Construction / Design Standards General Standard No. Standard Name Current Previous Revision Date Revision Date Revision Summary Author 00 00 00 Introduction 10/17/11 6/30/04 Updated Standard No. Jherschelman 01 41 00 Regulatory Requirements 10/17/11 6/30/04 Updated Standard No. Jherschelman Design Documents Information Requirements 10/17/11 General Commissioning Requirements 10/17/11 10/2/08 1.03, D, #5, Updated Standard No. Sfox, Jherschelman 01 91 01 Commissioning Steps 10/17/11 6/30/04 Updated Standard No. Jherschelman 01 91 02 Asset Tagging List 10/17/11 6/30/04 Updated Standard No. Jherschelman 01 91 03 Contractor Installed Equipment Input Form 10/17/11 6/30/04 Updated Standard No. Jherschelman 01 42 00 01 91 00 ELECTRICAL STANDARDS UPDATE TRACKER ELECTRICAL STANDARDS TABLE OF CONTENTS 9/8/10 Added1.01.8.q) 1.02.9.x)11.v) 13.t) 1.03.9.y) 11.y) 13.u), Updated Standard No. Jherschelman Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN / CONSTRUCTION GUIDELINES & STANDARDS GENERAL Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN / CONSTRUCTION GUIDELINES & STANDARDS GENERAL TABLE OF CONTENTS Section – Index 00 00 00 - Introduction ...................................................................................................... 1 01 41 00 – Regulatory Requirements................................................................................ 2 01 42 00 - Design Documents Information Requirements................................................. 3 01 91 00 - General Commissioning Requirements............................................................ 4 01 91 01 - BSC Commissioning Steps .............................................................................. 4 01 91 02 - BSC Asset Tagging List ................................................................................... 4 01 91 03 - Contractor Installed Equipment Input Form...................................................... 4 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 00 00 00 - INTRODUCTION 1.01 Mission Statement To identify specific materials, systems and/or construction methods that are required for consistent facility value. To ensure that the Beaumont Health System facilities are designed, engineered and constructed with materials and systems that provide optimum value thru a combination of first cost, long-term cost and quality. To provide a forum for the introduction of new building materials and systems, and a forum to change building materials and systems. o Introduction may be made by: Jones Lang LaSalle @ Beaumont Health System Staff Design Professionals Construction Professionals Suppliers/Vendors 1.02 To publish the agreed upon standards and guidelines in a form easily understood by architects, engineers, contractors and JLL@BHS staff. Introduction Set forth in these documents are standards and guidelines intended to serve as design and construction criteria for the Beaumont Health System facilities. As such, they reflect the planning, design, construction, and maintenance expertise of JLL@BHS personnel and consultants This information is to be applied to all renovation and new construction from the very first planning and design stages through actual construction and facilities maintenance and management. The information included within each section contains procedures to be followed, materials to be used, or design guidelines which we have found to be appropriate to assure the quality desired now and through our future maintenance of these facilities. Facilities personnel, as well as outside architects, consultants, and contractors, should become familiar with these standards and guidelines. 00 00 00 Introduction Issued 6/30/04 Revised 10/17/11 Page 1 of 2 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 00 00 00 - INTRODUCTION 1.03 Scope of the Standards The standards included herein shall serve as a code of quality for all design, construction, and maintenance procedures and projects. The level of quality deemed by any one standard is determined on the basis of reliability, serviceability, safety, and cost (including design, construction, inventory, operating, and maintenance costs). The information contained in these standards is not specific to any one project, but common to all. 1.04 A Dynamic Document Standards from all areas of design, construction and maintenance are continually being developed. This document is a "living" document keeping abreast of new and better procedures or materials as we become aware of them. To this end, JLL@BHS Policy 204, Maintenance of Design & Construction Guidelines, has been established to provide a mechanism by which the document can be update as the need arises. 1.05 Standards Versus Specifications These standards and guidelines shall form the basis from which to create drawings and specifications. All of the concepts and procedures included are for the use of Jones Lang LaSalle @ Beaumont Health System contracted designers, consultants and contractors. The use and inclusion of these standards in bid documents does not relieve the consultant or architect of the responsibility and legal liability for any bid documents created from these standards. 1.06 Availability These standards are developed and maintained by the Facilities Engineering Section of Jones Lang LaSalle @ Beaumont Health Systems, L. L. C, 30963 Woodward Avenue, Royal Oak, Michigan 48073, Julia Herschelman, telephone 248-551-3632. We appreciate any feedback you would like to give on the content or format of the standards. 00 00 00 Introduction Issued 6/30/04 Revised 10/17/11 Page 2 of 2 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 41 00 – REGULATORY REQUIREMENTS 1.01 General A. All codes, rules, regulations, guidelines, requirements, etc. which are used or referenced in the preparation of documents, and/or are required to be complied with by the Agencies Having Jurisdiction, shall be listed on the drawings or in the specifications of the project documents. The years and editions of these shall be accurately noted in reference to the respective time frame of the project. B. Included on the drawings or in the specifications of the project documents will also be the following information: 1. 2. 3. 4. 5. Building Occupancy Classification Building Construction Type Building Elements Listings including the hour ratings and assembly designation Building Seismic Criteria and Classification Finish Material Ratings C. Also included, for record and future reference, on the drawings or in the specifications of the project documents, shall be any granted variances or exceptions from any of the Authorities Having Jurisdiction. Inclusion of these in the record documents will ensure that they can be easily found, when the need arises, after the project is completed. D. All projects, in health care occupancies, will be designed to the 2000 NFPA 101 Life Safety Code to meet JCAHO and CMS requirements. These occupancies will include health care, ambulatory health care and business as defined by Joint Commission, CMS and NFPA. E. All Projects in occupancies that will provide patient care, and fall under the jurisdiction of Joint Commission, will be designed to the 2010 FGI Guidelines for Design and Construction of Health Care Facilities. These occupancies will include health care, ambulatory health care and business as defined by Joint Commission, CMS and NFPA. F. The Design Kick-Off Checklist that is issued with each project lists all of the usual rules and regulations that should be followed. This is not to be construed as a complete listing nor does it release the professional preparing and/or sealing the documents from complying with regulatory requirements not noted in this checklist. 01 41 00 Regulatory Requirements Issued 6/30/04 Revised 10/17/11 Page 1 of 1 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS 1.01 Schematic Design Minimum Requirements A. The purpose of the Schematic Design is to interpret the program data provided and produce a design that will satisfy all program requirements. It also must clarify the program, identify program oversights or excesses, and generally verify that the proposed program is functionally and fiscally feasible from an overall Building and Campus perspective. By the end of the Schematic Design all program issues should not have, or show, any unassigned spaces (other than shell space not being built out as part of the project). Any such spaces shown in the original program are anticipated to have been designated and resolved by the completion of Schematic Design. In addition, Schematic Design must resolve all breakthrough, phasing and renovation issues associated with the work. B. It should be noted that space allocations for infrastructure are a required basic part of the program. These spaces require vertical walk in shafts for mechanical and electrical distribution in the facility. In the past, there has been a proclivity with maximizing net assignable square footage for end users versus maintaining infrastructure allowances within the overall gross square footage. This ultimately has had a detrimental effect on the longterm functioning and future flexibility of some facilities. Health Care Facilities require generous provisions, with built-in allowances for future growth, for mechanical and electrical systems and equipment. Design philosophy must recognize this and adjust accordingly in the schematic development stages of a structure so as to maintain the minimum shaft and mechanical/electrical spaces programmed for this facility. Any proposed encroachment of User program square footage, into these infrastructure spaces must have JLL@BHS approval before proceeding. C. The following represents the minimum deliverables required for Schematic Design review and approval. Submittals that do not meet these requirements will not be reviewed or approved: 1. Program Reconciliation must be provided in a tabular format (Excel Format). This document will list each individual space, including circulation and shafts, indicating original program square footage, schematic design square footage, any variance square footage and a brief narrative description explaining the need for the variance. A detailed operational narrative with room-by-room descriptions is also required as an output of Schematic Design. 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 1 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS 2. Specifications in outline format including a narrative and descriptions of materials, finishes and proposed MEP systems. Note that the use of variable air volume systems will require a detailed economic cost evaluation by the A/E. These specifications shall also include a detailed listing of all applicable codes and any seismic requirements. Narratives shall include how design will provide accessibility to utility systems for service, maintenance and future remodeling. 3. CADD Requirements: All drawings and electronic files delivered to JLL@BHS shall follow JLL@BHS CADD Standards. 4. Integrated Systems Study: Show through various key building sections how structural, plumbing, fire protection, mechanical and electrical systems are to be coordinated and layered for physical fit, installation and accessibility for maintenance. 5. Site Requirements: a) Existing Conditions Civil Survey, b) Parking locations, c) Site entrance, d) New building entrance, e) Temporary entrances and site circulation, fencing, roadways, parking, lighting, signs, f) Building foot print, g) Demolition, h) Existing site utilities, i) New site utility requirements, j) Walkway locations, k) Any future expansion capabilities, l) Landscaping demolition, m) Roadways and drive, n) Storm Water Management criteria, o) Proposed location of any new underground utilities. 6. Building Exterior Envelope: a) Elevations of each side of the building addition including partial elevation of the existing building b) Building cross sections c) Exterior proposed wall details and sections d) Detailed wall sections at each type of window e) Roof layout f) Elevations and sections of proposed atriums, garden courts, etc. 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 2 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS 7. Structural: a) Structural scheme, b) Building frame and sizing of major components, c) Description of seismic analysis and methods to be employed, d) Canopy entrance framing, e) Shoring requirements, f) Stair details, g) Special requirements to protect existing structure, h) Typical floor framing requirements. 8. Building Floor Plans: a) Floor plans of each floor with column grid designations drawn at 1/8” of ¼” scale, b) Indicate area use and square footage c) Locations of vertical infrastructure shafts d) Layouts of all spaces including room names e) Circulation paths f) Layouts of surgical rooms at a larger scale with major items of equipment shown g) Show flexibility for building expansion h) All floor plans show at least the two most adjacent bays of the adjacent building i) Full floor plans showing project location and a minimum of any required building separations, and smoke barriers, existing and new j) Show all service support spaces such as janitors closets, electrical closets, mechanical shafts, soiled and clean utility rooms, public and staff toilet rooms k) Elevators and elevator equipment rooms l) Pneumatic tube station location(s) m) Interior partition types n) Include major pieces of equipment o) Legend of symbols and abbreviations p) Indicate what Barrier Free provisions are being provided. q) Locate required fire extinguishers. Verify travel distances are compliant with code. 9. Plumbing Plans: a) Location of all plumbing systems risers, b) Using the Facilities CADD one line diagram of all medical gases systems determine and show proposed points of new connections to these systems. Provide calculations indicating the adequacy or inadequacy of existing risers, 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 3 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS c) d) e) f) g) All fixtures and their location, Show suggested routing of all piping mains vertically and horizontally. Routing of roof drainage systems. Location of storm and sanitary pumps. Location of roof overflow outlets at grade. Specific care should be taken to locate these so that they do not flow across pedestrian walks and paths. 10. HVAC Plans: a) Mechanical Room plans showing major pieces of equipment such as air handlers, converters, pumps, condensate lift stations, etc. b) Block Load calculations including dew point calculations for all window types c) Main duct risers & proposed routing of duct mains on the floor, d) One line flow diagrams all systems such as ventilation air, chilled water, heating hot water, steam and condensate, e) Air intake and discharge locations. f) Perimeter heating systems indicating where radiant panels and finned tube will be used. g) Preliminary sections in mechanical rooms, h) Mechanical legend of symbols and abbreviations, i) Statement of design intent including winter and summer design conditions. j) Investigation of diesel exhaust plume and air intakes (existing and new) 11. Electrical Plans: a) Tabulation of lighting source proposed, and required footcandles, per type of area b) Fixture types per established JLL@BHS Standard c) Electrical equipment room plans showing location of all major pieces of equipment d) Investigation of existing normal and emergency power system to determine spare capacity e) One line diagrams of normal and emergency power distribution systems and how the new work will integrate with the existing Campus and building distribution systems f) Electrical closet locations g) Electrical legend of symbols and abbreviations, coordinated with JLL@BHS CADD Standards, Data/Communicationsdetermine, and indicate point of origin 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 4 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS h) i) j) k) l) m) 1.02 Estimated load calculations for normal and emergency power Details of emergency generator location Fire Command Center location Plan for redundant emergency supply to OR’s Identification of special electrical components and their location: UPS, TVSS, harmonic filters, power factor correction capacitors. Interview users for specific UPS, data, communication and emergency power requirements. Design Development Minimum Requirements A. Design Development should not proceed until the JLL@BHS Project manager has provided formal approval. This approval will not be given until all Schematic Design review comments have been responded to by the A/E. At the completion of Schematic Design all program space relationships, adjacencies, and square footage requirements are viewed as fixed and only minor programmatic revisions will be allowed. The JLL@BHS Project Manager must approve, in writing, any requested revisions that have a cost/budget or schedule impact before proceeding. B. A properly prepared set of Design Development documents should resolve all major conflicts and interference’s between disciplines and various trades work. To this end it is anticipated that the documents submitted for review in Design Development will represent approximately 60% completed Construction Documents. Plans and specifications for sitework, foundation, structure, and shell will be 100% complete at this time for early bid packages. Specifications for major long lead equipment such as elevators, air handling units, emergency generators, electrical substations, switch gear and paralleling gear will be 100% complete for a possible early bid package. C. The following represents the minimum deliverables required for Design Development review and approval. It is the Architect/Engineer’s responsibility to meet these requirements within the time frames published in the project’s schedule. Submittals that do not meet these requirements will not be reviewed or approved and will be required to be re-submitted with all required information within the project scheduled time frames. Schedule extensions for incomplete submittals will not be granted. 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 5 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS 1. Program Reconciliation must be provided in a tabular format (Excel Format). This document will list each individual space or room (including circulation and shafts) indicating original program square footage, schematic design, square footage, any variance square footage with a brief narrative description explaining the need for the variance that occurred in Design Development. A revised operational narrative should also be included. 2. Specifications shall be representative of the final construction specification to the extent that they shall relay full design intent establishing levels of materials quality, criteria for installation of material and systems. Equipment specifications shall be reasonably complete. 3. Clarifications: Submit a written narrative indicating areas or details that the A/E would like to receive clarification or direction on how to proceed. 4. Equipment Planning: All equipment planning shall be complete with detailed room by room descriptions listing all 5. CADD Requirements: All drawings and electronic files delivered to JLL@BHS shall follow JLL@BHS CADD Standards. 6. Site and Civil Work: 100% complete for early bid packages. It should be understood that if early bid packages for this work are to be issued before Design Development then the requirements that follow are to be submitted with the Schematic Design Review Package. a) Completed survey of the existing site showing all existing conditions, underground utilities and easements. b) All site drawings shall be drawn at a scale of 1”=30’-0” c) Site Drawing showing demolition d) Site Drawing showing all new utility work with all utilities that are to be demolished removed from this drawing. Only those existing utilities that are to remain and new utility work are to be shown e) Site Drawings with all new grading requirements, roadways, and drives, walkways etc. f) Temporary entrances and canopies g) Site storm water drainage requirements with calculations h) Building foot print i) In process Landscaping plans showing planting layout, landscape lighting and proposed irrigation plan 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 6 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS 7. Building Exterior Envelope a) Fully detailed and dimensioned elevations of each side of the building. These drawings shall indicate all future expansion capabilities. b) Completed Building Sections c) Full Details and sections of all window types d) Large scale canopy entrance plan and associated details e) Fully detailed exterior wall sections, particular attention should be given to waterproofing, vapor barriers, and insulation f) Roof plan showing all roof mounted equipment and roof penetrations. 8. Structural a) Fully detailed plans of building frame and structure b) Clear description of seismic requirements c) Shoring requirements full detailed. d) Canopy entrance framing e) Floor framing requirements f) Structural details at all breakthroughs into the existing buildings. g) Foundations drainage requirements h) Completed stair details i) All miscellaneous steel requirements j) Design Loads k) Special framing requirements for infrastructure shafts and grating l) Show all detailing with respect to future expansion capabilities m) Column grid designations 9. Building Floor Plans a) Cover Sheet b) Drawing List c) Composite of Fire and Smoke zones complete with locations of all rated walls d) ¼” scale plans of each floor with column grid designations e) Include all room names and Facilitech System Room numbers f) Interior room dimensions g) Large scale plans and details including special finishes in public areas 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 7 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS h) i) j) k) l) m) n) o) p) q) r) s) t) u) v) w) x) Large scale detailed plans of operating rooms, patient rooms and support spaces Equipment and furniture layouts. Show millwork Interior wall elevations showing placement of medical gas and electrical outlets Millwork elevations and details Door Schedule Door frame types and details Room Finish schedule Reflected ceiling plans with all devices such as sprinkler heads, lighting, exit signs, and fire alarm devices. Partition types and details Fire ratings of walls and smoke zones Elevator details and finishes Plans and details of areas to be remodeled in the existing building Access to roofs Expansion joint details and locations Miscellaneous supports systems for ceiling mounted equipment Show locations of fire extinguishers. 10. Plumbing Plans a) Revised and updated one line diagrams of medical gas systems including revised final calculations b) Riser diagrams of domestic hot and cold water c) Riser diagrams of waste and vent systems with fixture counts d) Floor plans with all plumbing systems laid out e) Completed roof and under ground drainage systems f) All fixtures and their locations g) Domestic hot water heating equipment h) Piping schematic diagrams i) Storm and Sanitary Sump Pump Details j) Location of medical gas alarms and zone valves. k) Location of roof overflow outlets at grade 11. HVAC Plans a) Mechanical Room Plans with all equipment and piping shown b) Updated and revised load calculations including finalized dew point calculations 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 8 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS c) d) e) f) g) h) i) j) k) l) m) n) o) p) q) r) s) t) u) v) Air handling unit duct riser diagrams with all required dampers and cfm requirements at each floor branch main takeoff Floor plans with duct layouts and terminal devices. Indicate on plans with screen symbolism areas beneath ductwork that are to be kept free of all other utilities in order to maintain access to fire/smoke dampers, valves, etc. HVAC piping plans Pneumatic tube system piping plans Perimeter heating plans with piping for radiant ceiling panels and finned tube radiation Updated statement of design intent Detailed sections of mechanical room Large scale plans of mechanical shafts at each floor One line flow diagrams of chilled water, heating hot water, steam and condensate Temperature control diagrams with sequence of operation and detailed points listing Duct details Fire/smoke/combination damper details Equipment schedules with clear delineation of present and future capacity requirements Steam PRV location and details All equipment details Demonstrate with composite sections that HVAC, plumbing, fire protection and electrical disciplines are coordinated for physical fit, service and accessibility for maintenance. Show location of all duct-balancing dampers on plans. Standard details or notes will not be acceptable Show on plans the location of all required piping balancing valves for all HVAC piping diagrams Show locations of temperature control panels and VFD’s Show wall ratings on base plans for HVAC to verify fire and smoke damper locations. 12. Fire Protection a) Floor plans with layouts of all sprinkler piping and head locations with preliminary hydraulic calculations 13. Electrical Plans a) Lighting plan of all floors b) Light level calculations c) Fixture switching/layout d) Electrical equipment plans and details 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 9 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS e) f) g) h) i) j) k) l) m) n) o) p) q) r) s) t) u) v) 1.03 All distribution, lighting and receptacle panel locations with designations as determined by JLL@BHS Facilities Management Power and signal floor plans showing locations of receptacle and data/communications outlets Site electrical plans-underground conduit/ducts, lighting, signs, security, gates and illuminated signs Communication riser diagrams Normal and Emergency power riser diagrams Normal and Emergency power one line diagrams Panelboard schedules, including present and future load capacities Fire alarm floor plans showing locations of required devices MCC locations and details of equipment served Fire alarm riser diagram Nurse call system layout Paging and music systems Control Diagrams Show main conduit runs for all conduits 2” and larger Lighting fixture schedule Show wall ratings on fire alarm plans Show special electrical components and their location: UPS, TVSS, harmonic filters, power factor correction capacitors. Verify users specific UPS, data, communication and emergency power requirements and show the system locations. Minimum Construction Drawings and Specification Requirements: A. Jones Lang LaSalle @ Beaumont Health System sets high standards and goals not only for itself but also for the consultants and contractors it employs. Our Client, Beaumont Health System, is a Health Industry Leader in providing the highest possible quality Health Care Services to its patients. One of the many ways this is accomplished is by constructing high quality facilities. The Essence of the Jones Lang LaSalle @ Beaumont Health System is to provide “Excellence in Environments that Help to Heal” and with this in mind JLL@BHS sets high standards of quality, goals and expectations. One of these expectations is that final construction documents prepared by the A/E of Record are to be well executed, highly detailed and complete in every way. A goal that follows from this expectation is a difficult one. We as a team need to strive to produce a set of construction documents that will reduce, if not eliminate, the issuance of any bulletins to correct errors and omissions after bids are received and contracts have been awarded. It is further recognized that 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 10 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS we are all human and that errors will occur, but our goal, as a team is to strive and extend our collective abilities to reduce the number of bulletins to zero. Bulletins are expensive and make budget management extremely difficult. The budget for this project is fixed and it is the project team’s responsibility to meet this budget without sacrificing the quality of the facility to be constructed. B. In preparing the construction documents the A/E needs to consider the above and what internal quality control changes will be required. When submitting final construction documents for review the A/E must consider that they are to be 100% complete (bid Ready) in all respects. Completeness and thoroughness of the documents are critical to the success of this project. Construction documents will be critically reviewed by JLL@BHS. Documents that are incomplete, or poorly coordinated, will be returned to the A/E until they are deemed ready for review and bidding. There will be no schedule extensions given for submittal of documents that are incomplete or poorly coordinated bid documents. C. The following represents the minimum deliverables required for Final Construction Documents: 1. Previous review Comment Response; the A/E shall include a complete written response to all JLL@BHS Design Development review comments. The A/E shall include and indicate any areas or details that vary from Design Development and may require further clarification. 2. Program Reconciliation must be provided in a tabular format (Excel Format). This document will list each individual space or room (including circulation and shafts) indicating original program square footage, Schematic Design, square footage, Design Development Square footage, any variance square footage with a brief narrative description explaining the need for the variance that occurred in preparation of Final Construction Documents. A revised and final operational narrative should also be included. 3. Specifications; .all specifications are to be 100% complete and shall include (for reference & coordination) all specification sections that were issued with earlier bid packages. Equipment, manufactures and model number shall not vary or be changed from those approved in Design Development. 4. Equipment Planning; include all complete room data sheets. 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 11 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS 5. CADD requirements; include a CD of all drawing files of bid documents including specifications. 6. Site and Civil Work: 100% complete. It is understood that if early bid packages for this work are to be issued before Final CD Review then the requirements that follow are to be submitted with the Design Development Review Package. a) Completed survey of the existing site showing all existing conditions, underground utilities and easements. b) All site drawings shall be drawn at a scale of 1”=30’-0” c) Site Drawing showing all necessary demolition d) Site Drawing showing all new utility work with all utilities that are to be demolished removed from this drawing. Only those existing utilities that are to remain and new utility work are to be shown. All underground utilities are to be clearly labeled complete with sizes of piping and conduits. e) Site Drawings with all new grading requirements, roadways, and drives, walkways etc. f) Site drawings are to be clearly defined showing details of curbing, expansion joints in roadways & sidewalks, manhole details, piping details, etc. g) Site storm water drainage requirements complete with calculations and drawings h) Building foot print i) 100% complete Landscaping plans showing planting layout, landscape lighting, irrigation plan, guying details, existing tree protection, planting details and soil preparation specifications. j) Coordinated site signage plan and any special requirements. 7. Building Exterior Envelope a) Fully detailed and dimensioned elevations of each side of the building. These drawings shall indicate all future expansion capabilities. b) Completed Building Sections c) Full Details and sections of all window types detailing flashing, waterproofing, insulation and caulking requirements at sills heads and jambs d) Large scale canopy entrance plan and associated details of all building entrances e) Fully detailed exterior wall sections, particular attention should be given to waterproofing, vapor barriers, and insulation 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 12 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS f) g) h) i) j) Roof plan showing all roof mounted equipment and roof penetrations. Roofing installation details including curbs, flashing requirements, etc. Exterior door details Typical exterior wall sections with clear indication installation of insulation and vapor barriers Building Elevations should show any planned exterior signage to be mounted on the building. 8. Structural a) Fully detailed plans of building frame and structure b) Clear description of seismic requirements c) Shoring requirements full detailed on drawings d) Canopy entrance framing e) Floor framing requirements f) Structural details at all breakthroughs into the existing buildings. g) Beam and Column schedules h) Foundation details i) Floor loading design load requirements clearly defined j) Foundations drainage requirements and lower level, under slab drainage k) Completed stair details l) All miscellaneous steel requirements m) Design Loads n) Special framing requirements for infrastructure shafts and grating o) Show all detailing with respect to future expansion capabilities p) Column grid designations q) If concrete structural systems are used show on plan, and fully detail, all embedded items such as Unistrut to facilitate installation of MEP systems and other equipment 9. Building Floor Plans a) Cover Sheet b) Drawing List c) Composite of Fire and Smoke zones complete with locations of all rated walls d) ¼” scale plans of each floor with column grid designations e) Include all room names and Facilitech System Room numbers f) Interior room dimensions 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 13 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS g) h) i) j) k) l) m) n) o) p) q) r) s) t) u) v) w) x) y) z) 10. Large scale plans and details including special finishes in public areas Large scale detailed plans of operating rooms, patient rooms and support spaces Equipment and furniture layouts. Show millwork Interior wall elevations showing placement of medical gas and electrical outlets Millwork elevations and details Door and hardware schedules Door frame types and details Room Finish schedules Reflected ceiling plans showing and coordinating all devices such as sprinkler heads, lighting, exit signs, and fire alarm devices. Partition types and details Fire ratings of walls and smoke zones Fire stopping details both typical and special Elevator details, finishes and lighting Plans and details of areas to be remodeled in the existing building Access to roofs and associated details Expansion joint details and locations Miscellaneous supports systems for ceiling mounted equipment Detailed large scale plans with elevations and construction details of all public spaces such as waiting rooms and lobbies with special interior design detail is used. Show fire extinguisher locations. Do a final verification that the travel distances are compliant with code. Plumbing Plans a) Revised and updated one line diagrams of medical gas systems including revised final calculations and cfm requirements shown on riser diagram b) Riser diagrams of domestic hot and cold water c) Riser diagrams of waste and vent systems with fixture counts d) Floor plans with all plumbing systems laid out e) Completed roof and under ground drainage systems f) All fixtures and their locations g) Domestic hot water heating equipment h) Piping schematic diagrams and equipment connection details 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 14 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS i) j) k) l) 11. Storm and Sanitary Sump Pump Details Medical gas piping floor plans Location of medical gas alarms and zone valves. Location of roof overflow outlets at grade. HVAC Plans a) Mechanical Room Plans with all equipment, ductwork and piping shown. Plans shall include all permanent scaffolding/platforms that may be required to meet OSHA & MiOSHA safety maintenance accessibility for equipment mounted in inaccessible locations. Plans shall demonstrate those service isles are maintained for service and equipment replacement. In this regard particular attention shall be given to smoke detectors. Access to mechanical rooms for equipment replacement through exterior louvers shall be maintained. b) Provide detailed coordinated sections through mechanical rooms showing equipment, ductwork, HVAC piping, plumbing piping and all conduit to demonstrate a fully coordinated design. c) Updated and revised HVAC load calculations including finalized dew point calculations d) Air handling unit duct riser diagrams with all required dampers and cfm requirements (both present and future cfm are to be shown) at each floor branch to main takeoff. Riser diagrams shall indicate AHU designation. e) Floor plans with duct layouts and terminal devices. Indicate on plans with screen symbolism areas beneath ductwork that are to be kept free of all other utilities in order to maintain access to fire/smoke dampers, valves, etc. f) HVAC piping plans with all piping clearly labeled, all pipe sizes shown and with flow direction indicated. Plan shall clearly indicate the location of all service balancing and isolation valves. Show isolation/balancing valves at all riser to floor branch mains indicating floor design gpm requirements. Show isolation valve at all branch main takeoffs. Standard details for reheat coils will be acceptable. g) Include HVAC piping riser diagrams chilled water, heating hot water, steam and condensate indicating gpm flow and/or lbs. per hour of steam requirements at each floor branch takeoff. h) Perimeter heating plans with piping for radiant ceiling panels and finned tube radiation. Indicate all required valves on plan. 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 15 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS i) j) k) l) m) n) o) p) q) r) s) t) u) v) w) x) y) 12. Updated statement of design intent Large scale plans of mechanical shafts at each floor showing all ductwork and piping Detailed temperature control diagrams with sequence of operation and detailed points listing all shown on the drawings. Sequences of operation in specifications will not be acceptable Smoke purge control strategy Mechanical piping details and diagrams of all equipment Duct details Fire/smoke/combination damper installation details Equipment schedules with clear delineation of present and future capacity requirements Steam PRV location and details All equipment details Demonstrate with composite sections that HVAC, plumbing, fire protection and electrical disciplines are coordinated for physical fit, service and accessibility for maintenance. Show location of all duct-balancing dampers on plans. Standard details or notes will not be acceptable Show on plans the location of all required piping balancing valves for all HVAC piping diagrams Converter equipment details and piping schematic diagrams Show locations of temperature control panels and VFD’s Show all required seismic bracing requirements for Mechanical Systems. Show wall ratings on HVAC plans to verify locations of smoke and fire dampers Fire Protection a) Floor plans with layouts of all sprinkler piping and head locations with design hydraulic calculations. b) Show all pipe hangers and required seismic bracing requirements c) Show all hydraulic calculation nodes d) Provide details and sequence of operation for pre-action system e) Include a plan of the Building’s existing fire pump loop and points of new connection f) Plans shall indicate the type, model number and quantity of each sprinkler head g) Fire protection drawing shall show all fire rated walls and smoke partitions 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 16 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS h) i) 13. All drain down solutions for the system shall show a location to the outside of the building that does not impact pedestrian and vehicular traffic or to a hard piped drain location. See JLL@BHS Standard Section 21 10 00 for additional requirements. Electrical Plans a) Lighting plan of all floors b) Light level calculations c) Fixture switching/layout d) Electrical equipment plans and details e) All distribution, lighting and receptacle panel locations with designations as determined by JLL@BHs TIG f) Power and signal floor plans showing locations of receptacle and data/communications outlets g) Site electrical plans-underground conduit/ducts, lighting, signs, security, gates and illuminated signs h) Communication riser diagrams i) Normal and Emergency power riser diagrams j) Normal and Emergency power one line diagrams k) Panelboard schedules, including present and future load capacities l) Fire alarm floor plans showing locations of required devices m) MCC locations and details of equipment served n) Fire alarm riser diagram o) Nurse call system layout p) Paging and music systems q) Control Diagrams r) Show main conduit runs for all conduits 2” and larger s) Emergency generator details t) Lighting fixture schedule u) Show wall ratings on the fire alarm plans for reference. v) Special electrical components and their locations: UPS, TVSS, harmonic filters, power factor correction capacitors. w) Show users specific UPS, data, communication and emergency power requirements and the system locations. 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 17 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS 1.04 1.05 Final Design Documents: A. At project completion and occupancy, the Architect/Engineer will provide the final design documents (project specifications and drawings) in both electronic (PDF & AutoCAD) and bond paper copy (1 each). These final design documents will include all addendum’s, responses to RFI’s and any bulletins that resulted in a drawing or specification change that occurred from the issue of the construction documents for bids through to the completion and occupancy of the project. B. At project completion and occupancy, the General Contractor will provide the as-builts in both electronic (AutoCAD) and bond paper copy (1 each). In addition one copy of all closeout documentation including guarantees, MSDS, permits & Certificates of Occupancy from all Authorities Having Jurisdiction (Building, Bureau of Fire Services, Health Facilities Engineering Section, etc.), testing reports, shop drawings & submittals, O&M, etc. will be provided as applicable to each project. Construction Document Information A. Information 1. Cover Sheet: a) Building Name / Site Location b) Floor and Tower c) Department or Suite Name d) Project name e) JLL@BHS Project Number f) JLL@BHS Project Manager g) Bureau of Fire Services Project Number h) Health Facilities Engineering Section Project Number i) Certificate of Need Number (C of N No.) if required. j) Site Plan locating project. k) A/E Consultant's Company Name and Address l) Sub-Consultant's Company Names and Addresses m) Construction Management Company Name and Address n) Sheet Index o) Package Name (Program, Schematic, Design Development, Construction, Addendum, Bulletin, etc.) p) Issue Date 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 18 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS B. Full Floor Locator Plan / Life Safety Floor Plan 1. For Hospital Projects: a) This can be a combined plan showing the project location and, at the minimum, the floor's smoke barriers and the 2hour building separations for the floor. Included on this plan, the general department/suite locations should be identified for the related adjacencies for the project. C. For Non-Hospital Projects: 1. A full Floor Locator Plan can be used as a Key Plan on each sheet of as a Floor Locator Plan on the Cover Sheet. Department / Suite locations are only required if they add clarity to the location of the project. D. Floor Plans 1. All floor plans, existing/demolition, remodeled, architectural, mechanical, plumbing, electrical, interiors, equipment, etc., must have room names and room numbers shown. This can be either the room name and number shown in each room, or the room number in the room with a corresponding room name listing on each sheet. E. 2. The room numbers will be from Beaumont's established room numbering system as provided by JLL@BHS' Planning and Technical Information Services. The door and opening numbers will be established from the room numbers so that we can tie them back to our database as used by our Facilities Management groups for reference. 3 All floor and equipment plans shall be 1/4" scale and show column numbers and column lines for locational reference. 4 Locations of temporary, construction partitions and temporary system support should be shown on the documents. Ceiling Plans 1. Show all wall rating information, new and existing. JLL@BHS should provide the required wall rating symbol designations. 2. Show a completely integrated ceiling system. Including all systems, i.e. lights, sprinklers, speakers, diffuses, grilles returns, exit signs, smoke detectors, etc. 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 19 of 20 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 42 00 – DESIGN DOCUMENTS INFORMATION REQUIREMENTS F. Demolition Plans 1. The type of systems and their construction should be identified and noted on the demolition plans. G. Regulatory Requirements: 1. All codes, rules, regulations, guidelines, requirements, etc., which are used or referenced in the preparation of documents, and/or are required to be complied with by the Agencies Having Jurisdiction, shall be listed on or in the project documents. The years and editions of these shall be accurately noted in reference to the time frame of the project. H. Included in this section will also be the following information: 1. Building Occupancy Classification 2. Building Construction Type 3. Building Elements Lists including the hour ratings and assembly designation 4. Building Seismic Criteria and Classification 5. Finish Material Ratings I. Also included within this section, for record and future reference, should be any granted Federal, State and/or City variances. J. All health care projects that fall under the jurisdiction of The Centers for Medicare and Medicaid Services (CMS) and/or The Joint Commission shall be designed to the 2000 Edition of the National Fire Protection Association 101 Life Safety Code. K. All health care projects that fall under the jurisdiction of The Joint Commission Shall be designed to the 2010 Edition of the Facility Guidelines Institute (FGI) Guidelines for the Design and Construction of Health Care Facilities 01 42 00 Design Documents Information Requirements Issued 6/30/04 Revised 10/17/11 Page 20 of 20 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS 1.01 1.02 Description A. Commissioning is a systematic process of ensuring that all building systems perform interactively according to the design intent and the owner’s operational needs. This is achieved by beginning in the design phase and documenting design intent and continuing through construction, acceptance and the warranty period with actual verification of performance. B. The commissioning process shall encompass and coordinate the traditionally separate functions of system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training. C. Commissioning during the construction phase is intended to achieve the following specific objectives according to the Contract Documents: 1) Verify that applicable equipment and systems are installed according to the manufacturer’s recommendations and to industry accepted minimum standards and that they receive adequate operational checkout by installing contractors. 2) Verify and document proper performance of equipment and systems. 3) Verify that O&M documentation left on site is complete. 4) Verify that the Owner’s operating personnel have received the required training. D. The commissioning process does not take away from or reduce the responsibility of the system designers or installing contractors to provide a finished and fully functioning system. E. The JLL@BHS Commissioning Steps process will be used as a guide for developing a commissioning plan. Coordination A. The Construction Commissioning Team will include Contractors, Subcontractors, and Equipment Manufacturers Representatives along with the System Designer, Engineer of Record, JLL@BHS Resident Engineer, JLL@BHS Facility Operations Staff, JLL@BHS Project Manager, Beaumont Fire Safety, and JLL@BHS Consultants. The entire team will participate in the development of a plan and schedule 01 91 00 General Commissioning Requirements Issued 6/30/04 Revised 10/17/11 Page 1 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS for the testing, start-up, and training for all new equipment building systems and infrastructure. This plan will be specific to the project. 1.03 B. All requirements for warrantees, testing, start-up, and training will be in the contract documents. The Commissioning Team in Step 2 of the JLL@BHS Commissioning Steps Process determined these requirements. C. The general contractor, construction manager or design/builder will integrate all commissioning activities into the master schedule. All Commissioning Team members will address any scheduling problems and make the necessary notifications in a timely manner to the general contractor, construction manager or design/builder in order to expedite the commissioning. Commissioning Process A. The commissioning plan provides guidance in the execution of the commissioning process. Just after the initial commissioning team meetings the JLL@BHS Project Manager will distribute to all the team members an updated plan which includes all their input. This will be considered the project’s “final” plan, though it will continue to evolve and expand as the project progresses. B. The following narrative provides a brief overview of the typical commissioning tasks as the project proceeds and the general order in which they occur. 1) Commissioning during construction begins with an initial meeting conducted by the JLL@BHS Project Manager where the commissioning process is reviewed with the commissioning team members. 2) Additional meetings will be required throughout construction. See project schedule. 3) Equipment documentation is submitted during normal submittals, including detailed start-up procedures. 4) The JLL@BHS Commissioning Team works with the contractors in developing startup plans and startup documentation formats. 5) In general, the checkout and performance verification proceeds from simple to complex; from component level to equipment to systems and intersystem levels with pre-functional checklists being completed before functional testing. 01 91 00 General Commissioning Requirements Issued 6/30/04 Revised 10/17/11 Page 2 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS 6) The contractors will execute and document the pre-functional checklists and performs startup and initial checkout. The JLL@BHS Commissioning Team documents that the checklists and startup were completed according to the approved plans. This may include the JLL@BHS Commissioning Team witnessing start-up of selected equipment. 7) The contractor develops specific equipment and system functional performance test procedures that are approved by the Commissioning Team. 8) The procedures are executed by the contractor, under the direction of, and documented by the JLL@BHS Commissioning Team. 9) Items of non-compliance in material, installation or setup are corrected at the contractor’s expense and the system re-tested. 10) The JLL@BHS Commissioning Team reviews the O&M documentation for completeness. 11) Commissioning is completed before Substantial Completion. 12) The JLL@BHS Commissioning Team reviews, pre-approves and coordinates the training provided by the contractor and verifies that it was completed. 13) Deferred testing is conducted, as specified or required. C. The cost of all testing, start-up, and training will be the responsibility of the contractors. This will include any testing equipment and re-testing necessary. The cost of the manufacturer’s representation for testing and training will the responsibility of the contractor. The number of hours along with the cost will be a separate line item in the bid. The cost of re-testing plus any costs incurred by other contractors for delays caused by the re-testing will be the responsibility of the contractor if the deficiency is theirs. If the contractor is not responsible the re-testing costs shall be negotiated with the JLL@BHS Project Manager. D. In addition to all required submittal data for approval of the equipment, O & M Manuals, and warrantee information, the contractor will be required to provide documentation on all testing, start-up, and training activities. This documentation will include but is not limited to: 01 91 00 General Commissioning Requirements Issued 6/30/04 Revised 10/17/11 Page 3 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS 1) 2) Installation, Start-up, and Check-out materials shipped with the equipment Factory or Field Check-out forms used by factory or field technicians 3) Pre-functional and Functional Test Procedures and Check Lists 4) Start-up and System Operational Procedures and Check Lists 5) Sequences of Operation, Control Drawings, Annotated PLC Ladder Logic printouts, or other equipment documentation. 6) Training Manuals 7) Re-testing of all deficiencies or non-conformance issues E. All forms and checklists will be developed by the contractor or subcontractor and will be specific to the equipment on this project. The JLL@BHS Commissioning Team will approve forms and checklists. F. Contractors will also be required to provide equipment data such as product numbers, make, model, location, serial numbers, and warranty information that is needed for the JLL@BHS equipment management system and warranty administration. The form used to document this information is included with this specification. This information will need to be provided before testing and training begins. G. All testing, start-up, and training will be scheduled in the Contractor’s Master CPM Schedule. Seasonal testing and deferred testing will also become part of this contract. Seasonal tests will be delayed until weather conditions are closest to the system’s design. Deferred tests due to the building structure, required occupancy phasing, or other deficiencies will be completed as soon as possible. Seasonal and deferred testing will follow the same procedures, be witnessed by the same personnel, and require the same documentation. A portion of Construction, Manager, Design/Builder, General or Subcontractor fees can be withheld until all testing is complete. H. Functional performance testing and verification may be achieved by manual testing or monitoring the performance and analyzing the results using the control system’s trend log capabilities. Simulating conditions may be allowed, though timing the testing to experience actual conditions is encouraged wherever practical. Each function and test shall be performed under conditions that simulate actual conditions as close, as is practically possible. The contractor executing the test shall provide all necessary materials, system modifications, etc. to 01 91 00 General Commissioning Requirements Issued 6/30/04 Revised 10/17/11 Page 4 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS produce the necessary flows, pressures, temperatures, etc. necessary to execute the test according to the specified conditions. At completion of the test the contractor shall return all affected building equipment and systems to their pre-test condition. I. The Engineer of Record, JLL@BHS Resident Engineer, and JLL@BHS Facility Operations Staff will be present at all Functional Tests and Start-up activities. The JLL@BHS Facility Operations Staff will designate the personnel to be present at the training sessions. All pre-functional and pre-start-up activities will be documented by the mechanical / electrical contractor and given to the JLL@BHS Project Manager before arrangements are made for the functional tests and start-up. At least 7 working days notice is needed. J. The contractor will submit at project closeout with the as-built drawings, a document verifying the following: K. 1) Systems were tested and function per design intent 2) Systems were installed per manufacturers recommendations and to industry accepted minimum standards 3) Systems received adequate operational check-out by installing contractors 4) Proper performance of equipment and systems was documented and given to the Owner. 5) O & M Manuals and as-built drawings are complete and accurate. 6) Training has been provided or funding for training has been provided for Owner’s operating personnel. The Engineer of Record, JLL@BHS Resident Engineer, and JLL@BHS Facility Management Staff will review and approve this document. 01 91 00 General Commissioning Requirements Issued 6/30/04 Revised 10/17/11 Page 5 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 01 - COMMISSIONING STEPS 1.1 COMMISSIONING STEPS Commissioning at Jones Lang LaSalle @ Beaumont Health System is a joint effort between Real Estate Development & Planning, Operations, and Engineering Support. Its purpose is to ensure that all hospital infrastructure, building systems and equipment are designed, installed, and operated correctly with proper operation and maintenance training, documentation, and quality control. Commissioning is a life cycle activity that starts at the beginning of design and carries on through the life of the project and, ultimately, the equipment. The Commissioning Team Leader is the Project Manager. They are ultimately responsible for completing the commissioning activities during design, construction/installation, and project closeout. They also brings the proper resources to the project at the appropriate time and act as a resource to Operations after the Project is complete. The Core Team Members are the Project Manager, Operations, the Resident Architect, the Resident Mechanical Engineer, the Resident Electrical Engineer, the Construction Manager, and the Technical Information Group. Team members listed below are in addition to the Core Team Members. Step No. 1 2 Commissioning Activity Project Phase Develop Project Commissioning Goals and Objectives: Review Project Scope Review Design Intent Review User Expectations Review Maintainer Expectations Develop Commissioning Scope Establish levels of Review Determine Agency Reviews & Submissions Determine Systems Testing Coordination Requirements Determine Warrantee Requirements and Planning/Programming 01 91 01 Commissioning Steps Planning/Programming Issued 6/30/04 Additional Team Members A/E, CM, Planner, Programmer, Infection Control, Beaumont Safety, Beaumont Fire Safety Deliverables/Expectations A/E, CM, Beaumont Fire Safety, Infection Control 1. Commissioning Responsibility Matrix 2. Commissioning Scope Statement Revised 10/17/11 1. Project Scope Delivered to Client and Commissioning Team 2. Commissioning Goals & Objective Statement Page 1 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 01 - COMMISSIONING STEPS Step No. 3 4 Administration Commissioning Activity Review Commissioning Scope as Applicable to Standards Determines which AMEP systems and equipment need to be commissioned Value Engineering Life Cycle Cost Analysis Lessons Learned Review Incorporate Commissioning Concerns during drawing and specification development Confirm system goals are being incorporated into drawings and specs Develop consensus on systems design Review standards and possible change Define shop drawing and asbuilt requirements Determine required testing Determines levels of testing: manufacturer, contractor, testing agency Define testing and forms Determine required submittals Define submittals and forms Determine required training Define training and forms Determine required operations manuals Determine required documentation Assign responsibilities 01 91 01 Commissioning Steps Project Phase Additional Team Members Deliverables/Expectations Planning/Programming A/E, CM 1. Commissioning Specification 2. Testing and Training Requirements defined. Design A/E, CM 1. Commissioning Check List Completed by Facility Services & Tech Services 2. Responsibility Matrix Issued 6/30/04 Revised 10/17/11 Page 2 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 01 - COMMISSIONING STEPS Step No. 5 6 7 Commissioning Activity Project Phase Develop Commissioning Schedule in conjunction with Construction Schedule Utility tie-ins Rough wall inspections Documentation & Photos Systems and equipment accessibility meetings Quality control meetings Pre-functional tests Functional Tests Project Close-out AHJ inspections Project Commissioning Close Out Development Edit Project Close-Out Check List to meet needs of Project Develop pre-functional and functional test forms specific to project Develop training forms specific to project Confirm as-built drawing requirements MEP System Change Validation Joint consultation and decision by all team members All changes to Standards reviewed and approved by Standards Committee All Changes Documented Bulletins/RFI’s issued and distributed Record Drawings Received Pre-Construction 01 91 01 Commissioning Steps Additional Team Members A/E, CM, Beaumont Fire Safety, JLL@BHS Safety, Infection Control, Subcontractors Deliverables/Expectations Pre-Construction Construction A/E, CM, Contractors, Vendors 1. Check Lists for inspection and testing 2. Training Schedule 3. As-built Drawing Monitoring Construction A/E, CM, Contractors, Beaumont Safety, JLL@BHS Safety, Infection Control 1. Minutes for Team Meetings to resolve issues 2. Dispute Resolution Documented 3. Bulletins Issued and Distributed for all changes Issued 6/30/04 Revised 10/17/11 1. Commissioning Schedule developed from Commissioning Check List 2. Construction Schedule that includes time for inspections, testing, training, close-out 3. Facility Services Schedule for Construction Walk-thrus Page 3 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 01 - COMMISSIONING STEPS Step No. 8 9 Commissioning Activity Project Phase Commissioning Acceptance Start-Up Testing completed and documented Maintenance training completed and documented User In-service completed Transfer of Warrantee Information to Facilities Services Operations and Maintenance Manuals given to Facilities Services Post-Occupancy Evaluation Final Payment Sign-off Standards revisions/modifications Life cycle cost analysis verification Update “Lessons Learned” List Pre-Occupancy 01 91 01 Commissioning Steps Post Occupancy Issued 6/30/04 Additional Team Members Beaumont Fire Safety, JLL@BHS Safety, Infection Control Deliverables/Expectations Beaumont Fire Safety, JLL@BJS Safety, Infection 1. Written Post-Occupancy Evaluation of Project 2. Updated Lessons Learned List 3. Standards Modification Submittals 4. Life Cycle Cost Analysis Review Revised 10/17/11 1. 2. 3. 4. 5. Signed Acceptance Documents Warrantee Information Given to FS IEI completed Equipment Tagged O & M Manuals delivered to Tech Library Page 4 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 02 ASSET TAGGING LIST (Equipment Requiring Product Data Information) Mechanical Air Handlers Humidifiers Cabinet Unit Heaters Domestic Water Heaters Medical Vacuum Pumps Medical Air Compressors Refrigeration Machine (Chiller) Forced Draft Steam Boilers Boiler Feed Pumps Condensate Pumps Medical Gas Alarm Panels Chilled Water Pumps Heating Hot Water Pumps Heat Recovery Unit Back Flow Preventers Hot Water Recirculating Pump Hoods (lab, exhaust, vent, etc.) Fans (Exhaust, Return, Roof Exhaust, Etc) Sub Stations Switchgear Motor Control Centers Paralleling Switchgear Emergency Generator Emergency Generator Remote Radiator Meters Master Clock System Automatic Transfer Switches Telemetry Power Panels Rated Doors Automatic Door Operators Platform Lift (Wheelchair) Elevators Dumbwaiters Pneumatic Tube Stations Domestic Water Booster Pump Sump Pump Sterilizers Condensate Receiver & Pump Unit Heater (Water) Unit Heater (Steam) Steam to water Heat Exchanger Lab Air Compressor Lab Air Desiccant Dryer Fan Coil Unit Duplex Instrument Air Compressor Instrument Air Dryer Air Conditioning Units Cooling Tower Tanks (fuel, condensate, water, etc.) Fuel Oil Pumps Dampers (Fire, Smoke, Combination) Variable Frequency Drives Electrical Distribution Panels Lighting Panels Isolation Panels Receptacle Panels Transformers Nurse Call Control Cabinets Closed Circuit TV System Alarm Panels Fire Alarm Panels Control Panels UPS Architectural Revolving Door Automatic Sliding Door Fire Extinguishers Conveying Systems Pneumatic Tube Blowers Pneumatic Tube Diverters Trash/Linen Chutes This list is not meant to be all-inclusive. All equipment that will need preventative or corrective maintenance should be included. 01 91 02 Asset Tagging List Issued 6/30/04 Revised 10/17/11 Page 1 of 1 Jones Lang LaSalle @ Beaumont Health System DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 01 91 03 CONTRACTOR INSTALLED EQUIPMENT INPUT FORM PO# (or Letter of Engagement #)** Project # Information Supplied By: Contractor Contractor Contractor Contractor Contractor Contractor Contractor Contractor Contractor Contractor Unit ID # Equip First Line of Description Facilitech Rm # Vendor / Contractor Manufacturer Serial Number Model # Cost Install Date Warranty Period **Where the PO# or EL# are different than the main PO# / EL#, please indicate the different number in the spreadsheet column / row related to that particular piece of equipment. All blank rows will be associated with the number indicated at the top. 01 91 03 Contractor Installed Equipment Input Form 1 Issued 6/30/04 Contractor Contractor Contractor Warranty Service Contact Drawing # Submittal la/karen contractor installed equip input form Revised 10/17/11 Page 1 of 1 Construction / Design Standards Electrical Standard No. Standard Name Current Previous Revision Summary Revision Date Revision Date Author 26 00 00 Basic Electrical Requirements 10/17/11 6/30/04 Updated Standard No. Jherschelman 26 05 13 Wire and Cable 10/17/11 6/30/04 Updated Standard No. Jherschelman 26 05 33.16 Boxes 10/17/11 6/30/04 Updated Standard No. Jherschelman 26 05 33.23 Raceways 10/17/2011 7/29/11 26 05 53 10/17/2011 7/29/11 1.01 C. 1. added, 1.02 !.2 added, updated Standards No Jherschelman Identification 1.05 h) added. "Life Safety removed from 1.05 a), Updated Standards No. 26 05 83 Wiring Connections & Connecting Devices 10/17/2011 7/29/11 1.01 B revised, Updated Standards No. Jschwartz Jherschelman Jherschelman 26 09 00 Electrical Monitoring & Control System 10/17/2011 11/19/08 See sections 1.01, B-5 and 2.01, B, Updated Standards No. Jschwartz Jherschelman 26 11 00 480 Volt Substations 10/17/2011 7/13/10 1.01 A4d - i-iv Closed Transition, add IRISS to 1.01.9.b, Updated Standards No. Jschwartz Jherschelman 26 18 36 Fuses 10/17/11 6/30/04 Updated Standard No. Jherschelman 26 33 53 Uninterruptible Power Supply 10/17/2011 7/29/11 Deleted MGE from 1.02 A, Updated Standards No. Jherschelman 26 50 00 Lighting Systems 10/17/2011 7/29/11 Added 1.02 L., Updated Standards No. Jherschelman 27 00 00 Telephone Data Requirements 10/17/2011 2/23/11 New Section, Dmeyers, Jherschelman 28 31 00 Fire Alarm Desing Requirements 10/17/11 5/24/10 New Section, Updated Standards No. FA/FS, JHerschelman 28 31 01 FA Design Drawings 10/17/11 TBD Updated Standard No. FA/FS, JHerschelman 1/24/2012 O:\FD_BuildingStds\JLL BHS Standards\Standards Update Tracker New #s 072811.xls Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN / CONSTRUCTION GUIDELINES & STANDARDS ELECTRICAL Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN / CONSTRUCTION GUIDELINES & STANDARDS ELECTRICAL TABLE OF CONTENTS Section - Index 26 00 00 - Basic Electrical Requirements.......................................................................... 1 26 05 13 - Wire & Cable .................................................................................................... 2 26 05 33.16 - Boxes .......................................................................................................... 3 26 05 33.23 - Raceways.................................................................................................... 4 26 05 53 - Identification ......................................................................................................5 26 05 83 - Wire Connections & Connecting Devices......................................................... 6 26 09 00 – Electrical Monitoring & Control System ............................................................7 26 11 00 – 480 Volt Substations ....................................................................................... 8 26 18 36 - Fuses ............................................................................................................... 9 26 33 53 – Uninterruptible Power Supply ..........................................................................10 26 50 00 - Lighting Systems.............................................................................................. 11 27 00 00 – Telephone Data Requirements.........................................................................12 28 31 00 – Fire Alarm Design Requirements .....................................................................13 28 31 01 – Fire Alarm Design Drawings (TBD) ..................................................................14 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 00 00 BASIC ELECTRICAL REQUIREMENTS PART 1: GENERAL 1.01 SYSTEM DESCRIPTION A. Seismic Requirements for the following equipment shall be provide - as defined by BOCA for essential facilities: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. All conduits 2 ½” and larger. All bus ducts. Primary switchgears. Medium voltage distribution systems. Transformers. Unit substations. Distribution panels. Power panels. Panelboards. Operating Room Hospital isolation Panels. Motor Control Centers. Uninterruptible Power Supply (UPS) Systems. Emergency Power Supply System. (EPSS) a) Generator. b) Parallel switchgear. c) Automatic Transfer Switches. Variable frequency drives. Light fixtures. Cable tray Fire alarm panels B. Mounting Heights: to centerline of outlet box or equipment, unless otherwise noted. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Bracket outdoor fixtures – 12 inches above door frame if above door, or even with the top of door frame if mounted at side of door. Bracket mirror lighting fixture – above mirror. Bracket exit lighting fixtures – 6’-8” to bottom of fixture for ceiling up to 9 feet. Mount at 8’-0” to bottom for ceiling higher than 9 feet. Recessed exit light fixture – above door, midway between top of door frame and ceiling if ceiling is 8 feet or 9 feet. For higher ceiling, mount 12 inches above door. Switches – 3’-10”. Receptacles, finished areas – 1’-6”. Receptacles, behind furniture partition system - 6” horizontally to top of box. Receptacles, mechanical rooms – 3’-0”. Clock outlets – 6’-8” to bottom of clock. Tel/Com outlets, desk mounted – 1’-6”. Tel/Com Outlets, behind furniture partition system - 6” horizontally to top of box. Telephone outlets, wall mounted – 4’-6” (to coin slot for Barrier Free). 26 00 00 Basic Electrical Requirements Issued 6/30/2004 Revised 10/17/11 Page 1 of 6 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 00 00 BASIC ELECTRICAL REQUIREMENTS 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. Safety switches – 4’-10”. Motor starters – 4’-10”. Panel cabinets – 6’-8” to top, providing bottom of cabinet is not less than 12 inches above the floor. Fire alarm pull stations – 3’-10”. Push buttons – 3’-10”. Fire alarm chime/speaker/bell – 6’-8” to bottom of device. Fire alarm strobe – 6’-8” minimum to bottom of device, 8’-0” maximum to top of device. Fire alarm audio/visual – 6’-8” minimum to bottom of device, 8’-0” maximum to top of device. . T.V. outlets – 1’-6”. Nurse call system. a) Patient station – 3’-10. b) Emergency call stations – 3’-0”. c) Duty station – 4’-6”. d) Corridor dome light – 7’-6”. C. System coordination and short circuit study. 1. The cost of a coordination and short circuit study, and breaker trip settings shall be included in the project. Studies shall be performed by an independent testing agency selected by Beaumont Services Company LLC. The coordination study shall include a list of all relay settings as determine for optimum performance. 2. Breaker trip settings, and all adjustable relay setting shall be determined, and set, by the same independent testing agency that did the studies. D. When ground-fault protection is provided at the service main(s), an additional step of fault protection shall be provided at the next level of protection downstream. Ground-fault protection devices shall be fully adjustable to provide selective coordination. Downstream devices shall be coordinated to open before the main. The purpose of this requirement is to limit the effects of a ground fault on the distribution system. A fault to ground in a distribution branch must not cause an entire area to lose power. After ground-fault equipment has been installed it shall be performance tested at each level of protection. E. Every effort shall be made to provide adequate power outlets. This is necessary so that portable plug-in-strips will not be required in the future. Temporary wiring methods must not be a future solution the lack of permanent wiring devices. Pay particular attention to receptacle layouts for offices and nurses stations. F. Branch Circuits 26 00 00 Basic Electrical Requirements Issued 6/30/2004 Revised 10/17/11 Page 2 of 6 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 00 00 BASIC ELECTRICAL REQUIREMENTS 1. Design spare capacity into branch circuits. Use lighting/power plans and panelboard schedules to indicate where branch circuits are used and loaded. Do not connect more than 1200 watts of lighting fixtures to any 20-ampere, 120-volt branch lighting circuit. Do not connect more than 3200 watts of lighting to any 20 ampere 277 volt branch lighting circuit. Limit the quantity of duplex receptacles on a typical general use receptacle circuit (120-volt, 20 ampere) to six (6). 2. Do not connect single phase motor loads to a general purpose or special receptacle circuit. Connect all single or three phase motor loads to independent circuits. 3. Do not connect power receptacles to lighting circuits. 4. Install Life Safety Branch circuits in a separate raceway system. Do not install Life Safety Branch, or Critical Branch, circuits in raceway containing normal power, except as permitted by the NEC. Install wiring for hospital essential electrical system in accordance with NFPA 70 and NFPA 99 (latest editions). 5. Branch circuit wires shall be sized for a maximum 3% voltage drop, based on copper cables, 86°F ambient, maximum 80% power factor and 80% circuit rating. Distance shall be one way from the panelboard to the farthest outlet or load. Minimum wire sizes shall be determined by the following table: Maximum Distance for Branch Circuit Wiring AWG 120V, 20A circuit 277V, 20A circuit #12 50ft 120ft #10 90ft 200ft #8 130ft 300ft 6. Where conduit sizes are not indicated, install sizes per NEC requirements, except do not use conduit smaller than 1/2 inch unless otherwise specified. 7. Wiring responsibilities: Designer’s specification shall indicate that the electrical contractor is responsible for wiring 120v power to smoke / fire dampers. Designer is responsible for providing circuiting on the construction documents. Electrical Contractor is responsible for providing connected circuit designation on the as-built drawings. 26 00 00 Basic Electrical Requirements Issued 6/30/2004 Revised 10/17/11 Page 3 of 6 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 00 00 BASIC ELECTRICAL REQUIREMENTS G. The Electrical Contractor shall warranty the electrical work for a period of one year from the date the electrical system is accepted by the BSC Project Manager. The warranty shall include parts (necessary for repairs at the job site), labor, travel, and expendables (used during the course of repair such as hardware, oils, tools, filters, cleaning agents and other service items used in the course of repair). H. Construction Drawings 1. 2. I. Show the following information on the construction drawings: a) SITE PLAN: Show electrical items including, but not limited to, exterior feeders, manholes, duct banks, primary switches, transformers, lighting fixtures, and existing underground utilities in the vicinity of the work being done. b) KEY OR LEGEND: Use BSC Standard graphic symbols. Symbols shall be sized for the format in which they will be printed. c) FIXTURE SCHEDULE: Shall indicate type; mounting height; number and type of lamps; number and type of ballast; finish when appropriate; method of mounting; manufacturer's name and catalog number; and two other acceptable manufacturers, when appropriate. Do not use "or equal." d) PANELBOARD AND SWITCHBOARD SCHEDULE: Shall include bus rating; circuit identification; circuit breaker description, including AIC rating; and the connected load on each circuit in amperes, or kW. Indicate total connected load, number and size of spare, and space, positions and demand load. Group the panelboard schedules together. e) ONE-LINE DIAGRAM: Every project that changes the electrical distribution system shall include a one-line diagram. Riser diagrams are not a substitute for a one-line diagram. The one-line diagram shall be compatible with the BSC record one-line drawing. The diagram shall be treated as a modification to the record one-line, and shall be capable of being inserted into the original document without changing the scale, or symbolism. Drawings shall be produce in accordance with the BSC, Technical Information Group, CAD Guidelines Manual. As-Built Drawings 1. The installing electrical contractor and the low voltage and signal subcontractors shall prepare detailed as-built drawings of the final installation. 2. A separate set of as-built drawings shall be produced for each electrical system. System drawings shall include: power, lighting, fire alarm, nurse 26 00 00 Basic Electrical Requirements Issued 6/30/2004 Revised 10/17/11 Page 4 of 6 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 00 00 BASIC ELECTRICAL REQUIREMENTS call, music and paging, TV, telemetry, physiological monitoring, data/communications, security, Cutler-Hammer PowerNet, ASCO Thin Web Server, and all other specialty systems installed. 3. As-built drawings shall not be a reproduction of the design documents. 4. The power as-built shall include a one-line drawing that is an exact representation of what has been installed. The one line shall include breaker and fuse sizes and the correct numbered positions of the breakers and fuses within the substations and panelboards. J. Energy Conservation 1. Energy conservation measures must be given early consideration (preliminary design phase) of the construction project. Review and coordinate all disciplines within the design team to achieve the optimal, energy efficient, design. 2. Consider the available lighting system ballasts, lamps, and controls, transformers, UPS, motors, and VFD’s when designing for the best energy efficiency. 3. Evaluate energy saving devices (e.g. motion sensors, photo sensors, time switches, etc) for cost effective implementation. Calculate the projected energy cost of various design alternatives. Use these devices if payback can be shown to occur within two years. 4. Minimize IR losses in the power distribution system. K. Magnetic Flux 1. Do not place electrical distribution equipment that generates high magnetic flux in the vicinity of sensitive electronic, or medical, equipment. 2. Some of the equipment that produces high flux includes: large transformers, large motors, distribution bus, UPS and other equipment and loads that draw substantial current. L. Monitoring systems 1. Cutler Hammer, PowerNet is used to monitor power at Substation mains and other selected distribution branches. Addition to this system shall be determined in the design phase of a project integrated into the existing network to obtain maximum, data acquisition, and performance. The Engineer of Record shall coordinate the design with Cutler Hammer engineering and use the master, BSC, 26 00 00 Basic Electrical Requirements Issued 6/30/2004 Revised 10/17/11 Page 5 of 6 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 00 00 BASIC ELECTRICAL REQUIREMENTS TIG document to show any addition(s), or modification(s), to the Cutler Hammer network. The section of the master document modified by the addition(s), and the costs for changing the program and graphic display, shall be included in the construction cost. 2. The Cutler Hammer E-Bill program is used for energy management purposes. Consult with JLL@BHS’s Energy Engineer for loads that need to be monitored by this system. The data for this program is obtained from the PowerNet system (described in item #1 above). At a minimum, a Cutler Hammer IQ Energy Sentinel shall be installed at the secondary main breakers of all new substations and at other selected locations as determined by the BSC Energy Engineer in the design phase of the project. The cost of the network connection and programming of each device shall be included in the construction cost. 3. ASCO’s Thin Web Server is used to monitor emergency power generators, parallel gear and automatic transfer switches. Additions to this system shall be determined in the design phase of a project integrated into the existing network to obtain maximum, data acquisition, and performance. The Engineer of Record shall coordinate the design with ASCO engineering and use the master, BSC, TIG document to show any addition(s), or modification(s), to the ASCO network. The section of the master document modified by the addition(s), and the costs for changing the program and graphic display, shall be included in the construction cost. 4. The Engineer of Record shall use the master document to show any addition(s), or modifications to the ASCO network. The section of the master document modified by the addition(s) shall be included in the contract documents. 5. Additions, or modifications, to monitoring systems shall be integrated with the existing networks so that performance is not degraded. 26 00 00 Basic Electrical Requirements Issued 6/30/2004 Revised 10/17/11 Page 6 of 6 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 13 WIRE and CABLE PART 1: GENERAL 1.01 DESCRIPTION A. Medium voltage cable. Greater than 600 and less than 69kV. 1. 2. 3. B. Connectors a) Connectors for splicing copper conductors: b) Connectors for straight splicing conductors: solderless compression 2-way type. c) Connectors for 3-way splicing conductors: solderless compression type. Lugs for terminating copper conductors: a) Solderless compression type, one hole for sizes through No. 4/0 AWG, and two hole for larger sizes. Stress Cones b) For indoor installation, use kit rated 15 KV. Installation shall be in conformance to cable manufacturer's requirements. Drain wires and shielding tape. a) Effectively ground at both ends. b) Prove effective ground continuity at all splices. 4. Apply fire wrapping to all cabling in all manholes and vaults 5. Labeling a) All cable shall be labeled in manholes, pull boxes and cable vaults b) Labeling shall indicate the phase and source of power. Low voltage wiring. Less than 600-volts 1. Furnish copper conductors of 98% conductivity unless otherwise specified 2. Conductors shall not be less than No. 12 AWG, except control conductors which may be No. 14 AWG, and signal system wiring which will be sized according to system manufacturer’s requirements.. 26 05 13 Wire And Cable Issued 6/30/2004 Revised 10/17/11 Page 1 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 13 WIRE and CABLE C. 3. Furnish solid conductors for sizes No. 14 AWG and smaller, and stranded conductors for sizes No. 12 AWG and larger 4. Color coding for branch circuits and feeders: 480/277 Volt 208/120 Volt Phase A Brown Black Phase B Orange Red Phase C Yellow Blue Neutral Gray White Ground Green Green 5. Wire for final connection in conduit to incandescent fixtures, HID fixtures with remote ballasts, and remote ballasts shall be stranded copper, NEC Type SF-2 rated 200 deg. C, 600 volts. 6. Wire for use in fluorescent fixture wiring channels shall be stranded copper, NEC Type RHH, THHN, or XHHW, rated 90 deg. C, 600 volts. 7. Wire for exposed cord connection to fluorescent Fixtures shall be three conductor stranded copper; NEC Type SO rated 60 deg. C, 600 volts 8. Wire for General Interior and Exterior Work shall be single conductor, annealed copper, rated 600 volts as follows: a) NEC Type THWN, rated 90 C, dry and damp location. b) NEC Type XHHW, rated 90 C, dry and damp location and 75 C, wet location Armored Cable, AC (Type HFC) 1. AC shall be UL Listed for Health Care Facility (HFC). Flexible armored cables shall not be utilized for any emergency system (life safety, critical or equipment) branch wiring, except as permitted in NEC, Article 517. 26 05 13 Wire And Cable Issued 6/30/2004 Revised 10/17/11 Page 2 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 13 WIRE and CABLE 2. Wire for general flexible armored cables: The galvanized steel armor cable shall be NEC Type AC, Multi-conductor cable, stranded, copper wire, THHN (90 Deg C) insulation, 600 volt rated. Cable shall contain a bare grounding conductor and an insulated ground conductor. 3. Do not substitute MC for HFC. One of the most important differences between these two cable types is the grounding means of the assembly. Type MC has only one equipment grounding means, a green grounding conductor. Type HFC cable uses the interior bond wire in combination with the exterior interlocked metal armor as the equipment grounding means of the cable. Type MC cable is manufactured with a green insulated grounding conductor, and this conductor, in combination with the metallic armor, produces a redundant equipment ground system. 4. The bare wire in Type AC cables is a bonding wire to enhance the ground fault capability of the interlocked outer metal armor. It does not have to be terminated like a bare grounding conductor because that is not its function. This bare bond wire may be trimmed off to the same length as the armor, or, brought up and over the red antishort bushing and back wrapped over the armor. 5. HFC can be utilized for normal branch wiring in concealed dry areas. Do not use in exposed areas, such as mechanical rooms. Do not use for home runs. 6. Flexible armored cables shall be securely supported per the requirements of NEC, Article 333. Support shall be made at intervals not exceeding 54-inches at within 12-inches of junction box D. Wire for Direct Burial or In Underground Duct or Conduit shall be single or multi-conductor, NEC Type USE rated 75 deg C, 600 volts. E. Multi-Conductor Control Cable for Installation in Conduit shall be consisting of 7 strand annealed copper individual conductors insulated with 26 mils linear polyethylene and 4 mils nylon, or 20 mils HMW polyethylene and 10 mils PVC, rated 90 deg C, 600 volts, color-coded per IPCEA, cabled round with fillers and binder tape, and covered with an overall jacket of PVC. F. Wire for use in High Temperature Areas as required shall be single conductor, annealed copper; NEC Type SA rated 125 deg C, 600 volts. G. Wiring of Branch Circuits and Grounding Systems for Hospital Isolated Power Centers (IPC). 26 05 13 Wire And Cable Issued 6/30/2004 Revised 10/17/11 Page 3 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 13 WIRE and CABLE 1. The State of Michigan no longer amends the NEC to require IPC in Hospital OR’s. IPC’s are required in certain wet locations, but in general their use will not be required. Verify wet use classification with the hospital governing authority. When IPC’s are used the wiring guidelines below shall be used. 2. Conductors shall be single conductors, annealed copper rated 60 volts, low leakage insulation with a dielectric constant of 3.5 or less. NEC type XHHW-2, rated for 90 deg. C, dry and wet locations. 3. Do not use wiring pulling compound to pull on IPC branch circuits. 4. Follow NEC color code requirements. 5. Switching in isolated circuits shall be two pole. 6. Limit the length of the branch circuit conductors, and the number of receptacles severed by one branch, to lessen the amount leakage current. H. Provide and secure labels identifying phase and neutral cables with circuit number (to identify origin of circuit i.e., circuit breaker position or switch position) for all cables in all terminal cabinets, panelboards, distribution, control and load centers, pull boxes and wherever conduit run is accessible. Mark the white marking strip of all control terminal blocks, with the same identification as the connecting wire, in permanent black ink. I. Multiwire branch circuits are allowed. Where circuits are known to serve loads that will create large harmonic currents, install a separate neutral wire for each single phase wire, or increase the size of the neutral to accommodate the total harmonic current anticipated. PART 2: PRODUCTS 2.01 MATERIALS A. Manufacturers: Medium voltage cable. Greater than 600 and less than 69kV 1. 2. 3. 4. 5. 6. Okonite Cabled Pirelli Phelps Dodge Rome Southwire 26 05 13 Wire And Cable Issued 6/30/2004 Revised 10/17/11 Page 4 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 13 WIRE and CABLE B. Manufacturers: Low voltage wire and cable. Less than 600-volts 1. Low voltage wire a) b) c) d) e) f) g) h) i) j) 2. B. American Insulated Wire Corp. Cablec Carol General Cable Corporation Okonite Pyrotenax Rockbestos Rome Cable Corp. Southwire Triangle PWC, Inc. Flexible armored cables shall be as manufactured by AFC, Series HCF-90 or equal with galvanized steel armor. Wire - Labels Low voltage wire and cable. Less than 600-volts 1. Wire labels for identification of conductors, shall be flame resisting, adhesive type. See Electrical Identification, Section 16195, for additional information. a) Brady b) Westline 26 05 13 Wire And Cable Issued 6/30/2004 Revised 10/17/11 Page 5 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.16 BOXES PART 1: GENERAL 1.01 SYSTEM DESCRIPTION A. Outlet boxes 1. 2. Sheet Steel Boxes: a) Galvanized or sherardized stock, 4 square x 2-1/8" deep. Boxes shall be not less than No. 14 gage b) All wiring device boxes for Duplex Receptacles, switches, data processing outlets and telephone outlets shall be nominal 4-inches square by 2-1/8 inches deep, with appropriate extension ring to bring box to no greater than ¼” from the surface of the finished wall. Use double device extension ring for double duplex receptacle and single device extension ring for single duplex receptacle. c) Boxes installed in combustible wall surfaces shall be flush with the wall, with knockout openings, single or multiple gang, with extensions, adapters, plaster rings, tile covers, fixture studs and cover plates. d) Provide accessories with same gage and finish as specified for boxes, except where special finishes are specified for covers and device plates. e) Provide sizes per NEC requirements for wiring space, except where minimum sizes are specified. f) Do not install recessed wall boxes back to back. g) Recessed boxes shall not compromise fire rated walls. When boxes are installed in fire rated walls, use construction methods that will maintain fire rating. h) All boxes shall have covers. Blank covers in finished areas shall be finished to match color of wall in which they are installed. i) Boxes for room lighting switches shall be installed on latch side of door within 12” of door frame. Cast boxes for dry locations a) 26 05 33.16 Boxes Use cast boxes for wiring devices installed outdoors or indoor for exposed construction. Issued 6/30/04 Revised 10/17/11 Page 1 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.16 BOXES 3. b) Cast boxes can have blank treaded fittings with plugs, but they shall not have knock-outs. c) Where an interior box is attached to an exterior wall, provide a 1/8” air gap between the back of the box and the wall to prevent corrosion of box due to condensation. Cast boxes for damp or wet locations. a) Receptacles in wet locations shall be installed with an outlet enclosure clearly marked "Suitable for Wet Locations While in Use". There must be a gasket between the box and the cover plate and between the cover plate and the hinged cover. The receptacle cover shall have a port to allow two 3/8" diameter cords to pass through. The enclosure must employ stainless steel mounting hardware. 4. In wet locations, or where an interior box is attached to an exterior wall, provide a 1/4-in air gap between the back of the box and the wall. 5. In damp or wet locations, surface-type enclosures within the scope of this standard shall be placed or equipped so as to prevent moisture or water from entering and accumulating within the cabinet or cutout box, and shall be mounted so there is at least 1/4in. airspace between the enclosure and the wall or other supporting surface. Enclosures installed in wet locations shall be weatherproof. 6. Conduit boxes for hazardous areas. Galvanized, cast or malleable iron, with threaded hubs and threaded covers, approved for use in Class 1, Group A, B, C, or D areas as applicable. Provide sizes per NEC requirements for wiring 7. Floor boxes: 26 05 33.16 Boxes a) Poke through fittings (for flush or pedestal mounting) prewired, suitable for 2-1/4" - 7" thick concrete floor, U.L. classified for fire resistance in 1-2 hour rated floors, complete with upper stationary and lower adjustable fire barriers that expand during fire conditions to provide a fire seal. b) Flush box shall have flush carpet flange, thermoplastic cover assembly, spring loaded self-closing lift covers, ability to handle power, data and communication services in a single unit, internal divider to separate power and low voltage wiring and integral factory installed junction box that will fit through 3" hole. c) Pedestal mounted box Issued 6/30/04 Revised 10/17/11 Page 2 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.16 BOXES B. Pull and junction boxes: Box and cover shall be made of galvanized steel. Box and cover shall be galvanized after fabrication. Gray painted finish. Keyhole screw slots for plated screws. Box shall be made of Code gauge steel and shall not have factory knockouts. 1. Install boxes in an accessible location. Access shall not be blocked by the work of any trade. 2. When a box is installed on the an exterior wall use spacers to provide a minimum 1/8” air gap between back of box and wall surface. PART 2: PRODUCTS 1.01 SYSTEM DESCRIPTION A. Outlet boxes 1. Sheet Steel Boxes a) Wall and junction boxes i. ii. iii. iv. 2. Partition and Channel Mounting Boxes: Trim line Type. a) b) c) d) e) 3. Raco 426 and 427 Appleton Steel City Appleton Steel City Cast boxes a) Galvanized or cadmium plated, single or multiple gang, with taper threaded hubs, adapters and cover plates. i. ii. iii. b) Appleton Crouse-Hinds Pyle-National Outdoor receptacle enclosures (for surface mounted case box) i. ii. iii. 26 05 33.16 Boxes Appleton Hoffman RACO Steel City TayMac Hubbell Cooper”WeatherBox” Issued 6/30/04 Revised 10/17/11 Page 3 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.16 BOXES c) Outdoor receptacle enclosures (for recessed case box) i. TayMac ii. Hubbell iii. Cooper”WeatherBox d) Conduit boxes for hazardous areas I. II. III. IV. B. Boxes, greater than 4 Inches by 4 Inches. Sheet Metal Boxes: Code gage, full seam welded with bent-in flanges seam welded at corner joints, screw fastened cover of same gage as box. Fasten cover with brass machine screws. Painted galvanized box and cover. 1. 2. 3. 4. 5. 6. 7. C. Hoffman OZ/Gedney OZ/Gedney Appleton Crouse-Hinds OZ/Gedney Pyle-National Fire rated poke through fittings 1. 1.02 Appleton Crouse-Hinds Pyle-National Killark Hubbell SYSTEM DESCRIPTION A. OUTLET BOXES B. Seismic Requirements: As defined by BOCA for essential facilities: 1. Partition and Channel Mounting Boxes: Trim line Type. 2. Raco 426 and 427 a) b) c) d) 26 05 33.16 Boxes Appleton Steel City Appleton Steel City Issued 6/30/04 Revised 10/17/11 Page 4 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.23 - RACEWAYS 1.01 SYSTEM DESCRIPTION A. Definition of Raceway: An enclosed channel of metal or nonmetallic materials designed expressly for holding wires, cables, or busbars. Raceways include, but are not limited to, rigid metal conduit, rigid nonmetallic conduit, intermediate metal conduit, liquid tight, flexible conduit, flexible metallic tubing, flexible metal conduit, electrical nonmetallic tubing, electrical metallic tubing, underfloor raceways, cellular metal floor raceways, surface raceways, wireways, and busways. B. In general, all conduit shall be, galvanized steel, EMT (minimum ¾”) with the following exceptions: 1. Where larger size is required by NEC for wire size and conduit fill. 2. In sizes 5” and larger. 3. In exterior, or underground, installations 4. Where ½ " EMT is adequate for single branch circuits, switch legs, or control wires. 5. Exposed exterior conduit concealed above 10' A.F.F. shall be rigid galvanized steel, or IMC. 6. 4800 volt medium voltage cable shall be installed in rigid galvanized steel conduit, or IMC. 7. Exposed interior conduit below 10' A.F.F. shall be rigid galvanized steel, or IMC. Rigid aluminum conduit shall be permitted in existing situations where its lighter weight would reduce installation costs. When aluminum is used consideration shall be given to galvanic corrosion. Where practicable, dissimilar metals in contact anywhere in the system shall be avoided to eliminate the possibility of galvanic action. 8. Flexible metal conduit may be used for interior light fixtures above suspended ceilings, maximum length 6 feet. Flexible metal conduit shall be steel – aluminum conduit is not acceptable. 9. Flexible metal conduit may be used for connections to vibrating equipment; i.e. transformers and motors. Flexible conduit shall be liquid tight where subjected to moisture. 10. In lieu of EMT, HFC (AC with redundant ground ) may be used for nonemergency branch circuits. 11. Heavy wall PVC is acceptable to use in parking structures where not exposed to physical damage. 26 05 33.23 – Raceways Issued 6/30/2004 Revised 10/17/11 Page 1 of 7 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.23 - RACEWAYS C. Underground conduit 1. For existing underground / under slab systems, GPS (ground penetrating radar) or equivalent survey shall be conducted prior to floor cutting or drilling to verify location of existing systems. 2. Install caution tape 18-inches above all underground conduit and duct banks. 3. Conduit under slabs or exterior below grade may be schedule 80 PVC, or schedule 40 when encased reinforced concrete with a minimum cover of 3-inches.of concrete. 4. Duct banks shall be installed to slope away from building and toward manholes. 5. PVC conduit installed in concrete duct banks shall be anchored down before concrete encasement is poured to prevent conduit from floating during the pour. 6. Use rigid conduit for all conduit ell’s and where conduit penetrates walls or floor slabs. Intent is to prevent: 1. The heat of friction from melting PVC and damaging cable, and 2. Physical damage to raceway at wall and floor penetrations during construction. 7. Concrete encasement shall be reinforced with steel re-rod and ties. 8. Contact AHJ before back filling. 9. Supports for cable and conduit in manholes shall be heavy duty nonmetallic glass reinforced polymer. 10. Manholes shall be supplied with sumps. 11. Prefabricate reinforced concrete manholes are acceptable. 12. Manhole covers shall be rated for vehicular traffic. D. NEC derating factors will dictate the use larger conductors and conduit as the quantity of current carrying conductors in a raceway increases. To contain the cost of conduit and wiring, limit the number of current carrying, branch circuit, conductors in a single raceway to nine, or less. Use multiwire circuiting where possible. Do not use multiwire circuiting where separate neutrals are required; e.g. where harmonic current will be present. E. The preferred method of connecting E.M.T. shall be with the use of compression fittings: however, malleable steel set screw fittings are acceptable. Cast metal set screw fittings are not acceptable. 26 05 33.23 – Raceways Issued 6/30/2004 Revised 10/17/11 Page 2 of 7 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.23 - RACEWAYS F. All cut ends of conduit must be reamed, to remove rough edges and protect the wire insulation from abrasion. G. Conduit shall be provided with an end bushing to protect the wiring within from abrasion, except where the conduit enters a box, fitting, or other enclosure designed to provide equivalent protection. H. PVC conduit used in outdoor environments, or in other areas of widely varying temperature, shall be installed using expansion fittings. Expansion shall be based on a temperature differential of 100° F. I. Insulation shall be installed in conduit that passes between areas of different temperature to prevent condensation from forming inside conduit and attached enclosures. In particular, insulation shall be installed in conduit entering from underground duct banks, or an exposed outdoor environment. J. Cable tray K. 1. Cable tray can be used for low voltage wiring. 2. Cable Tray for Power Cable Runs: NEMA Type A, ladder type, hot-dip galvanized steel with 12 inch rung spacing and a minimum of 4 inch inside depth from top of rung to top of outside rail. 3. For ladder tray, rung spacing shall not exceed 12 inches. 4. Provide anchor clips for attachment of cable 5. Horizontal and vertical bends, tees, crosses, reducers, hangers, splice plates, expansion fittings, adapters and other accessories designed for use exclusively with the tray and so designed as to enable "site" assembly, fitting and erection without the use of special tools 6. Cable tray installation shall be accessible. 7. A minimum clearance of 12-inches shall be maintained above the cable tray. 8. When cable tray changes direction the transition shall be made with radius bends. Busway. Routing of busway shall consider the affects of magnetic flux. Busway shall not be installed in close proximity of occupied areas, or in areas where sensitive electronics are used. 26 05 33.23 – Raceways Issued 6/30/2004 Revised 10/17/11 Page 3 of 7 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.23 - RACEWAYS L. Wireway. 1. Painted steel enclosure with screw fastened cover, bends, elbows, tees, crosses, adapters and accessories 2. Covers of recessed wireways shall be flush with the finished surface of wall in which they are installed. 3. Surface mounted wireways shall have hinged covers. 4. Surface mounted wireways shall not have knock-outs. 5. Provide sizes as required per NEC Article 362 requirements for wiring space, except where larger sizes are indicated. 6. Provide gaskets when located in outdoor areas and in other areas requiring gaskets. 1.02 PRODUCTS A. CONDUIT 1. Rigid Steel Conduit, Elbows, and Couplings: Zinc-coated threaded steel per ANSI C80.1 "Specification for Rigid Steel Conduit, Zinc-coated". Each length of conduit shall be threaded on both ends. a) b) c) d) 2. Intermediate Metal Conduit, Elbows and Couplings: Hot-dipped galvanized per ANSI C80.6 "Intermediate Metal Conduit". Each length of conduit shall be threaded on both ends. a) b) 3. Allied Triangle Electrical Metallic Tubing: Zinc-coated steel per ANSI C80.3 "Specification for Electrical Tubing, Zinc-coated". a) 4. Allied Republic Triangle Wheatland Triangle Flexible Steel Conduit: Per UL-1, "Flexible Steel Conduit". a) b) 26 05 33.23 – Raceways AFC Triangle Issued 6/30/2004 Revised 10/17/11 Page 4 of 7 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.23 - RACEWAYS 5. Liquid-Tight Flexible Steel Conduit: Per UL-360 "Liquidtight Flexible Steel Conduit, Electrical". a) b) 6. Explosion proof Flexible Metal Conduit: Approved for use in Class I, Group A, B, C and D areas and not requiring a bonding jumper. a) b) c) 1. Appleton Type "EX" Crouse-Hinds Type "EC" OZ/Gedney Type "EC" CONDUIT FITTINGS Fittings for Rigid Steel or Intermediate only, cadmium or zinc-plated, with taper threads, and screw attached cover plates. Provide gaskets when located in areas requiring gaskets. a) b) c) 2. AFC "Sealtite" Electriflex Appleton Form 35 Crouse-Hinds Form 8 OZ/Gedney Form 35 Expansion Fittings for Rigid Steel or Intermediate Metal Conduit: Cast or malleable iron bodies, with threaded end caps for receiving fixed and movable conduits, metallic pressure packing and copper bonding jumper assembly, and providing for a minimum of 2 inches movement of the conduit in either direction. a) b) c) Appleton Type XJ Crouse-Hinds Type XJ OZ/Gedney Type AX 3. Expansion Joint for Steel Conduit Encased in Concrete: Non-ferrous expansion joint consisting of a flexible tube with end fittings to receive the conduit and rubber tubing to cover the joint. 4. Seal Off Fittings for Sealing Conduit for Hazardous Areas: UL listed for use in Class I, Group A, B C, and D areas. a) b) c) 5. Appleton Crouse-Hinds OZ/Gedney Couplings and Connectors for EMT: Zinc-plated steel, compression type or set screw type. a) b) c) d) 26 05 33.23 – Raceways Appleton OZ/Gedney Thomas & Betts Midwest Issued 6/30/2004 Revised 10/17/11 Page 5 of 7 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.23 - RACEWAYS 6. Conduit Unions, on Continuous Run: a) 7. Fittings for Flexible Steel Conduit: Malleable iron or steel, zinc or cadmium plated, securing the conduit by clamping action around the periphery of the conduit. Do not furnish fittings that anchor the conduit by means of set screws a) b) 8. Appleton ST Series OZ/Gedney 4Q Thomas & Betts 5331 to 5360 9. Locknuts for Rigid Steel or Intermediate Metal Conduit: Malleable iron or steel, zinc or cadmium plated. 10. Bushings for 1 Inch and Smaller Rigid Steel Conduits or Intermediate Metal Conduit: Insulating plastic type of nonburnable thermosetting phenolic, conforming to Underwriters' Laboratories requirements. Do not furnish nonrigid plastic bushings. 11. Bushings for 1-1/4 Inch and Larger Rigid Steel Conduits or Intermediate Metal Conduit: Malleable iron or steel, zinc or cadmium plated, with insulating insert of thermosetting plastic as specified for smaller conduit bushings, molded and locked into the bushing ring. WIREWAYS 1. 2. 3. 4. D. Appleton OZ/Gedney Fittings for Liquid-Tight Flexible Steel Conduit: Designed to maintain the liquid-tight feature of the installation. Fittings shall be specifically approved for use with liquidtight flexible steel conduit. a) b) c) C. Erickson General Electric Hoffman Square D Wiremold CABLE TRAY 1. 2. 3. 4. 5. 6. B-Line Cablofil Chalfant Cope Globe MP Husky 26 05 33.23 – Raceways Issued 6/30/2004 Revised 10/17/11 Page 6 of 7 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 33.23 - RACEWAYS E. MISCELLANEOUS 1. Trapeze Hangers: Hot-dipped, galvanized cast malleable iron straps or structural steel with hot-dipped galvanized nuts and bolts. a) b) c) 2. Unistrut Kindorf Powerstrut Tap-on or indenter type fittings, die cast or sand cast fittings will not be acceptable. 26 05 33.23 – Raceways Issued 6/30/2004 Revised 10/17/11 Page 7 of 7 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 05 53 IDENTIFICATION PART 1: GENERAL 1.01 SYSTEM DESCRIPTION - DISTRIBUTION EQUIPMENT IDENTIFICATION All power panels, distribution panels, lighting panels, receptacle panels, motor control centers, transformers, disconnect switches, automatic transfer switches, isolated power centers and uninterruptible power supplies shall be labeled. A. Labeling nomenclature and the assignment of panel board numbering shall be coordinated with the BSC Electrical Shop before it is used on construction documents. B. Where panels are located in finished areas, identify them on the inside cover. C. For each component of equipment, unless otherwise specified, securely attach a plate with manufacturer's name and catalog number on it or stamp or cast into the body of the items the name and catalog number of the equipment. D. Apply labels to equipment after the general painting of the building interiors and other general painting is completed. E. Identification labels shall be: 1. 2. 3. F. Labels shall be: 1. 2. 3. 4. G. Black with White letters for normal power Red with white letters for emergency power. Orange with black letters for UPS. Line one of label shall be center justified 1/2" space between lines 1 and 2. Line two through five shall be left justified. 5/16" space between line 2, 3, 4 and 5. Line 1 shall describe the “Type of Panel or Equipment” followed by a dash; the “Type of Service”, followed by a dash; the “Panel Designation” followed by a dash; then the “Servicing Substation Source” or “UPS Number”. 1. Acceptable abbreviations for “Type of Panel or Equipment” are: a) b) c) d) 26 05 53 Identification PP – Power Panel DP – Distribution Panel LP – Lighting Panel RP – Receptacle Panel Issued 6/30/04 Revised 10/17/11 Page 1 of 8 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 05 53 IDENTIFICATION e) f) g) h) i) j) k) l) m) 2. 3. 26 05 53 Identification MCC – Motor Control Center T – Transformer DISC – Disconnect Switch CTK BKR – Circuit Breaker MTR. STR. – Motor Starter DISC. SW. – Disconnect Switch IPC – Isolated Power Center ATS – Automatic Transfer Switch Sub – Substation Acceptable abbreviations for “Type of Service” are: a) Normal System i. N – Normal System b) Essential System: i. L – Life Safety Branch ii. C – Critical Branch iii. E – Equipment Branch c) Uninterruptible Power System i. UPS – UPS System Line one examples: a) MCC-N-LL01-F i. Type of equipment is MCC (Motor Control Center) – Type of service is N (Normal System) – Panel Designation is LL01-Servicing substation source is Substation F. b) LP-L-304-AN i. This lighting panel feeds from the Life Safety Branch. c) RP-UPS-201-37 i. This 2nd floor receptacle panel is fed from UPS 37 d) PP-UPS-B02-98/99 i. This power panel feeds from a manual transfer switch on the output of UPS 98 and UPS 99. Issued 6/30/04 Revised 10/17/11 Page 2 of 8 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 05 53 H. IDENTIFICATION Line 2 shall indicate the voltage, phase designation and the number of conductors. Acceptable abbreviations are: Voltage Conductors Phase Designation 120V 208V 108/120V 240V 240/120V 277V 480V 480/277V 480V 1PH 3PH 3PH 3PH 1PH 1PH 3PH 3PH 3PH Number 2W 3W 4W 3W 3W 2W 3W 4W 3W 1. Line two example: 480V – 3PH - 3W I. Line three shall indicate the first disconnecting means and circuit feeding this panel or equipment. 1. J. Line three example: Fed from PP - N - LL04- F CKT #1 Line four shall indicate the location of the disconnecting means identified in line three. Line four shall indicate location by floor, building and room respectively. 1. Line four example: LL NTW Elect Rm 2. Acceptable abbreviations for floor are: a) b) c) d) e) f) g) h) i) j) k) l) 26 05 53 Identification Lower Level 1 - First Floor 2 - Second Floor 3 - Third Floor 4 - Fourth Floor 5- Fifth Floor 6-Sixth Floor 7-Seventh Floor 8-Eighth Floor Ninth Floor P – Penthouse Mezz - Mezzanine Issued 6/30/04 Revised 10/17/11 Page 3 of 8 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 05 53 3. IDENTIFICATION Acceptable abbreviations for building are: a) b) c) d) e) f) g) h) i) j) k) l) m) n) o) p) K. Line five shall indicate the substation and circuit feeding this equipment. 1. 1.02 Unit substations shall have an external, permanently attached, mimic bus diagram. The function of each substation cubicle shall be identified using one line diagram symbols. The cubicle symbols shall form a continuous one line diagram on the overall front elevation of the substation. SYSTEM DESCRIPTION - WIRING DEVICE IDENTIFICATION A. 1.04 Line five example: SUBSTATION F CKT 2 SYSTEM DESCRIPTION -UNIT SUBSTATION MIMIC BUS A. 1.03 NT - North Tower ET - East Tower NWT - North West Tower ST - South Tower SH - South Hospital CT - Central Tower NTE - North Tower East NTW - North Tower West ETN - East Tower North ETS - East Tower South CTN - Central Tower North CTE - Central Tower East CTW - Central Tower West CTS - Central Tower South CT OCT - Central Tower Octagon W - West Receptacle and light switch cover plates shall be identified with the circuit from which they are fed from using a Brady Handheld Labeling System. #TLS2200 with Label Part #PTL-45-430 and Font Size 7, and Brady #LAM-3-103 clear polyester applied over the top of the label. SYSTEM DESCRIPTION - POWER CONDUCTOR IDENTIFICATION A. Conductors shall be identified with the Brady Handheld Labeling System #TLS2200 with Label Part #PTL-19-499 and R4310 Ribbon, indicating the circuit number, wire number or phase letter at every terminal point or splice. Provide circuit identification of every unspliced conductor within each junction or pull box. For multi-conductor 6-pair cable, cable shall be identified with the Brady Handheld Labeling System #TLS2200 with Label Part #PTL-31-427 and R4310 Ribbon. B. The neutral conductor of a multiwire circuit shall be labeled to identify every circuit that it serves. Labeling shall be attached to the neutral wire in every junction or device box in which it appears. 26 05 53 Identification Issued 6/30/04 Revised 10/17/11 Page 4 of 8 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 05 53 1.05 IDENTIFICATION SYSTEM DESCRIPTION -JUNCTION BOX IDENTIFICATION A. B. C. D. E. F. G. H. Red = Emergency Power (Life Safety(deleted), Critical and Equipment) Black = Normal Power Yellow = Nurse Call Brown = Data/Communications (Telephone) Orange = Fire Alarm Blue = Communications (Paging, Music and Intercom) Pink = Security Purple = Life Safety Power Where spray paint is prohibited because of sensitive occupancy or fire hazard, a brush on painting method must be used. 1.06 SYSTEM DESCRIPTION - BRANCH CIRCUIT IDENTIFICATION A. Panelboards shall have typed circuit directories identifying each load and location. Up-date all existing panel schedules with new typed schedules for panels affected by work in this contract including additions or deletions to existing panels. B. Panel schedules shall be produced in digital format. Digital copies of all panel schedules shall be delivered to owner at the completion of the project. PART 2: PRODUCTS 2.01 DISTRIBUTION EQUIPMENT IDENTIFICATION LABELS A. For all power panels, distribution panels, lighting panels, receptacle panels, motor control centers, transformers, disconnect switches, automatic transfer switches, isolated power centers and uninterruptible power. B. Identification labels shall be made with “Brady Thermal Transfer Printable media. 1. Black with White letters for normal power circuit labeling: Brady THT-107-423 Stock label or Brady #Y80964 Item #0010 w/ R6007 Ribbon. 2. Red with white letters for emergency power: Brady THT-107-423 Stock label or Brady #Y80964 Item #0010 w/ R4407R Ribbon. 3. Orange with black letters for UPS circuit labeling: Brady THT-107439OR Stock label or Brady #Y80964 Item #1120 w/ R6007 Ribbon. 4. Brady #Y80964 labels are pre-cut to 4.00” x 6.50” from the factory for those printing without automatic cutter option. 26 05 53 Identification Issued 6/30/04 Revised 10/17/11 Page 5 of 8 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 05 53 2.02 SYSTEM DESCRIPTION -UNIT SUBSTATION MIMIC BUS B. 2.03 2.05 Unit substations external, permanently attached, mimic bus diagram shall be laminated plastic, or decals, as per the option available through the substation manufacturer. SYSTEM DESCRIPTION - WIRING DEVICE IDENTIFICATION A. 2.04 IDENTIFICATION Receptacle and light switch labels shall be made using a Brady Handheld Labeling System. #TLS2200 with Label Part #PTL-45-430 and Font Size 7, and Brady #LAM-3-103 clear polyester applied over the top of the label. SYSTEM DESCRIPTION - POWER CONDUCTOR IDENTIFICATION A. Conductors shall be identified with the Brady Handheld Labeling System #TLS2200 with Label Part #PTL-19-499 and R4310 Ribbon, indicating the circuit number, wire number or phase letter at every terminal point or splice. Provide circuit identification of every unspliced conductor within each junction or pull box. Multi-conductor 6-pair cable is identified with the Brady Handheld Labeling System #TLS2200 with Label Part #PTL-31-427 and R4310 Ribbon. B. The neutral conductor of a multiwire circuit shall be labeled to identify every circuit that it serves. Labeling shall be attached to the neutral wire in every junction or device box in which it appears. ARC FLASH WARNING LABEL A. All new electrical systems and major system modifications shall have a short circuit study performed and arc flash incident energy values calculated using EDSA 2005 Arc Heat software with the IEEE Standard 1584 calculations. B. The results of the EDSA software shall be entered into a MS Excel spreadsheet as detailed below. This spreadsheet is used by the Brady label maker as a source database and can be archived for future label reprinting or system revision. C. The layout of the label shall follow the standard BSC Arc Flash label as detailed on the following pages. 26 05 53 Identification Issued 6/30/04 Revised 10/17/11 Page 6 of 8 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 05 53 IDENTIFICATION Beaumont Services Company, LLC. Arc Flash Label Standard 26 05 53 Identification Issued 6/30/04 Revised 10/17/11 Page 7 of 8 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 05 53 IDENTIFICATION Beaumont Services Company, LLC. Arc Flash Label Standard 26 05 53 Identification Issued 6/30/04 Revised 10/17/11 Page 8 of 8 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 83 – WIRE CONNECTIONS AND CONNECTING DEVICES PART 1: GENERAL 1.01 SYSTEM DESCRIPTION - WIRING DEVICES A. All receptacles connected to emergency circuit shall be “red”. B. All receptacles connected to UPS circuits fed by emergency power shall be “red”. They shall also have an orange cover plate. C. Receptacles with surge protection shall be blue and have an indictor light and audible alarm to indicate malfunction. D. Install tamper resistant receptacles in pediatric and psychiatric care areas and other similar use areas. E. Convenience Receptacle Requirements. Convenience receptacles shall be specification grade, except hospital grade receptacles shall be used in the areas listed below: 1. All patient care areas including patient toilet rooms shall be hospital grade. 2. All emergency center patient care areas shall be hospital grade. 3. All surgical suites/operating areas shall be hospital grade. 4. All critical care areas shall be hospital grade. 5. All corridors shall be hospital grade,. 6. Other areas requiring hospital grade devices by code. F. Plug-in Strip shall utilize standard 20 ampere, 125 volt, 2 pole, 3 wire, duplex receptacles spaced 18 inches on centers, wired with single or multiple circuits, as indicated on Drawings, enclosed in a surface mounted steel raceway. Multiple circuit plug-in strips shall be wired with receptacles connected alternately. Plug-instrips shall accept standard size receptacles. Plug-in strips that utilize single receptacles in a pre-molded wiring harness shall not be used. G. Lighting connected to the Critical Branch of the Emergency System shall be locally switched. Lighting switches used to control lighting connected to the Critical Branch shall be illuminated, ivory, locator types with single, two pole or four pole as required for control scheme. The switch shall have an illuminated toggle; i.e. the toggle shall be illuminated (through the translucent ivory toggle) when the switch is in the “off” position. During a utility power outage the illuminated toggle will indicate to the staff that generator power is being supplied to the lighting in the room. 1. Life Safety Branch wiring shall not be controlled by local switching. Egress lighting, as required for NPFA 101, shall be panel switched and shall be 26 05 83 Wiring Connections & Connecting Devices Issued 6/30/04 Revised 10/17/11 Page 1 of 9 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 83 – WIRE CONNECTIONS AND CONNECTING DEVICES connected to the Life Safety Branch of the Emergency system It shall only be controlled at the panel, or with a “no-off-position” switching arrangement (three-way switch) as allowed by the NEC. H. Pilot light switches shall be used where illumination can not be seen from switch location; e.g. when a switch on the outside of an air handling unit controls lighting inside the air handling unit enclosure. I. In general, lighting switches shall be located in multiple and convenient locations so as to encourage energy conservation. J. Lighting switches in public corridors shall be key operated. K. After wiring connections have been made to wiring devices, the terminals shall be taped to insulate energized parts from contact with the grounded surfaces of the outlet box. Wiring devices with an approved terminal guard feature do not require taping. L. Dimmers. 1. Dimmers shall be sized so that load is a maximum of 80% of the rated load of the device. 2. Dimmer control shall be linear slide type with positive “on-off” switch. 3. Dimmers shall be equipped with “RFI” filters. 4. Dimmers shall meet the latest ANSI/IEEE Standard C62.41, tested to withstand voltage surges of up to 600 volts and current surges of up to 2000 amps without damage. M. Motion sensors shall have manual override features to allow lighting to be turned on if the sensor malfunctions. N. In addition to individual built-in toggle switches, counter light fixtures in large rooms with multiple under counter the fixtures shall be controlled by a master switch located at the door. The switch shall have an illuminated toggle pilot light to indicate that the power to the fixtures is available. O. Single phase motor loads shall not share a circuit with lighting or power receptacles. Connect all single and three phase motor loads to independent circuits. P. Receptacles shall be installed so that the grounding pin is on top for vertically installed devices, and the grounding pin is to the left (neutral slot on the top) for receptacle mounted horizontally. 26 05 83 Wiring Connections & Connecting Devices Issued 6/30/04 Revised 10/17/11 Page 2 of 9 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 83 – WIRE CONNECTIONS AND CONNECTING DEVICES Q. 1.02 Device Testing 1. The physical integrity of each receptacle shall be confirmed by visual inspection. 2. The continuity of the grounding circuit in each electrical receptacle shall be verified 3. Correct polarity of the hot and neutral connections in each electrical receptacle shall be confirmed with a testing device design for the purpose. 4. The retention force of the grounding blade of each electrical receptacle (except locking-type receptacles) shall be not less than 115 g (4 oz). SYSTEM DESCRIPTION - WIRING CONNECTIONS A. B. C. Connectors for copper conductors 1. In general, wiring shall be connected to wiring devices by the use of crimp connector. Crimp Connectors for Pigtail Splicing Conductors Up To and Including No. 10 AWG: Solderless type with a metallic insert crimp connector within a plastic insulating cover having a temperature rating of 105 deg C, 600 volts. 2. Connectors for Straight Splicing Conductors Up To and Including No. 10 AWG: Solderless compression type. 3. Twist-On Connectors for Pigtail Splicing Up to and Including No. 10 AWG: Metal wire spring pressure type connector with thermoplastic insulated cover with positive grip design having a temperature rating of 105 deg. C and a voltage rating of 600V. Lugs for terminating copper conductor 1. Lugs for Terminating Power Conductors Up To and Including No. 8 AWG: Solderless type, manufacturer's standard, unless otherwise specified. 2. Lugs for Terminating Power Conductors No. 6 AWG and Larger: Solderless compression type, one hole for No. 6 AWG through No. 4/0 AWG inclusive, and two hole for larger sizes. 3. Lugs for Terminating Control and Switchboard Wiring: Solderless compression type with tinned ring tongue. Terminal blocks 1. Terminal Blocks for Use in Control Wiring of Control Panels and Terminal Cabinets: Molded barrier type rated 30 amperes, 600 volts, with washer head binding screws and white marking strip. 26 05 83 Wiring Connections & Connecting Devices Issued 6/30/04 Revised 10/17/11 Page 3 of 9 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 83 – WIRE CONNECTIONS AND CONNECTING DEVICES 1.02 PRODUCTS A. Wiring Devices 1. Convenience Receptacles 20 Ampere Duplex Convenience Receptacles for 120 Volt, Single Phase Service: Straight blade, 2 pole, 3 wire, NEMA configuration 5-20R, rated 20 amperes, 125 volts, specification grade, for back and side wiring. 2. a) Specification Grade: i. Eagle 5362 Series ii. Hubbell 5362 Series iii. Leviton 5362 Series iv. Pass & Seymour 5362-A Series b) Hospital Grade: i. Hubbell 8300 Series ii. Leviton 8300 Series iii. Pass & Seymour 8300 Series c) Hospital Grade – Emergency: i. Same as Hospital Grade, but red in color. Special Receptacles a) Ground-Fault Interrupter: Duplex, 2 pole, 3 wire, grounding type, rated 20 ampere, 125 volt, NEMA configuration 5-20R. b) Specification Grade: i. Hubbell GF-5362 Series ii. Leviton 6899 Series iii. Pass & Seymour 2091Series c) Hospital Grade i. Hubbell GF8300 Series ii. Leviton 6899HG Series iii. Pass & Seymour 2091-HG Series d) Isolated Ground Receptacles: Duplex, 2 pole, 3 wire, isolated ground type, orange color or orange triangle on the face of receptacle, straight blade, rated 20 ampere, 125 volts, NEMA configuration 520R. 26 05 83 Wiring Connections & Connecting Devices Issued 6/30/04 Revised 10/17/11 Page 4 of 9 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 83 – WIRE CONNECTIONS AND CONNECTING DEVICES e) Specification Grade: i. Hubbell IG5362 Series ii. Leviton 5362IG Series iii. Pass & Seymour IG 6300 Series f) Hospital Grade: i. ii. iii. Hubbell IG8300 Series Leviton 5362IG Series Pass & Seymour IG 8300 Series g) Surge Suppression Receptacles: Duplex, 2 pole, 3 wire, surge suppression type, straight blade, rated 20 ampere, 125 volts, NEMA Configuration 5-20R. h) Specification Grade: i. Hubbell 5362-S (Blue Face), 5362-I (Ivory Face) ii. Leviton 5380-B (Blue Face), 5380-I (Ivory Face) iii. Pass & Seymour 5362BLSP (Blue Face), 5362ISP (Ivory iv. Face) i) Hospital Grade: i. Hubbell 8300HS (Blue Face), 8300HIS (Ivory Face) ii. Leviton 8380-B (Blue Face), 8380-I (Ivory Face) iii. Pass & Seymour 8300 BLSP (Blue Face), 8300 ISP (Ivory iv. Face) j) Hospital Grade – Emergency: i. Same as Hospital Grade, but red in color. k) Tamper Resistant Receptacles: Duplex, 2 pole, 3 wire, grounding type, rated 20 ampere, 125 volts, NEMA configuration 5-20R. Receptacle shall not operate if an object is inserted into only one blade opening. l) Hospital Grade: i. Hubbell HBLSG63H Series ii. Pass & Seymour SG63-H Series iii. Cooper TR830 Series m) Hospital Grade – Emergency: i. n) Same as Hospital Grade, but red in color. Twist –lock Devices 26 05 83 Wiring Connections & Connecting Devices Issued 6/30/04 Revised 10/17/11 Page 5 of 9 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 83 – WIRE CONNECTIONS AND CONNECTING DEVICES 3. o) Single Flush Twist-Lock Receptacle: Receptacles shall be twist-lock type, heavy duty construction, specification grade, grounding type, of the voltage and current characteristics required for the equipment indicated. Manufacturer shall match those of the convenience receptacles. p) Cord Type Twist-Lock Male Plug: Plug shall be twist-lock type with nylon body for use with strain relief grips, heavy duty construction, specification grade, grounding type, of the voltage and current characteristics required for the equipment indicated. Manufacturer shall match those of the convenience receptacles. q) Drop Cord Twist-Lock Female Connector: Female connector shall be twist-lock type with nylon body for use with strain relief grips, heavy duty construction, specification grade, grounding type, of the voltage and current characteristics required for the equipment indicated. Manufacturer shall match those of the convenience receptacles. r) Receptacles for Laser Equipment: 1) Straight blade, 2 pole, 3 wire, NEMA configuration L5-30R, rated 30 ampere, 125 volts, grounding type with stainless steel plate engraved “Laser”. Provide one matching plug. i. Hubbell 2610A, with stainless steel plate 7118 and matching plug 2611. ii. Leviton 2610, with stainless steel plate 84020-40 and matching plug 2611. 2.) Straight blade, 2 pole, 3 wire, NEMA configuration L6-30R, rated 30 ampere, 250 volts, grounding type with stainless steel plate engraved “Laser”. Provide one matching plug. i. Hubbell 2620A, with stainless steel plate 7118 and matching plug 2621. ii. Leviton 2620, with stainless steel plate 84020-40 and matching plug 2621 Light Switches: a) Switches for Controlling Lighting Directly on AC Systems in General: Toggle operated, ivory, nylon, heavy duty, flush, quiet type, with provision for back and side wiring, and rated 20 amperes, 120/277 VAC. 26 05 83 Wiring Connections & Connecting Devices Issued 6/30/04 Revised 10/17/11 Page 6 of 9 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 83 – WIRE CONNECTIONS AND CONNECTING DEVICES B. c) Specification Grade, Lock Type (Key Operated): i. Hubbell HBL1221LCN through HBL1223LCN Series with #HBL1209 keys. ii. Leviton 1221-2L through 1224-2L Series with #55500 keys. iii. Pass & Seymour 20AC1L through 20AC4L with #500K keys. d) Specification Grade, Lighted Toggle – Emergency: Ivory, nylon, toggle, light on with load off: i. Hubbell HBL1221ILCN(Single Pole). ii. Hubbell HBL1223ILCN(Three-Way). e) Specification Grade, Double Pole, Standard Toggle for control of view boxes connected to Hospital Isolation Panels: i. Hubbell HBL1222I ii. Leviton 1222-2 iii. Pass & Seymour CSB220 Manual Dimmers for Outlet Box Mounting Leviton "82000" Series (Incandescent) and “86000” Series (Fluorescent). Lithonia "DSD" Series. Lutron "Diva" Series. Prescolite "Element" Series. Pass & Seymour 91000 Series (Incandescent) and 93000 Series (Fluorescent). Plug-In Strips: 1. D. Specification Grade, Standard Toggle: i. Hubbell HBL1221ICN through HBL1224ICN Series ii. Leviton 1221-2 through 1224-2 Series iii. Pass & Seymour CSB120 through CSB420. Dimmers 1. 2. 3. 4. 5. 6. C. b) Wiremold G3000 Series with standard 20-ampere, 125-volt receptacles as specified above. Connectors for copper conductors 1. Connectors for Straight Splicing Conductors Up To and Including No. 10 AWG: Solderless compression type. a) b) Thomas & Betts "Sta-Kon" Burndy "Hydent" 26 05 83 Wiring Connections & Connecting Devices Issued 6/30/04 Revised 10/17/11 Page 7 of 9 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 83 – WIRE CONNECTIONS AND CONNECTING DEVICES 2. Twist-On Connectors for Pigtail Splicing Up to and Including No. 10 AWG: Metal wire spring pressure type connector with thermoplastic insulated cover with positive grip design having a temperature rating of 105 deg. C and a voltage rating of 600V. a) b) 3. Crimp Connectors for Pigtail Splicing Conductors Up To and Including No. 10 AWG: Solderless type with a metallic insert crimp connector within a plastic insulating cover having a temperature rating of 105 deg C, 600 volts. a) b) 4. Thomas & Betts 54500 Series Burndy type YS-L ILSCO CT or CTL Connectors for 3-Way Splicing Conductors No. 8 AWG and Larger: Solderless compression type. a) b) E. Buchanan #2011S (crimp connector) and #2014 (splice cap insulator) Ideal #411 (crimp connector) and #417 (wrap cap insulator) Connectors for Straight Splicing Conductors No. 8 AWG and Larger: Solderless compression 2-way type. a) b) c) 5. 3M "Scotchlok" Ideal "Wire-Nut" Thomas & Betts 54700 Series Burndy YS-T Lugs 1. Lugs for Terminating Power Conductors No. 6 AWG and Larger: Solderless compression type, one hole for No. 6 AWG through No. 4/0 AWG inclusive, and two hole for larger sizes. a) b) c) 2. Burndy Type YA-L Thomas & Betts Series ILSCO 54000 CR Lugs for Terminating Control and Switchboard Wiring: Solderless compression type with tinned ring tongue. a) b) Burndy "Hydent" Thomas & Betts "Sta-Kon" 26 05 83 Wiring Connections & Connecting Devices Issued 6/30/04 Revised 10/17/11 Page 8 of 9 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 05 83 – WIRE CONNECTIONS AND CONNECTING DEVICES F. Terminal blocks 1. Terminal Blocks for Use in Control Wiring of Control Panels and Terminal Cabinets: Molded barrier type rated 30 amperes, 600 volts, with washer head binding screws and white marking strip. a) b) c) d) G. Electrical splicing kits: a) H. Scotch 82 Aluminum Joint Compound: a) b) I. Cutler-Hammer, Inc., Bulletin 10987 General Electric EB-5 Marathon 2000 Series Square-D Burndy "Penetrox A" Thomas & Betts No. 21059 Insulating tape 1. General Use Tape: a) b) Scotch 33 Plus Okonite Type CLF Series 602-20 2. High Temperature Area Tape: a) Scotch 27 3. Outdoor Use Tape: a) Scotch 88 26 05 83 Wiring Connections & Connecting Devices Issued 6/30/04 Revised 10/17/11 Page 9 of 9 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 09 00 1.01 ELECTRICAL MONITORING & CONTROL SYSTEM WBH ROYAL OAK EMERGENCY POWER SUPPLY SYSTEM A. B. The Beaumont emergency power supply systems (EPSS) contain generators, automatic transfer switches (ATS), and uninterruptible power supplies (UPS) monitored by a Square D PowerLogic® SCADA server in the facilities electrical shop. 1. Any addition of a generator, ATS, or UPS to the EPSS shall include adding the new devices into the EPSS monitoring system and the server configuration. 2. Any removal of an existing generator, ATS, or UPS from the EPSS shall include removing the devices from the EPSS monitoring system and the server configuration. 3. Any reclassification or renaming of an existing generator, ATS, or UPS in the EPSS shall include changing the name of the device in the EPSS monitoring system server configuration. When adding a new ATS or UPS into the EPSS, the following procedure shall be followed. 1. The contractor shall purchase a programmable logic controller (PLC) ATS Interface enclosure from Square D PowerLogic®. This shall be the same product as was supplied to BSC for the existing EPSS. a) This enclosure shall be installed as close to the ATS as is practical. 2. The contractor shall purchase sufficient engineering labor from Square D PowerLogic® for on-site programming and configuration to add the new devices into the system. 3. The contractor shall connect the ATSs to the interface PLC enclosure using the same wiring methods, including interface relays and terminal strip wiring, as in the original EPSS monitoring project. a) This includes the Belden 8723, 4 conductor, 22awg, shielded twisted pair cable (or equivalent) for Modbus RS485 communications between the ATSs and the PLC. 26 09 00 Electrical Monitoring & Control System Issued 7/12/2007 Revised 10/17/11 Page 1 of 3 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 09 00 ELECTRICAL MONITORING & CONTROL SYSTEM b) 4. 5. This includes the Belden 27616, 8 conductor, 16awg, 600V, non- shielded cable (or equivalent) for 24V dc and I/O. The ATS Interface enclosure or UPS added to the EPSS will require a connection to the LAN from the closest communication closet. a) The LAN connection box will be mounted inside the ATS Interface enclosure, as was done in the original project. The LAN connection for the UPS will be mounted on the wall next to the unit. b) There shall be static IP addresses provided by WBH Communications before Square D PowerLogic® can begin to develop the programming to add the devices into the EPSS monitoring system. The UPS shall be supplied with an Ethernet communications card including an RJ-45 port. This card shall be connected to the LAN connection box described in 1.01, B4, a) above using a patch cord. a) This card shall be capable of being monitored by a web browser using the manufacturer’s on-board web page and by the EPSS monitoring system using SNMP or Modbus RTU. i. ii. iii. iv. 6. Liebert MGE Pulsar EX MGE Galaxy, Comet EX Eaton Powerware IntelliSlot Web Card Minislot 66244 Traverse 66074 Connect UPS-X The contractor shall connect hospital UPS 120V power to the ATS Interface enclosure and the communications closet. a) This may involve installing the smallest practicable 120/208V UPS receptacle panel near the ATSs, if this is not already available. b) One circuit from the receptacle panel shall supply the ATS Interface panel, and the second shall supply the communication closet which connects the EPSS devices to the LAN. 26 09 00 Electrical Monitoring & Control System Issued 7/12/2007 Revised 10/17/11 Page 2 of 3 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 09 00 2.01 ELECTRICAL MONITORING & CONTROL SYSTEM 7. There shall be additional labor cost in the project for BSC TIG department to modify the AutoCAD® one-line electrical drawing into a format that is compatible with the EPSS monitoring system graphics. There will be labor charges for BSC Engineering to add the new system into the remainder of the EPSS documentation. 8. Below is a typical representation of the EPSS inside the hospital. WBH TROY EMERGENCY POWER SUPPLY SYSTEM A. The WBH Troy emergency power supply system (EPSS) contains automatic transfer switches monitored by an Asco Thin-Web sever in the facilities electrical shop. B. The automatic transfer switches shall be equipped with an ASCO device “85L” ASCO power management and an ASCO device “72E” Ethernet connectivity module to allow communication and control through the Thin Web server. 26 09 00 Electrical Monitoring & Control System Issued 7/12/2007 Revised 10/17/11 Page 3 of 3 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 11 00 PART 1 1.01 480 Volt Substations GENERAL REQUIREMENTS SYSTEM DESCRIPTION A. The 480 volt double ended substation shall have the following features. 1. A graphic marking system on the switchgear that mimics the bus bars and identifies the feeder breaker connections as in a one-line diagram. a) b) 2. Both Main breakers and the Tie breakers will be provided with a lockable switch allowing for the operator to impose a temporary instantaneous trip setting for the purposes of arc flash protection of personnel working on the feeder breaker sections. a) 3. An example of this would be the Arcflash Reduction Maintenance System™ from Eaton Corp. The circuit breaker trip units for both of the main breakers, the tie breaker, and all feeder breakers shall be of the same type. These trip units shall be capable of monitoring current and voltage for the purposes of calculating watts and watt-hour values for the energy billing software in the BSC PowerNet normal power monitoring system. a) 4. This graphic mimic bus shall be installed on the front and rear of the switchgear. The feeder breakers and future positions will be labeled with engraved laminated plastic nameplates on the front and rear of the switchgear. An example of this would be Digitrip 1150+™ by Eaton Electrical. The PLC controlling the automatic transfer and manual operations shall be controlled with a color touch screen operator interface device. a) b) 26 11 00 480 Volt Substations This operator interface device shall display a one-line diagram of the substation when in automatic transfer mode. The one-line diagram shall change colors based on the status of the breakers in the system. This operator interface device shall allow the adjustment of time delay values used in the automatic operations. Issued 6/30/04 Revised 10/17/11 Page 1 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 11 00 480 Volt Substations c) d) This operator interface device shall display alarm messages in case of loss of phase voltage or other cause of automatic operation that shall remain displayed until acknowledged by an operator. This operator interface device shall allow manual control in open and closed transition mode. i. ii. iii iv e) f) 5. An example of this device would be PanelMate Power Pro 1700™ by Eaton Electrical. The PC-based operator interface programming software and all necessary communication cables shall be provided by the manufacturer to allow BSC to create archive copies of the application software in the unit. The programming software and all necessary communication cables for the PLC controlling the automatic transfer and manual operations shall be provided by the manufacturer. a) b) 6. The closed transition feature enables BSC to transfer the switchgear to a single-ended state and retransfer to normal condition without impacting the environment of care for hospital patients. The closed transition mode shall be allowed only when the pistol grip control switch is placed in bypass mode. The closed transition shall be initiated only by the operator interface device and shall select which breaker will be open after a momentary period where both mains and the tie are closed. This closed transition period shall be documented by the switchgear manufacturer to last a maximum of 80 milliseconds in duration. An example of the PC software would be WinGPC™ software for the D50™ plc by Eaton Electrical. For the example of a D50™ plc, there would be a RS232 cable and RS232-to-RS485 converter module required. The plc ladder logic application provided with the switchgear shall be provided in a hard-copy printout in the O & M manual. a) 26 11 00 480 Volt Substations This printout will be annotated with instruction and rung comments that allow a person to become familiar with the sequence of operation of the switchgear. Issued 6/30/04 Revised 10/17/11 Page 2 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 11 00 7. 480 Volt Substations The switchgear shall be provided with provisions for BSC supplied 120vac emergency power, in addition to an internal UPS for PLC CPU power, in the case of loss of power to both transformers in the substation. a) b) 8. The main bus metering device, for example the DP4000™ by Eaton Electrical, shall be provided with a separate source power supply module supplied by the internal UPS in the switchgear. This will allow the meter in the switchgear to ride through a power loss until the external emergency control power arrives. a) 9. Without control power the Tie breaker would not close in the case of loss of power to both transformers within 3 seconds. The main bus metering and circuit breaker trip unit communication to the Eaton Electrical PowerNet normal power monitoring system would also be lost. The manufacturer shall provide the means for all 120V control power of the switchgear to transfer from internal control transformer power to external emergency control power by providing all internal switching and a terminal strip for BSC to terminate incoming 120vac wiring. An example for a 24vdc UPS is the IQDP4120 by Eaton Electrical. The switchgear shall contain infrared sight glasses mounted on the front and rear panels of the switchgear to allow for regular infrared thermography of the electrical connections and bus bars. a) b) c) 26 11 00 480 Volt Substations The sight glasses shall be compatible with infrared thermography cameras by Flir Systems and Fluke model Ti25. An example of this would be the HWK-075-C-L by Hawk IR and IRISS. The sight glass manufacturer should be requested to provide the recommended installation locations for optimum viewing of the equipment. Issued 6/30/04 Revised 10/17/11 Page 3 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 11 00 1.02 480 Volt Substations SEQUENCE OF OPERATIONS A. The switchgear shall have the following automatic sequence of operations. 1. Loss of source voltage to main breaker Left. a) b) c) d) 2. Return of normal voltage to main breaker Left, following sequence 1 above. a) b) c) d) 3. Abnormal voltage detected at main breaker Right. Time delay 3 seconds (Adjustable). Main breaker Right opens. Tie breaker closes. Return of normal voltage to main breaker Right, following sequence 3 above. a) b) c) d) 5. Normal voltage returns to main breaker Left. Time delay 20 minutes (Adjustable). Main breaker Left closes. Tie breaker opens. Loss of source voltage to main breaker Right. a) b) c) d) 4. Abnormal voltage detected at main breaker Left. Time delay 3 seconds (Adjustable). Main breaker Left opens. Tie breaker closes. Normal voltage returns to main breaker Right. Time delay 20 minutes (Adjustable). Main breaker Right closes. Tie breaker opens. Loss of voltage to main breaker Left and main breaker Right. If loss of voltage occurs to both main breakers within the time delay of 3 seconds (Adjustable), the Tie breaker will not close without external control power. a) b) c) d) e) f) g) 26 11 00 480 Volt Substations Loss of voltage to main breaker Left. Time delay 3 seconds (Adjustable). Main breaker Left opens. Tie breaker closes. Loss of voltage to main breaker Right Time delay 3 seconds (Adjustable). Main breaker Right opens. Issued 6/30/04 Revised 10/17/11 Page 4 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION GUIDELINES AND STANDARDS SECTION 26 11 00 6. 480 Volt Substations Return of normal voltage to main breaker Right, following sequence 5 above. a) b) c) d) 7. Return of normal voltage to main breaker Left, following sequence 5 above. a) b) c) d) 8. Normal voltage returns to main breaker Right. Main breaker Right closes. Tie breaker closes, if it did not close in sequence 5 above. Upon return of normal voltage to main breaker Left, sequence 2 will be followed. Normal voltage returns to main breaker Left. Main breaker Left closes. Tie breaker closes, if it did not close in sequence 5 above. Upon return of normal voltage to main breaker Right, sequence 4 will be followed. Return of normal voltage to main breaker Left and main breaker Right, following sequence 5 above. a) b) c) d) e) f) 26 11 00 480 Volt Substations Normal voltage returns to main breakers Left and Right. Main breaker Left closes. Tie breaker closes, if it did not close in sequence 5 above. Time delay 20 minutes (Adjustable). Main breaker Right closes. Tie breaker opens Issued 6/30/04 Revised 10/17/11 Page 5 of 5 Jones Lang LaSalle @ Beaumont Health System, LLC. DESGIN/CONSTRUCION STANDARDS AND GUILDLINES SECTION 26 18 36 FUSES PART 1: GENERAL 1.01 SYSTEM DESCRIPTION A. Provide a spare set of fuses for each project. The quantity of fuses shall be determined by taking 10% of the totals of each type used to complete construction, but in no case shall it be less than one of each type used. B. For unit substations with 4800-volt primary fuses provide one set of spare fuses to match those selected for coordination. Provide a painted steel fuse storage cabinet in the substation room large enough to store the spare set of fuses. C. Fuses: shall be non-renewable high interrupting capacity D. Fuses for power feeders and/or branch circuits rated 600 ampere or lower: UL class RK1 current-limiting type with 200,000 ampere interrupting rating. E. Fuses for power feeders rated 601 ampere or greater: UL class L currentlimiting type with 200,000 ampere interrupting rating F. Lighting feeders and/or lighting panels: UL class RK1 current-limiting type with 200,000 ampere interrupting rating. G. Motors: UL class RK1, dual element, time-delay, current limiting with 200,000 interrupting rating. H. Lighting fixture ballasts: in-line fused in ballast compartment as recommended by ballast manufacturer. 1.02 PRODUCTS Fuses A. Fuses for power feeders and/or branch circuits rated 600 ampere or lower: UL class RK1 current-limiting type with 200,000 ampere interrupting rating. 1. 2. B. Fuses for power feeders rated 601 ampere or greater: UL class L currentlimiting type with 200,000 ampere interrupting rating. 1. 2. 26 18 36 Fuses Bussmann Low-Peak LPN-RK and LPS-RK Ferraz Shawmut A2D-R and A6D-R Bussmann Low-Peak Hi-Cap KRP-C Ferraz Shawmut A4BQ Issued 6/30/04 Revised 10/17/11 Page 1 of 2 Jones Lang LaSalle @ Beaumont Health System, LLC. DESGIN/CONSTRUCION STANDARDS AND GUILDLINES SECTION 26 18 36 C. D. Lighting feeders and/or lighting panels: UL class RK1 current-limiting type with 200,000 ampere interrupting rating. 1. Bussmann Limitron LPN-RK and A6D-R 2. Ferraz Shawmut A2D-R AND A6D-R Motors: UL class RK1, dual element, time-delay, current limiting with 200,000 interrupting rating. 1. 2. 26 18 36 Fuses FUSES Bussmann Low-Peak LPN-R and LPS-R Ferraz Shawmut A2D-R and A6D-R Issued 6/30/04 Revised 10/17/11 Page 2 of 2 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 33 53 – UNINTERRUPTIBLE POWER SUPPLY PART 1: GENERAL 1.01 SYSTEM DESCRIPTION. A. This section specifies single and three-phase, on-line, static-type, Uninterruptible Power Supplies (UPS). Installations shall be complete and include: transient voltage surge suppression (TVSS), input harmonics reduction filter, rectifiercharger, battery, battery disconnect device, inverter, static bypass transfer switch, external manually operated maintenance bypass switch, internal automatically operated bypass/isolation switch, local UPS alarm/monitoring panel, provisions for connection to the hospital’s “Emergency Power Monitoring System”, safety features as called for below, and (when wet cell batteries are used) a battery monitoring/testing system. B. Static, double inversion, UPS is the “Standard”, but new technologies; i.e., flywheel, compressed air and fuel cells, will be considered as they are developed and tested. Final decision on the best choice for the application shall be made after an evaluation of the options. C. Distribution systems for UPS’s 10KVA and larger shall be designed with provisions for connecting an external load bank for full capacity testing. D. UPS’s 10KVA and larger shall be load bank tested on site after installation. Document the test in a continuous time line, digitally recorded, format. A successful commissioning test shall show a continuously usable power output at rated load as the normal input supply is switch on and off. The test shall include operating the UPS using generator power as well as utility power. E. All UPS’s supporting critical systems shall be supplied by an emergency generator power source. F. All UPS’s shall have the ability to directly communicate with the “Emergency Power Monitoring System”. G. The harmonic filtering provided by some UPS manufactures, to limit input harmonics as required in this standard, may introduce leading (capacitive) power factor into the system and cause problem with generator voltage regulation. This condition shall be investigated by the consulting engineer, and mitigated if needed. H. UPS’s shall have the ability to compensate for input frequency deviations of +/1.5Hz because they will be connected to the essential electrical system (generator power) that may have small frequency variations. The UPS shall be investigated for compatibility with the generator source. I. When the UPS utilizes wet cell batteries a dedicated battery room shall be provided. The battery room shall have all required safety features including: eye 26 33 53 Uninterruptible Power Supply Issued 6/30/04 Revised 10/17/11 Page 1 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 33 53 – UNINTERRUPTIBLE POWER SUPPLY wash, spill containment, seismic bracing, and ventilation. Battery terminals and interconnecting bus shall be protected with insulating covers. J. Cooling for the UPS, and ventilation for the battery room, shall be on emergency power. K. UPS’s 30KVA and larger shall utilize wet cell batteries. UPS’s less than 30KVA shall utilize sealed “maintenance-free”, VRLA, batteries. Flywheel energy storage systems shall be considered in lieu of storage batteries. L. UPS shall supply output power that has 5%, or less, total harmonic, current, distortion. The UPS shall not reflect more than 10% total harmonic current distortion into the input, supply side, source M. UPS components shall be protected from surges that enter at each AC power input connection including main disconnect, static bypass transfer switch, and maintenance bypass/isolation switch. Protection shall be provided for the rectifiercharger, inverter, controls, and output components. N. Output voltage regulation shall be +/- 1% steady state, and +/- 8% at 50% load step. O. Uninterruptible power supplies shall have a fail-safe, synchronized, bypass feature that automatically switches the load to the supply source, without power interruption to the load, if there is an internal UPS failure. P. Uninterruptible power supplies that are hard wired into the distribution system supply shall have an external maintenance bypass configuration, which will allow the UPS to be taken off line, and be completely removed from the distribution system, without interruption to the load. An internal maintenance bypass, that is integral to the UPS, will not fulfill this requirement because the UPS cannot be physically removed without interrupting power to the load. Q. Provide a remote annunciation alarm panel for UPS when it is not located in close proximity to the loads it supplies. The users of the equipment being supplied by the UPS shall receive notification when the UPS is operating on battery, or in bypass. The annunciator shall be audible and visual. The audible alarm shall have a silencing feature that will shut off the audible alarm, but keep the visual signal active until the UPS is returned to its normal operating condition. R. A placard shall be posted at the remote annunciator with instructions listing phone numbers and procedures to follow in the event of an alarm. S. Wet cell batteries. 1. Battery racks shall be steel members powder-coated with ANSI #61 gray, acid-resistant, epoxy paint. Racks shall be suitable for a Seismic Zone 1 26 33 53 Uninterruptible Power Supply Issued 6/30/04 Revised 10/17/11 Page 2 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 33 53 – UNINTERRUPTIBLE POWER SUPPLY location. Racks shall be braced to prevent movement in the horizontal plane. T. 2. Provide and install disconnect switch and fuses in battery interconnect cabling. 3. Each battery rack must stand alone with a minimum clearance of 4 inches from any other object (walls, other racks, etc.). 4. Each frame within a rack must be anchored to the floor. Anchoring shall meet all local, state, and/or federal codes. 5. All battery interconnecting bus and terminals shall be provided with plastic insulating covers to shield connecting components and protect personnel from inadvertent contact of energized parts. Design considerations. 1. UPS’s generate heat, noise and magnetic flux in varying degrees. Consider these factors in determining the location of the UPS, and batteries. 2. Elevated temperatures reduce battery life. Room design shall maintain a room temperature that will not decrease the battery warranty (72-76°F). Install over temperature alarm in battery and UPS rooms. Provide adequate ventilation to prevent hydrogen accumulation. Provide alarm if ventilation, air flow, is disrupted. 3. Wet cell shall be provided with spark arrestors. 4. Do not locate sprinklers, or HVAC ducts, directly over UPS. Do not install piping or ductwork in UPS and battery rooms, unless they serve these rooms. 5. On large UPS systems, consider the benefits of using a separate by-pass source. If only one common source is used for both the normal input and the by-pass the by-pass will not be available if the normal fails due to a cable fault, loose terminal connections, malfunction circuit breaker tripping, etc. 6. As previous specified, the input current drawn by the UPS shall contain no more than 10% total harmonic distortion. Some manufactures may need to add optional input filters to comply with this requirement. These filters often contain capacitors that can cause over voltage problems in the emergency generator supply. Design the system so that the UPS’s are not the first load(s) to be connected to the generator. Balance the positive power factor load of the UPS capacitors with negative reactive loads; timing the reactive loads to be connected first. 26 33 53 Uninterruptible Power Supply Issued 6/30/04 Revised 10/17/11 Page 3 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 33 53 – UNINTERRUPTIBLE POWER SUPPLY 7. UPS’s are given a unique identification number and label by the Beaumont Services Company, Facilities Management Department. Consulted with the Electrical Shop and get a unique UPS designation. Use this designation in the construction documents and for the labeling the equipment. 8. Consider the environmental and safety issues associated with UPS batteries when locating and designing the system; i.e., eye wash equipment; insulation of electrical components, spill containment, hydrogen ventilation..etc. 9. Install 4-inch concrete,” housekeeping”, pad under UPS, and a spill containment curb around wet cell batteries. Provide absorbent, spill containment, pillows under battery rack(s). 10. Provide remote manual emergency stop controls, or automatic stop, when required by code. 1.02 PRODUCTS A. Approved UPS Manufacturers are: Pillar, MGE(deleted), Powerware, and Liebert. Any other manufacturer must be approved (in writing) by BSC before the specifications and drawings are issued for construction. B. Approved battery monitoring/testing systems are: BTECH Inc. and ALBER. 26 33 53 Uninterruptible Power Supply Issued 6/30/04 Revised 10/17/11 Page 4 of 4 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS PART 1: GENERAL 1.01 SYSTEM DESCRIPTION A. The lighting system shall be designed and installed in compliance with the Michigan Energy Code. B. Illumination Levels. Generally, the following maintained lighting levels will be provided: Area Footcandles Admitting Ambulance (local) Anesthetizing Autopsy and morgue Autopsy, general Autopsy table Morgue, general Museum Cardiac function lab Central Sterile Supply Inspection, general Inspection At sinks Work areas, general Processed storage Charting Conference Rooms Corridors Nursing areas-day Nursing areas-night Operating areas Delivery Recovery Labs Suites Service Critical Care areas General Examination (local) fixed Surgical task lighting Handwashing Cystoscopy room 26 50 00 Lighting Systems Issued 6/20/04 Notes 55-65 75-100 75-100 75-100 300-500 30-50 75-100 150-175 75-100 150-200 75-100 30-50 30-50 50-55 50-55 Surgical Suite 2 20-25 10-15 75-100 75-100 75-100 75-100 75-100 75-100 30-50 150 750-1000 150-200 75-100 Revised 10/17/11 2 Page 1 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS Area Footcandles Day Room/Dining Room Dialysis unit, medical General Reprocessing Dialysate Room Dietary General Dish Washing Tray Assembly Food Storage Electrical Rooms Elevators EKG and specimen room General On equipment Emergency Outpatient General Exam/Treatment (fixed) Endoscopy rooms General Peritoneoscopy Culdoscopy Examination & treatment rooms General Exam/treatment Eye surgery Fracture room General Local Handwash locations Inhalation therapy Janitors closet Laboratories General Specimen collection Tissue laboratories Microscopic reading room Gross specimen review Chemistry rooms Bacteriology rooms General 26 50 00 Lighting Systems Issued 6/20/04 Notes 30-50 30-50 75-100 30-50 30-50 50-75 50-75 20-30 15-25 15-20 7.5-10 15-20 75-100 150-175 75-100 30-50 30-50 50-55 150 150-200 Maybe Portable 2 75-100 150-200 30-50 30-50 20-30 50-55 75-100 150-200 30-50 150-200 75-100 75-100 Revised 10/17/11 Page 2 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS Area Footcandles Reading culture plates Hematology Laundry Preparation and tubs Washer & Dryer Linens Sorting soiled linen Central (clean) linen room Sewing room, general Sewing room, work area Linen closet Lobby Locker rooms Maintenance department Mechanical Rooms Medical illustration studio Medical rooms Nurseries General Exam/treatment Nurses Stations General Desk Corridors, day Corridors, night Medication station Nourishment room Obstetric delivery suite Labor rooms General Local Birthing room Delivery area Scrub, general General Delivery table Resuscitation Post-delivery recovery area Substerilization room Occupational therapy Work area, general 26 50 00 Lighting Systems Issued 6/20/04 Notes 150-200 75-100 30-50 30-50 30-50 30-50 30-50 75-100 7.5-10 15-20 20-25 30-40 15-25 150-200 75-100 15-20 150 2 May be portable 30-50 50-60 15-20 3-5 75-100 30-50 15-20 75-100 150-200 3 75-100 150-20 4 300-500 75-100 30-50 30-50 Revised 10/17/11 Page 3 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS Area Footcandles Work tables or benches Office Areas Patient Holding Areas Patient/Resident rooms General (entire room) Observation – night light Critical examination Notes 75-100 55-65 75-100 20-30 3-5 75-100 Reading Location 2 Maybe Portable 30-50 (Reading lamp or over bed fixture) Toilets LDR/LDRP task lighting as required Pharmacy General (entire room) Alcohol vault Laminar flow bench Night light Parental solution room Physical therapy departments Gymnasiums Tank rooms Treatment cubicles Post-anesthetic recovery room General Local Pulmonary function laboratories Radiology (Imaging suite) Diagnostic section General Waiting area Radiography/fluoroscopy room Film sorting Barium kitchen Radiation therapy section General Waiting area Isotope kitchen General Benches Computerized radiotomography section Scanning room Equipment maintenance room 26 50 00 Lighting Systems Issued 6/20/04 30-50 75-100 30-50 150-200 3-5 30-50 30-50 30-50 30-50 75-100 750-1000 75-100 2 20-25 20-25 3-5 150-200 75-100 2 20-25 7.5-10 75-100 75-100 7.5-10 75-100 Revised 10/17/11 Page 4 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS Area Footcandles Registration Retail – General Solarium General Local for reading Stairways Storage rooms Surgical suite Operating room general Operating table Scrub room Instruments and sterile supply room Clean up room, instruments Anesthesia storage Substerlizing room Surgical induction room Surgical holding area Tel/Com rooms Toilets/Bathing General (includes water closets, Notes 55-65 55-65 15-20 30-50 20-25 20-25 2 150-200 2 4 150-200 30-50 75-100 30-50 30-50 75-100 75-100 50 2 2 30-50 shower/tub) Night lighting Utility room (clean and soiled) General Work counter Waiting areas General Local for reading Note 1: Note 2: Note 3: Note 4: C. 3-5 30-50 50-75 15-20 30-50 Multi-level lighting, incandescent dimmed. Multi-level lighting and/or dimming as required. Supplemental illumination as in delivery room (2500 fc minimum) must be available. Operating Table requires additional 2500 fc (minimum). Lighting Fixtures 1. In an effort to limit the number replacement lamps that need to be kept in stock, new fixtures must use lamps that are already being used on the campus. See the appendix for approved “Lighting Fixture Schedule” and list of lamps. 26 50 00 Lighting Systems Issued 6/20/04 Revised 10/17/11 Page 5 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS D. E. 2. All “lay-in” grid fixtures shall have earthquake clips installed and shall be supported independently of the ceiling grid system using a minimum of two (2) safety wires on diagonally opposite corners of the fixture. 3. All fluorescent fixtures surface mounted to the suspended grid ceiling shall be supported independently of the grid. “Caddy” clips shall not be used. Lighting Fixture Lenses 1. Prismatic lenses shall be extruded of 100% virgin acrylic and shall be a minimum thickness of 0.156. Lenses larger than 2 foot by 4 foot shall be a minimum thickness of 0.187. 2. Plastic Lens will conform to State of Michigan Bureau of Fire Services Rules #248, 249 and 250. 3. All lighting fixtures shall have lenses to protect the lamps in patient care areas, including corridors where patients are likely to be transported. 4. Overlays lens in parabolic fixtures shall be 100% virgin acrylic. 5. Overlays lens in open down lights shall be clear tempered glass. Lamps 1. Incandescent: Extended service, rated at 130 volts and 2500 hours rated life, inside frosted. 2. Incandescent Halogen PAR: Tungsten Halogen Capsule PAR lamps, rated at 130 volts and 2000 hours minimum rated life. 3. Fluorescent T-5: Programmed start, nominal 48 inch long, 28 watt, miniature bipin lamp, 2900 lumen 4100K, 82 CRI (minimum) 4. Fluorescent T-8: Instant/Rapid start, 48 inch long, 32 watt, medium bi-pin lamp, 2850 lumens, 4100K, 75 CRI (minimum). 5. Fluorescent Compact: Type and wattage as indicated, preheat, 4100K, 82 CRI (minimum). 6. Metal Halide is the preferred HID source. 7. High pressure sodium lamps used not used on the site. 26 50 00 Lighting Systems Issued 6/20/04 Revised 10/17/11 Page 6 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS F. Ballasts 1. G. H. I. In general, provide two-lamp ballasts No more than two lamps will be served by one ballast. Do not use three, or four, lamp ballasts, particularly when the loss of one ballast can cause a black-out of an entire room. Exit lights 1. Exit lights shall be powered from the “Life Safety Branch” of the “Essential Electrical Distribution System. 2. Exit lights shall be LED type. 3. In special circumstances where the exit fixture will be subject to physical damage from materials management carts use selfilluminating exit on hinged mounting. This type of exit must be located adjacent to an unswitched, general illumination, fixture on emergency power. Emergency Battery Units 1. Where the Codes require battery powered lighting in addition to generator power lighting, evaluate the cost effectiveness of a central battery/inverter system in lieu of multiple, individual, battery units. 2. Battery units shall be used in areas where critical patient procedures are done, and where total blackout due to power failure is possible. Battery units shall be used in addition to general lighting connected to the Essential Electrical System. 3. Battery units shall be powered from the critical branch and be connected, ahead of all switching, to the branch circuit feeding the lighting in the room. Central battery/inverter systems 1. Where multiple battery unit would be required evaluate the life cycle cost of using a central battery system in lieu of individual battery units. 2. Systems shall comply with the requirements of NFPA 101. 3. Provide an external by-pass to allow the unit to be removed without disrupting the power to the fixtures. 4. System shall utilize VRLA batteries. 5. System shall be sized to accommodate 30% expansion. 26 50 00 Lighting Systems Issued 6/20/04 Revised 10/17/11 Page 7 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS J. K. L. Lighting controls 1. All three and four lamp fixtures will be dual switched: one ballast controlling inner lamp(s) and one ballast controlling outer lamps. 2. Motion sensors shall be considered for all areas where the space could be left unoccupied for longer than three hours. Outdoor Lighting Poles 1. Furnish pole, arm and fixture assemblies capable of withstanding a 100 MPH wind velocity for the total assembly. 2. Provide separate conduit(s) for low voltage wiring in light pole (i.e., security camera, phone, card reader, etc. 3. Provide adequate wiring space in pole base for wiring, fuses, and ballast (if remote ballast is required). Outdoor Power Signs 1. All outdoor signs, that have power, shall be provided with a disconnecting means, such as a switch, accessible from the exterior of the sign 2. The sign shall have a pilot light, to display that power is available, connected to the line side of all disconnecting means for the sign. PART 2: PRODUCTS 2.01 MATERIALS A. Lighting Fixtures 1. B. See Appendix for approved “Lighting Fixture Schedule”. Fluorescent Ballasts 1. Fluorescent Electronic Program Instant Start: Energy saving, high power factor, non-PCB, Class "P" approved. Individually fuse with Bussmann Type GMF fuses in HLR holders. Except in recessed fixtures, fuses shall be accessible from outside the fixture chassis. Use fuse rating as recommended by fixture manufacturer. Furnish commercial and recessed type fixtures with ballasts having a NEMA sound rating of "A" or better. All ballasts shall match the lamps specified. Ballasts shall have the following characteristics: a) b) c) 26 50 00 Lighting Systems Power Factor: 95% minimum at full light output. Total Harmonic Distortion: 10% maximum. Crest Factor: 1.7 maximum. Issued 6/20/04 Revised 10/17/11 Page 8 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS d) e) f) 2. Manufacturers: Subject to compliance with requirements, provide products of one of the following: a) b) c) d) 3. e) f) Power Factor: 95% minimum at full light output. Total Harmonic Distortion: 10% maximum. Crest Factor: 1.7 maximum. Temperature Rise: 30 degree C. maximum over 40 degree C. Ambient. Continuous Dimming: 100%-10% light output. "End of Lamp Life" circuitry. Manufacturers/Products: Subject to compliance with requirements, provide products of one of the following: a) b) c) 5. Advance General Electric MagneTek Triad Osram Sylvania Fluorescent Electronic Rapid Start Dimming: Energy saving, high power factor, non-PCB, Class "P" approved. Individually fuse with Bussmann Type GMF fuses in HLR holders. Except in recessed fixtures, fuses shall be accessible from outside the fixture chassis. Use fuse rating as recommended by fixture manufacturer. Furnish commercial and recessed type fixtures with ballasts having a NEMA sound rating of "A" or better. All ballasts shall match the lamps specified. Ballasts shall have the following characteristics: a) b) c) d) 4. Temperature Rise: 30 degree C. maximum over 40 degree C. Ambient. Continuous Dimming: 100%-10% light output. "End of Lamp Life" circuitry Advance Mark VII Series Lutron "EC010" Motorola Fluorescent Low Frequency Electronic (EMI/RFI sensitive locations): Energy saving, rapid start, high power factor, non-PCB, Class "P" approved. Individually fuse with Bussmann Type GMF fuses in HLR holders. Except in recessed fixtures, fuses shall be accessible from outside the fixture chassis. Use fuse rating as recommended by fixture manufacturer. Furnish commercial and recessed type fixtures with ballasts having a NEMA sound rating of "A" or better. All ballasts shall match the lamps specified. Ballasts shall have the following characteristics: 26 50 00 Lighting Systems Issued 6/20/04 Revised 10/17/11 Page 9 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS a) b) c) d) e) 6. Manufacturers: Subject to compliance with requirements, provide products of one of the following: a) C. Advance - PowrKut Metal Halide Ballast 1. High power factor, non-PCB, lead type constant wattage autotransformer with minimum output wattage regulation within plus or minus 5% for input voltage variation of +10%. Individually fuse all ungrounded legs of ballasts. Use fuse ratings as recommended by manufacturer. Use ballasts rated for operation in 55 deg. C ambient temperature for fixtures mounted indoors, except where otherwise specified in the fixture specification. Use ballasts rated for reliable starting down to minus 20 deg. F for fixtures/lamps mounted outdoors 2. Manufacturers: Subject to compliance with requirements, provide products of one of the following: a) b) D. Power Factor: 90% minimum. Total Harmonic Distortion: 20% maximum. Crest Factor: 1.7 maximum. Temperature Rise: 25 degree C. maximum over 40 degree C. Ambient. "End of Lamp Life" circuitry. Advance MagneTek Triad Incandescent Lamps 1. Extended service, rated at 130 volts and 2500 hours rated life, inside frosted. 2. Manufacturers: Subject to compliance with requirements, provide products of one of the following: a) b) c) 3. General Electric Osram Sylvania Philips Incandescent Halogen PAR: Tungsten Halogen Capsule PAR lamps, rated at 130 volts and 2000 hours minimum rated life. 26 50 00 Lighting Systems Issued 6/20/04 Revised 10/17/11 Page 10 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS 4. Manufacturers: Subject to compliance with requirements, provide products of one of the following: a) b) c) E. General Electric Osram Sylvania Philips Fluorescent Lamps 1. Fluorescent T-8: Instant/Rapid start, 48 inch long, 32 watt, medium bi-pin lamp, 2850 lumens, 4100K, 75 CRI (minimum). 2. Manufacturers/Products: Subject to compliance with requirements, provide products of one of the following: a) b) c) General Electric Osram Sylvania Philips 3. Fluorescent T-5: Programmed start, nominal 48 inch long, 28 watt, miniature bi-pin lamp, 2900 lumen 4100K, 82 CRI (minimum). 4. Manufacturers/Products: Subject to compliance with requirements, provide products of one of the following: a) b) Osram Sylvania Philips 5. Fluorescent T-5HO: Programmed start, nominal 48 inch long, 54 watt miniature bi-pin lamp, 5000 lumen, 4100K, 82 CRI (minimum). 6. Manufacturers/Products: Subject to compliance with requirements, provide products of one of the following: a) b) Osram Sylvania Philips 7. Fluorescent Compact: Type and wattage as indicated, preheat, 4100K, 82 CRI (minimum). 8. Manufacturer: Subject to compliance with requirements, provide products of one of the following: a) b) c) 26 50 00 Lighting Systems General Electric Osram Sylvania Philips Issued 6/20/04 Revised 10/17/11 Page 11 of 12 Jones Lang LaSalle @ Beaumont Health System, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 26 50 00 - LIGHTING SYSTEMS 9. Metal Halide Lamps 10. Manufacturers: Subject to compliance with requirements, provide products of one of the following: a) b) c) F. Exit Lighting 1. Manufacturers: Subject to compliance with requirements, provide products of one of the following: a) b) 2. G. General Electric Osram Sylvania Philips Sure-Lite Hubbell Self power exit Emergency Battery 1. Emergency battery units shall be recessed with minimum of two 12 watt tungsten halogen (h1212T-275 lumen) heads, maintenancefree 12 volt sealed lead calcium battery and self diagnostics. 2. Manufacturers: Subject to compliance with requirements, provide products of one of the following: a) b) c) d) 26 50 00 Lighting Systems Exide Cat.# CPH56-H1212W Dual-Lite Cat.#TB-521-12-T (12V,12W) Hubbell Cat. # CL-12-50-2-D Prescolite Cat.#ERT5-CVS-ELH-H1212 Issued 6/20/04 Revised 10/17/11 Page 12 of 12 BEAUMONT HOSPITALS IT Communications Section 27 00 00 TELEPHONE / DATA Requirements Updated 02/23/2011 by Doug Meyers Approvals Name Tim Purves Kathy Grady Dave Colburn Mark R. Taylor Doug Meyers Title Director Manager (Communications) Manager (Communications) Manager ( Network) Infrastructure System Analyst 1 Table of Contents SECTION 1: CLOSET ROOM REQUIREMENTS SECTION 2: VOICE BACKBONE SECTION 3: FIBER BACKBONE SECTION 4: STATION CABLING SECTION 5: CLOSET TERMINATIONS SECTION 6: CATEGORY 6 TEST PROCEDURES SECTION 7: CATEGORY 5 TEST PROCEDURES SECTION 8: MULTI-MODE FIBER BI-DIRECTIONAL LIGHT LOSS TEST PROCEDURES SECTION 9: SINGLE MODE FIBER BI- DIRECTIONAL LIGHT LOSS TEST PROCEDURES SECTION 10: MULTI AND SINGLE MODE OTDR TEST PROCEDURES SECTION 11: PREFERRED VENDOR Section 1 Telephone Equipment Room Requirements Ceiling Height: Minimum 8 ft. 6 in. Doorways: Minimum 36 in., swing inside Flooring: Tile or sealed cement floors Environmental Control: 64 F to 75 F, humidity 30% to 55% 24 hours per day False Ceilings: Not permitted Fire Protection: High temperature Sprinkler heads or dry methods Pre-action sprinkler system (no water in pipe until called for by smoke detector.) Main Equipment rooms only Flood Prevention: Avoid placing below or adjacent to areas of potential water hazard Floor loading: Minimum 2.4kPA Lighting: Minimum equivalent of 50-foot candles measured at 3ft above finished floor Location: To minimize the horizontal cable lengths (275ft) locate the closet as close as possible to the center of, and on the same floor as the area it is intended to serve. Ensure that closets are accessible from a hallway or other common area. Telecommunications closets must be dedicated to the telecommunications function and related support facilities. Power: A minimum of two dedicated 3-wire 120V AC 20A duplex receptacles on one dedicated emergency power circuits. Located at least 6in. but no higher than 18 inches above the finished floor. One outlet on each wall. Conduits to be buried in the walls NOT surface mounted. Provide 2ea quad receptacle to each relay rack; outlets must be two separate dedicated 120VAC 20A circuits one on Emergency Power and one on UPS Power (see diagram for more detail and field verify with WILLIAM BEAUMONT HOSPITAL COMMUNICATIONS DEPARTMENT before placement) Ground bus location determined by William Beaumont Hospital Communications Department. 2 Security: Closets are required to be locked Size: Closet size will be no less than 10ft x 10ft. Main Switch room will be no less than 13ft x 14ft Wall Linings: Line one closet wall with trade size ¾” 4’ x 8’ fire rated plywood and paint with off white fire retardant paint. WBH Communications staff will determine which wall. Conduits, raceways, If possible, locate backbone sleeves, slots, conduits and ducts: on the left side of the closet. Trays and conduits located within the ceiling shall protrude into the closet a minimum of 1” to 2”. All wall and floor penetrations shall maintain fire rating of structure. Fire alarm: Install smoke detectors in all telephone rooms Other Systems: Communications equipment rooms and closets are for Communications use only and not to be used for housing other systems or as a pass through for other systems. This includes electrical panels, nurse call panels, fire and security alarm panels, water and gas (oxygen, vacuum, etc…) pipes and p-tube systems. If any other systems must be colocated, then closet/equipment room size MUST increase accordingly. *Contractor must verify part numbers and/or comcodes. 3 Prototype Equipment Room With Avaya ATM/PNC GMCC EPN February 23, 2011 14 feet 4 Foot Clearance 19 inch Station Patch Panel Rack 4 Foot Clearance 4 - 4 Inch Conduits To The Right of Way Quad Outlet UPS Power Ameritech Interfaces 19 inch Data Equipment Rack 1 - Cisco 4500 2 Power Supplies 220 Volt 16 Amps each NEMA 6-20 Twist Lock Combined Heat 1500 BTU per Hour 19 inch Fiber Patch Panel Rack NOTE: Ladder rack running around the perimeter of the room and over the data racks 32 inches Ameritech Rack Power Requirements Non-UPS Power 1- 220 Volt 30 Amp 1 - 110 Volt 20 Amp Rack supplied by Ameritech for DS-3 26 1/2 X 23 1/2 3 1/2 Foot Clearance EPN 27 inches All 110 Outlets to be located under the plywood backboard 3 1/2 Foot Clearance 12 1/2 Feet Quad Outlet Emergency Power Standard Network Equipment All requires UPS Power 1 - Marconi 200 BX 2 Power Supplies 110 Volt 3 Amp each Slack Manager 39 inches Riser Wall-field Fire Rated Plywood covering al walls from ceiling to minimum18 inches above floor. Port Wall-field EPN Power Requirements UPS Power 17.5 Amp Draw 208 VAC, 60 Hz 30 Amp Breaker NEMA L6-30R Outlet Generates 1662 BTU per Hour Assumptions 1. Only one EPN will be used at the site... No space for expansion. 2. Equipment Room MDF will also be used for IDF purposes. Hence the station cable racks 3. UPS will be housed in separate electrical room. 4. No other equipment or panels, electrical, nurse call, HVAC, Fire Alarm, will be housed in the room. If so additional floor space will be needed. 5. All Riser Cable/Fiber will be fed up through the ceiling. If coming up through the floor additional space will be needed. 4 Prototype Equipment Room For Avaya G3si Telephone System February 23. 2011 14 feet 4 Foot Clearance 4 - 4 Inch Conduits To The Right of Way Quad Outlet UPS power 4 Foot Clearance 19 inch Station Patch Panel Rack Standard Network Equipment All requires UPS Power 1 - Marconi 200 BX 2 Power Supplies 110 Volt 3 Amp each 19 inch Data Equipment Rack Ameritech Interfaces Ameritech Rack Power Requirements Non-UPS Power 1- 220 Volt 30 Amp 1 - 110 Volt 20 Amp Combined Heat 1500 BTU per Hour 19 inch Station Patch Panel Rack NOTE: Ladder rack running around the perimeter of the room and over equipment racks 32 inches Rack supplied by Ameritech for DS-3 26 1/2 X 23 1/2 Heat generated 1000 BTU per hour 3 1/2 Foot Clearance G3si 27 inches All 110 Outlets to be located under the plywood backboard 3 1/2 Foot Clearance 12 1/2 Feet Quad outlet Emergency Power 1 - Cisco 4500 2 Power Supplies 220 Volt 16 Amps each NEMA 6-20 Twist Lock Slack Manager 39 inches Riser Wall-field Fire Rated Plywood covering al walls from ceiling to minimum18 inches above floor. Assumptions Port Wall-field G3si Power Requirements 2 Cabinets - Each requiring: UPS Power 6 Amp Draw 120 VAC, 60 Hz 15 Amp Breaker (total of 2) NEMA 5-15R Outlet (total of 2 duplex on separate circuits) Both cabinets combined generates 900 BTU per Hour 1. Only one EPN will be used at the site... No space for expansion. 2. Equipment Room MDF will also be used for IDF purposes. Hence the station cable racks 3. UPS will be housed in separate electrical room. 4. No other equipment or panels, electrical, nurse call, HVAC, Fire Alarm, will be housed in the room. If so additional floor space will be needed. 5. All Riser Cable/Fiber will be fed up through the ceiling. If coming up through the floor additional space will be needed. 5 Prototype Equipment Room With Prologix PBX February 23,2011 11 feet 3 Foot Clearance 19 inch Station Patch Panel Rack Quad UPS Power Riser Wall-field 19 inch Data Equipment Rack 3 Foot Clearance Standard Network Equipment All requires UPS Power 1 - Marconi 200 BX 2 Power Supplies 110 Volt 3 Amp each 1 - Cisco 4500 2 Power Supplies 220 Volt 16 Amps each NEMA 6-20 Twist Lock Combined Heat 1500 BTU per Hour Quad Emergency Power NOTE Ladder rack running around perimeter of room and over Data Racks. 3 1/2 Foot Clearance 12 1/2 Feet 19 inch Station Patch Panel Rack 4 Cabinet Prologix System Mounts Directly to the wall Measurements 12 Inches deep 49.5 inches wide 78 inches tall All 110 Outlets to be located under the plywood backboard Desk Fire Rated Plywood covering al walls from ceiling to minimum18 inches above floor. Assumptions Avaya Prologix PBX Prologix Power Requirements 4 Cabinets - Each requiring: UPS Power 3.5 Amp Draw 120 VAC, 60 Hz 15 Amp Breaker (total of 2) NEMA 5-15R Outlet (total of 2 duplex on separate circuits) All 4 cabinets combined generates 1134 BTU per Hour 1. Avaya wall mounted Prologix PBX will be used at the site (600 port 200 trunk capacity)... No space for expansion. 2. Equipment Room MDF will also be used for IDF purposes. Hence the station cable racks 3. UPS will be housed in separate electrical room. 4. No other equipment or panels, electrical, nurse call, HVAC, Fire Alarm, will be housed in the room. If so additional floor space will be needed. 5. All Riser Cable/Fiber will be fed up through the ceiling. If coming up through the floor additional space will be needed. 6 Prototype Closet February 23, 2011 10 Feet NOTE: Cabl-o-Fil rack running around the perimeter of the room and over the equipment racks 19 inch Station Patch Panel Rack Cisco 4500 Chassis 2 Power Supplies 110 Volt 16 Amp each UPS Required for patient care facilities 800 BTU heat dissipation 3 Feet Clearance 19 inch Data Equipment & Fiber Rack 6 – inch cable management between racks All 110 Outlets to be located under the plywood backboard 4 Feet Clearance 19 inch Station Patch Panel Rack Fire Rated Plywood covering 1l wall ceiling to 18 inches above floor. Assumptions 1. 2. 3. 4. 5. 6. Multiple Comm Closets with Riser Fiber Pass through required. UPS Power required at all hospital sites & patient care facilities (not required at non-patient care locations) UPS will be housed in separate electrical room. No other equipment or panels, electrical, nurse call, HVAC, Fire Alarm, will be housed in the room. If so additional floor space will be needed. Sufficient station ports to require dedicated rack for mounting patch panels. (A 7 foot rack can hold 15 48-port patch panes which is 360 locations.) Chassis based switch required for survivability, throughput, expandability, wireless. (A Cisco 45000 takes up about 1/2 of a 7 foot rack) 7 VOIP Equipment room February 23, 2011 10 Feet NOTE: Cabl-o-Fil rack running around the perimeter of the room and over the equipment racks 19 inch Station Patch Panel Rack Cisco 4500 Chassis 2 Power Supplies 110 Volt 16 Amp each UPS Required for patient care facilities 800 BTU heat dissipation 3 Feet Clearance 19 inch Data Equipment & Fiber Rack 6 – inch cable management between racks All 110 Outlets to be located under the plywood backboard 4 Feet Clearance 19 inch Station Patch Panel Rack Fire Rated Plywood covering 1l wall ceiling to 18 inches above floor. Assumptions 1. 2. 3. 4. 5. 6. Multiple Comm Closets with Riser Fiber Pass through required. UPS Power required at all hospital sites & patient care facilities (not required at non-patient care locations) UPS will be housed in separate electrical room. No other equipment or panels, electrical, nurse call, HVAC, Fire Alarm, will be housed in the room. If so additional floor space will be needed. Sufficient station ports to require dedicated rack for mounting patch panels. (A 7 foot rack can hold 15 48-port patch panes which is 360 locations.) Chassis based switch required for survivability, throughput, expandability, wireless. (A Cisco 45000 takes up about 1/2 of a 7 foot rack) 8 Section 2 Voice Backbone Lower Level From Main Switch Room to Lower Level closet. The SYSTIMAX cable and size (ARMM or ANMW Types) will be determined by Beaumont Hospitals Communications Department. Cable must be grounded on both ends Floor Closets From Lower Level to Floor closet will be an 400 pair ARMM. Cable must be grounded on both ends. Termination Blocks: SYSTIMAX 110 Field-Terminated Patch Panel Kit Product number: 110PA2-300FT Vertical X/C Troughs Required for all 110 blocks, minimum of 2 troughs per 110 block. Both types are listed but only one will be used. Product number: 110A3 Trough w/legs Product number: 110B3 Trough without legs Horizontal X/C troughs: Required for horizontal X/C management. Troughs will be located on top of every 110 column. Both types are listed, but only one type will be used. Product number: 188B1 without legs Product number: 188B2 with legs Protector Panel: Required when cable is entering or exiting buildings SYSTIMAX188-Type Multipair Protector Panel Product number: 188ENA1-100G Protector Unit: Required when cable is entering or exiting buildings SYSTIMAX 3B-EW Individual Protector Unit Product Number: 3B1-EW Wall Penetrations: All conduits entering from the outside must be sealed around the conduit as well as the inside of the conduit. *Contractor must verify part numbers and/or comcodes. *Must meet requirements for SYSTIMAX Certification * Contractor to supply equipment 9 Section 3 Fiber Backbone Innerduct: SELECT ONE OF FOLLOWING: Provide three (3) 1.25” PE innerduct for outdoor applications. Install in existing vacant 4” conduit. Provide three (3) 1.25” PVC innerduct for indoor applications for MDF to Main Lower Level Closet. Install in existing vacant 4” conduit. Provide two (2) 1.25” PVC innerduct for indoor riser applications. Install in existing vacant 4” conduit. Provide two (2) 1,25” Plenum innerduct for plenum applications. With 6” x 6” pull boxes at all riser closets Lower Level From Main Switch Room to Lower Level closet. The SYSTIMAX cable and size will be determined by Beaumont Hospitals Communications Department. Floor Closets From Main Switch room to Floor closet will be an SYSTIMAX 50 micron 12-strand multi mode fiber. Product number: LazrSPEED 300 P-012-DS-5L-FSUAQ or LazrSPEED 550 (P-012-DS-5K-FSUAQ). Use LazrSPEED 300 if the run is less then 300 meters, LazrSPEED 550 is run is from 300 to 550 meters Both are plenum rated. Riser Rated is also available – change the P to an R in first letter or Part Number. From Main Switch room to floor closet will be an SYSTIMAX 12 strand Single mode TerraSPEED fiber. Product number: R-012-DS-8W-FSUYL (Riser Rated) or P-012-DS-8W-FSUYL (Plenum Rated) Patch Panels SYSTIMAX Distribution System for MDF to Lower Level Closets Product number: 360G2-4U-MOD-SD (760101071) this 4 U sliding shelf accepts 12 cassettes. SYSTIMAX Distribution System for Riser closets Product number: 360 G2-1U-MOD-SD (760103085) this is the 1U shelf that holds 4 cassetes. Cassettes with couplers: 360 G2 Cartridge – 12-LC-LS-AQ (760109256) to be used in above fiber shelves. Connectors SYSTIMAX LC connector Bend Radius: Minimum bend radius is 10 times the diameter of the fiber cable. *Contractor must verify part numbers and/or comcodes. *Must meet requirements for SYSTIMAX Certification *Contractor to supply equipment. 10 Section 4 Hospital Station Cabling Station Cabling SYSTIMAX GigaSpeed XL Cable PVC or Plenum Product number: 1071 PVC or 2071 Plenum Color: Blue OR SYSTIMAX GigaSpeed 10XD Cable PVC or Plenum Product number: 1091 PVC or 2091 Plenum Color: White Outlets SYSTIMAX GigaSpeed XL Outlets Product number: MGS400BH-318 Color: Blue OR SYSTIMAX GigaSpeed X10D Outlet Product number: MGS600-262 Color: White Faceplate SYSTIMAX 4 outlet faceplates Product number: M14L-246 Blanks SYSTIMAX Product number: M20AP-246 Station Cabling Off-Site or Non Patient facility Cabling Uniprise 55N4 PVC Cat5E Uniprise 5504 Plenum Cat5E Uniprise 65N4 PVC Cat 6 Uniprise 6504 Plenum Cat 6. Outlets, Faceplates and blanks will stay the same as above. *Contractor must verify part numbers and/or comcodes. *Contractor to supply equipment. Station Cable Installation Guidelines 1.) The hospital standard for new construction is three Cat 6 cables. Only exceptions are in specific areas of the main Royal Oak campus, or otherwise specified by the Beaumont Hospitals Communications Department. a.) The hospital standard for all VOIP installations is two Cat 6 cables. These will be labeled as D,DA…example…1D,1DA 2.) Each cable will be properly marked and labeled at each end. Proper labeling will include a number that is unique from all others, (i.e.: 1,1A, 2, 2A, etc…) If three cables are pulled in on new construction jobs the cabling will be as follows: One cable to the wall field and the 11 remaining two cables to the Network rack. These will be labeled as follows:( 1V to the wall field, 1D, 1DA to the data racks 2V to the wall field, 2D, 2DA to the data racks, etc….) a) Cables shall be place with sufficient bending radius so as not to kink, shear or damage the cable. The bending radius must never be less than that specified by the manufacturer. b) A contractor will terminate all UTP station cables in compliance with SYSTIMAX standards, both ends. Therefore, proper slack must be maintained at both ends, 2 feet at the wall jack and at least 30 feet at the communications closet. Cables must be bundled neatly. c) Contractor will test each cable for near end cross talk (NEXT) in compliance with IEEE standards for Fast Ethernet, ATM, and Gigabit Ethernet. d) Contractor will provide complete and accurate cable records. Records must be in a format determined by William Beaumont Hospital Communications Department. Cable record Format Facilitech room number Cable number Closet id e) Cable specifications are as follows: Cable must be SYSTIMAX UTP four pair, Gigaspeed Cat 6 - 1071 or 2071 (no substitutions) cable must be IEEE 802.3 100base T compliant. Off campus buildings that may be using tray, rings, or that are not run in conduit will be SYSTIMAX four pair, Gigaspeed Cat 6 (2071). No substitutions except where specified GigaSpeed X10D (1091 or 2091). 8.) Must all be installed according to SYSTIMAX guidelines and able to meet all requirements for a Certified SYSTIMAX Solution with a 20-year warranty. 9.) Acceptable Cable Support Methods (Hospitals): a) Preferred method for Hospital pathways - Pathways from user location shall be continuous conduit to cable tray or to Communications Closet b) Alternative method for Hospital pathways – Conduit from user location past header with 2 inch J-hooks to corridor. Cable in corridor to be in either cable tray or conduit, to the Communications Closet. a. 2 inch J-hook capacities are no more than 12 cables or 4 full locations b. J-hooks to be no more than 4 feet apart c. All cable must be dressed using Velcro tie wrap d. Cable Tray will be 12 inches wide and 2 inches deep “CabloFil” tray e. Maximum fill for this tray is 250 cables or 83 full locations 12 10.) Acceptable Cable Support Methods (Off Campus): a) Preferred method for Off Campus pathways - Pathways from user location shall be continuous conduit to cable tray or to Communications Closet b) Alternative method for Off Campus pathways – Conduit from user location past header with 2 inch J-hooks to corridor. Cable in corridor to be in either cable tray or 4Inch J-hooks, to the Communications Closet. a. 2 inch J-hook capacities are no more than 12 cables or 4 full locations b. 4 inch J-hook capacities are no more than 36 cables of 12 full locations c. All J-hooks to be no more than 4 feet apart d. All cable must be dressed using Velcro tie wrap e. Cable Tray will be 12 inches wide and 2 inches deep “CabloFil” tray f. Maximum fill for this tray is 250 cables or 83 full locations Note: Contractor shall work in close cooperation with the Beaumont Hospital Communications Department and all work shall conform to this specification document. Should the Beaumont Hospital Communications Department make known to the JLL@BHs Project Manager an objection to the layout, the JLL@BHS Project Manager shall immediately notify the architect- engineer or general before proceeding with work. Conduit Size for Cat 6 cable Conduit Size (EMT) ¾” 1” 1-1/2” 2” 3” 4” Quantity of cables 4 7 16 26 69 116 This will allow for 40 % fill of the conduit and leave 60% spare. Conduit should not have more than 180 degrees total in conduit run, unless junction boxes are provided prior to immediately after the 180 degrees has been reached. Please consult Systimax guidelines in place at time of installation for cable fill for both Cat 6 and 6a as appropriate. 13 Section 5 Closet Terminations Voice Termination SYSTIMAX Field Terminated Wiring Block Kit Product number: 110AB2-100FT Data Termination SYSTIMAX 360 Patchmax GS XLPatch Panel Kit for Cat 6 Product number: 360-PM-GS3-2U-48P 760117366 this panel is now 2U for 48 ports. For 6A use 360-PM-GS5-2U-48P 760117374 Relay Rack Ortronics Data Rack (minimum 5ea Main Switch room and 3 ea. in riser closets) Ortronics: Rack Mighty MO 6 - 7’H x 10.5” Channel Depth part # MM6710 Ortronics: Vertical Cable Manager – Mighty MO 6 Channel – 6”x8”x7’ with door part # MM6VMD706 Ortronics: Four Post Server Rack – part # MM107SVR Patch Cables SYSTIMAX GigaSpeed patch cords (one pair per location) Part number: GS8E -7ft and -15ft CPC3312 for Cat 6 For 6A use 360GS10E cords in the same lengths. Tubular Runway Cablofil: Cable Tray – 12” W x 2” D x 10’ L (Black) part # CF54/300BL cable tray shall be installed around perimeter of room and wall to wall above relay racks *Contractor must verify part numbers and/or comcodes. *Contractor to supply equipment 14 Section 6 Standards for Testing and Documentation for Beaumont Hospitals Certification of an Installed Category 6 Link Horizontal Limitations: The maximum cable distance from Outlet to patch panel shall be 275 ft, (295 ft) independent of media type. A WORK STATION 275 ft B PATCH PANEL OUTLET HUB A or B must not be greater than 14 feet each Tests to Perform: Length, Near End Cross Talk (NEXT), PSNEXT, FEXT, PSFEXT, RL, Attenuation, Attenuation to Crosstalk Ratio (ACR), Wire Map, Impedance, Capacitance, Resistance, Delay, Cable Skew. Certification tests to be performed using an approved (Level III or Level IV) hand-held tester such as the Fluke DTX Cable Analyzer series. The following are the steps required to properly certify an installed link. Employees and contractors must follow all procedures to ensure proper test results. Step 1. Make sure that the Fluke DTX Cable Analyzer series or equivalent level III or Level IV tester has been fully charged. Step 2. Make sure the Fluke DTX Cable Analyzer series or equivalent level III or Level IV tester’s display indicates that CAT6 Permanent Link or Channel for channel. Step3. Review the Fluke DTX Cable Analyzer series or equivalent level III or Level IV tester’s Permanent Link or Channel calibration procedure and calibrate if needed for the test to be performed. Step 4. Enter the job number into the “Company Name” field. Step 5. Attach the Permanent link supplied cable to the permanent link portion of the link and perform a permanent link test. Press the “Autotest” button and wait until the “PASS” indicator appears. 15 Certification of an Installed Category 6 Link (continued) Step 6. Save the test result using the Circuit ID number designated for that location. (Beaumont Hospitals Communications Department to designate ID numbers) Repeat step 5 and 6 for all locations to be tested. Step 7. Contractor will provide Pass/Fail summary and hard and soft copies of the test results to the JLL@BHs Project Manager; The PM will forward copies to Beaumont Hospitals Communications Department. 16 Section 7 Standards for Testing and Documentation for William Beaumont Hospitals UTP Cable Certification for Gigabit Ethernet The 1000Base-T standard was developed with the goal of supporting the huge installed base of Category 5 UTP. However, the complex modulation technology developed for 1000Base-T is sensitive to cabling performance characteristics that were not defined in the original Category 5E UTP cabling or testing specifications. Therefore, it will be necessary to test new and existing Category 5E installations and new Category 6 for compliance with these additional requirements before running 1000Base-T traffic over these cabling runs. Horizontal Limitations: The maximum cable distance from Outlet to patch panel shall be 275 ft, (295 ft) independent of media type. A WORK STATION 275 ft B PATCH PANEL OUTLET HUB A or B must not be greater than 14 feet each Tests to Perform: Length, Near End Cross Talk (NEXT), PSNEXT, PSELFEXT, Attenuation, Attenuation to Crosstalk Ratio (ACR), Wire Map, Impedance, Capacitance, Resistance, Delay, Equal Level Far-End Crosstalk, Return Loss, Delay Skew. Certification tests to be performed using an approved (Level III or Level IV) hand-held tester such as the Fluke DSP, or DTX Cable Analyzer series. The following are the steps required to properly certify an installed link. Contractors must follow all procedures to ensure proper test results. The following are the steps required to properly certify an installed link. Employees and contractors must follow all procedures to ensure proper test results. Step 1. Make sure that the Fluke DTX Cable Analyzer series or equivalent level III or IV tester has been fully charged. 17 Step 2. Make sure the Fluke DTX Cable Analyzer series or equivalent level III or IV tester’s display indicates the permanent Link level to be tested. In the options menu choose the “Performance level” option. Scroll to the type of performance level you will be testing. I.e. UTP CAT 5E, UTP CAT 6, Permanent Link etc. Step3. Review the Fluke DTX Cable Analyzer series or equivalent level III or IV tester’s Permanent Link calibration procedure and calibrate if needed. Step 4. Enter the job number into the “Company Name” field. Step 5. Attach the Permanent link supplied cable to the permanent link portion of the link and perform a permanent link test. Press the “Autotest” button and wait until the “PASS” indicator appears. Step 6. Save the test result using the Circuit ID number designated for that location. (William Beaumont Hospital Communications Department to designate ID numbers) Repeat step 5 and 6 for all locations to be tested. Step 7. Contractor will provide Pass/Fail summary and hard and soft copies of the test results to the BSC Project Manager; The PM will forward copies to William Beaumont Hospital Communications Department. 18 Section 8 Standards for Testing and Documentation at William Beaumont Hospitals Light Loss Testing Multimode Fiber using the Siecor OTS Optical Tester Customer premises optical fiber has been and continues to be primarily 62.5 / 125 m multimode fiber unless otherwise specified. All multimode fiber shall be tested at 850 nm and 1300 nm wavelengths and shall not exceed maximum attenuation of 3.75 dB/km at 850 nm and 1.5 dB/km at 1300 nm. Establishing Reference Levels: Prior to testing, reference levels must be established. Step 1. Connect a short jumper with 5 turns on a 25 mm diameter mandrel wrap for (50um LOMMF) or 5 turns on a 20 mm diameter mandrel wrap for (62.5um MMF) between the source OTS and the meter OTS. Set both units to the same wavelength and press TX on the source unit to turn the transmitter on. The OTS meter will display the coupled output power of the source, typically around –20 dBm. Press the REF button to reference the power meter so that it indicates 0.0r (relative loss). Repeat this for each wavelength to be tested, ensuring that both the optical source and the meter are set to the proper wavelength. For Bi-directional testing, reverse the source/meter roles of the OTS units and repeat step 1. * Add Mandrel wrap as described above JUMPER OTS METER OTS SOURCE Step 2. Connect a short jumper with mandrel wrap as described above to the source OTS and another known good short jumper to the meter OTS. Connect the two jumpers with coupler of the same type as the fiber to be tested. Set both units to the same wavelength and press TX on the source unit to turn the transmitter on. The OTS meter will display the coupled output power of the source, through the cables you will be using during the test. Note this reference power level in the space provided on the Fiber Optic Test Sheet. Repeat this for each wavelength to be tested. If the loss through the test jumpers is less than or equal to 0.5 dB, both test jumpers are good and will provide a valid test. Otherwise, clean the connectors and repeat Step 2 until 0.5 dB or better is achieved. If necessary, replace the test jumper(s) and repeat Step 2. JUMPER JUMPER COUPLER OTS SOURCE OTS METER 19 Light Loss Testing Multimode Fiber (continued) Performing a Loss Test: Disconnect the jumper at the adapter and connect them to the respective patch panels at opposite ends of the same fiber as shown in the diagram below. Using the OTS Source as the transmitter, record the loss in dBm displayed by the OTS meter on the Fiber Optic Test Result Sheet. Repeat this for all wavelengths to be tested. For bi-directional testing, reverse the roles of the two OTS units and repeat the Loss test for all fibers. OPTICAL FIBER SYSTEM JUMPER JUMPER PATCH PANEL OTS SOURCE PATCH PANEL OTS METER All fiber will be identified and labeled to Beaumont specifications. Contractor will provide Pass/Fail summary and hard and soft copies of the test results to the JLL@BHs Project Manager; the PM will forward copies to Beaumont Hospitals Communications Department. 20 Section 9 Standards for Testing and Documentation at Beaumont Hospitals Light Loss Testing Singlemode Fiber using the EXFO FTB & Siecor OTS Optical Tester For growing bandwidth requirements and for longer distance runs, especially in uncontrolled environments, singlemode fiber is most often used. All singlemode fiber shall be tested at 1310 nm and 1550 nm wavelengths and shall not exceed maximum attenuation of 0.5 dB/km at 1310 nm and 0.5 dB/km at 1550 nm. Establishing Reference Levels: Prior to testing, reference levels must be established. Step 1. This test uses the EXFO OTDR as the source and the Siecor OTS as the meter for the single mode test. Set the output of the EXFO OTDR single mode module to continuous. Connect a short jumper between the EXFO single mode module and the meter OTS. Set both units to the same wavelength and turn the OTDR laser on. The OTS meter will display the coupled output power of the OTDR source. Press the REF button to reference the power meter so that it indicates 0.0r (relative loss). Repeat this for each wavelength to be tested, ensuring that both the optical source and the meter are set to the proper wavelength. JUMPER OTS METER EXFO OTDR SOURCE Step 2. Connect a short jumper to the EXFO OTDR and a short jumper to the meter OTS. Connect the two jumpers with coupler of the same type as the fiber to be tested. Set both units to the same wavelength and turn the OTDR laser on. The OTS meter will display the coupled output power of the source, through the cables you will be using during the test. Note this reference power level in the space provided on the Fiber Optic Test Sheet. Repeat this for each wavelength to be tested. If the loss through the test jumpers is less than or equal to 0.5 dB, both test jumpers are good and will provide a valid test. Otherwise, clean the connectors and repeat Step 2 until 0.5 dB or better is achieved. If necessary, replace the test jumper(s) and repeat Step 2. JUMPER JUMPER COUPLER OTS METER 21 Light Loss Testing Singlemode Fiber (continued) Performing a Loss Test: Disconnect the two jumpers at the adapter and connect them to the respective patch panels at opposite ends of the same fiber as shown in the diagram below. Using the EXFO OTDR as the transmitter, record the loss in dBm displayed by the OTS meter on the Fiber Optic Test Result Sheet. Repeat this for all wavelengths to be tested. For bi-directional testing, move the OTDR to the opposite end of the fiber to be tested and repeat the Loss test for all fibers. OPTICAL FIBER SYSTEM JUMPER JUMPER PATCH PANEL EXFO OTDR SOURCE PATCH PANEL For Bi-directional testing, move equipment to Opposite ends of the fiber to be tested and repeat test OTS METER Contractor will provide Pass/Fail summary and hard and soft copies of the test results to the BSC Project Manager; the PM will forward copies to William Beaumont Hospital Communications Department. 22 Section 10 Standards for Testing and Documentation at William Beaumont Hospitals OTDR Testing of Singlemode or Multimode Fiber Singlemode fiber shall be tested at 1310 nm and 1550 nm wavelengths and shall not exceed maximum attenuation of 0.5 dB/km at 1310 nm and 0.5 dB/km at 1550 nm. All multimode fiber shall be tested at 850 nm and 1300 nm wavelengths and shall not exceed maximum attenuation of 3.75 dB/km at 850 nm and 1.5 dB/km at 1300 nm. Step 1 Verify that the OTDR being used is capable of performing tests at the proper wavelengths and that all test parameters are set according to the fiber manufacturers specifications. Step 2. Connect one end of a 100’ jumper to output of the OTDR and the other end of the 100’ jumper to one end of the fiber to be tested. At the other end of the fiber to be tested connect another 100’ jumper. The other end of the second 100’ jumper is not connected. These two 100’ jumpers provide a discernable start and end point that is displayed on the OTDR trace. FIBER UNDER TEST 100’ JUMPER 100’ JUMPER OTDR Step 3. Depending on the OTDR in use, Manually or Automatically begin a test sweep. The sweep result should look similar to the sample below 100’ JUMPER FIBER UNDER TEST 100’ JUMPER Step 4. Save the sweep results and perform the test again for all required wavelengths. Processed results must include a copy of the sweep trace and all results as detailed on the attached sheet. Step 5. Contractor will provide hard and soft copies of the test results to the BSC Project Manager; the PM will forward copies to William Beaumont Hospital Communications Department. 23 Section 11 Preferred Vendor list for Communications 1. Shaw Systems & Integretion (SSI) Pat Smalarz 24650 Sherwood Center Line MI, 48015 (586) 427-1015 2. Industrial Electrical Co. Tom Darrish 275 E. Milwaukee Detroit, Michigan 48202 (313) 872-1133 3. Conti Technologies John Darrah 6417 Center Drive Suite 110 Sterling Heights, Mi. 48312 (586) 274-4800 24 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements PART - 1 1.01 GENERAL REQUIREMENTS GENERAL DESCRIPTION A. All fire alarm systems design / installation shall be bid separately from all other electrical systems (i.e. power, lighting, etc). This portion of the Fire Detection and Alarm System Standards is to provide requirements for engineering design services, which shall include, but shall not be limited to, field investigation, preparation of construction documents and construction administration related to the installation of, or revisions to, the fire alarm system serving William Beaumont Hospital(s) and ambulatory care facilities (refer to Beaumont Services Company Out-building Standard for other types of occupancies). B. Engineering services shall be as required for expansion of the existing system. Engineering Design shall be complete as required for a fully functional system. System designer shall be pre-qualified and approved by the Fire Protection Work Group. Current acceptable designer(s) include: Shaw Systems & Integration (expires 12-2011) 1.02 C. Engineering design shall be in accordance with these standards. No modifications to these standards will be accepted without the expressed written approval of the Fire Protection Work Group. It is the design engineer’s responsibility to document the Fire Protection Work Group’s approval of any such modifications prior to the execution of design work. D. The latest version of this standard is available online at www.beaumontservices.com\suppliers. CODES, STANDARDS, ORDINANCES AND PERMITS A. Design shall conform to the requirements of the applicable portions of the National Fire Protection Association (NFPA) Standards, Guides and Recommended Practices as well as other Codes and Standards as adopted by the Authorities Having Jurisdiction: NFPA 70 NFPA 70B NFPA 72 NFPA 80 NFPA 80A NFPA 90A NFPA 92A NFPA 96 NFPA 99 NFPA 101 NFPA 221 ADA - National Electric Code Recommended Practice for Electrical Equipment Maintenance National Fire Alarm Code Standards for Fire Doors and Fire Windows Recommended Practice for Protection of Buildings from Exterior Fire Exposures Standard for the Installation of Air Conditioning and Ventilation Systems Recommended Practice for Smoke Control Systems Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations Standard for Health Care Facilities Codes for Safety to Life from Fire in Buildings and Structures Standards for Fire Walls and Fire Barriers Americans with Disabilities Act 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 1 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements IFC MBC MMC NEMA AIA International Fire Code Michigan Building Code Michigan Mechanical Code Guide for Proper Use of System Smoke Detectors State of Michigan Barrier Free Requirements Guidelines for Design and Construction of Hospital and Health Care Facilities B. The cover sheet shall list the codes that are used for the fire alarm design. All drawings shall state in bold letters, “The Design and Installation Shall Conform to The William Beaumont Hospital Fire Detection and Alarm System Standards.” C. If there is a conflict between the referenced NFPA standards, Federal, State or Local codes and this specification, it is the Designers responsibility to bring the conflict to the attention of the “Owner” for resolution. Designer shall not attempt to resolve conflicts directly with the local authorities unless specifically authorized by the “Owner.” D. All devices, equipment and materials specified shall be new and listed by Underwriters Laboratories Inc. (ULI) for the intended use. All equipment shall be installed in accordance with Simplex's recommendations, guidelines and installation details as well as ULI listing limitations. Compatibility listing requirements for separate voice, fire alarm systems and smoke detectors shall be met. Documents shall require that the Contractor provide evidence, with the submittals, of listings of all proposed equipment and combinations of equipment. 1. All components for which ULI listing is required shall be listed in the current edition of the ULI Fire Protection Equipment Directory and shall be delivered to the project site with factory applied UL stickers. System components that do not meet these requirements are not acceptable. 2. Components for which ULI listing is "pending" are not acceptable. E. All devices, systems, equipment and materials furnished and installed shall be of types or models approved by the Authorities Having Jurisdiction for use in systems and occupancies of this type. F. All fire alarm system components shall be catalogued and purchased from Simplex under Beaumont Services Company, LLC. Pricing agreement and approved for use on the existing system. SimplexGrinnell shall provide an itemized quotation showing all appropriate discounted prices. G. All wiring shall be specifically approved for fire alarm use, wire and cable shall be UL Listed and in accordance with local codes and the Authorities Having Jurisdiction. H. Raceways containing conductors identified as "Fire Protective Alarm System" conductors shall not contain any other conductors serving other systems. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 2 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 1.03 PROJECT DESIGN DRAWINGS A. Project design drawings shall be prepared using the current version of AutoCad in accordance with Beaumont Services Company/Technical Information Group Standards and shall include the following: 1. Incorporate the guidelines for drawing layer and standards. 2. Utilize Beaumont Services Company/Technical Information Group Fire Alarm symbols, conventions, abbreviations and specialized terminology. Refer to sheets FASL-1 included in the appendix for standard symbols. 3. Floor plan drawings at l/8-inch scale generated from the Fire Alarm System Drawings. Drawings shall depict the required information showing proper spatial relationships between components, and shall reflect the corresponding system components as they are to be installed. Floor plans shall show the following minimal information: a) Name of owner and occupant b) Location, including street address c) Point of compass (north arrow) d) Graphical scale indicator e) Tower boundaries f) Smoke zone boundaries g) Rated walls h) All room names and numbers i) Key plan showing area of renovation or construction within the hospital or building j) Areas which are to be included in the current phase of the work k) Preliminary fire alarm device schedule, indicating quantity 4. Drawing list/index 5. Each drawing shall be cross-referenced to all related drawings and specific drawing details as necessary for the design drawings as a whole to clearly depict the proposed installation. 6. For drawings that have been revised, show revision (bulletin or addendum) number and date indicated in the title block with revisions described or indicated (clouded). 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 3 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 7. B. Provide Beaumont Services Project Manager name and Project number. Project design drawings shall be considered “installation drawings.” All devices, conduit, wiring etc. shall be indicated on plan in the actual location where it is intended to be installed so that substantial revisions in the field should not be required. Design drawings should be prepared so that conduit/cable routing, cable tray, junction box locations, device locations, etc. can be installed where indicated on plan. Drawings of a schematic nature, or drawings not providing sufficient detail, are not acceptable. Design drawings shall show the following information: 1. Location of existing Simplex Data Gathering Panels in the area of renovation or construction. 2. Location of new and existing fire alarm system terminal cabinets, including Typical Terminal Cabinet Detail. (Refer to sheet FADET-2 contained in the appendix.) 3. System network or terminal cabinet risers. For projects where new riser wiring is required, include the following information: a) Number, size and type of system riser conduits/raceways and the number, size and type of conductors/circuits contained therein. This information shall be depicted in sufficient detail to identify the conductors/circuits contained in any particular riser. b) The general arrangements of, and interconnections between, system components on each floor or level of the building. c) When multiple risers are required, a single line generic riser diagram is unacceptable. 4. Fire alarm system demolition as applicable. Include all fire alarm system devices to be demolished or relocated. 5. New 120-volt emergency electrical power (Life Safety Branch) connections, including circuit breaker number(s) and panel. 6. Detailed installation information and wiring diagrams for all Fire Alarm System devices. 7. When new control panels or terminal cabinets are required, include detailed wiring diagrams for all alarm control panels, control panel modules, power supplies, electrical power connections, auxiliary function relays, etc. Identifying all required terminations. 8. Sequence of Operation defining how system operates and the interaction of other systems. Including, but not limited to, mechanical air handling systems, fire suppression systems, wet chemical systems, pre-action systems, flooding gas systems, security systems, gas detection systems, elevator recall systems, smoke control systems, etc. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 4 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 9. 10. System programming requirements indicating the interaction of fire alarm input and output devices. Field program information shall include: a) Adding or deleting monitor and control points. Change in text descriptions associated with individual monitor/control points. This text must be approved by William Beaumont Hospital Security Department prior to programming. b) Device-specific programming for individual monitor points, such as fire alarm, supervisory alarm, priority 2 alarm, trouble alarm, etc. c) Device-specific programming for individual control points, as defined in Sequence of Operation (see #8 above). d) Temporarily bypass control points independent of their associated monitor points. Use of this feature shall allow any operator selected detector(s)/zone(s) to be monitored by the system while inhibiting all alarm inputs except for local display at CRT's and printers. Access to this feature shall be password protected. A listing function shall be available to list all bypassed devices/zones at designated printers and CRT's. e) Selective output of signals, by assigned priority, to annunciation devices including graphic annunciators, CRT's and printers. Each type of annunciator shall be capable of displaying and/or recording a different group of signals. f) Through programming, addressable monitor and control points may be combined into logical groups or zones (in software) to the extent that such grouping does not detract from the required operation of the system, including resounding of signals subsequent to actuation of the signal silence switch. All new and existing fire alarm system devices or system control panels interfaced with the fire alarm system, including but not limited to the following: a) Smoke detector b) Projected beam detectors c) Heat detectors d) Combination fire/smoke dampers, EPs, End switches e) Smoke dampers, EPs, End switches f) Manual fire alarm pull stations g) Fire fighter phones/jacks 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 5 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 11. h) Visual notification appliances including candela rating i) Audible notification appliances j) Control modules k) Monitoring modules l) Fire alarm relays m) Fire suppression system valve tamper switches n) Fire suppression system waterflow switches o) Door hold open and release devices p) Auto doors interfaced with the fire alarm system q) End of line devices r) Location of security system APC door control panels when interfaced with fire alarm system s) Elevators recall systems System raceways and wiring including: a) All wiring serving devices indicated in section 10. b) All wire types, color codes, conductor sizes, shields, etc. Refer to sheet FAWS contained in the appendix for addressable wiring legend c) All conduit, boxes, raceways, etc. serving all wiring. d) Conduit and wiring shall be shown as point-to-point (actual) conduit, raceway and circuit routing, identifying number, size and type of conduits/raceways and conductors. This information shall be depicted in sufficient detail to readily locate specific conduits, raceways and circuits in the field and to identify the specific conductors/circuits contained therein. French curve routing is not acceptable for depicting new conduits, raceways and circuits, or for depicting existing conduits, raceways and circuits whose detailed routing can be determined without demolition of existing construction. C. Shall indicate existing devices, conduit and associated wiring to be removed. For devices removed, all conduit and wiring shall also be removed to point of origin, unless required to maintain the operation of existing devices. D. Design engineer shall be responsible for determining the location of all new fire alarm system devices. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 6 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements E. Design engineer shall field verify the location of all existing fire alarm system devices, conduit, wiring, etc. In addition, fields verify the location of temperature control system control panels, motor starters, security system APC panels, etc. F. Include on the fire alarm drawings, all device labels. (Refer to sheet FADL “Device Labeling Scheme,” contained in the appendix.) G. Fire Alarm Address Label Schedule 1. Provide on the drawings a Fire Alarm Address Label Schedule, which will be used to program the fire alarm system with device and circuit information. The schedule shall include the following minimal information: a) Device type b) Device Location c) Node number d) Mapnet number e) List total quantity of all new initiating and notification devices f) Descriptor language indicating device and circuit information to be programmed into the fire alarm system. (Language shall be coordinated with WBH Security Department) (Refer to sheet FADS-1 in appendix “Fire Alarm Address Label Schedule (Descriptor Chart)”) 1.04 DESIGN CALCULATIONS A. The design database (program) shall be maintained by SimplexGrinnell. The design engineer will request from BSC FA/FS, the current program database, for design purposes. B. All design calculations and device addresses shall be coordinated, verified and approved by SimplexGrinnell, prior to issuance of construction documents. Design calculations will be submitted for the following new equipment: 1. Standby battery capacity calculations. Battery calculations shall list the type of devices and modules, quantities; unit and extended amperage draw for quiescent and alarm conditions, total amperage draw and battery amp/hour rating. For design criteria, the battery amp/hour rating listed by the manufacturer shall be de-rated by 20%. Include all system power requirements including those requirements for electrical door holders and door unlocking systems, visual-signaling appliances, or any other auxiliary function powered by the system. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 7 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 1.05 2. New AC power supply calculations, including all system loads associated with new AC power supplies and/or existing AC power supplies for which new loads are added. Include requirements for electrical door unlocking systems, visual-signaling appliances, or any other auxiliary function powered by AC power. 3. New DC power supply calculations, including all system loads associated with new DC power supplies and/or existing DC power supplies for which new loads are added. Include requirements for electrical door unlocking systems, visual-signaling appliances, voltage drop calculations, or any other auxiliary function powered by DC power. 4. Amplifier capacity calculations showing sizing of amplifiers, which are capable of powering all speakers simultaneously while operating at 80% of their rated capacity. DRAWING REVIEW/AGENCY APPROVAL A. William Beaumont Hospital Review and Approval: 1. Following the completion of the project design, submit to the Beaumont Services Company Project Manager, one (1) complete set of contract bid documents including one (1) set of drawings and an electronic copy. 2. Clearly indicate in the drawing issue/revision block that the drawings are submitted for Owners Review along with the date submitted. 3. Following receipt of Beaumont Services Company review comments, revise the drawings as indicated or directed. 4. Following the incorporation of review comments, indicate in the drawing issue/revision block that the drawings are submitted for bids along with the bid date. Bid date should be coordinated with the Beaumont Services Company project manager or design firm Project Architect as applicable. Submit to the Beaumont Services Company Project Manager, one (1) complete set of revised contract bid documents including one (1) set of drawings and an electronic copy. B. C. State of Michigan Review and Approval: 1. Bid drawings will be submitted for review to the State of Michigan MDCIS, Office of Fire Safety by Beaumont Services Company, L.L.C. This applies to new construction as well as renovation projects. 2. Bid drawings will also be submitted to the State of Michigan by the Fire Alarm System Contractor who will package the drawings with the Application for Fire Safety Plan Examination. City Review and Approval: 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 8 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 1. Bid drawings will be submitted for review to the City Fire Marshal’s Office by Beaumont Services Company, L.L.C. 2. A meeting will be scheduled to review the City Fire Marshal’s comments. The Beaumont Services Company, L.L.C. Project Manager will inform the appropriate parties if their presence is required at the review meeting. 3. Review comments of significance shall be revised on design drawings and incorporated into a bulletin. 4. Minor Review comments, when not required to be resubmitted shall be incorporated into as-built documents. 5. Construction shall not proceed until a red stamped set of approved drawings or Approved as Noted drawings is received from the City Fire Marshal’s Office. D. 1.06 Refer to the “REVIEW AND INSPECTION PROCEDURE FOR FIRE PROTECTION WORK” document RECORD DOCUMENTS A. Progress Documentation: 1. Fire alarm system drawings in AutoCAD format shall be made available by the designer to the fire alarm system contractor at no cost. 2. The fire alarm system contractor shall maintain a marked up set of design drawings to reflect “as-built” conditions on the job site for inspection. 3. The fire alarm system contractor shall deliver the field marked up as-built drawings to the fire alarm system designer. Fire alarm system designer shall incorporate these markups into as-built AutoCAD drawings to be included in project record documents. 4. All AutoCAD work shall be prepared using the current version of AutoCAD in accordance with Beaumont Services Company/Technical Information Group Standards. 5. One field marked up set of as-built drawings and an electronic AutoCAD copy shall be provided to the Beaumont Services Company Fire Alarm Fire Suppression Department at the time of each system tie in. B. Final Close Out Documentation: 1. As-built drawings shall include all changes to design documents. 2. As-built drawings shall be prepared in accordance with the Beaumont Services Technical Information Group standards. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 9 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 3. Submit to the Beaumont Services Company Project Manager, one (1) complete set of revised record documents including one (1) set of drawings and an electronic copy in the latest version of AutoCAD in use by the hospital, all in conformance with Beaumont Services Technical Information Group standards. 4. Final documents shall include all Fire Marshal changes/comments. 5. Final payment to fire alarm contractor shall not be made until final as-built drawings have been received by Beaumont Services Company/Technical Information Group. PART - 2 2.01 DESIGN AND MATERIALS SYSTEM CONFIGURATION A. Circuits: 1. Initiating Device Circuits (IDC) - Initiating device circuits shall be Class B, Style "B" as described in the latest applicable edition of NFPA 72. 2. Signaling Line Circuits (SLC) – Addressable initiating device circuits shall be Class B, Style "4" as described in the latest applicable edition of NFPA 72. 3. Notification Appliance Circuits (NAC) – Notification appliance circuits shall be Class B, Style “Y” as described in the latest applicable edition of NFPA 72. B. Network communication signaling line circuits: 1. Activation of all fire alarm device types shall be annunciated individually at the fire command center. (Networked) 2. Circuits connecting remote annunciation devices and central station monitoring equipment with the control panel, and the 4120 network interface communication system circuits between the data gathering panels and the system head-end equipment shall be Class A, Style "7" as described in the latest applicable edition of NFPA 72. 3. All addressable or digital data circuits, between the control unit and data gathering panels shall be considered signaling line circuits. C. Two Way Telephone Circuits: D. Two-way telephone communications service circuits shall be Class B, Style "X,” supervised with end-of-line resistors. E. Control Circuits: 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 10 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 1. 2.02 FIRE ALARM SIGNALS A. 2.03 Control circuits for supervised relays, control ZAM’s, or relay IAM’s shall be Class B, Style "X.” Activation of the following devices shall be recognized and annunciated individually at the fire command center as fire alarms: 1. Smoke detectors 2. Heat detectors 3. Manual fire alarm pull stations 4. Fire protection water flow alarm switches. 5. Kitchen hood fire suppression (Ansul) System. 6. Pre-action type fire suppression systems. Both first and second alarms shall be annunciated and shall result in a fire alarm condition. 7. Smoke type beam detectors, such as used in Atrium areas shall be monitored by the fire alarm system. 8. Air sampling Systems (VESDA) level 1 alarms. 9. Flame Detector (Ultraviolet) 10. Special Hazard Suppression System activation. SUPERVISORY ALARM SIGNALS A. The following conditions shall be recognized and annunciated individually at the fire command center as supervisory alarms: 1. Fire suppression valve supervisory switch actuation. 2. Gaseous systems abort stations. 3. Generator Running. 4. Fire pump (see sheet FAWD-10 for details) a) Pump Running b) Power Loss c) Phase Reversal d) Power on Emergency 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 11 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 2.04 2.05 e) Emergency Isolation Switch Open f) Pump Controller not in Auto 5. Smoke/fire damper Duct Smoke Detectors. 6. Low air monitors dry pipe or pre-action sprinkler systems. TROUBLE SIGNALS A. The system shall recognize and annunciate initiating device, signaling line circuit and notification appliance circuit trouble conditions as required by the latest applicable edition of NFPA 72. (Refer to table in section 2.01) B. The system shall recognize and annunciate the following trouble conditions: 1. Gaseous suppression system trouble signals. 2. Pre-Action Suppression systems trouble signals. 3. VESDA Panel trouble signals. 4. Damper position abnormal signals. 5. Airflow abnormal signals. 6. VFD abnormal signals. 7. AHU Power abnormal signals. 8. Interfaced Fire Alarm Control Panel trouble signals. 9. Generator abnormal signals. 10. Kitchen shunt trip power monitoring signals. 11. Communications Power abnormal signals. 12. Accordion fire door controller abnormal signals. PRIORITY 2 ALARMS A. The following conditions shall be recognized and annunciated individually at the fire command center as Priority 2 alarms: 1. ETO Gas monitoring alarms. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 12 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 2.06 2. H202 Monitoring alarms. 3. VESDA level 2 and level 3 alarms. 4. Refrigerant monitoring. 5. Elevator recall alarm. SYSTEM DESIGN REQUIREMENTS AND RELATED EQUIPMENT A. System components shall be modular in design to provide future expansion capability of the system. B. The system shall be designed and installed with sufficient capacity, power and control capability for all initiating, indicating and auxiliary function devices. Spare capacity shall pertain to quantities of device, circuits, power supplies, conductor amp capacities (size) and lengths, terminal cabinets, etc. Circuits, circuit boards, etc. shall have spare installed capacity enabling it to support a twenty percent (20%) increase in initiating, control and indicating device circuits. C. Initiating device circuits and notification appliance circuits shall be dedicated to the smoke-zone they serve and shall not cross smoke-zone boundaries. Refer to master zoning drawings. D. Alarm verification function shall be utilized for smoke detectors. E. Environmental conditions: 1. F. All system components shall be listed for the appropriate environment. Examples include: a) Humidity b) Outdoors c) Temperature d) Corrosive/Explosive atmospheres Electromagnetic Interference: 1. All fire alarm control equipment, devices and wiring shall be protected against unwanted radiated electromagnetic interference (EMI) and radio frequency interference (RFI) which can interfere with normal system processing and possibly cause unwanted alarms. 2. The system shall be designed to be unaffected by the operation of a handheld portable radio (walkie-talkie) of 5 watts power generating capability within 12 inches of any system device with all appropriate covers installed. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 13 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements G. Manual Fire Alarm Stations: 1. Manual fire alarm stations shall be of the single-action, non-coded type. They shall consist of housing, fitted with a pull-down lever, which when operated, locks in position after releasing a spring-loaded contact switch to effect activation of an alarm circuit. The body of the manual station shall be permanently attached to the back plate assembly. 2. Resetting the manual fire alarm stations after operation shall require the use of a key. Manual stations, which use a screwdriver or Allen wrench for reset, are not acceptable. 3. Each manual fire alarm station shall be monitored individually, via either an integral, addressable element or an addressable monitor module. 4. Manual fire alarm stations shall be semi-flush mounted in finished areas or surface mounted in unfinished areas, using appropriate Simplex back boxes and mounting hardware, on permanent walls or columns, 48" from the finish floor to the top of the operating lever of the manual fire alarm station. 5. Fire alarm pull stations in psychiatric units shall be of an institutional type operable by nursing staff only with a key. 6. Manual fire alarm stations shall be mounted as to not be obstructed by the exit door, when it is open. 7. Where Required: H. a) On each floor at the entrance to each enclosed stair. b) At each exit from the building or building separation on each level. c) At each nurses station. d) As necessary throughout the building, so that travel distance to the nearest manual fire alarm station does not exceed 200 feet. Smoke-Sensing Fire Detectors: 1. Area type smoke detectors shall be installed where indicated in this standard and required by applicable codes. Smoke detectors shall be of the analog initiating device type, photoelectric, and be ceiling mounted in conformance with the requirements of NFPA 72 and accessible utilizing a standard 12’ ladder. This type of detector should not be considered for use in atria, mechanical rooms, and other inaccessible areas. Examples include: a) Storage rooms greater than 100 square feet in area b) Soiled Utility rooms 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 14 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 2. 3. I. c) Electrical rooms d) Low Voltage rooms Projected Beam type detectors shall be installed in areas not readily accessible. Examples include: a) Atria b) High Ceiling Air Sampling type detectors shall be installed in areas not readily accessible due to mechanical obstructions, or when early detection is required. Sampling tube “test” ports shall be located 60” off the finished floor. Examples include: a) Mechanical rooms b) Computer rooms Heat Sensing Detectors should be considered in locations where installation of required smoke detectors would be inappropriate because of environmental conditions. Designer shall obtain approval from authorities having jurisdiction to substitute heat detectors for required smoke detectors: 1. J. Examples include: a) Power House b) Unheated spaces c) Generator rooms Duct Smoke Detectors shall be suitable for the full range of air velocity conditions in the air-handling systems in which they are installed: 1. Detectors shall be system type, consisting of a plug-in photoelectric type detector head in a duct-mounted housing equipped with air-sampling tubes providing airflow through the detector housing or an area type head installed within the ductwork itself (low velocity apps). The detector housing shall accommodate either ionization or photoelectric-type detector heads interchangeably. Detector operating voltage shall be 24 VDC. 2. Sampling tubes, which serve a duct detector, consist of both a supply tube and an exhaust tube. The supply tube shall extend across the full width of the duct. The exhaust tube is integral with the duct detector and is a set length. The ends of the sampling tubes shall be accessible from outside the duct and shall be sealed with removable plugs (to facilitate detector testing). 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 15 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 3. Each in-duct smoke detector shall be provided with a key operated remote test station, incorporating a remote alarm LED. Test stations shall be labeled with laminated adhesive tape labels with the detector address and AHU served, handwritten labels are unacceptable. Stations shall be installed in an accessible location. In finished areas, test stations shall be installed in the ceiling. In mechanical rooms, test stations shall be installed on the wall or column at 80" A.F.F. All installation locations of test stations shall be coordinated with Beaumont Services Co. Fire Alarm Fire Suppression group personnel prior to installation. 4. Where installation conditions fall outside the parameters of the in-duct detector's listing, the design engineer shall provide alternative means of detection acceptable to the owner and the authorities having jurisdiction. 5. Duct smoke detectors serving dampers at smoke barriers and shaft walls shall be wired to the associated smoke damper via the N/C auxiliary contact of the detector. Damper shall close upon detection of smoke (See sheet FAWD-7 for details). 6. Where monitoring of damper end switches is required for specialty areas such as atrium smoke control etc. they shall be monitored by the fire alarm system. All other end switches shall be monitored by the building automation control system (refer to sheet FAWD-8 for details). 7. AHU shutdown control schemes: In-duct smoke detectors used for controlling smoke dampers shall not shut down the AHU that serves the area, AHUs are shut down from duct smoke detectors at the AHU. If the smoke damper is installed in a location where it is determined that the closing of the damper may damage the ductwork, the damper end switch shall be wired to shutdown the AHU when the damper closes. (See sheet FAWD-9 for details). 8. K. a) AHU supply and return fans are shutdown via the fire alarm control relay located at the AHU control panel. Upon detection of smoke all duct detectors located at the unit and at shaft wall penetrations shall cause the unit to shutdown. b) Exhaust fans are shutdown via the exhaust fan damper end switch(s). Upon detection of smoke all duct detectors located at shaft wall penetrations shall cause the damper to close causing the exhaust fan to shutdown via the associated damper end switch. Dampers shall not utilize an H-O-A selector switch. Sprinkler System Devices: 1. All sprinkler system devices shall be provided and installed by the fire protection contractor unless otherwise indicated. These devices include: 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 16 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements a) Water flow alarm switches. b) Alarm pressure switches. c) Pre-action system releasing panel, alarm signal, supervisory signal, and trouble signal. d) Zonecheck water flow test pump assemblies. e) Supervisory pressure switches. f) Valve supervisory switches. g) Supervisory pressure switches on dry-pipe and pre-action sprinkler systems. h) Fire pump controller supervisory contacts. 2. Design documents shall require the Fire Alarm Installation Contractor to make all terminations necessary to monitor suppression system devices including terminations between the fire pump controllers and the fire alarm system terminal interface. 3. Design documents shall require the Fire Alarm Installation Contractor to coordinate with the Sprinkler Contractor and the Owner for testing these devices. Documentation of suppression system device testing shall be a part of this contract. L. Remote Alarm LED's: 1. One remote alarm LED with test switch shall be provided for each in-duct smoke detector. 2. All initiating devices concealed within a ceiling cavity/plenum, wall cavity or by equipment shall have a remote alarm LED 3. Remote alarm LED's shall be ceiling or wall mounted directly outside the room, in the corridor, where they will be readily visible to responding personnel. Locations are subject to owner's approval. In Mechanical Rooms, locate remote alarm LED's in accessible location as coordinated with the Owner. 4. All remote alarm LED's shall be identified with laminated adhesive tape labels with the detector address. Labels shall identify the type of its associated device(s) and the device location (i.e. room no.). M. Door Control: 1. Door holders to be arranged so that when an alarm is received in a tower, all doors on the fire floor in that tower and doors separating adjacent towers shall close. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 17 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements a) Doors, magnetically held open shall be controlled via an auxiliary relay door holder circuit originating in the fire alarm control panel. All magnetic door holders shall be 24 volt DC. Use wall mounted Simplex type magnetic door holders as specified herein wherever possible. (See sheet FAWD-1 for details) b) Automatic door operators located in fire and smoke partitions shall be de-energized when a fire alarm signal is received. Operators shall be controlled via a relay, rated for continuous duty, connected to an auxiliary relay door holder circuit as described above. In addition, where required, the door hardware shall positively latch preventing the door from being blown open. Door latching shall be accomplished through a fire alarm interface with the door latching hardware power supply. (See sheet FAWD-1 for details) c) When door is located at a building separation a relay rated for continuous duty shall be installed so that the door will release upon alarm from either building. (See sheet FAWD-2 for details) 2. Rolling Shutters at fire rated barriers shall be controlled via a Simplex addressable relay module located within three feet of the door controller. The relay shall be normally off. Only the smoke detectors on either side of the opening shall be programmed to release the door, unless otherwise deemed required for a specific application. (See sheet FAWD-3 for details) 3. Accordion Fire Doors at fire rated barriers shall be controlled via a Simplex addressable relay module located within three feet of the door controller. The relay shall be normally off. Only the smoke detectors on either side of the opening shall be programmed to release the door, unless otherwise deemed required for a specific application. (See sheet FAWD-4 for details) 4. Electrically locked doors located in paths of egress shall be unlocked when a fire alarm signal is received. This is accomplished through a fire alarm interface with the Access Control Panels referred to as ACP(s). Each ACP shall be provided with a fire alarm signal for each tower that the ACP serves. The fire alarm signal shall be provided from a control relay located adjacent to the ACP. The control relay (one per tower served by the ACP) shall be used to notify the ACP when a tower served is in alarm. (See sheet FAWD-5 for details) 5. Trash and Linen Chute Doors shall be controlled via a relay, rated for continuous duty, connected to an auxiliary relay door holder circuit as described in section 2.06-M-1. (See sheet FAWD-6 for details) N. Notification Signaling System 1. Notification signaling shall be accomplished throughout the premises via one-way fire alarm voice/tone speakers and strobe lights. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 18 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 2. Operating voltage of all fire alarm voice/tone speakers shall be 70 Volt. The calculated load of each amplifier shall be based on 70% of the amplifiers maximum capacity. 3. Operating voltage of all fire alarm strobe lights shall be 24 VDC. All strobes shall be powered from the fire alarm system. The calculated load of each strobe power supply or NAC panel shall be based on 70% of the strobe power supply or NAC panel’s maximum capacity. All strobe circuits shall be designed for no more than 10% voltage drop. 4. Removal of any notification-signaling device from its associated indicating appliance circuit shall cause a trouble signal at the Fire Command Center. 5. All notification-signaling devices shall be equipped with terminal connectors. Pigtail devices are not acceptable. 6. Notification signaling devices shall be installed and tapped to produce an audible output on alarm, which is clearly intelligible and clearly audible above ambient noise levels. 7. The notification signaling system(s) shall provide one channel communication capability via the fire alarm speakers. 8. The notification signaling system shall be arranged for automatic operation, with provision for manual operation/override. Equipment shall be arranged so that notification-signaling zones can be selectively addressed, individually, or in any combination of individual zones. 9. Locate speakers and strobes for optimum audibility and visibility. 10. Audible and visual notification appliance circuits shall be dedicated to the single smoke zone they serve. A single circuit shall not serve more than one smoke zone. Design drawings shall indicate smoke zones. O. Fire Alarm Speakers: 1. 2. Fire alarm speakers shall: a) Have variable watt input taps. b) Not be located at Nurses Stations. c) Speakers shall be located at a distance away from any system microphone to prevent feedback. Speakers shall be mounted in accessible locations on permanent walls or columns. If walls and columns are not available ceiling mounting is acceptable if ceiling height is less than 15 feet. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 19 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 3. P. The one-way voice paging system is required to provide clearly audible, intelligible voice messages, with the Owner being sole judge of whether or not voice messages are "intelligible." The quantity, locations and tapping of speakers shall be adjusted as necessary to meet this requirement. Visual Signaling Devices: 1. To allow synchronization between circuits all strobes shall be synchronized using smart sync-modules. All smart sync-modules shall be located adjacent to the system DGP. 2. Installation shall be on walls or columns at a height of 80” above finished floor to the bottom of the lens. If walls and columns are not available ceiling mounting is acceptable if ceiling height is less than 15 feet. 3. Strobes shall be installed where required by code and in storage rooms that exceed 200 square feet in area. 4. Areas where strobes are not to be installed: Q. a) Patient Toilet rooms b) Operating Rooms c) Private Offices d) Treatment Rooms e) Exam Rooms Notification Signaling Sequence of Operations: 1. FIRE ALARM SYSTEM SIGNALS a) Fire Alarm - A fire alarm signal is initiated by fire alarm pull stations, smoke detectors, heat detectors, waterflow alarm switches, special gaseous systems suppression agent discharge pressure switches, alarm and pressure switch contacts of monitored pre-action releasing panels and VESDA System alarm (level 3). Fire alarms are audibly and visually annunciated at all annunciation devices and automatically initiate voice message, remote signaling and auxiliary control functions. b) Latching Supervisory - A latching supervisory signal is initiated by duct smoke detectors and in-duct smoke detectors. Latching supervisory alarms are audibly and visually annunciated at all annunciation devices. Latching Supervisory signals do not initiate automatic notification signaling but do initiate auxiliary control functions (damper closure, fan shutdown, etc.). 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 20 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 2. c) Supervisory - A supervisory signal is initiated by sprinkler valve supervisory switches, gaseous systems abort stations, low air supervisory pressure switches, supervisory contacts associated with monitored fire pump controllers, generator running, manual control switches for auxiliary functions and status annunciation contacts for devices controlled or monitored by the fire alarm system as auxiliary functions. Supervisory alarms are audibly and visually annunciated at all annunciation devices. Supervisory signals do not initiate automatic notification signaling or auxiliary control functions. d) Trouble - A trouble condition signal is initiated by the system in response to fault conditions detected in supervised circuits and/or components. Common trouble contacts of monitored gaseous suppression releasing panels, pre-action suppression releasing panels, VESDA system panel common trouble contacts, damper position abnormal signals, airflow abnormal signals, VFD abnormal signals, AHU power abnormal signals, interfaced fire alarm control panel trouble signals, generator abnormal signals, kitchen shunt trip power monitoring signals, communications power abnormal signals, accordion fire door controller abnormal signals, etc. Trouble conditions are audibly and visually annunciated at all annunciator locations, main system panels and the Security Operations Center. They do not initiate automatic notification signaling or auxiliary control functions. e) Priority 2 - A priority 2 alarm is initiated by Powerhouse Freon detection, ETO gas monitoring, H O monitoring, VESDA System (level 2 and level 3) or activation of the elevator capture system. NOTIFICATION SIGNALING SEQUENCE OF OPERATIONS Upon receipt of a fire alarm signal, the following occurs (See above for fire alarm signals): Strobes on the fire floor, two floors above and one floor below shall activate within the building of origin. Simultaneously an automatic digitized voice message identifying the zone and area of origin operates automatically and repeats three rounds throughout the hospital and then shuts off. A "March Time" pattern of chimes and strobes will remain active within the building of origin until silenced and reset. Audible and flashing visual FIRE ALARM indication followed by an automatic digitized voice message identifying the zone and area of origin operates automatically and repeats three rounds throughout the hospital. After the digitized voice message is completed a "March Time" pattern of chimes and strobes will activate on the fire floor, two floors above and one floor below, only in the tower where the initiating signal occurs. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 21 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements Upon receipt of an additional fire alarm signal, the chime tone shall silence and the digitized voice message shall repeat three rounds. The strobes shall remain on. Actuation of a manual control switch at the Main Status Command Center's notification signaling panel to the "Evacuate" position activates the strobe lights and a Chime throughout the associated notification signaling zones. No other controls or switches are necessary in order to accomplish this function; "one-switch" manual notification signaling capability is required. Actuation of a manual control switch at the Main Status Command Center's notification signaling panel to the "Voice" position activates the speakers throughout the associated notification signaling zones. If the selected notification zone is in the alarm mode, it shuts off the chime tone. Voice messages can be transmitted from the command center serving the area when the microphone key is pressed. Returning the manual key switch to the automatic position causes the chime to resume The "Signal Silence" and "System Reset" switches are located at the Voice Command Center's. Royal Oak: The North Tower Command Center, the Center Tower Fire Command Center (In addition the Hospital Network IMS in the Fire Command Center located in Center Tower is capable of silencing the complete system and or resetting the complete system), the East Tower Command Center, the South Tower Command Center, and the Northwest Tower Command Center. Troy: The Hospital Main Command Center (N.P.U.), Professional Office Building the Hospital Main Command Center (N.P.U.), Ambulatory Care Center the Hospital Main Command Center (N.P.U.) Grosse Pointe: The Hospital Main Command Center 3. Typical Magnetic Door Hold Open Devices: Upon detection of smoke by any fire alarm initiating device located within the smoke zone/compartment/building, the following shall occur: The normally closed contact within an auxiliary relay located in the fire alarm data gathering panel (DGP/NODE) opens, de-energizing the 24 volt D.C. circuit serving the magnetic door holder, and closing the door on the fire floor of origin. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 22 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 4. Typical Magnetic Door Hold Open Device located at the border between two buildings: Upon detection of smoke by any fire alarm initiating device located within the smoke zone/compartment of either building, the following shall occur: The normally closed contact within an auxiliary relay located in the fire alarm data gathering panel (DGP/NODE) opens, de-energizing the 24 volt D.C. circuit serving the magnetic door holder, via the normally openpowered closed contact in a Simplex MR-101 control relay, closing the door. A second possible sequence could occur, were the opening of the normally closed contact within the auxiliary relay located in the fire alarm data gathering panel (DGP/NODE) would de-energize the 24 volt D.C. circuit serving the Simplex MR-101 control relay's coil, opening the normal open-powered closed contact in the relay, closing the doors. Refer to typical door interface wiring diagram on drawings for additional information as it relates to this project. 5. Typical Air Handling Unit Sequence of Operation, Purge and Shutdown: Refer to unit specific sequence of operation indicated on control wiring diagram sheets. 6. Typical Pre-Action System Sequence of Operation: Refer to device specific sequence of operations. Not applicable this project. R. Firefighter's Telephones/Telephone Jacks: 1. Location of firefighter's permanent telephone stations, plug-in telephone jacks and portable handset cabinets shall be approved by the AHJ and coordinated with architectural trades. 2. Permanent firefighter's telephone stations shall be provided at the following locations: 3. a) In each fire pump controller room. b) Security Operation Center. c) Master fire command center. d) Voice command centers. Plug-in firefighter's telephone jacks (for use with portable handsets) shall be provided at the following locations: a) In each exit stair at each floor landing, inside and outside of stairwell. b) In each elevator lobby. c) In each elevator car. d) In each elevator mechanical room. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 23 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements e) 2.07 2.09 4. The firefighter's telephone system shall provide one zone for each stairwell, each elevator lobby and for each bank of elevators and shall provide individual zones for the fire pump control rooms. Phone jacks in Data Gathering Panels (intended for use while servicing/testing the system) do not require separate zones and may be connected to any zone that is convenient. 5. Controls at the VCC and Master Fire Command Center allow operator selectable, two-way voice communications to each firefighter's telephone zone. Operation of a zone select switch or switches establishes communications between the VCC and Master Fire Command Center and the selected telephone zones. 6. Each telephone station or telephone jack shall be clearly and permanently labeled to allow the caller to identify his or her location to the master fire command center by voice. 7. Firefighters' telephone jacks in elevators and elevator lobbies shall consist of a single-gang, brushed stainless steel plate containing a plug-in type telephone jack, labeled "Firefighters' Telephone" with a permanent laminated adhesive tape label. The floor and elevator lobby designation or elevator car designation shall be prominently labeled immediately adjacent to the station. 8. Firefighter's telephone jacks shall be provided with terminal strips. Pigtail devices are not acceptable. AC POWER A. 2.08 Below each data gathering panel remote from the VCC. AC power for any new fire alarm equipment shall be served from the building's designated life safety emergency electrical power circuit, UPS power is preferred, and shall meet the requirements of NFPA 72. BATTERIES/SECONDARY POWER SOURCES A. New equipment batteries shall supply operating power for a minimum duration of four (4) hours. B. Batteries shall be sized to accommodate the connected design load, plus 30% spare capacity for future loads. REMOTE DATA GATHERING PANELS (DGPs) A. DGPs shall be Simplex 4100U series. B. DGPs shall be networked. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 24 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 2.10 C. DGPs shall be capable of stand-alone degrade mode operation, initiating notification signals (chimes and strobes) in their associated notification signaling zone(s) in response to fire alarm signals. D. Failure or malfunction of a data gathering panel shall not impair operation of fire alarm system devices and functions beyond those normally monitored or controlled by the affected DGP. CONDUIT SYSTEMS A. The requirements of this section apply to all fire alarm conduits, raceways, electrical enclosures, junction boxes, pull boxes and device back boxes. B. Fire alarm system conduit shall be dedicated to the fire alarm system and shall contain no unrelated conductors. C. Aluminum conduit is prohibited. D. All fire alarm system conduits shall be of the sizes and types specified. 1. E. Conduits shall be galvanized EMT except as noted below. a) Where exposed and subject to damage rigid steel shall be used. Including within stair enclosures, below a height of seven feet above the finished floor or in other locations where they are likely to be subject to mechanical damage. b) Flexible metallic conduit shall be steel and is permissible for whips to devices only, maximum length 6 feet. c) Conduits installed in damp, wet and corrosive locations, shall be PVC coated rigid steel. 2. Conduits shall be sized according to the conductors contained therein. Cross sectional area percentage fill for fire alarm system conduits shall not exceed 40%. 3. Conduits shall be ½ inch minimum. All fire alarm conduit shall be routed and installed to minimize the potential for physical damage, mechanical or by fire, and so as not to interfere with existing building systems, facilities or equipment, and to facilitate service and minimize maintenance. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 25 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 1. All fire alarm conduits, except final flexible conduit connections to devices, shall be solidly attached to building structural members, ceiling slabs or permanent walls. Conduits and boxes shall not be attached to existing conduit, ductwork, cable trays, other ceiling equipment, drop ceiling hangers/grids or partition walls, except where necessary to connect to initiating, notification signaling or auxiliary function devices. Hanger rods shall be 1/4-inch minimum diameter threaded steel rods. 2. All fire alarm system conduits shall be routed/installed either parallel or perpendicular to building structural members. 3. All fire alarm system conduits shall be installed at a height so as not to obstruct any portion of a window, doorway, stairway or a passageway, and shall not interfere with the operation of any existing mechanical or electrical equipment. 4. All fire alarm system conduits, junction boxes, pull boxes, terminal cabinets, electrical enclosures and device back boxes shall be readily accessible for inspection, testing, service and maintenance. 5. Pull boxes shall be installed in each fire alarm system conduit at intervals not to exceed 100 feet except for signaling line circuits between data gathering panels. Pull boxes shall be 4-inch square, minimum. 6. All device back boxes, junction boxes and terminal cabinets shall be sized to accommodate the number of conductors contained therein; extension rings or extension boxes are not to be used to meet conductor capacity requirements. Extension rings may be used for flush mounting of devices as needed. F. Conduit, raceways, junction boxes, panels, electrical enclosures, relays and device back boxes shall be exposed in unfinished areas and concealed in walls, ceiling spaces, electrical shafts or closets, in finished areas, except as noted on the drawings. G. All conduit penetrations of walls, floors and ceilings shall be sealed according to the Beaumont Services Co. Fire Stopping Standard. The fire alarm Contractor shall restore the walls, floors and ceilings to their original condition, fire resistance and integrity. The fire alarm system Contractor shall be responsible for all patching and touch-up painting necessitated by the performance of his work. Removal and repair of all finished surfaces shall be coordinated with, and is subject to the approval of the Owner. H. All fire alarm system, pull boxes, junction boxes and terminal cabinets shall be colored orange prior to installation. The Contractor shall provide touch-up painting, of conduits; pull boxes, junction boxes and terminal cabinets prior to final acceptance testing. All conduit couplings shall be colored orange. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 26 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements I. 2.11 The use of surface mounted back boxes and devices shall be subject to the approval of the Owner. All surface mounted device back boxes shall be manufactured by Simplex or be made of cast metal construction, designed and sized to accommodate the device(s) mounted on them. CONDUCTORS A. The requirements of this section apply to all fire alarm system conductors. B. All fire alarm system conductors shall be: 1. Installed in conduit or enclosed raceway. 2. Sized as recommended by Simplex and in accordance with the National Electrical Code Article 760. 3. Color coded. Refer to Fire Alarm Wiring Schedule sheet FAWS-1 as well as individual device wiring diagrams for color coding requirements. 4. Installed continuous without the use of splices or wire nuts. 5. All fire alarm system wiring shall be installed with wire numbers installed on the wire at each end and at all terminations. Locate wire numbers at accessible locations such as in junction boxes, enclosures, device boxes, etc. Wire numbering scheme for all purge and control wiring shall be in accordance with J.I.C. standards. 6. All fire alarm system conductors shall be of the type(s) specified herein. 7. a) All NAC, SLC, IDC, AC power conductors, shield drain conductors and grounding conductors, shall be copper. The use of aluminum wire is prohibited. b) All SLC’s, including all addressable initiating device circuits, shall be multi-conductor jacketed twisted cable or twisted shielded per Simplex/Grinnell's recommendations. c) All non-addressable initiating device circuits, indicating appliance circuits, 24 VDC auxiliary function circuits and firefighters' telephone circuits shall be twisted pairs or twisted shielded per Simplex's recommendations. Indicating appliance circuits, initiating device circuits, signaling line circuits and firefighters' telephone circuits shall be shielded. All fire alarm conductor terminations, except splices in shield drain conductors, and including field connections to supervisory resistors, diodes, relays or other devices, shall be to numbered terminals or terminal strips and shall be readily accessible for inspection, service, testing and maintenance. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 27 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 8. 9. a) All fire alarm conductor terminations shall be within junction boxes, device back boxes, terminal cabinets, control panels or other suitable metal enclosures. b) Terminals and terminal strips shall be suitable for the size and number of conductors connected to them. c) Each conductor termination shall be uniquely numbered with durable plastic tags or uniquely identifiable by a combination of numbers and color codes. These conductor numbers shall be shown on the Contractor's record drawings (floor plans and detailed wiring diagrams) in a manner allowing ready identification of all conductor terminations. d) All terminations are subject to the approval of the Owner. All control panel wiring shall conform to the requirements of this section: a) All control panel wiring shall be fully and neatly bundled with nylon tie wraps at 3-inch intervals. Bundled wiring shall be routed parallel to terminal strips within control panels, with individual conductors turned out at 90 ° angles to their associated terminal connections. AC power conductors shall be bundled and routed separately from low voltage conductors. A minimum 2-inch separation shall be maintained between AC power conductors and low voltage conductors wherever possible. All control cabinets shall be sized to accommodate the requirements of this section. b) Control panels shall not be used as raceways. Conductors, which do not terminate within a control panel, shall not be routed through that control panel. c) In accordance with manufacturers installation requirements, power limited wiring shall be installed only within the power limited wiring section of fire alarm panels. Non-power limited wiring shall be installed only within the non-power limited wiring section of fire alarm panels. d) Conduit connections shall not interfere with area designated for battery installation in a fire alarm panel. Where recommended by Simplex/Grinnell fire alarm circuits shall be twisted and shielded as necessary to prevent electrical and/or audio crosstalk between conductors installed in common conduits. Refer to drawing FAWD14 for details. a) Metallic continuity must be maintained throughout the entire length of the cable run. 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 28 of 29 Jones Lang LaSalle @ Beaumont Hospitals, LLC. DESIGN/CONSTRUCTION STANDARDS AND GUIDELINES SECTION 28 31 00 – Fire Alarm Design Requirements 2.12 c) Yellow heat shrink tubing and an insulated crimp connector (RB44 or equivalent) shall be used on all shield splices and terminations. 10. Conductors looped around terminals are not acceptable. 11. T-tapping of fire alarm circuits is prohibited. All device back boxes, junction boxes and pull boxes shall be accessible for inspection and maintenance. Junction pull boxes shall be installed on 100-foot centers maximum. The location of all back boxes, junction boxes and pull boxes shall be noted on the record drawings. Conduit mounting will not be acceptable as box support. Boxes shall be supported independently of conduit. PANEL NAMEPLATE A. All fire alarm panels, terminal cabinets, etc. shall have an approved label located on the cover. Brady Thermal Transfer Label or equivalent. B. Labels shall be orange with black lettering. C. Labels shall be 6.5"W. X 4.25"H. with adhesive back. D. Refer to panel details contained in the appendix for specific label requirements. PART - 3 3.01 All conductors shielding shall be continuous (with splices at device terminations only) for the length of the circuit, terminated at the associated control panel only. BOX LOCATION A. 2.13 b) Appendix DRAWINGS END OF SECTION 28 31 00 Fire Alarm Design Requirements Issued 05/24/10 Revised 10/11/17 Page 29 of 29