AGENDA SANTA MARGARITA WATER DISTRICT ENGINEERING AND OPERATIONS COMMITTEE MEETING March 11, 2016 CALL TO ORDER: 8:15 a.m., Conference Room, District Office 26111 Antonio Parkway, Rancho Santa Margarita, California COMMITTEE CHAIR: Justin McCusker COMMITTEE MEMBER: Charley Wilson 1. PUBLIC FORUM Persons wishing to address the Board of Directors on matters not listed on the Agenda may do so at this time. “Request To Be Heard” forms are available at the entrance to the Conference Room. Comments are limited to three minutes, unless further time is granted by the Presiding Officer. Please submit the form to the Recording Secretary or Committee Chair prior to the beginning of the meeting. Those wishing to address the Board of Directors on any item listed on the Agenda should submit a “Request To Be Heard” form to the Recording Secretary or Committee Chair before the Presiding Officer announces that agenda item. Your name will be called to speak at that time. 2. ACTION 2.1 Consideration and Action on Construction Services for Tesoro Zone II and Zone B Water Facilities, Rough Grading and Storm Drain Improvements, C-1767C ...................................................................................................................... Page 3 RECOMMENDATION: 2.2 1) Approve Change Order No. 1 to MGE in the amount of $68,540.69 for construction services; 2) Authorize Staff to apply liquidated damages on the MGE contract due to completion delays; 3) Approve Change Order No. 1 to BEI in the amount of $107,737.50 for construction management services. Construction Support Services for Tesoro Zone II and B Water Facilities, Domestic and Reclaimed Water Reservoirs, C-1767E ............................................... Page 7 President, Charley Wilson Vice President, Charles T. Gibson Finance Committee Chair, Justin T. McCusker Engineering Committee Chair, Saundra F. Jacobs Director, Betty Olson General Manager, Daniel R. Ferons Page 1 Engineering and Operations Committee Meeting Agenda March 11, 2016 Page 2 RECOMMENDATIONS: Authorize a Construction Management services contract to Butier Engineering Inc., in the amount of $151,160. 2.3 Consideration and Action on Chiquita Water Reclamation Plant Screw Press Installation and Grit Washer Replacement, Award of Construction Contract, C-1241T.002 and 1241T.006 ...................................................................................... Page 29 RECOMMENDATION: 2.4 Approve the award of the construction contract for $xxx,xxx to install two new screw presses, replace the existing grit washer and install a tertiary filter overflow diversion system. Consideration and Action on Construction Services for the Palmia Recycled Water Project, Contract C-1254C.1 ............................................................................ Page 35 RECOMMENDATION: Award contract to ______________ in an amount not to exceed $775,000 (estimated cost). 3. INFORMATION 3.1. Lake Mission Viejo APWTF Project Update. 3.2. Water Supply Projects Update .................................................................................... Page 38 3.3. Engineering Update. 3.4. Operations Update. ITEMS DISTRIBUTED TO THE BOARD LESS THAN 72 HOURS PRIOR TO MEETING Pursuant to Government Code section 54957.5, non-exempt public records that relate to open session agenda items and are distributed to a majority of the Board less than seventy-two (72) hours prior to the meeting will be available for public inspection in the lobby of the District’s business office located at 26111 Antonio Parkway, Rancho Santa Margarita, California 92688, during regular business hours. When practical, these public records will also be made available on the District’s Internet Web Site, accessible at http://www.smwd.com. Upon request, this agenda will be made available in appropriate alternative formats to persons with disabilities, as required by Section 202 of the Americans with Disabilities Act of 1990. Any person with a disability who requires a modification or accommodation in order to participate in a meeting should direct such request to Kelly Radvansky Secretary, Board of Directors, at (949) 459-6642 at least 48 hours before the meeting if possible. Page 2 Santa Margarita Water District MEMORANDUM TO: Board of Directors DATE: March 11, 2016 FROM: Don Bunts/Jeff McDonnell SUBJECT: Construction Services for Tesoro Zone II and Zone B Water Facilities, Rough Grading and Storm Drain Improvements, C-1767C SUMMARY Issue: The District has been implementing the mass grading and storm drain improvements associated with the Tesoro domestic and recycled water pipeline and reservoir facilities in Chiquita Canyon with its Contractor, McKenna General Engineering (MGE) since June 2015. Additional work has been identified to be included in the MGE contract. Butier Engineering, Inc., (BEI) has been performing the construction management services on behalf of the District for this project. BEI has been required to provide work outside of the original scope of work. MGE is, late in completing the project and per the contract documents is responsible for reimbursing the District for additional costs that have resulted. Recommendations: 1) Approve Change Order No. 1 to MGE in the amount of $68,540.69 for construction services; 2) Authorize Staff to apply liquidated damages on the MGE contract due to completion delays; 3) Approve Change Order No. 1 to BEI in the amount of $107,737.50 for construction management services. Fiscal Impact: Funding for these services is to be provided from the proceeds of the recently issued County of Orange Community Facilities District Bond (2015-1 Esencia - 489). Previously Related Action: In May 2015, the District awarded the construction services contract to MGE for $2,869,545.81. A construction management contract was also awarded to BEI for $203,340.00 in the same Board action. Anticipated Board Action Date: It is anticipated that this item will be brought to the entire Board for consideration on March 18, 2016. Adherence to Policy: • This project is consistent with the District’s mission o “… to collect and treat wastewater to protect the environment and public health.” o “Provide a high level of service with maximum cost effectiveness.” Page 3 Engineering and Operations Committee March 11, 2016 Page 2 “Plan for the future to guarantee a safe and sufficient water supply and wastewater reclamation service.” This project is consistent with the District’s Purchasing Policy and Procedures, Section VI. This proposed project is consistent with the District's Purchasing Policy because it: was competitively bid, was identified in the current fiscal year’s CIP, is more than $49,999 and requires Board approval (Exhibit 1, a, (1)). o • • DISCUSSION Change Order No. 1 for MGE: The extra work performed by MGE was miscellaneous in nature and covered different topics as follows: • • • Additional measures to enhance environmental compliance with District-issued permits. Modifications to the storm drain improvements, primarily the access manhole and junction structures. Additional storm water protection enhancements to better fortify against the forecasted El Nino winter. The above work items were successfully completed, and in some cases effected the Critical Path of the scheduling for which additional time is also due. Twelve adverse weather days are also recognized wherein critical path construction work could not proceed and have been considered in the proposed change order. Attached is Exhibit A which has been prepared by the Construction Manager, BEI. This exhibit includes a detailed description of all the extra work components included in this consideration and recommends a total change order cost of $68,540.69 and a time extension of 30 calendar days. This results in a revised contract completion date for MGE of January 8, 2016. Consideration of Applying Liquidated Damages to MGE MGE has not performed the work in accordance with the contract. The following is a partial list of items identified as being contributing factors to MGE not meeting the Contract time by MGE. These items have been observed and documented by BEI and staff during the course of construction: • • • Misspent significant time on the front end of the project. Replaced project manager twice during project. Never provided a full time project manager per the contract documents. Page 4 Engineering and Operations Committee March 11, 2016 Page 3 • • • • • • • Displayed minimal concern in meeting the District’s required time schedule. Made minimal efforts to recover lost time. Has not demonstrated expertise or compliance in either short term, or long term scheduling. Rework, and inefficiency of construction sequencing due to poor scheduling. o Handling large quantities of dirt several times instead of once. Did not submit progress payments, cost proposals, and other required correspondence in a timely manner. Did not submit progress payments, cost proposals, and other required correspondence with proper content and in a format sufficient for evaluation. Caused extra work and costs to other entities having an interest in the project such as Rancho Mission Viejo and GMU Geotechnical. Unfortunately, most of the above deficiencies by MGE have continued regardless of numerous attempts by BEI and District staff to bring MGE into compliance. The Special Provisions of the Contract Documents state that the Contractor shall be assessed liquidated damages in the amount of $1,500 per calendar day for each consecutive calendar day in excess of the time specified for completion of the Work. The intent of this is to reimburse the District for the damages it incurs resulting from the Contractor failing to complete the project within the time specified. The most direct realization of such damages is evident in the increased costs of construction management services. The current Contract completion date is January 8, 2016. Construction work remains ongoing as of the date of this report (16FEB16). As there are a few more appropriate extra work items that still need to be submitted by MGE, and subsequently reviewed by BEI and the District, there may be additional time extension that is due MGE. It is anticipated that such potential extension of time will not eliminate considerations of liquidated damages. Upon realization of the actual and applicable timetables, the District shall withhold liquidated damages from the Contractor from future progress payments. Applying the daily rate as specified, this produces a monthly rate of $45,000 and a total anticipated assessment of approximately $62,500. Change Order No. 1 for BEI The Construction Manger’s (CM) work and timetable is almost entirely dependent on the work quality and schedule of the Contractor. The CM’s main responsibility is to ensure that the Contractor performs work that is in general concurrence with the Contract Documents. This is primarily accomplished through monitoring the Contractor’s schedule, managing the correspondence, inspecting the actual construction work, and record keeping for all of the foregoing. When the Contractor does not perform its functions well, it creates additional work required for the CM. When the Contractor does not finish on required timetables, it directly extends the time exposure required by the CM. In the case of this specific project, both of these items have occurred. BEI has been instrumental in providing the necessary oversight Page 5 Engineering and Operations Committee March 11, 2016 Page 4 and proactive measures to ensure the District is adhering to the contractual requirements. This will be of significant benefit should additional measures be required to close out the contract with MGE. Please see attached Exhibit B in which BEI summarizes its assessment of the causes for additional CM services, provides an accounting of costs to date, and an estimate of the costs remaining. This supports a change order request of $107,737.50. Although it is estimated that MGE should be able to complete its work by the end of February 2016, the proposed budget has been provided for an additional two weeks of CM effort to mid-March in the event it becomes necessary. FUNDING Funding for these services is to be provided from the proceeds of the recently issued County of Orange Community Facilities District Bond (2015-1 Esencia - 489). The project code for these considerations is C00BQ3. McKenna General Engineering, Inc., Contract Summary Description Original Contact Amount Change Order No. 1 Revised Contract Amount Cost $2,869,545.81 $68,540.69 $2,938,086.50 % Increase 2.39% Butier Engineering, Inc., Contract Summary Description Original Contact Amount Change Order No. 1 Revised Contract Amount Cost $203,340.00 $107,737.50 $311,077.50 % Increase 52.98% Page 6 Santa Margarita Water District MEMORANDUM TO: Board of Directors DATE: March 11, 2016 FROM: Don Bunts SUBJECT: Construction Support Services for Tesoro Zone II and B Water Facilities, Domestic and Reclaimed Water Reservoirs, C-1767E SUMMARY Issue: The District has awarded the Construction Contract to perform the Reservoir improvements for the Tesoro Domestic and Recycled Water facilities in Chiquita Canyon. The prerequisite Mass Grading work is substantially complete and the new Pipeline project has been initiated. Each of these three projects are being constructed to support development of the Esencia planned community (also referred to as Ranch Plan Planning Area 2). Construction Management services have been enlisted by the District for the Mass Grading and Pipeline projects. Additional Construction Management support services are needed to facilitate the Reservoir project. Recommendations: Authorize a Construction Management services contract to Butier Engineering Inc., in the amount of $151,160. Fiscal Impact: Funding for these services is to be provided from the proceeds of the recently issued County of Orange Community Facilities District Bond (2015-1 Esencia - 489). Previously Related Action: In January, 2016, the District authorized a construction management contract to BEI for the Tesoro Pipelines project in the amount of $322,136. The Board was also advised of Staff’s recommendation that such a contract would be appropriate for consideration for the Reservoirs project. Anticipated Board Action Date: It is anticipated that this item will be brought to the entire Board for consideration on April 6, 2016. Adherence to Policy: • This project is consistent with the District’s mission o “… to collect and treat wastewater to protect the environment and public health.” o “Provide a high level of service with maximum cost effectiveness.” o “Plan for the future to guarantee a safe and sufficient water supply and wastewater reclamation service.” Page 7 Board of Directors March 11, 2016 Page 2 • • This project is consistent with the District’s Purchasing Policy and Procedures, Section VI. This proposed project is consistent with the District's Purchasing Policy because it: was competitively bid, was identified in the current fiscal year’s CIP, is more than $49,999 and requires Board approval (Exhibit 1, a, (1)). DISCUSSION Butier Engineering (BEI) is currently providing construction management services for the Mass Grading project, and also the Pipeline project. This additional assistance has proved beneficial in enabling the District to cover and manage more projects that are on concurrent and overlapping schedules. Given the anticipated number of District CIP projects over the next two years, third party construction management assistance for the Tesoro Reservoirs project will continue to allow the District to maintain schedules and internal production rates. As BEI is successfully managing the daily activities of the Mass Grading and Pipeline projects, and has developed and maintained the key relationships with our project partners and consultants associated with the overall Tesoro Water Facilities projects, it is logical that the same team continues with the additional construction management services. This eliminates the learning curve associated with the overall project and with the various individual entities that comprise the project team. BEI has agreed to maintain its same billing rate structure for this project which includes values that were more competitive than the other construction management firms with whom they competed for the original Mass Grading project. There is also added efficiency to the District in that the Mass Grading and Pipeline projects have overlapped by approximately eight weeks, and that the Reservoir and Pipeline projects are slated to be on almost identical schedules. This will enable the labor to be used concurrently and more efficiently for the group of projects, resulting in less overall costs for this service. Please find attached Exhibit A which provides the detailed proposal from BEI. FUNDING Funding for these services is to be provided from the proceeds of the recently issued County of Orange Community Facilities District Bond (2015-1 Esencia - 489). Project Codes BQ2, and B99 have been established to track construction expenses for the Domestic and Reclaimed Water Reservoirs, respectively. The table below provides a funding breakdown for the proposed approval of additional services. Page 8 Board of Directors March 11, 2016 Page 3 Tesoro Reservoirs Construction Management Services Butier Engineering, Inc. Tesoro Zone II 3 MG Res. Project Code C00BQ2 Tesoro Zone B 2 MG Res C00B99 Total Amount $75,580.00 $75,580.00 $151,160.00 Page 9 EXHIBIT A 1. EXECUTIVE SUMMARY LETTER March 1, 2016 Jeff McDonnell, P.E. Santa Margarita Water District 26111 Antonio Parkway Rancho Santa Margarita, CA 92688 Subject: Proposal to Provide Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project, Project No. C-1767E Dear Mr. McDonnell: Butier Engineering, Inc. is pleased to present one original and two (2) copies of its Proposal and Fee Schedule for the above stated subject. The Butier Team offers several distinguishing qualifications to Santa Margarita Water District (District). To address the demands of the Tesoro Reservoirs Project, we have assembled a team that has provided services on recent similar projects in Southern California. Our team provides several distinct features: Reservoir Experience Butier has unmatched regional experience in providing construction management, inspection, and contract administration services for numerous reservoirs that range in size from 1.25 MG to 21.5 MG. Please find a partial list of projects below and more detailed descriptions in Section 3, Project Experience. Rawlings Reservoir Repair and Replacement (City of Tustin)—Two 3.0 MG prestressed concrete reservoirs. Construction required 150,000 CY of grading and extensive temporary shoring constructed during the excavation phase. Nohl Canyon Water Storage Tank (City of Anaheim)—10 MG prestressed concrete reservoir. 500,000 CY of earth was reshaped into the basin where the water storage tank would eventually be constructed. 930 Zone Recycled Water Reservoir (Inland Empire Utilities Agency)—5.0 MG steel recycled water reservoir. Site grading included excavation, fill and disposal. Lakeview and Hidden Hills Reservoirs (Yorba Linda Water District)—8.0 MG cast-in-place concrete reservoir (Lakeview) and 2.0 MG reinforced concrete reservoir (Hidden Hills). Reconstruction of Overmyer Reservoir (City of Huntington Beach)—21.5 MG partially-buried w/vertical concrete walls and hopper bottom. Professional Relationship with SMWD and Rancho Mission Viejo Staff The proposed Butier team is a known entity to both District and RMV Engineering staff. Eric Weber, P.E., Resident Engineer and Casey Lack, Field CM/Inspector are currently providing identical services to the District for the Tesoro Rough Grading and Storm Drain Improvements Project and the Tesoro Water Facilities Zone II DW and Zone B RW Transmission Mains and Coto de Caza Trunk Sewer Relocation Project. In addition, members of our staff have a long standing professional relationship with Mr. Yates from Rancho Mission Viejo and his professional colleagues. Key Butier staff members have access to the Executive leadership of RMV. Coordination with Ranch staff is critical to delivering the project on schedule. Team Experience Our firm and proposed personnel demonstrate exceptional experience performing on projects of similar complexity and scope. We have comprehensive experience addressing key challenges that will be present in the Tesoro Reservoirs Project. Casey Lack, our proposed Field CM, has completed numerous steel and concrete reservoirs ranging in size from 2.6 MG to 8.0 MG. A partial project list is presented in his full résumé. Mr. Eric Weber provides SMWD with an experienced Resident Engineer to support Mr. Lack in the field. In addition, Butier personnel possess both QSP and QSD certifications to ensure SMWD and the contractor meet all required SWPPP requirements. 17782 E. 17th Street, Suite 107 Tustin, California 92780 Page 10 Tel: (714) 832-7222 Fax: (714) 832-7211 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E Unique Team Features Document Control System: Butier has migrated to a cloud-based document control system. Box.com offers a file architecture that provides controlled access for multiple project stakeholders to the entire project record. We have designed a document control program that takes our ability to communicate down to the smart phone level. This allows us to quickly and seamlessly distribute and aggregate project information. The project record is available to our field staff at the tablet level. This eliminates trips to the field office permitting the resource to remain on site for the full working day. Butier is currently using Box.com on projects ranging in size from $1.5 to $650 million. Extensive Experience in the Analysis and Defense of Contractor Claims—Butier’s senior staff has been responsible for the administration and defense of complex construction claims. Our project experience gives us a specific case history that aligns with the Tesoro Reservoirs project. Cost Control/Market Knowledge—The Butier team will provide unmatched cost control and estimating services. The firm’s strong relationship with the Southern California construction community allows us to provide market price cost estimates. We also have the ability to survey local contractors on the current bidding environment. Extensive Experience Working on Environmentally-Sensitive, Schedule-Driven projects—We have successfully completed projects constructed under nearly identical field conditions. Our firm has the depth of resources necessary to meet all of the potential construction issues presented by the Tesoro Reservoirs project. The construction management team will be managed out of Butier’s corporate office located at 17782 E. 17th Street, Suite 107, Tustin, CA. We appreciate the opportunity to meet the District’s project challenges with our most experienced personnel, and are confident that we have assembled a team that will serve the best interests of all project participants. If you have any questions regarding our proposal, please direct them to me for clarification at (714) 832-7222. Respectfully Yours, BUTIER Construction Managers, Consulting Engineers Mark M. Butier, Jr. Vice President/CFO 17782 E. 17th Street, Suite 107 Tustin, California Page 11 92780 Tel: (714) 832-7222 Fax: (714) 832-7211 2. SCOPE OF WORK Project Understanding The Butier Team is proposing to provide third-party construction management services to Santa Margarita Water District (District) for the Zone II and Zone B Reservoirs Project, which is the third phase of the Tesoro Zone II and B Water Facilities Program. The Butier Team is successfully providing identical services for the first and second phases of the program, which consists of the rough grading and storm drain project and the domestic water (DW) and recycled water (RW) transmission mains/pipelines project. The three related projects are located in an unincorporated area of Orange County (property owned by Rancho Mission Viejo) located two miles north of the Chiquita Water Reclamation Plant (CWRP) and within Chiquita Canyon. The Reservoirs will provide operational and emergency water supply to a portion of the Esencia Village planned community (Planning Area 2). The scope of work for the Zone II and Zone B Reservoirs includes the following: Zone II Domestic Water (DW) Storage Reservoir— The above ground 3.0 MG steel DW storage reservoir will be constructed to provide one day of peak demand and additional storage for fire flow requirements. The DW reservoir will serve the Zone II system. Supply to the Zone II tank will be delivered by gravity from the District’s South County Pipeline. Zone B Recycled Water (RW) Storage Tank—The 2.0 MG RW steel storage tank will be constructed 50 feet away from the Zone II DW tank. RW produced at the CWRP will be pumped from the existing Zone A system and stored to meet the peak daily irrigation demands in the upper elevation areas of the Esencia Village planned community. General Site Improvements—Installation of on-site steel piping sections, storm drain pipeline, four photovoltaic (solar) systems; and native habitat restoration on five (5) acres of sloped land. The District’s Board of Directors awarded a construction contract to Paso Robles Tank, Inc. on February 19, 2016, in the amount of $4,830,000 for construction of the reservoirs. The construction period will consist of 270 calendar days with an estimated completion date of September 2016. Project Approach/Scope of Work Please find below our Team’s plan to accomplish the work described in the RFP. Project Management A. Kick-Off Meeting The Butier Team will facilitate a “kick-off” meeting with the District to discuss the scope of work and parameters of the Project. The Resident Engineer (RE) will prepare and distribute a draft agenda in advance of the meeting for review and comment by the District. Specific Project goals will be identified and a strategy to accomplish these goals will be developed during the meeting. These goals will be memorialized into the project communications plan and distributed to all project stakeholders. The RE will prepare and distribute meeting minutes within two (2) working days of the meeting. The minutes will include action items and assign the project team members that are responsible for completing each item. 1. Construction Administration A. Contract Administration 1. Administration: The Resident Engineer will administer the construction contract and provide technical Field Management support to District staff to facilitate completion of the project. The Butier Team will become familiar with the District’s processes, procedures and objectives to provide services and assistance as directed by District staff. The Butier Team will work under the direction of the District Project Manager and develop and maintain open lines of communication and cooperation between other consultants, the contractor and District staff. SCOPE OF WORK Page 12 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E 2. Request for Information: The Butier Team will provide for timely, thorough, clear, effective and responsible communications to Requests for Information (RFIs), submittals, and other miscellaneous correspondence. The Field Construction Manager (FCM) will receive, log, and tract RFIs and will provide a technical review to determine if the issue is addressed adequately. The FCM will respond where the RFI can be addressed in the contract documents. All responses will be monitored with suspense action dates and follow-up procedures implemented to ensure timely action by all parties to project issues including input from District staff. Processing procedures will include obtaining a response to Contractor RFIs within the contract specified time frame. The RE will supply the District’s Project Manager its interpretation of the Request for Change, cost and schedule impact, and/or justification for denial or recommendation to execute a change. 3. QA/QC: The FCM will manage the Contractor's Quality Assurance/Quality Control. The Butier Team will maintain quality control on all work performed by the Contractor and subcontractors by implementing Quality Control Procedures that include the following: assigning experienced, qualified project personnel; implementing regular checking procedures and conducting technical reviews, if applicable resource-loaded schedules are the basis for evaluating performance and identifying if potential problems will occur. Second, variance identification / analysis to initiate recovery when problems occur. The primary resource loading for these evaluations include cost (dollars); man-hours (by craft); quantity of work (cubic yards, linear feet, etc.); and construction equipment listing. 4. Interaction with Agencies/ Stakeholders: The Butier Team will be responsible for coordinating and maintaining on-going interaction with appropriate agencies, utilities and District staff to ensure successful project completion. 5. Substitution Requests: The Resident Engineer will evaluate requests for material and equipment substitutions and changes based on compliance with contract specifications and taking into account the impacts to cost and schedule. Final authority on substitution requests will be the Design Engineer. 6. Resource Loading: The FCM and RE will monitor the contractor's resource loading and provide advice on corrective actions needed to maintain the schedule. 7. Submittal Review/Logging: Butier will establish a computerized systematic tracking procedure for timely submittal review and processing of shop drawings. Submittal tracking will be introduced into the document control system and status of submittals will be known at all times. This system will be coordinated with the Contractor per contract document requirements. The FCM will provide limited reviews as shop drawings are received during the construction phase and provide recommendations and review comments supplemented by District staff. The FCM will ensure that the Contractor’s submittal schedule is updated weekly and reviewed at weekly progress meetings. The RE will prepare a list of shop drawings that will be required of the Contractor and, in conjunction with the Contractor, attempt to review the submittals consistent with the critical path requirements. Exception reports identifying critical shop drawings either not submitted in a timely fashion or not obtaining acceptance or approval will be identified and problem submittals discussed for necessary action to accelerate approval process for non-conforming submittals. 8. Project Meetings: The Butier Team will conduct weekly job site progress meetings involving the project team and maintain action items, minutes of said meetings, and compliance with the contract provisions. Each meeting will cover site safety, progress, job problems, and any actions requiring clarification of design intent, ambiguities in contract documents, and other key issues. The Resident Engineer will maintain and distribute meeting minutes within two (2) working days. B. Document Control/Tracking The Butier Team will be responsible for document tracking and management, maintaining a current set of as-built drawings and specifications, and document SCOPE OF WORK Page 13 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E maintenance. The Team will utilize a filing system that complies with District Standards. Butier utilizes Box.com as an online, virtual file server. Box provides the project team with the ability to store all documents, spreadsheets, presentations, images, and video files within a specific project folder. The folders are organized according to the project preferences into sub-folders such as standard forms, meeting minutes, schedule information, cost information, etc. The Field Construction Manager can set permissions for the folder at any time in order to invite other team members to view, edit or upload files. As files are uploaded, downloaded, or edited, team members are notified through the Updates tab and email. Instead of sending an email, team members can also post feedback, requests, and project updates in the project’s shared online workspace. Box’s integrated file view feature lets team members view file formats without downloading or worrying about whether they have the right application to view the file. C. Controls and CPM Scheduling Butier’s Resident Engineer will provide comprehensive project scheduling and control expertise as follows: 1. Baseline Schedule Review: The RE and Senior Scheduler will review, analyze and comment on the Contractor’s baseline and project schedule critical path, and logic review. They will ensure that the schedule meets all requirements of the contract documents. 2. Progress Schedule Review: The FCM and RE will ensure that a two-week look-ahead schedule is developed in coordination with the Contractor and provided bi-weekly at progress meetings. The RE and Senior Scheduler will evaluate and monitor the construction schedule and progress for the overall project and will update the schedule to reflect actual progress and changes. Slippage of any contract activities on the critical path, as well as time sequence problems, will be identified early so that the construction management team may take corrective action, if possible. The Contractor should be required to re-evaluate the logic of his original schedule and resubmit revised planning should the original plan be ineffective or not followed. The RE will notify the District and Contractor when actual progress is behind. status of the project costs and budget throughout the project. The Butier Team utilizes Primavera P6 Professional Project Management to integrate cost and schedule. The cost-loaded CPM schedule will provide the PM with the basis for cash flow projections. 4. Reporting: The Butier Team will prepare daily reports and abbreviated monthly construction progress reports. The RE will prepare a monthly progress report and submit to the District for review. The report will include a summary of the prior month’s main accomplishments and current construction activities; overall Contractor’s conformance to contract schedule and quality requirements; identification of key problems, action items, and issues along with recommendation for solutions. 5. Progress Payment Review: The RE will receive, check, and verify all Contractor monthly progress payment requests and other project-related invoices based upon the cost-loaded schedule. The progress payment worksheet will be based on an approved schedule of values. Progress pay requests will be checked against the approved schedule of assigned values and actual in-place quantities verified at the end of the pay period. 6. Contract Extensions: The RE will review, analyze, and make recommendations on contractor time extensions/requests. All extensions must be supported by critical path impacts on the approved baseline schedule. All delays, regardless of source, will be documented as to the nature and responsibility and an analysis will be made of its effect on the project’s progress, including the effects of all authorized change orders. Following this procedure will assist the District in claims evaluation for recommendations of meritorious or non-meritorious Contractor claims. 7. Coordination of District Consultants: The FCM will coordinate with District consultants that are retained under separate contracts, including the Design Engineer, Geotechnical Consultant, and Biological and Cultural Resources Consultants. 8. Project Notice Coordination: The RE will receive and review project notices and submit to the District with appropriate recommendations. 3. Cost and Budget: The RE will establish a cost control system for monitoring and updating the SCOPE OF WORK Page 14 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E 9. Prevailing Wage Compliance: The Butier Team will verify that the Contractor is complying with applicable prevailing wage requirements. D. Change Order and Claims Management 1. Document Management: The FCM and RE will minimize the potential impact of claims through prompt and equitable resolution with minimal disruption to the on-going construction effort. The primary means of claims management is the prompt processing of change orders. Change orders must be fairly reviewed against the contract documents for validity. When deemed valid, reasonable and equitable adjustments in time and money are to be provided. If the District and the Contractor disagree over the contractual merit of a change order, a claim may arise. 2. Change Order Review: The Butier Team will review the claim documentation in detail and compile complete records to begin the evaluation. After receipt of a written claim, the RE will prepare a written acknowledgement of receipt of the claim. This correspondence clarifies the status of the request for all parties to minimize misunderstandings about the issues at depth. To supplement the technical and contractual evaluation of the claim, the RE will work closely with District staff to assess the risk of exposure and to determine an appropriate response to the claim. 3. Negotiate and Resolve Claims: The evaluation results and recommendations will be forwarded to the District's Project Manager. The recommendation may suggest a negotiated settlement (in which case a settlement strategy would need to be established) or may confirm the original results of the change order evaluation, in which case the claim would be denied and the dispute acknowledged. E. Safety and Security Monitoring The Contractor is solely responsible for safety. It is the responsibility of the Butier Team to monitor, approve safety protocols, and promote a safe overall environment for all workers and visitors to the site. 1. Safety: Butier will provide all necessary personal protective equipment (PPE) and follow a safety plan for the CM Team. Safety shall comply with all Federal, State and locally accepted safety regulations and measures. 2. Job Site Security Verification: Routinely check job site security and measures taken to protect the public from hazards. 2. Inspection Butier will provide comprehensive on-site inspection services by qualified inspectors as necessary to confirm that project is being constructed according to the plans and specifications. All inspectors have appropriate technical certifications in the designated field of expertise in which inspection services are being performed. All certifications have been provided under the key personnel’s résumés in Section 4, Key Personnel. A. Daily and Weekly Documentation The required inspection disciplines will provide daily and weekly inspection reports of material installations and deficiencies noted by qualified inspection personnel with follow-up procedures recommended for ensuring that corrections are made for nonconforming work necessary to comply with contract document requirements. The reports will be linked to both still and video graphic logs to highlight critical construction activity. In addition, FCM/Inspector will be responsible for the following: • Participating in weekly construction meetings. • Reviewing Contractor’s two week “look ahead” schedules and coordinate inspection staffing needs with the RE. • Review Contractor’s payment request with RE for accuracy • Review Contractor’s record drawings prior to monthly progress payment. Prepare written response giving general indication of missing items to be completed by Contractor. • Discuss responses to RFIs with the RE as required and coordinate the replies to the Contractor. • Assist the RE in the review of the submittals. • Provide documentation of construction activities, duration of activities, manpower and equipment allocation. SCOPE OF WORK Page 15 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E • Prepare and submit to the District daily inspection reports, documenting construction activities including the date, day of week, and weather conditions; hours of work; personnel on site; time periods of equipment being used; idle or inoperable equipment; details of each activity; difficulties encountered; controversial matters/disputes; deficiencies and violations; instructions issued to the contractor; safety concerns; major material and equipment deliveries to the site; names of visitors to the site; and delays and extra work. Inspection reports will be submitted to the District on a weekly basis. 1. Site Final Walk-Through: Coordinate and conduct a site final walk-through to verify completion of contract and all related items of work within 7 days of substantial completion. • Provide non-conformance reports. 5. Final Reporting: The RE will prepare and submit a final comprehensive executive summary report to the District within 7 calendar days of final completion. The report will include a complete overview of the contract, Contractor’s performance, accomplishments, a comparison of preliminary and final costs, cash flows, schedules, and recommendations for alleviating design, construction management, and construction problems on the project. • Provide weekly photographic/digital records of the project during construction. Log construction digital photographs on a daily basis. A digital photographic library will be maintained of significant construction activities. The photographs will be labeled with the date, location, and narrative information. Additional digital photographs will be taken to document differing site conditions, change order and claim items, and any special or unique conditions as they arise. The photographic library will be turned over to the District at the completion of the construction contract. 3. Surveying Butier has retained Northstar Surveys, Inc. to provide professional surveying services, if required. Richard E. Freese, P.L.S. will perform as the Principal Surveyor. Northstar’s survey crews are union affiliated, experienced in design and construction activities, and are equipped with the latest in Trimble GPS rovers, robotic total stations, and digital levels. Northstar is intimately familiar with the project site, having performed survey and design management for the Rancho Mission Viejo Company for a master community development and survey and design support for the Ortega Highway Phase 2 construction project. 2. Site Punch List: Develop site punch list and verify completion and obtain final documentation and releases within 7 days of substantial completion. 3. Record Drawing Review and Corrections: Verify and deliver contractor as-built marked up drawings to the District for record drawing preparation. 4. Permitting: Monitor permit and agency sign-offs. 6. Documentation Turnover: The Butier Team will furnish all original project documents and final project reports to the District within 14 calendar days of final completion. Project documents will be delivered in form and fashion acceptable to the District. The electronic files will be provided on flash drive or DVDs and will be labeled with the project name. 7. Warranty Coordination: The Butier Team will prepare a list of warranty items, warranty period, and warranty repair procedures, and turn over to the District Project Manager. 8. Demobilization: The FCM will demobilize the CM staff and facilities in accordance with the agreed upon plan. 4. Construction Closeout The Butier Team will close out construction and oversee demobilization at each site. The Site Closeout tasks will include the following: SCOPE OF WORK Page 16 3. PROJECT EXPERIENCE Butier and its team members are uniquely qualified to provide Construction Management and Inspection Services to Santa Margarita Water District (District) for the Zone II and Zone B Reservoirs Project. Butier’s 40-year history demonstrates our focus on water and wastewater infrastructure. This focused approach has enabled us to independently manage over $1 billion of public infrastructure projects. At the field team level, the key members bring construction management, inspection, and contract administration experience for numerous projects of similar size and complexity. Butier has successfully performed construction management and inspection services for the District’s Tesoro Zone II and B Water Facilities, Rough Grading and Storm Drain Improvements Project (C-1767C) and Domestic Water and Reclaimed Water Transmission Main and Coto de Caza Trunk Sewer Relocation Project (C1767D. The proposed Butier Team has developed and maintained key relationships with the District’s project stakeholders and consultants on the Tesoro Water Facilities projects, including Rancho Mission Viejo (property owner), Michael Baker International, Inc. (Engineer of Record), McKenna General Engineering, Inc. (Grading Contractor), CCL Construction, Inc. (DW and RW Pipeline Contractor), GMU Geotechnical, Inc. (Geotechnical Consultant), and ARMC (Archeological and Paleontological Consultant). Reservoir Experience Butier has unmatched regional experience in providing construction management, inspection, and contract administration services for numerous reservoirs that range in size from 1.25 MG to 21.5 MG. Please find a partial list of projects below and more detailed descriptions on the following pages. Nohl Canyon Water Storage Tank (City of Anaheim)— 10 MG prestressed concrete reservoir. 500,000 CY of earth was reshaped into the basin where the water storage tank would eventually be constructed. 930 Zone Recycled Water Reservoir (Inland Empire Utilities Agency)—5.0 MG steel recycled water reservoir. Site grading included excavation, fill and disposal. Otay Water Treatment Plant (City of San Diego)—Two 6.5 MG prestressed concrete reservoirs. Carlsbad 50 MGD Desalination Treatment Plant (Poseidon Water)—2.5 MG cast-in-place reinforced concrete reservoir. Lakeview Reservoir (Yorba Linda Water District)— Demolition and removal of two existing 2.0 MG welded steel tanks and construction of a new 8.0 MG cast-inplace concrete reservoir. Hidden Hills Reservoir (Yorba Linda Water District)— 2.0 MG, dual-bay hopper, buried reinforced concrete reservoir. Also included upgrades to existing booster pump station, piping, and associated inlet/outlet, overflows and drain structures. West Basin Water Recycling Facility Phase IV Design/Build Expansion (West Basin Municipal Water District)—5.0 MG Prestressed concrete reservoir. Design/Build of Springdale Reservoir (City of Huntington Beach)—9.0 MG cast-in-place reinforced concrete reservoir. Reconstruction of Overmyer Reservoir (City of Huntington Beach)—21.5 MG partially-buried w/vertical concrete walls and hopper bottom. San Joaquin Hills Reservoir Conversion (Irvine Ranch Water District)—3,036 AF recycled water reservoir. Rawlings Reservoir Repair and Replacement (City of Tustin)—Two 3.0 MG prestressed concrete reservoirs. Construction required 150,000 CY of grading and extensive temporary shoring constructed during the excavation phase. PROJECT EXPERIENCE Page 17 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E PROJECT EXPERIENCE Tesoro Zone II and B Water Facilities, Rough Grading and Storm Drain Improvements, C-1767C OWNER Santa Margarita Water District 26111 Antonio Parkway Rancho Santa Margarita, CA 92688 Butier Engineering, Inc. (Butier) is providing construction management and inspection services for the Tesoro Zone II and B Water Facilities project, which will provide operational and emergency water supply to a portion of the Esencia Village planned community (Planning Area 2). The project site is located in Rancho Mission Viejo (an unincorporated area of Orange County) located northeast of the City of San Juan Capistrano and two miles north of the Chiquita Water Reclamation Plant within Chiquita Canyon. The Zone II and B Water Facilities project consists of three separate construction contracts. The first contract (C-1767C) consists of the rough grading of an access road and reservoir site, earthen detention basins, storm drain system installation, habitat restoration, and miscellaneous surface improvements and appurtenant work. The earthwork and major drainage facilities precede all other activity, including the installation of domestic water (DW) and recycled water (RW) pipelines in several locations and a 3.0 MG steel DW storage reservoir and 2.0 MG RW steel storage tank. Butier has successfully performed construction management and inspection services for the mass grading project and has developed and maintained key relationships with the District’s project stakeholders and consultants. REFERENCE Jeff McDonnell, P.E. (949) 459-6504 jeffm@smwd.com CONSTRUCTION VALUE $2,869,545 ESTIMATED COMPLETION DATE March 2016 CONTRACTOR McKenna General Engineering, Inc. DESIGNER OF RECORD Michael Baker International, Inc. (formerly RBF Consulting) PROPOSED KEY PERSONNEL Mark Butier, Jr., Project Director Eric Weber, P.E., Resident Engineer Casey Lack, Field Construction Manager / Inspector Joseph Blum, Technical Advisor—Grading PROJECT EXPERIENCE Page 18 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E Tesoro Zone II DW and B Water Facilities, Domestic and Reclaimed Water Transmission Main and Coto de Caza Trunk Sewer Relocation (C-1767D) OWNER Santa Margarita Water District 26111 Antonio Parkway Rancho Santa Margarita, CA 92688 REFERENCE Jeff McDonnell, P.E. (949) 459-6504 jeffm@smwd.com CONSTRUCTION VALUE $4,846,098 ESTIMATED COMPLETION DATE September 2016 CONTRACTOR CCL Construction, Inc. Butier Engineering, Inc. (Butier) is providing construction management and inspection services for the DW and RW Transmission Main and Coto de Caza Trunk Sewer Relocation (C-1767D), which is the second phase of the Zone II and B Water Facilities project. The project is located south of Tesoro High School (off Oso Parkway) approximately 0.75 miles north of the Chiquita Water Reclamation Plant (CWRP) and next to the community of Coto de Caza and the Thomas F. Riley Regional Park. Major pipeline project elements include, but are not limited to, the following: Construction of approximately 15,500 feet of 24-inch domestic water (DW) CML&C WSP and 20-inch recycled water (RW) CML&C WSP transmission mains. Relocation of approximately 730 feet of the existing Coto de Caza Trunk Sewer that lies within a District easement. Construction of a temporary sewer bypass process due to the proposed grading construction of Rancho Mission Viejo’s Los Patrones Road project. The road will extend southward from Oso Parkway and into the central Esencia development area. Steel casings for pipelines at Los Patrones Crossing. Cathodic protection improvements for the steel pipelines. Construction of a paved and unpaved access road, road safety features, storm water protection systems, and biological resources mitigation for post construction site restoration. Coordination with District Operations and other contractors. DESIGNER OF RECORD Michael Baker International, Inc. (formerly RBF Consulting) PROPOSED KEY PERSONNEL Mark Butier, Jr., Project Director Eric Weber, P.E., Resident Engineer Casey Lack, Field Construction Manager / Inspector Joseph Blum, Technical Advisor—Grading PROJECT EXPERIENCE Page 19 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E IEUA 930 Zone Recycled Water Reservoir, Chino Hills OWNER Inland Empire Utilities Agency 6075 Kimball Avenue Chino, CA 91708 REFERENCE Shaun Stone, P.E. Manager of Engineering (909) 993-1600 sstone@ieua.org Butier Engineering, Inc. provided construction management and inspection services for the construction of a 5 MG welded steel recycled water reservoir. Since the recycled water use has continued to increase throughout the Cities of Chino Hills and Ontario, additional storage was needed. Increasing the storage capacity will enable IEUA to manage the recycled water demands more effectively during the hot summer peak demand periods. The project was funded in part by the State Water Resources Control Board Southern Area State Revolving Fund Loan and Water Recycling Grant Program. Construction of the recycled water reservoir included the following: Site grading including excavation, fill and disposal 910 lineal feet of 16-foot wide access road Excavation in City of Chino Hills streets Traffic control 2,488 lineal feet of 30-inch cement mortar lined and coated steel inlet/out pipeline 542 lineal feet of 18-inch cement mortar lined and coated steel pipe drain line 326 feet of 12-inch cement mortar lined and coated drain line Installation of yard piping and valving Electrical and instrumentation Installation of two (2) 4-inch recycled water laterals Cathodic protection Saw-cutting of pavement, pavement removal, and disposal Pavement replacement including grinding, base course, and surface course installation Utility connection including an SCE service line Installation of corrosion test station CONSTRUCTION VALUE $6 million COMPLETION DATE December 19, 2012 (start) June 13, 2014 (completion) PROPOSED KEY PERSONNEL Mark Butier, Jr., Project Director Casey Harris, Project Manager PROJECT EXPERIENCE Page 20 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E Rawlings Reservoir Repair and Replacement, Tustin, CA OWNER City of Tustin Public Works Department 300 Centennial Way Tustin, CA 92780 Butier Engineering, Inc. provided construction management and administration services for the Rawlings Reservoir Repair and Replacement Project. The former reservoir was a four (4) million gallon hopper bottom reservoir located in close proximity to multi-million dollar family residences and Foothill High School. Construction consisted of replacing the former reservoir with two DYK-style reservoirs, each with a three (3) million gallon capacity. This increased capacity has allowed for more water self-sufficiency in the Tustin community. The water is being used to meet daily demands in the Tustin Water Services Area and will be available in times of emergency such as an earthquake or local fire. The construction required 150,000 CY of grading, and a tie-back retaining wall, which was constructed during the excavation phase and after demolition of the former reservoir. The tie-backs extend beyond the City’s property and into an adjacent property. The upper tie-backs were de-tensioned and abandoned in place after the concrete for the reservoir tanks cured and prior to back filling for the tanks. Project Challenges/Solutions Butier worked closely with City staff and the design consultants (Tetra Tech and Leighton) to address construction access and complex geology and temporary shoring issues in the contract documents. This joint effort led to nearly $1 million in savings: Construction Access—The City entered into an agreement with the adjacent property owner of an undeveloped land. The agreement allowed the City to utilize the property for the purpose of facilitating construction by providing an access road down to the bottom of tank elevation, as well as providing a staging and stockpiling area. This foresight facilitated construction and minimized off-site hauling. Complex Geology and Temporary Shoring Issues—The site included weathered and fractured underlying bedrock (shear zone) and groundwater. A conceptual layout of the temporary shoring was developed by the Team prior to bid. Due to a concern of potential movement, monitoring of the ground and shoring was instituted in order to anticipate potential ground movement and protect the surrounding residences. REFERENCE Douglas Stack, P.E. Director, Public Works (714) 573-3150 dstack@tustinca.org CONSTRUCTION VALUE $12.5 million COMPLETION DATE 2013 PROPOSED KEY PERSONNEL Mark Butier, Jr., Project Director Joseph Blum, Construction Manager Steve Naylor, Inspector Casey Lack, Foreman (Pacific Hydrotech) AWARDS ASCE Orange County Branch 2014 Water Project of the Year PROJECT EXPERIENCE Page 21 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E Nohl Canyon Water Storage Tank, Anaheim, CA OWNER City of Anaheim 201 S. Anaheim Blvd. Suite 601 Anaheim, CA 92805 Butier Engineering, Inc. was a subconsultant to Tetra Tech, providing construction management, field engineering, and inspection services for this $20-million water storage tank project. The project team was also responsible for providing geotechnical, soils testing, noise/vibration monitoring, pre-inspection, community relations, and surveying services. The project consisted of the construction of a single 10-million gallon buried pre-stressed concrete circular tank to replace the existing Olive Hills Reservoir site in the City of Anaheim. The Olive Hills Reservoir had been out of service since February 1999. Water storage in this area is critical to the effective and efficient management of the City’s water supply and distribution. The City had been relying on a connection to the Metropolitan Water District to serve its needs on a temporary basis. MWD requested that the City develop storage capacity of its own. Feedback from the surrounding neighborhood was critical at all stages of the project. From the beginning, the City was committed to keeping nearby neighbors informed and involved. Through careful planning and community feedback, City staff was able to propose a water storage tank small (above ground) that would add reliability to the water system, as well as improve aesthetics and slope stability around the site. The decision to construct a 10 MG reservoir versus a 20 MG reservoir drastically reduced the construction impacts to the surrounding community. The design allowed for regrading the existing slopes to a flatter grade (2:1) and is consistent with the current codes with regard to new construction. Other improvements included the installation of additional piezometers and inclinometers, appurtenant pipeline and pump station improvements, and landscaping: REFERENCE Bill Moorhead, Project Manager (714) 765-4165 BMoorhead@anaheim.net CONSTRUCTION VALUE $20 million COMPLETION DATE 2010 (148 days ahead of schedule) PROPOSED KEY PERSONNEL Mark Butier, Jr., Project Director Joseph Blum, Construction Manager AWARDS 2011 CalGEO Outstanding Project Award Project Challenges: Community Outreach/Public Relations—Nohl Canyon was a high-profile, politicallysensitive project due to the size and proximity to multi-million dollar family residences and an elementary school. The Tetra Tech/Butier CM Team provided the public with a single point of contact eliminating nuisance calls to City senior management and City Council representatives. Large Scale Grading Operations—Experience of Butier’s Resident Engineer allowed the City, contractor, and community to efficiently plan the earth moving operation. After the old reservoir was removed, 500,000 cubic yards of earth—enough to fill over 150 Olympic-sized pools—was reshaped into the basin where the water storage tank would eventually be constructed. EIR Compliance—Work was conducted under tight permit constraints. Proposed staff was very familiar with the field implementation of the EIR. Contractor Claims—Project site presented constraints that could have generated many changes. The Tetra Tech/Butier team assembled a group of professionals who have extensive experience in change and claims control. PROJECT EXPERIENCE Page 22 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E Hidden Hills Reservoir, Yorba Linda, CA OWNER Yorba Linda Water District 1717 E. Miraloma Ave. Placentia, CA 92870 REFERENCE Joe Polimino (714) 701-3104 CONSTRUCTION VALUE $5.5 million COMPLETION DATE 2010 PROPOSED KEY PERSONNEL Mark Butier Jr., Project Director CONSTRUCTION MANAGEMENT SERVICES PROVIDED Construction Management Contract Administration Inspection Services Butier Engineering, Inc. was selected to provide construction management and inspection services for construction of a 2.0 million gallon, dual-bay hopper, buried concrete reservoir and upgrades to the existing Santiago Booster Pump Station (BPS). The Hidden Hills Reservoir is located adjacent to a single-family residential development to the south and east and undeveloped Chino Hills State Park to the north. Claims Management Owner Representation Change Order Control The scope of work included construction of the following: 2.0 million gallon buried concrete reservoir, piping and associated inlet, outlet, overflows and drain structures Approximately 1,500 lineal feet of 16-inch water transmission main and 18-inch storm drain within a new access road, including grading and paving as a proposed extension of Hidden Hills Road Upgrades to an existing pump station including new electrical circuits, conduit, cabinets and telemetry controls, pump replacements and various SCADA communication devices PROJECT EXPERIENCE Page 23 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E Construction of 8.0 Million Gallon Lakeview Reservoir Yorba Linda, CA OWNER Yorba Linda Water District 1717 E. Miraloma Ave. Placentia, CA 92870 REFERENCE Joe Polimino (714) 701-3104 Butier Engineering, Inc. was selected to perform construction management and inspection services for the construction of the Lakeview Reservoir. The 8.0 million gallon buried cast-inplace concrete reservoir is currently situated within an area of on-going construction of a booster pump station and residential development in Yorba Linda, CA. The scope of work for the Lakeview Reservoir included the following: Construct retaining wall and drainage structures along the south and west property lines Construct V-Ditch along south and west property lines and Air Gap Structure No. 1, including the offsite connection to the 24-inch storm drain in Melinda Street Construct the west bay of the reservoir and a portion of the center bay, including the deep piping under the reservoir to the outlet valve and leak detection vaults Demolish and remove old booster pump station, including all piping and ancillary equipment, when existing booster pump station is no longer in service Complete construction of the center bay of the reservoir, including all remaining deep piping under the reservoir to the outlet valve and leak detection vaults Partially backfill around the new reservoir and complete construction of all inlet and outlet piping, overflow piping, and associated valve vaults linking the new reservoir to the new booster pump station Put the new reservoir into operation with the new booster pump station, on a manual basis, following completion of the following tasks: fill with water and disinfect the new reservoir; monitor leakage and seal all visible leaks; drain some portion of water from each bay to flush out remaining sediment CONSTRUCTION VALUE $10.7 million COMPLETION DATE 2009 PROPOSED KEY PERSONNEL Mark Butier Jr., Project Director CONSTRUCTION MANAGEMENT SERVICES PROVIDED Construction Management Contract Administration Inspection Services Claims Management Owner Representation Change Order Control Continue backfilling as needed and complete construction of all electrical and instrumentation facilities, test all control systems, and put the control systems into operation Demolish and remove two existing 2.0 MG welded steel tanks, including concrete foundations, connecting piping, drainage facilities, and all electrical and control wiring and conducts Complete all remaining work including remaining backfill, retaining walls, roadways, drainage facilities, and finished grading PROJECT EXPERIENCE Page 24 4. KEY PERSONNEL Introduction Butier’s Team consists of skilled project / construction managers, resident engineers, schedulers, estimators, and inspectors who have successfully managed major water infrastructure projects throughout Southern California. By having the Butier Team serve the District as a single-source of field responsibility, the project activities will be well coordinated and delivered efficiently. We propose to approach this project with a spirit of partnership. This enables us to combine the knowledge, ideas, and talents of your staff with our construction administration experience to provide exceptional results. We have successfully demonstrated this on the current Tesoro Rough Grading and Storm Drain Improvements Project and the Zone II DW and Zone B RW Transmission Mains and Coto de Caza Trunk Sewer Relocation Project. Our key personnel are available during the proposed schedule for the Tesoro Water Facilities Zone II and Zone B Reservoirs Project. Nearly 80 percent of the proposed team resides in Orange County. Given the dynamic nature of construction services, it is important that the team can accommodate changing demands without compromising quality. More importantly, our personnel are familiar with the contractors performing work in the region. We have the unique ability to inform the District of the strengths and short comings of individual contractors. Butier’s philosophy is to assemble a construction management team based on the Owner’s various technical, environmental, economic, and political needs of a specific project. Typically, a Resident Engineer and Field Inspector(s) are assigned at the field level to manage daily site activities. Project site teams work under the direction of a Project Director or Senior Construction Manager, who has access to the technical and financial resources required for successful project completion, and who works closely with the Owner’s representative. Depending on a project’s size and sophistication, project teams may be further supplemented with in-house management support and/or outside consultants to meet the project’s schedule, budget, and delivery requirements. Construction Management Personnel Biographical sketches of our construction management team are provided in the table on the following page. Detailed résumés for Butier personnel, are provided at the end of this section. Construction Management Approach & Philosophy The value of the Butier Team to Santa Margarita Water District will be in the collective experience and abilities of its individual members to provide: independent, third party project/construction management; meet the District’s cost objectives; maintain a strong working relationship with interested stakeholders; meet the environmental objectives of the project; provide flexible staffing economies and implement a proactive change and claims control process. KEY PERSONNEL Page 25 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E Member Name / Role / Location Areas of Expertise/Specialization Yrs Exp Mark Butier Jr., Project Director Butier Engineering, Inc.—Tustin, CA Client relations, contract management, staff resource management, claims mitigation, and public outreach for water/wastewater transmission, treatment & storage projects. Acted as Project Director for the ECLWRF Phase II, III, IV and V Design-Build Expansions; Mobil Refinery 3.2 MGD RO/MF Wastewater Treatment Facility; and WRD’s Leo J. Vander Lans Advanced Water Treatment Facility Expansion. 25 Eric Weber, P.E. Resident Engineer Butier Engineering, Inc.—Tustin, CA Extensive experience in overseeing and supporting construction management and design processes QA/QC programs, safety programs, budget, design/submittal review, construction schedules, and project scope of work. Currently performing as Resident Engineer for SMWD’s Tesoro Rough Grading and Storm Drain Improvements Project and the Zone II DW and Zone B RW Transmission Mains and Coto de Caza Trunk Sewer Relocation Project. 12 Christopher “Casey” Lack Field CM/Inspector Butier Engineering, Inc.—Tustin, CA Experienced in all areas of the heavy civil infrastructure. Well-versed in contract negotiations, estimating, value engineering, document preparation, building code and OSHA regulations, material purchasing, and site management. Currently performing as Field CM/Inspector for SMWD’s Tesoro Rough Grading and Storm Drain Improvements Project and the Zone II DW and Zone B RW Transmission Mains and Coto de Caza Trunk Sewer Relocation Project. 25 Casey Harris, Senior Scheduler Butier Engineering, Inc.—Tustin, CA Multi-million dollar water/wastewater treatment, pump station, reservoir, and pipeline projects. Expert CPM scheduler and proficient in Primavera Project Planner. Senior Scheduler for the Carlsbad 50 MGD Seawater Desalination Treatment Plant. Successfully managed Phase II, III, IV and V Design/Build Expansions for the ECLWRF. 35 Joseph Blum Technical Advisor—Grading Butier Engineering, Inc.—Tustin, CA Experience in the construction of heavy civil engineering projects, including earth moving, mass grading (125 million CY of soil), wetlands, channels, recharge basins, large and small diameter pipelines, reservoirs, concrete structures, and flood control facilities. He has performed as the Project Manager for the City of Tustin’s Rawlings Reservoir Replacement Project and the Tustin Legacy grading and street improvement projects. 28 Bryan Wilson, Field Engineer Butier Engineering, Inc.—Tustin, CA Specializes in providing field engineering, contract administration, construction estimating, cost review, and inspection services for pipeline, water and wastewater treatment facility projects. Estimating experience covers all aspects of building and heavy civil design and construction, including earthwork, structural, and M/E/P. 18 Bart Crawford Civil/Structural Inspector Butier Engineering, Inc.—Tustin, CA Inspection oversight of water and wastewater treatment plants, pump stations, pipelines, and reservoirs. Lead Inspector for the West Basin ECLWRF Phase IV and V Expansion projects. Pipeline encasement construction oversight experience for 144” and 66” lines. 30 Steve Naylor Civil/Structural Inspector Butier Engineering, Inc.—Tustin, CA Provides civil/structural inspection oversight for water capital improvement projects, including pump stations, water/wastewater treatment plants, pipelines, reservoirs, and wells. ICC certified in reinforced concrete with specific experience in code enforcement. Performed as a QC Inspector for WBMWD’s ECLWRF Phase IV Design-Build Expansion and currently for WBMWD’s Facility-Wide Access Improvements Project. 27 Joseph Hawes, CWI Field Inspector Butier Engineering, Inc.—Tustin, CA Managed the scheduling and daily field operations for various public works, residential, and commercial projects, including pipelines, water treatment facilities, and airports. Well versed in numerous soils, asphalt and concrete testing procedures in accordance with AASHTO, ACI, ASTM, ICC, IBC, CBC, UBC and IBC standards. ICC certified for concrete, masonry, soils, spray-applied fireproofing, and structural steel and welding. 15 Richard Freese, P.L.S. Principal Surveyor Northstar Surveys, Inc.— San Juan Capistrano, CA Experienced in the following types of land surveys: State and BLM land division projects; GPS control surveys; quality control, settlement and as-built surveys; topographic surveys for quantity and mapping; layout and control for aerial surveys; all control necessary for use in construction; and tract boundary, ALTA and property subdivisions 29 KEY PERSONNEL Page 26 Santa Margarita Water District Construction Management Services for the Tesoro Water Facilities, Zone II and Zone B Reservoirs Project No. C-1767E SANTA MARGARITA WATER DISTRICT Jeff McDonnell, P.E., Project Manager District Staff Inspector STAKEHOLDERS DISTRICT CONSULTANTS Rancho Mission Viejo U.S. Fish & Wildlife Service Regional Water Quality Control Board CA Department of Fish & Wildlife General Contractor Paso Robles Tank, Inc. Design Engineers/Consultants Michael Baker Intl (formerly RBF) GMU Geotechnical, Inc. ARMC Public Utilities PROJECT DIRECTOR Mark Butier Jr. RESIDENT ENGINEER Eric Weber, P.E. TECHNICAL ADVISORS Casey Harris, Senior Scheduler Joseph Blum, Grading FIELD CM/INSPECTOR Christopher “Casey” Lack FIELD ENGINEER Bryan Wilson FIELD INSPECTORS Butier Engineering, Inc. Bart Crawford Steve Naylor Joseph Hawes SURVEYING Northstar Surveys, Inc. Richard E. Freese, PLS Principal Surveyor KEY PERSONNEL Page 27 SECTION 5. COST PROPOSAL SMWD: CM Services for Tesoro Water Facilities, Zone II and Zone B Reservoirs Task March April May June July August Sept October Per Category Per Category Total Cost Pre-Construction Services Project Director Resident Engineer Field Construction Manager M. Butier E. Weber C. Lack $ $ $ 168.00 154.00 130.00 M. Butier E. Weber C. Lack B Wilson $ $ $ $ 168.00 154.00 130.00 140.00 M. Butier E. Weber C. Lack $ $ $ 168.00 154.00 130.00 TBD TBD TBD $ $ $ M. Butier E. Weber C. Lack 40.0 20.0 0.0 $ 40.0 20.0 $ $ 6,160.00 2,600.00 Construction Administration Services Project Director Resident Engineer Field Construction Manager Field Engineer 0.0 $ 40.0 640.0 $ 98,560.00 20.0 0.0 100.0 $ $ 14,000.00 0.0 $ 0.0 168.0 $ $ - 0.0 $ 0.0 0.0 $ $ $ $ $ 168.00 154.00 130.00 0.0 $ - 0.0 0.0 $ $ - 0.0 $ - $ $ - 0.0 0.0 $ $ - $ $ $ $ 168.00 154.00 130.00 140.00 100.0 40.0 100.0 100.0 100.0 100.0 100.0 40.0 - Inspection Project Director Resident Engineer Field Construction Manager 24.0 24.0 24.0 24.0 24.0 24.0 24.0 21,840.00 Survey Northstar Miscellaneous Material Testing 8,000.00 - Construction Closeout Project Director Resident Engineer Field Construction Manager Extended Services: Total Man-Hours Per Month Hours Combined Project Director Resident Engineer Field Construction Manager Field Engineer M. Butier E. Weber C. Lack B. Wilson 100.0 0.0 40.0 20.0 40.0 164.0 0.0 100.0 24.0 40.0 124.0 0.0 100.0 24.0 0.0 124.0 0.0 100.0 24.0 0.0 124.0 0.0 100.0 24.0 0.0 124.0 0.0 100.0 24.0 0.0 124.0 0.0 100.0 24.0 0.0 84.0 0.0 40.0 24.0 20.0 968.0 0.0 680.0 188.0 100.0 $ $ 104,720.00 $ 24,440.00 $ 14,000.00 $ 151,160.00 Page 28 MEMORANDUM TO: Engineering and Operations Board Committee DATE: March 11, 2016 FROM: Don Bunts/Tricia Butler SUBJECT: Consideration and Action on Chiquita Water Reclamation Plant Screw Press Installation and Grit Washer Replacement, Award of Construction Contract, C-1241T.002 and 1241T.006 SUMMARY Issue: The existing belt filter presses and grit washer at the Chiquita Water Reclamation Plant (WRP) have reached the end of their service life. Newer technologies are available that provide a more cost effective operation and that reduces the potential for odors emitted from the processes. An overflow weir and piping is needed to convey flow from the filter influent channel to drain to avoid flooding of equipment in the filter complex in the event of filter plugging or other abnormal operating conditions. Recommendations: Approve the award of the construction contract for $xxx,xxx to install two new screw presses, replace the existing grit washer and install a tertiary filter overflow diversion system. The final numbers will be available for discussion at the March 11, 2016 Engineering and Operations Committee meeting. Fiscal Impact: Total construction project $xxx,xxx. Previously Related Action: In mid-2015, the Board approved pre-purchase of the screw presses. In October 2015, the board approved pre-purchase of the grit washer and engineering services for electrical and structural design, as well as a bulk polymer storage tank and conveyor as long lead equipment required for the screw press installation. In November 2015, the EOC reviewed the project in anticipation of bid and award. Anticipated Board Action Date: It is anticipated that this item will be brought to the entire Board for consideration at the March 18, 2016 Board of Directors meeting. Adherence to Policy: • This project is consistent with the District’s mission o “Provide a high level of service with maximum cost effectiveness.” o “Plan for the future to guarantee a safe and sufficient water supply and wastewater reclamation service.” • This project is consistent with the District’s Purchasing Policy and Procedures Page 29 Engineering and Operations Committee March 11, 2016 Page 2 DISCUSSION The existing Belt Filter Presses (BFPs) at the CWRP were installed with the initial plant construction in 1985. The two BFPs have reached the end of their service life and are costly to maintain. Over the years the cost of disposing of the dewatered biosolids has become significantly more expensive. One of the major components of this cost is the weight of the material (sludge) that must be disposed of offsite. The weight of the sludge can be decreased by reducing the amount of water in the “cake” which can only be accomplished by increasing the efficiency of the dewatering process. Earlier in 2015, District staff evaluated options for dewatering equipment including pilot testing of equipment. Based on this evaluation, the Huber Screw Presses were recommended and approved by the Board for pre-purchase as a long lead item. Pre-purchase of a bulk polymer storage tank and dewatered sludge cake conveyor were also approved. The proposed layout of the equipment is shown in Figure 1: Figure 1 - New Screw Press Layout Page 30 Engineering and Operations Committee March 11, 2016 Page 3 The existing grit classifier/washer was installed in the original Phase 1 Chiquita Water Reclamation Plant construction in 1985 and is shown in Figure 2. A view from below is provided in Figure 3. The temporary odor curtains are shown in Figure 4. Figure 2 - Existing Grit Washer Figure 3 - Existing Grit Washer from Below Page 31 Engineering and Operations Committee March 11, 2016 Page 4 Figure 4 - Existing Grit Washer - Temporary Curtains for Odor Control Page 32 Engineering and Operations Committee March 11, 2016 Page 5 Pre-purchase of a new grit washer was approved in October 2015, and design work initiated for the installation of the grit washer. The layout of the new grit washer is shown in Figure 5. The plan view is shown in the upper portion and a section view in the lower portion of Figure 5 Figure 5 - New Grit Washer installation Page 33 Engineering and Operations Committee March 11, 2016 Page 6 Construction requirements of both the screw press and grit washer are similar. Packaging the projects together should result in more competitive bids and savings in administration of fewer contracts. Both the grit washer replacement and the screw press installation will reduce the potential for odor emissions from the Chiquita Water Reclamation Plant. The screw presses enclose the dewatering process. Newer technology grit washing equipment such as the Huber grit washer selected for this project remove organics from the grit removed. Grit stored prior to disposal is clean and dry, compared to previous stored grit with organic, odor-emitting materials. In addition to the screw press and grit washer, installation of a tertiary filter overflow drain pipe is included in this design package. The CWRP has experienced overflow from the filter basins under certain abnormal operating conditions, which inundated and damaged pumps in an adjacent pump pit. An overflow pipe in the filter influent channel is proposed to convey overflow to the ocean outfall while the filter overflow conditions are being addressed. This overflow facility will also serve future filtration units when the recycling capacity is expanded. A photo of the Filter Area is shown in Figure 6. Filters (Below Grating) Pump Pit Figure 6 - Filter Chamber District staff managed the production of design plans and specifications, and completed the civil and mechanical design work. Sub-Consultants completed the electrical and structural engineering design. General Contractors submitted bids on Thursday, March 10th. The apparent low bidder is __________ with a bid of $xxx,xxx. Construction services are proposed to be performed by District staff. A summary of all the bids is provided in the attachment to this memo. FUNDING The proposed project is part of the Phase IV Chiquita WRP Expansion, Contract No. C00E28 in the current Capital Improvement Project budget, to be funded by future bond issue #4C for Chiquita. Page 34 MEMORANDUM TO: Board of Directors DATE: March 11, 2016 FROM: Don Bunts/Karla Houlihan SUBJECT: Consideration and Action on Construction Services for the Palmia Recycled Water Project, Contract C-1254C.1 SUMMARY Issue: The District is actively seeking ways to conserve domestic water and increase the domestic water supply reliability. The Palmia neighborhood has 18 domestic meters that currently supply domestic water for irrigation of the slopes and common areas. Expansion of the existing Zone C recycled water distribution system will be constructed to allow for the retrofit of these irrigation meters to recycled water services. The savings in domestic water will be up to 70 acre-feet per year. Recommendation: Award contract to _______________________in an amount not to exceed $775,000 (estimated cost). Fiscal Impact: Funding is to be provided from Capital New Projects Reserve. Previously Related Action: The Board has directed staff to maximize the use of recycled water for irrigation purposes and to convert those areas that provide the largest benefit/cost ratio. Anticipated Board Action Date: It is anticipated that this item will be brought to the entire Board for consideration at the April 22, 2016 Board of Directors meeting. Adherence to Policy: • • This project is consistent with the District’s mission o “…to provide our customers with quality water and wastewater services -maximizing human, environmental, and financial resources -- to help guide South Orange County’s current and future water and wastewater needs.” o “Provide a high level of service with maximum cost effectiveness.” o “Plan for the future to guarantee a safe and sufficient water supply and wastewater reclamation service.” This project is consistent with the District’s Purchasing Policy and Procedures. This proposed project is consistent with the District's Purchasing Policy because it was competitively bid, was identified in the current fiscal year’s CIP, is more than $50,000 and requires Board approval. Page 35 Board of Directors March 11, 2016 Page 2 DISCUSSION: The Palmia Recycled Water Distribution System is located in the Palmia neighborhood within the City of Mission Viejo. The proposed project includes the conversion of existing domestic irrigation services to recycled water irrigation services. In order to make the conversions of the 18 accounts and allow provisions for additional irrigation account conversions within multi-family developments, the Zone C recycled water distribution system will be extended from an existing lateral line that passes through the neighborhood on Monterey and Riviera. Exhibit A provides a graphical representataion of the project area within the District’s boundaries as well as the proposed distribution system. The project is an opportunity to expand the recycled system and decrease the use of imported water supply for non-potable demands. The distribution system includes the installation of 4- and 6- inch PVC pipe along with necessary appurtenances. The location of the existing meters will remain unchanged and the existing meters will be replaced with new meters. A portion of the area has already been modified to provide the necessary recycled water notifications and recycled water markings. Any additional required notifications, markings and signs will be installed prior to providing service to ensure all irrigation systems are properly marked prior to recycled water being delivered. The contractor has been tasked with completing the construction and retrofit in phases. This will allow groups of users to be brought online as the construction of the distribution system progresses. The phasing of the conversion of irrigation accounts from domestic to recycled water will allow the customers and the District to realize the benefits of the project rather than have to wait until the construction of the entire project is complete. Six of the bidders on the District’s pre-qualified contractors list are being notified of a pre-bid meeting being held on March 24, 2016. The project bid date is April 7, 2016. The low bidder, ______________________, has successfully completed other District projects in the past and has most recently completed projects in ________________. Staff recommends award of the contract to ________________to allow the construction services process to proceed. FUNDING Construction funding for this project will be from Project Code G00CRP. Description Project Code Funding Source Palmia Recycled Water Project Total G00CRP New Project Reserves Amount $ 775,000 $ 775,000 Page 36 388 S LO OS IS AL SA N E GU VD BL MI 358 L MA 514 529 ZA 200' 400' AN TL CA 473 0 NC 547 359 355 472 Y E R ACAPULCO VI ER A E T N 357 356 MO 570 391 523 492 392 SAN TA M ARG ARIT A PKW Y CANARIA 519 M A N A R A 479 R SE 476 A R OR D N A T RE A PROMENADE P:\PROJECTS\CONVERSION PROJECTS\PALMIA CONVERSION\NON DOMESTIC RETROFIT DISTRICT METER MAP.dwg, File date: 8/18/2015 8:27 AM, Print date: 8/19/2015 10:17 AM, by: Rivas, Alex 394 RI ASTORIA CARABELLA UN 466 LEGEND & ABBREVIATIONS 393 IRRIGATION METER TO BE CONVERTED 379 IRRIGATION METER FOR FUTURE CONVERSION PROPOSED RECYCLED WATER PIPE EXISTING RECYCLED WATER PIPE 379 IRRIGATION METER IDENTIFICATION NUMBER RW RECYCLED WATER MAY 2015 PALMIA RECYCLED WATER PROJECT EXPANSION OF THE ZONE D RECYCLED WATER DISTRIBUTION SYSTEM EXHIBIT A Page 37 MEMORANDUM TO: Engineering Committee FROM: Dan Ferons SUBJECT: Water Supply Projects Update DATE: March 11, 2016 DISCUSSION The District has an adopted strategic plan goal of the 10,000 to 14,000 acre feet (AF) of alternative domestic water supply other than Metropolitan Water District of Southern California. Currently the annual domestic water demand is approximately 24,000 AF and prior to the drought declaration it was 28,000 AF. The plan is for 30 to 50% of the supply to be under direct control of the District thereby reducing reliance on imported water from Colorado River or Northern California. The current water supply projects that are in various stages of review or planning are: • • • Cadiz: 5,000 AF of firm supply with an option for an additional 10,000 AF. This is raw water delivered to the Colorado River Aqueduct for proposed wheeling through the MWD system to the District for treatment at the Diemer Filtration Plant or the Baker Treatment Plant. CEQA litigation is ongoing with the Appeals Court date set for March 23, 2016. Cadiz is working with the Bureau of Land Management to review BLM’s determination for use of the railroad right-of-way for construction of the pipeline and MWD is reviewing its proposed operation of the Colorado River Aqueduct in the future. Poseidon: OCWD is reviewing delivery options if it enters into a purchase arrangement with Poseidon Huntington Beach. One of the options is delivery of 10 MGD to south county agencies by agreement. The District is interested in potentially receiving 5,000 AF. The Coastal Commission is scheduling a hearing on the permit application, potentially in May or July. The project has also submitted to the MWD Local Resource Program for funding. OCWD has not finalized participation in the plant. San Juan Watershed: The San Juan Basin Authority is finalizing a proposed project which can be developed in phases. The project report is scheduled to be completed this month. The District is reviewing the alternatives and phasing of the various elements including stormwater recharge, urban return flows and recycled water. A schedule will be developed over the next couple of weeks for review with the Board of Directors. Page 38 Board of Directors March 11, 2015 Page 2 • Cucamonga Valley Water District: The District has been working with various agencies to develop a delivery mechanism for supplemental water during the drought per the existing agreements. The water may be delivered via the Santa Ana River during low flow conditions, for subsequent delivery via a partner agency within the basin. Part of the analysis is looking at the demand curves for the year. As we consider the various deals we can enter into, the low flow environment may control the level of projects we participate in and how we participate. For example, we have 13 cfs capacity in the Baker Plant, which is 9,412 AF per year of supply or 785 AF per month. Our minimum flows for a day or two during the rainy season are 14 or 15 cfs, the average low is 17 or 18 cfs. As we discussed recently, this will impact our demands on the MWD treated capacity system with it being used for peaking. Page 39 SMWD CONSTRUCTION SUMMARY REPORT CURRENT PROJECTS DATE OF REPORT: MARCH 7, 2016 Contract Administrator Activity Name Engineer/ Consultant Contractor Contractor's P.O. No. Inspector Original Contract Amount Number of Change Orders Change Order Revised Contract Amount to Date Amount Total Billed to Date Total Amount Remaining Total Retention Project Award Date Project NTP Date Revised Original Completion Completion Date Date CAPITAL IMPROVEMENT PROJECTS COW CAMP 1B PIPELINES/1770B L&S/RMV/FLAT IRON RMV DIA/JOHN PSOMAS OLSSON 340772 TOM/JOHN SMWD SMWD STAFF S.S. MECHANICAL pending JOHN ESENCIA PA-2 LIFT STATION/1771 SMWD PSOMAS OLSSON 341764 JOHN/DOUG $2,157,000.00 SO. CO. PIPELINE CONNECTION 6 TURNOUT FLOW CONTROL/1771B SMWD SMWD SSC pending Tom ESENCIA ZONE 2 PUMP STATION/1767F SMWD PSOMAS SSC 351362 TESORO ROUGH GRADING & STORM DRAIN/1767C SMWD RBF/BAKER TESORO ZONE II & ZONE B TRANSMISSION MAINS/1767D SMWD TESORO ZONE 2 & B RESERVOIRS/1767E LOS PATRONES TEMPORARY RECYCLED WATER FAC/1685E PLANO FORCE MAIN TIJERAS CREEK CROSSING/1256.06 SMWD BAKER TREATMENT PLANT/1744 IRWD UPPER CHIQUITA RES. RECIRCULATION PUMP/1543A.09 $3,328,600.00 1 $134,610.00 $3,463,210.00 $3,275,321.75 $187,888.25 $163,766.09 17-Oct-14 $69,000.00 $64,000.00 $5,000.00 $3,200.00 1-Apr-15 $2,571,154.00 $1,751,843.00 $819,311.00 $87,592.15 11-May-15 21-May-15 30-Oct-15 $2,118,368.00 $2,118,368.00 $0.00 $2,118,368.00 26-Jan-16 19-Feb-16 15-Dec-16 TOM/DOUG $2,715,000.00 $2,715,000.00 $299,149.03 $2,415,850.97 $14,957.45 20-Nov-15 17-Dec-16 13-Sep-17 MC KENNA BUTIER/JEFF $2,869,548.81 $2,869,548.81 $2,488,740.70 $380,808.11 $124,437.04 22-May-15 29-Jun-15 13-Nov-15 RBF/BAKER CCL DIA $4,846,098.00 $4,846,098.00 $103,000.00 $4,743,098.00 $5,150.00 18-Dec-15 21-Jan-16 17-Oct-16 SMWD RBF/BAKER Bid opening 2/9/16 pending BUTIER/JEFF $4,830,000.00 $4,830,000.00 19-Feb-16 3-Mar-16 28-Nov-16 SMWD HUITT ZOLLAR LEATHERWOOD 351165 DIA $788,950.00 $788,950.00 $718,950.00 $70,000.00 $35,947.50 17-Oct-15 4-Nov-15 2-Feb-16 RELOCATION OF CP FOR CLOP/1252.30 SMWD RBF FARWEST 340776 DIA $101,230.00 $101,230.00 $101,230.00 $0.00 $5,061.50 17-Oct-14 24-Nov-14 27-Feb-15 2013 UPGRADE & REPL PROGRAM/1650F SMWD RBF FARWEST 331316 JAIME $99,100.00 $99,100.00 $98,995.00 $105.00 n/a 21-Feb-14 14-Apr-14 2015 PLANO FORCE MAIN SPILL REVEG/1256.05.01L SMWD DUDEK NAKAE 301822 JAIME $34,565.00 $34,565.00 $28,509.00 $6,056.00 n/a 13-May-11 31-May-12 31-May-17 UCR UPLAND RESTORATION & REVEG/1543A.03L SMWD PACIFIC RESTORATION 320513 JAIME $315,000.00 $315,000.00 $182,500.00 $132,500.00 n/a 14-Dec-11 30-Apr-13 30-Apr-18 MIDDLE CHIQUITA REVEG & 5 YEAR MAINT/1766.02L SMWD NAKAE 311140 TOM/DIA $857,840.00 $857,840.00 $452,383.45 $405,456.55 4-Dec-14 17-Feb-15 8-Dec-19 REVEG OVERSIGHT & ANNUAL REPORTS/1511G.01L SMWD LEATHERMAN BIOCONSULTING 320400 JAIME $11,800.00 $11,800.00 $11,800.00 $0.00 n/a 30-Jul-12 7-Jan-14 pending JOHN $498,460.50 $498,460.50 22-Jan-16 19-Feb-16 17-Feb-21 TOM $2,681,407.20 $2,681,407.20 $69,000.00 2 $414,154.00 $4,830,000.00 9-Mar-15 1-Jul-15 4-Sep-15 1-Mar-16 13-Dec-15 CATHODIC PROTECTION MITIGATION AND REVEGETATION GOBERNADORA MULTIPURPOSE BASIN MITIGATION AND YEAR MAINTENANCE/1685L.01 $22,619.18 5SMWD SMWD NATURES IMAGE SMWD SMWD STAFF L&S CONSTRUCTION $498,460.50 NON DOMESTIC CONVERSION PROJECTS CALIFIA ZONE C CONVERSION/1746 S:\_BOARD PACKAGES\2016 Staff Reports by Month\03 March\STANDING COMMITTEES\EO\SMWD Construction Report Jeff - Laurel BDM2 2016-03-07.xlsx Page 1 of 5 $1,089,523.00 $1,591,884.20 $54,476.15 3-Jun-15 12-Oct-15 Est. 18-Dec-15 Page 40Laurel Haberchak Printed: 3/7/2016 SMWD CONSTRUCTION SUMMARY REPORT DATE OF REPORT: JANUARY 15, 2016 Activity Name Contract Administrator Engineer/ Consultant Contractor CAPITAL IMPROVEMENT PROJECTS COMPLETED PROJECTS GOBERNADORA UPPER BASIN/1685C SMWD PACE J R FILANC GOBERNADORA LOWER BASIN/1685D SMWD PACE ACI MID CHIQUITA ZONE 1 & A PIPELINES/1766A SMWD RBF LEATHERWOOD MID CHIQUITA ZONE 1 & A RESERVOIRS/1767A&B SMWD RBF PASO ROBLES TANK CORDOVA LIFT STATION REHAB/1180.05 SMWD SMWD STAFF S.S. MECHANICAL Page 41 Contract Number of Change or's P.O. Inspect Original Contract Change Order Revised Contract No. or Amount Orders Amount to Date Amount 330573 JOHN $10,322,000.00 5 $3,772,312.00 $14,094,312.00 340850 JOHN $6,475,960.00 3 $279,324.43 $6,755,284.43 330538 DIA/TOM $5,591,100.00 $1,163,510.81 $6,754,610.81 330710 TOM/DIA $6,876,002.00 $30,847.32 $6,906,849.32 $11,439.00 $160,439.00 pending TOM $149,000.00 1 Page 42 Total Billed to Date Total Amoun t Remain ing Total Retention Project Award Date Original Project NTP Completion Date Date $14,094,312.00 $0.00 $704,715.60 25-Sep-13 16-Aug-13 31-Dec-15 $6,755,284.43 $0.00 $337,674.22 1-Oct-14 21-Oct-14 30-Apr-15 $6,754,610.81 $0.00 $260,680.00 16-Aug-13 16-Aug-13 30-Apr-14 $6,906,849.32 $0.00 $342,678.94 18-Oct-13 10-Nov-13 12-Sep-14 $160,439.00 $0.00 $8,021.95 1-Apr-15 21-May-15 18-Sep-15 Page 43 Revised Completion Date 28-Feb-15 21-Nov-14 31-May-15 Page 44