PETITION FOR APPROVAL OF REVISED REVENUE REQUIREMENT AND DETERMINATION OF GENERATION TARIFF FOR THE FINANCIAL YEAR 2015-16 AND TRUING-UP FOR FY 2013-14 AND ANNUAL PERFORMANCE REVIEW FOR FY 2014-15, Submission of Text and Affidavit To Assam Electricity Regulatory Commission By Assam Power Generation Corporation Limited Bijulee Bhawan, Paltanbazar Guwahati-781 001 April’15 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 BEFORE THE ASSAM STATE ELECTRICITY REGULATORY COMMISSION, GUWAHATI. Petition No. – Case No. (to be filed by the Office) IN THE MATTER OF Filing of Petition for Revised Revenue Requirement and Determination of Generation Tariff for the Financial Year 2015-16, Annual Performance Review for FY 2014-15, and Truing-Up for FY 2013-14 AND Petition for Determination of Tariff For the year 2015-2016 AND IN THE MATTER OF Assam Power Generation Corporation Limited Bijulee Bhawan, Paltanbazar, Guwahati-781 001. Petitioner I,______________________________________ son of Shri _________________________ aged _______ years residing at _________________________ do solemnly affirm and say as follows: I am the ___________________________ of Assam Power Generation Corporation Limited, the petitioner in the above matter and am duly authorized by the said Petitioner to make this affidavit for and on behalf of the Assam Power Generation Corporation Limited. The Statement made in the Petition based on information received from official records and I believe them to reflect truly and no material has been concealed from the statements so made or documents or supporting data etc. attached. Solemnly affirm at Guwahati on ___________th day of __________ 2014 that the contents of this affidavit are true to my knowledge, no part of it is false or no material has been concealed therefore and misleading material included therein. Deponent Place: Guwahati Date _________ By order of the Commission Secretary of the Commission Assam Power Generation Corporation Limited Page 1 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 TABLE OF CONTENTS 1. Legal and Regulatory Framework .........................................................................................09 2. Review of performance in FY 13-14 & FY 14-15 (Actual/Estimate) ....................................10 2.1. Status of APGCL Power station ...........................................................................................10 2.2. Investments (FY 14-15)........................................................................................................14 2.3. Highlights of the individual’s details of each expense for FY 13-14 & FY 14-15..........................16 2.3.1 Assumptions for 14-15………………………………………………………………………….16 2.3.2 Employees Expenses ..............................................................................................................................17 2.3.3 Repair & Maintenance..........................................................................................................................17 2.3.4 Administration and General Expenses ................................................................................................18 2.3.5 Income from Other Sources .................................................................................................................18 2.3.6 Depreciation ..........................................................................................................................................19 2.3.7 Repayment of Loan (Principal)............................................................................................................19 2.3.8 Interest & financing charges.................................................................................................................19 2.3.9 Interest on Working Capital .................................................................................................................20 2.3.10 Return on Equity………………………………………………………………………………20 2.3.11 Profit & Loss account ..........................................................................................................................20 2.3.12 Balance Sheet........................................................................................................................................21 3. Annual Revised Revenue Requirement (ARR) and Tariff Proposal for FY 15-16 ..............22 3.1. Multi- year framework .......................................................................................................22 3.2. Assumptions .......................................................................................................................22 3.3. Projected Operating Performance Data for FY 15-16 ........................................................37 3.4. Projected Financial Performance Data for FY 15-16 .........................................................40 3.4.1 Employees Expenses ..........................................................................................................40 3.4.2 Repairs & Maintenance ......................................................................................................41 3.4.3 Administration and General Expenses ...............................................................................53 3.4.4 Return on Equity.................................................................................................................53 3.4.5 Income from Other Sources................................................................................................53 3.4.6 Depreciation........................................................................................................................54 3.4.7 Interest & financing charges...............................................................................................54 3.4.8 Interest on Working Capital ...............................................................................................54 3.4.9 Repayment of Loan (Principal) ................................................................................................55 3.4.10 Fuel Cost .................................................................................................................................55 4. Profit & Loss Account for FY 15-16 ....................................................................................55 5. Balance Sheet.............................................................................................................................56 6. Proposed ARR and Tariff Proposal for FY 15-16 ....................................................................57 7. Directives of AERC...................................................................................................................58 8. Investment Plan during FY 15-16 …........................................................................................64 9. Statements of proposed Monthly Generation, Fuel Prices & Cost of Fuel for FY 2015-16 .78 10. Abstract of Technical Data for FY 2015-16 .............................................................................84 11. Various data as per Specified formats of Hon’ble Commission ..............................................86 12. Station wise information for claiming ARR and tariff for APGCL for FY 2015-16……..148 13. Appeal for Truing-up for FY 2013-14…............................................................................170 14. Petition for Annual Performance Review of 2014-15……………………………………...179 15. Statements of proposed Monthly Generation, Deviations comparing with Target of 2014-15 and Actual / Projected Cost of Fuel for FY 2014-15……………………………………...205 16. Annual Statement of Accounts: 13-14..................................................................................209 17. Annexure A, B, C, D, E, F, & G Assam Power Generation Corporation Limited Page 2 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 List of Tables Table 1 (A): Generation Target & Achievements of 2013-14 ...................................................................10 Table 1 (B): Generation Target & Achievements of 2014-15 (Actual/Estimate) .....................................11 Table 2: Comparison of Operating Performance of NTPS between FY 12-13, 13-14 and 15-16. .............12 Table 3: Comparison of Operating Performance of LTPS between FY 12-13, 13-14 and 14-15...............12 Table 4: Comparison of Operating Performance of KLHEP between FY 12-13, 13-14 and 14-15....................12 Table 5: Comparison of Operating Performance of MSHEP between FY 12-13, 13-14 and 14-15. ..................12 Table 6 (A): Investment of FY 14-15.........................................................................................................14 Table 6 (B): Breakup of Renovation & Modernisation Scheme……………………………………………......15 Table 7: Assumptions for FY 2014-15…………………………………………………………………...16 Table 8: Employees Expenses of FY 13-14& 14-15...................................................................................17 Table 9: Repairs & Maintenance of FY 13-14 & 14-15 ............................................................................. 17 Table 10: Administration and General Expenses of FY 13-14 & 14-15 ....................................................18 Table 11: Income from Other Sources of FY 13-14 & 14-15 ....................................................................18 Table 12: Depreciation of FY 13-14 & 14-15............................................................................................19 Table 13: Repayment of Loan (Principal) of FY 13-14 & 14-15 ...............................................................19 Table 14: Interest and Financing Charges of FY 13-14 & 14-15 ................................................................19 Table 15: Interest on Working Capital of FY 13-14 & 14-15 .....................................................................20 Table 16: ROE for FY 13-14 & 14-15………………………………………………………………..……….20 Table 17: Profit & Loss account of FY 13-14 & 14-15 ...............................................................................20 Table 18: Balance Sheet of FY 13-14 & 14-15 ...........................................................................................21 Table 19: Assumptions for FY 2015-16 various heads I............................................................................34 Table 20: Assumptions for FY 2015-16 various heads II ..........................................................................35 Table 21: Generation Projection for FY 2015-16.......................................................................................38 Table 22: Employees Expenses for FY 2015-16 ........................................................................................40 Table 23: Repairs & Maintenance for FY 2015-16....................................................................................41 Table 24: Administration and General Expenses for FY 2015-16..............................................................53 Table 25: Return on Equity for FY 2015-16 ..............................................................................................53 Table 26: Income from Other Sources for FY 2015-16 .............................................................................53 Table 27: Depreciation for FY 2015-16..................................................................................................... 54 Table 28: Interest & Financing charges for FY 2015-16............................................................................54 Table 29: Interest on Working Capital for FY 2015-16...............................................................................54 Table 30: Repayment of Loan (Principal) for FY 2015-16..........................................................................55 Table 31: Fuel Cost for FY 2015-16...........................................................................................................55 Table 32: Profit & Loss Account for FY 2015-16 ......................................................................................55 Table 33: Balance Sheet for FY 2015-16....................................................................................................56 Table 34: Proposed ARR and Tariff Proposal for FY 2015-16…………………………………………....57 Table 35: Investment 13-14........................................................................................................................180 Table 36: Employees Expenses 12-14 ........................................................................................................181 Table 37 Repairs & Maintenance for 12-14………………………………………………………………… 181 Table38: Administration and General Expenses for FY 2012-14...............................................................182 Table 39: Income from Other Sources for FY 2012-14 .............................................................................182 Table 40: Depreciation for FY 12-14.........................................................................................................182 Table 41: Repayment of Loan (Principal) for FY 2012-14..........................................................................185 Table 42: Interest & Finance Charges for FY 12-14 ...................................................................................185 Table 43: Interest on Working Capital for FY 2012-14 ..............................................................................185 Table 44: Profit & Loss account of FY 12-14 .............................................................................................185 Table 45: Balance Sheet of FY 12-14 .........................................................................................................187 Assam Power Generation Corporation Limited Page 3 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 List of Tables Table 46: Assumptions for FY 2014-15 various heads I.............................................................................188 Table 47: Assumptions for FY 2014-15 various heads II ...........................................................................189 Table 48: Actual Projected Operating Performance for FY 2014-15 ..........................................................190 Table 49: Employees Expenses for FY 2014-15 .........................................................................................192 Table 50: Repairs & Maintenance for FY 2014-15.....................................................................................192 Table 51: Administration and General Expenses for FY 2014-15...............................................................198 Table 52: Return on Equity for FY 2014-15 ...............................................................................................198 Table 53: Income from Other Sources for FY 2014-15 ..............................................................................201 Table 54: Depreciation for FY 2014-15..................................................................................................... .201 Table 55: Interest & Financing charges for FY 2014-15.............................................................................201 Table 56: Interest on Working Capital for FY 2014-15................................................................................202 Table 57: Repayment of Loan (Principal) for FY 2014-15...........................................................................202 Table 58: Fuel Cost for FY 2014-15............................................................................................................202 Table 59: Profit & Loss Account for FY 2014-15 .......................................................................................202 Table 60: Balance Sheet for FY 2014-15.....................................................................................................203 Table 61: Revised ARR for FY 2014-15………………………………………………………………204 Assam Power Generation Corporation Limited Page 4 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 List of Annexure Annexure I: Statements of proposed Monthly Generation, Fuel Prices & Cost of Fuel for FY 2015-16...................................................................................................................................78 Annexure II: Abstract of Technical Data for FY 2015-16 .......................................................84 Annexure III: Status of Hon'ble Commission's Formats.........................................................86 Annexure IV: Systematic Station wise Information for claiming ARR and Tariff ...............148 Annexure V: Statements of proposed Monthly Generation, Fuel Prices & Cost of Fuel for FY 2014-15.............................................................................................................................205 Annexure VI: Annual Statement of Accounts for FY 13-14....................................................209 Annexure A: Abstract of Quarterly Trial Balance…………………………………........A1-A12 Annexure B: Sanction letters of Loans from GOA received up to FY 13-14…………..B1-B35 Annexure C: Interest rate considered for State Govt. Loan……………………………...C1-C2 Annexure D: Loan drawl from PFCL during FY 13-14………………………………......D1-D3 Annexure E: Interest and repayments made to PFCL during FY 13-14…………….....E1-E44 Annexure F: TDS certificates on investments……………………………………………….....F1-F21 Annexure G: Sanction Letters of Grant received by APGCL…………………………..E1-E29 Assam Power Generation Corporation Limited Page 5 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Glossary Acronym A&G ABT ADB AEGCL AERC APDRP APGCL APDCL ARR ASEB CGM CT/PT EE FAS FY GoA GoI KV KVA KW KWH LRPP LTPS MIS MMSCMD MOU MU NERLDC NRPP NTPS O/H PGCIL Ph PLF R&M Rs SEBs ST T&D T.C. KLHEP Full form Administrative and General Availability Based Tariff Asian Development Bank Assam Electricity Grid Corporation Limited Assam Electricity Regulatory Commission Accelerated Power Development and Reforms Program Assam Power Generation Corporation Limited Assam Power Distribution Company Limited Annual Revenue Requirement Assam State Electricity Board Chief General Manager Current Transformer/Potential Transformer Executive Engineer Fuel Adjustment Surcharge Financial Year Government of Assam Government of India Kilo Volt Kilo Volt Ampere Kilo Watt Kilo Watt Hour Lakwa Replacement Power Project Lakwa Thermal Power Station Management Information Systems Million Metric Standard Cubic Meter per day Memorandum of Understanding Million Unit North East Region Load Despatch Centre Namrup Replacement Power Project Namrup Thermal Power Station Over Heads Power Grid Corporation of India Limited Phase Plant Load Factor Repairs and Maintenance Rupees State Electricity Boards Scheduled Tribe Transmission and Distribution Transportation Cost Karbi Langpi Hydro Electric Project Assam Power Generation Corporation Limited Page 6 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 BEFORE THE HON'BLE ASSAM ELECTRICITY REGULATORY COMMISSION FILINGNO......................... CASENO ........................... IN THE MATTER OF: Petition for Revised Revenue Requirement and Determination of Generation Tariff for the for the period 1st April 2015 to 31st March 2016 for the Assam Power Generation Corporation Limited (APGCL) and Truing-Up for FY 2013-14 and Annual Performance Review for FY 2014-15 AND IN THE MATTER OF: Assam Power Generation Corporation Limited incorporated under the provisions of the Companies Act, 1956 and having its registered office in the State of Assam THE HUMBLE APPLICANT ABOVE NAMED MOST RESPECTFULLY SHEWETH: 1 That the Assam Power Generation Corporation Limited, hereinafter named as APGCL, is a successor corporate entity, formed in pursuant to the notification of the Government of Assam, notified under sub-sections (1), (2), (5), (6) and (7) of Section 131 and Section 133 of the Electricity Act 2003(Central Act 36 of 2003), for the purpose of transfer and vesting of functions, properties, interests, rights, obligations and liabilities, along with the transfer of Personnel of the Board to the successor corporate entities. 2 That the Assam Power Generation Corporation Limited is a company incorporated with the main object of generation of electricity in the state of Assam. 3 That the Assam Power Generation Corporation Limited is a generating company under the provisions laid down in Section 14 Proviso 5, read with Section 131 (2) of the Electricity Act 2003. 4 That the licensee is now filing the Petition for Revised Revenue Requirement and Determination of Generation Tariff for the for FY 2015-16 for the Assam Power Generation Corporation Limited (APGCL)and Truing-Up for FY 2013-14 and Annual Performance Review for FY 2014-15. (PETITIONER) Assam Power Generation Corporation Limited Page 7 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 NOTES: In this petition: Previous Year is defined as the Financial Year (FY) 2013-2014 Current Year is defined as the Financial Year (FY) 2014-2015 Ensuing Year is defined as the Financial Years (FY) 2015-2016 Assam Power Generation Corporation Limited Page 8 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1. Legal and Regulatory Framework 1.1 Under the provisions of Electricity Act 2003 (hereinafter referred to as "Electricity Act") the Assam Electricity Reforms First Transfer Scheme, 2004 (hereinafter referred to as "Transfer Scheme") was notified by Government of Assam on 10th December 2004. Under Section 5 (2) of the transfer scheme the functions and undertakings as set out in Schedule-A of the transfer scheme stands transferred to Assam Power Generation Corporation Limited (APGCL). The final transfer scheme was notified by Govt. of Assam vide notification No: PEL/151/2003/Pt.349 Dtd. 16th Aug’ 2005 w.e.f 1st April’05. 1.2 Section 131 (2) of the Electricity Act provides "...Any property, interest in property, rights and liabilities vested in the State Government under sub-section (1) shall be re-vested by the State Government in a Government company or in a company or companies, in accordance with the transfer scheme so published along with such other property, interest in property, rights and liabilities of the State Government as may be stipulated in such scheme, on such terms and conditions as may be agreed between the State Government and such company or companies being State Transmission Utility or generating company or transmission licensee or distribution licensee,... ". 1.3 Section 62 of the Electricity Act 2003 requires the generating company to furnish details as may be specified by the Commission for determination of tariff. 1.4 Section 5, 6 & 7 of A. E. R. C. (Terms and conditions for determination of Tariff) Regulations 2006 lays down the following: Periodicity of tariff determination (Sec.-5) 1.4.1(Sec.5.2) Subject to other provisions of these Regulations, the expenses allowed to be recouped for any financial year, shall be subject to adjustments in any tariff to be fixed for the subsequent period, if the Commission is satisfied, that such adjustments for the excess amount or shortfall in the amount actually realized or expenses incurred is necessary and the same is not on account of any reason attributable to the licensee 1.4.2(Sec.5.3) In accordance with the principle of multi-year tariffs (MYT), the Commission approved three years control period i.e. 2010-11 to 2012-13and accordingly APGCL filed MYT petition for the said control period to AERC on 08/02/2010.Against Tariff Petitions of APGCL, AERC issued Tariff order for FY 2010-11 and approved ARR for FY 2010-11, FY 2011-12 & FY 2012-13 on 16thMay’2011. Latter APGCL filed Annual Performance Review of APGCL for FY 2011-12& Truing-up for FY 2009-10, FY 2010-11 on 4th June’12 and Revised Annual Revenue Requirement for FY 2012-13 and determination of Generation Tariff for FY 2012-13 on dated 26 th Sept’12.Further, APGCL filed MYT petition for the control period of FY 2013-14 to 2015-16 on 31.01.13.The Tariff for FY 2013-14 has been declared by AERC on 21.11.13 with effectuation date from 1st Dec’13. Thereafter, APGCL submitted petition for Revised ARR and tariff proposal for FY 2014-15 and True-up for FY 2012- to AERC 26/02/14. AERC declared tariff for FY 201415 on 21.11.14 with effectuation date from 1st Dec’14. Petition for determination of MYT (Sec.-6) 1.4.3(Sec.-6.1) The licensee and generating company may file a tariff petition annually with the Commission to determine changes to the current tariff by not later than 1stDecember unless an extension is granted by the Commission upon application. Petition for determination of tariff (Sec.-7) 1.4.4(Sec.-7.2) The licensee and generating company shall also submit financial information for the previous year and forecasts for current year, ensuing year and the years up to the end of the control period. 1.5 The petitioner has now prepared the revised ARR and Tariff proposal for FY 2015-16 and Truingup for FY 13-14 and Annual Performance Review for FY 2014-15 for the area of operation of APGCL and to submit the same to AERC on or before 20th December’2014, as extended by AERC on our appeal. 1.6 The status of the various data formats and forms, as required by the Hon'ble Commission, are furnished in Annexure III at Page No. 86 1.7 The Annual Accounts of APGCL for the year 2013-14 is enclosed in Annex. –VI at Page No. 207 Assam Power Generation Corporation Limited Page 9 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 2. Review of performance in FY 13-14 & 14-15 2.1 Status of APGCL Power station: APGCL’s 3 (three) operating power plants namely 119.5 MW (De-rated) Namrup Thermal Power Station (NTPS), 157.2 MW Lakwa Thermal Power Station (LTPS), and 100 MW Karbi Langpi Hydro-electric Power Station (KLHEP). 60 MW Chandrapur Thermal Power Station (CTPS) was closed since June’1999 due to exorbitant cost of generation for steep hikes of fuel oil. However the plant is being revived by using coal as an alternative fuel in JV on Public-Private- Partnership (PPP) mode on B-O-T basis. FY 2013-14: In the FY 2013-14, APGCL achieved gross generation of 1845.23MU as shown in Table 1(A). Table 1(A) Power Station Gross generation in MU Target Actual 523.41 526.57 855.30 896.15 390.00 422.51 17.69 0.00 1786.40 1845.23 NTPS LTPS + WHRU KLHEP Myntriang St-II Total % of achievements 101% 105% 108% 0% 103% NTPS: In the FY 2013-14 NTPS was able to achieve the normative PLF of 50% and it also surpassed it Target Gross generation. Hence, its performance was satisfactory. Unit #2 of NTPS was under forced shutdown since 03/07/13 due to high vibration problem. The unit was overhauled and put into operation on 31/10/13. LTPS: Unit #1 of LTPS was under planned shutdown from 14/04/13 for Major Overhauling. This was originally scheduled in 2012-13. However, due to deferment of the earlier scheduled shutdown, the Major Overhauling of Unit #1 was postponed to 2013-14. The original scheduled shutdown was for 25 days, but due to severe damage in internal parts, the overhauling work lasted for more than 4 months and the unit was ultimately put into operation from 10/09/13. Even though the performance of LTPS suffered a little bit due to this during this period, however, later the availability of LTPS improved to 76%. As a result LTPS was able to surpass the target in Gross Generation. KLHEP: The generation from 100 MW KLHEP crossed the design generation i.e. 390 MU in the month of Jan’14. This was possible due to sufficient availability of water and because of keeping the generating units in smooth running condition by doing timely repair & maintenance works. Total generation of KLHEP in the FY 2013-14 was 422.51 MU Myntriang St-II: Earlier Myntriang St-II SHEP project was expected to be completed in June’13. However due to delay in project work, the project started commercial operation from 08-08-14 only. Thus, there was no generation from Myntriang St-II SHEP in 2013-14. Assam Power Generation Corporation Limited Page 10 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FY 2014-15: In the FY 2014-15, the actual and anticipated gross generation of APGCL is as shown in Table 1(B). Table 1(B) Power Station NTPS LTPS + WHRU KLHEP Myntriang SHEP St-II Total Gross generation in MU % of achievement Target Actual 523.09 842.47 591.66 935.30 113% 111% 390.00 11.38 366.98 0.71 94% 6% 1766.94 1894.66 107% NTPS: Due to continuous efforts taken by APGCL, performance of NTPS has improved significantly compared to previous years, which can be observed in its average higher PLF of 57% and availability factor of 62.6% respectively during 2014-15. Due to such improved performance, NTPS surpassed Target generation for the FY 2014-15. LTPS: From April to the end of November 2014, performance of LTPS was satisfactory. During the period from April to November 2014 LTPS has achieved average PLF of 68% and availability of 78.4%. Due to such satisfactory performance, even though LTPS is constantly facing shortage of gas supply, it LTPS surpassed Target generation for the FY 2014-15. KLHEP: Due to shortfall in rain during the monsoon period of 2014-15, generation of KLHEP has suffered significantly. Generation of KLHEP in the FY 2014-15 was only 366.98 MU against approved generation of 390 MU. Myntriang SHEP St-II: Commercial Operation Date of Myntriang SHEP St-II was declared on 08-08-14. But the project was damaged heavily in the devastating flood of 22-08-14. The machines were put into trial run on 20-1014, however they were not stable. Both the units of Myntriang SHEP are not in operation at the moment. 2.1.1. Plant wise Performance Data: The following tables indicate the plant wise operating performance parameters of APGCL for FY 2012-13, FY 2013-14 and FY 14-15 (Actual/ Estimate) which reflects an improvement of plants performance of APGCL. Assam Power Generation Corporation Limited Page 11 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Table 2 NTPS Gross Energy in MU Aux. Power Cons. (%) Availability (%) PLF (%) Gross Station Heat Rate on GCV (Kcal/ Kwh) Sp. Gas Consumption (SCM/Kwh) FY 12-13 533.168 5.6% 54% 51% 4093 0.4458 FY 13-14 526.57 6.0% 61.7% 50% 3976 0.4290 FY 14-15 591.66 5.8% 62.6% 57% 4045 0.4254 Table 3 LTPS + WHRU Gross Energy in MU Aux. Power Cons. (%) Availability (%) PLF (%) Gross Station Heat Rate on GCV (Kcal/ Kwh) Sp. Gas Consumption (SCM/Kwh) FY 12-13 888.08 11.5% 73% 64% 3066 0.3219 FY 13-14 896.15 8.8% 86.1% 65% 3164 0.3303 FY 14-15 935.30 8.6% 78.4% 68% 3058 0.3088 Table 4 KLHEP Gross Energy in MU Aux. Power Cons. (%) Capacity Index (%) PLF (%) FY 12-13 344.02 0.5% 93% 39% FY 13-14 422.51 0.5% 91.5% 48% FY 14-15 366.98 0.5% 92.6% 42% Table 5 Myntriang St-II Gross Energy in MU Aux. Power Cons. (%) Availability (%) PLF (%) FY 12-13 N/A N/A N/A N/A FY 13-14 N/A N/A N/A N/A FY 14-15 0.71 1.7% 4.3% 4.2% 2.1.2. Brief Status of APGCL’s Running Power Stations Namrup Thermal Power Stations: (119.5 MW) At present Namrup Thermal Power Station is generating an average of 75-90 MW depending on availability of gas. The details of units are as under: Unit-1 (20 MW, GT): Unit is presently running at an average load of 19 MW. The unit is overdue for major overhauling and is scheduled to be overhauled in June’15-July’15 for 60 days. This was earlier scheduled in 2014-15. Unit-2 (21 MW, GT): Unit is presently running at an average load of 20 MW Unit-3 (21 MW, GT): Unit is presently running at an average load of 18 MW. The unit is overdue for major overhauling and is scheduled to be overhauled in Nov’15-Dec’15 for 60 days. Unit-4 (11 MW, GT): Unit presently runs at an average load of 9 MW. The unit was under shut down wef 09/09/14 for lube oil cooler fan damage and the unit was subsequently put under scheduled major overhauling. The unit resumed operation from 02/04/2015 after overhauling. Steam Turbine Unit 5 (24 MW): The unit is presently running with an average load of 12 Assam Power Generation Corporation Limited Page 12 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 MW due to technical constrain. Waste Heat Unit 6 (22.5 MW): Unit is presently running with an average load of 12 MW due to technical constraint. The unit is overdue for major overhauling and is scheduled to be overhauled in Aug’15-Sep’15 for 60 days. This was earlier scheduled in 2014-15. Lakwa Thermal Power Stations: (157.2 MW): Lakwa Thermal Power Station is generating a daily average of 100 – 125 MW depending on availability of gas. The details of the units are as under. Unit-1 (15 MW, GT): The unit is presently running at full load capacity. Unit-2 (15 MW, GT): The unit is presently running at full load capacity. The unit is overdue for major overhauling and is scheduled to be overhauled in Apr’15-May’15 for 50 days. This was earlier scheduled in 2014-15. Unit-3 (15 MW, GT): The unit is presently running at full load capacity. The unit is overdue for major overhauling and is scheduled to be overhauled in Jul’15-Aug’15 for 50 days. Unit-4 (15 MW, GT): The unit is presently running at full load capacity Unit-5 (20 MW, GT): The unit is presently running at full load capacity Unit-6 (20 MW, GT): The unit is presently running at full load capacity. The unit is overdue for major overhauling and is scheduled to be overhauled in Jun’15 for 25 days. Unit-7 (20 MW, GT): The unit is presently running at full load capacity. The unit was under shutdown for Major Inspection from 08-11-14 to 02-12-14. Unit-8 (37.2 MW WHRU): The unit is presently running with an average load of 30 to 32 MW. Karbi Langpi Hydro Electric Project (100 MW): Unit-1 (50 MW): The unit is presently in a healthy condition and running at full capacity depending on availability of water. Unit-2 (50 MW): The unit is presently in a healthy condition and running at full capacity depending on availability of water. Myntriang Small Hydro Electric Project St-II (3 MW): Unit 1 (1.5 MW) & Unit 2 (1.5 MW): The plant got affected by heavy flood on 22-08-14. All the equipments needed servicing. At present both the units are under forced shutdown. Assam Power Generation Corporation Limited Page 13 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 2.2 Investments Table 6 (A) Revised Investment Proposal for the FY 2014-15 Rs. in Crore Sl. No. Name of the Project Approved in the Tariff Order of 2014-15 Revised investment Proposal for 2014-15 Govt (Equity) GOA (Loan) Grant (Govt) FI (Loan) Remarks Total Thermal Wing 1 R&M of Namrup TPS 6.85 8.67 8.67 R&M of Lakwa TPS 23.20 20.19 20.19 R&M of Lakwa TPS (Major Overhauling of Unit#2) 12.50 2 3 R&M of KLHEP 4 100 MW Namrup RPP 5 6 7 5.82 0.00 1.56 1.56 165.00 70 MW Lakwa Replacement Power Project 660 MW Margherita Thermal Power Project Hydro Wing 9 MW Myntriang SHEP 0.00 1.00 0.60 0.60 0.00 2.00 2.00 0.00 8 6 MW Lungnit SHEP 22.00 9 120 MW Lower Kopilii HEP 0.00 7.00 7.00 0.00 7.00 Assam Power Generation Corporation Limited 7.00 Additional work of (i) Rs. 1.80 Cr due to procurement of 25 nos. of important mechanical, electrical & instrumentation spares required at NTPS for smooth and trouble free operations of the old GT units and its auxiliaries, (ii) Rs. 0.02 Cr due to revised estimate of Anti Erosion Measures at Dillighat intake from earlier Rs. 0.30 Cr to 0.32 Cr Amount reduced as the R&M proposal for 2014-15 by APGCL was curtailed by GOA and work is now going to be executed on priority basis. Details of Overhauling Cost of Unit #2 of LTPS is given at Page No. 193 Amount reduced as the work of procurement of 11/232/√3 kV, 21 MVA single phase generator transformer has been deferred due to fund constraint. Amount is reduced due to delay in resuming of Project work As per approved amount in the Annual Plan for construction of boundary wall at site As per approved amount in the Annual Plan for construction of boundary wall at site Land Compensation Due to litigations, bid finalization process is at present under suspension Earlier Rs. 15/- Cr was included in the Annual Plan Proposal for FY 2014-15 as govt. loan for part payment of land compensation. However, later it was decided to include the whole amount of land Compensation in the Govt. Page 14 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Equity to be given by AIFA in the meeting held on 05/08/14 with GOA. The proposed amount in Annual plan has thus been reduced to Rs. 7/- Cr. under Govt. loan for project development activities 10 Boundary Wall at Jagiroad for KLHEP Store Total Proposed Investment 0.33 236.70 0.36 0.36 0.00 40.38 7.00 0.00 Earlier estimate was as per the 2011-12 APWD price schedule. Estimate has been revised as per the 2013-14 APWD price schedule 47.38 Breakup of R&M Scheme is given in the table below: Table 6 (B) Sl No. Name of Schemes and Approved Outlay (A) R&M Works under Namrup Thermal Power Station (NTPS) 1. Procurement of 250 V,425 AH lead acid battery bank with suitable battery charger at NTPS 2. Procurement of Flexible gear coupling of GT-1, 3 of NTPS 3. 4. 5. Total (Rs. In Cr) 0.60 0.50 Procurement of Air Clutch Drum of GT-1,2,3 of NTPS Procurement of 66kV SF-6 Breaker for NTPS Switch yard 0.15 0.30 Procurement of Mechanical, Electrical & Instrumentation spares for generating unit and auxiliaries & execution of important works at NTPS Anti Erosion measure at Dillighat intake of NTPS 1.80 6. Boundary wall around the NTPS campus 7. (B) R&M works under Lakwa Thermal Power Station (LTPS) 8. Procurement of spares for Gas Compressor & air compressor of PhII at LTPS 9. Spares for major overhauling of GT #6 of LTPS Including work component 10. Work expenditure for major overhauling of GT #6 of LTPS 11. Diesel generator set with Control panel/breaker and shed for Water Intake pump house of WHRP New departmental quarters for officers of LTPS i. 1 no. Type-II multi strayed building with 2 blocks 12. ii. 1 no. Type-III multi storied building with 4 blocks 13 Spares for WHRP including balance of plant(BOP) for LTPS 14 Spares of electrical and instrumentation parts of Ph-II power house of LTPS (C) R&M Works under Karbi Langpi Hydel Power Project 15 Supply of Spares/Accessories for revival & up-gradation of instrumentation installed in Dam of KLHEP with installation charges 16 Procurement of Storage System for renovation of Electrical Stores at KLHEP 17 Communication Tower installation near surge shaft for online communication of data and information 2.3 Budget Proposal (Rs in Lakh) 8.67 0.32 5.00 0.60 15.00 0.70 0.55 20.19 0.00 0.75 0.90 1.08 0.61 0.36 0.54 1.56 0.66 The following tables highlight the individual’s details of each expense for 13Assam Power Generation Corporation Limited Page 15 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 14&14-15 (Actual/Estimate). 2.3.1 Assumptions for FY 2014-15 Table 7 2014-15 14.75% ST PLR R & M Expenses Employee Expenses A & G Expenses ROE escalation rates Other Income Provision for Taxes Provision for Bad and Doubtful Debts % of revenue Current Assets - per Actual O&M Expenses Maintenance spares Receivable against sale of power Current Assets - per AERC O&M Expenses & fuel Maintenance spares Receivable against sale of power Power purchase Payable Depreciation rate applicable for Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Lines & Cable Network Vehicles Furniture & fixture Office equipment Roads on land Belonging to others Capital spares at generating stations Cap of Asset Value 15.00% 8.42% 8.42% 14.00% @ 10% escalation at approved by Hon'ble AERC 0.00 On annual Expenditure 1% of Gross Block On the total revenue demand On annual Expenditure 1% of Gross Block On the total revenue demand Thermal 0.00 1.80% 2.57% 1.80% 6.00% 2.57% 18.00% 6.00% 6.00% 1.80% 4.75% 90.00% Hydel 0.00 1.80% 2.57% 1.80% 2.57% 2.57% 18.00% 6.00% 6.00% 1.80% 4.75% 90.00% Loan Rates - New Loan Institution 11.40% Existing Loans Rates of interest State Govt 10.50% Assam Power Generation Corporation Limited Page 16 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 @ different agreement rates 11.40% PFC Other Loan Repayment Govt Loan PFC Others 11.07 22.97 0.00 Thermal O & M for new stations on commercial startup year subsequently @ inflation Interest rate for investment income Hydel 5.72% O & M for new stations on commercial startup year subsequently @ inflation Interest rate for investment income 2.3.2 5.72% Employees Expenses Table 8 Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 2013-14 33.81 1.44 27.12 6.93 0.03 0.18 0.05 0.27 0.00 0.01 0.13 12.04 2014-15 36.65 1.66 29.85 5.61 0.03 0.09 0.05 0.29 0.00 0.01 0.14 12.16 82.00 0.00 82.00 86.54 0.00 86.54 Note: 1. Employee expenses for FY 14-15 are in actual up to 2nd quarter before any Head quarter adjustment. Regarding 3rd & 4th quarter of FY 14-15 expenses are assumed to be proportionate to the expenses of 1st & 2nd quarter. 2. Escalation taken @ 8.42 % for Employees cost, as the escalation rate was approved by AERC in Tariff order 14-15 2.3.3 Repairs & Maintenance Table 9 Particulars 2013-14 2014-15 A. Special Type Repair & Maintenance:- Assam Power Generation Corporation Limited Page 17 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Overhauling Works of Unit # 2 of LTPS under plant & Machinery B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: 0.00 6.44 20.60 1.81 0.87 0.89 0.03 0.06 0.26 0.08 1.23 0.20 26.03 14.74 0.27 0.31 1.10 0.09 0.26 0.14 0.20 1.41 0.23 25.19 Regular R&M cost for FY 14-15 is taken at par to that approved in Tariff order FY 14-15and in addition Lubricants & Consumable Stores & Turbine oil are also considered. Detailed justifications on Special type Repair & Maintenance for Overhauling Works of Unit # 2 of LTPS under plant & Machinery has been given in page No: 193 under APR for FY 2014-15 2.3.4 Administration and General Expenses Table 10 Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses Sub Total: Less: Capitalised Total: Note: 2013-14 0.35 0.81 0.12 0.01 0.02 0.02 0.60 0.02 0.07 0.76 0.04 9.72 12.53 0.00 12.53 2014-15 0.35 0.88 0.05 0.00 0.01 0.00 0.65 0.01 0.01 0.63 0.02 6.79 9.41 0.00 9.41 1. A&G expenses for FY 14-15 are in actual up to 2nd quarter before any Head quarter adjustment. Regarding 3rd & 4th quarter of FY 14-15 expenses are assumed to be proportionate to the expenses of 1st & 2nd quarter. 2.3.5. Income from Other Sources Table 11 Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: 2013-14 0.00 8.85 0.06 0.79 0.90 0.01 10.60 Assam Power Generation Corporation Limited 2014-15 0.00 8.85 0.06 0.79 0.90 0.01 10.60 Page 18 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Note: Other income incurred in FY 2013-14 is considered at par for FY 2014-15 2.3.6. Depreciation Table 12 Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & fixtures Office equipment Roads on land belonging to others Capital spares at generating stations Total (Less) : Depreciation on 90% of the Assets funded by Grants/subsidies Net Total 2013-14 0.00 0.72 3.82 3.02 15.07 4.27 0.21 0.12 0.04 0.05 0.00 3.72 31.05 2014-15 0.00 0.72 4.06 3.12 20.49 4.48 0.99 0.14 -2.56 0.06 0.00 7.43 38.93 -5.39 25.66 -6.12 32.81 Depreciation has been calculated using the schedule as prescribed by the AERC. Analysis of the trial balance under each function head has been carried out and the weighted average rate has been calculated and used for calculation. Depreciation on assets commissioned in a year is charged at the average balance for the year (since they could be commissioned at different date). 2.3.7 Repayment of Loan (Principal) Table 13 Particulars PFC Loan State Govt Loan Total 2013-14 22.97 0.00 22.97 2014-15 22.97 11.07 34.03 2013-14 50.67 0.05 50.72 -19.44 31.28 2014-15 52.41 0.05 52.46 -22.85 29.61 2.3.8. Interest & financing charges Table 14: Particulars Interest on loans Other finance charges Sub total Less: Interest capitalised Total Note: 1. Interest on loans & Other Finance Charges calculated for FY 13-14 @ 10.5% on loan outstanding for Loan from Govt. of Assam, @ actual interest calculated by PFC for Loan from PFCL. Interest on GPF is not claimed in true up 13-14 petition as the GPF trust not yet formed. But the same is expected to complete in FY 15-16 and hence claimed thereafter 2. Interest on loans & Other Finance Charges calculated for FY 14-15 @ 10.5% on loan outstanding for Loan from Govt. of Assam, @ actual interest rates charged by PFC for Loan up Assam Power Generation Corporation Limited Page 19 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 to Dec’14 from PFC and remaining on proportionate assumption. GPF trust is expected to complete in FY 15-16 and hence interest on GPF is claimed from FY 15-16 2.3.9 Interest on Working Capital Table 15: Particulars One month Fuel Cost One month approved O&M Cost Maintenance Spares Two month Receivables Total Interest @ 14.75% 2013-14 2014-15 32.10 9.79 12.48 96.97 151.34 22.32 39.79 9.83 12.90 113.99 176.50 26.03 Note: Interest on working capital is computed @ an interest rate of 14.75%.APGCL has not considered the O&M expenses of Rs. 3.10 Cr and 1% maintenance spares on GFA of Rs. 35.98 Cr in respect of Chandrapur TPS for FY 2013-14 since the same is inoperative power station, in the computation of interest on working capital. Similarly the same was also not considered for FY 2014-16 2.3.10 Return on Equity Table 16 Particulars Namrup TPS Lakwa TPS Lakwa WHRP Karbi Langpi HEP Myntriang SHEP Namrup RPP Total Particulars NTPS Opening Equity Closing Equity Average equity Rate ROE 2.3.11 13-14 64.62 64.74 64.68 0.14 9.06 14-15 64.74 69.44 67.09 0.14 9.39 2013-14 9.06 10.07 9.93 9.54 0.00 0.00 38.59 2014-15 9.39 10.67 9.93 9.54 0.86 0.00 40.39 Note: ROE calculated as follows: LTPS KLHEP LWHRP NRPP Myntriang 13-14 14-15 13-14 14-15 13-14 14-15 13-14 14-15 13-14 14-15 70.72 73.19 68.11 68.11 70.92 70.92 0.00 0.00 0.00 11.27 73.19 79.24 68.11 68.11 70.92 70.92 0.00 0.00 11.27 13.37 71.95 76.22 68.11 68.11 70.92 70.92 0.00 0.00 5.63 12.32 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 10.07 10.67 9.54 9.54 9.93 9.93 0.00 0.00 0.00 0.86 Total 13-14 14-15 274.37 288.22 288.22 301.08 281.30 294.65 0.14 0.14 38.59 40.39 Profit & Loss Account Table 17: Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges O&M expenses of CTPS 2013-14 2014-15 1845.23 1732.85 6.09% 1894.66 1778.73 6.12% 547.00 0.00 618.38 0.00 385.15 26.03 82.00 477.45 25.19 86.54 EXPENDITURE Generation Cost R&M Expenses Employee Expenses Assam Power Generation Corporation Limited Page 20 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement Add: Incentive for generation for FY 2013-14 Add: Incentive for Secondary Energy generation for FY 2011-12 9.41 32.81 52.46 -22.85 26.03 0.00 0.00 -10.07 574.91 38.59 10.60 0.45 603.35 7.97 0.00 0.00 0.00 687.04 40.39 10.60 0.93 717.76 2.51 -66.83 Surplus(+) / Shortfall(-) 2.3.12 12.53 25.66 50.72 -19.44 22.32 -99.38 Balance Sheet Table 18: Particulars Source of Fund Share Capital Reserve & Surplus Loans from State Govt Loans from others Total Contributions, grants & subsidies towards cost of Capital Asset Grand Total Application of Fund Net Fixed Assets (A) Gross Block (B) Less : Accumulated Depreciation (C) Net Fixed Assets (D) Capital-works-in-progress Total of (C) to (D) Investements Subsidy receivable from Govt Net Current Assets A. Current Assets, Loans & Advances i) Inventories ii) Receivables against Sale of Power iii) Cash & Bank Balance 2013-14 2014-15 455.86 36.33 135.78 405.49 455.86 43.60 172.46 405.49 1033.47 1077.42 380.38 407.54 1413.85 1484.95 1325.74 626.38 699.36 568.98 1268.34 0.00 1370.51 659.19 711.32 621.60 1332.92 0.00 68.25 3.44 154.09 81.90 4.13 184.91 Assam Power Generation Corporation Limited Page 21 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 iv) Loans & Advances v) Other current assets Total of A B. Current Liabilities and provisions i) Borrowing for Working Capital ii) Payment due on Capital Libilities iii) Other current liabilities Total of B Net Current Assets (A - B) Profit/ Loss Grand Total 57.40 76.23 359.41 68.88 91.48 431.30 386.91 386.91 -27.50 173.01 1413.85 406.26 406.26 25.04 127.00 1484.96 3.0 Revised Annual Revenue Requirement (ARR) for 2015-16 3.1 Multi- year framework In accordance with the principle of multi-year tariffs (MYT), the Commission approved three years control period i.e. 2010-11 to 2012-13 and accordingly APGCL filed MYT petition for the said control period to AERC on 08/02/2010.Against Tariff Petitions of APGCL, AERC issued Tariff order for FY 2010-11 and approved ARR for FY 2010-11, FY 2011-12 & FY 2012-13 on 16thMay’2011. Latter APGCL filed Annual Performance Review of APGCL for FY 2011-12& Truing-up for FY 2009-10, FY 2010-11 on 4th June’12 and Revised Annual Revenue Requirement for FY 2012-13 and determination of Generation Tariff for FY 2012-13 on dated 26th Sept’12.Further, APGCL filed MYT petition for the control period of FY 2013-14 to 2015-16 on 31.01.13.The Tariff for FY 2013-14 has been declared by AERC on 21.11.13 with effectuation date from 1st Dec’13. Thereafter, APGCL submitted petition for Revised ARR and tariff proposal for FY 2014-15 and True-up for FY 2012- to AERC 26/02/14. AERC declared tariff for FY 2014-15 on 21.11.14 with effectuation date from 1 st Dec’14. APGCL is now to submit revised ARR and Tariff petition for FY 2015-16 and APR for FY 2014-15 by considering the detailed assumptions on technical and financial data as mentioned below for Generation functions. 3.2 Assumptions Based on the current position of machine and gas availability of the existing Thermal Plants from various gas sources, M/c age factor, gas pricing, inflation trend etc., the fuel charges and fixed charges for LTPS & NTPS are projected and listed below. The CERC norm could not be followed in case of ageing NTPS, LTPS for indifferent mode of operation & frame sizes of the power stations. For KLHEP also CERC norms was found to be not applicable as the power project was commissioned after an inordinate delay of 25 years for which its project cost was not at par comparing with the norms of a Hydro Project’s having normal gestation period & commissioned in 2007. For NRPP, O&M cost have been considered as per DPR of the Power Projects. For all other APGCL Power Stations, Employees Cost and A&G Cost has been projected as per approved escalation rate of AERC in the Tariff Order of 2014-15. For Repair & Maintenance work 15% escalation rate has been considered. Note on Projected Auxiliary Power Consumption (APC) and Station Heat Rate (SHR) considered in the FY 2015-16 (a) Auxiliary Power Consumption (APC): Assam Power Generation Corporation Limited Page 22 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Years FY 12-13 FY 13-14 FY 2014-15 (Actual) Average Projected for FY 2015-16 Namrup TPS Aux. Power Cons. (%) Normative Aux. Power Cons. (%) 5.6% 4.5% 6.0% 4.5% 5.8% 4.5% 5.8% 4.5% 5.5% 4.5% Lakwa TPS with WHP Aux. Power Cons. (%) Normative Aux. Power Cons. (%) 11.5% 5.5% 8.8% 5.5% 8.6% 5.5% 9.7% 5.5% 7.5% 5.5% From the above table, it may be observed that the average actual Auxiliary Power Consumption (APC) for the last 3 years of both LTPS/NTPS found to be in higher side than the normative targets fixed by AERC. However, APGCL is constantly trying for reduction of APC to the extent possible. Following are the steps so far taken by APGCL as per recommendation of Energy Audit Report of NPC (National Productivity Council) ACTION TAKEN ON ENERGY AUDIT REPORT Lakwa Thermal Power Station (LTPS): The action taken against the recommendations of the Energy Audit Report of NPC along with other additional measures including the measures being taken for handing over the transformer feeders to AEGCL and APDCL at LTPS has been detailed below. Sl. NPC recommendation No. 1. 0.5% reduction in Instrument Air compressor(Cut off pressure is lowered to 6.2 kg/cm2 from 6.6kg/cm2) 2. Temperature inside the PH-I control room raised by 1°C 3. Temperature inside the PH-II control room raised by1°C 4. Indicating bulbs (2w) in the control panel ( Switch Yard replaced by 100 nos 0.5w LED bulbs 5. In PH-I control room: I) total 25 nos of FTLs (2x40W) replaced by 15 nos TS (62W) Bulbs II) Gas Turbine Floor: 48 nos Sodium Vapour Lamp (250W) replaced by 33 nos energy efficient Metal Halide (250W) bulbs Action Taken Action has been taken Action has been taken Action has been taken Action has been taken Action has been taken III) Gas Compressor Station: 20 nos 200W GLS Lamps replaced by 15 nos energy efficient Metal Halide 150W bulbs having more Lumens IV) Power House surrounding area: 30 Assam Power Generation Corporation Limited Page 23 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 6. nos (150W) Sodium Vapour Lamps replaced by 25 nos Metal Halide (150W) Lamps having more Lumens. PH-II Power House: i) 4 nos conventional (200W) bulbs replaced by CFL (20W) bulbs in machine compartments ii) 13 nos conventional (200W) bulbs replaced by CFL (20W) bulbs in Gas Compressor Station, 7. Action has been taken iii) 4 nos conventional (200W) bulbs replaced by CFL (20W) bulbs in Gas Intake and Metering Station. i) Colony Lighting: total 100 nos FTLs (40w) replaced by T5 (0.28W) bulbs, Action has been taken ii) Colony Lighting: total 6 nos 48W LED bulbs installed replacing 250W HPSV lamps, 8. Auxiliary consumption reduced by at least 0.2% by optimizing Gas Compressor running and diverting 0.4 to 0.6 MMSCMD gas to PH-I GTs Action has been taken from PH-Il Gas Compressors. (by not starting a gas compressor of rating: 525kw, 107A, 3.3KV, 0.85 pf for approx.10 days in a month.) 9. Skin Loss of GT#3 is minimized. Complete and new insulation will be Action has been taken done at the time of Major Overhauling which is already due. ADDITIONAL ENERGY SAVING MEASURES TAKEN AT LTPS Modification of cooling water line of Ph-II Gas Turbines for the following multifold benefits. I. 1 Reduction of auxiliary power consumption:- Both the fans and the running pump of each module are withdrawn after changeover to the new system resulting reduction of power consumption by the system considerably Action has been taken II. Availability of Gas and Steam Turbines: LTPS had to take shut down of GTs on failure of bearings of motors or fans, motor windings or pumps resulting in reduction of generation. During the period of October’12 to October’13 total Assam Power Generation Corporation Limited Page 24 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 cumulative period of outage of machine due to cooling water module problem was 139 hours. III. Capacity generation during summer season:-The machine loads had to reduce during high ambient temperature in summer season for restriction of high lube oil temperature. This reduction of GT’s load had cascading effect on STG loading. IV. Reduction of O&M cost: The O&M cost of age old cooling water module will be reduced substantially as the system will be remain as standby only. Others: Procurement of normative test checking equipment at LTPS 1 IRISYS Multipurpose Thermal Imager Model: IRI 4030 2 Pressure calibrator Make : FLUKE, USA Model :718300G Range : - 12 to 300 psi 3 Digital Photo Tachometer (Laser Type) Model : DT2234C 4 Boroscope KARL STORZ Endoskope Make: KARL STORZ Gmbh& Co. KG, 78532 Puttlingen, Germany. Measures to Control Transformer Loss 1 Used for non-contact temperature detection. Used for calibration of static and differential pressure transmitters. Used for non-contact speed detection Used for viewing of Gas turbine or machine internals which are otherwise cannot be seen from outside. Handing over of 33 kV transformer APGCL at present is operating and maintaining two nos. of 33 kV feeders at the LTPS switchyard. feeders to APDCL: APGCL is working on to handover these feeders to APDCL. In this connection, in the meeting held on 05/09/2012 at the Office Chamber of the Chairman, ASEB in presence of the officials from APGCL, AEGCL & APDCL, it was decided to take necessary action for handing over of 33 kV feeders to APDCL. The process of handing over these feeders to APDCL is in progress. The GM, LTPS vide his letter No. LTPS/GM/2014/T-93/2771 dated 09/12/14 has written to the GM, APDCL, Jorhat requesting him for a discussion on the mechanism for transfer of the 33 kV feeders from APGCL to APDCL. Accordingly the meeting was held on Feb’15 and processes of handing over the feeders are being initiated and completion is expected by Jun’15. Assam Power Generation Corporation Limited Page 25 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Namrup Thermal Power Station (NTPS) As the major Auxiliary Consumption loss in case of NTPS is observed in the switchyard, due importance has been given in handing over the relevant transformer feeders to AEGCL and APDCL. Along with this, other measures as per the comments/recommendations of the Energy Audit Report of NPC are also being taken for reducing APC loss. All this has been detailed below: Sl. Measures to Control APC No. Measures to Control Transformer Loss 1 Handing over of 6 nos. of 33 kV transformer feeders to APDCL Action Taken i. A meeting was held on 05/09/2012 at the Office Chamber of the Chairman, ASEB in presence of the officials from APGCL, AEGCL & APDCL where it was decided to take necessary action for handing over of the 220 kV, 132 kV, 66 kV and 33 kV feeders to AEGCL and APDCL respectively. ii. In another follow up meeting held between APDCL & APGCL on 02/02/2013 to discuss the modalities for the handover of the 33 kV system from APGCL to APDCL, it was informed by the APDCL authority that they are planning to construct a 33 kV substation at NTPS and the takeover of 33 kV feeders will be possible only after completion of the construction of the substation. iii. For this, in a separate communication, APDCL requested APGCL to provide land at NTPS for the construction of the said substation. The required land has been provided to APDCL and the same was informed to the CGM (D) vide letter no. APGCLCGM (G)/NTPS/APGCLAEGCL-APDCL/55/23 dated 24/07/2013. iv. In the meantime, six nos. of 33 kV breakers with terminal equipment were taken over by APDCL from 01/04/2013. v. In a meeting held on 16-08-2013 between the Senior Officers of the three Companies APGCL, APDCL and AEGCL, it was discussed that the tendering process for the shifting of the existing 33 kV system was going on and that the construction work was supposed to be completed by March’14. However, the work is not yet completed. vi. Construction of 132/33 kV APDCL substation is going on at NTPS. Transfer of the 6 nos. of 33 kV feeders to APDCL will be done after the commissioning of this substation. Assam Power Generation Corporation Limited Page 26 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 2 Handing over of 1 no. of 220 kV, 3 nos. i. of 132 kV and 6 nos. 66 kV transformer feeders to AEGCL ii. A meeting was held on 02/08/2013 between APGCL and AEGCL, where the modalities for the handover were discussed. The matter was also discussed in the meeting held on 16-08-2013 between the Senior Officers of the three Companies APGCL, APDCL and AEGCL, where it was decided that a detailed transfer scheme will be completed soon. iii. Further, APGCL has again requested AEGCL to complete the work at the earliest vide letter no. APGCL/CGM (G)/NTPS/APGCLAEGCL-APDCL/60/20 dated 31/03/2014 and vide letter dated 27/08/2014. iv. On 25/09/14 the following feeders/equipment along with the Control Room for operation of these feeders/equipment were handed over to AEGCL: a. 3 nos. of 66/132 kV auto transformers b. 1 no. of 132 kV Dibrugarh feeder c. 2 nos. of 132 kV Lakwa I & II feeders d. 2 nos. of 220 kV Tinsukia feeders along with 2 nos. of 220/132 kV transformers Action taken as per comments/recommendations of the Energy Audit Report by NPC 1 2 3 4 5 Minimization of the auxiliary consumption and improvement of power generation by modifying the illumination system by replacing the existing Filament bulbs, HPMV Lamps and fluorescent tubes with CFL/LED bulbs in phase-wise manner. Constant and strict monitoring of high current drawing auxiliaries such as, Cooling Water Pumps, Cooling Tower fans, Boiler Feed Pumps, Boiler Circulating Water Pumps etc. Regular checking of Boiler startup and Turbine Rolling timing up to synchronization to avoid unnecessary delay as far as practicable. Action has been taken Continuous monitoring is being done Continuous checking is being done Replacement age old motors of different pumps and Primary Oil Pumps with latest high efficiency energy saving motors. Action being taken Action to solve the problem of difference in temperature between the set temperature and actual temperature of the Action being taken Assam Power Generation Corporation Limited Page 27 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Control Room AC as observed by NPC. By taking above measures APGCL expect to reduce APC for NTPS from Current 5.8% [FY 2014-15 (Actual/Estimate)] to 5.5% and accordingly projected in the proposed tariff petition for FY 15-16. For LTPS basically the higher APC is due to consumption in the gas compressors. As the LTPS machines having heat rate almost double than the modern generating machines, it implies that the requirement of gas is also double in LTPS compared to similar generating capacity with the latest machines. Hence the capacity of gas compressor requirement is also enhanced to double attributing the higher APC. Also, as the pressure of gas supplied to LTPS is often lower than the agreed pressure by the supplier due to various reasons, the power consumed by the gas compressors also becomes higher due to extra work that has to be done by the compressors to increase the pressure to the rated pressure. This also contributes to higher APC of LTPS. By implementing the above measures APGCL expect to reduce APC for LTPS with WHU from Current 8.8% [FY 2014-15 (Actual/Estimate)] to 7.5% and accordingly projected in the proposed tariff petition for FY 15-16. Further, APGCL also put forwarded its comment in petition form on AERC’s draft notification on amendment on auxiliary consumption norms of NTPS and LTPS vide letter No: AERC/ CGM (G)/AERC/2013-14/115/Pt.-IX/19 Dtd. 21.08.14 appealing APC norms of 5.5% for NTPS and 7.5% for LTPS with WHU, which has been reproduced below. Assam Power Generation Corporation Limited Page 28 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Assam Power Generation Corporation Limited Page 29 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Assam Power Generation Corporation Limited Page 30 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Assam Power Generation Corporation Limited Page 31 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 In view of the above, the projections of APC for the FY 2015-16 have been summarized below: For Existing Power Projects: 1. Namrup TPS: APC of 5.5% has been considered based on the Petition of APGCL for review of the normative APC of NTPS & LTPS. 2. Lakwa TPS: APC of 7% for Open Cycle and 9.4% for WHU has been proposed as per DPR. Open Cycle APC of 7% has been considered for LTPS based on the Petition of APGCL for review of the normative APC of NTPS & LTPS. The overall APC for LTPS with WHU has been projected as 7.5%. 3. 63 MW NRPP: APC of 4.6% has been proposed for the GT by eliminating WHRU auxiliaries from the APC of 6.3% for NRPP taken from the approved DPR. 4. Karbi Langpi HEP: APC of 0.5% has been proposed as approved in Tariff Order for FY 201415. 5. Myntriang SHEP: APC of 1.0% has been proposed as approved in Tariff Order for FY 201415. (b) Station Heat Rate (SHR): APGCL has made all out efforts to operate its existing power plant to obtain optimum performance level to meet the operating norms fixed by AERC. However, due to fluctuation in supply of gas and intermittent under loading & outage of units due to technical reasons at times lead to higher GSHR in the past years for both LTPS & NTPS. To resolve the persistent higher heat rate issues of APGCL’s thermal power stations Hon’ble commission suggested that an institution like IIT / AEC may be approached for studying actual position of the generating stations the State Advisory Committee held on Dec’ 2012 and the report may be submitted to the Commission for review. Accordingly APGCL engaged IIT, Guwahati for the purpose and the report was submitted to AERC in Nov’13. Accordingly, Hon’ble Commission Notified Draft Amendment of Station Heat Rate of NTPS and LTPS on 31.07.14 as stated below: Station Approved (Previous) GSHR Amended GSHR (Kcal/kWh) (Kcal/kWh) - 4740 NTPS (Closed Cycle) 3266 LTPS(Open Cycle) LTPS (Closed Cycle) 3658 - 4170 4010 NTPS (Open Cycle) Assam Power Generation Corporation Limited 3200 Page 32 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Accordingly, APGCL considered Gross Station Heat Rate for NTPS with WHU as 4170 Kcal/Kwh and the Gross Station Heat Rate (open cycle) of 4010 kcal/kWh for LTPS as per AERC’s above draft notification. Gross Heat Rate for combined cycle operation has been derived with the projected generation of 171.12 MU for WHU as 3213 kcal/kWh as per the calculation given below: Gross Open Cycle Heat Rate of LTPS = Projected WHRU Generation of LTPS = Projected Total Generation of LTPS Gross Combined Cycle Heat Rate of LTPS 4010 kcal/kWh 171.12 MU = 861 MU = 4010 X [1-(171.12/861)] kcal/kWh = 3213 kcal/kWh Basis of projection of Generation of Waste Heat Recovery Unit # 8 of LTPS The average generation pattern of WHRU from FY2012-13 to September 2014-15 is 43% of the generation of Ph.-II Units # 5, 6 & 7. Accordingly for the FY 2015-16 the generation of WHRU has been projected considering above trend of 43% in respect to projected Ph.-II units’ generation of LTPS. Gas supply matters: The Gas Linkage for the existing Gas Plants of APGCL (LTPS & NTPS) is shown as under: 1. 2. LTPS → APM 0.40 MMSCMD from GAIL → Non-APM 0.5 MMSCMD from OIL NTPS→ APM 0.66 MMSCMD from OIL. Gas supply Position: Gas received during the FY 2013-14 are as under: LTPS = 296.00 MMSCM. NTPS = 225.90 MMSCM. The actual Gas supply for the FY 2014-15 are as under: LTPS = 291.17 MMSCM. NTPS = 250.25MMSCM. Projected Gas availability in the FY 2015-16 BCPL is expected to be commissioned in 2015-16. Earlier after commissioning of BCPL, APGCL was expected to get lean gas with lower CV. However, after assurance from the gas suppliers of APGCL for keeping the same CV of the supplied gas even after commissioning of BCPL, the avg. GCV of gas from 2011-12 to September 2014 has been considered for Generation Projection for 2015-16. The details of the gas availability for 2015-16 are given in the table below: Station Period NTPS 2015-16 LTPS 2015-16 Gas Source OIL APM GAIL APM Avg GCV from 2011-12 to Sep’14 in kcal/scm Contracted Availability Quantity (MMSCMD) (MMSCMD) 9300 0.66 0.66 9793 0.40 0.40 Assam Power Generation Corporation Limited Remarks Page 33 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Apr-Oct Nov-Mar 0.35 OIL NonAPM 9300 0.50 0.45 Gas availability from OIL to LTPS has been considered as per site experience Assumptions for various Heads – I Table 19: 2015-16 14.75% ST PLR R & M Expenses Employee Expenses A & G Expenses ROE escalation rates Other Income Provision for Taxes Provision for Bad and Doubtful Debts % of revenue Current Assets - per Actual O&M Expenses Mainranence spares Receivable against sale of power Current Assets - per AERC O&M Expenses & fuel Maintenance spares Receivable against sale of power Power purchase Payable Depreciation rate applicable for Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Lines & Cable Network Vehicles Furniture & fixture Office equipment Roads on land Belonging to others Capital spares at generating stations Cap of Asset Value 15.00% 8.42% 8.42% 14.00% @ 10% escalation at approved by Hon'ble AERC 0.00% On annual Expenditure 1% of Gross Block On the total revenue demand On annual Expenditure 1% of Gross Block On the total revenue demand Thermal 0.00 1.80% 2.57% 1.80% 6.00% 2.57% 18.00% 6.00% 6.00% 1.80% 4.75% 90.00% Hydel 0.00 1.80% 2.57% 1.80% 2.57% 2.57% 18.00% 6.00% 6.00% 1.80% 4.75% 90.00% Loan Rates - New Loan Assam Power Generation Corporation Limited Page 34 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Institution 11.40% Existing Loans Rates of interest State Govt 10.50% @ different agreement rates 11.40% PFC Other Loan Repayment Govt Loan PFC Others 15.20 22.97 0.00 Thermal O & M for new stations on commercial startup year subsequently @ inflation Interest rate for investment income Hydel 5.72% O & M for new stations on commercial startup year subsequently @ inflation Interest rate for investment income 5.72% Table 20 Assumptions for various heads – II INVESTMENT PROPOSED FOR 2015-16 NTPS LTPS KLHEP Construction of a new water intake pump house at Dilli river for consumptive water SOURCE PROPOSED (RS. IN CR) State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others 3.80 20.62 5.38 2.42 State Govt. equity State Govt. Loan 17.00 State Govt. Grant Assam Power Generation Corporation Limited Page 35 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 requirement of existing plant and Namrup Replacement Project. NRPP LRPP CACHAR DISTRIBUTED GENERATION SYSTEM BY GAS IC ENGINE EPC contrct for 2.0 MW Solar Power Project at NTPS EPC contrct for 2.0 MW Solar Power Project at LTPS Procurement/Acquisition of land for Titabor Gas Based Power Project MYNTRIANG LOWER KOPILI 21 MW Karbi Langpi Middle Stage-I 24 MW Karbi Langpi Middle Stage-II PFC Loan Others State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others Assam Power Generation Corporation Limited 160.00 54.90 78.60 3.80 0.83 16.86 17.00 17.00 0.49 8.12 23.50 183.00 7.00 0.25 0.25 Page 36 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 12 MW KLHEP Barrage Toe Project 60 MW Karbi Langpi Upper Stage Installation of deep tube well with submersible pump set for water supply at BKV Investigation Division Colony, Jagiroad TOTAL PROPOSED INVESTMENT State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others 0.25 0.25 State Govt. Equity State Govt. Loan 0.05 State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others Total 249.82 88.85 27.23 160.00 95.46 621.36 3.3. Projected Operating Performance Data for FY15-16. It is expected to continue the current rising trend of generation due to improvement in gas supply position of NTPS and LTPS and machines heath conditions of NTPS the station wise operating performance data are projected as shown in the following table. For KLHEP we have assumed the designed energy as generation target for this FY. Assumptions considered for projecting Operating Performance for 2015-16 are: a) Availability: Availability for Thermal Generation has been computed on the basis gross generation & projected Aux. cons. as per the formula below: Availability = Projected Gross Generation in MW / {total hours in a year X Installed Capacity in MW X (1-Projected Power as Consumption in %)} % For Hydro stations, availability has Auxiliary been considered per design data. b) Planned Outages: Details of Planned and Forced Outages Considered: i. For NTPS and LTPS, Planned outage has been considered as per the Maintenance Schedules for the year 2015-16 of the respective Power Stations. ii. In KLHEP, maintenance is carried out during the lean period and thus, it does not affect the generation of KLHEP. Hence, for projecting generation of KLHEP, design generation data has been considered. c) PLF: Plant Load Factor has been computed on the basis of gross generation as per the formula below: PLF = Projected Gross Generation in MW / Table (total hours 18 in a year X Installed Capacity in MW) % Assam Power Generation Corporation Limited Page 37 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 d) Gross Energy: Gross energy generation has been projected after considering Planned Maintenance of units, Unit Load factors and as per the Gas availability mentioned above at Page No. 33. Further, in case of NRPP, the PLF as mentioned in the DPR is 72%. However, this was calculated by considering lean gas availability after commissioning of BCPL. As the gas suppliers of APGCL has assured that they are going to maintain the present CV of gas even after commissioning of BCPL, the Gross energy from NRPP has been projected at 80% PLF as per the AERC norms for new thermal power projects. For calculating the Gross energy of NTPS old units after commissioning of 63 MW NRPP GT in Aug’15, 2 nos. of GT units from the old power station and the Waste Heat Unit No. 6 with a combined capacity of 63.5 MW (20 MW Unit #1 + 21 MW Unit #2 + 22.5 MW Unit #6) has been considered to be run with the daily average available gas of 0.29 MMSCMD left after using daily average gas of 0.37 MMSCMD by the GT unit of NRPP at a yearly PLF of 80%. For Hydro generating station, Gross Energy Generation has been considered as per design energy. e) Auxiliary Consumption: As mentioned in the Section 3.2 (a) above at Page No. 22 to 32. f) Gross Station Heat Rate: Gross Station Heat Rates for LTPS & NTPS have been considered as per the draft amendment of the AERC (terms and Conditions for Determination of Tariff) Regulations 2006, which are 4010 kcal/kWh for LTPS Open Cycle operation and 4170 kcal/kWh for NTPS combined cycle operation respectively. Table 21 Generation Projection for FY 2015-16 NTPS from Apr'15-July'15 Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) Gross Station Heat Rate on GCV (Kcal/ Kwh) Sp. Gas Consumption (SCM/Kwh) NTPS with units 1,2 & 6 from Aug'15 to Mar'16 Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) Gross Station Heat Rate on GCV (Kcal/ Kwh) Sp. Gas Consumption (SCM/Kwh) Total NTPS for 2015-16 Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) Gross Station Heat Rate on GCV (Kcal/ Kwh) Sp. Gas Consumption (SCM/Kwh) NRPP 63 MW GT from Aug'15 Gross Energy in MU Assam Power Generation Corporation Limited FY 15-16 179.17 5.5% 169.36 54% 51% 4170 0.4484 FY 15-16 163.81 5.5% 154.80 47% 44% 4044 0.4348 FY 15-16 342.98 5.5% 324.16 51% 48% 4110 0.4419 FY 15-16 295.14 Page 38 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) Gross Station Heat Rate on GCV (Kcal/ Kwh) Sp. Gas Consumption (SCM/Kwh) LTPS with WHRU Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) Gross Station Heat Rate on GCV (Kcal/ Kwh) Sp. Gas Consumption (SCM/Kwh) KLHEP Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) Myntriang SHEP St-II Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) Myntriang SHEP St-I Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) APGCL APGCL Total Gross Generation (MU) APGCL APC (%) APGCL Total Net Generation (MU) Availability (%) PLF (%) 4.6% 281.57 84% 80% 2830 0.3043 FY 15-16 861.00 7.5% 796.62 68% 63% 3213 0.3365 FY 15-16 390.00 0.5% 388.05 90% 45% FY 14-15 22.68 1.00% 22.45 91% 81% FY 14-15 18.91 1.0% 18.72 91% 81% FY 15-16 1930.71 5.13% 1831.57 72% 59% Comparison of Approved Generation for 2015-16 in the MYT Order for 2013-14 to 2015-16 and Revised Generation Projection for 2015-16 Total Generation Approved in the MYT Order for 2015-16 was 2200.35 MU. New projects considered were: 1. 100 MW NRPP: The Project was earlier expected to be commissioned in 2013-14. Annual energy approved for 2015-16 in the MYT from NRPP was 622.32 MU. However, due to delay in project work, now the 63 MW GT unit of the project is expected to be commissioned in August'15. 2. 70 MW LRPP: The project was earlier expected to be commissioned in 2015-16. Annual energy approved for the project in the MYT for 2015-16 was 415.80 MU. However, due to delay in the completion of the bidding process, the project is now expected to be commissioned after 2015-16. Assam Power Generation Corporation Limited Page 39 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 3. 6 MW Lungnit PP: The St-I of the project was earlier expected to be commissioned in 201415 and the St-II in 2015-16. Annual energy approved for the project in the MYT for 2015-16 was 26.74 MU. However, due to cancellation of the agreement with the EPC contractor for slow progress of work and litigations arising thereafter, now the project is not expected to be commissioned in 2015-16. 4. Myntriang SHEP St-I: The project was earlier expected to be commissioned in 2014-15. Annual energy approved for the project in the MYT for 2015-16 was 45.77 MU. However, due to delay in project work, the project is now expected to be commissioned in December'15 with generation of 19 MU of energy. This includes 3.5 MU from 3 MW enhancement of the St-I project. Because of the above, the Generation Projection for the FY 2015-16 has to be revised from the approved energy of 2200.35 MU to 1930.71 MU 3.4. Projected Financial Performance Data for FY 15-16 3.4.1 Employees Expenses Table 22 Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 2015-16 48.21 2.07 39.33 7.38 0.04 0.13 0.07 0.36 0.00 0.00 0.19 14.41 112.19 6.92 105.27 Note: The Hon’ble Commission approved an amount of Rs. 91.42 Crore towards employees cost in the MYT Order 13-16, however the Employee expenses for FY 14-15 in actual up to 2nd quarter and proportionate for 3rd and 4th quarter comes to Rs. 86.54 Crore. On escalating the same with an escalation factor @ 8.42% the total employees cost comes to Rs (86.54*108.42%=) 93.83 Crore. In addition to this Myntriang SHEP is expected to operate at full capacity considering enhanced capacity of 4.5 MW from Dec’15 which increases the employees cost proportionately by Rs. 2.35 Crore. Further the NRPP is proposed to be commissioned in the FY 15-16 (from August’15). The existing Namrup TPS is proposed to be operated simultaneously along with the NRPP with the left over gas utilizing units, 1, 2 & Waste Heat Unit 6. The balance units 3, 4 & 5 will be kept as standby to run at the event of excess gas availability and unscheduled outage of NRPP. Hence, the existing manpower of NTPS cannot be disturbed and cannot be spared for NRPP. New recruitment will be made for NRPP by creation of required post which is projected at Rs. 16.01 Crore (figure calculated as per DPR), thereby totaling the Employees cost at Rs (93.83+2.35+16.01)=Rs. 112.19 Crore. After capitalizing the figures comes to Rs.105.27 Crore. Assam Power Generation Corporation Limited Page 40 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 3.4.2 Repairs & Maintenance Table 23 Particulars 2015-16 A. Regular Repair & Maintenance:Plant & Machinery 16.95 B. Special Type Repair & Maintenance:Overhauling Works under plant & Machinery (details as follows) Total Plant & machinery (A+B) Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: 32.00 48.95 0.31 0.35 1.26 0.11 0.30 0.16 0.23 1.62 0.26 53.55 Note: 1. In the above consolidated projection of Repair & Maintenance (R&M) of APGCL, the NTPS component of R&M works amounting to Rs. 2.65 Cr. has been computed on the following modalities: Rs. in Cr. All units NTPS (119.5 MW) running till July'15 till commissioning of NRPP Unit 1 & 2 & 6 (63.5 MW) running from Aug'15 to March'16 with the left over gas after consumption in NRPP Standby unit 3, 4 & 5 (56 MW) from Aug'15 to March’16 for running in case of excess gas availability & unscheduled outage of NRPP. Total 0.88 0.94 0.83 2.65 2. APGCL feels that an escalation @ 8.42 % for Repair & maintenance expenses is on a lower side, taking an account of requirement of APGCL and old age of power stations, an escalation taken @ 15% on R&M projected for FY 15-16 is considered on Regular R&M works 3. Special Type Repair & Maintenance: To keep the generating machines in healthy and running conditions, we have to carry out the Major Overhauling (O/H), as per the OEM’s (Original Equipment Manufacturer) Operation Manual. 4. The details units of NTPS and LTPS which are proposed to be overhauled in FY 2015-16 as per OEMs recommendation are stated below: Station NTPS Unit 1 Description Amount (Rs. in Cr) Procurement of capital spares for Turbine unit-1 of NTPS 6.00 Work Component for Major Overhauling 0.00 Assam Power Generation Corporation Limited Page 41 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Total 6.00 3 Procurement of capital spares for Gas Turbine unit-3 of NTPS 6.00 Work Component for Major Overhauling 0.00 Total 6.00 6 Procurement of capital spares for Gas Turbine unit-6 of NTPS 2.00 Work Component for Major Overhauling 0.00 Total 2.00 14.00 Total NTPS 3 LTPS Procurement of capital spares for Gas Turbine unit-3 of phase I of LTPS. 17.50 Major Inspection/ Overhauling of Gas Turbine unit No. 3 of LTPS 0.50 Total 18.00 18.00 32.00 Total LTPS Grand Total APGCL proposed this Special type of above Repair & Maintenance cost amounting to Rs. 32.00 Cr. for consideration under Operation & maintenance (O&M) as a special case to keep these machines smooth running condition to enable to contribute power to the state of Assam to mitigate shortfall of power to the extent feasible. The details of unit wise running hours, since from the last overhauled, which justifies the OEM’s recommendation are furnished below: The Running hours since last overhauling of the units of LTPS and NTPS are: STATION UNIT LAST MAJOR INSPECTION (DATE/HR) RUNNING HOURS SINCE LAST MAJOR OVERHAULING AS ON 30/11/14 MAJOR OVERHAULING REQUIRED AT RUNNING HOURS AS PER OEM MANUAL #1 DATE- 10.09.13 / HR-148616 7530 28000 48965 28000 Major Overhauling Originally proposed in 2014-15. Now, scheduled in 2015-16. Amount already approved in the Review Order of 2013-14 and also in the Tariff Order of 2014-15. Action has already been initiated. LC opened and materials in transit. Materials likely to be reached at site by March’15 and overhauling will be done in the period Apr’15- LTPS #2 DATE- 14.07.07 / HR-128496 Assam Power Generation Corporation Limited Page 42 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 May’15 28000 Major Overhauling proposed in 2015-16 #3 DATE-29.11.04/ HR-1,02,835 48957 #4 DATE-25.08.10/ HR-55,357 28057 28000 #5 DATE-24.02.2014/ HR-80414 6690 32000 hrs to 48000 hrs depending on hot gas path inspection intervals 32000 hrs to 48000 hrs depending on hot gas path inspection intervals #6 DATE-31.03.2008/ HR-72886 44945 #7 Completed on 03/12/14 RH-84886 Major Overhauling completed in 2014-15 32000 hrs to 48000 hrs depending on hot gas path inspection intervals #1 DATE-10.10.2009/ HR-280666 39185 28000 Major Overhauling proposed in 2015-16 #2 DATE-26.06.13/ HR-260286 9349 28000 #3 DATE-20.08.10/ HR-294667 28750 28000 Major Overhauling proposed in 2015-16 #4 DATE-09.09.14/ HR-133220 Major Overhauling completed in 2014-15 28000 #5 DATE-17.06.10 (Forced shutdown due to Stator Problem)/ HR-209439 15647 75000 #6 DATE-May-01/ HR-164039 95924 75000 Major Overhauling proposed in 2015-16 NTPS Major Overhauling is scheduled in 2015-16. Amount already approved in the Annual Plan of 2014-15. Also included in the R&M DPR of 2013-14 to 201415 submitted to AERC From the above table it can be seen that the following overhauling has been proposed in the FY 2015-16: LTPS Unit-3: The last Major Overhauling of Unit 3 of LTPS was done on 29/11/04. Since then the unit has been in operation for 48957 hours till 30/11/14. As per the OEM’s guideline for WCL model W191 i.e. for Unit # 3, the overhauling hours may be extended up to 35,000 against the recommended 28,000. Assam Power Generation Corporation Limited Page 43 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Details of LTPS’ GT Units # 3 running hrs from the last overhauling justifying the need of Major overhauling as per OEM’s recommendations. GT UNIT LAST MAJOR INSPECTION (DATE/HR) LTPS #3 DATE-29.11.04/ HR-1,02,835 RUNNING HOURS SINCE LAST MAJOR OVERHAULING AS ON 30/11/14 48,957 (Major O/H is overdue) Hence major overhauling is overdue for Unit # 3 to ensure smooth operation of the generating Unit and it is proposed in Jul’15-Aug’15 for 50 days. The cost-benefit analysis of this overhauling has been calculated and given is below: Assam Power Generation Corporation Limited Page 44 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Cost Benefit Analysis for Major Overhauling of Unit #3 of LTPS: PROJECT: Major overhauling of LTPS Unit-3 PROJECT COST: Loan Interest rate for short term loan Rate (WACC) Project Life 18.00 18.00 15.00% 10.14% 4 Escalation of Annual O & M Depreciation : 8.42% 22.50% (Rs. in Cr) 1.NPV Evaluation No. of years ACQUISITI Fuel Cost ON COST FY 1 2 1 2 3 4 4 2015-16 2016-17 2017-18 2018-19 2018-19 3 18.00 Scrap value 18.00 ANNUAL O&M 4 5 6 7=3+4+5+6 ANTICIPAT EARNINGS PROVISIO PROFIT ED BEFORE N FOR AFTER TAX REVENUE TAXES TAXES 8 9=8-7 37.00 37.01 37.02 37.03 0.45 0.49 0.53 0.57 4.05 4.05 4.05 4.05 1.80 59.50 41.55 41.60 41.66 1.80 - 44.35 45.52 45.29 45.06 (15.15) 3.97 3.69 3.40 148.07 2.04 18.00 186.11 180.22 (4.10) Since NPV 2. IRR: DEPRECIA TOTAL TION EXPENSES > 10 11=9-10 0.00 0.00 0.00 0.00 - OPERATIN NPV OF G CASH OP. CASH FLOW FLOW 12=11+6 15 (15.15) 3.97 3.69 3.40 (11.10) 8.02 7.74 7.45 (11.10) 7.28 6.38 5.58 (4.10) 12.10 8.13 0, the major overhauling is accepted. FW OF CASH FLOW Year n 1 2 3 4 (11.10) 7.28 6.38 5.58 (11.10) 8.02 7.74 7.45 49.11% Assam Power Generation Corporation Limited Page 45 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 SOP determination from Major overhauling of LTPS Unit-3 Project cost Loan Equity 18.00 18.00 0.00 1 Annual O&M Interest and finance Charges depreciation Fixed charges Interest on working capital return on equity Fuel Cost Sale of Power (A+B+C) A B C D E 0.45 1.35 4.05 5.85 1.55 0.00 37.00 44.35 2 0.49 2.43 4.05 6.97 1.58 0.00 37.01 45.52 3 0.53 2.16 4.05 6.74 1.57 0.00 37.02 45.29 4 0.57 1.89 4.05 6.51 1.57 0.00 37.03 45.06 Note: 1 2 3 4 5 6 Depreciation @ 22.50% has been taken for evaluation purpose i.e 90%/4 Interest on short term loan 15% Annual O&M for the initial year of operation is taken at 2.5% of the project cost. O&M Escalation @ 8.42% Tax @ 32.4% Discounting factor (WACC) 10.14 % WACC=Rd*(1-t)*D/V+ Re*E/V where; Rd- cost of debt Re- cost of equity E/V- percentage of financing that is equity D/V- percentage of financing that is debt t- tax rate 7 Repayment of loan considered to be paid during the life of the project. 8 Estimated actual fuel cost computed is considered for revenue/ SOP determination NTPS Unit-1: The last Major Overhauling of Unit 1 of NTPS was done on 10.10.2009. Since then the unit has been in operation for 39185 hours till 30/11/14. As per the OEM’s guideline for Unit # 1, the overhauling hours is 24000 hrs. Details of NTPS’ GT Units # 1 running hrs from the last overhauling justifying the need of Major overhauling as per OEM’s recommendations. GT UNIT LAST MAJOR NSPECTION (DATE/HR) RUNNING HOURS SINCE LAST MAJOR OVERHAULING AS ON 30/11/14 NTPS #1 DATE-10.10.2009/ HR-280666 39185 (Major O/H is overdue) Hence major overhauling is overdue for Unit # 1 to ensure smooth operation of the generating Unit and it is proposed in Jun’15-Jul’15 for 60 days. The cost-benefit analysis of this overhauling has been calculated and is given below: Assam Power Generation Corporation Limited Page 46 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Cost Benefit Analysis for Major Overhauling of Unit #1 of NTPS: PROJECT: Major overhauling of NTPS Unit-1 PROJECT COST: 6.00 Loan 6.00 Interest rate for short term loan 15.00% Rate (WACC) 10.14% Project Life 4 Escalation of Annual O & M 8.42% Depreciation : 22.50% (Rs. in Cr) 1.NPV Evaluation No. of years 1 FY 2 1 2015-16 2 2016-17 3 2017-18 4 2018-19 4 2018-19 ACQUISITI ON COST 3 6.00 Scrap value 6.00 2. IRR: Fuel Cost ANNUA L O&M 4 62.04 62.07 62.10 62.12 5 0.15 0.16 0.18 0.19 248.34 0.68 Since NPV > Year n 1 2 3 4 DEPRECIA TION TOTAL EXPENSES 6 7=3+4+5+6 69.54 63.58 63.62 63.66 0.60 1.35 1.35 1.35 1.35 0.60 ANTICIPAT ED REVENUE 8 66.36 66.77 66.72 66.67 6.00 261.02 266.51 0, the major overhauling is accepted. FW OF CASH FLOW (1.84) (1.84) 3.58 3.94 3.20 3.88 2.86 3.82 205.78% EARNIN GS BEFORE TAXES 9=8-7 (3.19) 3.18 3.09 3.00 6.09 PROVISI ON FOR TAXES PROFIT AFTER TAX 10 11=9-10 (3.19) 2.59 2.53 2.47 0.00 0.59 0.56 0.53 1.69 4.40 Assam Power Generation Corporation Limited OPERATI NG CASH FLOW NPV OF OP. CASH FLOW 12=11+6 (1.84) 3.94 3.88 3.82 15 (1.84) 3.58 3.20 2.86 9.80 7.79 Page 47 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 SOP determination from Major overhauling of NTPS Unit-1 A B C D E Project cost Loan Equity 6.00 6.00 0.00 Annual O&M 1 0.15 2 0.16 3 0.18 4 0.19 0.45 1.35 1.95 2.36 0.00 62.04 66.36 0.81 1.35 2.32 2.37 0.00 62.07 66.77 0.72 1.35 2.25 2.37 0.00 62.10 66.72 0.63 1.35 2.17 2.37 0.00 62.12 66.67 Interest and finance Charges depreciation Fixed charges Interest on working capital return on equity Fuel Cost Sale of Power (A+B+C) Note: 1 2 3 4 5 6 Depreciation @ 22.50% has been taken for evaluation purpose i.e 90%/4 Interest on short term loan 15% Annual O&M for the initial year of operation is taken at 2.5% of the project cost. O&M Escalation @ 8.42% Tax @ 32.4% Discounting factor (WACC) 10.14 % WACC=Rd*(1-t)*D/V+ Re*E/V where; Rd- cost of debt Re- cost of equity E/V- percentage of financing that is equity D/V- percentage of financing that is debt t- tax rate 7 Repayment of loan considered to be paid during the life of the project. 8 Estimated actual fuel cost computed is considered for revenue/ SOP determination NTPS Unit-3: The last Major Overhauling of Unit 3 of NTPS was done on 20.08.10. Since then the unit has been in operation for 28750 hours till 30/11/14. As per the OEM’s guideline for Unit # 3, the overhauling hours is 24000 hrs. Details of NTPS’ GT Units # 3 running hrs from the last overhauling justifying the need of Major overhauling as per OEM’s recommendations. LAST MAJOR NSPECTION RUNNING HOURS SINCE LAST MAJOR GT UNIT (DATE/HR) OVERHAULING AS ON 30/11/14 28750 DATE-20.08.10/ NTPS #3 (Major O/H is overdue) HR-294667 Hence major overhauling is overdue for Unit # 3 to ensure smooth operation of the generating Unit and it is proposed in Nov’15-Dec’15 for 60 days. The cost-benefit analysis of this overhauling has been calculated and is given below: Assam Power Generation Corporation Limited Page 48 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Cost Benefit Analysis for Major Overhauling of Unit #3 of NTPS: PROJECT: Major overhauling of NTPS Unit-3 PROJECT COST: 6.00 Loan 6.00 Interest rate for short term loan 15.00% Rate (WACC) 10.14% Project Life 4 Escalation of Annual O & M 8.42% Depreciation : 22.50% 1.NPV Evaluation No. of years 1 1 2 3 4 4 2. IRR: FY 2 2015-16 2016-17 2017-18 2018-19 2018-19 ACQUISITI ON COST Fuel Cost ANNUA L O&M 3 6.00 4 40.72 40.73 40.75 40.77 5 0.15 0.16 0.18 0.19 Scrap value 6.00 162.97 Since NPV > 0.68 DEPRECIATI ON TOTAL EXPENSE S 6 1.35 1.35 1.35 1.35 0.60 7=3+4+5+6 48.22 42.25 2.28 2.31 .60 8 44.24 44.64 44.58 44.52 6.00 175.65 177.98 0, the major overhauling is accepted. Year n 1 2 3 4 ANTICIPATE D REVENUE (2.63) 3.09 2.76 2.46 EARNING S BEFORE TAXES 9=8-7 (3.98) 2.39 2.30 2.21 2.92 PROVISIO N FOR TAXES PROFIT AFTER TAX 10 11=9-10 (3.98) 2.05 1.99 1.93 0.00 0.34 0.31 0.28 0.92 2.00 OPERATIN G CASH FLOW 12=11+6 (2.63) 3.40 3.34 3.28 7.40 Rs Cr NPV OF OP. CASH FLOW 15 (2.63) 3.09 2.76 2.46 5.67 FW OF CASH FLOW (2.63) 3.40 3.34 3.28 115.46% Assam Power Generation Corporation Limited Page 49 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 SOP determination from Major overhauling of NTPS Unit-3 A B C D E Project cost Loan Equity 6.00 6.00 0.00 Annual O&M 1 0.15 2 0.16 3 0.18 4 0.19 0.45 1.35 1.95 1.57 0.00 40.72 44.24 0.81 1.35 2.32 1.58 0.00 40.73 44.64 0.72 1.35 2.25 1.58 0.00 40.75 44.58 0.63 1.35 2.17 1.58 0.00 40.77 44.52 Interest and finance Charges depreciation Fixed charges Interest on working capital return on equity Fuel Cost Sale of Power (A+B+C) Note: 1 2 3 4 5 6 Depreciation @ 22.50% has been taken for evaluation purpose i.e 90%/4 Interest on short term loan 15% Annual O&M for the initial year of operation is taken at 2.5% of the project cost. O&M Escalation @ 8.42% Tax @ 32.4% Discounting factor (WACC) 10.14 % WACC=Rd*(1-t)*D/V+ Re*E/V where; Rd- cost of debt Re- cost of equity E/V- percentage of financing that is equity D/V- percentage of financing that is debt t- tax rate 7 Repayment of loan considered to be paid during the life of the project. 8 Estimated actual fuel cost computed is considered for revenue/ SOP determination NTPS Unit-6: The last Major Overhauling of Unit 6 of NTPS was done on May-01. Since then the unit has been in operation for 95924 hours till 30/11/14. As per the OEM’s guideline for Unit # 6, the overhauling hours is 75000. Details of NTPS’ GT Units # 6 running hrs from the last overhauling justifying the need of Major overhauling as per OEM’s recommendations. LAST MAJOR NSPECTION RUNNING HOURS SINCE LAST MAJOR GT UNIT (DATE/HR) OVERHAULING AS ON 30/11/14 95924 DATE-May-01/ NTPS #6 (Major O/H is overdue) HR-164039 Hence major overhauling is overdue for Unit # 6 to ensure smooth operation of the generating Unit and it is proposed in Aug’15-Sep’15 for 60 days. The cost-benefit analysis of this overhauling has been calculated and is given below: Assam Power Generation Corporation Limited Page 50 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Cost Benefit Analysis for Major Overhauling of Unit #6 of NTPS: PROJECT: Major overhauling of NTPS Unit-6 PROJECT COST: 2.00 Loan 2.00 Interest rate for short term loan 15.00% Rate (WACC) 10.14% Project Life 4 Escalation of Annual O & M 8.42% Depreciation : 22.50% 1.NPV Evaluation No. of years 1 1 2 3 4 4 FY 2 2015-16 2016-17 2017-18 2018-19 2018-19 ACQUISI TION COST Fuel Cost 3 4 2.00 Scrap value 2.00 2. IRR: ANNUA L O&M 5 0.05 0.05 0.06 0.06 - Since NPV> 0.23 Year DEPRECIATI ON TOTAL EXPENSE S 6 0.45 0.45 0.45 0.45 0.20 7=3+4+5+6 2.50 0.50 0.51 0.51 0.20 ANTICIPAT ED REVENUE 8 0.67 0.80 0.77 0.75 2.00 4.23 2.98 0, the major overhauling is accepted. FW OF CASH FLOW n 1 (1.38) (1.38) 2 0.67 0.74 3 0.59 0.71 4 0.51 0.68 25.93% EARNIN GS BEFORE TAXES 9=8-7 (1.83) 0.29 0.26 0.23 (1.04) PROVISI ON FOR TAXES PROFIT AFTER TAX 10 0.00 0.00 0.00 0.00 11=9-10 (1.83) 0.29 0.26 0.23 - (1.04) Assam Power Generation Corporation Limited OPERATI NG CASH FLOW 12=11+6 (1.38) 0.74 0.71 0.68 0.76 (Rs. in Cr) NPV OF OP. CASH FLOW 15 (1.38) 0.67 0.59 0.51 0.39 Page 51 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 SOP determination from Major overhauling of NTPS Unit-6 A B C D E Project cost Loan Equity 2.00 2.00 0.00 Annual O&M 1 0.05 2 0.05 3 0.06 4 0.06 Interest and finance Charges depreciation Fixed charges Interest on working capital return on equity Fuel Cost Sale of Power (A+B+C) 0.15 0.45 0.65 0.02 0.00 0.00 0.67 0.27 0.45 0.77 0.02 0.00 0.00 0.80 0.24 0.45 0.75 0.02 0.00 0.00 0.77 0.21 0.45 0.72 0.02 0.00 0.00 0.75 Note: 1 2 3 4 5 6 Depreciation @ 22.50% has been taken for evaluation purpose i.e 90%/4 Interest on short term loan 15% Annual O&M for the initial year of operation is taken at 2.5% of the project cost. O&M Escalation @ 8.42% Tax @ 32.4% Discounting factor (WACC) 10.14 % WACC=Rd*(1-t)*D/V+ Re*E/V where; Rd- cost of debt Re- cost of equity E/V- percentage of financing that is equity D/V- percentage of financing that is debt t- tax rate 7 Repayment of loan considered to be paid during the life of the project. 8 Estimated actual fuel cost computed is considered for revenue/ SOP determination Assam Power Generation Corporation Limited Page 52 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 3.4.3 Administration and General Expenses Table 24 Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegram Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses Energy bill raised by APDCL Sub Total: Less: Capitalised Total: 2015-16 0.39 0.94 0.06 0.00 0.01 0.00 0.71 0.00 0.00 0.78 0.02 7.64 0.00 10.56 0.70 9.85 Note: Escalation taken @ 8.42% for A&G expenses 3.4.4 Return on Equity Table 25 Particulars Namrup TPS Lakwa TPS Lakwa WHRP Karbi Langpi HEP Myntriang SHEP Namrup RPP Total 2015-16 10.16 11.50 9.93 9.54 3.27 14.57 58.96 ROE calculated as follows: Particulars Opening Equity Closing Equity Average equity Rate ROE NTPS 15-16 69.44 75.68 72.56 0.14 10.16 LTPS 15-16 79.24 84.98 82.11 0.14 11.50 KLHEP 15-16 68.11 68.11 68.11 0.14 9.54 LWHRP 15-16 70.92 70.92 70.92 0.14 9.93 NRPP 15-16 0.00 208.12 104.06 0.14 14.57 Myntriang 15-16 13.37 33.34 23.35 0.14 3.27 3.4.5 Income from Other Sources Table 26 Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: 2015-16 0.00 8.85 0.06 0.79 0.90 0.01 10.60 Assam Power Generation Corporation Limited Page 53 of 228 Total 15-16 301.08 541.14 421.11 0.14 58.96 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Note: Other income incurred in FY 2013-14 is considered at par for FY 2015-16 3.4.6. Depreciation Table 27 Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & fixtures Office equipment Roads on land belonging to others Capital spares at generating stations Total (Less) : Depreciation on 90% of the Assets funded by Grants/subsidies Net Total 2015-16 0.00 0.74 4.41 3.59 39.43 5.21 1.06 0.12 0.16 0.06 0.00 3.56 58.35 -10.14 48.21 Depreciation has been calculated using the schedule as prescribed by the AERC. Analysis of the trial balance under each function head has been carried out and the weighted average rate has been calculated and used for calculation. Depreciation on assets commissioned in a year is charged at the average balance for the year (since they could be commissioned at different date). 3.4.7 Interest & financing charges Table 28 Particulars 2015-16 Interest on loans 69.20 Other finance charges 6.43 Sub total 75.63 Less: Interest capitalised -19.75 Total 55.88 Note: Interest on loans & Other Finance Charges calculated for FY 14-15 @ 10.5% on loan outstanding for Loan from Govt. of Assam, @ previous interest rates charged by PFC for Loan from PFC. GPF trust is expected to complete in FY 15-16 and hence interest on GPF is claimed from FY 15-16 3.4.8 Interest on Working Capital Table 29 Particulars One month Fuel Cost One month approved O&M Cost Maintenance Spares Two month Receivables Total Interest @ 14.75% 2015-16 43.49 13.77 13.28 138.48 209.02 30.83 Assam Power Generation Corporation Limited Page 54 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Note: Interest on working capital is computed @ an interest rate of 14.75% as per AERC 3.4.9 Repayment of Loan (Principal) Table 30 Particulars PFC Loan State Govt Loan Total 2015-16 22.97 15.20 38.16 3.4.10. Fuel Cost Table 31 Particulars Namrup TPS NRPP Lakwa TPS Total 2015-16 127.25 75.41 319.26 521.92 4. Profit & Loss Account Table 32 Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges O&M expenses of CTPS EXPENDITURE Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement Add: R&M Expenses approved vide letter No. AERC 442/2014/15 Surplus(+) / Shortfall(-) Assam Power Generation Corporation Limited 2015-16 1930.71 1831.57 5.13% 550.43 0.00 521.92 53.55 105.27 9.85 48.21 75.63 -19.75 30.83 0.00 0.00 0.00 825.51 58.96 10.60 0.93 874.79 26.73 -351.09 Page 55 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 5. Balance Sheet Table 33 Particulars Source of Fund Share Capital Reserve & Surplus Loans from State Govt Loans from others Total Contributions, grants & subsidies towards cost of Capital Asset Grand Total Application of Fund Net Fixed Assets (A) Gross Block (B) Less : Accumulated Depreciation (C) Net Fixed Assets (D) Capital-works-in-progress Total of (C) to (D) Investements Subsidy receivable from Govt Net Current Assets A. Current Assets, Loans & Advances i) Inventories ii) Receivables against Sale of Power iii) Cash & Bank Balance iv) Loans & Advances v) Other current assets Total of A B. Current Liabilities and provisions i) Borrowing for Working Capital ii) Payment due on Capital Libilities iii) Other current liabilities Total of B Net Current Assets (A - B) Profit/ Loss Grand Total 2015-16 455.86 302.14 229.12 660.95 1648.07 434.77 2082.84 2216.23 707.40 1508.83 424.60 1933.43 0.00 98.28 4.96 221.89 82.66 109.78 517.57 426.57 426.57 91.00 58.40 2082.83 Station wise information for claiming ARR and Tariff for FY 2015-16 is depicted in Annexure-IV (Page No. 148) Assam Power Generation Corporation Limited Page 56 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 6. Proposed ARR for FY 2015-16: Table 34: (Station wise, FY 15-16) (Rs in crore) Particulars NTPS Gross Generation (MU) Aux. Power Consumption (MU) Net Generation (MU) Fixed Charges Operation & Maintenance Employee Cost Repairs & Maintenance Administrative & General Expenses Interest & Finance Charge Interest on working Capital Taxes on income Depreciation Provision for Bad & Doubtful Debts Return on Equity Less: Other Income (A. 1) Total Fixed Charges LWHRP LTPS 342.98 18.82 324.16 171.12 16.09 155.04 689.87 48.29 641.58 (LTPS + LWHRP) 861.00 64.38 796.62 35.02 16.65 1.54 4.72 7.42 0.31 5.54 0.00 10.16 -3.68 77.67 9.51 0.83 0.47 12.44 1.44 0.00 10.93 0.00 9.93 0.00 45.54 30.55 28.35 3.74 6.85 15.23 0.31 8.73 0.00 11.50 -3.69 101.57 40.06 29.18 4.21 19.29 16.67 0.31 19.66 0.00 21.42 -3.69 147.12 2015-16 CTPS KLHEP Myntriang NRPP Total 0.00 0.00 0.00 390.00 1.95 388.05 41.59 0.42 41.17 295.14 13.58 281.57 1930.71 99.14 1831.57 3.45 0.00 0.01 0.04 0.00 0.00 0.00 0.00 0.00 0.00 3.50 14.59 7.69 2.97 11.19 2.22 0.31 8.74 0.00 9.54 -3.23 54.01 1.47 0.03 0.24 0.47 0.13 0.00 -0.52 0.00 3.27 0.00 5.09 10.67 0.00 0.89 20.18 4.39 0.00 14.78 0.00 14.57 0.00 65.48 105.27 53.55 9.85 55.88 30.83 0.93 48.21 0.00 58.96 -10.60 352.87 75.41 140.89 232.57 267.81 500.38 26.73 379.60 521.92 901.52 207.26 284.96 492.21 550.43 -351.09 (A. 2) R&M Expenses approved vide letter No. AERC 442/2014/15 "Order on Review Petition on Tariff Order for FY 13-14" dated 08.07.2014 (A) Total Fixed Cost (B) Fuel Cost 127.25 0.00 319.26 319.26 0.00 0.00 (C) ARR (A) + (B) 204.92 45.54 420.83 466.38 3.50 54.01 Fixed Cost Paise / Kwh (sent out) 239.59 293.76 158.32 184.68 139.19 Fuel Cost Paise/ Kwh (sent out) 392.56 0.00 497.61 400.77 0.00 Tariff Paise/ Kwh (sent out) 632.16 293.76 655.93 585.45 139.19 (D) Estimated revenue from Sale of Power for FY 2015-16 (calculated at approved Generation tariff for FY 2014-15) (E) Surplus/Deficit (C)-(D) 0.00 5.09 123.73 0.00 123.73 Note: The Secondary Energy Charges will be computed as per the lowest variable charge bearing Central Sector Generating Station as per CERC Tariff Order for FY 2014-19 Assam Power Generation Corporation LimitedPage57 of 229 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 7. Directives of AERC Directives of the Commission in its Tariff Order for 2014-15 Compliance of Old Directives issued in the Tariff Order for 2012 -13 & 2013-14 and New Directives issued in the Tariff Order for 2014-15 Directive No: AERC’s Directive Comments of the Commission in the Tariff Order for 2014-15 Status as on 31st December 2014 The Commission has taken note of APGCL’s submissions. TheCommissionacknowledges the efforts of APGCL in reducing the auxiliary Energy Consumption.However, the Commission is of the view that the targets specified under PATScheme are altogether for a different purpose and APGCL should strive to reducethe Auxiliary Consumption of NTPS and LTPS to the normative levels specified in theRegulations. APGCL is putting continuous efforts to reduce APC of LTPS and NTPS. The result of these efforts can be seen in the reduced APC of LTPS in the 3 rd quarter of LTPS at 8.07% from earlier 8.96% in the 2 nd quarter of 201415. The Commission again directs APGCL to vigorously pursue the matter with the Govt. of Assam, and complete the formalities of forming the Trust as early as possible. Noted. The matter is continuously being pursued with Govt. of Assam by APGCL Old Directives 1 Directive1: Auxiliary Consumption The auxiliary consumption of both the thermal stations (NTPS and LTPS) is on high side. The efforts should continue to reduce Auxiliary Consumption and the Auxiliary Consumption levels of both the Stations need to be brought down to the levels specified in the Regulations. 2 3 Directive2: Employee’s Provident Fund APGCL is utilizing the provident fund amount recovered from the employees and no such account is maintained. APGCL was directed to maintain separate accounts for the amounts recovered from the employees towards provident fund and its utilization duly audited by Statutory Auditors.The Commission again directs APGCL to pursue the matter with the Govt. of Assam, and the formalities of forming the Trust should be completed as early as possible. Directive-3: Procurement of Gas The process for handing over of transformer feeders to APDCL is going on in LTPS and NTPS and further reduction of APC is expected after the process is completed. Assam Power Generation Corporation LimitedPage58 of 229 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Compliance of Old Directives issued in the Tariff Order for 2012 -13 & 2013-14 and New Directives issued in the Tariff Order for 2014-15 Directive No: AERC’s Directive Comments of the Commission in the Tariff Order for 2014-15 Status as on 31st December 2014 APGCL is not getting the committed quantity of gas from the gas suppliers due to which generation of energy is getting reduced correspondingly. APGCL shall make all the efforts to get the gas supply as per commitment and also to get allotment of additional gas supply to overcome the problem of inadequate availability of power in the State. Noted. APGCL should submit a quarterly report to the Commission on the efforts made to procure committed quantity of gas and to get additional allotments, to overcome the generation problem, and the outcome of such efforts.reviewed. A statement of drawing of gaseous fuel by NTPS &LTPS in Oct’14 and Dec’14 is given below: Month Received/ Allotted Qty (MMSCM) NTPS (OIL) LTPS LTPS (GAIL) (OIL) Oct’14 21.14/20.46 9.91/ 15.50 14.73/ 12.40 (103%) (65%) (119%) Nov’14 10.99/ 15.0 10.52/ 12.00 19.76/ 19.8 (57%) (99.79%) (87.5%) Dec’14 20.54/ 20.46 13.74/ 15.5 10.70/ 12.40 (100%) (88.6%) (86.2%) During the 3rd quarter, natural gas supplied by both OIL and GAIL are found to be inconsistent. APGCL is making all out efforts to get the gas supply as per commitment. Additional allotment of gas of 0.15 MMSCMD from the ONGC gas fields in the Cachar district is in process. 4 5 Directive-4: Performance Parameters APGCL should expedite the on-going Renovation & Modernisation schemes and ensure timely completion of the projects. Directive-5: Monitoring of Progress of New Power Projects APGCL is directed to submit quarterly progress report on time on regular basis. APGCL should expedite the on-going Renovation & Modernisation schemes and ensure timely completion of the projects. Noted. APGCL submits the status of its ongoing Renovation & Modernisation schemes to the AERC quarterly. Noted. APGCL is directed to continue to submit quarterly progress report on time, on regular basis, till completion of the projects. Progress Report on implementation of New Projects (Thermal) & ongoing R&M projects had been submitted for the 2nd quarter of 2014-15 to AERC vide No. APGCL/CGM (G)/AERC/2011-12/115/Pt/28 dated Assam Power Generation Corporation LimitedPage59 of 229 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Compliance of Old Directives issued in the Tariff Order for 2012 -13 & 2013-14 and New Directives issued in the Tariff Order for 2014-15 Directive No: AERC’s Directive Status as on 31st December 2014 Comments of the Commission in the Tariff Order for 2014-15 17/10/14. 6 7 Directive-6: Performance of Petitioner’s Plants A lot of concern had been expressed by the stakeholders on the need for improvement in the performance of NTPS and LTPS where most of the Units are more than 25 years old. There is a scope for improvement in generation from these plants by increasing their existing capacities to at least their original design values, which have been stated to have reduced due to wear and tear during past many years. The more important issue is that of ensuring generation availability from these plants for longer duration of time as most of these plants have already outlived their originally envisaged useful life. Accordingly, the Commission was of the view that these plants urgently need Renovation, Modernization and Up gradation (RMU) for both improvement in generation capacity and life extension. The Commission therefore, directed the Petitioner to submit the final DPR with cost benefit analysis indicating life extension period shall be submitted for approval of the Commission as early as possible. Directive-7: Need for Augmenting Own Generating Capacity APGCL shall make all out efforts to complete the ongoing projects within stipulated time to avoid time and cost overruns. The DPRs submitted by APGCL are being reviewed by the Commission. Noted. The approved station wise amount by GOA in the Annual Plan of APGCL for the FY 2014-15 for execution necessary R&M works are stated below 1. NTPS - Rs. 8.67 Cr 2. LTPS – Rs. 20.19 Cr 3. KLHEP – Rs. 1.56 Cr Proposed station wise amount in the Annual Plan of APGCL to GOA for the FY 2015-16 for execution of necessary R&M works are stated below: 1. NTPS – Rs. 17.80 Cr 2. LTPS – Rs. 38.62 Cr 3. KLHEP – Rs. 7.80 Cr In this regard, the DPR for FY 2015-16 along with revised DPR for the FY 2014-15 has already been submitted vide No. APGCL/CGM (G)/AERC/201314/115/Pt-IX/33 dated 20/12/2014 for the Hon’ble Commission’s approval The progress of on-going projects is not satisfactory and there have been several delays in most of the projects, especially NRPP. APGCL should make all out efforts to complete the on-going projects, Noted. All out efforts are being made by APGCL for timely completion of its ongoing projects. APGCL submits the status of its ongoing projects to the AERC quarterly. Assam Power Generation Corporation LimitedPage60 of 229 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Compliance of Old Directives issued in the Tariff Order for 2012 -13 & 2013-14 and New Directives issued in the Tariff Order for 2014-15 Directive No: AERC’s Directive Comments of the Commission in the Tariff Order for 2014-15 Status as on 31st December 2014 including NRPP, within the stipulated time to avoidtime and cost overruns. 8 9. Directive-8: Submission of DPR for Renovation & Modernisation Schemes The Commission directs APGCL to include the major overhauling in the scope of work of Renovation and Modernisation and submit the Detailed Project Report with cost benefit analysis for approval of the Commission. Directive-9: Capital Cost of Small Hydro Projects The Commission directs APGCL to submit the Petition with detailed break-up of the Capital Cost for approval of the Commission. APGCL shall submit the DPR for Renovation and Modernisation activities for FY 2015-16 along with the APR Petition for FY 2014-15. The DPR for FY 2015-16 along with revised DPR for the FY 2014-15 was submitted vide No. APGCL/CGM (G)/AERC/2013-14/115/Pt-IX/33 dated 20/12/2014 Noted. The Commission directs APGCL to submit the Petition for Myntriang SHEPStage I, Lungnit SHEP and all small hydro projects in future with detailed break-up ofthe Capital Cost for approval of the Commission. Reply in response to AERC’s letter No. AERC.447/2014/6 dated 16.05.2014 in respect of Capital cost of 9 MW Myntriang &6 MW Lungnit SHEPs was submitted to the AERC vide letter No. APGCL/CGM (G)/MYT/13-16/232/Part/Myntriang Tariff/6 dated 28/10/2014. DPR for 4.5 MW enhancement of Myntriang SHEP is being prepared and will be submitted shortly. NewDirectives Directive-1: Implementation of on-going Projects 10 in a timely manner Assam Power Generation Corporation LimitedPage61 of 229 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Compliance of Old Directives issued in the Tariff Order for 2012 -13 & 2013-14 and New Directives issued in the Tariff Order for 2014-15 Directive No: AERC’s Directive Status as on 31st December 2014 Comments of the Commission in the Tariff Order for 2014-15 Noted. All out efforts are being made by APGCL for timely completion of its ongoing projects. 1x100MW NRPP: The Commission isconcerned about thesubstantial delay in commissioning of theon-going projects, especially NRPP. The Commission directs APGCL to make all-outefforts and all necessary steps to avoid further delay, and to ensure that the projectsare completed in a timely manner. Reasons for Delay in commissioning: Continuous poor progress of works due to poor management of site by BHEL’s sub contractors by way of insufficient machineries &labourers hampered progress of works. Non availability sufficient skilled manpower. Weather (In the whole year, only 5 months is favorable for ground work). Efforts by APGCL: Series of high level meetings and rigorous persuasion by APGCL including issue of pre- termination notice forced BHEL to replace the civil contractor. All critical areas of works for commissioning on open cycle mode first have been identified and progress of works is being reviewed weekly. To address any critical technical issues, design engineers of BHEL are being requisitioned to expedite the works. To make the outside labourers feel comfortable, all facilities like the following have been provided. i. ii. Labourers’ huts within the protected area of power plant. Additional Security by ex-service man&outsourced security personnel have Assam Power Generation Corporation LimitedPage62 of 229 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Compliance of Old Directives issued in the Tariff Order for 2012 -13 & 2013-14 and New Directives issued in the Tariff Order for 2014-15 Directive No: AERC’s Directive Status as on 31st December 2014 Comments of the Commission in the Tariff Order for 2014-15 iii. iv. been deployed specially for the project. 24/7 Patrolling is provided. Entry of unauthorized persons inside the protected area is restricted. Due to the efforts taken by APGCL to expedite the work of NRPP, civil works in all fronts is gaining momentum now and up to 50% Project Work has been completed by the end of December’14. The CCGT project is expected to be commissioned by mid of 2016. 11 12 Directive-2: Filing of complete Petitions within the scheduled dates It has been observed that the Petitions are not being filed on time, and even after filing of the Petitions, the necessary data and clarifications are not submitted on time, leading to delays in the tariff determination process. The Commission directs APGCL to ensure that the Petitions are filed on time, and all the necessary data and clarifications are submitted along with the Petition itself. Directive-3: Calculation of depreciation in accordance with the AERC Tariff Regulations It has been observed that APGCL does not submit the calculations of depreciation strictly in accordance with the AERC Tariff Regulations, 2006, and claims depreciation on assets funded through grants also. The Commission directs APGCL to ensure that in subsequent Petitions, the depreciation is computed strictly in accordance with the AERC Tariff Regulations, 2006. The Petition for Revised ARR and Tariff for 2015-16 was submitted to AERC with due extension on 20 th December 2014. The Petition for Revised ARR and Tariff for 2015-16 was submitted to AERC and the calculations of depreciation has been calculated as per the norms of AERC Assam Power Generation Corporation LimitedPage63 of 229 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 8. Investment Plan for FY 2015-16 The projected demand of power of Assam by end of 12th Plan (12-13 to 16-17) is 2293 MW as per CEA’s 17th EPS. To meet this energy demand to the extent feasible, APGCL, at the initiative of Govt. of Assam, has emphasized on development of large capacity thermal power projects based on coal & natural gas available in this region. This would in a way minimize over dependency on hydro power particularly during lean hydro generation period and to balance a suitable Thermal & Hydel generation ratio. Further, to harness renewable source of energy as per policy of GOA for development of SHP, APGCL has identified 37 Nos. of locations in Assam. Process has been initiated for engaging nationally/internationally reputed professional consultancy to prepare Techno Economic Studies including preparation of DPRs. In order to meet the ever growing demand of electricity in the state, APGCL has earmarked on large investment plan for development of power projects. This will also help in the growth & profitability of the company. The additional capacity envisaged after development & implementation of proposed thermal and hydro-electric power projects in 2015-16 along with proposed investment are shown in the Tables I & II below. On implementation of the proposed projects, APGCL will be in a position to mitigate considerably the shortfall of power in the state of Assam. Investment Plan Table-I Name of Power Station Namrup TPS Lakwa TPS with WHU Karbi Langpi HE Project Myntriang SHE Project Namrup RPP Lungnit SHE Project Lakwa RPP Gas IC Engine based Cachar PP Gas IC Engine based Titabor PP Margherita TPS Solar PV Project at LTPS Solar PV Project at NTPS Lower Kopili HEP TOTAL 12-13 13-14 14-15 15-16 Installed Installed Installed Installed MW MW MW MW 119.5 119.5 119.5 63.5 157.2 157.2 157.2 157.2 100.0 100.0 100.0 100.0 0.0 0.0 3.0 13.5 0.0 0.0 0.0 63.0 Commissioning beyond 2015-16 Commissioning beyond 2015-16 Commissioning beyond 2015-16 Commissioning beyond 2015-16 Commissioning beyond 2015-16 Commissioning beyond 2015-16 Commissioning beyond 2015-16 Commissioning beyond 2015-16 376.7 376.7 379.7 397.2 Assam Power Generation Corporation LimitedPage64 of 229 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Investment Plan Table-II Investment Proposal for the FY 2015-16 Name of the Project Sl. No. Revised Investment for 2015-16 Approved in the MYT Total Govt GOA Grant FI Order for Proposed (Equity) (Loan) (Govt) (Loan) 2015-16 investment Remarks Commercial Date of Operation if Commissioned in 2015-16 Thermal Wing 1 2 R&M of Namrup TPS R&M of Lakwa TPS 0.00 0.00 3 R&M of KLHEP 0.00 5.38 4 Construction of a new water intake pump house at Dilli river for consumptive water requirement of existing plant and Namrup Replacement Project. 0.00 17.00 5 100 MW Namrup RPP 6 70 MW Lakwa Replacement Power Project 0.00 277.76 3.80 The DPR for NTPS, LTPS & KLHEP 20.62 for proposed Renovation & 3.80 20.62 Modernisation Works in the FY 1516 has been furnished Vide Letter No: APGCL/CGM(G)/AERC/20137.80 14/115/Pt-IX/33 dtd 20/12/2014 as directed by the Hon’ble Commission in its Tariff Order for 2014-15. 2.42 17.00 New proposal. 160.00 54.90 78.60 Earlier NRPP was expected to be commissioned in 2013-14. However, due to slow progress of 63 MW GT expected to be 160.00 work by the EPC contractor BHEL, commissioned in August'15 the GT unit of the project is now expected to be commissioned in August’15 Earlier LRPP was expected to be commissioned in 2015-16. However, due to delay in 133.50 completion of the bidding process Commissioning beyond 2015-16 for various reasons, the project work is now expected to start in 2015-16 Assam Power Generation Corporation Limited Page 65 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 7 8 9 10 30 MW Cachar Distributed Generation System by Gas IC Engine EPC contract for 2.0 MW Solar Power Project at NTPS EPC contract for 2.0 MW Solar Power Project at LTPS Procurement/Acquisition of land for Titabor Gas Based Power Project 0.00 3.80 0.83 16.86 Due to non establishment of gas linkage, project work has not been started. Project work now is 21.49 expected to be started in 2015-16. Commissioning beyond 2015-16 Grant of Rs. 0.83 Cr is for procurement/acquisition of land for the project. 0.00 17.00 17.00 New Project Commissioning beyond 2015-16 0.00 17.00 17.00 New Project Commissioning beyond 2015-16 0.00 0.49 0.49 New proposal. Commissioning beyond 2015-16 Hydro Wing 11 13.5 MW Myntriang SHEP 12 6 MW Lungnit SHEP 0.00 8.12 23.50 21.00 13 120 MW Lower Kopili HEP 0.00 14 15 16 17 0.00 0.00 0.00 0.00 0.25 0.25 0.25 0.25 0.00 0.05 21 MW Karbi Langpi Middle Stage-I 24 MW Karbi Langpi Middle Stage-II 12 MW KLHEP Barrage Toe Project 60 MW Karbi Langpi Upper Stage Installation of deep tube well with submersible pump set for water supply 18 at BKV Investigation Division Colony, Jagiroad Total Proposed Investment 298.76 183.00 249.82 7.00 88.85 Due to delay in project execution, 2X3 MW St-I along with 1X3 MW the St-I of the project is yet to be enhancement and 1X1.5 MW 31.62 completed. Further, the project has enhancement in St-II is expected to been enhanced by another 4.5 MW be commissioned in December'15 Project work is at the moment at halt due to litigations related to 0.00 cancellation of Work Order with Commissioning beyond 2015-16 earlier EPC Contractor due to slow progress of work Project work has not started yet due to delay in obtaining various clearances. Project work is 190.00 Commissioning beyond 2015-16 expected to be started in the FY 2015-16 with the finance from the GOA. equity first. 0.25 0.25 Projects are in DPR preparation Commissioning beyond 2015-16 0.25 stage 0.25 0.05 New proposal. 27.23 255.46 621.36 Assam Power Generation Corporation Limited Page 66 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Breakup of R&M Plan for FY 15-16 is given in the table below: Sl No. (A) 1 2 3 4 5 6 (B) 7 8 9 Budget Proposal Name of Schemes and Approved Outlay (Rs in Cr.) R&M Works under Namrup Thermal Power Station (NTPS)-Govt. Loan: Replacement of existing 11 KV PILC single core copper cable from generator terminal to 11KV Unit Transformer of Gas Turbine Unit0.65 3 with XLPE cable along with terminal joints. Replacement of existing BHEL make AVR at GT Unit-3 with 0.60 microprocessor based AVR. Replacement of existing Analog AVR for Diesel Generator unit-1 & 0.30 2 of Diesel Power House by new microprocessor based digital AVR. Procurement & renovation of cooling tower of Steam Turbine unit1.00 5 Procurement & renovation of cooling tower of Steam Turbine unit1.00 6 Procurement of 66 kV, 800 A, double break triple pole gang 0.25 operated rotating centre pole isolating switch. R&M Works under Lakwa Thermal Power Station (LTPS) - Govt. Loan: Procurement and up gradation of one number Speedtronic Mark-IV Control System to Mark- VIe Control System at GT Unit-5 . Procurement of Plan security measures with CC camera and accessories. Repairing of one HT spare motor for gas compressor of Phase-II Power House. 0.20 0.35 Procurement of Phase-I 132 kV main bus sectionalizing system with breaker, isolator & electrical panels. 0.33 11 Procurement of Isolators of Phase-1 switchyard is required for replacement of the existing old isolators. 0.50 12 Procurement of relay of protection systems: i) Numerical relay for 3.3 kV system ii) Numerical relay for 33 kV system iii) Numerical relay for 132kV system. 0.34 13 Up-gradation of the existing damaged Hydrant fire fighting system of the Power Plant. 0.75 14 Procurement of Air Filter for Gas Turbine of Phase-II. 0.20 15 Procurement of three (3) numbers motor operated steam valves. 0.15 16 Procurement of one (1) no. new pump motor set for water Intake along with pipes, valves, cables etc. 0.65 19 20 21 22 23 24 25 Procurement of some major spares of WHRP. Fire tender with foam and water facility at LTPS . Procurement of spares for Gas Compressor & air compre4ssor of Phase-II at LTPS. Procurement of one no. 300AH, 120 V Battery bank for GT unit- 1 of LTPS Procurement of spares for GT Starting Diesel Engine of unit#1, #3, #5 & #6 . Development of existing colony water supply and WHRP supply system. Construction of new departmental quarters for employee: (a) One Type-V multistoried building with eight (8) blocks. (b) One Type-VI multistoried building with eight (8) blocks. 1.50 0.45 Repairing of a part of road inside colony at LTPS Development of the backyard of the new compressor building with PCC and road 1.20 Assam Power Generation Corporation Limited 3.80 7.00 10 17 18 Total (Rs. In Cr) 20.62 0.80 0.15 0.20 2.75 1.80 0.60 Page 67 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 26 27 (C) 28 Repairing of Burge at river Suffry at LTPS 0.10 Construction of Master Drain at LTPS 0.60 R&M Works under Karbi Langpi Hydro Electric Project: Govt. Loan Procurement of one no. 220/33 kV, 25.0 MVA Station Reserve Transformer with one set of C.T. (220 kV) for KLHPP 4.50 29 Procurement & 30 Procurement for renovation of 33 kV 8(Eight) units indoor Control/ Relay panel having 2 nos. Incomer & 6 nos. outgoing panel. 0.50 31 Procurement for renovation of Firefighting (Hydrant) system with Ecofriendly system and renewed positioning of piping system. 0.18 (D) 32 R&M Works under Karbi Langpi Hydro Electric Project: Govt. Grant Repairing of Amtereng Hatidubi Road 1.17 33 34 replacement of Shaft Seal KLHEP Hydro turbine. Boulder pitching at upstream side of right bank and left bank and downstream side of right bank at Hatidubi Dam including construction of stone masonry drain near Hatidubi Dam Slope stabilization works at the Right Bank (downstream side) and protection works at the top of landslide zone of Dam site at Hatidubi Dam, KLHEP Assam Power Generation Corporation Limited 0.20 0.50 5.38 2.42 0.75 Page 68 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 8.1. The brief Status of proposed on-going & new schemes of APGCL including R&M and joint venture projects are depicted below: 8.1.1. Renovation & Modernisation (R&M): In continuation of successful execution of R&M, PH-I, PH-II & PH-III schemes, it has been proposed for implementation of a comprehensive R&M schemes Phase-IV for LTPS, NTPS & KLHEP covering the period 2013-14 to 2015-16. The Ph.-IV R&M schemes have been necessitated in order to ensure maximum reliability and availability of the existing old units of both LTPS, NTPS & KLHEP to maximize generation. The R&M of power stations has been considered to be the most attractive economic option for the Company. R&M schemes are aimed at reducing auxiliary power consumption, and improving PLFs of generating units by sustaining an efficient and smooth operation of plants. Hence, keeping in view of the above, a comprehensive R&M Ph.-IV scheme has been formulated for LTPS, NTPS & KLHEP for implementation during the period of 2013-14 to 2015-16. The expenditures proposed to be incurred in the FY 15-16 as a part execution of the R&M Ph.-IV scheme & scope of works in general are mentioned below. R&M of Lakwa Thermal Power Station (For FY 2015-16): The R&M scheme has been proposed for the FY 2015-16 at an estimated cost of Rs 20.62 Crore under the Annual Plan of 2015-16. The scheme comprises of procurement and up gradation of 1. one number Speedtronic Mark-IV Control System to Mark- VIe Control System at GT Unit-5, 2. procurement of CC cameras and accessories for plant security, 3. Repairing of one HT spare motor for gas compressor of Phase-II Power House, 4. procurement of 132 kV Bus Isolator, 5. Procurement of Isolators of Phase-1 switchyard for replacement of the existing old isolators, 6. Procurement of relay of protection systems, 7. Up-gradation of the existing damaged Hydrant fire fighting system, 8. Procurement of Air Filter for Gas Turbine of Phase-II, 9. Procurement of three (3) numbers motor operated steam valves, 10. Procurement of one (1) no. new pump motor set for water Intake along with pipes, valves, cables etc., 11. Procurement of some major spares of WHRP, 12. Fire tender with foam and water facility at LTPS . 13. Procurement of spares for Gas Compressor & air compre4ssor of Phase-II at LTPS. 14. Procurement of one no. 300AH, 120 V Battery bank for GT unit- 1 of LTPS 15. Procurement of spares for GT Starting Diesel Engine of unit#1, #3, #5 & #6 . 16. Development of existing colony water supply and WHRP supply system, 17. Construction of new departmental quarters for employee, 18. Repairing of a part of road inside colony, 19. Development of the backyard of the new compressor building with PCC and road, 20. Repairing of Burge at river Suffry at LTPS. 21. Construction of Master Drain at LTPS R&M of Namrup Thermal Power Station (For FY 2015-16): The R&M scheme has been proposed for the FY 2015-16 at an estimated cost of Rs 3.80 Crore under the Annual Plan of 2015-16. The scheme comprises of 1. Replacement of existing 11 KV PILC single core copper cable from generator terminal to Assam Power Generation Corporation Limited Page 69 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 2. 3. 4. 5. 6. 11KV Unit Transformer of Gas Turbine Unit- 3 with XLPE cable along with terminal joints, Replacement of existing BHEL make AVR at GT Unit-3 with microprocessor based AVR, Replacement of existing Analog AVR for Diesel Generator unit-1 & 2 of Diesel Power House by new microprocessor based digital AVR, Procurement & renovation of cooling tower of Steam Turbine unit-5, Procurement & renovation of cooling tower of Steam Turbine unit-6, Procurement of 66 kV, 800 A, double break triple pole gang operated rotating centre pole isolating switch. R&M of Karbi Langpi Hydro Electric Project (For FY 2015-16): The R&M scheme has been proposed for the financial year 2015-16 at an estimated cost of Rs. 7.80 Crore under the Annual Plan of 2015-16. The scheme comprises of 1. Procurement of one no. 220/33 kV, 25.0 MVA Station Reserve Transformer with one set of C.T. (220 kV), 2. Procurement & replacement of Shaft Seal KLHEP Hydro turbine, 3. Procurement for renovation of 33 kV 8(Eight) units indoor Control/ Relay panel having 2 nos. incomer & 6 nos. outgoing panel, 4. Procurement for renovation of Firefighting (Hydrant) system with Ecofriendly system and renewed positioning of piping system, 5. Repairing of Amtereng Hatidubi Road, 6. Boulder pitching at upstream side of right bank and left bank and downstream side of right bank at Hatidubi Dam including construction of stone masonry drain near Hatidubi Dam. 7. Slope stabilization works at the Right Bank (downstream side) and protection works at the top of landslide zone of Dam site at Hatidubi Dam, KLHEP Status of On-going & New Projects of APGCL as on 31/12/2014 Ongoing Projects A. Thermal Projects I. 1x100MW Namrup Replacement Power Project (Ph-I): Present Status: After engagement of new Civil agency, M/s Power Mech Projects Ltd., Hyderabad for balance civil and structural works by BHEL 13-03-14, work has resumed at site and is in progress. BHEL has engaged the earlier mechanical contractor M/s Arun Construction, New Delhi under M/s NBPPL for balance electro- mechanical works. Civil works in all fronts are gaining momentum now. MEI erection works have also been started. Over all progress of works may be assumed approximately as 50%. Expected date of Commissioning of the project is by mid of 2016. Assam Power Generation Corporation Limited Page 70 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Financial Progress: a) Total Project Cost b) Total fund received c) Total fund released to the Implementing Agencies so far d) Funds utilized so far Rs. 693.73 Cr (Equity-30% (GoA) =Rs.208 Cr Term laon-70% (PFCL) =Rs.485cr) Rs. 348.0 crore (equity: 208cr & PFCL: 140cr) Rs. 283.83 crore to BHEL Rs. 45.29crore to other agencies Rs. 329.12crore B. Hydro Projects I. Myntriang SHP (3x3 MW St-I &3x1.5 MW St-II = 13.5MW): Stage II (2 x 1.5 MW) of Myntriang Small Hydro Electric Project was commissioned on 3rd March, 2014 and Commercial Operation was declared on 08-08-2014. The overall progress of works in Stage-I (2X3 MW) is 46 %. The project will be enhanced by another 4.5 MW (1X 1.5 in St-II and 1X 3 in St-I) through the existing EPC Contractor increasing the total capacity to 13.5 MW from 9 MW. Additional civil & hydro mechanical works are already being executed through the existing EPC Contractor as per supplementary agreement. The balance work of St-I along with the enhancement work is expected to be completed by December 2015. STATUS REPORT OF MYNTRIANG SHEP (STAGE I : 2 x 3.00 MW=6MW) SL No. 1 Description of Item Infrastructure Stage I Percentage of progress 95% 2 Concrete weir I 3 Power Channel I 86% (Excavation) 28% (Concreting) 82% (Excavation) 36% (Concreting) 4 Forebay I 5 Cross drainage work I 100% (Excavation) 60% (Concreting) 50% 6 Saddles & anchor I NIL 7 Power House and tail race I 15% (P.H Area) 8 Supply of hydro mechanical I equipment Supply & Erection of Electro I mechanical equipment NIL Penstock fabrication 15% 9 10 I 50% Assam Power Generation Corporation Limited Page 71 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 11 Additional Civil and Hydro I Mechanical works as per supplementary agreement for enhancement of power from 9MW (Stage-I: 2x 3.0MW & II Stage-II: 2x1.5MW) to 13.50 MW (Stage-I: 3x3.0MW & Stage-II: 3x1.5MW). 15% 99% II. Lungnit SHP (2x3 MW = 6 MW): After termination of the EPC contract with M/s P. Das & Co. and M/s Jyoti Ltd for slow progress of work, APGCL initiated necessary action for bidding process for completion of the Balance Works of the Project by inviting bids on 04/03/2014 with the date of submission of tender on 22/04/2014. In response, total 3 (three) nos. of bidders submitted their bids (Technical). Technical evaluation of the bids has been completed and approval of price bid is under consideration.However, selection of new EPC contractor is getting delayed due to litigations. The resumption of Project Work at the earliest is under active consideration by APGCL. St-II of Lungnit SHEP is expected to be completed within 20 months and St-I is expected to be completed within 30 months after the construction is resumed by the new EPC contractor. New Projects A. Thermal Projects I. 70 MW Lakwa Replacement Gas IC Engine Project: The first four units (15MWX4) of Lakwa Thermal power project have, on average, run for over twenty five years till date. Being of simple cycle, the heat rates of these units are twice as much as that of the modern combined cycle plant. It was decided to replace the first four units with a modern plant with better heat rate. Present Status 1. Investment Approval from Public Investment Board (PIB), GOA obtained. AIFA In principle sanctioned equity amount of Rs. 79.2 Crores for equity support. 2. EIA clearance of 70MW LRPP from MOE&F obtained Vide letter no J 13012/21/2012.IA.II (T) dated 14/10/2013. 3. DPR placed before AERC for approval. AERC in principle approved the DPR on 30/03/2013. 4. For Power Purchased Agreement (PPA) proposal placed before APDCL 5. Aviation Clearance obtained from AAI vide Letter no NER/ATM/2014/ 49E.0000-NOCSRCER 2604-06 dated 10/06/2014. 6. APGCL incorporated LRPP under Assam power sector enhancement investment project-II of Asian Development Bank (ADB) for arranging fund (Term Loan). Assam Power Generation Corporation Limited Page 72 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 7. Bid documents for Selection of EPC contractor Prepared in consultation with ADB’s Consultant and “Invitation for Bids (IFB)” sent to ADB on 31/12/2013 for publication in the ADB business opportunities Websites as advance procurement action. ADB published the IFB on their business opportunities Websites on 23/01/2014. APGCL uploaded the IFB and the BID Documents at website www.apgcl.org on 24/01/14 and published the IFB in local News Paper and National News paper on 25.01.2014. It is to be mentioned that the last date was extended twice for insufficient participation. Last date of submission of bid documents and opening of bid documents was on 16th May, 2014. 8. The technical bid was opened on 16-05-14. Only one party “Consortium of Wartsila India Ltd and Wartsila Finland OY” participated. Price bid was to be opened after approval of the Technical Bid. 9. Technical Bid evaluation report sent to ADB on 02/08/2014. ADB sought some clarifications on Technical Bid evolution report, APGCL’s replies to the clarifications on Technical bid evaluation report was sent to ADB on 04/09/2014. 10. ADB Letter dt 16.10.14 from Mr.YongpingZhai, Director, Energy Division, South Asia, Asian Development Bank, Manila, addressed to Director, PMU asked APGCL to go for Rebidding with Approval of Fresh Bid Documents from ADB. 11. APGCL published an Expression of Interest (EOI) on 18/11/2014 to discuss issues to facilitate broader participation of bidders and manufacturers in the up-coming re-bid for EPC procurement tender for LRPP. 12. The EOI meeting for LRPP was held on 26/11/2014 at Bijulee Bhawan and seventeen nos of various company representatives participated in the meeting in presence of ADB’s consultant. 13. Bid documents for Selection of EPC contractor Prepared in consultation with ADB’s Consultant and “Invitation for Bids (IFB)” send to ADB on 18/12/14 for publication in the ADB business opportunities Websites as advance procurement action. ADB published the IFB on their business opportunities Websites on 19/12/2014. APGCL uploaded the IFB and the BID Documents at website www.apgcl.org on 18/12/14 and published the IFB in local News Paper and National News paper on 19.12.2014. 14. Pre bid Discussion for Selection of EPC contractor of LRPP will be held on 09/01/2015. 15. Last date of submission of bid documents and opening of bid documents is 30/01/23015. II. 660 MW Margherita Coal Based Power Project: Assam Power Generation Corporation Ltd proposes to set up a Coal Based Power Project at village Saliki NC under MakumMauza of Margherita Sub-Division, Margherita, District Tinsukia, Assam. The Project site is situated in the vicinity of coal mines of North Eastern Coal Fields of Coal India Ltd and considered it as a pit head project. Present Status Project capacity has been increased to 660 MW from earlier 500 MW. Water drawl permission @3300 cum per hour for 660 MW obtained from the Water Resources Dept., GOA vide letter No. WR (ED) Tech/5110/05/140 dated 20/09/2014. Amended Terms of Reference (TOR) was granted for 1X660 MW project in the meeting with MOEF on 30/10/14. Assam Power Generation Corporation Limited Page 73 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Applied for Coal linkage of 1.57 MTPA for proposed 2X250 MW Margherita Power Project vide letter No. APGCL/CGM (G)/Margherita Project/JV/NTPC/209/39 dated 20/04/2013 to CEA. Due to change of configuration to 660 MW, fresh application was made for coal linkage of 1.83 MTPA instead 1.57 MTPA vide letter No. APGCL/CGM (G)/Margherita Project/JV/NTPC/209/65 dated 18/12/2014. The project is proposed to be implemented through JV with NEEPCO. Draft Memorandum of Understanding has already been approved by APGCL Board of Directors. Approval by NEEPCO Board of Directors is awaited. Consultancy Work Order was earlier awarded to M/s Fichtner India, Chennai for the preparation of DPR for Supercritical 1X660 MW after bidding process. However, the Terms and Conditions in the Work Order were not acceptable to Fichtner India, because of which the work was later awarded to M/s TCE, Bangalore. III. Distributed IC Engine for Generation from Gas of OIL/ ONGCL at different locations of Golaghat&Silchararea: Titabor PP:The pre-feasibility report (PFR) for Golaghat Project (now renamed as Titabor Power Project) was prepared. Allotment of Gas allocation is awaited. Meanwhile, ONGCL floated open NIT for gas fields at Golaghat. APGCL participated in the bidding processwith deviation clauses as per the approval by the APGCL Board. Tender opening date was 25.10.12.APGCL submitted its bid for two gas fields of Golaghat district with deviations from terms and conditions laid down by ONGC. ONGC requested APGCL to withdraw the deviations, which it was unable to do so for the sake of project viability. After which ONGCL cancelled the Tender. There has been no further progress on the matter since then. Meanwhile, APGCL wrote to the Chairman and Managing Director, ONGC and to the Secretary to Govt. of India, Ministry of Petroleum and Natural gas for additional gas vide letter No. MD / APGCL /PS / Misc / 2014 / 17 dated 25th July 2014 and MD /APGCL /PS /Misc /2014/30 dated 12th Sept, 2014 respectively to allocate 0.15 MMSCMD of gas available at ONGC gas fields near Golaghat District to APGCL. Discussion was also made by MD APGCL with ONGC and MOPNG to allocate the gas available in the small pockets of gas in that area to APGCL from which around 40 MW (nominal) of power is proposed to be generated with Gas IC Engine based technology. Cachar PP:ONGCL retendered for its Bhubandar and Banskadi Gas fields in December’13 in a two bid system. APGCL took part in the bidding which was closed on 05/05/14. Technical bids were opened on the same day and APGCL was the sole bidder for Bhubandar gas field and in Banskandi Gas field other than APGCL only AGCL took part in the bidding. Price Bid for Bhubandar Gas Field was opened on 07/10/14 and that for Banskandi Field was opened on 07/11/14. APGCL is awaiting further correspondence from ONGC. Implementation of Cachar Power Project is strictly dependent on the successful bidding of the Gas by APGCL from ONGCL. IV. 60 MW Revival of Chandrapur TPS on coal under JV mode: Regarding revival of CTPS on coal as alternative fuel through PPP, APGCL, land measuring approx. 67 acres and 6 cusec of water are to be transferred to JV Company i.e. M/s. IAPL on lease as per the joint venture agreement dtd. 02.02.2010. Assam Power Generation Corporation Limited Page 74 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Present Status: 1. M/s IAPL applied to Ministry of Coal for sanction of 0.2 Million Tonnes Coal linkage. 2. APGCL Board (resolution No. 4 dtd. 31/03/12) approved transfer of 67 acres of land along with existing water rights to the JV Company M/s IAPL. 3. The draft Lease Deed Agreement for transfer of Land & Buildings of CTPS has already been finalized with the consent of M/s IAPL and APGCL Board approved the same. 4. Fuel Supply Agreement (FSA) between M/s World Trade Raw Materials Inc, USA (having selling rights of coal from Indonesia) and M/s IAPL to import coal from Indonesia has been signed on 8th July'13. Coal from Indonesia will be used till coal linkage from GOI is obtained. 5. MOU has been signed between M/s IAPL and APDCL on 21 st August’2013 for sale of power. 6. Ministry of Environment & Forest, GOI has transferred the CTPS revival proposal to State Level Environment Impact Assessment Authority (SEIAA), GOA as the revival of CTPS project is a Category-B project and State Level Environment Impact Assessment Authority, Assam has now been constituted. 7. APGCL/ Commissioner & Secretary, Power, GOA requested State Level Environment Impact Assessment Authority (SEIAA), GOA for issue of necessary Environmental & Forest Clearance to the JV Company for implementation of the project without further delay.Environmental & Forest Clearance is likely to be received soon. 8. Process has been initiated to remove existing Boiler & Auxiliaries of 2x30 MW CTPS units to make room for new Boilers to be installed by M/s Imperial APGCL Power Limited. The award of contract for Disposal of Boiler & Auxiliaries of 2x30 MW CTPS units has been awarded to YashaswiIspat Pvt. Ltd., Guwahati-8. Lifting of scrap materials by the firm is under progress. B. Solar PV Projects: The Government of India had launched Jawaharlal Nehru National Solar Mission(JNNSM) to promote ecologically sustainable growth while addressing India’s energy security challenge and focus on setting up an enabling environment for solar technology penetration in the country. Under this Mission; Ministry of New and Renewable Energy (MNRE) is providing subsidy for promoting off-grid systems and Decentralised Solar Application scheme:”Operational Guidelines for Grid Connected roof top and small solar Power plant program”. APGCL is at present considering the following Solar PV Projects: Sl. No. 1 2 3 Project Name (APGCL) Namrup Solar PV Project Lakwa Solar PV Project Amguri Solar PV Project Capacity (MW) 2 2 60 Status DPR under preparation Draft DPR prepared and is under review C. Hydro Projects I. 120 MW Lower Kopili HEP: 1. Revised DPR was submitted to CEA after compliance of observations for Techno-Economic Clearance in March 2013. After examining the DPR, statutory authorities e.g., Central Electricity Authority (CEA), Central Water Commission (CWC), Geological Survey of India (GSI), Central Soil & Materials Research Station (CSMRS) raised certain observations Assam Power Generation Corporation Limited Page 75 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 regarding incorporation of some additional information in the DPR. All additional GeoTechnical explorations as suggested by GSI are completed. 2. Environment Impact Assessment (EIA) studies are being carried out by Water and Power Consultancy Services (WAPCOS) as consultant. Terms of Reference (TOR) for EIA have been received. Additional studies as stipulated in the TOR are going on. Draft EIA report is targeted for completion by July’15. 3. As suggested by the Forest Deptt, GOA, the revised forest clearance application has been uploaded in the website of MOEF. No comments have been received as on 31-12-14. 4. Hydrology, Power potential for (2X55+1X5+2X2.5)=120 MW, Power Evacuation arrangement, Instrumentation aspects, Geology aspects have been approved by the concerned Directorates of CWC/CEA and GSI. Clearances received from Ministry of Home Affairs (MOHA), Ministry of Defense (MOD). 5. Proposal for site specific seismic coefficients has been placed to Foundation Engineering and Seismic Aspects (FESA) Directorate of CWC for approval of the coefficients by National Committee on Seismic Design Parameter (NCSDP). The NCSDP meeting will be held on 0901-15. II. 21 MW KarbiLangpi Intermediate Stage-I, 24 MW KarbiLangpi Intermediate StageIIHEP & 12 MW KarbiLangpi Barrage Toe H.E. Projects : DPR is being prepared through M/s. LahmeyerInternational India (LII) for (i) Karbi Langpi Intermediate stage-I (21MW), (ii) Karbi Langpi Intermediate stage-II (24MW) and (iii) Karbi Langpi Barrage Toe H.E Project (12MW). DPR for Karbi Langpi Intermediate St-II has been approved by APGCL Board on 03-12-14. III. Projects Under Investigation: APGCL is doing survey and investigation at the following locations: 1) Sunani (KarbiAnglong) 2) Maine (KarbiAnglong) 3) Silbheta (KarbiAnglong) 4) Bonda (Kamrup) 5) Killing (KarbiAnglong) Assam Power Generation Corporation Limited Page 76 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Directive issued in Tariff Order for FY 14-15, reply to be furnished along with tariff Petition for FY 15-16 & APR for FY 14-15 1. Justification of under generation of Lakwa WHRU leading to higher Gross Station Heat Rate of LTPS (Combined Cycle) APGCL collected the details justification regarding under generation of WHRU from LTPS which has been stated below: The WHRP was commissioned on 17th January'12 with its 3 (three) HRSG in operation. In the initial period of STG operation, the sustainable load achieved was around 35-36 MW but the load started to decrease since May'12 end. On 8th October'12, the performance guarantee (PG) test was performed by BHEL. During performance guarantee test, the actual load achieved was 33.52 MW (after voltage & PF correction) which was submitted by BHEL as per their report number PEMC¬03692. The STG power output after GT exhaust flow and temperature correction was 35.2 MW. The correction factor of condenser was not accepted by APGCL. Considering the above PG test report and as per actual sustainable generation achieved during one year from commissioning, the most possible STG generation may be taken as 33.5 MW. It is expected that the present low output of 30.0 MW can be resolved by BHEL after improving the condenser low vacuum problem. The STG generation has reduced to average 30.0 MW gradually due to drop of condenser vacuum. BHEL technical team has already visited twice to LTPS to study particularly on the low generation caused by the drop of condenser vacuum. In view of the above, the decreasing trend of generation of WHRP as raised by AERC can be improved to the extent of PG test performance of 33.5 MW and not to that of the design output of 37.2 MW which includes the GT exhaust correction factor. As per contractual agreement, BHEL is to prove the design output as per approved PG test procedure which is still to be achieved. Comments: The design annual generation of WHRU as per approved DPR is 223 MU. Considering the current performance of WHRU @ 30 MW for the above stated constrain, the output has been reduced to 180 MU, which is at per with the actual generation of WHRU for FY 12-13, 13-14 and FY 2014-15 (up to Nov’14). However, it is expected to improve output of WHRU to the extent of 33.5 MW i.e. annual generation up to 200 MU after taking above corrective measures as recommended by BHEL. In this connection this may be mentioned here that as the auxiliary equipment’s consumption remain the same, the reduced output of the WHRU also attributed to higher APC LTPS (Combined Cycle). Further, for above reasons the lower output of the WHRU, the Gross Station Heat Rate (GSHR) of LTPS (Combined Cycle) is also increases as commented by the Hon’ble Commission in the Tariff Order for FY 2014-15. 2. Furnishing of DPR for Renovation & Modernisation for NTPS. LTPS & KLHEP along with APR for FY 15-16 DPR for NTPS, LTPS & KLHEP for proposed Renovation & Modernisation Works furnished Vide Letter No: APGCL/CGM(G)/AERC/2013-14/115/Pt-IX/33 dtd 20/12/2014 Assam Power Generation Corporation Limited Page 77 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Annexure I 9. Statements of proposed Monthly Generation, Fuel Prices &Cost of Fuel for FY 2015-16. Assam Power Generation Corporation Limited Page 78 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Proposed Monthly Generation for FY 2015-16 STATION Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Namrup TPS 119.5 MW from Apr'15 to Dec'15 Gross Gen. (MU) 44.16 45.63 43.91 45.48 0.00 0.00 0.00 APC @5.5% 2.42 2.50 2.40 2.49 0.00 0.00 0.00 Net Gen. (MU) 41.74 43.13 41.50 42.99 0.00 0.00 0.00 Namrup TPS 63.5 MW with Unit 1, 2 & 6 from Jan'16 to Mar'16 after commissioning of NRPP Gross Gen. (MU) 0.00 0.00 0.00 0.00 17.37 16.80 21.96 APC @5.5% 0.00 0.00 0.00 0.00 0.96 0.92 1.21 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Total 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 179.17 9.81 169.36 21.25 21.96 21.96 20.54 21.96 163.81 1.17 1.21 1.21 1.13 1.21 9.01 Net Gen. (MU) 0.00 Total of Namrup TPS for 2015-16 0.00 0.00 0.00 16.41 15.88 20.75 20.08 20.75 20.75 19.41 20.75 154.80 Gross Gen. (MU) APC @5.5% 44.16 45.63 43.91 45.48 17.37 16.80 21.96 21.25 21.96 21.96 20.54 21.96 342.98 2.42 2.50 2.40 2.49 0.96 0.92 1.21 1.17 1.21 1.21 1.13 1.21 18.82 Net Gen. (MU) 41.74 43.13 41.50 42.99 16.41 15.88 20.75 20.08 20.75 20.75 19.41 20.75 324.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37.50 1.72 35.77 36.29 1.67 34.62 37.50 1.72 35.77 36.29 1.67 34.62 37.50 1.72 35.77 37.50 1.72 35.77 35.08 1.61 33.46 37.50 1.72 35.77 295.14 13.58 281.57 53.66 55.45 53.66 55.45 55.45 53.66 55.45 60.62 62.64 62.64 58.59 62.64 689.87 3.76 3.88 3.76 3.88 3.88 3.76 3.88 4.24 4.38 4.38 4.10 4.38 48.29 14.94 13.64 10.79 15.43 15.43 14.94 13.77 13.44 15.10 13.77 14.44 15.43 171.12 1.40 1.28 1.01 1.45 1.45 1.40 1.29 1.26 1.42 1.29 1.36 1.45 16.09 68.59 69.09 64.44 70.88 70.88 68.59 69.22 74.06 77.74 76.41 73.03 78.07 861.00 5.16 5.16 4.77 5.33 5.33 5.16 5.18 5.51 5.80 5.68 5.46 5.84 64.38 NRPP 63 MW GT Gross Gen. (MU) APC @4.6% Net Gen. (MU) 157.2 MW Lakwa TPS LTPS GT Gross Gen. (MU) LTPS GT APC @7.0% (MU) WHRU Gross Gen. (MU) WHRU APC @9.4% (MU) LTPS Gross Gen. (MU) with WHRU Total APC @7.5% with WHRU Assam Power Generation Corporation Limited Fuel Cost (Rs. In Cr.) 67.45 59.80 127.25 75.41 319.26 Page 79 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 LTPS Net Gen. (MU) with WHRU 100 MW Karbi Langpi HEP 63.43 63.92 59.67 65.55 65.55 63.43 64.04 68.55 71.93 70.73 67.57 72.23 796.62 Gross Gen. (MU) 9.00 19.00 45.00 68.00 74.00 72.00 45.00 21.00 15.00 11.00 5.00 6.00 390.00 APC @ 0.5 % 0.05 0.10 0.23 0.34 0.37 0.36 0.23 0.11 0.08 0.06 0.03 0.03 1.95 Net Gen. (MU) 8.96 18.91 44.78 67.66 73.63 71.64 44.78 20.90 14.93 10.95 4.98 5.97 388.05 0.00 Myntriang Small HEP - Stage II (3 MW + 1.5 MW Enhancement from December'15) Gross Gen. (MU) 1.59 1.94 1.94 1.94 1.94 1.94 1.94 1.94 2.22 2.12 1.68 1.46 22.68 APC @ 1% Net Gen. (MU) 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.01 0.23 1.58 1.92 1.92 1.92 1.92 1.92 1.92 1.92 2.20 2.10 1.66 1.44 22.45 0.00 Myntriang Small HEP - Stage I (6 MW + 3 MW Enhancement - both from December'15) Gross Gen. (MU) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.46 5.43 4.29 3.73 18.91 APC @ 1% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.04 0.04 0.19 Net Gen. (MU) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.40 5.38 4.25 3.69 18.72 123.34 135.66 155.29 186.31 201.69 195.63 175.62 154.54 159.87 154.42 139.62 148.71 1930.71 7.64 7.78 7.42 8.18 8.40 8.13 8.35 8.47 8.89 8.74 8.29 8.85 99.14 115.70 127.88 147.88 178.12 193.28 187.50 167.27 146.07 150.99 145.68 131.33 139.87 1831.57 0.00 APGCL Gross Gen. (MU) APC @5.1% Net Gen. (MU) 521.92 Note: Earlier NRPP GT was expected to be commissioned by March'15 and the WHRU by September'15 as per BHEL's target date. However, based on the present work in progress, the GT unit is now expected to be commissioned in Aug'15 and the Waste Heat Recovery Unit in April'16. Assam Power Generation Corporation Limited Page 80 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Projected Gas Price for NTPS/ LTPS 2015-16 Remarks Namrup Thermal Power Station A. Gas supplied by OIL, Duliajan (APM) 1.00 Basic Price (for G.C.V. 10000)/ 1000 SCM 7399.45 2.00 3.00 4.00 Basic Price after adjustment (for G.C.V. 9300 Average) 6881.33 200.00 167.56 7048.90 845.87 7894.77 5.00 B. 1.00 2.00 3.00 Marketing Margin (for NCV 10000) /1000 SCM Marketing Margin after adjustment (for N.C.V. 8378/1000 SCM) Total VAT @ 12 % on above Total (A) As per new gas price implemented from Nov'2014 T.C. for Transportation of the OIL Gas by AGCL T.C./ 1000 SCM Fuel surcharge/ 1000 SCM Total Service Tax @ 12.36% on TC Total (B) Landed price of gas supplied to NTPS (A+B)/ 1000 SCM 417.69 31.76 449.45 51.63 501.08 Yearly escalation 3% on TC as per agreement. 8395.84 Lakwa Thermal Power Station A. Gas supply by GAIL (APM) 1.00 Basic Price (for G.C.V. 10000)/ 1000 SCM 7399.45 2.00 10% Royalty /1000 SCM Included Total 7399.45 3.00 Basic Price after adjustment (for G.C.V. 9793 Average)/ 1000 SCM 7246.48 4.00 Marketing Margin (for NCV 10000) /1000 SCM 200.00 5.00 Marketing Margin after adjustment (for N.C.V. 8823/1000 SCM) 176.46 6.00 VAT @ 12 % on above Total (A) B. Fixed Monthly Service charge(Rs./ 1000 SCM) Landed price of gas supply to LTPS by GAIL (A+B)/ 1000 SCM C. 890.75 8313.69 20.66 8334.35 Gas supplied by OIL Duliajan (Non APM) 1.00 Basic Price (for G.C.V. 10000)/ 1000 SCM 12332.42 2.00 Basic Price after adjustment (for GCV 9300 /1000 SCM) 11468.89 3.00 Marketing Margin (for NCV 10000) /1000 SCM 4.00 Marketing Margin after adjustment (for N.C.V. 8378/1000 SCM) Total VAT @ 12 % on above 167.56 11636.45 1396.37 Total (C) 13032.83 5.00 As per new gas price implemented from Nov'2014 As per new gas price implemented from Nov'2014 200.00 Assam Power Generation Corporation Limited Page 81 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 D. T.C for Transportation of OIL gas by AGCL T.C./ 1000 SCM 651.14 80.48 731.62 Service Tax @ 12.36% on TC Total Landed price of gas supply to LTPS by OIL (C+D)/ 1000 SCM Yearly escalation 3% on TC as per agreement. 13764.45 APGCL’s Projected Fuel cost for FY 2015-16 Cost of Fuel (NTPS) 2015-16 All units of Namrup TPS (From Apr'15Jul'15) Generation by APM Gas Gross Generation by APM Gas (MU) Net Generation by APM Gas (MU) Gross Heat Rate on GCV basis Kcal/Kwh Rate of Gas (for GCV 9300 Kcal/CUM) Rs./1000 CUM Cost of APM Gas (NTPS) in Rs. Average Gross Calorific of Gas Kcal/CUM Gas Quantity MMSCM 179.17 169.36 4170.00 7894.77 634276028.77 9300 80.34 Transportation Charge of Gas TC Rate of Gas Rs. /1000 CUM Total TC in Rs. Total cost of Fuel including TC Say Rs. In Cr. 501.08 40257155.64 674533184.41 67.45 Namrup TPS with Units 1, 2 & 6 after Commissioning of NRPP GT (From Aug'15-Mar'16) Generation by APM Gas Gross Generation by APM Gas (MU) Net Generation by APM Gas (MU) Gross Heat Rate on GCV basis Kcal/Kwh Rate of Gas (for GCV 9300 Kcal/CUM) Rs./1000 CUM Cost of APM Gas (NTPS) in Rs. Average Gross Calorific of Gas Kcal/CUM Gas Quantity MMSCM 163.81 154.80 4044 7894.77 562311019.38 9300 71.23 Transportation Charge of Gas TC Rate of Gas Rs. /1000 CUM Total TC in Rs. Total cost of Fuel including TC 501.08 35689575.51 598000594.90 Say Rs. In Cr. Total Cost of Gas 59.80 127.25 Total Gross NTPS Generation in 2015-16 (MU) Total Net NTPS Generation in 2015-16 (MU) 342.98 324.16 Average Fuel Cost Rs./Kwh Average Fuel Cost Rs./Kwh Sentout 3.71 3.93 NRPP (63 MW GT from Jan'16) Generation by APM Gas Assam Power Generation Corporation Limited Page 82 of 228 Cr. Cr. Cr. Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Gross GT Generation by APM Gas (MU) Net GT Generation by APM Gas (MU) Gross GT Heat Rate on GCV basis Kcal/Kwh Rate of Gas (for GCV 9300 Kcal/CUM) Rs./1000 CUM Cost of APM Gas (NRPP) in Rs. Average Gross Calorific of Gas Kcal/CUM Gas Quantity MMSCM Transportation Charge of Gas TC Rate of Gas Rs. /1000 CUM Total TC in Rs. Total cost of Fuel including TC Say Rs. In Cr. NRPP Fuel Cost Rs./Kwh NRPP Fuel Cost Rs./Kwh Sentout 295.14 281.57 2830 7894.77 709062012.33 9299.79 89.81 501.08 45003781.47 754065793.80 75.41 2.55 2.68 Cost of Fuel (LTPS) 2015-16 LTPS Fuel Cost Rs./Kwh Lakwa TPS with Waste Heat Unit Gross GT Generation by GAIL Gas (MU) Net GT Generation by GAIL Gas (MU) Gross GT Heat Rate on GCV basis Kcal/Kwh Average GCV of GAIL Gas Kcal/CUM GAIL Gas Quantity MMSCM Rate of Gas of GAIL Rs./1000 CUM Rate of GAIL Service Charge of transportatrion of Gas Rs./1000 CUM Total Rate of Gas of GAIL Rs./1000 CUM Cost of APM Gas (GAIL) in Rs. (A) (B) Generation by Non-APM Gas from OIL Gross GT Generation by OIL Gas (MU) Net GT Generation by OIL Gas (MU) Gross GT Heat Rate on GCV basis Kcal/Kwh Average GCV of OIL Gas Kcal/CUM OIL Gas Quantity MMSCM Rate of Gas of OIL Rs./1000 CUM Cost of Non-APM Gas (OIL) in Rs. TC Rate of Gas of OIL Rs. /1000 CUM Total TC in Rs. Total Fuel Cost for OIL Gas (B) Total Fuel Cost of LTPS (A) + (B) Say Rs. In Cr. Waste Heat Unit 8 Gross Generation (MU) Waste Heat Unit 8 Net Generation (MU) Total Gross Generation LTPS (MU) Total Net Generation LTPS (MU) Average LTPS Fuel Cost Rs./Kwh Average LTPS Fuel Cost Rs./Kwh Sentout Assam Power Generation Corporation Limited 357.54 332.51 4010.00 9793 146.40 8313.69 20.66 8334.35 1220148728.01 332.33 309.07 4010.00 9300 143.30 13032.83 1867604279.30 731.62 104841013.18 1972445292.49 3192594020.50 319.26 171.12 155.04 861.00 796.62 3.71 4.01 Page 83 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Annexure II 10. Abstract of Technical Data for FY 2015-16 Assam Power Generation Corporation Limited Page 84 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Abstract of Technical Data PertainingtoAPGCL(2015-16) Name of the Power Station Namrup TPS (From Apr'15 to Jul'15) Capacity Availability (MW) Factor (%) PLF% Gas Source OIL APM OIL 44.1% APM 119.50 54.2% 63.50 46.6% 105.50 50.6% 47.8% NRPP 63 MWGT (From Aug'15 to Mar'16) 63.00 83.9% 80.0% Lakwa WHRP 37.20 57.8% 52.4% 70.4% GAIL APM 65.4% OIL Non- Namrup TPS (U 1, 2 & 6) (From Aug'15 to Mar'16) NTPS Total Lakwa TPS (GT) 120.00 Total LTPS with WHRP 157.20 67.9% Karbi Langpi HEP 100.00 90% 4.50 Myntriang SHEP Stage-II Myntriang SHEP Stage-I Total APGCL 51.2% OIL APM 62.8% Gross (MU) %APC APC(MU) Station Heat GCV of Gas Total Gas Sp. Gas Rate on GCV Net (MU) Gas Kcal/ Availability Cons. (SCM/ Fuel cost (Rs.) Basis SCM (mscmd) (mscm) Kwh) (Kcal/ Kwh) TC(Rs.) Cost of Cost of fuel fuel (Rs./ (Sent out) Kwh) (Rs./ Kwh) 179.17 5.5% 9.81 169.36 9300 0.66 80.34 0.4484 4170 634276029 40257156 674533184 3.76 3.98 163.81 5.5% 9.01 154.80 9300 0.29 71.23 0.4348 4044 562311019 35689576 598000595 3.65 3.86 342.98 5.5% 18.82 324.16 9300 0.57 151.57 0.4419 4110 1196587048 75946731 1272533779 3.71 3.93 295.14 4.60% 13.58 281.57 9300 0.37 89.81 0.3043 2830 45003781 2.55 2.68 171.12 9.40% 16.09 155.04 9793 0.40 146.40 0.4095 4010 1220148728 7.00% 48.29 641.58 9300 0.39 143.30 0.4312 4010 1867604279 104841013 1972445292 3.71 4.01 357.54 332.33 861.00 7.48% 44.5% N/A 390.00 0.50% 1.95 388.05 91% 80.9% N/A 22.68 1.00% 0.23 22.45 9.00 91% 80.7% N/A 18.91 1.00% 0.19 18.72 397.20 72.3% 1930.71 5.13% 59.5% Total Fuel cost (Rs.) 64.38 796.62 99.14 1831.57 709062012 754065794 0 1220148728 9549 0.79 289.70 0.3365 3213 3087753007 104841013 3192594020 9436 2.11 531.08 0.4105 3873 4993402068 225791526 5219193594 Assam Power Generation Corporation Limited 2.70 2.85 Page 85 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Annex-III 11. Various data as per Specified formats of Hon’ble Commission. List of formats for which data has/ has not been furnished in this Petition Formats for which data have been submitted F-1,F-2,F-3, F-5, F-6, F-7, F-11, F-12, F-14, F15, F-16, F-17 Formats which are found not to be relevant F-4, F-8, F-9, F-10, F-13 Assam Power Generation Corporation Limited Page 86 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-1 SUMMARY SHEET Name of the Company Assam Power Generation Corporation Limited Name of the Power Station State District Assam Tariff Period From 01-04-2013 To 31-03-2016 S.No. Particulars (1) (2) 1. Calculation of Fixed Charges (Rs. Crs) 1.10 Depreciation [FROM-11 ] 1.20 Interest on Loan [FROM-12 ] 1.30 Return on Equity 1.40 Taxes on income 1.50 Interest on Working Capital [FROM-14 ] 1.60 O & M Expenses [FROM-15 ] 1.70 1.80 Other Finance Charges Less other Income 1.90 Prior Period Items 2013-14 2014-15 2015-16 (3) (4) (5) 25.66 32.81 48.21 31.23 29.56 49.45 38.59 0.45 40.39 0.93 58.96 0.93 22.32 120.56 26.03 121.14 30.83 168.67 0.05 -10.60 -10.07 0.05 -10.60 6.43 -10.60 R&M Expenses approved vide letter No. AERC 1.91 442/2014/15 "Order on Review Petition on Tariff 26.73 Order for FY 13-14" dated 08.07.2014 Total 2. Calculation of Rate of Energy Charge(Rs./kWh) Rate of Energy Charge from Primary Fuel (REC)p 2.20 Rate of Energy Charge from Secondary Fuel (REC) Rate of Energy Charge ex-bus (REC) ### ### 3B 3C 2 2.10 2.30 3A 1 3A,3B,3C 218.19 240.31 379.61 During Stabiliz ation 2.22 2.68 After Stabilizati on 2.85 0.00 0.00 0.00 2.22 2.68 2.85 Details of calculations to be furnished. If accounts of the company for more than one year i.e previous year, have not been audited, information as per this format may be furnished for such year(s) separately. If multi-fuel is used simultaneously; five 2.1 is respect of every fuel individually. The rate of energy charge shall be computed for open cycle operation and combined cycle operation separately in case of gas/liquid fuel fired plants The total energy charge shall be worked out based on ex-bus energy schedule to be sent out in case of plants covered by ABT, and ex-bus energy delivered sent out in case of plants not covered by ABT, as the case may be. Any escalation in fuel cost to be considered for subsequent years or FPA to take care of the escalation. PETITIONER Assam Power Generation Corporation Limited Page 87 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-2 Plant Characteristics Nam e of the Com pany Assam Pow er Generation Corporation Ltd Nam e of the Pow er Station Nam rup Therm al Pow er Station Basic characteristics of the plant 1 (I) 4 Gas Turbines (II) 1 Gas Fired Steam Turbine (III)1 Waste Heat Recovery Unit Fuel type 2 Natural Gas Module num ber of Unit num ber Details Rated Capacity (MW) Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 23 23 23 12.5 30 22.5 Apr - 65 Apr - 65 Apr - 65 Sep - 75 Apr - 76 Date of synchronization Mar - 85 Date of entry into commercial operation 11.25 (Single Boiler) Apr - 65 Apr - 65 Apr - 65 Sep - 75 Apr - 76 Apr - 90 Date of stabilisation Apr - 65 Apr - 65 Apr - 65 Sep - 75 Apr - 76 Capacity at the date of synchronization 23 23 23 12.5 30 Apr - 90 Capacity at the date of stabilisation 23 23 23 12.5 24 15 Derated Capacity (MW) 20 21 21 11 24 22.5 Has any performance test been performed No No No No No No NOT APPLICABLE If yes,capacity at test Type of cooling systen for condenser 3 Type of Boiler Feed pump 4 - - - Type of cooling system for electric generator 5 HydrogenHydrogen Hydrogen Any other special feature 6 - - Air - - Has the station received any notice or shut dow n the pow er station of penalty imposed for violation of any environmental standard by the Central/State Statutory Authorities Water Water BF-20 WEIR Air BF-20 WEIR Make Air Could not be loaded upto rated Could not be loaded upto rated capacity No If yes, furnish full details 1 Describe the basic characteristics of the plant e.g. in the case of a coal based plant w hether it is a conventional steam generator or circulating fluidized bed combustion generator or sub-critical once through steam generator etc. 2 Coal or natural gas or naphta or lignite etc. 3 Closed circuit cooling, once through cooling,sea cooling etc. 4 Motor driven, Steam turbine deriven etc. 5 Air cooled, w ater cooled, hydrogen cooled etc. 6 Any special feature such as merry-go-round, scrubbers etc.Specify all such features. PETITIONER Assam Power Generation Corporation Limited Page 88 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-3 Normative Parameters Name of the Company : Assam Power Generation Corp. Ltd. Name of the Power Station : Namrup Thermal Power Station Particulars Target Availability (Gross Generation in MU) Target Availability (%) FY 2012-13 Last Audited Year 2013-14 Current Year 2014-15 Ensuing Year 2015-16 533.17 526.58 591.66 342.98 54% 51% 51% 61.7% 50% 62.6% Normative PLF (%) 57% 48% Auxilary consumption(%) 5.6% 6.0% 5.8% 5.5% 4093 3976 4056 4562 4773 5405 5484 4429 Gross Station Heat Rate on GCV k.Cal/kWh Hours of operation at Target Availability Hours of operation at Target PLF Sp. Gas consumption (SCM/kWh) 4459 4362 4993 4186 0.4458 0.4290 0.4254 0.4419 O& M Charges (% of CC for plants less than 5 years old) (Based on actuals for plants more than 5 years Coal stock expense in months for working capital (WC) Oil stock in months for WC Spares stock for WC as % of O&M Receivables in Months for WC Rate of Return on Equity (%) PETITIONER Assam Power Generation Corporation Limited Page 89 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-2 Plant Characteristics Nam e of the Com pany Assam Pow er Generation Corporation Ltd Nam e of the Pow er Station Lakw a Therm al Pow er Station Basic characteristics of the plant 1 Gas Turbine Fuel type 2 Natural Gas Module num ber of Unit num ber Details Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 Unit 7 15 15 15 15 20 20 20 Rated Capacity (MW) 30-07-83 26-04-81 02-08-81 28-11-86 03-01-94 26-07-94 24-05-99 Date of synchronization Capacity at the date of synchronization 15 15 15 15 20 20 20 Date of entry into commercial operation 30-07-83 26-04-81 02-08-81 28-11-86 03-01-94 26-07-94 24-05-99 02-08-83 29-04-81 05-08-81 01-12-86 06-01-94 29-07-94 27-05-99 Date of stabilisation 15 Capacity at the date of stabilisation Has any performance test been performed Yes 15 If yes,capacity at test - Type of cooling systen for condenser 3 - Type of Boiler Feed pump 4 Type of cooling system for electric generatorAir Any other special feature 6 Unit 8 37.2 17.08.11 11 (w ith 1 HRSG) 17-01-12 17.01.12 15 15 15 20 20 20 33 Yes Yes Yes Yes Yes Yes Yes 15 15 15 20 20 20 - - - - - - - Water - - - - - - Air Air Air Air Air Air Kirloskar (325 KW, 53 CUM/Hr)/Sulzer (9.5 KW, 13.5 CUM/Hr) Air Scrubbers Scrubbers Scrubbers Scrubbers Scrubbers Scrubbers Scrubbers Has the station received any notice or shut dow n the pow er station of penalty imposed for violation of any environmental standard by the Central/State Statutory Authorities No If yes, furnish full details 1 Describe the basic characteristics of the plant e.g. in the case of a coal based plant w hether it is a conventional steam generator or circulating fluidized bed combustion generator or sub-critical once through steam generator etc. 2 Coal or natural gas or naphta or lignite etc. 3 Closed circuit cooling, once through cooling,sea cooling etc. 4 Motor driven, Steam turbine deriven etc. 5 Air cooled, w ater cooled, hydrogen cooled etc. 6 Any special feature such as merry-go-round, scrubbers etc.Specify all such features. PETITIONER Assam Power Generation Corporation Limited Page 90 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-3 Normative Parameters Name of the Company : Assam Power Generation Corp. Ltd. Name of the Power Station : Lakwa Thermal Power Station with WHRU FY 201213 Particulars Target Availability (Gross Generation in MU) Target Availability (%) Normative PLF (%) Auxilary consumption(%) Gross Station Heat Rate on GCV k.Cal/kWh Hours of operation at Target Availability Hours of operation at Target PLF Sp. Gas consumption (SCM/kWh) Last Audited Year 2013-14 Current Year 2014-15 Ensuing Year 2015-16 888.00 896.15 935.30 861.00 73% 86.1% 78.4% 68% 64% 65% 68% 63% 11.5% 8.8% 8.6% 7.5% 3066 3164 3058 3213 6395 7542 6868 5946 5606 5703 5957 5506 0.3219 0.3303 0.3088 0.3365 O& M Charges (% of CC for plants less than 5 years old) (Based on actuals for plants more than 5 years Coal stock expense in months for working capital (WC) Oil stock in months for WC Spares stock for WC as % of O&M Receivables in Months for WC Rate of Return on Equity (%) PETITIONER Assam Power Generation Corporation Limited Page 91 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-2 Plant Characteristics Name of the Company Assam Power Generation Corporation Ltd Name of the Power Station Karbi Langpi HEP Basic characteristics of the plant 1 (I) Fuel type 2 NIL Details 2 WaterTurbines Module number of Unit number Unit 1 Unit 2 Rated Capacity (MW) Date of synchronization Capacity at the date of synchronization Date of entry into commercial operation Date of stabilisation Capacity at the date of stabilisation Has any performance test been performed If yes,capacity at test Type of cooling systen for condenser 3 50 31-01-07 50 06-04-07 06-04-07 50 Yes 50 Not applicable 50 20-03-07 50 06-04-07 06-04-07 50 Yes 50 Not applicable Type of Boiler Feed pump 4 Not applicable Not applicable Air Air - - Type of cooling system for electric generator 5 Any other special feature 6 Has the station received any notice or shut down the power station of penalty imposed for violation of any environmental standard by the Central/State Statutory Authorities If yes, furnish full details 1 Describe the basic characteristics of the plant e.g. in the case of a coal based plant whether it is a conventional steam generator or circulating fluidized bed combustion generator or sub2 Coal or natural gas or naphta or lignite etc. 3 Closed circuit cooling, once through cooling,sea cooling etc. 4 Motor driven, Steam turbine deriven etc. 5 Air cooled, water cooled, hydrogen cooled etc. 6 Any special feature such as merry-go-round, scrubbers etc.Specify all such features. PETITIONER Assam Power Generation Corporation Limited Page 92 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-3 Normative Parameters Name of the Company : Assam Power Generation Corp. Ltd. Name of the Power Station : Karbi Langpi HEP Particulars Target Availability (Gross Generation in MU) Target Availability (%) FY 201213 Last Audited Year 2013-14 Current Year 2014-15 Ensuing Year 2015-16 344.02 422.51 366.98 390.00 93% 91.5% 92.6% 90% Normative PLF (%) 39% 48% 42% 45% Auxilary consumption(%) 0.5% 0.5% 0.5% 0.5% Gross Station Heat Rate on GCV k.Cal/kWh Hours of operation at Target Availability N/A N/A N/A N/A 8103 8015 8112 7924 Hours of operation at Target PLF 3425 4205 3679 3900 Sp. Gas consumption (SCM/kWh) O& M Charges (% of CC for plants less than 5 years old) (Based on actuals for plants more than 5 years Coal stock expense in months for working capital (WC) Oil stock in months for WC Spares stock for WC as % of O&M Receivables in Months for WC Rate of Return on Equity (%) PETITIONER Assam Power Generation Corporation Limited Page 93 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-5 Statement of Project Cost Upto (COD) Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Lower Kopili HEP Cost in Rs. Crore2 Sl. No. (1) 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical BOP Electrical & C & I External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & Equipment Initial spares Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works Erection Testing and commissioning Procurement & Management fee Installation & Engineering Estab./Construction supervision Training Construction Insurance Tools & Plants Acess and diversion Road Operators training As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 94 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1.25 1.26 2.0 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 Start up fuel Shared Facilities costs Taxes and Duties Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expences Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin Name of the Power Station 1275.00 195.00 1470.00 13.5 Myntriang SHEP Cost in Rs. Crore2 Sl. No. (1) 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical BOP Electrical & C & I External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & Equipment Initial spares Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works Erection Testing and commissioning Procurement & Management fee As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 95 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1.18 1.19 1.20 1.21 1.22 1.23 1.24 1.25 1.26 2.0 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 Installation & Engineering Estab./Construction supervision Training Construction Insurance Tools & Plants Acess and diversion Road Operators training Start up fuel Shared Facilities costs Taxes and Duties Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expences Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin Note: Details of Functional Assets Created on Capitalization Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Lines & Cable Network Vehicles Furniture & fixtures Office equipment Capital spares at generating stations Total: Name of the Power Station 134.83 12.45 147.28 11.12 1.63 40.45 13.52 76.75 3.81 0.00 0.00 0.00 0.00 147.28 Lungnit SHEP Cost in Rs. Crore2 Sl. No. (1) 1.0 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 96 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 1.25 1.26 2.0 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical BOP Electrical & C & I External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & Equipment Initial spares Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works Erection Testing and commissioning Procurement & Management fee Installation & Engineering Estab./Construction supervision Training Construction Insurance Tools & Plants Acess and diversion Road Operators training Start up fuel Shared Facilities costs Taxes and Duties Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expences Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin 50.81 4.80 55.61 Note: Assam Power Generation Corporation Limited Page 97 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Details of Functional Assets Created on Capitalization Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Lines & Cable Network Vehicles Furniture & fixtures Office equipment Capital spares at generating stations Total: Name of the Power Station 1.48 1.35 20.33 1.96 29.27 1.13 0.00 0.06 0.03 0.00 55.61 KLHEP (Intermediate Stage-I) Cost in Rs. Crore2 Sl. No. (1) 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical BOP Electrical & C & I External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & Equipment Initial spares Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works Erection Testing and commissioning Procurement & Management fee Installation & Engineering Estab./Construction supervision Training As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 98 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1.21 1.22 1.23 1.24 1.25 1.26 2.0 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 Construction Insurance Tools & Plants Acess and diversion Road Operators training Start up fuel Shared Facilities costs Taxes and Duties Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expences Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin Name of the Power Station 191.62 18.38 210.00 KLHEP (Intermediate Stage-II) Cost in Rs. Crore2 Sl. No. (1) 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical BOP Electrical & C & I External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & Equipment Initial spares Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 99 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 1.25 1.26 2.0 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 Erection Testing and commissioning Procurement & Management fee Installation & Engineering Estab./Construction supervision Training Construction Insurance Tools & Plants Acess and diversion Road Operators training Start up fuel Shared Facilities costs Taxes and Duties Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expenses Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin Name of the Power Station 228.12 21.88 250.00 KLHEP Barrage Toe Project Cost in Rs. Crore2 Sl. No. (1) 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical BOP Electrical & C & I External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 100 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 1.25 1.26 2.0 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 Equipment Initial spares Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works Erection Testing and commissioning Procurement & Management fee Installation & Engineering Estab./Construction supervision Training Construction Insurance Tools & Plants Acess and diversion Road Operators training Start up fuel Shared Facilities costs Taxes and Duties Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expences Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin Name of the Power Station 173.37 16.63 190.00 Namrup Replacement Power Project Cost in Rs. Crore2 Sl. No. (1) 1.0 1.1 1.2 1.3 1.4 1.5 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 101 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 1.25 1.26 2.0 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 BOP Electrical & C & I External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & Equipment Initial spares Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works Erection Testing and commissioning Procurement & Management fee Installation & Engineering Estab./Construction supervision Training Construction Insurance Tools & Plants Acess and diversion Road Operators training Start up fuel Shared Facilities costs Taxes and Duties Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expences Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin Note: Details of Functional Assets Created on Capitalization Land & Rights Buildings Hydraulic 614.73 79.00 693.73 0.00 0.00 0.00 Assam Power Generation Corporation Limited Page 102 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Other civil works Plant & Machinery Lines & Cable Network Vehicles Furniture & fixtures Office equipment Capital spares at generating stations Total: Name of the Power Station 31.72 643.92 1.30 0.00 5.60 0.00 11.19 693.73 Lakwa Replacement Power Project Cost in Rs. Crore2 Sl. No. (1) 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 1.25 1.26 2.0 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical BOP Electrical & C & I External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & Equipment Initial spares Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works Erection Testing and commissioning Procurement & Management fee Installation & Engineering Estab./Construction supervision Training Construction Insurance Tools & Plants Acess and diversion Road Operators training Start up fuel Shared Facilities costs Taxes and Duties As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 103 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expences Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin 282.65 55.59 338.24 Note: Details of Functional Assets Created on Capitalization Civil works 16.50 Plant & Machinery 253.88 Contingency 7.68 Env. Management Planning 2.20 Overhead Charges 2.39 IDC & FC 55.59 Total: 338.24 Name of the Power Station Margherita Thermal Power Project Cost in Rs. Crore2 Sl. No. (1) 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical BOP Electrical & C & I External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & Equipment Initial spares As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 104 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 1.25 1.26 2.0 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works Erection Testing and commissioning Procurement & Management fee Installation & Engineering Estab./Construction supervision Training Construction Insurance Tools & Plants Acess and diversion Road Operators training Start up fuel Shared Facilities costs Taxes and Duties Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expences Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin Name of the Power Station 3072.70 493.30 3566.00 Cachar Distributed Generation System by Gas IC Engine Cost in Rs. Crore2 Sl. No. (1) 1.0 1.1 1.2 1.3 1.4 1.5 1.6 Break Down1 (2) Cost of Land, Works, Plant & Equipment, service Land & Preliminary Investigation Site Development Steam Generator Island Tribune Generator Island BOP Mechanical BOP Electrical & C & I As per Original Approved (3) Completed Cost as on COD (4) Variation Reasons for Variation Admitted Cost3 (5) (6) (7) Assam Power Generation Corporation Limited Page 105 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 1.25 1.26 2.0 2.10 2.20 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 5.0 6.0 7.0 External water supply system External coal transportation system Rolling stock and locomotives Ash disposal Plant & Equipment Initial spares Civil Woks Ash disposal area development Township & Colony Temp. construction & enabling works Erection Testing and commissioning Procurement & Management fee Installation & Engineering Estab./Construction supervision Training Construction Insurance Tools & Plants Acess and diversion Road Operators training Start up fuel Shared Facilities costs Taxes and Duties Custom Duty Other Taxes & Duties Overheads Development expenses Legal fee etc. Eastablishment Owners Engg.Expenses Pre-operative expences Audit & Accounts Contingency Project cost without IDC & FC 4 IDC & FC Project cost including IDC & FC Working Capital Margin 146.14 16.82 162.96 1 The break down shown here is only illustrative for a Coal/lignite based project.In case of Gas/Liquid fuel based projects, break down in similar manner in the relevant heads applicable for such plants may be furnished. The petitioners may vary the break down incase of need.As far as possible the breakdown given here are to be adhered to. 2 If there are any iteams,which need to be shown in Indian Rupee and foreign currency(ies), the same should be shown Assam Power Generation Corporation Limited Page 106 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 separatly alongwith the currency, the exchange rate and the date e.g. Rs.80 Cr+US$50m=Rs.280Cr atUS $=Rs.40 as on say 4.1.1999. 3 In case the project has been completed and any tariff notification(s) has already been issued in the past by AERC, fill column 7 giving the cost as admitted by-(name of the authority) for the purpose of tariff notification already issued (enclose copy of tariff order). 4 If IDC has not been maintained separately and forms part of column 4, give a foot note accordingly. PETITIONER FORM-6 Final Package upto COD/ Transfer Scheme Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Lower Kopili HEP 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 1470.00 2 Debt: Equity Ratio as per transfer scheme (1) State Govt. Loan PFC Loan Public Bond Others MNRE NABARD New Loan Total Loans Grants Equity Foreign Domestic (Govt.) Total Equity Financial Package as Approved Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 (5) As Admitted on COD Currency and Amount (6) 1020.00 1020.00 450.00 450.00 Assam Power Generation Corporation Limited Page 107 of 228 (7) 3 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Name of the Company Assam Power Generation Corporation Limited Name of the Power Station 13.5 MW Myntriang SHEP 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 147.28 2 Debt: Equity Ratio as per transfer scheme Financial Package as Approved (1) State Govt. Loan PFC Loan Public Bond Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 As Admitted on COD Currency and Amount (5) (6) 39.82 Total Loans Grants 39.82 NABARD MNRE State Govt. Equity Foreign Domestic Total Equity 46.14 15.75 1.97 43.59 Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Lungnit SHEP Stage I & Stage II 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 55.00 2 Assam Power Generation Corporation Limited Page 108 of 228 (7) 3 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Debt: Equity Ratio as per transfer scheme (1) State Govt. Loan PFC Loan Public Bond Others Financial Package as Approved Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 (5) As Admitted on COD Currency and Amount (6) 3 (7) 2.00 30.50 32.50 Total Loans Grants NEC MNRE Total Grants Equity Foreign Domestic Total Equity 4.50 18.00 22.50 Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Namrup Replacement Power Project 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 693.73 2 Debt: Equity Ratio as per transfer scheme (1) State Govt. Loan PFC Loan NEC MNES NABARD Public Bond Financial Package as Approved Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 (5) As Admitted on COD Currency and Amount (6) 13.98 486.00 Assam Power Generation Corporation Limited Page 109 of 228 (7) 3 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Total Loans 499.98 Grants 193.75 Equity Foreign Domestic Total Equity Name of the Company Assam Power Generation Corporation Limited Name of the Power Station KLHEP (Intermediate Stage-I) 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 210.00 2 Debt: Equity Ratio as per transfer scheme (1) State Govt. Loan PFC Loan NEC MNES NABARD New Loans Total Loans Financial Package as Approved Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 (5) As Admitted on COD Currency and Amount (6) 147.00 147.00 Grants Equity Foreign Domestic(Govt.) Total Equity 63.00 63.00 Name of the Company Assam Power Generation Corporation Limited Name of the Power Station KLHEP (Intermediate Stage-II) Assam Power Generation Corporation Limited Page 110 of 228 (7) 3 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 250.00 2 Debt: Equity Ratio as per transfer scheme (1) State Govt. Loan PFC Loan NEC MNES NABARD New Loans Total Loans Financial Package as Approved Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 (5) As Admitted on COD Currency and Amount (6) 3 (7) 175.00 175.00 Grants Equity Foreign Domestic(Govt.) Total Equity 75.00 75.00 Name of the Company Assam Power Generation Corporation Limited Name of the Power Station KLHEP Barrage Toe project 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 190.00 2 Debt: Equity Ratio as per transfer scheme (1) State Govt. Loan PFC Loan NEC Financial Package as Approved Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 (5) Assam Power Generation Corporation Limited As Admitted on COD Currency and Amount (6) Page 111 of 228 (7) 3 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 MNES NABARD New Loans Total Loans 133.00 133.00 Grants Equity Foreign Domestic(Govt) Total Equity 57.00 57.00 Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Cachar Distributed Generating System 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 162.96 2 Debt: Equity Ratio as per transfer scheme (1) State Govt. Loan PFC Loan NEC MNES NABARD New Loans Total Loans Financial Package as Approved Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 (5) As Admitted on COD Currency and Amount (6) 114.07 114.07 Grants Equity Foreign Domestic (Govt) Total Equity 48.89 48.89 Name of the Company Assam Power Generation Corporation Assam Power Generation Corporation Limited Page 112 of 228 (7) 3 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Limited Name of the Power Station Lakwa Replacement power project 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 338.24 2 Debt: Equity Ratio as per transfer scheme (1) State Govt. Loan PFC Loan NEC MNES NABARD New Loans Total Loans Financial Package as Approved Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 (5) As Admitted on COD Currency and Amount (6) 265.10 265.10 Grants Equity Foreign Domestic (Govt.) Total Equity 73.14 73.14 Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Margherita TPP 1 Project Cost as on COD or as per transfer scheme Date of Commercial Operation 3566.00 2 Debt: Equity Ratio as per transfer scheme Assam Power Generation Corporation Limited Page 113 of 228 (7) 3 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 (1) State Govt. Loan PFC Loan NEC MNES NABARD New Loans Total Loans Financial Package as Approved Currency and 3 Amount (2) (3) Financial as on COD Currency and Amount (4) 3 As Admitted on COD Currency and Amount (5) (6) 3 (7) 2496.20 2496.20 Grants Equity Foreign Domestic (Govt.) Total Equity 1069.80 1069.80 1 Say US $ 200m+ Rs.400 Cr or Rs. 1200 Cr including US $200m at an exchange rate of 1US $=Rs.40/- 2 Date of Commercial Operation means Commercial Operation of the last unit For example : US $, 200m etc. 3 PETITIONER FORM-7 Statement Giving Details of Project Specific Loans 1 (As on COD /as per Transfer Scheme) Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Assam Power Generation Corporation Limited Page 114 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Particulars (1) 2 Source of Loan Package1 Package2 (2) State Govt., PFC Public Bond and others (3) Pack age3 (4) Pack age4 (5) Pack age5 (6) Pack age6 (7) Yes/ No Yes/ No Yes/ No Yes/ No 3 Currency Amount of Loan 4 Interest Type Fixed Interest Rate, if applicable Base Rate, if 5 Floating Interest Margin, if Floating 6 Interest Are there any 7 Caps/Floor Moratorium 8 Period Moratorium effective from Repayment 9 Period Repayment 10 Frequency Base Exchange 11 Rate Date of Base Exchange Rate See Details below Yes/No Yes/No 1 In case the project has been completed and any tariff notification(s) has already been issued in the past by AERC, the details in this form would pertains to loan package as on COD/ or as per transfer schme. 2 Source of loan means the agency from whom the loan has been taken such as WB, ADB, OECF, KWF, SBI, ICICI, IFC, PFC ETC. 3 Currency refers to currency of loan such as US $, DM, Yen, Indian Rupee etc. 4 Interest type means whether the interest is fixed or floating 5 Base rate means the base as PLR, LIBOR, etc. over which the margin is to be added. 6 Margin means the points over and above the floating rate. 7 At times caps/floor are put at which the floating rates are frozen. If such a condition exists, specify the limits. 8 9 Moratorium period refers to the period during which loan servicing liability is not required. Repayment period means the repayment of loan such as 7 years, 10 years, 25 years etc. 10 Repayment frequency means the interval at which the debt servicing is to be done such as monthly, quarterly, half yearly, annual, etc. 11 Base exchange rate means the exchange rate prevailing as on the date of COD. PETITIONER Station KLHEP ST. NTPS Source PFC Repayment Period 2013 2014 2015 -14 -15 -16 -8.34 -8.34 -8.34 -1.27 -1.27 -1.27 Assam Power Generation Corporation Limited Page 115 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 R&M - II - LTPS LWHRP NRPP Total PFC loan repayment LTPS NTPS KLHEP Myntriang NRPP Others Total State Govt. Loan Repayment Grand total Govt. of Assam -1.22 -1.22 -1.22 -12.13 -12.13 -12.13 0.00 0.00 0.00 -22.97 -22.97 -22.97 0.00 0.00 0.00 0.00 0.00 0.00 -2.20 -1.80 -5.86 -1.00 0.00 -0.20 -4.22 -2.67 -6.06 -1.00 -1.01 -0.24 0.00 -11.06 -15.20 -22.97 -34.03 -38.16 Assam Power Generation Corporation Limited Page 116 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-11 Statement of Depreciation Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Depreciation on Additional Capitalisation Detail of FERV Depreciati Financial on on Amount of Year Capital Amount of FERV on (Starting Cost as on Additional Depreciati which Depreciation amount from COD) COD Capitalisat on Amount depreciati ion on charged (1) (2) (3) (4) (5) (6) See Details below Note: Details of calculations to be furnished. PETITIONER Assam Power Generation Corporation Limited Page 117 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 APGCL Consolidated Sl. No 1 2 3 4 5 6 7 8 9 10 11 12 13 Depreciation of Assets Land & Rights Building Hydraulic Other Civil Works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & Fixtures Office Equipemnt Roads on land belonging to other Capital spares at Generating Stations TOTAL 14 Depreciation on 90% of the Assets funded by Grants/subsidies 15 Net Depreciation Balance of accumulate d depreciatio n at the end of the year Previous year 2013-14 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year Current year 2014-15 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year Ensuing year 2015-16 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 16.02 24.99 16.24 254.70 23.97 8.31 0.93 3.65 0.50 0.00 0.72 3.82 3.02 15.07 4.27 0.21 0.12 0.04 0.05 0.00 0.00 0.00 0.00 -0.49 0.00 0.00 0.00 0.00 0.00 0.00 16.74 28.81 19.26 269.28 28.24 8.51 1.05 3.69 0.55 0.00 0.72 4.06 3.12 20.49 4.48 0.99 0.14 -2.56 0.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.46 32.87 22.38 289.77 32.72 9.50 1.19 1.14 0.61 0.00 0.74 4.41 3.59 39.43 5.21 1.06 0.12 0.16 0.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.20 37.28 25.97 329.20 37.93 10.57 1.31 1.30 0.68 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.01 151.58 3.72 0.00 155.30 7.43 0.00 162.73 3.56 0.00 166.29 500.89 31.05 -0.49 531.45 38.93 0.00 570.38 58.35 0.00 628.73 0.00 -5.39 0.00 -5.39 -6.12 0.00 -11.51 -10.14 0.00 -21.66 500.89 25.66 -0.49 526.06 32.81 0.00 558.87 48.21 0.00 607.08 Assam Power Generation Corporation Limited Page 118 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Station : NTPS Sl. No 1 2 3 4 5 6 7 8 9 10 11 12 13 Depreciation of Assets Land & Rights Building Hydraulic Other Civil Works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & Fixtures Office Equipemnt Roads on land belonging to other Capital spares at Generating Stations TOTAL 14 Depreciation on 90% of the Assets funded by Grants/subsidies 15 Net Depreciation Balance of accumulate d depreciatio n at the end of the year 0.00 8.71 3.66 1.57 121.36 0.00 0.92 0.48 3.15 0.33 0.00 46.11 186.29 Previous year 2013-14 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.17 0.11 0.07 1.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.12 0.03 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.41 2.43 0.00 0.00 -0.43 186.29 2.00 0.00 0.00 8.88 3.77 1.64 122.81 0.00 0.95 0.60 3.17 0.37 Current year 2014-15 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.17 0.17 0.12 2.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.06 -2.57 0.04 0.00 0.00 0.00 0.00 0.00 0.00 188.72 2.25 2.96 0.00 0.00 -0.43 -0.43 188.29 2.53 0.00 46.52 0.00 0.00 9.04 3.94 1.76 125.51 0.00 0.96 0.66 0.61 0.41 Ensuing year 2015-16 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.17 0.23 0.16 3.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.12 0.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00 191.67 1.66 5.97 0.00 0.00 -0.86 -0.43 190.81 5.54 0.00 48.77 Assam Power Generation Corporation Limited 0.00 9.21 4.17 1.92 129.06 0.00 1.00 0.78 0.61 0.45 0.00 50.43 197.64 -1.29 0.00 196.35 Page 119 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Station : LTPS Sl. No 1 2 3 4 5 6 7 8 9 10 11 12 13 Depreciation of Assets Land & Rights Building Hydraulic Other Civil Works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & Fixtures Office Equipemnt Roads on land belonging to other Capital spares at Generating Stations TOTAL 14 Depreciation on 90% of the Assets funded by Grants/subsidies 15 Net Total Balance of accumulate d depreciatio n at the end of the year 0.00 4.34 0.23 1.19 88.17 0.00 0.90 0.40 0.35 0.16 0.00 104.87 200.61 Previous year 2013-14 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.08 0.01 0.05 1.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.01 0.00 0.00 0.00 0.00 0.00 0.00 3.31 5.46 0.00 0.00 -0.13 200.61 5.33 0.00 0.00 4.43 0.24 1.24 90.14 0.00 0.90 0.40 0.37 0.17 Current year 2014-15 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.08 0.01 0.06 6.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.07 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 206.07 5.17 11.74 0.00 0.00 -0.13 -0.13 205.94 11.61 0.00 108.18 0.00 4.51 0.25 1.30 96.44 0.00 0.92 0.48 0.37 0.18 0.00 113.36 217.82 -0.26 0.00 217.55 Ensuing year 2015-16 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.08 0.01 0.14 7.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.00 0.00 0.00 0.00 0.00 0.00 1.61 8.86 0.00 0.00 -0.13 8.73 Assam Power Generation Corporation Limited 0.00 4.59 0.27 1.44 103.44 0.00 0.93 0.48 0.37 0.20 0.00 114.96 226.68 -0.39 0.00 226.28 Page 120 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Station : CTPS Sl. No 1 2 3 4 5 6 7 8 9 10 11 12 13 Depreciation of Assets Land & Rights Building Hydraulic Other Civil Works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & Fixtures Office Equipemnt Roads on land belonging to other Capital spares at Generating Stations TOTAL 14 Depreciation on 90% of the Assets funded by Grants/subsidies 15 Net Total Balance of accumulate d depreciatio n at the end of the year 0.00 0.02 0.06 0.04 25.85 0.00 1.34 0.05 0.15 0.01 Previous year 2013-14 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.11 0.00 0.00 0.00 0.00 28.11 0.00 0.00 0.00 0.59 0.00 0.02 0.06 0.04 25.85 0.00 1.34 0.05 0.15 0.01 Current year 2014-15 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.11 0.00 0.00 0.00 0.00 28.11 0.00 0.00 0.00 0.59 0.00 0.02 0.06 0.04 25.85 0.00 1.34 0.05 0.15 0.01 Ensuing year 2015-16 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.02 0.06 0.04 25.85 0.00 1.34 0.05 0.15 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.11 0.00 0.00 0.00 0.00 28.11 28.11 0.00 0.00 28.11 0.00 0.59 Assam Power Generation Corporation Limited 0.00 0.59 Page 121 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Station : KLHEP Sl. No 1 2 3 4 5 6 7 8 9 10 11 12 13 Depreciation of Assets Land & Rights Building Hydraulic Other Civil Works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & Fixtures Office Equipemnt Roads on land belonging to other Capital spares at Generating Stations TOTAL 14 Depreciation on 90% of the Assets funded by Grants/subsidies 15 Net Total Balance of accumulate d depreciatio n at the end of the year Previous year 2013-14 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 2.94 20.41 12.17 0.00 23.97 0.00 0.47 3.11 2.02 0.00 4.06 0.00 0.00 0.00 0.00 0.00 0.00 4.85 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.35 0.00 9.67 0.00 0.00 -2.11 64.35 7.56 0.00 0.00 3.41 23.52 14.20 0.00 28.03 4.85 0.00 0.00 0.01 Current year 2014-15 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.47 3.11 2.03 0.00 4.06 0.00 0.00 0.00 0.00 0.00 0.00 0.77 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 74.02 0.01 10.47 0.00 0.00 -2.11 -1.80 71.91 8.67 0.00 0.00 0.00 0.00 3.88 26.64 16.23 0.00 32.09 5.61 0.00 0.01 0.01 Ensuing year 2015-16 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.47 3.11 2.06 0.00 4.12 0.00 0.00 0.00 0.00 0.00 0.00 0.77 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 84.49 0.03 10.58 0.00 0.00 -3.90 -1.84 80.59 8.74 0.01 0.01 Assam Power Generation Corporation Limited 0.00 4.35 29.75 18.29 0.00 36.21 6.39 0.00 0.02 0.02 0.01 0.03 95.07 -5.74 0.00 89.33 Page 122 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Station : LWHRP Sl. No 1 2 3 4 5 6 7 8 9 10 11 12 13 Depreciation of Assets Land & Rights Building Hydraulic Other Civil Works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & Fixtures Office Equipemnt Roads on land belonging to other Capital spares at Generating Stations TOTAL 14 Depreciation on 90% of the Assets funded by Grants/subsidies 15 Net Total Balance of accumulate d depreciatio n at the end of the year 0.00 0.00 0.63 1.27 19.33 0.00 0.29 0.00 0.00 0.00 0.00 0.00 21.53 Previous year 2013-14 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.00 0.40 0.85 11.64 0.00 0.18 0.00 0.00 0.00 0.00 0.00 13.07 0.00 0.00 0.00 0.00 -0.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.49 -2.02 21.53 11.05 -0.49 0.00 0.00 1.03 2.12 30.48 0.00 0.47 0.00 0.00 0.00 Current year 2014-15 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.00 0.40 0.85 11.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 34.11 0.00 12.92 0.00 0.00 -2.02 -2.02 32.09 10.90 0.00 0.00 0.00 0.00 0.01 1.43 2.96 41.97 0.00 0.65 0.00 0.00 0.00 Ensuing year 2015-16 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.00 0.40 0.85 11.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 47.02 0.03 12.95 0.00 0.00 -4.04 -2.02 42.98 10.93 0.00 0.00 Assam Power Generation Corporation Limited 0.00 0.01 1.83 3.81 53.46 0.00 0.83 0.00 0.00 0.00 0.00 0.03 59.98 -6.06 0.00 53.92 Page 123 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Station : Myntriang SHEP Sl. No 1 2 3 4 5 6 7 8 9 10 11 12 13 Depreciation of Assets Land & Rights Building Hydraulic Other Civil Works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & Fixtures Office Equipemnt Roads on land belonging to other Capital spares at Generating Stations TOTAL 14 Depreciation on 90% of the Assets funded by Grants/subsidies 15 Net Total Balance of accumulate d depreciatio n at the end of the year Previous year 2013-14 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.18 0.03 0.00 0.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.42 0.00 0.00 0.00 -0.70 -0.28 0.00 0.00 0.18 0.03 0.00 0.21 0.00 0.00 0.00 0.00 0.00 0.00 0.42 -0.70 0.00 -0.28 Current year 2014-15 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.00 0.37 0.06 0.00 0.42 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.84 0.00 0.00 -1.74 -0.90 0.00 0.00 0.55 0.08 0.00 0.62 0.01 0.00 0.00 0.00 0.00 0.00 1.27 -2.44 0.00 -1.18 Ensuing year 2015-16 Depreciatio Withdrawl Balance of n for the of accumulate year depreciatio d n depreciatio n at the end of the year 0.00 0.01 0.65 0.14 0.00 1.10 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.94 0.00 0.00 -2.46 -0.52 Assam Power Generation Corporation Limited 0.00 0.01 1.20 0.22 0.00 1.72 0.06 0.00 0.00 0.00 0.00 0.00 3.21 -4.90 0.00 -1.69 Page 124 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Station: NRPP Previous year 2013-14 Sl. No Depreciation of Assets Current year 2014-15 Balance of accumulated depreciation at the end of the year Depreciation for the year Withdrawl of depreciation Balance of accumulated depreciation at the end of the year Depreciation for the year Withdrawl of depreciation Balance of accumulated depreciation at the end of the year Ensuing year 2015-16 Depreciation Withdrawl of Balance of for the year depreciation accumulated depreciation at the end of the year 1 2 3 4 5 6 7 Land & Rights Building Hydraulic Other Civil Works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.26 17.39 0.00 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.26 17.39 0.00 0.02 8 9 10 Vehicles Furniture & Fixtures Office Equipemnt Roads on land belonging to other Capital spares at Generating Stations 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.15 0.00 0.00 0.00 0.00 0.00 0.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.24 0.00 0.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.05 0.00 18.05 0.00 0.00 0.00 -3.26 0.00 0.00 0.00 14.78 11 12 14 Depreciation on 90% of the Assets funded by Grants/subsidies 15 Net Total 0.00 0.00 0.00 0.00 0.00 Assam Power Generation Corporation Limited -3.26 0.00 14.78 Page 125 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-12 Statement showing Computation of Interest on Various Loans Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Particulars (1) (2) Year 1 Original Currency Loan-1 Loan-2 and so on Total Total Openin Openin Closing Closing Interest Repay Repay Interest Repay Interest g g Balanc Balanc due ment due due Balanc ment Balanc ment e e e e (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) Rs. Year 2 Original Currency Rs. Year 3 Original Currency See Details below Rs. Year... Original Currency Rs. Year... Original Currency Rs. Total Original Currency Rs. PETITIONER Existing Loans PFC O/Balance Additions Repayments C/Balance Total Interest Interest capitalised Interest charged to P&L A/c State Govt. Loan O/Balance Additions 13-14 14-15 15-16 306.48 50.00 -22.97 333.51 37.46 -15.32 22.14 333.51 0.00 -22.97 310.55 38.37 -18.65 19.72 310.55 160.00 -22.97 447.58 46.61 -9.77 36.84 117.58 18.57 136.15 47.38 172.46 71.85 Assam Power Generation Corporation Limited Page 126 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Repayments 0.00 -11.07 -15.20 C/Balance 136.15 172.46 229.12 Interest 13.21 14.04 17.15 Interest to be capitalised -4.12 -4.20 -4.54 Interest to be charged to P&L 9.09 9.84 12.62 Other O/Balance 0.00 0.00 0.00 Additions 0.00 0.00 95.46 Repayments 0.00 0.00 0.00 C/Balance 0.00 0.00 95.46 Interest 0.00 0.00 5.44 Interest to be capitalised 0.00 0.00 -5.44 Interest to be charged to P&L 0.00 0.00 0.00 Note: 1. The Closing balance of State Govt. Loan appeared in Annual Accounts on 31.03.14 is Rs. 135.78 Cr.And the Closing Balance of State Govt. Loan claimed in True up 13-14 on 31.03.14 is Rs. 136.15. The difference of (136.15-135.78)= Rs 0.37 Cr is on account of state govt. loan yet to be taken in Accounts. 2. Interest on state Govt loan appeared in Annual Accounts is Rs. 16.57 Cr. However interest on state Govt loan claimed is Rs. 9.09 Cr. The difference of (16.57-9.09)=7.48 Cr is on account of Penal interest of Rs. 3.36 Cr and Interest yet to capitalised of Rs. 4.12 Cr, not considered for true up. 3. In Note 26.1 of Annual Accounts, interest expense of Rs. 15.32 Cr is capitalised against NRPP. The said capitalisation is against PFC loan. In addition to this APGCL has further reduced the Interest and finance charges by Rs. 4.12 Cr against interest on State Govt loan yet to be accounted in Annual Accounts Description Govt Of Assam Other FI Loan PFC Total Rural Electrification 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.10 0.10 0.09 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.10 0.09 Additions 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.01 -0.01 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.09 0.08 Repayments 0.00 0.00 0.01 C/Balance 0.10 0.09 LTPS Total Interest 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.01 0.01 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.01 0.01 LWHRP 1314 1415 1516 1516 7.23 6.51 15-16 100.0 8 1415 7.23 14-15 112.2 1 1314 O/Balance 13-14 124.3 4 13-14 131.5 7 14-15 119.4 4 15-16 106.5 9 Additions 0.00 Repayments 0.00 0.00 0.72 0.00 0.72 0.00 12.13 100.0 8 0.00 12.13 0.00 12.85 106.5 9 0.00 12.85 93.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 C/Balance 7.23 6.51 5.79 0.00 12.13 112.2 1 87.95 0.00 0.00 0.00 0.00 12.13 119.4 4 Total Interest 0.76 0.68 0.61 14.88 13.36 11.83 0.00 0.00 0.00 15.64 14.04 12.44 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.76 0.68 0.61 14.88 13.36 11.83 0.00 0.00 0.00 15.64 14.04 12.44 15-16 1314 1415 1516 13-14 14-15 15-16 0.00 0.00 0.00 0.00 0.00 0.00 12.10 13.60 32.43 1.50 1516 32.4 3 20.6 2 14-15 Additions 1415 13.6 0 20.1 9 13-14 O/Balance 1314 12.1 0 0.00 0.00 0.00 0.00 0.00 0.00 1.50 20.19 20.62 R&M LTPS Assam Power Generation Corporation Limited Page 127 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Repayments 0.00 13.6 0 C/Balance 1.36 32.4 3 3.38 49.6 7 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -1.36 -3.38 0.00 0.00 0.00 0.00 0.00 0.00 13.60 32.43 49.67 Total Interest 1.28 1.37 3.23 0.00 0.00 0.00 0.00 0.00 0.00 1.28 1.37 3.23 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.28 1.37 3.23 0.00 0.00 0.00 0.00 0.00 0.00 1.28 1.37 3.23 LTPS Ph-II 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.70 0.70 0.63 13.41 12.19 10.97 0.00 0.00 0.00 14.11 12.89 11.60 Additions 0.00 0.00 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -1.22 -1.22 -1.22 0.00 0.00 0.00 -1.22 -1.29 -1.29 0.56 12.19 10.97 9.75 0.00 0.00 0.00 12.89 11.60 10.31 Repayments 0.00 0.00 0.07 C/Balance 0.70 0.63 Total Interest 0.07 0.07 0.06 1.54 1.40 1.25 0.00 0.00 0.00 1.62 1.46 1.31 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07 0.07 0.06 1.54 1.40 1.25 0.00 0.00 0.00 1.62 1.46 1.31 EAP Consulting Services 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.37 0.37 0.34 0.00 0.00 0.00 0.00 0.00 0.00 0.37 0.37 0.34 Additions 0.00 0.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.04 Repayments 0.00 0.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.04 C/Balance 0.37 0.34 0.30 0.00 0.00 0.00 0.00 0.00 0.00 0.37 0.34 0.30 Total Interest 0.04 0.04 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.04 0.03 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.04 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.04 0.03 1314 11.0 0 1415 11.0 0 15.6 7 1.80 24.8 6 1516 24.8 6 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 4.46 3.19 0.00 0.00 0.00 16.73 15.46 28.05 0.00 0.00 0.00 0.00 0.00 0.00 15.67 3.80 0.00 0.00 0.00 -1.27 -3.07 -3.94 0.00 0.00 0.00 15.46 28.05 27.91 R&M NTPS O/Balance NTPS Additions 0.00 Repayments 0.00 11.0 0 C/Balance 3.80 2.67 26.0 0 5.74 0.00 -1.27 -1.27 -1.27 4.46 3.19 1.91 Total Interest 1.14 1.74 2.36 0.42 0.32 0.21 0.00 0.00 0.00 1.57 2.05 2.57 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.14 1.74 2.36 0.42 0.32 0.21 0.00 0.00 0.00 1.57 2.05 2.57 1415 56.7 8 1516 52.9 1 13-14 14-15 15-16 1314 1415 1516 O/Balance 1314 51.3 9 64.66 56.31 0.00 0.00 0.00 13-14 124.3 9 14-15 121.4 4 15-16 109.2 3 Additions 5.39 0.00 0.00 0.00 0.00 5.39 -8.34 -8.34 0.00 0.00 0.00 C/Balance 5.43 5.99 52.3 6 0.00 0.00 56.7 8 1.92 5.79 52.9 1 64.66 56.31 47.97 0.00 0.00 0.00 -8.34 121.4 4 1.92 14.14 109.2 3 5.43 14.33 100.3 3 Total Interest 5.48 5.36 4.98 5.29 4.65 4.01 0.00 0.00 0.00 10.77 10.01 8.98 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.48 5.36 4.98 5.29 4.65 4.01 0.00 0.00 0.00 10.77 10.01 8.98 Survey & investigation of HEP 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.70 0.70 0.63 0.00 0.00 0.00 0.00 0.00 0.00 0.70 0.70 0.63 Additions 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07 0.00 Repayments 0.00 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.07 -0.07 KLHEP Repayments 73.00 0.00 -8.34 KLHEP Assam Power Generation Corporation Limited Page 128 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 MSHEP C/Balance 0.70 0.63 0.56 0.00 0.00 0.00 0.00 0.00 0.00 0.70 0.63 0.56 Total Interest 0.07 0.07 0.06 0.00 0.00 0.00 0.00 0.00 0.00 0.07 0.07 0.06 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07 0.07 0.06 0.00 0.00 0.00 0.00 0.00 0.00 0.07 0.07 0.06 Myntriang SHEP 1314 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 2.00 1415 10.0 0 9.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 10.00 9.00 Additions 8.00 0.00 0.00 0.00 0.00 0.00 8.00 0.00 0.00 0.00 10.0 0 0.00 1.00 0.00 Repayments 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -1.00 -1.00 C/Balance 9.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 9.00 8.00 0.28 0.26 0.95 0.63 0.84 0.37 0.00 0.00 0.00 0.00 0.00 0.00 0.28 0.95 0.84 0.00 0.00 0.00 0.00 0.00 0.00 -0.26 -0.63 -0.37 0.02 0.32 0.47 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.32 0.47 Development of Amguri 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.50 0.50 0.45 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.50 0.45 Additions 0.00 0.00 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.05 -0.05 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.45 0.40 Total Interest Interest capitalised Interest charged to P&L A/c Amguri Repayments 0.00 0.00 0.05 C/Balance 0.50 0.45 DHEP Total Interest 0.05 0.05 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.04 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.04 Dhansiri HEP 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 1.04 1.04 0.94 0.00 0.00 0.00 0.00 0.00 0.00 1.04 1.04 0.94 Additions 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.00 Repayments 0.00 0.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.10 -0.10 CTPS C/Balance 1.04 0.94 0.83 0.00 0.00 0.00 0.00 0.00 0.00 1.04 0.94 0.83 Total Interest 0.11 0.10 0.09 0.00 0.00 0.00 0.00 0.00 0.00 0.11 0.10 0.09 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.11 0.10 0.09 0.00 0.00 0.00 0.00 0.00 0.00 0.11 0.10 0.09 CTPS 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.50 0.50 0.45 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.50 0.45 Additions 0.00 0.00 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.05 Repayments 0.00 0.00 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.05 C/Balance 0.50 0.45 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.45 0.40 Total Interest 0.05 0.05 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.04 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.04 1415 10.1 3 1516 10.1 3 13-14 1516 0.00 0.00 0.00 13-14 100.1 3 14-15 150.1 3 Additions 0.00 0.00 50.00 0.00 0.00 0.00 0.00 50.00 0.00 15-16 150.1 3 160.0 0 Repayments 0.00 10.1 3 0.00 10.1 3 0.00 1.01 15-16 140.0 0 160.0 0 1415 90.00 14-15 140.0 0 1314 O/Balance 1314 10.1 3 0.00 140.0 0 0.00 140.0 0 0.00 300.0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 150.1 3 0.00 150.1 3 -1.01 309.1 1 NRPP Ph- I NRPP C/Balance 9.11 Assam Power Generation Corporation Limited Page 129 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Total Interest 1.69 1.69 1.06 1.06 0.96 0.32 15.32 15.32 18.65 18.65 29.31 0.00 0.00 0.00 -9.77 0.00 0.00 0.00 0.00 0.64 0.00 0.00 19.54 0.00 1415 12.7 5 1516 19.7 5 13-14 14-15 15-16 1314 O/Balance 1314 12.7 5 0.00 0.00 0.00 0.00 Additions 0.00 7.00 7.00 0.00 0.00 0.00 0.00 Repayments 0.00 12.7 5 0.00 19.7 5 0.00 26.7 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.33 1.33 1.37 1.37 2.14 2.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Lakwa RPP 1314 1415 1516 O/Balance 0.00 0.98 1.58 13-14 0.00 14-15 0.00 15-16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13-14 14-15 15-16 Interest capitalised Interest charged to P&L A/c Lower Kopili C/Balance Total Interest Interest capitalised Interest charged to P&L A/c Additions 0.98 0.60 0.00 Repayments 0.00 0.00 0.00 C/Balance 0.98 Other projects not yet commssioned Total Interest Interest capitalised Interest charged to P&L A/c 0.07 0.07 1.58 0.11 0.11 1.58 0.17 0.17 0.00 17.01 17.01 19.71 19.71 30.26 10.09 0.00 0.00 0.00 0.00 20.18 1415 1516 13-14 14-15 15-16 0.00 0.00 12.75 12.75 19.75 0.00 0.00 0.00 7.00 7.00 0.00 0.00 0.00 0.00 0.00 0.00 12.75 19.75 26.75 0.00 0.00 1.33 1.37 2.14 0.00 0.00 -1.33 -1.37 -2.14 0.00 0.00 0.00 0.00 0.00 0.00 1314 1415 1516 13-14 14-15 15-16 0.00 0.00 0.00 0.98 1.58 0.00 0.00 0.00 78.6 0 0.98 0.60 78.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 78.6 0 0.98 1.58 80.18 0.00 0.00 0.07 0.11 4.65 0.00 0.00 4.48 4.48 -0.07 -0.11 -4.65 0.00 0.00 0.00 0.00 0.00 0.00 1314 1415 1516 13-14 14-15 15-16 0.00 0.00 0.00 Lungnit SHEP 1314 1415 1516 O/Balance 3.00 3.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 3.00 3.00 Additions 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Repayments 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 C/Balance 3.00 3.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 3.00 3.00 Total Interest 0.31 0.31 0.32 0.32 0.32 0.32 0.00 0.00 0.00 0.00 0.00 0.00 0.31 0.32 0.32 0.00 0.00 0.00 0.00 0.00 0.00 -0.31 -0.32 -0.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Development of SHEP 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 1.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 1.00 Additions 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Repayments 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Interest capitalised Interest charged to P&L A/c C/Balance 1.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 1.00 Total Interest 0.11 0.11 0.11 0.11 0.11 0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.11 0.11 0.11 0.00 0.00 0.00 0.00 0.00 0.00 -0.11 -0.11 -0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Non Conventional Sources of Energy 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.40 0.40 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.40 0.40 0.40 Additions 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Repayments 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Interest capitalised Interest charged to P&L A/c C/Balance 0.40 0.40 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.40 0.40 0.40 Total Interest 0.04 0.04 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.04 0.04 Assam Power Generation Corporation Limited Page 130 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Interest capitalised Interest charged to P&L A/c 0.04 0.04 0.04 0.00 0.00 0.00 0.00 0.00 0.00 -0.04 -0.04 -0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 KLHEP (Upper) 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.40 1.30 1.30 0.00 0.00 0.00 0.00 0.00 0.00 0.40 1.30 1.30 Additions 0.90 0.00 0.25 0.00 0.00 0.00 0.00 0.00 0.00 0.90 0.00 0.25 Repayments 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 C/Balance 1.30 1.30 1.55 0.00 0.00 0.00 0.00 0.00 0.00 1.30 1.30 1.55 Total Interest 0.06 0.06 0.14 0.14 0.14 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.06 0.14 0.14 0.00 0.00 0.00 0.00 0.00 0.00 -0.06 -0.14 -0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 KLHEP (Intermediate) 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.40 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.40 1.00 1.00 Additions 0.60 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.60 0.00 0.50 Repayments 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Interest capitalised Interest charged to P&L A/c C/Balance 1.00 1.00 1.50 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 1.50 Total Interest 0.05 0.05 0.11 0.11 0.11 0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.11 0.11 0.00 0.00 0.00 0.00 0.00 0.00 -0.05 -0.11 -0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Setting up of a 200 MW (CCGT) 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.15 0.15 0.15 0.00 0.00 0.00 0.00 0.00 0.00 0.15 0.15 0.15 Additions 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Interest capitalised Interest charged to P&L A/c Repayments 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 C/Balance 0.15 0.15 0.15 0.00 0.00 0.00 0.00 0.00 0.00 0.15 0.15 0.15 Total Interest 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.02 0.02 0.00 0.00 0.00 0.00 0.00 0.00 -0.02 -0.02 -0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Margherita/Borgolai 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 1.35 2.25 4.25 0.00 0.00 0.00 0.00 0.00 0.00 1.35 2.25 4.25 Additions 0.90 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.90 2.00 0.00 Repayments 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 C/Balance 2.25 4.25 4.25 0.00 0.00 0.00 0.00 0.00 0.00 2.25 4.25 4.25 Total Interest 0.16 0.16 0.24 0.24 0.45 0.45 0.00 0.00 0.00 0.00 0.00 0.00 0.16 0.24 0.45 0.00 0.00 0.00 0.00 0.00 0.00 -0.16 -0.24 -0.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Golaghat 1314 1415 1516 13-14 14-15 15-16 1314 1415 1516 13-14 14-15 15-16 O/Balance 0.37 0.37 0.37 0.00 0.00 0.00 0.00 0.00 0.00 0.37 0.37 0.37 Additions 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Interest capitalised Interest charged to P&L A/c Interest capitalised Interest charged to P&L A/c Repayments 0.00 0.00 0.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.04 C/Balance 0.37 0.37 0.33 0.00 0.00 0.00 0.00 0.00 0.00 0.37 0.37 0.33 Total Interest 0.04 0.04 0.04 0.04 0.03 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.04 0.03 0.00 0.00 0.00 0.00 0.00 0.00 -0.04 -0.04 -0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Interest capitalised Interest charged to P&L A/c Assam Power Generation Corporation Limited Page 131 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Amring 1314 1415 1516 O/Balance 0.00 0.00 Additions 0.00 0.00 Repayments 0.00 0.00 1314 1415 1516 13-14 14-15 15-16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13-14 14-15 15-16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 C/Balance 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total Interest 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Solar PP at NTPS 1314 1415 1516 1314 1415 1516 O/Balance 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Additions 0.00 0.00 0.00 17.0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.00 Repayments 0.00 0.00 0.00 17.0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1314 1415 1516 0.00 0.00 0.00 1314 1415 1516 C/Balance 0.00 0.00 Total Interest 0.00 0.00 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.15 0.15 0.00 0.00 0.00 Solar PP at LTPS 1314 1415 1516 O/Balance 0.00 0.00 0.00 Additions 0.00 0.00 0.00 17.0 0 0.00 0.00 0.00 0.00 0.00 0.00 Repayments 0.00 0.00 0.00 17.0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1314 1415 1516 1314 1415 0.00 1516 0.00 1314 1314 0.00 1415 1415 1516 1516 0.00 0.00 0.00 0.00 17.00 0.00 0.00 0.00 0.00 0.00 17.00 0.00 0.00 0.15 0.00 0.00 -0.15 0.00 0.00 0.00 C/Balance 0.00 0.00 Total Interest 0.00 0.00 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.15 0.15 0.00 0.00 0.00 KLHEP Barrage Toe Project 1314 1415 1516 O/Balance 0.00 0.30 0.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.30 0.30 Additions 0.30 0.00 0.25 0.00 0.00 0.00 0.00 0.00 0.00 0.30 0.00 0.25 Repayments 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1314 1415 1516 1314 1415 1516 C/Balance 0.30 0.30 0.55 0.00 0.00 0.00 0.00 0.00 0.00 0.30 0.30 0.55 Total Interest 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.03 0.00 0.03 0.03 0.00 Interest capitalised Interest charged to P&L A/c 0.03 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.03 -0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Cachar distributed Generation system by Gas IC Engine 1314 1415 1516 1314 1415 1516 O/Balance 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Additions 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.8 6 Repayments 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 C/Balance 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.8 6 Total Interest 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Interest capitalised Interest charged to P&L A/c 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1314 1415 1516 1314 1415 1516 0.00 0.00 0.00 0.00 16.86 0.00 0.00 0.00 0.00 0.00 16.86 0.00 0.00 0.96 0.00 0.96 0.96 0.00 0.00 -0.96 0.00 0.00 0.00 0.00 0.00 Assam Power Generation Corporation Limited Page 132 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-14 Statement of Calculation of Average Rate of Interest (CC) on Working Capital Loans Name of the Company Assam Power Generation Corporation Limited Name of the Power Station Year ending March (1) (2) 2013-14 2014-15 2015-16 (3) (4) (5) INTEREST ON WORKING CAPITAL Fuel Cost - 1 month Fuel stock - 1 or 1/2 month Oil stock - 2 months O & M expenses - 1 month Spares 1 year = 40% of O & MLess 1/5th of initial capitalised spares for first 5 years Receivables - 2 months Total Working Capital (Rs. cr) Working Capital Loan allowed Weighted Average Interest Rate See Details below INTEREST ON WORKING CAPITAL (Rs cr) SL. NO. (1) a b c d e AMOUNT Source of Loan for Working Capital (Rs. in Crs) (2) (3) RATE OF INTEREST (Cash Credit) (%) (4) TOTAL Weighted Average Rate of Interest PETITIONER Period Interest on Working Capital as per AERC 2013-14 2014-15 2015-16 22.32 26.03 30.83 Assam Power Generation Corporation Limited Page 133 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-15 Calculation of Operation and Maintenance Expenses Assam Power Generation Corporation Limited Name of the Company Name of the Power Station (1) 2013-14 2014-15 2015-16 (2) (3) (4) O&M data projection for 2013-14 to 2015-16 A) Total O & M Expenses 120.56 121.14 168.67 120.56 121.14 168.67 1 B) Abnormal O&M expenses - On account of water charges - On account of other factors C) Calculation of Base O&M (A-B) Notes: 1 Abnormal O&M expenses such as on account of sharp increase in water charges etc. which are abnormal in nature and for which the utility shall file a separate petition. PETITIONER Assam Power Generation Corporation Limited Page 134 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-16 Details of Operation and Maintenance Expenses Name of the Company Assam Power Generation Corporation Limited Name of the Power Station (1) (A) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (2) Breakup of O& M expenses Employee cost & terminal benefit provisions Repair and Maintenance Stores consumed Power Charges Water Charges Communication expenses Travelling expenses Insurance - Plant & Machinery - Other Rent Security expenses Professional expenses Printing and Stationery Corporate office expenses allocation Other Expenses like employees past period liabilities Total (1 to 4) 2013-14 2014-15 2015-16 (3) (4) (5) See Details below LESS: RECOVERED (IF ANY) Net Expenses Notes: 1. The process of allocation of corporate expenses to generating stations should be specified. 2. An annual increase in O&M expenses under a given head ( in excess of 20 percent should be explained) 3. The data should be certified by statutory auditors. (B) Corporate office expenses (aggregate) - Direct employee expense - Repair and maintaenance - Training and Recruitment - Commmunication - Travelling - Security - Rent - Others PETITIONER Assam Power Generation Corporation Limited Page 135 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 APGCL Consolidated Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 2013-14 33.81 1.44 27.12 6.93 0.03 0.18 0.05 0.27 0.00 0.01 0.13 12.04 2014-15 36.65 1.66 29.85 5.61 0.03 0.09 0.05 0.29 0.00 0.01 0.14 12.16 2015-16 48.21 2.07 39.33 7.38 0.04 0.13 0.07 0.36 0.00 0.00 0.19 14.41 82.00 0.00 82.00 86.54 0.00 86.54 112.19 6.92 105.27 2013-14 0.35 0.81 0.12 0.01 0.02 0.02 0.60 0.02 0.07 0.76 0.04 9.72 0.00 12.53 0.00 12.53 2014-15 0.35 0.88 0.05 0.00 0.01 0.00 0.65 0.01 0.01 0.63 0.02 6.79 0.00 9.41 0.00 9.41 2015-16 0.39 0.94 0.06 0.00 0.01 0.00 0.71 0.00 0.00 0.78 0.02 7.64 0.00 10.56 0.70 9.85 2013-14 2014-15 2015-16 0.00 6.44 32.00 20.60 1.81 0.87 0.89 14.74 0.27 0.31 1.10 16.95 0.31 0.35 1.26 Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses Energy bill raised by APDCL Sub Total: Less: Capitalised Total: Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic Assam Power Generation Corporation Limited Page 136 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: Note: 1. 2. 0.03 0.06 0.26 0.08 1.23 0.20 26.03 0.09 0.26 0.14 0.20 1.41 0.23 25.19 Besides the cost of special type Repair & Maintenance, the approved O&M cost of 2014-15 is Rs. 17.11 Cr and adding Turbine and lubricant cost of Rs. 1.64 Cr, the O&M cost of 2014-15 appears to be Rs. 18.75 Cr. Taking an escalation rate of 15% (reasons mentioned at note 2 below) on this, O&M cost of 2015-16 has been projected at Rs. 21.55 Cr excluding the Special Type Repair & Maintenance cost of RS. 32 Cr. Total O&M cost for the FY 2015-16 including the Special Type Repair & Maintenance Cost is Rs. 53.55 Cr. as state above. Basis for taking 15% escalation rate is that as the machines become older, maintenance becomes costlier. Further, due to the increase in dollar value, APGCL is required to spend more in purchasing imported spares for its machines. In addition to these factors, the actual inflation (price rise) is much more than the escalation factor allowed by the commission. Considering all these factors, APGCL has taken 15% escalation to calculate the R&M cost for the year 2014-15. NTPS Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 2013-14 13.59 0.41 11.07 2.64 0.01 0.10 0.04 0.09 0.00 0.00 0.06 2.01 30.03 0.00 30.03 2014-15 14.74 0.54 12.19 2.08 0.01 0.05 0.04 0.10 0.00 0.00 0.09 2.46 32.30 0.00 32.30 2015-16 15.98 0.59 13.21 2.25 0.01 0.06 0.05 0.11 0.00 0.00 0.09 2.67 35.02 0.00 35.02 2013-14 0.18 0.00 0.05 0.01 0.01 0.01 0.03 0.01 0.00 0.24 0.01 3.22 3.75 2014-15 0.12 0.00 0.02 0.00 0.01 0.00 0.03 0.00 0.00 0.22 0.00 2.24 2.65 2015-16 0.07 0.00 0.01 0.00 0.01 0.00 0.02 0.00 0.00 0.13 0.00 1.30 1.54 Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses Sub Total: Assam Power Generation Corporation Limited Page 137 of 228 0.11 0.30 0.16 0.23 1.62 0.26 53.55 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Less: Capitalised Total: 0.00 3.75 0.00 2.65 0.00 1.54 2013-14 2014-15 2015-16 0.00 0.00 14.00 4.42 0.78 0.00 0.00 0.00 0.00 0.00 0.02 0.00 0.01 5.23 1.45 0.17 0.08 0.52 0.00 0.00 0.00 0.07 0.00 0.01 2.30 1.67 0.20 0.09 0.60 0.00 0.00 0.00 0.08 0.00 0.01 16.65 Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: NRPP Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 7.30 0.27 6.04 1.03 0.01 0.03 0.02 0.05 0.00 0.00 0.04 1.22 0.00 0.00 0.00 0.00 0.00 0.00 16.01 5.34 10.67 201415 201516 Administration and General Expenses Particulars 201314 Assam Power Generation Corporation Limited Page 138 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.06 0.00 0.01 0.00 0.01 0.00 0.02 0.00 0.00 0.11 0.00 0.00 0.00 1.13 Sub Total: Less: Capitalised Total: 0.00 0.00 0.00 0.00 0.00 0.00 1.33 0.44 0.89 201314 201415 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: LTPS Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost 201314 10.23 0.79 8.39 1.92 0.01 0.03 0.00 0.07 0.00 0.00 201415 11.09 0.85 9.23 1.55 0.01 0.03 0.00 0.08 0.00 0.00 Assam Power Generation Corporation Limited 201516 12.03 0.92 10.01 1.68 0.01 0.03 0.00 0.08 0.00 0.00 Page 139 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 0.05 5.36 0.04 5.30 0.04 5.75 26.85 0.00 26.85 28.19 0.00 28.19 30.55 0.00 30.55 201314 0.13 0.58 0.04 0.00 0.00 0.01 0.44 0.01 0.02 0.15 0.01 1.93 201415 0.12 0.63 0.02 0.00 0.00 0.00 0.48 0.00 0.00 0.12 0.00 2.08 201516 0.13 0.68 0.02 0.00 0.00 0.00 0.52 0.00 0.00 0.13 0.00 2.26 3.32 0.00 3.32 3.46 0.00 3.46 3.74 0.00 3.74 201314 201415 201516 0.00 6.44 18.00 4.77 0.58 0.13 0.00 0.00 0.01 0.18 0.04 1.23 0.00 6.95 7.03 0.03 0.06 0.29 0.04 0.13 0.01 0.01 1.41 0.00 15.45 8.08 0.03 0.07 0.33 0.05 0.15 0.01 0.01 1.62 0.00 28.35 Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses Sub Total: Less: Capitalised Total: Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: CTPS Employee Expenses Assam Power Generation Corporation Limited Page 140 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 201314 1.64 0.00 1.19 0.18 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 201415 1.78 0.00 1.31 0.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 1.93 0.00 1.42 0.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.02 0.00 3.02 3.18 0.00 3.18 3.45 0.00 3.45 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.05 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.06 0.00 0.06 0.02 0.00 0.02 0.01 0.00 0.01 201314 201415 201516 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses Sub Total: Less: Capitalised Total: Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic Assam Power Generation Corporation Limited Page 141 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits 201314 4.89 0.00 3.64 1.50 0.01 0.02 0.00 0.09 0.00 0.00 0.01 3.01 201415 5.30 0.00 4.00 1.33 0.01 0.00 0.00 0.10 0.00 0.00 0.01 2.70 2015-16 5.75 0.00 4.34 1.44 0.01 0.00 0.00 0.11 0.00 0.00 0.01 2.93 Subtotal Less: Capitalisation Total 13.17 0.00 13.17 13.46 0.00 13.46 14.59 0.00 14.59 201314 0.01 0.05 0.02 0.00 0.01 0.01 0.00 0.00 0.04 0.29 0.01 3.86 201415 0.12 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.22 0.01 2.34 2015-16 0.13 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.24 0.02 2.53 4.28 0.00 4.28 2.75 0.00 2.75 2.97 0.00 2.97 KLHEP Employee Expenses Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses Sub Total: Less: Capitalised Total: Assam Power Generation Corporation Limited Page 142 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: 201314 201415 2015-16 0.00 0.00 0.00 9.93 0.27 0.64 0.89 0.03 0.04 0.02 0.01 0.00 0.19 12.03 5.90 0.03 0.06 0.29 0.04 0.13 0.01 0.01 0.00 0.22 6.69 6.79 0.03 0.07 0.33 0.05 0.15 0.01 0.01 0.00 0.25 7.69 LWHRP Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 201314 3.17 0.24 2.60 0.60 0.00 0.02 0.00 0.01 0.00 0.00 0.01 1.66 201415 3.44 0.26 2.86 0.48 0.00 0.01 0.00 0.01 0.00 0.00 0.01 1.70 201516 3.73 0.29 3.10 0.52 0.00 0.01 0.00 0.01 0.00 0.00 0.01 1.84 8.32 0.00 8.32 8.78 0.00 8.78 9.51 0.00 9.51 201314 0.04 0.18 0.01 0.00 0.00 0.00 0.14 201415 0.00 0.20 0.01 0.00 0.00 0.00 0.15 201516 0.00 0.21 0.01 0.00 0.00 0.00 0.16 Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Assam Power Generation Corporation Limited Page 143 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses 0.00 0.01 0.05 0.00 0.60 0.00 0.00 0.04 0.00 0.05 0.00 0.00 0.04 0.00 0.05 Sub Total: Less: Capitalised Total: 1.03 0.00 1.03 0.44 0.00 0.44 0.47 0.00 0.47 201314 201415 201516 0.00 0.00 0.00 1.48 0.18 0.04 0.00 0.00 0.00 0.06 0.01 0.00 0.00 1.77 0.36 0.04 0.08 0.00 0.01 0.00 0.12 0.11 0.00 0.00 0.72 0.41 0.05 0.09 0.00 0.01 0.00 0.14 0.13 0.00 0.00 0.83 Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: Myntriang Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 2013-14 0.28 0.00 0.23 0.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2014-15 0.30 0.00 0.25 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2015-16 1.49 0.00 1.22 0.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.60 0.00 0.60 0.63 0.00 0.63 3.06 1.59 1.47 Assam Power Generation Corporation Limited Page 144 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses Sub Total: Less: Capitalised Total: 2013-14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.06 2014-15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.00 0.07 2015-16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.14 0.00 0.36 0.10 0.00 0.10 0.09 0.00 0.09 0.50 0.26 0.24 2013-14 2014-15 2015-16 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: Assam Power Generation Corporation Limited Page 145 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-17 Details/Information to be Submitted in respect of Fuel for Computation of Energy Name of the Company APGCL Name of the Power Station Namrup Thermal Power Station GAS Months For preceding 3rd Month APM NonAPM 20113.75 1613.22 For preceding 2nd Month APM NonAPM 19497.22 1550.14 For preceding 1st Month (October'14) APM NonAPM 20115.33 1028.59 Quantity of Gas (1000 SCM) Amount charged by the Gas Co. (Rs.) Transportation Charge (Rs.) 8817.00 8607.00 8607.00 8615.00 Weighted average GCV Gas kCal/CUM 8817.00 8615.00 Unit price of 5295.49 5241.66 5243.09 8738.48 Base price for CV (Rs/1000SCM) 8825.82 8736.11 Gas charged Marketing Margin (Rs/1000SCM) 176.34 176.34 172.14 172.14 172.30 172.30 by the Gas Co. Cess or duty (Rs/1000SCM) Sales Tax (VAT) (Rs/1000SCM) 656.62 1080.26 649.66 1068.99 649.85 1069.29 12% Transportation (Rs/1000SCM) Total (Rs/1000SCM) 6128.45 10082.42 6063.46 9977.23 6065.24 9980.07 Transportation Distance (Km) by Rate (Rs/1000SCM) 469.92 470.16 482.41 rail/ship/road Amount 10209841.00 9895564.00 10199940.00 (Pipe Line) Note: 1. Furnish copies of relevant coal/lignite price notifications or the fuel supply agreement, tariff rates of Railways or other transport authorities as applicable. 2. Similar details to be furnished for natural gas/liquid fuel for CCGT station and secondary fuel oil for coal/lignite based thermal. PETITIONER Assam Power Generation Corporation Limited Page 146 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 FORM-17 Details/Information to be Submitted in respect of Fuel for Computation of Energy Name of the Company APGCL Name of the Power Station Lakwa Thermal Power Station GAS Months For preceding 3rd Month Name of the Gas Supplier Quantity of Gas Amount charged by the Gas Co. Transportation Charge Weighted average GCV Gas Base price for CV Any other charge Unit price of Marketing Gas charged Margin by the Gas Royalty Co. Sales Tax (VAT) 12% Transportation Total Distance Transportation by Pipe Line Rate Amount GAIL OIL For preceding 2nd Month CANORO GAIL OIL For preceding 1st Month (Oct'14) CANORO GAIL OIL CANORO 13197.5 8880.3 908.9 11160.5 9726.6 865.7 14725.4 9913.7 907.1 kCal/CUM 9179 8817 9623 9305 8607 9603 9870 8615 9609 (Rs/1000SCM) 5513 8826 5056 5667 8736 5106 6007 8738 5109 183.6 176.3 192.5 186.1 172.1 192.1 197.4 172.3 192.2 (1000 SCM) (Rs.) (Rs.) (Rs/1000SCM) (Rs/1000SCM) (Rs/1000SCM) (Rs/1000SCM) 505.6 683.6 (Rs/1000SCM) 20.1 (Rs/1000SCM) 6400.1 510.6 1080.3 690.5 702.3 10082.4 6445 6575.2 510.9 1069.0 697.0 744.5 9977.2 6505.1 6968.8 20.1 1069.3 697.4 9980.1 6508.9 20.1 (Km) (Rs/1000SCM) 736.7 736.7 736.7 7211769.0 7803358.0 7971835.0 Note: 1. Furnish copies of relevant coal/lignite price notifications or the fuel supply agreement, tariff rates of Railways or other transport authorities as applicable. 2. Similar details to be furnished for natural gas/liquid fuel for CCGT station and secondary fuel oil for coal/lignite based thermal. PETITIONER Assam Power Generation Corporation Limited Page 147 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Annex-IV 12. STATIONWISE INFORMATION FOR CLAIMING ARR AND TARIFF FOR ASSAM POWER GENERATION CORPORATION LIMITED FOR FY 2015-16 Assam Power Generation Corporation Limited Page 148 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Table of Contents 1. Namrup Thermal Power Station 1.1 2. 152 FY 12-13 to 15-16 data ………………………... 155 FY 12-13 to 15-16 data ………………………... 158 FY 12-13 to 15-16 data ………………………... 161 ………………………... 163 ………………………... 166 Myntriang Small Hydro Electric Project 6.1 7.. ………………………... Namrup Replacement Power Project 5.1 6. FY 12-13 to 15-16 data Lakwa Waste Heat Recovery Power Project 4.1 5. 150 Karbi Langpi Hydro Electric Project 3.1. 4. ………………………... Lakwa Thermal Power Station 2.1. 3. FY 12-13 to 15-16 data FY 12-13 to 15-16 data Chandrapur Thermal Power Station 7.1 FY 12-13 to 15-16 data Assam Power Generation Corporation Limited Page 149 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 NTPS Employee Expenses 201213 12.82 0.12 8.64 2.47 0.01 0.09 0.02 0.00 0.00 0.01 0.04 4.64 201314 13.59 0.41 11.07 2.64 0.01 0.10 0.04 0.09 0.00 0.00 0.06 2.01 201415 14.74 0.54 12.19 2.08 0.01 0.05 0.04 0.10 0.00 0.00 0.09 2.46 201516 15.98 0.59 13.21 2.25 0.01 0.06 0.05 0.11 0.00 0.00 0.09 2.67 28.85 0.00 28.85 30.03 0.00 30.03 32.30 0.00 32.30 35.02 0.00 35.02 201213 0.11 0.24 0.05 0.00 0.16 0.01 0.00 0.00 0.02 0.24 0.02 201314 0.18 0.00 0.05 0.01 0.01 0.01 0.01 0.01 0.00 0.37 0.01 201415 0.12 0.00 0.02 0.00 0.01 0.00 0.03 0.00 0.00 0.22 0.00 201516 0.07 0.00 0.01 0.00 0.01 0.00 0.02 0.00 0.00 0.13 0.00 Administrative & purchase related expenses 1.47 3.22 2.24 1.30 Sub Total: Less: Capitalised Total: 2.31 0.00 2.31 3.87 0.00 3.87 2.65 0.00 2.65 1.54 0.00 1.54 201213 0.00 2.40 201314 0.00 2.95 201415 0.00 2.95 201516 0.00 2.95 Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Other Income Particulars Interest on Staff Loans and advance Income from Investment Assam Power Generation Corporation Limited Page 150 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: 0.01 0.22 0.10 0.00 2.72 0.01 0.26 0.46 0.00 3.68 0.01 0.26 0.46 0.00 3.68 0.01 0.26 0.46 0.00 3.68 201314 201415 201516 0.00 0.00 14.00 6.47 0.83 0.04 0.00 0.00 0.01 0.00 0.02 0.00 0.00 7.37 4.42 0.78 0.00 0.00 0.00 0.00 0.00 0.02 0.00 0.01 5.23 1.45 0.17 0.08 0.52 0.00 0.00 0.00 0.07 0.00 0.01 2.30 1.67 0.20 0.09 0.60 0.00 0.00 0.00 0.08 0.00 0.01 16.65 201213 0.00 0.00 0.01 0.08 1.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.37 201314 0.00 0.17 0.11 0.07 1.45 0.00 0.02 0.12 0.03 0.04 0.00 0.41 2.43 201415 0.00 0.17 0.17 0.12 2.70 0.00 0.01 0.06 -2.57 0.04 0.00 2.25 2.96 201516 0.00 0.17 0.23 0.16 3.55 0.00 0.04 0.12 0.00 0.04 0.00 1.66 5.97 1.37 -0.43 2.00 -0.43 2.53 -0.43 5.54 201213 1.83 201314 1.57 201415 2.05 201516 2.57 Repairs & Maintenance 201213 Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Hydraulic Other civil works Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: Depreciation Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & ficture Office equipment Roads on land belonging to others Capital spares at generating stations Total: Depreciation on 90% of the Assets funded by Grants/subsidies Net Total Interest & financing charges Particulars Interest on loans Assam Power Generation Corporation Limited Page 151 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Other finance charges Sub total Less: Interest capitalised Total 1.97 3.80 0.00 3.80 0.02 1.58 0.00 1.58 0.02 2.07 0.00 2.07 2.14 4.72 0.00 4.72 201213 6.52 201314 7.44 201415 9.19 201516 7.42 201213 201314 201415 201516 533.17 503.14 0.06 526.57 494.98 0.06 591.66 557.60 0.06 342.98 324.16 0.05 167.53 191.59 224.95 166.99 Interest on working Capital Particulars IWC Profit & Loss Account Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges EXPENDITURE Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement 140.23 7.37 28.85 2.31 1.37 3.80 0.00 6.52 146.57 5.23 30.03 3.87 2.00 1.58 0.00 7.44 194.13 2.30 32.30 2.65 2.53 2.07 0.00 9.19 127.25 16.65 35.02 1.54 5.54 4.72 0.00 7.42 -10.32 180.13 8.86 2.72 0.35 197.69 0.00 0.00 -3.36 193.36 9.06 3.68 0.15 198.88 0.00 0.00 0.00 245.16 9.39 3.68 0.31 251.18 0.00 0.00 0.00 198.14 10.16 3.68 0.31 204.92 Surplus(+) / Shortfall(-) -30.16 -7.29 -26.23 -37.93 201213 9.92 0.39 6.60 1.74 201314 10.23 0.79 8.39 1.92 201415 11.09 0.85 9.23 1.55 201516 12.03 0.92 10.01 1.68 LTPS Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Assam Power Generation Corporation Limited Page 152 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits 0.01 0.05 0.01 0.00 0.00 0.01 0.12 3.61 0.01 0.03 0.00 0.07 0.00 0.00 0.05 5.36 0.01 0.03 0.00 0.08 0.00 0.00 0.04 5.30 0.01 0.03 0.00 0.08 0.00 0.00 0.04 5.75 22.46 0.00 22.46 26.85 0.00 26.85 28.19 0.00 28.19 30.55 0.00 30.55 201213 0.08 0.11 0.03 0.00 0.07 0.00 0.03 0.01 0.01 0.10 0.03 201314 0.13 0.58 0.04 0.00 0.00 0.01 0.14 0.01 0.02 0.23 0.01 201415 0.12 0.63 0.02 0.00 0.00 0.00 0.48 0.00 0.00 0.12 0.00 201516 0.13 0.68 0.02 0.00 0.00 0.00 0.52 0.00 0.00 0.13 0.00 Administrative & purchase related expenses 0.54 1.93 2.08 2.26 Sub Total: Less: Capitalised Total: 1.00 0.00 1.00 3.10 0.00 3.10 3.46 0.00 3.46 3.74 0.00 3.74 201213 0.00 0.59 0.01 0.21 0.00 0.01 0.82 201314 0.00 2.95 0.03 0.26 0.43 0.01 3.69 201415 0.00 2.95 0.03 0.26 0.43 0.01 3.69 201516 0.00 2.95 0.03 0.26 0.43 0.01 3.69 201213 201314 201415 201516 Subtotal Less: Capitalisation Total Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Other Income Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:- Assam Power Generation Corporation Limited Page 153 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Hydraulic Other civil works Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: 0.00 6.44 18.00 2.18 0.44 0.18 0.18 0.00 0.01 0.16 0.01 0.00 0.00 3.15 4.77 0.58 0.13 0.00 0.00 0.01 0.18 0.04 1.23 0.00 6.95 7.03 0.03 0.06 0.29 0.04 0.13 0.01 0.01 1.41 0.00 15.45 8.08 0.03 0.07 0.33 0.05 0.15 0.01 0.01 1.62 0.00 28.35 201213 0.00 0.00 0.02 0.03 1.36 0.00 0.00 0.13 0.03 0.02 0.00 0.54 2.13 201314 0.00 0.08 0.01 0.05 1.98 0.00 0.00 0.00 0.02 0.01 0.00 3.31 5.46 201415 0.00 0.08 0.01 0.06 6.30 0.00 0.02 0.07 0.00 0.01 0.00 5.17 11.74 201516 0.00 0.08 0.01 0.14 7.00 0.00 0.00 0.00 0.00 0.02 0.00 1.61 8.86 2.13 -0.13 5.33 -0.13 11.61 -0.13 8.73 201213 3.52 2.12 5.64 0.00 5.64 201314 3.11 0.02 3.12 0.00 3.12 201415 3.02 0.02 3.04 0.00 3.04 201516 4.71 2.14 6.85 0.00 6.85 201213 5.12 201314 10.98 201415 13.23 201516 15.23 Depreciation Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & ficture Office equipment Roads on land belonging to others Capital spares at generating stations Total: Depreciation on 90% of the Assets funded by Grants/subsidies Net Total Interest & financing charges Particulars Interest on loans Other finance charges Sub total Less: Interest capitalised Total Interest on working Capital Particulars IWC Assam Power Generation Corporation Limited Page 154 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Profit & Loss Account Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges 201213 201314 201415 201516 696.72 611.18 0.12 703.59 642.97 0.09 720.27 660.18 0.08 689.87 641.58 0.07 182.78 264.46 307.03 294.99 EXPENDITURE Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement 225.16 3.15 22.46 1.00 2.13 5.64 0.00 5.12 238.58 6.95 26.85 3.10 5.33 3.12 0.00 10.98 283.33 15.45 28.19 3.46 11.61 3.04 0.00 13.23 319.26 28.35 30.55 3.74 8.73 6.85 0.00 15.23 -10.32 254.34 9.66 0.82 0.01 271.78 0.00 0.00 -3.36 291.57 10.07 3.69 0.15 298.11 0.00 0.00 0.00 358.31 10.67 3.69 0.31 365.60 Surplus(+) / Shortfall(-) -89.00 -33.64 -58.57 0.00 0.00 0.00 412.71 11.50 3.69 0.31 420.83 125.84 201213 4.74 0.00 2.93 1.18 0.00 0.02 0.01 0.18 0.00 0.00 0.02 1.74 201314 4.89 0.00 3.64 1.50 0.01 0.02 0.00 0.09 0.00 0.00 0.01 3.01 201415 5.30 0.00 4.00 1.33 0.01 0.00 0.00 0.10 0.00 0.00 0.01 2.70 201516 5.75 0.00 4.34 1.44 0.01 0.00 0.00 0.11 0.00 0.00 0.01 2.93 10.83 0.00 10.83 13.17 0.00 13.17 13.46 0.00 13.46 14.59 0.00 14.59 KLHEP Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total Assam Power Generation Corporation Limited Page 155 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Administration and General Expenses 201213 0.02 0.87 0.04 0.00 0.18 0.01 0.00 0.00 0.02 0.30 0.00 201314 0.01 0.05 0.02 0.00 0.01 0.01 0.00 0.00 0.04 0.46 0.01 201415 0.12 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.22 0.01 201516 0.13 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.24 0.02 Administrative & purchase related expenses 1.16 3.86 2.34 2.53 Sub Total: Less: Capitalised Total: 2.61 0.00 2.61 4.44 0.00 4.44 2.75 0.00 2.75 2.97 0.00 2.97 201213 0.00 2.40 0.01 0.20 0.05 0.00 2.65 201314 0.00 2.95 0.01 0.26 0.01 0.00 3.23 201415 0.00 2.95 0.01 0.26 0.01 0.00 3.23 201516 0.00 2.95 0.01 0.26 0.01 0.00 3.23 201213 201314 201415 201516 0.00 0.00 0.00 9.93 0.27 0.64 0.89 0.03 0.04 0.02 0.01 0.00 0.19 5.90 0.03 0.06 0.29 0.04 0.13 0.01 0.01 0.00 0.22 6.79 0.03 0.07 0.33 0.05 0.15 0.01 0.01 0.00 0.25 Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Other Income Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Hydraulic Other civil works Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil 6.79 0.17 0.64 0.32 0.00 0.07 0.01 0.02 0.00 0.00 Assam Power Generation Corporation Limited Page 156 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Total: 8.02 12.03 6.69 7.69 201213 0.00 0.74 4.96 2.27 0.00 4.50 0.84 0.00 0.01 0.01 0.00 0.01 13.33 201314 0.00 0.47 3.11 2.02 0.00 4.06 0.00 0.00 0.00 0.00 0.00 0.00 9.67 201415 0.00 0.47 3.11 2.03 0.00 4.06 0.77 0.00 0.01 0.00 0.00 0.01 10.47 201516 0.00 0.47 3.11 2.06 0.00 4.12 0.77 0.00 0.01 0.00 0.00 0.03 10.58 13.33 -2.11 7.56 -1.80 8.67 -1.84 8.74 201213 15.37 0.87 16.24 0.00 16.24 201314 10.84 0.02 10.86 0.00 10.86 201415 10.08 0.02 10.10 0.00 10.10 201516 9.04 2.14 11.19 0.00 11.19 201213 2.40 201314 2.34 201415 2.10 201516 2.22 201213 201314 201415 201516 344.02 342.30 0.01 422.51 420.40 0.01 366.98 365.15 0.01 390.00 388.05 0.00 57.02 75.39 70.35 74.04 Depreciation Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & ficture Office equipment Roads on land belonging to others Capital spares at generating stations Total: Depreciation on 90% of the Assets funded by Grants/subsidies Net Total Interest & financing charges Particulars Interest on loans Other finance charges Sub total Less: Interest capitalised Total Interest on working Capital Particulars IWC Profit & Loss Account Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges EXPENDITURE Assam Power Generation Corporation Limited Page 157 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement Surplus(+) / Shortfall(-) 0.12 8.02 10.83 2.61 13.35 16.24 0.00 2.40 0.00 12.03 13.17 4.44 7.56 10.86 0.00 2.34 0.00 6.69 13.46 2.75 8.67 10.10 0.00 2.10 0.00 7.69 14.59 2.97 8.74 11.19 0.00 2.22 0.00 0.00 -44.38 9.18 9.54 2.65 0.14 16.21 0.00 0.00 -3.36 47.05 9.54 3.23 0.15 53.50 0.00 0.00 0.00 43.77 9.54 3.23 0.31 50.38 0.00 0.00 0.00 47.40 9.54 3.23 0.31 54.01 40.81 21.89 19.97 20.03 201213 3.08 0.12 2.04 0.54 0.00 0.02 0.00 0.00 0.00 0.00 0.04 1.12 201314 3.17 0.24 2.60 0.60 0.00 0.02 0.00 0.01 0.00 0.00 0.01 1.66 201415 3.44 0.26 2.86 0.48 0.00 0.01 0.00 0.01 0.00 0.00 0.01 1.70 201516 3.73 0.29 3.10 0.52 0.00 0.01 0.00 0.01 0.00 0.00 0.01 1.84 6.96 0.00 6.96 8.32 0.00 8.32 8.78 0.00 8.78 9.51 0.00 9.51 201213 0.02 0.03 0.01 0.00 0.02 0.00 0.01 201314 0.04 0.18 0.01 0.00 0.00 0.00 0.04 201415 0.00 0.20 0.01 0.00 0.00 0.00 0.15 201516 0.00 0.21 0.01 0.00 0.00 0.00 0.16 LWHRP Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Assam Power Generation Corporation Limited Page 158 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Technical fees Other Professional fees Conveyance & Travel charges Freight 0.00 0.00 0.03 0.01 0.00 0.01 0.07 0.00 0.00 0.00 0.04 0.00 0.00 0.00 0.04 0.00 Other purchase related expenses 0.17 0.60 0.05 0.05 Sub Total: Less: Capitalised Total: 0.31 0.00 0.31 0.96 0.00 0.96 0.44 0.00 0.44 0.47 0.00 0.47 201213 0.00 0.57 0.00 0.06 1.35 0.00 1.98 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201213 201314 201415 201516 0.00 0.00 0.00 0.68 0.14 0.05 0.05 0.00 0.00 0.05 0.00 0.00 0.00 0.98 1.48 0.18 0.04 0.00 0.00 0.00 0.06 0.01 0.00 0.00 1.77 0.36 0.04 0.08 0.00 0.01 0.00 0.12 0.11 0.00 0.00 0.72 0.41 0.05 0.09 0.00 0.01 0.00 0.14 0.13 0.00 0.00 0.83 201213 0.00 0.00 0.56 0.94 13.10 201314 0.00 0.00 0.40 0.85 11.64 201415 0.00 0.00 0.40 0.85 11.49 201516 0.00 0.00 0.40 0.85 11.49 Other Income Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Hydraulic Other civil works Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: Depreciation Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Assam Power Generation Corporation Limited Page 159 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & ficture Office equipment Roads on land belonging to others Capital spares at generating stations Total: 0.00 0.20 0.00 0.00 0.00 0.00 0.00 14.80 0.00 0.18 0.00 0.00 0.00 0.00 0.00 13.07 0.00 0.18 0.00 0.00 0.00 0.00 0.00 12.92 0.00 0.18 0.00 0.00 0.00 0.00 0.03 12.95 14.80 -2.02 11.05 -2.02 10.90 -2.02 10.93 201213 16.76 0.00 16.76 0.00 16.76 201314 15.64 0.00 15.64 0.00 15.64 201415 14.04 0.00 14.04 0.00 14.04 201516 12.44 0.00 12.44 0.00 12.44 201213 1.79 201314 1.54 201415 1.44 201516 1.44 201213 201314 201415 201516 191.36 174.99 0.09 192.56 174.49 0.09 215.03 195.11 0.09 171.12 155.04 0.09 52.33 15.56 16.05 14.41 0.00 0.98 6.96 0.31 14.80 16.76 0.00 1.79 0.00 1.77 8.32 0.96 11.05 15.64 0.00 1.54 0.00 0.72 8.78 0.44 10.90 14.04 0.00 1.44 0.00 0.83 9.51 0.47 10.93 12.44 0.00 1.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Depreciation on 90% of the Assets funded by Grants/subsidies Net Total Interest & financing charges Particulars Interest on loans Other finance charges Sub total Less: Interest capitalised Total Interest on working Capital Particulars IWC Profit & Loss Account Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges EXPENDITURE Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Assam Power Generation Corporation Limited Page 160 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Total ROE Other Income Provision for taxes Annual Revenue Requirement Surplus(+) / Shortfall(-) 41.61 9.93 1.98 0.00 50.62 39.28 9.93 0.00 0.00 49.21 36.32 9.93 0.00 0.00 46.25 35.62 9.93 0.00 0.00 45.54 1.71 -33.66 -30.21 -31.13 NRPP Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 201213 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 7.30 0.27 6.04 1.03 0.01 0.03 0.02 0.05 0.00 0.00 0.04 1.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.01 5.34 10.67 201213 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 0.06 0.00 0.01 0.00 0.01 0.00 0.02 0.00 0.00 0.11 0.00 0.00 0.00 0.00 1.13 Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Administrative & purchase related expenses Assam Power Generation Corporation Limited Page 161 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Sub Total: Less: Capitalised Total: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.33 0.44 0.89 201213 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201213 201314 201415 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201213 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 0.00 0.00 0.00 0.26 17.39 0.00 0.02 0.00 0.15 0.00 0.00 0.24 18.05 Other Income Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Hydraulic Other civil works Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: Depreciation Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & ficture Office equipment Roads on land belonging to others Capital spares at generating stations Total: Assam Power Generation Corporation Limited Page 162 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Depreciation on 90% of the Assets funded by Grants/subsidies 0.00 Net Total 0.00 0.00 0.00 0.00 0.00 -3.26 14.78 201213 201314 201415 201516 5.07 0.00 5.07 19.71 0.00 19.71 19.71 0.00 30.26 0.00 30.26 -5.07 0.00 17.01 0.00 17.01 17.01 0.00 -10.09 20.18 0.00 0.00 0.00 4.39 201213 201314 201415 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 295.14 281.57 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.07 0.00 0.00 0.00 0.00 0.00 17.01 17.01 0.00 0.00 0.00 0.00 0.00 0.00 19.71 19.71 0.00 75.41 0.00 10.67 0.89 14.78 30.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Interest & financing charges Particulars Interest & financing charges Interest on loans Other finance charges Sub total Less: Interest capitalised Total Interest on working capital per AERC Profit & Loss Account Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges EXPENDITURE Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement Surplus(+) / Shortfall(-) -5.07 0.00 0.00 -10.09 4.39 0.00 0.00 0.00 126.32 14.57 0.00 0.00 140.89 140.89 Myntriang Employee Expenses Assam Power Generation Corporation Limited Page 163 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 201213 0.30 0.19 0.08 0.56 0.56 0.00 2013-14 0.28 0.00 0.23 0.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2014-15 0.30 0.00 0.25 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2015-16 1.49 0.00 1.22 0.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.60 0.00 0.60 0.63 0.00 0.63 3.06 1.59 1.47 2013-14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 2014-15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.00 2015-16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.14 0.00 0.06 0.07 0.36 0.10 0.00 0.10 0.09 0.00 0.09 0.50 0.26 0.24 2013-14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2014-15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2015-16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight 201213 0.02 0.10 Administrative & purchase related expenses Sub Total: Less: Capitalised Total: 0.12 0.12 0.00 Other Income Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: 201213 Assam Power Generation Corporation Limited Page 164 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Repairs & Maintenance 201213 Particulars 2013-14 2014-15 2015-16 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 201213 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2013-14 0.00 0.00 0.18 0.03 0.00 0.21 0.00 0.00 0.00 0.00 0.00 0.00 0.42 2014-15 0.00 0.00 0.37 0.06 0.00 0.42 0.01 0.00 0.00 0.00 0.00 0.00 0.84 2015-16 0.00 0.01 0.65 0.14 0.00 1.10 0.05 0.00 0.00 0.00 0.00 0.00 1.94 0.00 -0.70 -0.28 -1.74 -0.90 -2.46 -0.52 2013-14 0.28 0.00 0.28 -0.26 0.02 2014-15 0.95 0.00 0.95 -0.63 0.32 2015-16 0.84 0.00 0.84 -0.37 0.47 A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Hydraulic Other civil works Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: Depreciation Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & ficture Office equipment Roads on land belonging to others Capital spares at generating stations Total: Depreciation on 90% of the Assets funded by Grants/subsidies Net Total Interest & financing charges Particulars Interest on loans Other finance charges Sub total Less: Interest capitalised Total 201213 Assam Power Generation Corporation Limited Page 165 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Interest on working Capital 201213 Particulars IWC 2013-14 0.02 2014-15 0.07 2015-16 0.13 2013-14 2014-15 2015-16 0.00 0.00 0.00 0.71 0.70 0.02 41.59 41.17 0.01 0.00 0.00 0.00 0.00 0.03 0.60 0.10 -0.28 0.28 0.00 0.03 0.63 0.09 -0.90 0.95 0.00 0.03 1.47 0.24 -0.52 0.84 -0.26 0.02 -0.63 0.07 -0.37 0.13 0.00 0.00 0.00 0.49 0.00 0.00 0.00 0.49 0.00 0.00 0.00 0.24 0.86 0.00 0.00 1.11 0.00 0.00 0.00 1.82 3.27 0.00 0.00 5.09 -0.49 -1.11 -5.09 Profit & Loss Account Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges EXPENDITURE Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement Surplus(+) / Shortfall(-) 201213 7. Chandrapur Thermal Power Station 7.1. FY 12-13 to 15-16 Data Employee Expenses Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus 201213 1.79 0.00 1.02 0.19 0.00 201314 1.64 0.00 1.19 0.18 0.00 Assam Power Generation Corporation Limited 201415 1.78 0.00 1.31 0.09 0.00 201516 1.93 0.00 1.42 0.10 0.00 Page 166 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Subtotal Less: Capitalisation Total 3.01 0.00 3.01 3.02 0.00 3.02 3.18 0.00 3.18 3.45 0.00 3.45 201213 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Administrative & purchase related expenses 0.14 0.05 0.01 0.01 Sub Total: Less: Capitalised Total: 0.15 0.00 0.15 0.06 0.00 0.06 0.02 0.00 0.02 0.01 0.00 0.01 201213 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201213 201314 201415 201516 0.00 0.00 0.00 Administration and General Expenses Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Other Income Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: Repairs & Maintenance Particulars A. Special Type Repair & Maintenance:Overhauling Works Assam Power Generation Corporation Limited Page 167 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 B. Regular Repair & Maintenance:Plant & Machinery Buildings Hydraulic Other civil works Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: 0.00 0.00 0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201213 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201314 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201415 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201213 0.09 0.00 0.09 0.00 0.09 201314 0.05 0.00 0.05 0.00 0.05 201415 0.05 0.00 0.05 0.00 0.05 201516 0.04 0.00 0.04 0.00 0.04 201213 0.00 201314 0.00 201415 0.00 201516 0.00 Depreciation Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & ficture Office equipment Roads on land belonging to others Capital spares at generating stations Total: Depreciation on 90% of the Assets funded by Grants/subsidies Net Total Interest & financing charges Particulars Interest on loans Other finance charges Sub total Less: Interest capitalised Total Interest on working Capital Particulars IWC Profit & Loss Account Assam Power Generation Corporation Limited Page 168 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges EXPENDITURE Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement Surplus(+) / Shortfall(-) 201213 201314 201415 201516 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.11 3.01 0.15 0.00 0.09 0.00 0.00 0.00 0.03 3.02 0.06 0.00 0.05 0.00 0.00 0.00 0.00 3.18 0.02 0.00 0.05 0.00 0.00 0.00 0.00 3.45 0.01 0.00 0.04 0.00 0.00 0.00 0.00 0.00 3.35 0.00 0.00 0.00 3.35 0.00 0.00 0.00 3.16 0.00 0.00 0.00 3.16 0.00 0.00 0.00 3.24 0.00 0.00 0.00 3.24 0.00 0.00 0.00 3.50 0.00 0.00 0.00 3.50 -3.35 -3.16 -3.24 -3.50 Assam Power Generation Corporation Limited Page 169 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 APPEAL FOR TRUE-UP FOR THE FINANCIAL YEAR 2013-14 To Assam Electricity Regulatory Commission By Assam Power Generation Corporation Limited Bijulee Bhawan, Paltanbazar Guwahati-781 001 Assam Power Generation Corporation Limited Page 170 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 13.0. APPEAL FOR TRUING UP FOR FY 2013-14 Table 36: Particulars Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges Revenue from Secondary Energy Charges of KLHEP Total revenue from Sale of Power Other Income Total revenue income EXPENDITURE Cost of fuel Employee Expenses R&M Expenses Lubricants & Consumable stores Total R& M Expenses A&G Expenses Depreciation Interest & Finance Charges Provision for taxes Prior period items ROE Interest on working Capital Amount appeared in Annual Accounts 13-14 1786.40 1713.76 4.07% 1845.228 1732.847 6.09% 1845.23 1732.85 6.09% 483.95 547.05 544.49 10.99 494.94 10.55 557.60 2.51 547.00 10.60 557.60 289.45 78.12 14.91 385.36 82.00 24.60 1.23 25.83 12.53 28.68 43.96 0.45 84.15 385.15 82.00 494.94 688.79 613.95 7.97 494.94 0 688.79 -131.19 14.91 5.93 16.35 30.90 0.93 Amount claimed for TrueUp 37.99 18.25 Total Revenue Requirement Add: Incentive for generation for FY 2013-14 Add: Incentive for Secondary Energy generation for FY 2013-14 Gross Expenditure Surplus(+) / Shortfall(-) Note: I Approved Tariff Order 1314 26.03 12.53 25.66 31.28 0.45 -10.07 38.59 22.32 2.51 624.43 -66.83 Auxiliary Consumption: Actual APC of LTPS and NTPS for 2013-14 against normative APC is as given below: Power Station Normative APC Actual APC for 2013-14 LTPS NTPS KLHEP APGCL Total 5.5% 4.5% 0.50% 4.07% 8.78% 6.00%. 0.50% 6.09% APC as per APGCL’s Petition for Review of Normative APC 7.50% 5.50% 0.50% 5.33% Assam Power Generation Corporation Limited Page 171 of 228 Remarks *** ^^^ @@ $$ ## %% && Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 The Actual APC of APGCL is higher than the normative APC. Reason for this has already been explained in details in the Section 3.2 at Page No. 22 to 32 above. The actual APC of APGCL for 2013-14 is 6.09%. However, it comes down to 5.33% if the APC of LTPS and NTPS are considered as per APGCL’s Petition for review of normative APC of LTPS and NTPS. In view of this, APGCL appeals to AERC to consider APC of APGCL as 5.33%.for the True-up of 201314. Station Heat Rate: Actual Station Heat Rate of LTPS & NTPS against the Heat Rate given by AERC in the Draft amendment of AERC (Terms and Conditions for Determination of Tariff) Regulations 2006 is as given below: Station Actual Gross Heat Rate Heat Rate as per on GCV basis in 2013- AERC’s Draft Amended 14 (kcal/kWh) Regulation (kcal/kWh) LTPS with WHRU 3164 3200 NTPS 3976 4170 II Actual Station Heat Rates of LTPS and NTPS are more or less similar with that of the Draft Amended Regulation of AERC. In view of this, APGCL appeals to consider the actual Heat Rates of LTPS and NTPS in the True-up of 2013-14. III *** Note 21 of Annual Accounts 13-14 includes as follows:a. Sale of Power (ASEB) 547.00 b. Sale of scrap 0.06 Total Revenue from operation appeared in Profit & Loss Account 13-14 (less):- Sale of Scrap Total Revenue from tariff and Misc Charges claimed for true up 547.05 0.06 547.00 A statement of Month wise bill from Sale of Power is provided below: Assam Power Generation Corporation Limited Page 172 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 MONTHWISE BILL FOR SALE OF POWER For The Year 2013-14 MONTH Fixed Charge AMOUNT Variable Charge NTPS LTPS FPA Bill Secondary Charge Total NTPS (AMOUNT) LTPS (AMOUNT) Total SOP Total April'13 18,76,50,000.00 3,73,84,019.40 8,73,34,048.62 12,47,18,068.02 - 5,21,25,807.31 7,17,88,209.73 12,39,14,017.04 43,62,82,085 May'13 18,76,50,000.00 4,05,47,033.80 8,96,91,153.30 13,02,38,187.10 - 6,01,32,094.92 7,43,66,873.28 13,44,98,968.20 45,23,87,155 June'13 18,76,50,000.00 3,34,25,319.20 7,55,96,672.34 10,90,21,991.54 - 4,62,10,236.27 6,85,22,499.32 11,47,32,735.59 41,14,04,727 July'13 18,76,50,000.00 3,49,35,482.40 7,66,44,203.58 11,15,79,685.98 - 5,27,57,623.46 7,97,59,202.84 13,25,16,826.30 43,17,46,512 August'13 18,76,50,000.00 3,45,57,377.40 7,14,11,749.92 10,59,69,127.32 - 5,39,72,526.02 7,63,31,518.53 13,03,04,044.55 42,39,23,172 September'13 18,76,50,000.00 3,17,85,117.00 7,29,91,560.60 10,47,76,677.60 - 5,37,01,302.01 8,47,94,029.58 13,84,95,331.59 43,09,22,009 October'13 18,76,50,000.00 3,74,96,113.20 8,64,63,228.60 12,39,59,341.80 - 6,48,68,137.86 10,07,67,633.94 16,56,35,771.80 47,72,45,114 November'13 18,76,50,000.00 3,57,91,228.20 9,64,15,023.60 13,22,06,251.80 - 6,06,15,545.96 9,81,20,705.79 15,87,36,251.75 47,85,92,504 December'13 17,12,41,666.67 9,97,85,268.00 17,46,47,322.30 27,44,32,590.30 - 1,32,61,841.36 2,15,61,364.98 3,48,23,206.34 48,04,97,463 January'14 17,12,41,666.67 10,14,66,068.00 17,96,52,905.04 28,11,18,973.04 - 1,17,41,064.85 3,06,83,701.67 4,24,24,766.52 49,47,85,406 17,12,41,666.67 10,72,87,928.00 13,48,28,634.18 24,21,16,562.18 84,26,180.39 1,96,65,524.84 2,26,69,054.04 4,23,34,578.88 46,41,18,988 25,80,55,463.64 79,59,218.93 1,45,03,819.70 2,75,44,637.82 4,20,48,457.52 47,93,04,807 January'14 February'14 March'14 - 17,12,41,666.67 8,91,87,252.00 16,88,68,211.64 Additional for FY 13-14 TOTAL 2,18,61,66,666.68 68,36,48,206.60 1,31,45,44,713.72 1,99,81,92,920.32 52,18,526.25 52,18,526 35,30,043.09 2,51,33,968.66 35,30,043 50,35,55,524.56 75,69,09,431.52 1,26,04,64,956.08 Assam Power Generation Corporation Limited 5,46,99,58,512 Page 173 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 ^^^ IV V @ Other Income appeared in Profit and Loss A/c 13-14 10.55 Add:- Sale of Scrap appeared in Note 21 of Annual Accounts 13-14 Total Other Income claimed 0.06 10.60 Cost of fuel detailed in Note 24 of Annual Accounts is as follows: a. Gas b. Gas/Oil (Internal Combustion) Total 29.86 355.50 385.36 The Gas/Oil (internal combustion) includes Rs. 0.20 Crore towards Oil (Internal Combustion) which is now claimed in Repair & Maintenance. An abstract from Quarterly Trial Balance is Annexed at Annexure-A VI $$ 1. Repair & Maintenance claimed in true up as follows:Note 27 of Annual Accounts 13-14 (+) Lubricants and consumable stores (Note 24 of Annual Accounts) (+)Oil (Internal Combustion) ( Refer Note V) Total R& M Expenses Claimed 24.60 1.23 0.20 26.03 2. During FY 13-14 there was an expenditure for the Overhauling of Karbi Langpi HEP Unit #2 of Rs. 9.03 Cr. the Overhauling work was approved by the Commission in the following breakup: In the Tariff Order for 13-14: Rs. 4.10 Cr. In the Review Order of 13-14: Rs. 12.73 Cr. Total Overhauling amount: Rs. 16.83 Cr. Further there was an expenditure of Rs. 5.77 Cr for LTPS for procurement of Plant & Machinery spares. Moreover while approving R&M for FY 13-14 @ Rs. 14.91 does not include Lubricants & consumables and Turbine Oil expenses, which is now in addition to normal R&M expenses claimed in the true up. VII ++ The Hon’ble Commission has approved an amount of Rs. 5.93 for FY 13-14. However, during FY 13-14 an amount of Rs. 5.78 Cr has been further provided for Electricity Bill of Different Offices of APGCL to be paid to APDCL in addition to normal A&G expenses in the annual accounts, which resulted in increase in A&G expenses compared to previous year and than that approved by the Commission. VIII ## Depreciation Calculated at norms specified by Hon'ble AERC. IX %% 1. Sanction letters of Loans from GOA received up to FY 13-14 is provided at Annexure-B 2. Interest rate considered for State Govt. Loan is provided at Annexure-C 3. Loan drawl from PFCL during FY 13-14 is provided at Annexure-D 4. Interest and repayments made to PFCL during FY 13-14 and for FY 14-15 (up to Dec’14) is provided at Annexure-E 5. Moreover as the GPF trust is not formed till FY 13-14, no interest on GPF claimed for that FY in true up. X !! APGCL incurred Taxes on account of TDS on investments. Relevant TDS certificates are Annexed at F XI && Prior Period items appeared in Annual Accounts and claimed in True-up for FY 201314 is detailed below: Assam Power Generation Corporation Limited Page 174 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Appeared in Annual Accounts Details of Prior Period Items (a) Prior period income includes:(i) withdrawl of excess provision of interest on public bond as per C&AG's comment No.A.1 by Rs. 20,78,46,329/for periods 2005-06 to 2009-10 Claimed in True up Remarks 207846329 0.00 The said amount was not considered in earlier tariff orders by the Honble Commission in earlier tariff orders , hence not claimed. (ii) withdrawl of excess provision of bond repayment issued via warrant by Rs. 4,04,29,489/-. 40429489 0.00 The withdrawal of excess provision of bond repayment is a capital item and does not form part of any component of ARR , hence not taken into consideration (iii) withdrawl of provision made against "Assam Building & other Construction Workers Welfare Cess" in prior period as per C&AG commnent No.A.04 by Rs.1,73,63,728/-. 17363728 0.00 The Hon'ble Commission allowed provision for taxes on submission of payment challans for taxes and did not considered provision made against "Assam Building & Other Constuction workers welfare cess in earlier tariff orders and hence the said amount is not claimed. (iv) withdrawl of adjustment Jv. No.21 of FY 2012-13 as per POS-11 of C&AG audit by Rs.1,58,37,047/-. 15837047 0.00 The adjustment relates to oil stock which does not form of any component of ARR, hence not claimed in Prior period income: 100484453 (v) withdrawl of excess provision of ROP arrear for FY 09-10 100484453 (vi) withdrawl of ADB loan interest accounted in prior period 953971 vii) Interest income for prior period viii) Other income relating to prior period Subtotal (a) (b) Prior period expense includes:i) Operating expenses for Prior Period (KLHEP) (ii) LD recovered from BHEL against LWHRP booked as other income now rectified & adjusted with asset as per commnent C&AG No.A.03 by Rs.5,57,11,893/- 1315 1315 1030296 1030296 383946628 101516064 759224 759224 55711893 (iiI) Revenue surplus of Rs.96.38 crore for 09-10 and Rs.20.51 crore for 10-11 arrived by AERC while truing up adjusted as per commnent C&AG No.C.1 1168900000 iv) Other charges relating to Prior Period 93547 1225464664 841518036 Subtotal (b) Net Prior Period 0.00 The said amount was not considered in earlier tariff orders by the Honble Commission in earlier tariff orders , hence not claimed. 0.00 The amount of LD recovered from BHEL is adjusted with Asset and does not form part of any component of ARR , hence not claimed in prior period expense. However the effect of same is considered while computing Depreciation. 0.00 Revenue surplus of Rs.96.38 crore for 09-10 and Rs.20.51 crore for 1011 arrived by AERC while truing up adjusted as per comment C&AG No.C.1 93547 852771 -100663293 Assam Power Generation Corporation Limited Page 175 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 ENERGY CHARGE OF APGCL: 2013-14 STATION Energy Charge (Rs./kWh) Apr/13 May/13 Jun/13 Jul/13 Aug/13 Sep/13 Oct/13 Nov/13 Dec/13 Jan/14 Feb/14 Mar/14 Total Fuel Quantity (MMSCM) 26.41 26.64 23.40 21.92 21.99 23.11 23.45 25.21 26.70 27.76 24.10 25.32 296.00 Fuel Cost Rs. in Cr. 18.84 19.05 17.47 17.99 17.96 19.71 19.96 20.89 22.30 23.09 20.19 21.10 238.56 Energy Sent Out (MU) 69.31 71.18 60.00 60.83 56.68 57.93 68.62 76.52 78.67 80.93 60.73 76.07 817.47 Namrup TPS Fuel Quantity (MMSCM) Fuel Cost Rs. in Cr. Energy Sent Out (MU) 20.18 11.75 20.69 12.54 17.60 17.43 11.21 17.82 11.33 17.59 11.68 17.52 11.81 16.36 20.04 13.36 20.91 13.78 21.98 15.67 17.77 12.38 225.90 146.57 41.08 44.56 38.39 37.98 34.93 41.20 45.36 46.12 48.77 40.54 494.98 Lakwa TPS + WHRP 10.24 36.73 10.84 39.33 Assam Power Generation Corporation Limited 2.92 2.96 Page 176 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 1 2 NTPS LTPS Total 119.5 157.2 50% 50% 523.41 688.54 4.50% 5.50% 5 499.857 650.667 1150.523 6 50.30% 65.08% 6 526.568 896.150 1422.718 8 6.00% 8.78% 9 494.985 817.465 1312.450 10=(9-5) -4.872 166.799 Incentive Rs Crore Ex-bus energy eligible for incentive Net Generation (Actual) (MU) Actual aux. consumption(%) 4 Gross Generation(Actual) (MU) 3 Actual PLF Approved aux. consumption(%) 2 Net generation with target PLF(MU) Gross Generation with target PLF (MU) 1 Target PLF for allowing incentive(%) SI. No. Station Installed Capacity (MW) Incentive computation for thermal stations for FY 2013-14 11=25 paise x 10 0.00 4.17 4.17 Note: For NTPS the incentive is negative, hence it set to zero Target Capacity Index (Run of River with Pondage Power Station) Actual Capacity Index Capacity of APGCL (MW) Annual Fixed Charges of APGCL (Rs Crore) Annual Fixed Charges of KLHEP (Rs Crore) 1 2 3 4 5 6 7=(2x6)/5 KLHEP 100 85% 95.10% 376.7 218.20 57.92 Incentive in (Rs Crore) Capacity of KLHEP 1 Station SI. No. Incentive computation for Hydro station for FY 2013-14 8= 0.65 x (4-3) x 7 3.80 Assam Power Generation Corporation Limited Page 177 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Certificate for Energy Generation of APGCL for FY 2013-14 from SLDC Assam Power Generation Corporation Limited Page 178 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 PETITION FOR APPROVAL FOR ANNUAL PERFORMANCE REVIEW FOR THE FINANCIAL YEAR 2014-15 To Assam Electricity Regulatory Commission By Assam Power Generation Corporation Limited Bijulee Bhawan, Paltanbazar Guwahati-781 001 Assam Power Generation Corporation Limited Page 179 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 14 APPEAL FOR ANNUAL PERFORMANCE REVIEW OF 2014-15 14.1 Investments Table 35 Investment (13-14) Investment LTPS KLHEP NRPP MARGHERITA TPP MYNTRIANG KLHEP (Upper Stage) KLHEP (Inter.Stage-I) KLHEP (Inter.Stage-II) KLHEP Barrage Toe Project SOURCE State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant (Rs. in Crore) 2013-14 1.50 5.39 50.00 0.90 8.00 0.90 0.30 0.30 0.30 Assam Power Generation Corporation Limited Page 180 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 70 MW LRPP TOTAL 14.2 PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others 0.98 0.00 18.57 0.00 50.00 0.00 68.57 The following tables highlight the individual’s details of each expense for FY 1213 &13-14. 14.2.1 Employees Expenses for FY 12-13 & 13-14 Table 36 Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 2012-13 33.06 0.63 21.96 6.37 0.02 0.19 0.04 0.18 0.00 0.02 0.22 11.11 2013-14 33.81 1.44 27.12 6.93 0.03 0.18 0.05 0.27 0.00 0.01 0.13 12.04 73.80 1.67 72.11 82.00 0.00 82.00 14.2.2 Repairs & Maintenance for FY 12-13 & 13-14 Table 37 Particulars A. Special Type Repair & Maintenance:Overhauling Works B. Regular Repair & Maintenance:Plant & Machinery Buildings Other civil works Hydraulic 2012-13 2013-14 0.00 0.00 16.12 1.57 1.02 0.55 20.60 1.81 0.87 0.89 Assam Power Generation Corporation Limited Page 181 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: 0.00 0.09 0.22 0.05 0.00 0.00 19.62 0.03 0.06 0.26 0.08 1.23 0.20 26.03 14.2.3 Administration and General Expenses for FY 12-13 & 13-14 Table 38 Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Other purchase related expenses Energy bill raised by APDCL Sub Total: Less: Capitalised Total: 2012-13 0.23 1.25 0.13 0.00 0.43 0.02 0.04 0.01 0.05 0.70 0.15 3.48 0.00 6.50 0.12 6.38 2013-14 0.35 0.81 0.12 0.01 0.02 0.02 0.60 0.02 0.07 0.76 0.04 9.72 0.00 12.53 0.00 12.53 2012-13 0.00 5.96 0.03 0.69 1.50 0.01 8.17 2013-14 0.00 8.85 0.06 0.79 0.90 0.01 10.60 2012-13 0.00 0.74 5.55 3.32 15.75 4.50 1.04 0.13 0.04 2013-14 0.00 0.72 3.82 3.02 15.07 4.27 0.21 0.12 0.04 14.2.4. Income from Other Sources for FY 12-13 & 13-14 Table 39 Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: 14.2.5. Depreciation for FY 12-13 & 13-14 Table 40 Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & fixtures Assam Power Generation Corporation Limited Page 182 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Office equipment Roads on land belonging to others Capital spares at generating stations Total (Less) : Depreciation on 90% of the Assets funded by Grants/subsidies Net Total 0.03 0.00 0.55 31.66 0.05 0.00 3.72 31.05 31.66 -5.39 25.66 Note: Sanction Letters of Grant received by APGCL are annexed at G. Statement of Grant received by APGCL is provided below: 2012-13 Sl.No. FY 1.00 2.00 3.00 4.00 5.00 2004-05 2005-06 2006-07 2006-07 2006-07 Project for Lungnit SHEP LWHRP Myntriang SHEP KLHEP KLHEP & LWHRP 6.00 6.00 2008-09 Namrup RPP 7.00 2009-10 Myntriang SHEP 8.00 2009-10 Lungnit SHEP 9.00 2009-10 Lungnit SHEP 10.00 2009-10 Namrup RPP 11.00 2009-10 LTPS 12.00 2009-10 NTPS 13.00 2009-10 KLHEP 14.00 2009-10 Lungnit SHEP 15.00 2009-10 Amring SHEP 16.00 2010-11 Namrup RPP 17.00 2010-11 Myntriang SHEP 18.00 2011-12 Namrup RPP 19.00 2011-12 Lower Kopili HEP 20.00 2012-13 Namrup RPP 21.00 2012-13 Myntriang SHEP 22.00 2012-13 KLHEP Total Add : ADB grant Add: Donated Capital Assets Type of grant MNRE State Govt. grant NABARD State Govt. grant State Govt. grant Amount LWHRP 165000000.00 KLHEP 416570000.00 State Govt. grant NABARD MNRE MNRE State Govt. grant State Govt. grant State Govt. grant State Govt. grant NEC NEC State Govt. grant NABARD State Govt. grant State Govt. grant State Govt. grant NABARD State Govt. grant Total Capital Reserve as on 31.03.13 Grants & Subsidies on Capital Assets as on 01.04.13 Remarks 18000000.00 Work in progress 450000000.00 Capital asset 92289000.00 Work in progress 100000000.00 Capital asset Capital asset 581570000.00 300000000.00 150000000.00 18000000.00 18000000.00 122500000.00 40000000.00 10000000.00 30000000.00 15000000.00 4000000.00 270000000.00 36153000.00 609750000.00 50000000.00 616950000.00 150000000.00 190000000.00 3872212000.00 11839991.00 108447500.00 Work Work Work Work Work Work Work Work Work Work Work Work Work in progress in progress in progress in progress in progress Capital Capital Capital in progress in progress in progress in progress in progress in progress in progress in progress Capital asset asset asset asset 3,99,24,99,491 LWHRP KLHEP NTPS LTPS 61,50,00,000 73,65,70,000 13,02,87,491 4,00,00,000 1521857491.00 2470642000.00 3,99,24,99,491 Grants & Subsidies on Work in progress as on 2013-14 Cummulative grant received by APGCL as on 01.04.13 Less : Transfer of capital grant to revenue grant as per commnent C&AG No.A.02) Add: ADB loan to ADB grant as per order No.PEL.112/2005/54 dtd. 29/03/08) Cummulative grant received by APGCL as on 01.04.14 Grants & Subsidies on Capital Assets as on 01.04.14 LWHRP KLHEP NTPS LTPS Myntrian g SHEP Grants & Subsidies on Work in progress as on 01.04.14 Cummulative grant received by APGCL as on 01.04.14 61,50,00,000 54,65,70,000 13,16,03,045 4,00,00,000 3992499491.00 -190000000.00 1315554.00 3,80,38,15,045 1,76,16,15,045 Capital asset Capital asset Myntriang SHEP com m issioned in FY 2013-14. WIP Grants converted to Capital grant 42,84,42,000 2,04,22,00,000 3,80,38,15,045 Assam Power Generation Corporation Limited Page 183 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 2014-15 Sl.No. FY Project for Type of grant Amount Cummulative grant received by APGCL as on 01.04.14 1.00 2013-14 Namrup RPP State Govt. grant 2.00 2013-14 Myntriang SHEP State Govt. grant 3.00 2013-14 Myntriang SHEP State Govt. grant Remarks 3803815045.00 68550000.00 Work in progress 100000000.00 Capital asset 33000000.00 Capital asset Myntriang Small Hydro 4.00 2014-15 Electric Project State Govt. grant Cummulative grant received by APGCL as on 01.04.15 Grants & Subsidies on Capital Assets as on 01.04.15 70000000.00 4,07,53,65,045 LWHRP KLHEP NTPS LTPS Myntrian g SHEP 61,50,00,000 54,65,70,000 13,16,03,045 4,00,00,000 Capital asset 1,96,46,15,045 63,14,42,000 2,11,07,50,000 4,07,53,65,045 Grants & Subsidies on Work in progress as on Cummulative grant received by APGCL as on 01.04.15 2015-16 Sl.No. FY Project for Type of grant Cummulative grant received by APGCL as on 01.04.15 Amount 4075365045.00 Remarks Myntriang Small Hydro 1.00 2015-16 Electric Project 235000000.00 Capital asset 16700000.00 Capital asset State Govt. grant 7475000.00 Capital asset State Govt. grant 8250000.00 Work in progress 7.00 2015-16 State Govt. grant Cummulative grant received by APGCL as on 01.04.16 4870000.00 Work in progress 4,34,76,60,045 2.00 2015-16 5.00 2015-16 6.00 2015-16 Karbi Langpi Hydel Electric Project SD for slope stabilisation of Hatidubi KLHEP Dam SD for procurement/ acquisition of Land for Cachar distributed acquisition of Land for Titabor Pow er project State Govt. grant Grants & Subsidies on Capital Assets as on 01.04.16 LWHRP KLHEP NTPS LTPS Myntrian NRPP 61,50,00,000 57,07,45,000 13,16,03,045 4,00,00,000 86,64,42,000 1,98,77,50,000 NRPP expected commissioning in FY 2015-16. Hence WIP 4,21,15,40,045 Grants in respect of NRPP converted to Capital grant Grants & Subsidies on Work in progress as on 01.04.16 13,61,20,000 Cummulative grant received by APGCL as on 01.04.16 4,34,76,60,045 Assam Power Generation Corporation Limited Page 184 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 14.2.6 Repayment of Loan (Principal) for FY 12-13 & 13-14 Table 41 Particulars PFC Loan State Govt Loan Total 2012-13 22.97 0.00 22.97 2013-14 22.97 0.00 22.97 2012-13 44.30 4.96 49.26 -6.73 42.53 2013-14 50.68 0.05 50.73 -19.46 31.27 14.2.7. Interest & financing charges Table 42: Particulars Interest on loans Other finance charges Sub total Less: Interest capitalised Total 14.2.8 Interest on Working Capital Table 43: Particulars One month Fuel Cost One month approved O&M Cost Maintenance Spares Two month Receivables Total Interest @ 14.00 % for 12-13 & 14.75% for 13-14 2012-13 26.14 7.69 12.13 104.37 150.33 21.05 2013-14 32.10 9.79 12.48 96.97 151.34 22.32 Note: Interest on Normative working capital as per AERC 14.2.9. Profit & Loss account for 2012-13 & 2013-14 Table 44: Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges O&M expenses of CTPS EXPENDITURE Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital 2012-13 2013-14 1765.26 1631.60 7.57% 1845.23 1732.85 6.09% 459.66 0.00 547.00 0.00 365.50 19.62 72.11 6.38 31.66 49.26 -6.73 15.83 385.15 26.03 82.00 12.53 25.66 50.72 -19.44 22.32 Assam Power Generation Corporation Limited Page 185 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement Add: Incentive for generation for FY 2013-14 Add: Incentive for Secondary Energy generation for FY 2011-12 Surplus(+) / Shortfall(-) 0.00 0.00 -65.02 488.61 37.99 8.17 0.50 539.65 -79.99 Assam Power Generation Corporation Limited 0.00 0.00 -10.07 574.91 38.59 10.60 0.45 603.35 7.97 2.51 -66.83 Page 186 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 14.2.10 Balance Sheet for FY 12-13 & 13-14 Table 45: Particulars Source of Fund Share Capital Reserve & Surplus Loans from State Govt Loans from others Total Contributions, grants & subsidies towards cost of Capital Asset Grand Total Application of Fund Net Fixed Assets (A) Gross Block (B) Less : Accumulated Depreciation (C) Net Fixed Assets (D) Capital-works-in-progress (E) Asset not in use (F) Deferred Cost (G) Intengible Asset Total of (C) to (G) Investements Subsidy receivable from Govt Net Current Assets A. Current Assets, Loans & Advances i) Inventories ii) Receivables against Sale of Power iii) Cash & Bank Balance iv) Loans & Advances v) Other current assets Total of A B. Current Liabilities and provisions i) Borrowing for Working Capital ii) Payment due on Capital Libilities iii) Other current liabilities Total of B Net Current Assets (A - B) Profit/ Loss Grand Total 2012-13 2013-14 455.86 30.45 117.21 374.39 455.86 36.33 135.78 405.49 977.91 399.25 1377.16 1033.47 380.38 1413.85 1284.44 597.70 686.74 565.93 1325.74 626.38 699.36 568.98 1252.67 0.00 1268.34 0.00 58.23 94.86 117.64 56.51 66.38 393.62 68.25 3.44 154.09 57.40 76.23 359.41 355.77 355.77 37.85 86.64 1377.16 386.91 386.91 -27.50 173.01 1413.85 Assam Power Generation Corporation Limited Page 187 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 15. Revised Annual Revenue Requirement (ARR) for 2014-15 15.1 Table 46: Assumptions for various Heads – I 2014-15 14.75% ST PLR R & M Expenses Employee Expenses A & G Expenses ROE escalation rates Other Income Provision for Taxes Provision for Bad and Doubtful Debts % of revenue Current Assets - per Actual O&M Expenses Mainranence spares Receivable against sale of power Current Assets - per AERC O&M Expenses & fuel Maintenance spares Receivable against sale of power Power purchase Payable Depreciation rate applicable for Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Lines & Cable Network Vehicles Furniture & fixtures Office equipment Roads on land Belonging to others Capital spares at generating stations Cap of Asset Value 15.00% 8.42% 8.42% 14.00% @ 10% escalation at approved by Hon'ble AERC 0.00 On annual Expenditure 1% of Gross Block On the total revenue demand On annual Expenditure 1% of Gross Block On the total revenue demand Thermal 0.00 1.80% 2.57% 1.80% 6.00% 2.57% 18.00% 6.00% 6.00% 1.80% 4.75% 90.00% Hydel 0.00 1.80% 2.57% 1.80% 2.57% 2.57% 18.00% 6.00% 6.00% 1.80% 4.75% 90.00% Loan Rates - New Loan Institution Assam Power Generation Corporation Limited 11.40% Page 188 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Existing Loans Rates of interst State Govt 10.50% @ different agreement rates 11.40% PFC Other Loan Repayment Govt Loan PFC Others 11.07 22.97 0.00 Thermal O & M for new stations on commercial startup year subsequently @ inflation Interest rate for investment income Hydel 5.72% O & M for new stations on commercial startup year subsequently @ inflation Interest rate for investment income 5.72% 15.2 Table 47 Assumptions for various heads – II Investment NTPS LTPS KLHEP NRPP MARGHERITA TPP Rs. In Crores SOURCE State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity 2014-15 Fund from Annual Plan 13-14. Investment (14-15) 7.00 8.67 20.19 1.56 6.86 Assam Power Generation Corporation Limited Page 189 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 MYNTRIANG 120 MW Lower kopili Boundary wall at jagiroad for KLHEP Store KLHEP (Upper Stage) 70 MW LRPP TOTAL State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt . Equity State Govt. Loan State Govt. Grant PFC Loan Others State Govt. Equity State Govt. Loan State Govt. Grant PFC Loan Others 2.00 13.30 7.00 7.00 0.36 0.60 0.00 7.00 20.16 0.00 0.00 27.16 0.00 40.38 7.00 0.00 0.00 47.38 74.54 15.3. Actual/ Projected Operating Performance Data for FY 2014-15 Table 48 NTPS Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) Gross Station Heat Rate on NCV(Kcal/ Kwh) Sp. Gas Consumption (SCM/Kwh) LTPS with WHRU Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU FY 14-15 591.66 5.8% 557.60 62.6% 57% 4056 0.4254 FY 14-15 935.30 8.6% 855.30 Assam Power Generation Corporation Limited Page 190 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Availability (%) PLF (%) Gross Station Heat Rate on NCV(Kcal/ Kwh) Sp. Gas Consumption (SCM/Kwh) KLHEP Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Capacity Index (%) PLF (%) Myntriang SHEP St-II Gross Energy in MU Aux. Power Cons. (%) Net Generation in MU Availability (%) PLF (%) APGCL APGCL Total Gross Generation (MU) APGCL APC (%) APGCL Total Net Generation (MU) Availability (%) PLF (%) 78.4% 68% 3058 0.3088 FY 14-15 366.98 0.5% 365.15 92.6% 42% FY 14-15 0.71 1.7% 0.70 4.3% 4.2% FY 14-15 1894.66 6.12% 1778.73 76% 59% Variation of Actual/ Projected Heat Rate and Aux. Consumption with the Normative Parameters in FY 2014-15: Heat Rate: Actual Gross SHR on GCV basis(kcal/kWh) in FY 2014-15 Heat Rate as per AERC’s Draft Amended Regulation of 2006 (kcal/kWh) NTPS 4056 4170 LTPS With WHRU 3058 3200 Power Station From the above table it is observed that the actual Gross SHR of LTPS and NTPS in the FY 14-15 is more or less similar with that of the Draft Amended Regulation of AERC. In view of this, the projected Station Heat Rates of LTPS and NTPS have been considered in the Annual Performance Review of 2014-15. Aux. Power Cons. (APC): Power Station NTPS LTPS KLHEP Myntriang APGCL Normative Aux. Cons. Actual Aux. Cons. in FY 2014-15 4.5% 5.5% 0.5% 1.0% 4.2% 5.8% 8.6% 0.5% 1.7% 6.1% APC as per APGCL’s Petition for Review of Normative APC 5.5% 7.5% 0.5% 1.0% 5.5% Assam Power Generation Corporation Limited Page 191 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 From the above it is seen that the Actual/Projected APC of APGCL for 2014-15 is higher than the normative APC. Reason for this has already been explained in details in the Section 3.2 at Page No. 22 to 32 above. The actual/Projected APC of APGCL for 2014-15 is 6.1% if the APC of LTPS and NTPS are considered as per APGCL’s Petition for review of normative APC of LTPS and NTPS. In view of this, APGCL appeals to AERC to consider APC of APGCL as 5.5%.for the Annual Performance Review of 2014-15. 15.4. Actual/ Projected Financial Performance Data for FY 2014-15 15.4.1 Employees Expenses Table 49 Particulars Salaries Overtime Dearness Allowance Other Allowances Bonus Medical Allowances Leave Travel Assistance Earned Leave Encashment Workmen Compensatory Payment Other Staff Cost Staff Welfare Expenses Terminal Benefits Subtotal Less: Capitalisation Total 2014-15 36.65 1.66 29.85 5.61 0.03 0.09 0.05 0.29 0.00 0.01 0.14 12.16 86.54 0.00 86.54 Note: 1. Employee expenses for FY 14-15 are in actual upto 2nd quarter before any Head quarter adjustment. Regarding 3rd & 4th quarter of FY 14-15 expenses are assumed to be proportionate to the expenses of 1st & 2nd quarter. 15.4.2. (A) Regular Repairs & Maintenance Table 50 Particulars Plant & Machinery Overhauling Works Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: 2014-15 14.74 0.00 0.27 0.31 1.10 0.09 0.26 0.14 0.20 1.41 0.23 18.75 Note: Regular R&M cost for FY 14-15 is taken at par to that approved in Tariff order FY 14-15. In addition, Lubricants & Consumable Stores & Turbine oil is also considered. Assam Power Generation Corporation Limited Page 192 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 15.4.2. (B) Special Type Repair & Maintenance Works Particulars Plant & Machinery (Overhauling of Unit # 2 of LTPS) Total: 2014-15 6.44 6.44 Note: Originally the estimated approved amount of this overhauling works was Rs. 8.5 Cr., out of which Rs 2.0 Cr. was approved in Tariff Order for FY 2013-14 and Rs. 6.5 Cr. was booked in the revised ARR for FY 2015-16 against Repair Maintenance of the Unit in the "Order on Review Petition on Tariff Order of FY 2013-14" vide letter No. AERC 442/2014/15 dated 08.07.2014. However, the expenditure of Rs. 2.0 Cr., allowed in Tariff order for FY 2013-14, was not incurred in that FY. The present estimated overhauling cost involvement of LTPS Unit # 2 is around Rs.12.94 Cr. The variation in the estimated cost is due to additional works. Cost Benefit Analysis for the Special Type of Repair & Maintenance of Unit 2 of LTPS is given below: Major overhauling of LTPS Unit-2 PROJECT: PROJECT COST: Loan Interest rate for short term loan Rate (WACC) Project Life Escalation of Annual O & M Depreciation : 1,294.00 1,294.00 15.00% 10.14% 5 1/2 8.42% 16.36% 1.NPV Evaluation No. of FY years 1 2 0 2014-15 1 2015-16 2 2016-17 3 2017-18 4 2018-19 5 2019-20 6 2020-21 6 2020-21 ACQUISI TION COST Fuel Cost 3 4 1,294.00 Scrap value 1,294.00 ANNUAL DEPRECIA TOTAL O&M TION EXPENSES 5 32.35 34.29 36.35 38.53 40.84 21.65 20,366.73 204.01 > Since NPV 2. IRR: 6 1,850.13 3,701.28 3,702.30 3,703.34 3,704.39 3,705.29 211.75 211.75 211.75 211.75 211.75 105.87 129.40 1,294.00 7=3+4+5+6 ANTICIPA EARNINGS PROVISI TED BEFORE ON FOR REVENUE TAXES TAXES 8 9=8-7 1,294.00 2,094.23 3,947.32 3,950.40 3,953.61 3,956.97 3,832.81 2,292.80 4,319.57 4,303.32 4,286.78 4,270.39 4,052.69 (1,294.00) 198.57 372.26 352.92 333.17 313.42 219.87 21,735.34 23,525.55 1,790.21 10 0.00 52.01 45.74 39.34 32.94 36.94 206.96 PROFIT OPERATIN NPV OF AFTER G CASH OP. CASH TAX FLOW FLOW 11=9-10 12=11+6 (1,294.00) 198.57 320.25 307.18 293.83 280.48 182.94 (1,294.00) 410.32 532.00 518.92 505.57 492.22 418.21 1,583.24 2,877.24 0, the major overhauling is accepted. Year n 0 1 2 3 4 5 6 (1,294.00) 372.54 438.55 388.39 343.56 303.69 234.27 FW OF CASH FLOW (1,294.00) 410.32 532.00 518.92 505.57 492.22 418.21 28.88% Assam Power Generation Corporation Limited Page 193 of 228 15 (1,294.00) 372.54 438.55 388.39 343.56 303.69 234.27 787.01 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 SOP determination from Major overhauling of LTPS Unit-2 Project cost 1294.00 Loan 1294.00 Equity A B C D E 0.00 Annual O&M Interest and finance Charges depreciation Fixed charges Interest on working capital return on equity Fuel Cost Sale of Power (A+B+C) 1 32.35 2 34.29 3 36.35 4 38.53 5 40.84 6 21.65 97.05 211.75 341.15 174.69 211.75 420.73 155.28 211.75 403.37 135.87 211.75 386.14 116.46 211.75 369.05 97.05 105.87 224.57 101.52 0.00 1850.13 2292.80 197.57 0.00 3701.28 4319.57 197.64 0.00 3702.30 4303.32 197.30 0.00 3703.34 4286.78 196.96 0.00 3704.39 4270.39 122.82 0.00 3705.29 4052.69 NB: 1 Depreciation @ 16.36% has been taken for evaluation purpose i.e 90%/5.5 2 Interest on short term loan 3 Annual O&M for the initial year of operation is taken at 2.5% of the project cost. 4 O&M Escalation @ 8.42% 5 Tax @ 32.4% 6 Discounting factor (WACC) 15% 10.14 % WACC=Rd*(1-t)*D/V+ Re*E/V where; Rd- cost of debt Re- cost of equity E/V- percentage of financing that is equity D/V- percentage of financing that is debt t- tax rate 7 Repayment of loan considered to be paid during the life of the project. 8 Estimated actual fuel cost computed is considered for revenue/ SOP determination Assam Power Generation Corporation Limited Page 194 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 The work order for supply of the capital spares have been already issued to the OEM at an amount of Rs 12.29 Cr and LC for an amount of Rs. 12.29 Cr had been already been opened for procurement of these capital spares. The LC amount is likely to be encashed by the party in FY 14-15. In addition to the amount of Rs. 12.29 Cr for spares, another amount of Rs. 0.60 Cr for work component and Rs. 0.05 Cr for other miscellaneous expenses is estimated to incur for the overhauling of Unit#2 of LTPS totaling the whole amount to Rs. 12.94 Cr. The Board Resolution and Agenda for the procurement of spares is given below: Assam Power Generation Corporation Limited Page 195 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Assam Power Generation Corporation Limited Page 196 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 However, as per Hon'ble Commission's order dated.08.07.14, an amount of Rs. 6.5 Cr. is booked in the revised ARR for FY 2015-16 against Repair Maintenance of the Unit. The balance amount of Rs. 6.44 Cr. is shown in Revised ARR for FY 2014-15 under Annual Performance Review of the FY. It is appealed before Hon’ble Commission to approve the balance amount of Rs. 6.44 Cr for the above mentioned reasons. 15.4.2. Total Repairs & Maintenance [15.4.2. (A) + 15.4.2. (B)] Particulars Plant & Machinery Overhauling Works Buildings Other civil works Hydraulic Lines & Cable Network Vehicles Furniture & fixture Office equipment Lubricants & Consumable stores Turbine Oil Total: Assam Power Generation Corporation Limited 2014-15 21.18 0.00 0.27 0.31 1.10 0.09 0.26 0.14 0.20 1.41 0.23 25.19 Page 197 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 15.4.3 Administration and General Expenses Table 51 Particulars Rent, Rates & Taxes Insurance Telephone charges Postage & Telegrarm Legal charges Audit fees Consultancy charges Technical fees Other Professional fees Conveyance & Travel charges Freight Other purchase related expenses Energy bill raised by APDCL Sub Total: Less: Capitalised Total: 2014-15 0.35 0.88 0.05 0.00 0.01 0.00 0.65 0.01 0.01 0.63 0.02 6.79 0.00 9.41 0.00 9.41 Note: A&G expenses for FY 14-15 are in actual up to 2nd quarter before any Head quarter adjustment. Regarding 3rd & 4th quarter of FY 14-15 expenses are assumed to be proportionate to the expenses of 1st & 2nd quarter. 15.4.4 Return on Equity Table 52 Particulars Namrup TPS Lakwa TPS Lakwa WHRP Karbi Langpi HEP Myntriang SHEP Namrup RPP Total Particulars Opening Equity Closing Equity Average equity Rate ROE Return on equity calculated as follows:NTPS LTPS KLHEP LWHRP 14-15 14-15 14-15 14-15 64.74 73.19 68.11 70.92 69.44 79.24 68.11 70.92 67.09 76.22 68.11 70.92 0.14 0.14 0.14 0.14 9.39 10.67 9.54 9.93 Equity Base calculated is provided below: 2014-15 9.39 10.67 9.93 9.54 0.86 0.00 40.39 NRPP 14-15 0.00 0.00 0.00 0.14 0.00 Assam Power Generation Corporation Limited Myntriang 14-15 11.27 13.37 12.32 0.14 0.86 Total 14-15 288.22 301.08 294.65 0.14 40.39 Page 198 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 CALCULATION OF COST OF CAPITAL P 2009-10 s ar ul c tI ar Gross Fixed Assets Cost on 01-04-2009 as Audited Accounts 2009-10 2009-10 , 2010-11, 2011-12, 2012-13,2013-14,2014-15 & 2015-16 APGCL STATIONS NTPS LTPS BTPS CTPS KLHEP Lakwa Myntriang NRPP WHRP Total SHEP 212.35 214.68 91.49 34.46 517.11 0.00 0.00 0.00 1070.08 212.35 214.68 91.49 34.46 517.11 0.00 0.00 0.00 1070.08 1.43 24.02 0.02 -117.36 0.00 0.00 0.00 Gross Approved Fixed Asset as on 01-04-2009 Gross Fixed Assets Cost on 01-04-2010 as per Audited Accounts Additions during the F.Y. 2009-10 2010-11 Deductions during the FY 2009-10 Adjustment as on 01.04.2010 appeared in Annual accounts 25.48 -117.36 25.85 25.85 Approved Gross Capital Cost as on 01-04-2010 Gross Fixed Assets Cost on 01-04-2011 as per Audited Accounts Additions during the F.Y. 2010-11 213.78 238.71 0.00 34.46 517.11 0.00 0.96 5.98 0.00 1.53 0.17 0.00 0.00 0.00 1004.05 8.63 2011-12 Adjustment as on 01.04.2011 appeared in Annual accounts 0.00 Approved Gross Capital Cost as on 01-04-2011 214.74 244.68 0.00 35.98 0.44 -17.20 0.00 0.00 517.28 0.00 0.00 0.00 1012.69 Gross Fixed Assets Cost on 01-04-2012 as per Audited Accounts Additions during the F.Y. 2011-12 2012-13 Adjustment as on 01.04.2012 appeared in Annual 0.67 295.98 279.90 accounts 0.00 Approved Gross Capital Cost as on 01-04-2012 215.19 227.48 0.00 35.98 0.23 8.24 0.00 0.00 517.95 295.98 0.00 0.00 1292.59 Gross Fixed Assets Cost on 01-04-2013 as per Audited Accounts Additions during the F.Y. 2012-13 2013-14 Deductions during the FY 2012-13 13.44 0.00 21.90 -30.05 -30.05 Adjustment as on 01.04.2013 appeared in Annual accounts 0.00 Approved Gross Capital Cost as on 01-04-2013 215.41 235.72 0.00 35.98 0.38 8.24 0.00 0.00 501.34 295.98 0.00 0.00 1284.44 37.56 46.87 Gross Fixed Assets Cost on 01-04-2014 as per Audited Accounts 2014-15 Additions during the F.Y. 2013-14 0.45 Deductions during the FY 2013-14 0.24 -5.57 -5.57 Approved Gross Capital Cost as on 01-04-2014 215.79 243.96 0.00 35.98 15.67 20.19 0.00 0.00 501.79 290.64 37.56 0.00 1325.73 7.00 44.78 Gross Fixed Assets Cost on 01-04-2015 Additions during the F.Y. 2014-15 2015-16 Deductions during the FY 2014-15 1.92 0.00 0.00 Approved Gross Capital Cost as on 01-04-2015 231.45 264.15 0.00 35.98 20.80 19.12 0.00 0.00 503.72 290.64 44.56 0.00 1370.51 Gross Fixed Assets Cost on 01-04-2015 Additions during the F.Y. 2015-16 2016-17 7.85 1.50 102.72 693.73 845.72 deductions during the F.Y. 2015-16 0.00 Adjustment as on 01.04.2016 0.00 Approved Gross Capital Cost as on 01-04-2016 252.25 283.26 0.00 35.98 511.57 292.14 Assam Power Generation Corporation Limited 147.28 693.73 2216.23 Page 199 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 CALCULATION OF APPROVED EQUITY CAPITAL P ar ul tI c s r a Approved Capital Cost as on 01-04-2009 30% of Appvd. Capital cost Actual Equity Capital apportioned as on 01-042008 vide letter CGM (F & A) dtd 05/12/08 APGCL STATIONS CTPS KLHEP Lakwa Myntrian Namrup Other WHRP g SHEP RPP projects Total 91.49 34.46 517.11 0.00 0.00 0.00 0.00 1070.08 64.41 27.45 10.34 155.13 0.00 0.00 0.00 0.00 321.02 128.54 136.53 81.15 20.49 68.11 0.00 0.00 0.00 21.03 455.86 63.70 64.41 27.45 10.34 68.11 0.00 0.00 0.00 0.00 234.00 213.78 238.71 0.00 34.46 517.11 0.00 0.00 0.00 0.00 1004.05 64.14 71.61 0.00 10.34 155.13 0.00 0.00 0.00 0.00 301.22 128.54 136.53 0.00 20.49 68.11 0.00 0.00 0.00 102.18 455.86 64.14 71.61 0.00 10.34 68.11 0.00 0.00 0.00 0.00 214.19 214.74 244.68 0.00 35.98 517.28 0.00 0.00 0.00 0.00 1012.69 64.42 73.40 0.00 10.80 155.18 0.00 0.00 0.00 0.00 303.81 128.54 136.53 0.00 20.49 68.11 0.00 0.00 0.00 102.18 455.86 64.42 73.40 0.00 10.80 68.11 0.00 0.00 0.00 0.00 216.73 215.19 227.48 0.00 35.98 517.95 295.98 0.00 0.00 0.00 1292.59 64.56 68.24 0.00 10.80 155.39 88.79 0.00 0.00 0.00 387.78 128.54 136.53 0.00 20.49 68.11 70.92 0.00 0.00 31.26 455.86 64.56 68.24 0.00 10.80 68.11 70.92 0.00 0.00 0.00 282.63 215.41 235.72 0.00 35.98 501.34 295.98 0.00 0.00 0.00 1284.44 64.62 70.72 0.00 10.80 150.40 88.79 0.00 0.00 0.00 385.33 128.54 136.53 0.00 20.49 68.11 70.92 0.00 0.00 31.26 455.86 64.62 70.72 0.00 10.80 68.11 70.92 0.00 0.00 0.00 285.16 215.79 243.96 0.00 35.98 501.79 290.64 37.56 0.00 0.00 1325.73 NTPS LTPS BTPS 212.35 214.68 63.70 Revised Equity Capital Cost as on 01-04-2009. Approved Capital Cost as on 01-04-2010 30% of Appvd. Capital cost Actual Equity Capital Equity Capital as on 01-04-2010. Approved Capital Cost as on 01-04-2011 30% of Appvd. Capital cost Actual Equity Capital Approved Equity Capital as on 01-04-2011. Approved Capital Cost as on 01-04-2012 30% of Appvd. Capital cost Actual Equity Capital Equity Capital as on 01-04-2012. Approved Capital Cost as on 01-04-2013 30% of Appvd. Capital cost Actual Equity Capital Equity Capital as on 01-04-2013. Approved Capital Cost as on 01-04-2014 30% of Appvd. Capital cost Actual Equity Capital Equity Capital as on 01-04-2014. Approved Capital Cost as on 01-04-2015 30% of Appvd. Capital cost Actual Equity Capital 64.74 73.19 0.00 10.80 150.54 87.19 11.27 0.00 0.00 397.72 128.54 136.53 0.00 20.49 68.11 70.92 19.56 0.00 11.70 455.86 64.74 73.19 0.00 10.80 68.11 70.92 11.27 0.00 0.00 299.02 231.45 264.15 0.00 35.98 503.72 290.64 44.56 0.00 0.00 1370.51 69.44 79.24 0.00 10.80 151.12 87.19 13.37 0.00 0.00 411.15 128.54 136.53 0.00 20.49 68.11 70.92 25.22 0.00 6.04 455.86 69.44 79.24 0.00 10.80 68.11 70.92 13.37 0.00 0.00 311.87 252.25 283.26 0.00 35.98 511.57 292.14 147.28 693.73 0.00 2216.23 75.68 84.98 0.00 10.80 153.47 87.64 44.19 208.12 0.00 664.87 128.54 136.53 0.00 20.49 68.11 70.92 33.34 208.12 0.00 666.06 75.68 84.98 0.00 10.80 68.11 70.92 33.34 208.12 0.00 551.94 Estimated Equity Capital as on 01-04-2015. Approved Capital Cost as on 01-04-2016 30% of Appvd. Capital cost Actual Equity Capital Estimated Equity Capital as on 01-04-2016. NOTE: (1) Approved Equity Capital as on 01-04-2013 is the actual equity capital as on 01-04-2013 subject to a ceiling of 30% of the Approved Capital cost. Assam Power Generation Corporation Limited Page 200 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 15.4.5 Income from Other Sources Table 53 Particulars Interest on Staff Loans and advance Income from Investment Income from sale of scrap Rebate for timely payment Misc. receipts (except 62.901 & 62.908) Rent from residential building Total: 2014-15 0.00 8.85 0.06 0.79 0.90 0.01 10.60 15.4.6. Depreciation Table 54 Particulars Land & Rights Buildings Hydraulic Other civil works Plant & Machinery Thermal Plant & Machinery Hydel Lines & Cable Network Vehicles Furniture & fixtures Office equipment Roads on land belonging to others Capital spares at generating stations Total (Less) : Depreciation on 90% of the Assets funded by Grants/subsidies Net Total 2014-15 0.00 0.72 4.06 3.12 20.49 4.48 0.99 0.14 -2.56 0.06 0.00 7.43 38.93 -6.12 32.81 Depreciation has been calculated using the schedule as prescribed by the AERC. Analysis of the trial balance under each function head has been carried out and the weighted average rate has been calculated and used for calculation. Depreciation on assets commissioned in a year is charged at the average balance for the year (since they could be commissioned at different date). 15.4.7 Interest & financing charges Table 55 Particulars Interest on loans Other finance charges Sub total Less: Interest capitalised Total 2014-15 52.41 0.05 52.46 -22.85 29.61 Note: 1. Interest on loans & Other Finance Charges calculated for FY 14-15 @ 10.5% on loan outstanding for Loan from Govt. of Assam, @ actual interest rates charged by PFC for Loan up to Dec’14 from PFC and remaining on proportionate assumption. GPF trust is expected to complete in FY 15-16 and hence interest on GPF is claimed from FY 15-16 Assam Power Generation Corporation Limited Page 201 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 15.4.8 Interest on Working Capital Table 56 Particulars One month Fuel Cost One month approved O&M Cost Maintenance Spares Two month Receivables Total Interest @ 14.75% 2014-15 39.79 9.83 12.90 113.99 176.50 26.03 Note: Interest on Normative working capital worked out as per AERC norms 15.4.9 Repayment of Loan (Principal) Table 57 Particulars PFC Loan State Govt Loan Total 2014-15 22.97 11.07 34.03 15.4.10. Fuel Cost Table 58 Rs. In Cr. Particulars 2014-15 Namrup TPS 194.13 Lakwa TPS 283.33 Total 477.45 16. Profit & Loss Account Table 59 Particulars Power Generation Energy generated (MU) Sale of Power (MU) Auxiliary Consumption, Loss % INCOME Revenue from tariff & Misc. charges O&M expenses of CTPS EXPENDITURE Generation Cost R&M Expenses Employee Expenses A&G Expenses Depreciation Interest & Finance Charges Less: Interest & other expenses capitalised Interest on working Capital Other Debits (incl. Prov. for bad debts, int of W/Capital etc.) Extraordinary Items Assam Power Generation Corporation Limited 2014-15 1894.66 1778.73 6.12% 618.38 0.00 477.45 25.19 86.54 9.41 32.81 52.46 -22.85 26.03 0.00 0.00 Page 202 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Other (Misc.) - net prior period credit Total ROE Other Income Provision for taxes Annual Revenue Requirement Surplus(+) / Shortfall(-) 17. 0.00 687.04 40.39 10.60 0.93 717.76 -99.38 Balance Sheet Table 60 Particulars 2014-15 Source of Fund Share Capital Reserve & Surplus Loans from State Govt Loans from others Total Contributions, grants & subsidies towards cost of Capital Asset Grand Total Application of Fund Net Fixed Assets (A) Gross Block (B) Less : Accumulated Depreciation (C) Net Fixed Assets (D) Capital-works-in-progress Total of (C) to (D) Investements Subsidy receivable from Govt Net Current Assets A. Current Assets, Loans & Advances i) Inventories ii) Receivables against Sale of Power iii) Cash & Bank Balance iv) Loans & Advances v) Other current assets Total of A B. Current Liabilities and provisions i) Borrowing for Working Capital ii) Payment due on Capital Libilities iii) Other current liabilities Total of B Net Current Assets (A - B) Profit/ Loss Grand Total 455.86 43.60 172.46 405.49 1077.42 407.54 1484.95 1370.51 659.19 711.32 621.60 1332.92 0.00 81.90 4.13 184.91 68.88 91.48 431.30 406.26 406.26 25.04 127.00 1484.96 Station wise information for claiming Revised ARR for 2014-15 are depicted in Annexure-IV (Page No. 148) Assam Power Generation Corporation Limited Page 203 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 18. Proposed Revised ARR for 2014-15: Table 61 (Rs in crore) Particulars NTPS LWHRP LTPS 2014-15 (LTPS + CTPS LWHRP) KLHEP Myntriang Total 591.66 34.07 557.60 215.03 19.92 195.11 720.27 60.09 660.18 935.30 80.01 855.30 0.00 0.00 0.00 366.98 1.83 365.15 0.71 0.01 0.70 1894.66 115.92 1778.73 32.30 2.30 8.78 0.72 28.19 15.45 36.97 16.17 3.18 0.00 13.46 6.69 0.63 0.03 86.54 25.19 2.65 2.07 9.19 0.31 2.53 0.00 9.39 -3.68 57.05 0.44 14.04 1.44 0.00 10.90 0.00 9.93 0.00 46.25 3.46 3.04 13.23 0.31 11.61 0.00 10.67 -3.69 82.28 3.90 17.08 14.68 0.31 22.51 0.00 20.60 -3.69 128.53 0.02 0.05 0.00 0.00 0.00 0.00 0.00 0.00 3.24 2.75 10.10 2.10 0.31 8.67 0.00 9.54 -3.23 50.38 0.09 0.32 0.07 0.00 -0.90 0.00 0.86 0.00 1.11 9.41 29.61 26.03 0.93 32.81 0.00 40.39 -10.60 240.31 (B) Fuel Cost 194.13 0.00 (C) ARR (A) + (B) 251.18 46.25 Fixed Cost Paise / Kwh (sent out) 102.32 237.06 Fuel Cost Paise/ Kwh (sent out) 348.15 0.00 Tariff Paise/ Kwh (sent out) 450.47 237.06 (D) Revenue from Sale of Power for FY 2014-15 (E) Surplus/Deficit (C)-(D) 283.33 365.60 124.63 429.16 553.79 283.33 411.86 150.28 331.26 481.54 0.00 3.24 0.00 50.38 137.97 0.00 137.97 0.00 1.11 1586.77 0.00 1586.77 477.45 717.76 135.10 268.42 403.52 618.38 -99.38 Gross Generation (MU) Aux. Power Consumption (MU) Net Generation (MU) Fixed Charges Operation & Maintenance Employee Cost Repairs & Maintenance Administrative & General Expenses Interest & Finance Charge Interest on working Capital Taxes on income Depreciation Provision for Bad & Doubtful Debts Return on Equity Less: Other Income (A)Total Fixed Charges Note: The Secondary Energy Charges will be computed as per the variable charge of AGBPP, NEEPCO as per CERC Tariff Order 2009-14 which is the lowest in the NE region Assam Power Generation Corporation Limited Page 204 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 201516 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Annexure V Statements of proposed Monthly Generation, Deviations comparing with Target of 2014-15 and Actual / Projected Cost of Fuel for FY 2014-15 Assam Power Generation Corporation Limited Page 205 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 GENERATION OF APGCL: 2014-15 Total Latest Revised Fuel Cost (Rs. In Cr.) 46.84 2.80 44.05 591.66 34.07 557.60 194.13 64.81 5.09 57.23 4.97 720.27 60.09 63.89 59.72 52.26 660.18 21.02 1.82 19.21 85.48 6.75 78.73 18.63 1.77 16.86 88.06 7.31 80.75 18.19 1.65 16.54 83.00 6.74 76.26 17.92 1.29 16.63 75.15 6.26 68.89 215.03 19.92 195.11 935.30 80.01 855.30 32.06 0.16 31.90 21.91 0.11 21.80 17.87 0.09 17.78 12.09 0.06 12.03 10.74 0.05 10.68 366.98 1.83 365.15 0.00 0.214 0.002 0.213 0.009 0.001 0.007 0.017 0.001 0.016 0.000 0.000 0.000 0.000 0.000 0.000 0.102 0.001 0.101 0.71 0.01 0.70 0.00 200.15 10.43 189.72 148.75 8.73 140.02 159.10 9.94 149.17 156.40 10.38 146.03 137.98 9.22 128.76 132.83 9.12 123.72 1894.66 115.92 1778.73 Actual STATION 119.5 MW Namrup TPS Gross Gen. (MU) Aux. Cons. @5.8% Net Gen. (MU) 157.2 MW Lakwa TPS LTPS GT Gross Gen. (MU) LTPS GT APC 8.3%(MU) LTPS GT Net Gen. (MU) Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 50.66 2.75 47.91 50.19 2.79 47.40 48.96 2.56 46.40 49.65 2.88 46.78 53.00 2.93 50.07 50.75 2.96 47.79 50.98 3.20 47.78 45.57 2.73 42.83 51.70 3.08 48.62 50.47 2.98 47.49 42.89 2.42 40.47 56.26 4.97 63.01 5.81 55.63 4.83 57.88 4.69 57.16 5.13 54.36 4.80 64.40 5.08 55.65 4.24 64.45 4.93 69.44 5.55 51.29 57.20 50.80 53.19 52.02 49.56 59.32 51.41 59.52 19.50 1.80 17.70 82.51 7.61 74.90 16.58 1.66 14.92 72.21 6.49 65.72 12.83 1.41 11.42 70.70 6.10 64.60 18.33 1.73 16.60 75.49 6.86 68.63 16.42 1.67 14.74 70.78 6.47 64.30 20.73 1.83 18.90 85.13 6.91 78.22 15.46 1.59 13.87 71.11 5.83 65.28 18.97 0.09 18.87 27.76 0.14 27.62 39.78 0.20 39.58 50.85 0.25 50.60 63.49 0.32 63.18 63.83 0.32 63.51 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.368 0.007 0.361 0.000 0.000 0.000 151.67 10.49 141.17 148.93 9.19 139.74 160.13 9.17 150.96 179.71 10.05 169.65 185.02 9.75 175.27 WHRU Gross Gen. (MU) 19.43 WHRU Aux. Cons. 9.3%(MU) 1.70 WHRU Net Gen. (MU) 17.72 LTPS Gross Gen. (MU) with WHRU 75.69 Total Aux. Cons. 8.6%with WHRU 6.68 LTPS Net Gen. (MU) with WHRU 69.01 100 MW Karbi Langpi HEP Gross Gen. (MU) 7.64 Aux. Cons. @ 0.5 % 0.04 Net Gen. (MU) 7.60 Myntriang Small HEP - Stage II (3 MW)* Gross Gen. (MU) 0.000 Aux. Cons. @ 1.7% 0.000 Net Gen. (MU) 0.000 APGCL Gross Gen. (MU) 133.99 Aux. Cons. @6.1% 9.47 Net Gen. (MU) 124.52 283.33 477.45 *Myntriang St-II generation has been considered from the COD of 08-08-14 Assam Power Generation Corporation Limited Page 206 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 Deviations comparing with Target and Actual Generation for FY 2014-15 Power Station Item NTPS LTPS with WHU KLHEP Myntriag SHEP, StII APGCL Target of 14-15 Actual/Projected Generation for 14-15 Surplus (+)/ Deviation (-) Target of 14-15 Actual/Projected Generation for 14-15 Surplus (+)/ Deviation (-) Target of 14-15 Actual/Projected Generation for 14-15 Surplus (+)/ Deviation (-) Target of 14-15 Actual/Projected Generation for 14-15 Surplus (+)/ Deviation (-) Target of 14-15 Actual/Projected Generation for 14-15 Surplus (+)/ Deviation (-) 43.48 44.93 44.93 40.58 44.93 53.00 37.70 44.93 Actual 50.75 50.98 Total 2014-15 523.09 45.57 51.70 50.47 42.89 46.84 591.66 4.72 8.07 13.05 6.05 2.09 6.77 5.54 2.31 1.91 68.58 67.11 69.34 69.34 73.96 76.11 76.42 69.03 73.29 842.47 82.51 72.21 70.70 75.49 66.79 69.34 Actual 70.78 85.13 71.11 85.48 88.06 83.00 75.15 935.30 8.59 17.86 5.10 1.36 6.15 3.98 15.79 -2.85 9.37 11.64 13.97 1.86 92.83 9.00 19.00 45.00 68.00 74.00 21.00 15.00 11.00 5.00 6.00 390.00 7.64 18.97 27.76 39.78 50.85 72.00 45.00 Actual 63.49 63.83 32.06 21.91 17.87 12.09 10.74 366.98 -1.36 -0.03 -17.24 -28.22 -23.15 -8.51 11.06 6.91 6.87 7.09 4.74 -23.02 0.00 0.00 0.00 0.00 0.37 1.94 1.95 1.46 1.17 1.18 11.38 0.00 0.00 0.00 0.00 0.37 1.30 2.01 Actual 0.00 0.21 0.01 0.02 0.00 0.00 0.10 0.71 0.00 0.00 0.00 0.00 0.00 -1.30 -1.94 -1.93 -1.46 -1.17 -1.08 -10.67 119.59 128.57 155.43 182.27 188.64 140.38 137.99 133.82 115.78 125.40 1766.94 133.99 151.67 148.93 160.13 179.71 177.79 161.28 Actual 185.02 200.15 148.75 159.10 156.40 137.98 132.83 1894.66 14.40 23.09 -6.50 -22.14 -8.93 8.37 21.11 22.59 22.20 7.43 127.72 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 43.48 44.93 43.32 44.93 44.93 50.66 50.19 48.96 49.65 7.18 5.26 5.64 67.11 64.64 75.69 7.23 18.83 -1.79 38.87 Note: 1. Reduced generation of KLHEP is due to less rain fall in the monsoon season. 2. Myntriang St-II SHEP generation reduced as t he plant got affected by heavy flood on 22-08-14. All the equipments needed servicing. At present both the units are under forced shutdown. Assam Power Generation Corporation Limited Page 207 of 228 Petition for Approval for Revised ARR and Determination of Generation Tariff for the FY 2015-16 and Truing-Up for FY 2013-14 and APR for FY 2014-15 ACUAL/PROJECTED FUEL COST OF APGCL: 2014-15 Actual Projected Fuel Cost for FY 2014-15 (LTPS) Month Apr-14 Qty (MMSCM) Amount (Rs. in Cr) May-14 Jun-14 Jul-14 Aug-14 Sep-14 GAIL Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Total Mar-15 10.54 12.47 11.41 12.40 13.20 11.16 14.73 10.52 10.70 11.65 11.21 10.99 140.97 6.51 7.75 6.90 7.70 8.45 7.34 10.27 9.25 9.35 10.87 10.71 9.89 104.99 10.82 11.31 11.86 16.32 14.65 20.39 15.39 21.93 13.70 19.08 12.25 17.34 147.89 178.34 21.59 25.56 29.74 32.80 29.79 27.24 283.33 Qty (MMSCM) Amount (Rs. in Cr) 13.04 13.78 Total Amount (Rs. in Cr) 20.29 13.73 11.39 11.55 10.92 11.56 AGCL 9.79 10.59 10.28 11.07 21.47 18.45 19.26 18.73 20.54 19.98 18.29 19.93 251.70 18.40 48.13 18.29 51.09 16.51 46.30 18.33 45.57 194.13 477.45 13.49 18.41 Qty (MMSCM) 22.49 23.33 Fuel Cost for FY 2014-15 (MMSCM) (NTPS) 21.31 22.13 21.73 21.05 21.14 19.76 Amount (Rs. in Cr) Total APGCL 15.64 35.93 16.01 37.49 14.11 32.56 15.61 34.87 14.97 33.71 14.36 32.77 14.44 36.02 17.46 43.02 Note: 1. GOI revised the gas price of non-APM gas from earlier $4.2/MMBTU on NCV basis to $5.05/MMBTU on GCV basis w.e.f 1 st November 2014. 2. APM gas price was revised to $3.03/MMBTU on GCV from earlier $2.52/MMBTU on NCV from 1 st November 2014 Assam Power Generation Corporation Limited Page 208 of 228 Annex- VI ` AUDITED ANNUAL ACCOUNTS FOR FY 2013-14 ASSAM POWER GENERATION CORPORATION LIMITED Assam Power Generation Corporation Limited Page 209 of 228 ASSAM POWER GENERATION CORPORATION LIMITED BALANCE SHEET AS AT 31st MARCH, 2014 Particulars Note I.EQUITY & LIABILITES (A) Shareholder's Funds (a) Share Capital (c) Reserves and Surplus (B) Share Application Money (Pending Allotment) C. Non Current Liabilites (a) Long Term Borrowings (b) Differed Tax Liabilites (Net) (c) Other Long Term Liabilites (d) Long Term Provisions D. Current Liabilites (a) Short Term Borrowings (b) Trade Payables (c) Other Current Liabilites (d) Short Term Provisions Rupees in lakh 1 2 3 4 5 6 7 8 9 10 Total :: II. ASSETS (A) Non-Current Assets (a)Fixed Assets (i) Tangible Assets (ii) Intangible Assets (iii) Capital Work-In-Progress (iv) Intangible Assets Under Development (b) Non Current Investment (c) Differed Tax Assets (Net) (d) Long Term Loans & Advances (e) Others Non Current Assets (B) Current Assets (a) Current Investment (b) Inventories (c) Trade Receivable (d) Cash & Cash Equivalents (e) Short Term Loans & Advances (f) Others Current Assets As on 31st March 2014 As on 31st March 2013 45,585.98 20,737.33 53,387.87 739.37 3,633.47 16,748.92 15,147.11 6,795.39 162,775.44 45,585.98 31,260.51 48,419.89 739.37 3,045.20 12,790.75 15,229.39 7,556.88 164,627.97 69,935.92 56,898.33 - 68,673.47 56,593.29 - 6,825.08 344.10 15,408.79 5,739.80 7,623.42 162,775.44 5,822.61 9,485.66 11,763.97 5,651.37 6,637.60 164,627.97 11 12 13 14 15 16 17 18 19 20 Total :: Notes forming part of the Consolidated Financial Statements 1 - 41 Assam Power Generation Corporation Limited Page 210 of 228 ASSAM POWER GENERATION CORPORATION LIMITED STATEMENT OF PROFIT & LOSS ACCOUNT FOR THE YEAR ENDED 31.3.2014 st Particulars I.INCOME (a) Revenue From Operations (b) Other Income (c) Other Receipts Total Revenue :: II.EXPENDITURE (a) A. Cost of Materials Consumed (a) B. Cost of Materials Consumed (Lubricant) (b) Employee Benifites Expenses Losses relating to fixed assets (c) Finance Costs (d) Depriciation and Amortization Expenses (e) (i) Other Expenses (ii) Other Expenses - Prior period items As on 31 March 2013 (Rupees in lakh) 21 22 23 54,705.14 1,054.59 1,900.00 57,659.73 45,967.81 1,373.70 47,341.51 24 38,535.78 122.90 8,199.64 4,396.27 2,867.72 3,713.43 8,415.18 36,454.49 96.17 7,211.53 4,252.22 3,786.82 2,600.94 (6,502.12) 66,250.92 (8,591.19) (8,591.19) 47,900.05 (558.54) (558.54) 45.14 45.14 (8,636.33) 49.87 49.87 (608.41) (18.95) (1.33) Notes 25 26 27 (i) 27 (ii) Total Expenses :: Profit(Loss) Before Tax (I-II) Exceptional Item Profit(Loss) Before Extra ordinary item and Tax III.TAX EXPENSES (a) Current Tax (i) Income Tax (ii) MAT (iii) Building & other construction workers welfare cess (b) Deferred Tax Profit (Loss) For the Period IV. Earnings per share: (a) Basic (b) Diluted Notes forming part of the Consolidated Financial Statements st As on 31 March 2014 (Rupees in lakh) 28 1 - 41 Assam Power Generation Corporation Limited Page 211 of 228 ASSAM POWER GENERATION CORPORATION LTD. st CASH FLOW STATEMENT FOR THE YEAR ENDED 31 MARCH, 2014 As on 31st March 2014 (Rupees in lakh) As on 31st March 2013 (Rupees in lakh) (8,591.19) 2,867.72 4,396.27 (558.54) 3,477.93 (720.57) 0.30 4,252.22 7,263.99 (1,327.20) 7,009.88 6,451.34 7,064.82 3,114.42 10,179.24 8,852.04 45.14 8,806.90 (2,699.46) (1,280.25) 0.14 (3,979.57) 2,471.77 49.87 2,421.90 (4,130.17) (305.04) (4,435.21) 814.78 (15,236.96) 720.57 (13,701.61) A. CASH FLOW FROM OPERATING ACTIVITIES: Net Profit before Taxation Adjusted for: Tax Provision Deferred Tax Provision Profit/Loss on Sale of Assets Profit/Loss on Sale of Fixed Assets(Net) Profit/Loss on Sale of Current Investments-others Provision for Diminution in Current Investment Depreciation Lease Equalisation Transferred from general Reserve Income from Investment Interest /Other Income Lease Rent written off Capial Work in Progress written off Preliminary Expenses written off Prior Period Expenses Interest Expenses Operating profit before working capital changes Adjusted for : Increase in Current Assets Decrease in Current Liabilities Decrease in Loans & Advances Cash generated from operations Tax expenses Net Cash from Operating Activities B. CASH FLOW FROM INVESTMENT ACTIVITIES : Purchases of Fixed Assets Sale of Fixed Assets Purchase of Investments Sale of Investments Capital Work in Progress Income from Investment Interest/Other Income Net Cash Used in Investment Activities Assam Power Generation Corporation Limited Page 212 of 228 C. CASH FLOW FROM FINANCING ACTIVITIES : Proceeds from Share capital Proceeds from Long Term Borrowings Repayment of Finance Lease Liabilities Dividend Paid Interest paid Reserve & Surplus Net Cash Used in Financing Activities Net Increase/Decrease in Cash and Cash Equivalents (A+B+C) Opening Balance of Cash and Cash Equivalents Closing Balance of Cash and Cash Equivalents 4,967.96 588.28 (4,396.27) (1,886.84) (726.87) 8,577.20 (4,252.22) 9,836.08 14,161.06 3,644.82 2,881.35 11,763.97 15,408.79 8,882.62 11,763.97 NOTES FORMING PART OF THE CONSOLIDATED FINANCIAL STATEMENTS SIGNIFICANT ACCOUNTING POLICIES: 1. Basis of Preparation: The financial Statements have been prepared under the historical cost convention, based on accrual basis of accounting and in accordance with the generally accepted accounting principles and the provision of the Companies Act, 1956. 2. Use of Estimate: The preparation of financial statement in conformity with generally accepted accounting principles requires the management to make estimates and assumptions that affect the reported balances of assets and liabilities as of the date of the financial statement and reported amounts of income & expenses during the reporting period. Management believes that the estimates used in the preparation of financial statement are prudent and reasonable. Difference between the actual result and estimates are recognized in the period in which result are known/ materialized. 3. Inventories: Stock Accounts of the Company maintained for construction project has been treated as “Capital Stores” and that of O& M purpose treated as “Operational Stores”. Materials are issued to works at standard price. Issue of Standard Items is at Standard rates on FIFO basis. For Non-Standard Items receipt accounting is based on Basic Price+E/Duty+Sales Tax. Issue of Non-Standard Items is based on weighted average rate of previous month’s closing balance. If there is no closing stock in the previous month, valuation of issue is based on the first receipt rate of the current month. Shortages found on physical verification of stocks are booked under “Material Shortages pending investigation (Account code 22.8). These shortages are recovered from persons responsible or written off, as the case may be, on completion of investigation. 4. Capital –Work –in-progress: All expenses incurred for acquiring, erecting and commissioning of fixed assets including interest on long term loans utilized for meeting capital expenditure. Capital work in progress includes cost of material purchased, excise duty and other management overheads and are allocated to the fixed assets on the completion of the projects. 5. Operational Performance: The operational performance of the company is detailed in Annexure-A. The gross power generation of the company was 1845.228 MU. The Auxiliary consumption was 112.380 MU. Net power available for sale was 1732.847 MU and the power was sold for an amount of 547.00 crore to APDCL (ASEB). 6.Fixed Assets and Depreciation: a) The Fixed Assets are stated at cost, less accumulated depreciation/ amortization. Costs include all expenses incurred to bring the assets to its present location and condition. b) Depreciation for the period in respect of assets has been provided on straight line method as per Schedule-XIV of Companies Act, 1956. Depreciation on addition of assets has been calculated on pro-rata basis. Assam Power Generation Corporation Limited Page 213 of 228 ASSET Building (Residence) Building (Factory) Hydrulic Other Civil Works Plant & Machinary Lines & Cable Network Vehicles - truck, bus Vehicles - others Furniture & Fixtures Office Equipment Rate of Dep 1.63% 3.34% 4.75% 1.63% 5.28% 5.28% 11.31% 9.50% 6.33% 4.75% METHOD SLM SLM SLM SLM SLM SLM SLM SLM SLM SLM c) The Fixed Assets are depreciated up to 95% of the original cost after taking 5% as the residual value. d) Company’s assets are not subject to any lien. e) The expenditure on capital work-in-progress is transferred to appropriate asset on commissioning of the asset/when first put to use. f) As per the accounting policy followed by the Company, Consumers’ contribution, subsidies and grants towards cost of capital assets have not been reduced from the cost of assets but have been treated as ‘Reserves and Surplus’. However, the depreciation pertaining to fixed assets constructed out of consumer’s contribution, subsidies and grants towards cost of capital assets is charged. 7. Segment Reporting: The company has single business segment namely, “Generation of Electricity”. As regards geographical segment the area that falls under the company is similar in respect of economic and political condition etc. and therefore is not subject to different risk and return. Therefore, the company business doesn’t fall under the different segments as defined in AS 17 of ICAI. 8. Revenue Recognition: Sale of energy is accounted for based Tariff rates approved by AERC. 9. Accounting for Government Grants: Government grants received for capital works are treated as Capital Reserve. Govt. Grants towards cost of capital assets are contribution of the owner (i.e. State Govt.) towards capital of the Company. Fund brought in by the ‘owner’ cannot be construed as meeting a portion of the cost. Hence, in terms of AS-12 Govt. Grants has been treated as capital receipt and taken to Capital Reserve. Grants from ADB, though shown separately in the accounts are grants from the Govt. of Assam, which receives the fund from Central govt., the borrower in terms of the loan agreement with ADB. 10. Accounting for Investments: Investments are carried at cost. All the investment in UTI mutual fund has been redeemed. Investment in fixed deposits represents unutilized capital funds to be deployed for capital expenditure and shown as bank balance. 11. Retirement benefits: th Pursuant to the Transfer Scheme, the GoA vide Notification No.PEL.190/2004/69 dtd.4 February, 2005 notified the plan for meeting the terminal benefit obligations of personnel transferred from ASEB to successor entities. As per Clause 1.5 of the said notification “Terminal Benefit” means the ASEB’s employee related liabilities including payments of pension, gratuity, leave encashment and General Provident Fund and any other retirement benefits and applicable benefits including right to appropriate revisions in the above benefits consistent with the practice that were prevalent in ASEB: (A) Funding for past unfunded terminal liabilities is on the basis of actuarial valuation done as at th 30 September, 2012. The cash outflows towards past unfunded liabilities of existing employees, existing pensioners and existing family pensioners funded pattern will be guided by the aforesaid Govt. notification. (B) Funding for future services-Terminal Benefits: The company has made a provision for terminal liability for future service of its existing employees Assam Power Generation Corporation Limited Page 214 of 228 @23.31% of Basic plus DA as per AERC guidelines and in the line with the GoA’s Notification mentioned above. (C) Leave Encashment Benefit (LEB) of employees: Leave encashment benefit of the old employees are accounted on cash basis. LEB admissible to the employees are being paid by the Company and claim for recovery of the appropriate share of such fund (i.e. share of past liability) relating to period prior to 9.12.2004 is forwarded to the Pension Trust Authority as per GoA Notification mentioned here-in-above. (D) GPF deductions/payments of employees: Payments on account of GPF (Final Withdrawal and Non-refundable advance) to the existing employees are being made from the GPF Account of the Company. Claim for recovery of appropriate share of such fund (i.e. share of past unfunded liability) is forwarded to the Pension Trust authority as per GoA Notification mentioned above. Provision for interest on GPF is on the basis of average rate of 8.70 % applied on the average subscription of the employee. (E) Terminal benefit for new (appointed on or after 1.1.2004) employees: New Pension Scheme is being implemented for the new employees of the Company as per Government of India Notification No.5/7/2003-ECB & PR dated. 22.12.2003. The Company contributed the equal amount deducted from its employees, fall under New Pension Scheme. 12. Accounting for Borrowing Costs: Borrowing costs attributable to acquisition/construction or production of qualifying assets are capitalized as part of cost of such assets. A qualifying asset is an asset that necessarily takes a substantial period of time to get ready for its intended use or sale. Other borrowing costs are recognized as an expense in the period in which they are incurred. 13. Provision for Taxation: Provision for current tax is measured at the amount expected to be paid to the tax authorities, using the applicable rate and tax laws. 14. Repayment of Loans: No amount is being reserved for repayment of loan. However, repayments of loan, redemption of bonds and interest has been paid duly, except the GoA Loan. 15. Impairment of Assets: As per AS-28, an asset is treated as impaired when the carrying cost of assets exceeds its recoverable value. An Impairment Loss is charged to Profit & Loss A/c in the year in which the asset is identified as impaired. The Impairment Loss recognized in prior accounting periods is reversed if there has been a change in the estimate of recoverable amount. 16. Contingent Liabilities: Contingent liabilities are disclosed in respect of present possible obligation that arise from past events but their existence is confirmed by the occurrence or non-occurrence of one or more uncertain future events not wholly within the control of the Company. 17. Disclosures vide notification No.GSR 719(E) of Ministry of Corporate Affairs dated 1611-07: Outstanding amount to fuel suppliers of APGCL as on 31-03-14 in rupees crore is as tabulated below – Supplier OIL GAIL AGCL Outstanding principal Outstanding interest Total (in Rupees) 139.33 12.37 14.65 0.87 0.29 140.20 12.66 14.65 There are no suppliers in APGCL who fall under Micro, Small & Medium Enterprises Development Act, 2006. 18. Miscellaneous: i.Expenses incurred in raising of finance are being charged to revenue in the year in which these are incurred. Assam Power Generation Corporation Limited Page 215 of 228 ii.Interest on loans and advances to staff is recovered on completion of recovery of principal amount. ASSAM POWER GENERATION CORPORATION LIMITED Notes forming part of the Consolidated Financial Statements The Previous Year Figures have been regrouped/ reclassified,wherever necessary to conform to the current year presentation. 1. SHARE CAPITAL Particulars Authorised Shares Capital 100000000 equity share of 100 each Account codes As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 100,000.00 100,000.00 Issued, Subscribed and paid up 59.101 (i) 45585975 equity share of Rs 100/- each fully paid up 45,585.98 (Previous Year 5008 equity share of Rs 100/- each fully paid up) Total 45,585.98 1.1 45585975 ( 5008) Shares out of the issued , subscrided and paid up Shares Capital were allotted as fully paid up pursuant to transfer scheme without payment being received in cash. 1.2 the Details of Shareholders holding more than 5% Shares Name of the Shareholder As on 31-03-2014 No of Shares Governor of Assam 45585967 One number of share of Rs.100/- each by Shri S.Das, Shri S.Abbasi, Shri S.K.Handique, Shri S.Kar, Smti.K.Baruah, Shri A.C.Baruah, Shri S.K.Saha, Shri K.Patowali 8 % Held 45,585.98 45,585.98 As on 31-03-2013 No of Shares % 99.99998 99.99998 0.00002 0.00002 As on 31-03-2014 As on 31-03-2013 1.3 The Reconcillation of the number of shares outstanding is set out below : Account codes Particulars Equtity Shares at the beginning of the year Add: Shares Issued During the Year Equity Shares At the End of the Year 45585975 0 45585975 4558597 0 45585975 2. RESERVES AND SURPLUS Account codes Particulars General Reserves Capital Reserves 55.300 Profit & Loss Account Profit (Loss) as per last Balance Sheet Profit (Loss) for the year Total 2.1 Capital reserve includes:(a) Grant towards cost of Capital Assets (for WIP) (b) Donated Capital Assets (c) ADB Grant (for WIP) (d) GoA Grant (from NABARD for CWIP of Myntriang SHEP) Assam Power Generation Corporation Limited As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 38,038.15 39,924.99 (8,664.48) (8,636.33) (17,300.82) 20,737.33 (8,056.07) (608.41) (8,664.48) 31,260.51 As on 31-03-2014 (in Rs) 3,253,770,000 108,447,500 13,155,545 428,442,000 As on 31-03-2013 (in Rs) 3,575,770,000 108,447,500 11,839,991 428,442,000 Page 216 of 228 3. Shares Application Money Pending Allotment Account codes Particulars Capital of Assam State Electricity Board apportioned to the company as per notification of the Government of Assam which is pending allotment As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 59.102 0.00 0.00 Total 0.00 0.00 4. Long Term Borrowings Account codes Particulars As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) SECURED 52.111 Loans from PFC Total 33,351.33 33,351.33 30,648.00 30,648.00 0.00 13,578.01 6,408.40 50.13 20,036.54 13.16 11,720.97 5,975.22 62.54 17,771.89 UNSECURED Loans from ADB 52.112 State Govt. Loan 54.100 GPF 57.120 Staff Pension Fund (DCP) Total 4.1 Loan from PFC is secured against the assets created out of it. 4.2 Loan from State Govt. includes Rs.65,64,99,696/- as repayment due. 4.3 During the year Rs.50.00 crore loan was drawn from PFC against NRPP project. 5. OTHER LONG TERM LIABILITES Account As on 31-03-2014 As on 31-03-2013 Particulars codes (Rupees in lakh) (Rupees in lakh) Trade payable Liabilities to railways for Coal receipt 40.100 739.37 739.37 Total 739.37 739.37 5.1 Reconciliation with railways for settlement of dues is under progress & the process may take few more time. 6.LONG TERM PROVISION Particulars Provision For Employees Benefits Provision For Employees Benefits Others Provision for doubtful loans and advances Total Account codes 46.922 As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 3,633.47 3,045.20 0.00 3,633.47 0.00 3,045.20 7.SHORT TERM BORROWINGS Particulars Account codes As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) SECURED 0.00 0.00 0.00 0.00 0.00 0.00 UNSECURED Total Assam Power Generation Corporation Limited Page 217 of 228 8.TRADE PAYABLE Account codes Particulars As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) Micro Small And Medium Enterprises Others Liabilities for Supply of Gas Total 40.500 16,748.92 16,748.92 12,790.75 12,790.75 As on 31-03-2014 (Rupees in lakh) 0.00 8,980.78 As on 31-03-2013 (Rupees in lakh) 9.54 9,089.35 9.OTHERS CURRENT LIABILITES Particulars Interest accrued but not due on Borrowings Interest accrued and due on Borrowings Other Payables Liabilities for capital supplies /works Liabilities for supplies/works(O&M) Other Liabilities Advance (to) /from AEGCL Total 9.1 Interest accrued and due on borrowings includes Account codes 51.203 51.204 42.1-42.6 43.1-43.6 46.900 45.704 3,283.10 697.76 2,187.26 (1.79) 15,147.11 (a) State Govt Loan Rs.82,45,50,341/(b) PFC Loan Rs.7,35,28,009/- 2,919.24 730.49 2,482.56 (1.79) 15,229.39 10.SHORT TERM PROVISION Particulars Provision For Employes Benefits Salaries, wages, bonous Employees' contribution & recoveries Others Deposits and retention from suppliers and contractors Provision for Liability for Expenses Liability for Pension Provision of Audit Fees Provision for Building & other Construction workers welfare cess Provision for Minimum Alternate Tax Account codes As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 44.300 44.400 807.67 150.52 958.19 704.65 132.85 837.50 46.100 46.400 46.500 46.805 46.803 46.802 5,089.37 654.68 90.30 2.40 0.46 0.00 5,837.21 6,795.40 4,789.22 1,713.01 41.11 2.40 173.64 0.00 6,719.38 7,556.88 Total Assam Power Generation Corporation Limited Page 218 of 228 ASSAM POWER GENERATION CORPORATION LIMITED 11.FIXED ASSETS A/c Code As at 1.4.2013 Description GROSS BLOCK DEPRECIATION Adjustment Additions Deductions as at during the during the 1.4.2013 year year Adjustment Deduction as at Depreciation during the 1.4.2013 for the year year As at 31.3.2014 As at 1.4.2013 NET BLOCK As at 31.3.2014 As at 31.3.2014 As at 31.3.2013 2,283.39 5,136.59 5,816.90 34,222.53 2,759.29 85.89 91.48 68.10 2,079.19 2,193.51 12,184.27 13,038.75 33,492.25 1,688.26 38.28 44.72 39.75 2,079.19 2,248.98 11,359.43 16,694.55 33,094.08 2,839.59 9.14 42.77 29.25 0.50 27.74 27.99 5,109.19 248.50 69,935.91 68,673.47 68,673.47 72,966.18 56,898.33 56,593.29 TANGIBLE ASSETS OWN ASSETS 10.1 10.2 10.3 10.4 10.5 10.6 10.7 10.8 10.9 Land & Rights Building Hydraulic Other Civil Works Plant & Machinery Lines & Cable Network Vehicles Furniture & Fixtures Office Equipemnt Roads on land 11.1 belonging to others Capital spares at 11.3 Generating Stations Total Previous Year 2,079.19 4,445.63 15,742.50 18,463.06 65,354.14 4,414.57 124.17 412.65 97.07 281.77 (281.77) - 557.12 - 28.24 - - - 17,282.56 - - - 128,443.78 129,258.56 - CAPITAL WORK IN PROGRESS ASSET Building (Residence) Building (Factory) Hydrulic Other Civil Works Plant & Machinary Lines & Cable Network Vehicles - truck, bus Vehicles - others Furniture & Fixtures Office Equipemnt 31.27 1,578.36 392.59 2,635.99 32.98 5.32 10.78 Rate of Dep 1.63% 3.34% 4.75% 1.63% 5.28% 5.28% 11.31% 9.50% 6.33% 4.75% 4,687.29 2,190.31 557.12 3,005.09 2,079.19 4,476.90 17,320.86 18,855.65 67,714.78 4,447.55 124.17 136.20 107.85 28.24 17,282.56 132,573.95 128,443.78 2,196.65 4,383.07 1,768.51 32,260.06 1,574.98 115.03 369.88 67.82 0.25 17,034.06 59,770.31 56,292.38 3,847.00 324.84 1,163.01 (35.69) (281.80) (8.42) (5,008.94) - 86.74 753.52 201.39 1,637.63 21.30 6.55 3.40 8.70 - 0.25 - 148.25 - 2,867.73 3,786.82 308.89 12,173.37 62,638.04 59,770.31 METHOD SLM SLM SLM SLM SLM SLM SLM SLM SLM SLM Note:- (i) In the absence of shift log book for Plant & Machinary, depreciation on Plant & Machinary has Power been charged on continued Corporation process plant basis.Limited Assam Generation (ii) On fixed assets accuired during the year depreciation is charged on 'Put to Use' basis. Page 219 of 228 12. NON CURRENT INVESTMENT Particulars Trade Investment Others Investment Total Account codes As on 31-03-2014 (Rupees in lakh) 0.00 0.00 0.00 As on 31-03-2013 (Rupees in lakh) 0.00 0.00 0.00 Account codes As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 13.LONG TERM LOANS & ADVANCES Particulars Others Loans & Advances Security Deposits from consumers Total 48.100 & 48.200 0.00 0.00 0.00 0.00 14.OTHERS NON CURRENT ASSETS Account codes Particulars Others Prelimenary Expenses Total 17.300 As on 31-03-2014 (Rupees in lakh) 0.00 0.00 As on 31-03-2013 (Rupees in lakh) 0.00 0.00 15. CURRENT INVESTMENT Account codes Particulars As on 31-03-2014 (Rupees in lakh) 0.00 0.00 Investment in Equity Instruments Total As on 31-03-2013 (Rupees in lakh) 0.00 0.00 16. INVENTORIES Account codes Particulars 1. Capital Stores and Spares Fuel Stock Capital Materials Stock A/c 2. O&M Materials Stock A/c 3. Materials Stock Adjustments (Capital) Other Material Account Material stock-Excess/Shortage pending investigation - Capital Less Provision against Stock Net Total 21.101/125 22.601 22.602 22.501 22.700 22.800 46.920 As on 31-03-2014 (Rupees in lakh) 10.71 6,862.72 2,766.51 0.00 358.10 30.10 (3,203.05) 6,825.09 As on 31-03-2013 (Rupees in lakh) 7.41 7,393.76 1,318.22 0.00 276.17 30.10 (3,203.05) 5,822.61 17. TRADE RECEIVABLES Particulars Receivables against sale of power - APDCL Account codes 23.101 Total Assam Power Generation Corporation Limited As on 31-03-2014 (Rupees in lakh) 344.10 As on 31-03-2013 (Rupees in lakh) 9,485.66 344.10 9,485.66 Page 220 of 228 18. CASH & CASH EQUIVALENTS Account codes Particulars As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 696.87 61.13 14,650.79 Balances With Bank Cash In Hand Fixed Deposits with Banks 1,110.10 65.34 10,588.53 Total 15,408.79 18.1 Balances with bank includes closing bank balance of HQ as well as of all field units along with the fund in transit. 18.2 Fixed Deposits with Banks includes closing balance of fixed deposit at various banks. 11,763.97 19. SHORT TERM LOANS & ADVANCES Particulars (Unsecured & Considered Good) Advances for O&M supplies/works Loans and advances to staff Advance Tax/Income Tax deducted at source Account codes 26.1 to 26.8 27.1 & 27.2 27.400 Total As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 5,778.85 (39.05) 0.00 5,647.36 4.01 0.00 5,739.80 5,651.37 20. OTHER CURRENT ASSETS Account codes Particulars Interest Accrued on Investment Advance to suppliers (Capital ) Interest bearing Interest free Advance to contractors (Capital ) Advance to Capital Contractors - Interest Free Contractors materials control Account (capital) Income Accrued but not Due Fuel Related Receivables & Claims { Railway claims for Coal} Other Receivables Prepaid expenses Deposits(except (28.907) As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 25.100 25.500 0.00 1,345.78 0.00 1,454.48 25.600 25.700 6.12 0.00 6.12 0.00 28.300 28.500 28.800 752.94 747.91 4,753.21 0.00 0.55 442.12 747.91 3,902.26 77.46 0.55 28.900 Inter Unit A/c - Capital Expenditure & Fixed Assets 32.000 0.00 (1.92) Inter Unit A/c - Remittance to HQ 33.000 15.80 7.50 Inter Unit A/c - Opening Balance 36.802 1.11 1.11 Total 7,623.42 6,637.59 20.1 Other recivable includes proportion of unfunded liabilities to be received from the Pension Trust on account of GPF & LEB payment. Assam Power Generation Corporation Limited Page 221 of 228 21. REVENUE FROM OPERATIONS Account codes Particulars Sale of Power (ASEB) 61.101 Sale of scrap Total As on 31-03-2014 (Rupees in lakh) 54,699.58 5.56 54,705.14 As on 31-03-2013 (Rupees in lakh) 45,965.83 1.98 45,967.81 22. OTHER INCOME Account codes Particulars As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) Interest Interest on House Building Advances to Staff Interest on Investment (Fixed Deposit) 62.211 62.221 0.03 880.57 0.03 605.81 Dividend Dividend gain on investment in UTI mutual fund 62.222 0.00 114.76 62.273 62.361 62.900 62.901 4.26 78.91 0.00 89.56 1.26 1,054.59 0.00 58.62 9.63 583.71 1.14 1,373.70 Other Non Operating Income Interest from Banks (other than interest on fixed deposits) Rebate received for timely payment of dues of loans, interest, etc. Rebate for timely payment Misc.receipts (except 62.901 &62.908) Rentals from staff quarters Total * Interest on FD is calculated as closing balance of FD. 23. OTHER RECEIPTS Account codes Particulars As on 31-03-2014 (Rupees in lakh) 1,900.00 1,900.00 Revenue grant received Total As on 31-03-2013 (Rupees in lakh) 0.00 0.00 24.COST OF MATERIALS CONSUMED Particulars Indigenous Gas Gas/Oil (Internal Combustion) Lubricants and cunsumable stores Total Account codes 71.130 71.140 to 71.600 As on 31-03-2014 (Rupees in lakh) 2,985.80 35,549.98 122.90 38,658.68 As on 31-03-2013 (Rupees in lakh) 382.17 36,072.32 96.17 36,550.66 25. EMPLOYEE BENEFITS EXPENSES Particulars Salaries and Wages Salaries Overtime Dearness Allowance Account codes 75.100 75.200 75.300 Assam Power Generation Corporation Limited As on 31-03-2014 (Rupees in lakh) 3,380.68 143.72 2,712.21 Page 222 of 228 As on 31-03-2013 (Rupees in lakh) 3,349.31 63.01 2,195.02 Other Allowances Bonus Sub Total 75.400 75.500 Less:-Employees cost capitalised Salaries and Wages 75.900 Contribution to Provident and Other Funds Medical expenses reimbursement Leave travel concession (L.T.C) Earned leave encashment. Other Staff Cost Staff Welfare Staff Welfare Expenses 75.800 75.611 75.612 75.617 75.630 to 75.649 75.700 692.70 2.88 6,932.19 0.00 6,932.19 636.83 2.22 6,246.38 211.79 6,034.59 1,204.34 17.42 4.51 27.57 0.65 12.96 1,112.05 18.47 4.20 18.81 2.08 21.33 63.11 8,199.64 TOTAL: 64.89 7,211.53 25.2 Under 'Contribution to Provident and Other Funds', 23.31% of Pay and DA of employees who joined in service prior to 01-012004 and 10% of Pay and DA of employees who joined in service after 01-01-2004. 26. FINANCE COSTS Particulars Account codes As on 31-03-2014 (Rupees in lakh) Interest Expenses Interest on State Govt. Loan 78.100 1,657.16 Interest on PFC Loan 3,746.36 78.300 Interest on ADB Loan 78.400 0.00 Interest on GPF 78.852 520.08 Less:Interest Capitalised 1,532.04 78.900 4,391.56 Interest Expenses Bank charges 4.71 Total 4,396.27 26.1 Under 'Interest Expenses', an amount of Rs.15,32,04,111/- has been capitalised against NRPP. 26.2 165,716,474 (a) Interest on State Govt. Loan 0 (b) Interest on OD A/c 374,635,766 (c) Interest on PFC Loan 52,008,041 (d) Interest on GPF Assam Power Generation Corporation Limited Page 223 of 228 As on 31-03-2013 (Rupees in lakh) 1,404.75 2,752.95 1.38 475.49 401.40 4,233.17 19.05 4,252.22 27. OTHER EXPENSES Account codes Particulars Manufacturing Expenses Repair and Maintenance of Plant and Machinery Repair and Maintenance of Building Repair and Maintenance of Civil Works Repair and Maintenance of Hydraulic Works Repair and Maintenance of Lines, Cable Net Works etc TOTAL Establishment Expenses Rent Rates and Taxes Insurance Telephone Charges, Postage.Telegram& Tele Charges Tax Audit Fees Legal charges Audit Fee Consultancy charges Technical Fee Other Professional Charges Conveyance and Travel Other administrative expenses (except 76.130) Freight Other Purchase related expenses Other misc. expenses Repair and Maintenance of Vehicles Repair and Maintenance of Furniture and Fixures Repair and Maintenance of Office Equipment Less:-Administration and General Expenses capitalised Total Prior period items As on 31-03-2014 (Rupees in lakh) As on 31-03-2013 (Rupees in lakh) 74.100 74.200 74.300 74.400 74.500 2,060.00 181.23 88.84 86.65 3.36 2,420.08 1,612.44 156.54 55.43 101.84 0.15 1,926.40 76.101-76.102 76.103-76.106 76.107 76.108-76.109 76.130 76.110 76.111 76.112 76.113 76.114 76.115-76.119 76.120-76.190 76.210-76.220 76.230-76.299 76.501 35.22 80.96 11.50 1.15 0.10 1.94 2.09 18.89 1.80 6.66 117.44 968.57 3.28 0.45 3.42 6.03 25.91 7.94 0.00 1,293.35 8,415.19 22.82 125.56 12.67 0.54 0.10 43.63 1.90 4.02 0.77 5.02 69.52 353.08 5.45 0.02 5.40 9.10 22.19 4.72 (11.97) 674.54 (6,502.13) 12,128.62 (3,901.19) 74.600 74.700 74.800 76.900 Net Total (a) Prior period income includes:(i) withdrawl of excess provision of interest on public bond as per C&AG's comment No.A.1 by Rs. 20,78,46,329/(ii) withdrawl of excess provision of bond repayment issued via warrant by Rs. 4,04,29,489/-. (iii) withdrawl of provision made against "Assam Building & other Construction Workers Welfare Cess" in prior period as per C&AG commnent No.A.04 by Rs.1,73,63,728/-. (iv) withdrawl of adjustment Jv. No.21 of FY 2012-13 as per POS-11 of C&AG audit by Rs.1,58,37,047/-. (v) withdrawl of excess provision of ROP arrear for FY 09-10 after adjusting actual payment by Rs.10,46,19,575/-. (vi) withdrawl of ADB loan interest accounted in prior period by Rs.9,53,971/-. (b) Prior period expense includes:(i) LD recovered from BHEL against LWHRP booked as other income now rectified & adjusted with asset as per commnent C&AG No.A.03 by Rs.5,57,11,893/(ii) Revenue surplus of Rs.96.38 crore for 09-10 and Rs.20.51 crore for 10-11 arrived by AERC while truing up adjusted as per commnent C&AG No.C.1 28. EARNING PER SHARE (EPS) Account codes Particulars As on 31-03-2014 (Rupees in lakh) Net profit After Tax As per Statement of Profit & Loss (8,636.33) Number of Equity Shares 45585975 As on 31-03-2013 (Rupees in lakh) (18.95) Earning Per Share Face Value per Equity share 100 29. The balance amount of Preference Share Capital (Paid up) of Rs.31/- which was remained as it is after transferring of Preference Share Capital (Paid up) to Share Capital during 2011-12 has been withdrawal during the year after taking due approval from the Board of APGCL vide Minutes No.7(B) of Board Meeting No.53 dtd.07-02-14. Assam Power Generation Corporation Limited Page 224 of 228 (608.41) 45585975 (1.33) 100 30. Against Revision of Pay Rules, 2O1O, APGCL provided a lump-sum provision of Rs.31.75 crore for the period w.e.f. 01-01-06 to 31-03-09 in its Annual Accounts for FY 2008-09 and Rs.11.49 crore for FY 2009-10 in its Annual Accounts for payment of the arrear to its employees. But the arrear amount was declared to pay from 01-04-09 onwards only vide the said rules. The provision made in the annual accounts for FY 2008-09 of Rs.31.75 crore has already been withdrawn during the last year. The balance of excess provision of ROP arrear of Rs.10.46 crore has been withdrawn during the financial year after adjustment with the actual payment. 31. The 2x1.5 MW, stage-II of Myntriang Small Hydro Electric Project, Myntriang, Karbi Anglong District, was commissioned on 03-03-2014. The value of asset of stage-II is Rs.37.56 crore. Construction work for stage-I (2x3 MW) and capacity enhancement of both the stages are also going on. 32. AERC had issued revenue surplus of Rs.96.38 crore and Rs.20.51 crore for FY 2009-10 and FY 2010-11 while truing up and the same had been adjusted with the tariff order issued to APDCL. It was commented by C&AG while auditing the annual accounts of APGCL for FY 201213 vide comment No.C.1. So, the total amount of Rs.116.89 crore has been provided as prior period loss and has been adjusted with receivable against sale of power during FY 2013-14. 33. The Fixed Asset Register of APGCL was derived from the opening trial balance of APGCL as on 01-04-05 received on bifurcation of erstwhile ASEB. Over the past years since 2005-06, depreciation was calculated on the basis of this Fixed Asset Register. But during FY 2013-14, a massive physical verification of the fixed assets of APGCL was conducted by the technical wing. Thus, a new Fixed Asset Register alongwith physical verification of the assets was derived from the report and depreciation for the year has been calculated on the basis of this Fixed Asset Register. But due to time differences and calculation of depreciation on the detailed fixed assets, there occurred noticeable difference in various asset groups of fixed asset and depreciation. These differences are shown as adjustments as on 01-04-2013 to both assets and depreciations in Note-11 of the Annual Accounts. These adjustments neither affect the total fixed asset nor the total depreciation, but affect individual asset groups. 34. In absence of any specific information available with the Company in respect of any supplier attracting provisions of the Macro, Small and Medium Enterprises Development Act, 2006, no disclosure/ treatment has been considered necessary in this regard. 35. Remuneration to Managing Director: During Financial Year 2013-14, an amount of 11,37,233/- was paid as remuneration to the Managing Director. 36. Value of imports calculated on C.I.F. basis: Value of imports calculated on C.I.F. basis incurred during the year 2013-14 on import of Capital goods is 8,18,00,530/-. 37. Expenditure in foreign currency (on cash basis): The Expenditure in foreign currency (on cash basis) incurred during the year 2013-14 on import of capital goods is 8,18,00,530/-. 38. Number of employees who are in receipt of emoluments aggregating to 24,00,000/- per annum or 2,00,000/- per month as per Companies (Particulars of Employees) Rules, 1975 is nil. 39. An amount of 3,00,00,000/- was sanctioned as overdraft by pledging fixed deposit of 3,00,00,000/- with State Bank of India, New Guwahati Branch. 40. The Company prepares Bank Reconciliation Statement regularly. 41. Details of remuneration to Auditors: Particulars Amount ( ) Statutory Audit Fee Cost Audit Fee For Tax Audit Total 1,50,000.00 40,000.00 10,000.00 2,00,000.00 Assam Power Generation Corporation Limited Page 225 of 228 ASSAM POWER GENERATION CORPORATION LIMITED ANNEXURE - A OPERATIONAL PERFORMANCE Sl. No. Particulars Previous Year 2012-13 This Year 2013-14 (1) (2) (3) (4) 1 Installed Capacity (MW) (a) Thermal 60 60 102 105 (c) Gas 276.7 276.7 Total 438.7 441.7 --- --- 344.017 422.510 (c) Gas 1421.247 1422.718 Total 1765.264 1845.228 133.661 112.381 (b) Hydel 2 Power Generated (MU) (a) Thermal (b) Hydel 3 Less: Auxiliary Consumption (MU) 6 Total power available for sale (MU) 1631.603 1732.847 7 Power sold (MU) 1631.603 1732.847 8 Units generated per MW of installed capacity (in Lakh unit) 40.2 42.1 9 Plant Load Factor (%) 0% 0% (b) Hydel 38.50% 47.29% (c) Gas 58.63% 58.70% Percentage of generation to installed capacity 53.49% 55.92% (a) Thermal 10 Assam Power Generation Corporation Limited Page 226 of 228 ASSAM POWER GENERATION CORPORATION LIMITED ANNEXURE - B OPERATIONAL PERFORMANCE Sl. No. Particulars (1) (2) 1 Previous Year This Year 2012-13 2013-14 (3) (4) Installed Generation capacity (in MW) at the year end. (a) Thermal 60 60 102 105 (c) Gas 276.7 276.7 Total 438.7 441.7 53.49% 55.92% (b) Hydel 2 Plant Load Factor (%) 3 Power Generated (MU) (a) Thermal (b) Hydel --- --- 344.017 422.510 (c) Gas 1421.247 1422.718 Total 1765.264 1845.228 133.661 112.381 523.50 521.89 8442 8509 0.3683 0.3668 4 Auxiliary Consumption (MU) 5 Fuel a) Gas Consumption (MMSCM) b) Average calorific value of Gas (Kcal/SCM) c) Gas Consumption per unit of generation (in SCM/Kwh) Assam Power Generation Corporation Limited Page 227 of 228 ASSAM POWER GENERATION CORPORATION LIMITED Statutory information pursuant to Part IV of Schedule VI to the Companies Act, 1956 ANNEXURE-C BALANCE SHEET ABSTRACT AND COMPANY'S GENERAL BUSINESS PROFILE I. Registration Details Registration No. Balance Sheet Date II. State Code No.: 02 Capital raised during the year (Amount in Rs. Lakh) Public Issue: Bonus Issue: III. 02-07239 31-03-2014 NIL NIL Rights Issue Private Placement: NIL NIL Position of Mobilisation and Deployment of Funds (Amount in Rs. Lakh) Total Liabilities: 38,691 Total Assets: 38,691 Source of Funds: Paid up Capital: Share Deposit Secured Loans: 45,586 0 33,351 Reserves & Surplus: 20,737 Unsecured Loans: 20,037 69,936 35,941 17,301 Investments: Misc. Expenditure: Capital work in progress: 0 0 56,898 Total Expenditure: Profit/ Loss (-) after Tax: Dividend rate % 0 (8,636) NIL Application of Funds: Net Fixed Assets: Net Current Assets: Accumulated Losses: IV. Performance of Company (Amount in Rs.Lakh) Turnover: Profit/ Loss (-) before Tax: Earning per share in Rs.: V. 57,660 (8,591) (18.95) Generic Names of Three Principal Products/Services of Company (as per monetary terms) Item Code No. NIL Product description Generation of Electricity Assam Power Generation Corporation Limited Page 228 of 228 KDDEd^K&'KEd,EEh>KhEd^ K&ϮϬϭϯͲϭϰK&W'>