitled "Preparation" through "Grouting" may be deleted. URS FOR EQM SECTION 31 00 00 Page 32 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** Construct rip-rap [on bedding material] [on filter fabric] [with grout] [in accordance with [DOT] [_____] State Standard, paragraph [_____]] in the areas indicated. Trim and dress indicated areas to conform to cross sections, lines and grades shown within a tolerance of 0.1 foot. 3.17 Bedding Placement Spread [filter fabric] bedding material uniformly to a thickness of at least [3] [_____] inches on prepared subgrade as indicated. [Compaction of bedding is not required. Finish bedding to present even surface free from mounds and windrows.] 3.18 Stone Placement Place rock for rip-rap on prepared bedding material to produce a well graded mass with the minimum practicable percentage of voids in conformance with lines and grades indicated. Distribute larger rock fragments, with dimensions extending the full depth of the rip-rap throughout the entire mass and eliminate "pockets" of small rock fragments. Rearrange individual pieces by mechanical equipment or by hand as necessary to obtain the distribution of fragment sizes specified above. [For grouted rip-rap, hand-place surface rock with open joints to facilitate grouting and do not fill smaller spaces between surface rock with finer material. Provide at least one "weep hole" through grouted rip-rap for every 50 square feet of finished surface. Provide weep holes with columns of bedding material, 4 inches in diameter, extending up to the rip-rap surface without grout.] Grouting [Prior to grouting, wet rip-rap surfaces. Grout rip-rap in successive longitudinal strips, approximately 10 feet in width, commencing at the lowest strip and working up the slope. Distribute grout to place of final deposit and work into place between stones with brooms, spades, trowels, or vibrating equipment. Take precautions to prevent grout from penetrating bedding layer. Protect and cure surface for a minimum of 7 days.] 3.11 3.11.1 EMBANKMENTS Earth Embankments ************************************************************************** NOTE: Moisture content limits for compaction should be included in these paragraphs when necessary for obtaining strength and stability in embankments and fill, for controlling movement of expansive soils and when, in the opinion of the project geotechnical engineer, moisture control is required for the soils being used. ************************************************************************** Construct earth embankments from satisfactory materials free of organic or frozen material and rocks with any dimension greater than 3 inches. Place the material in successive horizontal layers of loose material not more than 12 inches in depth. Spread each layer uniformly on a soil surface that has been moistened or aerated as necessary, and scarified or otherwise broken up so that the fill will bond with the surface on which it is placed. After spreading, plow, disk, or otherwise brake up each layer; moisten or URS FOR EQM SECTION 31 00 00 Page 33 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 aerate as necessary; thoroughly mix; and compact to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials. Compaction requirements for the upper portion of earth embankments forming subgrade for pavements are identical with those requirements specified in paragraph SUBGRADE PREPARATION. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Rock Embankments ************************************************************************** NOTE: The designer will determine the appropriate values for all blank spaces, except the last one, on the basis of recent experience on similar construction or of test results obtained from construction and testing of a test section. The specific method by which density will be determined in the laboratory and measured in the field will be described in the project specification. The total thickness of the pavement structure, including select material subbase, base, and pavement will be placed in the last blank space in this paragraph. The first blank space applies to rock fill of small maximum dimension and maximum lift placement of 200 to 250 mm (8 to 10 inches). Coordinate maximum size with satisfactory material definition. If it is necessary to use larger rock and thicker lifts, the second expression in brackets is applicable. When thicker lifts are used, it may be necessary to specify a minimum number of passes of the compactor. Delete last sentence, unless the rock excavation is engineered to be used under pavements with sufficient fines to prevent consolidation of the embankment. ************************************************************************** Construct rock embankments from material classified as rock excavation, as defined above, placed in successive horizontal layers of loose material not more than [_____] inch in depth. Do not use pieces of rock larger than [_____] inch in the greatest dimension. Spread each layer of material uniformly, completely saturate, and compact to a minimum density of [_____] pcf. Adequately bond each successive layer of material to the material on which it is placed. Finish compaction with vibratory compactors weighing at least [_____] tons, heavy rubber-tired rollers weighing at least [_____] tons, or steel-wheeled rollers weighing at least [_____] tons. [Do not use rock excavation as fill material for the construction of pavements.] [In embankments on which pavements are to be constructed, do not use rock above a point [_____] inch below the surface of the pavement.] 3.12 3.12.1 SUBGRADE PREPARATION Proof Rolling ************************************************************************** NOTE: Specify proof rolling when the quality of the existing subgrade is questionable. Proof rolling can be used to verify that no unsatisfactory URS FOR EQM SECTION 31 00 00 Page 34 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 material is present (no bid quantity required, location shown or specified) or to locate suspected unsatisfactory material (indicate a bid quantity to be removed). Remove this paragraph if not required in the project. ************************************************************************** Finish proof rolling on an exposed subgrade free of surface water (wet conditions resulting from rainfall) which would promote degradation of an otherwise acceptable subgrade. [After stripping,] pProof roll the existing subgrade of the airfield[_____] with six passes of a [dump truck loaded with 4 cubic yards of soil] [ or a 15 ton, pneumatic-tired roller.] Operate the [roller] [or truck] in a systematic manner to ensure the number of passes over all areas, and at speeds between 2-1/2 to 3-1/2 mph. [When proof rolling, provide one-half of the passes made with the roller in a direction perpendicular to the other passes.] Notify the Contracting Officer a minimum of 3 days prior to proof rolling. Perform proof rolling in the presence of the Contracting Officer. Undercut rutting or pumping of material [as directed by the Contracting Officer] [to a depth of [_____] inch] and replace with [fill and backfill] [select] material. [Prepare bids based on replacing approximately [_____] square yards, with an average depth of [_____] inch at various locations.] 3.12.2 Construction ************************************************************************** NOTE: Moisture content limits for compaction should be included in these paragraphs when necessary for obtaining strength and stability in embankments and fill, for controlling movement of expansive soils and when, in the opinion of the project geotechnical engineer, moisture control is required for the soils being used. Special smoothness tolerances are not required for subgrades for railroads; therefore, both sets of brackets will be removed when writing specifications for preparation of railroad subgrade only. When writing specifications for preparation of roadway and/or airfield pavement subgrade, the brackets will be removed from the applicable sentences and the smoothness tolerances showing permissible deviations in fractions of a millimeter (inch) and the length of straightedge in meters (feet) will be inserted in the blanks as appropriate. ************************************************************************** Shape subgrade to line, grade, and cross section, and compact as specified. Include plowing, disking, and any moistening or aerating required to obtain specified compaction for this operation. Remove soft or otherwise unsatisfactory material and replace with satisfactory excavated material or other approved material as directed. Excavate rock encountered in the cut section to a depth of 6 inches below finished grade for the subgrade. Bring up low areas resulting from removal of unsatisfactory material or excavation of rock to required grade with satisfactory materials, and shape the entire subgrade to line, grade, and cross section and compact as specified. [After rolling, the surface of the subgrade for roadways shall not show deviations greater than 1/2 inch when tested with a 12-foot straightedge applied both parallel and at right angles to the URS FOR EQM SECTION 31 00 00 Page 35 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 centerline of the area.] [After rolling, do not show deviations for the surface of the subgrade for airfields greater than 1/4[_____] inch when tested with a 12[_____] foot straightedge applied both parallel and at right angles to the centerline of the area.] Do not vary the elevation of the finish subgrade more than 0.05 foot from the established grade and cross section. 3.12.3 Compaction ************************************************************************** NOTE: Use 90 percent of ASTM D698 or ASTM D1557 for General Site Compaction of cohesionless materials on Army projects and 85 percent of same for Navy projects. For Army projects see UFC 3-220-01, UFC 3-260-02 and DM 21.3 for criteria and design guidelines. Specify most jobs using ASTM D698 compaction, except for roads, airfields, and other heavily loaded areas, which should use ASTM D1557 compaction. Specify compaction in terms of one compaction effort (ASTM D698 or ASTM D1557), if possible. ************************************************************************** Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Except for paved areas and railroads, compact each layer of the embankment to at least 90[_____] percent of laboratory maximum density as determined by ASTM D1557. 3.12.3.1 Subgrade for Railroads Compact subgrade for railroads to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials. Subgrade for Pavements ************************************************************************** NOTE: If the compaction requirements are not shown in tabular form on the drawings, and the paragraphs as written are not adequate, paragraphs Subgrade for Pavements and Subgrade for Shoulders will be rewritten as follows: Subgrade for [pavements] [and] [shoulders] shall be compacted to at least the percentage of laboratory maximum density in the following table for the specific depths below the surface of the [pavement] [or] [shoulders] shown. URS FOR EQM SECTION 31 00 00 Page 36 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Percentage of Laboratory Maximum Density Required Depth Below Pavement or Shoulder Surface ( Inch) From To Fill Cohesive Materials Cut Cohesionless Cohesive Materials Materials Cohesionless Materials The desired depths and density percentages will be entered in the table in accordance with applicable data from the following manuals, as appropriate: UFC 3-250-01FA and UFC-3-260-02. ************************************************************************** Compact subgrade for pavements to at least [_____] percentage laboratory maximum density for the depth below the surface of the pavement shown. When more than one soil classification is present in the subgrade, thoroughly blend, reshape, and compact the top [_____] inch of subgrade. 3.12.3.1 Subgrade for Shoulders Compact subgrade for shoulders to at least 100[_____] percentage laboratory maximum density per ASTM D1557 for the [depth below the surface of shoulder shown] [full depth of the shoulder]top 24 below finished pavement or top 12 inches of subgrade, whichever is greater. 3.12.3.2 Subgrade for Airfield Pavements Compact top 24 inches below finished pavement or top 12 inches of subgrades, whichever is greater, to [100] [_____] percent of ASTM D1557; compact fill and backfill material to [100] [_____] percent of ASTM D1557. 3.13 SHOULDER CONSTRUCTION ************************************************************************** NOTE: Shoulder construction will form a part of the work to be performed under this section of the specifications except when shoulder construction is specified under the subbase, base-course, wearing course, or pavement sections of the specifications and is designated in the contract to be performed and paid for under one of these sections. ************************************************************************** Construct shoulders of satisfactory excavated or borrow material or as otherwise shown or specified.. Submit advanced notice on shoulder construction for rigid pavements. Construct shoulders immediately after adjacent paving is complete. In the case of rigid pavements, do not construct shoulders until permission of the Contracting Officer has been obtained. Compact the entire shoulder area to at least the percentage of maximum density as specified in paragraph SUBGRADE PREPARATION above, for specific ranges of depth below the surface of the shoulder. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Finish shoulder construction in proper sequence in such a manner that adjacent ditches will be drained effectively and that no damage of any kind is done to the adjacent completed pavement. Align the completed shoulders true to URS FOR EQM SECTION 31 00 00 Page 37 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 grade and shaped to drain in conformity with the cross section shown. 3.14 FINISHING Finish the surface of excavations, embankments, and subgrades to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within 0.1 foot of the grades and elevations indicated except that the degree of finish for subgrades specified in paragraph SUBGRADE PREPARATION. Finish gutters and ditches in a manner that will result in effective drainage. Finish the surface of areas to be turfed from settlement or washing to a smoothness suitable for the application of turfing materials. Repair graded, topsoiled, or backfilled areas prior to acceptance of the work, and re-established grades to the required elevations and slopes. 3.14.1 Subgrade and Embankments During construction, keep embankments and excavations shaped and drained. Maintain ditches and drains along subgrade to drain effectively at all times. Do not disturb the finished subgrade by traffic or other operation. Protect and maintain the finished subgrade in a satisfactory condition until ballast, subbase, base, or pavement is placed. Do not permit the storage or stockpiling of materials on the finished subgrade. Do not lay subbase, base course, ballast, or pavement until the subgrade has been checked and approved, and in no case place subbase, base, surfacing, pavement, or ballast on a muddy, spongy, or frozen subgrade. Capillary Water Barrier ************************************************************************** NOTE: The compacted thickness of capillary water barrier will be indicated and will not be less than 100 mm (4 inches). The paragraph will be deleted where site conditions make the barrier unnecessary. ************************************************************************** Place a capillary water barrier under concrete floor and area-way slabs grade directly on the subgrade and compact with a minimum of two passes of a hand-operated plate-type vibratory compactor. 3.14.2 Grading Around Structures Construct areas within 5 feet outside of each building and structure line true-to-grade, shape to drain, and maintain free of trash and debris until final inspection has been completed and the work has been accepted. 3.15 PLACING TOPSOIL ************************************************************************** NOTE: Topsoil will be separated, excavated, stored, and used for surface finish in preparation for seeding, sodding, or other planting only where the topsoil is definitely superior for grass and other plant growth as compared to the balance of the excavated materials. Generally, topsoil will be spread after other operations have been completed. When topsoil spreading is covered under a separate section of the specifications, this paragraph will URS FOR EQM SECTION 31 00 00 Page 38 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 be deleted. ************************************************************************** On areas to receive topsoil, prepare the compacted subgrade soil to a 2 inches depth for bonding of topsoil with subsoil. Spread topsoil evenly to a thickness of 4[_____] inch and grade to the elevations and slopes shown. Do not spread topsoil when frozen or excessively wet or dry. Obtain material required for topsoil in excess of that produced by excavation within the grading limits from [offsite areas] [areas indicated]. 3.16 TESTING ************************************************************************** NOTE: Density tests other than those specified in this paragraph may be required for certain types of soil, in which case paragraph "Degree of Compaction" will be edited accordingly and the laboratory compaction requirement applicable to the soil encountered will be specified. See UFC 3-260-02 for a discussion of conditions requiring nonstandard compaction control tests. ************************************************************************** Perform testing by a Corps validated commercial testing laboratory or the Contractor's validated testing facility. Submit qualifications of the Corps validated commercial testing laboratory or the Contractor's validated testing facilities. If the Contractor elects to establish testing facilities, do not permit work requiring testing until the Contractor's facilities have been inspected, Corps validated and approved by the Contracting Officer. a. Determine field in-place density in accordance with [ASTM D1556] [ ASTM D2167] [ASTM D6938]. [When ASTM D6938 is used, check the calibration curves and adjust using only the sand cone method as described in ASTM D1556. ASTM D6938 results in a wet unit weight of soil in determining the moisture content of the soil when using this method. b. Check the calibration curves furnished with the moisture gauges along with density calibration checks as described in ASTM D6938; check the calibration of both the density and moisture gauges at the beginning of a job on each different type of material encountered and at intervals as directed by the Contracting Officer.] [ASTM D2937, use the Drive Cylinder Method only for soft, fine-grained, cohesive soils.] When test results indicate, as determined by the Contracting Officer, that compaction is not as specified, remove the material, replace and recompact to meet specification requirements. c. Perform tests on recompacted areas to determine conformance with specification requirements. Appoint a registered professional civil engineer to certify inspections and test results. These certifications shall state that the tests and observations were performed by or under the direct supervision of the engineer and that the results are representative of the materials or conditions being certified by the tests. The following number of tests, if performed at the appropriate time, will be the minimum acceptable for each type operation. URS FOR EQM SECTION 31 00 00 Page 39 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.16.1 TYMX989345A FA3002-09-D-0002 TG02 Fill and Backfill Material Gradation One test per 1000[_____] cubic yards stockpiled or in-place source material. Determine gradation of fill and backfill material in accordance with [ASTM C136] [ASTM D422] [ASTM D1140]. 3.16.2 In-Place Densities ************************************************************************** NOTE: Density test frequency can vary from one test per 10 square meter (100 square feet) for small areas up to one test per 900 square meter (10,000 square feet). The following table will also help establish test frequency for various situations: Material Type Location of Material Test Frequency Undisturbed native soil Structures Subgrades Two random tests in building footings and two tests on subgrade within building line Structures (adjacent to) One test per structure per 2000 sq ft taken 1 foot below finished grade Site (except airfields) One test per 2500 sq ft Embankments or borrow Any One test per lift per 500 cubic yds placed Native soil subgrade other than structures and parking Borrow Any One test or one test per 10,000 sq ft whichever is greater One test per lift per 500 cubic yds placed Fills and backfills Any ************************************************************************** a. One test per 2500[_____] square feet, or fraction thereof, of each lift of fill or backfill areas compacted by other than hand-operated machines. b. One test per 250[_____] square feet, or fraction thereof, of each lift of fill or backfill areas compacted by hand-operated machines. c. One test per 100[_____] linear feet, or fraction thereof, of each lift of embankment or backfill for [roads] [airfields]. d. One test per 50[_____] linear feet, or fraction thereof, of each lift of embankment or backfill for railroads. 3.16.3 Check Tests on In-Place Densities If ASTM D6938 is used, check in-place densities by ASTM D1556 as follows: a. One check test per lift for each 20,000[_____] square feet, or fraction thereof, of each lift of fill or backfill compacted by other than hand-operated machines. URS FOR EQM SECTION 31 00 00 Page 40 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 b. One check test per lift for each 2000[_____] square feet, of fill or backfill areas compacted by hand-operated machines. c. One check test per lift for each 800[_____] linear feet, or fraction thereof, of embankment or backfill for [roads] [airfields]. d. One check test per lift for each 400[_____] linear feet, or fraction thereof, of embankment or backfill for railroads. 3.16.4 Moisture Contents In the stockpile, excavation, or borrow areas, perform a minimum of two tests per day per type of material or source of material being placed during stable weather conditions. During unstable weather, perform tests as dictated by local conditions and approved by the Contracting Officer. 3.16.5 Optimum Moisture and Laboratory Maximum Density Perform tests for each type material or source of material including borrow material to determine the optimum moisture and laboratory maximum density values. One representative test per 1000[_____] cubic yards of fill and backfill, or when any change in material occurs which may affect the optimum moisture content or laboratory maximum density. 3.16.6 Tolerance Tests for Subgrades Perform continuous checks on the degree of finish specified in paragraph SUBGRADE PREPARATION during construction of the subgrades. 3.16.7 Displacement of Sewers ************************************************************************** NOTE: The trench should be backfilled to at least 600 mm (2 feet). ************************************************************************** After other required tests have been performed and the trench backfill compacted to [[_____], feet above the top of the pipe] [the finished grade surface], inspect the pipe to determine whether significant displacement has occurred. Conduct this inspection in the presence of the Contracting Officer. Inspect pipe sizes larger than 36 inches, while inspecting smaller diameter pipe by shining a light or laser between manholes or manhole locations, or by the use of television cameras passed through the pipe. If, in the judgment of the Contracting Officer, the interior of the pipe shows poor alignment or any other defects that would cause improper functioning of the system, replace or repair the defects as directed at no additional cost to the Government. 3.17 DISPOSITION OF SURPLUS MATERIAL ************************************************************************** NOTE: Select last bracketed option for NAVFAC Hawaii projects. ************************************************************************** Remove surplus material or other soil material not required or suitable for filling or backfilling, and brush, refuse, stumps, roots, and timber [to a Government disposal area [as indicated][which is located within a haul URS FOR EQM SECTION 31 00 00 Page 41 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 distance of [_____] miles]][from Government property to an approved location ] [from Government property and delivered to a licensed/permitted facility or to a location approved by the Contracting Officer.] as directed by the Contracting Officer. -- End of Section -- URS FOR EQM SECTION 31 00 00 Page 42 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 01 13 (August 2008) --------------------------Preparing Activity: USACE Superseding UFGS-32 01 13 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 32 01 13 BITUMINOUS SEAL AND FOG COATS ************************************************************************** NOTE: This guide specification covers the requirements for bituminous surface coatings for low volume roads, parking areas, and other general applications. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: Bituminous seal coat should not be used on primary roads or airfield areas. Fog seals lower the frictional resistance of paved surfaces and will not be used on runways, high speed taxiway turnoffs, or moderate to high speed roads unless approval is obtained from NAVFAC HQ, AFCEC or the TSMCX. This section must be edited to remove all references to Fog Seal when it is not required in the project. UFC 3-250-03 should be used for guidance in preparing these specifications. ************************************************************************** URS FOR EQM SECTION 32 01 13 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.1 TYMX989345A FA3002-09-D-0002 TG02 MEASUREMENT AND PAYMENT PROCEDURES ************************************************************************** NOTE: Delete this paragraph when lump sum bidding is used. ************************************************************************** Measure the quantities of bituminous material in the accepted work and to be paid for, provided that the measured quantities are not more than 10 percent over the specified application rate. Any amount of bituminous material and aggregate more than 10 percent over the specified application rate for each application will be deducted from the measured quantities except for irregular areas where hand spraying of the bituminous material and hand spreading of the aggregate is necessary. 1.1.1 Bituminous Material Measurement Methods ************************************************************************** NOTE: When the bituminous material is measured in liters (gallons), the appropriate ASTM method will be retained for the type of bituminous material specified. ************************************************************************** The amount of bituminous material to be paid for will be measured in [ 2000 pound tons,] [ gallons at 60 degrees F]. Correct volumes measured at temperatures other than 60 degrees F in accordance with [ASTM D633][ ASTM D1250] [, using a coefficient of expansion of 0.00025 per degree F for asphalt emulsion]. 1.1.2 Payment ************************************************************************** NOTE: Delete this paragraph when lump sum bidding is used. ************************************************************************** The quantities of bituminous material, determined as specified above, will be paid for at the respective contract unit prices. Payment will constitute full compensation for all operations necessary to complete the work as specified herein. 1.1.3 Waybills and Delivery Tickets ************************************************************************** NOTE: Delete this paragraph when lump sum bidding is used. ************************************************************************** Do not remove bituminous material from the tank car or storage tank until measurements of the remaining quantity have been taken. Submit waybills and delivery tickets during the progress of the work. Before the final statement is allowed, file certified waybills and delivery tickets for all materials used in the work covered by this section. 1.2 REFERENCES ************************************************************************** NOTE: This paragraph is used to list the URS FOR EQM SECTION 32 01 13 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) AASHTO T 40 (2002; R 2006) Sampling Bituminous Materials ASTM INTERNATIONAL (ASTM) ASTM D140/D140M (2014) Standard Practice for Sampling Bituminous Materials ASTM D2397/D2397M (2013) Standard Specification for Cationic Emulsified Asphalt ASTM D2995 (1999; R 2009) Determining Application Rate of Bituminous Distributors ASTM D633 (2011) Volume Correction Table for Road Tar U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA) MUTCD 1.3 (2009) Manual on Uniform Traffic Control Devices SYSTEM DESCRIPTION ************************************************************************** NOTE: Retain equipment units required for the project and delete all others. ************************************************************************** 1.3.1 Equipment, Plant and Tools Equipment, plant and tools used in the work are subject to approval and shall be maintained in a satisfactory working condition at all times. Provide equipment which is adequate and has the capability of producing the URS FOR EQM SECTION 32 01 13 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 results specified. Provide calibrated equipment, such as asphalt distributors, scales, batching equipment, spreaders and similar equipment, that has been recalibrated by an approved calibration laboratory within [12] [_____] months prior to commencing work[and every [_____] months thereafter, by such laboratory from the date of recalibration, during the term of the contract]. Submit an equipment list with calibration reports. 1.3.2 Bituminous Distributors ************************************************************************** NOTE: The bracketed statements at the end of this paragraph apply specifically to Fog Seal. ************************************************************************** Provide distributors that have pneumatic tires of sufficient size and number to prevent rutting, shoving, or otherwise damaging any part of the pavement structure. Design and equip the distributor to distribute the bituminous material in a uniform double or triple lap at the specified temperature, at readily determined and controlled rates from 0.05 to 2.0 gallons/square yard, with a pressure range of 25 to 75 psi with an allowable variation from the specified rate of not more than plus or minus 5 percent, and at variable widths. Include in the distributor equipment a separate power unit for the bitumen pump, full-circulation spray bars, tachometer, pressure gauges, volume-measuring devices, adequate heaters for heating of materials to the proper application temperature, a thermometer for reading the temperature of tank contents, and a hand-held hose attachment suitable for applying bituminous material manually to areas inaccessible to the distributor. Equip the distributor to circulate and agitate the bituminous material during the heating process.[ Provide distributor with an adjustable, both horizontally and vertically, spray nozzle bar. Make normal width of bar application at least 12 feet, with provisions for lesser or larger width when necessary. Equip distributor with a meter having a dial registering feet of travel/min. Make both dials visible to the distributor driver. Provide a thermometer and well, not in contact with any heating tubes, for accurately indicating temperature of asphalt emulsion.] 1.3.3 Power Brooms and Power Blowers Provide power brooms and power blowers suitable for cleaning surfaces to [be treated] [which the seal coat is to be applied]. 1.3.4 Storage Tanks Provide tanks capable of heating the bituminous material, under effective and positive control at all times, to the required temperature. Accomplish heating by steam coils, hot oil, or electricity. Affix to the tank an armored thermometer with a range from 100 to 300 degrees F so that the temperature of the bituminous material may be read at all times. 1.3.5 Single-Pass, Surface-Treatment Machines Provide machines capable of spraying bituminous material in one pass; of distributing the bituminous material uniformly, at even heat, and in controlled amounts; over the surface to be sealed. 1.3.6 Vacuum Sweepers for Fog Seal Provide self-propelled, vacuum pickup sweeper capable of removing loose URS FOR EQM SECTION 32 01 13 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 sand, water, and debris from pavement surface. 1.4 SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.][information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-03 Product Data Waybills and Delivery Tickets Equipment List Inspection Reports SD-04 Samples Bituminous Materials Fog Seal[; G][; G, [_____]] URS FOR EQM SECTION 32 01 13 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 SD-06 Test Reports Tests 1.5 QUALITY ASSURANCE ************************************************************************** NOTE: Keep applicable tests and delete the others depending on whether this Section is used for Seal or Fog Coat. ************************************************************************** Perform sampling and testing using an approved commercial testing laboratory or facilities furnished by the Contractor. No work requiring testing will be permitted until the facilities have been inspected and approved. The first inspection will be at the expense of the Government. Costs incurred for any subsequent inspection will be charged to the Contractor. Perform tests in sufficient numbers, and at the location and times directed, to ensure that the materials meet specified requirements. 1.5.1 Samples Take samples of bituminous material in accordance with AASHTO T 40 or ASTM D140/D140M. 1.5.2 Bituminous Material Source Select sources from which bituminous materials are to be obtained and notify the Contracting Officer within 15 days after the award of the contract. From each source of supply, submit a one gallon sample of bituminous material. 1.5.3 Equipment Calibration ************************************************************************** NOTE: Bracketed statements apply to Fog Seal; remove when Fog Seal is not requirede in the project. ************************************************************************** Furnish all equipment, materials and labor necessary to calibrate the bituminous distributor. Perform all calibrations with the approved job materials and prior to applying the specified coatings to the prepared surface. Perform calibration of the bituminous distributor in accordance with ASTM D2995.[ Inspect all equipment prior to application of fog seal. Perform work to calibrate tank and measuring devices of the distributor. Perform inspection and calibration at the beginning of the work and at least once a day during construction.] 1.6 DELIVERY, STORAGE, AND HANDLING Deliver emulsified asphalt (fog seal) to the site in a homogenous and undamaged condition. Inspect the materials for contamination and damage. Unload and store the materials with a minimum of handling. Protect stored aggregate from contamination and segregation. Replace defective or damaged materials. 1.7 ENVIRONMENTAL REQUIREMENTS ************************************************************************** NOTE: Retain correct temperatures depending on the URS FOR EQM SECTION 32 01 13 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 type of coating used for the project. ************************************************************************** Apply the coating when the existing surface is dry, and when the weather is not foggy, rainy, or when the wind velocity will prevent the uniform application of the bitumen[or aggregates]. [Apply the bituminous seal coat only when the atmospheric temperature is above 60 degrees F in the shade and when the pavement surface temperature is above 60 degrees F, unless otherwise directed.] [Apply fog seal when atmospheric temperature is above 50 degrees F and rising or when pavement temperature is above 60 degrees F, unless otherwise directed.] PART 2 2.1 PRODUCTS EMULSIFIED ASPHALT FOR FOG SEAL ************************************************************************** NOTE: In the majority of applications, the cationic (CSS-1h) is preferable to the anionic (SS-1h) for use as fog seal. Cationic emulsion will cure at a faster rate than anionic and is more suitable where high humidity prevails. Anionic emulsions possess a negative charge on the asphalt droplets and cationic emulsions carry a positive charge on the asphalt droplets. All aggregate possess a negative surface charge at their natural pH. This negative surface charge varies in intensity depending on the geological source of the aggregate. ************************************************************************** Emulsified asphalt for Fog Seal shall conform to ASTM D2397/D2397M[CSS-1] [ CSS-1h] [_____] for cationic materials. Submit in accordance with paragraph titled "Sample Application", for approval and selection of one of the trial application rates. 2.2 WATER Provide fresh, clean, and potable water. PART 3 3.1 EXECUTION PREPARATION OF SURFACE ************************************************************************** NOTE: If the surface to be treated requires repairs, the method of repairs and extent of work involved should be shown or described. Removal of paint and rubber deposits are generally accomplished by high pressure water blasting. Few approved chemicals are effective and sandblasting is not permitted by air pollution regulations at some locations. Mechanical abrasion generally causes damage to the pavement. Bracketed sentence at the end of this paragraph applies to Fog Seal; remove when not used in the project. ************************************************************************** URS FOR EQM SECTION 32 01 13 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Repair damaged surface and fill cracks before starting work. Immediately before starting work, remove all loose material, dirt, clay, or other objectionable material from the surface to be treated with power brooms or power blowers, if needed. Paint firmly bonded to the surface that has the chalk removed may remain. Material removed from the surface shall not be mixed with the cover aggregate.[ When necessary to achieve a clean surface for fog application, flushing with water will be permitted.] 3.2 3.2.1 FOG SEAL APPLICATION Sample Application ************************************************************************** NOTE: In some localities an incompatibility may exist between the asphaltic emulsion and the water to be used for dilution due to their characteristics. Clear, potable water should be used, and if there is any doubt with the compatibility of the water and the asphalt emulsion, add the following to this paragraph: Prior to commencing work, 0.24 liter (one half pint) of the proposed asphalt emulsion and 0.24 liter (one half pint) of the proposed water shall be combined, agitated, and allowed to sit for a period of 24 hours to test their compatibility. If they prove to be incompatible, an approved chemical treatment shall be provided for all water used for dilution or a different and compatible source of water shall be selected. ************************************************************************** Determine the required application rate from a sample installation. Select an area of the prepared pavement at least 300 feet long and as wide as the distributor spray bar. Dilute emulsified asphalt with an equal part of water or as recommended by the manufacturer. Apply the water diluted asphalt emulsion in at least three test sections; each a minimum of 100 feet long. The trial applications shall be made at the rates of [0.08] [_____], [0.14][_____], and [0.20] [_____] gallons/square yard. The trial application rates may be modified if approved by the Contracting Officer. Additional trial applications may be made if warranted by pavement surface conditions. Use the rate which has been satisfactorily applied without leaving an excess of asphalt residue on the surface and has been approved, for the fog seal. 3.2.2 Application Inspection Inspect application of fog seal for uniformity. [During application, take [_____] sample for each [500] [_____] square yards of surface area to receive emulsified asphalt. Weigh samples to determine conformance with application rate.] 3.2.3 Inspection Reports Furnish a written report citing climatic temperature during application of fog seal, emulsion temperature during application, and rate of emulsion application. URS FOR EQM SECTION 32 01 13 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.2.4 TYMX989345A FA3002-09-D-0002 TG02 Application Following preparation of the surface, apply the water diluted asphalt emulsion at the rate determined from the trial application. Maintain application temperature of emulsified asphalt between 75 and 160 degrees F. To obtain uniform application of the fog seal at the junction of previous and subsequent applications, spread building paper on the surface of the applied material for a sufficient distance back from the ends of each application so that flow from the spray bar may be started and stopped on the paper, and so that all sprayers will operate at full force. Immediately after application, remove and properly dispose of the building paper. Treat spots unavoidably missed with the hand spray equipment. Base bids on application of diluted emulsion at 0.14 gsy. If the actual amount required is more or less than 0.14 gsy, an adjustment in the contract price will be made as provided by the contract. 3.3 SITE PROTECTION During applications, protect adjacent buildings, structures, vehicles, manhole covers, inlet grates, and trees to prevent being spattered or marred. 3.4 TRAFFIC CONTROL Protect freshly placed coatings from damage by traffic. Provide sufficient warning signs and barricades to prevent traffic over freshly treated surfaces. Protect treated areas from traffic for at least [2] [24] hours after final application of coatings, or for such time as necessary to prevent picking up. Immediately prior to opening to traffic, roll the entire treated area with a self-propelled pneumatic-tired roller. Provide warning signs and barricades for proper traffic control, in accordance with MUTCD. -- End of Section -- URS FOR EQM SECTION 32 01 13 Page 9 65% - 01/23/2015 This Page Left Intentionally Blank REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 01 19 (August 2008) Change 1 - 11/14 --------------------------Preparing Activity: USACE Superseding UFGS-32 01 19 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS ************************************************************************** NOTE: This guide specification covers the requirements for field molded sealants in sealing or resealing joints in rigid pavements on airfields, roads, streets, and other areas. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: In preparing contract specifications for concrete pavements the designer will use UFC 3-250-04 Standard Practice for Concrete Pavements. ************************************************************************** 1.1 UNIT PRICES ************************************************************************** NOTE: Delete this paragraph when lump sum bidding is used. ************************************************************************** URS FOR EQM SECTION 32 01 19 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.1.1 TYMX989345A FA3002-09-D-0002 TG02 Measurement Determine the quantity of each sealing item to be paid for by actual measurement of the number of linear feet of in-place material that has been approved by the Contracting Officer. 1.1.2 Payment Payment will be made at the contract unit bid prices per linear foot for the sealing items scheduled. The unit bid prices will include the cost of all labor, materials, and the use of all equipment and tools required to complete the work. 1.2 REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. ASTM INTERNATIONAL (ASTM) ASTM C1016 (2014) Standard Test Method for Determination of Water Absorption of Sealant Backing (Joint Filler) Material ASTM D5893/D5893M (2010) Cold Applied, Single Component, Chemically Curing Silicone Joint Sealant for Portland Cement Concrete Pavements ASTM D6690 (2012) Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements ASTM D789 (2007; E 2010) Determination of Relative Viscosity and Moisture Content of Polyamide (PA) URS FOR EQM SECTION 32 01 19 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 U.S. ARMY CORPS OF ENGINEERS (USACE) COE CRD-C 525 1.3 (1989) Corps of Engineers Test Method for Evaluation of Hot-Applied Joint Sealants for Bubbling Due to Heating SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.][information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-03 Product Data Manufacturer's Recommendations[; G][; G, [_____]]. Equipment. URS FOR EQM SECTION 32 01 19 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 SD-04 Samples Materials[; G][; G, [_____]]. SD-06 Test Reports Certified copies of the test reports[; G][; G, [_____]]. 1.4 1.4.1 QUALITY ASSURANCE Test Requirements ************************************************************************** NOTE: Select the applicable statement for testing and determining specification compliance and delete the inapplicable statement. The first statement will be selected for all projects except where the project is less than 200 liters (50 gallons) or 200 kg (500 pounds) of material. When the project requires less than 200 liters (50 gallons) or 200 kg (500 pounds) of sealant, the first statement can be deleted and the sealant and back-up material may be accepted on certified certificate which contains the test data showing compliance with the laboratory test requirements. The cost of testing can be obtained from U.S. Army Corps of Engineer Division Laboratories or Waterways Experiment Station. ************************************************************************** Test the joint sealant and backup or separating material for conformance with the referenced applicable material specification. [The materials will be tested by the Government. No material shall be used at the project prior to receipt of written notice that the materials meet the laboratory requirements. The cost of the first test of samples will be borne by the Government. If the samples fail to meet specification requirements, replace the materials represented by the sample and test the new materials at the Contractor's expense.] [Perform testing of the materials in an approved independent laboratory and submit certified copies of the test reports for approval 14[_____] days prior to the use of the materials at the job site. Samples will be retained by the Government for possible future testing should the materials appear defective during or after application.] Conformance with the requirements of the laboratory tests specified will not constitute final acceptance of the materials. Final acceptance will be based on the performance of the in-place materials. Submit samples of the materials (sealant, primer if required, and backup material), in sufficient quantity for testing and approval 14[_____] days prior to the beginning of work. No material will be allowed to be used until it has been approved. 1.4.2 Trial Joint Sealant Installation Prior to the cleaning and sealing of the joints for the entire project, prepare a test section at least 200 feet long using the specified materials and approved equipment, so as to demonstrate the proposed joint preparation and sealing of all types of joints in the project. Following the completion of the test section and before any other joint is sealed, inspect the test section to determine that the materials and installation meet the requirements specified. If it is determined that the materials or installation do not meet the requirements, remove the materials, and URS FOR EQM SECTION 32 01 19 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 reclean and reseal the joints at no cost to the Government. When the test section meets the requirements, it may be incorporated into the permanent work and paid for at the contract unit price per linear foot for sealing items scheduled. Prepare and seal all other joints in the manner approved for sealing the test section. 1.5 DELIVERY, STORAGE, AND HANDLING Inspect materials delivered to the job site for defects, unload, and store them with a minimum of handling to avoid damage. Provide storage facilities at the job site for maintaining materials at the temperatures and conditions recommended by the manufacturer. 1.6 ENVIRONMENTAL REQUIREMENTS The ambient air temperature and the pavement temperature within the joint wall shall be a minimum of 50 degrees F and rising at the time of application of the materials. Do not apply sealant if moisture is observed in the joint. PART 2 2.1 PRODUCTS SEALANTS ************************************************************************** NOTE: Select joint sealants based on the proposed use and local experience. ASTM D6690 (Type II or Type III) sealants should be specified for areas that will not receive fuel spillage, engine blast and heat exposure (i.e., areas where aircraft warm up their engines.) Type II sealant conforms to the discontinued ASTM D3405 requirements. Type III contains all of the requirements of Type II and has additional requirements for a water immersed bond test and an oven-aged resilience test as required by SS-S-1401C. ASTM D6690 (Type II or Type III) sealants are normally used on roadways, vehicle parking lots, and on some aircraft taxiways. ASTM D7116 sealants should be specified for areas that will receive fuel spillage but not heat or engine blast exposure. ASTM D7116 sealants are normally used on aircraft parking aprons and some vehicle maintenance areas. ASTM D6690 and ASTM D7116 sealants must be tested in accordance with COE CRD-C 525 in addition to the appropriate specification. This testing is required due to bubbling tendencies of hot-applied sealants when used in PCC joints. FS SS-S-200 Type H (hand-mix) or Type M (machine mix) sealants should be specified for areas that are subject to fuel spillage, heat or engine blast. FS SS-S-200 sealants are normally used in aircraft warm up areas, the first five hundred feet of runways, and some aircraft parking aprons. For large projects, FS SS-S-200 Type M is generally specified and Type H is generally specified for small projects; however, either is acceptable. The tack free time for the Type M material is shorter than the Type H material, so if an area needs to be URS FOR EQM SECTION 32 01 19 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 reopened quickly, Type M sealant should be specified. ASTM D5893/D5893M sealants may be specified in place of ASTM D6690 sealants. ASTM D5893/D5893M covers silicone sealants that provide improved life-cycle cost benefits. ************************************************************************** Materials for sealing cracks joints in the various paved areas are indicated on the drawings shall be as follows: as summarized below: Area Sealing Material Concrete-to-Asphalt Joints [_____] Concrete-to-Concrete Joints [_____] 2.2 [ASTM D6690, Type III and COE CRD-C 525] ASTM D5893[ASTM D5893/D5893M] PRIMERS When primers are recommended by the manufacturer of the sealant, use them in accordance with the recommendation of the manufacturer. 2.3 BACKUP MATERIALS ************************************************************************** NOTE: The use of a bond breaking separation tape or backup material in the joint may prevent an adverse reaction between incompatible materials, maintain the desired configuration (shape factor of the material), and act as a bond breaker to prevent excessive stresses from being placed on the sealant during pavement movement. Therefore, the separating or backup material should be carefully selected and installed to form an effective and durable support for the sealant. Separating or blocking media should be placed to a depth below the pavement approximately equal to the width of the joint. This is to achieve a shape factor (ratio of the depth of the sealant to the width of the joint) of 1. ASTM D5893/D5893M sealants sometimes require a shape factor of 0.5 instead of 1. This is equivalent to a width-to-depth ratio of 2:1 and will require the standard joint detail to be modified. If a ASTM D5893/D5893M sealant is to be used the placement depth of the bond breaking separating tape or backup material should be adjusted accordingly. Drawings should be included in the contract drawings to indicate application details. ************************************************************************** Provide backup material that is a compressible, nonshrinking, nonstaining, nonabsorbing material, nonreactive with the joint sealant. The material shall have a melting point at least 5 degrees F greater than the pouring temperature of the sealant being used when tested in accordance with ASTM D789. The material shall have a water absorption of not more than 5 percent of the sample weight when tested in accordance with ASTM C1016. Use backup material that is 25 plus or minus 5 percent larger in diameter than the nominal width of the crack. URS FOR EQM SECTION 32 01 19 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 BOND BREAKING TAPES Provide a bond breaking tape or separating material that is a flexible, nonshrinkable, nonabsorbing, nonstaining, and nonreacting adhesive-backed tape. The material shall have a melting point at least 5 degrees F greater than the pouring temperature of the sealant being used when tested in accordance with ASTM D789. The bond breaker tape shall be approximately 1/8 inch wider than the nominal width of the joint and shall not bond to the joint sealant. PART 3 3.1 EXECUTION EXECUTING EQUIPMENT Machines, tools, and equipment used in the performance of the work required by this section shall be approved before the work is started maintained in satisfactory condition at all times. Submit a list of proposed equipment to be used in performance of construction work including descriptive data, 14[_____] days prior to use on the project. 3.1.1 Joint Cleaning Equipment Tractor-Mounted Routing Tool Provide a routing tool, used for removing old sealant from the joints, of such shape and dimensions and so mounted on the tractor that it will not damage the sides of the joints. The tool shall be designed so that it can be adjusted to remove the old material to varying depths as required. The use of V-shaped tools or rotary impact routing devices will not be permitted. Hand-operated spindle routing devices may be used to clean and enlarge random cracks. 3.1.1.1 Concrete Saw Provide a self-propelled power saw, with water-cooled diamond or abrasive saw blades, for cutting joints to the depths and widths specified or for refacing joints or cleaning sawed joints where sandwaterblasting does not provide a clean joint. Sandblasting Equipment ************************************************************************** NOTE: Sandblasting equipment with a 6.4 mm (1/4 inch) nozzle requires at least 64.7 liters per second (137 cubic feet per minute) of air to function efficiently. A larger nozzle would not serve any useful purpose in cleaning joints. ************************************************************************** Include with the sandblasting equipment an air compressor, hose, and long-wearing venturi-type nozzle of proper size, shape and opening. The maximum nozzle opening should not exceed 1/4 inch. The air compressor shall be portable and capable of furnishing not less than 150 cfm and maintaining a line pressure of not less than 90 psi at the nozzle while in use. Demonstrate compressor capability, under job conditions, before approval. The compressor shall be equipped with traps that will maintain the compressed air free of oil and water. The nozzle shall have an adjustable guide that will hold the nozzle aligned with the joint URS FOR EQM SECTION 32 01 19 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 approximately 1 inch above the pavement surface. Adjust the height, angle of inclination and the size of the nozzle as necessary to secure satisfactory results. 3.1.1.2 Waterblasting Equipment ************************************************************************** NOTE: Waterblasting equipment varies considerably with respect to design of wand, nozzle, water pressure, and water volume, depending upon the manufacturer. Consequently, the effectiveness of a particular set of equipment cannot be predicted. Delete this paragraph if waterblasting will not be used. ************************************************************************** Include with the waterblasting equipment a trailer-mounted water tank, pumps, high-pressure hose, wand with safety release cutoff control, nozzle, and auxiliary water resupply equipment. Provide water tank and auxiliary resupply equipment of sufficient capacity to permit continuous operations. The nozzle shall have an adjustable guide that will hold the nozzle aligned with the joint approximately 1 inch above the pavement surface. Adjust the height, angle of inclination and the size of the nozzle as necessary to obtain satisfactory results. A pressure gauge mounted at the pump shall show at all times the pressure in psi at which the equipment is operating. 3.1.1.3 Hand Tools ************************************************************************** NOTE: Where spalled joint edges have not been repaired prior to any previous sealing, it may be necessary for the Contractor to employ other types of small tools for the repair work. Such tools should be carefully evaluated for potential spalling effects prior to approval for use. For repairing concrete pavements adjacent to joints, the designer is referred to Section 32 01 29.61 PARTIAL DEPTH PATCHING OF RIGID PAVING, and to Technical Manual 5-822-9. ************************************************************************** Hand tools may be used, when approved, for removing defective sealant from a crack and repairing or cleaning the crack faces. 3.1.2 Sealing Equipment ************************************************************************** NOTE: Delete the inappropriate paragraphs. ************************************************************************** 3.1.2.1 Hot-Poured Sealing Equipment The unit applicators used for heating and installing [ASTM D6690] [ ASTM D7116] joint sealant materials shall be mobile and shall be equipped with a double-boiler, agitator-type kettle with an oil medium in the outer space for heat transfer; a direct-connected pressure-type extruding device with a nozzle shaped for inserting in the joint to be filled; positive temperature devices for controlling the temperature of the transfer oil and sealant; and a recording type thermometer for indicating the temperature of URS FOR EQM SECTION 32 01 19 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the sealant. The applicator unit shall be designed so that the sealant will circulate through the delivery hose and return to the inner kettle when not in use. 3.1.2.2 Two-Component, Cold-Applied, Machine Mix Sealing Equipment Provide equipment used for proportioning, mixing, and installing FS SS-S-200 Type M joint sealants designed to deliver two semifluid components through hoses to a portable mixer at a preset ratio of 1 to 1 by volume using pumps with an accuracy of plus or minus 5 percent for the quantity of each component. The reservoir for each component shall be equipped with mechanical agitation devices that will maintain the components in a uniform condition without entrapping air. Incorporate provisions to permit thermostatically controlled indirect heating of the components, when required. However, immediately prior to proportioning and mixing, the temperature of either component shall not exceed 90 degrees F. Provide screens near the top of each reservoir to remove any foreign particles or partially polymerized material that could clog fluid lines or otherwise cause misproportioning or improper mixing of the two components. Provide equipment capable of thoroughly mixing the two components through a range of application rates of 10 to 60 gallons per hour and through a range of application pressures from 50 to 1500 psi as required by material, climatic, or operating conditions. Design the mixer for the easy removal of the supply lines for cleaning and proportioning of the components. The mixing head shall accommodate nozzles of different types and sizes as may be required by various operations. The dimensions of the nozzle shall be such that the nozzle tip will extend into the joint to allow sealing from the bottom of the joint to the top. Maintain the initially approved equipment in good working condition, serviced in accordance with the supplier's instructions, and unaltered in any way without obtaining prior approval. Two-Component, Cold-Applied, Hand-Mix Sealing Equipment Mixing equipment for FS SS-S-200 Type H sealants shall consist of a slow-speed electric drill or air-driven mixer with a stirrer in accordance with the manufacturer's recommendations. Submit printed copies of manufacturer's recommendations, [_____] days prior to use on the project, where installation procedures, or any part thereof, are required to be in accordance with those recommendations. Installation of the material will not be allowed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material. 3.1.2.2 Cold-Applied, Single-Component Sealing Equipment ************************************************************************** NOTE: Some ASTM D5893/D5893M sealants cure when exposed to moisture. When the sealant is moisture sensitive it is necessary to use Teflon-lined hoses to prevent the sealant from curing in the hoses. ************************************************************************** The equipment for installing ASTM D5893/D5893M single component joint sealants shall consist of an extrusion pump, air compressor, following plate, hoses, and nozzle for transferring the sealant from the storage container into the joint opening. The dimension of the nozzle shall be such that the tip of the nozzle will extend into the joint to allow sealing from the bottom of the joint to the top. Maintain the initially approved equipment in good working condition, serviced in accordance with the URS FOR EQM SECTION 32 01 19 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 supplier's instructions, and unaltered in any way without obtaining prior approval. Small hand-held air-powered equipment (i.e., caulking guns) may be used for small applications. SAFETY ************************************************************************** NOTE: Delete this paragraph if liquid oxygen (LOX) equipment, storage, or piping is not within the project area. Joint sealant should not be used within 8 m (25 feet) of any LOX equipment or storage. If LOX equipment, storage, or piping is within the project area, the designer will use continuously reinforced concrete slabs in the 8 m (25 feet) clear area of LOX to reduce the number of joints. If joints cannot be eliminated within the 8 m (25 feet) clear area, then the joints in the area should be thoroughly cleaned and left unsealed. LOX MUST NOT BE PERMITTED TO MIX WITH ANY ORGANIC MATERIAL. ************************************************************************** Do not place joint sealant within 25 feet of any liquid oxygen (LOX) equipment, LOX storage, or LOX piping. Thoroughly clean joints in this area and leave them unsealed. 3.2 PREPARATION OF JOINTS ************************************************************************** NOTE: The proper preparation of joints with respect to size of joint opening, required cleanliness of concrete surfaces to be bonded, and proper separation of noncompatible materials from the joint sealant cannot be overemphasized. The same applies to storage, preparation, proportioning, mixing and placement of sealants. The neglect of any facet of these operations can result, and has resulted, in poor performance of the joint sealant. ************************************************************************** Immediately before the installation of the sealant, thoroughly clean the joints to remove all laitance, curing compound, filler, protrusions of hardened concrete, and old sealant from the sides and upper edges of the joint space to be sealed. 3.2.1 Existing Sealant Removal ************************************************************************** NOTE: Delete this paragraph if the joints have never been sealed and renumber the subsequent paragraphs. Waterblasters have been used successfully to remove sealants that still have some resilience. A nozzle that puts out a thin stream of water is required to cut the sealant loose from the joint walls. The concrete saw should not be used if it will widen the joint to a width greater than one inch. ************************************************************************** URS FOR EQM SECTION 32 01 19 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Cut loose the in-place sealant from both joint faces and to the depth shown on the drawings, using the [tractor-mounted routing equipment] [concrete saw ] [waterblaster] as specified in paragraph EQUIPMENT. Depth shall be sufficient to accommodate any separating or backup material that is required to maintain the depth of new sealant to be installed. Prior to further cleaning operations, remove all loose old sealant remaining in the joint opening by blowing with compressed air. Hand tools may be required to remove sealant from random cracks. Chipping, spalling, or otherwise damaging the concrete will not be allowed. 3.2.2 Sawing ************************************************************************** NOTE: Joints often need to be refaced or widened to provide vertical faces and remove damaged concrete. Care should be used when refacing or widening joints so that the joint's width does not exceed 25 mm (1 inch). If the joint width exceeds 25 mm (1 inch), rebuilding of the joint should be considered. All joint walls should be vertical. The edges should not be rounded or beveled unless required by design. ************************************************************************** 3.2.2.1 Refacing of Joints ************************************************************************** NOTE: If the joints have never been sealed, change the title of this paragraph to Facing of Joints and the appropriate words and sentences used. If "dry" sawing is used to face or reface the joints, the debris may be removed using compressed air. ************************************************************************** Accomplish [refacing] [facing] of joints using a concrete saw as specified in paragraph EQUIPMENT [to remove all residual old sealant and a minimum of concrete from the joint face to provide exposure of newly cleaned concrete, and, if required, to enlarge the joint opening to the width and depth shown on the drawings.] [to saw through sawed and filler-type joints to loosen and remove material until the joint is clean and open to the full specified width and depth.] Stiffen the blade with a sufficient number of suitable dummy (used) blades or washers. Thoroughly clean, immediately following the sawing operation, the joint opening using a water jet to remove all saw cuttings and debris. 3.2.2.2 Refacing of Random Cracks ************************************************************************** NOTE: A vertical spindle routing device may be used to clean random cracks. Random cracks that are approximately 25 mm (1 inch) wide may be sandblasted clean to prevent additional widening of the crack instead of sawing or routing. ************************************************************************** Accomplish sawing of the cracks using a power-driven concrete saw as specified in paragraph EQUIPMENT. The saw blade shall be 6 inches or less in diameter to enable the saw to follow the trace of the crack. Stiffen the blade, as necessary, with suitable dummy (or used) blades or washers. URS FOR EQM SECTION 32 01 19 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Immediately following the sawing operation, thoroughly clean the crack opening using a water jet to remove all saw cuttings and debris. Sandblasting ************************************************************************** NOTE: Sandblasting of joints may not be permitted under certain conditions. Blowing sand and dust may either violate atmospheric pollution statutes, or may drift into areas where it would be objectionable. When sandblasting is prohibited, cleaning the joints with a waterblaster or wire brushes may be substituted. Wire brushes usually do not clean as well as the sandblaster or waterblaster and should only be used for small areas. When wire brushes are used, attention should be given to ensure worn brushes are not used and that the joints are being adequately cleaned. When waterblasting is required instead of sandblasting, replace the word sandblasting with waterblasting. ************************************************************************** The newly exposed concrete joint faces and the pavement surfaces extending a minimum of 1/2 inch from the joint edges shall be [sandblasted] [waterblasted] clean. use a multiple-pass technique until the surfaces are free of dust, dirt, curing compound, filler, old sealant residue, or any foreign debris that might prevent the bonding of the sealant to the concrete. After final cleaning and immediately prior to sealing, blow out the joints with compressed air and leave them completely free of debris and water. 3.2.3 Back-Up Material When the joint opening is of a greater depth than indicated for the sealant depth, plug or seal off the lower portion of the joint opening using a back-up material to prevent the entrance of the sealant below the specified depth. Take care to ensure that the backup material is placed at the specified depth and is not stretched or twisted during installation. Bond Breaking Tape Where inserts or filler materials contain bitumen, or the depth of the joint opening does not allow for the use of a backup material, insert a bond breaker separating tape to prevent incompatibility with the filler materials and three-sided adhesion of the sealant. Securely bond the tape to the bottom of the joint opening so it will not float up into the new sealant. 3.2.4 Rate of Progress of Joint Preparation Limit the stages of joint preparation, which include sandwaterblasting, air pressure cleaning and placing of the back-up material to only that lineal footage that can be sealed during the same day. 3.3 PREPARATION OF SEALANT ************************************************************************** NOTE: Delete the inappropriate paragraphs. ************************************************************************** URS FOR EQM SECTION 32 01 19 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.3.1 TYMX989345A FA3002-09-D-0002 TG02 Hot-Poured Sealants Sealants conforming to [ASTM D6690] [ASTM D7116] shall not be heated in excess of the safe heating temperature recommended by the manufacturer as shown on the sealant containers. Withdraw and waste sealant that has been overheated or subjected to application temperatures for over 4 hours or that has remained in the applicator at the end of the day's operation. 3.3.2 Type M Sealants Inspect the FS SS-S-200 Type M sealant components and containers prior to use. Reject any materials that contain water, hard caking of any separated constituents, nonreversible jell, or materials that are otherwise unsatisfactory. Settlement of constituents in a soft mass that can be readily and uniformly remixed in the field with simple tools will not be cause for rejection. Prior to transfer of the components from the shipping containers to the appropriate reservoir of the application equipment, thoroughly mix the materials to ensure homogeneity of the components and incorporation of all constituents at the time of transfer. When necessary for remixing prior to transfer to the application equipment reservoirs, warm the components to a temperature not to exceed 90 degrees F by placing the components in heated storage or by other approved methods but in no case shall the components be heated by direct flame, or in a single walled kettle, or a kettle without an oil bath. Type H Sealants Mix the FS SS-S-200 Type H sealant components either in the container furnished by the manufacturer or a cylindrical metal container of volume approximately 50 percent greater than the package volume. Thoroughly mix the base material in accordance with the manufacturer's instructions. The cure component shall then be slowly added during continued mixing until a uniform consistency is obtained. 3.3.2 Single-Component, Cold-Applied Sealants Inspect the ASTM D5893/D5893M sealant and containers prior to use. Reject any materials that contain water, hard caking of any separated constituents, nonreversible jell, or materials that are otherwise unsatisfactory. Settlement of constituents in a soft mass that can be readily and uniformly remixed in the field with simple tools will not be cause for rejection. 3.4 3.4.1 INSTALLATION OF SEALANT Time of Application Seal joints immediately following final cleaning of the joint walls and following the placement of the separating or backup material. Open joints, that cannot be sealed under the conditions specified, or when rain interrupts sealing operations shall be recleaned and allowed to dry prior to installing the sealant. 3.4.2 Sealing Joints ************************************************************************** NOTE: Joints should be slightly underfilled to preclude extrusion of the material above the surface URS FOR EQM SECTION 32 01 19 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 of the pavement at summertime temperatures. For airfield pavements, the sealant should be recessed 3 mm (1/8 inch) below the pavement surface; for roads, streets and parking lots, the sealant should be recessed 6 mm (1/4 inch). For pavements that receive tracked vehicle traffic, the sealant should be recessed a minimum of 6 mm (1/4 inch) below the pavement surface after it has cured or cooled to ambient temperature. ************************************************************************** Immediately preceding, but not more than 50 feet ahead of the joint sealing operations, perform a final cleaning with compressed air. Fill the joints from the bottom up to [1/8] [1/4]1/4 to 1/16 inch plus or minus 1/16 inch below the pavement surface. Remove and discard excess or spilled sealant from the pavement by approved methods. Install the sealant in such a manner as to prevent the formation of voids and entrapped air. In no case shall gravity methods or pouring pots be used to install the sealant material. Traffic shall not be permitted over newly sealed pavement until authorized by the Contracting Officer. When a primer is recommended by the manufacturer, apply it evenly to the joint faces in accordance with the manufacturer's instructions. Check the joints frequently to ensure that the newly installed sealant is cured to a tack-free condition within the time specified. 3.5 3.5.1 INSPECTION Joint Cleaning Inspect joints during the cleaning process to correct improper equipment and cleaning techniques that damage the concrete pavement in any manner. Cleaned joints will be approved prior to installation of the separating or back-up material and joint sealant. 3.5.2 Joint Sealant Application Equipment Inspect the application equipment to ensure conformance to temperature requirements, proper proportioning and mixing (if two-component sealant) and proper installation. Evidences of bubbling, improper installation, failure to cure or set will be cause to suspend operations until causes of the deficiencies are determined and corrected. 3.5.3 Joint Sealant Inspect the joint sealant for proper rate of cure and set, bonding to the joint walls, cohesive separation within the sealant, reversion to liquid, entrapped air and voids. Sealants exhibiting any of these deficiencies at any time prior to the final acceptance of the project shall be removed from the joint, wasted, and replaced as specified herein at no additional cost to the Government. 3.6 CLEAN-UP Upon completion of the project, remove all unused materials from the site and leave the pavement in a clean condition. -- End of Section -- URS FOR EQM SECTION 32 01 19 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 11 23 (August 2008) --------------------------Preparing Activity: USACE Superseding UFGS-32 11 23 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE ************************************************************************** NOTE: This guide specification covers the requirements for base course to be used directly under bituminous pavement courses. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: This guide specification is applicable to base courses placed directly beneath bituminous surface courses. The following must be taken into consideration when editing this specification. a. The material in this specification and on the drawings should be referred to as "aggregate base course (ABC)" whenever a base course material with a California Bearing Ratio (CBR) of 80 is required. "Aggregate Base Course" should be retained in the title and the rest of the specification should be edited accordingly to retain the information necessary for this material. b. The material in this specification and on the drawings should be referred to as "graded-crushed URS FOR EQM SECTION 32 11 23 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 aggregate base course (GCA)" wherever a base material with a CBR of 100 is required. "Graded-Crushed Aggregate Base Course" should be retained in the title and the rest of the specification should be edited accordingly to retain the information necessary for this material. c. When this specification is to be used in projects that require both types of materials, the title of this specification should be "Aggregate and/or Graded-Crushed Aggregate Base Course". Care must then be taken to assure that the drawings clearly call out which material is being used in any particular place and that this specification is edited to retain the information for both types of materials. If only a small amount of one of these types of materials is needed for the project, consideration should be made to determine if only one of these materials should be specified and the design adjusted. ************************************************************************** 1.1 UNIT PRICES ************************************************************************** NOTE: Delete unit price paragraphs when the work is covered by a lump-sum contract price. ************************************************************************** 1.1.1 Measurement ************************************************************************** NOTE: Delete the method of measurement paragraph not applicable to job conditions. The provision for stockpiling should be retained or deleted, as applicable, and the brackets will be removed. ************************************************************************** 1.1.1.1 Area Measure the quantity of [ABC] [and] [GCA] completed and accepted, as determined by the Contracting Officer, in square yards. 1.1.1.2 Volume Measure the quantity of [ABC] [and] [GCA] completed and accepted, as determined by the Contracting Officer, in cubic yards. The volume of material in-place and accepted will be determined by the average job thickness obtained in accordance with paragraph THICKNESS CONTROL and the dimensions shown. 1.1.1.3 Weight The tonnage of [ABC] [and] [GCA] material will be the number of tons of aggregate, [placed and accepted in the completed course][plus the amount] [placed in authorized stockpiles], as determined by the Contracting Officer. Deductions shall be made for any material wasted, unused, rejected, or used for convenience of the Contractor, and for water exceeding specified amount at time of weighing. URS FOR EQM SECTION 32 11 23 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.1.2 TYMX989345A FA3002-09-D-0002 TG02 Payment for Quantities Quantities of [ABC] [and] [GCA], determined as specified above, will be paid for at the respective contract unit prices, which shall constitute full compensation for the construction and completion of the [ABC] [and] [ GCA]. 1.1.3 Payment for Stabilization of Underlying Course Stabilization of cohesionless subgrade or subbase courses, as specified in paragraph PREPARATION OF UNDERLYING COURSE, will be paid for as a special item on a tonnage basis. This tonnage price will include the price of extra manipulation as required. 1.1.4 Waybills and Delivery Tickets Before the final statement is allowed, file certified waybills and certified delivery tickets for all aggregates actually used, as specified in the Submittals paragraph. 1.2 REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) AASHTO T 180 (2010) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop AASHTO T 224 (2010) Standard Method of Test for Correction for Coarse Particles in the Soil Compaction Test URS FOR EQM SECTION 32 11 23 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM INTERNATIONAL (ASTM) ASTM C117 (2013) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing ASTM C127 (2012) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate ASTM C128 (2012) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Fine Aggregate ASTM C131 (2006) Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine ASTM C136 (2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates ASTM C29/C29M (2009) Standard Test Method for Bulk Density ("Unit Weight") and Voids in Aggregate ASTM C88 (2013) Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate ASTM D1556 (2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method ASTM D1557 (2012) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3) ASTM D2167 (2008) Density and Unit Weight of Soil in Place by the Rubber Balloon Method ASTM D2487 (2011) Soils for Engineering Purposes (Unified Soil Classification System) ASTM D422 (1963; R 2007; E 2014; E 2014) Particle-Size Analysis of Soils ASTM D4318 (2010; E 2014) Liquid Limit, Plastic Limit, and Plasticity Index of Soils ASTM D5821 (2013) Standard Test Method for Determining the Percentage of Fractured Particles in Coarse Aggregate ASTM D6938 (2010) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth) URS FOR EQM SECTION 32 11 23 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates ASTM E11 (2013) Wire Cloth and Sieves for Testing Purposes 1.3 DEFINITIONS For the purposes of this specification, the following definitions apply. Aggregate Base Course Aggregate base course (ABC) is well graded, durable aggregate uniformly moistened and mechanically stabilized by compaction. 1.3.1 Graded-Crushed Aggregate Base Course Graded-crushed aggregate (GCA) base course is well graded, crushed, durable aggregate uniformly moistened and mechanically stabilized by compaction. GCA is similar to ABC, but it has more stringent requirements and it produces a base course with higher strength and stability. 1.3.2 Degree of Compaction Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum laboratory dry density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum dry density. Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve are expressed as a percentage of the laboratory maximum dry density in accordance with AASHTO T 180 Method D and corrected with AASHTO T 224. 1.4 SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office URS FOR EQM SECTION 32 11 23 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-03 Product Data Plant, Equipment, and Tools Waybills and Delivery Tickets SD-06 Test Reports Sampling and Testing[; G][; G, [_____]] Field Density Tests[; G][; G, [_____]] 1.5 QUALITY ASSURANCE Sampling and testing are the responsibility of the Contractor and performed by a testing laboratory approved in accordance with Section 01 45 00.00 10 QUALITY CONTROL. Work requiring testing will not be permitted until the testing laboratory has been inspected and approved. Test the materials to establish compliance with the specified requirements; perform testing at the specified frequency. The Contracting Officer may specify the time and location of the tests. Furnish copies of test results to the Contracting Officer within 24 hours of completion of the tests. 1.5.1 Sampling Take samples for laboratory testing in conformance with ASTM D75/D75M. When deemed necessary, the sampling will be observed by the Contracting Officer. 1.5.2 Tests Perform the following tests in conformance with the applicable standards listed. 1.5.2.1 Sieve Analysis ************************************************************************** NOTE: Testing in accordance with ASTM D422 will be required when the materials need to be tested for URS FOR EQM SECTION 32 11 23 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the percentage passing the 0.02 mm particle size. See paragraph Gradation Requirements. ************************************************************************** Make sieve analysis in conformance with ASTM C117 and ASTM C136. Sieves shall conform to ASTM E11. [Particle-size analysis of the soils shall also be completed in conformance with ASTM D422]. 1.5.2.2 Liquid Limit and Plasticity Index Determine liquid limit and plasticity index in accordance with ASTM D4318. 1.5.2.3 Moisture-Density Determinations ************************************************************************** NOTE: ASTM D1557 will be used for maximum density determinations, if gradation 3 is used (less than 30 percent retained on the 19 mm (3/4") sieve). AASHTO T 180, Method D will be used for the maximum density determinations, if gradations 1 or 2 are used (more than 30 percent retained on the 19 mm (3/4") sieve). ************************************************************************** Determine the laboratory maximum dry density and optimum moisture content in accordance with [ASTM D1557] or [AASHTO T 180, Method D and corrected with AASHTO T 224]. 1.5.2.4 Field Density Tests Measure field density in accordance with ASTM D1556, ASTM D2167 or ASTM D6938. [For the method presented in ASTM D1556 use the base plate as shown in the drawing.] [ For the method presented in ASTM D6938 check the calibration curves and adjust them, if necessary, using only the sand cone method as described in paragraph Calibration, of the ASTM publication. Tests performed in accordance with ASTM D6938 result in a wet unit weight of soil, and ASTM D6938 shall be used to determine the moisture content of the soil. The calibration curves furnished with the moisture gauges shall also be checked along with density calibration checks as described in ASTM D6938. The calibration checks of both the density and moisture gauges shall be made by the prepared containers of material method, as described in paragraph Calibration of ASTM D6938, on each different type of material being tested at the beginning of a job and at intervals as directed.] a. Submit certified copies of test results for approval not less than [30] [_____] days before material is required for the work. b. Submit calibration curves and related test results prior to using the device or equipment being calibrated. c. Submit copies of field test results within [24] [_____] hours after the tests are performed. 1.5.2.5 Wear Test Perform wear tests on [ABC] [and] [GCA] course material in conformance with ASTM C131. URS FOR EQM SECTION 32 11 23 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.5.2.6 TYMX989345A FA3002-09-D-0002 TG02 Soundness ************************************************************************** NOTE: Retain this paragraph only for graded-crushed aggregate base course. ************************************************************************** Perform soundness tests on GCA in accordance with ASTM C88. Weight of Slag ************************************************************************** NOTE: This paragraph will be omitted when it is highly unlikely that slag will be supplied as base course material. ************************************************************************** Determine weight per cubic foot of slag in accordance with ASTM C29/C29M on the [ABC] [and] [GCA] course material. 1.5.3 Testing Frequency 1.5.3.1 Initial Tests ************************************************************************** NOTE: The 0.02 mm sieve analysis requirements will be included when frost susceptibility concerns exist. ************************************************************************** Perform one of each of the following tests, on the proposed material prior to commencing construction, to demonstrate that the proposed material meets all specified requirements when furnished. If materials from more than one source are going to be utilized, this testing shall be completed for each source. a. Sieve Analysis [including the No. 635 sieve]. b. Liquid limit and plasticity index. c. Moisture-density relationship. d. Wear. [ e. Soundness.] [ f. Weight per cubic foot of Slag.] g. [_____]. 1.5.3.2 In Place Tests ************************************************************************** NOTE: If recycled concrete aggregate (RCA) is proposed as an aggregate source, include the last bracketed sentence ************************************************************************** Perform each of the following tests on samples taken from the placed and compacted [ABC] [and] [GCA]. Samples shall be taken and tested at the rates indicated. [Perform sampling and testing of recycled concrete aggregate at twice the specified frequency until the material uniformity is URS FOR EQM SECTION 32 11 23 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 established.] a. Perform density tests on every lift of material placed and at a frequency of one set of tests for every [ 250 square yards] [_____], or portion thereof, of completed area. b. Perform sieve analysis [including the No. 635 sieve] on every lift of material placed and at a frequency of one sieve analysis for every [ 500 square yards] [_____], or portion thereof, of material placed. c. Perform liquid limit and plasticity index tests at the same frequency as the sieve analysis. d. Measure the total thickness of the base course at intervals, in such a manner as to ensure one measurement for each [500] [_____] square yards of base course. Measurements shall be made in 3 inch diameter test holes penetrating the base course. 1.5.4 Approval of Material Select the source of the material [30] [_____] days prior to the time the material will be required in the work. Tentative approval of material will be based on initial test results. Final approval of the materials will be based on sieve analysis, liquid limit, and plasticity index tests performed on samples taken from the completed and fully compacted course(s). 1.6 ENVIRONMENTAL REQUIREMENTS ************************************************************************** NOTE: This paragraph may be deleted in localities where freezing temperatures do not occur, and elsewhere when it is definitely known that the work will not be carried on during periods when such temperatures are to be expected. Otherwise, this requirement will be retained, but the protective measures specified may be modified to suit local conditions and individual project requirements. ************************************************************************** Perform construction when the atmospheric temperature is above 35 degrees F. When the temperature falls below 35 degrees F, protect all completed areas by approved methods against detrimental effects of freezing. Correct completed areas damaged by freezing, rainfall, or other weather conditions to meet specified requirements. PART 2 2.1 PRODUCTS PLANT, EQUIPMENT, AND TOOLS ************************************************************************** NOTE: If desirable, requirements for types of equipment applicable to methods of construction based on local conditions will be included. ************************************************************************** All plant, equipment, and tools used in the performance of the work will be subject to approval before the work is started and shall be maintained in satisfactory working condition at all times. Submit a list of proposed equipment, including descriptive data. Provide adequate equipment having URS FOR EQM SECTION 32 11 23 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the capability of producing the required compaction, meeting grade controls, thickness control, and smoothness requirements as set forth herein. 2.2 AGGREGATES ************************************************************************** NOTE: Material requirements from State or other local highway agency specifications may be incorporated in contract documents for constructing aggregate base course for roads, streets, or similar use pavements if the following conditions are met: a. Percentage of material by weight passing the 0.075 mm (No. 200) sieve will not exceed 8. b. Where local conditions dictate a non-frost-susceptible material, particles passing the 0.02 mm particle size will not exceed 3 percent. c. Portion of the material passing the 0.425 mm (No. 40) sieve must have a liquid limit not greater than 25 and a plasticity index not greater than 5. d. Projects requiring not more than 600 cubic meters (750 cubic yards) of material must be approved by the Division Engineer. e. Projects requiring more than 600 cubic meters (750 cubic yards) must be approved by AFCEC, Navy EFD, or TSMCX prior to incorporation in the contract documents. A copy of the specifications or proper reference thereto and information regarding traffic conditions and facilities to be paved will be submitted to the AFCEC, Navy EFD or TSMCX, with the request for approval. f. Materials to be used for GCA must also meet the specified L.A. Abrasion and Sulfate Soundness requirements. g. Rounded aggregates (such as river-run gravel) will not be allowed since they do not provide sufficient interlocking action to produce the desired strengths and durability. ************************************************************************** Provide [ABC] [and] [GCA] consisting of clean, sound, durable particles of crushed stone, crushed slag, crushed gravel,[crushed recycled concrete,] angular sand, or other approved material. [ABC shall be free of lumps of clay, organic matter, and other objectionable materials or coatings.] [GCA shall be free of silt and clay as defined by ASTM D2487, organic matter, and other objectionable materials or coatings.] The portion retained on the No. 4 sieve is known as coarse aggregate; that portion passing the No. 4 sieve is known as fine aggregate. 2.2.1 Coarse Aggregate Provide coarse aggregates with angular particles of uniform density. URS FOR EQM SECTION 32 11 23 Page 10 When 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the coarse aggregate is supplied from more than one source, aggregate from each source shall meet the specified requirements and shall be stockpiled separately. a. Crushed Gravel: Crushed gravel manufactured by crushing gravels, and meets all the requirements specified below. b. Crushed Stone: Provide crushed stone consisting of freshly mined quarry rock, meeting all the requirements specified below. ************************************************************************** NOTE: Verify the subgrade soil contains less than 0.3 percent of sulfates, to prevent expansive ettringite reaction with the recycled concrete. See UFC 3-250-11, Appendix C for testing procedure. Otherwise, delete recycled concrete option. Do not permit recycled concrete aggregate (RCA) to be used in a airfield pavement section without evaluating for Alkali-Silica Reactivity (ASR). See IPRF-01-G-002-03-5, "Evaluation, Design and Construction Techniques for Airfield Concrete Pavement Used as Recycled Material for Base." For Air Force porjects, perform risk assessment in accordance with ETL 07-06, "Risk Assessment Procedures for Recycling Portland Cement Concrete (PCC) Suffering From Alkali-Silica Reaction (ASR) in Airfield Pavement Structures." ************************************************************************** c. Crushed Recycled Concrete: Provide crushed recycled concrete consisting of previously hardened portland cement concrete or other concrete containing pozzolanic binder material. The recycled material shall be free of all reinforcing steel, bituminous concrete surfacing, and any other foreign material and shall be crushed and processed to meet the required gradations for coarse aggregate. Reject recycled concrete aggregate exceeding this value. Crushed recycled concrete must meet all other applicable requirements specified below. d. Crushed Slag: Crushed slag is an air-cooled blast-furnace product having an air dry unit weight of not less than 70 pcf as determined by ASTM C29/C29M, and meets all the requirements specified below. Aggregate Base Course ABC coarse aggregate shall not show more than 50 percent loss when subjected to the Los Angeles abrasion test in accordance with ASTM C131. The amount of flat and elongated particles shall not exceed 30 percent. A flat particle is one having a ratio of width to thickness greater than 3; an elongated particle is one having a ratio of length to width greater than 3. In the portion retained on each sieve specified, the crushed aggregates shall contain at least 50 percent by weight of crushed pieces having two or more freshly fractured faces determined in accordance with ASTM D5821. When two fractures are contiguous, the angle between planes of the fractures must be at least 30 degrees in order to count as two fractured faces. Crushed gravel shall be manufactured from gravel particles 50 percent of which, by weight, are retained on the maximum size sieve listed in TABLE 1. URS FOR EQM SECTION 32 11 23 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.2.1.1 TYMX989345A FA3002-09-D-0002 TG02 Graded-Crushed Aggregate Base Course ************************************************************************** NOTE: The percentages of wear and soundness applicable to the specific job will be specified. A wear value of 40 will be used except that a value up to 50 percent may be used where local experience indicates that the material is satisfactory. ************************************************************************** GCA coarse aggregate shall not show more than [40] [50] percent loss when subjected to the Los Angeles abrasion test in accordance with ASTM C131. GCA coarse aggregate shall not exhibit a loss greater than 18 percent weighted average, at five cycles, when tested for soundness in magnesium sulfate, or 12 percent weighted average, at five cycles, when tested in sodium sulfate in accordance with ASTM C88. The amount of flat and elongated particles shall not exceed 20 percent for the fraction retained on the 1/2 inch sieve nor 20 percent for the fraction passing the 1/2 inch sieve. A flat particle is one having a ratio of width to thickness greater than 3; an elongated particle is one having a ratio of length to width greater than 3. In the portion retained on each sieve specified, the crushed aggregate shall contain at least 90 percent by weight of crushed pieces having two or more freshly fractured faces determined in accordance with ASTM D5821. When two fractures are contiguous, the angle between planes of the fractures must be at least 30 degrees in order to count as two fractured faces. Crushed gravel shall be manufactured from gravel particles 90 percent of which by weight are retained on the maximum size sieve listed in TABLE 1. 2.2.2 Fine Aggregate Fine aggregates shall be angular particles of uniform density. When the fine aggregate is supplied from more than one source, aggregate from each source shall meet the specified requirements. Aggregate Base Course ABC fine aggregate shall consist of screenings, angular sand, crushed recycled concrete fines, or other finely divided mineral matter processed or naturally combined with the coarse aggregate. 2.2.2.1 Graded-Crushed Aggregate Base Course ************************************************************************** NOTE: The GCA fine aggregate will be entirely the product of crushing, but need not be of the same material crushed for the coarse aggregate. Retain only the statement describing the method of crushing desired. ************************************************************************** Provide GCA fine aggregate consisting of angular particles produced by crushing stone, slag, [recycled concrete,] or gravel that meets the requirements for wear and soundness specified for GCA coarse aggregate. [ Fine aggregate shall be produced by crushing only particles larger than No. 4 sieve in size. The fine aggregate shall contain at least 90 percent by weight of particles having two or more freshly fractured faces in the portion passing the No. 4 sieve and retained on the No. 10 sieve, and in URS FOR EQM SECTION 32 11 23 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the portion passing the No. 10 sieve and retained on the No. 40 sieve.] [Fine aggregate shall be manufactured from gravel particles 95 percent of which by weight are retained on the 1/2 inch sieve.] 2.2.3 Gradation Requirements ************************************************************************** NOTE: Specify the gradation or gradations applicable to the specific job. The maximum size of aggregates will be specified in the blank space. The frost susceptibility requirement will be deleted in areas where the material is not subject to frost action. On the basis of local conditions, the percentage passing the 0.075 mm (No. 200) sieve may be further restricted to help control the amount of particles passing the 0.02 mm (No. 635) particle size. However, the cleaner gradations can have reduced stability. If more than one gradation is maintained, the designer must edit this specification and/or the project drawings to make sure it is evident where these different gradations are to be used. ************************************************************************** Apply the specified gradation requirements to the completed base course. The aggregates shall be continuously well graded within the limits specified in TABLE 1. Sieves shall conform to ASTM E11. TABLE 1. GRADATION OF AGGREGATES Percentage by Weight Passing Square-Mesh Sieve Sieve Designation No. 2 No. 3 2 inch 100 --- --- 1-1/2 inch 70-100 100 --- 1 inch 45-80 60-100 100 1/2 inch 30-60 30-65 40-70 No. 4 20-50 20-50 20-50 No. 10 15-40 15-40 15-40 No. 40 5-25 5-25 5-25 No. 200 0-8 0-8 0-8 NOTE 1: Particles having diameters less than No. 635 shall not be in excess of 3 percent by weight of the total sample tested. URS FOR EQM SECTION 32 11 23 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TABLE 1. TYMX989345A FA3002-09-D-0002 TG02 GRADATION OF AGGREGATES Percentage by Weight Passing Square-Mesh Sieve Sieve Designation No. 2 No. 3 NOTE 2: The values are based on aggregates of uniform specific gravity. If materials from different sources are used for the coarse and fine aggregates, they shall be tested in accordance with ASTM C127 and ASTM C128 to determine their specific gravities. If the specific gravities vary by more than 10 percent, the percentages passing the various sieves shall be corrected as directed by the Contracting Officer. 2.3 LIQUID LIMIT AND PLASTICITY INDEX ************************************************************************** NOTE: Aggregate should be nonplastic or as nearly so as possible. Values shown are the absolute maximum allowable values for liquid limit and plasticity index. ************************************************************************** Apply liquid limit and plasticity index requirements to the completed course and to any component that is blended to meet the required gradation. The portion of any component or of the completed course passing the No. 40 sieve shall be either nonplastic or have a liquid limit not greater than 25 and a plasticity index not greater than 5. PART 3 3.1 EXECUTION GENERAL REQUIREMENTS When the [ABC] [or] [GCA] is constructed in more than one layer, clean the previously constructed layer of loose and foreign matter by sweeping with power sweepers or power brooms, except that hand brooms may be used in areas where power cleaning is not practicable. Provide adequate drainage during the entire period of construction to prevent water from collecting or standing on the working area. Provide line and grade stakes as necessary for control. Grade stakes shall be in lines parallel to the centerline of the area under construction and suitably spaced for string lining. 3.2 OPERATION OF AGGREGATE SOURCES ************************************************************************** NOTE: Investigate the availability of Government-owned aggregate source that meets the specification requirement. If none is available, delete material in the brackets. ************************************************************************** Clearing, stripping, and excavating are the responsibility of the Contractor. Operate the aggregate sources to produce the quantity and quality of materials meeting the specified requirements in the specified time limit. [Upon completion of the work, the aggregate sources on Government property shall be conditioned to drain readily and shall be left URS FOR EQM SECTION 32 11 23 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 in a satisfactory condition.]Aggregate sources on private lands shall be conditioned in agreement with local laws or authorities. 3.3 STOCKPILING MATERIAL ************************************************************************** NOTE: In cases where material previously stockpiled under a separate contract is utilized in the construction of the base course, this requirement will be included in the specifications. When applicable, a separate item of work will be shown in the bid schedule to provide for the use of previously stockpiled materials. ************************************************************************** Clear and level storage sites prior to stockpiling of material. Stockpile all materials, including approved material available from excavation and grading, in the manner and at the locations designated. Aggregates shall be stockpiled on the cleared and leveled areas designated by the Contracting Officer to prevent segregation. Materials obtained from different sources shall be stockpiled separately. 3.4 PREPARATION OF UNDERLYING COURSE ************************************************************************** NOTE: Only the reference to the specification section that covers the preparation of the underlying course will be retained; other references will be deleted. The surface of the cohesionless subgrade or subbase may require stabilization prior to placement of the base course. This may be accomplished by compacting a layer of crushed aggregate into the surface. It may also be obtained by methods based on local experience. The additional crushed aggregate will be considered as part of the underlying course and may be paid for or included in the specification section that covers the preparation of subgrade or subbase for the particular project. ************************************************************************** Prior to constructing the base course(s), the underlying course or subgrade shall be cleaned of all foreign substances. At the time of construction of the base course(s), the underlying course shall contain no frozen material. The surface of the underlying course or subgrade shall meet specified compaction and surface tolerances. The underlying course shall conform to [Section 31 00 00 EARTHWORK][Section 32 11 16 SUBBASE COURSES]. Ruts or soft yielding spots in the underlying courses, areas having inadequate compaction, and deviations of the surface from the requirements set forth herein shall be corrected by loosening and removing soft or unsatisfactory material and by adding approved material, reshaping to line and grade, and recompacting to specified density requirements. For cohesionless underlying courses containing sands or gravels, as defined in ASTM D2487, the surface shall be stabilized prior to placement of the base course(s). Stabilization shall be accomplished by mixing [ABC] [or] [GCA] into the underlying course and compacting by approved methods. The stabilized material shall be considered as part of the underlying course and shall meet all requirements of the underlying course. The finished underlying course shall not be disturbed by traffic or other operations and URS FOR EQM SECTION 32 11 23 Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 shall be maintained in a satisfactory condition until the base course is placed. 3.5 3.5.1 INSTALLATION Mixing the Materials ************************************************************************** NOTE: More details of applicable methods of placing, mixing, and spreading will be included when appropriate. ************************************************************************** Mix the coarse and fine aggregates in a stationary plant, or in a traveling plant or bucket loader on an approved paved working area. Make adjustments in mixing procedures or in equipment, as directed, to obtain true grades, to minimize segregation or degradation, to obtain the required water content, and to insure a satisfactory base course meeting all requirements of this specification. 3.5.2 Placing Place the mixed material on the prepared subgrade or subbase in layers of uniform thickness with an approved spreader. When a compacted layer 6 inches or less in thickness is required, place the material in a single layer. When a compacted layer in excess of 6 inches is required, place the material in layers of equal thickness. No layer shall be thicker than 6 inches or thinner than 3 inches when compacted. The layers shall be so placed that when compacted they will be true to the grades or levels required with the least possible surface disturbance. Where the base course is placed in more than one layer, the previously constructed layers shall be cleaned of loose and foreign matter by sweeping with power sweepers, power brooms, or hand brooms, as directed. Such adjustments in placing procedures or equipment shall be made as may be directed to obtain true grades, to minimize segregation and degradation, to adjust the water content, and to insure an acceptable base course. 3.5.3 Grade Control The finished and completed base course shall conform to the lines, grades, and cross sections shown. Underlying material(s) shall be excavated and prepared at sufficient depth for the required base course thickness so that the finished base course and the subsequent surface course will meet the designated grades. 3.5.4 Edges of Base Course ************************************************************************** NOTE: The extra width of material is provided for a working platform during construction. This will provide the paving equipment a solid surface to track on and will help ensure a smoother pavement. ************************************************************************** The base course(s) shall be placed so that the completed section will be a minimum of [2] [_____] feet wider, on all sides, than the next layer that will be placed above it. Additionally, place approved fill material along the outer edges of the base course in sufficient quantities to compact to the thickness of the course being constructed, or to the thickness of each URS FOR EQM SECTION 32 11 23 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 layer in a multiple layer course, allowing in each operation at least a 2 foot width of this material to be rolled and compacted simultaneously with rolling and compacting of each layer of base course. If this base course material is to be placed adjacent to another pavement section, then the layers for both of these sections shall be placed and compacted along this edge at the same time. 3.5.5 Compaction ************************************************************************** NOTE: Appropriate percentage will be inserted in the first bracketed blank. Cohesionless materials are often free-draining; as such, the optimum water content is normally limited to the maximum water content the material will retain. This is usually evidenced by free water running from the mold during compaction testing. ************************************************************************** Compact each layer of the base course, as specified, with approved compaction equipment. Maintain water content during the compaction procedure to within plus or minus [2] [_____] percent of the optimum water content determined from laboratory tests as specified in this Section. Begin rolling at the outside edge of the surface and proceed to the center, overlapping on successive trips at least one-half the width of the roller. Alternate trips of the roller shall be slightly different lengths. Speed of the roller shall be such that displacement of the aggregate does not occur. In all places not accessible to the rollers, the mixture shall be compacted with hand-operated power tampers. Continue compaction until each layer has a degree of compaction that is at least [100] [_____] percent of laboratory maximum density through the full depth of the layer. Make such adjustments in compacting or finishing procedures as may be directed to obtain true grades, to minimize segregation and degradation, to reduce or increase water content, and to ensure a satisfactory base course. Any materials that are found to be unsatisfactory shall be removed and replaced with satisfactory material or reworked, as directed, to meet the requirements of this specification. 3.5.6 Thickness ************************************************************************** NOTE: When base courses are constructed less than 150 mm (6 inches) in total thickness, a deficiency of 13 mm (1/2 inch) in thickness of any area of such paving is considered excessive. Applicable to job conditions, the thickness-tolerance provisions may be modified as required, restricting all deficiencies to not over 6 mm (1/4 inch). ************************************************************************** Construct the compacted thickness of the base course as indicated. No individual layer shall be thicker than 6 inches nor be thinner than 3 inches in compacted thickness. The total compacted thickness of the base course(s) shall be within 1/2 inch of the thickness indicated. Where the measured thickness is more than 1/2 inch deficient, correct such areas by scarifying, adding new material of proper gradation, reblading, and recompacting as directed. Where the measured thickness is more than 1/2 inch thicker than indicated, the course shall be considered as conforming to the specified thickness requirements. Average job thickness shall be URS FOR EQM SECTION 32 11 23 Page 17 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the average of all thickness measurements taken for the job, but shall be within 1/4 inch of the thickness indicated. The total thickness of the base course shall be measured at intervals in such a manner as to ensure one measurement for each [500] [_____] square yards of base course. Measurements shall be made in 3 inch diameter test holes penetrating the base course. Proof Rolling ************************************************************************** NOTE: Drawings should be checked to ensure that any supplementary information required by this paragraph has been shown and that there is no conflict between the drawings and the specifications. Proof rolling is only applicable for flexible airfield pavement (see UFC 3-260-02). This paragraph will be deleted from all project specifications for courses under road pavement and under rigid airfield pavement unless it is specifically required by the design engineer. Proof rolling is not needed for airfield shoulder pavements. Air Force Bases: Proof roll each layer of base course of Type A traffic areas and the center 23 meters (75 feet) of heavy, modified heavy, and medium load runways with 30 coverages. Navy and Marine Corps Airfields: Proof roll top of completed base course on center 12 meters (40 feet) of taxiways and on center 30.5 meters (100 feet) of runways with 8 coverages. Apply 4 coverages to all other paved areas, exclusive of runway overrun and blast protection areas. Army Airfields: On Class IV airfields with runways greater than 1525 meters (5000 feet), proof roll each layer of base course in Type A traffic areas and center 23 meters (75 feet) of runways with 30 coverages. ************************************************************************** Proof rolling of the areas indicated shall be in addition to the compaction specified and shall consist of the application of [_____] coverages with a heavy pneumatic-tired roller having four or more tires, each loaded to a minimum of 30,000 pounds and inflated to a minimum of 125 psi. In areas designated, apply proof rolling to the top of the underlying material on which the base course is laid and to each layer of base course [top of the completed [ABC] [GCA] course]. Maintain water content of the underlying material at optimum or at the percentage directed from start of compaction to completion of proof rolling of that layer. Water content of each layer of the base course shall be maintained at the optimum percentage directed from start of compaction to completion of proof rolling. Any base course materials or any underlying materials that produce unsatisfactory results by proof rolling shall be removed and replaced with satisfactory materials, recompacted and proof rolled to meet these specifications. URS FOR EQM SECTION 32 11 23 Page 18 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.5.7 TYMX989345A FA3002-09-D-0002 TG02 Finishing The surface of the top layer of base course shall be finished after [final compaction] [and] [proof rolling] by cutting any overbuild to grade and rolling with a steel-wheeled roller. Thin layers of material shall not be added to the top layer of base course to meet grade. If the elevation of the top layer of base course is 1/2 inch or more below grade, then the top layer should be scarified to a depth of at least 3 inches and new material shall be blended in [and compacted] [, compacted and proof rolled] to bring to grade. Adjustments to rolling and finishing procedures shall be made as directed to minimize segregation and degradation, obtain grades, maintain moisture content, and insure an acceptable base course. Should the surface become rough, corrugated, uneven in texture, or traffic marked prior to completion, the unsatisfactory portion shall be scarified, reworked and recompacted or it shall be replaced as directed. 3.5.8 Smoothness The surface of the top layer shall show no deviations in excess of 3/8 inch when tested with a 12 foot straightedge. Take measurements in successive positions parallel to the centerline of the area to be paved. Measurements shall also be taken perpendicular to the centerline at [50] [_____] foot intervals. Deviations exceeding this amount shall be corrected by removing material and replacing with new material, or by reworking existing material and compacting it to meet these specifications. 3.6 TRAFFIC ************************************************************************** NOTE: Traffic will not be allowed on any base course placed for airfield pavements. For roads, traffic should only be allowed on the base courses when it cannot be diverted elsewhere; but precautions should be taken to limit the traffic and keep heavy equipment off. Any damage caused by traffic should be repaired to meet these specification requirements. Designer will choose the appropriate bracketed information. ************************************************************************** [Do not allow traffic on the completed base course.] [Completed portions of the base course may be opened to limited traffic, provided there is no marring or distorting of the surface by the traffic. Heavy equipment shall not be permitted except when necessary to construction, and then the area shall be protected against marring or damage to the completed work.] 3.7 MAINTENANCE Maintain the base course in a satisfactory condition until the full pavement section is completed and accepted. Maintenance shall include immediate repairs to any defects and shall be repeated as often as necessary to keep the area intact. Any base course that is not paved over prior to the onset of winter, shall be retested to verify that it still complies with the requirements of this specification. Any area of base course that is damaged shall be reworked or replaced as necessary to comply with this specification. URS FOR EQM SECTION 32 11 23 Page 19 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.8 TYMX989345A FA3002-09-D-0002 TG02 DISPOSAL OF UNSATISFACTORY MATERIALS Dispose of any unsuitable materials that must be removed [outside the limits of Government-controlled land] [as directed] [in waste disposal areas indicated]. No additional payments will be made for materials that must be replaced. -- End of Section -- URS FOR EQM SECTION 32 11 23 Page 20 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 11 33 (August 2008) --------------------------Preparing Activity: NAVFAC Superseding UFGS-32 11 33 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 32 11 33 CEMENT STABILIZED [BASE] [SUBBASE] COURSE AT AIRFIELDS AND ROADS ************************************************************************** NOTE: This guide specification covers the requirements for portland cement-stabilized base or subbase for airfields, roads and streets. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** ************************************************************************** NOTE: The following information should be shown on the project drawings: 1. Location, type and thickness of base and subbase materials. 2. Location of on-site aggregate sources when applicable. ************************************************************************** PART 1 1.1 GENERAL REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in URS FOR EQM SECTION 32 11 33 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) AASHTO M 81 (1992; R 2008) Standard Specification for Cutback Asphalt (Rapid-Curing Type) AASHTO M 82 (1975; R 2008) Standard Specification for Cutback Asphalt (Medium-Curing Type) ASTM INTERNATIONAL (ASTM) ASTM C117 (2013) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing ASTM C136 (2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates ASTM C150/C150M (2012) Standard Specification for Portland Cement ASTM D1140 (2000; R 2006) Amount of Material in Soils Finer than the No. 200 (75-micrometer) Sieve ASTM D1556 (2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method ASTM D1557 (2012) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3) ASTM D1632 (2007) Making and Curing Soil-Cement Compression and Flexure Test Specimens in the Laboratory ASTM D1633 (2000; R 2007) Compressive Strength of Molded Soil-Cement Cylinders URS FOR EQM SECTION 32 11 33 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM D2027/D2027M (2013) Cutback Asphalt (Medium-Curing Type) ASTM D2028/D2028M (2010) Cutback Asphalt (Rapid-Curing Type) ASTM D420 (1998; R 2003) Site Characterization for Engineering Design, and Construction Purposes ASTM D4318 (2010; E 2014) Liquid Limit, Plastic Limit, and Plasticity Index of Soils ASTM D558 (2011) Moisture-Density (Unit Weight) Relations of Soil-Cement Mixtures ASTM D560 (2003) Freezing and Thawing Compacted Soil-Cement Mixtures ASTM D6938 (2010) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth) ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH) NIOSH 81-123 1.2 (1981) Occupational Health Guideline for Chemical Hazards, (Vols. 1, 2, and 3) SUBMITTALS ************************************************************************** NOTE: Review Submittal Description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G". Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, URS FOR EQM SECTION 32 11 33 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are [for Contractor Quality Control approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-04 Samples [ Subbase aggregate ][ Base course aggregate ][ Flexible pavement base course ][ Rigid pavement base course ] Submit duplicate samples of material to be subjected to field testing, as required in paragraph entitled "Field Sampling and Testing." Select the source(s) and provide sample of the aggregate listed above before the materials are required for mix design. [Submit duplicate samples for approval at least 30 days prior to start of work. Do not use aggregate prior to receiving written approval of the samples]. Investigate new sources in accordance with ASTM D420. Take samples from pits, borrow areas, stockpiles or other locations in conformance with ASTM D75/D75M and test. For determining optimum moisture content and maximum density, samples of the blended mixture(s) shall be representative of the processing area before addition of cement. ************************************************************************** NOTE: Select the type of base or subbase for the required construction: airfields, roads, and streets. ************************************************************************** SD-05 Design Data ************************************************************************** NOTE: Specify at least 28 days for approval of mix designs. Identify the type of stabilized course. ************************************************************************** ************************************************************************** NOTE: In wet-dry and freeze-thaw conditions, cement may be added to the above composite materials to URS FOR EQM SECTION 32 11 33 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 obtain stability and load-carrying capacity as measured by the compressive strength, however: (1) If high quality granular materials are not available, the use of substandard materials fully stabilized with cement is acceptable. For such materials, the amount of cement should be determined by ASTM test methods of wetting-and-drying, and/or freezing-and-thawing. Marginal materials having high plasticity or otherwise undesirable characteristics, should be carefully evaluated based on a percent weight loss not to exceed 14 percent as determined by ASTM D559 or ASTM D560. Gradations shall be limited to not more than 45 percent of the material should be retained on the No. 4 sieve, and the maximum size of materials limited to one or 3/4 inch. (2) If the soil and aggregate mixture meet the requirements of the gradations given, the use of the test procedures in accordance with ASTM D559 and ASTM D560 may be waived and the required amount of cement may be determined on the basis of compressive strength. Maximum size of material for base course is usually limited to 1 1/2 inches, with between 30 and 45 percent retained on the No. 4 sieve. When freezing-and-thawing or wetting-and-drying does not occur in a specific location, the freeze-thaw test is valuable in that the test will indicate the internal structural weakness of the soil-cement-aggregate mixture, which otherwise appears more slowly under natural-occurring temperature or moisture fluctuations above the freezing point. The freeze-thaw and wet-dry tests determine the minimum cement content required to produce a structural material that will resist damage due to volume changes and are not meant to simulate specific climate environments. (3) NOTE FOR TABLE I: Use Table I and Gradation (1) as a requirement of import materials for airfield or major road or street applications. For non-critical applications, design an applicable gradation [(2)] dependent upon the availability of local materials, or delete Table 1 in its entirety. ************************************************************************** Mix design Job-mix formula Submit a contractor-furnished mix design [thirty] [_____] days prior to commencement of work. After receiving approval of the mix design, submit a job-mix formula. SD-06 Test Reports ************************************************************************** NOTE: Specify test reports for soil-cement loss if URS FOR EQM SECTION 32 11 33 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 such tests are required at paragraph entitled "Weight Loss of Specimens." ************************************************************************** Aggregate plasticity index Sieve analysis of aggregate Compressive strength [ Soil-cement weight loss ][ Aggregate percentage of wear ][ Existing soil moisture-density] Liquid limit of aggregates Plasticity index of aggregates Sieve analysis of combined material Compressive strength of soil aggregate material Optimum moisture content and maximum density Submit results of ASTM C136 sieve analysis and ASTM D1633 compressive strength testing. SD-07 Certificates Portland cement Location of aggregate source Method of installation Construction equipment list 1.3 1.3.1 DELIVERY AND STORAGE Cement Store cement immediately upon receipt. Store cement in bags on pallets in an airtight and weatherproof structure. Elevate pallets above surface a distance sufficient to prevent the absorption of moisture. Stack bags close together to reduce circulation of air, but do not stack against outside walls. The manner of storage shall permit easy access for inspection and identification of each shipment. Transfer bulk cement to elevated airtight and weatherproof bins. Cement shall be free-flowing and free of lumps. Test cement that has been in storage longer than 6 months by standard mortar tests or loss on ignition test and use such cement only with approval of the Contracting Officer. Show the date of receipt of shipment on each bag of cement. 1.3.2 Aggregates Store aggregates in a manner to minimize segregation and contamination. To prevent the inclusion of contaminants, store aggregates on surfaces covered URS FOR EQM SECTION 32 11 33 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 with tightly laid wooden planks, sheet metal, or other hard and clean material. Store aggregates of different sizes in separate piles. Form stockpiles of coarse aggregates by spreading the materials in horizontal layers not exceeding 5 feet in depth. Stockpiling may be the single-core type, cast and spread type or truck-dumped type. Should the coarse aggregates become segregated, re-mix the stockpile to conform to specified grading requirements. Aggregate obtained from below existing watertable shall be drained before use. 1.3.3 Curing Materials Deliver curing materials in original sealed containers showing trade name, specification number and manufacturer's name. Store in a manner that will prevent damage and contamination. 1.4 ENVIRONMENTAL CONDITIONS Do not construct [base] [subbase] when weather conditions will detrimentally affect quality of the finished course. Apply cement when the ambient temperature is a minimum of 40 degrees F and rising. Do not apply cement to aggregate materials that are frozen or contain frost. If ambient temperature falls below 40 degrees F, protect completed cement-treated areas against freezing. Reprocess, reshape, and recompact damaged material. Provide drainage to prevent water from collecting or standing stabilized areas, and on the pulverized, mixed, or partially mixed materials. 1.5 1.5.1 QUALITY ASSURANCE Required Data Submit location of aggregate source in writing. Do not construe Government approval of samples as approval of the source of the samples. Submit a construction equipment list, and method of proportioning, spreading, compacting and curing to be used, [thirty] [_____] days prior to commencement of work. PART 2 2.1 PRODUCTS CEMENT ************************************************************************** NOTE: Specify the type of cement, as required. Example: When base materials are in contact with soils having a moderate sulfate content (exceeding 0.20 percent or 2000 ppm), specify Type II, low alkali cement. ************************************************************************** ASTM C150/C150M, [Type I] [Type I or II] [Type II, low alkali]or ASTM C595/C595M[Type IP] [Type I PM]. 2.2 AGGREGATE MATERIALS ************************************************************************** NOTE: Select the type of base or subbase for the required construction: airfields, roads, and streets. ************************************************************************** URS FOR EQM SECTION 32 11 33 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS [2.2.1 TYMX989345A FA3002-09-D-0002 TG02 Subbase Aggregate ************************************************************************** NOTE: Choose this paragraph or the paragraph and subparagraphs below, entitled "Base Course Aggregate." ************************************************************************** ************************************************************************** NOTE: Select gradation requirements and other soil index values appropriate for base course or subbase course materials. Where high quality granular materials are not available, select materials which may be available on, or adjacent to, the project site. Aggregate should be clean and free from vegetable matter and other deleterious substances. Also aggregates may be imported from local or commercial sources. Material should consist of sand-clay mixtures; gravel; crushed stone, slag or gravel; or combinations of the above. Percentage of wear should not exceed 50 percent; dry unit weight of slag should not be less than 65 pounds per cubic foot; liquid limits and plasticity indexes for flexible or rigid pavements should be in accordance with second technical "NOTE" in paragraph entitled "SD-05, Design Data." ************************************************************************** Select aggregate materials which conform to ASTM D2487, classified as GW, GP, GM, GC, SW, SM, SC, SP or combination(s) thereof except as modified. Sample materials in accordance with ASTM D75/D75M. Plasticity index shall not exceed 12 or liquid limit not more than 21 when tested in accordance with ASTM D4318. [Dry weight of air cooled, blast-furnace slag shall be not less than [65] [70] [_____] pounds per cubic foot in accordance with ASTM C29/C29M]. Perform sieve analysis in accordance with ASTM C117 AND ASTM C136. Conform to the following gradation limits: TABLE I Sieve Designation Percent by Weight Passing (1) [(2)] No. 4 55 - 100 [_____] No. 10 36 - 60 [_____] 3 - 20 [_____] No. 100 ][2.2.1 Base Course Aggregate ************************************************************************** NOTE: Choose this paragraph and subparagraphs or the paragraph above, entitled "Subbase Aggregate." ************************************************************************** ************************************************************************** URS FOR EQM SECTION 32 11 33 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NOTE: Select gradation requirements and other soil index values appropriate for base course or subbase course materials. Where high quality granular materials are not available, select materials which may be available on, or adjacent to, the project site. Aggregate should be clean and free from vegetable matter and other deleterious substances. Also aggregates may be imported from local or commercial sources. Material should consist of sand-clay mixtures; gravel; crushed stone, slag or gravel; or combinations of the above. Percentage of wear should not exceed 50 percent; dry unit weight of slag should not be less than 65 pounds per cubic foot; liquid limits and plasticity indexes for flexible or rigid pavements should be in accordance with second technical "NOTE" in paragraph entitled "SD-05, Design Data." ************************************************************************** [Crushed] [and] [uncrushed] coarse and fine aggregate. Sample materials in accordance with ASTM D75/D75M. Material passing the No. 40 sieve shall have a maximum liquid limit of [25] [_____] and a maximum plasticity index of 12 in accordance with ASTM D4318. The aggregate sand equivalent is to exceed 18. Perform sieve analysis in accordance with ASTM C117 and ASTM C136. [2.2.1.1 Flexible Pavement Base Course ************************************************************************** NOTE: Choose this subparagraph or the subparagraph below, entitled "Rigid Pavement Base Course" when using the paragraph above, entitled "Base Course Aggregate." ************************************************************************** Plasticity index of less than [6] [_____] and liquid limit less than [25] [_____] in accordance with ASTM D4318. [Percentage of wear less than [50] [_____] percent in accordance with ASTM C131.] ][2.2.1.1 Rigid Pavement Base Course Plasticity index of less than [8] [_____] and liquid limit less than [25] [_____] in accordance with ASTM D4318. ]2.2.1.2 Gradation of Aggregate ************************************************************************** NOTE: Aggregate for use in Gradation (1) of Table II when mixed with Type II modified portland cement in an amount not to exceed 5 percent by weight of the dry aggregate and compacted at optimum moisture content, the minimum compressive strength of the compacted mixture shall be 750 psi at 7 days. Aggregate for use in Gradation (2) of Table II cement treated base shall have a compressive strength of 250 psi before mixing with Type II modified portland cement in an amount not to exceed 2 1/2 percent by weight of the dry aggregate and compacted at optimum moisture content to a minimum URS FOR EQM SECTION 32 11 33 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 compressive strength of 600 psi at 7 days. For specially designed gradations, [(3)], of Table II, see second technical "NOTE" in paragraph entitled "Cement Content." ************************************************************************** Conform to the following: TABLE I Sieve Designation Percent by Weight Passing (1) 3 inch 2 1/2 inch (2) [(3)] 100 [_____] 90-100 [_____] 2 inch [_____] 1 1/2 inch [_____] 1 inch 3/4 inch 100 [_____] 0-100 [_____] 1/2 inch No. 4 [_____] 5-70 55-70 No. 10 [_____] No. 30 2-55 [_____] No. 40 [_____] No. 200 ]2.3 [_____] 3-15 3-20 [_____] WATER Provide potable, clean, fresh and free from injurious amounts of oils, acid, salt, alkali, organic matter and other substances deleterious to the hardening of soil-cement. 2.4 CEMENT-TREATED [BASE] [SUBBASE] ************************************************************************** NOTE: Select the type of base or subbase for the required construction: airfields, roads, and streets. ************************************************************************** Uniformly blend aggregates and cement together, mixed with water. Provide cement treated [base] [subbase] produced with the following characteristics: URS FOR EQM SECTION 32 11 33 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.4.1 TYMX989345A FA3002-09-D-0002 TG02 Compressive Strength ************************************************************************** NOTE: Determine the load capacity requirements of the base. Select method (freeze-thaw method is more critical) for determining cement contents for soil-aggregate mixtures based on the nature of the available soil materials, climate conditions (wet-dry or freeze-thaw), and base requirements. For substandard granular materials, select wet-dry and/or freeze-thaw tests for mix design and the cement contents to determine if the hardened cement-treated materials will remain hard or soften from exposure to severe moisture variations and alternate freezing and thawing conditions. Specify compressive strength tests to evaluate the hardened characteristics of the soil-cement mixtures. Site investigation is necessary to determine the nature of existing on-site materials, and, if necessary, the availability and need of imported select materials. The specifier should insure that the following information is covered: (1) Identify the type of base in the project specification and on the drawings. (2) Specify the type or quality of the aggregate or soil-aggregate material before cement is added. (3) Specify test methods for determining the exact percentage of cement required for the select materials. Establish criteria for selecting the cement content to produce hard, durable cement stabilized base or subbase course. For substandard materials, specify maximum soil-cement losses for specimens tested that contain two or more different cement contents at 12 cycles of wetting-and-drying test or freezing-and-thawing test. For all types of material, specify compressive strength determinations of soil-cement mixtures for preparation of mix design and for field control tests. (Minimum unconfined compressive strengths: 300 psi for subbase and 650 psi for base course. See MIL-HDBK-1021/4). ************************************************************************** Unconfined compressive strength, at optimum moisture content, a minimum of [ 650300] psi [_____] at 7 days when tested in accordance with ASTM D1633. 2.4.2 Cement Content ************************************************************************** NOTE: Select the applicable paragraph(s) from the following: ************************************************************************** [ When blended with soil aggregates and water, mixture shall meet the indicated compressive strength not to exceed [[_____] percent of cement by weight of drying aggregate for base] [and] [[_____] percent of cement by weight of dry aggregate for subbase]. URS FOR EQM SECTION 32 11 33 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ] ************************************************************************** NOTE: Use this paragraph when the cement content is known or can be approximated by verification from local material sources. If such information is not available, substitute with an appropriate basis of bid paragraph or use unit prices. When conditions are favorable cement content may be as low as 1 1/2 percent of weight of dry aggregate. Should design requirements for cement content be higher than 4 percent for subbase and 6 percent for base course, compare and consider other more cost effective means of accomplishment. Alternate or additive treatments with lime, fly ash, filter cloth etc. should also be considered. Compressive strength minima/maxima indicated in second technical "NOTE" in paragraph entitled "SD-05, Design Data." ************************************************************************** [ When blended with imported aggregates and water, mixture is to meet indicated compressive strength while not exceeding [[6] [_____] percent of cement by weight of aggregate for base][[3] [_____] percent of cement by weight of aggregate for subbase]. ]2.4.3 Weight Loss of Specimens ************************************************************************** NOTE: Select the applicable paragraph(s) from the following: ************************************************************************** ************************************************************************** NOTE: Select both of these tests together, or use the freeze-thaw test only (it is the more critical). ************************************************************************** [ Less than 14 percent when subjected to 12 cycles of wet-dry tests in accordance with ASTM D559. ] ************************************************************************** NOTE: Select both of these tests together, or use the freeze-thaw test only (it is the more critical). ************************************************************************** [ Less than 14 percent when subjected to 12 cycles of freeze-thaw tests in accordance with ASTM D560. ]2.5 MIX DESIGN ************************************************************************** NOTE: Specify 7-day compressive tests when high-quality granular materials are specified. However, if available materials have between 37 and 63 percent retained on the No. 4 sieve or if materials are substandard in quality (cohesive) or are excessive in fines, specify freezing and thawing (ASTM D560) tests in conjunction with compressive tests. ************************************************************************** URS FOR EQM SECTION 32 11 33 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** NOTE: Select the type of base or subbase for the required construction: airfields, roads, and streets. ************************************************************************** Provide a mix design and job-mix formula for [plant mix material] [ mixed-in-place material] for [subbase] [base] prepared by an approved laboratory. Show amount of cement needed and the moisture-densityrelations of the composite aggregate mixture in accordance with ASTM D558. Mix design shall include certified test reports showing results of tests [and results of 7-day compressive tests][and results of 7-day compressive tests and wetting and drying tests] [and results of 7-day compressive test and the freezing and thawing tests]. Mold a minimum of [two] [three] [four] cylinders of each cement mixture in accordance with ASTM D1632, except that test specimen molds shall be 4 inches in diameter by4.6 inches high. Cure and test specimens in accordance with ASTM D1633 with the following exceptions: (1) cure specimens in moist room at 100 percent relative humidity for 7 days; and (2) after curing, cap specimens and immerse in water at room temperature for a period of 4 hours prior to testing. Before or during construction, if the source of any materials is changed, or if there is any variation in quality of materials furnished, conduct additional tests and adjust amount of cement as required to obtain the specified results. 2.6 CURING MATERIALS 2.6.1 Bituminous Material ************************************************************************** NOTE: Cutback and Emulsified Asphalts: Prior to specifying cutback and emulsified asphalts contact the State, County or Local Air Pollution Control District for guidelines as to which asphalt material is allowed in the applicable area. ************************************************************************** 2.6.1.1 Liquid Asphalt ASTM D2027/D2027M or AASHTO M 82, Type [MC-70] [MC-250] for medium-curing asphalt; ASTM D2028/D2028M or AASHTO M 81, type [RC-70] [RC-250] for rapid-curing asphalt. 2.6.1.2 Emulsified Asphalt ASTM D977 or AASHTO M 140, Type [RS-1] [RS-2] or AASHTO M 208[CRS-1] [CRS-2]. 2.6.2 Burlap FS CCC-C-467. 2.6.3 Polyethylene Sheeting White, opaque, free of defects, uniform in appearance, a minimum 4 mils thick. Water retention requirements shall be in accordance with ASTM C171. 2.6.4 Polyethylene-Coated Burlap White, opaque, 4 mil thick film, impregnated into, extruded on, or URS FOR EQM SECTION 32 11 33 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 permanently affixed to surface of one side of burlap weighing not less than 9 ounces per square yardprior to coating. Water retention requirements shall be in accordance with ASTM C171. Waterproof Paper White topside. Water retention requirements shall be in accordance with ASTM C171. PART 3 EXECUTION 3.1 3.1.1 SITE PREPARATION Cleaning and Grading ************************************************************************** NOTE: Select the type of base or subbase for the required construction: airfields, roads, and streets. ************************************************************************** ************************************************************************** NOTE: Specify this paragraph where subgrade or subbase preparation is required. Add compaction requirements if Section 31 00 00 EARTHWORK is not utilized. ************************************************************************** Clean debris from the area to be stabilized. Inspect [subgraderface] [subbase] for capability to withstand without displacement, compaction specified for the aggregate-cement mixture. Correct ruts, soft or yielding areas in [subgraderface] [subbase] by removing or adding material or aerating or wetting materials as required. [Clear and grub,] g Grade [proof roll] and shape the area to be stabilized to conform to lines, grades, and cross sections prior to placing cement-treated coursement [according to Section 31 00 00 EARTHWORK] [with a minimum compaction of 95 [_____] percent of maximum density in accordance with ASTM D1557 or as recommended by the Geotechnical Engineer.] The surface shall be approved by the Contracting Officer prior to [base] [subbase] course placement. Determine moisture-density relationship of existing soils in accordance with ASTM D1557. Perform laboratory tests on existing materials prior to initial construction. 3.1.2 Grade Control Maintain lines and grades indicated. When the stabilized course is part of a pavement which is to meet a fixed grade, construct a transition of sufficient length to minimize abrupt or noticeable grade changes. Operation of Government Borrow PitsPerform cleaning, stripping, and excavating in opening or operation of pits or quarries. Open pits in a manner that will expose vertical faces of the deposit for suitable working depths. Obtain materials excavated from pits in successive vertical cuts extending through exposed strata. Waste pockets or strata of unsuitable materials overlying or occurring in the deposit. Methods of operating pits and processing and blending of materials may be changed or modified by the Contracting Officer without adjustments in the contract price when such action is necessary to obtain material conforming to specified requirements. Upon completion of work, leave condition of pits in accordance with Section [01 57 19.00 20 TEMPORARY ENVIRONMENTAL CONTROLS.] URS FOR EQM SECTION 32 11 33 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.2 3.2.1 TYMX989345A FA3002-09-D-0002 TG02 MIXING AND PLACING Mixing ************************************************************************** NOTE: Specify central mixing plant when cement-stabilized base is used under rigid airfield pavements which have butt-type construction joints without load transfer devices and for all airfield base course applications under flexible pavement. For soil-cement subgrade or subbase, specify mixed-in-place method if mixing of cement to on-site native materials or to import materials is required at the site of the work. The method may also be used for subbase under rigid airfield pavements when butt-type construction joints are required in contracts. Central-plant mixing is preferred for cement stabilization for finer materials. (See DM 5.4 and MIL-HDBK 1021/4). ************************************************************************** Mix cement and aggregate [in a central mixing plant] [in a traveling plant] [in place]. Proportion aggregate by weight or by volume in such quantities that specified gradation, bearing ratio, liquid limit, and plasticity index requirements are met after [base] [subbase] has been placed and compacted. Proportion cement by weight in accordance with job-mix formula. Provide necessary moisture content for specified compaction by addition of water by weight or by volume. Mixing operations shall produce uniform blending and the method of discharging shall not produce segregation. 3.2.2 [Plant Mix Materials ************************************************************************** NOTE: Select the applicable paragraph(s) from the following: ************************************************************************** ************************************************************************** NOTE: Specify central mixing plant when cement-stabilized base is used under rigid airfield pavements which have butt-type construction joints without load transfer devices and for all airfield base course applications under flexible pavement. For soil-cement subgrade or subbase, specify mixed-in-place method if mixing of cement to on-site native materials or to import materials is required at the site of the work. The method may also be used for subbase under rigid airfield pavements when butt-type construction joints are required in contracts. Central-plant mixing is preferred for cement stabilization for finer materials. (See DM 5.4 and MIL-HDBK 1021/4). ************************************************************************** Materials from several sources which are blended and mixed or processed in a central mixing plant or in a traveling mixing plant. [Prepare base course materials for airfield portland cement concrete pavement in a central mixing plant.] Add cement in accordance with job-mix formula. Uniformly mix materials with required amount of water. After mixing is URS FOR EQM SECTION 32 11 33 Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 completed, transport the materials to, and spread on, prepared underlying course without undue loss of the moisture content. ][Mixed-In-Place Materials Materials which are proportioned and mixed or blended in place. Add cement in accordance with the job-mix formula. Apply water uniformly prior to and during the mixing operation, if necessary, to maintain required moisture content. ]3.2.2 Placing ************************************************************************** NOTE: Specify central mixing plant when cement-stabilized base is used under rigid airfield pavements which have butt-type construction joints without load transfer devices and for all airfield base course applications under flexible pavement. For soil-cement subgrade or subbase, specify mixed-in-place method if mixing of cement to on-site native materials or to import materials is required at the site of the work. The method may also be used for subbase under rigid airfield pavements when butt-type construction joints are required in contracts. Central-plant mixing is preferred for cement stabilization for finer materials. (See DM 5.4 and MIL-HDBK 1021/4). ************************************************************************** [Loose] [cCompacted] thickness of individual layers shall not exceed [8]12 inches [_____]. When stabilized course is constructed in more than one layer, clean previously constructed layers of loose and foreign matter by sweeping with power sweepers or power brooms, except that hand brooms may be used where permitted by the Contracting Officer. Not more than 60 minutes shall elapse between start of moist mixing and start of compaction of treated layer. Not more than 30 minutes shall elapse between placement of cement-treated aggregates in adjacent lanes. If elapsed time exceeds 30 minutes, provide construction joint. Layers are to be uniform in thickness. 3.2.3 Compaction ************************************************************************** NOTE: Specify degree of compaction in accordance with DM-5.4 or MIL-HDBK-1021/4 for flexible and rigid pavements. (For example: Specify 100 percent compaction for base course of flexible airfield pavements; see MIL-HDBK-1021/4). ************************************************************************** With the exception of materials placed by traveling-plant method, thoroughly loosen blended materials to full depth by disks or scarifiers and determine moisture content of mixture and compare with laboratory optimum moisture content. Begin rolling and compaction when moisture content is within plus or minus 2 percentage points of optimum moisture content. Compact layers of [base] [subbase] course materials. Continue compaction until layer or layers are compacted through full depth of [base] [subbase]. Begin rolling at outside edge of a minimum one half the width of the roller. Subsequent rolled trips shall be slightly different lengths. In places not accessible to rolling equipment, compact the URS FOR EQM SECTION 32 11 33 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 material by mechanical tamping. Continue blading, rolling and tamping until surface is smooth and free from waves and irregularities. Determine in-place density of compacted cement-aggregate mixture in accordance with ASTM D1556 with minimum compaction of [10095] [_____] percent of maximum density in accordance with ASTM D558. 3.3 3.3.1 FINISHING Finishing After compaction, moisten surface if necessary, and shape to required lines, grades and cross section. Lightly scarify surface to eliminate imprints made by the compacting or shaping equipment. Thoroughly compact surface to specified density with rubbertired rollers and smooth-wheel tandem rollers to provide a smooth, dense, uniform surface free of surface checking, ridges or loose material and conforming to crown, grade and line indicated. Complete finishing operations within 2 hours after completion of mixing operations. In places not accessible to finishing and shaping equipment, compact mixture with mechanical tampers to density specified; shape and finish by hand methods. Reprocess with additional cement, the portion of the compacted mix with density less than that specified, or that has not properly hardened, or that is improperly finished. 3.3.2 Edges of Stabilized Course Place material along edges of the stabilized course in a quantity that will compact to thickness of course being constructed. If constructed in two or more layers, place in a quantity that will compact to thickness of each layer. Allow in each operation, a minimum width of one foot of the shoulder to be rolled and compacted simultaneously with each layer of the stabilized course. 3.3.3 Thickness Control Where average measured thickness of stabilized course is more than 1/2 inch deficient in thickness, conduct additional tests and correct deficiencies as directed by the Contracting Officer. Correct excesses in thickness if so directed by the Contracting Officer. Average job thickness is the average of the job measurements determined as specified in paragraph entitled "Thickness Test," in this section, but within 1/2 inch of the thickness indicated. Replace material removed for test holes or for deficient thickness reconstruction and compact with new soil-cement mixture. 3.3.4 Construction Joints At the end of each work day, form a straight transverse construction joint by cutting back into completed work to form a true vertical face free of loose or shattered material. Remove improperly compacted material along construction joints and replace with soil-cement that is mixed, moistened, and compacted in accordance with this specification. 3.4 3.4.1 CURING AND PROTECTION Curing, Protection and Cover Immediately after completion of finishing operations, but no later than the end of each days stabilization work, protect the surface against rapid drying for seven days by one of the methods specified. In addition, protect the stabilized area from freezing during the curing period or until URS FOR EQM SECTION 32 11 33 Page 17 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 hardened, whichever period is longer. 3.4.2 Bituminous Material ************************************************************************** NOTE: Cutback and Emulsified Asphalts: Prior to specifying cutback and emulsified asphalts contact the State, County or Local Air Pollution Control District for guidelines as to which asphalt material is allowed in the applicable area. ************************************************************************** ************************************************************************** NOTE: For the specified bituminous materials, the recommended application temperatures may be selected from the following table and inserted in the blanks: LIQUID ASPHALT DEGREES F RC-70 or MC-70 120 - 185 RC-250 or MC-250 165 - 230 EMULSIFIED ASPHALT DEGREES F RS-1 75 - 130 RS-2 110 - 160 CRS-1 75 - 130 CRS-2 110 - 185 ************************************************************************** Immediately after finishing, clean surface of loose and foreign matter. Ensure that surface contains sufficient moisture, by applying water in a fine spray as required, to prevent penetration of bituminous material. Using a distributor, apply RC-70 bituminous material at a temperature between 125[_____] and 185[_____] (degrees F and at a rate between [0.20] [_____] and [0.25] [_____] gallons per square yard. Treat areas inaccessible to, or missed by distributor using manually operated hose attachment. Apply sand at [_____] (pounds per square yard to treated surfaces requiring protection from traffic. 3.4.3 Burlap or Cotton MatsMicro-Cracking BAfter the completed concrete-stabilized base course has cured, it shall be be intentially "micro-cracked" to discourage reflective cracking with five passes of a large vibratory roller between 24 and 72 hours after placement. urlap covers consisting of two or more layers of burlap having a combined weight of 14 ounces or more per square yard in a dry condition. Burlap may be either new or have been used only for curing concrete. Cotton mats and burlap strips shall have a length, after shrinkage, at least one foot greater than required to cover the entire width and edges of finished stabilized area. Mats shall overlap each other at least 6 inches. Thoroughly wet mats before placing and keep them continuously wet and in URS FOR EQM SECTION 32 11 33 Page 18 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 intimate contact with surface and edges of finished stabilized area during entire curing period. 3.4.4 Waterproof Paper, Blankets, or Impermeable SheetsBond Breaker MAfter the completed concrete-stabilized base course has cured, and immediately prior to placement of concrete pavement on the concrete-stabilized base surface, two coats of white pigmented concrete curing compound conforming to COE CRD-C 300 shall be applied to the surface of the concrete-stabilized base course to discourange reflective cracking at an application rate of 400 square feet per gallon for each coat. oisten surface with a fine spray of water, then cover with waterproof-paper, waterproof-paper blankets, polyethylene-coated burlap blankets, or polyethylene sheeting. Thoroughly saturate polyethylene-coated burlap with water before placing. Place waterproof-paper blankets, polyethylene-coated burlap blankets, or polyethylene sheeting with the light-colored side up. Extend sheets over the edges of stabilized area and secure in place during the curing period. Overlap edges of sheets a minimum of one foot and securely cement or tape to form continuous closed joints. Immediately repair tears and holes in sheets. Reject curing material that does not provide a continuous cover. Moist Curing Apply a 2 inch covering of soil or minimum 4 pounds per square yard of straw. Moisten material initially and keep moistened throughout curing period. 3.5 3.5.1 MAINTENANCE AND TRAFFIC CONTROL Maintenance After stabilization is completed, maintain [base] [subbase] except where succeeding course is under construction. Maintenance shall include drainage and watering as required to maintain course in proper condition. Correct deficiencies in thickness, composition, construction, smoothness or density which develop during maintenance to conform to requirements specified. Maintain surface moisture by lightly sprinkling with water to prevent dust. 3.5.2 Traffic Control Completed portions of the cement-stabilized area may be opened to light, local traffic provided the curing process is not impaired and to other traffic after curing period has elapsed, provided that the cement-stabilized course has hardened sufficiently to prevent surface marring or distortion by equipment or traffic. Do not permit heavy equipment on the area during protection and curing periods. Necessary cement and water may be hauled over the area with pneumatic-tired equipment on approval of the Contracting Officer. Protect finished portions of cement stabilized [base] [subbase] from traffic of equipment used in constructing adjoining sections in a manner to prevent marring or damaging completed work. 3.6 SAFETY REQUIREMENTS In addition to Safety Requirements contained within the Contract Clauses; prevent employee respiratory, eye or skin contact with Portland Cement during wet or dry mixing or of cutback asphalts during transport or URS FOR EQM SECTION 32 11 33 Page 19 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 application. Provide and require employee to use and dispose or clean the following in accordance with the pertinent provisions of NIOSH 81-123: a. Impervious: b. Splash-proof safety goggles and face shields. c. Respiratory protection equipment. 3.6.1 Clothing, boots and gloves. Additional Safety Requirements for Cutback Asphalts ************************************************************************** NOTE: Prior to specifying cutback and emulsified asphalts contact the State, County or Local Air Pollution Control District for guidelines as to which asphalt material is allowed in the applicable area. ************************************************************************** Application temperatures of asphalt cutbacks specified usually exceed flash point of the material. Take suitable safety precautions to prevent flashing of asphalt. Exercise the following minimum safety precautions: a. Do not permit open flames or sparks close to the cutback asphalts. Apply controlled heat in heating kettles, mixers, distributors, or other equipment designed and approved for the purpose. b. Do not use open flames to examine drums, tank cars, or other containers or cutback asphalts. c. Properly and fully vent vehicles transporting cutback asphalts. d. Permit only experienced personnel to supervise the handling of cutback asphalt materials. e. Comply with all applicable intrastate and interstate commerce regulations for transporting cutback asphalts. 3.7 FIELD SAMPLING AND TESTING ************************************************************************** NOTE: Specify duplicate samples for large projects which will require five or more days of continuous operation in processing and placement of base materials. In subsequent paragraphs, specify frequency of sampling according to size of proposed contract. ************************************************************************** In addition to provisions set forth elsewhere in this contract, specified sampling and testing shall be conducted by an approved laboratory. [Provide duplicate samples to the Contracting Officer on the average of [_____] samples a [week] [month]. Take duplicate samples at the same time and in the same manner as the original.] URS FOR EQM SECTION 32 11 33 Page 20 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.7.1 TYMX989345A FA3002-09-D-0002 TG02 Sampling 3.7.1.1 Aggregates at Source Collect samples by taking three incremental specimens at random from source material to make a composite sample a minimum of 150 pounds. Thereafter, during the course of the project, take one random sample from each [4000] [_____] tonsof material or a day's run, whichever is less. Take the samples at random to make a composite sample of not less than 50 pounds. Repeat the sampling when source of material is changed or when unacceptable deficiencies or variations from specified grading of materials are found in testing. 3.7.1.2 Cement-Treated Materials After cement and water have been added to the aggregates, thoroughly blend the mixture. Place a sample in a closed and insulated container, before cement hydration is completed, and promptly transport to the laboratory. 3.7.1.3 Sample Identification Place each sample in a clean container and securely close. sample with a tag containing the following information: Identify each Contract No.: Sample No.: Quantity: Date of Sample: Sampler: Source: Intended Use: For Testing: 3.7.2 Testing 3.7.2.1 Aggregate Testing Perform the following tests on each sample of the specified aggregate and existing soil-aggregate materials: a. Sieve analysis of combined material: b. Liquid limit: c. Plasticity index: ASTM C136 and ASTM D1140. ASTM D4318. ASTM D4318. Perform other specified tests when there is a change of aggregate source. Material shall conform to approved test results developed for the mix design. 3.7.2.2 Compressive Tests Test composite sample of cement treated materials for compressive strength. Mold specimens in accordance with ASTM D558, Method A or B (as URS FOR EQM SECTION 32 11 33 Page 21 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 appropriate), cure and test according to ASTM D1632 and ASTM D1633. Test specimens for compressive strength at 7 days, and submit results to the Contracting Officer. 3.7.2.3 Smoothness Test Test compacted surface with a 10 foot straightedge applied parallel with, and at right angles to center line of paved area, and correct deviations in excess of 1/2 inch. When [base] [subbase] course is to be constructed in more than one layer, specified smoothness requirements apply only to the top layer. 3.7.2.4 Thickness Test Measure thickness of the [base] [subbase] course using 3 inch diameter test holes through the full depth for each [500] [_____] square yards of completed course. Refill holes with cement treated material and compact. 3.7.2.5 Field Density Tests Perform field density tests in accordance with ASTM D1556 or ASTM D6938. Perform one field density test for each [2000] [_____] square yards for each layer of [base] [subbase] material placed. 3.7.2.6 Laboratory Test Determine optimum moisture content and maximum density relationship in accordance with ASTM D558. -- End of Section -- URS FOR EQM SECTION 32 11 33 Page 22 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 12 10 (August 2008) --------------------------Preparing Activity: USACE Superseding UFGS-32 12 10 (October 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 32 12 10 BITUMINOUS TACK AND PRIME COATS ************************************************************************** NOTE: This guide specification covers the requirements for bituminous tack and prime coats for airfield pavements, roads, parking areas and general paving needs. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 1.1 GENERAL UNIT PRICES ************************************************************************** NOTE: Delete unit price paragraphs when lump sum bidding is used. Edit submittal requirements accordingly. ************************************************************************** 1.1.1 Measurement ************************************************************************** NOTE: When the bituminous material is measured in liters (gallons), the appropriate ASTM method will be retained for the type of bituminous material specified. ************************************************************************** URS FOR EQM SECTION 32 12 10 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 The bituminous material paid for will be the measured quantities used in the accepted work, provided that the measured quantities are not 10 percent over the specified application rate. Any amount of bituminous material more than 10 percent over the specified application rate for each application will be deducted from the measured quantities, except for irregular areas where hand spraying of the bituminous material is necessary. Express measured quantities in [ 2000 pound tons] [ gallons at 60 degrees F. Volumes measured at temperatures other than 60 degrees F shall be corrected [in accordance with ASTM D1250][using a coefficient of expansion of 0.00025 per degree F for asphalt emulsion]]. 1.1.2 Payment The quantities of bituminous material, determined as specified above, will be paid for at the respective contract unit prices. Payment shall constitute full compensation for all operations necessary to complete the work as specified herein. 1.1.3 Waybills and Delivery Tickets Submit waybills and delivery tickets, during progress of the work. Before the final statement is allowed, file with the Contracting Officer certified waybills and certified delivery tickets for all bituminous materials used in the construction of the pavement covered by the contract. These submittals are required for Unit Pricing bid only. Do not remove bituminous material from storage until the initial outage and temperature measurements have been taken. The delivery or storage units will not be released until the final outage has been taken. 1.2 REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. URS FOR EQM SECTION 32 12 10 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) AASHTO T 102 (2009) Standard Method of Test for Spot Test of Asphaltic Materials AASHTO T 40 (2002; R 2006) Sampling Bituminous Materials ASTM INTERNATIONAL (ASTM) ASTM D1250 (2008) Standard Guide for Use of the Petroleum Measurement Tables ASTM D140/D140M (2014) Standard Practice for Sampling Bituminous Materials ASTM D2027/D2027M (2013) Cutback Asphalt (Medium-Curing Type) ASTM D2397/D2397M (2013) Standard Specification for Cationic Emulsified Asphalt ASTM D2995 (1999; R 2009) Determining Application Rate of Bituminous Distributors 1.3 SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 URS FOR EQM SECTION 32 12 10 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-03 Product Data Waybills and Delivery Tickets SD-06 Test Reports Sampling and Testing ************************************************************************** NOTE: Using local materials can help minimize transportation impacts, including fossil fuel consumption, air pollution, and labor. Using materials harvested and manufactured within a 800 km (500 mile) radius from the project site contributes to the following LEED credit: MR5. Coordinate with Section 01 33 29 LEED(tm) DOCUMENTATION. Use second option if Contractor is choosing local materials in accordance with Section 01 33 29 LEED(tm) DOCUMENTATION. Use second option for USACE projects. Army projects should include option, only if pursuing this LEED credit. ************************************************************************** [Use Local/Regional Materials or products extracted, harvested, or recovered, as well as manufactured, within a [500] [_____] mile radius from the project site, if available from a minimum of three sources.] [See Section 01 33 29 LEED(tm) DOCUMENTATION for cumulative total local material requirements. Tack and prime coat materials may be locally available.] [Submit documentation indicating distance between manufacturing facility and the project site. Indicate distance of raw material origin from the project site. Indicate relative dollar value of local/regional materials to total dollar value of products included in project in accordance with LEED NC.] 1.4 DELIVERY, STORAGE, AND HANDLING Inspect the materials delivered to the site for contamination and damage. Unload and store the materials with a minimum of handling. 1.5 ENVIRONMENTAL REQUIREMENTS Apply bituminous coat only when the surface to receive the bituminous coat is dry. Apply bituminous coat only when the atmospheric temperature in the shade is 50 degrees F or above and when the temperature has not been below 35 degrees F for the 12 hours prior to application, unless otherwise directed. URS FOR EQM SECTION 32 12 10 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS PART 2 2.1 TYMX989345A FA3002-09-D-0002 TG02 PRODUCTS PLANT, EQUIPMENT, MACHINES AND TOOLS Plant, equipment, machines and tools used in the work are subject to approval and must be maintained in a satisfactory working condition at all times. Calibrated equipment such as asphalt distributors, scales, batching equipment, spreaders and similar equipment, must have been recalibrated by a calibration laboratory within [12] [_____] months prior to commencing work [and every [_____] months thereafter, by such laboratory from the date of recalibration, during the term of the contract]. 2.1.1 Bituminous Distributor Provide a distributor with pneumatic tires of such size and number that the load produced on the base surface does not exceed 650 psi of tire width to prevent rutting, shoving or otherwise damaging the base surface or other layers in the pavement structure. Design and equip the distributor to spray the bituminous material in a uniform coverage at the specified temperature, at readily determined and controlled rates from 0.05 to 2.0 gallons per square yard, with a pressure range of 25 to 75 psi and with an allowable variation from the specified rate of not more than plus or minus 5 percent, and at variable widths. Include with the distributor equipment a separate power unit for the bitumen pump, full-circulation spray bars, tachometer, pressure gauges, volume-measuring devices, adequate heaters for heating of materials to the proper application temperature, a thermometer for reading the temperature of tank contents, and a hand hose attachment suitable for applying bituminous material manually to areas inaccessible to the distributor. Equip the distributor to circulate and agitate the bituminous material during the heating process. 2.1.2 Heating Equipment for Storage Tanks The equipment for heating the bituminous material shall be steam, electric, or hot oil heaters. Provide steam heaters consisting of steam coils and equipment for producing steam, so designed that the steam cannot get into the material. Fix an armored thermometer to the tank with a temperature range from 40 to 400 degrees F so that the temperature of the bituminous material may be determined at all times. 2.2 PRIME COAT ************************************************************************** NOTE: Remove brackets from around the material to be allowed in the contract specifications and delete the other materials and references. a. With growing environmental/safety regulations, more and more states are prohibiting the use of cutback asphalts in favor of emulsified asphalt materials. If cutback asphalts are used, one of the following types and grades can be recommended: Slow-Curing Type (ASTM D2026/D2026M): SC-70, SC-250. Medium-Curing Type (ASTM D2027/D2027M or AASHTO M 82): MC-30, MC-70, MC-250. Rapid-Curing Type (ASTM D2028/D2028M or AASHTO M URS FOR EQM SECTION 32 12 10 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 81): RC-70, RC-250. Selection of a particular type and grade should consider the nature of the surface to be treated. An open base course material will be penetrated readily, and all of the above types and grades can be considered except for the low viscosity MC-30. A tight surface is not going to be penetrated as readily; therefore, the less viscous materials are recommended such as RC-70, MC-30, MC-70 and SC-70. Some caution might be urged in using RC-70 or RC-250 because the solvent may separate or be absorbed by the base course fines and leave the asphalt deposited on the surface. Cutback asphalts can be used in cold-weather construction with less concern than emulsions which contain water. Less viscous grades may be used for cold-weather construction such as RC-70, MC-30 and MC-70. b. There are two types of emulsions that can be used for prime coats. A list of recommended emulsion grades by type is as follows: Anionic Emulsions ASTM D977: SS-1, SS-1h. Cationic Emulsions ASTM D2397/D2397M: CSS-1, CSS-1h. Penetration and coating will be most efficient at about optimum moisture content. Water dilution of the emulsion is also required to reduce viscosity. ************************************************************************** Provide asphalt conforming to either of [AASHTO M 81] [AASHTO M 82], Grade [_____] and specified in the following two subparagraphs. 2.2.1 Cutback Asphalt Provide cutback asphalt conforming to [ASTM D2026/D2026M, Grade SC-70] [ ASTM D2027/D2027M, Grade [MC-30][MC-70]] [ASTM D2028/D2028M, Grade RC-70]. 2.2.2 Emulsified Asphalt Provide emulsified asphalt conforming to [ASTM D977, Type [SS-1] [SS1h]] [ ASTM D2397/D2397M, Type [CSS-1] [CSS-1h]]. 2.3 TACK COAT Provide asphalt conforming to either of the following two subparagraphs. 2.4 Cutback Asphalt Provide cutback asphalt conforming to [ASTM D2026/D2026M, Grade SC-70] [ ASTM D2027/D2027M, Grade [MC-30] [MC-70]] [ASTM D2028/D2028M, Grade RC-70]. 2.4.1 Sub TitleEmulsified Asphalt Text Provide emulsified asphalt conforming to [ASTM D977, Type [SS-1] [SS1h]] [ URS FOR EQM SECTION 32 12 10 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM D2397/D2397M, Type [CSS-1] [CSS-1h]]. Dilute the emulsified asphalt with equal parts of water. The base asphalt used to manufacture the emulsion shall show a negative spot when tested in accordance with AASHTO T 102 using standard naphtha. PART 3 3.1 EXECUTION PREPARATION OF SURFACE ************************************************************************** NOTE: If the surface to be treated requires repairs, the method of repairs and extent of work involved should be shown or described. ************************************************************************** Immediately before applying the bituminous coat, remove all loose material, dirt, clay, or other objectionable material from the surface to be treated by means of hand brooms. The surface shall be dry and clean at the time of treatment. 3.2 APPLICATION RATE ************************************************************************** NOTE: The range of application rates for the bituminous materials is for the bituminous residue content and does not include water or solvents that are contained in emulsified or liquid bituminous materials. The use of liquid or emulsified material requires that the application rates be corrected. Any prescribed application should be corrected and divided into two applications 24 hours apart when necessary to avoid flowing off the surface because of grade or slope. Emulsified asphalt mixing grades such as SS-1, SS-1h, CSS-1, and CSS-1h perform best when diluted with equal parts of water and applied at the rate of 0.23-0.68 liter of diluted emulsion per square meter (0.05-0.15 gallon of diluted emulsion per square yard). ************************************************************************** The exact quantities within the range specified, which may be varied to suit field conditions, will be determined by the Contracting Officer. 3.2.1 Prime Coat Apply bituminous material for the prime coat in quantities of not less than 0.18 gallon nor more than 0.35 gallon per square yard of pavement surface. 3.3 3.3.1 APPLICATION TEMPERATURE Viscosity Relationship Asphalt application temperature shall provide an application viscosity between 10 and 60 seconds, Saybolt Furol, or between 20 and 120 centistokes, kinematic. Furnish the temperature viscosity relation to the Contracting Officer. URS FOR EQM SECTION 32 12 10 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.3.2 TYMX989345A FA3002-09-D-0002 TG02 Temperature Ranges ************************************************************************** NOTE: Normal spray application temperatures are as follows. Edit and coordinate materials with Part 2 PRODUCTS. Retain material to be allowed in the specification and delete the other materials. ************************************************************************** The viscosity requirements determine the application temperature to be used. The following is a normal range of application temperatures: Degrees F Liquid Asphalts MC-30 85-190 Emulsions CSS-1h 70-160 *These temperature ranges exceed the flash point of the material and care should be taken in their heating. 3.4 APPLICATION ************************************************************************** NOTE: Prime coats are required for Navy projects. If the designer for Army jobs chooses not to specify a prime coat at the time of design, delete all references to a prime coat within this section. If the drainage layer is used beneath the surfacing material (Asphalt cement hot mix concrete), the underlying material (base course) will not be primed and the appropriate paragraphs dealing with the prime coat will be deleted. ************************************************************************** 3.4.1 General Following preparation and subsequent inspection of the surface, apply the bituminous prime or tack coat with the Bituminous Distributor at the specified rate with uniform distribution over the surface to be treated. Properly treat all areas and spots missed by the distributor with the hand spray. Until the succeeding layer of pavement is placed, maintain the surface by protecting the surface against damage and by repairing deficient areas at no additional cost to the Government. If required, spread clean dry sand to effectively blot up any excess bituminous material. No smoking, fires, or flames other than those from the heaters that are a part of the equipment are permitted within 25 feet of heating, distributing, and transferring operations of bituminous material other than bituminous emulsions. Prevent all traffic, except for paving equipment used in constructing the surfacing, from using the underlying material, whether primed or not, until the surfacing is completed. The bituminous coat shall URS FOR EQM SECTION 32 12 10 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 conform to all requirements as described herein. 3.4.2 Prime Coat ************************************************************************** NOTE: Conditions where a prime coat may be beneficial include: preventing lateral movement of the unbound base during pavement construction, waterproofing during pavement construction, and forming a tight base to which the asphalt pavement will adhere. To specify the application of a prime coat, retain the first bracketed sentence and delete the text within the second set of brackets. Add prime coat details on drawings. If the prime coat will be retained as a Contractor's option, delete the first sentence and retain the bracketed text in the second set of brackets. ************************************************************************** Apply a prime coat at locations shown on the Drawings. Apply the bituminous material uniformly over the surface to be treated at a pressure range of 25 to 75 psi; the rate shall be as specified above in paragraph APPLICATION RATE. To obtain uniform application of the prime coat on the surface treated at the junction of previous and subsequent applications, spread building paper on the surface for a sufficient distance back from the ends of each application to start and stop the prime coat on the paper and to ensure that all sprayers will operate at full force on the surface to be treated. Immediately after application remove and destroy the building paper. 3.5 CURING PERIOD ************************************************************************** NOTE: Retain bracketed sentence if prime coat is specified. ************************************************************************** Following application of the bituminous material and prior to application of the succeeding layer of pavement, allow the bituminous coat to cure and to obtain evaporation of any volatiles or moisture. Maintain the coated surface until the succeeding layer of pavement is placed, by protecting the surface against damage and by repairing and recoating deficient areas. Allow the prime coat to cure without being disturbed for a period of at least 48 hours or longer, as may be necessary to attain penetration into the treated course. Furnish and spread enough sand to effectively blot up and cure excess bituminous material. 3.6 FIELD QUALITY CONTROL ************************************************************************** NOTE: Select the appropriate paragraph based on the amount of bituminous material required. ************************************************************************** Samples of the bituminous material used shall be obtained by the Contractor as directed, under the supervision of the Contracting Officer. The sample may be retained and tested by the Government at no cost to the Contractor. URS FOR EQM SECTION 32 12 10 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.7 TYMX989345A FA3002-09-D-0002 TG02 SAMPLING AND TESTING Submit copies of all test results for emulsified asphalt, and bituminous materials, within 24 hours of completion of tests. Furnish certified copies of the manufacturer's test reports indicating temperature viscosity relationship for cutback asphalt, compliance with applicable specified requirements, not less than 30 days before the material is required in the work. Perform sampling and testing by an approved commercial testing laboratory or by facilities furnished by the Contractor. No work requiring testing will be permitted until the facilities have been inspected and approved. 3.7.1 Sampling The samples of bituminous material, unless otherwise specified, shall be in accordance with ASTM D140/D140M or AASHTO T 40. Sources from which bituminous materials are to be obtained shall be selected and notification furnished the Contracting Officer within 15 days after the award of the contract. 3.7.2 Calibration Test Furnish all equipment, materials, and labor necessary to calibrate the bituminous distributor. Calibration shall be made with the approved job material and prior to applying the bituminous coat material to the prepared surface. Calibrate the bituminous distributor in accordance with ASTM D2995. 3.7.3 Trial Applications Before providing the complete bituminous coat, apply three lengths of at least 100 feet for the full width of the distributor bar to evaluate the amount of bituminous material that can be satisfactorily applied. 3.7.3.1 Prime Coat Trial Application Rate Unless otherwise authorized, apply the trial application rate of bituminous materials in the amount of 0.25 gallon per square yard. Other trial applications shall be made using various amounts of material as may be deemed necessary. 3.7.4 Sampling and Testing During Construction Perform quality control sampling and testing as required in paragraph FIELD QUALITY CONTROL. 3.8 TRAFFIC CONTROLS Keep traffic off surfaces freshly treated with bituminous material. Provide sufficient warning signs and barricades so that traffic will not travel over freshly treated surfaces. -- End of Section -- URS FOR EQM SECTION 32 12 10 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 12 17 (April 2008) Change 1 - 11/13 -------------------------Preparing Activity: NAVFAC Replacing without change UFGS-32 12 17 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 32 12 17 HOT MIX BITUMINOUS PAVEMENT ************************************************************************** NOTE: This guide specification covers the requirements for hot-mix asphalt pavement for leveling, binder, and wearing courses using virgin materials. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** ************************************************************************** NOTE: This guide specification is not intended for use in hot-mix recycling. ************************************************************************** ************************************************************************** NOTE: The following information shall be shown on drawings: 1. Layout and geometry of paving. 2. Cross section and thickness of paving. ************************************************************************** ************************************************************************** NOTE: Retain only the desired mixes in leveling, binder, and wearing courses. For airfield projects, aggregate gradations shall be as shown in Table I . URS FOR EQM SECTION 32 12 17 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 For vehicular pavement, show gradations for vehicular pavement from local state highway department (as appropriate to the Marshall Method for Design and Control of Bituminous Paving Mixtures). Generally, the maximum size of aggregate for wearing course should not exceed 40 percent of the designed thickness of the course (i.e., course thickness divided by 2.5); in no case should the aggregate size exceed one inch or one-half the thickness of the compacted wearing course or two-thirds the thickness of any binder or leveling course; gradation requirements for the leveling course should be specified to suit the project and may vary from a fine wearing course mix to a coarse binder course mix as dictated by project requirements. When appropriate, the wearing course mix may be specified as an option for the leveling and/or binder course mixes. ************************************************************************** PART 1 1.1 GENERAL REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) AASHTO M 156 (2013) Standard Specification for Requirements for Mixing Plants for Hot-Mixed, Hot-Laid Bituminous Paving Mixtures AASHTO M 320 (2010) Standard Specification for Performance-Graded Asphalt Binder URS FOR EQM SECTION 32 12 17 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASPHALT INSTITUTE (AI) AI MS-2 (1997 6th Ed) Mix Design Methods ASTM INTERNATIONAL (ASTM) ASTM C117 (2013) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing ASTM C127 (2012) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate ASTM C128 (2012) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Fine Aggregate ASTM C131 (2006) Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine ASTM C136 (2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates ASTM C188 (2014) Standard Test Method for Density of Hydraulic Cement ASTM C29/C29M (2009) Standard Test Method for Bulk Density ("Unit Weight") and Voids in Aggregate ASTM C88 (2013) Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate ASTM D1073 (2011) Fine Aggregate for Bituminous Paving Mixtures ASTM D1188 (2007; E 2010) Bulk Specific Gravity and Density of Compacted Bituminous Mixtures Using Paraffin-Coated Specimens ASTM D140/D140M (2014) Standard Practice for Sampling Bituminous Materials ASTM D2041/D2041M (2011) Theoretical Maximum Specific Gravity and Density of Bituminous Paving Mixtures ASTM D2172/D2172M (2011) Quantitative Extraction of Bitumen from Bituminous Paving Mixtures ASTM D242/D242M (2009) Mineral Filler for Bituminous Paving Mixtures ASTM D2726/D2726M (2013) Bulk Specific Gravity and Density URS FOR EQM SECTION 32 12 17 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 of Non-Absorptive Compacted Bituminous Mixtures ASTM D3666 (2013) Standard Specification for Minimum Requirements for Agencies Testing and Inspecting Road and Paving Materials ASTM D4867/D4867M (2009) Effect of Moisture on Asphalt Concrete Paving Mixtures ASTM D546 (2010) Sieve Analysis of Mineral Filler for Bituminous Paving Mixtures ASTM D692/D692M (2009) Coarse Aggregate for Bituminous Paving Mixtures ASTM D6927 (2006) Standard Test Method for Marshall Stability and Flow of Bituminous Mixtures ASTM D70 (2009; E 2009) Specific Gravity and Density of Semi-Solid Bituminous Materials (Pycnometer Method) ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates ASTM D854 (2014) Specific Gravity of Soil Solids by Water Pycnometer ASTM D979/D979M (2012) Sampling Bituminous Paving Mixtures 1.2 SUBMITTALS ************************************************************************** NOTE: Review Submittal Description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G". Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, URS FOR EQM SECTION 32 12 17 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are [for Contractor Quality Control approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: [ SD-04 Samples ************************************************************************** NOTE: Include requirements for test section[s] in all projects with 5,000 tons or more of asphaltic concrete. Test sections may be considered necessary and specified in smaller projects if the pavement structure is critical and the cost of a test section is deemed to be justified. Normally, a test section is required only for the wearing course. If it is deemed necessary to test other courses, the specifications must be modified to suit. ************************************************************************** Bituminous pavement ] SD-05 Design Data Job-mix formula Submit a job-mix formula, prepared specifically for this project [within one year of submittal for roads], for approval [by the Government] prior to preparing and placing the bituminous mixture. Design mix using procedures contained in Chapter V, Marshall Method of Mix Design, of AI MS-2. Formulas shall indicate physical properties of the mixes as shown by tests made by a commercial laboratory approved by the Contracting Officer, using materials identical to those to be provided on this project. Submit formulas with material samples. Job-mix formula for each mixture shall be in effect until modified in writing by the Contractor and approved by the Contracting Officer. Provide a new job-mix formula for each source change. Submittal shall include all tests indicated in MIX DESIGN section of this specification. ASPHALT CEMENT BINDER MIX DESIGN SD-06 Test Reports Specific gravity test of asphalt URS FOR EQM SECTION 32 12 17 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Coarse aggregate tests Weight of slag test Percent of crushed pieces in gravel Fine aggregate tests Specific gravity of mineral filler Bituminous mixture tests Aggregates tests Bituminous mix tests Pavement courses 1.3 1.3.1 QUALITY ASSURANCE Safety Requirements Provide adequate and safe stairways with handrails to the mixer platform, and safe and protected ladders or other means for accessibility to plant operations. Guard equipment and exposed steam or other high temperature lines or cover with a suitable type of insulation. [1.3.2 Mock-Up Test Section ************************************************************************** NOTE: Include requirements for test section[s] in all projects with 5,000 tons or more of asphaltic concrete. Test sections may be considered necessary and specified in smaller projects if the pavement structure is critical and the cost of a test section is deemed to be justified. Normally, a test section is required only for the wearing course. If it is deemed necessary to test other courses, the specifications must be modified to suit. ************************************************************************** Prior to full production of the [binder and] wearing course[s], prepare a quantity of bituminous mixture according to the job-mix formula. Construct a test section 200 feet long by not less than 10 feet wide and of the same compacted depth specified for the construction of the course which the test section represents. The underlying grade or pavement structure upon which the test section is to be constructed shall be the same as the remainder of the course represented by the test section. The equipment used in construction of the test section shall be the same type and weight to be used on the remainder of the course represented by the test section. Test not less than two samples of the mixture produced at the plant for gradation, asphalt cement content, stability, flow, air voids, voids in mineral aggregate, and in weight. Obtain not less than three cores from the test strip for density and thickness tests. Check the test section for smoothness and finish surface texture. If the test section should prove to be unsatisfactory, make the necessary adjustments to the mix design, plant operation, transportation, laydown, [and] [or] rolling procedures. Additional test sections, as required, shall be constructed and evaluated for conformance to the specified requirements. When test sections do not conform to specified requirements, remove and replace the bituminous pavement. A marginal quality test section that has been placed in an area of little or no traffic may be left in place. If a second test section also does not meet specified requirements, remove both sections at the Contractor's expense. Full production shall not begin without the Contracting Officer's approval. URS FOR EQM SECTION 32 12 17 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS ]1.3.2 TYMX989345A FA3002-09-D-0002 TG02 Required Data Job-mix formula shall show the following: a. Source and proportions, percent by weight, of each ingredient of the mixture; b. Correct gradation, the percentages passing each size sieve listed in the specifications for the mixture to be used, for the aggregate and mineral filler from each separate source and from each different size to be used in the mixture and for the composite mixture; c. Amount of material passing the No. 200 sieve determined by dry sieving; d. Number of blows of hammer compaction per side of molded specimen; e. Temperature viscosity relationship of the asphalt cement; f. Stability, flow, percent voids in mineral aggregate, percent air voids, unit weight; g. Asphalt absorption by the aggregate; h. Effective asphalt content as percent by weight of total mix; i. Temperature of the mixture immediately upon completion of mixing; j. Asphalt performance grade[viscosity grade] [ penetration range]; and k. Curves for the[leveling] [binder] [and] wearing course[s]. 1.3.3 Charts Plot and submit, on a grain size chart, the specified aggregate gradation band, the job-mix gradation and the job-mix tolerance band. 1.3.4 Selection of Optimum Asphalt Content Base selection on percent of total mix and the average of values at the following points on the curves for each mix: a. Stability: b. Unit Weight: c. Percent Air Voids: 1.4 Peak Peak Median DELIVERY, STORAGE, AND HANDLING Inspect materials delivered to the site for damage and store with a minimum of handling. Store aggregates in such a manner as to prevent segregation, contamination, or intermixing of the different aggregate sizes. 1.5 ENVIRONMENTAL CONDITIONS Place bituminous mixture only during dry weather and on dry surfaces. Place courses only when the surface temperature of the underlying course is greater than 45 degrees F for course thicknesses greater than one inch and 55 degrees F for course thicknesses one inch or less. URS FOR EQM SECTION 32 12 17 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.6 TYMX989345A FA3002-09-D-0002 TG02 CONSTRUCTION EQUIPMENT Calibrated equipment, such as scales, batching equipment, spreaders and similar equipment, shall have been recalibrated by a calibration laboratory approved by the Contracting Officer within [12] [_____] months of commencing work. 1.6.1 Mixing Plant ************************************************************************** NOTE: Insert minimum acceptable capacity. Suggest 100 tons/hr, except where project schedule requirements need greater production capacities. ************************************************************************** Design, coordinate, and operate the mixing plant to produce a mixture within the job-mix formula tolerances and to meet the requirements of AASHTO M 156, including additional plant requirements specified herein. The plant shall be a batch type, continuous mix type or drum-dryer mixer type, and shall have sufficient capacity to handle the new bituminous construction. Minimum plant capacity shall be [100] [_____] tons per hour. The mixing plant and equipment shall remain accessible at all times for inspecting operation, verifying weights, proportions and character of materials, and checking mixture temperatures. 1.6.1.1 Cold Aggregate Feeder Provide plant with a feeder or feeders capable of delivering the maximum number of aggregate sizes required in their proper proportion. Provide adjustment for total and proportional feed and feeders capable of being locked in any position. When more than one cold elevator is used, feed each elevator as a separate unit and install individual controls integrated with a master control. 1.6.1.2 Dryer Provide rotary drum-dryer which continuously agitates the mineral aggregate during the heating and drying process. When one dryer does not dry the aggregate to specified moisture requirements, provide additional dryers. 1.6.1.3 Plant Screens and Bins for Batch and Continuous Mix Plants Use screen to obtain accurate gradation and allow no bin to contain more than 10 percent oversize or undersize. Inspect screens each day prior to commencing work for plugged, worn, or broken screens. Clean plugged screens and replace worn or broken screens with new screens prior to beginning operations. Divide hot aggregate bins into at least three compartments arranged to ensure separate and adequate storage of appropriate fractions of the aggregate. 1.6.1.4 Testing Laboratory Provide a testing laboratory for control and acceptance testing functions during periods of mix production, sampling and testing, and whenever materials subject to the provisions of these specifications are being supplied or tested. The laboratory shall provide adequate equipment, space, and utilities as required for the performance of the specified tests. URS FOR EQM SECTION 32 12 17 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.6.1.5 TYMX989345A FA3002-09-D-0002 TG02 Surge and Storage Bins Use for temporary storage of hot bituminous mixtures will be permitted under the following conditions: a. When stored in surge bins for a period of time not to exceed 3 hours. b. When stored in insulated and heated storage bins for a period of time not to exceed 12 hours. If it is determined by the Contracting Officer that there is an excessive amount of heat loss, segregation and oxidation of the mixture due to temporary storage, discontinue use of surge bins or storage bins. 1.6.1.6 Drum-Dryer Mixer Do not use drum-dryer mixer if specified requirements of the bituminous mixture or of the completed bituminous pavement course cannot be met. If drum-dryer mixer is prohibited, use either batch or continuous mix plants meeting the specifications and producing a satisfactory mix. 1.6.2 1.6.2.1 Paving Equipment Spreading Equipment Self-propelled electronically controlled type, unless other equipment is authorized [by the Contracting Officer]. Equip spreading equipment of the self-propelled electronically controlled type with hoppers, tamping or vibrating devices, distributing screws, electronically adjustable screeds, and equalizing devices. Capable of spreading hot bituminous mixtures without tearing, shoving, or gouging and to produce a finished surface of specified grade and smoothness. Operate spreaders, when laying mixture, at variable speeds between 5 and 45 feet per minute. Design spreader with a quick and efficient steering device; a forward and reverse traveling speed; and automatic devices to adjust to grade and confine the edges of the mixture to true lines. The use of a spreader that leaves indented areas or other objectionable irregularities in the fresh laid mix during operations is prohibited. 1.6.2.2 Rolling Equipment Self-propelled pneumatic-tired rollers supplemented by three-wheel and tandem type steel wheel rollers. The number, type and weight of rollers shall be sufficient to compact the mixture to the required density without detrimentally affecting the compacted material. Rollers shall be suitable for rolling hot-mix bituminous pavements and capable of reversing without backlash. Pneumatic-tired rollers shall be capable of being operated both forward and backward without turning on the mat, and without loosening the surface being rolled. Equip rollers with suitable devices and apparatus to keep the rolling surfaces wet and prevent adherence of bituminous mixture. Vibratory rollers especially designed for bituminous concrete compaction may be used provided rollers do not impair stability of pavement structure and underlying layers. Repair depressions in pavement surfaces resulting from use of vibratory rollers. Rollers shall be self-propelled, single or dual vibrating drums, and steel drive wheels, as applicable; equipped with variable amplitude and separate controls for energy and propulsion. 1.6.2.3 Hand Tampers Minimum weight of 25 pounds with a tamping face of not more than 50 square URS FOR EQM SECTION 32 12 17 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 inches. 1.6.2.4 Mechanical Hand Tampers Commercial type, operated by pneumatic pressure or by internal combustion. PART 2 2.1 PRODUCTS AGGREGATES Grade and proportion aggregates and filler so that combined mineral aggregate conforms to specified grading. 2.1.1 Coarse Aggregates ************************************************************************** NOTE: When coarse and/or fine aggregate available locally is of questionable or unsatisfactory quality, modify paragraphs to allow only specific type(s) of aggregate with a satisfactory performance record. ************************************************************************** ASTM D692/D692M, except as modified herein. At least 75 percent by weight of aggregate retained on the No. 4 sieve shall have two or more fractured faces. Percentage of wear, Los Angeles test, except for slag, shall not exceed 40 in accordance with ASTM C131. Weight of slag shall not be less than 70 pounds per cubic foot. Soundness test is required in accordance with ASTM C88; after 5 cycles, loss shall not be more than 12 percent when tested with sodium sulfate or 18 percent when tested with magnesium sulfate. 2.1.2 Fine Aggregate ************************************************************************** NOTE: When coarse and/or fine aggregate available locally is of questionable or unsatisfactory quality, modify paragraphs to allow only specific type(s) of aggregate with a satisfactory performance record. ************************************************************************** ASTM D1073, except as modified herein. Fine aggregate shall be produced by crushing stone, slag or gravel that meets requirements for wear and soundness specified for coarse aggregate. Where necessary to obtain the gradation of aggregate blend or workability, natural sand may be used. Quantity of natural sand to be added shall be approved [by the Contracting Officer] and shall not exceed [15] [_____] percent of weight of coarse and fine aggregate and material passing the No. 200 sieve. 2.1.3 Mineral Filler Nonplastic material meeting the requirements of ASTM D242/D242M. 2.1.4 Aggregate Gradation ************************************************************************** NOTE: Delete from Table I, the gradations that will not be used as a part of this project. Generally, the layer thickness should be at least 57 mm (2.25 URS FOR EQM SECTION 32 12 17 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 inches) for gradation 1, 37 mm (1.5 inches) for gradation 2 and 28 mm (1 inch) for gradation 3 shown in Table 2. Use of gradation 3 should be limited to shoulders and leveling courses. ************************************************************************** The combined aggregate gradation shall conform to gradations specified in Table I, when tested in accordance with ASTM C136 and ASTM C117, and shall not vary from the low limit on one sieve to the high limit on the adjacent sieve or vice versa, but grade uniformly from coarse to fine. Table I. Aggregate Gradations Gradation 2 Sieve Size, inch Percent Passing by Mass 1 --- 3/4 100 1/2 76-96 3/8 69-89 No. 4 53-73 No. 8 38-60 No. 16 26-48 No. 30 18-38 No. 50 11-27 No. 100 6-18 No. 200 3-6 2.2 ASPHALT CEMENT BINDER ************************************************************************** NOTE: Performance Graded (PG) d asphalt binders should be specified wherever available. The same grade PG binder used by the state highway department in the area should be considered as the base grade for the project (e.g. the grade typically specified in that specific location for dense graded mixes on highways with design ESALS less than 10 million). The exception would be that grades with a low temperature higher than PG XX-22 should not be used (e.g. PG XX-16 or PG XX-10), unless the Engineer has had successful experience with them. Typically, rutting is not a problem on airfield URS FOR EQM SECTION 32 12 17 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 runways. However, the following grade "bumping" should be applied for paving in the runway and taxiway areas: to accommodate for aircraft tire pressure greater than 200 psi, increase the high temperature two grades. Each grade adjustment is 6 degrees C. The low temperature grade should remain the same. ************************************************************************** Asphalt cement binder shall conform to [ASTM D3381/D3381M Table 2, Viscosity Grade [_____]] [AASHTO M 320 Performance Grade (PG) 76-22[_____]][ ASTM D946/D946M Penetration Grade [_____]]. Test data indicating grade certification shall be provided by the supplier at the time of delivery of each load to the mix plant. Copies of these certifications shall be submitted to the Contracting Officer. The supplier is defined as the last source of any modification to the binder. The Contracting Officer may sample and test the binder at the mix plant at any time before or during mix production. Samples for this verification testing shall be obtained by the Contractor in accordance with ASTM D140/D140M and in the presence of the Contracting Officer. These samples shall be furnished to the Contracting Officer for the verification testing, which shall be at no cost to the Contractor. Samples of the asphalt cement specified shall be submitted for approval not less than 14 days before start of the test section. 2.3 MIX DESIGN The Contractor shall develop the mix design. The asphalt mix shall be composed of a mixture of well-graded aggregate, mineral filler if required, and asphalt material. The aggregate fractions shall be sized, handled in separate size groups, and combined in such proportions that the resulting mixture meets the grading requirements of the job mix formula (JMF). No hot-mix asphalt for payment shall be produced until a JMF has been approved. The hot-mix asphalt shall be designed using procedures contained in AI MS-2 and the criteria shown in Table II. If the Tensile Strength Ratio (TSR) of the composite mixture, as determined by ASTM D4867/D4867M is less than 75, the aggregates shall be rejected or the asphalt mixture treated with an approved anti-stripping agent. The amount of anti-stripping agent added shall be sufficient to produce a TSR of not less than 75. If an antistrip agent is required, it shall be provided by the Contractor at no additional cost. 2.3.1 JMF Requirements ************************************************************************** NOTE: In Table II, use a 75 Blow (compactive effort) Marshall Mix for all pavements designed for tire pressures of 100 psi or higher. For pavements designed for tire pressures less than 100 psi, use a 50 Blow Mix. Also, use a 50 Blow Mix for shoulder pavements. In Table II, delete the column which does not apply, unless the project includes both 75 Blow and 50 Blow mixes. Select the appropriate gradation and VMA requirements in Table III to be consistent with the gradation chosen in Table I. Delete the other two URS FOR EQM SECTION 32 12 17 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 lines in Table III. Remove item s., below if RAP is not used in the job. Tensile Strength Ratio for San Diego - El Centro, California area and other areas with lower quality aggregate (that meets all other requirements) and low annual rainfall, use 65, otherwise use 75. ************************************************************************** The job mix formula shall be submitted in writing by the Contractor for approval at least 14 days prior to the start of the test section and shall include as a minimum: a. Percent passing each sieve size. b. Percent of asphalt cement. c. Percent of each aggregate and mineral filler to be used. d. Asphalt viscosity grade, penetration grade, or performance grade. e. Number of blows of hammer per side of molded specimen. f. Laboratory mixing temperature. g. Lab compaction temperature. h. Temperature-viscosity relationship of the asphalt cement. i. Plot of the combined gradation on the 0.45 power gradation chart, stating the nominal maximum size. j. Graphical plots of stability, flow, air voids, voids in the mineral aggregate, and unit weight versus asphalt content as shown in AI MS-2. k. Specific gravity and absorption of each aggregate. l. Percent natural sand. m. Percent particles with two or more fractured faces (in coarse aggregate). n. Fine aggregate angularity. o. Percent flat or elongated particles (in coarse aggregate). p. Tensile Strength Ratio. q. Antistrip agent (if required) and amount. r. List of all modifiers and amount. s. Percentage and properties (asphalt content, binder properties, and aggregate properties) of RAP in accordance with paragraph RECYCLED HOT-MIX ASPHALT, if RAP is used. URS FOR EQM SECTION 32 12 17 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS Table II. TYMX989345A FA3002-09-D-0002 TG02 Marshall Design Criteria Test Property 50 Blow Mix Stability, pounds minimum *1350 Flow, 0.01 inch 8-18 Air voids, percent 3-5 Percent Voids in mineral aggregate (minimum) See Table III TSR, minimum percent 75 * This is a minimum requirement. The average during construction shall be significantly higher than this number to ensure compliance with the specifications. Table III. Minimum Percent Voids in Mineral Aggregate (VMA)** Aggregate (See Table 2) Minimum VMA, percent Gradation 2 14.0 ** Calculate VMA in accordance with AI MS-2, based on ASTM D2726/D2726M bulk specific gravity for the aggregate. 2.3.2 Adjustments to JMF The JMF for each mixture shall be in effect until a new formula is approved in writing by the Contracting Officer. Should a change in sources of any materials be made, a new mix design shall be performed and a new JMF approved before the new material is used. The Contractor will be allowed to adjust the JMF within the limits specified below to optimize mix volumetric properties. Adjustments to the JMF shall be limited to plus or minus 3 percent on the 1/2 inch, No. 4, and No. 8 sieves; plus or minus 1.0 percent on the No. 200 sieve; and plus or minus 0.40 percent binder content. If adjustments are needed that exceed these limits, a new mix design shall be developed. Tolerances given above may permit the aggregate grading to be outside the limits shown in Table I; this is acceptable. 2.4 RECYCLED HOT MIX ASPHALT ************************************************************************** NOTE: Reclaimed Asphalt Pavement (RAP) should not be used for surface mixes, except on shoulders. It can be used very effectively in lower layers, or for shoulders. The Contractor should be able to use URS FOR EQM SECTION 32 12 17 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 RAP, up to 30 percent, as long as the resulting recycled mix meets all requirements that are specified for virgin mixtures. Remove these paragraphs if RAP is not used. ************************************************************************** Reclaimed asphalt pavement (RAP) is not permitted. 2.5 SOURCE QUALITY CONTROL Employ a commercial laboratory approved by the Contracting Officer to perform testing. The laboratory used to develop the JMF and the laboratory used to perform all sampling and testing shall meet the requirements of ASTM D3666. A certification signed by the manager of the laboratory stating that it meets these requirements or clearly listing all deficiencies shall be submitted to the Contracting Officer prior to the start of construction. The certification shall contain as a minimum: a. Qualifications of personnel; laboratory manager, supervising technician, and testing technicians. b. A listing of equipment to be used in developing the job mix. c. A copy of the laboratory's quality control system. d. Evidence of participation in the AASHTO Materials Reference Laboratory (AMRL) program. 2.5.1 Tests Perform testing in accordance with the following: a. Specific Gravity Test of Asphalt: b. Coarse Aggregate Tests: (1) Bulk Specific Gravity: (2) Abrasion Loss: (3) Soundness Loss: ASTM D70 ASTM C127 ASTM C131 ASTM C88 c. Weight of Slag Test: ASTM C29/C29M d. Percent of Crushed Pieces in Gravel: e. Fine Aggregate Tests: (1) Bulk Specific Gravity: (2) Soundness Loss: Count by observation and weight ASTM C128 ASTM C88 f. Specific Gravity of Mineral Filler: g. Bituminous Mixture Tests: ASTM C188 or ASTM D854 (1) Bulk Specific Gravity: (2) Theoretical Maximum Specific Gravity: URS FOR EQM ASTM D1188 or ASTM D2726/D2726M SECTION 32 12 17 ASTM D2041/D2041M Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS (3) 2.5.2 Tensile Strength Ratio: TYMX989345A FA3002-09-D-0002 TG02 ASTM D4867/D4867M Specimens ASTM D6927 for the making and testing of bituminous specimens with the following exceptions: ************************************************************************** NOTE: At the text below, for traffic with tire pressures 100 psi and over and also for primary roads and streets, specify 75 blows; for tire pressures less than 100 psi and for secondary roads, streets, and parking areas, specify 50 blows. ************************************************************************** a. Compaction: Apply [5075 blows of the hammer to each flat face of the specimens for mix numbers [_____] and [_____]] [and 50 blows for mix numbers [_____] and [_____]]. b. Curves: Plot curves for the [leveling,] [binder,] [and] wearing course [s] to show the effect on the test properties of at least four different percentages of asphalt on the unit weight, stability, flow, air voids, and voids in mineral aggregate; each point on the curves shall represent the average of at least four specimens. c. Cooling of Specimen: After compaction is completed, allow the specimen to cool in air to the same temperature approximately as that of the water, 77 degrees F, to be used in the specific gravity determination. PART 3 3.1 3.1.1 EXECUTION PREPARATION Preparation of Asphalt Binder Material The asphalt cement material shall be heated avoiding local overheating and providing a continuous supply of the asphalt material to the mixer at a uniform temperature. The temperature of unmodified asphalts shall be no more than 325 degrees F when added to the aggregates. Modified asphalts shall be no more than 350 degrees F when added to the aggregate. 3.1.2 Preparation of Mineral Aggregates Store different size aggregate in separate stockpiles so that different sizes will not mix. Stockpile different-sized aggregates in uniform layers by use of a clam shell or other approved method so as to prevent segregation. The use of bulldozers in stockpiling of aggregate or in feeding aggregate to the dryer is prohibited. Feed aggregates into the cold elevator by means of separate mechanical feeders so that aggregates are graded within requirements of the job-mix formulas and tolerances specified. Regulate rates of feed of the aggregates so that moisture content and temperature of aggregates are within tolerances specified herein. Dry and heat aggregates to the temperature necessary to achieve the mixture determined by the job mix formula within the job tolerance specified. Provide adequate dry storage for mineral filler. URS FOR EQM SECTION 32 12 17 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.1.3 TYMX989345A FA3002-09-D-0002 TG02 Preparation of Bituminous Mixture Accurately weigh aggregates and dry mineral filler and convey into the mixer in the proportionate amounts of each aggregate size required to meet the job-mix formula. In batch mixing, after aggregates and mineral filler have been introduced into the mixer and mixed for not less than 15 seconds, add asphalt by spraying or other approved methods and continue mixing for a period of not less than 20 seconds, or as long as required to obtain a homogeneous mixture. The time required to add or spray asphalt into the mixer will not be added to the total wet-mixing time provided the operation does not exceed 10 seconds and a homogeneous mixture is obtained. When a continuous mixer is employed, mixing time shall be more than 35 seconds to obtain a homogeneous mixture. Additional mixing time, when required, will be as directed by the Contracting Officer. When mixture is prepared in a twin-pugmill mixer, volume of the aggregates, mineral filler, and asphalt shall not extend above tips of mixer blades when blades are in a vertical position. Overheated and carbonized mixtures, or mixtures that foam or show indication of free moisture, will be rejected. When free moisture is detected in batch or continuous mix plant produced mixtures, waste the mix and withdraw the aggregates in the hot bins immediately and return to the respective stockpiles; for drum-dryer mixer plants, waste the mix, including that in surge or storage bins that is affected by free moisture. 3.1.4 Transportation of Bituminous Mixtures Transport bituminous material from the mixing plant to the paving site in trucks having tight, clean, smooth beds that have been coated with a minimum amount of concentrated solution of hydrated lime and water or other approved coating to prevent adhesion of the mixture to the truck. Petroleum products will not be permitted for coating truck. If air temperature is less than 60 degrees F or if haul time is greater than 30 minutes, cover each load with canvas or other approved material of ample size to protect the mixture from the loss of heat. Make deliveries so that the spreading and rolling of all the mixture prepared for one day's run can be completed during daylight, unless adequate approved artificial lighting is provided. Deliver mixture to area to be paved so that the temperature at the time of dumping into the spreader is within the range specified herein. Reject loads that are below minimum temperature, that have crusts of cold unworkable material, or that have been wet excessively by rain. Hauling over freshly laid material is prohibited. 3.1.5 Surface Preparation of Underlying Course Prior to the laying of the asphalt concrete, clean underlying course of foreign or objectionable matter with power blowers or power brooms, supplemented by hand brooms and other cleaning methods where necessary. During the placement of multiple lifts of bituminous concrete, each succeeding lift of bituminous concrete shall have its underlying lift cleaned and provided with a bituminous tack coat if the time period between the placement of each lift of bituminous concrete exceeds 14 days, or the underlying bituminous concrete has become dirty. [Remove grass and other vegetative growth from existing cracks and surfaces.] 3.2 PLACEMENT 3.2.1 Machine Spreading ************************************************************************** NOTE: See Table IV for minimum spreading temperatures depending on temperatures of existing URS FOR EQM SECTION 32 12 17 Page 17 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 base course and thickness of layer being placed. TABLE IV MINIMUM SPREADING TEMPERATURES Base Temp. in Degrees F (*) Wearing, Binder, or Leveling Course Thickness, (Inches) 1/2 3/4 1 1 1/2 2 3 20-32 (**) --- --- --- --- --- --- +32-40 (**) +40-50 --- --- --- --- 295 --- --- --- 300 +50-60 --- --- 300 +60-70 --- 300 +70-80 300 +80-90 +90 * Note: 3 1/2 4 260 (**) 280 275 (**) 270 285 275 265 255 295 280 280 260 255 290 285 275 265 255 250 290 285 280 070 265 255 250 290 280 275 270 265 260 250 250 280 275 270 265 265 255 250 250 260 Base on which mix is placed. ** Note: Increase by 15 degrees when placement is on base or subbase containing frozen moisture. Normally, hot mix paving is not allowed on base temperatures below 45 degrees F. ************************************************************************** The range of temperatures of the mixtures at the time of spreading shall be between [250] [_____] degrees F and 300 degrees F. Bituminous concrete having temperatures less than minimum spreading temperature when dumped into the spreader will be rejected. Adjust spreader and regulate speed so that the surface of the course is smooth and continuous without tears and pulling, and of such depth that, when compacted, the surface conforms with the cross section, grade, and contour indicated. Unless otherwise directed, begin the placing along the centerline of areas to be paved on a crowned section or on the high side of areas with a one-way slope. Place mixture in consecutive adjacent strips having a minimum width of 10 feet, except where the edge lanes require strips less than 10 feet to complete the area. Construct longitudinal joints and edges to true line markings. Establish lines parallel to the centerline of the area to be paved, and place string lines coinciding with the established lines for the spreading machine to follow. Provide the number and location of the lines needed to accomplish proper grade control. When specified grade and smoothness requirements can be met for initial lane construction by use of an approved long ski-type device of not less than [30] [_____] feet in length and for subsequent lane construction by use of a short ski or shoe, in-place string lines for grade control may be omitted. Place mixture as nearly continuous as possible and adjust the speed of placing as needed to permit proper rolling. URS FOR EQM SECTION 32 12 17 Page 18 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.2.2 TYMX989345A FA3002-09-D-0002 TG02 Shoveling, Raking, and Tamping After Machine-Spreading Shovelers and rakers shall follow the spreading machine. Add or remove hot mixture and rake the mixture as required to obtain a course that when completed will conform to requirements specified herein. Broadcasting or fanning of mixture over areas being compacted is prohibited. When segregation occurs in the mixture during placing, suspend spreading operation until the cause is determined and corrected. Correct irregularities in alignment left by the spreader by trimming directly behind the machine. Immediately after trimming, compact edges of the course by tamping laterally with a metal lute or by other approved methods. Distortion of the course during tamping is prohibited. 3.2.3 Hand-Spreading in Lieu of Machine-Spreading In areas where the use of machine spreading is impractical, spread mixture by hand. The range of temperatures of the mixtures when dumped onto the area to be paved shall be between [250] [_____] and 300 degrees F. Mixtures having temperatures less than minimum spreading temperature when dumped onto the area to be paved will be rejected. Spread hot mixture with rakes in a uniformly loose layer of a thickness that, when compacted, will conform to the required grade, thickness, and smoothness. During hand spreading, place each shovelful of mixture by turning the shovel over in a manner that will prevent segregation. Do not place mixture by throwing or broadcasting from a shovel. Do not dump loads any faster than can be properly handled by the shovelers and rakers. 3.3 COMPACTION OF MIXTURE ************************************************************************** NOTE: Insert appropriate percent density; normally, 96 percent for pavements subject to vehicular traffic and 97 percent for pavements subject to aircraft traffic. ************************************************************************** Compact mixture by rolling. Begin rolling as soon as placement of mixture will bear rollers. Delays in rolling freshly spread mixture shall not be permitted. Start rolling longitudinally at the extreme sides of the lanes and proceed toward center of pavement, or toward high side of pavement with a one-way slope. Operate rollers so that each trip overlaps the previous adjacent strip by at least one foot. Alternate trips of the roller shall be of slightly different lengths. Conduct tests for conformity with the specified crown, grade and smoothness immediately after initial rolling. Before continuing rolling, correct variations by removing or adding materials as necessary. If required, subject course to diagonal rolling with the steel wheeled roller crossing the lines of the previous rolling while mixture is hot and in a compactible condition. Speed of the rollers shall be slow enough to avoid displacement of hot mixture. Correct displacement of mixture immediately by use of rakes and fresh mixture, or remove and replace mixture as directed. Continue rolling until roller marks are eliminated and course has a density of at least 95[_____] percent but not more than 100 percent of that attained in a laboratory specimen of the same mixture prepared in accordance with ASTM D6927. During rolling, moisten wheels of the rollers enough to prevent adhesion of mixture to wheels, but excessive water is prohibited. Operation of rollers shall be by competent and experienced operators. Provide sufficient rollers for each spreading machine in operation on the job and to handle plant output. In places not accessible to the rollers, compact mixture thoroughly with URS FOR EQM SECTION 32 12 17 Page 19 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 hot hand tampers. Skin patching of an area after compaction is prohibited. Remove mixture that becomes mixed with foreign materials or is defective and replace with fresh mixture compacted to the density specified herein. Roller shall pass over unprotected edge of the course only when laying of course is to be discontinued for such length of time as to permit mixture to become cold. 3.4 JOINTS Joints shall present the same texture and smoothness as other portions of the course, except permissible density at the joint may be up to 2 percent less than the specified course density. Carefully make joints between old and new pavement or within new pavements in a manner to ensure a thorough and continuous bond between old and new sections of the course. Vertical contact surfaces of previously constructed sections that are coated with dust, sand, or other objectionable material shall be painted with a thin uniform coat of emulsion or other approved bituminous material just before placing fresh mixture. 3.4.1 Transverse Roller shall pass over unprotected end of freshly laid mixture only when laying of course is to be discontinued. Except when an approved bulkhead is used, cut back the edge of previously laid course to expose an even, vertical surface for the full thickness of the course. When required, rake fresh mixture against joints, thoroughly tamp with hot tampers, smooth with hot smoothers, and roll. Transverse joints in adjacent lanes shall be offset a minimum of 2 feet. 3.4.2 Longitudinal Joints Space 6 inches apart. Do not allow joints to coincide with joints of existing pavement or previously placed courses. Spreader screed shall overlap previously placed lanes 2 to 3 inches and be of such height to permit compaction to produce a smooth dense joint. With a lute, push back mixture placed on the surface of previous lanes to the joint edge. Do not scatter mix. Remove and waste excess material. When edges of longitudinal joints are irregular, honeycombed, or poorly compacted, cut back unsatisfactory sections of joint and expose an even vertical surface for the full thickness of the course. When required, rake fresh mixture against joint, thoroughly tamp with hot tampers, smooth with hot smoothers, and roll while hot. 3.5 FIELD QUALITY CONTROL ************************************************************************** NOTE: The Contractor shall normally conduct all sampling and testing at his expense, as stated in the Quality Control section. There may be certain special occasions where the Government will conduct sampling and testing. In those cases, so state that sampling and testing will be conducted by the Government. ************************************************************************** ************************************************************************** NOTE: Employ a commercial laboratory approved by the Contracting Officer to perform all sampling and testing. The laboratory used shall meet the URS FOR EQM SECTION 32 12 17 Page 20 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 requirements of ASTM D3666 and as indicated in SOURCE QUALITY CONTROL section. ************************************************************************** 3.5.1 Sampling 3.5.1.1 Aggregates At Source Prior to production and delivery of aggregates, take at least one initial sample in accordance with ASTM D75/D75M [at the source] [from each stockpile ]. Collect each sample by taking three incremental samples at random from the source material to make a composite sample of not less than 50 pounds. Repeat the sampling when the material source changes or when testing reveals unacceptable deficiencies or variations from the specified grading of materials. 3.5.1.2 Cold Feed Aggregate Sampling Take two samples daily from the belt conveying materials from the cold feed. Collect materials in three increments at random to make a representative composite sample of not less than 50 pounds. Take samples in accordance with ASTM D75/D75M. 3.5.1.3 Coarse and Fine Aggregates Take a 50 pound sample from the cold feed at least once daily for sieve analyses and specific gravity tests. Additional samples may be required to perform more frequent tests when analyses show deficiencies, or unacceptable variances or deviations. The method of sampling is as specified herein for aggregates. 3.5.1.4 Mineral Filler ASTM D546. 3.5.1.5 Take samples large enough to provide ample material for testing. Pavement and Mixture Take plant samples for the determination of mix properties and field samples for thickness and density of the completed pavements. Furnish tools, labor and material for samples, and satisfactory replacement of pavement. Take samples and tests at not less than frequency specified hereinafter and at the beginning of plant operations; for each day's work as a minimum; each change in the mix or equipment; and as often as directed. Accomplish sampling in accordance with ASTM D979/D979M. 3.5.2 Testing 3.5.2.1 Aggregates Tests a. Gradation: b. Mineral Filler Content: c. Abrasion: ASTM C131 for wear (Los Angeles test). Perform one test initially prior to incorporation into the work and each time the source is changed. URS FOR EQM ASTM C136. ASTM D546. SECTION 32 12 17 Page 21 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.5.2.2 TYMX989345A FA3002-09-D-0002 TG02 Bituminous Mix Tests Test one sample for each 500 tons, or fraction thereof, of the uncompacted mix for extraction in accordance with ASTM D2172/D2172M; perform a sieve analysis on each extraction sample in accordance with ASTM C136 and ASTM C117. Test one sample for each [500] [_____] tons or fraction thereof for stability and flow in accordance with ASTM D6927. Test one sample for each material blend for Tensile Strength Ratio in accordance with ASTM D4867/D4867M. 3.5.2.3 Pavement Courses Perform the following tests: a. Density: For each [1000] [_____] tons of bituminous mixture placed, determine the representative laboratory density by averaging the density of four laboratory specimens prepared in accordance with ASTM D6927. Samples for laboratory specimens shall be taken from trucks delivering mixture to the site; record in a manner approved by the Contracting Officer the project areas represented by the laboratory densities. From each representative area recorded, determine field density of pavement by averaging densities of 4 inch diameter cores obtained from [leveling,] [binder, and] wearing course[s]; take one core for each [2000] [_____] square yards or fraction thereof of course placed. Determine density of laboratory prepared specimens and cored samples in accordance with ASTM D1188 or ASTM D2726/D2726M, as applicable. Separate pavement layers by sawing or other approved means. Maximum allowable deficiency at any point, excluding joints, shall not be more than 2 percent less than the specified density for any course. The average density of each course, excluding joints, shall be not less than the specified density. Joint densities shall not be more than 2 percent less than specified course densities and are not included when calculating average course densities. When the deficiency exceeds the specified tolerances, correct each such representative area or areas by removing the deficient pavement and replacing with new pavement. b. Thickness: Determine thickness of[binder and] wearing courses from samples taken for the field density test. The maximum allowable deficiency at any point shall not be more than 1/4 inch less than the thickness for the indicated course. Average thickness of course or of combined courses shall be not less than the indicated thickness. Where a deficiency exceeds the specified tolerances, correct each such representative area or areas by removing the deficient pavement and replacing with new pavement. c. Smoothness: Straightedge test the compacted surface of [leveling,] [binder, and] wearing course[s] as work progresses. Apply straightedge parallel with and at right angles to the centerline after final rolling. Unevenness o[leveling and] [binder]f course[s] shall not vary more than 1/4 inch in 10 feet; variations in the wearing course shall not vary more than 1/8 inch in 10 feet. Correct each portion of the pavement showing irregularities greater than that specified. ************************************************************************** NOTE: Regarding the text below, the Engineering Field Division (EFD) will determine whether the Contracting Officer or the Contractor will perform the survey. At the option of EFD, this subparagraph may be deleted entirely. URS FOR EQM SECTION 32 12 17 Page 22 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** d. Finished Grades: Finish grades of each course placed shall not vary from the finish elevations, profiles, and cross sections indicated by more than 1/2 inch. Finished surface of the final wearing course will be tested [by the Contracting Officer] by running lines of levels at intervals of [25] [_____] feet longitudinally and transversely to determine elevations of completed pavement. Within 45 days after completion of final placement, [perform a level survey at the specified grid spacing and plot the results on a plan drawn to the same scale as the drawings. Elevations not in conformance with the specified tolerance shall be noted on the plan in an approved manner. The survey shall be performed by a registered land surveyor.] [The Contracting Officer will inform the Contractor in writing of paved areas that fail to meet the final grades indicated within the specified tolerances.] Correct deficient paved areas by removing existing work and replacing with new materials that meet the specifications. Skin patching for correcting low areas is prohibited. e. Finish Surface Texture of Wearing Course: Visually check final surface texture for uniformity and reasonable compactness and tightness.Final wearing course with a surface texture having undesirable irregularities such as segregation, cavities, pulls or tears, checking, excessive exposure of coarse aggregates, sand streaks, indentations, ripples, or lack of uniformity shall be removed and replaced with new materials. 3.6 PROTECTION Do not permit vehicular [and aircraft] traffic, including heavy equipment, on pavement until surface temperature has cooled to at least 120 degrees F. Measure surface temperature by approved surface thermometers or other satisfactory methods. -- End of Section -- URS FOR EQM SECTION 32 12 17 Page 23 65% - 01/23/2015 This Page Left Intentionally Blank REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 13 11 (November 2012) Change 1 - 11/14 --------------------------Preparing Activity: USACE Superseding UFGS-32 13 11 (August 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 32 13 11 CONCRETE PAVEMENT FOR AIRFIELDS AND OTHER HEAVY-DUTY PAVEMENTS ************************************************************************** NOTE: This guide specification covers the requirements for construction of concrete pavement for Army, Navy and Air Force airfields and heavy-duty roads, parking areas, hardstands, and vehicular pavement. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: In preparing contract specifications for concrete pavement, the designer will use UFC 3-250-04 STANDARD PRACTICE FOR CONCRETE PAVEMENTS for guidance. State highway specifications may only be used for non organizational parking, roads, streets, and driveways where the equivalent passes of an 18-kip EASL are less than 5.7 million. All organizational vehicle parking, roads and airfield concrete pavements will use the Unified Facilities guide specifications without exception. Contact the Corps of Engineers Transportation URS FOR EQM SECTION 32 13 11 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Systems Center (TSMCX), the Air Force major command (MAJCOM) pavement engineers, or Naval Facilities Engineering Command (NAVFAC) for guidance on interpreting and editing this specification section. This specification section is structured for Contractor sampling and testing of materials and mixture proportioning. If Government sampling, testing and mixture proportioning is required, contact the TSMCX, MAJCOM pavement engineers, or NAVFAC for specification language. ************************************************************************** 1.1 UNIT PRICES ************************************************************************** NOTE: Any project large enough to use this guide specification should have Unit Price payment. For Lump Sum payment, include concrete unit price from Government estimate in paragraph Payments to provide cost basis for calculating payment reduction. ************************************************************************** 1.1.1 Measurements The quantity of concrete to be paid for will be the volume of concrete in cubic yards including thickened edges[monolithic curb], where required, placed in the completed and accepted pavement. Concrete will be measured in place in the completed and accepted pavement only within the neat line dimensions shown in the plan and cross section. No deductions will be made for rounded or beveled edges or the space occupied by pavement reinforcement, dowel bars, [tie bars, ]or electrical conduits, nor for any void, or other structure extending into or through the pavement slab, measuring 3 cubic feet or less in volume. No other allowance for concrete will be made unless placed in specified locations in accordance with written instructions previously issued by the Contracting Officer. The quantity of other materials specified herein, and used in the construction of the work covered by this section, will not be measured for payment, but will be considered a subsidiary obligation of the Contractor, covered under the price per cubic yard for concrete. Joint sealing materials are covered in Section 32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS or Section 32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS. 1.1.2 Payments ************************************************************************** NOTE: Use the applicable paragraph from the two choices below and delete the other. ************************************************************************** 1.1.2.1 Unit Price The quantity of concrete measured as specified above will be paid for at the contract unit price when placed in completed and accepted pavements. Payment will be made at the contract price for cubic yard for the scheduled item, with necessary adjustments as specified below. Payment will constitute full compensation for furnishing all materials, equipment, plant and tools, and for all labor and other incidentals necessary to complete the concrete pavement, except for other items specified herein for separate URS FOR EQM SECTION 32 13 11 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 payment. 1.1.2.2 Lump Sum The quantity of concrete will be paid for and included in the lump-sum contract price. If less than 100 percent payment is due based on the pay factors stipulated below, a unit price of [_____]$210.00 per cubic yard will be used for purposes of calculating the payment reduction. 1.1.3 Payment of Lots When a lot of material fails to meet the specification requirements, that lot will be accepted at a reduced price or shall be removed and replaced. The lowest computed percent payment determined for any pavement characteristic (i.e., thickness, grade, and surface smoothness) discussed below shall be the actual percent payment for that lot. The actual percent payment will be applied to the unit price and the measured quantity of concrete in the lot to determine actual payment. Use results of strength tests to control concreting operations. Strength will be evaluated, but will not be considered for payment adjustment. Any pavement not meeting the required 'specified strength' shall be removed and replaced at no additional cost to the Government. 1.1.4 Payment Adjustment for Smoothness a. Straightedge Testing: Location and deviation from straightedge for all measurements shall be recorded. When more than 5.0 and less than or equal to 10.0 percent of all measurements made within a lot exceed the tolerance specified in paragraph "Surface Smoothness", after any reduction of high spots or removal and replacement, the computed percent payment based on surface smoothness will be 95 percent. When more than 10.0 percent and less than or equal to 15.0 percent of all measurements exceed the tolerance, the computed percent payment will be 90 percent. When more than 15.0 and less than or equal to 20.0 percent of all measurements exceed the tolerance, the computed percent payment will be 75 percent. When more than 20.0 percent of the measurements exceed the tolerance, the lot shall be removed and replaced at no additional cost to the Government. b. Profilograph Testing: Location and data from all profilograph measurements shall be recorded. When the Profile Index of a 0.1 mile segment of a lot exceeds the tolerance specified in paragraph "Surface Smoothness" by 1.0 inch per mile but less than 2.0 inches per mile, after any reduction of high spots or removal and replacement, the computed percent payment based on surface smoothness will be 95 percent. When the Profile Index exceeds the tolerance by 2.0 inches per mile but less than 3.0 inches per mile, the computed percent payment will be 90 percent. When the Profile Index exceeds the tolerance by 3.0 inches per mile but less than 4.0 inches per mile, the computed percent payment will be 75 percent. When the Profile Index exceeds the tolerance by 4.0 inches per mile or more, the lot shall be removed and replaced at no additional cost to the Government. ************************************************************************** NOTE: Delete item c, Aircraft Arresting Systems, if not present or impacted by paving operations. ************************************************************************** c. Aircraft Arresting Systems. URS FOR EQM The 200 feet of airfield pavement on both SECTION 32 13 11 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the approach and departure sides of the arresting system pendant is a critical area. Consider this area as a separate lot for payment adjustment for smoothness. Protruding objects and undulating surfaces are detrimental to successful tailhook engagements and are not allowable. No exceedance of the tolerances specified in paragraph: "Surface Smoothness" is acceptable. Remove and replace pavements exceeding the tolerances, unless otherwise directed by the Contracting Officer. 1.1.5 Payment Adjustment for Plan Grade When more than 5.0 and less than or equal to 10.0 percent of all measurements made within a lot are outside the specified tolerance, the computed percent payment for that lot will be 95 percent. When more than 10.0 percent but less than 50 percent are outside the specified tolerances, the computed percent payment for the lot will be 75 percent. In any areas where the deviation from grade exceeds the specified tolerances by 50 percent or more, the deficient area shall be removed and replaced at no additional cost to the Government. 1.1.6 Payment Adjustment for Thickness Using the Average Thickness of the lot, determine the computed percent payment for thickness by entering the following table: Computed Percent Payment for Thickness Deficiency in Thickness Determined by cores Inches Pavements Equal To or Over 8 Inches Thick Pavements Less Than 8 Inches Thick 0.00 to 0.24 100 100 0.25 to 0.49 75 65 0.50 to 0.74 50 0 0.75 or greater 0 0 Where 0 percent payment is indicated, remove the entire lot and replace at no additional cost to the Government. Where either of the two cores from a sublot show a thickness deficiency of 0.75 inch or greater,[ 0.50 inch for pavements 8 inches or less in thickness] drill two more cores in the sublot and compute the average thickness of the four cores. If this average shows a thickness deficiency of 0.75 inch or more [ 0.50 inch for pavements 8 inches or less in thickness] remove the entire sublot. 1.2 REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. URS FOR EQM SECTION 32 13 11 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) AASHTO M 182 (2005; R 2009) Standard Specification for Burlap Cloth Made from Jute or Kenaf and Cotton Mats AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI) ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete ACI 214R (2011) Evaluation of Strength Test Results of Concrete ACI 305R (2010) Guide to Hot Weather Concreting ACI 306R (2010) Guide to Cold Weather Concreting ASTM INTERNATIONAL (ASTM) ASTM A1064/A1064M (2013) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete ASTM A184/A184M (2006; E2011) Standard Specification for Fabricated Deformed Steel Bar Mats for Concrete Reinforcement ASTM A615/A615M (2014) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement ASTM A775/A775M (2007b; R2014) Standard Specification for Epoxy-Coated Steel Reinforcing Bars ASTM A996/A996M (2014) Standard Specification for Rail-Steel and Axle-Steel Deformed Bars for Concrete Reinforcement URS FOR EQM SECTION 32 13 11 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM C1017/C1017M (2013) Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete ASTM C1064/C1064M (2011) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete ASTM C1077 (2014) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation ASTM C117 (2013) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing ASTM C123/C123M (2012) Standard Test Method for Lightweight Particles in Aggregate ASTM C1260 (2007) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method) ASTM C131 (2006) Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine ASTM C136 (2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates ASTM C138/C138M (2013a) Standard Test Method for Density ("Unit Weight"), Yield, and Air Content (Gravimetric) of Concrete ASTM C142/C142M (2010) Standard Test Method for Clay Lumps and Friable Particles in Aggregates ASTM C143/C143M (2012) Standard Test Method for Slump of Hydraulic-Cement Concrete ASTM C150/C150M (2012) Standard Specification for Portland Cement ASTM C1567 (2013) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method) ASTM C1602/C1602M (2012) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete ASTM C1646/C1646M (2008a) Making and Curing Test Specimens for Evaluating Frost Resistance of Coarse Aggregate in Air-Entrained Concrete by Rapid Freezing and Thawing URS FOR EQM SECTION 32 13 11 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM C172/C172M (2014) Standard Practice for Sampling Freshly Mixed Concrete ASTM C174/C174M (2013) Standard Test Method for Measuring Thickness of Concrete Elements Using Drilled Concrete Cores ASTM C192/C192M (2013a) Standard Practice for Making and Curing Concrete Test Specimens in the Laboratory ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method ASTM C260/C260M (2010a) Standard Specification for Air-Entraining Admixtures for Concrete ASTM C294 (2012) Standard Descriptive Nomenclature for Constituents of Concrete Aggregates ASTM C295/C295M (2012) Petrographic Examination of Aggregates for Concrete ASTM C31/C31M (2012) Standard Practice for Making and Curing Concrete Test Specimens in the Field ASTM C33/C33M (2013) Standard Specification for Concrete Aggregates ASTM C494/C494M (2013) Standard Specification for Chemical Admixtures for Concrete ASTM C618 (2012a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete ASTM C666/C666M (2003; R 2008) Resistance of Concrete to Rapid Freezing and Thawing ASTM C78/C78M (2012; E 2013) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading) ASTM C88 (2013) Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate ASTM C881/C881M (2013) Standard Specification for Epoxy-Resin-Base Bonding Systems for Concrete ASTM C94/C94M (2014a) Standard Specification for Ready-Mixed Concrete ASTM C989/C989M (2013) Standard Specification for Slag Cement for Use in Concrete and Mortars URS FOR EQM SECTION 32 13 11 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM D1751 (2004; E 2013; R 2013) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types) ASTM D2995 (1999; R 2009) Determining Application Rate of Bituminous Distributors ASTM D3665 (2012) Random Sampling of Construction Materials ASTM D4791 (2010) Flat Particles, Elongated Particles, or Flat and Elongated Particles in Coarse Aggregate ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates ASTM E1274 (2003; R 2012) Standard Test Method for Measuring Pavement Roughness Using a Profilograph NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA) NRMCA QC 3 (2011) Quality Control Manual: Section 3, Plant Certifications Checklist: Certification of Ready Mixed Concrete Production Facilities STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION (CALTRANS) CTM 526 (2002) Operation of California Profilograph and Evaluation of Profiles U.S. ARMY CORPS OF ENGINEERS (USACE) COE CRD-C 130 (2001) Standard Recommended Practice for Estimating Scratch Hardness of Coarse Aggregate Particles COE CRD-C 300 (1990) Specifications for Membrane-Forming Compounds for Curing Concrete COE CRD-C 521 (1981) Standard Test Method for Frequency and Amplitude of Vibrators for Concrete COE CRD-C 55 (1992) Test Method for Within-Batch Uniformity of Freshly Mixed Concrete COE CRD-C 662 (2009) Determining the Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials, Lithium Nitrate Admixture and Aggregate (Accelerated Mortar-Bar Method) 1.3 SYSTEM DESCRIPTION This section is intended to stand alone for construction of concrete URS FOR EQM SECTION 32 13 11 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 pavement. However, where the construction covered herein interfaces with other sections, the construction at each interface shall conform to the requirements of both this section and the other section, including tolerances for both. 1.3.1 Surface Smoothness ************************************************************************** NOTE: Edit these paragraphs as appropriate to the project. If it is desired to restrict surface smoothness testing and evaluation to either straightedge method or profilograph method, retain the one and delete the other; otherwise, retain both as a Contractor's option. Require use of the profilograph method for airfield taxiways and runways. When the profilograph method is allowed, and there are areas with dimensions less than 60 m (200 feet) in any direction, retain the straightedge method for these short runs. ************************************************************************** Use the profilograph method for all longitudinal testing, except for paving lanes less than 200 feet in length. Use the straightedge method for transverse testing, for longitudinal testing where the length of each pavement lane is less than 200 feet,[ within 200 feet on both the approach and departure sides of an aircraft arresting gear,] and at the ends of the paving limits for the project. Where drawings show required deviations from a plane surface (crowns, drainage inlets, etc.) or existing rough or high PI pavement, finish the surface to meet the approval of the Contracting Officer. Detailed notes shall be kept of the results of the testing and a copy furnished to the Government after each day's testing. ************************************************************************** NOTE: Retain first bracketed statements for airfield projects and delete the second set. Retain second bracketed statements for roads and streets projects and delete first set. ************************************************************************** a. Straightedge Testing: The finished surfaces of the pavements shall have no abrupt change of 1/4 inch or more, and all pavements shall be within the limits specified when checked with an approved 12 foot straightedge. [Runways and taxiways shall have a variation from the specified straight edge not greater than 1/8 inch in the longitudinal direction and not greater than 1/4 inch in the transverse direction.[ Runway pavement within 200 feet on both the approach and departure sides of an aircraft arresting gear shall have a variation in the longitudinal direction from the specified straightedge not more than plus or minus 1/8 inch.] All other airfield areas shall have a variation from a straight edge not greater than 1/4 inch in either the longitudinal or transverse direction.] [Roads, streets, tank hardstands, vehicular parking areas, and open storage areas shall have a variation from the specified straight edge not greater than 6 mm 1/4 inch in either the longitudinal or transverse direction.] b. Profilograph Testing: The finished surfaces of the pavements shall have no abrupt change of 1/4 inch or more, and each 0.1 mile segment of each pavement lot shall have a Profile Index not greater than specified when tested with an approved California-type profilograph. [Runways URS FOR EQM SECTION 32 13 11 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 and taxiways shall have a Profile index not greater than 7 inches per mile in the longitudinal direction. Runway and taxiway transverse smoothness shall be measured with the straight edge method and the straight edge requirements shall apply. All other airfield areas shall have a Profile Index not greater than 9 inches per mile in the longitudinal direction.] [Roads, streets, tank hardstands, vehicular parking areas and open storage areas shall have a Profile index not greater than 9 inches per mile in the longitudinal direction.] c. Bumps ("Must Grind" Areas): Any bumps ("must grind" areas) shown on the profilograph trace which exceed 0.4 inch in height shall be reduced by diamond grinding in accordance with subparagraph "Diamond Grinding of PCC Surfaces" below until they do not exceed 0.3 inch when retested. Such grinding shall be tapered in all directions to provide smooth transitions to areas not requiring grinding. d. Testing Method: After the concrete has hardened sufficiently to permit walking thereon, but not later than 48 hours after placement, test the entire surface of the pavement in each lot in such a manner as to reveal all surface irregularities exceeding the tolerances specified above. If any pavement areas are ground, these areas shall be retested immediately after diamond grinding. The entire area of the pavement shall be tested in both a longitudinal and a transverse direction on parallel lines. The transverse lines shall be 15 feet or less apart, as directed. The longitudinal lines shall be at the centerline of each paving lane shown on the drawings, regardless of whether the Contractor is allowed to pave two lanes at a time, and at the 1/8th point in from each side of the lane. Other areas having obvious deviations shall also be tested. Longitudinal testing lines shall be continuous across all joints. Transverse testing lines for pilot lanes shall be carried to construction joint lines and for fill-in lanes shall be carried 24 inches across construction joints, and the readings in this area applied to the fill-in lane. Straightedge testing of the longitudinal edges of slipformed pilot lanes shall also be performed before paving fill-in lanes as specified below. (1) Straightedge Testing: The straightedge shall be held in contact with the surface and moved ahead one-half the length of the straightedge for each successive measurement. Determine the amount of surface irregularity by placing the freestanding (unleveled) straightedge on the pavement surface and measuring the maximum gap between the straightedge and the pavement surface. Measurements shall be determined along the entire length of the straight edge. (2) Profilograph Testing: Perform profilograph testing using approved California profilograph and procedures described in ASTM E1274. The equipment shall utilize electronic recording and automatic computerized reduction of data to indicate "must-grind" bumps and the Profile Index for each 0.1 mile segment of the pavement lot. Grade breaks on aprons[parking lots] shall be accommodated by breaking the profile segment into short sections and repositioning the blanking band on each section. The "blanking band" shall be 0.2 inches wide and the "bump template" shall span 1 inch with an offset of 0.4 inch. The profilograph testing of the last 30 feet of a paving lane in the longitudinal direction from each day's paving operation shall be counted on the following day's continuation lane. The profile index shall be computed for each pass of the profilograph (3 per lane) in each 0.1 mile segment. URS FOR EQM SECTION 32 13 11 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 The profile index for each segment shall be the average of the profile indices for each pass in each segment. Profilographs of unequal lengths shall be scaled and proportioned to an equivalent 0.1 mile as outlined in the CTM 526. A copy of the reduced tapes shall be furnished the Government at the end of each day's testing. 1.3.2 Edge Slump and Joint Face Deformation a. Edge Slump: When slip-form paving is used, not more than 15.0 percent of the total free edge of each pavement panel shall have an edge slump exceeding 1/4 inch and none of the free edge of the pavement lot shall have an edge slump exceeding 3/8 inch. (A pavement panel is defined as a lane width by the length between two adjacent transverse contraction joints. The total free edge of the pavement will be considered to be the cumulative total linear measurement of pavement panel edge originally constructed as non-adjacent to any existing pavement; i.e., 100 feet of pilot lane originally constructed as a separate lane, will have 200 feet of free edge; 100 feet of fill-in lane will have no free edge, etc.,). The area affected by the downward movement of the concrete along the pavement edge shall not exceed 18 inches back from the edge. b. Joint Face Deformation: In addition to the edge slump limits specified above, the vertical joint face shall have a surface within the maximum limits shown below: Offset from Straightedge Applied Logintudinally to Pavement Surface Offset from Straightedge Applied Longitudinally to Vertical Face Offset from Straightedge Applied Top to Bottom Against the Joint Face Abrupt Offset in Any Direction Offset of Joint Face from True Vertical 3/8 inch 1/8 inch 1 inch/12 inches Airfield Pavement 1/8 inch 1/4 inch All Other Pavement 1/4 inch c. All other items same as airfield pavement Slump Determination: Immediately after the concrete has hardened sufficiently to permit walking thereon, the pavement surface of each lot shall be tested by the Contractor. Testing shall be performed with a minimum 12 foot straightedge to reveal irregularities exceeding the edge slump tolerance specified above. The vertical edge slump shall be determined at each free edge of each slipformed paving lane constructed. The straightedge shall be placed transverse to the direction of paving and the end of the straightedge located at the edge of the paving lane. Measurements shall be made at 5 to 15 foot spacings, as directed, commencing at the header where paving was started. Initially measurements shall be made at 5 foot intervals in each lane. When no deficiencies are present, the Contracting Officer may approve an increase in the interval. When any deficiencies exist, the interval will be returned to 5 feet. In no case shall the interval exceed 15 feet. In addition to the transverse edge slump determination above, the Contractor, at the same time, shall check the longitudinal surface smoothness of the joint on a continuous line 1 inch back from URS FOR EQM SECTION 32 13 11 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the joint line using the 12 foot straightedge advanced one-half its length for each reading. Other tests of the exposed joint face shall be made to ensure that a uniform, true vertical joint face is attained. The measurements shall be made by the Contractor, shall be properly referenced in accordance with paving lane identification and stationing, and a report given to the Contracting Officer within 24 hours after measurement is made. The report shall also identify areas requiring replacement. d. 1.3.3 Excessive Edge Slump: When edge slump exceeding the limits specified above is encountered on either side of the paving lane, additional straightedge measurements shall be made, if required, to define the linear limits of the excessive slump. The concrete slabs having excessive edge slump or joint deformation shall be removed and replaced to the next transverse joint in conformance with paragraph: REPAIR, REMOVAL, REPLACEMENT OF NEWLY CONSTRUCTED SLABS. Use of slip-form paving equipment and procedures that fail to consistently provide edges within the specified tolerances on edge slump and joint face deformation shall be discontinued and the pavements shall be constructed by means of standard paving procedures using fixed forms. Plan Grade Within 5 days after paving of each lot, the finished surface of the pavement area shall be tested, by running lines of levels at intervals corresponding with every longitudinal and transverse joint to determine the elevation at each joint intersection. The results of this survey shall be recorded and a copy given to the Government at the completion of the survey of each lot. The finished surfaces of airfield runway, taxiway, and apron pavements shall vary not more than 1/2 inch above or below the plan grade line or elevation indicated. The surfaces of other pavements shall vary not more than 3/4 inch. The above deviations from the approved grade line and elevation will not be permitted in areas where closer conformance with the planned grade and elevation is required for the proper functioning of appurtenant structures. The finished surfaces of new abutting pavements shall coincide at their juncture. 1.3.4 Flexural Strength ************************************************************************** NOTE: Normally, concrete for airfield pavement should be proportioned and accepted on the basis of 90-day flexural strength. However, if, because of scheduling time limits, it is necessary to proportion on the basis of 28-day flexural strength, modify these subparagraphs as appropriate. If it is desired to use 28-day strength for design of airfield pavement, approval must be obtained through the TSMCX, MAJCOM pavement engineers, or NAVFAC. Make the same changes if this is concrete for road pavement proportioned for 28-day strength (no approval needed). The designer may choose the first Option "Cylinders/Beam" or the second Option "Beams" for strength testing. ************************************************************************** Submit certified copies of laboratory test reports and sources for cement, URS FOR EQM SECTION 32 13 11 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 supplementary cementitious materials (SCM), aggregates, admixtures, curing compound, epoxy, and proprietary patching materials proposed for use on this project. All aggregate tests shall have been performed no earlier than 6 months prior to contract award. Each lot of pavement will be evaluated for acceptance in accordance with the following procedures. a. Sampling and Testing: For acceptance, one composite sample of concrete from each sublot shall be obtained in accordance with ASTM C172/C172M from one batch or truckload.[ Test beams 6 x 6 inches shall be fabricated and cured in accordance with ASTM C31/C31M; and tested in accordance with ASTM C78/C78M.] b. Computations: Average the eight 14-day strength tests for the lot. The average strength shall be used in accordance with paragraph "Concrete Strength for Final Acceptance" in PART 2. 1.3.5 Thickness Each lot of pavement will be evaluated for acceptance and payment adjustment in accordance with the following procedure. Two cores, between 4 and 6 inches in diameter, shall be drilled from the pavement, per sublot (8 per lot). The Contractor is responsible for drilling the cores within 3 days after lot placement, filling the core holes with an approved non-shrink concrete, respraying the cored areas with curing compound, and for measuring the cores. Each core shall be inspected for voids, thickness of paste on the surface, and depth of reinforcement (if required). Provide the results with the thickness measurement data. Eight measurements of thickness shall be made around the circumference of each core and one in the center, in accordance with ASTM C174/C174M, using calibrated calipers for specimens longer than 10 inches. The pavement thickness from the 8 cores for the lot shall be averaged and shall be evaluated as described in paragraph: PAYMENT ADJUSTMENT FOR THICKNESS above. 1.3.6 Diamond Grinding of PCC Surfaces In areas not meeting the specified limits for surface smoothness and plan grade, high areas shall be reduced to attain the required smoothness and grade, except as depth is limited below. High areas shall be reduced by grinding the hardened concrete with an approved diamond grinding machine after the concrete is 14 days or more old. Grinding shall be accomplished by sawing with an industrial diamond abrasive which is impregnated in the saw blades. The saw blades shall be assembled in a cutting head mounted on a machine designed specifically for diamond grinding that will produce the required texture and smoothness level without damage to the concrete pavement or joint faces. The saw blades shall be 1/8-inch wide and there shall be a minimum of 55 to 60 blades per 12 inches of cutting head width depending on the hardness of the aggregate. Each machine shall be capable of cutting a path 3 to 4 ft 3 to 4 ft wide. Grinding equipment that causes ravels, aggregate fractures, spalls or disturbance to the joints will not be permitted. The area corrected by grinding the surface of the hardened concrete shall not exceed 10 percent of the total area of any sublot. The depth of diamond grinding shall not exceed 1/4 inch. All pavement areas requiring plan grade or surface smoothness corrections in excess of the limits specified above, shall be removed and replaced in conformance with paragraph REPAIR, REMOVAL, REPLACEMENT OF NEWLY CONSTRUCTED SLABS. [In pavement areas given a wire comb or tined texture, areas exceeding 25 square feet that have been corrected by diamond grinding shall be retextured by transverse grooving using an approved grooving machine of standard manufacture. The grooves shall be 1/4 inch deep by 1/4 URS FOR EQM SECTION 32 13 11 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 inch wide on 1-1/2 inch centers and shall be carried into, and tapered to zero depth within the non-corrected surface, or shall match any existing grooves in the adjacent pavement.]All areas in which diamond grinding has been performed will be subject to the thickness tolerances specified in paragraph: Thickness, above. 1.4 SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.] [information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29SUSTAINABILITY REQUIREMENTS. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-03 Product Data Equipment URS FOR EQM SECTION 32 13 11 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Proposed Techniques[; G][; G, [_____]] Dowels[; G][; G, [_____]] Dowel Bar Assemblies[; G][; G, [_____]] SD-05 Design Data Proportioning Studies; G, ED SD-06 Test Reports Sampling and Testing; G, ED SD-07 Certificates Contractor Quality Control Staff; G, ED Laboratory Accreditation; G, ED NRMCA Certificate of Conformance; G, ED Commercial Laboratory; G, ED 1.5 QUALITY ASSURANCE ************************************************************************** NOTE: Where they are available, specify only ACI certified personnel. Check the American Concrete Institute (ACI) website for local availability (www.concrete.org/Certification). ************************************************************************** 1.5.1 Contractor Quality Control Staff Submit American Concrete Institute certification for Contractor Quality Control staff. Qualifications and resumes for petrographer, surveyor, concrete batch plant operator, and profilograph operator. All Contractor Quality Control personnel assigned to concrete construction shall be American Concrete Institute (ACI) certified in the following grade (or shall have written evidence acceptable to the Contracting Officer's representative of having completed similar qualification programs): a. CQC personnel responsible for inspection of concrete paving operations: ACI Concrete Transportation Inspector. b. Lead Foreman or Journeyman of the Concrete Placing, Finishing, and Curing Crews: ACI Concrete Flatwork Technician/Finisher. c. Field Testing Technicians: ACI Concrete Field Testing Technician, Grade I. d. Laboratory Testing Technicians: ACI Concrete Strength Testing Technician and Laboratory Testing Technician, Grade I or II. 1.5.2 Other Staff Submit for approval, the qualifications and resumes for the following staff: a. Petrographer: Bachelor of Science degree in geology or petrography, trained in petrographic examination of concrete aggregate according to ASTM C294 and ASTM C295/C295M and trained in identification of the specific deleterious materials and tests identified in this specification. Resume shall detail the education, training and URS FOR EQM SECTION 32 13 11 Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 experience related to the project-specific test methods and deleterious materials and shall be submitted at least 20 days before petrographic and deleterious materials examination is to commence. b. Licensed Surveyor: All survey work shall be performed under the supervision of a Licensed Surveyor. c. Concrete Batch Plant Operator: National Ready Mix Concrete Association (NRMCA) Plant Manager certification at the Plant Operator level. d. Profilograph Operator: Certification by equipment manufacturer or a state Department of Transportation. 1.5.3 Laboratory Accreditation ************************************************************************** NOTE: The USACE validation letter requirement does not apply to the Navy. ************************************************************************** Laboratory and testing facilities shall be provided by and at the expense of the Contractor. Submit accreditation of the commercial laboratory by an independent evaluation authority, indicating conformance to ASTM C1077, including all applicable test procedures. The laboratories performing the tests shall be accredited in accordance with ASTM C1077, including ASTM C78/C78M and ASTM C1260. The accreditation shall be current and shall include the required and optional test methods, as specified throughout this Section. Onsite temperature-controlled concrete curing facilities shall be provided. a. Aggregate Testing and Mix Proportioning: Aggregate testing and mixture proportioning studies shall be performed by a commercial laboratory. b. Acceptance Testing: Furnish all materials, labor, and facilities required for molding, curing, testing, and protecting test specimens at the site and in the laboratory. Steel molds shall be used for molding the beam specimens. Furnish and maintain boxes or other facilities suitable for storing and curing the specimens at the site while in the mold within the temperature range stipulated by ASTM C31/C31M. Flexural loading equipment shall be in accordance with ASTM C78/C78M. c. Contractor Quality Control: All sampling and testing shall be performed by an approved, onsite, independent, commercial laboratory, or for cementitious materials and admixtures, the manufacturer's laboratory. Submit USACE validation letter for commercial laboratory. d. Laboratory Inspection: The Government will inspect the laboratory equipment and test procedures prior to the start of concreting operations for conformance to ASTM C1077. The laboratory shall maintain this certification for the duration of the project. 1.5.4 Preconstruction Testing of Materials ************************************************************************** NOTE: Designer must edit this paragraph and following subparagraphs as appropriate. For Design Build Contracts the testing shall be performed by the Contractor utilizing an approved petrographer and commercial testing laboratory. Delete any URS FOR EQM SECTION 32 13 11 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 subparagraphs which are not applicable. Fill in blanks as appropriate. ************************************************************************** All sampling and testing shall be performed by, and at the expense of, the Contractor. Use an approved commercial laboratory or, for cementitious materials and chemical admixtures, a laboratory maintained by the manufacturer of the material. No material shall be used until notice of acceptance has been given. The Contractor will not be entitled to any additional payment or extension of time due to failure of any material to meet project requirements, or for any additional sampling or testing required. Additional tests may be performed by the Government at the discretion of the Contracting Officer; such Government testing will not relieve the Contractor of any testing responsibilities. 1.5.4.1 Aggregates Aggregates shall be sampled in the presence of a Government Representative. Samples shall be obtained in accordance with ASTM D75/D75M and shall be representative of the materials to be used for the project. Test results shall be submitted 7 days before commencing mixture proportioning studies. 1.5.4.2 Chemical Admixtures, Curing Compounds and Epoxies At least 30 days before the material is used, submit certified copies of test results for the specific lots or batches to be used on the project. Test results shall be not more than 6 months old prior to use in the work. Chemical admixtures that have been in storage at the project site for longer than 6 months or that have been subjected to freezing will be retested at the expense of the Contractor and will be rejected if test results are not satisfactory. 1.5.4.3 Cementitious Materials Cement[, ground granulated blast furnace (GGBF) slag,] [and pozzolan] will be accepted on the basis of manufacturer's certification of compliance, accompanied by mill test reports showing that the material in each shipment meets the requirements of the specification under which it is furnished. Mill test reports shall be no more than 1 month old, prior to use in the work. No cementitious material shall be used until notice of acceptance has been given by the Contracting Officer. Cementitious material may be subjected to testing by the Government from samples obtained at the mill, at transfer points, or at the project site. If tests prove that a cementitious material that has been delivered is unsatisfactory, it shall be promptly removed from the site of the work. Cementitious material that has not been used within 6 months after testing shall be retested at the Contractor's expense and shall be rejected if test results are not satisfactory. 1.5.5 Testing During Construction During construction, the Contractor is responsible for sampling and testing aggregates, cementitious materials, and concrete as specified herein. The Government will sample and test concrete and ingredient materials as considered appropriate. Provide facilities and labor as may be necessary for procurement of representative test samples. Testing by the Government will in no way relieve the Contractor of the specified testing requirements. URS FOR EQM SECTION 32 13 11 Page 17 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.5.6 TYMX989345A FA3002-09-D-0002 TG02 Test Section Up to 10 days, but not more than 60 days, prior to construction of the concrete pavement, construct a test section [near the job site, but not as part of the production pavement area.] [as part of the production paving area at an outer edge as indicated on the drawings]. Use the test section to develop and demonstrate to the satisfaction of the Contracting Officer the proposed techniques of mixing, hauling, placing, consolidating, finishing, curing, initial saw cutting, start-up procedures, testing methods, plant operations, and the preparation of the construction joints. Variations in mixture proportions, other than water, shall be made if directed. Vary the water content, as necessary, to arrive at the appropriate content. The mixing plant shall be operated and calibrated prior to start of placing the test section. Use the same equipment, materials, and construction techniques on the test section as will be used in all subsequent work. Base course preparation, concrete production, placing, consolidating, curing, construction of joints, and all testing shall be in accordance with applicable provisions of this specification. Three days after completion of the test section, provide eight cores at least 6 inch diameter by full depth cut from points selected in the test section by the Government. The cores will be evaluated for homogeneity, consolidation and segregation. Construct the test section meeting all specification requirements and being acceptable to the Contracting Officer in all aspects, including surface texture. Failure to construct an acceptable test section will necessitate construction of additional test sections at no additional cost to the Government. Test sections allowed to be constructed as part of the production paving which do not meet specification requirements shall be removed at the Contractor's expense. If the Contractor proposes to use slipform paving and is unable to construct an acceptable test section, the slipform paving equipment shall be removed from the job and the construction completed using stationary side forms and equipment compatible with them. Production paving shall not commence until the results on aggregates and concrete, including evaluation of the cores, and all pavement measurements for edge slump, joint face deformation, actual plan grade, surface smoothness and thickness have been submitted and approved by the Contracting Officer. Pavement accepted as a production lot will be evaluated and paid in accordance with Paragraph: ACCEPTABILITY OF WORK below. 1.5.6.1 Pilot Lane The test section shall consist of one paving lane at least 400 feet long and shall be constructed to the same thickness as the thickest portion of pavement shown on the Drawings. The lane width shall be the same as that required for use in the project. The test section shall contain at least one transverse construction joint. If [keyed or ]doweled longitudinal construction joints are required in any of the production pavements, they shall be installed full length along one side of the test strip throughout the test section. [If both keys and dowels are required, each shall be installed in half of the test section.] Two separate days shall be used for construction of the test section. 1.5.6.2 Fill-In Lane The first 400 feet of the initial production fill-in lane shall be considered a fill-in lane test section for purposes of testing and evaluation. All requirements for the test section are applicable, as appropriate. Obtain cores from the fill-lane lane side of the longitudinal construction joint with the pilot lane. The cores will be evaluated for URS FOR EQM SECTION 32 13 11 Page 18 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 homogeneity, consolidation, and segregation. 1.5.7 Acceptability of Work The materials and the pavement itself will be accepted on the basis of tests made by the Contractor. The Government may make check tests to validate the results of the Contractor's testing. If the results of the Contractor tests vary by less than 2.0 percent of the Government's test results, the results of the Contractor's tests will be used. If the results of the Government and Contractor tests vary by 2.0 percent, but less than 4.0 percent, the average of the two will be considered the value to be used. If these vary by 4.0 percent or more, each sampling and testing procedure shall be carefully evaluated and both the Government and the Contractor shall take another series of tests on duplicate samples of material. If these vary by 4.0 percent or more, the results of the tests made by the Government shall be used and the Government will continue check testing of this item on a continuous basis until the two sets of tests agree within less than 4.0 percent on a regular basis. Testing performed by the Government will in no way at any time relieve the Contractor from the specified testing requirements. 1.5.8 1.5.8.1 Acceptance Requirements Pavement Lots ************************************************************************** NOTE: The lot size can be specified on the basis of time or volume of production. Normally, it is most practical for construction oversight if a lot is made equal to one shift, but not over 10 hours. If the lot size is based on the amount of production, it should be selected to be approximately equal to the amount of concrete pavement produced in one shift (one day) of operation. The lot size should never exceed 750 cubic meters (1000 cu. yd.) of concrete pavement. When the total job does not exceed 750 cubic meters (1000 cu. yd.), the lot size becomes the total job. The following paragraphs will be edited accordingly. Do not change terminology (computed percent payment, actual percent payment, etc.). ************************************************************************** A lot will be that quantity of construction that will be evaluated for acceptance with specification requirements. A lot will be equal to one shift of production not to exceed 1000 cubic yards. In order to evaluate thickness, each lot will be divided into four equal sublots. Grade determinations will be made on the lot as a whole. Surface smoothness determinations will be made on every 0.1 mile segment in each lot. Location of all samples shall be selected on a random basis in accordance with ASTM D3665. When operational conditions cause a lot to be terminated before the specified four sublots have been completed, the following procedure shall be used to adjust the lot size and number of tests for the lot. Where three sublots have been completed, they shall constitute a lot. Where one or two sublots have been completed, they shall be incorporated into the next lot (except for the last lot), and the total number of sublots shall be used and acceptance criteria adjusted accordingly. URS FOR EQM SECTION 32 13 11 Page 19 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.5.8.2 TYMX989345A FA3002-09-D-0002 TG02 Evaluation Provide all sampling and testing required for acceptance and payment adjustment at the Contractor's expense. Individuals performing sampling, testing and inspection duties shall meet the required Qualifications. The Contracting Officer reserves the right to direct additional samples and tests for any area which appears to deviate from the specification requirements. Testing in these areas will be in addition to the sublot or lot testing, and the requirements for these areas will be the same as those for a sublot or lot. Provide facilities for and, where directed, personnel to assist in obtaining samples for any Government testing. 1.6 1.6.1 DELIVERY, STORAGE, AND HANDLING Bulk Cementitious Materials Furnish all cementitious material in bulk. The temperature of the cementitious material, as delivered to storage at the site, shall not exceed 150 degrees F. Sufficient cementitious materials shall be in storage to sustain continuous operation of the concrete mixing plant while the pavement is being placed. Provide separate facilities to prevent any intermixing during unloading, transporting, storing, and handling of each type of cementitious material. 1.6.2 Aggregate Materials Store aggregate at the site of the batching and mixing plant avoiding breakage, segregation, intermixing or contamination by foreign materials. Each size of aggregate from each source shall be stored separately in free-draining stockpiles. Aggregate stored on ground shall have a minimum 24 inch thick sacrificial layer left undisturbed. Fine aggregate and the smallest size coarse aggregate shall remain in free-draining storage for at least 24 hours immediately prior to use. Sufficient aggregate shall be maintained at the site at all times to permit continuous uninterrupted operation of the mixing plant at the time concrete pavement is being placed. Tracked equipment shall not be allowed on coarse aggregate stockpiles. 1.6.3 Other Materials Store reinforcing bars and accessories above the ground on supports. materials shall be stored avoiding contamination and deterioration. PART 2 All PRODUCTS ************************************************************************** NOTE: Delete any reference to any products which are not to be used on the project. Coordinate all product requirements with the appropriate agency's Pavements or Materials Engineer. ************************************************************************** 2.1 CEMENTITIOUS MATERIALS ************************************************************************** NOTE: Edit these paragraphs as appropriate for the particular project. Guidance for use of cementitious materials should be sought from the Pavement Materials engineer or from the TSMCX, Air URS FOR EQM SECTION 32 13 11 Page 20 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Force MAJCOM paving engineers, or NAVFAC, especially for areas subject to alkali-aggregate reactivity, or sulfate attack. When sulfate bearing soil or water is encountered, specify Type II cement for moderate sulfate concentration and Type V cement for high concentration and consider requiring use of fly ash or GGBF slag for partial replacement. Do not specify Type I or III cement. See UFC 3-250-04 for guidance. Specify limit on false set if it is a problem in the area. Type III cement should not be specified unless accelerated paving is involved and then only after laboratory mixture proportioning studies and tests during the design stage of the project. ************************************************************************** Cementitious materials shall be portland cement,[blended cement] or only portland cement in combination with supplementary cementitious materials (SCM), and shall conform to appropriate specifications listed below. New submittals are required when the cementitious materials sources or types change. 2.1.1 Portland Cement Provide portland cement conforming to ASTM C150/C150M, Type [I] [II] [V], low alkali [including false set requirements]. [Type III cement shall be used only in concrete in the following locations [_____].] Blended Cements Blended cement shall conform to ASTM C595/C595M, Type IP or IS, including the optional requirement for mortar expansion [and sulfate soundness]. The pozzolan added to the Type IP blend shall be ASTM C618 Class F or Class N and shall be interground with the cement clinker. The manufacturer shall state in writing that the amount of pozzolan in the finished cement will not vary more than plus or minus 5 mass percent of the finished cement from lot to lot or within a lot. The percentage and type of mineral admixture used in the blend shall not change from that submitted for the aggregate evaluation and mixture proportioning. The requirements of Table 2 in paragraph SUPPLEMENTARY CEMENTITIOUS MATERIALS (SCM) CONTENT do not apply to the SCM content of blended cement. 2.1.2 2.1.2.1 Pozzolan Fly Ash ************************************************************************** NOTE: Class C fly ash is not permitted for paving concrete. Use loss on ignition not exceeding 3 percent for frost areas to reduce carbon interference with air entraining admixture. ************************************************************************** Fly ash shall conform to ASTM C618, Class F, including the optional URS FOR EQM SECTION 32 13 11 Page 21 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 requirements for uniformity and effectiveness in controlling Alkali-Silica reaction and shall have a loss on ignition not exceeding [3] [6] percent. Class F fly ash for use in mitigating Alkali-Silica Reactivity shall have a total equivalent alkali content less than 3 percent. 2.1.2.2 Raw or Calcined Natural Pozzolan Natural pozzolan shall be raw or calcined and conform to ASTM C618, Class N, including the optional requirements for uniformity and effectiveness in controlling Alkali-Silica reaction and shall have a loss on ignition not exceeding [3] [6] percent. Class N pozzolan for use in mitigating Alkali-Silica Reactivity shall have a total equivalent alkali content less than 3 percent. 2.1.2.3 Ultra Fine Fly Ash and Ultra Fine Pozzolan Ultra Fine Fly Ash (UFFA) and Ultra Fine Pozzolan (UFP) shall conform to ASTM C618, Class F or N, and the following additional requirements: a. The strength activity index at 28 days of age shall be at least 95 percent of the control specimens. b. The average particle size shall not exceed 6 microns. 2.1.3 Ground Granulated Blast-Furnace (GGBF) Slag Ground Granulated Blast-Furnace Slag shall conform to ASTM C989/C989M, [Grade 100 or] Grade 120. [2.1.4 Silica Fume ************************************************************************** NOTE: Silica Fume shall only be used for OCONUS projects where Class F fly ash and GGBF slag are not available, and when approved by the TSMCX, Air Force major command (MAJCOM) pavement engineers, or NAVFAC. Delete this paragraph here and where encountered throughout the remainder of this section. ************************************************************************** Silica fume shall conform to ASTM C1240, including the optional limits on reactivity with cement alkalis. Silica fume may be furnished as a dry, densified material or as a slurry. Provide at the Contractor's expense the services of a manufacturer's technical representative, experienced in mixing, proportioning, placement procedures, and curing of concrete containing silica fume. This representative must be present on the project prior to and during at least the first 4 days of concrete production and placement using silica fume. ]2.1.4 Supplementary Cementitious Materials (SCM) Content ************************************************************************** NOTE: Use first tailoring option for Navy projects. Use second tailoring option for Army/Air Force projects. ************************************************************************** [The Contractor may elect to use one of the SCMs listed below, unless the SCM is required to mitigate ASR. The use of SCMs is encouraged in URS FOR EQM SECTION 32 13 11 Page 22 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 accordance with Section 01 62 35, Recycled/Recovered Materials.] TABLE 2 SUPPLEMENTARY CEMENTITIOUS MATERIALS CONTENT Supplementary Cementitious Material Minimum Content Maximum Content (percent) (percent) Class N Pozzolan and Class F Fly Ash SiO2 + Al2O3 + Fe2O3 > 70 percent 25 35 SiO2 + A12O3 + Fe2O3 > 80 percent 20 35 SiO2 + A12O3 + Fe2O3 > 90 percent 15 35 UFFA and UFP 7 16 GGBF Slag 40 50 2.2 AGGREGATES ************************************************************************** NOTE: The designer will ensure that aggregates available in the area meet the requirements of these specifications. Otherwise, the specification requirements must be modified to allow use of available material. This concern must be discussed and validated in the Design Analysis before preparation of the project specifications. During the design stage, the designer must assure that all aggregate materials in the area which meet the project specifications will also produce concrete of the specified flexural strength with a reasonable cementitious material content. Otherwise, specifications and design assumptions must be modified. It is imperative that all aggregate be investigated for problems related to alkali-aggregate reactions. ************************************************************************** 2.2.1 2.2.1.1 Aggregate Sources Durability ************************************************************************** NOTE: Use first Tailoring Option for Army and Air Force; second option is for Navy projects only. ************************************************************************** [Aggregate shall have a satisfactory service record in freezing and thawing of at least 5 years successful service in three concrete paving projects. The service record shall include a condition survey of the existing concrete and a review of the concrete-making materials, including coarse and fine aggregates, cement, and mineral admixtures. This review should consider the previous aggregate source and test results, cement mill certificate data, mineral admixture chemical and physical composition, and the mix design (cement factor and water-cementitious material ratio). Aggregate not having a satisfactory demonstrable service record shall have URS FOR EQM SECTION 32 13 11 Page 23 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 a durability factor of 50 or more when subjected to freezing and thawing of specimens prepared in accordance with ASTM C1646/C1646M and tested in accordance with ASTM C666/C666M, Procedure A.] 2.2.1.2 Alkali-Silica Reactivity Fine and coarse aggregates to be used in all concrete shall be evaluated and tested for alkali-aggregate reactivity. Both coarse aggregate size groups shall be tested. a. The fine and coarse aggregates shall be evaluated separately, using ASTM C1260. Test results of the individual aggregates shall have a measured expansion equal to or less than 0.08 percent after 28 days of immersion in a 1N NaOH solution. Should the test data indicate an expansion of greater than 0.08 percent, the aggregate(s) shall be rejected or additional testing shall be performed as follows: utilize the Contractor's proposed low alkali portland cement, blended cement, and/or SCM, and/or Lithium Nitrate in combination with each individual aggregate. If only SCMs are being evaluated, the testing shall be in accordance with ASTM C1567. If Lithium Nitrate is being evaluated, with or without SCMs, the testing shall be in accordance with COE CRD-C 662. Determine the quantity that will meet all the requirements of these specifications and that will lower the expansion equal to or less than 0.08 percent after 28 days of immersion in a 1N NaOH solution. Mixture proportioning shall be based on the highest percentage of SCM required to mitigate ASR-reactivity b. If any of the above options does not lower the expansion to less than 0.08 percent after 28 days of immersion in a 1N NaOH solution, reject the aggregate(s) and submit new aggregate sources for retesting. Submit the results of testing to the Contracting Officer for evaluation and acceptance. 2.2.1.3 Combined Aggregate Gradation In addition to the grading requirements specified for coarse aggregate and for fine aggregate, the combined aggregate grading shall meet the following requirements: a. The materials selected and the proportions used shall be such that when the Coarseness Factor (CF) and the Workability Factor (WF) are plotted on a diagram as described in d. below, the point thus determined shall fall within the parallelogram described therein. b. The Coarseness Factor (CF) shall be determined from the following equation: CF = (cumulative percent retained on the 3/8 in. sieve)(100)/(cumulative percent retained on the No. 8 sieve) c. The Workability Factor WF is defined as the percent passing the No. 8 sieve based on the combined gradation. However, WF shall be adjusted, upwards only, by 2.5 percentage points for each 94 pounds of cementitious material per cubic yard greater than 564 pounds per cubic yard. d. A diagram shall be plotted using a rectangular scale with WF on the Y-axis with units from 20 (bottom) to 45 (top), and with CF on the X-axis with units from 80 (left side) to 30 (right side). On this URS FOR EQM SECTION 32 13 11 Page 24 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 diagram a parallelogram shall be plotted with corners at the following coordinates (CF-75, WF-28), (CF-75, WF-40), (CF-45, WF-32.5), and (CF-45, WF-44.5). If the point determined by the intersection of the computed CF and WF does not fall within the above parallelogram, the grading of each size of aggregate used and the proportions selected shall be changed as necessary.) 2.2.2 2.2.2.1 Coarse Aggregate Material Composition ************************************************************************** NOTE: Crushing gravel tends to improve quality and bond characteristics and generally results in higher flexural strength of concrete. When mixture proportioning studies or local experience indicates that low flexural strength concrete will be produced with an uncrushed gravel, the possibility of producing higher strength concrete by crushing the gravel should be investigated. When desirable to limit coarse aggregate to crushed materials, modify this paragraph appropriately. Do not, under any conditions, permit use of steel furnace slag for any aggregate. (It is markedly different from iron blast furnace slag.) In power check pads, the high temperatures from jet blast can cause distress in aggregates in the concrete. Include bracketed item if power check pads are to be constructed. If no service record is available, lab study of available aggregates should be made. Only basalt is permitted on Navy projects. Special attention should be given to aggregates to be used for compass calibration pads. Aggregates with magnetic properties, such as, but not limited to, magnetite in granites, high-iron minerals in traprock, pyrite in limestone, and free iron or iron oxide in slag aggregate should not be used. When the paving of compass calibration pads is required, add the bracketed item concerning compass pads as additional requirements for coarse and fine aggregates. Retain the bracketed requirement for washing coarse aggregate if aggregates in the area require it. Add the requirement to use a log washer or other specific equipment if experience in the area shows the need. Delete if not needed. It is permissible to list certain aggregate sources that do not require washing, if that is appropriate. The designer must make the decision during preparation of specifications; do not make the Resident Engineer decide after award if aggregates need to be washed. ************************************************************************** Coarse aggregate shall consist of crushed or uncrushed gravel, crushed stone, [crushed adequately seasoned air-cooled iron blast-furnace slag; URS FOR EQM SECTION 32 13 11 Page 25 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 steel furnace slag will not be permitted]or a combination thereof. [Aggregate used for paving compass calibration hardstands shall be free of materials having undesirable magnetic properties, including magnetite in granite, high-iron minerals in traprock, and pyrite in limestone.] [Coarse aggregate used for paving power check pads shall be limestone, dolomite, basalt or other approved low-silica content aggregate which will not cause thermal distress from jet blast.]Aggregates, as delivered to the mixers, shall consist of clean, hard, uncoated particles meeting the requirements of ASTM C33/C33M except as specified herein. [Coarse aggregate shall be washed. Washing shall be sufficient to remove dust and other coatings.] [Coarse aggregate shall be cleaned by processing with an approved log washer.] [Iron blast-furnace slag conforming to the grading to be used in the concrete shall have a compact density of not less than 70 lb/cu. ft. determined in accordance with ASTM C29/C29M]Coarse aggregate shall not show more than 40 percent loss when subjected to the Los Angeles abrasion test in accordance with ASTM C131. The sodium sulfate soundness loss shall not exceed 12 percent, or the magnesium sulfate soundness loss shall not exceed 18 percent after five cycles when tested in accordance with ASTM C88. 2.2.2.2 Particle Shape Characteristics Particles of the coarse aggregate shall be generally spherical or cubical in shape. The quantity of flat and elongated particles in any size group coarser than the3/8 inch sieve shall not exceed 20 percent by weight as determined by the Flat Particle Test and the Elongated Particle Test of ASTM D4791. A flat particle is defined as one having a ratio of width to thickness greater than 3; an elongated particle is one having a ratio of length to width greater than 3. 2.2.2.3 Size and Grading ************************************************************************** NOTE: Fill in the blank according to the size aggregate available in the project area, and the type of paving. For thin bonded overlays, limit the nominal maximum aggregate size to less than one-third of the uniform overlay thickness (not including leveling portion). Use nominal maximum aggregate size of 37.5 mm (1-1/2 inch) whenever possible. A 25 mm (1-inch) nominal maximum aggregate size may be used to avoid durability problems associated with some larger size aggregate. ************************************************************************** The nominal maximum size of the coarse aggregate shall be [1.5] [_____] inch. Grade and furnish the individual aggregates in two size groups meeting the individual grading requirements of ASTM C33/C33M, Size No. 4 (1.5 to 0.75 inches) and Size No. 67 (0.75 inches to No. 4) to meet the coarseness and workability factor criteria for the contractor-proposed combined gradation. A third aggregate size group may be required to meet the above mentioned coarseness and workability criteria of paragraph COMBINED AGGREGATE GRADATION. 2.2.2.4 Deleterious Materials - Airfield Pavements ************************************************************************** NOTE: Include these deleterious material requirements for airfield paving projects only, otherwise, delete. In Table 5 select columns URS FOR EQM SECTION 32 13 11 Page 26 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 showing appropriate percentage by weight in accordance with the following. Delete the inapplicable column in the table and the heading of the column used. Weather Severity Air Freezing Index Coldest Year in 30 (a) Moderate 500 or less Moderate (b) 501 or more Severe 501 or more Average Precipitation for any Single Month During the Freezing Period Any Amount Less than 25 mm (1 inch) 25 mm (1 inch) or more (a) Calculated as described in UFC 3-130-01. See ASTM C33/C33M for simplified map of CONUS weather severity. (b) In poorly drained areas, the weather should be considered severe even though the other criteria indicate a rating of moderate. (c) For Navy projects, select "Negligible Weather" column or "Moderate Weather" column of Table 5. Delete the inapplicable columns and delete paragraphs a through h. ************************************************************************** The amount of deleterious material in each size group of coarse aggregate shall not exceed the limits shown in Table 5 below, determined in accordance with the test methods shown. TABLE 5 LIMITS OF DELETERIOUS MATERIALS IN COARSE AGGREGATE FOR AIRFIELD PAVEMENTS Percentage by Mass Materials (h) Severe Weather 0.2 Moderate Weather .02 Negligible Weather 1.0 0.1 0.2 -- Material finer than No. 200 sieve (b) (ASTM C117) Lightweight particles (c) (ASTM C123/C123M) Clay ironstone (d) (ASTM C295/C295M) Chert and cherty stone (less than 2.40 Sp. Gr.) (e) (ASTM C123/C123M and ASTM C295/C295M) 0.5 0.5 1.0 0.2 0.2 1.0 0.1 0.5 -- 0.1 0.5 -- Claystone, mudstone, and siltstone (f) (ASTM C295/C295M) 0.1 0.1 -- Clay lumps and friable particles (ASTM C142/C142M) Shale (a) (ASTM C295/C295M) URS FOR EQM SECTION 32 13 11 Page 27 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 TABLE 5 LIMITS OF DELETERIOUS MATERIALS IN COARSE AGGREGATE FOR AIRFIELD PAVEMENTS Percentage by Mass Materials (h) Severe Weather 0.2 Moderate Weather 0.2 Negligible Weather -- Shaly and argillaceous limestone (g) (ASTM C295/C295M) Other soft particles 1.0 1.0 1.0 (COE CRD-C 130) Total of all deleterious 1.0 2.0 3.0 substances exclusive of material finer than No. 200 sieve (a) Shale is defined as a fine-grained, thinly laminated or fissile sedimentary rock. It is commonly composed of clay or silt or both. It has been indurated by compaction or by cementation, but not so much as to have become slate. (b) Limit for material finer than No. 200 sieve will be increased to 1.5 percent for crushed aggregates if the fine material consists of crusher dust that is essentially free from clay or shale. (c) The separation medium shall have a density of Sp. Gr. of 2.0. This limit does not apply to coarse aggregate manufactured from blast-furnace slag unless contamination is evident. (d) Clay ironstone is defined as an impure variety of iron carbonate, iron oxide, hydrous iron oxide, or combinations thereof, commonly mixed with clay, silt, or sand. It commonly occurs as dull, earthy particles, homogeneous concretionary masses, or hard-shell particles with soft interiors. Other names commonly used for clay ironstone are "chocolate bars" and limonite concretions. (e) Chert is defined as a rock composed of quartz, chalcedony or opal, or any mixture of these forms of silica. It is variable in color. The texture is so fine that the individual mineral grains are too small to be distinguished by the unaided eye. Its hardness is such that it scratches glass but is not scratched by a knife blade. It may contain impurities such as clay, carbonates, iron oxides, and other minerals. Cherty stone is defined as any type of rock (generally limestone) that contains chert as lenses and nodules, or irregular masses partially or completely replacing the original stone. (f) Claystone, mudstone, or siltstone, is defined as a massive fine-grained sedimentary rock that consists predominantly of indurated clay or silt without laminations or fissility. It may be indurated either by compaction or by cementation. (g) Shaly limestone is defined as limestone in which shale occurs as one or more thin beds or laminae. These laminae may be regular or very irregular and may be spaced from a few inches down to minute fractions of an inch. Argillaceous limestone is defined as a limestone in which clay minerals occur disseminated in the stone in the amount of 10 to 50 percent by weight of the rock; when these make up from 50 to 90 percent, the rock is known as calcareous (or dolomitic) shale (or claystone, mudstone, or siltstone). URS FOR EQM SECTION 32 13 11 Page 28 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 TABLE 5 LIMITS OF DELETERIOUS MATERIALS IN COARSE AGGREGATE FOR AIRFIELD PAVEMENTS Percentage by Mass Materials (h) Severe Moderate Negligible Weather Weather Weather (h) Perform testing in accordance with the referenced test methods, except that the minimum sample size shall be as specified below. 2.2.2.5 Testing Sequence/Deleterious Materials in Coarse Aggregate Airfields Only ************************************************************************** NOTE: Contact TSMCX for guidance on available petrographers in USACE. Use Tailoring Option to select between Navy and Army/Air Force testing protocols. ************************************************************************** The Contractor will not be entitled to any extension of time or additional payment due to any delays caused by the testing, evaluation, or personnel requirements. [The size of the coarse aggregate sample shall be at least 200 pounds for the 3/4 inch and larger maximum size and 25 pounds for the No. 4 to 3/4 inch coarse aggregate and 10 pounds for the fine aggregate. Provide facilities for the ready procurement of representative test samples. The testing procedure on each sample of coarse aggregate for compliance with limits on deleterious materials shall be as follows:] [ Step 1: Wash each full sample of coarse aggregate for material finer than the No. 200 sieve. Discard material finer than the No. 200 sieve. Step 2: Test remaining full sample for clay lumps and friable particles and remove. Step 3: Test remaining full sample for lightweight particles (Sp. Gr. 2.0) and remove. Step 4. Test remaining full sample for chert and/or cherty stone with SSD density of less than 2.40 specific gravity. Remove lightweight chert and/or cherty stone. Restore other materials less than 2.40 to the sample. Step 5: Test remaining sample for clay-ironstone, shale, claystone, mudstone, siltstone, shaly and/or argillaceous limestone, and remove. Step 6: Test approximately one-fifth of remaining full sample for other soft particles.] 2.2.2.6 Deleterious Material - Road Pavements ************************************************************************** NOTE: Use this paragraph only for heavy-duty pavements, roads, streets, and parking lots for vehicular and tracked traffic. Otherwise, delete. ************************************************************************** URS FOR EQM SECTION 32 13 11 Page 29 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 The amount of deleterious material in each size group of coarse aggregate shall not exceed the limits in the following table when tested as indicated. LIMITS OF DELETERIOUS MATERIALS IN COARSE AGGREGATE FOR ROAD PAVEMENTS Percentage by Mass Clay lumps and friable particles (ASTM C142/C142M) 2.0 Material finer than No. 200 sieve (ASTM C117) 1.0 Lightweight particles (ASTM C123/C123M) 1.0 Other soft particles (COE CRD-C 130) 2.0 Total of all deleterious substances, exclusive of material finer than No. 200 sieve 5.0 The limit for material finer than the No. 200 sieve will be increased to 1.5 percent for crushed aggregates consisting of crusher dust that is essentially free from clay or shale. The separation medium for lightweight particles shall have a density of 2.0 specific gravity. This limit does not apply to coarse aggregate manufactured from blast-furnace slag unless contamination is evident. 2.2.3 2.2.3.1 Fine Aggregate Composition Fine aggregate shall consist of natural sand, manufactured sand, or a combination of the two, and shall be composed of clean, hard, durable particles meeting the requirements of ASTM C33/C33M. [Aggregate used for paving compass calibration hardstands shall be free of materials having undesirable magnetic properties, including magnetite in granite, high-iron minerals in traprock, and pyrite in limestone.]Each type of fine aggregate shall be stockpiled and batched separately. Particles of the fine aggregate shall be generally spherical or cubical in shape. 2.2.3.2 Grading Grading of the fine aggregate, as delivered to the mixer, shall conform to the requirements of ASTM C33/C33M and shall have a fineness modulus of not less than 2.50 nor more than 3.40. 2.2.3.3 Deleterious Material [Sample size for fine aggregate proposed for use in airfield paving shall be 10 pounds. ]The amount of deleterious material in the fine aggregate shall not exceed the following limits by mass: Material Percentage by Mass Clay lumps and friable particles ASTM C142/C142M 1.0 Material finer than No. 200 sieve ASTM C117 3.0 URS FOR EQM SECTION 32 13 11 Page 30 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Material Percentage by Mass Lightweight particles ASTM C123/C123M using a medium with a density of Sp. Gr. of 2.0 Total of all above 2.3 2.3.1 0.5 3.0 CHEMICAL ADMIXTURES General Requirements Chemical admixtures may only be used when the specific admixture type and manufacturer is the same material used in the mixture proportioning studies. The air-entraining admixture shall conform to ASTM C260/C260M. An accelerator conforming to ASTM C494/C494M, Type C, may be used only when specified in paragraph: SPECIFIED CONCRETE STRENGTH AND OTHER PROPERTIES below and shall not be used to reduce the amount of cementitious material used. Calcium chloride and admixtures containing calcium chloride shall not be used. Retarding or water-reducing admixture shall meet the requirements of ASTM C494/C494M, Type A, B, or D, except that the 6-month and 1-year compressive strength tests are waived. ASTM C494/C494M, Type F and G high range water reducing admixtures and ASTM C1017/C1017M flowable admixtures shall not be used. Lithium Nitrate The lithium admixture shall be a nominal 30 percent aqueous solution of Lithium Nitrate, with a density of 10 pounds/gallon, and shall have the approximate chemical form as shown below: Constituent Limit (Percent by Mass) LiNo3 (Lithium Nitrate) 30 +/- 0.5 SO4-2 (Sulfate Ion) 0.1 (max) Cl- (Chloride Ion) 0.2 (max) Na+ (Sodium Ion) 0.1 (max) K+ (Potassium Ion) 0.1 (max) Provide a trained representative to supervise the lithium nitrate admixture dispensing and mixing operations. [2.3.2 High Range Water Reducing Admixture (HRWRA) ************************************************************************** NOTE: High Range Water Reducing Admixtures are permitted only when using Silica Fume. Delete for all other projects ************************************************************************** A high-range water-reducing admixture shall meet the requirements of ASTM C494/C494M, Type F or G. The HRWRA shall be free from chlorides, URS FOR EQM SECTION 32 13 11 Page 31 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 alkalis, and shall be of the synthesized, sulfonated complex polymer type. The HRWRA shall be added to the concrete as a single component at the batch plant. The admixture shall be added to the concrete mixture only when its use is approved or directed, and only when it has been used in mixture proportioning studies to arrive at approved mixture proportions. Submit certified copies of the independent laboratory test results required for compliance with ASTM C494/C494M. ]2.4 MEMBRANE FORMING CURING COMPOUND ************************************************************************** NOTE: ASTM C309 may be used for roads and streets. Use CRD-C 300 for Army or Air Force airfield pavement projects. ************************************************************************** Membrane forming curing compound shall [be a white pigmented compound conforming to COE CRD-C 300.] [conform to ASTM C309, white-pigmented Type 2, Class B]. 2.5 WATER Water for injurious water, or meets the 2.6 mixing and curing shall be fresh, clean, potable, and free of amounts of oil, acid, salt, or alkali, except that non-potable water from concrete production operations, may be used if it requirements of ASTM C1602/C1602M. JOINT MATERIALS ************************************************************************** NOTE: Edit as appropriate for project requirements. Coordinate with Section 32 01 19 for Army projects and 32 13 73 for all other projects. ************************************************************************** 2.6.1 Expansion Joint Material Expansion joint filler shall be a preformed material conforming to [ ASTM D1751] [or] [ASTM D1752 Type [II] [III].] Expansion joint filler shall be 3/4 inch thick, unless otherwise indicated, and shall be furnished in a single full depth piece. 2.6.2 Slip Joint Material Slip joint material shall be 1/4 inch thick expansion joint filler, unless otherwise indicated, conforming to paragraph: Expansion Joint Material. 2.7 REINFORCING ************************************************************************** NOTE: Edit these paragraphs to conform to project requirements. Delete those not needed. Add epoxy-coated bars (ASTM A775/A775M) or low-alloy bars (ASTM A706/A706M) when required by design. ************************************************************************** All reinforcement shall be free from loose, flaky rust, loose scale, oil, grease, mud, or other coatings that might reduce the bond with concrete. Removal of thin powdery rust and tight rust is not required. However, URS FOR EQM SECTION 32 13 11 Page 32 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 reinforcing steel which is rusted to the extent that it does not conform to the required dimensions or mechanical properties shall not be used. 2.7.1 Reinforcing Bars and Bar Mats Reinforcing bars shall conform to [ASTM A615/A615M, billet-steel] [ ASTM A996/A996M, or rail and axle steel], Grade 60[_____]. Bar mats shall conform to ASTM A184/A184M. The bar members may be billet rail or axle steel. 2.7.2 Welded Wire Reinforcement Welded Wire Reinforcement shall be deformed or smooth, conforming to ASTM A1064/A1064M, and shall be furnished in flat sheets. 2.8 DOWELS[ AND TIE BARS] ************************************************************************** NOTE: Retain paragraph on dowels. Even if not required, design should normally allow dowels as an option. Edit tie bars as required by design. ************************************************************************** 2.8.1 Dowels Dowels shall be single piece bars fabricated or cut to length at the shop or mill before delivery to the site. Dowels shall be free of loose, flaky rust and loose scale and shall be clean and straight. Dowels may be sheared to length provided that the deformation from true shape caused by shearing does not exceed 0.04 inch on the diameter of the dowel and does not extend more than 0.04 inch from the end of the dowel. Dowels shall be plain (non-deformed) steel bars conforming to ASTM A615/A615M, Grade 40 or 60; ASTM A996/A996M, Grade 50 or 60. Dowel bars shall be epoxy coated in conformance with ASTM A775/A775M. Grout retention rings shall be fully circular metal or plastic devices capable of supporting the dowel until the epoxy hardens. Dowel sleeves or inserts are not permitted. 2.8.2 Dowel Bar Assemblies Dowel bar assemblies shall consist of a framework of metal bars or wires arranged to provide rigid support for the dowels throughout the paving operation, with a minimum of four continuous bars or wires extending along the joint line. The dowels shall be welded to the assembly or held firmly by mechanical locking arrangements that will prevent them from rising, sliding out, or becoming distorted during paving operations. [2.8.3 Tie Bars Tie bars shall be deformed steel bars conforming to ASTM A615/A615M, or ASTM A996/A996M, Grade 60 [_____], and of the sizes and dimensions indicated. Deformed rail steel bars and high-strength billet or axle steel bars, Grade 50 or higher, shall not be used for bars that are bent and straightened during construction. ]2.9 EPOXY RESIN All epoxy-resin materials shall be two-component materials conforming to the requirements of ASTM C881/C881M, Class as appropriate for each application temperature to be encountered, except that in addition, the URS FOR EQM SECTION 32 13 11 Page 33 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 materials shall meet the following requirements: a. Material for use for embedding dowels and anchor bolts shall be Type IV, Grade 3. b. Material for use as patching materials for complete filling of spalls and other voids and for use in preparing epoxy resin mortar shall be Type III, Grade as approved. c. Material for use for injecting cracks shall be Type IV, Grade 1. d. Material for bonding freshly mixed portland cement concrete or mortar or freshly mixed epoxy resin concrete or mortar to hardened concrete shall be Type V, Grade as approved. 2.10 EQUIPMENT All plant, equipment, tools, and machines used in the work shall be maintained in satisfactory working conditions at all times. Submit the following: a. Details and data on the batching and mixing plant prior to plant assembly including manufacturer's literature showing that the equipment meets all requirements specified herein. ************************************************************************** NOTE:For OCONUS projects, contact NRMCA (http://www.nrmca.org) concerning approved engineers available in the geographic area. ************************************************************************** b. Obtain National Ready Mixed Concrete Association (NRMCA) certification of the concrete plant. The concrete plant shall be inspected by an engineer approved by the NRMCA. A list of NRMCA approved engineers is available on the NRMCA website at http://www.nrmca.org. All fees and costs associated with this inspection shall be paid by the Contractor. Submit a copy of the NRMCA QC Manual Section 3 Concrete Plant Certification Checklist, NRMCA Certificate of Conformance, and Calibration documentation on all measuring and weighing devices prior to uniformity testing. c. A description of the equipment proposed for transporting concrete mixture from the central mixing plant to the paving equipment. d. A description of the equipment proposed for the machine and hand placing, consolidating and curing of the concrete mixture. Manufacturer's literature on the paver and finisher, together with the manufacturer's written instructions on adjustments and operating procedures necessary to assure a tight, smooth surface on the concrete pavement. The literature shall show that the equipment meets all details of these specifications. [Detailed information on automatic laser controlled systems shall be submitted if proposed for use.] 2.10.1 Batching and Mixing Plant ************************************************************************** NOTE: The batching and mixing plant should be on the construction site or as close as possible, but should be no farther than 15 minutes haul time from URS FOR EQM SECTION 32 13 11 Page 34 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the placing site during all periods of the work day. Verify the availability of water and electrical power for sites on Government land. On Navy projects, specify an off-site batch plant. Edit bracketed items as appropriate. Plant capacity should be governed by the laydown pattern or the size of the job to prevent delay of paving operations. ************************************************************************** a. Location: The batching and mixing plant shall be located [on project site as indicated on the drawings] [off Government premises no more than 15 minutes haul time from the placing site]. [Water and electrical power [are] [are not] available on the project site.] There shall be operable telephonic or radio communication between the plant and the placing site at all times concreting is taking place. b. Type and Capacity: The batching and mixing plant shall be a stationary-type central mix plant, including permanent installations or portable/relocatable plants installed on stable foundations. The plant shall be designed and operated to produce concrete within the specified tolerances, and shall have a capacity of at least 250 cubic yards [_____] per hour. The batching and mixing plant shall conform to the requirements of NRMCA QC 3 including provisions addressing: 1. 2. 3. 4. 5. c. Material Storage and Handling Batching Equipment Central Mixer Ticketing System Delivery System Tolerances: The following tolerances shall apply. Materials Percentage of Required Mass Cementitious Materials plus or minus 1 Aggregate plus or minus 2 Water plus or minus 1 Admixture plus or minus 3 For volumetric batching equipment for water and admixtures, the above numeric tolerances shall apply to the required volume of material being batched. Concentrated admixtures shall be uniformly diluted, if necessary, to provide sufficient volume per batch to ensure that the batchers will consistently operate within the above tolerance. ************************************************************************** NOTE: Edit as appropriate for project. Electric moisture meters should be required for large paving jobs. ************************************************************************** d. Moisture Control: The plant shall be capable of ready adjustment to compensate for the varying moisture contents of the aggregates and URS FOR EQM SECTION 32 13 11 Page 35 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 to change the quantities of the materials being batched. [An electric moisture meter complying with the provisions of COE CRD-C 143 shall be provided for measuring of moisture in the fine aggregate. The sensing element shall be arranged so that measurement is made near the batcher charging gate of the fine aggregate bin or in the fine aggregate batcher.] 2.10.2 Concrete Mixers a. General: Mixers shall be stationary or truck mixers. Mixers shall be capable of combining the materials into a uniform mixture and of discharging this mixture without segregation. The mixers shall not be charged in excess of the capacity recommended by the manufacturer. The mixers shall be operated at the drum or mixing blade speed designated by the manufacturer. The mixers shall be maintained in satisfactory operating condition, and the mixer drums shall be kept free of hardened concrete. Mixer blades or paddles shall be replaced when worn down more than 10 percent of their depth when compared with the manufacturer's dimension for new blades or paddles. b. Stationary: Stationary mixers shall be drum or pan mixers. Mixers shall be provided with an acceptable device to lock the discharge mechanism until the required mixing time has elapsed. c. Mixing Time and Uniformity for Stationary Mixers: For stationary mixers, before uniformity data are available, the mixing time for each batch after all solid materials are in the mixer, provided that all of the mixing water is introduced before one-fourth of the mixing time has elapsed, shall be 1 minute for mixers having a capacity of 1 cubic yard. For mixers of greater capacity, this minimum time shall be increased 20 seconds for each additional 1.33 cubic yard or fraction thereof. After results of uniformity tests are available, the mixing time may be reduced to the minimum time required to meet uniformity requirements; but if uniformity requirements are not being met, the mixing time shall be increased as directed. The mixing time for full batch production shall be a minimum of 75 seconds. Mixer performance tests at new mixing times shall be performed immediately after any change in mixing time. The Regular Test sequence shall be conducted for initial determination of the mixing time or as directed. When regular testing is performed, the concrete shall meet the limits of any five of the six uniformity requirements listed in Table 1 below. d. The Abbreviated Test sequence shall be conducted for production concrete verification at the frequency specified in Table 6. When abbreviated testing is performed, the concrete shall meet only those requirements listed for abbreviated testing. The concrete proportions used for uniformity tests shall be as used on the project. Regular testing shall consist of performing all six tests on three batches of concrete. The range for regular testing shall be the average of the ranges of the three batches. Abbreviated testing shall consist of performing the three required tests on a single batch of concrete. The range for abbreviated testing shall be the range for one batch. If more than one mixer is used and all are identical in terms of make, type, capacity, condition, speed of rotation, etc., the results of tests on one of the mixers shall apply to the others, subject to the approval of the Contracting Officer. All mixer performance (uniformity) testing shall be performed in accordance with COE CRD-C 55 and with paragraph titled TESTING AND INSPECTION FOR CONTRACTOR QUALITY CONTROL in PART 3. URS FOR EQM SECTION 32 13 11 Page 36 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 TABLE 1 UNIFORMITY REQUIREMENTS--STATIONARY MIXERS e. 2.10.3 Parameter Regular Tests Allowable Maximum Range for Average of 3 Batches Abbreviated Tests Allowable Maximum Range for 1 Batch Unit weight of air-free mortar Air content 2.0 lbs/cubic ft 2.0 lbs/cubic ft 1.0 percent -- Slump 1.0 inch 1.0 inch Coarse aggregate 6.0 percent 6.0 percent Compressive strength at 7 days Water content 10.0 percent 10.0 percent 1.5 percent Truck: Truck mixers shall not be used for mixing or transporting slipformed paving concrete. The only truck mixers used for mixing or transporting paving concrete shall be those designed with extra large blading and rear opening specifically for low-slump paving concrete. Truck mixers, the mixing of concrete therein, and concrete uniformity and testing thereof shall conform to the requirements of ASTM C94/C94M. The number of revolutions between 70 to 100 for truck-mixed concrete and the number of revolutions for shrink-mixed concrete shall be determined by uniformity tests as specified in ASTM C94/C94M and in requirements for mixer performance stated in paragraph TESTING AND INSPECTION FOR CONTRACTOR QUALITY CONTROL in PART 3. If requirements for the uniformity of concrete are not met with 100 revolutions of mixing after all ingredients including water are in the truck mixer drum, the mixer shall not be used until the condition is corrected. Water shall not be added after the initial introduction of mixing water except, when on arrival at the job site, the slump is less than specified and the water-cement ratio is less than that given as a maximum in the approved mixture. Additional water may be added to bring the slump within the specified range provided the approved water-cement ratio is not exceeded. Water shall be injected into the head of the mixer (end opposite the discharge opening) drum under pressure, and the drum or blades shall be turned a minimum of 30 additional revolutions at mixing speed. Water shall not be added to the batch at any later time.[ Mixer performance (uniformity) tests for truck mixers shall be made in accordance with ASTM C94/C94M.] Transporting Equipment Slipform concrete shall be transported to the paving site in nonagitating equipment conforming to ASTM C94/C94M or in approved agitators. Fixed form concrete shall be transported in approved truck mixers designed with extra large blading and rear opening specifically for low slump concrete. All transporting equipment shall be designed and operated to deliver and discharge the required concrete mixture completely without segregation. 2.10.4 Transfer and Spreading Equipment ************************************************************************** URS FOR EQM SECTION 32 13 11 Page 37 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NOTE: A transfer spreader is required for all Army and Air Force airfield paving projects. Delete this paragraph for Navy projects. Coordinate with Part 3 requirements in sub-paragraph: Traffic on Underlying Material. ************************************************************************** Equipment for transferring concrete from the transporting equipment to the paving lane in front of the paver shall be specially manufactured, self-propelled transfer equipment which will accept the concrete outside the paving lane and will transfer and spread it evenly across the paving lane in front of the paver and strike off the surface evenly to a depth which permits the paver to operate efficiently. 2.10.5 Paver-Finisher The following items a through e apply to both fixed-form and slip-form paver-finishers. Item f is applicable to fixed-form paver-finishers and item g is applicable to slip-form paver-finishers. a. General: The paver-finisher shall be a heavy-duty, self-propelled machine designed specifically for paving and finishing high quality pavement. The paver-finisher shall weigh at least 2200 lb/foot of lane width, and shall be powered by an engine having at least 6.0 horsepower/foot of lane width. The paver-finisher shall spread, consolidate, and shape the plastic concrete to the desired cross section in one pass. The mechanisms for forming the pavement shall be easily adjustable in width and thickness and for required crown. In addition to other spreaders required by paragraph above, the paver-finisher shall be equipped with a full width knock-down auger or paddle mechanism, capable of operating in both directions, which will evenly spread the fresh concrete in front of the screed or extrusion plate. b. Vibrators: Immersion vibrators shall be gang mounted at the front of the paver on a frame equipped with suitable controls so that all vibrators can be operated at any desired depth within the slab or completely withdrawn from the concrete, as required. The vibrators shall be automatically controlled so that they will be immediately stopped as forward motion of the paver ceases. [The paver-finisher shall be equipped with an electronic vibrator monitoring device displaying the operating frequency of each individual internal vibrator. The monitoring device shall have a readout display visible to the paver operator. It shall operate continuously while paving, and shall display all vibrator frequencies with manual or automatic sequencing among all individual vibrators.] The spacing of the immersion vibrators across the paving lane shall be as necessary to properly consolidate the concrete, but the clear distance between vibrators shall not exceed 30 inches. The outside vibrators shall not be more than 12 inches from the lane edge. Spud vibrators shall operate at a frequency of not less than 8000 impulses/minute and an amplitude of not less than 0.03 inch, as determined by COE CRD-C 521. c. Screed or Extrusion Plate: The paver-finisher shall be equipped with a transversely oscillating screed or an extrusion plate to shape, compact, and smooth the surface and shall so finish the surface that no significant amount of hand finishing, except use of cutting straightedges, is required. The screed or extrusion plate shall be constructed to provide adjustment for crown in the pavement. The URS FOR EQM SECTION 32 13 11 Page 38 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 entire machine shall provide adjustment for variation in lane width or thickness and to prevent more than 8 inches of the screed or extrusion plate extending over previously placed concrete on either end when paving fill-in lanes. Machines that cause displacement of properly installed forms or cause ruts or indentations in the prepared underlying materials and machines that cause frequent delays due to mechanical failures shall be replaced as directed. d. Longitudinal Mechanical Float: A longitudinal mechanical float may be used. If used, the float shall be specially designed and manufactured to smooth and finish the pavement surface without working excess paste to the surface. It shall be rigidly attached to the rear of the paver-finisher or to a separate self-propelled frame spanning the paving lane. The float plate shall be at least 5 feet long by 8 inches wide and shall automatically be oscillated in the longitudinal direction while slowly moving from edge to edge of the paving lane, with the float plate in contact with the surface at all times. e. Other Types of Finishing Equipment: Clary screeds, other rotating tube floats, or bridge deck finishers are not allowed on mainline paving, but may be allowed on irregular or odd-shaped slabs, and near buildings or trench drains, subject to the Contracting Officer's approval. Bridge deck finishers shall have a minimum operating weight of 7500 pounds and shall have a transversely operating carriage containing a knock-down auger and a minimum of two immersion vibrators. Vibrating screeds or pans shall be used only for isolated slabs where hand finishing is permitted as specified, and only where specifically approved. f. Fixed Forms: The paver-finisher shall be equipped with wheels designed to ride the forms, keep it aligned with the forms, and spread the load so as to prevent deformation of the forms. Paver-finishers traveling on guide rails located outside the paving lane shall be equipped with wheels when traveling on new or existing concrete to remain. g. Slipform: The slipform paver-finisher shall be automatically controlled and crawler mounted with padded tracks so as to be completely stable under all operating conditions. The paver-finisher shall finish the surface and edges so that no edge slump beyond allowable tolerance occurs. Suitable moving side forms shall be provided that are adjustable and will produce smooth, even edges, perpendicular to the top surface and meeting specification requirements for alignment and freedom from edge slump. 2.10.6 Curing Equipment Equipment for applying membrane-forming curing compound shall be mounted on a self-propelled frame that spans the paving lane. The reservoir for curing compound shall be constantly mechanically (not air) agitated during operation and shall contain means for completely draining the reservoir. The spraying system shall consist of a mechanically powered pump which will maintain constant pressure during operation, an operable pressure gauge, and either a series of spray nozzles evenly spaced across the lane to give uniformly overlapping coverage or a single spray nozzle which is mounted on a carriage which automatically traverses the lane width at a speed correlated with the forward movement of the overall frame. All spray nozzles shall be protected with wind screens. Calibrate the spraying system in accordance with ASTM D2995, Method A, for the rate of application required in paragraph: Membrane Curing. Any hand-operated sprayers allowed URS FOR EQM SECTION 32 13 11 Page 39 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 by that paragraph shall be compressed air supplied by a mechanical air compressor. If the curing equipment fails to apply an even coating of compound at the specified rate, it shall immediately be replaced. 2.10.7 Texturing Equipment ************************************************************************** NOTE: Designer must select type of texturing desired, retain that subparagraph, and delete the others. A genuine effort should be made to determine the type of texturing, if any, desired by the using service. If no guidance is given, the usual default method should be burlap drag. If other than a burlap drag textured finish is required, edit the appropriate paragraph(s) as shown below. For Air Force airfield paving projects, do not specify artificial turf, wire comb, or surface grooving textures. For Navy airfield paving projects, do not specify wire comb or surface grooving textures. Use Section 32 01 26.71 GROOVING FOR AIRFIELD PAVEMENTS, to specify saw-cut grooves. Spring tine grooving is limited to use on roads and streets only. ************************************************************************** a. General: Texturing equipment shall be as specified below. Before use, the texturing equipment shall be demonstrated on a test section, and the equipment shall be modified as necessary to produce the texture directed. b. Burlap Drag: A burlap drag shall be securely attached to a separate wheel mounted frame spanning the paving lane or to one of the other similar pieces of equipment. Length of the material shall provide 24 to 36 inches dragging flat on the pavement surface. Width shall be at least equal to the width of the slab. The material shall be clean, reasonably new burlap, completely saturated with water before attachment to the frame, always resaturated before start of use, and kept clean and saturated during use. Burlap shall conform to AASHTO M 182, Class 3 or 4. [ c. Broom: Surface texture shall be applied using an approved mechanical stiff bristle broom drag of a type that will uniformly score the surface transverse to the pavement center line. The broom shall be capable of traversing the full width of the pavement in a single pass at a uniform speed and with a uniform pressure. The scores shall be uniform in appearance and approximately 1/16 inch in depth but not more than 1/8 inch in depth.] [ d. Artificial Turf: The artificial turf drag shall be full-width and the leading transverse edge shall be securely fastened to a lightweight pole on a traveling bridge. At least 2 feet of the artificial turf shall be in contact with the concrete surface during texturing operations. The corrugations shall be uniform in appearance and approximately 1/16 inch in depth. A variety of different types of artificial turf are available and approval of any one type will be done only after it has been demonstrated by the Contractor to provide a URS FOR EQM SECTION 32 13 11 Page 40 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 satisfactory texture. One type that has provided satisfactory texture consists of 7,200 approximately 0.85-inches-long polyethylene turf blades per square foot.] [ e. 2.10.8 Deep Texturing Equipment: Texturing equipment shall consist of [a stiff bristled broom] [a comb with spring wire tines] [spring strips which will produce true, even grooves] forming a drag at least 4 feet long. This drag shall be mounted in a wheeled frame spanning the paving lane and so constructed that the drag is mechanically pulled in a straight line across the paving lane perpendicular to the centerline.] Sawing Equipment ************************************************************************** NOTE: Retain bracketed sentence as necessary to correlate with paragraph Removal of Existing Pavement Slab in PART 3. Otherwise delete. Also delete wheel saw option on Navy projects. ************************************************************************** Equipment for sawing joints and for other similar sawing of concrete shall be standard diamond-type concrete saws mounted on a wheeled chassis which can be easily guided to follow the required alignment. Blades shall be diamond tipped. If demonstrated to operate properly, abrasive blades may be used. Provide spares as required to maintain the required sawing rate. [Wheel saws used in the removal of concrete shall be saws with large diameter tungsten carbide tipped blades mounted on a heavy-duty chassis which will produce a saw kerf at least 1-1/2 inch wide.] All saws shall be capable of sawing to the full depth required. Early-entry saws may be used, subject to demonstration and approval of the Contracting Officer. No change to the initial sawcut depth shall be permitted. 2.10.9 Straightedge Furnish and maintain at the job site, in good condition, one 12 foot straightedge for each paving train for testing the hardened portland cement concrete surfaces. These straightedges shall be constructed of aluminum or magnesium alloy and shall have blades of box or box-girder cross section with flat bottom, adequately reinforced to insure rigidity and accuracy. Straightedges shall have handles for operation on the pavement. 2.11 SPECIFIED CONCRETE STRENGTH AND OTHER PROPERTIES ************************************************************************** NOTE: Fill in blanks as appropriate. Specified strength must be the flexural strength used in the structural design of the pavement and should not exceed 650 psi (4.5 MPa) at 90 days of age. Designer must also ensure that this strength is attainable with the available aggregates. Air content should be specified as 6 percent where freezing and thawing is a concern and 4 percent where it is not a concern. Specify strength at 90 days. However, modify to 28-days in line 2 if 28-day strength is used in paragraphs: Flexural Strength and Thickness. Be sure this and succeeding paragraphs correlate. ************************************************************************** URS FOR EQM SECTION 32 13 11 Page 41 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.11.1 TYMX989345A FA3002-09-D-0002 TG02 Specified Flexural Strength ************************************************************************** NOTE: Use the Tailoring Option "Beams" or "Cylinders/Beams" to specify flexural strength for concrete. ************************************************************************** Specified flexural strength, R, for concrete is 650[_____] psi at [28] [90] days, as determined by [tests made in accordance with ASTM C78/C78M of beams fabricated and cured in accordance with ASTM C192/C192M] Maximum allowable water-cementitious material ratio is 0.45. The water-cementitious material ratio will be the equivalent water-cement ratio as determined by conversion from the weight ratio of water to cement plus SCM by the mass equivalency method described in ACI 211.1. The concrete shall be air-entrained with a total air content of [4] [6] plus or minus 1.5 percentage points, at the point of placement. Air content shall be determined in accordance with ASTM C231/C231M. The maximum allowable slump of the concrete at the point of placement shall be 2 inches for pavement constructed with fixed forms. For slipformed pavement, at the start of the project, select a maximum allowable slump which will produce in-place pavement meeting the specified tolerances for control of edge slump. The selected slump shall be applicable to both pilot and fill-in lanes. 2.11.2 Concrete Temperature The temperature of the concrete as delivered shall conform to the requirements of paragraphs, Paving in Hot Weather and Paving in Cold Weather, in PART 3. Temperature of concrete shall be determined in accordance with ASTM C1064/C1064M. 2.11.3 Concrete Strength for Final Acceptance ************************************************************************** NOTE: Use the Tailoring Option to specify concrete strength by using "Cylinders/Beams" or "Beams". ************************************************************************** , [The strength of the concrete will be considered acceptable when the equivalent [90-day] [28-day] flexural strengths for each lot are above the 'Specified Flexural Strength' as determined by correlation with 14-day flexural strength tests specified in paragraph: "Mixture Proportioning for Flexural Strength" below, ]and no individual set (2 specimens per sublot) in the lot are 25 psi or more below the equivalent 'Specified Flexural Strength'. If any lot or sublot, respectively, fails to meet the above criteria, the lot or sublot shall be removed and replaced at no additional cost to the Government. This is in addition to and does not replace the average strength required for day-to-day CQC operations as specified in paragraph: Average CQC Flexural Strength Required for Mixtures, below. 2.12 MIXTURE PROPORTIONS ************************************************************************** NOTE: Edit bracketed items as appropriate. Normally, permit accelerator only with fast-track paving. If approval has been obtained and airfield pavement has been designed and specified for 28-day flexural strength in paragraph: Specified Flexural Strength, modify the following subparagraphs URS FOR EQM SECTION 32 13 11 Page 42 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 accordingly. Do the same if this is road pavement designed for 28-day strength. Use the higher bracketed cement content if pozzolan is used. ************************************************************************** 2.12.1 Composition Concrete shall be composed of cementitious material, water, fine and coarse aggregates, and admixtures. Supplementary Cementitious Materials (SCM) choice and usage shall be in accordance with paragraph: Supplementary Cementitious Materials (SCM) Content. The total cementitious material content shall be at least [ 470 lb./cu. yd.] [ 517 lb./cu. yd.]. Admixtures shall consist of air entraining admixture and may also include, as approved, [accelerator] [retarder] [and water-reducing admixture]. 2.12.2 Proportioning Studies Trial design batches, mixture proportioning studies, and testing requirements are the responsibility of the Contractor. Submit the results of the mixture proportioning studies signed and stamped by the registered professional engineer having technical responsibility for the mix design study, and submitted at least 30 days prior to commencing concrete placing operations. The results shall include a statement giving the maximum nominal coarse aggregate size and the weights and volumes of each ingredient proportioned on a one cubic yard basis. Aggregate quantities shall be based on the mass in a saturated surface dry condition. The recommended mixture proportions shall be accompanied by test results demonstrating that the proportions selected will produce concrete of the qualities indicated. Trial mixtures having proportions, slumps, and air content suitable for the work shall be based on methodology described in ACI 211.1, modified as necessary to accommodate flexural strength. Submit test results including: a. Coarse and fine aggregate gradations and plots. b. Combined aggregate gradation [and coarseness/workability] plots. c. Coarse aggregate quality test results, include deleterious materials. d. Fine aggregate quality test results. e. Mill certificates for cement and supplemental cementitious materials. f. Certified test results for air entraining, water reducing, retarding, non-chloride accelerating[, and Lithium Nitrate] admixtures. g. Specified flexural strength, slump, and air content. h. Documentation of required average CQC flexural strength, Ra. i. Recommended proportions/volumes for proposed mixture and each of three trial water-cementitious materials ratios. j. Individual beam breaks. k. Flexural strength summaries and plots. l. Correlation ratios for acceptance testing and CQC testing. m. Historical record of test results, documenting production standard deviation (if available). 2.12.2.1 Water-Cement Ratio At least three different water-cement ratios, which will produce a range of strength encompassing that required on the project, shall be used. The maximum allowable water-cement ratio required in paragraph: Specified Flexural Strength, above will be the equivalent water-cement ratio. Laboratory trial mixtures shall be proportioned for maximum permitted slump and air content. URS FOR EQM SECTION 32 13 11 Page 43 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.12.2.2 TYMX989345A FA3002-09-D-0002 TG02 Trial Mixture Studies Separate sets of trial mixture studies shall be made for each combination of cementitious materials and each combination of admixtures proposed for use. No combination of either shall be used until proven by such studies, except that, if approved in writing and otherwise permitted by these specifications, an accelerator or a retarder may be used without separate trial mixture study. Separate trial mixture studies shall also be made for concrete for each placing method (slip form, fixed form, or hand placement) proposed. The temperature of concrete in each trial batch shall be reported. Each mixture shall be designed to promote easy and suitable concrete placement, consolidation and finishing, and to prevent segregation and excessive bleeding. 2.12.2.3 Mixture Proportioning for Flexural Strength ************************************************************************** NOTE: The first Tailoring Option, "Beams", includes items a through j; the second option "Cylinders/Beams" includes the second listing of items 1 through 10. ************************************************************************** The following step by step procedure shall be followed: [ a. Fabricate all beams for each mixture from the same batch or blend of batches. Fabricate and cure all beams in accordance with ASTM C192/C192M, using 6 x 6 inch steel beam forms. b. Cure test beams from each mixture for 3, 7, 14, and [28][90]-day flexural tests; 6 beams to be tested per age. c. Test beams in accordance with ASTM C78/C78M. d. Using the average strength for each w/c at each age, plot all results from each of the three mixtures on separate graphs for w/c versus: 3-day flexural strength 7-day flexural strength 14-day flexural strength [28-day flexural strength] [90-day flexural strength] e. From these graphs select a w/c that will produce a mixture giving a [28] [90]-day flexural strength equal to the required strength determined in accordance with the next paragraph. f. Using the above selected w/c, select from the graphs the expected 3, 7 and 14-day flexural strengths. g. From the above expected strengths for the selected mixture, determine the Ratio of the 7-day flexural strength of the selected mixture to the [28][90]-day flexural strength of the mixture (for CQC control). h. From the above expected strengths for the selected mixture, determine the Ratio of the 14-day flexural strength of the selected mixture to the [28][90]-day flexural strength of the mixture (for acceptance). i. If there is a change in materials, additional mixture design studies shall be made using the new materials and new Correlation Ratios shall URS FOR EQM SECTION 32 13 11 Page 44 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 be determined. j. 2.12.3 No concrete pavement shall be placed until the Contracting Officer has approved the Contractor's mixture proportions. The approved water-cementitious materials ratio shall not exceed the maximum value specified in paragraph: Specified Flexural Strength, above and shall not be increased without the Contracting Officer's written approval.] Average CQC Flexural Strength Required for Mixtures In order to ensure meeting the strength requirements specified in paragraph: SPECIFIED CONCRETE STRENGTH AND OTHER PROPERTIES above, during production, the mixture proportions selected during mixture proportioning studies and used during construction shall produce a required average CQC flexural strength exceeding the specified strength, R, by the amount indicated below. This required average CQC flexural strength, Ra, will be used only for CQC operations as specified in paragraph: TESTING AND INSPECTION FOR CONTRACTOR QUALITY CONTROL in PART 3 and as specified in the previous paragraph. During production, the required Ra shall be adjusted , as appropriate and as approved, based on the standard deviation of [average [28] [90]]-day strengths being attained during paving. a. From Previous Test Records: Where a concrete production facility has previous test records current to within 18 months, a standard deviation shall be established in accordance with the applicable provisions of ACI 214R. Test records from which a standard deviation is calculated shall represent materials, quality control procedures, and conditions similar to those expected, shall represent concrete produced to meet a specified flexural strength or strengths within 150 psi of the [28] [90] -day flexural strength specified for the proposed work, and shall consist of at least 30 consecutive tests. Perform verification testing, as directed by the Contracting Officer, to document the current strength. A strength test shall be the average of the strengths of two specimens made from the same sample of concrete and tested at [28] [90] days. Required average CQC flexural strength, Ra, used as the basis for selection of concrete proportions shall be the value from the equation that follows, using the standard deviation as determined above: Ra = R + 1.34S Where: S = standard deviation R = specified flexural strength Ra = required average flexural strength Where a concrete production facility does not have test records meeting the requirements above but does have a record based on 15 to 29 consecutive tests, a standard deviation shall be established as the product of the calculated standard deviation and a modification factor from the following table: NUMBER OF TESTS 15 URS FOR EQM MODIFICATION FACTOR FOR STANDARD DEVIATION 1.16 SECTION 32 13 11 Page 45 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS NUMBER OF TESTS b. PART 3 3.1 TYMX989345A FA3002-09-D-0002 TG02 20 MODIFICATION FACTOR FOR STANDARD DEVIATION 1.08 25 1.03 30 or more 1.00 Without Previous Test Records: When a concrete production facility does not have sufficient field strength test records for calculation of the standard deviation, the required average strength, Ra, shall be determined by adding 15 percent to the specified flexural strength, R. EXECUTION PREPARATION FOR PAVING Before commencing paving, perform the following. If used, forms shall be in place, cleaned, coated, and adequately supported. Any reinforcing steel needed shall be at the paving site. All transporting and transfer equipment shall be ready for use, clean, and free of hardened concrete and foreign material. Equipment for spreading, consolidating, screeding, finishing, and texturing concrete shall be at the paving site, clean and in proper working order. All equipment and material for curing and for protecting concrete from weather or mechanical damage shall be at the paving site, in proper working condition, and in sufficient amount for the entire placement. 3.1.1 Weather Precaution When windy conditions during paving appear probable, equipment and material shall be at the paving site to provide windbreaks, shading, fogging, or other action to prevent plastic shrinkage cracking or other damaging drying of the concrete. 3.1.2 Proposed Techniques ************************************************************************** NOTE: Include joint layout and typical detail of joint/dowel bar spacing in drawings and coordinate with paragraph: Placing Dowels and Tie Bars. Insert office title for approval of joint plan changes. ************************************************************************** Submit placing and protection methods; paving sequence; jointing pattern; data on curing equipment and profilographs; demolition of existing pavements, as specified; pavement diamond grinding equipment and procedures. Submit for approval the following items: a. A description of the placing and protection methods proposed when concrete is to be placed in or exposed to hot, cold, or rainy weather conditions. b. A detailed paving sequence plan and proposed paving pattern showing all planned construction joints; transverse and longitudinal dowel bar spacing; and identifying pilot lanes and hand placement areas. No deviation from the jointing pattern shown on the drawings shall be made URS FOR EQM SECTION 32 13 11 Page 46 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 without written approval of the [design engineer] [_____]. c. Plan and equipment proposed to control alignment of sawn joints within the specified tolerances. d. Data on the curing equipment, media and methods to be used. e. Data on profilograph and methods to measure pavement smoothness. f. Pavement demolition work plan, presenting the proposed methods and equipment to remove existing pavement and protect pavement to remain in place. 3.2 3.2.1 CONDITIONING OF UNDERLYING MATERIAL General Procedures Underlying material, upon which concrete is to be placed shall be clean, damp, and free from debris, waste concrete or cement, frost, ice, and standing or running water. Prior to setting forms or placement of concrete, the underlying material shall be well drained and shall have been satisfactorily graded by string-line controlled, automated, trimmer/fine grader and uniformly compacted in accordance with the applicable Section of these specifications. The surface of the underlying material shall be tested as to crown, elevation, and density in advance of setting forms or of concrete placement using slip-form techniques. High areas shall be trimmed to proper elevation. Low areas shall be filled and compacted to a condition similar to that of surrounding grade, or filled with concrete monolithically with the pavement. Low areas filled with concrete shall not be cored for thickness to avoid biasing the average thickness used for evaluation and payment adjustment. Any underlying material disturbed by construction operations shall be reworked and recompacted to specified density immediately in front of the paver. If a slipform paver is used, the same underlying material under the paving lane shall be continued beyond the edge of the lane a sufficient distance and shall be thoroughly compacted and true to grade to provide a suitable trackline for the slipform paver and firm support for the edge of the paving lane. 3.2.2 Traffic on Underlying Material ************************************************************************** NOTE: Transporting equipment should not be allowed to operate on the prepared underlying material for airfield paving. Operating hauling equipment in the paving lane will cause the paver to stop frequently, producing a discontinuity in the pavement surface. Edit bracketed items as appropriate and coordinate with Part 2, subparagraph: Transfer and Spreading Equipment. ************************************************************************** After the underlying material has been prepared for concrete placement, no equipment shall be permitted thereon. Subject to specific approval, crossing of the prepared underlying material at specified intervals for construction purposes may be permitted, provided rutting or indentations do not occur. The surface shall be reworked and reprepared to the satisfaction of the Contracting Officer before concrete is placed. [No transporting equipment shall be allowed to operate on the prepared and compacted underlying material in front of the paver-finisher.] [Equipment shall be allowed to operate on the underlying material only if approved by URS FOR EQM SECTION 32 13 11 Page 47 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the Contracting Officer and only if no damage is done to the underlying material and its degree of compaction. Any disturbance to the underlying material that does occur shall be corrected, as approved, before the paver-finisher or the deposited concrete reaches the location of the disturbance and the equipment shall be replaced or procedures changed to prevent any future damage.] 3.3 WEATHER LIMITATIONS 3.3.1 Placement and Protection During Inclement Weather Do not commence placing operations when heavy rain or other damaging weather conditions appear imminent. At all times when placing concrete, maintain on-site sufficient waterproof cover and means to rapidly place it over all unhardened concrete or concrete that might be damaged by rain. Suspend placement of concrete whenever rain, high winds, or other damaging weather commences to damage the surface or texture of the placed unhardened concrete, washes cement out of the concrete, or changes the water content of the surface concrete. All unhardened concrete shall be immediately covered and protected from the rain or other damaging weather. Any slab damaged by rain or other weather shall be completely removed full depth, by full slab width, to the nearest original joint, and replaced at the Contractor's expense as specified in paragraph: REPAIR, REMOVAL AND REPLACEMENT OF NEWLY CONSTRUCTED SLABS below. 3.3.2 Paving in Hot Weather ************************************************************************** NOTE: Additional information concerning hot weather concreting may be obtained from ACI 305R. Do not delete this paragraph or the next paragraphs dealing with weather. ************************************************************************** When the ambient temperature during paving is expected to exceed 90 degrees F, the concrete shall be properly placed and finished in accordance with procedures previously submitted, approved, and as specified herein. The concrete temperature at time of delivery to the forms shall not exceed the temperature shown in the table below when measured in accordance with ASTM C1064/C1064M. Cooling of the mixing water or aggregates or placing in the cooler part of the day may be required to obtain an adequate placing temperature. Steel forms and reinforcing shall be cooled as needed to maintain steel temperatures below 120 degrees F. Transporting and placing equipment shall be cooled or protected if necessary to maintain proper concrete placing temperature. The finished surfaces of the newly laid pavement shall be kept damp by applying a fog spray (mist) with approved spraying equipment until the pavement is covered by the curing medium. Maximum Allowable Concrete Placing Temperature Relative Humidity, Percent, During Time of Concrete Greater than 60 Maximum Allowable Concrete Temperature in Degrees F 95 40-60 85 Less than 40 80 URS FOR EQM SECTION 32 13 11 Page 48 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.3.3 TYMX989345A FA3002-09-D-0002 TG02 Prevention of Plastic Shrinkage Cracking During weather with low humidity, and particularly with high temperature and appreciable wind, develop and institute measures to prevent plastic shrinkage cracks from developing. If plastic shrinkage cracking occurs, halt further placement of concrete until protective measures are in place to prevent further cracking. Periods of high potential for plastic shrinkage cracking can be anticipated by use of Fig. 4.2 of ACI 305R. In addition to the protective measures specified in the previous paragraph, the concrete placement shall be further protected by erecting shades and windbreaks and by applying fog sprays of water, the addition of monomolecular films, or wet covering. Apply monomolecular films after finishing is complete, do not use in the finishing process. When such water treatment is stopped, curing procedures shall be immediately commenced. Plastic shrinkage cracks that occur shall be repaired in accordance with paragraph: REPAIR, REMOVAL, REPLACEMENT OF NEWLY CONSTRUCTED SLABS. Plastic shrinkage cracks shall never be troweled over or filled with slurry. 3.3.4 Paving in Cold Weather Cold weather paving shall conform to ACI 306R. Special protection measures, as specified herein, shall be used if freezing temperatures are anticipated before the expiration of the specified curing period. Placement of concrete shall not begin unless the ambient temperature is at least 35 degrees F and rising. Thereafter, placement of concrete shall be halted whenever the ambient temperature drops below 40 degrees F. When the ambient temperature is less than 50 degrees F, the temperature of the concrete when placed shall be not less than 50 degrees F nor more than 75 degrees F. Heating of the mixing water or aggregates will be required to regulate the concrete placing temperature. Materials entering the mixer shall be free from ice, snow, or frozen lumps. Salt, chemicals or other materials shall not be incorporated in the concrete to prevent freezing. If allowed under paragraph: MIXTURE PROPORTIONS in PART 2, an accelerating admixture may be used when the ambient temperature is below 50 degrees F. Covering and other means shall be provided for maintaining the concrete at a temperature of at least 50 degrees F for not less than 72 hours after placing, and at a temperature above freezing for the remainder of the curing period. Remove pavement slabs damaged by freezing or falling below freezing temperature to full depth, by full slab width, to the nearest original joint, and replace at the Contractor's expense as specified in paragraph REPAIR, REMOVAL, REPLACEMENT OF NEWLY CONSTRUCTED SLABS. 3.4 CONCRETE PRODUCTION ************************************************************************** NOTE: Designer must correlate these paragraphs with paragraph EQUIPMENT. Delete item in brackets if truck mixers are not permitted. ************************************************************************** Batching, mixing, and transporting equipment shall have a capacity sufficient to maintain a continuous, uniform forward movement of the paver of not less than 2.5 feet per minute. Concrete transported in non-agitating equipment shall be deposited in front of the paver within 45 minutes from the time cement has been charged into the mixing drum, except that if the ambient temperature is above 90 degrees F, the time shall be reduced to 30 minutes. Concrete transported in truck mixers shall be URS FOR EQM SECTION 32 13 11 Page 49 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 deposited in front of the paver within 90 minutes from the time cement has been charged into the mixer drum of the plant or truck mixer. If the ambient temperature is above 90 degrees F, the time shall be reduced to 60 minutes. Every load of concrete delivered to the paving site shall be accompanied by a batch ticket from the operator of the batching plant. Tickets shall be on approved forms and shall show at least the mass, or volume, of all ingredients in each batch delivered, [the water meter and revolution meter reading on truck mixers] and the time of day. Tickets shall be delivered to the placing foreman who shall keep them on file and deliver them to the Government weekly, or as directed by the Contracting Officer. 3.4.1 Batching and Mixing Concrete Scale pivots and bearings shall be kept clean and free of rust. Any equipment which fails to perform as specified shall immediately be removed from use until properly repaired and adjusted, or replaced. 3.4.2 Transporting and Transfer - Spreading Operations Non-agitating equipment shall be used only on smooth roads and for haul time less than 15 minutes. Concrete shall be deposited as close as possible to its final position in the paving lane. All equipment shall be operated to discharge and transfer concrete without segregation. In no case shall dumping of concrete in discrete piles be permitted. No transfer or spreading operation which requires the use of front-end loaders, dozers, or similar equipment to distribute the concrete will be permitted. 3.5 PAVING ************************************************************************** NOTE: Designer must correlate these paragraphs with paragraph EQUIPMENT. ************************************************************************** 3.5.1 General Requirements Pavement shall be constructed with paving and finishing equipment utilizing rigid fixed forms or by use of slipform paving equipment. Paving and finishing equipment and procedures shall be capable of constructing paving lanes of the required width at a rate of at least 2.5 feet of paving lane per minute on a routine basis. Paving equipment and its operation shall be controlled, and coordinated with all other operations, such that the paver-finisher has a continuous forward movement, at a reasonably uniform speed, from beginning to end of each paving lane, except for inadvertent equipment breakdown. Backing the paver and refinishing a lane is not permitted. Remove and replace concrete refinished in this manner. Failure to achieve a continuous forward motion requires halting operations, regrouping, and modifying operations to achieve this requirement. Workmen with foreign material on their footwear or construction equipment that might deposit foreign material shall not be permitted to walk or operate in the plastic concrete. Where an open-graded granular base is required under the concrete, select paving equipment and procedures which will operate properly on the base course without causing displacement or other damage. 3.5.2 Consolidation Concrete shall be consolidated with the specified type of lane-spanning, gang-mounted, mechanical, immersion type vibrating equipment mounted in URS FOR EQM SECTION 32 13 11 Page 50 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 front of the paver, supplemented, in rare instances as specified, by hand-operated vibrators. The vibrators shall be inserted into the concrete to a depth that will provide the best full-depth consolidation but not closer to the underlying material than 2 inches. Excessive vibration shall not be permitted. If the vibrators cause visible tracking in the paving lane, the paving operation shall be stopped and equipment and operations modified to prevent it. Concrete in small, odd-shaped slabs or in isolated locations inaccessible to the gang-mounted vibration equipment shall be vibrated with an approved hand-operated immersion vibrator operated from a bridge spanning the area. Vibrators shall not be used to transport or spread the concrete. Hand-operated vibrators shall not be operated in the concrete at one location for more than 20 seconds. Insertion locations for hand-operated vibrators shall be between 6 to 15 inches on centers. For each paving train, at least one additional vibrator spud, or sufficient parts for rapid replacement and repair of vibrators shall be maintained at the paving site at all times. Any evidence of inadequate consolidation (honeycomb along the edges, large air pockets, or any other evidence) shall require the immediate stopping of the paving operation and approved adjustment of the equipment or procedures. 3.5.3 Operation When the paver approaches a header at the end of a paving lane, a sufficient amount of concrete shall be maintained ahead of the paver to provide a roll of concrete which will spill over the header. The amount of extra concrete shall be sufficient to prevent any slurry that is formed and carried along ahead of the paver from being deposited adjacent to the header. The spud vibrators in front of the paver shall be brought as close to the header as possible before they are lifted. Additional consolidation shall be provided adjacent to the headers by hand-manipulated vibrators. When the paver is operated between or adjacent to previously constructed pavement (fill-in lanes), provisions shall be made to prevent damage to the previously constructed pavement. Screeds or extrusion plates shall be electronically controlled from the previously placed pavement so as to prevent them from applying pressure to the existing pavement and to prevent abrasion of the pavement surface. The overlapping area of existing pavement surface shall at all times be kept completely free of any loose or bonded foreign material as the paver-finisher operates across it. When the paver travels on existing pavement, approved provisions shall be made to prevent damage to the existing pavement. Pavers using transversely oscillating screeds shall not be used to form fill-in lanes that have widths less than a full width for which the paver was designed or adjusted. 3.5.4 Required Results The paver-finisher, and its gang-mounted vibrators, together with its operating procedures shall be adjusted and operated and coordinated with the concrete mixture being used to produce a thoroughly consolidated slab throughout, true to line and grade within specified tolerances. The paver-finishing operation shall produce a surface finish free of irregularities, tears, voids of any kind, and any other discontinuities. The paver-finisher shall make only one pass across the pavement; multiple passes will not be permitted. The equipment and its operation shall produce a finished surface requiring no hand finishing other than the use of cutting straightedges, except in very infrequent instances. If any equipment or operation fails to produce the above results, the paving shall be stopped, the equipment shall be replaced or properly adjusted, the operation shall be appropriately modified, or the mixture proportions modified, in order to produce the required results before recommencing URS FOR EQM SECTION 32 13 11 Page 51 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 paving. No water, other than fog sprays (mist) as specified in paragraph: Prevention of Plastic Shrinkage Cracking above, shall be applied to the concrete or the concrete surface during paving and finishing. 3.5.5 Fixed Form Paving ************************************************************************** NOTE: Fixed-form paving should always be included as an option or mandatory item as appropriate. Edit bracketed items in subparagraph a. Keys are only permitted for roads and streets with a thickness of 230 mm (9 inches) or greater. Do not permit keys for airfield pavements. ************************************************************************** Paving equipment for fixed-form paving and the operation thereof shall conform to the requirements of paragraph EQUIPMENT, and all requirements specified herein. 3.5.5.1 Forms for Fixed-Form Paving ************************************************************************** NOTE: Delete subparagraph e. when overlay pavements are not required. ************************************************************************** a. Straight forms shall be made of steel and shall be furnished in sections not less than 10 feet in length. Flexible or curved forms of proper radius shall be used for curves of 100-foot radius or less. Wood forms for curves and fillets shall be made of well-seasoned, surfaced plank or plywood, straight, and free from warp or bend. Wood forms shall be adequate in strength and rigidly braced. Forms shall have a depth equal to the pavement thickness at the edge. Where the project requires several different slab thicknesses, forms may be built up by bolting or welding a tubular metal section or by bolting wood planks to the bottom of the form to completely cover the underside of the base of the form and provide an increase in depth of not more than 25 percent. The base width of the one-piece or built-up form shall be not less than eight-tenths of the vertical height of the form, except than forms 8 inches or less in vertical height shall have a base width not less than the vertical height of the form. Maximum vertical deviation of top of any side form, including joints, shall not vary from a true plane more than 1/8 inch in 10 feet, and the upstanding leg shall not vary more than 1/4 inch. [Where keyway forms are required, they shall be rigidly attached to the main form so no displacement can take place. Metal keyway forms shall be tack-welded to steel forms. Keyway forms shall be so aligned that there is no variation over 1/4 inch either vertically or horizontally, when tested with a 12 foot template after forms are set, including tests across form joints.] b. Form sections shall be tightly locked and shall be free from play or movement in any direction. Forms shall be provided with adequate devices for secure settings so that when in place they will withstand, without visible spring or settlement, the impact and vibration of the consolidating and finishing equipment. c. Set forms for full bearing on foundation for entire length and width and in alignment with edge of finished pavement. Support forms during entire operation of placing, compaction, and finishing so that forms URS FOR EQM SECTION 32 13 11 Page 52 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 will not deviate vertically more than 0.01 foot from required grade and elevations indicated. Conformity to the alignment and grade elevations shown on the drawings shall be checked and necessary corrections shall be made immediately prior to placing the concrete. The forms shall be cleaned and oiled each time before concrete is placed. No concrete shall be placed until setting of forms has been checked and approved by the CQC team. d. [ e. Do not anchor guide rails for fixed form pavers into new concrete or existing concrete to remain. Forms for overlay pavements and for other locations where forms must be set on existing pavements shall be held securely in place with stakes or by other approved methods. Holes in existing pavements for form stakes shall be carefully drilled by methods which will not crack or spall the existing pavement. After use, the holes shall be filled flush with the surrounding surface using approved material, prior to overlying materials being placed. Any method which does not hold the form securely or which damages the existing pavement shall be immediately discontinued. Prior to setting forms for paving operations, demonstrate the proposed form setting procedures at an approved location without proceeding further until the proposed method is approved by the Contracting Officer.] 3.5.5.2 Form Removal Keep forms in place at least 12 hours after the concrete has been placed. When conditions are such that the early strength gain of the concrete is delayed, leave the forms in place for a longer time, as directed. Remove forms by procedures that do not injure the concrete. Bars or heavy metal tools shall not be used directly against the concrete in removing the forms. Any concrete found to be defective after form removal shall be repaired promptly, using procedures specified or as directed. 3.5.6 Slipform Paving ************************************************************************** NOTE: Retain slipform paving as an option unless there are specific, valid reasons for deleting it. Be sure all other paragraphs correlate with choice made here. ************************************************************************** 3.5.6.1 General Paving equipment for slipform paving and the operation thereof shall conform to the requirement of paragraph EQUIPMENT, and all requirements specified herein. The slipform paver shall shape the concrete to the specified and indicated cross section, meeting all tolerances, in one pass. The slipform paver shall finish the surface and edges so that only a very minimum isolated amount of hand finishing is required. If the paving operation does not meet the above requirements and the specified tolerances, immediately stop the operation, and regroup and replace or modify any equipment as necessary, modify paving procedures or modify the concrete mix, in order to resolve the problem. The slipform paver shall be automatically electronically controlled from a taut wire guideline for horizontal alignment and on both sides from a taut wire guideline for vertical alignment, except that electronic control from a ski operating on a previously constructed adjoining lane shall be used where applicable for URS FOR EQM SECTION 32 13 11 Page 53 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 either or both sides. Automatic, electronic controls for vertical alignment shall always be used on both sides of the lane. Control from a slope-adjustment control or control operating from the underlying material shall never be used. Side forms on slipform pavers shall be properly adjusted so that the finished edge of the paving lane meets all specified tolerances. Dowels in longitudinal construction joints shall be installed as specified below. The installation of these dowels by dowel inserters attached to the paver or by any other means of inserting the dowels into the plastic concrete shall not be permitted. [If a keyway is required, a 26 gauge thick metal keyway liner shall be installed as the keyway is extruded. Keyway forms shall not vary more than plus or minus 1/8 inch from the dimensions indicated and shall not deviate more than plus or minus 1/4 inch from the mid-depth of the pavement. There shall be no abrupt offset either horizontally or vertically in the completed keyway. The keyway liner shall be protected and shall remain in place and become part of the joint.] 3.5.6.2 Guideline for Slipform Paving Accurately and securely install guidelines well in advance of concrete placement. Provide supports at necessary intervals to eliminate all sag in the guideline when properly tightened. The guideline shall be high strength wire set with sufficient tension to remove all sag between supports. Supports shall be securely staked to the underlying material or other provisions made to ensure that the supports will not be displaced when the guideline is tightened or when the guideline or supports are accidentally touched by workmen or equipment during construction. The appliances for attaching the guideline to the supports shall be capable of easy adjustment in both the horizontal and vertical directions. When it is necessary to leave gaps in the guideline to permit equipment to use or cross underlying material, provisions shall be made for quickly and accurately replacing the guideline without any delay to the forward progress of the paver. Supports on either side of the gap shall be secured in such a manner as to avoid disturbing the remainder of the guideline when the portion across the gap is positioned and tightened. The guideline across the gap and adjacent to the gap for a distance of 200 feet shall be checked for horizontal and vertical alignment after the guideline across the gap is tightened. Vertical and horizontal positioning of the guideline shall be such that the finished pavement shall conform to the alignment and grade elevations shown on the drawings within the specified tolerances for grade and smoothness. The specified tolerances are intended to cover only the normal deviations in the finished pavement that may occur under good supervision and do not apply to setting of the guideline. The guideline shall be set true to line and grade. 3.5.6.3 Laser Controls If the Contractor proposes to use any type of automatic laser controls, submit a detailed description of the system and perform a trial field demonstration in the presence of the Contracting Officer at least one week prior to start of paving. Approval of the control system will be based on the results of the demonstration and on continuing satisfactory operation during paving. 3.5.7 Placing Reinforcing Steel ************************************************************************** NOTE: Delete bracketed item if CRCP is not being constructed. URS FOR EQM SECTION 32 13 11 Page 54 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** The type and amount of steel reinforcement shall be as shown on the drawings. 3.5.7.1 Pavement Thickness Greater Than 12 Inches For pavement thickness of 12 inches or more, the reinforcement steel shall be installed by the strike-off method wherein a layer of concrete is deposited on the underlying material, consolidated, and struck to the indicated elevation of the steel reinforcement. The reinforcement shall be laid upon the prestruck surface, and the remaining concrete shall then be placed and finished in the required manner. When placement of the second lift causes the steel to be displaced horizontally from its original position, provisions shall be made for increasing the thickness of the first lift and depressing the reinforcement into the unhardened concrete to the required elevation. The increase in thickness shall be only as necessary to permit correct horizontal alignment to be maintained. Any portions of the bottom layer of concrete that have been placed more than 30 minutes without being covered with the top layer shall be removed and replaced with newly mixed concrete without additional cost to the Government. 3.5.7.2 Pavement Thickness Less Than 12 Inches For pavements less than 12 inches thick, the reinforcement shall be positioned on suitable chairs or continuous mesh support devices securely fastened to the subgrade prior to concrete placement. Concrete shall be vibrated after the steel has been placed. Regardless of placement procedure, the reinforcing steel shall be free from coatings which could impair bond between the steel and concrete, and laps in the reinforcement shall be as indicated. Regardless of the equipment or procedures used for installing reinforcement, ensure that the entire depth of concrete is adequately consolidated. [If reinforcing for Continuously Reinforced Concrete Pavement (CRCP) is required, the entire operating procedure and equipment proposed shall be submitted for approval at least 30 days prior to proposed start of paving.] 3.5.8 Placing Dowels[ and Tie Bars] ************************************************************************** NOTE: Delete references to slipform paving installation of dowels and tie bars if slipform paving is not allowed. Delete references to installation in contraction joints if not required. Delete bracketed references to tie bars, if tie bars are not used. Tie bars are not permitted in airfield pavements. Use tie bars only for roads and streets projects. ************************************************************************** The method used in installing and holding dowels in position shall ensure that the error in alignment of any dowel from its required horizontal and vertical alignment after the pavement has been completed will not be greater than 1/8 in. per ft. Except as otherwise specified below, horizontal spacing of dowels shall be within a tolerance of plus or minus 5/8 inch. The vertical location on the face of the slab shall be within a tolerance of plus or minus 1/2 inch). The vertical alignment of the dowels shall be measured parallel to the designated top surface of the pavement, URS FOR EQM SECTION 32 13 11 Page 55 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 except for those across the crown or other grade change joints. Dowels across crowns and other joints at grade changes shall be measured to a level surface. Horizontal alignment shall be checked perpendicular to the joint edge. The horizontal alignment shall be checked with a framing square. Dowels [and tie bars] shall not be placed closer than 0.6 times the dowel bar [tie bar] length to the planned joint line. If the last regularly spaced longitudinal dowel[tie bar] is closer than that dimension, it shall be moved away from the joint to a location 0.6 times the dowel bar [tie bar]length, but not closer than 6 inches to its nearest neighbor. Dowel (tie bar) interference at a transverse joint-longitudinal joint intersection shall be resolved by deleting the closest transverse dowel (tie bar). Dowels shall be installed as specified in the following subparagraphs. 3.5.8.1 Contraction Joints Dowels [and tie bars] in longitudinal and transverse contraction joints within the paving lane shall be held securely in place, as indicated, by means of rigid metal frames or basket assemblies of an approved type. The basket assemblies shall be held securely in the proper location by means of suitable pins or anchors. Do not cut or crimp the dowel basket tie wires. At the Contractor's option, in lieu of the above, dowels [and tie bars] in contraction joints shall be installed near the front of the paver by insertion into the plastic concrete using approved equipment and procedures. Approval will be based on the results of a preconstruction demonstration, showing that the dowels [and tie bars] are installed within specified tolerances. 3.5.8.2 Construction Joints-Fixed Form Paving Install dowels [and tie bars] by the bonded-in-place method or the drill-and-dowel method. Installation by removing and replacing in preformed holes will not be permitted. Dowels [and tie bars] shall be prepared and placed across joints where indicated, correctly aligned, and securely held in the proper horizontal and vertical position during placing and finishing operations, by means of devices fastened to the forms. The spacing of dowels [and tie bars] in construction joints shall be as indicated, except that, where the planned spacing cannot be maintained because of form length or interference with form braces, closer spacing with additional dowels [or tie bars] shall be used. 3.5.8.3 Dowels Installed in Hardened Concrete ************************************************************************** NOTE: The first Tailoring Option is for "Cylinders/Beams" and the second option is for "Beams". ************************************************************************** Install dowels in hardened concrete by bonding the dowels into holes drilled into the hardened concrete. The concrete shall have cured for 7 days or reached a minimum [flexural strength of 450 psi] before drilling commences. Holes 1/8 inch greater in diameter than the dowels shall be drilled into the hardened concrete using rotary-core drills. Rotary-percussion drills may be used, provided that excessive spalling does not occur to the concrete joint face. Continuing damage shall require modification of the equipment and operation. Depth of dowel hole shall be within a tolerance of plus/minus 1/2 inch of the dimension shown on the drawings. Upon completion of the drilling operation, the dowel hole shall URS FOR EQM SECTION 32 13 11 Page 56 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 be blown out with oil-free, compressed air. Dowels shall be bonded in the drilled holes using epoxy resin. Epoxy resin shall be injected at the back of the hole before installing the dowel and extruded to the collar during insertion of the dowel so as to completely fill the void around the dowel. Application by buttering the dowel will not be permitted. The dowels shall be held in alignment at the collar of the hole, after insertion and before the grout hardens, by means of a suitable metal or plastic grout retention ring fitted around the dowel. Dowels required to be installed in any joints between new and existing concrete shall be grouted in holes drilled in the existing concrete, all as specified above. [Where tie bars are required in longitudinal construction joints of slipform pavement, bent tie bars shall be installed at the paver, in front of the transverse screed or extrusion plate. Tie bars shall not be installed in preformed holes. A standard keyway shall be constructed, and the bent tie bars shall be inserted into the plastic concrete through a 26 gauge thick metal keyway liner. The keyway liner shall be protected and shall remain in place and become part of the joint. When bending tie bars, the radius of bend shall not be less than the minimum recommended for the particular grade of steel in the appropriate material standard. Before placement of the adjoining paving lane, the tie bars shall be straightened, using procedures which will not spall the concrete around the bar.] 3.5.8.4 Lubricating Dowel Bars The portion of each dowel intended to move within the concrete or expansion cap shall be wiped clean and coated with a thin, even film of lubricating oil or light grease before the concrete is placed. 3.6 FINISHING ************************************************************************** NOTE: Edit bracketed items as appropriate. Retain slipform paving subparagraph except when it is prohibited elsewhere. Delete Other Types of Finishing Equipment here and in PART 2, if not wanted. Hand finishing is to be allowed only for isolated, small, odd-shaped slabs or places inaccessible to the paver. ************************************************************************** Finishing operations shall be a continuing part of placing operations starting immediately behind the strike-off of the paver. Initial finishing shall be provided by the transverse screed or extrusion plate. The sequence of operations shall be transverse finishing, longitudinal machine floating if used, straightedge finishing, texturing, and then edging of joints. Finishing shall be by the machine method. The hand method shall be used only on isolated areas of odd slab widths or shapes and in the event of a breakdown of the mechanical finishing equipment. Supplemental hand finishing for machine finished pavement shall be kept to an absolute minimum. Any machine finishing operation which requires appreciable hand finishing, other than a moderate amount of straightedge finishing, shall be immediately stopped and proper adjustments made or the equipment replaced. Any operations which produce more than 1/8 inch of mortar-rich surface (defined as deficient in plus U.S. No. 4 sieve size aggregate) shall be halted immediately and the equipment, mixture, or procedures modified as necessary. Compensation shall be made for surging behind the screeds or extrusion plate and settlement during hardening and care shall be taken to ensure that paving and finishing machines are properly adjusted so that the finished surface of the concrete (not just the cutting edges of the URS FOR EQM SECTION 32 13 11 Page 57 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 screeds) will be at the required line and grade. Finishing equipment and tools shall be maintained clean and in an approved condition. At no time shall water be added to the surface of the slab with the finishing equipment or tools, or in any other way, except for fog (mist) sprays specified to prevent plastic shrinkage cracking. 3.6.1 Machine Finishing With Fixed Forms The machine shall be designed to straddle the forms and shall be operated to screed and consolidate the concrete. Machines that cause displacement of the forms shall be replaced. The machine shall make only one pass over each area of pavement. If the equipment and procedures do not produce a surface of uniform texture, true to grade, in one pass, the operation shall be immediately stopped and the equipment, mixture, and procedures adjusted as necessary. 3.6.2 Machine Finishing with Slipform Pavers The slipform paver shall be operated so that only a very minimum of additional finishing work is required to produce pavement surfaces and edges meeting the specified tolerances. Any equipment or procedure that fails to meet these specified requirements shall immediately be replaced or modified as necessary. A self-propelled nonrotating pipe float may be used while the concrete is still plastic, to remove minor irregularities and score marks. Only one pass of the pipe float shall be allowed. If there is concrete slurry or fluid paste on the surface that runs over the edge of the pavement, the paving operation shall be immediately stopped and the equipment, mixture, or operation modified to prevent formation of such slurry. Any slurry which does run down the vertical edges shall be immediately removed by hand, using stiff brushes or scrapers. No slurry, concrete or concrete mortar shall be used to build up along the edges of the pavement to compensate for excessive edge slump, either while the concrete is plastic or after it hardens. 3.6.3 Surface Correction and Testing After all other finishing is completed but while the concrete is still plastic, minor irregularities and score marks in the pavement surface shall be eliminated by means of cutting straightedges. Such straightedges shall be 12 feet in length and shall be operated from the sides of the pavement and from bridges. A straightedge operated from the side of the pavement shall be equipped with a handle 3 feet longer than one-half the width of the pavement. The surface shall then be tested for trueness with a straightedge held in successive positions parallel and at right angles to the center line of the pavement, and the whole area covered as necessary to detect variations. The straightedge shall be advanced along the pavement in successive stages of not more than one-half the length of the straightedge. Depressions shall be immediately filled with freshly mixed concrete, struck off, consolidated with an internal vibrator, and refinished. Projections above the required elevation shall also be struck off and refinished. The straightedge testing and finishing shall continue until the entire surface of the concrete is free from observable departure from the straightedge and conforms to the surface requirements specified in paragraph: ACCEPTABILITY OF WORK in PART 1. This straightedging shall not be used as a replacement for the straightedge testing of paragraph: Surface Smoothness in PART 1. Long-handled, flat bull floats shall be used very sparingly and only as necessary to correct minor, scattered surface defects. If frequent use of bull floats is necessary, the paving operation shall be stopped and the equipment, mixture or procedures adjusted to URS FOR EQM SECTION 32 13 11 Page 58 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 eliminate the surface defects. Finishing with hand floats and trowels shall be held to the absolute minimum necessary. Extreme care shall be taken to prevent overfinishing joints and edges. The surface finish of the pavement shall be produced essentially by the finishing machine and not by subsequent hand finishing operations. All hand finishing operations shall be subject to approval and shall be modified when directed. 3.6.4 Hand Finishing Use hand finishing operations only as specified below. 3.6.4.1 Equipment and Template In addition to approved mechanical internal vibrators for consolidating the concrete, provide a strike-off and tamping template and a longitudinal float for hand finishing. The template shall be at least 1 foot longer than the width of pavement being finished, of an approved design, and sufficiently rigid to retain its shape, and shall be constructed of metal or other suitable material shod with metal. The longitudinal float shall be at least 10 feet long, of approved design, and rigid and substantially braced, and shall maintain a plane surface on the bottom. Grate tampers (jitterbugs) shall not be used. 3.6.4.2 Finishing and Floating As soon as placed and vibrated, the concrete shall be struck off and screeded to the crown and cross section and to such elevation above grade that when consolidated and finished, the surface of the pavement will be at the required elevation. In addition to previously specified complete coverage with handheld immersion vibrators, the entire surface shall be tamped with the strike-off and tamping template, and the tamping operation continued until the required compaction and reduction of internal and surface voids are accomplished. Immediately following the final tamping of the surface, the pavement shall be floated longitudinally from bridges resting on the side forms and spanning but not touching the concrete. If necessary, additional concrete shall be placed, consolidated and screeded, and the float operated until a satisfactory surface has been produced. The floating operation shall be advanced not more than half the length of the float and then continued over the new and previously floated surfaces. 3.6.5 Texturing ************************************************************************** NOTE: Designer must select type of texturing desired, retain that subparagraph, and delete the others. A genuine effort should be made to determine the type of texturing, if any, desired by the using service. If no guidance is given, the usual default method should be burlap drag. If other than a burlap drag textured finish is required, edit the appropriate paragraph(s) as shown below. For Air Force airfield paving projects, do not specify artificial turf, wire comb, or surface grooving textures. For Navy airfield paving projects, do not specify wire comb or surface grooving textures. Use Section 32 01 26.71 GROOVING FOR AIRFIELD PAVEMENTS, to specify saw-cut grooves. URS FOR EQM SECTION 32 13 11 Page 59 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Spring tine grooving is limited to use on roads and streets only. ************************************************************************** Before the surface sheen has disappeared and before the concrete hardens or curing compound is applied, the surface of the pavement shall be given a texture as described herein. After curing is complete, all textured surfaces shall be thoroughly power broomed to remove all debris. 3.6.5.1 Burlap Drag Surface Surface texture shall be applied by dragging the surface of the pavement, in the direction of the concrete placement, with an approved burlap drag. The drag shall be operated with the fabric moist, and the fabric shall be cleaned or changed as required to keep clean. The dragging shall be done so as to produce a uniform finished surface having a fine sandy texture without disfiguring marks. 3.6.5.2 Artificial Turf Drag Surface Artificial turf texture shall be applied by dragging the surface of the pavement in the direction of concrete placement with an approved full-width drag made with artificial turf. 3.6.5.3 Broom Texturing Brooming should be completed before the concrete has hardened to the point where the surface will be unduly torn or roughened, but after hardening has progressed enough so that the mortar will not flow and reduce the sharpness of the scores. Successive passes of the broom shall be overlapped the minimum necessary to obtain a uniformly textured surface. Brooms shall be washed thoroughly at frequent intervals during use. Worn or damaged brooms shall be removed from the job site. Hand brooming will be permitted only on isolated odd shaped slabs or slabs where hand finishing is permitted. For hand brooming, the brooms shall have handles longer than half the width of slab to be finished. The hand brooms shall be drawn transversely across the surface from the center line to each edge with slight overlapping strokes. 3.6.5.4 Wire-Comb Texturing Surface texture shall be applied using an approved mechanical wire comb drag operated to comb the surface transverse to the pavement center line. The comb shall be capable of traversing the full width of the pavement in a single pass at a uniform speed and with a uniform pressure. Successive passes of the comb shall be overlapped the minimum necessary to obtain a continuous and uniformly textured surface. Texturing shall be completed before the concrete has hardened to the point where the surface and edges will be unduly torn, but after hardening has progressed to the point where the serrations will not close up. The serrations shall be 1/16 to 3/16 inch deep, 1/16 to 1/8 inch wide, and spaced 3/8 inch apart. Transverse texturing shall produce grooves in straight lines across each lane within a tolerance of plus or minus 1/2 inch of a true line. Surface Grooving The areas indicated on the drawings shall be grooved with a spring tine drag producing individual grooves 1/4 inch deep and 1/4 inch wide at a spacing between groove centerlines of 1-1/2 inches. These grooves shall be URS FOR EQM SECTION 32 13 11 Page 60 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 cut perpendicular to the centerline. Before grooving begins, the concrete shall be allowed to attain sufficient strength to prevent aggregate spalling. Grooves shall not be cut within 6 inches of a runway centerline, transverse joint, or crack; and they shall not be cut through neoprene compression seals. Transverse texturing shall produce grooves in straight lines across each lane within a tolerance of plus or minus 1/2 inch of a true line. 3.6.6 Edging After texturing has been completed, the edge of the slabs along the forms, along the edges of slipformed lanes, and at the joints shall be carefully finished with an edging tool to form a smooth rounded surface of 1/8 inch radius. Tool marks shall be eliminated, and the edges shall be smooth and true to line. No water shall be added to the surface during edging. Extreme care shall be taken to prevent overworking the concrete. 3.6.7 Outlets in Pavement Recesses for the tie-down anchors, lighting fixtures, and other the pavement shall be constructed to conform to the details and shown. The concrete in these areas shall be carefully finished a surface of the same texture as the surrounding area that will the requirements for plan grade and surface smoothness. 3.7 outlets in dimensions to provide be within CURING ************************************************************************** NOTE: Retain bracketed item at end of first paragraph mandating 24 hour moist cure only where locally required and only where approved by the using service. Membrane curing should be the first choice of curing methods. ************************************************************************** 3.7.1 Protection of Concrete Concrete shall be continuously protected against loss of moisture and rapid temperature changes for at least 7 days from the completion of finishing operations. All equipment needed for adequate curing and protection of the concrete shall be on hand and ready for use before actual concrete placement begins. If any selected method of curing does not afford the proper curing and protection against concrete cracking, the damaged pavement shall be removed and replaced, and another method of curing shall be employed as directed. Curing shall be accomplished by one of the following methods [except that only moist curing shall be used for the first 24 hours]. 3.7.2 Membrane Curing ************************************************************************** NOTE: The first Tailoring Option is for Army and Air Force jobs; the second option is for Navy projects only. ************************************************************************** A uniform coating of white-pigmented, membrane-forming, curing compound shall be applied to the entire exposed surface of the concrete as soon as the free water has disappeared from the surface after [finishing] [moist URS FOR EQM SECTION 32 13 11 Page 61 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 curing ceases]. Along the formed edge faces, it shall be applied immediately after the forms are removed. Concrete shall not be allowed to dry before the application of the membrane. If any drying has occurred, the surface of the concrete shall be moistened with a fine spray of water, and the curing compound applied as soon as the free water disappears. The curing compound shall be applied to the finished surfaces by means of an approved automatic spraying machine. [ The curing compound shall be applied with an overlapping coverage that will give a two-coat application at a coverage of 400 square feet per gallon, plus or minus 5.0 percent for each coat. A one-coat application may be applied provided a uniform application and coverage of 200 square feet per gallon, plus or minus 5.0 percent is obtained.] The application of curing compound by hand-operated, mechanical powered pressure sprayers will be permitted only on odd widths or shapes of slabs and on concrete surfaces exposed by the removal of forms. When the application is made by hand-operated sprayers, a second coat shall be applied in a direction approximately at right angles to the direction of the first coat. If pinholes, abrasions, or other discontinuities exist, an additional coat shall be applied to the affected areas within 30 minutes. Concrete surfaces that are subjected to heavy rainfall within 3 hours after the curing compound has been applied shall be resprayed by the method and at the coverage specified above. Areas where the curing compound is damaged by subsequent construction operations within the curing period shall be immediately resprayed. Concrete surfaces to which membrane-curing compounds have been applied shall be adequately protected during the entire curing period from pedestrian and vehicular traffic, except as required for joint-sawing operations and surface tests, and from any other possible damage to the continuity of the membrane. 3.7.3 Moist Curing ************************************************************************** NOTE: For OCONUS projects using Silica Fume, specify a minimum 24-hour moist cure before applying membrane curing compound. ************************************************************************** Concrete to be moist-cured shall be maintained continuously wet for the entire curing period, or until curing compound is applied, commencing immediately after finishing. If forms are removed before the end of the curing period, curing shall be carried out as on unformed surfaces, using suitable materials. Surfaces shall be cured by ponding, by continuous sprinkling, by continuously saturated burlap or cotton mats, or by continuously saturated plastic coated burlap. Burlap and mats shall be clean and free from any contamination and shall be completely saturated before being placed on the concrete. Lap sheets to provide full coverage. Provide an approved work system to ensure that moist curing is continuous 24 hours per day and that the entire surface is wet. 3.8 JOINTS ************************************************************************** NOTE: Edit bracketed items in following subparagraphs to conform to design requirements. Even if not required, dowels should be permitted for construction joints. The effect of tie bars on the pavement action and potential cracking should be analyzed before requiring or permitting their use. Remove joint types not required in the project. ************************************************************************** URS FOR EQM SECTION 32 13 11 Page 62 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.8.1 TYMX989345A FA3002-09-D-0002 TG02 General Requirements for Joints Joints shall conform to the locations and details indicated and shall be perpendicular to the finished grade of the pavement. All joints shall be straight and continuous from edge to edge or end to end of the pavement with no abrupt offset and no gradual deviation greater than 1/2 inch. Where any joint fails to meet these tolerances, the slabs adjacent to the joint shall be removed and replaced at no additional cost to the Government. No change from the jointing pattern shown on the drawings shall be made without written approval of the Contracting Officer. Joints shall be sealed immediately following curing of the concrete or as soon thereafter as weather conditions permit. Joints shall be sealed as specified in Section [32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS] [32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS]. 3.8.2 Longitudinal Construction Joints Dowels [or keys] [or tie bars] shall be installed in the longitudinal construction joints, or the edges shall be thickened as indicated. [Dowels] [Tie bars] shall be installed as specified above. [If any length of completed keyway of 5 feet or more fails to meet the previously specified tolerances, dowels shall be installed in that part of the joint by drilling holes in the hardened concrete and grouting the dowels in place with epoxy resin.]After the end of the curing period, longitudinal construction joints shall be sawed to provide a groove at the top for sealant conforming to the details and dimensions indicated. 3.8.3 Transverse Construction Joints Transverse construction joints shall be installed at the end of each day's placing operations and at any other points within a paving lane when concrete placement is interrupted for 30 minutes or longer. The transverse construction joint shall be installed at a planned transverse joint. Transverse construction joints shall be constructed by utilizing headers or by paving through the joint, then full-depth sawcutting the excess concrete. Pavement shall be constructed with the paver as close to the header as possible, and the paver shall be run out completely past the header. Transverse construction joints installed at a planned transverse joint shall be constructed as shown or, if not shown otherwise, shall be dowelled in accordance with paragraph: Dowels Installed in Hardened Concrete, or paragraph: Fixed Form Paving above. 3.8.4 Expansion Joints Expansion joints shall be formed where indicated, and about any structures and features that project through or into the pavement, using joint filler of the type, thickness, and width indicated, and shall be installed to form a complete, uniform separation between the structure and the pavement. The filler shall be attached to the original concrete placement with adhesive or other fasteners and shall extend the full slab depth. After placement and curing of the adjacent slab, sawcut the sealant reservior depth from the filler. Adjacent sections of filler shall be fitted tightly together, and the filler shall extend across the full width of the paving lane or other complete distance in order to prevent entrance of concrete into the expansion space. Edges of the concrete at the joint face shall be finished with an edger with a radius of 1/8 inch. URS FOR EQM SECTION 32 13 11 Page 63 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.8.5 TYMX989345A FA3002-09-D-0002 TG02 Slip Joints Slip joints shall be installed where indicated using the specified materials. Preformed joint filler material shall be attached to the face of the original concrete placement with adhesive or other fasteners. A 3/4 inch deep reservoir for joint sealant shall be constructed at the top of the joint. Edges of the joint face shall be finished with an edger with a radius of 1/8 inch. 3.8.6 Contraction Joints Construct transverse and longitudinal contraction joints by sawing an initial groove in the concrete with a 1/8 inch blade to the indicated depth. During sawing of joints, and again 24 hours later, the CQC team shall inspect all exposed lane edges for development of cracks below the saw cut, and shall immediately report results to the Contracting Officer. If the Contracting Officer determines that there are more uncracked joints than desired, the Contractor will be directed to saw succeeding joints 25 percent deeper than originally indicated at no additional cost to the Government. The time of initial sawing shall vary depending on existing and anticipated weather conditions and shall be such as to prevent uncontrolled cracking of the pavement. Sawing of the joints shall commence as soon as the concrete has hardened sufficiently to permit cutting the concrete without chipping, spalling, or tearing. The sawed faces of joints will be inspected for undercutting or washing of the concrete due to the early sawing, and sawing shall be delayed if undercutting is sufficiently deep to cause structural weakness or excessive roughness in the joint. The sawing operation shall be carried on as required during both day and night regardless of weather conditions. The joints shall be sawed at the required spacing consecutively in the sequence of the concrete placement. Adequate lighting shall be provided for night work. Illumination using vehicle headlights will not be permitted. A chalk line or other suitable guide shall be used to mark the alignment of the joint. Before sawing a joint, the concrete shall be examined closely for cracks, and the joint shall not be sawed if a crack has occurred near the planned joint location. Sawing shall be discontinued when a crack develops ahead of the saw cut. Immediately after the joint is sawed, the saw cut and adjacent concrete surface shall be thoroughly flushed with water and vacuumed until all waste from sawing is removed from the joint and adjacent concrete surface. The surface shall be resprayed with curing compound as soon as free water disappears. Necessary precautions shall be taken to insure that the concrete is properly protected from damage and cured at sawed joints. The top of the joint opening and the joint groove at exposed edges shall be tightly sealed with cord backer rod before the concrete in the region of the joint is resprayed with curing compound, and shall be maintained until removed immediately before sawing the joint sealant reservoir. The exposed saw cuts on the faces of pilot lanes shall be sealed with bituminous mastic or masking tape. After expiration of the curing period, the upper portion of the groove shall be widened by sawing with ganged diamond saw blades to the width and depth indicated for the joint sealer. The reservoir shall be centered over the initial sawcut. 3.8.7 Thickened Edge Joints Construct thickened edge joints as indicated on the drawings. Underlying material in the transition area shall be graded as shown and shall meet the requirements for smoothness and compaction specified for all other areas of the underlying material. URS FOR EQM SECTION 32 13 11 Page 64 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.9 3.9.1 TYMX989345A FA3002-09-D-0002 TG02 REPAIR, REMOVAL AND REPLACEMENT OF NEWLY CONSTRUCTED SLABS General Criteria New pavement slabs that are broken, have spalled edges, or contain cracks shall be removed and replaced or repaired, as specified at no cost to the Government. Removal of partial slabs is not permitted. Not more than 15.0 percent of each slab's longitudinal joint edge shall be spalled. Prior to fill-in lane placement, pilot lane slabs with spalls exceeding this quantity, regardless of spall size, shall be sawn full depth to remove the spalled face. All other slabs shall be removed, as directed. The Contracting Officer will determine whether cracks extend full depth of the pavement and may require cores to be drilled on the crack to determine depth of cracking. Such cores shall be at least 6 inch diameter, and shall be drilled and backfilled with an approved non-shrink concrete. Perform drilling of cores and refilling holes at no expense to the Government. 3.9.2 Slabs with Cracks Clean cracks that do not exceed 2 inches in depth; then pressure injected full depth with epoxy resin, Type IV, Grade 1. Remove slabs containing cracks deeper than 2 inches. 3.9.3 Removal and Replacement of Full Slabs Where it is necessary to remove full slabs, removal shall be in accordance with paragraph: Removal of Existing Pavement Slab below. Removal and replacement shall be full depth, by full width of the slab, and the limit of removal shall be normal to the paving lane and extend to each original joint. Dowels of the size and spacing as specified for other joints in similar pavement shall be installed by epoxy grouting them into holes drilled into the existing concrete using procedures as specified in paragraph PLACING DOWELS[ AND TIE BARS], above. Original damaged dowels[ or tie bars] shall be cut off flush with the joint face. Protruding portions of dowels shall be painted and lightly oiled. All four edges of the new slab shall thus contain dowels. Placement of concrete shall be as specified for original construction. Prior to placement of new concrete, the underlying material shall be recompacted and shaped as specified in the appropriate section of these specifications, and the surfaces of all four joint faces shall be cleaned of all loose material and contaminants and coated with a double application of membrane forming curing compound as bond breaker. Care shall be taken to prevent any curing compound from contacting dowels[ or tie bars]. The resulting joints around the new slab shall be prepared and sealed as specified for original construction. 3.9.4 Repairing Spalls Along Joints Where directed, spalls along joints of new slabs, along edges of adjacent existing concrete, and along parallel cracks shall be repaired by first making a vertical saw cut at least 1 inch outside the spalled area and to a depth of at least 2 inches. Saw cuts shall be straight lines forming rectangular areas. The concrete between the saw cut and the joint, or crack, shall be chipped out to remove all unsound concrete and into at least 1/2 inch of visually sound concrete. Spalls along joints to be sealed with compression seals shall be sawn, chipped out, and repaired to a depth to restore the full joint-face support. The cavity thus formed shall be thoroughly cleaned with high pressure water jets supplemented with oil-free compressed air to remove all loose material. Immediately before filling the cavity, a prime coat shall be applied to the dry cleaned surface of all URS FOR EQM SECTION 32 13 11 Page 65 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 sides and bottom of the cavity, except any joint face. The prime coat shall be applied in a thin coating and scrubbed into the surface with a stiff-bristle brush. Prime coat for portland cement repairs shall be a neat cement grout and for epoxy resin repairs shall be epoxy resin, Type III, Grade 1. The prepared cavity shall be filled with: Portland cement concrete or latex modified mortar for larger cavities, those more than 1/3 cu. ft. in size after removal operations; Portland cement mortar for cavities between 0.03 cu. ft. and 1/3 cu. ft.; and epoxy resin mortar or epoxy resin or latex modified mortar for those cavities less than 0.03 cu. ft. in size. Portland cement concretes and mortars shall be very low slump mixtures, 1/2 inch slump or less, proportioned, mixed, placed, consolidated by tamping, and cured, all as directed. Epoxy resin mortars shall be made with Type III, Grade 1, epoxy resin, using proportions and mixing and placing procedures as recommended by the manufacturer and approved by the Contracting Officer. Proprietary patching materials may be used, subject to approval by the Contracting Officer. The epoxy resin materials shall be placed in the cavity in layers not over 2 inches thick. The time interval between placement of additional layers shall be such that the temperature of the epoxy resin material does not exceed 140 degrees F at any time during hardening. Mechanical vibrators and hand tampers shall be used to consolidate the concrete or mortar. Any repair material on the surrounding surfaces of the existing concrete shall be removed before it hardens. Where the spalled area abuts a joint, an insert or other bond-breaking medium shall be used to prevent bond at the joint face. A reservoir for the joint sealant shall be sawed to the dimensions required for other joints. The reservoir shall be thoroughly cleaned and then sealed with the sealer specified for the joints. [In lieu of sawing, spalls not adjacent to joints and popouts, both less than 6 inches in maximum dimension, may be prepared by drilling a core 2 inches in diameter greater than the size of the defect, centered over the defect, and 2 inches deep or 1/2 inch into sound concrete, whichever is greater. The core hole shall be repaired as specified above for other spalls.] 3.9.5 Repair of Weak Surfaces Weak surfaces are defined as mortar-rich, rain-damaged, uncured, or containing exposed voids or deleterious materials. Diamond grind slabs containing weak surfaces less than 1/4 inch thick to remove the weak surface. Diamond grinding shall be in accordance with paragraph DIAMOND GRINDING OF PCC SURFACES in PART 1. All ground areas shall meet the thickness, smoothness and grade criteria of paragraph ACCEPTANCE REQUIREMENTS in PART 1. Remove and replace slabs containing weak surfaces greater than 1/4 inch thick. 3.9.6 Repair of Pilot Lane Vertical Faces Excessive edge slump and joint face deformation shall be repaired in accordance with paragraph EDGE SLUMP AND JOINT FACE DEFORMATION in PART 1. Inadequate consolidation (honeycombing or air voids) shall be repaired by saw cutting the face full depth along the entire lane length with a diamond blade. Obtain cores, as directed, to determine the depth of removal. 3.10 EXISTING CONCRETE PAVEMENT REMOVAL AND REPAIR ************************************************************************** NOTE: It is imperative that sufficient exploration be made (not just reference to as-built drawings) for the designer to know exactly what the in-place existing pavement thickness and load-transfer are at URS FOR EQM SECTION 32 13 11 Page 66 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the jointing area--dowels, keys, tie bars, etc--and its condition. Normally, the joint between the new pavement and existing pavement should be made at an existing joint in the old pavement. Coordinate with Section 02 41 00 DEMOLITION. ************************************************************************** Existing concrete pavement shall be removed at locations indicated on the drawings. Prior to commencing pavement removal operations, inventory the pavement distresses (cracks, spalls, and corner breaks) along the pavement edge to remain. After pavement removal, the remaining edge shall again be surveyed to quantify any damage caused by Contractor's removal operations. Perform both surveys in the presence of the Contracting Officer. Repairs shall be made as indicated and as specified herein. All operations shall be carefully controlled to prevent damage to the concrete pavement and to the underlying material to remain in place. All saw cuts shall be made perpendicular to the slab surface, forming rectangular areas. 3.10.1 Removal of Existing Pavement Slab ************************************************************************** NOTE: The saw cut at a distance from the joint should be sawed with a wheel saw which produces a 38 mm (1-1/2 inch) or wider kerf and better prevents stress from propagating across the saw cut. Specify wheel saw for Army and Air Force projects. Specify diamond saw for Navy projects. ************************************************************************** When existing concrete pavement is to be removed and adjacent concrete is to be left in place, the joint between the removal area and adjoining pavement to stay in place shall first be cut full depth with a standard diamond-type concrete saw. Next, a full depth saw cut shall be made parallel to the joint at least 24 inches from the joint and at least 6 inches from the end of any dowels. This saw cut shall be made with a [ wheel saw] [diamond saw] as specified in paragraph: Sawing Equipment. All pavement to be removed beyond this last saw cut shall be removed in accordance with the approved demolition work plan. All pavement between this last saw cut and the joint line shall be removed by carefully pulling pieces and blocks away from the joint face with suitable equipment and then picking them up for removal. In lieu of this method, this strip of concrete may be carefully broken up and removed using hand-held jackhammers, 30 lb or less, or other approved light-duty equipment which will not cause stress to propagate across the joint saw cut and cause distress in the pavement which is to remain in place. In lieu of the above specified removal method, the slab may be sawcut full depth to divide it into several pieces and each piece lifted out and removed. Suitable equipment shall be used to provide a truly vertical lift, and safe lifting devices used for attachment to the slab. 3.10.2 Edge Repair The edge of existing concrete pavement against which new pavement abuts shall be protected from damage at all times. Slabs which are damaged during construction shall be removed and replaced as directed by the Contracting Officer at no cost to the Government. Repair of previously existing damage areas will be considered a subsidiary part of concrete pavement construction. All exposed keys and keyways shall be sawn off full depth. URS FOR EQM SECTION 32 13 11 Page 67 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.10.2.1 TYMX989345A FA3002-09-D-0002 TG02 Spall Repair Not more than 15.0 percent of each slab's edge shall be spalled as a result of the Contractor's actions. Unless otherwise directed by the Contracting Officer, damaged slabs with spalls exceeding this quantity, regardless of spall size, shall be sawn full depth on the exposed face to remove the spalled face. Repair materials and procedures shall be as previously specified in paragraph: Repairing Spalls Along Joints. 3.10.2.2 Underbreak and Underlying Material All underbreak shall be repaired by removal and replacement of the damaged slabs in accordance with paragraph: Removal and Replacement of Full Slabs above. The underlying material adjacent to the edge of and under the existing pavement which is to remain in place shall be protected from damage or disturbance during removal operations and until placement of new concrete, and shall be shaped as shown on the drawings or as directed. Sufficient underlying material shall be kept in place outside the joint line to completely prevent disturbance of material under the pavement which is to remain in place. Any material under the portion of the concrete pavement to remain in place which is disturbed or loses its compaction shall be carefully removed and replaced with concrete. 3.11 PAVEMENT PROTECTION Protect the pavement against all damage prior to final acceptance of the work by the Government. Aggregates, rubble, or other similar construction materials shall not be placed on airfield pavements. Traffic shall be excluded from the new pavement by erecting and maintaining barricades and signs until the concrete is at least 14 days old, or for a longer period if so directed. As a construction expedient in paving intermediate lanes between newly paved pilot lanes, operation of the hauling and paving equipment will be permitted on the new pavement after the pavement has been cured for 7 days and the joints have been sealed or otherwise protected, the concrete has attained a minimum field cured flexural strength of 550 psi. and approved means are furnished to prevent damage to the slab edge. All new and existing pavement carrying construction traffic or equipment shall be continuously kept completely clean, and spillage of concrete or other materials shall be cleaned up immediately upon occurrence. Special care shall be used where Contractor's traffic uses or crosses active airfield pavement. Power broom other existing pavements at least daily when traffic operates. For fill-in lanes, equipment shall be used that will not damage or spall the edges or joints of the previously constructed pavement. 3.12 3.12.1 TESTING AND INSPECTION FOR CONTRACTOR QUALITY CONTROL Testing and Inspection by Contractor During construction, the Contractor is responsible for sampling and testing aggregates, cementitious materials (cement, GGBF and pozzolan), and concrete to determine compliance with the specifications. Provide facilities and labor as may be necessary for procurement of representative test samples. Furnish sampling platforms and belt templates to obtain representative samples of aggregates from charging belts at the concrete plant. Samples of concrete shall be obtained at the point of delivery to the paver. Testing by the Government will in no way relieve the Contractor of the specified testing requirements. Perform the inspection and tests described below, and based upon the results of these inspections and tests, URS FOR EQM SECTION 32 13 11 Page 68 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 take the action required and submit reports as required. This testing shall be performed regardless of any other testing performed by the Government, either for pay adjustment purposes or for any other reason. 3.12.2 Testing and Inspection Requirements Contractor CQC sampling, testing, inspection and reporting shall be in accordance with the following Table. Frequency TABLE 6 CONTRACTOR TESTING AND INSPECTION REQUIREMENTS Test Method Control Limit Corrective Action Fine Aggregate Gradation and Fineness Modulus 2 per lot ASTM C136 sample at belt 9 of 10 tests vary <0.15 from average Outside limits on any sieve 2nd failure Retest Stop, repair, retest Coarse Aggregate Gradation 2 per lot ASTM C136 sample at belt Outside limits on any sieve 2nd failure Retest 2 consecutive avgs of 5 tests out report to COR, stop ops, repair, retest report to COR, correct Workability Factor and Coarseness Factor Computation Same as C.A. and F.A. see paragraph AGGREGATES Use individual C.A. and F.A. gradations. Combine using batch ticket percentages. Tolerances: +/- 3 points on WF; +/- 5 points on CF from approved mix design values Check batching tolerances, recalibrate scales Aggregate Deleterious, Quality, and ASR Tests Every [30 ][60] days see paragraph AGGREGATES Stop production, retest, replace aggregate. Increase testing interval to 90 days if previous 2 tests pass Plant - Scales, Weighing Accuracy Monthly URS FOR EQM NRMCA QC 3 Stop plant ops, repair, recalibrate SECTION 32 13 11 Page 69 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS Frequency TYMX989345A FA3002-09-D-0002 TG02 TABLE 6 CONTRACTOR TESTING AND INSPECTION REQUIREMENTS Test Method Control Limit Corrective Action Plant - Batching and Recording Accuracy Weekly Record/Report Record Stop plant ops, required/recorded/actuarepair, recalibrate batch mass Plant - Batch Plant Control Every lot Record/Report Record type/amt of each material per lot Plant - Mixer Uniformity - Stationary Mixers Every 4 months during paving COE CRD-C 55 After initial approval, use abbreviated method Increase mixing time, change batching sequence, reduce batch size to bring into compliance. Retest Plant - Mixer Uniformity - Truck Mixers Every 4 months during paving ASTM C94/C94M Random selection of truck. Increase mixing time, change batching sequence, reduce batch size to bring into compliance. Retest Concrete Mixture - Air Content When test specimens prepared + 2 random ASTM C231/C231M Individual test sample at control chart: paving site Warning +/-1.0 Individual test control chart: Action +/-1.5 Range between 2 consecutive tests: Warning +2.0 Range between 2 consecutive tests: Action +3.0 Concrete Mixture - Unit Weight and Yield Adjust AEA, retest Same as ASTM C138/C138M Individual test Air Content sample at basis: Warning Yield paving site -0/+1 percent Individual test basis: Action Yield -0/+5 percent Concrete Mixture - Slump Check batching tolerances URS FOR EQM SECTION 32 13 11 Page 70 Halt operations, repair, retest Recalibrate AEA dispenser Halt operations, repair, retest Halt operations 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Frequency TABLE 6 CONTRACTOR TESTING AND INSPECTION REQUIREMENTS Test Method Control Limit Corrective Action When test specimens prepared + 4 random ASTM C143/C143M Individual test sample at control chart: Upper paving site Warning - 1/2 inch below max Individual test control chart: Upper Action - maximum allowable slump Range between each consecutive test: 1-1/2 inches Concrete Mixture - Temperature Adjust batch masses within max W/C ratio Stop operations, adjust, retest Stop operations, repair, retest When test ASTM C1064/C1064See paragraph WEATHER LIMITATIONS specimens sample at prepared paving site Concrete Mixture - Strength 8 per lot ASTM C31/C31M See paragraph CONCRETE STRENGTH TESTING for sample at CQC paving station Paving - Inspection Before Paving Prior to each paving operation Report Inspect underlying materials, construction joint faces, forms, reinforcing, dowels, and embedded items Paving - Inspection During Paving During paving operation Monitor and control paving operation, including placement, consolidation, finishing, texturing, curing, and joint sawing. Paving - Vibrators Weekly during paving COE CRD-C 521 Test frequency (in concrete), and amplitude (in air), measure at tip/head and average. Repair or replace defective vibrators. Moist Curing URS FOR EQM SECTION 32 13 11 Page 71 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS Frequency TYMX989345A FA3002-09-D-0002 TG02 TABLE 6 CONTRACTOR TESTING AND INSPECTION REQUIREMENTS Test Method Control Limit Corrective Action 2 per lot, Visual min 4 per day Membrane Compound Curing Daily Visual Repair defects, extend curing by 1 day Calculate coverage Respray areas where based on quantity/area coverage defective. Recalibrate equipment Cold Weather Protection Once per day 3.12.3 Visual Repair defects, report conditions to COR Concrete Strength Testing for Contractor CQC ************************************************************************** NOTE: If paragraph: Flexural Strength and Thickness is based on 28-day flexural strength for acceptance, modify this subparagraph to match it. The first option "Cylinders/Beams" includes items a through g; the second option "Beams" includes listing a through f. ************************************************************************** Contractor Quality Control operations for concrete strength shall consist of the following steps: [ a. Take samples for strength tests at the paving site. Fabricate and cure test beams in accordance with ASTM C31/C31M; test them in accordance with ASTM C78/C78M. b. Fabricate and cure 2 test beams per sublot from the same batch or truckload and at the same time acceptance beams are fabricated and test them for flexural strength at 7-day age. c. Average all 8 flexural tests per lot. Convert this average 7-day flexural strength per lot to equivalent [28][90]-day flexural strength using the Correlation Ratio determined during mixture proportioning studies. d. Compare the equivalent [28][90]-day flexural strength from the conversion to the Average Flexural Strength Required for Mixtures from paragraph of same title. e. If the equivalent average [28][90]-day strength for the lot is below the Average Flexural Strength Required for Mixtures by 69 psi flexural strength or more, at any time, adjust the mixture to increase the strength, as approved. f. The Contractor's CQC testing agency shall maintain up-to-date control URS FOR EQM SECTION 32 13 11 Page 72 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 charts for strength, showing the 7-day CQC flexural strength and the [28 ][90]-day flexural strength (from acceptance tests) of each of these for each lot.] 3.12.4 Reports All results of tests or inspections conducted shall be reported informally as they are completed and in writing daily. Prepare a weekly report for the updating of control charts covering the entire period from the start of the construction season through the current week. During periods of cold-weather protection, make daily reports of pertinent temperatures. These requirements do not relieve the Contractor of the obligation to report certain failures immediately as required in preceding paragraphs. Such reports of failures and the action taken shall be confirmed in writing in the routine reports. The Contracting Officer has the right to examine all Contractor quality control records. -- End of Section -- URS FOR EQM SECTION 32 13 11 Page 73 65% - 01/23/2015 This Page Left Intentionally Blank REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 17 24.00 10 (April 2008) -------------------------------Preparing Activity: USACE Superseding UFGS-32 17 24.00 10 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 32 17 24.00 10 PAVEMENT MARKINGS ************************************************************************** NOTE: This guide specification covers the requirements for marking and remarking airport and heliport pavements primarily, but may also be used for marking roads, streets and parking areas; this section also includes removal of paint or tape markings from pavement surfaces. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: Pavement markings are usually removed by water blasting; few chemical methods are effective. Sand or shotblasting may be prohibited by local air pollution regulations. Drawings will show the extent of pavement to have markings removed. Removal of raised or recessed markers or reflectors is not covered in this section. ************************************************************************** 1.1 UNIT PRICES ************************************************************************** URS FOR EQM SECTION 32 17 24.00 10 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NOTE: This paragraph should be deleted when pavement marking is included in a lump sum project. ************************************************************************** 1.1.1 Measurement 1.1.1.1 Surface Preparation The unit of measurement for surface preparation will be the number of square feet of pavement surface prepared for marking and accepted by the Contracting Officer. 1.1.1.2 Pavement Striping and Markings The unit of measurement for pavement striping and markings will be the number of square feet of reflective and nonreflective striping or marking actually completed and accepted by the Contracting Officer. Raised Pavement Markers The unit of measurement for raised pavement markers will be the number of square feet of each specific color required. Payment will be for the total number actually placed and approved by the Contracting Officer. 1.1.1.3 Removal of Pavement Markings The unit of measurement for removal of pavement markings shall be the number of square feet of pavement markings actually removed and accepted by the Contracting Officer. 1.1.2 Payment The quantities of surface preparation, pavement striping or markings, raised pavement markers, and removal of pavement markings determined as specified in paragraph Measurement, will be paid for at the contract unit price. The payment will constitute full compensation for furnishing all labor, materials, tools, equipment, appliances, and doing all work involved in marking pavements. Any striping or markings which are placed without reflective media, when reflective media is required, shall be removed and replaced at no cost to the Government. Striping or markings which do not conform to the alignment and/or location required shall be removed and replaced at no cost to the Government. 1.2 REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. URS FOR EQM SECTION 32 17 24.00 10 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. U.S. GENERAL SERVICES ADMINISTRATION (GSA) FS TT-B-1325 (Rev D; Notice 1) Beads (Glass Spheres) Retro-Reflective (Metric) FS TT-P-1952 (Rev E) Paint, Traffic and Airfield Markings, Waterborne 1.3 SYSTEM DESCRIPTION All machines, tools and equipment used in the performance of the work shall be approved and maintained in satisfactory operating condition. Submit lists of proposed equipment, including descriptive data, and notifications of proposed Contractor actions as specified in this section. List of removal equipment shall include descriptive data indicating area of coverage per pass, pressure adjustment range, tank and flow capacities, and safety precautions required for the equipment operation. Equipment operating on roads and runways shall display low speed traffic markings and traffic warning lights. 1.3.1 1.3.1.1 Paint Application Equipment Self-Propelled or Mobile-Drawn Pneumatic Spraying Machines The equipment to apply paint to pavements shall be a self-propelled or mobile-drawn pneumatic spraying machine with suitable arrangements of atomizing nozzles and controls to obtain the specified results. The machine shall have a speed during application not less than 5 mph, and shall be capable of applying the stripe widths indicated, at the paint coverage rate specified in paragraph APPLICATION, and of even uniform thickness with clear-cut edges. [Equipment used for marking streets and highways shall be capable of placing the prescribed number of lines at a single pass as solid lines, intermittent lines or a combination of solid and intermittent lines using a maximum of two different colors of paint as specified.] [The equipment used to apply the paint binder to airfield pavements shall be a self-propelled or mobile-drawn pneumatic spraying machine with an arrangement of atomizing nozzles capable of applying a line width at any one time in multiples of 6 inches, from 6 inches to 36 inches]. The paint applicator shall have paint reservoirs or tanks of sufficient capacity and suitable gauges to apply paint in accordance with requirements specified. Tanks shall be equipped with suitable air-driven mechanical agitators. The spray mechanism shall be equipped with quick-action valves conveniently located, and shall include necessary pressure regulators and gauges in full view and reach of the operator. Paint strainers shall be installed in paint supply lines to ensure freedom from residue and foreign matter that may cause malfunction of the spray guns. The paint applicator shall be readily adaptable for attachment of an air-actuated dispenser for the reflective media approved for use. Pneumatic spray guns shall be URS FOR EQM SECTION 32 17 24.00 10 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 provided for hand application of paint in areas where the mobile paint applicator cannot be used. 1.3.1.2 Hand-Operated, Push-Type Machines ************************************************************************** NOTE: Where pavement marking is limited to small street and parking areas, hand-operated push-type machines may be specified in lieu of detailed equipment requirements. ************************************************************************** All machines, tools, and equipment used in performance of the work shall be approved and maintained in satisfactory operating condition. Hand-operated push-type machines of a type commonly used for application of paint to pavement surfaces will be acceptable for marking small streets and parking areas. Applicator machine shall be equipped with the necessary paint tanks and spraying nozzles, and shall be capable of applying paint uniformly at coverage specified. Sandblasting equipment shall be provided as required for cleaning surfaces to be painted. Hand-operated spray guns shall be provided for use in areas where push-type machines cannot be used. 1.3.2 Reflective Media Dispenser The dispenser for applying the reflective media shall be attached to the paint dispenser and shall operate automatically and simultaneously with the applicator through the same control mechanism. The dispenser shall be capable of adjustment and designed to provide uniform flow of reflective media over the full length and width of the stripe at the rate of coverage specified in paragraph APPLICATION, at all operating speeds of the applicator to which it is attached. 1.3.3 Surface Preparation Equipment Sandblasting Equipment Sandblasting equipment shall include an air compressor, hoses, and nozzles of proper size and capacity as required for cleaning surfaces to be painted. The compressor shall be capable of furnishing not less than 150 cfm of air at a pressure of not less than 90 psi at each nozzle used, and shall be equipped with traps that will maintain the compressed air free of oil and water. 1.3.3.1 Waterblast Equipment The water pressure shall be specified at 2600 psi at 140 degrees F in order to adequately clean the surfaces to be marked. 1.3.4 Marking Removal Equipment Equipment shall be mounted on rubber tires and shall be capable of removing markings from the pavement without damaging the pavement surface or joint sealant. Waterblasting equipment shall be capable of producing an adjustable, pressurized stream of water. Sandblasting equipment shall include an air compressor, hoses, and nozzles. The compressor shall be equipped with traps to maintain the air free of oil and water. URS FOR EQM SECTION 32 17 24.00 10 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.3.4.1 TYMX989345A FA3002-09-D-0002 TG02 Shotblasting Equipment Shotblasting equipment shall be capable of producing an adjustable depth of removal of marking and pavement. Each unit shall be self-cleaning and self-contained, shall be able to confine dust and debris from the operation, and shall be capable of recycling the abrasive for reuse. Chemical Equipment Chemical equipment shall be capable of application and removal of chemicals from the pavement surface, and shall leave only non-toxic biodegradable residue. 1.4 SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.][information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00 URS FOR EQM SECTION 32 17 24.00 10 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 SUBMITTAL PROCEDURES: SD-03 Product Data Equipment[; G][; G, [_____]] Composition Requirements Qualifications SD-06 Test Reports Sampling and Testing SD-07 Certificates Volatile Organic Compound (VOC) 1.5 QUALITY ASSURANCE 1.5.1 Qualifications Submit documentation certifying that pertinent personnel are qualified for equipment operation and handling of chemicals. Traffic Controls ************************************************************************** NOTE: Guidance for traffic control procedures can be obtained from the Manual on Uniform Traffic Control Devices (MUTCD) for Streets and Highways. ************************************************************************** Suitable warning signs shall be placed near the beginning of the worksite and well ahead of the worksite for alerting approaching traffic from both directions. Small markers shall be placed along newly painted lines or freshly placed raised markers to control traffic and prevent damage to newly painted surfaces or displacement of raised pavement markers. Painting equipment shall be marked with large warning signs indicating slow-moving painting equipment in operation. 1.5.2 1.5.2.1 Maintenance of Traffic Airfield The performance of work in the controlled zones of airfields shall be coordinated with the Contracting Officer and with the Flight Operations Officer. Verbal communications shall be maintained with the control tower before and during work in the controlled zones of the airfield. The control tower shall be advised when the work is completed. A radio for this purpose [will be provided by the Government] [shall be provided by the Contractor and approved by the Contracting Officer]. Roads, Streets, and Parking Areas When traffic must be rerouted or controlled to accomplish the work, the necessary warning signs, flagpersons, and related equipment for the safe passage of vehicles shall be provided. URS FOR EQM SECTION 32 17 24.00 10 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.6 TYMX989345A FA3002-09-D-0002 TG02 DELIVERY, STORAGE, AND HANDLING All materials shall be delivered and stored in sealed containers that plainly show the designated name, formula or specification number, batch number, color, date of manufacture, manufacturer's name, and directions, all of which shall be plainly legible at time of use. 1.7 ENVIRONMENTAL REQUIREMENTS Pavement surface shall be free of snow, ice, or slush. Surface temperature shall be at least 40 degrees F and rising at the beginning of operations, except those involving shot or sand blasting. Operation shall cease during thunderstorms. Operation shall cease during rainfall, except for waterblasting and removal of previously applied chemicals. Waterblasting shall cease where surface water accumulation alters the effectiveness of material removal. PART 2 2.1 PRODUCTS PAINT The paint shall be homogeneous, easily stirred to smooth consistency, and shall show no hard settlement or other objectionable characteristics during a storage period of 6 months. Paints for airfields, roads, parking areas, and streets shall conform to FS TT-P-1952, color as [indicated] [selected]. Pavement marking paints shall comply with applicable state and local laws enacted to ensure compliance with Federal Clean Air Standards. Paint materials shall conform to the restrictions of the local Air Pollution Control District. RAISED REFLECTIVE MARKERS ************************************************************************** NOTE: Line marker segments having a 1 to 3 ratio of stripe to gap are standard. Line segments of 3 meters (10 feet) with gaps of 9 meters (30 feet) are recommended. When raised pavement markers are used in lieu of striping, the line marker segments shall have a 3 to 5 ratio of stripe to gap with line segments of 5 meters (15 feet) with gaps of 8 meters (25 feet) recommended. ************************************************************************** Either metallic or nonmetallic markers of the button or prismatic reflector type may be used. Markers shall be of permanent colors, as specified for pavement marking, and shall retain the color and brightness under the action of traffic. Button markers shall have a diameter of not less than 4 inches, and shall be spaced not more than 40 feet apart on solid longitudinal lines. Broken centerline marker spacings shall be in segments [of [_____]] [indicated] with gaps [of [_____]] [indicated] between segments. Markers shall have rounded surfaces presenting a smooth contour to traffic and shall not project more than 3/4 inch above level of pavement. Pavement markers and adhesive epoxy shall conform to ASTM D4280. 2.2 REFLECTIVE MEDIA Reflective media for airfields shall conform to FS TT-B-1325, Type I, Gradation A. Reflective media for roads and streets shall conform to FS TT-B-1325, Type I, Gradation A or AASHTO M 247, Type I. URS FOR EQM SECTION 32 17 24.00 10 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.3 TYMX989345A FA3002-09-D-0002 TG02 SAMPLING AND TESTING ************************************************************************** NOTE: Although provision is made for obtaining test reports, importance of Government testing of each batch of paint and reflective media is emphasized where quantities of 200 or more liters (50 or more gallons) are involved. For 200 (50) or less, the factor of time and value of material versus cost of testing may justify acceptance on the basis of test reports furnished. In such cases acceptability will be determined by persons within division or district offices technically qualified and specifically designated by division engineers. Requirements in this paragraph for Contractor testing may be modified to exempt materials that definitely will be Government tested. If all batches will be Government tested, requirements for Contractor testing will be deleted. ************************************************************************** Materials proposed for use shall be stored on the project site in sealed and labeled containers, or segregated at source of supply, sufficiently in advance of needs to allow 60 days for testing. Submit certified copies of the test reports, prior to the use of the materials at the jobsite. Testing shall be performed in an approved independent laboratory. Upon notification by the Contractor that the material is at the site or source of supply, a sample shall be taken by random selection from sealed containers in the presence of the Contracting Officer. Samples shall be clearly identified by designated name, specification number, batch number, manufacturer's formulation number, project contract number, intended use, and quantity involved. [Materials will be sampled and tested by the Government. No material shall be used at the project prior to receipt by the Contractor of written notice that the materials meet the laboratory requirements. The cost of initial testing of samples from each lot of materials will be borne by the Government. If the sample fails to meet specification requirements, the material represented by the sample shall be replaced and the new material will be tested. Cost of sampling and testing the new material will be borne by the Contractor.] [Testing shall be performed in an approved independent laboratory. If materials are approved based on reports furnished by the Contractor, samples will be retained by the Government for possible future testing should the material appear defective during or after application.] PART 3 3.1 EXECUTION SURFACE PREPARATION ************************************************************************** NOTE: Newly laid flexible and rigid pavements require aging prior to painting in order to obtain satisfactory paint performance. If practicable, all new pavement surfaces should be at least 30 days old before applying paint. When earlier application of paint is necessary because of operations requirements, the maximum period practicable should be specified. ************************************************************************** URS FOR EQM SECTION 32 17 24.00 10 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Thoroughly clean surfaces to be marked before application of the pavement marking material. Dust, dirt, and other granular surface deposits shall be removed by sweeping, blowing with compressed air, rinsing with water or a combination of these methods as required. Rubber deposits, surface laitance, existing paint markings, and other coatings adhering to the pavement shall be completely removed with scrapers, wire brushes, sandblasting, approved chemicals, or mechanical abrasion as directed. Areas of old pavement affected with oil or grease shall be scrubbed with several applications of trisodium phosphate solution or other approved detergent or degreaser, and rinsed thoroughly after each application. After cleaning, oil-soaked areas shall be sealed with cut shellac to prevent bleeding through the new paint. Pavement surfaces shall be allowed to dry, when water is used for cleaning, prior to striping or marking. Surfaces shall be recleaned, when work has been stopped due to rain. 3.1.1 Pretreatment for Early Painting ************************************************************************** NOTE: For new rigid pavements which require early painting, the following paragraph will be added. ************************************************************************** Where early painting is required on rigid pavements, apply a pretreatment with an aqueous solution, containing 3 percent phosphoric acid and 2 percent zinc chloride, to prepared pavement areas prior to painting. 3.1.2 Cleaning Existing Pavement Markings In general, markings shall not be placed over existing pavement marking patterns. Remove existing pavement markings, which are in good condition but interfere or conflict with the newly applied marking patterns. Deteriorated or obscured markings that are not misleading or confusing or interfere with the adhesion of the new marking material do not require removal. New preformed and thermoplastic pavement markings shall not be applied over existing preformed or thermoplastic markings. Whenever grinding, scraping, sandblasting or other operations are performed the work must be conducted in such a manner that the finished pavement surface is not damaged or left in a pattern that is misleading or confusing. When these operations are completed the pavement surface shall be blown off with compressed air to remove residue and debris resulting from the cleaning work. 3.1.3 Cleaning Concrete Curing Compounds On new portland cement concrete pavements, cleaning operations shall not begin until a minimum of 30 days after the placement of concrete. All new concrete pavements shall be cleaned by either sandblasting or water blasting. When water blasting is performed, thermoplastic and preformed markings shall be applied no sooner than 24 hours after the blasting has been completed. The extent of the blasting work shall be to clean and prepare the concrete surface as follows: a. There is no visible evidence of curing compound on the peaks of the textured concrete surface. b. There are no heavy puddled deposits of curing compound in the valleys of the textured concrete surface. URS FOR EQM SECTION 32 17 24.00 10 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 c. All remaining curing compound is intact; all loose and flaking material is removed. d. The peaks of the textured pavement surface are rounded in profile and free of sharp edges and irregularities. e. The surface to be marked is dry. 3.2 APPLICATION All pavement markings and patterns shall be placed as shown on the plans. 3.2.1 Paint Paint shall be applied to clean, dry surfaces, and only when air and pavement temperatures are above 40 degrees F and less than 95 degrees F. Paint temperature shall be maintained within these same limits. New asphalt pavement surfaces and new Portland concrete cement shall be allowed to cure for a period of not less than 30 days before applications of paint. Paint shall be applied pneumatically with approved equipment at rate of coverage specified. Provide guide lines and templates as necessary to control paint application. Special precautions shall be taken in marking numbers, letters, and symbols. Edges of markings shall be sharply outlined. 3.2.1.1 Rate of Application a. Reflective Markings: Pigmented binder shall be applied evenly to the pavement area to be coated at a rate of 105 plus or minus 5 square feet/gallon. Glass spheres shall be applied uniformly to the wet paint [on airfield pavement at a rate of 8] [on road and street pavement at a rate of 6] plus or minus 0.5 pounds of glass spheres per gallon of paint. b. Nonreflective Markings: Paint shall be applied evenly to the pavement surface to be coated at a rate of 105 plus or minus 5 square feet/gallon. 3.2.1.2 Drying The maximum drying time requirements of the paint specifications will be strictly enforced to prevent undue softening of bitumen, and pickup, displacement, or discoloration by tires of traffic. If there is a delay in drying of the markings, painting operations shall be discontinued until cause of the slow drying is determined and corrected. Raised Reflective Markers Prefabricated markers shall be aligned carefully at the required spacing and permanently fixed in place by means of epoxy resin adhesives. To insure good bond, pavement in areas where markers will be set shall be thoroughly cleaned by sandblasting and use of compressed air prior to applying adhesive. 3.2.2 Reflective Media Application of reflective media shall immediately follow application of pigmented binder. Drop-on application of glass spheres shall be accomplished to insure that reflective media is evenly distributed at the specified rate of coverage. Should there be malfunction of either paint URS FOR EQM SECTION 32 17 24.00 10 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 applicator or reflective media dispenser, operations shall be discontinued immediately until deficiency is corrected. 3.3 MARKING REMOVAL Pavement marking, shall be removed in the areas shown on the drawings. Removal of marking shall be as complete as possible without damage to the surface. Aggregate shall not be exposed by the removal process. After the markings are removed, the cleaned pavement surfaces shall exhibit adequate texture for remarking as specified in paragraph SURFACE PREPARATION. Demonstrate removal of pavement marking in an area designated by the Contracting Officer. The demonstration area will become the standard for the remainder of the work. 3.3.1 Equipment Operation Equipment shall be controlled and operated to remove markings from the pavement surface, prevent dilution or removal of binder from underlying pavement, and prevent emission of blue smoke from asphalt or tar surfaces. 3.3.2 Cleanup and Waste Disposal The worksite shall be kept clean of debris and waste from the removal operations. Cleanup shall immediately follow removal operations in areas subject to air traffic. Debris shall be disposed of at approved sites. -- End of Section -- URS FOR EQM SECTION 32 17 24.00 10 Page 11 65% - 01/23/2015 This Page Left Intentionally Blank REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 92 19 (October 2006) ---------------------------Preparing Activity: NAVFAC Replacing without change UFGS-02921 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 32 92 19 SEEDING ************************************************************************** NOTE: This guide specification covers the requirements for seeding. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** ************************************************************************** NOTE: The following information shall be shown on the project drawings: 1. Clearly indicate all areas to be turfed and if more than one type of turf is specified, delineate areas for each type. 2. All draft turf specifications shall be submitted to the cognizant Landscape Architect/Natural Resources Specialist for review to ensure that the specifications are in accordance with environmental conditions peculiar to the project areas. ************************************************************************** PART 1 1.1 GENERAL REFERENCES ************************************************************************** NOTE: This paragraph is used to list the URS FOR EQM SECTION 32 92 19 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. ASTM INTERNATIONAL (ASTM) ASTM D4972 (2013) pH of Soils U.S. DEPARTMENT OF AGRICULTURE (USDA) AMS Seed Act (1940; R 1988; R 1998) Federal Seed Act DOA SSIR 42 (1996) Soil Survey Investigation Report No. 42, Soil Survey Laboratory Methods Manual, Version 3.0 1.2 1.2.1 DEFINITIONS Stand of [Turf][_____] 95 percent ground cover of the established species. 1.3 RELATED REQUIREMENTS [Section 31 00 00 EARTHWORK], [Section 32 84 24 IRRIGATION SPRINKLER SYSTEMS], [Section 32 96 00 TRANSPLANTING EXTERIOR PLANTS], [Section 32 92 23 SODDING], [Section 32 92 26 SPRIGGING], [Section 32 93 00 EXTERIOR PLANTS], and Section 32 05 33 LANDSCAPE ESTABLISHMENT applies to this section for pesticide use and plant establishment requirements, with additions and modifications herein. 1.4 SUBMITTALS ************************************************************************** NOTE: Review Submittal Description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have URS FOR EQM SECTION 32 92 19 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 designated those items that require Government approval, due to their complexity or criticality, with a "G". Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are [for Contractor Quality Control approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-03 Product Data Wood cellulose fiber mulch Fertilizer Include physical characteristics, and recommendations. SD-06 Test Reports ************************************************************************** NOTE: In states that require certification, adjust testing requirements to suit local conditions. ************************************************************************** Topsoil composition tests (reports and recommendations). SD-07 Certificates State certification and approval for seed URS FOR EQM SECTION 32 92 19 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 SD-08 Manufacturer's Instructions Erosion Control Materials 1.5 DELIVERY, STORAGE, AND HANDLING 1.5.1 Delivery 1.5.1.1 Seed Protection Protect from drying out and from contamination during delivery, on-site storage, and handling. 1.5.1.2 [Fertilizer] [Gypsum] [Sulfur] [Iron] [and] [Lime] Delivery Deliver to the site in original, unopened containers bearing manufacturer's chemical analysis, name, trade name, trademark, and indication of conformance to state and federal laws. Instead of containers, [fertilizer] [gypsum] [sulphur] [iron] [and] [lime] may be furnished in bulk with certificate indicating the above information. 1.5.2 Storage 1.5.2.1 Seed, [Fertilizer] [Gypsum] [Sulfur] [Iron] [and] [Lime] Storage Store in cool, dry locations away from contaminants. 1.5.2.2 Topsoil Prior to stockpiling topsoil, treat growing vegetation with application of appropriate specified non-selective herbicide. Clear and grub existing vegetation three to four weeks prior to stockpiling topsoil. 1.5.2.3 Handling Do not drop or dump materials from vehicles. 1.6 TIME RESTRICTIONS AND PLANTING CONDITIONS ************************************************************************** NOTE: Check with the local Agriculture County Extension Service to determine proper planting seasons for specie specified, for the optimum cover depth, and for the proper rate of application for sowing and drilling seed as this rate varies with the specie of seed used and local conditions. Allow for planting period in the construction completion time. Delete time restrictions for continuous growing conditions. ************************************************************************** 1.6.1 Restrictions Do not plant when the ground is [frozen,] [snow covered,] muddy, or when air temperature exceeds [90] [_____] degrees Fahrenheit. URS FOR EQM SECTION 32 92 19 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.7 TYMX989345A FA3002-09-D-0002 TG02 TIME LIMITATIONS 1.7.1 Seed Apply seed within twenty four hours after seed bed preparation. PART 2 2.1 PRODUCTS SEED ************************************************************************** NOTE: The specific species and varieties used should be based on recommendations of the local Agriculture County Extension Service Office. ************************************************************************** 2.1.1 Classification Provide [State-certified] [State-approved] [Endophyte-enhanced] seed of the latest season's crop delivered in original sealed packages, bearing producer's guaranteed analysis for percentages of mixtures, purity, germination, weedseed content, and inert material. Label in conformance with AMS Seed Act and applicable state seed laws. Wet, moldy, or otherwise damaged seed will be rejected. Field mixes will be acceptable when field mix is performed on site in the presence of the [Contracting Officer] [_____]. 2.1.2 Planting Dates Planting Season Planting Dates [Season 1] [_____] [Season 2] [_____] [Temporary Seeding] [_____] 2.1.3 Seed Purity Botanical Common Name Name Minimum Percent Pure Seed Minimum Maximum Percent Percent Germination Weed Seed and Hard Seed [_____] [_____] [_____] [_____] [_____] [_____] [_____] [_____] [_____] [_____] [_____] [_____] [_____] [_____] [_____] URS FOR EQM SECTION 32 92 19 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.1.4 TYMX989345A FA3002-09-D-0002 TG02 Seed Mixture by Weight Planting Season Variety Percent (by Weight) [Season 1] [_____] [_____] [Season 2] [_____] [_____] [Temporary Seeding] [_____] [_____] Proportion seed mixtures by weight. Temporary seeding must later be replaced by [Season 1][Season 2] plantings for a permanent stand of grass. The same requirements of turf establishment for [Season 1][Season 2] apply for temporary seeding. 2.2 TOPSOIL ************************************************************************** NOTE: If topsoil properties are included in another section of Division 2, delete this paragraph and include a cross-reference to the appropriate section. Otherwise, select appropriate paragraphs on topsoil. Check with the local Agriculture County Extension Service Office for soil properties appropriate for the plant materials to be planted. Where suitable topsoil is available within limits of the work area, stripping and stockpiling of topsoil should be included in the applicable section of Division 2 of the specification. If suitable topsoil is not available within the limits of the work area, it should generally be the Contractor's option to either treat the soil of the graded areas with fertilizer and supplements so as to be conducive to turf establishment and maintenance, or to transport topsoil to the project site. Modify pH range for specified turf and geographical requirements. ************************************************************************** 2.2.1 On-Site Topsoil Surface soil stripped and stockpiled on site and modified as necessary to meet the requirements specified for topsoil in paragraph entitled "Composition." When available topsoil shall be existing surface soil stripped and stockpiled on-site in accordance with Section [31 00 00 EARTHWORK][31 23 00.00 20 EXCAVATION AND FILL]. 2.2.2 Off-Site Topsoil Conform to requirements specified in paragraph entitled "Composition." Additional topsoil shall be [furnished by the Contractor] [obtained from topsoil borrow areas indicated]. 2.2.3 Composition Containing from 5 to 10 percent organic matter as determined by the topsoil URS FOR EQM SECTION 32 92 19 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 composition tests of the Organic Carbon, 6A, Chemical Analysis Method described in DOA SSIR 42. Maximum particle size, 3/4 inch, with maximum 3 percent retained on 1/4 inch screen. The pH shall be tested in accordance with ASTM D4972. Topsoil shall be free of sticks, stones, roots, and other debris and objectionable materials. Other components shall conform to the following limits: Silt [25-50][7 to 17][_____] percent Clay [10-30][4 to 12][_____] percent Sand [20-35][70 to 82][_____] percent pH [5.5 to 7.0][_____] Soluble Salts [600] [_____] ppm maximum 2.3 SOIL CONDITIONERS ************************************************************************** NOTE: Prior to including these provisions in project specifications, perform tests of on-site topsoil to determine its suitability and the possible need of pH adjusters or soil conditioners. Delete these requirements in developed areas and on small projects where planting is minimal. ************************************************************************** Add conditioners to topsoil as required to bring into compliance with "composition" standard for topsoil as specified herein. 2.3.1 Lime ************************************************************************** NOTE: Use ASTM C602 calcium carbonate equivalent (C.C.E.) as specified in Table 1: for burnt lime, C.C.E. shall not be less than 140 percent; for hydrated lime, C.C.E. shall not be less than 110 percent; and for limestone, C.C.E. shall not be less than 80 percent. ************************************************************************** Commercial grade [hydrate] [or] [burnt] limestone containing a calcium carbonate equivalent (C.C.E.) as specified in ASTM C602 of not less than [_____] percent. 2.3.2 Aluminum Sulfate Commercial grade. 2.3.3 Sulfur 100 percent elemental URS FOR EQM SECTION 32 92 19 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.3.4 TYMX989345A FA3002-09-D-0002 TG02 Iron 100 percent elemental 2.3.5 Peat Natural product of [peat moss] derived from a freshwater site and conforming to [ASTM D4427] [as modified herein]. Shred and granulate peat to pass a 1/2 inch mesh screen and condition in storage pile for minimum 6 months after excavation. 2.3.6 Sand Clean and free of materials harmful to plants. 2.3.7 Perlite Horticultural grade. 2.3.8 Composted Derivatives Ground bark, nitrolized sawdust, humus or other green wood waste material free of stones, sticks, and soil stabilized with nitrogen and having the following properties: 2.3.8.1 Particle Size Minimum percent by weight passing: No. 4 mesh screen No. 8 mesh screen 2.3.8.2 95 80 Nitrogen Content Minimum percent based on dry weight: Fir Sawdust Fir or Pine Bark 2.3.9 0.7 1.0 Gypsum Coarsely ground gypsum comprised of calcium sulfate dihydrate 61 percent, calcium 22 percent, sulfur 17 percent; minimum 96 percent passing through 20 mesh screen, 100 percent passing thru 16 mesh screen. 2.3.10 Calcined Clay Calcined clay shall be granular particles produced from montmorillonite clay calcined to a minimum temperature of 1200 degrees F. Gradation: A minimum 90 percent shall pass a No. 8 sieve; a minimum 99 percent shall be retained on a No. 60 sieve; and a maximum 2 percent shall pass a No. 100 sieve. Bulk density: A maximum 40 pounds per cubic foot. FERTILIZER ************************************************************************** NOTE: Check with the local Agriculture County Extension Service Office for recommended fertilizer mixture for local conditions. URS FOR EQM SECTION 32 92 19 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** 2.4 Granular Fertilizer [Organic][synthetic], granular controlled release fertilizer containing the following minimum percentages, by weight, of plant food nutrients: [_____] percent available nitrogen [_____] percent available phosphorus [_____] percent available potassium [_____] percent sulfur [[_____] percent iron] Hydroseeding Fertilizer Controlled release fertilizer, to use with hydroseeding and composed of pills coated with plastic resin to provide a continuous release of nutrients for at least 6 months and containing the following minimum percentages, by weight, of plant food nutrients. [_____] percent available nitrogen [_____] percent available phosphorus [_____] percent available potassium [[_____] percent sulfur] [[_____] percent iron] 2.3 MULCH ************************************************************************** NOTE: Check with the local Agriculture County Extension Service Office to determine choice of mulch most suitable for the project area. Specify only one type of mulch. ************************************************************************** Mulch shall be free from noxious weeds, mold, and other deleterious materials. 2.3.1 Straw Stalks from oats, wheat, rye, barley, or rice. Furnish in air-dry condition and of proper consistency for placing with commercial mulch blowing equipment. Straw shall contain no fertile seed. Hay Air-dry condition and of proper consistency for placing with commercial mulch blowing equipment. Hay shall be sterile, containing no fertile seed. 2.3.1 Wood Cellulose Fiber Mulch ************************************************************************** NOTE: Wood cellulose fiber mulches have been successful on level areas or on slopes with slight grades where sufficient moisture is present to obtain a quick germination of grass seed. The material should be hydraulically applied at the following rates: Areas up to and including 3 to 1 slopes, at the rate of 1,000 pounds per acre; areas URS FOR EQM SECTION 32 92 19 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 steeper than 3 to 1 at the rate of 1,400 pounds per acre. It should not be specified for slopes 2 to 1 or greater in areas where drought may prevent germination of the seed or where runoff from heavy rains may cut gullies through the fiber mulch. In these areas use erosion control materials such as specified in paragraph entitled "Erosion Control Material." ************************************************************************** Use recovered materials of either paper-based (100 percent) or wood-based (100 percent) hydraulic mulch. Processed to contain no growth or germination-inhibiting factors and dyed an appropriate color to facilitate visual metering of materials application. Composition on air-dry weight basis: 9 to 15 percent moisture, pH range from 5.5 to 8.2[_____]. Use with hydraulic application of grass seed and fertilizer. 2.4 WATER ************************************************************************** NOTE: When water is Government furnished, locate the source. Recycled or reclaimed irrigation water may be available through a tertiary treatment plant on or off site. It is preferred that this type of water be used for irrigation whenever possible. Check project specific conditions. Unless otherwise directed, water shall be the responsibility of the Contractor. Water source shall be potable or non-potable. If non-potable edit specification accordingly. Source of water shall be approved by the Contracting Officer and shall be of suitable quality for irrigation, containing no elements toxic to plant life. Coordinate information presented here with Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS. ************************************************************************** Source of water shall be approved by Contracting Officer and of suitable quality for irrigation, containing no elements toxic to plant life. [2.5 EROSION CONTROL MATERIALS ************************************************************************** NOTE: The Contractor may propose other types of erosion control material, based on site conditions. ************************************************************************** Erosion control material shall conform to the following: [2.5.1 Erosion Control Blanket [100 percent agricultural straw][70 percent agricultural straw/30 percent coconut fiber matrix] stitched with a degradable nettings, designed to degrade within [12 months][18 months]. URS FOR EQM SECTION 32 92 19 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS ][2.5.2 TYMX989345A FA3002-09-D-0002 TG02 Erosion Control Fabric Fabric shall be knitted construction of polypropylene yarn with uniform mesh openings 3/4 to 1 inch square with strips of biodegradable paper. Filler paper strips shall have a minimum life of 6 months. ][2.5.3 Erosion Control Net Net shall be heavy, twisted jute mesh, weighing approximately 1.22 pounds per linear yard and 4 feet wide with mesh openings of approximately 1 inch square. ][2.5.4 Hydrophilic Colloids Hydrophilic colloids shall be physiologically harmless to plant and animal life without phytotoxic agents. Colloids shall be naturally occurring, silicate powder based, and shall form a water insoluble membrane after curing. Colloids shall resist mold growth. ]2.5.5 Erosion Control Material Anchors Erosion control anchors shall be as recommended by the manufacturer. ]PART 3 3.1 EXECUTION PREPARATION 3.1.1 EXTENT OF WORK Provide soil preparation (including soil conditioners as required), fertilizing, seeding, and surface topdressing of all newly graded finished earth surfaces, unless indicated otherwise, and at all areas inside or outside the limits of construction that are disturbed by the Contractor's operations. 3.1.1.1 Topsoil Provide 4 inches of [off-site topsoil][on-site topsoil][existing soil] to meet indicated finish grade. After areas have been brought to indicated finish grade, incorporate [fertilizer] [pH adjusters] [soil conditioners] into soil a minimum depth of [4] [_____] inches by disking, harrowing, tilling or other method approved by the Contracting Officer. Remove debris and stones larger than 3/4 inch in any dimension remaining on the surface after finish grading. Correct irregularities in finish surfaces to eliminate depressions. Protect finished topsoil areas from damage by vehicular or pedestrian traffic. 3.1.1.2 [Soil Conditioner Application Rates ************************************************************************** NOTE: Check with the local Agriculture County Extension Service and specify amounts applicable for the project area. ************************************************************************** Apply soil conditioners at rates as determined by laboratory soil analysis of the soils at the job site. For bidding purposes only apply at rates for the following: URS FOR EQM SECTION 32 92 19 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 [Lime [ [_____] pounds per acre] [ [_____] pounds per 1000 square feet.]] [Sulfur [ [_____] pounds per acre] [ [_____] pounds per 1000 square feet.]] [Iron [ [_____] pounds per acre] [ [_____] pounds per 1000 square feet.]] [Aluminum Sulfate [ [_____] pounds per acre] [ [_____] pounds per 1000 square feet.]] [Peat [ [_____] cubic yard per acre] [ [_____] cubic yards per 1000 square feet.]] [Sand [ [_____] cubic yard per acre] [ [_____] cubic yards per 1000 square feet.]] [Perlite [ [_____] cubic yard per acre] [ [_____] cubic yards per 1000 square feet.]] [Compost Derivatives [ [_____] cubic yard per acre] [ [_____] cubic yards per 1000 square feet.]] [Calcined Clay [ [_____] cubic yard per acre] [ [_____] cubic yards per 1000 square feet.]] [Gypsum [ [_____] cubic yard per acre] [ [_____] cubic yards per 1000 square feet.]] ]3.1.1.2 [Fertilizer Application Rates ************************************************************************** NOTE: Check with the local Agriculture County Extension Service and specify amounts applicable for the project area. Two fertilizer applications may be required when hydroseeding with wood fiber mulch. ************************************************************************** Apply fertilizer at rates as determined by laboratory soil analysis of the soils at the job site. For bidding purposes only apply at rates for the following: [Organic Granular Fertilizer [ [_____] pounds per acre] [ [_____] pounds per 1000 square feet.]] [Synthetic Fertilizer [ [_____] pounds per acre ] [ [_____] pounds per 1000 square feet.]] [Hydroseeding Fertilizer: [500[_____] pounds per acre] [ [_____] pounds per 1000 square feet.]] ]3.2 3.2.1 SEEDING Seed Application Seasons and Conditions ************************************************************************** NOTE: Check with the local Agriculture County Extension Service to determine proper planting seasons for specie specified, for the optimum cover depth, and for the proper rate of application for URS FOR EQM SECTION 32 92 19 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 sowing and drilling seed as this rate varies with the specie of seed used and local conditions. Allow for planting period in the construction completion time. Delete time restrictions for continuous growing conditions. ************************************************************************** ************************************************************************** NOTE: Delete the last two lines of this paragraph when hydroseeding is selected as the only seed application method. ************************************************************************** Immediately before seeding, restore soil to proper grade. Do not seed when ground is muddy [frozen] [snow covered] or in an unsatisfactory condition for seeding. If special conditions exist that may warrant a variance in the above seeding dates or conditions, submit a written request to the Contracting Officer stating the special conditions and proposed variance. Apply seed within twenty four hours after seedbed preparation. Sow seed by approved sowing equipment. Sow one-half the seed in one direction, and sow remainder at right angles to the first sowing. 3.2.2 Seed Application Method Seeding method shall be [broadcasted and drop seeding][drill seeding][ hydroseeding]. 3.2.2.1 [Broadcast and Drop Seeding Seed shall be uniformly broadcast at the rate of [_____] pounds per 1000 square feet. Use broadcast or drop seeders. Sow one-half the seed in one direction, and sow remainder at right angles to the first sowing. Cover seed uniformly to a maximum depth of 1/4 inch in clay soils and [1/2] [_____] inch in sandy soils by means of spike-tooth harrow, cultipacker, raking or other approved devices. ]3.2.2.2 [Drill Seeding ************************************************************************** NOTE: Check with the local Agriculture County Extension Service to determine proper planting seasons for specie specified, for the optimum cover depth, and for the proper rate of application for sowing and drilling seed as this rate varies with the specie of seed used and local conditions. Allow for planting period in the construction completion time. Delete time restrictions for continuous growing conditions. ************************************************************************** Seed shall be drilled at the rate of [_____] pounds per 1000 square feet. Use [cultipacker seeders] [grass seed drills] [_____]. Drill seed uniformly to average depth of [1/2] [_____] inch. ]3.2.2.1 [Hydroseeding ************************************************************************** NOTE: Check with the local Agriculture County Extension Service to determine rate of application. URS FOR EQM SECTION 32 92 19 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 This rate will vary due to site requirements for fertilizer, mulch material, and rates of seeding. ************************************************************************** First, mix water and fiber. Wood cellulose fiber, paper fiber, or recycled paper shall be applied as part of the hydroseeding operation. Fiber shall be added at 1,000 pounds, dry weight, per acre. Then add and mix seed and fertilizer to produce a homogeneous slurry. Seed shall be mixed to ensure broadcasting at the rate of 120 pounds per acre.[_____] pounds per 1000 square feet. When hydraulically sprayed on the ground, material shall form a blotter like cover impregnated uniformly with grass seed. Spread with one application with no second application of mulch. ]3.2.3 3.2.3.1 Mulching [Hay or Straw Mulch Hay or straw mulch shall be spread uniformly at the rate of 2 tons per acre. Mulch shall be spread by hand, blower-type mulch spreader, or other approved method. Mulching shall be started on the windward side of relatively flat areas or on the upper part of steep slopes, and continued uniformly until the area is covered. The mulch shall not be bunched or clumped. Sunlight shall not be completely excluded from penetrating to the ground surface. All areas installed with seed shall be mulched on the same day as the seeding. Mulch shall be anchored immediately following spreading. ]3.2.3.2 [Mechanical Anchor Mechanical anchor shall be a V-type-wheel land packer; a scalloped-disk land packer designed to force mulch into the soil surface; or other suitable equipment. ]3.2.3.3 [Asphalt Adhesive Tackifier Asphalt adhesive tackifier shall be sprayed at a rate between 10 to 13 gallons per 1000 square feet. Sunlight shall not be completely excluded from penetrating to the ground surface. ]3.2.3.1 [Non-Asphaltic Tackifier Hydrophilic colloid shall be applied at the rate recommended by the manufacturer, using hydraulic equipment suitable for thoroughly mixing with water. A uniform mixture shall be applied over the area. ]3.2.3.2 [Asphalt Adhesive Coated Mulch Hay or straw mulch may be spread simultaneously with asphalt adhesive applied at a rate between 10 to 13 gallons per 1000 square feet, using power mulch equipment which shall be equipped with suitable asphalt pump and nozzle. The adhesive-coated mulch shall be applied evenly over the surface. Sunlight shall not be completely excluded from penetrating to the ground surface. ][3.2.4 Rolling ************************************************************************** NOTE: Normally the roller weight should not exceed 90 pounds per foot of roller width. Light rolling is URS FOR EQM SECTION 32 92 19 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 needed on newly seeded and sprigged areas to firm the seed or sprigs into contact with the soil for optimum germination and growth. However, excessive soil compaction beyond this firming action will reduce the desirable percentages of air and water spaces in good growing topsoil. ************************************************************************** Immediately after seeding, firm entire area except for slopes in excess of 3 to 1 with a roller not exceeding [90] [_____] pounds for each foot of roller width. [If seeding is performed with cultipacker-type seeder or by hydroseeding, rolling may be eliminated.] ]3.2.4 Erosion Control Material ************************************************************************** NOTE: Specify erosion control where water concentrates and flows across areas at velocities which create an erosion hazard. Allow Contractor option for type of erosion control material, unless project specific requirements dictate otherwise. ************************************************************************** Install in accordance with manufacturer's instructions, where indicated or as directed by the Contracting Officer. 3.2.5 Watering Start watering areas seeded as required by temperature and wind conditions. Apply water at a rate sufficient to insure thorough wetting of soil to a depth of [2] [_____] inches without run off. During the germination process, seed is to be kept actively growing and not allowed to dry out. 3.3 PROTECTION OF TURF AREAS Immediately after turfing, protect area against traffic and other use. 3.4 3.4.1 [RENOVATION OF EXISTING TURF AREA [Aeration Upon completion of weed eradication operations and Contracting Officer's approval to proceed, aerate turf areas indicated , by approved device. Core, by pulling soil plugs, to a minimum depth of [_____] inches. [Leave all soil plugs, that are produced, in the turf area.] [Remove all debris generated during this operation off site.] [After aeration operations are complete, topdress entire area [ 1/4 inch] [ 1/2 inch] depth with the following mixture: [[_____] [[_____] [[_____] [[_____] [[_____] percent percent percent percent percent sand] humus] gypsum] organic fertilizer] synthetic fertilizer] Blend all parts of topdressing mixture to a uniform consistency throughout.] Keep clean at all times at least one paved pedestrian access route and one paved vehicular access route to each building. Clean all soil URS FOR EQM SECTION 32 92 19 Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 plugs off of other paving when work is complete. ]3.4.2 [Vertical Mowing Upon completion of aerating operation and Contracting Officer's approval to proceed, vertical mow turf areas indicated, by approved device, to a depth of [ 1/4 inch] [ 1/2 inch] above existing soil level, to reduce thatch build-up, grain, and surface compaction. Keep clean at all times at least one paved pedestrian access route and one paved vehicular access route to each building. Clean other paving when work is complete. Remove all debris generated during this operation off site. ]3.4.3 [Dethatching Upon completion of aerating operation and Contracting Officer's approval to proceed, dethatch turf areas indicated, by approved device, to a depth of [ 1/4 inch] [ 1/2 inch] below existing soil level, to reduce thatch build-up, grain, and surface compaction. Keep clean at all times at least one paved pedestrian access route and one paved vehicular access route to each building. Clean other paving when work is complete. Remove all debris generated during this operation off site. ]3.4.4 [Overseeding ************************************************************************** NOTE: Drill seeding is the most viable method of overseeding when significant vegetation remains. Existing vegetative cover (live or dead) may prevent desired soil contact when seeded by other methods. ************************************************************************** Apply seed in accordance with applicable portions of paragraph entitled "Seed Application Method" at rates in accordance with paragraph entitled "Seed Composition." ]]3.4 RESTORATION Restore to original condition existing turf areas which have been during turf installation operations at the Contractor's expense. clean at all times at least one paved pedestrian access route and vehicular access route to each building. Clean other paving when adjacent areas is complete. damaged Keep one paved work in -- End of Section -- URS FOR EQM SECTION 32 92 19 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-33 40 00 (February 2010) Change 4 - 11/14 ----------------------------Preparing Activity: USACE Superseding UFGS-33 40 00 (August 2009) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2014 ************************************************************************** SECTION 33 40 00 STORM DRAINAGE UTILITIES ************************************************************************** NOTE: This guide specification covers the requirements for storm drainage piping systems using concrete, clay, steel, ductile iron, aluminum, polyvinyl chloride (PVC), polyethylene (PE), polypropylene (PP) pipe and steel reinforced polyethylene (SRPE) pipe. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: On the project drawing, show: 1. Plan and location of all new pipelines, including type of service and size of pipe. 2. Location, size, and type of service of existing connecting, intersecting, or adjacent pipelines and other utilities. 3. Paved areas and railroads which pass over new pipelines. URS FOR EQM SECTION 33 40 00 Page 1 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 4. Profile, where necessary to show unusual conditions. 5. Invert elevations at beginning and end of pipelines and at manholes or similar structures. 6. Class or strength of pipe and limits for same where class or strength will be different for different sections of pipeline. Provide shape requirements if different shapes available. 7. Design details for pertinent manholes, catch basins, curb inlets, and head walls. 8. Store drainage lines and culverts required to be watertight. 9. Bedding conditions, where different from those specified in the appropriate NAVFAC specifications and location of cradle(s), when cradle is required if not covered under the appropriate NAVFACENGCOM specifications. ************************************************************************** 1.1 MEASUREMENT AND PAYMENT ************************************************************************** NOTE: Delete this paragraph when the work specified is included in a lump-sum contract price. Separate bid may be required for each item for the construction of the various sizes of pipe culverts and storm drains and individual miscellaneous drainage structures, including all excavation, materials, backfilling, etc., for the completed work. If separate bid items are used for the excavation, this fact should be clearly stated in the specifications and bid form, indicating that payment is to be made separately for earth excavation, rock excavation, borrow excavation, or other items that otherwise might be construed as the basis for a claim by the Contractor. Unit prices for rock excavation should be independent of, and not in addition to, the unit bid price for common excavation, unless so specified and so stated in the bid form. ************************************************************************** 1.1.1 Pipe Culverts and Storm Drains The length of pipe installed will be measured along the centerlines of the pipe from end to end of pipe without deductions for diameter of manholes. Pipe will be paid for at the contract unit price for the number of linear feet of culverts or storm drains placed in the accepted work. 1.1.2 Storm Drainage Structures ************************************************************************** URS FOR EQM SECTION 33 40 00 Page 2 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 NOTE: Fill brackets with depth requirements. ************************************************************************** The quantity of manholes and inlets will be measured as the total number of manholes and inlets of the various types of construction, complete with frames and gratings or covers and, where indicated, with fixed side-rail ladders, constructed to the depth of 12[_____] feet in the accepted work. The depth of manholes and inlets will be measured from the top of grating or cover to invert of outlet pipe. Manholes and inlets constructed to depths greater than the depth specified above will be paid for as units at the contract unit price for manholes and inlets, plus an additional amount per linear foot for the measured depth beyond a depth of 12[_____] feet. 1.1.3 Walls and Headwalls Walls and headwalls will be measured by the number of cubic yards of reinforced concrete, plain concrete, or masonry used in the construction of the walls and headwalls. Wall and headwalls will be paid for at the contract unit price for the number of walls and headwalls constructed in the completed work. 1.1.4 Flared End Sections Flared end sections will be measured by the unit. Flared end sections will be paid for at the contract unit price for the various sizes in the accepted work. 1.1.5 Sheeting and Bracing Payment will be made for that sheeting and bracing ordered to be left in place, based on the number of square feet of sheeting and bracing remaining below the surface of the ground. 1.1.6 Rock Excavation ************************************************************************** NOTE: Reference should be made to other sections of the project specifications, as applicable, or pertinent requirements may be included in this section. ************************************************************************** Payment will be made for the number of cubic yards of material acceptably excavated, as specified and defined as rock excavation in Section 31 00 00 EARTHWORK, measured in the original position, and computed by allowing actual width of rock excavation with the following limitations: maximum rock excavation width, 30 inches for pipe of 12 inch or less nominal diameter; maximum rock excavation width, 16 inches greater than outside diameter of pipe of more than 12 inch nominal diameter. Measurement will include authorized overdepth excavation. Payment will also include all necessary drilling and blasting, and all incidentals necessary for satisfactory excavation and disposal of authorized rock excavation. No separate payment will be made for backfill material required to replace rock excavation; this cost shall be included in the Contractor's unit price bid per cubic yard for rock excavation. In rock excavation for manholes and other appurtenances, 1 foot will be allowed outside the wall lines of the structures. URS FOR EQM SECTION 33 40 00 Page 3 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.1.7 TYMX989345A FA3002-09-D-0002 TG02 Backfill Replacing Unstable Material Payment will be made for the number of cubic yards of select granular material required to replace unstable material for foundations under pipes or drainage structures, which will constitute full compensation for this backfill material, including removal and disposal of unstable material and all excavating, hauling, placing, compacting, and all incidentals necessary to complete the construction of the foundation satisfactorily. Pipe Placed by Jacking Payment will be made for the number of linear feet of jacked pipe accepted in the completed work measured along the centerline of the pipe in place. 1.2 REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. ASTM INTERNATIONAL (ASTM) ASTM A123/A123M (2013) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products ASTM A48/A48M (2003; R 2012) Standard Specification for Gray Iron Castings ASTM A536 (1984; R 2009) Standard Specification for Ductile Iron Castings ASTM B26/B26M (2012) Standard Specification for Aluminum-Alloy Sand Castings ASTM C1103 (2003; R 2009) Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines URS FOR EQM SECTION 33 40 00 Page 4 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ASTM C139 (2011) Standard Specification for Concrete Masonry Units for Construction of Catch Basins and Manholes ASTM C1433 (2014) Standard Specification for Precast Reinforced Concrete Box Sections for Culverts, Storm Drains, and Sewers ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method ASTM C270 (2014) Standard Specification for Mortar for Unit Masonry ASTM C32 (2013) Standard Specification for Sewer and Manhole Brick (Made from Clay or Shale) ASTM C425 (2004; R 2013) Standard Specification for Compression Joints for Vitrified Clay Pipe and Fittings ASTM C443 (2011) Standard Specification for Joints for Concrete Pipe and Manholes, Using Rubber Gaskets ASTM C478 (2013) Standard Specification for Precast Reinforced Concrete Manhole Sections ASTM C55 (2014) Concrete Brick ASTM C62 (2013a) Building Brick (Solid Masonry Units Made from Clay or Shale) ASTM C655 (2014) Reinforced Concrete D-Load Culvert, Storm Drain, and Sewer Pipe ASTM C76 (2014) Standard Specification for Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe ASTM C923 (2008; R 2013) Standard Specification for Resilient Connectors Between Reinforced Concrete Manhole Structures, Pipes and Laterals ASTM C969 (2002; R 2009) Standard Practice for Infiltration and Exfiltration Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines ASTM C990 (2009; R 2014) Standard Specification for Joints for Concrete Pipe, Manholes and Precast Box Sections Using Preformed Flexible Joint Sealants ASTM D1056 (2014) Standard Specification for Flexible Cellular Materials - Sponge or Expanded URS FOR EQM SECTION 33 40 00 Page 5 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Rubber ASTM D1171 (1999; R 2007) Rubber Deterioration Surface Ozone Cracking Outdoors or Chamber (Triangular Specimens) ASTM D1557 (2012) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3) ASTM D1751 (2004; E 2013; R 2013) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types) ASTM D1752 (2004a; R 2013) Standard Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion ASTM D2167 (2008) Density and Unit Weight of Soil in Place by the Rubber Balloon Method ASTM D3212 (2007; R 2013) Standard Specification for Joints for Drain and Sewer Plastic Pipes Using Flexible Elastomeric Seals ASTM D6938 (2010) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth) 1.3 SUBMITTALS ************************************************************************** NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for URS FOR EQM SECTION 33 40 00 Page 6 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. An "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. ************************************************************************** Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-03 Product Data Placing Pipe Submit printed copies of the manufacturer's recommendations for installation procedures of the material being placed, prior to installation. SD-04 Samples Pipe for Culverts and Storm Drains SD-07 Certificates Resin Certification Pipeline Testing Hydrostatic Test on Watertight Joints Determination of Density Frame and Cover for Gratings 1.4 1.4.1 DELIVERY, STORAGE, AND HANDLING Delivery and Storage Materials delivered to site shall be inspected for damage, unloaded, and stored with a minimum of handling. Materials shall not be stored directly on the ground. The inside of pipes and fittings shall be kept free of dirt and debris. Before, during, and after installation, plastic pipe and fittings shall be protected from any environment that would result in damage or deterioration to the material. Keep a copy of the manufacturer's instructions available at the construction site at all times and follow these instructions unless directed otherwise by the Contracting Officer. Solvents, solvent compounds, lubricants, elastomeric gaskets, and any similar materials required to install plastic pipe shall be stored in accordance with the manufacturer's recommendations and shall be discarded if the storage period exceeds the recommended shelf life. Solvents in use shall be discarded when the recommended pot life is exceeded. URS FOR EQM SECTION 33 40 00 Page 7 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 1.4.2 TYMX989345A FA3002-09-D-0002 TG02 Handling Materials shall be handled in a manner that ensures delivery to the trench in sound, undamaged condition. Pipe shall be carried to the trench, not dragged. PART 2 2.1 PRODUCTS PIPE FOR CULVERTS AND STORM DRAINS ************************************************************************** NOTE: Where the type of pipe is to be the Contractor's option, the types (with size, class, shape, strength, sheet thickness, or gauge) that are acceptable should be listed. The inapplicable types of pipe will be deleted. In specifying plastic, clay, and concrete pipe or aluminum alloy and steel pipe for culverts and storm drains, pipe of comparable strength for the various sizes should be specified. Where economically feasible or required by special conditions, cast iron soil pipe meeting the requirements of ASTM A74 may be used for culverts and storm drains. The pipe class, the type of joint, and installation procedures should be as specified in Section 33 30 00 SANITARY SEWERS and Section 33 34 00 FORCE MAINS AND INVERTED SIPHONS; SEWER. Refer to the appropriate NAVFAC Design Manual on storm drainage for general information on suitable piping materials. Additional information may be obtained from the "Life Cycle Cost for Drainage Structures," Technical Report GL-882-2 by the U.S. Army Corps of Engineers. Pipe materials which are known to be unsuitable for local conditions (i.e., corrosion, root penetration, etc.) should not be permitted for the project. However, consideration should be given to use of more effective protective coatings and jointing methods where economically feasible. In areas where problems with root penetration are anticipated, specify pipe which has the kind of joint which will successfully resist root penetration. Generally speaking, the more watertight the joint, the greater will be the resistance to root penetration. Rubber-gasketed and compression-type joints are considered to give the best performance for this application. American Society of Civil Engineers (ASCE) Manual No. 37, "Design and Construction of Sanitary and Storm Sewers," contains methods of calculation for structural requirements of pipe; from these, the required strengths for pipe of various materials may determined. Investigate external loads, including earth loads, truck loads, seismic loads, and impact, URS FOR EQM SECTION 33 40 00 Page 8 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 in the design stage of the project. Give special attention, in the design stage of the project, to plastic pipe materials, particularly with respect to superimposed external loads which could cause excessive deflection of the pipe. The degree of sidefill compaction should be considered realistically, particularly in marginal cases. See also the appendices to ASTM D2321. ************************************************************************** Pipe for culverts and storm drains shall be of the sizes indicated and shall conform to the requirements specified. 2.1.1 Concrete Pipe ************************************************************************** NOTE: The various classes designate different D-loads. D-load is defined as the minimum required three-edge test load on a pipe to produce a 0.01 inch crack and/or ultimate failure in pounds per linear foot per foot (no metric definition) of inside diameter. Where sulfate-resistant pipe is required and concrete pipe is to be an option, specify Type II or Type V cement. Specify Type II (moderate sulfate resisting) cement when water-soluble sulfates (as S04) in the soil are in the range of 0.1 to 0.2 percent and, for water, are in the range of 150 to 1,000 parts per million. Specify Type V (sulfate resisting) cement when soils contain in excess of 0.2 percent water-soluble sulfate and water samples contain in excess of 1,000 parts per million. In areas where reactive aggregates are known to occur, specify low alkali cement. The following are requirements for NAVFAC LANT projects: Pipe sizes under 300 mm (12 inch) diameter shall be nonreinforced concrete pipe. Pipe sizes 300 mm (12 inch) diameter through 600 mm (24 inch) diameter may be either reinforced or nonreinforced concrete pipe. Pipe sizes larger than 600 mm (24 inch) diameter shall be reinforced concrete pipe. ************************************************************************** Manufactured in accordance with and conforming to ASTM C76, Class [I] [II] [III] [IV] [V], or ASTM C655, 1250[_____] D-Load. 2.1.1.1 Reinforced Arch Culvert and Storm Drainpipe Manufactured in accordance with and conforming to ASTM C506, Class [A-II] [A-III] [A-IV]. 2.1.1.2 Reinforced Elliptical Culvert and Storm Drainpipe Manufactured in accordance with and conforming to ASTM C507. Horizontal elliptical pipe shall be Class [HE-A] [HE-I] [HE-II] [HE-III] [HE-IV]. Vertical elliptical pipe shall be Class [VE-II] [VE-III] [VE-IV] [VE-V] URS FOR EQM SECTION 33 40 00 Page 9 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 [VE-VI]. 2.1.1.3 Nonreinforced Pipe Manufactured in accordance with and conforming to ASTM C14, Class [1] [2] [3]. 2.1.1.4 Cast-In-Place Nonreinforced Conduit ************************************************************************** NOTE: This type conduit should not be used beneath structures, for drain crossings, adjacent to paved areas, or under high fills. ************************************************************************** ACI 346, except that testing shall be the responsibility of and at the expense of the Contractor. In the case of other conflicts between ACI 346 and project specifications, requirements of ACI 346 shall govern. 2.1.2 Perforated Piping 2.1.2.1 Concrete Pipe Manufactured in accordance with and conforming to ASTM C444, and applicable requirements of ASTM C14, Class [_____]. Steel Reinforced Polyethylene (SRPE) Pipe SRPE pipe will meet the requirements of ASTM F2562 8" - 120" diameter pipe and AASHTO M 20 (12" - 60" diameter pipe). 2.2 DRAINAGE STRUCTURES Flared End Sections Sections shall be of a standard design fabricated from zinc coated steel sheets meeting requirements of ASTM A929/A929M. 2.2.1 Precast Reinforced Concrete Box ************************************************************************** NOTE: Where sulfate-resistant pipe is required and concrete pipe is to be an option, the use of Type II or Type V cement will be specified. ************************************************************************** Manufactured in accordance with and conforming to ASTM C1433. 2.3 MISCELLANEOUS MATERIALS ************************************************************************** NOTE: The shape, size, thickness of sections, kinds of materials, and weights for frames, covers, and gratings for inlets and manholes, as well as the amount of waterway opening for inlets and gratings should be indicated on the drawings. The covers and gratings should be designed to have ample strength for the traffic conditions to which they may be subjected. Fixed, straight-type galvanized steel URS FOR EQM SECTION 33 40 00 Page 10 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 ladders should be provided for manholes over 3.66 m (12 feet) deep measured form top of grate to invert of outlet pipe. ************************************************************************** 2.3.1 Concrete ************************************************************************** NOTE: Reference should be made to other sections of the project specifications, as applicable, or pertinent requirements may be included in this section. The air contents specified are for concrete that will be subjected to freezing weather and the possible action of deicing chemicals. In climates where freezing is not a factor but where air entrainment is used in local commercial practice to improve the workability and placability of concrete, concrete having air content of 4.5 plus or minus 1.5 percent may be specified as Contractor's option to nonairentrained concrete. ************************************************************************** Unless otherwise specified, concrete and reinforced concrete shall conform to the requirements for 4000[_____] psi concrete under Section 03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE[03 30 00.00 10 CAST-IN-PLACE CONCRETE] [03 30 00 CAST-IN-PLACE CONCRETE]. The concrete mixture shall have air content by volume of concrete, based on measurements made immediately after discharge from the mixer, of 5 to 7 percent when maximum size of coarse aggregate exceeds 1-1/2 inches. Air content shall be determined in accordance with ASTM C231/C231M. The concrete covering over steel reinforcing shall not be less than 1 inch thick for covers and not less than 1-1/2 inches thick for walls and flooring. Concrete covering deposited directly against the ground shall have a thickness of at least 3 inches between steel and ground. Expansion-joint filler material shall conform to ASTM D1751, or ASTM D1752, or shall be resin-impregnated fiberboard conforming to the physical requirements of ASTM D1752. 2.3.2 Mortar Mortar for pipe joints, connections to other drainage structures, and brick or block construction shall conform to ASTM C270, Type M, except that the maximum placement time shall be 1 hour. The quantity of water in the mixture shall be sufficient to produce a stiff workable mortar but in no case shall exceed 0.5[_____] gallons of water per sack of cement. Water shall be clean and free of harmful acids, alkalis, and organic impurities. The mortar shall be used within 30 minutes after the ingredients are mixed with water. The inside of the joint shall be wiped clean and finished smooth. The mortar head on the outside shall be protected from air and sun with a proper covering until satisfactorily cured. 2.3.3 Precast Concrete Segmental Blocks Precast concrete segmental block shall conform to ASTM C139, not more than 8 inches thick, not less than 8 inches long, and of such shape that joints can be sealed effectively and bonded with cement mortar. URS FOR EQM SECTION 33 40 00 Page 11 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.3.4 TYMX989345A FA3002-09-D-0002 TG02 Brick Brick shall conform to ASTM C62, Grade SW; ASTM C55, Grade S-I or S-II; or ASTM C32, Grade MS. Mortar for jointing and plastering shall consist of one part portland cement and two parts fine sand. Lime may be added to the mortar in a quantity not more than 25 percent of the volume of cement. The joints shall be filled completely and shall be smooth and free from surplus mortar on the inside of the structure. Brick structures shall be plastered with 1/2 inch of mortar over the entire outside surface of the walls. For square or rectangular structures, brick shall be laid in stretcher courses with a header course every sixth course. For round structures, brick shall be laid radially with every sixth course a stretcher course. 2.3.5 Precast Reinforced Concrete Manholes ************************************************************************** NOTE: Rubber-type gasket joints should be specified only where watertightness is essential. ************************************************************************** Conform to ASTM C478. Joints between precast concrete risers and tops shall be [full-bedded in cement mortar and shall be smoothed to a uniform surface on both interior and exterior of the structure] [made with flexible watertight, rubber-type gaskets meeting the requirements of paragraph JOINTS ]. Prefabricated Corrugated Metal Manholes Manholes shall be of the type and design recommended by the manufacturer. Manholes shall be complete with frames and cover, or frames and gratings. 2.3.6 Frame and Cover for Gratings ************************************************************************** NOTE: The likelihood of bicycle traffic should be considered in the selection of the type of inlet cover configuration. ************************************************************************** Submit certification on the ability of frame and cover or gratings to carry the imposed live load. Frame and cover for gratings shall be cast gray iron, ASTM A48/A48M, Class 35B; cast ductile iron, ASTM A536, Grade 65-45-12; or cast aluminum, ASTM B26/B26M, Alloy 356.OT6. Weight, shape, size, and waterway openings for grates and curb inlets shall be as indicated on the plans. The word "Storm Sewer" shall be stamped or cast into covers so that it is plainly visible. 2.3.7 2.3.7.1 Joints Flexible Watertight Joints ************************************************************************** NOTE: This paragraph covers compression-type rubber-gasketed joints. When pipe requiring a pressure-type joint is specified, the requirements of this paragraph may not apply and the joint should be made in accordance with the specifications for the pipe. ************************************************************************** URS FOR EQM SECTION 33 40 00 Page 12 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 a. Materials: Flexible watertight joints shall be made with plastic or rubber-type gaskets for concrete pipe and with factory-fabricated resilient materials for clay pipe. The design of joints and the physical requirements for preformed flexible joint sealants shall conform to ASTM C990, and rubber-type gaskets shall conform to ASTM C443. Factory-fabricated resilient joint materials shall conform to ASTM C425. Gaskets shall have not more than one factory-fabricated splice, except that two factory-fabricated splices of the rubber-type gasket are permitted if the nominal diameter of the pipe being gasketed exceeds 54 inches. b. Test Requirements: Watertight joints shall be tested and shall meet test requirements of paragraph HYDROSTATIC TEST ON WATERTIGHT JOINTS. Rubber gaskets shall comply with the oil resistant gasket requirements of ASTM C443. Certified copies of test results shall be delivered to the Contracting Officer before gaskets or jointing materials are installed. Alternate types of watertight joint may be furnished, if specifically approved. External Sealing Bands Requirements for external sealing bands shall conform to ASTM C877. 2.3.7.2 Flexible Watertight, Gasketed Joints ************************************************************************** NOTE: The inapplicable type of gasket material should be deleted. Type 2A1 should be specified where specific resistance to the action of petroleum base oils is not required. Type 2B3 has specific requirements for oil resistance with low swell. Fill in blank for any other combination of Class and Grade required. ************************************************************************** a. Gaskets: When infiltration or exfiltration is a concern for pipe lines, the couplings may be required to have gaskets. The closed-cell expanded rubber gaskets shall be a continuous band approximately 7 inches wide and approximately 3/8 inch thick, meeting the requirements of ASTM D1056, Type 2 [A1] [B3] [_____], and shall have a quality retention rating of not less than 70 percent when tested for weather resistance by ozone chamber exposure, Method B of ASTM D1171. Rubber O-ring gaskets shall be 13/16 inch in diameter for pipe diameters of 36 inches or smaller and7/8 inch in diameter for larger pipe having 1/2 inch deep end corrugation. Rubber O-ring gaskets shall be 1-3/8 inches in diameter for pipe having 1 inch deep end corrugations. O-rings shall meet the requirements of ASTM C990 or ASTM C443. Preformed flexible joint sealants shall conform to ASTM C990, Type B. b. Connecting Bands: Connecting bands shall be of the type, size and sheet thickness of band, and the size of angles, bolts, rods and lugs as indicated or where not indicated as specified in the applicable standards or specifications for the pipe. Exterior rivet heads in the longitudinal seam under the connecting band shall be countersunk or the rivets shall be omitted and the seam welded. Watertight joints shall be tested and shall meet the test requirements of paragraph HYDROSTATIC TEST ON WATERTIGHT JOINTS. URS FOR EQM SECTION 33 40 00 Page 13 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 2.3.7.3 TYMX989345A FA3002-09-D-0002 TG02 Steel Reinforced Polyethylene (SRPE) Pipe SRPE joints shall meet the requirements of ASTM D3212. Flap Gates Flap Gates shall be [medium] [or] [heavy]-duty with [circular] [rectangular] opening and double-hinged. [Top pivot points shall be adjustable.] The seat shall be one-piece cast iron with a raised section around the perimeter of the waterway opening to provide the seating face. The seating face of the seat shall be [cast iron] [bronze] [stainless steel] [neoprene]. The cover shall be one-piece cast iron with necessary reinforcing rib, lifting eye for manual operation, and bosses to provide a pivot point connection with the links. The seating face of the cover shall be [cast iron] [bronze] [stainless steel] [neoprene]. Links or hinge arms shall be cast or ductile iron. Holes of pivot points shall be bronze bushed. All fasteners shall be either galvanized steel, bronze or stainless steel. 2.4 STEEL LADDER Steel ladder shall be provided where the depth of the storm drainage structure exceeds 12 feet. These ladders shall be not less than 16 inches in width, with 3/4 inch diameter rungs spaced 12 inches apart. The two stringers shall be a minimum 3/8 inch thick and 2-1/2 inches wide. Ladders and inserts shall be galvanized after fabrication in conformance with ASTM A123/A123M. DOWNSPOUT BOOTS Boots used to connect exterior downspouts to the storm-drainage system shall be of gray cast iron conforming to ASTM A48/A48M, Class 30B or 35B. Shape and size shall be as indicated. 2.5 RESILIENT CONNECTORS ************************************************************************** NOTE: Delete the requirement for resilient connectors when a watertight connection between pipe and manholes and inlets is not required. ************************************************************************** Flexible, watertight connectors used for connecting pipe to manholes and inlets shall conform to ASTM C923. 2.6 HYDROSTATIC TEST ON WATERTIGHT JOINTS ************************************************************************** NOTE: When the quantity of pipe required for a project is so small that the provisions for testing and certification of watertightness of joints appears to be economically unfeasible, such provisions should be deleted. ************************************************************************** 2.6.1 Concrete, Clay, PVC, PE, SRPE and PP Pipe A hydrostatic test shall be made on the watertight joint types as proposed. Only one sample joint of each type needs testing; however, if URS FOR EQM SECTION 33 40 00 Page 14 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 the sample joint fails because of faulty design or workmanship, an additional sample joint may be tested. During the test period, gaskets or other jointing material shall be protected from extreme temperatures which might adversely affect the performance of such materials. Performance requirements for joints in reinforced and nonreinforced concrete pipe shall conform to ASTM C990 or ASTM C443. Test requirements for joints in clay pipe shall conform to ASTM C425. Test requirements for joints in PVC, PE, and PP plastic pipe shall conform to ASTM D3212. EROSION CONTROL RIPRAP Provide nonerodible rock not exceeding 15 inches in its greatest dimension and choked with sufficient small rocks to provide a dense mass with a minimum thickness of [8 inches] [as indicated]. PART 3 3.1 EXECUTION EXCAVATION FOR PIPE CULVERTS, STORM DRAINS, AND DRAINAGE STRUCTURES ************************************************************************** NOTE: Reference should be made to other sections of the project specifications, as applicable, or pertinent requirements may be included in this section. ************************************************************************** Excavation of trenches, and for appurtenances and backfilling for culverts and storm drains, shall be in accordance with the applicable portions of Section 31 00 00 EARTHWORK and the requirements specified below. 3.1.1 Trenching ************************************************************************** NOTE: Economic considerations should determine the width of trench to be used in the design analysis and to be specified for construction. Where it is more economical to control trench width and thereby use less costly pipe, the width of the trench shall vary with the pipe diameter and should be held to a minimum consistent with the space required for proper installation of the pipe and the backfill at the sides of the pipe. Where the sides of the excavations are to be supported, proper allowance should be made for the space occupied by the sheeting and bracing. ************************************************************************** The width of trenches at any point below the top of the pipe shall be not greater than the outside diameter of the pipe plus [_____] inches to permit satisfactory jointing and thorough tamping of the bedding material under and around the pipe. Sheeting and bracing, where required, shall be placed within the trench width as specified, without any overexcavation. Where trench widths are exceeded, redesign with a resultant increase in cost of stronger pipe or special installation procedures will be necessary. Cost of this redesign and increased cost of pipe or installation shall be borne by the Contractor without additional cost to the Government. URS FOR EQM SECTION 33 40 00 Page 15 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.1.2 TYMX989345A FA3002-09-D-0002 TG02 Removal of Rock ************************************************************************** NOTE: Unless otherwise specified, material used to replace unstable material or rock excavation should be compacted to a minimum density of 90 percent for cohesive soils and 95 percent for noncohesive soils, as determined by ASTM D1557. ************************************************************************** Rock in either ledge or boulder formation shall be replaced with suitable materials to provide a compacted earth cushion having a thickness between unremoved rock and the pipe of at least 8 inches or 1/2 inch for each foot of fill over the top of the pipe, whichever is greater, but not more than three-fourths the nominal diameter of the pipe. Where bell-and-spigot pipe is used, the cushion shall be maintained under the bell as well as under the straight portion of the pipe. Rock excavation shall be as specified and defined in Section 31 00 00 EARTHWORK. Removal of Unstable Material ************************************************************************** NOTE: Coordinate with preceding paragraph. ************************************************************************** Where wet or otherwise unstable soil incapable of properly supporting the pipe, as determined by the Contracting Officer, is unexpectedly encountered in the bottom of a trench, such material shall be removed to the depth required and replaced to the proper grade with select granular material, compacted as provided in paragraph BACKFILLING. When removal of unstable material is due to the fault or neglect of the Contractor while performing shoring and sheeting, water removal, or other specified requirements, such removal and replacement shall be performed at no additional cost to the Government. 3.2 BEDDING ************************************************************************** NOTE: It should be noted that pipe cover requirements will be different for different types of bedding. ************************************************************************** The bedding surface for the pipe shall provide a firm foundation of uniform density throughout the entire length of the pipe. 3.2.1 Concrete Pipe Requirements When no bedding class is specified or detailed on the drawings, concrete pipe shall be bedded in granular material minimum 4 inch in depth in trenches with soil foundation. Depth of granular bedding in trenches with rock foundation shall be 1/2 inch in depth per foot of depth of fill, minimum depth of bedding shall be 8 inch up to maximum depth of 24 inches. The middle third of the granular bedding shall be loosely placed. Bell holes and depressions for joints shall be removed and formed so entire barrel of pipe is uniformly supported. The bell hole and depressions for the joints shall be not more than the length, depth, and width required for properly making the particular type of joint. URS FOR EQM SECTION 33 40 00 Page 16 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.3 TYMX989345A FA3002-09-D-0002 TG02 PLACING PIPE ************************************************************************** NOTE: The Contractor should be required to perform deflection testing when warranted by the scope and size of the project. ************************************************************************** Each pipe shall be thoroughly examined before being laid; defective or damaged pipe shall not be used. Pipelines shall be laid to the grades and alignment indicated. Proper facilities shall be provided for lowering sections of pipe into trenches. Lifting lugs in vertically elongated metal pipe shall be placed in the same vertical plane as the major axis of the pipe. Pipe shall not be laid in water, and pipe shall not be laid when trench conditions or weather are unsuitable for such work. Diversion of drainage or dewatering of trenches during construction shall be provided as necessary. Deflection of installed flexible pipe shall not exceed the following limits: TYPE OF PIPE MAXIMUM ALLOWABLE DEFLECTION (percent) Note post installation requirements of paragraph DEFLECTION TESTING in PART 3 of this specification for all pipe products including deflection testing requirements for flexible pipe. 3.3.1 Concrete, Clay, PVC, Ribbed PVC, Ductile Iron and Cast-Iron Pipe Laying shall proceed upgrade with spigot ends of bell-and-spigot pipe and tongue ends of tongue-and-groove pipe pointing in the direction of the flow. Elliptical and Elliptical Reinforced Concrete Pipe The manufacturer's reference lines, designating the top of the pipe, shall be within 5 degrees of a vertical plane through the longitudinal axis of the pipe, during placement. Damage to or misalignment of the pipe shall be prevented in all backfilling operations. 3.3.2 Multiple Culverts ************************************************************************** NOTE: Where encasement or other special conditions are specified, minimum spacing as specified in this paragraph should not apply. ************************************************************************** Where multiple lines of pipe are installed, adjacent sides of pipe shall be at least half the nominal pipe diameter or 3 feet apart, whichever is less. URS FOR EQM SECTION 33 40 00 Page 17 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Jacking Pipe Through Fills Methods of operation and installation for jacking pipe through fills shall conform to requirements specified in Volume 1, Chapter 1, Part 4 of AREMA Eng Man. 3.4 JOINTING ************************************************************************** NOTE: Where watertightness is not required, watertight and at least one other type of joint should be included for each type of pipe required. Where watertightness is essential, delete paragraphs Cement-Mortar Bell-and-Spigot Joint through Plastic Sealing Compound Joints for Tongue-and-Grooved Pipe below. ************************************************************************** 3.4.1 3.4.1.1 Concrete and Clay Pipe Cement-Mortar Bell-and-Spigot Joint The first pipe shall be bedded to the established grade line, with the bell end placed upstream. The interior surface of the bell shall be thoroughly cleaned with a wet brush and the lower portion of the bell filled with mortar as required to bring inner surfaces of abutting pipes flush and even. The spigot end of each subsequent pipe shall be cleaned with a wet brush and uniformly matched into a bell so that sections are closely fitted. After each section is laid, the remainder of the joint shall be filled with mortar, and a bead shall be formed around the outside of the joint with sufficient additional mortar. If mortar is not sufficiently stiff to prevent appreciable slump before setting, the outside of the joint shall be wrapped or bandaged with cheesecloth to hold mortar in place. 3.4.1.2 Cement-Mortar Oakum Joint for Bell-and-Spigot Pipe A closely twisted gasket shall be made of jute or oakum of the diameter required to support the spigot end of the pipe at the proper grade and to make the joint concentric. Joint packing shall be in one piece of sufficient length to pass around the pipe and lap at top. This gasket shall be thoroughly saturated with neat cement grout. The bell of the pipe shall be thoroughly cleaned with a wet brush, and the gasket shall be laid in the bell for the lower third of the circumference and covered with mortar. The spigot of the pipe shall be thoroughly cleaned with a wet brush, inserted in the bell, and carefully driven home. A small amount of mortar shall be inserted in the annular space for the upper two-thirds of the circumference. The gasket shall be lapped at the top of the pipe and driven home in the annular space with a caulking tool. The remainder of the annular space shall be filled completely with mortar and beveled at an angle of approximately 45 degrees with the outside of the bell. If mortar is not sufficiently stiff to prevent appreciable slump before setting, the outside of the joint thus made shall be wrapped with cheesecloth. Placing of this type of joint shall be kept at least five joints behind laying operations. 3.4.1.3 Cement-Mortar Diaper Joint for Bell-and-Spigot Pipe The pipe shall be centered so that the annular space is uniform. The annular space shall be caulked with jute or oakum. Before caulking, the URS FOR EQM SECTION 33 40 00 Page 18 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 inside of the bell and the outside of the spigot shall be cleaned. a. Diaper Bands: Diaper bands shall consist of heavy cloth fabric to hold grout in place at joints and shall be cut in lengths that extend one-eighth of the circumference of pipe above the spring line on one side of the pipe and up to the spring line on the other side of the pipe. Longitudinal edges of fabric bands shall be rolled and stitched around two pieces of wire. Width of fabric bands shall be such that after fabric has been securely stitched around both edges on wires, the wires will be uniformly spaced not less than 8 inches apart. Wires shall be cut into lengths to pass around pipe with sufficient extra length for the ends to be twisted at top of pipe to hold the band securely in place; bands shall be accurately centered around lower portion of joint. b. Grout: Grout shall be poured between band and pipe from the high side of band only, until grout rises to the top of band at the spring line of pipe, or as nearly so as possible, on the opposite side of pipe, to ensure a thorough sealing of joint around the portion of pipe covered by the band. Silt, slush, water, or polluted mortar grout forced up on the lower side shall be forced out by pouring, and removed. c. Remainder of Joint: The remaining unfilled upper portion of the joint shall be filled with mortar and a bead formed around the outside of this upper portion of the joint with a sufficient amount of additional mortar. The diaper shall be left in place. Placing of this type of joint shall be kept at least five joints behind actual laying of pipe. No backfilling around joints shall be done until joints have been fully inspected and approved. 3.4.1.4 Cement-Mortar Tongue-and-Groove Joint The first pipe shall be bedded carefully to the established grade line with the groove upstream. A shallow excavation shall be made underneath the pipe at the joint and filled with mortar to provide a bed for the pipe. The grooved end of the first pipe shall be thoroughly cleaned with a wet brush, and a layer of soft mortar applied to the lower half of the groove. The tongue of the second pipe shall be cleaned with a wet brush; while in horizontal position, a layer of soft mortar shall be applied to the upper half of the tongue. The tongue end of the second pipe shall be inserted in the grooved end of the first pipe until mortar is squeezed out on interior and exterior surfaces. Sufficient mortar shall be used to fill the joint completely and to form a bead on the outside. 3.4.1.5 Cement-Mortar Diaper Joint for Tongue-and-Groove Pipe The joint shall be of the type described for cement-mortar tongue-and-groove joint in this paragraph, except that the shallow excavation directly beneath the joint shall not be filled with mortar until after a gauze or cheesecloth band dipped in cement mortar has been wrapped around the outside of the joint. The cement-mortar bead at the joint shall be at least 1/2 inch, thick and the width of the diaper band shall be at least 8 inches. The diaper shall be left in place. Placing of this type of joint shall be kept at least five joints behind the actual laying of the pipe. Backfilling around the joints shall not be done until the joints have been fully inspected and approved. URS FOR EQM SECTION 33 40 00 Page 19 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Plastic Sealing Compound Joints for Tongue-and-Grooved Pipe Sealing compounds shall follow the recommendation of the particular manufacturer in regard to special installation requirements. Surfaces to receive lubricants, primers, or adhesives shall be dry and clean. Sealing compounds shall be affixed to the pipe not more than 3 hours prior to installation of the pipe, and shall be protected from the sun, blowing dust, and other deleterious agents at all times. Sealing compounds shall be inspected before installation of the pipe, and any loose or improperly affixed sealing compound shall be removed and replaced. The pipe shall be aligned with the previously installed pipe, and the joint pulled together. If, while making the joint with mastic-type sealant, a slight protrusion of the material is not visible along the entire inner and outer circumference of the joint when the joint is pulled up, the pipe shall be removed and the joint remade. After the joint is made, all inner protrusions shall be cut off flush with the inner surface of the pipe. If non-mastic-type sealant material is used, the "Squeeze-Out" requirement above will be waived. 3.4.1.1 Flexible Watertight Joints Gaskets and jointing materials shall be as recommended by the particular manufacturer in regard to use of lubricants, cements, adhesives, and other special installation requirements. Surfaces to receive lubricants, cements, or adhesives shall be clean and dry. Gaskets and jointing materials shall be affixed to the pipe not more than 24 hours prior to the installation of the pipe, and shall be protected from the sun, blowing dust, and other deleterious agents at all times. Gaskets and jointing materials shall be inspected before installing the pipe; any loose or improperly affixed gaskets and jointing materials shall be removed and replaced. The pipe shall be aligned with the previously installed pipe, and the joint pushed home. If, while the joint is being made the gasket becomes visibly dislocated the pipe shall be removed and the joint remade. External Sealing Band Joint for Noncircular Pipe Surfaces to receive sealing bands shall be dry and clean. Bands shall be installed in accordance with manufacturer's recommendations. 3.5 DRAINAGE STRUCTURES ************************************************************************** NOTE: Coordinate with paragraph MISCELLANEOUS MATERIALS. ************************************************************************** 3.5.1 Manholes and Inlets ************************************************************************** NOTE: Prepare the required paragraph or section covering the essential requirements for reinforced concrete inlet construction and insert the required reference to the paragraph or section prepared to cover these items. Delete the requirement for flexible watertight connectors (last sentence) when a watertight connection between pipe and manholes and inlets is not required. ************************************************************************** URS FOR EQM SECTION 33 40 00 Page 20 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 Construction shall be of reinforced concrete, plain concrete, brick, precast reinforced concrete, precast concrete segmental blocks, prefabricated corrugated metal, or bituminous coated corrugated metal; complete with frames and covers or gratings; and with fixed galvanized steel ladders where indicated. Pipe studs and junction chambers of prefabricated corrugated metal manholes shall be fully bituminous-coated and paved when the connecting branch lines are so treated. Pipe connections to concrete manholes and inlets shall be made with flexible, watertight connectors. Walls and Headwalls ************************************************************************** NOTE: Dry-stone masonry may be specified and used for crib construction and/or sloping retaining walls that will sustain little or no earth pressure. ************************************************************************** Construction shall be as indicated. 3.6 STEEL LADDER INSTALLATION Ladder shall be adequately anchored to the wall by means of steel inserts spaced not more than 6 feet vertically, and shall be installed to provide at least 6 inches of space between the wall and the rungs. The wall along the line of the ladder shall be vertical for its entire length. 3.7 BACKFILLING ************************************************************************** NOTE: The thickness of layers of backfill and the degree of compaction required to prevent undesirable settlement should be determined by soil conditions and the job compaction requirements. When rigid pipe is to be placed under high fills, the imperfect trench method of installation may be specified. ************************************************************************** 3.7.1 Backfilling Pipe in Trenches After the pipe has been properly bedded, selected material from excavation or borrow, at a moisture content that will facilitate compaction, shall be placed along both sides of pipe in layers not exceeding 6 inches in compacted depth. The backfill shall be brought up evenly on both sides of pipe for the full length of pipe. The fill shall be thoroughly compacted under the haunches of the pipe. Each layer shall be thoroughly compacted with mechanical tampers or rammers. This method of filling and compacting shall continue until the fill has reached an elevation equal to the midpoint (spring line) of RCP or has reached an elevation of at least 12 inches above the top of the pipe for flexible pipe. The remainder of the trench shall be backfilled and compacted by spreading and rolling or compacted by mechanical rammers or tampers in layers not exceeding 6[_____] inches. Tests for density shall be made as necessary to ensure conformance to the compaction requirements specified below. Where it is necessary, in the opinion of the Contracting Officer, that sheeting or portions of bracing used be left in place, the contract will be adjusted accordingly. Untreated sheeting shall not be left in place beneath structures or pavements. URS FOR EQM SECTION 33 40 00 Page 21 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS 3.7.2 TYMX989345A FA3002-09-D-0002 TG02 Backfilling Pipe in Fill Sections For pipe placed in fill sections, backfill material and the placement and compaction procedures shall be as specified below. The fill material shall be uniformly spread in layers longitudinally on both sides of the pipe, not exceeding 6 inches in compacted depth, and shall be compacted by rolling parallel with pipe or by mechanical tamping or ramming. Prior to commencing normal filling operations, the crown width of the fill at a height of 12 inches above the top of the pipe shall extend a distance of not less than twice the outside pipe diameter on each side of the pipe or 12 feet, whichever is less. After the backfill has reached at least 12 inches above the top of the pipe, the remainder of the fill shall be placed and thoroughly compacted in layers not exceeding 6[_____] inches. Use select granular material for this entire region of backfill for flexible pipe installations. 3.7.3 Movement of Construction Machinery When compacting by rolling or operating heavy equipment parallel with the pipe, displacement of or injury to the pipe shall be avoided. Movement of construction machinery over a culvert or storm drain at any stage of construction shall be at the Contractor's risk. Any damaged pipe shall be repaired or replaced. 3.7.4 Compaction 3.7.4.1 General Requirements Cohesionless materials include gravels, gravel-sand mixtures, sands, and gravelly sands. Cohesive materials include clayey and silty gravels, gravel-silt mixtures, clayey and silty sands, sand-clay mixtures, clays, silts, and very fine sands. When results of compaction tests for moisture-density relations are recorded on graphs, cohesionless soils will show straight lines or reverse-shaped moisture-density curves, and cohesive soils will show normal moisture-density curves. 3.7.4.2 Minimum Density ************************************************************************** NOTE: For culverts or storm drains installed beneath structures (including embankments) that have critical stability requirements or settlement limitations, the maximum density requirements should be increased as necessary. If only a cohesive soil or only a cohesionless material will be used as backfill, the inapplicable value will be deleted. ************************************************************************** Backfill over and around the pipe and backfill around and adjacent to drainage structures shall be compacted at the approved moisture content to the following applicable minimum density, which will be determined as specified below. a. Under airfield and heliport pavements, paved roads, streets, parking areas, and similar-use pavements including adjacent shoulder areas, the density shall be not less than 90 percent of maximum density for cohesive material and 95 percent of maximum density for cohesionless material, up to the elevation where requirements for pavement subgrade URS FOR EQM SECTION 33 40 00 Page 22 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 materials and compaction shall control. b. Under unpaved or turfed traffic areas, density shall not be less than 90 percent of maximum density for cohesive material and 95 percent of maximum density for cohesionless material. c. Under nontraffic areas, density shall be not less than that of the surrounding material. 3.7.5 Determination of Density Testing is the responsibility of the Contractor and performed at no additional cost to the Government. Testing shall be performed by an approved commercial testing laboratory or by the Contractor subject to approval. Tests shall be performed in sufficient number to ensure that specified density is being obtained. Laboratory tests for moisture-density relations shall be made in accordance with ASTM D1557 except that mechanical tampers may be used provided the results are correlated with those obtained with the specified hand tamper. Field density tests shall be determined in accordance with ASTM D2167 or ASTM D6938. When ASTM D6938 is used, the calibration curves shall be checked and adjusted, if necessary, using the sand cone method as described in paragraph Calibration of the referenced publications. ASTM D6938 results in a wet unit weight of soil and ASTM D6938 shall be used to determine the moisture content of the soil. The calibration curves furnished with the moisture gauges shall be checked along with density calibration checks as described in ASTM D6938. Test results shall be furnished the Contracting Officer. The calibration checks of both the density and moisture gauges shall be made at the beginning of a job on each different type of material encountered and at intervals as directed. 3.8 3.8.1 PIPELINE TESTING Leakage Tests ************************************************************************** NOTE: When the quantity of pipe required for a project is so small that the provisions for testing and certification of watertightness of joints appears to be economically unfeasible, such provisions should be deleted. Select appropriate leakage rate. Delete paragraph when watertight joints are not required. ************************************************************************** Lines shall be tested for leakage by low pressure air or water testing or exfiltration tests, as appropriate. Low pressure air testing for concrete pipes shall conform to ASTM C969. Testing of individual joints for leakage by low pressure air or water shall conform to ASTM C1103. Prior to exfiltration tests, the trench shall be backfilled up to at least the lower half of the pipe. If required, sufficient additional backfill shall be placed to prevent pipe movement during testing, leaving the joints uncovered to permit inspection. Visible leaks encountered shall be corrected regardless of leakage test results. When the water table is 2 feet or more above the top of the pipe at the upper end of the pipeline section to be tested, infiltration shall be measured using a suitable weir URS FOR EQM SECTION 33 40 00 Page 23 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 or other device acceptable to the Contracting Officer. An exfiltration test shall be made by filling the line to be tested with water so that a head of at least 2 feet is provided above both the water table and the top of the pipe at the upper end of the pipeline to be tested. The filled line shall be allowed to stand until the pipe has reached its maximum absorption, but not less than 4 hours. After absorption, the head shall be reestablished. The amount of water required to maintain this water level during a 2-hour test period shall be measured. Leakage as measured by the exfiltration test shall not exceed [ 250 gallons per inch in diameter per mile of pipeline per day] [ 0.2 gallons per inch in diameter per 100 feet of pipeline per hour]. When leakage exceeds the maximum amount specified, satisfactory correction shall be made and retesting accomplished. 3.8.2 Deflection Testing ************************************************************************** NOTE: Delete this paragraph when no flexible piping has been allowed for the project. Specify only when warranted by scope or size of project or when a high degree of watertightness is required. Delete for all NAVFAC LANT projects. ************************************************************************** No sooner than 30 days after completion of installation and final backfill, an initial post installation inspection shall be accomplished. Clean or flush all lines prior to inspection. Perform a deflection test on entire length of installed flexible pipeline on completion of work adjacent to and over the pipeline, including leakage tests, backfilling, placement of fill, grading, paving, concreting, and any other superimposed loads. Deflection of pipe in the installed pipeline under external loads shall not exceed limits in paragraph PLACING PIPE above as percent of the average inside diameter of pipe. Determine whether the allowable deflection has been exceeded by use of a laser profiler or mandrel. a. Laser Profiler Inspection: If deflection readings in excess of the allowable deflection of average inside diameter of pipe are obtained, remove pipe which has excessive deflection, and replace with new pipe. Initial post installation inspections of the pipe interior with laser profiling equipment shall utilize low barrel distortion video equipment for pipe sizes 48 inches or less. Use a camera with lighting suitable to allow a clear picture of the entire periphery of the pipe interior. Center the camera in the pipe both vertically and horizontally and be able to pan and tilt to a 90 degree angle with the axis of the pipe rotating 360 degrees. Use equipment to move the camera through the pipe that will not obstruct the camera's view or interfere with proper documentation of the pipe's condition. The video image shall be clear, focused, and relatively free from roll static or other image distortion qualities that would prevent the reviewer from evaluating the condition of the pipe. For initial post installation inspections for pipe sizes larger than 48 inches, visual inspection shall be completed of the pipe interior. b. Pull-Through Device Inspection: Pass the pull-through device through each run of pipe by pulling it by hand. If deflection readings in excess of the allowable deflection of average inside diameter of pipe are obtained, retest pipe by a run from the opposite direction. If retest continues to show excess allowable deflections of the average inside diameter of pipe, remove pipe which has excessive deflection, URS FOR EQM SECTION 33 40 00 Page 24 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 replace with new pipe, and completely retest in same manner and under same conditions. Pull-through device: The mandrel shall be rigid, nonadjustable having a minimum of 9 fins, including pulling rings at each end, engraved with the nominal pipe size and mandrel outside diameter. The mandrel shall be 5 percent less than the certified-actual pipe diameter for Plastic Pipe, 5 percent less than the certified-actual pipe diameter for Corrugated Steel and Aluminum Alloy, 3 percent less than the certified-actual pipe diameter for Concrete-Lined Corrugated Steel and Ductile Iron Culvert provided by manufacturer. When mandrels are utilized to verify deflection of flexible pipe products, the Government will verify the mandrel OD through the use of proving rings that are manufactured with an opening that is certified to be as shown above. c. Deflection measuring device: Officer prior to use. d. Warranty period test: Pipe found to have a deflection of greater than allowable deflection in paragraph PLACING PIPE above, just prior to end of one-year warranty period shall be replaced with new pipe and tested as specified for leakage and deflection. Inspect 100 percent of all pipe systems under the travel lanes, including curb and gutter. Random inspections of the remaining pipe system outside of the travel lanes shall represent at least 10 percent of the total pipe footage of each pipe size. Inspections shall be made, depending on the pipe size, with video camera or visual observations. In addition, for flexible pipe installations, perform deflection testing on 100 percent of all pipes under the travel lanes, including curb and gutter, with either a laser profiler or 9-fin mandrel. For flexible pipe, random deflection inspections of the pipe system outside of the travel lanes shall represent at least 10 percent of the total pipe footage of each pipe size. When mandrels are utilized to verify deflection of flexible pipe products during the final post installation inspection, the Government will verify the mandrel OD through the use of proving rings. 3.8.3 Shall be approved by the Contracting Post-Installation Inspection Check each reinforced concrete pipe installation for joint separations, soil migration through the joint, cracks greater than 0.01 inches, settlement and alignment. Check each flexible pipe (HDPE, PVC, CMP, PP) for rips, tears, joint separations, soil migration through the joint, cracks, localized bucking, bulges, settlement and alignment. a. Replace pipes having cracks greater than 0.1 inches in width or deflection greater than 5 percent deflection. An engineer shall evaluate all pipes with cracks greater than 0.01 inches but less than 0.10 inches to determine if any remediation or repair is required. RCP with crack width less than 0.10 inches and located in a non-corrosive environment (pH 5.5) are generally acceptable. Repair or replace any pipe with crack exhibiting displacement across the crack, exhibiting bulges, creases, tears, spalls, or delamination. b. Reports: The deflection results and final post installation inspection report shall include: a copy of all video taken, pipe location identification, equipment used for inspection, inspector name, deviation from design, grade, deviation from line, deflection and deformation of flexible pipe systems, inspector notes, condition of joints, condition of pipe wall (e.g. distress, cracking, wall damage dents, bulges, creases, tears, holes, etc.). URS FOR EQM SECTION 33 40 00 Page 25 65% - 01/23/2015 REPAIR/REPLACE TAXIWAY G/G1 JBSA - RANDOLPH AFB, TEXAS TYMX989345A FA3002-09-D-0002 TG02 FIELD PAINTING [After installation, clean cast-iron frames, covers, gratings, and steps not buried in masonry or concrete to bare metal of mortar, rust, grease, dirt, and other deleterious materials and apply a coat of bituminous paint.] [After installation, clean steel covers and steel or concrete frames not buried in masonry or concrete to bare metal of mortar, dirt, grease, and other deleterious materials. Apply a coat of primer, [_____], to a minimum dry film thickness of [_____] mil; and apply a top coat, [_____] to a minimum dry film thickness of [_____] mils, color optional. Painting shall conform to Section 09 90 00 PAINTS AND COATINGS.] Do not paint surfaces subject to abrasion. -- End of Section -- URS FOR EQM SECTION 33 40 00 Page 26 65% - 01/23/2015 CONTRACT NO. SUBMITTAL REGISTER TITLE AND LOCATION FA3002-09-D-0002 CONTRACTOR Repair/Replace Taxiway G/G1 A C T I V I T Y T R A N S M I T T A L N O (a) S P E C N O S E C T ITEM SUBMITTED P A R A G# R A P H (b) (c) (d) (e) 01 33 00 02 41 00 03 30 53 SUBMITTAL FORM,Jan 96 DESCRIPTION SD-01 Preconstruction Submittals Submittal Register SD-01 Preconstruction Submittals Existing Conditions SD-07 Certificates Demolition Plan Notification SD-11 Closeout Submittals Receipts SD-02 Shop Drawings Installation Drawings SD-03 Product Data Air-Entraining Admixture Water-Reducing or Retarding Admixture Curing Materials Batching and Mixing Equipment Conveying and Placing Concrete Formwork Mix Design Data Ready-Mix Concrete Curing Compound Reinforcing Steel SD-06 Test Reports Aggregates Concrete Mixture Proportions C L A S S I F I C A T I O N G 1.11 G 1.2.1 1.7 G G 1.5 G CONTRACTOR ACTION O R A C T I O N A / E R E V W R (f) 1.7 CONTRACTOR: SCHEDULE DATES G O V T SUBMIT (g) APPROVAL MATERIAL NEEDED NEEDED BY BY (h) (i) APPROVING AUTHORITY A C T I O N DATE FWD TO APPR AUTH/ C O D E DATE OF ACTION (j) (k) DATE RCD DATE FWD DATE RCD FROM TO OTHER FROM OTH CONTR REVIEWER REVIEWER (l) (m) (n) MAILED TO CONTR/ C O D E DATE OF ACTION DATE RCD FRM APPR AUTH REMARKS (o) (p) (q) (r) 2.2.3.1 2.2.3.2 2.2.8 3.1.3.3 3.2 2.2.6 2.3 2.3 2.4.1 2.2.2 2.1.3 G G PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 7 PAGES CONTRACT NO. SUBMITTAL REGISTER TITLE AND LOCATION FA3002-09-D-0002 CONTRACTOR Repair/Replace Taxiway G/G1 A C T I V I T Y T R A N S M I T T A L N O (a) S P E C N O S E C T ITEM SUBMITTED P A R A G# R A P H (b) (c) (d) (e) 03 30 53 DESCRIPTION Compressive Strength Testing Slump Air Content Water SD-07 Certificates Cementitious Materials Pozzolan Aggregates SD-08 Manufacturer’s Instructions Curing Compound 03 40 00.00 10 SD-01 Preconstruction Submittals Quality Control Procedures SD-02 Shop Drawings Standard Precast Units Custom-Made Precast Units SD-03 Product Data Standard Precast Units Proprietary Precast Units Embedded Items Accessories SD-05 Design Data Design Calculations Concrete Mix Proportions SD-06 Test Reports Test Reports SD-07 Certificates SUBMITTAL FORM,Jan 96 3.8.3 3.8.3 3.8.3 2.2.4 CONTRACTOR: SCHEDULE DATES G O V T C L A S S I F I C A T I O N CONTRACTOR ACTION O R A C T I O N A / E R E V W R (f) SUBMIT (g) APPROVAL MATERIAL NEEDED NEEDED BY BY (h) (i) APPROVING AUTHORITY A C T I O N DATE FWD TO APPR AUTH/ C O D E DATE OF ACTION (j) (k) DATE RCD DATE FWD DATE RCD FROM TO OTHER FROM OTH CONTR REVIEWER REVIEWER (l) (m) (n) MAILED TO CONTR/ C O D E DATE OF ACTION DATE RCD FRM APPR AUTH REMARKS (o) (p) (q) (r) G G 2.2.1 2.2.2 2.4.1 1.4.2.2 1.2.1 1.2.2 G G 1.2.1 1.2.3 3.1.3 2.1.10 1.2.2 1.2.5.1 1.4.2.4 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 7 PAGES CONTRACT NO. SUBMITTAL REGISTER TITLE AND LOCATION FA3002-09-D-0002 CONTRACTOR Repair/Replace Taxiway G/G1 A C T I V I T Y T R A N S M I T T A L N O (a) S P E C N O S E C T ITEM SUBMITTED P A R A G# R A P H (b) (c) (d) (e) DESCRIPTION 03 40 00.00 10 Quality Control Procedures 31 00 00 SD-03 Product Data Utilization of Excavated Materials Rock Excavation Opening of any Excavation or Borrow Pit Shoulder Construction SD-06 Test Reports Testing Borrow Site Testing SD-07 Certificates Testing 32 01 13 SD-03 Product Data Waybills and Delivery Tickets Equipment List Inspection Reports SD-04 Samples Bituminous Materials Fog Seal SD-06 Test Reports Tests 32 01 19 SD-03 Product Data Manufacturer's Recommendations Equipment SD-04 Samples SUBMITTAL FORM,Jan 96 CONTRACTOR: SCHEDULE DATES G O V T C L A S S I F I C A T I O N CONTRACTOR ACTION O R A C T I O N A / E R E V W R (f) SUBMIT (g) APPROVAL MATERIAL NEEDED NEEDED BY BY (h) (i) APPROVING AUTHORITY A C T I O N DATE FWD TO APPR AUTH/ C O D E DATE OF ACTION (j) (k) DATE RCD DATE FWD DATE RCD FROM TO OTHER FROM OTH CONTR REVIEWER REVIEWER (l) (m) (n) MAILED TO CONTR/ C O D E DATE OF ACTION DATE RCD FRM APPR AUTH REMARKS (o) (p) (q) (r) 1.4.2.2 3.8 1.6.1.2 3.4 G 3.13 3.16 2.1 3.16 1.1.3 1.3.1 3.2.3 1.5.2 2.1 G G 3.1 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 7 PAGES CONTRACT NO. SUBMITTAL REGISTER TITLE AND LOCATION FA3002-09-D-0002 CONTRACTOR Repair/Replace Taxiway G/G1 A C T I V I T Y T R A N S M I T T A L N O (a) S P E C N O S E C T ITEM SUBMITTED P A R A G# R A P H (b) (c) (d) (e) 32 01 19 32 11 23 32 11 33 SUBMITTAL FORM,Jan 96 DESCRIPTION Materials SD-06 Test Reports Certified copies of the test reports SD-03 Product Data Plant, Equipment, and Tools Waybills and Delivery Tickets SD-06 Test Reports Sampling and Testing Field Density Tests SD-04 Samples Rigid pavement base course SD-05 Design Data Mix design Job-mix formula SD-06 Test Reports plasticity index plasticity index Sieve analysis Compressive strength Compressive strength weight loss moisture-density Liquid limit Sieve analysis of combined material C L A S S I F I C A T I O N G 1.4.1 G CONTRACTOR ACTION O R A C T I O N A / E R E V W R (f) 1.4.1 CONTRACTOR: SCHEDULE DATES G O V T SUBMIT (g) APPROVAL MATERIAL NEEDED NEEDED BY BY (h) (i) APPROVING AUTHORITY A C T I O N DATE FWD TO APPR AUTH/ C O D E DATE OF ACTION (j) (k) DATE RCD DATE FWD DATE RCD FROM TO OTHER FROM OTH CONTR REVIEWER REVIEWER (l) (m) (n) MAILED TO CONTR/ C O D E DATE OF ACTION DATE RCD FRM APPR AUTH REMARKS (o) (p) (q) (r) 2.1 1.1.4 1.5 1.5.2.4 G G 2.2.1.1 2.5 2.5 3.7.2.1 3.7.2.1 2.4.1 2.4.1 2.4.3 2.5 3.7.2.1 3.7.2.1 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 7 PAGES CONTRACT NO. SUBMITTAL REGISTER TITLE AND LOCATION FA3002-09-D-0002 CONTRACTOR Repair/Replace Taxiway G/G1 A C T I V I T Y T R A N S M I T T A L N O (a) S P E C N O S E C T ITEM SUBMITTED P A R A G# R A P H (b) (c) (d) (e) 32 11 33 32 12 10 32 12 17 SUBMITTAL FORM,Jan 96 DESCRIPTION Optimum moisture content and maximum density SD-07 Certificates cement Location of aggregate source Method Construction equipment list SD-03 Product Data Waybills and Delivery Tickets SD-06 Test Reports Sampling and Testing SD-05 Design Data Job-mix formula ASPHALT CEMENT BINDER MIX DESIGN SD-06 Test Reports Specific gravity test of asphalt Coarse aggregate tests Weight of slag test Percent of crushed pieces in gravel Fine aggregate tests Specific gravity of mineral filler Bituminous mixture tests Aggregates tests Bituminous mix tests CONTRACTOR: SCHEDULE DATES G O V T C L A S S I F I C A T I O N CONTRACTOR ACTION O R A C T I O N A / E R E V W R (f) SUBMIT (g) APPROVAL MATERIAL NEEDED NEEDED BY BY (h) (i) APPROVING AUTHORITY A C T I O N DATE FWD TO APPR AUTH/ C O D E DATE OF ACTION (j) (k) DATE RCD DATE FWD DATE RCD FROM TO OTHER FROM OTH CONTR REVIEWER REVIEWER (l) (m) (n) MAILED TO CONTR/ C O D E DATE OF ACTION DATE RCD FRM APPR AUTH REMARKS (o) (p) (q) (r) 3.7.2.6 2.1 1.5.1 1.5.1 1.5.1 1.1.3 3.7 1.3.2 2.2 2.3 2.5.1 2.5.1 2.5.1 2.5.1 2.5.1 2.5.1 2.5.1 3.5.2.1 3.5.2.2 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 7 PAGES CONTRACT NO. SUBMITTAL REGISTER TITLE AND LOCATION FA3002-09-D-0002 CONTRACTOR Repair/Replace Taxiway G/G1 A C T I V I T Y T R A N S M I T T A L N O (a) S P E C N O S E C T ITEM SUBMITTED P A R A G# R A P H (b) (c) (d) (e) 32 12 17 32 13 11 DESCRIPTION Pavement courses SD-03 Product Data Equipment Proposed Techniques Dowels Dowel Bar Assemblies SD-05 Design Data Proportioning Studies SD-06 Test Reports Sampling and Testing SD-07 Certificates Contractor Quality Control Staff Laboratory Accreditation NRMCA Certificate of Conformance Commercial Laboratory 32 17 24.00 10 SD-03 Product Data Equipment Composition Requirements Qualifications SD-06 Test Reports Sampling and Testing SD-07 Certificates Volatile Organic Compound (VOC) 32 92 19 SD-03 Product Data SUBMITTAL FORM,Jan 96 CONTRACTOR: SCHEDULE DATES G O V T C L A S S I F I C A T I O N CONTRACTOR ACTION O R A C T I O N A / E R E V W R (f) SUBMIT (g) APPROVAL MATERIAL NEEDED NEEDED BY BY (h) (i) APPROVING AUTHORITY A C T I O N DATE FWD TO APPR AUTH/ C O D E DATE OF ACTION (j) (k) DATE RCD DATE FWD DATE RCD FROM TO OTHER FROM OTH CONTR REVIEWER REVIEWER (l) (m) (n) MAILED TO CONTR/ C O D E DATE OF ACTION DATE RCD FRM APPR AUTH REMARKS (o) (p) (q) (r) 3.5.2.3 2.10 3.1.2 2.8.1 2.8.2 G G G 2.12.2 G ED 1.3.4 G ED 1.5.1 1.5.3 2.10 G ED G ED G ED 1.5.3 G ED 1.3 G 1.5.1 2.3 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 7 PAGES CONTRACT NO. SUBMITTAL REGISTER TITLE AND LOCATION FA3002-09-D-0002 CONTRACTOR Repair/Replace Taxiway G/G1 A C T I V I T Y T R A N S M I T T A L N O (a) S P E C N O S E C T ITEM SUBMITTED P A R A G# R A P H (b) (c) (d) (e) 32 92 19 33 40 00 SUBMITTAL FORM,Jan 96 DESCRIPTION Wood cellulose fiber mulch Fertilizer SD-06 Test Reports Topsoil composition tests SD-07 Certificates seed SD-08 Manufacturer’s Instructions Erosion Control Materials SD-03 Product Data Placing Pipe SD-04 Samples Pipe for Culverts and Storm Drains SD-07 Certificates Resin Certification Pipeline Testing Hydrostatic Test on Watertight Joints Determination of Density Frame and Cover for Gratings CONTRACTOR: SCHEDULE DATES G O V T C L A S S I F I C A T I O N CONTRACTOR ACTION O R A C T I O N A / E R E V W R (f) SUBMIT (g) APPROVAL MATERIAL NEEDED NEEDED BY BY (h) (i) APPROVING AUTHORITY A C T I O N DATE FWD TO APPR AUTH/ C O D E DATE OF ACTION (j) (k) DATE RCD DATE FWD DATE RCD FROM TO OTHER FROM OTH CONTR REVIEWER REVIEWER (l) (m) (n) MAILED TO CONTR/ C O D E DATE OF ACTION DATE RCD FRM APPR AUTH REMARKS (o) (p) (q) (r) 2.3.1 2.2.3 2.1 2.5 3.3 2.1 3.8 2.6 3.7.5 2.3.6 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 7 PAGES This Page Left Intentionally Blank